TECHNICAL S GL ND001TANDARDS COMMITTEE GENERAL GUIDELINES FOR MARINE PROJECTS .. GL 0001/ND This document has been replaced by the standard DNVGL-ST-N001 which may be accessed through https://my.dnvgl.com/ This document may still be valid for some existing projects. This Guideline was updated as part of the first stage of the harmonisation between the GL Noble Denton and DNV heritage marine services requirements. Refer also to DNVGL-SE-0080 Noble Denton marine services – Marine Warranty Survey for further details. All references to GL Noble Denton apply to the legal entity trading under the DNV GL or GL Noble Denton name which is contracted to carry out the scope of work and issues a Certificate of Approval, or provides a marine related advisory or assurance service. Once downloaded this document becomes UNCONTROLLED. 28 Jun 16 1.1 RLJ Replaced by DNVGL-ST-N001 14 Dec 15 1 RLJ Technical Standards Committee 22 Jun 13 0 RLJ Technical Policy Board Date Revision Prepared by Authorised by http://www.dnvgl.com/ GENERAL GUIDELINES FOR MARINE PROJECTS PREFACE This document has been drawn with care to address what are considered to be the primary issues in relation to the contents based on the experience of the GL Noble Denton Group of Companies (“the Group”). This should not, however, be taken to mean that this document deals comprehensively with all of the issues which will need to be addressed or even, where a particular matter is addressed, that this document sets out a definitive view for all situations. In using this document, it should be treated as giving guidelines for sound and prudent practice, but guidelines must be reviewed in each particular case by the responsible organisation in each project to ensure that the particular circumstances of that project are addressed in a way which is adequate and appropriate to ensure that the overall guidance given is sound and comprehensive. Reasonable precaution has been taken in the preparation of this document to seek to ensure that the content is correct and error free. However, no company in the Group shall be liable for any loss or damage incurred resulting from the use of the information contained herein or shall voluntarily assume a responsibility in tort to any party or shall owe a duty of care to any party other than to its contracting customer entity (subject always to the terms of contract between such Group company and subcontracting customer entity). This document must be read in its entirety and is subject to any assumptions and qualifications expressed therein as well as in any other relevant communications by the Group in connection with it. Elements of this document contain detailed technical data which is intended for analysis only by persons possessing requisite expertise in its subject matter. © 2015 Noble Denton Group Limited. The content of this document is the copyright of Noble Denton Group Limited. All rights reserved. Any reproduction in other material must have written permission. Extracts may be reproduced provided that their origin is clearly referenced. 0001/ND Rev 1 Page 2 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS CONTENTS SECTION 1 SUMMARY 2 INTRODUCTION 3 DEFINITIONS 4 THE APPROVAL PROCESS 5 HEALTH, SAFETY AND ENVIRONMENT 5.1 Introduction 5.2 Jurisdiction 5.3 Responsibilities 5.4 Risk Management 5.5 Qualification and Training 5.6 Safety Plan 5.7 Contingency and Emergency Planning and Procedures 5.8 Security and Tracking System 6 ORGANISATION, PLANNING AND DOCUMENTATION 6.1 Introduction 6.2 Organisation and Communication 6.3 Quality Assurance and Administrative Procedures 6.4 Technical Procedures 6.5 Technical Documentation 6.6 Documentation and Certification 7 METOCEAN CRITERIA & FORECASTS 7.1 Introduction 7.2 Design Environmental Condition and Operational Criteria 7.3 Unrestricted Operations 7.4 Weather Restricted Operations 7.5 Benign Weather Areas 8 WEIGHT CONTROL 8.1 Introduction 8.2 Weight Considerations 8.3 Centre of Gravity factors 8.4 Weight Control 8.5 Weighing 8.6 Weight and Buoyancy Control 9 STRUCTURAL STRENGTH 9.1 General 9.2 Structural Steel 9.3 Fillet welds 9.4 Doubler Plates 9.5 Bolted Connections for seafastenings 9.6 Light-weight Metallic and Composite Structures 9.7 Structural Concrete 9.8 Compressed Air 9.9 Documentation Requirements for Lifting, Towing & Mooring Gear 10 BUILDING / CONSTRUCTION BASIN 11 TOW-OUT FROM DRY-DOCK / BUILDING BASIN 11.1 Mooring and handling lines 11.2 Under-keel clearance for leaving basin 11.3 Side Clearances 11.4 Under-keel Clearance Outside Basin 11.5 Towage and marine considerations 0001/ND Rev 1 PAGE NO. 5 6 7 12 13 13 13 13 13 13 14 14 14 15 15 15 15 16 16 18 21 21 21 21 24 29 31 31 31 32 32 32 33 34 34 34 35 35 35 35 35 36 36 39 40 40 40 40 40 40 Page 3 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS 12 TEMPORARY BALLASTING AND COMPRESSED AIR SYSTEMS 12.1 General 12.2 Redundancy 12.3 Inlets and Outlets 12.4 Pipework 12.5 Umbilicals 13 USE OF DP VESSELS 13.1 Background 13.2 DP Equipment Classes 13.3 System Design & Capability 13.4 DP2 or DP3 Class 13.5 Operational Requirements 13.6 Vessel Clearances 13.7 Jack-Ups 13.8 Information Required for Approval 14 DECOMMISSIONING 14.1 General REFERENCES APPENDIX A - FILLET WELD STRESS CHECKING APPENDIX B - BOLTED CONNECTIONS 41 41 41 41 41 41 42 42 43 44 44 44 45 46 46 47 47 48 50 54 TABLES Table 6-1 Table 7-1 Table 7-2 Table 7-3 Table 7-4 Table 7-5 Table 7-6 Table 7-7 Table 7-8 Table 7-9 Table 7-10 Table 9-1 Table 9-2 Table 13-1 Table 13-2 Table B-1 Table B-2 Table B-3 Principal Vessel Documentation Metocean return periods – unrestricted operations Value of JONSWAP γ, ratio of Tp:Tz and Tp:T1 for each integer value of K Forecast Requirement Classes Alpha Factors for Waves - Forecast Requirement C (Low Sensitivity) Alpha Factors for Waves - Forecast Requirement B2 (Moderate Sensitivity) Alpha Factors for Waves - Forecast Requirement B1 (Moderate Sensitivity) Alpha Factors for Waves - Forecast Requirement A2 (High Sensitivity) Alpha Factors for Waves - Forecast Requirement A1 (High Sensitivity) Alpha Factors - Wind (all Forecast Requirements) Northern & Southern Boundaries of Benign Weather Areas by Month Load Factors for use with AISC 14th Edition Documentation Requirements for Lifting, Towing & Mooring Gear DP Equipment Classes DP Class Notations for various Classification Societies Resistance Factor by Hole Type Slip Coefficients Filler Plate Factors 18 22 23 27 27 28 28 28 28 28 29 34 37 43 43 55 55 56 FIGURES Figure 6-1 Figure 7-1 Figure 7-2 Example of document organogram Operation Periods Map Showing Benign Weather Areas 17 25 30 Figure A-1 Figure A-2 Figure A-3 Figure A-4 Effective Throat Dimension ‘a’ for Concave and Convex Fillet Welds Normal and Shear Stresses acting on the plane of Weld Throat Bracket connected by double Fillet Weld Stresses and Forces acting on Fillet Weld 50 50 51 52 0001/ND Rev 1 Page 4 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS 1 SUMMARY 1.1 These guidelines have been developed by GL Noble Denton to present material that is common to more than one of the other GL Noble Denton guidelines for the approval of marine projects. They include: The approval process for marine warranty Health Safety and Environment Organisation, planning and documentation Metocean criteria (design and operating) and forecasts Weight control Structural strength Building /construction basins Tow-out from dry-dock /building basin Temporary ballasting & compressed air systems Use of Dynamic Positioning (DP) vessels Decommissioning of platforms and topsides. 1.2 1.3 1 Updates from Rev 0 are described in Section 2.6. 0001/ND Rev 1 Page 5 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS 2 INTRODUCTION 2.1 This document is a prime reference for the specific guidelines developed by GL Noble Denton for application to marine projects, listed in Section 2.3. It contains items that were previously duplicated in more than one guideline. The specific Guidelines are intended to lead to an approval by GL Noble Denton. Such approval does not imply that compliance with national codes and legislation, or the requirements of other regulatory bodies, harbour authorities and/or any other parties would be given. This report should be read in conjunction with the specific GL Noble Denton Guideline documents, particularly: a. DNVGL-SE-0080 “Noble Denton marine services – Marine Warranty Survey”, Ref. [15] b. 0009/ND “Guidelines for Elevated Operations of Jack-Ups”, Ref. [1] c. 0013/ND “Guidelines for Load-Outs”, Ref. [2] d. 0015/ND “Guidelines for Concrete Gravity Structure Construction & Installation”, Ref. [3] e. 0016/ND “Seabed and Sub-seabed data required for approvals of Mobile Offshore Units (MOUs)”, Ref. [4] f. 0021/ND “Guidelines for the Approval of Towing Vessels”, Ref. [5] g. 0027/ND “Guidelines for Marine Lifting & Lowering Operations”, Ref. [6] h. 0028/ND “Guidelines for Steel Jacket Transportation & Installation”, Ref. [7] i. 0029/ND “Guidelines for Submarine Pipeline Installation”, Ref. [8] j. 0030/ND “Guidelines for Marine Transportations”, Ref. [9] k. 0031/ND “Guidelines for Float-Over Installations /Removals” , Ref. [10] l. 0032/ND “Guidelines for Moorings”, Ref. [11]. m. 0035/ND “Guidelines for Offshore Wind Farm Infrastructure Installation”, Ref. [12]. 2.2 2.3 2.4 2.5 2.6 Electronic versions of GL Noble Denton Guidelines are available on: https://www.dnvgl.com/rules-standards/noble-denton-maa-rules-and-guidelines.html Care should be taken when referring to any GL Noble Denton Guideline document that the latest revision is being consulted. Designers and installers of innovative designs or installation methods are recommended to discuss the procedures and design with the relevant GL Noble Denton office at an early stage of the project to ensure that it will be approvable without changes. This Revision 1 supersedes Revision 0 of 22 June 2013, and the main changes, marked with a line in the right hand margin, include: a. b. c. d. e. f. g. h. i. 2.7 Definitions updated in Section 3 The Approval Process in Section 4 is relocated to DNVGL-SE-0080 Changes to the requirements for metocean criteria and forecasts in Section 7. These include, clarifications to the use of seasonal data, updated return periods for unrestricted operations, changes in Alpha Factor (previously Metocean Reduction Factor), updated/added operational duration and reference periods, weather forecasting and associated parameters Clarification of weight contingency factors and CoG envelopes in Section 8 LRFD Option title refined in Table 9-1 Comparison of certification requirements for lifting, towing & mooring gear in Section 9.9 Clarification for channel widths in Section 11.3 Additional items for ballast or air systems cleanliness in Section 12.3.2 Updates for the use of DP in Section 13. Please contact the Technical Standards Committee Secretary at TSC@dnvgl.com with any queries or feedback. 0001/ND Rev 1 Page 6 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS 3 DEFINITIONS 3.1 Referenced definitions are underlined. 0001/ND Rev 1 Term or Acronym Definition 50/50 weight estimate The value representing the median value in the probability distribution of weight AISC American Institute of Steel Construction Alpha Factor The maximum ratio of operational criteria / design environmental condition to allow for weather forecasting inaccuracies. See Section 7.4.8. Approval The act, by the designated GL Noble Denton representative, of issuing a Certificate of Approval. ASD Allowable Stress Design (effectively the same as WSD) ASOG Activity Specific Operations Guidelines (for DP – See Section 13.5.1 k) Assured The Assured is the person who has been insured by some insurance company, or underwriter, against losses or perils mentioned in the policy of insurance. Barge A non-propelled vessel commonly used to carry cargo or equipment. (For the purposes of this document, the term Barge can be considered to include Pontoon, Ship or Vessel where appropriate). Benign (weather) area An area with benign weather as described in Section 7.5 BL / Breaking Load Certified minimum breaking load of wire rope, chain or shackles. CAMO Critical Activity Mode of Operation (for DP – See Section 13.5.1 k) Certificate of Approval A formal document issued by GL Noble Denton stating that, in its judgement and opinion, all reasonable checks, preparations and precautions have been taken to keep risks within acceptable limits, and an operation may proceed. Client The company to which GL Noble Denton is contracted to perform marine warranty or consultancy activities. Classification A system of ensuring ships are built and maintained in accordance with the Rules of a particular Classification Society. Although not an absolute legal requirement, the advantages (especially as regards insurance) mean that almost all vessels are maintained in Class. Competent person Someone who has sufficient training and experience or knowledge and other qualities that allow them to assist you properly. The level of competence required will depend on the complexity of the situation and the particular help required. Design environmental condition The design wave height, wind speed, current and other relevant environmental conditions specified for the design of a particular transportation or operation. DP Dynamic Positioning or Dynamically Positioned EPC Engineering, Procurement and Construction Page 7 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS Term or Acronym Definition FMEA or FMECA Failure Modes and Effects Analysis or Failure Modes, Effects and Criticality Analysis GL Noble Denton The legal entity trading under the DNV GL or GL Noble Denton name which is contracted to carry out the scope of work and issues a Certificate of Approval, or provides a marine related advisory or assurance service. HAZID Hazard Identification Study HAZOP Hazard and Operability Study HIRA Hazard Identification Risk Assessment IACS International Association of Classification Societies IMO / International Maritime Organization The United Nations specialized agency with responsibility for the safety and security of shipping and the prevention of marine pollution by ships Insurance Warranty A clause in the insurance policy for a particular venture, requiring the approval of a marine operation by a specified independent survey house. ISM / International Safety Management. The ISM Code provides an International standard for the safe management and operation of ships and for pollution prevention. JSA Job Safety Analysis Load-in The transfer of a major assembly or a module from a barge, e.g. by horizontal movement or by lifting. Load-out The transfer of a major assembly or a module from land onto a barge by horizontal movement or by lifting LRFD Load and Resistance Factor Design LS1 / Limit State 1 A design condition where the loading is gravity dominated; also used when the exclusions of Section 9.2.5 apply. LS2 / Limit State 2 A design condition where the loading is dominated by environmental / storm loads, e.g. at the 10- or 50-year return period level or, for weather-restricted operations, where an Alpha Factor according to Section 7.4.8 is to be applied. Marine Operation Generic term covering, but not limited to, the following activities which are subject to the hazards of the marine environment: Load-out / load-in Transportation / towage Lift / Lowering (offshore / inshore) Tow-out / tow-in Float-over / float-off Jacket launch / jacket upend Pipeline installation Construction afloat MARPOL 0001/ND Rev 1 International Convention for the Prevention of Pollution from Ships 1973/78, as amended. Page 8 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS 0001/ND Rev 1 Term or Acronym Definition MBL / Minimum Breaking Load The minimum allowable value of breaking load for a particular sling, grommet, wire or chain etc. MODU See MOU MOU / Mobile Offshore Unit For the purposes of this document, the term may include Mobile Offshore Drilling Units (MODUs), and non-drilling mobile units such as accommodation, construction, lifting or production units including those used in the offshore