Uploaded by Christine Eugenio

07-costacctng

advertisement
lOMoARcPSD|13494386
07 - CostAcctng
Cost Accounting And Cost Management (Far Eastern University)
Studocu is not sponsored or endorsed by any college or university
Downloaded by Christine Eugenio (darkchristine22@gmail.com)
lOMoARcPSD|13494386
Chapter 7
THE COST OF QUALITY AND
ACCOUNTING FOR PRODUCTION LOSSES
MULTIPLE CHOICE
Question Nos. 16, 17, 22, and 23 are AICPA adapted.
Question No. 24 is CIA adapted.
A
1.
The quality costs that are associated with materials and products that fail to meet quality
standards and result in manufacturing losses are known as:
A.
internal failure costs
B.
external failure costs
C.
prevention costs
D.
appraisal costs
E.
none of the above
D
2.
The quality costs that are associated with designing, implementing, and maintaining the quality
system are known as:
A.
appraisal costs
B.
internal failure costs
C.
external failure costs
D.
prevention costs
E.
none of the above
C
3.
The quality costs that are incurred to ensure that materials and products meet quality standards
are known as:
A.
external failure costs
B.
prevention costs
C.
appraisal costs
D.
internal failure costs
E.
none of the above
B
4.
The quality costs that are incurred because inferior quality products are shipped to customers
are known as:
A.
internal failure costs
B.
external failure costs
C.
prevention costs
D.
appraisal costs
E.
none of the above
82
Downloaded by Christine Eugenio (darkchristine22@gmail.com)
lOMoARcPSD|13494386
The Cost of Quality and Accounting for Production Losses
83
D
5.
All of the following are characteristics of total quality management except:
A.
the company's objective for all business activity is to serve its customers
B.
top management provides an active leadership role in quality improvement
C.
all employees are actively involved in quality improvement
D.
the company maintains a loosely defined system of identifying quality problems so as not
to stifle employee creativity
E.
the company provides continuous training as well as recognition for achievement
A
6.
The best approach to quality improvement is to concentrate on:
A.
prevention
B.
detection
C.
appraisal
D.
increased production
E.
none of the above
C
7.
A mathematical technique used to monitor production quality and reduce product variability is:
A.
the method of least squares
B.
the statistical scattergraph method
C.
statistical process control
D.
linear programming
E.
none of the above
D
8.
Appraisal costs include all of the following except:
A.
inspecting and testing materials
B.
inspecting products during and after production
C.
obtaining information from customers about product satisfaction
D.
designing quality into the product and the production process
E.
all of the above
B
9.
Internal failure costs include all of the following except:
A.
the cost of the scrap
B.
the cost of warranty repairs and replacements
C.
rework
D.
downtime due to machine failures
E.
all of the above
E
10.
All of the following accounts would be acceptable ones to credit at the time scrap is sold except:
A.
Scrap Sales
B.
Cost of Goods Sold
C.
Factory Overhead Control
D.
Work in Process
E.
all of the above would be acceptable
C
11.
Scrap includes all of the following except:
A.
the trimmings remaining after processing materials
B.
defective materials that cannot be used or returned to the vendor
C.
partially or fully completed units that are in some way defective
D.
broken parts resulting from employee or machine failures
E.
all of the above
Downloaded by Christine Eugenio (darkchristine22@gmail.com)
lOMoARcPSD|13494386
84
Chapter 7
A
12.
When spoilage occurs because of some action taken by the customer, the unrecoverable cost of
the spoilage should be charged to:
A.
Work in Process
B.
Spoiled Goods Inventory
C.
Factory Overhead Control
D.
Applied Factory Overhead
E.
none of the above
C
13.
When spoilage occurs because of some internal failure, the unrecoverable cost should be charged
to:
A.
Work in Process
B.
Spoiled Goods Inventory
C.
Factory Overhead Control
D.
Applied Factory Overhead
E.
none of the above
A
14.
When rework occurs because of some action taken by the customer, the cost of the rework
should be charged to:
A.
Work in Process
B.
Spoiled Goods Inventory
C.
Factory Overhead Control
D.
Applied Factory Overhead
E.
none of the above
C
15.
