CIV3284: Concrete Mix Design and Testing Lecturer: Ye Lu Semester 1, 2019 Group 18: Laila Halim (27830500) Athan Giuliani (27835510) Prahn Nicholson (28753968) Benjamin Di Petta (28751647) Mustafa Mirza (27937666) Farhaan Essa (25656805) Due date: 21/05/2019 i Executive Summary The British Method for mix design was adopted to create a 0.02π" batch concrete with a target slump of 120mm and target compressive strength of 35 MPa. This method involved a design for strength through free water to cement ratio, design for workability through free water content, as well as cement and total aggregate content and finally the proportion of fine and coarse aggregates. As the British method assumes that aggregates are in SSD state, further calculations were performed to adjust for the additional water uptake into the aggregate pores. The final mix design had 7.86kg cement, 13.69kg fine aggregate, 22.64kg coarse aggregate and 4.84kg water. The concrete batch was then prepared in the laboratory and tested in accordance with AS1012 parts 3-5 for its properties. This involved being subjected to a slump test, compaction factor test, air content test and checking the density of the concrete. The concrete sample was subsequently made and cured in accordance with AS1012, Part 8 before the sample compressive strength was tested. The concrete was found to have an average slump of 215mm, a density of 2382 kg/m3 , a compacting factor of 0.995, an air content of 1.4% and an ultimate compressive strength of 45 MPa. The density aligned well with expected density of normal strength concrete, however, the slump indicated that the concrete was far too fluid, and the compressive strength was higher than desired which would result in unnecessary expense. Future direction should see the reduction in strength as well as reduction in workability. A decrease in water to cement ratio would achieve a lower slump, however, this would additionally increase the strength of the concrete. Since the current slump does not comply with slump test standards, this must be prioritised and as such a compromise must be reached between the properties of slump and compressive strength. ii Table of contents 1.0 Introduction 1 2.0 Assumptions 2 3.0 Week 2 Mix Design 2 4.0 Moisture Adjustments and Final Mix Proportions 3 5.0 Mix design procedure 4 6.0 Mix design testing 5 6.1 Slump test 5 6.2 Compacting factor test 6 6.3 Air content test 6 6.4 Density of fresh concrete 7 6.5 Compression test 7 7.0 Testing Results 8 7.1 Slump Test 8 7.2 Density of Fresh Concrete 8 7.3 Compacting Factor 8 7.4 Air Content 9 7.5 Compressive Strength 9 7.6 Summary 9 8.0 Observations during mixing 10 9.0 Discussion 11 9.1 Explanation of Test Results 11 10.0 Analysis and alterations to mix design and actual mixing process 14 11.0 Conclusion 16 11.0 References 17 Appendix A - Week 2 Mix Design Calculations 18 iii List of Figures and Tables Table 1. Concrete Desired Properties..................................................................................................... 2 Table 2. Mixture Proportions before adjustment .................................................................................. 3 Table 3. Results of Oven-Drying Aggregates .......................................................................................... 3 Table 4. Proportion of Laboratory trial Batches, Including Weight Adjustment for Aggregate Moisture ................................................................................................................................................................ 4 Table 5. Measured slump for each specimen......................................................................................... 8 Table 6. Density Test Data and Result .................................................................................................... 8 Table 7. Compacting Factor Test Data and Result .................................................................................. 8 Table 8. Failure Loads for Compressive Strength Test ........................................................................... 9 Table 9. Summary of Test Results .......................................................................................................... 9 Table 10. Approximate compressive strength for different aggregate and cement types [2] ............. 18 Table 11. Approximate free-water content (kg/m3) for various maximum aggregate sizes, aggregate types and slump values [2] ................................................................................................................... 19 Table 12. Sieve Analysis Results ........................................................................................................... 21 Figure 1. Abrams cone dimensions [2] ................................................................................................... 5 Figure 2. Illustrative procedure for concrete slump test [3] ................................................................... 5 Figure 3. compaction factor test apparatus [4] ...................................................................................... 6 Figure 4. Compressive Strength v Age for 100% Moist Curing [7]........................................................ 12 Figure 5. Image of concrete cylinder after compressive testing .......................................................... 12 Figure 6. Stress-strain relationship of individual components [7]........................................................ 13 Figure 7. Relationship between curing temperature and % effect compared to 28-day strength [4]. 15 Figure 8. compressive strength versus free water/cement ratio [2].................................................... 18 Figure 9. Relationship between wet density, free-water content and specific gravity [2]................... 20 Figure 10. percentage of aggregate and free-water-cement ratio relationship [2] ............................. 20 iv 1.0 Introduction It is crucial that engineers have an understanding of the underlying principles and procedures involved in creation of the materials that they are working with. As such, this report involves the mix design of a concrete with specified slump and compressive strength, the creation of concrete cylinders using the calculated mix proportions, and finally property testing of the samples. The concrete constituents that will be included in the design include cement, water and aggregates. Cement and water form the paste that bonds the aggregates together. The water-cement ratio (w/c) is a crucial parameter as it has a significant effect on the workability and strength of the mix. Enough water is needed so that the concrete is flowable and able to be manipulated, but too much can be detrimental to strength. The aggregates are inert fillers in concrete, taking up approximately 60-80 percent of the mix due to their significant influence on cost reduction [1]. Aggregate grading, size and shape also has an impact on the strength, dimensional stability and durability [1] of the concrete. It is for these reasons that a mixture of both fine and coarse aggregates will be utilised in the design. After selecting the component materials, it is necessary to conduct theoretical mixture proportioning. Standard procedures are available for calculating the required proportions of each constituent, and the “British Method” (or “DOE Method”) will be utilised in this report. The British Method calculates the following constituents of the mix: β β β β β β β Water/cement ratio Water content Combined Specific Gravity Fineness Modulus Wet concrete density Total aggregate content Percentage of fine aggregates The use of this standard method will allow for an economic design that meets strength and workability requirements. It is not enough, however, to simply calculate the required amounts. It is inevitable that unforeseen laboratory conditions will have an influence on the resultant properties of the concrete, as well as the assumptions made during the theoretical design process. As such, test batches should be created and tested in the laboratory by standard methods. The test methods used in this report include compressive strength testing, the slump cone test for workability, the compacting factor test, a measurement of concrete density and air content. All tests will be conducted in accordance to the specification of AS1012. By completing standard tests, adjustments can be made to the mix design in an iterative manner until the desired properties are obtained and the engineer can be confident that the concrete will be satisfactory in service. This report will detail the mix proportion calculations for a 0.02π" batch of concrete with a slump of 120mm, and compressive strength of 35 MPa, as well as results from laboratory mixing and testing, comparisons between the theoretical and actual properties and suggestions for future mix improvements. 1 2.0 Assumptions There were several key assumptions that were made in order to conduct the concrete mix design, and these are detailed below: β β β β β β The selected cement type and type of coarse aggregate are assumed as GP (AS3972) and crushed aggregate consisting 14 mm maximum particle size of Granite material. The state of aggregate in the concrete mix was under the saturated and surface dry (SSD) condition until the adjustment is made. Adding chemical admixtures are negligible in concrete mix design. They are not considered in this report. The coarse aggregates were used as clean, hard, strong and chemically inert with unknown shape and surface texture. Specific gravity of fine aggregates, coarse aggregates and Portland GP cement are 2.65, 2.95 and 3.15 respectively. The combined SG of the aggregates in the mix design assumes a 50/50 proportion of fine and coarse aggregate by weight. 3.0 Week 2 Mix Design The initial Mix Design completed in week 2 followed the British Method. A summary of the parameters found during the mix design process as well as the mix proportions are tabulated below. For full calculations see Appendix A. Table 1. Concrete Desired Properties Desired Compressive strength 35 MPa Desired Slump 120mm Water to Cement Ratio Combined Specific Gravity Fineness Modulus Cement Content 0.575 2.8 2.104 391.3 kg/m3 Water Content 225 kg/m3 Wet Density 2450 kg/m3 Total Aggregate Content Percentage of Fine Aggregate 1833.7kg/m3 37.8 % 2 Table 2. Mixture Proportions before adjustment Mass for 1 m3 mixture (kg) Material Free-Water Mass 0.02 m3 (kg) 225 4.50 Cement 393.1 7.86 Fine Aggregate 693.1 13.86 Coarse Aggregate 1140.6 22.81 Total Mass (kg) 2451.8 49.04 4.0 Moisture Adjustments and Final Mix Proportions The British Method utilised for mix design is based on the assumption that the aggregates are in saturated and surface dry (SSD) conditions. A correction needs to be made to account