Assosa Water Supply Project CHAPTER FIVE 5.0 R I V E R D I V E RS I O N H E AD D I V E R S I ON W OR KS W E AR 5.1General A wear is an obstruction or barrier constructed across a river the obstruction is of small height in comparison with the dam, it is used for raising water level in river to divert the water into the intake. In this case the Hoha diversion weir site is located about 200m u/s of the bridge over the Hoha River on the Assossa – Kurmuk road. The bed level of this 1460m a.s.l The river bed is massive basaltic rock foundation. Page 54 Assosa Water Supply Project 5.2 Selection of Types of Weir Weir can be classified according to the material of construction and certain design futures as Masonry weirs with vertical drop or vertical drop weir Concrete weir with d/s glacis Rocks fill weirs with sloping aprons They are also classified as gravity and non gravity according to design aspect. From the above types of weir for our scheme we select massonary weir with vertical drop, because it is suitable for any type of foundation 5.3 Selection of site for Weir Having decides up on the location of the weir the actual site is selected with the following consideration. 1) A narrow, straight, well defined channel with defined banks is the best. 2) Availability of material of construction 3) Accessibility of the site to the road 4) Arrangement of diversion of the river 5.4 Design of Vertical Drop Weir The complete design of a vertical drop weir consists of the design calculation for the following i) Hydraulic calculation for fixing varios elevation ii) Design of a weir wall iii) Design of impervious apron iv) Design of inverted filter and d/s talus i) Hydraulic calculation Available data Qd = maximum flood discharge = 20m3/s Page 55 Assosa Water Supply Project River bed level = 1460m a.s.l Afflux = 1 (assumed) Lacey’s silt factor =1(assumed) Discharge concentration factor = 20% Coefficient of discharge =0.58 Intake level of main supply line = 1460m a.s.l Procedures Length of water way L = 4.7 Qd3/2 ,where Qd =20m3/s = 4.7 (20)3/2 = 13.67m Discharge (q) per unit width of the river q= Q/L = 20/14 = 1.43m3/s/m Regime scour depth is calculated from lacey’s formula q 2 1/ 3 R 1.35( ) f 1.43 2 1 / 3 R 1.35( ) 1.71m 1 , where f= silt factor Regime velocity (V) and velocity head (ha) V q 1.43 0.836m / s R 1.71 V 2 (0.836) 2 ha 0.0356m 2g 2 * 9.81 Design discharge over the crest of the weir is given by Page 56 Assosa Water Supply Project q = 1.7Hd3/2 Head over crest weir Hd = (q/1.7)2/3 = 0.891m Water level and Total energy levels are calculated as follows Elevation of T.E.L = River bed level + head over crest weir +Weir height = 1460 +0.89 + 1.5 = 1462.39m a.s.l Elevation of u/s H.F.L = u/s T.E.L -Va2/2g = 1462.39- 0.0356 = 1462.3564m a.s.l Elevation of d/s T.E.L = u/s T.E.L – Afflux = 1462.354 – 1 = 1461.354m a.s.l Elevation of d/s H.F.L = u/s H.F.L – Afflux = 1462.354 – 1 =1461.354m a.s.l 5.4.1 Design of under sluice portion Head over under sluice portion = u/s TEL - river bed level =1462.39 – 1460.0 =2.39m The under sluice portion is so designed that it can pass 20% of the maximum flood =0.2*20 =4m3/s Provide one under sluice with one meter width at the bottom of diversion q= Q sluice/L sluice =4m3 / 1m =4m3/s/m Scour depth (R) for the sluice section R=1.35(q2/f)1/3 =1.35(4/1)1/3 =3.402m Page 57 Assosa Water Supply Project 5.4.2 Design of weir wall The design of a vertical drop weir wall is similar to the of the over flow section of gravity dam ; Incase of weir greater the discharge the discharge the smaller is the difference of level between the head and tail water surfaces. Preliminary section of weir wall top width bottom width (picture) Top width (a) Is fixed as the largest of the following i) a= d/√G,, where d = maximum depth of water over the crest on u/s side) d = u/s HFL – crest level d = 1462.354 –1461.5 d = 0.354m G = specific gravity of wall material, 2.24kN/m3 a = 0.354 /√2.24 =0.57 ii) a =0.552(H)*(√d) = 0.552*√1.5*√0.85 iii) a =3/2*d / √G =3/2*0.854/√2.24 =0.57m Therefore take top width 0.65m which is the largest of the three results. Stability check for weir Under two states State 1) when the u/s is at crest level or at level of crest shutter and there is no flow State 2) when the water is passing over the weir crest and the weir is submerged Bottom width (b) Can be calculated by equating over turning moment to the resisting moments taken at the outer third point To find moment, we shall consider all the two states mentioned above. Page 58 Assosa Water Supply Project State 1) Head water at the crest level and no water to the d/s side -overturning moment with no shutter (assuming no shutter is provided) Mo =γH3/6 -Resisting moment M r = γ HG/6(b2+ab-a2) , G=2.24KN/m3 Equating overturning and resisting moments γH3/ 6 =γ HG/6(b2+ab+a2) H2=G (b2+ab-a2) 1.52 = 2.24(b2+0.65b-0.652) b2+0.65b- 1.427 =0 Solving quadratic equation, b=0.913m State -2) The weir is just submerged - Overturning moment Mo= hH2/2 Resisting moment M r = H (G-1)/12*(b2+ab-a2) Equating the two moments γhH2/2 = γ H/12 (G-1)(b2+ab-a2) hH = (G-1/6)(b2+ab-a2) where h=d, when the tail water is at crest level ,d and h be equal for this case the value of d(head over the crest ) is given by drowned weir formula. q= 2/3*cd*g2*d3/2 d=(1.52*g2/cd2*g2)2/3 ,where Cd – coefficient of discharge =0.58 d= 1.52*1.432/0.582*19.62 d=0.886≈1m= h 1*1.5 = (2.24-1)/6*(b2+0.65b-0.652) By solving quadratic equation b≈2.465m Therefore take bottom width, Page 59 Assosa Water Supply Project B=2.46m (which is larger) Depth of piles Bottom level of d/s pile=d/s HGL after retrogation-2R Where d/s HGL after ret rogation = d/s TEL –Velocity head =1461.39 -0.0356 =1461.354m a.s.l Bottom level of d/s pile =1461.354 – 2*1.71 =1457.934 m a.s.l Depth of d/s pile d2 = bed level –bottom level of d/s pile =1460m -1457.934m =2.066m Provide 2.5m depth of d/s pile Bottom level of u/s pile =u/s HFL -1.5R =1462.354 - 1.5*1.71 =1459.789m a.s.l Depth of u/s pile= Bed level – bottom level of u/s pile =1460m – 1459.789 d1=0.211m Provide 1m depth of d/s pile 5.4.3 Design of Impervious Apron For the under seepage, the worst condition will be when the water at the u/s is up to the crest and there is no tail water. If the floor of the weir is designed on’ Bligh Creep Theory’ The total creep length(l) L = CH L = 9*1.5 =13.5m, where C= Creep coefficient = 9 (for gravel mixed with sand and bolder) Page 60 Assosa Water Supply Project D/s impervious flow l1=2.21C*(H/13)1/2 =2.21C*(H/13)1/2 =6.75m U/s impervious floor length l2=18-6.75-(2.46+2*1+2*2.5) =1.783m (take 2m) Total length of d/s floor l3=18*C*((H/10)*(q*75))1/2 =18*9*((1.5/10)*(1.43*75))1/2 =8.66m (take 9m) Length of filter +launching apron=9-6.75 (Length of d/s protection work)=2.25m But, minimum length of d/s concrete block = 1.5d2 = 1.5*2.5 = 3.75m An inverted filter is provided immediately d/s of the d/s impervious floor beyond the d/s pile to relive the pressure so that piping does not occur. The filter is properly graded with finer layer at the bottom and its total thickness is usually between 50cm to 70cm (irrigation structure and water power eng ’g). Thus provide 1m*1m*1m concrete block over 0.5m thick inverted filter and the open joint with 10cm gap are filled with river sand. - Minimum length of d/s launching apron = 1.5d2= 1.5*2.5=3.75 Length of d/s protection work =3.75+3.75 =7.5 U/s protection work Minimum length of u/s concrete blocks = d1 = 1m Provide 1m*1m*1m thick concrete block. Minimum length of u/s launching apron at horizontal position = 1.5 * d1= 1.5*1 = 1.5m Thickness of horizontal launching apron T Page 61 Assosa Water Supply Project T 5 * d1 * t 5 *t 5 *1 1.118 1.2m 2d 1 2 2 Hence provide launching apron of length 1.5m and thickness of 1.5mand thickness of 1.2m Actual creep length (L) L = 2d1+L2+B+Ld+2d2 L = 2*1+2+2.46+6.75+2*2.5 L = 18.21m Residual head at the toe of the weir wall or at point B hH H (2d1 Lu B) L 1.5 h 1.5 (2 *1 2 2.46) 18.21 h 0.968m Thickness of impervious floor (t) using Bligh’s theory t 4 h 4 0.968 * * 1.04m 3 G 1 3 2.24 1 Therefore provide thickness of 1.04m for d/s floor from just near its junction with weir wall. hH Residual head at point C,(that is 3m from toe) Thus thickness (t ) 4 h 4 0.81 * * 0.77 0.8m 3 G 1 3 2.24 1 H * (2d1 Lu B 3) L 1.5 h 1.5 * (2 *1 2 2.46 3) 18.21 h 0.72m Therefore, provide thickness of 0.8m for the next 3m from point c Residual head at point D, at a distant of 5.5m from the toe of the weir wall Page 62 Assosa Water Supply Project hH H * (2d1 Lu B 5.5m) L 1.5 h 1.5 * (2 *1 2 2.41 5.5) 18.21 h 0.51m Thus thickness (t ) 4 h 4 0.64 * * 0.548m 3 G 1 3 2.24 1 Therefore provide thickness of 0.6 for the last 1.25m of d/s impervious floor. And also provide a nominal thickness of 0.5m below the u/s floor and below the weir wall. Page 63 Assosa Water Supply Project Fig 5.1 dimensions of same of weir body components Check for thickness by Khosla’s theory referring the above figure. I. Exit gradient II. Uplift pressure Exit gradient - Total length of the impervious floor b = 2m+2.41m+6.75m = 11.16m Depth of d/s pile (d2) = 2.5m Thus exit gradient (GE) = b 11.16 4.464 d2 2.5 H 1 1 1.5 0.114 1 safe! * * d 2 2.5 2.79 Because safe exit gradient for course sand with mixed gravel of weir foundation is 1 1 1 (1 2 ) 1 (1 4.464 2 ) 2.787 between 5 and 6 .(source 2 2 and water power eng ‘g, PUNMIA) irrigation structure Page 64 Assosa Water Supply Project II. Up lift pressure a) u/s pile b= 11.17m b 11.16 11.16 d1 1 1 (1 2 ) 6.1 2 1 2 1 1 6.1 2 E 1 * cos 1 * cos 6.1 E 1 26.53% d1 = 1m C1 100 E1 100 26.53 73.47% D1 100 D where D 1 1 1 6.1 1 * cos 1 * cos 6.1 1 D 8.48% D1 100 D 100 18.48 81.52% Correction for C1 Correction due to mutual interference Correction = 19 * D (d D) * b' b Where b’= the distance between two piles D=the depth of the pile line, the interference of which has to be determined on the neighboring pile of depth d. D is to be measure below the level at which interference is desired. b= total floor length b’=b=11.21 D= 2.5-0.5=2m and d = 1-0.5 = 0.5m Page 65 Assosa Water Supply Project Correction = 19 * D ( d D) 2 (0.5 2) * 19 * * 3.78%(ve) b' b 11.21 11.21 Thickness correction C1 81.52 73.47 * t D1 * 0.5 4.025%(ve) d 1 m 1 Correction due to slope at C1 is nil, as C1 is neither situated at the start nor at the end of the slope. Therefore corrected C1 73.47 4.025 3.78 81.275% B. d/s pile b=11.21m d2= 2.5m b 11.21 4.484 2.5 d2 1 (1 2 ) 2.79 2 1 2 1 1 2.79 2 E 2 * cos 1 * cos 2.79 1 E 2 * 73.39 * 40.77% 180 1 1 1 1 2.789 1 D 2 * cos 1 * cos 2.789 1 D 2 * 50.09 * 27.83% 180 C 2 0% Correction for E 2 Correction due to mutual interference b=b’=11.21 D=1-0.6=0.4 & d=2.5-0.6=1.9 Correction = 19 * 0.4 (1.9 0.4) D ( d D) * * 19 * 1.62%(ve) 11.21 11.21 b' b Page 66 Assosa Water Supply Project Thickness correction D2 40.77 27.83 * t E 2 * 0.5 2.588%(ve) d2 2.5m Note:-the correction is negative because the pressure at E2 shall be less than at E2’ Correction due to slope Correction due to slope is nil, as the point E 2 is neither situated at the start nor at the end of a slope. Hence corrected E 2 =40.77% - 1.62%- 2.588% = 36.57% Percentage pressure at toe B, C,D Percentage pressure at B E2 A E 2 C 1 * Ac ' b 81.27 36.57 A 36.57 * 6.75 63.48% 11.21 Thus residual head at pt, B = 2*63.48% = 1.269m Thickness of floor at B, t h 1.2965 1.04 ………………………………..ok! G 1 2.24 1 Percentage pressure at pt, C E2 B E 2 C 1 * Bc ' b 81.27 36.57 B 36.57 * 3.75 51.52% 11.21 Thus residual head at C = 2*51.52% = 1.03m Thickness of floor at B, t h 1.03 0.83 >0.8 ……………………….ok! G 1 2.24 1 There fore take t =0.83m from the 2.5m of the d/s impervious floor. Page 67 Assosa Water Supply Project Percentage pressure at D E2 C E 2 C 1 * Cc' b 81.27 36.57 C 36.57 * 21.25 41.55% 11.21 Thus residual head at D = 2*41.55% = 0.83m Thickness of floor at B, t h 0.83 0.63 0.6...................ok ! G 1 2.24 1 Therefore take t=0.63m from the last 1.25m of d/s impervious floor. %age presser at D ØD=Ø+ c1 E 2 b =36.57+ ( * DD / 81.27 36.57 ) *1.25 =41.55% 11.21 Therefore; Residual head at D=2*41.55% =0.83m Therefore; Thickness of floor at D t= h 0.83 = =0.63……………..Ok G 1 2.24 1 t=0.63m>0.6m Therefore take t =0.63m from the 1.25 of downstream impervious floor. 5.5 Water profile at weir site 5.5.1 Water profile u/s of the weir Water profile u/s of the river Effect of back water curve on structure To suggested weather river training works are required or not To determine the minimum height of river banks u/s of weir. To find out whether the water surface is high enough to deliver the required discharge to the off take canals Page 68 Assosa Water Supply Project Water profile d/s of the weir Required, to Carry out the stability analysis of the weir. Design the weir structurally Design the d/s ring wall and protector Hydraulic jump To check weather the hydraulic jump is occurs or not, if the d/c between u/s and d/s energy grade line is very high, there fore the energy must be dissipation be fore it reaches the natural river course, other wise it causes damage to the banks and d/s of the apron. Hydraulic jump is used to dissipate energy which is caused to increase by (He) He= ( q 0.66667 Vo 2 ) =hd+ 1 .7 2g = 0.891m Applying Bernoulli equation between section 1-1 and section 2-2 take reference datum river bed level Zo=Z1 Zo+P+hd+ V 12 2g Where Zo=Z1 and He= hd+Va2/2g P+hd+ Va 2 V 12 =Y1+ 2g 2g P+He= Y1+ 2.39= Y1+ V 12 V 12 =1.5+0.89= Y1+ 2g 2g V 12 ……………………….Equation 1 2g Applying continuity equation i.e. Q=VA Where, Q=q/B=V*B*Y, V1=q/Y1………………………………………Equation 2 Page 69 Assosa Water Supply Project Solving equation1 and 2 we get; 19.62Y13-46.89Y12+2.045=0 …………...Equation 3 Solving equation 3 by trial and error Y1=0.219 V1=q/Y1= 1.43 =6.53m/s 0.219 Fr1 (Fraud number)= V1 g * y1 = 6.53 9.81 * 0.259 =4.455 Critical depth (Yc)=(q2/2g)0.66667=(1.432/2*9.81)0.66667=0.6575 Y1=0.219<Yc: 0.22; therefore there will be jump. The conjugate(sequent) depth(i.e. Y2) Y2= Y 1 *[ (1 8Fi 2 ) 1 ] =0.1095[ (1 8 * 4..455) 1 2 Y2=1.274m Head loss (HL); HL= (Y 2 Y 1) 4Y 1Y 2 = (1.274 0.219) 3 =1.032m 4 *1.274 * 0.219 Length of jump L=5(y2-y1) = 5(1.274-0.219) = 5.275 = 5.275 < 6.75(d/s impervious length)…….ok! The down stream floor length (Apron length )should be greater than or equal to the length of the jump to accommodate the hydraulic jump in it. The Apron length determined for satisfying seepage requirement is enough to accommodate the jump.Finally, it is calculated that measures such as using chute blocks and end sill or extending the length of the down stream impervious floor which are used to bound the jump in the downstream impervious floor are not necessary. 