When rework occurs because of some internal failure, the cost of the rework should be charged
to:
A.
Work in Process
B.
Spoiled Goods Inventory
C.
Factory Overhead Control
D.
Applied Factory Overhead
E.
none of the above
C
16.
Newman Company's Job 1865 for the manufacture of 2,200 coats was completed during August
at the unit costs presented below. Due to an internal failure in the production process, 200
coats were found to be spoiled during final inspection that were sold to a jobber for $6,000.
Direct materials ...............................................................................................................
Direct labor ......................................................................................................................
Factory overhead ............................................................................................................
...............................................................................................................................
What would be the unit cost of good coats produced on Job 1865?
A.
$57.00
B.
$55.00
C.
$56.00
D.
$58.00
E.
none of the above
SUPPORTING CALCULATION:
$20 + $18 + $18 = $56
Downloaded by Christine Eugenio (darkchristine22@gmail.com)
$20
18
18
$56
lOMoARcPSD|13494386
The Cost of Quality and Accounting for Production Losses
A
17.
85
During March, Vaughan Company incurred the following costs on Job 009 for the manufacture
of 200 motors:
Original cost accumulation:
Direct materials ........................................................................................................
Direct labor ...............................................................................................................
Factory overhead (150% of direct labor) ...............................................................
Direct costs of reworking 10 units:
Direct materials ........................................................................................................
Direct labor ...............................................................................................................
....................................................................................................................................
$
660
800
1,200
$ 2,660
$100
160
$260
The rework costs were attributable to the exacting specifications of the customer. What is the
cost per finished unit of Job 009?
A.
$15.80
B.
$14.60
C.
$14.00
D.
$13.30
E.
none of the above
SUPPORTING CALCULATION:
$2,660 + $260 + (150% x $160) = $3,160  200 = $15.80
C
18.
Spoilage occurs as a result of an internal failure in a process cost system. Using average costing,
the number of equivalent units that production costs should be charged to would be based upon:
A.
spoiled units
B.
units transferred out and spoiled units
C.
units transferred out, spoiled units, and units in ending inventory
D.
units transferred out and units in ending inventory
E.
none of the above
D
19.
Spoilage occurs as a result of normal production shrinkage in a process cost system. Using
average costing, the number of equivalent units that production costs should be charged to
would be based upon:
A.
spoiled units
B.
units transferred out and spoiled units
C.
units transferred out, spoiled units, and units in ending inventory
D.
units transferred out and units in ending inventory
E.
none of the above
C
20.
In a process cost system, the cost of spoilage due to an internal production failure should be
recorded as:
A.
dr. Work in Process; cr. Finished Goods
B.
dr. Work in Process; cr. Factory Overhead Control
C.
dr. Factory Overhead Control; cr. Work in Process
D.
dr. Materials; cr. Factory Overhead
E.
dr. Finished Goods; cr. Work in Process
Downloaded by Christine Eugenio (darkchristine22@gmail.com)
lOMoARcPSD|13494386
86
B
Chapter 7
21.
Gyro Products transferred 10,000 units to one department. An additional 3,000 units of
materials were added in the department. At the end of the month, 7,000 units were transferred
to finished goods; while 4,000 units remained in work in process inventory. There was no
beginning inventory, and lost units were a result of normal production shrinkage. The
production costs for the period in this department would be effectively allocated over:
A.
12,000 units
B.
11,000 units
C.
10,000 units
D.
7,000 units
E.
13,000 units
SUPPORTING CALCULATION:
7,000 + 4,000 = 11,000
B
22.
In manufacturing its products for the month of March, Leo Co. incurred normal production
shrinkage of $10,000 and spoilage due to internal failure of $12,000. How much spoilage cost
should Leo charge to Factory Overhead Control for the month of March?
A.
$22,000
B.
$12,000
C.
$10,000
D.
$0
E.
none of the above
C
23.
Willis, Inc. instituted a new process in October. During October, 10,000 units were started in
Department A. Of the units started, 1,000 were lost in the process due to normal production
shrinkage, 7,000 were transferred to Department B, and 2,000 remained in work in process at
October 31. The work in process at October 31 was 100% complete as to materials costs and
50% complete as to conversion costs. Materials costs of $27,000 and conversion costs of
$40,000 were charged to Department A in October. What were the total costs transferred to
Department B?
