METHOD STATEMENT TARPING & DE-TARPING SYSTEM CONTRACT No.:139-CO3 1. SITE PREPARATION FOR SUPPORT INSDUSTRIES, STAGE-4 REV.: 01 PURPOSE: This Safety Standard has been developed to prevent injuries from workers and reduce losses due to property and/or equipment damage. 2. SCOPE OF WORK: This Scope of work is for Tarping & Untarping of trucks/trailers on site to ensure all the execution shall be in Accordance to the Royal Commissions standard and specification. 3. PROTECTIVE EQUIPMENTS: List of Protective Equipment (PPE’s) 1.0 Hard Hat 2.0 Harness/Retractable Lanyard 3.0 Safety Shoes 4.0 Gloves 5.0 Safety Glasses Dark/Clear 6.0 High Visibility Vest 4. DIFINATIONS: Client : Royal Commission for Jubail Consultant : RGCK Association/SABCO Contractor : M.M. Al-Harbi & Partners Co., Ltd. Project Name : Site Preparation for Support Industries Stage-4 METHOD STATEMENT TARPING & DE-TARPING SYSTEM CONTRACT No.:139-CO3 5. SITE PREPARATION FOR SUPPORT INSDUSTRIES, STAGE-4 REV.: 01 RESPONSIBILITIES: 5.1 Project Manager: Project Manager bears the final responsibility for the Safety and Quality of actual execution of works as well as zero injury during construction. 5.2 Construction Manager Construction Manager is responsible for managing manpower, equipment and material involved in construction and establishing/expediting progress plans. Further, technical problems that may arise at sites shall be resolved and supports be provided to suffice the conditions specified in the drawing. 5.3 Safety Manager Safety Manager Ensure the project is constructed in a way that minimizes its environmental impacts and maximizes workers safety and health. 6. WORK METHODOLOGY: 6.01 TARPING: After the Approval of Royal Commission of the Tarping & De-Tarping System proposed which serves as a pre-required document prior to start the execution of sand materials from borrow pit, then execution of the works shall proceed as follows; 6.01.1 Safety officer to undergo Safety Induction seminar to the workers especially working on height. 6.01.2 Construction ensure that have Tarping Station at Borrow pit area. 6.01.3 Construction supervisor ensure that have personnel, checker/tallymen have records and monitoring of every trips at site. 6.01.4 Checker/Tallymen must wearing complete PPE with harness retractable lanyard at all times. METHOD STATEMENT TARPING & DE-TARPING SYSTEM CONTRACT No.:139-CO3 SITE PREPARATION FOR SUPPORT INSDUSTRIES, STAGE-4 REV.: 01 6.01.5 To ensure the safety of all personnel at the top of tarping station while removing/covering green mesh net behind the bucket to the harness lanyard should be replaced with retractable appropriate in the distance from the ground. 6.01.6 Checker/Tallymen on the Tarping Station at borrow pit must have a record of all approved trailers and permits. 6.01.7 The personnel involved in tarping/untarping process needs to comply with the followings: Standing on a platform at all times. Platform’s height 4 meters. Must be hooked the safety harness at the dedicated rails attached on the platform during the process tarping/untarping. He must never attempt to get on board without the truck completely stopped at the station. Unroll the cover green mesh until it is covered evenly from side to side, next start connecting the green mess cover trailer tie downs. By the time the truck is ready to go out safety officer must ensure that beacon is in operation. 6.01.8 Tarping men ensure the wind does not affect the cover while transporting the sand materials. 6.01.9 Safety officer ensure the beacon light of truck/trailer is working before leaving the tarping station. 6.01.10 The next sequence of work/activity shall be under procedure of MST Hauling of sand material. All the above steps must be contacted on a steady pace NEVER in hurry. 6.02 DE-TARPING: 6.01.1 Construction ensure that location of De-Tarping Station is on Entrance area. 6.01.2 The person assign at De-Tarping station ensure and check the safety harness prior to use with the checklist and color code. METHOD STATEMENT TARPING & DE-TARPING SYSTEM CONTRACT No.:139-CO3 SITE PREPARATION FOR SUPPORT INSDUSTRIES, STAGE-4 REV.: 01 6.01.3 Checker/Tallymen at De-Tarping station ensure have a full body harness retractable lanyard at all times. 6.01.4 To ensure safety of all personnel at the top of tarping station while removing/covering green mesh net behind the bucket to the harness lanyard should be replaced with retractable appropriate in the distance from the ground 6.01.5 Ensure at all times should be 100% tied off even when there’s no truck/trailer arrives in the area. 6.01.6 Ensure to stop the truck/trailer properly before getting take off on the bucket and to start removing the green mesh cover. 6.01.7 Ensure to tied off the two lanyard from the body harness while working at the top of the truck/trailer. 6.01.8 Avoid unnecessary movements that are not related to work while on the top of Tarping/De-Tarping Station to prevent accident. 6.01.9 The checker/tallymen must have the records of every trips that coming on site. 6.01.10 The checker/tallymen before end of the day he must give the records to his superior/supervisor. 6.01.11 The personnel/foreman involved at work will advise the truck/trailer where the location of dumping. 6.01.12 The next sequence of work/activity shall be under procedure of MST backfilling. All the above steps must be contacted on a steady pace NEVER in hurry. 7. SAFETY: 7.01 Site Safety Management System shall be Applied: 7.01.1 Workers shall undergo Safety induction seminar conducted by Safety officer. In Addition to ensure to conduct safety work on METHOD STATEMENT TARPING & DE-TARPING SYSTEM CONTRACT No.:139-CO3 SITE PREPARATION FOR SUPPORT INSDUSTRIES, STAGE-4 REV.: 01 height prior to work start. The STAART for all activities shall be made by construction supervisor in daily basis and reviewed by safety officer and be available to all workers on site at all times. 7.01.2 Contractors will have a full time safety supervisor on site (Borrow Pit & Jobsite) at all times and will be erecting temporary shelter for drinking water and shade at Tarping/De-Tarping station. A portable toilet will also be available on site. 7.01.3 All workers will be wearing high visibility vests and flagman will be equipped with both red and green flags. 7.01.4 First Aid if required will be provided from our temporary facility at the nearest worksite area. 7.01.5 No work will commence until the necessary permits have been authorized and copy of these will be displayed at all times at the construction area. 7.01.6 Area barricading will be created where necessary to identify the construction areas Tarping/De-Tarping and Entry to Exit. 7.01.7 All equipment will have been inspected and approved and having serial number for use by Safety and all drivers/operators of equipment’s will be fully licensed and trained to use such equipment. 7.01.8 Safety officer must ensure none is standing near the trucks during operation. NO FOOT ON GROUND. 7.01.9 Contractors will operate under all terms and conditions of their safety procedures as per Royal Commission Standard. 8. ATTACHEMENT: