SITE ADDRESS: 1 Elm Park Road, London, SW3 6BD PREPARED BY: South Downs Safety Ltd CLIENT: Mr & Mrs Marar, c/o Sandbay Limited, South Tower, 26 Elmfield Road, Bromley, Kent, BR1 1WA PROJECT MANAGER: Synergy Ltd, The Boathouse, 27 Ferry Road, Teddington, TW11 9NN Contact: Tom Adams Tel: 07557 742515 DATE: 22.07.14 REF NO: MS038 METHOD STATEMENT & RISK ASSESSMENT SIGNING SHEET. All Trenchco operatives must read and understand the company’s project specific method statement and risk assessments contained within this document then sign and date below to confirm their acceptance of all site rules and safety procedures. NAME SIGNATURE Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP DATE OPERATION: Construction of double basement “top down” with secant piled walls, temporary piles, and casting of GF slab before excavating the basement, casting the basement slab and excavating the sub-basement. COMMENCEMENT DATE: T.B.A. DURATION: 30 Weeks CONTRACTS MANAGER: Liam Murphy – 07834 523871 RESPONSIBILITIES: The Contracts Manager will be responsible for: Explaining the content of the method statement and risk assessments to all operatives. Explaining the content of the Traffic Management Plan to all operatives. Ensuring that all persons comply with the safe systems of work laid down by Trenchco Ltd in this method statement and associated risk assessments. Completing any Client permits to work. Ensuring that all plant and equipment has valid Thorough Examination Certificates and that weekly visual inspections are completed. PRE-COMMENCEMENT REQUIREMENTS: All personnel arriving on site will attend the site induction, highlighting site rules and emergency procedures before working on site. Trenchco will be provided with information on any existing services, such as Utility Service/ Sumo drawings, before any excavations commence. All Site operatives to treat services as LIVE unless proof of isolation is provided from the Client or service provider. All plant operators to hold CPCS card, all other site workers to hold CSCS card. All plant to be delivered with the relevant documentation including Thorough Examination Certificates to demonstrate that the plant is fit for use. NO. OF OPERATIVES: 8 - 12 INDUCTION / BRIEFINGS: Induction to be given by Site Foreman / Supervisor TOOLS & MACHINERY: Hand tools, disc cutter, generator, vibrating poker, kangos, scabbling guns, air guns PLANT: 360⁰ Excavators (1no. 13T, 1no. 2 ½T), 13T crane with grab attachment, Grab Lorries, Piling Rig and associated power pack. FUME EXTRACTION: Excavators working beneath the GF and basement slabs will be fitted with catalytic converters and CO2 filters. In addition to this, forced ventilation will be provided in the form of fans and adjustable ductwork which will be secured to walls, props or piles as required. Gas monitors will be kept in the basement to alert the Supervisor of the build up of and CO emissions produced by plant or any natural gases present in the ground. PPE: Safety Footwear, Hard Hats, Hi-Visibility Jackets and Gloves (nitrile) & Goggles as required. CONTROL MEASURES: PPE / training / working in daylight hours only / risk assessments / 110v or battery tools / good housekeeping in place at all times EMERGENCY PROCEDURES: In the event of an emergency, operatives shall exit the basement via the securely tied ladders, positioned within the moling hole(s). In the event of a person becoming unconscious in the basement, the emergency services shall be contacted immediately. The Supervisor shall administer any remedial first aid and with the help of another operative, the injured person shall be placed on an evacuation stretcher and raised using a confined spaces rescue hoist, positioned above the slab opening.. Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP SUPERVISION: Site Supervisor on site full time with regular visits by the Contracts Manager. Monthly independent H&S Audits COMMUNICATION: The Site Supervisor will complete daily briefings with all operatives to highlight any specific hazards that could affect them. TRAINING: The Site Supervisor will hold a valid SSSTS Certificate. Mobile Tower Scaffolds will be erected by a PASMA trained operative. Plant will be operated by persons holding a valid CPCS certificate. Toolbox Talks will be completed weekly. Any statutory training will be refreshed as needed. RECORDING: Trenchco Ltd will record all training and induction provided and employees to sign as confirmation of their acknowledgement HOT WORKS: Disc cutters will produce sparks when cutting rebar and the specific risk assessment should be consulted prior to completing the work. A hot works permit will be issued by the Site Supervisor prior to any hot works and a minimum of 1no. water and 1no. CO2 extinguisher will be kept next to the work area. Operatives will be reminded to ensure all flammable materials are removed from the working area and screens to prevent the transfer of sparks erected as required. CLIENTS REQUIREMENTS: Requirements for the piling is set out in Engineer’s specification and must be followed without deviation. Any change to the specification must be approved by the engineer in writing prior to the change taking place. ACCESS & EGRESS: Safe access will be maintained into the excavation by means of a securely tied ladder in the “Moling Hole” which will be located adjacent to the site entrance allowing muck away lorries to be loaded directly. Task lighting will be installed at high level by way of 110v festoon lighting plugged into the site temporary supplies. VIBRATION & NOISE: The Site Supervisor shall inform the Contracts Manager of the specific model numbers of all vibrating tools as they arrive on site and together they will use the online HSE Vibration calculator to determine the recommended usage over 8 hour period and Noise levels dB (A). Below shows indicative exposure limits. EQUIPMENT Vibration K Factor Max Per 8hr Shift Decibel Level Max Per 8hr Shift Angle Grinder 1.5m/ sec² 8hrs Unknown 8hrs (SNR 25>) Circular Saw 1.5m/ sec² 8hrs 104dB(A) 8hrs (SNR 25>) Hammer Drill 13.5m/ sec² 1hr 6 mins Unknown 8hrs (SNR 25>) Petrol Disc Cutter 2.5m/s2 8hrs 97dB(A) 8hrs (SNR 25>) Poker Vibrator 75mm 12m/s2 21mins Unknown 8hrs (SNR 25>) SEGREGATION: Due to the requirement for constantly moving plant on site, it is impractical to have a permanent pedestrian route. However, a walkway through the site will be demarcated in Chapter 8 barriers so that it can be moved as required. Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP PLANT Piling rigs will have safety cages fitted and where they require adjustment to allow piles to be installed adjacent to underpins, additional barriers will be positioned 2m away from the rig to prevent persons coming into contact with the mechanism or auger and the RPM will be reduced to reduce the risk of injury in the unlikely event of contact with the rig. Moving Augers When moving augers, the following procedure shall be observed: Where possible, Augers to be moved singularly in the bucket of an excavator, held securely against the blade. Where chains are to be used, attached by a competent person, with a maximum load of 2no. augers and under no circumstances should the augers themselves be touched. Any positioning required shall be done by holding/ pushing the chains only. Although there are multiple trained banksman on site, only one shall be nominated at any one time by wearing an orange hi-viz vest as opposed to a standard yellow to ensure all person, in particular machine drivers, know who is responsible for instructing them. Where the nominated banksman needs to complete a different operation, he shall hand over the orange vest to another trained banksman who will assume his duties. EXCAVATIONS Edges of light wells will be protected with scaffold and will have combi-safe barriers fixed to them at all times. Suitable, securely tied ladder access will be maintained at all times in excavations. Spoil being excavated below the LGF and Basement slabs shall be battered back to eliminate the risk of collapse. Once top-down construction begins, a rescue tripod, harness and stretcher will be made available in the event that an operative requires rescuing. ENVIRONMENT: Oil storage for tanks and drums containing greater than 200ltrs will be contained in a secondary containment system, it must have a capacity of not less than 110% of the largest container's storage capacity or, if there is more than one container within the system, of not less than 110% of the largest container's storage capacity or 25% of their aggregate storage capacity, whichever is the greater. Oil storage will not be within 10m of a drain or watercourse and will be located away from regular vehicle movements to prevent damage and a double bunded fuel bowser will be used on site and will be locked when not in use. Drip trays will be used when refuelling plant, under oil containers when in use and under static plant. Spill kits will be provided next to all fuel storage. When dewatering, water will be pumped into a catch-pit with an overflow at high level, allowing clean water to be released into an agreed area. All sediment will settle in the bottom of the catch-pit which will be jet washed clean periodically and any sediment will be disposed of as general waste or used as backfill material where possible. SITE TRAFFIC: As per the Synergy Traffic Management Plan. Deliveries to site will approach from the West to avoid the A4/ A308 junction and South Kensington Station. Vehicles shall approach the sier via the Redcliffe Gardens North/. South link and turn left onto the A308 Fulham Road. From there vehicles shall proceed straight on Fulham Road and turn right into Park Walk, and then immediately left into Elm Park Road. On exiting the site, vehicles shall turn left in line with the current one way system onto Elm Park Road, left onto Beaufort Street and left onto Fulham Road and proceed West towards the Brompton Cemetery before turning right into Finborough Road and away from the area. Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP WASTE: During piling operations, muck away vehicles shall reverse onto the site on the existing ground. Once the piling is complete, the new GF shall be cast allowing vehicles to reverse onto it and be loaded directly by 13T excavator. Spoil will be removed by 13T machine reaching into the “Moling Hole” with a 2 ½T machine digging beneath the new GF slab. No spoil will be stockpiled on site as the 13T excavator shall load directly into the muck-away wagon. When excavating the sub-basement, the 2 ½T machine will dig itself down again with spoil being removed by 13T crane with grab attachment reaching down through the “Moling Hole” from above ground. Trenchco hold a valid Hazardous Waste Carriers License and an appropriate Waste Transfer Note will be completed for all waste removed from site and will be signed for by Site Supervisor before Lorry leaves site. DUST: All activities will assessed for the risks associated with dust production and where necessary, water will be used to suppress the dust by means of wet cutting and damping down with a hosepipe direct to the source. CONCRETE PIPE CLEANING: Blockages are cleared with the use of cleaning balls forced through the pipe system, propelled with compressed air. During this operation, the area will be cleared of all non-operational personnel. Pipes restrained mechanically with pressure released prior to clip loosening. The retaining cage will be fixed to the end of the pie with a retaining clip. The cleaning ball will be damped with water and placed inside the pipe at the pump end. Air will be introduced gradually to prevent uncontrolled release of the ball. An operative will tap the pipe work with a hammer to aid release of concrete inside and to track the progress of the ball. When the ball is close to the end of the pipe, the pressure will be reduced to slow the speed at which the ball exits the pipework. CONSTRUCTION SEQUENCE: Install secant piled walls Construct capping beams Construct GF Slab Begin reduce level dig for basement. Cast basement slab. Construct basement lining walls. Begin reduce level dig for sub-basement. Install below ground drainage. Cast sub-basement slab. Construct lining walls. Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP METHODOLOGY: PILING: The secant pile methodology comprises the formation of overlapping concrete piles. Typically alternate unreinforced or “female” piles are formed using lower strength concrete. The remaining piles are standard reinforced concrete “male” piles. The picture below shows a typical construction sequence: The piling working platform will be prepared where required by levelling the existing ground using a 2 ½T machine. Piling will commence in accordance with the Engineer’s specification and drawings. Piling rigs will be delivered to site with any protection to pavements as specified in the Traffic Management Plan. All plant will be delivered with a valid Thorough Examination Certificate and a competent operator, holding a CPCS qualification or similar. Prior to starting, the piling platform level will be checked to ensure that is consistent with the pile design. If there is a significant difference, the engineer shall be informed and the piling design amended before commencement. The rig will be erected in accordance with the manufacturers details on the piling platform and then levelled in position directly over the pile to be constructed where it will commence installation in sequence, with the rig traversing along the line of the piles. Prior to commencement of the operation, and auger “end cap” is fitted at the base of the auger to seal the hollow stem against the ingress of ground water and soil as the continuous flight auger bores into the ground to the required depth. Little spoil is removed during the boring phase. Bore spoil arisings and concrete over break is removed from the pile head by the attendant 360⁰ excavator. Once the auger has bored down leaving only approx 150mm above ground, the rig will be disconnected, an additional auger fitted and boring will continue. This process will be repeated until the final depth of the piles has been reached. In the event of a blockage, the auger is extracted by rotating anti-clockwise to leave as much spoil supporting the hole as possible. Blockages are cleared with the use of cleaning balls forced through the pipe system, propelled with compressed air. During this operation, the area will be cleared of all non-operational personnel and the pipes restrained mechanically with pressure released prior to clip loosening. In all instances, once the blockage is cleared, the hole is re-drilled to a founding level slightly deeper than originally achieved. Bore spoil arisings and concrete over break is removed from the pile head by the attendant 360⁰ excavator. The prefabricated reinforcing cages, with proprietary wheel clip on plastic spacers, is then installed into the bore hole. The cages will be lifted using the auxiliary line on the piling rig, as well as the attendant 360⁰ excavator, to prevent damage to the cage and to prevent spoil falling into the bore hole. The cages will be lowered into the bore hole with the Supervisor satisfying himself that the cage is lined up correctly before being detached from the attendant 360⁰ excavator. The cage will then be left attached to the auxiliary line of the rig and lowered under its own weight but may be assisted by the attendant 360⁰ excavator where additional pressure is required to force the cage into the pile. Concrete will be pumped directly into the bore holes until they are full. Any rebar protruding above ground level will be protected with “mushrooms” to prevent injury. Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP CAPPING BEAMS & SLABS: Once the above stages have been completed, the capping beam and ground floor slab will be constructed. Excavate to both sides of secant piles. Break down piles using attachment to 360⁰ Excavator where possible or with pneumatic tools to engineer’s levels. Once the formation is reached the Engineer will inspect & check the oversite is @ correct line and level. Blind & lay polythene to bottom of trench and GF slab. Where appropriate and shutter edges, then steelfixers will then install mesh reinforcement as per the engineers’ details. 4” pipes will be installed in the capping beam at 1m centres, directly above the centre line of the basement lining walls, allowing concrete to be poured from above ground level. Concrete will be pumped directly into the required areas direct from lorry. Poker beam and tamp to finish levels. Once hardened sufficiently remove shuttering. Note: When using vibrating equipment such as petrol saw, vibrating tamps & pokers check for usage times and rotate workforce to prevent over exposure, record daily exposure to each individual REDUCE LEVEL DIG: Excavation will continue with the 13T Excavator reaching into the “Moling Hole” and being fed by the smaller 2 ½T machine which will excavate areas that the larger machine cannot reach and will place spoil into the area for the larger machine to load lorries. Access into the excavation will be via a suitably tied ladder. BASEMENT SLAB: Once the formation is reached the Engineer will inspect & check the oversite is @ correct line and level. Blind & lay polythene to bottom of excavation. Where appropriate shutter edges, then steelfixers will then install mesh reinforcement as per the engineers’ details. Concrete will be pumped directly into the required areas direct from lorry through 4” pipes in the capping beam. Poker slab and tamp to finish levels. Once hardened sufficiently remove shuttering. Note: When using vibrating equipment such as petrol saw, vibrating tamps & pokers check for usage times and rotate workforce to prevent over exposure, record daily exposure to each individual Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP LINING WALLS: Lining walls will have shuttering erected in timber in 5 linear metre sections with propping as detailed below (typical detail only). Mobile tower scaffolds erected by a PASMA trained operative will be used for access during erection of shutters and for pouring the walls. Concrete will be pumped directly into the shuttering. Poker concrete and tamp to finish levels. Shutters to be struck once concrete has cured. Mobile tower scaffolds erected by a PASMA trained operative will be used to access the LGF slab soffit and straighten the starter bars. Columns will have shuttering erected to the soffit level. During the LGF slab construction 4” plastic pipes will have been installed above the centre of the columns, allowing concrete to be poured from above ground, rather than trailing pump pipework into basement. Poker concrete to finish levels. Shutters to be struck once concrete has cured. SUB-BASEMENT SLAB: Once the formation is reached the Engineer will inspect & check the oversite is @ correct line and level. Install below ground drainage. Blind & lay polythene to bottom of excavation. Where appropriate shutter edges, then steelfixers will then install mesh reinforcement as per the engineers’ details. Concrete will be pumped directly into the required areas direct from lorry through 4” pipes in the capping beam. Poker slab and tamp to finish levels. Once hardened sufficiently remove shuttering. Note: When using vibrating equipment such as petrol saw, vibrating tamps & pokers check for usage times and rotate workforce to prevent over exposure, record daily exposure to each individual. Lining walls for the sub-basement will be constructed as per the basement level. Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP TEMPORARY PILE REMOVAL: A “safe zone” will be demarcated around the temporary pile excluding all persons not completing removal of the piles. Access to the top of the pile will be completed from a mobile tower scaffold, erected by a PASMA trained operative. The top of the pile will be cut around the perimeter with a petrol cut-off saw, as close to the soffit of the GF slab as possible. An electric breaker or pneumatic breaker will be used to break out the top (approx 300mm) of the pile. Once the rebar has been exposed at the top of the pile, the remainder of the concrete will be broken down using a 2½ T excavator with a pecker attachment. The machine driver shall wear eye protection and ear defenders at all times when breaking the pile. As concrete is broken down and rebar is exposed, an operative shall cut the rebar using a petrol cut-off saw, using a mobile scaffold tower for access. The pile will be broken down in approx 1m sections. USE OF EXCAVATORS AS LIFTING EQUIPMENT: Under no circumstances will excavators be used for lifting persons as they operate at speeds which make them totally unsuitable for the lifting of persons. Excavators designed for lifting loads/ object handling should have a rated object handling capacity table inside the cab. If a rated object handling table is not present then the machine should not be used for object handling. The use of an excavator as lifting equipment poses additional hazards as the slinger needs to be in the “danger area” adjacent to the arm/ bucket etc. during the lift to attach and monitor the load during the lift. As such, clear lines of communication must be kept between the operator and the slinger at all times. All excavators and their lifting accessories will be suitable maintained, have a Thorough Examination completed and a certificate issued a minimum of every twelve months. Prior to any lifting operations with excavators, the appointed person will ensure that a risk assessment is completed, ensuring that the machine is capable of lifting the intended load, that lifting accessories are adequate and free from damage and that ground conditions are suitable to allow the lift to take place. The appointed person will brief all persons present/ involved in the lift on any significant