A.
$46,900
B.
$53,600
C.
$56,000
D.
$57,120
E.
none of the above
SUPPORTING CALCULATION:
Materials: $27,000  (7,000 + 2,000) = $3
Conversion: $40,000  (7,000 + 1,000) = $5
Transferred costs: 7,000 x $8 = $56,000
Downloaded by Christine Eugenio (darkchristine22@gmail.com)
lOMoARcPSD|13494386
The Cost of Quality and Accounting for Production Losses
D
24.
87
A company that manufactures baseballs begins operations on January 1. Each baseball
requires three elements: a hard plastic core, several yards of twine that are wrapped around the
plastic core, and a piece of leather to cover the baseball. The plastic core is started down a
conveyor belt and is automatically wrapped with the twine to the approximate size of the
baseball, at which time the leather cover is sewn to the wrapped twine. Finished baseballs are
inspected, and the ones that are defective due to internal production failure are pulled out.
Defective baseballs cannot be economically salvaged and are destroyed. Cost and production
reports for the first week of operations are:
Raw material cost ..............................................................................................................
Conversion cost .................................................................................................................
315
.................................................................................................................................
$
840
$ 1,155
During the week, 2,100 baseballs were completed; 2,000 passed inspection. There was no
ending work in process. The cost of the spoilage charged to Factory Overhead is:
A.
$33
B.
$22
C.
$1,100
D.
$55
E.
none of the above
SUPPORTING CALCULATION:
Materials: $840  (2,000 + 100) = $.40
Conversion: $315  (2,000 + 100) = $.15
Spoilage: 100 x $.55 = $55
A
25.
In a process cost system, the cost of rework usually is debited to:
A.
Factory Overhead Control
B.
Applied Factory Overhead
C.
Spoiled Goods Inventory
D.
Work in Process
E.
none of the above
The following questions are based on the Appendix to the chapter:
D
26.
If spoilage occurs as a result of an internal failure in a process cost system, using fifo costing, the
number of equivalent units that production costs should be charged to would be based upon:
A.
spoiled units
B.
units transferred out and spoiled units
C.
units transferred out, beginning inventory, and units in ending inventory
D.
units transferred out, spoiled units, units in ending inventory, and units in beginning
inventory
E.
none of the above
Downloaded by Christine Eugenio (darkchristine22@gmail.com)
lOMoARcPSD|13494386
88
Chapter 7
C
27.
If spoilage occurs as a result of normal production shrinkage in a process cost system, using fifo
costing, the number of equivalent units that production costs should be charged to would be
based on:
A.
spoiled units
B.
units transferred out and spoiled units
C.
units transferred out, beginning inventory, and units in ending inventory
D.
units transferred out, spoiled units, units in ending inventory, and units in beginning
inventory
E.
none of the above
B
28.
Primo Products transferred 15,000 units to one department. An additional 5,000 units were in
beginning inventory in the department. At the end of the month, 12,000 units were transferred
to the next department, 6,000 units remained in work in process, 40% complete as to conversion
costs and the remaining units were lost at the 75% stage of conversion. Beginning inventory
was 60% complete as to conversion costs and lost units were the result of internal failure. The
equivalent units of conversion cost using fifo costing is:
A.
14,400
B.
12,900
C.
13,900
D.
13,400
E.
none of the above
SUPPORTING CALCULATION:
Equivalent units in beginning inventory (40% x 5,000) ...............................................
Equivalent units started and completed during period
(12,000 - 5,000) ........................................................................................................
Equivalent units in ending inventory (40% x 6,000) ....................................................
Equivalent units of spoilage (75% x 2,000) ...................................................................
Total equivalent units .....................................................................................................
A
29.
2,000
7,000
2,400
1,500
12,900
Primo Products transferred 15,000 units to one department. An additional 5,000 units were
added in the department. At the end of the month, 12,000 units were transferred to the next
department, 6,000 units remained in work in process, 40% complete as to conversion costs and
the remaining units were lost at the 75% stage of conversion. Beginning inventory was 60%
complete as to conversion costs, and lost units were the result of normal production shrinkage.
