Uploaded by rodolfov26

AREMA Vol. 1

advertisement
2010
Manual for Railway Engineering
Volume 1
1
Track
Introduction
3
Foreword
Table of Contents
Chapter 1
Roadway and Ballast
(Chapters 3 and 10 were combined in 2000 to form Chapter 30)
Chapter 4
Rail
Chapter 5
Track
Chapter 30 Ties
General Subject Index
Copyright © 2010
by the
AMERICAN RAILWAY ENGINEERING AND MAINTENANCE-OF-WAY ASSOCIATION
All rights reserved
No part of this publication may be reproduced, stored in an information or data retrieval system, or
transmitted, in any form, or by any means—electronic, mechanical, photocopying, scanning, recording, or
otherwise—without the prior written permission of the publisher. Photocopying or electronic reproduction
and/or distribution of this publication is a violation of USA and International Copyright laws and is expressly
prohibited.
Correspondence regarding copyright permission should be directed to the Director of Administration, AREMA,
10003 Derekwood Lane, Suite 210, Lanham, MD 20706 USA.
ISSN 1542-8036 - Print Version
ISSN 1543-2254 - CD-ROM Version
1
INTRODUCTION
The AREMA Manual for Railway Engineering contains principles, data, specifications, plans and economics
pertaining to the engineering, design and construction of the fixed plant of railways (except signals and
communications), and allied services and facilities. This material is developed by AREMA technical committees,
is published on the AREMA web site for comments and then is approved for publication in the Manual by the
Association’s Board of Directors.
Designated as Recommended Practice1, the contents of the Manual are published as a guide to railways in
establishing their individual policies and practices relative to the subjects, activities and facilities covered in the
Manual, with the aim of assisting them to engineer and construct a railway plant which will have inherent
qualities of safe and economical operation as well as low maintenance cost.
The AREMA Manual is not a maintenance manual per se since the development of standards or criteria for the
maintenance of railway roadway, track and structures has always been considered to be the prerogative of the
individual railways based on the nature and characteristics of their plant and operations and the specific
characteristics of the geographical region or regions through which they operate.
The above statements also apply to the AREMA Portfolio of Trackwork Plans, which is a companion volume to
the AREMA Manual. The plans in the Portfolio relate to the design, details, materials and workmanship for
frogs, switches, crossings and other special trackwork and are prepared and maintained by Committee 5 –
Track, in addition to its Manual Chapter.
1
RECOMMENDED PRACTICE – A material, device, design, plan, specification, principle or practice recommended to the railways for use
as required, either exactly as presented or with such modifications as may be necessary or desirable to meet the needs of individual
railways, but in either event, with a view to promoting efficiency and economy in the location, construction, operation or maintenance of
railways. It is not intended to imply that other practices may not be equally acceptable.
© 2010, American Railway Engineering and Maintenance-of-Way Association
i
Introduction
THIS PAGE INTENTIONALLY LEFT BLANK.
© 2010, American Railway Engineering and Maintenance-of-Way Association
ii
AREMA Manual of Railway Engineering
1
FOREWORD
This manual is current for the dates indicated on the title page of Volume I and is kept current by the issuance
of annual updates.
The first two editions of the Manual were issued in 1905 and 1907 as the “Manual of Recommended Practice
for Railway Engineering and Maintenance of Way.” Both were bound volumes and published by the Association
under its original name – American Railway Engineering and Maintenance-of-Way Association.
In 1911, the Association changed its name to the American Railway Engineering Association and issued the
third edition of its Manual. This edition, and the next one in 1915, was called the “Manual of the American
Railway Engineering Association,” and was also a bound volume. The final bound volumes were published in
1921 and 1929 under the name “Manual of the American Railway Engineering Association for Railway
Engineering.” A number of Manual updates were issued between some of the bound volumes.
The first looseleaf edition of the AREMA Manual was issued in 1936 under the name “Manual for Railway
Engineering,” the next in 1953. In 1961, the publication was reissued and called the “Manual of Recommended
Practice for Railway Engineering.” The current title, “Manual for Railway Engineering,” was approved by the
Board of Directors in 1970 and reverts to the former, simpler, more functional name although the contents are
still recommended practice, as indicated in the preceding Introduction.
In 1996 the Manual was given a complete facelift. Not only was the manual available in paper form, it was also
available in an electronic version stored on a CD-ROM. The Manual was enlarged to an 8¹⁄₂  11 inch format,
perfect bound and divided into four volumes. For our users’ convenience, the Manual returned to a loose leaf
four volume set in 2000. Each volume covers one of four general areas: Track, Structures, Infrastructure and
Passenger, and Systems Management. The CD-ROM contains a complete version of the manual, which can be
run on several platforms (Windows, Macintosh, and Unix).
The Association also publishes the Portfolio of Trackwork Plans, which is a companion volume to the Manual
for Railway Engineering. The Portfolio contains specifications and plans relating to the design of frogs,
switches, crossings and other special trackwork. It was first issued about 1926 in cooperation with the
Manganese Track Society.
As shown on the following Contents pages, the AREMA Manual for Railway Engineering is issued in four
volumes, each volume divided into chapters with numbers corresponding to the numbers of the standing
technical committees charged with the primary responsibility for developing and maintaining the chapters. In
addition, each volume contains a General Subject Index which augments the separate Table of Contents
provided with each Chapter and Part of the Manual.
To make the Manual easier to use and facilitate reference to parts of it, the committee identification number is
carried throughout the publication by incorporating the number in the page numbering system. For complete
information on the key features of the Manual, such as page numbering system, document dates, article dates,
revision marks, and Proceedings references, the user is directed to the Introduction found in each Chapter.
As stated earlier, updates to the Manual normally are issued annually. Beginning in 2001, revision sets to the
looseleaf books are available.
© 2010, American Railway Engineering and Maintenance-of-Way Association
iii
Foreword
All holders of the Manual – individual AREMA members, individual nonmembers, railways, universities,
governmental agencies, consulting engineers, constructors, supply companies, or other firms – are notified each
year of the availability of the revised Manual and its cost.
Manuals ordered during the normal Association year will be furnished complete for the dates indicated on the
title page.
Copies of the complete Manual may be purchased from Association Headquarters at the then current prices,
which are subject to change without notice. To obtain current individual Chapters, please contact the
Publications Department at AREMA at 301-459-3200.
© 2010, American Railway Engineering and Maintenance-of-Way Association
iv
AREMA Manual of Railway Engineering
TABLE OF CONTENTS
Current until publication of next edition
FOREWORD
This Manual is divided into four Volumes which are further subdivided into Chapters and Parts. Each volume
contains a general subject index covering data found in all volumes. Each Chapter and Part are prefaced by a
Table of Contents.
Because of numbering of Chapters to coincide in most cases with AREMA technical committees, there are no
Chapters 3, 10, 19, 20, 21, 22, 23, 24, 25, 26, 29, 31 and 32. Committee 24 does not maintain a Manual Chapter.
VOLUME 1 – TRACK
Introduction
Foreword
Table of Contents
Chapter 1
Roadway and Ballast
Part 1
Roadbed
Part 2
Ballast
Part 3
Natural Waterways
Part 4
Culverts
Part 5
Pipelines
Part 6
Fences
Part 7
Roadway Signs
Part 8
Tunnels
Part 9
Vegetation Control
Part 10 Geosynthetics
Chapter 4
Rail
Part 1
Part 2
Part 3
Part 4
Part 5
Part 6
Design of Rail
Manufacture of Rail
Joining of Rail
Maintenance of Rail
Miscellaneous
Commentaries
Track
Part 1
Part 2
Part 3
Part 4
Tie Plates
Track Spikes
Curves
Track Construction
Chapter 5
© 2010, American Railway Engineering and Maintenance-of-Way Association
v
Table of Contents
VOLUME 1 – TRACK (CONT)
Part 5
Part 6
Part 7
Part 8
Part 9
Part 10
Track Maintenance
Specifications and Plans for Track Tools
Rail Anchors
Highway/Railway Grade Crossings
Design Qualification Specifications for Elastic Fasteners on Timber Cross Ties
Miscellaneous
Chapter 30 Ties
Part 1
Part 2
Part 3
Part 4
Part 5
General Considerations
Evaluative Tests for Tie Systems
Solid Sawn Timber Ties
Concrete Ties
Engineered Composite Ties
General Subject Index
VOLUME 2 – STRUCTURES
Chapter 7
Timber Structures
Part 1
Material Specifications for Lumber, Timber, Engineered Wood Products, Timber Piles,
Fasteners, Timber Bridge Ties and Recommendations for Fire-Retardant Coating for
Creosoted Wood
Part 2
Design of Wood Railway Bridges and Trestles for Railway Loading
Part 3
Rating Existing Wood Bridges and Trestles
Part 4
Construction and Maintenance of Timber Structures
Part 5
Inspection of Timber Structures
Part 6
Commentary
Chapter 8
Concrete Structures and Foundations
Part 1
Materials, Tests and Construction Requirements
Part 2
Reinforced Concrete Design
Part 3
Spread Footing Foundations
Part 4
Pile Foundations
Part 5
Retaining Walls, Abutments and Piers
Part 6
Crib Walls
Part 7
Mechanically Stabilized Embankment
Part 10 Reinforced Concrete Culvert Pipe
Part 11 Lining Railway Tunnels
Part 12 Cantilever Poles
Part 14 Repair and Rehabilitation of Concrete Structures
Part 16 Design and Construction of Reinforced Concrete Box Culverts
Part 17 Prestressed Concrete
Part 19 Rating of Existing Concrete Bridges
Part 20 Flexible Sheet Pile Bulkheads
Part 21 Inspection of Concrete and Masonry Structures
Part 22 Geotechnical Subsurface Investigation
Part 23 Pier Protection Systems at Spans Over Navigable Streams
Part 24 Drilled Shaft Foundations
Part 25 Slurry Wall Construction
Part 26 Recommendations for the Design of Segmental Bridges
Part 27 Concrete Slab Track
Part 28 Temporary Structures for Construction
Part 29 Waterproofing
© 2010, American Railway Engineering and Maintenance-of-Way Association
vi
AREMA Manual of Railway Engineering
Table of Contents
VOLUME 2 – STRUCTURES (CONT)
Chapter 9
Seismic Design for Railway Structures
Part 1
Seismic Design for Railway Structures
Part 2
Commentary to Seismic Design for Railway Structures
Chapter 15 Steel Structures
Part 1
Design
Part 3
Fabrication
Part 4
Erection
Part 6
Movable Bridges
Part 7
Existing Bridges
Part 8
Miscellaneous
Part 9
Commentary
Part 10 Bearing Design
Part 11 Bearing Construction
General Subject Index
VOLUME 3 – INFRASTRUCTURE AND PASSENGER
Commuter, Transit and High Speed Rail - Unified Table of Contents and Common Elements of
Planning, Design and Operations Analyses for Passenger Rail Systems
Chapter 6
Buildings and Support Facilities
Part 1
Specifications and General Design Criteria for Railway Buildings
Part 2
Design Criteria for Railway Office Buildings
Part 3
Design Criteria for Spot Car Repair Shops
Part 4
Design Criteria for Diesel Repair Facilities
Part 5
Energy Conservation and Audits
Part 6
Locomotive Sanding Facilities
Part 7
Design Criteria for Railway Materials Management Facilities
Part 8
Design Criteria for Railway Passenger Stations
Part 9
Design Criteria for Centralized Maintenance-of-Way Equipment Repair Shops
Part 10 Design Criteria for Observation Towers
Part 11 Design Criteria for CTC Centers
Part 12 Design Criteria for a Locomotive Washing Facility
Part 13 Passenger Rail (Coach)/Locomotive Maintenance, Repair and Servicing Facilities
Part 14 Selection and Maintenance of Roofing Systems
Part 15 Inspection of Railway Buildings
Part 16 Design Criteria for Main Line Fueling Facilities
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual of Railway Engineering
vii
Table of Contents
VOLUME 3 – INFRASTRUCTURE AND PASSENGER (CONT)
Chapter 11 Commuter and Intercity Rail Systems
Part 1
Introduction
Part 2
Corridor Planning Considerations
Part 3
Track and Roadway Considerations
Part 4
Facilities and Structural Considerations
Part 5
Vehicle Considerations
Part 6
Signals, Communications, and Propulsion Considerations
Part 7
Maintenance of Way Considerations
Chapter 12 Rail Transit
Part 1
Introduction
Part 2
Corridor Planning Considerations
Part 3
Track and Roadway Considerations
Part 4
Facilities and Structural Considerations
Part 5
Vehicle Considerations
Part 6
Signals, Communications, and Propulsion Considerations
Part 7
Maintenance of Way Considerations
Part 8
Embedded Track
Chapter 14 Yards and Terminals
Part 1
Generalities
Part 2
Freight Yards and Freight Terminals
Part 3
Freight Delivery and Transfer
Part 4
Specialized Freight Terminals
Part 5
Locomotive Facilities
Part 6
Passenger Facilities
Part 7
Other Yard and Terminal Facilities
Chapter 17 High Speed Rail Systems
Part 1
Introduction
Part 2
Corridor Planning Considerations
Part 3
Track and Roadway Considerations
Part 4
Facilities and Structural Considerations
Part 5
Vehicle Considerations
Part 6
Signals, Communications, and Propulsion Considerations
Part 7
Maintenance of Way Considerations
Chapter 18 Light Density and Short Line Railways
Part 1
General Engineering
Part 2
Track
Part 3
Bridges
Part 4
Communication and Signals
Chapter 27 Maintenance-of-Way Work Equipment
Part 1
General
Part 2
Roadway Machines
© 2010, American Railway Engineering and Maintenance-of-Way Association
viii
AREMA Manual of Railway Engineering
Table of Contents
VOLUME 3 – INFRASTRUCTURE AND PASSENGER (CONT)
Chapter 33 Electrical Energy Utilization
Part 1
Factors to Consider in Making Electrification Economic Studies
Part 2
Clearances
Part 3
Recommended Voltages
Part 4
Railroad Electrification Systems
Part 5
Signal Compatibility with Alternating Current Railway Electrification
Part 6
Power Supply and Distribution Requirements for Railroad Electrification Systems
Part 7
Rail Bonding
Part 8
Catenary and Locomotive Interaction
Part 9
Ancillary Power Systems
Part 10 Illumination
Part 12 Power Supply and Electrification Systems
General Subject Index
VOLUME 4 – SYSTEMS MANAGEMENT
Chapter 2
Track Measuring Systems
Part 1
Definitions
Part 2
Track Measuring Vehicles
Part 3
Typical Uses of Data Collected by Track Measuring Vehicles
Part 4
Measurement Frequency Practices for Track Geometry Measuring Vehicles
Chapter 13 Environmental
Part 1
Introduction
Part 2
Environmental Review Considerations
Part 3
Water and Wastewater Compliance
Part 4
Air Quality Compliance
Part 5
Waste Management
Chapter 16 Economics of Railway Engineering and Operations
Part 1
Railway Location
Part 2
Train Performance
Part 3
Power
Part 4
Railway Operation
Part 5
Economics and Location of Defect Detector Systems
Part 6
Railway Applications of Industrial & Systems Engineering
Part 7
Public Improvements – Their Costs and Benefits
Part 8
Organization
Part 9
Programming Work
Part 10 Construction and Maintenance Operations
Part 11 Equated Mileage Parameters
Part 12 Accounting
Part 14 Taxes
Part 15 Planning, Budgeting and Control
Chapter 28 Clearances
Part 1
Clearance Diagrams – Fixed Obstructions
Part 2
Equipment Diagrams
Part 3
Methods and Procedures
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual of Railway Engineering
ix
Table of Contents
VOLUME 4 – SYSTEMS MANAGEMENT (CONT)
AAR Scale Handbook (Included for Information Only)
Part 1
Specifications for the Location, Maintenance, Operation, and Testing of
Railway Track Scales
Part 2
Basic Specifications for the Manufacture and Installation of Railway Track Scales
Part 3
Specifications for the Design and Installation of Low Profile, Pitless, and Instrumented
Railway Track Scales
Part 4
Rules for the Manufacture, Installation, Location, Operation and Testing of Railway
Master Track Scales
Part 5
Vehicle Scales
Part 6
Hopper Type Scales
Part 7
Belt Conveyor Scales (Amended 2009)
Part 8
Mass Flow Meters (Added 2010)
Part 9
Other Scales
Guide for SI Metrication
General Subject Index
© 2010, American Railway Engineering and Maintenance-of-Way Association
x
AREMA Manual of Railway Engineering
1
CHAPTER 1
ROADWAY AND BALLAST1
TABLE OF CONTENTS
Part/Section
Description
Page
1
Roadbed . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.1
Exploration and Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.2
Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.3
Construction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.4
Maintenance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-1-1
1-1-3
1-1-12
1-1-38
1-1-53
2
Ballast . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.0
Substructure Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.1
Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.2
Scope (1991) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.3
Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.4
Property Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.5
Production and Handling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.6
Loading (1988) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.7
Inspection (1988) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.8
Sampling and Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.9
Measurement and Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.10
Maintenance Practices . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.11
Sub-ballast Specifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-2-1
1-2-4
1-2-5
1-2-9
1-2-9
1-2-10
1-2-13
1-2-13
1-2-14
1-2-14
1-2-15
1-2-15
1-2-19
Natural Waterways . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.1
General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.2
Drainage Basin Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.3
Capacity of Waterway Openings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.4
Basic Concepts and Definitons of Scour . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.5
Calculating Scour. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.6
Protecting Roadway and Bridges From Scour . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.7
Means of Protecting Roadbed and Bridges from Washouts and Floods . . . . . . . . . . . . . . . .
1-3-1
1-3-4
1-3-5
1-3-7
1-3-20
1-3-25
1-3-60
1-3-148
3
1
The material in this and other chapters in the AREMA Manual for Railway Engineering is published as recommended practice to
railroads and others concerned with the engineering, design and construction of railroad fixed properties (except signals and
communications), and allied services and facilities. For the purpose of this Manual, RECOMMENDED PRACTICE is defined as a
material, device, plan, specification, principle or practice recommended to the railways for use as required, either exactly as presented or
with such modifications as may be necessary or desirable to meet the needs of individual railways, but in either event, with a view to
promoting efficiency and economy in the location, construction, operation or maintenance of railways. It is not intended to imply that
other practices may not be equally acceptable.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-i
1
3
TABLE OF CONTENTS (CONT)
Part/Section
3.8
3.9
4
Description
Page
Construction and Protection of Roadbed Across Reservoir Areas . . . . . . . . . . . . . . . . . . . .
Glossary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-3-150
1-3-159
Culverts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.1
Location and Type . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.2
Specifications for Placement of Reinforced Concrete Culvert Pipe . . . . . . . . . . . . . . . . . . .
4.3
Specifications for Prefabricated Corrugated Steel Pipe and Pipe-arches for Culverts,
Storm Drains, and Underdrains . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.4
Specifications for Coated Corrugated Steel Pipe and Arches. . . . . . . . . . . . . . . . . . . . . . . .
4.5
Standard Specification for Corrugated Aluminum Alloy Pipe . . . . . . . . . . . . . . . . . . . . . . .
4.6
Specifications for Corrugated Structural Steel Plate Pipe, Pipe-arches, and Arches. . . . .
4.7
Specifications for Corrugated Structural Aluminum Alloy Plate Pipe, Pipe-arches,
and Arches . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.8
Hydraulics of Culverts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.9
Design Criteria for Corrugated Metal Pipes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.10
Design Criteria for Structural Plate Pipes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.11
Culvert End Treatments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.12
Assembly and Installation of Pipe Culverts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.13
Earth Boring and Jacking Culvert Pipe through Fills . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.14
Culvert Rehabilitation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.15
Specification for Steel Tunnel Liner Plates . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.16
Construction of Tunnel Using Steel Tunnel Liner Plates . . . . . . . . . . . . . . . . . . . . . . . . . .
4.17
Culvert Inspection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.18
Perforated Pipe Drains . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-4-1
1-4-6
1-4-9
1-4-26
1-4-29
1-4-56
1-4-65
1-4-68
1-4-70
1-4-75
1-4-77
1-4-82
1-4-90
1-4-91
1-4-100
5
Pipelines . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.1
Specifications for Pipelines Conveying Flammable Substances. . . . . . . . . . . . . . . . . . . . . .
5.2
Specifications for Uncased Gas Pipelines within the Railway Right-of-Way . . . . . . . . . . .
5.3
Specifications for Pipelines Conveying Non-Flammable Substances . . . . . . . . . . . . . . . . .
5.4
Specifications for Overhead Pipelines Crossings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.5
Specifications for Fiber Optic “Route” Construction on Railroad Right of Way . . . . . . . .
1-5-1
1-5-3
1-5-11
1-5-23
1-5-29
1-5-31
6
Fences . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.1
General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.2
Specifications for Wood Fence Posts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.3
Specifications for Concrete Fence Posts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.4
Specification for Metal Fence Posts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.5
Specifications for Right-of-way Fences . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.6
Stock Guards . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.7
Methods of Controlling Drifting Snow . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.8
Specifications for Snow Fences . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-6-1
1-6-3
1-6-4
1-6-6
1-6-10
1-6-13
1-6-20
1-6-21
1-6-24
7
Roadway Signs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
7.1
Classification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
7.2
Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
7.3
Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-7-1
1-7-2
1-7-4
1-7-4
1-4-9
1-4-17
1-4-17
1-4-24
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-ii
AREMA Manual for Railway Engineering
TABLE OF CONTENTS (CONT)
Part/Section
Description
Page
8
Tunnels . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
8.1
Scope (1994) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
8.2
Design (1994) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
8.3
Construction (1994) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
8.4
Measurement and Payment (1982). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
8.5
Lining (1982) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
8.6
Ventilation (1982) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
8.7
Increasing Clearances In Existing Tunnels (1982) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-8-1
1-8-2
1-8-2
1-8-3
1-8-6
1-8-6
1-8-6
1-8-7
9
Vegetation Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
9.1
Rationale and Scope of Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
9.2
Preparing a Vegetation Control Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
9.3
Executing a Vegetation Control Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
9.4
Evaluating Results of a Vegetation Control Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
9.5
Glossary (1994) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
9.6
Lead Agencies (1994) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
9.7
Commentary (1994) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-9-1
1-9-2
1-9-2
1-9-11
1-9-14
1-9-16
1-9-17
1-9-20
10 Geosynthetics. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
10.1
Geotextile Specifications for Railroad Track Separation/Stabilization Applications . . . . .
10.2
Geotextile Specifications for Railroad Drainage Applications . . . . . . . . . . . . . . . . . . . . . . .
10.3
Geotextile Specifications for Railroad Erosion Control Applications . . . . . . . . . . . . . . . . . .
10.4
Geocomposite Drainage System Specifications for Railroad Applications . . . . . . . . . . . . . .
10.5
Cellular Confinement System Specification for Railroad Use . . . . . . . . . . . . . . . . . . . . . . .
10.6
Geogrid Specifications for Ballast and Sub-Ballast Reinforcement . . . . . . . . . . . . . . . . . . .
1-10-1
1-10-3
1-10-9
1-10-15
1-10-20
1-10-24
1-10-28
Glossary. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-G-1
References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-R-1
1
3
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-iii
INTRODUCTION
The Chapters of the AREMA Manual are divided into numbered Parts, each comprised of related documents
(specifications, recommended practices, plans, etc.). Individual Parts are divided into Sections by centered
headings set in capital letters and identified by a Section number. These Sections are subdivided into Articles
designated by numbered side headings.
Page Numbers – In the page numbering of the Manual (1-2-1, for example) the first numeral designates the
Chapter number, the second denotes the Part number in the Chapter, and the third numeral designates the
page number in the Part. Thus, 1-2-1 means Chapter 1, Part 2, page 1.
In the Glossary and References, the Part number is replaced by either a “G” for Glossary or “R” for References.
Document Dates – The bold type date (Document Date) at the beginning of each document (Part) applies to the
document as a whole and designates the year in which revisions were last made somewhere in the document,
unless an attached footnote indicates that the document was adopted, reapproved, or rewritten in that year.
Article Dates – Each Article shows the date (in parenthesis) of the last time that Article was modified.
Revision Marks – All current year revisions (changes and additions) which have been incorporated into the
document are identified by a vertical line along the outside margin of the page, directly beside the modified
information.
Proceedings Footnote – The Proceedings footnote on the first page of each document gives references to all
Association action with respect to the document.
Annual Updates – New manuals, as well as revision sets, will be printed and issued yearly.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-iv
AREMA Manual for Railway Engineering
1
Part 1
Roadbed1
— 2007 —
FOREWORD
Since the development of soil and foundation engineering as an important branch of civil engineering during the
past few decades, earth and rock have come to be treated as construction materials. They have properties which
can be evaluated and they are subject to strains and failures in the same way as other building materials.
Earth and rock are different, however, from such materials as steel and concrete in one fundamental way of which
the designer should always be aware: each soil and rock deposit is extremely variable and has its own
characteristics which reflect its origin and the factors affecting it since. As a result, investigation and testing are
uniquely important if soils and rock are to be used economically and safely in engineering work.
This Part of the Manual is prepared with recognition of the importance of geotechnical knowledge in the design,
construction and maintenance of track. The subgrade is considered to be as important to track performance as the
rail and ballast. Keeping this balanced point of view in mind, an engineered approach is presented for many
roadbed problems rather than reference to standard practice.
The choice of available methods is given along with an evaluation of the judgment factors involved in many of the
questions relating to the design and construction of new roadbed and the upgrading and maintenance of existing
roadbed. Considerations such as drainage and slope stability which affect the roadbed directly but are centered
outside its physical limits are included.
Because of the variety of foundation conditions which occur and their associated problems, a number of references
are given. Details of methods are presented only when adequate information is hard to find elsewhere. Specialized
help is advisable when a detailed appraisal of the suitability and performance of particular deposits is required.
1
References, Vol. 74, 1973, p. 55; Vol. 77, 1976, p. 237; Vol. 87, 1986, p. 35; Vol. 89, 1988, pp. 40, 41. Reapproved with revisions 1988.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-1
1
3
Roadway and Ballast
TABLE OF CONTENTS
Section/Article
Description
Page
1.1 Exploration and Testing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.1.1 General (2000) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.1.2 Preliminary Exploration (2000). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.1.3 Detailed Geotechnical Exploration in Soil (2000). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.1.4 Detailed Geotechnical Exploration in Rock (2000). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.1.5 Construction Material Sources (2000). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-1-3
1-1-3
1-1-3
1-1-4
1-1-6
1-1-8
1.2 Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.2.1 General (2002) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.2.2 Cuts (2002) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.2.3 Fills (2002) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.2.4 Drainage (2003) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-1-12
1-1-12
1-1-13
1-1-23
1-1-32
1.3 Construction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.3.1 General (2005) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.3.2 Contract Documents (2005) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-1-39
1-1-39
1-1-39
1.4 Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-1-55
1.4.1 Maintenance of Roadbed (2007). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-1-55
1.4.2
Maintenane of Rock Slopes (2007). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-1-64
1.4.3 Maintenance of Earth Slopes (2007) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-1-65
1.4.4 Widening of Cuts (2007) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-1-67
1.4.5 Drainage and Erosion Control (2007) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-1-68
1.4.6 Methods of Opening Snow Blockades (2007) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-1-70
LIST OF FIGURES
Figure
1-1-1
1-1-2
1-1-3
1-1-4
1-1-5
1-1-6
1-1-7
1-1-8
1-1-9
1-1-10
1-1-11
1-1-12
1-1-13
1-1-14
1-1-15
Description
Page
Cut and Fill Section Components. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Width of Rock Cut Base . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Variable Slope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Uniform Slope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Permanent Bench . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Temporary Bench . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Zoning of Rock Fill Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Interception of Sidehill Seepage by Subdrainage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Lowering of Ground Water In a Wet Cut. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Lowering of Ground Water in Cut to Fill Transition (Longitudinal). . . . . . . . . . . . . . . . . . . . .
Lowering of Ground Water in Cut to Fill Transition (Sidehill) . . . . . . . . . . . . . . . . . . . . . . . . .
Example of Distorted Roadbed Cross Section . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Example Cross Section of Displaced Roadbed and Ballast Pocket . . . . . . . . . . . . . . . . . . . . . . .
Method of Marking Track for Treatment of Frost Heaving . . . . . . . . . . . . . . . . . . . . . . . . . . . .
General Approach to Rock Fall Hazard Management. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-1-13
1-1-17
1-1-19
1-1-20
1-1-21
1-1-21
1-1-29
1-1-37
1-1-37
1-1-38
1-1-38
1-1-57
1-1-57
1-1-63
1-1-65
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-2
AREMA Manual for Railway Engineering
Roadbed
LIST OF TABLES
Table
1-1-1
1-1-2
1-1-3
1-1-4
1-1-5
1-1-6
1-1-7
1-1-8
1-1-9
1-1-10
1-1-11
1-1-12
Description
Sources of Site Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Procedures for Soil Exploration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Standard Procedures for Soil Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Technical Descriptions of Cores or Fresh Exposures of Rock . . . . . . . . . . . . . . . . . . . . . . . . . . .
Typical Tests for Rock Samples. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Factors Affecting Width of Cut . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Factors Affecting Base Width of Rock Cuts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Design Factors for Rock Slopes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Improvement of Soils . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Soil Groups, Their Characteristics and Uses . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Guidelines for Limiting Velocities to Prevent Erosion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Potential Methods for Stabilizing Earth Slopes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Page
1-1-8
1-1-10
1-1-10
1-1-11
1-1-12
1-1-14
1-1-17
1-1-22
1-1-27
1-1-30
1-1-33
1-1-66
SECTION 1.1 EXPLORATION AND TESTING
1
1.1.1 GENERAL (2000)
a.
Roadbed construction and maintenance costs can be reduced by using an effective exploration and testing
program as the first and most important step of the design process.
b.
Site investigations are usually done in two phases:
(1) PRELIMINARY SITE INVESTIGATION - Review of information available from published sources and
previous investigations, supplemented by site reconnaissance. Roadbed maintenance investigations
should include a history of slow orders, surfacing operations, drainage condition changes, apparent
failure mechanism, failure frequency, and apparent correlation with weather.
(2) DETAILED SITE INVESTIGATION - Collection and analysis of detailed information on soil, rock,
groundwater, surface drainage, and topography determined by exploration, sampling, and laboratory
testing. Detailed maintenance information should include investigation of the ballast roadbed
interface, particularly "ballast pockets", their density and drainage.
1.1.2 PRELIMINARY EXPLORATION (2000)
1.1.2.1 Information Available
a.
New Construction - Geological, topographic, climatic, and seismic information from published sources is
useful in planning exploration work and interpreting site observations. See Table 1-1-1.
b.
Maintenance - Review the information for new construction as noted in Table 1-1-1, supplemented by a
performance history of the problem area. Include a review of the slow order history, surfacing operations,
track geometry history, traffic density history, drainage conditions, apparent failure mechanisms, frequency
of failure, and apparent correlation with weather. Some problem maintenance areas will become readily
apparent when the above information is graphed with respect to time.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-3
3
4
Roadway and Ballast
1.1.2.2 Photogrammetry
1.1.2.2.1 New Construction
a.
Aerial photographs at various scales are available for most locations. Photo mosaics can be assembled and
used in studying the site conditions. Photos on a large scale may be required for more detailed studies and
can be obtained on order.
b.
Stereo-optic viewing of overlapping aerial photographs assists inrecognizing land forms, landslides, general
soil types, drainage, and erosional features. Photo interpretation can aid in supplementing ground
observations and in planning an appropriate detailed site investigation program. Since aerial photographs
only showconditions at or near the ground surface, they cannot be used independently to give detailed
subsurface information for design.
c.
Other techniques for obtaining general surface conditions and landform characteristics as well as more
detailed information for track layout, drainage design, and asset location may include ground or aerial based
LIDAR (Light Detection and Ranging) and video based surveying techniques.
1.1.2.2.2 Maintenance
Aerial photographs are not routinely utilized. Soil Conservation Service photographswith adjacent soil types
superimposed on them may be useful. Site specific aerial photographs can provide useful information relative to
the local surface drainage conditions.
1.1.2.2.3 Site Reconnaissance
a.
New Construction - A thorough reconnaissance of the site is necessary to assess the existing conditions and
establish the need for appropriate detailed tests. Effective site reconnaissance requires close observation of
apparent surface soil conditions and rock exposures, as well as ground surface and drainage patterns.
Observation of nearby excavations may provide useful information. A particular warning is given by the
presence of soft ground, soils, which become weak when disturbed, ground water seepage, and eroding soil
banks.
b.
Maintenance - A thorough reconnaissance of the existing roadbed is necessary to understand the true
nature of the roadbed failure mechanism. This will include examination of the roadbed cross section,
profile, alignment, track geometry, and surface drainage. Look for ground water seepage, roadbed erosion,
track squeeze, slides, irregularity of the shoulder vegetation lines, and any site specific anomalies which
may be influencing the site conditions. Trackside trees and pole line are excellent indicators of slope
movement in a maintenance situation.
1.1.3 DETAILED GEOTECHNICAL EXPLORATION IN SOIL (2000)
1.1.3.1 General Soil Exploration Criteria
Construction or maintenance of a roadbed frequently involves an interface with, or the excavation of, either
naturally deposited or mechanically placed soils. The ultimate stability of the roadbed will be governed by the
engineering characteristics and suitability of these soils. An adequate exploration program should be developed
with the assistance of a qualified geotechnical engineer to define these parameters. Procedures utilized can
include, but should not be limited to, those listed in Table 1-1-2.
1.1.3.2 Embankment (Fill) Foundations
1.1.3.2.1 New Construction
a.
Embankment foundations are explored so that the embankments are designed to avoid failure or
compensate for settlement of the subsoil. The subsurface and surface drainage conditions must be
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-4
AREMA Manual for Railway Engineering
Roadbed
determined to avoid conditions such as sinkholes, springs under the fill, excessive pore water pressures in
the foundation soils, and inadvertent interception of an underground aquifer.
b.
Depending on the material conditions encountered, the exploration and sampling requirements can be quite
different. When granular material is encountered in the embankment foundation the exploration and
sampling may be less then that required for cohesive soils but should be sufficient to confirm the range of
the strength parameters. The depth and number of borings should be sufficient to provide the design
information required.
c.
Areas of new construction immediately adjacent to existing track, such as new sidings and auxiliary main
lines, do not require detailed exploration. These areas would normally require few widely spaced borings
unless specific problem areas warrant further examination. On new construction to avoid major problems at
tie ins attention should be paid to grubbing, stripping, and benching.
1.1.3.2.2 Maintenance
The First order of business in a catastrophic failure on an existing railroad embankment is to get the railroad open
for service. This usually doesn't allow sufficient time to do a thorough detailed site exploration prior to
reconstructing the roadbed. Many troublesome maintenance failures are of a "creeping" type. These manifest
themselves in a poor or degrading track alignment and surface. This type of failure often requires substantial
exploration to determine the failure mechanisms. Failure mechanism exploration is site specific and may be very
complicated. Borings are required of sufficient depth to intercept any failure planes, as a minimum at least below
the embankment foundation or depth of failure plane whichever is greater. Exploration of maintenance failure
mechanisms should not be limited solely to boring. Other methods may include any of the following; cross
trenches or test pits, inclinometer, piezometer, or examination of the exposed failed embankment surfaces.
1.1.3.3 Cuts
1
1.1.3.3.1 New Construction
a.
b.
c.
Locations of proposed cut slopes are explored to design stable slopes and berms. In fine grained soils this
requires suitable samples and appropriate laboratory tests to determine the shear strength characteristics
of the materials. In cohesionless, disturbed samples and standard penetration test values are usually
adequate. In cohesive soils it may be necessary to obtain undisturbed tube samples for tests which include
classification, water content, and shear strength. Most importantly, exploration should be carried out at
least below the bottom of the proposed cut or deeper if recommended by the geotechnical engineer.
The exploration should determine the level of the groundwater table and efforts should be made to
determine whether or not a perched water table exists. This may require a rather elaborate investigation,
including the installation of standpipes at selected locations. Particular care should be taken to identify
cohesionless layers that might become water-bearing at certain times or seasons. These can be expected to
erode back from the face of the cut, causing local instability or a build-up of excess water pressure leading to
a failure.
Sufficient information should be obtained to classify the materials likely to be encountered, determining
suitability of the materials for use in adjacent fills. A knowledge of the geology of the area is useful to
indicate the necessity for additional tests of a specialized nature. Some geological formations have swelling
characteristics and should be investigated.
1.1.3.3.2 Maintenance
Typical failures in an existing cut include filled or non-functional ditches, surface water eroding the slope, shallow
ballast sections, and inadequate subgrade support. An initial means for assessing the potential cause of a problem
begins with performing a field observation. The question to be answered is, "What has caused a previously stable
slope to fail?" Examine the top of the slope. Check the slope for chemical changes in soil properties, seepage and
drainage changes, and additional loading surcharge above the top of slope. Use cross trenches, inclinometer, aerial
photography, and previous area history to help determine the failure mechanism.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-5
3
4
Roadway and Ballast
1.1.3.4 Laboratory Testing and Analysis
Appropriate laboratory tests and analysis methods will be dependent on the soils encountered, the desired
construction or existing roadbed configuration, and the sampling methods utilized. These can include, but should
not be limited to, the tests listed in Table 1-1-3.
1.1.4 DETAILED GEOTECHNICAL EXPLORATION IN ROCK (2000)
1.1.4.1 General Rock Exploration Criteria
1.1.4.1.1 New Construction
a.
When construction of roadbed involves an interface with natural rock bedding (embankment fills), or
requires rock excavation and slope design (rock cuts), it is imperative that adequate insitu and laboratory
information is obtained on the structural nature of the rock. Beyond providing for sound design,
preliminary information will provide realistic parameters for estimating both construction costs and
schedules.
b.
The methods of obtaining information on rock formations can be grouped into two (2) categories: 1)
empirical - a study based solely on existing geological information and visible surface features, or 2)
intrusive - a study in which existing information is supplemented by subsurface exploration and testing of
the rock mass.
c.
The ultimate stability of a roadbed engineered through rock will be defined by the nature of any structural
discontinuities which may exist at the location. Major rock cuts will typically require detailed subsurface
exploration. Minor rock cuts often may be designed by an experienced engineer without subsurface
exploration. Both methods are valid provided that an educated decision is made for appropriateness. The
planning and execution of this exploration should be conducted with the assistance of a qualified
Engineering Geologist.
1.1.4.1.2 Maintenance
When roadbed maintenance problems exist as a result of existing rock cut slopes, or the failure of the embankment
bedding structure, it may be necessary to assess the stability of the associated rock structures prior to undertaking
corrective measures. Such assessments may require an intrusive study, but in many cases can be explored by a
detailed site investigation of geologic surface features and a thorough review of original construction plans and
exploration records.
1.1.4.2 Rock Exploration Methodology
1.1.4.2.1 New Construction
a.
The first step of the exploration process involves a detailed geological reconnaissance and mapping of site.
Utilize visible outcroppings to predict the strike and dip of beds, as well as to identify obvious faults,
discontinuities, jointing and fracture patterns. Utilize auger borings or test trenches through soil
overburden, to determine initial rock surface profiles when rock is not visible.
b.
From this information an exploration plan should be devised which will provide a continuity of data
regarding structure of rock. Undisturbed rock samples should be obtained from fresh unweathered
exposures at the site, or from core samples recovered from borings. To the extent possible, the subsurface
exploration program should be designed in an attempt to reveal potential structural discontinuities. Core
recovery should be monitored by a qualified Engineering Geologist, so that necessary changes may be made
to maximize recovery of useful data. The spacing and depth of bores will be project specific. All bores
should be advanced to a depth which is sufficient to verify the competency of the proposed subgrade. At
minimum, this depth will be the proposed subgrade elevation. On cuts of significant depth, exploration
should extend well outside the proposed centerline as significant discontinuities may exist which could
affect design of the upper portions of slopes. Detailed drilling logs should be maintained and the recovered
samples should be preserved for a mutually agreed upon period of time.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-6
AREMA Manual for Railway Engineering
Roadbed
c.
Undisturbed core samples are typically obtained using a standard diamond-tipped rock boring machine
equipped with a continuous recovery tube. The minimum size for a recovery tube should be type BX (15/8"), with sizes NQ (2") and NX (2-1/8") being more commonly used. For projects in areas of suspected
geologic irregularities use of even larger recovery tubes may be of value. Such a determination can be based
on the preliminary geologic data for the site.
1.1.4.2.2 Maintenance
Exploration of rock as related to roadbed maintenance problems, will rely primarily on visual examination of
exposed rock surfaces. When existing surface conditions do not obviously reveal the causes of the problem, it may
be necessary to use intrusive exploration techniques to identify the depths at which competent material is present.
This may reveal the presence of faults, fracture patterns, and structurally weak layers that could affect the
stability of the associated rock mass.
1.1.4.3 Examination and Testing
a.
Rock samples and cores provide an important record of visible structura information. Samples should be
examined and a final geologic log accurately prepared. See Table 1-1-4 for a list of recommended descriptive
terminology. The resulting data should be consolidated in a usable format which may include detailed
boring logs, and cross-sectional mapping of the rock structure. In general this detailed information provides
the primary tool for the Design Engineer in predicting the theoretical structural behavior of the rock mass.
This base information provides only qualitative design values which are used in part for detailed strength
and stability analysis .
b.
Representative samples from the rock cores can be utilized to determine the strength and deformation
characteristics of the rock as well as its potential for weathering. See Table 1-1-5 for a list of possible test
methods. These tests can provide much more precise design values, but test suitability is job specific and
should be determined with the assistance of an Engineering Geologist.
c.
Since many variables exist regarding rock mechanics, providing the most comprehensive information
available in a usable format will greatly assist the Design Engineer in development of a viable design or
corrective scheme.
1
3
1.1.5 CONSTRUCTION MATERIAL SOURCES (2000)
1.1.5.1 Site Sources
Borrow areas for soil embankment fill construction are often preliminarily explored by auger boring. The
suitability of such soils can be further verified by utilizing the sampling and testing procedures outlined elsewhere
in this section.
1.1.5.2 Commercial Sources
Select granular fill materials supplied by off-site commercial sources for use in embankment fill construction are
typically produced to defined specifications and should be tested to ensure consistent quality control.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-7
4
Roadway and Ballast
Table 1-1-1. Sources of Site Information
Type of Information and Usage
Source
Geological Surveys:
National:
National: Indexes to existing geologic mapping
United States - U.S. Geological Survey
and exploration.
Canada - Canadian Geological Survey
Detailed maps of Topography, Surface
Mexico - Colegio de Ingenieros de
Mineros, Metalurgistas y
and Subsurface structural
Geo’logos de Mexico
information.
Localized:
Correlation and characteristics of
State and Provincial Geological
geological deposits.
Surveys and Societies
Localized: Maps, bulletins, and reports on
Other:
locally unique subjects.
Independent Geologic Societies
Existing & Historical Land Use:
Maps and documents available on
exploration and use of mineral and
geologic resources.
Information on the structural nature
of deposits, and identification of
subsurface excavations and
discontinuity.
United States - Bureau of Land Management,
Department of Surface Mining,
Department of Mine Reclamation,
American Petroleum Institute
Canada - Department of Energy, Mines &
Resources (DEM&R)
Mexico - Com. de Fomento Minero Instituto
Nacional de Statistica Geografica
Informativa (INEGI)
Generalized Soil Information:
Maps and reports on surface
conditions with summaries of
subsurface geological conditions.
National:
United States - Department of
Agriculture Soil Conservation
Service
Canada - DEM&R, Environment
Canada
Mexico - ENEGI
Localized:
State and Provincial Conservation and
Agricultural Agencies
Aerial Photographs:
See Section:1.2.2
National:
United States - Department of
Agriculture Soil Conservation
Service
Canada - DEM&R, Environment
Canada
Mexico - ENEGI, Cia Topografica,
Ingenieria y Aerofotogrametri
Localized:
State and Provincial Agricultural or
Economic Development Agencies
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-8
AREMA Manual for Railway Engineering
Roadbed
Table 1-1-1. Sources of Site Information (Continued)
Type of Information and Usage
Atomospheric Conditions:
Information on rainfall and
temperature variation necessary for
the analysis of drainage, weathering
and frost penetration
Source
National:
United States - National Oceanic &
Atmospheric Administration,
National Weather Service
Canada - Environment Canada
Mexico - Servicio Meteorologico,
Servicio a la Navegacion en el
Espacio Aereo Mexicano
Localized:
State and Provincial Conservation and
Agricultural Agencies
Building and Seismic Design Codes:
United States - State and Municipal Building
Information on construction methods
Code Agencies
Canada - National Building Code
or design requirements.
Seismic considerations.
Mexico - Departamento del Distrito Federal
1
3
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-9
Roadway and Ballast
Table 1-1-2. Procedures for Soil Exploration
Procedure
ASTM Method
Site Characterization for Engineering, Design & Construction Purposes
D 420
Soil Investigation and Sampling by Auger Borings
D 1452
Penetration Test and Split-barrel Sampling of Soils
D 1586
Thin-wall Tube Geotechnical Sampling of Soils
D 1587
Field Vane Shear Test in Cohesive Soils
D 2573
Deep, Quasi-Static, Cone & Friction – Cone Penetration Tests of Soil
D 3441
Table 1-1-3. Standard Procedures for Soil Testing
Procedure
ASTM Method
Material Finer than No. 200 Sieve in Mineral Aggregates by Washing
C 117
Particle Size Analysis of Soils
D 422
Laboratory Compaction Characteristics of Soil using Standard Effort
D 698
Specific Gravity of Soils
D 854
Laboratory Compaction Characteristics of Soil using Modified Effort
D 1557
Density and Unit Weight of Soil in Place by the Sand-Cone Method
D 1556
Unconfined Compressive Strength of Cohesive Soil
D 2166
Density and Unit Weight of Soil in Place by the Rubber-Balloon Method
D 2167
Laboratory Determination of Water (moisture) Content of Soils & Rock
D 2216
One-Dimensional Swell or Settlement Potential of Cohesive Soils
D 4546
Classification of Soils for Engineering Purposes
D 2487
Description & Identification of Soils (visual-manual procedure)
D 2488
Liquid Limit, Plastic Limit, and Plasticity Index of Soils
D 4318
Maximum Index Density & Unit Weight of Soils Using a Vibratory Table
D 4253
Minimum Index Density & Unit Weight of Soils and Calculation of Relative Density
D 4254
Consolidated-Undrained Triaxial Compression Test of Cohesive Soils
D 4767
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-10
AREMA Manual for Railway Engineering
Roadbed
Table 1-1-4. Technical Descriptions of Cores or Fresh Exposures of Rock
Feature
Discontinuity
- Type
Description or Occurrence
Importance
Influence on Permeability,
Joints
Faults
Strength, and Deformation of
Bedding Planes (as in Sedimentary Rock) the Rock Mass.
Cleavage Planes (as in Slates)
Fracture with Striations or Slickenslides
(from past movement)
- Position
Closeness and Orientation of Joints
Thickness of Bedding Layers
Length of Core Pieces (as influenced by
drilling techniques)
Dip or Angle of Inclination from
Horizontal
Of Major Importance in Cut
Slopes and Tunnels.
- Surface
Fit of Surfaces - Tight or Open
Shape - Plane, Curved, or Irregular
Texture - Slick, Smooth, or Rough
Governs amount of
Interlocking and Apparent
Shearing Resistance along
Fractures.
Filling Material
May Govern Movement along
Properties - Type, Hardness, Thickness,
Discontinuities.
Variations
Origin - Derived from Rock by Alteration,
or from External Source
Rock Type and
Texture
Geologic Name Based on Mineral
Composition, Texture and Origin
Size and Angularity of Grains, Type of
Fracture, Luster, Lamination
Texture - Interlocking Grains Cemented
or Laminated - Foliated, Preferred
Orientation
Rock Hardness
Core
Recoverability
1
3
Relative hardness (give basis of
comparison)
Variations Due to Changes in Rock Type,
Weakened Rock, Weathering or
Decomposition Products
Severe Design and
Construction Problems may
Arise when Hardness of Parts
of Rock Mass Differ Radically
from Average Value.
Total Core Recovery (%)
Rock Quality Designation (RQD)
Identifies Weak Core
Classifies Relative Strength
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-11
Roadway and Ballast
Table 1-1-5. Typical Tests for Rock Samples
Procedure
ASTM Method
Specific Gravity and Absorption of...
- Coarse Aggregate
- Fine Aggregate
Soundness of Aggregates by use of
Sodium Sulfate or Magnesium
Sulfate
Resistance to Degradation by Impact
and Abrasion using the Los
Angeles Machine of...
- Large Size Coarse Aggregate
- Small Size Coarse Aggregate
Petrographic Examination of
Aggregate
Compression
- Uniaxial
C 127
C 128
C 88
To Indicate Rock’s Resistance to
Weathering
C 535
C 131
To serve as a measure of degradation
of mineral aggregates from a
combination of actions including
abrasion or attrition, impact and
grinding.
C 295
See text
Special
- Triaxial Stength of Undrained
Rock Core Specimens without
Pore Pressure Measurements
Comments
D 2664
SECTION 1.2
To Classify Rock for Strength and
Deformation Properties.
Utilizes Diamond Drilled Cores.
To Find Angle of Shearing Resistance
of Weak Rock Material with Random
Orientation of Joints.
Range of Normal Stresses Occurring
in Field are Applied.
DESIGN
1.2.1 GENERAL (2002)
a.
This section describes material and drainage issues that need to be evaluated as part of the design of cuts
and fills along railroad roadways. It is assumed that the general project alignment has been selected, field
exploration and soil sampling have been performed, and laboratory testing is completed prior to
commencing with the final design. Issues for consideration in design include horizontal and vertical
alignments and typical sections all of which are influenced by traffic considerations, topographical features,
drainage, and soils and rock data. Environmental conditions such as drainage, wetlands and contaminated
soils also influence the design.
b.
Subjects which could be common to both design and maintenance are found in Section 1.4, Maintenance.
These subjects include unstable subgrade conditions, frost heaving of tracks, rock falls, both cut and fill
slope failures, and erosion control. The issues which are discussed in Section 1.2, Design, address how soils
and drainage influence cuts and fills.
1.2.2 CUTS (2002)
1.2.2.1 General
a.
Definition: Cuts are made when excavations are required through hills to provide roadbed grades and to
acquire materials for use when constructing fill sections. Materials encountered in cuts can consist of
cohesive soils, cohesionless soils, rock or combinations thereof. The general components of a cut (and fill)
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-12
AREMA Manual for Railway Engineering
Roadbed
section consist of the back slope(s), benches (if required), foreslope(s), ditches, and the top of subgrade
(track roadbed) as presented in Figure 1-1-1. The “cut” width is the total of the backslope(s), ditches,
foreslope(s) top of subgrade widths, and interceptor ditches where required for the section(s). The purpose
of each of these segments are defined in Table 1-1-6.
1
Figure 1-1-1. Cut and Fill Section Components
3
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-13
Roadway and Ballast
Table 1-1-6. Factors Affecting Width of Cut
SEGMENT
PURPOSE
WHERE PROVIDED
WIDTH & PROFILE
A. Top of Subgrade
To provide a base for sub- Throughout cut and
ballast, ties, rails and
fill sections.
service roads.
Standard width.
B. Foreslope
To safely support track
and road subgrade. To
place subgrade at safe
height above maximum
design drainage levels.
Standard width.
C. Ditch
To carry run-off from
In all cuts.
watershed served and
seepage entering cut
while preventing
development of unstable
track subgrade
conditions.
Width as required to accomodate
hydraulics. Profile may need to
be different than track profile in
long level cuts.
D. Backslope
Resultant excavation
face located between
outer ditch line and
natural ground line.
Variable width depending on
slope, height of cut face, soil
stability, maintenance and
erodibility.
Throughout cut and
fill sections.
In all cuts.
E. Interceptor Ditches To carry runoff from the Above cut slope.
watershed served and
prevent surface runoff
from entering the cut.
b.
Width as required to
accommodate hydraulics.
Cut Section Design Requirements: The track roadbed (top of subgrade) portion of a cut should remain
stable during the excavation and track laying operations, and once the railroad line has been placed into
operation. Cut section design issues also include providing back slopes and foreslopes that will not fail.
Drainage ditches need to be sized to accommodate surface runoff and subsurface water which may seep
from the backslope face. Ditches made within rock cuts may need to be designed having additional width for
catchment of rock materials which may fall from the backslope face. Primary consideration when designing
this catchment width is to position the toe of slope at a point that will not allow falling rock fragments to
bounce into the track area. The working width required by ditch cleaning machines is important. The
materials that will be encountered in the cut must be evaluated for excavatability. Cuts may need to be
designed with flat slopes to facilitate self-cleaning by prevailing winds and minimize snow storage.
Benching of the backslope may be required to accommodate drainage and to catch falling rocks.
1.2.2.2 Back Slopes in Cuts
Slope stability analysis should be performed to aid in selecting the steepest safe backslope section. Cross-sections
should then be drawn transverse to the proposed track alignment to determine if safe cuts can be made within the
right-of-way lines or if additional right-of-way or soil slope reinforcement will be required for the project. Soils and
rock materials having varying strengths may necessitate that the backslope be cut at varying slopes. Subsurface
water that seeps from the face of the backslopes can facilitate embankment instability. Vertical interceptor drains
and horizontal drains may need to be designed into the backslope to intercept subsurface groundwater flow and
reduce hydrostatic pressures which could cause embankment instability.
1.2.2.3 Drainage Ditches in Cuts
Ditches designed for drainage and catchment (as shown in Figure 1-1-2) should be designed to have the capacity to
handle regional surface water runoff, snow storage and talus. The capacity is influenced by the width, depth and
gradient of the ditch. Reference should be made to Article 1.2.4 which provides specific ditch design guidelines.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-14
AREMA Manual for Railway Engineering
Roadbed
1.2.2.4 Track Bed Performance in Cuts
Track performance is enhanced by providing uniform stable subgrade conditions through out a given cut.
Providing drainage of the immediate subgrade materials generally improves subgrade stability by increasing the
materials strength while reducing the detrimental effects of frost action. Longitudinal and transverse drains can
be designed to facilitate subgrade drainage.
1.2.2.5 Cuts in Soil
1.2.2.5.1 General
a.
Considerations such as the proposed slope angle, drainage conditions, and moisture conditions and strength
of the soils encountered in a cut are the most significant factors that influence the stability of earth slopes.
All sloping soils have a tendency to move under the influence of gravity. Slope stability evaluations should
generally be made to select the cross-section for cuts over 15 feet deep. Observations of nearby cuts in
similar soils and natural slopes in the project locale can aid in slope design.
b.
It is important that the cut cross-section be wide enough to provide side ditches for interception of surface
water. Where it is not practical to collect surface drainage with adequate ditches, buried drainage pipes can
be provided. It may be very important to relieve subsurface water pressure in sloping ground to avoid slope
failures. The subsurface water pressure may be reduced by installing interceptor ditches or drains above
the slope, or horizontal buried drainage pipes at critical depths within the slope either longitudinal or
transverse to the cut face. In rare cases, vertical wells may be required.
1.2.2.5.2 Cuts in Cohesionless Soils (Sands and Gravels)
a.
Sands and gravels that are located above the ground water level generally will stand safely at a slope
2(H):1(V) or flatter. Steeper slopes may be able to be excavated and stand for short periods of time, but will
eventually try to assume a flatter slope. Finished slopes in sand-gravel materials that are exposed to
groundwater flow or seepage from the backslope face will routinely have to be cut flatter than would be
required for the same cohesionless soil cut in a non-saturated state. In areas of loose saturated cohesionless
soils, special provisions may be required to avoid liquefaction.
b.
The stability of slopes in sand is generally improved as the density of the cohesionless soil increases.
1
3
1.2.2.5.3 Cuts in Cohesive Soils (Silts and Clays)
a.
Cuts in cohesive soils need to be designed with caution. Previously stable slopes have been known to fail.
Cuts in cohesive soils should be designed using slope stability analysis. Local long-term experience may
prove to be an indicator of a stable slope for a particular soil profile. A slope of 2(H):1(V) or flatter generally
proves stable in cohesive soils. Clay slopes over 10 to 15 feet in height should be designed on the basis of
laboratory tests and slope stability analysis. In general, the higher the cut section becomes the flatter the
slope will have to be to remain stable. Highly plastic clay soils require flatter slopes than those discussed
above.
b.
The stability of clay slopes can be increased by the installation of drains and by flattening the cut slope.
c.
Cut slopes in areas where it is known that slides are inevitable may be designed to allow for slope movement
(failure) without interference to traffic.
1.2.2.5.4 Cuts in Non-Uniform Soils
Cuts in soils which are layered or contain seams of varied soil types should be designed on the basis of a slope
stability analysis. The seams that contain cohesionless (granular) soils are often water bearing during some part of
the year and drainage of these seams should be provided. Effective drainage may stabilize an otherwise unstable
slope if the soil properties of the unsaturated (drained) embankment soils are adequate.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-15
4
Roadway and Ballast
1.2.2.5.5 Cuts in Loess
In site specific cases cuts in loess can be designed with near-vertical or flatter slopes based upon the engineering
properties of the soils and the findings of slope stability analysis. Cuts in loess that are designed to have a nearvertical face should be carefully drained at the foot and top of the face. Loess soils possess a natural cementation
that is soluble, a uniform grading, and a vertical root hole structure. Deep cuts can be made with near vertical
faces and berms, but it is critical to the stability of the backslope that drainage be carefully designed and
maintained so that water does not accumulate atop the benches.
1.2.2.5.6 Cut Slope Summary
For every soil type it is necessary to maintain a safe and stable cut section. This should be the primary
consideration during design. Berms, drainage, erosion protection, filter layers, vegetation and proper selection of
the finished cut slope angle should be used as a means of achieving this end. Discussion is provided in Article 1.4.3
and Article 1.4.5. Cribs or retaining walls may be used in troublesome sections where berms and other less costly
means of providing a stable cut slope are unable to be installed. Details for the design of crib and retaining walls
are given in Chapter 8, Concrete Structures and Foundations. While slope control structures and techniques add
to costs, they will pay dividends in reduced requirements for slope restoration and ditch cleaning.
1.2.2.6 Cuts in Rock
1.2.2.6.1 General
The design of a rock cut is predicated on obtaining the lowest balanced construction and maintenance cost
consistent with safety. The ratio between construction and maintenance costs will vary with individual situations
and should be developed for each project.
1.2.2.6.2 Assembly of Design Information
a.
Factors which should be evaluated when designing rock cuts are the 3-dimensional competence of the rock
and overburden, and the depth and length of the cut.
b.
The first steps in design are the preparation of profiles and cross sections on which are plotted data obtained
during site investigation, test borings and laboratory testing, interpreted with the aid of geological maps,
groundwater surveys and aerial photographs. Knowledge of the behavior of similar rock in comparable cuts
can prove to be valuable design information.
c.
In layered formations, where dip or strike of the bedding planes is not normal to the center of the cut, it may
be desirable to evaluate sections on the dip of the bedding planes to aid in examining the stability of the cut
slope.
d.
As the characteristics of bedrock often vary greatly (over short distances) it is fundamental for economy that
the slope be fitted to the material and exposure on each side of the cut at each location. A uniform slope in
one segment of rock is not necessarily appropriate throughout the length of a cut if the condition of the rock
(i.e., strike and dip of bedding planes, fracturing, etc.) changes.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-16
AREMA Manual for Railway Engineering
Roadbed
1.2.2.6.3 Width of Base of Cut in Rock
The base width of a rock cut is determined by the total width of zones A, B, and C, shown in Figure 1-1-2 and
described in Table 1-1-7. Refer also to Article 1.2.2.6.7.
Figure 1-1-2. Width of Rock Cut Base
1
Table 1-1-7. Factors Affecting Base Width of Rock Cuts
SEGMENT
PURPOSE
WHERE PROVIDED
WIDTH & PROFILE
3
A. Roadbed
To provide base for
supporting ballast, ties
and rail.
Throughout cut.
Standard width.
B. Drainage Ditch
To carry run-off from
watershed served,
seepage entering cut,
and for service road.
Throughout cut.
Standard width with profile that may
have to be steeper than track profile
in long level cuts.
C. Catchment Ditch To contain material
Within broken or
(Optional)
which may fall from
rapidly weakening
faces of cut, and for
rocks cuts.
service and maintenance
access.
Of variable width depending on slope
and height of cut face, size and rate of
fall fragments and desirable frequency
of ditch cleaning. Primary
consideration in setting width is to
position the toe of slope at a point
which will not allow falling fragments
to bounce into track area. Working
width required by ditch cleaning
machines is important.
1.2.2.6.4 Stability of Rock Slopes
a.
Safe slopes are governed by the characteristics of the rock in the slope. Slope angles should be chosen
independently even in the same cut for sound rock, weathered or shattered rock, and overburden. See
Figure 1-1-3, Figure 1-1-4, Figure 1-1-5 and Figure 1-1-6.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-17
4
Roadway and Ballast
b.
For each rock material the slope is governed to a major degree by bedding planes, joints which are usually
perpendicular to the bedding, fracture patterns and faulting, all of which tend to make the rock perform as
a number of segments rather than as a mass. The influence of each of these characteristics should be
carefully assessed in analyzing slope stability. It should be noted that the slope of such discontinuities, as
entered on cross-sections, and profiles will not necessarily show their true angle of interception with the cut
slope, which should be considered in design.
c.
Stability of rock slopes can be analyzed using 3-D slope stability analysis with use of a stereo net software
program, or by the method of slices (when appropriate) as used with soil slopes, but it should be realized
that the surface of sliding will follow rock joints and defects where possible. Values of shear strength
(friction angle and cohesion) are chosen accordingly. Cohesion is usually neglected as its value along joints
in rock may be small. Experience is needed to design major slopes with safety and economy.
d.
Design factors for the more common rock conditions are discussed in Table 1-1-8. The effects of water
(hydrostatic) pressure in fissures is of primary importance in all cases.
e.
Rock falls and slides commonly occur during or soon after heavy rains, which is an indicator of the major
importance of seepage pressures on slope stability. Water has the dual effect of increasing shear stresses in
the slope by its weight and hydrostatic pressure, and at the same time decreasing the shear strength of rock
materials by weathering, freezing and expansion. Hence, it is important to keep water out of the slope if
possible.
Figure 1-1-3. Variable Slope
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-18
AREMA Manual for Railway Engineering
Roadbed
1
3
Figure 1-1-4. Uniform Slope
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-19
Roadway and Ballast
Figure 1-1-5. Permanent Bench
Figure 1-1-6. Temporary Bench
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-20
AREMA Manual for Railway Engineering
Roadbed
Table 1-1-8. Design Factors for Rock Slopes
Condition of Rock
Design of Slope
Hard rock with
random joints
Providing there are no adverse bedding planes or joint systems, ground water pressures
are low and blasting is presplit, slopes of 70 degrees are stable.
Layered rock
An accurate joint survey is important. If rock dips with the slope, and dip angle is greater
than angle of friction, critical slope is at angle of dip. If bedding is horizontal, stability is
as for massive rock. If bedding dips into slope, critical slope is between 70 degrees and 90
degrees; local rock falls may be frequent.
Fractured or
weathered rocks
Stability can be analyzed using shear strength parameters derived from field
observations. Angle of friction for angular crushed rock varies between 45-50 degrees.
Clay-shale rocks
Specialist advice is required as unloaded shale tends to decrease in strength with time.
f.
In most rock masses, the ground water table cannot be lowered economically. However, intercepting surface
ditches at the top of the slope or horizontal relief drains in the face or at the toe of the slope may have
benefits in certain cases (see Section 1.4, Maintenance).
1.2.2.6.5 Effect of Blasting
Uncontrolled blasting tends to open up cracks near the face of rock slopes, allowing an increase in the rate of
weathering, infiltration of water and consequent deterioration of the slope. Such blasting may facilitate excessive
rock falls for many years. A decision on the type of blasting should be part of the design procedure. The technique
of pre-splitting by blasting a line of drill holes on centers less than 4 feet apart can produce a slope surface with
minimum disturbance and negligible overbreak. Preservation of the rock segments in their pre-construction
position allows valid design assumptions to be made and minimizes ultimate maintenance costs.
1
1.2.2.6.6 Use of Benches on Rock Slopes
a.
Benches in rock cuts are used to catch falling rock, to prevent undermining of hard strata by differential
weathering, to reduce pressures at the toe of cuts and to handle drainage. Principles applying to the choice
of rock slopes and benches are illustrated in Figure 1-1-3, Figure 1-1-4, Figure 1-1-5, and Figure 1-1-6.
Where permanent benches are used to intercept falling rock, as shown in Figure 1-1-5, access should be
provided for periodic removal of debris. The width of such benches should be adequate for machine access
after weathering of the softer rock has taken place. A minimum width of 20 to 30 feet may be required.
b.
In shales and other soft-rock cuts, temporary benches may be designed to contain all debris from a steep
slope.
c.
A typical arrangement is shown in Figure 1-1-6. Debris from the top of the steep slope accumulates on the
bench to form a protective zone for the toe of the slope, while the upper portion of the steep slope weathers
back to its angle of repose. Provision for access to such slopes may not be required.
d.
Benches used to reduce the effects of differential weathering are located at the top of the weaker rock where
the stronger rock is set back to form the bench. The width of the bench is governed by the weathering
characteristics of the weaker rock and the height and angle of its slope. Provision for access may not be
required.
e.
In deep rock cuts, where weaker rock appears in the base of the cut, it may be necessary to introduce
benches to relieve the toe pressure. Such benches may serve other purposes, as noted above, to increase
safety and reduce maintenance costs.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-21
3
4
Roadway and Ballast
f.
A permanent bench may be required for accommodating longitudinal drainage from surface run-off or
subsurface seepage. Such an arrangement is usually complicated and expensive and should be avoided,
except in special circumstances.
g.
Drainage of benches is best accomplished by sloping them to the face of the cut thus moving water off the
bench as quickly as possible. Where rock on the surface of the bench presents open joints or fractures,
water may be prevented from entering the rock mass by covering the bench with a layer of clay or other
impervious material, thus reducing or eliminating deterioration of the rock by ice wedging and erosion.
1.2.2.6.7 Catchment Ditch Design
a.
In rockfall zones where benches cannot be provided, design of the slopes and catchment ditches are
important to prevent rock fragments from reaching the track. Falling rocks striking a slope flatter than
vertical will receive a horizontal component of force tending to throw them toward the track area. For this
reason, in rockfall zones the slope should be kept as nearly vertical as possible consistent with overall
stability.
b.
Unless mature cuts in similar rock can be observed, it is difficult to predict at the design stage the manner
in which rocks will fall and how fast they will accumulate at the base of the slope. Hence, ditches should be
designed with ample width to collect rockfall material, keep it out of the track area and permit economical
removal of debris. The cost of enlarging drainage ditches later to provide a catchment zone in rock cuts is
prohibitive.
c.
Measures described in Article 1.4.2 on maintenance of rock slopes may be incorporated in the design stage if
difficulties can be predicted.
1.2.3 FILLS (2002)
1.2.3.1 General
a.
Fills are used to raise the existing ground surface when required to achieve the desired level for roadbed
construction. They may serve to elevate the grade above existing or predicted water levels or snow depths;
to bury obstructions, undesirable topographic variations, and to achieve design grades. The two primary
components that need to be considered during fill design are the embankment and the natural foundation
that it is constructed on.
b.
Every railroad fill should be designed to satisfy the following requirements:
(1) To assure the stability of the embankment under its own weight and super imposed load.
(2) To assure stability of the combined embankment and foundation system.
(3) To economically tolerate the magnitude of anticipated settlement.
c.
These design requirements are satisfied by selecting suitable soil or rock to be used for construction,
controlling the placement of these materials as to location and compaction in the fill, and designing the
embankment to compensate for anticipated settlement. If the fill is to serve as an impoundment structure,
additional design considerations such as the permeability of the fill and its ability to withstand rapid draw
down of the water level, need to be taken into consideration.
d.
A balance factor should be computed when calculating the quantity of required borrow material to construct
an embankment fill. This balance factor is the ratio of the volume of soil from the borrow to the volume of
soil placed in the fill after compaction. No standard balance factor (shrinkage factor) should be assumed.
Fill materials are often compacted to a density different from their original density in the borrow. On large
projects it is advisable to find cut-to-fill ratios by field density. The balance factor should be increased to
compensate for soil that is lost in transport between the borrow and fill areas.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-22
AREMA Manual for Railway Engineering
Roadbed
1.2.3.2 Foundations of Fills
a.
The foundation for a fill is required to satisfy the same basic requirements of a continuous spread
foundation system. The foundation soil should have the strength to support the proposed embankment and
live loads with an adequate safety factor. In addition, the fill needs to be designed and constructed (i.e.,
compacted and placed within a range of moisture criteria) such that it can tolerate the projected degree of
settlement. It is occasionally necessary to remove and replace portions of weak or highly compressible
foundation elements or to improve their characteristics by using stabilization procedures or controlled
construction techniques. Controlled construction techniques could include one or combinations of the
following: 1. removal and reuse in compacted fill, 2. stage construction of the fill, 3. preloading and
surcharging or 4. installing subdrainage systems.
b.
Vegetation, topsoil and organic soils are normally removed to provide for the development of a good bond
between the fill and the subsoil. The removed materials may be stockpiled for future use as topdressing in
grassed areas.
c.
A fill underlain with “free-draining” sand or gravel will routinely have a factor of safety higher than those
for cohesive silty or clayey foundation materials. The performance of computer aided slope stability
analyses such as the “Modified Bishop”, “Bishop Simplified Method” or the “Janbu’s Simplified Method”
should be performed to determine the stability of both the embankment and foundation components of
proposed fills. A stability analysis that provides a safety factor of 1.0 implies that the driving forces that are
wanting to cause a failure are equal to the resisting force in the soil and that a failure is imminent.
Generally a factor of safety of 1.5 is considered adequate, although, lower safety factors may be considered
acceptable if the engineer performing the stability analysis has sufficient design data available for analysis.
Higher safety factors are required when limited test and field data are available for use in the performance
of the slope stability analysis.
d.
1
If the stability analysis indicates an adequate factor of safety for the foundation, the design will be based on
the internal stability of the embankment. When the foundation is too weak to provide adequate support one
or more of the following procedures could be adopted to achieve a stable fill:
(1) Total or partial removal of unsuitable foundation materials, displacement of these materials, and
replacement with compacted fill.
3
(2) Flattening of the slopes of the embankment section or the addition of berms at the toes of the
embankment.
(3) Installation of a foundation drainage system to reduce pore water pressures.
(4) Stage construction of the embankment.
4
(5) Densification of sandy foundation soils.
(6) Use of light embankment materials (fills).
(7) Mechanical reinforcement or underpinning systems.
(8) Preloading and surcharging the fill area to accelerate consolidation of clay or organic soils.
e.
Berms installed to improve weak foundation conditions should extend to sufficient distance beyond the
failure arc to provide an adequate factor of safety to the fill. Berms should also be checked for their own
stability.
f.
The magnitude of foundation material consolidation should be computed when embankments are built on
highly compressible ground. The magnitude of settlement within the embankment section may also need to
be taken into consideration when computing total settlement. The top width of the fill should be increased
to compensate for the computed settlement that will occur after completion of the embankment
construction. Foundation materials that consist of peat may be expected to significantly consolidate under
the weight of the fill.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-23
Roadway and Ballast
1.2.3.3 Soil Fills
1.2.3.3.1 General
a.
A soil embankment has three basic components: a center core, shoulders or shell, and a drainage system.
Homogeneous embankments use the same materials for the core and shoulders. Site conditions may not
require special drainage provisions other than side ditches. When the fill functions as an earth dam or
levee, the core is constructed of relatively impermeable material while the shell will generally be constructed
of a material that is more permeable than the core.
b.
Fill slopes should be designed based on the findings of slope stability analysis. The soil properties utilized in
the slope stability analysis should be determined by a geotechnical engineer using field investigation and
laboratory tests. Factors that will affect the factor of safety of a fill slope are the materials used for
construction, compaction of the fill material(s), stabilization berms, and the strength of the embankment
materials after compaction. Fills constructed of sandy (cohesionless) materials or of cohesive materials
should stand safely if constructed at slopes of 2(H):1(V), or flatter. Fills that have a sand core should be
capped with cohesive or other non-erosive materials to minimize erosion of the embankment slopes.
c.
It is important to study the effects that a new fill will have on the drainage of water. Effective drainage
away from the fill will routinely improve the stability of the proposed fill section. The probable settlement
of the fill should be considered when culverts are needed to transfer the flow of water from one side to the
other side of the fill. Sufficient camber should be included in the culvert installation to compensate for the
anticipated magnitude of settlement and to maintain positive flow through the culvert.
d.
The quality and ease of constructing soil fills varies widely. There are varying qualities of material available
for use when constructing an embankment. Routinely the materials that are available on the project are
used to construct fill for economic reasons.
e.
Soils that are used in the construction of fills often consist of a combination of fine grained (cohesive) and
coarse grained (cohesionless) materials. The cohesive fine grained materials consist of clays. Cohesionless
materials consist of fine grained silts; and coarse grained sands, gravels, cobbles and boulders.
f.
Cohesionless soils generally have a higher friction angle than cohesive soils, are best compacted using
vibratory equipment, are free draining, and have greater strength at higher densities. Moisture routinely
facilitates compaction. Relative density tests are the most appropriate means for defining the degree of
compaction for clean free-draining cohesionless materials.
g.
Cohesive (fine grained) soils generally consist of a combination of silts and clays. Some of the physical
properties of fine grained soils include:
(1) Soil moisture content influences compaction
(2) Greater degree of compaction increases the soil’s strength
(3) Saturation reduces the strength of the soil
(4) The friction angle and cohesion of the soil are the two parameters that describe the soils strength
(5) They are frost susceptible
(6) Compaction is best attained using sheepsfoot rollers and impact hammers
(7) The clay fraction of cohesive soils may exemplify swell characteristics
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-24
AREMA Manual for Railway Engineering
Roadbed
h. Fills that consist of cohesionless and cohesive soils have properties that are a combination of those that
occur for each of the two separate materials. In general, the level of compaction is influenced by the
composite soils moisture content. Non-free draining materials have moderate to low permeability. They
have the potential for creating high quality fills due to high cohesion and friction angle characteristics. This
fill material is more susceptible to frost action than purely cohesionless soils. Sheepsfoot and impact
equipment are the most appropriate means of achieving compaction. These materials exemplify low to
moderate swell potential depending on the clay fraction in the soil.
i.
The ability of various soil types to resist erosion on slopes is shown in Column 7 of Table 1-1-10. The
stability of soil types in rolled fills and their compaction characteristics are shown in Columns 10 and 11 of
the same Table. Methods of improving soils for use in fills are reviewed in Paragraph k below.
j.
The source of suitable soils is a primary factor in fill projects. Excavation, transportation and placement
costs govern the final choice. Fill may be obtained from adjacent cuts, borrow areas or commercial
suppliers.
k.
Improving the behavior of soil fills for any engineering purpose by methods which alter or control the
properties of the soil is generally termed soil stabilization. There are many procedures for creating more
desirable soil properties in soils, but each has limitations depending on the soil type. A stabilization method
should be suitable for the soil, have the required durability, provide the necessary performance economically
and be practical to the site. Table 1-1-9 presents some of the more common methods available for
improving the performance of fill materials.
1
Table 1-1-9. Improvement of Soils
Improvement
by
Densification
Methods
3
Procedure
Compaction
Rolling or vibrating of fill in layers with moisture
control.
Other Methods*
Vibration in depth (Vibrofloation – patented method)
Compaction piles, blasting, dynamic compaction,
compaction grouting, geo-piers.
Drainage
Gravity
Pumping
Consolidation*
Transpiration
Gravity removal of water using surface and subsurface
drains.
Mechanical removal of water.
Surcharge loading with drainage.
Planting or seeding with vegetation.
Modification
Blending*
Cement, lime, bitumen or calcium
chloride*
Adding select soil, mixing, compacting.
Adding to soil in small quantities, mixing with
moisture control, compacting, curing.
*Method requires specialist advice.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-25
4
Roadway and Ballast
1.2.3.3.2 Sidehill Fills
a.
The design and construction of a sidehill fill involves analyzing the stability of the natural slopes both uphill
and downhill from the embankment fill. The stability of these slopes and of the fill should be analyzed
separately and as a unit.
b.
Construction procedures should be provided to prevent the fill from sliding on the original slope. The
existing slope should be properly stripped of vegetation, stepped or notched into the hillside, scarified, and
compacted. The finished surface of the compacted fill should be allowed to remain slightly roughened to
facilitate bonding with subsequent lifts of fill. Drainage should be provided to intercept surface water
runoff on the uphill side of the fill and, thereby, prevent it from seeping along the fill-slope interface.
Erosion protection for the slopes may be necessary, as detailed in Article 1.4.5, Drainage and Erosion
Control (2007) below.
c.
The safety of fills constructed on sidehill slopes can be improved by increasing the size of the drainage ditch
on the uphill toe of slope and providing bonding benches and toe benches. The fill and its loads combine to
reduce the stability of the original slope. Care should be exercised to assure that excavations do not remove
material below the toe of the fill on the downhill side of the fill or that construction does not place a
surcharge on or above the uphill slope which will increase the moving forces.
1.2.3.4 Rock Fills
1.2.3.4.1 General
a.
Article 1.2.3.1 and Article 1.2.3.2 apply to rock fills as well as earthen cohesive and cohesionless soils. As
with earth fills, rock fills by economic necessity are composed of materials available from project cuts except
in unusual circumstances where the rock is of a nature that it will not support the loads placed upon it or
some other unacceptable condition exists.
b.
One such condition is the tendency of some rock fills to be subject to long term settlement due to the gradual
compaction of the embankment fill itself. Where long-term settlement cannot be tolerated, the use of select
borrow or a bridge or trestle may be required. Rock fills, however, are successfully used for railway
installations where settlement may be easily corrected by periodic track lifting. Many rock fills over 100
feet high have been successfully constructed and maintained. Geotechnical engineers who have knowledge
of rock fill construction should develop the construction details where very high fills appear economically
feasible.
1.2.3.4.2 Soft Rock Fills
a.
By definition herein, “soft rock” refers to rock which may be excavated by power machinery without
blasting or to rock which weathers rapidly upon exposure, even though blasting may have been required for
its initial removal.
b.
Soft rock may result in an impervious fill and therefore should be located within the fill at such locations
that will allow for proper drainage and maintain embankment stability. Soft rock fill materials are
sometimes treated as earth/soil materials when assigning strength characteristics and compaction
requirements. Slope design is best based on laboratory test results, with due regard given to possible
softening of the soft rock with aging and observation of performance of similar fills constructed in the past.
The suggested steepest slope for fills up to 30 feet high are 2(H):1(V) or flatter for impervious soft rock. A
geotechnical engineer should analyze and design fill sections constructed of soft rock.
1.2.3.4.3 Hard Rock Fills
a.
Hard rock requires blasting for removal and is sufficiently weather-resistant to retain its strength after long
exposure to elements. Fills containing only hard rock are usually resistant to slides and are otherwise stable
except that such fills often contain a high percentage of voids which cause long-term settlements.
Recommended slopes are 1.5(H):1(V) or flatter for fills up to 50 feet high, and 2(H):1(V) or flatter for higher
fills constructed of hard rock.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-26
AREMA Manual for Railway Engineering
Roadbed
b.
The percentage of voids and hence the settlement of a rock fill may be reduced by limiting the depth of each
layer placed during construction, mixing soft rock or soil with the hard rock, compacting the fill in place, or
any combination of these methods. Layers 24 to 30 inches deep are recommended with the maximum
individual rock size not exceeding the layer thickness. Heavy-duty, rubber-tired rollers (50 tons or heavier)
have been used to compact well-graded broken rock to 83 to 88% of its unit weight in the solid state.
1.2.3.4.4 Zoning of Rock
a.
When both hard and soft rock are available to construct a fill, it is recommended that each material be
located in such a position as to take advantage of and preserve its strength, reduce or eliminate slope
erosion, provide necessary drainage and avoid trapping of water within the fill.
b.
Figure 1-1-7 shows a cross-section of a fill where the softer, weaker and less pervious rock is located in the
core of the fill. The outer slope of the fill is determined by the slope needed for the weaker core material. By
enveloping the core with the hard rock, the resulting slopes are strengthened, drainage is provided and the
strength of the weaker rock materials is maintained by keeping its surface from the weather. Settlement is
also reduced because the softer core material may be compacted to a density more nearly to that which
existed in its natural state.
1
3
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-27
Roadway and Ballast
Figure 1-1-7. Zoning of Rock Fill Materials
c.
Other zoning arrangements may be made, such as protecting a soft-rock core with clay soil, placing hard and
soft materials in alternate layers, and mixing hard and soft materials to reduce settlement.
REFERENCES
(1) Duncan, C. Wyllie; Foundations On Rock; Chapman & Hall, London; 1992.
(2) American Society of Civil Engineers; Rock Foundations – Technical Engineering & Design Guides As
Adapted From The U.S. Army Corp of Engineers, No. 16; ASCE Press; 1996.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-28
AREMA Manual for Railway Engineering
(2)
(3)
Symbol
Soil Group
Field Identification
Gravels
(1)
GW
Well-graded GRAVELS and
well-graded GRAVELS with
SAND mixtures, trace to no
silt or clay
GP
Predominantly one size, or a
Poorly-graded GRAVELS
and poorly-graded GRAVEL range of sizes with some
with SAND mixtures, trace missing, no dry strength
to no silt or clay
GM
Sands
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
Table 1-1-10. Soil Groups, Their Characteristics and Uses
Wide range in grain sizes,
substantial amounts of all
intermediate sizes, no dry
strength
(4)
(5)
(6)
Value as
Frost
Drainage
Filter Layer
Heaving
(7)
Erosion on
Exposed
Slope
(8)
(9)
(10)
Stability in
Value as Pumping
Compacted
Subgrade
Action
Fills
(11)
(12)
Compaction
Characteristics
Typical Duty
Type Geotextile
Fabric Use
None to Excellent
very
slight
Fair
None*
Excellent
None
Very Good
Excellent; crawlertype tractor, rubbertired roller, steelwheeled roller
None required
None to Excellent
very
slight
Fair to poor None*
Excellent
None
Reasonably
good
Good; crawler-type
tractor, rubber-tired
roller, steel-wheeled
roller
None required
Very poor
None to
slight
Good
None
Reasonably
good
Good with close
moisture control;
rubber-tired roller,
sheepfoot roller
None required
SILTY GRAVEL and SILTY Fines with low or no plasticity, Slight to Fair to
GRAVEL with sand
slight to no dry strength
medium very poor
mixture
CLAYEY GRAVEL and
GC CLAYEY GRAVEL with
sand mixture
Plastic fines, medium to high
dry strength
Slight to Poor to
medium very poor
Not to be
used
None to
slight
Good
Slight
Fair
Excellent; rubberNone required
tired roller, sheepfoot
roller
Well-graded SAND and
well-graded SAND with
SW GRAVEL mixtures, trace to
no silt or clay
Wide range in grain sizes,
substantial amounts of all
intermediate sizes, no dry
strength
None to Excellent
very
slight
Excellent
Slight to
high with
decreasing
gravel
content
Excellent
None
Very good
Excellent; crawlertype tractor, rubbertired roller
None required
Predominantly one size, or a
Poorly graded SAND and
poorly graded SAND with
range of sizes with some
GRAVEL mixtures, trace to missing, no dry strength
no silt or clay
None to Excellent
very
slight
Fair to poor High
Good
None
Reasonably
good with
flat slopes
Good; crawler-type
tractor, rubber-tired
roller
None required
SILTY SAND and SILTY
SAND with GRAVEL
mixtures
Fines of low to no plasticity,
slight to no dry strength
Slight to Fair to
high
very poor
Very poor
High
Poor
None to
slight
Fair
Good with close
moisture control;
rubber-tired roller,
sheepfoot roller
Slight regular
Plastic fines, medium to high
dry strength
Slight to Very poor
high
Not to be
used
Slight
Poor
Slight
Fair
Excellent; rubberSlight regular
tired roller, sheepfoot
roller
SP
SM
CLAYEY SAND and
SC CLAYEY SAND with
GRAVEL mixture
Roadbed
1-1-29
Table 1-1-10. Soil Groups, Their Characteristics and Uses (Continued)
(3)
Symbol
Soil Group
Field Identification
Of High
Plasticity
ORGANIC
AREMA Manual for Railway Engineering
© 2010, American Railway Engineering and Maintenance-of-Way Association
Silts and Clays
Of Low
Plasticity
(2)
(4)
(5)
(6)
Frost
Value as
Drainage
Heaving
Filter Layer
(7)
Erosion on
Exposed
Slope
(8)
(9)
(10)
Stability in
Value as Pumping
Compacted
Subgrade
Action
Fills
(11)
(12)
Compaction
Characteristics
Typical Duty
Type Geotextile
Fabric Use
SILT or SILT with SAND or Fine grained, slight to no dry
GRAVEL; SANDY SILT or strength
SANDY SILT with
ML
GRAVEL; GAVELLY SILT
or GRAVELLY SILT with
SAND mixture
Medium Fair to
to very very poor
high
Not to be
used
Very high
Poor
Slight to Poor
bad
Poor to good with
close control of
moisture; rubbertired roller;
sheepfoot roller
Lean CLAY or Lean CLAY Medium to high dry strength
with SAND or GRAVEL;
SANDY LEAN CLAY or
SANDY Lean CLAY with
CL
GRAVEL; GRAVELLY
Leam CLAY or GRAVELLY
Lean CLAY with SAND
mixtures
Medium Very poor
to high
Not to be
used
None to
slight
Bad
Bad
Fair to good; rubber- Yes heavy
tired roller, sheepfoot
roller
Elastic SILT or elastic SILT Slight to medium dry strength Medium Poor to
to very very poor
with SAND or GRAVEL;
high
SANDY elastic SILT or
SANDY elastic SILT with
MH
GRAVEL; GRAVELLY
elastic SILT or GRAVELLY
elastic SILT with SAND
mixtures
Not to be
used
None to
slight
Bad
Very bad Poor
Poor to very poor;
sheepfoot roller
Yes heavy
Fat CLAY or fat CLAY with Sticky when wet, high dry
SAND or GRAVEL; SANDY strength
fat CLAY or SANDY fat
CH CLAY with GRAVEL;
GRAVELLY fat CLAY or
GRAVELLY fat CLAY with
SAND mixtures
Medium Very poor
Not to be
used
None
Bad
Very bad Fair with
flat slopes
Fair to poor;
sheepfoot roller
Yes extra heavy
Organic SILT or CLAY and High smell, dark colour,
with SAND or GRAVEL;
mottled appearance, slight to
SANDY or GRAVELLY
high dry strength
OH
organic SILT or CLAY with
GRAVEL or SAND
respectively
Medium Poor to
to high very poor
Not to be
used
Variable
Bad
Very bad Not to be
used
Poor to very poor
Yes extra heavy
Slight to Poor
high
Not to be
used
Not
applicable
Remove
completely
Very bad Not to be
used
Compaction not
possible
Yes extra heavy
PT
PEAT
Dark colour, spongy feel and
fibrous texture
Reasonable
Adapted from ASTM Method D 2487T
NOTES:
Column 2: Soil types in capitals and underlined make up more than 50% of sample. Other soil types in capitals make up more than 5%.
Column 4: Tendency of soil to frost heave.
Column 5: Ability of soil to drain water by gravity. Drainage ability decreases with decreasing average grain size.
Column 6: Value of soil as filter backfill around subdrain pipes to prevent clogging with fines, and as filter layer to prevent migration of fines from below.
Column 7: Ability of natural soil to resist erosion on an exposed slope. Soils marked * may be used to protect eroding slopes of other materials.
Column 8: Value as stable subgrade for roadbed, when protected by suitable ballast and sub-ballast material. Good soils may be used to protect poorer soils in subgrade.
Yes regular
Roadway and Ballast
1-1-30
(1)
Table 1-1-10. Soil Groups, Their Characteristics and Uses (Continued)
(2)
(3)
Symbol
Soil Group
Field Identification
(4)
(5)
(6)
Frost
Value as
Drainage
Heaving
Filter Layer
(7)
Erosion on
Exposed
Slope
(8)
(9)
(10)
Stability in
Value as Pumping
Compacted
Subgrade
Action
Fills
(11)
(12)
Compaction
Characteristics
Typical Duty
Type Geotextile
Fabric Use
Column 9: Tendency of soil to pump up and foul ballast under traffic.
Column 10: Stability of soil against bulging and subsidence when used in a rolled fill. Cross check with Column (7) to forecast tendency to erode.
Column 11: Equipment listed will usually produce the required densities with a reasonable number of passes when moisture content and thickness of lift are properly controlled.
Column 12: Typical type Geotextile Fabric. Use is dependent upon existing or proposed subgrade design. Fabric will not improve soil classification. If additional strength is required, use enough stabilized
material, granular base material, sub-ballast and ballast to properly span the weak subgrade soil.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
(1)
Roadbed
1-1-31
Roadway and Ballast
1.2.4 DRAINAGE (2003)
1.2.4.1 General
a.
This section deals with the surface and subsurface drainage of the roadway as distinguished from drainage
of the ground surface by natural waterways. The latter subject is dealt with in Part 3 Natural Waterways,
and Part 4 Culverts.
b.
Since water is the principal influence on soil stability in roadbed, subgrade and slopes, control of surface and
subsurface water is the most important factor in roadway design and maintenance.
1.2.4.2 Surface Drainage
a.
Surface water from the roadway area, and sometimes surrounding topography, is usually handled by a
system of ditches parallel to the roadbed with offtake ditches where necessary. The roadbed cross section,
slopes of cuts and fills, ditches, catch basins, and culverts should all form a balanced system to dispose of the
water without accumulation or excessive saturation which would produce damaging effects.
b.
The design capacity of any part of the system can be calculated if the quantity of water to be carried, the
distance and grade to outfall, and the infiltration factor of the soil are known. Ditches should be deep
enough and sized for handling the design runoff anticipated while allowing the subgrade to drain.
Trackside ditches should be sized for the anticipated runoff and the flow velocity calculated using the
Manning equation.
c.
The ditch grade may be governed by the track grade, particularly in long cuts or offtake drainage points.
However, more often than not, ditch grades will be governed by existing drainage patterns and points of
discharge. When the ditch is constructed in earth materials, the minimum recommended grade should not
be less than 0.25% to minimize sedimentation. However, exceptions to this may be dictated by local
topography such as in low-lying or flat terrain. Likewise, to prevent erosion, the maximum unlined ditch
grade and/or ditch configuration should be such that it will produce a velocity less than or equal to the
limiting velocity shown in Table 1-1-11. Erosion may also be prevented or reduced by paving, riprapping,
sodding, or constructing check dams depending on velocity, type of soil, and depth of flow (see Part 3
Natural Waterways). Linings for ditches are typically classified as either rigid or flexible. Asphaltic
concrete and Portland cement concrete linings are examples of rigid linings. Riprap, sod, and grass linings
are examples of flexible linings. Rigid linings are better at limiting erosion and they often permit higher
water velocities since they are smoother than flexible linings.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-32
AREMA Manual for Railway Engineering
Roadbed
Table 1-1-11. Guidelines for Limiting Velocities to Prevent Erosion
Material
d.
e.
Velocity
(Ft per Sec)
Sand
Up to 2
Loam
2-3
Grass
2-3
Clay
3-5
Clay and gravel
4-5
Good sod, coarse gravel, cobbles, soft shale
4-6
Characteristics of flow and their effects on erosion need to be considered. Generally speaking, flow in
trackside ditches may be classified as steady uniform flow provided the ditch section is relatively constant.
Open channel flow is uniform when the depth of flow is the same at every section of the channel, i.e. the
surface of the water is parallel to the channel. Flow in trackside ditches can be further classified as either
subcritical or supercritical. Flow down gentle slopes will most likely be subcritical. Flow down steep slopes
would most likely be supercritical. That is to say, when the depth of water is greater than the critical depth,
it is subcritical flow, and when the depth is less than critical, it is supercritical flow. Critical flow or flow
near critical depth tends to be unstable and exhibits turbulence and water surface undulations. Therefore,
the slope of the channel bed which would maintain critical flow, should be avoided. Critical flow is that state
of flow at which the specific energy is at a minimum for a given discharge. A hydraulic jump occurs when a
transition is made from subcritical to supercritical flow. Supercritical flow should be avoided in the
trackside ditch design because the higher velocity can cause scour/erosion at the downstream outlet. To
limit the effects of erosion at the outlet, a form of energy dissipation may be applied in the channel. Types
of energy dissipators include drop structures, roughness elements such as blocks and sills, ditch checks, etc.
These decrease the chance of a hydraulic jump occurring while also decreasing the chance of erosion/scour.
Ditches are commonly trapezoidal or V-shaped in section. In most cases, from a constructability standpoint,
it is not economical to vary the size/shape of the ditch. Although each ditch should be designed considering
soil type, hydraulics and method of construction, the minimum recommended depth is 2 feet below finished
subgrade at the shoulder of the roadbed. The minimum recommended depth is expected to provide
freeboard and prevent saturation and infiltration of stormwater into the sub-ballast and ballast section.
Additionally, the minimum recommended bottom width for trapezoidal ditches in earth materials is 3 feet
realizing that wider ditches may be easier to construct if right of way is available. Side ditches should be
located so that the stability of adjacent cuts and fills will be maintained. Generally the top surface of a
berm, if constructed or required between the toe of a fill and the ditch, should be sloped toward the ditch for
good drainage.
f.
Wide ditches are desirable at the toe of slopes in cuts where sloughed material tends to accumulate. Wide
ditches, in addition to providing storage space, also provide working space for equipment and subsequently
allow for periodic cleaning of debris and sloughed material.
g.
Ditches at the top of cut slopes to intercept runoff water from the uphill slope are often useful in reducing
slope erosion, sloughing, or in preventing the deterioration of a rock slope due to ice formation in cracks of
the rock. Intercepting ditches also reduce the quantity of water to be handled by trackside ditches. The
same care should be taken in designing intercepting ditches as side ditches so that they do not create serious
erosion problems. Seepage water occurring on the face of a slope may be intercepted and conducted away on
benches. Benches used for drainage should be sloped back from the face and thence laterally, and should be
lined if necessary to prevent infiltration.
h. In low-lying or flat terrain, it may be necessary to dig offtake or adjacent ditches away from the roadway for
a considerable distance to provide sufficient difference in elevation to produce drainage. In such locations,
sedimentation may occur requiring periodic cleaning of ditches. An alternate would be to provide
catchment areas outside the embankment area for accumulation and evaporation of runoff if right of way is
available.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-33
1
3
4
Roadway and Ballast
REFERENCES
(1) H.W. King, E.F. Brater, J.W. Lindell and C.Y. Wei, Handbook of Hydraulics, McGraw-Hill, New York 7th
Edition, 1996.
(2) Ven Te Chow, Ph.D., Open Channel Hydraulics, McGraw-Hill Book Company, New York, 1959, Reissued
1988.
(3) F.S. Merritt, M.K. Loftin and J.T. Ricketts, Standard Handbook for Civil Engineers, McGraw-Hill, New
York, 4th Edition, 1996.
1.2.4.3 Subsurface Drainage
1.2.4.3.1 Importance
a.
Only a portion of rainwater is handled by natural and man-made watercourses. The remaining water
infiltrates the soil and becomes either ground water or capillary water. Where ground water is high,
subsurface drainage may be needed to draw the water table down so that softening of the subgrade soils,
sloughing, or instability of slopes will not occur. Capillary water cannot be removed by drainage but can
sometimes be controlled by lowering the water table. Lowering the water table will assist in reducing the
amount of heaving track caused by frost, reduce the pumping and infiltration of soil into the sub-ballast and
ballast sections, and reduce the potential for developing ballast pockets.
b.
The suitability of various soil types to gravity drainage is given in Column 5 of Table 1-1-10.
1.2.4.3.2 Definition and Function of Subdrains
a.
A subdrain is any covered/sealed drain below the ground surface receiving water along its length through
perforations, porous walls, or joints placed in a trench backfilled with filter material.
b.
A subdrain may consist of a trench filled with clean, granular or crushed rock material, whereby water is
intended to pass through the interstices of the material instead of a pipe, typically referred to as a French
drain. Subdrains of this type frequently plug with fines from the adjacent ground unless protected by
adequate filters such as a non-woven geotextile fabric. When utilizing this technique extreme care should
be taken to provide for the proper design and installation. When installed properly, French drains are very
effective in permitting subgrades to drain and thereby further stabilizing them.
c.
A subdrain may consist of a trench with perforated pipe and geotextile fabric filled with clean, granular or
crushed rock material whereby water is intended to pass through the interstices of the rock material
through the perforations in the pipe and out through the pipe. The perforated pipe should be laid such that
the perforations are pointing down to the bottom of the trench.
d.
Subdrains may serve as cross drains or side drains. Cross drains are laid under the roadbed or other areas
to prevent water from gathering and provide a path for water to drain out of the substructure such as the
sub-ballast and subgrade. They are placed below the level of water accumulation and connected to a side
drain. Cross drains typically flow into a side drain unless they are directly connected to a roadside ditch or
the side of an embankment for discharge. Side drains are built to collect water from cross drains and to
intercept water flowing toward the roadbed, or collect water out of the substructure. An attempt should be
made to place side drains at the lowest part of seepage zones so as to collect as much of the flow of ground
water as possible.
1.2.4.3.3 Design
a.
Subdrainage pipe is available in perforated corrugated metal, rigid plastic, bituminized fiber, and perforated
or porous concrete. Part 4 Culverts, gives specifications for metal and concrete piping and methods of
installation.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-34
AREMA Manual for Railway Engineering
Roadbed
b.
Subdrainage pipe is available in diameters ranging from 2 to 24 inches. Where periodic cleaning of
subdrains is required, 6 inch pipe or larger is recommended. For pipe laid at a proper gradient and
surrounded with a proper filter material such cleaning should not be required. However, provisions for
clean out should be made as discussed in Paragragh d. below.
c.
The design of subdrainage installations is made from knowledge of the depth, flow quantity, direction of
flow, and seasonal fluctuations of the ground water table. Such information is best obtained by observing
the soil deposits and water levels in test pits during the wet season. The location, depth, and size of pipe,
French drains, and filter material are chosen accordingly. Subsurface drainage should be considered an
integral part of the entire drainage system and not just an isolated, separate component.
d.
In normal subdrainage, approximately 300 feet of 6 inch intercepting drain may be used before a change to
a larger size is necessary. Manholes/clean outs are usually installed at the same intervals.
e.
A slope to ensure a velocity of 2 feet per second should be used for pipe. It is important to locate the outlet
where it can be maintained free from any manner of clogging or backwater.
REFERENCES
(1) American Iron and Steel Institute, Handbook of Steel Drainage and Highway Construction Products,
Fifth Edition, 1994.
(2) Concrete Pipe Design Manual, American Concrete Pipe Association, Irving, Texas.
1
(3) Uni-Bell Handbook of PVC Pipe, Third Edition, 1991, Dallas, Texas.
1.2.4.3.4 Uses
Typical uses of subdrainage installations can be illustrated by the following examples. More details are found in
the references.
• Sidehill Seepage Under Track. Figure 1-1-8 shows a condition where a seepage zone tends to cause
subgrade softening. After investigation by auger borings or test pits, the seepage is intercepted before it
enters the roadbed area by a side drain, placed at a depth so that the affect of ground water is no longer
significant.
• Wet Cuts. Figure 1-1-9 shows a condition where track maintenance is required due to the saturated
condition of the subgrade. In addition to a substantial thickness of sub-ballast, intercepting subdrains
installed as shown on either side of track are necessary to stabilize the subgrade.
• Cut to Fill Transitions. Figure 1-1-10 and Figure 1-1-11 show applications of subdrains at cut to fill
transitions. At such locations, the flow of ground water from a cut is often interrupted by cross-sloping
impervious layers, causing wet conditions and soft subgrades. A cross drain placed at this transition may
intercept the seepage, and the local use of a sub-ballast thickness greater than normal will ensure a stable
subgrade.
• Yard and Station Areas. Unless the subgrade soil is free-draining, a system of subdrainage is advisable in
yard and station areas, usually combined with a storm drainage system. Longitudinal subdrains between
pairs of tracks with cross drains at 200- to 300-foot intervals will normally be satisfactory. Depth and
spacing will depend on soil and ground water conditions.
• Other Uses. Subdrains have also proven of benefit at road crossings, rail crossings, and behind bridge
abutments.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-35
3
4
Roadway and Ballast
Figure 1-1-8. Interception of Sidehill Seepage by Subdrainage
Figure 1-1-9. Lowering of Ground Water In a Wet Cut
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-36
AREMA Manual for Railway Engineering
Roadbed
Figure 1-1-10. Lowering of Ground Water in Cut to Fill Transition (Longitudinal)
1
3
4
Figure 1-1-11. Lowering of Ground Water in Cut to Fill Transition (Sidehill)
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-37
Roadway and Ballast
SECTION 1.3 CONSTRUCTION
1.3.1 GENERAL (2005)
a.
Construction should only occur after an engineering investigation and design have taken place and the
results of these activities have been packaged in the contract documents. These documents are prepared so
that the railroad or more typically, a Contractor can accomplish the project scope. Associated engineering
activities should be appropriate to the size and scope of the planned project. Section 1.3 consists of general
recommendations for new roadbed construction to include the initial survey, preparation of plans, and the
preparation of specifications for such items as clearing and grubbing, excavation and grading, erosion and
sediment control, placement of sub-ballast material, and final surface erosion control.
b.
An important distinction should be made between completely new railroad roadways designed and
constructed separate from existing operating tracks and facilities, and railroad roadbeds constructed
immediately adjacent to or beneath an operating railroad. The design approach and construction
methodology for railroad roadbeds may have significant differences for new roadbeds on a new alignment
versus roadbeds adjacent or beneath existing operating railroad. In instances where work is to be
performed in the vicinity of active railroad operations special safety considerations are warranted. A
flagman or other appropriate method should be used to protect equipment and personnel working within
the fouling limit of the track or as authorized by the operating railroad of the active track. All employees
working in this area must receive Roadway Worker Protection as specified by the operating railroad and
FRA requirements.
c.
It should be recognized that in rare instances projects arise that do not allow for a traditional engineering
analysis to be followed by the preparation of design documents. In these cases, the railroad or Owner should
employ technical professionals that can be involved in the expedited design process as well as throughout
the construction process to address site-specific issues, which would affect the performance of the new
roadbed.
1.3.2 CONTRACT DOCUMENTS (2005)
The preparation of Contract Documents is typically the deliverable product of the Design process. Contract
documents should include, but are not limited to: drawings/plans, technical specifications, the results of specialized
testing, the Owner’s contractual terms and conditions, and other pertinent project information. The owning
railroad or rail client usually has established guidelines as to the type and order of precedence of the specified
contents for the Contract Documents.
Although the Contract Documents should fully define the proposed project, it is advisable that all parties be
required to visit the site, attend pre-bid meetings when held, and become familiar with the project site conditions
prior to submitting proposals to perform the work. The purpose for these site inspections is to afford all parties the
opportunity to view and assess site conditions that might have an impact on construction. Examples of these
conditions may include physical site constraints, access limitations, obstructions, the location and number of
utilities, material disposal requirements, etc.
In some instances, the Railroad may have its own detailed set of standard Contract Documents, in which case the
site specific provisions need to be included. In other cases it may be more appropriate to use provisions from
applicable local or regional standard specifications, such as State Departments of Transportation, or County Public
Works Departments.
Contract Documents are typically made up of a number of sections. Sections that are most often included are:
a.
Contract Drawings: The drawings are the primary means of showing the known existing conditions and the
extent and magnitude of the proposed project. They provide a graphical representation of the work to be
performed and generally include plans and profiles, cross-sections, construction details, and may include
environmental and/or geotechnical information as appropriate.
b.
Technical Specifications: Written text that identifies and describes the scope of work, required submittals,
quality control procedures, products/materials, performance criteria, execution of work, and outlines
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-38
AREMA Manual for Railway Engineering
Roadbed
provisions for measurement and payment. Technical specifications may include such items as Demolition,
Site Preparation, Earthwork, Dewatering, Slope Protection, Drainage Systems, Site Utilities, Paving, and
Seeding and Mulching.
c.
Contract Terms and Conditions: This text defines the contractual obligations of all parties. Included in this
section are such things as safety requirements, insurance requirements, bonding, project schedule, track
occupancy issues, coordination with railroad forces, and project payments. Contract Terms and Conditions
are generally specific to the project and the Owner’s legal requirements, and will not be discussed in further
detail in this section.
d.
Other pertinent information usually contained in the contract documents may include such things as
geotechnical reports, environmental reports, drainage reports, utility agreements, and copies of permits
obtained by Owner and/or requirements for permits to be obtained by the Contractor.
1.3.2.1 Plans
Project plans typically include, but are not limited to, the following elements:
a.
Detailed plan and profile drawings show the project location, identify any affected real estate, and show
significant features of the area under consideration. Profiles should show existing ground elevations and the
elevations and grades of new construction within the limits of the project. Also shown in plan are such
things as highway crossings, existing and new track, existing and new drainage structures, pipelines and
utilities, location and water level of bodies of water and streams along the right-of-way, vegetation location
and type, and other information of use to the Engineer in estimating and planning the work and to the
Contractor in understanding and bidding the work.
b.
Soil and rock conditions may be shown. The presence of rock or soil strata may be shown on the profile
sheets but are more commonly represented by boring logs given in a geotechnical section of the project
drawings. This geotechnical information should be copied or reproduced in it’s entirety from the report of
the Geotechnical Engineer. It should be noted that subsurface information shown on the profile between
test pits or boreholes has been interpolated and may not conform to actual field conditions. It should be
made clear that this information is provided for information only and the Contractor is responsible for
interpretation of the information provided.
c.
Cross sections are typically cut at right angles to the centerline of construction. Typical cross sections for
cuts and fills should be provided for the length of the project at some specified interval, which provides
representation of the work to be performed and amount of materials to be excavated or filled. Cross sections
should show the existing ground surface and the design cuts and fills required. Fill sections should show the
type and thickness of fill materials to be placed. Drainage should be shown for both cut and fill sections.
Culvert details should be shown as well as details of berms or benches, slope keying, slope drainage and
blanketing, erosion protection, and any stabilization measures known to be required to produce a
satisfactory design.
1.3.2.2 Technical Specifications
The following section provides guideline recommendations for the major areas of work for roadbed related
construction activities. These specifications are not intended to be all-inclusive for a particular project, but serve
rather as a starting point for the development of project specific technical requirements.
1.3.2.3 General Conditions and Construction Engineering Control
It is recommended that the projects technical specifications include a section specifically covering the general
requirements for performance of work, and the means by which construction engineering and monitoring will be
performed.
