ALARM MANAGEMENT PHILOSOPHY Project Title: Project Number: SECL P.O. Number: Requisition Description: Requisition Number: Item Description: Item Number Doc.Number: □ □ West Qurna Field 2nd Phase Project SO2476 PO4500094236 Material Requisition For Integrated Control and Safety System (ICSS) 8015-0151-SECL-00-430-IN-RQ-20100 ICSS 8015-0151-22-PO-45-0009-4236-J08-00409 □ □ APPROVED REVIEWED WITH COMMENTS RESUBMIT THIS APPROVAL OR REVIEW DOES NOT RELIEVE THE VENDOR/SUBCONTRACTOR OF HIS RESPONSIBILITIES TO MEET ALL OF THE SPECIFIED REQUIREMENTS OF THE PURCHASE ORDER SIGN DATE ORIGINATOR CHECKED APPD(PR) D.K.YOON / J.S.PARK S.H.CHO K.T.KIM 09 JAN 2013 09 JAN 2013 09 JAN 2013 SAMSUNG ENGINEERING CO., LTD 00 20121218 Issue For Approval BH.HAM HK.LEE SB.LEE REV DATE DESCRIPTION MADE BY CHECKED BY APPROVED BY EMERSON PROCESS MANAGEMENT SAMSUNG ENGINEERING CO. LTD. SEOUL, KOREA LUKOIL MID-EAST LIMITED BASRAH, IRAQ [ 51 ] West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 DOCUMENT TITLE: DOCUMENT REVISION: REVISION DATE: PROJECT NUMBER: AUTHOR: Rev. : 00 Date ALARM MANAGEMENT PHILOSOPHY 00 Dec.18, 2012 3152425 Approvals: EPM: Date: Dec.18. 2012 Signature by the EPM Project Manager indicates that this document has been reviewed and approved to be issued in accordance with EPM internal quality procedures. EPM: Date: Dec.18. 2012 Signature by the Lead Engineer indicates that this document has been reviewed and approved to use as a basis for executing the West Qurna 2nd Phase Project. Customer: Date: Signature by the Customer representative indicates that this document has been reviewed and approved for EPM to use as a basis for executing the Diluted & Concentrated West Qurna Phase 2nd Phase Project. Reference Documents: Page : 2 Dec.18,2012 West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Rev. : 00 Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Date Page : 3 Dec.18,2012 Revision History: The following revision system is used: Revision "P" Preliminary issue - EPM/Customer review. Revision "00" (00, 01, 02 ... etc.) Issue For Approval (IFA). At this stage, the Customer approved the document. Revision "A" (A, B….. etc.) Approved For Construction (AFC) or Final after FAT Revision Revision Date Author Description 00 Dec.18.2012 BH.HAM Issue For Approval West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 4 Dec.18,2012 Table Of Contents: Approvals: .................................................................................................................. 2 Revision History: ....................................................................................................... 3 Table Of Contents: .................................................................................................... 4 Reference Documents................................................................................................. 6 1 Introduction ....................................................................................................... 7 1.1 2 Alarm System Philosophy ............................................................................... 9 2.1 3 Terms and Abbreviations ................................................................................ 7 Alarm Management Principles ........................................................................ 9 Alarm System Design Process ....................................................................... 12 3.1 Alarm System Category ................................................................................ 12 3.1.1 3.1.2 3.1.3 3.1.4 3.1.5 3.1.6 3.1.7 3.1.8 3.2 Alarm Selection Design Process ................................................................... 14 3.2.1 3.2.2 3.2.3 4 Emergency Planning and Response Alarms .....................................................................12 Safety Instrumented Systems Alarms ...............................................................................12 Engineered Alarms ............................................................................................................13 Operator Alarms ................................................................................................................13 Alarm Suppression ............................................................................................................13 Chattering Alarms..............................................................................................................13 Flooding Alarms ................................................................................................................13 State-Based Alarming .......................................................................................................14 Alarm Documentation and Rationalization ........................................................................14 Alarm Impact, Severity, and Response Time ....................................................................16 Alarm Rationalization Grid .................................................................................................18 Alarm System Implementation ........................................................................ 20 4.1 4.2 4.3 4.4 4.5 Operator Alarms ........................................................................................... 20 Engineered Alarms ....................................................................................... 21 Maintenance Alarms ..................................................................................... 22 External Device Health & Status Alarms ....................................................... 23 SIS Alarm Interface....................................................................................... 24 4.5.1 4.5.2 4.5.3 General..............................................................................................................................24 Pre-Alarms ........................................................................................................................26 Shutdown Alarms ..............................................................................................................26 West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 4.5.4 4.5.5 4.5.6 4.5.7 4.5.8 4.5.9 4.6 5 Dec.18,2012 Safety Instrumented Function Displays .............................................................................27 Maintenance Override Switch Use ....................................................................................27 Startup Override Alarm Suppression .................................................................................27 Deviation and Rate of Change Alarms/Alerts ....................................................................28 Conditional Alarm ..............................................................................................................28 Digital Alarm ......................................................................................................................29 Alarm Importance ..............................................................................................................30 Alarm Types and Message ........................................................................... 30 Alarm Suppression........................................................................................ 33 4.8.1 4.9 4.10 4.11 Date Page : 5 Alarm Priority ................................................................................................ 29 4.6.1 4.7 4.8 Rev. : 00 Automatic Alarm Suppression ...........................................................................................34 Alarm Filtering............................................................................................... 35 Alarm and Event Logging .............................................................................. 36 Alarm Summary ............................................................................................ 38 Alarm System Maintenance ............................................................................ 40 5.1 Alarm Performance Measures ...................................................................... 40 5.1.1 5.1.2 5.1.3 5.1.4 5.1.5 5.1.6 5.1.7 5.1.8 5.1.9 5.1.10 5.1.11 5.1.12 5.2 Alarm Performance Measures ...........................................................................................41 Design Metrics ...................................................................................................................41 Alarm Performance System ..............................................................................................45 State-Based or State-Dependent Alarms ..........................................................................45 Alarm Flood Suppression ..................................................................................................46 Emergency Shutdown Systems Special Considerations ...................................................47 Duplicate Alarms ...............................................................................................................48 Consequential Alarms .......................................................................................................48 Chattering Alarms..............................................................................................................48 Alarm Handling for Programs ............................................................................................49 PCS System Status Alarms ...............................................................................................49 Tag and Program References to Alarms ...........................................................................49 Management of Change ............................................................................... 