Upper Molweni River Wetland Rehabilitation Project Mend the Molweni Progress Report March 2023 Introduction The Mend the Molweni (MtM) project was started in 2022 as a focus project of the Hillcrest Conservancy. The aim of the project was to “adopt” a number of waterway points on the south side of Springside Nature Reserve, and rehabilitate these so that they no longer were a source of contamination of the headwaters of the Molweni River. This river begins with a spring and a dried out wetland, and then winds down through Springside Nature Reserve, out into a D’MOSS area then flows through Everton Gorge and crosses Kloof Falls Road near the Interpretative Centre in the Krantzkloof Nature Reserve, where it is dammed at the Kloof Falls Picnic Site. After leaving the Picnic Site, the Molweni River drops over the Kloof Falls, the highest falls on the river, into the Kloof Gorge. It flows along a granite base at the bottom of the gorge and exits the Krantzkloof Nature Reserve about 500m after Splash Rock. From the reserve, the Molweni River flows through a fertile plain in Lower Molweni, where it joins the Umgeni River at the Marble Arches, 16 kilometers from its source in Hillcrest. The Molweni gets a lot of attention along its course, and thus has the potential to be a completely rehabilitated and clean river in a network of rivers that are seriously compromised. Patching into the vision of the Transformative Riverine Management Programme (TRMP), our small project aims to be a model. It aims to model a partnership effort between civil society, the private sector and the municipality, and it aims to model how rivers can be restored. This progress report tells the story of a slow start, but steady effort, in which the eight original sites of the MoM have dropped to seven, and the rest are in various stages of development. The biggest lesson we have learned so far is that our original dream was very ambitious and that our timelines have had to stretch to fit the availability of the volunteer team involved. A reminder of the plan Our plan is to take seven sites and rehabilitate them in site-specific ways so that, together, they reduce the contamination of the Moweni River. Each site has its own unique location, characteristics, complications and opportunities. They are named and shown on the map below. Figure 1. Map of the MtM Summary of sites and proposed actions The following table summarises the MtM plan for each of the nine sites: Site Site 1: Springlea Wetland Site 2: Springside Ponds Wetland Site 3: Tree Park Wetland Site 4: Taxi rank bank Site 5: RailSpringside Manor system Site 6: Springside mini-weir system Site 7: 41 Springside Rd Site 8: Culvert at Stonewall Bridge Site 9: SNR weir wall: A later phase Description of actions Support, and learn from, landowners from Springlea Estate (led by Rod Edwards) in their commendable efforts to showcase a rehabilitated wetland. Continue and expand the work that has already been done in this site, as part of the MtM, by allocating labour resources to clear extensive AIP infestation and replanting with indigenous and wetland friendly alternatives. Primary intervention of this project Restore this wetland using an engineered solution, beginning with completely clearing the stormwater outlet and properly transforming the wetland into a filtering system, removing toxic pollution from the stormwater, as well as creating a valuable carbon sink. 4a: On the south bank: - Clear, landscape and maintain the bank containing the attenuation dam, exposing the original stone wall. - Clear the monitor the culvert system. 4b: On north bank: - Clear bank from roadside (including culvert opening) into SNR. - Create and maintain a wetland from the culvert opening into the reserve. It is proposed that HC takes a rational view of this site, doing smaller interventions to begin with: - Assess where all the contaminants are coming from. - Clear AIPs, Clear litter. - Create a water testing station with signage on complex wall. - Engage residents of complex, taxi owners, shops in an effort to build a partnership Rehabilitate the area between the culvert and SNR, by using a nature-based solution to manage water flow. - Clear the area of junk and AIPs - Create a series of small “weirs”, and plant up the area with water-cleaning plants (arums, juncus, vetiver etc) 7a: On south of Springside Rd: - Lobby Dept Roads & Stormwater management to engage DSW to prevent sewer spills into stormwater system. - Beautify the area between the “managed garden” (opposite nr 41) and the stormwater culvert. Create a Pollinator Ridge garden and a smaller indigenous patch (Jenny Dean’s Patch) 7b: On north side of Springside Rd: - Monitor & keep clear and clean the culvert system. - Engage landowner of nr 43 and propose a partnership wetland