Uploaded by info

Work Completion Report @Govindpur .(Rashleela Enterprises)

advertisement
Work completion Report
To,
M/S RASHLEELA ENTERPRISES PVT. LTD.
Sir,
Sub: Submission of work completion report.
Ref: Your P.O no: 80 DT: 12 Dec 2022.
Dtd
With reference to the above, the work of Four Earthing Station installation
and One Lighting Arrestor system is completed at Govindpur Plant and I would
like to submit the following information for your kind needful.
A. Earthing
1
2
3
Earth resistance
Size of the Earth flat
( 3 x 25 sq.mm galvanic iron flat)
Four separate Earthing points(50 MM , 3 Mtr)
1.
2.
3.
4.
Machine Feeder Contral panel. Pit No 1
Plant Machine (Body Earth). Pit No 2
Plant Machine (Body Earth). Pit No 3
Lightening Arrester . Pit no 4
B. Lightning arrestor.
4 Copper Bonded Spike rod LA (2 Mtr)
2 Ohms
76 Mtr
N-E readings
0.18 V
0.11 V
0.24 V
0.17 V
Installed at Plant
We certify that the above said system is installed and the equipment used in the system comply
the Technical and Safety Standards as specified in the regulations notified by the OMC , Odisha .
Signature of the Contractor
Elefix Services Private Limited
License No -3629(MV)
Address –Plot No 3D/229 , Sec-9
CDA , Cuttack , Pin -753014
Date: 22/12/2022