renewables sector. MWS Marine Warranty Surveyor (see Section 4) NDT / Non Destructive Testing Ultrasonic scanning, magnetic particle inspection, eddy current inspection or radiographic imaging or similar. May include visual inspection. NMD Norwegian Maritime Directorate Operational Criteria The metocean limits used when assessing weather forecasts to determine the acceptability of proceeding with (each phase of) an operation beyond the next Point of No Return. For a weather restricted operation / tow / transportation these equal the design environmental condition multiplied by an alpha factor. Operation Duration The planned duration of the operation from the forecast prior to either the operation start or Point of No Return, as appropriate, to a condition when the operations /structures can safely withstand a seasonal design storm (also termed “safe to safe” duration); this excludes the contingency period. Operational Reference Period The Operation Duration, plus the contingency period Platform The completed steel or concrete structure complete with topsides PNR / Point of No Return The last point in time, or a geographical point along a route, at which an operation could be aborted and returned to a safe condition. QRA Quantified Risk Analysis RCS / Recognized Classification Society Member IACS with recognized and relevant competence and experience in specialised vessels or structures, and with established rules and procedures for classification / certification of such vessels /structures under consideration. Reduced exposure operation /towage /transportation A weather-unrestricted operation which has an exposure sufficiently short (typically under 30 days) for the design extremes to be reduced. Applicable only to towages or transportations, See Section 7.3.2.4 and Section 6.5 of 0030/ND, Ref. [9]. Restricted operation See Weather-restricted operation. SOLAS International Convention for the Safety Of Life At Sea. An international treaty concerning the safety of merchant and other ships and MOUs. Page 9 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS Term or Acronym Definition Staged tow or transportation A weather restricted tow or transportation in which there is a commitment to seek shelter (or jack up at a standby location) on receipt of a weather forecast in excess of the operational criteria. This relies on there being sufficient suitable ports of shelter (or standby locations) along the route. It can proceed in stages between shelter points, not leaving or passing each shelter point unless there is a suitable weather forecast for the next stage. Each stage may, subject to certain safeguards, be considered a weather restricted operation. Statement of Acceptability See Section 4 Structure The object to be transported and installed, or a sub-assembly, component or module. Survey Attendance and inspection by a GL Noble Denton representative. Other surveys which may be required for a marine operation, including suitability, dimensional, structural, navigational, and Class surveys. Surveyor The GL Noble Denton representative carrying out a ‘Survey’. An employee of a contractor or Classification Society performing, for instance, a suitability, dimensional, structural, navigational or Class survey. SWL SWL is a derated value of WLL, following an assessment by a competent person of the maximum static load the item can sustain under the conditions in which the item is being used. Transportation The operation of transporting a tow or a cargo by a towage or a voyage. TRN / Technical Review Note Notes issued by the MWS in which MWS questions and comments are recorded for installation contractor action. Vessel A marine craft designed for the purpose of transportation by sea or construction activities offshore. See Barge Weather restricted tow or transportation A towage or transportation for which the strength or stability will not meet the unrestricted environmental criteria (typically 10 year return). It can either be weather-routed or staged depending on the sea room and sheltered port availability. Weather routed tow or transportation A weather restricted tow or transportation in which a weather forecasting organisation advises the relevant captain on the best route to avoid weather exceeding the Operational Criteria. This relies on there being adequate sea room and vessel speed to avoid bad weather. Weather routing may also be used for non-weather restricted voyages to reduce fuel costs or voyage time. Weather restricted operation 0001/ND Rev 1 A marine operation which can be completed within the limits of an operational reference period with a weather forecast not exceeding the operational criteria. The operational reference period (which includes contingencies) is generally less than 72 hours. The design environmental condition need not reflect the statistical extremes for the area and season. An alpha factor shall be accounted for in defining the design environmental condition (see Section 7.4.8). Page 10 of 57 1 1 GENERAL GUIDELINES FOR MARINE PROJECTS 0001/ND Rev 1 Term or Acronym Definition Weather unrestricted operation An operation with an operational reference period greater than the reliable limits of a weather forecast. The operational reference period (which includes contingencies) is generally more than 72 hours. The design weather conditions must reflect the statistical extremes for the area and season. The design weather is defined in Section 7.3. WLL / Working Load Limit The maximum force which a product is authorized to sustain in general service when the rigging and connection arrangements are in accordance with the design. See SWL. WSD Working Stress Design (effectively the same as ASD) Page 11 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS 4 THE APPROVAL PROCESS 4.1 The approval process is described in DNVGL-SE-0080 - Noble Denton marine service – Marine Warranty Survey, Ref [15]. Additional details for specific objects and operations are given in the relevant Guidelines (see references [1] to [12]). 0001/ND Rev 1 Page 12 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS 5 HEALTH, SAFETY AND ENVIRONMENT 5.1 INTRODUCTION 5.1.1 This Section contains general guidelines on safety and emergency issues. This subject must be managed by the client or his nominated contractor in accordance with local jurisdiction, as well as appropriate guidelines and specifications regarding health, safety and the environment (HSE). GL Noble Denton’s Scope of Work includes HSE issues only where explicitly stated. 5.2 JURISDICTION 5.2.1 In addition to Approval by GL Noble Denton, construction and marine operations will be subject to national and international regulations and standards on personnel safety and protection of the environment. It should also be noted that a marine operation can involve more than one nation’s area of jurisdiction, and that for barges and vessels the jurisdiction of the flag state will apply. 5.3 RESPONSIBILITIES 5.3.1 The owner of the structure will have the overall responsibility for planning and execution of the construction and marine operations, and hence also the safety of personnel, facilities and environment. The owner may delegate the execution and follow-up of these issues to a nominated third party such as an EPC-contractor. If a part of the marine operations is to be carried out near other facilities or their surroundings, safety zones shall be defined by the owner. 5.3.2 5.4 RISK MANAGEMENT 5.4.1 Risk management should be applied to the project to reduce the effects of hazards and to limit the overall risk. The preferred approach is achieved by addressing the following functions: a. Identification of potential hazards b. Preventative measures to avoid hazards wherever possible c. Controls to reduce the potential consequences of unavoidable hazards d. Mitigation to reduce the impact of risk, should hazards occur. 5.4.2 Each major marine operation should be subject to detailed hazard studies. Those taking part should include the personnel and organisations involved in the design of structures and systems, as well as those involved in the marine operation. Each major system essential to the performance and safety of marine operations including, for example, the power generation and the ballast and compressed air systems should be subjected to a rigorous study. A variety of techniques including HAZID, HAZOP, FMECA, HIRA, JSA and Tool Box Talks may be used as appropriate to monitor and control such hazards and to model their potential effects. QRA techniques may be used to compute the particular level of risk applicable to any operation, to compare levels of risk between alternative proposals or between known and novel methods, and to enable rational choices to be made between alternatives. Ideally, each of the various studies outlined above should be managed by a competent independent person familiar with the overall concept, but outside the team carrying out the relevant system or structure design or operational management. It is good practice that no major activity is carried out on a site without an approved Method Statement, and that the Risk Assessment process is part of that approval procedure, and that the Risk Assessment itself forms an appendix to the Method Statement. 5.4.3 5.4.4 5.4.5 5.4.6 5.4.7 5.5 QUALIFICATION AND TRAINING 5.5.1 Operation supervisors shall possess thorough knowledge and have experience from similar operations. Other key personnel shall have knowledge and experience within their area of responsibility. Before the start of an operation, all personnel involved shall be briefed by the supervisors regarding responsibilities, communication, safety, and step by step procedures and tasks. 0001/ND Rev 1 Page 13 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS 5.5.2 5.5.3 5.5.4 Adequate training appropriate to each individual’s function and situation should be given, including job training, site safety training and briefings, marine safety and survival training. A qualification matrix is recommended for correct tracking and control of personal qualifications. Computer simulation and training, and/or model tests can give valuable information for the personnel carrying out the operation. 5.6 SAFETY PLAN 5.6.1 A safety plan shall be included in the procedure manual for each operation. This plan consists of the safety rules that apply to minimise the following risks encountered during each operation: a. Risks inherent from the metocean conditions b. Risks incurred by construction, transportation, installation and commissioning activities c. Risks to the environment d. Risks due to simultaneous operations (SIMOPS) – see IMCA, Ref. [26] e. Risks due to working on live assets, etc. 5.7 CONTINGENCY AND EMERGENCY PLANNING AND PROCEDURES 5.7.1 Each operation is considered to progress from a condition of security to another condition of security. Contingency planning is required so that, in the event that an operation cannot be completed in the time and manner intended, an alternative condition of security can be achieved. Contingency and emergency planning should form part of the operational procedures. Plans should be developed for all foreseeable emergencies, which can include: a. Severe weather b. Planned precautionary action in the event of forecast severe weather c. Structural parameters approaching pre-set limits d. Stability parameters approaching pre-set limits e. Failure of mechanical, electrical or control systems f. Fire g. Collision h. Leakage i. Pollution j. Structural failure k. Mooring failure l. Human error m. Man overboard n. Personnel accidents or medical emergencies o. Terrorism and sabotage. 5.7.2 5.7.3 5.7.4 The procedures should detail alarm signals, reporting, communication, organisation and required equipment such as escape routes, personnel rescue means and fire- fighting equipment. Fire and evacuation alarms should be periodically tested, and drills should carried out periodically, or as required by safety legislation. 5.8 SECURITY AND TRACKING SYSTEM 5.8.1 Where necessary, a suitable security and tracking system should be in use to record personnel on the structure or vessels, to track their whereabouts, and if required, to restrict access to certain areas to authorised personnel only. The contractor is responsible for accident reporting to the owner and regulatory bodies. Any incidents, accidents or near-misses relevant to the safety of the structure or future marine operations shall also be reported to GL Noble Denton. 5.8.2 0001/ND Rev 1 Page 14 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS 6 ORGANISATION, PLANNING AND DOCUMENTATION 6.1 INTRODUCTION 6.1.1 This Section suggests the requirements for the organisation and documentation systems that should be set up for the performance of marine operations to allow the Marine Warranty Surveyor to approve them in a timely and economic manner. 6.2 ORGANISATION AND COMMUNICATION 6.2.1 An appropriate Project organisation chart shall be set up, illustrating how the marine operations integrate with the rest of the project. Key responsibilities shall be clearly defined, and the responsibilities and reporting lines shown on the organisation chart. Organisation charts shall be drawn up for each marine operation showing the reporting lines into the project organisation and those responsible. Such reporting lines may include: a. Client's representative b. Overall project management c. Operation management d. Towing vessels e. Mooring systems and marine spread f. Ballast system operation g. Weather forecasting h. Support services i. Advisory panel providing expertise as required j. Safety k. Statutory, regulatory and approving bodies l. Emergency response. 6.2.2 6.2.3 6.2.4 6.2.5 6.2.6 6.2.7 6.2.8 In each case the responsibilities and duties of each function shall be clearly defined to minimise uncertainties and overlapping responsibilities. During on-going marine operations the site team should be limited to those persons with defined roles during the operation. Back-up services, including emergency services, contingency assistance and technical advisory services shall be identified and appropriately located. Communication systems, including radio channels, telephone, telefax numbers, e-mail addresses and out-of-hours numbers shall be identified and checked for accuracy. Where personnel changes occur during the course of an operation because of shift changes, these shall be identified. Every effort should be made to avoid changes of key personnel during critical stages of the operation. Where transfer of responsibility is involved, times of and procedures for hand-over from one organisation to another (e.g. from fabrication to marine operations, from on-shore to offshore) shall be identified. When continuous operations using more than 1 shift are not standard practice then special provision to prevent fatigue must be made for operations that could continue beyond normal working hours. This includes provision of suitably experienced and briefed alternate personnel with good hand-overs at each shift change. 6.3 QUALITY ASSURANCE AND ADMINISTRATIVE PROCEDURES 6.3.1 A quality management system in accordance with the current version of ISO 9001, Ref. [30], or equivalent should be adopted and be in place. 0001/ND Rev 1 Page 15 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS 6.4 TECHNICAL PROCEDURES 6.4.1 6.4.2 Technical procedures shall be in place to control engineering related to the marine activities. The objective of these procedures is to define applicable technical standards to ensure agreement and uniformity, with bridging documents where necessary, on matters such as: a. International and national standards and legislation b. Certifying authority/regulatory body standards c. Marine warranty surveyor guidelines d. Project criteria e. Design basis f. Metocean criteria g. Calculation procedures h. Change management. 