Quality Control Questions Questions Q1 A quality inspector took six samples each of four observations, of the length of time (minutes) it took to process loan applications at a credit union. Data for the exercise is provided below: Sample Observation 1 12.11 12.14 12.10 12.11 2 12.11 12.10 12.11 12.08 3 12.15 12.12 12.10 12.11 4 12.09 12.09 12.11 12.15 5 12.12 12.10 12.08 12.10 6 12.09 12.14 12.13 12.12 Use the information to obtain two-sigma control limits for the means of future times. It is known from previous experience that the standard deviation of the process is 0.02 minute. Q2 A manager for an assembly department took data for twelve working days and found the following number of defectives of mobile phone chargers over the period. Construct a control chart for the fraction defective using three-sigma limits. Sample No. 1 2 3 4 5 6 7 8 9 10 11 12 No. of Samples 250 251 249 249 252 246 247 255 246 248 253 255 No. of Defectives 30 40 34 32 20 33 55 21 48 31 36 32 Fraction Defective 0.120 0.159 0.137 Q3 The postmaster of a small town receives a certain number of complaints each day about mail delivery. Construct a control chart to describe 98.5% of the variation in the following data and determine whether the process is in control: 1 2 3 4 5 6 DAY 7 5a 10 14 8 9 6 5 a Number of complaints 8 9 10 11 12 12 8 7 6 4 Quality Control Questions Q4 A medical facility does MRIs for sports injuries. Occasionally a test yields inconclusive results and must be repeated. Using the following sample data and n = 38, to construct a control chart that will describe 95% percent of the chance variation in the process when the process is in control. Is the process in control? If not, eliminate any values that are outside the limits and compute revised limits. 1 2 3 4 5 6 1b 2 2 0 2 1 SAMPLE 7 8 2 0 9 10 11 12 13 2 7 3 2 1 Q5 Using the appropriate control chart, determine two-sigma control limits for each of the following cases: a. An inspector found an average of 3.7 scratches in the exterior paint of each of the cars being shipped to dealers in a particular month. b. Before shipping lawn mowers to dealers, an inspector attempts to start each mower and notes any that do not start on the first try. The lot size is 100 mowers, and an average of 4 did not start. Q6 Surface defects have been counted on a number of rectangular steel plates, and the data is shown below. The control chart for nonconformities is to be set up using this data. a. Draw an appropriate control chart to describe 97.5% of the variation in the process. b. Determine whether or not the process is in control. c. Explain your response to (b) above. Sample No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Non-conformities 1 0 2 1 1 2 0 0 2 1 1 5 8 0 b Number of retests