Appendix A: ON JOB TRAINER REPORT Department of Technologies Sarhad University of Science and IT, Peshawar (To be completed by On Job Trainer) FINAL YEAR INDUSTRIAL TRAINING EVALUATION FORM AND RUBRICS _ Name of the Trainee: ______________________________________________ Father Name: ____________________________________________________ Registration #: ____________________________________________________ SNO. 1. Criteria Poor (1) Fair (2) Good (3) Excellent (4) Quality of Work Work was not done when assigned and very poor response. Work was done in a careless manner and was of erratic quality; work assignments were usually late and required review; made numerous errors. With a few minor exceptions, adequately performed most work requirements; most work assignments submitted in a timely manner; made occasional errors. Thoroughly and accurately performed all work requirements; submitted all work assignments on time; made few if any error. Unbale to learn and response to learning is very poor. Unable to ask any question or additional information about appropriate sources. Asked few if any questions and rarely sought out additional information from appropriate sources; was unable or slow to understand new concepts, ideas, and work assignments; was unable or unwilling to recognize mistakes and was not receptive to making needed changes and improvements In most cases, asked relevant questions and sought out additional information from appropriate sources; exhibited acceptable understanding of new concepts, ideas, and work assignments; was usually willing to take responsibility for mistakes and to make needed changes and improvements Consistently asked relevant questions and sought out additional information from appropriate sources; very quickly understood new concepts, ideas, and work assignments; was always willing to take responsibility for mistakes and to make needed changes and improvements. Not initiative and creative at all. Had little observable drive and required close supervision; showed little if any interest in meeting standards; did not seek out additional work and frequently procrastinated in completing assignments; suggested no new ideas or options Worked without extensive supervision; in some cases, found problems to solve and sometimes asked for additional work assignments; normally set his/her own goals and, in a few cases, tried to exceed requirements; offered some creative ideas Was a self-starter; consistently sought new challenges and asked for additional work assignments; regularly approached and solved problems independently; frequently proposed innovative and creative ideas, solutions, and/or options. PLO-11 2. Ability to Learn PLO-1 3 Initiative and Creativity PLO-12 Marks 4 Character Traits PLO-8 Regularly exhibited a negative attitude; was dishonest and/or showed a lack of integrity on several occasions. Was unable to recognize and/or was insensitive to ethical and diversity issues; displayed significant lapses in ethical and professional behavior Except in a few minor instances, demonstrated a positive attitude; regularly exhibited honesty and integrity in the workplace; was usually aware of and sensitive to ethical and diversity issues on the job; normally behaved in an ethical and professional Demonstrated an exceptionally positive attitude; consistently exhibited honesty and integrity in the workplace; was keenly aware of and deeply sensitive to ethical and diversity issues on the job; always behaved in an ethical and professional manner manner 5 Dependability PLO-11 6 Attendance and Punctuality Was generally unreliable in completing work assignments; did not follow instructions and procedures promptly or accurately; was careless, and work needed constant follow-up; required close supervision Was occasionally undependable in completing work assignments. Was generally reliable in completing tasks; normally followed instructions and procedures; was usually attentive to detail, but work had to be reviewed occasionally; functioned with only moderate supervision Was consistently reliable in completing work assignments; always followed instructions and procedures well; was careful and extremely attentive to detail; required little or minimum supervision Was absent excessively Was almost always late for work with less attendance. Was never absent and almost always on time; or usually reported to work as scheduled, but was always on time; or usually reported to work as scheduled and was almost always on-time Always reported to work as scheduled with no absences and was always on-time Was unwilling or unable to understand and support the organization’s mission, vision, and goals. Exhibited difficulty in adapting to organizational norms, expectations, and culture; frequently seemed to disregard appropriate authority and decision-making channels Adequately understood and supported the organization’s mission, vision, and goals; satisfactorily adapted to organizational norms, expectations, and culture; generally functioned within appropriate authority and decision-making channels Completely understood and fully supported the organization’s mission, vision, and goals; readily and successfully adapted to organizational norms, expectations, and culture; consistently functioned within appropriate authority and decision-making channels PLO-8 7 Organizational Fit PLO-6 …………………………On Job Trainer Signature Name: Date: _________ Department of Technologies Final Year Supervised Industrial TrainingOn-Job Trainer Evaluation Form Organization Name: ___________________________________________________________________ _ Sr.no Student Name Reg.No. PLO-11 Quality of Work PLO-1 Ability to Learn PLO-12 Initiative and Creativit y PLO-8 Characte r Traits (4) (4) (4) (4) PLO11 Dependa bility (4) PLO-8 Attenda nce and Punctual ity PLO-6 Organiza tional Fit Total (4) (4) (28) 1 2 3 4 _________________ _____________________________ [Type here] Weightag e (20%) SNO. 1. Criteria Analysis and approach PLO-4 2. Novelty and Creativity Poor (1) Fair (2) Good (3) Excellent (4) Unable to plan and set objectives for the realization of the industrial training. Moderately approach to plan and set objectives of the training, show little concern. Adequate analysis of the industrial training. Objectives have been set, but strategies to follow are not clearly stated. Complete analysis of the field training has been done. Objectives have been set. Strategies to follow have been defined. Unbale to think and create novelty. Description of unmet need or problem the project caters to is missing. The novelty of the proposed solution of different field tasks is marginal. Details of unmet needs the project caters to are there. Potential towards the field training have been identified. Milestones have not been achieved. Some of the milestones have been achieved Except in few cases, all milestones are completed according to the timeline defined All milestones are completed according to the timeline defined. Was absent excessively Was almost always late for work with less attendance. Was never absent and almost always on time; or usually reported to work as scheduled, but was always on time; or usually reported to work as scheduled and was almost always on-time Always reported to work as scheduled with no absences and was always on-time Student does not adapt to the organization and gives an impression of apathy or is often involved in disputes or arguments. Student shows no insight in functioning of the organization. Student repeatedly has difficulty to get things done within the team (e.g. receiving information, organizing materials or facilities, etc). Student does not adapt and remains passive or negative Student is able to indicate the responsibilities of the different units within the organization. Student is able to get things (e.g., receiving information, organizing material facilities, etc.) done within the team independently. Student is able to adapt to the new work environment in a productive and interactive way. Student knows how changes are realized in the organization. Student is able to independently get things done that affect the whole team. Student adapts well to the work environment, while reflecting on contributing with their personal view. Knowledge and skills remain insufficient (in relation to the prerequisites) and the student does not succeed to take appropriate action to remedy this. Students’ progress in knowledge and skills is limited and requires extensive guidance by the supervisor. The student adopts knowledge and skills independently, and asks for assistance from the supervisor if needed. Students explores solutions independently and seeks appropriate knowledge and skills required. PLO-12 3 Timeline and Implementation Progress PLO-11 4 Attendance and Punctuality PLO-8 5 Insight in the organization and adaptation capacity PLO-6 6 Development of knowledge and skills PLO-3 [Type here] Marks 7 Transfer of (prior) acquired knowledge to the professional context of the internship Student lacks relevant knowledge expected to such an extent that student is unable to perform the internship tasks. PLO-2 Student partly lacks relevant knowledge expected, or is sometimes unable to translate knowledge to the internship tasks, or does not increase knowledge where necessary. Signature of On-Job Trainee Advisor Student shows relevant knowledge on an academic level Student translates this knowledge to the internship tasks. Student increases knowledge where necessary Student shows relevant knowledge on an academic Student translates this knowledge to the internship tasks. Student increases knowledge where necessary and student increases the knowledge of the team/organization. Signature of ILO/Trainee Advisor APPROVAL ____________________________ Signature of Head of Department Appendix B: TRAINING ADVISOR REPORT THROUGH VISIT OR SURVEY Department of Technologies Sarhad University of Science and IT, Peshawar (To be completed by Trainer Advisor/ILO) FINAL YEAR SUPERVISED INDUSTRIAL TRAINING EVALUATION FORM AND RUBRICS _ of the Trainee: ______________________________________________ Father Name: ____________________________________________________ Registration #: ____________________________________________________ [Type here] Name …………………………On Trainee Advisor Signature Name: ________________________ Date: ________________________ Department of Technologies Final Year Supervised Industrial TrainingTrainee Advisor/ILO Evaluation Form [Type here] Organization Name: ___________________________________________________________________ _ Sr.no Student Name Reg.No. PLO-4 Analysis and approac h PLO-12 Novelty and Creativi ty PLO-11 Timeline and Impleme ntation Progress (4) (4) PLO-8 Attenda nce and Punctual ity PLO-6 Insight in the organiza tion and adaptati on capacity PLO-3 Develop ment of knowled ge and skills PLO-2 Transfer of acquired Total Weightag e (4) (4) (4) (4) (4) (10%) (28) 1 2 3 4 _________________ Name and Signature of Trainee Advisor/ILO [Type here] APPROVAL SN O. Criteria Poor (1) Fair (2) Good (3) Excellent (4) 1. Report Organization PLO-10 Report is disorganized and layout is somewhat weak. Report is disorganized and layout is somewhat weak. Most sections/subsections/steps are ordered well. No major problems with layout. All sections/subsections/steps are clearly organized in a logical order. Page layout is effective. 