CEng 146n Construction Methods and Project Management Project Network is a distributed model of work to be completed in a project. Such a model includes a hierarchy of interdependent work elements (processes, tasks, activities) sequenced and prioritized to identify and define the total effort of the project. PERT-CPM PERT was developed as a project schedule planning technique in the 1950s for the US Navy Special Projects Office, while CPM was developed at roughly the same time by Morgan R. Walker and James E. Kelly. Both methods are used to identify the minimum time needed to complete a project by considering all inter-dependent project activities that form the longest path or duration. PERT PROJECT EVALUATION REVIEW TECHNIQUE “Activity-on-Arrow” Three-time estimates for each activity, assuming a beta probability distribution for the time estimates. How long the activity can be delayed without extending or increasing the project completion time. SLACK=LS-ES SLACK=LF-EF STEPS/PROCEDURE 1. Construct a project network 2. Perform forward and backward passes 3. Determine the project completion time 4. Calculate the slack values 5. Determine the critical path/activities Activity (A) ES EF Time (t) LS LF ---------------------------------------------------------------MANAGEMENT AND ITS PROCESSES Project Management (Analogy) CPM CRITICAL PATH METHOD “Activity-on-Node” Does not involve probability but actual time estimate of activities in a project Critical Path Method (CPM) Actual time estimate of activities in a project. The time estimate is determined by the estimator, who is expected to be an experienced individual. The estimator would have had a long record of similar projects in the past. For each activity, there are four-time estimates: Earliest Start (ES) The earliest time it takes for an activity to begin. Earliest Finish (EF) An early start of an activity that will lead to an early finish. The assumption is that the activity begins with ES and ends with t. EF=ES+t Late Start (LS) A delay in the start of an activity. The latest time an activity can begin without delaying the project completion time. LS=LF-t Late Finish (LF) The late finish that could be allocated without extending the minimum completion time. *Slack Value Quality is meeting the needs and satisfaction of the ultimate end user of the project, the owner. Quality is the responsibility of all participants in a project, including all levels of management and workers in each of the principal parties. An attitude of achieving quality must be instilled in everyone and perpetuated throughout the work environment. The attitude should not be “What can we do to pass quality control or final inspection?” Instead, it should be “What can we do to improve our work and what is the best way we can furnish a project that meets the needs and satisfaction of the owner?” Key points in maintaining quality Project Management The art and science of coordinating people, equipment, materials, money, and schedule to complete a specified project on time and within the approved cost. Responsibilities of Teams and Project Manager Combine admin and behavioral knowledge Create a cordial environment that enables members to uplift each other Responsible for resolving disputes and establishing control Acts as the LEADER Decision-making Should develop its own leadership style The drive to achieve results must always be present. This attitude must also be instilled in everyone involved in the project. Good communication skills are a must for a manager. The management of a project requires the coordination of people and information. Coordination is achieved through effective communication. Project Management is Functional Management is concerned with concerned with What must be done When it must be done How much it will cost Coordinating overall needs Multi-discipline focus Reliance on others Project quality Administrative viewpoint A generalist’s approach How it will be done Who will do it How well it will be done Coordinating specific needs Single-discipline focus Providing technical expertise Technical quality Technical viewpoint A specialist’s approach Project Management Management vs. Functional Project Management – the process of initiating, planning, executing, controlling, and closing the work of a project to achieve a specific objective Functional management – managing the routing activities in the organization relating to various functions such as production, sales, marketing, finance, etc. in order to achieve the overall objective of the organization. ---------------------------------------------------------------PLANNING AND ITS NATURE I. Planning the process of thinking about the activities required to achieve a desired result. It is also a fundamental management function that involves deciding beforehand what is to be done, when it is to be done, how it is to be done, and who is going to do it. It is an intellectual process that lays down an organization’s objectives and develops various courses of action by which the organization can achieve those objectives. the formulation of a course of action to guide a project’s completion. It starts at the beginning of a project, with the scope of work, and continues, throughout the life of a project. A plan is the output of planning in which it provides a methodical way of achieving desired results. It also serves as a useful guide since without it, some minor tasks may be allotted with major attention which can somehow hinder the accomplishment of objectives. Determining Resources Needed Determination of resources (both human and nonhuman) that are required by a certain strategy or tactic will follow the moment that all the strategies and tactics have been devised already. This should be done to satisfy strategic requirements. Setting Standards During the planning stage, the setting of standard for measuring performance may be set. A standard is defined as a quantitative or qualitative measuring device designed to help monitor the performance of