Padma Bridge Composition
Introduction: The dream of Padma Bridge has turned into reality with its construction
inauguration in 12 December, 2015. The Padma Bridge is a multipurpose road-rail bridge across
the Padma River to be constructed in Bangladesh. When completed it will be the largest bridge
in Bangladesh and the first fixed river crossing for road traffic. It will connect Louhajong,
Munshiganj to Shariatpur and Madaripur, linking the south west of the country, to northern and
eastern regions. The bridge will contribute to a great extent to our communication, economy and
industrialization.
Padma Bridge Construction Project: The Padma Bridge project has been undertaken with the
main aim of improving the social, economic and industrial development of the south-west region
of Bangladesh.
The project also aims to provide the people in the south-west region with improved access to
markets and services. throughout the rest of the country while accelerating growth in Bangladesh
as a whole.
The Padma river divides the south-west zone from the northern and eastern regions of
Bangladesh. Construction of the river crossing will reduce the distance from the south west region
to Dhaka, the country's capital by more than 100 km and will also bring savings in passenger and
commodity movement and costs.
Design and Structure : The bridge design contract was awarded to a team led by Maunsell
AECOM, the New Zealand business of AECOM. The design team also includes experts from
North west Hydraulic Consultants, SMEC International, ACE Consultants, Aas Jakobsen and HR
Wallingford.
The bridge will be approximately 6.15 km long and 18.10 m wide. It will be a double deck
composite steel truss structure and will use 41 pieces. The main spans will be 150m long. The
upper deck will contain a four lane highway, while the lower deck will house a rail line, gas
transmission pipeline, optic fibre cable and power transmission lines.
Padma Multipurpose Bridge At a Glance :
Carries
Crosses
Locale
Maintained by
Designer
Contractor
Design
Meterial
Total length
Width
Construction begin
Construction end
Open
Motor Vehicles, Railway
Padma River
Louhajong, Munshiganj to Shariatpur and Locale
Madaripuf Bangladesh
Bangladesh Bridge Authority
Maunsell AECOM
China Major Bridge Engineering Corporation
Truss bridge
Steel
6,150 m (20,180 ft)
18.10 m (59.38 ft)
26 November 2014
23 June 2022
25 June 2022
Financing: The donor agencies including World Bank, Asian allegation of corruption
conspiracy (p) against former Communication Minister Syed Abul Hossain. However, the
government dismissed (f) the World Bank's allegation Development Bank and the JICA
promised a loan of $ 1.9 billion for the project. But the loan was cancelled by the donors on
the and decided to construct the bridge through its own fund.
The government has made an allocation of Tk 8100 crore for the Padma Bridge project in the,
Annual Development Programme (ADP) of the next fiscal year (2014-15). And thus, the
government will fund for the project for its total cost figuring BDT 301933.88. millions or
USD 3.868 billion (including VAT and IT).
Expected Benefits from the Bridge: It is expected that the Padma Multipurpose Bridge will
provide the people of our country with some obvious benefits. The expected (16) benefits that
the bridge will bring for us are given below.
The bridge will provide direct connectivity (P) between the central and southest part of the
country through a fixed link on the Padma river at Mawa-Janjira point. So it will lessen (PIP)
the pressure on ferry ghat and undoubtedly save time and money as well. The communication
will be smooth and quick for South Bangla-Dhaka-South Bangla. The distance between
Dhaka and Kolkata will be shorter than before. So communication, trade and commerce
between two areas will be faster, quicker, smoother and more extended.
As the bridge will have railway line apart from high way connection, all kinds of goods, things
and materials will be brought very easily and quickly from south region to Dhaka. So the
people of southern parts of Bangladesh will have a good link to boost up their economy and
change their life style.
The bridge has provision of rail, gas, electric line and fibre optic cable for future expansion.
So, the south-west part of the country will get the chance to be enlight with modern
technology, equipment and privileges.
The area of influence of the direct benefit of the project is about 44,000 km² or 29% of the
total area of Bangladesh.
Therefore, the project is viewed as very important infrastructure towards improving the
transportation network and regional economic development of the country.
Construction Completed so far: The construction of the bridge is going on in full swing. The
cost of the project has increased and deadline for completing it by June 2020 but Coronavirus
situation has hampered the work speed. So now it is uncertain to say that in which day it will
be completed. The completion of construction of the mega project includes the many
completion works of pier, steel, pile, bottom section driving, top section driving, base
grouting, truss fabrication, truss span and so on. Meanwhile more than one kilometres of the
Padma bridge has been visible. Upto July 2021 92% of total work of the Padma bridge has
been complete and the rest of the work will be completed during the time framed by the
government to fulfill the people's dream of the Padma bridge.
Conclusion: For the overall development of Bangladesh, the mighty Padma bridge will play
a vital role. So the Bangladesh Bridge Authority along with China Major Bridge Engineering
Corporation is working day and night to complete its construction. The day is not far away
from now when the construction will be complete and
Bangladesh will start getting benefits of the bridge. Earlier it was thought impossible to build
a mighty bridge like this with own fund but it is on the verse of completion. With this we can
prove that we can build a mighty bridge with our own fund without any loan or any help
from any monetary organization. The completion of construction will fulfill the long cherished
dream of Sheikh Mujibur Rahman especially dream of the people of Bangladesh.