Uploaded by Mohamad Qhaizul Azzmi Mohamed Zaki

Exxon GP 560202 OR ISO 12944 C5M painting

advertisement
GP 56-02-02
Painting General Requirements for New Construction
Version 4.2.0
December 2018
Painting General Requirements for
New Construction
GP 56-02-02
Scope
1) The purpose of this Global Practice (GP) is to define the minimum requirements for selection,
application, and quality control for coatings applied to new construction facilities and structures, both
onshore and offshore. It is a combination of the previous versions of the prior onshore and offshore
coating GPs. Maintenance painting and coating for field managed modification projects is covered
separately in GP 56-02-11.
2) For Midstream applications only, GP 19-04-01 is used for internal coatings and GP 19-77-03 for
underground tanks/separators.
3) The appendices provide references to specific coatings for piping, equipment, and structures based on
service and environment.
4) Tanks of bolted construction, as well as tanks and vessels constructed of nonmetallic materials are
outside the scope of this GP.
5) Buried or immersed pipelines are covered separately in GP 56-02-01.
Upstream, Pipeline and
Distribution
© ExxonMobil 2018
TEC5000
Page 1 of 67
Copyright Waiver:
ExxonMobil (EM) hereby licenses the use of ExxonMobil Engineering Practices System (EMEPS) Global Practices (GPs) for use by any EM division, subsidiary, or
more-than-50% owned and in-fact operationally controlled affiliate. The GPs may be downloaded and modified as necessary for project and affiliate use. Written
permission from EM is not required. However, any modified GPs must be renumbered to a project-specific or affiliate-specific number to differentiate them from the
GPs on the EMEPS website. EM-operated Joint Ventures (JVs) may utilize the GPs to create project-specific or location-specific specifications. It is the responsibility
of each affiliate or Joint Venture to ensure that the use of GPs and their derivatives is limited to affiliate or JV-related business and not disclosed or used outside the JV
without appropriate EM management approval.
Note to Third Parties:
Copyright 2018 ExxonMobil. All rights reserved. No portion of this work may be reproduced or distributed by any means or technology or otherwise used in any
manner without the express written consent of ExxonMobil.
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Table of Contents
Table of Tables .............................................................................................................. 5
1.
References ............................................................................................................. 6
1.1.
1.2.
1.3.
1.4.
1.5.
1.6.
1.7.
1.8.
1.9.
1.10.
1.11.
2.
Definitions and Acronyms .................................................................................. 10
2.1.
2.2.
3.
Contractor Procedure ................................................................................. 12
Pre-Production Meeting .............................................................................. 12
Manufacturer's Standard Finishes .............................................................. 12
Items Included in Contractor's Work Scope ................................................ 12
Items Not to Be Coated .............................................................................. 13
Safety and Environmental .......................................................................... 14
Qualification ........................................................................................................ 14
4.1.
4.2.
4.3.
5.
Definitions................................................................................................... 10
Acronyms ................................................................................................... 10
General ................................................................................................................. 11
3.1.
3.2.
3.3.
3.4.
3.5.
3.6.
4.
Global Practices–ExxonMobil Engineering Practices ................................... 6
ExxonMobil Data Sheets .............................................................................. 6
ANSI–American National Standards Institute ............................................... 6
ASTM International....................................................................................... 6
BSI–British Standards Institution .................................................................. 7
Deutsches Institut fur Gutesicherung und Kennzeichnung e.V..................... 8
ISO–International Organization for Standardization ..................................... 8
NACE International....................................................................................... 9
NORSOK–Norwegian Offshore Standards ................................................... 9
SN–Standard Norge ..................................................................................... 9
SSPC–The Society for Protective Coatings.................................................. 9
Documentation ........................................................................................... 14
Qualification of Procedures ........................................................................ 15
Coating Applicator Qualification ................................................................. 16
Materials............................................................................................................... 17
5.1.
5.2.
5.3.
5.4.
UPST, PL
Material Manufacturers ............................................................................... 17
Machined-Surface Coatings ....................................................................... 17
Abrasive Materials ...................................................................................... 17
Thinners, Solvents, and Cleaners .............................................................. 18
© ExxonMobil 2018
TEC5000
Page 2 of 67
GP 56-02-02
5.5.
6.
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Touch-Up Materials .................................................................................... 18
Shipping, Handling, and Storage ....................................................................... 19
6.1.
6.2.
6.3.
Delivery and Storage .................................................................................. 19
Date of Materials ........................................................................................ 19
Handling of Coated Items ........................................................................... 19
7.
Ambient Conditions and Application Equipment ............................................. 20
8.
Surface Preparation ............................................................................................ 20
8.1.
8.2.
8.3.
8.4.
8.5.
8.6.
9.
Pre-Blasting Preparation ............................................................................ 21
Scaffolding.................................................................................................. 21
Abrasive Blast Cleaning ............................................................................. 22
Steel That Has Been Shop Primed Only .................................................... 23
Power Tool Cleaning .................................................................................. 23
Galvanized Steel ........................................................................................ 23
Mixing and Applying Coatings ........................................................................... 24
9.1.
9.2.
9.3.
Mixing ......................................................................................................... 24
Preparation ................................................................................................. 24
Application—General ................................................................................. 25
10. Inspection and Testing ....................................................................................... 27
10.1.
10.2.
10.3.
10.4.
10.5.
Responsibility ............................................................................................. 27
Personnel Qualification .............................................................................. 27
Contractor's Responsibilities ...................................................................... 28
Compressed Air Quality Test...................................................................... 28
Nonconformance Report ............................................................................ 28
11. Remedial Work .................................................................................................... 33
11.1. General Repair ........................................................................................... 33
11.2. Repair of Immersion Coatings and Linings ................................................. 34
11.3. Damaged Repair of Hot-Dip Galvanizing.................................................... 34
Appendix A: Coating Schedule/Matrix ..................................................................... 36
A–1. Corrosivity Classifications ............................................................................ 36
A–2. Coating Schedule/Matrix .............................................................................. 38
Appendix B: Generic Coating Products/Coating Systems ...................................... 51
B-1: Generic Coating Products/Coating Systems.................................................. 51
B–2: Paint Manufacturers and Complying Products .............................................. 54
UPST, PL
© ExxonMobil 2018
TEC5000
Page 3 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Appendix C: Coating Qualification Procedure ........................................................ 56
C–1
C–2
C–3
C–3.1
C–3.2
C–3.3
C–4
C–5
C–6
C–7
Scope ......................................................................................................... 56
General....................................................................................................... 56
Coating System .......................................................................................... 56
Description ................................................................................................. 56
Formulation of Coating Materials................................................................ 57
Preparation and Conditioning of Test Panels ............................................. 57
Test Requirements and Acceptance Criteria .............................................. 58
Qualification Testing Requirements ............................................................ 60
Anti-Skid Systems ...................................................................................... 61
Test Reports ............................................................................................... 61
Appendix D: Midstream Tank Labeling Requirements ............................................ 62
Record of Change ....................................................................................................... 64
Attachment: Purpose Code Definitions.................................................................... 67
UPST, PL
© ExxonMobil 2018
TEC5000
Page 4 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Table of Tables
Table 1: Surface Preparation Standards .................................................................. 21
Table 2: Inspection and Testing Plan ....................................................................... 29
Figure 1: Repair Sketch ............................................................................................. 34
Table 3: Coating Systems for Minor Galvanizing Repairs ...................................... 35
Table 4: Coating Systems for Major Galvanizing Repairs ...................................... 35
Table A–1: Corrosivity Classifications per BS EN ISO 12944-2 ............................. 36
Table A–2: Corrosivity Classifications by Generic Environment Descriptions .... 37
Table A–3: Coating Schedule/Matrix ........................................................................ 38
Table B–1: Company Coating System Codes .......................................................... 51
Table B–2: Paint Manufacturers and Complying Products .................................... 54
Table C–1: Test Requirements and Acceptance Criteria ........................................ 58
Table C–2: Qualification Testing Requirements ...................................................... 60
Table D–1: Tank Labeling .......................................................................................... 62
Table D–2: Equipment Identification ........................................................................ 63
UPST, PL
© ExxonMobil 2018
TEC5000
Page 5 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
1. References
1) This Section lists the Practices, codes, standards, specifications, and publications that shall be used
with this document. Unless otherwise specified herein, use the latest edition.
2) Contractor shall be fully familiar with these documents and be able to demonstrate conformity to their
requirements. Contractor shall, Upon request, be able to produce these documents for onsite
verification of compliance.
1.1.
Global Practices–ExxonMobil Engineering Practices
GP 29-01-03
Material Selection for Upstream and Midstream Facilities and
Equipment
GP 29-02-19
Upstream Hot Dip Galvanizing of Structural Steelwork
GP 56-02-01
Coating Selection and Application Guide for Pipelines and PipelineRelated Facilities
GP 56-02-08
Thermal Spray Metallic Coatings
GP 56-02-11
Coatings for Maintenance and Other Small Projects
GP 56-02-13
Fluoropolymer Coatings for Fasteners
GP 66-01-03
Corrosion Protection for Risers
GP 70-01-05
Upstream Fireproofing
1.2.
ExxonMobil Data Sheets
I560202C01
1.3.
Inspection and Testing Requirements Sheet - Painting General
Requirements for New Construction - Offshore/Onshore - Daily Surface
Preparation and Coating - Customary Units
ANSI–American National Standards Institute
ANSI Z400.1/Z129.1
1.4.
Hazardous Workplace Chemicals - Hazard Evaluation and Safety Data
Sheet and Precautionary Labeling Preparation
ASTM International
ASTM A 780/A 780M
Standard Practice for Repair of Damaged and Uncoated Areas of HotDip Galvanized Coatings
ASTM D 520
Standard Specification for Zinc Dust Pigment
ASTM D 521
Standard Test Methods for Chemical Analysis of Zinc Dust (Metallic
Zinc Powder)
UPST, PL
© ExxonMobil 2018
TEC5000
Page 6 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
ASTM D 2106
Standard Test Methods for Determination of Amine Acid Acceptance
(Alkalinity) of Halogenated Organic Solvents
ASTM D 3359
Standard Test Methods for Measuring Adhesion by Tape Test
ASTM D 4228
Standard Practice for Qualification of Coating Applicators for
Application of Coatings to Steel Surfaces
ASTM D 4285
Standard Test Method for Indicating Oil or Water in Compressed Air
ASTM D 4414
Standard Practice for Measurement of Wet Film Thickness by Notch
Gages
ASTM D 4417
Standard Test Methods for Field Measurement of Surface Profile of
Blast Cleaned Steel
ASTM D 4541
Standard Test Method for Pull-Off Strength of Coatings Using Portable
Adhesion Testers
ASTM D 4752
Standard Test Method for Measuring MEK Resistance of Ethyl Silicate
(Inorganic) Zinc-Rich Primers by Solvent Rub
ASTM D 5162
Standard Practice for Discontinuity (Holiday) Testing of Nonconductive
Protective Coating on Metallic Substrates
ASTM D 5402
Standard Practice for Assessing the Solvent Resistance of Organic
Coatings Using Solvent Rubs
ASTM D 6677
Standard Test Method for Evaluating Adhesion by Knife
ASTM E 11
Standard Specification for Woven Wire Test Sieve Cloth and Test
Sieves
ASTM E 337
Standard Test Method for Measuring Humidity with a Psychrometer (the
Measurement of Wet- and Dry-Bulb Temperatures)
ASTM G 8
Standard Test Methods for Cathodic Disbonding of Pipeline Coatings
1.5.
BSI–British Standards Institution
BSI BS EN ISO 2812-2
Paints and Varnishes - Determination of Resistance to Liquids - Part 2:
Water Immersion Method
BSI BS EN ISO 4624
Paints and Varnishes - Pull-Off Test for Adhesion
BSI BS EN ISO 6272-1
Paints and Varnishes - Rapid-Deformation (Impact Resistance) Tests
Part 1: Falling-Weight Test, Large-Area Indenter
BSI BS EN ISO 8501
Preparation of Steel Substrates Before Application of Paints and Related
Products - Visual Assessment of Surface Cleanliness (all parts)
BSI BS EN ISO 8502-3
Preparation of Steel Substrates before Application of Paints and Related
Products - Tests for Surface Cleanliness - Part 3: Assessment of Dust on
Steel Surface Prepared for Painting (Pressure-Sensitive Tape Method)
BSI BS EN ISO 8502-6
Preparation of Steel Substrates before Application of Paints and Related
Products - Tests for the Assessment of Surface Cleanliness - Part 6:
Extraction of Soluble Contaminants for Analysis - The Bresle Method
UPST, PL
© ExxonMobil 2018
TEC5000
Page 7 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
BSI BS EN ISO 8502-9
Preparation of Steel Substrates before Application of Paints and Related
Products - Group B: Methods for the Assessment of Surface Cleanliness
- Part B9: Field Method for the Conductometric Determination of
Water-Soluble Salts
BSI BS EN ISO 8503
Preparation of Steel Substrates before Application of Paints and Related
Products - Surface Roughness Characteristics of Blast-Cleaned Steel
Substrates (all current parts)
BSI BS EN ISO 9227
Corrosion Tests in Artificial Atmospheres - Salt Spray Tests
BSI BS EN ISO 129442
Paints and Varnishes - Corrosion Protection of Steel Structures by
Protective Paint Systems - Part 2: Classification of Environments
BSI BS EN ISO 129445
Paints and Varnishes - Corrosion Protection of Steel Structures by
Protective Paint Systems - Part 5: Protective Paint Systems
BSI BS EN ISO 129449
Paints and Varnishes - Corrosion Protection of Steel Structures by
Protective Paint Systems Part 9: Protective Paint Systems and
Laboratory Performance Test Methods for Offshore and Related
Structures
1.6.
Deutsches Institut fur Gutesicherung und Kennzeichnung e.V.
RAL Classic Color
System
1.7.
German Color Standard
ISO–International Organization for Standardization
ISO 4624
Paints and Varnishes - Pull-Off Test for Adhesion
ISO 8501
Preparation of Steel Substrates before Application of Paints and Related
Products - Visual Assessment of Surface Cleanliness (all current parts)
ISO 8502-3
Preparation of Steel Substrates before Application of Paint and Related
Products - Tests for the Assessment of Surface Cleanliness - Part 3:
Assessment of Dust on Steel Surfaces Prepared for Painting (PressureSensitive Tape Method)
ISO 8502-6
Preparation of Steel Substrates before Application of Paints and Related
Products - Tests for the Assessment of Surface Cleanliness - Part 6:
Extraction of Soluble Contaminants for Analysis - The Bresle Method
ISO 8502-9
Preparation of Steel Substrates before Application of Paints and Related
Products - Tests for the Assessment of Surface Cleanliness - Part 9:
Field Method for the Conductometric Determination of Water-Soluble
Salts
ISO 8503
Preparation of Steel Substrates before Application of Paints and Related
Products - Surface Roughness Characteristics of Blast-Cleaned Steel
Substrates (all current parts)
ISO 9227
Corrosion Tests in Artificial Atmospheres - Salt Spray Tests
UPST, PL
© ExxonMobil 2018
TEC5000
Page 8 of 67
GP 56-02-02
1.8.
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
NACE International
NACE SP0178
Design, Fabrication, and Surface Finish Practices for Tanks and Vessels
to Be Lined for Immersion Service
NACE SP0304
Design, Installation, and Operation of Thermoplastic Liners for Oilfield
Pipelines
1.9.
NORSOK–Norwegian Offshore Standards
NORSOK M-501
1.10.
SN–Standard Norge
SN NS 476
1.11.
