Project Quotation
January 6, 2023
Rovisys
Ryan Murphy
COMPANY TO:
ATTENTION:
PROJECT NAME:
PROJECT LOCATION:
Quote# 22SB263
Equinix CL1 – SA/RA Damper Connection
Calgary
Thank you for the opportunity to present our quotation for the Electrical portion of the above project. We have based
our price on the scope of work outlined in the information received in the site visit.
Our total price to complete the work as listed is….
…$ 3,826.00
•
•
Make final connections for damper wiring.
We have not included for new cabling.
Please Note the Following:
1)
2)
3)
4)
5)
6)
Applicable GST is extra.
Cost in USD
Bonding is not required nor included in the costs
We have allowed for our own trade clean-up and removal of salvageable or recyclable materials. All other garbage removal associated with project will be placed into
bins supplied by general contractor. Bin charges etc., is extra if requested.
Price valid for acceptance for sixty days, payable net thirty days from date of invoice in CND funds.
We have included for one (1) year warranty. Labour only.
We trust the above meets with your approval and ask that if you have any questions, would like more information about the content of this estimate, or would like to proceed, please contact the
undersigned at our Calgary office.
Yours Very Truly,
Steve Barker, PEC
Project Manager
sbarker@westernelectrical.com
Direct - 403-984-1006
Cell
- 403-371-1337
Page 1 of 1