Method Statement Assessor Enter Company Name Here Department / Location Date Enter Company Logo 1. Preliminary Information Event Name Project Name Issue Date ADGP Project Type Location on site Construction Activations ADGP 2. Project Description Fan Zone Yes ☐ No ☐ Site start date MS Number Revision number 25-11-2019 Duration Est. End date Est. End time 5 days 3. Full Description & sequence of work to be carried 2-12-2019 11:00 PM Expand as required. On the 25th a truck will come from our side around noon that has all our activations All our products are already tested and prebuilt and are split in pieces We will assemble each activation and then some branding and painting will happen After that all electronics will be placed and tested We will start setting up on the 25th and our activations should be all set and tested by the 26th night or maximum 27th noon 4. Resources Personal details (including estimated employee numbers/trades and working hours) Employees: 5 (12 hours/day) (2 days) Training details (including specific training, competency and experience requirements for both operatives and supervisors) All people who are coming are well trained and experienced Sub-contractor work element / personnel (including type of sub-contracted work and workforce size/trades) Production: 7 (12 hours/day) Branding: 4 (12 hours/day) (2 days) Supervisor details and arrangements (including supervisor/operatives ratio, sub-contractor supervision details and arrangements for young persons/apprentices) Each team will have his own supervisor (1 for production, 1 for branding and 1 for employees) All supervisors are seniors with at least 10 years of experience in their field Plant / equipment requirement details (including vehicle movement and inspection/maintenance/testing arrangements) Only a truck is required to enter to drop the items each in its location Materials, movement and storage details (including control of manual handling, movement between levels, traffic interface and ignition sources) Handling will be properly done using approved methods, moving elements will be done using trucks and trolleys abiding by all safety rules On site storage is not required, only elements will be stored near each activation until they are assembled. Storage will happen in a very professional way without any risk to any employee, labor or any person around. 5. Risk Assessment(s) for significant activities Are there RA’s for: 4.1 Access/egress 4.2 Place of work 4.3 Others at risk 4.4 COSHH, noise, vibration, fire etc 4.5 Environmental risks 4.6 Sub-contracted activities Yes ☐ ☐ ☐ ☐ No ☐ ☐ ☐ ☐ N/A ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ 6. Control Measures to be used 5.1 Permit required 5.2 Security arrangements 5.3 Special training (confined space, towers, plant etc) Yes ☐ ☐ ☐ No ☐ ☐ ☐ RA Title/s Date of RA N/A ☐ ☐ ☐ 7. Emergency Arrangements 6.1 Rescue Click or tap here to enter text. 6.2 Fire fighting Click or tap here to enter text. 7.3 Details of rescue arrangements Click or tap here to enter text. 7.4 Special first aid arrangements Click or tap here to enter text. 7.5 Spillage containment arrangements (if appropriate to task) Click or tap here to enter text. Yes ☐ No ☐ NA ☐ ☐ ☐ ☐ 8. Temporary amended Systems Yes ☐ ☐ ☐ ☐ 7.1 Traffic routes 7.2 Emergency Arrangements 7.3 Services 7.4 Other No ☐ ☐ ☐ ☐ 9. Temporary amended Systems 8.1 Monitoring arrangements 8.2 Enforcement arrangements Yes ☐ ☐ No ☐ ☐ N/A ☐ ☐ ☐ ☐ Comments N/A ☐ ☐ Comments 10.General Comments Click or tap here to enter text. Our setup will be very smooth and fast since it is done already and all what need to do is assemble each piece in its place on site. Name of person completing form Signature Elie FARAH Date 18-11-2019 The following staff have been given instruction with regard to the contents of this method statement and have signed to state that they have read and understood its contents Name Job role Signature Date Elie FARAH Manager 18-11-2019 Sami Mohammed Assistant Manager 18-11-2019 Vishak Chavana Technical Engineer 18-11-2019 Isran Mohammed Event Manager 18-11-2019 Received by Approved For HSE Office Use Only Date Date Approved with comments Risk Assessment Date Comments Dated Rejected Date