Unit-10 “ NGL Extraction “ Objective • Unit 10 “ NGL Extraction Unit “ Objective : To Separate NGL from Dry feed gas in order to perform further processing in Fractionation unit to get the final products • Propane • LPG • DNG Sales Gas ( C1, C2) Dry Feed Gas ( C1, C2 , C3 , C4 , C5+) Unit 10 NGL (C3 , C4 , C5+) Selected process for NGL Extraction • ORTLOFF IOR “Improved Overhead Recycle Process” was selected for the NGL Extraction Section, to guarantee optimum recovery (Propane in excess of 98% and 100% of C4 plus) of NGL Liquids, in addition to the future, simple process conversion to “Gas Sub-Cooled Process”, to recover not less than 73% of Ethane. ORTLOFF IOR Process • Ortloff’s IOR process is a two column design, incorporating an Absorber and a Demethanizer. The Demethanizer overhead vapor is cooled and partially condensed, with the resulting liquids providing reflux for both columns. The cooling necessary to partially condense the Demethanizer overhead vapor is provided by Absorber overhead vapors. The two columns typically operate at about the same pressure, with pumps providing the energy required for the liquids to transfer between the columns. ORTLOFF IOR Process • The required cooling for the feed gas is carried out utilizing the cold residue gas from the top of the absorber using the gas/gas exchanger. Also utilizing the cold liquids from the bottom of the low temperature separator and the absorber bottom liquids, finally using the expander to reach the final required temperature. • The core of the process is utilizing the Demethanizer off gas after cooling and condensing to provide reflux to the absorber, where it will contact, rectify and absorb the propane plus component from the expander vapor interring the absorber. ORTLOFF IOR Process Guarantee • The plant is guaranteed to recover minimum of 96.5% of the available propane and essentially 100% of the butanes and heavier components when processing an inlet gas rate of 1350 MMSCFD of the design composition feed gas. • The IOR process will produce a deethanized NGL product meeting the desired product Specification, and about 1335 MMSCFD of sales gas product. The plant is also designed for easy conversion to the Gas Sub-cooled Process (GSP) for recovery of ethane product in the future. NGL Extraction Process Description • De-mercurized gas stream will split & pre-cool versus warming residue gas stream in the G/G PFHE (Unit 10-E-01) and liquid bottom streams (expander feed separator & absorber) in the G/L PFHE (Unit 10-E-02) respectively. 10-E-03 10-E-01 0-50% IN 79 Bar 30 C FV FIC 02 -26 C FY 01C SDV 10-V-01 FV Mercury Removal FY 02 -76 C FY 01D 50-100% IN 10-E-02 NGL Extraction Process Description • Pre-cooled gas will be flashed into Expander Feed Separator (Unit 10-V-01), to separate any condensed liquids , These liquids in the source of the cooling duty for feed gas in G/L (10E-02) “PASS B” 10-E-03 10-E-01 0-50% IN 79 Bar 30 C -66 C -35 C FV FIC 02 -26 C FY 01C SDV 10-V-01 LIC 15 Mercury Removal SDV FY 01D -55 C FV LV FY 02 -76 C Liquids to pass B 50-100% IN 10-E-02 NGL Extraction Process Description • Gas will then expand through Turbo-Expanders (Unit 10 U01A/B), with further cooling to -74 C, Two J.T. valves are provided in parallel to Expanders, to maintain plant in operation during Expanders trip & facilitate plant start-up. 10-E-03 10-E-01 0-50% IN FY 01C 79 Bar 30 C -26 C -66 C -35 C FV FIC 02 SDV SDV 10-V-01 LIC 15 Mercury Removal Expanders Fault Trip 10-U-01A/B Expanders Guide Vanes -74 C PV-12A HIC 02/04 PY 12B PIC 12A SP < 5 psi LV PV-12B FY 01D -55 C FV FY 02 SDV -76 C 50-100% IN 10-E-02 PIC 12B NGL Extraction Process Description • The Demethanizer (Unit 10-C-01) overhead vapor will cool versus warming residue gas stream in the G/G PFHE (Unit 10E-03), and will be flashed to Absorber (Unit 10-C-02) top where accumulated condensed liquids are placed in chimney tray 36 Bar -79 C SDV 10-E-03 36 Bar -34 C -74 C TV 10-E-01 SDV 0-50% IN FY 01C 79 Bar 30 C -26 C -66 C -35 C FV FIC 02 TIC 15 SDV 10-V-01 LIC 15 Mercury Removal 36 Bar 27 C SDV Expanders Fault Trip 10-U-01A/B Expanders Guide Vanes -74 C PV-12A HIC 02/04 PY 12B PIC 12A SP < 5 psi LV PV-12B FY 01D -55 C FV FY 02 SDV -76 C 50-100% IN 10-E-02 PIC 12B 10-C-02 10-C-02 10-C-01 NGL Extraction Process Description • Expanded liquids will feed the absorber tower, accumulated condensed liquids will be re-circulated by Reflux Pumps (Unit 10-P-01A/B) to reflux both Absorber & Demethanizer Columns, to minimize propane & heavier component vaporizing out of columns. SDV 10-E-03 36 Bar -34 C 36 Bar -79 