findings of the risk assessment, the method statement and operatives individual roles in carrying out the task. Where special lifting attachments are used, they must be compatible with the machine and its coupling methods to which they are being attached. The excavator operator must always make use of the safety lever/ armrest whenever the slinger is in the danger area to avoid moving the controls by mistake. The hazards associated with travelling with a suspended load, particularly the presence of personnel adjacent to the machines direction of travel, must be considered, assessed and recorded on the lifting plan. All persons involved will wear hard hats, protective footwear and high-visibility clothing as a minimum. Lifts will not take place where there are persons working underneath the load, for example in a trench, and the excavator operator will not move the machine until he has satisfied himself that all persons, including the slinger/ signaller, have moved themselves to a position of safety. When attaching slings to the hooking device or lifting point, care must be taken to ensure that the slings and their attachments are able to hang free at all times, particularly when using a “D-Shackle” as it may limit rotation. Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP RISK ASSESSMENTS Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP LOCATION / PROJECT 1 Elm Park Road HAZARD / WORK ACTIVITY ASSESSED Construction of Lining Walls and Columns H = HIGH RISK, M = MEDIUM RISK, L = LOW RISK, I = INSIGNIFICANT SIGNIFICANT RISKS H M L I WHO MAY BE HARMED 1: Burns to the skin from wet concrete X EMPLOYEES 2: Burns to eyes from wet concrete X SUBCONTRACTORS 3: Sensitisation/ dermatitis X OFFICIAL VISITORS 4: Manual handling injuries X GENERAL PUBLIC 5: Falls from height X 6: Vibration X 7: Noise X 8: CONTROL MEASURES X X X Mobile Tower Scaffolds erected by PASMA trained persons to be used for work above ground. Team lifting to be used when moving/ installing shuttering and props. PPE to be worn as detailed below. 4” plastic pipes to be installed during GF slab and capping beam construction, allowing concrete to be poured from above ground, avoiding concrete pipework being routed through basement. First aid kit and eye wash to be kept close to work area in case of splashes and spurts. Water supply to be available for rinsing skin after contact with wet cement. Operatives to be made aware of the dangers associated with wet cement. Barriers and signage to be used to warn third parties and prevent them entering the work area. Ear defenders to be worn when using vibrating pokers. Job rotation to be implemented when using vibrating pokers. INFORMATION, INSTRUCTION AND TRAINING Only trained Operatives will clean concrete pipework. PERSONAL PROTECTIVE EQUIPMENT SAFETY HELMET SAFETY BOOTS GOGGLES / VISOR OVERALLS HI-VIZ AUTHORISATION COMPLETED BY South Downs Safety X X X X X EAR DEFENDERS RESPIRATORY PROTECTION GLOVES (EN374 butyl rubber or nitrile) EAR PLUGS SIGNATURE Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP X DATE 22.07.14 LOCATION / PROJECT 1 Elm Park Road HAZARD / WORK ACTIVITY ASSESSED Cleaning Concrete Pipes H = HIGH RISK, M = MEDIUM RISK, L = LOW RISK, I = INSIGNIFICANT SIGNIFICANT RISKS H M L I 1: Persons being struck by ball. X 2: Property being struck by ball X 3: Struck by moving pipework X 4: Failure of pressure valve X X 5: Concrete Burns X 6: 7: 8: CONTROL MEASURES WHO MAY BE HARMED EMPLOYEES SUBCONTRACTORS OFFICIAL VISITORS GENERAL PUBLIC X X X X All persons not directly involved in the operation will clear the area. Pipes to be restrained mechanically with pressure released prior to clip loosening. Retaining cage to be fixed to the end of the pie with a retaining clip. The cleaning ball to be damped with water and placed inside the pipe at the pump end. Air to be introduced gradually to prevent uncontrolled release of the ball. An operative will tap the pipe work with a hammer to aid release of concrete inside and to track the progress of the ball. When the ball is close to the end of the pipe, the pressure will be reduced to slow the speed at which the ball exits the pipework. Suitable PPE to be worn as identified below. INFORMATION, INSTRUCTION AND TRAINING Only trained Operatives will clean concrete pipework. PERSONAL PROTECTIVE EQUIPMENT SAFETY HELMET SAFETY BOOTS GOGGLES / VISOR OVERALLS HI-VIZ AUTHORISATION COMPLETED BY South Downs Safety X X X X X EAR DEFENDERS RESPIRATORY PROTECTION GLOVES (EN374 butyl rubber or nitrile) EAR PLUGS SIGNATURE Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP X DATE 22.07.14 LOCATION / PROJECT 1 Elm Park Road HAZARD / WORK ACTIVITY ASSESSED Disc Cutters/ Abrasive Wheels H = HIGH RISK, M = MEDIUM RISK, L = LOW RISK, I = INSIGNIFICANT SIGNIFICANT RISKS H M L I 1: Bursting of wheel or disc X 2: Contact with wheel or disc X 3: Entanglement X 4: Fire X 5: Dust X 6: Noise X 7: Vibration X 8 CONTROL MEASURES WHO MAY BE HARMED EMPLOYEES SUBCONTRACTORS OFFICIAL VISITORS GENERAL PUBLIC X X X The correct wheel/disc for the machine is to be used. The correct wheel/disc for the work is to be used. Suitable PPE will be worn, safety boots, gloves, hard hat, eye protection and dust masks. Clothes will be secured to prevent entanglement. Ties will not be worn. Ear protection is to be worn as necessary. Dust suppression measures will be used. Establish safe working area to prevent unauthorised access. Fire extinguishers to be kept close at hand (1no. CO2 & 1no.Foam) Daily vibration exposure limits outlined Company method statement to be followed. Job rotation to avoid exceeding daily vibration exposure limits. Do not use more than one piece of vibrating equipment unless the “trigger time” has been calculated. Wet cutting shall be employed when cutting all stone/ concrete. INFORMATION, INSTRUCTION AND TRAINING Only trained Operatives will change/mount abrasive wheels and discs. PERSONAL PROTECTIVE EQUIPMENT SAFETY HELMET SAFETY BOOTS GOGGLES / VISOR OVERALLS HI-VIZ AUTHORISATION COMPLETED BY South Downs Safety X X X EAR DEFENDERS RESPIRATORY PROTECTION GLOVES EAR PLUGS X X X X SIGNATURE Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP DATE 22.07.14 LOCATION / PROJECT 1 Elm Park Road HAZARD / WORK ACTIVITY ASSESSED Excavators & Excavations H = HIGH RISK, M = MEDIUM RISK, L = LOW RISK, I = INSIGNIFICANT SIGNIFICANT RISKS H M L I 1: Fire (machine) X 2: Service Strike X 3: Plant striking operatives X 4: Falls from height X 5: Excavation collapse X 6: Noise X 7 8 CONTROL MEASURES WHO MAY BE HARMED EMPLOYEES SUBCONTRACTORS OFFICIAL VISITORS GENERAL PUBLIC X X X CAT Scan and/ or consult drawings to discover locations of services No persons to work within 1.5metres of excavators reach Where it is likely that a person could fall a sufficient distance that it would cause injury, suitable edge protection to be installed. Flashing beacon to be used at all times when machine is moving. Ventilation/ extraction to be used where using excavators in confined spaces where Carbon Monoxide could build up. No excavators to be used within 2.75metres of overhead power lines. Stop blocks to be used when dumpers are tipping into excavations Excavations to be battered back to suitable angle of repose, trench boxes used or sheet piles/ shoring installed to prevent collapse. Ear defenders