Uploaded by adada adadada

Exam 2 OPS MGMT.docx

advertisement
Below are the two tables you will need for this exam.
X-Bar Control Chart
Use the data below to work the problems in the next two sections.
Note that each sample has a size of 20, e.g. n=20.
Question 1
What is the value for A2?
1 / 1 point
Answer:
0.18
Hide Feedback
If you got this wrong, nothing else will be correct.
Question 2
1 / 1 point
What is the lower control limit?
Answer:
3.99
Hide Feedback
Question 3
What is the center line?
Answer:
1 / 1 point
4.01
Hide Feedback
Question 4
What is the upper control limit?
Answer:
4.04
Hide Feedback
1 / 1 point
Question 5
1 / 1 point
Point 1 is out-of-control.
True
False
Hide Feedback
Question 6
1 / 1 point
Point 2 is out-of-control.
True
False
Hide Feedback
Question 7
1 / 1 point
Point 3 is out-of-control.
True
False
Hide Feedback
Question 8
1 / 1 point
Point 4 is out-of-control.
True
False
Hide Feedback
Question 9
1 / 1 point
Point 5 is out-of-control.
True
False
Hide Feedback
Question 10
Point 6 is out-of-control.
True
False
Hide Feedback
1 / 1 point
Range Control Chart
Use the data from the prior section.
Question 11
1 / 1 point
What is the value for D3?
Answer:
0.41
Hide Feedback
If you get this wrong, the remainder of the problem will be wrong.
Question 12
What is the value for D4?
Answer:
1.59
Hide Feedback
1 / 1 point
If you get this wrong, the remainder of the problem will be wrong.
Question 13
1 / 1 point
What is the lower control limit?
Answer:
0.07
Hide Feedback
Question 14
What is the center line?
Answer:
0.16
Hide Feedback
1 / 1 point
Question 15
What is the upper control limit?
Answer:
0.26
Hide Feedback
1 / 1 point
Question 16
1 / 1 point
Point 1 is out-of-control.
True
False
Hide Feedback
Question 17
Point 2 is out-of-control.
True
False
Hide Feedback
1 / 1 point
Question 18
Point 3 is out-of-control.
True
False
Hide Feedback
1 / 1 point
Question 19
Point 4 is out-of-control.
True
False
Hide Feedback
1 / 1 point
Question 20
Point 5 is out-of-control.
True
False
Hide Feedback
1 / 1 point
Question 21
Point 6 is out-of-control.
True
False
Hide Feedback
1 / 1 point
p-Chart
Using the following sample data and three sigma, determine the UCL, center line, and LCL for a p-chart
and use that information to answer the questions that follow.
Note that the sample size is 150, the standard deviation is 0.010453, and p-bar is 0.0166667.
Carry out all calculations to at least six decimal points. There are 12 data sets. you may need to scroll to
the right to see them all.
Hide Feedback
These are small values so you have to carry out more decimal points. With less than four, you answers
may be incorrect due to rounding.
Question 22
1 / 1 point
What is the lower control limit?
Answer:
0
Hide Feedback
Question 23
What is the center line?
Answer:
0.0167
Hide Feedback
1 / 1 point
Question 24
What is the upper control limit?
Answer:
0.0480
Hide Feedback
1 / 1 point
Question 25
1 / 1 point
Point 1 is out-of-control.
True
False
Hide Feedback
Question 26
Point 2 is out-of-control.
True
False
Hide Feedback
1 / 1 point
Question 27
Point 3 is out-of-control.
True
False
Hide Feedback
1 / 1 point
Question 28
1 / 1 point
Point 4 is out-of-control.
True
False
Hide Feedback
Question 29
Point 5 is out-of-control.
True
False
Hide Feedback
1 / 1 point
Question 30
Point 6 is out-of-control.
True
False
Hide Feedback
1 / 1 point
Question 31
1 / 1 point
Point 7 is out-of-control.
True
False
Hide Feedback
Question 32
Point 8 is out-of-control.
True
False
Hide Feedback
1 / 1 point
Question 33
Point 9 is out-of-control.
