NNPC GAS INFRASTRUCTURE COMPANY LIMITED ENGINEERING, PROCUREMENT & CONSTRUCTION OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP - LOT 3) QUANTITATIVE RISK ASSESSMENT REPORT DOCUMENT NO.: NGIC-EEPSP_YNL-TSF-RPT-007 R01 13/06/2023 Issued for Review J.L. A.A. REV. DATE DESCRIPTION BY CHECKED Project Code Client Contractor Discipline Doc. Type NGIC EEPSP YNL TSF RPT Doc. Control No. A.U. NGIC APPROVED SequenceRev. Number 007 This document contains information, which is for company use only. This information is to be held in confidence. Disclosure, reproduction, or other use of this document is prohibited without the prior written consent of CLIENT R01 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 REVISION HISTORY Revision Date Description R01 11/06/2023 Issued for Review Quantitative Risk Assessment Report Remarks Page 2 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 EXECUTIVE SUMMARY This report presents the Quantitative Risk Assessment (QRA) conducted for EEPSP - LOT 3 project. It provides input to the Overall Design Safety Assessment for the EEPSP - LOT 3 project. The QRA quantifies the risk associated with Major Accident Event (MAEs) that have been assessed as having the potential to result in fatality. In quantifying the risk, the analysis has drawn upon the results and conclusions given in the various support studies, namely: • Process Hazard Analysis (PHA). • Fire and Explosion Risk Assessment (FERA). The overall objective of this Quantitative Risk Assessment is to provide assurance that EEPSP - LOT 3 project is designed with relevant engineering safeguards and the residual risk levels from the pipeline to the facility will be within acceptable guidelines. These assessments provide a numerical estimate of the residual safety risks during the operational phase associated with hydrocarbon gas releases from the facility in terms of: • Individual risk. • Societal risk. The study approach adopted internationally accepted risk analysis approach, covering the following methodology: • Step 1: Identification of major accident event • Step 2: Modelling of potential consequences including fire and explosion • Step 3: Calculation of frequency of hazardous event outcomes • Step 4: Calculation of risk levels • Step 5: Mitigation or reduction of risk study results with acceptable risk guidelines Potential Hazard Incidents identified covered the pipeline through to the facility. These include releases from various flammable gas streams, followed by jet fire, flash fire, and/or flammable gas dispersion. Comparing the Individual risk of major areas of concerns within the facility, it was observed that the risk was within the acceptable region while no societal risk was observed seeing that the risk contour did not reach any nearby community. Thus, posing no societal threat to the nearby community and thereby requiring no additional risk reduction measure as inherent risk are adjudge to be ALARP. Table of Contents Quantitative Risk Assessment Report Page 3 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 EXECUTIVE SUMMARY .................................................................................................................... 3 TABLE OF FIGURES ......................................................................................................................... 6 LIST OF TABLES............................................................................................................................... 7 ABBREVIATIONS .............................................................................................................................. 8 1.0 INTRODUCTION...................................................................................................................... 9 1.1 PROJECT DESCRIPTION ................................................................................................... 9 1.2 PROJECT OBJECTIVE ........................................................................................................ 9 1.3 PURPOSE ............................................................................................................................ 9 1.4 SCOPE ................................................................................................................................. 9 1.5 STUDY LIMITATION .......................................................................................................... 10 1.6 REFERENCES ................................................................................................................... 10 2.0 CODES AND STANDARDS .................................................................................................. 11 2.1 GENERAL .......................................................................................................................... 11 2.2 NATIONAL REGULATIONS ............................................................................................... 11 2.3 INTERNATIONAL CODES AND STANDARDS .................................................................. 11 3.0 EEPSP LOT 3 PROCESS DESCRIPTION............................................................................. 13 3.1 GENERAL .......................................................................................................................... 13 3.2 INLET FACILITY PIPING .................................................................................................... 13 4.0 QRA METHODOLOGY .......................................................................................................... 18 4.1 DATA SOURCE ASSUMPTION ......................................................................................... 19 4.2 MANNING DATA ................................................................................................................ 20 4.3 METEROLOGICAL DATA .................................................................................................. 20 4.4 FEED SOURCE AND INVENTORY ANALYSIS ................................................................. 21 5.0 HAZARD IDENTIFICATION .................................................................................................. 22 5.1 HOLE SIZE......................................................................................................................... 25 5.2 FAILURE CASE SELECTION............................................................................................. 26 6.0 FAILURE FREQUENCY ANALYSIS ..................................................................................... 27 6.1 PART COUNT ANALYSIS .................................................................................................. 27 6.2 EVENT TREE FREQUENCY .............................................................................................. 29 6.2.1 Ignition and Early Ignition ............................................................................................ 29 6.2.2 Explosion ..................................................................................................................... 29 6.2.3 Outcome Consequences ............................................................................................. 30 6.2.4 Immediate Fires ........................................................................................................... 30 6.2.5 Delayed Fires .............................................................................................................. 30 7.0 CONSEQUENCE ANALYSIS ................................................................................................ 31 7.1 SOURCE TERM MODELLING ........................................................................................... 31 7.2 PHYSICAL EFFECTS MODELLING ................................................................................... 32 Quantitative Risk Assessment Report Page 4 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 7.2.1 Jet Fires ...................................................................................................................... 32 7.2.2 Pool Fires .................................................................................................................... 32 7.2.3 Flash Fires................................................................................................................... 32 7.2.4 Fireballs ....................................................................................................................... 33 7.2.5 Gas Explosions ........................................................................................................... 33 7.3 8.0 SUMMARY OF CONSEQUENCE AND EVENT FREQUENCY RESULTS ......................... 33 RISK ACCEPTANCE CRITERIA ........................................................................................... 34 8.1 RISK ASSESSMENT FRAMEWORK ................................................................................. 34 8.2 INDIVIDUAL RISK CRITERIA............................................................................................. 35 8.3 SOCIETAL RISK CRITERIA ............................................................................................... 36 9.0 RISK ASSESSMENT AND RESULTS ................................................................................... 37 9.1 GENERAL .......................................................................................................................... 37 9.2 INDIVIDUAL RISK PER ANNUM (IRPA) ............................................................................ 37 9.3 POTENTIAL LOSS OF LIFE (PLL) ..................................................................................... 38 10.0 CONCLUSIONS AND RECOMMENDATION ........................................................................ 40 10.1 CONCLUSION.................................................................................................................... 40 10.2 RECOMMENDATION ......................................................................................................... 40 APPENDIX A: ASSUMPTION SHEET ..................................................................................... 41 APPENDIX B: PLOT PLAN ........................................................................................................ 60 APPENDIX C: ISOLATABLE SECTIONS .................................................................................. 62 APPENDIX D: MARKED DRAWINGS OF ISOLATABLE SECTIONS..................................... 68 APPENDIX E: EVENT TREE ................................................................................................... 88 APPENDIX F: CONSEQUENCE MODELLING RESULTS ...................................................... 95 Quantitative Risk Assessment Report Page 5 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Table of Figures Figure 1: Quantitative Risk Assessment Methodology ...................................................................... 19 Figure 2: Part Count and Leak distribution ........................................................................................ 28 Figure 3: Consequence modelling for an Event which involves Ignition ............................................ 31 Figure 4: ALARP Framework for Risk Criteria ................................................................................... 35 Figure 5: EEPSP Wind rose .............................................................................................................. 41 Figure 6: Part Count ......................................................................................................................... 49 Figure 7: Event Tree ......................................................................................................................... 52 Quantitative Risk Assessment Report Page 6 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 List of Tables Table 1: Reference Documents ........................................................................................................ 10 Table 2: List of NUPRC (Formerly DPR Regulations) ....................................................................... 11 Table 3: List of International Codes and Standards........................................................................... 11 Table 4: List of International Codes and Standards........................................................................... 20 Table 5: Status of HAZID Recommendations.................................................................................... 22 Table 6: HAZID Recommendations Summary .................................................................................. 23 Table 7: Representative Leak Sizes for QRA .................................................................................... 25 Table 8: Individual Risk Per Annum (IRPA) for EEPSP facility .......................................................... 38 Table 9: PPL for EEPSP facility ........................................................................................................ 38 Table 10: Wind rose Data – True North ............................................................................................ 42 Table 11: Feed gas Composition ...................................................................................................... 43 Table 12: Consequence Modelling Assumptions .............................................................................. 