C -74 C -74 C TV 10-E-01 SDV 0-50% IN FY 01C 79 Bar 30 C -26 C -66 C -35 C FV FIC 02 TIC 15 SDV 10-V-01 LIC 15 Mercury Removal Expanders Fault Trip -74 C 10-U-01A/B Expanders Guide Vanes -74 C PV-12A HIC 02/04 PY 12B PIC 12A SP < 5 psi LV -55 C FY 01D SDV PV-12B FV FY 02 -76 C 50-100% IN 10-E-02 10-P-01A/B 36 Bar 27 C SDV PIC 12B 10-C-02 10-C-02 10-C-01 NGL Extraction Process Description • All generated power from Both Expanders 10-U-01 A/B are utilized to compress residue gas through the Expander Compressors (Unit 10-K-01A/B) to Residue Gas Compressors. SDV 10-E-03 36 Bar -34 C 36 Bar -79 C -74 C -74 C TV 10-E-01 SDV 0-50% IN FY 01C 79 Bar 30 C -26 C -66 C -35 C FV FIC 02 TIC 15 SDV 10-V-01 LIC 15 Mercury Removal Expanders Fault Trip -74 C 10-U-01A/B 10-K-01A/B Expanders Guide Vanes -74 C PV-12A HIC 02/04 PY 12B PIC 12A SP < 5 psi LV -55 C FY 01D SDV PV-12B FV FY 02 10-P-01A/B 36 Bar 27 C SDV 10-C-02 10-C-02 10-C-01 PIC 12B -76 C 50-100% IN 10-E-02 Residue Gas Compressors NGL Extraction Process Description • Expander Feed Separator & Absorber liquids will provide the duty of inlet gas pre cooling in G/L PFHE “Pass B and Pass C respectively “ , after being partially vaporized downstream the G/L PFHE, both streams will feed the Demethanizer. SDV 10-E-03 36 Bar -34 C 36 Bar -79 C -74 C -74 C TV 10-E-01 SDV 0-50% IN FY 01C 79 Bar 30 C -35 C -26 C -66 C FV FIC 02 TIC 15 SDV LIC 15 Mercury Removal 10-V-01 Expanders Fault Trip 10-P-01A/B 36 Bar 27 C SDV -36 C -74 C 10-K-01A/B 10-U-01A/B Expanders Guide Vanes 29.5 C -74 C PV-12A HIC 02/04 PIC 12A PY 12B 10-C-02 10-C-02 SP < 5 psi FY 02 -55 C FV LV -76 C PIC 12B FV-18 FY 01D TV 10-E-02 SDV LV FIC 18 50-100% IN 10-C-01 SDV PV-12B 66-100% IN TY 12B LIC 08 -76 C New By passes “ G/L cold box passes 10-P-02A/Bmodifications “ 0-66% IN TIC 12 TY 12B Residue Gas Compressors NGL Extraction Process Description • Demethanizer Re-boiler (10-E-04) generate sufficient hot vapors to strip ethane and lighter components from the liquid flowing down the Demethanizer Column. to maintain C2/C3 Liq. Vol. % ratio of NGL liquids stream not to exceed 1.0%. SDV 10-E-03 36 Bar -34 C 36 Bar -79 C -74 C -74 C TV 10-E-01 SDV 0-50% IN FY 01C 79 Bar 30 C -35 C -26 C -66 C FV FIC 02 TIC 15 SDV LIC 15 Mercury Removal 10-V-01 Expanders Fault Trip 10-P-01A/B 36 Bar 27 C SDV -36 C -74 C 10-K-01A/B 10-U-01A/B Expanders Guide Vanes 29.5 C -74 C PV-12A HIC 02/04 10-C-02 10-C-02 SP < 5 psi FY 02 -55 C FV LV -76 C PIC 12B FV-18 FY 01D TV 10-E-02 SDV 10-C-01 66-100% IN TY 12B Hot Oil 10-E-04 LIC 04 24 Bar 150 C FV 92.7 C 10-P-02A/B 0-66% IN TIC 12 -76 C LV FIC 18 50-100% IN LIC 08 SDV PV-12B 24 Bar 200 C SDV PIC 12A PY 12B AIC 01 TIC 27 SDV C2/C3 FIC 06 LV TY 12B Fractionation Residue Gas Compressors Key Equipment BRAZED ALUMINIUM PLATE-FIN HEAT EXCHANGER “ Cold Boxes “ 1. 10-E-01/03 Gas/Gas Cold Box. 2. 10-E-02 Gas/Liquid Cold Box. 10-X-01 A/B Turbo expanders and compressor. 10-P-01/02 A/B CPC Chimney and Absorber bottom pumps Brazed Aluminum Plate-Fin Heat Exchanger Brazed Aluminum Plate-Fin Heat Exchanger Chart’s Brazed Aluminum Heat Exchangers (BAHX) are at the heart of cryogenic gas processing applications worldwide and offer vastly superior heat transfer performance versus their shell and tube counterparts. A Brazed Aluminum Heat Exchanger is typically 20% the size of a shell and tube exchanger of comparable performance. Furthermore, the alternating plate fin construction offers multiple stream capability and simplifies a series of shell and tube units to a single compact structure. Brazed Aluminum Plate-Fin Heat Exchanger Each Brazed Aluminum Heat Exchanger consists of alternating layers of corrugated fins (secondary heat transfer surface) separated by flat plates (primary heat transfer surface). Apart from the fluid entry and exit ports the edges are sealed with bars and the unit is brazed in a vacuum furnace. Construction is completed by attaching and welding the headers and nozzles over the entry and exit ports and the finished unit is rigorously tested for mechanical strength and leaks prior to despatch. 