2 Introduction PLO-7 No introduction/ too brief or irrelevant information is present & is not able to identify the impact of the present work, and the role of technologists /engineering technology solution in order to solve problems. The introduction section is brief and insufficient background information, problem statement, objective and expected results are shown which hardly identify the impact of the present work, and the role of technologists and solution in order to solve problems Sufficient background information, problem statement, & project objectives are shown to provide a reasonable analysis of the impact of the present work, the role of engineering technologists on society, towards solving defined problems Excellent introduction and interesting background information, problem statement & project objectives are present which clearly shows the ability to analyze the impact of the present work, the role of technologists on society, towards solving defined problems 3. Organization Profile Too limited literature review on organization profile. Moderate literature review and incomplete references. Good literature review about organization but incomplete references Excellent literature review and proper references Objectives of the training, Scope of responsibilities is not suitable, not described properly. Objectives of the training, Scope of responsibilities is discussed but not is a convincing manner & much is left to the readers’ imagination Objectives of the training, Scope of responsibilities is suitable, described properly and details is included Objectives of the training, Scope of responsibilities is suitable, described properly and is included with explanation of its adoption and supporting figures. Results & discussion are not provided Results stated briefly without discussion. Result is explained and moderate discussion is provided on the work performed. Result is explained and thorough discussion is provided with respect to assigned supervisory tasks. PLO-6 4. The Industrial Training Program (Objectives and Scope of responsibilities ) PLO-6 5. Supervisory Work Results & discussion PLO-6 [Type here] Marks 6. Conclusion PLO-4 7. Visuals PLO-10 Conclusion does not present the essential training and results. No recommendations for follow-up work given. Essential training results are not clearly stated. Recommendation for future work is incomplete. Most important results and contribution are presented. Strengths and limitations of the training are discussed. A good set of recommendations for future work is provided. Conclusions provide a succinct summary of all essential results. The discussion of strengths and limitations is insightful and objective. A clear and complete set of recommendations for follow-up work is provided The Graphs/tables/figures Most of the Graphs/tables/figures/pi Some of the Graphs/tables/figures/pictu All the Graphs/tables/figures/pict ____________________________ Signature of Head of Department [Type here] Appendix C: FY-SUPERVISORY TRAINING REPORT Department of Technologies Sarhad University of Science and IT, Peshawar (To be completed by the Examiner) FINAL YEAR INDUSTRIAL TRAINING REPORT EVALUATION FORM AND RUBRICS _ Name of the Trainee: ______________________________________________ Father Name: ____________________________________________________ #: ____________________________________________________ Registration /pictures are missing ctures are inadequate & not properly labelled res are adequate and labelled ures are adequate, well labeled and presented 8. Technical Writing PLO-10 Poor technical writing. Minimal use of technical language. Appropriate use of technical language Commendable use of technical language. 9. Plagiarism PLO-8 Report is 25% original Report is 50 % original Report is 75% original Report is 100% original …………………………Report Examiner Signature Name: ________________________ Date: ________________________ [Type here] [Type here] Department of Technologies Final Year Supervisory Industrial Training Report Marks Organization Name: ___________________________________________________________________ _ Sr .n o Student Name Re g. No . PLO-10 Report Organizati on PLO-7 Introduc tion PLO-6 Organizati on Profile PLO-6 The Industrial Training Program Objective s and Scope of responsibi lities PLO-6 Supervi sory Work Results & discussi on PLO-4 Conclus ion PLO10 visuals (4) (4) PLO-10 Technic al writing PLO-8 Plagiaris m Total Weigh tage (4) (4) (4) (4) (4) (4) (4) (36) 1 2 3 4 _______________________ Signature of Examiner [Type here] (50%) APPROVAL ____________________________ SN O. Criteria 1. Training Completion & Accuracy Poor (1) Fair (2) Good (3) The system failed to produce the right accurate results. The system execution led to inaccurate or incomplete results. It was not correctly functional or not all the features were implemented. The system was correctly functional and all of the features were implemented. The system was correctly functional and all of the features were implemented. It was demonstrated how the realworld problem was solved. Does not make use of analytical tools and/or engineering technology techniques & knowledge relevant to the project. Does not demonstrate requisite command of the material covered in the curriculum. Unable to finish the proposed project. Information is arranged in confused and unstructured way. Student lacks of confidence. Poor use of English. Does not attempt to look at audience at all. Read notes or looks at computer screen only. Presentation is too short or too long for the allocated time. Student cannot determine the impact of his/her work in terms of society, environment and sustainability Conclusions are not logical or are completely unrelated to the objectives, limited evaluation of significance and quality of results, recommendations are missing or irrelevant Employ some analytical tools and/or engineering technology techniques & knowledge acquired. Make progress towards addressing the technical challenges of the project. Complete most of the major tasks in the proposed project. Employ appropriate analytical tools and/or engineering technology techniques & knowledge acquired in his course of study to the project at hand. Clearly demonstrate mastery of many areas of the curriculum and is able to successfully complete the proposed project Slides cover accurate description of most of important outcomes. Use of charts, graphs, figures etc. Fair use of English. Hold attention by consistent use of direct eye contact. Presentation runs with desired pace and finishes within allocated time Employ appropriate analytical tools and/or engineering technology techniques & knowledge. Clearly demonstrates mastery of several areas of the curriculum and is able to propose innovative solutions to the technical challenges posed by the project. Slides cover complete, accurate description of important outcomes. Effective use of charts, graphs, figures etc. Use of fluent English and confident. Hold attention by direct eye contact and nature hand gestures. Excellent timing and smooth transition among different parts Student can clearly explain the impact of his/her work in terms of society, environment and sustainability Conclusions are logical and related to the objectives, clearly evaluate significance and quality of results, recommendations for future work are clearly stated and justified PLO-11 2 Lifelong Learning (concepts of system specification and implementation are included here) PLO-12 3 Delivery: Oral delivery, contact with audience, slides, timing PLO-10 4 Work Impact PLO-7 5 Conclusions and Recommendations PLO-4 [Type here] Slide’s cover some of the outcomes. Limited use of charts, graphs, figures etc. Use of English with noticeable errors. A few eye contacts only. Presentation pace is not well planned but finished within allocated time. Student is marginally aware of the impact of his/her work in terms of society, environment and sustainability Some of the conclusions are logical but are not necessarily related to the originally stated objectives, limited evaluation of significance and quality of results, recommendations are attempted but not justified Student is adequately aware of the impact of his/her work in terms of society, environment and sustainability Conclusions are logical, attempt to relate them to objectives, attempt to evaluate significance and quality of results, recommendations are clearly stated and justified Excellent (4) Marks 6 Question/answe rs Student has no or very less knowledge of both problem and solution. Cannot answer questions. Student is uncomfortable with information. Seems novice and can answer basic questions only. Student has competent knowledge and is at ease with information. Can answer questions PLO-5 Student has presented full knowledge of both problem and solution. Answers to questions are strengthened by rationalization and explanation Signature of Head of Department Appendix D: FY-SUPERVISORY TRAINING VIVA VOCE Department of Technologies Sarhad University of Science and IT, Peshawar (To be completed by the Examiner) INDUSTRIAL TRAINING VIVA PRESENTATION EVALUATION FORM AND RUBRICS _ Name of the Trainee: ______________________________________________ Father Name: ____________________________________________________ Registration #: ____________________________________________________ Department of Technologies Final Year Supervised Industrial Training- VIVA/PRESENTATION Evaluation Form [Type here] Organization Name: ___________________________________________________________________ _ Sr.No Student Name Reg .No PLO-11 Training completion & accuracy (4) PLO-12 Lifelong learning (4) PLO-10 Presentat ion & delivery (4) PLO-7 Work impact PLO-4 Conclusions & recommend ations (4) PLO-5 Questions & answers total (4) (4) (24) 1 2 3 4 _______________________ Signature of Examiner APPROVAL ____________________________ Signature of Head of Department [Type here] Weightage Total (20%) Table of Contents ACKNOWLEDGEMENT ....................................................................................................................... Power Sector of Pakistan ...................................................................................................................... KE HIERARCHY SESSION .................................................................................................................... 