Surface Preparation and Protective Coating
Paints and Coatings - Approval and Certification of Surface Treatment
Inspectors
SSPC–The Society for Protective Coatings
SSPC AB 1
Mineral and Slag Abrasives
SSPC AB 2
Cleanliness of Recycled Ferrous Metallic Abrasives
SSPC AB 3
Newly Manufactured or Re-Manufactured Steel Abrasives
SSPC GUIDE 15
Field Methods for Retrieval and Analysis of Soluble Salts on Steel and
Other Nonporous Substrates
SSPC PA 1
Shop, Field, and Maintenance Painting of Steel
SSPC PA 2
Measurement of Dry Coating Thickness with Magnetic Gages
SSPC QP 5
Standard Procedure for Evaluating Qualifications of Coating and Lining
Inspection Companies
SSPC SP 1
Solvent Cleaning
SSPC SP 3
Power Tool Cleaning
SSPC SP 5
White Metal Blast Cleaning (NACE NO. 1)
SSPC SP 10
Near-White Metal Blast Cleaning (NACE NO. 2)
SSPC SP 11
Power Tool Cleaning to Bare Metal
SSPC SP 16
Brush-Off Blast Cleaning of Coated and Uncoated Galvanized Steel,
Stainless Steels, and Non-Ferrous Metals
UPST, PL
© ExxonMobil 2018
TEC5000
Page 9 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
2. Definitions and Acronyms
2.1.
Definitions
Term
Description
Contractor Coating
Inspector (CCI)
Technically competent Coating Inspector certified to at least NACE
Level II or other internationally industry-recognized equivalent (e.g.,
The Society for Protective Coatings [SSPC], British Gas Approval
System [BGAS], Faglig Rad for Opplæring og Sertifisering av
Inspektører innen Overflatebehandling [FROSIO], or Association for
Certification and Qualification of Anticorrosive Paintwork [ACQPA]).
Fingerprinting
Method of positive identification for coating material as defined in BSI
BS EN ISO 12944-9, Annex B ''Cyclic Ageing Test.''
Fresh Water
Nonsaline water with a maximum pH of 7.5.
Immersion Service
Service where the coating can come into continuous contact with a fluid,
including fluid wet section of tank/vessel internals and coatings under
insulation, etc.
Splash Zone
Components of a facility that are alternately in and out of the water
because of tides, winds, and waves (defined as ± 5 m [16 ft]) from Mean
Astronomical Tide Level (MATL).
Work
As described in Company's contract document.
Worksite
As described in Company's contract document.
2.2.
Acronyms
Term
Description
CCI
Contractor Coating Inspector
CPT
Coating Procedure Test
CRA
Corrosion-Resistant Alloy
CUI
Corrosion Under Insulation
DFT
Dry Film Thickness
ESV
Emergency Shutdown Valve
FEED
Front End Engineering Design
FPSO
Floating, Production, Storage, and Offloading
HDG
Hot-Dip Galvanizing
HVAC
Heating, Ventilation, and Air Conditioning
ID
Inside Diameter
UPST, PL
© ExxonMobil 2018
TEC5000
Page 10 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Term
Description
IOZ
Inorganic Zinc
MATL
Mean Astronomical Tide Level
MEK
Methyl Ethyl Ketone
NSF
National Sanitation Foundation
NSS
Neutral Salt Spray
OD
Outside Diameter
OH&S
Occupational Health and Safety
P&ID
Piping and Instrumentation Drawing
PDS
Product Data Sheet (or Technical Data Sheet)
PFP
Passive Fire Protection
PPE
Personal Protection Equipment
RH
Relative Humidity
SDR
Specification Deviation Request
SDS
Safety Data Sheet (formerly called Material Safety Data Sheets [MSDS])
SI
System International of Units
SME
Subject Matter Expert
TSA
Thermal Spray Aluminum
TSZ
Thermal Spray Zinc
VOC
Volatile Organic Compound
WCP
Written Coating Procedure
3. General
1) Required coating systems and the items and surfaces to be coated with those systems are set forth in
Appendix A.
2) [A] Appendix B provides the generic coating types and compliant coatings from various manufacturers
for each of the codes identified in Appendix A. Where the nominated products are not available,
Contractor shall seek permission from Company to qualify a substitute product using a Specification
Deviation Request (SDR) and submitting the supporting documentation listed in Appendix C.
3) [A] Unless indicated otherwise in procurement documents, shop-fabricated structural steel and piping
shall be shop-primed and yard-finish-painted after assembly and testing. Process equipment and
machinery shall be primed and finish-coated in the shop.
4) Contractor shall control the quality of materials and services to meet the requirements of this GP,
applicable codes and standards, and other procurement documents. Documentation shall be prepared
UPST, PL
© ExxonMobil 2018
TEC5000
Page 11 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
and maintained to provide evidence of compliance with Company-approved procedures and this GP.
A copy of all coatings inspection documentation shall be provided to Company at the conclusion of
the project.
3.1.
Contractor Procedure
1) All coating work shall be performed in accordance with procurement documents, this GP, and
Contractor's Company-approved procedures.
2) As a minimum the procedures shall cover the following:
a) Surface preparation
b) Application of specific coating products
c) Personnel training and applicator qualification records in accordance with Section 4 of this GP
d) A quality plan in accordance with Section 10 of this GP
e) Safety, health, and environmental requirements
f) Protection of adjacent surfaces
3) Where applicable, a Subcontractor's procedures shall form part of Contractor's approved procedures.
4) [A] Contractor is responsible for obtaining Company approvals for all procedures before conclusion
of the Pre-production Meeting.
3.2.
Pre-Production Meeting
1) Before work commences, a pre-job conference shall be conducted to introduce contacts for
Contractor and Company and their project management and inspection representatives.
2) The purpose of the meeting shall be to resolve all issues related to safety, specification requirements,
Applicator's procedures, inspection procedures, acceptance criteria, delineation of responsibility, and
special job requirements.
3.3.
Manufacturer's Standard Finishes
1) Off-the-shelf items (e.g., pumps, compressors, motors, electrical and control cabinets and panels,
switchgear, and valves) may receive a Coating Manufacturer's standard coating system instead of the
one specified in Table A–3 if both of the following provisions are met:
a) [A] [C] Complete details of Coating Manufacturer's system have been provided for review and
approval.
b) [A] [C] The alternative proposed system is judged by Company to provide equal or better
performance to the GP specified system.
2) [A] Finish coat color shall be in compliance with Table A–3 of this GP. With the exception of Safety
Yellow, substitution of color may be approved by Company Representative without an SDR.
3.4.
Items Included in Contractor's Work Scope
All work shall be documented with written procedures. The following list provides a synopsis of work
tasks to be executed by Contractor:
1) Preparing of the surfaces and applying protective coatings to all surfaces as defined in Appendix B.
2) Establishing and maintaining an inventory log for materials (e.g., paint, thinners, and Abrasives).
UPST, PL
© ExxonMobil 2018
TEC5000
Page 12 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
3) Preparing the coating repair procedures for each system used.
4) Performing inspection and tests in accordance with Table 2.
5) Protecting surfaces not to be coated (e.g., machined surfaces and glass).
6) Protecting applied coating from degradation as a result of overblast or overspray.
7) Providing environmental control equipment to achieve and maintain the required application and the
required curing conditions.
8) Applying erection marking.
9) Performing touch-up and repair of defective or damaged coated surfaces.
10) Applying labeling or identification numbering.
11) Disposing of waste, including removal and disposal of all empty or partially empty containers, cloths,
plastic sheeting, solvents, blasting abrasives, equipment, and similar items in compliance with all
applicable regulations and Company requirements where appropriate regulations do not exist.
12) Contractor shall be fully familiar with the standards and documents in Section 1. Contractor shall be
able to produce these documents for onsite verification.
3.5.
Items Not to Be Coated
The following surfaces shall not be painted:
1) Concrete and concrete- and ceramic-masonry units and glass
2) Metal jacketing and weatherproofing on insulation
3) Plastic, rubber, and plastic-coated materials
4) Metal surfaces machined for metal-to-metal contact or to maintain tolerances
5) Electrical/instrument wire and cable
6) Door and building hardware
7) Lighting fixtures, switches, and receptacles
8) Grease fittings
9) Sight glasses, gauges, and thermometers
10) Pilot valves
11) Controllers, recorders, transmitters switches, and relays
12) Filter regulators
13) Nameplate tags
14) Stainless steel tubing (for corrosion resistant alloy piping, follow details in Appendix A)
15) Transducers, solenoid valves, valve positioners, and stems
16) Vents
17) Bug and bird screens
18) Copper-nickel anti-foul sheathing and fire line (flanges are painted in red color)
UPST, PL
© ExxonMobil 2018
TEC5000
Page 13 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
19) Cathodic protection anodes
20) Stainless steel junction and terminal boxes
21) Any other component identified during Front End Engineering Design (FEED)
22) Sealing surfaces (e.g., grooves in RTJ flanges, face of raised face flange) – coat everything up to the
sealing surface
3.6.
Safety and Environmental
1) [E] [A] All surface preparation coatings work and waste disposal shall be in accordance with governing
safety and environmental requirements. Contractor shall propose alternative coatings and solvents for
Company approval if the coatings herein specified do not comply with regulatory requirements
applicable at Contractor's shop locale or local regulatory requirements at the point of project installation
(e.g., Volatile Organic Compound [VOC] limits, restrictions on pigment, or generic coating types).
Contractor shall demonstrate that the requirements in Appendix C, Section C–3.2, have been met.
2) [S] All thinners, solvents, primers, and coating materials shall be regarded as hazardous materials,
and their use and storage shall comply with the following:
a) Occupational Health and Safety (OH&S) hazardous materials regulations (where applicable)
b) Dangerous goods regulations
c) Coating Manufacturer's recommendations
3) [S] All chemicals (e.g., coatings, solvents, thinners, clean-up materials, test materials, etc.) to be used
on site shall meet the following requirements:
a) Have a current Safety Data Sheet (SDS) that complies, as a minimum, with ANSI Z400.1/Z129.1
b) Prior to arrival onsite, be approved for use on the worksite
c) Be accompanied with the current SDS during transport
d) Have a copy of the relevant SDS kept in all paint stores and site offices
4) [S] All caution notices on the product containers and material labels shall remain intact and shall be
strictly observed.
5) [S] As a minimum, all Personal Protection Equipment (PPE) requirements stated in the SDS shall be
met when working with coatings, solvents, Abrasives, or any expendable products used in performing
the coating work.
6) [E] Excess or used solvents, paint, waste materials, and cleaning materials shall be handled in strict
accordance with SDS requirements and applicable disposal regulations and procedures.
4. Qualification
4.1.
Documentation
[A] The following documentation is required and is subject to Company review and approval:
1) A Written Coating Procedure (WCP) based on the requirements of this GP for each paint system to be
applied. Any conflicts amongst Coating Manufacturer recommendations, the WCP, and/or this GP
shall be submitted in writing to Company for resolution.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 14 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
2) A proposed daily inspection record (per Data Sheet I560202C01) for each item coated.
4.2.
Qualification of Procedures
4.2.1.
Written Coating Procedure
1) The WCP shall contain the following:
a) Identification of the structures, systems for each component to be coated, the coating system and
finish coat color to be applied, and the specific coating products to be used for each coat of each
system.
b) Current Product Data Sheets (PDSs).
c) SDSs for each product.
2) The WCP shall describe the following processes/procedures and indicate the proposed hold points for
inspection:
a) Coating material handling and storage and inventory controls.
b) Salt contamination measurement and control methods.
c) Metal preparation at welds and edges, both prior to blast cleaning and, to the extent that surface
anomalies are revealed during blasting, following the blast. Describe the tools, methods, materials,
and sequencing.
d) Surface preparation as follows:
i) Describe the degree of cleanliness and profile to be achieved.
ii) Stipulate the abrasive to be used.
iii) Where different types of surfaces comprising the items to be coated will be prepared to
different criteria, define the criteria applicable for each.
e) Describe the specific type/configuration of tools to be used for any alternative surface preparation
techniques other than abrasive blasting. Identify any surfaces that will not be abrasive blast
cleaned and cleaned per a proposed alternative surface preparation technique instead.
f) Environmental controls as follows:
i) Describe the type and capacity of dehumidification/humidification equipment.
ii) Provide a sketch showing how process air will be distributed throughout the work area.
iii) Describe the type, capacity, and ducting for dust collectors.
g) Scaffolding as follows:
h) [A] A scaffolding plan shall be provided showing layout and construction/dismantling sequences.
Materials for and type of framing and planks and clearances between scaffold and work surfaces
shall be indicated (see Section 8.2 of this GP for details).
i) Illumination: The type for general area and blast hose lighting shall be indicated.
j)
Application (type of equipment), touch-up, and curing.
k) Techniques to correct out-of-spec film thickness and surface treatment processes for "freshening"
coatings that have exceeded their recoat windows.
l)
Inspection.
m) Disposal of waste, debris, and unconsumed coating materials.
3) [A] Coating Subject Matter Expert (SME) shall review and advise approval of WCP. Companyapproved WCP shall be followed during all coating work. Company's approval does not relieve
UPST, PL
© ExxonMobil 2018
TEC5000
Page 15 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Contractor of its obligation to perform the coating work in accordance with the requirements of this
GP. Any change of coating material, methods, or equipment for surface preparation and coating
application shall require that the WCP be revised and reapproved.
4.2.2.
Coating Procedure Test
1) [A] A pre-production Coating Procedure Test (CPT) shall be used to qualify all coating procedures
using a test panel. The test panel referenced in ASTM D 4228, or a comparable type and size of
panel approved in advance by Company, may be used. Alternatively, the CPT may be performed in a
suitable location on the component to be coated. CPT test plates and test locations shall be on
material greater than 5mm (0.2 in.) thick, have adequate access and appropriate geometry to permit
pull-off adhesion testing to be performed.
2) A CPT shall be performed for each substrate and coating system expected to be applied. Environmental
conditions, surface preparation, coating application equipment, and procedures shall be similar to those
anticipated for the actual coating work. All coating application shall be as required in this GP.
"Coating application" shall include the following:
a) Repairs, including ''step'' masking (See Figure 1 for an illustrated example)
b) Intercoat techniques, including mist coating for silicate-type Inorganic Zinc (IOZ) and recoat
window refresher sweep blasting for epoxies
c) Curing
d) Coating inspection hold points
e) Testing requirements for the CPT, including acceptance criteria
3) [A] Inspection and testing requirements for the CPT shall include the same requirements as those
proposed for the work and shall meet the requirements of Table 2, plus any others that may be
deemed appropriate and are approved by Company.
4) Contractor shall be responsible for ensuring that each component of each batch of each product used
during production application is identical in formulation to those applied during the CPT. Company
may request fingerprinting of the products/materials used for the CPT to verify that the products and
materials used in the execution of the work scope are as tested.
5) All test panels prepared shall be safely stored by Contractor for the duration of the work or Company
may request to take care, custody, and/or control of them.
6) [A] Contractor shall submit a full and detailed report of the CPT trial outcome to Company for review
and acceptance prior to incorporating the coating systems into the work.
4.3.
Coating Applicator Qualification
1) [A] Personnel shall have knowledge of health and safety hazard, use of protection equipment,
application attributes of coating materials, mixing and thinning of coatings, induction period, coating
pot-life, surface requirements, etc. Each coating Applicator's qualifications may be reviewed by
Company Inspector or his or her designee to ensure that sufficient documented records are available
to support a determination of proficiency.
2) Contractor shall continuously monitor individual Applicator production and quality. Upon request,
Contractor shall produce these records for review by Company.
