Problems on Theory of constraint TOC Company produces two products, Y and Z that are processed in four departments, A, B, C and D. Product Y requires three types of materials, M1, M2 and M4. Product Z requires two types of materials, M2 and M3 The requirements for each product are summarized in the table below. Resource Required per unit of Product Y Required per unit of Product Z Material 1 Material 2 Material 3 Material 4 Department A ₹100 ₹100 ₹15 15 minutes ₹100 ₹100 10 minutes Department B Department C 15 minutes 15 minutes 30 minutes 5 minutes Department D 15 minutes 5 minutes TOC Each department has 2,400 minutes of available time per week. The Company's operating expenses are ₹30,000 per week. Based on current demand, the company can sell 100 units of product Y and 50 units of product Z per week. Sales prices are ₹450 for product Y and ₹500 for product Z. All four materials are available in sufficient quantities. The needed workers are also available. Required: 1. Determine the company's constraint. 2. Determine the throughput per unit for each product. 3. Determine the throughput per minute of the constrained resource for each product. 4. Determine the product mix needed to maximize throughput, i.e., the number of units of Y and Z that should be produced per week. 5. Determine the maximum net income per week for the Company. 6. Suppose the company broke the current constraint by doubling the capacity of that resource. What would become the new constraint? Solution TOC The following approach is useful when there are only two products and there is only one binding constraint in addition to demand. However, a different approach is needed when there are overlapping constraints, i.e., more than one binding constraint. Linear programming is needed to solve the more difficult problems involving multiple products with multiple binding constraints. 1. Determine the company's constraint. Time requirements to meet demand for each department are calculated as follows: Department Product Y A B C D (15 min)(100 units) (15 min)(100 units) (15 min)(100 units) (15 min)(100 units) Product Z (10 min)(50 units) (30 min)(50 units) (5 min)(50 units) (5 min)(50 units) Total Time Required Per Week 2,000 minutes 3,000 minutes 1,750 minutes 1,750 minutes Each machine center has only 2,400 minutes of available time per week. B is the constraint because it does not have enough capacity to process 100 units of Y and 50 units of Z per week. TOC 2. Determine the throughput per unit for each product Throughput per unit for each product is needed so that we can determine how to use the constraint to maximize throughput. Throughput per unit is as follows: Throughput Per Unit = Sales price - Materials Cost Product Y Z Sales price Materials Cost ₹450 – 215 ₹500 – 200 - Throughput Per Unit ₹235 ₹300 TOC 3. Determine the throughput per minute of the constrained resource for each product. Throughput/ Minute (constrained resource ) = Product Y Z Throughput/Unit Minutes required in B ₹235 ÷ 15 ₹300 ÷ 30 Throughput/Unit Minutes required in B Throughput/ Minute ₹15.67 ₹10.00 TOC 4. Determine the product mix needed to maximize throughput, i.e., the number of units of Y and Z that should be produced per week. • Maximizing throughput requires producing as much of the product with the highest throughput per minute of the constrained resource as needed to meet demand. • So the company should produce 100 units of product Y. • This requires (100 units)(15 minutes) = 1,500 minutes of time in the constraint department B and leaves 2,400 - 1,500 = 900 minutes for the production of 30 units of product Z, i.e., 900 minutes ÷ 30 minutes per unit = 30 units of Z. TOC 5. Determine the maximum net income per week for TOC Company. Sales: 100 units of Y = (100)(₹450) 30 units of Z = (30)(₹500) COGS: 100 units of Y = (100)(₹215) 30 units of Z = (30)(₹200) Throughput Less Operating expense Net income ₹45,000 15,000 ₹21,500 6,000 ₹60,000 27,500 32,500 30,000 ₹2,500 Note: An assumption in this illustration is that there are no beginning or ending inventories of work in process or finished goods. COGS: Cost of Goods Sold TOC 6. Suppose the company broke the current constraint by doubling the capacity of that resource. What would become the new constraint? Doubling the capacity of Department B would allow the company to produce 60 units of product Z in addition to the 100 units of product Y. Since only 50 units of Z are