11-KV Distribution Network ................................................................................................................. Integrated Business Centre .................................................................................................................. SMART GRID OVERVIEW .................................................................................................................. Oracle-NMS& SCADA Devices ............................................................................................................ Oracle MDM& AMI ............................................................................................................................. GIS Software: ....................................................................................................................................... Meter Repair ........................................................................................................................................ DISTRIBUTED GENERATION ........................................................................................................... [Type here] UTILITY ANALYTICS .......................................................................................................................... Partial Discharge Test of Current Transformer ................................................................................. [Type here] WAPDA Charter The Pakistan Water and Power Development Authority (WAPDA) was established through an act of parliament in February 1958 for integrated and rapid development and maintenance of water and power resources of the country. This includes controlling soil salinity and water logging to rehabilitate the affected land in order to strengthen the predominantly agricultural economy of the country. As per the charter, amended in March 1959 to transfer the existing electricity departments from the federating units to it, WAPDA has been assigned the duties of investigation, planning and execution of projects and schemes for: • Generation, Transmission and Distribution of Power, • Irrigation, Water Supply and Drainage, • Prevention of Water Logging and Reclamation of Saline Land, • Flood Control and • Inland Navigation. Under the later on developments, vis-à-vis the “Energy Policy 1994”, setting up of thermal power generation projects was shifted to the private sector. Similarly, as a result of restructuring of the Power Wing, the utility part was corporatised into independent companies. This shifts from convergence to divergence gave birth to 14 entities to operate in different zones. These are National Transmission and Dispatch Company (NTDC), four Thermal Power Generation Companies (GENCOs) and nine Distribution Companies (DISCOs). The present status of these companies is of corporate public limited entities under the residual Power Wing is therefore now responsible for major hydro-electric power projects and schemes in operation. Human Resources The Authority comprises of a Chairman and three Members, each heading Water, Power and Finance Wing. The Members oversee the affairs of their respective wings through General Managers for the streamlined operations in their respective areas. During past 62 years of its operations, WAPDA has developed its human resource as a reservoir of knowledge, competence and expertise through training and experience gained at the accomplished projects and remaining associated with diversified development activities. These include professionals, specialists, scientists, economists, administrators, accountants and skilled workers for planning, building, managing and operating various projects. Water Wing Water Wing Member (Water) controls the water wing through its implementation divisions including North, Central, South and Northern Areas in addition to project specific zones including Mangla, Neelum Jhelum, Mohmand Dam Diamer Basha Dam and Dasu Hydropower Projects. These zones cover, in general, Khyber Pakhtunkhwa, Punjab, Sindh and Balochistan, Gilgit-Baltistan and AJ&K. The activity of water wing involves execution of water storage Dams conveyance canals development of hydropower projects, Salinity Control & Reclamation Projects (SCARPS) and research in water sector. Chief Engineers and Projects [Type here] Directors at various levels are responsible for effective and timely implementation of Water Wing Projects. Financial affairs of this wing are looked after by GM Finance (Water). Apart from project offices, there are other offices including Hydro Resources Management (HRM), Technical Services (TS), Hydro Planning, Coordination & Monitoring (C&M) and Central Design Office (CDO) which provide various technical services to different projects. Hydro Resources Management (HRM) is responsible for the management of water resources throughout the country. This office performs various tasks like monitoring, collection, evaluation and publishing of hydro-meteorological data for planning, development and operation of water resources projects; coordination with federal/provincial flood management and reservoir operation authorities; , forecasting of water availability for distribution of water among provinces; annual, periodic and special inspections of water sector projects; evaluation of proposals submitted by consultants, reviewing PCII & PC-I for various projects and additional assignments assigned from time to time etc. Technical Services (TS) provides technical advisory services on different water resources and hydropower projects. Central Design Office (CDO) is responsible for providing one window design services for projects such as dams, power houses, irrigation and drainage networks, flood protection, roads and buildings, providing technical support to the field formations of WAPDA (Water Wing), GENCO, NTDC, DISCOs etc. during the implementation/construction of the new projects and remedial measures/trouble shooting for already completed projects reviewing of detail designs, tender/construction drawings, technical specifications implied/used by Consultants appointed for study of WAPDA Projects, imparting training to water wing drafting staff required for the departmental promotion and establishing drafting standards, schedule of rates and verification of nonscheduled rates etc. Hydro Planning Organization (HPO) is responsible for planning and feasibility studies of hydropower & water resources projects in the country. HPO at present has taken up hydropower projects at various stages of study having a total capacity of over 20,000 MW. The Office of Coordination & Monitoring Water provides streamlined information of Water Wing to the Government functionaries and Ministries. This office also has the responsibility of Human Resource Management & Administration to all WAPDA Water Wing office. [Type here] Power Wing WAPDA Power Wing is now responsible for operation and maintenance of the Hydel Power Stations under generation license granted by NEPRA in the name of General Manager (Hydel) Operation After-debundling of WAPDA into various companies related to the business of Thermal Generation, Transmission and Distribution,. The electricity produced from these Power Stations is delivered to NTDCL Grid System and invoices are raised to CPPAG according to the Tariff approved by NEPRA. Rehabilitation/ Refurbishment of old Hydel Power Stations is also planned and implemented to enhance the reliability and life of power plants. WAPDA is also responsible to associate and monitor the designs and erection/commissioning of future hydroelectric power stations and other Electrical & Mechanical Equipment. Power Wing is also providing technical and management trainings to its employees for capacity building at WAPDA Administrative & Staff College Islamabad, WAPDA Engineering Academy Faisalabad and Hydel Training Centre Mangla. This facility is also extended to employees of ex-WAPDA entities (NTDCL/DISCOs/GENCOs), AJK Hydro Board, Gilgit Baltistan and Power Stations in private sector. A separate establishment also exists in the Power Wing for Purchase & Disposal of unserviceable or surplus materials/items in all WAPDA formations. All the financial matters of Power Wing are managed by General Manager (Finance) Power under the control of Member Power. Presently, the total installed capacity of 21 No. WAPDA Hydel Power Stations is 8420 MW which is about 23% of the total system capacity of 36,166 MW from all sources. The Net Electrical Output is about 32,000 GWh per annum. Finance Member (Finance) oversees the financing functions of WAPDA and is the administrative head of WAPDA Audit, Accounts, Finance and Costing Cadres. General Manager (HRD) is vested with the responsibility for overall administration and services. Secretary WAPDA in addition to looking after day-to-day affairs of the Secretariat, prepares minutes of the Authority's meetings, maintains records of its decisions and issues its directives and coordinates among the three Wings besides monitoring and implementation of Authority's decisions. Authority Fund The Authority Fund consists of the following: • Loans and grants obtained from the federal and provincial governments • Sale proceeds of WAPDA Bonds • Loans obtained by the Authority with general sanctions of the government [Type here] • Foreign aids and loans obtained from the IBRD, ADB and other International loan giving agencies on such terms and conditions as may be approved by the Government • All other sums received by the Authority Water Wing Water Wing of WAPDA is responsible for planning, designing and execution of Water Resources Development Projects in the sector of irrigation, drainage and hydropower. Inter-provincial major surface water projects including large dams are also operated and maintained by Water Wing, WAPDA. Indus Basin Projects (5 Barrages, 8 inter-river Link Canals (1965 – 70), Mangla (1967) and Tarbela Dams (1976) have been completed by WAPDA Water Wing, and are contributing towards national economy. Water Wing is also carrying out IBP consequential works of Mangla Watershed Management Project, Chashma Barrage and C.J. Link Canal. Eighteen (18) million acres of land have been reclaimed from waterlogging & salinity in four provinces. More than 15,000 tube wells were installed and 12,000 km of surface drains and 13,000 km of pipe drains have been constructed in the waterlogged areas. These projects have enhanced cropping intensity from 70 % to more than 110 % in about 16 million acres of land. All these projects had already been handed over to respective provinces over the last decade. Chashma Hydropower Project, (184 MW), Ghazi Barotha Hydropower Project (1450 MW) have been operating since 2001 and 2003. National Drainage Program in four provinces has been completed since June 2007. Sabakzai Dam Project (0.015 MAF, 6875 acres), Mirani Dam (0.152 MAF, 33,200 acres), Mangla Dam Raising Project (additional 2.88 MAF storage & additional 644 Million Units), Satpara Dam (17.3 MW, 0.053 MAF, command area 15,536 acres), Gomal Zam Dam (17.4 MW, 0.892 MAF storage, command area 191,139 acres), Darawat Dam (0.089 MAF, 25,000 acres), Greater Thal Canal Phase-I (355,000 acres), Rainee Canal (113,690 acres) have been completed during 2007 – 2014. Duber Khwar Hydropower Project (130 MW), Khan Khwar HPP (72 MW), Allai Khwar HPP (121 MW), Satpara Dam (17.3 MW) and Jinnah HPP (96 MW) have been put in commercial operation during 2008 2014. The Water Sector Projects which are currently under construction include: Nai Gaj Dam (0.16 MAF, 28,800 acres), Kachhi Canal (Phase-I) in Balochistan (102,000 acres), Drainage Schemes in Sindh & Balochistan RBOD-I (517,310 acres) & RBOD-III (679,000 acre), Lining of Muzaffargarh & TP Link Canals (300,000 acres). The infrastructure Construction Work of Diamer Basha Dam (4500 MW) which includes employee's colony, staff offices, school etc. have been awarded and main dam work is planned to be awarded soon subject of arrangement of funds by GoP. [Type here] The Hydropower Projects which are currently under construction include: Golen Gol Hydropower Project (106 MW) Neelum Jhelum (969 MW) Hydropower Projects, Tarbela 4th extension (1410 MW) & Keyal Khwar HPP (128 MW), whereas Contracting for Stage-I of Dasu HPP (2160 MW) is in progress. WAPDA has lined up various projects for construction in the coming years, these projects include: Dasu Stage-II (2160 MW), Kurram Tangi Dam (83.4 MW, 0.9 MAF, 84,380 acres), Mohmand Dam (800 MW, 0.49 MAF, command area 16,737 acres), Bunji HPP (7100 MW), Tarbela 5th Extension HPP (1320 MW), Phandar HPP (80 MW), Lower Palas Valley HPP (665 MW), Lower Spat Gah HPP (496 MW), Thakot HPP (4000 MW), Basho HPP (40 MW), Harpo HPP (34.5MW), Patan HPP (2300 MW), Basho (40 MW), Shyok Dam (690 MW, 5.4 MAF), Chiniot Dam (69 MW, 1 MAF), Tungas HPP (2200 MW), Yulbo (2800 MW),Middle Palas Valley (398 MW), Upper Palas Valley (157 MW), Middle Spat Gah (501 MW), Upper Spat Gah (277 MW), Akhori Dam (600 MW, 6 MAF) D.G Khan Canal Lining (300,000 acres), CRBC Lift cum Gravity (284,140 acres). In addition, WAPDA has initiated construction work on 12 Small and Medium Dams, which are located in four provinces of Pakistan. Balochistan: Winder Dam (0.3 MW and 0.036 MAF storage), Naulong Dam (4.4 MW and 0.20 MAF storage), Hingol Dam (1 MW and 1.41 MAF storage), Garuk Dam (0.3 MW and 0.05 MAF storage) and Pelar Dam (0.3 MW and 0.099 MAF storage). Sindh: Nai Gaj Dam (4.2 MW and 0.30 MAF storage) and Darawat Dam (0.45 MW and 0.12 MAF storage). KPK: Kurram Tangi (83.4 MW and 1.2 MAF storage), Tank Zam Dam (25.5 MW and 0.345 MAF storage) and Daraban Zam Dam (0.75 MW and 0.069 MAF storage). Punjab: Ghabir Dam (0.15 MW and 0.066 MAF storage) and Papin Dam (0.3 MW and 0.089 MAF storage).0.345 MAF storage)and Daraban Zam Dam (0.75 MW and 0.069 MAF storage). Punjab: Ghabir Dam (0.15 MW and 0.066 MAF storage) and Papin Dam (0.3 MW and 0.089 MAF storage). [Type here] Power Wing At the inception of WAPDA during the year 1958, there was only 112 MW Hydel installed capacity. After establishing WAPDA, first major Hydropower Project completed by WAPDA was Warsak Hydroelectric Power Station (160 MW) in 1961 which doubled the Installed Capacity of WAPDA. Prior to re-structuring completed in 2007, WAPDA established other generation source in addition to Hydro such as Steam / Gas Turbines, Combined Cycle & Coal. Besides Electricity Generation, WAPDA established very large Network of Transmission & Distribution prior to re-structuring (2007) including 51,425 Km High Voltage (HV) and Extra High Voltage (EHV) Transmission Line, 705 Grid Stations, More than 187,648 km 11 KV High Tension (HT) and Low Tension (LT) Lines and Electrification of more than 136,000 villages. CORE ACTIVITIES / MANDATE OF WAPDA POWER WING After Re-structuring in 2007, Power Wing was split up into 15 companies i.e. NTDCL, 10 DISCOs & 4 GENCOs with separate management. WAPDA's role is now limited to the Operation and Maintenance of the running Hydel Power Stations and future development of Water resources as well as Hydro Electric Power Stations.. The present mandate of WAPDA Power Wing is as under:Operation & Maintenance of Hydel Power Station WAPDA is operating 21 Hydel Power Plants having total installed capacity of 8420 MW contributing & vital role to provide the cheap Hydel Energy to the National Grid Neelum Jhelum (969 MW) &Satpara (17.4 MW) are not included in WAPDA Hydroelectric Generation License and are being individually. Neelum Jhelum Hydropower company is responsible for O&M of Neelum Jehlum & Government of Gilgit Baltistan (GoGB) is responsible for O&M of Satpara Dam. Presently, tasks / works include Correspondence with NEPRA regarding Proposed Modification for New & Upcoming Hydel Projects in existing Generation License of WAPDA Hydroelectric Power Plants, Preparation and Submission of Monthly Invoice to CPPA-G for sale of Energy, Processing of procurement Cases and Finalization of O&M Budget Estimates / Foreign Exchange Budgets for Hydel Power Station. Rehabilitation of Existing Old Hydel Power Stations / Technical Monitoring of E&M Works of New Projects Tasks / works consisting of Preparation of Concept papers / feasibility studies and PC-I, Review of Bidding/Prequalification Documents, Approvals of PC-I from competent forum of Authority / GoP levels, Preparation and Evaluation of Expression Of Interest Documents, Evaluation of Technical & Financial Proposals of Consultants, Coordinate with the Consultants in pre and post Contract Award activities and to monitor the progress of the work on daily, fortnightly and monthly basis regarding to Rehabilitation of Existing Old Hydel Power Stations / Technical Monitoring of E&M Works of New Hydro Projects are being performed. Training activities [Type here] Hydel Generation plays an important role to provide the cheep Hydel Energy to the system. Trained and skilled staff is the back bone to run the system efficiently without any interruption and by increasing the availability and reliability of the system. To achieve the goals following setup of the Training Directorate is functioning. WAPDA Administrative Staff College, Islamabad WAPDA Engineering Academy, Faisalabad WAPDA Examination Directorate Mangla Hydel Training Centre, Mangla WAPDA Administrative Staff College, Islamabad The task of Staff College is to impart training of officers of WAPDA and Administrative skills including Project & Contract Management and Computer. base application programmers WAPDA Engineering Academy, Faisalabad The Academy being unique of its kind in the country is playing vital role in boosting up the technical known-how (electrical, mechanical, civil laboratories / workshops and gas, steam, analogue simulators) of Engineers and supervisory staff representing public and private sector. WAPDA Examination Directorate This Directorate is responsible to conduct Departmental Examination of BPS-16 to BPS-18 and Induction Examination of Officers of WAPDA. Mangla Hydel Training Centre, Mangla. This training centre is primarily responsible for training of subordinate staff and Hydel Engineers in their respective fields. In addition, orientation of new recruited Engineer pertaining to their job, Refresher Courses of WAPDA Engineers mandatory before promotion are also conducted in the Training Centre. Finance Wing Finance Wing of WAPDA headed by Member Finance, is responsible for all budgetary, financial and accounting matters, exclusively the financing and funds management for Wapda Projects. These functions are wing wise performed by GMF (W), GMF (P) and DGF (B&C) respectively. The financial matters of all three Wings are technically under overall control of Member Finance like preparation of PSDP budget proposals for Water and Power projects, financing of these projects both from local and international monitory & capital markets. Member Finance looks after revenue generation and financing needs of all the offices of WAPDA. The functions of Finance Wing may be broadly categorized under following financial activities: Budgeting and Management Information System: [Type here] Formulation of Public Sector Development Program, Preparation of Foreign Economic Assistance Budget, Budget chargeable to current Expenditure of Ministry, Determination of funding requirements, pleading the Budgetary needs of WAPDA and monitoring of different Development Programs. Accounts & Financial Reporting: Arrangements of Funds releases/allocations, Remittance of Funds to Projects, Management & maintenance of Foreign Loans/Grants/Credits, Audit reports, Inspection of Projects Accounts, Annual Accounts, Financial reporting, Proceeds of WAPDA Bonds/SUKUK/TFCs and compilation of Financial statement of Wapda Projects. Internal Audit: The Internal Audit division is to provide the WAPDA Authority and Management with systematic assurance, analysis, appraisals, recommendations, advice and information, with a view to assisting the Authority and Management on the effective discharge of their liabilities and the achievement of WAPDA mission and goals. There is a major role of Finance wing to observe NEPRA rules for the implementation of Wapda Tariff, obtaining Generation Licenses with its modifications. Also monitoring the activities related to Costing and Corporate Planning Cell in Wapda. Funding of Hydroelectric Projects (operational as well as under development) is also being carried out by Finance Wing. [Type here] Power Sector of Pakistan WAPDA was bifurcated in 2007 WAPDA PEPCO Responsible for Water Development Pakistan Electric Power Corporation and Hydro-Power Responsible for the management of all the affairs of the corporatized - (09) distribution Companies, 4 Generation Companies and NTDC All Companies work under independent Board of Directors (Chairman and some directors are from the Private Sector) NTDC (National Transmission and Dispatch Company): 1. Started working in 1998 2. Operates and Maintains twelve (12) - 500kV and twenty-one (21) – 220kV Grid Stations 3. 5077 km of 500kV transmission line and 7350 km of 220kV transmission line in Pakistan NEPRA (National Electric Power Regulatory Authority): 1. Approves tariffs for all Distribution Companies and approves performance codes/standards for the Distribution Companies 2. Some of the performance standards are: a. The distribution company shall supply 95% of its consumers within the range of +/- 5% of the nominal voltage and +/-1% of nominal frequency b. Following voltages shall be used for distribution i. 400/230V ii. 11kV iii. 33kV iv. 66kV [Type here] v. 132kV vi. 220kV 3. The Company shall supply Electric power to its customer of the power quality in accordance with IEEE standards 519-1992 pertaining Harmonic Content DISCOs (Distribution Companies): Pakistan has 11 electric supply Companies, i.e. 1. IESCO (Islamabad Electric Supply Company) 2. PPIB (Private Power Infrastructure Board) 3. AEDB (Alternative Energy Development Board) 4. GEPCO (Gujranwala Electric Power Company) 5. PESCO (Peshawar Electric Supply Company) 6. FESCO (Faisalabad Electric Supply Company) 7. HESCO (Hyderabad Electric Supply Company) 8. LESCO (Lahore Electric Supply Company) 9. QESCO (Quetta Electric Supply Company) 10. K-Electric (Karachi Electric Supply Company) Power System Structure in Pakistan Before 2007, Pakistan had a centralized power system structure, but the centralized power structure had proved not only inefficient, but also difficult to manage. The figure below depicts the Centralized Power System Structure of Pakistan [Type here] Controlling Body / Government Generation Setup Transmission Setup Distribution Setup Due to the inefficiencies and management issues involved in centralized power system structures, many nations around the world had started deregulating and restructuring the power system structures to increase efficiency, curtail losses and to improve management. The de-regulated and re-structured setup of WAPDA is as shown below Ministry of Water and Power NEPRA Residual Assets Autonomous Bodies WAPDA Finance Wing Common Services Authority GENCOs (3) NTDC (1) Hydel Development [Type here] DISCOs (9) Hydel Operations IPPs and SSP Water Wing Un-Bundled and re-structured setup of Pakistan The Un-Bundling and re-structuring of individual companies has made the management and running of these companies easier, compared to the centralized system. The above model can be further modified to include import/export of power from the distributed resources, a concept that is also known as “Distributed Generation” 11KV Distribution Network The electricity at our home has actually been through three major steps, Generation, transmission and distribution. The transmission of the electricity from the generation side to the grid station is done at 132kV to reduce the losses in transmission. Onwards from the Grid station to the substation or ring-main –unit (RMU), the 132kV is step-downed to 11kV. The distribution network is mainly powered by the 11kV till the PMTs due to several reasons. One of the major reasons that the distribution network from the grid station to the PMT is using 11kV because of the reduced losses as well as the factor that electricity theft is not possible on the 11kV and therefore the utility, which in our case is KE, use 11kV. The first feeder with which the main cable is connected is called the Primary Substation. For KE network, Karachi and its suburbs are divided on administrative purposes into 4 Regions, i.e. Region I, Region II, Region III and region IV. The Region II and Region III are further divided into 2 subregions. To handle these in-total 6 regions, 6 have established 6 Operation Control Rooms (OCRs). Each OCR controls multiple Area Operation Centers (AOCs). The OCRs are responsible for the 11kV networks, [Type here] the 0.4V network maintenance and management is under the control of the Network Customer Center (NCC). The 11kV operations are divided as follows: 11kV Operations 11 kV Operations DCDO Sub-Station Maintenance Control Room (SSMCRs) Under-Ground Maintenance Control Room (UGMCRs) OCR Area Operation Centers (AOCs) Mobile Workforce/Crews /Gangs Mobile Workforce/Crews /Gangs Mobile Workforce/Crews /Gangs Corrective Manager Preventive Manager The methodology or the Standard Operating Procedures defined for the rectification of the Main Cable Fault are: 1. Fault Indication: This step requires the knowledge regarding the fact that a fault has occurred through Customer Call, SCADA alarms, or Smart Meter Alarms. 