BZ460 Project Management
1
BZ460 Project Management
Activity
A
B
C
D
E
F
G
H
Estimated
Duration
2
10
8
15
7
20
12
5
Early
Start
0
2
2
2
12
10
19
31
Early
Finish
2
12
10
17
19
30
31
36
Late Start
4
6
7
8
16
15
23
35
Late
Finish
6
16
15
23
23
35
35
40
Total
Slack
4
4
5
6
4
5
4
4
Yes, the project can be completed within 40 weeks. It will take 36 weeks. The longest path in
the network is A-B-E-G-H.
Activity
A
B
C
D
E
F
G
Estimated
Duration
2
10
8
15
7
20
15
Early
Start
Early
Finish
Late
Start
Late
Finish
Total
Slack
3
12
13
19
18
19
33
31
8
16
15
23
23
23
35
35
5
4
2
4
Actual
Finish
3
12
13
2
BZ460 Project Management
H
5
33
38
35
40
2
The project can still be completed in the allotted time (40 weeks). The expected completion time
has moved from 36 to 38 weeks. Therefore attention should be given to activity F if there is a
need to speed up the expected completion time.