for the actual moisture conditions of the aggregate. The process to determine the moisture content of the aggregates is done through oven drying them and then attributing the difference in mass as water. To ensure that all the pores are empty, the aggregates are oven-dried at 105OC for 24 hours until they maintain a constant weight. Before and after readings are recorded, the moisture content is calculated, and the values are recorded below. Table 3. Results of Oven-Drying Aggregates Type Mass Container (g) Container and aggregate wet (g) Mass wet aggregate (g) Container and aggregate dry (g) m.c. % Coarse 48.1 460.5 412.4 458.6 0.458 Fine 47.5 570.6 523.1 569.2 0.264 π. π. % = (ππ€ππ‘ − ππππ¦)/(ππ€ππ‘ − πππππ‘πππππ) ∗ 100 πΆππππ π π. π. % = (460.5 − 458.6)/(412.4) ∗ 100 = 0.458 πΉπππ π. π. % = (570.6 − 569.2)/(523.1) ∗ 100 = 0.264 The values in column 2 of table 4 are calculated values for the amount of aggregate required assuming SSD condition. From this, the actual weight is adjusted to account for the moisture that is absorbed by the aggregates. The negative values in column 6 indicate the aggregates are partially dry, which is expected as they are stored indoors with exposure to drafts. To get them to SSD condition, the aggregates will absorb some of the water from the mixture, thus there needs to be more water added so that w/c ratio is not lowered (which would result in a lower rate of hydration and less workability). 3 Table 4. Proportion of Laboratory trial Batches, Including Weight Adjustment for Aggregate Moisture 1. Material Coarse Aggregate (CA) 2. 3. 4. 5. 6. 7. Calculated Trial Batch Absorption Moisture Free Trial batch weight, SSD Weight, SSD of aggregate, content of moisture weight in for 1m3 (kg) ac aggregate, on moisture 3 (kg/m ) (%) mc, (%) aggregate, condition for Mca mixing (kg) (kg) 1140.6 22.81 1.2 0.458 - 0.169 22.641 Fine Aggregate (FA) Cement (C) 693.1 13.86 1.5 0.264 - 0.171 13.689 393.1 7.86 7.86 Water (W) 225 4.5 4.84 Total Weight 2451.8 49.04 49.03 The final column in the table lists the final adjusted weights of the different materials required to make the desired concrete cylinders. 5.0 Mix design procedure The preparation of the concrete was done under supervision to ensure it was carried out as laid out in the Australian Standards, AS1012. As the calculations for the elements had been completed, it was just to ensure that they were mixed correctly. 1. Firstly, both aggregates and about β of the water were added to the mixer which was then operated for 30 seconds to wet the aggregate. 2. Secondly, the cement powder was added slowly to ensure no dust was produced when the mixer continued. The remainder of the water was slowly added within the next 2 minutes. 3. The mixer was then stopped for another 2 minutes and the mix was allowed to rest to ensure hydration occurred. 4. The concrete was mixed for a further 2 minutes to create the final product. 4 6.0 Mix design testing 6.1 Slump test The slump test was conducted according to AS1012 part 3. An inverted cone known as an “Abrams cone” was utilised with dimensions given in figure 1 below. Figure 1. Abrams cone dimensions [2] A fresh layer of concrete was placed in the cone until it was approximately one third filled. This layer was then compacted using a steel rod with 25 blows. A second layer was subsequently added filling the cone up to two thirds of its capacity and only the second layer was compacted with the steel rod and the same number of blows. The cone was then filled up to maximum capacity and compacted in the top one third of the cone using the steel rod and the same number of blows. After the cone was filled with concrete, the top of the cone was levelled using the steel rod. The cone was then gently lifted vertically over a 3 second period to allow the concrete to slump evenly and also reduce the chances of the concrete becoming a work hazard. The cone was then turned upside down and placed next to the concrete with the rod laid on top, and the slump was measured from top of the concrete to the rod. This process is illustrated in figure 2 below. Figure 2. Illustrative procedure for concrete slump test [3] 5 6.2 Compacting factor test The compacting factor test was carried out in accordance with AS1012 Part 3. The testing apparatus is shown in figure 3 below. Figure 3. compaction factor test apparatus [4] In order to carry the compacting factor test, the apparatus was first cleaned. The cylinder was then weighed, and the mass recorded. Following the mass measurement, the cylinder was placed directly under the hoppers and the hopper doors were secured shut. Fresh concrete was carefully poured into the top hopper up to capacity and the top was levelled off. The trap door of the first hopper was opened allowing the concrete to fall into the second hopper. The trap door of the second hopper was then opened allowing the concrete to flow into the cylinder. The impact upon hitting the cylinder compacts the concrete. The concrete was levelled at the top of the cylinder, all excess concrete on the edges of the cylinder was wiped off and the cylinder was again weighed. The initial mass of the cylinder was subtracted from this value and this was considered as the mass of partially compacted concrete. The cylinder was again cleaned and weighed. Fresh concrete was then poured into the cylinder in layers and vibrated until no bubbles appeared on the surface. Any excess concrete was wiped off and the cylinder was reweighed. The initial mass of the cylinder was subtracted from this value to give the mass of fully compacted concrete. The compacting factor was found by dividing the mass of the partially compacted concrete by the mass of the fully compacted concrete. 