50 West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 6 Dec.18,2012 REFERENCE DOCUMENTS Document No. Document Name Purpose EEMUA -191-1999 Alarm Systems – A guide to design, manage and procurement – publication no 191-1999 Alarm guidelines ISA/ANSI – 18.2 – 2009 Management of Alarm Systems for the Process Industries Alarm guidelines Alarm Management Hand book – Bill Hollifield and Eddie Habibi General reading on alarm management practical aspects West Qurna Field nd 2 Phase Project (Early Oil Phase) 1 Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 7 Dec.18,2012 INTRODUCTION This document covers following aspects on DeltaV alarm philosophy and management for the WQ-2 project Alarm System Philosophy Describes what the system is intended to do and the principles of how the system will be designed and implemented Alarm System Design Process Describes what the alarm system includes and the process that is used to define the alarm settings, alarm priority, required operator actions, maximum response time, and alarm suppressions Alarm System Implementation Effective presentation of information during normal operation and during complex process conditions such as plant upsets or trips. As a result of alarm system implementation, a large number of nuisance alarms, and duplicate alarms will be removed or avoid. Alarm System Maintenance System performance measurements in place to drive improvements using a management of change process. The intent is to make the alarm system sustainable 1.1 Terms and Abbreviations Table 1-1 and Table 1-2 below provides the list of the major terms and abbreviations used throughout this project. Term Description Acknowledged Alarm An alarm condition currently exists, the operator is aware Active Alarm An alarm condition currently exists Alarm A abnormal condition that must be brought to the operators attention and require the response Alert A signal to brought the operators aware about the condition, but that it is no response immediate Automatic Suppression Automatic action that automatically prevents alarm annunciation during temporary situations. See also “Suppressed Alarm” Cleared Alarm An alarm condition has returned to normal Consequential Alarm An alarm that always occurs because of or as a consequence of another alarm or state change. West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Term Rev. : 00 Date Page : 8 Dec.18,2012 Description Disabled Alarm An alarm that is prevented from being propagated to the operator (and logging system) i.e., the alarm propagation logic is disabled Device Smart field instrument Event Log Table containing a time stamped list of events recorded by the control system Inhibited Alarm As same as Disabled Alarm Log An entry placed in the event log for historical purposes Manual Disable Supervisor action that temporarily prevents alarm detection or propagation. Automatic restoration does not occur. See also “Disabled Alarm” Suppressed Alarm An alarm that is temporarily prevented from annunciating, both audibly and visually by lowering its priority to “log only”. Un-Acknowledged Alarm An alarm condition currently exists, the operator is not yet aware Table 1-1 Terms Abbreviation Description AOA Alarm Objectivity Analysis EEMUA The Engineering Equipment and Material Users Association ESD Emergency shutdown system Emerson Emerson Process Management, Hydrocarbon and Energy Industry Centre ICSS Integrated Control and Safety System I/O Input/Output PCS Process control system SIS Safety Instrumented System Table 1-2 Abbreviations and Acronyms West Qurna Field nd 2 Phase Project (Early Oil Phase) 2 Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 9 Dec.18,2012 ALARM SYSTEM PHILOSOPHY Every alarm should identify to the console operator an abnormal, unsafe, and urgent plant condition that requires them to take action or to make an assessment of the unit’s condition so that, where possible, they can avoid or minimize plant upset, asset, or environmental damage, and improve safety. An alarm is not A reminder for the operator to complete a task A mechanism to help perform routine surveillance of the plant The purpose of the alarm system is to assist the operator in detecting process problems and prioritizing their response. All alarms and shutdowns shall annunciate via the operator stations in the control room. Supplemental annunciation devices such as beacons and horns shall be used to annunciate gas or fire detection or facilitate evacuation within the plant. An alarm system monitors plant conditions and informs the operator of significant changes that require assessment and action. The alarm system helps the operator Maintain the plant within a safe operating envelope. The alarm system should help the operator correct problems from escalating. Identify deviations from operating conditions that could lead to financial loss. For example, pump damage from cavitation. Better understand complex process conditions such as during plant upsets or trips. The Alarm Help functionality within DeltaV provides the operator with information related to specific alarms.Each alarm can be configured by the plant engineering and operations groups to provide Alarm Help information when the alarm is active.The Alarm Help functionality will assist the WQ-2 Project,facility in complying with alarm system management requirements related to the ISA 18.2 standard for alarm management. 2.1 Alarm Management Principles Every alarm shall be subjected to following three questions West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 10 Dec.18,2012 1. Does the event require operator action? 2. Is this alarm the best indicator of the situation’s root cause? 3. Is this alarm resulting from a truly abnormal situation? The following two basic rules shall be adhered to 1. Events that do not require operator action shall not be allowed to produce alarms. 2. Alarms must be produced upon abnormal situations only, not from normal situations. The following principles shall guide the design of the alarm system All alarms require operator action. Every alarm, regardless of its priority, is important. Operator corrective action information is easily accessible from the operator interface. Alarms present information that is Relevant to the operator’s role at the time. Easy to understand. Important to the operators. Presented at a rate that is effective for the operator. Alarms assist operators in the management of the plant in terms of safety, environmental, production and plant assets. Alarms identify deviations from desired operating conditions that could lead to financial loss such as off specification product or low efficiency operation Alarms are designed to provide sufficient time for the operator to respond Alarm information (as a key component of the control system’s integrated operator interface) provides a clear navigational aid and prioritized response aid to the operators Alarms are categorized and prioritized using a structured review process aimed to meet the operators’ requirements The alarm design is documented and includes alarm limits, priorities, causes, consequences, correct actions, response time, and verifying information West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 11 Dec.18,2012 Changes to alarms are managed under a management of change (MOC) work process. All of change must be evaluated, analyzed properly and communicated to all affected personnel and team Nuisance alarms, unnecessary alarms and duplicate alarms shall be reduced or avoid during alarm system implementation The organization establishes a continuous improvement and performance monitoring process to support the alarm system An alarm system champion is assigned responsibility for the alarm system in each area of the plant West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 3 ALARM SYSTEM DESIGN PROCESS 3.1 Alarm System Category Rev. : 00 Date Page : 12 Dec.18,2012 The categories of alarms ranked in their order of importance are 1. Emergency Planning and Response (fire and gas, deluge, safety showers, evacuation, etc.) 2. Engineered alarms 3. Operator alarms 3.1.1 Emergency Planning and Response Alarms The following emergency planning and response alarms require panel operator action. These alarms will have high priority. Fire and gas Deluge Safety showers Evacuation 3.1.2 Safety Instrumented Systems Alarms Safety instrumented alarms have been selected by the process design team to ensure the safety of the plant and to prevent equipment damage.These alarms will be implemented in the safety instrumented systems and will identify when an automatic action has been initiated due to a severe abnormal condition in the plant.Pre-alarms will provide the plant operators with sufficient warning of the impending trip condition so that corrective actions can be taken to avert the situation.The pre-trip alarms may have higher priority than the trip alarms.The priority of the SIS alarm will be assessed using same alarm priority rationalization grind used for the PCS alarms.The alarm limits will be preset and not permitted to be changed without the appropriate management of change process, considering the safety life cycle (see ANSI/ISA S84.01 1996). West Qurna Field nd 2 Phase Project (Early Oil Phase) 3.1.3 Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 13 Dec.18,2012 Engineered Alarms Engineered alarms have been determined through the HAZOP reviews of the process design.These alarms settings will identify when the process is moving towards an unsafe operating condition.The alarm limits will be pre-set and not permitted to be changed without the appropriate management of change process review. These alarms are provided in the alarm and trip settings document.This document will be used as the basis for alarm objectivity analysis. 3.1.4 Operator Alarms Operator alarms are operator configurable alarms to assist in running the plant more efficiently. These alarms should never be safety related or related to some other condition that has a serious impact on the plant or its surroundings since such conditions are properly dealt with in the engineering alarms settings or other protective systems. An alarm priority called “operator” will be introduced in the system which will be lower than the low alarm priority. 3.1.5 Alarm Suppression Alarm suppression is the way to temporarily disable annunciation of an alarm in the DeltaV Operator Interface. This means that the suppressed alarm will not set off the workstation alarm horn and will not be displayed in the alarm summary or the alarm banner, but this alarm will still be registered in the alarms/events log. 3.1.6 Chattering Alarms Appropriate deadband must be selected for all alarms that are activated repeatedly over a short period of time.This may involve the programming of a deadband for analog trip values and a delay time for digital points. Concepts of on-delay, off-delay, and deadband are explained in Section 5.1.9 of this document. 3.1.7 Flooding Alarms Flooding alarms are several alarms that are shown to the panel operator on the alarm summary that allow the operator to take appropriate action over the process. West Qurna Field nd 2 Phase Project (Early Oil Phase) 3.1.8 Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 14 Dec.18,2012 State-Based Alarming Most alarms in a process unit pertain to the normal operating state of a piece of equipment. Equipment often has several normal, but differing, operating states. PCS alarm capabilities are normally only for a single-state, single-value trip points, and priorities. Examples include startup, shutdown, product or feed grade changes, half rate operation, etc. 3.2 Alarm Selection Design Process The selection of alarms and their configuration settings in the control system are critical to its success. Configuring too many alarms can lead to alarm system problems such as alarm floods and high nuisance alarm rates, which can cause the operator to miss critical alarm information. Not identifying or inappropriately setting an alarm limit on an important parameter in the process can lead to an unsafe plant condition or an economic loss for the company. The design process for the selection of alarms and their settings will use a systematic, structured analysis consistent with the overall alarm philosophy and plant risk assessment. This structured analysis will capture the alarm proposals coming from design engineering and the operational groups, and is called the alarm objectives analysis (AOA) or alarm documentation and rationalization (D&R). The D&R methodology is described below. 