45 Table 13: Manning Distribution for QRA............................................................................................ 59 Quantitative Risk Assessment Report Page 7 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 ABBREVIATIONS ABBREVIATION MEANING API American Petroleum Institute ALARP As Low As Reasonably Practicable ASME American Society Of Mechanical Engineers BS British Standard CA Condensate Accumulator CNL-EGP Chevron Escravos Gas Plant EEPSP Escravos Environs Power Supply Project ESD Emergency Shutdown EPC Engineering Procurement Construction ESD Emergency Shutdown FB Full Bore FERA Fire and Explosion Risk Assessment FC Failure Case HAZID Hazard Identification HC Hydrocarbon LFL Lower Flammability Limit LoPC Loss of Primary Containment MAH Major Accident Hazard NNPC Nigerian National Petroleum Company Limited NPSC Nigerian Pipelines and Storage Company PHAST Process Hazard Analysis Software Tool RoW Right of Way QRA Quantitative Risk Assessment TSC Technical Safety Control UFL Upper Flammability Limit WBH Water Bath Heater Quantitative Risk Assessment Report Page 8 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) 1.0 INTRODUCTION 1.1 PROJECT DESCRIPTION Revision No: R01 The Nigerian National Petroleum Company Limited (NNPC) through its Subsidiary NNPC Gas Infrastructure Company Limited (NGIC) Limited intends to construct 6" x 8km and 4” x 2km gas pipelines that will transport lean gas from Chevron Escravos Gas Plant (CNL-EGP) and NPSC Utility pipelines respectively to EEPSP Plant within PPMC tank farm at Escravos. To this end, Yonkys Ya-Star Nigeria Limited has been contracted to carry out the EPC works for gas supply to the power generation Plant at NPSC tank farm. 1.2 PROJECT OBJECTIVE The primary objective of the project is to supply gas through a tie-in at the 16” pipeline using the existing valve connection, and constructing a 6” spur line from the tie-in point. The early gas phase shall be constructed through a 4” pipe connection on the 8” utility pipeline at NPSC Tank farm via hot tapping. The project scope shall provide a facility for filtering/separating any liquid and debris including to heat and reduce the gas pressure (PRMS) to 2- 4 bar, that will be further reduced by the regulator to be provided for the gas driven generator. 1.3 PURPOSE The main purpose of this QRA are as follows: • Estimating risk levels and assessing their significance. This helps decide whether or not the risks need to be reduced. • Determine the characteristics of potential fire, dispersion and explosion event along with its potential escalation with focus on major accident event. • Identifying the main contributors to the risk. This helps understanding of the nature of the hazards and suggests possible targets for risk reduction measures • Assess the potential consequences in terms of impact on people, critical operation systems vulnerable infrastructures including onsite asset and public facility. • Evaluate the effectiveness of the hazard mitigation measures and identify any risk reduction opportunities to verify the intended design to ensure that potential major accident event are As low as reasonably practicable (ALARP). 1.4 SCOPE This study has assessed the consequences and likelihood of hazardous releases from new process equipment associated with the EEPSP project in the bid to ensure that all potential major accident event has been reduced to As low as reasonably practicable (ALARP) level. Hence, the scope of this Quantitative Risk Assessment cover the following facilities: • 6” x 8km pipeline from CNL facility to EEPSP Lot 3 Facility • 4” x 2km pipeline from NPSC facility to EEPSP Lot 3 Facility Quantitative Risk Assessment Report Page 9 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) • 1.5 Revision No: R01 Process Equipment and associated piping within EEPSP Lot 3 Facility STUDY LIMITATION This QRA studies did not fully access the risk associated with the 6” x 8km and 4” x 2km pipeline R.O.W from CNL Facility and NPSC Facility due to non-availability of the Manning/Presence Philosophy along pipeline R.O.W. Thus, risk associated with 6” x 8km and 4” x 2km pipeline R.O.W from CNL Facility and NPSC Facility shall be on hold. 1.6 REFERENCES Table 1: Reference Documents S/N Document Number 1. NGIC-EEPSP_YNL-PMS-BOD-001 Basis of Design 2. NGIC-EEPSP_YNL-PRO-PHI-003 Emergency Shutdown and Depressuring Philosophy 3. NGIC-EEPSP_YNL-PRO-RPT-002 Heat & Mass Balance Report for 7.5 MMSCFD 4. NGIC-EEPSP_YNL-PRO-RPT-003 5. NGIC-EEPSP_YNL-PRO-PFD-001 6. NGIC-EEPSP_YNL-PRO-PFD-003 7. NGIC-EEPSP_YNL-PRO-PID-002 8. NGIC-EEPSP_YNL-PRO-PID-003 9. NGIC-EEPSP_YNL-PIP-DRW-001 10. NGIC-EEPSP_YNL-PIP-PLN-001 11. NGIC-EEPSP_YNL-PIP-DRW-002 Plant 3D Model 12. NGIC-EEPSP_YNL-TSF-RPT-008 Fire & Explosion Risk Assessment Report 13. NGIC-EEPSP_YNL-TSF-RPT-009 Emergency Escape & Rescue Assessment Report Quantitative Risk Assessment Report Title Heat & Mass Balance Report for 10 MMSCFD PFD for PRMS for 10MMSCFD PFD for PRMS for 7.5MMSCFD P&IDs for PRMS for 10MMSCFD P&IDs for PRMS for 7.5MMSCFD Piping Isometrics Overall Piping Plot Plan Page 10 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) 2.0 CODES AND STANDARDS 2.1 GENERAL Revision No: R01 All standards, codes and regulations to which this document is based, shall be the latest revision. There are prescribed legal requirements or regulations for regulatory approval of design of safeguards by NUPRC (Formerly DPR), as part of the overall compliance management for projects. This QRA shall form part of the overall project risk management process which is required to be submitted as part of the facility Safety (Case) Report. 2.2 NATIONAL REGULATIONS Table 2: List of NUPRC (Formerly DPR Regulations) Document No. Document Title DPR Guide 0032 - 2020 Guidelines for Compliance with the Technical Safety Control (TSC) Requirements for Facility Development Projects and Modifications, August 2020 DPR Guide 0027 - 2021 Guidelines and Procedures for the Design, Construction, Operation and Maintenance of Oil and Gas Pipeline Systems in Nigeria - 2021. Guidelines Concerning Implementation and Use of Risk Based Inspections DPR in the Nigerian Petroleum Industry, 2006 2.3 INTERNATIONAL CODES AND STANDARDS Table 3: List of International Codes and Standards Document No. Document Title CMPT A Guide to Quantitative Risk Assessment for Offshore Installations, Publication 99/100a, 1999. IOGP 434-1 Analyze Frequencies of Releases from Process Equipment, IOGP Report No. IOGP 434-1, September 2019. IOGP 434-6.1 Risk Assessment Data Directory: Ignition Probabilities; IOGP Report No. 4346.1, March 2010 IOGP 434-3 Study Frequencies of Releases from a Variety of Storage Types; IOGP Report No. 434-3 Quantitative Risk Assessment Report Page 11 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 Document No. Document Title IOGP 434-15 Risk Assessment Data Directory: Vulnerability of Plant / Structure; IOGP Report No 434-15 Design and Installation of Pressure-Relieving Systems in Refineries, Part I API STD-520 and II API ST521 Pressure-relieving and Depressuring Systems API RP-521 Guide for Pressure-Relieving and De-pressuring Systems ISO 17776-2002 Guidelines on tools and techniques for hazard identification and risk assessment, 2002 UK HSE HSL/2005/58 Review of Hazard Identification Techniques, 2005 NFPA 921 Guide for Fire and Explosion Investigation EI 19 Fire Precautions at Petroleum Refineries and Bulk Storage Installations Quantitative Risk Assessment Report Page 12 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) 3.0 EEPSP LOT 3 PROCESS DESCRIPTION 3.1 GENERAL NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 The EEPSP Lot 3 Facility operation has been divided into two phase’s namely: Early gas and Permanent gas Phase. For the Early gas phase operation, the lean gas supplied to the PRMS is sourced from the 8” utility gas pipeline within NPSC facility. The pipeline operates at a pressure between 12 barg to 30 barg and temperature between 20 C ̊ to 30 C ̊ . While after Power plant commissioning, the gas supply shall be via a 6” pipeline originated from the 24” NGIC gas transmission pipeline via hot tap and from 16” pipeline through calve connection. 3.2 INLET FACILITY PIPING 3.2.1 Inlet Facility Piping for 7.5 MMSCFD The gas enters the facility with a maximum pressure of 30 barg and temperature of 30 C ̊ . The inlet Facility system consists of 4” pipeline from tie-in point at the existing 8” utility line within NPSC facility. The line is fitted with an Emergency shutdown valve (31-SDV-001A) which is controlled by a Pneumatic (gas) actuating system via a solenoid valve. Closing of shutdown valve (31-SDV-001A) shall initiated an ESD and OSD1 action. The line is also equipped with Pressure transmitter alarm high and low (31-PIA-001A) set at 32 barg and 5 barg respectively. The line is also equipped with a pressure high-high and low-low trip (31PZA- 002) set at 35 barg and 4 barg respectively which trigger OSD 1 action (Facility Shutdown). The inlet facility line is also furnished with a Temperature Alarm high and low (31-TIA-001A) set at 40 ̊C and 15 C ̊ respectively. In the event of fire, ESD is initiated and closes shutdown valve (31-SDV001A). 3.2.2 Inlet Facility Piping for 10 MMSCFD The gas enters the facility with a maximum pressure of 85 barg and temperature of 42 C ̊ . The inlet facility system consists of 6” pipeline from the Pig Launcher within CNL facility. The line is fitted with an emergency shutdown valve (31-SDV-001B) which is controlled by a pneumatic (gas) actuating system via a solenoid valve. Closing of shutdown valve (31-SDV-001B) is initiated by ESD and OSD1 action. The line is also equipped with Pressure transmitter alarm high and low (31-PIA-001B) set at 86 barg and 60 barg respectively. The line is also equipped with a pressure high-high and low-low trip (31PZA- 002B) set at 88 barg and 58 barg respectively which trigger OSD 1 action (Facility Shutdown). The inlet facility line is also furnished with a Temperature Alarm high and low (31-TIA-001B) set at Quantitative Risk Assessment Report Page 13 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 45 ̊C and 20 C ̊ respectively. In the event of fire, ESD is initiated and closes shutdown valve (31-SDV001B) 3.2.3 Gas Heating System For 7.5 MMSCFD And 10 MMSCFD The gas from the filter flows to the indirect water bath heater. For each of the PRMS facility, the heating system consists of two identical indirect water bath heaters, one in operation at any given time and one on standby. Each heater unit is made up of the following components • Stack • Gas/Heating section • Burner Management System • Fuel gas system • Fan for forced air • Water expansion tank for water refill • Pressure and temperature control system The gas enters the heaters at a temperature between 20 C ̊ to 30 C ̊ for 7.5 MMSCFD and between 26 ̊C to 42 C ̊ for the 10 MMSCFD PRMS and exits the heaters at a temperature of 41.50 C ̊ and 63.65 C ̊ for the 7.5 MMSCFD and 10 MMSCFD respectively. The gas outlet temperature from the heaters shall be set to compensate for the J-T effect (gas temperature drops during gas pressure reduction) and ensure acceptable gas temperature downstream the pressure reduction skid, which should be above the hydrocarbon dew point temperature of the gas. The indirect water bath heaters are equipped with temperature controller which keeps the temperature of the heaters between specific ranges to be advised by the vendor. Fuel gas supplied to gas heater burners shall be sourced from the fuel/instrument gas skid. The water bath heater is provided with a Burner Management System, PLC Function and Temperature controllers. The burner management system ensures safe start-up, operation and shutdown of the heaters. The burner heats bath water to achieve required gas outlet of 41.5 C ̊ 63.65 C ̊ for the respective PRMS. A temperature controller regulates the fuel gas and air ratio to the burner to increase and decrease the bath temperature so as to regulate the outlet gas temperature according to the design parameters. Pressure and temperature control sensors are provided at the inlet and outlet of each of the gas heater which triggers the necessary response at the predetermined set points. Temperature control valves (61-TCV-001 for 7.5 MMSCFD and 61-TCV-002 for 10 MMSCFD) is installed on bypass downstream of the water bath heater to ensure that the station outlet temperature meets export specifications (27 C ̊ ). The thermal control system (28-TICA-005) senses the outlet temperature of the gas located on the gas export line and signals to open the temperature control Quantitative Risk Assessment Report Page 14 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 valve (61-TCV-001 and 61-TCV-002) on the heater bypass, causing cold inlet gas to mix with the heated gas from the heater outlet, thereby regulating export gas the temperature. 