6.3 Air content test The air content test was conducted as per AS1012 Part 4. Fresh concrete was poured into a container to one third capacity of the container and compacted by vibration. This process was repeated for the next third and then the full capacity of the container. The excess from the top was cleared and the top of the concrete was levelled out. The edges of the container were thoroughly cleaned and wiped with a damp cloth to ensure the rubber seal is effective. A calibrated air entrainment meter was clamped down onto the bowl of concrete. The air entrainment meter contained two valves which were used to remove the air. This was done by pushing water through the left valve until the water had displaced all the air between the lid and the concrete surface, causing water to be pushed out of the right valve. The air valves were then shut. The hand pump at the top of the air lid was then used to pressurise a separate container. The pressure was then released to allow 6 air to flow from the pressure container into the test container. This then provided a calibrated value as a percentage. 6.4 Density of fresh concrete The testing of fresh concrete density was undertaken in accordance with AS1012 Part 5. A metal bowl was cleaned and filled with water to the brim and the mass of the container plus the water was recorded. The bowl was then emptied and wiped clean. Next, the bowl was filled with fresh concrete to one third capacity and compacted with a vibro-compactor until bubbling ceased. This process was then repeated for two thirds full and maximum capacity. The bowl with the compacted concrete was then weighed and the mass was recorded for density calculations. As the density of water is known, the volume of the bowl could be found. The density of the fresh concrete was then calculated as the mass of compacted concrete and bowl minus the mass of the bowl, divided by the volume of the bowl. 6.5 Compression test Three standard concrete test cylinders of 100mm diameter and 200mm length (AS1012.8 section 5) were used to make the specimens. Each cylinder was filled to approximately the one third mark and placed on the vibro-compactor. When sufficient compaction had occurred (but not enough to cause segregation), the vibration was stopped. This process was repeated until the cylinders were filled. The tops of the cylinders were then smoothed, covered with plastic and allowed to rest for 24hrs in their respective moulds to gain strength. After 24hrs the cylinders were removed from their moulds, marked/numbered for the group and were submerged in a curing tank filled with lime-saturate at 23 ± 2°πΆ for a period of 40 days. The specimens were then removed from the curing tank and allowed to air dry for a full day before testing. Unfortunately, due to laboratory timetabling, the standard curing time of 28 days specified in AS1012 Part 8 was unable to be followed. On the day of compression testing, the specimens were capped with a material containing mixtures of sulphur as per AS1012.9 section 6.2. It was ensured that the ends of the specimens were parallel within 2 degrees as they were to be in contact with the platens of the compressive testing machine. The concrete specimens were loaded into the compressive testing machine and the top plate was lowered so as to perform uniform loading on the specimen. Each sample was loaded to failure and the failure loads were recorded. 7 7.0 Testing Results 7.1 Slump Test Table 5. Measured slump for each specimen Test Slump (mm) Test 1 215 Test 2 215 Average 215 7.2 Density of Fresh Concrete π«ππππππ = π΄πππ/π½πππππ (π) As water has a known density of 1000ππ/ππ , the volume of the container can first be found. π½πππππ = (ππ. ππ − π. ππ)/ππππ = π. ππ ∗ ππ_π With a known volume, the density of the concrete can be calculated as per Equation 1. π«ππππππ = (ππ. ππ − π. ππ)/(π. ππ ∗ ππ_π ) π«ππππππ = ππππ ππ/ππ Table 6. Density Test Data and Result Weight Container (kg) 3.84 Weight Container + Water (kg) 10.90 Weight Container + Concrete (kg) Density (kg/m3) 20.66 2382 7.3 Compacting Factor The compaction factor can be calculated as a proportion of the fully compacted concrete, as per equation 2 below. πͺπππππππππ ππππππ = π − π΄πππ πͺπππππππ / π΄πππ πππππ πͺππππππππ πͺπππππππ πͺπππππππππ ππππππ = π − (ππ. ππ − ππ. π)/(ππ. π − ππ. π) πͺπππππππππ ππππππ = π. πππ (π) Table 7. Compacting Factor Test Data and Result Weight of Container (kg) 11.4 Weight of Container + Concrete (kg) 23.34 Weight of Container + Fully Compacted Concrete (kg) 23.4 Compacting Factor 99.5% 8 7.4 Air Content As in the method of testing, the air content can be read directly off the gauge. For the concrete mix, the gauge gave a value of 1.4%. 