ARC7051: Construction Law – Dispute Resolution Adjudication Report Group 14 Wei Hao Su Austin Byrne Khurram Shahzad DISPUTE IN RELATION TO CONSTRUCTION PROJECT LEADING TO ADJUDICATION BETWEEN Clear Cladding Ltd. Referring Party -and - CPM Developments Responding Party THE ADJUDICATORS DECISION Dated 21st June 2013 Overview The referring party Clear Cladding Ltd. have been employed by CPM Developments to undertake the design, manufacture and installation of cladding to the newly developed Manor Shopping Complex situated on the Malone Road, Belfast. CPM Developments requires the works to be completed by the 3rd of May 2013 in time for the grand opening. A tender price of £140,000 plus VAT was agreed between the two parties. A contract was drawn up on the 27th of March 2013 to agree the terms of the tender submission and an instruction issued to Clear Cladding to proceed with the design, manufacture and installation of the cladding. Clear Cladding was notified on the 1st of April 2013 that authorisation had been given to proceed on site for the purpose of obtaining measurements with installation to proceed from the 15th of April 2013. CPM Developments requested the cladding installation to be completed by Friday the 26 th of April, one week before the grand opening on the 3rd of May 2013. On the 19th of April Clear Cladding issued correspondence to CPM Developments outlining the problems they encountered when they arrived on site on the 15 Th April 2013. Clear Cladding arrived on site equipped with a large crew of workers and the necessary resources and equipment to commence installation of the external cladding panels. However, due to the construction of a footpath adjacent to the area of cladding, they were unable to gain access to commence installation. Clear Cladding also outlined a problem in the steel support system provided by CPM Developments. The design provided for the steel support system as highlighted is correspondence from Clear Cladding Ltd dated 8 th May 2013, was in contrast to that 1|Page which was detailed at the tender stage. In order to suit the changes in the steel support system, Clear Cladding had to refabricate a number of the panels to suit the layout of the joints in the structure. The cost of this remanufacture was £35,000 plus VAT of additional costs that Clear Cladding would have to pass on to the client CPM Developments. CPM Developments refute the additional claim of £35,000 as they believe this alteration is the responsibility of Clear Cladding Ltd. Due to the delays and required alterations, Clear Cladding was unable to complete the work by 26th April. This resulted in the grand opening date being postponed by one week until 10th May with a cost of £10,000 plus VAT to cover the cost of readvertising. CPM Developments claim in their correspondence of 10th May 2013 that the delay is the responsibility of Clear Cladding Ltd. Clear Cladding Ltd submitted a claim to cover the cost of the delay of £5,000 plus VAT and a further £35,000 plus VAT for the remanufacturing of the cladding panels. In total, the cost invoiced to CPM Developments by Clear Cladding Ltd is £180,000 plus VAT. CPM Developments Ltd agree to pay for the cladding works undertaken at Manor Shopping Complex minus the deduction of costs incurred for re-advertising of £10,000 plus VAT, leaving a closing balance of £130,000 plus VAT. Clear Cladding Ltd refuses to accept any reduction in settlement. As a result of this disagreement in final payment, both parties agreed to proceed with adjudication. 2|Page Introduction The two parties in dispute are: Clear Cladding Ltd, of New Forge Lane, Belfast, Northern Ireland (the Referring Party) CPM Developments of 21 Stranmillis Road, Belfast, Northern Ireland (the Responding Party). 2. The Parties referred to above entered into a contract on the 27 th March 2013 with an agreed price of £140,000 plus VAT for the design, manufacture and installation of external cladding works to be undertaken at Manor Shopping Complex, Malone Road, Belfast, Northern Ireland (“the Works”). 3. An invitation to tender for the proposed contract was offered by CPM Developments to Clear Cladding Ltd on 11th March 2013 and responded to by correspondence dated 22nd march 2013. CPM Developments subsequently accepted the tender price of £140,000 plus VAT in correspondence issued to Clear Cladding Ltd dated 27th March 2013. 4. Clear Cladding notified CPM Developments of their intention to refer the matter to adjudication if payment is not forthcoming in correspondence dated 28 th May 2013. 5. A Notice of Adjudication was issued by Clear Cladding Ltd to CPM Developments dated 10th June 2013. 6. Peter Stevens of 51 Malone Road, Belfast was appointed as adjudicator by agreement of Clear Cladding Ltd and CPM Developments dated 12th June 2013. This document represents the decision of Peter Stevens in relation to the dispute. 3|Page Conduct of the Adjudication 6. A written contract was entered into by both parties. As this was dated after 1 st June 1999, the Housing Grants, Construction and Regeneration Act, 1996 (Construction Contract NI Order 1997) and the Scheme for Construction Contracts in Northern Ireland Regulations (NI) 1999 apply. 7. Clause 3.1 (a) under the Construction Contract NI Order 1997 applies as the contract involves construction operations. 8. Clause 5.1, which relates to agreements with residential occupiers will not apply as the contract is between a developer and contractor. 9. Clear Cladding Ltd issued a notice of adjudication on 10th June 2013. 10. I agreed to act as adjudicator and notified both parties on 12th June 2013. 11. I received a response from Clear Cladding Ltd, the referring party on 14 th June 2013 together with further information relevant to the dispute. 12. The 21st of June was set for the Adjudication session with both parties having to sign an agreement to proceed. 13. The matters that are in dispute are outlined in this document. 14. I understand that the matters in dispute are outlined and referred to in the Notice of Adjudication dated 10th June 2013. 