by 2 Sequence to follow Introduction of Electric traction 25kv AC traction on IR Present/future scenario on IR Concern Possible alternatives. 2 x 25 kV a c system. Major components of 2 x 25 kV System. Experience of 2 x 25 kV system on IR. Comparison of two systems. Improvement in train operations. PROS & CONS OF 25 kV V/s 2 X 25 kV a.c. SYSTEM Financial evaluation Constraints in conversion of conventional 25kv system Conclusions & recommendations 3 Introduction of Electric traction World over electric traction was experimented with d.c power supply during initial days of electric traction. The first system with 25 kV, 50 Hz, a.c. power supply was introduced in Germany and France. 4 Five ‘standard’ types of electrification systems emerged & can be found across Europe: 750 V DC 3rd rail, 1.5 kV DC, 3 kV DC, 15 kV 16.7Hz AC and 25 kV 50Hz AC Status on IR S.No. Voltage Section 1 750 V DC Kolkata Metro 2. 1500 V DC Mumbai suburban area 3. 3000 V DC Earlier used on Kolkota Suburban area & a portion of E.Rly. but now changed to 25 kV a.c. 4. 2x25 KV AC Bina-Katni-Bishrampur including Chirimiri 5. 25 kV AC All other electrified sections except 1. to 3. above. 5 25 kv Conventional OHE system (w/o BT & RC) Return current goes back to TSS through rails and earth. • 25 kv Conventional OHE system (with BT & RC) Return current does not pass through the rails or earth but through a separate return conductor. Return conductor runs close & parallel to catenary wire, inductive interference is reduced. 6 25 kv Conventional OHE system (w/o BT & RC) 7 25 kv Conventional OHE system (w/o BT & RC) Return current goes back to TSS through rails and earth. • 25 kv Conventional OHE system (with BT & RC) Return current does not pass through the rails or earth but through a separate return conductor. Return conductor runs close & parallel to catenary wire, inductive interference is reduced. 8 Booster Transformer Feeding System with Return Conductor and Rail Joints) 9 • Introduction of CC +10 rake • Introduction of 25 tone axle load stock • Augmentation of automatic signaling in entire sections • Increase in no. of trains in the feeding zone of TSSs. • Increase in haulage capacity of trains • Increase in speed of the trains. 10 Concern Off late, Railways have been facing competition from road sector for freight traffic and from airlines for passenger traffic. Further, higher GDP growth @8% and above is expected in future. Railways shall have to cater much more traffic, thus it has become necessary to increase the speed, capacity and hauling load of the train, for which power requirements for running these trains shall also go up. 11 Possible alternatives Further reduction the spacing between Traction substations – construction of new TSS at 15-20 km interval, Tr line & bays, DJ operation constraints etc Increase in the capacity of the traction transformer- from 13.5/21.6 MVA to 30 MVA, additional cost of Approx. 1.5 crores. Parallel operation of transformers : construction cost of third bay associated switch gears. 2 x 25 kV a.c system: higher tonnage freight trains & higher speed passenger trains with minimum voltage drop can be hauled 12 2 x 25 kV a.c system Principal of operation Power is fed from the TSS at 50 kV and utilization is achieved at 25 kV by providing Auto-Transformers of adequate capacity and by providing one additional conductor -- feeder Wire. Provides +25 kV Voltage between OHE and rail and 25 kV voltage between Rail/earth and the Feeder Wire. Spacing & capacity of the AT’s depends upon system design capacity requirements and tolerable limits of the inductive interference levels and normally varies from 10 to 15 kms interval 13 Fig 3 2x25 Kv OHE system (with Auto transformer ) 14 2 x 25 kV a.c system contd…. The traction load is shared by both the adjacent ATs in inverse proportion of respective distances i.e. the AT nearer to the Locomotive will share more load than the other one. 15 SSP Contact wire SP TSS Rail AT 1 AT 2 2x25 kV system AT feeder AT 3 Location of train ----Share of trainload by AT1. 