Such a section clearly defines the responsibilities of both the Owner and Contractor regarding all aspects of project
engineering, administration, and construction management. Clear definition of the requirements and the
assignment of cost for each item are critical to project success.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-39
1
3
4
Roadway and Ballast
1.3.2.3.1 General Conditions
Items which should be considered for inclusion in "General Conditions" include:
• Safety of employees, public and railroad operations, including; Federal Railway Administration’s Roadway
Worker Protection program, Personal Protective Equipment requirements, and a clearly defined policy on
drug and alcohol possession or use by project personnel.
• Project specific regulations regarding allowable work hours, track curfews, and/or other railway imposed
limitations on construction.
• Project specific environmental restrictions, such as waste disposal, construction noise, airborne
particulate release, lighting, and vibration.
• Contractor’s responsibility for compliance with project specific environmental permits.
• Contractor’s responsibility to contact the applicable "Call Before You Dig" agency, and to comply with all
notification and permit requirements.
• Security of construction site including labor, material and equipment.
• Field Offices, including all required utility installations, necessary office equipment, and administrative
staffing requirements.
• Requirements for acceptance/unloading of railroad furnished material.
• Responsibility for preparing and updating Project schedule.
• Requirements for daily reporting and documentation.
• Inspection procedures.
• Provisions for ingress, egress and other use of work site or areas adjacent to work site.
Performance of General Condition items are normally considered incidental to the project and are not paid for
separately.
1.3.2.3.2 Surveying
The initial survey work, during the design phase, should establish horizontal and vertical control points for the
project. These control points should be preserved until construction is completed. Disturbance of survey points by
construction activities may result in the need to re-establish those points. Responsibility for this work should be
clearly defined in the contract documents. In addition to establishing the control points for the project, the
following additional survey work may be needed during construction.
a.
Establishment of Project Boundaries: Locate all surviving bench marks, and alignment reference and
stakes from the design survey activities as noted in design plans. These should include approximate rightof-way lines, temporary or permanent bench marks previously established, or facilities (utilities, drainage
structures, wells, etc.) which require special protection.
b.
Utility Locating: The location of existing utilities should be marked using color codes consistent with
APWA or NULCA standards.
c.
Construction Staking: Establish centerline staking at intervals appropriate to the project. Specific staking
stations would include all bridges, drainage structures, grade crossings, and utility crossings. Construction
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-40
AREMA Manual for Railway Engineering
Roadbed
stakes are also set to indicate cut and fill heights and the appropriate cut or fill slopes as required to
establish the desired cross section. It is often necessary to reestablish the construction stakes at various
times throughout the construction process.
d.
Permanent Instrumentation Benchmarks: In some cases, it is necessary to develop benchmarks for use in
long term monitoring of a construction project. In these cases, the specific requirements for establishment
of the benchmarks should be noted in the construction documents.
e.
As-built Surveys: At the conclusion of construction, a final as-built survey should be performed, and the
project documents should be updated to indicate any changes from the original design. These documents
become valuable in establishing maintenance practices and in design of future adjacent projects.
1.3.2.3.3 Construction Monitoring
Construction Monitoring involves the establishment of processes and procedures for the quality control and
quality assurance on the project. The individual technical specifications should establish testing requirements for
each type of work.
a.
Quality Control: This is the regular testing of materials to verify that the requirements established in the
contract documents have been achieved.
b.
Quality Assurance: This is the occasional document review and supplemental testing procedures,
performed for the purpose of ensuring that the established quality control process is being followed and is
effective.
The construction documents should clearly define the responsibility and process to be followed for both quality
control and quality assurance. These documents should also define how these activities are to be paid for, as well
as responsibility for any remedial activities which are identified as a result of the quality control or quality
assurance activities.
Each technical specification should identify the quality parameters the Contractor is expected to meet and the
specific test which should be used to determine when acceptable quality has been achieved. An example of a
quality control process is the performance of moisture content and density tests during fill placement. In addition
to portable test equipment, more permanent equipment such as standpipes, settlement gauges, and other
apparatus may need to be installed to measure and observe fill performance. The Contractor should be required to
facilitate such work and should avoid damaging such apparatus. Delays to his operations resulting from field tests
should not be cause for claims.
1.3.2.4 Environmental Control
1
3
4
Environmental Controls are procedures and devices which are utilized to ensure that construction activity
complies with applicable environmental laws and permitting requirements.
Most construction activities and projects will require permits from Federal, State, Provincial and/or local agencies.
Examples of these permits may include but are not limited to; Federal and or State Environmental Protection
Agency, Wetland and Work in Headwaters of the US Permit (USACOE 404), National Pollution Discharge
Elimination System (NPDES), Cultural Resources Affiliated Permits, Historical Preservation Associated Permits,
Environmental Impact / Assessment Affiliated Permits, State Department of Natural Resources, Threatened and
Endangered Species, and Federal Emergency Management Agency (FEMA) permits for work in floodways and
floodplains.
Certain projects may require review by the environmental analysis sections of the United States Surface
Transportation Board or Transport Canada.
The legal importance and potential impact to project cost and schedule of environmental permitting and
environmental control installation and maintenance should not be ignored.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-41
Roadway and Ballast
1.3.2.4.1 General
The Contractor should comply with all environmental control and discharge requirements set forth by applicable
regulatory agencies. Proper application and implementation of Permit requirements is necessary. Typically the
Owner, or its designated agent, must make application for necessary environmental permits. However, in some
instances the Contractor may be required to obtain specific permits that are directly related to his operations. The
United States Environmental Protection Agency (EPA) sponsors a web site with sample forms from the application
process. The site is http://www.epa.gov/owm/swhb.htm.
a.
Erosion and Sediment Control measures to obtain or be covered by a Federal 401 Water Quality Permit
should be prepared in accordance with the NPDES (National Pollution Discharge Elimination System)
requirements. This includes the preparation of a SWPPP (Storm Water Pollution Prevention Plan).
Typically this must be performed prior to a Contractor starting any work on the site that may disturb soil or
vegetation.
b.
Some railroad facilities are covered by blanket permits specifically for the maintenance of facilities on
existing railroad right-of-way.
1.3.2.4.2 Procedures
Erosion control devices should be placed in accordance with approved permits prior to beginning clearing and
grubbing, or any land disturbance activity. To perform as intended and ensure compliance with permits, devices
must be properly maintained throughout the construction process.
1.3.2.4.3 Measurement and Payment
a.
Typically the design and permitting costs associated with Environmental Control are the responsibility of
the Owner and a component of the Design Process. For some specific Environmental Control permits, the
Contractor rather than the Owner may be required to apply for, obtain, and pay for, a permit. In these cases
a separate pay item for this specific purpose is suggested.
b.
Environmental Control measures are typically measured and paid for by units of control devices installed,
or paid for by lump sum. The unit or lump sum prices submitted in the proposal typically include the entire
cost of furnishing all equipment, tools, materials, and labor for clearing and grubbing and disposal of
materials for the areas shown on the plans.
c.
It is important to consider and assign responsibility for the cost of Environmental Control maintenance
and/or replacement for the duration of the project. On highly complex projects, or projects of significant
anticipated duration, additional measurement and payment items may be warranted to adequately protect
the Owner and Contractor.
1.3.2.5 Clearing & Grubbing
1.3.2.5.1 General
a.
Clearing and grubbing should include the removal of items such as trees, brush, stumps, roots, all ground
vegetation, unsuitable materials, embedded logs, debris, structures, foundations, etc.
b.
All debris resulting from the clearing and grubbing operations should be disposed of by the Contractor, in
conformance with all applicable governmental regulations.
c.
It should be noted that timber located within the clearing limits might have value. Accordingly, contract
documents should clearly define ownership and disposition of timber.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-42
AREMA Manual for Railway Engineering
Roadbed
1.3.2.5.2 Procedures
a.
The Contractor should identify and protect existing utilities for the duration of the construction project.
The Contractor should identify and protect abandoned utilities, wells, or conduits not previously identified
until they may be properly retired.
b.
The Contractor should identify and protect established project survey control including, but not limited to,
permanent and temporary benchmark monuments and property corner pins.
c.
Clearing and grubbing should be performed using methods that are environmentally responsible and not
wasteful of earth materials required for construction purposes.
d.
All clearing, grubbing, and waste disposal should be done far enough in advance of other construction
operations so as to not cause delay.
e.
Trees and other growth outside the limits specified for clearing and grubbing should be preserved and
protected from damage during construction operations.
f.
During clearing and grubbing operations the various materials should be segregated by material type to
facilitate disposal or reuse. Typical categories would include wood, rock and masonry, steel, unsuitable
material, general debris, and useable soils. Special care must be given to control and properly dispose of any
hazardous waste encountered during the performance of these operations.
1.3.2.5.3 Measurement and Payment
a.
Clearing and Grubbing is typically measured and paid for by units of one acre or fraction thereof, actually
cleared and grubbed, or paid for by lump sum. The unit or lump sum prices submitted in the proposal
typically include the entire cost of furnishing all equipment, tools, materials, and labor for clearing and
grubbing and disposal of materials for the areas shown on the plans.
b.
For project sites where special or hazardous waste materials are likely to be generated during the clearing
and grubbing operation, additional measurement and payment items may be warranted. For example a
separate unit price for disposal by the ton or cubic yard may be used.
1
3
1.3.2.6 Grading
Grading includes all earthwork operations performed as part of the construction of the railroad roadway section
including the placement of granular sub-ballast materials. Work items typically include stripping, excavation,
subexcavation, excavation for drainage, and placement of embankment and sub-ballast. These are specifically
addressed in the following sections.
1.3.2.6.1 Stripping
1.3.2.6.1.1 General
Stripping is the process of removing surface layers of vegetation, organic material, top soil, or any other materials
unsuitable for use in the subgrade or foundation. If such materials can be utilized elsewhere on the project (such
as for final top dressing of slopes) or are desirable for sale to outside parties, they may be segregated from other
excavated materials and stockpiled.
1.3.2.6.1.2 Procedure
Stripping should be performed in accordance with the project plans or as directed by the Engineer. Typically
stripping should not take place until baseline excavation surveys have been performed.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-43
4
Roadway and Ballast
Depth of stripping should be closely monitored to ensure that the removal depth is sufficient to address design
concerns and/or variations in field conditions.
1.3.2.6.1.3 Measurement & Payment
Stripping is typically measured and paid for using an in-place cubic yard basis. If stripping is a minor component
of another excavation activity (such as major rock excavation) it may be considered incidental.
1.3.2.6.2 Excavation
1.3.2.6.2.1 General
Excavation is the process of removing material from a work site so that the designed Cut Section and subgrade
elevation are obtained. Materials to be removed are typically identified as either "Common Material (Soil)" or
"Rock". In some locations "Common Material" is referred to as "Unclassified Material".
1.3.2.6.2.2 Procedures
Excavation should be performed in accordance with the project plans or as directed by the Engineer.
Before any excavation work is performed the appropriate "Call Before You Dig Agency" should be contacted.
All excavation areas should be completed as far as is practical before borrow materials are obtained from outside
sources. Weather may prevent total utilization of material from excavation areas prior to use of borrow. Borrow
materials could be allowed ahead of completion of excavation only if it can be shown that all of the material from
planned excavation will subsequently be utilized for embankment. Total utilization of excavation materials is
important if the Contractor’s price for supplying borrow material is higher than his price for excavated material.
The Contractor should maintain all working surfaces in cuts and borrow areas in a well-drained condition at all
times. Surfaces should be shaped and rolled to facilitate positive drainage and minimize absorption of water.
Properly drained work areas typically allow construction to resume more quickly with less waste following rainfall
events.
All ditches should be of the adequate length, cross-sectional area and slope to accommodate anticipated flow per
the project plans, or as directed by the Engineer. All ditches should be graded to carry off water to the nearest
natural watercourse with a minimum change to established drainage patterns. Waste materials or other stockpiled
materials should be properly protected to avoid fouling of the channel.
Care should be taken to ensure that cut slopes and subgrade sections are not undercut when excavating ditches.
Ditches should be formed timely during the course of construction to promote positive drainage of the site and
facilitate other construction activities.
The Contractor should maintain haulage route surfaces to avoid rutting and water ponding. Ruts or depressions
that are allowed to remain on the surface of the finished subgrade will cause water pockets and subgrade
instability after train operations begin.
The Contractor should be prepared to supply and apply water or other means of reducing dust at the excavation
point or on haul roads when required by the Engineer or applicable environmental permits.
1.3.2.6.2.3 Excavation in Common Material
a.
"Common Material" should include all material other than "Rock" as defined herein. This should include
materials such as very stiff soils, glacial till, cemented gravel, and soft and disintegrated rock which can be
broken into pieces not exceeding 1 cu yd in size, by appropriate equipment, such as heavy ripping equipment
that does not require blasting for removal.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-44
AREMA Manual for Railway Engineering
Roadbed
b.
If the condition of the subgrade material in a cut is considered unsuitable by the Engineer, the material
should be removed or otherwise treated as directed. Replacement with backfill should be performed with
approved material that is compacted in accordance with the requirements of the project specification. The
supporting strength of the subgrade in cuts must be made at least equal to that on adjacent fills.
Subexcavation in cut areas and subsequent backfill with structural fill material is a common corrective
measure.
c.
Intercepting ditches should be excavated behind the top of cut slopes prior to excavation of the adjacent cut
at locations designated by the project plans or as directed by the Engineer to intercept water flowing toward
excavation areas. Material generated by excavation of intercepting ditches could be used to form a berm
between the intercepting ditch and the top of the cut.
d.
Material from any excavation, including drainage ditches, not required or not approved for use in fills
should be disposed of as approved by the Engineer.
e.
Excess material may require spreading, sloping, compaction or other treatment to ensure the stability of the
disposal area and its foundation. This is particularly important if the disposal area is located adjacent to or
above track grade.
f.
Slide materials that develop in cuts after they are properly formed, should be removed immediately by the
Contractor and the slopes should be modified, or otherwise treated as approved by the Engineer. Work
required to stabilize slopes could include such measures as flattening or benching of slopes, retainage
structure construction, surface or subsurface drains, and blanketing with coarse granular material.
1.3.2.6.2.4 Excavation in Rock
a.
"Rock" is typically all material considered as an integral part of bedrock which, in the opinion of the
Engineer, is not rippable, and requires continuous mechanical impacting, drilling and/or blasting operations
for removal. This definition of "Rock" may need to be adjusted to suit local conditions. Excavation of rock is
typically undertaken to enable the desired alignment to be created, enhance the stability of cut slopes, and
create drainage and catchment ditches. Project conditions may also require the generation of rock fill
material in lieu of "Common Material" borrow.
b.
The Contractor should exercise care and use suitable methods when excavating to avoid breaking down,
loosening or otherwise damaging rock beyond the specified subgrade level and cut slope lines. This general
requirement should be replaced by particular requirements where rock strata are adversely sloping or
jointed. The effect of blasting on long term slope maintenance should be considered and the appropriate
type of blasting specified.
c.
Side slopes in rock cuts may be formed by the general method of shaping them concurrently with or after
the removal of material from the cut or by the method of advance pre-splitting rock along the required plane
by blasting. If, in the opinion of the Engineer, the method chosen by the Contractor is not producing
acceptable forming of slopes, the Engineer may require a change in method. Rock beyond the line of the
side slopes, which is loosened by blasting or overbreak caused by construction operations beyond the
specified subgrade rendering it liable to slide or fall in the opinion of the Engineer should be removed by the
Contractor at his expense.
d.
Where rock materials are required for construction of fills, the Contractor should carry out blasting in such
a manner that the rock will generally meet fill requirements.
e.
The bottom of rock cuts should be excavated in such a manner that there will be free drainage without
water pockets. Ditches in rock cuts should be drilled and blasted only after the rock cut is excavated. It is
particularly important to prevent water pockets at the ends of rock cuts due to incomplete rock excavation
at the junction of rock and overburden at the specified subgrade level.
f.
Unless otherwise specified, excavation below the subgrade level should be built up with approved structural
fill material, compacted to the correct subgrade level and width for which no additional payment will be
made. In frost areas it is important that material approved for back fill in rock cuts be clean granular
material.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-45
1
3
4
Roadway and Ballast
g.
Intentional overexcavation and backfilling may be specified to remove rock subgrade material, in order to
provide a uniform track subgrade modulus between cuts and fills.
1.3.2.6.2.5 Controlled Blasting of Rock
a.
If controlled blasting is required to progress excavation, it should be done with extreme care only by
experienced and licensed Contractors in accordance with all applicable federal, state and local laws, codes,
and ordinances. The Contractor must fully comply with all regulations governing the transportation,
storage, handling, and use of explosives, and should be made responsible for obtaining all necessary permits.
b.
The Contractor should make all necessary arrangements satisfactory to the Engineer for the performance of
controlled blasting within the entire area of the contract. Complete and continuous precautions should be
taken by the Contractor to prevent any damages to persons, vehicles, railway equipment or track structure,
aerial or buried utility lines, structures, dwellings, or other manmade installations by reason of concussion,
vibration or flying material. When necessary to protect property or facilities from the mechanical effects of
controlled blasting, such as heaving by displacement, or projection of debris, properly weighted blasting
mats, steel cable meshes, or other approved protective devices shall be utilized.
c.
A detailed safety plan for the controlled blasting activities should be developed by the Contractor and
approved by the Engineer. Such a plan should outline the methods and signals to be utilized by the
Contractor to ensure clearance of the blast site, as well as the method to be utilized to absolutely protect rail
traffic before, during, and after the controlled blasting activity. No blasting shall be performed without the
presence of the Engineer or his authorized representative.
d.
Prior to the commencement of controlled blasting operations, the Contractor shall submit to the Engineer
for approval a blasting plan, including the drilling plan, a loading plan, and the type of initiation system to
be utilized. The use of electrical caps should not be allowed. Approval of the blasting plan by the Engineer
shall not relieve the Contractor from liability.
e.
If the Engineer deems that site conditions or the blasting plan warrant seismic monitoring, an evaluation
and seismic report for each shot shall be furnished to the Engineer for review. In the event the maximum
peak vector established for the location is exceeded, or if unexpected results occur, the Contractor shall
furnish an analysis of the affects on the surrounding conditions, i.e., structures, geology, etc., and the
proposed changes to the blasting plan to correct the action, to the Engineer for review and approval before
continuing blasting operations.
f.
When utilized to shape side slopes in cuts, advanced pre-splitting shall be performed in such manner as to
produce a uniform plane of rupture in the rock, such that the resulting back slope face shall be unaffected by
subsequent blasting and excavation operations within the section. The plane shall be formed for the entire
depth of the cut or to a predetermined bench level.
g.
Controlled blasting shall be performed in such a way that rock outside the authorized excavation lines shall
not be unduly loosened. If rock below the line of the side slope is loosened by advanced pre-splitting, or by
the primary blast to such an extent to render it liable to slip or slide, the loosened rock shall be removed by
the Contractor. Rock cuts shall be removed to a depth of 12 inches below the proposed subgrade elevation
and refilled to the subgrade elevation with approved material.
1.3.2.6.2.6 Measurement & Payment
The typical pay quantity for each classification, i.e. common material or rock, is the cubic yard. Payment is made
only for quantities of excavation which are required for the proper completion of work items covered in this
section. Additional excavation undertaken by the Contractor carelessly or solely for his benefit, such as required
for haul roads, relocation of equipment, and backfilling operations, should not be included when payment
quantities are measured.
When excavation is considered "Cut to Fill", material is typically measured once "in place", placed and accepted, or
calculated against the prepared (Cleared, Grubbed and Stripped) ground surface. Also see Placement of
Embankment.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-46
AREMA Manual for Railway Engineering
Roadbed
When excavation is considered "Cut to Waste" material is measured by determining a volume of excavation based
on an original (Cleared and Grubbed) ground surface and completed and accepted design surfaces.
It is recommended that care be taken in structuring of bid documents and specifications to avoid creating a
scenario where the Owners pay for excavation and then again pays for placement as embankment of the same
material.
1.3.2.6.3 Subexcavation
1.3.2.6.3.1 General
Subexcavation is defined as excavation that is required to remove unstable/unsuitable materials located below the
project plan grade lines. The need for subexcavation may be predetermined as part of a geotechnical exploration
program performed during the design phase of the project, or more routinely as an engineering decision made
during construction.
1.3.2.6.3.2 Procedures
Subexcavation should only be performed at the direction of the Engineer. In its simplest form, subexcavation may
consist of the total removal of unsuitable materials down to stable subgrade soils and replacement with compacted
earth fill. More complex forms of subexcavation may involve the excavation of a portion or all of the unsuitable
subgrade soils and their replacement with stabilization materials to facilitate the subsequent construction of the
embankment structure. Stabilization materials may consist of utilizing the excavated unsuitable soils and their
mixing with admixtures to make them suitable embankment soils. Stabilization materials may consist of granular
material possibly in combination with a geosynthetic material to facilitate subsequent grading operations. Other
locally accepted stabilization techniques may be utilized with approval of the Engineer.
1
1.3.2.6.3.3 Measurement & Payment
Measurement and payment may be based on a unit price compensation depending on the method of subexcavation
identified in the bid document; typically measured in cubic yards. The particular method may or may not be used
depending on site specific conditions. Measurement and payment may be based on a time and materials
compensation depending upon equipment, labor, and or material stated in the bid documents.
3
1.3.2.6.4 Placement of Embankment
1.3.2.6.4.1 General
Placement of Embankment is the process of constructing a foundation for the track structure where the natural
ground surface is below the desired elevation of the finished subgrade. Materials are placed so that the designed
Embankment Section and subgrade elevation are obtained. Materials to be placed are typically identified as either
"Common Material (Soil)" or "Rock", and are generally obtained from approved on-site excavation or approved on or
off-site borrow sites.
Materials consisting of "Common Material" should satisfy the soil characteristics designated for embankment fill as
specified in Table 1-1-10 in Section 1.2.3 to achieve appropriate design performance objectives.
1.3.2.6.4.2 Procedures
Placement of Embankment should be performed in accordance with the project plans or as directed by the
Engineer.
Embankment should be completed as far as is practical using suitable excavation material before borrow materials
are obtained from outside sources. Site conditions may prevent total utilization of excavated material and
necessitate use of borrow. However, consideration of the most efficient utilization of excavated materials is
important if the Contractor’s price for supplying borrow material is higher than his price for excavated material.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-47
4
Roadway and Ballast
The Contractor should maintain all working surfaces in areas where embankment placement activities are being
performed in a well-drained condition at all times. Embankment surfaces should be shaped and compacted during
placement to facilitate positive drainage and minimize absorption of water. Properly drained work areas typically
allow construction to resume more quickly with less waste following rainfall events.
Side and/or slope ditches, both above or at toe of embankments, should be constructed in a timely manner during
the course of construction to promote positive drainage of the site and facilitate placement of the embankment.
Care should be taken during placement of embankment material to avoid adverse impacts to previously
constructed ditches, drainage structures, or impede natural surface watercourses.
The Contractor should maintain haulage route surfaces to avoid rutting and water ponding. Ruts or depressions that are
allowed to remain on the working surface of the embankment will cause water pockets and subgrade instability.
The Contractor should be prepared to supply and apply water or other means of reducing dust at the placement
point or on haul roads when required by the Engineer or applicable environmental permits.
Final acceptance of embankment materials should only be made after the materials have been dumped, spread,
and compacted in place. Rejection by the Engineer may be made at the source, on the transporting vehicle, or in
place. Removal and disposal of all rejected embankment material should be at the Contractor’s expense.
The Contractor should inform the Owner of proposed off-site borrow sources, and allow sufficient time so that the
suitability of the material for use as fill can be investigated. The Contractor may be required to provide the
necessary personnel and equipment to perform adequate investigation and sampling. Responsibility for this
investigation should be defined in the construction documents. Representative samples of borrow materials should
be taken for laboratory testing to establish suitability of the material for use on the project.
"Fill Material" should be composed of "Common Material" or "Rock" as defined herein. In general, material such as
topsoil, loam, uniform fine sand, silt, and clay should be avoided. This recommendation can be modified and
adjusted on a site-specific basis depending upon local conditions, availability of borrow materials and prudent
design of the fill. However, the soil types named above are those usually found to be unsatisfactory for fills, and use
within the track subgrade area should be avoided if at all possible.
Borrow areas should not be excavated until they have been properly cleared and stripped, and mapped as required
by the contract documents. Borrow areas should be adequately drained during borrow operations, to prevent
saturation of the proposed fill materials.
At all times the Contractor should operate sufficient equipment to compact the fill at the rate at which it is being
placed. Choice of compaction equipment should be made by the Contractor and approved by the Engineer.
Typically, a sheeps-foot roller would be applicable for cohesive soil materials. A vibratory compactor would be
appropriate for granular fill materials. The chosen equipment must be capable of achieving the minimum
compaction requirement specified in the contract documents.
1.3.2.6.4.3 Construction of Fills with Common Material
Fills should be built by placing common material in successive layers over the full width of the embankment.
Where segregation is a concern, reblending for uniformity may be required. Where fills are designated to have
stabilization berms at or adjacent the toe of fill, the berms must be raised at the same time as the central portion of
the fill.
All earth-hauling equipment should be routed uniformly over the entire width of fill to obtain uniform compactive
effort from the earth-haul traffic.
Where new fill is placed against an existing slope, all vegetation should be removed, the surface deeply plowed or
stepped, and the new material thoroughly mixed with the old material to a horizontal distance approved by the
Engineer.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-48
AREMA Manual for Railway Engineering
Roadbed
Soil lumps larger than 8 inches in size should be broken by scarifiers or disks before compaction.
The thickness of each layer should normally not exceed 8 inches before compaction. Depending on the type of fill
material and the type of compacting equipment used, layers in excess of this thickness may be allowed with the
specific approval of the Engineer. In this case the Engineer may require the Contractor to perform rolling tests on
the fill material to determine acceptable layer thickness and minimum number of complete passes of the
compacting equipment to achieve the specified compaction. An additional rolling test should be considered
whenever either fill material or compacting equipment changes throughout a project.
Each layer should be fully compacted by approved mechanical compacting equipment before the next layer is
placed. A fully compacted layer typically should have a dry density of at least 95% of the maximum dry density as
determined by the current revision of ASTM Specification, Designation D 698T, Moisture-Density Relations of
Soils (Proctor Test), or 90% of ASTM D-1557 Moisture-Density Relations of Soils (Modified Proctor Test).
When the specified compaction density is not being obtained, placing of fill should be stopped and the material in
place should be scarified, adjusted in water content, if necessary, and re-rolled until the required compaction is
obtained. Alternately, material not fully compacted may be removed and replaced by the Contractor at his expense.
If before acceptance of the work, softening of the subgrade surface takes place under construction traffic to a
degree unsatisfactory to the Engineer, the soft material should be reworked or removed and replaced as indicated
previously. The cost of all such work should be borne by the Contractor.
In general, material approved for fill should have a natural water content close to the optimum water content for
compaction. When required, the Contractor should add water uniformly by means of an approved distributor to
any fill material, which is deficient in water content for compaction. If the fill material is too wet, it should be
scarified or disked and aerated until the proper water content is attained. With the approval of the Engineer, drier
soil may be blended with wet fill to achieve a water content suitable for compaction. It is important to note that
Soil strength depends on density and water content relative to optimum water content.
1
It should be noted that the ability to obtain desired compaction levels with certain types of soils may be improved
by adding lime, fly-ash, or other cementitious products. The use of such additives should be properly engineered.
3
1.3.2.6.4.4 Winter Grading with Common Materials
With the permission of the Engineer, the Contractor may place embankment during freezing weather. For this
purpose the Contractor should provide the necessary amount of earth moving and compacting equipment to assure
continuous operation during freezing weather in both excavation and embankment areas. All embankment
material should be compacted before freezing. If materials freeze before the required compaction is attained, the
placement of embankment should be stopped and the frozen material should be removed at the Contractor’s
expense before construction resumes. No snow, ice, or frozen material should be placed in the embankment, nor
should embankment be placed on materials incorporating snow and ice.
With proper guidance and expertise, it is possible to satisfactorily place embankment in temperatures down to 0
degrees F. A key consideration is access to borrow material known to have near optimum water content (as water
may not be added and drying of material in transit is minimal).
1.3.2.6.4.5 Construction of Fills with Rock
This section discusses some of the general issues associated with construction of fills using rock. While applicable
for any rock fill embankment construction, the guidelines below become increasingly important as fill size
increases.
In general, construction of fills using rock, both uniformly graded stone, and non-uniform shot rock, is less
complicated than fill construction using soil materials. This is due to the less critical role that moisture content
plays in achieving adequate compaction and relative density. Placement and compaction of rock fill material is
typically less affected by inclement weather than construction with Common Material.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-49
4
Roadway and Ballast
Rock fill should be transported and placed on site using methods approved by the Engineer. If well-graded rock fill
is specified, placement by end dumping should be avoided to reduce potential segregation of the material.
Segregated material should be re-blended, or otherwise modified by the addition of finer grained materials prior to
acceptance. The purpose of this practice is to reduce later migration of fines into poorly graded zones within the
fill.
Rock fill should be spread in the specified maximum loose lift thickness in near horizontal layers for the full width
of the design cross-section. The maximum loose lift thickness of rock fill typically should be no more than the size
of the maximum individual rock particle plus 30%. As example, shot rock fill with a maximum particle size of 24
inches, would equate to a maximum loose lift thickness of about 30 inches.
Each loose lift of rock fill should be compacted by full coverage with approved construction equipment until stable
as determined by the Engineer. In general, rock fill should be compacted using heavy pneumatic tired equipment,
tracked equipment, or vibratory roller type equipment. As example, a typical 30" rock fill lift should be compacted
with not less than four complete passes of a crawler type tractor weighing at least 25 tons. However, the Engineer
should be the final judge regarding the actual compactive effort required.
The void space within the rock fill matrix, the degree of compaction, and the overall fill height will influence the
degree to which the fill consolidates and settles. In general, some amount of settlement should be expected for
embankments constructed using rock fill, particularly if the fill has the potential for periodic saturation.
Depending on the size of the void space within the rock fill mass, a layer of geotextile, or a graded granular filter
layer may be warranted along the interface with adjacent finer grained materials. This is to reduce the potential
for migration of finer material into the rock fill void space. As noted above the use of a well-graded rock fill
material for embankment construction can help reduce this potential problem.
While moisture content of rock fill material is generally less critical to proper placement and compaction, repeated
saturation and drainage of rock fills can result in consolidation and settlement. In some instances, the addition of
water may aid in consolidation of the rock fill mass during initial compaction operations.
1.3.2.6.4.6 Widening of Existing Embankment Fills
The purpose of this section is to discuss some unique aspects of placing fill material for widening existing
embankments. Reference should be made to the recommendations presented above concerning general criteria for
fill placement and compaction.
Fill placement against an existing embankment should be performed using notching/benching techniques that
allow newly compacted fill to be constructed against existing stable embankment materials. These grading
operations should be performed using techniques that avoid undermining existing track structure, yet addresses
issues such as; clearing of the embankment slope, maintenance of drainage from within the existing embankment,
and preservation of existing embankment support elements.
Dependent upon site specific conditions, preparation of the slope and site should include removal of standing
vegetation and topsoil in a manner which does not destabilize the slope, This may require postponing the grubbing
of slopes until immediately prior to performing the notching/benching activities.
Fill placement against an existing embankment should include notching, keying or benching of the new material
into the existing slope as filling progresses.
The lateral extent of the notches, keys or benches, and the associated vertical cut in the existing slope, will depend
on the depth needed to remove soft or loose material and key into firm or competent material. In general, the size
of such notches, keys or benches is approximately 3 feet horizontally depending upon issues such as slope geometry,
undermining of track operations, etc. The actual geometry should be approved by the Engineer. During fill
placement, the width of the working surface, including the new fill and the notch or key, should be adequate to
facilitate safe equipment operation and proper mechanical compaction of the fill.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-50
AREMA Manual for Railway Engineering
Roadbed
If the existing embankment consists of granular material that drains easily and is widened by using lean clay
material there is the potential that water accumulation may occur along the non-uniform soil interface that may
result in slope stability problems unless drainage provisions are included in the construction. It is recommended
that the widened embankment be constructed of soils with characteristics similar to the existing embankment.
1.3.2.6.4.7 Fills in Soft Foundation Areas
Soft soil conditions that extend to shallow and great depths may unexpectedly be encountered during construction.
Depending on the depth and extent of such conditions, a variety of treatments may be appropriate.
In the case of shallow conditions, when the Engineer does not require subexcavation as a specific foundation
stabilization method and drainage of the foundation soils is impractical, it may be appropriate that an initial lift of
stabilization material may be installed. This initial supporting layer of fill is commonly termed a "bridging lift".
Normally this layer consists of granular or well graded rock material that is placed over the full foundation area of
the proposed fill. Its surface should be compacted. It is important to note that a variety of geosynthetic materials
are available for use in formation of "bridging lifts". Thereafter the remainder of the fill should be built up in
layers to the specified thickness.
In the case of deep soft conditions, more sophisticated solutions may be required. These may include staged
construction, surcharging, berm or buttress construction, deep foundation systems, and/or foundation drainage
techniques. Reference should be made to the design section of this text for recommendations concerning such
methods implementation.
1.3.2.6.4.8 Trimming
All cuts, fills and ditches should be left in a neatly trimmed condition to the specified widths, elevations, and slopes.
Borrow areas should be graded and finished to a neat and regular slope.
1
All waste and stockpile areas should be left in neat, trimmed conditions to the satisfaction of the Engineer.
Positive drainage of all areas should be provided.
3
1.3.2.6.4.9 Measurement & Payment
The pay for embankment construction is typically measured on a cubic yard basis (i.e., as measured either in place
or in the cut section). Payment is made only for quantities of embankment required for the proper completion of
work items covered in this section. Additional embankment undertaken by the Contractor carelessly or solely for
his benefit, such as required for haul roads, relocation of equipment, and backfilling operations, should not be
considered or measured for payment.
Care should be taken in structuring bid documents and specifications to avoid creating a scenario where the
Owner pays for excavation and also pays for placement of the same material as embankment.
1.3.2.6.5 Placement of Sub-ballast Material
1.3.2.6.5.1 General
The purpose of sub-ballast is to provide a separation layer between the subgrade and ballast using a material with
strength equal to or greater than the subgrade. Track laid on prepared subgrade without sub-ballast tends to drive
the ballast and/or ties into the roadbed forming depressions which later develop into ballast pockets requiring
additional maintenance. Sub-ballast can be considered as a component of either roadbed or track construction
depending on the project.
1.3.2.6.5.2 Materials and Procedures
Sub-ballast material should meet the requirements for quality and grading set out in Part 2, Ballast
.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-51
4
Roadway and Ballast
Sub-ballast material should be placed to the cross sections and tolerances shown on the plans. Placement should
be in layers not exceeding the thickness that can be effectively compacted to its full depth with the available
construction equipment.
Rutting or disturbance of the completed subgrade should be avoided. Disturbed or rutted subgrade materials
should be either properly reworked or removed from the fill and replaced.
1.3.2.6.5.3 Measurement and Payment
The measurement for sub-ballast material is commonly made on a net ton or in-place cubic yard basis per the
design cross-sections.
Payment should be based on quantities from certified scale tickets or as measured and calculated in-place per the
design cross sections by the Engineer. Said unit price should include the entire cost of supplying, hauling, placing,
moisture conditioning, blading, and compacting sub-ballast material.
1.3.2.6.6 Seeding and Mulching
1.3.2.6.6.1 General
The purpose of seeding and mulching is to establish managed vegetative growth to quickly stabilize exposed
earthen surfaces. It is recommended that all earthen slopes and surfaces disturbed or constructed under the
contract be seeded and mulched.
1.3.2.6.6.2 Materials
a.
Specifications for seed, fertilizer, and mulch, as well as their rate of application should conform to
recommendations of the applicable State or Provincial Department of Transportation, the United States
Department of Agriculture, or be obtained from a qualified agricultural consultant with experience in the
general vicinity of the project. Requirements of applicable project environmental permits should be
considered.
b.
Seed should be of high grade and of known vitality, purity, and germination and should be delivered in bags
or containers bearing seed tags as required by law, showing percent of germination, purity of seed, and
percent of weed seed.
c.
Fertilizer should be of standard commercial grade with the analysis shown on each package. If delivered in
bulk there should be a material certification provided with each delivery. Any fertilizer which becomes
caked or otherwise damaged should be rejected.
d.
Typical mulches include hay, straw, wood cellulose fiber, and recycled vegetative material.
e.
It should be noted that on a site-specific basis, erosion resistant specialty products and application methods
are available to aid in site revegetation.
1.3.2.6.6.3 Procedures
a.
Consideration should be given to the stockpiling of topsoil removed during stripping operations and to its
redistribution on disturbed or constructed surfaces.
b.
The surface to be seeded should be dressed to eliminate gullies on cut and fill slopes. Dressing should be
done by a drag or blades to produce a uniform surface. Plowing or disking is generally not necessary except
where construction operations have packed surfaces too hard to permit plant growth.
c.
Seed and fertilizer should be applied to take advantage of favorable weather conditions. It should be applied
by a method which provides uniform distribution in accordance with the appropriate specification.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-52
AREMA Manual for Railway Engineering
Roadbed
d.
It is advisable to set minimal plant establishment rates in the specifications to guarantee performance. In
such instances the Contractor may be required to redress and reseed the subject areas.
e.
Care should be taken to avoid contaminating the sub-ballast and ballast sections of existing or recently
completed trackage in the work zone with seed, mulch, or other material.
1.3.2.6.6.4 Measurement and Payment
a.
Seeding and mulching typically are measured by the acre or fraction thereof so treated.
b.
The unit price for seeding and mulching should include the entire cost of preparing the ground, furnishing,
hauling and placing materials discussed above and furnishing all labor, equipment, tools, and incidentals
necessary to complete the work.
SECTION 1.4 MAINTENANCE
1.4.1 MAINTENANCE OF ROADBED (2007)
1.4.1.1 General
a.
The roadbed is that portion of the track structure beneath the ballast section and within the zone of
influence of live traffic loads, including foundation support. The performance of the roadbed is greatly
influenced by the following factors:
1
(1) The presence of excess moisture in the roadbed and the site specific drainage characteristics of the
roadbed and ballast section.
3
(2) The engineering properties, thicknesses, and in-place densities, of the various materials.
(3) The effect upon the roadbed of environmental factors: especially, precipitation, temperature, and the
presence of groundwater.
(4) The magnitude, speed, and repetition of the rail traffic loads.
(5) The characteristics of the track superstructure (rail and ties), ballast and sub-ballast; especially, the
thickness of the ballast section.
b.
Of all the factors affecting roadbed performance, the presence of excess moisture in combination with one or
more other factors is the root cause for most roadbed maintenance problems. Therefore, the design and
maintenance of drainage away from, or out of, the track foundation materials is of primary concern and
paramount to the success of most corrective measures.
c.
The roadbed consists of the natural foundation materials (native soil or rock), and the overlying imported
soils extending downward from the bottom of the ballast and sub-ballast section that is within the major
zone of influence of live traffic loads. In new construction and in some existing tracks, the roadbed is
separated from the ballast and sometimes sub-ballast by distinct boundaries. However, in most cases, there
are no distinct boundaries between layers of the ballast, sub-ballast, and roadbed.
d.
The zone of significant influence from train loadings extends to an approximate depth of five feet beneath
the ballast section. Beneath this level, the stresses from live traffic loads are relatively low.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-53
4
Roadway and Ballast
e.
The roadbed can be composed of a wide variety of materials. The most predominant materials are local
native soils and soils imported from nearby sources. In the upper layers of the roadbed, imported materials
including cinders, sands, and pit run gravels may be found intermixed with the ballast materials that have
been placed during track surfacing cycles.
f.
The composition and thickness of the materials and the drainage conditions existing in the upper two feet of
the roadbed are extremely important because of the high stresses from track loads and exposure to
environmental factors. Roadbed induced track problems such as loss of line, surface, gauge, mud pumping
and ballast fouling in most cases can be traced to one or a combination of deficiencies in the material
properties, thickness, or drainage characteristic within the upper two feet of the roadbed. Therefore, most
roadbed maintenance measures may need to be concentrated at making improvements to the upper two feet
of the roadbed and especially to the interface between the ballast (or sub-ballast) and the roadbed soils in
addition to making improvements to the drainage.
g.
Additional details regarding the design and construction of roadbeds are discussed in greater detail in
Section 1.1 through 1.3 of this Manual.
1.4.1.2 Existing Roadbeds
a.
The great majority of railroad roadbeds in service today were originally constructed many years ago and
without the benefit of modern methods and equipment, or the benefit of current engineering
understanding. In many instances the track was built directly on top of the native loose soils or on nearby
borrow soils that were loosely dumped and spread in place to form narrow shallow fills with steep side
slopes. Little attention, if any, was given to selecting soils with more favorable roadbed properties or
compacting the roadbed soils before constructing track. However, over the years, these roadbeds have
tended to become firm and stable from the compaction and consolidation effects of rail traffic and from the
numerous surfacing cycles that have contributed granular materials and ballast to the roadbed. Subsurface
exploration of existing roadbeds will often reveal several layers of soil, imported granular materials, and old
ballast of varying thicknesses and depths. An example of a distorted roadbed and method of reporting such
conditions is shown in Figure 1-1-12.
LOOKING RAILROAD DIRECTION ________________________
BALLAST AND LOAM
0
1
BALLAST AND LOAM
LOAM
FOULED BALLAST
SLAG WITH SOME LIMESTONE
2
ND EL
TA
V
DIR GRA
Y
D
SAN
DIRTY SANDY GRAVEL
CLEAN SANDY
GRAVEL
3
4
5
GRAY MOTTLED CLAY (VERY SOFT)
6
7
STABLE FOUNDATION MATERIAL
12 11 10 9
8
7
6
5
4
3
2 1 0 1
FEET
2
3
4
5
6
7
8
9 10 11 12
Figure 1-1-12. Example of Distorted Roadbed Cross Section
b.
There are many instances of a continual loss of line and surface accompanied by mud pumping, often
referred to as “chronic spots” or “soft spots.” Subsurface explorations of these chronic problem areas will
often reveal unsuitable materials at great depths mixed with ballast sometimes referred to as “ballast
pockets.” An example cross section of typical ballast bowl or pockets is shown in Figure 1-1-13.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-54
AREMA Manual for Railway Engineering
Roadbed
DISPLACED SUBGRADE
(SHOULDER HEAVE)
ORIGINAL TOP
OF SUBGRADE
BALLAST SECTION
BALLAST POCKETS
TRAPPED
WATER
Figure 1-1-13. Example Cross Section of Displaced Roadbed and Ballast Pocket
c.
Another problem with some older fills is a cinder fill fire. Cinders were used as fill materials in a number of
older fills. The cincers frequently have an organic component related to unburned coal. The pressure of a
fill is not believed to be sufficient to ignite these fires. However, some are undoubtedly started by outside
combustion sources such as lightening and range fires. These fires can be spotted before they get very large
by their effect on vegetation or snow cover and their emission of a unique acetylene odor. These fires are
nearly impossible to put out with water. The best way to stop the fire is to dig out the cinders and replace
with a better fill material. It is possible to stop smoldering or burning by capping with cohesive fill that cuts
off the supply of oxygen. However, a small leak in the oxygen cap will limit its effectiveness to prevent
burns. The burning cider material can cause consolidation of the fill, which could result in settling of the
track structure.
1
1.4.1.3 Identifying Roadbed Instability
a.
b.
Initial evidence of roadbed instability is a continual loss of line and surface despite satisfactory rail and tie
condition and an assumed adequate ballast section. Loss of line and surface may continue even after several
ballast applications followed by lining and surfacing operations. A muddy, fouled ballast section and heaved
track shoulder (see Figure 1-1-13) are other indications of roadbed instability. Excess moisture and poor
drainage conditions are so closely related that evidence of either can almost be considered as an indicator of
roadbed instability. However, caution should be used before identifying a muddy fouled ballast section as
roadbed instability. In some cases internal abrasion and weathering of the ballast or windblown dirt and car
droppings will cause a fouled ballast section and give the appearance of roadbed instability. If any doubt
exists as to the cause or extent of roadbed instability; subsurface explorations, sampling and geotechnical
testing of the roadbed materials should be performed. The technique of excavating a trench several feet
deep across the width of the ballast section for the purpose of exposing the layers, thicknesses, and relative
positions of the roadbed materials is strongly recommended as an aid in the planning any roadbed corrective
measures. See example in Figure 1-1-12.
Vertical and lateral displacements of the roadbed as evidenced by loss of track line and surface may actually
originate beneath the roadbed zone. The possibility that embankment, slope, or foundation stability
problems exist and are contributing to roadbed displacements should be investigated and analyzed before
attempting roadbed corrective measures. Refer to Article 1.2.2 and Article 1.2.3 for further information.
1.4.1.4 Types of Roadbed Instability
a.
Possible indications of unstable track include the loss of surface, line and gauge, and fouled ballast. These
may be caused by the following roadbed conditions:
(1) Migration and pumping of the subgrade and roadbed materials into the ballast section. The ballast
section becomes contaminated with fine materials resulting in poor drainage, a dramatic decrease in the
overall strength of the ballast system, and a loss of surface and line.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-55
3
4
Roadway and Ballast
(2) The vertical and lateral displacement of the roadbed soils and roadbed materials as reflected in surface
and line of the track.
(3) Frost heaving of subgrade soils and roadbed materials.
b.
The presence of excess moisture in the roadbed is the single most important factor contributing to roadbed
instability. An increase in the weight, speed, and frequency of traffic will also contribute to overstressing
the subgrade and roadbed material and pumping fines upward into the ballast. Frost heaving is heavily
dependent on unfavorable environmental and roadbed material conditions and to a lesser extent on traffic.
1.4.1.5 Migration and Pumping of Roadbed Soils and Materials
a.
Subgrade and roadbed soils may be pumped up into the ballast voids by the action of repetitive wheel loads.
Fine sands, silts, clays, and clayey silts are highly susceptible to pumping when excess moisture is present in
the roadbed.
b.
Pumping and migration of roadbed soils can be controlled or eliminated in existing track by the methods
listed below:
(1) Improving the drainage to keep the roadbed dry. Both surface and subsurface drainage improvements
will reduce pore water pressure build up and will increase the strength of the roadbed. Surface drainage
of the roadway is described in Article 1.2.4. Improvements to subsurface drainage are described in
Article 1.2.4.2. Before considering subsurface drainage, an adequate field investigation and drainage
.
system design should be performed. Lateral and longitudinal subdrains consisting of perforated pipes,
geotextiles, and free draining backfill materials can be used in combination to improve the roadbed
drainage.
(2) Removing the track and fouled ballast and reconstructing the roadbed by adding a compacted granular
sub-ballast layer of sufficient thickness that will function as a firm, load bearing layer that diverts water
away from the roadbed. The sub-ballast also functions as a filter against the intrusion and migration of
roadbed and subgrade fines. It is recommended that the sub-ballast consist of a well graded crushed
rock that is consistent with the design recommendations presented in Section 2.11, Sub-ballast
Specifications. It is recommended that the sub-ballast layer be at least 6 inches thick and should be
placed and compacted in accordance with Section 2.11.
(3) Removing the track and fouled ballast and reconstructing the roadbed with a layer of high strength,
flexible or rigid stabilized material. Hot-mix asphalt concretes have been used with success as a flexible
stabilized roadbed. Lime treated soils, soil-cements, cement treated bases, and Portland cement
concretes have been used as rigid stabilized materials. The stabilized materials should be of adequate
thickness and include provisions for drainage and prevention of pumping.
(4) Placing an appropriate geotextile or filter fabric (combined with removal of fouled ballast) below the
ballast section. The application and physical requirements for geotextiles are given in Part 10,
Geosynthetics. With careful planning, the geotextile may be effectively placed during an undercutting
or sledding operation that avoids total removal or lifting of the track. The primary purpose of the
geotextile is to function as a filter that separates the ballast and sub-ballast from the fine grained
roadbed soils. The geotextile may also function to reinforce the roadbed and reduce ballast penetration
into the roadbed section.
(5) Injecting chemicals into the roadbed. Lime, lime/fly ash, and cement slurries injected at relatively
shallow depths and close spacing have been used with some success to reduce pumping and prevent
migration of fines into the ballast section. Use of chemical injection should be preceded by a program of
subsurface exploration, sampling, and laboratory testing to determine if the chemical will react with
and improve the roadbed material and soil.
(6) Increasing the thickness of the ballast section by track raise.
(7) Applying and compacting a layer of well graded sand utilizing large on-track equipment similar to an
undercutter. This equipment is capable of lifting the track as a unit, removing fouled ballast, laying and
compacting a sand layer and replacing the ballast. This technique and equipment has been used with
success in Europe.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-56
AREMA Manual for Railway Engineering
Roadbed
1.4.1.6 Vertical and Lateral Displacement of Roadbed Soils and Materials
a.
Areas where track settles repeatedly under traffic requiring frequent surfacing and lining can be caused by
deformation of weak and plastic subgrades and roadbed materials. The deformation may be accompanied by
the roadbed squeezing/pumping up between the ties or out at the end of ties, or bulging on the upper
roadbed side slopes. These track areas that require frequent surfacing are often called “soft spots”, “chronic
spots” or unstable roadbed.
b.
Soft spots usually occur where there are low strength and/or saturated subgrade soils and roadbed materials
that permanently deform under traffic causing a local depression in the roadbed beneath the track.
c.
Soft spots or unstable roadbed are believed to develop as follows:
(1) An existing track or recently constructed track is located over plastic subgrade or roadbed materials
that loses strength as a result of increase in moisture content. In most cases the roadbed and subgrade
become wet resulting in a loss of strength under repeated train loadings. Traffic loads transmitted
through the rail, tie and ballast structures overstress the roadbed and subgrade resulting in permanent
deformation and the creation of a depression that traps water. Trapped water facilitates further loss of
subgrade strength, resulting in track movement.
(2) The continual cycle of repetitive wheel loads combined with saturation results in the roadbed becoming
plastic and displacing or squeezing laterally beyond the ends of the ties to the track shoulder. Frequent
additions of ballast combined with surfacing supplies material that entraps more water, all of which
permits the deformation and displacement to continue.
(3) A ridge of displaced roadbed materials and soils is raised around each depression. Displaced soils are replaced
with ballast that forms a large ballast pocket capable of holding greater amounts of water. Roadbed materials
and soils at the base of the pocket continue to be saturated, weakened, and displaced, all resulting in a selfperpetuating condition.
d.
Corrective techniques for soft spots and unstable roadbed can be divided into those that must be performed
by removing the track and those that can be performed without removing the track.
e.
When the track cannot be removed; displaced and deformed roadbeds, soft spots, and ballast pockets may be
corrected by solutions such as:
(1) Improvements to surface and subsurface drainage. The surface drainage can be improved by
constructing a system of ditches parallel to the roadbed with catch basins, culverts and other surface
drainage facilities that will quickly dispose of surface water away from the track roadbed. However,
caution should be used when constructing parallel side ditches to avoid undermining adjacent roadbeds.
Subsurface drainage improvements should be preceded by a thorough field investigation including
subsurface explorations, trenches to expose the roadbed, laboratory testing and an analysis to design
any needed subsurface drainage system.
(2) Subsurface drainage systems that are properly installed can effectively drain water that is entrapped
within the subgrade soil and improve the bearing capacity of the roadbed materials. Subsurface
investigations performed by digging a cross trench will often make the problem apparent. The solution
to the problem sometimes consists of the installation of a French drain within the exploratory ditch.
The exploratory ditch should be dug deep enough to get to the bottom of the water pocket (ballast bowl)
and then backfilled with a free draining granular material. To prevent clogging this material should be
appropriately graded or protected with filter fabric. Installation of a perforated pipe to speed drainage
can increase its effectiveness.
(3) Another subsurface drainage system that may be appropriate to improve subgrade stability involves the
installation of a French drainage system parallel to the ends of ties with periodic lateral drain pipes
installed to drain into the adjacent railroad ditches.
(4) In many cases improvements to the drainage can be combined with other corrective techniques such as:
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-57
1
3
4
Roadway and Ballast
(a) Geotextiles, geogrids and other reinforcing materials may be installed in combination with
undercutting, sledding or other track raise techniques that avoids the total removal or shifting of
the track. The geotextile and geogrid used in this manner must possess the strength and other
material properties necessary to act as a reinforcement capable of bridging over the unstable area or
soft spot. The geotextile and/or geogrid should at least be 8 inches and preferably 12 inches beneath
the bottom of the tie, at least deep enough to avoid damage by surfacing equipment.
(b) Stabilization of the roadbed by lime, lime/fly ash, or cement injection. This treatment technique
can be used for void filling purposes and moisture reduction or for ground improvement due to
chemical reaction between the admixture and the roadbed materials. Use of lime, lime/fly ash or
cement injection should be preceded by a program of subsurface exploration, sampling and
laboratory testing to determine if the lime, lime/fly ash or cement will react with and improve the
roadbed soils and materials. The injection of lime and lime/fly ash slurry into unstable roadbeds,
soft spots and ballast pockets has been most successful with certain reactive clays, granular
materials, cinders, and silt materials. A grouting specialist should be consulted to determine
appropriate applications and expected results. Lime slurry chemically improves reactive soils and
increases the strength at depths to 40 feet. Double lime injection is often required to improve
shallow soil problems in areas where stresses are highest.
(c) Construction of shoulder berms. Railroad roadbeds constructed on shallow narrow embankments
often become unstable due to a combination of poor roadbed materials and a lack of lateral
confinement extending beyond the end of the ties. This condition can be corrected by the addition of
small berms to the roadbed side slopes. The effect of the berm construction on the roadbed drainage
should be carefully analyzed prior to building any berms. Stabilization berms should always be kept
below the level of the ballast and the upper portion of the sub-ballast. The berms should have good
cross slope to promote drainage.
f.
When the track must be removed; displaced and deformed roadbeds, soft spots and ballast pockets can often
be corrected by methods such as:
(1) Improving the surface and subsurface drainage conditions as described in Article 1.4.1.5.b.1, combined
with excavation and wasting of the fouled ballast and roadbed material and replacement with properly
placed and well compacted suitable soils and a sub-ballast layer as described in Article 1.4.1.5.b.2 or
replacement with a high strength stabilized layer of sub-ballast as described in Article 1.4.1.5.b.3.
(2) Excavation of the ballast and disturbed roadbed materials. Reconstruct with compacted fill materials.
Place geotextile and/or geogrid at the ballast/roadbed interface or the sub-ballast/roadbed interface.
Properly designed and installed geotextile will separate and act as a filter preventing the fine roadbed
and soil materials from migrating into the ballast section. Geotextiles and geogrids can be installed as
needed to reinforce the ballast/roadbed system. Improvements to surface and subsurface drainage
conditions should be performed as required to avoid future loss of subgrade strength.
(3) Injection or mixing of the track subgrade and foundation soils with lime, lime/fly ash, or cement in
combination with corrective methods listed above. Use of chemical injection or mixing should be
preceded by a program of subsurface exploration, sampling and laboratory testing to determine if the
chemical will react with and improve deficiencies within the track subgrade and foundation materials.
1.4.1.7 Frost-Heaving
1.4.1.7.1 Causes and Occurrence
a.
Frost-heaving of roadbed and ballast is caused by the simultaneous presence of fine-grained material, water
and freezing temperatures.
b.
The degree of frost heave in soils increases with increasing moisture content. Rough track is caused when
differential heaving of subgrade soils develops over short distances along or across the track.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-58
AREMA Manual for Railway Engineering
Roadbed
c.
These differences may be more or less than the uniform track heaving that seasonally occurs. More heaving
than average (rise in track) may occur typically at poorly drained areas (such as farm and road crossings).
Less heaving than average (dip in track) may occur at culverts and road crossings where de-icing chemicals
are applied. A change from a heaving to a non-heaving condition may occur at bridge approaches or at the
end of rock cuts. A good proportion of all types of heaving occur in regular track where no particular
features are present but a change in subgrade soil occurs. Before deciding on treatment it is important to
determine whether the rough track condition is created by a rise or a dip in the track.
d.
Rough track, caused by frost-heaving, causes excessive wear on both track and rolling stock and increases
the danger of accidents unless slow orders are applied or track conditions improved. The most common
method of improving the track surface is by the temporary shimming of ties. However, this is expensive,
reduces the service life of wood ties, and requires an experienced labor force to be kept on hand, particularly
at the start of freezing and thawing seasons when heaving and subsidence occur relatively suddenly.
Concrete ties cannot be shimmed more than a small amount. For these reasons, the methods of managing
track-heaving discussed below should be considered as an alternative to temporary shimming.
1.4.1.7.2 Track Betterment
a.
Frost-heaving under track may be reduced or made more uniform by influencing one or more of the
conditions causing it. This may occur as a side effect of work done primarily to improve other track
conditions:
(1) Cleaning of fouled ballast will remove fine-grained material and reduce capillary rise of water.
(2) Addition of a ballast lift will increase insulation that reduces frost penetration into subgrade soil.
1
(3) Addition of bank-widening material may reduce frost penetration into track shoulders.
b.
While beneficial, the overall effect of these measures on frost-heaving is limited. Where heaving of track
must be eliminated, a more direct approach to the problem is required.
3
1.4.1.7.3 Replacement of Frost-Heaving Material
a.
Although expensive under an operating track, replacement of frost-susceptible subgrade soil with a less
susceptible material is a method of treating the problem. Steps to be taken are:
(1) When frost-heaving and shimming are at a maximum in early spring, find by sighting along track
whether the trouble spot is caused by a rise or a dip in the track. Mark the location according to the
procedure shown in Figure 1-1-14. At the same time, excavate to find the maximum frost depth.
(2) After all frost is out of the ground, remove track and excavate over the length of section (A) in Figure 11-14 to remove the subgrade soil to a depth of at least 60% of the maximum frost depth. In both
transition zones (B), taper the excavation uniformly to zero at the outer ends. Carry the excavation to
the shoulders for proper drainage.
(3) Backfill to grade level with thoroughly compacted layers of non-heaving material (Column 4 of Table 11-10).
(4) Replace sub-ballast, ballast and track.
b.
Under special or extreme conditions, the installation of a layer of insulating material in the roadbed should
be considered.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-59
4
Roadway and Ballast
RISE
Nail or Stake
Maximum Height of Shims
6 Cribs
B
6 Cribs
A
Track
Maximum Height of Shims
B
DIP
Nail or Stake
Nail or Stake
End of Shimming
Track
12 Cribs
12 Cribs
B
A
B
ZONE A - FULL EXCAVATION OR TREATMENT
ZONE B - TAPERED EXCAVATION OR 1/2- STRENGTH TREATMENT
Figure 1-1-14. Method of Marking Track for Treatment of Frost Heaving
1.4.1.7.4 Drainage
Drainage improvement measures could be considered to reduce track heaving when ditches are less than several
feet below top of sub-ballast level or if water pockets exist within ballast bowls under the track section. Depending
on site conditions, improvements can include deepening of the railroad ditches. Additionally, consideration could
be given to the excavation and replacement of track shoulder materials with clean granular material and
installation of French drains transverse to the track alignment and at sufficient depth to drain of water pockets
located within ballast bowls beneath the tracks.
1.4.1.7.5 Use of De-icing Chemicals
a.
The controlled application of de-icing chemicals can reduce heaving of track economically and reasonably
effectively. Many chemicals have been tried for this purpose and ordinary crushed rock salt (NaCl) has been
found to provide adequate results.
b.
The procedure shown in Figure 1-1-14 should be used to show where the salt is to be applied. A small
quantity of salt is more effective than a larger quantity.
c.
Extensive use of salt or other de-icing chemicals for track de-icing may be restricted in some areas due to
potential environmental impacts. These restricted areas may include areas where tracks cross water supply
reservoirs, wetlands, etc.
1.4.1.7.6 Track Shimming
Shimming is done to restore track surface and level to a safe condition. For the purpose, wood shims are installed
on the top of ties which remain too low during track heaving. Shimming in no way reduces frost heaving and must
therefore be done every winter. Procedures used to shim track are given in Chapter 5, Track.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-60
AREMA Manual for Railway Engineering
Roadbed
1.4.2 MAINTENANCE OF ROCK SLOPES (2007)
1.4.2.1 Rock Falls
a.
Rock falls occur in cuts and on sidehill portions of railway lines in rough terrain. Where rock faces have
been exposed for a number of years, single rocks or small groups of rocks are usually involved rather than
the failure of entire slopes. For this reason, accurate prediction of rock falls is not always achievable.
However, an experienced person (geologist or geotechnical engineer) can assess the risk of rock falls at
particular locations and make recommendations, accordingly.
b.
Rock falls cost money due to regular maintenance, track patrols, train delays and rerouting required, and
damage to equipment, and/or injuries and sometimes deaths. Safety is the main concern.
1.4.2.2 Methods of Treatment
a.
From an assessment of site conditions and performance, the most suitable treatment of a dangerous rock
slope can be chosen. Treatment methods can include both preventive techniques and protective techniques.
Methods of treatment should be considered in the following priority if the danger of rock falls is to be
reduced:
(1) Stabilization, or preventing rocks from moving out of place unexpectedly (as with overall slope
flattening, rock scaling, and rock pinning or bolting).
(2) Protection of track, or keeping rocks which do move out of place from reaching the track (as with
netting, walls or rock sheds).
1
(3) Warning traffic when rocks arrive in the vicinity of track (as with slide detection fences).
b.
These techniques offer ways to manage the problem. Preventive measures address the cause of the
problem. Protective measures or warning methods by themselves have no effect on the causes of danger.
c.
A general approach to rock fall hazard management is outlined in Figure 1-1-15. Remedial treatment
methods are explained in Reference 40.
d.
Remedial work should be planned by railway engineering staff with particular experience in rock fall
problems, using consulting advice where needed.
e.
Good records are the basis for good planning and for the setting of priorities. Records should include the
time and exact location of accidents and delays to traffic, of all rocks found on track, and of the removal of
ditch debris, as well as plans and maintenance required for all stabilization and protection installations.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-61
3
4
Roadway and Ballast
Rock Fall Event
Assess Site Conditions
Angle, height, and condition of slope.
Size and condition of rocks,
Path of rock fall to track,
Maintenance required.
Engineering
Judgment
Scaling, excavation,
drainage, shotcreting,
support and restraint
systems, buttresses,
bolting, walls, or beams.
Warning
Methods
Protection
Methods
Stabilization
Methods
Track diversion;
Ditch shaped or bench
formed to retain rocks;
Net, fence, cables, blanket
or wire mesh;
Catch wall of concrete
gabions, old rails, or rock;
Shed or tunnel.
Electric wire;
Electric fence;
Combined warning and
protection.
Figure 1-1-15. General Approach to Rock Fall Hazard Management
1.4.2.3 Follow-up Inspections
A regular inspection should be made, preferably with an experienced person, to appraise hazards and decide on
action and priorities required. Rock work is best done by experienced contractors, with a contract drawn up to
allow flexibility in the work if conditions are found to be different than expected.
1.4.3 MAINTENANCE OF EARTH SLOPES (2007)
1.4.3.1 General
a.
Many earth slope failures are related to drainage problems. For maintenance of drainage see Article 1.4.5.1.
b.
Some roadbed failures can be prevented, solved or reduced by recognizing the problem and taking small
steps before the problem gets severe. Some warning signs of slope instability are:
• Cracks or seams in the roadbed especially near the ballast shoulder.
• Trees leaning.
• Ditches at the base of roadbed clogged because of bulges in fill.
• Slip circles or slides on the embankment.
• Seepage or extremely wet spots on the fill.
c.
Upon finding these conditions additional investigation should be done to determine the extent of the
problem. Most of these conditions will only be made worse by unloading ballast at the top of the fill.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-62
AREMA Manual for Railway Engineering
Roadbed
d.
Earth slope failures of this type can sometimes be contained by adding weight to the toe of the slide area.
Care should be taken to establish the shape of the failure plane. An excellent material to add weight is rip
rap, or shot rock fill. Granular material will allow any seepage water to drain from the face of the
embankment foreslope.
e.
Reducing the moisture content of the fill by methods described in Article 1.4.1.3.a. can also help to stop or
slow earth slope failures.
1.4.3.2 Methods of Earth Slope Restoration
a.
Methods of restoring slope stability are chosen on the basis of site observations and analyses made, and the
suitability, feasibility and economies of the various alternatives. It is sometimes possible to gain time to
implement these measures by temporarily moving the track around the area of instability.
b.
Methods are reviewed in Table 1-1-12.
Table 1-1-12. Potential Methods for Stabilizing Earth Slopes
Method
Remarks
Reducing Sliding Forces
1.
Remove soil at top of slide area, flatten slope.
Not always feasible.
2.
Divert surface water flows to reduce erosion and
infiltration.
Use ditches or flumes, lined if necessary. Reduce
infiltration by covering with materials that have low
permeability.
3.
Lower ground water level within sliding mass.
Assumes slide mass will release pore water to drains.
Drains can be excavated trench type drains or drilled in
horizontal or vertical drains.
4.
Eliminate leakage from culverts.
Not always feasible.
3
Increasing Resisting Forces
5.
Install pervious blanket.
To keep slope surface material in place, preventing
gullying and sloughing.
6.
Construct berm over lower portion of slide area and
beyond toe.
Useful if feasible. Proportion berm on basis of stability
analysis; ensure outer slope of berm is stable. Use free
draining material or install granular blanket on slope
beneath the berm to provide through drainage. Compact
berm material. Riprap facing should be installed on toe
of slopes that will be exposed to erosion by currents or
wave action.
7.
Install wall or crib (see Chapter 8, Concrete
Structures and Foundations, Part 5, Retaining
Walls, Abutments and Piers and Part 6, Crib
Walls).
Must be founded on stable ground. May be expensive.
8.
Install vertical piles along track.
Only successful if capable of resisting sliding forces. Piles
act as pins to resist the shear forces along the failure
plane. Piles may need to be drilled and socketed into
bedrock. Piling can also be installed as adjacent pairs on
either side of track and be tied together using either cable
or rods that are installed under the track. Lagging can be
installed between adjacent pins on the same side of the
track to form a crib.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1
1-1-63
4
Roadway and Ballast
Table 1-1-12. Potential Methods for Stabilizing Earth Slopes (Continued)
Method
Remarks
Special Methods
9.
Drill in tie-back anchors can be used with reaction
blocks or with vertical beams and lagging.
Must be designed by experienced engineer, especially if
planned for permanent support.
10. Densify soil by vibration or compaction.
Only possible with some granular soils. Specialized
technique.
11. Grout, freeze, or apply electro-osmosis.
Applicable only to special conditions. Very expensive.
Experienced advice required.
12. Plant stabilizing vegetation on face of slope.
Reduces water content of slope to shallow depths.
Experienced advice required.
13. Soil Nail walls.
Must be designed by experienced engineer, especially if
planned for permanent support.
1.4.4 WIDENING OF CUTS (2007)
1.4.4.1 Rock Cuts
a.
Before excavation is planned, a survey should be made of the engineering characteristics of the exposed
rock. Details of dip, joints, stratification, general competence and zones of weakness should be noted, along
with the depth and type of overburden.
b.
The new slope should be suited to the characteristics of the rock in which it is made so that minimum
maintenance is required in the future. For example, steeply dipping rock should be cut at the angle of dip.
This may include benches, or a slope varying with the weathering resistance of the various rock layers.
Drainage should be provided to reduce erosion and weathering. (See Article 1.2.2.1 for general design
procedure)
c.
Methods of treatment to stabilize the slope or protect the track from falling rocks may be considered as an
alternative to widening an unsafe rock cut, or applied in conjunction with excavation of the new slope.
d.
Blasting should be used only with approval of the Chief Engineer. The method of blasting chosen is most
important in reducing future rock scaling and other maintenance work required. Blasting programs should
be designed by qualified personnel. Control of flyrock is important. The use of presplitting for producing a
clean finished rock face should be considered.
1.4.4.2 Earth Cuts
a.
Cuts are widened in railway maintenance work to improve drainage, increase the stability of slopes, reduce
difficulties in maintaining track or clearing snow, or sometimes to obtain borrow materials. Whatever the
reason, it is important that cuts in either earth or rock be afforded good drainage to provide stable cut
backslopes.
b.
Article 1.2.2.3 provides general recommendations for use when choosing slopes that are safe for cuts in
various soils. The reduction of seepage pressures within the slope by means of horizontal drains may be
critical in cuts that have water-bearing soil layers. The selection of a safe cut slope may be derived from an
inspection of nearby stable cuts or natural slopes in similar soils. Existing conditions that need to be taken
into consideration include differences in the level of the groundwater table, vegetation, and other factors
that influence instability.
c.
In making the cut, even temporary over-steepening (or undercutting) of potentially unstable slopes should
be avoided, especially if the work is done during a wet season. Piles and lagging or crib walls can be used to
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-64
AREMA Manual for Railway Engineering
Roadbed
support the back slope of the ditch if there is restricted right-of-way width to cut an entire bank back to a
stable slope (and temporary stability of an undercut slope can be assured). Drainage through the supporting
structure should always be provided.
d.
In sidehill cuts, material excavated from the upper ditch or slope should not be placed on the downhill
shoulder if avoidable. This practice adds weight to the shoulder and can cause failure of the downhill slope.
Such excavated material should be wasted in an approved area.
e.
Vegetative root systems can help to bind a slope together while removing subsurface water that can also
improve slope stability. It should be preserved to the maximum extent possible on stable slopes. Vegetative
cover should be promptly reestablished on newly excavated cut slopes to minimize surface erosion and slope
stability. Surface drainage in a widened cut should be planned according to Article 1.2.4.2. A drainage
system which is balanced to handle both slope and roadbed drainage throughout the cut is essential.
Drainage of water from the top of the slope should be intercepted and brought around or down the slope
without causing surface erosion.
1.4.5 DRAINAGE AND EROSION CONTROL (2007)
1.4.5.1 Ditches and Drains
a.
b.
c.
Drainage is a very important function in providing for a stable track roadbed. Ditches of all types require
periodic maintenance to preserve their function. Excess vegetation, talus, and erosional deposits should be
removed to sustain positive ditch drainage. Excessive ditch scour/erosion must be corrected. Ditches not
properly maintained may form wetlands. Permitting, which takes time and can have associated ecominc
costes, is often required in advance of performing grading work to remove wetlands. Routine and timely
ditch cleaning can sustain stable track subgrade conditions while avoiding those costs associated with the
removal of wetland conditions.
Less evident but also important is the periodic maintenance of subdrainage systems. Pipes, manholes and/or
cleanouts should be periodically inspected and accumulations of sediment removed. It would be useful to
maintain records of locations, date of inspections, types of maintenance performed and conditions.
1
3
It is not generally realized that drilled-in horizontal drains also require maintenance. On an as-needed
basis, each pipe should be flushed or cleaned to remove materials that have accumulated within the pipes
and are blocking the flow of discharge waters. Failure to remove these materials can lead to a buildup of
seepage pressures within the track subgrade and embankment materials that can result in the
redevelopment of the instability conditions which the drains were originally installed to relieve.
4
1.4.5.2 Erosion Control
a.
Erosion of right-of-way slopes and ditches is caused by rainfall and frost, and affected by the steepness and
height of slopes. Resistance to erosion depends on the strength and cohesion of the slope or ditch soil and
the presence of protective cover such as vegetation.
b.
Erosion resulting in downstream siltation is unacceptable. Erosion control is required in association with all
new cut and fill slope construction. Additionally, periodic let down drains and ditches may be required on
long cut and fill slopes.
c.
Interceptor/diversion ditches should be constructed to prevent surface runoff water from running over and
down the sides of cut backslopes. Roadbed shoulders should be shaped to their original design configuration
to the extent possible to ensure uniform runoff.
d.
There are several methods of erosion control, including re-grading of slopes, flattening of slopes, using
variations of seeding and sodding, the use of layers of coarser materials, and vegetative matting.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-65
Roadway and Ballast
1.4.5.3 Seeding and Sodding
a.
Steps in seeding and mulching eroded slopes consist of filling gullies, placing topsoil where required,
applying fertilizer, seeding, mulching, and, if required, reseeding until vegetative cover is established. Local
state highway standards and specifications can be very helpful sources of information concerning
recommended seeding and sodding. Some railroads have their own standards/requirements for seeding,
fertilizer, seed mixtures and mulching. Suitable seed mixtures and fertilizers for particular locations can
also be recommended by agricultural bureaus. Grasses or ground covers can be used to control erosion.
However, ground covers can be killed by chemicals used to control vegetation along the right-of-way.
b.
The application of seed and fertilizer can be done on flat areas and moderate slopes with a seed drill, and on
steep slopes with a hydroseeder. A mulch spreader is used to apply straw tacked with asphalt. Although this
mechanical equipment is efficient and economical to use, small eroded areas can commonly be prepared and
treated by hand, with substantial benefits. Grass should be cut at least once to thicken the growth.
c.
Where active erosion of young growth may occur, vegetative matting can be used with seeding, giving good
protection against erosion. Seed and fertilizer is applied both under and over the matting, without mulch.
The matting should be applied according to the manufacturer’s specified procedures.
d.
Sod is costly and usually only used on areas where immediate vegetation coverage is required and for
aesthetic reasons. Where necessary to prevent slippage on slopes, sod should be pegged in place. Use of light
wire netting over the sod can improve stability of the sod layer.
1.4.5.4 Filter Layers
a.
Earth slopes can also be protected against erosion with a layer of coarser material. In such cases it is
essential to distribute surface runoff water and avoid concentrated flows of water from the top to the bottom
of the slope. Filling gullies with coarse material will not in itself prevent further erosion.
b.
A graded filter layer can be used as a maintenance method when water seepage from pervious layers in the
slope causes erosion. The filter layer is designed to keep the underlying soil in place while at the same time
carrying flow from both seepage and rainfall without eroding itself. The thickness of the layer depends on
the intensity of rainfall and on angle of repose of the filter material. A filter layer must be properly designed
and installed. Properly installed filter layers can prevent erosion under conditions that would cause seeding
or sodding to be an unsuccessful method of slope protection.
1.4.5.5 Filter Fabrics (see Chapter 1, Part 10)
a.
A geosynthetic layer or filter fabric can be installed to prevent erosion on earth slopes. These porous
membranes are available as woven fabric or as thin fibrous mats. In either form they are designed to be fine
enough to hold the slope soil material in place, but porous enough to allow passage of seepage water.
b.
The performance of filter fabrics is often superior to that of filter layers as they have a built-in filtering
capability which does not depend on field workmanship. Detailed installation procedures are available from
manufacturers. Generally, the slope to be protected must be uniform and gullies and holes filled. The fabric
is spread loosely on the slope, with proper overlapping and sheets pinned in place. A layer of random gravel
or crushed stone is placed immediately on top of the fabric to keep it in place, working from the base of slope
upward. This fabric must have sufficient puncture resistance and strength to avoid damage by either of the
techniques used for placement of gravel/stone or future erosion.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-66
AREMA Manual for Railway Engineering
Roadbed
1.4.6 METHODS OF OPENING SNOW BLOCKADES (2007)
1.4.6.1 General
a.
Keeping a railway line open in territory subject to heavy snow requires watchfulness, orderliness and
forethought. In the fall of the year all snow equipment and accessories should be tested and made ready for
use. A general program should be formulated for stationing snow-fighting equipment at vantage points,
outlining a general supervisory plan, and determining methods by which men are to be secured, protected
from hazards attending snow storms, fed and relieved.
b.
Where such reports are considered helpful, meteorological information should be made available for general
and division officers and local officers should be kept well informed of the progress of approaching storms.
c.
It is desirable to keep ahead of storms and not let the line become blocked. In some areas best results are
obtained when snow plows are started from terminals before the storm actually breaks and, in severe
storms, additional plows dispatched at such intervals as will preclude the formation of snow banks that
cannot be moved with plows. A follow-up locomotive to pull out the plow or its engine, or both, if they get
stalled or derailed, is good practice when conditions warrant. Prompt clearance of cuts before further snow
or wind storms is important. Secondary storms often cause the greatest problems.
d.
During severe storms, if there is difficulty in keeping the line open, consideration should be given to
reducing tonnage, double heading or the abandonment of trains and curtailment or complete stopping of
yard switching until the storm abates and the line is opened. Stalled trains and dead locomotives add much
expense, anxiety and hazard to the work of moving snow and delay the opening of blockades.
e.
No definite rule can be established for the use of flangers or plows. Much depends on the moisture content
of the snow, the formation of drifts, and on the available clear space for snow disposal.
1
1.4.6.2 On Line
a.
Flangers should be used for the removal of snow where the depth is less than 6 inches over the top of the
rail. Flanging of tracks is greatly expedited if the flanger is equipped with scoops for each direction, which
allow flangeways to be cleared in either direction without turning the flanger. The scoops must in all cases
be equipped with lowering and raising device operated from inside the car. A flanger may frequently be used
to good advantage by attaching it to the rear of a freight train and thus avoid using an extra train and crew.
b.
The wedge or snow plow placed on the pilot of the locomotive is useful for occasional light drifts of up to 2 or
3 feet over the top of the rail, if state laws permit such operation.
c.
The larger wedge or snow plow should be used for removing snow up to 6 or 8 feet deep which cannot be
removed by flangers or push plows on locomotive pilots. The effectiveness of these plows is greatly increased
if they are equipped with adjustable side wings, which can be used for widening the opening. These plows
should be equipped with a coupler on the front and rear to expedite the switching of cars off of siding or yard
tracks which must be cleared of snow. Means of communication by telephone or signals between crew and
plow operator expedite this operation.
d.
Great care must be exercised in the use of plows placed on the front of loaded ballast or gondola cars to
prevent the weight of the snow on the cutting edge of plow from riding on the rail and catching at frogs,
switches and crossing plank. This can be prevented by a narrow casting placed under the plow near the
cutting edge so as to ride on the rail and keep the plow up. Special consideration must be given the
designating and placing of this casting if self-guarded frogs are to be encountered. There are combined
flangers and plows so designed that this problem does not occur.
e.
Care must be taken when entering oblique snow drifts that do not allow the plows to strike the snow
squarely - as such conditions sometimes result in the plow turning over. The face of a drift should be
broken down or “faced” so that the plow will engage the snow and not ride atop the drift. If the plow has
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-67
3
4
Roadway and Ballast
been stuck and pulled back, the snow may have been compacted to such an extent that it should be broken
down before making another charge and possibly causing serious damage to the plow from impact with the
solid snow.
f.
Spreaders or spreader ditchers with a plow-shaped front make excellent snow movers. The spreader wings
can be used to good advantage to widen the cut after it is opened up. Many of these ditchers are equipped
with steel teeth (set under the front edge of the plow) which are very effective in cutting up ice which may
have formed between and over the rails.
g.
Ice cutter cars have been used with great effectiveness for loosening hard snow and ice which form in the
tracks, especially in yards, and on occasions in many miles of tracks. These cars are essentially box cars with
end lookout windows, and with compressed air equipment by means of which a lever may be moved to raise
and lower a plow or V-shaped steel plate, 1 inch thick, 6 inches wide, and about 4’- 9" long, placed below the
center of the car on edge and between the running rails. To this steel plate, 4 inches apart and extending 6
inches below its lower edge, are bolted tire-steel teeth with points inclined slightly forward. Extra teeth are
carried in the car. The cutter must, of course, be raised at turnouts and crossings.
h. Rotary snow plows are necessary for the quick removal of snow where the snowfall has filled deep cuts
which cannot be removed with push plow. Attempts to use them in shallow drifts not deep enough for
reasonably full contact of the wheel may cause the wheel to race under the light load and damage the
machinery.
i.
When operating flangers and plows over the line, the problem of keeping ice and snow out of guard rails,
frogs and switches is important, particularly in locations which are difficult for maintenance forces to get to
in severe storms. De-icing chemical can be used, but attention should be given to problems they can create
in electrified, automatic signal, or train-control territory.
1.4.6.3 In Yards and Terminals
a.
The method for removal of snow from yards and terminals depends upon the physical layout, the density of
traffic, and the amount of snow. If snow is not very deep, it is best not to remove it from the tracks, except to
make flangeways by hand shoveling, or with flangers if traffic will permit, and clean out of switches by hand
with shovels, brooms, or use of snow blowers or snow melters. Removal operations should avoid blowing
snow back over places already cleaned. The use of melters requires good drainage to carry away melted
snow as it may freeze and cause more trouble than the snow. Otherwise the heat must be great enough to
evaporate the water. Because of its potential to increase corrosion and electrical conductivity, salt should be
used sparingly. If possible, it should not be used in electrified, automatic signal or train-control districts and
should be used in other districts only during that portion of winter when snow melts during the daytime and
freezes at night. Salt may be used in some instances to prevent slippery conditions in the area of the switch
stand.
b.
In clearing yard tracks of heavier falls of snow, it is well first to pull cars off of four tracks; then run a plow
down one track and follow with a spreader, pushing the snow clear of adjacent tracks; then run the spreader
down the cleared tracks, repeating the operation until the snow is piled too high for further piling. The
clearing should then start on the other side of the pile and repeat. In some instances, where the yard is not
too wide and the snow not too heavy, the entire yard may be cleared with the spreader; thus picking up of
the snow is avoided. Where this cannot be done, the piles of snow must be left to melt or be mechanically
loaded onto cars.
c.
In cleaning snow off station platforms, where snowfall is light, hand methods are probably the most
economical. Use of brooms and snow shovels are effective. Snow should not be placed on tracks, as passing
trains may throw it onto platforms. Hand-operated power snow plows or farm tractor-type plows are useful
for platform cleaning. A supply of de-icer, salt, or sand should be on hand at stations to scatter over
platforms in sleeting and freezing weather.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-68
AREMA Manual for Railway Engineering
Roadbed
d.
At team yards snow can be pushed to the center or side of driveway with plows placed on trucks or tractors.
The snow may be left to melt or loaded onto trucks or cars by hand or machinery. Front-end loaders are
useful in this operation.
e.
Jet snow blowers on track equipment, revolving brooms attached to small tractors, and flangeway cleaners
attached to motor cars are other devices that have been found useful in cleaning crossings, yard leads, etc.
1
3
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-1-69
Roadway and Ballast
THIS PAGE INTENTIONALLY LEFT BLANK.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-1-70
AREMA Manual for Railway Engineering
1arema
Part 2
Ballast1
— 1997 —
FOREWORD
In the early days of the U.S. Railroad Industry, a variety of materials were used for track ballast to support the
track superstructure. Almost any ballast material which could be procured on line at a low unit cost was used
and considered satisfactory under the traffic loadings. As rail loadings and speed increased, track geometry
deterioration became a problem for the industry.
Track geometric deviations and rail wear were recognized as major maintenance problems in the early teens.
This resulted in the organization of a special joint committee sponsored by the AREMA and A.S.C.E. to study
stress in the railroad track structure under the chairmanship of Professor A. N. Talbot. The committee
immediately began their study of the track superstructure support, i.e. rails, cross ties, and fastenings. The
study produced the “U” value as a measurement of vertical track stiffness as defined in the AREMA Bulletin,
Volume 19, Number 205, March, 1918. The “U” value represents the stiffness of the track and involves
conditions of the ties, ballast and roadway. Study of “U” values in the superstructure indicated that the
influences of the track substructure (ballast and sub-ballast) were significant. Thus the need for better ballast
materials became more obvious.
Extensive ballast material tests were conducted by Rockwell Smith of the AREMA during the middle fifties and
sixties. The test results indicated that the ballast was an integral part of the track substructure and that
support in the roadbed section has a direct relationship to the quality of the ballast materials.
Today greater demands are placed on the track superstructure and substructure. Heavier wheel loads, higher
operating speeds and unit train consists demand better total performance of the track system. The
improvement of the performance of the substructure appears to be an economical approach to increasing the
strength of the track system.
More emphasis must be placed on the quality and type of ballast materials used in the substructure. Improved
geotechnical techniques and test methods together with a better understanding of soils have provided the
opportunity for ongoing tests to evaluate the quality and support characteristics of ballast materials.
1
References, Vol. 5, 1904, pp. 487, 502; Vol. 6, 1905, pp. 737, 745; Vol. 11, 1910, part 2, pp. 907, 930; Vol. 13, 1912, pp. 97, 949; Vol. 16,
1915, pp. 1007, 1159; Vol. 22, 1921, pp. 80, 958; Vol. 26, 1925, pp. 439, 1311; Vol. 31, 1930, pp. 768, 1740; Vol. 32, 1931, pp. 101, 731; Vol.
33, 1932, pp. 355, 798; Vol. 37, 1936, pp. 560, 575, 980, 987; Vol. 38, 1937, pp. 191, 621; Vol. 42, 1941, pp. 573, 831; Vol. 45, 1944, pp. 312,
637; Vol. 54, 1953, pp. 1092, 1385; Vol. 60, 1959, pp. 710, 1184; Vol. 63, 1962, pp. 576, 749; Vol. 65, 1964, pp. 504, 837; Vol. 67, 1966, pp.
539, 740; Vol. 76, 1975, p. 145; Vol. 78, 1977, p. 10: Vol. 87, 1986, p. 38; Vol. 89. 1988, pp. 40, 48, 58; Vol. 92, 1991, p. 35; Vol. 97, p. 20.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-2-1
1
3
Roadway and Ballast
During the past twenty year period, extensive ballast material tests have been conducted by the railroad
industry, the railway supply industry, universities and some governmental agencies. This includes the ballast
and roadway tests at TTCI (formerly FAST facility).
From the results of these multiple material tests and performance evaluations, improved information has been
obtained on the desirable physical and chemical properties of ballast materials which will provide performance
characteristics commensurate with current track loadings and cost effective maintenance requirements of the
track substructure.
The following Ballast Specification is the first general revision of the AREMA Ballast Specification in over forty
years. The Specification is the result of the aforementioned test data obtained in the laboratory, field testing,
and the actual performance evaluation of various ballast materials in track.
The efforts to produce a definitive ballast performance specification are not complete. A laboratory test to
simulate performance and evaluation of ballast materials in track has not been developed. However; ongoing
current ballast tests dedicated to the correlation of laboratory tests to field performance indicate that we may
be approaching our goal. The results of these testing programs could dictate further improvement of the Ballast
Specification in the future.
TABLE OF CONTENTS
Section/Article
Description
Page
2.0 Substructure Introduction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.0.1 Description (1991) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.0.2 Nomenclature (1991) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-2-4
1-2-4
1-2-4
2.1 Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.1.1 Track Substructure Design (1991) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-2-5
1-2-5
2.2 Scope (1991) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-2-9
2.3 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.3.1 Types of Materials (1991) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-2-9
1-2-9
2.4 Property Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.4.1 Physical Analysis (1991). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.4.2 Chemical Analysis (1988) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.4.3 Limiting Test Values (1997) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.4.4 Gradations (1988) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.4.5 Ballast Materials for Concrete Tie Track Installation (1988) . . . . . . . . . . . . . . . . . . . . . .
1-2-10
1-2-10
1-2-11
1-2-11
1-2-12
1-2-12
2.5 Production and Handling. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.5.1 General (1988) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-2-13
1-2-13
2.6 Loading (1988) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-2-13
2.7 Inspection (1988) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-2-14
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-2-2
AREMA Manual for Railway Engineering
Ballast
TABLE OF CONTENTS (CONT)
Section/Article
Description
Page
2.8 Sampling and Testing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.8.1 General (1988) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-2-14
1-2-14
2.9 Measurement and Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.9.1 General (1988) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-2-15
1-2-15
2.10 Maintenance Practices . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.10.1 Methods of Unloading and Distributing Ballast (1988) . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.10.2 Replacement of Ballast and In-Track Cleaning (1988) . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.10.3 Commentary (1988). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.10.4 Ballast Gradations (1988) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-2-15
1-2-15
1-2-15
1-2-15
1-2-18
2.11 Sub-ballast Specifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.11.1 General (1996) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.11.2 Design (1996) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.11.3 Testing (1996) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.11.4 Construction of Sub-ballast Section (1996) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.11.5 Production and Handling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.11.6 Inspection (1996) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.11.7 Measurement and Payment (1996) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-2-19
1-2-19
1-2-20
1-2-24
1-2-24
1-2-24
1-2-25
1-2-25
Commentary (1988) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-2-25
Summary (1988). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-2-26
3
LIST OF FIGURES
Figure
1-2-1
1-2-2
1-2-3
1-2-4
1-2-5
Description
Typical Section Track Substructure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Single Track, Superelevated . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Multiple Track, Tangent . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Multiple Track, Superelevated . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Example Using Table 1-2-4 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Page
1-2-6
1-2-6
1-2-7
1-2-7
1-2-23
LIST OF TABLES
Table
1-2-1
1-2-2
1-2-3
1-2-4
Description
Recommended Limiting Values of Testing for Ballast Material . . . . . . . . . . . . . . . . . . . . . . . . .
Recommended Ballast Gradations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Requirements for Filter Material (after USBR1963) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Sub-ballast Properties and Test Methods. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Page
1-2-12
1-2-13
1-2-23
1-2-24
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1
1-2-3
4
Roadway and Ballast
SECTION 2.0 SUBSTRUCTURE INTRODUCTION
2.0.1 DESCRIPTION (1991)
This part of these Specifications shall cover the design, materials, evaluation, production, construction and
maintenance and evaluation of those components of the track structure which are situated above the soils or
rock of the roadbed, or the wood, steel or concrete materials of the roadbed, installed for the purpose of
providing support to the rail-cross tie arrangement of a conventionally constructed track system.
2.0.2 NOMENCLATURE (1991)
Within these specifications, the following terms shall be defined as:
a.
Track Superstructure. The assembly of rail, cross ties, other track materials and special track materials
which are the components of a conventionally constructed track system.
b. Track Substructure. The strata of granular materials that are installed for the purpose of:
(1) Permitting drainage within the track substructure.
(2) Anchorage of the track superstructure in the three dimensions of space.
(3) Distribution of loads and transfer of the track superstructure loads to the underlying roadbed.
(4) Facilitating fine adjustment of track superstructure alignment, grade and cross level without system
reconstruction.
(5) Shielding the materials of the roadbed from climatic forces.
c.
Ballast. The upper stratum of the substructure upon which the superstructure is placed to a depth as
defined by the individual railway company standards.
d. Sub-ballast. A lower stratum of the substructure beneath the ballast section located upon the roadbed to
a depth as defined by the individual railway company standards.
e.
Roadbed. The stratum of soil or rock which is constructed in accordance with Part 1, Roadbed which
provides support for the track structure.
NOTE:
Except for new construction, the boundaries between the strata, as defined, may not be
distinct.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-2-4
AREMA Manual for Railway Engineering
Ballast
SECTION 2.1 DESIGN
2.1.1 TRACK SUBSTRUCTURE DESIGN (1991)
2.1.1.1 Description
This section of these specifications will discuss the cross sections of the track substructure components, the
ballast and sub-ballast sections. Single and multiple track construction will be addressed, as will track with
superelevation. The following figures are shown:
• Figure 1-2-1 Typical Section Track Substructure
• Figure 1-2-2 Single Track, Superelevated
• Figure 1-2-3 Multiple Track, Tangent
• Figure 1-2-4 Multiple Track, Superelevated
2.1.1.2 Variables of Design
The variables to be considered in establishing the dimensions of a track substructure are noted below and
shown on Figure 1-2-1. The variables of the track superstructure which effect the design of the substructure
are first noted.
1
2.1.1.2.1 For the Track Superstructure
• TRG = The Track Gage.
• TSE = The Superelevation of the Track.
• TTH = The Thickness of the Cross Tie.
3
• TLE = The Length of the Cross Tie.
• TWD = The Width of the Cross Tie.
• TSP = The Spacing of Cross Ties, center to center.
4
• The variables TRO, TTH, TLE, TWD and TSP are not shown on the figures.
2.1.1.2.2 For the Track Substructure
2.1.1.2.2.1 Ballast Section
• BDD = The Ballast Section Depth.
• BSW = The Ballast Section Shoulder Width.
• BSS = The Side Slope Run component of the Ballast Section in a unity rise to run ratio.
2.1.1.2.2.2 Sub-ballast Section
• SBD = The Sub-ballast Depth
• SBS = The Side Slope Run component of the Sub-ballast Section in a unity rise to run ratio.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-2-5
Roadway and Ballast
Figure 1-2-1. Typical Section Track Substructure
Figure 1-2-2. Single Track, Superelevated
2.1.1.2.2.3 Roadbed
• RSW = The Roadbed Shoulder Width.
• RBR = The Side Slope Run component of the Roadbed Section in a unity rise to run ratio.
• RBW = The Roadbed Berm Width.
2.1.1.3 Standards, Design Criteria and Regulation
Unless otherwise established by the Standards of Track Construction and as may be defined by individual
Railway standards, the Project Design Criteria, or a like document, the following paragraphs of this Part of this
Manual shall govern the proportioning of the track substructure components.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-2-6
AREMA Manual for Railway Engineering
Ballast
Figure 1-2-3. Multiple Track, Tangent
1
3
Figure 1-2-4. Multiple Track, Superelevated
2.1.1.4 Track Superstructure
a.
The Track Gage (TRG) shall be 56.50 inches, Standard Gage. The Superelevation of Track (TSE) shall be
determined in accordance with Chapter 5, Track, Part 3, Curves.
b. The Cross Tie Thickness (TTH), Length (TLE), Width (TWD) and the Spacing (TSP) shall be
proportioned in accordance with relationships show in Chapter 16, Economics of Railway Engineering
and Operations, Part 10, Construction and Maintenance Operations.
2.1.1.5 Track Substructure
2.1.1.5.1 Total Depth of Section (BDD + SBD)
The total depth of the track substructure section shall be determined in accordance with the relationships
shown in Chapter 16, Economics of Railway Engineering and Operations, Part 10, Construction and
Maintenance Operations. The sum of Ballast Section Depth (BDD) and Sub-ballast Depth (SBD) shall equal the
calculated total depth of track substructure section.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-2-7
4
Roadway and Ballast
2.1.1.5.2 Ballast Section
2.1.1.5.2.1 Ballast Section Depth (BDD)
a.
The ballast section is the upper portion of the track substructure section and is constructed of material
conforming to Article 2.3.1.
b. For single track construction, the measurement BDD is made under the Line Rail in tangent track, or
under inside rail in curved track, and is made with respect to the top of the sub-ballast at the center line
of track. On tangent multiple track construction, the measurement is made under that rail which is
toward the crown of the Sub-ballast Section. On curved multiple track construction, the measurement is
made under the rail to the inside of the curve.
c.
A value for BDD of a minimum of 12 inches is recommended for Standard Gage construction in main
track service or as defined by individual railway company standards.
2.1.1.5.2.2 Ballast Section Shoulder Width (BSW)
a.
The Ballast Section Shoulder Width is proportioned in accordance with Chapter 16, Economics of
Railway Engineering and Operations, Part 10, Construction and Maintenance Operations and is to
provide additional lateral strength to the track.
b. The measure is made from the end of the cross tie to the point of beginning of the Ballast Side Slope
(BSS), and is made in the plane of the top of the cross tie.
c.
A value for BSW of not less than 12 inches is recommended for Standard Gage construction of
continuous welded rail in main track service or as may be defined by individual railway company
standards.
2.1.1.5.2.3 Side Slope (BSS)
a.
The Side Slope run component of the Ballast Section is proportioned to provide confining pressure to
that part of the Ballast Section expected to transmit the vertical load from the bottom of the cross tie to
the top of the sub-ballast.
b. The BSS run component is measured in the plane of the top of the cross tie, and the rise component is
measured perpendicular to the run component.
c.
A BSS value of 2:1 is commonly used.
2.1.1.5.3 Sub-ballast
2.1.1.5.3.1 Sub-ballast Depth (SBD)
a.
The sub-ballast is the lower section of the track substructure and is constructed in accordance with the
specifications contained in Section 2.11, Sub-ballast Specifications.
b. The depth measured is made with respect to the top of the Roadbed.
c.
A value for SBD of 12 inches compacted is commonly used for Standard Gage construction in main track
service. A minimum value of 6 inches compacted is considered necessary to perform the separation of
layers and shielding of the roadbed from weather functions.
2.1.1.5.3.2 Side Slope (SBS)
a.
The Side Slope run component of the Sub-ballast Section is proportioned to provide drainage from the
top of the roadbed construction.
b. A value for SBS of not less than 24 or more than 40 is recommended. Sub-ballast materials having
relatively lower permeability rates may use relatively higher SBS values.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-2-8
AREMA Manual for Railway Engineering
Ballast
2.1.1.6 Roadbed
The Roadbed Shoulder Width (RSW), Side Slope Run component of the Roadbed (RBR), and Roadbed Berm
Width (RBW) shall be established in accordance with principals and recommendations contained in Part 1,
Roadbed.
SECTION 2.2 SCOPE (1991)
a.
These specifications cover the types, characteristics, property requirements and manufacture of mineral
aggregates for processed (prepared) ballast. Ideally processed ballast should be hard, dense, of an
angular particle structure providing sharp corners and cubical fragments and free of deleterious
materials. Ballast materials should provide high resistance to temperature changes, chemical attack,
have high electrical resistance, low absorption properties and be free of cementing characteristics.
Materials should have sufficient unit weight (measured in pounds per cubic foot) and have a limited
amount of flat and elongated particles.
b. The type or types and gradations of processed ballast materials as covered in these specifications and
testing requirements shall govern the acceptance or rejection of ballast materials by the Engineer, or as
directed by the individual railway company.
1
SECTION 2.3 MATERIALS
2.3.1 TYPES OF MATERIALS (1991)
a.
A variety of materials may be processed into railroad ballast. The following general classifications and
accompanying definitions list the most common materials. Detailed examination of individual materials
should be made to determine the specific mineralogical composition.
3
b. Granite is a plutonic rock having an even texture and consisting chiefly of feldspar and quartz.
Definitions: A plutonic rock is rock formed at considerable depth by chemical alteration. It is
characteristically medium to coarse grained, or granitoid texture.
c.
4
Traprock is any dark-colored fine grained non-granitic hypabyssal or extrusive rock.
Definitions: Hypabyssal – Pertaining to igneous intrusion or to the rock of that intrusion whose depth is
intermediate between that of plutonic and the surface.
d. Quartzite is a granoblastic metamorphic rock consisting mainly of quartz and formed by
recrystallization of sandstone or chert by either regional or thermal metamorphism. Quartzite may also
be a very hard but unmetamorphosed sandstone, consisting chiefly of quartz grains with secondary silica
that the rock breaks across or through the grains rather than around them.
Definitions: Granoblastic – type of texture is a nonschistose metamorphic rock upon which
recrystallization formed essentially equidimensional crystals with normally well sutured boundaries.
Chert-A hard, dense cryptocrystalline sedimentary rock consisting dominantly of interlocking crystals of
quartz.
e.
Carbonate rocks are sedimentary rocks consisting primarily of carbonate materials such as limestone
and dolomite.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-2-9
Roadway and Ballast
f.
Slags are materials formed during the metal making process by the fusion of fluxstones, coke and other
metallic particles and are generally of two types; iron blast furnace slag and steel furnace slag. Iron blast
furnace slag is produced during the blast furnace operation and is essentially a composition of silicates
and alumino silicates of lime and other bases. Steel furnace slag is a by-product of the open hearth,
electric or oxygen steel furnace and is composed primarily of oxides and silicates.
SECTION 2.4 PROPERTY REQUIREMENTS
2.4.1 PHYSICAL ANALYSIS (1991)
The methods of sampling and testing as defined by this specification are those in effect April 1985 and may be
revised or altered by the individual railway company.
2.4.1.1 Method of Sampling
Field samples shall be secured in accordance with the current ASTM Methods of Sampling, designation D 75.
Test samples shall be reduced from field samples by the means of ASTM C 702.
2.4.1.2 Sieve Analysis
Sieve analysis shall be made in accordance with ASTM Method of Test, designation C 136.
2.4.1.3 Material Finer Than No. 200 Sieve
Material finer than the No. 200 sieve shall be determined in accordance with the ASTM Method of Test,
designation C 117.
2.4.1.4 Bulk Specific Gravity and Absorption
The bulk specific gravity and percentage of absorption shall be determined in accordance with the ASTM
Method of Test, designation C 127.
2.4.1.5 Percentage of Clay Lumps and Friable Particles
The percentage of clay lumps and friable particles shall be determined in accordance with the ASTM Method of
Test, designation C 142.
2.4.1.6 Resistance to Degradation
The resistance to degradation shall be determined in accordance with the ASTM Method of Test, designation C
131 or C 535 using the grading as specified in Note # 1, Table 1-2-1. Materials having gradations containing
particles retained on the 1 inch sieve shall be tested by ASTM C 535. Materials having gradations with 100%
passing the 1 inch sieve shall be tested by ASTM C 131.
2.4.1.7 Sodium Sulfate Soundness
Sodium Sulfate Soundness tests shall be made in accordance with the ASTM Method of Test, designation C 88.
2.4.1.8 Unit Weight
The weight per cubic foot shall be determined in accordance with the ASTM Method of Test, designation C 29.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-2-10
AREMA Manual for Railway Engineering
Ballast
2.4.1.9 Percent of Flat and/or Elongated Particles
The percent of flat or elongated particles shall be determined in accordance with ASTM Standard Test Method,
designated D4791. The dimension ratio used in this test method shall be 1:3.
2.4.2 CHEMICAL ANALYSIS (1988)
a.
No specific chemical analysis is considered essential for the evaluation of granite, traprocks or quartzite
type materials provided that the materials are properly defined by applicable methods. For carbonate
materials, dolomitic limestones are defined as those materials which have a magnesium carbonate
(MgCo3) content of 28% to 36%. Those carbonate materials indicating magnesium carbonate values
above 36% shall be defined as dolomites and carbonate materials indicating magnesium carbonate values
below 28% shall be defined as limestones.
b. The magnesium carbonate (MgCo3) content of carbonate materials shall be tested and defined in
accordance with ASTM C 25.
c.
Standard Methods of Chemical Analysis of Limestone, Quick Lime and Hydrated Lime, or other test
methods as may be approved and directed by the Engineer.
d. Steel furnace slags consist essentially of calcium silicates and ferrites combined with fused oxides of iron,
aluminum, manganese, calcium and magnesium.
e.
Steel furnace slags having a content of more than 45% calcium oxide and/or a combined composition of
more than 30% of the oxides of iron and aluminum should not be used.
f.
Iron blast furnace slags consist essentially of silicates and aluminosilicates of calcium and other bases.
g.
Iron blast furnace slags having a content of more than 45% of the oxides of calcium or a combined
composition of more than 17% of the oxides of iron and aluminum should not be used.
1
3
2.4.3 LIMITING TEST VALUES (1997)
Table 1-2-1 outlines the limiting values of testing as may be defined by the designated test specifications. The
values for unit weight and bulk specific gravity are minimum values while the remainder are maximum
values.
Table 1-2-1. Recommended Limiting Values of Testing for Ballast Material
4
Ballast Material
Property
Granite Traprock Quartzite Limestone
Blast
Dolomitic
Furnace
Limestone
Slag
Steel
Furnace
Slag
ASTM Test
Percent Material
Passing No. 200
Sieve
1.0%
1.0%
1.0%
1.0%
1.0%
1.0%
1.0%
C 117
Bulk Specific
Gravity
(See Note 2)
2.60
2.60
2.60
2.60
2.65
2.30
2.90
C 127
Absorption Percent
1.0
1.0
1.0
2.0
2.0
5.0
2.0
C 127
0.5%
0.5%
0.5%
0.5%
0.5%
0.5%
0.5%
C 142
Clay Lumps and
Friable Particles
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-2-11
Roadway and Ballast
Table 1-2-1. Recommended Limiting Values of Testing for Ballast Material
Ballast Material
Property
Granite Traprock Quartzite Limestone
Blast
Dolomitic
Furnace
Limestone
Slag
Steel
Furnace
Slag
ASTM Test
Degradation
35%
25%
30%
30%
30%
40%
30%
See Note 1
Soundness
(Sodium Sulfate)
5 Cycles
5.0%
5.0%
5.0%
5.0%
5.0%
5.0%
5.0%
C 88
Flat and/or
Elongated Particles
5.0%
5.0%
5.0%
5.0%
5.0%
5.0%
5.0%
D 4791
Note 1: Materials having gradations containing particles retained on the 1 inch sieve shall be tested by ASTM
C 535. Materials having gradations with 100% passing the 1 inch sieve shall be tested by ASTM C 131.
Use grading most representative of ballast material gradation.
Note 2: The limit for bulk specific gravity is a minimum value. Limits for the remainder of the tests are
maximum values.
2.4.4 GRADATIONS (1988)
Table 1-2-2 outlines the recommended gradations to which the materials are to be processed for use as track
and yard ballast. The grading of the processed ballast shall be determined with laboratory sieves having square
openings conforming to ASTM specification E 11.
2.4.5 BALLAST MATERIALS FOR CONCRETE TIE TRACK INSTALLATION (1988)
The ballast materials as defined by this specification include the applicable test requirements for ballast
materials for the purpose of providing support to the rail-cross tie arrangement of a concrete tie track system
except that carbonate materials and slags as defined in Article 2.3.1 and gradation No. 57 as defined in
Article 2.4.4 shall be excluded.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-2-12
AREMA Manual for Railway Engineering
Ballast
Table 1-2-2. Recommended Ballast Gradations
Size No.
(See Note 1)
Nominal Size
Square
Opening
Percent Passing
3
2½
2
1½
24
2½ - ¾ 
100
90-100
25-60
25
2½  - d
100
80-100 60-85
50-70
3
2 - 1
–
100
4A
2 - ¾ 
–
100
–
–
100
4
1½  -
¾
1
¾
0-10
½
d
No.4
No. 8
0-5
–
–
–
25-50
–
5-20
0-10
0-3
–
95-100 35-70
0-15
–
0-5
–
–
–
90-100 60-90
10-35
0-10
–
0-3
–
–
90-100 20-55
0-15
–
0-5
–
–
5
1 - d
–
–
–
100
90-100 40-75
15-35
0-15
0-5
–
57
1 - No. 4
–
–
–
100
95-100
25-60
–
0-10
0-5
–
Note 1: Gradation Numbers 24, 25, 3, 4A and 4 are main line ballast materials. Gradation Numbers 5 and 57
are yard ballast materials.
SECTION 2.5 PRODUCTION AND HANDLING
1
2.5.1 GENERAL (1988)
a.
The aggregate production facility shall be of such a design to permit production and or blending without
excessive working of the materials and the facility must be approved by the purchaser. The capacity of
the production facility should be adequate to efficiently produce the anticipated daily loadings providing
sufficient stockpiles to facilitate loadings without any delays.
b. Blending, stockpiling and other production and handling operations shall be managed by the producer to
minimize segregation of the finished product. Stockpiling operations shall minimize as practical the
breakage or excessive fall in stockpiling operations and the movement of wheeled or tracked machines
over stockpiled materials shall be limited.
c.
Processed ballast shall be washed and/or rescreened as necessary to remove fine particle contamination
as defined by the specification or as directed by the individual railway company prior to stockpiling in
operations using stockpiles or immediately prior to loading operations.
SECTION 2.6 LOADING (1988)
a.
