CE 213 – 18 ENGINEERING UTILITIES SCHEDULE: TUESDAY / 10: 00 AM – 1:00 PM NAME: _____________________________ YEAR: ___________ DATE:______________________ A. CHB SIZE = 15 X 20 X 40 CHB FOOTING: THICKNESS =0.15 m WIDTH = 0.25 m B. COLUMNS C1 C2 C3 C4 C5 COLUMNS Dimension 0.20 x 0.20 0.20 x 0.20 0.20 x 0.20 0.20 x 0.20 0.20 x 0.20 Length 4m 6m 9m 11 m 9m FOOTINGS WIDTH LENGTH 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 THICKNESS 0.25 0.25 0.25 0.25 0.25 C. PLASTERING BOTH SIDES OF THE FIREWALL : THICKNESS = 16 mm COMPUTE THE FOLLOWING : 1. 2. 3. 4. Quantity of CHB number of pieces (15x20x40) Quantity of CHB mortar ; Cement and Sand Quantity of CHB Footing : Cement, sand and gravel Quantity of aggregates for columns including its footing : Cement, sand and gravel. 5. Quantity of aggregates for plastering work both sides; cement and sand NOTE: Use class B mixture for mortar, CHB footing, Columns and its footing ang plastering works. 2m C5 C4 8m C3 2m C2 C1 3m Column footing line Floor line CHB footing line 1m 4 .0 m 4 .0 m 13 .0 m 2.5 m m 2.5 m m