5.6 STRUCTURAL ANALYSIS OF WEIR Page 70 Assosa Water Supply Project Forces acting on weir body Hydrostatic pressure of the water Soil reaction at weir base Uplift pressure Friction force at the base which balance the horizontal force Weight of weir and water wedges The weir should be designed stable against - Overturning - Sliding - Over stress Where, The analysis of the weir is done for static condition. Static condition This is the case where by Water is impounded u/s of the weir and no over flow condition is observed. γw =unit weight of water = 10kN/m3 pw =water pressure M = unit weight of masonry (23KN/m3) Forces acting on the weir Hydrostatic force Pw = ½*γw*H2*L =1/2*9.81 KN/m3*1.52*1 , where γw= 9.81KN/m3 =11.036KN - Weight of weir W 1 =M*A*L =24 KN/m3*0.65*1.5*1 , where M= unit wt of masonry =24KN/m3 W 1=23.4KN W 2=M*A*L=24 KN/m3*1/2*1.81*1.5*1 W 2=32.58KN - Uplift pressure Page 71 Assosa Water Supply Project U=1/2* γw *H*b =1/2*9.81*1.5*2.46 U= 18.099 KN Type of Vertical force(KN) Horizontal force(KN) force Level Moment about the arm toe(KNm) from toe (+ve) (-ve) Pw (+ve) (-ve) 11.036 (m) (+ve) 0.5 5.518 (-ve) W1 23.4 2.135 49.96 W2 32.58 1.206 39.29 U 18.099 ∑H =55.98 ∑v=18.099 ∑H=11.036 1.64 29.68 ∑M=35.198 KN.m ∑M=89.25 KN.m ∑M=∑M-∑M ∑M=54.052KN.m 1) Check for overturning ∑M+/∑M- ≥1.5, 89.25/35.198 =2.53 > 1.5 ……..ok! Safe 2) Check for sliding ∑H/∑v < 0.75, 11.036/37.881=0.2913 < 0.75 ...ok! Safe 3) Check for over stresses In order to avoid lifting up the structures heel forces and tension occurrence at the base. The forces must pass through the middle third of the structures base. . The forces must pass through the middle third of the structures base (i.e. (e= B -X<B/6)) 2 X=∑M /∑V =54.052/37.881=1.426 e= 2.46 B -x = -1.426=0.196 2 2 e<B/6=2.46/6=0.46 0.196=e<=B/6=0.46, therefore it’s ok! Page 72 Assosa Water Supply Project Thus the structure is safe for all condition. 5.7 Design of Retaining Wall This is a structure place at stone angle normal to the direction of the fill of the water to retain the end of the approach and, to support the loads of the structure built . In order to prevent out flanking of water towards the main canal and safely over pass the discharge during high flood time. It is usually constructed from masonry or gabions and provided at both banks. Data available Height of retaining wall above the foundation =H++freeboard =1.5+0.946+0.5m (assumed)=2.9463m Top width of retaining wall=0.4m (with vertical water face) Assuming back slope of 1V:0.5H Angle of repose =30o Ranking coefficient of active earth pressure Ka= 1 sin 1 sin 30 = =1/3 1 sin 1 sin 30 5.7.1Structural analysis of retaining wall Force acting on a retaining wall - Weight of retaining wall - Weight of soil - Active earth pressure Page 73 Assosa Water Supply Project - Water pressure - Uplift earth pressure 1) Weight of retaining wall W1=A1*m*l=0.5*3*24*1=36KN , where m= Unit weight of massonary = 24KN/m3 W2= A2*m*l=0.5*3*1.5*24*1=54KN W3=A3*m*l=0.5*2.46*24*1=29.52KN 2) Weight of soil W4=A4*s*1=0.5*1.5*3*19*1=42.75 KN , where s = Unit weight of soil = 19KN/m3 W5=A5*s*1=0.5*3*19*1=28.5 KN 3) Active earth pressure PA=0.5*Ka*s*H2=0.5*1/3*19*32=28.5KN 4) Water pressure Pw=0.5*w*H2*1=0.5*9.81*1.52*1=11.036KN 5) Uplift earth pressure U=0.5*H*w*B*1=0.5*3*9.81*2.46*1=36.199KN Table 5.3 Forces and moments on retaining wall Type Vertical Horizontal Level of forces(KN) forces(KN) arm forces +ve -ve +ve -ve Moment about toe KN.m from toe +ve moment -ve moment (m) Page 74 Assosa Water Supply Project W1 36 0.25 9 W2 54 1 54 W3 29.52 1.23 36.309 W4 42.75 1.5 64.125 W5 28.5 2.25 64.125 PA 28.5 Pw 11.06 0.5 U ∑ 36.199 ∑V+=190.77 28.5 5.518 1.64 ∑H+=11.036 ∑H- ∑V-=36.199 ∑V 1 59.36 ∑M+=227.56 ∑M-=93.378 =28.5 = 154.571KN.m ∑M=∑M+-∑M-=227.56-93.378=134.182KN.m , ∑H =17.464KN.m a) Check the stability against over turning M Fso= M 1. For no water condition = 227.56 =7.78>1.5 ….OK! 28.5 , where ∑M-=excluding hydrostatic and uplift force 2. Normal flow condition Fso=∑M+/∑M-=227.56/93.378=2.44>1.5…… ok! b) Check stability against sliding ∑H/ ∑V=17.46/154.571= 0.113<0.75…….Ok safe! CHAPTER SIX INTAKE AND PUMP 6.1 INTAKE 6.1.1 GENERAL Page 75 Assosa Water Supply Project The intake or intake works are the structures placed in a surface water source which consists of the opening strainers or grating through which the water entered and the conduit conveyed the water, usually by gravity , to a well or sump. From the well or sump, the water is pumped to the mains or treatment plant. The structure may be of stone masonry, brick masonry and R.C.C. or concrete blocks. It is to be constructed water tight and it should be designed for all forces likely to come upon it including the pressure due to water wave action, wind, floating derbies etc 6.1.2 SITE SELECTION Success of an intake greatly depends up on its location while selection of sie for an intake, the following mentioned points should be kept in mind 1. The intake site should be such that the water available is of best quality and can be easily and economically purified. 2. The intake should be located at such a site where sufficient quality of water remains available under all circumstances. 3. Site should be such that the intake work can provide more quality of water if required in future for expansion of water works 4. At selected site the velocity the velocity of flow in the source should gentle, otherwise heavy currents may endanger the safety of the intake towers and stirrup the silt from the bottom. 5. The site should be easily accessible without any obstruction and should be free from the effects of loads. 6. It should be near the treatment plant so that conveyance cost from the source to the works can be minimized. 7. It should not located in navigation channels generally polluted and may also damage the structure. 8. It should not be on curve in case o meandering river. If there is no alternative, then intake should be located on the outer bank and not on the inner bank. Water concentrated more near the outer bank although erosion problem will be there. Inner bank always keeps on silting and this may bock the intake and put it out of commission. 9. It should be located on the upstream side of the town. Water will not be contaminated due to sewerage disposal. 6.1.3 River Intake Types Types of river intake are 1. Intake wells Page 76 Assosa Water Supply Project 2. Weir intakes 3. Pipe intakes 1. Intake wells: this is a circular masonry tower, two to six meters in diameter, provided on the bank. The water flows in to the intake wells through the penstocks located at different levels. The penstocks can be closed or opened with valves. These penstocks face down stream to avoid the entry of silt. This type of intake is adopted for rivers, which have sufficient flow through out the year. 2. Weir Intake: water is drawn from the through a channel into a sump well. For rivers which are more or less dry in summer, a weir is built across the river to the required height, to store excess floodwater during the rainy season. A channel is provided from the river to the intake well from where water flows by gravity or is pumped. 3. Pipe intake: when a small quantity of water to be drawn the pipe intake ids economical. The required number of intake pipes is laid across the river bed. The pipes are supported on masonry blocks at regular intervals. The ends are provided with strainers and anchoreerd firmly by masonry blocks. The pipes carry water to a jack well. 6.1.4 Design consideration of Intakes The design of intake structure is generally specific. Rarely can a standard design be adopted for a given site without major modification s. Some design considerations that must be addressed in the design of each structure are listed below. 1. Intake Velocities: The velocity water entering the intake port is the single most important design value to be selected by an engineer. High intake velocities increase headless, entrain suspended matter , trap fish other aquatic animals .low velocities on the other hand require the intake port to be larger and so add to the cost of the structure 2. Intake Port Location: properly designed intake structures should provide water provide water treatment plant operators the flexibility to draw water from the stream with the best water quality. In order to achieve this multiple intake ports set at various levels are generally provided. 3. Gates: are used in intake structure to control inflow of water from the raw water source into the water conveyance system. Gates typically in intake structures are sluice gates. 4. Coarse screen-trash rack: intake ports should be equipped with a coarse screen to prevent large objects form entering the conveyance systems 5. Fine screen: Fine screens are used to remove smaller objects that nay pumps or other equipment. Page 77 Assosa Water Supply Project 6.1.5 Design of Intake structures 6.1.5.1 The inlet opening is sized such that from maximum day demand can be withdrawn from a single level at a maximum recommended velocity of 0.15 m/sec (Water Treatment Plant Design, AWWA) Q=0.119m/s, V=0.15m/s A=Q/V = 0.119/0.15 =0.79m2 Using square opening the sixe will be, b= √A =√0.79 =0.89m Therefore, square opening of 0.89*0.89 is to be provided 6.1.5.2. Design of Coarse Screen The coarse screen will be located at the intake slightly projected away from the intake gate. This will prevent derbies from interfering with the operation of the gate. The coarse screen will be constructed of flat bars attached to concrete seat projected from the intake tower. It is typically installed vertically The recommended spacing between bars is (50-100mm) Taking spacing of 50mm. Provide bar with size 10mm*50mm at a center to center spacing of 50mm. Check of head loss Using Kirecher’s formula for head loss through bar screen hl= ( w 4/3 * Va 2 ) *Sin <0.15 ,(maximum head loss) b 2g where hl = head loss w = width of bars b = clear space between the bars Va = velocity head = angle wich the bars make with the horizontal = dimensional coefficient that is a function of bars geometry and is equal to 2.42 for rectangular b 10 *10 3 4/3 (0.15)2 Hl=2.42( ) * *Sin (90) =3.246*10-4m 3 2 * 9.81 50 *10 =3.246*10-4mthemaximum head loss=0.15m………………….ok! Provide two ports bottom and top of intake tower. The bottom port should be at least 1mabove the bed of the river to prevent rolling bodies to enter in to the ports. Page 78 Assosa Water Supply Project 6.1.5.4 Design of Fine Screen (strainer) Fine screens are provided on the two circular intake conduits to trap sediments that are too small to be captured by coarse screen. Design Criteria (Water treatment plant design, AWWA) 1. Total area of clear opening in screen 200% or more than the area of channel protected by the screen. 2. Maximum head loss should be limited to 0.8-1.5m 3. Velocity through hole is 0.15-0.3m/s. it is recommended that the velocity be near the lower limit to prevent the entry of impurities. 4. Opening the strainer hole be 6-9mm. 5. Discharge through screen= 119*10-3m3/s Assume (take) velocity through the screen 0.18m/sand height of strainer 0.45m. Aeff = Q/V = (119*10-3m3/s) /0.18m/s = 0.661m2 Agross = 2 * Aeff = 2 *0.661 = 1.322m2 Perimeter = Agross / height = 1.322m2/0.45m=2.94m Diameter = perimeter / 3.14 = 0.936m Provide cylindrical strainer of height 0.45m and diameter 0.936m 6.1.5.5 Sump Well In design of sump well care must be exercised To maintain sufficient depth of water to avoid air entry during drawdown To obtain uniform distribution of inflow Design criteria Detention period = 30min(t) Velocity in suction ppipe =2m/s (1.5-3m/s) Ratio of bell mouth diameter of suction pipe =D/d (1.5-2) Page 79 Assosa Water Supply Project Minimum width of sump well =2nD Where n=number of units D=diameter of suction pipe Submergence of pump to prevent air entry, H> 2D Bottom clearance of suction bell mouth= D/4 to D/2 Volume of sump well = t* Q = 30*60*119*10-3 =214.2m3 Diameter of suction pipe Velocity in suction pipe is 2m/s A=Q/V=0.5*0.119/2 =0.02975 A=∏d2//4 d=√4A/∏ =√4*0.02975/∏ d=0.195m 195mm diameter suction pipe is to be provided for each pump Opening of bell mouth, D/d =1.8 D=1.8*d D=1.8*0195 = 0.351m (351mm) Minimum water level to prevent entry of air during drawdown is H min= 2*D =2*0.351= 0.702m Assume depth below river bed =1.5m Min= width of sump well =2nD =2*3*0.702 =4.212 Take width 4m Provide free board = 0.5m Depth from top of ground level river bed Total depth =0.5m + 1.5m +3m =5m Correctional area =214.2m3/5m =42.89m2 ,providing rectangular , dimension of sump is 4*11m 6.1.5.6 Design of Overflow Conduit The pump unit installed for the first phase should have a capacity of maximum daily demand for the year 2018. But the sump well is designed for maximum daily demand for the year 2028. Therefore, there is an overflow discharge. Q overflow=Incoming discharge-Pumping rate per 2018 =119-39.44 =79.56l/s Taking velocity of 0.6m/s, Page 80 Assosa Water Supply Project Area of overflow conduit = Q overflow/V =79.56* 10-3m3/s/0.6m/s =0.1326m2 D=√4A/∏ =√(4*0.1326)/∏ =0.411m 450mm diameter pipe for overflow need be provided. 6.1.5.7 Design of delivery pipe Delivery pipe designed for the maximum day demand for the year 2028 which is 119l/s. Assuming a velocity of 0.9m/in the pipe, the required diameter of pipe will be D= √4*0.119/0.9*∏ =0.410m , take D=450mm So provide a 450mm cast iron main is provided. 6.2 Construction The intake structure should be constructed from R.C.C structure to with stand the water pressure and some impact force due to the rolling stoned and logs. The foundation depth should be below the normal scour depth the normal scour depth. The steel sluice gates are provided at the openings or the impacts should have a capacity to resist lateral pressure 6.3 Pump 6.3.1 General Pump is a mechanical device to increase the pressure energy of a liquid. In most of the case pump is used for raising fluids from a lower level to a higher level. This is achieved by crating a low pressure at the inlet or suction end and high pressure at the outer or delivery end of the pump. 6.3.2 Pumping design parameter Capacity The capacity of a pump is the volume of liquid pumped per unit of time which usually are measured in liter per second or cubic meters per second Head In pump system the head refers to both pump systems having one or more pumps and corresponding piping system. The height to which a pump can raise liquid is the pump head and the head required to overcome the losers in a pipe system at a given flow rate is the system head. The head against which the pump must work when water is being pumped is called total dynamic head. Efficiency Page 81 Assosa Water Supply Project Thee pump should be selected to operate near its peak efficiency point. In typical water supply applications, pumps operate over a bond of head conditions. Therefore they can not operate at their peak efforts all the time. Shut off and Run out Continued operation condition will result in damage to the pump from over heating. The higher discharge head can dam age piped and valves from excessive pressure and higher power requirements can overload pump driver. 6.3.3 Determination of pipe size from sump well to treatment plant (phase 1) a) diameter of suction pipe q = 39.44l/s Velocity of flow in the pipe may vary from 0.8m/s to 1.8m/s Take v = 1.8m/s A = Q/V = (39.44*10-3m3/s)/1.8m/s = 0.0219m2 Area= D 2 4 , d= 4* A = 4 * 0.0219 =0.167m=167mm So provide d=200mm (available in the market) Check velocity of flow V Q 0.03944 1.255m / s A * 0.2 2 4 V 1.255m / s 1.8m / s.........ok! b. Diameter of delivery pipe To determine economic diameter of pumping main we use lea formula D 0.97to1.22 Q Where Q is in m3/s D-economic diameter of pipe in (m) Assuming, D 1.00 Q 1.00 39.44 *10 3 0.199m 199mm Provide pipe size of D=200 mm (market available) V Check velocity of flow Q 0.03944 1.255m / s A * 0.2 2 4 Page 82 Assosa Water Supply Project V 1.255m / s 1.8m / s.........ok! 6.3.3.1 Determination of total lift of the pump The total head against which the pump should work includes discharge lift and total loss of head due to friction, entrance, exit etc in suction and rising mains hf fLV 2 2 gd Where h f =head loss in (m) L=length of pipe in (m) V=velocity of flow in pipe(m/s) g=acceleration due to gravity f=dimensionless friction factor Cast iron is selected for rising main. Length of pipe from pumping station to treatment plant. L =0.555Km=555m f=0.02(for cast iron) V Q 0.03944 1.255m / s A * 0.2 2 4 I) h f fLV 2 0.02 * 555 *1.255 2 4.46m 2 gd 2 * 9.81 * 0.2 II) Entry loss, he V2 (1.255) 2 0.040m 2 * (2 g ) 2 * (2 * 9.81) III) Head loss due to construction such as valve pipeline (h1) h1 kV 2 0.5 * (1.255) 2 0.0401m 2g 2 * 9.81 k=0.5 for circular pipe H L h f he h1 4.46 0.040 0.040 4.54m Static head against which the pump lift is Hs= (elevation of treatment plant –elevation of sump well) +depth of sump well below ground level) Hs= (1470-1460) +5=15m Hence total dynamic head (Hf) =Hs+HL Hf =15+4.54 =19.54m Page 83 Assosa Water Supply Project Therefore for the first phase two pumps one as stand by each discharging a capacity of 39.44l/s and head of 19.54m required for the second phase one additional pump with delivery head of 19.45m is required. 6.3.4 Power required of pump (phase i ) The water hoarse power = qwh/75 = 39.44*10-3*1000*19.54/75 = 10.28Hp The power input to the pump = Pp = WHP/EP, where = efficiency of pump = 10.28/0.8 = 12.85HP Power required of pump for the second phase I.e. from 2018 – 2028 The water horse power = QWH/75 , where Qmax = maximum flow rate at 2028 = 119l/sec WHP = QWH/75 =119*10-3*1000*19.54/75 =31.00Hp 6.3.5 Determination of pipe size from clear water well to reservoir (phase I) a) Diameter of suction pipe Q = 39.44*10-3 V = 1.8m/s…………range between 0.8 to 1.8m/s A =Q/V = 39.44*10-3/1.8 = 0.0219m2 d= 4* A = 0.167m =167mm Therefore provide d =200mm (market available) b) Diameter of delivery pipe To determine economic diameter of pumping main we use lea formula D = 0.97 to 1.22 Q , take d = 1.00 Q =0.199m =199mm Therefore provide D = 200mm (market available) 6.3.6 Determination of total lift of the pump from clear water well to service reservoir (phase I) Friction loss (hf) =flv2/2gd Cast iron is selected for the rising of main length of pipe from clear water well to service reservoir is 5km L = 13888.88m=13.88Km F = 0.02 (for cast iron) Page 84 Assosa Water Supply Project V= Q/A= 0.03944/3.214 *0.22/4 =1.255m/s i) Hf = flv2/2gd = 0.02*13888.88*1.2552/2*9.81*0.2= 111.49m ii) entry loss(he) = v22(2g)+ 0.04m iii) loss due to valve and pipe fitting hl = kv2/2g= 0.5*1.2552/2*9.81=0.04m HL =hf+he+hl = 111.57+0.04+0.04= 40.22m Static head against which the pump lift Hs = elevation of service reservoir – elevation of clear water well+4.42m = 1720 -1470 +4.42 = 254.42m H is to prevent air entry Total dynamic head = 254.42 +111.57 = 365.99m Therefore from treatment to service reservoir two pumps is needed one as stand by each discharging a capacity of 39.44l/s and the head of 365.99m is required for the second phase one additional pump is required to deliver the head of 365.99m 6.3.7 Power requirement of pump from clear water well to service reservoir The water horse power =QWH/75 = 39.44*10-3*1000*365.99/75 = 192.46Hp The power input to the pump Pp = WHP/Ep = 192.46/0.8 240.58Hp Where, Ep = efficiency of pump Power required for the second phase The water horse power =QWH/75= 119*10-3*1000*365.99/75 = 580.7Hp 6.3.7.1 Selection of Suitable type of pump Criteria for the selection of type of pump For proper selection of a pump it is necessary to brave certain essential data on the pump installation The information should includes 1) Nature of liquid to be pumped 2) Capacity of pump 3) Suction condition 4) Discharge condition 5) Total head 6) Location of geometrical in doors ,outdoors ,elevation….etc Page 85 Assosa Water Supply Project After having the idea of essential data on the pump installation the following points may be kept in mind while selecting any pumping necessary for the water works. 1) Reliability of service – it should be reliable and should not fail suddenly and cause trouble 2) Capacity – it should be capable of pumping required quantity of water 3) Cost –it should be cheap in initial cost 4) Power – The which issued for running pump should be available easly at low cost 5) Maintenance – the maintenance cost of running ump be as less as possible 6) Efficiency – pump should have high efficiency 7) Depreciation – pump should have long life and depreciation 8) Promptness – it sho0uld be prompt enough in service Considering all the above factors, among the available type of pump we select centrifugal pump out of the other type of pump, because centrifugal pump is used in most water supply system due to its satisfactory and economical than the other type of pump and fulfils all the above criteria. Generally from the above consideration for Assosa town water supply projects to lift water from sump well to treatment plant one working and one stand by multistage centrifugal pump which has a capacity to lift a head of 19.54m and a discharge of 0.03944m3/s connected parallels should be provided and also to lift a water from clear water well to service reservoir .for the second phase two working and one stand by multistage centrifugal pump is required which has a capacity to lift 365.99m from sump well to treatment plant and a discharge of 0.119m3/s and which has a capacity of lift 19.54m from clear water well to service reservoir and a discharge of 0.119m 3/s connected parallel should be required Page 86 Assosa Water Supply Project CHAPTER SEVEN 7.0 WATER QUALITY AND TREATMENT 7.1. Objective of treatment The objective treatment process is to remove all the undesirable impurities, to the extent where they do not cause any trouble to human health and water is available to the consumers as per health standards. Following may be the objects. To remove color, dissolved gasses, and murkiness of water. To remove objectionable taste and color. To kill the troublesome bacteria To estimate the corrosive properties of water .this treatment is essential from pipes and pipe fittings safely point of view. Page 87 Assosa Water Supply Project To make safe for drinking and domestic purpose, and also for various industrial purposes like brewing, dying, stream boilers etc. 7.2. Water quality analysis The quality of raw water should be compared with the world health organization (WHO) drinking water quality guide lines and treatment will be done for unacceptable parameters. In order to remove suspended solids, biological and microbiological impurities, high turbidity due to iron and floating or other non chemical pollution, color odor and taste an appropriate and sound treatment must be carried out before supplying the water for the community. 7.3. Treatment process Treatment process have been given here .it is not essential that all these process will have to be employed at all places, but it depends up on the quality of raw water .in the case of raw water ,obtained from lakes, screening and sedimentation are not required ,because suspended and floating debris have already settled in the lake basin. But aeration is a must because lake wastes have generally no treatment is required. Only disinfection may be done and supplied to the consumers therefore, the character and degree of treatment directly depends up on the nature of water or in other words on the source. Screening –used to exclude floating mater, it is done just at the intake. Aeration – employed where elements causing taste and odor have to be removed. Sedimentation and coagulation – in this process suspended impurities like silt, clay, sand, and some bacteria are removed. Filtration – employed to remove very fine particles and colloidal matter which may have escaped from sedimentation process ,micro-organisms are also removed largely. Other processes – used in specific cases ; - removing hardiness if it is beyond permissible limits. - Removing color taste and odor if any. Page 88 Assosa Water Supply Project -Removing iron and manganese if present. -maintain fluorides between 1to 1.5 p.p.m by adding if in deficiency and removing if in excess. 7.4 Treatment plant location Correct location of the plant plays a very important role in its success. A comparative study of site involves a number of considerations such as All the processes should be located in such a sequence that water may be flowing from one process to the other. Elevations of different processes should be such that no pumping is required and water keeps on flowing from one plant to the other. All plants should be located in such a way that minimum area is covered by it .adequate place for the future extension. Residual colony should be located by the side of the water works. This facilitates better working and control on the working of different units. A well establishment laboratory should be located at the site so that the quality of water may cheeked, before treatment and after treatment Physical characteristics of the site will affect construction. Flooding, foundation conditions, ground water level and site preparation including clearing, grading and drainage are factors which influence directly the cost of the plant. In the final analysis selection of a site will depend on analyses involving engineering and operation costs and a judgment of the factors which can not be expressed in dollar values. As mentioned above the site should be adequate for ultimate needs surplus land is preferable. Lay out of treatment plant A complete water treatment plant consists of; Intake works including pumping pumping plant Sedimentation and coagulation Filtration Disinfection Pure water storage reservoir Page 89 Assosa Water Supply Project Pumping plant for pumping purified water from clear water storage reservoir to the service reservoir If water is hard, sometimes, softening plant is used, before the filtration plant. 7.5 Treatment plant units The most common treatment units used in the treatment of surface water are the. They are selected based up on the quality of the raw water to be treated. The order of various treatment plants is 1. balancing chamber 2. mixing chamber 3. flocculation 4. sedimentation 5. filtration 6. disinfection 7. clear water well 7.6. Design of treatment plant units 7.6.1. Balancing chamber It is located above all the components so that gravity flow to the treatment is maintained. From the intake structure the raw water is conveyed to the balancing chamber. The balancing chamber is recommended to make the flow current free (stabilization of current) so that the work of the treatment plant is not disturbed highly and continuous flow is attained. Maximum day demand=0.055217 m3/sec Detention time=15 min Volume =0.055217*15*60=49.695≈50m3 Therefore provide 50m3balancing chamber in the first and second phase. 7.6.2. Mixing chamber Flush mixer is used to provide rapid mixing so as to disperse the coagulants in the raw water. Page 90 Assosa Water Supply Project A mechanical flush mixer is used because they have a reliable and continuous supply of power and they are efficient. Capacity of flush mixer = maximum day demand * detention time Assuming detention period = 45sec Capacity of flush mixer = 0.055217m3/sec*45sec=2.485m3 Therefore provide and 1.8m depth of mixing chamber. 7.6.3. Flocculation The term flocculation is used to denote the process of floc formation. floc is a thick insoluble gelatinous precipitate produced when coagulant is added to the water and thoroughly mixed. The floc has the property of arresting the suspended impurities in water during its down ward settlement to wards the bottom of the tank. In the flocculation chamber, after sever agitation, mixer is kept slowly agitated for about 30min.during this period, coagulants get necessary contact opportunity and develop floc after the development of floc, the mixture is still kept slowly agitated to increase the number of collisions or contact with water. The slow agitation of mixture after the vigorous agitation is called flocculation. The two types of flocculators are mechanical flocculator and hydraulic flocculator. In Mechanical flocculator the velocity gradient is created by mechanical power input. They also require extensive maintenance and the system is complex. In hydraulic flocculators hydraulic energy provides the necessary velocity gradient. However, due to these difficulties with mechanical flocculation techniques, flocculators using hydraulic energy are appropriate for water treatment plant in developing countries. The most widely used hydraulic flocculator is the baffled channel flocculator (Schulz and Okun 1984) .it is widely used in developing countries and performs efficiently over a wide range of flows. Baffled channels can be classified in to horizontal flow and vertical flow flocculator. Horizontal flow flocculator with around the end baffles are some times preferred over vertical flow flocculator with over and under baffles because they are easier to drain &clean 7.6.3.1 Design of horizontal baffled channel flocculator Page 91 Assosa Water Supply Project With a horizontal baffled channel flocculator, mixing is accomplished by the change in direction of flow of water through channels this change creates head loss in the channels, which in turn creates a velocity gradient for slow mixing. Guidelines for the design and construction of baffled channel flocculator horizontal. Distance between baffles should not be less than 45cm to permit cleaning. Clear distance between the end of each baffle and the wall is about 1.5times the distance between baffles, should not be less than 1.0m. Depth of water should not be less than 1m. Avoid using the asbestos-cement baffle because they corrode at the PH of alum coagulation. Decay resistance timber should be used for baffle; wood construction is preferred over metal parts. Detention time varies from 15 to 30 min. The water velocity varies from 0.1to 0.3m/s. Velocity gradient should vary between10 to100sec -1 loss of head is 15 to 60 cm (source SCHULZ & OKUN) The flocculator will be designed for a maximum day demand of the town and plus treatment loss of around 5% of the maximum day demand. The flocculator is divided in to three sections of equal volume, each section having constant velocity gradient of 55, 40, 25sec-1 respectively. Maximum day demand=0.055217m3/sec Qmax = Q+5 %( Q) = 0.055217+ (5/100)*0.055217m3/sec =0.058m3/sec Length of flocculator is taken as 5m - Viscosity of water (µ) =1.14*10-3Kg/m-sec -density of water (ρ) = 1000Kg/m3 -roughness coefficient of baffles (f) = 0.3 Page 92 Assosa Water Supply Project -detention time for the total section = 18min Design of the first flocculation basin section -detention time=6min -velocity gradient=55sec-1 -water velocity=0.3m/sec -depth of water=1.8m -flocculation time=18min Total volume of flocculation V=Q*t V=0.058*20*60=69.6m3 Top width of flocculator,W W=V/A = = =7.73m Width of each section = 7.73/3 = 2.6m Number of baffles in the first flocculation section is given by: 2 2* *t H * L *G 3 * n Q * (1.14 f ) 1 Where n = number of baffles in the basin H = depth of water in the basin (m) L = length of the basin (m) G = velocity gradient (S-1) Q = flow rate (m3/s) t = detention time(s) = density of water (kg/ms) = dynamic viscosity (kg/ms) f = coefficient of friction of the baffles Page 93 Assosa Water Supply Project 2 *1.14 *10 3 * 6 * 60 1.8 * 5 * 55 2 3 Therefore, n * 74 0.058 1000 * (1.14 0.3) 1 Spacing between baffles, s L 5 0.067m n 74 Since 0.067m is below the minimum range of design criteria, we take the minimum spacing between baffles as 0.45m So, number of baffles (n) = L 5 = =11.00 spacingbet weenbaffle s 0.45 Spacing between baffles and the walls is = 1.5*distance between baffles =1.5*45cm =0.675cm Head loss in the flocculation section h * t * G 2 1.14 *10 3 * 6 * 60 * 55 2 = 1000 * 9.81 *g = 0.126m Design of second flocculation basin section Detention time = 5min Velocity gradient =40 sec-1 Number of baffles in the second flocculation section, 2 *1.14 *10 3 * 6 * 60 1.8 * 5 * 40 2 3 * n 32 0.058 1000 * (1.14 0.3) 1 Spacing between baffles, s, s L 5 0.156m 0.45m n 32 Since 0.156m is below the minimum range of design criteria, we take the minimum spacing between baffles as 0.45m So, number of baffles (n) = L 5 = =11.00 0.45 spacingbet weenbaffle s Page 94 Assosa Water Supply Project Spacing between end of baffles and the walls is = 1.5*spacing between baffles = 1.5*0.45m = 0.675m Head loss h = 1.14 *10 3 * 6 * 60 * 40 2 1000 * 9.81 h = 0.0669 (say 0.07m) Design of third flocculation basin section Detention time = 5min. Velocity gradient = 25sec-1 Number of baffles in the third flocculation section 2 *1.14 *10 3 * 6 * 60 1.8 * 5 * 25 2 3 n * 0.058 1000 * (1.14 0.3) 1 n 23 Spacing between baffles, s s L 5 0..217m 0.45m n 23 Since 0.217m is below the minimum range of design criteria, we take the minimum spacing between baffles as 0.45m So, number of baffles (n) = L 5 = =11.00 0.45 spacingbet weenbaffle s Spacing between baffles and the walls is = 1.5*spacing between baffles = 1.4*0.45 =0.675m Head loss = =0.02614m Total head loss through the flocculation sections = 0.126+0.07+0.02614 = 0.22m------ (.15-.6m) ok! The second phase to the year 2028; Three similar horizontal flocculators as standard above is to be constructed. Page 95 Assosa Water Supply Project 7.6.4 SEDIMENTATION The sedimentation process in water treatments provides for the settling and removal of flocculated particles prior to filtration. The removal efficiency in the sedimentation basin determines the subsequent loadings on the filters and, accordingly has a marked influence on their capacity, the length on the filters and quality of the filtered water. The two major classifications for the design of sedimentation basins are:- Horizontal – flow unit - Up flow unit The design of such unit include:-Shape - Detention time -Number of basins - Volume of sludge storage -Dimensions - Method of sludge removal -Velocity - Inlet and out let arrangements -Direction of flow - characteristic of the in coming flocculated water The horizontal – flow sedimentation basin is preferable and chosen for our treatment due to the advantage of It is widely used in the world because of its efficiency and inherent simplicity. It is with out mechanical sludge removal, so that does not require no important equipment and labor for cleaning. Constriction cost is low, permitting over sizing. Operational and maintenance are simple. 7.6.4.1 Design of horizontal flow sedimentation For the design purpose, the horizontal flow sedimentation tank may be divided in to four zones. Inlet zone Settling zone Page 96 Assosa Water Supply Project Sludge zone and Outlet zone The sedimentation tank is designed with the assumption that the flow remains steady and all the suspended particles are uniformly distributed on the full cross section of the tank at right angles to the flow for the full length of the settling zone. The inlets and outlets are designed in such a manner that they cause minimum disturbance to the flowing water in the tank. The flow is designed to meet the following requirements, The amount of water flowing out from the tank in 24 hours should at least be equal to the daily demand. Velocity of flow should be so adjusted that suspended impurities of coarser nature are removed. The design of sedimentation tank is governed by; -the quantity of water to be treated -the selected detention period -the selected surface loading rate (over flow rate) Design of inlet zone The velocity through the perforated baffle is about 0.2-0.3m/sec. The head loss is estimated to be 1.7 times the velocity head. Diameter of holes is 5cm; recommended range is 3-5cm. -Taking a velocity of 0.25m/s -Total area of opening = = (0.058m3/s)/0.25m/s=0.232m2 -Area of each opening with a diameter of 50mm; = =0.00196m2 -Number of baffle holes required= 0.232/0.00196 = 118 -Head loss= Page 97 Assosa Water Supply Project Design of settling zone As soon as a particle enters the settling zone, two forces act up on it. The flow of water imparts horizontal force while gravitation force develops vertical component on the particle. The particle moves under the influence of both this forces and traces a parabolic path. Before entering the outlet zone, if a particle reaches the settling zone it is considered removed. The assumptions for design of settling zone are For installation planed with new technology and good operation the surface loading rate is taken with in a range of (30-40m/day) [Okun, 1984]. - Surface loading rate=35m/day = 4.05*10-4m/sec - Detention time = 2 hr (2-3hr) -length to width ratio = 4 ( >3) Volume of tank (V) = detention period*design flow = 2hr*0.058m3/sec*3600sec/hr =417.6m3≈418m3 Surface loading rate = 35m/day=4.05*10-4m/sec= Therefore, W=6m and , where L=4*W L=24m Depth (d) = Check for detention period (2-3hr) -----ok! T= Check for horizontal flow v= (4-36m/hr)---ok! Therefore provide a rectangular settling tank with, Length= 24m Page 98 Assosa Water Supply Project Width= 6m Depth= 2.9m The some standard and number of unit should be provided for the phase II. Design of sludge zone The sludge zone is designed to accommodate all the settled particles during the process of sedimentation. It should be located at such a position that while cleaning the sludge, least disturbance is caused to the settling water. Normally the bottom floors of the tanks are made to wards one side or to wards the center of the tank. Cast iron pipes, fitted with gate valves are provided at the lowest points of the floor, from where sludge is removed under hydrostatic pressure. To facilitate drainage of the basin, the floor should be slope about 10% from the side walls to the center line and 5-8% from the outlet end to the inlet end. Provide depth of sludge zone =0.3m Therefore total depth of sedimentation tank with a free board of 0.3m will be; =depth of settling zone +depth of sludge zone+ free board =2.9m+0.3m+0.3m =3.5m Design of outlet Zone Weir or perforated bounders are the most common structures for with drawing the effluent water form the basin. Weir lengths should be selected to prevent high velocities of approach and disturbance of the sludge layer. The formula for acceptable weir length (adopted, from IRE, 1981) L 0.2 Q Hvs Where L = Combined weir length (m) Q = Flow rate (m3 / day) H = Depth of tank (m) Vs = Settling velocity (m/day) For the phase I L 0.2 * 4770.75 9.08 m 9m 2.9 * 35 Page 99 Assosa Water Supply Project For the phase II L 0.2 * 10257.41 2.9 * 35 19.53 20 m Provide width of each weir as 1.5m. 7.6.5 FILTRATION Filtration is a physical, chemical and biological process for separating suspended impurities from water by passage through a porous media. Screening of water removes larger suspended solids from water and sedimentation following chemical coagulation removes most of the residual suspended matter. However, there will still remain suspended matter and some fine floc particles. Flirtation of water is done to remove them and to produce still further positive bacterial content in the water. Filtration is also done to ensure safe, clear, and attractive water. Filtration process is the most important part of water purification. It consists of passing water through a thick layer of sand. During its passage through sand, the following effects take place, I.Fine suspended and colloidal matter which may be present in water is removed almost completely. II.Chemical characteristics of water get reduced. III.The number of bacteria is considerably reduced. These phenomena can be explained on the basis of four actions Mechanical string Sedimentation Biological metabolism Electrolytic changes Performance of filter unit is predicted in terms of; - The influent characteristics - The characteristics of media Page 100 Assosa Water Supply Project - The mode of operation of filter Classification of filters Filters may be classified under two heads 1. Pressure filters 2. Gravity filters I. Slow sand filters and II. Rapid sand filters I.Slow sand filters Consists of an enclose tank, under drainage system, base material or gravel, filter medium of sand and other ancillary fixtures for the proper functioning of the filter. They installed in a water tight tank made from stone masonry, brick masonry or cement concrete. The floor and sides are all coated with water proofing agent. Generally slow sand filters; - Requires large area for installation - Coagulation is not required - Construction is simple - Cost of operation is low - High initial cost of both land and material - High efficient in the removal of bacteria but less efficient in the removal of color and turbidity. - Not flexible for meeting variation in demand. - Skilled man power is not essential - The filter can be constructed of local labor and material; it is suitable for small towns and villages where land is cheaply available. - Rate of filtration is low II. Rapid sand filters Consists a rectangular water-tight tank made from stone masonry or concrete. The tank is rendered water-tight by applying a coat of water proofing material. Generally rapid sand filters; - Requires small area for its installation Page 101 Assosa Water Supply Project - Construction is complex - Cost of operation is high - Low initial cost of both land and material - Less efficient in removal of bacteria but it have high efficient in removal of color and turbidity. - Quit flexible for reasonable fluctuation of demand - Method of cleaning is short and speedy. - Skilled man power is essential - It is suitable for big cities where land cost is high and variation in demand of water is considerable. - Rate of filtration is high Based on the rate of filtration, rapid sand filter is preferable. In most cases, when population growth is high and the town expands extensively, as for assosa town case, rapid sand filter is recommended from economical point of view. 7.6.5.1. Design of rapid sand filter Important purification effects in rapid sand filtration is adsorption of impurities having an electronic charge of the filter bed material are supplemented by the electric kinetic charge produced by the high rate of water. The design consideration for rapid sand filter included I. filter unit II. Filter media III. Under drains IV. Back washing arrangement V Filter control system Filter Unit. The size of a filter unit is determined by the required amount of water needed. It consists of two or more units of sizes depending upon the capacity of the plant. - Depth of tank ranges between (2.5-3.5m) Page 102 Assosa Water Supply Project - Length to breadth ratio of between (1.25-1.33) - Surface area of each filter ranges between (10-80m2) - Rate of filtration is between (4000-5000l/m2/hr) Based on the above recommendations - Assume rate of filtration =5000l/m2/hr - Total quantity of water to be treated = 0.055217m3/hr =0.1988*106 l/hr - Total area of filter bed required(A) = = 39.76m2 ≈40m2 = - Number of filter units required, (Water Supply Eng ’g Santosh K. Garg 1995) N Where; Q = maximum day demand in million litters per day = 24*0.1988*106l/day = 4.7712*106l/day N = 1.22* = 2.66 ≈ 3 units At least one filter unit should be added for emergency or during repair work of any of the other. Hence adopting four units is reasonable. 40 =13.3 m2. ( 10-80 m2) ----ok! 3 - Area of each filter unit = - Assuming length to width as 1.3 A=L*W=13.3 m2 but L=1.30*W 13.3 m2 = 1.30W 2 W= =3.2m L = 1.3*3.2m = 4.2m Therefore, provide four numbers of rapid sand filters with the size of each unit 3.2*4.2.one unit is required for stand by or during repair work of any other units. The same standard and number of filter units will be provided in the second phase. Page 103 Assosa Water Supply Project Filter media The choice of filter media is dictated by the durability required, the desired degree of purification and the length of filter run and ease of backwash sought. Sand is the cheapest filter medium and has been widely used. The ideal medium should have such a size and be of such a material that it will provide a satisfactory effluent, retain a maximum quantity of solid, and be readily cleaned with a minimum of wash water. The sand used in rapid sand filters should be free from dirt, hard resistance, and preferably of quartz or quartzite. Conventional rapid sand filter generally uses sand layer of effective size varying from 0.45mm to 0.55mm having uniformity coefficient (D 60/D10) ranging from 1.2 to 1.7. The sand depth, when used alone ranges from 600mm to 700mm in most applications. In standard rapid sand filters the filter medium may be underlain by 400 to 600mm gravel which serves to support the sand, permit the filtered water to remove freely to ward the under drain and also allows the wash water to move more or less uniformly upward to the sand. It is placed in 5 or 6 with the finest size on top. It is also specified that it should be hard, rounded, and durable, weight approximately 1600 Kg/m 3, be free from flat, thin or long pieces and contain no loam, sand, clay, shells or other foreign materials. Table 7. .A common grading and layer thickness are as follows:sand gravel Grading (mm) Thickness (mm) Grading (mm) Thickness(mm) 40 to 60 120 to 200 2.5 70 20 to 40 80 to 120 7.5 70 10 to 20 80 to 120 15 100 5 to 10 60 to 80 30 100 2.5 to 5 60 to 80 50 160 Total depth = 400 to 600 Total=500mm Total depth of filter media :Page 104 Assosa Water Supply Project = (depth of and) + (depth of gravel) = 700 mm + 500 mm = 1200 mm = 1.2 m 7.6.6. Under drain System The under drain system of a filter is an important component in the design and operation. The selection is based on the filter type and size, media characteristics, and the selected method of back washing. The under drain contain a central manifold and lateral that are perforated. The selected under drain system, - Collect the filtered water percolating down through the sand and gravel layers - Durable, reliable, and cost effective - Ensure uniform flow distribution of the back wash Design guide line for the design of pipe under drain system (NWS and DB 1988) 1. Ratio of length of lateral to its diameter should not exceed 60. 2. Diameter of perforations is the lateral should be from 6-12mm 3. Spacing of perforations along the lateral may vary from 75mm for the smaller holes to 200mm for the larger. 4. Ratio of total area of perforations in the under drain system to total cross sectional area of laterals should not exceed 0.5 for the larger holes and should decrease to 0.25 for the smaller. 5. Ratio of total area of perforation in the under drain system to the entire filter area may be as low as 0.002. 6. Spacing of lateral may be as great as 300mm 7. Rate of washing may be varied from 0.15-0.9/min. Design based on the guide lines -Area of each filter = 3.2*4.2 =13.44m2 Total area of perforation =0.3% of area of filter =0.003*13.44 = 0.04m2 Page 105 Assosa Water Supply Project Total area of lateral= 2*area of perforation =2*0.04 = 0.08m2 Assume diameter of lateral = 0.05m =0.002m2 Area of lateral = Number of lateral = = =40, (20 on each side of the lateral) Area of manifold= (1.5-2)*total area of laterals =1.5*0.08m2 = 0.12m2 Dmanifold = 0.4m Spacing of laterals = = = 0.21m (< 0.3m) ----ok! Length of lateral on each side of manifold= Assume spacing of perforation=20cm c/c Total area of perforation on one lateral= =0.001m2 = Number of perforation per lateral= = = 7. 5 (take 7) Area of each perforation = = =1.4286cm2≈1.43cm2 Therefore diameter of perforation = =1.349cm≈1.4cm Check; < 60 Page 106 Assosa Water Supply Project < 60 ………ok! Total number of perforation = number of perforation per lateral*number of laterals = 7*40 = 280 Area of perforation =1.43cm2 Total area of perforation = 1.43*280 = 400cm2 = 0.04m2……..ok! This is equal to the designed total area of perforation (0.04m2) 7.7. Back wash arrangements A filter unit is washed when filtering medium has become so dirty. Due to this dirt, when the water passes through the filter medium, it experiences frictional loss of resistance known as head loss. When the head loss exceed 1.5-2.5m, the filter needs cleaning. Washing is accomplished by reversing of water through the filter but using a much higher rate. Back wash is provided from an elevated tank. 7.7.1. Wash water tank The wash water tank is designed to store wash water at least for the two filters. Assume amount of wash water as 4% of filtered water in one day Assume rate of filtration 4m /hr The time required for washing one filter unit is 15min =0.25 hr is lost in one day for washing Quantity of wash water = (4/100)*13.44*23.75*4m/hr =50.534m3/unit The tank should have storage capacity to store wash water for at least two units. Therefore; capacity of wash water tank =50.534m3/unit*2unit =101.1m3 Depth of storage tank for wash water should be between 2.3-3.5m. Taking d=3m For a circular tank of depth 3m, the diameter will be; Page 107 Assosa Water Supply Project V=A*d D= = = 6.55m There fore provide wash water tank of 6.55m diameter and 3m deep with free board of 0.3m. 7.7.2. Wash water supply main Size of the down water pipe bringing the water to the filters for back washing be 40cm in diameter. The time taken for washing is 10 min. Velocity in the pipe while washing one filter unit. = =1.5m/sec < 3m/sec…... ok! Therefore, provide a wash water supply main having a diameter of 40cm. Wash water trough Wash water troughs serve to collect and carry to the main gutter the dirty water resulting from washing the filter. Assume a wash water rate of 0.6m/min (0.6-0.9m/min) Wash water discharge for one filter =0.6*3.2*4.2 =8.064m3/min =0.1344m3/sec Assuming a spacing of 1.6m for wash water trough (recommended 1.5-2m), this will run parallel to the longer dimension of the filter unit. Number of trough =3.2/1.6 =2 Discharge per unit trough = (0.1344m3/sec)/2 =0.0672m3/sec For the width of 0.4m the water depth of upper end is given by h=1.73 (source Steel and GC Ghee 1979) Q= 1.376*b*h3/2 Page 108 Assosa Water Supply Project 0.0672= 1.376*0.4*h3/2 h= 0.246m = 0.3m providing a free board of 0.1m (0.05-0.1m) Provide 2 troughs of 0.4m wide and 0.3m deep in each filter. 7.7.3. Pump for lifting wash water One pump with one stand by will provide for pumping water in to the tank which has to supply it to two filter unit in 24 hrs. Let the total quantity of water lifted in 8hr of one shift. = 14.135m3/hr Total capacity of pump required= Therefore provide one pump having 14.135m 3/hr capacities including one pump set as stand by. Assuming permissible velocity, v=1.3m/sec (0.6-1.55m/sec recommended) Area of a rising pipe= Q/v = (14.135/3600)/1.3 =0.0302m 2 Diameter of rising pipe, D= = 0.196m=200mm Assuming the lift of water including friction losses to be 15m, Therefore the horse power (HP) of the pump = = = 1718.055h.p Assuming efficiency of the motors and pumps as 80%and 70%, the B.H.P off the pumping sets. B.H.P =1718.055/(0.8*0.7) = 3067.955hp 7.8.Filter control system It is essential to control the rate of filtration, because, a sudden increase in the rate will make water to pass through the filter bed with out proper treatment or the dissolved gases may get released due to sudden increase in the negative pressure. On the other hand a sudden reduction in filtration rate will also release bubbles of gas present in the sand, making a hole through the filter bed. Therefore, to obtain a constant rate of filtration, a rate controlling device is fitted to the filter. Page 109 Assosa Water Supply Project There are two practical methods of operating filters and these differ primarily in the way that the driving force is applied across the filter. These methods are referred to as constant rate filtration and declining rate filtration. In constant rate filtration, when water is taken out of service for back washing or returned to service after back washing, the water level gradually rises or lowers in the operating filters until sufficient head is achieved to handle the flow. Thus, the rate changes are made slowly and smoothly without the abrupt changes associated with automatic or manual equipment. The head loss for a particular filter is evidenced by the water level in the filter box. When the water reaches a desired maximum level, back wash of that filter is required. Declining rate filtration provides significantly better filter effluent quality than constant rate filtration. Less available head loss is needed compared with that required for constant rate operation because the flow rate through the filter decreases toward the end of the filter run. The head loss in the under drain and effluent piping system, therefore, decrease and becomes available to sustain the run for a longer period than would be possible under constant rate operation with the same available head. The water levels in the filters should be 1.2m above the filter media at the beginning of a filter run and raise to full available depth of 3.2m before back washing becomes necessary. 7.9. Clear water well Clear water well is constructed in connection with the filter, which is used to reserve storage and to allow the plant to operate with out too frequent variation of its output rate. The size of the clear water well mostly varies from ¼ to 1/3 of the daily capacity of the plant. Quantity of water to be stored = = 7329.309/4 = 1832.33 Provide a depth of 3m, the area of the tank required =1832.33/3 = 610m3 Page 110 Assosa Water Supply Project Therefore, reservoir of plan area and depth m shall be provided with addition of free bored of 30cm 7.10. Coagulation The single most important step in removal of very fine suspended solids from water is proper coagulation. Once the coagulation step is performed properly, operation of the plant is comparatively simple. Its main objective is to unit several colloidal particles together to form bigger sized settle able flocs which may settle down easily. The principle of coagulation may be explained from the following 2 aspects. 1- Floc formation – when coagulant is added to the water and thoroughly mixed, it produces a thick insoluble gelatinous precipitate. This precipitate is called floc. The floc has the property of removing fine and colloidal particles quickly. 2- Electrical charge – the floc ions are found to posses the positive electric charge while all the colloidal particles have negative charge, therefore flocs attract the colloidal particles and cause their removal by settlement at the bottom of tank. The common chemicals generally used for coagulation are; 1. Aluminum sulphate 2. Sodium sulfate 3. Ferrous sulfate 4. Magnesium carbonate 5. Poly electrolyte 7.10.1.DOSAGE OF COAGULANTS The dosage of coagulants which should be added in the water depends on the following factors; - Kind of coagulants - Turbidity of water - Color of water Page 111 Assosa Water Supply Project - PH-value of water - Temperature of water - Mixing and flocculation time 7.11. Disinfection A safe water supply is the prime concern of any water supply project. Safty against disease is of utmost importance in water supply, especially the water borne, water related, or water based diseases such as cholera, typhoid, and many others. Even though a certain degree of disease causing pathogen removal is achived in treatment process such as flocculation and filtration, there still exist a significant number of pathogens that are not removed by these processes. This necessitates subsequent treatment to remove pathogens, which are conventionally carried out by disinfection. Disinfection is generally the final treatment process in water treatment train. Disinfection is carried out through chemical means. Requirements of a good disinfectant The following are requirements of a good disinfectant: It should be economical and easily available in bulk. from water and make it safe for the consumers. It should be able to destroy all the harmful bacteria and other organisms Disinfectant should immediately attack bacteria when mixed with water. odor and taste. treated water could be easily determined. After disinfection, the water should not become toxic and carry objectionable Disinfectant should be such that their strength or concentration in the Their dose should be such that there is always some residual concentration for protection of water from contamination during storage, and conveyance, through distribution system. Page 112 Assosa Water Supply Project In water supply, chlorine is the disinfectant almost universally, since it is the final safe guard for the quality the water, the necessity of the continuous and effective application of chlorine cannot be over emphasized. The objective of chlorination is to destroy pathogens in water and provide some additional protection against subsequent contamination. Chlorine dissolves more readily in cold water. In the liquid form it has a yellow color and a specific gravity of 1.4. Reaction rate increases with rise in temperature and lowering oof PH value. The gas is toxic, and irritating to eyes, impairs respiration, and can cause death at high dosages. Chlorination can be achieved in two ways: direct solution feed, where chlorine gas is fed directly into the treated water, or else using hypochlorite salts such as calcium hypochlorite and sodium hypochlorite. Hypochlorite tablets are used for emergency disinfection in times of disaster, when normal water treatment is not operating. Factors affecting efficiency of chlorine are 1. Nature of pathogens to be destroyed 2. Type and concentration of disinfectant 3. Temperature of water 4. Time of contact 5. Physical and chemical properties of water to be treated 6. PH (alkalinity/acidity) of water Page 113 Assosa Water Supply Project CHAPTER EIGHTH DISTRIBUTION RESERVOIR 8.1Service reservoir Distribution reservoir is also called service reservoir. Service reservoirs are used for storing the treated water with in or near to the demand (distribution) area, distributing the treated water to the customers. They are also designed to meet the water demand during fire break, pumps failure, repair, etc and used to balance the hourly fluctuation of water demand. 