demanded, the company would have unused capacity in all departments. Therefore, external demand would become the constraint. Of course the new solution would be at the intersection of the demand constraints, i.e., 100 Ys and 50 Zs. Graphic Analysis TOC The following graphic analysis provides a general approach for solving simple product mix problems that is also applicable when there are overlapping constraints. First, plot the constraints to find the feasible solution space. The B constraint is 15Y + 30Z = 2,400 so Department B could produce 160 Y's (i.e., 2,400/15) or 80 Z's (i.e., 2,400/30), or some combination of Y and Z indicated by the constraint line connecting those two points on the graph. The department B constraint and demand constraints define the feasible solution space indicated by the mustard colored area on the graph. TOC TOC 2. Check the solution at each corner point, or plot the objective function and move it to the right as far as possible in the feasible solution space. The objective function is to maximize throughput where Throughput = 235Y + 300Z. Checking the corner points we find that 100 Y and 30 Z provides the greatest amount of throughput. Corner Point 100 Y and zero Z 100 Y and 30 Z 60 Y and 50 Z Zero Y and 50 Z Throughput (100)(235) = 23,500 (100)(235) + (30)(300) = 32,500 (60)(235) + (50)(300) = 29,100 0 + (50)(300) = 15,000 TOC • If we plot the objective function 235/300 (i.e., it takes .7833 of a Z to produce as much throughput as 1 Y), • we can locate the solution by moving it to the outer most point in the feasible solution space as illustrated below. • The first objective function shows that 100 Ys would produce the same throughput as 78.3333 Zs. • This is an iso-throughput line indicating that any point on the line represents a combination of Y and Z that produces ₹23,500 of throughput. • The point indicated by 100 Y and 30 Z is the last point the objective function touches in the feasible solution space as we move it up and to the right. • This point indicates the solution to our product mix problem. TOC TOC Q2. A Furniture Company XYZ produces two products, End Tables and Sofas that are processed in five departments, Saw Lumber, Cut Fabric, Sand, Stain, and Assemble. End tables are produced from raw lumber. Sofas require lumber and fabric. Glue and thread are plentiful and represent a relatively insignificant cost that is included in operating expense. The specific requirements for each product are provided in the table below. Resource or Activity (Quantity available per month) Lumber (4,300 board feet) Fabric (2,500 yards) Saw Lumber (280 hours) Cut Fabric (140 hours) Sand (280 hours) Stain (140 hours) Assemble (700 hours) & Required per End Table 10 board ft @ ₹10 = ₹100 30 minutes 30 minutes 20 minutes 60 minutes Required per Sofa 7.5 board ft @ ₹10 = ₹75 10 yards @ 17.50 = ₹175 20 minutes 20 minutes 10 minutes 30 minutes 90 minutes TOC The Company's operating expenses are ₹75,000 per month. Based on current demand, the company can sell 300 End Tables and 180 Sofas per month. Sales prices are ₹300 for End Tables and ₹500 for Sofas. Required: 1. Determine the XYZ Company's constraint. 2. Determine the throughput per minute of the constrained resource for each product. 3. Determine the product mix needed to maximize throughput, i.e., the number of End Tables and Sofas that should be produced per month. 4. Determine the maximum net income per month for the XYZ Company. 5. Suppose XYZ Company broke the current constraint resource. What would become the new constraint? 6. Solve the XYZ Company product mix problem assuming that only 3,000 board feet of lumber can be obtained rather than 4,300 board feet. TOC Q3. A Company produces two products, X and Y that are processed in two departments, A and B. The requirements for each product are provided in the table below. Resource Department A Department B Required per unit of Product X 2 hours 3 hours Required per unit of Product Y 4 hours 2 hours Weekly capacity is 80 hours for Department A and 60 hours for Department B. Throughput per unit is ₹60 for X and ₹50 for Y. Required: 1. Assume that the company can sell as much of X and Y as it can produce. Determine the number of units of X and Y that should be produced per week to maximize throughput. 2. Now assume that Weekly demand is 12 for Product X and 14 for Product Y. What would be the new product mix needed to maximize throughput?