CIVE 422: Construction Methods and Safety Management Chapter 5: Managing Costs & Profits Hiam Khoury Construction Engineering and Management Civil and Environmental Engineering 2 Example 3 Income Chart 4 Income Chart (cont’d) 5 Breakeven Chart (cont’d) 6 7 8 9 Indirect Costs & Construction • Indirect costs are not directly related to quantity of construction performed BUT different quantities require diff. levels of support Size of support organization+ G&A depend on amount of construction realized 10 Markup & Market • Obvious relationship between markup and competitive position in the market • If M increases, competitive position may decrease limits the construction volume and impacts income •May even be impossible to find a markup that can generate a construction volume that will allow a contractor to breakeven or make an attractive profit •You may want to adjust the financial mix by changing prices, reducing construction costs or reducing general overhead •Use competitor’s historical markups to aid in setting your profit and overhead markup 11 Earned Value • Measures performance at a certain data date with regards to – Schedule – Cost • Ignores items which do not have a cost – For example, submittals • BAC, BCWS, BCWP, ACWP, SV, CV, SPI, CPI, EAC, etc. 12 Budgeted Cost at Completion (BAC) • The total budget of the project 13 Budgeted Cost of Work Scheduled (BCWS) • The expected cost of the work that is scheduled to be performed during a specific period of time 14 Budgeted Cost of Work Performed (BCWP) • The expected cost of the work that is actually performed during a specific period of time 15 Actual Cost of Work Performed (ACWP) • The actual cost of the work that is performed during a specific period of time • Hard to calculate in a timely matter because of lag in receiving and processing invoices 16 Other Earned Value Metrics SV: Schedule Variance, BCWP–BCWS (SV >0: ahead of schedule, SV<0:behind schedule) CV: Cost Variance, BCWP–ACWP (CV>0:under budget, CV<0:over budget) %SV: % Schedule Variance, 100*SV/BCWS %CV: % Cost Variance, 100*CV/BCWP SPI: Schedule Performance Index, BCWP/BCWS (SPI > ahead of schedule, SPI <1: behind of schedule) CPI: Cost Performance Index, BCWP/ACWP (CPI >1:under budget, CPI <1:over budget) EAC = ACWP+(BAC-BCWP) OR EAC=BAC/CPI 17 SPI/CPI Target levels 18 Earned Value & S-Curves 19 Earned Value & S-Curves (cont’d) 20 Earned Value & S-Curves (cont’d) 21 Earned Value- Example A project has been defined that consists of 12 activities (each requires one month to complete) for which the estimated costs and durations have been defined 22 Earned Value- Example (cont’d) 23 Earned Value Concept (cont’d) 24 QUESTIONS? 25