3) Contractor shall immediately replace an Applicator who demonstrates an inability to meet the quality
requirements of this GP.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 16 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
4) [A] An Applicator who has been previously replaced due to inability to meet the requirements of this
GP must produce a CPT in accordance with this GP for each coating he/she will be applying and submit
them for inspection by Company Inspector or Company designee. The Applicator will require written
approval from Company prior to being permitted to complete work associated with Company project.
5. Materials
5.1.
Material Manufacturers
1) [A] All coating material shall be as specified in this GP. Where the nominated or any of the alternate
products are not available, Contractor may seek permission from Company to qualify a substitute
product using the appropriate procedures in Appendix C. Exceptions require written Company
approval and shall be qualified in the CPT. The substitute products shall not be incorporated into the
work until written Company approval is received by Contractor.
2) The coatings specified in Table B–2 are intended to be available worldwide. Contractor is
responsible for preparation of procedures based on products of one Coating Manufacturer for each
system. Contractor shall purchase coating materials in a timely manner.
3) [A] All materials applied to any one surface or piece of equipment shall be products of a single Coating
Manufacturer. Compatibility between products of more than one Coating Manufacturer (to be applied
to the same surfaces) shall be proven by the application of a test patch followed by adhesion assessment
per ASTM D 3359 "Test Method A—X-Cut Tape Test" for coatings with a DFT up to 300 µm (12 mils)
or ASTM D 6677 for above 300 µm (12 mils) before incorporating the material into the work by
Contractor. Acceptance criteria shall be as established by Coating Manufacturer of the overcoats and
shall be subject to Company approval.
4) Contractor is responsible for passing through to Coating Manufacturer the requirement that "retains"
(spare liquid paint samples) shall be available for each part (i.e., for base and hardener for two-part
materials) of each batch of coating material applied under this GP, including CPT materials. Retains
shall be kept for 24 months. The volume of retained material shall be at least 0.5 L (1 pint).
5) [S] Contractor shall obtain and furnish Company with certifications from Coating Manufacturer of
each coating material applied showing that materials used contain no elements or compounds of lead,
chromium, cadmium, tin, or other hazardous metals. This includes pigments used to obtain specific
colors. In any case, incidental traces of lead and other heavy metals shall not exceed 0.1% total by
weight of the coating's composition in the dried film. Only ASTM D 520 Type II or Type III zinc
shall be used in the manufacture of zinc-rich primers. Removal, disposal, and replacement of coating
found not to meet these requirements will be at Contractor's expense.
5.2.
Machined-Surface Coatings
[A] Machined surfaces for which no specifically required coating system is specified shall be protected
with a Company-approved temporary preservative.
5.3.
Abrasive Materials
1) [S] Silica sand and other potentially silica-containing material shall not be used for abrasive blasting.
2) Only new aluminum oxide or new garnet abrasive shall be used for preparing Corrosion-Resistant
Alloy (CRA) (e.g., stainless steel).
UPST, PL
© ExxonMobil 2018
TEC5000
Page 17 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
3) Abrasive awaiting or in use shall be stored in such a manner as to ensure that it is kept dry and to
prevent contamination.
5.3.1.
Applicable Standards
1) All new abrasive media for blast cleaning shall be clean and dry, furnished either in bulk or packaged,
and shall be free of clay, oil, or other contaminants.
2) The abrasive gradation shall be capable of producing the specified surface profile.
3) Mineral and slag Abrasives shall additionally meet the requirements of SSPC AB 1, Class A.,
Crystalline silica less than or equal to 1% per SSPC AB 1 standard.
4) Ferrous metal Abrasives shall comply with SSPC AB 3 and if recycled, to SSPC AB 2.
5) [A] Recycled Abrasive shall be replenished with adequate new media to replace the spent material
and to achieve the required profile. The use of recycled abrasive and the recovery system to be used
shall be approved by Company prior to use.
5.3.2.
Material Test Certification
The following testing shall be performed and certified by the Abrasives Supplier:
1) For ferrous metallic abrasive, qualification testing shall consist of all of the testing set forth in SSPC AB
3, Section 4 "Requirements," while conformance testing may be limited to size, conductivity, and
cleanliness. An inspection lot for conformance testing shall constitute each 15,000 kg (16.5 short tons)
or each manufacturing batch, whichever is less.
2) For mineral and slag Abrasives, qualification testing shall consist of all of the testing set forth in SSPC
AB 1, Section 4 "Requirements," while conformance testing may be limited to size, conductivity, and
cleanliness. An inspection lot for conformance testing shall constitute each 10,000 kg (11 short tons) or
each manufacturing batch, whichever is less.
3) Testing to verify compliance with SSPC AB 2 is Contractor's responsibility.
4) Contractor is responsible for ensuring that the abrasive materials testing and documentation required
by the applicable SSPC abrasive specifications is obtained from the abrasive Supplier and is available
to Company's site representative.
5.4.
Thinners, Solvents, and Cleaners
1) Thinners, solvents, and cleaners shall be as manufactured or specified by Coating Material
Manufacturer and shall be identified by the product number or generic description and accompanied
by an SDS and PDS.
2) [S] Only manufacturer's original containers designed for the purpose may be used to contain thinners,
solvent, or cleaners.
3) Labeling allows verification that the correct material is being used and allows tracking of batch
numbers.
5.5.
Touch-Up Materials
1) [A] Materials for touch-up of damaged areas of surfaces shall be per Company-approved procedure or
the same as those that were originally applied.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 18 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
2) Touch-up materials shall be provided in pre-measured units. Only previously unopened complete kits
shall be mixed.
6. Shipping, Handling, and Storage
6.1.
Delivery and Storage
1) Coating materials shall be delivered to the place of application in unopened, original containers as
provided by Coating Manufacturer. Each container shall bear a legible product designation, unique
batch number, expiration date, shelf life, data of manufacture, and color code (if applicable). The
labeling shall meet the obligations of all applicable statutory requirements. Damaged or containers
failing to meet these requirements shall remain unopened, the property of Contractor, be removed
from the work site as soon as practicable, and be permanently marked "not to be used."
2) Container labeling shall remain legible throughout the duration of the container's use. Any container
of material, where the label has become illegible or detached, shall remain the property of Contractor
and shall be removed from the site at Contractor's expense.
3) Material shall be transported, handled, and stored in accordance with Coating Manufacturer's latest
published instructions and shall be protected from damage, moisture, direct sunlight, and
temperatures below 5 °C (41 °F) or above 32 °C (90 °F). Storage facility shall be well ventilated and
free from open flame or other sources of ignition and meet all applicable statutory requirements.
6.1.1.
Traceability
1) The coating materials shall be traceable to a batch certification issued by Coating Manufacturer. At
any time, Company may request Contractor to provide a fingerprinting of the coating material on site
to verify the authenticity and complement the traceability of materials supplied.
2) Contractor shall obtain batch certificates from Coating Manufacturer for all material to be
incorporated into the work. These certificates shall be kept onsite during the work and shall be
submitted to Company as part of the closeout report.
6.2.
Date of Materials
1) Coating material shall not be used beyond its expiration date and all expired coating material will
remain the property of Contractor and shall be removed from the site and disposed of at Contractor's
expense.
2) Containers of coatings or components shall not be opened except for immediate use.
6.3.
Handling of Coated Items
1) Coated items shall not be handled before Coating Manufacturer's published handle time has elapsed.
2) Coated items shall be protected from mechanical damage during application, storage, or transit to
prevent damage to the finished coating.
3) Metal equipment used for handling coated parts, including forks and chokers, shall be encased with
compressible materials proven to be slip-safe.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 19 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
7. Ambient Conditions and Application Equipment
1) Contractor shall not conduct final surface preparation or apply coatings unless the temperature of the
substrate is expected to remain 3 °C (5 °F) minimum above the ambient dew point. The substrate
temperature during coating application and curing shall be maintained between 10 °C (50 °F)
minimum and 40 °C (105 °F) maximum, or per Manufacturer's PDS. Relative Humidity (RH) shall
be below 85% during final surface preparation and coating application. Climate controlled buildings
and enclosures may be required.
2) [A] Before application of additional topcoats, epoxy-coated surfaces shall be checked for amine blush
per ASTM D 2106 Method B, using an Elcometer 139 test kit, or Company-approved equivalent if
one or more of the following exist:
a) The substrate did not remain 3 C (5 F) or more above the dew point until the epoxy coating was
cured.
b) Coating mix temperature and induction time is suspected to have been too low, too short, or
otherwise inadequate.
c) Water wetted the epoxy-coated surfaces before the coating reached cure.
d) There is evidence of condensation having formed on the coated surfaces before the cure time had
elapsed, or an amine blush is visually apparent.
3) Where amine blush is indicated by testing, all surfaces coated on that day shall be cleaned to remove
the amine. All amine blush shall be completely removed before application of subsequent coats.
4) Application equipment shall be as recommended by Coating Manufacturer and shall be suitable for
applying the coating as specified.
5) Equipment air supply lines shall be equipped with aftercoolers, knockout pots, or traps to remove
moisture and oil.
6) Compressed air shall be tested to ensure that it is clean and dry per Section 10.4 of this GP.
8. Surface Preparation
1) Prior to the start of work, Contractor shall be responsible for the following:
a) Examining all surfaces to be coated to determine their acceptability for the specified work.
b) Providing immediate written notification to Company if the surfaces are found to be
unacceptable. Contractor shall not commence work on the affected area until corrective action on
the item has been completed.
c) Commencement of work prior to taking corrective action shall preclude any subsequent claim by
Contractor. Company may require corrective action at Contractor's expense.
2) Cleaning and coating shall be coordinated with other fabrication operations. Prior to starting any
cleaning or coating operations, Contractor shall ensure that the surface is ready for cleaning and coating.
3) Areas that may become inaccessible or difficult to paint after erection shall be painted prior to
assembly or erection.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 20 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
4) Internal surfaces of non-galvanized structural shapes, such as tubular structures that are not accessible
for proper preparation and painting, shall be closed from the environment by seal welding. Stitch
welding or skip welding is not permitted. Structures to be galvanized shall be designed and fabricated
with sufficient vents to allow flow of molten zinc into internal surfaces without air pockets.
5) Weld joints in closely spaced pipe and structures shall be abrasive blast cleaned and primed prior to
installing the next layer of pipe or structure, taking appropriate precautions to prevent overblast damage.
6) Assembled mechanical rotating equipment such as turbines shall not be blast cleaned as part of
painting operations and shall be suitably protected from abrasive damage. Turbine intakes shall be
sealed during abrasive blast cleaning and abrasive removal.
7) For the purpose of this GP, the following surface preparation standards shall be deemed equivalent.
Table 1: Surface Preparation Standards
NACE
SSPC
ISO
1
5
Sa 3
2
10
Sa 2½
3
6
Sa 2
8.1.
Pre-Blasting Preparation
1) Oil- and grease-contaminated surfaces shall be cleaned per SSPC SP 1 prior to abrasive blast cleaning.
2) Flame cut edges shall be ground to remove the hard surface layer and to achieve at least a 2 mm
(0.079 in.) radius.
3) All sharp edges shall be processed to achieve at least a 3 mm (0.118 in.) continuous radius. Welds
shall be processed as required to result in smooth ripples and be free of spatter, sharp edges, and
undercutting. Welds in immersion service surfaces shall be processed as required to conform, as a
minimum, to NACE SP0178, Section 5 "Surface Finish Practices," and Appendix C, "Written and
Graphic Descriptions of Various Degrees of Surface Finishing of Welds that May Be Specified in
Preparation for Lining of Tanks and Vessels" Preparation Designation "C."
4) If grinding of welds is required, then such grinding shall be performed in accordance with procedures,
including appropriate precautions, approved by Fabricator of the weld.
5) Weld grinding shall be subject to inspection and/or control by a qualified individual approved by
Fabricator of the weld.
6) [A] Before abrasive blast cleaning, all steel shall be high-pressure water washed with a minimum
pressure of 1,200 kPa (175 psi) using fresh water to remove soluble salt contamination. The salt
concentration on surfaces sampled in accordance with a Company-approved procedure shall not
exceed limits set in Table 2 (see Section 10 of this GP for details).
8.2.
Scaffolding
1) Areas pre-blasted prior to scaffold erection shall be protected against profile knock-down at scaffold
post support points by means of fire retardant compressible material such as rubber sheets.
2) Protruding horizontal and vertical members shall be capped and open ends sealed to minimize blast
dust accumulation.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 21 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
3) Scaffold members shall not be welded to surfaces that will be lined or otherwise coated.
4) Scaffold planks shall be configured to minimize buildup of spent abrasive.
5) Upon completion and acceptance of the abrasive blast, scaffolding connections shall be disassembled
in order to remove all vestiges of trapped abrasive and dust. With dust collectors operating, each
member and joining hardware shall be hammered to dislodge entrained spent abrasive. This is
required to prevent abrasive from subsequently falling into uncured coating/lining material.
Scaffolding levels shall be reconfigured as necessary to facilitate coating application.
6) Scaffolding shall remain in-place until the work of all other disciplines requiring access to the
scaffolding has been completed and until application and all required inspection is complete and any
associated repairs have been made.
7) Dismantling shall be done one level at a time to facilitate touch-up.
8) Precautions shall be taken to protect existing coating work from damage during dismantling of the
scaffolding. This shall include protective coverings as needed. A qualified painter shall be present
throughout the scaffold removal process to repair damage and to prepare and coat previously
inaccessible spots such as post contact areas.
8.3.
Abrasive Blast Cleaning
1) Surfaces to be coated shall be abrasive blast cleaned per the requirements of Table B–1.
2) Surface profile shall be in accordance with Table A–3. The profile shall be measured using any of the
devices defined in the ISO 8503 (BSI BS EN ISO 8503) series of standards or ASTM D 4417. Only
the profile measurement device that is appropriate to the blast media used shall be utilized.
3) No acid wash or other solvent cleaning solutions shall be used after blast cleaning or fresh water
washing. This includes inhibitive solutions intended to prevent rust.
8.3.1.
Compressed Air
1) Compressed air shall be clean, dry, and oil-free.
2) Traps (in addition to oil and water extractors mounted on the compressor) shall be used in compressed
air lines to remove oil and moisture from air close to the point of use. The traps shall be emptied at least
once per shift or more frequently if necessary to maintain air quality.
3) The compressed air shall be tested per the requirements of Table 2.
8.3.2.
Protecting Other Equipment
1) Blast cleaning shall not be performed in the immediate area where application or curing of coating is
in progress.
2) All surfaces and equipment not to be coated shall be suitably protected from blast cleaning, including
fasteners factory-coated per GP 56-02-13.
8.3.3.
Repairs
Burrs, slivers, scabs, sharp edges, and weld spatter, which become visible after blasting, shall be removed
per the requirements of Section 8.1.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 22 of 67
GP 56-02-02
8.3.4.
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Cleaning
1) The final surface preparation shall not commence if the substrate surface temperature is less than 3 °C
(5 °F) above the air dew point, if the surface is wet, or if there is a possibility that the surface will be
subject to wetting before the first coat of the specified system can be applied.
2) For work being performed outside an enclosure or building where the temperature and humidity are
being controlled the specified coating shall be applied within 4 hours of blast cleaning. For work
inside an environmentally controlled enclosure or building, the period can be extended. In either
case, the coating must be applied before any deterioration of the prepared surface is visible. If the 4
hour criterion above is exceeded, if visible rusting occurs, or if the cleaned surface becomes wet or
otherwise contaminated, then these surfaces shall be re-blasted to the degree specified in Table B–1.
3) [A] After cleaning and immediately before coating, dust shall be removed with clean, dry, oil-free
compressed air. Vacuuming shall be used also if the surface is not dust free. Company approval of
final surface cleanliness is required.
