DNVGL-RP-F115 Edition September 2019 Pre-commissioning of submarine pipelines The electronic PDF version of this document, available at the DNV GL website dnvgl.com, is the official, binding version. DNV GL AS This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used RECOMMENDED PRACTICE DNV GL recommended practices contain sound engineering practice and guidance. © DNV GL AS September 2019 Any comments may be sent by e-mail to rules@dnvgl.com This service document has been prepared based on available knowledge, technology and/or information at the time of issuance of this document. The use of this document by others than DNV GL is at the user's sole risk. DNV GL does not accept any liability or responsibility for loss or damages resulting from any use of this document. This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used FOREWORD This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Changes - current CHANGES – CURRENT This document is a republished version of the October 2018 amendment of the first edition of DNVGLRP-F115 (September 2016). No changes have been made to the content of this document. Amendments October 2018 References to legacy DNV documents have been updated to reflect the new DNV GL portfolio. Editorial corrections In addition to the above stated changes, editorial corrections may have been made. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 3 The partners of the JIP were: — — — — — — — Dong Energy Baker Hughes Halliburton Pipeline & Process Services Technip Subsea 7 Nord Stream AG Statoil — — — — — — INPEX Saipem ConocoPhillips IKM Testing Atlas Copco Wood Group Subsea Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 4 Changes - current This recommended practice is one of a series resulting from a joint industry project (JIP) led by DNV GL to reduce cost and increase predictability without compromising quality and safety in international offshore development projects by recommending standardized parameter for selected items. This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Acknowledgements Acknowledgements................................................................................. 4 Section 1 Introduction............................................................................................ 7 1.1 General............................................................................................. 7 1.2 Objective...........................................................................................7 1.3 Scope and application.......................................................................7 1.4 Limitations........................................................................................ 7 1.5 Structure of this recommended practice...........................................8 1.6 Referenced standards....................................................................... 8 1.7 Definitions.........................................................................................9 1.8 Units............................................................................................... 13 Section 2 Pre-commissioning philosophy.............................................................. 14 2.1 General........................................................................................... 14 2.2 Pipeline system design................................................................... 14 2.3 Flooding, cleaning and gauging...................................................... 15 2.4 Pressure testing..............................................................................15 2.5 Dewatering and drying................................................................... 15 Section 3 Flooding, cleaning and gauging.............................................................17 3.1 Flooding.......................................................................................... 17 3.2 Cleaning.......................................................................................... 19 3.3 Gauging...........................................................................................21 Section 4 System pressure test............................................................................ 24 4.1 Objectives....................................................................................... 24 4.2 Pressure test operation.................................................................. 25 4.3 Acceptance criteria......................................................................... 29 Section 5 Dewatering, drying, inerting and product filling....................................31 5.1 Dewatering..................................................................................... 31 5.2 Drying............................................................................................. 34 5.3 Inerting...........................................................................................38 Section 6 Miscellaneous issues............................................................................ 40 6.1 Operational principles..................................................................... 40 6.2 Documentation................................................................................41 Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 5 Contents Changes – current.................................................................................................. 3 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used CONTENTS 6.5 Temporary pre-commissioning equipment...................................... 46 6.6 Pre-commissioning fluid................................................................. 48 6.7 Corrosion assessment and water treatment................................... 49 6.8 Other considerations/special systems............................................ 52 Section 7 References.............................................................................................54 7.1 References...................................................................................... 54 Appendix A Checklist for flooding, cleaning and gauging......................................55 A.1 Checklist for flooding, cleaning and gauging.................................. 55 Appendix B Checklist for system pressure testing................................................ 57 B.1 Checklist for system pressure testing........................................... 57 Appendix C Checklist for system test pressure calculation................................... 60 C.1 Checklist for system test pressure calculation................................ 60 Appendix D Checklist for dewatering, drying and inerting.................................... 65 D.1 Checklist for dewatering, drying and inerting.................................65 Changes – historic................................................................................................ 67 Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 6 Contents 6.4 Pig traps (launchers and receivers) and test heads........................ 46 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used 6.3 Pigs and pig trains......................................................................... 43 1.1 General The pre-commissioning phase is an important and essential part of any pipeline project, normally consisting of the following activities: Figure 1-1 Pre-commissioning operations Note that some pipelines do not require drying/inerting (e.g. water injection, production and MEG lines). Most pipeline codes have some requirements to gauging and pressure testing. However, this is the first recommended practice covering pre-commissioning operations specifically as a whole, e.g. taking into consideration overall design, system arrangements, management and planning, functional requirements and execution principles for pre-commissioning operations of a pipeline system. 1.2 Objective The objective of this document is to provide guidance on safe, reliable and effective planning, design and execution of pre-commissioning activities for submarine pipeline systems. 1.3 Scope and application This recommended practice is intended to be used as supplement to DNVGL-ST-F101, i.e. submarine pipeline systems. The philosophy in this report applies to new pipeline systems as well as existing pipeline systems e.g. subject to repairs. 1.4 Limitations The following general limitations apply: — Flexible pipe systems are not covered by this recommended practice; however flexible pipe section, e.g. flexible tails, or flexible risers, may be pre-commissioned along with the rest of the pipeline system according to this recommended practice. The following operations – and the sequence of these – are commonly defined as commissioning operations and not further considered in this recommended practice: — Product filling; introduction of product into the pipeline. Pending degree of pre-commissioning operation, product filling may involve use of pigs as barriers for separation. — Decommissioning; temporarily or permanently taking an operating line out of service. Pending system status and purpose of decommissioning, this will normally include use of pigs for removal of the product from the pipeline system. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 7 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used SECTION 1 INTRODUCTION Sometimes the dewatering pig train may be driven by the product and then dewatering will be part of the commissioning. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- 1.5 Structure of this recommended practice This recommended practice is structured to constitute the basis for a pre-commissioning manual (project specific). The following operations – and the sequence of these - are commonly defined as standard for precommissioning: 1) 2) 3) 4) 5) 6) Flooding; flooding the pipeline with the pre-commissioning fluid, normally by use of separation pig(s) in order to remove air and/or in combination with cleaning. See [3.1]. Cleaning; removal of internal debris from the pipeline following installation. Normally performed by running one or several pigs through the pipeline. See [3.2]. Gauging; verification of the pipeline’s cross section profile. Normally performed by running one or more pigs with a metallic plate of specified size through the length of the pipeline. Alternative to gauging plates are instrumented gauging tools/calliper pigs. See [3.3]. System pressure testing; verify that the pipeline system is free from gross errors and leakages. Normally performed with water or other incompressible media. See Sec.4. Dewatering; removal of the pre-commissioning fluid. Normally performed by running one or more pigs as separation/barrier between various media. See [5.1]. Drying and inerting; removal of residual pre-commissioning fluid and lowering the dew point to acceptable level. Normally most relevant for gas/condensate systems and normally involves nitrogen/dry air purging or vacuum drying, alternatively MEG swabbing can be considered. See [5.2] and [5.3]. Guidance note: Note that the above operations may be performed in a different order or in combination, and that one or more operations could be omitted. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- 1.6 Referenced standards 1.6.1 Relationship to other standards The following standards include requirements which, through reference in the text constitute requirements of this document. References are either defined as normative or informative. Normative references in this document are indispensable for its application. Informative references provide additional information intended to assist the understanding or use of the document. Guidance note: Normative references are typically referred to as ‘testing shall be performed in accordance with ISO xxx’, while informative references are typically referred to as ‘testing may be performed in accordance with ISO xxx or ISO yyyy’, or ‘recommended practice for testing is given in DNVGL-RP-F xxx’. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- In case of conflict between requirements of this document and a referenced DNV GL service documents, the requirements of the document with the latest revision date shall prevail. Any conflict is intended to be removed in next revision of that document. Where reference is made to standards other than DNV GL service documents, the valid revision should be taken as the revision which was current at the date of issue of this standard. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 8 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Guidance note: This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used 1.6.2 DNV GL standards The latest revision of the following document applies. Document code Title DNVGL-ST-F101 Submarine pipeline systems 1.6.3 DNV GL recommended practices The latest revision of the following documents applies: Document code Title DNVGL-RP-A203 Technology qualification DNVGL-RP-F109 On-bottom stability design of submarine pipelines DNVGL-RP-F113 Pipeline subsea repair DNVGL-RP-N101 Risk management in marine and subsea operations 1.6.4 Other standards Document code Title API 5L Specification for Line Pipe API 17B Recommended Practice for Flexible Pipe ASME B31.4 Pipeline Transportation Systems for Liquid Hydrocarbons and Other Liquids ASME B31.8 Gas Transmission & Distribution Piping System ISO 13623 International Standard, Petroleum and natural gas industries – Pipeline transportation systems ISO 8573 Compressed air - Part 1: Contaminants and purity classes ISO 9001 Quality management systems – Requirements 1.7 Definitions 1.7.1 Definitions Table 1-1 Definition of terms Term Description acceptance criteria specified indicators or measures providing an acceptable level and that are used in assessing the ability of a component, structure or system to perform its intended function battery limit the interface between the pipeline or pipeline system and adjacent facilities not defined as parts of the pipeline or pipeline system Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 9 Description components bends, fittings, flanges, valves, mechanical connectors, isolation joints, anchor flange, buckle arrestor, pig traps, clamps, couplings etc. debris the undesirable particles and objects present in the pipeline such as rust, loosely adhered mill scale, weld splatter, construction objects, sand, rubble, litter etc. free flooding flooding operation performed without the use of pumps, regardless of the use of pig or not golden welds critical welds e.g. tie-in welds that will not be subject to pressure testing, where 100% ultrasonic testing, 100% radiographic testing, and 100% magnetic particle testing or 100% liquid penetrant testing of non- ferromagnetic materials shall be performed, see DNVGL-STF101 Sec.10 for more details gross error a gross error is referred to as a significant error or damage present in the system that normally should have been discovered by quality control activities prior to or during pipeline installation Damages caused during ploughing, other trenching methods or third party damages e.g. anchor, anchor chains or wires are all to be considered as gross errors. HISC issues and other defects (e.g. creep mechanisms causing failure after a number of hours) are also referred to as gross errors. hold period the time the pressure is kept within the system after stabilisation is confirmed incidental pressure the maximum internal pressure the pipeline or pipeline section is designed to withstand during any incidental operating situation (including dynamic effects) leak test test to detect leakages in the pipeline system or local connections mill pressure test the hydrostatic strength test of each joint performed at the mill pipeline system pipeline with compressor or pump stations, pressure control stations, flow control stations, metering, tankage, supervisory control and data acquisition system (SCADA), safety systems, pig launchers and receivers (if relevant), corrosion protection systems, and any other equipment, facility or building used in transportation of fluids product fluid transported in pipeline safety class a concept adopted to classify the significance of the pipeline system with respect to consequence of failure, see DNVGL-ST-F101 Sec.2 stabilisation period from the time the test pressure has been reached and until the commencement of the hold period strength test the strength test shall reflect the highest utilisation the part will be exposed to during its entire life For linepipe see definition of m pressure test. system pressure test final test of the complete submarine pipeline system to reveal gross errors or leaks submarine pipeline system please see definition in DNVGL-ST-F101 Sec.1 treated water shall be understood as water which has been treated with additives Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 10 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Term This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used 1.7.2 Abbreviations Table 1-2 Definition of abbreviations Term Definition CRA corrosion resistant alloy FCG flooding, cleaning, and gauging FEED front end engineering design HAZOP hazard and operability study HISC hydrogen induced stress cracking HSE health, safety and environment ID pipeline inner diameter ILT in-line tee MEG methyl ethylene glycol MIC microbiologically influenced corrosion PLEM pipe line end manifold PPE personal protection equipment QHSE quality, health, safety and environment RP recommended practice SCADA supervisory control and data acquisition system SJA safe job analysis SMYS specified minimum yield stress SRB sulphate reducing bacteria UV ultra violet Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 11 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used 1.7.3 Symbols Table 1-3 Definition of symbols Symbol SI-Unit Definition [1/K] coefficient of volumetric thermal expansion of pipe wall material - pressure test ratio, see DNVGL-ST-F101 Table 5-8 (typically 1.05) [1/K] coefficient of volumetric thermal expansion factor of test medium [J/kgK] heat capacity of test medium [-] discharge coefficient [m] inner diameter of pipe [m] outer diameter of pipe [Pa] Young’s Modulus 2 [m/s ] gravity constant = 9.81 [Pa] bulk modulus of test medium [m] pipeline length [kg] mass of test medium at end of test hold period, at ( [kg] mass of test medium at start of test hold period, at ( [kg/kmol] air molecular weight (= 28.97) [-] Poisson ratio = 0.3 [-] incidental to design pressure ratio [Pa] pressure outside pipe [Pa] internal design pressure [Pa] incidental pressure [Pa] local incidental pressure [Pa] local test pressure [Pa] required local test pressure [Pa] governing system test pressure (considering actual test medium density) [Pa] differential pressure Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS ) ) Page 12 SI-Unit 3 Definition [m /s] volume rate [J/kmole-K] universal gas constant = 8314.5 J/kmole-K 3 [kg/m ] density of test medium [s] time [s] test hold period [°C] temperature [°C] temperature variation 2 [W/m °C] total heat transfer coefficient for steel wall, insulation, coating and surroundings 3 actual pipe volume at pressure [m ] 3 pipe volume with zero overpressure [m] water depth [m] pipe wall thickness [-] volume fraction of air before pressurizing [-] volume fraction of air at start of test hold period [-] compressibility of gas [m ] This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Symbol and temperature 1.7.4 Verbal forms Table 1-4 Definition of verbal forms Term Definition shall verbal form used to indicate requirements strictly to be followed in order to conform to the document should verbal form used to indicate that among several possibilities one is recommended as particularly suitable, without mentioning or excluding others, or that a certain course of action is preferred but not necessarily required may verbal form used to indicate a course of action permissible within the limits of the document 1.8 Units SI units are recommended. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 13 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used SECTION 2 PRE-COMMISSIONING PHILOSOPHY 2.1 General The pre-commissioning philosophy shall be established considering as a minimum the following: — pipeline system configuration — pipeline characteristics: — product — diameter, features and length — seabed topography — pre-commissioning system design: — overall pre-commissioning installation/pre-commissioning sequence — pre-commissioning battery limits — component spread requirements: — compressors and pumps — pigs and pig trains — pig launchers and receivers — pre-commissioning fluids — space requirements — vessel requirements — access to pipeline ends or on intermediate structures (ILTs, PLEMs ....) — outline procedures including: — — — — flooding, cleaning, and gauging - method and acceptance criteria system pressure testing - method and acceptance criteria dewatering, drying and inerting - method and acceptance criteria contingency plan — special system evaluations: — — — — — — — pre-commissioning fluid, chemical treatment and filtration filling direction, water disposal codes break (onshore/offshore) multi-diameter pipeline, connect to live pipeline material considerations (seawater, exposure limitations) winterisation/freeze protection subsea connectors flooding caps, pressure caps and their associated tooling — quality and HSE considerations — planning, schedule and engineering considerations — documentation requirements. 2.2 Pipeline system design The pipeline system design should address pre-commissioning and commissioning operations. These issues should be considered at the earliest stage during FEED phase. System design should allow for access and connection of relevant equipment for performing necessary precommissioning and commissioning work. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 14 — provision and location of permanent/temporary pig traps, where applicable — venting, isolation and draining arrangements relative to pig launch/receipt, where applicable, pressure testing and future tie-in — pre-commissioning fluid injection (such as dead leg flushing) — possibility for proper removal of air during filling with pre-commissioning fluid — pigging direction(s), where applicable — piggable item list covering, where applicable: — minimum allowable bend radius — minimum distance between bends, Tees, Wyes and other components — maximum allowable internal diameter change with tapering requirements when/if change in inner diameter is required — internal coating evaluations in relation to effects on dewatering/drying and types of allowed/ recommended pigs to be used (gas lines) — subsea connection and flushing/purging of relevant piping/volumes (operational pigging) — fluid diversion in case of subsea pig launcher/receiver used during operational life (kicker and bypass lines) — system component specific design requirement, such as subsea connectors cladding or ID matching the pipe ID, full bore valves and valve seats capable of withstanding the differential pressure generated by the water column and test pressure, valves seats capable of withstanding void in case vacuum drying is foreseen, etc. 2.3 Flooding, cleaning and gauging A philosophy for flooding, cleaning and gauging shall be established considering pre-commissioning fluid source location and quality, need for filtering and additives, the direction of flooding, free flooding or using pump spread or a combination, see checklist in App.A. Vessel requirements for flooding, pig tracking, pig retrieval shall be established, in case of vessel operations. Special cleaning requirements through all phases of the project, e.g. internal sand blasting, use of end protectors, handling procedures, and inspection need to be established. Gauging technique for multi diameter pipeline systems shall be decided. Confirmation of acceptance criteria shall be ensured. Contingency possibilities shall be evaluated. 2.4 Pressure testing A philosophy for pressure testing shall be established considering individual component testing, hold periods, codes and code breaks, test sections and golden welds. Vessel requirements for pressure testing and leak detection shall be established, in case of offshore operations. Contingency possibilities shall be evaluated. See checklists in App.B and App.C. 2.5 Dewatering and drying A dewatering and drying philosophy shall be established considering all relevant parameters, see checklist in App.D. Requirements to inerting and preservation shall be established. Figure 2-1 illustrates the decision making process of dewatering and drying operations in general. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 15 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used The design should as a minimum include for: This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Figure 2-1 Dewatering and drying flowchart Pre-commissioning of submarine pipelines DNV GL AS Page 16 Recommended practice — DNVGL-RP-F115. Edition September 2019 3.1 Flooding 3.1.1 Objectives The objective of flooding is to prepare for cleaning, gauging, tie-in and pressure testing of the pipeline system. The flooding, cleaning and gauging operations may be combined. Guidance note: Flooding may also be required in order to stabilise the pipeline on the seabed and increase the submerged weight prior to trenching. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- 3.1.2 Flooding operation 3.1.2.1 Flooding technique selection Flooding may be performed either by pumping or free flooding. The use of pig(s) as an interface between the pre-commissioning fluid and empty pipeline is the preferred method for flooding, see [3.1.2.4]. This interface, when propelled in a steady and controlled manner will minimise residual air and assist with removal of any construction debris present. 3.1.2.2 Fluids Requirements and recommendations to quality of pre-commissioning fluids are given in [6.6] and [6.7]. Pre-commissioning fluid should be sampled and analysed, in due time before the operation, to verify if additives are required and/or to determine the appropriate additive treatment strength. Samples of the pre-commissioning fluid should be taken during flooding operation, where practicable, to document actual properties. When pre-commissioning operations are performed from environmentally sensitive area, specific considerations should be taken to minimize as much as possible the impact of such fluids in case of pipeline failure. 3.1.2.3 Flooding direction Flooding direction should preferably be from the deep end towards the shallow end of the pipeline to minimize residual air content and to limit the risk of excessive pig speed. If this is not possible – given system or operational constraints - due considerations should be made with respect to any need to ‘back-pressure’ the pipeline with compressed air or by partially or completely preflooding the line before the pig run (as a measure for pig speed control). In addition, the direction may be dictated by other aspects associated with the pipeline design, e.g. wyes, non-return valves. Special care should be taken in case of pressurised air systems. Allowable pressures should be kept significantly below the systems design pressure. 3.1.2.4 Flooding with pigs Use of separation pig(s) as interface between the pre-commissioning fluid and empty pipeline is the preferred method for flooding a pipeline. This is in order to: — Create a defined interface between the filling fluid and air within the pipeline. — Ensure that any air bypassing the initial filling pig is captured in the slugs of fluid between the following pigs in the pig train. — Remove debris from the pipeline and to keep loose debris in suspension so that it can be discharged from the receiving end of the line (pig receiver). See [3.2]. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 17 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used SECTION 3 FLOODING, CLEANING AND GAUGING — pig launchers and receivers must be designed to accommodate the required number of pigs including expected debris and accommodate the required flow rates of the operation — pig design — pig speed and pig separation control, see [6.3.3] and [6.3.2] — suitably sized filling equipment — volume of fluid supply reservoir — need for pre-flooding. Adequate sized filters/strainers shall be used to limit the ingress of debris, see [6.6]. 3.1.2.5 Free flooding A 'free flooding' operation is performed without the use of pumps. The differential pressure between pipeline internal and external pressure at seabed is the driving force. This flooding is done with or without use of pigs. Free flooding operations are normally followed by further flooding operations by use of pumps (at either topside or subsea) and pigs to remove residual air, cleaning and gauging. Guidance note: If the pipeline requires to be re-pigged after free flooding, the accumulative effects of entrapped air at local high points should be taken into account when selecting the pumping equipment and effect on pigs. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- Considerations should be given to sizing inlet piping to limit water velocity. Adequately sized filters/strainers should be used to limit the ingress of particles and organic material. Free flooding generates a risk of ingress of unknown quantity of solids such as sand and organic materials into the pipeline. To minimise the above risk, water supply should be taken at a suitable distance above the seabed. If the free-flooded fluid does not contain any chemical treatment, consideration to exposure time to untreated water and entrained debris should be given. Guidance note: In some cases, a pig may be launched during free flooding operations to ensure the interface between the fill water and the empty pipeline is maintained. This is usually carried out when the topography of the pipeline is ‘undulating’. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- 3.1.3 Special considerations For pipelines located in areas with extreme topography or riser sections, excessive pig speeds resulting from steep inclination of various sections may be expected. Gradients greater than 1:10 in conjunction with elevation changes in the order of tens of metres will generally result in unstable pig speeds. The detailed flooding flow behaviour of the pipeline should be analysed to determine if the pig speed instability is detrimental to the pigging operation, otherwise the following methods may be considered: — — — — — pumping water in front of the pig train free flooding air packing the pipeline to an appropriate pressure prior to pigging fill against a controlled discharge to allow pressure to build up in front of the leading pig use of high friction pigs. In smaller diameter (<0.152 m (6")) pipelines, it is advisable that filling is carried out without the use of pigs, although solid cast or foam pigs may be evaluated if a barrier in front of the filling fluid is required. See [3.1.2] and [6.3.2]. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 18 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used The following should be considered: For requirements to the pre-commissioning fluid, see [6.6]. For requirements for additives, see [6.7]. For temporary equipment, see [6.5]. 3.1.5 Acceptance criteria Flooding is considered acceptable when: — pipeline filled with pre-commissioning fluid in accordance with the requirements and successful arrival of all pigs — successful air inclusions check (to be performed during system pressure test). 3.2 Cleaning 3.2.1 Objective Cleaning as part of pre-commissioning operations is usually conducted in order to ensure that debris is removed together with any foreign objects which may have been deposited into the pipeline during construction activities. The objective of cleaning operation will be to: — Ensure the product in the pipeline is not contaminated. — Allow effective use of product corrosion inhibitors during operations, hence if the internal pipe surface is corroded these product inhibitors cannot come into contact with the surface they are intended to protect. — Ensure flow-efficiency. This particularly applies to longer pipelines where flow-effects due to debris and internal roughness are of larger importance. — Prevent damage to permanent equipment, e.g. valves. 3.2.2 Cleaning operation 3.2.2.1 Cleaning technique selection Pipeline cleaning may be performed by the following methods or in combination: — — — — pigging high velocity water flushing high velocity air flushing gel cleaning. 3.2.2.2 Pigging On larger diameter (≥0.152 m (6")) pipelines the most common and preferred cleaning technique during pre-commissioning operations is to use bi-directional pigs, with or without brushes. In most cases these pigs also have magnets attached to pick up material i.e. welding wire, bolts, nuts, pig brush bristles, etc. The more pigs that are passed through a pipeline, the better the cleaning effect will be. Metal brush pigs shall generally not be used in CRA pipelines in order to avoid iron inclusions that will lead to unsightly staining or initiate pitting corrosion. Brushes and pigs should be made from a suitably compatible chrome nickel alloy or from non-metallic materials. In many cases aggressive mechanical brush cleaning of CRA’s is not advised as this will disrupt the 'passive' layer on the material. As this material is particularly susceptible to contamination by carbon steel the use of magnetic pigs for removal of ferrous materials is advised. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 19 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used 3.1.4 Technical requirements In internally coated pipelines, brushes (metallic) shall not be used. However, nylon brushes may be proposed if verified to be suitable for the type of internal coating. If a pipeline is expected to have much debris, bypass ports may be included in the pigs. 3.2.2.3 High velocity water flushing In smaller diameter pipelines (<0.152 m (6")) where pigs are not used, or found unfeasible, cleaning may be carried out by ‘high velocity’ water flushing. Selection of required flushing rate (velocity) should consider: — — — — — — pipeline diameter pipeline length pipeline internal roughness pipeline design/operation pressure viscosity of flushing medium (to verify level of turbulent flow) available flushing spread capacity (flow/pressure). There is no common industry accepted velocity range for ‘high velocity’ flushing, however, a minimum velocity of 1 m/s is commonly used. Pressure/flow plots should be generated from the operation for subsequent correlation and comparison with calculated pressure/flow profile. Debris flushed from the pipeline should be collected and analysed to confirm effectiveness of the cleaning, where feasible and if required. 3.2.2.4 High velocity air flushing High velocity air flushing is generally limited to short, smaller diameter pipelines. 'Oil free' compressed air is run through the pipeline and debris blown out at one end into a ‘knock out’ drum. There is a safety issue with this type of cleaning due to the high energy expansion of the air used. Effectiveness of air flushing to transport debris/particles increases with increasing pressure (air density) and velocity. Due to the lower air density compared to water, a higher flushing velocity is normally required compared to water flushing. Minimum air flushing velocity required transporting debris/particles of a certain size and characteristics in a horizontal pipe section may be estimated based on available transport models. An upper limit on air flushing velocity should be specified considering risk of erosion and damage to system due to direct debris impact. 