3.2.1 Alarm Documentation and Rationalization Documentation and rationalization (D&R) is a sound, consistent, and logical methodology by which alarms are determined and prioritized. Alarms resulting from the methodology are said to be “rationalized”. D&R is used in the following ways To reduce, on an existing system, the number of configured alarms and thus the alarm load created from them To correct a misconfigured system for performance improvement To insure consistency in alarm settings To eliminate duplicate alarms To insure proper and meaningful priority and trip point settings To configure alarms on points added or modified by projects In conjunction with PHA revalidation if alarms are specified West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 15 Dec.18,2012 To verify proper configuration of nuisance alarms as they are identified To create the master alarm database, used as a reference for statebased alarm management, flood alarm suppression, and audit/enforce mechanisms During a unit rationalization, all alarmable PCS points shall be rationalized, along with any other systems which provide alarm or abnormal situation notification to the board operator. The impact, severity, and response time matrices defined in the next section should be used to rationalize each alarm and will be documented in the results. Background information on the matrix components (impact assumptions, severity, etc.) should also be provided in the documentation for future reference. Any deviation from the alarm priority, as defined in the rationalization matrices, must be identified during the course of the rationalization and documented. For proper rationalization, it is a recognized best practice that the following groups participate Operations technicians (operators) Production and/or process engineers familiar with the process Safety and environmental (part time as needed) Process control (part time as needed) PCS specialists Other individuals with knowledge of the process unit, its operation and specific equipment, its advanced control schemes, unit hazards, and the alarm philosophy will be needed periodically. The entire team must understand the alarm philosophy before starting the rationalization. Documents required for a thorough rationalization include Unit P&IDs Operating procedures PCS configuration database Results from HAZOP or PHA reviews PCS graphic printouts Process control and safeguarding narrative All rationalized process alarms within an operating unit should be documented. The documentation should include all information required to define the alarm, its purpose, and the data required for rationalization.For new projects and West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Rev. : 00 Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Date Page : 16 Dec.18,2012 incremental changes to the unit, full alarm justification and documentation should be provided as part of the project scope, accompanying any other required project documentation (for example, MOC documents). For ease of access and maintainability, the alarm system documentation should be maintained through a uniform electronic database system across the entire clients’ site As a minimum, the following items will be documented for each alarm Possible causes of the alarm Operator response or recommended corrective actions for the alarm Potential consequences if the operator does not respond to the alarm (or, if the alarm were not present) Time available for operator to respond and mitigate identified consequences The reasons for over-riding priority recommendations determined by the rationalization principles Operations should have on-demand access to the above documentation of the alarm system, preferably electronically, in the form of a master alarm database. The master alarm database has several other important uses, particularly for alarm auditing and settings enforcement. 3.2.2 Alarm Impact, Severity, and Response Time Key aspects for the selection of alarm priorities are Alarm priorities will be set for three levels of urgency (low, medium, high) based upon The potential consequences (safety, environmental, production, and plant assets) that the operator could prevent by responding appropriately The time available for the operator to carry out the required response All alarms (regardless of priority) are important and require operator attention Impact Category Safety None Minor Major Severe Any alarm wherein the failure of proper action to be taken can result in likely harm to a person will be prioritized as “high.” Assumption is that other layers of protection operate. West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Impact Category None Environmental No Effect Minor Minimal exposure. No impact. Does not cross fence line. Contained release. Little, if any, clean up. Source eliminated. Negligible financial consequences. Event Type “Recordable”, No reporting to Alberta Rev. : 00 Date Of Production Loss No loss Event costing <$100,000, notification only at operations superintendent level Dec.18,2012 Major Severe On-site H2S or other release. Contamination causes some non-permanent damage. “Event Type Reportable”, incident reported as not violating permit. Uncontained release of materials with major environmental impact and possible third party impact. Widespread neighbor complaints. Exposed to life-threatening hazard. Disruption of basic services. Impact involving the community. Catastrophic property damage. Extensive cleanup measures and financial consequences. “Event Type Reportable” incident reported as violating permit. Isolated neighbor complaints. Costs or Value Page : 17 Event costing loss of ~ half day production, notification at operations manager level Event costing >$n,000,000 (approximately one day production volume), notification above operations manager level Table 2 Alarm Rationalization Consequence Grid The assumptions in Table 3 below were considered while preparing the alarm rationalization consequence grid above. Assumption Description Probability It is inappropriate to consider probability in an alarm rationalization consequence grid. The assumption is that the alarm (however improbable the process situation) has occurred. The consequence to be considered is the event that will take place if the alarm is ignored. Alarm rationalization is not a PHA, or SIL, or LOPA review. Such probability and risk analyses are used to determine the need for redundancy in a system, not the priority of an alarm when an event does happen. Multiple Failures It is inappropriate to assume multiple cascading failures in discussing an alarm consequence scenario. This is best explained by an example. Consider a vessel that has a high pressure alarm. The vessel has a pressure relief device which is routed to the flare that actuates above the high alarm setting. During rationalization, it will be assumed that all protective systems (for example, pressure relief devices or other independent alarms) are active and functional. Failure to respond to the high pressure alarm would therefore have environmental West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Assumption Time to Respond Rev. : 00 Date Page : 18 Dec.18,2012 Description (flaring) and/or economic (loss of product to the flare) impacts, but no personnel safety impact. In terms of setting the appropriate alarm priority, it would not be appropriate to say that the consequence would be that in the high pressure scenario, the relief device would also fail, the vessel would rupture, and personnel could be injured (i.e. a personnel safety impact). Maximum time to respond is the time within which the operators can take action(s) to prevent or mitigate the undesired consequence(s) caused by an abnormal condition. This response time must include the action of outside personnel following direction from the console operator. To clarify, this is not how long it actually takes the operator to take the action. It is how much time is available to take effective action from when the alarm sounds to when the consequence is unavoidable. The board operator’s ability to respond to an alarm in a timely fashion determines the degree of success in preventing loss. The consequences of an uncorrected alarm generally worsen with the passage of time. During an abnormal condition, the board operator is confronted with making decisions on numerous tasks that must be performed in an appropriate sequence. The timing and the order of executing these tasks determines the outcome of the operator’s effort. For example, if two process variables are deviating from normal and can potentially cause the same significant loss, the operator must quickly decide which variable to address first. In such a case, the operator must take action to address the variable that is more volatile or can reach the point of loss in the shortest time. Therefore, the shorter the time available to respond, the higher the priority of the alarm will be, assuming equal consequences can result. For each alarm being rationalized, and, for each area, the maximum time allowable to respond will be identified. This value will allow the response time to be placed in one of the following response time classes: greater than 30 minutes 10 to 30 minutes 3 to 10 minutes less than three minutes Table 3 Assumptions 3.2.3 Alarm Rationalization Grid The alarm rationalization grid for WQ-2 Project is derived based on severity of consequence and the time to response and is given in Table 4 below. This grid will be used in identifying the priority of engineering alarms. West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Page : 19 Date Dec.18,2012 Potential Consequences Urgency/Response Time No Effect Production/Quality Plant Asset/Reliability Safety/Environmental >30 min No alarm Re-engineer alarm Re-engineer alarm Re-engineer alarm 10-30 minutes No alarm Low Low Medium 3-10 minutes No alarm Low Medium Medium Less than three minutes No alarm Medium High High Table 4 Alarm Rationalization Grid Include threshold for not alarming to over 30 minutes. In such a case, the alarm should be redesigned to require action in a shorter time frame. Some exceptions are acceptable. Note that a maximum time allowable to respond of greater than 30 minutes does not meet the criteria for an alarm. While an operator may have a “time horizon” of several hours or more in adjusting process parameters and monitoring their effects, it is inappropriate to sound an alarm for which no action is required for more than 30 minutes. Alarms are to signal conditions that require quick action and must have a characteristic of urgency. Something that can be avoided for more than a half hour with no effect is not an event requiring quick action. This is not an absolute principle, and there will be exceptions. For example, an alarm of the failure of a system that acts to protect the long-term health of equipment, such as a corrosion inhibitor addition system. Failure to take action on the alarm might not have consequences for weeks or months, but the system is needed and the failure must be addressed, not forgotten about. The general rule is that response to such an alarm should be the initiation of a maintenance request before the end of the shift. The need for the alarm system to retain a sense of urgency allows for such exceptions. West Qurna Field nd 2 Phase Project (Early Oil Phase) 4 Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 20 Dec.18,2012 ALARM SYSTEM IMPLEMENTATION The alarm management features in DeltaV are structured for the effective management of the alarm system. Alarm priorities, alarm types, alarm suppression, alarm filtration, conditional alarms, operator alarms, engineered alarms, and plant areas all affect the way the system manages individual alarms. This section describes these systemwide concepts. Alarms from third party packages will be communicated to PCS over a serial link or OPC and will be time stamped and logged into the event chronicle of the DeltaV HMI in the same way as PCS alarms. Each package may have a different alarm area as defined in the configuration specification. There are 100 plant areas available in the DeltaV database and each area may have the same or different alarm priority. 