people, capital goods, or processes. II. Organizing the arrangement of resources in a systematic manner to fit the project plan. A project must be organized around the work to be performed. There must be a breakdown of the work to be performed into manageable units, which can be defined and measured. III. Staffing the selection of individuals who have the expertise to produce the work. The persons that are assigned to the project team influence every part of a project. Most managers will readily agree that people are the most important resource on a project. People provide the knowledge to design, coordinate, and construct the project. The numerous problems that arise throughout the life of a project are solved by people. IV. Directing the guidance of the work required to complete a project. The people on the project staff that provides diverse technical expertise must be developed into an effective team. Although each person provides work in his or her area of expertise, the work that is provided by each must be collectively directed in a common effort and in a common direction V. Controlling the establishment of a system to measure, report, and forecast deviations in the project scope, budget, and schedule. The purpose of project control is to determine and predict deviations in a project so corrective actions can be taken. Project control requires the continual reporting of information in a timely manner so management can respond during the project rather than afterward. Control is often the most difficult function of project management ---------------------------------------------------------------CONSTRUCTION METHODS are the techniques construction professionals use to build structures and complete projects. Classified by the materials they require, their design and their purpose, professionals separate construction methods into many types. Being able to identify some of these types helps establish your career in the construction field. The building practices professionals use when creating houses, offices, and other buildings. The construction method a team of professionals decides to use oen depends on factors such as costs, the materials available, the expertise of the construction team, and the building’s location. Are important for construction professionals, engineers, and architects to understand. This knowledge helps design structures, plan projects, and create safe working environments. It is also useful information to know when interviewing for positions related to the construction field. Precast Flat Panel When construction professionals use a precast flat panel system for a building, they create the floor and walls of the structure off-site. The project manager or the engineer who designed the building often provides a third-party factory with specific measurements for floor and wall panels. Then, the professionals transport these panels and put them together with the use of heavy machinery. This construction method is useful for buildings with a repeated design, such as stores in strip malls or office buildings. Concrete walls and floors Professionals pour and cure concrete walls and floors, also known as cement floors, on the construction site. Often, when professionals use special tools to allow the concrete walls and floors a smooth texture and finish. Concrete walls and floors offer many advantages, such as low production costs and minimal maintenance for the building owner. Professionals use this method for a variety of projects, including basements and ground floors for homes and industrial buildings. Precast concrete foundation building. Manufacturing professionals create these steel beams in factories and then ship them to the construction site. Professionals recommend this construction method for buildings that need extensive structural support, such as skyscrapers. ---------------------------------------------------------------CONSTRUCTION MANAGEMENT Context The responsibilities of construction managers (CMs) generally revolve around the paperwork documentation performed at the jobsite to support superintendents and subcontractors in the construction of a building. Professionals use precast concrete when a project requires rapid installation of the foundation for a structure. For these projects, manufacturers create all the components for the foundation in factories and transport them to the construction site. There, construction professionals piece the concrete components together to lay the foundation of the building. This is ideal for construction sites in areas of extreme weather or contaminated grounds because it requires minimal soil excavation. Timber Framing Construction manager responsibilities include: Estimating anticipated construction costs Cost control Cash flow projections and management Processing invoices from subcontractors and suppliers Processing pay requests to the project owner Managing change orders Financially closing out the construction project, a variety of other advanced financial management topics such as activity-based costing, lean construction techniques, time value of money, taxes and audits, and the developer’s pro forma. Everything that is done at the job site is connected with the operations of the construction company in the home office, and it is important that job site managers understand why they manage finances and other methods and how the management of work and finances relates to the operation of the home office department. When implementing timber framing methods, construction professionals use high-quality and heavy-duty lumber. In this method, professionals connect long beams of timber together to make a building frame. Timber framing is a historic construction method that has become a modern design trend for American homes. Heavy Steel Framing “Construction is a risky business.” - 70% of the contractors in business on the first of any year will fail within seven years. Warning signs from construction firms Inefficient financial management system; Borrowed