100% SHARE OF TRAIN LOAD BY AT _____ Share of train load by AT2. Share of trainload by AT3. 0 L L 16 Major components of 2x 25 kV System Auto-Transformer Scott-connected transformer V-Connected Transformer Capacitance - Resistance Devices Series Capacitors Fault locators 17 Experience of 2 x 25 kv system on IR On IR 2x25 kv system was commissioned in Bina-Katni-Anuppur-Bishrampur including Chirimiri section in 1995-96. This section falls in erstwhile S.E.Railway of Indian Railway presently in Bilaspur division of South Eastern Railway and Jabalpur division of west Central Railway 18 Experience of 2 x 25 kv system on IR contd…. In the past 7 – 8 years, the system is being loaded to only 22% of the designed capacity in WCR portion. The system had been designed to cater for running of 2 no. 9000-ton trains & 4 nos. 7500 tone trains, which probably has not happened. In SECR due to operational requirements, one TSS i.e. Bishrampur has been closed down in Dec 1999 & the transformers of balance TSSs are loaded to maximum 50-55 % of the total rated capacity . 19 Experience of 2 x 25 kv system on IR contd…. Thus, the system is highly underutilized at present and advantage of 2x25 kV system could not be availed by IR. That is perhaps the reason that this experiment could not continue in other sections 20 COMPARISON OF TWO SYSTEMS Voltage profile of section :Due to less OHE current,OHE voltage profile of the 2x25 kV system is better. Harmonic: Since the fault levels are much higher on the 25 kV & 220 /132Kv side, there are less harmonics on the system. Technology :The technology of 2x25 kV system is bit complex due to the provision of equipment like; Scott connected transformer, C-R device etc Substation Spacing: : The substation spacing for 2x25 kV system is 80 – 100 kms.as compared to approx. 40 – 60 kms for conventional system. 21 IMPROVEMENTS ON TRAIN OPERATION 2 x 25 kV system is highly suitable for highspeed corridors and high haulage capacity sections. Improved operational benefits for the drivers due to less frequent opening/closing of breakers at neutral sections. No arcing problems encountered at overlaps as in the case of BT/RC system. 22 PROS & CONS OF 25 kV V/s 2 X 25 kV a.c. SYSTEM MERITS OF THE SYSTEM Reduced infrastructure cost due to increased spacing between TSSs. reduced voltage droop & losses due to lower current in feeder circuit. Better voltage regulation even on heavier load current, thereby allowing more traffic in the section. No requirement of BT & RC throughout the section. Most suited for highly loaded sections i.e. where load is in the range of 9000 ton plus and also more suitable for high speed operations. Technology for manufacturing most of the items already exists in the country and therefore local availability is not an issue anymore 23 PROS & CONS OF 25 kV V/s 2 X 25 kV a.c. SYSTEM DEMERITS OF THE SYSTEM Time required for maintenance including slewing of OHE is more Initial cost of 2x25 kV system as a whole is approx. 10-12% higher than the conventional cost. C-R Panel failures have been reported by WCR due to HT bushing bursting and burning of register elements, for which indigenous sources are not available but can be developed once the demand is there. Losses are on higher side, in case the load on the system is less than say 50% of the rated load. 24 Financial evaluation In the present energy fuel scenario, when electrification projects are yielding very high return i.e. 20 – 40%, even with marginal higher cost of 2 x 25 kV a.c. system, this system would be financially viable. Further,it will provide very high capacity for future growth to implement heavy haul for quantum jump in through put without any additional infrastructure. 25 FINANCIAL EVALUATION OF THE SYSTEM The brief summary of salient features of both the sections is givenCost/RKM in the followingCost/TKM table: RKM TKM Total Section VijayawadaVSKP (Conventional) sanctioned/Ex ecuted cost ( Rs. In Crs.) 202.74 Bina-Katni (2x25 kv 201.18 system) 366 268 905 702 0.55 0.75 0.22 0.29 Basis Completio n report. 