4) Machined surfaces shall be cleaned in accordance with SSPC SP 1 before the application of
temporary protective coating.
8.3.5.
Protecting Machined Surfaces and Openings
1) Machined surfaces shall be protected from damage due to cleaning and coating operations.
2) The machined portion of pipe flange mating faces shall be masked to protect the gasket surface and
internal components. The remaining part of the flange face (including bolt holes) shall then be blast
cleaned and coated.
3) Equipment shall have all openings temporarily plugged, masked, and/or blinded before abrasive
blasting. Protection, as well as any contamination that has entered, shall be removed by Contractor
after the coating application is completed.
4) [S] Contractor shall implement a procedure for tracking the installation of temporary masking, blinds,
and plugs to ensure that they are removed at the end of the coating works.
8.4.
Steel That Has Been Shop Primed Only
[R] Unless specified by Company SME, shop primers shall be removed prior to coating per Appendix A–1.
If shop primer is allowed to remain, then sweep blasting shall be required prior to overcoating.
8.5.
Power Tool Cleaning
1) [A] Only the types of surface preparation tools and materials identified in the approved WCP shall be
used. Surfaces for preparation using power tool cleaning rather than abrasive blast cleaning shall be
identified beforehand in the WCP and approved by Company before work starts.
2) The only acceptable power tool alternative to abrasive blast cleaning is SSPC SP 11.
3) Power tools used to clean carbon steel shall not be used to clean stainless steel. Metals contacting
stainless steel in the process of power tool cleaning shall be CRA, not carbon steel.
8.6.
Galvanized Steel
1) Requirements for Hot-Dip Galvanizing (HDG) shall be per GP 29-02-19 and are covered in
procurement documents for the item. Except for stair treads and grating, galvanized surfaces for
which painting is required shall be painted as detailed in Appendix A of this GP.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 23 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
2) Before coating, galvanized surfaces shall be cleaned with a 5–71/2% aqueous ammonia solution and
flushed with potable water. Alternatively, cleaning may be done with an alkaline detergent followed
by pressure washing at a minimum pressure of 20 MPa (2,900 psia) with warm/hot potable water.
Subsequent to cleaning, sweep blast (per SSPC SP 16) using a fine abrasive (U.S. standard sieve size
#80–120) at a reduced pressure 275 kPa (40 psia).
3) Repair of galvanized steel is covered in Section 11 of this GP.
4) [S] Hollow components shall be designed to provide proper venting of all sections during HDG.
9. Mixing and Applying Coatings
9.1.
Mixing
1) Mixing, thinning, applying, and curing of the coating material shall be in accordance with Coating
Manufacturer's latest published instruction; if conflicts are found between these requirements, then
written direction from Company shall be sought.
2) Before mixing, all coating precursors shall be between 15 C (59 ºF) and 32 ºC (90 ºF) or at a
temperature recommended by Coating Manufacturer.
3) Before application, mixed components shall be allowed to complete Coating Manufacturer's
recommended induction time.
4) Only previously unopened complete kits shall be mixed. No partial kits shall be allowed at any time.
5) [A] Only thinners, diluents, and retardants from the same Manufacturers as the specified coating shall
be used for that coating. These shall only be used at the rate recommended by Coating Manufacturer
for the specific application and only where necessary for proper application.
6) Coatings prepared in their original containers shall not be transferred until all settled solids are
incorporated.
7) Coating materials shall be thoroughly mixed until they are smooth and free from lumps, then strained
through a 595 m (30-mesh), or finer, screen.
8) Coating materials shall be agitated as necessary to keep the solids in suspension during application.
Zinc-rich coatings shall be mechanically agitated at all times.
9) Manufacturer's induction time for the coating shall be strictly observed based on the coating material
temperature. The mixed components shall not be applied until the induction time has passed.
10) The pot life of any paint shall be carefully noted, and any mixed paint that has exceeded pot life shall
be discarded regardless of apparent condition.
9.2.
Preparation
1) No coating material shall be applied closer than 100 mm (4 in.) from adjacent non-cleaned or nonabraded surfaces.
2) The application of the coating shall be performed only when the environmental conditions meet the
parameters specified in Section 7 of this GP.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 24 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
3) Immediately prior to coating, the prepared surface shall be in compliance with the surface cleanliness
criteria defined in Section 8 of this GP.
4) Enclosures to permit coating of surfaces during inclement weather may be used, provided the
environmental restrictions specified are maintained throughout the coating and curing periods.
5) Where the environment is being artificially controlled within an enclosure, the temperature and
humidity within the enclosure shall be continually monitored and recorded at a period no greater than
15 minutes. The record shall form part of the daily report.
9.3.
Application—General
9.3.1.
Intercoat Considerations
1) Overcoats and topcoats shall be applied within Coating Manufacturer's recoat times. Contractor shall
provide a WCP for reworking coating that has exceeded the maximum overcoat window including
coating compatibility testing per Table 2.
2) IOZ coatings shall be cured and demonstrate an average resistance rating of not less than 4 when
evaluated per ASTM D 4752. To achieve full cure additional time and increased humidity may be
required for IOZ primer applied in dry weather.
3) Substrate and prior coat surfaces shall be verified to be suitably dust free by assessing per ISO 8502-3
(BSI BS EN ISO 8502-3). Rating shall be 2 or better.
4) [A] Where equipment manufacturer's standard finishes are inadequate, upgrading by overcoating may
be considered subject to Company written approval. Prior to and as a condition for overcoating,
compatibility shall be established by means of the patch test described in Table 2 (see Section 10 of
this GP for details).
9.3.2.
Dry Film Thickness
1) Dry Film Thickness (DFT) of each coating shall be within the minimum and maximum specified in
Table B–2 of this GP. If additional coats are required to achieve the specified DFT, then they shall be
applied at no additional cost to Company and in accordance with Coating Manufacturer's recoating
instructions and the dry-film thickness restrictions.
2) DFT that exceed the nominated DFT in Table B–2 by less than three times shall be visually inspected
for runs, sags and other imperfections. In the absence of defects, no remedial action is required for
these coatings. However, regardless of the visual appearance, DFT in excess of three times the
nominated DFT in Table B–2 shall be replaced to full specification requirements following total
removal to the requirements of SSPC SP 10. Areas receiving a stripe coated shall be exempt from
this requirement.
3) The following requirements apply for IOZ primer applied outside the thickness range indicated in
Table B–2:
a) Excessive thickness shall be reduced by hand abrading.
b) Primer of insufficient thickness shall be completely replaced to full specification requirements
following total removal to the requirements of SSPC SP 10.
4) Upon completion of corrective actions, coating thickness shall be re-inspected to confirm that it is
within the specified range in Table B–2.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 25 of 67
GP 56-02-02
9.3.3.
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Equipment
1) Coating shall be applied using only equipment recommended by Coating Manufacturer's PDS. The
equipment shall be clean and regularly serviced in line with the equipment manufacturer's requirements
and must perform within the equipment manufacturer's tolerances.
2) Spray tips shall be regularly inspected to ensure that they meet the specification stated on the
published Coating Manufacturer's datasheet. Spray tips shall not be modified or remanufactured to
meet these requirements and shall be as supplied by the equipment manufacturer. Tips worn beyond
the stated specification shall be immediately discarded.
3) With the exception of stripe coats, conventional or airless spray is the preferred application method
for liquid coatings. Stripe coats shall be applied by brush only with the coating thoroughly worked in
around edges. See Section 9.3.7 for details.
4) Paint brushes and rollers shall be compatible with the coating material and only used if an approved
application method in Manufacturer's PDS. Application shall be interrupted if there is visual
evidence of bristles or roller lint contaminating freshly applied coating. Brushes/rollers shall be
replaced. If the problem persists, then Coating Manufacturer shall be consulted for recommendations
as to the appropriate equipment.
5) Heating, air-conditioning, or dehumidification equipment may be required to meet the requirements
of this GP (refer to Section 7 for details) and to achieve the agreed-upon schedule.
9.3.4.
Surface Damage/Imperfections
1) Runs, sags, voids, drips, overspray, loss of adhesion, blistering, peeling, mudcracking, inadequate
cure, or rusting of the substrate shall not be permitted.
2) Where shop coating has been damaged in transit or where damage has occurred to field coats, the
following shall apply:
a) All damaged and loosely adhering coating shall be removed and the surface thoroughly cleaned.
b) Edges of the breaks shall be feathered and the designated number of prime, intermediate, and
finish coats applied. The requirements of Section 11 of this GP shall apply when making repairs.
c) The finish coat for repairs shall match the original color and gloss.
3) Damaged coatings shall be retouched before succeeding coats are applied.
9.3.5.
Color
1) The specific topcoat color for a given surface should be as indicated in Appendix A of this GP unless
otherwise identified in the project specific documentation.
2) Contractor shall bring to the attention of Company if the proposed color scheme contravenes local
regulatory requirements at the point of project installation.
3) The color of successive coats shall vary slightly from the color of preceding coats to permit easy
identification without affecting finish color.
9.3.6.
Stainless Steels
1) Paints containing low melting point metal pigments such as lead, cadmium, or zinc shall not be used
to overcoat stainless steel materials. Such paints shall not be applied in proximity to stainless steel
where the stainless steel could be contaminated.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 26 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
2) Overspray protection shall be provided as required.
9.3.7.
Stripe Coats
1) All welds, threads, nuts, crevices, and sharp edges shall receive at least one stripe coat applied by
brush. If the stripe coat manifests visible holidays, then a second stripe coat shall be applied.
2) Welds, edges, crevices, nuts, and threads in lined tanks shall receive two brush-applied stripe coats.
3) Stripe coating shall be done with material specified for the second coat before spray application of the
second coat.
9.3.8.
Overcoating Inorganic Zinc Primer
1) Application process variables such as the applied thickness and RH will influence the thoroughness of
the cure. Special techniques may be needed to promote cure under adverse conditions. For example,
water misting or steam is sometimes used to compensate for dry, windy conditions.
2) Full cure must be achieved before IOZ primer is overcoated. Demonstration of cure by solvent rub
may be required.
3) Coatings to be applied over IOZ primer shall first be applied as a mist coat followed by a full coat of
the specified material.
9.3.9.
Air/Soil Interface
Refer to GP 59-01-12 for air/soil interface requirements.
10. Inspection and Testing
10.1.
Responsibility
1) Contractor shall control the quality of items and services to meet the requirements of the applicable
codes and standards and other requirements of this GP.
2) Documentation shall be prepared and maintained to provide evidence of compliance with Companyapproved procedures and this GP.
10.2.
Personnel Qualification
1) Personnel performing inspection or verification shall have a minimum of 5 years experience in
similar projects. A minimum of one Site Inspector shall hold current certification in accordance with
one of the following:
a) SN NS 476 (Inspector Level)
b) Certified NACE Coating Inspector, Level 3
c) Level II qualification requirements described in SSPC QP 5, Section 6, "Personnel"
d) FROSIO Level III
e) An equivalent qualification recognized by Company
2) [A] Any other coating inspector on site shall have a minimum of 5 years experience in similar projects
and hold at least a NACE Level 1 (or Company-approved equivalent) coating inspector certification.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 27 of 67
GP 56-02-02
10.3.
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Contractor's Responsibilities
1) Contractor and Contractor's Vendors and Subcontractors shall grant Company Inspectors unimpeded
access to inspect all work performed by Contractor, Vendors, and Subcontractors.
2) Contractor shall not initiate any painting activities subject to the inspections listed in Table 2 without
prior notification and the onsite presence of Company Inspector.
3) The inspections listed in Table 2 shall be understood to be "hold points."
4) [A] Upon completion, the work shall be subject to final inspection, review, and sign-off, in
accordance with the project requirements.
5) Contractor shall furnish the necessary testing and inspection instruments. Inspection instruments
shall be properly calibrated and maintained. Such equipment shall be available for use by Company
in conducting surveillance of the work.
6) Inspection activities shall be documented on a form similar to Company Data Sheet I560202C01.
10.4.
Compressed Air Quality Test
1) Prior to using compressed air, the quality of the air downstream of the separator shall be tested in
accordance with ASTM D 4285.
2) This test shall be performed at the frequency indicated in Table 2. At the beginning of each shift, a
blowdown interval of 60 seconds shall be allowed prior to performing the test, during which time the
air stream shall not be directed at work surfaces.
3) This test also shall be made after any interruption of the air compressor operation or as required by
Company.
4) The air shall be used only if the test indicates no visible contamination, oil, or moisture. If contaminants
are evident, then the equipment deficiencies shall be corrected and the air stream shall be retested.
5) Separators shall be bled continuously.
6) All compressed air lines shall be tested individually prior to use.
7) Surfaces determined to have been blasted or blown down with contaminated air shall be cleaned of
that contamination per SSPC SP 1 and reblasted with clean air and abrasive.
10.5.
Nonconformance Report
1) Work found unacceptable by Company shall be promptly corrected in accordance with this GP.
2) In accordance with the Project Execution Plan, within 36 hours of discovery, Contractor shall submit
a Nonconformance Report to Company identifying any defect and detailing the repair procedure.
3) Any defects disclosed by inspection shall be reinspected after correction.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 28 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Table 2: Inspection and Testing Plan
Test Type
Method
Frequency
Acceptance
Criteria
Consequence
Environmental
Conditions
Ambient and steel
temperature
At the work location
before start of each
shift + minimum
twice per shift
In accordance
with specified
requirements
No blasting or
coating
SSPC AB 1
Each 10,000 kg
(22 ton), or
manufacturing batch,
whichever is less
Qualification and
conformance
testing per SSPC
AB 1, Section 5
No blasting or
coating
SSPC AB 2
Each 15,000 kg
(33 ton), or
manufacturing batch,
whichever is less
Qualification and
conformance
testing per SSPC
AB 2, Section 4
and Section 5
ASTM D 4285
Before start of each
shift or change in
compressed air
source and at 4 hour
intervals thereafter
Per the Standard
(No visible
contamination)
RH
Dew point
Testing and
Certification
of Abrasive
Materials
Compressed
Air Quality
Service, clean,
and replace
hoses, filters,
Knockout pots,
aftercoolers.
Pressure wash
with cleanser
and reblast
contaminated
surfaces.
Visual
Examination
Visually, for sharp
edges, weld spatter,
slivers, rust grade,
etc.
100% of all surfaces
No defects; refer
to specified
requirements
Defects to be
repaired
Surface
Cleanliness
(a) SSPC VIS 1 or
ISO 8501 (BSI BS
EN ISO 8501)
(a) 100% visual of all
surfaces
(a) In accordance
with specified
requirements
(a) Re-blasting
(b) ISO 8502-3 (BSI
BS EN ISO 8502-3)
(b) Spot checks, but
not less than 1 per 10
m² (100 ft2)
(b) Max quantity
and size rating 2
(b) Recleaning and
retesting until
acceptable
a) Visual
b) For dust
Specific location to
be determined by
Company Inspector
UPST, PL
© ExxonMobil 2018
TEC5000
Page 29 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Test Type
Method
Frequency
Acceptance
Criteria
Consequence
Soluble Salts
Extraction:
(a) Immersion
surfaces (includes
underwater
insulation):
(a) Average
conductivity
corresponding to
 20 mg/m2
(2 μg/cm²) and
maximum
conductivity
corresponding to
 30 mg/m2 water
soluble salts.