The manufacturer shall arrange the required supply of railcars, unless the purchase arrangement
provides otherwise. The manufacturer shall assure the fitness of the cars for loading of the prepared
materials, arranging to clean cars of deleterious materials, plug leaks and other like operations, as
necessary.
b. Unless otherwise specified, rail cars shall be ballast cars furnished by the purchaser or hopper-type, or as
designated by the Engineer.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-2-13
3
4
Roadway and Ballast
SECTION 2.7 INSPECTION (1988)
a.
The railway company, or its representatives, reserve the right to visit the producers facility during usual
business hours unscheduled for the following purposes:
(1) Observe sampling and testing procedures to assure compliance with the requirements of these
specifications.
(2) Obtain representative samples of the prepared material being produced and shipped.
(3) Review plant inspection, methods, quality control procedures, equipment and examine test results of
current and previous tests.
b. The manufacturer shall provide the inspector with such assistance, materials, and laboratory testing
equipment as necessary to perform on production site gradation and percent passing No. 200 Mesh Sieve
analysis. Performance of these tests at the time of an unscheduled inspection visit is the right, but not
the duty, of the inspector.
SECTION 2.8 SAMPLING AND TESTING
2.8.1 GENERAL (1988)
a.
The quality of a material to be used for ballast shall be determined prior to its acceptance by the
purchaser. A series of tests as specified herein shall be made at a testing laboratory approved by the
purchaser to establish the characteristics of the materials being tested.
b. Once a source has been accepted to supply ballast material, periodic quality control samples shall be
taken to insure continued compliance with the specification. A representative sample of prepared ballast
shall be taken for gradation from each 1000 tons of ballast being loaded for shipment. This sample shall
be taken in accordance with ASTM D 75, and in the quantities as listed within that standard. A
gradation report shall be prepared on each sample containing the following information: Source
identification, date, sample number, shipment or car number, and the sieve analysis. The gradation
specification shall appear on the test form.
c.
In the event any two individual samples fail to meet the gradation requirement, immediate corrective
action shall be taken to restore the production process to acceptable quality. The purchaser shall be
advised in writing of the corrective action being taken. In the event of repeated failures, i.e. two or more
samples failing in two successive shipments, the purchaser reserves the right to reject the shipment.
d. A full range of laboratory testing, as defined by this specification, shall be performed at least two times a
year or as directed by the Engineer, to insure the quality of the material being produced. If the supplier
changes the location of the source or encounters changes within the supply source, laboratory testing
should be performed on the new material to ensure compliance with specifications.
e.
Prior to installation, the supplier shall provide the Engineer with certified results of ballast quality and
gradation as conducted by a testing laboratory accepted by the Engineer. The supplier shall receive
approval of the Engineer for the Testing Laboratory prior to performing the aforementioned tests.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-2-14
AREMA Manual for Railway Engineering
Ballast
SECTION 2.9 MEASUREMENT AND PAYMENT
2.9.1 GENERAL (1988)
a.
Ballast shall be measured on a per ton basis and payment shall be made on the number of tons of
acceptable materials furnished. No allowance will be made for moisture content of ballast materials
loaded by any acceptable method. Weight tickets or records shall be maintained for a period of not less
than six months for reference.
b. The number of tons shall be determined by one of the following methods and shall be approved by the
purchaser:
(1) Certified scale weights as determined by track scales (static or in motion weighing) truck scales or
belt scales which load directly into the railcar.
(2) Average weight agreements as mutually agreed upon by the purchaser and producer. The average
net weight for each type and series of railcars shall be determined by the purchaser and producer to
establish the average weight agreement per car. The average weight in the specified or type of cars
shall be checked quarterly by the purchaser or as designated by the Engineer. The average weight
will be calculated on lots of not less than ten (10) cars. The purchaser shall advise the producer if
there is any variance in the average weight of the cars selected. The purchaser and the supplier will
jointly make any changes in the loading methods to insure compliance with the weight agreement.
SECTION 2.10 MAINTENANCE PRACTICES
1
2.10.1 METHODS OF UNLOADING AND DISTRIBUTING BALLAST (1988)
Ballast shall be unloaded and distributed as outlined in the Chapter 16, Economics of Railway Engineering and
Operations, Part 10, Construction and Maintenance Operations or as defined by individual railway company
standards.
3
2.10.2 REPLACEMENT OF BALLAST AND IN-TRACK CLEANING (1988)
Replacement of ballast and cleaning shall be performed in accordance with the Chapter 16, Economics of
Railway Engineering and Operations, Part 10, Construction and Maintenance Operations or as defined by
individual railway company standards.
4
2.10.3 COMMENTARY (1988)
a.
Ballast is a selected crushed and graded aggregate material which is placed upon the railroad roadbed for
the purpose of providing drainage, stability, flexibility, uniform support for the rail and ties and
distribution of the track loadings to the subgrade and facilitating maintenance. There are distinct
differences in the mineral composition of the various aggregate materials used for roadway ballast
applications and the respective in track performance of those materials. Likewise, many variations exist
in the mineral properties of aggregate materials within the same general nomenclature of the aggregates
known as granites, traprocks, quartzites, dolomites, and limestones. One particular aggregate material
may possess most of the desirable characteristics for a good ballast material while a deposit of apparently
similar material located in the same general geographical area will not meet the applicable specification
requirements for railroad ballast.
b. Thus, when selecting ballast materials it is necessary to define the type of material and the physical and
chemical properties which can be measured in the laboratory by specific test methods. It is also most
important to consider the field performance and behavioral characteristics of the ballast material in the
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-2-15
Roadway and Ballast
roadbed section. Some of the properties which affect the field performance of ballast materials can be
related to the crushing characteristics, hardness, durability, weight and other physical and chemical
properties which are defined in the specification.
c.
High standards must be established for railroad ballast to provide a quality track structure. Likewise,
ballast required for concrete tie installations must exhibit some different behavioral and performance
characteristics than those ballast materials which will provide satisfactory field performance for wood tie
installations. Ballast is an integral part of the roadbed structure. The ballast section must react to track
loadings in combination with the superstructure and sub-ballast to provide supporting strength for the
track and roadbed commensurate with specific railroad loadings and operating requirements.
d. To provide track stability, the ballast must perform several well defined functions. The ballast must
sustain and transmit static and dynamic loads in three directions (transverse, vertical and longitudinal)
and distribute those loads uniformly over the subgrade. A prime function of the ballast is to drain the
track system. The ballast must also perform a maintenance function to provide proper track alignment,
cross level, and grade.
e.
The most commonly used ballast materials today on the U.S. railroads are granites, traprocks,
quartzites, limestones, dolomites and slags, which are defined in the specification. The specification does
not limit the use of any rock type which can be processed into ballast when the material is properly
defined and tested in accordance with the specifications and is approved by the engineer or purchaser. It
is necessary; however, to warn the engineer that materials which tend to create fines will fill the voids
between the particles and could inhibit drainage. Some of the powdery fines of carbonate materials have
a tendency to cement together and a clogging action could occur.
f.
The preferred ballast materials would be a clean and graded crushed stone aggregate and/or processed
slag with a hard, dense, angular particle structure providing sharp corners and cubicle fragments with a
minimum of flat and elongated pieces. These qualities will provide for proper drainage of the ballast
section. The angular material will provide interlocking qualities which will grip the ties more firmly to
prevent movement. Flat and elongated particles in excess of the maximum as specified in the
specification could restrict proper consolidation of the ballast section. The ballast must have high wear
and abrasive qualities to withstand the impact of traffic loads without excessive degradation. The
stability of the ballast section is directly related to the internal shearing strength of the assembly of
ballast particles. The material must possess sufficient unit weight (measured in pounds per cubic foot) as
set out in the specification to provide a stable ballast section. The ballast must also provide high
resistance to temperature changes, chemical attack, exhibit a high electrical resistance and low
absorption properties. A ballast material should be free of cementing properties. Deterioration of the
ballast particles should not induce cementing together of the degraded particles. Cementing reduces
drainage capabilities, reduces resiliency, and provides undesirable distribution of track loads and in most
instances results in permanent track and roadbed deformations. Cementing also interferes with track
maintenance. Basically, all ballast materials are placed and tamped in the ballast section in accordance
with similar maintenance practices. The materials are then subjected to basic loading patterns, however,
there are several factors which will materially affect the in track performance and stability of ballast
materials.
g.
Drainage is the first and prime consideration in the roadbed maintenance and performance of a ballast
material. Individual ballast particles must provide a free-draining and clean section for proper drainage
of surface water to parallel side ditches or runoff areas. Excessive moisture in subgrades and ballast
sections are a primary source of track roadway problems. Side ditches should be free-draining and
prevent standing water which could saturate the roadway subgrade. A wet ballast section reduces the
shearing strength of the assembly of ballast particles and dirty, moist ballast sections will support the
growth of vegetation which reduces the drainage capability of the ballast material. Drainage is a most
important factor in contractive and expansive subgrade soil conditions which are prone to cause
pumping conditions in the roadbed section.
h. Track loading patterns and traffic density, weight of the rail section, grades, the cross section of the
ballast section, the sub-ballast and the roadbed interaction together with climatic conditions are major
considerations in the performance of ballast materials. A well compacted subgrade and sub-ballast
section will provide stable and uniform areas for the distribution of the track loads throughout the
ballast section.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-2-16
AREMA Manual for Railway Engineering
Ballast
i.
j.
The quality tests as specified in the specification identify several physical properties and characteristics
which are desirable for ballast materials. None of the tests considered on an individual basis, however,
are indicative of the field performance one might expect from the material.
For instance, the test for friable materials (ASTM C 142) identifies materials which are soft and poorly
bonded which will result in separate particles being detached from the mass. The test can identify
materials which will deteriorate rapidly. Clay in the ballast material is determined by the same test
method. Excessive clay can restrict drainage and will promote the growth of vegetation in the ballast
section.
k. The Sodium Sulfate Soundness Test (ASTM C 88) is conducted with the test sample saturated with a
solution of sodium sulfate. This test will appraise the soundness of the aggregate. Materials which do not
meet applicable test limits can be expected to deteriorate rapidly from weathering and freezing and
thawing. There is some preference for the Magnesium Sulfate Soundness Test, but there is insufficient
historical data available for comparison to the Sodium Sulfate Soundness Test which has been used for
many years.
l.
The concentration of fine material below the 200 sieve in the ballast material is determined by the
ASTM test method C 117. Excessive fines are produced in some types of crushing and processing
operations and could restrict drainage and foul the ballast section.
m. The test for flat or elongated particles is determined by ASTM method D 4791 using one of the three
dimension ratios. Track stability can be enhanced by eliminating flat or elongated material in excess of
the specification by defining a flat or elongated particle as one that has a width to thickness or length to
width ratio greater than three.
n. Specific gravity and absorption are measured by test method ASTM C 127. Specific gravity in the
English measurement system is related to weight and the metric system relates to density. The higher
the specific gravity, the heavier the material. A stable ballast material should possess the weight limits as
shown in the specification (Test Method ASTM C 29) to provide suitable weight and mass to provide
support and alignment to the track structure. Absorption is the measurement of the ability of the
material to absorb water. Excessive absorption can result in rapid deterioration during wetting and
drying and freezing and thawing cycles.
o.
The Los Angeles Abrasion Test is a factor in determining the wear characteristics of the ballast material.
As directed in the specification, the larger ballast gradations should be tested in accordance with ASTM
C 535 while ASTM C 131 is the wear test for smaller gradations. The Los Angeles Abrasion Test relates
to the abrasive wear resistance of the aggregate. Excessive abrasion loss of an aggregate will result in
reduction of particle size, fouling of the ballast section, reduction of drainage and loss of supporting
strength of the ballast section. The Los Angeles Abrasion Test can, however, produce laboratory test
results which are not indicative of the field performance of ballast materials. Limestones are primarily
calcium carbonate materials with small traces of other minerals. Calcium carbonates are a basic
ingredient in the manufacture of cements and degraded carbonate fines have an experience of cementing
together in the track structure when degraded particles are produced by track loads imposed upon the
track structure and ballast section.
p. The performance of granites, traprocks and quartzites differ from that of the limestones when subjected
to the same wear and abrasive loading conditions. Granites and traprocks can be coarse-to-fine grained
materials and degradation of these materials produces granular fines which do not induce cementing in
the roadway.
q. The ongoing ballast and roadway tests at TTCI (formerly FAST facility) have also confirmed that the Los
Angeles Abrasion Laboratory Test is not indicative of the field performance of ballast materials.
r.
We must bring to the attention of the engineer that considerable variables exist with many laboratory
physical testing methods and procedures and the Los Angeles test is no exception. Not only do variables
exist between individual tests, but between testing laboratories as well. Studies conducted by ASTM
Committee No. C9 (the committee responsible for the ASTM abrasion test methods and procedures)
indicated that for nominal ¾ inch maximum coarse aggregate with percentages of wear in the range of
10% to 45%, the multi-laboratory coefficient of variation is 4.5%. Therefore, the results of two properly
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-2-17
1
3
4
Roadway and Ballast
conducted ASTM Los Angeles Abrasion tests from two different laboratories on the same sample of the
same coarse aggregate could vary as much as 12.7%. ASTM C 131 defines this variable as a part of the
Los Angeles Abrasion Test.
s.
Likewise, the Sodium Sulfate Soundness Test is not at all precise, particularly in testing limestones. The
test results may be affected significantly if the test solution has previously been used to test other
carbonate rock samples. The test does provide the opportunity to develop relationships between various
materials and will most certainly indicate the presence of shale in carbonate materials.
t.
The variables in the aforementioned tests and the lack of correlation between the laboratory tests and
field performance of ballast material are the prime reasons for ongoing research to develop laboratory
tests which are indicative of field performance of ballast materials. The AREMA Ballast Committee is
actively pursuing current ballast testing programs in conjunction with the railroads, the A.A.R., T.S.C.,
FAST and the railroad supply industry to develop laboratory tests to predict field performance.
2.10.4 BALLAST GRADATIONS (1988)
a.
The gradation of a ballast material is a prime consideration for the in track performance of ballast
materials. The gradation must provide the means to develop the compactive or density requirements for
the ballast section and provide necessary void space to allow proper run off of ground water.
b. Ballast gradations should be graded uniformly from the top limit to the lower limit to provide proper
density, uniform support, elasticity and to reduce deformation of the ballast section from repeated track
loadings.
c.
The AREMA mainline ballasts are graded in three sizes from 2½ inches to ¾ inches, 2 inches to 1 inch
and 1-1/2 inches to 3₀4 inch; however, two additional gradations No. 25 and No. 4-A have been added to
the specification to meet requirements of the railroads.
d. Rail yards and some industrial track gradations are generally graded from 1 inch to d inch, (AREMA No.
5 gradation, Table 1-2-2), to provide improved walkway and safety conditions along the track. The finer
gradations for yard applications do not restrict track drainage as the construction practices for yard
facilities provide quick run off of ground water through the means of under track and yard drainage
systems. A consideration in the selection of the proper ballast gradation is the selection of a ballast that
will limit the amount of material removed from the track section during undercutting operations. Most
undercutting operations remove all of the material below the ¾ inch size. Limiting the amount of the
inch material in the original gradation will reduce the amount of ballast removed when undercutting
operations are used to clean and restore the track ballast section. The larger ballast gradations being
used on the railroads today do not increase the cost of tamping. Mechanization has eliminated most of
the necessity for manual labor in the roadway maintenance practices.
e.
The type of ballast selected for use under concrete ties is a direct function of the track performance with
the concrete tie. Extensive field tests of several designs of concrete ties have been installed on various
types of ballast materials. The tests concluded that the loading characteristics of the concrete tie are
quite different from the loadings imposed on wood ties on the same ballast cross section. Concrete ties
which are heavier and less flexible to absorb impact loadings, transmit greater loads to the ballast
section and thus create higher crushing loads on the individual ballast particles. Consequently, the
selection of ballast materials for concrete ties must be very restrictive to provide satisfactory track
performance. Ballast for concrete tie installations must be limited to either crushed granites, traprocks
or quartzites.
f.
A very important consideration is the selection of the proper gradation of the ballast material for
concrete ties. The early concrete tie installations were placed on ballast materials graded to the AREMA
No. 4 (1½ inches- ¾ inch), resulting in good in track performance, although other ballast materials
graded smaller than the AREMA No. 4, Table 1-2-2 gradation did not provide satisfactory support and
restraint qualities. Concrete ties placed on ballast gradations smaller than AREMA No. 4 resulted in
suspect performance in the first phase of the concrete tie tests conducted at the A.A.R. FAST test facility.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-2-18
AREMA Manual for Railway Engineering
Ballast
g.
Two examples of very good performance of the AREMA No. 4 gradation is the granite ballast used for the
concrete tie roadway on the Florida East Coast and the granite ballast used in the concrete tie test
installed by the Santa Fe several years ago near Streator, Illinois.
h. Concrete ties placed on gradations conforming to AREMA No. 3 (2 inches-1 inch) and AREMA No. 24
(2½ inches- ¾ inch have also exhibited good support qualities and performance characteristics during
the second phase roadway tests at TTCI (formerly FAST facility).
i.
Likewise, ballast graded larger than the AREMA No. 24 gradation has performed well on the northeast
corridor concrete tie installations.
SECTION 2.11 SUB-BALLAST SPECIFICATIONS
2.11.1 GENERAL (1996)
a.
This part of the specifications cover design, materials and construction of the sub-ballast section laying
between the track ballast and the subgrade as defined in Article 2.0.2d, and composed of a section of
smaller dense or well graded granular material. Sub-ballast material is primarily used for the
construction of new tracks.
b. For over 50 years railroad construction and maintenance practices have utilized a roadway structure for
heavy traffic composed of a ballast section approximately 24 inches in depth that included both track
ballast and sub-ballast. Experience has indicated a substantial portion of this ballast depth may be
successfully composed of a compacted sub-ballast material also serving as a buffer or filter to prevent
subgrade material from penetrating the sub-ballast section while at the same time permitting water
from whatever source to escape from the area of the subgrade surface. Discussion of the functions of the
sub-ballast is provided in the commentary. The engineer must follow established engineering principles
for the design, selection of materials and construction of the sub-ballast section of the track
substructure.
1
3
2.11.2 DESIGN (1996)
a.
The railroad substructure must be designed so that the subgrade, sub-ballast and track ballast provide
uniform support and distribution of superstructure loadings. The subgrade strength will dictate the
combined depth of ballast and sub-ballast materials.
b. The following conditions should be considered in the design of the sub-ballast section:
(1) Engineering properties of subgrade soil.
(2) Support capability of subgrade.
(3) Unit load applied to the ballast at the base of tie.
(4) Total thickness (track ballast + sub-ballast).
(5) Sub-ballast properties.
(6) Gradation of sub-ballast.
(7) Installation and compaction.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-2-19
4
Roadway and Ballast
2.11.2.1 Subgrade Soils
a.
The minimum data needed to evaluate the subgrade soils should be classification (which requires
Atterberg limits and gradation as appropriate) and strength (lowest expected). The depths and
thicknesses of the lower strength layers to a depth of at least 2 feet should be examined. The following
current ASTM test designations may be used in developing the necessary data where appropriate for
design:
Plastic Limit and Plasticity Index . . . . . . . . D4318
Grain Size Analysis . . . . . . . . . . . . . . . . . . . . D421 (Sample Preparation)
D422 (Test Procedure)
Compaction Test . . . . . . . . . . . . . . . . . . . . . . D698
D1557
Unconfined Compression Test . . . . . . . . . . . D2166
b. Where cohesive soils exist in the subgrade, resulting of an unconfined compression test of the compacted
cohesive material (saturated) will give a cohesion or shear strength for use in design. It may not be
necessary to develop shear values from tests for some non-cohesive soils but where necessary standard
tests may be performed. In absence of testing, caution is advised in applying the AREMA allowable
bearing pressure of 20 psi for design from Chapter 16, Economics of Railway Engineering and
Operations.
c.
The level of stress in the subgrade should not exceed an allowable bearing pressure that includes a safety
factor. A minimum factor safety of a least 2 and as much as 5 or more should be provided to prevent
bearing capacity failure or undue creep under the loaded area. When subgrade support is marginal
and/or where the liquid limit of the subgrade soil exceeds a value of 30 or the plasticity index exceeds 12,
special attention should be given to that soil. A change of subgrade soil or stabilization of the subgrade
material may be considered to obtain a more reliable support for the sub-ballast.
2.11.2.2 Loads Supported by Track Ballast
a.
Many variables affect the stress placed by the wheel load on the tie and the load is distributed over many
ties.
b. Example calculation follows:
(1) Problem: Develop ballast depth below base of tie for a proposed track supporting a 36 inches
diameter wheel (36,000-lb wheel load) at speed of 55 mph, 136-lb rail and 798–6 oak ties
@ 21 inches spacing. Assume a saturated subgrade support value of 18 psi includes a safety factor
of 2.
(2) The AREMA impact factor for track:
33V/100D
where:
V = velocity in mile per hour
D = diameter of the wheel
Impact Factor = (33  55) / (100  36) = 1,815/3,600 = 0.50.
(3) Distribution Factor: For 21 inches tie spacing 47% of axle load is assumed applicable to each tie
either side of the applied load. (Arrived at by using Talbot distribution utilizing a track modulus of
3,500 lb per inch per inch).
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-2-20
AREMA Manual for Railway Engineering
Ballast
(4) AREMA formula for average ballast pressure (psi) at tie face:
ABP = [2P (1 + IF/100) (DF/100)]/A
where:
P=
IF =
DF =
A=
36,000 (Wheel loading in lb)
50 (Impact factor in percent)
47 (Distribution factor in percent)
918 Area of face of 7 9 8 -6ties in sq in.
ABP = Average ballast pressure at base of tie
ABP = [2  3,600 (1 + 50/100) (47/100)]/918 = 55 psi
2.11.2.3 Depth of Ballast Plus Sub-ballast
a.
The distribution of loads to depth is approximately the same regardless of the granular material.
Therefore the combined depth of sub-ballast and ballast is calculated as a single unit to develop the
pressure on the subgrade. Talbot developed an empirical formula for vertical pressure exerted by the
ballast under the tie at its intercept with the rail at a depth below the bottom surface of the tie.
pc = 16.8 pa/h1.25
1
where:
pc = bearing pressure on subgrade including safety factor
pa = uniformly distributed pressure over tie face
h = depth below face in inches
b. If the tie pressure pa in pounds per square inch and the bearing capacity of the subgrade pc are known,
the minimum depth of ballast in inches required to produce a stable structure is:
3
h = (16.8 pa/pc)4/5
c.
Assuming an allowable subgrade pressure of 18 psi (a safety factor of 2) and using the unit tie face
pressure developed above of 55 psi, solve for ballast depth:
h = (16.855/18)4/5 = (924.0/18.0)4/5 = 23.4 inches
d. The capacity of the subgrade including the safety factor must always be equal to or greater than the load
placed upon it.
2.11.2.4 Location of Ballast – Sub-ballast Interface
The sub-ballast layer depends upon its state of compaction to be most effective. The present specified depth of
12 inches of track ballast below the tie precludes the maintenance tamping from penetrating and damaging the
sub-ballast layer. The force calculated by the above formula for a point 12 inches beneath the tie is 41.4 psi, a
force that will reduce tendency of larger ballast particles to penetrate the sub-ballast. The remaining depth of
required ballast is furnished by the sub-ballast.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-2-21
4
Roadway and Ballast
2.11.2.5 Sub-ballast Materials
a.
Material most commonly available for use as sub-ballast are those aggregates ordinarily specified and
used in construction for highway bases and subbases. These include crushed stone, natural or crushed
gravels, natural or manufactured sands, crushed slag or a homogeneous mixture of these materials.
Other natural on site materials conforming to proper engineering standards and specifications as may be
defined by individual railway companies may be used.
b. The sub-ballast shall be a granular material so graded as to prevent penetration into the subgrade and
penetration of track ballast particles into the sub-ballast zone. Applying the filter principle used in
drainage to the grading of the subgrade material will determine the grain size distribution of the subballast. Most state highway specifications include standard gradations for dense graded aggregate (DGA)
and aggregate base course (ABC). These gradations may meet the requirements for use as sub-ballast.
Other standard gradations may also meet these requirements.
c.
Prepare the gradation curve for the sub-ballast by plotting the grain size distribution for the subgrade on
a semi-logarithmic paper, using the logarithmic scale for the grain sizes and the natural scale for percent
passing. Determine the grain-sizes at 15%, and 50% points on the chart. Use these values with relevant
ratios from Table 1-2-3 to compute the limiting grain sizes at the 15% and 50% passing lines on the
chart. The maximum grain size of the sub-ballast must not exceed the maximum grain size of the track
ballast. No more than 5% of the sub-ballast should pass the No. 200 sieve. Construct lines connecting the
minimum and maximum points to set limits for the sub-ballast material. See example
Figure 1-2-5.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-2-22
AREMA Manual for Railway Engineering
Ballast
Table 1-2-3. Requirements for Filter Material (after USBR1963)
Character of Filter Materials
Ratio R50
Ratio R15
5 to 10
–
12 to 58
12 to 40
9 to 30
6 to 18
Uniform grain-size distribution (U = 3 to 4)
Well graded to poorly graded (non-uniform); subrounded grains
Well graded to poorly graded (non-uniform); angular particles
R50 = D50 of filter material /
D50 of material to be protected
Note:
R15 = D15 of filter material /
D15 of material to be protected
Grain-size curves (semilogarithmic plot) of sub-ballast and subgrade should be
approximately parallel in the finer range of sizes.
This table was prepared especially for earth dam design and since the use here is for
a different purpose the values given may be slightly exceeded. In event that soil in
subgrade may be subject to piping, position the maximum percentage value of D for
the sub-ballast to be less than 5 ¥ D85 of the subgrade soil. The sub-ballast in this
case should be well graded.
1
3
4
Figure 1-2-5. Example Using Table 1-2-4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-2-23
Roadway and Ballast
2.11.3 TESTING (1996)
Some of the most frequently used tests for sub-ballast material are given in Table 1-2-4 which state properties,
test methods, and comments on limiting values.
Table 1-2-4. Sub-ballast Properties and Test Methods
Property
Test Method
Comments
Particle Size Analysis
ASTM D 422
See Article 2.11.2.5
Moisture Density Relation
ASTM D 1557
Maximum Dry Density
and Optimum Moisture
Content
Liquid and Plastic Limits
Minus No. 40 Sieve
ASTM D 423
ASTM D 424
See Design Section
Degradation–Los Angeles Abrasion
ASTM C 131
Variable (Note 1)
Sodium Sulphate Soundness
ASTM C 88
Variable (Note 1)
Percent Material Passing No. 200 Sieve
ASTM C 117
Variable (Note 1)
Permeability
ASTM D 2434
Variable (Note 1)
Specific Gravity
ASTM C 127
Variable (Note 1)
Note 1: The numerical value of these tests will depend upon the physical and chemical
characteristics of both the ballast and subgrade as well as the material used for sub-ballast
and values as may be defined by the individual railway companies.
2.11.4 CONSTRUCTION OF SUB-BALLAST SECTION (1996)
a.
The subgrade shall have been graded, shaped and compacted as required by the plans and specifications.
The top of the subgrade requires special attention to obtain uniform density. A uniformly smooth surface
compacted to specifications is required, containing no ruts, pot holes, loose soil or any imperfection
retaining water on the surface. The surface shall be inspected by the engineer and if surface fails to
conform to specifications the engineer may require blading, rolling and compacting to provide a
satisfactory surface.
b. The sub-ballast material shall be transported and delivered to the site in a manner that will prevent
segregation or loss of material. The material shall be placed in layers of 3 inches to 6 inches (or as
directed by the engineer) and compacted to depth and density as required by the plans and specifications.
The sub-ballast shall be shaped as required by the plans and specifications and the finished surface shall
be free from surface defects and imperfections that will retain water or restrict free flow of water.
c.
Vehicular traffic is to be kept to a minimum across the newly prepared sub-ballast surface. The
contractor shall be responsible for maintaining a firm, true and smooth surface compacted to the
required density until track ballast is placed on the sub-ballast.
2.11.5 PRODUCTION AND HANDLING
Production and handling shall conform to Section 2.5, Production and Handling, of this chapter for track
ballast.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-2-24
AREMA Manual for Railway Engineering
Ballast
2.11.6 INSPECTION (1996)
Inspection of material at production site shall conform to Section 2.7 of this chapter.
2.11.7 MEASUREMENT AND PAYMENT (1996)
a.
The pay item for furnishing, placing, shaping, compacting and maintaining the sub-ballast until
acceptance by the railway shall be “sub-ballast” and the pay unit shall be by the ton.
b. Measure and payment for water used to moisten subgrade prior to placing the sub-ballast, in mixing subballast material to maintain proper moisture during compaction and maintenance of the surface during
construction shall not be measured for separate payment but shall be considered incidental to subballast payment.
COMMENTARY (1988)
a.
Sub-ballast exists under most of all railroad tracks as a result of degradation of track ballast material.
Most of our rail lines are over a century old and during that period weathering and mechanical forces
from traffic have reduced the size of the earlier ballasts to much smaller particles.
b. Sub-ballast is used in new construction and rehabilitation of the track substructure when the entire
track superstructure has been removed to rebuild the subgrade. The sub-ballast performs several
important functions:
1
(1) The sub-ballast must be sufficiently impervious to divert most of the water falling into the track to
the side ditches to prevent saturation of the subgrade which would weaken the subgrade and
contribute to failure under load.
(2) The sub-ballast must be sufficiently pervious to permit release of the capillary water or seepage of
water to prevent the accumulation of water below the sub-ballast. This condition could cause failure
of the subgrade. If the sub-ballast material is not sufficiently pervious, a layer of sand or other
suitable material meeting engineering standards as outlined in this specification should be
constructed between the subgrade and sub-ballast sections of the roadway structure.
(3) The sub-ballast must possess sufficient strength to support the load applied by the ballast section
and transfer the load to the subgrade.
(4) A sufficient thickness of non-frost susceptible sub-ballast should be provided in those installations
where extreme environmental conditions (freezing and thawing) are encountered.
(5) The finished surface of the sub-ballast section should be stable to provide a construction platform for
placing the track ballast and superstructure without rutting or other surface irregularities which
could pocket water. As defined, there are many preferred characteristics which will determine the
performance of a suitable sub-ballast material. Therefore, it is imperative for the engineer to follow
established engineering principles and select those materials meeting performance criterion
commensurate with roadway stability requirements. The Engineer may also define other tests of a
proposed sub-ballast material in addition to the tests outlined in Table 1-2-4 to define other
properties of the track ballast and subgrade where unusual subgrade or ballast conditions exist.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-2-25
3
4
Roadway and Ballast
SUMMARY (1988)
a.
The AREMA Ballast Specification is intended as a guideline and cannot cover all of the requirements
necessary for the full appraisal of the in track performance of a ballast material. It is not possible to
incorporate into the laboratory tests those field factors which include geographical and climatic
conditions, load variations, subgrade conditions, and other conditions which will actually determine the
total in track performance of a ballast material. Generally, the revised specifications have established
material standards and test requirements which will provide more efficient ballast materials
commensurate with current roadbed structure and performance requirements.
b. The AREMA Ballast Committee will continue to pursue the multiple ballast testing programs and will
modify the ballast specification, as required, to produce a more definitive ballast specification for the
railroad industry.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-2-26
AREMA Manual for Railway Engineering
1
Part 3
Natural Waterways
— 2005 —
TABLE OF CONTENTS
Section/Article
Description
Page
3.1 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.1.1 Scope (1992) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.1.2 Importance (1992) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-3-4
1-3-4
1-3-5
3.2 Drainage Basin Data. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.2.1 General (1992) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-3-5
1-3-5
3.3 Capacity of Waterway Openings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.3.1 General (1984) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.3.2 Methods (1984) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.3.3 Summary (1984) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-3-7
1-3-7
1-3-8
1-3-18
3.4 Basic Concepts and Definitons of Scour . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.4.1 Scour (2005) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.4.2 Long-term Elevation Streambed Changes (Aggradation and Degradation) (2005) . . . . .
3.4.3 Contraction Scour (2005) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.4.4 Local Scour (2005) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.4.5 Lateral Stream Migration (2005) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.4.6 Total Scour (2005) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.4.7 References for Section 3.4 (2005) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-3-20
1-3-20
1-3-21
1-3-22
1-3-22
1-3-23
1-3-24
1-3-24
3.5 Calculating Scour . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.5.1 Predicting Aggradation and Degradation (2005). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.5.2 Predicting Lateral Migration (2005) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.5.3 Estimating Contraction Scour (2005) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.5.4 Estimating Local Pier Scour (2005) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.5.5 Evaluating Local Scour at Abutments (2005) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.5.6 Total Scour Calculation Problem (2005) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.5.7 References for Section 3.5 (2005) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-3-25
1-3-25
1-3-28
1-3-31
1-3-43
1-3-49
1-3-53
1-3-59
3.6 Protecting Roadway and Bridges From Scour . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.6.1 Embankment (2005) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.6.2 Bridges (2005) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.6.3 Countermeasure Selection (2005) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-3-60
1-3-60
1-3-61
1-3-62
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-1
1
3
Roadway and Ballast
TABLE OF CONTENTS (CONT)
Section/Article
3.6.4
Description
Page
Countermeasure Design Guidance (2005). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-3-77
3.7 Means of Protecting Roadbed and Bridges from Washouts and Floods . . . . . . . . . . . .
3.7.1 General (1996) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.7.2 Roadway (1996). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.7.3 Bridges (1996) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-3-145
1-3-145
1-3-145
1-3-146
3.8 Construction and Protection of Roadbed Across Reservoir Areas . . . . . . . . . . . . . . . .
3.8.1 General (1978) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.8.2 Determination of Wave Heights (1978). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.8.3 Construction of Embankment and Roadbed (1978) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.8.4 Construction of Embankment Protection (1978) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-3-147
1-3-147
1-3-147
1-3-153
1-3-154
3.9 Glossary. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-3-156
LIST OF FIGURES
Figure
1-3-1
1-3-2
1-3-3
1-3-4
1-3-5
1-3-6
1-3-7
1-3-8
1-3-9
1-3-10
1-3-11
1-3-12
1-3-13
1-3-14
1-3-15
1-3-16
1-3-17
1-3-18
1-3-19
1-3-20
1-3-21
1-3-22
1-3-23
1-3-24
1-3-25
1-3-26
1-3-27
1-3-28
1-3-29
1-3-30
Description
Page
Log Pearson Type III Exceedance Probability Plot. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Velocities of Flow, Rural Watersheds (Reference 49) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Curve Number Method for Estimating Lag (L) [L = 0.6tc], Urban Watersheds (Reference 49)
Pier Scour Depth in a Sand-bed Stream as a Function of Time. . . . . . . . . . . . . . . . . . . . . . . . .
Schematic Representation of Scour at a Cylindrical Pier . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Specific Gage Data for Cache Creek, California . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Flow Patterns in Meanders. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Case 1A: Abutments Project into Channel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Case 1B: Abutments at Edge of Channel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Case 1C: Abutments Set Back from Channel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Case 2A: River Narrows . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Case 2B: Bridge Abutments and/or Piers Constrict Flow . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Case 3: Relief Bridge Over Floodplain . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Case 4: Relief Bridge Over Secondary Stream. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Fall Velocity of Sand-sized Particles with Specific Gravity of 2.65 in Metric Units . . . . . . . . .
Comparison of Scour Equations for Variable Depth Ratios (y/a) (HEC-18) . . . . . . . . . . . . . . .
Common Pier Shapes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Multiple Columns Skewed to the Flow . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Topwidth of Scour Hole . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Schematic Representation of Abutment Scour . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Scour of Bridge Abutment and Approach Embankment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Orientation of Embankment Angle, q, to the Flow . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Abutment Shape . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Cross Section for Total Scour Problem . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Hydraulic Data for Contraction Scour Calculations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Hydraulic Data for Local Scour Calculations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Total Scour Plot. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Comparison of Channel Bend Cross Sections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Effect of Turbulence Intensity on Rock Size Using the Isbash Approach . . . . . . . . . . . . . . . . .
Placement of Pier Riprap . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-3-9
1-3-18
1-3-19
1-3-21
1-3-23
1-3-26
1-3-29
1-3-34
1-3-35
1-3-36
1-3-37
1-3-38
1-3-39
1-3-39
1-3-41
1-3-44
1-3-45
1-3-47
1-3-49
1-3-50
1-3-50
1-3-52
1-3-52
1-3-54
1-3-55
1-3-57
1-3-59
1-3-72
1-3-79
1-3-80
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-2
AREMA Manual for Railway Engineering
Natural Waterways
LIST OF FIGURES (CONT)
Figure
1-3-31
1-3-32
1-3-33
1-3-34
1-3-35
1-3-36
1-3-37
1-3-38
1-3-39
1-3-40
1-3-41
1-3-42
1-3-43
1-3-44
1-3-45
1-3-46
1-3-47
1-3-48
1-3-49
1-3-50
1-3-51
1-3-52
1-3-53
1-3-54
1-3-55
1-3-56
1-3-57
1-3-58
1-3-59
1-3-60
1-3-61
1-3-62
1-3-63
1-3-64
1-3-65
1-3-66
1-3-67
1-3-68
1-3-69
1-3-70
1-3-71
1-3-72
1-3-73
1-3-74
1-3-75
Description
Page
Section View of a Typical Setup of Spill-through Abutment on a Floodplain With Adjacent Main
Channel. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-81
Plan View of the Location of Initial Failure Zone of Rock Riprap for Spill-through Abutment 1-3-82
Characteristic Average Velocity for SBR<5 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-84
Characteristic Average Velocity for SBR>5 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-85
Characteristic Average Velocity for SBR>5 and SBR<5. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-86
Plan View of the Extension of Rock Riprap Apron . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-87
Typical Guide Bank (Modified from Bradley). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-89
English Version of Nomograph to Determine Guidebank Length (after Bradley) . . . . . . . . . . 1-3-91
Example Guide Bank Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-94
Extent of Protection Required at a Channel Bend (after USACE) . . . . . . . . . . . . . . . . . . . . . . . 1-3-97
Definition Sketch for Spur Angle (after Karaki 1959) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-98
Launching of Stone Protection on a Riprap Spur . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-100
Gabion Spur Illustrating Flexible Mat Tip Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-101
Permeable Wood-slat Fence Spur Showing Launching of Stone Toe Material (after Brown) . 1-3-102
Relationship Between Spur Length and Expansion Angle for Several Spur Permeabilities
(after Brown). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-103
Spur Spacing in a Meander Bend (after Brown) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-103
Typical Straight, Round Nose Spur . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-105
Impermeable Spur Field in Top Photograph With Close-up Shot of One Spur in the Lower Photograph,
Vicinity of the Richardson Highway, Delta River, Alaska . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-106
Example of Spur Design. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-107
Angle of Repose of Riprap in Terms of Mean Size and Shape of Stone (Chen and Cotton 1988) 1-3-110
Methods of Providing Toe Protection (USACE 1991) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-114
Alternative Method of Providing Toe Protection (HEC-11) . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-115
Flank Details (HEC-11) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-116
Rock-fill Trench (after HDS 6) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-118
Windrow Revetment, Definition Sketch (after USACE 1981). . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-119
Typical Sand-cement Bag Revetment (after Brown 1985). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-121
Typical Stacked Block Gabion Revetment Details . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-124
Gabion Basket Fabrication . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-126
Schematic of a Vertical Drop Caused by a Check Dam . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-128
Design Example of Scour Downstream of a Drop Structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-130
Encroachment on a Meandering River . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-132
Perspective View of Hardpoint Installation With Section Detail (after Brown) . . . . . . . . . . . . 1-3-137
Typical Jack Unit (after Brown) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-138
Retarder Field Schematic (after HDS 6). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-138
Timber Pile Bent Retarder Structure (after Brown) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-139
Typical Wood Fence Retarder Structure (after Brown). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-140
Light Double Row Wire Fence Retarder Structure (after Brown) . . . . . . . . . . . . . . . . . . . . . . . 1-3-140
Heavy Timber-pile and Wire Fence Retarder Structure (after Brown) . . . . . . . . . . . . . . . . . . . 1-3-141
Typical Longitudinal Rock Toe-dike Geometries (after Brown) . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-143
Longitudinal Rock Toe-dike Tiebacks (after Brown) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-143
Timber Pile, Wire Mesh Crib Dike With Tiebacks (after Brown) . . . . . . . . . . . . . . . . . . . . . . . . 1-3-144
Anchorage Schemes for a Sheetpile Bulkhead (after Brown) . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-144
Wave Heights and Minimum Wind Durations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-149
Wave Periods . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-150
Fetch Example Calculation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3-151
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-3
1
3
4
Roadway and Ballast
LIST OF FIGURES (CONT)
Figure
Description
Page
1-3-76 Wave Run-up Ratios . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-3-152
LIST OF TABLES
Table
1-3-1
1-3-2
1-3-3
1-3-4
1-3-5
1-3-6
1-3-7
1-3-8
1-3-9
1-3-10
1-3-11
1-3-12
1-3-13
1-3-14
1-3-15
1-3-16
1-3-17
1-3-18
1-3-19
1-3-20
1-3-21
1-3-22
1-3-23
Description
Page
Rural Area Runoff Coefficient Values . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Urban Area Runoff Coefficient Values. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Storm Duration Calculations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Values of N in the Kerby Formula . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Values of c in Izzard Formula. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Soil Type Groupings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Determining Antecedent Moisture Condition . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Curve Numbers for Various Cover and Soil Types [AMC = II] (Reference 50) . . . . . . . . . . . .
Antecedent Moisture Condition to Curve Number Conversion . . . . . . . . . . . . . . . . . . . . . . . . .
Correction Factor, K1, for Pier Nose Shape . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Correction Factor, K2, for Angle of Attack, q, of the Flow . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Increase in Equilibrium Pier Scour Depths, K3, for Bed Condition . . . . . . . . . . . . . . . . . . . . .
Abutment Shape Coefficients . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Stream Instability and Bridge Scour Countermeasures Matrix . . . . . . . . . . . . . . . . . . . . . . . . .
Coordinates for Guide Bank on the Right Bank of Figure 10.4 . . . . . . . . . . . . . . . . . . . . . . . . .
Rock Riprap Gradation Limits . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Riprap Gradation Classes (English) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Standard Gabion Sizes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
River Response to Cutoffs (HDS 6) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Wind Relationship – Land to Water . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Wave Height Distributions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Sample Computation for Determining Wave Height and Protection Needs . . . . . . . . . . . . . . .
Filter Blanket Limits. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-3-10
1-3-11
1-3-12
1-3-12
1-3-12
1-3-14
1-3-14
1-3-15
1-3-16
1-3-45
1-3-46
1-3-46
1-3-52
1-3-64
1-3-96
1-3-112
1-3-112
1-3-124
1-3-135
1-3-148
1-3-149
1-3-153
1-3-155
SECTION 3.1 GENERAL1
3.1.1 SCOPE (1992)
This subject concerns the determination of the location, size, and shape of drainage structures. It also includes
consideration of flood flows and water-borne materials in surface waters, the protection of the roadway in
contact with surface water, and the protection of structures carrying tracks over waterway openings.
1
References, Vol. 39, 1938, pp. 322, 786; Vol. 51, 1950, pp. 706, 839; Vol. 54, 1953, pp. 1087, 1385; Vol. 62, 1961, pp. 678, 936; Vol. 73, 1972,
p. 143; Vol. 85, 1984, p. 5; Vol. 93, 1992, p 34.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-4
AREMA Manual for Railway Engineering
Natural Waterways
3.1.2 IMPORTANCE (1992)
Properly designed openings, control of flood flows, and protection of roadway and structures are of vast
importance from the standpoints of safety, economy, and continuity of operation during flood periods. With the
ever-present menace of floods and then disastrous consequences, every related problem is deserving of accurate
and exhaustive survey and careful planning.
SECTION 3.2 DRAINAGE BASIN DATA1
3.2.1 GENERAL (1992)
a.
Survey requirements depend in some degree upon whether the waterways are to be crossed by a new
line, or whether the replacement of an existing waterway structure is involved.
b. For the crossing of a new line the survey requirements are extensive and general in nature, involving the
determination of the drainage area and its shape; the stream and slope profile; soil, vegetation and
climatic characteristics; as well as topographical details in the vicinity of the most probable point of
crossing.
c.
For the replacement of an existing waterway structure the survey requirements may be the same as
those for a new line, but in many cases the required waterway area will likely be determined from past
performance of the stream at the structure to be replaced. Observation may have indicated that a change
in size, shape or location of the waterway structure may be desirable. Maintenance of railroad operation
during construction and how well the existing structure fits into the local topography may control the
design of the new structure. All such facts should be considered in determining survey requirements.
d. Consideration should always be given to probable future changes in conditions above and below the point
of crossing which would in any way affect the performance of the stream – for example, channel
improvements and the construction or removal of dams or revetments. Also, a search should be made for
future subdivision or commercial development plans.
e.
For small culverts or replacements some of the data listed here may be unnecessary and some will have
been predetermined, but all of the following items should be considered in order that survey notes may
include all the information necessary for the design of the most suitable structure:
(1) Area of drainage basin.
(2) Shape and contour of drainage basin.
(3) Location, length and slope of defined channels.
(4) Slope of stream bed and side slopes.
(5) Character of soil and subsoil.
(6) Vegetation – timber, grass, cultivated or barren, and probable changes.
1
References, Vol. 39, 1938, pp. 322, 786; Vol. 51, 1950, pp. 706, 839; Vol. 54, 1953, pp. 1087, 1385; Vol. 62, 1961, pp. 678, 936; Vol. 73, 1972,
p. 143; Vol. 85, 1984, p. 5; Vol. 93, 1992, p 34.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-5
1
3
4
Roadway and Ballast
(7) Climatic conditions – accumulation of snow and ice.
(8) Precipitation – local records, if any, of intensity, duration, frequency, and temporal and area
distribution.
(9) Natural and artificial storage – lakes, swamps, reservoirs.
(10) Channel course – fixed or changeable.
(11) Channel material – rock, boulders, gravel, sand, clay, silt.
(12) Channel erosion – amount and nature of material transported.
(13) Possibility of ice gorges, or drift accumulations.
(14) Elevation of backwater from larger stream below crossing.
(15) Determination of past flood crests and frequency. On an existing line crossing a wide valley with two
or more openings secure high water profile across the valley on both sides of the railroad
embankment.
(16) Character of current – rate of flow – steady or variable.
(17) Waterway area, relative flood flows and adequacy of existing drainage structures nearby on the
waterway.
(18) Topography over liberal area in vicinity of crossing. Typical flood channel sections.
(19) Location of right-of-way limits.
(20) Property lines and owners names along stream if channel change is contemplated.
(21) Track profile, alignment and topography for sufficient distance to cover any probable change, or as
necessary to portray conditions.
(22) Borings locate and give character of material found.
(23) Determine most favorable angle of stream crossing.
(24) Location – mile post and survey station.
(25) Location of borrow pit if bridge filling is involved.
(26) Location and elevation of improvements which might be subject to flooding by backwater upstream
from track.
(27) Flood plain regulations and studies, if available.
(28) Governmental regulations and requirements.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-6
AREMA Manual for Railway Engineering
Natural Waterways
SECTION 3.3 CAPACITY OF WATERWAY OPENINGS1
3.3.1 GENERAL (1984)
a.
In the past, in the design of drainage structures, it was considered sufficient to provide a waterway
opening of a certain area, based on an area formula (e.g. Talbot’s formula); also, in case the flow (Q) were
known, one could assume a velocity of flow (V) (usually taken as 10 feet per sec) and, thus, arrive at the
required area (A) of opening. Modern practice is to first calculate the drainage, or flow, then to design the
structure to accommodate the flow (Reference 6) using the principles of hydraulics.
b. Before deciding on the hydraulic capacity to be provided in a structure, it is advisable to make a thorough
search to determine what precipitation and stream flow records are available in the general region of the
project site. Where data and time are available, several methods of determining the required capacity
should be used, and their results compared before a decision is made. Extensive study and research are
in continuous progress by various public agencies in the field of flood runoff and waterway requirements,
and it is expected that much additional useful data will be developed.
c.
These agencies are much better suited, both in full-time personnel in this specialized field and in access
to pertinent data as quickly as it becomes available, than are most railroads. Therefore, the needs of
railroad personnel dealing with drainage matters are best served by having at hand a list of agencies
through which they can obtain the latest information on the subject. In order to take full advantage of
this and to insure uniformity of design criteria on the individual railroad, it is advisable that all drainage
recommendations and supporting data should clear through a designated “drainage engineer” before
final decision.
1
d. A list of Federal and State agencies in the United States that are engaged in research, accumulation of
data, and the statistical analysis of precipitation and runoff is given below:
• Federal
United States Geological Survey
Water Supply Papers
Flood Magnitude-Frequency Reports
Federal Highway Administration
Transportation Research Board
Soil Conservation Service
Corps of Engineers, U.S. Army
Water and Power Resources Service
National Oceanic and Atmospheric Administration
3
4
• State
Highway Departments
Water Resources Department
Public Works Departments
Universities
• County or Parish
Highway Departments
Public Works Departments
In Canada, stream flow data can be secured from the Water Survey of Canada Division of Environment
Canada at Ottawa. Stream flow data are, generally, not available for Mexico.
1
References, Vol. 42, 1941, pp. 543, 831; Vol. 53, 1952, pp. 699, 1106; Vol. 54, 1953, pp. 1087, 1385; Vol. 62, 1961, pp. 678, 936; Vol. 73,
1972, p. 144; Vol. 85, 1984, p. 5.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-7
Roadway and Ballast
3.3.2 METHODS (1984)
3.3.2.1 General
The recommended methods will be those most easily applied that give the best results with a minimum of
available information. The basic data required are covered in Section 3.2, Drainage Basin Data. In addition, an
indispensable aid is a collection of topographic maps as published by the U.S. Geological Survey in conjunction
with TVA, Mississippi River Commission, U.S. Corps of Engineers, etc. With these data in hand, the engineer
can proceed to specific methods. These methods are presented in the sections which follow.
3.3.2.2 Statistical Methods
a.
When there exist sufficient flow data for the waterway under consideration, a statistical analysis can be
undertaken to estimate the probability that a given magnitude of flow can occur or be exceeded
(Reference 13). Federal regulations mandate the use of the Log Pearson Type III distribution, a
procedure for analyzing extreme events such as maximum yearly discharges for a stream.
b. Special plotting paper (probability  2 log cycles) can be used for this analysis by following the steps
listed below:
(1) Collect runoff data from a stream gaging station near to the desired location, as obtained from such
as the U.S. Geological Survey Water Supply Papers. A usable record must have a continuity of data of
20 years or more.
(2) Arrange the data by listing in descending order the magnitudes of the largest recorded peak
discharges, i.e. the largest first. The ranking is only by discharge quantity and is independent of
when the discharge occurred in the period of record. The series may be terminated when the number
of peak discharges equals the number of years of record. The peak discharges should then be
numbered (labelled) from one to the number of years of record.
(3) Calculate the exceedance probability by first calculating the estimated return period for each peak
discharge by
n + 1
T r = ----------------m
EQ 1
where:
n = number of years of record
m = rank or order number of that particular peak discharge
The exceedance probability
1 and represents the probability that the specific peak discharge will occur or beexceeded
p = ----Tr
(4) Utilizing the plotting paper, select a suitable vertical scale so all the discharge data can be graphed
and still allow predicted values to be read. Plot the data of peak discharges on the vertical axis and
the exceedance probability (%) on the horizontal axis. Fit the best straight line to the plotted data.
As an example, using Figure 1-3-1, the probability that a discharge of 10,000 c.f.s. will be equalled
or exceeded is 10.9% (i.e. a return period of 9.1 years) for this record. Again, using Figure 1-3-1,
the 100-year discharge (100 year return period or 1% exceedance probability) is 15,800 c.f.s.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-8
AREMA Manual for Railway Engineering
Natural Waterways
c.
The design flood frequency to be used is a matter of engineering judgment and economics. A number of
trials should be made using a wide range of frequencies. In this way the possibilities of damage because
of too small an opening can be assessed. The cost of providing for the maximum possible flood of 100 year
frequency or greater can also be determined and a prudent decision made. In general practice, railroad
drainage openings should be designed for floods in the range of 25 to 50 years. This does not imply that a
100-year flood design would be out of place in certain instances. Because of the susceptibility of railroads
to legal action for damages, it would probably be unwise to design for less than a 25-year flood, except in
special instances where results of lesser design are fully understood.
d. After the design flow in cubic feet per second has been determined, the basic hydraulic formula Q = AV
can be used to determine the average velocity in feet per second through a given area of opening in
square feet. For structures on unstable soils, 3 feet per sec may be the maximum allowable velocity
without damaging scour; generally, 3 to 6 feet per sec will cause little, if any, scour in fairly good soils.
Culverts and other paved waterways are frequently designed for flows as high as 10 feet per sec. If time
permits and greater refinement is desired, there is a multitude of hydraulics texts and manuals available
for the design of waterway openings, (Reference 6 and 45).
1
3
4
Figure 1-3-1. Log Pearson Type III Exceedance Probability Plot
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-9
Roadway and Ballast
3.3.2.3 The Rational Method
3.3.2.3.1 General
a.
The rational method is an old, simple, widely used (and often criticized) method employed in the
determination of peak discharges from a given watershed. The method is based on the idea that the peak
rate of surface outflow from a given watershed will be proportional to the watershed area and the
average rainfall intensity over a period of time just sufficient for all parts of the watershed to contribute
to the outflow (Reference 38). The constant of proportionality is then supposed to reflect all those
characteristics of the watershed. In its simplest form, the rational formula is written as
EQ 2
Q = CiA
where:
Q = peak discharge (cubic feet per second – cfs)
C = ratio or peak runoff rate to average rainfall rate over the
time of concentration (runoff coefficient)
i = rainfall intensity (inches/hour)
A = area of watershed under consideration (acres)
b. In general the rational method should be applied to drainage basins less than 200 acres in area and is
best suited for well-defined drainage basins, such as urban areas.
3.3.2.3.2 Determining Runoff Coefficient
a.
Values of runoff coefficient are given separately for rural areas and urban areas in Table 1-3-1 and
Table 1-3-2, as taken from Schwab, et al (Reference 46).
Table 1-3-1. Rural Area Runoff Coefficient Values
Vegetation and
Topography
Soil Texture
Open Sandy
Loam
Clay and Silt
Loam
Tight Clay
Woodland
Flat 0-5% slope
0.10
0.30
0.40
Rolling 5-10% slope
0.25
0.35
0.50
Hilly 10-30% slope
0.30
0.50
0.60
Pasture
Flat
0.10
0.30
0.40
Rolling
0.16
0.36
0.55
Hilly
0.22
0.42
0.60
Cultivated
Flat
0.30
0.50
0.60
Rolling
0.40
0.60
0.70
Hilly
0.52
0.72
0.82
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-10
AREMA Manual for Railway Engineering
Natural Waterways
Table 1-3-2. Urban Area Runoff Coefficient Values
Description of Area
Runoff Coefficients
Business
Downtown
Neighborhood
0.70 to 0.95
0.50 to 0.70
Residential
Single-family
Multi-units, detached
Multi-units, attached
Residential (suburban)
Apartment
0.30 to 0.50
0.40 to 0.60
0.60 to 0.75
0.25 to 0.40
0.50 to 0.70
Industrial
Light
Heavy
0.50 to 0.80
0.60 to 0.90
Miscellaneous
Parks, cemeteries
Playgrounds
Railroad yard
Unimproved
0. 10 to 0.25
0.20 to 0.35
0.20 to 0.35
0.10 to 0.30
1
b. The runoff coefficient is influenced by many variables, and does not remain constant during a given
storm. Thus, “engineering judgment” must be liberally applied in the selection of the coefficient
magnitude.
3
3.3.2.3.3 Determining Rainfall Intensity
a.
The rainfall intensity is the average value in inches per hour during the time of concentration which, by
definition, is the time required for runoff to flow from the most remote part of the drainage area to the
outlet structure.
4
b. Rainfall intensity relations will usually fit the following equation:
m
cT
i = -------------------n
t + d
EQ 3
where:
i = intensity (inches/hour)
T = return period (years)
t = storm duration (minutes)
c, d, m, n = regional coefficients
c.
As an example, Fair et al (Reference 22) found that in Indiana the following magnitudes apply:
5 < c < 50
0 < d < 30
0.1< m < 0.5
0.4 < n < 1.0
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-11
Roadway and Ballast
d. Reference may also be made to the rainfall intensity curves presented by various publications
(Reference 24 and 26). These data may be used in the rational formula in concert with the appropriate
storm duration.
e.
The appropriate return period has been discussed in Article 3.3.2.2 and the reader is referred to that
discussion.
f.
The appropriate storm duration may be calculated from the information found in Table 1-3-3.
Table 1-3-3. Storm Duration Calculations
Name
Ragan (1972)
(Reference 45)
Kerby (1959)
(Reference 34)
Izzard (1946)
(Reference 32)
Equation for t
Notes
n varies from about 0.025 to 0.040 for flow over
natural earthen materials
EQ 4
0.6 0.6
L n
t = --------------------0.4 0.3
i s
NL 0.467
t = 0.827  ---------
 0.5
s
–2  3
2 0.0007i + c iL
t = ------ -----------------------------L ----------------13
60
43200
S
L < 1200 ft; N as in Table 1-3-4
EQ 5
for iL < 500; c as in Table 1-3-5
EQ 6
t = overland flow time (min), considered to be equal to storm duration
L = basin length (ft)
S = basin slope (ft/ft)
i = rainfall intensity (in/hr)
Table 1-3-4. Values of N in the Kerby Formula
Type of Surface
N
Smooth impervious surface
0.02
Smooth bare packed soil
0.10
Poor grass, cultivated row crops or moderately rough bare surface
0.20
Deciduous timberland
0.60
Pasture or average grass
0.40
Conifer timberland, deciduous timberland with deep forest litter or dense grass
0.80
Table 1-3-5. Values of c in Izzard Formula
Surface
N
Smooth asphalt surface
0.007
Concrete pavement
0.012
Tar and gravel pavement
0.017
Closely clipped sod
0.046
Dense bluegrass turf
0.060
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-12
AREMA Manual for Railway Engineering
Natural Waterways
3.3.2.3.4 Application of the Rational Method
a.
Determine the basin area A (acres) by using USGS topographical maps, maps developed from a survey of
the area, or plans made specifically for the basin. This area can then be found by use of a planimeter,
counting squares, etc.
b. By the use of Tables for rural and urban areas from Article 3.3.2.3.2, find the appropriate value of C
(runoff coefficient). If the land is a conglomerate of uses, a composite C value may be determined by:
 C 1 A 1 + C 2 A 2 + YC n A n 
C comp = -----------------------------------------------------------------At
EQ 7
where:
C1, C2…Cn are the runoff coefficients associated with component areas A1, A2 …An and
At = A1 + A2 + …An.
c.
Determine the magnitude of rainfall intensity. The storm duration for the basin can be determined by
using one of the equations listed in the Table 1-3-3 in Article 3.3.2.3.3. This magnitude is found by
knowing the basin length, slope, and cover.
d. Determine rainfall intensity by using EQ 3 with appropriate coefficients, or by entering an intensityduration-frequency diagram (Reference 24 and 26).
e.
The data of paragraph a, paragraph b and paragraph d are then inserted into EQ 1 to yield the predicted
peak discharge.
1
3.3.2.4 Soil Conservation Service Curve Number Method
3.3.2.4.1 The Theory
a.
This method develops the quantity of runoff from a given amount of precipitation, and considers the
effects of basin soil and cover types, rainfall depth, and antecedent moisture conditions (Reference 49).
b. The total runoff is calculated as the difference between total rainfall and total abstraction, which is the
sum of total infiltration and how much water is used to initially wet the surface and fill surface
depressions. The method assumes that the ratio of runoff to available water is the same as the ratio of
infiltration to ultimate total abstraction. The resulting equation is:
2
 P  t  – 0.2S 
R  t  = ------------------------------------ P  t  + 0.8S 
EQ 8
where:
R(t) = runoff (cumulative) (inches)
P(t) = total rainfall (inches)
S = ultimate total abstraction
c.
This calculation is made for 4 or 5 storms of different convenient storm durations to assess which
produces the most severe condition. Often local custom dictates which storms must be examined.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-13
3
4
Roadway and Ballast
3.3.2.4.2 Determining the Parameter S
a.
Soil type is variable, and four groupings have been created based on infiltration capacity. Table 1-3-6 lists
these soil criteria:
b. Also to be considered is the antecedent moisture condition (AMC), which is an indication of how much
rain has fallen on the basin recently. See Table 1-3-7.
c.
Then, knowing the soil group and the antecedent moisture condition class, a curve number (CN) is
established from Table 1-3-8 which is representative of a large variety of conditions.
Table 1-3-6. Soil Type Groupings
Soil
Group
Characteristics
A
Soils in this category have a high infiltration rate even when thoroughly wetted and consist
mainly of deep, well-to excessively-drained sands or gravels. (Low runoff potential)
B
Soils in this category have moderate infiltration rates when thoroughly wetted and consist of
moderately deep to deep, moderately well to well-drained soils with moderately fine to moderately
coarse textures.
C
Soils in this category have slow infiltration rates when thoroughly wetted and consist mainly of
soils with a layer that impedes downward movement of water, or soils with moderately fine to fine
textures.
D
Soils in this category have a very slow infiltration rate when thoroughly wetted and consist mainly
of clay soils with high swelling potential, soils with a permanently high water table, soils with a
claypan or clay layer at or near the surface, and shallow soils over nearly impervious material.
(High runoff potential)
Table 1-3-7. Determining Antecedent Moisture Condition
Antecedent Moisture
Condition Class
5-Day Antecedent Rainfall
(inches)
Dormant Season
Growing Season
I
Less than 0.5
Less than 1.4
II
0.5 1.1
1.4 2.1
III
over 1.1
over 2.1
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-14
AREMA Manual for Railway Engineering
Natural Waterways
Table 1-3-8. Curve Numbers for Various Cover and Soil Types [AMC = II] (Reference 50)
Land Use Description
Hydrologic Soil Group
A
B
C
D
72
62
81
71
88
78
91
81
Pasture or range land: poor condition
good condition
68
39
79
61
86
74
89
80
Meadow: good condition
30
58
71
78
Wood or forest land:
45
25
66
55
77
70
83
77
Open spaces: lawns, parks, golf course, cemeteries, etc.,
good condition: grass cover on 75% or more of the area
fair condition: grass cover on 50% to 75% of the area
39
49
61
69
74
79
80
84
Commercial and business areas (85% impervious)
89
92
94
95
Industrial districts (72% impervious)
81
88
91
93
77
61
57
54
51
85
75
72
70
68
90
83
81
80
79
92
87
86
85
84
Paved parking lots, roofs, driveways, etc. (Note 3)
98
98
98
98
Streets and roads:
paved with curbs and storm sewers (Note 3)
gravel
dirt
98
76
72
98
85
82
98
89
87
98
91
89
69-71
71-73
73-75
75-78
77-80
79-82
82-84
84-86
86-88
86
88
90
Cultivated Land:
without conservation treatment
with conservation treatment
thin stand, poor cover, no mulch
good cover
Residential (Notes 1 and 4):
Average Lot Size
1/8 acre or less
1/4 acre
1/3 acre
1/2 acre
1 acre
Average % Impervious (Note 2)
65
38
30
25
20
Urban areas:
Low density (15-18% impervious surfaces)
Medium density (21-27% impervious surfaces)
High density (50-75% impervious surfaces)
Note 1: Curve numbers are computed assuming the runoff from the house and driveway is directed towards
the street with a minimum of roof water directed to lawns where additional infiltration could occur.
Note 2: The remaining pervious areas (lawn) are considered to be in good pasture condition for these curve
numbers.
Note 3: In some warmer climates of the country a curve number of 95 may be used.
Note 4: Curve numbers may vary with different parts of the country. The local SCD office should be contacted
for recommended numbers in that locality.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-15
1
3
4
Roadway and Ballast
d. Knowing the curve number (CN), the value of S (ultimate total abstraction) is found from:
1000
S = ------------- – 10
CN
e.
EQ 9
If different antecedent moisture conditions exist than those of Group II, the conversions to CN found in
Table 1-3-9 may be used (Reference 49):
Table 1-3-9. Antecedent Moisture Condition to Curve Number Conversion
CN for
Condition II
100
99
98
97
96
95
94
93
92
91
90
89
88
87
86
85
84
83
82
81
80
79
78
77
76
75
74
73
72
71
70
69
68
67
66
65
64
63
62
CN for
Condition I
100
97
94
71
89
87
85
83
81
80
78
76
75
73
72
70
68
67
66
64
63
62
60
59
58
57
55
54
53
52
51
50
48
47
46
45
44
43
42
CN for
Condition III
100
100
99
99
99
98
98
98
97
97
96
96
95
95
94
94
93
93
92
92
91
91
90
89
89
88
88
87
86
86
85
84
84
83
82
82
81
80
79
CN for
Condition II
61
60
59
58
57
56
55
54
53
52
51
50
49
48
47
46
45
44
43
42
41
40
39
38
37
36
35
34
33
32
31
30
CN for
Condition I
41
40
39
38
37
36
35
34
33
32
31
31
30
29
28
27
26
25
25
24
23
22
21
21
20
19
18
18
17
16
16
15
25
20
15
10
5
0
12
9
6
4
2
0
CN for
Condition III
78
78
77
76
75
75
74
73
72
71
70
70
69
68
67
66
65
64
63
62
61
60
59
58
57
56
55
54
53
52
51
50
43
37
30
22
13
0
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-16
AREMA Manual for Railway Engineering
Natural Waterways
3.3.2.4.3 Application of the CN Method – Total Flow
a.
Let us assume the CN has been established, and S has been calculated. By selecting a rainfall depth for a
particular storm, the runoff may be calculated using EQ 8. The runoff (inches) is multiplied by the basin
area, and the result is converted to units of volume of runoff for the basin.
b. For a basin which has a conglomerate of soil types, a weighted CN may be calculated from:
 CN 1 A 1 + CN 2 A 2 + YCN n A n 
CN comp = ---------------------------------------------------------------------------------At
EQ 10
where:
CN1, CN2…CNn are the curve numbers associated with component areas A1, A2 … An and
At = A1 + A2 … + An.
c.
The application yields the total amount of runoff from the given rainfall. For design, then, this is
repeated for storms of different duration and amount of rainfall.
3.3.2.4.4 Determining Peak Flow from a Rainfall Event
a.
The peak flow to be expected from a storm many times is more important than the total flow because the
peak flow must be carried by the waterway opening. The following procedure is adapted from the
principles of the unit hydrograph (Reference 49) and is intended for the designer’s use as a prediction
tool.
1
b. The steps in the procedure follow.
(1) For the basin, determine:
3
(a) the basin area (square miles)
(b) the basin curve number for the soil type(s) and antecedent moisture condition (as in
Article 3.3.2.4.2)
(c) the depth, and time distribution of the rainfall for the storm in question.
4
(2) Find the time of concentration, tc. This value may be obtained using Figure 1-3-2 for rural
watersheds or Figure 1-3-3 for urbanized watersheds. In using Figure 1-3-2, the ordinate is entered
with the travel path slope, then the diagonal line which represents the basin characteristics is
intercepted, and a velocity is found by reading the abscissa. The time is then found by dividing the
travel path by the velocity and appropriate conversions. Figure 1-3-3 utilized the curve number,
travel length, and watershed in the calculation of the watershed lag L. This lag is converted to tc by
the empirical relationship L = 0.6tc.
(3) Calculate peak flow:
AR
q p = 484
--------------------0.667t c
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-17
Roadway and Ballast
where:
qp = peak flow (c.f.s.)
A = basin area (sq miles)
R = runoff depth (inches) (as calculated by EQ 8)
tc = time of concentration (hours)
c.
Repeat paragraph b(1) through paragraph b(3) for storms of different duration and amount of rainfall;
for example, durations of from 0.2 to 24 hours, or as load experience dictates, using associated rainfalls
from hydrologic records for the locality. More detailed information can be found in Reference 49, as
obtained from U.S. Supt. of Documents.
3.3.3 SUMMARY (1984)
The procedures of Article 3.3.2 will provide the design engineer with a good estimate of the capacity required
for his waterway opening provided the results are used with engineering judgement. For those interested in
additional tops in hydrology for engineering use, Reference 8, 17, and 35 are highly recommended.
Figure 1-3-2. Velocities of Flow, Rural Watersheds (Reference 49)
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-18
AREMA Manual for Railway Engineering
Natural Waterways
1
3
4
Figure 1-3-3. Curve Number Method for Estimating Lag (L) [L = 0.6tc], Urban Watersheds
(Reference 49)
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-19
Roadway and Ballast
SECTION 3.4 BASIC CONCEPTS AND DEFINITONS OF SCOUR1
3.4.1 SCOUR (2005)
3.4.1.1 Definition
Scour is the result of the erosive action of flowing water, excavating and carrying away material from the bed
and banks of streams and from around the piers and abutments of bridges. Different materials scour at
different rates. Loose granular soils are rapidly eroded by flowing water, while cohesive or cemented soils are
more scour-resistant. However, ultimate scour in cohesive or cemented soils can be as deep as scour in sandbed streams. Under constant flow conditions, scour will reach maximum depth in sand-bed and gravel-bed
material in hours; cohesive bed material in days; glacial till, sandstones, and shale in months; limestone in
years, and dense granite in centuries. Under flow conditions typical of actual bridge crossings, several floods
may be needed to attain maximum scour.
Determining the magnitude of scour is complicated by the cyclic nature of the scour process. Scour can be
deepest near the peak of a flood, but hardly visible as floodwaters recede and scour holes refill with sediment.
3.4.1.2 Clear-Water and Live-Bed Scour
There are two conditions for scour at a bridge: clear-water and live-bed scour. Clear-water scour occurs when
there is no movement of the bed material in the flow upstream of the crossing or the bed material being
transported in the upstream reach is transported in suspension through the scour hole at the pier or abutment
at less than the capacity of the flow. At the pier or abutment the acceleration of the flow and vortices created by
these obstructions cause the bed material around them to move. Live-bed scour occurs when there is transport
of bed material from the upstream reach into the crossing. Live-bed local scour is cyclic in nature; that is, the
scour hole that develops during the rising stage of a flood refills during the falling stage.
Typical clear-water scour situations include (1) coarse-bed material streams, (2) flat gradient streams during
low flow, (3) local deposits of larger bed materials that are larger than the biggest fraction being transported by
the flow (rock riprap is a special case of this situation), (4) armored streambeds where the only locations that
tractive forces are adequate to penetrate the armor layer are at piers and/or abutments, and (5) vegetated
channels or overbank areas.
During a flood event, bridges over streams with coarse-bed material are often subjected to clear-water scour at
low discharges, live-bed scour at the higher discharges and then clear-water scour at the lower discharges on
the falling stages. Clear-water scour reaches its maximum over a longer period of time than live-bed scour
(Figure 1-3-4). This is because clear-water scour occurs mainly in coarse-bed material streams. In fact, clearwater scour may not reach a maximum until after several floods. Maximum clear-water pier scour is about 10
percent greater than the equilibrium local live-bed pier scour.
1
Sections 3.4 through 3.6 contain condensed material from Federal Highway Association (FHWA), U.S. Army Corps of Engineers
(USACE) and American Society of Civil Engineers (ASCE) publications; primarily FHWA HEC-11, HEC-14, HEC-18, HEC-20, HEC-23,
HDS-2 and HDS-6. For more detailed analysis and design information, refer to these organizations and publications. The bibliography at
the end of each subsection contains additional references.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-20
AREMA Manual for Railway Engineering
Natural Waterways
Figure 1-3-4. Pier Scour Depth in a Sand-bed Stream as a Function of Time
Live-bed pier scour in sand-bed streams with a dune bed configuration fluctuates about the equilibrium scour
depth (Figure 1-3-4). This is due to the variability of the bed material sediment transport in the approach flow
when the bed configuration of the stream is dunes. However, with the exception of crossings over large rivers
(i.e., the Mississippi, Columbia, etc.), the bed configuration in sand-bed streams will plane out during flood
flows due to the increase in velocity and shear stress. For general practice, the maximum depth of pier scour is
approximately 10 percent greater than equilibrium scour. For a discussion of bedforms in alluvial channel flow,
see Chapter 3 of HDS 6.
1
3
3.4.2 LONG-TERM ELEVATION STREAMBED CHANGES (AGGRADATION AND
DEGRADATION) (2005)
Aggradation and degradation are long-term streambed elevation changes due to natural or man-induced causes
which can affect the reach of the river on which the bridge is located. Aggradation involves the deposition of
material eroded from the channel or watershed upstream of the bridge; whereas, degradation involves the
lowering or scouring of the streambed due to a deficit in sediment supply from upstream.
Long-term bed elevation changes may be the natural trend of the stream or the result of some modification to
the stream or watershed. The streambed may be aggrading, degrading, or in relative equilibrium in the vicinity
of the bridge crossing. Long-term aggradation and degradation do not include the cutting and filling of the
streambed in the vicinity of the bridge that might occur during a runoff event (contraction and local scour). A
long-term trend may change during the life of the bridge.
These long-term changes are the result of modifications to the stream or watershed. Such changes may be the
result of natural processes or human activities. The engineer must assess the present state of the stream and
watershed and then evaluate potential future changes in the river system. From this assessment, the longterm streambed changes must be estimated.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-21
4
Roadway and Ballast
3.4.3 CONTRACTION SCOUR (2005)
Contraction scour occurs when the flow area of a stream at flood stage is reduced, either by a natural
contraction of the stream channel or by a bridge. It also occurs when overbank flow is forced back to the
channel by railway embankments at the approaches to a bridge. From continuity, a decrease in flow area
results in an increase in average velocity and bed shear stress through the contraction. Hence, there is an
increase in erosive forces in the contraction and more bed material is removed from the contracted reach than
is transported into the reach. This increase in transport of bed material from the reach lowers the natural bed
elevation. As the bed elevation is lowered, the flow area increases and, in the riverine situation, the velocity
and shear stress decrease until relative equilibrium is reached; i.e., the quantity of bed material that is
transported into the reach is equal to that removed from the reach, or the bed shear stress is decreased to a
value such that no sediment is transported out of the reach. Contraction scour, in a natural channel or at a
bridge crossing, involves removal of material from the bed across all or most of the channel width and can occur
as either clear-water or live-bed scour.
Live-bed contraction scour is typically cyclic; for example, the bed scours during the rising stage of a runoff
event and fills on the falling stage. The cyclic nature of contraction scour causes difficulties in determining
contraction scour depths after a flood. The contraction of flow at a bridge can be caused by either a natural
decrease in flow area of the stream channel or by abutments projecting into the channel and/or piers blocking a
portion of the flow area. Contraction can also be caused by the approaches to a bridge cutting off floodplain
flow. This can cause clear-water scour on a setback portion of a bridge section or a relief bridge because the
floodplain flow does not normally transport significant concentrations of bed material sediments. This clearwater picks up additional sediment from the bed upon reaching the bridge opening. In addition, local scour at
abutments may well be greater due to the clear-water floodplain flow returning to the main channel at the end
of the abutment.
Other factors that can cause contraction scour are (1) natural stream constrictions, (2) long railroad
approaches to the bridge over the floodplain, (3) ice formations or jams, (4) natural berms along the banks due
to sediment deposits, (5) debris, (6) vegetative growth in the channel or floodplain, and (7) pressure flow.
3.4.4 LOCAL SCOUR (2005)
Local scour involves removal of material from around piers, abutments, spurs, and embankments. Local scour
can be either clear-water or live-bed scour. The basic mechanism causing local scour at piers or abutments is
the formation of vortices (known as the horseshoe vortex) at their base (Figure 1-3-5). The horseshoe vortex
results from the pileup of water on the upstream surface of the obstruction and subsequent acceleration of the
flow around the nose of the pier or abutment. The action of the vortex removes bed material from around the
base of the obstruction. The transport rate of sediment away from the base region is greater than the transport
rate into the region, and, consequently, a scour hole develops. As the depth of scour increases, the strength of
the horseshoe vortex is reduced, thereby reducing the transport rate from the base region. Eventually, for livebed local scour, equilibrium is reestablished between bed material inflow and outflow and scouring ceases. For
clear-water scour, scouring ceases when the shear stress caused by the horseshoe vortex equals the critical
shear stress of the sediment particles at the bottom of the scour hole.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-22
AREMA Manual for Railway Engineering
Natural Waterways
Figure 1-3-5. Schematic Representation of Scour at a Cylindrical Pier
1
In addition to the horseshoe vortex around the base of a pier, there are vertical vortices downstream of the pier
called the wake vortex (Figure 1-3-5). Both the horseshoe and wake vortices remove material from the pier
base region. However, the intensity of wake vortices diminishes rapidly as the distance downstream of the pier
increases. Therefore, immediately downstream of a long pier there is often deposition of material.
Factors which affect the magnitude of local scour depth at piers and abutments are (1) velocity of the approach
flow, (2) depth of flow, (3) width of the pier, (4) discharge intercepted by the abutment and returned to the main
channel at the abutment (in laboratory flumes this discharge is a function of projected length of an abutment
into the flow), (5) length of the pier if skewed to flow, (6) size and gradation of bed material, (7) angle of attack
of the approach flow to a pier or abutment, (8) shape of a pier or abutment, (9) bed configuration, and (10) ice
formation or jams and debris.
3
3.4.5 LATERAL STREAM MIGRATION (2005)
4
In addition to the types of scour mentioned above, naturally occurring lateral migration of the main channel of
a stream within a floodplain may affect the stability of piers in a floodplain, erode abutments or the approach
embankments, or change the total scour by changing the flow angle of attack at piers and abutments. Factors
that affect lateral stream movement also affect the stability of a bridge foundation.
Streams are dynamic. Areas of flow concentration continually shift banklines, and in meandering streams
having an "S-shaped" planform, the channel moves both laterally and downstream. A braided stream has
numerous channels which are continually changing. In a braided stream, the deepest natural scour occurs
when two channels come together or when the flow comes together downstream of an island or bar. This scour
depth has been observed to be 1 to 2 times the average flow depth.
A bridge is static. It fixes the stream at one place in time and space. A meandering stream whose channel
moves laterally and downstream into the bridge reach can erode the approach embankment and can affect
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-23
Roadway and Ballast
contraction and local scour because of changes in flow direction. A braided stream can shift under a bridge and
have two channels come together at a pier or abutment, increasing scour.
Factors that affect lateral shifting of a stream and the stability of a bridge are the geomorphology of the stream,
location of the crossing on the stream, flood characteristics, the characteristics of the bed and bank material,
and wash load. It is difficult to anticipate when a change in planform may occur. It may be gradual or the
result of a single major flood event. Also, the direction and magnitude of the movement of the stream are not
easily predicted. While it is difficult to evaluate the vulnerability of a bridge due to changes in planform, it is
important to incorporate potential planform changes into the design of new bridges and the design of
countermeasures for existing bridges.
Countermeasures for lateral shifting and instability of the stream may include changes in the bridge design,
construction of river control works, protection of abutments with riprap, or careful monitoring of the river in a
bridge inspection program. Serious consideration should be given to placing footings/foundations
located on floodplains at elevations the same as those located in the main channel. Control of
lateral shifting requires river training works, bank stabilizing by riprap, and/or guide banks.
3.4.6 TOTAL SCOUR (2005)
Total scour at a railroad crossing is comprised of three components:
(1) Long-term degradation of the river bed
(2) Contraction scour at the bridge
(3) Local scour at the piers or abutments
These three scour components are added to obtain the total scour at a pier or abutment. This assumes that
each component occurs independent of the other. Considering the components additive adds some
conservatism to the design. In addition, lateral migration of the stream must be assessed when evaluating
total scour at bridge piers and abutments.
3.4.7 REFERENCES FOR SECTION 3.4 (2005)
Richardson, E.V. and Davis, S.R., 2001. "Evaluating Scour at Bridges," Fourth Edition, Report FHWA NHI 01001, Federal Highway Administration, Hydraulic Engineering Circular No. 18, U.S. Department of
Transportation, Washington, D.C.
Richardson, E.V., Simons, D.B., and Lagasse, P.F., 2001. "River Engineering for Highway Encroachments –
Highways in the River Environment," Report FHWA NHI 01-004, Federal Highway Administration, Hydraulic
Design Series No. 6, Washington, D.C.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-24
AREMA Manual for Railway Engineering
Natural Waterways
SECTION 3.5 CALCULATING SCOUR
3.5.1 PREDICTING AGGRADATION AND DEGRADATION (2005)
3.5.1.1 Long-Term Bed Elevation Changes
Long-term bed elevation changes may be the natural trend of the stream or may be the result of some
modification to the stream or watershed. The streambed may be aggrading, degrading, or in relative
equilibrium in the vicinity of the bridge crossing. The problem for the engineer is to estimate the long-term bed
elevation changes that will occur during the life of the structure.
Factors that affect long-term bed elevation changes are dams and reservoirs (up- or downstream of the bridge),
changes in watershed land use (urbanization, deforestation, etc.), channelization, cutoffs of meander bends
(natural or man-made), changes in the downstream channel base level (control), gravel mining from the
streambed, diversion of water into or out of the stream, natural lowering of the fluvial system, movement of a
bend and bridge location with respect to stream planform, and stream movement in relation to the crossing.
Tidal ebb and flood may degrade a coastal stream; whereas, littoral drift may result in aggradation. The
elevation of the bed under bridges over a tributary to a larger stream will follow the trend of the larger stream
unless there are controls. Controls could be bedrock, dams, culverts or other structures. The changes in bed
elevation decrease the further upstream the bridge is from the confluence with another stream or from other
bed elevation controls.
The U.S. Army Corps of Engineers (USACE), U.S. Geological Survey (USGS), and other Federal and State
agencies should be contacted concerning documented long-term streambed variations. If no data exist or if
such data require further evaluation, an assessment of long-term streambed elevation changes for riverine
streams should be made using the principles of river mechanics. Such an assessment requires the
consideration of all influences upon the bridge crossing, i.e., runoff from the watershed to a stream (hydrology),
sediment delivery to the channel (watershed erosion), sediment transport capacity of a stream (hydraulics), and
response of a stream to these factors (geomorphology and river mechanics). Significant morphologic impacts
can result from human activities. The assessment of the impact of human activities requires a study of the
history of the river, as well as a study of present water and land use and stream control activities.
1
3
3.5.1.2 Estimating Long-Term Aggradation and Degradation
The following sections outline procedures that can assist in identifying long-term trends in vertical stability.
4
Bridge Inspection Records
The bridge inspection reports for railroad or highway bridges on the stream where a new or replacement bridge
is being designed are an excellent source of data on long-term aggradation or degradation trends. Also,
inspection reports for bridges crossing streams in the same area or region should be studied. Railroad bridges
sometimes have records with a long history going back 100 years or more that document streambed conditions
during original construction. For most highway bridges, the biannual inspection includes taking the elevation
and/or cross section of the streambed under the bridge. These elevations are usually referenced to the bridge,
but these relative bed elevations will show trends and can be referenced to sea level elevations. Successive
cross sections from a series of bridges in a stream reach can be used to construct longitudinal streambed
profiles through the reach.
Gaging Station Records
The USGS and many State Water Resource and Environmental agencies maintain gaging stations to measure
stream flow. In the process they maintain records from which the aggradation or degradation of the streambed
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-25
Roadway and Ballast
can be determined. Gaging station records at the bridge site, on the stream to be bridged and in the area or
region can be used.
Where an extended historical record is available, one approach to using gaging station records to determine
long-term bed elevation change is to plot the change in stage through time for a selected discharge. This
approach is often referred to as establishing a "specific gage" record.
Figure 1-3-6 shows a plot of specific gage data for a discharge of 500 cfs from about 1910 to 1980 for Cache
Creek in California. Cache Creek has experienced significant gravel mining with records of gravel extraction
quantities available since about 1940. When the historical record of cumulative gravel mining is compared to
the specific gage plot, the potential impacts are apparent. The specific gage record shows more than 10 ft of
long-term degradation in a 70-year period.
Figure 1-3-6. Specific Gage Data for Cache Creek, California
Geology and Stream Geomorphology
The geology and geomorphology of the site needs to be studied to determine the potential for long-term bed
elevation changes at the bridge site. Quantitative techniques for streambed aggradation and degradation
analyses are covered in detail in HEC-20. These techniques include:
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-26
AREMA Manual for Railway Engineering
Natural Waterways
• Incipient motion analysis
• Analysis of armoring potential
• Equilibrium slope analysis
• Sediment continuity analysis
Sediment transport concepts and equations are discussed in detail in HDS 6.
Computer Models
Sediment transport computer models can be used to determine long-term aggradation or degradation trends.
These computer models route sediment down a channel and adjust the channel geometry to reflect imbalances
in sediment supply and transport capacity. The BRI-STARS and HEC-6 models are examples of sediment
transport models that can be used for single event or long-term estimates of changes in bed elevation. The
information needed to run these models includes:
• Channel and floodplain geometry
• Structure geometry
1
• Roughness
• Geologic or structural vertical controls
• Downstream water surface relationship
3
• Event or long-term inflow hydrographs
• Tributary inflow hydrographs
• Bed material gradations
• Upstream sediment supply
4
• Tributary sediment supply
• Selection of appropriate sediment transport relationship
• Depth of alluvium
These models perform hydraulic and sediment transport computations on a cross section basis and adjust the
channel geometry prior to proceeding with the next time step. The actual flow hydrograph can be used as
input.
Aggradation, Degradation, and Total Scour
Using all the information available estimate the long-term bed elevation change at the bridge site for the design
life of the bridge. Usually, the design life is 100 years. If the estimate indicates that the stream will
degrade, use the elevation after degradation as the base elevation for contraction and local scour.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-27
Roadway and Ballast
That is, total scour must include the estimated long-term degradation. If the estimate indicates that
the stream will aggrade, then (1) make note of this fact to inspection and maintenance personnel, and (2) use
existing ground elevation as the base for contraction and local scour.
3.5.2 PREDICTING LATERAL MIGRATION (2005)
3.5.2.1 Initiation of Meanders
Although there is no completely satisfactory explanation of how or why meanders develop, it is known that
meanders are initiated by localized bank retreat which alternates from one side of the channel to the other in a
more or less regular pattern. The primary features of the flow pattern through meander bends are:
• Superelevation of the water surface against the outside (convex) bank (Figure 1-3-7A)
• Transverse current directed towards the outer bank at the surface and towards the inner bank at the
bed producing a secondary circulation additional to the main downstream flow (Figure 1-3-7B)
• Maximum-velocity current which moves from near the inner bank at the bend entrance to near the
outer bank at the bend exit, crossing the channel at the zone of maximum bend curvature
The transverse current and the primary downstream flow component combine to produce the helicoidal motion
to the flow. The superelevation of the water surface against the outer bank of a bend produces a locally steep
downstream energy gradient and, in turn, a zone of maximum boundary shear stress (b) in close proximity to
the outer bank just downstream of the bend apex (Figure 1-3-7A).
Secondary currents, which are usually weaker than primary ones, influence the distribution of velocity and
boundary shear stress. The bend cross-section can be divided into three regions relative to the pattern of
secondary flow (Figure 1-3-7B):
• Mid-channel region, helicoidal flow is well established passing nearly 90 percent of the flow
• Cell of opposite circulation develops in the outer bank region: the strength of this cell increases with
discharge, the steepness of the bar, and the acuteness of the bend
• Inner bank region where shoaling over the point bar induces a net outward flow, forcing the core of
maximum velocity more rapidly toward the outer bank; increasing stage tends to reduce the shoaling,
allowing an inward component of near-bed flow over the bar top
The location and timing of the flow pattern varies with discharge, bend tightness, and cross-sectional form.
Primary currents are dominant at high discharges because the main flow follows a straighter path, but
secondary currents are relatively strong at intermediate discharges.
The pattern of primary and secondary currents influences the distribution of erosion and deposition in
meanders. In general, erosion in the bend is concentrated along the outer bank downstream of the bend apex
where the currents are strongest, while point bar building predominates in a parallel position along the
opposite bank, with material supplied by longitudinal and transverse currents. This produces a largely
downvalley component to meander migration.
3.5.2.2 Evaluation and Prediction of Lateral Migration
In general, most streams are sinuous to some degree and the majority of bank retreat and lateral migration
occurs along meander bends. As such, the following discussion on evaluating and predicting lateral migration
will focus on meander bends. One of the most practical methods for determining lateral stability and migration
rates involves the analysis of sequential historic aerial photographs, maps, and surveys (Lagasse et al. 2003).
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-28
AREMA Manual for Railway Engineering
Natural Waterways
1
Figure 1-3-7. Flow Patterns in Meanders
(A) Location of maximum boundary shear stress (b), in a bend with a well-developed point bar
(B) Secondary flow at a bend apex showing the outer bank cell and the shoaling-induced
outward flow over the point bar.
The most accurate means of measuring changes in channel geometry and lateral adjustments is through
repetitive surveys of the channel cross section. However, this data is rarely available. The next easiest and
relatively accurate method of determining migration rates and direction is through the comparison of
sequential historical aerial photography (photos), maps, and surveys. Accuracy in such an analysis is greatly
dependent on the period over which migration is evaluated, the amount and magnitude of internal and external
perturbations forced on the system over time, and the number and quality of sequential aerial photos and
maps. The analysis will be much more accurate for a channel that has coverage consisting of multiple data sets
(aerial photos, maps, and surveys) covering a long period of time (several tens of years to more than 100 years)
versus an analysis consisting of only two or three data sets covering a short time period (several years to a few
tens of years). Predictions of migration for channels that have been extensively modified or have undergone
major adjustments attributable to extensive land use changes will be much less reliable than those made for
channels in relatively stable watersheds.
Historical aerial photos and maps can be obtained from a number of federal, state, and local agencies (Lagasse
et al. 2003). Extensive topographic map coverage of the United States at a variety of scales can be obtained
from the local or regional offices of the U.S. Geological Survey. In general, both air photos and maps are
required to perform a comprehensive and relatively accurate meander migration assessment. Since the scale of
aerial photography is often approximate, contemporary maps are usually needed to accurately determine the
true scale of air photos. Distortion of the image on aerial photos is also a common problem and becomes greater
as one moves further away from the center of the photo. Expensive equipment, which is generally needed to
rectify and eliminate aerial photo distortion, is often unavailable, so distortion and scale differences must be
accounted for by some other means. The scale problem is easily rectified through the use of multiple distance
measurements taken between common reference points on the photos and maps. The measurements of
distance between several reference-point pairs common to both the photos and maps are then averaged to
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-29
3
4
Roadway and Ballast
define an average scale for the photos. Common reference points can include cultural features such as building
corners, roads or fences and their intersections, irrigation channels and canals, or natural features such as
isolated rock outcrops, large boulders, and trees, drainages and stream confluences, and the irregular
boundaries of water bodies.
The accurate delineation of a bankline on aerial photos is primarily dependent on the density of vegetation at
the top of the bank. Top bank is easily defined if stereo-pairs of photos are available. However, single photos
can be used relatively easily if one knows what to look for. For banks with little or no vegetation, the top of the
bank is easily identified. The abrupt change between the water and the top of the bank along the convex bank
in a bend or an eroding cutbank is defined by an abrupt change in the contrast and color (color photo) or gray
tone (black and white photo). Usually the water is significantly darker than the top of bank. Along the concave
or inner bank of a bend, exposed bar sediment is lighter colored than the river or the top of bank. The top bank
along a point bar is usually defined by persistent vegetation such as mature trees and shrubs.
Where vegetation becomes increasingly dense along a bank, small sections of the top of the bank may be visible
such that a line can be drawn connecting the sections. Often, the top of the bank may be completely obscured
by vegetation and one may be required to locate the top of the bank by approximation. In this case, one can
assume that the trunks of the largest trees growing along the river are nearly vertical and are located just
landward of the top of the bank. Therefore, a line that approximates the top of the bank may be drawn just
riverward of the center of the tree. The amount of error involved with this method increases with decreasing
stream size.
If the density of vegetation along a stream is such that an accurate delineation of the top of the bank cannot be
made, then the use of the channel centerline may be required. The centerline is drawn with reference to
bankfull conditions. Therefore, the channel centerline can and often does cross the exposed portions of point
bars. Usually the channel centerline can be delineated more easily than a bankline masked by vegetation since
the centerline can be drawn equidistant from the edge of mature vegetation on either side of the channel.
There are three general methods of assessing lateral bank erosion and meander migration using maps and
aerial photographs. The following discussion will deal with assessments using air photos, but the same
methods can be used when making assessments or measurements from maps. In order of increasing
complexity and accuracy, distances of lateral retreat can be:
• Estimated by visual comparison of two air photos flown at different times
• Measured by scaling distances directly from the bank to fixed reference points common to both
photographs
• Measured on a drawing on which historic channel banklines taken from sequential air photos are
superimposed at the same scale
The first method provides a preliminary assessment of stability, especially where significant changes in bank
position have occurred. The second method requires measurements made along a line described by two
reference points on either side of the bank that are common to both photos. The second method will usually
only provide a few accurate measurements along the bank, depending on the number of reference points and
the number of lines that can be drawn across the bend. Additional problems may be associated with the
location of the lines since they may not be perpendicular to bank retreat nor allow a measurement at the point
of maximum retreat.
The third method is relatively easy and accurate. This method requires that the banklines and the common
reference points from each historic air photo be traced onto a transparent or semi-transparent sheet after they
have been enlarged or reduced to a common scale. The channel centerline can also be delineated on the same
sheet at the same time. Then, each bankline or centerline is transferred to and superimposed on a common
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-30
AREMA Manual for Railway Engineering
Natural Waterways
sheet such that a sequential comparison of the banklines or centerlines can be made. The total bankline area
eroded can be measured for each period and divided by the bankline length to define the average bank retreat.
Dividing either the maximum distance or the average distance of bank retreat by the number of years between
air photos results in a maximum or average migration rate, respectively. Drawing a line perpendicular to
centerline at the location of maximum retreat defines the direction of maximum retreat. This process is
repeated for each series of sequential photos. Based on the measurements between years, one may be able to
define migration rates relative to significant hydrologic or geomorphic events. Overall rates can also be
determined by summing the distances and dividing by the total number of years between the earliest and latest
photos.
3.5.3 ESTIMATING CONTRACTION SCOUR (2005)
3.5.3.1 Contraction Scour Conditions
Contraction scour equations are based on the principle of conservation of sediment transport (continuity). In
the case of live-bed scour, the fully developed scour in the bridge cross section reaches equilibrium when
sediment transported into the contracted section equals sediment transported out. As scour develops, the
shear stress in the contracted section decreases as a result of a larger flow area and decreasing average velocity.
For live-bed scour, maximum scour occurs when the shear stress reduces to the point that sediment transported
in equals the bed sediment transported out and the conditions for sediment continuity are in balance. For
clear-water scour, the transport into the contracted section is essentially zero and maximum scour occurs when
the shear stress reduces to the critical shear stress of the bed material in the section. Normally, for both livebed and clear-water scour the width of the contracted section is constrained and depth increases until the
limiting conditions are reached.
1
Live-bed contraction scour occurs at a bridge when there is transport of bed material in the upstream reach
into the bridge cross section. With live-bed contraction scour the area of the contracted section increases until,
in the limit, the transport of sediment out of the contracted section equals the sediment transported in.
Clear-water contraction scour occurs when (1) there is no bed material transport from the upstream reach
into the downstream reach, or (2) the material being transported in the upstream reach is transported through
the downstream reach mostly in suspension and at less than capacity of the flow. With clear-water contraction
scour the area of the contracted section increases until, in the limit, the velocity of the flow (V) or the shear
stress (Jo) on the bed is equal to the critical velocity (Vc) or the critical shear stress (Jc) of a certain particle size
(D) in the bed material.
There are four conditions (cases) of contraction scour at bridge sites depending on the type of contraction, and
whether there is overbank flow or relief bridges. Regardless of the case, contraction scour can be evaluated
using two basic equations: (1) live-bed scour, and (2) clear-water scour. For any case or condition, it is only
necessary to determine if the flow in the main channel or overbank area upstream of the bridge, or approaching
a relief bridge, is transporting bed material (live-bed) or is not (clear-water), and then apply the appropriate
equation with the variables defined according to the location of contraction scour (channel or overbank).
To determine if the flow upstream of the bridge is transporting bed material, calculate the critical velocity for
beginning of motion Vc of the D50 size of the bed material being considered for movement and compare it with
the mean velocity V of the flow in the main channel or overbank area upstream of the bridge opening. If the
critical velocity of the bed material is larger than the mean velocity (Vc > V), then clear-water contraction scour
will exist. If the critical velocity is less than the mean velocity (Vc < V), then live-bed contraction scour will
exist. To calculate the critical velocity use the following equation:
Vc = Kuy1/6D1/3
EQ 11
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-31
3
4
Roadway and Ballast
where:
Vc = Critical velocity above which bed material of size D and smaller will be transported, m/s
(ft/s)
y = Average depth of flow upstream of the bridge, m (ft)
D = Particle size for Vc, m (ft)
D50 = Particle size in a mixture of which 50 percent are smaller, m (ft)
Ku = 6.19 SI units
Ku = 11.17 English units
The D50 is taken as an average of the bed material size in the reach of the stream upstream of the bridge. It is
a characteristic size of the material that will be transported by the stream. Normally this would be the bed
material size in the upper 1 ft of the stream bed.
Live-bed contraction scour depths may be limited by armoring of the bed by large sediment
particles in the bed material or by sediment transport of the bed material into the bridge crosssection. Under these conditions, live-bed contraction scour at a bridge can be determined by
calculating the scour depths using both the clear-water and live-bed contraction scour equations
and using the smaller of the two depths.
3.5.3.2 Contraction Scour Cases
Four conditions (cases) of contraction scour are commonly encountered:
Case 1. Involves overbank flow on a floodplain being forced back to the main channel by the approaches to
the bridge. Case 1 conditions include:
a.
The river channel width becomes narrower either due to the bridge abutments projecting into the
channel or the bridge being located at a narrowing reach of the river (Figure 1-3-8);
b. No contraction of the main channel, but the overbank flow area is completely obstructed by an
embankment (Figure 1-3-9); or
c.
Abutments are set back from the stream channel (Figure 1-3-10).
Case 2. Flow is confined to the main channel (i.e., there is no overbank flow). The normal river channel
width becomes narrower due to the bridge itself or the bridge site is located at a narrower reach of the river
(Figure 1-3-11 and Figure 1-3-12).
Case 3. A relief bridge in the overbank area with little or no bed material transport in the overbank area
(i.e., clear-water scour) (Figure 1-3-13).
Case 4. A relief bridge over a secondary stream in the overbank area with bed material transport (similar to
Case 1) (Figure 1-3-14).
Notes:
(1) Cases 1, 2, and 4 may either be live-bed or clear-water scour depending on whether there is bed
material transport from the upstream reach into the bridge reach during flood flows. To determine
if there is bed material transport compute the critical velocity at the approach section for the D50 of
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-32
AREMA Manual for Railway Engineering
Natural Waterways
the bed material using the equation given above and compare to the mean velocity at the approach
section. To determine if the bed material will be washed through the contraction determine the ratio
of the shear velocity (V*) in the contracted section to the fall velocity (T) of the D50 of the bed
material being transported from the upstream reach (see the definition of V* in the live-bed
contraction scour equation). If the ratio is much larger than 2, then the bed material from the
upstream reach will be mostly suspended bed material discharge and may wash through the
contracted reach (clear-water scour).
(2) Case 1c is very complex. The depth of contraction scour depends on factors such as (1) how far
back from the bank line the abutment is set, (2) the condition of the overbank (is it easily eroded, are
there trees on the bank, is it a high bank, etc.), (3) whether the stream is narrower or wider at the
bridge than at the upstream section, (4) the magnitude of the overbank flow that is returned to the
bridge opening, and (5) the distribution of the flow in the bridge section, and (6) other factors.
The main channel under the bridge may be live-bed scour; whereas, the set-back overbank area may
be clear-water scour.
WSPRO or HEC-RAS can be used to determine the distribution of flow between the main channel
and the set-back overbank areas in the contracted bridge opening. However, the distribution of flow
needs to be done with care. Studies by Chang and Sturm (HEC-18) have shown that conveyance
calculations do not properly account for the flow distribution under the bridge.
1
3
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-33
Roadway and Ballast
Figure 1-3-8. Case 1A: Abutments Project into Channel
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-34
AREMA Manual for Railway Engineering
Natural Waterways
1
3
4
Figure 1-3-9. Case 1B: Abutments at Edge of Channel
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-35
Roadway and Ballast
Figure 1-3-10. Case 1C: Abutments Set Back from Channel
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-36
AREMA Manual for Railway Engineering
Natural Waterways
1
3
4
Figure 1-3-11. Case 2A: River Narrows
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-37
Roadway and Ballast
Figure 1-3-12. Case 2B: Bridge Abutments and/or Piers Constrict Flow
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-38
AREMA Manual for Railway Engineering
Natural Waterways
1
Figure 1-3-13. Case 3: Relief Bridge Over Floodplain
3
4
Figure 1-3-14. Case 4: Relief Bridge Over Secondary Stream
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-39
Roadway and Ballast
If the abutment is set back only a small distance from the bank (less than 3 to 5 times the average
depth of flow through the bridge), there is the possibility that the combination of contraction scour
and abutment scour may destroy the bank. Also, the two scour mechanisms are not independent.
Consideration should be given to using a guide bank and/or protecting the bank and bed under the
bridge in the overflow area with rock riprap. See Section 3.6 for guidance on designing rock riprap.
(3) Case 3 may be clear-water scour even though the floodplain bed material is composed of sediments
with a critical velocity that is less than the flow velocity in the overbank area. The reasons for this
are (1) there may be vegetation growing part of the year, and (2) if the bed material is fine
sediments, the bed material discharge may go into suspension (wash load) at the bridge and not
influence contraction scour.
(4) Case 4 is similar to Case 3, but there is sediment transport into the relief bridge opening (live-bed
scour). This case can occur when a relief bridge is over a secondary channel on the floodplain.
Hydraulically this is no different from Case 1, but analysis is required to determine the floodplain
discharge associated with the relief opening and the flow distribution going to and through the relief
bridge. This information could be obtained from WSPRO or HEC-RAS.
3.5.3.3 Live-Bed Contraction Scour
A modified version of Laursen's 1960 equation for live-bed scour at a long contraction is recommended to
predict the depth of scour in a contracted section. The equation assumes that bed material is being transported
from the upstream section.
y2 ⎛ Q2 ⎞
=⎜
⎟
y1 ⎝ Q 1 ⎠
6 /7
⎛ W1 ⎞
⎜
⎟
⎝ W2 ⎠
k1
EQ 12
ys = y2 - yo = (average contraction scour depth)
EQ 13
where:
y1 = Average depth in the upstream main channel, m (ft)
y2 = Average depth in the contracted section,m (ft)
yo = Existing depth in the contracted section before scour, m (ft) (see Note 7)
Q1 = Flow in the upstream channel transporting sediment, m3/s (ft3/s)
Q2 = Flow in the contracted channel, m3/s (ft3/s)
W1 = Bottom width of the upstream main channel that is transporting bed material, m (ft)
W2 = Bottom width of the main channel in the contracted section less pier width(s), m (ft)
k1 = Exponent determined below
V*/ T
k1
Mode of Bed Material Transport
<0.50
0.59
Mostly contact bed material discharge
0.50 to 2.0
0.64
Some suspended bed material discharge
>2.0
0.69
Mostly suspended bed material discharge
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-40
AREMA Manual for Railway Engineering
Natural Waterways
V* = ((gy1S1)1/2, shear velocity in the upstream section, m/s (ft/s)
 Fall velocity of bed material based on the D50, m/s (Figure 1-3-15)
g = Acceleration of gravity (9.81 m/s2) (32.2 ft/s2)
S1 = Slope of energy grade line of main channel, m/m (ft/ft)
 Shear stress on the bed, Pa (N/m2) (lb/ft2)
 Density of water (1000 kg/m3) (1.94 slugs/ft3)
Notes:
(1) Q2 may be the total flow going through the bridge opening as in cases 1a and 1b. It is not the total
flow for Case 1c. For Case 1c contraction scour must be computed separately for the main channel
and the left and/or right overbank areas.
(2) Q1 is the flow in the main channel upstream of the bridge, not including overbank flows.
(3) W1 and W2 are not always easily defined. In some cases, it is acceptable to use the topwidth of the
main channel to define these widths. Whether topwidth or bottom width is used, it is important to
be consistent so that W1 and W2 refer to either bottom widths or top widths.
1
3
4
Figure 1-3-15. Fall Velocity of Sand-sized Particles with Specific Gravity of 2.65 in Metric Units
(4) The average width of the bridge opening (W2) is normally taken as the bottom width, with the width
of the piers subtracted.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-41
Roadway and Ballast
(5) Laursen's equation will overestimate the depth of scour at the bridge if the bridge is located at the
upstream end of a natural contraction or if the contraction is the result of the bridge abutments and
piers. At this time, however, it is the best equation available.
(6) In sand channel streams where the contraction scour hole is filled in on the falling stage, the y0
depth may be approximated by y1. Sketches or surveys through the bridge can help in determining
the existing bed elevation.
(7) Scour depths with live-bed contraction scour may be limited by coarse sediments in the
bed material armoring the bed. Where coarse sediments are present, it is recommended
that scour depths be calculated for live-bed scour conditions using the clear-water scour
equation (given in the next section) in addition to the live-bed equation, and that the
smaller calculated scour depth be used.
3.5.3.4 Clear-Water Contraction Scour
The recommended clear-water contraction scour equation is:
EQ 14
EQ 15
ys = y2 - yo = (average contraction scour depth)
where:
y2 = Average equilibrium depth in the contracted section after contraction scour, m (ft)
yo = Average existing depth in the contracted section, m (ft)
Q = Discharge through the bridge or on the set-back overbank area at the bridge associated
with the width W, m3/s (ft3/s)
Dm = Diameter of the smallest nontransportable particle in the bed material (1.25 D50) in the
contracted section, m (ft)
D50 = Median diameter of bed material, m (ft)
W = Bottom width of the contracted section less pier widths, m (ft)
Ku = 0.025 SI units
Ku= 0.0077 English units
EQ 14 is a rearranged version of EQ 11.
Because D50 is not the largest particle in the bed material, the scoured section can be slightly
armored. Therefore, the Dm is assumed to be 1.25 D50. For stratified bed material the depth of
scour can be determined by using the clear-water scour equation sequentially with successive Dm
of the bed material layers.
3.5.3.5 Contraction Scour With Backwater
The live-bed contraction scour equation is derived assuming a uniform reach upstream and a long contraction
into a uniform reach downstream of the bridge. With live-bed scour the equation computes a depth after the
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-42
AREMA Manual for Railway Engineering
Natural Waterways
long contraction where the sediment transport into the downstream reach is equal to the sediment transport
out. The clear-water contraction scour equations are derived assuming that the depth at the bridge increases
until the shear-stress and velocity are decreased so that there is no longer any sediment transport. With the
clear-water equations it is assumed that flow goes from one uniform flow condition to another. Both equations
calculate contraction scour depth assuming a level water surface (ys = y2 -yo). A more consistent computation
would be to write an energy balance before and after the scour. For live-bed the energy balance would be
between the approach section (1) and the contracted section (2). Whereas, for clear-water scour it would be the
energy at the same section before (1) and after (2) the contraction scour.
Backwater, in extreme cases, can decrease the velocity, shear stress and the sediment transport in
the upstream section. This will increase the scour at the contracted section. The backwater can,
by storing sediment in the upstream section, change live-bed scour to clear-water scour.
3.5.4 ESTIMATING LOCAL PIER SCOUR (2005)
3.5.4.1 General
Local scour at piers is a function of bed material characteristics, bed configuration, flow characteristics, fluid
properties, and the geometry of the pier and footing. The bed material characteristics are granular or non
granular, cohesive or noncohesive, erodible or non erodible rock. Granular bed material ranges in size from silt
to large boulders and is characterized by the D50 and a coarse size such as the D84 or D90 size. Cohesive bed
material is composed of silt and clay, possibly with some sand which is bonded chemically. Rock may be solid,
massive, or fractured. It may be sedimentary or igneous and erodible or non erodible.
Flow characteristics of interest for local pier scour are the velocity and depth just upstream of the pier, the
angle the velocity vector makes to the pier (angle of attack), and free surface or pressure flow. Fluid properties
are viscosity, and surface tension which for the field case can be ignored.
Pier geometry characteristics are its type, dimensions, and shape. Types of piers include single column,
multiple columns, or rectangular; with or without friction or tip bearing piles; with or without a footing or pile
cap; footing or pile cap in the bed, on the surface of the bed, in the flow or under the deck out of the flow.
Important dimensions are the diameter for circular piers or columns, spacing for multiple columns, and width
and length for solid piers. Shapes include round, square or sharp nose, circular cylinder, group of cylinders, or
rectangular. In addition, piers may be simple or complex. A simple pier is a single shaft, column or multiple
columns exposed to the flow. Whereas, a complex pier may have the pier, footing or pile cap, and piles exposed
to the flow.
Local scour at piers has been studied extensively in the laboratory; however, there is limited field data. The
laboratory studies have been mostly of simple piers, but there have been some laboratory studies of complex
piers. Often the studies of complex piers are model studies of actual or proposed pier configurations. As a result
of the many laboratory studies, there are numerous pier scour equations. In general, the equations are for livebed scour in cohesionless sand-bed streams.
A graphical comparison of the more common equations is given in Figure 1-3-16. Some of the equations have
velocity as a variable, normally in the form of a Froude Number. However, some equations, such as Laursen's
do not include velocity. A Froude Number of 0.3 was used in Figure 1-3-16 for purposes of comparing
commonly used scour equations. Based on a comparison of the equations with the laboratory data and
available field data, the Colorado State University (CSU) equation is recommended to estimate pier scour.
3.5.4.2 Local Pier Scour Equation
To determine pier scour, an equation based on the CSU equation is recommended for both live-bed and clearwater pier scour. The equation predicts maximum pier scour depths. The equation is:
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-43
1
3
4
Roadway and Ballast
EQ 16
Figure 1-3-16. Comparison of Scour Equations for Variable Depth Ratios (y/a) (HEC-18)
As a Rule of Thumb, the maximum scour depth for round nose piers aligned with the flow is:
ys = 2.4 times the pier width (a) for Fr  0.8
EQ 17
ys = 3.0 times the pier width (a) for Fr > 0.8
In terms of ys/a, EQ 16 is:
EQ 18
where:
ys = Scour depth, m (ft)
y1 = Flow depth directly upstream of the pier, m (ft)
K1 = Correction factor for pier nose shape from Figure 1-3-17 and Table 1-3-10
K2 = Correction factor for angle of attack of flow from Table 1-3-11 or EQ 19
K3 = Correction factor for bed condition from Table 1-3-12
a = Pier width, m (ft)
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-44
AREMA Manual for Railway Engineering
Natural Waterways
L = Length of pier, m (ft)
Fr1 = Froude Number directly upstream of the pier = V1/(gy1)1/2
V1 = Mean velocity of flow directly upstream of the pier, m/s (ft/s)
g = Acceleration of gravity (9.81 m/s2) (32.2 ft/s2)
The correction factor, K2, for angle of attack of the flow, , is calculated using the following equation:
EQ 19
If L/a is larger than 12, use L/a = 12 as a maximum in EQ 19 and Table 1-3-11. Table 1-3-11 illustrates the
magnitude of the effect of the angle of attack on local pier scour.
1
Figure 1-3-17. Common Pier Shapes
3
Table 1-3-10. Correction Factor, K1, for Pier Nose Shape
Shape of Pier Nose
K1
(a) Square nose
1.1
(b) Round nose
1.0
(c) Circular cylinder
1.0
(d) Group of cylinders
1.0
(e) Sharp nose
0.9
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-45
Roadway and Ballast
Table 1-3-11. Correction Factor, K2, for Angle of Attack, , of the Flow
Angle
L/a=4
L/a=8
L/a=12
0
1.0
1.0
1.0
15
1.5
2.0
2.5
30
2.0
2.75
3.5
45
2.3
3.3
4.3
90
2.5
3.9
5.0
Angle = skew angle of flow
L = length of pier
Table 1-3-12. Increase in Equilibrium Pier Scour Depths, K3, for Bed Condition
Bed Condition
Dune Height m
K3
Clear-Water Scour
N/A
1.1
Plane bed and Antidune flow
N/A
1.1
Small Dunes
3 > H > 0.6
1.1
Medium Dunes
9>H>3
1.2 to 1.1
Large Dunes
H>9
1.3
Notes:
(1) The correction factor K1 for pier nose shape should be determined using Table 1-3-10 for angles of
attack up to 5 degrees. For greater angles, K2 dominates and K1 should be considered as
1.0. If L/a is larger than 12, use the values for L/a = 12 as a maximum in Table 1-3-11 and EQ 19.
(2) The values of the correction factor K2 should be applied only when the field conditions are such that
the entire length of the pier is subjected to the angle of attack of the flow. Use of this factor will
result in a significant over-prediction of scour if (1) a portion of the pier is shielded from the direct
impingement of the flow by an abutment or another pier; or (2) an abutment or another pier
redirects the flow in a direction parallel to the pier. For such cases, judgment must be exercised to
reduce the value of the K2 factor by selecting the effective length of the pier actually subjected to the
angle of attack of the flow. EQ 19 should be used for evaluation and design. Table 1-3-11 is intended
to illustrate the importance of angle of attack in pier scour computations and to establish a cutoff
point for K2 (i.e., a maximum value of 5.0).
(3) The correction factor K3 results from the fact that for plane-bed conditions, which is typical of most
bridge sites for the flood frequencies employed in scour design, the maximum scour may be 10
percent greater than computed with Equation 3.6. In the unusual situation where a dune bed
configuration with large dunes exists at a site during flood flow, the maximum pier scour may be
30 percent greater than the predicted equation value. This may occur on very large rivers, such as
the Mississippi. For smaller streams that have a dune bed configuration at flood flow, the dunes will
be smaller and the maximum scour may be only 10 to 20 percent larger than equilibrium scour. For
antidune bed configuration the maximum scour depth may be 10 percent greater than the computed
equilibrium pier scour depth (see HDS 6).
(4) Piers set close to abutments (for example at the toe of a spill through abutment) must be carefully
evaluated for the angle of attack and velocity of the flow coming around the abutment.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-46
AREMA Manual for Railway Engineering
Natural Waterways
3.5.4.3 Scour for Complex Pier Foundations
Most pier scour research has focused on solid piers with limited attention to determining scour depths for (1)
pile groups, (2) pile groups and pile caps, or (3) pile groups, pile caps and solid piers exposed to the flow. In the
general case, the flow could be obstructed by three substructure elements (scour-producing components), which
include the pier stem, the pile cap or footing, and the pile group. Reference to FHWA's HEC-18 is suggested for
methods and equations to determine scour depths for complex pier foundations.
3.5.4.4 Multiple Columns Skewed to the Flow
For multiple columns (illustrated as a group of cylinders in Figure 1-3-18) skewed to the flow, the scour depth
depends on the spacing between the columns. The correction factor for angle of attack would be smaller than
for a solid pier. Raudkivi in discussing effects of alignment states "...the use of cylindrical columns would
produce a shallower scour; for example, with five-diameter spacing the local scour can be limited to about 1.2
times the local scour at a single cylinder."
In application of EQ 16 with multiple columns spaced less than 5 pier diameters apart, the pier width 'a' is the
total projected width of all the columns in a single bent, normal to the flow angle of attack (Figure 1-3-18). For
example, three 2.0 m (6.6 ft) cylindrical columns spaced at 10.0 m (33 ft) would have an 'a' value ranging
between 2.0 and 6.0 m (6.6 and 33 ft), depending upon the flow angle of attack. This composite pier width
would be used in EQ 16 to determine depth of pier scour. The correction factor K1 in EQ 16 for the
multiple column would be 1.0 regardless of column shape. The coefficient K2 would also be equal to 1.0 since
the effect of skew would be accounted for by the projected area of the piers normal to the flow.
1
3
4
Figure 1-3-18. Multiple Columns Skewed to the Flow
The scour depth for multiple columns skewed to the flow can also be determined by determining the K2 factor
using EQ 19 and using it in EQ 16. The width "a" in EQ 16 would be the width of a single column.
If the multiple columns are spaced 5 diameter or greater apart; and debris is not a problem, limit
the scour depths to a maximum of 1.2 times the local scour of a single column.
The depth of scour for a multiple column bent will be analyzed in this manner except when addressing the
effect of debris lodged between columns. If debris is evaluated, it would be logical to consider the multiple
columns and debris as a solid elongated pier. The appropriate L/a value and flow angle of attack would then be
used to determine K2 in EQ 19.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-47
Roadway and Ballast
3.5.4.5 Scour From Debris on Piers
Debris (or ice) lodged on a pier can increase local scour at a pier. The debris may increase pier width and deflect
a component of flow downward. This increases the transport of sediment out of the scour hole. When floating
debris or ice is lodged on the pier, the scour depth can be estimated by assuming that the pier width is larger
than the actual width. The problem is in determining the increase in pier width to use in the pier scour
equation. At large depths, the effect of the debris or ice on scour depth should diminish. Debris and ice effects
on contraction scour can also be accounted for by estimating the amount of flow blockage (decrease in width of
the bridge opening) in the equations for contraction scour. Limited field measurements of scour at ice jams
indicate the scour can be as much as 10 to 30 ft.
3.5.4.6 Topwidth of Scour Holes
The topwidth of a scour hole in cohesionless bed material from one side of a pier or footing can be estimated
from the following equation:
EQ 20
where:
W = Topwidth of the scour hole from each side of the pier or footing, m (ft)
ys = Scour depth, m (ft)
K = Bottom width of the scour hole related to the depth of scour
 Angle of repose of the bed material ranging from about 30 to 44
The angle of repose of cohesionless material in air ranges from about 30× to 44×. Therefore, if the bottom
width of the scour hole is equal to the depth of scour ys (K = 1), the topwidth in cohesionless sand would vary
from 2.07 to 2.80 ys. At the other extreme, if K = 0, the topwidth would vary from 1.07 to 1.8 ys. Thus, the
topwidth could range from 1.0 to 2.8 ys and depends on the bottom width of the scour hole and composition of
the bed material. In general, the deeper the scour hole, the smaller the bottom width. In water, the angle of
repose of cohesionless material is less than the values given for air; therefore, a topwidth of 2.0 ys is suggested
for practical applications (Figure 1-3-19).
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-48
AREMA Manual for Railway Engineering
Natural Waterways
Figure 1-3-19. Topwidth of Scour Hole
1
3.5.5 EVALUATING LOCAL SCOUR AT ABUTMENTS (2005)
3.5.5.1 General
Scour occurs at abutments when the abutment and embankment obstruct the flow. Several causes of abutment
failures during post-flood field inspections of bridge sites have been documented:
3
• Overtopping of abutments or approach embankments
• Lateral channel migration or stream widening processes
• Contraction scour
4
• Local sour at one or both abutments
Abutment damage is often caused by a combination of these factors. Where abutments are set back from the
channel banks, especially on wide floodplains, large local scour holes have been observed with scour depths of
as much as four times the approach flow depth on the floodplain. As a general rule, the abutments most
vulnerable to damage are those located at or near the channel banks.
The flow obstructed by the abutment and approach railroad embankment forms a horizontal vortex starting at
the upstream end of the abutment and running along the toe of the abutment, and a vertical wake vortex at the
downstream end of the abutment (Figure 1-3-20).
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-49
Roadway and Ballast
Figure 1-3-20. Schematic Representation of Abutment Scour
Figure 1-3-21. Scour of Bridge Abutment and Approach Embankment
The vortex at the toe of the abutment is very similar to the horseshoe vortex that forms at piers, and the vortex
that forms at the downstream end is similar to the wake vortex that forms downstream of a pier. Research has
been conducted to determine the depth and location of the scour hole that develops for the horizontal (so called
horseshoe) vortex that occurs at the upstream end of the abutment, and numerous abutment scour equations
have been developed to predict this scour depth.
Abutment failures and erosion of the fill also occur from the action of the downstream wake vortex. However,
research and the development of methods to determine the erosion from the wake vortex has not been
conducted. An example of abutment and approach erosion of a bridge due to the action of the horizontal and
wake vortex is shown in Figure 1-3-21.
The types of failures described above are initiated as a result of the obstruction to the flow caused by the
abutment and railroad embankment and subsequent contraction and turbulence of the flow at the abutments.
There are other conditions that develop during major floods, particularly on wide floodplains, that are more
difficult to foresee but that need to be considered in the hydraulic analysis and design of the substructure:
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-50
AREMA Manual for Railway Engineering
Natural Waterways
• Gravel pits on the floodplain upstream of a structure can capture the flow and divert the main channel
flow out of its normal banks into the gravel pit. This can result in an adverse angle of attack of the
flow on the downstream embankment with subsequent breaching of the embankment and/ or failure of
the abutment.
• Levees can become weakened and fail with resultant adverse flow conditions at the bridge abutment.
• Debris can become lodged at piers and abutments and on the bridge superstructure, modifying flow
conditions and creating adverse angles of attack of the flow on bridge piers and abutments.
3.5.5.2 Designing for Scour at Abutments
The preferred design approach is to place the abutment foundation on scour resistant rock or on deep
foundations. Present technology has not developed sufficiently to provide reliable abutment scour estimates
for all hydraulic flow conditions that might be reasonably expected to occur at an abutment. Therefore,
engineering judgment is required in designing foundations for abutments. In many cases, foundations can be
designed with shallower depths than predicted by the equations when they are protected with rock riprap
and/or with a guide bank placed upstream of the abutment.
The potential for lateral channel migration, long-term degradation and contraction scour should be considered
in setting abutment foundation depths near the main channel. It is recommended that the abutment scour
equations presented in this section be used to develop insight as to the scour potential at an abutment.
1
3.5.5.3 Abutment Conditions
Abutments can be set back from the natural stream bank, placed at the bankline or, in some cases, actually set
into the channel itself. Common designs include stub abutments placed on spill-through slopes, and vertical
wall abutments, with or without wingwalls. Scour at abutments can be live-bed or clear-water scour. The
bridge and approach embankment can cross the stream and floodplain at a skew angle and this will have an
effect on flow conditions at the abutment. Finally, there can be varying amounts of overbank flow intercepted
by the approaches to the bridge and returned to the stream at the abutment. More severe abutment scour will
occur when the majority of overbank flow returns to the bridge opening directly upstream of the bridge
crossing. Less severe abutment scour will occur when overbank flows gradually return to the main channel
upstream of the bridge crossing.
3.5.5.4 Abutment Skew
4
The skew angle for an abutment (embankment) is depicted in Figure 1-3-22. For an abutment angled
downstream, the scour depth is decreased, whereas the scour depth is increased for an abutment angled
upstream.
3.5.5.5 Abutment Shape
There are three general shapes of abutments: (1) spill-through abutments, (2) vertical walls without wing
walls, and (3) vertical-wall abutments with wing walls (Figure 1-3-23). These shapes have varying angles to the
flow. As shown in Table 1-3-13, depth of scour is approximately double for vertical-wall abutments as compared
with spill-through abutments. Similarly, scour at vertical wall abutments with wingwalls is reduced to 82
percent of the scour of vertical wall abutments without wingwalls.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
3
1-3-51
Roadway and Ballast
Figure 1-3-22. Orientation of Embankment Angle, , to the Flow
Figure 1-3-23. Abutment Shape
Table 1-3-13. Abutment Shape Coefficients
Description
K1
Vertical-wall abutment
1.00
Vertical-wall abutment with wing walls
0.82
Spill-through abutment
0.55
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-52
AREMA Manual for Railway Engineering
Natural Waterways
3.5.5.6 Live-Bed Scour at Abutments
An equation based on field data of scour at the end of spurs in the Mississippi River (obtained by the USACE)
can be used for estimating abutment scour. This field situation closely resembles the laboratory experiments
for abutment scour in that the discharge intercepted by the spurs was a function of the spur length. The
modified equation, is applicable when the ratio of projected abutment (embankment) length (L) to the flow
depth (y1) is greater than 25. This equation can be used to estimate scour depth (ys) at an abutment where
conditions are similar to the field conditions from which the equation was derived:
EQ 21
where:
ys = Scour depth, m (ft)
y1 = Depth of flow at the abutment on the overbank or in the main channel, m (ft)
Fr = Froude Number based on the velocity and depth adjacent to and upstream of the
abutment
L = Length of embankment projected normal to the flow m (ft)
K1 = Abutment shape coefficient (from Table 1-3-13)
K2 = Coefficient for angle of embankment to flow
1
K2 = (see Figure 1-3-22 for definition of 
if embankment points downstream
if embankment points upstream
For cases where the abutment (embankment) length is small in comparison to flow depth (L/y1  25), the
following equation for local live-bed scour can be used to estimate abutment scour at a stable spill slope when
the flow is subcritical:
3
EQ 22
Where the variables are defined as for EQ 21. EQ 21 and EQ 22 are recommended for both live-bed and clearwater abutment scour conditions.
3.5.6 TOTAL SCOUR CALCULATION PROBLEM (2005)
Figure 1-3-24 shows a cross section plot of a railroad crossing a small stream. The bridge is 50 feet long with
vertical abutments and a single pier in the channel. The left and right abutments are set back 10 and 15 feet
from the channel banks, respectively. The rectangular pier is 1.5 feet wide by 12 feet long and is located in the
center of the bridge but not in the center of the channel. The channel bed and floodplain material is a silty sand
with a median grain size, D50, equal to 0.20 mm (0.00066 ft). Figure 1-3-25 shows the channel, floodplain and
railroad crossing in plan and includes the hydraulic data required for contraction scour calculations in the
channel and overbank areas under the bridge. Figure 1-3-26 shows the hydraulic data for computing pier and
abutment scour. Assume zero and eight degree angles of attack for the pier scour computation. The flow data
are from a hydraulic analysis of the crossing for the design discharge of 1000 cfs. The railroad grade is at an
elevation of 13.0 ft, the bridge low chord is at an elevation of 10.0 ft, the water surface at the crossing is at
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-53
4
Roadway and Ballast
elevation 8.5 ft, the floodplain is at elevation of 5.0 ft and the channel invert is at an elevation of -0.9 ft. The
crossing causes 0.5 feet of backwater at the cross section upstream of the bridge (water surface equals 9.0 feet).
Figure 1-3-24. Cross Section for Total Scour Problem
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-54
AREMA Manual for Railway Engineering
Natural Waterways
1
3
Figure 1-3-25. Hydraulic Data for Contraction Scour Calculations
4
3.5.6.1 Main Channel Contraction Scour
Determine if the upstream channel flow is live-bed or clear-water by comparing the average channel velocity to
the critical velocity for 0.20 mm sand.
Average channel velocity
V = Q1/A = 700 / (25.0 x 9.0) = 3.1 ft/s
Critical velocity (EQ 11)
Vc = Kuy1/6D1/3 = 11.17 (9.0)1/6 (0.00066)1/3 = 1.4 ft/s
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-55
Roadway and Ballast
The channel flow velocity is greater than the critical velocity for the bed material and the channel contraction
scour is live-bed. Determine k1 for the live-bed contraction scour equation. Compute the ratio of shear velocity
(V*) to particle fall velocity ( from Figure 1-3-15) to determine the mode of bed material transport and k1.
V* = (gy1S1)1/2 = (32.2 x 9.0 x 0.00035)1/2 = 0.32 ft/s
 = 0.025 m/s = 0.082 ft/s
V*/ = 0.32 / 0.082 = 3.9
The ratio of shear velocity to fall velocity is greater than 2.0 and the mode of bed material transport is mostly
suspended. Therefore k1 = 0.69.
Live-bed contraction scour (EQ 12 and EQ 13)
ys = y2 - y0 = 11.2 - 8.5 = 2.7 ft
3.5.6.2 Right overbank contraction scour
Assume that the overbank contraction scour is clear water. This assumption can be checked by comparing the
upstream floodplain flow velocity (V = 0.38 ft/s) to the critical velocity (Vc = 1.2 ft/s).
Clear-water contraction scour (EQ 14 and EQ 15)
Dm = 1.25D50 = 1.25 x 0.00066 = 0.00083 ft
ys = y2 - y0 = 4.8 - 3.5 = 1.3 ft
3.5.6.3 Left overbank contraction scour
ys = y2 - y0 = 3.1 - 3.5 = -0.4 ft (actually 0.0 ft)
Negative clear-water scour indicates that there is insufficient velocity to cause erosion in the overbank area
under the bridge. Therefore, the there is no contraction scour on the left overbank. Sediment will not deposit
in the left overbank area under the bridge because there is no sediment in transport from the floodplain
upstream (clear-water upstream floodplain flow).
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-56
AREMA Manual for Railway Engineering
Natural Waterways
Figure 1-3-26. Hydraulic Data for Local Scour Calculations
1
3.5.6.4 Pier Scour
Pear Scour for zero degree angle of attack (EQ 16)
Although the pier is not in the center of the channel, use the maximum channel velocity since the channel has
the potential to migrate laterally. The pier shape is square end (K1 = 1.1), the angle of attack is 0 degrees (K2
= 1.0), and the bed condition is small dunes or plane bed (K3 = 1.1).
3
4
Pier scour for 8 degree angle of attack (EQ 16 and EQ 19)
The pier shape is not included because angle of attack is greater than 5 degrees (K1 = 1.0), the angle of attack
is 8 degrees (K2 = 1.5 from Table 1-3-11 for 8 degrees and L/a = 12/1.5 = 8 or use EQ 19), and the bed condition
is small dunes or plane bed (K3 = 1.1).
K2 = (Cos  + (L / a) Sin )0.65 = (Cos 8 + (12 / 1.5) Sin 8)0.65 = 1.6
Note: The difference between Table 1-3-11 and EQ 19 is due to linear interpolation and rounding when using
the table.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-57
Roadway and Ballast
3.5.6.5 Right Abutment Scour
Check the ratio of embankment length (L) to flow depth at the abutment (y1) to determine which equation is
applicable. L / y1 = 105 / 3.5 = 30 > 25. Use EQ 21. Abutment shape is vertical-wall (K1 = 1.0) and the
embankment is perpendicular to flow ( = 90, K2 = 1.0).
For deep abutment scour, protect the abutment with riprap (Article 3.6.4.2). Also consider using a spill through
slope to reduce scour to 8.0 ft and provide riprap protection.
3.5.6.6 Left Abutment Scour
Check the ratio of embankment length (L) to flow depth at the abutment (y1) to determine which equation is
applicable. L / y1 = 70 / 3.5 = 20 < 25. Use EQ 22. Abutment shape is vertical-wall (K1 = 1.0) and the
embankment is perpendicular to flow ( = 90, K2 = 1.0).
For deep abutment scour, protect the abutment with riprap (Article 3.6.4.2). Also consider using a spill through
slope to reduce scour to 6.0 ft and provide riprap protection.
3.5.6.7 Plot Total Scour
The total scour is the sum of long-term degradation, contraction and local scour. Figure 1-3-27 shows the
contraction and local scour plotted in the bridge cross section. If long-term degradation is expected, then it
should be included in the main channel prior contraction and local scour. If the channel could migrate laterally,
then the maximum scour can occur at piers located in the overbank areas. The local scour hole side slopes are
shown at a 1.25H:1V slope due to the cohesive channel bed and floodplain materials. The abutment scour could
be eliminated with well designed riprap and the abutment scour could be substantially reduced if the abutment
included a spill-through slope. However, the spill-through slope would reduce also bridge open area. The
channel pier should be designed for the maximum potential scour.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-58
AREMA Manual for Railway Engineering
Natural Waterways
1
Figure 1-3-27. Total Scour Plot
3
3.5.7 REFERENCES FOR SECTION 3.5 (2005)
Arneson, L.A. and Shearman, J.O., 1998. "User's Manual for WSPRO – A Computer Model for Water Surface
Profile Computations," Office of Technology Applications, Federal Highway Administration, FHWA Report No.
FHWA-SA-98-080.
Lagasse, P.F., Schall, J.D., and Richardson, E.V., 2001. "Stream Stability at Highway Structures," Hydraulic
Engineering Circular No. 20, Third Edition, FHWA NHI 01-002, Federal Highway Administration, Washington,
D.C.
Lagasse, P.F., Spitz, W.J., Zevenbergen, L.W., and Zachmann, D.W., 2003. "Handbook for Predicting Stream
Meander Migration Using Aerial Photographs and Maps," Ayres Associates for the National Cooperative
Highway Research Program, Transportation Research Board, National Research Council, Washington, D.C.
Molinas, A., 1990. "Bridge Stream Tube Model for Alluvial River Simulation" (BRI-STARS), User's Manual,
National Cooperative Highway Research Program, Project No. HR15-11, Transportation Research Board,
Washington, D.C.
Richardson, E.V. and Davis, S.R., 2001. "Evaluating Scour at Bridges," Fourth Edition, Report FHWA NHI 01001, Federal Highway Administration, Hydraulic Engineering Circular No. 18, U.S. Department of
Transportation, Washington, D.C.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-59
4
Roadway and Ballast
Richardson, E.V., Simons, D.B., and Lagasse, P.F., 2001. "River Engineering for Highway Encroachments –
Highways in the River Environment," Report FHWA NHI 01-004, Federal Highway Administration, Hydraulic
Design Series No. 6, Washington, D.C.
U.S. Army Corps of Engineers, 1993. "Scour and Deposition in Rivers and Reservoirs," User's Manual, HEC-6,
Hydrologic Engineering Center, Davis, CA.
U.S. Army Corps of Engineers, 2001. "River Analysis System," HEC-RAS, Hydraulic Reference Manual Version
3.0, Hydrologic Engineering Center, Davis, CA.
SECTION 3.6 PROTECTING ROADWAY AND BRIDGES FROM SCOUR
Adequate protection against floods and washouts is essential not only for maintenance of dependable service,
but also to avoid heavy expenditures to replace damaged facilities and restore operation.
3.6.1 EMBANKMENT (2005)
3.6.1.1 General – Risks and Possible Damage
Water overflowing the embankment, either from a direct flow or backwater, frequently results in damage to the
railroad. This damage may be as severe as a washout or less apparent in other forms, such as, a loss of the
shoulder, a steepening of the embankment, a loss of crib or shoulder ballast, or a softening of the subgrade's
support characteristics. Damage resulting from sloughing and slides is usually more severe as the water
recedes from a saturated embankment. Loose, fine-grained, cohesionless soils are more susceptible to
sloughing. In general, soil conditions, vegetation, and the rapidity at which the water recedes are primary
factors in determining the risk of sloughing.
3.6.1.2 Temporary Protection Measures
Temporary protection of the railway embankment section is sometimes necessary, particularly in flood events
where immediate action is necessary and time constraints do not permit implementation of a permanent
solution. Periodic and close track inspections of flood and washout susceptible areas and identification of high
risk locations will be a beneficial first step in determining the appropriate remedial repair.
Temporary protection of potential overflow slopes and fill sections subject to erosion and sloughing can be
provided by placement of an armor of heavy weight material, not easily displaced by floodwaters, such as largesized stone (riprap) or sandbags. In blanketing the slopes, it is critical that the toe be adequately protected to
minimize the risk of base scour and possible embankment failure. Raising the embankment shoulder with
riprap and sandbags can also be a suitable means for temporary relief.
3.6.1.3 Permanent Protection Measures
In overflow territories, care must be taken to review the adequacy of design, location and construction of
existing drainageways and make appropriate corrections if deficiencies are found. Sufficient waterway capacity
is essential to minimize heading during floods and, if necessary, provisions should be made for additional relief
openings to handle the flow. The impact of runoff from neighboring facilities, existing and proposed, must also
be assessed. Input from applicable local, state, or federal authorities should be sought in these preliminary
drainage assessments.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-60
AREMA Manual for Railway Engineering
Natural Waterways
Selection of the optimal permanent protection measure should be done on a site-specific basis and will depend
on many factors, including service requirements, severity and extent of the damage potential, embankment soil
characteristics, and economic considerations. A subsurface exploration of the area in question, performed
during the preliminary stages, can many times generate valuable information and aid in the selection and
design process.
In general, depending upon service requirements, a track raise is the best assurance for reliable operation.
Embankments subject to severe side erosion can be protected by relocation of the track and/or channel, or
construction of revetments as discussed in Article 3.6.4.5. In overflow bottoms where either a channel change,
installation of additional openings, or a track raise or relocation do not afford sufficient relief, consideration
should be given to facing the downstream side of the embankments at least at critical locations with riprap or
other suitable means of protection. Covering erosion-susceptible slopes with a thick vegetative cover can
furthermore provide protection by impeding surface erosion.
On light traffic density lines where the aforementioned extensive measures cannot be economically justified,
consideration might be given to anchoring the track to the roadbed, at designated locations throughout the
overflow area, utilizing cable tied to rail, timber pile, screw anchors driven in the roadbed or hot asphalt
impregnated ballast. Under these conditions use of a heavy course ballast tends to reduce the incidence of
ballast displacement. When using this last method of protection, the railroad is accepting the risk of traffic
disruption due to flooding and washouts.
3.6.2 BRIDGES (2005)
1
3.6.2.1 General – Risks and Possible Damage
Protection against flood damage for structures calls for resourcefulness during the immediate flooding threat,
as well as during the implementation of permanent protection measures. Temporary measures should be given
consideration to prevent both minor and major damage. Minor damage can be categorized as scour on the
shoulders or behind the abutments, debris hung up in the waterway opening, overtopping, and various other
damage that can be immediately detected and repaired. Major damage includes items such as contamination of
ballast decks and track beds, scouring around piling, piers, foundations, and backwalls; channel changes
resulting in silting or bypassing the structure; culvert piping or joint separation; etc.
3
3.6.2.2 Temporary Protection Measures
The need for temporary protection should be considered not only prior to and during floods, but also when the
structure is under construction. Temporary measures to consider during or immediately preceding a flood
include, identification of high-risk areas, frequent inspection, remove or pass debris through the structure to
avoid accumulation, and the placement of riprap or sandbags. The following are temporary measures to be
considered when the structure is in the design or construction stage; all the measures considered previously,
and others such as fence jetties, rock jetties, and channel cutoffs.
3.6.2.3 Permanent Protection Measures
Permanent protection measures require that sound engineering principles be employed to protect the structure
from flood damage and allow its continued function as designed. Bridges and culverts must be designed with
sufficient waterway opening to handle the design storm. In addition, both structures must be designed with an
adequate opening to pass the anticipated debris. When conditions change in the upstream basin, some of the
measures detailed in various articles in Article 3.6.4 may need to be incorporated in the structure protection
plan. Permanent protection might also include underwater or other inspections of potential problem areas.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-61
4
Roadway and Ballast
3.6.3 COUNTERMEASURE SELECTION (2005)
3.6.3.1 General
A countermeasure is defined as a measure incorporated into a stream crossing system to monitor, control,
inhibit, change, delay, or minimize stream and bridge stability problems (HEC-23). Countermeasures may be
installed at the time of railroad construction or retrofitted to resolve stability problems at existing crossings.
Retrofitting is good economics and good engineering practice in many locations because the magnitude,
location, and nature of potential stability problems are not always discernible at the design stage, and indeed,
may take a period of several years to develop.
A countermeasure does not need to be a separate structure, but may be an integral part of the roadbed. For
example, relief bridges on floodplains are countermeasures which alleviate scour from flow contraction at the
bridge over the stream channel. Some features that are integral to the railroad design serve as
countermeasures to minimize stream stability problems. Abutments and piers oriented with the flow reduce
local scour and contraction scour. Also, reducing the number of piers and/or setting back the abutments
reduces contraction scour.
Countermeasures which are not integral to the embankment may serve one function at one location and a
different function at another. For example, bank revetment may be installed to control bank erosion from
meander migration, or it may be used to stabilize streambanks in the contracted area at a bridge. Other
countermeasures are useful for one function only. This category of countermeasures includes spurs constructed
in the stream channel to control meander migration.
A countermeasure matrix (Table 1-3-14) has been developed which lists most countermeasures presently in use
for stream instability and scour problems and summarizes river environmental factors that influence the
selection of a countermeasure for a specific problem (HEC-23). In selecting a countermeasure it is necessary to
evaluate how the stream might respond to the countermeasure, and also how the stream may respond as the
result of the activities of other parties.
3.6.3.2 Overview of the Countermeasure Matrix
A wide variety of countermeasures have been used to control channel instability and scour at bridge
foundations. The countermeasure matrix, presented in Table 1-3-14, is organized to highlight the various
groups of countermeasures and to identify their individual characteristics. The left column of the matrix lists
types of countermeasures in groups. In each row of the matrix, distinctive characteristics of a particular
countermeasure are identified. The matrix identifies most countermeasures in use today and lists information
on their functional applicability to a particular problem, their suitability to specific river environments, the
general level of maintenance resources required, and which states have experience with specific
countermeasures. Finally, a reference source for design guidelines is noted, where available.
Countermeasures have been organized into groups based on their functionality with respect to scour and
stream instability. The three main groups of countermeasures are: hydraulic countermeasures,
structural countermeasures and monitoring. The following outline identifies the countermeasure groups
in the matrix:
Group 1. Hydraulic Countermeasures
• Group 1.A: River training structures
– Transverse structures
– Longitudinal structures
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-62
AREMA Manual for Railway Engineering
Natural Waterways
– Areal structures
• Group 1.B: Armoring countermeasures
– Revetment and Bed Armor
• Rigid
• Flexible/articulating
– Local armoring
Group 2. Structural Countermeasures
• Foundation strengthening
• Pier geometry modification
Group 3. Monitoring
• Fixed Instrumentation
• Portable instrumentation
1
• Visual Monitoring
3.6.3.3 Countermeasure Groups
Group 1. Hydraulic Countermeasures
Hydraulic countermeasures are those which are primarily designed either to modify the flow or resist erosive
forces caused by the flow. Hydraulic countermeasures are organized into two groups: river training
structures and armoring countermeasures. The performance of hydraulic countermeasures is dependent
on design considerations such as filter requirements and edge treatment.
Group 1.A River Training Structures. River training structures are those which modify the flow. River
training structures are distinctive in that they alter hydraulics to mitigate undesirable erosional and/or
depositional conditions at a particular location or in a river reach. River training structures can be constructed
of various material types and are not distinguished by their construction material, but rather, by their
orientation to flow. River training structures are described as transverse, longitudinal or areal depending
on their orientation to the stream flow.
• Transverse river training structures are countermeasures which project into the flow field at an
angle or perpendicular to the direction of flow.
• Longitudinal river training structures are countermeasures which are oriented parallel to the
flow field or along a bankline.
• Areal river training structures are countermeasures which cannot be described as transverse or
longitudinal when acting as a system. This group also includes countermeasure "treatments" which
have areal characteristics such as channelization, flow relief, and sediment detention.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-63
3
4
Roadway and Ballast
1-3-64
Table 1-3-14. Stream Instability and Bridge Scour Countermeasures Matrix
AREMA Manual for Railway Engineering
© 2010, American Railway Engineering and Maintenance-of-Way Association
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
Table 1-3-14. Stream Instability and Bridge Scour Countermeasures Matrix (Continued)
Natural Waterways
1-3-65
Roadway and Ballast
Group 1.B Armoring Countermeasures. Armoring countermeasures are distinctive because they resist the
erosive forces caused by a hydraulic condition. Armoring countermeasures do not necessarily alter the
hydraulics of a reach, but act as a resistant layer to hydraulic shear stresses providing protection to the more
erodible materials underneath. Armoring countermeasures generally do not vary by function, but vary more in
material type. Armoring countermeasures are classified by two functional groups: revetments and bed
armoring or local scour armoring.
• Revetments and bed armoring are used to protect the channel bank and/or bed from
erosive/hydraulic forces. They are usually applied in a blanket type fashion for areal coverage.
Revetments and bed armoring can be classified as either rigid or flexible/articulating. Rigid
revetments and bed armoring are typically impermeable and do not have the ability to conform to
changes in the supporting surface. These countermeasures often fail due to undermining. Flexible/
articulating revetments and bed armoring can conform to changes in the supporting surface and
adjust to settlement. These countermeasures often fail by removal and displacement of the armor
material.
• Local scour armoring is used specifically to protect individual substructure elements of a bridge
from local scour. Generally, the same material used for revetments and bed armoring is used for local
armoring, but these countermeasures are designed and placed to resist local vortices created by
obstructions to the flow.
Group 2. Structural Countermeasures
Structural countermeasures involve modification of the bridge structure (foundation) to prevent failure from
scour. Typically, the substructure is modified to increase bridge stability after scour has occurred or when a
bridge is assessed as scour critical. These modifications are classified as either foundation strengthening or
pier geometry modifications.
• Foundation strengthening includes additions to the original structure which will reinforce and/or
extend the foundations of the bridge. These countermeasures are designed to prevent failure when the
channel bed is lowered to an expected scour elevation, or to restore structural integrity after scour has
occurred. Design and construction of bridges with continuous spans provide redundancy against
catastrophic failure due to substructure displacement as a result of scour. Retrofitting a simple span
bridge with continuous spans could also serve as a countermeasure after scour has occurred or when a
bridge is assessed as scour critical.
• Pier geometry modifications are used to either reduce local scour at bridge piers or to transfer
scour to another location. These modifications are used primarily to minimize local scour.
Group 3. Monitoring
Monitoring describes activities used to facilitate early identification of potential scour problems. Monitoring
could also serve as a continuous survey of the scour progress around the bridge foundations. Monitoring allows
for action to be taken before the safety of the railroad is threatened by the potential failure of a bridge.
Monitoring can be accomplished with instrumentation or visual inspection. A well designed monitoring
program can be a very cost-effective countermeasure. Two types of instrumentation are used to monitor bridge
scour: fixed instruments and portable instruments.
• Fixed instrumentation describes monitoring devices which are attached to the bridge structure to
detect scour at a particular location. Typically, fixed monitors are located at piers and abutments. The
number and location of piers to be instrumented should be defined, as it may be impractical to place a
fixed instrument at every pier and abutment on a bridge. Instruments such as sonar monitors can be
used to provide a timeline of scour, whereas instruments such as magnetic sliding collars can only be
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-66
AREMA Manual for Railway Engineering
Natural Waterways
used to monitor the maximum scour depth. Data from fixed instruments can be downloaded manually
at the site or it can be telemetered to another location.
• Portable instrumentation describes monitoring devices that can be manually carried and used
along a bridge and transported from one bridge to another. Portable instruments are more cost
effective in monitoring an entire bridge than fixed instruments; however, they do not offer a
continuous watch over the structure. The allowable level of risk will affect the frequency of data
collection using portable instruments.
• Visual inspection describes standard monitoring practices of inspecting the bridge on a regular
interval and increasing monitoring efforts during high flow events (flood watch). Typically, bridges are
inspected on an annual schedule. Where stream stability is questionable, channel bed elevations at
each pier location can be recorded during the annual inspection. The channel bed elevations should be
compared with historical cross sections to identify changes in bed elevations due to degradation or
lateral migration. Channel elevations should also be taken during and after high flow events. If
measurements cannot be safely collected during a high flow event, the engineer should determine if
the bridge is at risk and if train operation restrictions are necessary. Underwater inspections of the
foundations could be used to supplement the visual inspection after a flood.
3.6.3.4 Countermeasure Characteristics
The countermeasure matrix (Table 1-3-14) was developed to identify distinctive characteristics for each type of
countermeasure. Five categories of countermeasure characteristics were defined to aid in the selection and
implementation of countermeasures:
1
• Functional Applications
• Suitable River Environment
• Maintenance
3
• Installation/Experience by State
• Design Guidelines Reference
These categories were used to answer the following questions:
4
• For what type of problem is the countermeasure applicable?
• In what type of river environment is the countermeasure best suited or, are there river environments
where the countermeasure will not perform well?
• What level of resources will need to be allocated for maintenance of the countermeasure?
• What states or regions in the U.S. have experience with this countermeasure?
• Where do I obtain design guidance reference material?
Functional Applications
The functional applications category describes the type of scour or stream instability problem for which the
countermeasure is prescribed. The five main categories of functional applications are local scour at abutments
and piers, contraction scour, and vertical and lateral instability. Vertical instability implies the long-term
processes of aggradation or degradation over relatively long river reaches, and lateral instability involves a
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-67
Roadway and Ballast
long-term process of channel migration and bankline erosion problems. To associate the appropriate
countermeasure type with a particular problem, filled circles, half circles and open circle are used in the matrix
as described below:
n
well suited/primary use - the countermeasure is well suited for the application; the countermeasure has a good record of success for the application; the countermeasure was implemented primarily for this application.
n
possible application/secondary use - the countermeasure can be used for the application;
the countermeasure has been used with limited success for the application; the countermeasure was implemented primarily for another application but also can be designed to function
for this application.
In addition, this symbol can identify an application for which the countermeasure has performed successfully and was implemented primarily for that application, but there is only a
limited amount of data on its performance and therefore the application cannot be rated as
well suited.

unsuitable/rarely used - the countermeasure is not well suited for the application; the
countermeasure has a poor record of success for the application; the countermeasure was not
intended for this application.
N/A
not applicable - the countermeasure is not applicable to this functional application.
Suitable River Environment
This category describes the characteristics of the river environment for which a given countermeasure is best
suited or under which there would be a reasonable expectation of success. Conversely, this category could
indicate conditions under which experience has shown a countermeasure may not perform well. The river
environment characteristics that can have a significant effect on countermeasure selection or performance are:
• River type
• Stream size (width)
• Bend radius
• Flow velocity
• Bed material
• Ice/debris load
• Bank condition
• Floodplain (width)
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-68
AREMA Manual for Railway Engineering
Natural Waterways
For each environmental characteristic, a qualitative range is established (e.g., stream size: Wide, Moderate, or
Small) to serve as a suitability discriminator. While most characteristics are self explanatory, both HEC-20
("Stream Stability at Highway Structures") and HDS 6 ("River Engineering for Highway Encroachments")
provide guidance on the range and definitions of these characteristics of the river environment. In the context
of this matrix, the bank condition characteristic (Vertical, Steep, or Flat) considers the effectiveness of a given
countermeasure to protect a bank with that configuration, not the suitability for installation of the
countermeasure on a bank with that configuration.
Where a block is checked for a given countermeasure under an environmental characteristic, the
countermeasure is considered suitable or has been applied successfully for the full range of that environmental
characteristic.
The checked block means that the characteristic does not influence the selection of the countermeasure, i.e.,
the countermeasure is suitable for the full range of that characteristic. For example, guide banks have been
applied successfully in braided, meandering, and straight streams; however, bendway weirs/stream barbs
are most suitable for installation on meandering streams.
Maintenance
The maintenance category identifies the estimated level of maintenance that may need to be allocated to
service the countermeasure. The ratings in this category range from "Low" to "High" and are subjective. The
ratings represent the relative amount of resources required for maintenance with respect to other
countermeasures within the matrix shown in Table 1-3-14. A low rating indicates that the countermeasure is
relatively maintenance free, a moderate rating indicates that some maintenance is required, and a high rating
indicates that the countermeasure requires more maintenance than most of the countermeasures in the
matrix.
1
Installation/Experience by State Departments of Transportation
This category identifies states (or a region) where a particular countermeasure has been installed. These
listings may not include all of the states which have used a particular countermeasure. Certain
countermeasures are used in many states. These countermeasures have a listing of "Widely Used" in this
category. Both successful, and unsuccessful experiences are reflected by the listing.
3
Design Guideline Reference
Reference manuals which provide guidance in countermeasure design have been developed by government
agencies through research programs. The FHWA has produced a wealth of information through the federally
coordinated program of highway research and development. The design guideline reference column identifies
reference manuals where guidance on design of the countermeasures can be obtained. The references are
symbolized by numbers in this column. The numbers correspond to the numbers of the references listed on the
second page of the matrix. Countermeasures for which design guidelines are provided in HEC-23 are
referenced using DG#, where # represents a number assigned to the design guideline (see also Section 3.6.4).
3.6.3.5 Summary
The countermeasures matrix is convenient reference guide on a wide range of countermeasures applicable to
scour and stream stability problems. An engineering plan to install countermeasures should provide
conceptual design and cost information on several alternative countermeasures, with a recommended
alternative based on a variety of engineering, environmental and cost factors. The countermeasures matrix is a
good way to begin identifying and prioritizing possible alternatives. The information provided in the matrix
related to functional applications, suitable river applications and maintenance issues should facilitate
preliminary selection of feasible alternatives prior to more detailed investigation.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-69
4
Roadway and Ballast
3.6.3.6 Selection of Countermeasures for Stream Instability
The selection of an appropriate countermeasure for a specific bank erosion problem is dependent on factors
such as the erosion mechanism, stream characteristics, construction and maintenance requirements, potential
for vandalism, and costs. Perhaps more important, however, is the effectiveness of the measure selected in
performing the required function.
Protection of an existing bank line may be accomplished with revetments, spurs, retardance structures,
longitudinal dikes, or bulkheads (Table 1-3-14). Spurs, longitudinal dikes, and area retardance structures can
be used to establish a new flow path and channel alignment, or to constrict flow in a channel. Because of their
high cost, bulkheads may be appropriate for use only where space is at a premium. Channel relocation may be
used separately or in conjunction with other countermeasures to change the flow path and flow orientation.
Erosion Mechanism
Bank erosion mechanisms are surface erosion and/or mass wasting. Surface erosion is the removal of soil
particles by the velocity and turbulence of the flowing water. Mass wasting is by slides, rotational slip, piping
and block failure. In general slides, rotational slip and block failure result from the bank being undercut by the
flow. Also, seepage force of the pore water in the bank is another factor that can cause surface erosion or mass
wasting. The type of mechanism is determined by the magnitude of the erosive forces of the water, type of bed
and bank material, vegetation, and bed elevation stability of the stream.
Stream Characteristics
Stream characteristics that influence the selection of countermeasures include (see also Table 1-3-14):
• Channel width
• Bank height
• Channel configuration
• Channel material
• Vegetative cover
• Sediment transport condition
• Bend radii
• Channel velocities and flow depth
• Ice and debris
• Floodplain characteristics
Channel Width. Channel width influences the use of bendway weirs and other spur-type countermeasures. On
smaller streams (<250 feet wide), flow constriction resulting from the use of spurs may cause erosion of the
opposite bank. However, spurs can be used on small channels where the purpose is to shift the location of the
channel.
Bank Height. Low banks (<10 feet) may be protected by any of the countermeasures, including bulkheads.
Medium height banks (from 10 to 20 feet) may be protected by revetment, retardance structures, spurs, and
longitudinal dikes. High banks (>20 feet) generally require revetments used alone or in conjunction with other
measures.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-70
AREMA Manual for Railway Engineering
Natural Waterways
Channel Configuration. Spurs and jack fields have been successfully used as a countermeasure to control the
location of the channel in meandering and braided streams. Also, bulkheads, revetments, and riprap have been
used to control bank erosion resulting from stream migration. On anabranching streams, revetments, riprap,
and spurs have been used to control bank erosion and channel shifting. Also, channels that do not carry large
flows can and have been closed off.
Channel Material. Spurs, revetments, riprap, jack fields, or check dams can be used in any type of channel
material if they are designed correctly. However, jack fields should only be placed on streams that carry
appreciable debris and sediment in order for the jacks to cause deposition and eventually be buried.
Bank Vegetation. Vegetation such as willows can enhance the performance of structural countermeasures and
may, in some cases, reduce the level of structural protection needed. Meander migration and other bank
erosion mechanisms are accelerated on many streams in reaches where vegetation has been cleared.
Sediment Transport. The sediment transport conditions can be described as regime, threshold, or rigid.
Regime channel beds are those which are in motion under most flow conditions, generally in sand or silt-size
noncohesive materials. Threshold channel beds have no bed material transport at normal flows, but become
mobile at higher flows. They may be cut through cohesive or noncohesive materials, and an armor layer of
coarse-grained material can develop on the channel bed. Rigid channel beds are cut through rock or boulders
and rarely or never become mobile. In general, permeable structures will cause deposition of bed material in
transport and are better suited for use in regime and some threshold channels than in rigid channel conditions.
Impermeable structures are more effective than permeable structures in channels with little or no bed load, but
impermeable structures can also be very effective in mobile bed conditions. Revetments can be effectively used
with mobile or immobile channel beds.
Bend Radii. Bend radii affect the design of countermeasures, because some countermeasures will only function
properly in long or moderate radius bends. Thus, the cost per meter (foot) of bank protection provided by a
specific countermeasure may differ considerably between short-radius and longer radius bends.
1
Channel Velocities and Flow Depth. Channel hydraulics affect countermeasure selection because structural
stability and induced scour must be considered. Some of the permeable flow retardance measures may not be
structurally stable and countermeasures which utilize piles may be susceptible to scour failure in high velocity
environments.
Ice and Debris. Ice and debris can damage or destroy countermeasures and should always be considered during
the selection process. On the other hand, the performance of some permeable spurs and area retardance
structures is enhanced by debris where debris accumulation induces additional sediment deposition.
Floodplains. In selecting countermeasures for stream stability and scour, the amount of flow on the floodplain
is an important factor. For example, if there is appreciable overbank flow, then the use of guide banks to protect
abutments should be considered. Also, spurs perpendicular to the approach embankment may be required to
control erosion.
Construction and Maintenance Requirements
Standard requirements regarding construction or maintenance such as the availability of materials,
construction equipment requirements, site accessibility, time of construction, contractor familiarity with
construction methods, and a program of regular maintenance, inspection, and repair are applicable to the
selection of appropriate countermeasures. Additional considerations for countermeasures located in stream
channels include: constructing and maintaining a structure that may be partially submerged at all times, the
extent of bank disturbance which may be necessary, and the desirability of preserving streambank vegetative
cover to the extent practicable.
Vandalism
Vandalism is always a maintenance concern since effective countermeasures can be made ineffective by
vandals. Documented vandalism includes dismantling of devices, burning, and cutting or chopping with knives,
wire cutters, and axes. Countermeasure selection or material selection for construction may be affected by
concerns of vandalism. For example, rock-filled baskets (gabions) may not be appropriate in some urban
environments.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-71
3
4
Roadway and Ballast
Costs
Cost comparisons should be used to study alternative countermeasures with an understanding that the
measures were installed under widely varying stream conditions, that the conservatism (or lack thereof) of the
designer is not accounted for, that the relative effectiveness of the measures cannot be quantitatively evaluated,
and that some measures included in the cost data may not have been fully tested by floods.
3.6.3.7 Countermeasures for Meander Migration
The best countermeasure against meander migration is to locate the bridge crossing on a relatively straight
reach of stream between bends. At many such locations, countermeasures may not be required for several
years because of the time required for the bend to move to a location where it becomes a threat to the railroad
facility. However, bend migration rates on other streams may be such that countermeasures will be required
after a few years or a few flood events and, therefore, should be installed during initial construction.
Stabilizing channel banks at a railroad stream crossing can cause a change in the channel cross section and an
increase in stream sinuosity upstream of the stabilized banks. Figure 1-3-28a illustrates a natural channel
section in a bend with the deeper section at the outside of the bend and a gentle slope toward the inside bank
resulting from point bar growth. Figure 1-3-28b illustrates the scour which results from stabilizing the outside
bank of the channel and the resulting steeper slope of the point bar on the inside of the bend. This effect must
be considered in the design of the countermeasure and the bridge. It should also be recognized that the thalweg
location and flow direction can change as sinuosity upstream increases.
Countermeasures for meander migration include those that:
• Protect an existing bank line
• Establish a new flow line or alignment
• Control and constrict channel flow
The classes of countermeasures identified for bank stabilization and bend control are bank revetments, spurs,
retardance structures, longitudinal dikes, vane dikes, bulkheads, and channel relocations. Also, a carefully
planned cutoff may be an effective way to counter problems created by meander migration. These measures
may be used individually or in combination to combat meander migration at a site. Some of these
countermeasures are also applicable to bank erosion from causes other than bend migration.
Figure 1-3-28. Comparison of Channel Bend Cross Sections
(a) for Natural Conditions, and (b) for Stabilized Bend (after Brown)
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-72
AREMA Manual for Railway Engineering
Natural Waterways
3.6.3.8 Countermeasures for Channel Braiding and Anabranching
Channel braiding occurs in streams with an overload of sediment, causing deposition and aggradation. As
aggradation occurs, the slope of the channel increases, velocities increase, and multiple, interconnected
channels develop. The overall channel system becomes wider and multiple channels are formed as bars of
sediment are deposited in the main channel (see HEC-20 or HDS 6).
Braiding can also occur where banks are easily eroded and there is a large range in discharge. The channel
becomes wider at high flows, and low-flow forms multiple interconnected channels. In an anabranched stream,
flow is divided by islands rather than bars, and the anabranched channels are more permanent than braided
channels and generally convey more flow.
Braided channels change alignment rapidly, and are very wide and shallow even at flood flow. They present
problems at bridge sites because of the high cost of bridging the complete channel system, unpredictable
channel locations and flow directions, difficulties with eroding channel banks, and in maintaining bridge
openings unobstructed by bars and islands.
Countermeasures used on braided and anabranched streams are usually intended to confine the multiple
channels to one channel. This tends to increase the sediment transport capacity in the principal channel and
encourage deposition in secondary channels. These measures usually consist of dikes constructed from the
margins of the braided zone to the channel over which the bridge is constructed. Guide banks at bridge
abutments (see Article 3.6.4.3) in combination with revetment on embankment fill slopes (see Article 3.6.4.5),
riprap on embankment fill slopes only, and spurs (see Article 3.6.4.4) arranged in the stream channels to
constrict flow to one channel have also been used successfully.
1
Since anabranches are permanent channels that may convey substantial flow, diversion and confinement of an
anabranched stream is likely to be more difficult than for a braided stream. The designer may be faced with a
choice of either building more than one bridge, building a long bridge, or diverting anabranches into a single
channel.
3.6.3.9 Countermeasures for Degradation and Aggradation
3
Bed elevation instability problems are common on alluvial streams. Degradation in streams can cause the loss
of bridge piers in stream channels and can contribute to the loss of piers and abutments located on caving
banks. Aggradation causes the loss of waterway opening in bridges and, where channels become wider because
of aggrading streambeds, overbank piers and abutments can be undermined. At its worst, aggradation may
cause streams to abandon their original channels and establish new flow paths which could isolate the existing
bridge.
Countermeasures to Control Degradation
Countermeasures used to control bed degradation include check dams and channel linings. Check-dams and
structures which perform functions similar to check-dams include drop structures, cutoff walls, and drop
flumes. A check-dam is a low dam or weir constructed across a channel to prevent upstream degradation (see
Article 3.6.4.7).
Channel linings of concrete and riprap have proved unsuccessful at stopping degradation. To protect the lining,
a check-dam may have to be placed at the downstream end to key it to the channel bed. Such a scheme would
provide no more protection than would a check dam alone, in which case the channel lining would be
redundant.
Bank erosion is a common hydraulic hazard in degrading streams. As the channel bed degrades, bank slopes
become steeper and bank caving failures occur. The USACE found that longitudinal stone dikes, or rock
toe-dikes, provided the most effective toe protection of all bank stabilization measures studied for very dynamic
and/or actively degrading channels.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-73
4
Roadway and Ballast
Countermeasures to Control Aggradation
Currently, measures used in attempts to alleviate aggradation problems include channelization, debris basins,
bridge modification, and/or continued maintenance, or combinations of these. Channelization may include
dredging and clearing channels, constructing small dams to form debris basins, constructing cutoffs to increase
the local slope, constructing flow control structures to reduce and control the local channel width, and
constructing relief channels to improve flow capacity at the crossing. Except for debris basins and relief
channels, these measures are intended to increase the sediment transport capacity of the channel, thus
reducing or eliminating problems with aggradation. Cutoffs must be designed with considerable study as they
can cause erosion and degradation upstream and deposition downstream (see Article 3.6.4.8). The most
common bridge modifications are increasing the bridge length by adding spans and increasing the effective flow
area beneath the structure by raising the bridge deck.
A program of continuing maintenance has been successfully used to control problems at bridges on aggrading
streams. In such a program, a monitoring system is set up to survey the affected crossing at regular intervals.
When some pre-established deposition depth is reached, the bridge opening is dredged or cleared of the
deposited material. In some cases, this requires opening a clearing after every major flood. This solution
requires surveillance and dedication to the continued maintenance of an adequate waterway under the bridge.
Otherwise, it is only a temporary solution. A debris basin or a deeper channel upstream of the bridge may be
easier to maintain. Continuing maintenance is not recommended if analysis shows that other countermeasures
are practicable.
3.6.3.10 Selection of Countermeasures for Scour at Bridges
The selection of an appropriate countermeasure for scour at a bridge requires an understanding of the erosion
mechanism producing the specific scour problem. For example, contraction scour results from a sediment
imbalance across most or all of the channel while local scour at a pier or abutment results from the action of
vortices at an obstruction to the flow. Degradation is a component of total scour, but is considered a channel
instability problem.
3.6.3.11 Countermeasures for Contraction Scour
Severe contraction of flow at railroad stream crossings has resulted in numerous bridge failures at abutments,
approach fills, and piers from contraction scour. Design alternatives to decrease contraction scour include
longer bridges, relief bridges on the floodplain, and superstructures at elevations above flood stages of extreme
events. These design alternatives are integral features of the facility which reduce the contraction at bridges
and, therefore, reduce the magnitude of contraction scour.
The elevation of bridge superstructures is recognized as important to the integrity of the bridge because of
hydraulic forces that may damage the superstructure. These include buoyancy and impact forces from ice and
other floating debris. Contraction scour is another consideration in setting the superstructure elevation. When
the superstructure of a bridge becomes submerged or when ice or debris lodged on the superstructure causes
the flow to contract, flow may be accelerated and more severe scour can occur. For this reason, where
contraction scour is of concern, bridge superstructures should be located with clearance for debris, and, if
practicable, above the stage of floods larger than the design flood.
Similarly, pier design, span length, and pier location can become more important contributors to contraction
scour where debris can lodge on the piers and further contract flow in the waterway. In streams which carry
heavy loads of debris, longer, higher spans and solid piers will help to reduce the collection of debris. Where
practicable, piers should be located out of the main current in the stream, i.e., outside the thalweg at high flow.
There are numerous locations where piers occupy a significant area in the stream channel and contribute to
contraction scour.
The principal countermeasure used for reducing the effects of contraction is revetment on channel banks and
fill slopes at bridge abutments (see Article 3.6.4.5). However, guide banks may be used to reduce the effects of
contraction by moving the site of local scour caused by the turbulence of intersecting flows and contraction
away from the bridge abutment (see Article 3.6.4.3).
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-74
AREMA Manual for Railway Engineering
Natural Waterways
The potential for undesired effects from stabilizing all or any portion of the channel perimeter at a contraction
should be considered. Stabilization of the banks may only result in exaggerated scour in the streambed near
the banks or, in a relatively narrow channel, across the entire channel. Stabilization of the streambed may also
result in exaggerated lateral scour in any size stream. Stabilization of the entire stream perimeter may result
in downstream scour or failure of some portion of the countermeasures used on either the streambed or banks.
3.6.3.12 Countermeasures for Local Scour
Local scour occurs in bridge openings at piers and abutments. In general, design alternatives against
structural failure from local scour consist of measures which reduce scour depth, such as pier shape and
orientation, and measures which retain their structural integrity after scour reaches its maximum depth, such
as placing foundations in sound rock and using deep piling. Countermeasures which can reduce the risk from
scour include riprap.
Abutments
Countermeasures for local scour at abutments consist of measures which improve flow orientation at the bridge
end and move local scour away from the abutment, as well as revetments and riprap placed on spill slopes to
resist erosion.
Guide banks are earth or rock embankments placed at abutments. Flow disturbances, such as eddies and
cross-flow, will be eliminated where a properly designed and constructed guide bank is placed at a bridge
abutment. Guide banks also protect the railroad embankment, reduce local scour at the abutment and adjacent
piers, and move local scour to the end of the guide bank (see Article 3.6.4.3).
1
Local scour also occurs at abutments as a result of expanding flow downstream of the bridge, especially for
bridges on wide, wooded floodplains that have been cleared for construction of the railroad. Short guide banks
extending downstream of the abutment to the tree line will move this scour away from the abutment, and the
trees will retard velocities so that flow redistribution can occur with minimal scour.
Revetments may consist of pervious rock or rigid concrete. Rock riprap revetment provides an effective
countermeasure against erosion on spill slopes (see Article 3.6.4.2). Rigid revetments have been more
successful where abutments are on the floodplain rather than in stream channels because hydrostatic pressure
behind the revetments is not usually a problem. Precautions against undermining of the toe and upstream
terminus of all revetments are always required (see Article 3.6.4.5).
Other countermeasures have been successfully used to inhibit scour at abutments where the abutment is
located at the streambank or within the stream channel. These measures include dikes to constrict the width
of braided streams and retards to reduce velocities near the streambank.
Piers
Three basic methods may be used to prevent damage from local scour at piers. The first method is to place the
foundation of the structure at such a depth that the structural stability will not be at risk with maximum scour.
The second is to provide protection at or below the streambed to inhibit the development of a scour hole. The
third measure is to prevent erosive vortices from forming or to reduce their strength and intensity.
Streamlining the pier nose decreases flow separation at the face of the pier, reducing the strength of the
horseshoe vortices which form at piers. Practical application of this principle involves the use of rounded or
circular shapes at the upstream and downstream faces of piers in order to reduce the flow separation. However,
flow direction can and does change with time and with stage on some streams. Piers oriented with flow
direction at one stage or at one point in time may be skewed with flow direction at another. Also, flow direction
changes with the passage of bed forms. In general, piers should be aligned with the main channel design flow
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-75
3
4
Roadway and Ballast
direction and skew angles greater than 5 degrees should be avoided. Where this is not possible, a single
cylindrical pier or a row of cylindrical columns will produce a lesser depth of local scour.
The tendency of a row of columns to collect debris should be considered. Debris can greatly increase scour depths.
Webwalls have been used between columns to add to structural strength and to reduce the tendency to collect
debris. Webwalls should be constructed at the elevation of stream flood stages which carry floating debris and
extended to the elevation of the streambed. When installing a webwall as a countermeasure against debris, the
potential for significantly increased scour depths should be considered if the approach flow might impinge on the
wall at a high angle of attack.
Riprap is commonly used to inhibit local scour at piers at existing bridges. This practice is not recommended as an
adequate substitute for foundations or piling located below expected scour depths for new or replacement bridges.
It is recommended as a retrofit or a measure to reduce the risk where scour threatens the integrity of a pier (see
Article 3.6.4.1). The practice of heaping stones around a pier is not recommended because experience has shown
that continual replacement is usually required. Success rates have been better with alluvial bed materials where
the top of the riprap was placed at or below the elevation of the streambed.
3.6.3.13 References for Section 3.6.3
Bertoldi, D.A., Jones, J.S., Stein, S.M., Kilgore, R.T., and Atayee, A.T., 1996. "An Experimental Study of Scour
Protection Alternatives at Bridge Piers, FHWA-RD-95-187, Office of Engineering and Highway Operations
R&D, McLean, VA.
Bradley, J.N., 1978. "Hydraulics of Bridge Waterways," Hydraulic Design Series No. 1, U.S. Department of
Transportation, FHWA, Washington, D.C.
Brice, J.C. and Blodgett, J.C., 1978. "Countermeasure for Hydraulic Problems at Bridges, Volumes 1 and 2,"
FHWA-RD-78-162 and 163, USGS, Menlo Park, CA.
Brown, S.A., 1985. "Design of Spur-type Streambank Stabilization Structures," FHWA/RD-84/101, FHWA,
Washington, D.C.
Brown, S.A., 1985. "Streambank Stabilization Measures for Highway Engineers, FHWA/RD-84/100, FHWA,
Washington, D.C.
Brown, S.A. and Clyde, E.S., 1989. "Design of Riprap Revetment," Hydraulic Engineering Circular No. 11,
FHWA-IP-89-016, Washington, D.C.
Chang, F. and Karim, M., 1972. "An Experimental Study of Reducing Scour Around Bridge Piers Using Piles,"
South Dakota Department of Highways, Report.
Clopper, P.E., 1989. "Hydraulic Stability of Articulated Concrete Block Revetment Systems During Overtopping
Flow," FHWA-RD-89-199, Office of Engineering and Highway Operations R&D, McLean, VA.
Clopper, P.E., 1992. "Protecting Embankment Dams with Concrete Block Systems," Hydro Review, Vol. X, No.
2, April.
Clopper, P.E. and Chen, Y., 1988. "Minimizing Embankment Damage During Overtopping Flow," FHWA-RD-88181, Office of Engineering and Highway Operations R&D, McLean, VA.
Federal Highway Administration, 1998. "Scour Monitoring and Instrumentation," Demonstration Project 97
Participants Workbook, FHWA-SA-96-036, Office of Technology Applications, Washington, D.C.
Fotherby, L.M. and Ruff, J.F., 1995. "Bridge Scour Protection System Using Toskanes - Phase 1," Pennsylvania
Department of Transportation, Report 91-02.
Karim, M., 1975. "Concrete Fabric Mat, Highway Focus, Vol. 7.
Keown, M.P., 1983. "Streambank Protection Guidelines for Landowners and Local Governments," U.S. Army
Corps of Engineers, Waterways Experiment Station, Vicksburg, MS.
Lagasse, P.F., Richardson, E.V., Schall, J.D., and Price, G.R., 1997. "Instrumentation for Measuring Scour at
Bridge Piers and Abutments," NCHRP Report 396, Transportation Research Board, National Research
Council, National Academy Press, Washington, D.C.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-76
AREMA Manual for Railway Engineering
Natural Waterways
Lagasse, P.F., Schall, J.D., and Richardson, E.V., 2001, "Stream Stability at Highway Structures," Third Edition,
Hydraulic Engineering Circular No. 20, FHWA-NHI-01-002, Washington, D.C.
Lagasse, P.F., Zevenbergen, L.W., Schall, J.D., and Clopper, P.E., 2001. "Bridge Scour and Stream Instability
Countermeasures – Experience, Selection, and Design Guidelines," Second Edition, Report FHWA NHI 01-003,
Federal Highway Administration, Hydraulic Engineering Circular No. 23, U.S. Department of Transportation,
Washington, D.C.
McCorquodale, J.A., 1991. "Guide for the Design and Placement of Cable Concrete Mats," Report Prepared for
the Manufacturers of Cable Concrete.
McCorquodale, J.A., 1991. "Cable-tied Concrete Block Erosion Protection," Hydraulic Engineering '93, San
Francisco, CA, Proceedings (1993), pp. 1367-1372.
Odgaard, A.J. and Wang, Y. 1991. "Sediment Management with Submerged Vanes, I and II," Journal of
Hydraulic Engineering, ASCE Vol. 117, 3, Washington, D.C.
Paice, C. and Hey, R., 1993. "The Control and Monitoring of Local Scour at Bridge Piers," Proceedings
Hydraulic Engineering 1993, San Francisco, CA.
Richardson, E.V., Simons, D.B., and Lagasse, P.F., 2001. "River Engineering for Highway Encroachments Highways in the River Environment," Report FHWA NHI 01-004, Federal Highway Administration, Hydraulic
Design Series No. 6, Washington, D.C.
Simons, D.B. and Chen, Y.H., 1984. "Hydraulic Tests to Develop Design Criteria for the Use of Reno
Mattresses," Civil Engineering Department - Engineering Research Center, Colorado State University, Fort
Collins, CO.
U.S. Army Corps of Engineers, 1981. "The Streambank Erosion Control Evaluation and Demonstration Act of
1974," Final Report to Congress, Executive Summary and Conclusions.
1
3.6.4 COUNTERMEASURE DESIGN GUIDANCE (2005)
3.6.4.1 Rock Riprap at Piers and Abutments
Introduction
3
Present knowledge for designing riprap at bridge piers is based on research conducted under laboratory
conditions with little field verification. Flow turbulence and velocities around a pier are of sufficient magnitude
that large rocks move over time. Bridges have been lost due to the removal of riprap at piers resulting from
turbulence and high velocity flow. Usually this does not happen during one storm, but is the result of the
cumulative effect of a sequence of high flows. Therefore, if rock riprap is placed as scour protection
around a pier, the bridge should be monitored and inspected during and after each high flow
.
event to insure that the riprap is stable
Sizing Rock Riprap at Piers
As a countermeasure for scour at piers for existing bridges, riprap can reduce the risk of failure.
Riprap is not recommended as a pier scour countermeasure for new bridges. Determine the D50 size
of the riprap using the rearranged Isbash equation to solve for stone diameter (in meters (ft), for fresh water):
2
0.692  KV 
D 50 = ------------------------------- S s – 1 2g
EQ 23
where:
D50 = median stone diameter, m (ft)
K = coefficient for pier shape
V = velocity on pier, m/s (ft/s)
Ss = specific gravity of riprap (normally 2.65)
g = 9.81 m/s2 (32.2 ft/s2)
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-77
4
Roadway and Ballast
K = 1.5 for round-nose pier
K = 1.7 for rectangular pier
The effect of turbulence intensity on required rock size is illustrated in Figure 1-3-29.
To determine V multiply the average channel velocity (Q/A) by a coefficient that ranges from 0.9 for a pier
near the bank in a straight uniform reach of the stream to 1.7 for a pier in the main current of flow around a
sharp bend.
(1) Provide a riprap mat width which extends horizontally at least two times the pier width, measured
from the pier face.
(2) Place the top of a riprap mat at the same elevation as the streambed. Placing the bottom of a riprap
mat on top of the streambed is discouraged. In all cases where riprap is used for scour control, the
bridge must be monitored during and inspected after high flows.
It is important to note that it is a disadvantage to bury riprap so that the top of the mat
is below the streambed because inspectors have difficulty determining if some or all of
the riprap has been removed. Therefore, it is recommended to place the top of a riprap mat at
the same elevation as the streambed.
(a) The thickness of the riprap mat should be three stone diameters (D50) or more. In general, the
bottom of the riprap blanket should be placed at or below the computed contraction scour depth.
(b) In some conditions, place the riprap on a geotextile or a gravel filter. However, if a well-graded
riprap is used, a filter may not be needed. In some flow conditions it may not be possible to place
a filter or if the riprap is buried in the bed a filter may not be needed.
(c) The maximum size rock should be no greater than twice the D50 size.
Design Example for Riprap at Existing Bridge Piers
Riprap is to be sized for an existing 6 ft diameter circular pier. The velocity was determined to be 6 ft/s using
the continuity equation. The pier is located between the bank and the thalweg on a gradual bend. A velocity
multiplier of 1.2 should be used to account for pier location in the channel, since the calculated value represents
a cross section average. The computed contraction scour at the pier is approximately 3.9 ft.
Step 1. Determine D50 and Dmax for the riprap protection using EQ 23.
2
0.692  KV 
D 50 = ------------------------------- S s – 1 2g
2
  1.5   1.2   6  
D 50 = 0.692 --------------------------------------------------- = 0.8ft
 2.65 – 1   2   32.2 
D max  2 (0.8)  16
. ft
Step 2. Extent of riprap from edge of pier = 2(6) = 12 ft.
Step 3. Depth of riprap from streambed at pier = Contraction Scour = 3.9 ft.
Step 4. Use well graded riprap such that placement of filter material under water can be avoided. The
gradation should be determined using the guidance for revetments (Article 3.6.4.5). This part of the design
is not conducted here.
Figure 1-3-30 presents the riprap placement resulting from the design.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-78
AREMA Manual for Railway Engineering
Natural Waterways
(SI Units)
1
3
4
(English Units)
Figure 1-3-29. Effect of Turbulence Intensity on Rock Size Using the Isbash Approach
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-79
Roadway and Ballast
Figure 1-3-30. Placement of Pier Riprap
References for Riprap at Piers
Lagasse, P.F., Zevenbergen, L.W., Schall, J.D., and Clopper, P.E., 2001. "Bridge Scour and Stream Instability
Countermeasures – Experience, Selection, and Design Guidelines," Second Edition, Report FHWA NHI 01-003,
Federal Highway Administration, Hydraulic Engineering Circular No. 23, U.S. Department of Transportation,
Washington, D.C.
Richardson, E.V. and Davis, S.R., 2001. "Evaluating Scour at Bridges," Hydraulic Engineering Circular 18,
Fourth Edition, FHWA NHI 01-001, Federal Highway Administration, U.S. Department of Transportation,
Washington, D.C.
3.6.4.2 Rock Riprap at Abutments
Introduction
The FHWA conducted two research studies in a hydraulic flume to determine equations for sizing rock riprap
for protecting abutments from scour (Pagan 1991, Atayee 1993). The first study investigated vertical wall and
spill-through abutments which encroached 28 and 56 percent on the floodplain, respectively. The second study
investigated spill-through abutments which encroached on a floodplain with an adjacent main channel
(Figure 1-3-31). Encroachment varied from the largest encroachment used in the first study to a full
encroachment to the edge of main channel bank. For spill-through abutments in both studies, the rock riprap
consistently failed at the toe downstream of the abutment centerline (Figure 1-3-32). For vertical wall
abutments, the first study consistently indicated failure of the rock riprap at the toe upstream of the centerline
of the abutment.
Field observations and laboratory studies indicate that with large overbank flow or large drawdown through a
bridge opening that scour holes develop on the side slopes of spill-through abutments and the scour can be at
the upstream corner of the abutment. In addition, flow separation can occur at the downstream side of a bridge
(either with vertical wall or spill-through abutments). This flow separation causes vertical vortices which erode
the approach embankment and the downstream corner of the abutment.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-80
AREMA Manual for Railway Engineering
Natural Waterways
Sizing Rock Riprap at Abutments
For Froude Numbers (V/(gy)1/2) 0.80, the recommended design equation for sizing rock riprap for spillthrough and vertical wall abutments is in the form of the Isbash relationship:
2
D 50
K
V
--------- = -------------------- ------y
 S s – 1  gy
EQ 24
where:
D50 = median stone diameter, m (ft)
V = characteristics average velocity in the contracted section (explained below), m/s (ft/s)
Ss = specific gravity of rock riprap
g = gravitational acceleration, 9.81 m/s2 (32.2 ft/s2)
y = depth of flow in the contracted bridge opening, m (ft)
K = 0.89 for a spill-through abutment
1.02 for a vertical wall abutment
For Froude Numbers >0.80, EQ 25 is recommended:
2
D 50
K
V
---------- = -------------------- ------y
 S s – 1  gy
0.14
EQ 25
1
where:
K = 0.61 for spill through abutments
= 0.69 for vertical wall abutments
3
4
Figure 1-3-31. Section View of a Typical Setup of Spill-through Abutment on a Floodplain With
Adjacent Main Channel
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-81
Roadway and Ballast
Figure 1-3-32. Plan View of the Location of Initial Failure Zone of Rock Riprap for Spill-through
Abutment
In both equations, the coefficient K, is a velocity multiplier to account for the apparent local acceleration of flow
at the point of rock riprap failure. Both of these equations are envelope relationships that were forced to over
predict 90 percent of the laboratory data.
A recommended procedure for selecting the characteristic average velocity is as follows:
(1) Determine the set-back ratio (SBR) of each abutment. SBR is the ratio of the set-back length to
channel flow depth. The set-back length is the distance from the near edge of the main channel to
the toe of abutment.
SBR = Set-back length/average channel flow depth
(a) If SBR is less than 5 for both abutments (Figure 1-3-33), compute a characteristic average
velocity, Q/A, based on the entire contracted area through the bridge opening. This includes the
total upstream flow, exclusive of that which overtops the railroad.
(b) If SBR is greater than 5 for an abutment (Figure 1-3-34), compute a characteristic average
velocity, Q/A, for the respective overbank flow only. Assume that the entire respective overbank
flow stays in the overbank section through the bridge opening.
(c) If SBR for an abutment is less than 5 and SBR for the other abutment at the same site is more
than 5 (Figure 1-3-35), a characteristic average velocity determined from Step 1a for the
abutment with SBR less than 5 may be unrealistically low. This would, of course, depend upon
the opposite overbank discharge as well as how far the other abutment is set back. For this case,
the characteristic average velocity for the abutment with SBR less than 5 should be based on the
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-82
AREMA Manual for Railway Engineering
Natural Waterways
flow area limited by the boundary of that abutment and an imaginary wall located on the
opposite channel bank. The appropriate discharge is bounded by this imaginary wall and the
outer edge of the floodplain associated with that abutment.
(2) Compute rock riprap size from EQ 24 or EQ 25, based on the Froude Number limitation for these
equations.
(3) Determine extent of rock riprap.
(a) The apron at the toe of the abutment should extend along the entire length of the abutment toe,
around the curved portions of the abutment to the point of tangency with the plane of the
embankment slopes.
(b) The apron should extend from the toe of the abutment into the bridge waterway a distance equal
to twice the flow depth in the overbank area near the embankment, but need not exceed 25 ft
(Figure 1-3-36).
(c) Spill-through abutment slopes should be protected with the rock riprap size computed from EQ
24 or EQ 25 to an elevation 2 ft above expected high water elevation for the design flood.
Upstream and downstream coverage should agree with step 3a except that the downstream
riprap should extend back from the abutment 2 flow depths or 25 ft which ever is larger to
protect the approach embankment. In the southeast a guide bank 50 ft long at the downstream
end of the abutment to protect the downstream side of the abutment is often used.
(d) The rock riprap thickness should not be less than the larger of either 1.5 times D50 or D100. The
rock riprap thickness should be increased by 50 percent when it is placed under water to provide
for the uncertainties associated with this type of placement.
1
(e) The rock riprap gradation and potential need for underlying filter material must be considered
(see Article 3.6.4.5).
3
Design Example for Riprap at Bridge Abutments
Riprap is to be sized for an abutment located on the floodplain at an existing bridge. The bridge is 650 ft long,
has spill through abutments on a 1V:2H side slope and 7 equally spaced spans. The left abutment is set back
from the main channel 225 ft. Given the following table of hydraulic characteristics for the left abutment size
the riprap.
Hydraulic Property
Value
Remarks
y (ft)
2.7
Flow depth adjacent to abutment
Q (cfs)
7,720
Discharge in left overbank
A (ft2)
613.5
Flow area of left overbank
Step 1. Determine characteristic average velocity, V. Abutment is set back more than 5 average flow depths,
therefore overbank discharge and areas are used to determine V.
V = Q/A = 7720/613.5 = 12.6 ft/s
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-83
4
Roadway and Ballast
Figure 1-3-33. Characteristic Average Velocity for SBR<5
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-84
AREMA Manual for Railway Engineering
Natural Waterways
1
3
4
Figure 1-3-34. Characteristic Average Velocity for SBR>5
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-85
Roadway and Ballast
Figure 1-3-35. Characteristic Average Velocity for SBR>5 and SBR<5
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-86
AREMA Manual for Railway Engineering
Natural Waterways
1
3
4
Figure 1-3-36. Plan View of the Extension of Rock Riprap Apron
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-87
Roadway and Ballast
Step 2. Determine the Froude Number of the flow.
Fr = V/(gy)1/2 = 12.6/(32.2(2.7)) = 1.35
Step 3. Determine the D50 of the riprap for the left abutment. The Froude Number is greater than 0.8,
therefore, use Equation 8.3.
2
D 50
K
V
---------- = -------------------- ------y
 S s – 1  gy
0.14
2
D 50
0.61
12.6
---------- = --------------------- -----------------------------2.7
2.65 – 1  32.2   2.7 
0.14
= 0.40
Step 4. Determine riprap extent and layout.
• Extent into floodplain from toe of slope = 2(2.7) = 5.4 ft
• Vertical extent up abutment slope from floodplain = 2.0 ft + 2.7 ft = 4.7 ft
• The downstream face of the embankment should be protected a distance of 25 ft from the point of
tangency between the curved portion of the abutment and the plane of the embankment slope.
• Riprap mattress thickness = 1.5 (1.1) = 1.7 ft. Also, the thickness should not be less than D100.
• Riprap gradation and filter requirements should be designed using Article 3.6.4.5. This portion of the
design is not conducted for this example.
References for Riprap at Abutments
Atayee, A. Tamin, 1993, "Study of Riprap as Scour Protection for Spill-through Abutment," presented at the
72nd Annual TRB meeting in Washington, D.C., January.
Lagasse, P.F., Zevenbergen, L.W., Schall, J.D., and Clopper, P.E., 2001. "Bridge Scour and Stream Instability
Countermeasures – Experience, Selection, and Design Guidelines," Second Edition, Report FHWA NHI 01-003,
Federal Highway Administration, Hydraulic Engineering Circular No. 23, U.S. Department of Transportation,
Washington, D.C.
Pagan-Ortiz, Jorge E., 1991, "Stability of Rock Riprap for Protection at the Toe of Abutments Located at the
Floodplain," FHWA Research Report No. FHWA-RD-91-057, U.S. Department of Transportation, Washington,
D.C.
3.6.4.3 Guide Banks
Background
When embankments encroach on wide flood plains, the flows from these areas must flow parallel to the
approach embankment to the bridge opening. These flows can erode the approach embankment. A severe flow
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-88
AREMA Manual for Railway Engineering
Natural Waterways
contraction at the abutment can reduce the effective bridge opening, which could possibly increase the severity
of abutment and pier scour.
Guide banks (formerly known as spur dikes) can be used in these cases to prevent erosion of the approach
embankments by cutting off the flow adjacent to the embankment, guiding streamflow through a bridge
opening, and transferring scour away from abutments to prevent damage caused by abutment scour. The two
major enhancements guide banks bring to bridge design are (1) reduce the separation of flow at the upstream
abutment face and thereby maximize the use of the total bridge waterway area, and (2) reduce the abutment
scour due to lessening turbulence at the abutment face. Guide banks can be used on both sand- and gravel-bed
streams.
Principal factors to be considered when designing guide banks, are their orientation to the bridge opening, plan
shape, upstream and downstream length, cross-sectional shape, and crest elevation. Bradley is used as the
principal design reference for this section (Bradley 1978).
Figure 1-3-37 presents a typical guide bank plan view. It is apparent from the figure that without this guide
bank overbank flows would return to the channel at the bridge opening, which can increase the severity of
contraction and scour at the abutment. Note, that with installation of guide banks the scour holes which
normally would occur at the abutments of the bridge are moved upstream away from the abutments. Guide
banks may be designed at each abutment, as shown, or singly, depending on the amount of overbank or flood
plain flow directed to the bridge by each approach embankment.
1
3
4
Figure 1-3-37. Typical Guide Bank (Modified from Bradley)
The goal in the design of guide banks is to provide a smooth transition and contraction of the streamflow
through the bridge opening. Ideally, the flow lines through the bridge opening should be straight and parallel.
As in the case with other countermeasures, the designer should consider the principles of river hydraulics and
morphology, and exercise sound engineering judgment.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-89
Roadway and Ballast
Design Guidelines
Orientation: Guide banks should start at and be set parallel to the abutment and extend upstream from the
bridge opening. If there are guide banks at each abutment, the distance between them at the bridge opening
should be equal to the distance between bridge abutments. Best results are obtained by using guide banks with
a plan form shape in the form of a quarter of an ellipse, with the ratio of the major axis (length Ls) to the minor
axis (offset) of IV:2.5H. This allows for a gradual constriction of the flow. Thus, if the length of the guide bank
measured perpendicularly from the approach embankment to the upstream nose of the guide bank is denoted
as Ls, the amount of expansion of each guide bank (offset), measured from the abutment parallel to the
approach embankment, should be 0.4 Ls.
The plan view orientation can be determined using EQ 26, which is the equation of an ellipse with origin at the
base of the guide bank. For this equation, X is the distance measured perpendicularly from the bridge approach
and Y is the offset measured parallel to the approach embankment, as shown on Figure 1-3-37.
EQ 26
It is important that the face of the guide bank match the abutment so that the flow is not disturbed where the
guide bank meets the abutment. For new bridge construction, abutments can be sloped to the channel bed at
the same angle as the guide bank. For retrofitting existing bridges modification of the abutments or wing walls
may be necessary.
Length: For design of guide banks, the length of the guide bank, Ls must first be determined. This can be
easily determined using a nomograph which was developed from laboratory tests performed at Colorado State
University and from field data compiled by the USGS. For design purposes the use of the nomograph involves
the following parameters:
Q = total discharge of the stream, m3/s (ft3/s)
Qf = lateral or flood plain discharge of either flood plain intercepted by the embankment,
m3/s (cfs) (ft3/s)
QA = discharge in 30 m (100 ft) of stream adjacent to the abutment, m3/s (ft3/s)
b = length of the bridge opening, m (ft)
An2 = cross-sectional flow area at the bridge opening at normal stage, m2 (ft2)
Vn2 = Q/An2 = average velocity through the bridge opening, m/s (ft/s)
Qf/QA = guide bank discharge ratio
Ls = projected length of guide bank, m (ft)
A nomograph is presented in Figure 1-3-38 to determine the projected length of guide banks. This nomograph
should be used to determine the guide bank length for designs greater than 50 ft and less than 250 ft. If the
nomograph indicates the length required to be greater than 250 ft the design should be set at 250 ft. It is
recommended that the minimum length of guide banks be 50 ft. An example of how to use this nomograph is
presented in the next section.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-90
AREMA Manual for Railway Engineering
Natural Waterways
1
3
4
Figure 1-3-38. English Version of Nomograph to Determine Guidebank Length (after Bradley)
FHWA practice has shown that many guide banks have performed well using a standardized length of 150 ft.
Based on this experience, guide banks of 150 ft in length should perform very well in most locations. Even
shorter guide banks have been successful if the guide bank intersects the tree line. If the main channel is equal
to or less than 100 ft use the total main channel flow in determining the guide bank discharge ratio (Qf/QA).
Crest Height: As with deflection spurs, guide banks should be designed so that they will not be overtopped at
the design discharge. If this were allowed to occur, unpredictable cross flows and eddies might be generated,
which could scour and undermine abutments and piers. In general, a minimum of 2 ft of freeboard, above the
design water surface elevation should be maintained.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-91
Roadway and Ballast
Shape and Size: The cross-sectional shape and size of guide banks should be similar to deflector, or
deflector/retarder spurs discussed in Article 3.6.4.4. Generally, the top width is 10 to 13 ft, but the minimum
width is 3 ft when construction is by drag line. The upstream end of the guide bank should be round nosed.
Side slopes should be 1V:2H or less.
Downstream Extent: In some locations, guide banks have been extended downstream of the abutments to
minimize scour due to rapid expansion of the flow at the downstream end of the abutments. These downstream
guide banks are sometimes called "heels." If the expansion of the flow is too abrupt, a shorter guide bank, which
usually is less than 50 ft long, can be used downstream. Downstream guide banks should also start at and start
parallel to the abutment and the distance between them should enlarge as the distance from the abutment of
the bridge increases.
In general, downstream guide banks are a shorter version of the upstream guide banks. Riprap protection,
crest height and width should be designed in the same manner as for upstream guide banks.
Riprap: Guide banks are constructed by forming an embankment of soil or sand extending upstream from the
abutment of the bridge. To inhibit erosion of the embankment materials, guide banks must be adequately
protected with riprap or stone facing.
Rock riprap should be placed on the stream side face as well as around the end of the guide bank. It is not
necessary to riprap the side of the guide bank adjacent to the railroad approach embankment. As in the case of
spurs, a gravel, sand, or geotextile filter may be required to protect the underlying embankment material (see
HEC-11 and Article 3.6.4.5). Riprap should be extended below the bed elevation to a depth as recommended in
Article 3.6.4.5 (below the combined long-term degradation and contraction scour depth), and extend up the face
of the guide bank to 2 ft above the design flow. Additional riprap should be placed around the upstream end of
the guide bank so to protect the embankment from scour.
As in the case of spurs, it is important to adequately tie guide banks into the approach embankment for guide
banks on non-symmetrical railroad crossings. Hydraulics of Bridge Waterways (Bradley 1978) states:
"From meager testing done to date, there is not sufficient evidence to warrant using longer dikes (guide
banks) at either abutment on skewed bridges. Lengths obtained from [the nomograph] should be adequate
for either normal or skewed crossings."
Therefore, for skewed crossings, the length of guide banks should be set using the nomograph for the side of the
bridge crossing which yields the largest guide bank length.
Other Design Concerns: In some cases, where the cost of stone riprap facing is prohibitive, the guide bank can
be covered with sod or other minimal protection. If this approach is selected, the design should allow for and
stipulate the repair or replacement of the guide bank after each high water occurrence. Other measures which
will minimize damage to approach embankments, and guide banks during high water are:
Keep trees as close to the toe of guide bank embankments as construction will permit. Trees will
increase the resistance to flow near and around the toe of the embankment, thus reducing velocities and
scour potential.
Do not allow the cutting of channels or the digging of borrow pits along the upstream side of approach
embankments and near guide banks. Such practices encourage flow concentration and increases
velocities and erosion rates of the embankments.
In some cases, the area behind the guide bank may be too low to drain properly after a period of flooding.
This can be a problem, especially when the guide bank is relatively impervious. Small drain pipes can be
installed in the guide bank to drain this ponded water.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-92
AREMA Manual for Railway Engineering
Natural Waterways
In some cases, only one approach will cut off the overbank flow. This is common when one of the banks
is high and well defined. In these cases, only one guide bank may be necessary.
Design Example Of Guide Bank Installation
For the example design of a guide bank, Figure 1-3-39 will be used. This figure shows the cross-section of the
channel and flood plain before the bridge is constructed and the plan view of the approach, guide banks, and
embankments after the design steps outlined below are completed.
Step 1. Hydraulic Design Parameters
The first step in the design of guide banks requires the computation of the depth and velocity of the design
flood in the main channel and in the adjacent overbank areas. These studies are performed by using step
backwater computations upstream and through the bridge opening. The computer program HEC River
Analysis System (RAS) is suitable for these computations. Using this program or by using conveyance curves
developed from actual data, the discharges and depths in the channel and overbank areas can be determined.
To use the conveyance curve approach, the designer is referred to example problem number 4 in Hydraulics of
Bridge Waterways (Bradley 1978) for methods to determine these discharges and areas. That publication also
contains another example of the design of a guide bank.
For this example, the total, overbank, and channel discharges, as well as the flow area are given. We also
assume that a bridge will span a channel with a bottom width of 230 ft and that the abutments will be set
back 148 ft from each bank of the main channel. The abutments of this bridge are spill-through with a side
slope of 1V:2H. The design discharge is 12,360 cfs, which after backwater computations, results in a mean
depth of 11.8 ft in the main channel and a mean channel velocity of 3 ft/s.
Step 2. Determine Qf in the Left and Right Overbank
1
3
The depth in each overbank area is given as 3.9 ft and the widths of the left and right overbank areas are 295 ft
and 590 ft, respectively. Velocity in the overbank areas (assuming no railroad approach embankment, i.e., at an
upstream cross section) is 1.2 ft/s. The floodplain flow is equal to 1,413 cfs for the left overbank and 2,825 cfs
for the right overbank.
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-93
Roadway and Ballast
Figure 1-3-39. Example Guide Bank Design
Using the continuity equation and noting that the abutments are set back 148 ft from each bank, the flood
plain discharge intercepted by each approach embankment is:
Q = AV
(Qf) right = 2,825 - (148) (3.9) (1.2) = 2132 cfs
(Qf) left = 1,413 - (148 (3.9) (1.2) = 720 cfs
Step 3. Determine QA and Qf/QA for the Left and Right Overbank
The overbank discharge in the first 100 ft of opening adjacent to the left and right abutments needs to be
determined next. Since for this case the flow is of uniform depth (3.9 ft) and velocity (1.2 ft/s) over the entire
width of the floodplain, and both abutments are set back more than 100 ft from the main channel banks, the
value of QA will be the same for both sides:
(QA) right = (100) (3.9) (1.2) = 468 cfs
(QA) left = (100 (3.9) (1.2) = 468 cfs
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-94
AREMA Manual for Railway Engineering
Natural Waterways
For the left and right overbanks the reference values of Qf /QA can be determined by simple division of the
discharges determined in previous steps:
For design purposes, the largest value will result in the more conservative determination of the length of the
guide banks, except where Step 4 indicates a guide bank is required for only one of the overbank areas.
Step 4. Determine the Length of the Guide Bank, Ls
The average channel velocity through the bridge opening can be determined by dividing the total discharge of
the stream, Q, by the cross-sectional flow area at the bridge opening, An2, which in this case includes the main
channel (2,714 ft2) plus 148 ft of the left and right overbank areas adjacent to the abutments at the bridge
opening (1,154 ft2). Thus:
1
For Qf /QA equal to 4.5 and an average channel velocity of 3.2 ft/s, the length of the guide bank is determined
using the nomograph presented in Figure 1-3-38.
For the left abutment, a Qf /QA of 1.5 and Vn2 of 3.2 ft/s indicate that Ls would be less than 50 ft. Thus, no
guide bank is required for the left overbank for this example.
3
Step 5. Miscellaneous Specifications
The offset of the guidebank is determined to be 55.2 ft by multiplying Ls by 0.4. The offset and length
determine the plan layout of the guide bank. Coordinates of points along the centerline can be determined
using EQ 26, which is the equation of an ellipse with a major to minor axis ratio of 2.5:1. The coordinates for a
138 ft long guide bank with a 55.2 ft offset are presented in Table 1-3-15.
These coordinates would be used for conceptual level design. For construction, coordinates at an offset or along
the toe of side slope would be necessary.
The crest of the guide bank must be a minimum of 2 ft above the design water surface (elevation 1070.2 ft).
Therefore, the crest elevation for this example should be greater than or equal to 1072.2 ft. The crest width
should be at least 3 ft. For this example, a crest width of 10 ft will be specified so that the guide bank can be
easily constructed with dump trucks.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-95
4
Roadway and Ballast
Table 1-3-15. Coordinates for Guide Bank on the Right Bank of Figure 10.4
X (ft)
Y (ft)
0
55.2
30
53.9
60
49.7
90
41.8
120
27.3
138
0.0
Stone or rock riprap should be placed in the locations shown on Figure 1-3-39. This riprap should extend a
minimum of 2 ft above the design water surface (elevation 1070.2 m) and below the intersection of the toe of
the guide bank and the existing ground to the combined long-term degradation and contraction scour depth.
References for Guidebank Design
Bradley, J.N., 1978. "Hydraulics of Bridge Waterways," Hydraulic Design Series No. I U.S. Department of
Transportation, FHWA.
Brown, S.A. and Clyde, E.S., 1989. "Design of Riprap Revetment," Hydraulic Engineering Circular No. 11,
FHWA-IP-89-016. Prepared for the Federal Highway Administration, Washington, D.C.
Karaki, S.S., 1959. "Hydraulic Model Study of Spur Dikes for Highway Bridge Openings," Colorado State
University, Civil Engineering Section, Report CER59SSK36, September, 47 pp.
Karaki, S.S., 1961. "Laboratory Study of Spur Dikes for Highway Bridge Protection," Highway Research Board
Bulletin 286, Washington, D.C., p. 31.
Lagasse, P.F., Zevenbergen, L.W., Schall, J.D., and Clopper, P.E., 2001. "Bridge Scour and Stream Instability
Countermeasures – Experience, Selection, and Design Guidelines," Second Edition, Report FHWA NHI 01-003,
Federal Highway Administration, Hydraulic Engineering Circular No. 23, U.S. Department of Transportation,
Washington, D.C.
U.S. Army Corps of Engineers, 2001. "HEC-RAS River Analysis System," User's Manual, Version 3.0 ,
Hydrologic Engineering Center, Davis, CA.
3.6.4.4 Spurs
Background
A spur can be a pervious or impervious structure projecting from the streambank into the channel. Spurs are
used to deflect flowing water away from, or to reduce flow velocities in critical zones near the streambank, to
prevent erosion of the bank, and to establish a more desirable channel alignment or width. The main function
of spurs is to reduce flow velocities near the bank, which in turn, encourages sediment deposition due to these
reduced velocities. Increased protection of banks can be achieved over time, as more sediment is deposited
behind the spurs. Because of this, spurs may protect a streambank more effectively and at less cost than
revetments. Furthermore, by moving the location of any scour away from the bank, partial failure of the spur
can often be repaired before damage is done to structures along and across the stream.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-96
AREMA Manual for Railway Engineering
Natural Waterways
Spurs are generally used to halt meander migration at a bend. They are also used to channelize wide, poorly
defined streams into well-defined channels. The use of spurs to establish and maintain a well-defined channel
location, cross section, and alignment in braided streams can decrease the required bridge lengths, thus
decreasing the cost of bridge construction and maintenance.
Spur types are classified based upon their permeability as retarder spurs, retarder/deflector spurs, and
deflector spurs. The permeability of spurs is defined simply as the percentage of the spur surface area facing
the streamflow that is open. Deflector spurs are impermeable spurs which function by diverting the primary
flow currents away from the bank. Retarder/deflector spurs are more permeable and function by retarding flow
velocities at the bank and diverting flow away from the bank. Retarder spurs are highly permeable and
function by retarding flow velocities near the bank.
Design Considerations
Spur design includes setting the limits of bank protection required; selection of the spur type to be used; and
design of the spur installation including spur length, orientation, permeability, height, profile, and spacing.
Longitudinal Extent of Spur Field. The longitudinal extent of channel bank requiring protection is discussed in
Brown (1985, 1989). Figure 1-3-40 was developed from USACE studies of the extent of protection required at
meander bends (USACE 1981). The minimum extent of bank protection determined from Figure 1-3-40 should
be adjusted according to field inspections to determine the limits of active scour, channel surveys at low flow,
and aerial photography and field investigations at high flow. Investigators of field installations of bank
protection have found that protection commonly extends farther upstream than necessary and not far enough
downstream. However, such protection may have been necessary at the time of installation. The lack of a
sufficient length of protection downstream is generally more serious, and the downstream movement of
meander bends should be considered in establishing the downstream extent of protection.
1
3
4
Figure 1-3-40. Extent of Protection Required at a Channel Bend (after USACE)
Spur Length. Spur length is taken here as the projected length of spur normal to the main flow direction or
from the bank. Where the bank is irregular, spur lengths must be adjusted to provide for an even curvature of
the thalweg. The length of both permeable and impermeable spurs relative to channel width affects local scour
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-97
Roadway and Ballast
depth at the spur tip and the length of bank protected. Laboratory tests indicate that diminishing returns are
realized from spur lengths greater than 20 percent of channel width. The length of bank protected measured in
terms of projected spur length is essentially constant up to spur lengths of 20 percent of channel width for
permeable and impermeable spurs. Field installations of spurs have been successful with lengths from 3 to 30
percent of channel width. Impermeable spurs are usually installed with lengths of less than 20 percent while
permeable spurs have been successful with lengths up to 25 percent of channel width. However, only the most
permeable spurs were effective at greater lengths.
The above discussion assumes that stabilization of the bend is the only objective when spur lengths are
selected. It also assumes that the opposite bank will not erode. Where flow constriction or changing the flow
path is also an objective, spur lengths will depend on the degree of constriction required or the length of spur
required to achieve the desired change in flow path. At some locations, channel excavation on the inside of the
bend may be required where spurs would constrict the flow excessively. However, it may be acceptable to allow
the stream to do its own excavation if it is located in uniformly graded sand
Spur Orientation. Spur orientation refers to spur alignment with respect to the direction of the main flow
current in a channel. Figure 1-3-41 defines the spur angle such that an acute spur angle means that the spur is
angled in an downstream direction and an angle greater than 90 indicates that the spur is oriented in a
upstream direction.
Figure 1-3-41. Definition Sketch for Spur Angle (after Karaki 1959)
Permeable retarder spurs are usually designed to provide flow retardance near the streambank, and they
perform this function equally as well without respect to the spur angle. Since spurs oriented normal to the
bank and projecting a given length into the channel are shorter than those at any other orientation, all retarder
spurs should be constructed at 90 with the bank for reasons of economy.
Spur orientation at approximately 90 has the effect of forcing the main flow current (thalweg) farther from the
concave bank than spurs oriented in an upstream or downstream direction. Therefore, more positive flow
control is achieved with spurs oriented approximately normal to the channel bank. Spurs oriented in an
upstream direction cause greater scour than if oriented normal to the bank, and spurs oriented in a
downstream direction cause less scour.
It is recommended that the spur furthest upstream be angled downstream to provide a smoother transition of
the flow lines near the bank and to minimize scour at the nose of the leading spur. Subsequent spurs
downstream should all be set normal to the bank line to minimize construction costs.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-98
AREMA Manual for Railway Engineering
Natural Waterways
Spur Permeability. The permeability of the spur depends on stream characteristics, the degree of flow
retardance and velocity reduction required, and the severity of the channel bend. Impermeable spurs can be
used on sharp bends to divert flow away from the outer bank. Where bends are mild and only small reductions
in velocity are necessary, highly permeable retarder spurs can be used successfully. However, highly permeable
spurs can also provide required bank protection under more severe conditions where vegetation and debris will
reduce the permeability of the spur without destroying the spur. This is acceptable provided the bed load
transport is high.
Spurs of varying permeability will provide protection against meander migration. Impermeable spurs provide
more positive flow control but cause more scour at the toe of the spur and, when submerged, cause erosion of
the streambank. High permeability spurs are suitable for use where only small reductions in flow velocities are
necessary as on mild bends but can be used for more positive flow control where it can be assumed that clogging
with small debris will occur and bed load transport is large. Spurs with permeability up to about 35 percent can
be used in severe conditions but permeable spurs may be susceptible to damage from large debris and ice.
Spur Height and Crest Profile. Impermeable spurs are generally designed not to exceed the bank height
because erosion at the end of the spur in the overbank area could increase the probability of outflanking at high
stream stages. Where stream stages are greater than or equal to the bank height, impermeable spurs should be
equal to the bank height. If flood stages are lower than the bank height, impermeable spurs should be designed
so that overtopping will not occur at the bank. Bank erosion is more severe if the spur is oriented in the
downstream direction.
The crest of impermeable spurs should slope downward away from the bank line, because it is difficult to
construct and maintain a level spur of rock or gabions. Use of a sloping crest will avoid the possibility of
overtopping at a low point in the spur profile, which could cause damage by particle erosion or damage to the
streambank.
1
Permeable spurs, and in particular those constructed of light wire fence, should be designed to a height that
will allow heavy debris to pass over the top. However, highly permeable spurs consisting of jacks or
tetrahedrons are dependent on light debris collecting on the spur to make them less permeable. The crest
profile of permeable spurs is generally level except where bank height requires the use of a sloping profile.
3
Bed and Bank Contact. The most common causes of spur failure are undermining and outflanking by the
stream. These problems occur primarily in alluvial streams that experience wide fluctuations in the channel
bed. Impermeable rock riprap spurs and gabion spurs can be designed to counter erosion at the toe by
providing excess material on the streambed as illustrated in Figure 1-3-42 and Figure 1-3-43. As scour occurs,
excess material is launched into the scour hole, thus protecting the end of the spur. Gabion spurs are not as
flexible as riprap spurs and may fail in very dynamic alluvial streams.
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-99
Roadway and Ballast
Figure 1-3-42. Launching of Stone Protection on a Riprap Spur
(a) before launching at low flow, (b) during launching at high flow, and (c) after scour
subsides (after Brown)
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-100
AREMA Manual for Railway Engineering
Natural Waterways
1
3
4
Figure 1-3-43. Gabion Spur Illustrating Flexible Mat Tip Protection
(a) before launching at low flow, (b) during launching at high flow, and (c) after scour subsides
(after Brown)
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-101
Roadway and Ballast
Permeable spurs can be similarly protected with a riprap toe as illustrated in Figure 1-3-44. The necessity for
using riprap on the full length of the spur or any riprap at all is dependent on the erodibility of the streambed,
the distance between the slats and the streambed, and the depth to which the piling are driven. This would
also be appropriate as a retrofit measure at a spur that has been severely undermined, and as a design for
locations at which severe erosion of the toe of the streambank is occurring.
Figure 1-3-44. Permeable Wood-slat Fence Spur Showing Launching of Stone Toe Material
(after Brown)
Piles supporting permeable structures can also be protected against undermining by driving piling to depths
below the estimated scour. Round piling are recommended because they minimize scour at their base.
Extending the facing material of permeable spurs below the streambed also significantly reduces scour. If the
retarder spur or retarder/deflector spur performs as designed, retardance and diversion of the flow within the
length of the structure may make it unnecessary to extend the facing material the full depth of anticipated
scour except at the nose.
Spur Spacing. Spur spacing is a function of spur length, spur angle, permeability, and the degree of curvature
of the bend. The flow expansion angle, or the angle at which flow expands toward the bank downstream of a
spur, is a function of spur permeability and the ratio of spur length to channel width. This ratio is susceptible
to alteration by excavation on the inside of the bend or by scour caused by the spur installation. Figure 1-3-45
indicates that the expansion angle for impermeable spurs is an almost constant 17. Spurs with 35 percent
permeability have almost the same expansion angle except where the spur length is greater than about 18
percent of the channel width.
As permeability increases, the expansion angle increases, and as the length of spurs relative to channel width
increases, the expansion angle increases exponentially. The expansion angle varies with the spur angle, but not
significantly.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-102
AREMA Manual for Railway Engineering
Natural Waterways
Figure 1-3-45. Relationship Between Spur Length and Expansion Angle for Several Spur
Permeabilities (after Brown)
1
Spur spacing in a bend can be established by first drawing an arc representing the desired flow alignment
(Figure 1-3-46). This arc will represent the desired extreme location of the thalweg nearest the outside bank in
the bend. The desired flow alignment may differ from existing conditions or represent no change in conditions,
depending on whether there is a need to arrest erosion of the concave bank or reverse erosion that has already
occurred. If the need is to arrest erosion, permeable retarder spurs or retarder structures may be appropriate.
If the flow alignment must be altered in order to reverse erosion of the bank or to alter the flow alignment
significantly, deflector spurs or retarder/deflector spurs are appropriate. The arc representing the desired flow
alignment may be a compound circular curve or any curve which forms a smooth transition in flow directions.