6.5 TECHNICAL DOCUMENTATION 6.5.1 An integrated document numbering system for the entire project is suggested, including documents produced by client, contractors, sub-contractors and vendors. Documents relating to marine operations should be grouped into levels according to their status, for example: a. Criteria and design basis documents b. Procedures and operations manuals c. Supporting documents, including engineering calculations, equipment specifications and systems operating manuals. 6.5.2 6.5.3 Procedure documents, intended to be used as an active tool during marine operations should include a section which clearly shows their references to higher and lower level documents, and should list all inter-related documents. A document organogram is often helpful as shown in the following Figure. 0001/ND Rev 1 Page 16 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS MWS PRE-REQUISITES DIAGRAM PROJECT INFORMATION DOCUMENTS PROCEDURES, MANUAL AND METHOD STATEMENTS ON – SITE MWS SURVEYS PROJECT SPECIFICATIONS WEIGHT DETERMINATION WEIGHING EQUIPMENT INSPECTION DESIGN BASIS FOR TYPICAL OPERATIONS LAND TRANSPORTATION LIFTING EQUIPMENT INSPECTION PROJECT ORGANOGRAM LOADING OR OFFLOADING OPERATIONS LASHING AND SEAFASTENINGS INSPECTION MARINE TRANSPORTATIONS TRAILERS, SPMT’S, JACKS, CRANES, INSPECTION INSTALLATION OPERATIONS VESSELS, BARGES, FLOATING CRANES INSPECTION OPERATIONS INVOLVING SELFELEVATING UNITS SAILAWAY INSPECTION INSTALLATION TOOLS INSPECTION SELF-ELEVATING SYSTEM INSPECTION Figure 6-1 6.5.4 Example of document organogram Essential elements to be included in or referred to by a marine operation document include: a. Introduction b. Reference documents c. Outline execution plan d. Organogram and lines of command e. Job-descriptions for key personnel f. Safety plan g. Authorities and permits including notification and approval requirements h. Contractual approvals and hand over i. Environmental criteria, including design and operational criteria j. Operational bar chart, showing the anticipated duration of each activity, inter-related activities, key decision points, hold points k. Specific step-by-step instructions for each phase of the operation including sequence, timing, resources and check lists l. Reference to related drawings and calculations, e.g. environmental loads, moorings, ballast, stability, bollard pull m. Contingency and emergency plans n. Emergency Preparedness Bridging Document. 0001/ND Rev 1 Page 17 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS 6.5.5 6.5.6 Documents referred to by a marine operation procedure document should be available and accessible on board or on site close to the operation for reference by those involved. The top level procedure document should define the On-Scene Commander in the event of an emergency situation and the interfaces between the various parties involved. 6.6 DOCUMENTATION AND CERTIFICATION 6.6.1 The applicable documentation and certificates shown in Table 6-1 shall be valid for marine vessels. Some documentation is mandatory to comply with international legislation and standards. The documentation and certification requirements for any particular structure, vessel or operation should be determined in advance. Where new documentation is needed, the issuing authority and the Rules to be applied should be identified. Table 6-1 Principal Vessel Documentation Document / Certificate Description Bridging Document Recommended when the vessel’s operations are managed by more than one party. It outlines the vessel’s Safety Management System interface with that of the other parties and contains a responsibility matrix to provide clear guidance on operating principles and procedures for compliance and to ensure that the management onus is allocated. Should be signed by all concerned parties for acceptance. Cargo Securing Manual Provides guidance and specifies arrangements on stowage and securing of cargo. It accounts for the types of cargo and transverse, longitudinal and vertical forces which may arise during adverse weather and sea conditions that are likely to be experienced during the voyage. Approved by the Flag State. Certificate for Civil Liability for Bunker Oil Pollution Required for vessels over 1,000 gt. (gross tonnage). Generally issued by a P&I (Protection & Indemnity) Club Class (Hull and machinery) Vessels and their machinery, built and maintained in accordance with the Rules of a Classification Society will be assigned a class in the Society’s Register Book, and issued with the relevant Certificates, which will indicate the character assigned to the vessel and machinery. Issued by the Classification Society. While it is desirable for vessel to be classed for insurance and condition purposes it is not generally a legal requirement for it to be classed as long as it has a valid load-line or load-line exemption certificate. In addition to Class Certificates the most recent Class Status report detailing the present status and list of outstanding class requirements shall be submitted. Customs clearance Issued by Customs confirming that so far as they are concerned the vessel is free to sail. Issued after light dues have been paid, and on production of various other mandatory documentation. Garbage Management Plan A plan for management of waste. It may be documented within the vessel’s Safety Management System and should be approved by the Vessel Operator /Manager. g.t. / gross tonnage See Tonnage Certificate International Oil Pollution Prevention (IOPP) Certifies that the vessel complies with international oil pollution regulations (MARPOL Annex 1). Unless stated otherwise, all vessels over 400 gt must comply with the requirements of the code. Issued by the Flag State, or the appointed Classification Society. ISM Document of Compliance Certificate issued to the Vessel Operator /Manager stating that the Company complies with the requirements of the ISM Code and is endorsed for the type of ship for which this applies. (Note: The vessel must belong to one of the stated types.) 0001/ND Rev 1 Page 18 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS Document / Certificate Description Lifesaving Appliances Normally covered under Cargo Ship Safety Equipment Certificate. Where temporary equipment, e.g. liferafts or fire-fighting equipment, is placed on a structure not in possession of a Cargo Ship Safety Equipment Certificate, it is expected that each item would will be individually certified, with an in-date inspection. Load Line Issued after a vessel has been marked with her assigned load line marks. The Certificate gives details of the dimensions related to the freeboard, and the various special marks, e.g. TF (Tropical Fresh), WNA (Winter North Atlantic) etc. The vessel must be periodically inspected, to confirm that no changes have occurred to the hull or superstructure which would render invalid the data on which the assignment of freeboard was made. Issued by the Flag State, or appointed Classification Society. Load Line Exemption Where a vessel or structure is exempt from some or all of the provisions of the above, it may be issued with a Load Line Exemption Certificate, which will include any qualifying provisions. Issued by the Flag State, appointed Classification Society, or Port Authority. MODU /MOU certificate This may be a substitute for the Ship Safety Construction, Ship Safety Equipment and Safety Radio certificates Navigation Lights and Shapes Normally covered under Cargo Ship Safety Equipment Certificate. Where temporary lights are placed on a structure not in possession of a Cargo Ship Safety Equipment Certificate, it is expected that they will be individually certified, or in possession of a manufacturer’s guarantee of compliance. Panama Canal documentation For transit through the Panama Canal, drawings are required showing the extent of visibility from the bridge, and the extension of bilge keels, if fitted. Registry The Certificate of Registry is required by all commercial vessels. It contains the details from the Flag State Register in which the vessel has been registered, including principal dimensions, tonnage, and ownership. Issued by the Flag State Register. Safe Manning document A document issued by Flag State, showing the minimum safe manning for a vessel Safety Management Certificate (SMC) A document issued to a ship which signifies that the Company and its shipboard management operate in accordance with the approved Safety Management System. Issued by the Flag State, or appointed Classification Society. Safety Radio Certificate Issued by the Flag State after survey of the vessel’s radio installation, declaring that it is satisfactory for the intended service. Ship Safety Construction Covers the hull, machinery and equipment of a ship over 500 gt (gross tonnage) and shows that the ship complies with the construction and safety regulations applicable to the ship and the voyages she is to be engaged in. Issued by the Flag State, or appointed Classification Society. Ship Safety Equipment This is a record of the safety equipment carried on the vessel (over 500 gt), in compliance with SOLAS, including lifesaving appliances, fire- fighting equipment, lights and shapes, pilot ladders, magnetic compass etc. Issued by the Flag State, or appointed Classification Society. Ship Sanitation Control Certificate or Exemption Certificate (replaces De-rat) Competent authorities use this document, which carries a six month period of validity, to identify and record all areas of ship-borne public health risks (not limited to rodents), together with any required control measures to be applied. SOPEP Shipboard Oil Pollution Emergency Plan - Class approved 0001/ND Rev 1 Page 19 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS Document / Certificate Description SPS (Special Purpose Ship) certificate This may be a substitute for the Ship Safety Construction, Ship Safety Equipment and Safety Radio certificates Tonnage Certificate Shows the Tonnage as obtained by measurement, and is a measure of volume rather than weight. 1 ton equals 2.83 cu.m (100 cu.ft). Measured by a surveyor appointed by the Flag State. Transportation or towing manual A manual providing the Master with the key information that he needs, including the cargo and route. See Appendix G of 0030/ND, Ref. [9], for more details. Trim and Stability booklet A booklet setting out the vessel’s stability particulars, and allowing the actual draught, trim and stability characteristics and limitations to be determined for any cargo arrangement. Usually prepared by designers, and must be approved by the Flag State or a delegated Classification Society. 0001/ND Rev 1 Page 20 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS 7 METOCEAN CRITERIA & FORECASTS 7.1 INTRODUCTION 7.1.1 7.1.2 This Section refers to the metocean criteria applicable for marine operations. The metocean criteria should be established dependent on the duration of each discreet phase of a marine operation, which may be a weather-restricted or a weather unrestricted operation as defined in Section 3. Reference may be made to ISO 19901-1, Ref. [31],. Metocean criteria are generally used for analysis to a recognised standard (including relevant safety factors). For seasonally based data, the data for the month of the operation and the following month shall be used. In addition to this, if the operation is to be carried out in the first 10 days of the month, the data used shall also include the preceding month. If a marine operation has started and a subsequent forecast exceeds allowable values, contingency planning shall be followed. Requirements for contingency planning are in Section 5.7. 7.1.3 7.1.4 7.2 DESIGN ENVIRONMENTAL CONDITION AND OPERATIONAL CRITERIA 7.2.1.1 The design environmental condition consists of the wave height, wind speed, current and other relevant environmental conditions specified for the design of a particular marine operation. The operational criteria are the limiting metocean criteria for which each phase of a particular marine operation can occur, under the approval of GL Noble Denton. The operational criteria shall consider both the design environmental condition and practical aspects of the operation, such as personnel transfers, assisting vessels, ROV's, etc. A weather unrestricted operation is not limited by practical aspects, and therefore the operational criteria are the design environmental condition. The design environmental condition is based on extreme statistical data and is addressed in Section 7.3.2. It may be impractical and/or uneconomical to design marine operations based on extreme statistical data. Therefore the design environmental condition can be set independent of extreme statistical data for weather restricted operations. For this case, the operational criteria are defined as the design environmental condition reduced by an alpha factor to account for weather forecasting inaccuracies. However, if the resulting operational criteria are too low, the waiting time for acceptable conditions could be excessive. Discussion on the setting of design environment conditions and weather forecast requirements are in Section 7.4. 7.2.1.2 7.2.1.3 7.2.1.4 7.3 UNRESTRICTED OPERATIONS 7.3.1 7.3.1.1 GENERAL Whilst an operation may be defined as unrestricted, specific portions may be dependent on suitable weather forecasts, e.g. the departure of a tow from safe haven as described in Section 14.4 of 0030/ND, Ref. [9]. Such restrictions shall be agreed before the start of an operation and are normally included on the Certificate of Approval. 7.3.2 7.3.2.1 RETURN PERIODS The return periods for unrestricted marine operations, apart from moorings, and the elevated operation of jack-ups, should be related to its operational reference period, as defined in Section 3. For design criteria for moorings see Section 7 of 0032/ND, Ref. [11], and for the elevated operation of jack-ups see 0009/ND, Ref. [1]. As general guidance, the following criteria may be applied using independent extremes for unrestricted marine operations: 7.3.2.2 0001/ND Rev 1 Page 21 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS Table 7-1 7.3.2.3 7.3.2.4 7.3.2.5 7.3.3 7.3.3.1 7.3.3.2 7.3.4 7.3.4.1 7.3.4.2 7.3.4.3 Metocean return periods – unrestricted operations Operational reference period Wind Wave and Current Up to 3 days[1] 5 year return, seasonal 3 month return, seasonal. 