4.1 Operator Alarms Individual operators have a need for “on-the-fly” configuration of various system reminders and functions. For example, tank levels when filling or transferring, where the alarm limits do not correspond to the amount desired to be moved. Operator change of the overall alarm system trip points has been proven to be a problematic practice. The setting of individual preferences as alarm limits results in sub-optimization of the process, causes shift-based process variation, introduces non-rationalized alarms, and contributes to alarm floods, and is therefore not in keeping with best practices. WQ-2 Project , may address this need and problem by providing the “operator” priority alarm. The settings and existence of these is controllable by the operator. They are not “rationalized”. The same principles as for regular alarming, however, should be followed, such as operator alarms being configured only for events requiring action. Operator alarms should not be used to replace surveillance of the process (“running by alarms”). During periods of engineered alarm activation, the operator alarms can be filtered from the alarm summary display and not interfere with the proper response to rationalized alarms. There are six operator alarms available per PCS control loop. West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Page : 21 Date Dec.18,2012 By default, these alarms are disabled from the system configuration. As the systems are being commissioned, the control room operator can enter valid alarm limits and enable the alarm as required to operate the process. Alarm deadband is defaulted to 0.5%. Alarm Name Operator Control Default Enable Default Alarm Limit % of Scale Allowable Priority Choice Description HI_HI_ALM Y N 90 Engineer Engineer high-high alarm HI_ALM Y N 80 Operator Operator high alarm LO_ALM Y N 20 Operator Operator low alarm LO_LO_ALM Y N 10 Engineer Engineer low-low alarm DV_HI_ALM Y N 5 Operator Operator deviation high alarm DV_LO_ALM Y N -5 Operator Operator deviation low alarm Table 5 Summary of Operator Alarms Table Title Indicates the default values if the alarm is not enabled on P&ID and control narrative otherwise valid values are entered. 4.2 Engineered Alarms Engineered alarms are not alterable by the operator. They are to provide warning of conditions that require operator action in order to avoid a recognized consequence. There are six engineered alarms available per PCS control loop and indicator point. The deadband for all engineered alarms and will be set at 0.5 % of the engineered scale by default. Alarm Name Operator Control Default Enable Alarm Setpoint % of Scale Priority ENG_HI_ALM N ENG_LO_ALM N Description N* All are determined via rationalization All are determined via rationalization Engineered high-high alarm N* “ ” Engineered high alarm West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 22 Dec.18,2012 ENG_HI_HI_ALM N N* ” ” Engineered low alarm ENG_LO_LO_ALM N N* ” ” Engineered low-low alarm ENG_DV_LO_ALM N N* ” ” Engineered deviation high alarm ENG_DV_HI_ALM N N* ” ” Engineered deviation low alarm Table 6 Summary of Engineered Alarms Table 6 Indicates the default values if the alarm is not enabled on P&ID and control narrative otherwise valid values are entered. Time Base hh:mm:ss Process Variable KPa Prorate PV for 60 Seconds Deviation Alarm Note: 5 Second Scan for PV 12:00:00 50 12:00:05 50.1 Abs (50.1-50)* (60/5) = 1.2 Clear Clear 12:00:10 50.2 Abs (50.2-50.1)* (60/5) = 1.2 Clear 12:00:15 51.1 Abs (51.1-50.2)* (60/5) = 10.8 Active unacknowledged 12:00:20 51.1 Abs (51.1-51.1)* (60/5) = 0 Clear unacknowledged 12:00:25 52.6 Abs (52.6-51.1)* (60/5) = 18 Active unacknowledged 12:00:30 52.5 Abs (52.5-52.6)* (60/5) = 1.2 Clear unacknowledged Table 7 Deviation Alarm Example 4.3 Maintenance Alarms There will be MAINT_HI, MAINT_LO. The MAINT priority will not show on the operator’s normal alarm summary display. West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 23 Dec.18,2012 All instrument malfunction/diagnostics which are not applicable to operator action (for example, many fieldbus diagnostics) shall have a MAINT priority. Instrument malfunction alarms that do require operator notification will become a part of PV_BAD alarms and their priority is determined during alarm objectivity analysis. Operator response to those will be an attempt at troubleshooting, then either writing a work order, or calling out for immediate maintenance (based upon a list of important instruments and operator judgment) The following priorities are recommended for various devices 1. Diagnostics on PCS hardware, such as redundant power supplies, redundant communications boxes, redundant controllers, etc – MAINT_HI, possibly on immediate maintenance callout list. 2. Diagnostics on externally connected complex hardware, such as analyzers / surge controllers MAINT_HI. Provide support diagnostics that explain the relevance to the operator. 3. Instrument malfunction alarms that do not require operator notification shall have MAINT_LO. 4. Investigate alarm group displays for PVBAD. 5. Others (case by case, default is MAINT_HI). 4.4 External Device Health & Status Alarms External systems such as analyzers, surge controllers, equipment cabinets, PLCs, and ESD logic solvers are often connected to the PCS directly or via serial, Modbus, or similar methods. It is common for these systems to have multiple health status indicators. Often these are all individually alarmed, which is not a best practice.The best practice is that System Health & Status Alarms shall be shown on control console by difference levels of pictures. The operator responses to an external device’s health/status alarms should include the following Understand the new limitations of the connected device relative to the alarm produced. (Is the device failure, fault, or still functional? Can the readings be trusted or are they suspect?) West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 24 Dec.18,2012 Act accordingly as per procedures. For example if the analyzer is no longer functioning, begin manual sampling Involve maintenance or staff as appropriate per procedure, based on the particular problem Proper alarm configuration is to provide a single “common trouble” point indicating an “OR” from several status inputs. This common point is alarmed for the operator. Grouping the status points into more than one, but still a small number, of logically-related common trouble points is also acceptable. For example, multiple vibration instruments on the compressor should be combined into a common vibration trouble point based upon any of them reaching a particular value. All are logged, but only the common trouble point is alarmed. Additionally there could be an oil system common trouble point being fed from several oil-related inputs. The individual status points feeding the common point shall be configured with LOG priority (if it is desired to record their individual time of activation). For all such common trouble points, provide detailed displays that show the status of all of the health indicator inputs. This should then be the associated display for the common trouble point. The graphics should also indicate the functional groups to contact for repair, based on the failure type. 4.5 SIS Alarm Interface Alarms from the SIS will be time stamped and logged into the event chronicle of the DeltaV HMI in the same way as PCS alarms. Only a brief discussion is given for SIS alarms here. Please refer to SIS configuration specification for more detail. 4.5.1 General Prior sections of this document refer to various types of alarms (operator, engineered, conditional). It is important to understand that, for safety reasons, all the safety pre-alarms and shutdown alarms are considered to be engineered alarms. There is no provision to modify these alarms from the DeltaV HMI, nor is there a manner (outside the proper overrides) to bypass or turn off these alarms. All alarm values for an input device shall be visible from the faceplates on the HMI for that device. Deadband values and range settings are treated in a similar manner. West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 25 Dec.18,2012 Shutdown alarms (also referred to as “trip alarms”) shall not be suppressed by maintenance overrides. Pre-alarms (also referred to as “pre-trip alarms”) shall also not be suppressed by maintenance overrides. SIS Alarms shall be annunciated on the DeltaV HMI alarm banner and alarm list. The application of ISA S84 or Licensor Design Standards may require the installation of double or triple redundant sensors and alarming in some instances. This may or may not involve “voting” systems. During process upsets and abnormal situations, the multiple alarming provided may produce undesirable multiple alarms from the same event. In addition, routine shutdowns may result in the activation of several alarms, adding a large number of alarms to the alarm summary. Such nuisance alarms must be avoided if at all possible. All redundant and voting installations must be designed and reviewed on a case-by-case basis to ensure minimal multiple alarms result from process deviations the operator will not receive a flood of unnecessary alarms during routine startup, shutdown, or other periods when the hazard scenario is not valid pre-trip or trip conditions will not create multiple alarms from different sensors The case-by-case review of these redundant installations may require further study outside of the normal alarm system documentation and rationalization process. Safety considerations inherent in these redundant installations may necessitate dynamic alarm changes in the logic solver equipment, instead of in the PCS. There are several techniques to provide the degree of safety provided by sensor redundancies and separate logic solvers, without producing excessive alarms. For example, voting logic within the PCS can be considered for alarm actuation. Annunciation of ESD bypasses must be considered carefully for proper priority selection. It may well be that rationalization shows that the pre-alarm to a trip might be a higher priority alarm than the trip notification alarm (for example, “the shutdown has occurred”). This is perfectly acceptable. At the pre-trip point, the operator can still take effective action to avoid the trip, which may have avoidable major West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 26 Dec.18,2012 consequences. These consequences can no longer be avoided once the trip occurs. The consequences of ignoring the trip notification alarm at that point may make the trip-caused upset worse if the operator fails to take the correct post-trip actions. The voted alarm result must be clear and easily understood by the operator. Consider voting logic output to a dedicated, alarmed flag, or discrete tag on the PCS. The operating schematics or graphics must be designed to properly indicate the voted result and the status of the multiple initiators, to prevent operator confusion and provide rapid assessment and verification. In the event of equipment trips with several possible causes: alarm the overall trip event trip initiators may not need alarms log initiator activation for historical analysis provide adequate first-out or interlock initiator display to allow the operator to identify the trip cause 4.5.2 Pre-Alarms Pre-alarms shall give the operator the opportunity to take corrective action before a process shutdown occurs. Reset action is not required, and prealarms should not be defeated by maintenance overrides. A device that is in pre-alarm shall be prioritized by the AOA team. Pre-alarm acknowledgement is purely an HMI function, and once acknowledged the device shall appear as solid alarm colour (non-flashing). If the device reverts to normal before the operator has acknowledged the alarm, the device shall flash in hatch alarm colour. 