City of Mandurah Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge July 2011 Contents 1. 2. 3. 4. 5. 6. 7. 8. 61/26421/105205 Introduction 1 1.1 General 1 1.2 Scope of Report 2 Existing Bridge Information 4 2.1 Existing Bridge Details 4 2.2 Reference Information 4 2.3 Site Inspection 4 2.4 Existing Bridge Condition 5 Details of Refurbishment Works for Each Option 6 3.1 Introduction 6 3.2 Option 1 – Upgrade bridge capacity to 100% T44 6 3.3 Option 2 – Retain existing 17 tonne load limit 9 3.4 Option 3 – Convert to a pedestrian footbridge (5kPa load limit) 10 Future Maintenance Requirements 12 4.1 Expected Remaining Life of Bridge 12 4.2 Specific Future Maintenance Works 12 Cost Estimates 14 5.1 Refurbishment Options 14 5.2 Bridge Replacement 14 Whole of Life Cost Comparison 15 6.1 Introduction 15 6.2 NPV Analysis Qualifications 15 6.3 NPV Analysis Assumptions 16 6.4 Summary of Results 17 Non-Financial Considerations 18 7.1 Heritage 18 7.2 Bridge Standards and Safety 18 7.3 Comparison of Construction Impacts 19 Conclusions Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge 20 Figure Index Figure 1: Locality Plans (not to scale) Appendices 61/26421/105205 A Schedule of Stringer Repairs B Cross-sections for Existing Bridge and Refurbishment C Cost Estimates for Refurbishment Options 1, 2 and 3 D Whole of Life Cost Analysis Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge 1 1. Introduction 1.1 General Bridge No. 230, known as Old Mandurah Traffic Bridge, carries Pinjarra Road over the Mandurah Estuary providing a link from Mandurah City and Commercial Centre on the east side to residential and coastal areas on the west side (refer to the location plan below-left and an enlargement on the right), and is used by approximately 20,000 vehicles per day. Bridge No. 230 Bridge No. 230 Figure 1: Locality Plans (not to scale) The existing bridge was constructed in 1953, and has a concrete substructure and a predominately timber superstructure, except for the navigation spans which consist of steel beams. The bridge is substandard in relation to current design standards in a number of areas, including load capacity, traffic lane widths and shared path width. The bridge is also suffering increasing rates of deterioration to the timber superstructure and concrete substructure, which may require increasing inspection and maintenance costs. The City of Mandurah is planning for replacement of the bridge, and a draft concept design report has been prepared previously by AECOM, which outlines options for the replacement of the bridge in order to facilitate stakeholder and public consultation. 61/26421/105205 Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge 1 In order to support and further inform the decision making and public consultation processes, further investigation was required of the available options to refurbish the existing bridge and extend its service life, including estimation of the associated construction costs and future maintenance costs to refurbish and maintain the existing structure. GHD were engaged by the City of Mandurah to carry out an economic viability assessment for the replacement of the bridge. 1.2 Scope of Report This report presents the preliminary designs for several options to refurbish the existing bridge and extend its service life, and compares the estimated costs for these to the costs associated with a new replacement bridge. The comparison take into account whole of life costs including estimated on-going maintenance and also the eventual replacement at the end of the service life for the refurbished bridge. In addition there are non-financial considerations in comparing the refurbishment against the replacement of the bridge which are also discussed. The bridge replacement option used for the cost comparisons is based on the incrementally launched option from the concept design report by AECOM. This concept was for a bridge carrying 3 lanes of traffic, which is wider than the existing bridge and understood to be the preferred configuration for the bridge replacement. An additional replacement option for a 2 lane bridge as per the existing bridge configuration has also been included in the whole of life cost comparison, as it provides a more direct comparison to the existing bridge for assessment of replacement vs refurbishment. 1.2.1 Preliminary Refurbishment Designs The preliminary design of the bridge refurbishment has been carried out for 3 options: Option 1 – Retain the existing bridge and construct a new reinforced concrete overlay and associated repairs to improve capacity to 100% T44 and Group 1 (road train) vehicles. Significant ongoing maintenance is also expected for the bridge to maintain this capacity. Option 2 – Retain the existing bridge and construct a new reinforced concrete overlay and associated repairs to maintain the current 17 tonne capacity. Ongoing maintenance is expected for the bridge to maintain this capacity. Option 3 – Retain the existing bridge and convert it to a pedestrian-use footbridge only. Some ongoing maintenance and repairs will still be required. Full details of the anticipated refurbishment works for each option are included in Section 3 and future ongoing maintenance in Section 4. 1.2.2 Cost Estimates For each of these options, cost estimates for the construction of the refurbishment works have been prepared, as well as cost estimates for anticipated future maintenance works over the remaining life of the bridge. 61/26421/105205 Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge 2 Details of the cost estimates are discussed in Section 5. 1.2.3 Whole of Life Cost Assessments The costs including ongoing maintenance for each option have been compared to the cost for replacement of the bridge using a Net Present Value (NPV) analysis. The NPV analysis has been carried out over a 30 year time period. The details are discussed in Section 6. 1.2.4 Non-Financial Considerations for Refurbishment vs Replacement There are many other assessment criteria other than cost on which to compare the refurbishment options against the replacement of the bridge. Replacement of the bridge will provide many other benefits in addition to reduction of future maintenance, and conversely there are also other arguments in favour of retaining the existing bridge. A brief comparison of the refurbished bridge against a replacement bridge has been undertaken on several criteria, and is presented in Section 7. 61/26421/105205 Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge 3 2. Existing Bridge Information 2.1 Existing Bridge Details The existing bridge is approximately 186m long from abutment to abutment and has 23 spans, comprising 21 spans of approximately 7.6m with timber stringers and decking, and 2 navigation spans of approximately 12m with steel beams supporting timber bearers and decking. There are a number of timber and steel stringer strengthenings that have been added over time between the original timber stringers, as well as replacement steel stringers. The bridge substructure comprises concrete piles with a concrete headstock at the piers and concrete walls at the abutments. Fishing platforms located below the bridge are supported on concrete corbels integrated into the piles. The deck has an existing reinforced concrete overlay, which according to MRWA records was constructed in 1987. The overall bridge width is 9.17m, with a road carriageway width of 6.7m between kerbs, and a separate footpath approximately 1.75m wide. The guardrails comprise w-beam with timber posts for both sides of the roadway and also at the edge of the footpath. There are a number of services located on the bridge running below the footpath or cantilevered from the piers. For the refurbishment of the bridge, these can generally be retained in their current positions, but they have not been specifically investigated as part of this report. Confirmation of the services requirements will need to be obtained prior to detailed design of any major refurbishment works. The bridge currently has a posted load limit of 17 tonnes. 2.2 Reference Information The following reference information has been used to develop the refurbishment work scopes, prepare cost estimates and undertake the NPV analysis. Project brief issued by email dated 1/11/2010 to M. Jones of GHD; Concept Report for Replacement of Bridge 230 (Draft), AECOM, September 2010 (Document no. 60103037.215.R01); Existing bridge drawings supplied by MRWA; Timber Bridge Detailed Inspection Reports (DIR) prepared by MRWA; Cost data on previous bridge repairs and maintenance undertaken by City of Mandurah; 2.3 Site Inspection An inspection of the bridge was undertaken on the 19th November 2010 by Matthew Jones and Nicholas Meyer of GHD, following a project kick-off meeting with Michael Gunton from City of Mandurah. 61/26421/105205 Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge 4 The purpose of the inspection was to review the latest MRWA DIR for the bridge while on site and gain a better understanding of the work scope for the various bridge refurbishment options. 2.4 Existing Bridge Condition Based on the site inspection and review of the latest MRWA DIR, the bridge condition can be summarised as follows: Several of the timber stringers are showing signs of deterioration, however, based on the latest MRWA Timber Bridge Detailed Inspection Report (DIR) and subsequent load rating by MRWA, they are all currently still adequate for the 17 tonne load limit; The steel beams and bracing in the navigation spans are showing signs of corrosion and the original protective coating appears to be approaching the end of its life; There are numerous observed areas of minor concrete spalling to the piles or headstocks and cracking to some of the concrete piles. There is no detailed condition survey or testing information available from which to confirm the likely cause of cracking or the extent of any chloride contamination of the concrete, and accordingly the rates for future deterioration can be accurately estimated at this stage. 61/26421/105205 Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge 5 3. Details of Refurbishment Works for Each Option 3.1 Introduction The required refurbishment works for each of the three proposed options are listed in the sections below. The refurbishments works are divided into initial repairs and refurbishment works, which will comprise the initial capital expenditure to upgrade the bridge and extend its service life, and future maintenance, which will be required to keep the bridge in service. Due to the age of the bridge and its nature as a timber structure, there will be significant ongoing maintenance expenditure required in comparison to a full replacement structure. A summary schedule of the anticipated timber stringer replacements that will be required for each refurbishment option, and possible numbers of replacements in the future as the bridge continues to deteriorate is included in Appendix A. Typical cross-section sketches of the existing bridge and the proposed refurbishment options are included in Appendix B. It should be noted that the design for the refurbishments has only been carried out to a preliminary level, in order to develop a scope for the works for the purpose of preparing comparative cost estimates. Only a few of the spans have been load rated, and stringer replacements for other spans have simply been estimated by extrapolation. The extent of concrete substructure repairs has also been assumed based on currently available visual inspection information. Further investigation of concrete condition and structural analysis of all spans would be required if any of the refurbishment options are to be investigated and documented in greater detail. 3.2 Option 1 – Upgrade bridge capacity to 100% T44 This option will provide a replacement of the reinforced concrete overlay(RCO) which will upgrade and extend the life of the current superstructure, together with strengthening and replacement of the stringers in the timber spans and the navigation spans to upgrade the load capacity from 17 tonnes to full capacity for T44 loading and MRWA Group 1 vehicles (ie road train combinations). As part of this option, the guardrails will be upgraded to the current standard for Regular Performance Level to AS5100, and MRWA standard pedestrian balustrade will be installed along the footpath edge. The width of the road carriageway will also be increased to 7.2m between kerbs, which will accommodate two 3.0m wide traffic lanes with 0.6m wide shoulders. Note however, that the current standard width for a new bridge with around 20,000 vehicles per day would be 3.5m wide lanes and a minimum width of 8.2m between kerbs, so the upgraded bridge will still be below the standard required for a replacement bridge. This width cannot be accommodated on the existing bridge without significant modification and strengthening. The preliminary design refurbishment works for this option are as follows: 61/26421/105205 Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge 6 3.2.1 Substructure Repairs Reinforced Concrete Piles (including fishing platform corbels) Construct a reinforced concrete encasement repair to an estimated 22 piles (1 pile per pier). This is based on the number of piles exhibiting signs of cracking and spalling, plus allowance for additional piles due to possible chloride contamination which could result in deterioration in the future (this would need to be confirmed by detailed condition assessment prior to a detailed design). Each encasement repair shall extend from 1m below to 3m above the low water level and will also breakout of defective concrete and installation of a sacrificial anode system to the reinforcement. Temporary propping at each pier may be required during these works and has been allowed for in cost estimates. Some of the piles to be encased may have corbels supporting the fishing platform. It is assumed that these will generally be recreated as part of the encasement detail (actual details and modifications to fishing platforms not part of the scope at this stage). Apply a silane treatment to 100% of all pile surfaces above the high water level including 100% of all encasement repair surfaces above the high water level. (This treatment shall comprise Emer-Stop Crème applied in accordance with manufacturer’s recommendations or similar). Reinforced Concrete Capbeams (including stair & stringer corbels) Conduct concrete patch repairs to an estimated 22m 2 (approximately 0.5m2 on each side of each headstock beam). Apply a silane treatment to 100% of all headstock surfaces. 