Chapter 9 & 26 - Limiting Factor, Throughput, & Linear Programming Limiting Factor Analysis - - - In the short term the sales demand maybe in excess of current production capacity. This could be because the output is restricted by a shortage of either of the following resources: o Skilled Labour o Materials o Equipment, or o Space A limiting factor (AKA Scarce resource) is any factor that is in scare supply. o The scarce resource stops the organization from expanding its activities further, so that there is a maximum level of activity at which the organization can operate. Within a short-term time period it is unlikely that constraints can be removed, and additional resources acquired. - Assumption – Based on marginal costing principles i.e., fixed cost is unaffected. - Contribution/Profit Maximisation Combination – Where there is a limiting factor, products should be ranked based on their contribution per limiting factor or scarce resource. o Profit is maximized when the greatest possible contribution to profit is obtained each time the scarce or limiting factor is used. - Process o Determine which products / activities have the greatest contribution per scarce resource and rank products/activities accordingly - from highest to lowest contribution per scarce resource. o Allocate the scarce resource based on the ranking above and work out the optimal production plan. o This will maximize the amount of contribution (and profit) overall. - Qualitative Factors to consider before determining the final production programme: o Customer Goodwill may be lost causing a fall in future sales if the organization cannot produce all the products in its product line. o Inability to satisfy demand for certain products may drive customers away to competitors. o Relatedness of the products – e.g., are they complementary or substitute goods? If so, lower sales for one product will affect sales of the other products, which have not been taken into account. - Downsides of Limiting Factor Analysis: o Difficulty in applying this procedure if there is more than one scarce resource. Therefore, Linear Programming would have to be used to determine the optimal production programme. o Only applies to those situations in which capacity constraints cannot be removed in the short term. In the longer-term additional resources should be acquired if the contribution from the extra capacity exceeds the cost of acquisition. - Contribution = Selling Price – Total Variable Cost OR - Contribution = Profit + Fixed Cost Explain briefly why the concept of contribution analysis is used in situations of scarce resources? - This concept is based on marginal costing principles. Fixed costs are sunk or irrelevant to the decision. Therefore, it is prudent to rank products based on contribution per unit of scarce resource and to produce and sell products that have not the highest contribution per unit but contribution per limiting factor. This is how the scarce resource should be allocated. Using this concept in limiting factor decisions will maximise profits. - We should always prioritize the sales of our products according to their contribution per limiting factor. Usually, the limiting factor is Demand and we can use contribution margin per unit to prioritize. When a resource becomes the limiting factor we do the same thing and prioritize by contribution margin per limiting factor, (e.g. the scarce resource of labour, raw materials etc.) Throughput Accounting - The theory of constraints (TOC) and throughput accounting are illustrations of where cross-functional collaboration between operations management and accounting can help to generate improved performance. - Goldratt and Cox (1984) advocated a new approach to production management called Optimized Production Technology (OPT). o OPT is based on the principle that profits are expanded by increasing throughput of the plant. - Throughput is a measure of profitability and is defined by the following equation: o Throughput = Sales Revenue – Direct Material Cost ο§ Only Direct Materials Cost is thought to be variable whereas rest of the costs (i.e., Direct Labour, Production Overhead, etc.) are thought to be Fixed. The OPT approach determines what prevents throughput being higher by distinguishing between bottleneck and non-bottleneck resources. - - A bottleneck is a limiting factor whose capacity limits the throughput of the whole production process. o The aim is to identify bottlenecks and remove them or, if this is not possible, ensure that they are fully utilized at all times. o Non-bottleneck resources should be scheduled and operated based on constraints within the system and should not be used to produce more than the bottlenecks can absorb. ο§ E.g. Two machines – X & Y. X can produce 500 units and Y produces 600 units then Machine X is a bottle neck and only 500 units should be produced as an additional 100 units will just result in increase in WIP and no increase in sales revenue. o The OPT philosophy therefore advocates that non-bottleneck resources should not be utilized to 100 per cent of their capacity, since this would merely result in an increase in inventory. There is no point in a nonbottleneck activity supplying more than the bottleneck activity can consume. This would merely result in an increase in WIP inventories and no increase in sales volume. - The theory of constraints (TOC) is described by Goldratt and Cox (1992) as the process of maximizing operating profit when faced with bottleneck and nonbottleneck operations. The process involves five steps: 1. 2. 3. 