AusNet Services - RIN Supporting Document

advertisement
RIN Supporting Information
EDPR 2016-20
(PUBLIC)
Document number
NA
Issue number
1
Status
Final
Approver
Jacqui Bridge
Date of approval
30 April 2015
AusNet Services
RIN Supporting Information
ISSUE/AMENDMENT STATUS
Issue
Number
Date
1
30 April
2015
Description
Initial document draft
Author
J Dyer
Approved
by
J Bridge
Disclaimer
This document belongs to AusNet Services and may or may not contain all available information on
the subject matter this document purports to address.
The information contained in this document is subject to review and AusNet Services may amend
this document at any time. Amendments will be indicated in the Amendment Table, but AusNet
Services does not undertake to keep this document up to date.
To the maximum extent permitted by law, AusNet Services makes no representation or warranty
(express or implied) as to the accuracy, reliability, or completeness of the information contained in
this document, or its suitability for any intended purpose. AusNet Services (which, for the purposes
of this disclaimer, includes all of its related bodies corporate, its officers, employees, contractors,
agents and consultants, and those of its related bodies corporate) shall have no liability for any loss
or damage (be it direct or indirect, including liability by reason of negligence or negligent
misstatement) for any statements, opinions, information or matter (expressed or implied) arising out
of, contained in, or derived from, or for any omissions from, the information in this document.
Contact
This document is the responsibility of AusNet Services.
Please
contact
the
indicated
owner
of
the
document
with
any
inquiries.
John Dyer
AusNet Services
Level 31, 2 Southbank Boulevard
Melbourne Victoria 3006
Ph: (03) 9695 6000
ISSUE 1
UNCONTROLLED WHEN PRINTED
2/ 16
AusNet Services
RIN Supporting Information
Table of Contents
1
Introduction .................................................................................................................................. 4
1.1
Purpose ....................................................................................................................................................... 4
1.2
Structure ...................................................................................................................................................... 4
2
Replacement Capital Expenditure Modelling ............................................................................ 4
3
Appendices ................................................................................................................................. 14
3.1
Vegetation Management Audits ............................................................................................................... 14
3.2
Forecast Distribution System Maps ......................................................................................................... 15
ISSUE 1
UNCONTROLLED WHEN PRINTED
3/ 16
AusNet Services
RIN Supporting Information
1 Introduction
1.1
Purpose
The purpose of this document is to provide information in relation to information requested in
Schedule 1 of the Regulatory Information Notice (RIN) for the forecast period 1 January 2016 to 31
December 2020.
Most of the information requested in Schedule 1 is included in AusNet Services’ submission, the
appendices to the submission, or in supporting documentation. Information is included in this
document where the submission, the appendices to the submission, or the supporting documentation
does not provide the information requested in Schedule 1.
1.2
Structure
This document provides information referenced to the numbering in Schedule 1 of the RIN.
2 Replacement Capital Expenditure Modelling
RIN
Reference
Commentary
6.1(a)(i)(A)
Data in template 2.2 has been provided in the asset categories defined in Appendix F of
the RIN with the exception of the following nine categories.
OTHER - CURRENT TRANSFORMERS
Current Transformers (CTs) measure the current flowing through a high voltage
electricity circuit within the distribution network and transform this current into
convenient quantities for use in protection and control relays. Current transformers are
located in zone substations.
OTHER - VOLTAGE TRANSFORMERS
Voltage transformers (VTs) measure the operating voltage of a high voltage electricity
circuit and transform this measurement into convenient voltages for use in protection
and control relays. VTs consist of Capacitive Voltage Transformers (CVT) and Magnetic
Voltage Transformers (MVT) (single and three-phase). Voltage transformers are
located in zone substations.
OTHER - STATION SERVICES
Station services transform high voltages to low voltages for use within the zone
substation. Low voltages are used to provide power at the station for equipment such
as lights, air conditioners and battery chargers. Includes the transformer, similar to a
distribution transformer and associated equipment such as fuses.
OTHER – EARTHING
Station earth grids are installed below ground level in zone substations. Typically, the
grids comprise stranded copper conductor that is welded together at connection and
crossover points. Vertical copper risers (typically, flat copper conductor) are then
welded to the grid and either welded or bolted to the installed plant and equipment
items.
OTHER - CAPACITOR BANK
A capacitor bank is a grouping of several identical capacitors interconnected in parallel
or in series to correct or counteract undesirable characteristics, such as power factor
ISSUE 1
UNCONTROLLED WHEN PRINTED
4/ 16
AusNet Services
RIN Supporting Information
lag or phase shifts inherent in alternating current (AC) electrical power supplies. These
are located in zone substations. This category does not include pole-top capacitors
installed on feeders.
OTHER - NEUTRAL EARTH RESISTORS
Neutral Earth Resistors (NERs) are passive devices, with no moving parts, protected
from the weather within an enclosure and only operate during medium voltage network
phase to earth faults. The NER limits the magnitude of the earth fault current that would
flow on the occurrence of a phase to earth fault in a medium voltage circuit. This
improves public safety by limiting the energy released at the fault location, reducing risk
of bushfire ignition.
OTHER - SURGE DIVERTERS
Surge arresters (also known as surge diverters) are used to protect key items of
electrical plant within the zone substation that are susceptible to internal failure following
transient lightning over-voltages or over-voltage surges created by network switching.
Surge arresters are installed between each active phase and the electrical earth grid at
66 kV line entries, on each side of power transformers, at cable ends and on 22 kV, 11
kV and 6.6 kV feeder exits from zone substations. The category does not include surge
arresters outside zone substation such as those installed on lines and distribution
transformers.
OTHER - SITE REPAIRS
The site repairs category covers civil infrastructure including buildings, environmental
systems, security fence and overall switchyard including switchyard surface, access
roads, stations lights, cable ducts and trenches, signage and name plates, support
structures and foundations that all contribute to the overall function of the stations. This
category only includes zone substation and voltage regulator sites.
OTHER – REGULATORS
Line voltage regulators are the means by which the distribution voltage is kept at the
appropriate level. Regulators are either directly mounted on a pole or on a suitable
foundation in an enclosure at the base of a pole midway along a 22kV feeder. All such
line voltage regulators are located in regional areas of Victoria. Both three-phase and
single-phase regulators are used.
6.1 (b)(i)(ii)
AusNet Services uses condition, not age-based, probability distributions to forecast
asset replacement volumes. The methods used to forecast asset replacements are
detailed in the Plant Strategies and summarised in Appendix - Network Capital
Expenditure Overview 2016-2020.
The methodology used to determine the replacement life statistics provided in the 2014
Category Analysis RIN is described in the AusNet Electricity Services Pty Ltd Category
Analysis Basis of Preparation 2014 Regulatory Year.
The replacement life statistics were based on recorded disposal life of the assets
extracted from AusNet Services’ Asset Management systems.
6.1 (b)(iii)
AusNet Services considers that a normal distribution should be used to simulate the
replacement needs of an asset category unless appropriate information is available to
develop a more appropriate distribution. Our experience is that the detailed information
is rarely available to develop a more appropriate distribution and therefore factors such
as the skewness of the distribution cannot be properly considered.
Most asset categories in Template 2.2 comprise a mix of assets including differing
material types, manufacturers and technologies. For example, wood poles in a
specified voltage range are likely to comprise a variety of timber species. Further, the
rate of deterioration of assets is dependent upon the environment and operating
conditions. The typical age when the ‘wear out’ phase becomes evident will depend
ISSUE 1
UNCONTROLLED WHEN PRINTED
5/ 16
AusNet Services
RIN Supporting Information
upon these factors and the asset condition monitoring methodology.
Any process to verify that the parameters are a reasonable estimate of life should
consider available data and experience. For example, if the estimated life is based on
recorded age at asset disposal, consideration should be given to factors such as the
proportion of assets that are replaced for reasons other than end of effective life and
asset design life.
6.1 (c) (ii) The derivation of unit costs is detailed in Appendix 7C – Unit Rates.
(iii) (iv) (v) Double counting has been avoided by developing the forecast in asset categories
consistent with AusNet Services’ budget process and by explicitly accounting for
potential double counting. For example, the conductor replacement forecast assumes a
level of ‘business as usual’ conductor replacement which is included in the total
forecast. Another example is circuit breakers where the breakers to be replaced in zone
substation rebuild projects is explicitly separated from the program of circuit breaker
replacements.
Variability in unit costs will occur in all asset categories. The variability arises from many
factors such as location, terrain, material type, structure complexity, and emergency vs
planned replacement. As described in the Unit Rates document, unit costs for most
assets have been derived from a 12 month historical period. The forecast programs are
extensions of current programs and therefore the historical unit rates should provide a
reasonable estimate of future unit costs.
6.1 (d)
The key drivers affecting asset replacement expenditure are described in Chapter 7 of
the submission, Appendix 7A – Network Capital Expenditure Overview and in the asset
plant strategies. A summary of the factors and the affected asset categories is shown
below.
Factor
Asset categories
Impact
Network safety
obligations (Rules,
codes, license
conditions, statutory
requirements)
Lines assets
including
cross-arms,
conductors, EDO
fuses.
Secondary
equipment
Most asset
categories
Assets are replaced before the end of
their effective life in order to reduce the
risk of bushfire ignition.
Asset factors –
installation profile
Poles,
cross-arms,
conductor, power
transformers,
circuit breakers
Value of Customer
Reliability (External
factor)
Zone substation
plant
The quantity of assets reaching the end
of effective life is increasing the need for
asset replacements. This particularly
affects poles, cross-arms and conductors
where historical volumes of asset
replacements have been small as a
proportion of the asset population.
(Further detail is provided in plant asset
strategy documents.)
The lower Value of Customer Reliability
combined with the use of economic
analysis to determine the timing of plant
Development of asset
management system &
techniques (Internal
planning & asset
management
approaches.)
ISSUE 1
UNCONTROLLED WHEN PRINTED
Risk based analysis leads to life
extension of lower risk assets; particularly
in stations.
Improved condition monitoring
techniques should lead to more targeted
replacement of assets resulting in lifeextension of some assets and less
failures in other asset classes.
Improved condition assessment and data
leads to more accurate forecasts of
replacement needs.
6/ 16
AusNet Services
RIN Supporting Information
Security requirements
Zone substations
replacements leads to assets remaining
in service longer (and therefore fewer
replacements than would otherwise
occur.)
The threat of terrorist related activity and
increasing theft incidents leads to
increasing measures to mitigate the risk.
These measure lead to changing
standards and higher replacement costs.
For example, a deteriorated zone
substation fence will be replaced with a
more expensive fence.
7.2 (a)(iii)
Maximum demand forecasts were prepared for each zone substation and each
distribution feeder for each year of the forecast period. The average was calculated by
summing the P50 forecast growth for each year and dividing by the number of years.
Table 2.4.1- The average growth rate for the terminating zone substation of the subtransmission line was applied.
Tables 2.4.2 and 2.4.3 - Growth rate forecasts applied directly.
Table 2.4.4 - Growth rate estimated to be the growth rate of the HV feeder the
distribution substation is connected to.
7.2 (b)
The information provided below relates to the forecast elements of Table 2.4.6.The
Historical elements of Table 2.4.6 are described in the document Reset Regulatory
Information Notice Basis of Preparation – Historical Information.
Costs included in this table are the direct costs consistent with the Project Costs
Estimating Methodology. These include costs such as the cost of project approval,
design, materials, outage planning and procurement. They exclude an allocation of
overhead costs (such as legal or HR) and exclude other costs such as network
planning.
Forecast capacity and costs associated with the subtransmission lines segment were
sourced from the KLO-DRN 66kV line and KMS1 rearrangement projects.
High voltage feeders’ capacity and costs were extracted from the specific projects
included in the forecast. The costs and capacity were allocated to urban or rural
short/long based on the current or expected categorisation of the feeder.
An analysis of historical projects was used to allocate forecast Distribution substation
expenditure into urban or rural short/long. Each substation upgrade was assumed to
add 50 kVA of capacity.
All forecast augmentation expenditure has been allocated to the NSP-initiated &
capacity related augmentation group. No expenditure was allocated to the Customerinitiated & capacity related augmentation group as the AER’s Augmentation Model
Handbook (2013) states that “…the augex model is not intended for the assessment of
capex allocated to the customer connection component of demand-driven system
capex.”
7.2 (c)
The projects and programs that have been allocated to the unmodelled augmentation
category in table 2.4.6 are shown below. These projects and programs are described in
the Electricity Distribution Network – EDPR Network Capital Expenditure Overview
2016 to 2020. Supply improvement capital expenditure is a component of the
Distribution Substations & LV program described in 12.2.3 of the Network Capital
Expenditure Overview document.
Program
(Primary driver)
Supply
ISSUE 1
UNCONTROLLED WHEN PRINTED
Proportion of
unmodelled
augmentation in
template 2.4.6
3%
Relationship to demand, service levels and
network capacity
This program is targeted at improving power
7/ 16
AusNet Services
RIN Supporting Information
improvement
Vibration
Dampers &
Armour Rods
(Safety)
Overhang
Removals
(Safety)
Animal / Bird
Proofing (Safety
and Reliability)
Enhanced
Protection &
Control (Safety
& Reliability)
55%
quality. Improvements to power quality are often
made by adding or reconfiguring circuits;
primarily at the LV level. The addition of circuits
results in augmentation of the network.
None
12%
None
22%
No relationship to demand or network capacity.
Should result in some improvement to service
through less outages.
None
7%
7.2 (d) (ii) AusNet Services has not performed any analysis of the distribution of network
(D) (E)
augmentation utilisation thresholds. A normal distribution is likely to simulate the
augmentation needs of a network segment.
The utilisation thresholds are a reasonable estimate as they are based on actual
augmentation as described below:
AER segment groups 1 & 3 – Completed projects were analysed to determine the
mean value of the utilisation threshold.
For AER segment groups 5, 6 & 7 – The utilisation threshold is that applied to actual
projects. i.e. AusNet Services augments distribution feeders when utilisation reaches
100%.
For AER segment groups 9, 10 & 11 – The utilisation threshold is that applied to actual
projects. i.e. AusNet Services augments distribution transformers when utilisation
reaches 120%.
7.2 (d) (iii) There is a low probability that any double-counting of augmentation has occurred
(C) (D)
because there are very few augmentation projects and, if any additional capacity is
added say, at a different segment, then the added capacity will be immaterial.
The parameters are a reasonable estimate as they are based on actual historical
projects and standard upgrade sizes.
7.2 (e)
There are a number of factors which may result in different augmentation requirements
for AusNet Services compared to other DNSPs. These include:
Probabilistic planning – AusNet Services applies probabilistic planning which can lead
to the deferral of augmentation that might otherwise proceed if a deterministic standard
were applied. Under probabilistic planning there may be conditions under which all the
load cannot be supplied with a network element out of service hence the N-1 criterion is
not met. This affects subtransmission and HV including subtransmission lines, zone
substations and HV feeders. AusNet Services is likely to have lower augmentation
levels on these network elements than other DNSPs that do not apply probabilistic
planning.
Active Demand Management (DM) program – AusNet Services has an active DM
program targeted at reducing peak demands. This program leads to deferral (or
indefinite postponement) of network augmentation projects. This primarily impacts zone
substations and HV feeders (as these have been the primary DM target) but will have a
secondary impact on subtransmission lines and distribution substations.
AusNet Services is likely to have lower augmentation levels on these network elements
ISSUE 1
UNCONTROLLED WHEN PRINTED
8/ 16
AusNet Services
RIN Supporting Information
than other DNSPs that do not have an active DM program.
Rural network – A large proportion of the network is rural and rural networks typically
have few interconnections and, in some cases are supplied by radial subtransmission
lines. This means that load transfers are not widely available and lead to augmentation
of the network earlier than a highly interconnected network. This primarily impacts HV
feeders, subtransmission lines and zone substations. This will result in higher
augmentation levels on these network elements than other DNSPs that have urban
networks or higher customer densities.
Residential customers – AusNet Services has a greater proportion of residential
customers than other DNSPs. The network residential customers have a summer air
conditioning peak that occurs in the evening. Because the peak occurs late in the day
there is very little offset from solar PV generation. This impacts all network segments
and will result in AusNet Services having higher augmentation than other DNSPs that
have a greater proportion of industrial and commercial customers.
Growth corridors – The network on the fringe of Melbourne contains two residential
growth corridors. The new customers connecting in these growth corridors generate
demand growth in the areas and so network augmentation is required even if demand
per customer is falling. This differs from growth in established areas where a fall in
demand offsets the growth from infill customer connections. The impact in the
forthcoming regulatory control period from these growth corridors is expected to be at
the HV feeder and distribution substation levels. This will result in AusNet Services
having higher augmentation than other DNSPs that do not have high residential growth
corridors.
8.3 (r)
8.3 (r) (i)
(A)
16 feeder projects are planned to commence or continue during the forthcoming
regulatory period:
• Upgrade CLN22
• New CRE24 Feeder
• New CLN24 Feeder
• Upgrade CPK22
• New DRN24 Feeder
• Reconfigure HPK13, 21 & 23
• Upgrade KLO14
• Extend KLO11 Feeder
• Reconfigure KLO14 & DRN22
• OFR #1 Bus & OFR11 & OFR12
• New OFR13 Feeder
• Reconfigure TT6 & EPG31
• Reconfigure TT9 & TT4
• Upgrade WT9 Feeder
• Reconfigure WT13 & WT6 Feeders
• WGL13 Upgrade
Project
Feeders
Upgrade
CLN22
CLN13
CRE33
ISSUE 1
UNCONTROLLED WHEN PRINTED
Future
Load
Transfers
Between
Feeders
& 0
Comments
CRE33 is a long feeder and is required
for LLG contingency & thus no load
transfers available. Project timing is
9/ 16
AusNet Services
RIN Supporting Information
selected after all the neighbouring
feeders reach their ratings and thus no
load transfer capability.
New
CRE24
Feeder
CLN13,
0
CLN12 &
CRE33
CRE33 is a long feeder and is required
for LLG contingency & thus no load
transfers available. Project timing is
selected after all the neighbouring
feeders reach their ratings and thus no
load transfer capability.
New
CLN24
Feeder
CLN22
0
New feeder to address new growth in SE
of CLN. Only feeder in the area is
CLN22. Project timing is selected after all
the neighbouring feeders reach their
ratings and thus no load transfer
capability.
Upgrade
CPK22
CPK11,
0
CPK12,
CPK23 &
RWN31
This is to address the low feeder rating
due to low design temperature at the start
of the feeder. Thus, load transfers
assumed zero.
New
DRN24
Feeder
DRN13 & 0
DRN23
The new feeder to address the load
growth on DRN13. DRN23 is a long rural
feeder and additional load will cause
voltage and reliability issues. Due to the
feeder configurations and these issues,
load transfer assumed to be zero.
Reconfigure HPK13, 21 230 A
HPK13, 21 & CRE21
& 23
Sufficient load transfers available
between these feeders. Thus, project is
to transfer the load.
Upgrade
KLO14
KLO24,
100 A
KMS21 &
DRN22
This project is to address KLO14 new
loads. DRN22 = 60 A & KMS21 = 40A.
Extend
KLO11
Feeder
KLO14
KLO24 feeder over-loaded. To address
new loads on KLO24. KLO14 is 100%
loaded.
0
Reconfigure KLO24,
DRN22 = 60 This project is to address KLO14 new
KLO14 & KMS21 & A & KMS21 loads and to transfer load to DRN22.
= 40A.
DRN22
DRN22
OFR
#1 OFR22
Bus
& OFR23
OFR11 &
OFR12
New
OFR13
Feeder
& 0
Project timing is selected after all the
neighbouring feeders reach their ratings
and thus no load transfer capability.
OFR22,
0
OFR11 &
OFR23
Project timing is selected after all the
neighbouring feeders reach their ratings
and thus no load transfer capability.
Reconfigure EPG31
TT6
&
EPG31
60 A
This project is to transfer load from TT6
to EPG31. Unable to transfer to TT9 as it
is carrying over the rating. No transfers.
Transfers are only to EPG31.
Reconfigure EPG31,
TT9 & TT4
TT6 & TT4
50 A
This project is to transfer load from TT9
to EPG4. Unable to transfer to EPG31
ISSUE 1
UNCONTROLLED WHEN PRINTED
10/ 16
AusNet Services
RIN Supporting Information
and TT9 - No transfers. Transfers are
only to TT4.
Upgrade
WT9
Feeder
WT12
0
Reconfigure WT6
& 100A
WT13
& SMG31
WT6
Feeders
WGL13
Upgrade
8.3 (r) (i)
(B)
WGL11
and
WGL21
WT12 does not have capacity for load
transfers.
50 A each to WT6 & SMG31.
WGL21: No WGL21 and WG12 are forecast to be >
90% loaded at time of augmentation.
transfer
capacity
WGL12: No
Transfer
capacity
Project
Load Growth Rate
Comments
Upgrade CLN22
19.8% p.a.
Growth rate 2015-2020 for
CLN13.
New CRE24 Feeder
19.8% p.a.
Growth rate 2015-2020 for
CLN13.
New CLN24 Feeder
19.8% p.a.
Growth rate 2015-2020 for
CLN13.
Upgrade CPK22
2.5% p.a.
Growth Rate for CPK22.
New DRN24 Feeder
10.2% p.a.
Growth rate 2015-2020 for
DRN13.
Reconfigure HPK13, 21 & 2.6% p.a.
23
Growth rate 2015-2020.
Upgrade KLO14
11.8% p.a.
Growth rate 2015-2020.
Extend KLO11 Feeder
11.8% p.a.
Growth rate 2015-2020 for
KLO24.
Reconfigure
DRN22
KLO14
& KLO14: 11.8% p.a.
DRN22: 2.0% p.a.
Growth rate 2015-2020.
OFR #1 Bus & OFR11 & 29.4% p.a.
OFR12
Growth rate 2015-2020 for
OFR24.
New OFR13 Feeder
Growth rate 2015-2020 for
OFR24.
Reconfigure
EPG31
TT6
29.4% p.a.
& TT6: 1.7% p.a.
EPG31: -0.2% p.a.
Reconfigure TT9 & TT4
TT9: 1.8% p.a.
TT4: 0.0% p.a.
Growth rate 2015-2020.
Upgrade WT9 Feeder
3.3% p.a.
Growth rate 2015-2020.
Reconfigure WT13 & WT6 WT13: 1.0% p.a.
Feeders
WT6: 0.7% p.a.
Growth rate 2015-2020.
WGL13 Upgrade
Growth rate 2015-2020.
ISSUE 1
UNCONTROLLED WHEN PRINTED
WGL13: 5.24% p.a.
11/ 16
AusNet Services
RIN Supporting Information
8.3 (r) (i) There are no assumed block loads and associated demand assumptions for any of the
(C)
projects.
8.3 (r) (ii)
Project
Existing
Embedded Comments
Generation Capacity
Upgrade WT9 Feeder
50 A
Temporary Grid Energy
Storage System (GESS)
is available on WT12.
There is no existing embedded generation capacity connected to the other feeders to
be augmented.
8.3 (r) (iii)
8.3 (r) (iv)
No future embedded generation is forecast for any of the feeder projects.
Project
Assumed
Embedded
Capacity
Upgrade CLN22
1000 kW
Reconfigure WT13 & WT6 400 kW
Feeders
Future Comments
Generation
Demand
management
contract
with
large
customer
for
peak
demand reduction.
Demand
management
contract
with
large
customer
for
peak
demand reduction.
There are no non-network solutions on the other feeders to be augmented.
8.3 (r) (v)
No future non-network solutions are assumed for the following feeder augmentation
projects:
• Upgrade CLN22
• New CRE24 Feeder
• New CLN24 Feeder
• Upgrade CPK22
• Reconfigure HPK13, 21 & 23
• Upgrade KLO14
• Extend KLO11 Feeder
• Reconfigure KLO14 & DRN22
• New OFR13 Feeder
• Reconfigure TT9 & TT4
• Reconfigure WT13 & WT6 Feeders
Non-network solutions are considered for the following feeder augmentation projects
• New DRN24 Feeder
• OFR #1 Bus & OFR11 & OFR12
• Reconfigure TT6 & EPG31
• Upgrade WT9 Feeder
• WGL13 Upgrade
Details of the non-network solutions are provided in Chapter 9, Demand Management.
8.3 (r) (vi)
There is no diversity between feeders. All feeders subject to augmentation and adjacent
feeders that could provide load transfer experience an evening peak.
ISSUE 1
UNCONTROLLED WHEN PRINTED
12/ 16
AusNet Services
RIN Supporting Information
10.15
Audits of vegetation management compliance are undertaken annually by Energy Safe
Victoria (ESV). Copies of the audit reports for 2011, 2012, 2013 and 2014 are attached
as an appendix to this document.
21.5
Actual and forecast payments to embedded generators to avoid network augmentation
are shown below.
Embedded
2011
Generator
Actual/budget ($end 2015)
Traralgon
Power Station
Bairnsdale
Power Station
2012
2013
-
-
C-I-C
C-I-C
2014
2015
C-I-C
C-I-C
C-I-C
C-I-C
C-I-C
C-I-C
Forecast ($end 2015)
2016
Traralgon
Power Station
Bairnsdale
Power Station
30.1
2017
2018
2019
2020
C-I-C
C-I-C
C-I-C
C-I-C
C-I-C
C-I-C
C-I-C
C-I-C
C-I-C
C-I-C
Forecast maps of AusNet Services’ distribution system for the forthcoming regulatory
control period are attached as an appendix to this document. A single new major
network asset is proposed; a sub-transmission line from zone substation KLO to zone
substation DRN.
ISSUE 1
UNCONTROLLED WHEN PRINTED
13/ 16
AusNet Services
RIN Supporting Information
3 Appendices
3.1
Vegetation Management Audits
Attached.
ISSUE 1
UNCONTROLLED WHEN PRINTED
14/ 16
AusNet Services
RIN Supporting Information
3.2
Forecast Distribution System Maps
ISSUE 1
UNCONTROLLED WHEN PRINTED
15/ 16
AusNet Services
RIN Supporting Information
ISSUE 1
UNCONTROLLED WHEN PRINTED
16/ 16
SP AusNet Distribution BFM Audit Report
Table of Contents
BUSHFIRE MITIGATION AUDIT 2011-2012........................................................................................................ 2
1.
AUDIT SCOPE AND APPROACH .............................................................................................................. 2
1.1
1.2
1.3
2.
BUSHFIRE MITIGATION PLAN......................................................................................................................... 2
ELECTRIC LINE CLEARANCE MANAGEMENT PLAN ........................................................................................ 6
CFA EXPECTATIONS FOR THE 2011/12 FIRE SEASON .................................................................................... 7
GENERAL MATTERS .................................................................................................................................. 7
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10
3.
MANAGEMENT OPERATIONAL ORGANISATION STRUCTURE .......................................................................... 7
MAJOR STEP CHANGES .................................................................................................................................. 7
NEW INITIATIVES THE ELECTRICITY SUPPLIER HAS IMPLEMENTED TO MITIGATE FIRES ................................ 8
ANALYSIS OF FAULTS FOR POTENTIAL CAUSES OF FIRE ................................................................................ 9
ANALYSIS OF ASSET FAILURES .................................................................................................................... 10
PREPARATION FOR THE FIRE DANGER PERIOD ............................................................................................. 11
FIRE SEASON OPERATIONAL PLANS ............................................................................................................. 14
EFFECTIVENESS OF THE OPERATIONAL PLANS ............................................................................................. 14
ASSISTANCE PROVIDED TO FIRE CONTROL AGENCIES ................................................................................. 15
EFFECTS OF FIRE ON ASSETS ........................................................................................................................ 16
ASSET INSPECTION AND MAINTENANCE PROGRAM ................................................................... 18
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
4.
GENERAL ..................................................................................................................................................... 18
ASSET INSPECTION ....................................................................................................................................... 19
ASSET INSPECTORS TRAINING AND QUALIFICATIONS .................................................................................. 21
CONDUCTORS AND TIES ............................................................................................................................... 22
POLE TOP ATTACHMENTS ............................................................................................................................ 23
FUSE UNITS .................................................................................................................................................. 25
SURGE DIVERTERS ....................................................................................................................................... 25
COMPANY SPECIFIC QUESTIONS .................................................................................................................. 26
VEGETATION MANAGEMENT............................................................................................................... 27
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
4.11
VEGETATION MANAGEMENT ORGANISATION STRUCTURE .......................................................................... 27
OVERVIEW ................................................................................................................................................... 27
CLEARANCE SPACE FOR ELECTRIC LINES .................................................................................................... 30
HAZARD TREES ............................................................................................................................................ 32
HABITAT TREES ........................................................................................................................................... 33
NOTIFICATION AND CONSULTATION ............................................................................................................ 34
URGENT CUTTING OR REMOVAL.................................................................................................................. 35
ADDITIONAL DUTIES OF LOCAL COUNCILS, ROADS CORPORATION AND OTHERS ....................................... 35
MANAGEMENT PROCEDURES TO MINIMISE DANGER ................................................................................... 36
DISPUTE RESOLUTION .................................................................................................................................. 36
TRAINING AND QUALIFICATIONS ................................................................................................................. 36
5.
FIELD AUDITS AND DATABASE VERIFICATION ............................................................................. 37
6.
OBSERVATIONS ......................................................................................................................................... 38
7.
CONCLUSIONS ........................................................................................................................................... 38
8.
RECOMMENDATIONS .............................................................................................................................. 39
IJM Consulting Pty Ltd
1 of 39
SP AusNet Distribution BFM Audit Report
BUSHFIRE MITIGATION AUDIT 201 1-2012
1. A U D IT S C O PE
AND
A P PR O AC H
The audit was conducted on SP AusNet Distribution (SP AusNet (D) in accordance with Energy Safe
Victoria (ESV) Bushfire Mitigation Audits 2011/2012 Scope of Works, dated August 2011, and in
conjunction with Electricity Safety Regulations and other subordinate legislation. Particular emphasis was
placed on the Policies, Procedures, and Practices adopted in the Electricity Supplier’s plans that mitigate
the potential for bushfire starts. SP AusNet’s (D) Bushfire Mitigation Plan 2011-12 Electricity Distribution
Network (BMP) and Vegetation Management Plan and Procedures 2011-2012 (VMP) have been used as
the base reference documents to outline the Company’s standard of performance, and activities
undertaken to comply with the intent of the Regulations.
As part of this implementation, an assessment of the Electricity Supplier’s assets and vegetation line
clearance was carried out in the field.
th
The Audit was conducted in three stages, between 26 September 2011 and 1st October 2011 with the
Company being given a weeks notice on all aspects of the audit to be undertaken. (SP AusNet (D)
requested that they be given 2 weeks notice of the scope and questions in the future:
1. A follow-up on issues raised from ESV’s assessment of the Company’s Bushfire Mitigation Plan;
2. A desktop assessment of the Company’s policies, procedures and work program in relation to their
Bushfire Mitigation and Vegetation Management Plans, including deviations from past practices to
determine the effectiveness of the programs over the past 12 months;
3. The field audit included a detailed check of 107 sites (104 sites in the HBRA and 3 sites in the LBRA)
after downloading the pole details and asset defects from the Company’s database. The sites were
visited with a Company representative where the detailed information taken from the Company’s
database records were crosschecked against the actual assets in the field. Where an asset
defect/anomaly existed not recorded by the Company or the vegetation clearances at the site did not
meet the new Electricity Safety (Electric Line Clearance) Regulations 2010 it was noted. The
information was then filtered to determine the:

accuracy of the Asset Inspectors inspection and data capture;

accuracy of the vegetation assessment and data capture; and

quality of the information contained in the Company’s database.
The field audits were carried out within the Electricity Suppliers licensed boundaries in accordance with
the areas specified by ESV Executive Manager Infrastructure Safety. The level of the Company’s
compliance was determined from the selections.
1.1
Bushfire Mitigation Plan
SP AusNet (D) submitted their Bushfire Mitigation Plan 2011-2012 and Bushfire Mitigation Strategy 2011th
2012 to Energy Safe Victoria (ESV) on 30 June 2011.
The Plan outlines how the Company intends to comply with the Electricity Safety Act and the Electricity
Safety (Bushfire Mitigation) Regulations 2003 plus Amendment Interim Regulations 2010.
The objectives of the SP AusNet (D) Bushfire Mitigation Plan (BMP) are to:

To be the primary tool for the implementation of SP AusNet's bushfire mitigation programs;

To compile in one place all the essential information for the implementation of SP AusNet's bushfire
mitigation programs in a format that can be readily understood by personnel at all levels;

To be an information resource on bushfire mitigation issues, relevant legislation and policies for the
control of associated operational activities;

To provide a basis for assigning responsibilities for bushfire mitigation to SP AusNet's personnel and
service providers;
IJM Consulting Pty Ltd
2 of 39
SP AusNet Distribution BFM Audit Report

To provide a consistent approach to bushfire mitigation management which ensures that changes to
personnel and organisation structure do not detract from the standard of bushfire mitigation
performance;

To minimise and control incidents with the potential to start a bushfire; and

To help demonstrate due diligence on the part of SP AusNet in preventing incidents which may cause
the ignition of fire and threaten public safety.
They are aiming to adopt the following long-term strategies to minimise the risk of electric lines starting
fires or causing electrocution.

Use skilled people and modern technology to continue to develop and improve methods of
environmental management and ongoing development of fire safe distribution assets;

Work with municipalities, landowners and other affected persons to ensure the planting of appropriate
trees near powerlines and relocation of powerlines where appropriate; and

Investigation and implementation of new technologies that reduce the risk, for example line insulation
techniques, undergrounding and line protection devices.
The Bushfire Mitigation Plan 2011-2012 and Bushfire Mitigation Strategy 2011-2012 is detailed and
covers the intent of the Regulations and at the date of the audit had not been approved by ESV.
Additional Information Requested by ESV
ESV requested clarification and additional information in relation to the BMP in an email to SP AusNet
th
dated 4 August 2011. SP AusNet provided a full response to this request, including an updated BFM
th
Plan and Strategy, in an email to ESV dated 14 September 2011.

Observation - The table of prescribed particulars of the regulations and the corresponding location of
SP AusNet Reference Documents presented in section 8.1 and 8.2 of the Plan are a reflection of the
2003 regulations and do not include amendments introduced in 2010 detailing regulations pertaining
to major electricity companies. It is suggested that the Plan be reviewed in consideration of these
amendments and omissions be addressed.
Response - Plan has been reviewed and updated accordingly.

5A(c) - The Strategy document identifies those persons responsible for carrying out the plan but does
not provide the addresses of these persons.
Response - Strategy has been updated to include this information.

5A(i) -The Plan identifies a document (Procedure BFM 21-62) as containing information regarding
various works and the due dates of these works for achieving strategies to minimise the risk of the
supply networks starting fires. No copy of this procedure was provided with the submission.
Response - Copy of BFM 21-62 provided.
The Manual identified a program to install NERs at other Zone Substations but no copy of this
program was provided with the submission.
Response - No additional NERS are planned at this stage, but this is subject to ongoing review based
on risk.

5A(j) - The Strategy document describes aerial inspection of at-risk supply networks alternating with
ground level inspections to achieve an inspection interval of less than 37 months. The quality of
information received from aerial inspection should be demonstrated to be as good as, or better than,
that obtained from ground level inspection.
Response - On 25/8/11 SP AusNet was granted an exemption by ESV to enable the implementation
of a transition program to achieve full compliance with the requirement for an inspection interval of no
longer than 37 months. In granting this exemption ESV have reviewed aerial inspection images of SP
AusNet distribution line assets and considered the enhanced ground based inspection program that
will now also include visual inspections of the upper sides of pole top hardware. On this basis ESV
have accepted that SP AusNet meets the requirement for the inspection intervals.
The plan should describe how an inspection frequency of no less than 37 months will be achieved for
electrical assets located in areas where aerial inspection cannot be undertaken.
IJM Consulting Pty Ltd
3 of 39
SP AusNet Distribution BFM Audit Report
Response - SP AusNet has identified those assets where aerial inspections cannot be performed and
for these assets will carry out ground-based inspections at an inspection interval of no longer than 37
months.

5A(k) - The Strategy document refers to refresher training in accordance with VESI training matrix.
ESV has yet to approve a training course, including practical assessment, for inspection of at-risk
supply networks.
Response - A training course for asset inspectors is being developed by Gippsland TAFE and will
require final approval by ESV. In the interim SP AusNet applied to ESV for an exemption from this
requirement until such time as the training course can be finalised and approved. ESV responded on
25/8/11 that whilst they do not propose to grant this exemption, they expect that there will be an
approved asset inspection training course in place (including a process for recognition of prior
learning) in September 2011. On this basis the expectation is that there will be a high level of
acceptance of existing asset inspectors.

5A(l)(i) - The Strategy document refers to an operational procedure when a fire occurs (BFM 21-83)
but no copy of this procedure was provided with this submission.
Response - Copy of BFM 21-83 provided.

5A(l)(ii) - the Manual document identifies the following in relation to operation and maintenance on
days of TFB. No documents were provided to support these procedures.

Permits Required for Days of Total Fire Ban (Procedure BFM 21.80).
Response - Copy of BFM 21-80 provided.

Maintenance and Construction Activities on Total Fire Ban Days (Procedure BFM 21.82).
Response - Copy of BFM 21-82 provided.

Bushfire Mitigation Strategy Plan (BFM 21-63) – Total Fire Ban Day.
Response - Copy of BFM 21-63 provided.
and also:

In general a 3.5kA phase to ground fault level is the point at which a NER is installed or the
feeder is suppressed on Days of Total Fire Ban.
Response - This is the fault level above where it has been found that a meaningful reduction in
fault level can be achieved by installing an NER.
No documents were provided to support these procedures.

5A(m) - The Manual, at section 8.4.3 describes a line inspection frequency of 5 years and 3 months
for timber poles and 10 years and 3 months for concrete poles. These inspection frequencies do not
meet the requirements for inspection of at-risk electric lines.
Response - This will be updated in the Manual to meet the new requirements.
The Manual describes investigation of significant fires by reference to BFM 21-70 and BFM 21-71 but
copies of these documents were not provided with this submission.
Response - Copies of BFM 21-70, BFM 21-70A, BFM 21-70B, BFM 21-70C, BFM 21-70D, BFM 2170E and BFM 21-71 provided.

5A(n)(i) - The Manual describes measuring the Bushfire Mitigation Index according to procedure BFM
21-67 but no copy of this procedure was included with this submission.
Response - Copy of BFM 21-67 provided.
IJM Consulting Pty Ltd
4 of 39
SP AusNet Distribution BFM Audit Report

5A(n)(ii) to (vi) - The Plan did not contain details of processes and procedures to be employed to:

Identify deficiencies in the Plan or its implementation;
Response - The Bushfire Mitigation Management Committee meets regularly and has
responsibility to review and approve the plan and then monitor its implementation. SP AusNet has
also developed and monitors the achievement of KPIs that are designed to minimise bushfire risk,
including by the implementation of programs under the plan.

Monitor and audit the effectiveness of inspections carried out under the plan;
Response - ESV carry out annual BFM audits, which include checking to ensure that nothing has
been missed by SP AusNet’s asset inspectors. Independent audits of the asset inspectors are
also carried out regularly. As indicated in the response to item 5 above, ESV have advised that
there will be an approved asset inspection training course in place (including a process for
recognition of prior learning) in September 2011.

Improve the plan and its implementation if deficiencies are identified;
Response - As per the response to the first dot point above.

Ensure necessary training is provided;
Response - SP AusNet has developed and implemented employee training policies and
procedures to ensure that both initial and refresher training is performed as required. It also
reviews these requirements for contractors as part of the process of their engagement and
ongoing employment.

Monitor and audit the competence of persons carrying out inspection under the plan.
Response - As per the response to the second dot point above.

5A(p)(i) - Providing a Private Electric Line brochure to customers with POELs does not fulfil the
requirement to enhance public awareness of the responsibilities of owners of POELs in relation to
bushfire mitigation.
Response - The following address shows the media release we drafted and distributed to kick off the
public awareness campaign. This was sent to media in regional Victoria. The following address
shows the Television and Radio advertisements we produced and which appeared on regional TV
and radio during last summer.
http://www.sp-ausnet.com.au/?id=2202421008A14E92BB2BD6129CA257694000273A6

5A(p)(ii) - No copy of the POEL brochure was provided with this submission so it is not clear if it
informs the public of the responsibility of the electricity company to inspect POELs within its
distribution areas.
Response - The following address is to our external website for people to access the Private
Overhead Electric Line brochure.

ES Act 1998 s.113B(3) (a) - While SP AusNet’s website invites the public to view the accepted
bushfire mitigation plan no copy of an accepted bushfire mitigation plan was found on its website.
Response - The accepted BFM Plan for the Electricity Distribution Network for 2010/11 can be
viewed at the following address.

ES Act 1998 s.113B(3) (b) - No mention was found in the plan or documents associated with this
submission to indicate the plan and associated documents would be made available for inspection at
the company’s principal office in Victoria.
Response - Section 7 of the plan has been updated accordingly.
The Company’s Bushfire Mitigation Plan is supported by the Bushfire Mitigation Strategy and Manual and
is a complex set of documents and in the Auditors opinion would benefit from the consolidation of
strategies, policies, and procedures to a specific document covering all aspects of their BFM programs.
IJM Consulting Pty Ltd
5 of 39
SP AusNet Distribution BFM Audit Report
1.2
Electric Line Clearance Management Plan
The Vegetation Management Plan and Procedures 2011-2012 for SP AusNet (D) was originally submitted
st
on 31 March 2011. The Plan contains the process and procedure to be employed to meet the Electricity
Safety (Clearance of Lines) Regulations 2010.
The objectives of the Vegetation Management Plan (VMP) are to:
To implement a powerline vegetation management strategy that complies with the requirements of all
participants and creates a harmonious balance for the community between preservation of the
environment, safety, and cost effectiveness.
SP AusNet (D) aims to:

Meet the requirements of the Act, Regulations and Code;

Review annually and develop management programs, processes, practices, methods and implement
efficiencies for the benefit of customers and other stakeholders;

Preserve and enhance the integrity of existing and proposed vegetation;

Minimise the frequency and length of disruptions to the general public;

Be committed to the safety of the community, as a whole, and employees engaged in the provision of
the services;

Raise awareness of all aspects of line clearance through increased communication;

Adopt the following long-term strategies to minimise the risk of electric lines starting fires and causing
electrocution;

Use skilled people and modern technology to continue to develop and improve methods of
environmental management and ongoing development of fire safe distribution assets;

Work with municipalities, landowners and other affected persons to ensure the planting of
appropriate trees near powerlines and relocation of powerlines where appropriate; and

Investigate and implement new technologies that reduce the risk eg. Line insulation techniques,
EDO fuse phase out/replacement, undergrounding, and line protection devices and fault energy
reduction measures (NERs, auto reclose suppression).
On the 8th August 2011 SP AusNet (D) received a table from ESV titled ELCMP Evaluation and was
requested to provide responses/clarifications to 2 items and amend the ELCMP accordingly:

3(a) & (b) - While the submitted plan does not describe a requirement to inspect a reported hazard
tree by a suitably qualified arborist the plan does refer to Procedure VEM 20-01 – Hazardous Tree
and 56M Assessment where this requirement might be described. VEM 20-01 requires reported
trees to be assessed by a Field Officer (not defined) as distinct from a Field Assessor (defined as
qualified and experienced).
Response: SP AusNet has removed the term Field Officer and added a definition for Assessor. SP
AusNet has also replaced the word Field Officer throughout the document with ‘Arborist’ to better
reflect the current mode of operation (see revised document VEM 20-01 attached).

The procedure calls for an Arborist’s assessment once the DB and Council(s) have agreed the tree is
a hazard. This does not quite appear to be what the regulation is calling for.
Response: SP AusNet’s interpretation of what “the procedure calls for” (referring to VEM 20-01) is
different to that of ESV. Section 9.2 of SP AusNet’s Procedure VEM 20-01 “Council / Shire Tree
Negotiations” refers only to the process of seeking an agreed approach in relation to the hazard tree
inspection program and not whether an individual tree is hazardous or not. This determination is
made by SP AusNet’s arborist.
th
These documents have been amended and were submitted to ESV on the 15 September 2011. At the
date of the audit SP AusNet (D) had not received an acceptance from ESV for their Electric Line
Clearance Management Plan.
IJM Consulting Pty Ltd
6 of 39
SP AusNet Distribution BFM Audit Report
1.3
CFA Expectations for the 2011/12 Fire Season
th
Mr Luke Heagerty conducted a briefing on 27 October 2011, which covered the expected risk and
severity of fire conditions, weather, and projected anticipated commencement of the Victorian declaration
periods. Victoria can expect an above normal grass fire potential this season, as a result of significant
rainfall across the State. This is a complete change in conditions from the last decade and providing
similar background conditions to Ash Wednesday:

Wetter seasonal rainfall this year;

Grass growth across the state is prolific and widespread, representing a return to conditions more
consistent with the long term average;

Highest on record rainfall and partial inundation has resulted in significant and widespread native
grass growth across the Mallee;

Expected above average temperatures (both day and Night) this season;

Prolific grass growth in paddocks and roadsides;

The reduction of stock during last 10 years of drought and the switch to grain farming reduces fire
breaks and adds available ground fuel; and

The forests are saturated which has reduced the risk of campaign fire potential this season.
In consideration of the above indicators the implementation of the fire declaration dates is to be
progressive across the State. These dates shall come into effect as the fire risk increases with the
st
exception of the Colac Otway and Corangamite Shires, which are to commence on the 1 November
2011. No indication was given when the remaining Shires are likely to declare but it is expected that it
would progress from the North West through the State. At the time of the audit no Shire had been
declared in SP AusNet’s operational area.
2. G E NER A L M A TT ER S
2.1
Management Operational Organisation Structure
SP AusNet’s (D) current operation/maintenance management organisation structure is outlined in the
Bushfire Mitigation Strategy:

The Group General Manager, Networks Strategy & Development has overall accountability for
Bushfire Mitigation obligations.

The Network Strategy & Planning Manager and the Manager, Networks Safety and Risk are
responsible for developing and implementing policies and strategies to satisfy Bushfire Mitigation
obligations.

The Manager Asset Engineering is responsible for the implementation of the policies and strategies
through a team comprising the Works Planning and Performance Monitoring Manager, the Works
Integration Manager and two Regional Maintenance Representatives each functionally responsible
for Bushfire Mitigation works.
2.2
Major Step Changes
SP AusNet (D) has implemented the following step changes in the last 12 months:

SP AusNet’s (D) transition plan includes an assessment that has been carried out to determine the
highest risk areas in SP AusNet (D) HBRA. The inspections are to be prioritised on risk during the
transition period. The fire consequence assessment was conducted by Doctor Tollhurst of Melbourne
University and this has been incorporated into a Network Fire Risk Model;

Priority Codes have been reviewed to provide a uniform approach to time delay between observing a
defect and maintaining or replacing the item. The alignment of the Priority Targets (PT) is across
Transmission, Distribution, and Gas. Currently the Priority Rating system across the 3 main business
streams allows for 19 different categories. The intention is to simplify this down to eight (8);
IJM Consulting Pty Ltd
7 of 39
SP AusNet Distribution BFM Audit Report

2.3
In 2011 Select Solutions changed their 56M tree data capture from a paper based process to an
electronic process using a Personal Digital Assistant (PDA). This change enables the data to be
transferred directly to the 56M database eliminating the time consuming process of hand writing on
spreadsheets in the field and then manually inputting the information into the database. This process
also reduces the possibility of errors from data inputting occurring.
New Initiatives the Electricity Supplier has Implemented to Mitigate Fires
SP AusNet (D) has implemented several major programmes and expanded some initiatives previously
commenced to mitigate fires within their operational area:

EDO Fuse replacement – This program requires the progressive replacement of 11,050 EDO units
with Boric Acid fuses over a period of 5 years. During 2011, 2,000 have been programmed for
replacement with the Company behind target at the date of the audit with 346 completed and 290
units on issue to Thiess.

Conductor replacement – This program requires the replacement of 250 kilometres of conductor
(predominantly steel conductor with a small amount of copper), which is to be carried out over a 2
year period. At the time of the audit SP AusNet (D) stated that they are behind target due to adverse
environmental conditions. The Company anticipates that they should be able to catch up during the
summer period.

Neutral Screen Service cable replacement – This program requires the replacement of approximately
28,000 neutral screen service cables over a period of 5 years. The Company are on target with
13,823 completed to date.

Introduction of a plan to inspect assets at no more than 37 month intervals - As directed by ESV, SP
AusNet is rescheduling its asset inspection program to ensure that all poles are inspected within the
st
specified 37 month window. It is aimed to achieve full compliance as per the transition plan by 31
December 2012. The Company is on target.

Ground based Asset Inspection has been in-sourced - This function was previously carried out by
UAM and SP AusNet (D) has now moved 36 of UAM’s existing asset inspectors to Select Solutions.
This commenced on 1st April 2011.
Previous commenced initiatives/step changes:

An audit of the Asset Inspection process was undertaken by an SP AusNet Internal Audit in 2011.
This reviewed the benefits of undertaking an aerial inspection program and compared the results of
maintenance items identified from conventional ground based inspections performed on the same
poles in three sample areas - Completed

The Steel conductor Assessment Guide developed by SP AusNet’s Distribution Asset Engineering
department in conjunction with experienced field personnel and is now fully operational.

Conductor replacement – This program required the replacement of 169 kilometres of aging copper
or corroded steel conductor during 2008 to 2011. At the time of the audit SP AusNet (D) have
completed 151 kilometres of this project. The remaining 3 shutdowns are to be carried out during the
summer period when access becomes available – In progress

The introduction of a mid cycle inspection that involves an aerial patrol (by helicopter) or alternatively
by ground based aerial devices (EWP, Himast, Drone, Camera on a Stick) in areas that cannot be
covered by the helicopter, of all assets in the HBRA. This is aimed at capturing issues relating to the
pole top structure that can only be detected from above, and in addition gives the Company a second
assessment of the asset half way through the cycle. This was introduced early to mid 2009 and all
st
assets are to be inspected by 31 March 2012 – In progress
IJM Consulting Pty Ltd
8 of 39
SP AusNet Distribution BFM Audit Report
2.4
Analysis of Faults for Potential Causes of Fire
Reporting Fire Starts to ESV
SP AusNet’s (D) criteria for reporting fire starts to ESV are detailed in their Bushfire Mitigation Reporting
procedure covering:

Pole Fire Report;

Pole and Crossarm Failure Report;

Flashover Report;

Plant Failure Report.
All ground and pole fires and other electrical incidents are reported to Energy Safe Victoria in accordance
with the Electricity Safety Act – Section 1.4.2 (1) & (2) and Electricity Safety (Management) Regulations
Section 27 (2) and as detailed in the ESV Distribution Business Electrical Safety Performance Reporting
Guide.
Reporting is undertaken using the following methods:

As soon as practicable report to ESV by telephone all relevant details;

Follow up with a completed Electrical Incident Confirmation Form (Schedule 1) sent to ESV by fax or
email within 2 business days of the telephone report; and

Send by fax, surface mail or email a complete Electrical Incident Report Form (Schedule 2) to ESV
within 20 business days of the telephone report
Ground Fire Starts from Electrical Distribution/Transmission Assets in the Last 12 Months
There have been 21 ground fire starts in SP AusNet (D)’s operational area over the past 12 months.
These are broken down by:

HBRA - 16

LBRA – 5
Pole Top Fires in the Last 12 Months
There have been 117 pole top fires in SP AusNet (D)’s operational area over the past 12 months. These
are broken down by:

HBRA - 114

LBRA – 3
Since January 2010 ESV has amended the definition of pole top fires to include “fires on aerial network
assets themselves (e.g. pole fires, “candling” fuses etc), irrespective of whether they start a ground fire or
not” and the Company has modified their report to comply with this directive.
Reviews Conducted on Potential Causes of Fire Starts
SP AusNet Distribution conducts reviews on potential causes of fire starts and produces a summary
report annually and they use history of fires as a catalyst to review potential causes of fire starts. The
Bushfire Mitigation Management Committee (BMMC) requests that the fire reports for the past 12 months
be reviewed and the details checked. The aims of this exercise are:

To determine if there are any trends in the probable causes of these fires, in particular, if there has
been any increase in the number of fires starting at a particular asset; and

To use these results to determine any future improvement plans concerning the management of
electrical assets.
IJM Consulting Pty Ltd
9 of 39
SP AusNet Distribution BFM Audit Report
During the period 2004 – 2010/11 there have been 18 probable causes of fire reviews carried out and of
the 18 the following 8 have been updated in 2011:

Trees;

Conductor;

Fuses;

Birds;

Pole;

Transformer Failure;

Vehicles;

Surge Diverters
An analysis carried out to identify the root cause of the failures as outlined in the “Action Plan to Mitigate
potential fires caused by SP AusNet Distribution Assets” shows the number of fires started was lower
than in the previous four years. In addition, the number of fires likely to start from conductors, joints, etc,
had dropped to 3.
A review of fire starts over the past 5 years has been conducted which has resulted in expanded
programs in the following areas:

Conductor replacement of corroded copper and steel conductor;

Conductor joint replacement;

Steel conductor audit;

Neutral Screen service cable replacement;

Fitting of Service Cable break away device when a service is replaced or repaired;

Pole top rebuild program and crossarm replacement;

Special Pole top aerial inspections;

Replacement of Air break switches with gas switches;

Reduction of bird and animal contact hazards;

Earth Testing program;

EDO fuse replacement program;

Assessment of hazard trees that are outside the clearance space; and

Publicity programs to reduce probable fires due to human activity.
All programs above have now been implemented and are ongoing.
2.5
Analysis of Asset Failures
Where an asset failure occurs on SP AusNet’s (D) system it is reported in the PowerOn Fault report
system, which also records all faults on the network. This system has a field covering the asset affected
that is linked to the root cause of each fault. Raw data for 2010-2011 is provided from this system and
used in the “Action Plan to analysis asset failures with the aim of mitigating potential fires. The report
“Action Plan to Mitigate Potential Fires caused by SP AusNet Distribution Assets” has an appendix that
lists the faults against each type of asset and the root cause of the fault.

Survey of Pole failures

Pole failure Newborough

Pole failure Xmas Hills

Strength testing of disc insulators.

Pole failure Ringwood

Bent Stay bolt failure- Gooramadda

Pole failure Benalla

Bent stay Bolt Analysis by Attar

Pole failure – by Car – Croydon

Pole Failure – Emerald
SP AusNet (D) has developed a range of strategies, which also included the analyses of asset failures,
and the introduction of advanced technologies and service life condition monitoring.
IJM Consulting Pty Ltd
10 of 39
SP AusNet Distribution BFM Audit Report
These strategies are contained on SP AusNet’s Intranet.