61/26421/105205 Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge 7 3.2.2 Superstructure Repairs Timber Stringers Replace an estimated 15 timber stringers with new steel beams (410UB60 grade 300), in accordance with MRWA Specification 850 Clause 850.33. New stringers will generally be supported on existing concrete corbel at each end. Install an estimated 10 new steel beams (410UB60 grade 300) as additional strengthening stringers between existing stringers near edges of the carriageway, in accordance with Specification 850 Clause 850.33. Navigation Spans Remove the existing bracing in each of the 2 navigation spans. Abrasive blast and recoat the existing steel beams with a new protective coating. Allow for access scaffold and encapsulation during blasting, with construction one span at a time to allow navigation access. Each beam is a 24”x7.5”x95lbs/ft RSB and there are 5 beams in each span (10 beams in total). Refer existing drawing for typical navigation span details. Install 3 new 700WB150 in each navigation span (6 new beams in total) to strengthen the spans. Install new bracing. Reinforced Concrete Overlay Demolish the existing overlay and construct the new overlay in two halves, allowing one lane of traffic to be open at all times. Remove the timber decking along both edges of the carriageway as per typical cross-section detail and replace with permanent Bondek formwork. Remove all timber decking, joists and bearers below the existing footpath overlay and replace with Bondek formwork. Prepare the remaining timber decking in accordance with MRWA Specification 850 Clause 850.41. Replace any timber planks that are found to be in a poor condition after the overlay is removed with Bondek and concrete (replace an estimated 5 planks per span for full width). Cut-out the top corners of each abutment to allow for the construction of the new wider RCO. Construct the new RCO with a minimum thickness of 145mm and a 2-way crossfall. At each end of the new RCO, remove the last 4 deck planks and construct a new sill beam to support the end of approach slabs. Provide a 100mm UPVC downpipe on each side of the carriageway at the mid-span of each span. Also provide a downpipe for the footpath on each span. Apply a 40mm asphalt seal on the overlay within the carriageway. 61/26421/105205 Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge 8 3.2.3 Approach Slabs and Expansion Joints Demolish the existing approach slabs and expansion joints and construct the new approach slabs and expansion joints in two halves, allowing one lane of traffic to be open at all times. Construct two new approach slabs, each having a length of 5m. Construct a new footpath slab alongside each new approach slab. Include steel nosing along the edges of the two expansion joints and install a Wabo compression seal or similar in each expansion joint. Apply 40mm asphalt seal on each approach slab. 3.2.4 Guardrails Guardrails on the Bridge The existing timber guardrails shall be upgraded to meet the current MRWA barrier standards. Remove the existing timber guardrails on both the carriageway and the footpath. Install a regular performance level guardrail, with top rails (4 rails in total), on each side of the carriageway. Mount the guardrails on the top of the kerbs of the new RCO using cast-in anchor bolts. Guardrails will extend to the end of approach slabs. Install a MRWA standard balustrade along the footpath edge to the ends of the approach slabs. Guardrails on the Approaches The new deck is wider than the existing deck, and therefore the existing guardrails on the approaches will need to be replaced. Install a W-beam guardrail, with an ET2000 extruder terminal, on each side of each approach slab. The total length of each approach guardrail shall be 22.5m. Install thriebeam transition segments to join the bridge guardrail at the end of the approach slabs, as per MRWA standard drawings. Alternative guardrail end treatments could also be considered, however the above is a standard MRWA end treatment which has been used for preliminary costing purposes. 3.3 Option 2 – Retain existing 17 tonne load limit This option will provide a replacement of the reinforced concrete overlay (RCO) which will upgrade and extend the life of the current superstructure, however, the current load capacity of 17 tonnes will be maintained which reduces the extent of stringer replacement and strengthening works required. As part of this option, the guardrails will be upgraded to the current standard for Regular Performance Level to AS5100, and MRWA standard pedestrian balustrade will be installed along the footpath edge. The width of the road carriageway will also be 61/26421/105205 Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge 9 increased to 7.2m between kerbs, which will accommodate two 3.0m wide traffic lanes with 0.6m wide shoulders. Note however, that the current standard width for a new bridge with around 20,000 vehicles per day would be 3.5m wide lanes and a minimum width of 8.2m between kerbs, so the upgraded bridge will still be below the standard required for a replacement bridge. This width cannot be accommodated on the existing bridge without significant modification and strengthening. The preliminary design refurbishment works for this option are as follows: 3.3.1 Substructure Repairs The same works as for Option 1 applies. Refer Section 3.2.1. 3.3.2 Superstructure Repairs Stringers No stringers replacements or additional stringers are required. Navigation Spans The same works as for Option 1 applies (refer Section 3.2.2) except that: No additional steel beams are required. Retain existing bracing. Reinforced Concrete Overlay The same works as for Option 1 applies. Refer Section 3.2.2. 3.3.3 Approach Slabs and Expansion Joints The same works as for Option 1 applies. Refer Section 3.2.3. 3.3.4 Guardrails The same works as for Option 1 applies. Refer Section 3.2.4. 3.4 Option 3 – Convert to a pedestrian footbridge (5kPa load limit) This option will provide a replacement of the reinforced concrete overlay (RCO) which will upgrade and extend the life of the current superstructure, however, it will not require any widening and its load capacity can be downgraded for a pedestrian only structure. A lot of the repair works to deteriorating members from the other options is still included however, as it is still required to extend the life of the bridge and maintain it in a serviceable condition. The preliminary design refurbishment works for this option are as follows: 3.4.1 Substructure Repairs The same works as for Option 1 applies. Refer Section 3.2.1. 61/26421/105205 Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge 10 3.4.2 Superstructure Repairs Stringers No stringers require replacement. No additional steel beams are required. Navigation Spans The same works as for Option 1 applies (refer Section 3.2.2) except that: No additional steel beams are required. Retain existing bracing. Reinforced Concrete Overlay Similar works to Option 1 still applies (refer Section 3.2.2), except that: The full width of the bridge shall be refurbished in one stage, rather than in two halves. No cut-outs of either abutment are required as the width of the existing bridge shall be maintained. The new RCO shall have a minimum thickness of 130mm. No asphalt seal is required. Details are as per sketch cross-section for Option 3 in Appendix Appendix B. 3.4.3 Approach Slabs and Expansion Joints No new approach slabs or expansion joint are required after demolition of existing. 3.4.4 Guardrails A new MRWA standard balustrade shall be installed on each side of the bridge. 61/26421/105205 Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge 11 4. Future Maintenance Requirements 4.1 Expected Remaining Life of Bridge The remaining life of the existing structure is difficult to estimate without a detailed condition assessment. With ongoing repairs and maintenance to the piles and stringers as outlined in this report, the remaining life will be controlled by the timber decking and replacement overlay, and the portion of the piles below the waterline which are not encased as part of the repairs. The piles below the water would be expected to have a reasonably long remaining life, due to the absence of oxygen at that level. This would need to be confirmed by a detailed investigation in case there were other issues that are not apparent with the currently available information. The superstructure after construction of a new RCO would normally be expected to last for up to 30 years, subject to detailed inspections every 5 years and replacement/maintenance of any stringers or other elements that deteriorate over this time. Further assessment of the remaining life of the decking and RCO beyond 30 years would need to be undertaken at that time. 4.2 Specific Future Maintenance Works In order to carry out a whole of life cost comparison between the refurbishment options and a new replacement bridge, estimates have been made of the likely future maintenance required to keep the refurbished bridge in service over its expected 30 year remaining life. These estimates assume that the works in Section 3 have already been carried out. They have been based on estimation of the future rate of deterioration, based on judgement, previous experience and comparison of stringer conditions in the previous three MRWA Timber Bridge Detailed Inspection Reports to gauge the previous rate of deterioration. They should be used for comparative purposes only. In order to accurately assess the maintenance requirements, a detailed condition assessment of the bridge components (e.g. type, severity & extent of defects and quantification of deterioration mechanisms such as rot in timber, carbonation and chloride penetration in concrete) would be required. 4.2.1 Option 1 Substructure Maintenance In 10 years’ time, assume: 10 piles will require a concrete encasement repair. 2 22m of capbeam surface concrete will require patch repairs. In 20 years’ time, assume: 61/26421/105205 Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge 12 10 piles will require a concrete encasement repair. 22m2 of capbeam surface concrete will require patch repairs. Superstructure Maintenance In 10 years’ time, assume: 30 timber stringers will need to be replaced with new steel beams (410UB60 grade 300). In 20 years’ time, assume: 20 timber stringers will need to be replaced with new steel beams (410UB60 grade 300). The steel beams in the navigation spans will require another blast and re-coat. 4.2.2 Option 2 Substructure Maintenance See 4.2.1 Superstructure Maintenance In 10 years’ time, assume: 20 timber stringers will need to be replaced with new steel beams (410UB60 grade 300). In 20 years’ time, assume: 10 timber stringers will need to be replaced with new steel beams (410UB60 grade 300). The steel beams in the navigation spans will require another blast and re-coat. 4.2.3 Option 3 Substructure Maintenance See 4.2.1 Superstructure Maintenance In 10 years’ time, assume: 10 timber stringers will need to be replaced with new steel beams (410UB60 grade 300). In 20 years’ time, assume: 10 timber stringers will need to be replaced with new steel beams (410UB60 grade 300). The steel beams in the navigation spans will require another blast and re-coat. 61/26421/105205 Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge 13 5. Cost Estimates 5.1 Refurbishment Options Cost estimates have been prepared for the proposed refurbishment option works and are included in Appendix C. They have been prepared by a Quantity Surveyor and are based on the costs for similar previous works, with allowance for escalation to 2010. A contingency amount of approximately 15% is included, and allowances have also been made for design fees and project management costs. Cost estimates for anticipated future specific maintenance are also included. Note that these have all been estimated at 2010 rates. Conditions and exclusions applicable to the cost estimates are included within the Appendices. 5.2 Bridge Replacement The cost of the bridge replacement was estimated as $25 million based on the incrementally launched, 3-lane option from the AECOM Concept Design Report. Review of this cost estimate was not part of the scope for this report. The cost for the 2-lane bridge replacement option used as a more direct comparison to the existing bridge was calculated on a pro-rata basis based on the approximate deck area. 61/26421/105205 Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge 14 6. Whole of Life Cost Comparison 6.1 Introduction The three refurbishment options outlined in this report have been compared to the alternative of replacing the bridge with a new incrementally launched structure as per the AECOM Concept Report. The comparison has been made based on the future costs associated with each option over a period of 30 years, calculated as a net present value (NPV) by using appropriate discount & inflation rates. The basis and qualifications for these calculations are outlined in the following sections and a summary of the NPV results and sample spreadsheet showing the calculations for one inflation and discount rate scenario are included in Appendix D. 6.2 NPV Analysis Qualifications The NPV calculations are directly related to the discount rate of return and inflation rate applicable over the duration of the analysis. A number of assumptions and qualifications are used to select the rates used in analysis as detailed below. According to basic financial theory, projects which yield a negative NPV are generally rejected. Since an upgrade to or replacement of the existing bridge does not yield a quantifiable return on the invested capital, the option with the highest/least negative NPV is considered the optimal. 6.2.1 Inflation Rate Inflation rates have been assumed by inspection of rates over the last 20 years from data obtained from the Reserve Bank of Australia. For the majority of the last twenty years, the inflation rate has been confined to a band of between 2 – 3.5% with occasional spikes to around 4%. Since the inflation rate is very difficult to fine-tune within a narrow range, rates of 2%, 2.75% and 3.5% have been used for analysis. 6.2.2 Discount Rate For the purposes of analysis, the discount rate has been assumed to be constant over the duration of the NPV analysis. A typical approach in choosing the discount rate is assessing the opportunity cost. The discount rate can be considered as the rate at which the capital required for the bridge could return if invested elsewhere. Discount rates of 6%, 7.5% and 9% have been used for analysis. It should be noted that NPV calculations are very sensitive to the discount rate of return used in analysis. Additionally, the discount rate does not include an adjustment for risk. Therefore, the lower bound discount rate of 6% is a conservative rate assuming low risk whereas a 61/26421/105205 Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge 15 9% discount rate implies that the alternative investment has a more significant degree of risk attached. 6.2.3 Whole of Life Cost Comparison The NPV analysis has been conducted over a period of 30 years. Since the discount and inflation rates are difficult to predict and are unlikely to be constant throughout the 30 year period, a sensitivity analysis has been completed using combinations from the range of values noted above to produce nine separate scenarios. Conservative scenarios using the lowest discount rate, highest inflation rate and a decrease in the capital cost of the bridge replacement, or an increase in the Option 1 and 2 refurbishment and maintenance costs have also been compared as an additional scenario to test the sensitivity of the NPV to these cash flows. Results are included in the summary spreadsheet included in Appendix D. 6.3 NPV Analysis Assumptions 6.3.1 Cost of Capital Option 1: The capital cost comprises substructure repairs, superstructure repairs, construction of approach slabs and replacement of guardrails. The life of the bridge after refurbishments is assumed to be 30 years, at which point a new bridge will need to be constructed at a cost of $25 million as noted in Section 5.2. Option 2: The capital cost is as above for Option 1, except that slightly reduced scope and refurbishment costs applies. Option 3: Since the existing bridge would be converted to a pedestrian-only footbridge, a traffic bridge would still need to be constructed. For the analysis it has been assumed that this bridge will cost $25 million and would be constructed in five years’ time. There has been no reduction in cost for the new bridge by considering a small reduction in width that could be possible by leaving out a footpath. Option 4: The capital cost for the new, 3-lane bridge is $25 million as noted in Section 5.2. The life of the new bridge after completion is assumed to be 100 years. The AECOM Concept Report details the list of exclusions from the estimated capital cost (also listed in the NPV analysis spreadsheets). The report notes that this cost has been assumed from a base rate per square metre for the bridge and is a preliminary cost estimate only. Option 5: The capital cost for the new, 2-lane bridge is $19.5 million and was calculated by applying the square metre rate from the AECOM Concept Report to the reduced deck area, as noted in Section 5.2. The life of the new bridge after completion is assumed to be 100 years. The exclusions from capital cost are as per Option 4 above. 6.3.2 Future Maintenance Future maintenance works required for the bridge for each option have been detailed in Section 4 and are based on the assumptions and limitations outlined in that Section. 61/26421/105205 Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge 16 For Options 1, 2 and 3, additional allowance for routine maintenance expenditure of $50,000 every 5 years has been made, which would cover inspections, timber preventative treatment and minor repairs. For Options 3, 4 & 5 some general maintenance comprising a detailed condition assessment for the new bridge has been included on a 10 year cycle. 6.4 Summary of Results It can be seen from the spreadsheet summary table in Appendix D that Option 5 (replacement of bridge with 2-lane structure) has the most favourable (highest) NPV for a low discount rate and Option 2 (retain bridge at existing capacity) has the highest NPV for a high discount rate. For the medium discount rate of 7.5%, the NPV of options 2 and 5 are quite close with Option 2 yielding the highest NPV at lower inflation rates, and the order reversing for a high inflation rate scenario. There is also not a great deal of difference between Options 1 and 2 and the decision between these would come down to the operational desirability of upgrading the bridge capacity. Option 4 (replacement 3-lane bridge) has lower NPV than Option 5 in all scenarios due to the extra cost for the wider bridge, but does become competitive with Options 1 & 2 when using the lowest discount rate and higher inflation as per Scenario 3. For Option 4 to yield the highest NPV with these rates (excluding Option 5), the replacement cost needs to be reduced to $21 million or the refurbishment and future maintenance costs for Options 1 & 2 need to be slightly increased. In every scenario the NPV for Option 3 is the lowest and least competitive. 61/26421/105205 Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge 17 7. Non-Financial Considerations Note this section is not intended to be exhaustive, but is to recognise that there are many other criteria other than whole of life costs on which to compare the refurbishment and replacement options, and to prompt further discussions. 7.1 Heritage A detailed heritage assessment is outside the scope of this report, however, the existing bridge and fishing platforms have been a long-standing icon for the City of Mandurah due to its prominent location, and heritage issues will need to be considered in the final assessment of refurbishment and replacement options. A further option, which was not considered as part of the whole of life cost assessment in this report, would be to construct a new bridge but retain several spans of the existing bridge and fishing platform, together with appropriate interpretation facilities. It should be noted that after construction of a new RCO, replacement of several stringers with steel, and upgrade of guardrails and other elements to current standards as per the scope of Options 1 and 2, the bridge will be significantly modified from its original state. Retaining several spans as a heritage display (and not a functional traffic bridge) would provide the opportunity to restore those spans to original condition with a fully timber superstructure. 7.2 Bridge Standards and Safety Although the refurbishment options have been directly compared to the replacement bridge in the whole of life cost analysis, there are significant improvements to the standards for a new bridge. These should be taken into account when making any value for money judgements from the net present value analysis results. The new bridge will have a design life of 100 years minimum compared to only 30 years for the refurbishment of the existing bridge; The new bridge will be designed to the current design loading from AS5100 Bridge Design (i.e. full SM1600 traffic loading). A refurbished bridge will only cater for T44 loading which is the standard from the now superseded Austroads 1992 Bridge Design Code (and this applies for Option 1 only). The capital expenditure for the new bridge (Option 4) on which the whole of life cost assessments were based is for a 3 lane structure with standard width 3.5m lanes which will provide greater traffic capacity. The refurbishment Options 1 and 2 will provide 2 lanes only with 3.0m wide lanes plus a shoulder. It should be noted that the option of a new 2-lane bridge (Option 5) was comparable to retaining the existing structure (Option 2). The new bridge will provide the opportunity to improve the navigation span clearances. 61/26421/105205 Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge 18 The new bridge will be a more modern structure with improved aesthetics, although this is a highly subjective judgement and there are also heritage issues to be considered. 7.3 Comparison of Construction Impacts Construction of the refurbishment works for Options 1 and 2 would require closure of the road to traffic, or at the very least reduction to a single narrow lane which will still cause disruption (and be required for a longer construction period than a full closure). The replacement of the bridge would be on a new alignment which would allow the existing road and bridge to remain open, except possibly for a short period when tying in the new alignment to existing approach roads. There would be minimal impacts on estuarine traffic for the replacement bridge construction as outlined in the AECOM report. 61/26421/105205 Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge 19 8. Conclusions Preliminary designs for several refurbishment options have been prepared, and comparatively assessed on a whole of life cost basis to the cost of a new incrementally launched bridge. The refurbishment of the existing bridge is expected to result in a remaining life of up to 30 years, subject to detailed inspections every 5 years and ongoing replacement and maintenance of any stringers or other elements that deteriorate over this time. The initial capital costs for refurbishment of the existing bridge as per Options 1 and 2 are lower than the cost for a replacement bridge (with either 2 or 3 lanes). When whole of life costs are taken into account using a net present value analysis, the difference between refurbishing and replacing is reduced, and replacement with a new 2-lane bridge (Option 5) is shown to be more favourable for scenarios with a low discount rate, while Options 1 and 2 are still slightly more favourable for scenarios with a high discount rate. For a unique scenario where the discount rate is low, inflation rate is high, and refurbishment and maintenance costs are slightly increased above the current cost estimates, it can be shown that the replacement with a 3 lane bridge (Option 4) is also more favourable that Option 1 and 2. Option 3 (constructing a new bridge and maintaining the existing bridge for pedestrian use only) is significantly less competitive than the others. The replacement of the existing bridge does offer significant improvements in nonfinancial areas including improved standards for load capacity, traffic capacity in the case of a new 3-lane bridge, safety, and the reduction in the need for ongoing inspections, monitoring and maintenance. The final selection of the preferred bridge upgrade option will depend on an assessment of all financial and non-financial considerations together with the results of consultation of the community and relevant stakeholders. 61/26421/105205 Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge 20 Appendix A Schedule of Stringer Repairs 61/26421/105205 Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge Old Mandurah Traffic Bridge Job no. 61/26421 STRINGER REPLACEMENT SCHEDULE Based on MRWA DIR 11/12/09 and GHD site inspection 19/11/10 Original Construction Current # New steel UBs required Span # Timber # Timber # Steel UB # Total Load Rated Option 1 T44 Option 2 17t Option 3 5kPa Current Poor Condition 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 10 13 13 11 12 12 11 13 11 10 10 12 10 10 9 12 11 12 13 13 13 3 1 0 3 1 1 1 0 2 1 1 1 1 3 2 0 2 0 1 2 2 13 14 13 14 13 13 12 13 13 11 11 13 11 13 11 12 13 12 14 15 15 Yes 0 0 0 Yes 0 0 0 Yes Yes Yes 2 2 2 0 0 0 0 0 0 Yes 0 0 0 2 1 0 0 2 0 1 1 1 5 2 1 2 3 1 3 2 2 6 2 1 189 241 28 6 24 0 0 0 0 Totals: 23 269 Total for 6 rated spans: Estimated total for 23 spans: Notes 1 2 The spans that were selected for load rating included the critical stringers that were identified in the MRWA DIR and from the GHD site inspection The 'number of new steel UBs required' includes those required for replacement and addition 38 Appendix B Cross-sections for Existing Bridge and Refurbishment Note: Cross sections are based on preliminary design only and are intended to indicate the extent of the proposed replacement reinforced concrete overlays and guardrail arrangement. Existing or proposed stringer replacements or strengthening are not shown. 