Cost Management Plan PROJECT COST AND FINANCE MANAGEMENT ASSIGNMENT # 2 Submitted to: “SIR MUHAMMAD SHOAIB” Submitted by: MAHAM MANGRIO (01-298172-045) SYED ABDUL HANNAN SHERAZI (01-298172-118) Program & Section: “MS (PM) 1-C Dated: 26th October, 2017 1 Cost Management Plan COST MANAGEMENT PLAN CHAMBER OF HORROR 2 Cost Management Plan TABLE OF CONTENTS INTRODUCTION .......................................................................................... 4 ROLES AND RESPONSIBILITY ..................................................................... 4 UNIT OF MEASURE ..................................................................................... 5 LEVEL OF PRECISON ................................................................................... 6 LEVEL OF ACCURACY ................... Ошибка! Закладка не определена. ORGANIZATIONAK PROCEDURE LINKS ...................................................... 6 CONTROL THRESHOLD ............................................................................... 8 RULES OF PERFORMANCE MEASUREMENT................................................. 8 REPORTING FORMAT .................................................................................. 8 PROCESS DESCRIPTION .............................................................................. 8 ADDITIONAL DETAILS ........................................................................ 9 APPROVAL…………………………………………………………..10 ANNEXURE…………………………………………………………..11 3 Cost Management Plan 1. INTRODUCTION i. PURPOSE The purpose of designing this Cost Management Plan is to clearly describe the methodology for monitoring and controlling the cost of this project i.e. Chamber of Horrors during the project lifecycle. It includes the system and baseline for measurement of the project costs, their reporting, and controlling mechanism so that the successful completion of the project within the allotted budget can be ensured. For successful completion of this project within a given time and budget all the key project members and stakeholders must adhere to and work within this Cost Management Plan and the overall project plan it supports. ii. The cost management plan of Chamber of horrors will describe following components in detail:a. Unit of Measure b. Level of Precision c. Level of Accuracy d. Organizational Procedure Linkage e. Control Threshold f. Rules of Performance Measurement g. Reporting formats h. Process Description i. Additional Details 2. ROLES AND RESPONSIBILITIES The project manager will work with the project sponsor to define roles and expectations for resources involved in managing the overall project cost. These roles should define ownership for review, approval of all project activities, approval of project expenses and day to day cost management. The Project manager will be entirely responsible for coordinating with the sponsor so that there shall be smooth process and it will also help in completing project on time and within specific budget. The project manager will be responsible for assigning the task to the team and for that he must have good communication skills and he will also be responsible to monitor the execution of all 4 Cost Management Plan the activities. The project manger will be responsible for managing and reporting of project cost throughout the project duration. A meeting will be arranged monthly on the status of the project and project manager will be responsible to give updates on the project cost management of the preceding month. The following table will illustrate the roles & responsibilities more clearly:ROLE RESPONSIBILITY REPORTING Project Manager Manages the overall project Sponsor & Stakeholder Project Team To accomplish tasks assigned Project Manager by project manger Sponsor Provides funding for project Stakeholder Provides Feedback 3. UNIT OF MEASURE The area of the building is measured in acres. Element Unit Area 1 Acre 1Acre 43560 The human resource cost is measured on the basis of man hours and days. It will be based on man hours and days consumed by project manager, project team and other support staff. Element Unit Human Resource Man hours 12 per day Staff days 6 days All monetary resources is managed in Pakistani Rupees (PKR). The material of the projects will be measured accordingly: 5 Cost Management Plan Elements Unit Material Paint litre Cement bags 1 bag 20kg Tiles Sqft All the decoration items are measured on Lump sum basis. Machinery operating cost will be managed in terms of per electric unit. 4. LEVEL OF PRECISON If any of the amounts contains decimal point less than 5 than it will be ignored, the value before decimal points will be considered. For example 2.3 will be rounded off to 2. If amount will have decimal value more than 5 it will be rounded off to the nearest net value. For example 2.8 will be rounded off to 3. The cost of each activity will be rounded off to the net whole figure in tens & thousand places. For example 12356 will be rounded off to 12360. 5. LEVEL OF ACCURACY The level of accuracy of this project is +/-10%. 6. ORGANIZATIONAL PROCEDURE LINKAGE This part of the plan contains following points:- i. Annex A refers to the WBS of this project ii. Annex B refers to the WBS dictionary iii. Annex C refers to details of cost breakdown 6 Cost Management Plan 7. CONTROL THRESHOLD The maximum cost for chamber of horror is 30 million. Acceptable threshold level set for this project is +/- 5%. If the cost exceeds this level than the change in cost management plan will be requested. 8. RULES OF PERFORMANCE MEASUREMENT Earned Value Management (EVM) technique will be used to control cost throughout the project life cycle. Project Control Accounts Manager will be responsible for tracking costs and reporting it to PFO and Project Manager. Project Finance Officer will be responsible for finding out Cost performance indexes (CPI) and Schedule performance indexes (SPI) on monthly basis to keep track of cost and expenditures. Earned Value Threshold Metric Frequency of Blue Red Reporting CPI +/- 15% Weekly 0.8≤CPI≤1.2 CPI<0.8 or CPI>1.2 SPI +/- 15% Weekly 0.8≤SPI≤1.2 SPI<0.8 or SPI>1.2 Cost Performance Index (CPI) will be reported weekly and is the project’s EV/AC Schedule Performance Index (SPI) will be reported weekly and is the project’s EV/P 9. REPORTING FORMATS Document Expenditure status Frequency Monthly RESPONSIBLE Submitted TO Control accounts manager Project manager & report Project finance manager Detail project report Quarterly Work package manger Project Manager & Sponsor Apart from documentation to control the project cost and schedule performance, the 7 Cost Management Plan project manager will check the project on daily basis and for effective monitoring. 