Conductors

Line Voltage Regulators

Capacitor Banks & Pole Top Capacitors

Poles

Circuit Breakers


Civil Infrastructure
Power Transformers
Regulators

Crossarms

Protection and Control Systems

Distribution Transformers

Public Lighting

Electrical Earths

Services Cables

MV Switches & ACR’s

Surge Diverters in Zone Substations

MV Fuse Switch Disconnectors

Neutral Earthing Devices

HV Switches, Disconnectors & Earth Switches

Auxiliary Power Supplies

Instrument Transformers

Communication Systems

Insulated Cable systems

Remote control and monitoring

Insulators/ Medium Voltage

Asset Date Gathering Networks

Line Surge Diverters
&
Station
voltage
The following projects were instigated as a direct result of reviews over the last 5 years:

Neutral Screen service cable replacement - Ongoing

Conductor replacement of corroded copper and steel conductor - Ongoing

Pole top rebuild program - Ongoing

Conductor joint replacement - Ongoing

EDO fuse replacement program - This program also involves a change of supplier for EDO fuse links
from ABB to NGK and where EDO fuse tubes are found to be > 10 years they are to be replaced with
new EDO fuse tubes - Ongoing
SP AusNet (D) has also carried out extensive risk assessments as part of it’s ESMS for the electricity
distribution network that was submitted to and received acceptance from ESV. Many of the risks
identified and assessed were associated with asset classes and subclasses.
2.6
Preparation for the Fire Danger Period
SP AusNet (D) has developed a List of Works required to be undertaken in readiness for the next Fire
Season and this is outlined in the Bushfire Mitigation Calendar of Important Events Procedure and at the
date of the audit the status of the works to be undertaken in readiness for the next fire season is as
follows:

Prepare list of outstanding critical maintenance items. Forward list to Manager Asset Engineering
and Manager, Networks Safety and Risk - Ongoing

Prepare summary of Fire Reports and issue to BMMC - Ongoing

Prepare Bushfire Mitigation Report and issue summarised report to BMMC - Ongoing

Provide BMMC with Bushfire Mitigation Status Report - Ongoing

Review Bushfire Mitigation Reports and initiate action as required - Ongoing

Resolve queries & initiate action on matters requiring attention from summarised Bushfire Mitigation
Report - Ongoing

Include summary of Bushfire Mitigation Report in Business Report - Ongoing

Arrange meetings of BMMC - Ongoing
IJM Consulting Pty Ltd
11 of 39
SP AusNet Distribution BFM Audit Report

Prepare SP AusNet Vegetation Management Plan - Complete

Approve SP AusNet’s Vegetation Management Plan - Complete

Submit Vegetation Management Plan to the ESV for approval by 28 February - Complete

Finalise Fire & General Liability Insurance Renewal Underwriting Submission - Complete

Draft Bushfire Mitigation Strategy Plan and submit to BMMC for endorsement - Complete

Submit Bushfire Mitigation Plan to ESV for approval by 1 July - Complete

Decide on advertising for summer period - Complete

Commence monthly BFM reporting to ESV until end of the fire season (BFM Index) - In progress

Issue letter and information brochures to Overhead Private Electric Line customers - In progress

Request permits to work on days of Total Fire Ban from MFB, CFA and DSE - October

Coordinate senior management review visit programs - October

Post on the Intranet copies of permits to work on Days of Total Fire Ban - November/December

Perform Senior Management Reviews - December

Target date for submission of Operational Contingency Plan (if required) - 1 December

Complete all BFM works - 1 December

Complete all vegetation works in HBRA areas - 15 December

Complete all BFM obligations - 15 December
st
st
th
th
SP AusNet has not made any significant modifications to their Bushfire Mitigation Calendar of Important
Events in the last 12 months.
Corrective action where Deadlines are not achieved Prior to the Summer Fire Season
SP AusNet (D) outlines in their Bushfire Mitigation Manual the requirement to establish an Operational
Contingency Plan detailing those lines on which fire prevention work is incomplete and for which possible
disconnection maybe required on days of Total Fire Ban. This is supported by the Operational
Contingency Procedures Plan that describes the process to be undertaken before supply can be
disconnected.
The role of the Bushfire Mitigation Management Committee (BMMC) is to oversee the promulgation of
policy and standards and review performance of the various bushfire mitigation programs.
The Committee focuses on a range of matters such as to:

Approve changes to policy or standards, which impact the bushfire mitigation program and the
Business Rules;

Initiate review of operating, design and maintenance standards where required to meet the KPI’s of
the Bushfire Mitigation Program

Co-ordinate the Insurance Program and the Public Awareness Program;

Initiate and maintain appropriate systems to monitor performance and compliance, Initiate recovery
actions when required;

Arrange Senior Management Audits;

Monitor significant events;

Liaise at high level with external authorities;

Report to the Environmental Management Committee;

Report performance against KPI’s to Asset Governance Committee and key stakeholders:

Assess network bushfire risks in accordance with the corporate risk framework;
IJM Consulting Pty Ltd
12 of 39
SP AusNet Distribution BFM Audit Report

Monitor the delivery of the Bushfire Mitigation program against KPI’s and initiate corrective actions
where required;

Monitor the scope of internal audits to ensure desired compliance objectives are being met;

Review corrective actions from internal and external BFM audits and initiate corrective actions as
required;

Manage and coordinate audits conducted by ESV;

Oversee the management of the risk of SP AusNet’s assets causing a bushfire.
The frequency of meetings is monthly or more often as required, especially in the lead up to the fire
season.
SP AusNet has a number of mature processes to monitor the performance of contractors across their
operational area to ensure activities are completed by the Fire Danger Period deadlines. Monitoring has
always ensured the Fire Danger Period deadlines are achieved and therefore to date SP AusNet (D) has
not needed to put corrective actions in place.
These processes cover:

monthly contractor meetings;

regular field inspections;

regular bushfire mitigation meetings.
Works Remaining to be completed prior to the CFA Fire Declaration Dates
At the time of audit SP AusNet (D) was in the process of working through the items identified for
rectification in preparation for the Fire Danger Period. Their Look Ahead Report lists any outstanding
st
works to be completed prior to their nominal Fire Danger Period (nominally the 1 December). The
Company had completed their September BFM meeting but the minutes were not finalised so for this
report the August 2011 outstanding works figures have been used:

Attachments – 897

Bird Covers – 378

Conductors – 11

Line Inspection – 4009

Surge Diverters - 0

Poles Not Fire Safe

Group 1 & 2 (unserviceable poles) – 196

Group 3 (Limited Life past Inspection) – 122
Reporting Requirements to ESV on Outstanding Works Prior to and During the Fire Danger Period
SP AusNet (D) provides regular reports in an agreed format to ESV with additional information supplied
on request. The Bushfire Mitigation Index report (BMI) is prepared and submitted to ESV between
September and declaration date monthly, and during the Fire Danger Period monthly or more often by
agreement with ESV.
The Company stated that they have the resources to complete all outstanding works prior to the Fire
Danger Period. Due to adverse environmental conditions and limited access the Company has secured
additional resources to ensure completion of all outstanding works prior to fire danger period. These
additional resources are made up of:

Tenix;

Thiess;

Jemena;

Transfield;

Conneq.
IJM Consulting Pty Ltd
13 of 39
SP AusNet Distribution BFM Audit Report
2.7
Fire Season Operational Plans
In general terms, during the Fire Danger Period SP AusNet Distribution’s network is operated as normal
and apart from the “CFA Restrictions for the Declared Fire Danger Period” procedure and the “Bushfire
Mitigation Strategy 2011-2012” there are no operations or maintenance activities on the network that are
specific to the declared Fire Danger Period.

The CFA Restriction procedure specifies fire fighting equipment required on vehicles travelling offroad during the declared fire season. SP AusNet (D) has adopted the CFA requirements for vehicles
as standard;

The Bushfire Mitigation Strategy 2011-2012 outlines the process on how to deal with urgent defect
work identified by Asset Inspectors during the declared Fire Danger Period.
Operational Plans Followed in the Event of a Fire
SP AusNet (D) has a procedure that sets out the process to be followed when SP AusNet Distribution
personnel or their contractors attend a fire. The fault crew is to immediately call Customer Energy and
Operations Team (CEOT) and inform them of:

any isolation required;

the size of the fire;

the requirement for the CFA/MFB to attend; and

another crew is required to assist.
The fault crew assesses the immediate public risk and isolates the fault if appropriate. The fault crew is
to remain on site until the fire is out or SP AusNet Networks or contractor personnel have relieved them.
The site is not to be left until a thorough inspection of the affected assets has been performed and the
assets confirmed as good. That is, leaving the assets permanently or temporarily repaired so that the
appropriate standards are maintained. This is to be carried out in conjunction with the CFA (or MFB if
appropriate) to ensure no poles/cross arms continue to burn.
When a fire or disaster occurs and is established by a MECC Coordinator, the authorised Electrical
Operator is not to proceed into the defined Fire Disaster Zone either through road blocks or other access
routes.
SP AusNet (D) had several minor fires (grass and pole top) during the Fire Danger Period 2010/11 of
which the process above was put in place and this proved to be effective. The procedure allows for
escalation should it be required associated with the size of the fire.
2.8
Effectiveness of the Operational Plans
The Bushfire Mitigation Strategy 2011-2012 outlines the SP AusNet’s Centre Electrical Operational Team
(CEOT) responsibilities on days of TFB covering the following activities.
Urgent Defective Private Lines - Disconnection of any outstanding urgent defective Private Overhead
Electric Lines (POELs), which includes:

Arranging Field Crews to disconnect any urgent defective POELs;

Contacting owners of urgent defective POELs to advise them of the disconnection;

Arranging Field Crews to reconnect any disconnected POELs when TFB has ended.
The Asset Inspections Manager has the responsibility to ensure that the CEOT has up to date information
on all urgent defective POELs required to be disconnected on TFB days.
Fires - The Availability Officer is to be advised immediately of any fires attended by fault crews,
regardless of how they were started
IJM Consulting Pty Ltd
14 of 39
SP AusNet Distribution BFM Audit Report
Sustained Unplanned Interruptions to Supply - If any feeder or HV line protection device operates and
supply is interrupted (other than successful reclosers) and the fault is not known:

The feeder or line must be patrolled prior to attempting restoration.

If the suppression of an Automatic Circuit Recloser or Circuit Breaker was for the sole purpose of
working on the line, then only one attempt to reclose may be made. This is dependent upon the
conditions of the day and should not be attempted under extreme conditions of wind and temperature.
Area Operations Officers - To notify the CEOT of any planned interruptions that have been cancelled, and
those that have Regional Manager’s approval to proceed. The CEOT in turn is to:

Advise the Faults Call Centre and the NSC Complaints Resolution Team Leaders

Update Power-on to reflect the cancellation

Liaise with Senior Network Services Representatives as to media releases of cancelled interruptions
where appropriate
This information is to be available to the Faults Team Leader no later than 15 minutes prior to the planned
interruption time.
Auto Reclose Suppression - The Manager, Network Operations shall ensure auto reclose is suppressed
on designated feeders supplying HBRA areas on TFB days.
POEL Disconnections - POELS with urgent defects shall, where practicable, be disconnected for the full
period of the TFB.
st
st
On 31 January 2011 the CFA declared a TFB day for the East Gippsland District for 1 February 2011.
On receipt of this advice, the CEOT sent an email to all SP AusNet personnel informing them of this. As
a result, Level 2 in SPIRACS was declared.
2.9
Assistance Provided to Fire Control Agencies
SP AusNet Distribution’s Bushfire Mitigation Manual outlines the assistance to be provided to Emergency
Response Authorities.
SP AusNet is represented on each of the 8 Regional Fire Management Planning Committees and support
is provided to the fire control agencies on an as needs basis through this committee process. The
Company has also established strong working relationships and communication links with Municipal Fire
Prevention Committees, ESV, CFA, Department of Sustainability and Environment, Local Government
and other relevant authorities. This includes developing guidelines that set out the electrical hazards,
which may be encountered in carrying out their duties and in conducting any investigation of fires near
their electricity assets.
SP AusNet personnel maintain contact with the CFA to discuss matters of common interest including
liaison, fire hazard ratings and fire period declarations; and to assess climatic conditions and bushfire risk
for the current season in consultation with fire authorities in order to decide whether the completion of
bushfire mitigation activities in certain regions need to be advanced to ensure zero index is achieved by
declaration.
In the event of a major fire necessitating field work such as major repairs and/or protection of our assets,
the SP AusNet officer responsible for bushfire mitigation, or other appropriate officer as nominated by the
SP AusNet, is to co-ordinate and direct activities associated with the fire (field assessment, damage,
reinstatement, operational requirements) and set up a base and establish communications/liaison with the
CFA, Operating Authority and field areas.
IJM Consulting Pty Ltd
15 of 39
SP AusNet Distribution BFM Audit Report
2.10 Effects of Fire on Assets
As a direct result of the Victorian Bushfire Royal Commission report SP AusNet (D) has implemented the
following in order to achieve the recommendations:
Recommendation 27

The progressive replacement of all SWER (single-wire earth return) power lines in Victoria with aerial
bundled cable, underground cabling, or other technology that delivers greatly reduced bushfire risk.
The replacement program should be completed in the areas of highest bushfire risk within 10 years
and should continue in areas of lower bushfire risk as the lines reach the end of their engineering
lives

The progressive replacement of all 22-kilovolt distribution feeders with aerial bundled cable,
underground cabling or other technology that delivers greatly reduced bushfire risk as the feeders
reach the end of their engineering lives. Priority should be given to distribution feeders in the areas of
highest bushfire risk.
Status – This recommendation was referred by the Victorian Government to the Powerline Bushfire
Safety Taskforce (PBST) for consideration. The PBST (established by the Victorian Government in
2010 and includes representatives from ESV and the distribution businesses), is due to submit its
th
final report to the Victorian government by 30 September 2011 and it SP AusNet’s (D) intention to
implement this recommendation once it has been reviewed and agreed by the Victorian Government
and subject to funding.
Recommendation 28

The State (through Energy Safe Victoria) require distribution businesses to change their asset
inspection standards and procedures to require that all SWER lines and all 22-kilovolt feeders in
areas of high bushfire risk are inspected at least every three years.
Status – an exemption has been received from ESV to allow SP AusNet (D) to implement a
transitional program to achieve full compliance by 2015
Recommendation 29

The State (through Energy Safe Victoria) require distribution businesses to review and modify their
current practices, standards and procedures for the training and auditing of asset inspectors to
ensure that registered training organisations provide adequate theoretical and practical training for
asset inspectors.
Status – A training course for Asset Inspectors is being developed by Gippsland TAFE in associated
with the industry and requires final approval by ESV. In the interim SP AusNet applied to ESV for an
exemption for this requirement until the training course can be finalised and approved.
In response to this application ESV stated in their letter dated 25th August 2011 that ESV does not
propose to grant an exemption from the requirements of the Regulation 5A(k). ESV expects there
shall be an approved asset inspection training course in place (including a process for recognition of
prior learning) in September 2011. The Exemption is that there shall be a high level of acceptance of
existing asset inspectors.
Recommendation 30

The State amend the regulatory framework for electricity safety to require that distribution businesses
adopt, as part of their management plans, measures to reduce the risks posed by hazard trees that
is, trees that are outside the clearance zone but that could come into contact with an electric power
line having regard to foreseeable local conditions.
Status – SP AusNet applied for and received an Exemption from ESV to enable a transition period to
achieve full compliance with the requirements for maintaining the minimum clearance space by
nominated dates depending on the assets involved. ESV granted the Exemption on the basis that it
recognised that the achievement of full compliance will take time.
IJM Consulting Pty Ltd
16 of 39
SP AusNet Distribution BFM Audit Report
Recommendation 31

Municipal councils include in their municipal fire prevention plans for areas of high bushfire risk
provision for the identification of hazard trees and for notifying the responsible entities with a view to
having the situation redressed.
Status – an exemption has been received from ESV to allow SP AusNet (D) a transition period to
achieve full compliance.
SP AusNet applied for and received funding under its “Enhanced Safety Program” in the last
Electricity Distribution Price Review (EDPR) following the determination by the Australian Energy
Regulator (AER) to implement the requirements of Recommendations 30 & 31 over the 5 year period
between 2011 and 2015.
Recommendation 32

The State (through Energy Safe Victoria) require distribution businesses to do the following:

disable the reclose function on the automatic circuit reclosers on all SWER lines for the six weeks
of greatest risk in every fire season

adjust the reclose function on the automatic circuit reclosers on all 22-kilovolt feeders on all total
fire ban days to permit only one reclose attempt before lockout.
Status – This Recommendation was referred by the Victorian Government to the PBST for
consideration. The PBST is due to submit its final report to the Victorian government by 30th
September 2011 and its SP AusNet’s (D) intention to implement this recommendation once it has
been reviewed and agreed by the Victorian Government and subject to funding. In the meantime it
has been agreed by the Victorian Government that the Distribution companies, including SP AusNet,
are to implement some changes to the operation of the distribution network that addresses this
Recommendation during the forthcoming Fire Danger Period as a trial.
Recommendation 33

The State (through Energy Safe Victoria) require distribution businesses to do the following:

fit spreaders to any lines with a history of clashing or the potential to do so.
Status – A directive from ESV for retrofitting of spreaders was issued in January 2011 that requires
SP AusNet (D) to retrofit spreaders on specific lines in the HBRA by 1st November 2015 and in all
other areas by 1st November 2020. A program was subsequently submitted to ESV that meets the
requirement of this directive. ESV has since responded by requesting additional information
associated with this program and SP AusNet (D) is in the process of providing this. Once the
program is accepted by ESV the ESMS for the electrical distribution network is to be updated, which
should then enable a pass through application by SP AusNet to the AER for funding.

fit or retrofit all spans that are more than 300 metres long with vibration dampers as soon as is
reasonably practicable
Status – A directive from ESV for retrofitting of dampers was issued in January 2011 that requires SP
st
AusNet (D) to retrofit dampers on specified lines in the HBRA by 1 November 2015 and all other
st
areas by 1 November 2020. (SP AusNet has a significant volume of work to perform in order to
meet the requirements of this directive.) In response to this directive SP AusNet (D) submitted a
st
prioritised plan to ESV on 1 February 2011 which was not accepted by ESV on the basis that they
considered the costs in the current regulatory period would be too high. A revised plan was
submitted by SP AusNet (D) in August 2011 which extended the installation time in the LBRA to 2025
however, ESV has rejected this plan on the basis that it does not meet the 2020 date of completion
rd
for all works in the LBRA. A 3 plan is now being prepared by SP AusNet (D) and is to be submitted
to ESV. Once the program is accepted by ESV the ESMS for the electrical distribution network is to
be updated, which should then enable a pass through application by SP AusNet to the AER for
funding.
IJM Consulting Pty Ltd
17 of 39
SP AusNet Distribution BFM Audit Report
Several implementations from the Recommendations are subject to The Powerline Bushfire Safety
Taskforce, which has now completed its work, and the report is being finalised by the Secretary for
submission to the Victorian Government by 30th September 2011. The report included a range of work
packages that consider various criteria and results in difference levels of bushfire risk reduction, along
with estimates of the expenditure and timelines required for each. Following review and acceptance of
specific work package(s) by the Government, the DB’s need to reach agreement with the AER by October
2012 on the pass through of costs for this regulatory period so that works can commence by 1st January
2013.
At this stage the report remains confidential, as the Government has chosen not to release it to the
community at this stage.
3. A SS ET I N SP EC T I O N
3.1
AND
M A I NT E N A NC E P R O GR A M
General
Asset Inspection Manual Priority Codes
The priority codes in SP AusNet’s Asset Inspection Manual are not contained within the Bushfire
Mitigation Plan as they were removed to allow for their common use across all 3 networks. The
application of the Priority Codes is outlined in the Asset Inspection Manual associated with the Q4 codes
(Asset Item). The actual codes are defined in standard operating procedures.
Priority Codes Alignment with the Fire Risks
SP AusNet’s priority codes for action on distribution assets have been established to align with the
potential risk of failure and not to fire risk. A priority rating is a predetermined a timeframe allowed to
complete a task, based on the type of defective or critical plant and the likelihood of failure and
consequence.
Currently the priority rating system indicates the perceived urgency to complete an item without indicating
the business expectation of how long that should be. The business then relies on personnel sourcing the
correct matrix or procedural document in order to determine the allowable timeframe to complete the task.
A Priority Target is a measure of calendar days.

PT1 - 1 Calendar day;

PT 7 - 7 Calendar days;

PT14 - 14 Calendar days;

PT30 - 30 Calendar days (1 month);

PT90 - 90 Calendar days (3 months);

PT180 - 180 Calendar days (6 months);

PT365 - 365 Calendar days (1 year); and

PT912 - 912 Calendar days (2.5 years).
PT912 is to be phased out in the HBRA and replaced by an observation code however it will remain in the
LBRA where the inspection cycle is 5 years.
At the time of the audit SP AusNet (D) has 1418 corrective work orders on issue that are past their target
date. This is predominately due to adverse environmental conditions during the winter months.
Policy Regarding Unserviceable Poles, Staked and Reinstated and Returned to Limited Life
SP AusNet’s (D) Asset Inspection Manual describes all processes in the inspection of poles. Inspection
programs designate poles as either:

Serviceable;

Limited life – must be retested, replaced, staked (where suitable) or have approved repair action
taken;
IJM Consulting Pty Ltd
18 of 39
SP AusNet Distribution BFM Audit Report

Unserviceable - must be replaced, staked (where suitable) or have approved repair action taken; or

Pole Staking – a pole is staked in accordance with the criteria set out in Table 2 of the “Pole Stake or
Replace Decision Matrix of the Distribution Standard Maintenance Guideline”.
When eventually the staked pole deteriorates the pole may be classified as limited life and at this stage
the pole is to be retested in accordance with the Company’s Business Rules (currently tested every 2.5
years).
Unserviceable Poles Remaining in the System During the Fire Danger Period
SP AusNet (D) Bushfire Mitigation Manual has business rules for the time allowed to action poles
classified as Unserviceable (to be actioned within 90 days). The Bushfire Mitigation Manual has no
requirement to treat unserviceable poles differently in the Fire Danger Period. Any pole found to require
an urgent repair is done as a fault.
The Company had 626 unserviceable poles remaining in their system during the 2010/11 Fire Danger
Period broken down into:

HBRA = 238

LBRA = 388
Period from Inspection to Issuing of Work Orders
SP AusNet performs a two stage inspection process. Stage one is in the field with an Asset Inspector
where the inspector performs tests and inspections of the asset, collects data and hi-resolution digital
imagery. Stage two is in the office with a qualified Technical Assessment Officer reviewing the digital
imagery on large 80cm monitors. Work is issued post stage one inspection on average to the following
timeframes:

PT30 = < 7 days (ie. 7 days to assess and issue the work to construction and then 23 days to
complete the rectification);

PT90 = < 28 days (ie. 28 days to assess and issue the work to construction and then 62 days to
complete the rectification);

PT180 or greater = < 42 days. (ie. 42 days to assess and issue the work to construction and then
138 days to complete the rectification).
This works the same for the mid cycle aerial inspection with the priority being allocated at the time of
inspection and the countdown commencing at that point.
Identification of Inappropriate Pole Assemblies
SP AusNet’s (D) Standard Installation Manual has three types of pole top assemblies, i.e. Pole Assembly
A (pole cap with a strap), B (concrete pole), and P bracket (current standard for wood poles).
Note: Pole Assembly A has been superseded by the P bracket.
The Company’s Asset Inspection Manual has a procedure for visual inspection in relation to the
identification and requirement for correction of inappropriate pole top angle assemblies.
The Asset Inspector is required to determine missing or unsecured pole cap or major splits in the top of
the pole.
3.2
Asset Inspection
Asset Inspection Alignment to the 37-Month Inspection Requirement
Ground level inspections of assets are carried out at intervals of no longer than five years and three
months. In addition, aerial inspections of assets in HBRA’s are carried out at intervals of no longer than
five years and three months. The ground level and aerial inspections are staggered to provide an
effective inspection interval in HBRA’s of less than 37 months.
An application for an Exemption, together with justification for SP AusNet’s (D) proposed inspection
program to comply with the Regulatory requirement for a 37 month inspection cycle in HBRA’s has been
submitted to ESV, subsequently accepted and is now being implemented. The Company shall make a
subsequent Exemption request following the new Bushfire Mitigation Regulations that are due by 21
October 2011.
IJM Consulting Pty Ltd
19 of 39
SP AusNet Distribution BFM Audit Report
Pole inspected (cyclic):

Timber/steel = 5 years & 3 months maximum (to be carried out by a staggered cycle where the
inspection is no greater than 37 months.)

Concrete = 37 month maximum (HBRA to be carried out by a staggered cycle where the inspection is
no greater than 37 months and the LBRA is moving to a 5 year cycle over a transition period to March
2016)
However the SP AusNet (D) is aiming to achieve an inspection cycle of 2.5 years or 4 inspections in 10
years (2 x ground and 2 x aerial inspection).
nd
SP AusNet monitors inspection on a daily basis and as at 22 September 2011 the Company has 33,542
inspections to be completed prior to the CFA Fire Danger Periods.
These are broken into:

Cyclic Inspection – 33,390

Limited Life Retest – 152
The 33,390 poles outside the 37 month inspection cycle are covered by the transition period in the ESV
exemption. At the date of the audit 7,033 poles outside the 5 years plus 3 month inspection period are
programmed for inspection by the end of November 2011.
SP AusNet has developed a process flow based on the requirements of the move to the 37 month cycle
requirement for wood, concrete and steel in the HBRA, and is also progressing toward a 5 year cycle for
concrete poles in the LBRA which commenced in April 2011 with an estimated completion date of March
2016.
Limited Life Poles
The retest period for Limited Life poles has not altered and remains at PT912 days, i.e. 2.5 years.
In the Auditors opinion this is out of step with their current operation. The Company should consider
reducing their limited life retest period to approximately half their inspection cycle. (The inspection cycle
is now being aimed at 2.5 years or 4 in 10 years - 2 x ground and 2 x aerial inspection);
There were 489 poles re-inspected during the 2010/11 fire Danger Period broken down into the following
areas:

Central – declared 30/11/2010 to 22/03/2011 – 255 Limited Life inspections

East – declared 14/12/2010 to 28/03/2011 – 181 Limited Life inspections

North – declared 14/12/2010 to 07/03/2011 – 53 Limited Life inspections
Pole Staking or Temporary Supporting
SP AusNet’s (D) has a policy for temporary supporting or fully supporting unserviceable poles that cannot
be changed within the specified priority timeframe (PT90) as follows.
Temporary Supported:

All poles not suitable for staking and classified unserviceable for greater than 90 days, are to be
temporarily supported until conditions allow access.

Any pole that is temporarily supported is to be replaced within 180 days of the inspection date.
Fully Supported:

All poles not suitable for staking and classified unserviceable for greater than 90 days and which are
not suitable for temporary supporting, shall be fully reinforced by a dummy/support pole until
conditions allow access.

Any pole that is fully supported is to be replaced within 365 days of the inspection date and a status
of limited life applied.
IJM Consulting Pty Ltd
20 of 39
SP AusNet Distribution BFM Audit Report
The Company has 23,771 poles rated as staked reinstated to serviceable and 704 staked poles rated as
Limited Life:

HBRA = 13,042

LBRA = 10,729
The process has been in use since 1980 and the Company does not have the records available to
provide a profile of the age of poles after staking.
SP AusNet (D) currently has 76 temporary supported poles Identified in Q4 with an Unserviceable
Temporary support (UT) status.

HBRA = 76

LBRA = Zero
With the installation of temporary supported status it extends the time by an additional 6 months thereby
allowing the Company 9 months to change the pole.
In the Auditors opinion temporary supporting of poles is an acceptable practice up to but should not
remain in service during the Fire Danger Period.
SP AusNet (D) currently has 90 staked poles that have been reclassified as unserviceable within their
network:

HBRA = 51

LBRA = 39
Wood Pole Design Criteria Loadings
SP AusNet (D) are still using the same specs and testing criteria for poles as previously established by
the State Electricity Commission of Victoria. This incorporates the safety factor of 2 for concrete, 2.5 for
treated wood poles, and 3.5 for de-sapped poles, however they are in the process of implementing the
revised limit state design criteria specified in AS7000.
The design tool used by line designers and surveyors is known as “NPoles”, which has been updated to
accommodate the design criteria changes. The testing criteria for thickness of wood is based on a
combination of remaining strength and a conservative estimate for the loss of wood due to deterioration
during the next inspection period .
SP AusNet has individual records of wood loss in each pole to demonstrate this approach is safe.
3.3
Asset Inspectors Training and Qualifications
The service provider (Select Solutions) has a system of recording and managing training requirements
including a training matrix and Asset Inspector specific training records. All Asset Inspector qualifications
and refresher training is in line with both Business and VESI requirements.
The modules include:

Certificate II Asset Inspection / Asset
Inspection underpinning knowledge (Not
Refreshed);

CPR;

VESI First Aid in an ESI Environment;

Sae Approach Distances;

Manual Handling;

Safe to Approach SWER;

Traffic Management (Traffic Control);

Traffic
Management
Schemes);
IJM Consulting Pty Ltd
(Traffic
Guidance

Line Inspection Manual – Duties of the Line
Inspector and Pole Inspection (Not Refreshed);

Identify
Transmission
and
hardware (Not Refreshed);

Line Inspection Manual – Pole Inspection and
reinforced pole inspection (Not Refreshed);

Line Inspection Manual – Line hardware
Inspection (Not Refreshed);

Line Inspection Manual – HV Fuse and Surge
Arrestors (Not Refreshed);

Line Inspection Manual – Conductors (Not
Refreshed);
Distribution
21 of 39
SP AusNet Distribution BFM Audit Report

VESI Safety Framework;

Line Inspection Manual
Inspection (Not Refreshed);

Enter Enclosures;

Apply ESI Safety rules (Green/Blue Book
training) (Not Refreshed);

Line Inspection manual – Preservation and
treatment of poles, wood technology (Not
Refreshed);

Network Operator Induction;

Australian ESI skills passport (Not Refreshed);

Apply OHS practices in the workplace (Not
Refreshed);

Line Inspection Manual
Refreshed);

Comply with environmental and incident
response procedures (Not Refreshed);

Construction Industry Induction (White/Red
Card) (Not Refreshed);

Working safety near live electrical apparatus as
non electrical worker (Not Refreshed);
3.4
–
–
Private
Line
Termites
(Not
Conductors and Ties
SP AusNet has produced a comprehensive Steel Conductor Assessment Guide. Asset Inspectors are
trained on how to apply the assessment. All conductors identified by an Asset Inspector as having a
condition rating 6 or below receive a detailed conductor assessment. This detailed conductor
assessment is then undertaken by a team using special hi powered camera equipment and detailed
analysis on 80cm television monitors.
Conductors

Condition Rating 8 - Majority of surface has a white metallic coating with white corrosion i.e. loose
zinc, product on it. Rust beginning to form.

Condition Rating 7 - Relatively light coloured rust all over. If on a concrete pole then conductor must
be satisfactory for 10 yrs until next inspection.

Condition Rating 6 - No galvanizing remains, surface no longer smooth medium pitting/flaking, no
loss of cross section. Create work order PT912 condition monitor.

If any conductor or hardware requires a reassessment prior to the next cyclic pole inspection, assign
PT912

Condition Rating 5 - No galvanizing remains, advanced corrosion, and pitting. Pitting has caused
some loss of cross section.

Condition Rating 4 - No galvanizing remains. Significant corrosion and excessive pitting. Significant
loss of cross section.

Condition Rating 3 - No galvanizing remains. Major pitting/flaking. The conductor has lost shape, it
may appear deformed.

Condition Rating 1 Emergency Response (Fault) - Variations of the above references that are
deemed critical at the inspector’s discretion.
Conductor Ties

Condition Rating 8 - Patchy rust present. Mostly galvanized. Tie wire intact, and firmly holding
conductor to insulator. Suitable to go through to next inspection.

Condition Rating 7 - Partial galvanizing remains. (Dark Red Rust) minor pitting/flaking present. Tie
wire is intact, still firmly holding conductor to insulator. Stretched ties still holding conductor to
insulator. Suitable to go through to next inspection. If on a concrete pole then tie must be satisfactory
for 10 yrs until next inspection.

Condition Rating 6 - Minimal galvanizing remains. (Dark Red Rust) medium pitting/flaking present.
Tie wire Strands no longer smooth. Tie wire is intact and still holding conductor to insulator. If any
conductor or conductor hardware requires a reassessment prior to the next cyclic pole inspection,
assign PT912
IJM Consulting Pty Ltd
22 of 39
SP AusNet Distribution BFM Audit Report

Condition Rating 5 - No galvanizing remains. Advanced corrosion and pitting. Pitting has caused
some loss of cross section. Tie wire is intact and still holding conductor to insulator

Condition Rating 4 - No galvanizing remains. Significant corrosion and excessive pitting. Significant
loss of cross section. One broken tie wire strand present, but forces holding conductor onto insulator.
Two remaining tie wire strands still intact. Ties visibly loose around neck of insulator. Stretched ties,
conductor is lifting from insulator.

Condition Rating 3 - No galvanizing remains. Major pitting/flaking. The tie wire has lost shape, it may
appear deformed. One or two broken tie wire strands present, forces still holding conductor to
insulator. Only one tie wire strand remaining intact. The weight and tension (force) of the conductor
on the insulator reduces the risk of falling.

Condition Rating 1 Emergency Response (Fault) - Variations of the above references that are
deemed critical at the inspector’s discretion.
Life Assessment of LV Spreaders
LV spreaders are being inspected from the ground every 37 months (irrespective of whether it is
inspected from the air) as per the Transition Plan, and are replaced or maintained based on condition.
SP AusNet has not considered there is a need to establish a life assessment of LV spreaders as they are
low cost items.
In the Auditors opinion, irrespective of the low cost, an LV spreader that is suspected to be reaching its
end of life is a proven high fire risk item and needs to be determined
3.5
Pole Top Attachments
SP AusNet (D) does not have a current remedial program for bulk replacement of HV wooden crossarms.
However during the recent re-conductor program all wooden HV crossarms were replaced with steel
irrespective of condition. Where major works are carried out on the pole (e.g. insulator or pole
replacement) the HV crossarm is also upgraded to steel.
Their standard is that once a HV crossarm has deteriorated (classified as PT365 or less) it is replaced
with a HV steel crossarm and deteriorated LV crossarms are replaced with timber crossarms.
SP AusNet (D) has a cyclic program for inspection and assessment of wooden crossarms. The
assessment of crossarm condition and subsequent action falls in line with the Asset Inspection Manual.
Two methods of inspection are used to assess pole top assets.

Ground based - During the periodic inspection of poles and other structures a ground based
inspection is completed on all assets.

Aerial - An alternate inspection is also undertaken of the assets attached to distribution poles. This
inspection is completed between ground based inspections. The method uses equipment to view the
asset from above or up close. Equipment being used is Ladders, EPV, Helicopter, Elmast telescopic
mast with camera, or an UAV (Unmanned aerial vehicle).
Inspection of Wood Crossarms – Viewed From Ground
Crossarms are initially inspected from two positions on the ground using a pair of image stabilised
binoculars, then photographed showing location and construction detail, any defect observed is
photographed using the camera zoom features. This method provides an inspection and record of the
visible parts of the structure such as the ends and sides. When the Asset Inspector observes
deterioration or if maintenance is required, a rating is required that is based on a cautious evaluation of
risk. This report is recorded in the Asset Inspectors PDE.
The top surface and holes is where decay usually begins on the wooden crossarm. Any defects may be
deduced by indicators such as insulator pins leaning over, open cracks or splits or enlarged holes.
The photographs are examined by a technical assessor whilst checking the inspection results and all
defects are rechecked and rated with a new maintenance priority. The site maybe re-visited by the
technical assessor or they could use an EPV, extension mast or stick with camera or from helicopter to
verify the assessment, and work orders are recreated with the new priority rating for replacement.
IJM Consulting Pty Ltd
23 of 39
SP AusNet Distribution BFM Audit Report
Since 1990, the wood used for crossarms has been of high durability and strength. Before this date, a
range of the timber species was used. These provided a service life that varied between two to forty
years service.
Inspection of Wood Crossarms – Viewed From Above Ground
On inspections viewed from above ground all distribution poles in the HBRA are inspected either by
aircraft and/or where there are no fly zones then they are again inspected from the ground. This
inspection focuses on an assessment of the upper part of the crossarm that may be difficult to assess
from the ground without the aid of hi-resolution digital imagery.
Following these inspections, the same process is followed, i.e., the Technical Assessment Officer views
the reports and the photographs taken and appropriate work orders created for any item found that needs
maintenance or replacement.
SP AusNet (D) asset replacement program estimates 8,743 units are to be replaced during the 20112012 financial year. As at the end of August 2011, 5,289 units have been completed against a forecast
prediction year to date (month 5) of 3,118, therefore the Company is ahead of target with this program.
Contaminated HV Insulators
SP AusNet (D) do not have a policy for contaminated HV insulators however in polluted areas targeted
insulator washing programs are conducted. The Company does not consider oxidized insulators as an
issue based on history.
Bird and Animal Proofing
Bird and animal proofing is targeted on all HV structures within the High Bushfire Risk Areas as defined
by the CFA. All new HV poles are installed with animal proofing regardless of location. Known areas of
high possum activity or extra large bird activity also receive consideration for Bird and Animal contact
mitigation.
The “Animal Proofing – Standard Guidelines” policy involves the ceasing of installation of covers on
conductor ties and conductor at the 22kV post insulator due to the following issues:
Inspection of ties cannot be performed without removing the cover (tie inspections are required for
live-line work);

There is a tendency for insects to hide under the covers (leading to bird activity);

Costly to cover all insulator lengths.
The policy involves utilising post insulators of sufficient length that do not require animal/bird barriers
(except where there is known large bird/ high animal activity on a concrete pole) as follows.
New 22kV Construction (Concrete or Wood poles in Fire or Non-Fire Areas):
Use 9 shed tie-top / clamp-top, or in high-pollution areas use 11shed 22kV insulators.

No animal/bird barriers/covers are required for the above insulators except where there is known
large bird/ high animal activity on a concrete pole (fire or non-fire area) – in these instances install
disc-type bird/animal barriers to the base of insulators.
Existing Construction – non-bridging insulators:
When work is carried out on an existing pole with 9 shed 22kV insulators with covers fitted to the
insulator and conductor, remove all existing covers, and implement dot point 2 above.

When work is carried out on an existing concrete pole with 22kV insulators with less than 9 sheds in
fire or non-fire area :
Replace insulators with 9 shed or 11shed (high pollutions area) insulators implement dot point 2
above – Preferred Option, or

Fit disc-type bird/animal barrier to the base of existing insulator (remove any covers to be
installed on conductor tie or conductor) - Non Preferred Option
IJM Consulting Pty Ltd
24 of 39
SP AusNet Distribution BFM Audit Report
Existing Construction – bridging insulators:

When work is carried out on an existing concrete pole with 22kV bridging insulators with less than 9
sheds in fire or non-fire area:

If no bird/animal barriers installed, fit disc-type bird/animal barrier to the base of existing insulator
Existing bird/animal covers installed on the conductor tie & conductor are acceptable and can remain.
“D” Loops
The inspection acceptance criteria adopted for the classification of serviceable D Loops is outlined in the
SP AusNet Distribution Asset Inspection Manual.

Burnt or discoloured “D” Loop steel wrap or where the “D” loop is toggled at both ends.

For transformers of 50kVa or less they are recorded as stock item only.

For transformers greater than 50kVA or spur lines with more than one transformer they are recorded
as a work order only.
3.6
Fuse Units
EDO’s
SP AusNet’s (D) Surge Diverter and HV Fuse Identification 2004 Manual identifies brown bodied EDO
fuses for wood pole installations only.
The Asset Inspectors are required to identify non-acceptable units & tubes during the cyclic inspection
program. Any units or tubes identified during this process are given a priority associated with an age
based profile and actioned accordingly. In addition, SP AusNet (D) has a specific program that targets
EDO units in high fire risk consequence areas (per Doctor Tolhurst model). These units are removed and
generally replaced with Boric Acid fuses.
During 2010 a review of Q4 revealed that they had 1,099 brown bodied EDO fuses and 4,273
brown/black EDO fuse tubes as non-acceptable across both the HBRA & LBRA.
Boric Acid Fuses
SP AusNet (D) has encountered minor problems with water ingress into the Boric Acid fuse when the fuse
has been left in the open position during inclement weather. They do not have an issue with
inappropriate storage of these fuse elements as they are held within the covered section of the store.
The Company has carried out extensive investigations involving manufacturers, and as a result has
issued instructions to field personnel on handling Boric Acid Fuses covering:.

Storage - Ensure that the fuse tubes are always kept in the sealed plastic bag inside the box when
they are stored in trucks. Do not keep unpacked fuse tubes in open air (especially in job lots):

Installation - Ensure that fuse tubes are NOT kept hanging upside down in an open position in the
fuse mounts for more than a day e.g. awaiting commissioning.
Over the past 3 years SP AusNet (D) has purchased 23,968 Boric Acid (BA) fuse units. The Company
stated that their database for the installation of Boric Acid units is not up to date although they have had 5
hang ups involving these units in the last 12 months.
3.7
Surge Diverters
SP AusNet (D) Surge Diverter and HV Fuse Identification Manual have photographs clearly indicating the
surge arrester types that are suitable for installation across their Network. The types of surge diverter
currently in service within SP AusNet’s (D) operational area are:

Bowthorpe 1973 - 1978 (SWER 12.7kV Silicon Carbide type);

Bowthorpe 1973 - 1978 (22kV Silicon Carbide type);

Asea 1978 - 1982 (22kV Silicon Carbide type. Fitted with adaptor for earth lead disconnect device);

Bowthorpe 1980 - 1981 (22kV Silicon Carbide type);

Bowthorpe 1980 - 1983 (SWER 12.7kV & 22kV Silicon Carbide type);
IJM Consulting Pty Ltd
25 of 39
SP AusNet Distribution BFM Audit Report

Bowthorpe 1980 - 1992 (22kV Zinc Oxide Type);

Bowthorpe 1982 - 1995 (22kV Silicon Carbide Type);

Bowthorpe 1985 – 1995 (Identified by NO Earth Lead Disconnect);

Bowthorpe 1986 - 1989 (22kV Zinc Oxide Type);
All polymeric surge diverters are acceptable to SP AusNet (D) with the exception of Cooper VARISTAR
AZLP 1992 & Cooper VARIGAP AZLP 1992.
Any surge diverters identified during the asset inspection cycle are given a priority associated with type
and conditioned and actioned accordingly.
The Asset Inspector is required to identify missing or disconnected surge diverters on:

Transformer => 100kVa,

Missing or blown lead on Transformer < 100kVa,

Missing or blown on fuseless Transformers regardless of size,

Surge Diverter missing or blown from HV cable head,

Surge Diverter missing or blown from HV ABC interface,

Surge Diverter missing or blown from substation on HV term pole,

Surge Diverter missing from gas switch on an open point,

Surge Diverter missing or blown the ACR’s and Regulators.
th
As at 28 September 2011 SP AusNet (D) has 120 units of non-acceptable Surge Diverters in service
identified by the failure code 70B:

12 are committed for replacement and work orders have been issued;

55 have provisional status – indicates the Field Asset Inspector has identified these units while
performing stage one of the inspection cycle; and

53 have raised status – Indicates Technical Assessment Officer (TAO) to review the field
assessment. At this point there is an expectation that a large number of these units may be found to
be disconnected from supply and the TAO then reviews the criteria and classifies the unit either for
replacement or cancels the work order
3.8
Company Specific Questions
Current HV Construction Standard Crossarms & Insulators
The current standard construction for 66kV and 22kV covering length and type of crossarms requires the
installation of steel crossarms for both voltages. This involves a range of crossarms from SL1, SL2,
SL10, SL11, SL12, SL20 plus S(INT)2 for intermediate construction and SL21, SL22, SL23, SL24, SL25,
SL26, SL27 and SL28 plus S(ST)2.6 for strain constructions.
The type of construction (cruciform or vertical) and the installation how the insulators are installed is
determined at the design stage based on the variable options to achieve appropriate line clearances for
the voltage.
There is an established standard in SP AusNet (D) that only line post insulators (porcelain or polymeric)
be used for intermediate construction and polymeric, or glass disc insulators for strain construction. The
creepage distance (insulators length) varies dependent on the voltage and the environment.
Installation Dampers and Armour Rods
SP AusNet’s (D) standard for the installation of Amour Rods and Vibration Dampers is outlined in the
Standard Installations Manual. This details the location and type of armour rods and dampers to be
installed appropriate to the construction type, landscape and the stringing tension.
IJM Consulting Pty Ltd
26 of 39
SP AusNet Distribution BFM Audit Report
To alleviate confusion in the field with respect to the installation of armour rods and vibration dampers
and to make it easier for the installers SP AusNet (D) has introduced the following rules:

Install Armour rods on all HV AAC, ACSR, SG/GZ and SC/AC conductor types at the insulator
position for all conductors regardless of tension or insulator type.

Install vibration Dampers on all HV conductors regardless of span lengths or tension. For new
constructions install on spans either side of the pole at each pole location. For maintenance work
install on either side of the pole being worked on.
The Company understands that this is above the minimum standard requirement.
This instruction to all staff was sent out in a Lines Group NSD standard Bulletin in September 2011
therefore the effect in the field was not noticeable during the field audit.
4. V E GE T AT I ON M A N A G EM EN T
4.1
Vegetation Management Organisation Structure
The following management structure outlines SP AusNet’s positions and responsibility for the preparation,
approval, resourcing, submission, and implementation of the Vegetation Management Plan:

Charles Popple - General Manager Network Strategy & Development

Gary Towns - Manager Asset Engineering

Renzo Negrelli - Environment Manager

Matt Peters - Group Manager Utility Solutions

David Crook – Vegetation & Easement Manager

Karl Jesser – Vegetation & Easement Area Manager Rural

Brett Fox - Vegetation & Easement Area Manager Urban
4.2
Overview
Transitional Vegetation Management Plan
SP AusNet (D) submitted a Transitional Vegetation Management Plan requesting an exemption to
achieve the requirements of the Electricity Safety (Electric Line Clearance) Regulations 2010 to ESV on
th
th
the 16 December 2010 and it was granted by ESV on the 24 January 2011.
The Company’s Vegetation Management Plan exemption from the requirement to maintain a clearance
space in accordance with tables 1, 2, and 3 of the Code of Practice for electric line clearance in the
Electricity Safety (Electric Line Clearance) Regulations 2010. The Exemption takes effect on the date on
which the Director of Energy Safety signs this exemption document and expires as follows (unless
revoked earlier in accordance with this clause):

Clause 2.1 – on 30 December 2013 – Minimum Clearance Spaces Surrounding a Powerline All Areas
- Aerial Bundled Cable or Insulated Cable (as at 31 December 2011 22% of the Network is to be
complete) – SP AusNet is on target with this requirement

Clause 2.2.2 – on 30 December 2013 – Minimum clearance Spaces Surrounding a Powerline – Low
Bushfire Risk Areas – Other than Aerial Bundled Cable or Insulated cable (as at 31 December 2011
40% of the Network is to be complete) – SP AusNet is on target with this requirement

Clause 2.3.2 – on 30 June 2013 – Minimum clearance Spaces Surrounding a Powerline – High
Bushfire Risk Areas – Other than Aerial Bundled Cable or Insulated cable (as at 31 December2011
93% of the Network is to be complete) – SP AusNet is on target with this requirement

Clause 2.3.3 – on 29 June 2015 – Minimum clearance Spaces Surrounding a Powerline – High
Bushfire Risk Areas – Other than Aerial Bundled Cable or Insulated cable - Overhanging Trees (as at
31 December 2011 there are to be only 1880 spans with overhanging trees in HBRA on the network)
– SP AusNet is on target with this requirement
IJM Consulting Pty Ltd
27 of 39
SP AusNet Distribution BFM Audit Report
The changes to the Regulations have been communicated to the Vegetation Management Company,
Select Solutions (a division of SP AusNet) employees and contractors during the Assessment Procedure
th
Training delivered on the 16 February 2011.
The Company has not implemented any further changes since the delivery of the 2009/10 Victorian
Bushfire Royal Commission report as the only impact on vegetation management relates to Hazard trees
and the Company already has a program in place to manage this requirement.
Proportion of the Network Annually Inspected for Vegetation Line Clearance
The Vegetation Management Company inspects the clearance space in accordance with the following
cycles:

all spans are assessed at least annually in the hazardous bushfire risk area to allow for any clearing
to be undertaken to maintain compliance to the regulations;

all spans are assessed at least biennially in the low bushfire risk area, however during the transition
period the cycle is progressively reducing to achieve a 1 year cycle.
In determining the location where work is required to maintain the clearance space one or more of the
following inspection programs are undertaken:

cyclic work programs;

pre-summer inspection in hazardous bushfire risk areas; and

reports from asset inspections.
The above are supplemented by reports from the public on areas of concern. At each location the most
appropriate method of maintaining the clearance between powerlines and vegetation is to be determined.
In the HBRA all spans are programmed to be inspected and cleared prior to 31st October 2011 or
st
declaration, whichever comes first. At 1 September 2011 SP AusNet (D) pre-summer vegetation
inspection had 1,098 spans outstanding to be inspected and 7,086 spans yet to be cleared. The
st
Company considers (environmental conditions permitting) they are on target to meet the 31 October
deadline for 99% of the network. There should be approximately 1,000 spans remaining to be cleared
after this date which are predominantly climbing spans in Leongatha and Traralgon plus a small number
th
of wet spans in all areas that have been given until the 30 November to achieve a zero index.
In the LBRA SP AusNet (D) is slightly behind target to meet its biennial inspection and cutting program. A
KPI report was produced that shows a 45% actual completion of program against a target of 51%
completion against program. The works program is slightly behind target for August and YTD, impacted
by wet weather and an increase in find rates of 2.3% which accounts for an additional 10% (Approx.) in
cut spans. The Program is also still recovering from the impact of a climbing incident in late May.
Additional resources are to be engaged as required.
Cutting/Removal Cycle
If cutting and/or removal is deemed the most appropriate method then the cutting/removal cycle shall be
determined at each locality. In specific locations and from time to time the maintenance cycle may be
varied as per the following;

Rural Areas – 6 months to 3 years as appropriate;

Urban Areas – 6 months to 2 years as appropriate.
The process used to determine the Maintenance Cycle at specific locations takes into consideration the
following factors;

Financial and budgetary constraints;

Community impacts;

Environmental and conservation issues;

Tree species & regrowth characteristics;

Line voltage & configuration; and

Area fire rating.
IJM Consulting Pty Ltd
28 of 39
SP AusNet Distribution BFM Audit Report
SP AusNet uses a Vegetation Management Program to detail the priority of the feeders to be inspected
and actioned in accordance with their procedure.
The HBRA program has been established to show the pre-summer inspection and cutting by feeders with
the aim that all works are completed by a nominal date of 31st October. The works program is slightly
behind target for August and YTD, impacted by
SP AusNet (D) is confident they have the resources to achieve their pre-summer cutting.
Default Times for Vegetation Classified as Requiring Attention
SP AusNet Distribution classifies vegetation as requiring attention as:

PT1 (55’s) - On the day of inspection vegetation has been recently contacting the conductor due to
sag or sway or environmental conditions, but is not physically in contact on the day required to be cut
or removed within 24 hours;

PT30 (56’s) - On the day of inspection vegetation is within the clearance space as defined in the
Electricity Safety (Electric Line Clearance) Regulations 2005 but is not in contact with open wire
conductors or un-insulated assets required to be cleared within 4 weeks;

PT 2011 - On the day of inspection vegetation is ‘highly likely’ to encroach upon the required distance
as defined in the Electricity Safety (Electric Line Clearance) Regulations 2005, prior to the end of the
bushfire declaration period. i.e. vegetation requiring action in the current year’s cycle;

PT RE - On the day of inspection vegetation is outside the clearance space as defined in the
Electricity Safety (Electric Line Clearance) Regulations 2005, and where vegetation ‘may’, although
there is some uncertainty encroaches upon the clearance space prior to the end of the bushfire
declaration period. In this instance a RE code allows a re-assessment to take place closer to the
declared fire season. i.e. vegetation ‘may’ require action in the current year’s cycle;

PT 2012 - No action required this year – may require action in 2012;

PT 2013 - No action required this year – may require action in 2013;

PT 2014 - No action required this year – may require action in 2014

PT CV - Vegetation within the span may require action beyond 2014 ; and

PTM - Phantom Code – to be used in the following circumstances. When using a PTM code, there
must be a detailed explanation of the reason why that span requires a PTM code.
Measures Adopted to Assess Performance
As part of its Environmental Management System, SP AusNet has developed a set of Key Performance
Indicators (KPIs), measures and targets to monitor its overall environmental performances. KPI targets
are set each year and monitored and reported to Senior Management and the Board on a quarterly basis.
The Bushfire Mitigation Index is reported to and monitored by Senior Management and the Bushfire
Mitigation Management Committee monthly. The KPIs related to bushfire mitigation aspects together with
the 2011/2012 measures and targets are detailed below.

Bushfire Mitigation Index during the Declaration Period 0%;

Ground fires associated with SP AusNet assets/activities as a % of CFA wildfires for period 1 July
2011 to 30 June 2012 < 1.0%.
Audit Processes Adopted To Determine Compliance
The accountability for auditing of the Vegetation Management Group rests primarily with the Manager
Asset Engineering, Network Strategy and Development who is responsible for the regular auditing of the
Vegetation Management Group to ensure that it complies with the requirements of their Plan.
This includes:

Internal audits prior to the commencement of the fire season to validate the completion of all bushfire
mitigation obligations prior to the commencement of the fire season;
IJM Consulting Pty Ltd
29 of 39
SP AusNet Distribution BFM Audit Report

As part of the Senior Management Bushfire Mitigation Review Program, reviews of all facets of the
Bushfire Mitigation Program are undertaken by managers at General Management level to validate
the efficacy of SP AusNet’s management process, program compliance, and program relevance.
These audits are undertaken during December of each year;

Audits are undertaken during the fire season to check that vegetation clearances are being
maintained;

The SP AusNet Internal Auditor undertakes audits of the Bushfire Mitigation Management system;
SP AusNet or its nominated representative is responsible to conduct a sample audit of the contractor’s
work (without any limitation), procedures, and practices in order to determine their compliance with the
relevant Standards and Codes of Practice.

The V&E group field officer/representative then undertakes a compliance audit based on but not
limited to the following criteria:

Assessment:

Cutting:

Correct priority coding of all spans;

Clearance achieved;

Identification of all assets;

Appropriate cutting techniques used;

Correct property owner identification;

Site tidiness;

Correct identification of voltages;

Correct herbicide application;

Correct identification of fire zones.

Slashing requirements met.
Where deadlines are not achieved prior to the Fire Danger Period
SP AusNet has a number of mature processes in place to monitor the performance of the contractor
company responsible for their operational area to ensure the Fire Danger Period deadline is always
achieved and therefore has not needed to put corrective actions in place.

monthly contractor meetings;

regular field inspections;

regular bushfire mitigation meetings;

tracking via the BFM Index.
4.3
Clearance Space for Electric Lines
Methods Employed to Calculate Vegetation Clearance
SP AusNet (D) has a procedure that matches the requirements of the Regulations, which gives
consideration to sag and sway of lines when determining the clearance space and when assigning
assessment codes:

PT1 - within the clearance space and is in contact with the conductors;

PT30 - within the clearance space but not in contact with the conductors;

2011 - outside the clearance space but highly likely to encroach in the clearance space prior to the
end of the declaration period;

RE - outside the clearance space but may encroach in the clearance space prior to the end of the
declaration period;

2012 - no action required this year – may require action in 2012;

2013 - no action required this year – may require action in 2013.
Vegetation clearance consistency is achieved by the Vegetation Management group through the
engagement of qualified/competent contractors supported by an established refresher training program
combined with audits covering assessment and cutting.
IJM Consulting Pty Ltd
30 of 39
SP AusNet Distribution BFM Audit Report
The audit sample size is based on established criteria and is determined by the number of spans
submitted as completed.

An audit sample is selected, for each WO submitted. The WO size submitted for assessment is to be
approximately 500 spans. Should the sample size submitted be below 40 spans, then a minimum of
20 spans are to be audited. The sample size can be based either on the exact number of spans
submitted or the closest lower number of spans.

To ensure that the work order (WO) is consistently audited across the entire spread of assessment or
cutting data, the sample size is divided into the number of spans submitted. This calculation
methodology is to be employed for each individual audit.
Methods Employed to Monitor the Growth of Vegetation.
The assessment of growth rates is used to determine the amount of cutting required to maintain
vegetation outside of the clearance space. The assessment methodology by in-field assessors include:

Climate factors (Rainfall, temperature, wind, and amount of sun);

Soil factors (Soil Makeup or structure, Moisture content, Mulch and Drainage);

Topography (Aspect (North/South), Slope, and Elevation); and

Competition (other vegetation, animals, History of Pruning).
Sites are not always easy to assess. The factors within the site and the way trees interact on that site are
independent of each other. However, the VMC often come across conditions, which can be described
either as ‘ideal’ for tree growth or at the other end of the scale, ‘very poor’. In these circumstances growth
rates and patterns are easier to predict.
Management Plan/Program for the Removal of Overhanging Vegetation in the HBRA
SP AusNet (D) submitted a request to ESV for an Exemption to clause 2.3.3 of the Regulations on the
th
th
16 December 2010 and ESV approved this on the 24 January 2011.
The following outlines the agreed timeframe to achieve compliance.

