Minimum Max-Lateness Job Scheduling: Inversion Removal Alternate Schedule with Multiple Inversions: One such schedule could be: Job 4, Job 1, Job 3, and Job 2. This schedule clearly doesn't follow the earliest-deadline-first strategy, and contains the following inversions: - Job 4 is processed before all other jobs. - Job 3 is processed before Job 2. Step-by-Step Removal of Inversions: Step 1: Move Job 4 to the end, as its deadline is the last among all jobs. Resultant Schedule: Job 1, Job 3, Job 2, and Job 4. Step 2: Address the inversion between Job 3 and Job 2 by switching their positions. Resultant Schedule: Job 1, Job 2, Job 3, and Job 4. Now, the schedule adheres to the earliest-deadline-first strategy. Conclusion: Starting with a schedule containing multiple inversions (Job 4, Job 1, Job 3, and Job 2), we systematically removed each inversion to arrive at the optimal earliest-deadline-first schedule (Job 1, Job 2, Job 3, and Job 4).