3
4
Figure 1-3-46. Spur Spacing in a Meander Bend (after Brown)
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-103
Roadway and Ballast
Next, draw an arc representing the desired bankline. This may approximately describe the existing concave
bank or a new theoretical bankline which protects the existing bank from further erosion. Also, draw an arc
connecting the nose (tip) of spurs in the installation. The distance from this arc to the arc describing the
desired bank line, along with the expansion angle, fixes the spacing between spurs. The arc describing the ends
of spurs projecting into the channel will be essentially concentric with the arc describing the desired flow
alignment.
Establish the location of the spur at the downstream end of the installation. This is normally the protected
abutment or guidebank at the bridge. Finally, establish the spacing between each of the remaining spurs in the
installation (Figure 1-3-46). The distance between spurs, S, is the length of spur, L, between the arc
describing the desired bank line and the nose of the spur multiplied by the cotangent of the flow expansion
angle, . This length is the distance between the nose of spurs measured along a chord of the arc describing spur
nose location. Remaining spurs in the installation will be at the same spacing if the arcs are concentric. The
procedure is illustrated by Figure 1-3-46 and expressed in EQ 27.
S = L cot
EQ 27
where:
S = spacing between spurs at the nose, m (ft)
L = effective length of spur, or the distance between arcs describing the toe of spurs and the
desired bank line, m (ft)
 expansion angle downstream of spur nose, degrees
At less than bankfull flow rates, flow currents may approach the concave bank at angles greater than those
estimated from Figure 1-3-45. Therefore, spurs should be well-anchored into the existing bank, especially the
spur at the upstream end of the installation, to prevent outflanking.
Shape and Size of Spurs. In general, straight spurs should be used for most bank protection. Straight spurs are
more easily installed and maintained and require less material. For permeable spurs, the width depends on the
type of permeable spur being used. Less permeable retarder/deflector spurs which consist of a soil or sand
embankment should be straight with a round nose as shown in Figure 1-3-47.
The top width of embankment spurs should be a minimum of 3 ft. However, in many cases the top width will be
dictated by the width of any earth moving equipment used to construct the spur. In general a top width equal
to the width of a dump truck can be used. The side slopes of the spur should be 1V:2H or flatter.
Riprap. Rock riprap should be placed on the upstream and downstream faces as well as on the nose of the spur
to inhibit erosion of the spur. Depending on the embankment material being used, a gravel, sand, or geotextile
may be required (see HEC-11). The designer is referred to HEC-11 and Article 3.6.4.5 for design procedures for
sizing riprap at spurs.
It is recommended that riprap be extended below the bed elevation to a depth equal to the combined long-term
degradation and contraction scour depth. Riprap should also extend to the crest of the spur, in cases where the
spur would be submerged at design flow, or to 2 ft above the design flow, if the spur crest is higher than the
design flow depth. Additional riprap should be placed around the nose of the spur (Figure 1-3-47), so that spur
will be protected from scour. Figure 1-3-48 shows an example of an impermeable spur field and a close-up of a
typical round nose spur installation.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-104
AREMA Manual for Railway Engineering
Natural Waterways
Figure 1-3-47. Typical Straight, Round Nose Spur
Design Example of Spur Installation
Figure 1-3-49 illustrates a location at which a migrating bend threatens an existing bridge (existing conditions
are shown with a solid line). Ultimately, based upon the following design example, seven spurs will be required.
Although the number of spurs is not known in advance, the spurs (and other design steps) are shown as dashed
lines on Figure 1-3-49 as they will be specified after completing the following design example. Assume that the
width of the river from the desired (north) bankline to the existing (south) bankline is 164 ft.
For this example, it is desirable to establish a different flow alignment and to reverse erosion of the concave
(outside) bank. The spur installation has two objectives: (1) to stop migration of the meander before it
damages the railroad stream crossing, and (2) to reduce scour at the bridge abutment and piers by aligning flow
in the channel with the bridge opening. Impermeable deflector spurs are suitable to accomplish these
objectives and the stream regime is favorable for the use of this type of countermeasure. The expansion angle
for this spur type is approximately 17 for a spur length of about 20 percent of the desired channel width, as
indicated in Figure 1-3-45.
1
3
Step 1. Sketch Desired Thalweg
The first step is to sketch the desired thalweg location (flow alignment) with a smooth transition from the
upstream flow direction through the curve to an approach straight through the bridge waterway (Figure 1-349). Visualize both the high-flow and low-flow thalwegs. For an actual location, it would be necessary to
examine a greater length of stream to establish the most desirable flow alignment. Then draw an arc
representing the desired bankline in relation to thalweg locations. The theoretical or desired left bank line is
established as a continuation of the bridge abutment and left bank downstream through the curve, smoothly
joining the left bank at the upstream extremity of eroded bank.
Step 2. Sketch Alignment of Spur Tips
The second step is to sketch a smooth curve through the nose (tip) locations of the spurs, concentric with the
desired bankline alignment. Using a guideline of 20 percent of the desired channel width for impermeable
spurs (see Spur Length) the distance, L, from the desired bankline to the spur tips (Figure 1-3-49) would be:
L = 0.20(164ft) = 33ft
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-105
4
Roadway and Ballast
Figure 1-3-48. Impermeable Spur Field in Top Photograph With Close-up Shot of One Spur in the
Lower Photograph, Vicinity of the Richardson Highway, Delta River, Alaska
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-106
AREMA Manual for Railway Engineering
Natural Waterways
Figure 1-3-49. Example of Spur Design
1
Step 3. Locate First Spur
Step number three is to locate spur number 1 so that flow expansion from the nose of the spur will intersect the
streambank downstream of the abutment. This is accomplished by projecting an angle of 17 from the abutment
alignment to an intersection with the arc describing the nose of spurs in the installation or by use of EQ 27.
Spurs are set at 90 to a tangent with the arc for economy of construction. Alternatively, the first spur could be
considered to be either the upstream end of the abutment or guide bank if the spur field is being installed
upstream of a bridge. Thus, the spur spacing, S, would be:
3
S = L cot = (33ft) cot17 = 108ft
It may be desirable to place riprap on the streambank at the abutment. Furthermore, the size of the scour hole
at the spur directly upstream of the bridge should be estimated using the procedures described in Article 3.5.5.
If the extent of scour at this spur overlaps local scour at the pier, total scour depth at the pier may be increased.
This can be determined by extending the maximum scour depth at the spur tip, up to the existing bed elevation
at the pier at the angle of repose.
Step 4. Locate Remaining Spurs
Spurs upstream of spur number 1 are then located by use of EQ 27, using dimensions as illustrated in Figure 13-46 (i.e., the spacing, S, determined in Step 3). Using this spur spacing, deposition will be encouraged between
the desired bank line and the existing eroded bank.
The seventh and last spur upstream is shown oriented in a downstream direction to provide a smooth
transition of the flow approaching the spur field. This spur could have been oriented normal to the existing
bank, and been shorter and more economical, but might have caused excessive local scour. Orienting the
furthest upstream spur at an angle in the downstream direction provides a smoother transition into the spur
field, and decreases scour at the nose of the spur. As an alternative, a hard point could be installed where the
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-107
4
Roadway and Ballast
bank is beginning to erode (see Article 3.6.4.9). In this case the hard point can be considered as a very short
spur which is located at the intersection of the actual and planned bank lines. In either case, spurs or hard
points should be anchored well into the bank to prevent outflanking.
References for Spur Design
Brown, S.A., 1985. "Streambank Stabilization Measures for Highway Stream Crossings–Executive Summary,"
FHWA/RD-84/099, Federal Highway Administration, Washington, D.C.
Brown, S.A., 1985. "Streambank Stabilization Measures for Highway Engineers," FHWA/RD-84. 100 Federal
Highway Administration, McLean, VA.
Brown, S.A. and Clyde, E.S., 1989. "Design of Riprap Revetment," Hydraulic Engineering Circular No.11,
FHWA-IP-89-016. Prepared for the Federal Highway Administration, Washington, D.C.
Karaki, S.S., 1959. "Hydraulic Model Study of Spur Dikes for Highway Bridge Openings," Colorado State
University, Civil Engineering Section, Report CER59SSK36, September, 47 pp.
Lagasse, P.F., Zevenbergen, L.W., Schall, J.D., and Clopper, P.E., 2001. "Bridge Scour and Stream Instability
Countermeasures – Experience, Selection, and Design Guidelines," Second Edition, Report FHWA NHI 01-003,
Federal Highway Administration, Hydraulic Engineering Circular No. 23, U.S. Department of Transportation,
Washington, D.C.
Richardson, E.V. and Davis, S.R., 2000. "Evaluating Scour at Bridges," Report FHWA NHI 01-001, Federal
Highway Administration, Hydraulic Engineering Circular No. 18, U.S. Department of Transportation,
Washington, D.C.
Richardson, E.V., Simons, D.B., and Lagasse, P.F., 2001. "River Engineering for Highway Encroachments Highways in the River Environment," Report No. FHWA NHI 01-004, Hydraulic Design Series No. 6, Federal
Highway Administration, Washington, D.C.
U.S. Army Corps of Engineers, 1981. "The Streambank Erosion Control Evaluation and Demonstration Act of
1974," Final Report to Congress, Executive Summary and Conclusions.
3.6.4.5 Revetments
Introduction
Revetments are used to provide protection for embankments, streambanks, and streambeds. They may be
flexible or rigid and can be used to counter all erosion mechanisms. They do not significantly constrict channels
or alter flow patterns. Revetments do not provide resistance against slumping in saturated streambanks and
embankments, and are relatively unsuccessful in stabilizing streambanks and streambeds in degrading
streams. Special precautions must be observed in the design of revetments for degrading channels.
Flexible Revetments
Flexible revetments include rock riprap, rock-and-wire mattresses, gabions, precast concrete blocks, rock-fill
trenches, windrow revetments, used tire revetments, and vegetation. Rock riprap adjusts to distortions and
local displacement of materials without complete failure of the revetment installation. However, flexible
rock-and-wire mattress and gabions may sometimes span the displacement of underlying materials, but usually
can adjust to most local distortions (see Article 3.6.4.6). Used tire mattresses and precast concrete block
mattresses are generally stiffer than rock riprap and gabions and, therefore, do not adjust well to local
displacement of underlying materials.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-108
AREMA Manual for Railway Engineering
Natural Waterways
Design guidelines, design procedures, and suggested specifications for rock riprap, wire enclosed rock, stacked
block gabions, and precast concrete blocks are included in HEC-11. Since rock riprap is commonly used as a
countermeasure for stream bank erosion, a short discussion of the types of rock riprap and a design procedure
as discussed in HEC-11 follows.
Riprap as discussed in this section is defined as a flexible channel or bank lining consisting of a well-graded
mixture of angular rock usually dumped in place. Other types of riprap are "hand-placed" and "keyed or plated"
riprap. Hand-placed riprap is carefully placed by hand or by a mechanized manner in a definite pattern with
voids between the large stone being filled with smaller rock. Plated riprap is placed on the bank with a skip and
tamped into place using a heavy steel plate leaving a smoother surface than dumped riprap. See HEC-11 for
more information on each of these types.
Dumped riprap does not mean end dumping from trucks and allowing the material to roll down the slope which
can cause size segregation. It means that the riprap is placed in a manner to prevent segregation by using a
crane with a bucket or dragline. Regardless of how it is placed, care should be taken to prevent segregation of
the rock mixture. Dumped riprap should form a layer of loose stone where individual stones may move
independently to adjust to the movement of the bank material being protected. This minor movement may
occur without complete failure of the installation. This movement allows the riprap to be somewhat "self
healing" and is one of the main advantages of dumped rock riprap.
Design Guidelines
HEC-11 provides design guidance for sizing the rock for dumped riprap used for bank protection. The
procedure is based on the tractive force theory but has velocity as its primary design parameter. The equation
is based on the assumption of uniform or gradually varying flow. A stability factor is used to correct the
equation for bends and turbulent mixing at rapidly varying flow conditions.
1
The stone size is established by this equation:
EQ 28
3
where:
D50 = median particle size, m (ft)
C = correction for specific gravity and stability factor
Va = average velocity in the main channel, m/s (fps)
davg = average flow depth in the main flow channel, m (ft)
K1 = bank angle correction factor as given below
Ku = 0.0059 SI
Ku = 0.001 English
4
2 0.5
sin 
K 1 = 1 – -------------2
sin 
EQ 29
where:
 bank angle with the horizontal
 riprap material’s angle of repose as given in Figure 1-3-50
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-109
Roadway and Ballast
Figure 1-3-50. Angle of Repose of Riprap in Terms of Mean Size and Shape of Stone (Chen and
Cotton 1988)
The average flow depth and velocity used in EQ 28 are main channel values where the main channel is defined
as the area between the channel banks.
The correction for the specific gravity and the stability factor is defined by the following equation:
1.5
1.61  SF 
C = ------------------------------1.5
 Ss – 1 
EQ 30
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-110
AREMA Manual for Railway Engineering
Natural Waterways
where:
Ss = specific gravity of the rock riprap
SF = stability factor as described below
The stability factor (SF) is defined as the ratio of the riprap material critical shear stress and average tractive
force exerted by the flow field. As long as the SF is greater than 1, the critical shear stress of the material is
greater than the flow induced tractive stress, and the riprap is considered stable. A SF of 1.2 was used in the
development of EQ 28.
The SF may be used to reflect the level of uncertainty in the conditions at the site due to discharge estimation
inaccuracies, debris, ice impacts, etc. Suggested values for the SF are:
Condition
SF Range
Uniform flow conditions: Straight or mildly curving reach (curve 1.0 - 1.2
radius/channel width >30); impact from wave action and floating
debris is minimal; little or no uncertainty in design parameters.
Gradually varying flow: Moderate bend curvature (30 > curve 1.3 - 1.6
radius/channel width >10): impact from waves or floating debris
moderate.
Approaching rapidly varying flow: Sharp bend curvature (10 > 1.6 - 2.0
curve radius/channel width); significant impact potential from
floating debris and/or ice; significant wind and/or boat generated
waves (1 - 2 ft); high flow turbulence; turbulent mixing at bridge
abutments; significant uncertainty in design parameters.
1
Thickness of Riprap. All stones should be contained reasonably well within the riprap layer thickness. The
following criteria are given in HEC-11.
3
• It should not be less than the spherical diameter of the D100 stone or less than 1.5 times the spherical
diameter of the D50 stone, whichever results in the greater thickness.
• It should not be less than 1 ft for practical placement.
• The thickness determined by either 1 or 2 should be increased by 50 percent when the riprap is placed
underwater to compensate for uncertainties associated with this placement.
• An increase in layer thickness of 0.5 to 1 ft, accompanied by an increase in stone sizes, should be made
where the riprap will be subject to attack by floating debris, ice, or by waves from boat wakes, wind, or
bedforms.
Gradation of Riprap. The gradation of stones in riprap revetment affects the riprap's resistance to erosion. The
stone should be reasonably well graded throughout the riprap layer thickness. Specifications should provide for
two limiting gradation curves, and the stone gradation (as determined from a field test sample) should lay
within these limits. The gradation limits should not be so restrictive that production costs would be excessive.
HEC-11 presents suggested guidelines for establishing gradation limits (see Table 1-3-16). Table 1-3-16 and
Table 1-3-17 present six suggested gradation classes based on AASHTO specifications (AASHTO 1999).
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-111
4
Roadway and Ballast
Table 1-3-16. Rock Riprap Gradation Limits
Stone Size Range
m (ft)
Stone Weight Range
kg (lb)
Percent of Gradation
Smaller Than
1.5 D50 to 1.7 D50
3.0 W50 to 5.0 W50
100
1.2 D50 to 1.4 D50
2.0 W50 to 2.75 W50
85
1.0 D50 to 1.15 D50
1.0 W50 to 1.5 W50
50
0.4 D50 to 0.6 D50
0.1 W50 to 0.2 W50
15
Table 1-3-17. Riprap Gradation Classes (English)
Riprap
Class
Rock Size1
(ft)
Rock Size2
(lbs)
Percent of Riprap
Smaller Than
Facing
1.30
0.95
0.40
200
75
5
100
50
10
Light
1.80
1.30
0.40
500
200
5
100
50
10
1/4 Ton
2.25
1.80
0.95
1,000
500
75
100
50
10
1/2 Ton
2.85
2.25
1.80
2,000
1,000
500
100
50
5
1 Ton
3.60
2.85
2.25
4,000
2,000
1,000
100
50
5
2 Ton
4.50
3.60
2.85
8,000
4,000
2,000
100
50
5
1Assuming
2Based
a specific gravity of 2.65
on AASHTO gradations
Gradation of the riprap being placed is controlled by visual inspection. To aid the inspector's judgment, two or
more samples of riprap of the specified gradation should be prepared by sorting, weighing, and remixing in
proper proportions. Each sample should weigh about 5 to 10 tons. One sample should be placed at the quarry
and one sample at the construction site. The sample at the construction site could be part of the finished riprap
blanket. These samples should be used as a frequent reference for judging the gradation of the riprap supplied.
Filter Systems. A filter system should be provided to prevent the migration of the fine soil between the voids of
the riprap. The system may be either a granular filter or an engineering filter fabric. Consultation with a
geotechnical engineer may be useful in making the proper selection.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-112
AREMA Manual for Railway Engineering
Natural Waterways
Granular Filters. In using a granular filter system, the filter ratio as stated in the following relationships
should be met.
EQ 31
The left side of the inequality in EQ 31 is intended to prevent erosion (piping) through the filter and the center
portion provides for adequate permeability for structural bedding. The right portion provides a uniformity
criterion.
If a single layer of filter will not satisfy the equation, two or more layers must be used. The filter requirement
applies between the bank material and the filter as well as the filter and the riprap. The thickness of the filter
blanket should be from 150 mm (6 in) and 380 mm (15 in) for a single layer, or from 100 mm (4 in) to 200 mm
(8 in) for individual layers of a multilayer installation.
Engineering Fabric Filters. For the proper design of a geotextile filter system, see Holtz et al. (FHWA HI-95038). The fabric should provide drainage and filtration. Therefore, both functions should be considered in the
selection of the filter material.
Edge Treatment. To prevent undermining at the toe and flanks of the riprap, special edge treatment may be
required such as:
1
• Extending the lower toe of the riprap below the anticipated contraction scour and long-term
degradation depth.
• Placing launchable stone at the toe of the installation that will slide into the scour hole as it develops.
This method requires extra material to be placed at bottom of the installation in a trench or extending
into the stream (Figure 1-3-51 and Figure 1-3-52). For additional information, see HEC-11.
• The flanks may be protected as illustrated in Figure 1-3-53. In Section A-A, the area shown as
"compacted backfill" may be completely filled with riprap.
3
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-113
Roadway and Ballast
Figure 1-3-51. Methods of Providing Toe Protection (USACE 1991)
Revetment Riprap Design Example
The following design example illustrates the general revetment riprap design procedure. From a field survey of
the site and an analysis of the stream using a water surface profile program such as HEC-RAS the following
data have been established.
Given:
Channel width = 300 ft
Bend radius = 200 ft
Average velocity in main channel (Va) = 12.6 fps
Average depth in main channel (da) = 12 ft
Available rock riprap has a specific gravity of 2.60 and is considered angular.
A 1 vertical to 2 horizontal (1V:2H) bank slope is to be used.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-114
AREMA Manual for Railway Engineering
Natural Waterways
1
3
4
Figure 1-3-52. Alternative Method of Providing Toe Protection (HEC-11)
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-115
Roadway and Ballast
Figure 1-3-53. Flank Details (HEC-11)
Solution:
Using EQ 28, EQ 29, and EQ 30, the following size is established.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-116
AREMA Manual for Railway Engineering
Natural Waterways
3
D 50
K u CV a
= --------------------------------0.5
1.5
d avg K 1
2 0.5
sin 
K 1 = 1 – -------------2
sin 
1.5
1.61  SF 
C = ------------------------------1.5
 Ss – 1 
EQ 32
From Figure 1-3-46 for angular stone, a value of 41 for the angle of repose would be a good initial estimate to
use. For a side slope of 1V:2H:
2 0.5
sin 
K 1 = 1 – --------------2
sin 
2 0.5
 0.447 
= 1 – ---------------------2
 0.656 
= 0.73
Assuming for a gradually varying flow with moderate bend curvature, the stability factor (SF) is 1.6. (See the
previous guidance for stability factor.)
1.5
1.5
1.61  SF 
1.61  1.6 
C = ------------------------------- = -------------------------------- = 1.61
1.5
1.5
 Ss – 1 
 2.60 – 1 
1
The required stone size is then found.
3
Using this stone size of 1.5 ft, recheck the angle of repose. It would be close to the original 41 that was
assumed and would be acceptable.
Taking this computed size of stone, compare it to a class of riprap that is available and use the next larger size
(perhaps the AASHTO 1/4 ton class riprap).
The layer thickness would be twice the mean size (2 D50) or the thickness equal to the D100.
The need for a filter system depends on the parent material at the site. Normally a filter system will be
required. It may be either a granular filter or a geotextile.
Rock-Fill Trenches and Windrow Revetment
Rock-fill trenches are structures used to protect banks from caving caused by erosion at the toe. A trench is
excavated along the toe of the bank and filled with rocks as shown in Figure 1-3-54. The size of trench to hold
the rock fill depends on expected depths of scour.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-117
4
Roadway and Ballast
Figure 1-3-54. Rock-fill Trench (after HDS 6)
As the streambed adjacent to the toe is eroded, the toe trench is undermined and the rock fill slides downward
to pave the bank. It is advantageous to grade the banks before placing riprap on the slope and in the toe trench.
The slope should be at such an angle that the saturated bank is stable while the stream stage is falling.
An alternative to a rock-fill trench at the toe of the bank is to excavate a trench above the water line along the
top of the bank and fill the trench with rocks. As the bank erodes, stone material in the trench is added on an
as-needed basis until equilibrium is established. This method is applicable in areas of rapidly eroding banks of
medium to large size streams.
Windrow revetment (Figure 1-3-55) consists of a supply of rock deposited along an existing bank line at a
location beyond which additional erosion is to be prevented. When bank erosion reaches and undercuts the
supply of rock, it falls onto the eroding area, thus giving protection against further undercutting. The resulting
bank line remains in a near natural state with an irregular appearance due to intermittent lateral erosion in
the windrow location. The treatment particularly lends itself to the protection of adjacent wooded areas, or
placement along stretches of presently eroding, irregular bank line.
The effect of windrow revetment on the interchange of flow between the channel and overbank areas and flood
flow distribution in the flood plain should be carefully evaluated. Windrow installations will perform as guide
banks or levees and may adversely affect flow distribution at bridges or cause local scour. Tying the windrow to
the embankment at an abutment would be contrary to the purpose of the windrow since the rock is intended to
fall into the channel as the bank erodes. This would potentially expose the abutment.
The following observations and conclusions from model investigations of windrow revetments and rock-fill
trenches may be used as design guidance. More definitive guidance is not presently available (USACE 1981).
• The application rate of stone is a function of channel depth, bank height, material size, and estimated
bed scour.
• A triangular windrow is the least desirable shape, a trapezoidal shape provides a uniform blanket of
rock on an eroding bank, and a rectangular shape provides the best coverage. A rectangular shape is
most easily placed in an excavated trench.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-118
AREMA Manual for Railway Engineering
Natural Waterways
1
3
4
Figure 1-3-55. Windrow Revetment, Definition Sketch (after USACE 1981)
• Bank height does not significantly affect the final revetment; however, high banks tend to produce a
nonuniform revetment alignment. Large segments of bank tend to break loose and rotate slightly on
high banks, whereas low banks simply "melt" or slough into the stream.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-119
Roadway and Ballast
• Stone size influences the thickness of the final revetment, and a smaller gradation of stone forms a
more dense, closely chinked protective layer. Stones must be large enough to resist being transported
by the stream, and a well-graded stone should be used to ensure that the revetment does not fail from
leaching of the underlying bank material. Large stone sizes require more material than smaller stone
sizes to produce the same relative thickness of revetment. In general, the greater the stream velocity,
the steeper the side slope of the final revetment. The final revetment slope will be about 15 percent
flatter than the initial bank slope.
• A windrow segment should be extended landward from the upstream end to reduce the possibility of
outflanking of the windrow.
Rigid Revetments
Rigid revetments are generally smoother than flexible revetments and thus improve hydraulic efficiency and
are generally highly resistant to erosion and impact damage. They are susceptible to damage from the removal
of foundation support by subsidence, undermining, hydrostatic pressures, slides, and erosion at the perimeter.
They are also among the most expensive streambank protection countermeasures.
Concrete Pavement
Concrete paving should be used only where the toe can be adequately protected from undermining and where
hydrostatic pressures behind the paving will not cause failure. This might include impermeable bank materials
and portions of banks which are continuously under water. Sections intermittently above water should be
provided with weep holes. Refer to HEC-11 for design of concrete pavement revetment.
Sacks
Burlap sacks filled with soil or sand-cement mixtures have long been used for emergency work along levees and
streambanks during floods (Figure 1-3-56). Commercially manufactured sacks (burlap, paper, plastics, etc.)
have been used to protect streambanks in areas where riprap of suitable size and quality is not available at a
reasonable cost. Sacks filled with sand-cement mixtures can provide long-term protection if the mixture has set
up properly, even though most types of sacks are easily damaged and will eventually deteriorate. Sand-cement
sack revetment construction is not economically competitive in areas where good stone is available. However,
where quality riprap must be transported over long distances, sack revetment can often be placed at a lesser
cost than riprap.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-120
AREMA Manual for Railway Engineering
Natural Waterways
Figure 1-3-56. Typical Sand-cement Bag Revetment (after Brown 1985)
If a sack revetment is to be constructed, the sacks should be filled with a mixture of 15 percent cement
(minimum) and 85 percent dry sand (by weight). The filled sacks should be placed in horizontal rows like
common house brick beginning at an elevation below any toe scour (alternatively, riprap can be placed at the
toe to prevent undermining of the bank slope). The successive rows should be stepped back approximately onehalf-bag width to a height on the bank above which no protection is needed. The slope of the completed
revetment should not be steeper than 1:1. After the sacks have been placed on the bank, they can be wetted
down for a quick set or the sand-cement mixture can be allowed to set up naturally through rainfall, seepage or
condensation. If cement leaches through the sack material, a bond will form between the sacks and prevent
free drainage. For this reason, weepholes should be included in the revetment design. The installation of
weepholes will allow drainage of groundwater from behind the revetment thus helping to prevent a pressure
buildup that could cause revetment failure. This revetment requires the same types of toe protection as other
types of rigid revetment.
1
3
References for Revetment Design
AASHTO, 1999. "Model Drainage Manual," Metric Edition, American Association of State Highway and
Transportation Officials, Washington, D.C.
Brown, S.A., 1985. "Streambank Stabilization Measures for Highway Engineers," FHWA/RD-84, 100 Federal
Highway Administration, McLean, VA.
Brown, S.A. and Clyde, E.S., 1989. "Design of Riprap Revetment," Hydraulic Engineering Circular No.11,
FHWA-IP-89-016. Prepared for the Federal Highway Administration, Washington, D.C.
Chen, Y.H. and Cotton, G.K., 1988. "Design of Roadway Channels with Flexible Linings," U.S. Department of
Transportation, Federal Highway Administration, FHWA IP87-7, NTIS PB89-122584, Hydraulic Engineering
Circular No. 15.
Holtz, D.H., Christopher, B.R., and Berg, R.R., 1995. "Geosynthetic Design and Construction Guidelines,"
National Highway Institute, Publication No. FHWA HI-95-038, Federal Highway Administration, Washington,
D.C., May.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-121
4
Roadway and Ballast
Hydrologic Engineer Center, 2001. "HEC-RAS River Analysis System," Hydraulic Reference Manual, Version
3.0, U.S. Army Corps of Engineers, Davis, CA.
Lagasse, P.F., Zevenbergen, L.W., Schall, J.D., and Clopper, P.E., 2001. "Bridge Scour and Stream Instability
Countermeasures – Experience, Selection, and Design Guidelines," Second Edition, Report FHWA NHI 01-003,
Federal Highway Administration, Hydraulic Engineering Circular No. 23, U.S. Department of Transportation,
Washington, D.C.
Richardson, E.V., Simons, D.B., and Lagasse, P.F., 2001. "River Engineering for Highway Encroachments Highways in the River Environment," Report No. FHWA NHI 01-004, Hydraulic Design Series No. 6, Federal
Highway Administration, Washington, D.C.
U.S. Army Corps of Engineers, 1981. "The Streambank Erosion Control Evaluation and Demonstration Act of
1974," Final Report to Congress, Executive Summary and Conclusions.
U.S. Army Corps of Engineers, 1991. "Hydraulic Design of Flood Control Channels," EM 1110-2-1601,
Department of the Army, Washington, D.C.
3.6.4.6 Wire-Enclosed Rock
Wire-enclosed rock (gabion) revetments consist of rectangular wire mesh baskets filled with rock. The most
common types of wire-enclosed revetments are mattresses and stacked blocks. The wire cages which make up
the mattresses and gabions are available from commercial manufacturers. If desired, the wire baskets can also
be fabricated from available wire fencing materials. This section provides design guidance for stacked block
gabion revetment. Reference to HEC-11 is suggested for design guidance on gabion mattresses.
As a revetment, wire-enclosed rock has limited flexibility. They will flex with bank surface subsidence;
however, if excessive subsidence occurs, the baskets will span the void until the stresses in rock-filled baskets
exceed the tensile strength of wire strands. At this point, the baskets will fail (Escarameia 1998).
The conditions under which wire-enclosed rock is applicable are similar to those of other revetments. However,
their economic use is limited to locations where the only rock available economically is too small for use as rock
riprap slope protection. The primary advantages of wire-enclosed rock revetments include:
Their ability to span minor pockets of bank subsidence without failure
The ability to use smaller, lower quality, and less dense, rock in the baskets
Disadvantages of the use of wire-enclosed rock revetments include:
Susceptibility of the wire baskets to corrosion and abrasion damage
High labor costs associated with fabricating and filling the wire baskets
More difficult and expensive repair than standard rock protection
Less flexibility than standard rock protection
The most common failure mechanism of wire basket revetments has been observed to be failure of the wire
baskets. Failure from abrasion and corrosion of the wire strands has even been found to be a common problem
when the wire is coated with plastic. The plastic coating is often stripped away by abrasion from sand, gravel,
cobbles, or other sediments carried in natural stream flows (particularly at and near flood stages). Once the
wire has been broken, the rock in the baskets is usually washed away. To avoid the problem of abrasion and
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-122
AREMA Manual for Railway Engineering
Natural Waterways
corrosion of the wire baskets, it is recommended that wire-enclosed rock revetments not be used on lower
portions of the channel bank in environments subject to significant abrasion or corrosion.
An additional failure mechanism has been observed when the wire basket units are used in high-velocity, steepslope environments. Under these conditions, the rock within individual baskets shifts downstream, deforming
the baskets as the material moves. The movement of material within individual baskets will sometimes result
in exposure of filter or base material. Subsequent erosion of the exposed base material can cause failure of the
revetment system.
Stacked Block Gabions
Stacked block gabion revetments consist of rectangular wire baskets which are filled with stone and stacked in
a stepped-back fashion to form the revetment surface (Figure 1-3-57). They are also commonly used at the toe
of embankment slopes as toe walls which help to support other upper bank revetments and prevent
undermining.
As illustrated in Figure 1-3-57, the rectangular basket or gabion units used for stacked configurations are more
equidimensional than those typically used for mattress designs. That is, they typically have a square cross
section. Commercially available gabions used in stacked configurations include those listed in Table 1-3-18
having 3-foot widths and thickness. Other commercially available sizes can also be used in the stacked block
configurations.
Conceptually, the gabion units for stacked block configurations could also be fabricated from available fencing
materials. However, the labor intensive nature of such an installation makes it impractical in most cases.
Therefore, only commercially available units are considered in the following design guidelines.
1
Design Guidelines for Stacked Block Gabions
Components of stacked gabion revetment design include layout of a general scheme or concept, bank and
foundation preparation, unit size and configuration, stone size and quality, edge treatment, backfill and filter
considerations, and basket or rock enclosure fabrication. Design guidelines for stone size and quality, and bank
preparation are generally available from manufacturer's literature (see also HEC-11).
General: Stacked gabion revetments are typically used when the slope to be protected is greater than 1:1 or
when the purpose of the revetment is for flow training. They can also be used as retaining structures when
space limitations prohibit bank grading to a slope suitable for other revetments. Typical design schemes
include flow training walls, Figure 1-3-57(a), and low or high retaining walls (Figure 1-3-57(b) and (c),
respectively.
Stacked gabion revetments must be based on a firm foundation. The foundation or base elevation of the
structure should be well below any anticipated scour depth. Additionally, in alluvial streams where channel bed
fluctuations are common, an apron should be used as illustrated in Figure 1-3-57(a) and (b). Aprons are also
recommended for situations where the estimated scour depth is uncertain.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-123
3
4
Roadway and Ballast
Figure 1-3-57. Typical Stacked Block Gabion Revetment Details
(a) training well with counterforts, (b) stepped back low retaining wall with apron; (c) high retaining
wall, stepped-back configuration; (d) high retaining wall, batter type
Table 1-3-18. Standard Gabion Sizes
Thickness
(ft)
Width
(ft)
Length
(ft)
Wire-Mesh
Opening Size
(in x in)
0.75
6
9
2.5 x 3.25
0.75
6
12
2.5 x 3.25
1.
3
6
3.25 x 4.5
1.
3
9
3.25 x 4.5
1.
3
12
3.25 x 4.5
1.5
3
6
3.25 x 4.5
1.5
3
9
3.25 x 4.5
1.5
3
12
3.25 x 4.5
3
3
6
3.25 x 4.5
3
3
9
3.25 x 4.5
3
3
12
3.25 x 4.5
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-124
AREMA Manual for Railway Engineering
Natural Waterways
Size and Configuration: Common commercial sizes for stacked gabions are listed in Table 1-3-18. The most
common sizes used are those having widths and depths of 3 ft. Sizes less than 1 ft thick are not practical for
stacked gabion installations.
Typical design configurations include flow training walls and structural retaining walls. The primary function
of flow training walls (Figure 1-3-57(a)) is to establish normal channel boundaries in rivers where erosion has
created a wide channel, or to realign the river when it is encroaching on an existing or proposed structure. A
stepped-back wall is constructed at the desired bank location and counterforts are installed to tie the walls to
the channel bank at regular intervals as illustrated. The counterforts are installed to form a structural tie
between the training wall and the natural stream bank, and to prevent overflow from scouring a channel
behind the wall. Counterforts should be spaced to eliminate the development of eddy or other flow currents
between the training wall and the bank which could cause further erosion of the bank. The dead water zones
created by the counterforts so spaced will encourage sediment deposition behind the wall which will enhance
the stabilizing characteristics of the wall.
Retaining walls can be designed in either a stepped-back configuration as illustrated in Figure 1-3-57(b) and
(c), or a batter configuration as illustrated in Figure 1-3-57(d). Structural details and configurations can vary
from site to site.
Gabion walls are gravity structures and their design follows standard engineering practice for retaining
structures. Design procedures are available in standard soil mechanics texts as well as in gabion
manufacturer's literature.
Edge Treatment: The flanks and toe of stacked block gabion revetments require special attention. The
upstream and downstream flanks of these revetments should include counterforts, see Figure 1-3-57(a). The
counterforts should be placed 12 to 18 ft from the upstream and downstream limits of the structure, and should
extend a minimum of 12 ft into the bank.
1
The toe of the revetment should be protected by placing the base of the gabion wall at a depth below anticipated
scour depths. In areas where it is difficult to predict the depth of expected scour, or where channel bed
fluctuations are common, it is recommended that a mattress apron be used. The minimum apron length should
be equal to 1.5 times the anticipated scour depth below the apron. This length can be increased in proportion to
the level of uncertainty in predicting the local toe scour depth.
3
Backfill/Filter Requirements: Standard retaining wall design requires the use of selected backfill behind the
retaining structure to provide for drainage of the soil mass behind the wall. The permeable nature of gabion
structures permits natural drainage of the supported embankment. However, since material leaching through
the gabion wall can become trapped and cause plugging, it is recommended that a granular backfill material be
used, see Figure 1-3-57(d). The backfill should consist of a 2- to 12-inch (5.1- to 30.5-cm) layer of graded
crushed stone backed by a layer of fine granular backfill.
4
Basket Fabrication: Commercially fabricated basket units are formed from galvanized steel wire mesh of triple
twist hexagonal weave. The netting wire and binding wire specifications are the same discussed for mattress
units. Specifications for galvanizing and PVC coatings are also the same for block designs as for mattresses.
Figure 1-3-58 illustrates typical details of basket fabrication.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-125
Roadway and Ballast
Figure 1-3-58. Gabion Basket Fabrication
Construction
Construction details for gabion installations typically vary with the design and purpose for which the protection
is being provided. Several typical design schematics are presented in Figure 1-3-57 and Figure 1-3-58.
As with mattress designs, fabrication and filling of individual basket units can be done at the site, or at an offsite location. The most common practice is to fabricate and fill individual gabions at the design site. The
following steps outline the typical sequence used for installing a stacked gabion revetment or wall:
Step 1. Prepare the revetment foundation. This includes excavation for the foundation and revetment wall.
Step 2. Place the filter and gabion mattress (for designs which incorporate this component) on the prepared
grade, then sequentially stack the gabion baskets to form the revetment system.
Step 3. Each basket is unfolded and assembled by lacing the edges together and the diaphragms to the sides.
Step 4. Fill the gabions to a depth of 1-foot with stone form 4 to 12 inches in diameter. Place one connecting
wire in each direction and loop it around two meshes of the gabion wall. Repeat this operation until the gabion
is filled.
Step 5. Wire adjoining gabions together by their vertical edges; stack empty gabions on the filled gabions and
wire them at front and back.
Step 6. After the gabion is filled, fold the top shut and wire it to the ends, sides and diaphragms.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-126
AREMA Manual for Railway Engineering
Natural Waterways
Step 7. Crushed stone and granular backfill should be placed in intervals to help support the wall structure. It
is recommended that backfill be placed at 3-course intervals.
References for Wire Enclosed Rock
Brown, S.A. and Clyde, E.S., 1989. "Design of Riprap Revetment," Hydraulic Engineering Circular No.11,
FHWA-IP-89-016. Prepared for the Federal Highway Administration, Washington, D.C.
Escarameia, M., 1998. "River and Channel Revetments – A Design Manual," Thomas Telford Limited, London.
3.6.4.7 Check Dams/Drop Structures
Background
Check dams or channel drop structures are used downstream of bridge crossings to arrest head cutting and
maintain a stable streambed elevation in the vicinity of the bridge. Check dams are usually built of rock riprap,
concrete, sheet piles, gabions, or treated timber piles. The material used to construct the structure depends on
the availability of materials, the height of drop required, and the width of the channel. Rock riprap and timber
pile construction have been most successful on channels having small drops and widths less than 100 ft. Sheet
piles, gabions, and concrete structures are generally used for larger drops on channels with widths ranging up
to 300 ft. Check dam location with respect to the bridge depends on the hydraulics of the bridge reach and the
amount of headcutting or degradation anticipated.
Check dams can initiate erosion of banks and the channel bed downstream of the structure as a result of energy
dissipation and turbulence at the drop. This local scour can undermine the check dam and cause failure. The
use of energy dissipators downstream of check dams can reduce the energy available to erode the channel bed
and banks. In some cases it may be better to construct several consecutive drops of shorter height
to minimize erosion. Concrete lined basins as discussed later may also be used.
1
Lateral erosion of channel banks just downstream of drop structures is another adverse result of check dams
and is caused by turbulence produced by energy dissipation at the drop, bank slumping from local channel bed
erosion, or eddy action at the banks. Bank erosion downstream of check dams can lead to erosion of bridge
approach embankments and abutment foundations if lateral bank erosion causes the formation of flow
channels around the ends of check dams. The usual solution to these problems is to place riprap revetment on
the streambank adjacent to the check dam (see Article 3.6.4.5).
3
Erosion of the streambed can also be reduced by placing rock riprap in a preformed scour hole downstream of
the drop structure. A row of sheet piling with top set at or below streambed elevation can keep the riprap from
moving downstream. Because of the problems associated with check dams, the design of these
countermeasures requires designing the check dams to resist scour by providing for dissipation of excess energy
and protection of areas of the bed and the bank which are susceptible to erosive forces.
4
Bed Scour For Vertical Drop Structures
Estimating Bed Scour. The most conservative estimate of scour downstream of channel drop structures is for
vertical drops with unsubmerged flow conditions. For the purposes of design the maximum expected scour can
be assumed to be equal to the scour for a vertical, unsubmerged drop, regardless of whether the drop is actually
sloped or is submerged.
A sketch of a typical vertical drop structure with a free overfall is shown in Figure 1-3-59. An equation
developed by the Bureau of Reclamation (USBR) is recommended to estimate the depth of scour downstream of
a vertical drop:
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-127
Roadway and Ballast
Figure 1-3-59. Schematic of a Vertical Drop Caused by a Check Dam
ds = K u Ht
0.225 0.54
q
EQ 33
– dm
where:
ds = local scour depth for a free overall, measured from the streambed downstream of the
drop, m (ft)
q = discharge per unit width, m3/s/m (cfs/ft)
Ht = total drop in head, measured from the upstream to the downstream energy grade line,
m (ft)
dm, Yd = tailwater depth, m (ft)
Ku = 1.90 (SI)
Ku = 1.32 (English)
It should be noted that Ht is the difference in the total head from upstream to downstream. This can be
computed using the energy equation for steady uniform flow:
EQ 34
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-128
AREMA Manual for Railway Engineering
Natural Waterways
where:
Y = depth, m (ft)
V = velocity, m/s (ft/s)
Z = bed elevation referenced to a common datum, m (ft)
g = acceleration due to gravity 9.81 m/s2 (32.2 ft/s2)
The subscripts u and d refer to upstream and downstream of the channel drop, respectively.
The depth of scour as estimated by the above equation is independent of the grain size of the bed material. This
concept acknowledges that the bed will scour regardless of the type of material composing the bed, but the rate
of scour depends on the composition of the bed. In some cases, with large or resistant material, it may take
years or decades to develop the maximum scour hole. In these cases, the design life of the bridge may need to
be considered when designing the check dam.
The check dam must be designed structurally to withstand the forces of water and soil assuming
that the scour hole is as deep as estimated using the equation above. Therefore, the designer should
consult geotechnical and structural engineers so that the drop structure will be stable under the full scour
condition. In some cases, a series of drops may be employed to minimize drop height and construction costs of
foundations. Riprap or energy dissipation could be provided to limit depth of scour (see, for example, Peterka
and HEC-14).
1
Check Dam Design Example
Given:
Channel degradation is threatening bridge foundations. Increasing the bed elevation 4.6 ft will stabilize the
channel at the original bed level. A drop structure will raise the channel bed and reduce upstream channel
slopes, resulting in greater flow depths and reduced velocity upstream of the structure. For this example, as
illustrated by Figure 1-3-60, the following hydraulic parameters are used:
Design Discharge
Q
= 5,900 ft3/s
Channel Width
B
= 105 ft
Upstream Water Depth
Yu
= 10.6 ft
Tail Water Depth
dm, Yd
= 9.5 ft
Unit Discharge
q
= 56.2 ft3/s/ft
Upstream Mean Velocity
Vu
= 5.3 ft/s
Downstream Mean Velocity
Vd
= 5.9 ft/s
Drop Height
h
= 4.6 ft
4
Solution:
Ht is calculated from the energy equation. Using the downstream bed as the elevation datum gives:
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
3
1-3-129
Roadway and Ballast
EQ 35
Using EQ 33, the estimated depth of scour below the downstream bed level is:
ds = K u Ht
0.225 0.54
q
– dm
EQ 36
Figure 1-3-60. Design Example of Scour Downstream of a Drop Structure
d s = 1.32  5.6 
0.225
 56.2 
0.54
– 9.5
In this case, the unsupported height of the structure is (h + ds) or 12.2 ft. If, for structural reasons, this height
is unacceptable, then either install riprap to limit scour depth or a series of check dams could be constructed. It
should be noted that if a series of drops are required, adequate distance between each drop must be maintained.
Lateral Scour Downstream of Check Dams
Lateral scour of the banks of a stream downstream of check dams can cause the streamflow to divert around
the check dam. If this occurs, a head cut may move upstream and endanger the railroad crossing. To prevent
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-130
AREMA Manual for Railway Engineering
Natural Waterways
this the banks of the stream must be adequately protected using riprap or other revetments. Riprap should be
sized and placed in a similar fashion as for spurs and guide banks. The designer is referred to HEC-11 for
proper sizing, and placement of riprap on the banks. Revetments are discussed in Article 3.6.4.5.
References for Check Dam Design
Brown, S.A. and Clyde, E.S., 1989. "Design of Riprap Revetment," Hydraulic Engineering Circular No.11,
FHWA-IP-89-016. Prepared for the Federal Highway Administration, Washington, D.C.
Federal Highway Administration, 1983. "Hydraulic Design of Energy Dissipators for Culverts and Channels,"
Hydraulic Engineering Circular Number 14, U.S. Department of Transportation, Washington, D.C.
Lagasse, P.F., Zevenbergen, L.W., Schall, J.D., and Clopper, P.E., 2001. "Bridge Scour and Stream Instability
Countermeasures – Experience, Selection, and Design Guidelines," Second Edition, Report FHWA NHI 01-003,
Federal Highway Administration, Hydraulic Engineering Circular No. 23, U.S. Department of Transportation,
Washington, D.C.
Pemberton, E.L. and Lara, J.M., 1984. "Computing Degradation and Local Scour," Technical Guidelines for
Bureau of Reclamation, Engineering Research Center, Denver, CO, January.
Peterka, A.J., 1964. "Hydraulic Design of Stilling Basins and Energy Dissipators," Engineering Monograph No.
25, Bureau of Reclamation, Division of Research, Denver, CO.
1
3.6.4.8 Channel Cutoffs
Design Considerations
For some railroad encroachments, a change in the river channel alignment is advantageous. When a river
crossing site is so constrained by non-hydraulic factors that consideration of alternative sites is not possible, the
engineer must attempt to improve the local situation to meet specific needs. Also, the engineer may be forced
to make channel improvements in order to maintain and protect existing embankment in or adjacent to the
river.
Suppose a meandering river is to be crossed with the alignment, as shown in Figure 1-3-61(a). Assume that the
alignment is fixed by constraints in the acquisition of the right-of-way. To create better flow alignment with
the bridge, consideration is given to channel improvement as shown in Figure 1-3-61(b). Similarly,
consideration for improvement to the channel would also be advisable for a hypothetical lateral encroachment
of a roadway as depicted in Figure 1-3-61(c). In either case, the designer's questions are how to realign the
channel, and what criteria to use to establish stable channel dimensions.
Prior to realigning a river channel the stability of the existing channel must be examined. A stream
classification, recent and past aerial photographs and field surveys are generally necessary (see Article 3.4.5).
The realigned channel may be made straight without curves, or may include one or more curves. If curves are
included, the radii of curvature, the number of bends, the limits of rechannelization (hence the length or slope
of the channel) and the cross-sectional area are decisions which have to be made by the designer. Different
rivers have different characteristics and historical background with regard to channel migration, discharge,
stage, geometry and sediment transport. As indicated in the previous chapters, it is important for the designer
to understand and appreciate river hydraulics and geomorphology when making decisions concerning channel
relocation. It is difficult to state generalized criteria for channel relocation applicable to every river.
Knowledge about river systems has not yet advanced to such a state as to make this possible. Nevertheless, it is
possible to provide some principles and guidelines for the design engineer.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-131
3
4
Roadway and Ballast
Figure 1-3-61. Encroachment on a Meandering River
As the general rule, the radii of bends (Rc) as shown in Figure 1-3-61(a) should be made about equal to the
mean radii of bends in extended reaches of the river. When the angle  defined in Figure 1-3-61(a) exceeds
about 40 degrees, this provides a sufficient crossing length for the thalweg to shift from one side of the channel
to the other. Generally, it is necessary to stabilize the outside banks of the curves in order to hold the new
alignment, and depending upon crossing length some amount of maintenance may be necessary to remove
sandbars after large floods so that the channel does not develop new meander patterns in the crossings during
normal flows.
Any designed increase in width should be limited to about 10 to 15 percent. Wider channels would be
ineffective. Deposition would occur along one bank and the effort of extra excavation would be wasted.
Furthermore, bar formation would be encouraged, with resultant tendencies for changes in the meander
pattern leading to greater maintenance costs for bank stabilization and removal of the bars to hold the desired
river alignment. The depth of flow in the channel is dependent on discharge, effective channel width, sediment
transport rate (because it affects bed form and channel roughness) and channel slope.
This discussion pertains to alluvial channels with silt and sand sized bed materials. For streams with gravel and
cobble beds, the usual concern is to provide adequate channel cross-sectional dimensions to convey flood flows.
If the realigned channels are made too steep, there is an increase in transport rate of the bed material. The
deposition of material in the reaches downstream of the crossing tends to form gravel bars and encourages
changes in the planform of the channel. Short-term changes in channel slope can be expected until equilibrium
is reestablished over extended reaches both upstream and downstream of the rechannelized reach. Bank
stabilization may be necessary to prevent lateral migration, and periodic removal of gravel bars may also be
necessary.
Assessment of Stability for Relocated Streams
Brice (1980) reported case histories for channel stability of relocated streams in different regions of the United
States. Based on his study, the recommendations and conclusions presented here apply to specific aspects of
the planning and construction of channel relocation. They are intended for assessment of the risk of instability
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-132
AREMA Manual for Railway Engineering
Natural Waterways
and for reduction of the degree of instability connected with relocation. Serious instability resulting from
relocation can be observed either when the prior natural channel is unstable or when floods of high recurrence
interval occur during or soon after construction. Although there is an element of uncertainty in channel
stability, the experience represented by Brice's study sites provides useful guidelines for improvement in the
performance of relocated channels.
Channel Stability Prior To Relocation. Assessment of the stability of a channel prior to relocation is needed
to assess erosion-control measures and risk of instability. An unstable channel is likely to respond unfavorably
to relocation. Bank stability is assessed by field study and the stereoscopic examination of aerial photographs.
The most useful indicators of bank instability are cut or slumped banks, fallen trees along the bankline, and
wide, unvegetated, exposed point bars. Bank recession rates are measured by comparison of time-sequential
aerial photographs. Vertical instability is equally important but more difficult to determine. It is indicated by
changes in channel elevation at bridges and gaging stations. Serious degradation is usually accompanied by
generally cut or slumped banks along a channel.
Erosion Resistance Of Channel Boundary Materials. The stability of a channel, whether natural or
relocated, is partly determined by the erosion resistance of materials that form the wetted perimeter of the
channel. Resistant bedrock outcrops, which extend out into the channel bottom, or that lie at shallow depths,
will provide protection against degradation. Not all bedrock is resistant. Erosion of shale, or of other
sedimentary rock types interbedded with shale, has been observed. Degradation was slight or undetected at
most sites where bed sediment was of cobble and boulder size. However, serious degradation may result from
relocation. Degradation may result from the relocation of any alluvial channel, whatever the size of bed
material, but the incidence of serious degradation of relocated channels is slight.
The cohesion and erosion resistance of banks tend to increase with clay content. Banks of weakly coherent
sand or silt are clearly subject to rapid erosion, unless protected with vegetation. No consistent relation was
found between channel stability and the cohesion of bank materials, probably because of the effects of
vegetation.
Length Of Relocation. The length of relocation contributes significantly to channel instability at sites where its
value exceeded 250 channel widths. When the value is below 100 channel widths, the effects of length of
relocation are dominated by other factors. The probability of local bank erosion at some point along a channel
increases with the length of the channel. The importance of vegetation, both in appearance and in erosion
control, would seem to justify a serious and possibly sustained effort to establish it as soon as possible on the
graded banks.
Bank Revetment. Revetment makes a critical contribution to stability at many sites where it is placed at bends
and along embankments. Rock riprap is by far the most commonly used and effective revetment (see
Article 3.6.4.5).
Check Dams (drop structures). In general, check dams are effective in preventing channel degradation (see
Article 3.6.4.7). The potential for erosion at a check dam depends on its design and construction, its height and
the use of revetment on adjoining banks. A series of low check dams, less than about 2 ft in height, is probably
preferable to a single higher structure, because the potential for erosion and failure is reduced. One critical
problem arising with check dams relates to improper design for large flows. Higher flows have worked around
the ends of many installations to produce failure.
Maintenance. The following problems that can be controlled by maintenance were observed along relocated
channels: (1) growth of annual vegetation in channel; (2) reduction of channel conveyance by overhanging
trees; (3) local bank cutting; and (4) bank slumping. The expense of routine maintenance or inspection of
relocated channels beyond the right-of-way is probably prohibitive. However, most of the serious problems
could be detected by periodic inspection, perhaps by aerial photography, during the first 5 or 10 years after
construction.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-133
1
3
4
Roadway and Ballast
Relationship Between Sinuosity And Stability. This relationship is summarized as follows: (1) Meandering
does not necessarily indicate instability; an unstable stream will not remain highly sinuous for very long,
because the sinuosity will be reduced by frequent meander cutoffs; (2) Where instability is present along a
reach, it occurs mainly at bends; straight segments may remain stable for decades; and (3) The highest
instability is for reaches whose sinuosity is in the range of 1.2 to 2 and whose type is either wide bend or
braided point bar.
River Response to Cutoffs
The following three conceptual examples provide a summary of river response to cutoffs. In Table 1-3-19, each
individual case is identified in the first column to show the physical situation that exists prior to the cutoff. In
the following three columns some of the major effects (local, upstream, and downstream) resulting from the
cutoff at a particular crossing are given.
Case (1) illustrates a situation where artificial cutoffs have straightened the channel downstream of a
particular crossing. Straightening the channel downstream of the crossing significantly increases the channel
slope. This causes higher velocities, increased bed material transport, degradation and possible head cutting in
the vicinity of the structure. This can result in unstable river banks and a braided streamform. The
straightening of the main channel can drop the base level, adversely affecting tributary streams flowing into
the straightened reach of the main channel.
Case (2) illustrates a situation where the main channel is realigned in the vicinity of the bridge crossing. A
cutoff is made to straighten the main channel through the selected bridge site. As discussed in Case (1),
increased local gradient, local velocities, local bed material transport, and possible changes in the
characteristics of the channel are expected due to the new conditions. As a result the channel may braid. A
short cut off section (1 or 2 bends) can be designed to transport the same sediment loads that the river is
capable of carrying upstream and downstream of the straightened reach; however, it may be difficult to achieve
stability when multiple bends in a long reach are cut off.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-134
AREMA Manual for Railway Engineering
Natural Waterways
Table 1-3-19. River Response to Cutoffs (HDS 6)
Bridge Location
Local Effects
1 - Steeper slope
Upstream Effects
Downstream Effects
See local effects
1 - Deposition downstream of straightened
channel
2 - Higher velocity
2 - Increase in flood
stage
3 - Increased transport
4 - Degradation and
possible headcutting
3 - Loss of channel
capacity
5 - Banks unstable
4 - Degradation in
tributary
6 - River may braid
(1) Cutoffs downstream of crossing
7- Danger to bridge
foundation from
degradation and local
scour
1 - None if straight
section is designed to
transport the sediment
load of the river and if it is
designed to be stable
when subjected to
anticipated flow.
Otherwise same as in
Case (1) above
1 - Similar to local
effects
1 - Similar to local
effects
1
(2) River channel relocation at crossing
site
3
1 - Energy gradient
also increased in
the reach upstream
and may cause
2 - Highway fill is subject change of river form
to scour as channel tends from meandering to
braided
to shift to old alignment
1 - Increased energy
gradient and potential
bank and bed scour
3 - Reach is subject to
bed degradation as
headcut develops at the
downstream end and
travels upstream
4 - Lateral drainage into
the river is interrupted and
may cause flooding and
erosion
(3) Longitudinal encroachment
2 - Rate of sediment
transport is increased.
As the headcut travels
upstream severe bank
and bed erosion is
possible
1 - Channel will
aggrade as the
sediment load coming
from bed and bank
erosion is received
2 - Channel may
deteriorate from
meandering to braided
3 - If tributaries in the
zone of influence exist
they will respond to
lowering of base level
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-135
4
Roadway and Ballast
It is possible to build modified reaches of main channels that do not introduce major adverse
responses due to local steepening of the main channel. In order to design a straightened channel so
that it behaves essentially as the natural channel in terms of velocities and magnitude of bed material
transport, it is usually necessary to build a wider, shallower section.
Case (3) illustrates an example of longitudinal encroachment. Here, a few bends of a meandering stream have
been realigned to accommodate a railroad (see Case 2). There are two problems involved in channel
realignment. First, the length of realigned channel is generally shorter than the original channel which results
in a steeper energy gradient in the reach (Case 1). Second, the new channel bank material in the realigned
reaches may have a smaller resistance to erosion. As a result of these two problems, the channel may suffer
instability by the formation of a headcut from the downstream end and increased bank erosion. The realigned
channel may also exhibit a tendency to regain the lost sinuosity and may approach and scour the railroad
embankment. To counter these local effects one could design the realignment to maintain the original channel
characteristics (length, sinuosity). Another way would be to control the slope by a series of low check dams. In
any case, bank protection by riprap, jacks or spurs will be needed.
References for Channel Cutoffs
Brice, J.C., 1980. "Stability of Relocated Stream Channels," FHWA-RD-80-158, Federal Highway
Administration, Washington, D.C.
Richardson, E.V., Simons, D.B., and Lagasse, P.F., 2001. "River Engineering for Highway Encroachments –
Highways in the River Environment," Report FHWA NHI 01-004, Federal Highway Administration, Hydraulic
Design Series No. 6, Washington, D.C.
3.6.4.9 Other Countermeasures
Introduction
Article 3.6.4.1 through Article 3.6.4.8 contain specific design procedures for a variety of stream instability and
bridge scour countermeasures that have been applied successfully on a state or regional basis. Other
countermeasures such as retarder structures, longitudinal dikes, bulkheads, and even channel relocations may
be used to mitigate scour at bridges or stream bank erosion. Some of these measures are discussed and general
guidance is summarized in this section.
Hardpoints
Hardpoints consist of stone fills spaced along an eroding bank line, protruding only short distances into the
channel. A root section extends landward to preclude flanking. The crown elevation of hardpoints used by the
USACE at demonstration sites on the Missouri River was generally at the normal water surface elevation at the
toe, sloping up at a rate of about 1 ft in 10 ft toward the bank. Hardpoints are most effective along straight or
relatively flat convex banks where the streamlines are parallel to the bank lines and velocities are not greater
than 10 ft/s within 50 ft of the bank line. Hardpoints may be appropriate for use in long, straight reaches
where bank erosion occurs mainly from a wandering thalweg at lower flow rates. They would not be effective
in halting or reversing bank erosion in a meander bend unless they were closely spaced, in which case spurs,
retarder structures, or bank revetment would probably cost less. Figure 1-3-62 is a perspective of a hardpoint
installation. Hardpoints have been used effectively as the first "spur" in a spur field (see Article 3.6.4.4).
Retarder Structures
Retarder structures are permeable or impermeable devices generally placed parallel to streambanks to reduce
velocities and cause deposition near the bank. They are best suited for protecting low banks or the lower
portions of streambanks. Retarder structures can be used to protect an existing bank line or to establish a
different flow path or alignment. Retards do not require grading of the streambank, and they create an
environment which is favorable to the establishment of vegetation.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-136
AREMA Manual for Railway Engineering
Natural Waterways
Figure 1-3-62. Perspective View of Hardpoint Installation With Section Detail (after Brown)
Jacks. Jacks most commonly consist of three linear members fixed together at their midpoints so that each
member is perpendicular to the other two. Wires are strung on the members to resist distortion and to collect
debris. Cables are used to tie individual jacks together and for anchoring key units to deadmen (Figure 1-3-63).
Jacks are effective in protecting banks from erosion only if light debris collects on the structures thereby
enhancing their performance in retarding flow. However, heavy debris and ice can damage the structures
severely. They are most effective on mild bends and in wide, shallow streams which carry a large sediment load.
1
Where jacks are used to stabilize meandering streams, both lateral and longitudinal rows are often installed to
form an area retarder structure rather than a linear structure. Lateral rows of jacks are usually oriented in a
downstream direction from 45 to 70. Spacing of the lateral rows of jacks may be 50 to 200 ft depending on the
debris and sediment load carried by the stream. A typical jack unit is shown in Figure 3.60 and a typical area
installation is shown in Figure 1-3-64. Photographs of jacks and other arrangements that provide similar
modus operandi can be found in a paper by Byers.
3
Outflanking of jack installations is a common problem. Adequate transitions should be provided between the
upstream bank and the structure, and the jack field should be extended to the overbank area to retard flow
velocities and provide additional anchorage. Jacks are not recommended for use in corrosive environments or
at locations where they would constitute a hazard to recreational use of the stream.
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-137
Roadway and Ballast
Figure 1-3-63. Typical Jack Unit (after Brown)
Figure 1-3-64. Retarder Field Schematic (after HDS 6)
Fence Retarder Structures. Fence retarder structures provide protection to the lower portions of banks of
relatively small streams. Posts may be of wood, steel, or concrete and fencing may be composed of wood planks
or wire.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-138
AREMA Manual for Railway Engineering
Natural Waterways
Scour and the development of flow channels behind linear structures are common causes of failure of
longitudinal fences. Scour at the supporting members of the structure can be reduced by placing rock along the
fence or the effects of scour can be overcome by driving supporting members to depths below expected scour.
Tiebacks can be used to retard velocities between the linear structure and the streambank, thus reducing the
ability of the stream to develop flow channels behind the structure.
Timber Pile. Timber pile retarder structures may be of a single, double, or triple row of piles with the outside
of the upstream row faced with wire mesh or other fencing material. They have been found to be effective at
sharp bends in the channel and where flows are directly attacking a bank. They are effective in streams which
carry heavy debris and ice loads and where barges or other shipping vessels could damage other
countermeasures or a bridge. As with other retarder structures, protection against scour failure is essential.
Figure 1-3-65 illustrates a design.
Wood Fence. Wood fence retarder structures have been found to provide a more positive action in maintaining
an existing flow alignment and to be more effective in preventing lateral erosion at sharp bends than other
retarder structures. Figure 1-3-66 is an end view of a typical wood fence design with rock provided to protect
against scour.
Wire Fence. Wire fence retarder structures may be of linear or area configuration, and linear configurations
may be of single or multiple fence rows. Double-row fence retards are sometimes filled with brush to increase
the flow retardance. Figure 1-3-67 and Figure 1-3-68 illustrate two types of wire fence retarder structures.
Longitudinal Dikes
Longitudinal dikes are essentially impermeable linear structures constructed parallel with the streambank or
along the desired flow path. They protect the streambank in a bend by moving the flow current away from the
bank. Longitudinal dikes may be classified as earth or rock embankment dikes, crib dikes, or rock toe-dikes.
1
3
4
Figure 1-3-65. Timber Pile Bent Retarder Structure (after Brown)
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-139
Roadway and Ballast
Figure 1-3-66. Typical Wood Fence Retarder Structure (after Brown)
Figure 1-3-67. Light Double Row Wire Fence Retarder Structure (after Brown)
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-140
AREMA Manual for Railway Engineering
Natural Waterways
1
3
4
Figure 1-3-68. Heavy Timber-pile and Wire Fence Retarder Structure (after Brown)
Earth or Rock Embankments. As the name implies, these dikes are constructed of earth with rock revetment
or of rock. They are usually as high or higher than the original bank. Because of their size and cost, they are
useful only for large-scale channel realignment projects.
Rock Toe-Dikes. Rock toe-dikes are low structures of rock riprap placed along the toe of a channel bank. They
are useful where erosion of the toe of the channel bank is the primary cause of the loss of bank material. The
USACE has found that longitudinal stone dikes provide the most successful bank stabilization measure studied
for channels which are actively degrading and for those having very dynamic beds. Where protection of higher
portions of the channel bank is necessary, rock toe-dikes have been used in combination with other measures
such as vegetative cover and retarder structures.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-141
Roadway and Ballast
Figure 1-3-69 shows the typical placement and sections of rock toe-dikes. The volume of material required is
1.5 to 2 times the volume of material that would be required to armor the sides of the anticipated scour to a
thickness of 1.5 times the diameter of the largest stone specified. Rock sizes should be similar to those specified
for riprap revetments (see Article 3.6.4.5). Tiebacks are often used with rock toe-dikes to prevent flanking, as
illustrated in Figure 1-3-70. Tiebacks should be used if the toe-dike is not constructed at the toe of the channel
bank.
Rock toe-dikes are useful on channels where it is necessary to maintain as wide a conveyance channel as
possible. Where this is not important, spurs could be more economical since scour is a problem only at the end
projected into the channel. However, spurs may not be a viable alternative in actively degrading streams (see
Article 3.6.4.4).
Crib Dikes. Longitudinal crib dikes consist of a linear crib structure filled with rock, straw, brush, automobile
tires or other materials. They are usually used to protect low banks or the lower portions of high banks. At
sharp bends, high banks would need additional protection against erosion and outflanking of the crib dike.
Tiebacks can be used to counter outflanking.
Crib dikes are susceptible to undermining, causing loss of material inside the crib, thereby reducing the
effectiveness of the dike in retarding flow. Figure 1-3-71 illustrates a crib dike with tiebacks and a rock toe on
the stream side to prevent undermining.
Bulkheads. Bulkheads are used for purposes of supporting the channel bank and protecting it from erosion.
They are generally used as protection for the lower bank and toe, often in combination with other
countermeasures that provide protection for higher portions of the bank. Bulkheads are most frequently used
at bridge abutments as protection against slumping and undermining at locations where there is insufficient
space for the use of other types of bank stabilization measures, and where saturated fill slopes or channel banks
cannot otherwise be stabilized.
Bulkheads are classified on the basis of construction methods and materials. They may be constructed of
concrete, masonry, cribs, sheet metal, piling, reinforced earth, used tires, gabions, or other materials. They
must be protected against scour or supported at elevations below anticipated total scour, and where sections of
the installation are intermittently above water, provisions must be made for seepage through the wall. Some
bulkhead types, such as crib walls and gabions, should be provided with safeguards against leaching of
materials from behind the wall.
Bulkheads must be designed to resist the forces of overturning, bending and sliding, either by their mass or by
structural design. Figure 1-3-72 illustrates anchorage schemes for a sheetpile bulkhead. Because of costs, they
should be used as countermeasures against meander migration only where space is not available to construct
other types of measures.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-142
AREMA Manual for Railway Engineering
Natural Waterways
1
Figure 1-3-69. Typical Longitudinal Rock Toe-dike Geometries (after Brown)
3
4
Figure 1-3-70. Longitudinal Rock Toe-dike Tiebacks (after Brown)
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-143
Roadway and Ballast
Figure 1-3-71. Timber Pile, Wire Mesh Crib Dike With Tiebacks (after Brown)
Figure 1-3-72. Anchorage Schemes for a Sheetpile Bulkhead (after Brown)
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-144
AREMA Manual for Railway Engineering
Natural Waterways
References for Other Countermeasures
Brown, S.A., 1985. "Streambank Stabilization Measures for Highway Engineers," FHWA/RD-84/100, FHWA,
Washington, D.C.
Byers, William G. 1962. Stabilization of Canadian River at Canadian, TX, Journal of the Waterways and Harbor
Division, Proceedings of ASCE August 1962, WW3, pages 13-26.
Lagasse, P.F., Zevenbergen, L.W., Schall, J.D., and Clopper, P.E., 2001. "Bridge Scour and Stream Instability
Countermeasures – Experience, Selection, and Design Guidelines," Second Edition, Report FHWA NHI 01-003,
Federal Highway Administration, Hydraulic Engineering Circular No. 23, U.S. Department of Transportation,
Washington, D.C.
Richardson, E.V., Simons, D.B., and Lagasse, P.F., 2001. "River Engineering for Highway Encroachments –
Highways in the River Environment," Report FHWA NHI 01-004, Federal Highway Administration, Hydraulic
Design Series No. 6, Washington, D.C.
SECTION 3.7 MEANS OF PROTECTING ROADBED AND BRIDGES FROM WASHOUTS
AND FLOODS
1
3.7.1 GENERAL (1996)
Adequate protection against floods and washouts is essential not only for maintenance of dependable service,
but also to avoid heavy expenditures to replace damaged facilities and restore operation.
3.7.2 ROADWAY (1996)
3
3.7.2.1 General – Risks and Possible Damage
Water overflowing the embankment, either from a direct flow or backwater, frequently results in damage to the
roadway. This damage may be as severe as a washout or less apparent in other forms, such as, a loss of the
shoulder, a steepening of the embankment, a loss of crib or shoulder ballast, or a softening of the subgrade’s
support characteristics. Damage resulting from sloughing and slides are usually more severe as the water
recedes from a saturated embankment. Loose, fine-grained, cohesionless soils are more susceptible to
sloughing. In general, soil conditions, vegetation, and the rapidity at which the water recedes are primary
factors in determining the risk of sloughing.
3.7.2.2 Temporary Protection Measures
a.
Temporary protection of the roadway section is sometimes necessary, particularly in flood events where
immediate action is necessary and time constraints do not permit implementation of a permanent
solution. Periodic and close track inspections of flood and washout susceptible areas and identification of
high risk locations will be a beneficial first step in determining the appropriate remedial repair.
b. Temporary protection of potential overflow slopes and fill sections subject to erosion and sloughing can
be provided by placement of an armor of heavy weight material, not easily displaced by floodwaters, such
as large-sized stone (riprap) or sandbags. In blanketing the slopes, it is critical that the toe be adequately
protected to minimize the risk of base scour and possible embankment failure. Raising the roadbed
shoulder with riprap and sandbags can also be a suitable means for temporary relief.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-145
4
Roadway and Ballast
3.7.2.3 Permanent Protection Measures
a.
In overflow territories, care must be taken to review the adequacy of design, location and construction of
existing drainageways and make appropriate corrections if deficiencies are found. Sufficient waterway
capacity is essential to minimize heading during floods and, if necessary, provisions should be made for
additional relief openings to handle the flow. The impact of runoff from neighboring facilities, existing
and proposed, must also be assessed. Input from applicable local, state, or federal authorities should be
sought in these preliminary drainage assessments.
b. Selection of the optimal permanent protection measure should be done on a site-specific basis and will
depend on many factors, including service requirements, severity and extent of the damage potential,
embankment soil characteristics, and economic considerations. A subsurface exploration of the area in
question, performed during the preliminary stages, can many times generate valuable information and
aid in the selection and design process.
c.
In general, depending upon service requirements, a track raise is the best assurance for reliable
operation. Roadbeds subject to severe side erosion can be protected by relocation of the track and/or
channel, or construction of revetments as discussed in Article 3.4.5 and Article 3.4.7, respectively. In
overflow bottoms where either a channel change, installation of additional openings, or a track raise or
relocation do not afford sufficient relief, consideration should be given to facing the downstream side of
the roadbed at least at critical locations with riprap or other suitable means of protection. Covering
erosion-susceptible slopes with a thick vegetative cover can furthermore provide protection by impeding
surface erosion.
d. On light traffic density lines where the aforementioned extensive measures cannot be economically
justified, consideration might be given to anchoring the track to the roadbed, at designated locations
throughout the overflow area, utilizing cable tied to rail, timber pile, or screw anchors driven in the
roadbed. Under these conditions use of a heavy course ballast tends to reduce the incidence of ballast
displacement. When using this last method of protection, the railroad is accepting the risk of traffic
disruption due to flooding and washouts.
3.7.3 BRIDGES (1996)
3.7.3.1 General – Risks and Possible Damage
Protection against flood damage for structures calls for resourcefulness during the immediate flooding threat,
as well as during the implementation of permanent protection measures. Temporary measures should be given
consideration to prevent both minor and major damage. Minor damage can be categorized as scour on the
shoulders or behind the abutments, debris hung up in the waterway opening, overtopping, and various other
damage that can be immediately detected and repaired. Major damage are items such as contamination of
ballast decks and roadbed; scouring around piling, piers, foundations, and backwalls; channel changes resulting
in silting or bypassing the structure; culvert piping or joint separation; etc.
3.7.3.2 Temporary Protection Measures
The need for temporary protection should be considered not only prior to and during floods, but also when the
structure is under construction. Temporary measures to consider during or immediately preceding a flood
include, identification of high-risk areas, frequent inspection, remove or pass debris through the structure to
avoid accumulation, and the placement of riprap or sandbags. The following are temporary measures to be
considered when the structure is in the design or construction stage; all the measures considered previously,
and others such as fence jetties, rock jetties, and channel cutoffs.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-146
AREMA Manual for Railway Engineering
Natural Waterways
3.7.3.3 Permanent Protection Measures
Permanent protection measures require that sound engineering principles be employed to protect the structure
from flood damage and allow its continued function as designed. Bridges and culverts must be designed with
sufficient waterway opening to handle the design storm. In addition, both structures must be designed with an
adequate opening to pass the anticipated debris. This also requires occasional re-evaluation as the drainage
area or other conditions change. Some of the measures detailed in various articles in Section 3.4, Basic
Concepts and Definitons of Scour, may need to be incorporated in the structures protection plan. Permanent
protection might also include underwater or other inspections of potential problem areas.
SECTION 3.8 CONSTRUCTION AND PROTECTION OF ROADBED ACROSS RESERVOIR
AREAS1
3.8.1 GENERAL (1978)
a.
The construction and protection of roadbed across reservoir areas present many problems that are not
encountered in normal roadbed construction. Analysis of these problems can best be made by
subdividing the subject into three sections, as follows:
• Determination of Wave Heights
1
• Construction of Embankment and Roadbed
• Construction of Embankment Protection
b. The term “reservoir area” as used in this report also includes lakes, natural and artificial river pools, and
other inland waters on which waves may be generated.
3
3.8.2 DETERMINATION OF WAVE HEIGHTS (1978)
a.
Knowledge relating to wind velocities over land and over water, and wave heights on inland reservoirs,
has increased in recent years as a result of studies made by the Coastal Research Center (formerly
known as the Beach Erosion Board), and by the Corps of Engineers at Fort Peck Reservoir in northeast
Montana, Denison Reservoir on the Oklahoma-Texas state line, and Lake Okeechobee in Southern
Florida.
b. These studies resulted in the publication of Technical Memorandum No. 132, “Waves in Inland
Reservoirs” (Reference 4) by the Beach Erosion Board, essentially the same information having
appeared in ASCE Proceedings Paper No. 3138 (May 1962), corrected May 1963.
c.
The methods subsequently described are adapted from Technical Memorandum No. 132, and are
adequate for ordinary wave problems. For more extensive or complicated situations, the designer should
refer to Technical Memorandum No. 132, or to Technical Report No. 4, “Shore Protection Planning and
Design” (Reference 5) by the Beach Erosion Board, or to other references listed in these publications.
d. Elements affecting the determination of wave heights may be listed as follows.
1
References, Vol. 56, 1955, pp. 706, 1118; Vol. 57, 1956, pp. 649, 1080; Vol. 63, 1962, pp. 578, 749; Vol. 66, 1965, pp. 523, 746; Vol. 78, 1977,
p. 124.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-147
4
Roadway and Ballast
3.8.2.1 Effective Fetch (F)
a.
Fetch, or the distance over which the wind blows, was originally designated as the greatest straight-line
distance across open water. Subsequent studies have shown that the shape of an open-water area affects
the effective fetch.
b. For a given size and shape of water area, effective fetch is determined by laying out seven radials at 6
degrees intervals on each side of a central line through the point under study, extending them to their
point of intersection with the shore line. The scaled component of each radial’s projection on the central
radial is then multiplied by the cosine of its angle with the central radial. The sum of these values
divided by the sum of the cosines determines the effective fetch (F) for that location. An example of this
calculation is shown in Figure 1-3-75.
3.8.2.2 Wind Velocity (U)
a.
Wind velocities over water are higher than over land, and although individual observed values may vary
considerably, average values for this relationship have been observed as shown in Table 1-3-20.
Table 1-3-20. Wind Relationship – Land to Water
Fetch in Miles
U water
Wind ratio --------------------U land
0.5
1.08
1
1.13
2
1.21
4
1.28
6 and over
1.31
b. Thus, a wind having a velocity of 40 mph over land could be expected to attain a velocity of 40 1.28, or
51 mph over water if the effective fetch were 4 miles.
3.8.2.3 Minimum Wind Duration (ta)
With wind velocity assumed to be constant over a particular fetch, the height of waves being generated will
progressively increase with time up to a maximum value for that velocity. The minimum wind duration in
minutes for producing this maximum wave can be determined from the dashed lines in Figure 1-3-73, given the
wind velocity in miles per hour and the effective fetch in miles.
3.8.2.4 Significant Wave Height (Hs)
Although successive waves in a group will vary in height, the significant wave height is defined as the average
of the highest one-third of the waves being generated, measured from trough to crest, and is determined from
the solid diagonal lines in Figure 1-3-73. Since wind-generated waves on a large body of water are not uniform
in height, the significant wave height thus determined will be exceeded approximately 13% of the time.
3.8.2.5 Specific, or Design, Wave Height (Ho)
a.
Wave studies have shown that wind-generated waves are not uniform in height, but consist of groups of
waves with varying heights. Studies of inland reservoirs show the following relationship between the
significant wave height (Hs) which is exceeded 13% of the time, and a selected specific wave height (Ho)
exceeded less frequently (Table 1-3-21).
b. Having determined the significant wave height from Figure 1-3-73, a design wave of acceptable
frequency of occurrence is computed by multiplying Hs by the corresponding ratio value in Table 1-3-21.
A ratio of 1.87 is frequently used for the so-called maximum wave, but over extended periods of
observation, individual waves may even exceed this value.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-148
AREMA Manual for Railway Engineering
Natural Waterways
1
Figure 1-3-73. Wave Heights and Minimum Wind Durations
3
Table 1-3-21. Wave Height Distributions
Ratio of Specific Wave Height Ho to Significant Wave
Height Hs (Ho / Hs)
(1)
Percent of Waves Exceeding
Specific Wave Height Ho
(2)
1.00
13
1.07
10
1.27
4
1.40
2
1.60
1
1.67
0.4
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-149
Roadway and Ballast
3.8.2.6 Wave Period (T)
The significant wave period represents the average interval in seconds between successive waves, and is
determined from Figure 1-3-74. The resulting wave period is also applicable to the higher waves in the group.
3.8.2.7 Wave Length (L)
a.
The wave length (L) is measured from crest to crest of waves in feet, and is equal to 5.12 T2. However,
wave heights and other characteristics are limited by the depth of water in which they are generated if
that depth is less than approximately one-half the wave length. Observations at Lake Okeechobee
(Reference 32) indicated that waves were limited to a maximum significant wave height of
approximately 0.6 of the average depth of water in the generating area, regardless of duration and
velocity of wind.
b. For determining the characteristics of shallow-water-generated waves, reference may be made to the
previously mentioned Technical Memorandum No. 132, or Technical Report No. 4.
Figure 1-3-74. Wave Periods
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-150
AREMA Manual for Railway Engineering
Natural Waterways
3.8.2.8 Set-up, or Wind Tide (S)
a.
An enclosed body of water over which a wind is blowing tends to pile up at higher elevations at the
leeward end, and on long fetches this set-up may assume importance in the design of bank protection.
The increase in water level above the still-water elevation that would prevail without wind action is
determined by the formula:
2
U F
S = -----------------1400D
where:
S = set-up in feet
U = velocity of the wind in miles per hour
F = fetch in statute miles
D = average depth of the body of water in feet
b. Fetch distance used here differs from effective fetch (F) previously described in that it may be of a curved
or sweeping character, and need not move in a straight line. It can also be greater in length than the
effective fetch (see Figure 1-3-75).
1
3
4
Figure 1-3-75. Fetch Example Calculation
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-151
Roadway and Ballast
3.8.2.9 Wave Run-up (R)
On readying a fill a wave will run up the slope to an elevation largely dependent on the angle of the slope, the
roughness of the embankment, and the steepness of tide wave (Ho/Lo). From Figure 1-3-76, relative run-up on
smooth or average riprap covered slopes can be determined where the embankment slope and steepness of
design wave are known. Run-up (R) in feet is secured by multiplying the relative run-up thus found by the
design wave height (Ho), and total run-up will then be the sum of run-up (R) and set-up (S).
Figure 1-3-76. Wave Run-up Ratios
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-152
AREMA Manual for Railway Engineering
Natural Waterways
3.8.2.10 Summary
For a sample computation for determining wave height and protection needs see Table 1-3-22 and Figure 1-375.
Table 1-3-22. Sample Computation for Determining Wave Height and Protection Needs
(See Figure 1-3-75)
Description
1. Effective fetch (F)
Amount
1.42 miles
2. Average wind velocity over land
40 mph
3. Average wind velocity over water (U), = 40 1.21 from Table 1-3-20
48 mph
4. Minimum duration (td) to produce computed wave, from Figure 1-3-73
23 min
5. Significant wave height (Hs), from Figure 1-3-73
2.6 ft
6. Design wave height (Ho), exceeded by only 0.4% of the waves, = Hs + 1.67 from Table 1-3-21
4.3 ft
7. Wave period (T) for significant and design waves, from Figure 1-3-74
8. Wave length (Lo) for design wave = 5.12
T2
9. Wave steepness (Ho/Lo) = 4.3/46.1
3.0 sec
46.1 ft
0.093
2
U Fs
- , where wind tide fetch (Fs) is 6.24 miles (Figure 1-3-75), and average
10. Set-up (S) = ----------------1400 D
depth of lake is 30 ft
0.34 ft
11. Relative run-up ratio (R/Ho) for riprap on 2.5:1 slope, and HoLo = 0.093, using Figure 1-3-76
0.94
12. Wave run-up, (R), (line 6 line 11)
13. Total run-up, (line 10 + line 12)
Weight of rock protection, from Article 3.8.4.2,
where:
S = 2.6 for limestone
H = 4.3, design wave height
cot a = 2.5 for 2.5:1 slope
then:
Wavg
Wmax
Wmin
Minimum Thickness
4.0
4.3 ft
3
162 lb
648 lb
20 lb
18 in
3.8.3 CONSTRUCTION OF EMBANKMENT AND ROADBED (1978)
a.
The embankment should be constructed in accordance with Part 1, Roadbed, except as modified in
conformance with the following:
b. That portion of the embankment which will be submerged should have side slopes not steeper than 3 to
1, and no material should be used in the embankment which has a liquid limit in excess of 60 as
determined in accordance with ASTM Designation D 423-61T, Standard Method of Test for Liquid Limit
of Soils. Width of roadbed, side slopes, prepared ballast and sub-ballast should be in accordance with the
standards of the railroad company. Factors not encountered in ordinary roadbed construction that
should receive consideration include probable maximum water-surface elevation, frequency of
occurrence and duration of embankment submergence, possible head on the embankment (water surface
on one side higher in elevation), and drawdown effect due to the rapid release of stored water.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1
1-3-153
4
Roadway and Ballast
c.
The probable maximum water surface elevation, together with the design wave height, wind tide and
wave run-up effects will govern the elevation at which the roadbed should be constructed. In special
cases the increased headwater elevation due to inflowing water may also be significant.
d. Frequency and duration of embankment submergence is important in determining the suitability of
available embankment material and recommended slopes. An embankment that is stable under ordinary
conditions may not be stable when saturated because of long submergence.
e.
The permeability of the soil to be used in the embankment should be considered in connection with the
probable maximum rate of drawdown in the case of reservoirs. Embankments composed of impervious
materials that are stable when dry, or even when saturated, may fail if the water surface is lowered
rapidly while the embankment is saturated. Pervious free-draining soils are not as susceptible to failure
from this cause as are impervious soils.
3.8.4 CONSTRUCTION OF EMBANKMENT PROTECTION (1978)
3.8.4.1 General
Experience has shown that in the majority of cases, dumped riprap furnishes the best type of protection at the
lowest ultimate cost. Its effectiveness depends on the quality of the rock and its weight or size, thickness of the
layer, shape of the individual stones, slope of the embankment, and stability of tile base or filter on which it is
placed. Usually, the availability of riprap sources determines to some extent the quality and size of stone used
for slope protection.
3.8.4.2 Weight and Thickness of Riprap
a.
Formulas for rock protection of slopes have, until recent years, become more applicable to costal
installations. Requirements for inland bodies of water have been found to require somewhat different
standards of design. One extremely useful set of formulas appears in the Corps of Engineers’ Manual,
EM 1110-2-2300 (1 April 1959), and is substantially as follows:
2
62.4aS H o
W avg = ------------------------------------------------------3
1.82  S – 1  cot a
W max = 4 ¥ W avg
W avg
W max = ------------8'
Minimum Thickness in Inches = 18
3
W avg
-----------------62.4 S
where:
W = weight of individual stones in pounds
S = specific gravity of the rock
Ho = design wave height in feet
a = the angle of slope with the horizontal
b. Gradation of weights of stone should fall within the following classifications: At least 45% shall be
greater than Wavg with not more than 10% greater than Wmax or 10% less than Wmin.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-154
AREMA Manual for Railway Engineering
Natural Waterways
c.
It should be noted that riprap selected by the use of these formulas is suitable for protecting
embankments against wave action in normal circumstances. Special consideration should be given to
specific needs for protection of foundations from scour, or at locations where riprap may be displaced by
ice action.
d. All stone for riprap shall be preferably of angular and irregular shape, and of a quality that will
reasonably withstand the action of water, frost, or other weathering.
3.8.4.3 Minimum Requirements
a.
The protective covering should extend from the natural ground surface at the toe of slope to an elevation
at least 2.0 feet above the height of total run-up as determined in Article 3.8.2.9, or 4.0 feet above stillwater elevation, whichever is greater. Where the natural ground does not provide adequate support, or
where scour is possible, riprap should be extended below the toe of slope by trenching to the required
depth.
b. The thickness of riprap cover should satisfy design requirements of Article 3.8.4.2, but should not be less
than 18 inches thick.
3.8.4.4 Filter Blanket
a.
A bedding layer or filter blanket should be provided underneath riprap protection when the compacted
material of the underlying embankment consists of silt or fine sand. In this case there is danger of the fill
material being washed out through voids in the riprap by wave action which can result in undermining
of the cover material.
b. The filter blanket, composed of gravel (preferably crushed), crushed rock or slag, should be not less than
6 inches and not more than 12 inches in thickness, and should be placed on the embankment slope to
form a backing for the riprap protection, and should be reasonably well graded within the limits found in
Table 1-3-23.
1
3
Table 1-3-23. Filter Blanket Limits
Sieve Size
Percent by Weight Passing
3 inch
100
1-1/2 inch
No. 40
4
40-60
0-5
3.8.4.5 Littoral Currents and Refraction
Littoral current, the result of waves breaking at an angle to the shoreline, and refraction, the process by which
the direction of a wave moving in shallow water at an angle to bottom contours is changed, are primarily the
concern of designers of coastal shore-protection structures, and are not covered here. Reference is made to the
Beads Erosion Board’s Technical Report No. 4, “Shore Protection Planning and Design,” for detailed
information on these subjects.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-155
Roadway and Ballast
SECTION 3.9 GLOSSARY
The following terms are for general use in Part 3. Specialized terms appear in individual paragraphs. Refer to
the Glossary located at the end of the chapter for definitions.
Abrasion
Aggradation
Alluvial Channel
Alluvial Fan
Alluvial Stream
Alluvium
Alternating Bars
Anabranch
Anabranched Stream
Anastomosing Stream
Angle of Repose
Annual Flood
Antecedent Moisture Condition
Apron
Apron, Launching
Areal Precipitation Distribution
Armor (Armoring)
Articulated Concrete Mattress
Artificial Obstruction
Average Velocity
Avulsion
Backcurrent
Backfill
Backwater
Backwater Area
Bank
Bank, Left (Right)
Bank Protection
Bank Revetment
Bankfull Discharge
Bar
Base Floodplain
Bed
Bed Form
Bed Layer
Bed Load
Bed Load Discharge (or Bed Load)
Bed Material
Bed Sediment Discharge
Bed Shear (Tractive Force)
Bed Slope
Bedding Layer
Bedrock
Blanket
Boulder
Braid
Braided Stream
Bridge Opening
Bridge Waterway
Bulk Density
Bulkhead
Bulking
Catchment
Causeway
Caving
Cellular-block Mattress
Channel
Channel Cut-off
Channel Diversion
Channel Pattern
Channel Process
Channelization
Check Dam
Choking (of Flow)
Clay (Mineral)
Clay Plug
Clear-Water Scour
Cobble
Cohesionless Soil
Concrete Revetment
Confluence
Constriction
Contact Load
Contraction
Contraction Scour
Coriolis Force
Countermeasure
Crib
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-156
AREMA Manual for Railway Engineering
Natural Waterways
Crib Dike
Critical Shear Stress
Cross Section
Crossing
Culvert
Current
Current Meter
Curve Number Method
Cut Bank
Cutoff
Cutoff Wall
Daily Discharge
Debris
Degradation
Degradation (Bed)
Depth of Scour
Design Flow (Design Flood)
Dike
Dike (Groin, Spur, Jetty)
Dikes, Jetties, Groins
Discharge (Q)
Dominant Discharge
Drainage Basin Area (A)
Drainage Structure
Drawdown Effect
Drift
Eddy Current
Effective Fetch (F)
Embankment
Entrenched Stream
Ephemeral Stream
Equilibrium Scour
Erosion
Erosion Control Matting
Exceedance Probability
Fabric Mattress
Fall Velocity
Fascine
Fence Jetty
Fetch
Fetch Length
Fill Slope
Filter
Filter Blanket
Filter Fabric (Cloth)
Fine Sediment Load
Flanking
Flashy Stream
Flood-frequency Curve
Floodplain
Floods
Flow-control Structure
Flow Hazard
Flow Slide
Fluvial Geomorphology
Fluvial System
Foreshore
Freeboard
Froude Number
Gabions
General Scour
Geomorphology/Morphology
Grade-control Structure (Sill, Check Dam)
Graded Stream
Gravel
Groin
Grout
Guide Bank
Hardpoint
Headcutting
Heading
Helical Flow
Hydraulic Capacity
Hydraulic Model
Hydraulic Problem
Hydraulic Radius
Hydraulic Structures
Hydraulics
Hydrograph
Hydrology
Icing
Imbricated
Impermeable
Impervious
Incised Reach
Incised Stream
1
3
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-157
Roadway and Ballast
Infiltration
Interface
Invert
Island
Jack
Jack Field
Jetty
Lateral Erosion
Launching
Laursen Scour Design
Leeward
Levee
Liquid Limit (LL)
Littoral Current
Live-bed Scour
Load (or Sediment Load)
Local Scour
Log Pearson Type III Distribution
Longitudinal Profile
Lower Bank
Mathematical Model
Mattress
Meander or Full Meander
Meander Amplitude
Meander Belt
Meander Length
Meander Loop
Meander Radius of Curvature
Meander Ratio
Meander Scrolls
Meander Width
Meandering Stream
Median Diameter
Mid-channel Bar
Middle Bank
Migration
Minimum Wind Duration (ta)
Mud
Natural Levee
Neville Sediment-Transport Scour Design
Nominal Diameter
Nonalluvial Channel
Normal Stage
Overbank flow
Overtopping/Overflowing
Oxbow
Pavement
Paving
Peaked Stone Dike
Perennial Stream
Permeable
Phreatic Line
Pile
Pile Dike
Pilot Channel
Piping
Point Bar
Poised Stream
Probable Maximum Flood
Propeller Backwash
Quarry-run Stone
Railbank Protection
Rainfall Intensity (i)
Rapid Drawdown
Rational Method
Reach
Recurrence Interval
Refraction
Regime
Regime Change
Regime Channel
Regime Formula
Reinforced-earth Bulkhead
Reinforced Revetment
Relief Bridge
Retard (Retarder Structure)
Return Period (T)
Revetment
Riffle
Riparian
Riprap
River Training
Rock Jetty Dike
Rock-and-wire Mattress
Roughness Coefficient
Rubble
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-158
AREMA Manual for Railway Engineering
Natural Waterways
Runoff
Runoff Coefficient (c)
Sack Revetment
Saltation Load
Sand
Scour
Sediment or Fluvial Sediment
Sediment Concentration
Sediment Deposition
Sediment Discharge
Sediment Load
Sediment-Transport Scour
Sediment Yield
Seepage
Shear Stress
Sheet Pile
Shoal
Significant Wave Height (HS)
Sill
Silt
Silting
Sinuosity
Slope (of Channel or Stream)
Slope Protection
Sloughing
Slope-area Method
Slump
Soil-cement
Sorting
Specific Wave Height (HO)
Spill-through Abutment
Spread Footing
Spur
Spur Dike
Stability
Stable Channel
Stage
Stone Riprap
Storm Duration (t)
Stream
Streambank Erosion
Streambank Failure
Streambank Protection
Sub-bed Material
Subcritical, Supercritical Flow
Surface Runoff
Suspended Sediment Discharge
Temporal Precipitation Distribution
Tetrahedron
Tetrapod
Thalweg
Tieback
Timber or Brush Mattress
Timber Pike Dike
Time of Concentration (tc)
Toe of Bank
Toe Protection
Total Scour
Total Sediment Load
Tractive Force
Trench-fill Revetment
Turbulence
Ultimate Scour
Ultimate Total Abstraction (S)
Undermining
Uniform Flow
Unit Discharge
Unit Shear Force (Shear Stress)
Unsteady Flow
Upper Bank
Velocity
Velocity (V) - Water
Velocity (U) - Wind
Vertical Abutment
Vortex
Wandering Channel
Wandering Thalweg
Wash Load
Washout
Watershed
Waterway Opening Width (Area)
Wave Length (L)
Wave Period (T)
Wave Run-up (R)
Weephole
Wind Tide (S)
1
3
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-3-159
Roadway and Ballast
Windrow Revetment
Wire Mesh
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-3-160
AREMA Manual for Railway Engineering
1
Part 4
Culverts1
— 2006 —
TABLE OF CONTENTS
Section/Article
Description
Page
4.1 Location and Type. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.1.1 Waterway Required (1995) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.1.2 Span Required (1995) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.1.3 Character of Hydraulic Bedload (Abrasive, Corrosive, Etc.) (1995) . . . . . . . . . . . . . . . . . .
4.1.4 Topographic Conditions Determining Angle, Gradient, and Length of
Structure (1987) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.1.5 Foundation Conditions (1987) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.1.6 Height and Character of Embankment (1987) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.1.7 Loading, Live and Dead (1984) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.1.8 Economics of Various T ypes (1984) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-4-7
1-4-7
1-4-8
1-4-8
1-4-9
4.2 Specifications for Placement of Reinforced Concrete Culvert Pipe. . . . . . . . . . . . . . .
1-4-9
4.3 Specifications for Prefabricated Corrugated Steel Pipe and Pipe-arches for Culverts,
Storm Drains, and Underdrains . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.3.1 General (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.3.2 Material (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.3.3 Fabrication (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.3.4 Coupling Bands (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.3.5 Shape (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.3.6 Workmanship (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.3.7 Mill or Shop Inspection (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.3.8 Field Inspection and Acceptance (1989). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-4-10
1-4-10
1-4-10
1-4-10
1-4-13
1-4-14
1-4-16
1-4-16
1-4-17
4.4 Specifications for Coated Corrugated Steel Pipe and Arches . . . . . . . . . . . . . . . . . . . .
4.4.1 Specification for Bituminous Coated Galvanized Steel Pipe and Pipe Arches (1989). . . .
4.4.2 Specification for Polymeric Coated Corrugated Galvanized Steel Pipe or Pipe
Arches (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1
1-4-6
1-4-6
1-4-6
1-4-6
1-4-17
1-4-17
1-4-17
References, Vol. 40, 1939, pp. 520, 729; Vol. 51, 1950, pp. 708, 839; Vol. 54, 1953, pp. 108, 1385; Vol. 62, 1961, pp. 678, 936; Vol. 85, 1984,
p. 5; Vol. 89, 1988, p. 40; Vol. 90, 1989, p. 34; Vol. 93, 1992, pp. 34, 39; Vol. 94, 1994, p. 30; Vol. 96, p. 20.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-1
1
3
Roadway and Ballast
TABLE OF CONTENTS (CONT)
Section/Article
Description
Page
4.5 Standard Specification for Corrugated Aluminum Alloy Pipe. . . . . . . . . . . . . . . . . . . .
4.5.1 General (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.5.2 Material (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.5.3 Fabrication (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.5.4 Coupling Bands – Class I and Class II (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.5.5 Shape – Class I and Class II (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-4-17
1-4-17
1-4-18
1-4-20
1-4-22
1-4-23
4.6 Specifications for Corrugated Structural Steel Plate Pipe, Pipe-arches, and Arches
4.6.1 General (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.6.2 Material (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.6.3 Fabrication (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-4-24
1-4-24
1-4-24
1-4-26
4.7 Specifications for Corrugated Structural Aluminum Alloy Plate Pipe,
Pipe-arches, and Arches . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.7.1 General (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.7.2 Material (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.7.3 Fabrication (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-4-26
1-4-26
1-4-26
1-4-28
4.8 Hydraulics of Culverts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.8.1 Introduction (1989). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.8.2 Design Method (1989). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.8.3 Flow Conditions (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.8.4 Hydraulic Computations (1989). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-4-29
1-4-29
1-4-29
1-4-30
1-4-34
4.9 Design Criteria for Corrugated Metal Pipes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.9.1 Criteria (1994). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.9.2 Formulas (1994) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.9.3 Loads (1994) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.9.4 Pipe Culvert Design Properties (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.9.5 Minimum and Maximum Height of Cover in Feet (1989) . . . . . . . . . . . . . . . . . . . . . . . . .
4.9.6 Pipe Arches (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-4-56
1-4-56
1-4-56
1-4-58
1-4-58
1-4-60
1-4-63
4.10 Design Criteria for Structural Plate Pipes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.10.1 Criteria Formulas (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.10.2 Seam Strength of Structural Plate Pipes (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.10.3 Minimum and Maximum Height of Cover in Feet (1989) . . . . . . . . . . . . . . . . . . . . . . . . .
1-4-65
1-4-65
1-4-65
1-4-66
4.11 Culvert End Treatments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.11.1 Introduction (1992). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.11.2 Headwalls (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.11.3 Wingwalls (1995) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.11.4 Inverts and Aprons (1995) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-4-68
1-4-68
1-4-68
1-4-69
1-4-70
4.12 Assembly and Installation of Pipe Culverts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.12.1 General (1995) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.12.2 Alignment (1995) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.12.3 Construction Methods (1995). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.12.4 Preparation of Foundation (1995) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.12.5 Handling and Unloading (1995). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.12.6 Assembly (1995) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-4-70
1-4-70
1-4-71
1-4-71
1-4-71
1-4-71
1-4-72
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-2
AREMA Manual for Railway Engineering
Culverts
TABLE OF CONTENTS (CONT)
Section/Article
4.12.7
4.12.8
4.12.9
4.12.10
4.12.11
Description
Page
Backfill (1995) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Multiple Installations (1995) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
End Treatment (1995). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Protection of Pipe Culvert from Construction Loads (1995) . . . . . . . . . . . . . . . . . . . . . . .
Safety Provisions (1995) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-4-72
1-4-74
1-4-74
1-4-74
1-4-75
4.13 Earth Boring and Jacking Culvert Pipe through Fills . . . . . . . . . . . . . . . . . . . . . . . . . .
4.13.1 General (1995) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.13.2 Type of Pipe Suitable for Jacking (1992) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.13.3 Size and Length of Pipe (1992) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.13.4 Precautions in Unstable Soils (1992) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.13.5 Protection of Pipe Against Percolation, Piping and Scour (1992) . . . . . . . . . . . . . . . . . . .
4.13.6 Safety (1992) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-4-75
1-4-75
1-4-76
1-4-76
1-4-76
1-4-77
1-4-77
4.14 Culvert Rehabilitation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.14.1 General (1992) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.14.2 Survey of Existing Structures (1992) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.14.3 Methods of Rehabilitation (1992) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.14.4 Localized Repairs (1992) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.14.5 Relining Materials (1992) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.14.6 In Place Installation of Concrete Invert (1992) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-4-77
1-4-77
1-4-77
1-4-78
1-4-78
1-4-79
1-4-81
4.15 Specification for Steel Tunnel Liner Plates . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.15.1 General (1992) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.15.2 Material (1992) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.15.3 Fabrication (1992) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.15.4 Coatings (1992) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.15.5 Design (1992) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-4-82
1-4-82
1-4-83
1-4-83
1-4-84
1-4-84
4.16 Construction of Tunnel Using Steel Tunnel Liner Plates. . . . . . . . . . . . . . . . . . . . . . . .
4.16.1 Scope (1992) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.16.2 Description (1992) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.16.3 Installation (1992) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.16.4 Measurement (1992) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.16.5 Payment (1992) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-4-90
1-4-90
1-4-90
1-4-90
1-4-90
1-4-90
4.17 Culvert Inspection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.17.1 Introduction (2001) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.17.2 Definition of a Culvert (2001) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.17.3 Key Differences From Bridges and Other Structures (2001) . . . . . . . . . . . . . . . . . . . . . . .
4.17.4 Safety (2001) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.17.5 Inventory, Assessment of Existing Conditions, and Frequency of Inspection (2001) . . . .
4.17.6 Physical Condition Assessment (2001). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.17.7 Evaluation/Recommended Action (2001) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.17.8 Inspection Follow-up (2001) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-4-91
1-4-91
1-4-91
1-4-91
1-4-92
1-4-93
1-4-94
1-4-97
1-4-97
4.18 Perforated Pipe Drains . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.18.1 General (2006) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.18.2 Applications (2006) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-4-100
1-4-100
1-4-100
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-3
1
3
4
Roadway and Ballast
TABLE OF CONTENTS (CONT)
Section/Article
4.18.3
4.18.4
4.18.5
4.18.6
4.18.7
4.18.8
4.18.9
4.18.10
Description
Page
Materials (2006) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Related Filter Materials (2006) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Hydraulic Design (2006). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Structural Design (2006) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Construction Requirements (2006) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Inspection and Acceptance (2006) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Operation and Maintenance (2006) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Safety Provisions (2006). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-4-100
1-4-101
1-4-101
1-4-102
1-4-102
1-4-104
1-4-104
1-4-104
LIST OF FIGURES
Figure
1-4-1
1-4-2
1-4-3
1-4-4
1-4-5
1-4-6
1-4-7
1-4-8
1-4-9
1-4-10
1-4-11
1-4-12
1-4-13
1-4-14
1-4-15
1-4-16
1-4-17
1-4-18
1-4-19
1-4-20
1-4-21
1-4-22
1-4-23
1-4-24
Description
Page
Inlet Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Outlet Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Relationship of Headwater to High Tailwater and Other Terms in EQ 4-1 . . . . . . . . . . . . . . .
Low Tailwater in Relation to Terms of the Flow Equation . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Difference Between Energy Grade Line and Hydraulic Grade Line . . . . . . . . . . . . . . . . . . . . .
Inlet Control – Headwater Depths for Corrugated Metal Pipe Culverts . . . . . . . . . . . . . . . . . .
Inlet Control – Headwater Depths for Corrugated Metal Pipe-arch Culverts. . . . . . . . . . . . . .
Inlet Control – Headwater Depths for Structural Plate Pipe-arch Culverts with 18-inch
Radius Corner Plate for Three Types of Inlet (Reference 22) . . . . . . . . . . . . . . . . . . . . . . .
Inlet Control – Headwater Depths for Structural Plate Pipe-arch Culverts with 31-inch
Radius Corner Plate for Three Types of Inlet (Reference 22) . . . . . . . . . . . . . . . . . . . . . . .
Inlet Control – Headwater Depths for Concrete Pipe Culverts for Three Types of Inlet
(Reference 22) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Inlet Control – Headwater Depths for Oval Concrete with Long Axis Horizontal for
Three Types of Inlet (Reference 22) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Inlet Control – Headwater Depths for Oval Concrete Pipe Culverts with Long Axis
Vertical for Three Types of Inlet (Reference 22) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Outlet Control – Head for Corrugated Metal Pipe Culvert with Submerged Outlet
and Culvert Flowing Full (See Note Under Sketch at Top) (Reference 22). . . . . . . . . . . . . . . .
Outlet Control – Head for Corrugated Metal Pipe-arch Culvert with Submerged Outlet
and Flowing Full (Reference 22). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Outlet Control – Head for Structural Plate Pipe Culvert with Submerged Outlet
and Flowing Full (Reference 22) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Outlet Control – Head for Structural Plate Pipe-arch Culvert with 18-Inch Corner
Radius with Submerged Outlet and Flowing Full (Reference 22) . . . . . . . . . . . . . . . . . . . . . . .
Outlet Control – Head for Concrete Pipe Culverts with Submerged Outlet and
Flowing Full (Reference 22) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Outlet Control – Head for Oval Concrete Pipe Culverts with Long Axis Horizontal or
Vertical Submerged Outlet and Flowing Full (Reference 22). . . . . . . . . . . . . . . . . . . . . . . . . . .
Hydraulic Elements for Circular Corrugated Steel Pipe . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Hydraulic Properties of Corrugated Steel and Structural Plate Pipe-arches . . . . . . . . . . . . . .
Comparison of Waterway Cross-sectional Areas at Equal Depths of Flow in Circular
Pipe and Pipe-arch. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Proper Bedding and Haunch Support . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Minimum Permissible Spacings for Multiple Installations . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Using Warped Fill to Balance Loads Across Ends of Culverts . . . . . . . . . . . . . . . . . . . . . . . . . .
1-4-30
1-4-31
1-4-33
1-4-33
1-4-33
1-4-36
1-4-37
1-4-38
1-4-39
1-4-40
1-4-41
1-4-42
1-4-44
1-4-45
1-4-46
1-4-47
1-4-48
1-4-49
1-4-50
1-4-52
1-4-55
1-4-73
1-4-74
1-4-75
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-4
AREMA Manual for Railway Engineering
Culverts
LIST OF FIGURES (CONT)
Figure
1-4-25
1-4-26
1-4-27
1-4-28
1-4-29
Description
CMP Liner Pipe Installation Showing Guide Rails, Grout Plugs and Adjusting Rods . . . . . . .
Example of New Invert in CMP . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Diagram for Coefficient Cd for Tunnels in Soil . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Culvert Inspection Form . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Typical Underdrain Detail . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Page
1-4-80
1-4-82
1-4-87
1-4-98
1-4-102
LIST OF TABLES
Table
1-4-1
1-4-2
1-4-3
1-4-4
1-4-5
1-4-6
1-4-7
1-4-8
1-4-9
1-4-10
1-4-11
1-4-12
1-4-13
1-4-14
1-4-15
1-4-16
1-4-17
1-4-18
1-4-19
1-4-20
1-4-21
1-4-22
1-4-23
1-4-24
1-4-25
1-4-26
1-4-27
1-4-28
1-4-29
1-4-30
1-4-31
1-4-32
1-4-33
1-4-34
1-4-35
1-4-36
1-4-37
Description
Page
Corrugations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4-11
Perforations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4-11
Pipe Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4-12
Riveted Seams. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4-13
Pipe Arch Specification Requirements Pipe Arches – 2-2/3  1/2 Corrugations (See Note 3) 1-4-15
Pipe Arch Specification Requirements Pipe Arches – 3 1 and 5 1Corrugations (See Note 2) . .