3.2.2.5 Gel cleaning Gel cleaning may be used where a significant amount of debris is expected and there is a high risk that a brush/cleaning pig may get stuck due to build-up of debris in front of the pig. Gel enhances the efficiency of the pigs as they: — seal the pig — prevent build-up of debris in front of the pig by keeping the debris in suspension — further lubricates the pig which reduces wear. A trailing pig (foam/sealing pig) behind the gel would normally be recommended in order to have a defined interface to pump against during gel cleaning operations. Guidance note: A ‘pick-up’ gel is used to keep debris in suspension and away from the pigs. A ‘sealing gel’ at either end of the gel pig train protects the ‘pick-up’ gel from the propelling medium which may be liquid, product, air or nitrogen. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 20 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Metal brush pigs may be used in flexible pipelines with internal metal carcass provided they are compatible with the carcass material. Metallic brushes shall not be used in flexible pipe sections without an internal metal carcass. If it is required to run pigs through permanent mainline valves, consideration to valve protection/pre-cleaning before pigging shall be given. Debris from the pipeline may block or contaminate small bore pipe work and instrument branches. Consideration shall be given to blanking or removing these branches/items. Design of the pig receiver and discharge pipe work should consider preventing blockage by providing adequate space in front of the pigs for any debris pushed by the pigs. If using gel as a part of the pre-commissioning gel intruding into small bore piping and/or gel not sufficiently removed and being transported into the process systems may cause problems and needs to be considered. 3.2.4 Acceptance criteria The standard acceptance criteria is to reduce the ‘debris’ in a pipeline to a level that will not affect pipeline performance, receiving facilities and its components during operation. The acceptance criteria shall be defined or agreed by the operator. The preferred method for determining pipeline cleanliness shall be evaluated and selected for the individual pipeline system. This could be based on the following: — Weight of debris in front of last pig and between intermediate pigs (trend of recovered debris). — Disk condition for the recovered pigs. — Analysis of water discharged from the pipeline in front of, between pigs, and after the pig train. Note that the first and last of these options may not be feasible for subsea pipeline with both ends subsea. 3.3 Gauging 3.3.1 Purpose The purpose of gauging is to confirm that the bore is of an acceptable minimum diameter, suitable for transportation of the product and the future running of pigs. Gauging shall also be performed to indicate that no larger damage/dents or excessive ovalisation/local buckling has been introduced during installation of the pipeline. Gauging should be undertaken upon completion of pipeline system installation and of all operations likely to induce impact on the pipeline, e.g. trenching, backfilling, pipeline lifting and lowering etc. 3.3.2 Gauging operation 3.3.2.1 Pigging with gauge plate Gauge plates only provide information on the maximum deviation in pipeline cross section. If the gauge plate is damaged during its run through the pipeline it normally gives no indication of the following: — Location damage occurred. — Number of damaged areas. — Type of obstruction that caused the damage, i.e. pipe dent, debris, bends or valves (gauge plate on several pigs may aid in deciding if the damages are due to debris). Gauge plates are only suitable for gauging the minimum diameter in multi-internal diameter pipelines. In such case a calliper pig will be required. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 21 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used 3.2.3 Special considerations 3.3.2.3 Calliper pig These can be mechanical lever callipers, or high standoff electronic measuring devices. Depending upon design they will give minimum and maximum ID based on points on the clock face around the pipe. The more advanced electronic devices, in conjunction with an odometer will give a bore map of the entire pipe. Some electronic gauging pigs are bi-directional. Specific care shall be taken in the design of the electronic housing and sleeping mode should be recommended to save the battery life. Guidance note: Calliper pigs are sometimes used during pre-commissioning, in addition to regular gauging, to perform a baseline survey of the complete pipeline system to be used as reference for later inspection runs. Later inspections should then use equivalent pig configuration. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- Bi-directional calliper pig should be run if: — Damaged gauge plates require further investigation. — The pipeline system has variations in nominal ID and it is required to prove the ID of the larger ID sections. — It is required to prove that the pipeline system is free of damages, dents or buckles beyond what can be detected by the selected gauge plate size. — It is required to document that no excessive ovalisation has taken place. 3.3.3 Technical requirements 3.3.3.1 Gauge plate material and fabrication The following should be used as basis for the design and fabrication of gauge plates: — — — — — Aluminium construction, between 3 mm and 10 mm thick. Chamfered 45° x half plate thickness on leading edge. Slotted, with 8-12 slots (depending on pig size). Gauge plate size should comply with the requirements given in [3.3.5]. Size (OD) should be stamped on face of plate and visible when installed on pig. 3.3.3.2 Gauge plate location It is good practice to have gauge plates on several of the pigs in the flooding, cleaning and gauging pig train. As a minimum one gauge plate should be fitted on the last pig of the pig train to reduce the risk of damage to the plate by debris. The gauge plate shall be mounted on the pig in such a way that it is not damaged by contact with pipe wall in bends or with preceding discs during running or during pig insertion/retrieval, and normally on the rear disc package, close to the guiding disc. For pigs that need to be back loaded, precautions to prevent interference/contact to the gauge plate from guide and seal discs need to be considered in the pig design. 3.3.3.3 Calliper pig Calliper pig shall comply with technical requirements stated in DNVGL-ST-F101 Sec.10. The reporting specification of a calliper pig should be equal or better than a gauge plate. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 22 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used 3.3.2.2 Instrumented gauge plate An instrumented gauge plate gives an indication of whether a gauge plate is damaged or not via a signal that is activated if the gauge plate is damaged. Thus it indicates the gauge plate condition prior to removal of the gauge pig from the pipeline. The signal may also aid in localization of an indicated damage. 3.3.4.1 Multi diameter pipelines For gauging pipelines with variable internal diameters, 'intelligent' gauging tool (bi-directional calliper pig) should be used. Gauge plates are ineffective on multi-diameter pipelines as they have a fixed size based on the smallest pipe internal diameter and therefore the larger diameter pipeline sections cannot be checked. The gauge plate proves the internal bore of the pipeline at a given minimum internal diameter and ‘passage’ of a gauge plate may be used to ensure passage of a future calliper pig. 3.3.4.2 Expansion pools Pigging onshore, i.e. pull-through of gauge plate(s), may not sufficiently confirm pigging ability of the spools after installation as these types of measurement 'tools' always will be positioned in the lower part of the pipe during the pull-through operation. Use of a 'wheel trolley' or centralising discs as part of the gauging device may solve this problem. 3.3.5 Acceptance criteria A gauge plate is acceptable if no deflection of the plate is observed. If several gauge plates are used at least one of the gauge plates shall be acceptable. The gauge plate may show minor abrasions and ‘nicks’ on the plate edges. Any such defects shall be analysed and subject to operator’s acceptance. A damaged gauge plate is indicative of a reduction in pipeline bore either by debris, damage to the pipeline or partially closed valve. To conduct an investigation the following considerations would be required: — — — — — — Occurrence of high pressure spikes on the pressure recording from the pig run. Calculation of pig position at high pressure spikes. Likely areas of concern on pipeline i.e. component location, changes in pipe diameter. Levels of debris discharged. Past history of pipeline installation. The gauging shall document that the minimum ID is above a given requirement. The gauge plate size shall be according to DNVGL-ST-F101 Sec.10. Guidance note: Care must be taken during gauge pig loading and unloading so as not to cause any damage. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 23 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used 3.3.4 Special considerations 4.1 Objectives According to DNVGL-ST-F101 the pipeline system shall be subject to a pressure test after installation. The system pressure test shall be considered as a test for: — gross errors — leakages. 4.1.1 Gross errors For a new pipeline system the system pressure test will enable the confirmation that the pipeline system is acceptable with reference to risk associated with gross errors, such as: — Damages caused during pipe handling, transportation, storage, pipeline installation and tie-ins. — Damages caused during ploughing, other trenching methods, by anchor, anchor chains, wires etc. 4.1.2 Leakages The system pressure test will enable the confirmation that the pipeline system, including pipeline and components, is free of leakages. Note, however that the system pressure test only will detect leakages above a certain threshold depending on pipeline volume and holding period. Procedure for localization of any leaks discovered during system pressure testing should be developed as part of the system pressure test procedure. 4.1.3 Limitations The system pressure test is not suitable to prove structural capacity of the pipeline system; hence the test should not be considered a strength test. Guidance note: The structural capacity of each linepipe should be confirmed by the mill pressure test, see DNVGL-ST-F101. The mill pressure test should constitute the highest utilisation (hoop stress) of the line pipe since the consequence of failure will be least. In the same way as for linepipes, all pipeline components (e.g. connector, flanges, wyes, tees, valves etc.) must have been previously tested at a pressure in line with the governing code for than component. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--Guidance note: For a typical system test pressure utilisation of the girth weld will not be sufficient to detect a structural weakness in the girth weld apart from gross errors. The structural capacity of the girth weld must be ensured by proper welding procedures and quality control, see DNVGL-ST-F101. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- 4.1.4 Waiving of system pressure test The pipeline system pressure test may be waived. See DNVGL-ST-F101 Sec.5. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 24 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used SECTION 4 SYSTEM PRESSURE TEST 4.2.1 When to perform the system pressure test All intervention work on the submarine pipeline system, including crossings, trenching, gravel dumping, artificial backfill, subsea assemblies, riser installation, as-built surveys etc. should be completed before the final pressure test commences, see DNVGL-ST-F101 Sec.10. Guidance note: Project specific requirements for inspection and/or installation constraints may require that the system pressure test is performed prior to completion of all intervention work. Trenching, post-lay rock dumping and as-built surveys may be performed after the system pressure test if it is considered unlikely that the pipeline system will be damaged during these activities. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- 4.2.2 System battery limits and isolation The extent of the system pressure test should normally include all permanent components and connections within the pipeline system. The system may be tested as separate sections. This requires that the tie-in welds between sections are ‘Golden welds’. Pipeline components that will be exposed to the test pressure shall previously have been tested to a pressure not less than the local system test pressure. Testing should not be performed against in-line valves, unless possible leakage and strength of the valve is considered. If testing towards valves cannot be avoided, the most conservative approach would be to assume that the valve is leak tight. Tie-in of a new pipeline system into an existing system will require special considerations. The pipeline system code breaks shall be defined during pipeline system design. 4.2.3 Specification of test pressure The required system test pressure along the entire pipeline shall be established in accordance with DNVGLST-F101. The required local system test pressure during the test shall meet the following requirement: — safety class (in operation): medium and high — test pressure (local) = 1.05 x incidental pressure (local) — safety class (in operation): low — test pressure (local) = 1.03 x incidental pressure (local). Guidance note: The test pressure is the internal pressure at a specified elevation. Normally the reference point for the specified test pressure is the same as the point of pressure monitoring. If this is not the case the test pressure at the point (elevation) of pressure monitoring shall be established based on difference (in elevation) between point of reference and point of monitoring. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--Guidance note: The checklist attached in App.C may be used as reference for specifying test pressure. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- For a pipeline system comprising of different parts (rigid pipeline with flexible riser or flexible tail or pipeline with different wall thickness), the part with the lower allowable test pressure shall determine the overall Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 25 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used 4.2 Pressure test operation 4.2.4 Specification of hold period The required test pressure hold period after stabilisation is minimum 24 hours, see DNVGL-ST-F101. For 3 pipeline volumes of less than 5000 m shorter holding periods may be agreed (between company and contractor during the design phase). Guidance note: In case a shorter holding period is considered, other parameters than the volume also need to be considered such as the leak potential, coating, complexity of the system et cetera. See also [4.2.5] and App.C. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- Longer hold periods should be applied to confirm leak tightness for longer pipelines, see [4.2.5]. 4.2.5 Confirmation of pipeline leak thightness One of the objectives of the system pressure test is to confirm that the pipeline is ‘free from leaks’. It is, however, not possible to confirm absolute leak tightness from the test due to allowance for some pressure variation and limitation in hold period. For practical purposes it is of interest to correlate the results from the system pressure test with a corresponding loss of product when the pipeline is put in operation. In other words, the system pressure test may be used to confirm that the pipeline is free of leaks above a certain size. If the calculated leak size is found unacceptable for longer pipelines, longer hold periods may be agreed to reduce maximum theoretical leak rate. Formulas that may be used to correlate a (pinhole) theoretical size of a leak path with the recorded pressure decay rate are given in App.C. 4.2.6 Equipment and instrumentation 4.2.6.1 General For the purpose of the system pressure test, the instrumentation and equipment used should be able to measure: — flow/mass rate of added test fluid during pressurisation — pressure — temperature. 4.2.6.2 Pressure recording The test pressure shall be measured using a dead weight tester or a high accuracy pressure transducer. In addition a high accuracy large diameter pressure gauge/subsea display shall be used. Dead weight testers shall not be used before a stable condition is confirmed, and shall not be used offshore when positioned onboard a vessel or subsea. Time history of the test pressure shall be recorded. Guidance note: Pressure recording frequency will depend on the used instrumentation. Typical values are: — every 15 min by an operator — every second by a data logger. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- 4.2.6.3 Temperature recording Instrumentation for monitoring and recording ambient and/or test fluid temperature is only mandatory if the acceptance criteria for the test allows for temperature correction of the test results. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 26 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used test pressure while maintaining required system test pressure. For rigid pipelines 0.96 of SMYS shall not be exceeded. Alternatively, the parts may have to be tested separately. 4.2.6.4 Equipment sensitivity and accuracy Requirements on system pressure test equipment's sensitivity and accuracy in DNVGL-ST-F101 Sec.10 are applied for instruments and test equipment. 4.2.6.5 Calibration Instruments and test equipment have to be calibrated in accordance with requirement in DNVGL-ST-F101 Sec.10. 