A.) SLABS
ITEMS
Primary Beams (2UPN) are properly
placed onto U-heads of the shoring
Secondary Beams (HT20) follows correct
spacing as per design
Secondary Beams (HT20) are connected
properly onto 2UPN through Mf
Connectors
HT20 overlaps are placed properly
without extensive cantiléver.
Phenolic used is of good quality.
Phenolic properly nailed on mix joists
OK
NOT OK
□
□
□
□
□
□
□
□
□
□
□
□
COMMENTS
Alsina Formwork South East Asia Corporation
Unit 901, The Infinity Tower - 26th Street, Bonifacio Global City
Taguig City, 1634 (Philippines) - Tel.: (+632) 834 7553 / 54
No wide phenolic gaps on the decking
Guardrails are fixed properly onto HT20
or 2UPN with the right connectors
Brace tubes, Wood or other materials
serving as guadrail are secured and
properly placed.
B.) OTHERS
□
□
□
□
□
□
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
__________________
Alsina Site Supervisor
__________________
Date
Download