4.5.3 Shutdown Alarms Shutdown initiators shall be trapped so that the operator, when troubleshooting, can always find the source of the shutdown (in the event that the initiating condition is only present for a short duration). Reset action is required. Shutdown alarms are not defeated by maintenance overrides (although the actual trip is prevented in such a case). West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 27 Dec.18,2012 A “ready to reset” button shall be provided. This button will alert the operator that the initiating condition(s) are normal (the deadband is satisfied) and the interlock is ready to be reset. A device that is in shutdown and has high priority when in alarm shall appear flashing red on the HMI process screen. Shutdown alarm acknowledgement is purely an HMI function, and once acknowledged the device shall appear as solid red (non-flashing). Shutdown alarms may be ganged for large pieces of equipment to reduce alarm flooding. For example, a common furnace shutdown may be generated on a furnace trip. The operator will use the safety instrumented function displays to diagnose the cause of the problem. 4.5.4 Safety Instrumented Function Displays A display scheme will be utilized for shutdown interlocks that have multiple initiators. This shall be displayed on the HMI screens in specialized Level 3 displays. The format of these screens is addressed in the SIS configuration specification. 4.5.5 Maintenance Override Switch Use Maintenance override switches (MOS) are used to put a device into maintenance mode. They are also referred to as class ‘A’ overrides. A maintenance person typically puts a device into maintenance bypass when the device is to be repaired or calibrated. All safety shutdown initiators will be provided with a maintenance override switch (MOS). Pre-alarms and shutdown alarms associated with the sensor will not be disabled while the maintenance override switch is engaged. For SIL 2 and 3, shutdown alarms the setting of a maintenance override notification alarm shall be initiated whenever something is in MOS. This prevents the operator from unknowingly leaving a device in MOS (the MOS notification alarm cannot be suppressed and therefore cannot be ignored). 4.5.6 Startup Override Alarm Suppression In programming terms, overrides/bypasses/permissive are typically classified into three categories or classes class A, B, and C. Class A overrides are West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 28 Dec.18,2012 typically maintenance type overrides, and are analogous to the MOS discussed in the previous section. Shutdown initiator overrides are often required for start-up. A typical example would be for low flow shutdowns. MOS should not be used for such purposes, since the application of these overrides would adversely affect the availability calculations and hence safety. An operational override shall be used for these requirements, and the override automatically de-activates under predefined conditions. For the above low flow trip the operational override would have a time-out function. In programming terms, this would be called a class B override. In some cases it may be that the trip may need to return to a normal process condition before de-activating. These types of overrides are referred to as a class C override. Some of these operational override need detailed process information. An example would be the isolation of a feed to storage under high temperature conditions. Since the lines are insulated the material may take some time to cool down. There may be a conditional override based on another temperature (a class C) together with a timed bypass (class B). While a device is in a startup override mode (class B or C), the shutdown alarms and pre-alarms shall be inhibited. When a process is intentionally stopped, either through automatic logic or manually, alarms that would normally be suppressed during startup are also viewed as nuisance alarms while shutdown. Therefore, when a process is intentionally stopped and an initiating device would cause an alarm, that alarm will be inhibited by the SIS. 4.5.7 Deviation and Rate of Change Alarms/Alerts In addition to the internal system diagnostics for initiators, the application will also include custom diagnostic logic to detect out-of-range or faulted status, flat-line and high rate-of-change conditions, and deviation. Depending on the nature of the alarm/alert and which system the equipment is in, either the PCS or SIS will generate the alarm/alert. Refer to SIS Configuration Specification for further details. 4.5.8 Conditional Alarm The DeltaV conditional alarming feature provides the ability to easily add alarm time delays and enable/disable alarms to minimize nuisance alarms. This is West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 29 Dec.18,2012 functionality available to the PCS and SIS, however it is only available in the SIS in certain cases. Refer to the SIS Configuration Specification for further detail. 4.5.9 Digital Alarm The DeltaV Digital Alarm will be from the digital input like Pressure, Level, Limit switchs or another type on discrete input in PCS or SIS system.There will be indication to the operator on the Level-3 process graphics 4.6 Alarm Priority There are 12 possible alarm priority levels numeric values 4 through 15.The highest priority value is 15 (it is used for the most important alarm). The lowest priority value is 4. The alarm priorities configured for WQ-2 project are given in Table 8. An operator display will provide a list of all PCS module alarms currently suppressed at any point in time. The operator cannot disable or suppress engineered alarms. Maintenance alert information will use two of the alarm priorities.This information will not be shown on the alarm summary. Priority CRITICAL WARNING ADVISORY Priority in DeltaV Priority Level Auto Acknowledge Auto Acknowledge Inactive Horn Sound S_CRITICAL 15 NO NO YES E_CRITICAL 14 NO NO YES F_CRITICAL 13 NO NO YES F_WARNING 11 YES YES None D_CRITICAL 10 YES YES None D_WARNING 9 YES YES None ADVISORY 7 YES YES None Table 8 Alarm Priority Settings West Qurna Field nd 2 Phase Project (Early Oil Phase) 4.6.1 Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 30 Dec.18,2012 Alarm Importance The acknowledged status of the alarm, the current alarm state, the priority value, and the time stamp on the alarm determine the alarm's importance in the system 1. Unacknowledged alarms have a higher importance than acknowledged alarms. 2. After the acknowledgement status is considered, alarms that are still active are considered more important than alarms that have already cleared but have not been acknowledged by the operator yet. 3. When more than one alarm has the same acknowledgment status and active status, alarm with higher priority value has the highest importance. When more than one alarm has the same priority value, active status, and acknowledgment status, the newer alarm has a higher importance. For example, the most recent, acknowledged, active alarm with a priority value of 15 is the most important alarm in the system. Then, a new alarm occurs that is unacknowledged and has a priority value of 7. This new alarm is of higher importance than an acknowledged alarm with a priority value of 15 because of the acknowledgement status of the alarms. 4.7 Alarm Types and Message An alarm type defines a set of characteristics that determine how alarms appear on alarm summary displays and in the event chronicle. The alarm types used in this project are listed in Alarm Type Name Alarm Word Category Alarm Message Any Alarm ANY SYSTEM Any alarm value %P1 Change From Normal CFN PROCESS Change from normal value %P1 Change of State COS PROCESS Change of state Communication Error COMM INSTRUMENT Communication error Deviation Alarm DEV PROCESS Deviation alarm target %P1 actual %P2 DISC_ALM DISC_ALM PROCESS Change of state from %P1 Discrete Device FAILED PROCESS %P1 ENG_DEV_ALM ENG_DEV PROCESS ENG deviation alarm target %P1 actual P2 ENG_HIGH_ALM ENG_HIGH PROCESS ENG high alarm value %P1 limit %P2 West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Alarm Type Name Alarm Word Category Rev. : 00 Date Page : 31 Dec.18,2012 Alarm Message ENG_HIHI_ALM ENG_HIHI PROCESS ENG high-high alarm value %P1 limit %P2 ENG_LOLO_ALM ENG_LOLO PROCESS ENG low-low alarm value %P1 limit %P2 ENG_LOW_ALM ENG_LOW PROCESS ENG low alarm value %P1 limit %P2 ENG_RATE_ALM ENG_RATE PROCESS ENG rate of change rate %P1 limit %P2 Floating Point Error FLT SYSTEM Floating point error General I/O Failure IOF INSTRUMENT General I/O failure High Alarm HIGH PROCESS High alarm value %P1 limit %P2 High High Alarm HIHI PROCESS High-high alarm value %P1 limit %P2 Low Alarm LOW PROCESS Low alarm value %P1 limit %P2 Low Low Alarm LOLO PROCESS Low-low alarm value %P1 limit %P2 New Alarm NEW SYSTEM New alarm value %P1 Open Circuit Detected OCD INSTRUMENT Open circuit detected Over Range OVER INSTRUMENT Over range value %P1 Rate of Change RATE PROCESS Rate of change rate %P1 limit %P2 Statistical Alarm ERROR SYSTEM Statistical alarm type %P1 value %P2 Under Range UNDER INSTRUMENT Under range value %P1 User Define Alarm 1 desc ALARM PROCESS %P1 User Define 2 Alarm 2 desc. ALARM PROCESS %P1 %P2 Table 9 below. Each standard alarm is associated with one of these alarm types. Alarm Type Name Alarm Word Category Alarm Message Any Alarm ANY SYSTEM Any alarm value %P1 Change From Normal CFN PROCESS Change from normal value %P1 Change of State COS PROCESS Change of state Communication Error COMM INSTRUMENT Communication error Deviation Alarm DEV PROCESS Deviation alarm target %P1 actual %P2 DISC_ALM DISC_ALM PROCESS Change of state from %P1 Discrete Device FAILED PROCESS %P1 ENG_DEV_ALM ENG_DEV PROCESS ENG deviation alarm target %P1 actual P2 ENG_HIGH_ALM ENG_HIGH PROCESS ENG high alarm value %P1 limit %P2 ENG_HIHI_ALM ENG_HIHI PROCESS ENG high-high alarm value %P1 limit %P2 ENG_LOLO_ALM ENG_LOLO PROCESS ENG low-low alarm value %P1 limit %P2 ENG_LOW_ALM ENG_LOW PROCESS ENG low alarm value %P1 limit %P2 West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Alarm Type