61/26421/105205 Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge Appendix C Cost Estimates for Refurbishment Options 1, 2 and 3 61/26421/105205 Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge PRELIMINARY COST PLANNING OLD MANDURAH TRAFFIC BRIDGE (BRIDGE 230) Economic Viability Assessment for Refurbishment Contract No: Unknown Job No.: A2448 21 December, 2010 OLD MANDURAH TRAFFIC BRIDGE (BRIDGE 230) Economic Viability Assessment for Replacement CONDITIONS & EXCLUSIONS 1.00 This Cost Indication is conditioned as follows: 1.01 These prices are current as at January 1, 2010 and are based on the rate currently used in similar contracts for MRWA 1.02 Escalation of cost has been incorporated up to December 31, 2009 1.03 This cost indication is accurate within the following range: 1.04 The percentage cost of General Items Etc is based on the percentage cost of similar MRWA Projects over the last 12 Months 1.05 The Percentage cost for Contingencies is based on a percentage similar to that on similar MRWA Projects over the last 12 months 2.00 This Cost Indication excludes the cost of the following: 2.01 Removal of asbestos 2.02 Any necessary excavation in rock 2.03 Any removal and replacement of unsuitable materials 2.04 The value of Principal supplied items including searching for and stockpiling of embankment construction and pavement construction materials 2.05 Allowances of accelerated construction periods 2.06 Holding Costs and interest charges 2.07 Time extension costs 2.08 Legal fees 2.09 Relocation of services other than those indicated in the Cost Indication Details 2.10 Allowances for charges and costs levied by Authorities, Councils and Service Bodies * See Below 2.11 Aboriginal heritage, cultural and native title issues 2.12 Redevelopment work of surplus land prior to disposal 2.13 Loss of business claims 2.14 Increased costs due to labour shortages in the Region 2.15 Increase in tender prices due to the current over supply of work for Contractors * Please note: It is no longer Davson+Ward Pty Ltd Company Policy to nominate limits of accuracy due to the current economic climate DAVSON+WARD Pty. Ltd. Summary Quantity Surveyors Construction Cost Consultants OLD MANDURAH TRAFFIC BRIDGE (BRIDGE 230) Economic Viability Assessment for Replacement SUMMARY OPTION 1 - Upgrade bridge capacity to 100% T44 2.1 Substructure Repairs $2,030,477.70 2.2 Superstructure Repairs $5,166,404.18 2.3 Approach Slabs and Expansion Joints $494,159.07 2.4 Guardrails $921,904.96 $8,612,945.92 2.5 Future Specific Maintenance 2.5.1.1 - Substructure - 10 Years $658,763.20 2.5.1.2 - Substructure - 20 Years $658,763.20 2.5.2.1 - Superstructure - 10 Years $187,357.22 2.5.2.2 - Superstructure - 20 Years $259,211.06 OPTION 2 - Retain existing 17 tonne load limit 3.1 Substructure Repairs $2,030,477.70 3.2 Superstructure Repairs $4,783,694.05 3.3 Approach Slabs and Expansion Joints $494,159.07 3.4 Guardrails $921,904.96 3.5 Future Specific Maintenance 3.5.1.1- Substructure - 10 Years $658,763.20 3.5.1.2 - Substructure - 20 Years $658,763.20 3.5.2.1 - Superstructure - 10 Years $124,904.81 3.5.2.2 - Superstructure - 20 Years $196,758.66 Manduralh Bridge Refurbishment Summary $8,230,235.78 DAVSON+WARD Pty. Ltd. Summary Quantity Surveyors Construction Cost Consultants OLD MANDURAH TRAFFIC BRIDGE (BRIDGE 230) Economic Viability Assessment for Replacement OPTION 3 - Convert to a pedestrian footbridge (5kPa load limit) 4.1 Substructure Repairs $2,030,477.70 4.2 Superstructure Repairs $3,985,417.99 4.3 Approach Slabs and Expansion Joints $163,191.05 4.4 Guardrails $387,527.25 4.5 Future Specific Maintenance 4.5.1.1- Substructure - 10 Years $658,763.20 4.5.1.2 - Substructure - 20 Years $658,763.20 4.5.2.1 - Superstructure - 10 Years $62,452.41 4.5.2.2 - Superstructure - 20 Years $196,758.66 Manduralh Bridge Refurbishment Summary $6,566,613.99 DAVSON+WARD PTY. LTD. Option 1 Quantity Surveyors and Construction Cost Consultants OLD MANDURAH TRAFFIC BRIDGE (BRIDGE 230) OPTION 1 - Upgrade Bridge Capacity to 100% T44 Item Description Unit Qty Rate Amount No. 22 $8,750.00 $192,500.00 2.1 SUBSTRUCTURE REPAIRS 1.1 2.1.1 Reinforced Concrete piles Allow for the removal or breakout of defective concrete and provide and construct concrete encasement of piles including all necessary formwork, reinforcement and dewatering as required 1.2 Allow for temporary propping of each pier during the pile repairs complete No. 22 $26,750.00 $588,500.00 1.3 Allow for Silane treatment of all concrete surfaces above high water level complete Item 1 $285,000.00 $285,000.00 2.1.2 Reinforced Concrete Capbeams (including Stair and Stringer Corbels) 1.4 Apply concrete patch repairs to all capbeams m2 22 $585.00 $12,870.00 1.5 Allow for Silane treatment of all surfaces of capbeams complete Item 1 $55,000.00 $55,000.00 SUB-TOTAL $1,133,870.00 ADD Preliminary items (Includes: Insurances, Contractor's Superintendence, site establishment, Contractors site offices and area, Superintendent's Office Survey costs and all other items included in the normal Schedule No. 1 - General Items) % 30 $340,161.00 ADD Contingencies % 15 $170,080.50 GST EXCLUSIVE AMOUNT Mandurah Bridge Upgrade Indicative Cost Indication $1,644,111.50 DAVSON+WARD PTY. LTD. Option 1 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty % 5 $82,205.58 % 1 $16,441.12 TENDER AND CONTRACT ADMINISTRATION (City of Mandurah) % 4 $57,543.90 PROJECT MANAGEMENT (City of Mandurah) % 4 $65,764.46 $1,866,066.55 SURVEY, DESIGN AND DOCUMENTATION ETHNOGRAPHIC SURVEYS AND CLEARANCES Rate ESTIMATED GST PAYABLE OPTION 1 - 2.1 - TOTAL OF PRELIMINARY COST INDICATION Mandurah Bridge Upgrade Indicative Cost Indication Amount $164,411.15 $2,030,477.70 DAVSON+WARD PTY. LTD. Option 1 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty Rate Amount m 113 $465.00 $52,545.00 m 75 $425.00 $31,875.00 Item 1 $8,670.00 $8,670.00 Item 1 $75,000.00 $75,000.00 m 75 $1,275.00 $95,625.00 $25,000.00 $25,000.00 2.2 SUPERSTRUCTURE REPAIRS 1.6 1.7 1.8 2.2.1 Timber Stringers Galvanised 410UB60 steel section stringers including all fasteners, bearing brackets and preparing to receive all as detailed on the drawings as replacement of removed Stringers (In No. 15) New 410UB60 Grade 300 beams complete (In No. 10) 2.2.2 Navigation Spans Allow for the removal of existing bracing complete 1.9 Allow for abrasive blasting and recoating of existing steel beams including all access scaffolding and encapsulating during the blasting 1.10 New 700WB150 beams fixed complete (In No. 6) 1.11 Allow for new bracing complete Item 1 1.12 2.2.3 Reinforced Concrete Overlay Remove existing bituminous pavement complete m2 1,231 $15.00 $18,465.00 1.13 Remove existing concrete overlay complete m2 1,365 $275.00 $375,375.00 1.14 Remove existing concrete and timber footpath slab including all timber supports m2 315 $115.00 $36,225.00 1.15 Remove existing timber balustrade to edge of footpath complete m 184 $18.00 $3,312.00 1.16 Remove existing timber decking to edge of deck and prepare for new formwork m2 552 $55.00 $30,360.00 1.17 Allow for the removal of existing planks and replacement with 1mm Bondek and concrete No. 110 $1,265.00 $15,000.00 Item 1 $965,000.00 $965,000.00 m3 450 $940.00 $423,000.00 1.18 1.19 Falsework Provision and erection of falsework including maintenance and removal including provision of access to carry out repairs Concrete Reinforced Insitu Concrete Class S40 Deck slab and Sill Beams Mandurah Bridge Upgrade Indicative Cost Indication DAVSON+WARD PTY. LTD. Option 1 Quantity Surveyors and Construction Cost Consultants Item 1.20 1.21 1.22 Description Formwork DECK Formwork to edge of deck slab Permanent Steel Formwork 1mm thick Bondek to soffit of deck slab installed as detailed in the Drawings 1mm thick Bondek to soffit of footpath slab as detailed in the Drawings Unit Qty Rate Amount m2 300 $365.00 $109,500.00 m2 552 $125.00 $69,000.00 m2 432 $125.00 $54,000.00 t 1.5 $33,514.00 $50,271.00 Steel Reinforcement DECK & SILLS Reinforcing Bars to AS/NZS 4671 Grade 500N 1.23 Bars less than 16mm diameter in Kerbs 1.24 Reinforcing Fabric to AS 1304 SL81 Reinforcing fabric to deck slab & sills m2 3900 $60.00 $234,000.00 1.25 SL81 Reinforcing fabric to deck kerbs m2 650 $65.00 $42,250.00 m2 650 $125.00 $81,250.00 Item 1 $35,600.00 $35,600.00 m² 1,325 $1.20 $1,590.00 m² 1,325 $23.50 $31,137.50 No 42 $500.00 $21,000.00 1.26 1.27 1.28 1.29 1.30 Timber Bridges TIMBER DECK PREPARATION TO RECEIVE CONCRETE OVERLAY Clean & Prepare existing timber decking to receive concrete overlay, including hessian covering, fungicide treatments and all other cast in items not covered in these Bills all as detailed in the Drawings (PROVISIONAL QUANTITY) Allow for cutting at existing abutments to take new with of reinforced concrete overlay. Asphalt Surfacing BRIDGEWORKS Tack coat 50mm dense graded asphalt on bridge deck and approach slabs Scuppers 100mm Diameter UPVC downpipes including all joiners and fastening cast into the concrete deck all as detailed on the Drawings SUB-TOTAL Mandurah Bridge Upgrade Indicative Cost Indication $2,885,050.50 DAVSON+WARD PTY. LTD. Option 1 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty ADD Preliminary items (Includes: Insurances, Contractor's Superintendence, site establishment, Contractors site offices and area, Superintendent's Office Survey costs and all other items included in the normal Schedule No. 1 - General Items) % 30 $865,515.15 ADD Contingencies % 15 $432,757.58 Rate GST EXCLUSIVE AMOUNT Amount $4,183,323.23 % 5 $209,166.16 % 1 $41,833.23 TENDER AND CONTRACT ADMINISTRATION (City of Mandurah) % 4 $146,416.31 PROJECT MANAGEMENT (City of Mandurah) % 4 $167,332.93 $4,748,071.86 SURVEY, DESIGN AND DOCUMENTATION ETHNOGRAPHIC SURVEYS AND CLEARANCES ESTIMATED GST PAYABLE OPTION 1 - 2.2 - TOTAL OF PRELIMINARY COST INDICATION Mandurah Bridge Upgrade Indicative Cost Indication $418,332.32 $5,166,404.18 DAVSON+WARD PTY. LTD. Option 1 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty Rate Amount 2.3 APPROACH SLABS AND EXPANSION JOINTS 1.31 Remove existing bituminous pavement complete m2 67 $15.00 $1,005.00 1.32 Rip up and remove existing concrete approach slabs complete m2 75 $455.00 $34,125.00 Item 1 $35,000.00 $35,000.00 m3 6 $3,100.00 $18,600.00 1.33 1.34 Earthworks Allow for trimming and compacting the ground ready to receive concrete including all necessary topping up of the fill material Concrete Plain Insitu Concrete Class N20 50 Blinding layer under approach slab (In 120 m2) 1.35 Reinforced Insitu Concrete Class S40 Approach slab m3 20 $765.00 $15,300.00 1.36 Formwork Sides of approach slab m2 40 $335.00 $13,400.00 1.37 Soffit of approach slab m2 7 $425.00 $2,975.00 Steel Reinforcement Reinforcing Bars to AS/NZS 4671 Grade 500N 1.38 Bars less than 16 diameter in approach slab t 0.40 $4,250.00 $1,700.00 1.39 Bars 16 - 36 diameter in approach slab t 3.31 $4,250.00 $14,067.50 No. 26 $3,000.00 $78,000.00 m 20 $3,000.00 $60,000.00 Bridge Bearings 1.40 APPROACH SLAB BEARINGS Approach slab bearing comprising 1000 x 160 x 5 Thick ultra high molecular weight polyethylene sheet (HDPE), 1000 x 120 x 10 thick rubber bearing pad with 50-60 durometer hardness, galvanised dowel cap cast into approach slab and 20 diameter galvanised dowel 120 long cast into deck slab Compression Joint Seal 1.41 Compression seal including galvanised expansion joint edging with anchor straps cast into concrete and galvanised cover plates (In 2 No. expansion joints) Mandurah Bridge Upgrade Indicative Cost Indication DAVSON+WARD PTY. LTD. Option 1 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty Rate Amount 1.42 Asphalt Surfacing BRIDGEWORKS Tack coat m² 72 $1.20 $86.40 1.43 50mm dense graded asphalt on approach slabs m² 72 $23.50 $1,692.00 SUB-TOTAL $275,950.90 ADD Preliminary items (Includes: Insurances, Contractor's Superintendence, site establishment, Contractors site offices and area, Superintendent's Office Survey costs and all other items included in the normal Schedule No. 1 - General Items) % 30 $82,785.27 ADD Contingencies % 15 $41,392.64 GST EXCLUSIVE AMOUNT $400,128.81 % 5 $20,006.44 % 1 $4,001.29 TENDER AND CONTRACT ADMINISTRATION (City of Mandurah) % 4 $14,004.51 PROJECT MANAGEMENT (City of Mandurah) % 4 $16,005.15 $454,146.19 ESTIMATED GST PAYABLE $40,012.88 SURVEY, DESIGN AND DOCUMENTATION ETHNOGRAPHIC SURVEYS AND CLEARANCES OPTION 1 - 2.3 - TOTAL OF PRELIMINARY COST INDICATION Mandurah Bridge Upgrade Indicative Cost Indication $494,159.07 DAVSON+WARD PTY. LTD. Option 1 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty Rate Amount m 368 $25.00 $9,200.00 2.4 GUARDRAILS 1.44 2.4.1 Guardrails on the Bridge Remove existing guardrail with timber posts and W Beam Road Safety Barrier Systems