8.2 Types of reservoir Distributions reservoirs are classified based on their support, shape, and material of construction. A) Based on support of ground Distribution reservoirs are of two general types: 1. Surface reservoirs These reservoirs have little or no elevation above the ground and which are usually constructed of earthen, masonry, or a combination of both, or reinforced cement concrete. They can be circular or rectangular in shape. 2. Elevated reservoirs These reservoirs built entirely above the ground such as stand pipes and elevated Tanks. They help to reduce pumping cost by giving head for gravity flow distribution. They are usually of steel reinforced concrete or wood. Many surface reservoirs are built on hills and thus comprise elevated storage. B) Based on geometry Page 114 Assosa Water Supply Project Circular reservoir Rectangular reservoirs C) Based on material of construction Steel Reinforced concrete Masonry etc. 8.3 Purposes of reservoir Distribution reservoirs serve a variety of purposes as described below: A) With regard to water quantity 1. Storage for fluctuating demand: Reservoirs are filling when the rate of pumping exceeds the demand rate and are emptying when the reverse occurs. This action permits pumps to operate at constant rates throughout any one day and thereby allows the use of pumps of less capacity. 2. Fire storage The immediate availability of large quantities of water within the water supply system is required to safe guard the community against fire breakout. 3. Emergency / break down storage The storage of sufficient amount of water with in the system gives protection the failure of the pump, power driving motors, or a supply conduit. This against quantity of water depends on the time taken during the repair work, and as such it is variable, therefore, it is very difficult to estimate. B) With regard to pressure distribution 1. Equalizing pressure in the system. 2. Raising pressures at remote points from pumping stations. 3. Equalizing heads on pumps if the reservoirs are nearly pumping plant station. Page 115 Assosa Water Supply Project 8.4 Location of distribution reservoir Generally distribution reservoirs are located near the central portion of the distribution area. It is always better to construct them on high ground of city or town at such place where it can be constructed economically and also by considering the elevation of the highest building to be supplied The location of the proposed reservoir site selected should be to fully the gravity distribution system because it reduces the cost of pumping and also to enable a good flow to be maintained to those top most places 8.5 Accessories of reservoir Following are the various accessories, which are commonly provided in the reservoirs i. Inlet pipe for the entry of water. ii. Outlet pipe for the withdrawal of water. iii. Over flow pipe to prevent over flow of water. iv. Float switch to stop the pump when the tank is full. v. Float gauge to show the depth of water in the tank. vi. Washout pipe for washing out the suspended impurities in the tank vii. Manhole for providing entry into the tank. viii. Access ladder to inspect the top & bottom of the tank. ix. Ventilation for fresh air circulation in the tank. x. Chlorinator incase when the water is directly pumped in the over head reservoir from the tube wells 8.6 Determination of storage capacity of the reservoir Page 116 Assosa Water Supply Project The required reservoir capacity is determined by using 1. Analytical method 2. Mass curve 3. Sequent peak algorithm For the Assosa water supply scheme, the analytical and the mass curve methods are selected for their simplicity of calculation and interpretation. The long study of 24 hourly peak factors of the Assosa town Time 1 2 Hourly factor 0.3 0.3 0.3 0.3 0.3 0.6 1.1 2 1.8 1.6 1.5 1.4 Time 13 21 Hourly factor 1.3 1.3 1.3 1.5 1.6 1.4 1.2 0.9 0.7 0.5 0.4 0.3 14 3 15 4 16 5 17 6 18 7 19 8 20 9 10 22 11 23 12 24 When water is supplied for balancing the variable demand against a constant rate of pumping for 24 hrs The analysis of storage capacity can be calculated as follows. Phase I (2008 – 2018) Total demand of the town =3407.7m3/day Total demand of the town in liters per day=34077 Hourly demand of the town = 141987.5 liters Pumping hours=16 Page 117 Assosa Water Supply Project The calculation is as shown bellow in table Table 8.1 the analytical calculation of storage capacity for phase I Time Hourly (hr) Hourly Factor (1) (2) (3) supply(liters) Hourly demand(liter s) Cumulative hourly supply(liters) Cumulative hourly demand(liters) (5) (6) (4) Excess supply (liters) (5) – (6) +ve (7) demand(lit ers) (6) (5) +ve – (8) 1 0.3 0 42596.3 0 42596.25 42596.3 2 0.3 0 42596.3 0 85192.5 85192.5 3 0.3 0 42596.3 0 127788.75 127789 4 0.3 0 42596.3 0 170385 170385 5 0.3 212981.25 42596.3 212981.25 212981.25 6 0.6 212981.25 85192.5 298173.75 127788.7 5 454360 184583.7 5 425962.5 7 1.1 212981.25 156186 638943.75 8 2 212981.25 283975 851925 738335 113590 9 1.8 212981.25 255578 1064906.25 993912.5 70993.75 10 1.6 212981.25 227180 1277887.5 1221092.5 56795 11 1.5 212981.25 212981 1490868.75 1434073.75 56795 12 1.4 212981.25 198783 1703850 1632856.25 70993.75 13 1.4 0 198783 1703850 1831638.75 127789 14 1.3 0 184584 1703850 2016222.5 312373 15 1.3 0 184584 1703850 2200806.25 496956 16 1.5 212981.25 212981 1916831.25 2413787.5 496956 17 1.6 212981.25 227180 2129812.5 2640967.5 511155 18 1.4 212981.25 198783 2342793.75 2839750 496956 19 1.2 212981.25 170385 2555775 3010135 454360 20 0.9 212981.25 127789 2768756.25 3137923.75 369168 21 0.7 212981.25 99391.3 2981737.5 3237315 255578 22 0.5 212981.25 70993.8 3194718.75 3308308.75 113590 23 0.4 212981.25 56795 3407700 3365103.75 42596.25 Page 118 Assosa Water Supply Project 24 0.3 0 42596.3 3407700 3407700 Thus the reservoir capacity for phase I from the above table will be Maximum value of excess supply = 184583.75liters maximum value of excess demand = 511155liters capacity of reservoir = 184583.75+511155 =695738.75liters=695.739m3 For fire requirement (10%) = 69.574m3 Miscellaneous losses (3%) = 20.87217m3 Total recommended reservoir capacity = 786.1852m3 Say=800m3 of standard reservoir capacity Using mass curve method mas curve diagram for phase one cumulative supply and demand in miliun liters 4 3.5 3 2.5 2 cumulative supply comulative demand 1.5 1 0.5 0 0 2 4 6 8 10 12 14 16 18 20 22 24 -0.5 time in (hrs) Figure 8.1 mass curves for phase I Page 119 Assosa Water Supply Project Phase II (2018-2028) Total demand of the town =7329.309m3/day Total demand of the town in liters per day=7329309Hourly demand of the town = 305387.875liters Pumping hours=20 Pumping rate=366465.45liters/hour Thus the reservoir capacity for phase I from the above table will be Maximum value of excess supply = 855086.05liters maximum value of excess demand = 977241.2liters capacity of reservoir = 855086.05+977241.2=1832327liters =1832.327m3 For fire requirement (10%) = 183.233m3 Miscellaneous losses (3%) = 54.96982m3 Total recommended reservoir capacity = 2070.53m3 Say=2100m3 of standard reservoir capacity Provide additional two reservoirs with capacity of 500m3 and 800m3 for second phase Page 120 Assosa Water Supply Project Table 8.2: the analytical calculation of storage capacity for phase II Excess Time Hourly (hr) Hourly Factor supply(liters) Hourly demand(liters) (1) (2) (3) (4) Cumulative hourly supply (liters) Cumulative hourly demand(liters) (6) (5) supply (liters) (5) – (6) +ve value only (7) demand (liters) – (5) +ve value only (8) 1 0.3 0 91616.363 0 91616.3625 91616.363 2 0.3 0 91616.363 0 183232.725 183232.73 3 0.3 366465.5 91616.363 366465.45 274849.0875 91616.3625 4 0.3 366465.5 91616.363 732930.9 366465.45 366465.45 5 0.3 366465.5 91616.363 1099396.35 458081.8125 641314.538 6 0.6 366465.5 183232.73 1465861.8 641314.5375 824547.263 7 1.1 366465.5 335926.66 1832327.25 977241.2 855086.05 8 2 366465.5 610775.75 2198792.7 1588016.95 610775.75 9 1.8 366465.5 549698.18 2565258.15 2137715.125 427543.025 10 1.6 366465.5 488620.6 2931723.6 2626335.725 305387.875 11 1.5 366465.5 458081.81 3298189.05 3084417.538 213771.513 12 1.4 366465.5 427543.03 3664654.5 3511960.563 152693.938 13 1.4 0 427543.03 3664654.5 3939503.588 274849.09 14 1.3 0 397004.24 3664654.5 4336507.825 671853.32 15 1.3 366465.5 397004.24 4031119.95 4733512.063 702392.11 16 1.5 366465.5 458081.81 4397585.4 5191593.875 794008.47 17 1.6 366465.5 488620.6 4764050.85 5680214.475 916163.62 18 1.4 366465.5 427543.03 5130516.3 6107757.5 977241.2 19 1.2 366465.5 366465.45 5496981.75 6474222.95 977241.2 20 0.9 366465.5 274849.09 5863447.2 6749072.038 885624.84 21 0.7 366465.5 213771.51 6229912.65 6962843.55 732930.9 22 0.5 366465.5 152693.94 6596378.1 7115537.488 519159.39 23 0.4 366465.5 122155.15 6962843.55 7237692.638 274849.09 24 0.3 366465.5 91616.363 7329309 7329309 0 0 Page 121 Assosa Water Supply Project Using mass curve method mass curve diagram 8 cumulative supply and demand in 10^6 liters 7 6 5 4 cumulative supply comuulative demannd 3 2 1 0 0 2 4 6 8 10 12 14 16 18 20 22 24 -1 time in(hrs) Figure 8.2 mass curve diagrams for phase II 8.7 Depth and shape of service reservoir 8.7.1 Depth of service reservoir For any given quantity of water either shallow reservoir having long walls and large floor are, or alternatively a deep reservoir constructed with high retaining wall and smaller floor area. Factors influencing a depth of a given storage are Depth at which suitable foundation conditions are encountered Depth at which out let main must laid Slope of ground, nature and types of backfill The slope and size of the land available 8.7.2 Shape of service reservoir Circular reservoir is geometrically the most economical shape give, the least amount of walling for a given volume and depth, it has the attraction of allowing of construction thin reinforce concrete. Page 122 Assosa Water Supply Project 8.9 Structural Design of service reservoir 8.9.1 Water Tank (reservoir) Design Consideration The primary purpose of design is to achieve acceptable probabilities that the structure being designed will not become unfit in any way for the use it is intended. To accommodate the required amount of water and to ensure water tight structure, the reservoir must be designed using reinforced cement concrete that accounts for tensile forces as well as those due to bending. The different types of reservoirs depending on the geometry (Circular and Rectangular), supports (resting on the ground, under ground and elevated), and end restraints (free sliding, hinged and fixed at top and/or base) should be compared and selected based on their suitability and economic condition during the design of water containing reservoirs. For small capacities rectangular tanks are usually used. And for bigger capacities circular tanks are generally used to ensure economical and efficient system of work. The design of tank should also consider both full and empty conditions, and the assumptions regarding the arrangement of loading conditions so as to cause the most critical effects. When the structure is empty it must have strength to withstand the active pressure of any retained earth. The possible resistance of the earth, never certain to act, is generally ignored when designing for structure full of water. Important considerations have to be given in limiting the size of crack (mostly with no cracks) so that leakage does not take place. The design generally governed by the requirements of the elastic design method, but stability considerations are particularly important. The design has to take careful account of the construction methods to be used. The requirements for the elastic design method are listed as follows. Page 123 Assosa Water Supply Project Concrete grade class as C- 30 with a minimum cement content of 330 kg/m3 and has maximum water cement ration = 0.55, but the concert should not be more than the maximum cement content to keep the shrinkage down. The maximum cracked width is limited to 0.2mm for all faces of liquid containing or excluding structures, unless aesthetic appearance is critical, where 0.1mm is required to avoid staining of concrete. Minimum cover = 40mm Maximum bar spacing = 300mm The allowable tensile stresses in concrete than control cracks in concrete grade of C-30 shall be 1.44 N/mm2 and 2.02 N/mm2 due to direct tension and bending respectively. The allowable tensile stresses in steel taken as 100 N/mm2 using deformed bars for alternate wetting and drying exposure conditions. The maximum steel area in each of the two directions at right angle are 0.3% of the concrete area (0.15% near each face) for deter med bars. The operational processes with in the water and other industries dealing with fluids often require circular structures to ensure their systems of work carried out efficiently and economically. Hence circular tank is chosen for the design of Assosa town water supply project. The primary stresses set up with in the structure are usually a result of the ring tension