3 to 7 days 10 year return, seasonal 1 year return, seasonal 7 days to 1 month 25 year return, seasonal (or 10yr +0.7*(50yr-10yr)) 10 year return, seasonal 7 days to 1 month For transportation, use reduced exposure towage /transportation computation (as defined in Section 3) with a minimum of the 1 year seasonal return For transportation, use reduced exposure towage /transportation computation (as defined in Section 3) with a minimum of the 1 year seasonal return 1 month to 1 year 75 year return, seasonal (or 50yr +0.7*(100yr-50yr)) 50 year return, seasonal More than 1 year 100 year return, seasonal 100 year return, seasonal General Note: The values above are applicable to the WSD design approach and therefore differ from the values given in DNV-OS-H101. Note 1 – Operations up to 3 days may also be defined as restricted operations. See Section 7.4. If conditions are determined using the joint probability of different parameters, then the return period should be increased by a factor of 4 i.e. 10 years to say 50 years and 50 years to 200 years, unless the loadings are dependent on a single parameter in which case the value of that parameter shall be taken from a joint probability combination in which it is maximised. For towages or transportations, the design extremes may be reduced below the 10 year seasonal return, to give the same probability of encounter as a 30 day exposure to a 10 year seasonal storm. In this case the “adjusted” design extremes are defined in terms of the 10% risk level (see Section 6.5 of 0030/ND, Ref. [9]. The design extremes shall not be reduced below the 1 year seasonal return. Directionality of the environment may be considered. WIND The design wind speed shall generally be the 1 minute mean velocity at a reference height of 10m above sea level. A longer or shorter averaging period may be used for design depending upon the nature of the marine operation, the structure involved and the response characteristics of the structure to wind. The relationship between wind velocity at the reference and actual elevations above sea level and between different averaging periods can be found in ISO 19901-1 "Metocean design and operational considerations", Ref. [31]. WAVES The design maximum wave shall be the most probable highest individual wave in the design seastate, assuming an exposure of 3 hours. The determination of the height, period and crest elevation of the maximum wave should be determined from an appropriate higher-order wave theory and account for shallow water effects. Seastates shall include all relevant spectra up to and including the design storm seastate for the construction site or towage route. Long-crested seas shall be considered unless there is a justifiable basis for using short-crested seas or these are more critical. Consideration should be given to the choice of spectrum. In the simplest method the peak period (Tp) for all seastates considered, should be varied as: (13.Hs) < Tp < (30.Hs) 0001/ND Rev 1 Page 22 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS 7.3.4.4 7.3.4.5 7.3.4.6 where Hs is in metres, Tp in seconds. The effects of swell should also be considered if not already covered in this peak period range. A reduced range of Tp may be used if the route specific data and natural periods allow. However, this method incorrectly assumes that all periods are equally probable. As a result this method should generally produce higher design responses than would be the case when using the more robust Hs-Tp method described in the following Section 7.3.4.4. Where the natural periods fall outside the range of peak periods given above, the analysis shall also consider Tp equal to the natural period(s) ±1 second; the associated Hs may be used. In the alternative method, a contour is constructed within the Hs-Tp plane that identifies equally probable combinations of Hs & Tp for the design return period subject to theoretical constraints on wave breaking. This contour should also cover swell. Hs-Tp combinations from around the contour should be tested in motion response calculations to identify the worst case response (there is no need to consider a range of Tp with each Hs). The relationship between the peak period Tp and the zero-up crossing period Tz is dependent on the spectrum. For a mean JONSWAP spectrum (γ=3.3) Tp/Tz = 1.286; for a Pierson-Moskowitz spectrum (γ=1) Tp/Tz = 1.41. The following Table 7-2 indicates how the characteristics of the JONSWAP wave energy spectrum vary over the range of recommended seastates. The constant, K, varies from 13 to 30 as shown in the equation in Section 7.3.4.3 above. T1 is the mean period (also known as Tm). Table 7-2 7.3.4.7 7.3.4.8 7.3.4.9 7.3.5 7.3.5.1 Value of JONSWAP γ, ratio of Tp:Tz and Tp:T1 for each integer value of K Constant K γ Tp/Tz Tp/T1 Constant K γ Tp/Tz Tp/T1 13 5.0 1.24 1.17 22 1.4 1.37 1.27 14 4.3 1.26 1.18 23 1.3 1.39 1.28 15 3.7 1.27 1.19 24 1.1 1.40 1.29 16 3.2 1.29 1.20 25 1.0 1.40 1.29 17 2.7 1.31 1.21 26 1.0 1.40 1.29 18 2.4 1.32 1.23 27 1.0 1.40 1.29 19 2.1 1.34 1.24 28 1.0 1.40 1.29 20 1.8 1.35 1.25 29 1.0 1.40 1.29 21 1.6 1.36 1.26 30 1.0 1.40 1.29 For operations involving phases sensitive to extreme sea states, such as temporary on-bottom stability or green water assessment, the maximum wave height and associated period should be used. For precise operations sensitive to small fluctuations of the sea level even under calm sea state conditions, the occurrence of long period, small amplitude swell on the site should be checked and its effects on the operations evaluated. Attention should also be paid to areas prone to strong currents acting against the waves which would amplify the steepness of the sea state (i.e. reduce the wave encounter period that drives dynamic response). CURRENT The design current shall be the rate at mean spring tides, taking account of variations with depth and increases caused by the design storm and storm surge. 0001/ND Rev 1 Page 23 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS 7.3.5.2 Currents may be divided into two different categories: a. Tidal currents b. Residual currents that remain when the tidal component is removed, including river outflows, surge, wind drift, loop and eddy currents. 7.3.5.3 Tidal currents may be predicted reliably, subject to long term measurement (at least one complete lunar cycle at the same season of the year as the actual planned operation). Residual currents may only be reliably predicted or forecast using sophisticated mathematical models. 7.3.6 7.3.6.1 OTHER PARAMETERS Other factors including the following may be critical to the design or operations and should be addressed: a. Water level including tide and surge b. Sea icing, icing on superstructure c. Exceptionally low temperature d. Large temperature differences e. Water density and salinity f. Bad visibility. 7.4 WEATHER RESTRICTED OPERATIONS 7.4.1 7.4.1.1 GENERAL A marine operation with an operational reference period (as defined in Section 3) generally less than 72 hours may be classed as a weather restricted operation The design environmental conditions for such an operation may be set independent of extreme statistical data, provided that: The Alpha factors in Section 7.4.8 shall be considered when selecting the design environmental criteria The statistics indicate an adequate frequency and duration of the required weather windows Dependable weather forecasts are received at appropriate intervals The start of the operation is governed by an acceptable weather forecast, covering the operational reference period Adequate marine and contingency procedures are in place. 0001/ND Rev 1 Page 24 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS 7.4.1.2 A marine operation with an operational reference period greater than 72 hours may exceptionally be classed as a weather-restricted operation, provided that: Project specific Alpha factors shall be agreed with GL Noble Denton and be considered when selecting the design environmental criteria An acceptable weather forecast service is contracted and is available for advice at any time. Dependable weather forecasts are received at appropriate intervals. Management resources of interested parties are always available with the right authority level to monitor any operation decisions. Adequate marine and contingency procedures are in place. A risk assessment has been carried out and the results accepted by GL Noble Denton. The quality of data available and weather forecasts for the area and season should influence the assessment of overall risk. 7.4.2 7.4.2.1 OPERATION DURATION AND OPERATIONAL REFERENCE PERIOD The operation duration shall account for the interval between the acceptable forecast and the start of the operation as shown in Figure 7-1. The start of the operation and Point(s) of No Return shall be clearly defined and agreed with GL Noble Denton. Weather forecast issued Operation starts Weather forecast issued Weather forecast issued Weather forecast issued Estimated time for operation Contingency Period Operation Duration Operation Reference Period Required Weather Window Figure 7-1 7.4.2.2 7.4.2.3 7.4.2.4 Operation Periods The Operational Reference Period includes a Contingency Period, and covers from the forecast prior to the start of the operation until the structure and equipment are in safe states. This is also termed “safe to safe” duration. When defining the Operational Reference Period required for a weather restricted operation, the schedule should be as realistic as possible. The Operational Reference Period should be the bestestimate Operation Duration plus contingencies for: a. Inaccuracy in operation schedule. For schedules based on field experience gained from previous similar operations it is possible that a lower contingency can be justified. b. Technical / mechanical / operational delays. For operations using vulnerable or critical equipment extra contingency should be allowed. c. Inaccuracy in the timing and length of window predicted by the metocean forecast. Extra contingency can be necessary for operations where metocean conditions are difficult to predict because of the area or the time of the year. For situations where a contingency duration has not been defined, the contingency duration shall be at least the Operation Duration (as defined in Section 3) with a minimum of 6 hours. Additional contingency duration may be required for complex subsea operations. 0001/ND Rev 1 Page 25 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS 7.4.2.5 The forecast weather window duration shall be not less than the Operational Reference Period. 7.4.3 7.4.3.1 IMPACT ON DESIGN During design the following should be considered: a. Measures to minimize the duration of critical activities, without compromising the safety of the operation, in order to provide more margin on the weather window b. Re-design of the operation and/or structure so that higher metocean conditions can be safely sustained c. Contingency situations, and back-up and stand-by measures d. Whether delays to previous activities could push the operation into an unfavourable season. 7.4.4 7.4.4.1 MARGINS ON WEATHER For weather restricted operations, the forecast environmental conditions for each phase of the operation shall not exceed the operational criteria for that phase. The operational criteria are calculated by multiplying the design environmental condition by an Alpha factor. Unless agreed otherwise with GL Noble Denton, the Alpha factor shall be a maximum of the applicable value from Section 7.4.8. 7.4.5 7.4.5.1 POINT OF NO RETURN (PNR) Weather restricted operations may be divided into sequences where the operation can be aborted and brought to a safe condition within the remainder of the existing weather window. The Point of No Return (PNR) should be defined as the last point in time, or a geographical point along a route, at which an operation can be aborted and returned to a safe condition. For the critical operation period between any PNR and the structure reaching a safe condition, the reliability of the weather window and forecast is crucial. 7.4.5.2 7.4.5.3 7.4.6 7.4.6.1 7.4.6.2 7.4.6.3 WEATHER / METOCEAN FORECASTS REQUIREMENTS Project specific forecasts shall be obtained before and during all marine operations. The forecast shall be issued at suitable regular intervals dependent on the operation, and at least every 12 hours. Wherever possible a second forecast should be obtained from an independent source before critical operations. For complex and/or longer weather-restricted operations, the forecaster(s) should preferably be present at site to check the local situation and provide regular weather briefings. Reference may be made to the Handbook of Forecasting Services, Ref. [37]. Where operations are sensitive to local environmental conditions, or to changes in these, facilities for on-site monitoring should be considered. 7.4.7 7.4.7.1 FORECAST PARAMETERS The forecast should cover short, medium term and outlook periods and include relevant parameters such as: a. Synopsis, barometric pressure, temperature b. Wind direction and velocity c. Waves and swell - significant and maximum height, direction and period d. Visibility, rain, snow, sleet, icing and sea ice e. Confidence level of the forecast and each of the key parameters. 7.4.7.2 Other conditions such as current, tide and surge can be relevant to certain operations. Such conditions can require real time measurement as well as regular forecasting before and during operations. Attention should be paid to local current phenomenon, for instance: a. Loop-eddy currents in the Gulf of Mexico b. Soliton currents in the South China Sea. Forecasts, especially for Operational Reference Periods over 24 hours, should have a high confidence level. 7.4.7.3 0001/ND Rev 1 Page 26 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS 7.4.8 7.4.8.1 7.4.8.2 ALPHA FACTOR The Alpha factor shall be selected using the Operation Duration. The Forecasting Requirement Classes in the following Table 7-3 should be agreed with GL Noble Denton for each relevant operation at an early stage of each project. Table 7-3 Forecast Requirement Classes Forecast Requirement A1 A2 B1 B2 C Wave Alpha Factor Table 7-8 Table 7-7 Table 7-6 Table 7-5 Table 7-4 Wind Alpha Factor Table 7-9 For weather sensitivity HIGH MODERATE LOW Typically required for the following examples. (These may vary depending on the value of the structures and complexity /weather sensitivity of the operations) Major, e.g. Mating Offshore float-over Offshore installation GBS Float-out or tow Significant, e.g. Offshore lifting Subsea installation Sensitive barge towing Jack-up move Routine, e.g. Inshore /onshore lifting Load-out (without tidal restrictions) Standard towage Dedicated meteorologist YES Not required [1] Not required Meteorologist on site YES NO Not required Not required Environmental monitoring & feedback to meteorologist YES NO YES Not required NO Independent weather 2 2 1 forecasts required [2] Notes: 1. The “on duty” meteorologist shall be consulted if the weather situation is unstable and/or close to the defined limit. 2. Independent weather forecasts shall be taken from different atmospheric models and the sources shall be agreed in advance. 7.4.8.3 7.4.8.4 Although reliable weather windows of more than 3 days may be possible with stable weather patterns, such weather patterns should not be assumed for planning purposes. The Alpha factors for waves are shown in Table 7-4 through Table 7-9. These are applicable to the WSD design approach and are therefore lower than the values given in DNV-OS-H101. In the following tables factors for intermediate wave heights can be obtained by linear interpolation between values for the same operational duration. Other values may be agreed with GL Noble Denton on a case specific basis. Table 7-4 Operation Duration < 12 hours < 24 hours < 36 hours < 48 hours < 72 hours 0001/ND Rev 1 Alpha Factors for Waves - Forecast Requirement C (Low Sensitivity) Hs < 1 m 0.58 0.56 0.55 0.53 0.49 Operational Significant Wave Height Hs = 2 m Hs = 4 m 0.68 0.70 0.65 0.68 0.63 0.65 0.61 0.63 0.56 0.61 Hs > 6 m 0.71 0.69 0.68 0.66 0.64 Page 27 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS Table 7-5 Alpha Factors for Waves - Forecast Requirement B2 (Moderate Sensitivity) Operational Significant Wave Height (No monitoring) Hs < 1 m Hs = 2 m Hs = 4 m Hs > 6 m 0.61 0.71 0.74 0.75 0.59 0.69 0.71 0.73 0.58 0.67 0.69 0.71 0.56 0.63 0.67 0.69 0.52 0.59 0.63 0.68 Operation Duration < 12 hours < 24 hours < 36 hours < 48 hours < 72 hours Table 7-6 Alpha Factors for Waves - Forecast Requirement B1 (Moderate Sensitivity) Operational Significant Wave Height (With monitoring) Hs < 1 m Hs = 2 m Hs = 4 m Hs > 6 m 0.80 0.85 0.89 0.89 0.64 0.75 0.77 0.78 As for Table 7-5 above Operation Duration < 4 hours < 12 hours > 12 hours Table 7-7 Alpha Factors for Waves - Forecast Requirement A2 (High Sensitivity) Operational Significant Wave Height (No monitoring) Hs < 1 m Hs = 2 m Hs = 4 m Hs > 6 m 0.64 0.75 0.77 0.78 0.61 0.71 0.75 0.77 0.61 0.69 0.71 0.75 0.59 0.67 0.69 0.72 0.54 0.61 0.67 0.70 Operation Duration < 12 hours < 24 hours < 36 hours < 48 hours < 72 hours Table 7-8 Alpha Factors for Waves - Forecast Requirement A1 (High Sensitivity) Operation Duration < 4 hours < 12 hours < 24 hours > 24 hours Table 7-9 Operation Duration < 24 hours < 48 hours < 72 hours 0001/ND Rev 1 Operational Significant Wave Height (With monitoring) Hs < 1 m Hs = 2 m Hs = 4 m Hs > 6 m 0.80 0.85 0.89 0.89 0.69 0.81 0.85 0.85 0.64 0.75 0.77 0.80 As for Table 7-7 above Alpha Factors - Wind (all Forecast Requirements) Design Wind Speed (Vd) Vd < 05 x V 10 year return Vd > 05 x V 10 year return 0.71 0.76 0.67 0.71 0.62 0.67 Page 28 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS 7.5 BENIGN WEATHER AREAS 7.5.1 Areas considered benign are shown in the following Table 7-10 and Figure 7-2 for different months. In general they have the following characteristics: a. virtually free of monsoons, Tropical Revolving Storms or Tropical Cyclones b. exceeding Beaufort Force 5 for <20% of any month (in a “typical” year) c. However these areas may experience sudden vicious squalls and very rare tropical storms or cyclones. Table 7-10 Basin Jan Northern & Southern Boundaries of Benign Weather Areas by Month Feb North Atlantic Mar Apr May 20ºN Red Sea Jun 15ºN 23ºN Persian (Arabian) Gulf Arabian Sea (see Note 1) Bay of Bengal Northwest Pacific to 160ºW Northeast Pacific (see Note 2) Aug 10ºN Sep Oct 9ºN Nov Dec 13ºN 15ºN coast 23ºN coast 4ºN coast 8ºN 4ºN 7ºN 5ºN 4ºN coast 7ºN 4ºN 7ºN 5º0N 4ºN Hong Kong – Manila or 10ºN 5ºN 4ºN 23ºN 5ºN 8ºN South Atlantic 6ºN 9ºN 5ºN 11ºN 4ºN 9ºN 23ºN 23ºS South Indian 7ºS SW Pacific from 125ºE to 130ºW Southeast Pacific to 130ºW 8ºS Key Jul 9ºS 8ºS 10ºS 6ºS 8ºS 15ºS 7 ºS 23ºS 5ºS 7ºS 8ºS 23ºS All year boundary Intermediate boundary Maximum area boundary Notes: 1. The boundary between the Arabian Sea and Bay of Bengal is assumed to be 75ºE. 2. The Northeast Pacific is from 160ºW to the American coast but 88ºW for May to November inclusive. 