10-E-01 Gas/Gas Cold Box Hot Side Cold Side Design Temp. Max/Min °C 50/-196 50/-196 Design Pressure Max. Barg 79 36 No of layers per Core 65 66 Design Data Total No. Of Cores 3 Operating Parameters Temp in °C 30 -56 Temp Out °C -46 23 Pressure In Barg 59 28.5 Pressure Drop across Layers 0.8 0.65 10-E-03 Gas/Gas Cold Box Hot Side Cold Side Design Temp. Max/Min °C 50/-196 50/-196 Design Pressure Max. Barg 79 36 No of layers per Core 63 64 Design Data Total No. Of Cores 3 Operating Parameters Temp in °C -46 -84 Temp Out °C -82 -16 Pressure In Barg 30.6 29.7 Pressure Drop across Layers 0.6 1.3 10-FT-01/10FT-02 Ratio = 15-20 % Cold Side Max T = 50 Deg C , Max P = 36 Barg Hot Side Max T = 50 Deg C , Max P = 79 Barg Cold Side Max T = 50 Deg C , Max P = 36 Barg Hot Side Max T = 50 Deg C , Max P = 79 Barg Gas /Gas Cold Box Brief History 2004/2005: • High deferential pressure across Gas/Gas exchanger has been recorded , The inlet strainers (For the hot paths 24” and 36” ) were found collapsed and were re-fabricated again. • Many rupture disk was executed in both Gas/Gas and Gas/Liquid exchangers • Chemical cleaning with Toluene has been implemented also to reduce the high ΔP. 2006: • on 16 oct. 2006 , external gas leakage combined with insulation powder “Perlite” was observed from the housing of gas/gas exchanger 10-E-01/03. • IN 2006 this failed cold box was replaced in a plant shutdown by a new one and went for a CM to repair the crack. Gas /Gas Cold Box Brief History 2006 Failure resulted in the following modifications : • Adding nitrogen source equipped with flow transmitter and regulator to the cold box casing , also adding gas detectors to protect accumulation of hydrocarbon in casing in case of leakage. • Adding internal temperature transmitters and alarms application in order to monitor temperature differences between adjacent streams and rate of temperature change which was necessary to control the thermal stresses and protect cold box integrity. • 2014: • During plant start-up At 10:56 AM, an external gas leakage observed from the breathing hatch of Gas/Gas heat exchanger 10-E01/03 combined with Perlite release . • On March, 2014 shutdown, performed swapping for the failed gas/gas exchanger. • The last failure causes are still under investigation . 10-E-02 Gas/Liquid Cold Box Hot Side Cold Side (B/C) Design Temp. Max/Min °C 50/-196 50/-196 Design Pressure Max. Barg 79 36 No of layers per Core 104 96 Design Data Total No. Of Cores 1 Operating Parameters Temp in °C 30 -82 for B / -84 for C Temp Out °C -71 24 for B / -52 for C Pressure In Barg 59 32 Bar Pressure Drop across Layers 0.17 0.27 for B /0.73 for C Hot Side Max T = 50 Deg C , Max P = 79 Barg Cold Side B Max T = 50 Deg C , Max P = 36 Barg Cold Side C Max T = 50 Deg C , Max P = 36 Barg Min T = - 90 “ ENNPI SPECS” Gas /Liquid Cold Box Brief History 2004/2005: • Since the plant start up a high pressure drop issue through pass “C” was raised and communicated with the vendor (CHART) without serious progress • 2008: • an external gas leakage was detected from the housing of 10-E-02 as a result of hair crack in a plug welding of pass “B” internal vessel. Investigation showed that was due to high thermal stress during unplanned SD / start up . • Accordingly the G/L cold box was replaced by a new one on the end of October 2008. • Although a new gas liquid cold box was installed, the pressure drop through pass “C” increased dramatically same as happened with the old one. Gas /Liquid Cold Box Brief History • Quantity of Liquid collected in the expander feed sep. and absorber tower was dropped dramatically as a result of: • El-Gamil feed gas became leaner since July 2010 as a result of opened a new TUNA wells circa ( 210 MMSCFD ) • Upgrade plant capacity from 1100 to 1272 MMSCFD through utilizing more gas from Hap’y (leaner composition) affected mix feed gas . • The design case for rich gas and lean gas are 2.4 % and 1.9 % respectively , while the current is 1.62% as more gas from Hap’y was utilized in addition to El-Gamil became leaner . • Accordingly the liquid collected in expander feed separator became lower which affected the liquid flow rate through pass “B” and consequently the Temperature difference between adjacent streams. Gas /Liquid Cold Box Brief History • 2011 : On 2nd of May 2011, Operations reported a leak from the top of Cold box gas liquid exchanger through detecting alarm from gas detection on the top of the cold box, the operation was continued after performing a contingency plan and risk assessment till the planned shutdown in June 2011 where it was replaced by the repaired gas liquid cold box. • Investigation shows that during unplanned shut down excessive thermal stresses occur to different paths specially the liquid paths B and C both the rate of change in temperature and the temperature difference between two adjacent streams are exceeding the recommended range. It was recorded that in 30th of April one day before discovering the leakage a thermal stresses was applied to the liquid core see in the adjacent part to the defected part of B . Gas /Liquid