1-4-15
Gage or Decimal Thickness . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4-18
Chemical Composition . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4-19
Mechanical Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4-19
Dimensions of Corrugations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4-21
Minimum Rivet Diameter (See Note 3) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4-21
Pipe Sheet Thickness to Lock Seam Strength . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4-22
Flat Sheet or Plate, Bolts, Nuts, and Extrusion Physical Properties . . . . . . . . . . . . . . . . . . . . . 1-4-27
Entrance Loss Coefficients for Corrugated Metal Pipe or Pipe Arch (Reference 22) . . . . . . . . 1-4-31
Values of Coefficient of Roughness (n) for Standard Corrugated Metal Pipe (Manning’s Formula)
(Reference 1). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4-35
Values of n for Structural Plate Pipe for 62 Corrugations (Manning’s Formula) (Reference 25) 1-4-35
Length Adjustment for Improved Hydraulics . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4-44
Length Adjustment for Improved Hydraulics . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4-46
Length Adjustments for Improved Hydraulics. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4-47
Full Flow Data for Round Pipe . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4-51
Full Flow Data for Corrugated Steel Pipe-arches . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4-52
Full Flow Data for Structural Plate Pipe-arches – Corrugations 6  2 . . . . . . . . . . . . . . . . . . 1-4-53
Full Flow Data for Corrugated Steel Pipe-arches – Corrugations 6  2 . . . . . . . . . . . . . . . . . 1-4-54
Live Loads for Cooper E-80 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4-58
Gage vs Metal Thickness . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4-58
Metal Mechanical Properties . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4-58
Minimum Longitudinal Seam Strength in Kips per Foot . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4-59
Steel and Aluminum Corrugated Pipes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4-59
Steel Round Corrugated Pipe Minimum and Maximum Height of Cover in Feet . . . . . . . . . . . 1-4-61
Aluminum Round Corrugated Pipe Minimum and Maximum Height of Cover in Feet . . . . . . 1-4-62
Typical Allowable Bearing Pressures (See Note 1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4-63
Steel and Aluminum Arch Pipes Minimum Thickness of Metal (Gage) . . . . . . . . . . . . . . . . . . . 1-4-64
Steel and Aluminum Structural Plate Pipes in Kips per Foot all Bolts to be
3/4 inch in Size . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-4-65
Steel and Aluminum Structural Plate Pipes Section Properties. . . . . . . . . . . . . . . . . . . . . . . . . 1-4-65
Steel Round Structural Plate Pipe Minimum and Maximum Height of Cover (ft) . . . . . . . . . . 1-4-66
Aluminum Round Structural Plate Pipe Minimum and Maximum Height of Cover (ft) . . . . . 1-4-67
Aluminum Round Structural Plate Pipe Minimum and Maximum Height of Cover (ft) . . . . . 1-4-67
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-5
1
3
4
Roadway and Ballast
LIST OF TABLES (CONT)
Table
Description
Page
1-4-38 Effective Sectional Properties Based on the Average of One Ring of Plates . . . . . . . . . . . . . . .
1-4-39 Live Loads, Including Impact, for Various Heights of Cover for Cooper E 80 . . . . . . . . . . . . .
1-4-40 Longitudinal Seam Strengths . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-4-85
1-4-86
1-4-88
SECTION 4.1 LOCATION AND TYPE
4.1.1 WATERWAY REQUIRED (1995)
Determination of the proper size culvert opening requires knowledge of the drainage area, runoff, data on past
performance, such as highwater marks above, at and below the opening, and pertinent formulas, with experience
and good judgment in interpreting them. Consideration of the stream both above and below the opening is
necessary. The ideal opening is one in which the velocity of the stream above the opening is maintained or
somewhat increased through the opening and below to a point where the flow will have no effect on the railway.
See Part 3, Natural Waterways.
4.1.2 SPAN REQUIRED (1995)
a.
The span of the culvert should be such that the property above will not be injuriously affected at time of
maximum runoff, nor a head created which will induce destructive velocities.
b.
In shallow fills the span may have to be increased to provide the predetermined area. For pipe culverts,
where practical, the cover should be a minimum of 22 feet below the bottom of tie.
c.
For practical reasons, a minimum size pipe culvert should be established, even though runoff computations
may show that a size smaller than the minimum might be used. For main line track a minimum diameter of
24 inches is recommended, while for highway crossings and unimportant track, the minimum diameter may
be reduced to 18 inches. Pipe structures smaller than these are difficult to clean out and may be of
insufficient capacity if freezing occurs.
4.1.3 CHARACTER OF HYDRAULIC BEDLOAD (ABRASIVE, CORROSIVE, ETC.) (1995)
a.
Except in localities of such special service classifications as mineralized, organic, and salt water, which are
relatively small in area as compared with the entire country, corrosion from soil and water is far less
important in shortening the life of drainage structures than is the abrasive action of the hydraulic bedload.
So far as soil corrosion on the outside of structures is concerned, extensive soil corrosion tests of the Bureau
of Standards show conclusively that in only about 10% of the soils is corrosion from the outside severe: that
in about another 10% the corrosion is mildly severe, and that in more than 80% the soil corrosion is
negligible.
b.
Turning to internal corrosion, mine water, especially from coal mines, is particularly difficult to handle as it
attacks all commonly used materials except possibly well burnt vitrified clay pipe.
c.
The alkali soils are of two kinds, black alkali and white alkali. White alkali usually contains quantities of
sulfates, carbonates or chlorides, which on evaporation of moisture in the soil leaves a white crust on the
surface. The black alkali, a sodium carbonate, does not leave the white crust.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-6
AREMA Manual for Railway Engineering
Culverts
d.
The white alkalies, particularly the sulfates, are more severe on concrete than metal. The black alkalies and
the chloride salt alkalies, on the other hand, are relatively more severe on metal than on concrete.
e.
Sea water is injurious to all types of drainage materials. The chlorides in the salt water shorten the life of
metal structures, while the alternate wetting and drying, and the frost action in cold climates accelerate the
deterioration of concrete.
f.
Wherever the service conditions are such as to indicate severe abrasive or corrosive action, the available
drainage material that will be least affected should be used, resulting in a structure that will give the lowest
cost per year of service.
4.1.4 TOPOGRAPHIC CONDITIONS DETERMINING ANGLE, GRADIENT, AND LENGTH
OF STRUCTURE (1987)
a.
A culvert, being an enclosed channel substituted for an open waterway, is a fixed section of what is possibly
an unstable stream that is changing its course, scouring deeper, or filling up. The alignment, gradient and
length of the structure should therefore be determined so as to obtain the most economical safe installation.
b.
The best alignment is that which gives the water a straight entrance into the culvert and a direct exit. A
stream that is very crooked, or one that is changing its course, may possibly be relocated to make it cross the
roadbed at or near a right angle, but the best general principle is to make the alignment of the structure
coincide as nearly as possible with that of the stream.
c.
A culvert should usually be given the same general gradient as the stream bed. One of the most common
mistakes is to place the invert at the same elevation as the stream bed. The result is that sedimentation
reduces the effective area of the opening.
d.
Under new fills where there is a possibility of subsidence of the natural ground thereunder, culverts should
be laid or constructed with sufficient camber so that there will be no dips or depressions in the culvert when
subsidence has stopped.
e.
The length of a culvert depends upon the shoulder-to-shoulder width of the roadbed, the height of fill, the
slope of the embankment, the gradient of the culvert, the skew angle, and whether or not headwalls are to
be built. The best method of determining the required length is by the use of a cross-sectional sketch of the
embankment and a plan and profile of the water course.
4.1.5 FOUNDATION CONDITIONS (1987)
Every structure should have the best foundation possible to obtain within the limits of the allowable cost for the
structure. But it is not always possible to obtain a satisfactory foundation for some types of structures at a
reasonable cost, and it is in these cases that cost comparisons may play an important part in the choice of the type
of structure to be used. The heavier a structure is per foot of length, the greater the required bearing power of the
soil underneath. In the case of rigid types of structures, cradling or even piling is sometimes necessary. In all cases
backfill should be thoroughly tamped and compacted to a minimum 90% density as determined by ASTM D-698.
4.1.6 HEIGHT AND CHARACTER OF EMBANKMENT (1987)
A factor that must be considered in the selection of structures is that of transverse forces in fills. These forces are
manifested by the tendency of the fill material to move downward and outward, seeking its angle of repose and
tending to separate the lengths of pipe culverts and open cracks in masonry. Transverse forces are present in every
fill but are likely to be particularly severe on sidehill locations.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-7
1
3
4
Roadway and Ballast
4.1.7 LOADING, LIVE AND DEAD (1984)
Extensive research work on the problem of culvert loading and design has been done. The results of this research
are given in the following references:
a.
Iowa State Experiment Station, Ames, Iowa.
Bulletin 79, “Experimental Determination of Static and Impact Loads Transmitted to Culverts.”
Bulletin 96, “Theory of External Loads on Closed Conduits.”
Bulletin 112, “The Supporting Strength of Rigid Pipe Culverts.”
b.
American Railway Engineering Association, Proceedings, Vol. 27, 1926, page 794, Proceedings, Vol. 29,
1928, page 527.
Discussion and analysis of culvert loading and failures as developed by tests carried out under the
sponsorship of this committee at various points, including the Farina test under high fills on the then new
Edgewood cutoff of the Illinois Central Railroad. These tests involved both rigid and flexible type culverts.
c.
A culvert pipe placed under an embankment derives its ability to support the superimposed load from two
sources:
(1) The strength of the pipe ring or shell to resist external pressures; this may be termed inherent strength,
and,
(2) The lateral pressure of the embankment material upon the sides or vertical projection of the pipe,
producing stresses in the pipe ring directly opposite to those produced by the vertical load and therefore
assisting the pipe in supporting the vertical load.
In a rigid pipe, such as concrete, cast iron, vitrified clay, etc., the inherent strength of the pipe is the
predominant source of supporting ability. The only lateral pressure that can be safely depended upon to
augment the load-carrying capacity of the pipe is the active lateral pressure of the embankment material
since the rigid pipes deform but little, if any, under the vertical load and consequently the sides do not move
outward enough to develop any appreciable passive resisting pressure in the surrounding embankment
material.
In a flexible pipe considerable strength is obtained through ring compression, but in bending (flexural)
strength is low. Therefore, a large part of its ability to support the vertical load must be derived from the
passive pressures induced or set up as the sides move outward against the surrounding material. The ability
of a flexible pipe to deform readily without failure and thus utilize the passive pressures set up on the sides
of the pipe is its principal distinguishing structural characteristics and accounts for the fact that such a
relatively lightweight pipe of low inherent strength can support high embankments without showing
evidence of structural distress.
4.1.8 ECONOMICS OF VARIOUS TYPES (1984)
a.
Requirement of any opening is a suitable continuing passageway for the water. Any economic study must
include (1) interest on the investment, (2) maintenance costs, and (3) provision for an annual payment
which will accumulate to a sufficient amount to replace the structure at the end of its useful life (or retire
bonds sold to secure funds for the existing structure – the result being the same from an economic study
standpoint). The sum of these three charges is the annual cost. The principle involved is long established
and widely used.
b.
To arrive at the amount of interest on the investment, the initial cost installed must be determined. The
items included in the cost are: Engineering; superintendence; labor; material, tools, equipment, supplies,
and transportation and handling thereof, including stores expense; for supporting tracks – sheeting,
shoring, pumping, excavation, including channel changes, building the structure, backfilling and restoring
the tracks; all the costs from inception to completion.
c.
In preparing cost estimates, different methods of installation should be investigated. Under some
conditions, when using pipe, a sizable saving can be made by such methods as tunneling, threading, and
jacking.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-8
AREMA Manual for Railway Engineering
Culverts
d.
Having arrived at the cost of the structure ready for service, the first item of annual cost is obtained by
multiplying this initial cost by the average interest rate paid on railroad bonds over a period of years.
e.
The second item is that of maintenance, the estimate of which should be based upon actual records of costs
of maintenance of similar structures.
f.
The third item, replacement annuity, is dependent upon the sum necessary to be accumulated, the rate of
return on sinking funds, and the useful life of the structure. With this information and a table of annuities,
the third item in the annual cost formula is easily obtained.
g.
The useful life for structures of various types should be estimated for each major service classification, from
records of the company, or from an examination of structures in each service classification that have been in
service for at least 5 to 10 years. Much can be learned from painstaking field inspection of existing
structures if all factors affecting the performance of the structures are taken into consideration.
h. Since cost comparisons are so easily made, and since it is one of the chief functions of a railroad engineer to
operate the road, in so far as his sphere of influence extends, at the lowest true annual cost possible,
economic comparisons should be made one of the guides toward the selection of drainage structures.
SECTION 4.2 SPECIFICATIONS FOR PLACEMENT OF
REINFORCED CONCRETE CULVERT PIPE
1
See Chapter 8, Concrete Structures and Foundations, Part 10, Reinforced Concrete Culvert Pipe.
SECTION 4.3 SPECIFICATIONS FOR PREFABRICATED CORRUGATED STEEL PIPE AND
PIPE-ARCHES FOR CULVERTS, STORM DRAINS, AND UNDERDRAINS
3
4.3.1 GENERAL (1989)
4.3.1.1 Scope
4
This specification covers coated, prefabricated corrugated steel pipe and pipe arches for use as culverts, storm
sewers and underdrains.
4.3.1.2 Class
Pipe and pipe arches shall be of the following classes with respect to corrugations (See Table 1-4-1):
• Class I Annular corrugations.
• Class II Helical corrugations.
4.3.1.3 Shape
Pipe and pipe arches shall be of the following cross-sectional shapes:
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-9
Roadway and Ballast
• Shape 1 Pipe, full circular cross section.
• Shape 2 Pipe, factory elongated.
• Shape 3 Pipe arch cross section.
4.3.2 MATERIAL (1989)
4.3.2.1 Steel Sheets
Corrugated steel pipe and pipe arches shall be fabricated from either of the following materials:
• Steel sheet, zinc coated in accordance with AASHTO M-2l8.
• Steel sheet, aluminum coated in accordance with AASHTO M-274.
4.3.2.2 Rivets
All rivets shall conform to the specifications of ASTM designation A31, Grade A, and shall be electroplated in
accordance with the specifications of ASTM designation A 164, Type RS.
4.3.3 FABRICATION (1989)
4.3.3.1 Corrugations
The corrugations shall form smooth, continuous curves and tangents. The crests and valleys of annularly
corrugated pipe and pipe arches shall form circumferential rings about the longitudinal axis of the pipe. The crests
and valleys of helically corrugated pipe and pipe arches shall form helices about the longitudinal axis of the pipe,
and the direction of the corrugations shall be not less than 45 degrees from the longitudinal axis of the pipe. The
dimensions of the corrugations shall be as specified in Table 1-4-1.
Table 1-4-1. Corrugations
Class
I
II
Diameter
Nominal
Size
Maximum Pitch
Minimum
(Note 1)
Inside Radius
8–96
2-2/31/2
2-3/4
11/16 
12–96
31
3-1/4
9/32 
6–18
1-1/21/4
1-7/8
9/32 
12–96
2-2/31/2
2-3/4
11/16 
48–120
31
3-1/4
9/32 
48–120
51
5-1/4
1-9/32 
Note 1: Pitch is measured at right angles to the corrugation.
Note 2: Depth shall not overrun by more than 5%.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-10
AREMA Manual for Railway Engineering
Culverts
4.3.3.2 Perforations for Underdrains
Perforations, unless otherwise specified, shall be arranged in two groups of longitudinal rows placed symmetrically
on each side of an unperforated segment corresponding to the flow line of the pipe. The longitudinal rows within
each group shall be spaced on approximately 1-1/2 inches centers in annularly corrugated pipe and on
approximately 1 inch centers on helically corrugated pipe. The perforations shall have a diameter of approximately
3/8 inch and shall be located on the inside crests, or on the neutral axis, of all corrugations except that perforations
are not required within 6 inches of each pipe or in the crests of corrugations where seams are located. The
minimum number of longitudinal rows of perforations and the minimum width of the unperforated segment shall
be as shown in Table 1-4-2.
Table 1-4-2. Perforations
Nominal
Inside Diameter
Inches
Minimum Number or
Rows of
Perforations
Minimum Width
of Unperforated
Segment
Inches
6
4
4
8
4
7
10
4
9
12
6
9-1/2
15
6
13
18
6
16-1/2
21
6
20
24
8
22
1
3
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-11
Roadway and Ballast
4.3.3.3 Widths of Laps (Class I Annular Pipe)
a.
The lapped joints in longitudinal seams shall be as shown in Table 1-4-3.
b.
The average inside diameter of circular pipe and pipe to be reformed into pipe arches shall not vary more
than 1/2 inch from the nominal diameter when measured on the inside crest of the corrugations for
diameters through 48 inches and 1% for diameters greater than 48 inches. In no case shall the difference in
diameter of the abutting pipe ends be more than 1/2 inch.
Table 1-4-3. Pipe Requirements
Nominal Inside
Diameter
Inches
Corrugation Depth
Nominal
Inches
Minimum Width
or Lap
Inches
8
1/2
1-1/2
10
1/2
1-1/2
12
1/2
1-1/2
15
1/2
1-1/2
18
1/2
1-1/2
21
1/2
1-1/2
24
1/2
2
30
1/2
2
36
1/2
2
36
1
3
42
1/2 or 1
3
48
1/2 or 1
3
54
1/2 or 1
3
60
1/2 or 1
3
66
1/2 or 1
3
72
1/2 or 1
3
78
1/2 or 1
3
84
1/2 or 1
3
90
1
3
96
1
3
102
1
3
108
1
3
114
1
3
120
1
3
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-12
AREMA Manual for Railway Engineering
Culverts
4.3.3.4 Riveted Seams
a.
Rivets shall be of the diameter shown in Table 1-4-4.
Table 1-4-4. Riveted Seams
Gage
b.
Sheet Thickness
Inches
Rivet Diameter
Inches
2-2/3 x 1/2
31
16
0.064
5/16
3/8
14
0.079
9/32
3/8
12
0.109
3/8
7/16
10
0.138
3/8
7/16
8
0.168
3/8
7/16
All rivets shall be cold driven in such a manner that the metal shall be drawn tightly together throughout
the entire lap. The center of each rivet shall be not closer than 2 rivet diameters from the edge of the sheets.
All rivets shall have full hemispherical heads or heads of a form acceptable to the engineer. They shall be
driven in a neat, workmanlike manner to completely fill the hole without bending. Longitudinal seams shall
be riveted with one rivet in each corrugation for pipes less than 42 inches in diameter and two rivets in each
corrugation for pipes 42 inches in diameter and larger. Circumferential seams shall be riveted with a rivet
spacing of 6 inches except that six rivets will be sufficient in 12 inches diameter pipe. The longitudinal
seams of all 1 inch corrugated depth shall be two rivets in each corrugation.
1
4.3.3.5 Welded Seams (Class II Helical Pipe)
Helically corrugated welded seam pipe shall have a continuous welded seam extending from end to end of each
length of pipe section. The welded seam shall be of the high-frequency resistance butt welded type and shall be
sufficiently strong to develop the full strength of the pipe.
4.3.3.6 Lock Seams (Class II Helical Pipe)
Helically corrugated lock seam pipe shall have a continuous folded lock seam extending from end to end of each
length of pipe section. Folded lock seams shall be formed with sufficient pressure to prevent any seam slippage that
would seriously affect the load-carrying capacity of the pipe but without damaging the metal to such an extent that
a plane of weakness is created. The metal used in fabricating lock seam shall be one that will permit cold forming
without damage.
4.3.4 COUPLING BANDS (1989)
a.
Field joints for each class of corrugated steel pipe shall provide circumferential and longitudinal strength to
preserve the pipe alignment, prevent separation of pipe and prevent infiltration of side fill material. The
coupling bands shall be made of the same base metal as the pipe and shall be similarly coated. Coupling
bands may be the next thickness lighter than that used for the pipe but not more than 0.109 inch (12 gage)
nor less than 0.052 inch (18 gage). To facilitate field jointing, the ends of individual pipe section with helical
corrugations may be rerolled to form circumferential corrugations extending at least two corrugations from
the pipe end. All types of pipe ends, whether rerolled or not, shall be matched in a joint such that the
maximum difference in the diameter of abutting pipe ends is 2 inch.
b.
Class I pipe furnished with circumferential corrugations, including rerolled end helical pipe, shall be field
jointed with locking bands. The corrugated bands shall be not less than 7 inches wide for diameters through
36 inches, and 102 inches wide for all other pipe diameters. Wider bands should be considered where
transverse forces are present, particularly on side hill slopes.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-13
3
4
Roadway and Ballast
c.
Class II pipe with helical corrugations shall be field jointed, preferably with bands with projections. The
projections shall conform substantially to the shape and depth of the pipe corrugations and shall be in
circumferential rows with one projection for each corrugation of helical pipe. Bands shall be so constructed
as to lap on an equal portion of each of the culvert sections to be connected. The bands for pipe diameters of
12 inches to 54 inches incl., shall be at least 102 inches wide and shall have two circumferential rows of
projections: and for pipe diameters 60 inches and greater shall be at least 163 inches wide and shall have
four circumferential rows of projections. The band shall be connected in a manner approved by the chief
engineer or his representative, with a suitable fastening device such as galvanized 2 inches by 2 inches by
3/16 inch angles, or integrally or separately formed and attached flanges bolted with 2 inch-in-diameter
galvanized bolts, or a wedgelock constructed of the same gage as the band itself. The 102 inches band shall
have two, and the 163 inches band shall have three 2 inch band shall have two, and the 163 inches band
shall have three 2 inch diameter galvanized fastening bolts.
d.
Underdrain pipe may be field jointed with bands as described above or with a smooth sleeve-type coupler.
The sleeve-type coupling may be either plastic or galvanized steel, suitable for holding the pipe firmly in
alignment without the use of sealing compound or gaskets. Integral formed flanges fastened with 3/8 inch
diameter galvanized bolts may be used in lieu of angles on two-piece corrugated bands.
e.
Other equally effective types of coupling bands and/or band-fastening devices may be used if approved by
the chief engineer or his representative.
4.3.5 SHAPE (1989)
a.
Class I and Class II pipe shall be furnished, as specified, as Shape 1, Shape 2 or Shape 3.
b.
Shape 1 pipe shall be round pipe, available in diameters of 6 inches to 120 inches, incl.
c.
Shape 2 pipe shall be factory elongated to form an approximate ellipse with the vertical diameter
approximately 5% greater than the nominal diameter of the corresponding round pipe. Shape 2 pipe shall be
available in nominal diameters of 48 inches to 120 inches incl.
d.
Shape 3 pipe arch shall be fabricated by reforming a circular pipe to a multi-centered pipe having an archshaped top with a slightly convex integral bottom. The pipe-arch shall conform to the requirements of
Table 1-4-5 and Table 1-4-6. The longitudinal seams of riveted pipe arches shall not be placed in the haunch
area.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-14
AREMA Manual for Railway Engineering
Culverts
Table 1-4-5. Pipe Arch Specification Requirements Pipe Arches – 2-2/3   1/2 Corrugations
(See Note 3)
Pipe Arch
Size
Inches
Equivalent
Diameter
Inches
Span
Inches
(Note 1)
Rise
Inches
(Note 1)
Minimum Corner
Radius
Inches
Maximum B
Inches
(Note 2)
17 13
21 15
15
17
13
3
5-1/4
18
21
15
3
6
24 18
21
24
18
3
7-1/4
28 20
35 24
24
28
20
3
8
30
35
24
3
9-1/2
42 29
49 33
36
42
29
3-1/2
10-1/2
42
49
33
4
11-1/2
57 38
64 43
48
57
38
5
13-1/2
54
64
43
6
15
71 47
77 52
60
71
47
7
16-1/2
66
77
52
8
18
1
83 57
72
83
57
9
20
Note 1: A tolerance of ±1 or 2% of equivalent circular diameter, whichever is greater, will be
permissible in span and rise.
Note 2: B is defined as the vertical dimension from a horizontal line across the widest portion of the
arch to the lowest portion of the base.
Note 3: All dimensions are measured from the inside crests of the corrugations.
3
Table 1-4-6. Pipe Arch Specification Requirements Pipe Arches – 3 1 and 5 1Corrugations
(See Note 2)
Pipe Arch
Size
Inches
Equivalent
Diameter
Inches
Span
Inches
(Note 1)
Rise
Inches
(Note 1)
Minimum Corner
Radius
Inches
40 31
46 36
36
40–1.8
31+1.8
5
42
46–2.1
36+2.1
6
53 41
60 46
48
53–2.4
41+2.4
7
54
60–2.7
46+2.7
8
66 51
73 55
60
66–3.0
51+3.0
9
66
73–3.3
55+3.3
12
81 59
87 63
72
81–3.6
59+3.6
14
78
87–4.4
63+4.4
14
95 67
84
95–4.8
67+4.8
16
103 71
112 75
90
103–5.2
71+5.2
16
96
112–5.6
75+5.6
18
117 79
102
117–5.9
79+5.9
18
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-15
Roadway and Ballast
Table 1-4-6. Pipe Arch Specification Requirements Pipe Arches – 3 1 and 5 1Corrugations
(See Note 2) (Continued)
Pipe Arch
Size
Inches
Equivalent
Diameter
Inches
Span
Inches
(Note 1)
Rise
Inches
(Note 1)
Minimum Corner
Radius
Inches
128 83
137 87
108
128–6.4
83+6.4
18
114
137–6.9
87+6.9
18
120
142–7.1
91+7.1
18
142 91
Note 1: Negative and positive numbers listed with span and rise dimensions are negative and positive
tolerances.
Note 2: All dimensions are measured from the inside crests of the corrugation.
4.3.6 WORKMANSHIP (1989)
Pipe shall show careful, finished workmanship in all particulars and shall be free from the following defects:
a.
Undue deviation from true shape.
b.
Uneven laps.
c.
Variations from a reasonably straight center line.
d.
Ragged or diagonally sheared edges.
e.
Loose, unevenly lined or spaced rivets, or welds.
f.
Poorly formed rivet heads.
g.
Illegible brand.
h. Dents or bends, other than corrugations.
i.
Poor welds.
j.
Poorly formed lock seams and/or damaged lock seam metal.
k.
Bruised, scaled or broken coating.
4.3.7 MILL OR SHOP INSPECTION (1989)
If the purchaser so elects, he may have the material inspected in the shop where it is fabricated. He may require
from the mill that a chemical analysis be made of any heat. The purchaser, or his representative, shall have free
access to the mill or shop for inspection purposes, and every facility shall be extended to him for this purpose. Any
material included in any shipment which has been rejected at the mill or shop will be considered sufficient cause
for the rejection of the entire shipment.
4.3.8 FIELD INSPECTION AND ACCEPTANCE (1989)
The field inspection shall be made by the purchaser, who shall be furnished by the seller with an itemized
statement of the sizes and lengths of pipe for deficiencies in length of sheets used, nominal specified diameter, net
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-16
AREMA Manual for Railway Engineering
Culverts
length of finished pipe and any evidences of poor workmanship as outlined above. The inspection may include the
taking of samples for chemical analysis and determination of weight of zinc coating. If 25% of the pipe in any
shipment fails to meet all the requirements of this specifications, the entire shipment may be rejected.
SECTION 4.4 SPECIFICATIONS FOR COATED CORRUGATED STEEL PIPE AND
ARCHES
4.4.1 SPECIFICATION FOR BITUMINOUS COATED GALVANIZED STEEL PIPE AND PIPE
ARCHES (1989)
Corrugated steel galvanized pipe or pipe arches shall be bituminous coated or coated and paved in accordance with
current AASHTO Specification M-190.
4.4.2 SPECIFICATION FOR POLYMERIC COATED CORRUGATED GALVANIZED STEEL
PIPE OR PIPE ARCHES (1989)
Corrugated steel galvanized pipe or pipe arches shall be polymeric coated in accordance with current AASHTO
Specification M-246.
1
SECTION 4.5 STANDARD SPECIFICATION FOR CORRUGATED ALUMINUM ALLOY PIPE
4.5.1 GENERAL (1989)
3
4.5.1.1 Scope
This specification covers corrugated aluminum pipe for use as culverts, storm drains, and underdrains.
4.5.1.2 Class
4
Pipe and pipe arches shall be of the following classes with respect to corrugations (See Table 1-4-10):
• Class I – Annular corrugation.
• Class II – Helical corrugation.
4.5.1.3 Shapes
Pipe and pipe arches shall be of the following cross-sectional shapes:
• Shape 1 – Pipe, full circular cross-section.
• Shape 2 – Pipe, factory elongated.
• Shape 3 – Pipe arch cross section.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-17
Roadway and Ballast
4.5.2 MATERIAL (1989)
4.5.2.1 Sheet or Coil
Corrugated aluminum pipe and pipe arches shall be fabricated from clad 3004 H34 aluminum sheets or in coil cutto-length conforming to the current ASTM specification designation B-209 and latest AASHTO specification Ml97. The corrugations shall conform to the requirements set in Table 1-4-10.
4.5.2.2 Accepted Brands of Aluminum Alloy
No aluminum alloy will be accepted under the specification and no bids will be considered for the materials above
described until after the sheet manufacturer’s certified analysis and manufacturer’s guarantee has been passed
upon by the engineer and accepted. Misbranding or other misrepresentation and non-uniformity of product will
each be considered a sufficient reason to discontinue the acceptance of any brand under this specification and
notice sent to the sheet manufacturer of the discontinuance of acceptance of any brand will be considered to be
notice to all culvert companies which handle that particular brand.
4.5.2.3 Sheet Manufacturer’s Certified Analysis
The manufacturer of each brand shall file with the engineer a certificate setting forth the name or brand of
aluminum alloy to be furnished and a statement that the material conforms to the specified chemical composition
limits. The certificates shall be sworn to for the manufacturer by a person having legal authority to bind company.
4.5.2.4 Sheet Manufacturer’s Guarantee
The manufacturer of the sheets shall submit with the certified analysis a guarantee providing that all aluminum
alloy furnished shall conform to the specification requirements, shall bear a suitable identification brand or mark,
and shall be replaced without cost to the purchaser when not in conformity with the specified analysis, sheet
thickness or cladding thickness, and the guarantee shall be so worded as to remain in effect as long as the
manufacturer continues to furnish material.
4.5.2.5 Thickness
All the thickness of both flat sheet or formed coil shall have the gage or decimal thickness found in
Table 1-4-7.
Table 1-4-7. Gage or Decimal Thickness
Gage
Specified Inches
Minimum Inches
16
0.060
0.057
14
0.075
0.072
12
0.105
0.101
10
0.135
0.130
8
0.164
0.158
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-18
AREMA Manual for Railway Engineering
Culverts
4.5.2.6 Chemical Composition
The core metal and cladding shall conform to the chemical requirements of Table 1-4-8.
Table 1-4-8. Chemical Composition
Culvert Sheet Core %
(Note 1)
Type
Culvert Sheet Cladding %
(Note 1)
Silicon
0.3
(Si + Fe) = 0.7
Iron
0.7
Copper
0.25
0.10
Manganese
1.0 – 1.5
0.10
Magnesium
0.8 – 1.3
0.10
Zinc
0.25
0.8 – 1.3
Other, each
0.05
0.05
Total
0.15
0.15
Note 1: Composition in percent maximum unless shown as range.
1
4.5.2.7 Mechanical Requirements
The material shall conform to the mechanical properties of Table 1-4-9.
Table 1-4-9. Mechanical Requirements
Tensile Strength
psi
Minimum
Maximum
Yield Strength,
psi (0.2% offset)
Minimum
0.048 to 0.113
31,000
37,000
24,000
4
0.114 to 0.249
31,000
37,000
24,000
5
Thickness
inches
Elongation
in 2%
Minimum
3
4
4.5.2.8 Cladding Thickness
The clad in each side shall be 5% of the total thickness.
4.5.2.9 Tests by Sheet Manufacturer
Sampling and testing by the purchaser shall conform to the latest requirements as outlined in AASHTO M-197.
4.5.2.10 Dimensions and Tolerances
The latest AASHTO M-197 specs shall be followed.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-19
Roadway and Ballast
4.5.2.11 Marking
Each corrugated sheet or coil used in corrugated pipe shall be identified by the manufacturer and producer
showing the following:
a.
Name of sheet manufacturer.
b.
Alloy and temper.
c.
Manufacturer’s standard thickness.
d.
Manufacturer’s date of corrugating by a six digit number indicating in order of the year, month, and day of
the month.
e.
Identification of the pipe fabricator if different than the sheet manufacturer.
4.5.2.12 Rivets
Rivets shall conform to the chemical composition shown in ASTM B-316 for alloy 6053 T4 and shall have the
following mechanical properties:
Tensile strength . . . . . . . . . . . . . 25,000 psi
Yield strength . . . . . . . . . . . . . . . 14,000 psi
Shear . . . . . . . . . . . . . . . . . . . . . . 15,000 psi
Elongation . . . . . . . . . . . . . . . . . . 16%
4.5.3 FABRICATION (1989)
Pipe under this section shall be fabricated with circumferential corrugation and riveted, lap joint construction or
with helical corrugations and a continuous lock or welded seam extending from end to end each length of pipe.
4.5.3.1 Corrugations
The corrugations shall form smooth, continuous curves and tangents. The radii of curvature of the corrugations
shall be at least one-half the depth of the corrugations. The crests and valleys of annularly corrugated pipe and
pipe arches shall form circumferential rings about the longitudinal axis of the pipe. The crests and valleys of
helically corrugated pipe and pipe arches shall form helices about the longitudinal axis of the pipe, and the
direction of the corrugations shall be not less than 45 degrees from the longitudinal axis of the pipe. The
dimensions of the corrugations shall be as specified in Table 1-4-10.
4.5.3.2 Class I – Annular Corrugation
Pipe under this class shall be of riveted fabrication. The corrugation shall be 2 inch from 12 inches to 84 inches or
1 inch from 36 inches to 90 inches diameter.
4.5.3.3 Width of Laps
The lapped joints in circumferential seams shall be 1-1/2 inches. The lapped joints in longitudinal seams shall be 11/2 inches, for pipe diameters of 8 to 21 inches: 2 inches for pipe diameters of 24 inches, 30 inches, and 36 inches;
and 3 inches for pipe diameters of 42 to 90 inches.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-20
AREMA Manual for Railway Engineering
Culverts
Table 1-4-10. Dimensions of Corrugations
Corrugations
Class
(Note 3)
I (Annular)
II (Helical)
Depth
Inches
(Note 2)
Pitch
Inches
Diameter
Inches
Minimum
(Note 1)
Maximum
(Note 1)
12 – 84
2-1/4
2-3/4
1/2
1
36 – 120
2-3/4
3-1/4
36 – 120
5-3/4
6-1/4
1
6, 8, 10
1-3/8
1-7/8
1/4
12 – 21
2-1/4
2-3/4
7/16
12 – 84
2-1/4
2-3/4
1/2
30 – 90
2-3/4
3-1/4
1
Note 1: The pitch shall be measured at right angles to the corrugations.
Note 2: The depth shall not underrun by more than 5%.
Note 3: Underdrains – Pipe is available with or without perforations.
1
4.5.3.4 Riveted Seams
a.
Rivets shall be of the diameter for either the sheet thickness or pipe diameter or both as shown in Table 1-411. All rivets shall be cold driven in such a manner that the metal shall be drawn tightly together
throughout the entire lap. The center of each rivet shall be not closer than 2-rivet diameter from the edge of
the sheets. All rivets shall have full hemispherical heads or heads of a form acceptable to the engineer. They
shall be driven in a neat, workmanlike manner to completely fill the hole without bending.
Table 1-4-11. Minimum Rivet Diameter
(See Note 3)
3
Corrugation
Thickness Inches
2-2/3 x 1/2
(Note 1)
3x1
(Note 2)
0.060
5/16
0.075
5/16
3/8
3/8
0.105
3/8
3/8
3/8
0.135
0.164
4
1/2
1/2
1/2
Note 1: One rivet each valley for pipes 36 inches and smaller.
Two rivets each valley for pipes 42 inches and larger.
Note 2: Two rivets each valley for all diameters.
Note 3: Rivet sizes shown are minimum. Larger rivets or additional
rivets are permissible if necessary to increase seam strength.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-21
Roadway and Ballast
b.
Longitudinal seams for 7/16 inch and 2 inch, shall be riveted with one rivet each corrugation for pipes less
than 42 inches in diameter, and two rivets in each corrugation for pipes 42 inches in diameter and larger.
The longitudinal seams of 1 inch corrugation depth shall be riveted with two lines of rivets spaced
longitudinally on 3 inches center. The distance between center lines of two rivet rows shall not be less than
12 inches. For 1 inch depth corrugations, in lieu of shop riveting, pipe may be field assembled using 2 inch
diameter aluminized or galvanized steel bolts. Spacing and location of field bolts will be the same as spacing
and location of shop rivets.
4.5.3.5 Class II – Helical Corrugation
Pipe under this class shall be helically corrugated pipe with continuous lock seam extending from end to end of
each pipe. The corrugation requirements are as outlined in Article 4.5.3.1. The corrugation for helical pipe is
shown in Table 1-4-10.
a.
Pipes fabricated with a continuous helical lock seam parallel to the corrugation may be used for full circle
and equivalent pipe arch sizes.
b.
The lock seam shall be formed in the tangent element of the corrugation profile with its center near the
neutral axis of the corrugation profile. The edges of the sheets within the cross section of the lock seam shall
lap at least 5/32 inch for the pipes 10 inches or less in diameter and at least 5/16 inch for pipe greater than
10 inches in diameter with an occasional tolerance of minus 10% of lap with allowable.
c.
The lapped surfaces shall be in tight contact. The profile of sheet on at least one side of the lock seam and
adjacent to the 180 degrees fold shall have a minimum retaining offset of 2 sheet thickness. There shall be
no excessive angularity on the interior of the 180 degrees fold of metal at the lock seam which will cause
visual cracks in the sheet. Roller indention shall not cause cracks in the sheet or a loss of metal contact
within the seam.
d.
The lock seam shall be mechanically staked at periodic intervals or otherwise specially constructed to
prevent slippage. Tensile specimens cut from production pipe normal to and across the lock seam develop
the strength as tabulated in Table 1-4-12.
Table 1-4-12. Pipe Sheet Thickness to Lock Seam Strength
Pipe Sheet Thickness Minimum Lock Seam Strength
Inches
Pounds/Inch
0.060
170
0.075
245
0.105
425
4.5.4 COUPLING BANDS – CLASS I AND CLASS II (1989)
a.
Field joints for pipe sections shall be made with coupling bands which will provide the circumferential and
longitudinal strength required to preserve the pipe alignment and to prevent separation of pipe sections,
thereby minimizing infiltration of fill material. Coupling bands shall be made of the same alloy material as
the pipe, shall have corrugations that mesh with the corrugations of the pipe sections to be connected, and
shall be formed to fit the shape specified for those sections. The bands shall be not more than one standard
use thickness lighter than that used for the pipe sections to be connected, but never less than 0.048 inch
material. The bands shall be fabricated to lap on an equal portion of each of the sections connected.
b.
Bands with corrugations shall be not less than 7 inches wide for pipe 12 inches to 30 inches in diameter, not
less than 12 inches for pipe diameters 36 inches to 60 inches, inclusive, and not less than 24 inches for pipe
diameters 66 inches and larger. The 1 inch depth corrugation shall always have 2 feet wide bands. Wider
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-22
AREMA Manual for Railway Engineering
Culverts
bands should be considered where transverse forces are present, particularly on sidehill slopes. The bands
shall have 2 inches by 2 inches by 3/16 inch aluminum alloy connection angles conforming to ASTM B22 1,
alloy 6063-T6, welded or riveted securely to the band ends. Aluminum alloy lugs or integrally formed flanges
are acceptable in lieu of angles.
c.
The bands shall be installed as specified and tightened in place by not less than 2 inch galvanized steel bolts
or aluminized steel bolts through the vertical legs of connection angles. Bands 7 inches wide shall have 2
bolts; 12 inches bands, 3 bolts; and 24 inches bands, 4 bolts.
d.
Perforated pipe may be joined with bands as described above.
For pipe diameters 12 inches to 36 inches, inclusive, one-piece coupling bands utilizing a slip seam may be
specified. This device provides for coupling band expansion by mechanically slipping the lock seam so that
the coupler may be slipped over the ends of the pipe sections to be connected. The coupler is drawn snug
over the pipe by reversing the method of slipping the seam and is then tightened to prevent further slippage.
Mechanical slipping of seams is effected by means of a 2 inch bolt with double reverse threads used in
conjunction with extruded aluminum lugs tapped to receive the 2 inch threaded bolt and welded to the band,
one on each side of the helical seam.
e.
Other equally effective coupling bands or methods for connecting the pipe sections may be used when
specified or if approved by the Chief Engineer.
4.5.5 SHAPE – CLASS I AND CLASS II (1989)
1
Class I and Class II pipe shall be furnished as specified as Shape 1, Shape 2 or Shape 3.
4.5.5.1 Shape 1
Shape 1 pipe shall be round pipe, available in diameter of 6 inches to 90 inches inclusive.
4.5.5.2 Shape 2
3
Shape 2 pipe shall be factory elongated to form an approximate ellipse with the vertical diameter approximately 5%
greater than the nominal diameter of the corresponding round pipe. Shape 2 pipe available in normal diameter of
48 inches to 90 inches inclusive.
4.5.5.3 Shape 3
Shape 3 pipe arch shall be fabricated by reforming a circular pipe to a multi-centered pipe having an arch-shaped
top with a slightly convex integral bottom. Class I pipe to be reformed into pipe arch shall have the longitudinal
lapped seams staggered so as to alternate on each side of the top center line by approximately 10% of the periphery.
The pipe arch shall conform to the equivalents of Table 1-4-5 and Table 1-4-6 under specifications for corrugated
steel pipe.
SECTION 4.6 SPECIFICATIONS FOR CORRUGATED STRUCTURAL STEEL PLATE PIPE,
PIPE-ARCHES, AND ARCHES
NOTE:
Design of structural steel plate pipes, pipe arches and arches are based on empirical rules.
4.6.1 GENERAL (1989)
These specifications cover corrugated structural steel plate pipe, pipe arch, and arch culverts 60 inches or more in
diameter or in span.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-23
4
Roadway and Ballast
4.6.2 MATERIAL (1989)
4.6.2.1 Description of Plates
a.
Plates shall consist of structural units of galvanized corrugated steel. The corrugations shall run at right
angles to the longitudinal axis of the structure and shall have a pitch of 6 inches, with a tolerance of 3 inch
and a depth of 2 inches, with a tolerance of 1/8 inch. The radius of the inside of the corrugation shall be at
least 1-1/16 inches. Plates shall be furnished in standard sizes to permit structure length increments of 2 feet. Plates shall have approximately a 2 inches lip beyond each end crest.
b.
The gage of plates and radii of curvature shall be as specified. The plates at longitudinal and circumferential
seams shall be connected by bolts. Joints shall be staggered so that not more than three plates come
together at any one point. Each plate shall be curved to a circular arc.
c.
Plates for a pipe arch, when assembled, shall form a cross section made up of four circular arcs tangent to
each other at their junctions and symmetrical about the vertical axis. Pipe arches shall be installed with the
flat side down.
4.6.2.2 Base Metal
The base metal of the corrugated steel plates shall conform to the requirements of current ASTM Specification,
Designation A-761.
4.6.2.3 Spelter Coating
a.
A coating of prime western spelter, or equal, of not less than 12 oz. per square foot on each surface for 0.188
inch or thicker and 1 oz. per square foot on each surface less than 0.188 inch in thickness shall be applied by
the hot-dip process. If the average spelter coating as determined from the required samples is less than the
amount specified above, or if any one specimen shows a deficiency of 10%, the lot sampled shall be rejected.
Spelter coating shall be of first-class commercial quality, free from injurious defects, such as blisters, flux
and uncoated spots.
b.
The sheets are to be galvanized after fabrication.
4.6.2.4 Physical Properties
a.
b.
The minimum physical properties of the flat sheet or plate before corrugation shall be as follows:
Tensile strength, psi. . . . . . . . . .
42,000
Yield point, psi . . . . . . . . . . . . . .
28,000
Elongation in 2, %. . . . . . . . . . .
30
The supplier shall certify that the tests performed on each heat of the material furnished meet the above
requirements.
4.6.2.5 Sampling
For testing the weight of the spelter coating and for chemical analysis of the base metal, when required, a sample
approximately 3 inch square, or a sample of equivalent area, shall be cut from the corner of one plate in each 100
plates of a shipment or fraction thereof, or coupons approximately 6 inch square of the same gage and base metal
as the material sampled shall be attached to the center of one edge of the plates before galvanizing. If the result of
a weight of coating test for any coupon does not conform to the requirements specified, retests of two additional
samples cut from the product plates for the order shall be made, each of which shall conform to the requirements
specified.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-24
AREMA Manual for Railway Engineering
Culverts
4.6.2.6 Test for Spelter Coating
The test for weight of spelter coating shall be made in accordance with the hydrocholoric acid-antimony chloride
method, as described in current ASTM Specification, Designation A 90.
4.6.2.7 Identification
a.
No plates shall be accepted unless the metal is identified by a stamp on each plate showing:
(1) Name of base metal manufacturer.
(2) Name of brand and kind of base metal.
(3) Gage number.
(4) Weight of spelter coating.
(5) Identification symbols showing heat number.
b.
The identification brands shall be so placed that when the pipe or arch is erected the identification will
appear on the inside of the structure.
4.6.2.8 Bolts
a.
Bolts for connecting plates shall be not less than 3/4 inch in diameter, of proper length to accommodate the
number of plate laps, and the bolts and nuts shall be hot-dip galvanized to conform with the requirements of
the current ASTM Specification, Designation A. 153. The threads shall be American Standard Coarse
Thread Series, Class 2, free fit. Bolt and nut materials shall conform to the requirements of the current
ASTM Specification, Designation A 449 and A 563 Grade C respectively.
b.
The bolts may be sampled and tested before erection is commenced or the bolts may be accepted on the
manufacturer’s certification.
c.
Bolt heads and nuts, shaped to provide adequate bearing, shall be used.
1
3
4.6.2.9 Gage Determination and Tolerance
The gage shall be determined by the weight of fabricated galvanized plates. The average weight of any one lot of
plates shall not underrun the theoretical weight by more than 5%, and no individual plate weighed shall underrun
the theoretical weight by more than 10%.
4.6.2.10 Field Inspection and Acceptance of Plates
a.
The field inspection shall be made by the engineer. The manufacturer shall furnish an itemized statement of
the number and length of the plates in each shipment.
b.
Each plate included in a shipment failing to meet the requirements of these specifications shall be rejected,
and if 25% of the plates fail to meet the requirements the entire shipment may be rejected.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-25
4
Roadway and Ballast
4.6.3 FABRICATION (1989)
4.6.3.1 Forming and Punching Plates
a.
Plates shall be formed to provide lap joints. The bolt holes shall be so punched that all plates having like
dimensions, curvature, and the same number of bolts per foot of seam, shall be interchangeable. Each plate
shall be curved to the proper radius so that the dimensions of the finished structure will be as specified.
b.
Unless otherwise specified, bolt holes along those edges of the plates that will form longitudinal seams in the
finished structure shall be staggered in rows 2 inches apart, with one row in the valley and one in the crest
of the corrugations. Bolt holes along those edges of the plates that will form circumferential seams in the
finished structure shall provide for a bolt spacing of not more than 12 inches. The minimum distance from
center of holes to the edge of the plate shall be 1-3/4 times the diameter of the bolt. The diameter of the bolt
hole in the longitudinal seams shall not exceed the diameter of the bolt by more than 1/8 inch.
c.
Plates for forming skewed or sloped ends shall be cut so as to give the angle of skew or slope specified. Flame
cut edges shall be free from oxide or burrs and shall present a workmanlike finish. Legible identification
numerals shall be placed on each part plate to designate its proper position in the finished structure.
d.
When specified, the structural plate for round pipe shall be formed so as to provide, when assembled, an
elliptical cross section having a vertical elongation of approximately 5%.
SECTION 4.7 SPECIFICATIONS FOR CORRUGATED STRUCTURAL ALUMINUM ALLOY
PLATE PIPE, PIPE-ARCHES, AND ARCHES
NOTE:
Design of structural aluminum alloy pipes, pipe arches and arches are based on empirical
rules.
4.7.1 GENERAL (1989)
These specifications cover aluminum alloy corrugated structural plate pipe, pipe arches and arch culverts 60 inches
or more in diameter or in span.
4.7.2 MATERIAL (1989)
4.7.2.1 Description of Plates
a.
Plates shall consist of structural units of uncoated aluminum alloy. The corrugations shall run at tight
angles to the longitudinal axis of the structure and shall have a pitch of 9 inches with a tolerance of 3/8 inch
and a depth of 2-1/2 inches with a tolerance of 1/8 inch. The radius of the inside of the corrugation shall be
not less than 2 inches. Plates shall have approximately a 2 inches lip beyond each end crest.
b.
The gage plates and radii of curvature shall be as specified. The plates at longitudinal and circumferential
seams shall be connected by bolts. Joints shall be staggered so that not more than three plates come
together at any one point. Each plate shall be curved to a circular arc.
c.
Plates for a pipe arch, when assembled, shall form a cross section made up of four circular arcs tangent to
each other at their junctions and symmetrical about the vertical axis. Pipe arches shall be installed with the
flat side down.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-26
AREMA Manual for Railway Engineering
Culverts
4.7.2.2 Base Metal
The plates shall be fabricated from aluminum alloy 5052-H141. The chemical composition of the plates shall
conform to ASTM Designation B209 alloy 5052. Aluminum bolt and nut material shall conform to the Chemical
requirements of ASTM Designation B-211 alloy 6061-T6. Bolts and nuts may be aluminum, aluminized steel, or
galvanized steel. Extrusion material shall conform to the Chemical requirements of ASTM B22l alloy 6063-T6.
4.7.2.3 Physical Properties
a.
The minimum physical properties of the flat sheet or plate, bolts, nuts and extrusion are found in Table 1-413.
b.
The supplier shall certify that the tests performed on each heat of the material furnished meet the above
requirements.
Table 1-4-13. Flat Sheet or Plate, Bolts, Nuts, and Extrusion Physical Properties
Thickness Inches
Tensile Strength
(psi)
Yield Point
(psi)
Plate
0.100-0.174
35,500
24,000
6
Plate
0.175-0.300
34,000
24,000
8
Bolts
0.125-8.000
42,000
35,000
10
Extrusions
0.125-1.000
31,000
24,000
10
Item
Elongation in
2 inches, %
1
4.7.2.4 Identification
a.
No plates shall be accepted unless the metal is identified by a stamp on each plate showing:
3
(1) Name of base metal manufacturer.
(2) Name of brand and kind of base metal or alloy designation.
(3) Manufacturer’s standard thickness.
(4) Manufacturer’s date of processing by a six (6) digit number indicating in order the year, month, and day
of month.
b.
The identification brands shall be so placed that when the pipe or arch is erected the identification will
appear on the inside of the structure.
4.7.2.5 Bolts
a.
Bolts for connecting plates shall be not less than : inch in diameter, of proper length to accommodate the
number of plate laps, and the bolts and nuts shall be hot-dip galvanized to conform with the requirements of
the current ASTM Designations A 307 or A 325 or aluminum conforming with ASTM Designation B-211
alloy 6061. Aluminum nuts shall be prelubricated with a suitable wax compound. The threads shall be
American Standard Coarse Thread Series, Class 2, free fit.
b.
The bolts may be sampled and tested before erection is commenced or the bolts may be accepted on the
manufacturer’s certification.
c.
Bolt heads and nuts, shaped to provide adequate bearing, shall be used.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-27
4
Roadway and Ballast
4.7.2.6 Gage Determination and Tolerance
The gage shall be determined by the weight of fabricated plates. The average weight of any one lot of plates shall
not underrun the theoretical weight by more than 5%, and no individual plate weighed shall underrun the
theoretical weight by more than 10%.
4.7.2.7 Field Inspection and Acceptance of Plates
a.
The field inspection shall be made by the engineer. The manufacturer shall furnish an itemized statement of
the number and length of the plates in each shipment.
b.
Each plate included in a shipment failing to meet the requirements of these specifications shall be rejected,
and if 25% of the plates fail to meet the requirements, the entire shipment may be rejected.
4.7.3 FABRICATION (1989)
4.7.3.1 Forming and Punching Plates
a.
Plates shall be formed to provide lap joints. The bolt holes shall be so punched that all plates having like
dimensions, curvature, and the same number of bolts per foot of seam, shall be interchangeable. Each plate
shall be curved to the proper radius so that the dimensions of the finished structure will be as specified.
b.
Unless otherwise specified, bolt holes along those edges of plates that will form longitudinal seams in the
finished structure shall be in rows 1-3/4 inches apart, with a pair in the valley and crest of the corrugations.
Bolt holes along those edges of the plates that will form circumferential seams in the finished structure shall
provide for a bolt spacing of not more than 9-5/8 inches. The minimum distance from center of holes to the
edge of the plate shall be 1-3/4 times the diameter of the bolt. The diameter of the bolt hole in the
longitudinal seams shall not exceed the diameter of the bolt by more than 1/8 inch.
c.
When specified, the structural plate for round pipe shall be formed so as to provide, when assembled, an
elliptical cross section having a vertical elongation of approximately 5%.
SECTION 4.8 HYDRAULICS OF CULVERTS
4.8.1 INTRODUCTION (1989)
a.
Designing a culvert has not yet reached the stage where two or more individuals will always arrive at the
same answer, or where actual service performance matches the designer’s anticipation. The reason is that
the engineer’s interpretation of field data and hydrology is often influenced by personal judgment, based on
his own experience in a given locality. However, field data, hydrology and hydraulic research are closing the
gap to move the art of designing a culvert a little closer to becoming a science.
b.
Up to this point, the design procedure has consisted of collecting field data, compiling facts about the
roadway, and making a reasonable estimate of flood flow for a chosen frequency. The fourth step is to design
an economical culvert to handle the flow (including debris) with minimum damage to the right of way or
adjacent property.
c.
Factors to consider include: type of structure; area and shape of waterway opening; approximate length and
slope of culvert barrel; and treatment of inlet and outlet ends.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-28
AREMA Manual for Railway Engineering
Culverts
4.8.2 DESIGN METHOD (1989)
a.
The culvert design process shall strive for a balanced result. Pure fluid mechanics should be combined with
practical considerations to help assure satisfactory performance under actual field conditions. This includes
prospective maintenance and the handling of debris.
b.
As a minimum, it is recommended that the culvert shall be designed to discharge:
(1) a 25-year flood without static head at entrance, and
(2) a 100-year flood using the available head at entrance, the head to 2 feet below base of rail, or the head to
a depth of 1.5 times the culvert diameter/rise, whichever is less.
c.
This approach lends itself well to most modern design processes and computer programs such as those
published by the Federal Highway Administration (Reference 21). It applies a usable rational control to the
elusive matter of minimum waterway area which constitutes good practice. This design method is highly
recommended and is followed here in conjunction with the Federal Highway Administration charts
(Reference 22). However, the final decision regarding the appropriate method for sizing culverts is the
responsibility of the design engineer. Other methods may be more appropriate for a given individual
situation.
d.
The permissible height of water at the inlet controls hydraulic design, not vice versa. This should be
stipulated for each site in which ponding is allowed, based on the following risk conditions:
(1) Risk of overtopping the embankment, and attendant risk to human life.
1
(2) Potential damage to the roadway, due to saturation of the embankment.
(3) Traffic interruptions.
(4) Damage to adjacent, upstream and/or downstream property, or to the channel or flood plain
environment.
3
(5) Intolerable outlet velocities, and scour and erosion.
(6) Injurious deposition of bed load, and/or clogging by debris on recession of flow.
(7) Operational requirements of the railroad.
(8) Future repairs to the culvert.
4
4.8.3 FLOW CONDITIONS (1989)
a.
Conventional Culverts considered here are circular and oval pipes and pipe arches, with uniform barrel
cross-section throughout. There are two major types of culvert flow – with inlet control or outlet control.
b.
Inlet Control. Under inlet control, the cross-sectional area of the barrel, the inlet configuration or geometry
and the amount of headwater or ponding are primary importance (Figure 1-4-1).
c.
Outlet Control involves the additional considerations of the tailwater in the outlet channel, and the slope,
roughness and length of barrel (Figure 1-4-2).
4.8.3.1 Hydraulics of Culverts in Inlet Control
a.
Inlet control means that the discharge capacity is controlled at the entrance by the headwater depth, crosssectional area and type of inlet edge. The roughness, length and outlet conditions are not factors in
determining capacity.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-29
Roadway and Ballast
b.
Figure 1-4-1 shows both unsubmerged and submerged projecting entrances.
c.
Headwater depth, HW, shown in Figure 1-4-1 is the vertical distance from the culvert inlet at the entrance
to the energy line of the headwater pool.
d.
Entrance loss, depends upon the geometry of the inlet edge and is expressed as a function of the velocity
head.
e.
Research with models and some prototype testing have resulted in the use of the coefficients listed in
Table 1-4-14 for various types of edge treatment.
NOTE:
Inlet control is one of the two major types of culvert flow. Condition A with
unsubmerged culvert inlet is preferred to the submerged end. Slope, roughness and
length of culvert barrel are of no consideration in inlet control.
Figure 1-4-1. Inlet Control
Table 1-4-14. Entrance Loss Coefficients for Corrugated Metal Pipe or Pipe Arch (Reference 22)
Inlet End of Culvert
Coefficient ke
Projecting from fill (no headwall)
0.9
Headwall or headwall and wingwalls square-edge
0.5
Mitered (beveled) to conform to fill slope
0.7
End-Section conforming to fill slope (Note 1)
0.5
Headwall, rounded edge
0.2
Beveled Ring
0.25
Note 1: End Sections available from manufacturers.
4.8.3.2 Hydraulics of Culverts in Outlet Control
HW = H + ho –LSo – Vl2/2g
EQ 4-1
where:
H = head, ft
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-30
AREMA Manual for Railway Engineering
Culverts
1
NOTE:
Outlet control involves these factors: cross-sectional area of barrel; inlet geometry;
ponding; tailwater; and slope, roughness and length of culvert barrel.
3
Figure 1-4-2. Outlet Control
ho = TW (under conditions shown in Figure 1-4-3 and Figure 1-4-4)
L = Length of culvert, ft
4
So = slope of barrel, ft/ft
Vl = approach velocity, ft/sec
4.8.3.3 Headwater Depth (HW)
The head water depth is the vertical distance from the culvert invert at the entrance (full cross-section) to
the surface of the headwater pool (depth + velocity head). Water surface and energy line at the entrance
are assumed to coincide.
4.8.3.4 Hydraulic Slope
The hydraulic slope or hydraulic grade line, sometimes called the pressure line is defined by the elevations
to which water would rise in small vertical pipes attached to the culvert wall along its length. (Figure 1-42 ) The energy line and the pressure line are parallel over the length of the barrel except in the vicinity of
2
the inlet where the flow contracts and re-expands (Figure 1-4-5 ). The difference is the velocity head, V .
------2g
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-31
Roadway and Ballast
4.8.3.5 Head (H)
The head (Figure 1-4-5) or energy required to pass a given quantity of water through a culvert flowing in outlet
2
V , and entrance loss He, and a friction loss Hf. This
control (with barrel full) is made up of velocity head H v = -----2g
energy is obtained from ponding at entrance and slope of pipe, and is expressed in equation form:
EQ 4-2
H = Hv + He + Hf
4.8.3.6 Entrance Loss (He)
Entrance Loss depends upon the geometry of the inlet edge. This loss is expressed as a coefficient ke multiplied by
the barrel velocity head or
2
V
H e = k e ------2g
EQ 4-3
Figure 1-4-3. Relationship of Headwater to High Tailwater and Other Terms in EQ 4-1
Figure 1-4-4. Low Tailwater in Relation to Terms of the Flow Equation
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-32
AREMA Manual for Railway Engineering
Culverts
Figure 1-4-5. Difference Between Energy Grade Line and Hydraulic Grade Line
1
4.8.3.7 Friction Loss (Hf)
a.
Friction loss is the energy required to overcome the roughness of the culvert barrel and is expressed in the
following equation:
2
2
 29n L  V
H f = ------------------------------------ R 1.33  2g
EQ 4-4
3
where:
n = Manning’s friction factor. See Table 1-4-15 and Table 1-4-16
4
L = length of culvert barrel, ft
V = mean velocity of flow in barrel, ft/sec
g = acceleration of gravity, 32.2, ft/sec2
A
R = hydraulic radius, or ---------- ft
WP
WP = wetted perimeter, ft
b.
Substituting in EQ 4-2 and simplifying (for Bernoulli’s Theorem) we get for full flow:
2
2

n L V
H =  l + k e + 29
--------------------- ------1.33  2g

R
c.
EQ 4-5
Nomographs for solving EQ 4-5 are shown in Reference 22.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-33
Roadway and Ballast
4.8.4 HYDRAULIC COMPUTATIONS (1989)
a.
Following the balanced design approach, establish the minimum opening required to pass the 25-year flood
with no ponding.
b.
From the hydrology data the 25-year discharge has been established. The pipe size to carry this flow with no
head at the entrance, HW/D = 1.0, is determined from the charts. Using the 25-year discharge, determine
the pipe size required for both inlet and outlet control and use whichever is greater. This is the minimum
size opening required in the culvert.
c.
Inlet Control. From Figure 1-4-6 through Figure 1-4-12 the headwater for a given pipe can be determined.
Using the minimum size selected for the 25-year flood, determine the headwater (for the entrance condition
desired) for the 100-year flood discharge. If this amount of headwater is acceptable for the culvert in
question, the minimum size is satisfactory for the full 100-year design discharged in inlet control. If the
headwater is too high, a larger size must be selected corresponding to the maximum permissible headwater.
Now check for possible outlet control, as follows.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-34
AREMA Manual for Railway Engineering
1-4-34
Table 1-4-15. Values of Coefficient of Roughness (n) for Standard Corrugated Metal Pipe (Manning’s Formula) (Reference 1)
Flowing:
Diameters 8 in.
Full Unpaved
Full 25% Paved
Part Full Paved
0.024
0.021
0.027
Flowing:
Pipe Arch
10 in. 12 in. 15 in. 18 in. 24 in. 30 in. 36 in. 42 in. 48 in. 54 in. and Larger
0.012 0.014 0.011 0.012 0.013 0.015 0.017 0.018 0.019 0.020 0.021
0.014 0.016 0.017 0.018 0.020 0.019
0.012 0.013 0.015 0.017 0.019 0.020 0.021 0.022 0.023
17×13 21×15 28×20 35×24 42×29 49×33 57×38 64 × 43 in. and Larger
Full Unpaved
0.026
Part Full Unpaved 0.029
Annular
2-2/3 × 1/2 in.
0.013 0.014 0.016 0.018 0.019 0.020 0.021 0.022
0.018 0.019 0.021 0.023 0.024 0.025 0.025 0.026
Helical – 3 × 1 in.
Flowing:
3 × 1 in
36 in. 42 in. 48 in. 54 in. 60 in. 66 in. 72 in. 78 in. &
larger
Full Unpaved
Full 25% Paved
0.027
0.023
0.022 0.022 0.023 0.023 0.024 0.025 0.026
0.019 0.019 0.020 0.020 0.021 0.022 0.022
Flowing:
Annular
5 × 1 in.
Full Unpaved
Full 25% Paved
0.025
0.022
0.027
0.023
Helical – 5 × 1 in.
48 in. 54 in. 60 in. 66 in. 72 in. 78 in. &
Larger
0.022 0.022 0.023 0.024 0.024
0.019 0.019 0.020 0.021 0.021
0.025
0.022
All pipe with smooth interior* All Diameters 0.012
*Includes full paved pipe, concrete lined pipe and spiral ribbed pipe.
Table 1-4-16. Values of n for Structural Plate Pipe for 6 ″ × 2 ″ Corrugations (Manning’s Formula) (Reference 25)
Corrugations
6″ × 2″
Plain – unpaved
25% Paved
Diameters
5 ft
7 ft
10 ft
15 ft
0.033
0.028
0.032
0.027
0.030
0.026
0.028
0.024
Culverts
AREMA Manual for Railway Engineering
© 2010, American Railway Engineering and Maintenance-of-Way Association
Corrugations
Helical
Annular
2-2/3 × 1/2 1-1/2 × 1/2
in.
in.
Roadway and Ballast
NOTE:
The manufacturers recommended keeping HW/D to a maximum of 1.5 and
preferably to no more than 1.0.
Figure 1-4-6. Inlet Control – Headwater Depths for Corrugated Metal Pipe Culverts
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-36
AREMA Manual for Railway Engineering
Culverts
1
3
4
NOTE:
Headwater depth should be kept low because pipe arches are generally used where
headroom is limited.
Figure 1-4-7. Inlet Control – Headwater Depths for Corrugated Metal Pipe-arch Culverts
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-37
Roadway and Ballast
Figure 1-4-8. Inlet Control – Headwater Depths for Structural Plate Pipe-arch Culverts with
18-inch Radius Corner Plate for Three Types of Inlet (Reference 22)
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-38
AREMA Manual for Railway Engineering
Culverts
1
3
4
Figure 1-4-9. Inlet Control – Headwater Depths for Structural Plate Pipe-arch Culverts with
31-inch Radius Corner Plate for Three Types of Inlet
(Reference 22)
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-39
Roadway and Ballast
Figure 1-4-10. Inlet Control – Headwater Depths for Concrete Pipe Culverts for Three Types of Inlet
(Reference 22)
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-40
AREMA Manual for Railway Engineering
Culverts
1
3
4
Figure 1-4-11. Inlet Control – Headwater Depths for Oval Concrete with
Long Axis Horizontal for Three Types of Inlet
(Reference 22)
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-41
Roadway and Ballast
Figure 1-4-12. Inlet Control – Headwater Depths for Oval Concrete Pipe Culverts with
Long Axis Vertical for Three Types of Inlet
(Reference 22)
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-42
AREMA Manual for Railway Engineering
Culverts
d. Outlet Control. Using the size selected for inlet control use Figure 1-4-13 through Figure 1-4-18 to
determine the headwater depth in outlet control. If the depth here is greater than that for inlet control, the
culvert is assumed to be in outlet control and the higher depth applies.
e.
Wall roughness factors used are stated on the flow charts (Table 1-4-17 through Table 1-4-19). For other
values of n, use an adjusted value for length, L ´, on the length scales on the charts. L ´ is calculated by the
formula:
n 2
L  = L  -----
 n
EQ 4-6
where:
L = Actual length
n´ = Actual value of Manning’s n
n = Value of Manning’s n shown on chart.
f. Using L´ on the length scales in the charts, adjust the result for the Manning’s n desired.
g. The appropriate k curve is selected for the entrance condition desired. Typical values of k are found in
e
e
Table 1-4-14.
h. If the culvert is in outlet control and the headwater exceeds the allowable, a larger size can be selected
corresponding to acceptable headwater depth. In such a case, alternate solutions should be considered for
corrugated steel structures with lower roughness coefficients. See Table 1-4-15. A smaller size of paved pipe
or helical pipe may be satisfactory.
i. Entrance conditions should also be considered. It may be economical to use a more efficient entrance than
planned if a size difference results. Check the lowest ke curve results.
j. For graphed hydraulic elements and properties of circular corrugated steel pipe and corrugated steel and
structural plate pipe-arches refer to Figure 1-4-19 and Figure 1-4-20.
1
3
k. For full-flow data refer to Table 1-4-20 through Table 1-4-23.
l. For a comparison of waterway cross-sectional areas at equal depths of flow in circular pipe and pipe-arch
refer to Figure 1-4-21. Note that the pipe-arch handles a larger volume at the lower levels of
flow.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-43
4
Roadway and Ballast
Figure 1-4-13. Outlet Control – Head for Corrugated Metal Pipe Culvert with Submerged Outlet
and Culvert Flowing Full
(See Note Under Sketch at Top) (Reference 22)
Table 1-4-17. Length Adjustment for Improved Hydraulics
Pipe Diameter
Inches
Roughness Factor
n´
for Helical Corrugations
(Note 1)
12
24
36
48
0.011
0.016
0.019
0.020
Length Adjustment Factor
 2
n

--- n
0.21
0.44
0.61
0.70
Note 1: Other values of roughness, n, are applicable to paved pipe, lined pipe and pipe with 3  1 inch
corrugations. See Table 1-4-15. To use the above chart for these types of pipe and pipe arches, use
adjusted length factors computed per EQ 4-6.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-44
AREMA Manual for Railway Engineering
Culverts
1
3
4
Figure 1-4-14. Outlet Control – Head for Corrugated Metal Pipe-arch Culvert with
Submerged Outlet and Flowing Full
(Reference 22)
(For length adjustment see Table 1-4-17 on Page 1-4-44.)
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-45
Roadway and Ballast
Figure 1-4-15. Outlet Control – Head for Structural Plate Pipe Culvert with
Submerged Outlet and Flowing Full
(Reference 22)
Table 1-4-18. Length Adjustment for Improved Hydraulics
Roughness Factor
Pipe Diameter,
ft
5
7
10
15
Curves Based on
Actual n´ = (Note 1)
n=
0.0328
0.0320
0.0311
0.0302
0.033
0.032
0.030
0.028
Length
Adjustment
Factor
 2
n

--- n
1.0
1.0
0.93
0.86
Note 1: See Table 1-4-15.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-46
AREMA Manual for Railway Engineering
Culverts
1
3
NOTE:
For 31-inch corner radius use structure sizes with equivalent areas on the 18-inch
corner radius scale.
Figure 1-4-16. Outlet Control – Head for Structural Plate Pipe-arch Culvert with 18 -Inch Corner
Radius with Submerged Outlet and Flowing Full
(Reference 22)
Table 1-4-19. Length Adjustments for Improved Hydraulics
Roughness Factor
Pipe Arch
Size, ft
Curves based on n
Actual n´
(Note 1)
6.1 4.6
8.1 5.8
11.4 7.2
16.610.1
0.0327
0.0321
0.0315
0.0306
0.0327
0.032
0.030
0.028
Length Adjustment Factor
 2
n

--- n
1.0
1.0
0.907
0.837
Note 1: See Table 1-4-16.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-47
4
Roadway and Ballast
Figure 1-4-17. Outlet Control – Head for Concrete Pipe Culverts with
Submerged Outlet and Flowing Full
(Reference 22)
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-48
AREMA Manual for Railway Engineering
Culverts
1
3
4
Figure 1-4-18. Outlet Control – Head for Oval Concrete Pipe Culverts with
Long Axis Horizontal or Vertical Submerged Outlet and Flowing Full
(Reference 22)
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-49
Roadway and Ballast
Figure 1-4-19. Hydraulic Elements for Circular Corrugated Steel Pipe
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-50
AREMA Manual for Railway Engineering
Culverts
Table 1-4-20. Full Flow Data for Round Pipe
Diameter,
in.
Area,
ft2
Hydraulic
Radius, ft
Diameter,
in.
Area,
ft2
Hydraulic
Radius, ft
12
0.785
0.250
156
132.7
3.25
15
1.227
0.3125
162
143.1
3.375
18
1.767
0.375
168
153.9
3.5
21
2.405
0.437
174
165.1
3.625
24
3.142
0.50
180
176.7
3.75
30
4.909
0.625
186
188.7
3.875
36
7.069
0.75
192
201.1
4.0
42
9.621
0.875
198
213.8
4.125
48
12.566
1.0
204
227.0
4.25
54
15.904
1.125
210
240.5
4.375
60
19.635
1.25
216
254.5
4.5
66
23.758
1.375
222
268.8
4.625
72
28.27
1.5
228
283.5
4.75
78
33.18
1.625
234
298.6
4.875
84
38.49
1.75
240
314.2
5.0
90
44.18
1.875
246
330.1
5.125
96
50.27
2.0
252
346.4
5.25
108
63.62
2.25
258
363.1
5.375
114
70.88
2.375
264
380.1
5.5
120
78.54
2.5
270
397.6
5.625
126
86.59
2.625
276
415.5
5.75
132
95.03
2.75
282
433.7
5.875
138
103.87
2.875
288
452.4
6.0
144
113.10
3.00
294
471.4
6.125
150
122.7
3.125
300
490.9
6.25
1
3
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-51
Roadway and Ballast
Figure 1-4-20. Hydraulic Properties of Corrugated Steel and Structural Plate Pipe-arches
Table 1-4-21. Full Flow Data for Corrugated Steel Pipe-arches
Corrugations 2-2/3" x 1/2"
Dimensions, in.
Pipe-arch
Waterway
Area,
ft2
Corrugations 3" x 1" and 5" x 1"
Hydraulic
Radius Diameter,
A/D,
in.
ft
Equiv.
Size,
in.
Waterway
Area,
ft2
Hydraulic
Radius
A/D,
ft
Pipe
Diameter
Span
Rise
15
17
13
1.1
0.280
54
60 46
15.6
1.104
18
21
15
1.6
0.340
60
66 51
19.3
1.230
21
24
18
2.2
0.400
66
73 55
23.2
1.343
24
28
20
2.9
0.462
72
81 59
27.4
1.454
30
35
24
4.5
0.573
78
87 63
32.1
1.573
36
42
29
6.5
0.69
84
95 67
37.0
1.683
42
49
33
8.9
0.81
90
103 71
42.4
1.80
48
57
38
11.6
0.924
96
112 75
48.0
1.911
54
64
43
14.7
1.04
102
117 79
54.2
2.031
60
71
47
18.1
1.153
108
128 83
60.5
2.141
66
77
52
21.9
1.268
114
137 87
67.4
2.259
72
83
57
26.0
1.38
120
142 91
745
2.373
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-52
AREMA Manual for Railway Engineering
Culverts
Table 1-4-22. Full Flow Data for Structural Plate Pipe-arches – Corrugations 6 2
Corner Plates 9 pi
Dimensions, ft-in.
Radius (Rc) = 18 in.
Waterway
Area,
ft2
Hydraulic
Radius, ft
Span
Rise
6-1
4-7
22
1.29
6-4
4-9
24
1.35
6-9
4-11
26
1.39
7-0
5-1
28
1.45
7-3
5-3
30
1.51
7-8
5-5
33
1.55
7-11
5-7
35
1.61
8-2
5-9
38
1.67
8-7
5-11
40
1.71
8-10
6-1
43
1.77
9-4
6-3
45
1.81
9-6
6-5
48
1.87
9-9
6-7
51
1.93
10-3
6-9
54
1.97
10-8
6-11
57
2.01
10-11
7-1
60
2.07
11-5
7-3
63
2.11
11-7
7-5
66
2.17
11-10
7-7
70
2.23
12-4
7-9
73
2.26
12-6
7-11
77
2.32
12-8
8-1
81
2.38
12-10
8-4
85
2.44
13-5
8-5
88
2.48
13-11
8-7
91
2.52
14-1
8-9
95
2.57
14-3
8-11
100
2.63
14-10
9-1
103
2.67
15-4
9-3
107
2.71
15-6
9-5
111
2.77
15-8
9-7
116
2.83
15-10
9-10
121
2.89
16-5
9-11
125
2.92
16-7
10-1
130
2.98
1
3
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-53
Roadway and Ballast
Table 1-4-23. Full Flow Data for Corrugated Steel Pipe-arches – Corrugations 6 2
Corner Plates 15 pi
Radius (Rc) = 31 in.
Rise, ft-in.
Area, ft2
Hydraulic
Radius, ft
13-3
9-4
97
2.68
13-6
9-6
102
2.74
14-0
9-8
105
2.78
14-2
9-10
109
2.83
Span, ft-in.
14-5
10-0
114
2.90
14-11
10-2
118
2.94
15-4
10-4
123
2.98
15-7
10-6
127
3.04
15-10
10-8
132
3.10
16-3
10-10
137
3.14
16-6
11-0
142
3.20
17-0
11-2
146
3.24
17-2
11-4
151
3.30
17-5
11-6
157
3.36
17-11
11-8
161
3.40
18-1
11-10
167
3.45
18-7
12-0
172
3.50
18-9
12-2
177
3.56
19-3
12-4
182
3.59
19-6
12-6
188
3.65
19-8
12-8
194
3.71
19-11
12-10
200
3.77
20-5
13-0
205
3.81
20-7
13-2
211
3.87
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-54
AREMA Manual for Railway Engineering
Culverts
1
NOTE:
The pipe arch handles a larger volume at the lower levels of flow.
3
Figure 1-4-21. Comparison of Waterway Cross-sectional Areas at Equal Depths of Flow in
Circular Pipe and Pipe-arch
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-55
Roadway and Ballast
SECTION 4.9 DESIGN CRITERIA FOR CORRUGATED METAL PIPES
4.9.1 CRITERIA (1994)
Four criteria must be considered in the structure design of a flexible buried conduit. The criteria are seam
strength, flexibility factor, wall area and buckling.
4.9.2 FORMULAS (1994)
4.9.2.1 Seam Strength
a.
Seam strength shall be sufficient to develop the compressive thrust in the pipe wall. This compressive thrust
(T) in lb per lineal foot of structure is:
S
T =  LL + DL  --2
EQ 4-7
EQ 4-8
C = T(S.F.) = Compressive thrust with safety factor
where:
LL = Design Live Load (psf) (See Article 4.9.3.b)
DL = Dead Load (psf) (See Article 4.9.3.a)
S = Span (ft) (Max dia of pipe)
SF = Safety Factor. Recommend SF = 3
b.
The value for C should not exceed values shown in Article 4.9.4c, Table 1-4-27.
4.9.2.2 Handling and Installation Strength
a.
Handling and installation rigidity is measured by a Flexibility Factor (F.F.) determined by the formula:
FF = S2/EI
EQ 4-9
where:
FF = Flexibility Factor in inches per pound.
S = Max. span in inches
E = Modulus of elasticity of the pipe material (psi) (See Table 1-4-26)
I = Moment of inertia per unit length of cross section of the pipe (inches to 4th power per inch)
(See Table 1-4-28)
b.
FF shall not exceed 0.043 for 2inch depth corrugation; 0.033 for 1 inch depth corrugation.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-56
AREMA Manual for Railway Engineering
Culverts
4.9.2.3 Wall Area
Formula for wall area is:
T
A = ---fa
EQ 4-10
where:
A = Required wall area (in.2/ft) (See Table 1-4-28)
T = Thrust (lb/ft) (See Article 4.9.2.1)
fa = Allowable wall stress = minimum yield point divided by an appropriate safety factor;
fy
f a = ------EQ 4-11
SF
fy = Minimum yield point (psi – see Article 4.9.4b, Table 1-4-26)
4.9.2.4 Buckling
Corrugations with the required wall area, A, shall be checked for possible buckling. If the allowable buckling stress
fcr/SF, is less than fa, the required area must be recalculated using fcr/SF in lieu of fa. Formulae for buckling are:
f 2
r 24E
u  KS 2
if S < ---- ----------- then f cr = f u – ---------- -------48E  r 
K fu
r
if S > ---K
24E
12E
----------- then f cr = -----------------fu
 KS
- 2
 ------r 
1
EQ 4-12
EQ 4-13
3
where:
fcr = critical buckling stress (psi)
S = max, span in inches
4
r = Radius of gyration in inches (See Table 1-4-28)
E = Modulus of elasticity (psi) (See Article 4.9.4b) Table 1-4-26
K = Soil stiffness factor (See below)
SF = Safety factor (Recommend SF = 2)
fu = Minimum tensile strength (psi) (See Article 4.9.4.b) (See Table 1-4-26)
Soil stiffness factor = 0.22 for 95% compaction
0.33 for 90% compaction
0.44 for 85% compaction
4.9.3 LOADS (1994)
a.
Dead load = 120 lb per cubic foot  height of cover in feet.
b.
Live loads, including 50% impact, for Cooper E-80 as shown in Table 1-4-24.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-57
Roadway and Ballast
Table 1-4-24. Live Loads for Cooper E-80
Height of
cover (ft)
Live Load
lb/sq ft
Height of
Cover (ft)
Live Load
lb/sq ft
2
3800
12
800
5
2400
15
600
8
1600
20
300
10
1100
30
100
4.9.4 PIPE CULVERT DESIGN PROPERTIES (1989)
a.
Gage vs metal thickness in inches to be used in design of pipe culverts are shown in Table 1-4-25.
b.
Mechanical properties of metal to be used in design of pipe culverts are shown in Table 1-4-26.
c.
Seam strength of riveted pipe culverts are shown in Table 1-4-27.
d.
Section properties of corrugated metals are shown in Table 1-4-28.
Table 1-4-25. Gage vs Metal Thickness
Steel
Aluminum
Specified Thickness
Specified Thickness
16
0.064
0.060
14
0.079
0.075
12
0.109
0.105
10
0.138
0.135
8
0.168
0.164
Gage
Table 1-4-26. Metal Mechanical Properties
Minimum Tensile
Strength (psi)
Minimum Yield
Point (psi)
Mod of
Elasticity psi
Steel
45000
33000
29106
Aluminum
31000
24000
10106
Metal
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-58
AREMA Manual for Railway Engineering
Culverts
Table 1-4-27. Minimum Longitudinal Seam Strength in Kips per Foot
Corrugation
2-2/3 x 1/2 and 2 x 1/2
Gage
Single Rivet
k/ft
Double Rivet
k/ft
3x1
6x1
Double Rivet
k/ft
Double Rivet
k/ft
Riveted Steel Pipe
16
16.7
21.6
28.7
–
14
18.2
29.8
35.7
–
12
23.4
46.8
53.0
–
10
24.5
49.0
63.7
–
8
25.6
51.3
70.7
–
Riveted Aluminum Pipe
16
9.0
14.0
16.5
16.0
14
9.0
18.0
20.5
19.9
12
15.6
31.5
28.0
27.9
10
16.2
33.0
42.0
35.9
8
16.8
34.0
54.5
43.5
1
Table 1-4-28. Steel and Aluminum Corrugated Pipes
Corrugation
2-2/31/2
A
r
I 10–3
A
r
I 10–3
A
r
I 10–3
in 2
--------ft
in.
in 4
--------ft
in 2
--------ft
in.
in 4
--------ft
in 2
--------ft
in.
in 4
--------ft
16
0.755
.1712
1.89
0.890
.3417
8.66
0.794
.3657
8.85
14
0.968
.1721
2.39
1.113
.3427
10.89
0.992
.3663
11.09
12
1.356
.1741
3.43
1.560
.3448
15.46
1.390
.3677
15.65
10
1.744
.1766
4.53
2.008
.3472
20.18
1.788
.3693
20.32
8
2.133
.1795
5.73
2.458
.3499
25.09
2.186
.3711
25.09
Gage
3
5  1 (Note 1)
31
4
Note 1: Not applicable for aluminum corrugated pipes
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-59
Roadway and Ballast
4.9.5 MINIMUM AND MAXIMUM HEIGHT OF COVER IN FEET (1989)
Minimum and maximum height of cover for various thickness (gage) of metal are given in Table 1-4-29 for Steel
Round Pipe and in Table 1-4-30 for Aluminum Round Pipe. The design criteria used in development of Table 1-429 and Table 1-4-30 are as follows:
4.9.5.1 Safety Factors
SF = 3.0 for longitudinal seams
SF = 2.0 for pipe wall buckling
SF = 2.0 for wall area
FF = 0.043 for 2 depth corrugation and 0.033 for 1 depth corrugation.
4.9.5.2 Design Factors
• Dead load pressure = 120 psf per foot of height.
• Live load pressure = As shown in Table 1-4-24 for Cooper E-80 Live Load plus 50% of the live load for
impact.
• Seam strengths, modulus of elasticity, tensile strength.
• Yield point, etc., used are as shown in Tables.
• Soil stiffness coefficient “K” = 0.33 for 90% compaction based on ASTM D698.
• These tables are based on structural considerations. Abrasive or corrosive conditions at the site may
require a greater sheet thickness or protective coating and invert paving.
• Maximum height of cover may be controlled by maximum head water depth.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-60
AREMA Manual for Railway Engineering
Culverts
Table 1-4-29. Steel Round Corrugated Pipe
Minimum and Maximum Height of Cover in Feet
Sheet Thickness
Pipe
Dia. Ins.
(Inch and Gage)
2-2/3 x 1/2 and 2 x 1/2 in. Corrugation
0.064
16 ga
0.079
14 ga
0.109
12 ga
12
1-1/2-90 1-1/2-100
15
1-1/2-70 1-1/2-80
18
1-1/2-60 1-1/2-65 1-1/2-85
21
1-1/2-50 1-1/2-55 1-1/2-70
24
1-1/2-45 1-1/2-50 1-1/2-65
30
2-35
36
3-30
42
2-30
48
3-30
0.138
10 ga
0.168
8 ga
5 x 1 or 3 x 1 in. Corrugation
0.064
16 ga
0.079
14 ga
0.109
12 ga
0.138
10 ga
0.068
8 ga
1-1/2-40 1-1/2-50
2-30
1-1/2-40 1-1/2-45
1-1/2-45 1-1/2-70 1-1/2-73 1-1/2-80
2-40
2-65
2-65
2-70
2-35
2-55
2-60
2-60
2-35
2-50
2-50
2-55
3-30
2-35
2-55
2-70
2-75
66
2-45
2-50
3-25
2-35
2-50
2-60
2-70
72
2-45
2-45
4-25
3-30
2-45
2-55
2-65
2-40
6-20
3-30
2-45
2-50
2-60
7-20
4-25
2-40
2-50
2-55
90
4-25
2-35
2-45
2-50
96
7-20
2-35
2-40
2-45
102
7-20
3-30
3-40
3-45
108
3-30
3-35
3-40
114
3-30
3-35
3-40
120
3-25
3-35
3-35
54
60
78
84
1-1/2-40 1-1/2-45 1-1/2-70 1-1/2-85 1-1/2-95
1-1/2-40 1-1/2-65 1-1/2-75 1-1/2-85
Note 1: All 42 inches in diameter and larger and all 1 inches depth corrugation shall be double riveted or
equal.
Note 2: Height of cover is measured from base of cross tie to top of pipe.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-61
1
3
4
Roadway and Ballast
Table 1-4-30. Aluminum Round Corrugated Pipe
Minimum and Maximum Height of Cover in Feet
Sheet Thickness and Gage
Pipe
Diameter
Ins.
2-2/3 x 1/2 and 2 x 1/2 in. Corrugation
0.060
16 ga
0.075
14 ga
12
1-1/2-50 1-1/2-50
15
1-1/2-40 1-1/2-40
0.105
12 ga
0.135
10 ga
18
3-30
3-30
1-1/2-55
21
4-25
4-25
1-1/2-45
24
5-25
5-25
1-1/2-40 1-1/2-45
0.164
8 ga
3 x 1 in. Corrugation
0.060
16 ga
30
2-30
2-35
36
3-25
3-30
3-30
42
1-1/2-50
5-25
48
1-1/2-40 1-1/2-45
0.075
14 ga
0.105
12 ga
0.135
10 ga
1-1/2-35 1-1/2-50 1-1/2-75
3-30
0.164
8 ga
1-1/2100
1-1/2-40 1-1/2-65 1-1/2-85
4-25
2-35
2-55
2-75
5-25
2-30
2-50
2-65
60
3-30
2-45
2-60
66
4-25
2-40
2-55
72
2-35
2-50
78
2-35
2-45
54
84
3-40
90
3-40
Note 1: All 42 inches and larger and all 1 inches depth corrugation shall be double riveted or equal.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-62
AREMA Manual for Railway Engineering
Culverts
4.9.6 PIPE ARCHES (1989)
4.9.6.1 Calculations
Pipe arches are structurally calculated by same method as standard round pipe, but the maximum soil bearing
pressures at the small radius corners must be considered. The design must state the type of backfill materials
required around the small radius corners.
4.9.6.2 Corner Pressures Formula
Pc = PvRt/Rc
EQ 4-14
where:
Pc = Pressure acting on soil at small radius corners (lb/ft2)
Pv = Design Pressure (lb/ft2)
Rt = Radius at crown (ft)
Rc = Radius at corner or small radius (ft)
Some typical allowable bearing pressures for various backfill materials are given in Table 1-4-31. The values of
allowable bearing pressures of backfill material shown in Table 1-4-31 are for preliminary design purposes only,
and allowable bearing pressure of actual used backfill material should be tested to ensure it is equal to the design
pressure.
1
Table 1-4-31. Typical Allowable Bearing Pressures
(See Note 1)
Class of Material
Allowable Design
Bearing Pressure
Concrete (3 sacks per cu, yd)
25
TSF (Note 2)
Cement treated sand and gravel
20
TSF (Note 2)
Compacted gravel or sand and gravel
6
TSF (Note 2)
Loose gravel or compacted coarse sand
4
TSF (Note 2)
Loose coarse sand or gravel and sand
3
TSF (Note 2)
Loose fine sand
2
TSF (Note 2)
Medium stiff clay
22
TSF (Note 2)
Medium soft clay
12
TSF (Note 2)
Silt and very fine sand
2
TSF (Note 2)
Swamp material (muck, peat, etc.)
0
TSF (Note 2)
3
4
Note 1: To be used only for design purpose (See Article 4.9.6.2)
Note 2: Tons per square foot
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-63
Roadway and Ballast
4.9.6.3 Minimum and Maximum Height of Cover for Arch Pipes
Minimum height of cover for 2-2/31/2, 51 or 31 corrugation shall not be less than 2 feet nor less than the
span. Maximum height of cover shall not be greater than 30 feet (Height of cover is measured from base of cross-tie
to top of arch pipe) (Table 1-4-32).
Table 1-4-32. Steel and Aluminum Arch Pipes
Minimum Thickness of Metal (Gage)
Minimum Thickness of Metal (Gage)
Equiv.
Pipe
Diameter
Inches
Span
Rise
(Inches)
15
17 13
0.079 (14 ga)
0.135 (10 ga)
18
21 15
0.079 (14 ga)
0.135 (10 ga)
21
24 18
0.079 (14 ga)
0.135 (10 ga)
24
28 20
0.079 (14 ga)
0.135 (10 ga)
30
35 24
0.109 (14 ga)
0.135 (10 ga)
36
42 29
0.138 (10 ga)
0.164 (8 ga)
42
49 33
48
2-2/3 x 1/2 in. Corrugation
Steel
Aluminum
5 x 1 or 3 x 1 in. Corrugation
Steel
Aluminum
0.064 (16 ga)
0.105 (12 ga)
0.109 (12 ga)
0.064 (16 ga)
0.105 (12 ga)
57 37
0.138 (10 ga)
0.079 (14 ga)
0.135 (10 ga)
54
64 43
0.138 (10 ga)
0.079 (14 ga)
0.135 (10 ga)
60
71 47
0.138 (10 ga)
0.109 (12 ga)
0.135 (10 ga)
66
77 52
0.138 (10 ga)
0.109 (12 ga)
0.135 (10 ga)
72
81 59
0.109 (12 ga)
0.135 (10 ga)
78
87 63
0.109 (12 ga)
0.164 (8 ga)
84
95 67
0.109 (12 ga)
90
103 71
0.109 (12 ga)
96
112 75
0.138 (10 ga)
102
117 79
0.138 (10 ga)
108
128 83
0.168 (8 ga)
114
13787
0.168 (8 ga)
Note 1: Arch pipes 42 and larger and all 1 depth corrugation shall be double riveted or equal.
Note 2: Soil bearing pressures at corners must be determined. See Article 4.9.6.2
Note 3: In weak bearing soils, a larger diameter round pipe may be required and partly buried
to obtain minimum cover, but the same rise and area of the proposed pipe arch should
be maintained. Another method is to replace the weak bearing soils with a high
bearing value material for a distance great enough so that the high corner pressures
no longer has an adverse effect. (See Article 4.9.6.2 for requirements).
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-64
AREMA Manual for Railway Engineering
Culverts
SECTION 4.10 DESIGN CRITERIA FOR STRUCTURAL PLATE PIPES
4.10.1 CRITERIA FORMULAS (1989)
a.
Four criteria shall be considered in the design of structural plate pipe culverts, which are the same as stated
in Article 4.9.1.
b.
Formulas given under Article 4.9.2 shall be used in the design of structural plate culvert pipes. Table 1-4-24
and Table 1-4-26 may be used, but all other properties needed for solving the formulas are furnished in
Table 1-4-33 and Table 1-4-34.
c.
Recommended safety factors are given for each formula under Article 4.9.2, except that flexibility factor
shall not exceed 0.02 for round pipe, 0.03 for arch pipes and 0.03 for arches.
4.10.2 SEAM STRENGTH OF STRUCTURAL PLATE PIPES (1989)
Minimum longitudinal seam strength in kips per foot are shown in Table 1-4-33 and section properties in
Table 1-4-34.
Table 1-4-33. Steel and Aluminum Structural Plate Pipes in Kips per Foot
all Bolts to be 3/4 inch in Size
Thickness
Gage
12
10
8
7
5
3
1
Steel
Inches
Aluminum
Inches
4
0.109
0.138
0.168
0.188
0.218
0.249
0.280
0.10
0.125
0.15
0.175
0.20
0.225
0.250
43
62
81
93
112
132
144
62 Steel
92-1/2 Aluminum
Bolts Per Foot
Steel Bolts
Aluminum Bolts
5-1/3 Per Foot 5-1/3 Per Foot
6
180
8
28.
41.
54.1
63.7
73.4
83.2
93.1
194
26.4
34.8
44.4
52.8
52.8
52.8
52.8
3
4
Table 1-4-34. Steel and Aluminum Structural Plate Pipes Section Properties
62 Steel
92-1/2Aluminum
Gage
A
(inch2/ft)
r
(inch)
I 10–3
inch4/inch
A
inch2/foot
r
inch
I 10–3
inch4/inch
12
10
8
7
5
3
1
1.556
2.003
2.449
2.739
3.199
3.650
4.119
0.682
0.684
0.686
0.688
0.690
0.692
0.695
60.411
78.175
96.163
108.000
126.922
146.172
165.836
1.404
1.750
2.100
2.449
2.799
3.149
3.501
0.8438
0.8444
0.8449
0.8454
0.8460
0.8469
0.8473
83.065
103.991
124.883
145.895
166.959
188.179
209.434
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1
1-4-65
Roadway and Ballast
4.10.3 MINIMUM AND MAXIMUM HEIGHT OF COVER IN FEET (1989)
a.
Minimum and maximum height of cover measured from base of ties to top of pipe for various thickness
(gage) of metal are given in Table 1-4-35 for steel and Table 1-4-36 for aluminum structural plate pipes
using steel bolts and Table 1-4-37 using aluminum bolts. Minimum height of cover shall not be less than 2
feet nor less than one fourth the maximum span. Greater cover for protection from heavy equipment may be
needed during construction.
b.
Safety Factors used in Table 1-4-35, Table 1-4-36 and Table 1-4-37 are as follows:
Longitudinal Seams. . . . . . . . . . . . . . . . . . . 3
Wall Buckling. . . . . . . . . . . . . . . . . . . . . . . . 2
Wall Area . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
Flexibility Factor . . . . . . . . . . . . . . . . . . . . . 0.02
Dead Load Pressure . . . . . . . . . . . . . . . . . . 120 psf of height
Live Load E-80 plus 50% for impact. . . . . .
Soil Stiffness Coefficient “K” . . . . . . . . . . . = 0.33 for 90% compaction base on ASTM D-698
c.
The tables are based on structural considerations. Abrasive or corrosive conditions at the site may require a
greater thickness in the bottom plates.
Table 1-4-35. Steel Round Structural Plate Pipe Minimum and Maximum Height of Cover (ft)
4 Bolts per Foot
Span
(ft)
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
6 Bolts/ft 8 Bolts/ft
Plate Thickness inches and gage
0.109
12 ga
0.138
10 ga
0.168
8 ga
0.188
7 ga
0.218
5 ga
0.243
3 ga
0.280
1 ga
0.280
1 ga
0.280
1 ga
3-30
4-25
6-20
2-40
3-35
3-30
3-30
4-25
2-55
3-50
3-45
3-40
3-35
2-60
3-55
3-50
3-45
3-40
2-75
3-65
3-60
3-55
3-50
2-90
3-80
3-70
3-65
3-60
2-100
3-85
3-80
3-70
3-65
2-125
3-110
3-100
3-90
3-80
2-130
3-120
3-105
3-95
3-90
4-25
6-20
7-20
8-20
4-30
4-30
4-30
4-25
5-25
4-40
4-35
4-30
4-30
5-30
5-25
4-45
4-40
4-40
4-35
5-35
5-30
4-55
4-50
4-45
4-45
5-40
5-40
5-35
5-35
6-30
4-60
4-55
4-50
4-50
5-45
5-40
5-40
5-40
6-35
6-30
4-75
4-70
4-65
4-60
5-55
5-45
5-45
5-40
6-35
6-30
6-30
6-30
6-20
4-80
4-75
4-70
4-65
5-60
5-45
5-45
5-40
6-35
6-30
6-30
6-30
6-20
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-66
AREMA Manual for Railway Engineering
Culverts
Table 1-4-36. Aluminum Round Structural Plate Pipe Minimum and Maximum Height of Cover (ft)
Steel Bolts
5-1/3 Bolts Per Foot
Span
(ft)
Plate Thickness and Gage
0.100
12 ga
0.125
10 ga
0.150
8 ga
0.175
7 ga
0.200
5 ga
0.225
3 ga
0.250
1 ga
6
6-25
3-35
2-50
2-55
2-65
2-75
2-85
7
8-20
3-30
2-40
2-50
2-55
2-65
2-70
8
4-25
2-35
2-40
2-50
2-55
2-60
9
5-25
3-30
3-35
3-45
3-50
3-55
10
7-20
3-30
3-35
3-35
3-45
3-50
11
4-25
3-30
3-35
3-40
3-45
12
5-25
3-25
3-30
3-35
3-40
13
7-20
4-25
4-30
4-35
4-40
5-25
4-25
4-30
4-35
4-25
4-30
4-30
4-25
4-30
14
15
16
17
1
5-30
Table 1-4-37. Aluminum Round Structural Plate Pipe Minimum and Maximum Height of Cover (ft)
Span
(ft)
Aluminum Bolts
5-1/3 bolts per foot
Plate thickness and gage (Note 1)
0.100
12 ga
0.125
10 ga
0.150
8 ga
0.175
7 ga
6
6-20
3-30
2-40
2-45
7
8-20
4-25
2-35
2-40
8
4-20
2-30
2-35
9
8-20
4-25
3-30
10
6-20
3-25
11
7-20
4-25
12
6-20
13
7-20
14
9-20
15
10-15
3
4
Note 1: Gages 5, 3 and 1 have same strength as gage
7 since bolts control.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-67
Roadway and Ballast
SECTION 4.11 CULVERT END TREATMENTS
4.11.1 INTRODUCTION (1992)
a.
The design and installation of each culvert should be considered as an individual engineering and economic
problem. The engineer should determine the basic requirements of type strength, capacity, service, location,
alignment, grade, and other factors pertinent to the efficient function and economic installation and
maintenance of the culvert.
b.
In addition, he should decide if the physical conditions, both present and during the projected life of the
culvert, warrant the inclusion of headwalls, wingwalls, inverts, and aprons as part of the installation.
c.
Occasionally, aesthetic considerations may require the use of these appurtenances within built-up
communities or in prominent locations where a pleasing appearance is necessary, but normally this is not a
major consideration. In most cases it is more expedient to use other and less expensive methods to avoid all
or part of these end finishes. For example, except where limited right-of-way makes it necessary to provide
headwalls and wingwalls, it is usually more economical to extend pipe culverts. Box and arch culverts,
especially when of large capacity, present a somewhat different problem. Again, however, the cost of
installation should be carefully compared with other solutions, such as grouted rip-rap, sheet piling, etc.,
which might provide adequate protection at less cost.
4.11.2 HEADWALLS (1989)
4.11.2.1 Factors and Conditions
The following factors and conditions may require the use of headwalls:
a.
Angle of shearing resistance, type, height, and stability of fill material.
b.
Inability to hold good vegetation on slopes.
c.
Prevention of washouts.
d.
Reduction in cost of culvert by shortening installations.
e.
Right-of-way limitations.
f.
Longitudinal stability for short pipe sections to prevent pulling apart. (Only where adequate foundation is
available.)
g.
Improvement of appearance.
h. Prevention of undercutting, scour, burrowing and seepage.
i.
Increase hydraulic efficiency.
4.11.2.2 Design
a.
Headwalls should be designed by the engineering department, usually the bridge engineers office, and
standard design procedures should be followed.
b.
Economic considerations, based primarily on the required height of the headwall, will determine whether a
gravity or reinforced concrete type of structure should be used. The design should provide for all loads,
including surcharge and impact, and particular attention should be given to the method used to determine
earth thrust. It is very important that the actual soil conditions closely approximate the theoretical
conditions assumed in the design. If not, only design methods which through past experience are known to
give satisfactory results should be used.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-68
AREMA Manual for Railway Engineering
Culverts
c.
The headwall should have adequate integral strength, and should be proportioned to prevent sliding or
overturning from excessive soil pressures. It should be self supporting, and every effort should be made to
design against settling. In the case of pipe culverts, this point cannot be overemphasized, as the
effectiveness of a carefully located and bedded pipe can be nullified by the settling of an inadequately
supported headwall.
d.
Cut-off walls, where required, should be of sufficient depth to eliminate undercutting.
4.11.3 WINGWALLS (1995)
4.11.3.1 Factors and Conditions
The following factors and conditions may require the use of wingwalls:
a.
Angle of shearing resistance, type, height and stability of fill material.
b.
Height of culvert.
c.
Direction, width and gradient of stream channel.
d.
Amount and velocity of runoff.
e.
Need for increased hydraulic efficiency.
f.
Prevention of scour during periods of maximum runoff.
1
4.11.3.2 Design
a.
Structurally, the same principles govern the design of wingwalls as for headwalls.
b.
Gravity-type construction is economically desirable for walls of limited height. The walls should be self
supporting, and a well reinforced apron, where required, would achieve the desired result. Footing to meet
the most adverse conditions encountered should be used, and should be proportioned to provide uniform
bearing pressure over the full length of the wingwall. This will assist in preventing separation between the
body of the culvert and the wings.
c.
Perpendicular, oblique, or parallel wingwalls, or a combination thereof, should be used, depending on the
physical and hydraulic conditions involved. Careful field engineering is necessary to ascertain that the
wingwalls, if skewed, will not change stream direction or encourage turbulence during periods of heavy
runoff.
d.
The height of the culvert and incidence of high water will, to a great extent, govern the length of the wings.
Oblique walls are usually tapered from the top of the headwall to a height of approximately 2 feet. Parallel
walls may taper their full length to the footing.
4.11.4 INVERTS AND APRONS (1995)
4.11.4.1 Factors and Conditions
The following factors and conditions may require the installation of inverts and aprons:
a.
Prevention of erosion and scour; dispersion of flow.
b.
Resistance to corrosive and abrasive materials carried by a stream.
c.
Increased hydraulic efficiency.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-69
3
4
Roadway and Ballast
d.
Use of culvert as cattle underpass or other purpose, in addition to drainage.
4.11.4.2 Design
a.
Inverts and aprons should be carefully designed and reinforced, and should be built to carry and control the
hydraulic bedload.
b.
Aprons should be long enough to carry the water well past the toe line at embankments, and should be so
designed as to avoid turbulence and eddies. Cut-off walls should be used to prevent undercutting, where
necessary.
c.
Inverts and aprons of culverts handling abrasive and corrosive waters require special care. Those carrying
large quantities of abrasive material can be readily protected by properly designed and bonded paving. Mine
water, however, particularly from coal, copper and zinc mines, attacks concrete. Water passing through
sulfur-bearing rocks or soils and alkaline water have a similar deteriorating effect. Asphaltic or other
nonmetallic paving should be considered where corrosive rather than abrasive attack is the governing
factor.
d.
Paving of inverts of culverts to be used as a cattle underpass should be designed to provide reasonably
secure footing. Brushed concrete provides an excellent invert if the slope is not excessive. Where this
condition exists, cleats may be formed in the concrete to provide additional footing. Bituminous material
may also be used as a paving, although small sharp-hoofed livestock will soon cut this type of paving badly,
and cause it to deteriorate quickly.
SECTION 4.12 ASSEMBLY AND INSTALLATION OF PIPE CULVERTS
4.12.1 GENERAL (1995)
a.
This portion of the specification presents information pertaining to installation of pipe culverts including
alignment; construction methods and procedures; preparation of foundation; unloading and assembly;
placement and compaction of backfill; end treatment; and safety provisions.
b.
This information is not intended to be all inclusive. The user should be aware that pipe manufacturers
provide installation instructions pertaining to their individual products. Additionally, industry standards, as
well as national specifications, are available to assist the user in proper installation of pipe culverts.
Available references for pipe culvert installation are found at the end of this chapter. Also, the reader is
referred to Chapter 8, Concrete Structures and Foundations, Part 10, Reinforced Concrete Culvert Pipe,
Section 10.4, Installation for further information on the proper installation of concrete culvert pipe.
4.12.2 ALIGNMENT (1995)
a.
It is important to properly locate the culvert in order to provide the stream with as direct an entrance and
exit configuration as possible. Inlet and outlet orientation can be improved by means of a channel change or
skewed alignment or a combination of both, Elbows, typically less than 45 degrees, can be installed in the
culvert to facilitate alignment changes. However, such alignment changes must be approved by appropriate
governing agencies and the railroad Chief Engineer.
b.
Proper culvert alignment also involves attention to grade line. Culvert grade is essential to the effective and
safe functioning of the structure. The ideal grade for a culvert is one which results in neither silting nor in
excessive velocities and scour. Culvert line and grade is to be established by the project engineer.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-70
AREMA Manual for Railway Engineering
Culverts
4.12.3 CONSTRUCTION METHODS (1995)
a.
Pipe culvert installation may be by open embankment construction, trench excavation, tunneling, jacking,
or a combination of such methods, depending upon site conditions and requirements.
b.
Trench construction, if done improperly, can be one of the most dangerous situations in construction. In situ
soil strength and groundwater elevation must be considered. Consult a qualified geotechnical engineer for
design of excavation supports as required. The pipe contractor or railway must strictly conform to all
Federal, State and Local regulations and, in particular, the requirements of the Occupational Safety and
Health Administration (OSHA).
c.
Refer to Section 4.13, Earth Boring and Jacking Culvert Pipe through Fills for information on earth
boring and jacking culvert pipe.
4.12.4 PREPARATION OF FOUNDATION (1995)
a.
Pressures caused by both live and dead loads are transmitted from the pipe culvert to the sidefill
embankments and the strata underlying the pipe. The supporting soil under the embankments and the pipe
must provide required support without excessive settlement. Precautions for soft foundations and for rock
strata must be considered if applicable.
b.