3. The equator is the Southern boundary for areas in the Northern hemisphere and the Northern boundary for areas in the Southern hemisphere. 0001/ND Rev 1 Page 29 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS 1 Figure 7-2 0001/ND Rev 1 Map Showing Benign Weather Areas Page 30 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS 8 WEIGHT CONTROL 8.1 INTRODUCTION 8.1.1 This section addresses weights and CoGs for structural and installation checks. Weights, CoG and ranges/envelopes for both structural and installation design should account for the considerations discussed in this section. Weights used for contractual purposes are excluded. For calculation purposes conservative values of weight and CoG should be used. Weight control shall be performed by means of a well-defined and documented system, complying with the ISO International Standard ISO 19901-5 – Petroleum and Natural Gas Industries – Specific requirements for offshore structures – Part 5: Weight control during engineering and construction, Ref. [32]. Ref. [32] states (inter alia) that: “Class A (weight control) will apply if the project is weight- or CoG-sensitive for lifting and marine operations or during operation (with the addition of temporaries), or has many contractors with which to interface. Projects may also require this high definition if risk gives cause for concern”. “Class B (weight control) shall apply to projects where the focus on weight and CoG is less critical for lifting and marine operations than for projects where Class A is applicable”. “Class C (weight control) shall apply to projects where the requirements for weight and CoG data are not critical”. Unless it can be shown that a particular structure and all operations are not weight or CoG sensitive, and this agreed with GL Noble Denton, then Class A weight control shall apply, as shown in Section 4.2 of ISO 19901-5, Ref. [32]. Weight reports should be issued in accordance with Section 6 of Ref. [32]. Weight reports not in accordance should be submitted to the relevant GL Noble Denton office at an early stage of the project to ensure that they will be acceptable without changes. 8.1.2 8.1.3 8.1.4 8.1.5 8.2 WEIGHT CONSIDERATIONS 8.2.1 A Not To Exceed (NTE) weight shall be defined for any part or all of the structure for any phase when too high a weight could be critical. In addition to any in-place design and operational considerations, the following factors can control the NTE weight: a. Draught and stability for float-out, towages, matings and installation; b. Allowable stresses in the structure for marine operations; c. Limitations due to crane, load-out trailers, other equipment or ground-bearing capacity. Where a structure is to be weighed and a weighing contingency factor has been included when defining the NTE weight then the NTE weight shall be used for checks. If this approach is adopted then the maximum allowable weighed weight is the NTE reduced by a weighing contingency factor corresponding to the accuracy of the weighing equipment. Where a structure is to be weighed and no weighing contingency factor has been included in defining the NTE weight then the NTE weight shall be increased by a design weighing contingency factor. If this approach is adopted the maximum allowable weighed weight is NTE weight increased by the design weighing contingency factor and reduced by the weighing contingency factor applicable to the weighing equipment used. Where a structure (excluding piles) is not to be weighed, the defined NTE weight shall be used for checks. The defined NTE weight shall be greater than the gross weight factored by the applicable of the following weighing contingency factors: 1.03 for Class A (as defined by ISO Standard, Ref. [32]) 1.10 for Class B and C (as defined by ISO Standard, Ref. [31). 8.2.2 8.2.3 8.2.4 0001/ND Rev 1 Page 31 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS 8.2.5 8.2.6 8.2.7 The weight contingency factors for piles shall be submitted to GL Noble Denton for approval and shall consider the following as a minimum: plate thickness tolerance fabrication tolerances For calculation purposes conservative values of weight should be used. Where the minimum weight could be critical in an operation e.g. transportation motions, the possible minimum weight, reduced by the weighing contingency factor in accordance with Section 8.2.4, should also be considered. An adequate reserve shall be added to the 50/50 weight estimate, as defined in Ref. [32] to suit each particular operation considering the weight and CoG sensitivity and the maturity of the project design. In general, the reserve applied to the final 50/50 weight estimate should be not less than 5%. 8.3 CENTRE OF GRAVITY FACTORS 8.3.1 For Class A and B structures a CoG envelope shall be applied to allow for CoG inaccuracies. For Class C structures a CoG envelope is recommended. The size of the CoG envelope should reflect the operational and structural sensitivity to CoG variations and the most conservative centre of gravity position within the envelope should be taken. For early design stages, too small an envelope should be avoided and envelope sizes less than 0.05L x 0.05B x 0.05H are normally not recommended, where L, B and H are the Length, Breadth and Height of the structure. For Class C, if a CoG envelope is not used then a CoG inaccuracy factor of 1.10 shall be applied to the weight. Where it can be documented that a lower CoG inaccuracy factor is applicable, this should be submitted to GL Noble Denton for review and acceptance. The CoG contingency factors for piles shall be determined considering the pile length and the plate manufacturer’s plate thickness tolerance specification. 8.3.2 8.3.3 8.3.4 8.4 WEIGHT CONTROL 8.4.1 8.4.6 Prior to any structure being weighed, a predicted weight and CoG report shall be issued, so that the weighed weight and CoG can immediately be compared with the predicted results. The cause(s) of significant deviations between the weighed and predicted results (both weight and CoG) shall be investigated and reported. Where weight is added to/removed from the structure after weighing, a weight control system shall be adopted to ensure that the weight and CoG details based on the weighing are updated with any changes. The weight changes due to items that are added and removed shall include their weighing contingency factors. The final derived weight and CoG values shall be submitted. A statement may be required from a responsible engineer confirming that the structure and the lifting equipment, seafastenings, etc. remain adequate for the final weight and CoG. When the installation of a large number of nominally identical items is to be approved, the weight control programme should be documented to show the effects of all potential variations on the final weights and the results certified by a competent person. During construction afloat, periodic draught measurements and weight control audits and inclining tests shall be carried out when a particular structure and its marine operations are weight or CoG sensitive, particularly prior to critical operations such as deck mating. See Section 14.1.2 for weight control for decommissioning /removal. 8.5 WEIGHING 8.5.1 The actual weight and CoG position shall be determined by weighing unless agreed otherwise with GL Noble Denton. A weighing procedure for the structure shall be produced and include the specification, including accuracy, for all equipment. The accuracy of the weighing equipment shall be certified by a Competent Body. The weighing should preferably be carried out a minimum of 3 times with the load cells interchanged between each of the weighing operations. 8.4.2 8.4.3 8.4.4 8.4.5 0001/ND Rev 1 Page 32 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS 8.5.2 Where the actual weight including weighing and contingency factors or the CoG is outside the design values considered the effects of the deviations shall be quantified and the operational procedures modified where necessary. 8.6 WEIGHT AND BUOYANCY CONTROL 8.6.1 Where the balance between weight and buoyancy is critical to the draught, stability or floating behaviour, the dimensional and buoyancy control and monitoring shall be maintained to an appropriate degree of accuracy. 0001/ND Rev 1 Page 33 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS 9 STRUCTURAL STRENGTH 9.1 GENERAL 9.1.1 The structural strength of the final structure in the installed condition is the responsibility of the assured and would normally be verified and accepted by the certifying authority. The Marine Warranty Surveyor takes no responsibility for the installed condition unless the Marine Warranty Survey scope specifically addresses this case e.g. for jack-up site approval. Although a Marine Warranty Surveyor does not certify the final structure he shall ensure that the load cases relevant to load-out, construction afloat, towage, transportation and installation are suitably addressed in the design. The loadings used for structural strength assessment should be determined in accordance with the requirements of the applicable Code(s), Standard(s) and Guideline(s). It is important to recognise that the metocean design criteria (i.e. the design environmental condition) used to determine the loads applicable to Weather-Restricted operations will be greater than the Operational Criteria that apply to (each phase of) the operation. This is due the requirement to apply an Alpha factor in accordance with 7.4.8. 9.1.2 9.1.3 9.2 STRUCTURAL STEEL 9.2.1 The primary structure and any critical temporary works like lifting attachments, spreader bars and seafastenings shall be of high quality structural steelwork with full material certification and NDT inspection certificates showing appropriate levels of inspection. It shall be assessed using the methodology of a recognised and applicable offshore code including the associated load and resistance factors for LRFD codes or safety factors for ASD/WSD codes. Traditionally AISC has also been considered a reference code, e.g. by API RP2A. Although specifically not recommended by API 22nd edition, if the ANSI / AISC 360-10 American National Standard “Specification for Structural Steel Buildings” of June 2010 (in the AISC 14th edition) is used, the allowables shall be compared against member stresses determined using a load factor on all loads (dead, live, environmental, etc.) of no less than those detailed in the following Table 9-1. 9.2.2 Table 9-1 9.2.3 Type WSD option LRFD Option To be used only with the loading criteria given in the GL Noble Denton Guidelines Limit State 1 (LS1): 1.00 1.60 Limit State 2 (LS2): 0.75 1.20 Note: The load factor of 0.75 for the WSD/LS2 case arises because the basic allowable stress in AISC WSD 14th edition is 0.6*yield and the traditional 1/3 increase to 0.8*yield (i.e. to 0.6*yield*4/3) for environmental load cases is not included. As an alternative, the load is multiplied by 3/4 and used with the standard allowable of 0.6*yield in order to achieve the safety levels that have been used and accepted over many years. Stress in fillet welds for brackets loaded by a force acting in a direction parallel to the weld bead shall be assessed using the method presented in Appendix A. The allowables shall be compared against member stresses determined using a load factor on both dead and live loads of no less than LS1: 1.40 LS2: 9.2.4 Load Factors for use with AISC 14th Edition 1.05 Any load case may be treated as a gravity-load dominated limit state (LS1). 0001/ND Rev 1 Page 34 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS 9.2.5 The infrequent load cases, generally limited to survival and damaged cases, including design cases for weather-restricted operations where an Alpha factor according to Section 7.4.8 is to be applied, may be treated an LS2, environmental load dominated, case. This does not apply to: Steelwork subject to deterioration and/or limited initial NDT unless the condition of the entire loadpath has been verified, for example the underdeck members of a barge or vessel. Steelwork subject to NDT prior to elapse of the recommended cooling and waiting time as defined by the Welding Procedure Specification (WPS) and NDT procedures. In cases where this cannot be avoided by means of a suitable WPS, it may be necessary to increase the strength or impose a reduction on the design/permissible seastate. Steelwork supporting sacrificial bumpers and guides. Spreader bars, lift points and primary steelwork of lifted items. Structures during a load-out. 9.2.6 The design of non-tubular connections shall be in accordance with an appropriate standard such as AISC Ref. [13], using a consistent safety format and factors. 9.3 FILLET WELDS 9.3.1 Appendix A gives the requirements for checking fillet welds. 9.4 DOUBLER PLATES 9.4.1 Doubler plates are generally recommended for use: a. when attaching seafastenings or sacrificial anodes to permanent steel work subject to fatigue or if the permanent structure could be damaged when the attachments are burnt off after use. b. To avoid welding onto other welds. 9.4.2 Doubler plates are generally NOT recommended for use when tension can cause overstress in the doubler plate or the structure to which it is attached. 9.5 BOLTED CONNECTIONS FOR SEAFASTENINGS 9.5.1 Appendix B gives the requirements for bolted connections for seafastenings which involving cyclic loading due to the dangers of progressive collapse. 9.6 LIGHT-WEIGHT METALLIC AND COMPOSITE STRUCTURES 9.6.1 9.6.3 Different light weight metallic and composite materials will have their own advantages, disadvantages and problems. The designers or manufacturers shall specify any handling /connection requirements which must appear in the relevant procedures and towing /transportation manuals. Tugger line systems are very important while handling lightweight alloy items in order to avoid any impact with sea-fastening, grillage or offshore structures which may cause plastic deformations. A structural assessment of an innovative structure and/or material cargo during temporary stages may not always be available for GL Noble Denton to review due to confidentiality concerns. In this case, after agreement with the Insurance Underwriter and the Client, GL Noble Denton may accept an official document from the designer stating maximum allowable loads from the seafastenings and allowable accelerations for the structure /cargo to keep within allowable stresses during transport or installation. Alternatively one of the parties may confirm that they will take responsibility in case of blade damage during load-out, transport or installation. 9.7 STRUCTURAL CONCRETE 9.7.1 The strength of concrete and its reinforcement including any pre- or post-tensioning shall comply with a recognised and appropriate concrete design code, such as those listed in ISO 19903, Ref [33]. Any time-dependent properties of the materials shall be taken into account. 