Name Alarm Word Category Rev. : 00 Date Page : 32 Dec.18,2012 Alarm Message ENG_RATE_ALM ENG_RATE PROCESS ENG rate of change rate %P1 limit %P2 Floating Point Error FLT SYSTEM Floating point error General I/O Failure IOF INSTRUMENT General I/O failure High Alarm HIGH PROCESS High alarm value %P1 limit %P2 High High Alarm HIHI PROCESS High-high alarm value %P1 limit %P2 Low Alarm LOW PROCESS Low alarm value %P1 limit %P2 Low Low Alarm LOLO PROCESS Low-low alarm value %P1 limit %P2 New Alarm NEW SYSTEM New alarm value %P1 Open Circuit Detected OCD INSTRUMENT Open circuit detected Over Range OVER INSTRUMENT Over range value %P1 Rate of Change RATE PROCESS Rate of change rate %P1 limit %P2 Statistical Alarm ERROR SYSTEM Statistical alarm type %P1 value %P2 Under Range UNDER INSTRUMENT Under range value %P1 User Define Alarm 1 desc ALARM PROCESS %P1 User Define 2 Alarm 2 desc. ALARM PROCESS %P1 %P2 Table 9 Standard and Custom Alarm Types, Category, and Message %P1 and %P2 represent the values of user-defined parameters. User-defined parameters typically capture the value that caused the alarm, the limit value that was in effect at the time the alarm was detected. For example, the alarm description column would show “High Alarm Value 50.5 Limit 45.0” in the alarm summary display. By default, HH and LL alarms will NOT be configured for PCS alarms. They will be configured only under the following conditions The operator must take different and/or more severe actions for initial alarm and combination alarm There must be enough time in-between alarms to perform the successful initial alarm corrective action before the combination alarm trips Experience shows that 90+% of all HI-HH and LO-LL combinations will be eliminated during rationalization, if these principles are followed. If the HH or LL alarm is actually used to trigger a trip (and is thus a “trip notification alarm”), West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 33 Dec.18,2012 then it is allowed. The rule above is met because the action for the trip is different than the action for the pre-trip. 4.8 Alarm Suppression Alarm suppression is the way to temporarily disable annunciation of an alarm in the DeltaV Operator Interface – it means that the suppressed alarm will not set off the workstation alarm horn and will not be displayed in the alarm summary and in the alarm banner, but this alarm will still be registered in the alarms/events log. Note that suppression uses the OPSUP parameter. The use of this parameter does not affect any interlock activity that is triggered by the alarm. The interlock will function regardless of the value of OPSUP. Alarm suppression is typically used when the operator needs to suppress a single or small number of alarms. These alarms are typically considered nuisance for the reason that maintenance personnel may be working on a certain transmitter or device that causes the alarm to ring in and out frequently. There are several ways to suppress an alarm, typically From the detail display, activate the alarm suppression check box From faceplate, right click on alarm box and select the alarm From the alarm summary, right click on the alarm and select suppress alarm Shift supervisor level access will be required to suppress alarms. Operators should check the suppressed alarm display at the start of every shift. Alarms suppressed for sensor malfunction reasons must be unsuppressed after sensor repairs are made. Staff should periodically assess the duration of suppressed alarms and insure the suppression process remains controlled. All suppressed alarms will be displayed on the alarm suppression screen. This graphic shows information similar to what is on the alarm summary, and will look like this West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 34 Dec.18,2012 Figure 1 Alarm Suppression Window The procedure for un-suppressed alarm is typically done from the alarm suppression screen by right clicking on the alarm and selecting ‘un-suppressed alarm’ or from the detail faceplate as described above. Un-suppressing an active alarm will cause the alarm to be displayed in the alarm banner and alarm summary screen. Note: Suppressing an alarm only removes the alarm from the alarm banner and alarm summary, but does not remove any interlocks or actions from this alarm that have been configured in the control system. 4.8.1 Automatic Alarm Suppression Under certain process conditions some alarms shall be suppressed to prevent floods of nuisance alarms (for example, for the steam generator, it does not make sense to show low flow alarms for the passes if the generator is not running and the water system is not commissioned). Special modules will be configured in each DeltaV controller to suppress alarms in the control modules under the certain conditions. The conditions shall be determined by the process designers and operations. The alarms suppression shall be implemented by momentary writing “1” to the “OPSUP” parameter of the selected module alarm(s) when suppression condition becomes active and by momentary writing “0” when the condition becomes inactive West Qurna Field nd 2 Phase Project (Early Oil Phase) 4.9 Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 35 Dec.18,2012 Alarm Filtering Alarm filtering is typically used when the operator needs to view all the alarms in a process plant area; a typical process area consists of the major equipment like the SIH_05 and SIH_06. The area alarm filtering icon enables you to turn on the areas from which we want to see alarms and to turn off the areas from which we do not want to see alarms. An area that has been turned off is filtered. Figure 2 Alarm Filter Window The alarm filter is used to filter alarms in up to 100 plant areas by the following procedure 1. Check the box next to an area to display that area's alarms in the alarm banner, the alarm summary, and the alarm suppression screen. 2. Clear the check box to filter alarms by preventing that area's alarms from being displayed in the alarm banner, the alarm summary screen, the alarm suppression screen, and the alarm filter screen. 3. Click the ‘all on’ button to see alarms from all areas that can be turned on. Click the ‘all off’ button to filter (that is, to prevent display of) alarms from all areas. 4. Click an alarm area to see detailed information (for example, time of alarm, module, description, parameter, alarm description, and message) on the alarms for that area. 5. Click the ‘description’ column in the detailed information area to open the faceplate picture, the primary control picture, or both pictures for that West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 36 Dec.18,2012 module. This is known as alarm direct access. Two buttons in the alarm banner enable and disable alarm direct access. The total count of unacknowledged alarms, active alarms, and suppressed alarms for an area that is checked is displayed next to the plant area name. The total number of alarms, the number of unacknowledged alarms, and the number of suppressed alarms are shown across the top of the area alarm details section. The details section of this picture uses the DeltaV alarm summary object Whenever an area is being filtered or an alarm is being suppressed, an indicator appears on the alarm acknowledge button on the toolbar, as shown below Indicator Indicator Meaning Indicates that one or more areas are being filtered out. Indicates that one or more alarms are being suppressed. Indicates that an alarm is being suppressed and an area is being filtered. Table 10 Alarm Indicators Alarm filtering only affects what is seen through the DeltaV HMI screens. It does not affect the event chronicle database or the association between workstations, users, and alarms that is defined in the PCS or the area keys assigned in the user manager. Alarm filtering affects only the machine on which the filter settings were made and is independent of the user. If you filter alarms and then log off the machine, the next user to log on will not see alarms from the areas that you filtered. In this project, alarm segregation is done on each operator console according to the area of operation to prevent alarm overload. Wherever helpful, alarms should be segregated for annunciation to the operator. 4.10 Alarm and Event Logging Alarm logging will be performed on two workstations in the system – Application WS running historian (primary storage) and ProPlus WS (backup storage). Both workstations shall have all plant areas assigned to their alarms collection subsystem. Alarms and events records shall be kept in the DeltaV West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 37 Dec.18,2012 alarms database for 30 days (available through the process history view) and then purged into the text files located in the specified directories. Process history view application on operator workstations shall be configured to connect to application station when displaying alarms/events. Figure 3 Alarms Collection Configuration on the ProPlus and Application Workstations The application process history view provides a spreadsheet view of the events and process alarms that occur. It also captures system events such as operator changes, control module installations, and changes in device status. Each event record is made up of fields such as date/time, event type, category, area, node, module, etc West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 38 Dec.18,2012 Figure 4 Alarm and Event Viewer 4.11 Alarm Summary The DeltaV system software provides a visual tool for monitoring alarms called the alarm summary link. The alarm summary link allows you to monitor, acknowledge, and list alarms using a variety of filtering and sorting methods. Alarm messages in the alarm summary link's display can be color-coded to provide visual clues to the operators. Alarms can be sorted as per the table below. Attribute Sorts Alarms By Time In The time the alarm first occurred. Block Type The block type. For example: AI, AO, DI, DO. Module The block's name. Priority The alarm priority, as defined for each block in the process database (low, medium, or high). Node The node name where the alarm originated. The sort by node on is based on the order the nodes appear in the network list in the SCU. West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Attribute Rev. : 00 Date Page : 39 Dec.18,2012 Sorts Alarms By Ack/Time Acknowledgement and then by time in. When sorting alarms in descending order, unacknowledged alarms appear before acknowledged alarms. Ack/Priority Acknowledgement and then by priority. When sorting alarms in descending order, unacknowledged alarms appear before acknowledged alarms. Table 11 Alarm Summary Parameters Module alarm information is displayed in the alarm summary display until the module value returns to a normal state and an operator has acknowledged that alarm. The following figure shows a sample alarm summary screen. Figure 5 Alarm Summary Screen Note: Only priority and ACK columns background color changes based on alarm priority West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 5 ALARM SYSTEM MAINTENANCE 5.1 Alarm Performance Measures Rev. : 00 Date Page : 40 Dec.18,2012 Despite best efforts to design an alarm system to minimize nuisance alarms and provide only meaningful alarms, there will be a need to change, delete or add new alarms. There is no panacea that can be prescribed to alarms systems, which will provide instant and universal improvement in performance. There are, however, some prerequisites to achieving improvements in alarm systems 1. A real commitment by senior management of the plant to promote a culture of continuous improvement is required. All staff needs to be helped and encouraged to develop a strategy for improving the alarm system. 