3.2.4 Pressure Reduction System The pressure reduction section of the stations consists of two parallel trains mounted on a skid. Each has a maximum flow capacity of 7.5 MMSCFD and 10 MMSCFD. The pressure reduction skid operates with one (1) runs while the second train remains on standby. The primary function of the Pressure Reduction System is to reduce the incoming gas pressure to a constant outlet pressure that has been determined by the customer. Each run is equipped with dual pressure control valve 71-PCV-001A/71-PCV-002A, 71-PCV003A/71-PCV-004A for the 7.5 MMSCFD 71-PCV-001A/71-PCV-002A, 71-PCV-003B/71-PCV-004B for the 10 MMSCFD (one active and fail open mode, the second one monitor and fail close mode) to reduce the pressure from 12 - 30 barg for 7.5 MMSCFD and 68 – 85 barg for 10 MMSCFD to 2 – 4 barg. Pressure alarm sensors, pressure safeguarding sensors, pressure relief valves. In normal operation, the active valve will be controlling the gas pressure and the monitor valve will be set slightly above the active valve to monitor and be ready to take over control if the active valve fails. A failure of the active valve will drive the valve fully open hence the designation FO. Each of the valves shall be fitted with a pneumatic position actuator that uses gas for control. A Pressure Transducer shall be provider to convert electric signal from the Control room to pneumatic signal to drive the valve. Each run has isolation valves at the inlet and outlet while a Shutdown Valve (71-SDV-001A, 71SDV-002A for 7.5 MMSCFD and 71-SDV-001B, 71-SDV-002B for 10 MMSCFD) to isolate each run in an event of emergency or operational requirement. Pressure Sensor (71-PIA-005/007A for 7.5 MMSCFD and 71-PIA-005B/007B for 10MMSCFD with High and Low Alarm set point of 5.0 barg and 1.8 barg respectively, initiates high and low alarm for the operator action. In the event of no operator action on high and low pressure alarm, the Pressure Safeguarding trip (71PZA-006A/008A for 7.5 MMSCFD and 71-PZA-006B/008B) downstream the PCV’s shall initiate an OSD 1 to protect to protect the system from over pressure. Relief valves (PSV-001A/002A for 7.5 MMSCFD and PSV-001B/002B for 10 MMSCFD) are provided at each run to protect the system from over pressure due to control valve failure. Also, a means of discharging each run from its inventory shall be provided through manual blowdown valves Quantitative Risk Assessment Report Page 15 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) 3.2.5 Revision No: R01 Gas Metering System The purpose of the gas metering system is to meter the volume of gas consumed by the customer and it is measured in MMSCFD. This is achieved by installing Coriolis meter to capture flow communicating with a Flow Computer. The metering system has two (2) runs, where one shall be active and one on standby. Each train has isolation valves at each end. The gas from the pressure reduction skid enters to the metering skid at the pressure between 2 – 4 barg and temperature of 27 C ̊ . 3.2.6 Instrument Gas / Fuel Gas System The instrument gas system receives gas from four input sources from both 7.5 MMSCFD and 10 MMSCFD PRMS; the first two input sources are from the facility inlet line which is provided for black start and the second two input sources are from upstream the pressure reduction system. The pressure and temperature from the inlet line are between 12 barg to 85 barg and between 20 C ̊ to 42oC respectively, while during normal operation, the pressure and temperature from upstream the pressure reduction system shall be the output conditions from the indirect water bath heaters. From the inlet sources, the gas lines are routed to the instrument/fuel gas heater (F-45001) where the gas is heated to a temperature of 37.11 C ̊ during cold start and bypass during normal operations. It is then brought to the pressure control valve 45-PCV-001/002. The instrument gas leaves the pressure control valve at a pressure of 7.0 Barg and temperature of 25°C. The gas is scrubbed from any liquid that may have formed through the scrubbers (S-45001/S-45002). The instrument gas is then fed to the users at the scrubber conditions through the header via the instrument gas buffer for the field instruments and direct connection for the indirect water bath heaters. A temperature indicator and control (45-TICA-001) is provided the instrument/fuel distribution manifold that senses the temperature of the gas, then regulates the instrument/fuel gas heater temperature output to maintain the required temperature. The conditioned gas is distributed to the fuel gas system comprising of the indirect water bath heaters and to the instrument gas buffer which is further distributed to all the instruments within EEPSP Lot 3 PRMS facility. 3.2.7 Outlet Facility Piping/Pipelines The gas leaves the metering station through an 8” line which is tied into the Power Plant receiving line at a pressure and temperature of 2 - 4 barg and 27 C ̊ respectively. The export line is equipped with Pressure transmitter alarm high and low (28-PIA-003A and 28-PIA-003B) set at 5 barg and 1.8 barg respectively. The custody line is furnished with an emergency shutdown valve (28-SDV-001A and 28- Quantitative Risk Assessment Report Page 16 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 SDV-001B) which is controlled by a pneumatic (gas) actuating system and actuate upon ESD activation. The line is also equipped with a pressure high-high and low-low trip (28-PZA-004A and 28-PZA- 004B) set at 5.5 barg which trigger ESD 1 action (Facility Shutdown). The outlet facility line is also furnished with a Temperature Indicator and Control Alarm high and low (28-TICA-005A and 28-TICA-005B) set at 27 C ̊ . This device senses the outlet temperature of the gas located on the gas export line and signals to open the temperature control valve (61-TCV-001 and 61TCV-002) on the heater bypass, causing cold inlet gas to mix with the heated gas from the heater outlet, thereby regulating export gas the temperature. 3.2.8 Condensate Accumulator The condensate system is provided within the EEPSP PRMS facility and comprises of an instrument fitted condensate vessel (V-25003). All condensates from the filter separator, instrument gas scrubbers, vent stack, and Pig Receiver Barrel, etc. are channeled into the vessel. The vessel operates close to atmospheric pressure. It is equipped with a pressure safety valve set at 10 barg to protect the vessel against gas blow-by and an open vent to guide against gas implosion during condensate evacuation. Pressure sensors (25-PIA-003) with high and low alarm set point of 5.0 barg and are below atmospheric pressure respectively, initiate high and low alarm for operator action. In the event of no operator action on high- and low-pressure alarm, the pressure safeguarding trip (25PZA-002) shall initiate an ESD1 to protect the system from over Pressure. They are provided with level gauges (25-LG-002) and level transmitters (25-LIA-003) to monitor the liquid level in the vessel. During operation, the level indicator and control transmitters (25-LIA-003) set between 268 mm to 1072 mm to monitor the level of the liquid and activate an alarm if the liquid level is high. 3.2.9 Vent Stack The EEPSP PRMS facility and pipelines are complemented by a vent network and a cold vent stack. This system is designed to receive hydrocarbon discharges from pressure relief systems and blowdown the gas during emergency shutdown with depressurization and blowdown for maintenance purposes. Quantitative Risk Assessment Report Page 17 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) 4.0 NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 QRA METHODOLOGY The QRA study was performed according to the general methodology presented in figure 1 below. • Hazard Identification: to determine the incident scenarios, hazards and hazardous events, their causes and mechanisms. • Frequency Estimation: to determine the frequency of occurrence of identified hazardous events and the various consequences. • Consequence Analysis: to determine the extent of the consequences of identified hazardous events. • Risk Summation: to determine the risk levels. • Risk Assessment: to identify if the risk is tolerable/intolerable and to identify risk reduction or mitigation measures and prioritise these using techniques such as risk ranking or cost-benefit analysis. Quantitative Risk Assessment Report Page 18 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 Figure 1: Quantitative Risk Assessment Methodology These elements as shown in the Figure 1 above are procedure used for both information generation and decision-making in managing the risk. 4.1 DATA SOURCE ASSUMPTION The assumptions made for the QRA are listed in the following table and detailed in the appropriate Assumption Sheets in Appendix A. Quantitative Risk Assessment Report Page 19 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 Table 4: List of International Codes and Standards Assumption Sheet No. 4.2 Subject 001 Weather and Meteorological Data 002 Process Parameters and Stream Composition 003 Consequence Modelling Assumptions 004 Isolatable Inventories Approach 005 Isolatable Inventories Approach 006 Failure Frequencies 007 Event Trees 008 Hazardous Event Modelling (Hole Size) 009 Consequence End point 010 Risk Tolerability Criteria 011 Manning Level and Distribution MANNING DATA The installation is primarily considered as an unmanned facility. The manning distribution assumptions have a key influence on the IRPA results, as well as an impact on the societal risk results. The total POB considered for the study is 6 persons. The working hours are consider to be 2 x 12 hour shifts (days and night) and 26 weeks a year i.e. 2190 on-shift hours. Rotation pattern are for all crew members are considered to be 2 weeks / 2 week. The detailed manning distribution with daily hour distribution as per areas are described in Appendix A, Assumption Register. 4.3 METEROLOGICAL DATA Wind statistics (strength and direction) used for the modelling have been provided in Appendix A. Information about the wind speed stability combinations is not available, so it has been assumed that these could be represented by F2 (Pasquill stability F-stable, wind speed 1.5m/s) and D5 (Pasquill stability D-neutral, wind speed 5m/s). It has further been assumed that D5 occurs for 87% of the time and F2 for the remainder. This in line with common QRA practice. Thus, Wind speed of 5m/s (D5) shall be for this QRA. Quantitative Risk Assessment Report Page 20 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) 4.4 NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 FEED SOURCE AND INVENTORY ANALYSIS Material compositions and operating conditions are to be based on the worst case (e.g., rich/lean) and worst season, if more than one is provided. The material characterization such as pressure, temperature, composition etc. for each scenario shall be taken from P&IDs and the M&HB. To have more conservative approach, the condition such as maximum pressure and minimum temperature stream in the section shall be taken into consideration. Stream compositions will be based on those given in the H&MB sheets and shown in Appendix A. Quantitative Risk Assessment Report Page 21 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) 5.0 Revision No: R01 HAZARD IDENTIFICATION The first stage in any risk assessment is to identify the potential incidents that could lead to the release of a hazardous material from its normal containment and result in a major accident. This is achieved by a systematic review of the facilities to determine where a release of a hazardous material could occur from various parts of the installation. In this study, only flammable hazards are relevant involving loss of containment of hydrocarbon gas. Flammable hazards may manifest as high thermal radiation from fires and overpressures following explosions that may cause direct damage, building collapse, etc. Flammable hazards are present throughout the facility and associated pipelines. Fires may occur if flammable materials are released to the atmosphere and ignition takes place. Below shows the summary of the Hazards from the HAZID worksheet Table 5: Status of HAZID Recommendations Extreme Risk Hazard High Risk Hazard Medium Risk Hazard Low Risk Hazard 1 19 5 2 Quantitative Risk Assessment Report Page 22 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 Table 6 below shows the general hazards that were found for loss of containment in the EEPSP project, along with possible causes, expected consequences and proposed or inherent safeguards. Table 6: HAZID Recommendations Summary Category Natural & Environment Hazard Cause Lightening Inherent Safeguard / Proposed Recommendation Scenario Description / Consequences Area is lightening prone and release of lightening energy can become ignition risk on coincident loss of • primary containment, leading to fire/explosion (injuries/fatalities & asset damage) • Natural & Environment Natural & Environment Erosion Subsidence Created (Manmade) Security Hazards Effect of Facility on Surrounding Proximity to Population Quantitative Risk Assessment Report Soil erosion could lead to collapsed foundation and cracking of piping, with potential for loss of primary containment • Lightening Protection System Geo-tech & Topographical survey completed The most up-to-date internal testing systems are applied to discover any defects and fix them early Provide fit for purpose foundation and erosion control structures • Check soil bearing capacity and carry out fit for purpose foundation to manage the risk of subsidence Exposure to security hazard could lead to loss of • primary containment resulting into fire and explosion which may lead to injuries/fatalities and asset • damage Facility is fenced, CCTV systems, security hut installed • Carry out fire and explosion risk assessment for the project and implement mitigation plans for control of offsite impact Subsidence could result into cracking of piping/equipment and loss of primary containment Fire and explosion from EEPSP can result to offsite injuries/fatalities security risk assessment Page 23 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Category Hazard Cause Scenario Description / Consequences Revision No: R01 Inherent Safeguard / Proposed Recommendation Accidental events (seal leaks, loss of primary Continuous Plant • containment from the facility) may lead to discharge Discharges to Soil to soil (environmental pollution) Provide accidental oil contaminated system for the liquid pig receiver Emergency Response Absence of emergency response requirements • (ESD/Blowdown, etc.) could escalation of major • accident scenario (Loss of Primary containment /fire) ESD, Blowdown incorporated in the design Develop emergency response plan and integrate with Lot 1 facility Facility Hazard Sources of Ignition Ignition sources from EEPSP site could lead to fire • and explosion during loss of primary containment scenario Carry out hazardous area classification for the facility and develop access control procedure Facility Hazard Asset Integrity Management Improper asset integrity management could result • into loss of primary containment, with escalated consequences Carry out HAZOP recommendations Tie-ins (shutdown requirements) Improper tie-in arrangements / operation will result to major accident - loss of primary containment possibly leading to injuries/fatalities, asset damage from • ignited release and environmental pollution from unignited release Develop a tie-in plan Environment Damage Facility Hazard Facility Hazard Quantitative Risk Assessment Report Page 24 of 99 study and implement NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 The hazardous scenarios that become MAEs are: • Loss of containment of Flammable HC gas (Vapor) and resultant consequence includes; i) Jet fire (pressurized release) ii) Flash fire from dispersing vapor cloud. • Loss of containment of Flammable HC condensate (liquid) and resultant consequence includes; i) Jet fire (pressurized release) ii) Flash fire from dispersing vapor cloud. 