7.5 Compressive Strength Once the three cylinders had cured for 40 days, they were taken out of the bath and left to dry overnight. The results obtained from compression test are shown in table 8 below. Table 8. Failure Loads for Compressive Strength Test Load (kN) Cylinder 1 Cylinder 2 Cylinder 3 Average 370 370 310 350 7.6 Summary Table 9. Summary of Test Results Test Type Slump Density Compacting Factor Air Content Compressive Strength Overall Result Achieved 215 mm 2382 kg/m3 0.995 1.4 % 350 kN = 45 MPa 9 8.0 Observations during mixing It is essential that fresh concrete has sufficient workability to allow for mixing, manipulation, placement, transportation and finishing. The concrete mix was observed to have a high water content and this allowed for good workability. The high w/c was evident by the ease at which the fresh concrete could be scooped and lifted from the mixer, as well as the tendency for the mixture to drip from the scoop during transportation to the slump cones and standard cylinders. The high fluidity and lubrication that was observed during scooping made it abundantly clear that a high slump would be achieved. This high water content was confirmed during the slump test as the slump was recorded at 215mm. Once the cone was lifted, the fresh concrete had no resemblance to the shape of the cone it was contained in. With the slump being greater than 150mm, it was classified as a total collapse. Segregation is the separation of constituents of the concrete mix. This process can have detrimental effects on the concrete, creating a non-homogeneous mixture with non-uniform properties. The high w/c and likely excess of water present in the concrete mix increased the likelihood of segregation occurring. This was a concern for the compaction of the fresh concrete during the creation of the concrete cylinders for the compression test. During vibration, it was observed that the coarse aggregates had a tendency to drop and the cement paste a tendency to rise quite quickly. As a result, additional care was taken during compaction by keeping the frequency of vibration at a moderate level and ensuring that vibration was not performed for too long. 10 9.0 Discussion 9.1 Explanation of Test Results The properties of the concrete mix found through testing were not satisfactory, which can be expected for mix trials. Both the experimental slump and compressive strength varied significantly with expected targets. The target slump of 120mm indicates a workable concrete that still held its general shape, however this was exceeded significantly. The actual slump of 215mm results in a concrete that is much too workable which could lead to problems such as segregation, excessive bleeding and lower strength. The higher than expected slump can certainly be attributed to the fact that, even though supervised, the concrete mixing and testing was being performed by students for the first time which could have led to inaccuracies from lack of experience. These human errors could have included prodding the concrete too much/with too much force that segregation of the mix could have occurred, or not prodding each layer consistently. The difference in slump suggests that too much water was added to the concrete mix. The slump of concrete is directly proportional to its water content, and therefore too much water will lead to a large slump. This could possibly be due to inaccuracies involved in measuring how much water the aggregates would absorb to be in SSD condition, or the aggregates not having enough time to completely reach saturated state before slump testing [5], leaving excess water in the mix. A slump of greater than 150mm is considered a total collapse failure, suggesting that the concrete is not suitable to be used for construction purposes. Therefore, the result obtained indicates an undesirable mix. The density of concrete achieved by the mix design was 2382 kg/m3 which is within the range for normal strength concrete of 2000-2600 kg/m3 [6]. This indicates satisfactory testing performance as expected from a basic level test. The compaction factor test was a more practical test of workability, by reflecting how the concrete is placed during construction. The compacting factor of 0.995 that was obtained from testing is a very high value, given that typical concrete has a range of compaction factors from approximately 0.6<CF<1 [2]. This value for compaction factor concurs with the slump of 215mm, and further suggests that there was too much water added to the concrete mix. The actual compressive strength of the concrete, 45 MPa, exceeded the target strength of 35 MPa despite having a very high workability. Concrete is usually tested 28 days after it is mixed as by this stage is has almost reach full strength. AS-3600 specifies the characteristic compressive strength of concrete to be at 28 days, hence the calculations are done based on this timeline. Our concrete was tested after a period of 41 days (40 of which in the curing tank), which means that concrete will have gained some additional strength in that time period. The influence of curing time on compressive strength is shown in figure 4 below. It can be seen that there is roughly an 8% increase in strength for 40 days in the tank, hence one would expect a value of 38 MPa for the mix designed in this report. Another factor that could have caused the unexpectedly high strength is the level of compaction. Despite, compacting each layer exactly 25 times, the degree of compaction may have been better than expected, resulting in less air voids and a higher strength. 