generated by the contained liquid and the main reinforcement therefore consists of bond of circular steel hops. The ability of the cylinder to increase in diameter is resisted, however at the base where restraints occur. If out ward movement is prevented by a fixed joint the ring tension will be zero and vertical bending movement and sheared force will occur. Out of three types of base conditions i.e. free sliding, pined and fixed base, fixed base is the most effective due to the above reasons i.e. the ring tension will be zero and only Page 124 Assosa Water Supply Project vertical bending moment and shear force will occur. Therefore, due to its effectiveness, fixed base type is selected for the design of the circular reservoir 8.9.2 Design of 800m3 circular reservoir Type: Fixed base and free ends At the top of the will, shear force and bending moments are zero, and at the base of the wall, slope and deflection is zero. F W * H Figure 8.3 fixed base and free end reservoir Capacity of reservoir = 800m3 Height of reservoir = 4m Assumed free board = 0.2m Total height of reservoir = 4m+0.2m =4.2m Diameter of reservoir = D= 4V = *H 4 * 800 =16m 3.1416 * 4 Assume top thickness of wall =200mm Assume bottom thickness of wall=250mm The average thickness of wall tavg= 200 250 =-225mm 2 Page 125 Assosa Water Supply Project 8.9.2.3 Design of reservoir wall Internal force acting on the rank wall For determining internal forces of the tank wall of fixed base and free top tank ,coefficients are available in standard tables for a given The value of h2 d .t H2 =4.4444 D * t avg Then the corresponding value of moment and hoop tension coefficients is calculated as follows. Table 8.3 Coefficients for vertical moments in circular reservoirs 0.1H 0.2H 0.3H 0.4H 0.5H 0.6H 0.7H 0.8H 0.9H 1H 4 0.0003 0.0015 0.0028 0.0047 0.0.0066 0.0077 0.0069 0.0023 -0.0080 -0.0268 4.444 0.000212 0.001192 0.002272 0.00390 0.00572 0.003908 0.00646 0.002852 -0.007032 -0.02477 0.0046 0.0059 0.0059 0.0028 -0.0058 -0.022 H2 D * t avg 8 5 0.0001 0.0008 0.0016 0.0029 Table 8.4 Coefficient for hoop tension H 2 0H D * t avg 4 0.067 0.1H 0.2H 0.3H 0.4H 0.5H 0.6H 0.7H 0.8H 0.9H 0.16 0.256 0.339 0.403 0.429 0.409 0.334 0.210 0.073 0.2511 0.3421 0.4171 0.4503 0.409 0.3624 0.2318 0.0814 0.245 0.346 0.428 0.477 0.409 0.398 0.259 0.092 4 4.444 0.0484 0.15 2 5 0.025 0.13 7 Page 126 Assosa Water Supply Project Considering alternative exposure of wetting and drying the allowable stress based on BS: 5337 (elastic design method) For strength design fs, allow= 100N/mm2 (direct tension) fc, allow=11N/mm2 (due to bending) n=15 For no crack design fct, allow=2.02N/mm2 (due to bending) fct, allow=1.444N/mm2 (due to direct tension) 8.9.2.4 Detail Reinforcement a) Vertical section of the tank wall: -It is treated as tension member with cracked section i.e. only reinforcement resists the maximum hoop tension. The maximum hoop tension occurs at 0.5H with a coefficient 0.4503. I. horizontal reinforcement For the analysis purpose let divided wall into two pars Case1: For the top half of the wall, from 0.0H to 0.5H From the table above the minimum coefficients is 0.4503 Hence the hoop tension can be calculated as TH = max .coeff * w * H * r where r= D/2=16/2=8m =0.4503*9.81*4*8=141.3582KN per meter depth of wall Therefore area of hoop tension steel required assuming concrete section is cracked TH 141.3582 *10 3 As 1413.582mm2 100 fs , allow As= 1413.582mm2 Asmin= ok 0.3 * b * t 0.3 *1000 * 225 =675mm2… 100 100 Spacing of 14 ring bars required s b * as 1000 *153.86 108.844mm2 Smax=300mmor t=225mm As 1413.582 Page 127 Assosa Water Supply Project Provided: 14 ring bars at 70mm c/c in one layer placed on water face of for upper half wall Check thickness of wall for no cracks Thickness of wall is determined using requirement of resistance to crack; therefore thickness of wall is determined by limiting tensile stress in the concrete to allowable stress value as f ct TH 141.3582 *10 3 0.5775 N / mm2 f ct ,allow 1.44 N / mm2 Ac (n 1) * As 1000 * 225 (15 1) *1413.582 It is ok. Therefore, thickness is adequate for no concrete crack Case 2: For hoop reinforcement applied on bottom half of the wall, hoop tension developed at depth of (0.6H=2.4m) from top may be used as given below TH max .coeiff * w * H * r 0.409 * 9.81* 4 * 8 128.3933KN / m Area of reinforcement required the hoop for unit strip of wall As TH 128.3933 *10 3 1283.933mm2 As min 675mm2 100 fs , allow Check thinness of wall for no crack f ct TH 128.39333 *10 3 0.5284 N / mm2 f c ,allow 1.44 N / mm2 Ac (n 1) * As 1000 * 225 (15 1) *1283.933 It is ok. Therefore trial thickness is adequate for crack Spacing of ring bar using 14 S as * b S max 300mm or t=225mm As S 153.86 *1000 119.835mm 1283.933 Therefore, provide 14 ring bars @ 120mm c/c in one layer placed on water face for bottom half of wall. Page 128 Assosa Water Supply Project b) Horizontal section of the tank wall: -The internal forces in this section are (+ve) and (-ve) moments with maximum coefficients of 0.006908 and -0.02477 respectively i. Vertical reinforcement The maximum positive and the maximum negative moment is calculated as follows M max max .coeiff * w * H 3 (+ve) max.coeff=0.006908 @0.8H (-ve) max coeff=-0.02477@1H Therefore, (+ve) moment =0.006908*9.81*43=4.3371KN-m per meter width (-ve) moment =-0.02477*9.81*43=-6.4040KN-m per meter width Take absolute value of the result, the maximum moment is therefore M max 6.404 =6.404KN-m per meter width Check thickness of wall for flexure fs,allow=130N/mm2 fc,allow=11N/mm2 Design constant of balanced section are: r f s ,allow f c ,allow jb 1 kb 130 11.82 11 15 n 0.539 n r 15 11.82 kb 0.8136 3 Rb 0.5 * f c,allow * kb * jb 0.5 *11* 0.539 * 0.8136 2.5028N / mm2 Then the effective depth of section (dreq) is given by d req M max Rb * 6 6.4040 *10 2.5025 *1000 50.5638mm Thickness of wall taking 14 bars and 40mm cover Page 129 Assosa Water Supply Project t t req d req cov er / 2 50.5638mm 40mm 14mm / 2 97.5638mm t assu 225mm it is ok . Then t(req) will be t req t assu 40mm 14mm / 2 178mm Vertical reinforcement to be placed on water face is obtained for maximum negative moment Then area of reinforcement (ve) As M max 6.4040 *10 3 340.1551mm2 As min 675mm2 f s ,allow * jb * d req 130 * 0.8136 *178 Hence take As=Asmin=675mm2 t=250 d=178 b=100 Figure 8.4 Transformed section or equivalent section Page 130 Assosa Water Supply Project A *Y A Taking a unit width of reservoir and 250mm bottom thickness of the centriods of section is x i i i 1000 * 250 *125 15 * 675 *178 127.063mm 1000 * 250 15 * 675 Moments of area of equivalent concrete sections I ce b * x 3 b * ( D x) n * As * (d x) 2 3 3 I ce 1000 *127 3 1000 * (225 127) 3 15 * 675 * (178 127) 2 3 3 =1022860124mm4=1022.860*106mm4 f ct M max* ( D x) 6.404 *10 6 * (250 127) 0.77008 N / mm2 f ct , allow 2.02 N / mm2 Ice 1022.860124 *10 6 Therefore the thickness is adequate for no crack Spacing of 14 bars S as * b 153.86 *1000 228.056mm Smax=300mm or t=225mm As 675 Therefore provide: 14 bars at 225mm c/c vertically in the inner face. Vertically reinforcement on outer (+ve)Mmax=4.337KN-m per meter width Using t=225mm, 14 bars D= 225-14/2-40=178mm Hence (+ve)As= (ve) M max 4.337 *10 6 230.369mm2 As min 675mm2 f s ,allow * jb * d 130 * 0.8136 *178 Therefore As=675mm2 should be taken Spacing of 14 bars S as * b 153.86 *1000 228mm Smax=300m or t=225mm As 4 * 675 Therefore spacing S= 225mm should be taken. Provide 14 bars at 225mm c/c in the outer face Page 131 Assosa Water Supply Project 8.10 Design of roof slab Cover slab of service tank (reservoir) is treated as roof slab, which is simply supported by the circular wall. Consider cover slab as freely supported at edges and load uniformly Using strength limit design state For C-300MPa, f cd For S-300MPa f yd 0.67 f cu fy m 0.67 * 30 13.4MPa 1.5 300 260.87 MPa 1.15 Where w 1.5 fcu=300MPa fy=300MPa For S-300MPa maximum design constant for single reinforcement according to ACI max 0.437, max 0.34, max 0.75 b Dead load (own weight) = t* c , where t=thickness of slab=200mm =0.2*25=5 Kn/m2 Live load (LL) =0.5 KN/m2 (based on EBCS; 1995) Therefore the design load on the slab qd= 20 =1.3DL+1.6LL=1.3*5+1.6*0.5=7.3 KN/m2 Page 132 Assosa Water Supply Project qd= 7.3KN/m2 D=16m Figure 8.4 load on roof slab Design load on the base slab 1 Design moment at the center of slab 3 * Wd * x 2 3 * 7.3 * 8.15 2 M r M 90.916 KN .M 16 16 2 At the edge of the slab M r 0, M wd 2 7.3 * 8.15 2 x 60.611KN M 8 8 Check thickness for flexure b 0.0028 0.0028 0.5828 260.87 f yd 0.0035 0.0035 2 *10 3 Es Balanced mechanical reinforcement ratio max 0.75 * b 0.75 * 0.5828 0.437 Then effective depth of section (dreq) is given by d req M max 90.916 *10 6 140.952mm f cd * max * b 13.4 * 0.3145 *1000 Using 14 bars and cover of 40 mm Treq d req cov er / 2 =140.952+40+14/2=187.952mm Treq 187.952mm t assum 225mm And d t assum 40 / 2 =(200-40-14/2)mm=153m Page 133 Assosa Water Supply Project Reinforcement a) At the center of slab M r M 90.916kn m M 90.916 *10 6 0.290 f cd * b * d 2 13.4 *100 *1532 1 (1 2 ) 1 (1 2 * 0.290) 0.352 Then As * f cd * b * d f yd 0.352 *13.4 *1000 *153 2766.4mm2 As min 293.25mm2 260.87 Spacing using 14 bars S a s * b 153.938 *1000 55.646 S max 300mmor400mm As 2766.4mm 2 Therefore, provide 14 bars at 55mmc/c in the form of mesh at the center of slab b) At the edge of the slab M M r 60.611KN M M 60.611 *10 6 0.193 f cd * b * d 2 13.4 *1000 *1532 1 (1 2 ) 1 (1 2 * 0.193) 0.216 Then Therefore As * f cd * b * d f yd 0.216 *13.4 *1000 *153 0.5 * b * d 1692.563mm2 As min 225mm2 f yk 260.87 Spacing of bars using 14 bars S a s * b 153.938 *1000 90.682 As 1697.563mm 2 Page 134 Assosa Water Supply Project Therefore provide 14 bars at 90mm c/c in the form of ring at the edge of slab just above mesh reinforcement. Check thickness for shear vmax 0.5 * wd * x 0.5 * 7.3 * 8.15 29.748KN Shear capacity of the slab, Vc vc 0.4 * f ctd * (1 50 ) * b * d f ctd 0.35 * f ctk 1.5 0.35 * 30 1.278 N / mm2 1.5 As 1697.563 0.011 b * d 1000 *153 /2 0.011 0.005 2 vc 0.4 *1.278 * (1 50 * 0.0053) *1000 *153 97.767 KN Vmax 29.748kn Therefore thickness is adequate for shear. 8.11 Design of circular base –slab Section of base slab design considering simply supported at edge by ring beam and monolithic with the wall of the tank supported uniform load due to own weight, roof slab, and weight of water when the tank is full of water i.e qd =wt. of base slab + wt. of water +wt. of roof slab Considering exposure condition for base slab continuous liquid contact thus the allowable stress used for design are fs,allow=130N/mm2, fc,allow=11N/mm2, and n=15 Design constant of balanced section for flexural member Page 135 Assosa Water Supply Project r f s ,allow f c ,allow jb 1 130 11.82 11 kb n 15 0.539 n r 15 11.82 kb 0.8136 3 Rb 0.5 * f c,allow * kb * jb 0.5 *11* 0.539 * 0.8136 2.5028N / mm2 Shear at the base of wall = direct tension developed in the base slab H2 Thus, the coefficients of 4.444 from table is 0.12999 D *t Therefore direct tension developed in the base of slab is calculated as follow TH 0.1299 * W * H 2 0.1299 * 9.81* 4 2 20.3885KN Per meter width of the slab Section of base slab monolithic with the wall of the tank is designed for combined action of direct tension caused by water pressure on the wall. Maximum moment of slab caused by uniform load on the base slab and restraints moments of the wall caused by water pressure Consider thickness of wall t= 400mm Effective depth of slab considering 16 bar and 40mm cover D=t- cover- / 2 =400-40-8=352mm Wt. of base slab =0.352m*25KN/m3=8.8KM/m2 Wt. of roof slab= Wt. of water =7.3KN/m2 =4m*9.81KN/m3=39.24KN/m2 Total load =qd=8.8+7.3+39.34=55.34KN/m2 For simply supported circular slab (with radius =4m) the maximum radial and circumferential moments are obtained by Mr M 3 * q d * a 2 3 * 55.34 * 4 2 166.020 KN m at the center of the slab 16 16 Msupport= (-ve) Mbase,wall=6.4040KN-m …. Restraint moment at the base of wall Reinforcement of base of slab Page 136 Assosa Water Supply Project Minimum area of reinforcement for base of slab of unit width (BS: 5337) Asmim= 0.3 * b * t 0.3 *1000 * 400 1200mm2 100 100 At the center of the slab design for combined action of TR= 20.3855KN and M=166.02KN-m Therefore the required reinforcement is determined by (+ve)As= Spacing of 20 bar S T 166.02 *10 6 20.3885 *10 3 M R 4616.1014mm2 130 f s * j * d f s 130 * 0.8136 * 352 b * as 1000 * 314.16 68.057mm Smax=300mm As 4616.1014 Provided: 20 bars at 65 mm c/c in the form of mesh placed at the bottom of slab At the support: Design for combined action of T=20.3885KN and M=-6.4040KN-m Therefore required reinforcement is determined by (-ve)As= M 6.404 *10 6 20.3885 *10 3 328.845mm2 Asmin =1200mm2 f s * j * d 130 * 0.8136 * 352 130 There fore take As=1200mm2 Therefore extra bars are required in addition to vertical bars of wall. Check trail thickness of slab for no crack due negative moment & direct tension ( A * Y ) 400 *1000 * 200 15 *1200 * 352 206.5455mm 400 *1000 15 *1200 A Location of neutral axis of equivalent un-crack concrete section of wall Y Moments of inertial and area of equivalent un-cracked concrete section of wall b* y b * ( D y) 3 n * Ast * (d y) 2 3 3 3 I ce 1000 * 206.54453 (400 206.5445) 3 I ce 1000 * 15 *1200 * (352 206.5445) 2 3 3 Page 137 Assosa Water Supply Project I ce 5731296970mm4 Then tensile stress due to moment and direct tension f ctb M * ( D Y ) 6.404 *10 6 * (400 206.5445) 0.2162 N / mm 2 5731296970 I ce f ct TR 20.3885 *10 3 0.05097 Ace 400 *1000 Then check tensile stress interaction equation for no concrete crack f ctb f ctb,allow f ct f ct ,allow 0.2162 0.05097 0.14245 1….. Ok 2.02 1.44 Therefore trial thickness of wall is adequate for no concrete crack! The design of 500m3 is done in a similar fashion of design of 800m3. For the calculation of bill of quantities we considered proportional amount as their volume. CHAPTER NINE Distribution system 9.1 General After the water has reached to the service reservoir, it becomes necessary to distribute it to a number of houses, industries and public places by means of network of distribution system. The distribution systems, the distribution systems consist of pipes of various sizes, valves, meters, distribution reservoirs, pumps, hydrants etc. the pipe lines carry water to each and every street and road. Valves control the flow of water through the pipes. Meters are provided to measure the quantity of water consumed by the individual Page 138 Assosa Water Supply Project as well as by the town. Hydrants are provided to connect the water to the fire fighting equipment during fine accident. Service connection is done to connect the individual building with the water line passing through the streets. Pumps are provided to pump the water to the elevated service reservoir or directly in the water mains to obtain the required pressure in the pipe lines. The layout of the roads and the elevation of the town also considered to select the layout of the distribution systems respectively the following are the requirement of a good distribution system It should convey the reacted water to the consumers with the same degree of purity. The water should reach to every consumer with the required pressure head. Sufficient quantity of reacted water should reach for the domestic and industrial use. The distribution system should be economical and easy to maintain and operate. It should be able to transport sufficient quantity of water during emergency shuch as fire fighting. During repair work, it should not cause obstruction to the traffic. It should be safe against any future pollution. The pipe lines as much as possible should not be laind below the sewer lines. The quality of the pipe should be good and it should not burst. It should be water-tightt and the water losses dur to leakage should be bare minimum as much as possible. For efficient distribution it is required that water should each to every consumers with required rate of flow. There fore, some pressure in pipe lines is necessary which should force the water to reach at every place. 