5.1 HOLE SIZE There is a possibility of failure associated with each mechanical component of the plant. These are generic failures and can be caused by such mechanisms as weld failure, corrosion, vibration or external impact (mechanical or overpressure). The range of possible releases for a given component covers a wide spectrum, from a pinhole leak up to a catastrophic rupture (of a vessel) or fullbore rupture (of a pipe/pipeline). It is both timeconsuming and unnecessary to consider every part of the range; instead, representative failure cases are generated. For a given component these should represent fully both the range of possible releases and their total frequency. The range of leak sizes considered for QRA is listed in table 7 below. Table 7: Representative Leak Sizes for QRA Leak Type Representative hole Size (mm) Small Leak 7 Medium Leak 22 Large Leak 70 Rupture 150 For each identified failure case, the appropriate data required to define that case are input to the DNV PHAST modelling package. When the appropriate inputs are defined, PHAST calculates the source terms of each release, such as the release rate, release velocity, release phase and drop size. These source term parameters then become inputs to the consequence modelling. Alternatively, PHAST allows these source terms to be input directly. Quantitative Risk Assessment Report Page 25 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) 5.2 Revision No: R01 FAILURE CASE SELECTION Failure Case Selection stage identifies the failure cases, or major accident hazards, that will have the potential to result in risks to personnel within the facilities and around the pipeline path, and hence will be inputs to the risk modeling. The Failure case for the entire EEPSP facilities has been summarized in Appendix A. Quantitative Risk Assessment Report Page 26 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) 6.0 Revision No: R01 FAILURE FREQUENCY ANALYSIS Failure frequencies was determined for each event in order to perform a probabilistic risk assessment. Generally, a number of techniques are available to determine such frequencies. The approach relies on generic data. This provides failure frequencies for equipment items where data has been obtained from failure reports from a range of facilities. This section presents the failure frequency for the hazard scenarios identified. The failure data of release was derived from the International Association of Oil and Gas Producers (IOGP) as detailed in the QRA Assumption register. 6.1 PART COUNT ANALYSIS There are a number of ways of estimating the leak frequency in a system, varying from a qualitative approaches to complicated component failure mode analysis and failure rate data. Hence the most preferred approach to estimate leak frequency for QRA is to count the number of main equipment items, valves, flanges, Instruments and Length of pipe. The number of Equipment items multiplied by their respective component leak frequency give the overall leak frequency for the process being represented by a given isolatable section. Thus, two key parameters are required to define the leak frequency from the system namely: i) Individual component leak frequency ii) Number of Equipment items in the system. Hence, the Part count for the Isolatable section was given as; Part Count = Individual component leak frequency X Number of Equipment items in the system See Figure 2 for Part count and Leak size distribution. Quantitative Risk Assessment Report Page 27 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Figure 2: Part Count and Leak distribution Quantitative Risk Assessment Report Page 28 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) 6.2 Revision No: R01 EVENT TREE FREQUENCY An Event Tree is constructed by laying out each identified contributing factor in chronological order and assessing all possible combinations of factors to provide a number of possible hazardous event outcomes. The lines connecting the contributing factors correspond to all the possible paths that can occur during the development of the physical phenomenon. Each branching along the path shows either the possibility of two different “spontaneous” outcomes or the occurrence of success or failure in mitigation of the incident. The Top Event on the left side of the event tree is the release of flammable hydrocarbon from the pipeline. For each top event, the base expected frequency of occurrence has been calculated. On the right side of the tree, the top event develops, through the subsequent branches, a number of outcomes. The frequency of each single outcome is equal to the frequency of the top event multiplied for the branch probabilities of all nodes along the path. Having estimated the isolatable sections frequencies as presented in Appendix E, the range of possible consequences that could occur after the initiating failure is developed using event tree analysis (ETA) and the probabilities of alternative outcomes are also estimated. The event tree shown in Appendix D was used in this study considering the following factors within the event tree: 6.2.1 i) Ignition and early ignition probabilities; and ii) Explosion given ignition probability. Ignition and Early Ignition A fire will develop if a leak is ignited. Ignition probabilities used for event trees are based on release rates given in Cox, Lees and Ang, as shown in Assumption Sheet 011. If the release is ignited immediately, a jet or pool fire is assumed to develop before any mitigating measures can be taken. However, if the leak is not immediately ignited, i.e., delayed ignition, the release may disperse to some distance before coming in contact with an ignition source. For volatile or gaseous substance, it will result in a flash fire or explosion if the gas accumulates in a congested area. 6.2.2 Explosion In case of delayed ignition of flammable gas, unignited vapours may have started to accumulate in congested areas and may result in an explosion. An explosion is defined as an ignited event that generates sufficient overpressure to produce immediate escalation of the event. The probability of delayed ignition leading to an explosion is based on historical data as presented by Cox, Lees and Ang. These explosion probabilities are presented in Assumption Sheet 011. Quantitative Risk Assessment Report Page 29 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) 6.2.3 Revision No: R01 Outcome Consequences As shown in Appendix F, the event tree outcomes are grouped together into the following event outcomes, with the consequences of each group modelled to determine the overall risk (event tree outcome frequency multiplied by the consequence). This section outlines the event tree outcomes for the facility as modelled in this analysis and determined and used excel calculatiom in generating the PLL to personnel. 6.2.4 Immediate Fires Generally, for low-pressure liquid releases, pool fires are modelled with the fire size depending on the inventory available to the fire, any containment (such as bunding) and drainage. For gas releases, jet fires are typically modelled. Jet fires are directional and of high intensity. For rupture scenarios, ignited gas releases are modelled as fireball scenarios as typically the whole inventory of the isolatable section is discharged within seconds. For isolatable sections with only piping, gas jet fires are modelled for rupture of the piping. 6.2.5 Delayed Fires In the case of a delayed ignition, the ensuing flash fires flash back to the release source and generally continue as a jet fire, depending on the hazard scenario under consideration. Equipment and piping congestion and a lack of adequate ventilation may result in an explosion causing damage to the surrounding area. An event tree used for this study is shown in Appendix E. Quantitative Risk Assessment Report Page 30 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) 7.0 Revision No: R01 CONSEQUENCE ANALYSIS Consequence analysis methodology comprises source term and physical effects modelling. Software package DNV PHAST 8.4 has been used for the calculation of the consequence effects. Consequence modelling has been carried out for the identified hazard scenarios, including release rates, thermal radiation extent, dispersion and explosion overpressure distance. Figure 3 depicts the process by which this consequence analysis was conducted. The first step is to define the potential event sequences and potential Hazard Incident. Accidents begin with a hazard incident, which usually results in the loss of containment of material from the process. Typical hazard incidents might include the rupture or break of the pipeline. Once the Hazard Incident is known, source models are selected to describe how materials are discharged from the process. The source model provides a description of the rate of discharge. Dispersion models convert the source term outputs to concentration fields downwind from the source. A dispersion model is subsequently used to describe how the material is transported downwind and dispersed to some concentration levels. For flammable releases, fire models convert the source model information on the release into energy hazard potentials such as thermal radiation. Figure 3: Consequence modelling for an Event which involves Ignition 7.1 SOURCE TERM MODELLING A source term describes the flow rate in the event of a leak. The release rate was modelled using the consequence modelling software package, DNV PHAST v8.4. Determination of the source term would depend on the release conditions e.g., pressure, temperature, phase of release, mode of release i.e., a hole from an equipment etc. Based on the representative hole sizes presented in Quantitative Risk Assessment Report Page 31 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 Assumption Sheet 008, the initial release rates generated by PHAST v8.4 due to release from each isolatable sections are presented in Appendix B 7.2 PHYSICAL EFFECTS MODELLING The type of event outcome following a loss of containment scenario depends on many factors such as the material, its phase, the operating conditions and the location of the release. The MAE to be modelled are namely jet fires, pool fires, flash fires, fireballs, flammable gas dispersion, Gas explosion. More details on the modelled outcomes are presented below. 7.2.1 Jet Fires A jet fire describes the flame produced due to the ignition of a continuous pressurised leak or discharge from process vessels and piping. It is a burning jet of gas or atomised liquid of defined shape based on the momentum and dispersion of the release. This type of fire represents the most hazardous fire attack on a vessel as it acts like a blowtorch directed at the vessel, both annealing and eroding the metal surface of the equipment. Jet fires may also result from releases of high-pressure liquid containing dissolved gas, due to the gas flashing off and turning the liquid into a spray of small droplets. 7.2.2 Pool Fires A pool fire is a burning pool of liquid that has collected on a horizontal surface. If the liquid pool formed after a spill is ignited soon after release, the flammable atmosphere will only exist close to the surface of the pool. The heat generated by the fire above the surface of the pool causes the evaporation of more fuel for the fire and the fire then becomes self-sustaining. The fire will cover the entire surface of the pool. Pool fires do not create extreme temperatures; usually resulting in incomplete combustion and producing a smoky cloud, since the interior of the pool is starved of oxygen. They are unlikely to cause failure of structural members but may cause failure of other vessels that are engulfed in the fire or the 37.5 kW/m2 thermal radiation. 7.2.3 Flash Fires A flash fire is a fire that burns back from an ignition source to its point of release origin and is of extremely short duration lasting only a few seconds. Therefore it will not cause structural damage. However the intensity of the thermal radiation is sufficient to result in fatalities for those engulfed in the flash fire. After flash back, it will continue to burn as a jet fire depending on the source conditions. The size of a flash fire is dependent on the time delay before ignition and the flammability limits of the gas. If the gas plume is allowed to fully develop to its stoichiometric concentration before ignition, the extent of the flash fire will be the volume of the plume that is within the flammability limits, beyond which the gas will not ignite as its concentration is no longer flammable. Thus, the flash fire results are presented in terms of distance to the Lower Flammability Limit (LFL) in this study. Quantitative Risk Assessment Report Page 32 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) 7.2.4 Revision No: R01 Fireballs A fireball is an intense spherical fire resulting from a sudden release of pressurised liquid or gas that is immediately ignited, burning as it expands, forming a ball of fire, rising in the air. A fireball expand rapidly may cause fatalities among people within it. Fireball durations are typically 5 – 20 seconds, and so the heat loads are unlikely to damage any equipment. 