31 December 2011 – 120 spans to be actioned;

31 December 2012 – 219 spans to be actioned;

31 December 2013 – 340 spans to be actioned;

31 December 2014 – 560 spans to be actioned;

29 June 2015 – 761 spans to be actioned.
There has been an increase in the total of Code 56M spans caused by the boundary changes from LBRA
to HBRA by the CFA this year

Total 56M Spans as of 8-1-11 – 2177 spans to be actioned;

Less new 56M caused by HBRA Change by CFA – 149

Total to be actioned – 2028

Less Augmentation spans projects programmed to 13-12-11 – 150

New target as of 31-12-11 – 1878
The clearance space in the HBRA shall in general be in accordance with tables 1 and 2 of the Code
except for overhanging trees in certain circumstances (56Ms). These trees are of a size, age, and
significance where community outrage, environmental impact, and negative economical benefits prevent
them from being cleared. These trees require re-augmentation solutions to ensure that the clearance
space is clear at all times.
Whilst SP AusNet is transitioning to compliance overhanging trees shall be managed according to the
following process;

an annual risk assessment is to be undertaken by an arborist who has the qualification of National
Certificate Level IV in Horticulture and Arboriculture including the "Assess Trees" module, or the
equivalent of that certificate, and at least 3 years of field experience in assessing trees; and
IJM Consulting Pty Ltd
31 of 39
SP AusNet Distribution BFM Audit Report

the annual risk assessment on the tree shall be in accordance with Procedure VEM 20-01-Vegetation
and Easement Management Hazardous Tree and 56M Assessment and be completed before 1
November in each year; and

keep records for a period of no less than 5 years of the annual risk assessment on any branches and
trees, including details of the condition and possible hazards in relation to each tree and branch.
These overhanging trees shall be allowed to remain during the transition period provided they meet the
following criteria;

any overhanging branches and the trees supporting the branches do not exhibit any potentially
hazardous structural defects; and

a minimum clearance of 3000 millimetres is maintained above the powerline to any overhanging tree
branch.
This assessment program is currently in progress therefore the data was not available for this audit.
Select Solutions considers that they are approximately 80% through the program and are confident they
th
shall meet the contract requirement date of 14 October for completion.
Management of Vegetation within the Clearance Space for Covered Conductors (ABC)
Currently SP AusNet (D) has an Exemption under Regulation 10 of the Electricity Safety (Electric Line
Clearance) Regulations 2010 which allows vegetation within the clearance space for covered conductors
st
(ABC) until the 31 December 2013 which is in line with their Transitional Plan.
Under the Transitional Plan the Company is exempted from commencement of cyclic clearing – aerial
bundled cable or insulated cable - all areas until June 2012, at which time they are required to have 35%
clearance completed.
Management of Vegetation within the Clearance Space for Covered Conductors
Where vegetation is the responsibility of SP AusNet (D) to clear all endeavours are made to clear
vegetation around insulated cables so that they do not enter the clearance space during the nominated
12-month cycle. Due to a previous cutting regime there are a number of trees that have large
limbs/trunks adjacent to or below the conductors that are inside the required clearance space. These
trees require augmentation solutions to ensure that the clearance space remains clear at all times.
Where a customer’s service wire / cable / line are not compliant to the 2010 Regulations an advisory
notice is issued at the time of inspection and all PDA: PCS defect fields are completed with no further
follow up being carried out until the following annual cyclic inspection.
The Vegetation Management Plan does not give any special consideration to achieve service clearance
(customer’s responsibility) for high-populated vegetated areas.
4.4
Hazard Trees
The Assessor is responsible for the identification of hazardous trees whilst carrying out standard
assessment tasks. A hazardous tree can be defined as any tree that is considered a threat to any SP
AusNet electrical asset. This includes trees that have been identified to exhibit evidence of either or all of
the following;

dead or dying;

decay;

overbalanced;

ground lifting.
The identification of trees that could become a hazard is included in routine inspection and is recorded on
the Hazardous Tree database.
SP AusNet has a process in place where a Council may contact the vegetation group and advise them of
a tree that they believe is hazardous to their assets. The call is recorded in the D&T ESR Database and
then sent to an appropriate Arborist to investigate.
IJM Consulting Pty Ltd
32 of 39
SP AusNet Distribution BFM Audit Report
There are several means by which Hazard Trees are reported:

Inspections undertaken as part of the formal hazardous tree program; and

Information obtained from councils, public, other authorities, company personnel, contractors.
The Company has identified 5,822 Hazard trees during the past 12 months.
The following steps outline what actions are to take place once a hazardous tree has been identified and
reported to an arborist for assessment.

If the assessed tree is likely to fail at any moment then the Arborist must report this to the Program
Leader for immediate action;

If the tree is not likely to fail at any moment the Tree Assessment - Hazard Tree or 56M Span form is
to be completed and submitted (electronically) to the Program Leader.
The Program Leader prioritises works according to the hazard rating of the tree or:

Allocates work to the relevant contractor for cutting;

Allocates to an Arborist for Re-Assessment if the tree is not to be actioned prior to the declared
bushfire period.
The Program Leader is responsible for:

ensuring that random audits are conducted on a sample of completed works; and

updating the Hazard Tree Database.
4.5
Habitat Trees
SP AusNet (D) ensures the cutting or removal of trees that are the habitat of any threatened “Invertebrate
Fauna” or “Vertebrate Fauna” is undertaken outside of the breeding season for that species wherever
practicable. If it is not practicable to undertake the cutting outside of the breeding season then
translocation of the fauna must be undertaken wherever practicable.
The process to be undertaken is through:

The engagement of a suitably qualified Environmental Expert;

The development and review of a number of relevant procedures/processes;

Consultation with DSE, Local Government and land owners to establish areas where threatened
species exist;

Implementing systems to ensure compliance with the code

Awareness training of existing/future cutting resources regarding threatened species.
The Environmental Expert liaises with external stakeholders on threatened flora & fauna and works with
the DSE, Local Government and land owners at a local level to develop a “Threatened Vertebrate and
Invertebrate List” of the species that exist in each Region, and the location of these species on each
Distribution feeder or Transmission line. Once determined, these locations are mapped onto the VMS
system and details incorporated into the ESR database to ensure works are undertaken in a considered
manner.
Access to this information is to be made available to employees and contractors in accordance with SP
AusNet’s (D) Transition Plan. However the Personal Digital Assistant (PDA) currently being used by field
staff contains regions of the Vegetation Management System which has the facility to flag spans where
there is an ESR requirement. This alerts the contractor to go to the printouts of the ESR database
appropriate to the region issued. It is anticipated that the information gained from the Environmental
Expert should be available to employees and contractors by January 2012.
The printout from the ESR database shall then list all areas of “threatened species” on that feeder. The
ESR database has been in existence for approximately 6 years and is understood by all vegetation field
personnel.
IJM Consulting Pty Ltd
33 of 39
SP AusNet Distribution BFM Audit Report
4.6
Notification and Consultation
SP AusNet has a procedure that outlines the process to be employed to notify and, where appropriate,
consult with persons affected by cutting or removal activities. The affected persons at each location shall
be determined as part of the vegetation assessments at each location.
After determining who should be notified, the process of consultation is employed at all levels where
proposed vegetation removal or cutting immediately affects the owner/occupier of the land. If urgent
pruning is undertaken in accordance with the Code, the responsible person or landowner shall be notified
as soon as practicable after the event in accordance with section 6 of the Code.
Notice by the Electricity Supplier Prior to Cutting or Removal of Vegetation
Before performing any cutting required by the Code SP AusNet gives at least 14 days written notice to the
occupier of the land on which the vegetation is to be cut and any affected person. If the tree intended to
be removed is within the boundary of a private property consultation is employed for the following:

arrangements for property access;

the use of chemicals for the treatment of regrowth;

the disposal of debris resulting from pruning and clearing;

planning of new powerlines which require pruning or clearing.
A signed record detailing the proposed works in accordance with the outcome of the consultation is
prepared and a copy provided to all parties. Where the affected person refuses to sign, a copy signed by
the SP AusNet representative is provided to the affected person detailing the proposed works.
Variations made to Vegetation Clearance Activities
In accordance with the VMP the method to maintain clearance between powerlines and vegetation shall
be determined so that Code compliance is achieved. This however does not preclude affected persons
from negotiating conditions under which other solutions may be used.

During the consultation process, where agreement to the vegetation management solution is not
achieved, the affected person shall be advised of the procedures to negotiate alternative powerline
construction arrangements to avoid or reduce the need for cutting or removal and the conditions that
apply to such arrangements. Costs of alternative proposals shall be provided to affected persons;

Where agreement is reached, a signed record detailing the proposed works in accordance with the
outcome of the consultation shall be prepared and a copy provided to all parties. Where the affected
person refuses to sign, a copy signed by the SP AusNet representative shall be provided to the
affected person detailing the proposed works.
Vegetation of Cultural or Environmental Significance
The Company has a procedure to ensure vegetation of Cultural or Environmental Significance is identified
and given special consideration when cutting or removal of vegetation is proposed.
The location of important vegetation is determined by consultation including:

Government Records;

Local Government and Interest Groups;

Land Owners.
The PDA currently being used by field staff contains regions of the Vegetation Management System and
has the facility to flag spans where there is an ESR requirement. This alerts the contractor to go to the
printouts of the ESR database appropriate to the region issued. The printout from the ESR database lists
all vegetation of Cultural or Environmental Significance on that feeder.
Consultation and negotiation with those responsible for vegetation of Cultural or Environmental
Significance is undertaken prior to commencement of works to obtain the most effective way of protecting
the affected vegetation while maintaining public safety.
IJM Consulting Pty Ltd
34 of 39
SP AusNet Distribution BFM Audit Report
Methods utilised to avoid and minimise the impact on vegetation include but are not limited to the following:

Transplanting of significant trees away from powerlines;

Line Augmentation/Relocation;

Reduced Cutting Cycles;

Site Specific Management Plans.
There are a number of single tree plans in the ESR database, which have specific instructions for
contractors to minimise the cutting impact on the tree. Advice is obtained from a qualified Arborist or
horticulturalist in relation to the regrowth of that vegetation prior to commencing cutting or removal of
vegetation of Cultural or Environmental Significance.
4.7
Urgent Cutting or Removal
SP AusNet Distribution’s has a procedure that describes the process by which the need to undertake
urgent pruning of vegetation near powerlines is minimised and if required how it is to be undertaken.
Urgent pruning/clearing may be required as a result of:

Encroachment or growth of vegetation that was not anticipated in the management plan. Need for
urgent pruning as a result of this is avoided by carrying out annual assessments and pruning/clearing
which allows for re-growth;

A tree falling or damage to a tree requiring the tree to be cleared to maintain the clearance space
required by this code. Need for urgent pruning as a result of this is minimised by managing the
network in accordance with the Hazardous Tree Procedure;

From the 1st November (if declaration was imminent) in any year until the end of the fire danger
period declared under the Country Fire Authority Act. The need for urgent pruning as a result of this
is avoided by having a tree assessment and pruning/clearing programme completed before the
Bushfire Declaration date in each specific region.
If urgent pruning is required the vegetation distance achieved must not exceed 1 metre beyond the
clearance space (including the distance allowed for the sag and sway of the conductors). If urgent
pruning has occurred the owner and occupier of the land on which vegetation was cleared is notified as
soon as practicable after completing the pruning or clearing using the Urgent Tree Works Notification
form.
Records of this type are recorded in the Extra Service Required Call Log (ESRCL) database for a period
of at least 2 years. These details include but are not limited to the following:

When and where the pruning or clearing was undertaken,

Details of why the pruning or clearing was required,

Details of the last inspection of that section of the electric line where the clearing was required.
To date Select Solutions has not had to undertaken any urgent pruning of this type.
4.8
Additional Duties of Local Councils, Roads Corporation and Others
The Company has a procedure, which outlines the process to be employed to assist Local Councils,
Road Corporation and Others in carrying out their duties about vegetation near powerlines. They
proposed vegetation work programs and advice on the need to use safe electrical work practices are
communicated to Local Government Authorities to ensure that tree clearing activities are coordinated and
rationalised.
On request, SP AusNet assists Responsible Persons to safely prune or remove trees near powerlines by:

providing specialist advice on safe work practices;

de-energising lines by agreement;

suppressing the auto reclose feature on HV circuits by agreement;

providing a list of authorised local service providers;
IJM Consulting Pty Ltd
35 of 39
SP AusNet Distribution BFM Audit Report

advising them on where to obtain advice and information on methods for maintaining clearance
between electric lines and vegetation; and

advising how to identify places where the cutting or removal of trees will be required.
SP AusNet annually sends out a letter advising all shires/councils of their requirements under the “No Go
Zone” legislation.
4.9
Management Procedures to Minimise Danger
SP AusNet (D) has a procedure, which outlines the process to be employed to provide advice to
occupiers of land where there is vegetation near a Private Overhead Electric Line (POEL). SP AusNet
communicates these line clearance issues by:

Issuing a letter to owners of overhead private electric lines each year to advise them of their
responsibilities in relation to such lines, the dangers of cutting and removal of vegetation, and the
precautions they should take to safely maintain the line;

Issuing a letter to owners of POEL’s of any tree clearing requirement it finds during inspections of
POELs;

Issuing a maintenance notice to property owners when tree clearing is required around service lines
which are their responsibility.
Leading up to and throughout the summer period, SP AusNet undertakes a public awareness program
utilising mediums which include print, electronic media and mobile billboards which primarily focus on the
danger of vegetation being too close to powerlines.
4.10 Dispute Resolution
Should a dispute arises during the process of consultation between landowners, affected persons and SP
AusNet regarding proposed cutting/removal/alternative construction activities, it is to be resolved in
accordance with SP AusNet’s complaint procedure. The Customer Complaint Procedure is based on the
resolution of the complaint at the lowest management level possible. The majority of issues arising have
been resolved at this level.
If the dispute cannot be settled at the current negotiating level, then the process allows for escalation up
to the next level of management within the appropriate organisation. The final escalation then rests with
the Energy and Water Ombudsman (Victoria) Limited.
There have been 14 complaints escalated to this level over the past 12 months. In addition, there were 9
other enquiries. Not withstanding the nature of the dispute, and the need to resolve the dispute in
accordance with the dispute resolution procedure, SP AusNet’s duty to maintain the clearance space at all
times should not be compromised.
SP AusNet Distribution provided an example of an ESR customer ID 2089 Mr David Honig who contacted
the EWOV to complain about proposed tree cutting and requesting that the work be carried out on the
weekend. This is an ongoing annual issue with this customer.
4.11 Training and Qualifications
SP AusNet (D) employees are required to have sufficient knowledge and training to ensure that
vegetation activities under their control are conducted in a safe and environmentally responsible manner.
The Company only engages contractors who have sufficient experience in the electrical industry to
perform tree clearing works in a safe manner. Whilst the level of experience that a new employee has
varies greatly, all employees that are new to the electrical industry must be approved by SP AusNet and
be initially supervised by an experienced person.
The Company has a procedure to ensure that cutting or removal of vegetation is undertaken in a
responsible manner. The procedure stipulates that SP AusNet Distribution is to conduct regular training
needs analysis of their employees and contractors to ensure that the level of training is consistent with
the requirements of the post. Results of audit processes are then reviewed in determining these needs.
IJM Consulting Pty Ltd
36 of 39
SP AusNet Distribution BFM Audit Report
Training programs emphasise the need to cut to meet Code requirements and prevent excessive pruning.
Auditing of contractors regularly undertaken to verify this requirement is being meet. The training
program covers competencies for:

Ground worker

Tree Climber

Wood Chipper Operator

Assessor

EWP worker
5. F IEL D A U DI TS
A ND
D A TA B AS E V ER IF IC AT IO N
The field audit included a detailed check of 107 sites (104 sites in the HBRA and 3 sites in the LBRA)
after downloading the pole details and asset defects from the Company’s database. The sites were
visited with Company representatives (Asset Performance Co-Coordinator and Select Solutions Program
Leaders) where the detailed information taken from the Company’s database records were crosschecked
against the actual condition of the assets in the field. Where an asset defect/anomaly existed that was
not recorded by the Company or the vegetation clearances at the site did not meet the new Electricity
Safety (Electric Line Clearance) Regulations 2010 it was noted. The information was then filtered to
determine the:

accuracy of the Asset Inspectors inspection and data capture;

accuracy of the vegetation assessment and data capture; and

accuracy of the information contained in the Company’s database.
The standard of asset maintenance and its agreement with the database in the LBRA was not able to be
determined due the lines that were chosen to be audited were under major road realignment or being
converted to underground due to expansion of residential subdivisions in the area.
Only minor non-maintenance items were identified that needed to be included in work packs for field
crews when carrying out other maintenance or construction work on the lines. They did not constitute an
immediate fire risk for the forthcoming for Fire Danger Period.
Vegetation clearances in the HBRA audited areas were excellent and cleared to Code requirements,
however vegetation service cable clearances on private property require more attention.
Results of Field Audit / Database Check
Total Sites Audited in the Field (Chosen from 205 plus sites downloaded sites form the
Company’s database)
107
Defective/Missing Asset Items
15
Audited items not Matching Company Database
1
Vegetation Spans Non Compliant with the Regulations - Electricity Suppliers Responsibility
(HBRA = 2 – LBRA = Zero)
2
Vegetation Spans Non Compliant with the Regulations - Other Authorities Responsibility (HBRA
= 2 – LBRA = Zero)
2
SP AusNet (D) is at present carrying out the pre-summer works and they have assured the Auditor that
they are able to complete all outstanding works for both assets and vegetation prior to their nominal
st
declaration date of 1 December 2011, or earlier if the CFA should bring forward the Fire Danger Period
dates. The Company is also confident that they can maintain a zero index throughout the Fire Danger
Period.
IJM Consulting Pty Ltd
37 of 39
SP AusNet Distribution BFM Audit Report
6. O B S ER V AT IO N S
There are 6 general and 6 field audit Company specific observations made during the audit
relating to SP AusNet’s (D) Bushfire Mitigation Program:

The Company is in the process of changing to a one year vegetation inspection and clearing cycle in
the LBRA. This is programmed to commence in 2012;

In the main vegetation found requiring cutting that is the responsibility of the Company had been
inspected and cut or programmed for cutting;

Vegetation Maintenance Notices are being issued to customers to clear their service lines but until
follow-up is carried out in the main it will not occur;

In the Auditors opinion temporary supporting of poles is an acceptable practice up to the Fire Danger
Period but they should not remain in service during that period;

SP AusNet has not considered there is a need to establish a life assessment of LV spreaders as they
are low cost items. In the Auditors opinion, irrespective of the low cost, an LV spreader is suspected
to be reaching its end of life and is a proven high fire risk item and remainder of life needs to be
determined;

The move by the Company to install service cable breakaway devices is excellent as it leaves the
services de-energised on the ground after being hit by vehicles or branches and reduces the risk to
the public;

There was little evidence within the areas audited in the field of an increased retrofitting program for
vibration dampers and armour rods at this stage, as the Company has only just sent out a Lines
Group NSD Standard Bulletin in September stating their requirements to all staff;

There were several defective crossarms between Corryong and Walwa, which the Auditor could not
gain details of due to paddocks being under flood. This area was flown in January 2011 so it is
anticipated that they were assessed in line with the field audit assets that were able to be checked;

Bird and animal proofing program is very evident in the field and it is clearly being requested in the
work orders being raised covering targeted HV structures;

The priorities being allocated by aerial inspectors is on the conservative side which matches with the
Company’s statement that the inspectors have been informed that “if there is a doubt they are to
allocate a lower priority”;

The Company is aiming to achieve an inspection cycle of 2.5 years or 4 inspections in 10 years (2 x
ground and 2 x aerial inspection). In the Auditors opinion this aim could be confirmed as policy (eg.
2.5 years plus 3 months) as it clearly aligns with current practice and well within the Regulations.

Doctor Tollhurst of Melbourne University conducted a fire consequence assessment and this has
been incorporated into a Network Fire Risk Model. In the Auditors opinion this assessment could be
used to determine areas (e.g. bushfire consequence figure of 1000 or greater) where new customers
or customers that are doing major relocation of the service point of attachment could be made to
install an underground service. This would reduce the risk of service damage/fires rather that
continually adding to the problem.
7. C O NC L U SI O N S
SP AusNet’s (D) Bushfire Mitigation Management personnel were well prepared and co-operative during
the audit and provided information to demonstrate their bushfire mitigation preparedness for the
forthcoming Fire Danger Period. Three Company personnel accompanied the field auditor and worked in
cold and inclement weather to maintain the audit schedule.
The Company’s Bushfire Mitigation documentation is complex and in the Auditors opinion would benefit
from consolidating their Bushfire Mitigation Plan, Strategy, and Manual (which contains their policies and
procedures) into one specific document covering all aspects of their bushfire mitigation programs.
IJM Consulting Pty Ltd
38 of 39
SP AusNet Distribution BFM Audit Report
The field audit of the Company’s operational area covered lines mainly in the HBRA (Kangaroo Ground
Patten Hill, Nariel Valley, Walwa, Burrowye, and Beechworth). The lines chosen in the LBRA (Whittlesea
and Diamond Valley) were under major road realignment or being converted to underground due to
expansion of residential subdivisions in the area. 21 minor defects and/or vegetation non-conformances
were identified out of 107 sites visited (104 HBRA and 3 LBRA).
SP AusNet (D) appears to have significantly improved the standard of asset inspection with only minor
differences being detected between the database/inspection reports and the actual assets in field within
the areas covered by this audit. The Company had carried out an aerial inspection of the areas audited in
the North East and allocated a conservative priority of identified defects, which was most times higher
than what the Auditor would have allocated. This is a direct change from the results of pervious year’s
audits.
SP AusNet (D) has established and gained agreement with ESV for transitional arrangements to comply
with the Electricity Safety (Electric Line Clearance) Regulations 2010 with arrangements providing for full
th
compliance by 29 June 2015. During the transitional period, they are therefore operating outside the
new/changed obligations imposed under the 2010 Regulations.
Although the pre-summer inspection cut was not complete the easements throughout the areas audited
were clear. Each site was crosschecked against the vegetation database and in all cases the vegetation
that was the responsibility of the Company to cut was programmed but in some cases access would be
difficult at this time due to flooding or poor ground conditions, although no site constituted an immediate
danger. The Company is issuing Vegetation Maintenance Notices to customers to clear their service
lines but in the main this is ineffective as there is no follow-up or penalties involved.
Although this audit was carried out earlier this year the Company is well into their pre-summer scheduled
work and in the Auditor’s opinion SP AusNet’s (D) preparedness for the forthcoming fire season is in line
with their Bushfire Mitigation and Vegetation Management Plans. At the date of the audit the Company
was confident that they have the resources to complete the remaining asset replacement work and the
vegetation pre-summer cutting/removal. This opinion was supported from observations in the field.
8. R EC OM ME N D A TI O NS
It is recommended that:

SP AusNet (D) modifies the heading of document number BFM 21-77 & BFM 21-78 to reflect that this
procedure is used across the business;

SP AusNet (D) modified the Business Rules to reflect the change in inspection cycles and
acknowledge the transition period for concrete, steel, and timber poles.

SP AusNet (D) considers reducing their limited life retest period to approximately half their inspection
cycle. (Currently 2.5 years with the asset inspection cycle now being aimed at 2.5 years or 4 in 10
years - 2 x ground and 2 x aerial inspection);

SP AusNet negotiate with ESV to amend the targets in the Exemption to reflect the actual total of
56M spans to be eliminated

SP AusNet (D) moves to completing the changing of all unserviceable poles in the HBRA before the
commencement of the Fire Danger Period and should any be detected during the Fire Danger Period
that they are treated as faults and changed immediately;

SP AusNet (D) instigates a follow-up to the Vegetation Maintenance Notices for customer service
clearance and ensures that clearance is achieved;

SP AusNet (D) modifies their Vegetation Management Plan to reflect the correct terminology in
relation to information issued to POEL and private service lines, which is the owner’s responsibility.
Auditor’s Signature:
Date: 1 November 2011
Ian J McDonald
IJM Consulting Pty Ltd
39 of 39
SP AusNet BFM Audit Report 2012
Table of Contents
BUSHFIRE MITIGATION AUDIT 2012-2013........................................................................................................ 2
1.
AUDIT SCOPE AND APPROACH .............................................................................................................. 2
1.1
1.2
1.3
2.
BUSHFIRE MITIGATION PLAN......................................................................................................................... 2
VEGETATION MANAGEMENT PLAN ................................................................................................................ 4
CFA/DSE EXPECTATIONS FOR THE 2012/13 FIRE SEASON ............................................................................ 4
GENERAL MATTERS .................................................................................................................................. 5
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
3.
MANAGEMENT OPERATIONAL ORGANISATION STRUCTURE .......................................................................... 5
BFM PLAN – MONITORING & AUDITING ....................................................................................................... 7
MAJOR STEP CHANGES .................................................................................................................................. 8
ADDITIONAL INITIATIVES IMPLEMENTED TO MITIGATE FIRES IN THE PAST 12 MONTHS ............................... 9
ANALYSIS OF FAULTS FOR POTENTIAL CAUSES OF FIRE .............................................................................. 10
PREPARATION FOR THE FIRE DANGER PERIOD ............................................................................................. 11
FIRE SEASON OPERATIONAL PLANS ............................................................................................................. 13
PROTECTION SETTINGS ................................................................................................................................ 14
ASSET INSPECTION AND MAINTENANCE PROGRAM ................................................................... 14
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
3.10
3.11
4.
GENERAL ..................................................................................................................................................... 14
BRIEFING EMPLOYEES AND CONTRACTORS ON POLICY/PROCEDURES ......................................................... 15
ASSET INSPECTION ....................................................................................................................................... 17
TRAINING QUALIFICATIONS AND AUDITING ................................................................................................ 17
ARMOUR RODS & VIBRATION DAMPERS ..................................................................................................... 18
CONDUCTOR ................................................................................................................................................ 19
SWER CONVERSION .................................................................................................................................... 19
CROSSARMS ................................................................................................................................................. 20
HV FUSE REPLACEMENT ............................................................................................................................. 20
SWER OCR/ACR REPLACEMENT ............................................................................................................... 21
3-PHASE ACR CONTROLLERS ...................................................................................................................... 22
VEGETATION MANAGEMENT............................................................................................................... 23
4.1
4.2
4.3
4.4
4.5
4.6
4.7
5.
VEGETATION MANAGEMENT ORGANISATION STRUCTURE .......................................................................... 23
MEASURES ADOPTED TO ASSESS PERFORMANCE ........................................................................................ 23
VEGETATION MANAGEMENT PROGRAMS AND CYCLES ............................................................................... 24
CLEARANCE SPACE FOR ELECTRIC LINES .................................................................................................... 27
HAZARD TREES ............................................................................................................................................ 28
ALTERNATIVES TO TREE CLEARING............................................................................................................. 29
COMPANY SPECIFIC QUESTIONS .................................................................................................................. 29
FIELD AUDITS AND DATABASE VERIFICATION ............................................................................. 30
5.1
5.2
5.3
ASSET FIELD AUDIT ..................................................................................................................................... 30
RESULTS OF FIELD AUDIT / DATABASE CHECK............................................................................................ 31
CONSTRUCTION SCHEDULING AND SCOPE OF WORKS ................................................................................. 31
6.
OBSERVATIONS ......................................................................................................................................... 33
7.
CONCLUSIONS ........................................................................................................................................... 34
8.
RECOMMENDATIONS .............................................................................................................................. 35
IJM Consulting Pty Ltd
1 of 35
SP AusNet BFM Audit Report 2012
BUSHFIRE MITIGATION AUDIT 201 2-2013
1. A U D IT S C O PE
AND
A P PR O AC H
The audit was conducted on SP AusNet Distribution in accordance with Energy Safe Victoria (ESV)
Bushfire Mitigation Audits 2012/2013 Scope of Works, dated August 2012, and in conjunction with
Electricity Safety Regulations and other subordinate legislation. Particular emphasis was placed on the
policies, procedures, and practices adopted in the Electricity Supplier’s plans that mitigate the potential
for bushfire starts. The SP AusNet Bushfire Mitigation Plan (BMP) and Vegetation Management Plan
2012-13 (VMP) have been used as the base reference documents to outline the Company’s standard of
performance, and activities undertaken to comply with the intent of the Regulations.
st
th
The audit was conducted in four stages, between 1 November 2012 and 12 November 2012 which
included an assessment of the Electricity Supplier’s assets and vegetation line clearances in the field.
The Company was given a minimum of a weeks notice on the aspects of the audit to be undertaken. As
part of this implementation:
1. A desktop assessment was conducted of the Company’s policies, procedures and work programs in
relation to their bushfire mitigation and vegetation management plans, including deviations from past
practices to determine the effectiveness of the programs over the past 12 months, including a
detailed audit of the statistics supplied to ESV and assessment of the Company’s ability to meet
agreed targets;
2. A discussion with field personnel and their Management (at their depots) to determine their
understanding of the Company’s major bushfire mitigation programs and the methods used to
disseminate information relating to changes to the Company’s policies and procedures;
3. A field audit which included a detailed check of 266 asset sites after downloading pole details and
asset notifications (defects) from the Company’s database. (195 sites in the high bushfire risk area
(HBRA) and 71 sites in the low bushfire risk area (LBRA). The sites were visited with Company
representatives where the data records were crosschecked against the actual assets in the field.
Where an asset defect/anomaly existed that was not recorded by the Company or the vegetation
clearances at the site did not meet the Electricity Safety (Electric Line Clearance) Regulations 2010 it
was noted. The information was then filtered to determine the:

accuracy of the Asset Inspectors assessment and data capture;

accuracy of the vegetation assessment and data capture; and

quality of the information contained in the Company’s database.
4. For the vegetation audit 4 separate areas of SP AusNet’s vegetation data was downloaded from the
Company’s database showing pre-summer inspection and cutting complete of which 208 sites were
chosen. These sites were then visited and an assessment made from this sample on the ability of the
Company to achieve code clearance and meet regulatory requirements for the Fire Danger Period;
5. The audit also included visiting 10 sites taken at random from the Electricity Suppliers work schedule
to confirm that work in the field is being completed in line with Company policies and procedures, and
that the standard complies to their construction manuals;
The field audits were carried out within the Electricity Supplier’s licensed boundaries in accordance with
the areas specified by ESV Executive Manager Infrastructure Safety. The level of the Company’s
compliance was determined from the selections.
1.1
Bushfire Mitigation Plan
th
SP AusNet Distribution submitted their Bushfire Mitigation Plan to Energy Safe Victoria on 28 June
th
2012, and a letter of acknowledgement was received on 12 July 2012. The BMP outlines how the
Company intends to comply with the Electricity Safety Act and the Electricity Safety (Bushfire Mitigation)
Regulations 2003 plus the Amendment Interim Regulations 2010.
IJM Consulting Pty Ltd
2 of 35
SP AusNet BFM Audit Report 2012
The objectives of the SP AusNet Bushfire Mitigation Plan are to:

Describe the strategies and programs implemented to mitigate the risk of fire ignition from supply
network assets in high bushfire risk areas;

Describe the processes and procedures for monitoring the implementation and effectiveness of the
bushfire mitigation strategies and programs;

Describe the corrective action processes and procedures ensuring effectiveness of the bushfire
mitigation program;

Describe the processes and procedures that apply to operation and maintenance of the supply
network in high bushfire risk areas during the fire season period and total fire ban and code red days;

Nominate persons responsible for preparation and implementation of the Plan and their contact
details;

Provide contact details in the event of an emergency;

Demonstrate compliance with the Electricity Safety (Bushfire Mitigation) Regulations 2003; and
Appendix 1 provides a compliance matrix for this Plan.
SP AusNet responded to previous ESV audit observations that their Plan and Strategy should be
reviewed to provide a less complex framework. The Company consulted with ESV on the development of
a revised BFM Plan which has now replaced the previous version of a combined BFM Plan and Strategy.
The new Bushfire Mitigation Plan 2012- 2013 is detailed and covers the intent of the Regulations and was
accepted by ESV on the 31 October 2012.
Additional Information Requested by ESV for the BMP
ESV required SP AusNet to provide additional information in the BFM Plan due to the revision of the
Electricity Safety (Bushfire Mitigation) Regulations on 28 June 2012. The changes included unintended
consequences that effectively required all network assets to have prescribed inspection intervals of < 37
months.
SP AusNet applied to ESV for an exemption from regulations 5A (e), (g), (h), (j), (l), (m) and (o) of the
Electricity Safety (Bushfire Mitigation) Regulations for all supply networks within low bushfire risk areas on
13 July 2012. ESV subsequently consulted with SP AusNet over the required information to support the
exemption application. A revised exemption application was made in SP AusNet’s letter dated 10
September 2012.
The Company subsequently submitted a revised BFM Plan (version 16) on 15 October 2012 in
accordance with the regulatory framework under the exemption request. ESV responded on 18 October
2012, providing an evaluation matrix noting some minor changes required of the BFM Plan.
1. 5A(h) Preventative strategies to be adopted by the major electricity company to minimise the risk of
the major electricity company’s supply networks starting fires.
ESV - 8.2.1 ‘All remaining supply network assets are exempt from a prescribed maximum inspection
interval of 37 months. These assets do present a risk of bushfire ignition and are therefore excluded
from the Bushfire Mitigation Plan’
Plan must consider LBRA area in accordance with the Act and
Regulations. This area has a Low Bushfire risk and can not be excluded from the plan on the
grounds of no risk.
SP AusNet Response - Amended in Plan (v16) dated 18/10/2012
2. 5A(i) A list of all works required for the strategies referred to in paragraph (h) to be undertaken and
the date by which the works are to be completed.
ESV - What is the BMI calculation? Where is it? How often is it reported to ESV?
SP AusNet Response - Not discussed in Plan. Details of BFM Index for Distribution are referenced
in the BFM Manual and procedures. (As with Transmission). Report is sent monthly ESV during
declared fire season.
IJM Consulting Pty Ltd
3 of 35
SP AusNet BFM Audit Report 2012
3. 5A(j) a plan for inspection that ensures that all of the major electricity company's supply networks are
inspected at regular intervals of no longer than 37 months;
ESV - See 1 above for comment.
SP AusNet Response - Refer 1 above
4. 5A (n)(vi) monitor and audit the competence of the persons assigned to carry out inspections under
the plan;
ESV - Plan mentions audit templates. Please provide templates.
SP AusNet Response - Provided templates
SP AusNet subsequently responded the same day with revisions to the BFM Plan (v16) as recommended
and received acceptance of their Bushfire Mitigation Plan 2012-2013 on 31 October 2012.
1.2
Vegetation Management Plan
SP AusNet submitted their Vegetation Management Plan on 30th March 2012 and received approval of
their Plan from Energy Safe Victoria on 4th July 2012. ESV did not request any additional information
regarding the Plan prior to acceptance.
The objectives of the Vegetation Management Plan are:

To demonstrate SP AusNet’s compliance with the Electricity Safety (Electric Line Clearance)
Regulations 2010 (the Regulations) and the Schedule - Code of Practice for Electric Line Clearance
(the Code) for the preparation of a management plan;

To provide a framework to ensure the prescribed clearances are maintained between vegetation and
electric lines.

To provide for safe and reliable operation of distribution lines;

To attain self-managing easements by removing inappropriate species, limiting existing vegetation
height to an acceptable level at any position along a span and encouraging low growing appropriate
species;

To develop easements in the long term which are more sustainable, are subject to minimal
disturbance to significant vegetation and provide amenity for the community;

To provide guidance to SP AusNet personnel and contractors for vegetation management practices
associated with the Code; and

Implement the Plan in accordance with exemptions
SP AusNet’s VMP is detailed and well laid out making it easy to read and understand.
1.3
CFA/DSE Expectations for the 2012/13 Fire Season
The CFA conducted a briefing on 30th October 2012, which covered the expected risk and severity of fire
conditions, weather, and projected anticipated commencement of the Victorian declaration periods.
Recent climate conditions have shown:

The past three years has seen above average rains across most of Victoria. However more recently
(last 12 months) drier than average conditions have been experienced across the north.

In relation to temperature there has been above average temperatures across large areas of the
State for the last 12 months, this is particularly pronounced in the past month.

Minimum temperatures have been close to average across much of the State in the last month with
the exception being southern coastal areas.
IJM Consulting Pty Ltd
4 of 35
SP AusNet BFM Audit Report 2012
In relation to SP AusNet’s operational areas the CFA Regions expect:

Spring grass growth continuing, better than in recent years including grass fuel loads abutting urban
interface;

Silage being cut, hay season is beginning;

Good cropping growth however in some areas the growth delayed due to frosts;

Most forest areas have good moisture recovery after effects of drought and will dry later in the
season;

Forest fuels are damp but with prolonged higher Fire Danger Index days will support intense fires
under the right conditions;

Coastal heath lands are prone to fire even early in the fire season, a number of fires have already
occurred in these areas;
In consideration of the above indicators the CFA has concluded that:

The next three months are expected to have average rainfall and a slightly elevated chance of
exceeding average maximum and minimum temperatures;

Coastal areas of Gippsland have been drier and warmer than average resulting in a number of fires
already, this is expected to continue throughout the summer period;

Key risk for this summer will be short fast running grassfires possibly beginning in the west of the
State.
The implementation of the fire declaration dates is to be progressive across the State. These dates shall
come into effect as the fire risk increases with the exception of the Colac Otway and Corangamite Shires,
st
which commenced on the 1 November 2011. No indication was given when the remaining Shires are
likely to declare but it is expected that it would progress from the North West through the State. At the
time of the audit no Shire had been declared in SP AusNet’s operational area.
2. G E NER A L M A TT ER S
2.1
Management Operational Organisation Structure
SP AusNet’s BFM Plan discusses management of the bushfire mitigation obligations through the
Networks Safety Management Committee (NSMC).
The principle objective and role of the NSMC is to understand and manage the safety and bushfire risks
in planning, designing, constructing, operating, maintaining and decommissioning its supply networks to
minimise in so far as is practicable
a) the hazards and risks to the safety of any person arising from the supply network;
b) the hazards and risks of damage to the property of any person arising from the supply network;
and
c) if that network is an at-risk supply network, the bushfire danger arising from that network.
Accordingly, the Charter for the NSMC is to guide development, implementation, and monitoring of
network asset management strategies and programs with the objective of minimising risks and hazards to
persons and property as low as reasonably practicable (ALARP). The committee, whose membership
consists of senior personnel from various business streams, provides the operational leadership and
coordination of resources engaged in the development and implementation of bushfire mitigation,
vegetation management and asset safety programs designed to achieve this objective.
The NSMC utilise a range of performance indicators to monitor implementation of the Plan which are
provided in a monthly Network Safety Report. The key indicators are:

Bushfire Mitigation Index – monitors implementation of inspection, maintenance, and replacement
activities contained within the General Maintenance program. Maintaining a ‘zero index’ is a key
performance objective during the declared fire season; and

Enhanced Safety Program reports – monitors implementation of individual Enhanced Network Safety
programs.
IJM Consulting Pty Ltd
5 of 35
SP AusNet BFM Audit Report 2012
The NSMC Charter includes member titles, roles, and responsibilities.

Group General Manager, Networks Strategy & Development

GM Operations and Services Integrated Network Services – leads and directs the operations and
services team to safely deliver the approved programs to work within time and cost budgets, while
managing risks to ensure total asset service performance and HSE targets are met;

GM Select Solutions – responsible for establishing and managing a stand alone business unit to
increase business value for SP AusNet through growth and provision of excellent service to
customers;

Director Network Engineering – responsible for the delivery of the Asset Management Plan for NSD
through transforming Asset Management Strategies into short and long term plans to maximise
network performance in order to generate value from networks and assets for the benefit of the
community, customer, and security holders;

Director, Regulation and Network Strategy – is responsible for optimising regulatory outcomes and
revenue and aligning Regulatory and Network Strategies to maximise performance; and

Manager Network Safety – is responsible for the implementation of the policies and strategies for
ensuring that SP AusNet manages the Network Safety risks associated with designing, operating,
maintaining and constructing a safe, high performing and sustainable electricity transmission and
distribution assets to fulfil regulatory obligations, business drivers and risk exposure for SP AusNet,
its customers and the general public.
A detailed organisational hierarchy is available on their Intranet (InSite), which illustrates the respective
reporting hierarchy of NSMC members.
Depot Audit Comment:
SP AusNet’s personnel structure for field activities are as follows:

Eastern Region Manager is accountable to manage the field and office based service teams in
delivering construction, maintenance, fault response, design, and customer negotiations and to be
carried out within approved programs of work, within time and cost budgets, while managing risk.

Site Manager is responsible for establishment of the work sites. The ongoing oversight of all HSE&Q
on site for the duration of the project and feedback of issues to the project leader;

Works Manager is responsible to ensure the effective delivery of the Network Services Group works
program on budget, on time with compliance to quality, environmental and safety standards;

Planner is accountable for the scheduling, co-ordination and facilitation of planning outages of the
Electricity network

Crew Leader provides operational leadership to meet schedule, quality and cost target while ensuring
company safety and environmental policies and procedures are applied and adhered to by all team
members.

Worksite Leader is to lead and manage a work crew to ensure the completion of activities in a timely
and cost effective manner whilst working within Company OH&S policies and procedures and using
efficient work practices.

Truck Leader – Position description was requested but not supplied

Glove & Barrier Linesman is to install and maintain electrical network assets supplying domestic,
industrial and commercial customers in accordance to SP AusNet’s standards and procedures.
Conduct day to day operations according to SP AusNet values of Safety, Passion, Teamwork,
Integrity, and Excellence ensuring company safety and environmental policies and procedures are
applied and adhered to by all team members.

Apprentice Electrical Line Workers undertake a four year program to be trained in the installation,
repair and maintenance of overhead lines and cables carrying electricity to domestic, commercial and
industrial users
IJM Consulting Pty Ltd
6 of 35
SP AusNet BFM Audit Report 2012
2.2
BFM Plan – Monitoring & Auditing
The bushfire mitigation program is monitored in accordance with the requirements of the Bushfire
Mitigation manual and reported via the Network Safety Report (NSR) with the following sections providing
the monitoring reports:

Network Performance KPIs which include the Bushfire Mitigation Index and F-factor performance;

A summary of progress against the Enhanced Network Safety programs; and

A summary of progress against operational programs that includes vegetation management.
Auditing of works is monitored and reported through section 8 of the NSR. Audits include a broad range
of auditing performed under the quality management system:

Asset Inspector Work Quality;

Metering Quality of Work;

Quality of Work;

EWP Audit;

Maintenance; and

Servicing and Metering Worksite.
The Technical Compliance Audit Strategy covers each of the major asset class and three major phases of
the asset life cycle have been considered. The phases and assets are tabulated into life cycle phases of:

Design Components;

Construction Components; and

Maintenance Components.
Identify Deficiencies - Deficiencies of the plan are identified and reported through the NSR reports to the
NSMC. These deviations are noted in the NSMC minutes and assigned appropriate persons to
implement remedial actions to bring the plan on target. The NSMC monitors progress of the remedial
actions.
Monitor and Audit - The effectiveness of inspections carried out under the plan is via:

Monitoring of the inspection program is achieved by reporting provided in the NSR by measuring
delivery against seasonalised targets, and Network performance KPI’s

Audit of the effectiveness is monitored directly through the NSR. Audit of asset inspector’s work is
undertaken in accordance with SP AusNet’s procedure. The audit results are represented via the
scorecard
Plan Improvement - Improving the Plan’s implementation is derived through the iterative process of
monitoring network performance KPIs, program implementation KPIs, and auditing provided through the
NSR, and managed through the NSMC, and Network Safety Group.
The Network Safety Management Committee has 2 agenda items that directly relate to the identification
of improvements / initiatives and emerging risks. Examples in the September minutes are:

Wires Down Alert;

Service Disconnect Device;

HV ABC Failures; and

Conductor Failure.
IJM Consulting Pty Ltd
7 of 35
SP AusNet BFM Audit Report 2012
2.3
Major Step Changes
SP AusNet has implemented the following step changes in the last 12 months:
1. SP AusNet has established the Network Safety group within the Network Strategy & Development
division with a focus to manage network safety outcomes for the three networks (Transmission,
Distribution, and Gas). As such, this group is also responsible for the management of the regulatory
obligations under the Electricity Safety Act 1998 and are therefore the primary point of liaison with
ESV.
Within the Network Safety group is a Bushfire Mitigation Manager to oversee the development and
implementation of the bushfire mitigation policies, procedures, and programs. The Bushfire
Taskforce Manager is responsible for the monitoring and implementation of the Victorian Bushfire
Royal Commission and Power lines Bushfire Safety Taskforce recommendations.

Reporting to the Manager Network Safety (new position) are:

Bushfire Mitigation Manager;

Network Risk & Performance Manager; and

Bushfire Taskforce Implementation Manager.
2. SP AusNet has established the Networks Safety Management Committee with a Charter;
3. The Network Safety group has developed and implemented a monthly Network Safety Report that
enables the NSMC to monitor network performance KPIs, implementation of operational programs
and auditing of works under these programs; and
4. Since last fire season SP AusNet has progressed with the replacement of SWER OCR’s with remote
control ACR’s in the areas identified by ESV’s 2011/12 Fire Loss Consequence Model as having the
highest 80% loss consequence. SP AusNet anticipates these ACR’s, together with multi-phase
ACR’s/CB’s controlling networks within these areas, to be capable of remote control for the 2012/13
declared fire season. The list of devices is provided to ESV in accordance with the BFM Plan as the
list is updated.
Depot Audit Comment:
Step changes that have been introduced into the Seymour/Leongatha depot during the last 12 months
are:

Smart phones – for faults and communications;

IPads - Direct access to emails and some systems;

Issue of laptops to new connections staff to enable reprogramming of smart meters for solar
installations;

Sharing of work between capital and maintenance to maintain skills;

Small jobs used as training for apprentices;

Combining crews over large shutdown areas into specialist groups;

Balancing of internal and contract crews by the employment of additional SP AusNet Line workers;

Introduction of a training program for A grade electricians to convert to Line Workers. (4 in East, 4 in
North & SP AusNet are looking for other DB’s to make up class size – 15 in total), with the aim of
future employment in the faults and new connections as inspectors;

Worker input into fleet management and design of new equipment;

Modified work methods to achieve access and job completion; and

Training of personnel in heavy vehicle recovery.
IJM Consulting Pty Ltd
8 of 35
SP AusNet BFM Audit Report 2012
2.4
Additional Initiatives Implemented to Mitigate Fires in the Past 12 Months
SP AusNet has implemented the following additional initiatives to mitigate fires in the past 12 months;

A rapid earth fault current limiter (REFCL) at Woori Yallock zone substation trial has commenced and
is currently at the design stage. As a consequence of the 2009 Victorian Bushfires Royal
Commission, the Powerlines Bushfire Safety Taskforce (PBST) was established to undertake
investigation into more complex technical solutions that may be applied within Victoria’s electrical
distribution networks to mitigate the risk of fire ignition from network faults. The PBST identified an
opportunity, through the application of REFCL’s, to reduce the risk of fire ignition by 70% for network
related faults.
Accordingly, a key driver for establishing a trial REFCL within SP AusNet’s network is to determine
the suitability and effectiveness of this technology as a means of mitigating the risk of fire ignition
associated with faults on complex rural distribution networks.
Details of this trial are discussed in the Enhanced Network Safety Strategy accepted by ESV;

A trial of approximately 1km of Hendrix covered cable has been established at Coldstream to
determine its effectiveness as an alternative to bare conductors in the highest bushfire risk areas.
The trial is not complete at this time;

A revision to the enhanced Network Safety strategy has been accepted by ESV for:

Additional EDO’s – 9,514;

Revised scope to 3ph ACR controller program;

Zone substation protection relay replacements – 114 replacements & 107 upgrades;

Trial rapid earth fault current limiter (REFCL) at Woori Yallock zone substation;

Aerial spaces – 10,242 spans to be surveyed and rectified; and

Vibration dampers and armour rods – approx. 59,600 poles by 2016
Progress on Previous Initiatives/step Changes During the Past 12 Months
SP AusNet’s progress on previous commenced initiatives / step changes during the last 12 months:

Mid cycle inspection: Now adopted and integrated within the asset management system as part of the
cyclic inspection program to achieve compliance with the prescribed requirement to inspect <37
month intervals. The transition to compliance is scheduled for completion by 31 December 2012 in
accordance with the exemption provided by ESV - On track to complete prior to the transitional plan
target date; and

Priority Codes: Implemented within the BFM Plan – Completed.
In addition the following initiatives have been implemented to mitigate fires in the past 12 months:

EDO Fuse replacement - Program is ahead of schedule and is reported quarterly to ESV;

Conductor replacement - Program is progressing to schedule and is reported quarterly to ESV;

Neutral Screen Service cable replacement – Program is ahead of schedule and is reported quarterly
to ESV; and

HV Insulator replacement program - Program is ahead of schedule and is reported quarterly to ESV;

Bird & animal proofing – Program is ahead of schedule and is reported quarterly to ESV;

Accelerated crossarm replacement program – Program is slightly below target and is reported
quarterly to ESV;

Hazard tree removal program – Program is ahead of schedule and is reported quarterly to ESV; and

Ground based Asset Inspection - Completed.
IJM Consulting Pty Ltd
9 of 35
SP AusNet BFM Audit Report 2012
2.5
Analysis of Faults for Potential Causes of Fire
The Network Safety Report illustrates the number of asset related fires for 2011 and 2012 YTD against
the five year benchmark (2006-2010) established by the AER for reporting against the F-factor incentive
mechanism. This mechanism is designed to reduce the number of fires incidents associated with network
assets.
Ground Fire Starts from Electrical Distribution
SP AusNet has had 51 ground fire starts from distribution assets in the last 18 months (March 2011 –
September 2012).
FIRE YTD (18 months) to September 2012
Cause
Ground
Asset
Total
Tree
15
12
27
FOLCB/Isolators
6
11
17
HV Fuses
6
145
151
Animal / Bird
6
2
8
Conductor
3
7
10
Tx / Surge diverter
6
5
11
Cable
3
3
6
Vehicles
4
1
5
Crossarm
1
6
7
Pole fire
1
13
14
Street light
0
24
24
Pole Top Fires
The March Network Safety Report (NSR) indicates 125 asset fires out of a total 160 for the 12 months to
March 2012. The September 2012 NSR indicates 93 asset fires out of a total 108 for the six months to
September 2012. Note: Trees have been excluded from the pole top fire count.
Review of Analysis of Faults for Potential Causes of Fire and Asset Failures
EDO fuse hang-ups are the predominant cause of asset fires. SP AusNet has prepared a plan to
increase the volume of EDO replacement with Boric Acid through to the end of 2015. The replacement
program is prioritised in accordance with the Fire Loss Consequence Model.
The Enhanced Network Safety strategy provides detail of the program that has been accepted by ESV.
Other programs included within the enhanced network safety program include conductor, crossarm, and
insulator and service cable programs together with a hazard tree removal program. Progress of these
programs is provided monthly in the Network Safety Report to the Network Safety Management
Committee and quarterly reporting to ESV.
Risk Analysis of Potential Fire Starts in LBRA fringing HBRA
SP AusNet has performed analysis of reported ground fire incidents in LBRA’s for 2012. All incidents
2
have been contained with the LBRA. The largest fire incident was an area of 115m . This incident was
due to an excavator making contact with overhead high voltage conductors on a commercial property.
2
The remaining incidents averaged 10m .
Analysis of ground fire incidents over the same period in the HBRA’s indicated an average fire size of
2
2
700m with the largest being 10,000m .
IJM Consulting Pty Ltd
10 of 35
SP AusNet BFM Audit Report 2012
The CFA’s assessment criterion for an LBRA is that it is not capable of carrying a fire into HBRA’s.
These results, together with experience gained in undertaking fire hazard mapping with the CFA, indicate
the CFA’s assessment criteria is consistent with LBRA’s not being capable of carrying fire into HBRA’s.

2012 LBRA Ground Fire Incidents = 8

2012 HBRA Ground Fire Incidents = 25
Actions Arisen from the Analysis
SP AusNet’s Enhanced Network Safety Strategy is focused toward the mitigation of fire and electric
shock risks across the Network. This involves detailed analysis being carried out of Network incidents
and the monitoring of trends in Network asset class failure. An example of this is the introduction of an
EDO replacement program.
SP AusNet maintains the fire control authority’s ratings within its geographical information system (GIS)
for its assets. The Bushfire Mitigation Plan provides details of the GIS that delineate HBRA’s and LBRA’s
and the activities in relation to the fire hazard rating of an area.
2.6
Preparation for the Fire Danger Period
The status of the List of Works that are to be undertaken in readiness for the next fire season is as
follows:

Monthly monitoring through the Network Safety Management Committee and reported via the
Network Safety Report:

Prepare list of outstanding critical maintenance items;

Prepare summary of Fire Reports and issue to NSMC;

Prepare Bushfire Mitigation Report and issue summarised report to NSMC;

Provide NSMC with Bushfire Mitigation Status Report;

Review Bushfire Mitigation Reports and initiate action as required;

Resolve queries & initiate action on matters requiring attention from summarised Bushfire
Mitigation Report;

Include summary of Bushfire Mitigation Report in the Network Safety Report; and

Arrange meetings of NSMC.

Prepare SP AusNet’s Vegetation Management Plan - Complete;

Approve SP AusNet’s Vegetation Management Plan – Complete;

Submit Vegetation Management Plan to the ESV for approval by 28 February – Complete;

Finalise Fire & General Liability Insurance Renewal Underwriting Submission – In Progress;

Finalise Bushfire Mitigation Plan and submit to NSMC for endorsement – Complete;

Submit Bushfire Mitigation Plan to ESV for approval by 1 July – Complete;

Decide on advertising for summer period – Complete;

Commence monthly BFM reporting to ESV upon declaration until end of the fire danger period (BFM
Index) – Pending Declaration;

Issue letter and information brochures to Overhead Private Electric Line customers - In progress;

Request permits to work on days of Total Fire Ban from MFB, CFA and DSE – Completed;

Coordinate senior management review visit programs – In Progress;

Post on the Intranet copies of permits to work on Days of Total Fire Ban – In Progress;

Perform Senior Management Reviews – November & December;
IJM Consulting Pty Ltd
11 of 35
SP AusNet BFM Audit Report 2012

Target date for submission of Operational Contingency Plan (if required) - Pending Declaration;

Complete all BFM works - Pending Declaration;

Complete all vegetation works in HBRA areas - Pending Declaration; and

Complete all BFM obligations - Pending Declaration.
Changes Implemented to the List of Works in the last 12 months
SP AusNet is currently in the process of updating their Calendar of Events. The main change that has
occurred is the removal of specific dates with reference to Declaration.
Deadlines Not Achieved Prior to the Fire Danger Period
The Bushfire Mitigation Manual contains the process for establishing contingency planning in the event
bushfire mitigation works are not complete. The Network Safety Management Committee is responsible
for initiating the establishment and meeting frequency of sub-working group/s, if required, to develop and
implement network contingency plans to ensure the management of outstanding bushfire mitigation risks
or hazards that have not been addressed through normal business processes.
If required, an Operational Contingency Plan is to be prepared to identify transmission and distribution
lines on which fire prevention work is incomplete and for which disconnection may be appropriate on
Total Fire Ban and Code Red days.
Disconnection of the electricity supply to an area on Total Fire Ban or Code Red days has serious
implications for the community in terms of disruption to communications, water supply pumps and general
fire-fighting services, and must only be considered as a last resort action when the local weather
conditions become extreme.
Outstanding Works to be Completed Prior to the Fire Danger Period
SP AusNet uses the Bushfire Mitigation Index to monitor all outstanding Bushfire Mitigation works. At the
date of the audit the following items were outstanding in HBRA:
th
Maintenance Activity
Current @ 29 September
2012
Look Ahead @ 31
December 2012
Cyclic Pole Inspections
9,292
9,980
POEL Inspections (# poles)
14
128
Pre-summer vegetation Inspections
0
0
US & Limited Life poles
75
522
5,852
5,852
347
1,124
Conductor outstanding
7
13
Unacceptable surge diverters
15
36
Bird covers outstanding
36
262
Spans not cleared of vegetation
Attachments outstanding
st
SP AusNet has stated that they have the resources in place to complete outstanding works.

The September Network Safety Report provides forward resource planning for bushfire mitigation
(maintenance) works for the North and East Regions and balance resources between other network
activities to ensure the bushfire mitigation works are completed within the required timeframes;

The Central Region, where the work is contracted to Tenix, is monitored in a similar fashion to North
& East regions via their contractual arrangements. Tenix manage and plan the necessary resourcing
levels to meet Bushfire Mitigation obligations; and
IJM Consulting Pty Ltd
12 of 35
SP AusNet BFM Audit Report 2012

2.7
All Bushfire Mitigation works for North, East & Central are monitored by the Integrated Network
Service (INS) works management group to coordinate all construction resources. This may mean
that internal or other service provider resources are moved into Central Region to support the Tenix
contract.
Fire Season Operational Plans
SP AusNet has a procedure that requires the business to ensure compliance during the declared fire
season:

Prior to the declaration of the fire season SP AusNet is to obtain annual fire season permits from the
MFB, CFA and DSE enabling the use of fire in the open air on Total Fire Ban days.

Copies of the permits to be placed on SP AusNet’s networks Intranet site.

Field managers to ensure that relevant personnel within their organisation, including contractors, are
advised of the permits. Should restricted activities such as welding, gas cutting, and grinding, using a
blow lamp or gas torch are to be undertaken on days of Total Fire Ban, a current copy of the
appropriate permit must be held on site. All conditions on the permits must be adhered to.

SP AusNet personnel are to ensure that contractors under their control adhere strictly to the
conditions of the permits.

Field crews shall ascertain Total Fire Ban status prior to commencement of any work in fire hazard
areas.

Work on easements on Total Fire Ban days in fire hazard areas must be suspended, unless
otherwise specifically approved by the responsible SP AusNet officer. Before work can commence a
risk assessment and approval is to be carried out by the responsible officers.