2. Fault Identification: This step is determining of the type of the fault that has occurred, for example, was it a breaker trip, feeder trip, or wire/cable breakage, etc 3. Fault Localization: This step is determining or pin-pointing the exact location of the fault. 4. Back-Feeding: This step is performed to temporarily restore the power of the effected customers through some alternative source, till the time the primary source where the fault has occurred is being repaired or restored. [Type here] 5. Fault Rectification: Fault removal 6. Restoration: Removal of the fault and rolling back any temporary measures or action taken on the affected area, and restoring the grid back to its original state. Customer care Customer care department is considered to be the FACE of WAPDA. Any customer having an enquiry that is complaint, suggestion or request first concerns with the department of customer care. A call on 118* actually binds the channel between the consumer and the utility representative. It is considered to be the toughest department to have worked in as handling such remorse issues requires not just skills of a spokesperson but a mind of peace and fragility of water. Customer Accounts Department of Customer Accounts (CA) deals with the billing infrastructure of the connected consumers. Firstly the meter reading is recorded by a MR that is Meter Reader, his job is to survey his devised area and to look over all the meter readings and calculate the amount of units consumed by subtracting the new recorded reading with the previous recorded reading. He performs this task in G-Sheets or HHU that is Hand Held Units, the meters that are being recorded are called as MRU or Meter Reading Units previously known as sections. And a single survey consisting about multiple MRUs is considered to be a LOT. Now after MR has recorded the reading he brings it back to DEO that is Data Entry Officer, he actually punches those readings into SAP.ISU that is industry specific utility. Screening and different checks will be performed through this reading and a final bill in printed from this software. Now different procedure is forecasted when MR would be unable to get the reading of designated place, which includes average billing that is if MR is unable to fetch the reading KE bills the consumer on basis of average units consumed and balances it out under next month reading. Now the day DEO [Type here] enters all the reading in the software is considered to be as the cycle day or now-a-days termed as portions. Such tedious procedure has to go through for billing a consumer under normal circumstances. SMART GRID OVERVIEW A smart grid is a class of technologies that people are using to bring utility electricity delivery systems into the 21st century, Smart Grid can also be seen as the computerization of the existing HT and LT network as well as merging the Information and Communication Technology into the Grid for Real Time monitoring and controlling of the grid. These systems are made possible by two-way digital communications technologies and computer processing. The purpose of the smart grid technology is to improve the efficiency, reliability, economics, and sustainability of the production and distribution of electricity. Electronic power conditioning and control of the production and distribution of electricity are important aspects of the smart grid SMART GRID BENEFITST EXAS Tech University 10 1. Improving Power Reliability and Quality – Better monitoring using sensor networks and communications – Better and faster balancing of supply and demand 2. Minimizing the Need to Construct Back-up (Peak Load) Power Plants – Better demand side management – The use of advanced metering infrastructures 3. Enhancing the capacity and efficiency of existing electric grid – Better monitoring using sensor networks and communications – Consequently, better control and resource management in real-time 4. Improving Resilience to Disruption and Being Self-Healing [Type here] – Better monitoring using sensor networks and communications – Distributed grid management and control 5. Expanding Deployment of Renewable and Distributed Energy Sources – Better monitoring using sensor networks and communications – Consequently, better control and resource management in real-time – Better renewable energy forecasting models 6. Automating maintenance and operation – Better monitoring using sensor networks and communications – Distributed grid management and control 7. Reducing greenhouse gas emissions – Supporting / encouraging the use of electric vehicles – Renewable power generation with low carbon footprint 8. Reducing oil consumption – Supporting / encouraging the use of electric vehicles – Renewable power generation with low carbon footprint 9. Enabling transition to plug-in electric vehicles – Can also provide new storage opportunities 10. Increasing consumer choice – The use of advanced metering infrastructures – Home automation – Energy smart appliances – Better demand side Management SMART GRID PRIORTITY AREAS 1. Demand Response and Consumer Energy Efficiency 2. Wide‐Area Situational Awareness 3. Energy Storage 4. Electric Transportation 5. Advanced Metering Infrastructure [Type here] 6. Distribution Grid Management 7. Cyber Security 8. Network Communications The WAPDA smart Grid department was established with the main task of introducing Smart Grid technology in Pakistan, to improve network planning & management while reducing aggregate technical & commercial losses. The Smart Grid department has been putting great hard work and effort into implementation of the smart-grid technology across Karachi. Presently, KE is implementing 2 smart grid clusters across Karachi The HT network has SCADA devices installed and the LT network has the smart-meters. All the devices, i.e. smart meters and SCADA, communicate their data to the Head end devices that communicates the data to the respective software. KE is presently using the following softwares for the data and the network management of the Smart Grid, i.e. Oracle Utilities Network Management System (OUNMS), HX8000 for SCADA Devices, Oracle Utilities Meter Data Management System (OUMDM), ESRI Geographical Information System (GIS), Oracle Utilities Business Intelligence software (OUBI), for generation of report generation and business interface, these softwares are one of the most widely used softwares around the world in the utilities, the Head End have their own softwares for communication and management of the data. The Oracle Utilities softwares have been integrated with the SAP software modules as it is the Enterprise Resource Planning system (ERP) that has been implemented in Wapda. The SAP respective module that are integrated with the Oracle systems are SAP IS-U B&I (for billing), SAP IS-U EDM (for Loss Calculation), SAP CRM (for Customer Relation Management) and SAP PM (for Maintenance). [Type here] Oracle-NMS& SCADA Devices Oracle NMS is a network management system acquired by the Wapda for the integration and management of the Wapda HT network for smart grid network management. Oracle NMS provides the user with vast functionalities and operational support that could provide KE with the key cutting edge benefits that would allow the KE with the much needed insight, real time management and fault and error indication of the system. These benefits combined with the different functionalities and operation abilities of the system would greatly enhance the capabilities of Wapda and would allow KE to adopt modern business practices at par with those being adopted around the world. [Type here] Oracle NMS has different features such as web management, feeder load management, outage management system, distribution management system, crew/gang allocation, tracking of the crews/gangs, notification of different alarms and events, SCADA along with Fault Location Isolation Service and Restoration, Fault Location Analysis, etc.. The NMS receives data from SCADA devices installed in the HT network, because presently NMS is not being implemented on the LT network. The SCADA devices would allow real time values and information regarding the current, voltage, VAR, VA and the threshold limits that have been applied in the systems. The software also provides different critical features like storm management, allows simulation (study mode) and “what if” scenarios. The system allows the replication of the real time situations and values in simulation allowing the user to test the pros and cons of different actions, as well as the system would also provide different suggestion and solutions to the user. These features allow the user to carry out the best possible measure for the respective issue. It also allows a satellite view of the HT network spread out via integration with the GIS software allowing the proper fault indication and network overview. This feature allows user to have insight in the connection and location of the different devices, feeders, and substations. NMS allows creating authority for control zones that would allow a hierarchical structure with respect to the Wapda hierarchy. The power flow analysis, Volt/VAR, suggested switching, and conservative voltage reduction are one of the few highly important tools that have been provided in the oracle NMS software. These tools allow a greater level of control of the grid and the network in the hands of the users and tilt the direction of the user towards pre-emptive dealing with conditions that could result in greater faults. Power Flow Extensions enable engineering analysis of the electrical distribution system for use in the operations and control center rather than [Type here] for design or planning purposes. They assess the equipment loading and feeder voltage profiles for selected portions of the electrical network, and provide overload, fault, and voltage violation information for review. Suggested Switching helps to generate switching steps for two fundamental types of scenarios. Switching steps can be generated to restore power to a DE energized device, or to de-energize and isolate a device that is currently energized while minimizing the amount of resulting dropped load. The software produces restoration steps by solving the power flow for each eligible tie point with adjacent feeders, in order to determine the remaining feeder capacity and the overloads after the de-energized section is picked up. Several alternate switching plans may be produced and listed in ranked order. The user can select the desired switching plan and generate it in Web Switching Management. When your objective is to isolate a device, restoration steps are similarly obtained while accounting for the effects of the switching steps required for isolation of the desired devices. Volt/VAR Optimization generates a set of optimal substation transformer tap positions and capacitor bank statuses to minimize power losses and maintain power quality as the system load changes. Volt/VAR Optimization also allows you to specify a particular loading scenario against which to perform the Volt/VAR analysis. Based on the selected load scenario, Volt/VAR optimization uses the real-time load values or appropriately loads values from the historic load profile for all load points in the analysis area. The user-selectable load scenarios are: •Real-time loads •Scaled loads •Peak loads •Specific period loads Feeder Load Management (FLM) is also one of the major tools of NMS that allows you to manage energy delivery in the electric