Industry Learnings on Burner Boom Related Structures Erick Dubis (Completions Engineer) May 2011 Atwood Eagle King Post Structure Safety Issue DRIMS #5223563 Abstract The following presentation shows how industry and internal learnings related to burner boom installation have influenced positively in Woodside. The events describe how a few changes to a design, though potentially insignificant if looked in isolation, when combined could lead to exceeding the design safety factors or structural failure. The slides also describe how Woodside’s and contractors internal process prevented an escalation of the event, and some improvements that have been made to the processes since the events occurred. King Post Structure Safety Issue DRIMS #5223563 Slide 2 Standard King Post Boom Rig-up Water Nozzle King post Burner Head Pedestal King Post Structure Safety Issue DRIMS #5223563 Slide 3 Background Background: • Rig and testing contractors confirmed that the same 85ft burner booms have been safely used before on the same rig. • Certified documentation was provided on the king post structure that supports the burner boom. • Burner booms were safely installed. • Investigation results from another operator, related to a burner boom collapse, and an additional modification required to the decks, drove the team to revisit burner boom and rig documentation. • A quick verification of the structures suitability was conducted by an engineering firm to asses the impact of the new required modifications. • Some inconsistencies were found in the rig structures and the burner boom weights. King Post Structure Safety Issue DRIMS #5223563 Slide 4 Background • A full investigation/verification by an external specialist was conducted, this involved physical verification of the structures in place against certified drawings. • Calculations showed the structures were overstressed, not only for the required modifications, but overstressed by the burner booms already in place. The investigation and calculations revealed: • Inconsistencies with the rig drawings and physical structures. • Inconsistencies with the testing contractors actual booms weights and weights assumed in the existing drawings and calculations. • Some structures were severely overstressed and close to failure. King Post Structure Safety Issue DRIMS #5223563 Slide 5 Snowball Effect Water Nozzle Burner Head Additional 300kg Additional 400kg Pedestal 1m higher King Post Structure Safety Issue DRIMS #5223563 Slide 6 Consequence One of the pedestals bent and tore its bracing King Post Structure Safety Issue DRIMS #5223563 Slide 7 Inadequate MOC Snowball Effect Causes: • Inadequate MOC in place for the additional weight on the boom: • Improvements to the burner head and added approximately 400kg. • New the water nozzle added 300kg. • Inadequate MOC in place by for the structural changes: • Burner boom pedestal was 1m higher than the certified drawings . • Rig drawings had inconsistencies with actual structures regarding positioning and reenforcements. • No standardized verification process. An additional weight of ~ 700 kg and a taller pedestal created a bending moment that pushed the structures close to failure. King Post Structure Safety Issue DRIMS #5223563 Slide 8 Swiss Cheese Barrier Model Rig Contractor Testing Contractor Woodside Built in Safety Factors King Post Structure Safety Issue DRIMS #5223563 Slide 9 Actions Taken Actions taken for mitigation and prevention: Mitigations • Burner booms were placed in a safe position to avoid structure overload. • Structures were strengthen to withstand the loads. • Pedestal was repaired and extra bracing was placed. Future Preventions • Lesson learnt were captured. • An independent structural study is now performed in Woodside as part of the QA/QC process before installing the burner booms. King Post Structure Safety Issue DRIMS #5223563 Slide 10 What was Prevented? King Post Structure Safety Issue DRIMS #5223563 Slide 11