Passes Modification • Before The Modifications : • The gas/liquid heat exchanger had very wide temperature difference between hot and cold streams at the midpoint of the exchanger. the feed gas is cooled down at G/L exchanger by two cold streams, the flashed liquids from expander feed separator” pass B” and then the liquid stream from absorber bottom pump. The hot stream at midpoint reaches 13C’ while the temp of flashed liquids from expander feed separator is -60 C’ and the temp of the absorber bottom liquids at the midpoint is -20 C’ leading to an average cold side metal temp of -40 C’ and the temp difference between hot and cold adjacent layers is 53 C’ which is higher than the max allowable temp difference recommended by manufacturer of 28 C’ to avoid risk of thermal stresses. Gas /Liquid Passes Modification • Before The Modifications : Lean Gas , without LPG reinjection Feed gas in , pass A 20C’ 8.5 MMSCFH 30 C’ To Demethanizer Diff = 10 C’ 13 C’ Avg= -40 C’ Diff = 53 C’ -20C’ Pass B IN -60 C’, 27.3 TON/H To Demethanizer Diff = 23C’ Feed gas OUT , pass A, -57 C’ Pass C IN -80C’, 156 TON/H Gas /Liquid Passes Modification • After Studying the proposals for required modifications to overcome this issue , the chosen proposal was : • Installing a pipeline connecting inlet of pass C to inlet of pass B of G/L cold box with flow control valve controlling the split liquid flow. • Part of the liq. stream from absorber bottom pump is mixed with the expander feed separator bottom liquid to enhance pass B heat duty , adjusts the Demethanizer temperature profile in the stripping section as well as reducing load on rectifying section accordingly propane % recovery improved to above 99%. • A bypass line installed on pass B with SDV opened during process S/D to protect the cold box from thermal stresses during transient periods of S/D and start up. Gas /Liquid Passes Modification • On March, 2014 shutdown, performed swapping for 10-E-02 and executed the project of G/L by-pass modification (PMR 25/2013) by constructing new 6” line taking slip stream from absorber bottom to be mixed with expander feed separator liquids feeding pass “B” to increase flow rate across the pass, increasing the duty across the pass, and lowering the temperature difference between two adjacent layers at the middle of 10-E-02 to be lower than 30°C as per chart recommendations to prevent thermal stresses. • 6” line is equipped with flow control valve 10-FV-18 and two isolation manual ball valves and 4” bypass gate valve. • Another line 12” was constructed to by-pass pass “B” in shutdown cases to prevent thermal stresses during those cases. • 12” line is equipped with 12” on-off valve 10-SDV-17 (normally closed) and two isolation ball 12” manual valves. Gas /Liquid Passes Modification • After The Modifications : Feed gas in , pass A 8.5 MMSCFH 27 C’ 20 C’ To demethanizer Diff =16C’ SDV Liq from bottom of exp feed sep pass B IN -80 C’, 65TON/H -54 C’ Diff =26 C’ -75C’, 40 TON/H -58 C’ To demethanizer TV-12 Diff =23C’ Feed gas OUT , pass A, -73C’ pass C IN -80C’, 103.3TON/H -80C’, 0 TON/H Flow control valve -80C’, 65 TON/H Liq from absorber bottom pump CPC Pumps • CPC Chimney and Absorber bottom pumps (10-P-01A/B,10-P-02 A/B) are centrifugal pumps , they comply with API-610 ISO standard , with a type code of (OH4) , this type characteristics are : 1- Overhung pump. 2- Vertical pump. 3- Rigidly Coupled (Pump shaft is rigidly coupled to driver shaft ). 4- Single stage . CPC Pumps CPC Pumps CPC Pumps 10-P-01 A/B 10-P-02 A/B -49 -49 36/27.2 36/26.9 Differential Pressure Bar 2.8 3.1 NPSHA m 6 3 190000 190000 Suction Temp Out °C -84 -84 Suction Pressure Barg 30 30 Design Data Liquid Temp. Max °C Suction Pressure Max/Rated. Barg Operating Parameters Average Flow Rate Kg / hr Turbo-Expanders • Turboexpander : also referred to as a turbo-expander or an expansion turbine, is a centrifugal or axial flow turbine through which a high pressure gas is expanded to produce work that is often used to drive a compressor. • Because work is extracted from the expanding high pressure gas, the expansion is approximated by an isentropic process (i.e., a constant entropy process) and the low pressure exhaust gas from the turbine is at a very low temperature, depending upon the operating pressure and gas properties. • Turboexpanders are very widely used as sources of refrigeration in industrial processes such as the extraction of ethane and natural gas liquids (NGLs) from natural gas Turbo-Expanders • Turboexpander : also referred to as a turbo-expander or an expansion turbine, is a