11 Figure 4. Compressive Strength v Age for 100% Moist Curing [7] The additional 10 MPa of strength achieved for the concrete would be inappropriate in industry as the concrete will have a higher than necessary cost. As such, the concrete mix should be adjusted to reduce the strength, and this will be discussed in section 10. Figure 5. Image of concrete cylinder after compressive testing Figure y shows one of three of the cylinders after being subject to the compressive test. Based on figure 5 failure can be seen to occur partially in the aggregates as well as the concrete paste. As the interior of the concrete specimen could not be seen during testing, it is difficult to determine with certainty whether the aggregates or the cement paste failed first. Considering the generally understood behaviour of aggregates and cement paste to applied stress as shown in figure 6 below, it is likely that the cement paste was the first to fail. 12 Figure 6. Stress-strain relationship of individual components [7] Ultimately, the most common problem amongst the tests is the workability being too high, which links to the water content. The water content could have been too high for several reasons. Firstly, calculations could have been performed incorrectly during the initial mix design or in the adjustment. Secondly, there may have been too much water directly added to the mixture through lack of care. Finally, the water content of the aggregates could have actually been greater than calculated from the oven-dry test, so they did not absorb as much moisture as calculated, or worse, contained free water which added to the w/c ratio of the mixture. 13 10.0 Analysis and alterations to mix design and actual mixing process If another mix trial was to be conducted in the laboratory there are a variety of amendments that could be made to the mixture proportions, resulting either due to failures in the previous design or any improvements that could be realised. These alterations will be outlined below within the context of analysis into why such an outcome occurred. Firstly, the concrete mix produced in the laboratory had a much larger slump than was designed being approximately 80% higher than designed for. As such the concrete had far too much workability with the simple amendment being to reduce the water to cement ratio of the mix. Yet the compressive strength achieved was also 29% greater than the target strength of the concrete mix, although this may have been affected by the sample being cured for a period longer than was accounted for in the design stage of the project. As such any efforts to improve the slump of the material involving a reduction in the water to cement ratio would also likely result in further discrepancies between the actual and targeted concrete compressive strength. Hence, if the mixture proportions were to be further adjusted to have a lower water to cement ratio, consideration would have to be given to determining an optimal amount that reduces workability to an acceptable level without further altering the achieved compressive strength. Aside from altering the water to cement ratio to improve the concrete slump test closer to the desired workability, smaller aggregate sizes could be utilised than initially proposed. With smaller aggregate sizes there is a corresponding increase in the total surface area of the aggregates leading to a sparser coating of cement paste and as such a reduction in the workability of the concrete. Although this is once again offset by increased concrete compressive strength due to the greater interlocking of particles. Another alternative concerning the aggregates is to use a type with sharp corners which will tend to interfere with one another as concrete flows, which again will result in reduced slump and as such workability. The sample had a target sump of 120mm, but the sample produced greatly exceeded this amount having a slump of 215mm. The discrepancy between the target and actual slump was extremely large and may have occurred due to a variety of reasons including the mix design process as discussed above, with the water to cement ratio and aggregate size as well as shape potentially contributing to a greater than desired slump. Other potential causes of discrepancy beyond the mix design may have been the unintentional incorrect carrying out of the test. The standards deal in approximate amounts with the cone meant to be filled in 3 layers each with approximately one third of the cone volume, with each of these layers then rodded 25 times uniformly over the cross section. As such poor layering of the concrete and inconsistent rodding may have contributed slightly to the unexpected slump results. Ultimately though it is unlikely these systematic errors were large factors in the slump achieved and correcting for such inconsistencies in testing is not feasible as the purpose of the slump test is a fast, on site test, render mechanising the process impractical. Despite this, all future test mixes should be taken in ensuring the test is carried out in accordance with AS1012, Part 3 [8]. The concrete sample was found to have a compressive strength which greatly exceeded the design goal of 35 MPa. This outcome is unexpected when observed in context with the results in the preceding workability tests. With the concrete having greater strength and greater workability than designed for this result was not predicted as greater strength is usually obtained at the expense of the concrete workability. As discussed in previous sections, amending either of these issues in the mix is likely to result in the other property of the concrete being further displaced from the design goal. There are a variety of reasons this may have occurred. Firstly, concrete compressive strength is usually measured after 28 days, yet the samples were tested after 41 days. As they were in the curing tank for almost all of this time, a reduction in water loss due to evaporation leads to an efficient hydration process, further increasing their strength [9]. 