Where the underlying foundation material is unsuitable, this material must be removed and replaced with
suitable bedding material placed and compacted to provide a continuous foundation that uniformly supports
both the culvert pipe and the sidefill embankments.
c.
If rock layers are encountered at design culvert invert grade, this rock must be excavated underneath the
pipe culvert and replaced with suitable compacted bedding material. The depth of over-excavation required
will be dependent upon culvert size and height of cover. However, generally a depth of 12 inches – 24 inches
is sufficient.
1
4.12.5 HANDLING AND UNLOADING (1995)
a.
Pipe shall be shipped and handled in such a manner as to prevent damage to the pipe or to the pipe coating.
Pipes shall not be dropped or dragged over the ground. Pipes shall be handled by slings, forks, etc., as
required by pipe weight and site conditions. Safety of workers is of paramount importance in all handling
operations. Consult with pipe manufacturer regarding specific handling and lifting precautions and
requirements. Rough handling is to be avoided. Any damage to coated pipes shall be repaired with an
approved field repair method prior to installation.
3
b.
Pipe culvert materials must be properly stored if extended time will elapse prior to installation. Pipe
coatings or pipe materials affected by UV rays or temperature extremes should be stored under a protective
shelter until they can be properly installed. In the case of structural plate culverts, plates should be stored
in a manner where moisture will drain rather than collect in the plates. Protected storage is preferred.
Stacking plates to provide proper drainage and ventilation helps prevent storage stains.
4
4.12.6 ASSEMBLY (1995)
a.
Proper assembly of pipe culverts will be dependent upon a number of factors, including the type of culvert
pipe material; whether the pipe is factory pipe or field-bolted structural plate pipe; the type of pipe joints;
site conditions; etc.
b.
Joints for pipe culverts can be especially critical depending upon the soil type and conditions, slope of the
culvert, infiltration and exfiltration requirements, etc. Field joints must meet the performance criteria
established by the project specifications.
c.
It is not the intention of this text to address the specifics of assembly for all pipe culvert products. Rather,
the culvert pipe manufacturers should provide assembly instructions for their products. In addition, the
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-71
Roadway and Ballast
reader is referred to the Reference 1, 30, 38, 47, 50, 51 and 52 at the end of this chapter for more detailed
information regarding assembly of culvert pipe.
4.12.7 BACKFILL (1995)
a.
Proper backfill material selection, placement and compaction is essential to the satisfactory performance of
pipe culverts. Railroad and highway engineering departments should have established criteria for
construction of fill embankments. While such fill requirements may be adequate for pipe culvert
installations in general, specific requirements may vary depending on pipe culvert material, size and shape;
fill heights and in situ conditions.
b.
Generally, the selected culvert backfill material should be a well graded granular material, although
cohesive materials can be used if careful attention is given to compaction and optimum moisture content.
Use of excavated, on site material may be possible provided this material possesses the required engineering
properties. The selected fill material must be free from large clods, frozen lumps, rocks, debris and organic
material. Extremely fine granular fill may not be suitable due to the possibility of infiltration and piping
action. However, use of a filter fabric separator between fill materials of dissimilar size may solve this
problem.
c.
Special care must be taken to provide proper bedding and haunch support for the pipe. See Figure 1-4-22. A
relatively loose layer of bedding (generally several inches thick) should be placed under the pipe. However,
the fill in the haunch areas is to be carefully compacted to provide support in these critical areas. This is
especially important for pipe-arch shapes.
d.
The selected backfill material should be placed in layers not exceeding 6 inches to 8 inches thickness and
compacted to specified density at or near optimum moisture content. Care must be taken to maintain
balanced loading on the pipe culvert by keeping the fill level approximately equal on both sides of the pipe at
all times. Generally, a compaction density conforming to 90% of ASTM D698 (Standard Proctor) should be
adequate. However, individual project specifications will control.
e.
Flowable fill material such as cement slurry and other controlled low strength materials (CLSM) may be
used if economically justifiable. Care must be taken to maintain balanced loading and pressure on the
culvert pipe and prevent flotation of the pipe.
f.
The width of the select fill envelope will be dependent upon site conditions. In narrow trench installation
conditions, the select fill must fill the trench from the culvert pipe to the trench wall. Trench width will
normally be controlled by the width necessary to install connecting bands or to assemble plates as well as by
the width necessary to permit proper placement and compaction of the backfill. Generally a distance of 2
diameter to 1 diameter each side of the pipe is adequate for embankment installations. However, the project
engineer must make this determination, taking into account pipe size and shape, height of cover and live
load pressures, and in situ soil parameters.
g.
The select backfill material is to be placed and compacted to a point where minimum cover height above the
pipe for anticipated live loads is reached. The remainder of the fill can be standard embankment (or trench)
fill meeting the specifications for the given project.
h. Compaction of the backfill must be performed in a carefully controlled manner to ensure uniform, dense
backfill. Compaction equipment used must not cause distortion to the culvert pipe. Lighter equipment
should be used immediately adjacent to the pipe and for the first few lifts above the pipe.
i.
Proper protection must be provided for anticipated construction loads. Additional fill material — properly
placed and compacted — may be needed as a temporary protective pad for heavy equipment loads in excess
of design loads for the pipe culvert.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-72
AREMA Manual for Railway Engineering
Culverts
1
Figure 1-4-22. Proper Bedding and Haunch Support
3
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-73
Roadway and Ballast
4.12.8 MULTIPLE INSTALLATIONS (1995)
When two or more culvert pipes are installed in adjacent, parallel lines, the spacing between the pipes must be
adequate to allow proper backfill placement and compaction. This minimum spacing will be dependent upon the
shape and size of the pipe culvert, type of end treatment proposed, type of backfill material and type and size of
compaction equipment used. Figure 1-4-23 provides some general guidelines.
Where the limits on structure spacing are restrictive, the use of flowable fill, CLSM, or low strength portland
cement grout, between structures often can reduce the spacing requirements to a practical limit equal to the few
inches required for hoses, nozzles, etc., used to place this backfill.
Figure 1-4-23. Minimum Permissible Spacings for Multiple Installations
4.12.9 END TREATMENT (1995)
Proper end treatment is critical to protect the culvert pipe from washout, piping, undermining, scour, etc. Slope
paving, rip rap, headwalls/wingwalls, end sections, cutoff walls and toe walls are possible end treatment details
which can be incorporated into culvert design. Warped fill embankments may be needed to provide balanced
loading near the ends of culverts that are skewed to the embankment. See Figure 1-4-24 for clarification.
Protection of the pipe culvert installation from hydraulic action is critical during all phases of construction.
4.12.10 PROTECTION OF PIPE CULVERT FROM CONSTRUCTION LOADS (1995)
It is important to protect pipe culvert structures throughout the construction process because the structure does
not develop full structural capacity until it is properly installed in an adequate backfill envelope including
sufficient minimum cover for anticipated live loads. Heavy construction equipment must not cross the pipe culvert
until sufficient minimum cover height has been achieved. In addition, heavy equipment is to be kept away from the
sides of the pipe culvert to avoid unbalanced loading and possible culvert distortion or displacement. The culvert
manufacturer should be contacted regarding any questions about minimum cover and equipment loads.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-74
AREMA Manual for Railway Engineering
Culverts
1
3
Figure 1-4-24. Using Warped Fill to Balance Loads Across Ends of Culverts
4.12.11 SAFETY PROVISIONS (1995)
Individual railroads may require specific precautions as deemed advisable to insure the safety of the trains, tracks
and construction workers throughout the pipe culvert installation process. Regardless of the installation methods
chosen, the track must be adequately supported during construction. All procedures involved in the installation
must comply with applicable guidelines and regulations, including OSHA requirements.
SECTION 4.13 EARTH BORING AND JACKING CULVERT PIPE THROUGH FILLS
4.13.1 GENERAL (1995)
a.
Where conditions are suitable, the installation of pipe culverts by jacking and/or earth boring can be a viable
alternative to more standard methods of installation such as open cut or tunneling. Possible advantages of
jacking or boring include:
(1) Lower cost.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-75
4
Roadway and Ballast
(2) Minimal interruption of traffic.
(3) Minimal disturbance of roadbed.
b.
Costs may be higher, although not necessarily prohibitive, in unstable soils and embankments containing
boulders, stumps, waste from rock cuts, or similar obstructions.
c.
Before it is decided that jacking is the proper method to use, all conditions involved in the operation should
be investigated. Cost estimates for open cut placement or tunneling should be compared with the probable
cost for jacking and/or boring. Such estimates should include expenses due to interference with traffic and
excess maintenance until embankment becomes stabilized. Additionally, relative safety of the various
installation methods must be considered. The exposed vertical face associated with the jacking operation
may not be desirable in certain soil conditions and should be addressed by a qualified engineer.
d.
It is recommended that pipe boring and jacking operations be performed by an experienced specialty
contractor normally engaged in performing this type of service. Most railroad maintenance-of-way
departments are not equipped to undertake such a project.
e.
For further information on earth boring and jacking methods refer to Reference 27.
4.13.2 TYPE OF PIPE SUITABLE FOR JACKING (1992)
a.
Ideally pipe materials to be used in the boring and jacking process should have a smooth exterior wall. The
most commonly used materials for pipes installed by the boring and jacking contractor are smooth wall steel
pipe or tongue and groove circular concrete pipe. Other shapes, such as precast reinforced concrete box
sections and reinforced concrete elliptical pipe sections, have been successfully jacked. Under certain
conditions, corrugated metal pipe can also be jacked.
b.
Concrete pipe is manufactured with tongue and groove joints which provide a smooth outside surface. An
appropriate class of concrete pipe should be selected to provide the compression strength to resist the axial
forces imposed by jacking. Supplemental joint reinforcing may be required if eccentric loading of the joint is
a possibility.
4.13.3 SIZE AND LENGTH OF PIPE (1992)
a.
The size of pipe that can be placed by jacking will vary with local site conditions. The jacking contractor and
pipe manufacturer should be consulted regarding suitable size and length limits.
b.
Concrete pipe sections are usually manufactured in eight foot lengths; however, other lengths may be
available.
4.13.4 PRECAUTIONS IN UNSTABLE SOILS (1992)
a.
The jacking method is not well adapted to placing pipe in unstable soils, unless certain precautions are
taken. Before undertaking an operation of this kind a thorough investigation of conditions should be made.
Borings into the fill where there is doubt as to the nature of the material may be desirable. Unstable soil
conditions should be evaluated by a qualified geotechnical engineer for recommendations on the most
appropriate method of soil stabilization.
b.
If jacking is decided upon it will probably be beneficial to work continuously to minimize the tendency of the
material to “freeze” around the pipe. However, lubricants such as bentonite slurry are available to minimize
the freezing tendency. The approach trench should be properly sheeted and braced on the sides and working
face. Wet sandy soils can be de-watered by various means including well points. The excavation should not
be carried more than a few inches ahead of the pipe. If the pipe seizes, jacking may have to be done from
both ends, or installation of intermediate hydraulic jacking stations may be required. In some instances,
switching to trenching or open cut methods may be required.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-76
AREMA Manual for Railway Engineering
Culverts
c.
Excessive voids shall not be permitted in the jacking process. Grout points shall be installed in pipe and all
voids shall be filled by pressure grout as soon as possible after the completion of the project.
4.13.5 PROTECTION OF PIPE AGAINST PERCOLATION, PIPING AND SCOUR (1992)
a.
If it is anticipated that the pipe will discharge under head for any considerable period, and particularly if it
lies in easily eroded material, precautions against percolation or piping along the outside should be taken.
b.
Concrete collars, grout injected collars, cut-off walls, slope paving or similar impermeable slope barriers
should be considered as a precaution against percolation or piping along the outside of the conduit.
c.
Should it be necessary to protect the ends against scour, concrete pavement or riprap can be provided at the
end of the pipe. In extreme cases energy dissipaters can be used to reduce the outlet velocity of flow to
acceptable limits.
4.13.6 SAFETY (1992)
Trenching is one of the most dangerous situations in modern construction. Since a jacking operation generally
involves some form of trenching or pit construction, the jacking contractor or railway forces must strictly conform
to all Federal, State and local regulations and in particular, the requirements of the Occupational Safety and
Health Administration (OSHA).
1
SECTION 4.14 CULVERT REHABILITATION
4.14.1 GENERAL (1992)
a.
The purpose of this part of the Manual is to guide the design engineer in his decision to rehabilitate or
replace deteriorated or failing culverts and to recommend methods for the culvert rehabilitation or repair.
b.
While the magnitude of rehabilitation may at times appear enormous, rehabilitation often is very cost
effective when compared to the alternative of new construction.
c.
It is recommended that a regular program of culvert inspection and evaluation be instituted to identify
deteriorated and/or failing culvert sections.
4.14.2 SURVEY OF EXISTING STRUCTURES (1992)
a.
Once a problem is identified, a careful survey should be made of the existing structure to determine the
exact size and shape. It is necessary to know the exact cross-section of the opening at all limiting points, the
alignment of the structure with respect to its centerline, and whether projecting parts of the existing culvert
can be removed. Any old falsework piling, boulders or ledge rock in the waterway that might interfere with
rehabilitation efforts should be noted. In addition, the structural integrity of the culvert and the foundation
conditions under the existing structure should be evaluated.
b.
Given the above information, the design engineer can effectively consider the comparative advantages of
rehabilitation or replacement of the culvert. Items of consideration should include:
(1) Extent of critical nature of the deterioration.
(2) Available track time.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-77
3
4
Roadway and Ballast
(3) Site accessibility.
(4) Available time that flow can be restricted.
(5) Useful service life/life-cycle cost analysis.
(6) Required hydraulic capacity.
(7) Environmental considerations.
4.14.3 METHODS OF REHABILITATION (1992)
If the decision is to rehabilitate the culvert, the design engineer has several options to consider. Methods of culvert
rehabilitation include:
a.
Localized repairs.
b.
Reline the existing structure.
(1) Slip line with slightly smaller diameter pipe or tunnel liner plate.
(2) Inversion lining.
(3) Shotcrete lining.
(4) Cement mortar lining.
c.
In place installation of concrete invert.
Other methods of pipeline rehabilitation are available, but some may not be practical for culverts.
4.14.4 LOCALIZED REPAIRS (1992)
In some cases it is practical to consider localized repair. This can be an economical solution when the overall
condition of the culvert is still performing as designed but has isolated areas of deterioration that if left unattended
would lead to major problems in the future. Techniques that are available to the engineer include:
a.
Grouting. Voids in the backfill caused by leaking joints or pipe wall perforations can be filled by pumping a
sand-cement mortar grout into the void. This can be done from the inside if the structure is large enough or
from the outside of shallow buried structures. Filling the void with grout should prevent further loss of
backfill.
b.
Patching. Localized damage to linings, coatings or pavements in culverts can be patched to prolong the life
of a drainage structure. The area to be repaired should be properly cleaned and the repair material should
match the original material if possible.
c.
Internal Expanding Bands. Pipe joints that have become separated to a degree where loss of backfill is a
threat to the grade of the track above the structure can be repaired with bands couplers that are tightened
from inside the pipe. These bands then expand against the inside wall to form a seal.
d.
Sealing. Elastomeric grout can be used effectively to seal and prevent loss of fine backfill through open pipe
joints. This grout is mechanically pushed into the open joint with the aid of an inflatable bladder. The
chemical grout turns into an elastomeric seal immediately upon contact with water. This material is
normally not used to fill voids because of its cost.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-78
AREMA Manual for Railway Engineering
Culverts
4.14.5 RELINING MATERIALS (1992)
The selection of the reline material is dependent upon the condition of the conduit to be rehabilitated and its
diameter and/or shape. If the line has deteriorated to the point that it is structurally deficient, the rehabilitation
should have sufficient structural capability to withstand the imposed dead and live loads.
4.14.5.1 Sliplining
a.
If after hydraulic evaluation, the downsizing of the existing line is acceptable, then standard corrugated
metal pipe may be used and provided in lengths which would facilitate insertion. Hydraulic advantages may
be gained by improvements to inlet details (see Article 4.8.3.1) or by using helical corrugated steel pipe if
the existing pipe is annularly corrugated.
b.
Hydraulic capacity can be maximized by the use of lined metal pipe. Choices of this type of pipe include:
(1) 100% asphalt lined.
(2) 100% cement mortar lined.
(3) Double-wall CMP.
(4) Spiral rib CMP.
c.
Connection of the liner pipe segments can be achieved with either internal or external adjustable bands
depending upon the available clearance within the culvert.
d.
If the culvert to be relined is large enough for a person to enter, “guide rails” may be installed to insure that
the proper alignment and grade of the liner pipe is maintained. If the lining of the pipe is to be placed at the
same grade as the pipe being lined, skid bars attached to the lining pipe are used in lieu of the guide rails.
Also it is common practice to specify grout plugs and hold-down devices
(Figure 1-4-25).
e.
Where physical constraints and/or safety concerns limit the use of the liner pipe sections, it may become
necessary to use tunnel liner plates. This permits the entire assembly to be erected from inside the
structure.
f.
After the liner pipe has been secured in place, the annular space between the liner pipe and the existing
culvert should be filled. Suitable fill material will vary depending on the type and size of structure, the area
to be filled, the equipment available and the structural requirements. Typical materials (referred to as
CLSM, Controlled Low Strength Material) include cement or chemical grout, concrete slurry and sand.
g.
Care must be taken during filling to eliminate voids. Filling must be done in a balanced fashion and in a
manner that does not cause deformation of the lining pipe. The lining pipe may need to be internally braced
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-79
1
3
4
Roadway and Ballast
(or externally blocked) to resist grouting pressure. The lining pipe may also need to be secured to resist
flotation during grouting.
Figure 1-4-25. CMP Liner Pipe Installation Showing Guide Rails, Grout Plugs and Adjusting Rods
4.14.5.2 Inversion Lining
a.
Inversion lining is accomplished by using needle felt, of polyester fiber, which serves as the “form” for the
liner. The use of this method requires that the pipe be taken out of service during the rehabilitation period.
One side of the felt is coated with a polyurethane membrane and the other is impregnated with a
thermostating resin.
b.
The physical properties of the felt and chemicals must be determined for the specific project.
c.
Inversion lining is most commonly accomplished by specialized contractors in rehabilitation of sanitary
sewers and storm sewers and is not often practical in culvert rehabilitation.
4.14.5.3 Shotcrete Lining
a.
Shotcrete is a term used to designate pneumatically applied cement plaster or concrete. A gun operated by
compressed air is used to apply the cement mixture.
b.
When properly made and applied, shotcrete is extremely strong, dense concrete and resistant to weathering
and chemical attack. For relining existing structures, the shotcrete typically is from 2 to 4 inches thick
depending on conditions and may be steel reinforced.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-80
AREMA Manual for Railway Engineering
Culverts
4.14.5.4 Cement Mortar Lining
a.
For small diameter pipe which is not easily accessible, a cement mortar lining may be applied.
b.
This method involves the use of a mortar projection machine and an attached mechanical trowel. The
assembly is pulled through the culvert as mortar is applied to the interior surface and troweled.
4.14.6 IN PLACE INSTALLATION OF CONCRETE INVERT (1992)
a.
In some cases, the deterioration of the culvert may be limited to the invert. The upper segment may still
exhibit acceptable structural integrity and rehabilitation with a cast-in-place reinforced concrete invert may
be an acceptable alternative (Figure 1-4-26).
b.
This method is generally limited to larger diameter pipes where it is possible for a person to enter and work
within the conduit.
c.
Prior to placing the new invert, it is necessary to divert the stream flow, remove debris and loose material,
and clean the area to receive the new concrete. Next, a reinforcing mesh or bars are secured to the original
culvert. Then an appropriate thickness of concrete is applied to the invert and troweled smooth to conform
to the shape of the bottom of the culvert.
d.
An epoxy type sealer may be applied to the concrete invert to seal the concrete pores and increase service
life.
e.
The engineer or designer may also want to refer to Chapter 8, Concrete Structures and Foundations, Part
14, Repair and Rehabilitation of Concrete Structures.
1
3
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-81
Roadway and Ballast
Figure 1-4-26. Example of New Invert in CMP
SECTION 4.15 SPECIFICATION FOR STEEL TUNNEL LINER PLATES
4.15.1 GENERAL (1992)
4.15.1.1 Scope
These specifications cover cold-formed steel tunnel liner plates, fabricated to permit in-place assembly of a
continuous steel support system as excavation of the tunnel progresses.
4.15.1.2 Authority of Engineer
The engineer shall decide which type of tunnel liner plate shall be used and his decision shall be final.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-82
AREMA Manual for Railway Engineering
Culverts
4.15.2 MATERIAL (1992)
4.15.2.1 Plates
a.
The tunnel liner plates shall be fabricated from structural quality, hot-rolled, carbon-steel sheets or plates
conforming to ASTM Specification A 569.
b.
The mechanical properties of the flat plate before cold forming shall be:
Tensile strength, psi . . . . . . . . . 42,000 min
Yield strength, psi . . . . . . . . . . . 28,000 min
Elongation in 2, % . . . . . . . . . . 30 min
4.15.2.2 Bolts
a.
Bolts and nuts used with lapped seams shall be not less than 5/8 inches in diameter. The bolts shall conform
to ASTM Specification A 449 for plate thicknesses equal to or greater than 0.209 inches and A 307 for plate
thicknesses less than 0.209 inches. The nut shall conform to ASTM Specification A 307, Grade A.
b.
Bolts and nuts used with four flanged plates shall be not less than1/2 inch in diameter for plate thicknesses
to and including 0.179 inch and not less than 5/8 inch in diameter for plates of greater thickness. The bolts
and nuts shall be quick-acting coarse thread and shall conform to ASTM Specification A 307, Grade A.
1
4.15.3 FABRICATION (1992)
4.15.3.1 Plate Size and Weight
The plate width shall be l6 or 18 inch. The plate lengths shall provide circumferential wall coverage in two or more
multiples equivalent to 6, 12, 14 or 16 inch of diameter. The maximum weight of a single plate without bolts shall
be 90 lb.
3
4.15.3.2 Plate Joints
All plates shall be punched for bolting on both longitudinal and circumferential seams or joints and shall be so
fabricated as to permit complete erection from the inside.
4
4.15.3.2.1 Circumferential
Bolt spacing in circumferential flanges shall be not more than 92 inches center to center and shall be a multiple of
the plate length so that plates having the same curvature are interchangeable and will permit staggering of the
longitudinal seams.
4.15.3.2.2 Longitudinal
4.15.3.2.2.1 Four-Flanged Plates
The longitudinal flanges shall be punched to accommodate 3 bolts in a 16 inch plate width.
4.15.3.2.2.2 Two-Flanged Plates
The longitudinal lapped seams shall be punched to accommodate 4 bolts per foot.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-83
Roadway and Ballast
4.15.3.3 Plate Configuration
All plates shall be cold formed to provide a pattern of corrugations or panels in the skin section, which, along with
the circumferential flanges, will develop the effective sectional properties shown in Table 1-4-38.
4.15.4 COATINGS (1992)
Steel liner plates are often used only to maintain the tunnelled opening until a carrier pipe is installed and
backpacked. In such use the liner is expendable and no purpose is served by extending its life. If the steel liner
plates compose the finished structure, then the expense of corrosion-resistant coatings is justified.
4.15.4.1 Zinc Coating
When required, and so specified, the liner plates shall be galvanized to meet the requirements of AREMA
Specification for Corrugated Structural Plate Pipe, Pipe Arches and Arches. Bolts and Nuts shall be galvanized to
meet the requirements of ASTM Specification A 153.
4.15.4.2 Bituminous Coating
In addition, when so specified, the liner plates shall be bituminous-coated to meet the requirements of AREMA
Specification for Bituminous Coated Corrugated Metal Pipe and Arches.
4.15.5 DESIGN (1992)
4.15.5.1 General
a.
These criteria cover the design of cold-formed panel steel tunnel liner plates. The minimum thickness shall
be as determined by design in accordance with Article 4.15.5.2, Article 4.15.5.3, Article 4.15.5.4,
Article 4.15.5.5, and Article 4.15.5.6. The construction shall conform to Section 4.16, Construction of
Tunnel Using Steel Tunnel Liner Plates and Table 1-4-38.
b.
The supporting capacity of a nonrigid tunnel lining such as a steel liner plate results from its ability to
deflect under load so that side restraint developed by the lateral resistance of the soil constrains further
deflection. Deflection thus tends to equalize radial pressures and to load the tunnel liner as a compression
ring.
c.
The load to be carried by the tunnel liner is a function of the type of soil. In a granular soil, with little or no
cohesion, the load is a function of the angle of internal friction of the soil and the diameter of the tunnel
being constructed. In cohesive soils such as clays and silty clays the load to be carried by the tunnel liner is
affected by the shearing strength of the soil above the roof of the tunnel.
d.
A subsurface exploration program and appropriate soil tests should be performed at each installation before
undertaking a design.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-84
AREMA Manual for Railway Engineering
Culverts
Table 1-4-38. Effective Sectional Properties Based on the Average of One Ring of Plates
Thickness
(Inches)
Area
(Inch 2/Inch)
Moment of Inertia
(Inch 4/Inch)
Radius of Gyration
(Inch)
18 inch Wide – 2 Flange Plates
0.075
0.105
0.135
0.164
0.179
0.209
0.239
0.096
0.135
0.174
0.213
0.233
0.272
0.312
0.034
0.049
0.064
0.079
0.087
0.103
0.118
0.60
0.60
0.61
0.61
0.61
0.62
0.62
16 inch Wide – 4 Flange Plates
0.105
0.120
0.135
0.164
0.179
0.209
0.239
0.313
0.375
0.0656
0.0759
0.0851
0.1040
0.1140
0.1380
0.1510
0.1930
0.2290
0.0398
0.0468
0.0517
0.0709
0.0771
0.0904
0.1180
0.1620
0.2200
0.41
0.41
0.41
0.44
0.44
0.44
0.47
0.49
0.52
1
4.15.5.2 Loads
The external load on a circular tunnel liner made up of tunnel liner plates, may be predicted by various methods.
In cases where more precise methods of analysis are not employed, the external load P can be predicted by the
following:
a.
If the grouting pressure is greater than the computed external load, the external load P on the tunnel liner
shall be the grouting pressure.
b.
In general the external load can be computed by the formula:
EQ 4-15
P = P1 + Pd
where:
P = the external pressure on the tunnel liner
P1 = the vertical pressure at the level of the top of the tunnel liner due to live loads
Pd = the vertical pressure at the level of the top of the tunnel liner due to dead load
Values of P1 for Cooper E 80 live load, including an allowance of 50% for impact, are approximately as shown
in Table 1-4-39.
c.
Values of Pd may be calculated using modified Marston’s formula for load as follows, or any other suitable
method.
EQ 4-16
Pd = Cd W D
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-85
3
4
Roadway and Ballast
Table 1-4-39. Live Loads, Including Impact, for Various Heights of Cover for Cooper E 80
(See Note 1)
Height of Cover (Ft)
Load Lb/Ft2
2
3800
5
2400
8
1600
10
1100
12
800
15
600
20
300
30
100
Note 1: If height of cover (from bottom of cross tie to top of
structure) is over 30 feet, use dead load only. For live load
other than Cooper E 80, the above values should be
accordingly adjusted.
d.
In the absence of adequate borings and soil tests, the full overfill height should be the basis for Pd in the
tunnel liner plate design. Values of Pd may be calculated using Marston’s formula
where:
Cd = coefficient for tunnel liner (Figure 1-4-27)
W = total (moist) unit weight of soil
D = horizontal diameter or span
4.15.5.3 Structural Criteria
The following criteria must be considered in the design of liner plates:
a.
Joint strength.
b.
Handling and installation strength.
c.
Critical buckling of linear plate wall.
d.
Deflection or flattening of tunnel section.
4.15.5.4 Joint Strength
a.
Seam strength for liner plates must be sufficient to withstand the thrust developed from the total load
supported by the liner plate. This thrust, T, in pounds per lineal foot is:
PD
T = --------2
EQ 4-17
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-86
AREMA Manual for Railway Engineering
Culverts
Ø = soil friction angle
H = height of cover
1
Figure 1-4-27. Diagram for Coefficient Cd for Tunnels in Soil
where:
3
P = load as defined in Article 4.15.5.2
D = diameter or span in feet
b.
Ultimate design longitudinal seam strengths are found in Table 1-4-40.
c.
Thrust, T, multiplied by the safety factor, should not exceed the ultimate seam strength.
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-87
Roadway and Ballast
Table 1-4-40. Longitudinal Seam Strengths
Plate Thickness
Inches
Ultimate Strength,
Kips/Ft
2 flange
4 flange
0.075
20.0
–
0.105
30.0
26.4
0.135
47.0
43.5
0.164
55.0
50.2
0.179
62.0
54.5
0.209
87.0
67.1
0.239
92.0
81.5
0.250
–
84.1
0.313
–
115.1
0.375
–
119.1
4.15.5.5 Minimum Stiffness for Installation
The liner plate ring shall have enough rigidity to resist the unbalanced loadings of normal construction: grouting
pressure, local slough-ins and miscellaneous concentrated loads. The minimum stiffness required for these loads
can be expressed for convenience by the formula below. It must be recognized, however, that the limiting values
given here are only recommended minimums. Actual job conditions may require higher values of effective stiffness.
Final determination on this factor should be based on intimate knowledge of a project and practical experience.
EI
Minimum Stiffness = ------D2
EQ 4-18
where:
D = diameter in inches
E = modulus of elasticity, psi
I = moment of inertia, in.4/in.
EI
For 2-Flange ------- = 50 minimum
D2
EI
For 4-Flange ------- = 110 minimum
D2
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-88
AREMA Manual for Railway Engineering
Culverts
4.15.5.6 Critical Buckling of Liner Plate Wall
a.
Wall buckling stresses are determined from the following formulas:
f 2
r 24E
u  KD 2
For diameters less than ---- ----------- : f c = f u – ---------- -------- in psi
K fu
48E  r 
r 24E
12E in psi
For diameters greater than -------------- : f c = ----------------2
K fu
 KD

 -------r 
EQ 4-19
EQ 4-20
where:
fu = minimum specified tensile strength, psi
fc = buckling stress, psi, not to exceed specified yield strength
K = soil stiffness factor, which will vary from 0.22 for soils where Ø > 15 to 0.44 where Ø < 15 to
0.44
D = pipe diameter, inches
r = radius of gyration of section
E = modulus of elasticity, psi
b.
1
Design for buckling is accomplished by limiting the ring compression thrust T to the buckling stress
multiplied by the effective cross section area of the liner plate divided by the factor of safety:
f cA
T = --------FS
EQ 4-21
3
where:
T = thrust per lineal foot from Article 4.15.5.4
A = effective cross section area of liner plate, square inches per foot
FS = factor of safety for buckling
4
4.15.5.7 Deflection or Flattening
a.
Deflection of a tunnel depends significantly on the amount of over excavation of the bore and is affected by
delay in backpacking or inadequate backpacking. The magnitude of deflection is not primarily a function of
soil modulus or the liner plate properties, so it cannot be computed with usual deflection formulas.
b.
Where the tunnel clearances are important, the designer should oversize the structure to provide for a
normal deflection. Good construction methods should result in deflections of not more than 3% of the
nominal diameter.
4.15.5.8 Safety Factors
Longitudinal seam strength . . . . 3
Pipe wall buckling. . . . . . . . . . . . 2
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-89
Roadway and Ballast
SECTION 4.16 CONSTRUCTION OF TUNNEL USING STEEL TUNNEL LINER PLATES
4.16.1 SCOPE (1992)
These specifications are intended to cover the installation of tunnel liner plates in tunnels constructed by
conventional tunnel methods. For the purposes of these specifications, tunnels excavated by full face, heading and
bench, or multiple drift procedures are considered conventional methods. Liner plates used with any construction
procedure utilizing a full or partial shield, a tunneling machine or other piece of equipment which will exert a force
upon the liner plates for the purpose of propelling, steering or stabilizing the equipment are considered special
cases and are not covered by these specifications.
4.16.2 DESCRIPTION (1992)
a.
This item shall consist of furnishing cold formed steel tunnel liner plates conforming to these specifications
and of the sizes and dimensions required on the plans, and installing such plates at the locations designated
on the plans or by the engineer, and in conformity with the lines and grades established by the engineer. The
completed liner shall consist of a series of steel liner plates assembled with staggered longitudinal joints.
Liner plates shall be fabricated to fit the cross section of the tunnel. Liner plates herein described must
meet the section properties — thickness, area, and moment of inertia — as listed in Table 1-4-38.
b.
All plates shall be connected by bolts on both longitudinal and circumferential seams or joints and shall be
so fabricated as to permit complete erection from the inside.
c.
Grout holes 2 inches or larger in diameter shall be provided as shown on the plans to permit grouting as the
erection of tunnel liner plates progresses.
4.16.3 INSTALLATION (1992)
a.
All liner plates for the full length of a specified tunnel shall be of one type only, either the flanged or the
lapped seam type of construction.
b.
Liner plates shall be assembled in accordance with the manufacturer’s instructions.
c.
Coated plates shall be handled in such a manner as to prevent bruising, scaling, or breaking of the coating.
Any plates that are damaged during handling or placing shall be replaced by the contractor at his expense,
except that small areas with minor damage may be repaired by the contractor as directed by the engineer.
d.
Voids occurring between the liner plate and the tunnel wall shall be force-grouted. The grout shall be forced
through the grouting holes in the plates with such pressure that all voids will be completely filled. The
frequency of grouting shall be as directed by the engineer.
e.
Full compensation for backpacking or grouting shall be considered as included in the contract price paid for
tunnel and no separate payment will be made therefor.
4.16.4 MEASUREMENT (1992)
The length of tunnel to be paid for will be the length measured on the tunnel liner plate invert.
4.16.5 PAYMENT (1992)
Payment for the footage of each size of tunnel as determined under measurement shall be paid for at the contract
unit prices per lineal foot bid for the various sizes, which payment shall include full compensation for furnishing all
labor, materials, tools, equipment and incidentals to complete this item, including removal and disposal of material
resulting from the excavation of the bore and force-grouting voids.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-90
AREMA Manual for Railway Engineering
Culverts
SECTION 4.17 CULVERT INSPECTION
4.17.1 INTRODUCTION (2001)
a.
Railroad rights-of-way across North America contain numerous culvert structures, in a variety of sizes and
made from a variety of materials, buried beneath the track structure. Culverts, just like any other type of
structure, require maintenance and inspection on a regular basis in order to perform as intended. However,
items critical to a culvert inspection may not be those typically associated with a bridge inspection and
special training is required.
b.
Lack of knowledge regarding proper installation, inspection and maintenance is a primary cause of poor
performance of culverts and other drainage structures. The fact that culverts are buried in an embankment
and are not generally visible at track level contributes to the problem since they usually do not receive the
same attention that bridges, tunnels and other major structures receive. A failure of a culvert structure can
have the same catastrophic result as a bridge or tunnel collapse. Routine and proper inspection of railway
culverts is not only recommended but is necessary to assure that these important structures are functioning
as originally designed.
4.17.2 DEFINITION OF A CULVERT (2001)
a.
A culvert can be defined as a drainage opening or conduit passing through an embankment for the purpose
of conveying water. Culverts are usually hydraulic conduits; however, short span structures such as a
cattlepass or pedestrian underpass would fall under the general classification of culverts.
b.
Culverts, unlike bridges, have no definite distinction between substructure and superstructure. While some
agencies distinguish between bridges and culverts based solely on size, with spans of 10' frequently selected
as the limiting factor, the true difference is the basis upon which culverts are designed - both structurally
and hydraulically.
1
4.17.3 KEY DIFFERENCES FROM BRIDGES AND OTHER STRUCTURES (2001)
3
4.17.3.1 Structural Differences Between Culverts and Bridges
a.
Culverts are designed to support not only the live load of railway traffic but also the dead load of the soil and
track structure above. However, the live load becomes less of a factor as the depth of cover above the culvert
increases, due to distribution of the live load through the soil. Bridges do not generally have an overburden
of soil above the spanning elements.
b.
Flexible culverts essentially function as a soil-structure interaction system. The quality and stability of soil
materials surrounding most culvert structures are critical to their ability to carry load. While rigid culverts
(such as reinforced concrete, thick walled metal pipe, etc.) are designed differently than flexible culverts,
there still is a degree of dependency upon quality of backfill surrounding the culvert. The type of backfill
and degree of compaction affect side support and foundation support. Bridges, on the other hand, are
usually designed to transfer vertical loads to the subsurface by way of piles or spread footings.
4.17.3.2 Hydraulic Differences Between Culverts and Bridges
a.
Most culverts are designed to operate efficiently under submerged inlet conditions. As flow increases,
ponding occurs at the upstream end of the culvert. The resultant rise in water surface elevation increases
the head at the inlet end and increases hydraulic capacity of the culvert, provided, of course, that proper end
treatment, cutoff walls, embankment slope protection, etc. are incorporated into the design.
b.
Bridges are not usually designed to create a restriction of flow at the upstream end of the structure. In fact,
most bridges are designed to pass the maximum amount of flow without submerging any of the spanning
elements.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-91
4
Roadway and Ballast
c.
Scour protection of footings - whether for bridge abutments or piers or for arch-type culverts - is a concern
common to bridges and culverts.
4.17.3.3 Inspector Qualifications and Training
a.
While actual inspection items, techniques, etc. are discussed later in this section, it is important to
distinguish between culverts and bridges when it comes to several visual observations. Many bridge
inspectors are trained to look for cracks, rust, spalling concrete, exposed rebar, etc. as signs of obvious
distress. While such factors may be a valid concern for culverts, oftentimes minor problems such as surface
rusting and perforations are noted while culvert deflection, distortion, embankment settlement, erosion,
and other more serious factors are ignored.
b.
Inspectors must be trained to recognize the critical factors involved with inspection of culverts. The culvert
inspector should have knowledge of how culverts function, hydraulically and structurally, and the
significance of defects that may be found during inspection, along with the load bearing capacity that the
culvert must maintain. The culvert inspector must be capable of working under physically demanding
conditions, including cramped spaces, rugged terrain, steep embankments, and in and around water. The
inspector must also be able to read plans, construction documents, inspection reports, and have a knowledge
of the use of various types of measuring devices, and also the ability to use a surveyors level when necessary.
c.
The inspector should have a minimum of 2 years of culvert inspection assignments, working under the
supervision of a qualified culvert inspector, and/or should have completed a comprehensive training course
for culvert inspection on the subjects as outlined in Paragraph b above.
4.17.4 SAFETY (2001)
a.
Culvert inspection in many cases presents certain hazards to personnel performing the inspection. In order
to properly evaluate the structural integrity of a culvert, it is usually necessary to perform an internal
inspection of the conduit. Many smaller diameter culverts may exist under railroad properties which makes
internal inspection difficult. It is recommended that culverts less than 30 inches in diameter not be entered
by inspection personnel without special precautions. Internal inspection of culverts in this size range is best
conducted using specially designed video cameras, deflection recording devices, or similar methods.
Culverts 30 inches in diameter and larger should only be entered by inspection personnel trained in working
within confined spaces and using procedures in full compliance with all applicable State, Local and Federal
regulations (i.e., OSHA, Roadway Workers Protection Act, and other FRA regulations).
b.
Most railroad culverts are located at the base of relatively steep embankments and many contain high
parapet and/or wingwalls. At such locations, fall protection measures should be implemented. Fast moving
water may also present additional hazards. Culverts should never be entered if water depths in
combination with flow velocity make conditions potentially dangerous. Even low flow depths can cause
problems with footing, etc. and care must be taken. As with any maintenance-of-way function, the risk of
working along an active railroad is also a consideration.
c.
Inspectors and maintenance workers should never enter culverts if conditions or the structural integrity of
the culvert appear questionable. However, the appropriate railway office should be notified of the culvert
problems as soon as possible.
d.
In light of the risks associated with culvert inspection, it is necessary that culvert inspectors receive
adequate training prior to undertaking any field inspection of culvert facilities. If a railroad or transit
company does not have adequately trained culvert inspection personnel, it is recommended that internal
inspection services be contracted to a specialty firm.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-92
AREMA Manual for Railway Engineering
Culverts
4.17.5 INVENTORY, ASSESSMENT OF EXISTING CONDITIONS, AND FREQUENCY OF
INSPECTION (2001)
4.17.5.1 Inventory
It is important and extremely useful to develop a comprehensive list of all existing culvert structures, in a logical
order, so that a specific culvert can easily be found when necessary. This is generally done in several ways. One
would be to provide a system map, or a series of division or regional maps of the railroad system, showing location
of each culvert and structure by milepost and also with a brief description of the culvert at each location. This
provides a quick easy reference for determining the location of culverts for upcoming inspections, and also for the
location of culverts that might fall within other types of construction projects. In addition to this, a comprehensive
listing by line segment, and milepost order, along with a listing of the structural characteristics, age, skew angle,
and general condition, is probably the most useful for documenting all culvert structures.
4.17.5.2 Assessment of Existing Conditions
It is important that any inventory of existing culvert structures contain not only the specific structural
characteristics of the culvert, but also an assessment of existing conditions which relate directly to the condition
and future life of that culvert. This listing is very useful in planning future culvert maintenance and replacement,
and is also a very valuable tool in planning periodic, intermediate culvert inspections. This listing should be
updated annually with current inspection results, and it is also important, of course, to update this listing with the
addition of new culverts and by the deletion of culverts that have been retired and removed, so that the
information provided is accurate and current. Any modifications to the adjacent drainage area that may affect the
hydraulic performance of the culvert should be noted.
4.17.5.3 Frequency of Inspection
a.
Following an initial assessment, the frequency of inspection is dependent upon the age and condition of the
culverts within the system. It is suggested that every culvert in the system be inspected at least every five
years. A specific culvert condition or deficiency along with specific types of soil conditions, and other local
conditions, may require more frequent inspections, and this should be determined by a qualified inspector.
b.
It is advisable that interim inspections be carried out immediately after major rain storms, or any time
when it is known that the culvert, or culverts in question, have been subjected to heavy run off or very high
stream flows. These inspections should be made as soon after a major storm as possible, or at least before
the track is to be used again. It may also be advisable to have a listing of specific culverts and locations
which are susceptible to high runoff, heavy drift loads, ice flow or severe scour.
c.
Areas that have significant construction and new development occurring in the upstream watershed should
receive interim inspections.
4.17.6 PHYSICAL CONDITION ASSESSMENT (2001)
4.17.6.1 Condition of Roadbed/Track Surface
a.
Quite often a track irregularity, such as an alignment problem or a settlement problem, is indicative of the
fact that the underlying culvert is possibly failing in some manner. It is important, not only for the culvert
inspector to be aware of this, but also for the personnel doing periodic track inspections to be aware of
locations of culverts. Any track irregularities over a culvert should be communicated to the appropriate
railway office for a follow-up culvert inspection. Track conditions that may indicate underlying culvert
problems include track alignment irregularities, track settlement, side-slope failures, and also scouring of
side slopes by recent water flow.
b.
In some cases, culvert problems may be due to settlement or movement of the fill around the culvert. Part 1
Roadbed, discusses precautions that should be taken to avoid this problem. Culvert distress may also occur
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-93
1
3
4
Roadway and Ballast
without attendant roadbed surface or track alignment problems. Lack of surface problems does not
supersede the need for thorough periodic culvert inspections.
4.17.6.2 Condition of Upstream/Downstream Channel
a.
In addition to structural failure, a culvert can also fail hydraulically. Culverts that are plugged, damaged,
improperly installed, or not sized properly usually are not capable of handling the flows needed to maintain
good drainage under the track and roadbed structure.
b.
The culvert should be inspected to see that it is well aligned with the stream channel both vertically with
the streambed profile and horizontally with the channel alignment. Loss of embankment, inlet and outlet
scour, and backwater conditions may be symptoms of inadequate culvert capacity.
c.
In some cases, the installation of pavement, riprap, headwalls, toe walls, and/or collars may improve a
culvert’s hydraulic performance. If such structures are already in place, they should be inspected closely for
damage, proper location and sizing, and hydraulic performance. Drift problems, turbulence, or other
impediments to smooth stream flow through the culvert should be noted. See 4.1.1 Waterway Required
(1995), for more information.
4.17.6.3 Visual Appearance
a.
The culvert inspector must be aware of the important aspects related to visual appearance of the culvert as
they pertain to the type of culvert (i.e., rigid or flexible) and the culvert material (i.e., metal, concrete,
plastic, etc.). Problems vary in relevancy and significance depending upon culvert type and culvert material.
A proper inspection of a culvert must start with the determination of culvert type and identification of
culvert material.
b.
Observation should be made of the actual shape of the culvert as compared to original design geometry. If
irregularities in cross-sectional shape are observed, the culvert must be inspected carefully to determine if it
is structurally sound. It may be necessary to perform interim inspections to observe whether the culvert is
continuing to deform.
c.
Deviations in alignment as compared to previous inspection records or as-built conditions should be
assessed for risk to culvert performance. Changes in vertical or horizontal alignment may indicate unstable
or poorly compacted support soils, or may also indicate the displacement of soils caused by water flowing
along and/or under the pipe through the subgrade, also referred to as “piping”.
4.17.6.4 Physical Condition of Culvert
There are a number of physical manifestations of possible distress in culverts. This section discusses some of these
problems in general terms; however, the significance of such problems will vary depending upon the culvert type
and material. Refer to Report No. FHWA-IP-86-2 Culvert Inspection Manual - Supplement to the Bridge Inspector’s
Training Manual (Reference 11) and An Empirical Approach for Predicting Deflection in Large Metal Culverts
(Reference 19) for more detail regarding further investigation of specific defects.
4.17.6.4.1 Corrosion
Corrosion may be due to soils or effluent with an extreme pH or restivity and/or the presence of contaminants.
Evidence of corrosion will vary depending upon the type of culvert material. Corrosion is typically manifested by
rusting, perforations or metal loss in a metal culvert and by spalling of concrete and exposed reinforcing steel in a
concrete culvert. The amount of corrosion that has developed in the culvert, particularly along the culvert flow
line, should be noted. It must be determined as to whether a loss of section is impairing the culvert’s ability to
carry the prescribed loads.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-94
AREMA Manual for Railway Engineering
Culverts
4.17.6.4.2 Abrasion
Abrasion may be a critical component of deterioration for all types of culverts. Abrasion may wear away any
protective coatings and allow corrosion to begin and proceed at an accelerated rate. Abrasion is critical as it will
reduce the cross sectional area of the wall and eventually impair the integrity and load bearing capacity of the
culvert. Abrasion will occur particularly in pipes with steep gradients, and also in areas where high flow rates
carrying sand and rocks can wear away the culvert invert.
4.17.6.4.3 Coating Loss
Coatings are intended to extend the life or improve hydraulic performance of the culvert. Coating loss can occur by
a chemical reaction or by abrasion and may be followed by increased corrosion of the culvert; loss of structural
integrity; and/or reduction in hydraulic capacity.
4.17.6.4.4 Perforations
Perforations of the culvert wall are also evidence of abrasion and/or corrosion and are indicative of loss of wall
thickness. This could represent a severe condition. The culvert should be evaluated to ascertain the extent of
metal loss and to determine if it is losing its structural integrity (and load bearing capacity). Severely perforated
culvert wall sections may indicate the need for immediate repair or rehabilitation of the culvert.
4.17.6.4.5 Cracks
Cracks may be indicative of more serious underlying problems. The significance of these cracks will vary
depending upon the type of culvert material, along with crack location, size and orientation. Cracks should be
noted; monitored for propagation; and if warranted, evaluated for their effect on structural capacity.
1
4.17.6.4.6 Seams
Seams, if present, must be inspected as they are critical to the culvert’s structural and hydraulic performance.
Problem seams may allow loss of backfill, lead to infiltration/exfiltration of flow, affect structure performance, and
should be evaluated for possible repair.
3
4.17.6.4.7 Joints
Joints should be inspected for proper alignment and possible cracking. Misaligned joints contribute to loss of soil,
infiltration/exfiltration of flow and other maintenance problems. Joint deficiencies should be noted and evaluated.
4
4.17.6.4.8 Undermining (Scour/Piping)
Undermining/scour can occur at the exposed ends or footings of the culvert, as well as along the length of the
culvert. Scour may be obvious during the visual inspection at the ends of the culvert. However, scour along the
footings of arch culverts and piping may be less obvious. The extent of scour and resulting undermining should be
determined and evaluated from a loss of support perspective. Appropriate repair measures to prevent future scour
and to restore support to the culvert is essential.
4.17.6.4.9 End Treatment
End treatment usually consists of headwalls, wingwalls, cut-off walls, toe-walls, slope protection, energy
dissipators or flared end sections. Visual inspection of these items involves looking for cracks, misalignment,
shifting or settling of headwalls or wingwalls, signs of scour, undermining or hydraulic piping. Any evidence of
problems may require immediate repair to assure that the track subgrade remains stable.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-95
Roadway and Ballast
4.17.6.5 Baseline Measurements
At the onset of a regular culvert inspection program, it is recommended that baseline measurements be taken for
all culverts along the right-of-way. This information, in conjunction with the culvert inventory previously
mentioned, will become valuable in the event difficulties are encountered. It is recommended that, where
practical, the following information be recorded:
a.
Span
b.
Rise
c.
Skew angle
d.
Elevations at invert and crown along the conduit at least every 25 ft.
e.
Top of rail and top of subgrade elevations at centerline of culvert and centerline of track, and at 50-ft. and
100-ft. stations either side of the culvert.
f.
Length of culvert
g.
Distance from centerline of track to each end of the culvert
h. Configuration and dimensions of headwalls, toe walls, wingwalls or other end treatments
i.
Differences in alignment, shape, materials, etc. along the culvert length
j.
Channel characteristics upstream and downstream
k.
Drainage area characteristics
4.17.6.6 Culvert Inspection Form
Figure 1-4-28 represents a sample culvert inspection form that can be used by most railroad companies to
inventory and assess existing culverts on their railroads.
4.17.7 EVALUATION/RECOMMENDED ACTION (2001)
4.17.7.1 Action Plan
It will be up to the culvert inspector to notify the particular railroad’s engineering department of the nature and
extent of the defects found. Depending on the conditions observed in the inspection of the culvert, an action plan
must be developed. That course of action can come in several forms as noted below.
4.17.7.1.1 Speed Restrictions/Class Reduction
It will be up to the culvert inspector to notify the appropriate railroad official if the condition of the pipe appears to
be such that there is potential for subgrade instability, track settlement, or any track alignment irregularities that
may warrant the need to reduce train speed. If such restriction is necessary, it must be placed immediately and
should not be removed until the proper corrective action to stabilize the culvert, subgrade, and track structure has
been completed.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-96
AREMA Manual for Railway Engineering
Culverts
4.17.7.1.2 Monitoring Program
The defects found may be such that no track or subgrade instability has occurred, and structural integrity and
hydraulic performance of the culvert will be satisfactory. However, conditions observed may indicate potential
deterioration and require establishing a plan for periodic monitoring of the culvert and the overlying track and
subgrade conditions for the short or long term. It is recommended that appropriate measurements be taken as
part of this monitoring program and compared against the measurements taken as part of the baseline
measurements. It is important to note any localized distortions and deformations and to determine if these areas
need further attention. The need for corrective action will be determined by conditions observed in the monitoring
program and will be dependent upon the rate of change as evidenced by the measurements taken.
4.17.7.1.3 Rehabilitation
In many situations, rehabilitation or repair of the existing culvert may be a viable option. Various means are
available, depending upon the type and extent of the problems discovered. See Section 4.14 Culvert Rehabilitation.
4.17.7.1.4 Replacement
Replacement of the culvert is necessary if a decision is made that rehabilitation is not an economical, structurally
feasible, or hydraulically acceptable option. When replacement is indicated, proper intermediate steps must be
taken to insure the stability and safety of the track structure.
4.17.8 INSPECTION FOLLOW-UP (2001)
There should be a follow up procedure in effect to determine that any monitoring programs that have been set up
to observe ongoing culvert conditions have been followed, and possibly to reevaluate the need to continue
monitoring and/or perform a subsequent, complete inspection. Follow up for rehabilitation should be made to
determine that the repairs that were made were sufficient to restore the structural integrity of the culvert and to
provide the proper stability and support for the track structure and subgrade. If the culvert has been replaced, the
follow up inspection should be made to determine that the replacement culvert was properly installed and the
surrounding and adjacent soils properly compacted so that the culvert is operating properly, and the track
structure is being properly supported.
1
3
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-97
Roadway and Ballast
Figure 1-4-28. Culvert Inspection Form
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-98
AREMA Manual for Railway Engineering
Culverts
1
3
4
Figure 1-4-28 Culvert Inspection Form (Continued)
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-99
Roadway and Ballast
SECTION 4.18 PERFORATED PIPE DRAINS
4.18.1 GENERAL (2006)
This portion of the Manual shall give guidance to constructing perforated pipe underdrains (or subdrains) with a
granular filter. This work shall consist of furnishing and installing perforated pipe and porous backfill. Pipe
underdrains shall have the nominal diameter specified, shall be placed in a trench to the established line and grade,
and shall be backfilled as specified herein.
4.18.2 APPLICATIONS (2006)
There are numerous types of applications for perforated pipe underdrains (or subdrains) in conjunction with
railroad facilities. Grade crossings, lateral drains in the right of way installed parallel to the track, intermodal
facilities, railroad yards, loading docks, bridge abutments, rock ledges and other narrow right of way constraints
involving tight clearances are examples of situations possibly requiring underdrains. However, perforated pipe
underdrains should not be used as a replacement for conventional ditch construction unless thorough site
investigative work is conducted to insure adequate subgrade and ballast drainage.
Loading situations vary at such sites – ranging from maintenance vehicles, highway legal loads, etc., up to E 80 and
greater rail loads. Consideration must also be given to construction live loads. Vehicles used at intermodal facilities
typically represent significant wheel loads that would influence the design of subdrain pipe. Suitable design
methodology and installation standards must address intended use, loading, height of cover and pipe product
characteristics.
4.18.3 MATERIALS (2006)
Taking into consideration such factors as vehicle loads, cover depths, and product design requirements, pipe shall
be of the type and size listed in the project specifications. Generally acceptable pipe materials (except as noted
below) may include, but are not limited to, the following:
4.18.3.1 CORRUGATED POLYETHYLENE PIPE
Shall conform to AASHTO M252 or AASHTO M294.
4.18.3.2 PROFILE WALL PVC PIPE
Shall conform to AASHTO M304, ASTM F794 or F949.
4.18.3.3 CORRUGATED STEEL PIPE
Shall conform to AASHTO M36, M190 Type A, M240, M245 or M246; ASTM A760, A762 or A845.
4.18.3.4 CORRUGATED ALUMINUM ALLOY PIPE
Shall conform to M196; ASTM B745.
4.18.3.5 PVC/ABS COMPOSITE PIPE
Shall conform to AASHTO M264; ASTM D2680.
4.18.3.6 PVC SOLID WALL PIPE
Shall conform to AASHTO M278; ASTM D3034; F679, F758.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-100
AREMA Manual for Railway Engineering
Culverts
4.18.3.7 ABS SOLID WALL PIPE
Shall conform to ASTM D2751.
4.18.3.8 PERFORATED REINFORCED CONCRETE PIPE
Shall conform to AASHTO M175; ASTM C444
Note – Not all the pipe products listed above are suitable under the anticipated loads (such as railroad live loads
and construction traffic) for this application. The designer should check the loading conditions for the specific
application at hand. Additionally, lateral edgedrain type products, addressed separately in Chapter 1, Part 10 of the
Manual, may also be suitable pipe underdrain materials.
4.18.4 RELATED FILTER MATERIALS (2006)
4.18.4.1 GRANULAR FILTER MATERIALS
It is recommended that a granular filter material consist of a washed, well-graded, angular material that provides
necessary pipe support while retaining free drainage characteristics. Generally the ballast used beneath the track
structure is suitable for this purpose. Pipe perforation geometry (i.e., opening size and shape) should be considered
when specifying minimum gradation of filter material.
4.18.4.2 FILTER FABRIC
1
Filter fabrics shall conform to the requirements stated in Chapter 1, Part 10 of this Manual.
4.18.5 HYDRAULIC DESIGN (2006)
a.
b.
The hydraulic design of the subsurface drainage system begins with determining the flow. This is
accomplished using a combination of analytical and empirical methods as required. Field investigations
should include soil and geological studies, borings to find the elevation and extent of the water table, and
measurements of the groundwater discharge. The investigation should be thorough and ideally conducted
during the rainy season or during snowmelt if the region has snow cover. It may involve digging a trench to
aid in estimating flow.
After the design flow is established, the underdrain piping may be sized per the resultant unit inflow and
available outlet locations. The following conditions apply to the design of the subsurface drainage system:
(1) Outlets for the underdrain system should be provided for at intervals preferably not exceeding 1000
feet. Outlets may be run into a storm drainage system or natural waterway, depending upon local
regulations.
(2) Pipe underdrains should be placed on grades steeper than 0.5% if possible. Minimum grades of 0.2% are
acceptable.
(3) The depth of the underdrain will depend on the permeability of the soil, the elevation of the water table,
and the amount of drawdown necessary to achieve stability.
(4) The hydraulic design analysis should be made in accordance with ANSI/ASCE 12-92 “Standard
Guidelines for the Design of Urban Subsurface Drainage,” as well as applicable portions of this Manual.
(5) Due to concerns for clogging, a minimum of 12-inch diameter should be considered for all newly
installed underdrains.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-101
3
4
Roadway and Ballast
4.18.6 STRUCTURAL DESIGN (2006)
Due to the wide variety of applications for perforated pipe underdrain systems within and/or adjacent to railroad
subgrades, careful consideration should be given to the pipe material and installation method chosen. Figure 1-429 shows a typical subdrain installed parallel to the track and below the subballast. Consideration should be given
to the railroad live load influence zone to determine the installation requirements and pipe material selection for
the intended application. In addition, the dead load of the soil or ballast material above the pipe must be taken into
consideration. If the installation is beyond the limits of the influence zone, consideration should be given to any
potential live load effects from vehicles and maintenance of way equipment that may operate above the completed
underdrain system. Underdrains installed perpendicular to the track should be installed using the same criteria as
contained elsewhere within this Manual.
Figure 1-4-29. Typical Underdrain Detail
4.18.7 CONSTRUCTION REQUIREMENTS (2006)
The recommended construction method for a typical subdrain installation shall be as follows:
4.18.7.1 EXCAVATION
Trench excavation shall be of such dimensions as to provide ample room for construction. Trench widths shall be
at least 12 inches wider than the outside diameter of the pipe (6-inches either side of the pipe). The bottom of the
trench, in so far as is practical, shall be excavated to permit proper placement of the pipe. The excavation for the
underdrain shall include the removal of any obstructions encountered. Unless otherwise required, the trench shall
be excavated to a depth at least 3 inches below the outside bottom elevation of the planned underdrain.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-102
AREMA Manual for Railway Engineering
Culverts
4.18.7.2 FILTER FABRIC PLACEMENT
The underdrain trench shall be lined with filter fabric. The fabric shall be in intimate contact with the trench and
the bottom of the trench as shown in Figure 1-4-29.
4.18.7.3 SUBGRADE AND FOUNDATION PROPERTIES
Site preparation should be in accordance with the contract plans and specifications. Bedding for subsurface
drainage systems should be as specified and completed to the design line and grade. The pipe shall be laid on
bedding fill shaped to fit the pipe throughout its entire length. The intrusion of foreign material into any portion of
the drainage system due to construction and weather events should be prevented until the system is adequately
protected by backfill. When necessary, all excavations should be dewatered prior to and during installation and
backfilling of the system.
4.18.7.4 LAYING PIPE
a.
The pipe shall be laid true to line and grade with close fitting joints. Joining systems should be “soil tight.”
Joints may be split coupler bands, bell-bell couplers, bell and spigot, or other equally effective joining
systems recommended by the pipe manufacturer. Selection of the allowable configuration of joint shall be as
per the site demands (i.e., steep slopes for the outlet piping would demand a restraining joint system such as
the split coupler band which engages the exterior corrugations of the pipe wall).
b.
Lateral connections shall be made with suitable branch fittings (i.e., tees, wyes, etc.). The upper ends of the
pipe underdrains shall be closed with plugs or endcaps. All appurtenances to the underdrain piping should
be as per the pipe manufacturer’s recommendation for the proposed loading condition. When the total
connected length of the underdrain piping exceeds the limits of available maintenance equipment, clean out
points should be incorporated for maintenance purposes and located at a maximum of 500 feet apart.
c.
Perforated pipe shall be so laid that the perforations are in the bottom half of the pipe (the invert). Where
perforated pipe installations outlet into open ditches, a minimum of 8 feet of pipe from the outlet shall be
non-perforated. Pipe discharge outlets shall be constructed concurrently with the underdrains. Design and
construction details must consider proper protection of the exposed ends of the pipe.
1
3
4.18.7.5 BACKFILLING
a.
b.
After the pipe has been placed, the granular filter material shall be placed for the full width of the trench
around the pipe and shall extend to the bottom of the ballast. Granular backfill is to be placed in a balanced
fashion in maximum loose lifts of 6-10 inches and compacted per the project’s requirements. Compaction
equipment must be of the type and size so as not to damage the pipe. The area above the trench shall be
filled with ballast and compacted to match the ballast profile. (See Figure 1-4-29.)
The pipe underdrains require adequate minimum cover to protect the pipe from vehicle loads – both
temporary construction loads and long-term design loads. Minimum cover heights required must take into
account the type of pipe, vehicle load, and quality of the backfill. Suitable minimum cover limits should be
established in the project specifications.
4.18.8 INSPECTION AND ACCEPTANCE (2006)
4.18.8.1 RECEIVING AND STORING OF MATERIALS
All construction materials must be carefully and thoroughly inspected prior to and during placement. Shipments of
select fill materials and drainage products should be accompanied by certified test reports as required. All drainage
products or drainage system components should be measured to check size, shape, and fit. All materials must be
inspected to ensure that they are free of foreign deposits, defects, and damage. Repairs may be performed on
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-4-103
4
Roadway and Ballast
damaged goods following inspection and approval of the owner and/or project engineer and after consultation with
the manufacturer. Such repairs must follow applicable specifications and accepted industry standards. Materials
should be stored to avoid damage. Observance of any special handling methods required shall be verified and
recorded. The inspector is responsible for monitoring the contractor’s observance of these requirements.
4.18.8.2 CONSTRUCTION INSPECTION
All phases of the installation of the underdrain systems and any related products should be inspected to ensure
that all materials are installed per the manufacturer’s standards and the project specifications. The installation
should be monitored for proper line, grade and joint integrity. Select backfill material shall conform to project
specifications and the proper placement and compaction of this fill material must be verified.
4.18.8.3 FINAL INSPECTION AND ACCEPTANCE
Prior to acceptance, the underdrain system should be inspected. Final inspection may be by means of a closed
circuit television or other acceptable verification method used to supplement the “as-built” drawings of the
underdrain system and to assure that the system was constructed properly.
4.18.9 OPERATION AND MAINTENANCE (2006)
The design engineer or other so qualified individual should prepare an operations and maintenance plan. Guidance
in preparing such a plan can be found in ASCE 14-93 “Standard Guidelines for Operation and Maintenance of
Urban Subsurface Drainage.”
4.18.10 SAFETY PROVISIONS (2006)
Individual railroads may require specific precautions as deemed advisable to insure the safety of the trains, tracks
and construction workers throughout the perforated pipe underdrain installation process, particularly when
installed adjacent to live track. Regardless of the installation methods chosen, the track must be adequately
supported during construction. All procedures involved in the installation must comply with applicable guidelines
and regulations, including FRA and OSHA requirements.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-4-104
AREMA Manual for Railway Engineering
118
Part 5
Pipelines1
— 2008 —
PREAMBLE
The position of the Association is that the encasement of pipelines transporting liquids under pressure across, over,
or under a railroad operating right-of-way, or that railroad right-of-way proposed for future operations, is in the
best interest of the railroad, public, and parties contracting for the crossing.
The encasement, when installed in accordance with the recommended practice of the Association, permits the
pipeline operating company to install a facility of usual design, at or near, a usual depth of cover or a usual
overhead clearance requirement. Installation of the encasement pipe prior to pipeline construction activities
reduces the risk of delay caused by encountering unanticipated facilities, poor subsurface conditions, or difficult
attachment at the crossing location.
1
The encasement affords the pipeline and railroad companies a measure of protection from damage to their
operating facilities resulting from the actions of unauthorized parties, or the errant actions of authorized parties.
Additionally, it shields the pipeline from potential physical damage as a result of derailment, thus reducing the risk
of product loss in the surrounding soil and promoting the earliest possible safe return to operation of the pipeline
facility. By conducting the flow of lost product to the outer limits of the railroad operating right-of-way, the risk of
delay or curtailment of railroad operations during repair and cleanup activities is reduced. Allowing both the
railroad and pipeline companies to resume safe operation of their facilities as quickly as possible following an event
serves the interests of the public, the railroad, and the pipeline company.
3
The Association supports research for engineered encasements that allow cathodic protection and railroad service
protection.
TABLE OF CONTENTS
Section/Article
Description
5.1 Specifications for Pipelines Conveying Flammable Substances . . . . . . . . . . . . . . . . . .
5.1.1 Scope (1993) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.1.2 General Requirements (2002). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.1.3 Steel Carrier Pipe (2002). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.1.4 Plastic Carrier Pipe Conveying Non Liquid Flammable Substances (2002) . . . . . . . . . . .
1
Page
1-5-3
1-5-3
1-5-4
1-5-5
1-5-6
References, Vol. 34, 1933, p. 163, 830; Vol. 42, 1941, pp. 555, 831; Vol 43, 1942, pp. 481, 731; Vol. 54, 1953, pp. 1089, 1385; Vol. 55, 1954,
pp. 692, 1054; Vol. 56, 1955, pp. 688, 1115; Vol. 57, 1956, pp. 645, 1077; Vol. 62, 1961, pp. 692, 938; Vol. 63, 1962, pp. 582, 750; Vol. 65,
1964, pp. 491, 835; Vol. 67, 1966, pp. 527, 739; Vol. 72, 1971, p. 109; Vol. 73, 1972, p. 150; Vol. 92, 1991, p. 39; Vol. 94, p. 42. Latest page
consist: 1 to 19 incl. (1993).
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-1
Roadway and Ballast
TABLE OF CONTENTS (CONT)
Section/Article
5.1.5
5.1.6
5.1.7
5.1.8
Description
Page
Casing Pipe (2002) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Construction (2002) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Approval of Plans (2002) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Execution of Work (1993). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-5-7
1-5-8
1-5-10
1-5-11
5.2 Specifications for Uncased Gas Pipelines within the Railway Right-of-Way. . . . . . . .
5.2.1 Scope (1993) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.2.2 General Requirements (2002) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.2.3 Carrier Pipe (2002) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.2.4 Construction (1993) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.2.5 Approval of Plans (2002) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.2.6 Execution of Work (1993). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.2.7 Commentary (1993) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-5-11
1-5-11
1-5-12
1-5-13
1-5-21
1-5-22
1-5-22
1-5-22
5.3 Specifications for Pipelines Conveying Non-Flammable Substances . . . . . . . . . . . . . .
5.3.1 Scope (1993) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.3.2 General Requirements (2002) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.3.3 Carrier Pipe (2002) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.3.4 Steel Casing Pipe (2002). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.3.5 Construction (2002) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.3.6 Approval of Plans (1993) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.3.7 Execution of Work (1993). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-5-23
1-5-23
1-5-23
1-5-24
1-5-25
1-5-27
1-5-28
1-5-29
5.4 Specifications for Overhead Pipelines Crossings. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.4.1 Scope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.4.2 General Conditions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.4.3 General Design Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.4.4 Structural Elements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.4.5 Inspection and Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-5-29
1-5-29
1-5-29
1-5-29
1-5-30
1-5-31
5.5 Specifications for Fiber Optic “Route” Construction on Railroad Right of Way . . . .
5.5.1 Scope (2001) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.5.2 Planning (2001) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.5.3 Design (2001) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.5.4 Construction (2001) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.5.5 Documentation (2001) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.5.6 Maintenance (2001) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.5.7 Definitions (2001) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.5.8 Abbreviations (2001) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.5.9 Appendix (2001) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-5-31
1-5-31
1-5-32
1-5-32
1-5-37
1-5-40
1-5-41
1-5-42
1-5-45
1-5-46
LIST OF FIGURES
Figure
1-5-1
1-5-2
1-5-3
Description
Page
Casing Pipe Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Uncased Gas Pipelines Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Casing Pipe Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-5-5
1-5-12
1-5-23
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-2
AREMA Manual for Railway Engineering
Pipelines
LIST OF FIGURES (CONT)
Figure
1-5-4
1-5-5
1-5-6
1-5-7
1-5-8
1-5-9
1-5-10
1-5-11
1-5-12
1-5-13
Description
Page
Methodology for Equating Fiber Optic Cable Locations to Railroad Track & Right-of-Way Maps1-5-47
Bridge Definition . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-5-48
Cable Depth Around Culverts and Ditches. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-5-49
Bore Pit Location . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-5-50
Regen Location . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-5-52
Conventional Fill Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-5-53
Standard Turnout . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-5-55
General Shoring Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-5-56
Fill Installation Directional Bore . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-5-57
Installation on Top of Cut . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-5-58
LIST OF TABLES
Table
1-5-1
1-5-2
1-5-3
1-5-4
1-5-5
1-5-6
Description
Minimum Wall Thickness for Steel Casing Pipe for E80 Loading . . . . . . . . . . . . . . . . . . . . . . .
Plan Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Minimum Nominal Wall Thickness (in.) for Uncased Carrier Pipe . . . . . . . . . . . . . . . . . . . . . .
Plan Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Minimum Wall Thickness for Steel Casing Pipe for E80 Loading . . . . . . . . . . . . . . . . . . . . . . .
Plan Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Page
1-5-7
1-5-11
1-5-14
1-5-22
1-5-26
1-5-28
SECTION 5.1 SPECIFICATIONS FOR PIPELINES CONVEYING FLAMMABLE
SUBSTANCES
1
3
5.1.1 SCOPE (1993)
These specifications cover minimum requirements for pipelines installed on or adjacent to railway rights-of-way to
carry liquid flammable products or highly volatile substances under pressure. The term “engineer” used herein
means the chief engineer of the railway company or the authorized representative. These specifications may be
increased when risks from any of the following conditions are increased:
a.
Track speed.
b.
Traffic density.
c.
Traffic sensitivity.
d.
Terrain conditions, cuts/fills, etc.
e.
Curvature and grade.
f.
Bridges and other structures.
g.
Pipe size, capacity and material carried.
h. Environmental risks/damages.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-5-3
4
Roadway and Ballast
5.1.2 GENERAL REQUIREMENTS (2002)
a.
Pipelines under railway tracks and across railway rights-of-way shall be encased in a larger pipe or conduit
called the casing pipe as indicated in Figure 1-5-1. Except for plastic carrier pipe, casing pipe may be
omitted in the following locations:
(1) Under secondary or industry tracks as approved by the engineer.
(2) On pipelines in streets where the stress in the pipe from internal pressure and external loads does not
exceed 40 percent of the specified minimum yield strength (multiplied by longitudinal joint factor) of
the steel pipe material, as approved by the engineer.
(3) On gas pipelines as provided in Section 5.2.
b.
Pipelines shall be installed under tracks by boring or jacking, if practicable.
c.
Pipelines shall be located, where practicable, to cross tracks at approximately right angles thereto but
preferably at not less than 45 degrees and shall not be placed within a culvert, under railway bridges nor
closer than 45 ft. to any portion of any railway bridge, building or important structure, except in special
cases and then by special design as approved by the engineer.
d.
Pipelines carrying flammable substances shall, where practicable, cross any railway where tracks are
carried on an embankment.
e.
Emergency response procedures should be developed to handle a situation in which a pipeline leak or
railroad derailment or incident may jeopardize the integrity of the pipeline. Local conditions should be
considered when developing these procedures.
f.
Where laws or orders of public authority prescribe a higher degree of protection than specified herein, then
the higher degree of protection so prescribed shall be deemed a part of these specifications.
Note 1: See Article 5.1.3
Note 2: See Article 5.1.4
Note 3: See Article 5.1.6.2
Note 4: See Article 5.1.6.4
Note 5: See Article 5.1.6.5
Figure 1-5-1. Casing Pipe Installation
g.
Pipelines and casing pipe shall be suitably insulated from underground conduits carrying electric wires on
railway rights-of-way. All pipelines, except those in streets, shall be prominently marked at the rights-of-way
(on both sides of track for undercrossings) by signs substantially worded thus:
“High pressure…main…in vicinity. Call…”
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-4
AREMA Manual for Railway Engineering
Pipelines
h. Additional signing may be required by the engineer where above signs are not readily visible from the track.
5.1.2.1 Pipeline Inspection and Maintenance
a.
Pipeline owners engaged in the transport of liquid flammable or highly volatile substances are subject to
regulations of the Federal Government. These regulationsrequire certain inspection routines that, in the
general case, are conducted from within the carrier pipe or by non-destructive methods not requiring it be
exposed.
b.
It is the responsibility of the pipeline owner to conduct the necessary inspections without interference to the
operations of the Railway Company. Should it become necessary to expose a pipe for an inspection, or for its
replacement, the owner shall design a procedure that does not interfere with Railway operations, and shall
make prior arrangements with the Railway as may be necessary to permit safe conduct of the work.
c.
Pipeline maintenance shall be limited to the installation of a new carrier pipe in an existing casing, renewal
of carrier and casing pipe separators or the installation of a new crossing. In all cases, the work shall be
conducted in the same manner as in the installation of a new crossing, which is subject to the requirements
of these specifications. Casings abandoned or replaced by new location work shall be backfilled by methods
and materials as directed by the Engineer. The location of abandoned facilities shall be recorded and
records maintained by the pipeline owner.
d.
The owners of pipelines not subject to regulation requiring inspection are expected to inspect their facilities
as a matter of due diligence in the conduct of its business. The Railway may, as a right but not a duty,
require an inspection of the construction, to include receiving a written report of findings certified by a
registered professional engineer. Maintenance of these facilities shall be conducted as above described.
1
5.1.3 STEEL CARRIER PIPE (2002)
a.
Pipelines carrying oil, liquefied petroleum gas and other flammable liquid products shall be of steel and
conform to the requirements of the current ANSI B 31.4 Liquid Transportation Systems for Hydrocarbons,
Liquid Petroleum Gas, Anhydrous Ammonia, and Alcohols, and other applicable ANSI codes, except that the
maximum allowable stresses1 for design of steel pipe shall not exceed the following percentages of the
specified minimum yield strength (multiplied by longitudinal joint factor) of the pipe as defined in the above
codes.
b.
Requisites for steel carrier line pipe under railway tracks shall apply for a minimum distance of 50 ft.
(measured at right angles) from centerline of outside tracks or 2 ft. beyond toe of slope or 25 ft. beyond the
ends of casing (when casing is required), whichever is greater.
c.
The pipe shall be laid with sufficient slack so that it is not in tension.
4
5.1.3.1 Allowable Hoop Stress Due to Internal Pressure
5.1.3.1.1 With Casing Pipe
The following percentages apply to hoop stress in steel pipe within a casing under railway tracks and across
railway rights-of-way:
1
a.
Seventy-two percent on oil pipelines.
b.
Fifty percent for pipelines carrying condensate, natural gasoline, natural gas liquids, liquefied petroleum
gas, and other liquid petroleum products.
c.
Sixty percent for gas pipelines.
If the maximum allowable stress in the carrier pipe on either side of the crossing is less than specified above, the carrier pipe at the
crossing shall be designed at the same stress as the adjacent carrier pipe.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
3
1-5-5
Roadway and Ballast
5.1.3.1.2 Without Casing Pipe
The following percentages apply to hoop stress in steel pipe without a casing under secondary or industry tracks:
a.
Sixty percent for oil pipelines.
b.
Forty percent for pipelines carrying condensate, natural gasoline, natural gas liquids, liquefied petroleum
gas, and other liquid petroleum products.
c.
For gas pipelines see Section 5.2.
5.1.3.1.3 On Right-of-Way
The following percentages apply to hoop stress in steel pipe laid longitudinally on railway rights-of-way:
a.
Sixty percent for oil pipelines.
b.
Forty percent for pipelines carrying condensate, natural gasoline, natural gas liquids, liquefied petroleum
gas, and other liquid petroleum products.
c.
For gas pipelines see Section 5.2.
5.1.4 PLASTIC CARRIER PIPE CONVEYING NON LIQUID FLAMMABLE SUBSTANCES
(2002)
a.
Plastic carrier pipelines shall be encased according to Article 5.1.5.
b.
Plastic carrier pipe material includes thermoplastic and thermoset plastic pipes. Thermoplastic types
include Polyvinyl Chloride (PVC), Acrylonitrile Butadiene Styrene (ABS), Polyethylene (PE), Polybutylene
(PB), Cellulose Acetate Butyrate (CAB) and Styrene Rubber (SR). Thermoset types include Reinforced
Plastic Mortar (RPM), Reinforced Thermosetting Resin (FRP) and Fiberglass Reinforced Plastic (FRP).
c.
Plastic pipe material shall be resistant to the chemicals with which contact can be anticipated. Plastic
carrier pipe shall not be utilized where there is potential for contact with petroleum contaminated soils or
other non-polar organic compounds that may be present in surrounding soils.
d.
Plastic carrier pipe can be utilized to convey flammable gas products provided the pipe material is
compatible with the type of product conveyed and the maximum allowable operating pressure is less than
100 psi. Carrier pipe materials, design and installation shall conform to Code of Federal Regulation 49 CFR
Part 178 to 199, specifically Part 192 and American National Standards Institute (ANSI) B31.3 and B31.8
and ASTM D2513. Codes, specifications and regulations current at time of constructing the pipeline shall
govern the installation of the facility within the railway rights-of-way. The proof testing of the strength of
carrier pipe shall be in accordance with ANSI requirements. Plastic carrier pipelines will be encased
according to Article 5.1.5.
5.1.5 CASING PIPE (2002)
a.
Casing pipe and joints shall be of steel and of leakproof construction, capable of withstanding railway
loading. The inside diameter of the casing pipe shall be large enough to allow the carrier pipe to be removed
subsequently without disturbing the casing pipe. All joints or couplings, supports, insulators or centering
devices for the carrier pipe within a casing under railroad tracks shall be taken into account.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-6
AREMA Manual for Railway Engineering
Pipelines
b.
When casing is installed without benefit of a protective coating or said casing is not cathodically protected,
the wall thickness shall be increased to the nearest standard size which is a minimum of 0.063 in. greater
than the thickness required except for diameters under 12-3/4 in.
Table 1-5-1. Minimum Wall Thickness for Steel Casing Pipe for E80 Loading
When coated or
cathodically protected
Nominal Thickness (inches)
When not coated or
cathodically protected
Nominal Thickness (inches)
12-3/4 and under
0.188
0.188
14
0.188
0.250
16
0.219
0.281
18
0.250
0.312
20 and 22
0.281
0.344
24
0.312
0.375
26
0.344
0.406
28
0.375
0.438
30
0.406
0.469
32
0.438
0.500
34 and 36
0.469
0.531
38
0.500
0.562
40
0.531
0.594
42
0.562
0.625
44 and 46
0.594
0.656
48
0.625
0.688
50
0.656
0.719
52
0.688
0.750
54
0.719
0.781
56 and 58
0.750
0.812
60
0.781
0.844
62
0.812
0.875
64
0.844
0.906
66 and 68
0.875
0.938
70
0.906
0.969
72
0.938
1.000
Nominal Diameter (inches)
1
3
4
5.1.5.1 Steel Casing Pipe
Steel pipe shall have a specified minimum yield strength, SMYS, of at least 35,000 psi.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-5-7
Roadway and Ballast
5.1.5.2 Flexible Casing Pipe
For flexible casing pipe, a maximum vertical deflection of a casing pipe of 3 percent of its diameter plus 1/2 in.
clearance shall be provided so that no loads from the roadbed, track, traffic or casing pipe itself are transmitted to
the carrier pipe. When insulators are used on the carrier pipe, the inside diameter of flexible casing pipe shall be at
least 2 in. greater than the outside diameter of the carrier pipe for pipe less than 8 in. in diameter; at least 3-1/4 in.
greater for pipe 8 in. to 16 in., inclusive, in diameter and at least 4-1/2 in. greater for pipe 18 in. in diameter and
over. Flexible pipe must be able to be electronically located.
5.1.5.3 Length of Casing Pipe
Casing pipe under railway tracks and across railway rights-of-way shall extend to the greater of the following
distances, measured at right angles to centerline of track. If additional tracks are constructed in the future or if the
railway determines that the roadbed should be widened, the casing shall be extended or other special design
incorporated:
a.
2 ft. beyond toe of slope.
b.
3 ft. beyond ditch.
c.
A minimum distance of 25 ft. each side from centerline of outside track when casing is sealed at both ends.
d.
A minimum distance of 45 ft. each side from centerline of outside track when casing is open at both ends.
e.
Plastic carrier pipe conveying flammable substances shall be encased the entire limits of the right-of-way. If
special conditions exist which prevent encasement within the entire limits of the right-of-way, the minimum
encased lengths must be approved by the engineer.
5.1.6 CONSTRUCTION (2002)
a.
Casing pipe shall be so constructed as to prevent leakage of any substance from the casing throughout its
length, except at ends of casing where ends are left open, or through vent pipes when ends of casing are
sealed. Casing shall be so installed as to prevent the formation of a waterway under the railway, and with an
even bearing throughout its length, and shall slope to one end (except for longitudinal occupancy).
b.
Where casing and/or carrier pipe is cathodically protected, the engineer shall be notified and a suitable test
made to ensure that other railway structures and facilities are adequately protected from the cathodic
current in accordance with the recommendation of current Reports of Correlating Committee on Cathodic
Protection, published by the National Association of Corrosion Engineers.
5.1.6.1 Method of Installation
a.
Installations by open-trench methods shall comply with Part 4, Culverts, Section 4.12, Assembly and
Installation of Pipe Culverts, of this Chapter.
b.
Bored or jacked installations shall have a bored hole diameter essentially the same as the outside diameter
of the pipe plus the thickness of the protective coating. If voids should develop or if the bored hole diameter
is greater than the outside diameter of the pipe (including coating) by more than approximately 1 in.,
remedial measures as approved by the engineer shall be taken. Boring operations shall not be stopped if
such stoppage would be detrimental to the railway.
c.
Tunneling operations shall be conducted as approved by the engineer. If voids are caused by the tunneling
operations, they shall be filled by pressure grouting or by other approved methods which will provide proper
support.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-8
AREMA Manual for Railway Engineering
Pipelines
5.1.6.2 Depth of Installation
5.1.6.2.1 Casing Pipe
Casing pipe under railway tracks and across railway rights-of-way shall be not less than 5-1/2 ft. from base of
railway rail to top of casing at its closest point, except that under secondary or industry tracks this distance may be
4-1/2 ft. On other portions of rights-of-way where casing is not directly beneath any track, the depth from ground
surface or from bottom of ditches to top of casing shall not be less than 3 ft.
5.1.6.2.2 Carrier Pipe
Steel carrier pipe installed under secondary or industry tracks without benefit of casing shall be not less than 10 ft.
from base of railway rail to top of pipe at its closest point nor less than 6 ft. from ground surface or from bottom of
ditches. Plastic carrier pipe must be encased under secondary or industry tracks within the limits of the right-ofway.
5.1.6.3 Inspection and Testing
ANSI Codes current at time of constructing the pipeline, shall govern the inspection and testing of the facility
within the railway rights-of-way except as follows:
a.
One-hundred percent of all steel pipe field welds shall be inspected by radiographic examination, and such
field welds shall be inspected for 100 percent of the circumference.
b.
The proof testing of the strength of carrier pipe shall be in accordance with ANSI requirements.
1
5.1.6.4 Seals
a.
Where ends of casing are below ground they shall be suitably sealed.
b.
Where ends of casing are at or above ground surface and above high-water level they may be left open,
provided drainage is afforded in such manner that leakage will be conducted away from railway tracks or
structure. Where proper drainage is not provided, the ends of casing shall be sealed.
3
5.1.6.5 Vents
Casing pipe, when sealed, shall be properly vented. Vent pipes shall be of sufficient diameter, but in no case less
than 2 in. in diameter, shall be attached near end of casing and project through ground surface at right-of-way lines
or not less than 45 ft. (measured at right angles) from centerline of nearest track. Vent pipe, or pipes, shall extend
not less than 4 ft. above ground surface. Top of vent pipe shall be fitted with down-turned elbow properly screened,
or a relief valve. Vents in locations subject to high water shall be extended above the maximum elevation of high
water and shall be supported and protected in a manner that meets the approval of the engineer. Vent pipes shall
be no closer than 4 ft. (vertically) from aerial electric wires.
5.1.6.6 Shut-Off Valves
Accessible emergency shut-off valves shall be installed within effective distances each side of the railway as
mutually agreed to by the engineer and the pipeline company. These valves should be marked with signs for
identification. Where pipelines are provided with automatic control stations at locations and within distances
approved by the engineer, no additional valves shall be required.
5.1.6.7 Longitudinal Pipelines
Longitudinal pipelines should be located as far as possible from any track. They must not be within 25 ft. of any
track and must have a minimum of 6 ft. ground cover over the pipeline up to 50 ft., measured from the track
centerline. Where pipeline is laid more than 50 ft. from centerline of track, minimum cover shall be at least 5 ft.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-5-9
4
Roadway and Ballast
Pipelines must be marked by a sign approved by the engineer every 500 ft. and at every road crossing, streambed,
other utility crossing, and at locations of major change in direction of the line. Longitudinal carrier pipeline shall
be steel. Plastic carrier pipe may be utilized for longitudinal installation with approval by the engineer, but shall
be encased within the limits of the right-of-way. Casing may be omitted with approval of the engineer, provided
that minimum burial depth is increased to comply with the most conservative requirements of either: the
engineer’s instructions, current ANSI specifications, current OSHA regulations, or local regulatory agency
specifications.
5.1.7 APPROVAL OF PLANS (2002)
a.
Plans for proposed installation shall be submitted to and meet the approval of the engineer before
construction is begun.
b.
Plans shall be drawn to scale showing the relation of the proposed pipeline to railway tracks, angle of
crossing, location of valves, railway survey station, right-of-way lines and general layout of tracks and
railway facilities. Plans should also show a cross section (or sections) from field survey, showing pipe in
relation to actual profile of ground and tracks. If open-cutting or tunneling is necessary, details of sheeting
and method of supporting tracks or driving tunnel shall be shown.
c.
In addition to the above, plans should contain the following data:
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-10
AREMA Manual for Railway Engineering
Pipelines
Table 1-5-2. Plan Data
Carrier Pipe
Casing Pipe
Contents to be handled
Outside Diameter
Pipe Material
Specification and grade
Wall thickness
Actual Working pressure
Type of joint
Coating
Method of installation
Vents: Number:
Size:
Seals: Both ends:
Height above ground:
One end:
Type:
Bury: Base of rail to top of casing:
Bury: (Not beneath tracks)
ft.
in.
ft.
Bury: (Roadway ditches)
ft.
1
in.
in.
Type, size and spacing of insulators or supports:
Distance C.L. track to face of jacking/receiving pits
ft.
in.
Bury: Base of rail to bottom jacking/receiving pits
ft.
in.
Cathodic protection:
Yes No
3

5.1.8 EXECUTION OF WORK (1993)
4
The execution of work on railway rights-of-way, including the supporting of tracks, shall be subject to the
inspection and direction of the engineer.
SECTION 5.2 SPECIFICATIONS FOR UNCASED GAS PIPELINES WITHIN THE RAILWAY
RIGHT-OF-WAY
5.2.1 SCOPE (1993)
These specifications cover minimum specifications for pipelines installed on or adjacent to railway rights-of-way to
carry flammable and nonflammable gas products which, from their nature or pressure, might cause damage if
escaping on or in the vicinity of railway property. The term “engineer” as used herein means the chief engineer of
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-5-11
Roadway and Ballast
the railway company or the authorized representative. These specifications may be increased when risks from any
of the following conditions are increased:
a.
Track Speed.
b.
Traffic density.
c.
Traffic sensitivity.
d.
Terrain conditions, cuts/fills, etc.
e.
Curvature and grade.
f.
Bridges and other structures.
g.
Pipe size, capacity and material carried.
h. Environmental risks/damages.
5.2.2 GENERAL REQUIREMENTS (2002)
a.
Pipelines shall be installed under tracks by boring or jacking, if practicable.
b.
Pipelines shall be located, where practicable, to cross tracks at approximately 90 degrees but not less than
45 degrees, and shall not be placed within a culvert, under railway bridges, nor closer than 45 ft. to any
portion of any railway bridge, building or other important structure, except in special cases and then by
special design as approved by the engineer.
c.
Pipelines carrying flammable gas products shall, where practicable, cross any railway where tracks are
carried on an embankment.
d.
Emergency response procedures should be developed to handle a situation in which a pipeline leak or
railroad derailment or incident may jeopardize the integrity of the pipeline. Local conditions should be
considered when developing these procedures.
e.
Uncased gas pipelines under railroad track and on right-of-way shall be installed as indicated in Figure 1-52.
Note 1: See Article 5.2.3.2
Note 2: See Article 5.2.4.2
Figure 1-5-2. Uncased Gas Pipelines Installation
f.
Where laws or orders of public authority prescribe a higher degree of protection than specified herein, then
the higher degree of protection so prescribed shall be deemed a part of these specifications.
g.
Pipelines and casing pipe shall be suitably insulated from underground conduits carrying electric wires on
railway rights-of-way. All pipelines, except those in streets, shall be prominently marked at the rights-of-way
(on both sides of track for undercrossings) by signs substantially worded thus:
“High pressure…main…in vicinity. Call…”
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-12
AREMA Manual for Railway Engineering
Pipelines
h. Additional signing may be required by the engineer where above signs are not readily visible from the track.
5.2.2.1 Pipeline Inspection and Maintenance
a.
Pipeline owners engaged in the transport of flammable and non-flammable gas products are subject to
regulations of the Federal Government. These regulations require certain inspection routines that, in the
general case, are conducted from within the carrier pipe or by non-destructive methods not requiring it be
exposed.
b.
It is the responsibility of the pipeline owner to conduct the necessary inspections without interference to the
operations of the Railway Company. Should it become necessary to expose a pipe for an inspection, or for its
replacement, the owner shall design a procedure that does not interfere with Railway operations, and shall
make prior arrangements with the Railway as may be necessary to permit safe conduct of the work.
c.
Pipeline maintenance shall be limited to the installation of a new carrier pipe at a new crossing location,
which is subject to the requirements of these specifications. Carrier pipes abandoned by new location work
shall be backfilled by methods and materials as directed by the Engineer. The location of abandoned
facilities shall be recorded and records maintained by the pipeline owner.
d.
The owners of pipelines not subject to regulation requiring inspection are expected to inspect their facilities
as a matter of due diligence in the conduct of its business. The Railway may, as a right but not a duty,
require an inspection of the construction, to include receiving a written report of findings certified by a
registered professional engineer. Maintenance of these facilities shall be conducted as above described.
5.2.3 CARRIER PIPE (2002)
1
a.
Pipelines carrying flammable and nonflammable gas products shall be of steel and shall conform to the
requirements of the current ANSI B 31.8 Gas Transmission and Distribution Piping Systems, and other
applicable ANSI codes.
b.
Carrier line pipe construction shall be approved by the engineer. Joints for carrier line pipe must be of an
approved welded type. Steel pipe must have a specified minimum yield strength, SMYS, of at least 35,000
psi. The nominal wall thickness for the steel carrier pipe, specified minimum yield strength, SMYS,
maximum allowable operating pressure, MAOP, and outside pipe diameter, D, are given in Table 1-5-3.
c.
3
These Table 1-5-3 wall thicknesses are based on four design criteria. These design criteria consider:
(1) The maximum allowable hoop stress due to internal pressure as specified in regulatory codes;
(2) The maximum combined multiaxial stress due to external and internal loads;
4
(3) Fatigue in girth welds due to external live loads;
(4) Fatigue in longitudinal seam welds due to external live loads.
d.
The greatest wall thickness resulting from each of the design conditions are shown in Table 1-5-3.
e.
Design parameter assumptions used to calculate the Table 1-5-3 wall thicknesses are as follows:
• Depth of carrier from base of rail is 10 ft.
• Double Track condition is assumed.
• Modulus of Soil Reaction E´ = 500 psi.
• Soil Resilient Modulus Er = 10,000 psi.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-5-13
Roadway and Ballast
• Girth weld is located at centerline of track.
• Overbore of 2" over pipe diameter during installation.
• Class location design factor F = 0.6 used in design criterion paragraph c(1) given above.
• Factor of Safety FS = 1.5 used in design criteria b, c, and d given above.
f.
See “Design of Uncased Pipeline at Railroad Crossings” as referenced in Article 5.2.7 for additional details
on the design parameters used to determine the wall thickness.
g.
If actual crossing conditions fall outside these parameters, tending to require a thicker walled pipe, a
detailed analysis must be performed using the design methodology referenced in Article 5.2.7. Design
calculations must be provided for railroad review when conditions outside those above are present.
Table 1-5-3. Minimum Nominal Wall Thickness (in.) for Uncased Carrier Pipe
D (in.)
SMYS (psi)
35000
42000
52000
SMYS (psi)
60000
70000
35000
MAOP < 100 psi
42000
52000
60000
70000
MAOP < 200 psi
< 18.0
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
20.0
0.219
0.219
0.219
0.219
0.219
0.219
0.219
0.219
0.219
0.219
22.0
0.226
0.226
0.226
0.226
0.226
0.226
0.226
0.226
0.226
0.226
24.0
0.250
0.250
0.250
0.250
0.250
0.250
0.250
0.250
0.250
0.250
26.0
0.281
0.281
0.281
0.281
0.281
0.281
0.281
0.281
0.281
0.281
28.0
0.281
0.281
0.281
0.281
0.281
0.312
0.281
0.281
0.281
0.281
30.0
0.312
0.312
0.312
0.312
0.312
0.344
0.312
0.312
0.312
0.312
32.0
0.344
0.344
0.344
0.344
0.344
0.344
0.344
0.344
0.344
0.344
34.0
0.344
0.344
0.344
0.344
0.344
0.406
0.344
0.344
0.344
0.344
36.0
0.375
0.375
0.375
0.375
0.375
0.406
0.375
0.375
0.375
0.375
38.0
0.406
0.406
0.406
0.406
0.406
0.438
0.406
0.406
0.406
0.406
40.0
0.406
0.406
0.406
0.406
0.406
0.469
0.406
0.406
0.406
0.406
42.0
0.438
0.438
0.438
0.438
0.438
0.500
0.438
0.438
0.438
0.438
MAOP < 300 psi
< 12.75
MAOP < 400 psi
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
14.0
0.188
0.188
0.188
0.188
0.188
0.203
0.188
0.188
0.188
0.188
16.0
0.188
0.188
0.188
0.188
0.188
0.281
0.188
0.188
0.188
0.188
18.0
0.219
0.188
0.188
0.188
0.188
0.281
0.219
0.188
0.188
0.188
20.0
0.250
0.219
0.219
0.219
0.219
0.312
0.250
0.219
0.219
0.219
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-14
AREMA Manual for Railway Engineering
Pipelines
Table 1-5-3. Minimum Nominal Wall Thickness (in.) for Uncased Carrier Pipe (Continued)
D (in.)
SMYS (psi)
35000
42000
52000
SMYS (psi)
60000
70000
35000
MAOP < 300 psi - Continued
42000
52000
60000
70000
MAOP < 400 psi - Continued
22.0
0.281
0.226
0.226
0.226
0.226
0.344
0.281
0.226
0.226
0.226
24.0
0.312
0.250
0.250
0.250
0.250
0.375
0.281
0.250
0.250
0.250
26.0
0.344
0.281
0.281
0.281
0.281
0.406
0.312
0.281
0.281
0.281
28.0
0.375
0.312
0.281
0.281
0.281
0.438
0.344
0.281
0.281
0.281
30.0
0.406
0.312
0.312
0.312
0.312
0.469
0.375
0.312
0.312
0.312
32.0
0.438
0.344
0.344
0.344
0.344
0.500
0.406
0.344
0.344
0.344
34.0
0.469
0.375
0.344
0.344
0.344
0.531
0.438
0.344
0.344
0.344
36.0
0.500
0.406
0.375
0.375
0.375
0.562
0.469
0.375
0.375
0.375
38.0
0.531
0.438
0.406
0.406
0.406
0.625
0.500
0.406
0.406
0.406
40.0
0.562
0.469
0.406
0.406
0.406
0.656
0.531
0.406
0.406
0.406
42.0
0.594
0.500
0.438
0.438
0.438
0.688
0.562
0.438
0.438
0.438
MAOP < 500 psi
< 8.625
MAOP < 600 psi
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
10.75
0.188
0.188
0.188
0.188
0.188
0.203
0.188
0.188
0.188
0.188
12.75
0.219
0.188
0.188
0.188
0.188
0.250
0.203
0.188
0.188
0.188
14.0
0.250
0.188
0.188
0.188
0.188
0.281
0.210
0.188
0.188
0.188
16.0
0.281
0.219
0.188
0.188
0.188
0.312
0.250
0.188
0.188
0.188
18.0
0.312
0.250
0.188
0.188
0.188
0.344
0.281
0.219
0.188
0.188
20.0
0.344
0.281
0.219
0.219
0.219
0.375
0.312
0.250
0.219
0.219
22.0
0.375
0.312
0.250
0.226
0.226
0.438
0.344
0.281
0.226
0.226
24.0
0.406
0.344
0.281
0.250
0.250
0.469
0.375
0.312
0.250
0.250
26.0
0.469
0.375
0.281
0.281
0.281
0.500
0.406
0.344
0.281
0.281
28.0
0.500
0.406
0.312
0.281
0.281
0.562
0.469
0.375
0.312
0.312
30.0
0.531
0.438
0.344
0.312
0.312
0.594
0.500
0.406
0.344
0.312
32.0
0.562
0.469
0.375
0.344
0.344
0.625
0.531
0.406
0.375
0.344
34.0
0.625
0.500
0.406
0.344
0.344
0.688
0.562
0.438
0.375
0.344
36.0
0.656
0.531
0.438
0.375
0.375
0.719
0.594
0.469
0.406
0.375
38.0
0.688
0.562
0.469
0.406
0.406
0.750
0.625
0.500
0.438
0.406
40.0
0.719
0.594
0.500
0.406
0.406
0.781
0.688
0.531
0.469
0.438
42.0
0.750
0.656
0.500
0.438
0.438
0.844
0.719
0.562
0.500
0.469
MAOP < 700 psi
MAOP < 800 psi
< 6.625
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
8.625
0.188
0.188
0.188
0.188
0.188
0.203
0.188
0.188
0.188
0.188
0.219
0.188
0.188
0.188
0.188
0.250
0.203
0.188
0.188
0.188
10.75
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-5-15
1
3
4
Roadway and Ballast
Table 1-5-3. Minimum Nominal Wall Thickness (in.) for Uncased Carrier Pipe (Continued)
D (in.)
SMYS (psi)
35000
42000
52000
SMYS (psi)
60000
70000
35000
MAOP < 700 psi - Continued
42000
52000
60000
70000
MAOP < 800 psi - Continued
12.75
0.281
0.219
0.188
0.188
0.188
0.312
0.250
0.188
0.188
0.188
14.0
0.312
0.250
0.188
0.188
0.188
0.344
0.281
0.219
0.188
0.188
16.0
0.344
0.281
0.219
0.188
0.188
0.375
0.312
0.250
0.219
0.188
18.0
0.375
0.312
0.250
0.219
0.219
0.438
0.344
0.281
0.226
0.219
20.0
0.438
0.344
0.281
0.226
0.226
0.469
0.406
0.312
0.250
0.250
22.0
0.469
0.406
0.312
0.281
0.226
0.500
0.438
0.344
0.281
0.250
24.0
0.500
0.438
0.344
0.281
0.250
0.562
0.469
0.375
0.312
0.281
26.0
0.562
0.469
0.375
0.312
0.281
0.625
0.500
0.406
0.344
0.312
28.0
0.594
0.500
0.406
0.344
0.281
0.656
0.562
0.438
0.375
0.312
30.0
0.656
0.531
0.438
0.375
0.312
0.719
0.594
0.469
0.406
0.344
32.0
0.688
0.562
0.469
0.406
0.344
0.750
0.625
0.500
0.438
0.375
34.0
0.750
0.625
0.500
0.438
0.375
0.812
0.688
0.531
0.469
0.406
36.0
0.781
0.656
0.531
0.469
0.375
0.844
0.719
0.562
0.500
0.438
38.0
0.844
0.688
0.562
0.500
0.406
0.906
0.750
0.625
0.531
0.438
40.0
0.875
0.750
0.594
0.500
0.438
0.938
0.812
0.656
0.562
0.469
42.0
0.938
0.781
0.625
0.531
0.469
1.000
0.844
0.688
0.594
0.500
MAOP < 900 psi
MAOP < 1000 psi
< 6.625
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
8.625
0.219
0.188
0.188
0.188
0.188
0.250
0.188
0.188
0.188
0.188
10.75
0.279
0.219
0.188
0.188
0.188
0.307
0.250
0.188
0.188
0.188
12.75
0.312
0.281
0.219
0.188
0.188
0.344
0.281
0.250
0.188
0.188
14.0
0.344
0.312
0.250
0.203
0.188
0.375
0.312
0.250
0.219
0.188
16.0
0.406
0.344
0.281
0.219
0.188
0.438
0.375
0.312
0.250
0.219
18.0
0.469
0.375
0.312
0.250
0.219
0.500
0.406
0.344
0.281
0.250
20.0
0.500
0.438
0.344
0.281
0.250
0.562
0.469
0.375
0.312
0.281
22.0
0.562
0.469
0.375
0.312
0.281
0.625
0.500
0.406
0.344
0.281
24.0
0.625
0.500
0.406
0.344
0.312
0.688
0.562
0.438
0.375
0.312
26.0
0.656
0.562
0.438
0.375
0.312
0.750
0.594
0.469
0.406
0.344
28.0
0.719
0.594
0.469
0.406
0.344
0.750
0.656
0.531
0.438
0.375
30.0
0.750
0.625
0.500
0.438
0.375
0.812
0.688
0.562
0.469
0.406
32.0
0.812
0.688
0.562
0.469
0.406
0.875
0.719
0.594
0.531
0.438
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-16
AREMA Manual for Railway Engineering
Pipelines
Table 1-5-3. Minimum Nominal Wall Thickness (in.) for Uncased Carrier Pipe (Continued)
D (in.)
SMYS (psi)
35000
42000
52000
SMYS (psi)
60000
70000
35000
MAOP < 900 psi - Continued
42000
52000
60000
70000
MAOP < 1000 psi - Continued
34.0
0.875
0.719
0.594
0.500
0.438
0.938
0.781
0.625
0.562
0.469
36.0
0.906
0.781
0.625
0.531
0.469
1.000
0.812
0.688
0.594
0.500
38.0
0.969
0.812
0.656
0.562
0.500
1.062
0.875
0.719
0.625
0.531
40.0
1.031
0.875
0.688
0.625
0.531
1.125
0.906
0.750
0.656
0.562
42.0
1.062
0.906
0.750
0.656
0.562
1.188
0.969
0.781
0.688
0.594
MAOP < 1100 psi
MAOP < 1200 psi
< 5.563
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
6.625
0.188
0.188
0.188
0.188
0.188
0.203
0.188
0.188
0.188
0.188
8.625
0.250
0.203
0.188
0.188
0.188
0.277
0.219
0.188
0.188
0.188
10.75
0.307
0.250
0.203
0.188
0.188
0.344
0.277
0.219
0.188
0.188
12.75
0.375
0.312
0.250
0.219
0.188
0.406
0.330
0.281
0.226
0.188
14.0
0.406
0.344
0.281
0.226
0.219
0.438
0.375
0.312
0.250
0.219
16.0
0.469
0.406
0.312
0.281
0.219
0.500
0.406
0.344
0.281
0.250
18.0
0.531
0.438
0.344
0.312
0.250
0.562
0.469
0.375
0.344
0.281
20.0
0.594
0.500
0.406
0.344
0.281
0.625
0.531
0.438
0.375
0.312
22.0
0.625
0.531
0.438
0.375
0.312
0.688
0.562
0.469
0.406
0.344
24.0
0.688
0.594
0.469
0.406
0.344
0.750
0.625
0.500
0.438
0.375
26.0
0.750
0.625
0.500
0.438
0.375
0.812
0.688
0.562
0.469
0.406
28.0
0.812
0.688
0.562
0.469
0.406
0.875
0.719
0.594
0.500
0.438
30.0
0.875
0.750
0.594
0.531
0.438
0.938
0.812
0.625
0.562
0.469
32.0
0.938
0.781
0.625
0.562
0.469
1.000
0.875
0.688
0.594
0.500
34.0
1.000
0.844
0.688
0.594
0.500
1.062
0.875
0.719
0.625
0.531
36.0
1.062
0.875
0.719
0.625
0.531
1.125
0.938
0.750
0.656
0.562
38.0
1.125
0.938
0.750
0.656
0.562
1.188
1.000
0.812
0.719
0.594
40.0
1.156
0.969
0.812
0.688
0.594
1.250
1.031
0.844
0.750
0.625
42.0
1.250
1.031
0.844
0.750
0.625
1.312
1.094
0.906
0.781
0.656
MAOP < 1300 psi
MAOP < 1400 psi
< 5.563
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
6.625
0.219
0.188
0.188
0.188
0.188
0.250
0.188
0.188
0.188
0.188
8.625
0.277
0.250
0.188
0.188
0.188
0.312
0.250
0.219
0.188
0.188
0.344
0.307
0.250
0.203
0.188
0.365
0.307
0.250
0.219
0.219
10.75
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-5-17
1
3
4
Roadway and Ballast
Table 1-5-3. Minimum Nominal Wall Thickness (in.) for Uncased Carrier Pipe (Continued)
D (in.)