mini-project on the water course from the culvert into SNR. Heavy contamination of stormwater drain, at times when Water & Sanitation plant overflows (just behind panelbeater). Main actions: - Monitor W&S plant and report spillages. - Mobilise St Helier vet and Church to assist to keep water channel clear and clean. Old weir, damaged by floodwaters, river flowing into property across from SNR gate. • Design an action plan to rehabilitate this section Progress to date per site The biggest achievement so far has been the mobilization of support from inividuals and businesses to support the efforts of the MtM. This is a key objective of the TRMP and the MTM in order to build sustainability and local responsibility into the process. The conservancies movement in eThekwini is all about engaging locals in protecting the natural assets in their own areas. Projects such as the MtM are ways in which this can be mobilized. Site 1: Springlea Estate This beautifully restored wetland takes dirty water at the spring site that has been contaminated by road runoff, and takes it through 100m of restored and forested land into which a wide range of water-cleaning plants have been planted. At the end of the property, the stream flows clean into a small pond, before making its way through other residential properties into the Springside Ponds area. Rod Edwards has led this project. He has also mobilized the other residents of the estate to “adopt” the end of Tree Park closest to them, and assist with the rehabilitation of that area, meeting the effort of the Hillcrest Conservancy team working on the rest of the Tree Park. PIC Figure 2. Community-restoration of wetland at Springlea Site 2: Springside Ponds Wetland The plan at this site is to radically upscale the maintenance work that has been taking place here for some years already. The site has a long history, but essentially was privately owned and then handed over to Council and incorporated into SNR. The area receives flow from the Springlea stream as well as from another spring located in a private property (8 Shortlands Rd) just to the north of the Springside Ponds. The landowners at the latter site are (like Springlea) in the process of rehabilitating their property, removing AIPs and restoring the spring. The Springside Ponds area has been contaminated by a wide range of AIPs for many years, and efforts of the HC committee to manage this has been more about controlling the expansion than total eradication. Apart from the large invasive trees, many elderberry trees, Camphors, Lantana and wild ginger had taken over the site. There are also invasive reeds in the waterway area. The MtM project has enabled a more concerted approach to eliminate the invasives. Site 2 is project-managed by Barry Lang. Progress so far So far, an assessment and plan has been developed, and an access path from the Scout Hall has been cut to enable access for a contractor (Simon Maphumulo from Msenge Landscapes). In November, Msenge Landscapes spent three days with their team and did a significant clearing, under the guidance of Barry Lang from HC. As the clearing has happened, so Barry and George Victor have replanted indigenous plants in the site. The following set of photographs show the area before and after the clearing exercise. Before Figure 3. Before pictures of the Springside Ponds After Figure 4. After pictures of the Springside Ponds As the clearing work settles, and the new indigenous plant material establishes itself, so additional pond restoration work will take place, making this a very special wetland ecosystem, home to rare frogs and other fauna and flora. The headstart provided by the MtM will enable this shift from tedious clearing to creative restoration. Site 3: Tree Park Wetland This site lies parallell to and between Springside Road and Inanda Road. The site was “adopted” by HC in 2020, as it was a huge eyesore in the middle of Hillcrest, and represented a great bopportunity to develop a managed park-like area for local residents. In the two years, many gum trees were removed and replaced with over 60 indigenous trees, giving the area its new name: Tree Park. There is a culvert running from the edge of Garden Road, under Inanda Road, with an outlet that comes out into the wetland area. This pipe is often blocked, and the area has become a catch-all site for vast amounts of litter. The litter comes from people who use the area, passers-by on foot and car, the culvert and wind. It aggregates due to a lack of care and thus the neglected, mostly dry wetland has trapped large amounts of litter between the sedge grasses. Some of these layers of plastic and other rubbish are now as much as half a metre deep. until just over a year ago when the Hillcrest Conservancy "adopted" this space. Since then, a weekly litter