7.2.5 Gas Explosions An explosion is the uncontrolled release of energy from a flame front propagating through a flammable medium, characterised by the generation of heat, light and pressure; it is the pressure generated that causes explosions to be a hazard outside the flame. The potential for generating pressure is determined by the flame speed, defined as the rate of propagation of the flame front. The laminar burning velocity is the velocity at which a plane combustion wave propagates through an infinite stationary flammable mixture and is a fundamental property of any flammable mixture. For most fuels, the maximum laminar burning velocity occurs at fuel concentrations slightly richer than stoichiometric. The flame speed is not in general equal to the laminar burning velocity due to the effects of the geometry of the explosion, the expansion of the flammable mixture and gas turbulence. For each release, the extent of the vapour cloud to its LFL level is compared against the confined areas identified on both EEPSP plot plan. This may not be the true representation of the equipment layout in this location the 2D layout to estimate the VBR for both locations. Those vapour clouds that extend into confined areas are modelled for explosion given that stoichiometric fraction of the flammable gas in the confined area may lead to an explosion. Explosion modelling were performed with the TNO Multi-Energy model in the DNV PHAST V8.4. 7.3 SUMMARY OF CONSEQUENCE AND EVENT FREQUENCY RESULTS The consequence and event frequency results for all the hazard scenarios identified are summarised in Appendix F. Quantitative Risk Assessment Report Page 33 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) 8.0 Revision No: R01 RISK ACCEPTANCE CRITERIA The risks evaluated within this study were referenced against NUPRC accepted criteria, in order to determine the acceptability of the risks and any need for risk reduction measures to be implemented within the design process. The risk criteria used are drawn from the widely used framework set out by NUPRC, using the As Low As Reasonably Practicable (ALARP) principle, and proposes risk acceptance criteria to be used as guidance for this study. 8.1 RISK ASSESSMENT FRAMEWORK The following measures of acceptability was evaluated in assessing the risks from any hazardous activity: • Individual risk criteria was evaluated to limit risks to personnel on the facility. • Cost-benefit analysis was used to ensure that, once the above criteria are satisfied, an optimum level of safety measures is chosen for the activity, taking costs as well as risks into account. The simplest framework for risk criteria is a single risk level which divides tolerable risks from intolerable ones. Such criteria give attractively simple results, but they need to be used very carefully, because they do not reflect the uncertainties both in estimating risks and in assessing what is tolerable. A more flexible framework specifies a level, usually known as the maximum tolerable criterion, above which the risk is regarded as intolerable whatever the benefit may be and must be reduced. Below this level, the risks should also be made As Low As Reasonably Practicable (ALARP). This means that when deciding whether or not to implement risk reduction measures, their cost may be taken into account, using cost-benefit analysis. In this region, the higher the risks, the more it is worth spending to reduce them. If the risks are low enough, it may not be worth spending anything, and the risks are then regarded as negligible. This approach can be interpreted as dividing risks into three tiers (as is illustrated in figure 8-1 below): • An upper band where risks are intolerable whatever the benefit the activity may bring. Risk reduction measures or design changes are considered essential. • A middle band (or ALARP region) where the risk is considered to be tolerable only when it has been made ALARP. This requires risk reduction measures to be implemented if they are reasonably practicable, as evaluated by cost-benefit analysis. • A negligible region where the risks are negligible and no risk reduction measures are needed. Quantitative Risk Assessment Report Page 34 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 Figure 4: ALARP Framework for Risk Criteria 8.2 INDIVIDUAL RISK CRITERIA Individual risk is widely defined as the risk of fatality (or serious injury) experienced by an individual, noting that the acceptability of individual risks should be based on that experienced by the most exposed (i.e. ‘worst-case’) individual. The criteria used for individual risks are the ones widely used in the industry and approved for use by NUPRC. These criteria are: • The acceptable criterion, for the public, corresponding to the level below which individual risks can be treated as effectively negligible, is 10-6 per year (i.e., 1 in 1,000,000 years) • If the risk calculated from heat radiation at residential areas exceeds 5 x 10-7 per year, this will cause injury after 30 seconds of direct exposure to the heat. The risk of injury in this case is 5 x 10-7 (i.e. 5 injuries in 10,000,000 years), which may be considered negligible. In terms of the acceptability of individual risks, it should be noted that: • Individual risks are typically presented as contours that correspond to the risk experienced by a person continuously present, outdoors, at each location. • While people are unlikely to remain “continuously present, outdoors” at a given point, the individual risk levels used to assess residential developments are modified to account for 30% presence factor or the proportion of time spent outdoors. That is, it should be conservatively assumed that dwellings are occupied at 70% times. Quantitative Risk Assessment Report Page 35 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) • 8.3 NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 It should also be noted that lower criteria are often adopted with respect to vulnerable populations, such that schools and hospitals, for example, should be located such that the individual risks are well below 10-6 per year. SOCIETAL RISK CRITERIA A proposed criterion for Societal Risk is set out in form of an F-N curve, which gives the cumulative frequency (F) of exceeding a number of fatalities (N). It is, however, important to note that the risk contour did not reach the community close to facility. Quantitative Risk Assessment Report Page 36 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) 9.0 RISK ASSESSMENT AND RESULTS 9.1 GENERAL Revision No: R01 The results of the risk analysis are presented in this section. The results are expressed in terms of: • IRPA for onsite worker groups; • PLL per annum for onsite workers Note that F-N curve for offsite societal risk was not consider since that the risk contour didn’t reach the communities surrounding the facility, thus posing no societal risk threat. In addition, the risk results for the EEPSP were generated from the generated event trees. A spreadsheet was used to calculate the risks and generate a wide range of risk indicators in a variety of formats. The objective in compiling this risk results section was to present sufficient information to provide an understanding of the key risk drivers without reporting the entire model output 9.2 INDIVIDUAL RISK PER ANNUM (IRPA) A spreadsheet was also used to integrate frequencies and consequences of the various outcomes in order to give measures of the Individual Risk (IR) level with respect as per location occupied by onsite worker. IRPA is the statistical likelihood of an identified individual perishes during a year of facility operation. It is a measure of “inherent” risk and is applicable regardless of population density. IRPA is the calculated probability of fatality per annum to a hypothetical individual who is present at the site 24 hours a day, 365 days a year, i.e. it does not take into account the actual amount of time a person spends at site. IRPA is defined in Equation below as: 𝐼𝑅𝑃𝐴 = 𝐿𝑆𝐼𝑅 x Rate of Time in Plant Total Manhour LSIR – Location Specific Individual Risk LSIR is a function of the Probability of Fatality and Frequency of a hazardous event for the occupied location in the facility. 𝐿𝑆𝐼𝑅 = Fatality level x Event frequency Occupied location/area within the EEPSP facility is given as: • Station Inlet area • Pig Receiver area • Control Building • Gate House Quantitative Risk Assessment Report Page 37 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) • Water Treater Area • Process Area 1(Filter Separator Area) • Process Area 2 (Water Bath Heater Area) • Process Area 3 (Condenser Accumulation Area) • Process Area 4 (PRMS /MS1) • Process Area 5 (PRMS /MS2) Revision No: R01 Table 8: Individual Risk Per Annum (IRPA) for EEPSP facility S/n Occupied Area LSIR IRPA 1 Station Inlet Area 4.47E-03 3.32E-06 2 Pig Receiver Area 4.32E-03 3.22E-06 3 Control Building 0.00E+00 0.00E+00 4 Gate House 0.00E+00 0.00E+00 5 Water Treatment Plant Area 0.00E+00 0.00E+00 6 Process Area 1(Filter Separator Area) 1.05E-02 7.85E-06 7 Process Area 2 (Water Bath Heater Area) 1.14E-02 8.48E-06 8 Process Area 3 (Condenser Accumulation Area) 7.98E-04 5.94E-07 9 Process Area 4 (PRMS /MS1) 2.90E-03 2.16E-06 10 Process Area 4 (PRMS /MS2) 6.72E-04 5.00E-07 9.3 POTENTIAL LOSS OF LIFE (PLL) PPL is the calculated Individual Risk Per Annum with respect to number of onsite worker. Table 9: PPL for EEPSP facility S/n Occupied Area No of Workers IRPA PPL 1 Station Inlet Area 2 3.32E-06 6.65E-06 2 Pig Receiver Area 3.22E-06 6.43E-06 3 Control Building 0.00E+00 0.00E+00 Quantitative Risk Assessment Report Page 38 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) No of Workers Revision No: R01 S/n Occupied Area 4 Process Area 1(Filter Separator Area) 7.85E-06 Process Area 2 (Water Bath Heater Area) 8.48E-06 Process Area 3 (Condenser Accumulation Area) 5.94E-07 Process Area 4 (PRMS /MS1) 2.16E-06 Process Area 4 (PRMS /MS2) 5.00E-07 5 6 7 8 IRPA PPL 1.57E-05 1.70E-05 1.19E-06 4.32E-06 1.00E-06 9 Gate House 2 0.00E+00 0.00E+00 10 Water Treatment Plant Area 2 0.00E+00 0.00E+00 Comparing the IRPA and PPL values within the facility ie Tables 8 and 9 with the ALARP Framework, it can be deduced that the risk are within negligible region in the ALARP triangle, hence there will no need for any further risk reduction measures. Quantitative Risk Assessment Report Page 39 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) 10.0 NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 CONCLUSIONS AND RECOMMENDATION Based on the findings of this QRA and the subsequent analysis completed, the following conclusions and recommendations can be made: 10.1 CONCLUSION The results of this QRA report show that the 1 x 10-6 risk contour (which is the risk of fatality to the public) does not appear for the 30 years of operation of this facility since as there are no visible dwelling around the pipeline vicinity. This pipeline operations is considered ALARP if all the initial design assumptions are upheld. 10.2 RECOMMENDATION i) The emphasis on risk reduction should be on preventative measures, i.e. to minimize the potential for leaks to occur. This would majorly be achieved through appropriate design (to recognized standards) and through effective inspection, testing and maintenance plans / procedures. All of these measures are already included in the pipeline design and mitigation measures to be followed strictly by OWNER. ii) For isolation to be effective first requires detection to occur. Close monitoring and rapid shutdown of the pipeline in case of an emergency are important to limiting the effects of leaks. Quantitative Risk Assessment Report Page 40 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) APPENDIX A: Revision No: R01 ASSUMPTION SHEET ASSUMPTION SHEET Project: ENGINEERING, PROCUREMENT & CONSTRUCTION OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP - LOT 3) Assumption No.: 001 Revision: 0 Date: 08/06/2023 Subject: Weather and Meteorological Data Assumption: Weather conditions are used in DNV PHAST (consequence modelling). Assumptions regarding the required inputs are as follows: • Relative humidity of 84.66% is assumed based on the Mean Relative Humidity. • An ambient temperature of 30°C is assumed based on the ‘Ground Temperature. • The wind conditions are: Day Time: • 5D – Pasquill stability factor D with wind speed 5m/s; and Night Time: • 1.5F – Pasquill stability factor F with wind speed 1.5m/s. Wind rose data for Escravos area will be used for the project; Figure 5: EEPSP Wind rose Quantitative Risk Assessment Report Page 41 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 ASSUMPTION SHEET Project: ENGINEERING, PROCUREMENT & CONSTRUCTION OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP - LOT 3) Assumption No.: 001 Revision: 0 Date: 08/06/2023 Subject: Weather and Meteorological Data Based on the windrose data, the following wind direction data has been extracted, assumes true north. Table 10: Wind rose Data – True North N NNE NE ENE E ESE SE 0 22.5 45 67.5 90 112.5 135 5D 0.3 0 0.05 0 0.2 0 0.1 SES S SSW SW WSW W WNW NW 157.5 180 202.5 225 247.5 270 292.5 315 0 0.43 0 0 0.83 0 0 0 Weather Justification: The weather conditions have a key influence on flammable cloud dispersion and hence the consequences associated with any release and direct impact on consequence modelling results. The influence of any specific weather category and direction will vary for every release. Minor changes in the meteorological assumptions will have a negligible influence on the risk results. References: 1. Nigerian Meteorological Data (NiMET) 2. http://www.metartaf.com/NG Comments: Quantitative Risk Assessment Report Page 42 