Lab Work Exercise, MS Project 2016, Project Management [ITDB 3111] Using MS-Project 2016 and critical path techniques, schedule the various tasks of Sur Refineries L.L.C., project properly. Assume that the projects’ starts on 01st Nov 2017. Duration for task Resources Task Name Completion Predecessors J1 8 weeks --- R1,R2 J2 30 days --- R3 J3 15 weeks J2 SS, J1 FS R4 J31 3 weeks J2 J32 12 weeks J1 J4 3 months J2 FS, J3 SS R5 J5 22 days --- R6 J6 5 weeks J4 FF, J5 SS J7 20 months J5,J6 J71 8 months J4 J72 12 months J5 J8 12 weeks J9 180 days J10 2 months J2 FS,J5 SS,J7 FF J8 J7, J8 (End) R2,R1 R5 R3 R5,R6 R1,R3,R5,R6 a) In your project calendar, set working days are from Sunday to Thursday (9am – 12.30pm) and (1.30 pm – 5pm), all Fridays are full-day holiday and all saturays are half-working day in the afternoon. Set the hourly pay as RO: 6/hr and RO: 12/hr for over time after the working hours. Assign the subtasks, its dependencies and resources required for your project tasks. Assume that R1, R3 as employees; R2, R5 as physical resources; R4, R6 as software/ internet resources. Also assume that the resources R1, R6 are available for sharing with one other team or project only. b) Create its Network diagram, Tracking Gantt chart and save them in your exam folder as two different files. Set the milestones for tasks Ph3, Ph5 & Ph8 and show them in your project timeline. Page 1 of 2 c) Analyze and determine the minimum critical path using PERT chart, which is required for completing this entire project. Page 2 of 2