Bitfury – Inplenion. ERP Implementation Phase 1. Discovery and BRD Project kick-off call 23 November 2021 AT Discovery # Person 1 Carlo Frondaroli 2 Vadim Krutov 3 Oleg Blinkov 4 Alexey Deyneko 5 Oleg Voronkov 6 Vincent Schreuder 7 Ellen Gormley 8 Natalia Tcarakova 9 Dmitry Strukov 10 Mike Hurton 11 Katerina Doykova 12 Paul Doodson 13 Henk van der Merwe 14 Naeem Essop 15 Gabriel Burgener 16 Mariana Pencheva 17 Suzanne Stoop 2 Phase Project Team Department Finance Strategy & Business efficiency Mining Operations IT and Infrastructure Strategy & Business efficiency Supply Chain Management Finance Hardware Sales Strategy & Business efficiency LiquidStack IT and Infrastructure Finance Position CFO Chief of staff Head of DC Development & Operations IT and Digital Transformation Director Business Efficiency Manager Supply Chain Manager Finance Director Head of Customer Care Senior Strategic Analysis Manager Financial Controller IT Product owner NetSuite Administrator Role Project Sponsor Project Director SME SME Co-Project Manager Co-Project manager, SCM Process owner SME SME SME SME SME SME Contract owner form Inplenion side Co-Project Manager SME SME SME @ carlo.frondaroli@bitfury.com vadim.krutov@bitfury.com oleg.blinkov@bitfury.com alexey.deyneko@bitfury.com oleg.voronkov@bitfury.com vincent.schreuder@bitfury.com natalia.tcarakova@bitfury.com ellen.gormley@bitfury.com dmitry.strukov@bitfury.com mike.hurton@liquidstack.com katerina.doykova@bitfury.com paul.doodson@bitfury.com henk.vdmerwe@inplenion.com naeem.essop@inplenion.com gabriel.burgener@inplenion.com mariana.pencheva@inplenion.com suzanne.stoop@inplenion.com Legal Notice: All information in this presentation is strictly confidential and may not be reproduced, transmitted or used in any form. AT Discovery Phase Objectives and approach Discovery phase objective is to acquire implementation playbook - Business requirements document (BRD), which is containing: To-be processes described Approach to to-be processes automation: Ready for implementation in vanilla NetSuite The list of Netsuite customizations and automation/arrangement outside system Highlevel architecture design Implementation phases, anticipated timelines and workload Implementation risks register What should be addressed: Define Objects for master data Sales orders lifecycle management Procurement and Purchase Order lifecycle management Inventory management Manufacturing management Delivery and logistics management Demand and Supply planning and balancing How should be performed – Bitfury and Inplenion will work as a single team in close cooperation with regard to this project phase: 3 Discover as-is processes in depth Bring best practices and Netsuite specifics on the table Identify chellenges and produce options Describe dilemmas and facilitate discussion to the decision Legal Notice: All information in this presentation is strictly confidential and may not be reproduced, transmitted or used in any form. AT Scope structure Project scope is structured from NetSuite implementation sequence perspective: • • • • • • • • • • • Inventory Valuation Method (Direct Cost Evaluation…) Transition (Dummy) Items for Order2Cash Phase 1 Contract Manufacturing Locations Traceability Warehousing, Inflow, Outflow, and Transit Inventory Transfer (Wafers Transfer to Taiwan) Inventory Transfer (Chips Transfer to Taiwan) Inventory Transfer (Chips & PSU Transfer to China) Transfer (Servers Transfer to Data Centres – EU Inventory Items and Fixed Assets Fixed Assets to Inventory Conversion – Inplenion Solution Order2Cash • • • • • Order Management Process (Sales Channels, Order Types, Users) Outbound Shipment and Fulfilment Process (Shipment Terms, Customs,) Payments and AR Register Intercompany Order Management Workflow Procure2Pay • • • • • Procurement Management (Vendors, Pos, Users) Inbound Shipments and Item Receipts Internal & at Contract Manufacturers Landed Costs Internal & at Contract Manufacturers Payments, and AP Register