4. Identify the system’s bottlenecks; Decide how to exploit the bottlenecks; Subordinate everything else to the decision in step 2; Elevate (remove) the system’s bottlenecks; 5. If, in the previous steps a bottleneck has been broken, go back to step 1 and repeat the process for the new bottleneck. - The TOC is a process of continuous improvement to clear the throughput chain of all constraints. Thus, step 4 involves taking action to remove (that is elevate) the constraint. o This might involve replacing a bottleneck machine with a faster one, increasing the bottleneck efficiency or changing the design of the product to reduce the processing time required by the activity. o When a bottleneck activity has been elevated and replaced by a new bottleneck, it is necessary to return to step 1 and repeat the process. - To apply TOC ideas Goldratt and Cox advocate the use of three key measures: 1. Throughput contribution - which is the rate at which the system generates profit through sales. It is defined as sales less direct materials. 2. Investments (inventory) - which is the sum of inventories, research and development costs and the costs of equipment and buildings. 3. Other operational expenses (also known as total factory cost and conversion costs), - which include all operating costs (other than direct materials) incurred to earn throughput contribution. o The TOC aims to increase throughput contribution while simultaneously reducing inventory and operational expenses. o However, the scope for reducing the other operational expenses is limited since they must be maintained at some minimum level for production to take place at all. In other words, other operational expenses are assumed to be fixed costs. o The duo advocated a throughput orientation whereby increasing throughput must be given first priority, decreasing inventories second and decreasing operational expenses last. o The TOC adopts a short-run time horizon and treats all operating expenses (including direct labour but excluding direct materials) as fixed, thus implying that variable costing should be used for decision-making, profit measurement and inventory valuation. Throughput Accounting ratio - Galloway and Waldron (1988) advocated an approach called throughput accounting to apply the TOC philosophy. - To ascertain the optimal use of the bottleneck activity, they rank the products according to a measure they have devised called the throughput accounting (TA) ratio. The define the TA ratio as: - π»πππππππππ ππππππππππ πππππ [π»π·π¨πΉ] = Where πβπππ’πβππ’π‘ ππππ‘ππππ’π‘πππ [π ππ‘π’ππ] πππ ππππ‘πππ¦ βπ πΆππ π‘ πππ ππππ‘πππ¦ βπ - π»πππππππππ ππππππππππππ [πΉπππππ] πππ πππππππ ππ = πβπππ’πβππ’π‘ πππ π’πππ‘ πππππ’ππ‘ ′ π π‘πππ ππ πππ‘π‘ππππππ πππ ππ’πππ πππ π’πππ‘ o Throughput per unit – Sales price – direct materials cost πππ‘ππ πΉπππ‘πππ¦ πΆππ π‘ (π.π.ππ‘βππ ππππππ‘πππππ ππ₯ππππ ππ ) - πͺπππ πππ πππππππ ππ = - For multi products, return per factory hr differs due to different throughput contribution per unit but cost per factory hr remains the same. - Interpretation o TPAR > 1 – suggests that throughput contribution exceeds operating costs so the product should make a profit. Priority should be given to the products generating the best ratios. o TPAR < 1 – suggests that throughput is insufficient to cover operating costs. πππ‘ππ πππ‘π‘ππππππ πππ ππ’πππ π‘πππ ππ£πππππππ Multi-product Decisions - Throughput accounting may be applied to a multi-product decision making problem in exactly the same way as was described for limiting factor analysis - Given that fixed costs are unaffected by the production decision in the short run, the approach should be to maximise the throughput contribution earned. Process: 1. 2. 3. 4. 5. Identify the bottleneck constraint. Calculate the throughput per unit for each product. Calculate the throughput per unit of the bottleneck resource for each product. Rank the products in order of the throughout per unit of the bottleneck resource. Allocate resources using this ranking Improving TPAR 1. Increase the sales price for each unit sold, to increase the throughput per unit 2. Reduce material costs per unit (e.g., by changing materials or switching suppliers) 3. Reduce total operating expenses, to reduce the cost per factory hour 4. Improve the productivity of the bottleneck, e.g., the assembly workforce or the bottleneck machine, thus reducing the time required to make each unit of product. Throughput Return per factory hour would increase and therefore the TPAR would increase. Differences between Throughput and Contribution 1. Contribution treats direct materials, direct labour and variable overheads as variable costs, whereas through-put accounting assumes that only direct materials represent variable costs. 2. Throughput accounting is thus more short-term oriented and assumes that direct labour and variable overheads cannot be avoided within a very short-term period. In contrast, contribution assumes that the short term represents a longer period than that assumed with throughput accounting and thus classifies direct labour and variable overheads as variable costs that vary with output in the longer term. Linear Programming - Linear Programming is a technique for solving certain types of decision problems where more than one scarce resource exists. o It is applied to those problems which require the optimisation of some criterion, for example maximising profit / contribution or minimising costs, but where the actions that can be taken are restricted by limitations, such as the amount of finance available o Decision problems consisting of 2 products only will be dealt with o 2 or more products – simplex method will be used (outside the scope of the module) - The objective function refers to the quantification of an objective, and usually takes the form of maximizing profits or minimizing costs. Assumptions - Contribution per unit for each product and the utilization of resources per unit are the same whatever quantity of output is produced and sold within the output range being considered - It must also be assumed that units produced, and resources allocated are infinitely divisible. This means that an optimal plan that suggests we should produce 94.38 units is possible. However, it will be necessary to interpret the plan as a production of 94 units. Graphical Method - The graphical method of linear programming can be used when there are just two products. The steps involved are as follows: 1. Formulate the problem a. Define Variables b. Specify