14 For future mixes, it is vital the process be carried out properly and in accordance with the relevant Australian standards. In spite of this being a potential reason for the conflicting results it would still have been expected that for such a large slump that concrete strength would have been severely diminished so other factors must also have affected the strength of the concrete without reducing its workability. Other such factors relate to the curing and temperature. In relation to the curing process, the ideal curing temperature is 230C [4]. The error margin in the curing tank was 2 degrees. The effect of the difference in temperate is shown in figure 7 below, where short term effects outweigh the long term. For the first few days, the difference could alter the resultant strength by up to 5%, however as time reaches 30 days and beyond the effect of temperature is negligible. With such considerations in mind, future test samples should be cured for the correct amount of time, and if possible, in an environment with a temperate above 130C in order to make the curing effects negligible to strength. Figure 7. Relationship between curing temperature and % effect compared to 28-day strength [4]. Amendments relating to the durability of the concrete have not been considered as testing of the sample could not reveal any necessary changes to improve this aspect of the proposed concrete mix. The density achieved is expected for normal strength concrete. If future mixes require a higher or lower density than adjustment of the type of aggregate would be required. Ultra -lightweight concrete for instance utilises aggregates with a low density of < 500 kg/m3 [6]. As previously noted, the concrete displayed a compressive strength result greater than the target strength. Whilst it is unconventional to attempt to reduce the compressive strength of the concrete in order to comply with the design specifications of the project this has been briefly considered. As workability and strength are inversely related, achieving this improved workability has been prioritised due to its clear failure to meet not only design but slump test standards. As a result, any amendments to the concrete mix outlined above would be adopted, but not without consideration for attempting to strike a balance between rectifying the two discrepancies in workability and strength. When analysing the performance of the concrete overall it appears the most critical downfall of the mix design proposed is its failure to meet maximum workability requirements, as well as exceeding the design strength. As such the concrete mix failed to meet design specifications and further revisions to the concrete mix design must be made to achieve a sample that is in line with the project specifications. 15 11.0 Conclusion The project concrete mix design representing a 0.02m3 volume of concrete was conducted over two lab sessions, once for mixing and fresh concrete test and the other for compression test. The British method was adopted and then adjusted to target a specified slump of 120mm and compressive strength of 35 MPa. The final mixing proportions of batch concrete comprised 7.86 kg cement content, 13.69kg of fine aggregates, 22.64 of coarse aggregates and 4.84kg of water that were estimated during the lab experiment. Considering all the assumptions of saturated and surface dry condition and relevant information provided, the obtained result for slump test was expectedly higher than the target value, a percentage error of 79.2% between the target and actual height in slump [10]. Experimental errors likely influenced the slump, as well as aggregates possibly not reaching SSD state, meaning that the workability of concrete increased through a greater amount of free-water in mixtures. Additionally, the compressive strength testing trial was performed following the moist-curing process, and the obtained strength was again higher than the target strength (with 28.6% percentage error [10]). This higher than expected result was likely due to the compressive test being conducted after 41 days, rather than the 28 days recommended by Australian Standard AS1012. In conclusion, it is necessary to adjust the mix design in order to better suit the project requirements and ensure that the concrete has a workability that is compliant with industry standards and a lower compressive strength to ensure cost efficiency. This could be achieved by adjusting the water-cement ratio, or size and shape of the aggregates. It is understood that a compromise must be made between the workability and the strength as they are inversely proportional, and it is suggested that the workability requirements should be prioritised. The results from the concrete testing additionally highlight the importance of following the exact specifications within AS1012 during the preparation and testing processes, as well as having experienced personnel conduct these processes to reduce the margin for human errors. 