and Traffic Barriers for Structures 1.45 BARRIER Galvanised Regular Performance Level barrier m 370 $850.00 $314,500.00 1.46 BALUSTRADE Galvanized and painted balustrade m 204 $560.00 $114,240.00 m 45 $25.00 $1,125.00 m 45 $350.00 $15,750.00 1.47 2.4.2 Guardrails on Approach Slabs Remove existing guardrail with timber posts and W Beam Road Safety Barrier Systems and Traffic Barriers for Structures 1.48 BARRIER Galvanised W-Beam barrier 1.49 Galvanised Thriebeam/W-Beam transition No. 4 $6,500.00 $26,000.00 1.50 Galvanised modified eccentric loader terminal (ET 2000) No. 4 $8,500.00 $34,000.00 SUB-TOTAL $514,815.00 ADD Preliminary items (Includes: Insurances, Contractor's Superintendence, site establishment, Contractors site offices and area, Superintendent's Office Survey costs and all other items included in the normal Schedule No. 1 - General Items) % 30 $154,444.50 ADD Contingencies % 15 $77,222.25 GST EXCLUSIVE AMOUNT $746,481.75 Mandurah Bridge Upgrade Indicative Cost Indication DAVSON+WARD PTY. LTD. Option 1 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty % 5 $37,324.09 % 1 $7,464.82 TENDER AND CONTRACT ADMINISTRATION (City of Mandurah) % 4 $26,126.86 PROJECT MANAGEMENT (City of Mandurah) % 4 $29,859.27 $847,256.79 ESTIMATED GST PAYABLE $74,648.18 SURVEY, DESIGN AND DOCUMENTATION ETHNOGRAPHIC SURVEYS AND CLEARANCES OPTION 1 - 2.4 - TOTAL OF PRELIMINARY COST INDICATION Mandurah Bridge Upgrade Indicative Cost Indication Rate Amount $921,904.96 DAVSON+WARD PTY. LTD. Option 1 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty Rate Amount No. 10 $8,750.00 $87,500.00 No 10 $26,750.00 $267,500.00 m2 22 $585.00 $12,870.00 2.5 FUTURE MAINTENANCE 2.5.1 Substructure Maintenance 10 YEARS 1.51 1.52 2.1.1 Reinforced Concrete piles Allow for the removal or breakout of defective concrete and provide and construct concrete encasement of piles including all necessary formwork, reinforcement and dewatering as required Allow for temporary propping of each pier during the pile repairs complete 2.1.2 Reinforced Concrete Capbeams (including Stair and Stringer Corbels) 1.53 Apply concrete patch repairs to all capbeams SUB-TOTAL $367,870.00 ADD Preliminary items (Includes: Insurances, Contractor's Superintendence, site establishment, Contractors site offices and area, Superintendent's Office Survey costs and all other items included in the normal Schedule No. 1 - General Items) % 30 $110,361.00 ADD Contingencies % 15 $55,180.50 GST EXCLUSIVE AMOUNT $533,411.50 % 5 $26,670.58 % 1 $5,334.12 TENDER AND CONTRACT ADMINISTRATION (City of Mandurah) % 4 $18,669.40 PROJECT MANAGEMENT (City of Mandurah) % 4 $21,336.46 $605,422.05 ESTIMATED GST PAYABLE $53,341.15 SURVEY, DESIGN AND DOCUMENTATION ETHNOGRAPHIC SURVEYS AND CLEARANCES OPTION 1 - 2.5.1.1 - SUBSTRUCTURE - TOTAL OF PRELIMINARY COST INDICATION Mandurah Bridge Upgrade Indicative Cost Indication $658,763.20 DAVSON+WARD PTY. LTD. Option 1 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty Rate Amount No. 10 $8,750.00 $87,500.00 No. 10 $26,750.00 $267,500.00 m2 22 $585.00 $12,870.00 20 YEARS 1.54 1.55 2.1.1 Reinforced Concrete piles Allow for the removal or breakout of defective concrete and provide and construct concrete encasement of piles including all necessary formwork, reinforcement and dewatering as required Allow for temporary propping of each pier during the pile repairs complete 2.1.2 Reinforced Concrete Capbeams (including Stair and Stringer Corbels) 1.56 Apply concrete patch repairs to all capbeams SUB-TOTAL $367,870.00 ADD Preliminary items (Includes: Insurances, Contractor's Superintendence, site establishment, Contractors site offices and area, Superintendent's Office Survey costs and all other items included in the normal Schedule No. 1 - General Items) % 30 $110,361.00 ADD Contingencies % 15 $55,180.50 GST EXCLUSIVE AMOUNT $533,411.50 % 5 $26,670.58 % 1 $5,334.12 TENDER AND CONTRACT ADMINISTRATION (City of Mandurah) % 4 $18,669.40 PROJECT MANAGEMENT (City of Mandurah) % 4 $21,336.46 $605,422.05 ESTIMATED GST PAYABLE $53,341.15 SURVEY, DESIGN AND DOCUMENTATION ETHNOGRAPHIC SURVEYS AND CLEARANCES OPTION 1 - 2.5.1.2 - SUBSTRUCTURE - TOTAL OF PRELIMINARY COST INDICATION Mandurah Bridge Upgrade Indicative Cost Indication $658,763.20 DAVSON+WARD PTY. LTD. Option 1 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty m 225 Rate Amount 2.5.2 Superstructure Maintenance 10 YEARS 1.57 2.2.1 Timber Stringers Galvanised 410UB60 steel section stringers including all fasteners, bearing brackets and preparing to receive all as detailed on the drawings as replacement of removed Stringers (In No. 30) $465.00 $104,625.00 SUB-TOTAL $104,625.00 ADD Preliminary items (Includes: Insurances, Contractor's Superintendence, site establishment, Contractors site offices and area, Superintendent's Office Survey costs and all other items included in the normal Schedule No. 1 - General Items) % 30 $31,387.50 ADD Contingencies % 15 $15,693.75 GST EXCLUSIVE AMOUNT $151,706.25 % 5 $7,585.31 % 1 $1,517.06 TENDER AND CONTRACT ADMINISTRATION (City of Mandurah) % 4 $5,309.72 PROJECT MANAGEMENT (City of Mandurah) % 4 $6,068.25 $172,186.59 ESTIMATED GST PAYABLE $15,170.63 SURVEY, DESIGN AND DOCUMENTATION ETHNOGRAPHIC SURVEYS AND CLEARANCES OPTION 1 - 2.5.2.1 - SUPERSTRUCTURE - TOTAL OF PRELIMINARY COST INDICATION Mandurah Bridge Upgrade Indicative Cost Indication $187,357.22 DAVSON+WARD PTY. LTD. Option 1 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty m 150 Item 1 Rate Amount 20 YEARS 1.67 2.2.1 Timber Stringers Galvanised 410UB60 steel section stringers including all fasteners, bearing brackets and preparing to receive all as detailed on the drawings as replacement of removed Stringers (In No. 20) $465.00 $69,750.00 2.2.2 Navigation Spans 1.68 Allow for abrasive blasting and recoating of existing steel beams including all access scaffolding and encapsulating during the blasting $75,000.00 $75,000.00 SUB-TOTAL $144,750.00 ADD Preliminary items (Includes: Insurances, Contractor's Superintendence, site establishment, Contractors site offices and area, Superintendent's Office Survey costs and all other items included in the normal Schedule No. 1 - General Items) % 30 $43,425.00 ADD Contingencies % 15 $21,712.50 GST EXCLUSIVE AMOUNT $209,887.50 % 5 $10,494.38 % 1 $2,098.88 TENDER AND CONTRACT ADMINISTRATION (City of Mandurah) % 4 $7,346.06 PROJECT MANAGEMENT (City of Mandurah) % 4 $8,395.50 $238,222.31 ESTIMATED GST PAYABLE $20,988.75 SURVEY, DESIGN AND DOCUMENTATION ETHNOGRAPHIC SURVEYS AND CLEARANCES OPTION 1 - 2.5.2.2 - SUPERSTRUCTURE- TOTAL OF PRELIMINARY COST INDICATION Mandurah Bridge Upgrade Indicative Cost Indication $259,211.06 DAVSON+WARD PTY. LTD. Option 2 Quantity Surveyors and Construction Cost Consultants OLD MANDURAH TRAFFIC BRIDGE (BRIDGE 230) OPTION 2 - Retain Existing 17 tonne load limit Item Description Unit Qty Rate Amount No. 22 $8,750.00 $192,500.00 3.1 SUBSTRUCTURE REPAIRS 2.1 3.1.1 Reinforced Concrete piles Allow for the removal or breakout of defective concrete and provide and construct concrete encasement of piles including all necessary formwork, reinforcement and dewatering as required 2.2 Allow for temporary propping of each pier during the pile repairs complete No. 22 $26,750.00 $588,500.00 2.3 Allow for Silane treatment of all concrete surfaces above high water level complete Item 1 $285,000.00 $285,000.00 3.1.2 Reinforced Concrete Capbeams (including Stair and Stringer Corbels) 2.4 Apply concrete patch repairs to all capbeams m2 22 $585.00 $12,870.00 2.5 Allow for Silane treatment of all surfaces of capbeams complete Item 1 $55,000.00 $55,000.00 SUB-TOTAL $1,133,870.00 ADD Preliminary items (Includes: Insurances, Contractor's Superintendence, site establishment, Contractors site offices and area, Superintendent's Office Survey costs and all other items included in the normal Schedule No. 1 - General Items) % 30 $340,161.00 ADD Contingencies % 15 $170,080.50 GST EXCLUSIVE AMOUNT Mandurah Bridge Indicative Cost Indication $1,644,111.50 DAVSON+WARD PTY. LTD. Option 2 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty % 5 $82,205.58 % 1 $16,441.12 TENDER AND CONTRACT ADMINISTRATION (City of Mandurah) % 4 $57,543.90 PROJECT MANAGEMENT (City of Mandurah) % 4 $65,764.46 $1,866,066.55 SURVEY, DESIGN AND DOCUMENTATION ETHNOGRAPHIC SURVEYS AND CLEARANCES Rate ESTIMATED GST PAYABLE OPTION 2 - 3.1 - TOTAL OF PRELIMINARY COST INDICATION Mandurah Bridge Indicative Cost Indication Amount $164,411.15 $2,030,477.70 DAVSON+WARD PTY. LTD. Option 2 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty Item 1 Rate Amount 3.2 SUPERSTRUCTURE REPAIRS 2.6 3.2.2 Navigation Spans Allow for abrasive blasting and recoating of existing steel beams including all access scaffolding and encapsulating during the blasting $75,000.00 $75,000.00 2.7 3.2.3 Reinforced Concrete Overlay Remove existing bituminous pavement complete m2 1,231 $15.00 $18,465.00 2.8 Remove existing concrete overlay complete m2 1,365 $275.00 $375,375.00 2.9 Remove existing concrete and timber footpath slab including all timber supports m2 315 $115.00 $36,225.00 2.10 Remove existing timber balustrade to edge of footpath complete m 184 $18.00 $3,312.00 2.11 Remove existing timber decking to edge of deck and prepare for new formwork m2 552 $55.00 $30,360.00 2.12 Allow for the removal of existing planks and replacement with 1mm Bondek and concrete No. 110 $1,265.00 $15,000.00 Item 1 $965,000.00 $965,000.00 2.14 Concrete Reinforced Insitu Concrete Class S40 Deck slab and Sill Beams m3 450 $940.00 $423,000.00 2.15 Formwork DECK Formwork to edge of deck slab m2 300 $365.00 $109,500.00 m2 552 $125.00 $69,000.00 m2 432 $125.00 $54,000.00 2.13 2.16 2.17 Falsework Provision and erection of falsework including maintenance and removal including provision of access to carry out repairs Permanent Steel Formwork 1mm thick Bondek to soffit of deck slab installed as detailed in the Drawings 1mm thick Bondek to soffit of footpath slab as detailed in the Drawings Mandurah Bridge Indicative Cost Indication DAVSON+WARD PTY. LTD. Option 2 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty t 1.5 Rate Amount Steel Reinforcement DECK & SILLS Reinforcing Bars to AS/NZS 4671 Grade 500N 2.18 Bars less than 16mm diameter in Kerbs 2.19 Reinforcing Fabric to AS 1304 SL81 Reinforcing fabric to deck slab & sills m2 2.20 SL81 Reinforcing fabric to deck kerbs 2.21 2.22 2.23 2.24 2.25 Timber Bridges TIMBER DECK PREPARATION TO RECEIVE CONCRETE OVERLAY Clean & Prepare existing timber decking to receive concrete overlay, including hessian covering, fungicide treatments and all other cast in items not covered in these Bills all as detailed in the Drawings (PROVISIONAL QUANTITY) Allow for cutting at existing abutments to take new with of reinforced concrete overlay. Asphalt Surfacing BRIDGEWORKS Tack coat 50mm dense graded asphalt on bridge deck and approach slabs Scuppers 100mm Diameter UPVC downpipes including all joiners and fastening cast into the concrete deck all as detailed on the Drawings $33,514.00 $50,271.00 3900 $60.00 $234,000.00 m2 650 $65.00 $42,250.00 m2 650 $125.00 $81,250.00 Item 1 $35,600.00 $35,600.00 m² 1,325 $1.20 $1,590.00 m² 1,325 $23.50 $31,137.50 No 42 $500.00 $21,000.00 SUB-TOTAL $2,671,335.50 ADD Preliminary items (Includes: Insurances, Contractor's Superintendence, site establishment, Contractors site offices and area, Superintendent's Office Survey costs and all other items included in the normal Schedule No. 1 - General Items) % 30 $801,400.65 ADD Contingencies % 15 $400,700.33 GST EXCLUSIVE AMOUNT Mandurah Bridge Indicative Cost Indication $3,873,436.48 DAVSON+WARD PTY. LTD. Option 2 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty % 5 $193,671.82 % 1 $38,734.36 TENDER AND CONTRACT ADMINISTRATION (City of Mandurah) % 4 $135,570.28 PROJECT MANAGEMENT (City of Mandurah) % 4 $154,937.46 $4,396,350.40 SURVEY, DESIGN AND DOCUMENTATION ETHNOGRAPHIC SURVEYS AND CLEARANCES Rate ESTIMATED GST PAYABLE OPTION 2 - 3.2 - TOTAL OF PRELIMINARY COST INDICATION Mandurah Bridge Indicative Cost Indication Amount $387,343.65 $4,783,694.05 DAVSON+WARD PTY. LTD. Option 2 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty Rate Amount 3.3 APPROACH SLABS AND EXPANSION JOINTS 2.26 Remove existing bituminous pavement complete m2 67 $15.00 $1,005.00 2.27 Rip up and remove existing concrete approach slabs complete m2 75 $455.00 $34,125.00 Item 1 $35,000.00 $35,000.00 m3 6 $3,100.00 $18,600.00 2.28 2.29 Earthworks Allow for trimming and compacting the ground ready to receive concrete including all necessary topping up of the fill material Concrete Plain Insitu Concrete Class N20 50 Blinding layer under approach slab (In 120 m2) 2.30 Reinforced Insitu Concrete Class S40 Approach slab m3 20 $765.00 $15,300.00 2.31 Formwork Sides of approach slab m2 40 $335.00 $13,400.00 2.32 Soffit of approach slab m2 7 $425.00 $2,975.00 Steel Reinforcement Reinforcing Bars to AS/NZS 4671 Grade 500N 2.33 Bars less than 16 diameter in approach slab t 0.40 $4,250.00 $1,700.00 2.34 Bars 16 - 36 diameter in approach slab t 3.31 $4,250.00 $14,067.50 No. 26 $3,000.00 $78,000.00 m 20 $3,000.00 $60,000.00 Bridge Bearings 2.35 APPROACH SLAB BEARINGS Approach slab bearing comprising 1000 x 160 x 5 Thick ultra high molecular weight polyethylene sheet (HDPE), 1000 x 120 x 10 thick rubber bearing pad with 50-60 durometer hardness, galvanised dowel cap cast into approach slab and 20 diameter galvanised