to be worn by operator and persons working close to machine when pecker/ breaker in use. Fuel to be stored in suitable container away from the work area. Machine to be switched off prior to re-fuelling. Machine to be refuelled using a suitable nozzle or funnel to prevent splashes or spills. INFORMATION, INSTRUCTION AND TRAINING Only persons holding valid CPCS qualification, or similar, to operate excavators. Only person holding valid Banksman’s certificate to direct plant operators. PERSONAL PROTECTIVE EQUIPMENT SAFETY HELMET SAFETY BOOTS GOGGLES / VISOR OVERALLS HI-VIZ AUTHORISATION COMPLETED BY South Downs Safety X X EAR DEFENDERS RESPIRATORY PROTECTION GLOVES EAR PLUGS X X SIGNATURE Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP DATE 22.07.14 LOCATION / PROJECT 1 Elm Park Road HAZARD / WORK ACTIVITY ASSESSED Use of Hand Tools H = HIGH RISK, M = MEDIUM RISK, L = LOW RISK, I = INSIGNIFICANT SIGNIFICANT RISKS H M L I 1: Fire X X 2: Flying objects X 3: Sharp edges X 4: Falls from height X 5: Slips, trips and falls X 6: Noise X 7: Manual handling X 8: Vibration X CONTROL MEASURES WHO MAY BE HARMED EMPLOYEES SUBCONTRACTORS OFFICIAL VISITORS GENERAL PUBLIC X X X A visual check to be carried out before use to check tools are in a safe condition eg No burrs, split, Handles, loose hammer heads, splayed spanner heads etc. and damaged tools to be repaired or replaced immediately All tools to be stored in a tool locker, tool box or removed from site when not in use Keep the work area tidy and clear of obstructions slipping and tripping hazards Suitable PPE to be provided and worn as needed including hand, eye and face protection Covers to be fitted to sharp edges such as Knife blades and saw edges when not in use Tools such as cutters and scissors to be kept In closed position when not in use For petrol operated tools, extinguishers to be available & fuel must be kept away from the work area in a suitable container. Vibration test to be consulted and “trigger time” not exceeded for each piece of equipment. Only 110v tools to be used. When using pneumatic tools, the compressor must have whip protection fitted. Damping down shall be employed wherever there is a risk of activities producing significant dust levels. INFORMATION, INSTRUCTION AND TRAINING Only persons holding relevant training certificate to use hand tools (where applicable). PERSONAL PROTECTIVE EQUIPMENT SAFETY HELMET SAFETY BOOTS GOGGLES / VISOR OVERALLS HI-VIZ AUTHORISATION COMPLETED BY South Downs Safety X X X EAR DEFENDERS RESPIRATORY PROTECTION GLOVES EAR PLUGS X X SIGNATURE Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP DATE 22.07.14 LOCATION / PROJECT 1 Elm Park Road HAZARD / WORK ACTIVITY ASSESSED Concrete Pouring H = HIGH RISK, M = MEDIUM RISK, L = LOW RISK, I = INSIGNIFICANT SIGNIFICANT RISKS H M L I 1: Burns to the skin from wet concrete X 2: Burns to eyes from wet concrete X 3: Sensitisation/ dermatitis X 4: Manual handling injuries X 5: Falls from height X 6: Vibration X 7: Noise X 8 CONTROL MEASURES WHO MAY BE HARMED EMPLOYEES SUBCONTRACTORS OFFICIAL VISITORS GENERAL PUBLIC X X X COSHH assessments and Health and Safety Data sheets will be issued to operatives before using hazardous substances Personal Protective Equipment to be issued and worn as identified on the COSHH Risk Assessment to prevent against burns to the skin and eyes Suitable clothing to be worn to protect the skin from cuts and abrasions Masks to be worn when mixing concrete Excavator to be used to lift concrete pipes or team lifting when not possible. First aid kit and eye wash to be kept close to work area in case of splashes and spurts. Water supply to be available for rinsing skin after contact with wet cement. Operatives to be made aware of the dangers associated with wet cement. Barriers and signage to be used to warn third parties and prevent them entering the work area. Excavator to be used to lift heavy items such as pile cages. Ear defenders to be worn when using vibrating pokers. Job rotation to be implemented when using vibrating pokers. INFORMATION, INSTRUCTION AND TRAINING Only trained persons to operate plant. PERSONAL PROTECTIVE EQUIPMENT SAFETY HELMET SAFETY BOOTS GOGGLES / VISOR OVERALLS HI-VIZ AUTHORISATION COMPLETED BY South Downs Safety X X X X X EAR DEFENDERS RESPIRATORY PROTECTION GLOVES (EN374 butyl rubber or nitrile) EAR PLUGS SIGNATURE Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP X X DATE 22.07.14 LOCATION / PROJECT 1 Elm Park Road HAZARD / WORK ACTIVITY ASSESSED Waste Removal/ Operation of Grab Lorries H = HIGH RISK, M = MEDIUM RISK, L = LOW RISK, I = INSIGNIFICANT SIGNIFICANT RISKS H M L I WHO MAY BE HARMED 1: Falling materials X EMPLOYEES 2: Grab striking property or equipment X SUBCONTRACTORS 3: Grab striking persons X OFFICIAL VISITORS 4: Falls from height X GENERAL PUBLIC 5: Entanglement X 6 7 8 CONTROL MEASURES X X X X Only plant holding a valid Thorough Examination certificate to be used on site. Banksman to ensure no operatives or members of the public come into contact with the vehicle or grab. Grab only to be operated when standing on flat, level ground. Only use grab when the operator has a clear view of the property and any surrounding equipment. No standing on the load or anywhere except a formal working platform with edge protection. Do not use grab for dragging/ moving the skip. No persons allowed within the working range of the grab or the crane arm. Do not overload the truck at any time. Do not drive away from site unless the bucket is in the down position and locked into place. Driver to reverse into site under instruction from a trained banksman. Banksman to ensure no members of the public are present during reversing operation. INFORMATION, INSTRUCTION AND TRAINING Only trained persons to operate grab lorries. PERSONAL PROTECTIVE EQUIPMENT SAFETY HELMET SAFETY BOOTS GOGGLES / VISOR OVERALLS HI-VIZ AUTHORISATION COMPLETED BY South Downs Safety X X X X EAR DEFENDERS RESPIRATORY PROTECTION GLOVES EAR PLUGS SIGNATURE Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP X DATE 22.07.14 LOCATION / PROJECT 1 Elm Park Road HAZARD / WORK ACTIVITY ASSESSED Work at Height H = HIGH RISK, M = MEDIUM RISK, L = LOW RISK, I = INSIGNIFICANT SIGNIFICANT RISKS H M L I 1: Falling materials X 2: Falls from height X 3: Collapse of access equipment X 4: Overturning of access equipment X 5: Manual handling injuries X 6 7 8 CONTROL MEASURES WHO MAY BE HARMED EMPLOYEES SUBCONTRACTORS OFFICIAL VISITORS GENERAL PUBLIC X X X Edges of all excavations to be protected with scaffold poles and combi-safe barriers. Mobile tower scaffolds or Class 1 industrial step ladders to be used for gaining access to work at height. Stepladders to be inspected for defects prior to use. Stepladders to be used on level ground only. Stepladders to be used in the fully open position with the retaining hinges engaged. Mobile tower scaffolds to be erected by competent persons only. Towers to be fitted with guard rails to 950mm, mid-rails leaving no unprotected gaps of more than 470mm and toe boards to 150mm. Outriggers to be used in accordance with manufacturers’ instructions. No materials to be stored on the working platform. Access to working platform to be via internal ladder only, not by climbing the outside of the tower. INFORMATION, INSTRUCTION AND TRAINING Only