LOGIC FOR PS FIORI APPS

advertisement
For this app My projects active
In this app it has to display all the active project list available in the system.
Here in the above screen shot you can observe the highlighted part is the list of active projects
available in the system T-code CJ20N.
For this app multi project view it has to display all the projects available in the system with respect
to status of the project is CRTD – CREATED REL- RELEASE TECO-TECHINICALLY COMPLETED.
From the above screen shots, you can observe the different project list available in the system at
different status of the project.
Here in this app confirm project milestone. This app is used to confirm the milestone of a project.
Here in the above screen shot you can observe the highlighted part at actual date tab. If that date is
displayed, then it is considered as confirmation of a project milestone. This functionality of
confirmation has to be triggered from app once you can be able to fetch the data.
In the above app upcoming milestone. We use this app to determine the list of milestones in the
project which yet to be confirmed or need to be confirmed in future.
Here in the above screenshot, you can observe the highlighted tab actual date is blank. This type of
milestones is considered as upcoming milestones of the project. This type of milestones list available
in the project has to be displayed in the app (upcoming milestones).