Uploaded by danny hahaha

activity-15 compress

advertisement
SIMBALA, Andi Te’a Mari O.
ID Number: 2204965
Production and Operations Management (1498)
BS Accountancy 2
Activity 15
Given the activities of a project; their optimistic (to), most likely (tm) and pessimistic
(tp) time estimates; and their immediate predecessors shown below:
1. When is the earliest project completion?
2. Which activities are critical (should not be delayed)?
3. Which activities are noncritical (can be delayed)?
4. How long can each of the activities be delayed without delaying the whole project
(maximum slack)?
Activities
A
B
C
D
E
F
G
H
I
J
List of Paths
A–B–I–J
A–C–D–I–J
E–F–J
G–H–J
Immediate
Predecessors
A
A
C
E
G
B, D
F, H, I
to
1
4
2
4
1
3
7
6
1
13
Activity Times, months
tm
tp
4
13
7
16
2
2
6
14
3
5
5
13
10
13
7
14
1
1
16
25
5 + 8 + 1 + 17
5 + 2 + 7 + 1 + 17
3 + 6 + 17
10 + 8 + 17
te
5
8
2
7
3
6
10
8
1
17
Path Lengths
31
32
26
35
1. When is the earliest project completion?
The earliest project completion time is 35 months after the execution of the project has
been started.
2. Which activities are critical (should not be delayed)?
The critical activities are the activities in the critical path. Therefore, the critical activities
are G, H and J.
3. Which activities are noncritical (can be delayed)?
The noncritical activities are the rest of the activities that are not critical. Therefore, the
noncritical activities are A, B, C, D, E, F, and I.
4. How long can each of the activities be delayed without delaying the whole project (maximum
slack)?
Activities
Maximum Slack, months
A
B
C
D
E
F
G
H
I
J
3
4
3
3
9
9
0
0
4
0
Download