centrifugal or axial flow turbine through which a high pressure gas is expanded to produce work that is often used to drive a compressor. • Because work is extracted from the expanding high pressure gas, the expansion is approximated by an isentropic process (i.e., a constant entropy process) and the low pressure exhaust gas from the turbine is at a very low temperature, depending upon the operating pressure and gas properties. • Turboexpanders are very widely used as sources of refrigeration in industrial processes such as the extraction of ethane and natural gas liquids (NGLs) from natural gas Turbo-Expanders Schematic diagram of a turbo- expander driving a compressor. Turbo-Expanders 10-U-01 A/B • Turboexpander system consists of two frame 5.0 Mafi-Trench compressor loaded turboexpanders equipped with S2M magnetic bearings. Each is mounted on a rigid steel skid base and supported by a control and seal gas system. System components are arranged for ease of operation and maintenance. • The expander-compressor consists of three basic sections: 1. The expander section with inlet and discharge flanges. 2. The rotating assembly or center section. 3. The compressor section with inlet and discharge flanges. Turbo-Expanders 10-U-01 A/B Expander Rotating Section assembly Compressor section Turbo-Expanders 10-U-01 A/B Description 1.Inlet guide vanes The inlet guide vanes regulate mass flow to the expander. The mechanism is designed to withstand full expander inlet pressure and can be adjusted to vary flow over the range of approximately 0 to approximately 125% of the design mass flow rate. An air-loaded actuator with positioner controls the guide vane opening. A control signal causes the actuator to adjust the inlet guide vane opening to compensate for changes in process conditions. Turbo-Expanders 10-U-01 A/B Description Turbo-Expanders 10-U-01 A/B Description 2. EXPANDER AND COMPRESSOR WHEELS • Mafi-Trench Expander and Compressor wheels are machined from solid plate or bar for maximum strength and integrity . The radial inflow expander wheel with our variable inlet guide vane design produces high efficiencies • over a broad operating range. 3. Shaft • Wheels are attached to the shaft on a special tapered profile. Turbo-Expanders 10-U-01 A/B Description Turbo-Expanders 10-U-01 A/B Description 4. Shaft Seal • Shaft seals are labyrinth type to minimize seal gas leakage. The design incorporates a steel rotating labyrinth running adjacent to a glass fiber reinforced seal cartridge over a broad operating range. 5. Active Magnetic Bearing • An active magnetic bearing is an electromagnetic device that maintains the relative position of a rotating assembly (rotor) with respect to a stationary part (stator). The electromagnetic forces implemented for this are controlled by an electronic control cabinet. • An active magnetic bearing is, therefore, made up of two distinct parts, the bearing itself and the electronic control system. Turbo-Expanders 10-U-01 A/B Description Turbo-Expanders 10-U-01 A/B Description Turbo- expander Magnetic bearing and Magnetic beraing control system Turbo-Expanders 10-U-01 A/B Description 6. AUTOMATIC THRUST EQUALIZER SYSTEM (ATE) • Use active, automatic thrust balancing methods to keep normal thrust bearing differential loads near Zero . • Current signals from the magnetic thrust bearing system are used to control a pressure control valve which adjusts the pressure behind the expander wheel to maintain balanced thrust loads. Turbo-Expanders 10-U-01 A/B Description Turbo-Expanders 10-U-01 A/B Description 7. Seal Gas System • The buffer gas system filters and regulates gas flow to the labyrinth seals inside each turbo-expander. These seals are located between each impeller and its associated auxiliary bearing. • The buffer gas system performs three important functions: (1) Ensures that adequate buffer gas is available to carry away heat generated by the magnetic bearings and by rotor. (2) Keep cold, unclean process gas away from the auxiliary bearings. (3) Maintain a positive pressure in the bearing housing (to prevent entrance of air). • The seal gas pressure is controlled by primary and secondary regulating valve that automatically maintains a constant seal gas pressure across the seals Turbo-Expanders 10-U-01 A/B Description Labyrinth seal showing seal gas flow path Turbo-Expanders 10-U-01 A/B Expander Compressor Suction Pressure Barg 64.7 23.7 Discharge Pressure. Barg 26 33.1 Suction Temperature °C -35 26.4 Discharge Temperature °C -75.2 54 Design Data Turbo-Expanders 10-U-01 A/B • The following slides