clean-up has been carried out, over sixty indigenous trees have been planted on the site, and pathways have been created and maintained. The public is encouraged to use the site as a place to walk themselves and their dogs. The area is now referred to as Tree Park. This site is high profile, as it is exposed to motorists using Inanda Road, walkers and cyclists using the rail trail, and visitors to Sam's Social House. The wetland rehabilitation intervention here is the primary activity of the MtM Project, and is anticipated to take years to complete. Proposed Action: As part of the MtM, Hillcrest Conservancy plans to begin the task of restoring this wetland, beginning with completely clearing the stormwater outlet and properly transforming the wetland into a filtering system, removing toxic pollution from the stormwater, as well as creating a valuable carbon sink. The restored wetland would add to the already rehabilitated road/rail reserve. The constructed wetland will trap litter ready for collection, filter the water through a wetland area, and also act as an attenuation dam, preventing unmanaged surges in the stormwater that seriously affect the banks on to Springside Road and erode the streams in SNR. The entire rehabilitation project will be documented as it evolves, and we hope to engage local schools in the project, as well as local businesses and concerned citizens. The opportunity to upgrade this wetland as a public space will set the standard for other such projects in the eThekwini area. This project will require a significant investment over time. The aim is to develop a plan of action, and then phase in activities as resources become available. Site 3 is project managed by George Victor. Progress so far A site inspection was made by Geoff Tooley from eThekwini Municipality Roads and Stormwater department, to advise on the site as well as the impact factors on stormwater management flowing from the site onto Springside Road and into SNR. It was noted that during the April 2022 floods, there was significant damage emanating from inadequate systems on and around Tree Park, including damage to the rail embankment opposite 19 Springside Road resulting in road closure. It was agreed that some drainage would be necessary to allow for storm water from the mainline track to fall into the drop inlet here. Cross drainage from the cycle track will be necessary to prevent future accumulation of storm water at that site. Subsequent local storm surges have necessitated the need to investigate the possibility of incorporating some storm water attenuation capabilities given the ongoing damage to Springside Nature Reserve. A study of this will be needed to ascertain how the area can be shaped to allow for this in the wetland scenario. Evidence of laundry grey water pollution was noted in the storm water system – future monitoring to be done. Given the scale and complexity of the task, a decision was taken to employ the expertise of professionals to do the site and feasibility assessment, and develop a plan. Verdant Environmental with the assistance of GroundTruth, developed a Wetland Creation Plan. The study undertook to address the following: • Identify practical wetland creation objectives. • Identify practical wetland creation rehabilitation interventions to meet the objectives. • Identify the preferred location and conceptual design of the engineering structures by qualified professional civil engineers. • Compile a preliminary re-vegetation plan. • Compile a preliminary estimate of quantities for all interventions. • Calculate ecosystem services and wetland habitats gains of the proposed plan. The site is indicated by the following picture. Figure 5. Site and site characteristics Verdant Environmental put forward the following objectives for the wetland creation plan: • To divert all stormwater flows into a broad, gently sloping basin adjacent to the existing stormwater drain. • Ensure that permanently waterlogged conditions are created within the basin by both increasing the retention time of water within the basin and reducing infiltration rates. • Ensure that water is discharged from the wetland back into the stormwater system is done in a controlled manner such that erosion risks are mitigated. • Facilitate the establishment of herbaceous obligate wetland vegetation communities suitable to the levels of saturation to be achieved. To achieve the objectives, the following would need to be done: • Intervention 1 – _Earthworks and reshaping. • Intervention 2 – _Drop inlet structure at culvert inlet. • Intervention 3 – _Re-vegetation plan. The documents are attached as Appendix 1A and 1B. As noted above, the task will be phased over time. Aside from commissioning the Wetland Creation Plan, the site has been cleared on several occasions. The