The equivalent units of conversion cost using fifo is:
A.
11,400
B.
14,400
C.
12,900
D.
13,400
E.
none of the above
SUPPORTING CALCULATION:
Equivalent units in beginning inventory (40% x 5,000) ...............................................
Equivalent units started and completed during period
(12,000 - 5,000) ........................................................................................................
Equivalent units in ending inventory (40% x 6,000) ....................................................
Total equivalent units .....................................................................................................
Downloaded by Christine Eugenio (darkchristine22@gmail.com)
2,000
7,000
2,400
11,400
lOMoARcPSD|13494386
The Cost of Quality and Accounting for Production Losses
89
PROBLEMS
PROBLEM
1.
Journal Entries for Scrap. Munoz Metal Products accumulates metal shavings from the shop floor and sells
them periodically to a nearby scrap dealer. Scrap sales, on account, for the period just ended total $2,300.
Required:
Indicate the journal entries when:
(1)The scrap sales are viewed as additional revenue.
(2)The scrap sales are viewed as a reduction of the cost of goods sold during the period.
(3)The scrap sales are viewed as a reduction of factory overhead.
(4)The scrap sales are traceable to individual jobs and are viewed as a reduction in the cost of materials used
on the jobs.
SOLUTION
(1)
(2)
(3)
(4)
Accounts Receivable ...................................................................................
Scrap Sales (or Other Income) ..........................................................
2,300
Accounts Receivable ...................................................................................
Cost of Goods Sold..............................................................................
2,300
Accounts Receivable ...................................................................................
Factory Overhead Control.................................................................
2,300
Accounts Receivable ...................................................................................
Work in Process ..................................................................................
2,300
2,300
2,300
2,300
2,300
PROBLEM
2.
Spoilage in a Job Order Cost System. Walker Inc. manufactures custom wood products. During the
current period, an order for 2,000 workbenches was begun on Job 1994. After the job was completed, the
benches were inspected and 100 units were determined to be defective. The customer has agreed to accept
the order with only 1,900 units instead of the quantity originally ordered. The spoiled units can be sold as
seconds for $25 each. Spoiled goods are kept in a separate inventory account from finished goods. Total
costs charged to
Job 1994 follow:
Materials .....................................................................................................................................
Labor (200 hours x $15 per hour) ..................................................................................................
Factory overhead ($9.50 per labor hour) ......................................................................................
Total cost charged to Job 1994.......................................................................................................
Custom jobs are marked up 150 percent on cost.
Downloaded by Christine Eugenio (darkchristine22@gmail.com)
$
5,100
3,000
1,900
$ 10,000
lOMoARcPSD|13494386
90
Chapter 7
Required:
(1)
(2)
Assuming that the defective units were the result of an internal failure (i.e., an employee error or a
machine failure), prepare the appropriate general journal entries to record the transfer of the
defective units to a separate inventory account and the completion and shipment of Job 1994 to the
customer.
Assuming that the defective units were the result of a change in design specified by the customer after
the units were completed, prepare the appropriate general journal entries to record the transfer of
the defective units to the separate inventory account and the completion and shipment of Job 1994 to
the customer.
SOLUTION
(1)
(2)
Spoiled Goods Inventory (10 units x $25 salvage) ...................................
Factory Overhead Control ........................................................................
Work in Process (10 units x $50* cost) .............................................
250
250
Cost of Goods Sold .....................................................................................
Work in Process ($10,000 - 500) ........................................................
9,500
Accounts Receivable ($9,500 x 150%) ......................................................
Sales .....................................................................................................
14,250
Spoiled Goods Inventory (10 units x $25 salvage) ...................................
Work in Process ..................................................................................
250
Cost of Goods Sold .....................................................................................
Work in Process ($10,000 - $250) ......................................................
9,750
Accounts Receivable ($9,750 x 150%) ......................................................
Sales .....................................................................................................
14,625
* $10,000 total job cost
= $50 per unit
200 units on job
Downloaded by Christine Eugenio (darkchristine22@gmail.com)
500
9,500
14,250
250
9,750
14,625
lOMoARcPSD|13494386
The Cost of Quality and Accounting for Production Losses
91
PROBLEM
3.