10. PROCESS DESCRIPTION i. Project Cost Tool TASKS TOOL Budgeting Information Cost Estimation EVM analysis Graphs For All these tasks MS Excel will be used as Cost tool Budget Tracking ii. Cost Reporting Reporting for cost management will be included in the monthly project status report. The Monthly Project Status Report will include a section labelled, “Cost Management”. This section will contain the Earned Value Metrics identified in the previous section. All cost variances outside of the thresholds identified in this Cost Management Plan will be reported on including any corrective actions which are planned. Change Requests which are triggered based upon project cost overruns will be identified and tracked in this report. Analysis of project performance may result in a change request to the cost baseline or other components of the project management plan. Change requests may include preventive or corrective actions, and are processed for review and disposition through the Perform Integrated Change Control process. 8 Cost Management Plan iii. Control Costs Project cost control includes: 11. Influencing the factors that create changes to the authorized cost baseline; Ensuring that all change requests are acted on in a timely manner; Managing the actual changes when and as they occur; Ensuring that cost expenditures do not exceed the authorized funding by period, by WBS component, by activity, and in total for the project; Monitoring cost performance to isolate and understand variances from the approved cost baseline; Monitoring work performance against funds expended; Preventing unapproved changes from being included in the reported cost or resource usage; Informing appropriate stakeholders of all approved changes and associated cost; and Bringing expected cost overruns within acceptable limits. ADDITIONAL INFORMATION i. CONTINGENCY PLAN Following is the procedure for applying contingency to cover cost increases or schedule slippages. Contingencies are under the sole control of the management of horror house. The application of contingency will be transparent to customers and will occur when the project manager makes a request to company management to apply it. The steps to apply contingency are as follows: 1. Identify the reason for the cost increase or schedule slippage and the expected total impact. 2. Present the contingency request to the management of Chamber of Horrors project 3. Upon approval, update the project plan, reducing the cost contingency available. 4. If the request is not approved, follow company management’s directions for dealing with the cost increase. 9 Cost Management Plan a) Potential Causes of Increases in Costs and Efforts: Following is the list for each cost category, of the factors that could lead to increase in costs: i. Designing project activities may require more effort of developers than planned, resulting in increased labor cost. Unplanned, paid overtime may require completing the project activities on schedule. ii. Software Acquisition Costs: Additional software is required by the project team to complete the project. The cost of acquiring material is higher than planned. iii. Labor Costs: Other Costs: Additional functionality or module may be added. 12. APPROVALS The signatures of the people below indicate an understanding in the purpose and content of this document by those signing it. By signing this document you agree to this as the formal Cost Management Plan for the Building Expansion Project. Approver Name Title Ali Quresshi Project Sponsor Maham Mangrio Project Manager Hannan Sherazi Project Manager Signature Date 10 Cost Management Plan Annex-A Work Break Down Structure (WBS) 11 Cost Management Plan Annex -B ACTIVITY LISTING WORK PACKAGE ID 1.1 WORK PACKAGE Building Outdoor Environment 1.2 2.1 2.2 3.1 3.2 4.1 Interior designing Exterior Designing Dummies Actors Mask ACTIVITY Selection of building (21780 sq/ft) which must have two floor s and a basement. Artificial trees/bushes Artificial Graveyard Wall decoration Placement of props Design furniture Design wall hangings Maintain intensity of lightening effect in each area Outdoor graveyard Design Horror park Design horror parking area Maintain intensity of effects in external environment of house The collection of dummies includes: Witches Dracula Horror dolls Mermaids Mummy Monkey Proper training will be given to each actor and after final test of they will be selected. Design Horror animated masks Paints Dough Brushes 12 Cost Management Plan Clothes 4.2 Wigs 4.3 . Music Collection of Wigs of all shades and style. Collection of horror songs Sequencing all the songs according to the activities Maintain intensity of fog Arrange different qualities of fog according to the requirement of attractions Arrangement of dim and bright lights Maintenance of lightning effect 5.1 Fog 5.2 Designer for designing clothes will be appointed. Clothes will be designed according to the shows requirement. 5.3 a. M n c e Lights o f l 6.1 Props The props that will be designed are : Skeleton Soldiers Bats Dentist chair Webs Pumpkins Tombstones Tags 13 Cost Management Plan 6.2 Instruments Crockery 6.3 Musical instruments Hammers Tool kits Horror themed crockery will be designed. 14 Cost Management Plan COST BREAKDOWN WORK PACKAGE ID 1.1 Annex- C WORK PACKAGE Building Outdoor Environment Cost 3000000 300000 1.2 2.1 2.2 3.1 3.2 4.1 4.2 4.3 Interior designing 500000 Exterior Designing 500000 Dummies 10000 Actors 200000 Mask 100000 Clothes 500000 Wigs 10000 Music 5.1 Fog 50000 Lights 400000 Props 50000 5.2 5.3 6.1 15