Workflow Inventory Management 4 Legal Notice: All information in this presentation is strictly confidential and may not be reproduced, transmitted or used in any form. AT Scope structure Project scope is structured from NetSuite implementation sequence perspective: Manufacturing Data Centers and Locations Demand & Supply Planning 5 • • • • • • • • • • Assemblies, Sub-Assemblies, Serialized Assemblies, BOM Setup Inventory Accounting/Costing Setup Contract Manufacturing Setup Contract Manufacturing Make to Stock Process (Chips, PSU) Wafers cutting and Chips Production Inplenion Solution Contract Manufacturing Make to Order Process (Servers) Serialized Assemblies and Fixed Assets Inbound and Outbound Transfer Evaluation of manufacturing capacity planning alter natives • • • • • New Data Centres Operations of Data Centres Locations and Contract Manufacturers Locations Financial Impact for Consignment Reporting and Classification • • • • • • • • Demand Planning Overall Process Sales Forecast Opportunities and Weighted Average Orders to Demand Plan MRP (Push Approach for Wafers / Chips / PSU) MRP (Pull Approach for Servers) Item Supply Planning Outcome Procurement NetSuite Planning and Budgeting (Optional) Legal Notice: All information in this presentation is strictly confidential and may not be reproduced, transmitted or used in any form. AT Project management structure and roles Project Committee board Bitfury: • Carlo Frondaroli – CFO, Role: Project sponsor • Vadim Krutov - Chief of staff, Head of Strategy & Business efficiency, Head of Commercial stream, Role: SME. Project Director • Oleg Blinkov - Head of DC Development, Operations and SCM; • Alexey Deyneko - IT and Digital Transformation Director Inplenion: • Henk van der Merwe – Program director; Role: Contract owner form Inplenion side Project Management Bitfury • Oleg Voronkov – Role: Project manager • Vincent Schreuder – Role: Co-Project manager, SCM Process owner Inplenion • Naeem Essop – Role: Project manager Workshop Streams Bitfury • Vincent Schreuder – Head of SCM, Role: SME • Natalia Tcarakova – Head of Customer Care, Role: SME • Oleg Voronkov – Business Efficiency manager, Acting Customer Care function supervisor, Role: SME • Ellen Gormley – Finance Director, Role: SME • Dmitry Strukov – Role: Accounting architecture and audit SME • Mike Hurton - Financial Controller, LiquidStack, Role: SME • Katerina Doykova – IT Product owner, Role: SME • Paul Doodson - NetSuite Administrator, Role: SME Inplenion • Gabriel Burgener • Mariana Pencheva • Suzanne Stoop 6 • • • • Project direction and goal setting Decisions on dilemmas and options Progress assessment Resources delegation • • • • • • • Scope and Schedule management Team orchestration Risks management and mitigation Dilemmas description and reporting for decision making Progress Reporting Communication support Project administration • Subject matter expertise and Process description by owners – as-is processes and current business practice NetSuite as-is setup and access by System owners and administration Elaboration of to-be processes description with Best practices Deliverables drafting and validation • • • Legal Notice: All information in this presentation is strictly confidential and may not be reproduced, transmitted or used in any form. AT Communication Forum guidance Frequency Project Committee call Thursday @ 1 CET bi-weekly Forum Representation Inplenion and BITFURY Key Team Members Project management call Monday, Inplenion to send BITFURY Wednesday sync Progress Reporting frequency WeeklyOnce a week Thursday morning Project communication space Inplenion Internal • • 7 Project chat – MS Teams (project managers and workshop groups) SharePoint space Legal Notice: All information in this presentation is strictly confidential and may not be reproduced, transmitted or used in any form. AT Discovery 8 Phase timelines Legal Notice: All information in this presentation is strictly confidential and may not be