15. The Referring Party are also claiming for additional works and loss of time. 4|Page 16. Having carried out a review of the information provided, I believe the dispute to be “what sum, if any is due to the Referring Party in relation to additional works carried out between 27th March 2013 and 8th May 2013”. 17. In order to resolve the dispute, there are a number of issues that must be agreed. These issues as derived from the notice of adjudication submitted by the referring party. 1. Has the referring party received payment for the amount stated in the contract? 2. Is the responding party liable for the cost of delay on site of £5,000 plus VAT? 3. Whose responsibility is the design of the steel support? 4. Is the sum of £35,000 plus VAT a realistic cost for the issue with the design of the steel support or the sum of £10,000 plus VAT a realistic cost of delay? 5. The costs for the adjudication. Issue 1: Has the referring party received payment for the amount stated in the contract? 18. In light of documents provided, there was no payment made by CDM developers to referring party as both parties were not agreed on a final sum. 19. The responding party stated that from the works completed a closing balance of £130,000 plus VAT will be paid. 5|Page 20. This closing balance is in comparison to the initial agreed fee £140,000 minus a deduction of £10,000 plus VAT for re-advertising and breach of contract as requested by the responding party. Issue 2: Is the responding party liable for the cost of delay on site of £5,000 plus VAT? 21. The contract documents indicated that referring party (Clear Cladding Ltd) proceeded on site on 15th April to start installation of the cladding. 22. On arrival on site it was evident that footpath construction was in progress adjacent to the location of the cladding works. For this reason Clear Cladding Ltd were unable to begin the cladding works and left the site. 23. Responding party (CPM Developments) claimed that according to their site manager, Clear Cladding could have gained access by squeezing through the footpath works.. 24. The responding party (CPM Developments) site manager’s duty was to check the site at a prior date and to be aware of the issue before the referring party (Clear Cladding Ltd) arrived on-site 25. Perusal of the contract would indicate that it would be reasonable for Clear Cladding to expect a clear uninterrupted access to the site on the 15th April 2013. Issue 3: Whose responsibility is the design of the steel support? 26. It was clearly stated in the contract documents provided that the referring party (Clear Cladding Ltd) would undertake the design, manufacture and installation of the 6|Page cladding. The responding party (CPM Developments) stated within the contract that they would provide the steel support system to facilitate external cladding on site. 27. Referring party (Clear Cladding) identified a problem in the design of the steel support which caused an issue in the joints of the cladding whilst on site on the 15th April 2013, stating that this differed from that detailed at the tender stage. 28. The responding party (CPM Developments) failed to accept the suggestion of the referring party (Clear Cladding) stating that they neglected to consider the jointing detail in the structural steel system. No evidence was provided to support these rejections. Issue 4: Is the sum of £35,000 plus VAT a realistic cost for the issue with the design of the steel support or the sum of £10,000 plus VAT a realistic cost of delay? 29. A design flaw in the steel support was identified by Clear Cladding Ltd which resulted in the joints being incompatible with the steel cladding. 30. The responding party (CPM Developments) claimed that the referring party (Clear Cladding) overlooked the jointing detail which resulted in the refabricating of a number of panels. The referring party (Clear cladding) proceeded to undertake the work without providing the client with an early warning and an indication of the associated costs submitted through invoices and records. 31. There was no amendment to the contract to cover the additional costs. The referring party completed the works on the presumption that fair valuation would be recoverable. 7|Page 32. In consultation with a number of experts from the industry, a “Reasonable Persons Test” was carried out. The value of £20,000 was agreed to be a fair price for the works completed. Issue 5: The costs of adjudication. 33. I have spent 30 working hours on this case at a cost of £375.00 plus VAT per hour. A total of £11,250 exclusive of VAT is due in respect of costs. 8|Page Adjudicators’ decision 34. Therefore, I as adjudicator conclude the following: 1. It was the negligence of the responding party (CPM Developments) to alter the steel support system without notifying the referring party (Clear Cladding Ltd.). Therefore the responding party (CPM Developments) shall pay the sum of £20,000 plus VAT to the referring party (Clear Cladding Ltd.) for the prefabrication of the panels. 2. The responding party (CPM Developments) shall pay £5000 plus VAT to referring party (Clear Cladding Ltd.) for the time delayed on site. 3. The referring party (Clear Cladding Ltd.) are not liable to pay £10,000 plus VAT to responding party (CPM Developments) for re-advertising costs. 4. The responding party (CPM Developments) shall pay the interest on all outstanding monies at the appropriate rate, to the referring party (Clear Cladding Ltd). 5. I am allowing the responding party (CPM Developments) 21 working days to make financial arrangements for above payments to be made to the referring party (Clear Cladding Ltd). 6. Both parties shall pay my fees in equal share (50:50) as agreed upon appointment. I hereby give my permission to both parties if they wish to apply to the court for an order requiring compliance with this decision as agreed on appointment. Signed: _____________________ Mr Peter Stevens 9|Page Date: 21st June 2013. 10 | P a g e