Steam or clean
water washing
and retesting
until entire
2,000 m2
(21,500 ft2)
test area is
acceptable
ISO 8502-6 (BSI BS
EN ISO 8502-6)
(Bresle)
Assessment:
ISO 8502-9 (BSI BS
EN ISO 8502-9)
(Conductometric)
Or
6 samples/2,000 m2
(21,500 ft2) of
fabrication
Specific location to
be determined by
Company Inspector (1)
Extraction:
SSPC GUIDE 15,
Section 4.6, Filter
Paper Extraction
Method
(Elcometer 130 SC
400)
Assessment:
SSPC GUIDE 15,
Section 5.3, Field
Procedure for
Analyzing Filter
Paper for Soluble
Salts
(b) (Conductometric)
(b) Atmospheric
Surfaces:
4 samples/2,000 m2
(21,500 ft2) of
fabrication
Specific location to
be determined by
Company Inspector (1)
Roughness
UPST, PL
Per ASTM D 4417 or
ISO 8503 (BSI BS
EN ISO 8503)
Each component, or
once per 10 m2
(100 ft2)
© ExxonMobil 2018
(b) Average
conductivity
corresponding to
 30 mg/m2 and
maximum
conductivity
corresponding to
 40 mg/m2 water
soluble salts
As specified
TEC5000
Re-blasting,
using coarser
or harder
abrasive and/or
more nozzle
pressure.
Page 30 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Test Type
Method
Frequency
Acceptance
Criteria
Consequence
Extent of
Intercoat Cure
Perform solvent rub
test to ensure:
Perform 3 tests per
500 m² (5,000 ft2) of
surface to be coated
(a) Average
resistance rating
not less than 4
(a)
Inadequately
cured IOZ:
(a) IOZ is fully cured
per ASTM D 4752
Take action to
enhance level
of cure (e.g.,
water misting).
If ineffective,
remove and
reapply
inadequately
cured IZ.
(b) Epoxy for
immersion, splash
zone exposure, or
under insulation is
recoatable per ASTM
D 5402. Unless
otherwise instructed,
in writing, by
Coating
Manufacturer,
perform 50 double
rubs using Methyl
Ethyl Ketone (MEK.)
Presence of
Amine
UPST, PL
ASTM D 2106
(b) Discoloration
shall be visible on
the rub cloth, or
Thumbnail
indentation at the
center of the rub
path shall be
possible, or
(b) Overcured
Epoxy:
Sweep blast
using reduced
nozzle
pressure and
fine abrasive
Reduction in gloss
shall be visually
discernible.
According to Section
7 and Section 9
requirements
© ExxonMobil 2018
No amine blush
present
TEC5000
Remove amine
blush before
application of
next coat
Page 31 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Test Type
Method
Frequency
Acceptance
Criteria
Consequence
Compatibility
Apply test patch and
test per ASTM D
3359, Method A for
coatings with a DFT
<300 µm (12 mils) or
ASTM D 6677 for
coatings =>300 µm
(12 mils). Patch may
be as small as 200
cm2 (31 in.2). Apply
first coat of overcoat
system only.
One for each
component coated
with Vendor
standard, except one
in 25 for identical
components.
As established by
Coating
Manufacturer of
the overcoats
Remove
incompatible
coating before
applying
specified
system from
Appendix A.
Use liquid
stripper or
SSPC SP 11
Visual
Examination
of Coating
Visual to confirm
absence of
contamination,
solvent
pinholes/popping,
sagging, or other
surface defects
100% of surface after
each coat.
According to
specified
requirements
Repair of
defects
Holiday
Detection
ASTM D 5162
Method A
Tank surfaces
accessible without
scaffolding plus
surfaces that will be
in the splash zone.
No holidays
Repair and
retesting.
Film
Thickness
SSPC PA 2—
calibrate on smooth
surface
Per SSPC PA 2
SSPC PA 2 and
Table B–2 of this
GP.
Repair,
additional
coats, or
recoating as
appropriate.
Adhesion
ISO 4624 (BSI BS
EN ISO 4624) or
ASTM D 4541 using
a self-aligning
device, and
performed when
systems are fully
cured
Spot checks
Minimum 5 MPa
(725 psi) for
epoxy;
Coating to be
rejected
(With Vendor
Standard
Coating)
UPST, PL
© ExxonMobil 2018
Minimum 3 MPa
(435 psi) for zincprimed systems
TEC5000
Page 32 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Notes for Table 2:
(1)
To prevent subsequent contamination of abrasive, salt contamination of received plate shall be
verified by testing of top and bottom stacked plates for each shipment. Additional plate testing
and cleaning may be required. No plate shall indicate an average contamination exceeding the
limit stipulated in this Table for the applicable service.
11. Remedial Work
11.1.
General Repair
1) Coated surfaces within the scope of this GP that are damaged during assembly or handling shall be
repaired in accordance with procedures accepted by Company, using the same system as that being
repaired.
2) The surface shall be restored to meet the specified surface preparation requirements for cleanliness
and profile.
3) As indicated in Figure 1, successive coats of multicoat systems shall be "stepped" outward onto the
preexisting coating from the bare metal. The repair area may be rectangular or square depending on
the dimensions of the exposed metal and shall be accomplished in no fewer than two masking steps.
4) The coating to be overlapped shall be abraded and edge-feathered into the adjacent bare spot.
5) Feathering and surface abrasion shall be accomplished by hand sanding or by abrasive blasting using
reduced nozzle pressure per the WCP or in Coating Manufacturer's written procedure/application notes.
6) A "fringe" of abraded original coating will be visible when the masking is removed. The top coat
while abraded shall be intact.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 33 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Figure 1: Repair Sketch
Y
X
X
D
B
C
A
Legend:
A - Boundary of typical holiday or damage spot with feathered edges of existing coating system
B - Limit of first masking (1st coat of 2-coat system or 1st and 2nd coat of 3- or 4-coat system)
C - Limit of second masking (subsequent coat(s) of 2-, 3-,and 4-coat systems)
D - Visible boundary of abraded surface of existing coating
X = 15 mm (0.6 in.) minimum, 25 mm (1.0 in.) maximum distance between boundaries
Y = 5 mm (0.2 in.) minimum, 15 mm (0.6 in.) maximum distance between boundaries
11.2.
Repair of Immersion Coatings and Linings
In addition to the general repair requirements listed in Section 11.1, the following repair criteria apply:
1) Where holiday testing of linings reveal pinholes, the lining at the affected spots shall be removed with
a rotary burr to expose the substrate.
2) Vacuum blast-type equipment and masking shall be used to prevent damage to adjacent coated areas.
3) Profile needs to be restored after the coating is removed.
11.3.
Damaged Repair of Hot-Dip Galvanizing
11.3.1.
Minor Damage
For repair of welds and minor damage less than 0.1 m2 (155 in.2), the following requirements shall apply:
1) Feather edge of intact galvanized surface.
2) Upon completion of appropriate surface preparation as stated in Table B–1, apply one of the
following coating systems.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 34 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Table 3: Coating Systems for Minor Galvanizing Repairs
Color Topcoat
Coating System
Not required or not specified
R
Required
O or M
3) Alternative "cold galvanizing" paints may be used for repair of minor damage provided that the
product contains with concentrations by weight of zinc dust in the range of 65 to 69% in the liquid
product, or above 92% in the dried film, as specified in ASTM A 780/A 780M.
11.3.2.
Major Damage
For major galvanized repair larger than 0.1 m2 (155 in.2), use the following instructions:
1) Feather edge of intact galvanized surface.
2) Upon completion of appropriate surface preparation as stated in Table B–1, apply one of the
following coating systems.
Table 4: Coating Systems for Major Galvanizing Repairs
UPST, PL
Color Topcoat
Coating System
Not required or not specified
G or M
Required
O or M
© ExxonMobil 2018
TEC5000
Page 35 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Appendix A: Coating Schedule/Matrix
A–1. Corrosivity Classifications
1) Table A–1 describes the geographical set of conditions used to select the correct corrosivity class for
coating systems regarding offshore/coastal versus onshore/inland from the selection tables.
2) [A] Some construction projects will consist of both onshore and offshore portions, which span two or
more classification categories. In these cases, the default coating classification shall be the most
severe category, with exceptions granted on an individual basis. Final designation of corrosivity
classification for purposes of coating selection requires Company approval
Table A–1: Corrosivity Classifications per BS EN ISO 12944-2
BSI BS EN ISO 12944-2 Simplified Corrosivity Categories and
Relevant Summary Descriptions
Typical Company
Example
CX. Extreme.
Offshore Africa,
Malaysia
Offshore areas with high salinity and subtropical to tropical climate
Industrial areas with extreme humidity and aggressive atmosphere
C5. Very high.
Offshore Gulf of
Mexico, Australia
Offshore, temperate to sub-tropical climate
Onshore coastal (within 1 km [0.65 mile] of waterfront) in tropical climate
Onshore Africa
Humid coastal/inland environments subject to high deposition rates of
wind-borne chlorides
C4. High.
Onshore coastal (within 1 km [0.65 mile] of waterfront) in temperate
climate
Offshore subarctic
Tropical inland areas subject to high deposition rates of wind-borne
chlorides
C3. Medium.
Onshore coastal Gulf of
Mexico
Offshore Sakhalin Island
and Canada East
Onshore coastal
Sakhalin Island and
Canada East
Subarctic coastal (within 1 km [0.65 mile] of waterfront)
Offshore Arctic
Non-coastal urban/industrial in tropical or temperate climate
Onshore inland
Indonesia
C2. Low.
Germany (inland)
UPST, PL
© ExxonMobil 2018
TEC5000
Page 36 of 67
GP 56-02-02
Painting General Requirements for New Construction
BSI BS EN ISO 12944-2 Simplified Corrosivity Categories and
Relevant Summary Descriptions
V 4.2.0
DEC 2018
Typical Company
Example
Dry rural areas and regions remote from the coast or sources of pollution
Arctic coastal environments
North Slope Alaska
C1. Very Low.
LaBarge, Wyoming
Unpolluted inland alpine or arid regions.
Inside Heating,
Ventilation, and Air
Conditioning (HVAC)
modules, any location
Indoor controlled environment
Table A–2: Corrosivity Classifications by Generic Environment Descriptions
Tropical
Temperate
Subarctic
Arctic
Offshore
CX
C5
C4
C2
Coastal
C5
C4
C3
C2
Inland
C4
C3
C2
C1
Arid
C2
C2
C1
C1
HVAC
C1
C1
C1
C1
UPST, PL
© ExxonMobil 2018
TEC5000
Page 37 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
A–2. Coating Schedule/Matrix
1) All temperatures noted in this schedule shall be anticipated operating conditions, not design
conditions.
2) Equipment and piping requiring steam-out, dry-out, or regeneration shall be painted with coatings
having a heat resistance capable of withstanding the conditions.
3) Refractory-lined items such as heaters and stacks shall be painted in accordance with calculated cold
face temperatures.
Table A–3: Coating Schedule/Matrix
System Code for
Corrosivity Class
BSI BS
EN ISO
12944-2
C4-CX
Items
Offshore
and
Coastal
BSI BS
EN ISO
12944-2
C1-C3
Remarks
Inland
Onshore
1.0
Structural Steel – Topside or Onshore
1.1
Flare boom and Radio
A or C
Towers to 80 C (175 F)
1.2
Flare boom above 80 C
(175 F)
D or E
1.3
Carbon Steel Helideck
A or C
1.4
Aluminum Helideck
1.5
Crane structure
1.6
Beneath Cementitious Fireproofing
1.6.1
Structural Steel
UPST, PL
Finish Coat Color (1)
Aviation Hazard ID per
Local Aviation
Authority
Notes 3, 6
Aviation Hazard ID per
Local Aviation
Authority
Note 15
—
Colors and marking per
Local Aviation
Authority. See GP 2501-13 for details.
Note 14, 17
P
—
Colors and marking per
Local Aviation
Authority. See GP 2501-13 for details.
Note 14
A or C
M or F
Yellow, RAL 1004
Note 6
B
© ExxonMobil 2018
M or F
Note 7
—
No color requirement
TEC5000
—
Page 38 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
System Code for
Corrosivity Class
BSI BS
EN ISO
12944-2
C4-CX
Items
Offshore
and
Coastal
1.7
Columns, beams, girders, A or C
trusses, channels,
bulkheads, deck bottoms,
or other structural
members
BSI BS
EN ISO
12944-2
C1-C3
Finish Coat Color (1)
Remarks
Gray, RAL 7038
Galvanized (GP
29-02-19)
Inland
Onshore
HDG or
G
Code G (GP 5602-08)
Notes 3, 6
1.8
Deck, top surface,
Laydown decks
A or C
—
Gray, RAL 7038
Note 14
1.9
Escape walkways
A or C
—
Yellow, RAL 1004
Note 14
1.10
Galvanized Steel
H
No color requirement
—
1.10.1
Assembled galvanized
structures, including
bolts, (only where color
is required)
As specified
Notes 3, 6
H
Galvanized grating, stair
treads and threaded
galvanized piping
HDG only
1.10.2
1.10.3
1.10.4
1.10.5
UPST, PL
Galvanized deck plate
(Checker plates are not
allowed) and ladder
rungs
Per GP 29-02-19
Gray, RAL 7038
Note 14
Safety Yellow, RAL
1004
—
H
Galvanized ladders,
cages, platforms, and
handrail assemblies, all
surfaces
H
Galvanized cable trays
—
© ExxonMobil 2018
HDG only
—
TEC5000
Page 39 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
System Code for
Corrosivity Class
BSI BS
EN ISO
12944-2
C4-CX
Items
Offshore
and
Coastal
1.11
Corrosive solids handling —
service (e.g., conveyers
and stacker/reclaimers,
sulfur granulators, and
sulfur bulk storage
sheds.)
Columns, beams, girders,
trusses, channels, girts
and purlins or other
structural members
including ladders, cages
and handrails
2.0
BSI BS
EN ISO
12944-2
C1-C3
Finish Coat Color (1)
Remarks
—
—
Inland
Onshore
W
In-water/over-water structures including berths, piers, moorings,
jetties, bulkheads, pipe racks, and access walkways. OR
—
Splash Zone ([*] From +5 m (16 ft) to −5 m (-16 ft) [See project
definition.])