dowel 120 long cast into deck slab Compression Joint Seal 2.36 Compression seal including galvanised expansion joint edging with anchor straps cast into concrete and galvanised cover plates (In 2 No. expansion joints) Mandurah Bridge Indicative Cost Indication DAVSON+WARD PTY. LTD. Option 2 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty Rate Amount 2.37 Asphalt Surfacing BRIDGEWORKS Tack coat m² 72 $1.20 $86.40 2.38 50mm dense graded asphalt on approach slabs m² 72 $23.50 $1,692.00 SUB-TOTAL $275,950.90 ADD Preliminary items (Includes: Insurances, Contractor's Superintendence, site establishment, Contractors site offices and area, Superintendent's Office Survey costs and all other items included in the normal Schedule No. 1 - General Items) % 30 $82,785.27 ADD Contingencies % 15 $41,392.64 GST EXCLUSIVE AMOUNT $400,128.81 % 5 $20,006.44 % 1 $4,001.29 TENDER AND CONTRACT ADMINISTRATION (City of Mandurah) % 4 $14,004.51 PROJECT MANAGEMENT (City of Mandurah) % 4 $16,005.15 $454,146.19 ESTIMATED GST PAYABLE $40,012.88 SURVEY, DESIGN AND DOCUMENTATION ETHNOGRAPHIC SURVEYS AND CLEARANCES OPTION 2 - 3.3 - TOTAL OF PRELIMINARY COST INDICATION Mandurah Bridge Indicative Cost Indication $494,159.07 DAVSON+WARD PTY. LTD. Option 2 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty m 368 Rate Amount 3.4 GUARDRAILS 2.39 3.4.1 Guardrails on the Bridge Remove existing guardrail with timber posts and W Beam $25.00 $9,200.00 Road Safety Barrier Systems and Traffic Barriers for Structures 2.40 BARRIER Galvanised Regular Performance Level barrier m 370 $850.00 $314,500.00 2.41 BALUSTRADE Galvanized and painted balustrade m 204 $560.00 $114,240.00 m 45 m 45 $350.00 $15,750.00 2.42 3.4.2 Guardrails on Approach Slabs Remove existing guardrail with timber posts and W Beam $25.00 $1,125.00 Road Safety Barrier Systems and Traffic Barriers for Structures 2.43 BARRIER Galvanised W-Beam barrier 2.44 Galvanised Thriebeam/W-Beam transition No. 4 $6,500.00 $26,000.00 2.45 Galvanised modified eccentric loader terminal (ET 2000) No. 4 $8,500.00 $34,000.00 SUB-TOTAL $514,815.00 ADD Preliminary items (Includes: Insurances, Contractor's Superintendence, site establishment, Contractors site offices and area, Superintendent's Office Survey costs and all other items included in the normal Schedule No. 1 - General Items) % 30 $154,444.50 ADD Contingencies % 15 $77,222.25 GST EXCLUSIVE AMOUNT $746,481.75 Mandurah Bridge Indicative Cost Indication DAVSON+WARD PTY. LTD. Option 2 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty % 5 $37,324.09 % 1 $7,464.82 TENDER AND CONTRACT ADMINISTRATION (City of Mandurah) % 4 $26,126.86 PROJECT MANAGEMENT (City of Mandurah) % 4 $29,859.27 $847,256.79 ESTIMATED GST PAYABLE $74,648.18 SURVEY, DESIGN AND DOCUMENTATION ETHNOGRAPHIC SURVEYS AND CLEARANCES OPTION 2 - 3.4 - TOTAL OF PRELIMINARY COST INDICATION Mandurah Bridge Indicative Cost Indication Rate Amount $921,904.96 DAVSON+WARD PTY. LTD. Option 2 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty Rate Amount No. 10 $8,750.00 $87,500.00 No. 10 $26,750.00 $267,500.00 m2 22 $585.00 $12,870.00 3.5 FUTURE MAINTENANCE 2.5.1 Substructure Maintenance 10 YEARS 2.46 2.47 3.1.1 Reinforced Concrete piles Allow for the removal or breakout of defective concrete and provide and construct concrete encasement of piles including all necessary formwork, reinforcement and dewatering as required Allow for temporary propping of each pier during the pile repairs complete 3.1.2 Reinforced Concrete Capbeams (including Stair and Stringer Corbels) 2.48 Apply concrete patch repairs to all capbeams SUB-TOTAL $367,870.00 ADD Preliminary items (Includes: Insurances, Contractor's Superintendence, site establishment, Contractors site offices and area, Superintendent's Office Survey costs and all other items included in the normal Schedule No. 1 - General Items) % 30 $110,361.00 ADD Contingencies % 15 $55,180.50 GST EXCLUSIVE AMOUNT $533,411.50 % 5 $26,670.58 % 1 $5,334.12 TENDER AND CONTRACT ADMINISTRATION (City of Mandurah) % 4 $18,669.40 PROJECT MANAGEMENT (City of Mandurah) % 4 $21,336.46 $605,422.05 ESTIMATED GST PAYABLE $53,341.15 SURVEY, DESIGN AND DOCUMENTATION ETHNOGRAPHIC SURVEYS AND CLEARANCES OPTION 2 - 3.5.1.1 - SUBSTRUCTURE - TOTAL OF PRELIMINARY COST INDICATION Mandurah Bridge Indicative Cost Indication $658,763.20 DAVSON+WARD PTY. LTD. Option 2 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty Rate Amount No. 10 $8,750.00 $87,500.00 No. 10 $26,750.00 $267,500.00 m2 22 $585.00 $12,870.00 20 YEARS 2.49 2.50 3.1.1 Reinforced Concrete piles Allow for the removal or breakout of defective concrete and provide and construct concrete encasement of piles including all necessary formwork, reinforcement and dewatering as required Allow for temporary propping of each pier during the pile repairs complete 3.1.2 Reinforced Concrete Capbeams (including Stair and Stringer Corbels) 2.51 Apply concrete patch repairs to all capbeams SUB-TOTAL $367,870.00 ADD Preliminary items (Includes: Insurances, Contractor's Superintendence, site establishment, Contractors site offices and area, Superintendent's Office Survey costs and all other items included in the normal Schedule No. 1 - General Items) % 30 $110,361.00 ADD Contingencies % 15 $55,180.50 GST EXCLUSIVE AMOUNT $533,411.50 % 5 $26,670.58 % 1 $5,334.12 TENDER AND CONTRACT ADMINISTRATION (City of Mandurah) % 4 $18,669.40 PROJECT MANAGEMENT (City of Mandurah) % 4 $21,336.46 $605,422.05 ESTIMATED GST PAYABLE $53,341.15 SURVEY, DESIGN AND DOCUMENTATION ETHNOGRAPHIC SURVEYS AND CLEARANCES OPTION 2 - 3.5.1.2 - SUBSTRUCTURE - TOTAL OF PRELIMINARY COST INDICATION Mandurah Bridge Indicative Cost Indication $658,763.20 DAVSON+WARD PTY. LTD. Option 2 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty m 150 Rate Amount 3.5.2 Superstructure Maintenance 10 YEARS 2.52 3.2.1 Timber Stringers Galvanised 410UB60 Grade 300 steel section stringers including all fasteners, bearing brackets and preparing to receive all as detailed on the drawings as replacement of removed Stringers (In No. 20) $465.00 $69,750.00 SUB-TOTAL $69,750.00 ADD Preliminary items (Includes: Insurances, Contractor's Superintendence, site establishment, Contractors site offices and area, Superintendent's Office Survey costs and all other items included in the normal Schedule No. 1 - General Items) % 30 $20,925.00 ADD Contingencies % 15 $10,462.50 GST EXCLUSIVE AMOUNT $101,137.50 % 5 $5,056.88 % 1 $1,011.38 TENDER AND CONTRACT ADMINISTRATION (City of Mandurah) % 4 $3,539.81 PROJECT MANAGEMENT (City of Mandurah) % 4 $4,045.50 $114,791.06 ESTIMATED GST PAYABLE $10,113.75 SURVEY, DESIGN AND DOCUMENTATION ETHNOGRAPHIC SURVEYS AND CLEARANCES OPTION 2 - 3.5.2.1 - SUBSTRUCTURE - TOTAL OF PRELIMINARY COST INDICATION Mandurah Bridge Indicative Cost Indication $124,904.81 DAVSON+WARD PTY. LTD. Option 2 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty m 75 Item 1 Rate Amount 20 YEARS 2.53 3.2.1 Timber Stringers Galvanised 410UB60 steel section stringers including all fasteners, bearing brackets and preparing to receive all as detailed on the drawings as replacement of removed Stringers (In No. 10) $465.00 $34,875.00 3.2.2 Navigation Spans 2.54 Allow for abrasive blasting and recoating of existing steel beams including all access scaffolding and encapsulating during the blasting $75,000.00 $75,000.00 SUB-TOTAL $109,875.00 ADD Preliminary items (Includes: Insurances, Contractor's Superintendence, site establishment, Contractors site offices and area, Superintendent's Office Survey costs and all other items included in the normal Schedule No. 1 - General Items) % 30 $32,962.50 ADD Contingencies % 15 $16,481.25 GST EXCLUSIVE AMOUNT $159,318.75 % 5 $7,965.94 % 1 $1,593.19 TENDER AND CONTRACT ADMINISTRATION (City of Mandurah) % 4 $5,576.16 PROJECT MANAGEMENT (City of Mandurah) % 4 $6,372.75 $180,826.78 ESTIMATED GST PAYABLE $15,931.88 SURVEY, DESIGN AND DOCUMENTATION ETHNOGRAPHIC SURVEYS AND CLEARANCES OPTION 2 - 3.5.2.2 - SUBSTRUCTURE - TOTAL OF PRELIMINARY COST INDICATION Mandurah Bridge Indicative Cost Indication $196,758.66 DAVSON+WARD PTY. LTD. Option 3 Quantity Surveyors and Construction Cost Consultants OLD MANDURAH TRAFFIC BRIDGE (BRIDGE 230) OPTION 3 - Convert to a pedestrian footbridge (5kPa Load Limit) Item Description Unit Qty Rate Amount No. 22 $8,750.00 $192,500.00 4.1 SUBSTRUCTURE REPAIRS 3.1 4.1.1 Reinforced Concrete piles Allow for the removal or breakout of defective concrete and provide and construct concrete encasement of piles including all necessary formwork, reinforcement and dewatering as required 3.2 Allow for temporary propping of each pier during the pile repairs complete No. 22 $26,750.00 $588,500.00 3.3 Allow for Silane treatment of all concrete surfaces above high water level complete Item 1 $285,000.00 $285,000.00 4.1.2 Reinforced Concrete Capbeams (including Stair and Stringer Corbels) 3.4 Apply concrete patch repairs to all capbeams m2 22 $585.00 $12,870.00 3.5 Allow for Silane treatment of all surfaces of capbeams complete Item 1 $55,000.00 $55,000.00 SUB-TOTAL $1,133,870.00 ADD Preliminary items (Includes: Insurances, Contractor's Superintendence, site establishment, Contractors site offices and area, Superintendent's Office Survey costs and all other items included in the normal Schedule No. 1 - General Items) % 30 $340,161.00 ADD Contingencies % 15 $170,080.50 GST EXCLUSIVE AMOUNT Mandurah Bridge Upgrade Indicative Cost Indication $1,644,111.50 DAVSON+WARD PTY. LTD. Option 3 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty % 5 $82,205.58 % 1 $16,441.12 TENDER AND CONTRACT ADMINISTRATION (City of Mandurah) % 4 $57,543.90 PROJECT MANAGEMENT (City of Mandurah) % 4 $65,764.46 $1,866,066.55 SURVEY, DESIGN AND DOCUMENTATION ETHNOGRAPHIC SURVEYS AND CLEARANCES Rate ESTIMATED GST PAYABLE OPTION 2 - 3.1 - TOTAL OF PRELIMINARY COST INDICATION Mandurah Bridge Upgrade Indicative Cost Indication Amount $164,411.15 $2,030,477.70 DAVSON+WARD PTY. LTD. Option 3 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty Item 1 Rate Amount 4.2 SUPERSTRUCTURE REPAIRS 3.6 3.2.2 Navigation Spans Allow for abrasive blasting and recoating of existing steel beams including all access scaffolding and encapsulating during the blasting $75,000.00 $75,000.00 3.7 4.2.3 Reinforced Concrete Overlay Remove existing bituminous pavement complete m2 1,231 $15.00 $18,465.00 3.8 Remove existing concrete overlay complete m2 1,365 $275.00 $375,375.00 3.9 Remove existing concrete and timber footpath slab including all timber supports m2 315 $115.00 $36,225.00 3.10 Remove existing timber balustrade to edge of footpath complete m 184 $18.00 $3,312.00 3.11 Remove existing timber decking to edge of deck and prepare for new formwork m2 552 $55.00 $30,360.00 3.12 Allow for the removal of existing planks and replacement with 1mm Bondek and concrete No. 110 $1,265.00 $15,000.00 Item 1 $785,000.00 $785,000.00 3.14 Concrete Reinforced Insitu Concrete Class S40 Deck slab and Sill Beams m3 420 $940.00 $394,800.00 3.15 Formwork DECK Formwork to edge of deck slab m2 200 $365.00 $73,000.00 m2 552 $125.00 $69,000.00 m2 432 $125.00 $54,000.00 3.13 3.16 3.17 Falsework Provision and erection of falsework including maintenance and removal including provision of access to carry out repairs Permanent Steel Formwork 1mm thick Bondek to soffit of deck slab installed as detailed in the Drawings 1mm thick Bondek to soffit of footpath slab as detailed in the Drawings Mandurah Bridge Upgrade Indicative Cost Indication DAVSON+WARD PTY. LTD. Option 3 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty t 1.5 Rate Amount Steel Reinforcement DECK & SILLS Reinforcing Bars to AS/NZS 4671 Grade 500N 3.18 Bars less than 16mm diameter in Kerbs 3.19 Reinforcing Fabric to AS 1304 SL81 Reinforcing fabric to deck slab & sills m2 3.20 SL81 Reinforcing fabric to deck kerbs 3.21 3.22 Timber Bridges TIMBER DECK PREPARATION TO RECEIVE CONCRETE OVERLAY Clean & Prepare existing timber decking to receive concrete overlay, including hessian covering, fungicide treatments and all other cast in items not covered in these Bills all as detailed in the Drawings (PROVISIONAL QUANTITY) Scuppers 100mm Diameter UPVC downpipes including all joiners and fastening cast into the concrete deck all as detailed on the Drawings $33,514.00 $50,271.00 1850 $60.00 $111,000.00 m2 500 $65.00 $32,500.00 m2 650 $125.00 $81,250.00 No 42 $500.00 SUB-TOTAL $21,000.00 $2,225,558.00 ADD Preliminary items (Includes: Insurances, Contractor's Superintendence, site establishment, Contractors site offices and area, Superintendent's Office Survey costs and all other items included in the normal Schedule No. 1 - General Items) % 30 $667,667.40 ADD Contingencies % 15 $333,833.70 GST EXCLUSIVE AMOUNT $3,227,059.10 % 5 $161,352.96 % 1 $32,270.59 TENDER AND CONTRACT ADMINISTRATION (City of Mandurah) % 4 $112,947.07 PROJECT MANAGEMENT (City of Mandurah) % 4 $129,082.36 $3,662,712.08 SURVEY, DESIGN AND DOCUMENTATION ETHNOGRAPHIC SURVEYS AND CLEARANCES ESTIMATED GST PAYABLE OPTION 2 - 3.2 - TOTAL OF PRELIMINARY COST INDICATION Mandurah Bridge Upgrade Indicative Cost Indication $322,705.91 $3,985,417.99 DAVSON+WARD PTY. LTD. Option 3 Quantity Surveyors and Construction Cost Consultants Item Description Mandurah Bridge Upgrade Unit Qty Indicative Cost Indication Rate Amount DAVSON+WARD PTY. LTD. Option 3 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty Rate Amount 4.3 APPROACH SLABS AND EXPANSION