DETAILED ENGINEERING OF THE FOLLOWING SECTIONS 1. We have placed the order for the following core equipment Ball Mill, Hydro cyclone, Scalping Screen & Cyclone feed Pumps (2nos.) to TH Minerals. Flotation Cells Rougher (6 nos.), Cleaner – 1 (5 nos.), Cleaner – 2 (5 nos.) and Cleaner – 3 (3 nos.) to Delkor. Thickeners each for Concentrate & Tailing to Delkor. Horizontal Belt Vacuum Filter press each for Concentrate & Tailing to Delkor. NOTED. 2. Plant complete detailed integration engineering including utilities like piping engineering with complete BOM / MTO for the piping work. NOTED. Piping detailed engineering can be undertaken with following activities/services/deliverables: a. Piping General Arrangement Drawings, comprising of Plans, Sections & Elevations b. Pipe Support Arrangement Drawings c. Pipe Stress Analysis (as required) d. Piping Isometrics (as required) e. MTO for Pipes, Fittings, Valves 3. The preparation of the G.A. drawings of the building after incorporating the above core equipment which are good for civil design. It is presumed that Item No. 3 refers to Mechanical GA Drawing(s)/Equipment Location Plan(s) which shall be used as Assignment Drawing(s) for Civil design. Please confirm. 4. Review the documents received from the suppliers like PFD, P&ID & Mass and Water Balance. It is presumed that above deliverables shall be available from Process Licensor/Technology Provider/OEM and ‘review’ of the same is restricted within checking the completeness of information furnished in above deliverables for carrying out detailed engineering for piping. 5. Review the plant review w.r.t to the completeness of the plant. 6. Complete assistance for the finalization of the pending ordering of the equipment. Not clear. Requesting to clarify the equipment on which you need this support from detailed engineering consultant. 7. Preparation of the overall control philosophy of the plant. Overall control philosophy of the plant is to be obtained from Process Licensor/Technology Provider. 8. Review & preparation of the equipment cum load list and ensure completeness of the same. Equipment cum load list are Licensor/Technology Provider. 9. to be obtained from Process Review and preparation of the scheme for utilities such as compressed air distribution, water distribution & Firefighting etc. NOTED. Can be undertaken; however please confirm whether it would be restricted within compressed air distribution, water distribution & Firefighting, or anything else also. 10. Preparation of the detailed fabrication drawings of all the site fabricated items such as sumps, tanks, chutes, ducts, pipes, bins & hoppers etc. NOTED. Can be undertaken; however the general arrangement drawings showing all nozzles, details of supports (skirt/leg/lug), design & locations of lifting lugs & stiffeners are to be provided by Process Licensor/Technology Provider/OEM/Equipment Supplier. 11. Review of the mass pulls considered and slurry & froth pump sizing calculation. It is excluded from the scope of detailed engineering consultant. 12. Concurrence of the civil & electrical drawings w.r.t to the Mechanical G.A Drawings. It shall be restricted within the interdisciplinary review of civil & electrical drawings w.r.t to the Mechanical G.A Drawings, and not the engineering review. INFORMATION REQUIRED FOR SUBMISSION OF TECHNO-COMMERCIAL OFFER 1. Overall Plant Layout/Plot Plan 2. PFD & P&IDs from Process Licensor/Technology Provider 3. Design Basis Report, if available. INFORMATION REQUIRED FOR CARRYING OUT DETAILED ENGINEERING FOR THE ITEMS COMMENTED IN RED 1. Overall Plant Layout/Plot Plan, with all necessary coordinates. 2. PFD & P&IDs from Process Licensor/Technology Provider. 3. Design Basis Report, if any. 4. Piping Materials Specification (PMS), if available. 5. Valve Materials Specification (VMS), if available. 6. Pipe Support Design Standard of Customer, if available. 7. General Arrangement Drawings and Data Sheets from Vendor(s) for all equipment. 8. Mechanical GA Drawings for all Rooms/Buildings.