most recent workparty carried out on the second “birthday” of Tree Park in November, took out over 20 black bags of rubbish. In addition to this, A large section of the site has been cut and cleared to provide for improved access and to protect newly planted trees. Some sections of the blocked earth drains were cleared to allow for drying out for future earthworks. The blocked section of the road pipe was cleared of a silt build-up to allow for water to flow into the wetland area. A temporary litter trap was installed to catch new litter from the system preventing it from being carried into the rail culvert. So far, one public stakeholders meeting has been held on site together with the committee followed by an article published in the press showing some of the wetland trees and detailing the river management work to be done. Site 4a & 4b: The Taxi Rank culvert This site affects SNR in several ways. There is a complex roads and stormwater management system that does not meet the use intensity. The hard surfaces around the Pick ‘n Pay and Taxi Rank and areas on the opposite side of the Taxi Rank have grown extensively in recent years, all discharging water into the culverts heading towards SNR. The Taxi Rank itself has grown over the years and there are limited facilities within that precinct. Taxi owners wash their vehicles with dirty water taken from the culvert system. The even dirtier water then washes back into the system and is discharged into SNR through the various culverts. From Springside Road, rain offtake adds to the large amount of water already being managed by just two culvert systems, both of which feed into one area that discharges into SNR. The strategy here is to do what is possible within the constraints of the site complexity. Site 4a is between the rail line and Springside Road. The plan here is to: • Clear, landscape and maintain the bank containing the attenuation dam, exposing the original stone wall, and drawing attention to the stormwater management culvert system. • Clear and monitor the culvert system, engaging relevant authorities as necessary. • Engage taxi owners and businesses in the area to assist in the management of water contamination. On the area between Springside Road and SNR, the plan is to clear the bank, landscape with indigenous grasses and plants, expose and keep clear the culvert system, monitor the flow and report to the Roads and Stormwater authorities. Over time we will develop a plan to manage the flow of water into SNR, using a weir-based approach. Progress so far We have engaged Geoff Tooley from Roads & Stormwater regarding the infrastructural issues affecting this site. He has advised that the fall of the storm water and the close proximity to the road, does not permit much in the way of water purification systems on Site 4a. The “washing machine” effect of the water flow can be seen in the attached picture, and will require some remedial work by the municipality. Figure 6. Washing machine effect of water flow The bank has been cleared to a degree, exposing the stone farm wall. This requires regular maintenance. As we can, we will “landscape” with low-maintenance indigenous so that the need for grass cutting is reduced. Figure 7. Taxi Rank Bank, showing exposed stone wall Site 5: Rail-Springside Manor System This site lies between Springside Manor complex and the rail line behind the Shell Garage/Pick’nPay precinct. The aim with this site was essentially to clear and monitor the stormwater and sewerage interface. The area is often the point of contamination and is tied to two other sites of the MtM Project, namely sites 6 and 7. Progress so far The area has been kept clear by consistent brush-cutting by the HC Wednesday workparty. This is a complex and challenging site. It is extremely degraded and problems arise from multiple sources (garage, shops, PNP parking bay, taxi rank, vagrants, Springside Manors Complex). Despite the challenges associated with this site, we will target it in the coming months as this is directly associated Figure 8. Before pictures of Site 5 with the area we name Site 6, discharging extremely contaminated water into the stormwater culvert system that flows directly into the reserve. If we can intervene in a way that moderates the volume of water flowing and the degree of water contamination at this site, then Site 6 will become more of a water polishing site. Site 6: Springside Road Mini-Weir System This site is located between Springside Manor (on the east end) and the property nr 43. It is a waterway catching stormwater from the system feeding Site 5, from Springside Manor and from Springside Road, at culvert number BKS069. It is always running. The waterway runs into SNR. The site was selected as we believe it will be possible to build a multi-weir