show the alarm limits for the Expander –compressor package , to operate the equipment safely Seal gas DP 2.4 Barg “ low alarm as per MAFI-Trench CONTROL SETPOINT 1.8 is the trip point Seal gas filter DP 1.7 barg low alarm as per MAFITrench CONTROL SETPOINT Bearing House Pressure 14 barg low alarm as per MAFI-Trench CONTROL SETPOINT Boundary Housing Differential Pressure 0.2 mbar High alarm as per MAFITrench CONTROL SETPOINT Expander Bearing Temp. 10 Deg C low alarm as per MAFI-Trench CONTROL SETPOINT Compressor Bearing Temp. 99 Deg C High alarm as per MAFI-Trench CONTROL SETPOINT Speed Transmitters 12100 RPM high alarm as per MAFITrench CONTROL SETPOINT Position :90 µm High alarm Unbalance : 36 µm High alarm as per MAFI-Trench CONTROL SETPOINT 110 Deg C High alarm as per MAFITrench CONTROL SETPOIN T 150 µm High alarm as per MAFI-Trench CONTROL SETPOINT Position :90 µm High alarm Unbalance : 36 µm High alarm as per MAFI-Trench CONTROL SETPOINT Position :90 µm High alarm Unbalance : 36 µm High alarm as per MAFI-Trench CONTROL SETPOINT Position :90 µm High alarm Unbalance : 36 µm High alarm as per MAFI-Trench CONTROL SETPOINT +/- 200 trip as per MAFITrench CONTROL SETPOINT 65 Deg C High alarm as per MAFITrench CONTROL SETPOINT Absorber and De-methanizer Absorber 10-C-02 De-methanizer 10-C-01 36 36 -110/145 -85/145 Cold Conservation Cold / Heat Conservation Diameter m 5.344 4.570 Length m 18.04 8.1 Bed Height 29.7 No. of Trays 6 theoretical stages 30 Trays Type N.A Valve Type Packing Type FLIXIMIX 700 SS N.A Design Data Design Pressure Barg Design Temperature Min/ Max °C Insulation De-Methanizer Reboiler Shell Side Tube Side 36 24 -100/150 5/300 Design Data Design Pressure Barg Design Temperature Min/ Max °C No. of tube Type Duty MMcal 1634 Kittle reboiler TEMA class R 22 Applied Modification in Unit-10 • All of these modifications are implemented according to technical studies and MOC/PMR procedure in objective to enhance UGDC facilities availability, and productivity. 10-PSV-36 (Absorber PSV) Modification: • Adding a new tail pipe Objective: • Decrease tail pipe back pressure and also decrease velocity to be lower than 0.7 MACH limit. Cold Box Exchangers 10-E-01/03-02 Modification: • Adding nitrogen source equipped with flow transmitter and regulator to the cold box casing. • Adding internal temperature transmitters and alarms application. • Adding gas detectors. Objective: • Protect accumulation of hydrocarbon in casing in case of leakage. • Monitoring temperature differences between adjacent streams and rate of temperature change. • Controlling thermal stresses and protect cold box integrity. Absorber 10-C-02 Modification: • Adding 2oo3 10-PSHH-29A/B/C at the top of absorber for U-10 ESD. Objective: • To prevent a phenomenon known as “Acoustic failure” which may occur D/S the absorber relief valves as the relief capability may be insufficient for a blocked outlet relief scenario. Absorber Platforms 10-C-02 Modification: • Repairing the absorber skids as the present were rust-hit and became unsafe to use. Objective: • The company’s eagerness to achieve the most safe work conditions for workers by performing the repairing process. Absorber CPC Pumps 10-P-01/02 Modification: • Bearing lubrication routed from pumps discharge through internal bearing to the impeller suction instead of drain. Objective: • Save hydrocarbon losses. G/L Cold Box Passes Modifications Modification: • Installing a pipeline connecting inlet of pass C to inlet of pass B of G/L cold box with flow control valve controlling the split liquid flow. • A bypass line installed on pass B with SDV opened during process S/D to protect the cold box from thermal stresses during transient periods of S/D and start up. Objective: • Maintained Cold Box integrity as the temperature difference in the mid point has been reduced to below 28 Deg. C as per CHART recommendations . Unit 10 Dead Legs Modification: • Connecting 7 points of hydrocarbon deal legs in the piping to the closed drain network , this modification has been implemented in 2014 SD . Objective: • Availing a higher performance during plant dry out be directly draining these dead legs to close drain system, also eliminating the using of hoses for this purpose which comply with QHSE requirements . Most important Control Loops in U-10 In the upcoming slides , the most important control loops inside Unit-10 are simply described . 