on their credit line to the limit; Poor estimating processes and/or results; Poor project management systems and personnel; An adequate business plan is not in place; and Internal and external communication problems, among others. “An increase in volume or total revenue will solve all of their financial problems.” – FALSE Much like timber framing, heavy steel framing attaches steel beams to create the frame of a A contractor will choose to pursue construction work or feel they have the resources to do so They see a potential to make a reasonable fee The contractor already has a positive history with the client or is interested in a future relationship with the client, and/or they have a positive history with the architect or engineer or are interested in a future relationship with those firms This type of work is already a specialty of the contractor the contractor has sufficient bonding capacity which is especially important on a public bid project qualified and available employees are already on the payroll and ready to start a new project the contractor has the necessary construction equipment or immediate access to equipment the home office overhead is staffed adequately with specialists to support the project team including estimators, schedulers, and cost accountants Basic Rules The original estimate and schedule should be shared with the contractor’s field supervisor, including superintendents and foremen in order for them to plan and implement the work they need to have been given the complete picture. eighty percent of the costs and risks on a project fall within 20% of the construction activities – this is known as the Pareto 80-20 rule. The job site team should focus on the riskiest activities. Cost reporting data has to be timely and accurate. If actual cost data was not input to the accounting system accurately, then the results will be of no value to the jobsite team. Question to ponder: “Can they really ‘control’ the operations of the construction craftsmen in the field, or are they doing their best to ‘manage’ the process so that the craftsmen can achieve the estimate?” ---------------------------------------------------------------- CONSTRUCTION TYPES/INDUSTRY SECTORS Construction projects can be categorized into different sectors along the lines of type of building or how the facility is utilized. Types of Sectors: 1. Commercial Includes retail, office, schools, fire stations, churches, and others Entertainment and hospitality are subsets of commercial and include movie theaters, bowling alleys, and restaurants. 2. Residential Includes individual spec home and custom home construction Also includes apartments, condominiums, senior housing, and hotels – especially if wood-framed as they include materials and methods similar to apartments 3. Heavy Civil Projects include bridges, roads, and utility projects 4. Industrial Projects Are very specialized including power plants, utility treatment plants, refineries, and others 5. Hybrid or mixed-use developments (MXD) Include two or three different uses, such as a downtown high-rise hotel with underground parking, a restaurant, retail space, and luxury condominiums on the top floors. ---------------------------------------------------------------LIFE CYCLE OF A PROJECT 1. Initiation Determination of project’s feasibility by evaluating pros and cons Consideration of the project’s objectives for it can be an opportunity or a problem Appointment of a project manager to control the project 2. Planning Creation of the outline, time frame, and other activities of the construction plan Preparation of the budget of the project by considering the estimated costs. This includes the costs of the equipment, material, and manpower. Project has to be developed in detail to meet its objectives Identification of the resources and strategies to obtain supplies to be conducted by the project manager’s team 3. Execution/Implementation Phase of the project is practically into performance mode Heads of all the teams executing the plan will submit their progress report to the project manager so that he can make necessary adjustments 4. Controlling/Performance and Monitoring Phase Performance and progress of the entire project are measured to ensure that the project is running as per the schedule 5. Completing/Closing Finalization and the stoppage of the supplies, final touches including planting and landscaping as well as cleaning the surroundings and final inspection of the project before handing over the building to its owners CONSTRUCTION PRACTITIONERS The Project Manager The individual charged with the overall coordination of the entire construction program for the owner which includes planning, design, procurement, and construction. Among his/her duties: Clear definition of the goals of the project Investigate alternative solutions for the problem Develop a detailed plan to make the selected program a reality Implement the plan and control the project Construction Professionals These are the parties responsible for constructing the project in traditional management where the owner, design professional, and contractors would be termed prime contractors. The prime contractor is responsible for delivering a complete project in accordance with the contract documents. Design Professionals Architect An individual who plans and designs buildings and their associated landscaping. Engineer This usually refers to an individual or a firm engaged in the design or other work associated with the design or construction. Engineering-Construction Firm This is a type of organization that combines both architect/engineering and construction contracting. This type of company has the ability to execute a complete design-build sequence. Owner/Client The individual or organization for whom a project is to be built under a contract. They may handle all or a portion of planning, project management, design, engineering, procurement, and construction. They are subcategorized to public owners and private owners.