system, augmented by the planting of “water cleaning” indigenous plants, creating a small wetland. In this way, the water flowing into the Molweni in SNR will be free of contamination. This site is being project-managed by George Victor, Bobby Jackson and Stephen Knight. The waterway carries much more water than originally anticipated. In heavy rains, the hard surface runoff results in a roaring rush of water. There are several problems resulting from this escalated situation, including: • Large volumes of contaminated water flowing into the Molweni River in SNR. • Bank erosion on either side of the waterway, both next to the road and further down as it flows into the reserve. This represents a threat to the road and to boundary wall of nr 41 Springside Road. • There are many AIPs contaminating the banks, especially on the side of the Zondi property. Figure 9. The waterway below the culvert The plan is to reduce the problems identified by managing the water flow and creating a system to polish the water through various interventions. To do this we will: • Create a gabion mattrass to help stabilize the point where the water flows from the culvert and trap solid waste. • Create opportunities for oxygenation of the water through bubble action in order to clean the water soluble contamination. • Expose the waterway to sunlight by removing shade trees and other AIPs from the banks. • Create small pools of water using rocks and gabions and tree trunks, planted with watercleaning plants to further decontaminate the water. • Change the flow of the water where possible to break the direct strength of the flow to inhibit bank erosion. • Remove the intense AIP infestation as this is a seedbank resulting in AIP infestations downstream. • Regular clearing of solid waste in the gabions and in the waterway itself. Progress so far AIP clearing on both sides of the waterway inside SNR has begun, exposing how much there is to do! A plan was devised, using gabions approximately 1 metre from the fence to bolster the sides and sandbags top create the weir system. The site and plan were inspected by Geoff Tooley, who has approved the concept from an engineering perspective. He has agreed to support the request to the municipality to provide additional work at the pipe outlet. A call made to the private sector for support resulted in an enthusiastic response from Sefton Fripp from Fibretex (sandbags) and Daniel Viglieno from Gabion Baskets. The two supporters visited the site and provided valuable input into the plan. In February, the gabion mattrass and side walls were installed and the evidence of their effectiveness is already observable. The landowners from nr 49 (Arthur Leuschke) and 51 (Cyril Zondi) are aware of the project and are supportive. Figure 10. Gabion baskets in the waterway More recently, on 19 March, as part of the eThekwini Enviro Week, a work party planted two wetland gardens on either side of the weir. These gardens will look lovely but will also provide a seed bank for water cleaning and bank stabilisation plants downstream. Figure 11. Work party planting up the wetland gardens Site 7a: Pollinator Ridge and Jenny Dean’s Patch & Site 7b: Dalton’s Waterway This site is located on both sides of Springside Road alongside the railway (opposite Platz Restaurant) and nr 42-43 Springside Road. The area hosts a stormwater system that comes from two points – one from behind the KwikSpar, the other from near the Pick’nPay / Shell garage – meeting between the railway and Springside Rd. At a point south of the railway line there is a sewer line that surcharges regularly into the stormwater drain 1. It is likely that the problem of contamination of this waterway in general relates to the oil dumping from all the restaurants in the “feeder” precinct. 1 Recently on a Saturday morning in December 2022, we were clearing that area, and at about 10h30, for no obvious reason, a massive quantity of sewerage came barraging down the stormwater drain straight into the river. The volume was really pumping – possible 1,5 feet deep. The smell was shocking. This site was chosen for a number of reasons: the landscaping is relatively simple, the site has excellent visibility to passing cars, cyclists using the adjacent track and walkers; and it builds on landscaping and maintenance work already being done by Dalton Taylor, who owns the two properties adjacent to the site. The management of the sewer surcharges is complex, but we believe that there is sufficient interest from various stakeholders to effect a collaborative approach here, between Departments of Roads & Stormwater, Water & Sanitation, the commercial centre businesses and the MtM Team. The aim of this mini-project is to clear existing debris and solid waste, track the sources of contaminants (dumped solid waste as