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 ASSUMPTION SHEET Project: ENGINEERING, PROCUREMENT & CONSTRUCTION OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP - LOT 3) Assumption No.: 002 Revision: 0 Date: 08/06/2023 Subject: Process Parameters and Stream Composition Assumption: Material compositions and operating conditions are to be based on the worst case (e.g., rich/lean) and worst season, if more than one is provided. The material characterization such as pressure, temperature, composition etc. for each scenario shall be taken from P&IDs and the M&HB. To have more conservative approach, the condition such as maximum pressure and minimum temperature stream in the section shall be taken into consideration. Stream compositions will be based on those given in the H&MB sheets and shown in Tables 11 below Table 11: Feed gas Composition S/N Component Formula Average Mole 1 Nitrogen N2 0.3180 2 Methane CH4 88.9274 3 Carbon-dioxide CO2 2.1729 4 Ethane C2H4 6.0411 5 Propane C3H8 1.8150 6 i-Butane C4H10 0.2650 7 n-Butane C4H10 0.2283 8 i-Pentane C5H12 0.0372 9 n-Pentane C5H12 0.1445 10 n-Hexanes C6H14 0.0475 11 n-Heptane C7H16 0.0031 12 n-Octane C8H18 0.0000 13 n-Nonane C9H20 0.0000 Total Quantitative Risk Assessment Report 100 Page 43 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 Justification: This is a conservative approach. The process parameters have direct impact in the gas dispersion and explosion simulations. References: 1. NGIC-EEPSP_YNL-PRO-RPT-002 Heat & Mass Balance Report for 7.5 MMSCFD 2. NGIC-EEPSP_YNL-PRO-RPT-003 Heat & Mass Balance Report for 10 MMSCFD 3. NGIC-EEPSP_YNL-PRO-PFD-001 PFD for PRMS for 10MMSCFD 4. NGIC-EEPSP_YNL-PRO-PFD-003 PFD for PRMS for 7.5MMSCFD 5. NGIC-EEPSP_YNL-PRO-PID-002 P&IDs for PRMS for 10MMSCFD 6. NGIC-EEPSP_YNL-PRO-PID-003 P&IDs for PRMS for 7.5MMSCFD Comments: Quantitative Risk Assessment Report Page 44 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 ASSUMPTION SHEET Project: ENGINEERING, PROCUREMENT & CONSTRUCTION OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP - LOT 3) Assumption No.: 003 Revision: 0 Date: 08/06/2023 Subject: Consequence Modelling Assumptions Assumption: The following general modelling assumptions was used for the assessment. Table 12: Consequence Modelling Assumptions Parameter Meteorological Data Flammable Gas End Points Dispersion Averaging Times Solar Radiation Modelling Assumptions • Wind speed 1.5m/s and Pasquill stability class ‘F’ • Wind speed 5m/s and Pasquill stability class ‘D’ Distances to 1/2 LFL and UFL. The averaging time for flammable gas dispersions will be set at 18.75s which is the default setting in the software (Reference 4). 1.04 kW/m2 solar radiation allowance will be included in the thermal radiation calculation for day and nighttime respectively. A surface roughness parameter of 0.045mm is adopted for all wind Surface Roughness speeds and stability classes. This reflects the equivalent of open countryside, and flat land/open farmland. Release Orientation A release height of 1m will be used. Justification: This is a conservative approach. The process parameters have direct impact in the gas dispersion and explosion simulations. References: 1. CMPT, A Guide to Quantitative Risk Assessment for Offshore Installations, Publication 99/100a, 1999. 2. IP- 19 IP Model Code of Safe Practice in the Petroleum Industry. 3. Methods of the Calculation of Physical Effects ‘Yellow Book' CPR 14E Comments: Quantitative Risk Assessment Report Page 45 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 ASSUMPTION SHEET Project: ENGINEERING, PROCUREMENT & CONSTRUCTION OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP - LOT 3) Assumption No.: 004 Revision: 0 Date: 08/06/2023 Subject: Isolatable Inventories Approach Assumption: Isolatable inventories were determined from a review of the PFD and P&IDs. Isolation of streams were based on the following: • Between Emergency Isolation Valves. • Between emergency isolation valves (ESDV or XZVs) and sectionalizing block valves. Isolatable Section (IS) IS-01 FC-01 4” above ground line from NPSC Facility Tie in - station inlet header FC-02 Instrument gas from Station inlet to Instrument gas Skid. FC-03 Inlet Filter separator package V-25001A FC-04 IS-02 Inlet Indirect Water Bath Heater F-61001A FC-06 Inlet Indirect Water Bath Heater F-61001B FC-07 Inlet Pressure Reduction Skid Package FC-08 Inlet Pressure Reduction Skid – IGS/FS Skid FC-10 FC-56 FC-11 FC-12 IS-04 FC-13 FC-14 FC-15 IS-05 Inlet Filter separator package V-25001B FC-05 FC-09 IS-03 Section Description Failure Cases (FC) No. FC-16 Quantitative Risk Assessment Report Inlet metering & control package 7000-PK-002 1” PRMS line – IGS /FS 6” above ground line from CNL Facility Tie in - station inlet header 1” above ground liquid outlet of the filter separators V-25001A to closed drain V-25002 1” above ground liquid outlet of the filter separators V-25001B to closed drain V-25002 1/ ” 2 above ground liquid outlet of the Vent Stack 7000-FS-003 to closed drain 1” liquid outlet of Pig Receiver PR-31001 to Condensate Accumulator V25002 1/ ” 2 liquid outlet of the Instrument Supply Vessel to Condensate Accumulator V-25002 1” 7.5MMSCFD Station inlet line – 4” Inlet Isolation Vent header. Page 46 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) FC-18 2” 7.5 MMSCFD Filter separator package V-25002A Pressure Relief line to 4” Filter Separator Vent header FC-19 2” 10 MMSCFD Filter separator package V-25002A Pressure Relief line to 4” Filter Separator Vent header FC-20 2”,1”, 1” 7.5 MMSCFD Filter separator package V-25002B Pressure Relief line to 4” Filter Separator Vent header. FC-21 2”, 1”, 1” 10 MMSCFD Filter separator package V-25002B Pressure Relief line to 4” Filter Separator Vent header FC-22 2”, 7.5 MMSCFD Indirect Water bath heater F-61002A Pressure Relief line to 4” WBH Vent header. FC-23 IS-07 Revision No: R01 2” 10 MMSCFD Indirect Water bath heater F-61002B Pressure Relief line to 4” WBH Vent header. FC-24 1” 7.5 MMSCFD Indirect Water bath heater F-61002A Pressure Relief line to 4” WBH Vent header. FC-25 1” 10MMSCFD Indirect Water bath heater F-61002B Pressure Relief line to 4” WBH Vent header header FC-26 3” 7.5MMSCFD PRMS Relief line to 4” PRMS Vent header FC-27 3” 10MMSCFD PRMS Relief line to 4” PRMS Vent header FC-28 2” 7.5 MMSCFD PRMS Blowdown line to 4” PRMS Vent header. FC-29 2” 10 MMSCFD PRMS Blowdown line to 4” PRMS Vent header. FC-30 1”7.5MMSCFD Gas Metering System Relief line to 2” Gas Metering Vent header. FC-31 1”10MMSCFD Gas Metering System Relief line to 2” Gas Metering Vent header. FC-32 4” Pig Launcher Relief line to 4” Pig System Vent header FC-33 4” Pig Receiver Relief line to 4” Pig System Vent header FC-34 4” Pipeline Vent header, 4” Metring Skid 1&2 Vent header, 4” PRMS Skid 1&2 Vent header, 4” Indirect WBH 1&2 vent header, Inlet Isolation vent header, 4” Pigging System Vent header to 8” Cold Vent Header FC-35 FC-35 4” Inlet piping to Inlet Filter separator V-25002A FC-36 1” Filter separator Relief to 4” Filter separator V-25002A Vent header FC-37 1” Filter separator Relief to 4” Filter separator V-25002A Vent header FC-38 4” Filter separator V-25002B outlet line to inlet header WBH F-61002B FC-39 1” ” Filter separator V-25002B liquid outlet line to Condensate accumulator Quantitative Risk Assessment Report Page 47 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) IS-08 IS-09 IS-10 IS-11 IS-12 Revision No: R01 FC-40 4” Filter separator V-25002A and 4” Filter separator V-25002B outlet to 4” WBH F-61002A inlet line. FC-41 4” WBH F-61002A outlet line to 4” WBH F-61002A Warm gas header FC-42 1” WBH F-61002A outlet By-pass line to 4” WBH F-61002A Cold vent header. FC-43 1” BDV line via 4” Filter separator V-25002A and 4” Filter separator V25002B outlet to 4” WBH F-61002A Cold vent header. FC-44 4” WBH F-61002A outlet line via 4” WBH F-61002B cold gas header to 4” WBH F-61002B inlet line. FC-45 4” WBH F-61002B Outlet line via 4” WBH F-61002B Warm gas header to PRMS. FC-46 1” WBH F-61002B outlet By-pass line to 4” WBH F-61002B Cold vent header. FC-47 4” WBH F-61002B Warm gas header to 4” PRMS Header. FC-48 4” PRMS Header via 2” line via to IGP/FS Skid FC-49 6” Tie-in line to Pig launcher FC-50 6” Pig Launcher line to 4” Facility Inlet line FC - 51 1” Pig Receiver Relief line to 4” Pig Receiver Cold Vent Header. FC - 52 2” Pig Receiver Kicker line to 4” Facility Inlet line FC - 53 4” 10MMSCFD PRMS line to 8” 10MMSCFD PRMS header line FC – 54 8” 10MMSCFD PRMS line to 8” Gas Metering System FC - 55 8” 10MMSCFD Gas Metering System header to 8” 10MMSCFD Gas Metering System outlet line via 8” header. FC - 56 8” 10MMSCFD Gas Metering System outlet – EEPSP Power plant FC- 57 4” 7.5 MMSCFD PRMS line to 8” 10MMSCFD PRMS header line FC- 58 8” 7.5 MMSCFD PRMS line to 8” Gas Metering System FC - 59 8” 7.5 MMSCFD Gas Metering System header to 8” 7.5 MMSCFD Gas Metering System outlet line via 8” header. Quantitative Risk Assessment Report Page 48 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 ASSUMPTION SHEET Project: ENGINEERING, PROCUREMENT & CONSTRUCTION OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP - LOT 3) Assumption No.: 005 Revision: 0 Date: 08/06/2023 Subject: Process Block and Equipment Part Count Assumption: Facility process shall be divided into process blocks representative of the process areas on the facility. Within each process block the equipment will be split up into isolatable process sections defined by the operating conditions of the plant and the hydrocarbon fuel components present. For each isolatable process section, the total equipment counts will be used to calculate the total leak frequencies. The counts in all sections will be made on the basis of major equipment items like vessels, columns, heat exchangers including the piping. Only equipment in service during normal operation and with the potential to release HC vapour will be taken into account. Equipment used on an infrequent basis such as pig launchers will be excluded from the study. For each major piece of equipment fittings count will be done using the project PFD/P&ID. The fittings count will then be used in conjunction with the equipment information for each of the isolatable sections to give a leak frequency per hole size for each of the isolatable sections. To determine event frequency failures, the parts count for the flowlines/pipeline will be performed using basic process flow diagrams. To complete the parts count, it is assumed that a flange creates potential for 2 leak points as shown in figure below. The parts count results are provided in Table below. The Parts Count exercise will take the following into consideration: 1. All valves have two flanges. 2. Where a flanged valve separates isolatable section, the upstream flange will be counted with the valve only. 3. A leak is assumed from two connected flanges; viz; Figure 6: Part Count Quantitative Risk Assessment Report Page 49 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 ASSUMPTION SHEET Project: ENGINEERING, PROCUREMENT & CONSTRUCTION OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP - LOT 3) Assumption No.: 005 Revision: 0 Date: 08/06/2023 Subject: Process Block and Equipment Part Count Parts Description Actuated valves Flanges Non-Return Valves Pipe length Quantitative Risk Assessment Report Parts Count 3 8 (16 leak points) 1 50m Page 50 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 ASSUMPTION SHEET Project: ENGINEERING, PROCUREMENT & CONSTRUCTION OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP - LOT 3) Assumption No.: 006 Revision: 0 Date: 08/06/2023 Subject: Failure Frequencies Assumption: As Weam has not received a database from the Owner, hence, the generic failure data for valves, flanges, pipeline, etc. has been used as the basis of the frequency analysis as prescribed in IOGP 434 – 01 Process Release Frequencies. Data from the EGIG Pipeline Incidents as well as local available and relevant online data were considered and used for specific onshore pipeline hazards such as external interference, external corrosion and materials defects data. The EGIG database represents a source of pipeline fault data, which is specific to the European transmission and based on incidents occurring during over half a million pipeline operating years (of which over 90% is natural gas pipelines) between 1970 and 2016. The primary failure frequencies that will be used are given below. Justification: • • • Key influence on the risks (i.e., risk is directly proportional to frequency). CONTRACTOR assumes that frequency analysis based on Parts Count Approach was used. CONTRACTOR considers flanges, instrument connections/ small bore fittings in release frequency estimation. • CONTRACTOR considers main equipment and associated piping in release frequency estimation. References: IOGP, “Process Release Frequencies,” Risk Assessment Data Directory, International Association of Oil & Gas Producers, Report No. 434‐01, September 2019; 2) EGIG: Gas Pipeline Incident - 10th Report of the European Gas Pipeline Incident Data Group (period 1970 – 2016) 3) ANSI/ASME B31.8: Gas Transmission and Distribution Piping Systems Comments: 1) Quantitative Risk Assessment Report Page 51 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 ASSUMPTION SHEET Project: ENGINEERING, PROCUREMENT & CONSTRUCTION OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP - LOT 3) Assumption No.: 007 Revision: 0 Date: 08/06/2023 Subject: Event Trees Assumption: The event tree analysis is used to estimate event outcome frequency (i.e., jet fire, flash fire, pool fire & explosion). The type of ignition and release orientations are accounted for in event tree branches. Event tree probabilities will include Immediate ignition, Delayed ignition and No ignition. The generic event trees considered for gas, two-phase & liquid releases are presented in figure