If a Total Fire Ban day occurs prior to the declaration date for a region, priority outstanding
maintenance items, including vegetation management items, shall be managed so that they are fire
safe. Where a risk has been identified, courses of action may include fuel reduction within close
proximity of assets with outstanding urgent maintenance items or de-energisation of the assets.
CFA Restrictions for the Declared Fire Danger Period procedure requires personnel engaged in network
activities within the open air to have the necessary fire fighting equipment aboard their vehicles, vehicle
exhaust checks are performed prior to the fire season, and for compliance with fire authority requirements
for naked flames and grinding equipment.
The Bushfire Mitigation Plan addresses the treatment of private overhead electric lines with urgent
defects and network protection and control management.
Operational Plans followed in the Event of a Fire.
The BFM Manual refers to procedures that set out the process to be followed when SP AusNet personnel
or their contractors attend a fire. The fault crew is to immediately call Customer Energy and Operations
Team (CEOT) and inform them of:

any isolation required;

the size of the fire;

the requirement for the CFA/MFB to attend; and

another crew is required to assist.
The fault crew assesses the immediate public risk and isolates the fault if appropriate. The fault crew is
to remain on site until the fire is out or SP AusNet Networks or contractor personnel have relieved them.
The site is not to be left until a thorough inspection of the affected assets has been performed and the
assets confirmed as good. That is, leaving the assets permanently or temporarily repaired so that the
appropriate standards are maintained. This is to be carried out in conjunction with the CFA (or MFB if
appropriate) to ensure no poles/cross arms continue to burn.
SP AusNet had several minor fires (grass and pole top) during the Fire Danger Period 2011/12 of which
the process above was instigated and this proved to be effective. The Operations Procedures When A
Fire Occurs procedure allows for escalation should it be required associated with the size of the fire.
IJM Consulting Pty Ltd
13 of 35
SP AusNet BFM Audit Report 2012
Access under the Municipal Emergency Co-ordination Centre (MECC)
When a fire or disaster occurs and is established by a MECC Coordinator, the authorised Electrical
Operator is not to proceed into the defined Fire Disaster Zone either through road blocks or other access
routes.
Operational Plans Adopted in the Past 12 Months
SP AusNet’s fire incidents are reported through IMS and demonstrate a structured approach toward the
investigation, cause assessment, and corrective measures taken to restore supply or asset security.
Information includes fire size, damage and whether emergency services attended.
An example of the Operation Contingency Plan being implemented in the last 12 months is where SP
AusNet suppressed the auto reclose feature on the automatic circuit reclosers on days of TFB.
2.8
Protection Settings
SP AusNet’s BFM Plan describes the suppression requirements of automatic circuit reclosing devices on
days of Total Fire Ban and Code Red. The Company has a register of units to be suppressed which is
held by the Customer Energy & Operation Team (CEOT/ control room). This register is kept up to date
and is provided to ESV during the declared fire season.
Protection Settings on SWER OCR’s / Automatic Circuit Reclosers (ACR)’s for Total Fire Ban and Code
Red days
SP AusNet has established their protection settings, for the highest consequence areas, in line with the
Powerlines Bushfire Safety Taskforce recommendation 2 for Code Red and TFB days.
Area
Total Fire Ban Day
Code Red Day
Rural powerlines in the worst areas (approximately 20
per cent of rural powerlines)
Two fast protection
operations
One fast protection
operation
3. A SS ET I N SP EC T I O N
3.1
AND
M A I NT E N A NC E P R O GR A M
General
Meeting Policy Timeframes in the HBRA
SP AusNet’s Network Strategy and Development Division (NSD) have a Service Level Agreement with
Select Solutions Division that state the periods from inspection to work order completion. A priority target
is a measure of calendar days. They are:

PT1 - 1 Calendar Day

PT 7 - 7 Calendar Days

PT14 - 14 Calendar Days

PT30 - 30 Calendar Days (1 month);

PT90 - 90 Calendar Days (3 months);

PT180 - 180 Calendar Days (6 months);

PT365 - 365 Calendar Days (1 year); and

PT912 - 912 Calendar Days (2.5 years)
As at the date of the audit SP AusNet is meeting their policy timeframes in the HBRA.
th
The Company has 9,292 distribution poles in the HBRA outside the 37 month inspection cycle as at 29
October 2012 which are covered by the transition period in the ESV exemption. In addition there are
presently 27 poles on 6 private electric lines in the HBRA reported as outside the 37 month inspection
cycle due to access issues.
IJM Consulting Pty Ltd
14 of 35
SP AusNet BFM Audit Report 2012
3.2
Briefing Employees and Contractors on Policy/Procedures
SP AusNet’s policies and procedures are administered by the Health Safety Environment and Quality
Team within People and Safety. This team coordinates development, review and distribution of these
policies and procedures to employees and contractors via the SP AusNet Intranet (InSIte) or CD to
contractors. Updates to contractors may be via email between CD distributions. Notification of updates
to policies and procedures is distributed via email.
SP AusNet has several methods for the dissemination of information to employees and contractors:

Quarterly management briefings;

Safety grams;

Monthly work group meetings;

Technical bulletins;

Formal presentations (by subject matter experts);

Presentation packs
stakeholders);

Daily pre-start meetings;

Weekly newsletter (Connect);

Pride Newsletter

Quarterly magazine (Energise)
(to
be
used
by
Depot Audit Comment:
SP AusNet communicates changes to policies, procedures, and programs with its field personnel via:

Morning brief/tool box meeting(all site personnel attend)

Bimonthly Work group meeting

Email with links to Intranet item

Crew briefing weekly (Safety grams, Operational issues, Policy, procedures changes, and HR,
organisational changes, and work related feedback.

Information displayed on notice board (changed out minimum weekly & retained for personnel on
extended leave);

Regional H & S meeting;

Quarterly Employee briefings conducted by senior management;

Quality Monthly performance report; and

Quality briefing to Quarterly and bi-monthly regional management meetings.
Check of Understanding
SP AusNet employees training and competency is maintained in accordance with the requirements of the
VESI training and competency requirements. The understanding is confirmed via:

Annual refresher training of employees;

Pre start meetings to share information with work groups;

Bi Monthly work group meetings to share information;

Policy and Procedure revisions are shared with work groups;

Auditing and compliance programs;

Mission Zero conversations;

Competency Check of Understanding at end of formal training sessions; and

Questions and answers.
IJM Consulting Pty Ltd
15 of 35
SP AusNet BFM Audit Report 2012
Depot Audit Comment
Depot sites managers confirm through questions and answers involving the crew in the presentations and
safety conversations in the field during site visits. The site manager has a target of 100 safety
conversations annually to be achieved. In addition the following is part of normal field practice:

Crew Leader / Truck Leader carries out a quality check per the listing of the work completed against
scope of works;

Review of program to ensure that it incorporates the change of policy / procedure;

Continual check of job in line with the scope;

Attendance List required to be signed that personnel attended and understood information presented;

Safety conversation (which may include work method);

External audits; and

Bushfire Mitigation audits against scope of works.
HS&EQ support the field personnel by appointing external auditors to monitor the quality of the work and
compliance with HS&E:

PPE;

Public/worksite management including traffic management;

Environmental management;

Task undertaken in line with policy and procedures; and

Correction actions are then implemented should it be required.
Method used to Issue and Monitor Work.
Work packages are issued to Planners from the Maintenance Group. Work schedules are developed by
the Depot Planner (4 to 6 week work packages). Planners schedule their work to be completed by the
priority allocation and / or declaration date to ensure that the BFM index is zero from declaration date.
The maintenance activities are planned and allocated via the Q4 workbench with weekly monitoring tools.
e.g. The hit list, is used to monitor completion by due priorities.
SP AusNet is currently reviewing the enterprise asset management platform with the view of migrating
from Q4 to an alternative system with enhanced integrated capabilities.
Compliance to the Scope of Work
Compliance with scope requirements are verified by:

Work packages include the work scopes;

Maintenance manuals provide standards for work;

Details of work completed are recorded in the work package file;

Photos of work completed are included in work package file;

The work pack has the facility to highlight incomplete work.

The crew / truck leader signs off the completed job and is to the required standard

External Audits of work quality; and

Safety Conversations with work groups.
IJM Consulting Pty Ltd
16 of 35
SP AusNet BFM Audit Report 2012
3.3
Asset Inspection
The Bushfire Mitigation Plan confirms SP AusNet’s inspection standard is to ensure compliance with the
prescribed inspection interval of <37 months in the HBRA. SP AusNet achieves compliance through a
combination of two inspection cycles:

One ground based test and inspect; and

Aerial / ground inspection of above ground assets.
These two inspection programs are set to a five years interval but are offset by 2.5 years to one another
to achieve an effective inspection interval of 30 months.
Asset inspection is forecast to achieve transition exemption expiry date of 31 December 2012 for
compliance with the <37 month inspection interval for HBRA overhead electric lines.
SP AusNet has targets for Asset Inspection and progress against targets is reported to the NSMC. The
targets and actual at September 2012 is:

HBRA Inspection Target – 96% complete against a target of 99.6% (on schedule to complete prior to
31 December 2012).
SP AusNet has, in total, 9,292 distribution poles outside the 37 month inspection cycle which are covered
by the transition period in the ESV exemption. In addition there are presently 6 POEL’s with 27 poles
reported as outside the 37 month inspection cycle due to access issues.
3.4
Training Qualifications and Auditing
SP AusNet has recruited one Asset Inspector in the past 12 months who had previously successfully
completed his Certificate II in Asset Inspection while working on a different network. The Company has
overseen the training and qualification of six (6) Asset Inspectors in the past 12 months that were
recruited as Trainee Inspectors. These Trainees successfully completed the Certificate II in Asset
Inspection through the Gippsland Institute of TAFE and were deemed competent prior to commencing
work on the network.
The 6 Trainee Inspectors worked under supervision during the training period until deemed competent.
Asset Inspectors Refresher Training
All Asset Inspector refresher training is in line with both Business and VESI requirements and detailed in
the Training Matrix.
Formal refresher training

Traffic
Management
Guidance Schemes)

Working Safely in the Construction Industry
(white card)

Entry to Enclosures

Safe to Approach SWER

ESI Safety rules

Safe to Approach Distances

VESI Safety Framework

Provide First Aid in an ESI Environment

VESI Environmental Framework

Perform CPR

Manual Handling
(Traffic
Control/Traffic
Processes and Procedures to Monitor, Audit and Assess Asset Inspections
SP AusNet monitors competency of persons by audits using in-house and external independent auditors
to determine quality of work and competency of the inspector.

Whilst carrying out inspection activities on site. This includes vehicle, equipment, skills, H & S, works
practices, and compliance with asset inspection manuals;

Post inspection audits of quality and adherence to requirements of the inspection manual.
IJM Consulting Pty Ltd
17 of 35
SP AusNet BFM Audit Report 2012
Where it is identified that an Inspector’s quality of work is suffering the Inspector skill level is reviewed
and the following actions may be applicable:

Downgrade level and increase auditing;

Retrain and increase auditing;

Increase auditing;

Reinspection.
Once any of the above points have been identified the Company initiates an appropriate reinspection
program or review of work since the Inspector’s last competency audit.
ESV conducted an audit of SP AusNet’s training and competency processes in April 2012. The report is
still to be finalised by ESV.
3.5
Armour Rods & Vibration Dampers
SP AusNet’s standard for the installation of armour rods and vibration dampers has not changed from
what was originally established by the SECV. The standard is specified on drawings EVX9/7037 &
EVX9/7037/1. The application is based on tensions, length of span and type of conductor independent of
HBRA or LBRA.
In June 2012 SP AusNet issued further instructions to the field by way of a Bulletin to install armour rods
on all nominated types of conductors regardless of tension and to install vibration dampers on specified
conductors regardless of tensions with the exception of slack spans.
Program for the Installation of Armour Rods and Vibration Dampers under Agreement with ESV
SP AusNet's plan for fitting armour rods and vibration dampers was approved by ESV on 28 March 2012.
The plan is summarised in SP AusNet’s AMS - Enhanced Network Safety. Program performance is
reported to the NSMC.
Annual Installation Alignment with Agreed ESV Targets – The program has only just begun for the
installation of armour rods and vibration dampers and initially addresses spans greater than 300m in
HBRA’s. The program includes the installation of approximately 60,000 armour rod and vibration
dampers on distribution pole top structures up to 2015 and a further 188,000 sites by 2020. The program
includes a target project that begun in July 2012 and the fitting of this equipment under BAU. The
volumes being recorded are structures that are compliant as per Technical Bulletin 86-2012 and ESV
directive dated 4th January 2011.
The program agreed with ESV covering the installation of Armour rods and Vibration dampers in the
HBRA is:

December 2012 – Installed 1,300;

March 2013 – Installed 1,882;

March 2014 – Installed 18,000;

March 2015 – Installed 3,900;

December 2015 – Installed 59,645.
As at the end of September there have been 760 Vibration Dampers and Armour Rods fitted against the
December 2012 target of 1300. The Company is slightly ahead of target at the date of the audit.
The program agreed with ESV covering Armour rods and Vibration dampers in the LBRA is a further
188,000 sets to be installed between December 2015 and December 2020
Additional Items added since the Program – The plan was based on a statistically significant sample of
60,000 pole top structures identifying the application of armour rods and vibration dampers. Results of
this sample were used to estimate the armour rod / vibration damper program. On 29 May 2012 SP
AusNet submitted to ESV proposed volumes of works for the Safety Improvement program that SP
AusNet would be undertaking for each of the remaining years of the current period.
Changed from Original Targets - At this point in time SP AusNet has not identified any variances to this
program. The Company is confident they can meet the agreed program timeframes.
IJM Consulting Pty Ltd
18 of 35
SP AusNet BFM Audit Report 2012
Depot Audit Comment:
Across all worksites where access to the HV system is available the line workers are asked to fit armour
rods and vibration dampers to specifications where appropriate, irrespective to the scope of works. The
specification for Armour Rods and Vibration Dampers includes the conductor, stringing, and span length.
The installation of armour rods and vibration dampers are carried out via 2 programs. Internal resources
are fitting them in relation to existing work and a contractor has been engaged to target the installation on
a feeder basis.
3.6
Conductor
SP AusNet’s Conductor Replacement Strategy details a high level conductor replacement plan and the
Enhance Network Safety document nominates conductor replacement quantities for the period 20112015. A targeted program to replace approximately 1,771km of galvanised steel conductor and 284km of
copper conductor up to the end of the 2015/16 financial year is established.
Program for the Replacement of Conductors and Agreement with ESV
The Company have an agreement with ESV for the replacement of Copper (CU) and steel Gz/St
conductor, although ESV’s Monitoring Safety Program indicates targets of:

December 2012 – CU 72 km and Gz/St 95 km;

March 2013 – CU 72 km and Gz/St 418 km;

March 2014 – CU 165 km and Gz/St 836 km;

March 2015 – CU 235 km and Gz/St 1304 km; and

December 2015 – CU 284 km and Gz/St 1770 km.
Annual Installation Alignment with Agreed ESV Targets – SP AusNet has an agreed program with ESV
for the replacement of steel (1771km) and copper conductor (284km) by end of December 2015.
SP AusNet stated that the copper program is slightly behind schedule but will be back on target at end of
financial year.

ESV Copper Conductor Replacement Target = 52 kilometres – YTD (September) = 47 – behind
target; and

ESV Steel Conductor Replacement Target = 210 kilometres – YTD (September) = 228 – ahead of
target.
Additional Items added - The final target volumes have not changed but the yearly forecast budgets have
altered from the original AER submission due to start up and design time required. The target
modification has been agreed with ESV.
th
Changed from Original Targets - As of the 30 September 2012 all programs are forecast to meet the end
of program timelines.
Depot Audit Comment:
Field personnel are aware of the program being implemented to match the ESMS program for the
replacement of corroded steel and copper conductor. They are encouraged to report defective or
deteriorated conductor and where possible provide photographic evidence / samples. Where conductor
fails under fault conditions like for like is installed or temporary repairs are carried out.
The actual reconductoring is carried out once a design check is completed and issued as a capital project
issued.
3.7
SWER Conversion
SP AusNet augments its network in accordance with the Distribution Network Planning Guideline. This
requires an engineering approach to provide cost effective design of augmentation. Accordingly, there is
no specific policy to replace SWER with 22kV and no program/targets in place to replace or convert
SWER to 22kV.
IJM Consulting Pty Ltd
19 of 35
SP AusNet BFM Audit Report 2012
Depot Audit Comment:
Field personnel understanding of SWER conversion is:

Loading may require the splitting of a system and the installation of a second ISO or the conversion of
part of or all of the system to single or 3 phase supply.

Supply request for single or 3 phase
SWER conversion is carried out once a design is completed and project issued as a Capital project.
3.8
Crossarms
SP AusNet replaces crossarms in accordance with the Crossarm Replacement Strategy which is
summarised in the Enhanced Network Safety Strategy. LV crossarms are replaced like for like whereas
HV crossarms are replaced with steel.
Program for Replacement of Crossarms and Agreement with ESV
As part of the Enhanced Safety program SP AusNet is aiming to replace 46,785 crossarms by the end of
December 2015. This program has been agreed with ESV:

December 2012 – 19,725 Crossarms;

March 2013 – 21,225 Crossarms;

March 2014 – 30,582 Crossarms;

March 2015 – 38,939 Crossarms; and

December 2015 – 49,785 Crossarms.
In the auditor’s opinion and observations in the field this program is paramount to risk reduction of fire
starts in the HBRA and supply reliability in the LBRA
Annual Installation Alignment with Agreed ESV Targets – ESV Crossarm Replacement Target is 18,125
YTD (September) and SP AusNet has achieved 21,074 – Ahead of target
Additional Items added – There have been no additional items added since the program was established.
Changed from Original Targets - The Enhanced Network Safety crossarm replacement program is well
advanced on achieving the ESV end of year target.
Depot Audit Comment:
Crossarms are traditionally replaced due to deterioration caused by age, weather, fruiting fungal, and
beetle attack. The work is issued through the Maintenance packages with all HV arms replaced with steel
and LV with wood.
3.9
HV Fuse Replacement
SP AusNet’s HV Fuse replacement policy is detailed in their Enhance Network safety document approved
by ESV. The key focus of the EDO strategy is to:

Replace 20,314 EDO units with Boric Acid, or equivalent, in areas of high fire loss consequence
identified through the PBST fire loss consequence model by 2016;

Replace 11,246 EDO tubes in areas of high fire loss consequence identified through the PBST fire
loss consequence model by 2016;

Replace double vented EDO’s;

Replace brown and black fuse carriers;

Maintain condition based replacements (i.e. Corrosion, cracked insulators);

Replace EDO’s with BA or equivalent where fault current exceed 1,800 amps; and

Fault crews replace all EDO fuse carriers when attending EDO fuse hang-up.
IJM Consulting Pty Ltd
20 of 35
SP AusNet BFM Audit Report 2012
Program for HV Fuse Replacement and Agreement with ESV
The MV Fuse Asset Management strategy has forecast the replacement of 10,825 expulsion dropout
(EDO) fuse units by 2015/16. This program has been agreed with ESV:

December 2012 – 6,516 Fuse units;

March 2013 – 6,715 Fuse units;

March 2014 – 8,165 Fuse units;

March 2015 – 9,615 Fuse units; and

December 2015 – 10,825 Fuse units.
EDO fuse hang-ups are the predominant cause of asset fires. SP AusNet has prepared a plan to
increase the volume of EDO replacement with Boric Acid through to the end of 2015. The replacement
program is prioritised in accordance with the Fire Lose Consequence Model.
The Network Safety report fires year to date statistics shows 52 HV fuse fire starts across ground and
assets therefore this item is the major contributor of the 119 YTD fire starts recorded.
Priority for HV fuse Replacements in their BFM Program
SP AusNet has identified HV fuse units as potential sources of fire ignition. Targeted replacement
programs for high pollution areas enhance the routine replacement outlined in the MV Fuse Switch
Disconnectors strategy and summarised in the Enhanced Network Safety strategy. Monitoring of fire
incident data has indicated bird and animal flashovers to earthed EDO brackets on concrete poles
together with ‘candling’/’hang-ups’ of EDO fuse tubes as key sources of fire ignition requiring targeted
replacement with Boric Acid. The replacement program targets the highest consequence areas in
accordance with the Fire Loss Consequence Model (FLCM).
Annual Installation Alignment with Agreed ESV Targets – ESV Fuse Replacement Target is 6,523 YTD
(September) and SP AusNet has achieved 6,977 – Ahead of target
Additional Items added – At the date of the audit no additional items have been added to the original
program however agreement has been reached with ESV for additional EDO replacements which SP
AusNet are in the process of including in its program. The additional units identified are to address the
highest consequence areas in accordance with the Fire Loss Consequence Model.
Changed from Original Targets - The Enhanced Network Safety fused replacement program is well
advanced on the ESV end of year target.
Depot Audit Comment:
HV fuse units (EDO’s and powder filled) are being replaced with Boric Acid units. There was a bulk
change program carried out in 2011 where 600 units were changed out. Unit replacement is now carried
out under a scope of works as per the Asset Engineering instruction except under fault conditions.
3.10 SWER OCR/ACR Replacement
SP AusNet’s Enhanced Network Safety procedure outlines the OCR/ACR replacement policy on their
SWER network. The driver for the replacement of the existing SWER protection scheme with digital
protection and SCADA control and targeted 3 phase ACR’s is the community benefit offered through
reducing the risk of fire starts on high bushfire risk days by altering the reclose function or settings on
reclosers in HBRA’s during the fire season either at the start of each fire season or by changing it on high
fire risk days.
Program for SWER OCR/ACR Replacement and Agreement with ESV
SP AusNet has an agreed program with ESV for the replacement of 525 existing SWER OCR’s with
ACR’s by end of December 2015. This program has been agreed with ESV:

December 2012 – 120 ACR unit/controllers installed;

March 2013 – 135 ACR unit/controllers installed;

March 2014 – 250 ACR unit/controllers installed;
IJM Consulting Pty Ltd
21 of 35
SP AusNet BFM Audit Report 2012

March 2015 – 381 ACR unit/controllers installed; and

December 2015 – 525 ACR unit/controllers installed.
Annual Installation Alignment with Agreed ESV Targets – ESV SWER OCR/ACR Replacement Target is
95 YTD (September) and SP AusNet has achieved 131 – Ahead of target
Additional Items added – There has been no additional items added since the program was established.
th
Changed from Original Targets - As of the 30 September the program to date target has been exceeded
and year-end target remains on track. SP AusNet is on track meet the end of program target schedule.
Depot Audit Comment:
Field personnel are aware that SP AusNet is moving to the replacement of SWER OCR with ACR control
units in their high consequence area. These upgrades are being carried out in 2 stages with the field
crews installing and wiring and Meter and Test personnel commissioning the units.
3.11 3-Phase ACR controllers
SP AusNet’s Enhanced Network Safety procedure outlines the 3 phase ACR replacement policy in their
22kV network. Achievement of ESV Directives and PBST recommendations will be through the
replacement, upgrade of 234 ACR control boxes and replacement of 170 zone substation relays by
2015/16.
Program for 3-Phase ACR controllers and Agreement with ESV
SP AusNet has an agreed program with ESV for the replacement of 234 existing 3-Phase ACR’s by the
end of December 2015.

December 2012 – 52 Replace/upgrade of 3 phase ACR controllers;

March 2013 – 65 Replace/upgrade of 3 phase ACR controllers;

March 2014 – 114 Replace/upgrade of 3 phase ACR controllers;

March 2015 – 173 Replace/upgrade of 3 phase ACR controllers; and

December 2015 – 225 Replace/upgrade of 3 phase ACR controllers.
Annual Installation Alignment with Agreed ESV Targets – ESV Replace/upgrade of 3 phase ACR
controllers Target is 32 YTD (September) and SP AusNet has achieved 103 – Ahead of target
Additional Items added – There has been no additional items added since the program was established.
Changed from Original Targets - SP AusNet has applied for a variation to the Scope of Works of which
ESV has accepted. Although the volume remains constant the mix of activities has changed across the
program:

Modify 3ph ACR controller – 158 units;

Replace 3ph ACR controller – 39 units; and

Replace 3ph ACR - 37 units.
th
As of the 30 September the program to date target has been exceeded and year-end target remains on
track. The end of program target is scheduled to be met.
Depot Audit Comment
Field personnel are aware that SP AusNet is moving to the upgrade of 3-phase ACR’s to include auto
control in the high consequence areas. This work is being carried out with internal resources and an
additional contract with Jemena. They are not aware of the completion date for this work.
IJM Consulting Pty Ltd
22 of 35
SP AusNet BFM Audit Report 2012
4. V E GE T AT I ON M A N A G EM EN T
4.1
Vegetation Management Organisation Structure
The following management structure outlines SP AusNet’s positions responsible for the preparation,
approval, resourcing, submission and deployment of their Plan and positions responsible for carrying out
the Plan;

Group General Manager Network Strategy & Development

Director Network Engineering

Manager Networks Safety

Bushfire Mitigation Manager is responsible for developing and managing activities associated with
environmental and bushfire strategies, plans and business solutions to ensure SP AusNet meets its
safety and environmental responsibilities in delivering a safe, high performing and sustainable
electricity transmission and distribution network.

The Group Manager Utility Solutions is responsible for leading and managing the field and office
based vegetation, easement, & asset inspection management teams in developing and delivering the
distribution and transmission vegetation easement and asset inspection programs.

Vegetation & Easement Manager – Position description requested but not supplied.

Vegetation and Easements Central Area Manager Utility Services leads the group of the central V&E
group as a business operation within Utility Services to manage network assets relations obligations
for SP AusNet/Jemena and drive the growth of unregulated income.

Vegetation & Easements Area Manager – Central (Select Solutions) is responsible for leading and
managing the field and office based central vegetation and easement management team in
developing the distribution vegetation management easement programs
Depot Audit Comment:
Vegetation activities for SP AusNet are managed by Select Solutions (a division of SP AusNet).

Vegetation Program Leaders

Field Officers

Northern Region Assessment Officer (Internal) / Contracted in other 2 regions
The Company has contracted 4 service providers to cover the field cutting work across the regions.
4.2
Measures Adopted to Assess Performance
As part of its Environmental Management System, SP AusNet has developed a set of Key Performance
Indicators (KPIs), to monitor its overall environmental performances. KPI targets are set each year and
monitored and reported to Senior Management and the Board on a quarterly basis. The Bushfire
Mitigation Index is reported to and monitored by Senior Management and the Network Safety Committee
monthly. The KPIs related to vegetation bushfire mitigation aspects together with the 2012/2013 measures
and targets are detailed below;

Bushfire Mitigation Index Declaration Period - 0%

F-factor regulatory performance incentive scheme (fire incidents) < 257

Hazard tree removal program (per annum removals) - 5,000
Compliance with the Electric Line Clearance Regulation Code
The accountability for auditing of the Vegetation Management Group rests primarily with the Manager
Network Safety, Network Strategy and Development who is responsible for the regular auditing of the
Vegetation Management Group to ensure that it complies with the requirements of the VMC.
IJM Consulting Pty Ltd
23 of 35
SP AusNet BFM Audit Report 2012
This includes:

Internal audits prior to the commencement of the fire season to validate the completion of all bushfire
mitigation obligations prior to the commencement of the fire season.

As part of the Senior Management Bushfire Mitigation Review Program, reviews of all facets of the
Bushfire Mitigation Program are undertaken by managers at General Management level to validate
the efficacy of SP AusNet’s management process, program compliance, and program relevance.
These audits are undertaken during December of each year.

Audits are undertaken during the fire season to check that vegetation clearances are being
maintained.

SP AusNet’s internal auditor undertakes audits of the Bushfire Mitigation Management system.

Annual audits conducted by Energy Safe Victoria.
SP AusNet or its nominated representative conducts a sample audit of the contractor’s work (without any
limitation), procedures, and practices, in order to determine their compliance with the relevant Standards
and Codes of Practice.
The V&E group field officer/representative then undertakes a compliance audit based on but not limited to
the following criteria;
Assessment
Cutting

Correct priority coding of all spans;

Clearance achieved;

Identification of all assets;

Appropriate cutting techniques used;

Correct property owner identification;

Site tidiness;

Correct identification of voltages; and

Correct herbicide application; and

Correct identification of fire zones.