9.6.2 0001/ND Rev 1 Page 35 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS 9.8 COMPRESSED AIR 9.8.1 Compressed air may be used to resist hydrostatic head on internal or external walls during ballasting, for reducing draft, or for reducing overall bending moments by air cushions in skirt cells under well controlled conditions. However its absence should not, in general, result in structural collapse i.e. it should be used only to increase structural safety factors. Where the requirements of Section 9.8.1 cannot be met, then a risk assessment shall be carried out to determine possible causes and probabilities of loss of compressed air. Mitigating measures to reduce the risks to an acceptable level shall be agreed with GL Noble Denton. 9.8.2 9.9 DOCUMENTATION REQUIREMENTS FOR LIFTING, TOWING & MOORING GEAR 9.9.1 The following Table 9-2 summarises and compares the requirements in 0027/ND for lifting, 0030/ND for towing and 0032/ND for mooring gear which take precedence in case of discrepancies. 0001/ND Rev 1 Page 36 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS Table 9-2 Documentation Requirements for Lifting, Towing & Mooring Gear Documented inspection by competent person (See Note 2) Use Item Certificate valid for (See Note 1) Lifting Cranes In date As required by crane certifying body (See Note 3) Lifting points Not required See 0027/ND Ref [6] Sec. 12.7 Lifting tools 4 years (default) < 6 months Shackles (see Note 4) 2 years offshore & inshore 4 years onshore < 6 months & MPI /UT every 2 years Slings /grommets 2 years offshore & inshore 4 years onshore < 6 months offshore & inshore < 12 months onshore Spreader bar /frame See comment Before use Bollard pull <10 years Not applicable Derate if >10 years - see 0030/ND, Ref [9] Section 12.1 Delta plates /master links & shackles <5 years < 12 months & MPI /UT every 2 years Pennants & bridles <5 years < 12 months Submerged bridles <5 years See Note 5 Towlines <5 years < 12 months Spelter sockets <2 years < 12 months Lashing equipment <4 years < 12 months Anchors No limit if in good condition Depends on condition (Surveyor’s discretion) Towing Mooring Comments Unless certificate states differently See 0027/ND Ref [6] Section 15.5 1 (see Note 6) Bollards and shore anchors See 0032/ND, Ref [11], Section 14.6 Kenters & similar <5 years depends on use and fatigue life Chains Depends on chain history Synthetic lines Depends on use and fatigue life Wires < 5 years depends on use and fatigue life see DNV-OSS-101 9.4.7 Notes: 1. Certificates shall be issued or endorsed by a body approved by an IACS member for the certification of this type of equipment and show the design minimum breaking load or proof load and design safety factor on minimum breaking load. 2. Competent person is defined in Section 3. In addition, all hardware must be thoroughly visually inspected before each use and any damaged areas inspected more thoroughly before deciding on use. 3. Cranes to be currently certified by an IACS member for the proposed load and conditions. Typically annual inspections for the whole crane and weekly for critical items. Additional NMD requirements may apply for Norway. 0001/ND Rev 1 Page 37 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS 4. For shackles accepted without documented material properties complying with OS-H205 Sec 4.2.3.2, the proof load certificate should not be older than 2 years. 5. Inspection regime to be agreed with rig operator. Higher safety factors to be agreed if inspection periods longer than that for above water inspections to allow for corrosion, fatigue & longer inspection times. Min 20% extra SF for each year after first, i.e. 80% extra safety factor for 5 years between inspections. Maximum age from new for such equipment to be 5 years. 6. Towlines shall not be in use longer than 100,000 nautical miles, of which no more than 50,000 miles shall have been in adverse weather conditions (nominally > Beaufort force 6). Within 5 years from new or previous similar test about 10 - 12 m of towline shall be cut out and break tested or proof loaded to 1.5 x BP without yielding. Max towline life 5 years if not adequately documented in towline log. Tow wires shall be terminated with hard eye thimbles or closed sockets. Aluminium or alloy ferrules should not be used. 0001/ND Rev 1 Page 38 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS 10 BUILDING / CONSTRUCTION BASIN 10.1 The surrounding walls of any building / construction basin shall be designed in accordance with accepted civil and geotechnical engineering practice, guidelines, codes and standards. Where materials are used whose stability characteristics can be affected by a change in pore water pressure, suitable monitoring devices shall be installed and the data retrieved and analysed by competent geotechnical engineers to ensure continuing stability of the walls throughout the period of the platform construction. Meteorological design criteria for the basin design shall be at least the 100 year independent extremes. Consideration shall be given to the design of the basin walls, including but not limited to the following: a. The integrity of the walls shall remain stable when subjected to: The highest astronomical tide, plus Storm surge, plus Maximum wave crest height, corrected for shoaling and run-up if applicable. 10.2 10.3 10.4 b. c. d. e. f. 10.5 The walls shall be of adequate height to prevent overtopping, except by spray, in the above conditions. Walls shall be protected against the effects of collision, scour (including propeller scour) and wave action. The effects of ice loading shall be considered when applicable. Mooring and winching loads. Equipment /crane loads on the edges and around the edges of the basin. Pumping capacity shall be adequate for maximum seepage, rainfall (including run-off from surrounding land) and spray overtopping and allow for loss of pumps or power sources. 0001/ND Rev 1 Page 39 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS 11 TOW-OUT FROM DRY-DOCK / BUILDING BASIN 11.1 MOORING AND HANDLING LINES 11.1.1 11.1.2 If the structure is to remain afloat at moorings inside the dock or basin, then the moorings shall be designed in accordance with 0032/ND, Ref. [11], taking into account the weather criteria of Section 7. Handling lines and winching equipment shall be designed to withstand the design loads arising, assuming that handling operations are weather-restricted operations. All wires shall be designed to a safety factor on certified breaking load of not less than 3.0. Connections to the structure and to the shore shall be designed in accordance with 0032/ND, Ref. [11]. 11.2 UNDER-KEEL CLEARANCE FOR LEAVING BASIN 11.2.1 11.2.3 11.2.4 11.2.5 If the unit is likely to be at moorings in the dock or basin at maximum draught for any significant time, the effects of siltation and negative surge shall be considered. When moored in, or leaving the dock or basin, the unit shall have a minimum under-keel clearance, using tidal rise if necessary, of at least 0.5 metres for a period adequate for float-out, including contingencies. This would normally be of the order of 3 hours before, to 3 hours after high water. The planned float-out operation, excluding contingencies, should normally be planned to be completed before high water. Compressed air may be used to reduce draught if required, subject to the requirements of Section 9.8. A tide gauge shall be installed on site to check that actual tidal levels correspond to those predicted. At least 4 visible draught scales shall be painted on or fixed to the structure. 11.3 SIDE CLEARANCES 11.3.1 Depending on the positional control of the unit during the exit of the basin, the channel width at full depth should normally be not less than: 1.2 x B when inside the basin, and 2.0 x B when immediately outside of the basin, where B = maximum structure dimension, normal to the direction of travel. The required clearances may be reduced if the unit is winched out along a fendered guide. The required clearances may need to be increased if tugs are used instead of winches for control inside the basin. 11.2.2 11.3.2 11.3.3 11.4 UNDER-KEEL CLEARANCE OUTSIDE BASIN 11.4.1 Once outside the building basin the minimum under-keel clearance shall be as required by Section 14.20 of 0030/ND, Ref. [9] until final emplacement. 11.5 TOWAGE AND MARINE CONSIDERATIONS 11.5.1 Tugs, towage and marine considerations for tow out of dock shall be in accordance with 0030/ND, Ref. [9]. An exclusion zone for marine traffic should be agreed with the Port Authority and any other relevant authorities. 11.5.2 0001/ND Rev 1 Page 40 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS 12 TEMPORARY BALLASTING AND COMPRESSED AIR SYSTEMS 12.1 GENERAL 12.1.1 12.1.2 Regardless of any requirement to change draught during construction, towage or installation operations, floating structures should be fitted with a means of pumping out water from all compartments. Any special cases where this does not apply shall be agreed with GL Noble Denton and may be subject to a specific risk assessment. All ballasting procedures shall, wherever possible, be reversible so that, in case of emergency, the structure can be returned to a safe draught within 24 hours. If this is not feasible (for instance if there is an unstable phase during submergence before installation) then a risk assessment shall be carried out to demonstrate the acceptability of the system and procedures and submitted for GL Noble Denton approval. 12.2 REDUNDANCY 12.2.1 The design of the ballasting system shall be such that the failure of any one valve to open or close, or the fracture of any pipe, will not cause flooding of the unit, or failure to flood when required. All remotely controlled valves shall be capable of operation by a secondary, preferably manual system. Any automatic or radio controlled system shall have a manual override system. The secondary valve operation system may be by ROV, provided that ROV access and a suitable ROV are available at all stages of the operation. The time for the ROV to get to and operate the valve shall ensure that the valve can be operated before the flow through it is critical. Sufficient redundancy of pumps, power supplies, cross-over pipework and instrumentation shall be provided so that essential operations can continue in the event of failure of any one component or system. 12.2.2 12.2.3 12.2.4 12.3 INLETS AND OUTLETS 12.3.1 All internal and external inlets shall be adequately protected to prevent damage by entering debris and cables. All internal compartments must be cleaned of debris before immersion or towage starts. When a dry-dock or building basin are flooded before float-out, the area should be cleared to avoid the potential for blockage of piping inlets /outlets due to debris. When inlets are near the seabed, care shall be taken to avoid sucking in mud or sand that can block the pumping systems or filters. Where inlets or outlets are near the seabed, care shall be taken to avoid scour that could have adverse effects on foundations of any structure or grounded vessel, or reduce under-keel clearances. Except when in use for inlet or discharge, all openings to sea shall be protected by a double barrier. Any external valves and pipework shall be protected against collision and fouling by towlines, mooring lines or handling wires. 12.3.2 12.3.3 12.3.4 12.3.5 12.3.6 12.4 PIPEWORK 12.4.1 12.4.2 All essential pipework shall be of permanent-type construction and hydrostatically tested to a minimum of 1.3 times the design pressure. Temporary flexible hoses are not generally permitted. Where their use cannot be avoided, for instance for supply of back-up compressed air from a compressor barge alongside, then a risk assessment shall be carried out to demonstrate the acceptability of the system and submitted for GL Noble Denton approval. 12.5 UMBILICALS 12.5.1 If umbilicals are necessary to provide power and/or hydraulic services during any marine operation, adequate back-up capability shall be provided, and fail-safe systems shall be incorporated into critical controls. 0001/ND Rev 1 Page 41 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS 13 USE OF DP VESSELS 13.1 BACKGROUND 13.1.1 A DP (Dynamic Positioning) vessel is defined as a vessel that automatically maintains its position (fixed or predetermined track) by means of thruster force. A DP system means the complete installation necessary for dynamically positioning a vessel and comprises the following sub-systems: Power system Thruster system DP control system 13.1.2 A DP control system means all control components and systems, hardware and software necessary to dynamically position the vessel. The DP control system consists of the following: Computer system/joystick Sensor system Display system Position reference systems, and Associated cabling and cable routeing 13.1.3 The position and heading (either absolute or relative to another vessel) are determined from a number of independent position reference systems including DGPS, taut wire, laser based (e.g. Fanbeam or CyScan), radar (e.g. Artemis, RadaScan, RADius), acoustic transponders (e.g. ultra or super-short baseline or long base line). The position of each sensor on the vessel needs to be known so that corrections due to trim, heel etc. can be made. The results from each reference system are factored to allow for possible system errors and these factors are constantly adjusted in the light of discrepancies from the positions calculated by each other system in operation. The forces on the vessel from wind, waves and currents are also constantly calculated using the results from other sensors and these, together with the offset from the required position, are used to calculate and control the required thrust vector for each propeller or thruster to maintain position. Unknown forces on the vessel, or erroneously calculated forces, can arise from many causes including: a. Mooring or fender loads from vessels alongside b. Collisions with other vessels or structures c. Horizontal forces caused when a load is lowered onto stabbing guides on another structure or vessel. d. Forces from towing (including ploughs or trenchers) e. Helicopter down-draught affecting wind measurement sensors f. Horizontal reactions from the seabed on a jack-up leg when the leg engages with the seabed. On extracting legs, there will be a similar loss of an unknown restraining force from the soil. In each case the DP control system will tend to react against the unknown force, often producing detrimental effects. In these cases the gain for the relevant measuring system may need to be reduced, or other procedures implemented before a loss of position occurs. 13.1.4 13.1.5 0001/ND Rev 1 Page 42 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS 13.2 DP EQUIPMENT CLASSES 13.2.1 The following Table shows IMO definitions (from Ref. [29]) Table 13-1 13.2.2 Class IMO Definition 1 For equipment class 1, loss of position may occur in the event of a single fault. (This class is unlikely to be suitable for most operations approved by a MWS) 2 For equipment class 2, a loss of position is not to occur in the event of a single fault in any active component or system. Normally static components will not be considered to fail where adequate protection from damage is demonstrated and reliability is to the satisfaction of the Administration. Single failure criteria include: 1. Any active component or system (generators, thrusters, switchboards, remote controlled valves, etc.) 2. Any normally static component (cables, pipes, manual valves, etc.) which is not properly document with respect to protection and reliability. 3 For equipment class 3, as for Class 2 but a single failure includes: 1. Items listed above for class 2, and any normally static component is assumed to fail. 2. All components in any one watertight compartment, from fire or flooding. 