4.2.7 Pipeline condition prior to testing 4.2.7.1 Test medium With reference to the main objective of the system pressure test, the test medium should be water or other suitable liquids, e.g. glycol (MEG). For arctic conditions sub-zero ambient temperature conditions need special consideration. It should be noted that sub-zero temperatures may also occur in deep waters. Freezing temperature of water depends on the salinity of the water and pressure. Different freeze depressants such as methanol or glycol may be used in combination with water to lower the freezing temperature. Testing with air or inert gases may be feasible for a pure leak test. The system shall then be inspected for leaks during the test. Test pressure is normally equal to design pressure. 4.2.7.2 Requirement to residual air content Air shall be removed from the pipeline system during flooding, cleaning and gauging operations in order to minimise the amount of compressed air in the pipeline during pressure testing operations. The residual air content during pressure testing should not exceed 0.2% of the total volume of the pipeline and be confirmed at 35% of test pressure, or at maximum 3.5 MPa (35 bar), see Figure 4-1. Figure 4-1 Determination of volume of air Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 27 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Independent of whether temperature corrections are allowed for in the specified acceptance criteria, the temperature should be monitored at the test head. Where the test head constitutes a high point in the system it should be ensured that any residual air is vented off prior to pressure testing. 4.2.8 Volume/pressure calculations The total volume of test medium required to pressurise/depressurise the pipeline to/from the target test pressure shall be calculated prior to test execution to ensure that sufficient test medium and pump capacity is available and that no test medium is lost during pressurisation. A theoretical pressure response curve linking the pipeline pressure to the added volume of test medium should be established before start of the test, accounting for pipeline expansion and compressibility of test medium, see App.C (formula in step 9). 4.2.9 Pressurisation Pressurisation of the pipeline shall be performed as a controlled operation with consideration for maximum allowable velocities in the pipeline and inlet piping. The last 5% up to the test pressure shall be raised at a reduced rate to ensure that the test pressure is not exceeded. The mill test pressure shall never be exceeded. Time shall be allowed for confirmation of temperature and pressure stabilisation before the test hold period begins. 4.2.10 Stabilisation period From the time the test pressure has been reached and the pipeline system is isolated from the active test equipment (pump accumulator) a certain stabilisation period will be required. The stabilisation period is from the time the test pressure has been reached and until the commencement of the hold period, i.e. the time of acceptance of the pressure test minus the specified hold period. Re-pressurisation and restart of stabilisation period may be required. Guidance note: The stabilisation period will vary depending on temperature gradient and any volume expansion. Typically well insulated pipe-inpipe systems and systems containing flexible pipe sections may require longer stabilisation periods. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- 4.2.11 Hold period monitoring and inspection The system test pressure and temperature (if relevant) shall be monitored and recorded during pressurisation, stabilisation and test hold periods. Data logging should be performed at a sufficient frequency in order to evaluate the test results and acceptance of the test. Guidance note: If possible the pressure variations should be recorded electronically to allow for continuous evaluation (i.e. calculations) of system test pressure variations. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- In general, visual inspection is not required during system pressure test. For subsea connections ROV leak observations may be facilitated by use of local dye injection/dye-sticks. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 28 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used The pressure test can be performed even when the air content exceed 0.2% provided a linear trend between added volume and pressure response can be established and the precision of the leak test will not be impaired, and the larger safety risk is verified to be acceptable following a risk assessment. The most likely leak points in a pipeline system are mechanical connectors due to ROV or diver tie-in operations, if relevant. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- For the purpose of a pure leak test, e.g. with inert gas, inspection of the entire pipeline route must be performed in order to confirm leak tightness. The test should be terminated if it is evident that the acceptance criteria, see [4.3], cannot be met. Guidance note: Abnormal system response such as unexpected pressure increase or decrease occurring during system pressure test execution may be related to: — Pipeline expansion. — External heating or cooling of test fluid. — Moving (raising) air pockets. Note: This phenomenon may create a safety risk for equipment and personnel, particularly in case of deep water pipelines. — Pipeline rupture or leak. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- 4.2.12 De-pressurisation De-pressurisation of the pipeline system shall be performed as a controlled operation with consideration for maximum allowable velocities in the pipeline and the discharge piping. De-pressurisation rates shall be recorded. Guidance note: Subsea de-pressurisation operation could be left 'unmanned' provided that during engineering phase a proper calculation note demonstrate that use of suitable orifices will fulfil de-pressurization requirements. In this case a minimum 30 min monitoring will be required during the de-pressurisation. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- 4.3 Acceptance criteria 4.3.1 Pressure variations Acceptance criteria for the system pressure test shall be established prior to execution of the test. For a rigid pipeline designed according to DNVGL-ST-F101 the pressure test is acceptable if the submarine pipeline system is free from leaks, and the pressure variation is within ± 0.2% of the test pressure. A pressure variation up to an additional ± 0.2% of the test pressure is normally acceptable if the total variation (i.e. ± 0.4%) can be documented that the additional pressure variations is caused by a combination of: — temperature variations — tidal water variations. If pressure variations greater then ± 0.4% of the test pressure are observed, the holding period shall be extended until a full hold period with acceptable pressure variations has occurred. The pressure test is acceptable when a minimum hold period (see [4.2.4]) of acceptable pressure variations have been recorded. For a pipeline system comprising of rigid pipeline and flexible parts (e.g. flexible tails), an equivalent acceptable pressure variation criterion should be determined on a project basis, e.g. by weighing the criteria for the different parts with respect to their volumes. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 29 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Guidance note: For a leak-tight pipeline the rate of change will typically show an exponential trend with time until a level is reached where the test pressure is influenced only by variations in ambient conditions. Compliance with ±0.2% pressure variation within a hold period of 24 hrs corresponds to a rate of change of 0.00083 MPa/hr (0.0083 bar/hr) for a test pressure of 10 MPa (100 bar). The plot intervals need to consider the sensitivity of the pressure recording system. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- 4.3.1.1 Temperature corrections Pressure variations caused by documented temperature variation can be accounted for, see DNVGL-ST-F101 Sec.10. Guidance note: Corrections based on temperature variations will normally require a number of measuring points along a pipeline. The set-up of measuring points for temperature measurements and methodology for evaluation shall be decided prior to the pressure test. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- As a first principle the test should comply with the acceptance criteria of ±0.2% variation in test pressure with no temperature correction. In case the test results are to be corrected for variations in ambient temperature, the requirements to temperature recordings and method for correction shall be established prior to test execution. The method shall include description of ambient temperature measurements, see [4.2.6.3], and equations for corrections are given in App.C. If temperature correction is to be applied a correlation between the local temperatures of test fluid as function of local variation in ambient temperature shall be demonstrated with reference to the pipeline design and insulation properties. 4.3.1.2 Tidal corrections Maximum variation in tides shall be established and effect on the system test pressure determined prior to the test. For a system pressure test monitored from either a fixed (non-floating) offshore facility or from land, no compensation for variation in tidal water should be allowed for. For a system pressure test monitored from a floating facility where the pressure at the vessel may vary due to variation in hydrostatic column height, compensation for variation in tides may be allowed, see also App.C. In cases where tidal water variations may have a significant effect, the duration of the system pressure test should be sufficient to reflect both a reducing and increasing tide (i.e. hold period >12 hrs). For a system pressure test monitored from a floating facility the effect of swell may also be filtered away from the measured pressure in case the effect is well documented. Guidance note: Effect of tidal variation on the differential pressure across the pipe wall and subsequent variation in effective pipeline volume is normally negligible. However, when the pressure is recorded from a floating facility (vessel) the pressure recorded at the vessel will be influenced by the variation in hydrostatic column height from the seabed to the vessel. For moderate tidal variations the effects are normally negligible. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 30 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Guidance note: 5.1 Dewatering 5.1.1 Objective The objective of dewatering is to remove the initial fill/pre-commissioning fluid to prepare for introducing product to the pipeline system or to make the pipeline system ready for drying, see [5.2]. The objective may be achieved following two different ways; either to minimize the residual precommissioning fluid content or to condition the residual fluid. The approach taken will depend on the intended pipeline service and with consideration for subsequent drying operation. In addition to fluid removal, removing any construction devices which are normally removed from the system prior to pre-commissioning, e.g. isolation spheres used for tie-ins should be accounted for. 5.1.2 Dewatering operation 5.1.2.1 Dewatering technique selection The following dewatering techniques may be selected depending on the requirement for water removal: — Dry gas pipelines: dewatering to be followed by a drying operation. Glycol train may be considered. — All other pipelines: dewatering to include e.g. MEG/methanol swabbing, or just product filling. Dewatering pig train may include batches with fresh water to remove/dilute salt water on the pipe wall along with e.g. MEG to condition remaining water film on pipe wall. Dewatering engineering and sequence will always consider the removal/drainage of the residual fluid in branches, low points, valve cavities and dead legs of piping or at least minimizing/conditioning the remaining fluid. 5.1.2.2 Dewatering medium Dewatering medium is typically: — — — — — air nitrogen glycol (batches or small volume pipelines) product (oil or gas) or stabilised hydrocarbon (diesel) process water (water injection lines). Dewatering medium shall be selected in accordance with the following criteria: — need and type of the subsequent drying operation — risk of flow assurance issues such as hydrate formation and emulsion formation during the dewatering operation — disposal of the dewatering fluid — criticality in case of contingency including environmental impact — corrosion (with prolonged exposure to high air pressure/oxygen content, relevant for deep water pipelines) — safety risk by use of product. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 31 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used SECTION 5 DEWATERING, DRYING, INERTING AND PRODUCT FILLING The following guidelines are highlighted in relation to the use of different propelling fluids: 1) Air: preferred for the dry export pipelines that will be subjected to a subsequent air/vacuum drying. Glycol, instead of methanol, may be used in case of swabbing in order to prevent explosive mixture risk. Evaluate risk of nitrogen hydrates when pressures and temperatures during dewatering are greater than 30 MPa (300 bar) and lower than 8°C. 2) Nitrogen: attractive in case of limited system volume considering that line dewatering will achieve also the inerting. Not convenient when a subsequent drying is required. 3) MEG or MEG gel: mainly considered for short subsea piping arrangements, manifolds piping, spools and jumpers. To verify any impact for the required displacement pressure and any issue caused by the liquid slug generated during the start-up of gas systems. 4) Hydrocarbon gas: advantage of combining product filling and dewatering by use of glycol train, more stringent operating and safety requirements, to verify the risk of hydrate formation at the expected pressure and temperature during dewatering. In order to carry out the dewatering of gas pipelines with product, risk of discharge to environment, system details and expected pig performance must be carefully assessed prior to choosing this alternative. Should subsea receival of pigs be considered, then adequate safety precautions must be provided to control pig receival. This alternative combines product filling, dewatering, and drying in one single operation. 5) Export product: mainly used for liquid export lines. Special attention should be paid in case of using un-stabilized liquid stream. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- Air used as dewatering medium for a pipeline that will be followed by a drying operation, shall be dried to such an extent to avoid re-introduction of water behind the dewatering train. Guidance note: Dew points of injected dewatering medium shall be limited to the practical limit of -40°C @ atm pressure. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- 5.1.2.3 Dewatering direction Dewatering direction shall be selected based on system configuration, considering the following issues: — — — — — — space availability and logistics at the two ends pipeline bathymetric profile and water depth pipeline design features such as change in pipeline ID, Wyes, bends, valves, tees etc. discharge location for the pre-commissioning and dewatering fluids different required performance (in terms of pressure and flow rate) for the dewatering spread dewatering control, acceptance criteria and monitoring requirement. 5.1.2.4 Dewatering speed Dewatering speed shall be controlled to maintain pig integrity and operation performance. The following issues shall be considered when selecting dewatering speed: — — — — — line diameter roughness of the line internal surface pipeline length presence and types of irregularities along the pipeline liquid vs. gas propellant of the pigs. Guidance note: Pig speed to be used for dewatering operation is normally limited to: - Steel mandrel disc/cup pigs. 0.3 - 1.2 m/s - All-urethane/hollow urethane pigs: 0.4 - 0,8 m/s For deep-water pipeline dewatering, lower pigging velocity down to 0.1 – 0.2 m/s may be evaluated. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 32 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Guidance note: 5.1.2.5 Pressure The dewatering station delivery pressure shall be estimated considering the characteristics of the pipeline, the configurations at the launching and receiving ends and all the different contributions to the system pressure drop. Estimation of the main operating parameters of the dewatering operation shall be made. These calculations may be done by simulation models. Model accuracy and detail shall be consistent with the project stage and the operation criticality. Guidance note: The contributions to be taken into account in the dewatering pressure estimate are: 1) Friction pressure drop of the pipeline section filled with water. The pressure drop of the pipeline section filled with air may be neglected. 2) Static heads: the air head should not be neglected in the case of deep-water pipelines. 3) Concentrated pressure drops such as dewatering pigs, connection hoses and intermediate joints, pig launching and receiving heads, back-pressure control. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- Guidance note: 1) In the case of water discharge on to platform or onshore, the input to the simulation model will typically be the discharge water flow rate. 2) In case of subsea discharge, the input to the simulation model will typically be the injected air flow rate considering that the outlet pressure is determined by the environment. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- Shut-down of the compressors before completion of the dewatering operation (i.e. pig train displaced up to the receiver location by gas expansion) may be performed. Appropriate time and procedure for dewatering compressor shut-down shall be defined considering the operating scenario, the operation criticality and any constraint/uncertainty. 5.1.2.6 Equipment The dewatering station design and sizing shall be based on the calculated requirements (expected range of flow rates and pressures for air, nitrogen or liquid displacement stream) and with a defined spare capacity and spare philosophy. 