2. An owner for the alarm system is required to Ensure consistent standards are set and maintained Control changes to alarms and alarm system, manage records and documentation Set performance measures for the alarm system, manage performance reporting and the resulting action for improvements 3. Thorough application of the basic improvement techniques. Some basic techniques are listed below but this is not an exhaustive list Review alarm behavior following all upsets to confirm usability Tune alarm settings on nuisance alarms Adjust deadbands on alarms which often repeat Review alarm messages which operators do not understand or know how to respond Review alarm suppression methods and adjust accordingly Apply de-bounce timers and delay timers to repeating alarms Introduce logic to combine and simplify redundant sets of alarms Group alarms which all have the same operator response West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 5.1.1 Rev. : 00 Date Page : 41 Dec.18,2012 Alarm Performance Measures It will be difficult to sustain the alarm system as a usable system unless alarm system performance measurements are put in place. There are several qualitative measures that can be put in place, such as operator questionnaires to determine usefulness or usability of alarms. Below are quantitative metrics that can be used as performance metrics. The source of the metrics is the Alarm Systems - A guide to Design, Management and Procurement, EEMUA, Appendix 11. 5.1.1.1 Key Perforamance Indicator Alarm System KPI reports both EEMUA-191 and ISA-18.2 stress the importance of periodic measurement of Key Performance Indicators (KPIs). DeltaV Analyze provides a ready-to-use KPI report that can be scheduled or run on-demand and filtered by operator console position. The report contains ten KPI calculations, pie charts for alarm priority and rate distribution, timeline alarm activity charts for the report period and day with the most alarms, toptwenty lists of modules with frequent, fleeting, stale and often-suppressed alarms and a list of disabled alarms. Information sharing is simplified with the report’s Microsoft Excel format and user control over file naming and destination folder. Reports can be produced on demand or scheduled by shift, day, week or month. 5.1.2 Design Metrics Design metrics can be used during the alarm system design phase to check whether the design is appropriate for the type of facility and determine the effort that will be required to maintain the system over the lifetime of the plant. As the complexity of the process increases, one would expect more alarms per operator are required. 5.1.2.1 Operating Metrics Each area of the plant will periodically assess the performance of its alarm system. The assessment should occur monthly and include the following key performance indicators Average alarm rate (number of alarms per 10 minute period) Alarm frequency distribution (for example, % of time at less than one, 110 and greater than 10 alarms/10 minute window) West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 5.1.2.2 Rev. : 00 Date Page : 42 Dec.18,2012 Peak alarm rate (maximum number of alarms per 10 minute period) Standing alarms (average number of active alarms per 10 minute period) Alarm floods per month (number of 10 minute periods where there were more than 10 incoming alarms) Worst actors monitor reviewed weekly Average Alarm Rate The average alarm rate per operator is a simple indication of the workload imposed on the operator by the alarm system. Typically this is measured over a weekly period. Average alarm rates of less than one alarm per 10 minute window should be achieved at Long Lake. This level is successfully being met at many facilities. Key Performance Indicator (KPI) Interim Target for Systems Undergoing an Alarm Improvement Effort Long Term Target Target Average Process Alarm Rate 300 per day 5 per hour (<120 per day – EEMUA) Percentage of time alarm rate exceeds Target Average Process Alarm rate 5% 0% - EEMUA Alarm Event Priority Distribution based on at least one week of data ~80% Low, ~15% High, <=5% Emergency – EEMUA ~80% Low, ~15% High, <=5% Emergency – EEMUA Inhibited / Disabled or otherwise Suppressed Alarms Zero (Unless as part of defined shelving, flood suppression, or state-based strategy) Zero (Unless as part of defined shelving, flood suppression, or state-based strategy) Chattering Alarms 10 or less in a one-week period 0 per day Stale alarms (more than 24 hours old) 20 or less in a one-week period 0 per day Floods (10 to 20 alarms in a 10 minute period) <= 5 per day <= 3 / day Floods (>20 alarms in a 10 minute period) <= 3 per day 0 per day Process changes in Alarm Priority, Alarm Trip Point, Alarm Enable Status, Tag execution status None that are unauthorized. None that are unauthorized. None that are not part of a defined Shelving, Flood Suppression, or State-based Strategy. None that are not part of a defined shelving, flood suppression, or state-based strategy. Table 12 Benchmarks for Assessing Average Alarm Rates West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Priority Rev. : 00 Date Page : 43 Dec.18,2012 Target Maximum Rate Critical (Emergecy) Very infrequently High Less than 5 per shift Medium Less than 2 per hour Low Less than 10 per hour Table 13 Target occurrence rates of alarms of different priorities Metric Alarms per Control Valve Low Average High 1 4 6 Alarms per Analogue Measurment 0.5 1 2 Alarms per Digital Measurment 0.2 0.4 0.6 Table 14 Guidance on alarms per plant sub-system What is important about these target rates is not only the ability of operators to respond to alarms, but also the operators’ attention to the importance of the alarm. The greater the number of high priority alarms compared to say low priority alarms, the operator will over time discount the priority of alarms all together and treat each with the same level of attention, thus defeating a key feature of alarm systems. Table15 provides current industry measurement of the long-term alarm rate average for plants in steady sate operation.It can be easily seen that the industry standard is well above what is recognized as an acceptable level, and is significantly higher than the target maximum rate of one per 10 minute shown in Table15. Long term average alarm rate in steady state operation Acceptability More than 1 per minute Very likely to be unacceptable One per 2 minutes Likely to be over demanding One per 5 minutes Manageable Less than one per 10 minutes Very likely to be acceptable Table 15 Benchmarks for assessing average alarm rates West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 44 Dec.18,2012 Other dynamic alarm system metrics, such as the number of alarms following a plant upset, the number of standing alarms and operator response times provide tools to review and modify alarm systems to improve performance. What is lacking at present is a relatively easy method of measuring alarm system performance in terms that are not subject to intensive post mortem studies of events or extensive alarm system data collection.It may remain a fact of alarm system design and maintenance that the effort required for continuous improvement is exhaustive, however the benefits can not be readily argued without a link between operator action, production targets and dynamic alarm activity. 5.1.2.3 Frequency of Alarms/Worst Actors The 10 worst actor tags often account for over 50 % of the alarm rate. As a component of the alarm performance monitoring, WQ-2 Project , should establish a weekly report showing the 10 worst actor tags and their relative contributions to the alarm rate. The tags identified in this report will be used as a standing work order for review and correction by operations, control, and instrument personnel. 5.1.2.4 Number of Alarms Following a Major Plant Upset Operator performance during plant upsets is strongly affected by the number of alarms they must deal with. The number of alarms following a plant upset is a good metric for assessing the effectiveness of the alarm design process. As stated in the alarm design process section, accounting for human limitations in the alarm system design is a complex requirement and is difficult to implement. This metric measures the effectiveness of the design relative to this design principle. Figure 45 in Alarm Systems - A Guide to Design, Management and Procurement, EEMUA Appendix 11, gives some guidance on alarm rates following an upset and it is recommended that this be used as the benchmark for this metric. If the metric falls into the “definitely excessive” or “hard to cope” category, the alarm system design should be reviewed to improve the alarm filtering, suppression and modal alarming and also consider deleting some alarms. West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 5.1.2.5 Rev. : 00 Date Page : 45 Dec.18,2012 Number of Standing Alarms A high number of standing alarms can indicate that many of the generated alarms do not require operator action or are nuisance alarms. Those not requiring operator action should be targeted for deletion. The cause of the nuisance alarms needs to be determined and fixed so as not to create an environment of operator complacency to alarms. Long standing alarms can also be an indicator of a poorly operated or maintained plant. Thus a periodic review of the long standing alarms can help determine if this is the case. 5.1.2.6 Priority Distribution The effective use of alarm priority can be checked by looking at the distribution of alarms sorted by priority over a period of time. A large percentage of high priority alarms indicates that the control system is not effectively keeping the process within bounds, and that operator action is needed to avoid a significant consequence. Either that, or the assigned priority is incorrect. 5.1.3 Alarm Performance System The source of the data for metric calculations/reporting is the CSS alarm and events database. The calculations and reporting should be done using alarm analysis software. 