3. All components in any one fire sub-division, from fire or flooding (for cables, see also para 3.5.1 of Ref. [29]. Classification societies have used the IMO principles of equipment class and redundancy requirements as the basis for their own DP class rules. The table below lists equivalent DP class notations attributable to the leading classification societies. Table 13-2 13.2.3 DP Equipment Classes DP Class Notations for various Classification Societies IMO Equipment Class LR DNV (DYNPOS) DNV (DPS) GL ABS BV N/A DP (CM) DYNPOS AUTS DPS 0 DP 0 DPS-O Dynapos SAM Class 1 DP (AM) DYNPOS AUT DPS 1 DP 1 DPS-1 Dynapos AM/AT Class 2 DP (AA) DYNPOS AUTR DPS 2 DP 2 DPS-2 Dynapos AM/AT R Class 3 DP (AAA) DYNPOS AUTRO DPS 3 DP 3 DPS-3 Dynapos AM/AT RS Notes: 1. The DNV DP class notations have been given as have the GL DP class notations, since at time of preparing this revision, these DP class notations have not been affected by the merger of DNV and GL into DNV GL. 2. The DP class notations on the top row relate to DP systems which have a lower level of DP capability than is required for IMO equipment class 1. Vessels with DP1 class or equivalent or, lesser capability, should not operate in DP within a 500 m statutory exclusion zone unless a suitable and sufficient risk assessment has been carried out and appropriate .provision has been made in its vessel-specific CAMO (Critical Activity Mode of Operation) and its ASOG (Activity Specific Operations Guidelines) 0001/ND Rev 1 Page 43 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS 13.3 SYSTEM DESIGN & CAPABILITY 13.3.1 Any vessel operating on DP should comply with the following: a. The DP system should be designed, equipped and operated in accordance with IMO MSC/Circ.645 – “Guidelines for Vessels with Dynamic Positioning Systems”, Ref. [29]. b. The required DP equipment class for a pipelay vessel should be in accordance with DNV-OSF101, Ref. [16] Section 10, Clause C500. c. The vessel’s DP FMEA should meet the standards of detail and analysis in the following industry guidance: IMCA M 166 “Guidance on Failure Modes and Effects Analysis”, Ref. [23], IMCA M 178 “FMEA Management Guide”, Ref. [24] IMCA M 04/04 2004 “Methods of Establishing the Safety and Reliability of DP Systems”, Ref. [18] MTS “DP Vessel Design Philosophy Guidelines”, Ref. [35]. d. e. f. A DP Capability Analysis should be provided which meets the standards contained in IMCA M 140 “Specification for DP Capability Plots”, Ref. [21] There should be a valid CMID (Common Marine Inspection Document), IMCA M 149, Ref. [22], from a recognized independent auditing organization. The vessel should have an Annual DP Trials programme which meets the standards given in IMCA M 190 “Guidance for Developing and Conducting Annual DP Trials Programmes for DP Vessels”, Ref. [25], and should provide historical evidence of having conducted Annual DP Trials. 13.4 DP2 OR DP3 CLASS 13.4.1 Vessels with DP class notations equivalent to IMO Equipment Class 3 should offer a higher level of fault tolerance than vessels with DP class notations equivalent to IMO DP Equipment Class 2. Vessels with DP Class 3 equivalent notations should be used in operations where the consequences of a loss of position are considered to have a reasonable potential to result in death, substantial structural damage or significant environmental pollution. As a general guide, operations in this category could include drilling, diving support, and heavy lift operations, and accommodation support where the DP accommodation vessel is linked by gangway to the offshore structure. The above general guide does not preclude the use of DP Class 2 vessels for these operations provided that they have been subjected to a full and detailed risk assessment and appropriate additional risk reduction measures agreed with GL Noble Denton. 13.4.2 13.4.3 13.5 OPERATIONAL REQUIREMENTS 13.5.1 Any vessel operating on DP shall comply with the following: a. The vessel should be operated in accordance with the guidance given in MTS “DP Operations Guidance”, Ref. [34], IMCA M103, “The Design and Operation of Dynamically Positioned Vessels”, Ref. [19], and IMCA M 220 “Guidance on Operational Activity Planning”, Ref. [27]. b. Where a DP Class 2 or 3 vessel is used, the vessel should be operated in such a way that it will not lose position if the vessel suffers its worst case failure. The vessel’s environmental limits should be determined by inspection of the DP capability analysis for the vessel’s worst case failure such that the vessel should not be operated in environmental conditions which exceed the environmental envelope calculated for worst case failure. c. The procedures should identify the phases of the operations which are most vulnerable to failures and the contingency actions can be taken to mitigate the consequences. d. The vessel’s procedures should give the maximum weather limitations for operating on DP for all expected types of operation. e. The vessel’s key DP personnel should comply with the competency guidelines given in IMCA M117, “The Training and Experience of Key DP Personnel”, Ref. [20]. 0001/ND Rev 1 Page 44 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS f. g. h. i. j. k. The operator of the vessel shall demonstrate that all findings from annual DP trials have been addressed in line with the provisions of IMCA M190, as follows: “A” Category Findings – for immediate attention ”B” Category Findings – for action when reasonably convenient ”C” Category Findings – for future attention/consideration. DP Mobilisation trials and checks shall be carried out before arrival at the location. The mobilisation trials should be used to verify the integrity and performance of the vessel’s DP system, including power generation, distribution and power management, propulsion and rudders, auxiliaries, DP control system, position references and sensors. DP Location Arrival tests and checks shall be completed on arrival at the location and prior to commencement of operations. The location arrival tests should include full functional tests of the DP system and check that the DP system is set up properly prior to the start of operations. The DP vessel shall be equipped with suitable position reference and sensors in accordance with the vessel’s DP class notation. Position reference systems should be selected with due consideration to operational requirements, with regard to restrictions caused by the manner of deployment, expected performance in working situations and potential conflicts when using a combination of absolute and relative systems. Consideration should be given ensuring safe working separations between DP vessels and fixed structures incorporating rotating laser measuring systems (e.g. CyScan or Fanbeam), or radar distance measurement (e.g. RadaScan or RADius) into vessel DP systems. The safe working separation should be addressed in the DP vessel’s ASOG or ASOGs of all DP vessels involved in the operation. A DP vessel should be operated in accordance with its vessel specific CAMO or TAM (where appropriate) and it’s ASOG. The CAMO sets out the most fault tolerant configuration for the DP system and its associated plant and equipment. The CAMO usually defines the most robust fault tolerant configuration of the DP system ensuring that a single point failure does not exceed the vessel’s identified worst case failure. The CAMO should be implemented during all critical DP activities undertaken by the vessel. The TAM is a risk based mode in which the DP vessel may be set up and operated, accepting that a single point failure could result in exceeding the vessel’s identified worst case failure. A TAM is usually applied to less critical activities where a risk assessment determines that the consequences of exceeding the vessel’s worst case failure are acceptable. The ASOG sets out the operational, environmental and equipment performance limits for the vessel and the specific activity the vessel is undertaking. These limits are set according to the level of risk. Where the risks are high, the limits are at their most stringent. The limits may be relaxed where the risks are low. (Refer to MTS “DP Operations Guidance”, Ref. [34], for details.). 13.6 VESSEL CLEARANCES 13.6.1 For vessels with DP class notations equivalent to IMO Equipment Class 2 and 3, when operating in DP, there should always be an adequate clearance distance between the DP vessel and the nearest point on the adjacent offshore structure, other DP vessel or other obstruction, whether above or below the surface. As a general rule the clearance distance should not be less than 10 metres. In exceptional circumstances it may be acceptable for the clearance distance to be reduced to 5 metres or less but only after a full and detailed risk assessment and the implementation of additional risk reduction measures agreed with GL Noble Denton. Vessels with a DP class notation equivalent to IMO Equipment Class 1 or lower should not be operated in DP adjacent to an offshore structure, other DP vessel or other obstruction, whether above or below the surface unless a suitable and sufficient risk assessment has been carried out and appropriate .provision has been made in its vessel-specific CAMO (Critical Activity Mode of Operation) and its ASOG (Activity Specific Operations Guidelines). 0001/ND Rev 1 Page 45 of 57 1 1 GENERAL GUIDELINES FOR MARINE PROJECTS 13.7 JACK-UPS 13.7.1 Jack up vessels that are operated in DP should have DP control system features and DP operational procedures which minimise the horizontal reaction forces at touchdown and lift off so that, as far as is possible, the thruster forces balance the wind drag and current forces. This reduces the potential for the horizontal forces or moments to be transferred from the vessel through the legs to the seafloor. See IMCA M 223, Ref. [28], for more details. An alternative is to leave a location under manual control. When leaving from alongside a surface or subsea structure, the procedures shall mitigate the risk of collision, especially if the current and/or wind and waves are pushing the jack-up towards the structure. 13.7.2 13.8 INFORMATION REQUIRED FOR APPROVAL 13.8.1 The following initial information should be submitted if approval of DP operations is required. When inadequate documents are submitted a vessel visit may be required. a. Detailed DP system description showing compliance with Sections 13.3.1 a & b and 13.4. b. FMEA showing compliance with Section 13.3.1 c. c. A DP Capability Analysis showing compliance with Section 13.3.1 d. d. CMID showing compliance with Section 13.3.1 e. e. Evidence of having conducted Annual DP Trials showing compliance with Section 13.3.1 f. f. Operating procedures showing compliance with Sections 13.5.1 a to d. These should include the CAMO, TAM and ASOG. g. Nautical Institute (or other recognised) DP Operator certificates and evidence of competence assurance of key DP personnel showing compliance with Section 13.5.1 e. h. Trials reports and close outs for annual trials showing compliance with Section 13.5.1 f. i. Records of checklists showing compliance with Section 13.5.1 g & h. j. Details of position reference systems showing compliance with Section 13.5.1 i & j. k. Documented CAMO, TAM (where appropriate) and ASOG referred to in Section 13.5.1 k. 0001/ND Rev 1 Page 46 of 57 1 GENERAL GUIDELINES FOR MARINE PROJECTS 14 DECOMMISSIONING 14.1 GENERAL 14.1.1 The same requirements should apply for decommissioning /platform removal work as for installation which are covered in: a. 0013/ND “Guidelines for Load-Outs”, Ref [2] b. 0015/ND “Guidelines for Concrete Gravity Structure Construction & Installation”, Ref. [3] c. 0027/ND “Guidelines for Marine Lifting & Lowering Operations”, Ref. [6] d. 0028/ND “Guidelines for Steel Jacket Transportation & Installation”, Ref. [7] e. 0029/ND “Guidelines for Submarine Pipeline Installation”, Ref. [8] f. 0031/ND “Guidelines for Float-Over Installations /Removals” , Ref. [10]. 14.1.2 However there can be differences in approach for: Weight control - due to lack of suitable records Structural conditions - due to corrosion and wear HAZMAT and other hydrocarbon residues Reduced value of the equipment for which more damage may be acceptable. Any such differences should be discussed on a case-by-case basis and agreed with GL Noble Denton. 14.1.3 When the operations are not covered in the GL Noble Denton guidelines then reference may be made to DNV-RP-H102 “Marine Operations During Removal of Offshore Installations”, Ref. [17]. 0001/ND Rev 1 Page 47 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS REFERENCES [1] [2] [3] [4] [5] [6] [7] [8] [9] [10] [11] [12] [13] [14] [15] [16] [17] [18] [19] [20] [21] [22] [23] [24] [25] [26] [27] [28] [29] [30] [31] [32] [33] [34] [35] [36] GL Noble Denton 0009/ND “Guidelines for Elevated Operations of Jack-Ups”. GL Noble Denton 0013/ND “Guidelines for Load-Outs”. GL Noble Denton 0015/ND “Guidelines for Concrete Gravity Structure Construction & Installation”. GL Noble Denton 0016/ND “Seabed and Sub-seabed data required for approvals of Mobile Offshore Units” GL Noble Denton 0021/ND “Guidelines for the Approval of Towing Vessels”. GL Noble Denton 0027/ND “Guidelines for Marine Lifting & Lowering Operations”. GL Noble Denton 0028/ND “Guidelines for Steel Jacket Transportation & Installation”. GL Noble Denton 0029/ND “Guidelines for Submarine Pipeline Installation” GL Noble Denton 0030/ND “Guidelines for Marine Transportations”. GL Noble Denton 0031/ND “Guidelines for Float-Over Installations /Removals” GL Noble Denton 0032/ND “Guidelines for Moorings”. GL Noble Denton 0035/ND “Guidelines for Offshore Wind Farm Infrastructure Installation” AISC: Specification for Structural Steel Buildings, 2010, (included in AISC Steel Construction Manual 14th Edition) AISC: Design Guide 17 High Strength Bolts “A Primer for Structural Engineers”; G Kulak; 2002 & 2003; DNVGL-SE-0080 “Noble Denton marine services – Marine Warranty Survey” DNV-OS-F101 – Submarine Pipeline Systems. October 2010 DNV DNV-RP-H102 “Marine Operations During Removal of Offshore Installations” IMCA M 04/04 2004 Methods of Establishing the Safety and Reliability of DP Systems IMCA M 103 The Design and Operation of Dynamically Positioned Vessels IMCA M 117 The Training and Experience of Key DP Personnel IMCA M 140 Specification for DP Capability Plots IMCA M 149 Common Marine Inspection Document IMCA M 166 Guidance on Failure Modes and Effects Analysis IMCA M 178 FMEA Management Guide IMCA M 190 Guidance for Developing and Conducting Annual DP Trials Programmes for DP Vessels IMCA M 203 Guidance on Simultaneous Operations (SIMOPS) IMCA M 220 Guidance on Operational Activity Planning IMCA M 223 Guidance for the Positioning of Dynamically Positioned (DP) Jack-up Vessels On and Off the Seabed IMO MSC/Circ.645 Guidelines for Vessels with Dynamic Positioning Systems ISO 9001 “Quality Management Systems — Requirements” ISO 19901-1:2006 – Petroleum and Natural Gas Industries “Specific requirements for offshore structures – Part 1: Metocean Design and Operating Considerations". ISO 19901-5:2005 – Petroleum and Natural Gas Industries “Specific requirements for offshore structures – Part 5: Weight control during engineering and construction”. ISO 19903:2006 - Petroleum and natural gas industries -- Fixed concrete offshore structures Marine Technology Society (MTS) “DP Operations Guidance” Part 1 and Part 2 (Appendix 1 DP MODUs, Appendix 2 – Project and Construction Vessels, Appendix 3 – DP Logistics Vessels) Marine Technology Society (MTS) “DP Vessel Design Philosophy Guidelines Part 2” Research Council on Structural Connections (RCSC), “Specification for Structural Joints Using High-Strength Bolts”; 2009 0001/ND Rev 1 Page 48 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS [37] World Meteorological Organisation, Marine meteorology and related oceanographic activities, Report no 36, “Handbook of offshore forecasting services”, prepared by The Offshore Weather Panel, WMO/TD-NO 850, 1997. All GL Noble Denton Guidelines can be downloaded from https://www.dnvgl.com/rules-standards/noble-denton-maa-rules-and-guidelines.html 0001/ND Rev 1 Page 49 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS APPENDIX A - FILLET WELD STRESS CHECKING A.1 A.2 The effective length of a fillet weld, l, should be taken as the length over which the fillet is full-size. This may be taken as the overall length