16 11.0 References [1] P. Mehta, P. Monteiro (2014). Concrete: Microstructure, Properties, and Materials, Fourth Edition. McGraw-Hill Education. [2] F. Azhari (2019). Concrete Mix Design Lecture. Monash University. [3] The Constructor. (2019). Concrete Slump Test for Workability -Procedure and Results. [online] Available at: https://theconstructor.org/concrete/concrete-slump-test/1558/ [Accessed 20 May 2019]. [4] The Constructor. (2019). Compaction Factor Test for Concrete Workability - Method and Procedure. [online] Available at: https://theconstructor.org/concrete/compaction-factortest/1565/ [Accessed 20 May 2019]. [5] R. Dhir et al. (2019). Fresh Concrete Properties. Sustainable Construction Materials. [6] F. Azhari (2019). Concrete Aggregates Lecture. Monash University [7] Azhari, F (2019). Properties of Hardened Concrete Lecture. Monash University [8] Australian standards, AS1012.3.1, 2014, Methods of testing concrete - Determination of properties related to the consistency of concrete - Slump test [9] Australian standards, AS1012.8.1, 2014, Methods of testing concrete - Method for making and curing concrete - Compression and indirect tensile test specimens [10] C. Foundation, "Percent Error", CK-12 Foundation, 2019. [Online]. Available: https://www.ck12.org/chemistry/percent-error/lesson/Percent-Error-CHEM/. [Accessed: 21May- 2019]. 17 Appendix A - Week 2 Mix Design Calculations Stage 1 - Design for Strength The water/cement ratio is found through its relationship with the compressive strength over time. First estimating a w/c ratio of 0.5 as per convention and utilising Table 10, a value of 45 MPa after 28 days can be found for General Purpose Crushed Cement. Table 10. Approximate compressive strength for different aggregate and cement types [2] As shown in Figure 8, the second curve is then used to find the w/c ratio of the same cement that has a 35 MPa strength after 28 days. The w/c is estimated to be 0.575. Figure 8. compressive strength versus free water/cement ratio [2] Stage 2 - Design for Workability After the aggregate has absorbed enough water to become a saturated and surface dry condition, the leftover water is classified as free-water. It is used in the process of cement hydration - to produce C-S-H - and workability. To find the free-water content, Table 11 is used. 18 Table 11. Approximate free-water content (kg/m3) for various maximum aggregate sizes, aggregate types and slump values [2] As shown in table 11, only free-water content values are supplied for maximum aggregate sizes of 10mm and 20mm and thus linear interpolation is required. With a maximum aggregate size of 14mm, that being crushed and a slump of 120mm, the approximate free-water is between 210 and 235 kg/m3 . Linearly interpolating these values gives a free-water content of 225 kg/m3 as shown in the calculation below. ππππ π€ππ‘ππ ππππ‘πππ‘ = 235 + 210 − 235 (14 − 10) = 225 ππ π_" 20 − 10 Stage 3 - Cement Content To find the cement content, equation 3 is utilised. πΆπππππ‘ πΆπππ‘πππ‘ = lmnn opqnm rstqntq o ⁄r (3) πΆπππππ‘ πΆπππ‘πππ‘ = 225 ÷ (0.575) = 391.3 ππ π_" Stage 4 - Determine Total Aggregate Content To calculate the total aggregate amount, Equation 4 was utilised. πππ‘ππ π΄πππππππ‘π πΆπππ‘πππ‘ = πππ‘ π·πππ ππ‘π¦ − πΆπππππ‘ ππππ‘πππ‘ − πΉπππ π€ππ‘ππ ππππ‘πππ‘ (4) From Stages 2 and 3, the Cement content is 391.3 kg/m3 and Free-Water Content is 225 kg/m3. It is known that the specific gravity of coarse aggregates is 2.95 and fine aggregates is 2.65. Assuming a 50/50 ratio of course and fine aggregate, the specific gravity of the total aggregate can be calculated, ππΊ = 2.95 + 2.65 = 2.8 2 19 Figure 9. Relationship between wet density, free-water content and specific gravity [2] Reading off Figure 9, a value of 2450 kg/m3 for the Wet Density is found, and the total aggregate content can be calculated. πππ‘ππ π΄πππππππ‘π πΆπππ‘πππ‘ = 2450 − 225 − 391.3 = 1833.7 ππ π_~ Stage 5 - Proportion of Fine/Coarse Aggregate The proportion of fine aggregate used in the cement mixture is dependent on w/c ratio, maximum aggregate size, slump and fineness modulus. The relationships are shown on the graphs of Figure 10. Figure 10. percentage of aggregate and free-water-cement ratio relationship [2] 20 The only unknown to be worked out is the fineness modulus, which is determined based on the sieve analysis, for which the data is given. The sum of the cumulative percentage retained is divided by 100 which results in a Fineness Modulus of 2.104. These results are shown in table 4 below. Table 12. Sieve Analysis Results Sieve Size (mm) % Retained Cumulative % 4.75 0.6 0.6 2.96 3.2 3.8 1.18 13.2 17 0.6 21.6 38.6 0.3 22.2 60.8 0.15 28.8 89.6 0.075 9.4 - <0.075 1 - SUM 210.4 Now, the Figure 10 graphs can be utilised. For a maximum aggregate size of 10mm the percentage of fine aggregate is found to be 41% and for 20mm the fine aggregate percentage is 33%. These two values are then interpolated for the situational maximum aggregate size of 14mm to find a percentage of fine aggregate of 37.8% as shown below. πππππππ‘πππ ππππ ππππππππ‘π = 33 + 33 − 41 (14 − 10) = 37.8% 20 − 10 This leaves 62.2% of the total aggregate mass to be coarse. Thus, for a volume of 1m3, there would be 391.3kg cement, 693.1kg of fine aggregate, 1140.6 kg of coarse aggregate and 225kg of free-water. In the lab, there the batch volume will be 0.02m3. This would require 7.86kg cement, 13.86kg of fine aggregate, 22.81 kg of coarse aggregate and 4.50kg of free-water. 21