2.1
Columns, beams, girders,
struts, or other structural K
members in water
Coating Manufacturer's
Standard Gray (for
system K only)
Notes 7, 12
2.2
Columns, beams, girders,
struts, or other structural
D
members over water in
splash zone
No color requirement
Notes 7
2.3
Driven "H", sheet and
pipe piles
No color requirement
Notes 12, 19
3.0
Submerged Zone (all surfaces below splash zone)
3.1
Columns, beams, girders,
struts, or other structural K
members
UPST, PL
K
© ExxonMobil 2018
No color requirement
TEC5000
—
Notes 7, 12
Page 40 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
System Code for
Corrosivity Class
BSI BS
EN ISO
12944-2
C4-CX
Items
Offshore
and
Coastal
4.0
BSI BS
EN ISO
12944-2
C1-C3
Finish Coat Color (1)
Remarks
Inland
Onshore
Topsides and Onshore Equipment and Piping (excluding tanks)
Note 8
Fabricated Piping and Supports including Risers above splash zone,
Valves, Wellheads for all areas except splash zone
Vessels and Heat Exchangers; External Surfaces (shop primed and
topcoated after assembly and testing)
Pumps, Compressors, and Rotating Equipment; External Surfaces
4.1
Carbon Steel
4.1.1
Risers - splash zone to
Emergency Shutdown
Valve (ESV), operating
temperature < 90 C
(195 F)
Polychlo
roprene
per GP
56-02-07
or TSA
per GP
56-02-08
Risers - splash zone to
ESV, operating
temperature > 90 C (195
F)
Monel
cladding
or
sheathing
, or TSA
per GP
56-02-08
4.1.3
Risers - above the ESV
per piping
4.1.4
Supports, including shoes A or C
4.1.5
Uninsulated structural
members, piping,
equipment, wellheads to
80 °C (175 F)
A or C
M or F
Uninsulated, 80–400 °C
(175–750 F) – onshore
or above splash zone
D
E
4.1.2
4.1.6
4.1.7
UPST, PL
Note 7
No color requirement
Note 11
No color requirement
Note 11
—
—
—
M or F
Gray, RAL 7038
Gray, RAL 7038
Uninsulated to 80 °C
(175 F) – in splash zone D or K
excluding Risers
© ExxonMobil 2018
—
Note 8
For E, Coating
Notes 8, 15, and
Manufacturer's Standard 24
Color
—
Coating Manufacturer's
Standard Color (for K)
TEC5000
Notes 8, 15, and
24
Page 41 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
System Code for
Corrosivity Class
BSI BS
EN ISO
12944-2
C4-CX
Items
Offshore
and
Coastal
4.1.8
Uninsulated, 80–400 °C
(175–750 F) – in splash
zone excluding Risers
BSI BS
EN ISO
12944-2
C1-C3
Finish Coat Color (1)
Remarks
No color requirement
Note 8
Safety Red, RAL 3000
Note 8
Inland
Onshore
—
D
4.1.9
Fire water lines and
firefighting equipment
onshore or above splash
zone
4.1.10
Insulated piping, to 80 °C
(175 F) onshore or
I
above splash zone
(except sweating service)
No color requirement
Notes 25, 31
4.1.11
Insulated pressure
vessels, to 80 °C (175 F)
onshore or above splash D
zone (except sweating
service)
No color requirement
—
4.1.12
Insulated, to 80 °C
(175 F) and in sweating
service
No color requirement
Note 31
No color requirement
Note 25
No color requirement
Notes 25
4.1.13
A or C
M or F
D
Insulated, 80–400 °C
(175–750 F) onshore or
above splash zone
D
Insulated, Cyclic Service
onshore or above splash
zone
D
4.1.14
Insulated in splash zone
Consult Company Coating SME
—
4.1.15
Underground piping
K
No color requirements
Note 26
4.1.16
Vertical Pump, Inside
Diameter (ID), and
Rotating Parts, Including
Alloy
No color requirements
Notes 8, 24
K
Pump Caisson Outside
Diameter (OD)
K
No color requirements
Notes 8, 24
4.1.13
4.1.17
UPST, PL
© ExxonMobil 2018
TEC5000
Page 42 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
System Code for
Corrosivity Class
BSI BS
EN ISO
12944-2
C4-CX
Items
Offshore
and
Coastal
4.1.18
Splash Zone Portion of
Pump Caisson OD (See
2.0 in this table for
details.)
4.2
Stainless Steel (all grades)
4.2.1
Uninsulated to 65 °C
(150 F)
Finish Coat Color (1)
Remarks
No color requirements
Notes 8, 24
Inland
Onshore
K
Notes 7, 10, and
16
P
4.2.2
Insulated, -200 to 0 C (240–32 F)
J
4.2.3
Insulated, 0–65 C (32150 F) including
sweating service
I
4.2.4
BSI BS
EN ISO
12944-2
C1-C3
No
coating
required
Uninsulated/Insulated
with an operating
temperature of:
Coating Manufacturer's
Standard
Notes 8, 28
No color requirements
Note 28
No color requirements
Notes 28, 31
No color requirements
—
Austenitic SS, 65–150 °C
(150–300 F) or in cyclic
service.
Duplex SS, 110–150 °C
(230–300 F)
D
Super Duplex SS, 120–
150 °C (250–300 F)
6Mo Superaustenitic SS,
130–150 °C (265–
300 F)
4.2.5
UPST, PL
Uninsulated or Insulated
Continuously op temp >
150 °C (300 F)
—
No coating required
© ExxonMobil 2018
TEC5000
Page 43 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
System Code for
Corrosivity Class
BSI BS
EN ISO
12944-2
C4-CX
Items
Offshore
and
Coastal
BSI BS
EN ISO
12944-2
C1-C3
Finish Coat Color (1)
Remarks
Inland
Onshore
4.2.6
Uninsulated/Insulated (all
temperatures – except in
sweating service) located No coating required
within an HVAC
controlled module
Notes 8, 9, 20,
24, and 25
5.0
Electric Motors and Other Equipment
Notes 5, 8
Instrument and Control Panels
5.1
Carbon steel
Manufacturer's
Coating Manufacturer's
three-coat system (if Standard
equivalent to system
M or F) with a total
DFT of 250 m (10
mils) minimum
5.2
Stainless Steel
No coating required
6.0
Tanks and Sumps
6.1
Carbon Steel External Surfaces
6.2
Aboveground uninsulated A or C
and not under Epoxy
Passive Fire Protection
6.3
Z
6.4
Aboveground insulated,
to 80 °C (175 F)
I
6.5
Aboveground insulated,
80–400 ºC (175–750 F)
D
6.6
Aboveground insulated,
Cyclic or Sweating
Service
D
Below ground
K
UPST, PL
—
Notes 7, 8, and
21
Uninsulated with
Intumescent Passive Fire
Protection
6.7
Note 23
© ExxonMobil 2018
—
M or F
Nonvolatile Products:
Gray, RAL 7038
Notes 8, 9, and
20
Volatile Products:
White, RAL 9002
No color requirement
Note 3
No color requirement
Notes 25
No color requirement
Notes 15, 25
No color requirement
Notes 25, 30, and
31
No color requirement
—
TEC5000
Page 44 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
System Code for
Corrosivity Class
BSI BS
EN ISO
12944-2
C4-CX
Items
Offshore
and
Coastal
6.8
Stainless Steel (all grades)
6.8.1
Uninsulated to 65 °C
(150 F)
P
6.8.2
Insulated, -200 to 0 C (240–32 F)
J
6.8.3
Insulated, 0–65 C (32150 F) including
sweating service
D
6.8.4
BSI BS
EN ISO
12944-2
C1-C3
Finish Coat Color (1)
Remarks
Inland
Onshore
Notes 7, 10, and
16
none
Uninsulated/Insulated
with an operating
temperature of:
Coating Manufacturer's
Standard
Notes 8, 28
No color requirements
Note 28
No color requirements
Note 28, 31
No color requirements
—
Austenitic SS, 65–150 °C
(150–300 F) or in cyclic
service.
Duplex SS, 110–150 °C
(230–300 F)
D
Super Duplex SS, 120–
150 °C (250–300 F)
6Mo Superaustenitic SS,
130–150 °C (265–
300 F)
6.8.5
Uninsulated or Insulated
Continuously op temp >
150 °C (300 F)
—
No coating required
6.8.6
Uninsulated/Insulated (all
temperatures – except in
sweating service) located —
within an HVAC
controlled module
6.8.7
Below ground
6.9
Carbon Steel Internal Surfaces and Incidental Stainless Steel Internal Parts
UPST, PL
No coating required
Notes 8, 9, 20,
24, and 25
Not recommended to use Stainless Steel below —
ground – consult SME
© ExxonMobil 2018
TEC5000
Page 45 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
System Code for
Corrosivity Class
BSI BS
EN ISO
12944-2
C4-CX
Items
Offshore
and
Coastal
6.9.1
6.9.2
6.9.3
7.0
7.1
Potable water
BSI BS
EN ISO
12944-2
C1-C3
Other services not listed
above, including
chemical tanks, etc.
Remarks
Coating Manufacturer's
Standard Colors
—
Coating Manufacturer's
Standard Colors
Note 22
Inland
Onshore
T
Diesel oil, Base oil,
Slops, Ballast water, Jet
fuel
Finish Coat Color (1)
S
—
Refer to GP 56-02-21
Furnaces, Stacks, Breeching, Ducts, Exhausts and Boilers; External Surfaces (Carbon
Steel)
Uninsulated, to 80 °C
(175 F)
A or C
M or F
Furnaces, Exhausts and
Boilers: Gray: RAL
7038.
Note 8
Stacks, Breeching, and
Ducts: Black, RAL
9017
7.2
Uninsulated > 80 °C (175
D
F)
7.3
Insulated, to 80 °C (175
F)
I
7.4
Insulated, 80–400 °C
(175–750 F)
D
7.5
Insulated, Cyclic Service
8.0
E
D
Coating Manufacturer's
Standard Colors
Notes 8, 24
No color requirement
Note 25
No color requirement
Note 25
No color requirement
Notes 15, 25, and
30
Skid-mounted Subsea Equipment – External Surfaces
Notes 5, 8, 23
8.1
Uninsulated
8.2
Insulated
UPST, PL
K
As
Qualified
by
Insulatio
n
Supplier
© ExxonMobil 2018
—
Coating Manufacturer's
standard light color
Note 8
—
No color requirement
Note 13
TEC5000
Page 46 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
System Code for
Corrosivity Class
BSI BS
EN ISO
12944-2
C4-CX
Items
Offshore
and
Coastal
9.0
9.1
9.2
9.3
9.4
10.0
UPST, PL
Finish Coat Color (1)
Carbon Steel Exterior –
without intumescent
epoxy passive fire
protection
Carbon Steel Exterior –
with epoxy passive fire
protection
A or C
Note 7
Gray, RAL 7038
—
Gray, RAL 7038
—
No coating unless
otherwise required in
project architectural
scheme
—
[*] Off-white (unless
otherwise required in
project architectural
scheme)
—
M or F
Z
Aluminum or Stainless
Steel Exterior
—
Interior
Concrete workshop
floors
Remarks
Inland
Onshore
Living Quarters/Control Rooms/Workshops
N
9.5
BSI BS
EN ISO
12944-2
C1-C3
L
—
No color requirement
Floating, Production,
See GP 28-02-06 for details.
Storage, and Offloading
(FPSO) Vessel Hulls
© ExxonMobil 2018
TEC5000
Notes 14, 27
—
Page 47 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Notes for Table A–3:
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
[A] Color designations are per RAL Classic Color System. All colors are subject to project
approval and may be revised or modified to match existing colors, and as such should not
require a specification deviation.
Note not used.
Surfaces using an epoxy passive fireproofing (PFP) shall utilize System Z, or the system
recommended by the PFP Manufacturer. See GP 70-01-05 for guidance on placement and types
of PFP.
Note not used.
Individual components of skid-mounted units shall be coated as noted for each item listed in this
schedule or as allowed by Note 23.
Faying surfaces of painted steel members designed for high-strength bolting in friction-type
joints shall be primed only. The primer shall be certified by Coating Manufacturer to have been
rated by testing to provide the slip class required by the structural design (Class A or B). Do not
paint galvanized faying surfaces.
Paint used for shop marking and materials identification shall be compatible with subsequent
finish coats.
Identification numbers shall be placed on all plant equipment (e.g., pipe, vessels, pumps,
exchangers, etc.) and shall correspond to the Piping and Instrumentation Drawing (P&ID)
numbers. Lettering or stenciling shall be a minimum of 50 mm (2 in.) high and shall be of a
contrasting color. Incoming and exiting line service shall be identified in a similar manner; 25
mm (1 in.) or smaller lettering is acceptable. Stencil color shall be distinctly different color from
background paint and should be consistent throughout the facility. For Midstream tank
applications, refer to Appendix D for detailed tank labeling requirements.
The following requirements apply to the exterior of storage tanks for Upstream:
(a) On tank roofs that are painted white, an area 1.6 m (5 ft) in diameter surrounding gauging
hatches shall be painted black with the urethane finish for the system listed in Table B–1.
(b) Storage tanks shall be inscribed with the date of painting and/or cleaning. Letters 25 mm (1
in.) high, with 3 mm (0.12 in) stroke characters and numerals, shall be painted on the tank with
the red urethane finish for the systems listed in Table B–1.
(c) Inscriptions shall be as follows:
(i) "SHELL PAINT (date)" shall be painted on the shell 200 mm (8 in.) above the edge of the
manhole cover closest to the product inlet and outlet nozzles. The inscription shall straddle
the vertical centerline of the manhole.
(ii) "ROOF PAINTED (date)" shall be painted 25 mm (1 in.) above the inscription given in
Item (i.)
(iii) "CLEANED (date)" shall be painted on the manhole cover 150 mm (6 in.) above the
centerline.
(iv) "INTERIOR LINED (date)" shall be painted 25 mm (1 in.) above the inscription given in
Item (ii.) The date in each inscription shall consist of the month and year only, in that
order, and both shall be indicated in numbers (e.g., "7-02" for July 2002.)
(d) See Note 8. An identification number shall be painted on each tank in a location readily
visible to plant operators. For Midstream tank applications, refer to Appendix D for detailed
tank labeling requirements.
(10)
Do not paint stainless instrument and control tubing.
(11)
See GP 66-01-03 for details.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 48 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
(12)
[A] If an economic evaluation determines that the cathodic protection system alone is more cost
effective, then the coating system may be deleted with Company approval.
(13)
Surface preparation and coating for subsea insulated equipment shall be as qualified by subsea
insulation supplier, and shall conform to NORSOK M-501 system 9 or equivalent. See GP 6508-01 for details.
(14)
Apply broadcast-type skid-resistant coating material in two stages. Broadcast skid resistant
#30–#40 Aluminum Oxide Grit into surface of wet second coat of Epoxy. Sweep up excessive
grit when dry. Using roller, apply "Epoxy Finish" to seal over grit.
(15)
Apply TSA in accordance with GP 56-02-08. In those instances where an option is allowed in
Table B–1, System D is preferred. However, the alternative coating system may be used if
design life is less than 15 years or economic analysis proves the alternative system to be more
economical during the life cycle.
(16)
Refer to GP 29-01-03 for stainless steel operating temperature limits. Upstream stainless steels
include 304/316/300 Series Austenitic Stainless Steel, 22Cr Duplex, 25Cr Super Duplex, and
6Mo Super Austenitic. Stainless steel shall not be coated with zinc pigmented or zinc-rich
coatings including TSZ, epoxy zinc, IOZ, etc.
(17)
Coating system A shall not be used where surfaces may be exposed to mechanical ice removal
or the use of deicing salts – System C must be used.
(18)
Note not used.
(19)
The extent of coating is as follows:
Sheet Piles—All surfaces both sides except the interlocking groove.
Pipe Piles—Exterior surface only from top of pile to at least 3 m (10 ft) below the mud line.
Additional coating length may be required to achieve cathodic protection for the pile structure
and/or adjacent structure.
(20)
If lined, stencil "Lined Vessel – No Hot Work" in characters at least 8 cm (3 in.) high on side of
tank or, for ballast tanks, on deck. This caution should be within 1 m (3 ft) of each personnel
entry hatch.
(21)
Commence blasting and coating work only after completion of all "hot work," both within the
tank and on exterior surfaces of substrates that will be coated on their interiors.
(22)
For tanks in hydrocarbon service, coat entire tank bottom and at least 1 m (3 ft) of sides or
expected high water level if greater and surfaces where water is expected to condense. Tanks in
other services shall be 100% internally coated.
(23)
[A] Manufacturer’s system shall have surface preparation of SP10 minimum, and DFT 250
micron (10 mil) minimum. If manufacturer’s system does not meet these minimum
requirements, with Company approval, refinish components and equipment delivered with
Vendor's standard factory finish with System "L."
(24)
Color does not require an exact match to a specific color chip. Use Coating Manufacturer's
standard version for this color in the specified product.
(25)
[R] Where practicable, alternate methods to insulation for providing personnel protection should
be considered (e.g., cages.)
