Concrete Works Working Crew: Carpenter - 4 Mason - 4 Laborer – 12 DAILY LABOR COST = [4(600) + 4(600) + 12(500)] = ₱10,800/MD Structure: Footing Quantity: 0.432 m³ Difficulty Factor: 1.00 Construction Method: Mixing concrete with bagger mixer and placing Ideal Crew Daily Output: 6 m³ SOLUTION: 1 LABOR UNIT COST = ₱10,800/MD x 1.00 x 6 𝑚³ = ₱1,800 /m³ DURATION = 0.432 𝑚³ 6 𝑚³/𝑀𝐷 = 0.072 days Structure: Columns Quantity: 0.918 m³ Difficulty Factor: 1.15 Construction Method: Mixing concrete with bagger mixer and placing Ideal Crew Daily Output: 6.0 m³ SOLUTION: 1 LABOR UNIT COST = ₱10,800/MD x 1.15 x 6.0 𝑚³ = ₱2,070.00 /m³ DURATION = 0.918 𝑚³ 6 𝑚³/𝑀𝐷 = 0.153 days Structure: Beams Quantity: 17.31 m³ Difficulty Factor: 1.15 Construction Method: Mixing concrete with bagger mixer and placing Ideal Crew Daily Output: 6.0 m³ SOLUTION: 1 LABOR UNIT COST = ₱10,800/MD x 1.15 x 6 𝑚³ = ₱2,070.00 /m³ DURATION = 17.31 𝑚³ 6 𝑚³/𝑀𝐷 = 3 days Structure: Slab Quantity: 58.365 m³ Difficulty Factor: 1.20 Construction Method: Mixing concrete with bagger mixer and placing Ideal Crew Daily Output: 6 m³ SOLUTION: 1 LABOR UNIT COST = ₱10,800/MD x 1.20 x 6 𝑚³ = ₱2,160.00 /m³ DURATION = 58.365 𝑚³ 6 𝑚³/𝑀𝐷 = 10 days Structure: Stairs Quantity: 1.325 m³ Difficulty Factor: 1.25 Construction Method: Mixing concrete with bagger mixer and placing Ideal Crew Daily Output: 6.0 m³ SOLUTION: 1 LABOR UNIT COST = ₱10,800/MD x 1.25 x 6.0 𝑚³ = ₱2,250.00 /m³ DURATION = 1.325 𝑚³ 6.0 𝑚³/𝑀𝐷 = 0.221 days Structure: Septic Tank Quantity: 1.998 m³ Difficulty Factor: 1.15 Construction Method: Mixing concrete with bagger mixer and placing Ideal Crew Daily Output: 6.0 m³ SOLUTION: 1 LABOR UNIT COST = ₱10,800/MD x 1.15 x 6.0𝑚³ = ₱2,070.00 /m³ DURATION = 1.998 𝑚³ 6 𝑚³/𝑀𝐷 = 0.333 days TOTAL NUMBER OF DAYS: 13.80 DAYS = 14 MAN DAYS Project : 2-Storey Residential Building Item No. Description Quantity Unit : III : Structural Concrete : 80.348 : cu.m NAME AND SPECIFICATION QUANTITY UNIT UNIT RATE COST P M A T E R I A L S A. Portland Cement Washed Sand 1001 52.348 bags cu.m 235.00 1,365.00 235,235.00 71,455.02 Washed Gravel 104.639 cu.m 1,310.00 137,077.09 TOTAL DESIGNATION OF PERSONNEL L A B O R Carpenter Mason Laborer B. TOTAL 151,200.00 DESIGNATION OF PERSONNEL E Q U I P M E N T C. D. E. F. G. H. I. One bagger mixer Concrete Vibrator Minor Tools TOTAL TOTAL DIRECT COST (A+B+C) OCM PROFIT VAT Mob/Demob TOTAL COST (D+E+F+G+H) P NUMBER 4 4 12 No. of Days 14 14 14 Unit Rate 600.00 600.00 500.00 443,767.11 COST 33,600.00 33,600.00 84,000.00 P NUMBER No. of Days 1 1 14 14 Unit Rate COST 1,350.00 725.00 18,900.00 10,150.00 2,543.00 P P 31,593.00 626,560.11 93,984.02 62,656.01 39,160.01 6,265.60 828,625.75 J. UNIT COST 10,312.96