of the weld reduced by twice the effective throat thickness a. Provided that the weld is full size throughout its length, including starts and terminations, no reduction in effective length need be made for either the start or the termination of the weld. The effective throat thickness, a, of a fillet weld should be taken as the height of the largest triangle (with equal or unequal leg) that can be inscribed within the fusion faces and the weld surface, measured perpendicular to the outer side of this triangle, see Figure A.1. a a Figure A-1 A.3 Effective Throat Dimension ‘a’ for Concave and Convex Fillet Welds A uniform distribution of stress is assumed on the throat section of the weld, leading to the normal and shear stresses shown in Figure A.2. σ┴ = normal stress perpendicular to the throat σ║ = normal stress parallel to the axis of the weld τ┴ = shear stress (in the plane of the throat) perpendicular to the axis of the weld τ║ = shear stress (in the plane of the throat) parallel to the axis of the weld σ║ σ┴ τ║ τ┴ Figure A-2 A.4 Normal and Shear Stresses acting on the plane of Weld Throat The normal stress σ║ parallel to the axis is not considered when verifying the design resistance of the weld. 0001/ND Rev 1 Page 50 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS A.5 The two stress conditions perpendicular to the axis of the weld, σ┴ and τ┴ may be considered to be A.6 equal in magnitude in the case where the load P acting on the bracket is applied parallel to the axis of the weld. This can be seen in the assumption in Figure A-3 that the load vectors should be drawn with the symmetry that is illustrated. The design resistance of the fillet weld will be sufficient if the following is satisfied: 2 3 11 2 2 0.5 m yield Eqn 1 Where: σyield is the yield stress of the material γm is the appropriate material factor selected A.7 A.8 Fillet Welded Bracket For a bracket subjected to a load P parallel to the weld line as shown in Figure A.3 and where the base structure to which the bracket is welded is adequately stiff the bending load applied to the weld line can be considered to vary linearly and the shearing load at the weld to be constant, as shown in the figure. In this case the maximum perpendicular load per unit weld length, fv, can be described as shown in Eqn 2. fv 6 P h A.9 1 l2 Eqn 2 The uniform shear load per unit weld length, fh, is given by fh P l Eqn 3 P h a Plane of throat of weld l a.τ┴ = shear force per unit length fv = 6Ph/(l2)= Figure A-3 0001/ND Rev 1 max bending tension per unit length Bracket connected by double Fillet Weld Page 51 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS A.10 Double Fillet For a double fillet weld as shown in Figure A.4 the force fv may be considered as being resisted by a combination of normal and shear stresses acting on the throat of the weld as illustrated in the diagram. The applied load also produces a shear stress on the weld throat of τ║ acting at right angles to the other shear stress τ┴. A.11 These stresses can be combined to form the von Misses equivalent stress (see Eqn 1). The equations for σ┴, τ┴ and τ║ are given in Eqn 4 and Eqn 5. ll 3 2 Ph al2 Eqn 4 P 2 al Eqn 5 fv = 6.P.h/(l2) a.σ┴ Fillet weld #1 Weld #2 a.τ┴ Weld #1 2 fv = 6.P.h/(l ) a.τ┴ Fillet weld #2 a.τ┴ a.τ┴ a.σ┴ a.σ┴ a.σ┴ Stresses and Resultant Forces Figure A-4 A.12 Vector Force Diagram Stresses and Forces acting on Fillet Weld The resulting limiting value for the weld throat thickness, a, is given in Eqn 6. P . a l yield m A.13 2 18 h 3 4 l Eqn 6 Single Fillet For a bracket with a single fillet weld of length l the resulting limiting value for the weld throat thickness, a, is given in Eqn 7. P . a l m yield 0001/ND Rev 1 2 72 h 3 l Eqn 7 Page 52 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS A.14 A.15 A.16 Selection of Yield Stress and Material Factor The yield stress used should be the lowest of the yield stress values of the weld itself and the two parts of metal welded together. The material factor, γm, shall be taken as 1.0. Note: The applied loads shall be increased by the following factors: 1.40 for LS1 checks where the loading is gravity dominates; also used when the exclusions of 9.2.5 apply. 1.05 for LS2 checks where the loading is dominated by environmental / storm loads. Alternative Methods An alternative approach can be found in GL Rules, 1. Ship Technology, part 1. Seagoing Ships, Chapter 3. Hull Structures, Section 19. Welded Joints. 0001/ND Rev 1 Page 53 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS APPENDIX B - BOLTED CONNECTIONS B.1 B.1.1 B.1.2 B.1.3 B.2 B.2.1 B.2.2 B.3 B.3.1 B.3.2 B.3.3 B.4 B.4.1 B.4.2 AIM AND SCOPE This Appendix offers guidance on the selection of standards suitable for use when designing and specifying a bolted connection for marine seafastenings. In addition bolt installation and tightening requirements are discussed. Due to the difficulty of inspecting the adequacy of a bolted connection after it has been made up the significance of correct preparation, installation and accurate documentation is emphasised. In bolted connections for use with marine seafastenings it is essential that there is not only adequate design and properly detailed construction drawings but also correct supervision and documentation to confirm that a bolted connection has been made correctly. Bolts that are not torqued up correctly or that need lock nuts should not be used for connections involving cyclic loading (e.g. seafastening) due to the dangers of progressive collapse. GENERAL CONSIDERATIONS This Appendix is aimed at situations where bolted connections are used in a marine environment to form a temporary connection between steel items for seafastening purposes. Traditionally cargo seafastenings have consisted of welded connections. However in some circumstances bolts are more convenient for securing cargo items as they can be removed more quickly. It is assumed that the cargo items are small in comparison to the ship or barge and that the fastening will not be required to transmit forces resulting from flexure of the supporting vessel or that if they do so these forces have been accurately determined and included in the design. Due to the typically cyclic nature of forces applied to marine seafastening connections, bolted connections which are to be used in this manner should be designed as “slip critical”, that is the load is carried by means of friction between the faying (or touching) surfaces of the items connected. The purpose of the bolts is thus to provide the necessary clamping force between the faying surfaces to ensure the friction load can be carried without slip. In this way the bolts themselves are not required to carry shear or edge bearing forces. It follows that correct installation and pretensioning of the bolts is essential. CODES AND GUIDELINES A suitable internationally recognised standard should be used for the design of slip critical bolted connections. Such a code is the AISC Specification for Structural Buildings (Ref. [13]) which deals with the design of connections in Chapter J. Section J3-8 deals with slip-critical connections. This code provides for the use of both the Load and Resistance Factor Design (LRFD) and the Allowable Strength Design (ASD) methodology. In this note the design of bolts will be illustrated using the LRFD approach. Helpful guidance in the design and specification of bolted connections is given in the AISC Design Guide 17 on “High Strength Bolts”, Ref. [14]. Specifications for bolts, washers, holes, assembly, etc. and much useful information for the design of slip-critical bolted connections is also provided in the Research Council on Structural Connections (RCSC); “Specification for Structural Joints Using High-Strength Bolts”, see Ref. [36]. BOLTED CONNECTION DESIGN STRENGTH Load Resistance Factor Design (LRFD) The following summary of some of the main requirements for bolted joint design is based on the LRFD approach presented in AISC (Ref. [13]). In LRFD design when a structure or structural component ceases to fulfil the intended purpose in some way, it is said to have exceeded a limit state. The design strength Ф.Rn is the nominal strength Rn multiplied by the resistance factor Ф. The design strength of each structural component or assemblage must equal or exceed the factored load, which is the relevant load or load combination comprising the sum of the nominal loads multiplied by load factors. The load factors reflect uncertainty in individual load magnitudes. 0001/ND Rev 1 Page 54 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS B.4.3 For marine seafastenings the load factors to be used should be those provided in Table 9-1 of these guidelines. The load factor recommended for the LS1 limit state is 1.60 and this is the appropriate value to use for the analysis of slip critical joints. The factored load must be smaller than the design resistance: Factored Load = 1.6 x Load < Ф.Rn NOTE: The requirement that bolted connections be designed using the LS1 load factor applied to the extreme loads is to account for the criticality and sensitivity of pretensioned and slip-critical joints and the fact that the design load has a significant probability of being exceeded. B.4.4 High Strength Bolts in Slip-Critical Connections Chapter J3-8 of AISC, Ref. [13], describes how for high strength bolts in slip critical connections the design slip resistance is Ф.Rn where Rn is the nominal strength of the joint and Ф, the resistance factor, with values given in the following table. Table 14-1 Resistance Factor by Hole Type Ф,(LRFD) Type of holes For standard size and short-slotted holes perpendicular to the direction of the load 1.0 For over-sized and short-slotted holes parallel to the direction of the load 0.85 For long-slotted holes 0.7 The nominal strength of the joint, Rn, is defined in J3-8 in AISC, Ref. [13], as: Rn = μ.Du.hf.Tb.Ns where: μ = mean slip coefficient for Class A or B surfaces as applicable, and determined as follows, or as established by tests. Table B-2 Slip Coefficients Type of surface μ For Class A surfaces (unpainted clean mill scale steel surfaces or surfaces with Class A coatings on blast-cleaned steel or hot dipped galvanised or roughened surfaces) 0.3 For Class B surfaces (unpainted blast-cleaned steel surfaces with Class B coatings on blast-cleaned steel) 0.5 Du = 1.13; a multiplier that reflects the ratio of the mean installed bolt pretension to the specified minimum bolt pretension. The use of other values may be approved by the engineer of record. Tb = minimum fastener tension (see Table J3.1 or J3.1M of AISC, Ref. [13]) 0001/ND Rev 1 Page 55 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS hf = factor for fillers, determined as follows: Single Filler Plate Table B-3 Multiple Filler Plates Filler Plate Factors Number of fillers hf Where there are no fillers or where bolts have been added to distribute loads in the filler 1.0 Where bolts have not been added to distribute the load in the filler: for one filler between connected parts 1.0 for two or more fillers between connected parts 0.85 Ns = number of slip planes required to permit the connection to slip. B.4.5 Combined Tension and Shear in Slip Critical Connections When a slip-critical connection is subjected to an applied tension that reduces the net clamping forces the available slip resistance per bolt as given above shall be multiplied by a factor ks as follows: ks = 1 - Tu/(Du.Tb.Nb) [LRFD type analysis] (see AISC, Ref. [13], J3-9) where: Nb = number of bolts carrying the applied tension Tu = tension force due to LRFD load combinations Tb = minimum fastener tension given in Table J3.1 or J3.1M B.4.6 Fatigue Given the cyclic nature of the loadings arising from vessel motion in a seaway, the fatigue limit state of the bolts and the connected parts shall be considered for voyages of more than 2 days i.e. approximately when the number of cycles could exceed 20,000 cycles. For further guidance on fatigue, see Appendix 3 of AISC, Ref. [13], Chapter 7 of AISC, Ref. [14] and 5.5 of RCSC, Ref. [36]. For connections that experience tension, account shall be taken of the increase in the nominal bolt loads due the effects of prying; alternatively the connected parts shall be shown to be of sufficient thickness that prying forces are not significant. AISC, Ref. [14], provides useful guidance on prying. Consideration of fatigue is particularly important for bolts in tension where relative stiffness effects can cause the cyclic load/stress range to be more pronounced than some expect, even without the consideration of prying. To ensure that the actual tensile fatigue is adequately addressed by the calculations, it is essential to ensure good fit-up of the mating surfaces and proper pretension of all the bolts. Any yielding of the bolts under extreme loading would reduce the pretension and significantly reduce the fatigue life. Where the load range is variable, the damage should be assessed using the Palmgren-Miner summation method. B.4.7 B.4.8 0001/ND Rev 1 Page 56 of 57 GENERAL GUIDELINES FOR MARINE PROJECTS B.4.9 B.4.10 B.4.11 B.4.12 B.4.13 B.4.14 Installation and inspection of Bolted Assemblies Pre-installation verification should be carried-out according to Section-7 RCSC, Ref. [36], during which tension calibration must be used to confirm both the suitability of the complete fastener assembly and the pretensioning procedure. According to these recommendations a representative sample of not fewer than three complete fastener assemblies of each combination of diameter, length, grade and lot to be used in the work shall be checked at the site of installation in a tension calibrator to verify that the pretensioning method develops a pretension that is equal to or greater than that specified. Minimum bolt pretensions are specified in Table 7.1 of RCSC, Ref. [36], It is essential that bolted assemblies be correctly stored, matched and made-up and that the correct pretension is introduced into the bolts, (see RCSC, Ref. [36], Installation, Section-8.2). Attention should be paid to providing correctly hardened washers where necessary (e.g. when oversize or slotted holes are used; when high strength bolts are used with low yield material; when Direct Tension Indicators “DTI” used in the pretensioning method), see RCSC, Ref. [36], Section 8.2.4, etc.). Faying surfaces in slip-critical joints must meet the requirements in RCSC Specification (see Ref. [36]) Sections 3.2 and 3.2.2. It is assumed due to the nature of the application that surfaces will be uncoated, hence, they shall be free of scale, except for tight mill scale, and free of coating, including inadvertent overspray, in areas closer than one bolt diameter but not less than 1 inch (25mm) from the edge of any hole and in all areas within the bolt pattern. Where faying surfaces are coated or galvanized, the requirements in Section 3.2.2.b and 3.2.2.c of RCSC, Ref. [36], shall apply. The inspection of bolted connections should be according to RCSC (Ref. [36], Inspection, Section 9.2). B.5 B.5.1 Particular Points to Note Re-use of bolts which have been pre-tensioned is not permitted by most codes. Re-use will be considered on a case by case basis, taking due account of factors including, but not limited to: The number of uses proposed and how they are recorded The means of identifying batches of bolts Whether initial pretensioning has exceeded 60% of bolt yield strength, or loads have exceeded the maximum design values. The procedure for ensuring that the required pre-tension is achieved for each use in accordance with 0 i.e. a tension calibration should be undertaken before each use and for each batch Fatigue and how the fatigue history can be measured. In general it will be difficult to justify pretension bolts re-use if the fatigue and usage history of each bolt is not known or if pretensioning may have exceeded 60% of yield. B.5.2 Gasket or other compressible materials should not be introduced within the grip of the bolted connection. Nuts should never be welded to prevent movement or loosening. B.5.3 0001/ND Rev 1 Page 57 of 57