the objective function (Maximising or minimising) c. Establish Constraints d. Construct Objective Function 2. Draw the constraints on the graph 3. Establish the feasible region for optimal solution 4. Determine the optimal solution - To prevent nonsensical results, we must include a non-negativity requirement or constraint, which is a statement that all variables in the problem must be equal to or greater than zero. Optimal Solution - Graphical Method o Plot the Contribution Function inside the feasible region by choosing a random total contribution value. o Extend that contribution line until it intersects with the last corner of the feasible region boundary (Corner in the feasible region that intersects with the highest contribution line). - Algebraically o Find coordinates of the corner points of the feasible region o Work out the total contribution at each corner and select the point which results in the highest contribution. Binding Constraints, Slack and Surplus - The constraints that are at the optimal production point are called binding constraints. Thus, if this constraint were to be changed slightly (in a certain direction), this optimal solution would no longer be feasible. - Slack occurs when the maximum availability of a resource or other constraining factor is not used (there are more resources available than are required). Slack is the amount of the unused resource or other constraint, where the constraint is a ‘less than or equal to’ constraint. o Slack occurs in non-binding constraint. - Surplus occurs when more than a minimum requirement is used: surplus is the excess over the minimum amount of constraint, where the constraint is a ‘more than or equal to’ constraint. Implications of Slack - - If the amount of slack is high, it is an indication of inefficient use of a particular resource. If possible, the resource should be re-allocated to another part of the business. Resources such as labour time may even be subcontracted to another business. If slack is low, then management should be alert to the fact that this resource could become binding constraint and take on appropriate action, e.g., recruit additional labour, etc. Shadow Prices - The shadow price (or dual price or opportunity cost) of a limiting factor is the increase in value which would be created by having one additional unit of the limiting factor (binding constraint). o In terms of LP, it is the extra contribution or profit that may be earned by relaxing a binding constraint by one unit i.e., extra contribution from employing an extra labour hour or using an extra kg of materials. - When the additional unit is added to the constraint equation, the constraint line moves up in the graph. - This optimal response from an independent marginal increase in a resource is called the marginal rate of substitution o I.e., increase in qty of products produced from increasing one kg of materials or employing an extra labour hour. - The shadow price represents the maximum premium above the basic rate that an organisation should be willing to pay for one extra unit of a resource. - If Shadow price for an additional kg of material is £0.40 and the cost of material per unit was £4. Hence, the maximum amount that the organisation should be willing to pay for an additional unit of material is £4.40. Of course, any amount below £4.40 will result in an increase in total contribution and hence profits. - Since shadow prices indicate the effect of one unit change in a constraint, they provide a measure of the sensitivity of the result. - The shadow price of a constraint that is not binding at the optimal solution is zero. - Shadow prices are only valid for a small range before the constraint becomes nonbinding or different resources become critical. Uses of Linear Programming 1. Calculation of Relevant Costs - - LP can assist in the calculation of relevant costs which is essential for decision making. When a resource is scarce, alternative uses exist that provide a contribution. An opportunity cost is therefore incurred whenever the resource is used. The relevant cost for a scarce resource is calculated as: o Acquisition Cost of resource + Opportunity Cost The Opportunity cost is the shadow price of the limiting constraint. 2. Maximum payment for additional scarce resources - - Opportunity costs provide important information in situations where a company can obtain additional scarce resources, but only at a premium. How much should the company be prepared to pay? For example, the company may be able to remove the labour constraint by paying overtime. The maximum the company can pay is the basic labour rate plus the shadow price for an additional unit of labour. The total contribution will therefore be improved by any additional payment below the shadow price. 3. Control - Opportunity costs are also important for cost control. The responsibility centre should therefore be identified not only with the acquisition cost but also with the opportunity cost from the loss of one scarce unit of materials (shadow price). - This process highlights the true cost of the inefficient usage of scarce resources and encourages responsibility heads to pay special attention to the control of scarce factors of production. - This approach is particularly appropriate where a firm has adopted an optimized production technology (OPT) strategy because variance arising from bottleneck operations will be reported in terms of opportunity cost rather than acquisition cost. 4. Managing bottleneck Constraints - When scarce resources are fully utilized, they are referred to as bottleneck operations/resources. It is important that managers seek to increase the efficiency and capacity of bottleneck operations. - Capacity can be increased by working overtime on the bottleneck, subcontracting some of the work that is undertaken by bottleneck operations, investing in additional capacity at the bottleneck and implementing business process improvements such as business process reengineering (BPR) and total quality management processes.