JOINTS 3.23 Remove existing bituminous pavement complete m2 67 $15.00 $1,005.00 3.24 Rip up and remove existing concrete approach slabs complete m2 75 $455.00 $34,125.00 3.25 Allow for filling behind abutment with pavement material and Asphalt surfacing Item 1 $56,000.00 $56,000.00 SUB-TOTAL $91,130.00 ADD Preliminary items (Includes: Insurances, Contractor's Superintendence, site establishment, Contractors site offices and area, Superintendent's Office Survey costs and all other items included in the normal Schedule No. 1 - General Items) % 30 $27,339.00 ADD Contingencies % 15 $13,669.50 GST EXCLUSIVE AMOUNT $132,138.50 % 5 $6,606.93 % 1 $1,321.39 TENDER AND CONTRACT ADMINISTRATION (City of Mandurah) % 4 $4,624.85 PROJECT MANAGEMENT (City of Mandurah) % 4 $5,285.54 $149,977.20 ESTIMATED GST PAYABLE $13,213.85 SURVEY, DESIGN AND DOCUMENTATION ETHNOGRAPHIC SURVEYS AND CLEARANCES OPTION 2 - 3.2 - TOTAL OF PRELIMINARY COST INDICATION Mandurah Bridge Upgrade Indicative Cost Indication $163,191.05 DAVSON+WARD PTY. LTD. Option 3 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty m 413 m 368 Rate Amount 4.4 GUARDRAILS 3.26 3.4.1 Guardrails on the Bridge Remove existing guardrail with timber posts and W Beam $25.00 $10,325.00 Road Safety Barrier Systems and Traffic Barriers for Structures 3.27 BALUSTRADE Galvanized and painted balustrade $560.00 $206,080.00 SUB-TOTAL $216,405.00 ADD Preliminary items (Includes: Insurances, Contractor's Superintendence, site establishment, Contractors site offices and area, Superintendent's Office Survey costs and all other items included in the normal Schedule No. 1 - General Items) % 30 $64,921.50 ADD Contingencies % 15 $32,460.75 GST EXCLUSIVE AMOUNT $313,787.25 % 5 $15,689.36 % 1 $3,137.87 TENDER AND CONTRACT ADMINISTRATION (City of Mandurah) % 4 $10,982.55 PROJECT MANAGEMENT (City of Mandurah) % 4 $12,551.49 $356,148.53 ESTIMATED GST PAYABLE $31,378.73 SURVEY, DESIGN AND DOCUMENTATION ETHNOGRAPHIC SURVEYS AND CLEARANCES OPTION 3 - 4.4 - TOTAL OF PRELIMINARY COST INDICATION Mandurah Bridge Upgrade Indicative Cost Indication $387,527.25 DAVSON+WARD PTY. LTD. Option 3 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty Rate Amount No. 10 $8,750.00 $87,500.00 No. 10 $26,750.00 $267,500.00 m2 22 $585.00 $12,870.00 4.5 FUTURE MAINTENANCE 4.5.1 Substructure Maintenance 10 YEARS 3.28 3.29 3.1.1 Reinforced Concrete piles Allow for the removal or breakout of defective concrete and provide and construct concrete encasement of piles including all necessary formwork, reinforcement and dewatering as required Allow for temporary propping of each pier during the pile repairs complete 3.1.2 Reinforced Concrete Capbeams (including Stair and Stringer Corbels) 3.30 Apply concrete patch repairs to all capbeams SUB-TOTAL $367,870.00 ADD Preliminary items (Includes: Insurances, Contractor's Superintendence, site establishment, Contractors site offices and area, Superintendent's Office Survey costs and all other items included in the normal Schedule No. 1 - General Items) % 30 $110,361.00 ADD Contingencies % 15 $55,180.50 GST EXCLUSIVE AMOUNT $533,411.50 % 5 $26,670.58 % 1 $5,334.12 TENDER AND CONTRACT ADMINISTRATION (City of Mandurah) % 4 $18,669.40 PROJECT MANAGEMENT (City of Mandurah) % 4 $21,336.46 $605,422.05 ESTIMATED GST PAYABLE $53,341.15 SURVEY, DESIGN AND DOCUMENTATION ETHNOGRAPHIC SURVEYS AND CLEARANCES OPTION 3 - 4.5.1 - SUBSTRUCTURE - TOTAL OF PRELIMINARY COST INDICATION Mandurah Bridge Upgrade Indicative Cost Indication $658,763.20 DAVSON+WARD PTY. LTD. Option 3 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty Rate Amount No. 10 $8,750.00 $87,500.00 No. 10 $26,750.00 $267,500.00 m2 22 $585.00 $12,870.00 20 YEARS 3.31 3.32 2.1.1 Reinforced Concrete piles Allow for the removal or breakout of defective concrete and provide and construct concrete encasement of piles including all necessary formwork, reinforcement and dewatering as required Allow for temporary propping of each pier during the pile repairs complete 2.1.2 Reinforced Concrete Capbeams (including Stair and Stringer Corbels) 3.33 Apply concrete patch repairs to all capbeams SUB-TOTAL $367,870.00 ADD Preliminary items (Includes: Insurances, Contractor's Superintendence, site establishment, Contractors site offices and area, Superintendent's Office Survey costs and all other items included in the normal Schedule No. 1 - General Items) % 30 $110,361.00 ADD Contingencies % 15 $55,180.50 GST EXCLUSIVE AMOUNT $533,411.50 % 5 $26,670.58 % 1 $5,334.12 TENDER AND CONTRACT ADMINISTRATION (City of Mandurah) % 4 $18,669.40 PROJECT MANAGEMENT (City of Mandurah) % 4 $21,336.46 $605,422.05 ESTIMATED GST PAYABLE $53,341.15 SURVEY, DESIGN AND DOCUMENTATION ETHNOGRAPHIC SURVEYS AND CLEARANCES OPTION 1 - 2.5.1.2 - SUBSTRUCTURE TOTAL OF PRELIMINARY COST INDICATION Mandurah Bridge Upgrade Indicative Cost Indication $658,763.20 DAVSON+WARD PTY. LTD. Option 3 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty m 75 Rate Amount 4.5.2 Superstructure Maintenance 10 YEARS 3.34 3.2.1 Timber Stringers Galvanised 410UB60 Grade 300 steel section stringers including all fasteners, bearing brackets and preparing to receive all as detailed on the drawings as replacement of removed Stringers (In No. 10) $465.00 $34,875.00 SUB-TOTAL $34,875.00 ADD Preliminary items (Includes: Insurances, Contractor's Superintendence, site establishment, Contractors site offices and area, Superintendent's Office Survey costs and all other items included in the normal Schedule No. 1 - General Items) % 30 $10,462.50 ADD Contingencies % 15 $5,231.25 GST EXCLUSIVE AMOUNT $50,568.75 % 5 $2,528.44 % 1 $505.69 TENDER AND CONTRACT ADMINISTRATION (City of Mandurah) % 4 $1,769.91 PROJECT MANAGEMENT (City of Mandurah) % 4 $2,022.75 $57,395.53 ESTIMATED GST PAYABLE $5,056.88 SURVEY, DESIGN AND DOCUMENTATION ETHNOGRAPHIC SURVEYS AND CLEARANCES OPTION 3 - 4.5.1 - SUPERSTRUCTURE - TOTAL OF PRELIMINARY COST INDICATION Mandurah Bridge Upgrade Indicative Cost Indication $62,452.41 DAVSON+WARD PTY. LTD. Option 3 Quantity Surveyors and Construction Cost Consultants Item Description Unit Qty m 75 Item 1 Rate Amount 20 YEARS 3.35 3.2.1 Timber Stringers Galvanised 410UB60 steel section stringers including all fasteners, bearing brackets and preparing to receive all as detailed on the drawings as replacement of removed Stringers (In No. 10) $465.00 $34,875.00 3.2.2 Navigation Spans 3.36 Allow for abrasive blasting and recoating of existing steel beams including all access scaffolding and encapsulating during the blasting $75,000.00 $75,000.00 SUB-TOTAL $109,875.00 ADD Preliminary items (Includes: Insurances, Contractor's Superintendence, site establishment, Contractors site offices and area, Superintendent's Office Survey costs and all other items included in the normal Schedule No. 1 - General Items) % 30 $32,962.50 ADD Contingencies % 15 $16,481.25 GST EXCLUSIVE AMOUNT $159,318.75 % 5 $7,965.94 % 1 $1,593.19 TENDER AND CONTRACT ADMINISTRATION (City of Mandurah) % 4 $5,576.16 PROJECT MANAGEMENT (City of Mandurah) % 4 $6,372.75 $180,826.78 ESTIMATED GST PAYABLE $15,931.88 SURVEY, DESIGN AND DOCUMENTATION ETHNOGRAPHIC SURVEYS AND CLEARANCES OPTION 3 - 4.5.2 - SUPERSTRUCTURE - TOTAL OF PRELIMINARY COST INDICATION Mandurah Bridge Upgrade Indicative Cost Indication $196,758.66 Appendix D Whole of Life Cost Analysis Summary of all NPV Results using different discount & inflation rate scenarios NPV calculations - Options 1 to 5 for Scenario 3 (as a sample of calculations done for all scenarios) 61/26421/105205 Old Mandurah Traffic Bridge (Bridge No. 230) Economic Viability Assessment for Replacement of the Bridge Old Mandurah Traffic Bridge (Bridge No. 230) over Mandurah Estuary - Summary Summary of NPV Results from sensitivity analysis using different discount & inflation rate scenarios Scenario Discount Rate Inflation Rate Option (refer notes below) 1 2 3 4 5 1 6.00% 2.00% 2 6.00% 2.75% 3 6.00% 3.50% 4 7.50% 2.00% 5 7.50% 2.75% 6 7.50% 3.50% 7 9.00% 2.00% 8 9.00% 2.75% 9 9.00% 3.50% Lower replace cost Higher refurb & maintain 6.00% 3.50% 6.00% 3.50% -13,771 -13,331 -27,157 -19,775 -15,425 -14,902 -14,456 -27,830 -20,362 -15,883 -20,357 -19,882 -27,061 -19,152 -15,049 -23,866 -23,208 -30,697 -22,788 -17,776 Estimated NPV ($ 000's) -17,700 -17,242 -29,137 -21,484 -16,758 -19,770 -19,304 -29,902 -22,128 -17,261 -22,312 -21,837 -30,697 -22,788 -17,776 -14,775 -14,330 -27,760 -20,301 -15,836 -16,152 -15,700 -28,464 -20,909 -16,310 -17,840 -17,381 -29,193 -21,531 -16,795 -12,847 -12,412 -26,505 -19,200 -14,977 Most favourable (highest) NPV of all options Most favourable (highest) NPV of Options 1 - 4 only Summary of assumptions for each option: Option 1 - Upgrade bridge capacity to 100% T44 & Grp 1 Vehicles Construct substructure & superstructure repairs including RCO as detailed in report in 2011. Estimated cost $8.613 million as per cost indication. Life of bridge after refurbishment is estimated to be 30 years, providing at the least that the following maintenance works are carried out over the bridge life. Replace bridge with new bridge in 30 years at cost of $25 million as per AECOM Concept Report cost for incrementally launched bridge. Carry out substructure maintenance works in 10 years time as detailed in report. Estimated cost $700k as per cost indication. Carry out superstructure maintenance works in 10 years time as detailed in report. Estimated cost $200k as per cost indication. Carry out further substructure maintenance works in 20 years time as detailed in report. Estimated cost $700k as per cost indication. Carry out further superstructure maintenance works in 20 years time as detailed in report. Estimated cost $260k as per cost indication. Carry out routine maintenance over the bridges life, say $50k per 5 year cycle Option 2 - Retain bridge at existing 17 tonne load capacity Construct substructure & superstructure repairs including RCO as detailed in report in 2011. Estimated cost $8.230 million as per cost indication. Life of bridge after refurbishment is estimated to be 30 years, providing at the least that the following maintenance works are carried out over the bridge life. Replace bridge with new bridge in 30 years at cost of $25 million as per AECOM Concept Report cost for incrementally launched bridge. Carry out substructure maintenance works in 10 years time as detailed in report. Estimated cost $700k as per cost indication. Carry out superstructure maintenance works in 10 years time as detailed in report. Estimated cost $130k as per cost indication. Carry out further substructure maintenance works in 20 years time as detailed in report. Estimated cost $700k as per cost indication. Carry out further superstructure maintenance works in 20 years time as detailed in report. Estimated cost $200k as per cost indication. Carry out routine maintenance over the bridges life, say $50k per 5 year cycle Option 3 - Convert bridge to pedestrian-only footbridge (5 kPa load capacity) Construct substructure & superstructure repairs including RCO as detailed in report in 2011. Estimated cost $6.567 million as per cost indication. Life of bridge after refurbishment is estimated to be 30 years, providing at the least that the following maintenance works are carried out over the bridge life. Construct new traffic bridge in 2015 at cost of $25 million as per AECOM Concept Report cost for incrementally launched bridge. Carry out substructure maintenance works in 10 years time as detailed in report. Estimated cost $700k as per cost indication. Carry out superstructure maintenance works in 10 years time as detailed in report. Estimated cost $70k as per cost indication. Carry out further substructure maintenance works in 20 years time as detailed in report. Estimated cost $700k as per cost indication. Carry out further superstructure maintenance works in 20 years time as detailed in report. Estimated cost $200k as per cost indication. General maintenance works for the new bridge costing $50k every 10 years are incurred. Carry out routine maintenance over the old bridges life, say $50k per 5 year cycle Option 4 - Construct incrementally launched, 3-lane bridge as per AECOM Concept Report Construct new incrementally launched, 3-lane bridge as per AECOM Concept Report in 2015. Estimated cost is $25 million as specified in this report. Estimated cost above includes contractor site facilities and overheads, but excludes contingency & risk, contract administration, design & consultancy fees, road approaches, fishing platform, services relocation and escalation as noted in AECOM report. Estimated life of new bridge is 100 yrs, with associated maintenance works carried out as per below. General maintenance works costing $50,000 every 10 years are incurred following completion of the bridge. Option 5 - Construct incrementally launched, 2-lane bridge (with rates factored down from AECOM Concept Report) Option included for purposes of direct comparison between upgrade of existing 2-lane bridge, and replacement with new 2-lane bridge. Construct new incrementally launched, 2-lane bridge (for purposes of comparing new structure of equivalent width to existing structure). Cost is estimated as $19.5 million by factoring down cost of 3-lane bridge specified in AECOM Concept Report Estimated cost above includes contractor site facilities and overheads, but excludes contingency & risk, contract administration, design & consultancy fees, road approaches, fishing