(26)
Only for buried piping within battery limits. For pipelines, refer to GP 56-02-01.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 49 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
(27)
Where additional nonslip material is required or for dust control (e.g., helicopter workshops.)
(28)
No coating is required for 22Cr Duplex SS below 110 C (230 F), 25Cr Super Duplex SS
below 120 C (250 F), and 6Mo Superaustenitic SS below 130 C (265 F).
(29)
Note not used.
(30)
Cyclic Service is any process for which there are repeated temperature cycles, excluding startups and/or maintenance shutdowns, from ambient or below to the maximum operating
temperature.
(31)
Sweating Service is any process that operates below the ambient dew point but at or above 0 C
(32 F).
UPST, PL
© ExxonMobil 2018
TEC5000
Page 50 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Appendix B: Generic Coating Products/Coating Systems
B-1: Generic Coating Products/Coating Systems
Table B–1: Company Coating System Codes
System Code
Prep
Coat 1
Coat 2
Coat 3
Coat 4
A (6, 8)
SP 10
Zinc-Rich
Epoxy
Epoxy Mastic
High Build
(HB) Epoxy
Urethane
B (6)
SP 10
Zinc-Rich
Epoxy
HB Epoxy
C (6)
SP 10
IOZ
HB Epoxy
D
SP 5
(TSA) (1)
Silicone (for
color only) (9)
E (6)
SP 10 (2)
IOZ
SP 10
IOZ
HB Epoxy
G (6)
SP 5
(TSZ)
Note: system O
to be used if
color is
required
—
—
H
Note 3
Epoxy Primer
or Epoxy
Mastic
Urethane (not
required if
under
cementitious
fireproofing)
—
—
I
SP 5
Heat Resistant
Epoxy
Heat Resistant
Epoxy
—
—
J
SP 10
Heat Resistant
Epoxy
—
—
K
SP 5
100% Solids
Epoxy
100% Solids
Epoxy
—
—
L
Note 7
Epoxy Mastic
Epoxy Mastic
Urethane
—
M (6, 8)
SP 10
Zinc-Rich
Epoxy
HB Epoxy
Urethane
—
N
SP 10
Epoxy Mastic
Urethane
O
SP 5
TSZ
Epoxy Mastic
F
(6)
UPST, PL
© ExxonMobil 2018
—
—
TEC5000
—
HB Epoxy
—
Urethane
—
—
—
—
Urethane
—
Urethane
—
—
Page 51 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
System Code
Prep
Coat 1
Coat 2
Coat 3
P
SP 10
HB Epoxy
HB Epoxy
Urethane
Q
SP 10
Silicone
R (6)
SP 11
Galv Repair
S
SP 5
T
SP 5
—
DEC 2018
Coat 4
—
—
—
Galv Repair
—
—
Tank lining
Tank lining
—
—
National
Sanitation
Foundation
(NSF) Epoxy
NSF Epoxy
—
—
U (Not Used)
—
—
—
—
—
V (Not Used)
—
—
—
—
—
W
SP 10
Epoxy Primer
Heat Resistant
Epoxy
Heat
Resistant
Epoxy
Z(4, 6)
SP 5
Zinc
Phosphate (5)
Epoxy PFP
Urethane (5)
UPST, PL
© ExxonMobil 2018
TEC5000
Urethane
—
Page 52 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Notes for Table B–1:
(1)
TSA shall be applied per GP 56-02-08.
(2)
Maximum profile shall not exceed 50 μm (2 mils).
(3)
Prior to coating, prepare surfaces by washing and sweep blasting per Section 8.6 of this GP.
HDG per GP 29-02-19.
(4)
Surfaces to be coated with an intumescent epoxy shall be primed, fireproofed, and topcoated as
recommended by the intumescent fireproofing Manufacturer. See GP 70-01-05 for guidance on
placement and types of PFP. TSA, IOZ, and TSZ shall not be used as a primer under fireproofing.
(5)
Only products from Coating Manufacturer's published approval coatings list for use with epoxy
PFP may be used.
(6)
Thermal sprayed zinc and zinc pigment coatings shall not be used on stainless steel.
(7)
Requirements for concrete painting:
a)
Remove oil and grease (SSPC SP 1) and abrasive blasting concrete.
b)
Remove all surface laitance and provide surface appearance of medium grade abrasive
paper.
c)
Concrete to be dry and free from contamination.
d)
Primer coat shall be diluted by 10–15% with Manufacturer's recommended thinner.
e)
Ensure good ventilation during application.
f)
Nonslip material may be added to this coating system by broadcast into the second coat.
(8)
Coating Systems A or M shall not be used where surfaces may be exposed to mechanical ice
removal or the use of deicing salts.
(9)
Silicone sealer coats shall be applied over TSA only if color coding is required. See GP 56-02-08
for details.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 53 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
B–2: Paint Manufacturers and Complying Products
The coatings specified in Table B–2 are intended to be available worldwide and are subject to periodic
review, change, or removal by Company.
Table B–2: Paint Manufacturers and Complying Products
Generic
Product
Identifier
DFT Min/Max
(each coat)
Carboline
Hempel
International
Jotun
Sherwin
Williams
PPG
IOZ
60–100 m (2–4
mils)
Carbozinc
11
Galvosil
15700
Interzinc 22
Resist 86
Zinc Clad II
Sigmazinc 9
Zinc-Rich
Epoxy
75–120 m (3–5
mils)
Carbozinc
859
Avantguard
750
Interzinc 52
Barrier 80
Zinc Clad
IV
Sigmazinc
68
Epoxy
Primer
75–120 m
Carboguard
60
15570
Interseal
670HS
Penguard
Universal
Macropoxy
646
Sigmacover
2
Carboguard
891
35560
Interline 850
Tankguard
412
Macropoxy
646 PW
Sigmaguard
CSF 585
Carbomastic
635
XO Quattro
17634
Intershield
300
Penguard
Universal
SeaGuard
6000
Sigmaprime
700
Thermaline
450EP
85671
Intertherm
228HS
Tankguard
Storage
Epo-Phen
Phenguard
930
Carboguard
60
XO Quattro
17820
Intergard 475
HS
Penguard
Midcoat
Macropoxy
646
Sigmaprime
200
Carbothane
134HG
55610
Interthane 990
Hardtop
XP
Acrolon
218 HS
Sigmadur
550
Carbomastic
15
45881
Interseal
670HS
Aluminum
Jotamastic
80
Macropoxy
646
Sigmacover
2
Phenoline
Tankshield
35530
Interzone 954
Jotamastic
SF
Nova-Plate
325
Sigmashield
880
Thermaline
4700
5691
Intertherm 50
Solvalitt
Heat Flex
1000
Sigmatherm
540
Carboguard
60
45881
Intergard 740
Jotamastic
90
SeaGuard
5000 HS
Sigmacover
2
(3–5 mils)
NSF
Epoxy
150–250 m
Marine
Epoxy
130–165 m
HeatResistant
Epoxy
75–125 m
(6–10 mils)
(5–7 mils)
(3–5 mils)
HB
Epoxy
130–200 m
Urethane
40–75 m
(5–8 mils)
(2–3 mils)
Epoxy
Mastic
100–200m
100%
Solids
Epoxy
300–500 m
Silicone
20–35 m
(4–8 mils)
(12–20 mils)
(1–2 mils)
Epoxy
Finish (1)
UPST, PL
(Note 1)
© ExxonMobil 2018
TEC5000
Page 54 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Generic
Product
Identifier
DFT Min/Max
(each coat)
Carboline
Hempel
International
Jotun
Sherwin
Williams
PPG
Tank
liner
150–200 m (68 mils) min (4)
Plasite 7122
HS
85671
Interline 984
Jotamastic
SF
Epo-Phen
Novaguard
840
Galv
Repair
25–35 m
—
16490
Galvanite
Zinc Clad 5
Sigmazinc
19
Epoxy
PFP
(Note 5)
JotaChar
750
Firetex
M90
PittChar XP
—
(3–5 mils)
ThermoLag
3000
—
Chartek 7
Notes:
(1)
Apply in two stages: first layer 75–125 μm (3–5 mils), second layer 50–75 μm (2–3 mils). A coat of urethane may
be substituted for the second layer where required for color or aesthetics (gloss). See Note (13) of Table A–3 for
application and aggregate details.
(2)
Coating system codes are a single letter. Coat 1 and coat 2, and, where called for, coat 3 and coat 4 are full
coats in addition to any stripe or mist coating that may be required.
(3)
Gray box indicates no complying products produced by Manufacturer as of publication of this GP.
(4)
See Manufacturer's data sheet for specific recommended DFT for each product in immersion service.
(5)
Refer to GP 70-01-05 for PFP requirements.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 55 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Appendix C: Coating Qualification Procedure
C–1 Scope
1) The purpose of this Appendix is to provide a method to evaluate the suitability of a coating system to
perform as a protective coating for structures operated by Company in both onshore and offshore
facilities. Further, its intention is also to provide a consistent and documented approval process for
selection of coating material to be included in this GP and evaluate alternate materials for specific
projects. Coatings listed in Table B–2 are exempt from this qualification requirement.
2) [*] Only suppliers listed in Table B–2 are eligible to qualify a coating system using this procedure
under the requirements of this Appendix.
3) The qualification procedure applies only to coatings that are not listed in Table B–2.
4) Coating systems approved for use in GP 56-02-11 do not require retesting.
C–2 General
1) Manufacturer shall provide materials of the same generic type as those listed in the coating systems
provided in Table B–1 for each consecutive coating layer and for the services indicated.
2) [A] Where Manufacturer proposes an alternative coating system, a significant cost or performance
benefit for using the proposed system shall be demonstrated. The performance benefit shall be
demonstrated by comparison to Company-approved equivalent incumbent coating system using the
testing defined in this Appendix.
3) A certified third-party laboratory shall carry out the technical assessment, and Manufacturer's inhouse test results shall only be accepted when the testing has been witnessed and certified by a
recognized third party.
C–3 Coating System
C–3.1 Description
For each product submitted for technical assessment, the following information shall be required from
Coating Manufacturer:
1) A coating system description in accordance with BSI BS EN ISO 12944-9, Section 7.1 ''Description.''
2) An SDS, as a minimum, in accordance with ANSI Z400.1/Z129.1 and meeting all regulatory
requirements of the locale for which the product is to be used.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 56 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
3) Current and published PDSs and application notes, which provide, as a minimum, the details
described in BSI BS EN ISO 12944-9, Section 6.4 "Required product information.''
4) Written and verifiable case histories from Coating Manufacturer for the product in similar service to
that proposed for a period of not less than 5 years.
C–3.2 Formulation of Coating Materials
1) [S] The formulations and coating systems shall meet or exceed the health and safety statutory
requirements in force at the point of application of the product. If the application or end use of the
product is controlled in some locales, then these locales shall be clearly defined in writing by Coating
Manufacturer (e.g., lead content in zinc dust, VOC, etc.)
2) Paint Manufacturers shall confirm in writing all low melting point alloys in their paint products and
whether they contain constituents (e.g., free chlorides, zinc, etc.) that could be harmful to stainless
steels or nickel-chromium alloys.
3) Any changes in formulation of the coating or application techniques shall be cause for retesting.
4) The minimum zinc dust pigment content of the nonvolatile portion of zinc primer shall be in
accordance with SSPC V2 Table 2 ''Paint Specification 20.''
5) Only ASTM D 520, Type II, or Type III zinc shall be used in the manufacture of zinc-rich primers.
The zinc powder shall also comply with any additional statutory requirements in effect at the location
where the coating is to be used. Individual components in the zinc dust pigment shall be determined
per the test methods specified in ASTM D 521.
6) [S] New coating materials shall contain no elements or compounds of lead, chromium, cadmium, tin,
or other hazardous metals, including pigments used to obtain specific colors or additions to promote
cure. Where incidental traces of lead and other heavy metals exist, these traces shall not exceed
0.01% total by weight of the coating's composition in the dried film.
C–3.3 Preparation and Conditioning of Test Panels
C–3.3.1 Sample Plates
1) The panels shall be prepared in accordance with BSI BS EN ISO 12944-9 with the exception of the
panel size, which may be reduced providing this does not compromise any of the testing requirements
or the test equipment used. The panel thickness is to remain as stated in BSI BS EN ISO 12944-9.
All panel edges shall have a minimum radius of 2 mm (0.1 in.).
2) Sufficient plates shall be available to perform the tests for each system in triplicate, with each test
plate being subjected to the same test simultaneously.
C–3.3.2 Surface Preparation
1) Surface preparation shall be in strict accordance with the latest published PDS or application notes for
the product. With the exception of the surface tolerant coatings, all coatings shall be applied to panels
prepared by abrasive blasting.
2) Testing of surface tolerant coatings requires the production of two sets of plates referred to here as
Sets A and B The set shall be prepared as follows:
a) Set A—Abrasively blasted per Manufacturer's published PDS
b) Set B—Mechanical cleaned to SSPC SP 3
UPST, PL
© ExxonMobil 2018
TEC5000
Page 57 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
C–3.3.3 Application and Curing
1) Application and curing of the coating shall be in strict accordance with the latest published PDS or
application notes for the product.
2) The coating system proposed shall overlap the back of the test plate by a minimum of 25 mm (1 in.)
and shall fully coat the edges of the test piece.
3) When cured, the coatings shall be inspected visually for defects (e.g., pinholes, voids, bubbles, mud
cracking, sags, runs, etc.) Visual defects on the panel shall be cause for rejection of the panel, and no
further testing shall be performed on this panel. After the panel has been rejected, it shall be prepared
again in accordance with this Appendix, recoated, and used for testing.
C–3.3.4 Dry Film Thickness
DFT readings are required to be taken and recorded for each layer or coat of the coating system applied in
accordance with BSI BS EN ISO 12944-5.
C–3.3.5 Over-Coating Time
Over-coating times in the latest published PDS or application notes for the product shall be strictly followed.
C–3.3.6 Conditioning/Curing
Conditioning/curing of the panels shall be in accordance with BSI BS EN ISO 12944-9 for a period of not
less than 3 weeks or as stated in the latest published PDS or application notes for the product.
C–3.3.7 Porosity
Once the panel has been fully cured, the panel shall be tested for porosity (i.e., holidays) in accordance
with ASTM D 5162. If any porosity is found, then the panel shall be rejected, and no further testing shall
be performed on this panel. If required, the rejected panel may be prepared and recoated in accordance
with this Appendix.
C–4 Test Requirements and Acceptance Criteria
A minimum of two out of three panels shall pass the acceptance criteria for the system to be deemed to
have passed the test. Test requirements and acceptance criteria are provided in Table C–1.
Table C–1: Test Requirements and Acceptance Criteria
Performance
Tests
Test Requirement
Fingerprint
FTIR spectra
Aging
Resistance
BSI BS EN ISO 12944-9, Annex B ''Cyclic
Ageing Test''
Standard Procedure (Neutral Salt Spray
[NSS] solution)
UPST, PL
Duration (hrs)
Acceptance
Criteria
—
© ExxonMobil 2018
4,200
TEC5000
Per Table 5, BSI BS
EN ISO 12944-5
See Note (1) for
exceptions
Page 58 of 67
GP 56-02-02
Painting General Requirements for New Construction
Performance
Tests
Test Requirement
Sea Water
Immersion
BSI BS EN ISO 2812-2,
Test Fluid — NSS from ISO 9227 (BSI BS
EN ISO 9227) Test fluid temperature 45 °C
(110 °F)
Cathodic
Disbonding
ASTM G 8
ASTM G 42
Impact
Resistance
BSI BS EN ISO 6272-1
Edge
Retention
NACE SP0304
Thermal
Cycling
NACE SP0304
Resistance to
In-Services
Temperature
Continuous exposure to −20 °C (−4 °F)
V 4.2.0
Duration (hrs)
4,200
No blisters, rusting,
flaking, or cracking
720
N/A
>5J
No evidence of
cracking
720
Continuous exposure at 90 °C (195 °F) dry
heat
720
Continuous exposure at 230 °C (450 °F) dry
heat
> 50%
No evidence of
cracking
No flaking,
cracking,
disbonding, or
discoloration
Adhesion > 70% of
original
No flaking,
cracking, or
disbonding.