PASMA trained persons to erect tower scaffolds. PERSONAL PROTECTIVE EQUIPMENT SAFETY HELMET SAFETY BOOTS GOGGLES / VISOR OVERALLS HI-VIZ AUTHORISATION COMPLETED BY South Downs Safety X X EAR DEFENDERS RESPIRATORY PROTECTION GLOVES EAR PLUGS X X SIGNATURE Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP DATE 22.07.14 LOCATION / PROJECT 1 Elm Park Road HAZARD / WORK ACTIVITY ASSESSED Basement Construction H = HIGH RISK, M = MEDIUM RISK, L = LOW RISK, I = INSIGNIFICANT SIGNIFICANT RISKS H M L I 1: Falling materials X 2: Falls from height X 3: Structural Collapse X 4: Fumes X 5: Manual handling injuries X 6: Emergency Access X 7: Waste Removal X 8: CONTROL MEASURES WHO MAY BE HARMED EMPLOYEES SUBCONTRACTORS OFFICIAL VISITORS GENERAL PUBLIC X X X Edges of excavations to be protected with scaffold poles and combi-safe barriers to a minimum height of 950mm No persons to work beneath excavator while removing spoil. Excavators working in basement to have catalytic converters and CO2 filters fitted. Excavators to have valid Thorough Examination Certificate present. Excavators to be operated by CPCS trained persons. Access into basement to be via a securely tied ladder. Temporary propping to be installed as per method statement and engineer’s details. Forced air ventilation/ extraction to be fitted. Excavators and Genie lifts to be used to raise/ lower heavy items. Mobile tower scaffolds to be used for access to height once in excavation. Suitable 110v task lighting to be provided, fixed at high level to avoid trailing cables. INFORMATION, INSTRUCTION AND TRAINING Only PASMA trained persons to erect tower scaffolds. Only CPCS trained persons to operate excavators. PERSONAL PROTECTIVE EQUIPMENT SAFETY HELMET SAFETY BOOTS GOGGLES / VISOR OVERALLS HI-VIZ AUTHORISATION COMPLETED BY South Downs Safety X X EAR DEFENDERS RESPIRATORY PROTECTION GLOVES EAR PLUGS X X SIGNATURE Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP DATE 22.07.14 LOCATION / PROJECT 1 Elm Park Road HAZARD / WORK ACTIVITY ASSESSED Pile Removal Using an Excavator H = HIGH RISK, M = MEDIUM RISK, L = LOW RISK, I = INSIGNIFICANT SIGNIFICANT RISKS H M L I WHO MAY BE HARMED 1: Fire (machine) X EMPLOYEES 2: Service Strike X SUBCONTRACTORS 3: Plant striking operatives X OFFICIAL VISITORS 4: Flying Debris X GENERAL PUBLIC 5: Vibration X 6: Noise X 7: Build up of CO² X 8 CONTROL MEASURES X X X Safe zone to be demarcated around the pile being removed. No persons to work within 1.5metres of excavators reach Flashing beacon to be used at all times when machine is moving. Ventilation/ extraction to be used where using excavators in confined spaces where Carbon Monoxide could build up. Gas monitor to be used in accordance with agreed procedure and risk assessment. Goggles to be worn by excavator driver. Ear defenders to be worn by operator and persons working close to machine when pecker/ breaker in use. Fuel to be stored in suitable container away from the work area. Machine to be switched off prior to re-fuelling. Machine to be refuelled using a suitable nozzle or funnel to prevent splashes or spills. RESIDUAL RISK INFORMATION, INSTRUCTION AND TRAINING LOW Only persons holding valid CPCS qualification, or similar, to operate excavators. Only person holding valid Banksman’s certificate to direct plant operators. PERSONAL PROTECTIVE EQUIPMENT SAFETY HELMET SAFETY BOOTS GOGGLES / VISOR OVERALLS AUTHORISATION COMPLETED BY South Downs Safety X X X EAR DEFENDERS RESPIRATORY PROTECTION GLOVES HI-VIZ SIGNATURE Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP X X DATE 22.07.14 COSHH ASSESSMENTS Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP Project 1 Elm Park Road Substance or Item Cement / Concrete dust Use Production of Mortar and Concrete Location of Use Confined Space Inside Restricted Hazardous Contents Mixture of cement and pulverised ash or similar. Fine and course aggregate. Water. IRRITANT Route of Exposure Skin First Aid TOXIC HARMFUL Eyes Outside Restricted CORROSIVE Eyes Open Air FLAMMABLE Inhalation Eyes Wash immediately with water and seek medical attention Skin Wash with soap and water, seek medical attention if symptoms persist Ingestion Move to fresh air, give nothing by mouth and seek medical attention Inhalation Move to fresh air, seek medical attention if symptoms persist Personal Protective Equipment Gloves Yes to EN374 (butyl rubber or nitrile) Respiratory Yes, if mixing in confined space Clothing Trousers and long sleeves, wellingtons if standing in concrete during pour. Eye Protection Yes where risks of splashes/ spurts. Waste Disposal / Storage Spillage/release Allow to dry and transfer into suitable container. Disposal Can be disposed of in skip as general waste Fire Flash point N/A Extinguishers N/A Further Information HEALTH RISKS: - EYES: Can cause severe irritation, burns and long-term damage. - SKIN: Can cause irritant and allergic dermatitis as well as severe burns. - INHALATION: May cause irritation to eyes and respiratory tract - INGESTION: May cause irritation and sickness Completed By Signature Date South Downs Safety 22.07.14 Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP EXPLOSIVE Cuts Project Substance or Item Use Location of Use Confined Space Hazardous Contents Catalytically cracked oils. 1 Elm Park Road Diesel Refuelling Inside Restricted Outside Restricted IRRITANT Route of Exposure Skin First Aid TOXIC HARMFUL Eyes Wash immediately with water and seek medical attention Eyes CORROSIVE Skin Open Air FLAMMABLE Eyes Skin Wash with soap and water, seek medical attention if symptoms persist Ingestion Move to fresh air, give nothing by mouth and seek medical attention Inhalation Move to fresh air, seek medical attention if symptoms persist Personal Protective Equipment Gloves Yes to EN374 (butyl rubber or nitrile) Respiratory N/A Clothing Trousers and long sleeves. Eye Protection Yes where risks of splashes/ spurts. Waste Disposal / Storage Spillage/release Absorb with sand or similar and transfer into suitable container. Disposal Must be disposed of as hazardous waste as toxic to aquatic organisms. Fire Flash point 52˚c - 96˚c Extinguishers CO2, Dry Powder or Foam. Further Information Refuelling only to take place in well ventilated areas and remove all sources of ignition prior to refuelling No smoking at any time while refuelling or near fuel containers. Wash hands before eating or drinking. Spill kit(s) to be available at re-fuelling points Completed By South Downs Safety Signature Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP Date 22.07.14 EXPLOSIVE Skin Project 1 Elm Park Road Substance or Item Mould Oil Use Coating/ Release of Concrete Shuttering Location of Use Confined Space Inside Restricted Outside Restricted Hazardous Contents Mesitylene <1.0% 1,2,4-Trimethylbenzene <1.0% Straight Run Kerosene 5-10% Solvent Naptha (Petroleun), Medium Aliph IRRITANT Route of Exposure Skin First Aid TOXIC HARMFUL Eyes CORROSIVE Eyes Open Air FLAMMABLE Inhalation Eyes Wash immediately with water and seek medical attention Skin Wash with soap and water, seek medical attention if symptoms persist Ingestion Move to fresh air, give nothing by mouth and seek medical attention Inhalation Move to fresh air, seek medical attention if symptoms persist Personal Protective Equipment Gloves Yes to EN374 (butyl rubber or