1. Inlet gas flow ratio control 10-FFIC-01 PID (10-GD-04040) • Dry gas from de-mercury removal unit is cooled via two separate flow paths, one using cool residue gas in the gas/gas exchanger, and the other in a gas/liquid exchanger utilized a cool liquid from expander feed separator (pass B), and the bottom liquid from absorber tower (pass C). • The total plant inlet flow is therefore used as the set point input to a flow ratio controller. The inlet gas flow to the gas liquids exchanger can therefore be set at some set ratio of inlet gas flow rate depending on process conditions. • Sometimes the ratio will set remotely by the temperature controller 10-TIC12. • Flow split is manipulated as the primary control within a programmed range of flow ratios (approximately 10% - 20% of inlet gas to the gas liquids exchanger). • In order to maintain the desired ratio under all operating condition, the output of the flow ratio controller, FFC is split ranged between two valves, one in the inlet gas line to the GAS/GAS Exchanger and the other to the GAS/LIQUIDS exchanger. 1. Inlet gas flow ratio control 10-FFIC-01 continued. • A typical split range could be implemented as follows: FFC Output 0% 50% 100% • FV-A FV-B Position (Gas/Gas) Position (Gas/Liquids) 0-50% Close Limit Open Open 50-100% Open Open Close Limit As can be seen from the table above when the FFC output is at 50% both valves will be fully open, between 50% and 0% valve FV-A will be moving from open to closed and between 50% and 100% valve FV-B will be moving from open to closed. 2. Gas/Liquids Exchanger Temperature Control 10-TIC-12 PID (10-GD-B-04041-1) • The main objective of the mentioned loop is to adjust heat amount, and temperature of the liquid feed to the de-methanizer tower coming from absorber bottom liquid via gas/liquid exchanger pass C. • In order to satisfy this objective the output of TIC-12 is a split range: • From 0% to 66% are used to rest the flow ratio controller 10-FFIC-01of the inlet gas flowing through the gas liquid exchanger, while the output increase (0%-66%) the ratio setting will decrease, then the amount of gas flowing to 10-E-02 also decrease until output 66% the gas will be at a minimum stop. • From 66% to 100% will start open the bypass valve 10-TV-12 located on by pass line of 10-E-02 pass C that to decrease inlet temperature to 10-C-01. 2. Gas/Liquids Exchanger Temperature Control 10-TIC-12 Continued FFC ratio (inlet gas to 10-E-02) TV Position (Pass C bypass) TC Output Max. To Min. 0-66% Close-Open 66-100% 0% Maximum Closed 33% Mid scale Closed 66% Minimum Start to Open 100% Minimum Open As can be seen from table above, 0% output means a maximum flow of inlet gas to 10-E-02, 33% output is a normal design flow, and 66% is a minimum stopping flow based upon chart recommendation. 3. Gas/liquid new by-pass Modification control: 10-FIC-18 PID (10-GD-B-04041-1) • Flow controller 10-FIC-18 control the flow rate of withdrawn split stream from absorber bottoms to be mixed with flashed liquids from expander feed separator feeding pass “B” of E-02 to reduce and control the temperature difference between adjacent streams at the middle of E-02 below 28°C to avoid thermal stresses. • Opening the flow control valve 10-FV-18 will increase the flow rate across pass “B” and with lower temperature allowing higher duty within pass “B”, reducing feed gas temperature at the middle of pass “A” dramatically, reducing the temperature of outlet pass “C”, and lowering the temperature difference between adjacent streams till reaching acceptable difference. 4. Expander Inlet Temperature Control: 10-TIC-15 (PID 10-GD-B-04041-2) • 10-TIC-15-temperature controller controls the inlet temperature of expander 10-x-01A/B. The output signal is connected to 10-TV-15 valve on a bypass line of the cold gas from absorber tower 10-C-02 to expander compressor via de-methanizer overhead condenser, then Gas/Gas heat exchanger 10-E01. • When the bypass valve is opened, it will reduce the cool residue gas flow through Gas/Gas exchanger, thereby raising the inlet gas stream out of Gas/Gas exchanger to maintain the expander inlet temperature not below a certain temperature depend upon the inlet feed gas composition, because it is possible under certain operating condition the warm feed to expander can provide improved recovery. 5. Reflux Flow Ratio Control: 10-FIC-08. (PID-10-GD-B-04045-1A) • The reflux flow for both absorber 10-C-02 and de-methanizer 10-C-01 are controlled by 10-FIC-08 control loop. 10-FIC-08 set value is reset manually according to process optimization calculation depending on the operating condition. • The output signal is connected to 10-FV-08 flow valve on demethanizer reflux line for constant amount of reflux to 10-C-01 at certain condition; consequently the remaining reflux will go through the middle section of absorber. 