5.1.2.7 Discharge of fluids The pre-commissioning fluid discharge strategy shall be addressed for the dewatering operation, in particular to assess the environmental impact, see also [6.1.2]. 5.1.3 Special considerations 5.1.3.1 Dewatering of non-piggable systems Dewatering operation could be required also for systems that are not piggable. The following alternatives should be evaluated for these systems: — Gravity displacement is applicable to pipelines with constant down-hill slope. If gas is used as displacement medium, an interface with a glycol batch(s) is recommended to limit the water content and to prevent the hydrate formation. — Alternatively nitrogen and glycol displacement is applicable to systems having limited volume. Connections with valves shall be arranged and methodology to minimise the risk of potential leaks during the operating life should be implemented upon completion of the pre-commissioning phase. The Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 33 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used In case of dewatering without the use of pigs by a liquid, topics such as contamination length, mixing distance, over-pumping requirements, impact of the displacement liquid on the system during the start-up phase should be evaluated. 5.1.4 Technical requirements For requirements to pigs and pig trains, see [6.3]. For temporary equipment, see [6.5]. 5.1.5 Acceptance criteria Dewatering acceptance criteria shall be established prior to operation. The following parameters should be considered when specifying dewatering acceptance criteria: — received fluid volume and trend (in front of the dry sweeping pigs) — purity of received fresh water (desalination water), alternatively glycol batches — pig retrieval and pig status through visual inspection. Guidance note 1: Desalination slug fresh water purity: a target for maximum chlorides content of 200 mg per kg of water for carbon steel pipelines is normally accepted. In the case of CRA pipelines, the above specified maximum chloride content must be reduced based on the type of material. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--Guidance note 2: For dry gas pipelines the acceptance criteria should be at least 97% glycol concentration in the last batch and could be relaxed case by case. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- Details regarding sampling the received glycol/methanol batches as well as fresh water, detailing number, volume and timing between subsequent sampling should be prepared as part of the operating procedure. Evaluation of the glycol content in the received batch(es) can be performed using the following methods: 3 — measure of the density (kg/m ) of the sample — measure of the refractive index of the sample. 5.2 Drying 5.2.1 Objective The objective of drying is the removal of the water left in the pipeline after the dewatering operation in order to: — prevent corrosion development — avoid hydrate formation — prevent transport product contamination. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 34 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used residual water content should be typically lower than 20% vol. or such as to maintain a margin to hydrate generation. — Glycol displacement is applicable to systems of limited volume like non-piggable spools or jumpers connecting to subsea structures that become free flooded during installation. Normally, volumes of flushed glycols in the order of 2 or 3 times the volume to be treated, would allow for the conditioning of the system. After the flushing operation the system may be left filled with glycol in readiness for start-up of operations. — Onshore pre-filling with MEG gel or liquid MEG. To be considered for spools and jumpers. 5.2.2.1 Drying method selection The selection of method to be used for drying a pipeline is dependent on the pipeline characteristics, system lay-out, feasibility, schedule, environmental condition, and dryness requirement. The following drying methods are standard for pipelines: — convection drying using dry gas, normally air — vacuum drying. Drying with air may be combined with running foam pigs (for shorter pipelines) to enhance the effectiveness of the drying operation. Evaluation of the optimum time for drying should be addressed. Drying operation should be performed on the complete system i.e. after completion of all the intermediate tie-ins with the target of minimising any re-contaminated area. Vacuum drying is not considered efficient for longer, smaller bore pipelines. Drying, as described above, may be avoided by use of glycol train during dewatering operations. 5.2.2.2 Conventional drying using a dry air A typical drying process includes the following phases: 1) 2) 3) Drying phase when the dry air flowing over the wet surface remove the water left by the dewatering operation. Soak test (if any), see [5.2.2.4] for details. Final purging when the full pipeline volume is replaced and the documentation of the pipeline content status taken during the soak test is analysed at the outlet. Guidance note: The factors affecting the convective drying efficiency are: — The operation pressure should be minimised. In particular, the outlet back pressure should be kept at a minimum in order to maximise drying efficiency. — The drying fluid (normally air) flow rate. An optimum rate for drying can be established, however the consequences on the increased operating pressure profile should be understood and evaluated. — The ambient temperature of the operation affects the water saturation content for a unit mass of drying gas at a certain pressure. Normally this parameter is not controllable. — The pipeline 'geometrical effects' including 1) how the liquid film is distributed on the wall, 2) the adhesion and absorption of the liquid film on the pipe wall, 3) the actual pressure profile along the pipeline during drying when considering also the air gravitational head. — The dryness (water dew point) of the drying fluid, normally air. It should be noted that improvement of this parameter beyond a certain value has marginal effect on the operation efficiency while significantly impacting mobilised spread performance/size. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- A water dew point of the inlet air (drying gas) of minus 40 °C at 0.1 MPa (1 atm) is normally a good compromise between the operation efficiency and the required spread complexity and performance for most of the operating scenarios. Lower air dew point could be required in cold climates and deep water pipelines. Compressors shall provide oil-free air, ref [6.6.3], to prevent fouling/degradation of the downstream drying column/sieves and to avoid oil deposits forming in the pipeline which will shield water moisture from the dry air or depress its actual vapour pressure due to the oil-water interfacial tension force. Launch of foam pigs during drying is an acceptable practice. However, it is to be noted that the pipeline is not dried by using foam pigs. Dry air will dry-out the pipeline while the foam pigs are used to increase the process efficiency. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 35 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used 5.2.2 Drying operation Maximum pipeline distance that can be run by foam pigs is mainly dependent on the pipeline internal wall conditions. For new pipelines (better if internally coated) distance of up to 200-300 km may be considered feasible. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- The optimum range for dry gas flow rate shall be identified. For an efficient operation the drying gas flow rate shall normally be sufficiently high to maintain turbulent flow throughout the pipeline length. Guidance note: Up to a certain level an increase of gas flow rate reduces the time required for drying, besides, by increasing the pressure profile along the line (as effect of the larger flow rate), the water saturation decreases to the extent of not being compensated by the increase of introduced gas mass. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- 5.2.2.3 Vacuum drying Vacuum drying operation is performed through the following phases: 1) 2) Start air evacuation. Leak test. The vacuum plant shall be turned off and isolated and pipework shall be checked for in-leaks. In-leaks shall then be rectified or, if not possible, quantified. Any in-leakage rate still remaining from unrectifiable in-leaks as estimated from this test is used when analysing the final soak test results. Guidance note 1: Typically it is performed in the absolute pressure range of 0.01-0.02 MPa (100-200 mbara). ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- 3) Water evaporation. During this phase the rate of vapour generation drastically increases resulting in a reduction in the rate of pressure decline. Guidance note 2: Attempt to rapidly reduce the pressure could generate ice from the free water in the pipeline in case of insufficient heat exchange coefficient with the ambient. Ice formation has to be avoided as it will reduce the potential of the water to evaporate and as such to be evacuated from the pipeline. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- 4) Pressure draw-down. The draw-down pumping shall be maintained until a pressure lower than that required for the specified dew point is achieved. Typical final pressure draw-down absolute pressure is lower than 0.1 kPa (1 mbara). Guidance note 3: If a dew point of -20°C is required, equivalent to absolute pressure of about 0.1 kPa (1 mbara), pumping should be continued until a pressure of approximately absolute pressure of 0.05 kPa (0.5 mbara) or less is achieved. This is carried out to ensure that a stable balanced absolute pressure of 0.1 kPa (1 mbar) is obtained throughout the pipeline system. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- 5) 6) 7) Soak test. See [5.2.2.4] for details. Purging phase. Purging shall be conducted by feeding nitrogen (or dry air) under vacuum conditions. Line packing. Final packing pressure is generally defined on the basis of project requirements and following the required conditions for the start up. If no specific requirements are given, the pipeline shall be pressurized up to absolute pressure of 0.11 – 0.15 MPa (1.1 – 1.5 bara). 5.2.2.4 Soak test Soak test may be used to prove that no significant water is present in the pipeline. Soak test is performed by suspending drying operation (convectional drying or vacuum drying) and close in the pipeline for a period dependent upon the length and volume of the pipeline (typically 12 – 48 hours). In this way, any remaining water will be picked up by under-saturated air. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 36 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Guidance note: The effectiveness to obtain a representative documentation of the pipeline content status via a soak test is uncertain in particular for longer length. The water picked-up during the soak period can then re-condense in a downstream section at lower temperature or turbulence/mixing effects occurring when the flow is re-started could actually significantly disturb or even hide the taken pipeline content status. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- 5.2.3 Technical requirements For air drying it shall be confirmed that all valves are drained and normally set in half open position (after foam pigging to be completed, if any) prior to commencing drying operation. For vacuum drying it shall be confirmed that: — Valve seats can withstand foreseen vacuum. — Vacuum does not generate ovalisation of the pipeline. For temporary equipment and instrumentation, see [6.5]. 5.2.4 Acceptance criteria 5.2.4.1 General The drying acceptance criterion for pipelines shall be based on the amount of water left in the pipeline for a unit of volume of gas at standard conditions. The final acceptance criteria for the dew point should consider the gas specification requirements. 5.2.4.2 Acceptance criteria for convection drying For the convection drying the following two alternative criteria can be applied: 1. Outlet dew point trend and a successful soak test. Drying until the following conditions are verified: — achievement of outlet dew point — performance of a soak test for a given duration — no significant increase of the outlet dew point when flowing a minimum of 1 pipeline volume at drying operating pressure during the 'final purging' phase (i.e. following the soak test) still reaching a dew point plateau below the minimum. 2. Difference between inlet and outlet dew point. Drying until the difference of inlet and outlet dew points is less than a predetermined quantity as reported here below. Typical requirements are: o - Inlet dew point: - 40 C @ atm. - Gap between inlet and outlet dew point: lower thank 7 C. o Guidance note 1: Field experience indicates that 10-15 pipeline volumes (after depressurisation) of dry air are required to reach the acceptable results in an internally coated pipeline. Larger volumes shall be expected for non-internally coated pipeline. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--Guidance note 2: Theoretically, foam pig launch should continue until the pigs are received nearly 100% dry. In order to confirm that the line is sufficiently dry to perform a 'soak' test, 2 or 3 'dry' pigs should be received. From a practical point of view, if two successive pigs are received carrying 10% or less of the estimated water capacity of the pig, then further foam pigging can be ceased. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 37 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Guidance note: Pipeline pressure trend during the performance of the soak test: the resulting pressure after an initial stabilization period should remain below the dew point equivalent pressure correlating to the desired dew point (for a dew point of -20°C, this is 0.1kPa (1mbar)) , notwithstanding any allowance for in-leakage observed during step 2) of [5.2.2.3]. Pressure and corresponding dew point shall be continuously monitored and recorded during the final drawdown phase (following soak test) until reaching the vacuum level available before the start of the soak test. 5.3 Inerting 5.3.1 Objective The objective of inerting is to reduce the oxygen content to an acceptable level before introducing hydrocarbon gas. 5.3.2 Inerting operation 5.3.2.1 Nitrogen intering Either the entire pipeline system can be purged with nitrogen, or a slug of nitrogen can be injected ahead of the gas being used to commission the pipeline. This creates an inert environment that cannot support combustion when the final product is introduced and also it may reduce or eliminate corrosion prior to operation. The nitrogen gas can be produced from vaporized liquid nitrogen, or be membrane generated. Guidance note: Where membrane generated nitrogen is used, the purity of nitrogen entering the pipeline will typically be 95%. In most cases a final oxygen level of 5% will be acceptable. Where vaporised liquid nitrogen (LN2) is used this has purity better than 99.99%, hence oxygen levels well below the accepted requirement are achieved. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- 5.3.2.2 Vacuum By pulling a vacuum on the pipeline system the pressure is reduced and hence close to all air is removed from the system. Relative to an initial absolute pressure of 0.1 MPa (1 bara), the mass of air after reducing the absolute pressure in the line down to 0.1 kPa (1mbara) is reduced by 99.9%. If required, it is possible to purge the pipeline with nitrogen at low pressures to displace the partial pressure of air with a partial pressure of nitrogen. The dew point measurement during the purging phase must be monitored and recorded, and confirmed to be below the specified acceptance level until reaching the specified packing absolute pressure (typically 0.11 – 0.15 MPa (1.1 - 1.5 bara)). 5.3.3 Technical requirements For temporary equipment, see [6.5]. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 38 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used 5.2.4.3 Acceptance criteria for vacuum drying A commonly used acceptance criterion for vacuum drying is a dew point of -20°C. This corresponds to a saturation absolute pressure of 0.103 kPa (1.03 mbara) and to residual water content in the pipeline of 0.9 3 g/m . More stringent requirements may be specified, but will normally require significantly longer drying times. The nitrogen purity achieved shall be as specified for the project. If a slug of nitrogen in front of the natural gas is used, then the mixing zones must be calculated in order to verify that the slug length is sufficient to prevent an explosive mixture. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 39 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used 5.3.4 Acceptance criterion 6.1 Operational principles 6.1.1 Management Management of pre-commissioning projects and activities should be in compliance with the requirements of the individual contracts, governing regulations/codes/standards and in compliance with industry best practice. Good communication in all phases of the project is essential and sufficient systems should be in place to ensure proper and correct exchange of information, notifications and messages. 