Pop Quiz B Name:__________________________________________________ Activity A B C D E F G H 1. 2. 3. 4. 5. Immediate Predecessors None None A B B C, D D, E F,G Time (weeks) 5 3 3 3 5 4 4 4 Draw the network diagram and show all early and late, start and finish times. What is (are) the critical path(s)? What is the expected completion time of this project? Which activity (activities) has (have) slack and how much? If the duration of activity “F” was reduced to 1 week, would the project duration change? Pop Quiz B Name:__________________________________________________ Activity A B C D E F G H 1. 2. 3. 4. 5. Immediate Predecessors None none A B B C, D D, E F,G Time (weeks) 5 3 3 3 5 4 4 4 Draw the network diagram and show all early and late, start and finish times. What is (are) the critical path(s)? ACFH, BEGH What is the expected completion time of this project? - 16 Which activity (activities) has (have) slack and how much? D, S =2 If the duration of activity “F” was reduced to 1 week, would the project duration change? NO* 3 8 0 3 8 E (5) B (3) G (4) 3 0 8 12 3 3 6 8 12 8 D (3) 0 12 H (4) 12 5 12 F (4) A (5) 5 5 0 16 5 8 8 8 C (3) 5 8 *Because critical path BEGH would be unaffected 12 16