SMYS (psi)
35000
42000
52000
SMYS (psi)
60000
70000
35000
MAOP < 1300 psi - Continued
42000
52000
60000
70000
MAOP < 1400 psi - Continued
12.75
0.438
0.344
0.281
0.256
0.219
0.438
0.375
0.312
0.256
0.250
14.0
0.469
0.375
0.312
0.279
0.226
0.500
0.406
0.344
0.281
0.281
16.0
0.531
0.438
0.375
0.312
0.281
0.562
0.469
0.375
0.344
0.312
18.0
0.594
0.500
0.406
0.344
0.312
0.625
0.531
0.438
0.375
0.344
20.0
0.656
0.562
0.438
0.375
0.344
0.688
0.594
0.469
0.406
0.375
22.0
0.719
0.594
0.500
0.438
0.406
0.750
0.656
0.531
0.469
0.375
24.0
0.812
0.656
0.531
0.469
0.406
0.844
0.688
0.562
0.500
0.438
26.0
0.844
0.719
0.594
0.500
0.438
0.906
0.750
0.625
0.531
0.469
28.0
0.906
0.781
0.625
0.531
0.469
0.969
0.812
0.656
0.594
0.500
30.0
0.969
0.812
0.688
0.594
0.500
1.031
0.875
0.719
0.625
0.531
32.0
1.031
0.875
0.719
0.625
0.531
1.094
0.938
0.750
0.656
0.562
34.0
1.125
0.938
0.750
0.656
0.562
1.156
1.000
0.812
0.719
0.594
36.0
1.188
1.000
0.812
0.719
0.625
1.250
1.062
0.875
0.750
0.656
38.0
1.250
1.062
0.844
0.750
0.656
1.312
1.094
0.906
0.781
0.688
40.0
1.312
1.094
0.906
0.781
0.688
1.375
1.156
0.938
0.844
0.719
42.0
1.375
1.156
0.938
0.844
0.719
1.469
1.219
1.000
0.875
0.750
MAOP < 1500 psi
< 4.5
MAOP < 1600 psi
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
5.563
0.219
0.188
0.188
0.188
0.188
0.219
0.188
0.188
0.188
0.188
6.625
0.250
0.203
0.188
0.188
0.188
0.280
0.219
0.188
0.188
0.188
8.625
0.312
0.277
0.219
0.188
0.188
0.344
0.277
0.250
0.219
0.188
10.75
0.406
0.344
0.279
0.226
0.219
0.438
0.344
0.279
0.250
0.219
12.75
0.469
0.406
0.312
0.281
0.250
0.500
0.406
0.344
0.312
0.250
14.0
0.500
0.438
0.344
0.312
0.250
0.562
0.469
0.375
0.312
0.281
16.0
0.594
0.500
0.406
0.344
0.312
0.625
0.531
0.438
0.375
0.312
18.0
0.656
0.562
0.469
0.406
0.344
0.688
0.594
0.469
0.406
0.344
20.0
0.719
0.625
0.494
0.438
0.375
0.781
0.656
0.531
0.469
0.406
22.0
0.812
0.688
0.562
0.469
0.406
0.844
0.719
0.594
0.500
0.438
24.0
0.875
0.750
0.594
0.531
0.438
0.938
0.781
0.625
0.562
0.469
26.0
0.938
0.812
0.656
0.562
0.500
1.000
0.844
0.688
0.594
0.500
28.0
1.031
0.875
0.688
0.625
0.531
1.062
0.906
0.750
0.656
0.562
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-18
AREMA Manual for Railway Engineering
Pipelines
Table 1-5-3. Minimum Nominal Wall Thickness (in.) for Uncased Carrier Pipe (Continued)
D (in.)
SMYS (psi)
35000
42000
52000
SMYS (psi)
60000
70000
35000
MAOP < 1500 psi - Continued
42000
52000
60000
70000
MAOP < 1600 psi - Continued
30.0
1.094
0.938
0.750
0.656
0.562
1.156
0.969
0.781
0.688
0.594
32.0
1.156
0.969
0.812
0.688
0.594
1.219
1.031
0.844
0.719
0.625
34.0
1.250
1.031
0.844
0.750
0.625
1.312
1.094
0.906
0.781
0.656
36.0
1.312
1.094
0.906
0.781
0.688
1.375
1.156
0.938
0.812
0.719
38.0
1.375
1.156
0.938
0.844
0.719
1.469
1.219
1.000
0.875
0.750
40.0
1.438
1.219
1.000
0.875
0.750
1.531
1.281
1.062
0.906
0.781
42.0
1.531
1.281
1.062
0.938
0.781
—
1.344
1.094
0.969
0.844
MAOP < 1700 psi
MAOP < 1800 psi
< 4.0
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
4.5
0.188
0.188
0.188
0.188
0.188
0.203
0.188
0.188
0.188
0.188
5.563
0.258
0.188
0.188
0.188
0.188
0.258
0.219
0.188
0.188
0.188
6.625
0.280
0.250
0.188
0.188
0.188
0.312
0.250
0.219
0.188
0.188
8.625
0.375
0.312
0.250
0.219
0.188
0.375
0.312
0.250
0.219
0.188
10.75
0.438
0.365
0.312
0.256
0.219
0.469
0.406
0.312
0.279
0.250
12.75
0.531
0.438
0.375
0.312
0.281
0.562
0.469
0.375
0.344
0.281
14.0
0.594
0.500
0.406
0.344
0.312
0.625
0.500
0.406
0.375
0.312
16.0
0.656
0.562
0.438
0.406
0.344
0.688
0.594
0.469
0.406
0.344
18.0
0.750
0.625
0.500
0.438
0.375
0.781
0.656
0.531
0.469
0.406
20.0
0.812
0.688
0.562
0.500
0.406
0.875
0.719
0.594
0.500
0.438
22.0
0.906
0.750
0.625
0.531
0.469
0.969
0.781
0.656
0.562
0.500
24.0
1.000
0.812
0.656
0.594
0.500
1.031
0.875
0.719
0.625
0.531
26.0
1.062
0.906
0.719
0.625
0.531
1.125
0.938
0.750
0.656
0.562
28.0
1.156
0.969
0.781
0.688
0.594
1.219
1.000
0.812
0.719
0.625
30.0
1.219
1.031
0.844
0.719
0.625
1.312
1.094
0.875
0.750
0.656
32.0
1.312
1.094
0.875
0.781
0.656
1.375
1.156
0.938
0.812
0.688
34.0
1.375
1.156
0.938
0.812
0.688
1.500
1.219
1.000
0.875
0.750
36.0
1.469
1.219
1.000
0.875
0.750
1.562
1.312
1.062
0.906
0.781
38.0
1.562
1.312
1.062
0.906
0.781
—
1.375
1.125
0.969
0.844
40.0
—
1.375
1.094
0.969
0.844
—
1.438
1.156
1.000
0.875
42.0
—
1.438
1.156
1.000
0.875
—
1.500
1.219
1.062
0.906
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-5-19
1
3
4
Roadway and Ballast
Table 1-5-3. Minimum Nominal Wall Thickness (in.) for Uncased Carrier Pipe (Continued)
D (in.)
SMYS (psi)
35000
42000
52000
SMYS (psi)
60000
70000
35000
MAOP < 1900 psi
42000
52000
60000
70000
MAOP < 2000 psi
< 3.5
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
0.188
4.0
0.188
0.188
0.188
0.188
0.188
0.219
0.188
0.188
0.188
0.188
4.5
0.219
0.188
0.188
0.188
0.188
0.219
0.188
0.188
0.188
0.188
5.563
0.258
0.219
0.188
0.188
0.188
0.281
0.250
0.188
0.188
0.188
6.625
0.312
0.250
0.219
0.188
0.188
0.344
0.280
0.219
0.188
0.188
8.625
0.406
0.344
0.281
0.277
0.219
0.438
0.344
0.281
0.250
0.219
10.75
0.500
0.406
0.344
0.312
0.250
0.531
0.438
0.375
0.312
0.256
12.75
0.594
0.500
0.406
0.344
0.312
0.625
0.531
0.438
0.375
0.312
14.0
0.656
0.531
0.438
0.375
0.344
0.688
0.562
0.469
0.406
0.344
16.0
0.750
0.625
0.500
0.438
0.375
0.781
0.656
0.531
0.469
0.406
18.0
0.812
0.688
0.562
0.500
0.438
0.875
0.719
0.594
0.500
0.438
20.0
0.906
0.781
0.625
0.531
0.469
0.969
0.812
0.656
0.562
0.500
22.0
1.000
0.844
0.688
0.594
0.500
1.062
0.875
0.719
0.625
0.531
24.0
1.094
0.906
0.750
0.656
0.562
1.156
0.969
0.781
0.688
0.594
26.0
1.188
1.000
0.812
0.688
0.594
1.250
1.062
0.844
0.750
0.625
28.0
1.312
1.062
0.875
0.750
0.656
1.344
1.125
0.906
0.781
0.688
30.0
1.375
1.156
0.938
0.812
0.688
1.438
1.219
0.969
0.844
0.719
32.0
1.469
1.219
1.000
0.844
0.750
1.531
1.281
1.031
0.906
0.781
34.0
1.562
1.312
1.062
0.906
0.781
—
1.375
1.094
0.969
0.812
36.0
—
1.375
1.125
0.969
0.844
—
1.438
1.156
1.000
0.875
38.0
—
1.438
1.188
1.031
0.875
—
1.531
1.219
1.062
0.906
40.0
—
1.531
1.219
1.062
0.906
—
—
1.312
1.125
0.969
42.0
—
—
1.281
1.125
0.969
—
—
1.375
1.188
1.000
5.2.3.1 Allowable Hoop Stress Due to Internal Pressure
The maximum allowable hoop stress due to internal pressure shall be sixty percent of SMYS or per ANSI Code if
lower allowable percentage of hoop stress applies.
5.2.3.2 Length of Special Carrier Pipe
Carrier pipe, with nominal wall thickness greater than or equal to those shown in Table 1-5-3, shall extend from
right-of-way line to right-of-way line, or 25 ft. from centerline track, whichever distance is greater, unless special
conditions exist which prevent this from occurring or as approved by the engineer.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-20
AREMA Manual for Railway Engineering
Pipelines
5.2.3.3 Cathodic Protection
a.
Carrier pipes must be coated and cathodically protected to industry standards and test sites for monitoring
pipeline provided within 50 ft. of crossing.
b.
Where carrier pipe is cathodically protected, the engineer shall be notified and a suitable test made to
ensure that other railway structures and facilities are adequately protected from the cathodic current in
accordance with the recommendation of current Reports of Correlating Committee on Cathodic Protection,
published by the National Association of Corrosion Engineers.
5.2.4 CONSTRUCTION (1993)
5.2.4.1 Special Protection
When the engineer determines there is a possibility of having foreign materials in the subgrade, unusual potential
for third party damage exists, or for other reasons, special protection of the carrier pipe will be required. Special
protection may require concrete jacketed steel pipe be used, or protection slabs be placed above the pipe, the depth
of burial increased, or other means. Soil borings may also be required to determine soil characteristics and to
identify if foreign material is present in the bore.
5.2.4.2 Depth of Burial
a.
b.
Carrier line pipe under railway tracks shall not be less than 10 ft. from the base of railway rail to the top of
the pipe at its closest point. At all other locations on the rights-of-way the minimum ground cover must be 6
ft. Where it is not possible to secure the above depths, casings as specified in Section 5.1, Specifications for
Pipelines Conveying Flammable Substances, or other means of protection, will be required.
1
The Inspection and Testing, and Shutoff Valves specifications are the same as in Section 5.1, Specifications
for Pipelines Conveying Flammable Substances, Article 5.1.6.3 and Article 5.1.6.6 respectively.
5.2.4.3 Longitudinal Pipelines
Longitudinal pipelines should be located as far as possible from any track. They must not be within 25 ft. from the
centerline of any track and must have a minimum of 6 ft. ground cover over the pipeline up to 50 ft. from
centerline of track. Where pipeline is laid more than 50 ft. from centerline of track, minimum cover shall be at least
5 ft. Pipelines must be marked by a sign approved by the engineer every 500 ft. and at every road crossing,
streambed, other utility crossing, and at locations of major change in direction of the line. The nominal wall
thickness of the pipeline is to be in accordance with Table 1-5-3.
5.2.4.4 Method of Installation
Installations shall be bored or jacked, and shall have a bored hole diameter essentially the same as the outside
diameter of the pipe plus the thickness of the protective coating. If voids should develop or if the bored hole
diameter is greater than the outside diameter of the pipe (including coating) by more than approximately 1 in.,
remedial measures as approved by the engineer shall be taken. Boring operations shall not be stopped if such
stoppage would be detrimental to the railway.
5.2.5 APPROVAL OF PLANS (2002)
a.
Plans for proposed installation shall be submitted to and meet the approval of the engineer before
construction is begun.
b.
Plans shall be drawn to scale showing the relation of the proposed pipeline to railway tracks, angle of
crossing, location of valves, railway survey station, right-of-way lines and general layout of tracks and
railway facilities. Plans should also show a cross section (or sections) from field survey, showing pipe in
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-5-21
3
4
Roadway and Ballast
relation to actual profile of ground and tracks. If open-cutting or tunneling is necessary, details of sheeting
and method of supporting tracks or driving tunnel shall be shown.
c.
In addition to the above, plans should contain the following data found in Table 1-5-4.
Table 1-5-4. Plan Data
Description
Carrier Pipe
Contents to be handled
Outside Diameter
Pipe Material
Specification and grade
Wall thickness
Actual Working pressure
Type of joint
Coating
Method of installation
Bury: Base of rail to top of carrier
ft.
Bury: (Not beneath tracks)
Bury: (Roadway ditches)
ft.
Bury: Base of rail to bottom jacking/receiving pits
Yes 
in.
ft.
Distance C.L. track to face of jacking/receiving pits
Cathodic protection?
in.
ft.
ft.
in.
in.
No 
5.2.6 EXECUTION OF WORK (1993)
The execution of work on railway rights-of-way, including the supporting of tracks, shall be subject to the
inspection and direction of the engineer.
5.2.7 COMMENTARY (1993)
A commentary on the “Design of Uncased Pipelines at Railroad Crossings” and the “Guidelines for Pipelines
Crossing Railroads” outline the design methodology as developed by Cornell University under the sponsorship of
the Gas Research Institute. This information is published in AREA Bulletin No. 738 Vol. 93, 1992.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-22
AREMA Manual for Railway Engineering
Pipelines
SECTION 5.3 SPECIFICATIONS FOR PIPELINES CONVEYING NON-FLAMMABLE
SUBSTANCES
5.3.1 SCOPE (1993)
Pipelines included under these specifications are those installed to carry steam, water or any nonflammable
substance except nonflammable gas products as covered in Section 5.2 which, from its nature or pressure, might
cause damage if escaping on or in the vicinity of railway property. The term “engineer” as used herein means chief
engineer of the railway company, or the authorized representative.
5.3.2 GENERAL REQUIREMENTS (2002)
a.
Pipelines under railway tracks and across railway rights-of-way shall be encased in a larger pipe or conduit
called the casing pipe as indicated in Figure 1-5-3. Casing pipe may be omitted under the following
conditions:
(1) Under secondary or industry tracks as approved by the engineer.
(2) On pipelines in streets where joints are of leakproof construction and the pipe material will safely
withstand the combination of internal pressure and external loads.
(3) For non-pressure sewer crossings where the pipe strength is capable of withstanding railway loading.
1
b.
Pipelines shall be installed under tracks by boring or jacking, if practicable.
c.
Pipelines shall be located, where practicable, to cross tracks at approximately right angles thereto but
preferably at not less than 45 degrees and shall not be placed within culverts nor under railway bridges
where there is likelihood of restricting the area required for the purposes for which the bridges or culverts
were built, or of endangering the foundations.
d.
Pipelines laid longitudinally on railway rights-of-way shall be located as far as practical from any tracks or
other important structures . If located within 25 ft. of the centerline of any track or where there is danger of
damage from leakage to any bridge, building or other important structure, the carrier pipe shall be encased
or of special design as approved by the engineer.
3
4
Note 1: See Article 5.3.4.3
Note 2: See Article 5.3.5.2
Figure 1-5-3. Casing Pipe Installation
e.
Where laws or orders of public authority prescribe a higher degree of protection than specified herein, then
the higher degree of protection so prescribed shall supersede the applicable portions.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-5-23
Roadway and Ballast
f.
Pipelines and casing pipe shall be suitably insulated from underground conduits carrying electric wires on
railway rights-of-way. Pipeline must be able to be electronically located.
5.3.2.1 Pipeline Inspection and Maintenance
a.
Pipeline owners engaged in the transport of non-flammable substances are subject to regulations of the
Federal Government. These regulations require certain inspection routines that, in the general case, are
conducted from within the carrier pipe or by non-destructive methods not requiring it be exposed.
b.
It is the responsibility of the pipeline owner to conduct the necessary inspections without interference to the
operations of the Railway Company. Should it become necessary to expose a pipe for an inspection, or for its
replacement, the owner shall design a procedure that does not interfere with Railway operations, and shall
make prior arrangements with the Railway as may be necessary to permit safe conduct of the work.
c.
Pipeline maintenance shall be limited to the installation of a new carrier pipe in an existing casing, renewal
of carrier and casing pipe separators or the installation of a new crossing. In all cases, the work shall be
conducted in the same manner as in the installation of a new crossing, which is subject to the requirements
of these specifications. Casings abandoned or replaced by new location work shall be backfilled by methods
and materials as directed by the Engineer. The location of abandoned facilities shall be recorded and
records maintained by the pipeline owner.
d.
The owners of pipelines not subject to regulation requiring inspection are expected to inspect their facilities
as a matter of due diligence in the conduct of its business. The Railway may, as a right but not a duty,
require an inspection of the construction, to include receiving a written report of findings certified by a
registered professional engineer. Maintenance of these facilities shall be conducted as above described.
5.3.3 CARRIER PIPE (2002)
a.
Carrier line pipe and joints shall be of acceptable material and construction as approved by the engineer.
Joints for carrier line pipe operating under pressure shall be leakproof mechanical or welded type.
b.
The pipe shall be laid with sufficient slack so that it is not in tension.
c.
Plastic carrier pipe materials includes thermoplastic and thermoset plastic pipes. Thermoplastic types
include Polyvinyl Chloride (PVC), Acrylonitrile Butadiene Styrene (ABS), Polyethylene (PE), Polybutylene
(PB), Cellulose Acetate Butyrate (CAB) and Styrene Rubber (SR). Thermoset types include Reinforced
Plastic Mortar (RPM), Reinforced Thermosetting Resin (FRP) and Fiberglass Reinforced Plastic (FRP).
(1) Plastic pipe material shall be resistant to the chemicals with which contact can be anticipated. Plastic
carrier pipe shall not be utilized where there is potential for contact with petroleum contaminated soils
or other non-polar organic compounds that may be present in surrounding soils.
(2) Plastic carrier pipes operating under pressure shall be encased according to Article 5.3.4. Casing may
be omitted with approval by the engineer, provided that minimum burial depth is increased to comply
with the most conservative requirements of either: the engineer's instructions, current ANSI
specifications, current OSHA regulations, or local regulatory agency specifications.
(3) Plastic carrier pipes without casing shall be designed to withstand internal operating pressures
according to ANSI B31.3 specifications. External loads due to soil pressures and railroad live loads from
Table 4.9.1 of Chapter 1 shall be used to determine deflection. Deflection resulting from external
loading shall be calculated assuming there is no internal pressure. Deflection shall be limited to no more
than 5% of the diameter.
(4) Design shall consider differential settlement of attachments, longitudinal bending, shear loadings due
to uneven settlement of pipe bedding, temperature induced stresses, ground movement due to seasonal
variations in moisture content (i.e. expansive clays), seismic ground movement and potential for ground
cover surface erosion.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-24
AREMA Manual for Railway Engineering
Pipelines
(5) The plastic pipe material must be compatible with the type of product conveyed and the temperature
range anticipated for the transported materials and surrounding environment. The maximum allowable
operating pressure is 100 psi. Plastic carrier pipe design and installation shall conform to the ANSI
B31.3 specifications and/or the following specifications:
d.
Specification No.
Carrier pipe properties:
ANSI/AWWA C900-89
Polyvinyl Chloride (PVC) pressure pipe, 4 in. through 12 in. for water
distribution.
ANSI/AWWA C901-96
Polyethylene (PE) pressure pipe and tubing, 1/2 in. through 3 in. for
water service.
ANSI/AWWA C902-88
Polybutylene (PB) pressure pipe and tubing, 1/2 in. through 3 in. for
water.
ANSI/AWWA C905-88
Polyvinyl Chloride (PVC) water transmission pipe, nominal diameters 14
in. through 36 in.
ANSI/AWWA C906-90
Polyethylene (PE) pressure pipe and fittings, 4 in. through 63 in. for
water distribution.
ANSI/AWWA C907-90
Polyvinyl Chloride (PVC) pressure fittings for water, 4 in. through 8 in.
ANSI/AWWA C950-95
Fiberglass pressure pipe.
Codes, specifications and regulations current at time of constructing the pipeline shall govern the
installation of the facility within the railway rights-of-way. The proof testing of the strength of carrier pipe
shall be in accordance with ANSI requirements.
1
5.3.4 STEEL CASING PIPE (2002)
a.
b.
Casing pipe and joints shall be leakproof construction, capable of withstanding railroad loading. The inside
diameter of the casing pipe shall be at least 2 in. greater than the largest outside diameter of the carrier
pipe, joints or couplings, for carrier pipe less than 6 in. in diameter; and at least 4 in. greater for carrier pipe
6 in. and over in diameter. It shall, in all cases, be great enough to allow the carrier pipe to be removed
subsequently without disturbing the casing pipe or roadbed.
3
When casing is installed without benefit of a protective coating or said casing is not cathodically protected,
the wall thickness shown above shall be increased to the nearest standard size which is a minimum of 0.063
in. greater than the thickness required except for diameters under 12-3/4 in. (Table 1-5-5).
4
5.3.4.1 Steel Casing Pipe Strength
Steel casing pipe shall have a specified minimum yield strength, SMYS, of at least 35,000 psi.
5.3.4.2 Concrete and Corrugated Metal Pipe
For pressures under 100 psi in the carrier pipe, the casing pipe may be reinforced concrete pipe conforming to
AREMA specifications in Chapter 8, Concrete Structures and Foundations, Part 10, Reinforced Concrete
Culvert Pipe, coated corrugated metal pipe or steel tunnel liner plate conforming to the AREMA specifications for
such pipe, Part 4, Culverts, this Chapter.
5.3.4.3 Length of Pipe
Casing pipe under tracks and across railway rights-of-way shall extend to the greater of the following distances,
measured at right angles to centerline of track. If additional tracks are constructed in the future or the railway
determines that the roadbed should be widened, the casing shall be extended or other special design incorporated.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-5-25
Roadway and Ballast
• 2 ft. beyond toe of slope.
• 3 ft. beyond ditch.
• A minimum distance of 25 ft. from center of outside track when end of casing is below ground.
Table 1-5-5. Minimum Wall Thickness for Steel Casing Pipe for E80 Loading
Nominal Diameter (inches)
When coated or
When not coated or
cathodically protected
cathodically protected
Nominal Thickness (inches) Nominal Thickness (inches)
12-3/4 and under
0.188
0.188
14
0.188
0.250
16
0.219
0.281
18
0.250
0.312
20 and 22
0.281
0.344
24
0.312
0.375
26
0.344
0.406
28
0.375
0.438
30
0.406
0.469
32
0.438
0.500
34 and 36
0.469
0.531
38
0.500
0.562
40
0.531
0.594
42
0.562
0.625
44 and 46
0.594
0.656
48
0.625
0.688
50
0.656
0.719
52
0.688
0.750
54
0.719
0.781
56 and 58
0.750
0.812
60
0.781
0.844
62
0.812
0.875
64
0.844
0.906
66 and 68
0.875
0.938
70
0.906
0.969
72
0.938
1.000
5.3.5 CONSTRUCTION (2002)
Casing pipe shall be so constructed as to prevent leakage of any substance from the casing throughout its length
except at ends. Casing shall be so installed as to prevent the formation of a waterway under the railway, with an
even bearing throughout its length, and shall slope to one end (except for longitudinal occupancy).
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-26
AREMA Manual for Railway Engineering
Pipelines
Where casing and/or carrier pipe is cathodically protected, the engineer shall be notified and suitable test made to
ensure that other railway structures and facilities are adequately protected from the cathodic current in
accordance with the recommendations of current Reports of Correlating Committee on Cathodic Protection,
published by the National Association of Corrosion Engineers.
5.3.5.1 Method of Installation
a.
Installations by open-trench methods shall comply with Part 4, Culverts, Section 4.12, Assembly and
Installation of Pipe Culverts. Plastic pipelines shall be installed according to ASTM D 2774 and D 2321.
b.
Bored or jacked installations shall have a bored hole diameter essentially the same as the outside diameter
of the pipe plus the thickness of the protective coating. If voids should develop or if the bored hole diameter
is greater than the outside diameter of the pipe (including coating) by more than approximately 1 in.,
remedial measures as approved by the chief engineer of the railway company shall be taken. Boring
operations shall not be stopped if such stoppage would be detrimental to the railway.
c.
Tunneling operations shall be conducted as approved by the engineer. If voids are caused by the tunneling
operations, they shall be filled by pressure grouting or by other approved methods which will provide proper
support.
5.3.5.2 Depth of Installation
5.3.5.2.1 Casing Pipe
Casing pipe under railway tracks and across railway rights-of-way shall be not less than 5-1/2 ft. from base of
railway rail to top of casing at its closest point, except that under secondary or industry tracks this distance may be
4-1/2 ft. On other portions of rights-of-way where casing is not directly beneath any track, the depth from ground
surface or from bottom of ditches to top of casing shall not be less than 3 ft.
1
5.3.5.2.2 Carrier Pipe
Carrier pipe installed under secondary or industry tracks without benefit of casing shall be not less than 4-1/2 ft.
from base of railway rail to top of pipe at its closest point nor less than 3 ft. from ground surface or from bottom of
ditches. Plastic carrier pipe must be encased under secondary or industry tracks according to Article 5.3.4.
3
5.3.5.3 Shut-Off Valves
Accessible emergency shut-off valves shall be installed within effective distances each side of the railway as
mutually agreed to by the engineer and the pipeline company. These valves should be marked with signs for
identification. Where pipelines are provided with automatic control stations at locations and within distances
approved by the engineer, no additional valves shall be required.
5.3.5.4 Longitudinal Pipelines
Pipeline laid longitudinally on railway rights-of-way 50 ft. or less from centerline of track, shall be buried not less
than 4 feet from ground surface to top of pipe. Where pipeline is laid more than 50 ft. from centerline of track,
minimum cover shall be at least 3 feet. Plastic carrier pipe may be utilized for longitudinal installations with
approval by the engineer, but shall be encased within the right of way. Casing may be omitted with approval of the
engineer, provided that minimum bury depth is increased to comply with the most conservative requirements of
either: the engineer’s instructions, current ANSI specifications, current OSHA regulations, or local regulatory
agency regulations. Pipelines must be marked by a sign approved by the engineer every 500 ft. and at every road
crossing, streambed, other utility crossing, and at locations of major change in direction of the line.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-5-27
4
Roadway and Ballast
5.3.6 APPROVAL OF PLANS (1993)
Plans for proposed installation shall be submitted to and meet the approval of the engineer before construction is
begun.
Plans shall be drawn to scale showing the relation of the proposed pipeline to railway tracks, angle of crossing,
location of valves, railway survey station, right-of-way lines and general layout of tracks and railway facilities.
Plans should also show a cross section (or sections) from field survey, showing pipe in relation to actual profile of
ground and tracks. If open-cutting or tunneling is necessary, details of sheeting and method of supporting tracks or
driving tunnel shall be shown.
a.
In addition to the above, plans should contain the following data:
Table 1-5-6. Plan Data
Carrier Pipe
Casing Pipe
Contents to be handled
Outside Diameter
Pipe Material
Specification and grade
Wall thickness
Actual Working pressure
Type of joint
Coating
Method of installation
Seals: Both ends:
One end:
Type:
Bury: Base of rail to top of casing
Bury: (Not beneath tracks)
ft.
in.
ft.
Bury: (Roadway ditches)
ft.
in.
in.
Type, size and spacing of insulators or supports
Distance C.L. track to face of jacking/receiving pits
Bury: Base of rail to bottom jacking/receiving pits
Cathodic protection?
Yes No
ft.
ft.
in.
in.

5.3.7 EXECUTION OF WORK (1993)
The execution of the work on railway rights-of-way, including the supporting of tracks, shall be subject to the
inspection and direction of the engineer.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-28
AREMA Manual for Railway Engineering
Pipelines
SECTION 5.4 SPECIFICATIONS FOR OVERHEAD PIPELINES CROSSINGS
5.4.1 SCOPE
This section shall govern the design of pipelines which cross the tracks or right-of-way of a Railway Company on
overhead structures. It shall include pipelines attached to existing or new vehicle or pedestrian bridges, and
existing or new bridges designed for the exclusive use of pipeline facilities. It shall apply to pipelines designed for
all levels of operating pressures, to include vacuums, and to all commodities, flammable and non-flammable,
usually transported through pipelines.
5.4.2 GENERAL CONDITIONS
5.4.2.1 Location Investigation
Where possible, pipelines shall be installed underground. There may be circumstances that warrant consideration
of an overhead pipeline crossing; however, an overhead crossing of the tracks or right-of-way of a Railway by a
pipeline facility will be investigated for permitting only in the case where the applicant can demonstrate it has
exercised due diligence in locating a subgrade crossing.
5.4.2.2 Use of Existing Structures
In no case shall a bridge or overhead structure owned or maintained by a Railway be used for the attachment of a
pipeline facility. Applications proposing to make an attachment to an overhead structure owned and maintained by
a party other than a Railway shall submit evidence that the owner of the structure has reviewed the plan and has
issued, or proposes to issue, a permit or license for the facility.
1
5.4.3 GENERAL DESIGN REQUIREMENTS
5.4.3.1 Leak Protection
The design shall provide for protection of the property and track structure of a Railway in the event of a pipeline
leak or failure by use of a casing pipe or other means acceptable to the Railway. The design shall direct leaking
liquid and dense gaseous products off the Railway right of way, but in no case, less than 25 feet beyond the back of
parallel roadway ditches.
3
5.4.3.2 Emergency Shut-Off Valves
Accessible emergency shut-off valves shall be installed within an effective distance on each side of the Railway
right of way. The Engineer may, at his option, accept existing automatic control stations as suitable emergency
shut-off valves.
5.4.3.3 Other
Emergency telephone numbers shall be clearly posted on both ends of an overhead pipeline crossing, and pipelines
and pipeline bridge structures must have effective apparatus to prevent unauthorized access.
Additional pipeline attachments to an existing overhead pipeline crossing shall be approved by the Railway.
Overhead pipelines could be subjected to high temperatures from the exhaust stacks of stationary running
locomotives positioned directly under the carrier pipe. Pipeline contents and the pipeline materials may be
adversely affected. The design shall incorporate suitable insulation or other heat deflection measures to prevent
damages and insure pipeline integrity under high temperature conditions.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-5-29
4
Roadway and Ballast
5.4.4 STRUCTURAL ELEMENTS
The structural elements of an overhead pipeline facility shall be the casing pipe, the carrier pipes, attaching
hangers or bearings and the supporting bridge.
5.4.4.1 Pipeline Design
5.4.4.1.1 Casing Pipes
Casing pipes shall be assumed to provide no structural support to the carrier pipe. The dead load of the casing pipe
shall be included in the calculation of the dead load of the carrier pipe, and the load effects of wind and ice on the
carrier pipe shall be calculated with respect to the diameter of the casing pipe.
5.4.4.1.2 Carrier Pipes
Carrier pipes shall be designed in accordance with the most restrictive applicable federal or local regulation for the
operating pressure and commodity of the facility. In addition to the loads exerted on the pipe by the conditions of
its operation, the structural loads resulting from suspension or bearing conditions shall be considered.
5.4.4.2 Supporting Bridge Design
5.4.4.2.1 General Design Considerations
Bridge spans, bents or piers and foundations shall be designed in accordance with generally accepted engineering
practice, accounting for all dead, live, impact, seismic and secondary force loads. Pipe hanger and bearing
attachment device design shall consider thermal expansion and seismic displacements.
Drawings, plans, calculations and other documents representing the details of an application shall be prepared,
signed and sealed by a professional engineer registered to practice in the state of the installation.
5.4.4.2.2 New Overhead Pipeline Bridges
Overhead pipeline bridges shall be designed in accordance with the following criteria:
Clearances shall be:
VERTICAL—Not less than 25 feet above highest top of rail of the tracks to be spanned, except that cable supported
spans shall have a vertical clearances of not less than 50 feet.
HORIZONTAL—Not less than 25 feet from the centerline of the nearest existing main, siding, spur, or industry
track, except in cases where the Engineer directs that additional clearance for future tracks must be provided. If
conditions warrant, the engineer may require Pier Protection in accordance with Chapter 8, Concrete Structures
and Foundations, Part 2, Reinforced Concrete Design.
New beam span, girder and truss type structures and the details of the proposed attachment shall be designed in
general accordance with Chapter 15 of this Manual of Recommended Practice.
New cable suspended type structures shall be reviewed only upon special application to the Railway. Such
application shall identify the design specifications to be used, to include the loads, allowable stresses and design
considerations to be applied. Unless otherwise directed by the Engineer, cable supported spans shall include a
minimum floor system with lateral bracing.
5.4.4.2.3 Attachments to Existing Overhead Bridges
Where the pipeline is to be attached to an existing overhead structure not specifically designed for pipelines, the
following shall apply:
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-30
AREMA Manual for Railway Engineering
Pipelines
Existing structures proposed as support for a pipeline shall be investigated for the additional loads of the operating
pipeline facility. Additionally, the report of the professional engineer shall contain a conclusion with respect to the
effects of the additional loads on the existing structure.
Pipelines shall be installed inside the main structural members of the supporting bridge. In cases where this is not
practical, the pipeline may be attached to the outside surface of the structure, but in no case shall the bottom of the
pipeline be less than one foot above the elevation of the lowest main structural member of the supporting bridge.
Pipe hanger and bearing attachment device design, and their connections to the supporting structure and the
pipeline, shall be based on unit stresses equal to one-half (1/2) those otherwise permitted. Attachment device
design shall consider thermal expansion, live loads deflection of the existing bridge, and seismic displacements.
Pipeline and attachment designs shall consider the force and effect of the elements of the weather. Attachments
shall be protected against corrosion in situations where chemical ice removal is utilized, or other corrosive
condition is known or suspected.
5.4.5 INSPECTION AND MAINTENANCE
Overhead pipelines, attachment devices, and supporting structures should be inspected and maintained on a
routine basis. Also, emergency response procedures should be developed to handle a situation in which an accident
or incident might jeopardize the integrity of pipeline facility.
SECTION 5.5 SPECIFICATIONS FOR FIBER OPTIC “ROUTE” CONSTRUCTION ON
RAILROAD RIGHT OF WAY
1
5.5.1 SCOPE (2001)
These general requirements and specifications are provided only as a guideline for the successful completion of
fiber optic installation. This shall include parallel and crossings on railroad right-of-way by railroads or outside
communication companies that enter into agreements with railroads. All railroads shall reserve the right to
change these recommendations as needed, and are not to be taken as authority to construct without prior review
and approval by each of the participating railroads. Any items not covered specifically herein are to be in
accordance with American Railway Engineering and Maintenance-of-Way Association (AREMA) standards and
recommended practices, subject to the approval of the participating railroad’s Engineering Department. All
railroads shall reserve the right to change these recommendations as needed without prior notice. A glossary of
terms used in this document follows in Article 5.5.7. Dimensions are given in English with metric units in
parentheses.
5.5.2 PLANNING (2001)
5.5.2.1 Coordinate the engineering criteria, from the preliminary route inspection through the actual route
design, with railroad representative.
5.5.2.2 When planning a fiber system project.
a.
Identify and note on maps any potential impact to the railroad track structure or right-of-way.
b.
Note vegetation, property uses and topography not indicated on maps.
c.
Note cuts and fills.
d.
Identify potential track crossings, particularly under-track bores.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-5-31
3
4
Roadway and Ballast
5.5.2.3 Fiber Optic installations are governed by unique rules and regulations. It is the responsibility of the
Fiber Optic Company that these be adhered to during planning, including preliminary investigations and
route surveys on the railroad’s right-of-way.
5.5.2.4 Special permission is required for the use of all vehicles, including ATV’s, on the railroad’s right-ofway. Obtain permission to occupy the property or right-of-way of landowners other than the railroad.
5.5.2.5 It is the fiber optic company’s responsibility to obtain any permits, if required.
5.5.3 DESIGN (2001)
5.5.3.1 Conventional Build General Requirements (See Paragraph 5.5.3.6 for Railplow)
5.5.3.1.1 Detail all fiber facilities including lines, repeater sites, junctions, and structures.
5.5.3.1.2 Design the fiber system, if practical, to run near the outer limits of the Railroad’s right-of-way.
Keep the fiber system running line as straight as possible while maintaining a consistent distance from
track centerline.
5.5.3.1.3 Design the fiber system to run on the field side of all railroad structures, including bridges, signal
facilities, buildings and platforms.
5.5.3.1.4 If the fiber system has to be placed under an existing signal or communication structure, place
the system a minimum of 10 feet (3.05 meters) under natural ground. This extra depth may also be
required in “signal sensitive areas” such as interlocking or control plants.
5.5.3.1.5 If the fiber system has to be located under existing signal or communication wires, a minimum 2
feet (.61 meters) of separation is required.
5.5.3.1.6 Fiber optic cable must not be installed within 5 feet (1.52 meters) of underground power or signal
lines, unless suitably insulated.
5.5.3.1.7 If the fiber system is designed within 30 feet (9.14 meters) of a track centerline or structure of any
type, excavations within this area may require shoring designed to include train or structure surcharges.
In such cases, submit shoring plans with calculations, stamped by a licensed civil engineer, to the railroad
for approval prior to construction. See 5.5.3.2 Trenches and Excavations. Refer to Figure 1-5-11.
5.5.3.1.8 Do not design fiber system components that create stumbling hazards on the railroad’s right-ofway.
5.5.3.1.9 Design the fiber system to be installed a minimum of 42 inches (1.07 meters) below natural
ground, except as noted herein. See Figure 1-5-6.
5.5.3.1.10 In the event local ground conditions prohibit the placement of the fiber system at a depth of at
least 42 inches (1.07 meters), the fiber system must be encased, and specific approval by the railroad is
required.
5.5.3.1.11 Compact all backfill in excavations and trenches to 95% maximum density as defined in ASTM
Standard D698. Use clean, suitable backfill material.
5.5.3.1.12 Design the fiber system to be buried a minimum of 60 inches (1.52 meters) below the bottom of
all culverts on the railroad’s right-of-way, or around the end of the culvert (field side) and 60 inches (1.52
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-32
AREMA Manual for Railway Engineering
Pipelines
meters) below the bottom of the flow line. Only after specific evaluation by the railroad will any system be
allowed to be placed over the top of any culvert. See Figure 1-5-6.
5.5.3.1.13 Locate and identify buried utilities and other potential obstructions.
5.5.3.1.14 Do not attach the fiber system to railroad bridges to cross waterways, highways, etc., unless no
other feasible alternative exists. Fully explore the burying alternative before submitting requests to attach
the fiber system to a bridge, and provide appropriate documentation, detailing the reasons why an
attachment is necessary.
a.
Submit bridge attachment designs, for approval prior to construction. Include details at and around the
bridge backwalls.
b.
Design bridge attachments that will not interfere with nor delay future repair, replacement, inspection and
other construction to take place on or near the bridge (superstructure and substructure).
c.
Include in the design extra cable in a protected facility near the bridge so the bridge can be raised if
necessary, and prevent delay to railroad operations.
d.
Design the fiber system so it does not obstruct the bridge bearings. See Figure 1-5-5.
e.
If practical, design the fiber system to be installed on the downstream side of the bridge.
f.
Fiber system must not be attached to a timber bridge, nor to the handrails of bridges.
5.5.3.1.15 Design handholes, splice boxes and manholes for appropriate loading conditions. In general,
locations within 30 feet (9.14 meters) of track centerline should be designed for a Cooper E80 surcharge,
while all other installations should withstand AASHTO H-20 highway loading requirements, in addition to
soil-pressures. If a future main track is anticipated, the installation must be designed to handle surcharge
loadings.
5.5.3.1.16 Show the location of fiber system marker signs on the design drawings, and submit a detail of
the sign, including it’s color, for approval. This also applies to aerial marker signs.
1
3
5.5.3.2 Trenches and Excavations
5.5.3.2.1 Use shoring conforming to the most restrictive of railroad, state, OSHA, or AREMA standards in
all excavations where required. Refer to OSHA standard in 29 CFR XVII Paragraph 1926.650. Submit
shoring plans involving the railroad’s track or structures for approval prior to construction. See Figure 15-11.
5.5.3.2.2 All excavations and trenches will be attended or protected. Fence, fill or guard each site prior to
leaving. Monitor shored trenches and excavations continuously during work for signs of instability and
failure.
5.5.3.3 Bridges and Above Ground Installations
5.5.3.3.1 Fall protection is required for work performed on all bridges and above ground installations.
Work on all bridges and structures on the railroad’s right-of-way is governed by the most restrictive of
OSHA (29 CFR Parts 1910 and 1926), FRA Bridge Worker Safety Regulations (49 CFR Part 214), or state
regulations.
5.5.3.3.2 Contractors performing work on bridges and above ground facilities on or over railroad property
must submit written documentation certifying their employees have received proper training in fall
protection prior to engaging in work on railroad property. The contractor must further satisfy the railroad
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-5-33
4
Roadway and Ballast
representative that proper equipment and compliance with these standards will be adhered to on the job
site.
5.5.3.4 Trenchless Installation of Fiber Systems
5.5.3.4.1 Submit plans for all bores that impact railroad’s right-of-way for approval. This includes both
under-track bores and parallel-to-track bores. Detail the following on the plans:
a.
Boring methods and equipment;
b.
Depth(s) of the fiber system;
c.
Locations of bore pits relative to track centerline;
d.
Casing specifications.
e.
Excavation supports at bore pits
5.5.3.4.2 An extensive geotechnical analysis may be required to verify that railroad tracks will not be
affected by the proposed bore. It is the responsibility of the fiber optic company or its contractor to
provide such an analysis at the railroad’s request.
5.5.3.4.3 All bores are subject to railroad, federal, state and/or local requirements.
5.5.3.4.4 Ultimate approval of the boring process rests with the railroad. The railroad has the authority to
delay the operation or establish additional requirements based on site characteristics.
5.5.3.4.5 Under-track bores are subject to the following requirements:
a.
Keep track bores under mainline tracks to a minimum.
b.
Locate the fiber system a minimum of 66 inches (1.68 meters) below the base of rail or natural ground,
whichever is greatest.
c.
Encase in galvanized steel pipe or black iron pipe [Specified Minimum Yield Strength of 30,000 psi (241,318
kPa) or above] all fiber system lines under tracks in a single casing. For depths greater than 15 feet (4.57
meters) below the natural ground, Schedule 80 PVC pipe may be used in lieu of steel pipe or black iron pipe.
Extend the casing a minimum of 30 feet (9.14 meters) from centerline of nearest track, measured
perpendicular to the track, or longer, to stay out of cuts and/or fills. Multiple duct installations must use a
single Schedule 80 or better casing for the bore. The crossing angle shall not be less than 45 degrees.
d.
If practical, design track bores to be greater than 150 feet (45.72 meters) from the nearest bridge, culvert,
track switch (see Figure 1-5-10), building or other major structure.
e.
Design bore pits to be a minimum of 30 feet (9.14 meters) from centerline of nearest track when measured
at right angles to the track. See Figure 1-5-7. Do not locate bore pits in the slope of a cut or fill section of
the roadbed. Keep the bore pit size to a minimum. Location of crossings shall be in an area that does not
require extensive shoring. See 5.5.3.2 Trenches and Excavations. Refer to Figure 1-5-11.
f.
Keep bore pits and other excavations to the minimum size necessary.
5.5.3.4.6 Generally accepted dry bore installation methods for under-track or parallel-to-track bores
include:
a.
Jacking the casing through the subgrade.
b.
Dry auger boring.
c.
Dry mini-directional boring.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-34
AREMA Manual for Railway Engineering
Pipelines
Other methods will be considered on a case-by-case basis. Wet bores are not allowed for installing fiber
systems on the railroad’s right-of-way. Wet bores in this context refer to the use of liquids to displace soil.
5.5.3.4.7 All boring methods are subject to the following conditions:
a.
The machine operator follows all railroad standards and OSHA regulations, including the use of grounding
mats and other safety measures.
b.
The machine operator has control over the direction of the boring tool.
c.
Pull back methods use mandrels up to two inches (50.8 millimeters) larger than the diameter of the casing,
up to a casing diameter of 8 inches (203.2 millimeters).
d.
Shallow bores, misdirected bores, or other unsuccessful bores are abandoned and filled at the discretion of
the railroad.
e.
If a bore is unsuccessful, future attempts are made only with the approval of the railroad.
f.
Auger heads are not allowed more than six inches (152.4 millimeters) ahead of the casing being inserted.
g.
Any parallel-to-track bore that is made in either a cut back or fill section will be located a minimum of 60
inches (1.52 meters) below the toe of the ballast section or natural ground, whichever is lower. See
Figure 1-5-12 & Figure 1-5-13.
5.5.3.4.8 Trenchless directional bores will be considered for under-track and parallel-to-track bores on a
case-by-case basis, subject to these additional constraints.
a.
Under-track bores must be installed a minimum depth of 12 feet (3.66 meters) below the base of rail or 15
feet (4.57 meters) below the natural ground line, whichever is greater.
b.
An approved slurry must be kept to a minimum and only used for head lubrication and/or spoils return.
Calculate anticipated slurry use and monitor slurry use during the bore operation to determine slurry loss
into the surrounding soil. A bentonite slurry should be used to seal the hole with a minimum of 95% return.
Should excessive slurry loss occur, operations must cease immediately.
c.
Maximum size of the finished hole is 10 inches (254 millimeters).
d.
Submit complete specifications for the machine to be used, including:
1
3
(1) Operating and maximum pressures of liquid at the drilling head;
4
(2) Water volume;
(3) Source of water;
(4) Power supply;
(5) Type of reamer or cutting tool, number and size of holes/nozzles on the head, and method of head
control;
(6) Volume of anticipated spoils removal.
e.
Bore stems and cutting heads may have to be left in the ground if they can not be retrieved through the bore
hole. Open excavation to retrieve the parts may not be possible.
5.5.3.4.9 Special conditions such as rock drilling that require the use of high-pressure air or water are
subject to all of the conditions of this section and will be evaluated as they occur. Blasting is not allowed.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-5-35
Roadway and Ballast
5.5.3.4.10 Installation of fiber cable on pole lines within the railroad right-of-way will be considered on an
individual basis.
5.5.3.4.11 Any overhead crossing of the track by the fiber system must at least adhere to AREMA
Clearances. Fiber optic cables on polelines must be routinely inspected and maintained.
5.5.3.5 Repeater Stations (Regens)
5.5.3.5.1 Submit the regen design with the running line plan. Indicate all details of the site, such as
building size, building access, concrete pad depth, soil removal and method conforming to environmental
requirements, power supply, distance from track centerline, fences, all appurtenances, and distances from
all road crossings.
5.5.3.5.2 Include with the power supply detail the following: voltages, distances relative to the mainline and
other structures, overhead clearances and below ground dimensions.
5.5.3.5.3 Locate regens a safe distance from the nearest grade crossing. The governing minimum distance
is the most stringent of either:
(1) Local, state, or AASHTO clear sight distance requirements for grade crossings, or
(2) 500 feet (152 meters). See Figure 1-5-8. These requirements could vary due to train and vehicle speeds
at the crossings.
5.5.3.5.4 Do not locate regens under signal, communication, or power lines.
5.5.3.5.5 Locate regens a minimum of 50 feet (15.24 meters) from centerline of the nearest track to the
nearest element of the regen facility, and avoid placement adjacent to track curves. See Figure 1-5-8.
5.5.3.5.6 Do not place regens where vision will be obstructed or interfere with railroad operations. Train
signals must be clearly visible.
5.5.3.5.7 Regens may have to be located on private property to meet the requirements of this section.
5.5.3.6 Railplow Design
5.5.3.6.1 Routes that will utilize an on-track plow shall be designed approximately 11 feet (3.35 meters)
from the centerline of track or beyond the toe of ballast line.
5.5.3.6.2 The running line shall not be permitted between centerline of tracks. Hand holes and pull boxes
shall be no closer then 15 feet (4.57 meters) to the centerline of track.
5.5.3.6.3 Signal facilities should be avoided by trenching behind the facility.
5.5.3.6.4 The depth of the installation shall be 42 inches (1.07 meters) or greater. Other considerations may
apply depending on the specific code.
5.5.3.6.5 The distance to centerline of track for bores and other excavations will be a minimum of 20 feet
(6.10 meters) to accommodate railplow design and construction. Excavations in these areas must not
violate train and structure surcharges.
5.5.3.6.6 Locate regens a minimum of 30 feet (9.14 meters) from centerline of the nearest track to the
nearest element of the regen facility, and avoid placement adjacent to track curves. See Figure 1-5-8.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-36
AREMA Manual for Railway Engineering
Pipelines
5.5.4 CONSTRUCTION (2001)
5.5.4.1 Complete arrangements must be made for safety training and protection of construction operations
prior to any construction activity.
5.5.4.2 Obtain approval from the railroad for any deviation to the construction drawings and indicate such
changes on the construction drawings.
5.5.4.3 Avoid the slope of cut or fill sections when designing the running line. Design the fiber system to
run over the top of a cut section whenever possible. See Figure 1-5-9 & Figure 1-5-13. Note: Railplow
construction may require cable to be in the bottom of the cut section.
5.5.4.4 If the fiber system has to be located in the ditch, place the system a minimum of 60 inches (1.52
meters) beyond the toe of the slope and a minimum of 60 inches (1.52 meters) below the bottom of the flow
line. The fiber optic company may want to consider placing the fiber system at extra depth to allow for
ditch cleaning.
5.5.4.5 Stabilize any waterways that have been plowed or cut. Use rip-rap or other approved erosion
control methods.
5.5.4.6 Use OSHA and railroad approved shoring procedures on all trenches and excavations. See 5.5.3.2
Trenches and Excavations.
5.5.4.7 Backfill, cover or fence all excavations when unattended.
1
5.5.4.8 No equipment is allowed on any track ballast section.
5.5.4.9 Do not foul the track ballast with dirt or other foreign materials.
5.5.4.10 Do not store or place equipment, supplies, materials, tools, or other items within 25 feet (7.62
meters) of the nearest track centerline, or within 500 feet (152.4 meters) of road crossing.
3
5.5.4.11 Start cleanup and restoration of the railroad’s right-of-way immediately after the fiber system
installation in each construction area and continue on a daily basis as the project progresses until
complete. Ensure that any stumbling hazards are removed immediately.
5.5.4.12 Take care not to foul the ballast, block ditches, or culverts, or otherwise impede drainage. If
chipping is approved, remove any brush or items that can not be chipped to 1 inch (2.54 centimeters).
5.5.4.13 Bridge attachments are generally not permitted. The fiber optic company must provide written
justification prior to applying for permission to attach to the railroad bridge. Detailed drawings prepared
by a registered structural engineer must be prepared for review and approval by the railroad. Install only
railroad approved bridge attachments incorporating the following:
a.
The Fiber Optic Company is to install extra cable in a protective facility near the bridge so the bridge can be
raised if necessary and without delay to railroad operations.
b.
Install the fiber system so as not to obstruct the bridge bearings. See Figure 1-5-5. The conduit should not
be placed on top of the deck unless clearances can be obtained to stay outside the track structure for normal
maintenance. Place the conduit on the outside of the superstructure by supporting it from the concrete
deck, curb and/or walkway. Tie maintenance must not be impeded.
c.
Exercise care in trenching between the toe of the roadbed slope and bridge backwalls, typically by handdigging or dry boring.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-5-37
4
Roadway and Ballast
d.
Torch cutting or welding of bridge members is not allowed. Drill holes, if approved, are required for bracket
attachment and specify high strength bolts (ASTM A325) for any brackets. Provide an expansion joint in
detail.
e.
If brackets must be removed from the bridge, do not torch cut bolts. After removing the bracket, insert a
bolt in the open hole and paint with galvanized paint. If the bridge is concrete, cut the bolt flush with the
concrete surface.
f.
Touch-up any scratched galvanized bridge surfaces, including bracket attachments, with galvanized paint,
including those areas of bridge steel that are to be covered by the brackets. The painted area should extend
at least 2 inches (5.08 centimeters) beyond the contact surface.
5.5.4.14 Fall protection conforming to all Federal Railroad Administration and OSHA regulations is
required for work performed on all bridges and above ground installations.
5.5.4.15 Install marker posts, handholes, splice boxes and manholes at least 30 feet (9.14 meters) from the
centerline of mainline tracks or 15 feet (4.572 meters) from the centerline of other tracks. Install them so as
not to create a stumbling hazard or to interfere with railroad operations. The signs should be placed at
intervals that will permit viewing from any direction, as approved by railroad.
5.5.4.16 Railroad personnel will locate, remove, and replace all guy wires on railroad pole lines, if
permitted.
5.5.4.17 Coordinate work on railroad poles with the railroad.
5.5.4.18 Follow applicable national electric codes for all pole work.
5.5.4.19 Obtain approval for all wire drops and splice locations from the railroad prior to construction.
5.5.4.20 Ensure all power lines on the poles have been de-energized. Check the poles for structural
integrity before climbing. Use climbing equipment conforming to OSHA regulations. In addition, comply
with federal, state, and local laws and regulations.
5.5.4.21 Do not throw trash into any excavations.
5.5.4.22 Contain all construction-generated waste material and remove it to an approved disposal site.
This includes, but is not limited to, excavated foundations, old dump sites, debris, concrete or masonry
obstructions, organic matter, rocks and boulders.
5.5.4.23 Remove all abandoned fiber optic cable systems from the right-of-way. Coordinate the method of
cable removal with the railroad.
5.5.4.24 Regrade and clean construction sites to the condition they were before the project began. Reseed
disturbed areas with indigenous grass species. Perform clean-up and restoration as the project
progresses.
5.5.4.25 Repair or replace any disturbed fencing to equal or better condition. Immediately repair and/or
monitor fences used to contain livestock. Ensure that livestock are not released onto the railroad’s rightof-way.
5.5.4.26 Do not operate heavy equipment on railroad’s paved roads located on the right-of-way without
prior approval of the railroad. Use a protective covering over paved roads when crossing them with heavy
equipment. Repair roads damaged or cut through. Coordinate such moves with the railroad.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-38
AREMA Manual for Railway Engineering
Pipelines
5.5.4.27 When installing cable on top of cuts, do not operate equipment or install cable within 5 feet (1.52
meters) of the top of the slope, or the interceptor ditch. (See Figure 1-5-13.)
5.5.4.28 Comply with all applicable federal, state and local environmental laws and regulations.
5.5.4.29 Where Public Utilities Commission requirements meet or exceed the requirements of the Railroad,
those requirements will apply. This would include but not be limited to, safety, clearances and walkways.
5.5.4.30 Maintain all existing facilities used to protect the public and/or railroad employees. Install
additional facilities when needed to protect the public and/or railroad employees.
5.5.5 DOCUMENTATION (2001)
5.5.5.1 Construction drawings must have proper railroad engineering stationing ties, to result in
acceptable As Built drawings. If construction plans are approved without the proper ties, it is the fiber
optic company’s responsibility to provide them prior to As Built drawing approval. See Figure 1-5-4.
Methodology for Equating Fiber Optic Cable Locations to Railroad Track & Right-of-Way Maps.
5.5.5.2 Include the following information on all construction plans and final As Built drawings:
a.
Alignment of the cable with railroad engineering stationing at each running line change or PI (point of
intersection) including handholes, sign and markers.
b.
The depth of cable.
c.
Bridges (the railroad engineering stationing shown is measured from the inside backwall of a bridge). See
Figure 1-5-5. Show the bridge milepost designation.
d.
Bridge attachments and their details.
e.
Culverts.
f.
Signals, signal houses and other signal facilities.
g.
All grade crossings, overhead viaducts and underpasses, including name of the street (public or private) and
railroad mile marker designation.
1
3
h. All utility crossings (both underground and overhead), and all parallel utilities.
i.
Rivers, fences, and polelines.
j.
Railroad right-of-way limits.
k.
Railroad station names and mile markers.
l.
All mainline track, sidings, spur tracks and turnouts.
4
5.5.5.3 Include a separate detailed drawing for each regen station. Show all details of the site referenced to
the mainline track, such as:
a.
Table of contents or list of drawings.
b.
Building size and distance building is from all road crossings.
c.
Distance the regen building is from centerline of all adjacent tracks.
d.
Power supply required for the regen building, including locations relative to the mainline, voltages, above
and below ground dimensions.
e.
Building access.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-5-39
Roadway and Ballast
f.
Any other facility pertinent to the project.
g.
Location of fencing around the regen site, complete with dimensions.
5.5.5.4 Include the following additional information on construction drawings submitted to the Railroad:
a.
General notes along with the symbols and their meanings.
b.
A sheet showing all the special details.
c.
Small scale maps showing the overall cable route.
d.
Schematic showing regen sites.
e.
Sheet showing various methods of erosion control.
f.
Sheet showing details for backhoe trenching below a ditch, trench below a stream, direct burial for a ditch
or creek crossing (plan and profile view).
g.
Sheet showing detail for placement of conduit in rock, including provisions for protecting Railroad ballast
where it may be fouled by rock sawing operations.
h. Include all boring and casing details. This includes, but is not limited to, dimensions, bore pit locations, and
casing specifications.
5.5.5.5 Show all measurements of each of the above from and at right angles to the centerline of the
nearest mainline track. Show on the drawing the distance to the next facility as measured along the
centerline of the main track.
5.5.5.6 Note: Mile markers found in the field are representative of actual mileposts found on railroad rightof-way maps. These are intended to provide general locations of facilities for location by railroad
personnel. These mile markers are not accurately located on railroad maps and should not be used to
establish railroad stationing. Show them on your drawings for reference only.
5.5.5.7 Submit As Builts no later than 90 days after the completion of the installation of the fiber system on
the Railroad’s right-of-way.
5.5.6 MAINTENANCE (2001)
5.5.6.1 Emergency Maintenance
In the event emergency work is required, the following procedures apply:
a.
Call the railroad for emergency approval. The railroad will determine inspector/flagger needs based on site
conditions.
b.
Perform emergency work only when appropriate flagging/inspection personnel are on site.
c.
Following the completion of emergency repairs to restore the fiber system to service, permanent restoration
of the fiber system falls under the conditions of the following section.
5.5.6.2 Regular Maintenance
5.5.6.2.1 Notify the railroad prior to entering the railroad’s right-of-way to repair or maintain the fiber
system.
5.5.6.2.2 The methods and procedures of all maintenance and repair work are subject to the consent and
approval of the railroad. Submit to the railroad for approval plans for any work not previously detailed in
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-40
AREMA Manual for Railway Engineering
Pipelines
the approved Construction Plans. Include (as applicable) drawings showing the plan, elevation, details,
Railroad engineering stationing and methods of the proposed construction, installation, maintenance,
repair, replacement or other work.
5.5.6.2.3 Fiber optic company crew locations and the number of crews may be restricted depending on
railroad flagger availability, job site access and adequate radio communications.
5.5.6.2.4 Ensure that all representatives and employees of the fiber optic company and its contractor have
been safety trained.
5.5.6.2.5 Follow the construction guidelines in Article 5.5.4 Construction (2001) for any repair or
maintenance work involving alteration of the fiber system.
5.5.6.2.6 Never allow work to disrupt rail operations, including but not limited to, train operations, facilities
maintenance and communications.
5.5.6.2.7 Do not store or place equipment, supplies, materials, tools, or other items within 25 feet (7.62
meters) of the nearest track centerline unless the railroad approves such placement.
5.5.6.2.8 Begin clean-up and restoration immediately upon completion of maintenance operations.
Restore the railroad’s right-of-way to the same condition as prior to the maintenance being performed.
5.5.6.2.9 Remove abandoned fiber optic cable, see Article 5.5.4 Construction (2001). If cable is not
removed, maintain records of the location of abandoned cable.
1
5.5.7 DEFINITIONS (2001)
Aerial Marker Sign: A large sign, typically in the shape of a “V” that can be observed from the air, used for
aerial location and inspection of the fiber system.
As Built: A drawing, depicting the actual location of the fiber cable in relation to the Railroad, having proper
documentation for approval by the Railroad.
3
Ballast: The rock that supports the track and ties. This rock is groomed to keep the track in place, drain water
away from the track and distribute the weight of trains to surrounding soil. Do Not Disturb!
Branchline: A secondary route to the Railroad that, for safety reasons, should be treated as a primary line.
Bridge Attachment: A Railroad approved method of affixing the fiber system to one of the Railroad’s bridges.
Bridge Backwall: The topmost portion of an abutment above the elevation of the bridge bearing, functioning
primarily as a retaining wall for the roadbed.
Bridge Bearing: The contact area and/or physical connection between bridge girders and bridge abutments or
piers (Figure 1-5-5).
Casing: A secondary, independent, rigid covering used to protect the fiber system and the roadbed when installed
under the Railroad’s tracks.
Car: Any vehicle that can move on the track structure and is not self-propelled.
Centerline of Track: An imaginary line, that runs down the center of the two rails of a track.
Conduit: An independent tube or duct system used to house one or more fiber optic cables.
Contractor: Any fiber optic company authorized worker, other than a railroad employee, who is working on
railroad property as a fiber optic company representative or agent.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-5-41
4
Roadway and Ballast
Cut: A section of earth that has been excavated to allow construction of the Railroad’s track where an
embankment remains on one or both sides of the track.
Directional Bore: A method that controls the direction of boring and eliminates conventional bore pits allowing
for a longer bore length than conventional methods.
Dispatcher: A Railroad employee responsible for authorizing all track use, including train movements and
maintenance.
Drawings: A graphic representation of proposed fiber routes, detailed construction plans, or As Builts.
Dry Bore: A method that utilizes conventional bore pits without using a liquid to displace soil.
Encased: A term used to indicate that the fiber system has a secondary, independent, rigid, protective covering.
Engine: The vehicle used to pull cars. Typically this refers to the locomotive, but can be any self-propelled
vehicle.
Excavation: Any removal of earth to allow installation of the fiber system.
Fall Protection: A requirement by the FRA, that ensures training and protection for work performed on any
structure that is at a height of 12 feet (3.66 meters) or more above water or ground, and/or while working at a
height of 12 feet (3.66 meters) or more.
Fiber Optic Company: The company that enters into the agreement with the Railroad and has the ultimate
responsibility for the fiber system. This includes any contractor, employee, or consultant hired by that company.
Fill: A section of earth built up to support the Railroad’s track structure.
Flagger: A railroad employee, who provides for the safe use of the Railroad’s right-of-way.
Foul the Ballast: Anything that contaminates the ballast section of the roadbed and inhibits the ballast from
supporting the track, draining water, or suppressing weed growth.
Foul the Track: Any obstruction that renders the track system unsafe for train passage.
Grout: A cementitious or epoxy substance used to repair concrete, fill holes in concrete, or to anchor bolts, rods,
etc., in concrete. Grout must be approved by the Railroad prior to use.
Handhole: A buried facility that can contain a splice or extra cable.
Hy Rail: A vehicle, typically driven on highways, that has a specially manufactured attachment, that allow the
vehicle to travel on railroad tracks.
Industry Track: A secondary track designed to allow access to industries along the main track.
Innerduct: Flexible independent tubes inside a conduit.
Job Site: Any area where work is performed, where materials and equipment are stored, or which employees
access during the fiber project.
Locate: The determination in the field of the depth and horizontal position of fiber optic systems or other
underground utilities.
Mainline: The primary track used by trains. Some of the routes have double, triple and quadruple mainline
tracks.
Marker signs: Signs placed by the fiber optic company indicate a fiber system is in the area, provide a toll free
number for information regarding the system, and provide the fiber optic company’s name.
Milemarkers: Field indicators of approximate distance from a specific point on the Railroad system used for
approximate locations of Railroad facilities. They are not to be used to establish railroad stationing.
Milepost: A theoretical breakdown of rail lines into mile-long segments.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-42
AREMA Manual for Railway Engineering
Pipelines
On Track Safety: A set of safety rules, developed and promulgated by the FRA, that must be complied with to
work on or near railroad property. Specific training and obedience to these rules is a requirement of the FRA.
Where individual railroad rules are more stringent, those rules shall apply. Significant fines and the loss of your
permission to work on railroad right-of-way, can result from the violation of these rules.
Point of Intersection: A point on a map or drawing indicating the location of a curve in the fiber system. The
point is the vertex of an angle formed by the intersection of two sequential, non-parallel segments of the fiber
system.
Protected Facility: A handhole, manhole or box that can withstand external pressures and protect the fiber
system.
Pull Box: A facility generally used to pull cable through a conduit system.
Railplow: Rail mounted plowing equipment pulled or powered by locomotive power.
Regen: An acronym for a regeneration facility. Typically a building along the fiber system route housing
equipment.
Regen facility: The Regen building and all of its appurtenances such as fences, signs, posts, or other physical
features.
Right-of-way: Land that the Railroad owns or owns an interest in that contains facilities for train operations and
which is utilized in the performance of the fiber project.
Roadbed: The graded area beneath and on either side of the track.
Running Line: Proposed or existing location of the fiber system.
Safety Training: A session conducted by a qualified railroad representative, or it’s agent at which railroad rules
and regulations are presented and discussed.
1
Shoring: Methods and materials used to prevent the collapse of the earthen walls of excavations.
Siding: A secondary track used for the passing of trains on single-track routes.
3
Signal: A Railroad facility used to inform Railroad personnel of track conditions.
Splice: A point in the fiber optic system running line where cables are fused together to create a continuous
system.
Spur Track: A secondary track designed to allow access to industries along the main track.
Switch: A moveable track device that allows trains to transfer from one track to another, encompassing the
distance from the point of switch to the point of frog. (See Figure 1-5-10).
Tracks: The rails, ties and ballast and roadbed that compose the traveling surface used by trains.
Track Structure: The rails, ties, ballast and roadbed that compose the traveling surface used by trains.
Trains: One or more engines coupled together, with or without cars that use the Railroad’s tracks.
Train Movement: Any motion of engines and/or cars over the Railroad’s tracks.
Trench: A narrow section of earth removed to allow installation of the fiber system.
Valuation Map: A Railroad map depicting the Railroad’s facilities and engineering stationing.
Wet Bores: Are bores that use liquid to displace soil.
Yard: A collection of secondary tracks used to store equipment (cars, engines, maintenance machines, etc.),
assemble or disassemble trains, and/or conduct other Railroad operations.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-5-43
4
Roadway and Ballast
5.5.8 ABBREVIATIONS (2001)
AASHTO: American Association of State Highway and Transportation Officials
ANSI: American National Standards Institute
AREMA: American Railway Engineering and Maintenance-of-Way Association
ASTM: American Society for Testing and Material
BIP: Black Iron Pipe
Br.: Bridge
CE: Chief Engineer
CIP: Corrugated Iron Pipe
CL/Trk: Center Line of Track
CMP: Corrugated Metal Pipe
Conc.: Concrete
C/L: centerline
FIBOCO: An acronym for the fiber optic company
FRA: Federal Railroad Administration
F/L: Flow Line
GSP: Galvanized Steel Pipe
HDPE: High Density Polyethylene Plastic
HH: Handhole
Lt.: Left
MH: Manhole
MM: Mile Marker
MP: MilePost
OSHA: Occupational Health & Safety Administration
PI: Point of Intersection
PVC: Polyvinyl Chloride Plastic
Rt.: Right
R/L: Running Line
R/W: Right-of-way
R-O-W: Right-of-way
Xing: Crossing
5.5.9 APPENDIX (2001)
List of Exhibits:
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-44
AREMA Manual for Railway Engineering
Pipelines
A: METHODOLOGY FOR EQUATING FIBER OPTIC CABLE LOCATIONS TO RAILROAD TRACK AND
RIGHT-OF-WAY MAPS
B: BRIDGE DEFINITION
C: CABLE DEPTH AROUND CULVERTS AND DITCHES
D: BORE PIT LOCATION
E: REGEN LOCATION
F: CONVENTIONAL FILL INSTALLATION
G: STANDARD TURNOUT (TRACK SWITCH)
H: GENERAL SHORING REQUIREMENTS
I: DIRECTIONAL BORE FILL INSTALLATION
J: INSTALLATION ON TOP OF CUT
1
3
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-5-45
Roadway and Ballast
1-5-46
AREMA Manual for Railway Engineering
© 2010, American Railway Engineering and Maintenance-of-Way Association
Figure 1-5-4. Methodology for Equating Fiber Optic Cable Locations to Railroad Track & Right-of-Way Maps
Pipelines
1
3
4
Figure 1-5-5. Bridge Definition
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-5-47
Roadway and Ballast
Figure 1-5-6. Cable Depth Around Culverts and Ditches
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-48
AREMA Manual for Railway Engineering
Pipelines
1
3
4
Figure 1-5-7. Bore Pit Location
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-5-49
Roadway and Ballast
Figure 1-5-8. Regen Location
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-50
AREMA Manual for Railway Engineering
© 2009, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
Pipelines
1-5-51
Figure 1-5-9. Conventional Fill Installation
Roadway and Ballast
Figure 1-5-10. Standard Turnout
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-52
AREMA Manual for Railway Engineering
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
Pipelines
1-5-53
Figure 1-5-11. General Shoring Requirements
Roadway and Ballast
1-5-54
AREMA Manual for Railway Engineering
© 2010, American Railway Engineering and Maintenance-of-Way Association
Figure 1-5-12. Fill Installation Directional Bore
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
Pipelines
1-5-55
Figure 1-5-13. Installation on Top of Cut
Roadway and Ballast
THIS PAGE INTENTIONALLY LEFT BLANK.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-5-56
AREMA Manual for Railway Engineering
1
Part 6
Fences1
— 1994 —
TABLE OF CONTENTS
Section/Article
Description
Page
6.1 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-6-3
6.2 Specifications for Wood Fence Posts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.2.1 Material (1994) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.2.2 Physical Requirements (1994) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.2.3 Design (1987) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.2.4 Manufacture (1987) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.2.5 Inspection (1991) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.2.6 Delivery (1991). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.2.7 Preservative Treatment (1991) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-6-4
1-6-4
1-6-4
1-6-5
1-6-5
1-6-6
1-6-6
1-6-6
6.3 Specifications for Concrete Fence Posts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.3.1 Materials (1991). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.3.2 Proportioning and Mixing (1991) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.3.3 Manufacturer (1991) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-6-6
1-6-6
1-6-7
1-6-7
6.4 Specification for Metal Fence Posts. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.4.1 Classes (1987) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.4.2 Material (1987) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.4.3 Workmanship (1987) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.4.4 Finish (1987) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.4.5 Special Fabrication for Line Posts (1987) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.4.6 Special Fabrication for End, Corner, and Gate Posts (1987) . . . . . . . . . . . . . . . . . . . . . . .
6.4.7 Weights and Shapes (1987) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.4.8 Inspection (1987) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-6-10
1-6-10
1-6-10
1-6-10
1-6-10
1-6-11
1-6-11
1-6-11
1-6-13
6.5 Specifications for Right-of-way Fences . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.5.1 General (1987) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.5.2 Material (1991) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.5.3 Erection (1991) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-6-13
1-6-13
1-6-17
1-6-18
1
References, Vol. 43, 1942, pp. 510, 731; Vol. 54, 1953, pp. 1091, 1385; Vol. 63, 1962, pp. 590, 752; Vol. 67, 1966, pp. 537, 740; Vol. 88, 1987,
pp. 34; Vol. 92, 1991, p. 40; Vol. 94, 1994, p. 31.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-6-1
1
3
Roadway and Ballast
TABLE OF CONTENTS (CONT)
Section/Article
Description
Page
6.6 Stock Guards . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.6.1 General (1991) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-6-20
1-6-20
6.7 Methods of Controlling Drifting Snow. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.7.1 Justification and Scope (1994) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.7.2 References (1994) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.7.3 Definitions and Terminology (1994) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.7.4 Specifications for Roadbed Geometry (1994) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.7.5 Specifications for Clearing and Mowing Vegetation (1994) . . . . . . . . . . . . . . . . . . . . . . . .
6.7.6 Specifications for Placement of Bungalows and Other Structures (1994) . . . . . . . . . . . .
6.7.7 Temporary Control Measures (1994) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-6-21
1-6-21
1-6-21
1-6-21
1-6-22
1-6-23
1-6-23
1-6-23
6.8 Specifications for Snow Fences. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.8.1 Effectiveness and Applications (1994). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.8.2 Structural Fences (1994) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.8.3 Tree and Shrub Plantings (1994) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-6-24
1-6-24
1-6-24
1-6-39
LIST OF FIGURES
Figure
1-6-1
1-6-2
1-6-3
1-6-4
1-6-5
1-6-6
1-6-7
1-6-8
1-6-9
1-6-10
1-6-11
1-6-12
1-6-13
1-6-14
1-6-15
1-6-16
1-6-17
1-6-18
1-6-19
1-6-20
1-6-21
1-6-22
Description
Page
Plan of Concrete Fence Posts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Typical Cross Sections of Steel Fence Posts Commonly Available. . . . . . . . . . . . . . . . . . . . . . .
Class A Fence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Class B Fence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Class C Fence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Class D Fence. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Guidelines for Minimum Height of Roadbed above Grade . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Recommended Cut Section to Prevent Snowdrift Encroachment . . . . . . . . . . . . . . . . . . . . . . .
Snow Storage Capacity Versus Effective Fence Height . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Definition of Terms in the Calculation of Snow Transport . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Shape of Equilibrium Drifts Formed by 50% Porous Snow Fences Having
Effective Height H. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Illustration of Three-dimensional Rounding of Drifts at Fence Ends . . . . . . . . . . . . . . . . . . . .
Placement of Fences when Wind Angle  is less than 65 degrees . . . . . . . . . . . . . . . . . . . . . . .
Stepping-down Height at Fence Ends Allows Fences to be Placed Closer to Track and
Improves Effectiveness . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Herringbone Arrangement is Effective in Reducing Drifting Snow When Wind is
Aligned Parallel to Track . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Extending Snow Fences Beyond Protected Area Compensates for “End Effect” and
Variations in Prevailing Wind Direction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Effect of Bottom Gap on Storage Capacity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
How Snow Storage Capacity Varies With Snow Fence Porosity . . . . . . . . . . . . . . . . . . . . . . . .
How Length of Downwind Drift Varies With Snow Fence Porosity . . . . . . . . . . . . . . . . . . . . .
Generic Plan for the “Wyoming” Snow Fence with Vertical Height H . . . . . . . . . . . . . . . . . . .
U-clip Used to Attach “Wyoming” Fence to Re-bar Anchor . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Panel Placement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1-6-8
1-6-11
1-6-13
1-6-14
1-6-15
1-6-16
1-6-22
1-6-23
1-6-25
1-6-25
1-6-26
1-6-26
1-6-27
1-6-28
1-6-28
1-6-29
1-6-30
1-6-31
1-6-31
1-6-33
1-6-33
1-6-35
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-6-2
AREMA Manual for Railway Engineering
Fences
LIST OF FIGURES (CONT)
Section/Article
1-6-23
1-6-24
1-6-25
1-6-26
Description
Plastic Fencing Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Methods for Accommodating Slope Changes Using Synthetic Materials . . . . . . . . . . . . . . . . . .
Recommended Planting Arrangement for Locations Having Moderate Snow Transport. . . . .
Snowbreak Forest. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Page
1-6-38
1-6-38
1-6-39
1-6-40
LIST OF TABLES
Table
1-6-1
1-6-2
1-6-3
1-6-4
1-6-5
1-6-6
1-6-7
1-6-8
1-6-9
1-6-10
1-6-11
Description
Design and Dimensions of Fence Posts. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Compressive Strength Variances. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Curing Duration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Metal Quality . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Nominal Weights of Line Posts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Nominal Weights of End, Gate and Corner Assemblies. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Wire Tensile Strength . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Range of Fence Heights Required in U.S.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
“Wyoming-Type” Snow Fence Construction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Wood Pole Sizes and Specifications. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Embedment Depth . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Page
1-6-5
1-6-7
1-6-9
1-6-10
1-6-12
1-6-12
1-6-17
1-6-25
1-6-34
1-6-36
1-6-36
1
SECTION 6.1 GENERAL
This Part of the Chapter is prepared for the purpose of presenting specifications for various types of fencing and
components.
3
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-6-3
Roadway and Ballast
SECTION 6.2 SPECIFICATIONS FOR WOOD FENCE POSTS
6.2.1 MATERIAL (1994)
6.2.1.1 Kinds of Wood
The manufacturer may furnish posts made from any of the following woods listed unless otherwise specified by the
purchaser.
With the exception of Redwood, all kinds of wood should receive preservative treatment.
Black Locust
Black Walnut
Ash
Hackberry
Cypress
Heart Yellow Pine
Beech
Maple
Catalpa
Larch
Birch
Red Oak
Cedar
Red Mulberry
Black Gum
Sap Yellow Pine
Chestnut
Redwood
Cherry
Sap Fir
Douglas Fir
White Oak
Elm
Sycamore
Hickory
6.2.2 PHYSICAL REQUIREMENTS (1994)
6.2.2.1 Defect1
Posts shall be free from the following defects: decay, excessive crook, wane on rectangular posts, holes in top of
post, numerous holes, large knots, large shakes and splits.
6.2.2.2 Defects Allowable1
a.
In round cedar posts, pipe or stump rot up to 0.75 inch in diameter in butt end.
b.
Peck in cypress up to limitation of holes.
c.
Crook that does not exceed 3 inches measured perpendicular between the longitudinal axis and a straight
line from the center of one end to the center of the other end.
d.
Wane on rectangular posts not exceeding one-fourth of the dimension of the faces.
e.
Holes other than in top of post not exceeding 1 inch in diameter and 3 inches deep.
f.
Numerous holes that are not damaging in effect.
g.
Knots in round posts whose average diameter is less than one-third the diameter of post.
h. Knots in rectangular posts whose average diameter is less than 0.25 the width of surface in which the knot
appears.
i.
1
Numerous knots that are not damaging in effect.
For definition of terms please see “Definition of Terms Used in Describing Standard Grades for Lumber,” Chapter 7, Timber
Structures, Part 1, Material Specifications for Lumber, Timber, Engineered Wood Products, Timber Piles,
Fasteners, Timber Bridge Ties and Recommendations for Fire-Retardant Coating for Creosoted Wood.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-6-4
AREMA Manual for Railway Engineering
Fences
j.
Large shakes in rectangular posts whose maximum dimension between parallel lines does not exceed 0.25 of
the minimum thickness of post.
k.
In round posts shakes not damaging in effect.
l.
Splits not damaging in effect.
6.2.3 DESIGN (1987)
6.2.3.1 General
Posts shall be of the size and dimensions specified in the order.
6.2.3.2 Dimensions
All posts shall be in accordance with the designs and dimensions shown in Table 1-6-1.
Table 1-6-1. Design and Dimensions of Fence Posts
Dimensions
Intermediate
or Line Posts
Design
At Small End
End, Corner, Anchor
and Gate Posts
Length
At Small End
Length
4 inch diameter
7 feet
8 inch diameter
8 feet
5 inch diameter
8 feet
–
–
Rectangular 4" × 4"
7 feet
8" × 8"
8 feet
5" × 5"
8 feet
–
–
19 inch perimeter
7 feet
–
–
21 inch perimeter
8 feet
–
–
19 inch perimeter
7 feet
–
–
21 inch perimeter
8 feet
–
–
Round
Halved
Quartered
1
3
4
6.2.4 MANUFACTURE (1987)
6.2.4.1 General Requirements
All posts shall be straight, well manufactured, of natural taper, free from projections and cut square at ends unless
small end is roofed. Inner skin must be removed and roofing or gaining of treated posts shall be done before
treatment.
6.2.4.2 Tolerances
a.
Posts shall not be more than 1 inch shorter nor 3 inches longer than the length specified.
b.
Posts shall not be more than 1/4 inch smaller nor more than 1 inch larger than the diameters, widths and
perimeters specified.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-6-5
Roadway and Ballast
6.2.5 INSPECTION (1991)
6.2.5.1 General
All materials and all processes of manufacture shall be subject to inspection and approval at all times. Free access
shall be provided during regular working hours for all authorized inspectors to all parts of the manufacturing
facility in which the posts or materials are made, stored or prepared.
6.2.5.2 Manner
Inspectors will make a reasonably close inspection of each post, which shall be judged independently, without
regard for decisions on others in the same lot. Posts too soiled for ready examination will be rejected. Posts shall be
turned over as inspected.
6.2.6 DELIVERY (1991)
6.2.6.1 Separated as Specified
Posts shall be separated according to the kind of wood, shape and size or as may be required in the order for them.
6.2.7 PRESERVATIVE TREATMENT (1991)
6.2.7.1 Specifications
Posts shall be treated in accordance with the AREMA specifications see Chapter 30, Ties, Part 1, General
Considerations.
SECTION 6.3 SPECIFICATIONS FOR CONCRETE FENCE POSTS
6.3.1 MATERIALS (1991)
Cement, aggregate, water and metal reinforcement shall conform in quality to the AREMA specifications see,
Chapter 8, Concrete Structures and Foundations, Part 1, Materials, Tests and Construction Requirements, with
the following exceptions:
• The maximum size of aggregate shall be not more than three-quarters the clear embedment distance.
• Reinforcement shall be in the form of round or square bars or cold drawn steel wire. Crimped, stranded or
flat reinforcement shall not be used.
• Where choices can be made between sizes of reinforcement, it is preferable to use the larger number of
smaller bars.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-6-6
AREMA Manual for Railway Engineering
Fences
6.3.2 PROPORTIONING AND MIXING (1991)
Proportioning and mixing concrete shall be in accordance with the AREMA specifications see, Chapter 8, Concrete
Structures and Foundations, Part 1, Materials, Tests and Construction Requirements, with the exception that
the compressive strength of concrete shall vary with the amount of clear imbedment of reinforcement, as shown in
Table 1-6-2.
Table 1-6-2. Compressive Strength Variances
Clear Imbedment
Inches
Class of Concrete
Compression Strength
Psi at 28 Days
Gallons of Water per
Sack of Cement
3/4
3500
5.00
1/2
4000
4.50
3/8
4500
4.00
6.3.3 MANUFACTURER (1991)
6.3.3.1 General
1
The concrete fence post shall be manufactured in accordance with the dimensions shown in Figure 1-6-1.
6.3.3.2 Molds
Molds shall be substantial, true to plan and preferably of metal. They shall be thoroughly cleaned before concrete is
placed.
3
6.3.3.3 Placing Reinforcing
The reinforcing shall be securely held in position during the placing and setting of concrete. Spacers that would
cause distinct lines of cleavage shall not be used.
6.3.3.4 Compacting
Concrete shall be thoroughly compacted into the molds and around the reinforcing. This is best accomplished by
high frequency vibration of the molds.
6.3.3.5 Finish
Imperfections such as exposure of reinforcing, sand streaking due to loss or lack of cement paste, honeycomb
clusters or pockets of coarse aggregate without proper mixture of the finer components of concrete, cracks or other
evidence of improper mixing or faulty construction shall cause the rejection of the post. Patching will not be
permitted.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-6-7
4
Roadway and Ballast
Figure 1-6-1. Plan of Concrete Fence Posts
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-6-8
AREMA Manual for Railway Engineering
Fences
6.3.3.6 Curing
a.
Curing shall start immediately after placement of concrete and shall extend for the following periods of time
depending upon the temperature being maintained uniformly during the curing period shown in Table 1-63.
Table 1-6-3. Curing Duration
Approximate Temperature
Degree F
b.
Curing Period in Days
50
14
70
10
90
7
120
2
Temperatures exceeding 140 degrees F must not be used. No evaporation or other loss of moisture from the
concrete shall be permitted during curing period, or while cooling off after heat curing.
6.3.3.7 Inspection
All materials and all processes of manufacture shall be subject to inspection and approval at all times. Free access
shall be provided for all authorized inspectors to all parts of the plant in which the posts or the materials are made,
stored or prepared.
1
6.3.3.8 Tests
a.
b.
Posts should be carefully made so as to secure a uniform strength in substantially all posts, and this
strength should usually be such that the post will withstand a force of not less than 180 lb at right angles to
the axis of the post, the post acting as a cantilever beam supported at the ground line and the force being
applied 5 feet above the ground line.
3
During the curing or cooling off period, posts submerged in water for 2 hr and wiped off, shall not show an
increase in weight.
6.3.3.9 Patents
4
The manufacturer shall pay all royalties for the use of patented designs or devices or forms of construction and
protect the railway company from all claims of infringement or liability for use of such patents.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-6-9
Roadway and Ballast
SECTION 6.4 SPECIFICATION FOR METAL FENCE POSTS
6.4.1 CLASSES (1987)
Metal fence posts shall be divided into two classes:
a.
Posts which support the straightaway body of the fence shall be designated as line posts.
b.
Such other special posts as are needed at the end or corner of the fence and at gates, shall be designated as
end, corner, and gate posts.
6.4.2 MATERIAL (1987)
Posts shall be fabricated from hot rolled steel sections meeting either of the requirements shown in Table 1-6-4.
Table 1-6-4. Metal Quality
Tensile Properties
Grade
Hot rolled carbon steel-minimum carbon content 0.35%
Hot rolled rail steel (Note 1)
Yield Str.
Psi
Ult. Str.
Psi
40,000 min 70,000 min
50,000
80,000 min
Note 1: As defined in the U.S. Bureau of Standards Commercial Standard CS150-48,
rail steel products shall be rolled from standard Tee-Section steel Rails. No
other material such as those known by terms “rerolled”, “rail steel
equivalent”, and “rail steel quality” shall be substituted.
6.4.3 WORKMANSHIP (1987)
All posts shall be smoothly rolled or formed and shall be straight throughout their length. Each finished post shall
be free from burrs or other deformation caused by fabrication. They shall also be free from slivers, depressions,
seams, crop ends and evidence of being burnt. (The above does not refer to rough places caused by zinc coating
when galvanized.)
Excessive bow, camber, twist, or other injurious defects shall be considered cause for rejection of such posts.
6.4.4 FINISH (1987)
a.
Painted posts shall be cleaned of all loose scale prior to finishing and one or more coats of high grade,
weather-resistant, special steel paint or enamel shall be applied and baked.
b.
Galvanized posts shall be galvanized by the hot dip process and shall possess a uniform coating of Prime
Western spelter or better grade, with not less than 2 oz per square foot of surface.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-6-10
AREMA Manual for Railway Engineering
Fences
6.4.5 SPECIAL FABRICATION FOR LINE POSTS (1987)
a.
Line posts shall be fabricated to the section agreed upon by the purchaser.
b.
Line posts shall be tee, U, Y, channel, or other suitable section and shall have corrugations, knobs, notches,
holes, or studs so placed and constructed as to engage at least 12 fence line wires in proper position in a
height of 5 feet above the surface of the ground. Posts may be punched with holes in such position and of
such size as will not impair the strength of the post.
c.
If the posts are not so designed as to make anchorage for alignment unnecessary an anchorage device shall
be rigidly fabricated to bottom portion of posts. Anchor plates on line posts shall weigh 0.67 lb or more each
and shall be tapered to facilitate driving. Anchor plates shall be clamped, welded, or riveted to the posts in a
substantial manner to prevent displacement of anchor plates when posts are driven.
d.
All posts shall permit the refastening of the wire at least five times without damage to the connection
appliance, if an integral part of the post.
e.
All posts shall be capable of being driven in ordinary earth without injury to the post.
f.
All posts shall have sufficient length so that when installed with the required height above ground, 1/3 of
the total length shall be underground, providing that the post shall extend into the ground not less than 21/2 feet.
6.4.6 SPECIAL FABRICATION FOR END, CORNER, AND GATE POSTS (1987)
End, corner, and gate post assemblies shall be angle sections consisting of 2-1/2" × 2-1/2" × 1/4" uprights and the
required number of braces, either 2" × 2" × 1/4" or an alternate of approximately equal weight, such as a 2-1/2" ×
2-1/2" of appropriate thickness. For joining the uprights and braces shall be supplied with the necessary holes and
bolts of standard commercial quality or other satisfactory substitute, such as castings. All posts shall have
sufficient length to permit installing 3 feet into the ground.
3
6.4.7 WEIGHTS AND SHAPES (1987)
a.
Sketches shown are suggestive of typical cross sections commonly supplied. Sizes shown in Figure 1-6-2 are
approximately half scale, however, both overall and thickness dimensions will vary with individual post
designs. All sections will conform to standard nominal weight of 1.33 lb per foot.
b.
Sections shown do not illustrate features for attaching fence wire and preventing vertical displacement,
such as rolled in lugs, notches, studs, corrugations, or punched oval, round or slotted holes.
Figure 1-6-2. Typical Cross Sections of Steel Fence Posts Commonly Available
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1
1-6-11
4
Roadway and Ballast
6.4.7.1 Nominal Weight
a.
Line posts shall have a nominal weight of 1.33 lb per foot, exclusive of anchor plate.
b.
Angle type end, corner and gate posts shall have a nominal weight of 4.10 lb per ft for upright members and
bracing members shall have a nominal weight of 3.19 lb per ft.
c.
Permissible variation in weight shall be a maximum of 3-1/2% over or under nominal weight shown in
Table 1-6-5 and Table 1-6-6. Weights are to be taken on the total lot of posts in each order.
d.
Permissible variation in length shall be a maximum of 1 inch, under and 2 inches over the designated length
of the post.
Table 1-6-5. Nominal Weights of Line Posts
Post Lengths
Feet
Weight (Note 1)
Pounds
5
7.32
5-1/2
7.99
6
8.65
6-1/2
9.32
7
9.98
7-1/2
10.65
8
11.31
Note 1: Includes anchor plates and paint.
Table 1-6-6. Nominal Weights of End, Gate and Corner Assemblies
Post Assembly
Length
Feet
Weight (Note 1)
Pounds
End or gate (1 brace)
7
51
Corner (2 braces)
7
73
End or gate (1 brace)
8
58
Corner (2 braces)
8
84
End or gate (1 brace)
9
66
Corner (2 braces)
9
94
Note 1: Includes weight of paint and bolts.
6.4.7.2 Formed Wire Fasteners
Each line post shall be furnished with not less than 5 suitable galvanized wire fasteners or clamps of not less than
0.120 inch in diameter for attaching the fence wires to the post. Ordinary wire staples will not be considered
suitable fasteners.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-6-12
AREMA Manual for Railway Engineering
Fences
6.4.8 INSPECTION (1987)
Inspection and approval of the posts shall be made by the engineer or other authorized representative of the
purchaser. Such inspection shall be made at the plant of the manufacturer, who will allow the inspector access to all
operations involved and shall facilitate as much as possible the work of inspection and provide necessary facilities
for inspection. Posts selected by the inspector at random, shall be inspected, and if they meet the requirements, the
lot shall be accepted.
SECTION 6.5 SPECIFICATIONS FOR RIGHT-OF-WAY FENCES
6.5.1 GENERAL (1987)
6.5.1.1 Classes
The height and construction of right-of-way fences shall conform to statutory requirements. Standard right-of-way
fences shall be divided into four classes.
6.5.1.2 Class A Fence (See Figure 1-6-3)
a.
Class A fence shall consist of 9 longitudinal smooth galvanized steel wires; the longitudinal and stay wires
shall be No. 9 gage.
b.
The spacing of the longitudinal wires (commencing at the bottom) shall be 4, 4-1/2, 5, 5-1/2, 6, 7, 8 and
9 inches. The bottom wire shall be 5 inches above the ground and the stay wires shall be spaced 12 inches
apart.
c.
When used as a hog-tight fence, a strand of barbed wire shall be added 2-1/2 inches below the woven
wire.
1
3
4
Figure 1-6-3. Class A Fence
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-6-13
Roadway and Ballast
6.5.1.3 Class B Fence (Figure 1-6-4)
a.
Class B fence shall consist of 7 longitudinal smooth galvanized steel wires; the longitudinal and stay wires
shall be No. 9 gage.
b.
The spacing of the longitudinal wires, commencing at the bottom shall be 6-1/2, 7, 7-1/2, 8, 8-1/2 and
9 inches. The bottom wire shall be 7 inches above the ground and stay wires shall be spaced 12 inches
apart.
Figure 1-6-4. Class B Fence
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-6-14
AREMA Manual for Railway Engineering
Fences
6.5.1.4 Class C Fence (Figure 1-6-5)
Class C Fence shall consist of woven wire fencing 25-1/2 inches high with 3 strands of barbed wire above. The
woven wire fencing shall consist of 7 longitudinal, smooth galvanized steel wires. The longitudinal and stay wires
shall be No. 9 gage and the stay wires shall be 12 inches apart. The spacing of the longitudinal wires, commencing
at the bottom, shall be 3, 3-1/2, 4, 4-1/2, 5 and 5-1/2 inches, and the bottom wire shall be 2 inches above the ground.
The spacing of the barbed wires above the woven wire shall be 4-1/2, 10 and 12 inches.
1
3
Figure 1-6-5. Class C Fence
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-6-15
Roadway and Ballast
6.5.1.5 Class D Fence (Figure 1-6-6)
a.
Class D Fence shall consist of 5 strands of galvanized steel ribbon, smooth round or barbed wire fencing.
b.
The spacing of the wires, commencing at the bottom, shall be 10, 10, 12 and 12 inches. The bottom wire
shall be 10 inches above the ground.
c.
The longitudinal wires of all woven wire fencing under Classes A, B and C shall be provided with tension
curves to take up expansion and contraction.
Figure 1-6-6. Class D Fence
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-6-16
AREMA Manual for Railway Engineering
Fences
6.5.2 MATERIAL (1991)
6.5.2.1 Intermediate or Line Posts
See Section 6.2, Specifications for Wood Fence Posts, Section 6.3, Specifications for Concrete Fence Posts,
Section 6.4, Specification for Metal Fence Posts.
6.5.2.2 End, Corner, Anchor and Gate Posts
See Section 6.2, Specifications for Wood Fence Posts, Section 6.3, Specifications for Concrete Fence Posts,
Section 6.4, Specification for Metal Fence Posts.
6.5.2.3 Braces
Braces for end, corner, anchor and gate posts shall be made of intermediate or line posts, or 4" × 4" sawed lumber
of a quality equal to the specifications for wood fence posts. Where concrete posts are used, 4" × 4" concrete braces
are recommended.
6.5.2.4 Wire
Barbed wire and woven wire fencing shall be constructed of a good commercial quality galvanized steel wire. If
copper-bearing base metal is used, the copper content shall not be less than 0.2%. Wire for fencing must stand,
without sign of fracture, winding tight around wire of the same size; and it shall have a minimum ultimate tensile
strength as shown in Table 1-6-7.
1
Table 1-6-7. Wire Tensile Strength
Type
Tensile Strength (Min)
Line Wire No. 7 Gage
2200 lb
Line Wire No. 9 Gage
1500 lb
Line Wire No. 12-1/2
Gage
700 lb
Stay Wire No. 9 Gage
1100 lb
3
4
6.5.2.5 Locks
The locks or fastenings at the intersection of the longitudinal and stay wires shall be of such design as will prevent
them from slipping either longitudinally or vertically.
6.5.2.6 Fastenings
Staples used for fastening the longitudinal wires to wood posts shall be made of No. 9 galvanized steel wire. They
shall be 1 inch long for hardwood and 1-1/2 inches long for softwood. Fastenings for concrete and steel posts to be
as indicated under specifications for these posts.
6.5.2.7 Galvanizing
a.
The galvanizing of wire shall consist of a uniform coating of zinc, the weight of which shall be not less than
1.20 oz per sq ft of surface treated. For woven wire, ASTM A116, and for barbed wire, ASTM A121 is to be
complied with.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-6-17
Roadway and Ballast
b.
The weight of coating shall be determined by a stripping test; using the hydrochloric acid-antimony chloride
method. Since the density of steel (0.283 lb per cubic inch.) is known, it is only required to determine the
diameter of the stripped wire and the ratio of the weight of zinc to the weight of the stripped wire. The
sample of galvanized wire may be of any length over 12 inches, but preferably about 24 inches. It shall be
cleaned with gasoline or benzine and dried thoroughly, then weighed carefully to 0.01 g. The sample shall
then be stripped of the zinc coating by immersing in hydrochloric acid (concentrated HCl with sp gr 1.19) to
which has been added antimony chloride solution (made by dissolving 20 g of antimony trioxide Sb O, or 32
g of antimony trichloride SbCl in 1000 cc of hydrochloric acid HCl of sp gr 1.19) in the proportion of 1 cc of
the antimony chloride solution to each 100 cc of hydrochloric acid. As soon as the violent chemical action on
the wire ceases the wire shall be removed from the acid, washed in water and wiped dry. Its diameter shall
then be measured to 0.001 inch by taking the mean of two measurements at right angles to each other. The
stripped sample is then weighed to 0.01 g. The original weight (W1) minus the stripped weight (W2) divided
by the stripped weight (W2) gives the ratio (r) of the zinc to iron for the sample under test. The weight of
coating in ounces per square foot of stripped wire surface is determined by multiplying the constant 163 by
the diameter (d) in inches of the stripped wire by the above ratio. This calculation may be expressed by the
following formula:
Ounces of zinc per square foot of stripped wire surface = 163 dr
where:
d = diameter in inches of the stripped wire
W1 – W2
r = ----------------------W2
6.5.2.8 Manufacture
a.
In barbed wire the twist shall be uniform throughout and so twisted that the strain shall come equally on all
strands.
b.
The horizontal wires of all woven wire fencing may be provided with tension curves to compensate for
expansion and contraction.
c.
The fencing shall be so fabricated as not to remove any of the galvanizing or impair the tensile strength of
the wire.
6.5.3 ERECTION (1991)
6.5.3.1 End, Corner, Anchor and Gate Posts
End corner, anchor and gate posts shall be set vertical, at least 3'–4" in the ground, thoroughly tamped, braced and
anchored. In long runs of fence, anchor posts shall be spaced not more than 1/4 mile apart.
6.5.3.2 Intermediate or Line Posts
Intermediate or line posts shall be set at least 2'–4" in the ground and not more than 16'–6" apart, center to center.
The first line post from any corner, anchor or gate post shall be set 10 feet, center to center, from the same.
6.5.3.3 Post Holes
a.
Holes of full depth shall be provided for all end, corner, anchor, and gate posts, even if blasting must be
resorted to. Posts may be installed in drilled holes of the same dimension as the post and the post made firm
in place, or they may be installed in larger drilled or dug holes and backfilled and compacted. For
intermediate or line post, where rock is encountered, not more than two adjacent wood posts shall be set on
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-6-18
AREMA Manual for Railway Engineering
Fences
sills 6" × 6" × 4' long, braced on both sides by 2'–6" inch braces, 3 feet long. Holes shall be provided for all
other posts. Posts shall be set with large end down and in perfect line on the side on which the wire is to be
strung. After the fence is erected, the tops of the wood posts shall be sawed off with a 1/4 pitch, the high side
being next to the wire and 2 inches above it.
b.
Backfill of post holes shall be compacted by mechanical means to at least 90% of the ASTM D1557 maximum
density at moisture content of within 4% of optimum. An acceptable alternate method of backflll would be
the use of a sand-cement slurry consisting of 2 sacks of cement per cubic yard of clean, washed concrete sand
and sufficient water to produce a thick slurry. This slurry would be placed in the post holes.
6.5.3.4 Anchoring
Wood end, corner, anchor and gate posts shall be anchored by gaining and spiking two cleats to the side of the
posts, at right angles to the line of the fence, one at the end bottom, the other just below the surface of the ground.
The cleat near the ground surface shall be put on the side next the fence and the bottom cleat shall be put on the
opposite side. Intermediate wood posts set in depressions of the ground shall be anchored by gaining two cleats into
the side near the bottom of the post, same to be properly spiked.
6.5.3.5 Cleats, Sills, Etc.
All cleats shall be 2" × 6" × 2' long. All sills, braces and cleats shall be made of sawed lumber of a quality equal in
durability to that of the posts.
6.5.3.6 Bracing
End, corner, anchor and gate posts shall be braced by using an intermediate or line post or a 4" × 4" brace gained
into the end, corner, anchor or gate post, about 12 inches from the top and into the next intermediate or line post
about 12 inches from the ground and be securely fastened. A cable made of a double strand of No. 9 galvanized soft
wire looped around the end, corner, anchor or gate post near the ground line, and around the next intermediate or
line post about 12 inches from the top, shall be put on and twisted until the top of next intermediate or line post is
drawn back about 2 inches.
6.5.3.7 Stretching
1
3
Longitudinal wires shall be stretched uniformly tight and parallel; stays shall be straight, vertical and uniformly
spaced. Wires shall be placed on the side of the post away from the track, except that on curves of 1 degree or more
the wires shall be placed on the side of the post away from the center of the curve.
4
6.5.3.8 Stapling
Staples shall be set diagonally with the grain of the wood and driven home tight. The top wires shall be double
stapled.
6.5.3.9 Splicing
Approved bolt clamp splice or a wire splice made as follows may be used: The ends of the wires shall be carried 3
inches past the splicing tools and wrapped around both wires backward from the tool for at least five turns, after
the tool is removed, the space occupied by it shall be closed by pulling the ends together.
6.5.3.10 Gates
a.
A hinged metal gate is recommended.
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-6-19
Roadway and Ballast
b.
The width of farm gates should be not less than 12 feet depending upon the size of agricultural machinery in
use in the vicinity, or as required by the laws of the states through which the railway operates. The
minimum height of farm gates should be 4'–6" from the surface of the roadway.
c.
Farm gates should be hinged so as to open away from the track, and, if hinged, swing shut by gravity, and
the end of the gate opposite the hinged end should lap by the post a sufficient distance to prevent it from
being opened by side pressure.
SECTION 6.6 STOCK GUARDS
6.6.1 GENERAL (1991)
a.
A stock guard should be so constructed as to avoid projecting surfaces liable to be caught by loose or
dragging portions of equipment.
b.
It should be effective against all livestock, have no parts which would catch or hold animals or unnecessarily
endanger employees who pass over it in the discharge of their duties.
c.
It should be reasonable in first cost, durable and easily applied and removed, so as to permit repairs to track
at minimum expense.
d.
It should not rattle during passage of trains.
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-6-20
AREMA Manual for Railway Engineering
Fences
SECTION 6.7 METHODS OF CONTROLLING DRIFTING SNOW
6.7.1 JUSTIFICATION AND SCOPE (1994)
a.
Although snow fences have been used to protect railways in the U.S. since the 1870’s, the need for passive
snow control was diminished by the development of rotary snow plows and more powerful locomotives, and
by the increasing frequency of train traffic that helped to keep drifts from blocking tracks. In recent years,
however, the need for drift control on railroads has been renewed by technological advances. Remotely
controlled switches must be free of snow and ice, and thermal scanners are subject to dysfunction when
snow or ice accumulates in the optical path. In addition, the increasing costs of derailments adds incentive
for drift protection.
b.
The methods for preventing or mitigating drifting snow problems discussed here are 1) elevating the road
bed above grade, 2) widening cuts to allow the wind to keep tracks blown clear and to provide space for snow
to accumulate without encroaching on the tracks, 3) clearing and mowing vegetation along the roadway, 4)
placement of bungalows and other structures to prevent the drifts formed by these structures from affecting
operations, 5) plowing snow ridges or berms, 6) erecting snow fences, and 7) planting trees and shrubs.
6.7.2 REFERENCES (1994)
The guidelines presented here are adapted from the following references, which may be consulted for more detailed
information. The References are located at the end of this chapter.
1
• Design Guidelines for the Control of Blowing and Drifting Snow (Reference 14).
• Snow Fence Guide (Reference 48).
• Drifting Snow (Reference 16).
6.7.3 DEFINITIONS AND TERMINOLOGY (1994)
3
Definitions and terminology are listed here and defined in the Glossary located at the end of this chapter.
Bottom Gap
Setback Distance, D
Effective Fence Height, H
Snowfall Water-Equivalent
End-Effect
Snow Storage Capacity
Equilibrium Drift
Snow Transport
Fetch
Snow-Trapping Efficiency
Porosity Ratio, P
Wind Angle, 
4
© 2010, American Railway Engineering and Maintenance-of-Way Association
AREMA Manual for Railway Engineering
1-6-21
Roadway and Ballast
6.7.4 SPECIFICATIONS FOR ROADBED GEOMETRY (1994)
6.7.4.1 Elevating Roadbed
a.
Elevating the roadbed above-grade reduces the accumulation of snow on the track, but does not eliminate
snow problems at thermal scanners or other sensitive locations. As a general rule, snow fences are required
to protect locations where track is at or above the surrounding terrain.
b.
Minimum embankment height (He, feet) above grade is given by:
H = 0.4S + 2
where:
He = measurement from top of ballast
S = mean annual snowfall, in feet (Figure 1-6-7).
6.7.4.2 Cut Sections
a.
Widening cuts allows wind to keep the tracks swept clean of snow. Deeper cuts should also be designed to
accumulate snow to reduce the quantity of blowing snow crossing the tracks. In cut sections, the roadbed
(bottom of ballast) should be at least 2 feet higher than the bottom of ditch.
b.
As shown in Figure 1-6-8, minimum horizontal distance, Wtop, from shoulder of roadbed to top of cut is:
Wtop = 95 + 5.8H (sin )
where:
H = depth of cut measured from roadbed shoulder elevation
 = the wind angle (Figure 1-6-8)
c.
Backslopes should be 5:1 or steeper. These guidelines apply to through-cuts and to both windward and
leeward sidehill cuts. Although this geometry will prevent drift encroachment on the track, snow fences may
still be required to protect sensitive locations such as switches, thermal scanners, and dragging-equipment
detectors.
Figure 1-6-7. Guidelines for Minimum Height of Roadbed above Grade
6.7.5 SPECIFICATIONS FOR CLEARING AND MOWING VEGETATION (1994)
Mowing and brushing operations as normally carried out for fire prevention and other purposes can also reduce
snow deposition on the track. Particular attention should be paid to removing or cutting back brush and trees
© 2010, American Railway Engineering and Maintenance-of-Way Association
1-6-22
AREMA Manual for Railway Engineering
Fences
Figure 1-6-8. Recommended Cut Section to Prevent Snowdrift Encroachment
within the right-of-way that would otherwise cause drifts to form at critical locations. An option to removing trees
is to prune the lower branches to a height of 7 feet.
6.7.6 SPECIFICATIONS FOR PLACEMENT OF BUNGALOWS AND OTHER STRUCTURES
(1994)
Buildings and other structures on the upwind side of the track can cause drifts that interfere with the operation of
switches, thermal scanners, and other equipment. Where prevailing wind directions are well-defined, these
problems can be avoided by siting these structures on the downwind side of the track. Where buildings must be
placed on the upwind side, they should be located so that the drifts formed around the ends of the building do not
encroach on a sensitive area. The drift wings that form around the ends of a rectangular building having width W
across the wind, extend laterally to 1.5W on both sides of the building centerline.
1
6.7.7 TEMPORARY CONTROL MEASURES (1994)
A common emergency practice in severe winters is to create snow ridges or berms outside of the right-of-way using
graders or dozers. Unfortunately, such barriers do not have much storage capacity. A single row of 4-foot snow
fence would catch as much snow as fourteen, 2-foot-tall snow ridges spaced 10 feet apart. Snow fences are therefore
more effective and less expensive than snow berms.
3
4
© 2010, American Railway Engine
Download