Uploaded by Jason Castro

EXTENSION OF THE WRITTEN ASSIGNMENT TO THE LITTLEFIELD PROJECT copy copy

advertisement
What the maximum number jobs per day an individual machine at each station can process (i.e., what is
the capacity of machines at each station)?
Resources
Machine at Station 1
Machine at Station 2
Machine at Station 3
Number of Kits
2
2
2
Utilization
20%
14%
39%
Capacity
2=.20x, x=10units/day
2= .14x, x= 14
2= .39, x= 5
How many machines you would need at each station to meet the demand at peak level (after day 180)?
Resources
Demand at peak level
Capacity per machine
Machine at Station 1
Machine at Station 2
Machine at Station 3
26
26
26
10 kits/day
14 kits/day
5 kits/day
# of resources needed
to meet demand
(rounded up)
26/10= 3
26/14= 2
26/5= 6
Download