Entries for Charging Rework Costs Caused by Internal Failure and by Change in Customer Specification.
Albany Appliances manufactured 100 microwave ovens in a recent production run and discovered that 10
ovens were defective and required reworking as follows:
Rework cost per unit:
Materials .........................................................................................................................................
Labor...............................................................................................................................................
Factory overhead ...........................................................................................................................
Total .........................................................................................................................................
Normal production cost per unit:
Materials .........................................................................................................................................
Labor...............................................................................................................................................
Factory overhead ...........................................................................................................................
Total .........................................................................................................................................
$
$
10
25
25
60
$
50
75
75
$ 200
Required:
(1)
(2)
Prepare the journal entries to record (a) the normal production costs, (b) the rework costs, and (c)
the transfer of the job costs to Finished Goods assuming that rework costs were caused by an internal
failure.
Prepare the same journal entries as in (1), assuming that rework costs were caused by a change in
customer specifications.
SOLUTION
(1)
(a)
(b)
(c)
(2)
Work in Process ..............................................................................
Materials ...................................................................................
Payroll .......................................................................................
Applied Factory Overhead ......................................................
Debit
20,000
5,000
7,500
7,500
Factory Overhead Control ($60 x 10)............................................
Materials ...................................................................................
Payroll .......................................................................................
Applied Factory Overhead ......................................................
600
Finished Goods ($200 x 100) ..........................................................
Work in Process .......................................................................
20,000
100
250
250
20,000
(a)
Same as first entry in (1) (a) above.
(b)
Work in Process ..............................................................................
Materials ...................................................................................
Payroll .......................................................................................
Applied Factory Overhead ......................................................
600
Finished Goods ................................................................................
Work in Process .......................................................................
20,600
(c)
Downloaded by Christine Eugenio (darkchristine22@gmail.com)
Credit
100
250
250
20,600
lOMoARcPSD|13494386
92
Chapter 7
PROBLEM
4.
Computation of Equivalent Units With Production Losses. Potter Paint Company manufactures paint in
three departments using a process cost system with an average cost flow assumption. Selected cost and
production data for the Blending Department, the second department in the production process, for the
month just ended, are as follows:
Units in beginning work in process .....................................................................................................
Units received from Mixing Department ............................................................................................
Units transferred to Finishing Department ........................................................................................
Units in ending work in process ...........................................................................................................
Units spoiled due to internal failure ....................................................................................................
Work in process, beginning inventory:
Cost from preceding department .................................................................................................
Materials .........................................................................................................................................
Labor...............................................................................................................................................
Factory overhead ...........................................................................................................................
Costs added during the period:
From preceding department .........................................................................................................
Materials .........................................................................................................................................
Labor...............................................................................................................................................
Factory overhead ...........................................................................................................................
5,000
25,000
20,000
7,000
3,000
$
4,200
1,960
895
685
$ 15,900
8,775
4,550
3,770
The paint is inspected at the end of the process in the Blending Department to detect any spoiled batches.
Ending inventory is 75% complete as to materials and 25% complete as to conversion costs.
Required:
(1)
(2)
Compute the equivalent units of production for each cost element in the Blending Department for the
month just ended.
Determine the average cost per equivalent unit for each cost element.
SOLUTION
(1)......................................................................
Equivalent units transferred out ......................
Equivalent units in ending inventory ...............
Equivalent units of spoilage ..............................
Total equivalent units ........................................
From
Preceding
Department
20,000
7,000
3,000
30,000
Materials
20,000
5,250
3,000
28,250
Downloaded by Christine Eugenio (darkchristine22@gmail.com)
Labor
20,000
1,750
3,000
24,750
Overhead
20,000
1,750
3,000
24,750
lOMoARcPSD|13494386
The Cost of Quality and Accounting for Production Losses
(2)......................................................................
Cost in beginning inventory ..............................
Cost added during the period ...........................
Total cost to be accounted for ...........................
Divide by equivalent units .................................
Cost per equivalent units ...................................