True
False
Hide Feedback
1 / 1 point
Question 34
1 / 1 point
Point 10 is out-of-control.
True
False
Hide Feedback
Question 35
Point 11 is out-of-control.
True
False
Hide Feedback
1 / 1 point
Question 36
Point 12 is out-of-control.
True
False
Hide Feedback
1 / 1 point
C Chart
Using the data shown below, develop a three-sigma C-chart. Use that C-chart to work the problems that
follow.
Hide Feedback
A common mistake is to work a C-chart as a p-chart.
Question 37
1 / 1 point
What is the lower control limit?
Answer:
0.000
Hide Feedback
Make sure you are working this as a C-chart.
Question 38
What is the center line?
1 / 1 point
Answer:
4.917
Hide Feedback
Make sure you are working this as a C-chart.
Question 39
What is the upper control limit?
Answer:
11.569
Hide Feedback
Make sure you are working this as a C-chart.
1 / 1 point
Question 40
Period 1 is out-of-control.
True
False
Hide Feedback
1 / 1 point
Question 41
1 / 1 point
Period 2 is out-of-control.
True
False
Hide Feedback
Question 42
Period 3 is out-of-control.
True
False
Hide Feedback
1 / 1 point
Question 43
Period 4 is out-of-control.
True
False
Hide Feedback
1 / 1 point
Question 44
1 / 1 point
Period 5 is out-of-control.
True
False
Hide Feedback
Question 45
Period 6 is out-of-control.
True
False
Hide Feedback
1 / 1 point
Question 46
Period 7 is out-of-control.
True
False
Hide Feedback
1 / 1 point
Question 47
1 / 1 point
Period 8 is out-of-control.
True
False
Hide Feedback
Question 48
Period 9 is out-of-control.
True
False
Hide Feedback
1 / 1 point
Question 49
Period 10 is out-of-control.
True
False
Hide Feedback
1 / 1 point
Question 50
1 / 1 point
Period 11 is out-of-control.
True
False
Hide Feedback
Question 51
Period 12 is out-of-control.
True
False
Hide Feedback
1 / 1 point
Process Capability
Use the following information to work the problems in this section.
A process has a mean of 1.25 and a standard deviation of 0.03. The customer wants the process to have
a mean between 1.15 and 1.40.
Question 52
What is the process capability index (Cpk).
Answer:
1.111
Hide Feedback
1 / 1 point
Question 53
1 / 1 point
What is the process capability index (Cp).
Answer:
1.389
Hide Feedback
A common mistake is to forget the last step and pick which of the numbers is the smallest.
Reliability
Question 54
0 / 1 point
A product is composed of three parts. In order for the product to function properly in a given situation,
each of the parts must function. The probabilities of functioning properly for the three parts are 0.94,
0.83, and 0.89 respectively. What is the overall probability that the product will function properly?
Answer:
0.57
(0.69)
Hide Feedback
Use the series reliability formula.
Question 55
1 / 1 point
A component is absolutely critical to the proper functioning of a product. It has a reliability of 0.68. To
improve its reliability, the firm has designed in two backup components with reliabilities of 0.57 and 0.57
respectively. All three must fail in order for the product to fail. What is the overall reliability of the
component and its two backups?
Answer:
0.926
Hide Feedback
Use the formula for reliability with redundancy.
Question 56
0 / 1 point
A product has three components, A, B, and C. A failure of any of these three components would cause
the product to fail. They have reliabilities of 0.83, 0.86, and 0.77 respectively. A failure of C might cause
safety issues so it has a redundant backup D with a reliability of 0.85. What is the overall reliability of the
product?
Answer:
0.648
(0.689)
Hide Feedback
You must first find the combined reliability for C and D using the redundancy formula. Then, you give the
series reliability for A, B, and the combined C/D.
Question 57
1 / 1 point
A copier has a mean time between failure of 2,730 hours and a mean time to repair of 41 hours. What is
its availability?
Answer:
0.989
Hide Feedback
Use the availability formula, MTBF/(MTBF+MTR).
Download