below. Figure 7: Event Tree The probability of explosion upon ignition of explosive mixture depends on its release rate and is taken from Cox, Lee and Ang, data published the IP Research Report, as presented in Table below: Release Rate Probability of Explosion given Ignition Minor (< 1 kg/s) 0.04 Major (1 – 50 kg/s) 0.12 Massive (> 50 kg/s) 0.3 References: Quantitative Risk Assessment Report Page 52 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 ASSUMPTION SHEET Project: ENGINEERING, PROCUREMENT & CONSTRUCTION OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP - LOT 3) Assumption No.: 007 Revision: 0 Date: 08/06/2023 Subject: Event Trees 1. Energy Institute, Ignition Probability Review, Model Development and Look-Up Correlations, IP Research Report, January 2006 2. Cox, A.W., Lees, F.P., and Ang, M.L., “Classification of Hazardous Locations”, IChemE. (1990). Comments: Quantitative Risk Assessment Report Page 53 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 ASSUMPTION SHEET Project: ENGINEERING, PROCUREMENT & CONSTRUCTION OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP - LOT 3) Assumption No.: 008 Revision: 0 Date: 08/06/2023 Subject: Hazardous Event Modelling (Hole Size) Assumption: Hole Size Distribution The release scenarios for each hazard identified is broken down into representative hole sizes. The following was be applied for the pipeline segments: The following leak sizes was considered: Release Size Representative Range (mm) Release Size (mm) Description 1–3 7 Small 10 – 50 22 Medium 50 – 150 70 Large 150 150 Full Rupture 3 – 10 Justification: The dispersion and consequences associated with the pseudo components are relatively sensitive to assumptions affecting the heat transfer to the cloud. Hence, the above values are relatively conservative representative conditions, but will not necessarily correspond to the worst-case dispersion conditions that may occur. The release size selected as representative is a key factor in the release parameters and subsequent consequences for each case. The assumptions have a direct impact on consequence impact assessment and escalation potential. References: 1. IOGP, “Process Release Frequencies,” Risk Assessment Data Directory, International Association of Oil & Gas Producers, Report No. 434‐1, March 2010; Comments: Quantitative Risk Assessment Report Page 54 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 ASSUMPTION SHEET Project: ENGINEERING, PROCUREMENT & CONSTRUCTION OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP - LOT 3) Assumption No.: 009 Revision: 0 Date: 08/06/2023 Subject: Consequence End point Assumption: Based on fluid composition and conditions, the following consequence scenarios was be considered: • Jet fire – Jet fires was considered for all vapour inventories and for liquid streams where the components of the stream are predominantly flammable. • Pool fire – Pool fires may be considered for all liquid hydrocarbon streams where the components of the stream are predominantly flammable. • Vapour Cloud Explosion (VCE) – Burning gas cloud that develops high overpressures. This is likely to kill anyone within it and may also severely damage steel structures. • Flash fire – A fire that propagates through a cloud of gas. This may be lethal for anyone within it but is unlikely to damage steel structures. The table below summarizes the consequence end-points that was used to calculate the consequences. Consequence Event Parameter Thermal Radiation (Jet Fire, Pool Fire, Fireball) 4.7kW/m2 Description CMPT defines 5kW/m2 as the limiting radiation intensity for escape action lasting more than a few minutes in normal plant clothing. Limiting radiation intensity for escape actions lasting a few 12.5kW/m2 seconds. At this level, the pain threshold is reached in about 4 seconds, and second degree burns on exposed skin in about 40 seconds. Taken as the criterion for immediate fatality. At this level, the pain threshold is virtually instantaneous, and second degree 37.5kW/m2 burns on exposed skin occur in about 8 seconds. This thermal radiation level is sufficient to cause damage to process equipment after prolonged exposure. Flammable Gas 50% LFL The 50% LFL result is presented to account for inconsistent gas cloud dispersion due to wind speed and stability. Flash fire envelope. Personnel within gas cloud are engulfed LFL in a fire that, although brief, is likely to cause death due to inhalation of hot combustion gases, if not due to burns. Quantitative Risk Assessment Report Page 55 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Probability of death of 100% is assumed for people within the cloud. Explosion Overpressure Overpressure (bar) Effects 0.02 Shattering of windows 0.13 Frame distortion of steel framed building, dangerous for people, 1% lethality. 0.2 Steel framed building pulled out from foundation References: 1. CMPT, A Guide to Quantitative Risk Assessment for Offshore Installations, Publication 99/100a, 1999. Comments: Quantitative Risk Assessment Report Page 56 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 ASSUMPTION SHEET Project: ENGINEERING, PROCUREMENT & CONSTRUCTION OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP - LOT 3) Assumption No.: 010 Revision: 0 Date: 08/06/2023 Subject: Risk Tolerability Criteria Assumption: Individual Risk Calculations The risk results will be presented as individual risk. The UK Institution of Chemical Engineers (1992) defines risk as ‘the frequency at which an individual may be expected to sustain a level of harm from the realization of specified hazards’. It is usually taken to be the risk of death and expressed as a risk per year. The most common example of individual risk is the iso-risk contour. This allows for major hazard areas to be easily identified and the effects on specific vulnerable locations to be more easily observed. A determination of individual risks to the public, and to employees, forms the basis for risk-decision making. It provides an overall assessment of the level of risk to the exposed population and highlights the major contributors to the risk. Individual risk assessment combines the results of the consequence modelling, with a detailed assessment of frequencies, utilizing failure frequency data. The following risk criteria are used by the NNPC to assess the individual risk exposed to employees, contractors as well as public people: • Maximum tolerable risk for workers 1E-03 per year • Maximum tolerable risk for the public 1E-04 per year • Broadly acceptable risk 1E-06 per year In between the maximum tolerable and broadly acceptable levels, NNPC requires that risk be reduced to a level which is As Low As Reasonably Practicable (ALARP), taking account of the costs and benefits of any further risk reduction. Near to the broadly acceptable criterion, the risks are considered tolerable if the cost of risk reduction exceeds the improvement gained. Near to the maximum tolerable criterion, the risks are only considered tolerable if risk reduction is impracticable or if its cost is grossly disproportionate to the improvement gained. Societal Risk Calculations (F-N Curve) A determination of societal risks to the public and to employees provides important input to risk- decision making. It provides an assessment of the magnitude of risk associated with major events, in terms of impact to large numbers of people. Major contributors to the societal risks are also identified. Societal risk can be represented Quantitative Risk Assessment Report Page 57 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 ASSUMPTION SHEET Project: ENGINEERING, PROCUREMENT & CONSTRUCTION OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP - LOT 3) Assumption No.: 010 Revision: 0 Date: 08/06/2023 Subject: Risk Tolerability Criteria • graphically, in the form of FN curves • numerically, in the form of a risk integral FN Curves Societal risk can be represented by FN curves, which are plots of the cumulative frequency (F) of various accident scenarios against the number (N) of casualties associated with the modelled incidents. The plot is cumulative in the sense that, for each frequency, N is the number of casualties that could be equaled or exceeded. Often ‘casualties’ are defined in a risk assessment as fatal injuries, in which case N is the number of people that could be killed by the incidents. ‘Criterion lines’ on FN plots have been suggested as a means to define risk zones/ categories. Risk Integrals The potential loss of life (PLL) is the average number of fatalities per year. HSE does not have the criteria for PLL of onsite population. PLL will only be presented to discuss the relative ranking of hazards and the key risk contributors. d All the native files used for the QRA exercise will be made available to the client upon request. Justification: Risk acceptance criteria are used to evaluate whether the risk to people is unacceptable or within tolerable limits. References: Comments: Quantitative Risk Assessment Report Page 58 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 ASSUMPTION SHEET Project: ENGINEERING, PROCUREMENT & CONSTRUCTION OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP - LOT 3) Assumption No.: 011 Revision: 0 Date: 08/06/2023 Subject: Manning Level and Distribution Assumption: The EEPSP facility is predominantly unmanned, hence for the IRPA calculation the Process areas of the facility, the following onsite manning level and distribution have been considered; Work Team / Crew Shift Pattern Fraction of Hours Outdoor/in Process Area Operation 12 hours per day / per year (365 days) 6 hours per shift (0.5) Security 12 hours per day / per year (365 days) (0.5) Janitor 12 hours per day / per year (365 days) (0.5) Table 13: Manning Distribution for QRA Justification: Define manning levels and distribution for input to the QRA References: 1) IOGP, “Process Release Frequencies,” Risk Assessment Data Directory, International Association of Oil & Gas Producers, Report No. 434‐01, September 2019; Comments: Quantitative Risk Assessment Report Page 59 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) APPENDIX B: NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 PLOT PLAN Quantitative Risk Assessment Report Page 60 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 61 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) APPENDIX C: NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 ISOLATABLE SECTIONS Quantitative Risk Assessment Report Page 62 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 ISOLATABLE SECTION BOUNDARY DESCRIPTION Section Boundary Isolatable Section (IS) IS-01 From Colour Code Failure Cases (FC) No. To 4"-600 BA-31001 31 SDV-001A FC-01 4” above ground line from NPSC Facility Tie in - station inlet header FC-02 Instrument gas from Station inlet to Instrument gas Skid. FC-03 Inlet Filter separator package V-25001A FC-04 IS-02 31 SDV-001A 25 PSV-001A, 25 SDV-001A, 25 PSV001B, 25 25 SDV001B, 71 SDV-001A, 71 SDV-001B Inlet Indirect Water Bath Heater F-61001A FC-06 Inlet Indirect Water Bath Heater F-61001B FC-07 FC-09 IS-04 24" Pipeline 25 SDV-001A/001B Inlet Pressure Reduction Skid – IGS/FS Skid Inlet metering & control package 7000-PK-002 1” PRMS line – IGS /FS FC-56 6” above ground line from CNL Facility Tie in - station inlet header FC-11 FC-12 Quantitative Risk Assessment Report Inlet Pressure Reduction Skid Package FC-10 Station Inlet Closed drain header Inlet Filter separator package V-25001B FC-05 FC-08 IS-03 Section Description 1” above ground liquid outlet of the filter separators V-25001A to closed drain V-25002 1” above ground liquid outlet of the filter separators V-25001B to closed drain V-25002 Page 63 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 FC-13 FC-14 FC-15 IS-05 31 SDV-001B/ 25 PSV-002A / 25 PSV002B/ 61-BVS-002A, 71 PSV-002A, 71 PSV-001A, 71BDV003, 31PSV-002 above ground liquid outlet of the Vent Stack 7000-FS-003 to closed drain 1” liquid outlet of Pig Receiver PR-31001 to Condensate Accumulator V-25002 1/ ” 2 liquid outlet of the Instrument Supply Vessel to Condensate Accumulator V-25002 FC-16 1” 7.5MMSCFD Station inlet line – 4” Inlet Isolation Vent header. FC-18 2” 7.5 MMSCFD Filter separator package V-25002A Pressure Relief line to 4” Filter Separator Vent header FC-19 2” 10 MMSCFD Filter separator package V-25002A Pressure Relief line to 4” Filter Separator Vent header FC-20 2”,1”, 1” 7.5 MMSCFD Filter separator package V-25002B Pressure Relief line to 4” Filter Separator Vent header. FC-21 2”, 1”, 1” 10 MMSCFD Filter separator package V-25002B Pressure Relief line to 4” Filter Separator Vent header Vent Stack FC-22 2”, 7.5 MMSCFD Indirect Water bath heater F-61002A Pressure Relief line to 4” WBH Vent header. FC-23 2” 10 MMSCFD Indirect Water bath heater F-61002B Pressure Relief line to 4” WBH Vent header. FC-24 Quantitative Risk Assessment Report 1/ ” 2 1” 7.5 MMSCFD Indirect Water bath heater F-61002A Pressure Relief line to 4” WBH Vent header. Page 64 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 FC-25 1” 10MMSCFD Indirect Water bath heater F-61002B Pressure Relief line to 4” WBH Vent header header FC-26 3” 7.5MMSCFD PRMS Relief line to 4” PRMS Vent header FC-27 3” 10MMSCFD PRMS Relief line to 4” PRMS Vent header FC-28 FC-29 31 SDV-001B IS-07 25 PSV-002A , Filter Separator V-25002A FC-30 1”7.5MMSCFD Gas Metering System Relief line to 2” Gas Metering Vent header. FC-31 1”10MMSCFD Gas Metering System Relief line to 2” Gas Metering Vent header. FC-32 4” Pig Launcher Relief line to 4” Pig System Vent header FC-33 4” Pig Receiver Relief line to 4” Pig System Vent header FC-34 4” Pipeline Vent header, 4” Metring Skid 1&2 Vent header, 4” PRMS Skid 1&2 Vent header, 4” Indirect WBH 1&2 vent header, Inlet Isolation vent header, 4” Pigging System Vent header to 8” Cold Vent Header FC-35 FC-35 4” Inlet piping to Inlet Filter separator V-25002A FC-36 FC-37 Filter Separator V25002A Quantitative Risk Assessment Report WBH F-61002A 2” 7.5 MMSCFD PRMS Blowdown line to 4” PRMS Vent header. 