6.1.2 Quality and HSE Project specific QHSE requirement should be defined. A quality plan should be developed based on the principles of ISO 9001 or equivalent and should identify required organisation, resources, activities and control points to ensure work is performed in compliance with relevant regulations, standards and specifications. An HSE manual should be developed, taking into consideration the occupational health, safety of personnel and assets, and the environment during all phases of the work. Essential elements that should be covered are: — — — — — — — — — personnel safety and training operational safety, inclusive of PPE chemical handling, inclusive safety data sheets noise pollution risk management and evaluation management of change communication and emergency procedures odour, if any. In order to minimize the environmental impact of operation the following issues should be addressed: — Environmental friendly fluid treatment should always be selected. The effectiveness of the treatment shall be considered. — Disposal of chemically treated pre-commissioning fluid by e.g. an environmental risk assessment. A test programme should be carried out, if required. — When discharging to the marine environment, consideration should be given to utilizing mechanical discharging devices that will allow mixing and diluting of the test fluid in the marine environment. — Potential for erosion from discharge/turbidity of pre-commissioning fluid. — Location of equipment to minimize consequences of intentional/unintentional discharge of oil, diesel or chemicals. Consider use of bunds. — Noise from pre-commissioning equipment or gas venting from the pipeline. — Operational duration: extended operations may cause disturbance to the local environment. — Seasonal and tidal factors: these factors should be investigated before discharging operations. Guidance note 1: When discharging treated seawater overboard, the discharge depth, location, and sea currents shall take into consideration the intake for vessel and/or platform water makers. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 40 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used SECTION 6 MISCELLANEOUS ISSUES A guideline for environmental risk assessment is the comparison of the PEC (predicted environmental concentration) vs. PNEC (predicted no-effect concentration). If the ratio PEC/PNEC is lower than 1, the product poses no risk. Besides, if this ratio is equal to or higher than 1, management measures have to be taken to reduce the exposure to an acceptable level. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- A hazard and operability study (HAZOP) should be performed dedicatedly for each operation/procedure. DNVGL-RP-N101 may be followed. 6.1.3 Planning and engineering For planning and engineering the following list of required documentation may be used as guidance: — philosophy or method statement — project/execution schedule — calculations and selection of treatment, equipment (based on required capacities/ performance) and spares — layout and arrangement drawings for permanent and temporary equipment — execution manuals/procedures, providing all information needed for execution of the individual operations, including operation manuals for temporary equipment/components — interface and mobilisation manuals — contingency plans — spare philosophy — pipeline systems piggability study. Risk evaluation and HAZOP findings should be implemented in the operational manuals/ procedures prior to start of any operations. 6.1.4 Execution Execution of offshore/onshore operations shall be in accordance with the project philosophy/ method statement and/or execution manual/procedures and take into account safety and risk elements brought forward relative to the individual operations. Special focus should be put on operations involving work on/ with/in connection with operating pipelines or use of hydrocarbon fluid as propelling medium. Pre-commissioning personnel should be sufficiently trained and briefed for the operations to be conducted. Leading/supervisory personnel should have relevant and prior experience from the types of operations to be performed. 6.2 Documentation 6.2.1 General Pre-commissioning documentation shall at a minimum consist of: — — — — — — specifications design reports of equipment and systems manufacturing and calibration certificates test reports of temporary equipment and assembly procedures final documentation. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 41 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Guidance note 2: A pre-commissioning specification should be developed for the pipeline system, describing principal methodology and requirements for execution of all operations relevant for the work. Reference levels/heights for design and test pressures should be stated explicitly. Functional requirements of spreads, equipment, personnel and acceptance criteria/results of the operations should be clearly defined. Limitations and boundary conditions for the work, relative to the pipeline system or any appurtenant systems, should be highlighted. Detailed procedures shall be prepared for the pre-commissioning activities and be made available to all parties prior to the operation. The following checklist is provided for guidance: — — — — — — — — — — — — — step by step execution plan including contingency operations established operational limitations identified communication plan established mobilisation plan established pre-commissioning spread mobilised and calibrated and function tested with appropriate certificates inspection and test plan established agreed reporting format and frequency valve status check treatment dosage established environmental log established toolbox meetings/JSA held and findings communicated to all involved parties operational acceptance documents management of change system established. 6.2.3 Final documentation The final documentation shall include all relevant information, calculations and considerations made in order to ensure the traceability of the pre-commissioning performed. Final documentation produced in connection with pre-commissioning of the pipeline system shall as a minimum include: — approved procedures — management of change — flooding, cleaning and gauging operations: — — — — — — volume of fluid introduced log of additives debris record gauge results pig condition report acceptance documents — pressure test: — pressure log and charts including temperature log — pressure test acceptance documents — dewatering, drying and inerting operations: — — — — calculated volume or removed fluid (during drying) pig condition report level of dryness achieved for inerting, final oxygen concentration achieved Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 42 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used 6.2.2 Documentation prior to execution — environmental accounting: — list of chemicals used, discharges to sea an air — report of noise pollution during operation, if any — log of activities — statement of compliance — instrument and calibration certificates — original records from all recorded information for pre-commissioning — daily log of operations — lessons learnt/recommendations for later pre-commissioning operations. Guidance note 1: A description of the activities and calculations to be performed as part of the pre-commissioning process should be considered in early design phases to prevent misperception of purpose of the test during execution and the test results. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--Guidance note 2: The checklist for system pressure testing given in App.B may be used as part of the final documentation. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- 6.3 Pigs and pig trains 6.3.1 General This section gives recommendations for pigs and pigging operations required for filling, cleaning, gauging and dewatering. The following shall be considered when selecting pig type/train design and operation: — Objective of the pigging operation. Pre-commissioning pigs are normally divided into groups to serve the following purposes: — — — — — — batching or separation of fluids/products displacement of fluids cleaning gauging dewatering or combinations of the above. — Pipeline characteristics, see [2.2] and also App.A and App.D for details. — Operational conditions, see [2.3] and [2.5], see App.A and App.D for details. 6.3.2 Pig train design 6.3.2.1 Flooding, cleaning and gauging For larger diameter pipelines (≥0.152 m (6")) flooding, cleaning and gauging pig trains should be used. This may range from one single pig, to a train of four or more when combined with cleaning and gauging operations. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 43 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used — acceptance documents Pig body and ancillary items must be compatible with pipeline material and components. Brush pigs are often used for cleaning, but normally not applicable for pipe with internal coating, flexibles and CRA materials. Foam pigs can be used as separation pigs, but are not recommended in the cleaning and gauging precommissioning stages as they are less effective compared to metal bodied disc pigs. It is not recommended to perform fill operations on pipelines < 0.152 m (6") diameter by use of metal bodied pigs. If a pig is to be used a solid cast or foam type should be considered. All pigs used during flooding and cleaning operations should be bi-directional. Pigs with bypass ports may be used to keep debris suspended in front of the pig if the pipeline is expected to contain large amount of debris. Bypass ports shall be used with caution if multiple pigs are used in the cleaning train as these will have to be sized appropriately throughout the train to ensure pig separation is maintained. The pig design shall ensure that pressure cannot be trapped inside any part of the pig. Guidance note 1: Bidirectional separation pigs are typically made up from a metal body with flexible sealing discs. The sealing discs are typically made from types of polyurethane of varying hardness, depending on the requirements to durability, support and flexibility of a particular pig. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--Guidance note 2: For optimum separation pig design and choice, pig trials may be carried out on a custom built pipe test loop that represents the unique pipeline system characteristics and any special features e.g. ID changes, valves, tees, wye, etc. In this way the pig sealing length, number of sealing discs, sizes, disc/guide configuration and material can be optimised for a particular pipeline. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- For air filled pipelines it is common practice to inject a slug of pre-commissioning fluid ahead of the first pig to provide lubrication for the pig discs and provide for a cleaning flow ahead of the leading pig. The precommissioning fluid volume to be injected ahead of the first pig should consider the pipeline characteristics and expected debris in the pipeline. Guidance note 3: The volume pumped in front of first pig and between each pig should be based upon the following minimum sizes: — Pipelines ≤ 2 km – volume to fill up 50m pipeline length — Pipelines > 2 km to ≤ 5 km – volume to fill up 75 m pipeline length — Pipelines > 5km to ≤ 10 km – volume to fill up 100 m pipeline length — Pipelines > 10 km to ≤ 20km – volume to fill up 200 m pipeline length — Pipelines > 20 km to ≤ 50 km – volume to fill up 250 m pipeline length — Pipelines ≥ 150 km – volume to fill up 300-400 m pipeline length. A sliding scale between separation distances can be used to fit the exact length of the pipeline with the spacing required for that length of pipeline adjusted between two separation bands. When gas is used as separation or propellant fluid, due consideration should be taken for the compressibility of the gas with respect to pig spacing. Larger pig spacing will normally be required. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 44 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Figure 6-1 Typical FCG pig train design In some cases there may be a requirement to pump additional water in front of the filling pig train to reduce high pig velocities. Water pumped in front of the pig train can have a ‘dampening’ effect on pig train velocity, see [3.1.3]. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- 6.3.2.2 Dewatering The main variables that define a pig train composition can be summarised as follows: — — — — pipeline service design of pigs composing the dewatering train number of pigs composing the dewatering train type, size and number of batches included in the dewatering train. The pipeline service is the main driver in selecting the dewatering train configuration as it defines the efficiency required for the operation and requirement for chemical/rinsing treatment (if any). Dewatering trains for pipelines required to be dried after dewatering should be designed to remove as much water as possible and reduce any possible causes that could impact negatively the succeeding drying operation (e.g. salt deposit) via rinsing. Dewatering trains for other pipelines should be designed to remove water but also to chemically treat/dilute (glycol or methanol swabbing) the film of water left after the operation to reduce or eliminate the possibility of hydrate formation during the succeeding start-up phase. Guidance note 1: Dilution models should be used to assess the optimum combination relevant to number of batches and their sizing, considering requirements (e.g. the required final glycol purity), operation criticalities (consequences associated to repeating the run) and constraints (e.g. maximum number of pig in the dewatering/swabbing train). The model detail and expected precision should be established considering the risks and related consequences of not achieving the intended operation results (i.e. mainly the dilution of the residual water film). ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--Guidance note 2: The main functional requirement to a dewatering pig/pig train is the ability to displace as much water as possible during the operation. Strict tolerances on disk sizes and hardness may improve the efficiency. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- The operational safety aspects related to dewatering of longer and deep-water pipelines using air as propelling fluid should address both pig wear/pig damage and explosion risks. 6.3.3 Pig speed Pig speed is normally in the order of 0.5 – 1.0 m/s. Sealing capabilities of modern pigs are generally very good and pigging operations may very well be conducted at much lower velocities. Lower pig speed for dewatering may be considered, see [5.1.2.4]. Optimum pigging speed should be established and defined based on the type of operation and pipeline system to be pigged. Extremely high pig speeds (+10 m/s) should be avoided, especially in connection with compressed air/ nitrogen pigging as friction forces between pig and pipe wall may generate high temperatures that may damage (melt) the sealing discs. When composing pig trains for combined operations the pig train speed shall be limited by the pig having the most stringent requirement. 6.3.4 Pig tracking The primary method for controlling and monitoring pig speed and separation and consequently pig location is the rate of propelling fluid and/or discharge rate of pre-commissioning fluid in front of the pig train. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 45 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Guidance note 4: The following principles/systems are most common for tracking and location of pipeline pigs: — — — — acoustic magnetic electromagnetic radioactive. Pig detection shall be qualified for the pipeline configuration considering pipeline content and characteristics as e.g. coating, pipe-in pipe, burial or rock dumping. Each detection type/principle has its pros and cons; which should be carefully evaluated in order to obtain the required reliability and functionality of the tracking system. The number of and location of tracking devices in pig trains should be considered for each operation. Common practice is to have tracking devices on the first and last pig in a pig train. Considerations should be given to ensure sufficient battery life time of tracking devices accounting for possible delays in pigging operation and time for detection (i.e. time for positioning tracking vessel and ROV along pipelines. 6.4 Pig traps (launchers and receivers) and test heads Pig launchers and receivers should be designed and tested according to the applicable design standard and be suitable to facilitate pre-commissioning operations. Temporary launchers/receivers used during system pressure test should have a design pressure at least equal to the pipeline design pressure, see DNVGl-ST-F101 Sec.10. The design should prevent unintended opening while being pressurised. The pig launcher and receiver facilities need to be sized and configured to accommodate all types of pigs planned for during pre-commissioning, including any isolation spheres etc. used for tie-in. Special considerations should be given to design of subsea pig launchers/receivers with respect to ROV interface and weight and sizing for installation and removal. Considerations shall be made concerning double valves in start-up and lay down heads when used for pressure test as well as launchers/receivers. Wet buckle contingency shall be considered. 6.5 Temporary pre-commissioning equipment 6.5.1 General requirements The following requirements should be included for as relevant for the individual operations: — Design and testing of all temporary equipment shall be according to recognised standards. — Pressure producing equipment should have capacities of at least 10% in excess of the planned operational level/point. — Design pressure of equipment should be equal to or greater than the maximum expected pressure during the pre-commissioning operations. — Pre-commissioning equipment shall have sufficient flow capacity to accommodate the specified volumes and rates of filling/treatment/discharge of pre-commissioning fluid. — Contingency shall be provided for all critical spread components. — Mechanical maintenance of rotating and hydraulic equipment for long durations of operations. — Frost protection of equipment spread under arctic/cold conditions. — Cooling water/medium temperature checks under tropic/warm conditions. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 46 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used As an additional control pig tracking can be used to verify pig position and flow meter readings and to confirm arrival of pigs. 6.5.2 Function testing All critical and essential parts of the pre-commissioning spread should be function tested and accepted by operator prior to mobilisation. Final function testing of the complete pre-commissioning spread should be performed after rig-up on site, in due time prior to start of operations. 6.5.3 Instrumentation, logging and recording Reading resolution, ranges and accuracies of pressure test instruments shall be in accordance with [4.2.6]. Reading resolution, ranges and accuracies of general pre-commissioning instruments should be in accordance with Table 6-1 below. Table 6-1 Reading resolution, ranges, and accuracies of general pre-commissioning instruments Instrumentation Resolution Range Accuracy Dew point meter 1.0°C +40°C to -50°C ± 1.0°C Ambient temperature recorder (24 hr.) 0.5°C -20°C to 80°C ± 1°C Temperature probes (digital) 0.1°C -50°C to +50°C ± 0.2°C 2) Pressure gauge and recorder 0.05 MPa (0.5barg) 0-120% ± 1% Pressure gauge and recorder 2/0.1/0.05/0.01 kPa 3) (vacuum operation) (20/1/ 0.5/0.1mbar) 0 kPa - 100/10/5/1 kPa (0mbar-1000/100/50/10mbar) Flow meter and recorder Dependent upon pipeline volume Dependent upon pipeline volume ± 2% and/or spread capacity Barometer 0.01 kPa (0.1mbar) Relevant to site 1) ± 1% 1) ± 0.08 kPa (0.8mbar) Notes: 1) Percentage of full range. 2) Percentage of maximum pressure expected during the relevant pre-commissioning operations. 3) Different pressure gauges required for different vacuum ranges. Back-up/contingency units should be provided for all essential instrumentation. In addition to electronic data recording, manual recording of operational data should be made regularly at sufficient and adapted intervals to provide control of the status and progress of the on-going operation(s). 6.5.4 Equipment on board vessels Pre-commissioning operations from vessels should be subject to the following additional evaluations: — Establishment of environmental restrictions to the operations. — Hose type and capacity, handling and configuration during operation, including hose reels position on deck. Hose collapse to be addressed separately. — Quick disconnect system. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 47 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used For temporary equipment that is used for more than one pressure test, the cyclic loading needs to be considered to avoid failures due to e.g. fatigue, exposure to chemicals or other mechanical damage. 6.6.1 General All fluids used for pre-commissioning shall be in compliance with local and statutory rules and regulations. The fluids marked X in Table 6-2 below are typically used during pre-commissioning (less frequent use is marked in brackets). Table 6-2 Fluids used during pre-commissioning Commissioning fluid Cleaning Gauging Pressure test Dewatering X X X X Water Drying X X Nitrogen X (X) X (X) (X) (X) (X) Preservation (X) Air MEG Inerting (X) X X (X) Guidance note 1: Water is the main type of pre-commissioning fluid used during pre-commissioning operations; filling, cleaning, gauging and hydrostatic pressure testing. Water is used during filling and pigging due to its low cost and eases of access (subsea pipelines) and for testing operations due to its incompressibility and inert properties. Low temperatures (i.e. winter conditions) may require use of MEG as an additive to water. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--Guidance note 2: If gas is used as fluid for pressure test, it may cause increased harm to personnel in case of pipeline or equipment failure due to its higher energy storage. In this case, strength of the pipelines/equipment need to be confirmed (e.g. by strength test) before pressure test can be performed at least for pipelines/equipment located at location class 2. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- 6.6.2 Water Filtered and chemically treated seawater is commonly used as the pre-commissioning fluid when the pipeline volume and location exclude the use of potable/fresh water. The need for and use of chemical additives shall be documented, see [6.7]. All water entering the pipeline system shall as a minimum be filtered to remove suspended particles larger than 50 micron and should have 3 an average content of suspended matters not exceeding 20g/m to prevent larger particles/volumes to enter the pipeline, see DNVGL-ST-F101. Guidance note: The type of filtration required depends largely upon the water source conditions and the volumes required. For relatively small 3 volumes from a clean source (e.g. < 2m /min), basket filters may be suitable. Where the water supply is less clean, self-cleaning filters may be required in order to meet the required cleanliness whilst maintaining the required pumping rates of larger diameter 3 pipelines (e.g. ≥ 2m /min). ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- If potable/fresh water is used the requirements to maximum levels of chloride should be defined. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 48 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used 6.6 Pre-commissioning fluid Use of air as pre-commissioning fluid is normally limited to dewatering and drying, through use of compressor spreads that injects air as the driving medium for pigs or for purging the pipeline systems. For air drying operations, the air injected in to the pipeline should have an oil content not exceeding the levels set out in ISO 8573-1 oil class 1. For other pre-commissioning operations involving compressed air, oil levels set out in ISO 8573-1 oil class 2 and 3 should be acceptable. Such standards are commonly referred to as 'oil-free'. The condition of the air with respect to pressure, temperature and dew point, shall be established. Special care should be paid to use of air in connection with hydrocarbon operating systems as the oxygen in the air may cause spontaneous combustion/explosion. 6.6.4 Nitrogen Use of nitrogen as pre-commissioning fluid is normally limited to dewatering, drying, inerting and preservation. Nitrogen can be supplied in racks (as gas), in tanks (as liquid) and also through nitrogen generation plants (membrane units) on site. Nitrogen is used in pipeline pre-commissioning operations due to its inert nature/properties. The concentration of the nitrogen shall be established, see [5.3]. 6.7 Corrosion assessment and water treatment 6.7.1 Corrosion assessment Routines and specifications for assessing both environmental risks related to disposal and corrosion risks related to the pre-commissioning and operational phases shall be established. Pre-commissioning fluid discharge permits shall be obtained, as required. If seawater is used it shall be tested for concentrations of oxygen and organic matter. It is recommended to acquire the water from a certain depth above the seabed in order to avoid contaminations by seabed sediments. 6.7.2 Corrosion threats In Table 6-3 are listed the potential effects of pre-commissioning fluid on corrosion for different types of linepipe materials. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 49 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used 6.6.3 Air Potable water (treated fresh water) Pipe material Corrosion mechanism and form CMn steel 13Cr O2-corrosion Under deposit corrosion MIC(aerobic) Localised corrosion (O2) Recommended Treated seawater Corrosion mechanism O2-corrosion MIC (aerobic/anaerobic) Yes Recommended and form Yes Under deposit corrosion Yes 3,4) MIC(aerobic/anaerobic) Localised corrosion (O2) 316 (clad/lined) No corrosion Yes 4) 22Cr No corrosion Yes 4) 25Cr No corrosion Yes 4) Alloy 625 (clad/ lined) No corrosion Yes 4) Alloy 825 (clad/ lined) No corrosion Yes 4) MIC(aerobic/anaerobic) Localised corrosion (O2) MIC(aerobic/anaerobic) Localised corrosion (O2) MIC(aerobic/anaerobic) Localised corrosion (O2) MIC(aerobic/anaerobic) Localised corrosion (O2) MIC(aerobic/anaerobic) Localised corrosion (O2) No Treated fresh water 1) is preferred Treated fresh water 1) is preferred Yes 2) Yes 2) Treated fresh water 1) is preferred Notes: 1) For Alloy 825, 316 and 22Cr seawater may be used if precautions are taken regarding treatment (filtered and added chemicals to reduce the corrosivity) and maximum exposure time. 2) Untreated seawater may be used for stainless steel 25Cr and Alloy 625. 3) Treated fresh water shall be added oxygen scavenger to avoid corrosion; primarily by aerobic bacteria. 4) Treated fresh water shall have low chloride content typically 50 mg/l for 13 Cr and 200 mg/l for other stainless steel types. Microbiologically influenced corrosion (MIC) may cause corrosion damage to CMn steel and CRA linepipe materials. Bacteria introduced during pre-commissioning may also cause MIC during subsequent operation. Guidance note: MIC is not critical for pipelines to be operated with dry gas or dehydrated condensate. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- 6.7.3 Water treatment It is normal practice to treat the water entering a pipeline system during filling and/or pigging operations in order to prevent pipeline internal corrosion. Selection of additives should be based on evaluation of objective, interaction with pipeline materials and effects on personnel and environment during handling, injection and discharge and documented in the final documentation. As a minimum the following shall be addressed: — national/authority regulations Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 50 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Table 6-3 Potential effects of pre-commissioning fluid on corrosion for different types of linepipe materials project requirements pipeline geographical location (environmentally sensitive areas) filling water temperature and quality pipeline material pipe wall surface (coated/uncoated) additive retention period required disposal of treated water. An assessment of the compatibility of the different additives shall be carried out in order to eliminate detrimental chemical interactions. Guidance note: Additives will generally not be used in the pig separation slugs during filling, cleaning and gauging operations since these slugs will be discharged from the system during the pigging operation and will therefore have no effects relative to pipeline protection. In cases where pig trains are inserted in the pipeline system at an early stage of the project – chemical inhibiting of the separation slugs may be required. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- The following lists examples of different additives typically used: Table 6-4 Examples of different additives Type of additive Corrosion mechanisms Mitigating effect Oxygen scavenger Oxygen corrosion and MIC aerobic bacteria Reduce amount of oxygen Biocide Microbiologically influenced corrosion Reduce bacteria content Sodium hydroxide (NaOH) Enhanced bacteria growth and oxygen corrosion Increase pH to mitigate bacteria growth and decrease corrosion of carbon steel Corrosion inhibitors Oxygen corrosion Reduce oxygen corrosion Scale inhibitor Scaling due to high pH in seawater Reduce scaling Removes/dissolves water from the pipe wall during dewatering/swabbing operations. Effective as frost protection and may be used to prevent bacterial growth MEG Oxygen scavenger may be required to avoid formation of colloidal rust affecting discharge of water and to avoid the biocide to react with oxygen. Biocide addition to seawater is always recommended for CMn steel pipelines if the duration of exposure is exceeding a certain period of time. This is typically set to 28 days in warm waters, necessary for bacteria to form a biofilm causing MIC or if there is otherwise a risk of introducing anaerobic bacteria (primarily SRB) into the production system causing corrosion damage at a later stage. The amount of biocide to be added is dependent on the temperature, pH and the length of time the water will be left in the pipeline. Biocides for SRB control are not necessary for fresh water if the sulphate content is low. Adjusting pH > 10 is a method of suppressing the bacteria growth and rendering the water non-corrosive to CMn steel and CRA linepipe materials. Increasing pH of seawater may result in precipitation of scale on the pipe walls and in the pipeline, which may give detrimental effects on subsequent cleaning and drying. Scale may further be treated with scale inhibitors, if required. UV treatment may be considered as an alternative to biocide treatment, subject to specific project evaluation. Acceptable exposure time, i.e. time period the pipe wall can be exposed to the pre-commissioning fluid, shall be established ensuring efficiency of additives and limit any corrosion processes during precommissioning. Contingency plans to avoid exceeding the acceptable exposure time shall be established. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 51 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used — — — — — — — Due to the environmental impact of fluid discharge, consideration shall always be given to the use of more environmentally friendly additives or limit the amount used. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- 6.7.4 Additive dosages and consumption Systems shall be in place ensuring that the correct additive dosages are injected. Spare capacity for chemical injection system shall be available, to take into account deviation in pre-commissioning fluid as compared to planned flow rate. Guidance note: Chemical suppliers should be consulted to define a concentration range that will ensure flexibility related to deviations from planned flow rate. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- 6.8 Other considerations/special systems 6.8.1 Pipeline system components All pipeline system components shall be designed according to the applicable design standard and tested separately prior to installation. Test pressure shall be at least equal to the pipeline system test pressure. Valves should not be used as end closures during system testing unless the valve design allows for full differential pressure across the valve body. If testing is performed against closed valves, considerations should be given to through-valve leakage rates and the possibility for measuring these. Conservatively no leakage should be allowed unless the amount is measured and documented. Inline valves and arrangements should be full bore and without internal obstructions that may restrict or damage pigs during pigging. Considerations should be given to the necessity for including valve cavities during pressure testing by having half open valves. Bends should be designed for pigging and have a bend radius of minimum 5 x ID. Smaller bend radii may be allowed subject to qualification of piggability. Tee sections should be designed for pigging. Bars in barred tees should not protrude into the main line bore. Sizing and spacing, also including distance to bends, should be specifically considered to prevent by-pass during pigging. Wye pieces should be designed to allow pigging of both the connecting lines. Due considerations should be made to the branch line angle into the main bore with respect to pigging (sealing distance). It shall be confirmed that expansion spools are suitable for all planned pre-commissioning activities, in particular considering pigging operations. Expansion spool inner diameter and bend radius should be checked. Prior to installation each expansion spool should be cleaned, gauged and tested to minimum the same requirements as for the complete pipeline system. 6.8.2 Combination of rigid and flexible pipelines The behaviour of flexible flow lines during pressurisation shall be taken into account for system pressure test. Due considerations shall be given to establishing acceptance criteria for combined flexible-rigid line systems. The supplier of flexible pipe or riser shall be involved in the selection of pig design. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 52 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Guidance note: Special design considerations should be made to lines (new/old) connecting to lines in operation through e.g. hot-tapping. Double isolation valves with bleed should be included in order to ensure adequate precommissioning/commissioning of the connecting line. Ventilation and drain points for testing and purging (gas lines) should be included and placed at functional and appropriate locations. 6.8.4 Multi diameter pipelines If a pipeline system consists of multi-diameter sections due considerations should be made with respect to: — — — — — required pigging direction (launch and receiving facilities) inner diameter transition design gauging technique (gauge plate versus calliper) pigging speed and control later pigging during operational phase. In order to provide sufficient sealing effects throughout the entire pipeline the smaller ID section should preferably be towards the end of the pig run(s). Guidance note: ID variations up to 8-10% are normally acceptable for modified standard disc pigs. ---e-n-d---o-f---g-u-i-d-a-n-c-e---n-o-t-e--- 6.8.5 Wet buckle contingency Pigs may be inserted into start-up heads to allow for cleaning and dewatering in case of wet buckle during pipeline installation. Contingency plans should include pumps, dewatering compressors, pipeline retrieval equipment, etc. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 53 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used 6.8.3 Connecting to pipelines in operation 7.1 References /1/ rd Pipeline design and construction – A practical approach; M. Mohitpour, H. Golshan, A. Murray, 3 Ed. 2008 Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 54 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used SECTION 7 REFERENCES A.1 Checklist for flooding, cleaning and gauging Project: Item Pipeline system configuration Date: Y N Question Comments Is the pipeline onshore or offshore? Are both ends accessible? Will there be need for vessel(s) to flood? Is subsea flooding an option? Is one flowing direction preferred? Pipeline characteristics Is it a one diameter or multi-diameter pipeline? (state minimum and maximum internal diameter) What is the minimum bend radii (and bend angles)? Are there any pipeline features and types: valves, Tees, wyes, branch connections, elevations etc.? Is the pipeline internally coated or not? Material quality, use of CRA? What is the maximum seawater exposure time acceptable for the submarine pipeline system? Flexible tails or flexible risers? Length of submarine pipeline system, giving implications for pig design? How is the permanent pig trap design? How is the temporary pig trap design? (is it rated for pressure test? Are pig traps adequate for the required number of pigs/calliper and for the accumulated debris in front of the cleaning train?) Flooding Will free flooding be used? In case pump flooding is required, is the pump spread specified? Will water quality/water testing be required Water treatment required? Level of filtration required? Water in front of first pig? Pigs Is the pig design accounting for the pipeline characteristic stated above? Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 55 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used APPENDIX A CHECKLIST FOR FLOODING, CLEANING AND GAUGING Item This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Project: Date: Y N Question Comments Is the pig material compatible with pipeline materials (including internal coatings)? Pigging directions (one way or bi-directional) Use of magnets? Number of pigs? Pig spacing established? Type of pigs to be used (brushes, bypass pigs, jetting pigs)? Gauge plate/location of damage/on each pig? Use of instrumented gauge plate (smart gauge)? Use of calliper gauging (uni-directional)? Operational conditions What are the necessary driving pressures for the pigging operations? What will the pig velocity be (based on available and/or necessary flow) Will pig tracking be required? Will a pig tracking vessel be required? Onshore launch/receiving? Offshore (topside) launch/receiving? Subsea launch/receiving? Any weather criteria limitations for the offshore operations? Use of hot stabs, design of hot stabs required? Hoses (type/handling)? Calliper/electronic pigs, transponder/pingerbattery life time? Remote start/sleep mode required? Use of isotope as tracking device? (strength, specialist personnel) May access be partial restricted due to other simultaneous operations, e.g. drilling rig? Acceptance criteria Acceptance criteria for flooding? Acceptance criteria for cleaning? Acceptance criteria for gauging? Contingency Has contingency operations been established in case anything goes wrong? Has a wet buckle contingency been established? Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 56 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used APPENDIX B CHECKLIST FOR SYSTEM PRESSURE TESTING B.1 Checklist for system pressure testing Project: Item Date: Ref. sec. Y N Comment Comment Definition of objective (to be performed prior to test execution) Application and [1.3] limitation The recommended practice applies for the current pipeline system Test objective The objective with the test is to check for gross errors and leakages (and not to document structural capacity) Waiving of system pressure test [4.1.4] Definition and documentation The system pressure test should be waived. (Special considerations should be made according to DNVGL-ST-F101) Definition and documentation of test objective is included in design documentation Planning and design (to be performed prior to test execution) Specification of [4.2.2] test The test should be performed as a subsea hydrostatic test after installation Battery limits and code break Battery limits and code break have been clearly established When to perform the system pressure test [4.2.1] When to perform the system pressure test is considered and planned Test medium [4.2.7.1] Applicable test medium for working environment is decided; the availability and special chemical considerations are reflected. Test pressure [4.2.3] The test pressure is calculated and meets the requirement in DNVGL-ST-F101 along the entire pipeline system. (Checklist in ?Appendix C may be used) Equipment and [4.2.3] instrumentation The equipment and instrumentation are fit for purpose and certified as required. The availability, number and location of equipment and instrumentation is considered HSE HSE issues such as location of equipment, test area, and personnel safety are considered and documented [6.1.2] Equipment and [4.2.6.4] instrumentation sensitivity Equipment sensitivity is according to recommended specifications Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 57 Item This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Project: Date: Ref. sec. Y N Comment Comment Calibration of [4.2.6.5] equipment and instrumentation The equipment have been calibrated according to the recommendations Acceptance criteria [4.3] The acceptance criteria are established prior to the test commences. Volume of test medium [4.2.8] The total amount of test medium required to pressurise the pipeline prior to testing to ensure that sufficient pump capacity and test medium is available Air content [4.2.7.2] The allowable air content and its influence on the safety and test results are considered Stabilisation period [4.2.10] The required stabilisation period is considered Hold period [4.2.4] The minimum required hold period is established. Confirmation [4.2.5] of pipeline leak tightness Confirmation of pipeline leak tightness is reflected Temperature corrections [4.3.1.1] Temperature corrections should be accounted for during the test. Temperature corrections [4.3.1.1] If temperature corrections should be considered: The requirements to temperature recordings and method for correction is established prior to test execution Tidal corrections [4.3.1.2] Tidal corrections should be considered (only relevant if the system pressure test is monitored from a floating vessel) Tidal corrections [4.3.1.2] If tidal corrections should be considered: The method for correction is established prior to test execution. Documentation Documentation of the planning activities (including relevant calculations) is included in official design documentation Execution Test initiation [4.2.7] All relevant aspects related to definition of test objective and planning (given above) are considered and documented. Testing may start. Pressurisation ratio [4.2.9] Pressurisation ratio is according to recommendations Monitoring [4.2.11] The test is continuously monitored during pressurisation, stabilisation and test hold periods Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 58 Date: Item Ref. sec. Data logging frequency [4.2.11] The data logging frequency is sufficient Visual inspection [4.2.11] For the purpose of a pure leak test, visual inspection is considered Y N Abnormal system response Depressurisation This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Project: Comment Comment Relevant abnormal system response is considered. The system pressure test shall be terminated if any abnormal system response is identified during testing [4.2.12] Applicable de-pressurization ratio is established Acceptance and final documentation Acceptance criteria [4.3] Final documentation Acceptance criteria are met and the test is considered successful Final documentation is prepared and contains all relevant information for traceability. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 59 C.1 Checklist for system test pressure calculation Project: Date: Step Description no. 1 Find the design pressure and its reference elevation, 2 Guidance note Value From design brief. , Find the incidental to design pressure ratio, From design brief. Calculate the incidental pressure (at reference level 4 5 ), Find the operational density of content, Determine the local incidental pressure, If the design pressure is defined at a low elevation, a low density will be conservative unless the test medium has a lower density than during operation. 'Local' pressure means that it is adjusted to the relevant elevation (at height 'h', positive upwards) with the column weight pressure. Note that the requirement, (DNVGL-ST-F101 Eq. 5.1) =.......... =.......... , only applies to the reference level, i.e. the difference between local design pressure and local incidental pressure is a fixed pressure, not a relative value. Determine the system test pressure = .......... =.......... . (DNVGL-ST-F101 Eq. 4.1) 6 =.......... .......... (DNVGL-ST-F101 Table 3-1) 3 Unit =.......... The required local system test pressure, , is times the local incidental pressure (typically 5% higher than the local incidental pressure) along the entire pipeline. Note that this is not the actual test pressure that you will get as you normally will have different densities in the test media and operational media. It is the minimum required value. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS =.......... =.......... Page 60 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used APPENDIX C CHECKLIST FOR SYSTEM TEST PRESSURE CALCULATION Date: Step Description no. 7 Guidance note Determine governing elevation and system test pressure, , (DNVGL-ST- F101 Sec.5) Value Unit To exceed the required test pressure along the whole pipeline, the system test pressure will be governed by the highest point in the tested system if the density ratio between system pressure test content and operation content is larger than . =.......... (=1.05, ref. DNVGL-ST-F101 Table 5-9) As the system pressure test content normally is water which normally has a significantly higher density than the operational content (i.e. larger than 1.05 times the operational content) this is often the case. In the rare case that the test medium has a density lower than 1.05 times the operational content density, the reference point for the system test pressure calculation will be the lowest point in the system. This will then typically apply to a water injection pipeline. 8 Calculate the local system test pressure based on the reference point, e.g. at pressure gauge (DNVGL-ST-F101, Eq. 4.2) From the local test pressure, calculated the test pressure at the elevation where the pressure is monitored. = .......... =.......... =.......... Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 61 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Project: Date: Step Description no. 9 Guidance note The pipeline pressure response as function of added volume mass may be calculated for an axially constrained pipeline according to, ref. Sec.7 /1/: Value Unit Establish the total volume of water required to perform the pressure test. For an non-axially-restrained where: 3 = [m ] initial pipeline volume = [m] pipeline (steel) outer diameter = [m] pipeline wall thickness = [-] Poisson ratio = [Pa] Young's modulus of steel pipe material = [Pa] test pressure = [Pa] initial pressure = [Pa] bulk modulus of test medium Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 62 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Project: Date: Step Description no. 10 Guidance note The following expressions may be used to correlate a (pinhole) theoretical size of a leak path with the recorded pressure decay rate. Defining the decay rate from the system pressure test in MPa as: Value Unit Establish theoretical pinhole size leak. Using the equations for a non-axially restrained pipe, the loss rate of test medium correlates with variation in test pressure at constant temperature according to, ref. Sec.7 /1/: where: = [Pa/hr] variation in pressure recorded 3 = [m /s] loss rate of test water = [Pa] bulk modulus of test medium = [m] pipeline outer diameter = [m] pipeline wall thickness (average if variable wall thickness) = [Pa] Young's Modulus = [-] Poisson ratio 10 The equivalent pinhole diameter can then be calculated according to: = ....... Where: = [Pa] Differential pressure across pipe wall during test taken as the average difference between internal test pressure an external pressure 3 = [m /s] loss rate of test water 3 = [kg/m ] density of test medium = [m] equivalent pinhole size = [-] discharge coefficient (typical value 0.6) Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 63 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Project: Date: Step Description no. 11 Guidance note For a pipeline that is free to expand both in axial and lateral direction the temperature correction of the system pressure test results may be estimated according to the following expression, ref /1/: Value Unit Establish temperature correction terms. = ....... Correspondingly, for a pipeline that is restrained axially the temperature correction of the system pressure test results may be calculated according to the following expression, ref /1/: In lieu of specific data the coefficients of volumetric expansion and bulk modulus of water can be found in ref. Sec.7 /1/. [1/°C] Coefficient of volumetric thermal expansion factor of test medium [1/°C] Coefficient of volumetric thermal expansion coefficient of pipe wall material 12 For a system pressure test monitored from a floating facility where the pressure at the vessel may vary due to variation in hydrostatic column, compensation for variation in tidal water may be allowed for according to the following correction: where: Establish tidal correction terms. = ....... = [Pa] variation in pressure recorded at vessel = [m] tidal variation @ location of test vessel/rig (positive for increasing WD) 3 = [kg/m ] density of test medium 2 = [m/s ] gravity 13 Any corrections performed to the pressure test data shall be limited to the medium that can actually be accounted for (i.e. volume of collected test medium, ). Establish correction terms for loss of test water. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS = ....... Page 64 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Project: This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used APPENDIX D CHECKLIST FOR DEWATERING, DRYING AND INERTING D.1 Checklist for dewatering, drying and inerting Project Item Pipeline system configuration Date Y N Question Comments Is the pipeline onshore or offshore? Are both ends accessible? Will there be need for vessel(s) to dewater? Is one flowing direction preferred? Is system start-up philosophy established and will it influence the pre-commissioning? Overall project schedule relevance? Is drying operation required after/in conjunction with dewatering? Pipeline characteristics Is it a one diameter or multi-diameter pipeline? (state minimum and maximum internal diameter) What is the minimum bend radii (and bend angles)? Are there any pipeline features and types: valves, Tees, wyes, branch connections, or dead legs that need special considerations regarding dewatering? Is the pipeline internally coated or not? Material quality, use of CRA? Flexible tails or flexible risers? Length of pipeline system, giving implications for drying technique selection? Discharge Is the discharge location chosen? Is a diffuser required Will permits to discharge be required? How will discharging be monitored? Handling of discoloured water/use of settling pond required? Analysis of discharged water required? Quality of discharged MEG batches, if any used during dewatering has to be monitored? MEG batches, if any used during dewatering can to be discharged to sea? Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 65 Item Pigs and pig receiver This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Project Date Y N Question Comments Pig and pig train designed according to the pipeline characteristics above? Pig tracking/pig tracking vessel required? Pig tracking by outlet water velocity measurement? Pig receiver design to accommodate use of hydrocarbon as propelling medium? Compressors Compressor package designed for the required dewatering pressured and flowrate to maintain the required dewatering velocity? Use of 'oil free' air? Dryer requirements established? Is any noise protection required, e.g. silencer for depressurization, noise from compressor station? Dew point measurements requirements established (2 different designs/make at each end)? Acceptance criteria Acceptance criteria are established Inerting Inerting by nitrogen required? Purity of nitrogen? Use of nitrogen slug (typ. 10%) or full volume (100%) to inert? Inerting as part of vacuum drying? Contingency Has contingency operations been established in case anything goes wrong? Has the reliability of gas supply been addressed? Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 66 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used Changes – historic CHANGES – HISTORIC There are currently no historical changes for this document. Recommended practice — DNVGL-RP-F115. Edition September 2019 Pre-commissioning of submarine pipelines DNV GL AS Page 67 This copy of the document is intended for use by Lee, Dan at McDermott Inc. only. Downloaded 2021-07-27. No further distribution shall be made. Requires a valid subscription to be used About DNV GL DNV GL is a global quality assurance and risk management company. Driven by our purpose of safeguarding life, property and the environment, we enable our customers to advance the safety and sustainability of their business. We provide classification, technical assurance, software and independent expert advisory services to the maritime, oil & gas, power and renewables industries. We also provide certification, supply chain and data management services to customers across a wide range of industries. Operating in more than 100 countries, our experts are dedicated to helping customers make the world safer, smarter and greener. SAFER, SMARTER, GREENER