From
Preceding
Department
$
4,200
15,900
$ 20,100
30,000
$
.67
93
Materials
$
1,960
8,775
$ 10,735
28,250
$
.38
Labor
$
895
4,550
$ 5,445
24,750
$
.22
Overhead
$
685
3,770
$ 4,455
24,750
$
.18
PROBLEM
5.
Spoilage With a Salvage Value in a Process Cost System Using an Average Cost Flow Assumption. Carter
Company manufactures a single product in two departments, Cutting and Finishing. Units of a product are
started in the Cutting Department and then transferred to the Finishing Department where they are
completed. Units are inspected at the 80% stage of completion in the Finishing Department. Good units
are transferred to finished goods inventory when completed and spoiled units are transferred to a separate
inventory account. Spoiled units are inventoried at their salvage value of $3 each, and the unrecoverable cost
of spoilage, which was caused by an internal failure, should be charged to the appropriate account.
Materials are added at the beginning of the production process. At the end of June, 2,000 units were
still in process in the Finishing Department, 100% complete as to materials and 60% complete as to
conversion costs. During July, 20,000 units were transferred from the Cutting Department to the Finishing
Department and 15,000 were transferred from the Finishing Department to finished goods inventory. At the
end of July, the Finishing Department still had 4,000 units in process, 100% complete as to materials and
20% complete as to conversion costs. Cost data related to July operations in the Finishing Department
follow:
Costs charged to the department: .............................................................................
Cost from preceding department ......................................................................
Materials ..............................................................................................................
Labor....................................................................................................................
Factory overhead ................................................................................................
Beginning
Inventory
$6,050
3,410
1,638
2,184
Added
This Period
$54,450
30,690
14,742
19,656
Required:
Complete the following cost of production report for the Finishing Department based on the
data presented for July, assuming the company uses a process cost system with average costing to account for
its production.
Downloaded by Christine Eugenio (darkchristine22@gmail.com)
lOMoARcPSD|13494386
94
Chapter 7
SOLUTION
Carter Corporation
Finishing Department
Cost of Production Report
For July, 19-Quantity Schedule
Beginning inventory ...............................................
Received from Cutting Department .....................
Transferred to finished goods ...............................
Ending inventory....................................................
Spoiled in process ...................................................
Cost Charged to Department
Beginning inventory:
Cost from preceding department ...................
Materials ..........................................................
Labor. ..............................................................
Factory overhead .............................................
Total cost in beginning inventory ............
Cost added during period:
Cost from preceding department ...................
Materials ..........................................................
Labor. . .............................................................
Factory overhead .............................................
Total cost added during period ................
Total cost charged to the department...................
Materials
Labor
100%
100%
20%
80%
Total
Cost
$
$
$
$
$
Overhead
20%
80%
Equivalent
Units*
Quantity
2,000
20,000
22,000
15,000
4,000
3,000
22,000
Unit
Cost
6,050
3,410
1,638
2,184
13,282
54,450
30,690
14,742
19,656
119,538
132,820
Downloaded by Christine Eugenio (darkchristine22@gmail.com)
22,000
22,000
18,200
18,200
$2.75
1.55
.90
1.20
$6.40
lOMoARcPSD|13494386
The Cost of Quality and Accounting for Production Losses
Cost Accounted for as Follows
Transferred to
finished goods.................................
Transferred to spoiled goods
inventory at salvage value .............
Charge to factory overhead
for spoilage:
Cost from preceding
department ..............................
Materials ........................................
Labor. . ...........................................
Factory overhead ...........................
Less salvage value of
spoiled units .............................
Work in process,
ending inventory:
Cost from preceding
department ..............................
Materials ........................................
Labor. . ...........................................
Factory overhead ...........................
Total cost accounted for ......................
Units
15,000
95
%
Complete
100%
Unit
Cost
$
3,000
3,000
3,000
3,000
3,000
100%
100%
80%
80%
$
3,000
4,000
4,000
4,000
4,000
100%
100%
20%
20%
$
Total
Cost
6.40
$96,000
3.00
9,000
2.75
1.55
.90
1.20
$ 8,250
4,650
2,160
2,880
$ 17,940
3.00
9,000
2.75
1.55
.90
1.20
11,000
6,200
720
960
8,940
18,880
$132,820
* Total number of equivalent units required in the cost accounted for section determined as follows:
Equivalent units transferred out ..........................