Adhesion > 70% of
original
Continuous exposure at 450 °C (850 °F) dry
heat
Thick Film
Cracking
Acceptance
Criteria
Diameter of
cathodic
disbondment shall
be < 10 mm
(0.4 in.)
N/A
Continuous exposure at 120 °C (250 °F) dry
heat
DEC 2018
NACE TM0104
—
No evidence of
cracking
Notes:
(1)
BSI BS EN ISO 12944-9, Table 5 shall be used as the acceptance criteria with the exception of
the following:
Assessment Method
Before Aging
After Aging
BSI BS EN ISO 4624
Minimum 5 MPa (725 psi)
Minimum 5 MPa (725 psi) or 70% of
the initial value
Minimum 10 MPa (1,450 psi)
for internal tank coatings.
(2)
Minimum 10 MPa (1,450 psi) for
internal tank coatings
After aging, the test panels shall be conditioned for 2 weeks prior to retesting for adhesion.
Conditioning shall occur at room temperature and an RH of less than 60%. Test panels shall not
be stoved or artificially force-dried.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 59 of 67
GP 56-02-02
Painting General Requirements for New Construction
Performance
Tests
Test Requirement
V 4.2.0
Duration (hrs)
DEC 2018
Acceptance
Criteria
(3)
Coating systems that have a total DFT greater than 150 μm (6 mils) shall not be scored around
the pull dolly.
(4)
Cathodic disbonding testing shall be in accordance with this Appendix and not as defined in BSI
BS EN ISO 12944-9.
C–5 Qualification Testing Requirements
The proposed coating system shall be tested in accordance with Table C–2.
Thick Film Cracking
450 °C (850F)
230 °C (450 F)
In-Service
Temp
120 °C (250 F)
90 °C (195 F)
40 °C (100 F)
−20 C (−4 F)
Thermal Cycling
Edge retention
Impact Resistance
Cathodic
Disbondment
ASTM G 8
Sea Water Immersion
Aging Resistance
Fingerprint
Case Histories
PDS
SDS
Coating System
Manufacturer's
Documentation
Table C–2: Qualification Testing Requirements
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S
T
UPST, PL
N/A
N/A
N/A
© ExxonMobil 2018
TEC5000
Page 60 of 67
450 °C (850F)
230 °C (450 F)
120 °C (250 F)
90 °C (195 F)
Thick Film Cracking
DEC 2018
In-Service
Temp
V 4.2.0
40 °C (100 F)
−20 C (−4 F)
Thermal Cycling
Edge retention
Impact Resistance
Cathodic
Disbondment
ASTM G 8
Aging Resistance
Fingerprint
Case Histories
PDS
SDS
Coating System
Sea Water Immersion
Painting General Requirements for New Construction
Manufacturer's
Documentation
GP 56-02-02
U
Not Used
V
Not Used
W
X
Not Used
Y
Not Used
Z
Notes:
(1)
Paint Manufacturer's documentation as defined in this procedure.
(2)
Water-borne IOZ silicates shall be tested to the requirements of Coating Code A.
(3)
Shall follow surface-tolerant required test coating test protocol.
(4)
Case histories must include re-inspection of applied coating not less than 3 years after application.
C–6 Anti-Skid Systems
The anti-skid material used in anti-skid systems shall be of a nonferrous-containing and non-sparking or
low sparking material. The sparking intensity of this material shall be below that of carbon steel. Antiskid systems shall be tested for aging resistance with and without anti-skid material. The panels with the
anti-skid material do not require a scribe. There shall be no disbonding or cracks with and without antiskid material. Panels containing anti-skid material shall not be subject to adhesion testing.
C–7 Test Reports
1) The test reports shall contain the information as defined in Appendix C of this GP and in BSI BS EN
ISO 12944-9. If additional testing other than those in BSI BS EN ISO 12944-9 is specified by this
Appendix, the results shall be placed as appendices at the end of the report. Each appendix, as a
minimum, shall meet the reporting requirement as defined by the relevant standard.
2) All test reports shall be in English and System International of Units (SI) units.
3) All test reports shall be less than 7 years old at the date of submission and shall be for the current
formulation.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 61 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Appendix D: Midstream Tank Labeling Requirements
1) The following surfaces and materials shall not be painted or coated:
a) Nonferrous metals
b) Austenitic stainless steels
c) Galvanized or aluminized surfaces
d) Building brick, masonry units, and wall tile
e) Concrete structures and foundations
f) Plastic and plastic-coated materials
2) After the final coat of paint has completely dried, each tank shall be numbered and lettered with black
paint using stencils or decals with the information listed in Table D–1.
Table D–1: Tank Labeling
1.
Near tank inlet/outlet valves (6 in. letters):
T-#
PRODUCT NAME
2.
Above respective tank valves—as applicable (6 in. letters):
INLET
3.
HIGH
SUCTION
NORMAL
SUCTION
FLOATING
SUCTION
LOW
SUCTION
WATER
DRAWOFF
Near tank inlet valves—as applicable (2 in. letters):
CAUTION: This tank equipped with a floating suction. Remove pontoons prior to hydrotesting.
4.
5.
At ground level indicator (2 in. letters):
Innage
MMC
Safe Fill Height:
xx' xx"
Xx' xx"
Tank Capacity:
xx,xxx bbl
Roof on Legs (if
applicable)
xx' xx"
Barrels per foot
x, xxx bbl/ft
Xx ' xx"
Above tank manways—as applicable (2 in. letters):
WARNING: This tank has been in leaded product service.
6.
Near base of tank stair (2 in. letters):
Tank Cleaned MM/YY:
Contractor Name
Vendor Phone Number
Tank Painted MM/YY:
Contractor Name
Vendor Phone Number
Surface Prep
UPST, PL
© ExxonMobil 2018
Surface Preparation
TEC5000
Page 62 of 67
GP 56-02-02
Painting General Requirements for New Construction
Fiberglass Lining MM/YY
Primer
Product
Intermediate
Product
Finish
Product
V 4.2.0
DEC 2018
Contractor Name
Vendor Phone Number
Devoe Devmat 111
7.
Near water draw-off—if applicable (2 in. letters):
CAUTION: This tank has a plastic bottom liner. Do not enter or perform mechanical work
within 24 in. (609.6 mm) of the bottom without permission of Terminal Superintendent.
8.
At gauge hatch (2 in. letters):
Flammable: Avoid Inhaling Fumes (if applicable)
9.
Innage
MMC
Gauge Height:
xx' xx"
xx' xx"
Safe Fill Height:
xx' xx"
xx' xx"
Safe Fill Capacity:
xx,xxx bbl
Roof on Legs: (if applicable)
xx' xx"
Barrels per Foot:
x,xxx bbl/ft
xx' xx"
Near tank vents/inspection hatches—as applicable (2 in. letters):
Flammable: Avoid Inhaling Fumes
Notes for Table D–1:
(1)
[*] Information in bold/underlined text shall be furnished by Company Representative and
applied by Coating Contractor.
(2)
2 in. = 50.8 mm
6 in. = 152.4 mm
3) [*] Equipment, such as pumps, towers, drums, motors, and piping shall be identified as directed by
Owner's Engineer and in accordance with Table D–2. Where required by local ordinance, decals to
identify product per NFPA 704 shall be applied above each tank inlet and outlet nozzle.
Table D–2: Equipment Identification
UPST, PL
Pipe, Equipment, or Covering
Nominal Outside Diameter, in. (mm)
Letter and Number Height,
in. (mm)
11/2–4 (38.1–101.6)
1 (25.4)
6–12 (152.4–304.8)
2 (50.8)
14–48 (355.6–1219.2)
3 (76.2)
Over 48 (1219.2)
4 (101.6)
© ExxonMobil 2018
TEC5000
Page 63 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Record of Change
Version 1.0.0
Location
Action
Date: 10/04
Description
This GP replaces GP 25-01-05 and GP 22-01-02. Historical information
regarding changes to the original documents may be obtained via
EMEPS master.
Version 1.1.0
General
Replacement
Date: 04/05
Reference to GP 66-02-03 replaced with GP 66-01-03.
Version 2.0.0
This GP
Modifications
Date: 07/06
This Version reflects a document that has been changed throughout. The
overall objective of these changes is to:
(1) Include new standards that codify practices and procedures
previously described less precisely in the text.
(2) Identify contemporary coating products expressly indicated by their
Coating Manufacturers as appropriate for use in conjunction with this
GP. All Coating Manufacturers were given an opportunity to review this
version to ensure their understanding of the context/service in which
their products would be used.
(3) Incorporate details once relegated to notes by relocated to the text.
(4) Provide details that reflect lessons learned. In particular, the
topsides/onshore primer now includes organic zinc-rich epoxy rather
than being solely reliant on ethyl silicate inorganic zinc. Rub tests are
prescribed to ensure IZ is properly cured prior to overcoating and to
confirm that prior coats of an epoxy lining will be receptive to
overcoating (i.e., are demonstrably within their maximum recoat times).
(5) Add details, including sketches, to optimize tie-in and repair details.
Individuals interested in performing a side-by-side comparison between
this version and the prior version (1.1) can obtain a copy of that version
from the EMEPS editorial staff.
Title
Modification
Title of GP was changed by addition of "Offshore."
Section 1
Modifications
The following reference was added: GP 29-01-35.
The following references were deleted: GP 03-20-01, ASTM E 337, FED
STD 595B, NEMA Z535.1, All OSHA references, SSPC QP 1,
SSPC QP 3
Data Sheet I290202C01 title was changed per new GP title.
Section 9.5
Modification
Table 1 was modified.
Section 10.1
Addition
Figure 1, Repair Sketch, was added.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 64 of 67
GP 56-02-02
Appendix
Painting General Requirements for New Construction
Modification
V 4.2.0
DEC 2018
Appendix C was deleted.
Tables A–1, A–2, and B–1 were revised.
Data Sheet
Modification
Data Sheet I 02C01 title was changed per new GP title.
All Global
Practice s
Modifications
To standardize the format of the Global Practices and to meet other
requirements, the following changes have been implemented:
"For ExxonMobil Use Only" has been replaced with "For Company Use
Only."
A copyright waiver has been added in the first page Footer.
The definition of asterisks in the Scope has been deleted. The asterisk is
now defined in the Purpose Code attachment and is used within brackets
as other Purpose Codes.
Multiple paragraphs within a Section have been numbered.
The standard text for Required References has been modified.
The standard text for Additional Requirements has been modified.
The [S] Purpose Code has been modified.
The following Purpose Codes have been added:
[*] for additional information or decision required of Owner's
Engineer.
[A] for approval requirements before beginning work or finalizing
design.
Version 3.0.0
Date: 11/12
GP Number
Renumbered
GP 29-02-02 renumbered to GP 56-02-02.
General
Addition
Updated Purpose Codes and Rationales throughout GP.
General
Modification
Updated the coating systems.
General
Modification
Updated the painting products.
Version 3.1.0
Table A-2
Modification
Date: 11/12
Changed "Temperature-Resistance Epoxy" to "Heat Resistance Epoxy."
Version 4.0.0
Date: 07/18
GP Number
Modification
Combined GP 56-02-02 and GP 56-02-03 into one GP.
GP Title
Modification
Changed Title from ''Painting General Requirements - Offshore.''
General
Modification
Updated Purpose Codes, Rationales, references, and unit conversions and
clarified content throughout GP.
Section 3
Modification
Item (2): Modified requirements for generic coating products.
Section 3.6
Modification
Items (2)–(4): Added requirements for coatings and equipment to
comply with Safety Data Sheet.
Section 4.2.2
Modification
Items (3)–(6): Modified requirements for inspection and testing of
coating.
Section 4.3
Modification
Item (2)–(4): Modified requirements for qualification of Applicator.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 65 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Section 6.1.1
Addition
Added Section with requirements for traceability and certificates for
coating material.
Appendix A
Modification
Modified requirements for Coating Schedule/Matrix.
Table A–1
Modification
Added new rows for Corrosivity Categories.
Table A–2
Modification
Added new rows for Structural Steel.
Appendix B
Addition
Added new Appendix B.
Appendix C
Addition
Added new Appendix C.
PL Only
PL initial endorsement as of 07/18.
Version 4.1.0
Date: 09/18
General
Modification
Updated reference in GP.
Scope
Modification
Item (2): Modified requirements for application of internal coatings.
Version 4.2.0
Date: 12/18
General
Modification
Updated Purpose Codes, Rationales, references, and unit conversions and
clarified content throughout GP.
Table A-3
Modification
Added new rows for Galvanized Steel and insulated pressure vessels.
Appendix D
Addition
Added Appendix D and tables for tank labeling and equipment
identification.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 66 of 67
GP 56-02-02
Painting General Requirements for New Construction
V 4.2.0
DEC 2018
Attachment: Purpose Code Definitions
Code
Description
*
Assigned to paragraphs that require the Owner's Engineer to provide additional information or
make a decision.
A
Assigned to paragraphs that require approval from the Owner's Engineer before the work may
proceed or the design is finalized.
C
Assigned to paragraphs whose primary purpose is reduced costs. Reduced cost in this context
refers to initial investment cost and does not include life cycle cost considerations. Life cycle cost
considerations are captured under reliability, maintainability, or operability purpose codes.
E
Assigned to paragraphs whose primary purpose is driven by environmental considerations.
Environmental considerations typically include specifications intended to protect against
emissions/leakage to the air, water, and/or soil. Deviations from the specifications contained in
such paragraphs require formal review and approval according to local environmental policy.
I
Assigned to paragraphs that provide only clarifying information, such as Scope statements,
definitions of terms, etc.
M
Assigned to paragraphs whose primary purpose is to provide for maintainability of equipment or
systems. Maintainability provisions are those that facilitate the performance of maintenance on
equipment/systems either during downtimes or during onstream operations.
O
Assigned to paragraphs whose primary purpose is to assure operability of equipment or systems.
Operability is the ability of the equipment/system to perform satisfactorily even though conditions
are off-design, such as during start-ups, process swings, subcomponent malfunction, etc.
R
Assigned to paragraphs whose primary purpose is to improve or assure the reliability of equipment
or systems. Reliability is a measure of the ability of equipment/systems to operate without
malfunction or failure between planned maintenance interventions.
S
Assigned to paragraphs containing specifications/guidance where the primary purpose is the
avoidance of incidents impacting personnel safety, process safety, and the public in general and/or
involving responses to emergency situations. Any deviation from the specifications contained in
such designated paragraphs requires formal review and approval according to local safety policy.
Personnel Safety:
Refers to the prevention of incident-related personnel injuries or illness, e.g.,
burns, cuts, abrasions, inhalation of or exposure to dangerous substances,
etc., that could result in medical treatment, restricted work, lost-time
incidents, or fatalities.
Process Safety:
Refers to the prevention and control of process releases, fires, and/or
explosions that could result in damage to equipment, process disruption, or
personnel injury or illness.
Purpose Code Hierarchy: Purpose Codes assigned to a numbered item apply to all associated subitems.
Purpose codes assigned to an individual subitem apply only to that subitem.
UPST, PL
© ExxonMobil 2018
TEC5000
Page 67 of 67
Download