nitrile) Respiratory Yes, if mixing in confined space Clothing Trousers and long sleeves, wellingtons if standing in concrete during pour. Eye Protection Yes where risks of splashes/ spurts. Waste Disposal / Storage Spillage/release Allow to dry and transfer into suitable container. Disposal Can be disposed of in skip as general waste Fire Flash point N/A Extinguishers N/A Further Information HEALTH RISKS: - EYES: Can cause mild irritation and redness. - SKIN: Can cause mild irritation and redness. Long term exposure could lead to contact dermatitis. - INHALATION: May cause irritation to eyes and respiratory tract - INGESTION: May cause irritation and sickness Completed By Signature Date South Downs Safety 22.07.14 Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP EXPLOSIVE Cuts Project 1 Elm Park Road Substance or Item Hydraulic Oil Use Maintenance of Plant Location of Use Confined Space Inside Restricted Hazardous Contents C15 – C19 Alkanes <1% Zn dialkyldithiophoshate <1% Alkylphenol, Synthetic, neutral <1% Calcium petroleum sulphonate <1% IRRITANT Route of Exposure Skin First Aid TOXIC Outside Restricted HARMFUL Eyes CORROSIVE Eyes Open Air FLAMMABLE Inhalation EXPLOSIVE Cuts Eyes Wash immediately with water and seek medical attention Skin Wash with soap and water, seek medical attention if symptoms persist Ingestion Move to fresh air, give nothing by mouth and seek medical attention Inhalation Move to fresh air, seek medical attention if symptoms persist Personal Protective Equipment Gloves Yes to EN374 (butyl rubber or nitrile) Respiratory N/A Clothing No specific clothing requirements Eye Protection Yes where risks of splashes/ spurts. Waste Disposal / Storage Spillage/release Allow to dry and transfer into suitable container. Disposal Not classified as hazardous and can be disposed of in skip as general waste Fire Flash point Not classified as flammable but is combustible. Extinguishers CO2 Further Information This product is not classified as hazardous under current UK Health and Safety and Environmental legislation, for the application for which it was intended. This product is of low oral and dermal toxicity and under normal conditions of use should present no health hazards. However, in common with most mineral oils, prolonged and repeated skin contact may cause dermatitis and the risk of skin disorders may be increased if the product has become contaminated. Completed By Signature Date South Downs Safety 22.07.14 Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP Project 1 Elm Park Road Substance or Item Chemical Resin Use Fixing/ Anchoring Rebar Location of Use Confined Space Inside Restricted Hazardous Contents Urethanmethacrylate oligomer 10-20% Methacrylic acid, monoester with propane-1,2-diol 5-10% Dibenzoyl peroxide 10-15% IRRITANT Route of Exposure Skin First Aid TOXIC Outside Restricted HARMFUL Eyes CORROSIVE Eyes Open Air FLAMMABLE Inhalation EXPLOSIVE Cuts Eyes Wash immediately with water and seek medical attention Skin Wash with soap and water, seek medical attention if symptoms persist Ingestion Move to fresh air, do not induce vomiting, give nothing by mouth and seek medical attention Inhalation Move to fresh air, seek medical attention if symptoms persist Personal Protective Equipment Gloves Yes to EN374 (butyl rubber or nitrile) Respiratory Full face mask with charcoal filter if used in high concentrations. Mask with FFPV3 filter for short term. Clothing Trousers and long sleeves, wellingtons if standing in concrete during pour. Eye Protection Yes with side protection where risks of splashes/ spurts. Waste Disposal / Storage Spillage/release Allow to dry and transfer into suitable container. Disposal In accordance with waste code 15 01 10; packaging containing residues of or contaminated by dangerous substances. Fire Flash point Not known but combustion gases principally have to be considered as toxic substances. Extinguishers CO2 Further Information HEALTH RISKS: - EYES: Classified as irritating to eyes. - SKIN: Can cause sensitisation by skin contact.. - INHALATION: Harmful by inhalation and may cause irritation to eyes and respiratory tract - INGESTION: May cause irritation and sickness Completed By Signature Date South Downs Safety 22.07.14 Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP Project 1 Elm Park Road Substance or Item Rock Oil Lithium EP2 Use Greasing Plant Location of Use Confined Space Inside Restricted Hazardous Contents Zinc Dialkyldithiophosphate <10% IRRITANT Route of Exposure Skin First Aid TOXIC Outside Restricted HARMFUL Eyes CORROSIVE Eyes Open Air FLAMMABLE Inhalation EXPLOSIVE Cuts Eyes Wash immediately with water and seek medical attention if blinking or redness persists. Skin Wash with soap and water and rinse thoroughly. Ingestion Move to fresh air, do not induce vomiting, give nothing by mouth and seek medical attention Inhalation Move to fresh air, seek medical attention if symptoms persist Personal Protective Equipment Gloves Yes to EN374 (butyl rubber or nitrile) Respiratory N/A Clothing Trousers and long sleeves. Eye Protection Yes where risks of splashes/ spurts. Waste Disposal / Storage Spillage/release Allow to dry and transfer into suitable container. Disposal Can be disposed of in skip as general waste Fire Flash point >200°C Extinguishers Water. Further Information Non-flammable. Not classified as hazardous under EC regulations and not expected to present a significant hazard under anticipated conditions or normal use. No expected symptoms in relation to any health effects. Completed By South Downs Safety Signature Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP Date 22.07.14 Project 1 Elm Park Road Substance or Item Stihl HP “-Stroke Oil Use Fuel additive for plant and petrol powered tools. Location of Use Confined Space Inside Restricted Outside Restricted Hazardous Contents Non-hazardous mixture of base oils and additives. IRRITANT Route of Exposure Skin First Aid TOXIC HARMFUL Eyes CORROSIVE Ingestion Open Air FLAMMABLE Inhalation EXPLOSIVE Cuts Eyes Wash immediately with water and seek medical attention if blinking or redness persists. Skin Wash with soap and water and rinse thoroughly. Ingestion Move to fresh air, do not induce vomiting, give nothing by mouth and seek medical attention Inhalation Move to fresh air, seek medical attention if symptoms persist Personal Protective Equipment Gloves Yes to EN374 (butyl rubber or nitrile) Respiratory N/A Clothing Trousers and long sleeves. Eye Protection Yes where risks of splashes/ spurts. Waste Disposal / Storage Spillage/release Allow to dry and transfer into suitable container. Disposal Can be disposed of in skip as general waste Fire Flash point >260°C Extinguishers Water or foam. Further Information Non-flammable. Not classified as hazardous under EC regulations and not expected to present a significant hazard under anticipated conditions or normal use. No expected symptoms in relation to any health effects. Would release Carbon Monoxide (CO) in the event of burning. Completed By South Downs Safety Signature Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP Date 22.07.14 Project 1 Elm Park Road Substance or Item Fosroc Cebex 100 Use Concrete additive for dry packing underpins Location of Use Confined Space Inside Restricted Outside Restricted Hazardous Contents Silica Sand 