2x25 Kv system costlier by 28% Completio n report Higher cost is due to the fact that at the time of installation & commissioning of 2x25 kv system, all the equipments of 2 x 25 kV a.c. system were imported & system was designed for 9000 tone trains instead of 4730 tone for conventional system 26 Comparative cost/TKM for various electrification projects (Cost in Crs. Of Rs.) Sanctio ned cost Electric al cost 234.62 160.00 41.00 288 729 VL-Trichi 91.69 50.00 20.00 178 LINWadi 67.00 22.00 161 Section MGSZFR Average 87.37 PSI cost RK M TK TK M M/ RK M Cost/TKM Railway Board sanction Total Electri cal PSI 2.5 0.32 0.22 .06 21.7.06 284 1.6 0.32 0.18 .07 07.7.06 333 2.1 0.26 0.20 .07 23.8.06 .07 27 COST COMPARISON OF CONVENTIONAL & 2X25KV AT SYSTEM FOR 100 RKM SECTION (as on 2006) S.N Items 25 kV conventional system 2 x 25 kV AT System 1 TSS ** 344.74 899.00 2 SP 21.12 3 SSP 4 10 km Transmission Line per TSS @Rs 24lacs per km & bay cost as Rs. 80 lacs 5 PSI erection charges (40 % of PSI equipments) 6 OHE cost (with 10% BT RC for conventional OHE, as per unit estimate of CORE/Allahabad. Feeder wire cost added for 2x25 kv system) 7 ** *** conventional system (3TSS, 3 SP, 4 SSP) 2 x 25 kV AT System (1TSS, 1 SP, 4 SSP) 1034.22 899.00 113.53 63.36 113.53 16.44 112.24 65.76 448.96 320.00 320.00 960.00 320.00 465.34 584.60 3799.20 4176.00 Total 6387.9 6542.1 Total cost per TKM 9.1 9.3 (2.4 % higher) 15.83 17.40 PSI cost for conventional system taken as per CORE unit estimate. Two sets, three single-phase v connected transformer considered. 28 FINANCIAL EVALUATION OF THE SYSTEM IR has saved Rs.17,000 crores due to electrification during the period 2000-01 to 2005-06, as per the published figures of Annual Statistical Statement. With this level of savings, we should not hesitate to spend a little higher on 2 x 25 kV system as compared to conventional 25 kV system at this stage only. It is being commonly considered by other countries world over. 29 Constraints in conversion of conventional 25kv system 2x25 kv system appears to be only alternative to meet the future load requirements especially in heavy density traffic routes. However, converting the existing 25 kv conventional system to 2x25 Kv system has is not very easy,it has its Constraints in conversion of conventional 25kv system to 2x25 kv system: own constraints • Super structures needs to be attached to mast to run feeder wire, for which power block shall be required. • Feeder wire needs to be erected above the centenary wire & it will not be possible to strung the wire by using wire trains, in fact this work will have to be carried out manually. Huge power block shall be required to execute this work. 30 It is for the above reasons that, most of the Railways world over go in for 2x25kv in the initial stage itself even though the traffic density is less at that time but expected to increase in future. It is for the above reasons that, most of the Railways world over go in for 2x25kv in the initial stage itself even though the traffic density is less at that time but expected to increase latter on. 31 Conclusions & recommendations • It’s the high time that a feasibility-cum-commercial study is carried out for all the high density routes, where power supply systems are nearing saturation, to arrive at a best possible system instead of implementing the adhoc measures by adding additional substations in the system. •A comparative study be undertaken for 2x25 kV system vis-àvis the conventional/BT-RC system and if 2x25 kV system proves to be cheaper, this can be straightway implemented. • Keeping in view the future scenario of load and traffic level, it is worth to adopt the 2x25kv system at initial stage itself, especially wherein 30tonne axle load trains are expected to run in automatic signaling territory . 32 33