9.2 Methods of distribution For efficient distribution it is required that water should reach to every consumer with required rate of flow. Therefore, some pressure in pipelines is necessary to force the water to reach at every node. This can be done by one of the following methods, as local conditions or other considerations may dictate. I gravity distribution system This is possible when the source of the supply is at some elevation above the city so that sufficient pressure can be maintained in the mains for domestic and fire service. This is the most reliable method if the conduit leading from source to city is adequate in size and well safe guarded against accidental breaks. Page 139 Assosa Water Supply Project II pumping system with out storage In this system water is directly pumped in mains. Since the pumps have to work at different rates in a day, the maintenance const increases. It is preferred to have number of pumps and only the required numbers may work at various times to meet the varying demand, in place of proving pump of variable speed. High lift pumps are required and their operations are continuously watched. If the power fails, the whole supply of town will be stopped. Therefore, it is better to have a diesel pumps in addition to the electric pumps as standby. During fires, the water dan be pumped in the required quantity by the stand by units also. III combined gravity and pumping system (dual system) In this system the pump is connected to the mains as well as to an elevated reservoir. At the beginning when the demand is small the water is stored in the elevated reservoir, when the demand increases the flow in the distribution system comes from both the pumping station as well as elevated reservoir. In this system water comes from two sources from reservoir and for pumping station, which is called dual system this system is more reliable and economical because it requires uniform rate of pumping but meets low as well as maximum demand, the water stored in elevated reservoir meets the requirements of demand during breakdown of pumps and for fire fighting. Following are the main advantages of this system:i) The balance reserve in the storage reservoir will be utilized during fire. In case of fire demand is more and if required the water supply of few localities may be closed. ii) This system is the overall best system. It is economical efficient and reliable. iii) This system has the advantages that during power failure, the balance water stored in the reservoir will be supplied to the town. iv) The pumps have to work at constant speed with out any variation in their speed. In Assosa town the water is distributed to the community by the gravity system because the service reservoir is located at high elevation of the town. So the water reaches to every consumer in sufficient quantity. 9.3 layout of distribution system Depending upon their layout direction of supply, they are classified as follows:i. Dead end or three system:- it is suitable for irregular developed towns or cities. In this system one man starts from service reservoir along the main road. Sub mains are connected to the main in both the direction along other roads, which meet the roads Page 140 Assosa Water Supply Project carrying sub-mains, branches and minor distributors are laid and are connected to sub mains. From these branches service connections are made to individual houses. the advantage of these system are cheap in initial cost and easy determination of pipe diameter, value size etc. but the main disadvantage of f this system is formation of dead ends and if pipe breaks down or is closed for repair, the whole locality beyond the point grows without water. Since the water is reaching at each point from one side only it can not meet the fire demand. ii. Grid-iror system: - this system is most convenient for towns having rectangular layout of roads. Actually, this system is an improvement over dead end system. All the dead ends ae interconnected with each other and water circulated freely through out the system. In this system mainline is laid along the main road. Sub-mains are taken in both directions along other minor roads and streets. From these sub-mains branches are taken out and are interconnected to each other and water circulates freely through out the system. This system removes all the disadvantages of dead end system. Following are main advantages of this system i.As the water is supplied from both the sides to every point, very small area will be affected during repair. ii.Since the water reaches every point form more than one route, the friction losses and the sizes of the pipes are reduced. iii.All the dad ends are completely eliminated, therefore the water remains in continuous flow and there is no stagnation and chance of pollution is reduced to minimum. iv.In case of fire, more quantity of water can be diverted towards the affected area, by closing the valves of near by localities. As this system has many advantages it also has some disadvantages:i.More number of valves and longer length of pipe is required in this system, there by increasing the overall cost. ii.If one section is to be repaired more number of valves are required to be closed. iii.The design is difficult and costlier. Considering the above advantage and layout of roads of Assosa town this method is adopted. III circular or ring system:- this system is adopted only in well planned locality of cities. In this system each locality is divided into square and the water main are laid around all the four sides of the square. All the sub-mains and branches ae taken off from the boundary mains and are are inter connected. This system is the best of the other system but it requires many valves and more pipe length. The ring system is most suitable for towns and cities having well planned road. Page 141 Assosa Water Supply Project iv.Radial system:- actually this is the reverse of ring system and water flows towards outer periphery from one point. The entire district is divided in to various zones and one reservoir is placed for each zone which is placed at the center of the zone. The water lines are laid radically from it. 9.4 design procedure of the distribution system First of all the layouts of the distribution pipes are prepared and the position of valves, fire hydrants etc, are also marked on it. The reduced levels of the town at various points are also marked on it. The reduced levels of the town at various point are also marked on the plan. Now the total population to be served at each node is also marked on the plan. After this the minimum water pressure required at the tail end and near the highest building of the city are also determined and noted on the plan. After completing the above work, the main work is to determine the sizes of distribution popes, which would be capable to carry the required quantity of water at the desired pressure. 9.5 selections of pipe materials The types of pipe used for distributing water under pressure includes: ductile iron, cast iron, asbestos, cement concrete, steel and PVC. Small diameter pipes for house connection are usually plastic. For use in transmission and distribution system pipe materials must have the following characteristics. Adequate tensile and bending strength to with stand external loads that result from trench back fill and earth movement caused by freezing, thawing or unstable soil condition Ability to resist impact loads encountered in transportation, handling and installation. Smooth, non corrosive interior surface for minimum resistance to water flow. Pipe materials that can be provided with tight joints and easy to tap for making connections. Among different types of pipes, existing on the market PVC pipes are selected for the distribution system. This is because PVC pipes are light in weight, cheap, easy to join and install durable, good electric insulators and free from corrosion. Additionally, DCI pipes are extended from borehole to service reservoir due to its strength and resistance to corrosion. 9.6 design of pipelines Till date no direct methods are available for the design of distribution pipes. While doing the design first of all the diameters of pipes are assumed, the terminal pressure heads which could be made available at the end of each pipe section after allowing for the loss of pressure head in the pipe section when full peak flow discharge is flowing are then determined. The determination of the friction loss in each pipe section is done. The total Page 142 Assosa Water Supply Project discharge flowing through main pipe is to be determined in advance. While design of pipes the following points should be kept in mind: The main lines should be designed to carry and times the average demand of the city. The water demand at various pints in the city should be noted. The velocity in pipelines should be less than 2m/sec. In the distribution system the minimum size of distribution pipe is as 50mm and service pipe of 20mm is used for giving house connection. 9.7 pressure in distribution When the water enters in the distribution main the water head continuously is lost due to friction in pipes, at entrance of reduces, due to valves, bends, meters etc till it reaches consumers tap. The net available head at the consumers tap is the head at the entrance of the water minus all the losses in the way. The effective head available at the service connection to the building is very important because, the height up to which the water can rise in the building will depend on this available head only. The greater the geed the more will be the height up to which it will rise. If adequate head is not available at the connection to the building, the water will not reach the upper storey, to overcome this difficulty the required effective head is maintained lithe street pipe lines. The water should reach for each and every consumer. Therefore it should reach on the upper most storeys. The pressure which is required to be maintained in the distribution system depends up on the following factors: The height of the highest building up to which water should reach without boosting. The distance of the locality form the distribution reservoir Supply is to be metered or not, higher pressure will be required to compensate for the high loss of head in meters. How much pressure will be required for fie hydrants. The funds available for the project work. 9.8 nodal demand computation The average consumption in the odes can be determined in two ways 1. From the geographical map, by dividing the system in to a number of areas assumed to be supplied from the corresponding node. 2. By calculating the average number of consumers per meter of pipe in each loop. Even dispersion of house connections through the system is assumed in both cases. Location of the source connections to the system will depend on the route of secondary mains, more over; Page 143 Assosa Water Supply Project They should be concentrated towards the areas of higher demand The pipe route should be as short as possible. The pipe should be easily accessible; passing underneath the building should be avoided. 9.9 computer analysis of distribution system The distribution network is simulated using Epanet 2.0. The simulation was carried out for extended period analysis by taking in to consideration the hourly demand variation pattern on maximum and average day. The analysis began by feeding assumed diameter in the computer; and the pressure, velocity and headless are checked for peak and average flow. As the result of Epanet 2.0 analysis is shown in the appendix. . 9.10 appurtenances The different device required for controlling the flow of water for preventing leakage and other similar purposes in water distribution network is called appurtenances. In this network the following appurtenance are used:1. Valves: - in distribution network it is used to control flow of water, regulates pressure, releases and admits air, prevents flow of water in opposite direction and so on. Valves such as check valves, pressure valves, gate valves, air relief valves and drain valves are to be provided where they are needed. 2. Pipe fittings:- the various pipe fittings such as beds, crosses, tees, elbows, caps, ripples, plugs, flanges are to be provided during the laying of the distribution. 3. Manholes: - for inspection and maintenance purpose manholes are to be provided at every junction of pipes and at places where valves are to be installed and when t here is a change in direction of pipes. Page 144