platform, services relocation and escalation as noted in AECOM report. Estimated life of new bridge is 100 yrs, with associated maintenance works carried out as per below. General maintenance works are estimated at $40,000 every 10 years following completion of the bridge, calculated by factoring down maintenance works for 3-lane bridge. Additional scenarios to test sensitivity to estimated capital and maintenance costs Using the most favourable discount rate and inflation rate for Option 4, the following adjustments were made to the cashflow assumptions: Lower Replace cost As per Options described above, except cost for new replacement bridge taken as $21 million, in 30 years for Options 1 & 2, and in 2015 for Options 3 & 4 Replacement bridge taken as $16 million in 2015 for Option 5 Higher Refurb and Maintain As per Options described above, except cost the substructure & superstructure repairs including RCO in 2011, and cost for substructure & superstructure maintenance in 10 years & 20 years for Options 1 & 2 slightly increased. Old Mandurah Traffic Bridge NPV Analysis (5 options).xls Summary Old Mandurah Traffic Bridge (Bridge No. 230) over Mandurah Estuary - Scenario 3 Option 1 - Upgrade bridge capacity to 100% T44 & Grp 1 Vehicles Assumptions: Construct substructure & superstructure repairs including RCO as detailed in report in 2011. Estimated cost $8.613 million as per cost indication. Life of bridge after refurbishment is estimated to be 30 years, providing at the least that the following maintenance works are carried out over the bridge life. Replace bridge with new bridge in 30 years at cost of $25 million as per AECOM Concept Report cost for incrementally launched bridge. Carry out substructure maintenance works in 10 years time as detailed in report. Estimated cost $700k as per cost indication. Carry out superstructure maintenance works in 10 years time as detailed in report. Estimated cost $200k as per cost indication. Carry out further substructure maintenance works in 20 years time as detailed in report. Estimated cost $700k as per cost indication. Carry out further superstructure maintenance works in 20 years time as detailed in report. Estimated cost $260k as per cost indication. Carry out routine maintenance over the bridges life, say $50k per 5 year cycle Discount & inflation rates as below Values below in $000's Sources of Cash Flow Capital - substructure & superstructure repairs Capital - new bridge Substructure maintenance in 10 yrs Superstructure maintenance in 10 yrs Substructure maintenance in 20 yrs Superstructure maintenance in 20 yrs Routine maintenance every 5 years ($ 000's) Year 8,613 25,000 700 200 700 260 50 Yr 0 Yr 30 Yr 10 Yr 10 Yr 20 Yr 20 Yr 5 cycle NPV Analysis Discount Rate: Inflation Rate: 6.00% 3.50% Discount Factor 1.00 0.94 0.89 0.84 0.79 0.75 0.70 0.67 0.63 0.59 0.56 0.53 0.50 0.47 0.44 0.42 0.39 0.37 0.35 0.33 0.31 0.29 0.28 0.26 0.25 0.23 0.22 0.21 0.20 0.18 0.17 Escalation Factor 1.00 1.04 1.07 1.11 1.15 1.19 1.23 1.27 1.32 1.36 1.41 1.46 1.51 1.56 1.62 1.68 1.73 1.79 1.86 1.92 1.99 2.06 2.13 2.21 2.28 2.36 2.45 2.53 2.62 2.71 2.81 Year Year number 2011 0 2012 1 2013 2 2014 3 2015 4 2016 5 2017 6 2018 7 2019 8 2020 9 2021 10 2022 11 2023 12 2024 13 2025 14 2026 15 2027 16 2028 17 2029 18 2030 19 2031 20 2032 21 2033 22 2034 23 2035 24 2036 25 2037 26 2038 27 2039 28 2040 29 2041 30 Capital Expenditure Maintenance - Substructure Maintenance - Superstructure Maintenance - Routine -8613 Cash Flow -8613 0 0 0 0 -50 0 0 0 0 -950 0 0 0 0 -50 0 0 0 0 -1010 0 0 0 0 -50 0 0 0 0 -25000 Discounted Cash Flow Inflated Cash Flow -8613 -8613 0 0 0 0 0 0 0 0 -37 -44 0 0 0 0 0 0 0 0 -530 -748 0 0 0 0 0 0 0 0 -21 -35 0 0 0 0 0 0 0 0 -315 -627 0 0 0 0 0 0 0 0 -12 -28 0 0 0 0 0 0 0 0 -4353 -12217 NPV -25000 -700 -200 -50 -50 -700 -260 -50 -50 -50 -22,312 Option 2 - Retain bridge at existing 17 tonne load capacity Assumptions: Construct substructure & superstructure repairs including RCO as detailed in report in 2011. Estimated cost $8.230 million as per cost indication. Life of bridge after refurbishment is estimated to be 30 years, providing at the least that the following maintenance works are carried out over the bridge life. Replace bridge with new bridge in 30 years at cost of $25 million as per AECOM Concept Report cost for incrementally launched bridge. Carry out substructure maintenance works in 10 years time as detailed in report. Estimated cost $700k as per cost indication. Carry out superstructure maintenance works in 10 years time as detailed in report. Estimated cost $130k as per cost indication. Carry out further substructure maintenance works in 20 years time as detailed in report. Estimated cost $700k as per cost indication. Carry out further superstructure maintenance works in 20 years time as detailed in report. Estimated cost $200k as per cost indication. Carry out routine maintenance over the bridges life, say $50k per 5 year cycle Discount & inflation rates as below Values below in $000's Sources of Cash Flow Capital - substructure & superstructure repairs Capital - new bridge Substructure maintenance in 10 yrs Superstructure maintenance in 10 yrs Substructure maintenance in 20 yrs Superstructure maintenance in 20 yrs Routine maintenance every 5 years ($ 000's) Year 8,230 25,000 700 130 700 200 50 Yr 0 Yr 30 Yr 10 Yr 10 Yr 20 Yr 20 Yr 5 cycle NPV Analysis Discount Rate: Inflation Rate: 6.00% 3.50% Discount Factor 1.00 0.94 0.89 0.84 0.79 0.75 0.70 0.67 0.63 0.59 0.56 0.53 0.50 0.47 0.44 0.42 0.39 0.37 0.35 0.33 0.31 0.29 0.28 0.26 0.25 0.23 0.22 0.21 0.20 0.18 0.17 Escalation Factor 1.00 1.04 1.07 1.11 1.15 1.19 1.23 1.27 1.32 1.36 1.41 1.46 1.51 1.56 1.62 1.68 1.73 1.79 1.86 1.92 1.99 2.06 2.13 2.21 2.28 2.36 2.45 2.53 2.62 2.71 2.81 Year Year number 2011 0 2012 1 2013 2 2014 3 2015 4 2016 5 2017 6 2018 7 2019 8 2020 9 2021 10 2022 11 2023 12 2024 13 2025 14 2026 15 2027 16 2028 17 2029 18 2030 19 2031 20 2032 21 2033 22 2034 23 2035 24 2036 25 2037 26 2038 27 2039 28 2040 29 2041 30 Capital Expenditure Maintenance - Substructure Maintenance - Superstructure Maintenance - Routine -8230 Cash Flow -8230 0 0 0 0 -50 0 0 0 0 -880 0 0 0 0 -50 0 0 0 0 -950 0 0 0 0 -50 0 0 0 0 -25000 Discounted Cash Flow Inflated Cash Flow -8230 -8230 0 0 0 0 0 0 0 0 -37 -44 0 0 0 0 0 0 0 0 -491 -693 0 0 0 0 0 0 0 0 -21 -35 0 0 0 0 0 0 0 0 -296 -589 0 0 0 0 0 0 0 0 -12 -28 0 0 0 0 0 0 0 0 -4353 -12217 NPV -25000 -700 -130 -50 -50 -700 -200 -50 -50 -21,837 Old Mandurah Traffic Bridge NPV Analysis (5 options).xls Scenario 3 -50 Option 3 - Convert bridge to pedestrian-only footbridge (5 kPa load capacity) Assumptions: Construct substructure & superstructure repairs including RCO as detailed in report in 2011. Estimated cost $6.567 million as per cost indication. Life of bridge after refurbishment is estimated to be 30 years, providing at the least that the following maintenance works are carried out over the bridge life. Construct new traffic bridge in 2015 at cost of $25 million as per AECOM Concept Report cost for incrementally launched bridge. Carry out substructure maintenance works in 10 years time as detailed in report. Estimated cost $700k as per cost indication. Carry out superstructure maintenance works in 10 years time as detailed in report. Estimated cost $70k as per cost indication. Carry out further substructure maintenance works in 20 years time as detailed in report. Estimated cost $700k as per cost indication. Carry out further superstructure maintenance works in 20 years time as detailed in report. Estimated cost $200k as per cost indication. General maintenance works for the new bridge costing $50k every 10 years are incurred. Carry out routine maintenance over the old bridges life, say $50k per 5 year cycle Discount & inflation rates as below Values below in $000's Sources of Cash Flow Capital - substructure & superstructure repairs Capital - new bridge Substructure maintenance in 10 yrs Superstructure maintenance in 10 yrs Substructure maintenance in 20 yrs Superstructure maintenance in 20 yrs New bridge general maintenance - 10 yr cycle Routine maintenance every 5 years ($ 000's) Year 6,567 25,000 700 70 700 200 50 50 Yr 0 Yr 4 Yr 10 Yr 10 Yr 20 Yr 20 Yr 14, 24 Yr 5 cycle NPV Analysis Discount Rate: Inflation Rate: 6.00% 3.50% Discount Factor 1.00 0.94 0.89 0.84 0.79 0.75 0.70 0.67 0.63 0.59 0.56 0.53 0.50 0.47 0.44 0.42 0.39 0.37 0.35 0.33 0.31 0.29 0.28 0.26 0.25 0.23 0.22 0.21 0.20 0.18 0.17 Escalation Factor 1.00 1.04 1.07 1.11 1.15 1.19 1.23 1.27 1.32 1.36 1.41 1.46 1.51 1.56 1.62 1.68 1.73 1.79 1.86 1.92 1.99 2.06 2.13 2.21 2.28 2.36 2.45 2.53 2.62 2.71 2.81 Year Year number 2011 0 2012 1 2013 2 2014 3 2015 4 2016 5 2017 6 2018 7 2019 8 2020 9 2021 10 2022 11 2023 12 2024 13 2025 14 2026 15 2027 16 2028 17 2029 18 2030 19 2031 20 2032 21 2033 22 2034 23 2035 24 2036 25 2037 26 2038 27 2039 28 2040 29 2041 30 -50 -50 Capital Expenditure Maintenance - Substructure Maintenance - Superstructure General & Routine Maintenance -6567 Cash Flow -6567 0 0 0 -25000 -50 0 0 0 0 -820 0 0 Discounted Cash Flow Inflated Cash Flow -6567 -6567 0 0 0 0 0 0 -19802 -22724 -37 -44 0 0 0 0 0 0 0 0 -458 -646 0 0 0 0 NPV -25000 -700 -70 -50 -50 -700 -200 -50 -50 -50 0 -50 -50 0 0 0 0 -950 0 0 0 -50 -50 0 0 0 0 0 0 0 -22 -36 -21 -35 0 0 0 0 0 0 0 0 -296 -589 0 0 0 0 0 0 -12 -28 -12 -28 0 0 0 0 0 0 0 0 0 0 -30,697 Option 4 - Construct incrementally launched, 3-lane bridge as per AECOM Concept Report Assumptions: Construct new incrementally launched, 3-lane bridge as per AECOM Concept Report in 2015. Estimated cost is $25 million as specified in this report. Estimated cost above includes contractor site facilities and overheads, but excludes contingency & risk, contract administration, design & consultancy fees, road approaches, fishing platform, services relocation and escalation as noted in AECOM report. Estimated life of new bridge is 100 yrs, with associated maintenance works carried out as per below. General maintenance works costing $50,000 every 10 years are incurred following completion of the bridge. Discount & inflation rates as below Values below in $000's Sources of Cash Flow Capital General maintenance - 10 yr cycle ($ 000's) Year 25,000 50 Yr 4 Yr 14, 24 NPV Analysis Discount Rate: Inflation Rate: 6.00% 3.50% Discount Factor 1.00 0.94 0.89 0.84 0.79 0.75 0.70 0.67 0.63 0.59 0.56 0.53 0.50 0.47 0.44 0.42 0.39 0.37 0.35 0.33 0.31 0.29 0.28 0.26 0.25 0.23 0.22 0.21 0.20 0.18 0.17 Escalation Factor 1.00 1.04 1.07 1.11 1.15 1.19 1.23 1.27 1.32 1.36 1.41 1.46 1.51 1.56 1.62 1.68 1.73 1.79 1.86 1.92 1.99 2.06 2.13 2.21 2.28 2.36 2.45 2.53 2.62 2.71 2.81 Year Year number 2011 0 2012 1 2013 2 2014 3 2015 4 2016 5 2017 6 2018 7 2019 8 2020 9 2021 10 2022 11 2023 12 2024 13 2025 14 2026 15 2027 16 2028 17 2029 18 2030 19 2031 20 2032 21 2033 22 2034 23 2035 24 2036 25 2037 26 2038 27 2039 28 2040 29 2041 30 Capital Expenditure General Maintenance -25000 -50 -50 Cash Flow 0 0 0 0 -25000 0 0 0 0 0 0 0 0 0 -50 0 0 0 0 0 0 0 0 0 -50 0 0 0 0 0 0 Discounted Cash Flow Inflated Cash Flow 0 0 0 0 0 0 0 0 -19802 -22724 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -22 -36 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -12 -28 0 0 0 0 0 0 0 0 0 0 0 0 NPV -22,788 Old Mandurah Traffic Bridge NPV Analysis (5 options).xls Scenario 3 Option 5 - Construct incrementally launched, 2-lane bridge (with rates factored down from AECOM Concept Report) Assumptions: Construct new incrementally launched, 2-lane bridge (for purposes of comparing new structure of equivalent width to existing structure). Cost is estimated as $19.5 million by factoring down cost of 3-lane bridge specified in AECOM Concept Report Estimated cost above includes contractor site facilities and overheads, but excludes contingency & risk, contract administration, design & consultancy fees, road approaches, fishing platform, services relocation and escalation as noted in AECOM report. Estimated life of new bridge is 100 yrs, with associated maintenance works carried out as per below. General maintenance works are estimated at $40,000 every 10 years following completion of the bridge, calculated by factoring down maintenance works for 3-lane bridge. Discount & inflation rates as below Values below in $000's Sources of Cash Flow Capital General maintenance - 10 yr cycle ($ 000's) Year 19,500 40 Yr 4 Yr 14, 24 NPV Analysis Discount Rate: Inflation Rate: 6.00% 3.50% Discount Factor 1.00 0.94 0.89 0.84 0.79 0.75 0.70 0.67 0.63 0.59 0.56 0.53 0.50 0.47 0.44 0.42 0.39 0.37 0.35 0.33 0.31 0.29 0.28 0.26 0.25 0.23 0.22 0.21 0.20 0.18 0.17 Escalation Factor 1.00 1.04 1.07 1.11 1.15 1.19 1.23 1.27 1.32 1.36 1.41 1.46 1.51 1.56 1.62 1.68 1.73 1.79 1.86 1.92 1.99 2.06 2.13 2.21 2.28 2.36 2.45 2.53 2.62 2.71 2.81 Year Year number 2011 0 2012 1 2013 2 2014 3 2015 4 2016 5 2017 6 2018 7 2019 8 2020 9 2021 10 2022 11 2023 12 2024 13 2025 14 2026 15 2027 16 2028 17 2029 18 2030 19 2031 20 2032 21 2033 22 2034 23 2035 24 2036 25 2037 26 2038 27 2039 28 2040 29 2041 30 Capital Expenditure General Maintenance -19500 -40 -40 Cash Flow 0 0 0 0 -19500 0 0 0 0 0 0 0 0 0 -40 0 0 0 0 0 0 0 0 0 -40 0 0 0 0 0 0 Discounted Cash Flow Inflated Cash Flow 0 0 0 0 0 0 0 0 -15446 -17724 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -18 -29 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -10 -23 0 0 0 0 0 0 0 0 0 0 0 0 NPV -17,776 Old Mandurah Traffic Bridge NPV Analysis (5 options).xls Scenario 3