JOB HAZARD ANALYSIS
Company: R2L PROJECT AND CONSULTANCY SERVICES
Project: TAPA KING AYALA MALLS VERMOSA
Given by: J U L I E T C A N S U L O
Date: JA N UA R Y 1 0 , 2 0 2 4
ACTIVITY
1. Toolbox meeting,
mobilization,
demobilization
2. Preparation of tools,
equipment and materials
3. Concrete chipping, frame
works,concreting (CHB
Laying, plumbing works, layout and restoration)
HAZARD
RISK
miscommunication
Physical injury
a) Defective tools equipment and
materials including unguarded power
tools.
a) Unsafe behavior for
digging
b) Misuse of tools
c) Scattered materials
a) Hand and foot injury.
b) Back pain (ergonomics)
c) Slip, trip and fall
a) Hand injury risk
b) Dust Inhalation/eye
irritation
c) Slipping and tripping
CONTROL
a) Secure work permit prior to
start activities.
b) work area assessment.
c) Conduct toolbox meeting
and discussed daily
activities and task.
d) d) Coordination with other
contractors.
)
Conduct
daily inspection of
a
tools, equipment and materials
prior to start the activities.
b) All moving parts of power
tools shall be securely guarded.
c) Use safety gloves and safety
shoes.
d) Applied proper lifting
techniques.
e) Buddy-buddy system
f) Conduct proper 5s
g) Make sure unused tools,
equipment and materials are
secured barricade.
a) Right kind of tool/PPE for
the job must be
implemented.
b) Adequate supervision for
employees while at work.
c) Buddy-buddy system
d) Maintain clean, smooth
4. Hot works and cutting
(mechanical works)
5. Drilling (ceiling works,
carpentry, masonry)
6. Use of defective/damaged
ladder
a) Electrocution
b) Inexperienced personnel
c) Fire Hazards
Smoke, toxic inhalation
a) Struck by flying object
b) Inhalation of dust
c) scattered materials
a) Eye irritation
b) Cardio infection
c) Slip, trip,
a) Use of defective/damaged
ladder
a) Fall of person/collapse of
ladder
walking and working
surface.
e) Clean up slippery
materials.
a) All equipment shall be
turned off when not in
use.
b) Use panel/Extension and
breaker
c) Personnel working with
power tools,equipment
Personnel working with
power tools,equipment
protection
d) 1.1 Combustibles around
the work area shall be
removed/protected.
1.2 Portable fire extinguisher
shall be available.
1.3 Provide warning sign for
every hot works
a) Use face shield and
spectacles
b) Provide and install
protective covering
c) Conduct proper 5s
a) Ensure that all parts of the
ladder are in good
condition.
b) Ensure that ladder is
properly setup.
c) One personnel will hold the
ladder below to support stability
of the ladder.
d) Use full body harness and
hook the lanyard on an
anchorage if needed.
e) Place and set-up ladder on a
stable and level ground.
f) Always maintain three point
contact on the ladder when
7. Painting works
8. Use of temporary power
supply
a) Health hazard
b)Improper/unsafe practices for
storing materials
c) Fire hazards
a) Unskilled electricians
b) b) Unauthorized shutdown/
power interruption of service
c) ) Energized lines
d) Unsorted materials
a) 1.1 Inhalation of dust
1.2 harm to skin and eye
b) Slipped caused by spilled
materials
-Electrocution/injury
- Equipment Damage
- Pilferage
- Excess materials and waste
-ripping Hazard
climbing, working and going
down.
g) Ladder must not have lose
steps/rungs and no worn out
parts.
h) Do not over extend when
working on ladder.
i) Set up ladder away from
access area.
a) Used proper PPE during
application
1.1 Quick removal of spilled
materials
1.2 Wash thoroughly before
eating and at the end of the day
b) Paints shall be stored in a well
ventilated flammable storage.
c) No painting should be carried
out nearby hot works activity.
A)Temporary electrical
installation shall be done only
certified electricians.
b) Coordination from the client
shall be obtained prior to any
shutdown during power tapping
and isolation.
C) Temporary wiring shall be
protected from possible damage
and cuts.
d) Ensure wire and cables are
properly spliced.
e) Injury fatality and equipment
damage shall be reported to the
client
F)All extension cords and
temporsry power supply shall be
protected by breakers.
G) Flammable materials shall be
segregate from non-flammable
materials
Prepared By:
Juliet Cansulo
Safety Officer
H) Make sure all unnecessary
materials will be pull out of work
area and placed to designated
area.
I) Maintain pathways free from
any obstacle.
J) Errect barricades/flagging
around from the unsecure and
unused materials from the work
areas.