60-100% Calcium Lignosulphonate Powder 10-30% Aluminium Powder (Stabilised) <1% IRRITANT Route of Exposure Skin First Aid TOXIC HARMFUL Eyes CORROSIVE Ingestion Open Air FLAMMABLE Inhalation EXPLOSIVE Cuts Eyes Wash immediately with water and seek medical attention if blinking or redness persists. Skin Wash with soap and water and rinse thoroughly. Ingestion Move to fresh air, do not induce vomiting, drink plenty of water or milk and seek medical attention Inhalation Move to fresh air, seek medical attention if symptoms persist Personal Protective Equipment Gloves Yes to EN374 (butyl rubber or nitrile) Respiratory Yes, with P2 filter as minimum. Clothing Trousers and long sleeves. Eye Protection Yes where risks of splashes/ spurts. Waste Disposal / Storage Spillage/release Allow to dry and transfer into suitable container. Disposal Can be disposed of in skip as general waste Fire Flash point >260°C Extinguishers Water or foam. Further Information Non-flammable. Dust may irritate throat and respiratory system and cause coughing. Not likely, due to the form of the product. Ingestion may cause severe irritation of the mouth, the oesophagus and the gastrointestinal tract. Dust has an irritating effect on moist skin. Prolonged contact with wet cement/mixture may cause burns. Dust or splashes from the mixture may cause permanent eye damage. Immediate first aid is necessary. Frequent inhalation of dust over a long period of time increases the risk of developing lung diseases. Completed By South Downs Safety Signature Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP Date 22.07.14 Project Substance or Item Use Location of Use Confined Space Hazardous Contents Benzene <1% N-hexane <5% Toluene <10% Gasoline >90% IRRITANT Route of Exposure Skin First Aid 1 Elm Park Road Petrol Refuelling Plant & Equipment Inside Restricted TOXIC Outside Restricted HARMFUL Eyes CORROSIVE Eyes Open Air FLAMMABLE Inhalation Eyes Skin EXPLOSIVE Cuts Wash immediately with water and seek medical attention. Remove contaminated clothing and wash with soap and water and rinse thoroughly. Amy injection of petrol under the skin should be considered a medical emergency. Ingestion Move to fresh air, do not induce vomiting, give nothing by mouth and seek medical attention Inhalation Remove to fresh air, keep the patient warm and at rest. If breathing is irregular or stopped, give nothing by mouth and administer CPR and seek medical attention. Personal Protective Equipment Gloves Yes to EN374 (butyl rubber or nitrile) Respiratory Yes with FFPV3 filter if area is poorly ventilated. Clothing Trousers and long sleeves. Eye Protection Yes where risks of splashes/ spurts. Waste Disposal / Storage Spillage/release Allow to dry and transfer into suitable container. Disposal Remove all sources of ignition immediately. Contain and collect spillage with non-combustible absorbent materials, (e.g. sand, earth, vermiculite) place in a suitable container for disposal in accordance with the waste regulations. Storage Store minimum quantities possible in Flame-proof, ventilated steel container with spill kits and extinguishers kept adjacent to storage. Fire Flash point 40° Extinguishers Foam, dry chemical powder, carbon dioxide, water spray Further Information Hazardous decomposition products include smoke, sulphur oxides and carbon monoxide. Extremely flammable, high hazard. The liquid can release vapours at temperatures below ambient which form flammable mixtures. Vapours settle to ground level and may reach ignition sources remote from the point of escape via drains and underground passages. Static discharge material can accumulate static charges which may cause an incendiary electrical discharge. Completed By South Downs Safety Signature Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP Date 22.07.14 Project Substance or Item Use Location of Use Confined Space Hazardous Contents 1 Elm Park Road Arco Line Marking Spray Paint Marking Lines/ Setting Out Inside Restricted Outside Restricted Open Air Mixed Aromatic Hydrocarbons 10 2-Butoxyethanol 5-10% 1-Methoxy-2-Propanol 5-10% Propan-2-one 40-60% Butane 10-30% Propane 10-30% IRRITANT Route of Exposure Skin First Aid TOXIC HARMFUL Eyes CORROSIVE Ingestion FLAMMABLE Inhalation EXPLOSIVE Cuts Eyes Skin Ingestion Inhalation Wash immediately with water and seek medical attention. Remove contaminated clothing and wash with soap and water and rinse thoroughly. Move to fresh air, do not induce vomiting, give nothing by mouth and seek medical attention Remove to fresh air, keep the patient warm and at rest. If breathing is irregular or stopped, give nothing by mouth and administer CPR and seek medical attention. Personal Protective Equipment Gloves Yes to EN374 (butyl rubber or nitrile) Respiratory Yes with FFPV3 filter if area is poorly ventilated. Clothing Trousers and long sleeves. Eye Protection Yes where risks of splashes/ spurts. Waste Disposal / Storage Spillage/release Allow to dry and transfer into suitable container. Disposal Contain and collect spillage with non-combustible absorbent materials, (e.g. sand, earth, vermiculite) place in a suitable container for disposal in accordance with the waste regulations. Storage Store away from direct sunlight and any potential sources of heat or ignition. Fire Flash point Unknown. Extinguishers Alcohol resistant foam, CO², water spray (do not use water jet) Further Information Vapours are heavier than air and may spread along floors. Vapours may form explosive mixture with air. Fire may produce dense black smoke containing hazardous combustion products. Decomposition products may be a hazard to health. Do not allow run-off from fire fighting to enter drains or water courses. Completed By South Downs Safety Signature Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP Date 22.07.14 Project 1 Elm Park Road Substance or Item Tu-Chem Ecotard Use Concrete Retarder Location of Use Confined Space Inside Restricted Hazardous Contents None but contains nipacide cfx/3. IRRITANT Route of Exposure Skin First Aid TOXIC Outside Restricted HARMFUL Eyes CORROSIVE Ingestion Open Air FLAMMABLE Inhalation EXPLOSIVE Cuts Eyes Wash immediately with water and seek medical attention if symptoms persist. Skin Remove contaminated clothing and wash with soap and water and rinse thoroughly. Ingestion Wash with water if irritation occurs. Inhalation Should produce no symptoms but consult a Doctor if presenting any symptoms. Personal Protective Equipment Gloves Yes to EN374 (butyl rubber or nitrile) Respiratory N/A Clothing N/A Eye Protection If risk of splashes or spurts. Waste Disposal / Storage Spillage/release Allow to dry and transfer into suitable container. Disposal Contain and collect spillage with non-combustible absorbent materials, (e.g. sand, earth, vermiculite) place in a suitable container for disposal in accordance with waste code 16 03 06. Storage Store away from direct sunlight and any potential sources of heat or ignition. Fire Flash point Product does not support combustion. Extinguishers N/A Further Information Avoid excessive heat as in combustion toxic fumes can be emitted. Avoid strong oxidising agents and acids. Completed By South Downs Safety Signature Tel 020 8732 3030 Fax 020 8203 8143 www.trenchco.co.uk Trenchco Ltd - 499 Watford Way, Mill Hill, London NW7 2QP Date 22.07.14