distribution system and [Type here] identify problem areas. Feeder Load Management monitors the vital signs of the distribution system and identifies areas of concern so that the distribution operator is forewarned and can efficiently focus attention where it is most needed. It allows for more rapid correction of existing problems and enables possibilities for problem avoidance, leading to both improved reliability and energy delivery performance. Feeder Load Management is automatically triggered by pertinent changes in the electric distribution system, such as increased demand or switch status changes. Feeder Load Management provides dynamically updated views of closest-in-time alarms, peak loads, and present loads of all the feeders. Feeder Load Management directs users to those feeders where capacity margins and/or device limits are at risk or violated. The purpose of the Fault Location Isolation Service and Restoration (FLISR) tool is to respond to protection trips of SCADA monitored and controlled switches (such as the feeder circuit breakers CB and downstream re-closers). FLISR automatically identifies the faulted section using the protection trip and Fault Indication flags and then automatically schedules the isolation and restoration actions to restore the non-faulted areas de-energized by isolating the fault. It can also present the isolation and restoration actions for execution by the user. If Oracle NMS Power Flowis implemented, FLISRwill use power flow analysis in the solution analysis. In short NMS is a highly applicable and important system that is required to manage the operation-ability of the smart grid network and to conduct its monitoring in the real time. Though KE would not be able to implement all of its operations all at once, because the existing transmission and distribution setup is quite obsolete and would require massive investment for up gradation, but installation and integration of the smart devices into the existing system would allow real time monitoring of the system but would also extend the life of the system as it would provide the required necessary insight into the system and would allow the option of preventive maintenance rather than being totally blind sighted regarding the grid and the network. What NMS has to offer for KE itself is quite huge, but what KE [Type here] can extract at the moment requires KE to modify its existing operations with respect to the system with is quite advanced and extensive and provides the proper example of centralized command and control. The OUNMS is a type of Advanced Distribution Management and the architecture is shown below. SCADA Devices: SCADA SCADA (supervisory control and data acquisition) is a category of software application program for process control, the gathering of data in real time from remote locations in order to control equipment and conditions. SCADA is used in power generation plants as well as in transmission and distribution departments of different utility companies, oil and gas refining, telecommunications, transportation, and water and waste control. SCADA systems include hardware and software components. The hardware gathers and feeds data into a computer that has SCADA software installed. [Type here] The computer then processes this data and presents it in a timely manner. SCADA also records and logs all events into a file stored on a hard disk or sends them to a printer. SCADA warns when conditions become hazardous by sounding alarms. D-SCADA D-SCADA provides a low-cost modular system option for interaction with automated and intelligent distribution system field devices. It uses a simplified data model that is typically generated through an automated process. The DSCADA may be implemented to communicate directly with the field through a variety of methods to meet specific customer requirements. D-SCADA includes the following 1. Data acquisition: provides the interface to the system field devices and ensures data integrity. 2. Inter-Control Center Communications Protocol (ICCP) interface: provides the ICCP interface that connects D-SCADA to the OMS and MWFM system. It facilitates real-time data transmission and reception. 3. Intelligent electronic device (IED) management tools: enables the user to view and change the status of the data acquisition function’s objects and the system field devices. They also display IED communication errors and allow the user to view and reset communication error counts. 4. Network control executive: handles switching commands from the OMS and manages their execution. 5. Data archiving interface: directs scanned and derived system data to an independent long-term archiving system. 6. Configuration management tool: monitors the status of key components of the D-SCADA network servers, printers, network interfaces, true time devices, database domains, etc. 7. Distribution management system: A comprehensive and intricate DMS is capable of managing fault detection, isolation, and recovery and Volt/VAR control while interfacing with (or integrating functionality [Type here] traditionally found in) distribution SCADA systems, workforce management systems, outage management systems and geographic information systems. 1. DTU: Devices on substation are called Distribution Terminal Unit (DTUs) model used by KE HXDTU3000. 2. RTU: Remote Terminal Units (RTUs) like Fault Current Indicators (FCIs) are being placed on Underground and Overhead lines. 3. DCU: The data from the devices installed on Substation, underground cables and overhead lines is then gathered into a Data Control Unit (DCU), model used by KE is HXDCU40. Communication from all the devices installed in D-SCADA system of KElectric like the readings from FCI to DCU is being conducted at 2.4GHz through Zigbee technology. FCIs R DISPLAY Y SCREEN B DCU Oracle MDM& AMI MDM is the Oracle Utilities Meter Data Management software that is required for the control and management of the Advanced Metering Infrastructure (AMI) meters or in simpler words the smart meters. The purpose of MDM is defined in simpler terms is collection of data and profiles from different data devices, i.e. meters at different ends and as well as head ends, and then providing the respective data to the respective systems for their operations. For example the MDM receives the data from the meters installed and then would provide the load profiles to the NMS for its calculation and operations. [Type here] Wapda deploys Oracle utilities data management system (MDM) for storage and acquisition of vast amount of data received through head-end system from smart meters. The software imports, validate, store and format data before making it available for billing and analysis purpose. This database with its analytical tools is also interfaced with other information systems like customer information system (CIS), billing system, Outage management system (real-time outage information from AMI meters), geographic information system (GIS), and transformer load management. One of the primary functions of MDM is to implement validation; estimation and editing on AMI data to ensure that inspire of disruptions in communication networks or at customer premises, the data sent to the aforementioned systems is complete and accurate. The key features of MDM include its capability to provide smart meter integration with head-end -systems, supports different commodities: electric, gas, water and others. It has 360 degree user interface that provides all data related to a device like average usage profile, outage period, meter reader remarks etc, Facilitate new customer programs by providing multiple bill determinants rules (like peak demand, time of use, critical peak pricing, real time pricing).It has usage & event subscriptions so that the data could be published to downstream systems. MDM has several functional areas 1. Service Provider: A service provider is required for the transmission and receiving of the data from the meter to the system and from the system to the meter. For every system there is a service provider, its function is to either route data from any system to the MDMS (head end systems have service provider to send info from meters to MDMS) or from MDMS to any system. (CIS have service provider to receive bill determinants from MDMS). 2. Device Management: Most devices are meters. Device info includes its manufacturer, model, head end system which holds record of its measurements. [Type here] Every device has measuring components and the combination of unit of measure (UOM like kWh), time of use (TOU: on-peak or off-peak) and Service quantity identifier (SQI: energy consumption or generation) shows what the device measures. Device configuration shows how the measuring components are configured. 3. Validate-Estimate-Edit (VEE): The Initial Measurement Data is recorded and VEE rules are applied on it. The VEE rules validate the meter reading that whether the reading is matches the historical data pattern or in other terms performs the sanity check of the reading, incase the reading fails the sanity check, and the reading is edited with the estimated value keeping in view the past trend of the specific meter readings. Each measuring component is periodically measured. Each MC has its associated VEE group. When initial measurements are initialized, VEE rules are applied based on its VEE group & associated region, device type, customer type, usage pattern. 4. Measurements: The system creates final Measurements once the Initial Measurement Data has successfully passed the VEE rules. If measuring component is re-measured, there may be an existence of multiple readings, but for a specific date & time only one final measurement is allowed. there are derived values as well like the value calculated after distribution loss is calculated or after conversion in different unit of measure 5. Installation Information: A service point exists for every geographic location at which a device can be installed; it includes postal address, geographic identifiers, and other geographic-related attributes that could directly impacting VEE and usage calculation logics. The Installation Information also maintains an event history and the removal date if any so that the system can recalculate the historical usage 6. Usage Subscription: It is an actually a record of an ongoing request to calculate billing determinants for one or more service points. It has a 1:1 correlation with a contract in the CIS (that is a system-of-record). [Type here] All contractual information that impacts how bill determinants are calculated is defined on the usage subscription and it is synced with CIS system that provides the data. CIS is a SAP module used in the customer accounts. 7. Usage Calculation Rules: The system performs usage calculation rules on the billing determinants from the usage subscription for a given time period. The usage calculation rules can be run in the real time and in the in batch process which is a standard integration in the CIS. 8. Usage Transaction: It records the results of the usage calculations, which would be sent out to one or more of the participants in the MD, such as the energy service provider associated with the subscription’s service point of view. The service point measurement can periodically “push usage” to the system, whereas the CIS system can also request usage when it would require calculating the billing determinants. 9. Communication: MDM has inbound and outbound communication is a record of a messages sent or received by a service provider or by an MDM participant to / from the head – end or the edge application. The purpose of inbound and out bound communication is defines below: Inbound Comm.: record of message sent by a service provider, although initial measurements are true inbound communications yet they are not regarded as inbound due to their large volumes. Outbound: record of message sent from MDMs or sent to MDM participants, while usage transaction is true outbound comm. it is no considered outbound due to their large volumes. 