6. De-methanizer Overhead Accumulator Level Control 10-LIC-06 (PID 10-GD-B-04045-A1) • The liquid level of de-methanizer Overhead Accumulator (upper section of 10-C-02) is controlled by 10-LIC-06-control loop. 10-LIC-06 set value is reset manually according to the amount of liquid condensed from demethanizer overhead gas. • In case of high liquid level and to avoid liquid carryover from absorber upper section chimney to the packing middle section of 10-C-02, the output signal from 10-LIC-06 will open 10-LV-06 level valve on absorber reflux line, to keep a stable amount of reflux to 10-C-01 at certain condition, that to avoid disturbance at the de-methanizer tower. 8. Cascade Control of Absorber Bottom Liquids 10-LIC08, & 10-FIC-10 PID (10-GD-B-04045) • The absorber bottom liquid from 10-C-02 is controlled by 10-FIC-10-cascade control loop. 10-FIC-10 set value is changed by 10-LIC-08-output signal. 10FV-10-control valve operate to adjust 10-FI-10-flow rate to the set value. In this control loop, 10-LIC-08 controllers continuously changes 10-FIC-10 set value with the liquid level fluctuation in 10-C-02-bottom section. Unit Shut Down • Level (1) ESD will be activated in one or more of the following ways: • Manually via dedicated push buttons on the control room ESD panel . • High high liquid level in the flare KO drums 97-V-01/02/03. . • Automatically from the Fire and Gas system upon confirmed signal from two or more process areas . • Low low instrument air pressure . • Automatically from low export gas pipeline pressure . • High high liquid level in H.P fuel gas KO drum. • ESD level (0) is emergency depressurizing system and it is generated only by manual push button on matrix panel in control room. Unit Shut Down • ESD level (0) is emergency depressurizing system and it is generated only by manual push button on matrix panel in control room. • Action: • Close all ESD valves. • Permission to all blow down system, however the blow down for each unit will be manually from ESD matrix panel through operator’s intervention. • Open SDV on plant by pass line (HAP’Y and ELGAMEL). • ESD level (1) is same as level (0), except that the permission of blow down is not included. Unit Shut Down • Unit Shutdown “LEVEL 2 ESD “will be initiated in case of one of the following reasons occurred: • Confirmed Fire & Gas detection in U-10. • High High Temperature (10-TAHH-06 A/B/C ) for gas inlet to 10-E-01. • High High liquid level (10-LAHH-03 A/B/C) for exp. feed separator 10V-01. • High High Pressure (10-PAHH-29 A/B/C) for absorber. • Low Low temperature (10-TALL-01) for residue gas. • Push buttons installed in front of the unit control panel (UCP) or from the control & shutdown system (CSS). • Plant Level 1 ESD. Unit Shut Down • • • • • • • • • • • • • – Unit Isolation and valves status : The ESD system will close the following: 10-SDV-01 (Gas inlet to 10-E-01 Hot side). 10-SDV-14 (Bypass of 10-SDV-01). 10-SDV-02 (10-K-01A Suction). 10-SDV-04 (10-U-01A Suction). 10-SDV-07 (10-K-01B Suction). 10-SDV-08 (10-U-01B Suction). 10-SDV-09 (10-E-04 Hot Oil Supply). 10-SDV-10 (10-C-01 Bottom). 10-SDV-11 (10-C-02 Bottom). 10-SDV-12 (10-C-02 to 10-P-01 A/B). 10-SDV-15 (10-E-03 Cold Stream Outlet). 10-SDV-13 (10-V-01 Liquid Outlet). Equipment Shut Down LEVEL 3 • Shut down of expander compressor (10-X-01A/B), expander/compressor automatically stops at one of the following condition: – Expander bearing low temperature trip 10-TALL-03A/B. – Magnetic bearing trip (alarm level 2 & level 3) 10-XSD-04A/B. – Bearing housing low-pressure trip 10-PALL-11A/B. – Watchdog Failure from magnetic bearing cabinet 10-XSD-02A/B. – Expander speed too low from magnetic bearing cabinet 10-XSD03A/B. – Expander/Compressor high-speed trip 10-SAHH-01A/B. – Seal gas low differential pressure trip 10-PDALL-04A/B. – Low-Low pressure of re-compressor suction line 10-PALL-14. – High-High temperature of re-compressor discharge line 10-TAHH17. – Low-Low Expander suction Temperature 10-TALL-01. – High Differential pressure across Expander compressor strainers Equipment Shut Down LEVEL 3 • Absorber Bottom Pump 10-P-02A/B Shut Down In case of 10-P-02A/B shut down, the cause and necessary action are as follows: • Absorber bottom liquid Low-Low 10-LSLL-09 Equipment Shut Down LEVEL 3 • De-Methanizer Reflux Pump 10-P-01A/B Shut Down: In case of 10-P-01A/B shut down, the cause and necessary action are as follows: • De-methanizer OVHD accumulator (upper section of 10-C-02) liquid level Low-Low 10-LSLL-07.