5.1.4 State-Based or State-Dependent Alarms Most alarms in a process unit pertain to the normal operating state of a piece of equipment. But, equipment often has several normal, but differing, operating states. PCS alarm capabilities are normally only for single-state, single-value trip points and priorities. State examples include startup, shutdown, differing grades of product or feed, half rate operation, etc. Besides individual pieces of equipment, sections of an operating unit may have different operating modes where fixed alarms produce inconsistent results. For example, the process may run in modes where certain sub-sections are intentionally shut down, producing a variety of alarms. Or, redundant equipment may produce alarms when unused, even though that is a “normal” and proper operating condition. In these circumstances, the alarms produced West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 46 Dec.18,2012 do not meet the real criteria for an alarm (there is no operator action to take) and will become stale and contribute to alarm floods and confusion. It is a best practice that all such normal operating states should not cause alarms. Alarms should be produced only upon abnormal or unexpected events. State-based methodologies produce dynamic alarm configurations based upon the specific process & equipment conditions. Multiple alarm trip point and priority settings are configured for appropriate alarms and enabled based on plant state. Two components are required for handling state based alarms a state detector and a state enforcer. The detector uses available information (which can include operator input if desired) to correctly identify the current operating state of the equipment, while the enforcer actually makes the desired alarm modifications. Neither of these tasks may be automated. If multiple process states producing differing alarms are identified, these must be documented during the alarm rationalization. State transitions requiring alarm system modifications should be handled by one of the following methods Fully automated transition, with no input required from the operator Semi-automated transition, utilizing the operator to identify/confirm the correct state and initiate the change Manual transition, with changes identified and performed individually by the operator For fully automatic transitions, documentation and other indication must be provided to communicate the current operating state to the operator. Automatic transitions requiring operator initiation should include a “failsafe” to monitor the process and return critical alarms to service. The manual transitions shall be fully documented for the operator, and include custom designed operating schematics or reports for review, and to approve that all settings are correct. Any software methodology for dynamic change of alarms must be robust and have fail-safe mechanisms. 5.1.5 Alarm Flood Suppression Alarms give the proper information to the operator so that the best possible actions can be taken to prevent or mitigate operational upsets. Alarms will not West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 47 Dec.18,2012 be presented to the operator at a rate faster than he/she can respond. Periods of alarm activity with presentation rates higher than the operator can respond are defined as alarm floods. When the operator experiences an alarm flood, his/her effectiveness is diminished because important information could be missed. Alarm floods can make a difficult process situation much worse. In a severe flood, the alarm system becomes a nuisance, a hindrance, or a distraction, rather than a useful tool. Flood suppression is the dynamic management of pre-defined groups of alarms based on detection of equipment state and triggering events. 5.1.6 Emergency Shutdown Systems Special Considerations Special considerations for ESD systems include the following If there are duplicate or similar analog measurements input to both the PCS and the ESD (for control and trip determination, respectively), do not provide multiple alarms from both sources for the same process condition. The reading not alarmed may be displayed on the graphic and also logged. If the ESD reading is chosen to be alarmed as a pretrip indicator, insure that its associated display parameter goes to the correct PCS graphic for taking corrective action. Often the PCS tag, not the ESD reading, is the preferable place for the alarms, since the PCS is where the operator can take corrective, pre-trip action Valve position switches on ESD shutoff valves are often set to alarm when the valve performs the ESD action. This is incorrect; there should be an alarm only when the valve did not perform the proper action, so that the operator can take further action Bad value alarms on devices connected only into the PLC should not produce a general PLC health/status alarm when activated. Such alarms should annunciate in the PCS as a bad value alarm on a tag representing the point in the PLC The process for obtaining ESD input or output bypass authority (generally for testing purposes) must be done per the WQ-2 Project site procedure and recorded properly. New facilities must be designed and implemented to work within the procedural guidelines established in that procedure. West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 48 Dec.18,2012 When inputs or outputs to an ESD system are bypassed for testing, such a condition must be annunciated per standards and displayed to the operator on the schematics. 5.1.7 Duplicate Alarms Duplicate alarms, where several alarms on different process parameters indicate the same abnormal situation, should be removed. In most cases, the documentation and rationalization team shall select the best indicator of the root cause and place the alarm on that device. 5.1.8 Consequential Alarms WQ-2 Project facility process units are highly integrated systems with many interrelations. A single alarm may propagate through other alarms in the system. For example, a pump trip alarm may result in numerous low header pressure or low feed flow alarms. Often a consequential alarm can be handled by the same methods as duplicate alarms and voting alarms, or incorporated into a state-based alarming strategy. 5.1.9 Chattering Alarms To minimize chattering alarms, which activate repeatedly over a short period of time, appropriate deadbands must be selected for all alarms. This may involve the programming of a deadband for analog trip values, and a delay time or filter for discrete points. Determination by historical performance is recommended. Best practice “starting points” for design are listed in Table 16 below. Signal Type Filter Time Constant Deadband Delay Time Flow 2 sec 5% 15 sec Level 2 sec 5% 60 sec Pressure 1 sec 2% 15 sec Temperature 0 sec 1% 60 sec Table 16 Deadband and Delay Time Delay time – sometimes called a “debounce timer” – is a selectable system capability of some alarm types. An ON-DELAY requires that an alarm be in effect for the specified number of seconds before it is initially annunciated to West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 49 Dec.18,2012 the operator. An OFF-DELAY immediately annunciates the alarm to the operator but will not clear it until it has remained clear for the specified number of seconds. Both techniques can be quite powerful for dealing with chattering alarms. Select on-delay time > 30 seconds while keeping in mind the impact of delaying an initial alarm display. 5.1.10 Alarm Handling for Programs In general, a program implemented in a PCS does a task that the operator relies on. Failure of that program means the operator must act in a different way very similar to the treatment of an external device health alarm. Programs, however, often produce cryptic or unexplained alarms or error messages, some of which are useful to the program creator but not to the operator. Such alarms must be eliminated. Programs must be accompanied by documentation for the operator regarding the action to take based on the specific alarm. 5.1.11 PCS System Status Alarms Alarms specific to the internal workings of a PCS system should be absent under normal operating conditions, and they should not be tolerated when they occur. PCS status displays should have no “stale” error messages. If many system status errors are present, new system alarms are difficult to recognize and respond to. Operators should know the proper response to each type of system status alarm, including the functional group to contact and the degree of urgency for the contact. 5.1.12 Tag and Program References to Alarms A logic point should not look at parameters on a source point that depend on the alarm function of the point in some way because those parameters are too easily changed. Instead, a logic point should look at the PV of a source point and compare that to a numeric value coded in the logic point itself or stored in an array point. These are much less likely to be changed. The same concept applies to programs implemented on the PCS and for communication between points other than logic points. West Qurna Field nd 2 Phase Project (Early Oil Phase) 5.2 Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 50 Dec.18,2012 Management of Change Having expended time and effort into determining proper alarm settings, these must be maintained and not allowed to drift into other configurations. To maintain the integrity of the alarm system, management of change procedures must be in effect that address changes to alarm systems. Such changes must be properly evaluated, authorized and communicated to all affected personnel and shifts. MOC procedures must define the minimum level to invoke appropriate approvals and documentation. Changes in alarm priority Changes in alarm trip point Creation of new alarms Deletion of existing alarms Change of alarm type Change of alarm description or text message Temporary suppression of alarms (an approved shelving methodology must be used) Point execution status (turning a sensor “on” or “off”) Changes in alarm presentation on graphics Additions of, modifications to, or updates to alarm handling capabilities such as alarm shelving systems or state based alarming configuration The following changes should be controlled in a way to ensure that only authorized, knowledgeable people perform the changes. Controller tuning parameters Point ranges Modification of logic points, interlocks, embedded programs, PCS operating system software, and similar functions The change system itself must be designed to accommodate the number of certain types of changes that are necessary, without an over-burden of paperwork, but without compromising safety. Audit and enforcement software should be used to periodically check for changes from the proper settings, to report such changes, and to restore the system to the proper settings. West Qurna Field nd 2 Phase Project (Early Oil Phase) Doc. Title ALARM MANAGEMENT PHILOSOPHY Doc. No. 8015-0151-22-PO-45-0009-4236-J08-00409 Rev. : 00 Date Page : 51 Dec.18,2012 The proper settings reside in a master alarm database. The MOC system must insure timely update of that database so that proper changes do not get “undone” by the enforcement software. Note that audit and enforcement software/methodologies must understand any state-based, flood suppression, shelving, or other alarm handling strategies being employed and work correctly in conjunction with them. To emphasize, best practices support that the integrity of the overall alarm system is of such importance as to require MOC around all alarm priorities, including “low.” This is why a separate operator alert system/priority is a best practice as well. The alarm system champion for the area in question should be notified of any and all alarm changes so that they can maintain the integrity of the alarm system. Exceptions that do not require an MOC include the operation of alarm handling strategies of state based, flood suppression, or shelving as defined in this philosophy document. Alterations to the configuration of these strategies themselves, however, must be done utilizing MOC and proper review and authorization.