10. Events: Devices can send/communicate different type of Events, for example, some of the major events are: a. “Last Gasp”: If a meter detects power loss is imminent, it sends a last-gasp message to notify the utility regarding the power failure or outage condition. b. “Tamper Detection”: This event occurs when the meter detects that a consumer or someone is tampering with the meter. [Type here] The purpose of meter event is to create or register the interest of the service provider or utility regarding any ongoing activity or abnormal condition. 11. Activity: Activity is a record of an event taking place; activity can also be related to any combination of “master – data” objects. 12. Service Requests: These requests are created to orchestrate communication sent to the head end systems, such as, a request to commission a meter, turn a meter off, ping a meter, etc., are all orchestrated via a service request. The service request can be created via different methods, for example; services call from an external system, a user online/ real – time, or a business process. MDM provide benefits to both utilities and consumers, some of which are described below: 1. Supports smart grid and smart programs allowing customers to easily access usage and program information 2. Provides a central data source for all utility departments 3. Optimizes asset utilization through load aggregation 4. Improves on-time and accurate billing with comprehensive integration of meter–to-cash operations 5. Aids detection of energy and water theft. Determines effectiveness of energy/water and conservation programs. Meter [Type here] Head Meter BTS Station Service Provider KE SERVER The Graphical representation of the MDM system is as follows: The system generates service requests to either enable or disable the service at the service System System maintains information about all the meters and the service points at which they are installed (the CIS is the system of records) Meter and Service Points It initiates business processes that commissions, decommissions and monitor the state of the smart meters CIS Service Requests Smart Meter Messages The system is the system of record for all measurements and meter events The system transforms the data measurements in billable data that is used by the subscribing [Type here] Outage Management Market Participant Measurements and Events Billable Usage Mobile Workforce/Crews Oracle Utilities MDM – … Echelon L+G Meters Fusion Middleware & SGG Meter Data Management Device Interfaces Devices VEE VEE Groups Usage Sub. Service Points 360 º Portals Exception Man. Bill Determinants Custom Rules Measurement Svcs. Reporting CSS BI EE OU Application Framework Fusion Middleware Customer Care and Billing Other Systems: Billing, Work Management, etc. 24 24 © 2010 Oracle Corporation – Proprietary and Confidential V2 Conceptual Architecture The Oracle MDM software applies Middleware Software fusion and Smart Grid Gateway to communicate between the Meters, in this case the LANDIS and GRYS meters, and the Oracle Utilities MDM software. The data from the meters after being transferred to the Oracle Utilities MDM is extracted by the Business Intelligence and CSS systems, in this case the Oracle Utilities Business Intelligence (OUBI) software. The above mentioned systems are directly integrated with the OUMDM software, but for those systems such as SAP ERP modules or other Oracle softwares like OUNMS requires middleware for the fusion and transfer of data from one system to another as per the requirement of the system. AMI: Advanced metering infrastructure (AMI) is architecture for automated, twoway communication between a smart utility meter with an IP address and a utility company. The goal of an AMI is to provide utility companies with real-time data about power consumption and allow customers to make [Type here] informed choices about energy usage based on the price at the time of use. AMI is seen as an important part of any smart grid initiative. Wapda is purchasing smart meters by 1. IskraMeaco (Slovenia) via TMA (sales agent) 2. Hexing (Chinese) via KBK (local dilution) 3. Holley (China) via IMS (local assembly) Meters are classified into the following major categories 1. Electrostatic meters 2. Electromechanical meters Meters used by WAPDA are of the following types 1. Single phase Direct Online Meters 2. Three phase Direct Online Meters 3. CT Operated Meters 4. CTPT Meters Advance Metering Infra-structure is essentially another department of Smart Grid. That is responsible for the installation of smart meters, gathering data from them and enhancing company’s profits and protecting revenues by applying advanced metering techniques on the basis of data being gathered from the meters. Previously there were three ways to access a meter. 1. By meter Reader 2. By the information consumer provides. 3. Meter inspector. Concept of smart meters has revolutionized the system. These meters can perform two ways communication which means it sends information containing any sort of alarm, outage (which is called last gasp information; [Type here] the data the meter sends just as its capacitor gets discharge due to outage or shutdown). Etc. Thus advance metering reduces the time and efforts and increases customer satisfaction because the complaints get resolved quickly. Smart meters and smart grid cannot completely eradicate theft but the purpose of installation of these devices is to get an insight of the events on the field. Smart meters send interval base data, the interval is set to be of 15 minutes. The billing period of the meters is set to be of 30 minutes. The hierarchy of installation of meters is as follows Feeder Isolation point Distribution t/f Consumer The data by smart meters then would be integrated directly into the softwares like MDM through which it would be easy to identify the reasons of energy and positions of faults and outages. Communication of smart meters is GPRS and GSM based. It has a modem, and a module in which SIM is connected. KE is using SIMs of Mobilink and Telenor in there meters. There are two possible topologies which can be followed, either to have a SIM installed in every meter which would obviously be expensive, or to have SIM in only one meter and by using parallel communication connect the meters to a universal BUS that is RS-485 this would be a much cheaper option. KE is following the parallel communication topology, which is further elaborated in the following figure. HEAD METER (SIM) RS-485 METER [Type here] METER METER METER METER Meter Head Meter BTS Station Service Provider KE SERVER Alarm and Event Communication from meter to the software GIS Software: Geographical Information System is used to represent Electrical Transmission and Distribution network with satellite imaging. GIS helps to determine • Current location of different electrical component • All underground, overhead, LT and HT network present in a system • How much customers are linked to a feeder or connection • Every component of the network even the poles are named with an ID number which helps to locate the component faster in the system. • Distance between any two components can be determined easily through GIS • GIS helps to understand the conditions of the network that could help in installing new component at a particular location. • GIS even helps in editing as to look for how can a system be designed. • GIS helps in forecasting the accessibilities that CAN/CANNOT be acquired within a location. • GIS could also help in localization and back feeding the network under a particular feeder. • For poles it can also indicate the purpose of its position, for example whether it’s an SHANKLE point or T/OFF pole etc. • GIS serves as the basic parameter for implementation of Smart Grid on the system. [Type here] • It could be very helpful in indicating the location of the fault and forwarding to rectify the matter faster. • GIS also helps to identify the strength of a cable connecting a PMT to feeder, whether it underground or overhead, whether HT or LT. • It helps in identifying how many PMTs or Poles are connected to a particular feeder. • GIS has an accuracy up to -+3m of indicating a network to the original system planted by the engineers. • Generally GIS helps in serving the overview of the system, how it is integrated and how efficiently it can be designed and implemented. Meter Repair There are several different types of meters: 1. CT/PT meters on HT 2. CT operated meter on LT 3. Direct Online 1 - ᵠ meters 4. Direct Online 3 - ᵠ meters There are two categories of meters; 1. Electro-Mechanical Meters: has dials in units of revolutions/kWh 2. Electro-Static Meters: has impulses with units of impulse/kWh The meters are tested on the Faulty Meter Report by the meter reader or the consumer. Several tests are performed on the meter to verify whether the meter is faulty or not. The types of test performed on the meters are: [Type here] 1. Dial Test: Revolution test of the meter Dial. 2. Creeping Test: Forward and backwards movement of the meter dial in the absence of the electric supply. 3. Physical Test: Integrity Check of the Meter 4. Accuracy Test: Test on 1/10 of load, ¼ of load, ½ of load, and full load. The Meters are of different Accuracy Classes, i.e. Class-0.5 (0.5% accuracy), Class-1 (1-% Accuracy), Class-2 (2% Accuracy). DISTRIBUTED GENERATION What is Distributed Generation? Distributed generation (or DG) generally refers to small-scale (typically 1 kW – 50 MW) electric power generators that produce electricity at a site close to customers or that are tied to an electric distribution system. Distributed generators include, but are not limited to synchronous generators, induction generators, reciprocating engines, micro turbines (combustion turbines that run on high-energy fossil fuels such as oil, propane, natural gas, gasoline or diesel), combustion gas turbines, fuel cells, solar photovoltaic, and wind turbines. Applications of Distributed Generating Systems There are many reasons a customer may choose to install a distributed generator. DG can be used to generate a customer’s entire electricity supply; for peak shaving (generating a portion of a customer’s electricity onsite to reduce the amount of electricity purchased during peak price periods); for standby or emergency generation (as a backup to Wires Owner's power supply); as a green power source (using renewable technology); or for increased reliability. In some remote locations, DG can be less costly as it eliminates the need for expensive construction of distribution and/or transmission lines. [Type here] Benefits of Distributed Generating Systems Distributed Generation: a. Has a lower capital cost because of the small size of the DG (although the investment cost per kVA of a DG can be much higher than that of a large power plant). b. May reduce the need for large infrastructure construction or upgrades because the DG can be constructed at the load location. c. If the DG provides power for local use, it may reduce pressure on distribution and transmission lines. d. With some technologies, produces zero or near-zero pollutant emissions over its useful life (not taking into consideration pollutant emissions over the entire product lifecycle i.e. pollution produced during the manufacturing, or after decommissioning of the DG system). e. With some technologies such as solar or wind, it is a form of renewable