well as sewerage and chemicals in the storm water culvert system) and create a visually appealing and environmentally active site to bring awareness to this project. It was decided to create a managed ridge of pollinator wild flowers along a 50m stretch between Springside Road and the railway, create a patch of visually impressive indigenous plants near the culvert, and use the culvert wall to put up educational material. This site is project-managed by Bobby Jackson. Progress so far Jenny Dean Wildflowers was approached for help and she happily provided advice, a sketch for the site as well as donated some plants and compost. Other plants were sourced from a pile of plants that had been discarded by a local resident. A “public” work party resulted in the removal of a huge volume of solid waste from one of the of the stormwater channels. Dalton XX has agreed to be an active member of this project, extending what he already does to manage the area just above “our” chosen site. The two areas for landscaping were left with their existing, largely indigenous, groundcovers intact and the following were planted into the area with as little disturbance as possible: Syncolostemon densiflorus, Polygala virgate, Aloe arborescens and A. tenuoir, and Agapanthus. We plan to add Kniphofia sp. and Aristea aristata when available. We also plan to add signage regarding the site, the whole project and plants and their pollinators. Ongoing maintenance of the site is a challenge that still needs to be addressed, hopefully by local residents volunteering their energy and time once they become aware of the wide benefits to a successful MTM project. However, through the MtM, we will provide regular monthly maintenance sessions. Figure 12. Planting up Jenny Dean's Patch Figure 13. Pollinator Ridge taking shape Figure 14. Pollinator ridge taking greater shape - 18 March In respect of the stormwater management plan, so far George Victor and Gill Noyce have had a number of meetings with some of the neighbouring centre landlords. The idea of setting up a collaboration between them and the municipality for a local group to take over the management of the sewer pump stations, in the way that is done by Toyota in another part of Durban. Solving this issue is critical to the management of water contamination going into the Molweni in SNR. Site 7b is a stormwater culvert that feeds water into SNR via the property owned by Dalton Taylor. Dalton has already crawled into the culvert and cleared out the significant blockage that was impeding water flow. A sustainable solution to improving the efficacy of this water flow still needs to be formulated. Figure 15. Stormwater channel taking water into SNR Education and awareness building This sub-project involves creating information boards to explain what we are doing with the MtM and why. There will be a “mother” board located at Tree Park with a large information board that explains the MtM aims and objectives, its alignment to the TRMP and what and where the components are. Then at each individual site, a smaller set of information boards will explain the aims and objectives of each sub-project. The progress of the project is regularly reported on in the Highway Mail. General activities The MtM Project aims not only to contribute to improving water quality of the headwaters of the Molweni, and thereby the rest of the river, but also seeks to engage neighbourhood communities in caring for “their” natural assets, including rivers. Aligning the MtM with the TRMP was an elaboration of this commitment. It is always a challenge to mobilise community voluntarism, and our approach has sought to embrace the nudge theory, which says that the more people see that actions serve their own interests and concerns, the more likely they are to feel attached to the action. An important part of the MtM work has consequently been to make the project visible and kbnown to the community, and to make it useful in some way. The site at Springlea (Site 1) is an excellent example whereby a resident of the complex has restored a section of the area, creating a beautifulk wetland, for the benefit of the environment and the benefit of the landowners. This successful project has resulted in other landowners of that complex choosing to do more. They know what is being done, why and how it adds value to their lives and their land. In respect of the other sites, we have chosen locations that are visible and accompanied the water cleaning components with beautification through landscaping in an effort to attract attention, support and involvement. So far, we have the active support of a number of businesses in the various sites as well as individuals from the surrounding community who have assisted in clearing work parties, waterway monitoring and reporting.