2” 10 MMSCFD PRMS Blowdown line to 4” PRMS Vent header. FC-38 1” Filter separator Relief to 4” Filter separator V-25002A Vent header 1” Filter separator Relief to 4” Filter separator V-25002A Vent header 4” Filter separator V-25002B outlet line to inlet header WBH F-61002B Page 65 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) WBH F-61002A 31 SDV-001B 25 SDV-002A 25 PSV-002A , Filter Separator V-25002B Revision No: R01 FC-39 1” ” Filter separator V-25002B liquid outlet line to Condensate accumulator FC-40 4” Filter separator V-25002A and 4” Filter separator V-25002B outlet to 4” WBH F-61002A inlet line. FC-41 FC-42 Filter Separator V25002A WBH F-61002A 25 SDV-001A IS-08 IS-09 31 PSV-002 31 SDV-002 Quantitative Risk Assessment Report 4” WBH F-61002A outlet line to 4” WBH F-61002A Warm gas header 1” WBH F-61002A outlet By-pass line to 4” WBH F-61002A Cold vent header. WBH F-61002B FC-43 1” BDV line via 4” Filter separator V-25002A and 4” Filter separator V-25002B outlet to 4” WBH F-61002A Cold vent header. 25 SDV-002B FC-44 4” WBH F-61002A outlet line via 4” WBH F-61002B cold gas header to 4” WBH F-61002B inlet line. FC-45 4” WBH F-61002B Outlet line via 4” WBH F-61002B Warm gas header to PRMS. FC-46 1” WBH F-61002B outlet By-pass line to 4” WBH F-61002B Cold vent header. FC-47 4” WBH F-61002B Warm gas header to 4” PRMS Header. FC-48 4” PRMS Header via 2” line via to IGP/FS Skid FC-49 6” Tie-in line to Pig launcher FC-50 6” Pig Launcher line to 4” Facility Inlet line FC - 51 1” Pig Receiver Relief line to 4” Pig Receiver Cold Vent Header. FC - 52 2” Pig Receiver Kicker line to 4” Facility Inlet line 61-BDV-002A, WBH F-61002A, 71-SDV001B, 71-SDV-002B 31 SDV-002 31 PSV-003 Page 66 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 FC - 53 IS-10 IS-11 71 SDV-001B 28 SDV-001B 28 SDV-001B EEPSP Power Plant FC – 54 8” 10MMSCFD PRMS line to 8” Gas Metering System FC - 55 8” 10MMSCFD Gas Metering System header to 8” 10MMSCFD Gas Metering System outlet line via 8” header. FC - 56 FC- 57 IS-12 71 SDV-001A Quantitative Risk Assessment Report 28 SDV-001A 4” 10MMSCFD PRMS line to 8” 10MMSCFD PRMS header line 8” 10MMSCFD Gas Metering System outlet – EEPSP Power plant 4” 7.5 MMSCFD PRMS line to 8” 10MMSCFD PRMS header line FC- 58 8” 7.5 MMSCFD PRMS line to 8” Gas Metering System FC - 59 8” 7.5 MMSCFD Gas Metering System header to 8” 7.5 MMSCFD Gas Metering System outlet line via 8” header. Page 67 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) APPENDIX D: NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 MARKED DRAWINGS OF ISOLATABLE SECTIONS Quantitative Risk Assessment Report Page 68 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 69 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 70 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 71 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 72 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 73 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 74 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 75 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 76 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 77 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 78 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 79 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 80 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 81 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 82 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 83 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 84 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 85 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 86 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 87 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) APPENDIX E: NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 EVENT TREE Quantitative Risk Assessment Report Page 88 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 89 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 90 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 91 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 92 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 93 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Quantitative Risk Assessment Report NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 Page 94 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) APPENDIX F: NGIC-EEPSP_YNL-TSF-RPT-007 Revision No: R01 CONSEQUENCE MODELLING RESULTS Quantitative Risk Assessment Report Page 95 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 Release Inventory Calculation Isolatable Section (IS) IS-01 IS-02 IS-03 IS-04 Colour Code Release Hole size Scenario Name Weather Category 5D Jet Fire Initial Release at time = 5 mins Dispersion Initial Release after 5mins Vapour Cloud Explosion (VCE) Flame Length Downwind Radiation Distances [m] Downwind Distances [m] Maximum Distance to Overpressures [m] 4KW/m2 12.5 KW/m2 37.5 KW/m2 UFL LFL 50% LFL 0.02 bar 5.41 6.01 n/a n/a n/a 2.50 4.40 0.20 bar n/a 0.13 bar n/a Small 7mm leak - Small IS-01-S-7mm Medium 22mm leak - Medium IS-01-M-22mm 14.72 21.38 17.58 15.39 2.38 7.31 15.05 30.09 13.90 0.21 Large 70mm - Large IS-01-L-70mm 35.20 61.12 46.71 39.02 6.24 24.29 63.55 119.71 71.60 68.70 Full Bore 150mm - Rupture 47.43 85.25 63.88 52.11 9.32 41.60 110.29 205.42 128.55 123.91 Small 7mm leak - Small IS-01-FB150mm IS-02-S-7mm 5.13 5.93 5.36 4.52 1.02 2.39 4.22 n/a n/a n/a Medium 22mm leak - Medium IS-02-M-22mm 10.02 13.34 11.30 9.96 1.65 4.96 8.52 67.20 37.23 35.42 Large 70mm - Large IS-02-L-70mm 48.11 86.73 64.91 52.88 7.94 30.98 49.60 106.44 48.45 46.34 Full Bore 150mm - Rupture IS-02-FB150mm 48.11 86.73 64.91 52.88 7.94 30.98 49.60 106.44 48.45 46.34 Small 7mm leak - Small IS-03-S-7mm Medium 22mm leak - Medium IS-03-M-22mm Large 70mm - Large IS-03-L-70mm Full Bore 150mm - Rupture IS-03-FB150mm Small 7mm leak - Small IS-04-S-7mm Medium 22mm leak - Medium Large Full Bore IS-05 IS-06 Possibility 5D 5D IS-03 to be considered as Pipeline section 2 5D 5.99 7.17 6.35 5.57 1.11 2.93 5.03 n/a n/a n/a IS-04-M-22mm 9.86 18.91 14.31 12.02 2.09 6.04 10.87 26.56 13.22 12.41 70mm - Large IS-04-L-70mm 28.90 57.38 42.43 34.76 5.21 17.69 33.43 64.65 30.26 30.19 150mm - Rupture IS-04-FB150mm 74.15 154.43 112.46 90.49 7.40 27.27 43.95 90.12 41.68 41.17 Small 7mm leak - Small Medium 22mm leak - Medium Large 70mm - Large Full Bore 150mm - Rupture 8.51 10.88 9.42 8.33 1.41 4.15 7.19 n/a n/a n/a IS-04-M-22mm 21.76 34.39 27.30 23.41 3.70 11.73 29.06 51.15 26.05 24.54 IS-04-L-70mm 28.02 55.55 41.11 33.71 6.57 25.12 66.78 120.97 71.85 68.88 IS-04-FB150mm 53.83 109.78 80.49 65.17 14.75 68.64 132.05 235.80 123.39 121.73 IS-04-S-7mm 5D Utility Line (No HC Hazard present) Utility Line (No HC Hazard present) IS-07 Small 7mm leak - Small Medium 22mm leak - Medium Large 70mm - Large Full Bore 150mm - Rupture Quantitative Risk Assessment Report n/a 8.29 10.55 9.14 8.22 1.38 4.05 6.99 n/a n/a n/a IS-07-M-22mm 18.09 27.36 22.06 18.95 3.09 9.26 21.43 45.22 24.90 23.68 IS-07-L-70mm 27.56 54.61 40.42 33.15 6.47 24.53 65.27 119.60 71.58 68.68 IS-07-FB150mm 54.16 110.47 81.00 65.58 14.92 58.77 88.95 185.26 90.87 88.15 IS-07-S-7mm 5D Page 96 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Revision No: R01 Release Inventory Calculation Isolatable Section (IS) Colour Code Release Hole size IS-08 Possibility Scenario Name 5D Jet Fire Initial Release at time = 5 mins Dispersion Initial Release after 5mins Vapour Cloud Explosion (VCE) Flame Length Downwind Radiation Distances [m] Downwind Distances [m] Maximum Distance to Overpressures [m] 4KW/m2 12.5 KW/m2 37.5 KW/m2 UFL 6.47 7.86 6.92 6.23 1.17 LFL 50% LFL 0.02 bar 0.13 bar 0.20 bar 3.16 5.44 n/a n/a n/a Small 7mm leak - Small Medium 22mm leak - Medium IS-08-M-22mm 9.86 18.90 14.31 12.01 2.09 6.04 10.87 26.55 13.22 12.41 Large 70mm - Large IS-08-L-70mm 28.26 56.05 41.47 34.00 5.92 21.05 37.69 71.73 35.31 33.98 Full Bore 150mm - Rupture IS-08-FB150mm 73.72 153.46 111.76 89.95 8.57 31.95 49.69 107.93 49.44 47.08 Small 7mm leak - Small IS-09-S-7mm 5.75 6.85 6.07 5.09 1.08 2.81 4.84 n/a n/a n/a Medium 22mm leak - Medium IS-09-M-22mm 9.87 18.91 14.31 12.02 2.10 6.05 10.87 26.56 13.22 12.41 Large 70mm - Large IS-09-L-70mm 29.28 58.17 43.00 35.21 4.95 16.40 31.75 61.64 28.09 26.07 Full Bore 150mm - Rupture 74.15 154.43 112.45 90.49 6.90 25.15 41.42 79.41 39.46 37.09 Small 7mm leak - Small IS-09-FB150mm IS-10-S-7mm 8.22 10.44 9.06 8.15 1.38 4.01 6.93 n/a n/a n/a Medium 22mm leak - Medium IS-10-M-22mm 17.20 25.71 20.81 17.85 2.94 8.73 19.67 33.87 14.64 13.48 Large 70mm - Large IS-10-L-70mm 27.56 54.62 40.42 33.16 6.47 24.54 64.83 113.12 70.32 67.74 Full Bore 150mm - Rupture IS-10-FB150mm 54.39 110.97 81.36 65.86 15.01 55.76 82.53 179.96 86.36 82.27 Small 7mm leak - Small IS-11-S-7mm 1.75 1.78 0.83 n/a 0.41 0.81 1.43 n/a n/a n/a Medium 22mm leak - Medium IS-11-M-22mm 5.01 5.84 5.03 2.22 0.78 2.37 3.97 n/a n/a n/a Large 70mm - Large IS-11-L-70mm 16.58 23.57 19.34 16.58 1.11 3.13 5.10 n/a n/a n/a Full Bore 150mm - Rupture IS-11-FB150mm 31.31 51.84 40.19 33.76 1.18 3.36 5.42 n/a n/a n/a Small 7mm leak - Small IS-11-S-7mm 1.75 1.78 0.83 n/a 0.41 0.82 1.43 n/a n/a n/a Medium 22mm leak - Medium IS-11-M-22mm 5.02 5.86 5.04 2.26 0.68 2.03 3.43 n/a n/a n/a Large 70mm - Large IS-11-L-70mm 17.71 25.37 20.79 17.77 0.82 2.45 4.01 n/a n/a n/a Full Bore 150mm - Rupture IS-11-FB150mm 31.31 51.84 40.19 33.76 0.82 2.45 4.01 n/a n/a n/a IS-09 IS-10 IS-11 IS-12 Quantitative Risk Assessment Report IS-08-S-7mm Weather Category 5D 5D 5D 5D Page 97 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Equipment Description Equipment Release size and Credibility Revision No: R01 Possible outcome Scenario Name Weather Category Jet Fire Initial Release at time = 5 mins Flame Length Filter Separator V-25001A V-25001B Water Bath Heater F-61001A F-61001B Filter Separator V-25002A V-25002B Water Bath Heater F-61002A F-61002B Pressure Reduction Skid Gas Metering Skid Condensate Accumulator Pipeline type V-25002 Small 7mm leak - Small Medium Large 22mm leak Medium 70mm - large Full-bore 150mm -Rupture V-FB-150mm Small 7mm leak - Small WBH-S-7mm Medium Large 22mm leak Medium 70mm - large Full-bore 5D V-S-7mm - V-M-22mm V-L-70mm 5D Dispersion Initial Release after 5mins Vapour Cloud Explosion Downwind Distance [m] Maximum Distance to Overpressure [m] Downwind Radiation Distance [m] 4KW/m2 12.5KW/m2 37.5W/m2 UFL LFL 50%LFL 0.02 bar 0.13 bar 0.20 bar 5.18 5.99 5.41 4.62 0.95 2.41 4.25 n/a n/a n/a 10.52 14.16 11.95 10.49 1.73 5.21 9.07 n/a n/a n/a 24.69 39.39 30.96 26.03 4.38 14.30 37.46 n/a n/a n/a 47.93 86.34 64.64 52.67 8.65 33.83 53.10 n/a n/a n/a 4.84 5.54 5.02 3.90 0.91 2.25 3.97 n/a n/a n/a WBH-M-22mm 9.74 12.89 10.94 9.66 1.61 4.82 8.24 n/a n/a n/a WBH-L-70mm 23.67 37.37 29.48 24.80 4.20 13.39 34.95 65.21 36.84 35.13 150mm -Rupture WBH-FB-150mm 45.94 82.08 61.62 50.29 7.86 30.50 48.86 104.68 47.46 45.59 Small 7mm leak - Small V-S-7mm 8.12 10.29 8.93 8.04 1.36 3.96 6.84 n/a n/a n/a Medium V-M-22mm 16.09 23.68 19.27 16.37 2.75 8.11 17.54 32.25 14.32 13.24 Large 22mm leak Medium 70mm - large V-L-70mm 27.57 54.64 40.44 33.17 6.47 24.55 63.30 109.67 61.60 58.69 Full-bore 150mm -Rupture V-FB-150mm 54.72 111.67 81.86 66.27 14.94 51.98 75.55 166.46 83.61 80.20 Small 7mm leak - Small WBH-S-7mm 7.79 9.73 8.52 5.04 1.32 3.73 6.51 n/a n/a n/a Medium WBH-M-22mm 14.79 21.42 17.57 13.98 2.49 7.39 15.17 30.30 13.94 12.96 Large 22mm leak Medium 70mm - large WBH-L-70mm 33.28 56.37 43.32 36.09 6.14 23.06 58.85 106.53 60.99 58.24 Full-bore 150mm -Rupture WBH-FB-150mm 63.55 121.56 88.90 71.05 12.83 47.34 70.10 156.15 73.85 70.38 Small 7mm leak - Small PRS-S-7mm Medium 22mm leak Medium Large 70mm - large PRS-L-70mm Full-bore 150mm -Rupture PRS-FB-150mm Small 7mm leak - Small GM-S-7mm Medium 22mm leak Medium Large 70mm - large GM-L-70mm Full-bore 150mm -Rupture GM-FB-150mm Small 7mm leak - Small CA-S-7mm Medium Large 22mm leak Medium 70mm - large Full-bore 150mm -Rupture Release size and Credibility Possible outcome Quantitative Risk Assessment Report - - - - - - 5D 5D 5D PRS-M-22mm On Hold pending availability of Vendor Information 5D GM-M-22mm On Hold pending availability of Vendor Information 5D 1.10 1.77 1.08 0.81 n/a n/a n/a n/a n/a n/a CA-M-22mm 2.97 4.99 2.83 1.46 n/a 0.19 0.29 n/a n/a n/a CA-M-70mm 12.04 15.70 13.78 12.99 n/a n/a 27.56 63.85 36.58 34.93 CA-FB-150mm 21.12 30.64 25.54 22.99 n/a 26.38 39.72 80.47 45.87 44.40 Page 98 of 99 NNPC GAS INFRASTRUCTURE COMPANY LIMITED NGIC-EEPSP_YNL-TSF-RPT-007 EPC OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT (EEPSP–LOT 3) Equipment Description Equipment Release size and Credibility Revision No: R01 Possible outcome Scenario Name Weather Category Jet Fire Initial Release at time = 5 mins Flame Length 2Km Pipeline 8 Km Pipeline Dispersion Initial Release after 5mins Vapour Cloud Explosion Downwind Distance [m] Maximum Distance to Overpressure [m] Downwind Radiation Distance [m] 4KW/m2 12.5KW/m2 37.5W/m2 UFL LFL 50%LFL 0.02 bar 0.13 bar 0.20 bar 5.41 6.30 5.68 3.65 1.54 7.47 21.36 32.77 22.48 21.86 14.93 21.77 17.88 15.65 4.80 23.34 65.24 99.87 67.75 65.81 Small 7mm leak - Small Medium 22mm leak Medium Large 70mm - large 29.74 50.98 39.13 32.40 7.00 18.00 42.78 86.21 48.98 46.73 Full-bore 100mm -Rupture 30.41 51.69 39.93 33.70 10.21 50.59 119.94 196.43 126.80 122.60 Small 7mm leak - Small 5.42 6.31 5.69 5.05 1.05 2.52 4.45 n/a n/a n/a Medium 22mm leak Medium 14.97 21.84 17.93 15.70 2.42 7.44 15.47 30.44 13.97 12.98 Large 70mm - large 45.37 83.68 62.75 51.94 7.95 34.34 88.55 162.47 96.03 92.02 Full-bore 150mm -Rupture 57.79 110.31 81.47 66.51 10.65 49.23 123.85 233.84 142.13 136.59 Quantitative Risk Assessment Report 5D - 5D Page 99 of 99