energy. f. Can increase power reliability as back-up or stand-by power to customers. g. Offers customers a choice in meeting their energy needs. Challenges associated with Distributed Generating Systems a. There are no uniform national interconnection standards addressing safety, power quality and reliability for small distributed generation systems. b. The current process for interconnection is not standardized among provinces. [Type here] c. Interconnection may involve communication with several different organizations d. The environmental regulations and permit process that have been developed for larger distributed generation projects make some DG projects uneconomical. e. Contractual barriers exist such as liability insurance requirements, fees and charges, and extensive paperwork. UTILITY ANALYTICS • Phase balancing: If power factor of all the three phases are same that indicates the phases are balanced as power factor is the cosine of phase difference. • Voltage analysis: If load voltages of all the three phases are same that indicates the voltages are balanced. • Load Balancing: If the line currents of the three phases are not same that means the load unbalancing has occurred and thus some current must be flowing through the neutral otherwise the neutral current must be zero. Ideally, I1<0 +I2<120 +I3<240 =IN=0 Line loss analysis: knowing the conductor material (resistivity), its length to which it is extended and its cross sectional area the total resistance of the conductor can be known. Multiplying this resistance with square of current, line loss can be calculated. Line loss=I2R where R=PL/A Transformer load management: If the customers connected to a particular PMT are continuously facing tripping or explosions of PMT that means that the transformer is running on over load. Thus by [Type here] summing up the maximum demands of the consumers a PMT should be installed of such rating that it does not trip. ∑Customers Max Demand< PMT rating Unit Difference analysis: The difference of the power provided by the PMT to a particular area and the sum of total power consumed by the customers connected to that PMT. If an enormous difference is observed in these two measurements then that means the company is facing loss. ∑KW PMT-∑KW Consumer=Δ Feeder load management: If the feeder of a particular area is tripping frequently that means it is being overloaded. Sum of all PMTs connected to a single feeder must not exceed the feeder’s maximum capacity in order to avoid tripping. ∑Rating of All PMTs < Feeder Maximum Capacity Fault current: If any fault current is detected by FCIs it can be observed on the data table. Any abrupt rise in current means that a fault has occurred. Fault current is normally 6 times the nominal current. X up to fault-1 *100 • Fault location analysis: On the basis existence of fault current on the data sheet, we can know location of the fault that on what patch fault has occurred. And how many consumers are affected of that particular area. • Short circuit KVA: The magnitude of short circuit fault current multiplied by voltage of the line before occurrence of fault can be used to calculate the short circuit KVA of the asset. And thus we can know the capacity of the instrument [Type here] Short Circuit KVA= Post fault current * pre fault voltage • Asset utilization monitoring: Assets can be defined as any device or instrument that is important to the company. It can be a meter, PMT, or any device. Through the data we can see if the PMT is running on overload so it can be changed before exploding etc. • Power factor analysis: Lesser power factor causes burden to the utility company and also to the consumer as consumer always pays for active power consumption lesser power factor indicates that it is using more reactive power. The data indicates the different values of power factors, it is thus easy for the company to impose penalty on the consumer if its power factor is less than 0.85. • Outage minutes validation: The data can provide us with the duration of outage, formula for outage duration can be expressed as, Duration= Power Up (time/min) - Power Down (time/min) Outage dollarization: The amount of revenue lost by the utility due to outage. For example, 4000 customers are effected due to outage of 4 hours with 15 Rs per unit cost and an average of 1.5kWh per house. The revenue lost by the company in that 4 hours will be 3lac 60thousand rupees. Outage Dollarization (Rs) = No. of outage hours*no of consumers under outage*per unit cost*average energy consumed per hour • Customer segmentation: On the basis of the data consumers can be categorized into different segments. For example, the area from which the revenue is not being regained by the company or the utility company is facing loss. The consumers of that area can be segmented into high loss similarly category of medium loss and low loss can be designed. [Type here] • Diversion and back feeding: Knowing load of the PMTs connected to a particular feeder, we can devise a diversion plan or back feeding pattern during outage. Let suppose that if a feeder has capacity of 10,000 KVA and the summation of all the PMTs connected to it are 8000 KVA, which means if there is outage in any other area so the 2000KVA load of that area can be fed through this feeder. Feeder Capacity-∑PMTs rating= Back feeding Capacity • Events and alerts: Alerts and events can be identified by the current flowing through the system, system voltages, power factor and apparent power. When the total KVA rating not equals to the consumed KVA rating of the system there is said to be theft present in the system. Other alerts such as temper alerts in meter can be identified through a notification from the meter. • Load profile analysis: Load profile analysis can be performed by the voltage, active and reactive power consumed by the system by constructing the graph of present values and indicating the Max Demand, Utilization factor etc. concerning the system. • Demand Factor: Consumers do not use all the devices at full load simultaneously. Maximum demand for each consumer is therefore less then total connected load. Demand Factor= Max Demand/ Total connected load Demand factor is usually less than 1. Average Load or Average Demand: From the data average demand can be calculated in a particular time interval. As it is the ratio of energy consumed in a given time period [Type here] Av. Load=Energy Consumed in a given period/Hours in that time period • Diversity Factor: Maximum demands of individual consumers are not likely to occur simultaneously, so there is diversity in occurrence of load. Large diversity factor has the effect of reducing the maximum demand, consequently lesser plant capacity is required, thus capital cost is reduced and the cost of generation is also reduced. Diversity Factor= Sum of individual maximum demand/coincident max demand of whole system • Utilization Factor: capacity Maximum Demand/Rated System Partial Discharge Test of Current Transformer Partial discharge is a localized dielectric breakdown of a small portion of a solid or fluid electrical insulation system under high voltage stress, which does not bridge the space between two conductors. 1. Reasons PD level over 2,500pC (in paper) and over 10,000pC (in oil) may be destructive ionization a. Insulation Degradation (Reversible) i. Conductive mode particles, bridges gap in oil insulations, causes 100pC to 10,000pC ii. Increased moisture content around 3-4% resulting in concentration of the moisture in oil; also causes reduction in PD inception voltage by approx. 20%, resulting PD discharge 2,000 – 4,000pC. iii. Poor impregnation, resulting PD discharge 1,000 – 2,000pC. [Type here] iv. Air gas bubbles (3 – 5mm), resulting PD discharge 1,000 – 10,000pC. b. Oil Barrier Insulation break-down (Irreversible) i. Breakdown of oil gap; apparent change 10,000pC and rises rapidly to 100,000 – 1,000,000pC ii. Incipient carbonizing the cellulose (heating over 300C); corresponds to several charge pulse of 100,000 – 1,000,000pC c. Creeping Discharge i. Splitting oil molecules under effect of sparking. Formation of hydrocarbons followed by formation of carbonized traces in pressboard. Lowering of PD magnitude to 1,000 – 5,000pC d. Failure of turn – to – turn insulation i. Sporadic PD pulses of magnitude 400 – 1000pC ii. Rises up to more than 100,000pC 2. Sources of PD generation Components Sources of PD Core and coil Assembly Operating Voltage oil-barrier-paper structure and oil Electrostatic Shields Leeds [Type here] Typical Faults Oil/surface contamination with PD attributed to particles, bubbles, reversible change of static electrification, insulation condition bad impregnation, high moisture, PD attributed to the Partial breakdown in irreversible degradation oil; surface of insulating material discharge; creeping discharge Sparking and arcing between bad connection “Conductor under floating potential” discharges Tracking in wooden blocks PD associated with voltage induced by main magnetic flux PD associated with voltage induced by stray flux [Type here] closed loops between adjacent members linked by the main flux (insulated bolts of core, pressing bolts, pressing metal rings, etc); sparking due to floating potential closed loops between adjacent members linked by stray flux; floating potential (e.g. ungrounded magnetic shunts) Bushings Operating Voltage Localized defect within the core: bad impregnation, high moisture, short-circuits between layers, sparking across the core surface Breakdown in oil; surface discharge across the porcelain Operating voltage PD associated with operating voltage at the fix tap position: PD associated with switching process LTC 3. Methods of PD detection Type of sensors [Type here] Partial breakdown in the selector and in the diverter switch compartment Poor or worn out contacts Advantages Disadvantages Electric Direct connection to the test tap, or through high frequency CT on the grounded wire, (“Rogovski coils”) Additional sensors in bus duct, electrostatic shields, neural etc. High sensitivity Can De-energizing for be calibrated in sensors terms of apparent installation charge Approximate location of PD source All capabilities to trend data Use of PD pattern Recognition technology Sensors configuration can match for better noise rejection Electro-magnetic (Antenna) RF UHF Easy to use Possible assessing external PD problems including PD in the bushings Serving as a noise (corona) channel High disturbances Only discharges of extremely high level can be detected Difficult to distinguish an equipment having problems from surrounding equipment Acoustics Piezo-accelerometer placed on transformer tank [Type here] Easy to install Capability detecting acoustic emission magnitude and trend, Pulse repetition rate and trend Localizing a source of PD Low sensitivity Minimal detecting apparent charge >10,000pC Responded to rain, sleet, electrical disturbances in the 4. Transformer Tests i. Accuracy Test ii. Dielectric insulation tests iii. Temperature rise tests iv. Short time current tests v. Verification of terminal markings and polarity 5. 6. [Type here] Standards Standard Standard Number Year Indian 2705 1992 British BS EN 60044-1 1999 International Electro-technical Commission (IEC) IEC 60044-1 2000 Australian AS 1675 1986 Australian AS 60044-1 2007 American ANSI C.57.13 1993 Chinese CNAS-PD20/09-B/1 Ref: ISO/IEC 17025 Typical specification for a 11 kV CT a. System voltage:11 kV Insulation level voltage (ILV) : 12/28/75 kV Ratio: 200/1 - 1 - 0.577 A Core 1: 1A, metering, 15 VA/class 1, ISF<10 Core 2: 1 A, protection, 15 VA/5P10 Core 3: 0.577 A, Class PS, KPV>= 150 V, Imag at Vk/2 <=30 mA, RCT at 75 C<=2 ohms Short time rating:20 kA for 1 second [Type here]