reproduced, transmitted or used in any form. AT Initial Workshop sessions timelines Proposed Date/time Session Length Topic Suggestion: To discuss as part of Kick-off (we’ll have 1 hour call) 20min High-level overview, parking lot Focus on general company details (locations, market, number of employees, etc.) confirming agenda/participants, general preferences, build-out of initial parking lot topics and scope for all topics Bitfury: ● Carlo Frondaroli ● Vadim Krutov ● Oleg Blinkov ● Alexey Deyneko ● Oleg Voronkov ● Vincent Schreuder ● The rest of team is optional Inplenion: ● Meenakshi Sooneeram ● …. ● …. 30th of November 10:00 - 11:40 CET OR 14:00 - 15:40 CET 1hr40min Design to Build Bitfury: ● Oleg Voronkov ● Vincent Schreuder ● Ellen Gormley ● Dmitry Strukov ● Mike Hurton ● + Finance controllers Inplenion: ● Meenakshi Sooneeram ● Warwick Smith ● …. 9 Agenda Focus on item strategy, warehouse setup, inventory management Who should attend Legal Notice: All information in this presentation is strictly confidential and may not be reproduced, transmitted or used in any form. AT Initial Workshop sessions timelines Proposed Date/time Session Length Topic Agenda Who should attend 1st of December 10:00 - 12:00 CET OR 14:00 - 16:00 CET 2hr Procure to Pay Focus on Expense reporting, inventory planning, purchasing, receiving, vendor returns 6th of December 10:00 - 12:00 CET OR 14:00 - 16:00 CET 2hr Order to Cash Focus on shipping, quotes, orders, fulfillment, invoicing, payment collection, RMA Bitfury: ● Oleg Voronkov ● Vincent Schreuder ● Ellen Gormley ● Dmitry Strukov ● Mike Hurton ● Paul Doodson ● + Finance controllers Inplenion: ● Meenakshi Sooneeram ● Tanja Chater ● …. Bitfury: ● Oleg Voronkov ● Vincent Schreuder ● Natalia Tcarakova ● Mike Hurton Inplenion: ● Meenakshi Sooneeram ● …. ● …. 10 Legal Notice: All information in this presentation is strictly confidential and may not be reproduced, transmitted or used in any form. AT Initial Workshop sessions timelines Proposed Date/time Session Length Topic Agenda 7th of December 2hr Plan to Produce 2hr Demand Planning Work Order, BOM, Manufacturing Cost Templates, WIP, Bitfury: Manufacturing Routings, Outsourced Manufacturing ● Oleg Voronkov ● Vincent Schreuder ● Dmitry Strukov ● Mike Hurton Inplenion: ● Meenakshi Sooneeram ● Warwick Smith ● …. Safety Stock, Let Sizing Method, Fixed Lot Size, Supply Bitfury: Planning Periods, Supply Type, Demand Source, ● Oleg Voronkov Forward and Backward Consumption Days, Demand and● Vincent Schreuder Planning Time Fences, Reschedule In/Out Days ● Dmitry Strukov ● Mike Hurton Inplenion: ● Meenakshi Sooneeram ● Warwick Smith ● Tanja Chater 13:00 - 15:00 CET 13th of December 10:00 - 11:30 CET OR 13:00 - 14:30 CET 11 Who should attend Legal Notice: All information in this presentation is strictly confidential and may not be reproduced, transmitted or used in any form. AT Initial Workshop sessions timelines Proposed Date/time Session Length Topic Agenda Who should attend 14th of December 1hr30min Record to Report Focus on Accounting, Finances, Taxes, etc. 30min Parking lot review Review of any questions not addressed in other topics, customizations Bitfury: ● Oleg Voronkov ● Vincent Schreuder ● Ellen Gormley ● Dmitry Strukov ● Mike Hurton ● + Finance controllers Inplenion: ● Meenakshi Sooneeram ● …. …. Bitfury: ● Oleg Voronkov ● Vincent Schreuder ● Ellen Gormley ● Dmitry Strukov ● Mike Hurton ● + Finance controllers Inplenion: ● Meenakshi Sooneeram ● …. 10:00 - 11:30 CET OR 13:00 - 14:30 CET To be confirmed by Client 12 Legal Notice: All information in this presentation is strictly confidential and may not be reproduced, transmitted or used in any form. AT Questions 13 Legal Notice: All information in this presentation is strictly confidential and may not be reproduced, transmitted or used in any form. Thank you 14 Legal Notice: All information in this presentation is strictly confidential and may not be reproduced, transmitted or used in any form.