Equivalent units in ending inventory ...................
Equivalent units of spoilage ..................................
Total equivalent units ............................................
Prior
Dept. Cost
15,000
4,000
3,000
22,000
Materials
15,000
4,000
3,000
22,000
Downloaded by Christine Eugenio (darkchristine22@gmail.com)
Labor
15,000
800
2,400
18,200
Overhead
15,000
800
2,400
18,200
lOMoARcPSD|13494386
96
Chapter 7
PROBLEM
6.
Production Shrinkage in a Process Cost System Using an Average Cost Flow Assumption. Carrera
Chemical Inc. uses a process cost system with an average cost flow assumption to account for the production
of its only product. The product is manufactured in two departments. Units of product are started in the
Cooking Department and then transferred to the Blending Department where they are completed. Because
of the intense heat applied in the Cooking Department, some of the production volume is lost to evaporation.
Labor and overhead are treated as one element of cost in the Cooking Department (i.e., conversion cost).
Data related to May operations in the Cooking Department follow:
Units in beginning inventory .................................................................................................................
Units started in process this period ......................................................................................................
Units transferred to the Blending Department this period ................................................................
Units in ending inventory (100% materials, 40% conversion cost) ...................................................
Costs charged to the department: .............................................................................
Materials ..............................................................................................................
Conversion cost ....................................................................................................
Required:
for May.
Beginning
Inventory
$4,375
2,975
Prepare a cost of production report for the Cooking Department based on the data
Downloaded by Christine Eugenio (darkchristine22@gmail.com)
10,000
45,000
40,000
9,000
Added
This Period
$11,795
6,181
presented
lOMoARcPSD|13494386
The Cost of Quality and Accounting for Production Losses
97
SOLUTION
Carrera Chemical Inc.
Cooking Department
Cost of Production Report
For May, 19--
Quantity Schedule ....................................................................
Beginning inventory .................................................................
Started in process this period ..................................................
Materials
Transferred to Blending Department.....................................
Ending inventory......................................................................
Lost in process ..........................................................................
Cost Charged to Department ..................................................
Beginning inventory:
Materials ............................................................................
Conversion cost ..................................................................
Total cost in beginning inventory ..............................
Cost added during period:
Materials ............................................................................
Conversion cost ..................................................................
Total cost added during period ..................................
Total cost charged to the department.....................................
Cost Accounted for as Follows
Transferred to Blending
Department ....................................
Work in process,
ending inventory:
Materials ........................................
Conversion cost ..............................
Total cost accounted for ......................
Units
%
Complete
100%
Total
Cost
Quantity
10,000
45,000
55,000
40,000
9,000
6,000
55,000
40%
Equivalent
Units*
$
4,375
2,975
7,350
$
11,795
6,181
17,976
25,326
$
$
Conversion
Cost
Unit
Cost
49,000
43,600
$.33
.21
$.54
Unit
Cost
Total
Cost
$21,600
40,000
100%
$.54
9,000
9,000
100%
40%
$.33
.21
$2,970
756
3,726
$25,326
* Total number of equivalent units required in the cost accounted for section determined as follows:
Equivalent units transferred out ..............................................................................
Equivalent units in ending inventory .......................................................................
Total equivalent units ................................................................................................
Downloaded by Christine Eugenio (darkchristine22@gmail.com)
Materials
40,000
9,000
49,000
Conversion
Cost
40,000
3,600
43,600
lOMoARcPSD|13494386
98
Chapter 7
This problem is based on material presented in the Appendix to the chapter.
PROBLEM
7.
Spoilage With a Salvage Value in a Process Cost System With a Fifo Cost Flow Assumption. School Craft
Petroleum Company uses a process cost system with a fifo cost flow assumption to account for production,
which is manufactured in two departments. Units of product are started in the Cracking Department and
then transferred to the Refining Department where they are completed. Units are inspected at the end of the
production process in the Refining Department. Good units are transferred to finished goods inventory and
spoiled units are transferred to a separate inventory account. Spoiled units are inventoried at their salvage
value of $8 each, and the unrecoverable cost of spoilage resulting from an internal production failure is
charged to the appropriate account. Data related to September operations in the Refining Department
follow:
Units in beginning inventory (60% materials, 30% labor, 30% overhead) ......................................
Units received from Cracking Department this period ......................................................................
Units transferred to the finished goods inventory this period ............................................................
Units transferred to special inventory account this period ................................................................
Units in ending inventory (100% materials, 50% labor, 50% overhead) .........................................
Costs charged to the department: .............................................................................
Cost from preceding department .......................................................................
Materials ..............................................................................................................
Labor ....................................................................................................................
Factory overhead .................................................................................................
Beginning
Inventory
$17,889
2,733
7,278
12,350
2,800
8,400
7,600
1,100
2,500
Added
This Period
$68,040
11,900
30,063
51,016
Required:
Prepare a cost of production report for the Refining Department based on the data presented
for September.
Downloaded by Christine Eugenio (darkchristine22@gmail.com)
lOMoARcPSD|13494386
The Cost of Quality and Accounting for Production Losses
99
SOLUTION
School Craft Petroleum Company
Refining Department
Cost of Production Report
For September, 19-Quantity Schedule
Beginning inventory ...............................................
Received from Cracking Department ..................
Transferred to finished goods ...............................
Ending inventory....................................................
Spoiled in process ...................................................
Cost Charged to Department
Beginning inventory:
Cost from preceding department ...................
Materials ..........................................................
Labor ..............................................................
Factory overhead .............................................
Total cost in beginning inventory ............
Cost added during current period:
Cost from preceding department ...................
Materials ..........................................................
Labor ..............................................................
Factory overhead .............................................
Total cost added during period ................
Total cost charged to the department...................
Materials
60%
Labor
30%
100%
100%
50%
100%
Total
Cost
$
$
$
$
$
Overhead
30%
Quantity
2,800
8,400
11,200
7,600
2,500
1,100
11,200
50%
100%
Equivalent
Units*
Unit
Cost
17,889
2,733
7,278
12,350
40,250
68,040
11,900
30,063
51,016
161,019
201,269
Downloaded by Christine Eugenio (darkchristine22@gmail.com)
8,400
9,520
9,110
9,110
$
8.10
1.25
3.30
5.60
$ 18.25
lOMoARcPSD|13494386
100
Chapter 7
Cost Accounted for as Follows
Transferred to finished goods:
From beginning inventory ..............
Cost to complete this
period:
Materials .............................
Labor ...................................
Factory overhead ................
Started and completed
this period ..................................
Total cost transferred to
Finishing Department ...............
Transferred to spoiled goods
inventory at salvage value ...............
Charged to factory overhead for
spoilage:
Cost of completed spoiled
units ............................................
Less salvage value of spoiled
units ............................................
Work in process,
ending inventory:
Cost from preceding
department ................................
Materials ..........................................
Labor. ..............................................
Factory overhead .............................
Total cost accounted for ........................
Units
%
Complete
2,800
2,800
2,800
40%
70%
70%
4,800
100%
Unit
Cost
$
1.25
3.30
5.60
Total
Cost
$
1,400
6,468
10,976
$
40,250
$
59,094
$ 18.25
87,600
$
1,100
1,100
$
100%
100%
100%
50%
50%
8,800
$ 18.25
$ 20,075
8.00
8,800
8.10
1.25
3.30
5.60
$ 20,250
3,125
4,125
7,000
1,100
2,500
2,500
2,500
2,500
8.00
$
146,694
11,275
$
34,500
201,269
* Number of equivalent units of cost added during the current period determined as follows:
To complete beginning inventory ....................
Started and completed this period ...................
Ending inventory...............................................
Spoiled units ......................................................
Total equivalent units .......................................
Prior
Dept. Cost
0
4,800
2,500
1,100
8,400
Materials
1,120
4,800
2,500
1,100
9,520
Downloaded by Christine Eugenio (darkchristine22@gmail.com)
Labor
1,960
4,800
1,250
1,100
9,110
Overhead
1,960
4,800
1,250
1,100
9,110
Download