Slashing requirements met.
4.3
Vegetation Management Programs and Cycles
The Vegetation Management Company, Select Solutions inspects the clearance space in accordance
with the following cycles:

all spans are assessed at least annually in the hazardous bushfire risk area to allow for any clearing
to be undertaken to maintain compliance to the regulations; and

all spans are assessed at least biennially in the low bushfire risk area, however during the transition
period the cycle is progressively reducing to achieve a 1 year cycle.
In determining the location where work is required to maintain the clearance space one or more of the
following inspection programs are undertaken:

cyclic work programs;

pre-summer inspection in hazardous bushfire risk areas; and

reports from asset inspections.
The above are supplemented by reports from the public on areas of concern.
At each location the most appropriate method of maintaining the clearance between powerlines and
vegetation shall be determined.
Depot Audit Comment:
SP AusNet carries out annual inspection between March and August for cutting in the HBRA and have
suspended cyclic cutting. The inspection component varies from year to year depending on access.
IJM Consulting Pty Ltd
24 of 35
SP AusNet BFM Audit Report 2012
East
The company carries out cyclic slashing of easements.
st
SP AusNet has a tentative date of 31 October or declaration, whichever is sooner, for all priorities up to
365 to be completed. Where it is not possible to achieve these target dates the Company instigates a
reinspection and monitoring program until the works are completed.
South Coast
In HBRA all spans are inspected annually which is carried out by ground based inspectors.
In LBRA all spans are inspected biennially transitioning to annually. The South Coast area of SP AusNet
commenced the transition in 2012.
Cutting/Removal Cycle for Bare and Covered Conductors
If cutting and/or removal is deemed the most appropriate method then the cutting/removal cycle shall be
determined at each locality. In specific locations and from time to time the maintenance cycle may be
varied as per the following:

Rural Areas – 6 months to 3 years as appropriate; and

Urban Areas – 6 months to 2 years as appropriate.
The process used to determine the Maintenance Cycle at specific locations takes into consideration the
following factors:

Regulator clearance requirements;

Financial and budgetary constraints;

Community impacts;

Environmental and conservation issues;

Tree species & regrowth characteristics;

Line voltage & configuration; and

Area fire rating.
Areas Cyclic Cut in 2012
SP AusNet uses a Vegetation Management Program to detail the priority of the feeders to be inspected
and actioned in accordance with their procedure:

At the start of the year the LBRA program was a continuation of their existing 2 year plan with a move
to the transitional plan commencing in July 2012; and

The HBRA program has been established to show the pre-summer inspection and cutting by feeders
with the aim that all works are completed by a nominal date of 31st October.
SP AusNet’s Assessing Program is complete and the Cutting Program is on target for completion on the
th
30 November. It is anticipated that approximately 500 priority spans may remain at the end of October.
These consist of “wet spans” where Select Solutions are waiting for dryer weather to get machinery into
spans, with a small number of ESR customers to finalise. Pre-summer cutting works should be complete
prior to the November target date or the declaration of the bushfire period.
SP AusNet is on target to meet its LBRA biennial inspection and cutting program however during the
transition period the cycle is progressively reducing to achieve a 1 year cycle. A KPI report was produced
that shows 2,700 spans have been assessed against a target of 24,715 spans completion against
program. The works program is slightly behind target owing to resources being utilised on the HBRA
program due to a slight increase in find rates and wet weather.
IJM Consulting Pty Ltd
25 of 35
SP AusNet BFM Audit Report 2012
Default Times Set for Vegetation Classified as Requiring Attention
SP AusNet classifies vegetation as requiring attention as:

PT1 (55’s) - On the day of inspection vegetation has been recently contacting the conductor due to
sag or sway or environmental conditions, but is not physically in contact on the day required to be cut
or removed within 24 hours;

PT30 (56’s) - On the day of inspection vegetation is within the clearance space as defined in the
Electricity Safety (Electric Line Clearance) Regulations 2010 but is not in contact with open wire
conductors or un-insulated assets required to be cleared within 4 weeks;

PT 365 - Vegetation is outside the clearance space, but is ‘highly likely’ to encroach upon it prior the
end of the declared Fire Danger Period in the current assessment year;

RE - Vegetation is outside the clearance space however there is some uncertainty whether or not it
may encroach upon it prior to the next assessment cycle;

PT 720 - Vegetation is outside the clearance space, and will not encroach upon it between a period
commencing not less than 365 days up to a maximum of 720 days;

CC - The predominant vegetation characteristics observed throughout the span have historically not
required any action to maintain the clearance space;

PTM - Phantom Code – The PTM code shall be assigned to indicate the following:

Public Light not supplied by an overhead cable;

An abandoned line;

A POEL; or

When there is a duplicate Tree Record.
Deadlines not Achieved Prior to the Fire Danger Period
SP AusNet has a number of mature processes in place to monitor the performance of the contractor
company responsible for their operational area to ensure the Fire Danger Period deadline is always
achieved and therefore has not needed to put corrective actions in place.

Monthly contractor meetings;

Regular field inspections;

Regular Network Safety Management Committee meetings; and

Tracking via the BFM Index.
Rectification Requirements for Transitioned Spans
SP AusNet has an agreed program for the transition to compliance and this aligns with the conditions of
th
the exemption granted by ESV on 24 January 2011:

Cyclic Clearing Aerial Bundled Cable or Insulated Cable all areas – Target: 100% to be completed by
31 December 2013;

Cyclic Clearing Powerlines other than Aerial Bundled Cable or Insulated Cable LBRA – Target: 100%
to be completed by 31 December 2013;

Cyclic Clearing Powerlines other than Aerial Bundled Cable or Insulated Cable HBRA – Target: 100%
to be completed by 31 December 2013; and

Overhanging Trees – power lines other than Aerial Bundled Cable or Insulated Cable HBRA – Target
2,058 by 29 June 2015.
IJM Consulting Pty Ltd
26 of 35
SP AusNet BFM Audit Report 2012
Annual Installation Alignment with Agreed ESV Targets - SP AusNet has an established program for the
th
transition to compliance and this aligns with the conditions of the exemption granted by ESV on 24
January 2011:

Cyclic Clearing Aerial Bundled Cable or Insulated Cable all areas – Target: 31 December 2013 –
Currently 49% compliant to code against 50% - slightly behind target

Cyclic Clearing Powerlines other than Aerial Bundled Cable or Insulated Cable LBRA – Target: 31
December 2013 – Currently 51% compliant to code against 63% - behind target

Cyclic Clearing Powerlines other than Aerial Bundled Cable or Insulated Cable HBRA – Target: 30
June 2013 – Currently 94% compliant to code against 97% - slightly behind target

Overhanging Trees – power lines other than Aerial Bundled Cable or Insulated Cable HBRA – Target
2,058 by 29 June 2015 – Currently 539 spans compliant to code against 339 – ahead of target
Additional Items Added – The original targets for the transitional plan were established on a percentage of
the Network to be completed in line with schedule of dates. There has been an additional 58 included in
the program.
Changed from Original Targets – The change was due to the rezoning of LBRA boundaries with schedule
of dates. There has been no change to the original area from the agreement.
Depot Audit Comment:
Field personnel have a solid understanding of the transitional program covering open and covered
conductors in both HBRA and LBRA.
4.4
Clearance Space for Electric Lines
Program for Removal of Overhanging Vegetation in the HBRA and Agreement with ESV
SP AusNet’s Vegetation Management Plan objectives require compliance with the Electricity Safety
(Electric Line Clearance) Regulations 2010 including compliance with the transition plan agreed with
ESV.
The agreed transition plan for overhanging trees on power lines other than Aerial Bundled Cable or
Insulated Cable in the HBRA is:

31 December 2011 – 120 spans;

31 December 2012 – 219 spans;

31 December 2013 – 340 spans;

31 December 2014 – 560 spans and;

29 June 2015 – 761 spans;
st
st
st
st
th
Number of Agreed Annual Trees/Spans - SP AusNet has an established transition program for the
removal of all overhanging vegetation in the HBRA which aligns with the conditions of the exemption
th
granted by ESV on 24 January 2011. Their program is to replace 2000 spans bare LV and HV
conductors that involve 56M removal.
Changes from Original Targets - During the 3 yearly CFA reviews of the fire ratings, in certain areas some
spans that were originally LBRA and have been changed to HBRA which has caused an increase in the
number of 56Ms on the network with 58 spans being added to the program. All of these have been
picked up during this year’s cyclic assessment and have been assessed by an Arborist. This is an
ongoing issue.
Meeting Agreed Program Timeframes – The Company is confident that they can meet the agreed
program timeframes, as they are ahead of target at the date of the audit.
IJM Consulting Pty Ltd
27 of 35
SP AusNet BFM Audit Report 2012
Depot Audit Comment:
In the North and East any new overhanging vegetation found is coded as a PT30 and arrangements
made for cutting in accordance with the priority allocation. In addition, the Company is managing the 56M
database where all known overhanging vegetation is registered. The aim is to progressively reduce the
sites by either cutting or augmentation.
In Central there is a greater emphasis on alternate construction due to a number of ecological issues.
All 56M’s on the database are annually assessed by a qualified Arborist. Should the Arborist determine
that a particular 56M requires immediate action the 56M procedure is invoked and vegetation actioned
accordingly.
4.5
Hazard Trees
SP AusNet has a procedure for the management of hazard trees which requires the assessor to carry out a
visual inspection of the surrounding vegetation from the location they have positioned themself in to view the
“clearance space” to identify any obvious hazard trees. Typically these would be:

Poor anchorage/instability (ie: root uplift, severed roots;

Major stage of decline (ie: dead and dangerous limbs);

Major decay / major cavities;

Excessive imbalance towards electrical assets; and

Obvious cracks / splits in trees.

Other trees or limbs that may be unstable and could fall on the powerlines under the range of weather
conditions that can be reasonably expected to prevail in the locality
The identification of trees that could become a hazard is included in routine inspections and is recorded
on the Hazardous Tree database. This database is used to manage hazardous trees and was sighted
and used by the auditor during the field audit.
Established Program for the Removal of Hazard Trees
SP AusNet has several means by which Hazard Trees are reported:

Inspections undertaken as part of the formal hazardous tree program; and

Information obtained from councils, public, other authorities, company personnel, contractors.
st
The company has identified 12,036 Hazard trees since 1 April 2011 and actioned 7,473.
The following steps outline what actions are to take place once a hazardous tree has been identified and
reported to an Arborist for assessment:

If the assessed tree is likely to fail at any moment then the Arborist must report this to the Program
Leader for immediate action; or

If the tree is not likely to fail at any moment the Tree Assessment - Hazard Tree or 56M Span form is
to be completed and submitted (electronically) to the Program Leader.
The Program Leader prioritises works according to the hazard rating of the tree or:

Allocates work to the relevant contractor for cutting;

Allocates to an Arborist for re-assessment if the tree is not to be actioned prior to the declared
bushfire period.
The Program Leader is responsible for ensuring that random audits are conducted on a sample of
completed works and updating and maintaining the Hazard Tree Database.
Number of Outstanding Hazard Trees - SP AusNet has 4,563 outstanding trees with a rating of 2, 3 or 4
st
in the database since 1 April 2011.
The Company has made a commitment to clear 5,000 hazard trees annually (Financial year April to
March). As at end of September 2,646 trees have been cleared against a target of 2497 YTD – slightly
ahead target.
IJM Consulting Pty Ltd
28 of 35
SP AusNet BFM Audit Report 2012
Depot Audit Comment:
During the easement inspection the Assessment Officer is required to determine imminent threat from
hazard trees. The Assessment Officer prioritises the hazard tree and notifies the Program Leader of the
threat. Arrangements are then made for a specialist Arborist to conduct a detailed assessment and
recommend appropriate action.
In addition, SP AusNet runs a detailed Hazard Tree program where a Level 4 Arborist systematically
evaluates and prioritises existing Hazard trees.
4.6
Alternatives to Tree Clearing
SP AusNet has a procedure for alternative methods to be considered to avoid tree pruning consisting of
the following considerations:

Alternative methods for distribution powerlines such as re-routing or placing underground;

Alternative methods available for maintaining clearance spaces include vegetation removal,
replacement, and pruning. Vegetation is managed either by clearing or in special cases pruning
where a landowner/occupier or affected person objects to the methods proposed by the Vegetation
Management Group. The Vegetation Management Group may provide suitable replacement plants to
the affected person where clearing has taken place. In consultation with the affected person, the
Vegetation Management Group may negotiate phased vegetation replacement with compatible plants
where inappropriate vegetation has been identified along an easement;

While removal of all trees may be appropriate in some circumstances, other circumstances may
require a management plan to provide for controlled retention of compatible vegetation without
unreasonably increasing risk. Vegetation management plans provide for a layered approach, which
address a range of situations; and

Consideration of alternative methods is subject to agreement negotiated for recovery of
implementation costs.
Established Program for Alternatives to Tree Clearing
The Company has an established transition program for the removal of all overhanging vegetation in the
th
HBRA which aligns with the conditions of the exemption granted by ESV on 24 January 2011. This
program is mainly aimed at the alternative to cutting 56M’s sites.
SP AusNet is confident that they can meet the agreed program timeframes, as they are ahead of target at
the date of the audit.
Depot Audit comment:
The Vegetation Management group do not have a direct budget for relocation of lines. The field officers
are encouraged to recommend relocation where it is the most cost effective and best option to achieve
code clearances. This program is managed through the Hazard Tree Program Leader.
A specialist team in SP AusNet has been established to manage the relocations required in the central
area due to the 56M program.
4.7
Company Specific Questions
Select Solutions field officers utilise Tru Pulse Laser Rangefinders to determine span lengths and assist
in challenges to contractors work quality. The assessors do not utilise these devices for cyclic audits as it
is impractical due to the time taken to take a reading for each tree.
IJM Consulting Pty Ltd
29 of 35
SP AusNet BFM Audit Report 2012
Depot Audit Comment:
Support systems available in the depots are:

Q4 (select personnel full access allowing updating);

AM/FM;

Spatial Analysis Mapping Systems (SAMS) – Google Earth with AM/FM overlaid;

IMS (Incident management);

MAXIMO (select personnel full access allowing updating);

Workbench - Planning Tool (full access allowing updating);

OAS;

Intranet;

Intranet – available via the IPad is the construction manuals;

Mobile phones;

TMR;

Portable radios;

NEMS (Operational) (select personnel full access allowing updating); and

Field manuals (online or hard copy).
Support systems available in the Field are read only:

Smart phones;

Tablet / laptop;

Tom Tom GPS;

Hard copy field service manuals; and

TMR / portable radios.
5. F IEL D A U DI TS
5.1
A ND
D A TA B AS E V ER IF IC AT IO N
Asset Field Audit
The field audit included a detailed check of SP AusNet’s assets and vegetation at 474 sites (HBRA 329 &
LBRA 145) after downloading pole details and asset defects from the Company’s database. Asset sites
were visited with a Company representative where the information taken from the database records were
crosschecked against the actual condition of the assets in the field. Were an asset defect/anomaly
existed and was not recorded by the Company or the vegetation clearances at the site did not meet the
new Electricity Safety (Electric Line Clearance) Regulations 2010, it was noted.
The asset areas audited in the HBRA were between Seymour and Yea in the Northern Region, and
Gelliondal and Hedley in Gippsland. They were all within the 37 month inspection requirement. The
assets were in good condition and complied with the Company’s Bushfire Mitigation Plan.
The assets were in a poorer condition in the LBRA declared townships of Seymour and Leongatha than in
the HBRA. The Seymour, Yea, and Toora townships were all inspected within the 5 year inspection
period for wood poles and 10 years for concrete (under the transitional agreement). Some assets that
are showing signs of deterioration may require additional assessment before the next cyclic inspection.
In association with the 266 asset sites audited the vegetation clearances were checked which highlighted
that the vegetation clearances across network that are the responsibility of SP AusNet both LBRA and
HBRA have been cleared to Code. The line clearances for covered conductors (services), being the
responsibility of the customer, were not being cleared but in most cases they had been issued a defect
notice requesting that the work be carried out.
IJM Consulting Pty Ltd
30 of 35
SP AusNet BFM Audit Report 2012
Vegetation Line Clearance Audit
208 sites were audited covering:

134 sites in the HBRA (Northern and Gippsland Regions) inspected and cut this year as part of the
pre-summer speed cut. This audit showed that the Company was inspecting and cutting in line with
their policy and the area audited would, in the auditors opinion, remain clear of the clearance space
for the 12 month period;

33 sites in the LBRA non-declared (Yea) that were inspected and cut in 2011. This showed that
Company were achieving a two year clearance on the open mains but still need to work at clearances
on covered conductor relating to services customer responsibility. There was a vast improvement on
previous years for services where SP AusNet has the responsibility to maintain the clearance.

41 sites in the LBRA non-declared (Toora in Gippsland) that were inspected and cut in 2012. This
showed that the Company had code cleared this year to a high standard but again still needs to work
at clearances on covered conductor relating to customer responsibility services.
5.2
Results of Field Audit / Database Check
Total Sites Audited in the Field – (HBRA x 329 & LBRA x 145)
474
Defective/Missing Asset Items Not Matching Database – (HBRA x 10 & LBRA x 6)
16
Asset Audit Sites - Vegetation Spans Non Compliant with the Regulations - (HBRA x 195 +
LBRA x 71 Sites Audited) – SP AusNet’s Responsibility - (HBRA x 0 & LBRA x 2)
2
Asset Audit Sites - Vegetation Spans Non Compliant with the Regulations - (HBRA x 195 +
LBRA x 71 Sites Audited) - Other Responsible Persons - (HBRA x 2 & LBRA x 30)
32
Vegetation Spans Audit - LBRA 2011 Inspected & Cut - (33 Sites Audited)

Vegetation Spans Non Compliant with the Regulations - SP AusNet’s Responsibility (0)

Vegetation Spans Non Compliant with the Regulations - Other Responsibility (12)
12
Vegetation Spans Non Compliant with the Regulations - Following Pre-summer HBRA Cut

0
SP AusNet - (134 Sites Audited )
The Toora LBRA cut was carried out in 2012 so the results are not included above
Sites audited - Toora Township LBRA:
41

Vegetation Spans Non Compliant with the Regulations - SP AusNet’s Responsibility;
3

Vegetation Spans Non Compliant with the Regulations - Other Responsibility;
8

Trees Not Matching Database;
8
5.3
Construction Scheduling and Scope of Works
The scope of work being used by SP AusNet is issued by the Maintenance Coordinator in a work
package that includes:

Maintenance Project File Cover Sheet;

Scope of Works (Work order module) or Work Order which details all items to be addressed and
timeframes;

SAMS ViewPort Overlay which highlights the type of inspection carried out. Eg. Aerial or ground;

File feedback;
IJM Consulting Pty Ltd
31 of 35
SP AusNet BFM Audit Report 2012

JSA;

Fusing Changes;

Specific items to be addressed downloaded from Asset Inspectors program;

AM/FM printout with locations highlighted;

Application for Access permit;

Access permit schematics detailing shutdown area; and

Job File Contents Checklist.
The audit included visiting 10 Bushfire Mitigation work sites taken at random from SP AusNet’s work
schedule with the aim of confirming that the work in the field was being completed in line with the
Company’s policies, procedures, and compliance to the construction manuals. The 10 sites selected for
audit were:
Northern Region - Seymour Depot

NSMR – W2391728 Replace existing black bird covers with new barrier/glove as required by 3
paddock access – Completed as per construction manual (Photo 20) Completed;

NSMR – W2391733, Replace existing damaged 5 shed insulator with new 9 shed insulator x 2,
aluminium ties required Completed as per construction manual (Photo 21) – Completed;

NSMR – W2476002, Remove existing HV fuses and fit new boric acid fuse units and fit stand off
insulators, fully insulated leads, new surge diverters to tank, Raychem caps to surge diverters,
bushings and fit HV covers covering to surge diverter leads - Completed as per construction manual
(Photo 18) – Completed;

NSMR – W2417933, Surge diverter remove 3 x unacceptable - Completed as per construction
manual (Photo 23) – Completed;

NSMR – W23301159, Replace existing HV inter xarm with new LW20 xarm and fit 3 x 9 shed
insulators - Completed as per construction manual (Photo 19) – Completed;
Gippsland region - Leongatha Depot

LGA023-1-HP–LEO154SSR, LGA014A9 - LEO330MIN, Replace HV24 with LS22 Ampact Bail’s 6K
B/A units, fit vibration dampers, fit L/A’s to Pole, fit Raychem & Stringer covering. Replace wrap on D
loops with Ampact Bail’s , fit vibration dampers (Photo 34) – Completed;

LGA011H9 – LEO150HVX - LEO330MIN, Replace rusty broken tie, fit vibration dampers, fit pole cap,
fit 2 L/A’s to Tx, fit Raychem & stinger(Photos 25, 26,27,& 28) – Completed;

LGA001G22 – LEO330MIN, Fit L/A’s to pole, fit vibration dampers, fit Pole Cap (Photo 31 &32)
Completed;

LGA001G22 – LEO330MIN, Fit disc cover to 5 shed insulator, re tie broken tie & remove, blown L/A
(Photo 29 & 30) - Completed;

LGA023-OUTTRIM – Replace Poles, Replace Pole, Fit vibration dampers, 3 ph inter s/stn, ampact
Bail’s, vibration dampers (Photo 33) – Completed;
All work was completed in line with the work scopes which aligned to with the Company’s policies, and
procedures.
IJM Consulting Pty Ltd
32 of 35
SP AusNet BFM Audit Report 2012
Depot Audit Comment
Select Solutions issues the work package to the Planner who determines the delivery dates, manpower,
and equipment, which is then issued to a crew or truck leader who then refines the work scope to suit the
environment and reality of making it work in the field. Once finalized it is included in the daily work sheet
and issued at the job start meeting.
The Work Site Leader has the authority and responsibility to review the job for conformance against the
construction manual and scope of work prior to energisation. On completion the Maintenance package is
returned to the Scheduler to confirm that the work has been carried out. The Scheduler has the
responsibility to arrange for approximately 5% of the maintenance packages to be audited through an
external auditing company.
The Site Manager monitors the weekly program and reports to the Delivery Manager / Regional Manager
/ Works Coordinator on the delivery across the region on planned verses actual.
Should any activity be missed the Planner reschedules the work to match the delivery date.
To confirm the quality of work SP AusNet uses a Quality of Work Audit checklist of which the Work Site
Leader or his delegate is obliged to confirm each item has been completed prior to closing out the job.
Any items that are not fully completed are noted in the File Feedback sheet.
6. O B S ER V AT IO N S
There are 6 general and 15 field audit Company specific observations made during the audit relating to
SP AusNet’s Bushfire Mitigation Program:

The Bushfire Mitigation Committee has been replaced by the Network Safety Management
Committee which provides a holistic approach to network safety and maintenance management
across the electrical Transmission, Distribution, and Gas business. The Company sees a direct
alignment of Bushfire Mitigation and Network Safety;

The Network Safety report is new (Introduced in March 2012) and is a comprehensive document
providing an excellent means of monthly snapshots across all programs of the business;

The change of focus on Network Safety has changed the way SP AusNet is managing their bushfire
risk across the Network. There is a greater focus on removal of risk for deteriorating assets;

It was a refreshing change to audit the Company when dealing with personnel who have the
knowledge, experience and attitude to drive change across the network Bushfire Mitigation and
maintenance programs;

Across most of the Network safety programs where targets are agreed with ESV, SP AusNet is
achieving the target or delivering results greater than agreed;

The Network Safety report for the year to date statistics shows 52 HV fuse fire starts across ground
and assets therefore this item is the major contributor of the 119 YTD fire starts recorded. In the
Auditors opinion the program should be escalated and the completion date bought forward to match
the risk profile of this item;

In the Auditor’s opinion and observations in the field showed crossarm replacement program currently
in progress is paramount to the Company’s risk reduction of fire starts in the HBRA and supply
reliability in the LBRA;

The Company is issuing defect notices to the customers for services that were in breach of the Code
but there is no follow-up action being carried out and it appears that in most cases the customer is not
complying with the notices;

SP AusNet is removing black bird covers as they have proven to be unreliable with birds nesting in
them;

There is definite evidence in the audited areas that the annual cut is being carried out with line
clearances achieved that would remain clear for the next 12 months in the HBRA;
IJM Consulting Pty Ltd
33 of 35
SP AusNet BFM Audit Report 2012

In the majority of cases where the Asset Inspector noted a wooden crossarm to be monitored (P9 or
P10) in the HBRA the Auditor did not agree and would have allocated a priority that would have
required the crossarm to be replaced;

In the opinion of the auditor a 5 year LBRA inspection period is too long for an accurate life
assessment for wooden crossarms. The inspectors need to take a more conservative approach
when allocating priorities;

A high percentage of wooden crossarms in the LBRA are in poor condition and are likely to be a
major workload for the near future;

The asset database was accurate with only minor differences occurring due to the lag in updating
items that have been completed in the field;

Assets within the HBRA areas audited were in a reasonable condition to enter the fire danger period;

After auditing the Northern and Gippsland regions the focus for future maintenance needs to be on
Gippsland as the assets are not to the same standard as the North Region;

The vegetation database information provided can be difficult to interpret due to poor area location
descriptions in both the HBRA and LBRA;

The Company is not able to achieve clearances on other responsible persons covered conductors
(services) but are clearing services that are their responsibility;

In some cases service vegetation line clearance (SP AusNet responsibility) is not being cut hard
enough to achieve 12 month Code clearance and the Company may need to return during the 12
month period;

In the LBRA the mains clearances achieved in the 2011 cut were to an extent to ensure clearance
remains for the 2 year inspection period;

Leongatha is a declared area but the Leongatha Council is not carrying out its responsibility to
maintain Code clearance.
7. C O NC L U SI O N S
SP AusNet’s Bushfire Mitigation Management personnel were well prepared and co-operative during the
audit and provided information that clearly demonstrates their bushfire mitigation preparedness for the
forthcoming fire danger period. The Bushfire Mitigation Plan was reviewed and rewritten this year and
provides a fresh approach to an established document. The Vegetation Management Plan is a well
prepared document that is easy to follow. These two documents form the basis of the Company’s BFM
activities and are supported by a comprehensive set of mature policies, strategies, and procedures.
The Company has established and gained agreement with ESV for a transitional period with established
target dates and clearance percentages to comply with the Electricity Safety (Electric Line Clearance)
Regulations 2010. These arrangements provide for full compliance by June 2015. During the transitional
period they are therefore operating outside the new/changed obligations imposed under the 2010
Regulations.
In addition the Company has established programs to meet agreed timeframes for the items covered
under ESV directives. They are, at the time of the audit, in the majority ahead or on target across the
range of activities being undertaken.
The depot audits demonstrated that SP AusNet is disseminating their policies, procedures, and
maintenance programs to their employees and contractors and that employees and contractors have an
understanding of the Bushfire Mitigation program targets and timeframes that must achieved. The
Company has processes in place to confirm understanding and monitor the Company’s obligations to
meet agreed timeframes and targets.
There were ten bushfire mitigation project scopes of works chosen at random from the Company’s
September/October work schedule. All work had been completed in line with the scope of works and to
required standard laid down in the construction manual, policies, and procedures. There are sites across
the network where access is still an issue.
IJM Consulting Pty Ltd
34 of 35
SP AusNet BFM Audit Report 2012
The field audit highlighted that the Company’s assets and vegetation line clearances in the HBRA were in
good condition however asset maintenance and vegetation clearances on service conductors in the
LBRA were not to the same standard.
SP AusNet is targeting all their Bushfire Mitigation work to be completed by 30 November 2012 and they
consider they are on target to achieve this aim. The Company is confident they have the programs and
resources in place to complete their Bushfire Mitigation commitments before the start of the Fire Danger
Period and are well positioned to maintain a zero index throughout the period.
In the Auditor’s opinion after auditing SP AusNet’s programs and checking the condition of assets in the
field that they are is in a position to achieve their bushfire preparedness in line with their Bushfire
Mitigation and Vegetation Management Plans, and should be fire safe prior to the progressive
introduction of the 2012/13 fire danger period.
8. R EC OM ME N D A TI O NS
It is recommended that:

SP AusNet escalate the fuse replacement program to reduce their fire start risk;

SP AusNet conduct a closer inspection of all items found during the field audit and arrange corrective
action; and

SP AusNet implements a follow-up procedure for service clearances where customers have been
given a defect notice and not carried out the line clearance work required to maintain code
clearances.
th
Auditor’s Signature:
Date: 25 November 2012
Ian J McDonald
IJM Consulting Pty Ltd
35 of 35
AusNet Services BFM Line Clearance Audit Report 2014
Table of Contents
1.
Audit Scope, Objective and Criteria ............................................................................................... 2
2.
Audit Methodology .......................................................................................................................... 2
2.1
HBRA Sites Audit ....................................................................................................................... 3
2.2
LBRA Sites Audit ........................................................................................................................ 3
3.
Summary of Identified Compliance Matters ................................................................................... 4
3.1
High Bushfire Risk Area - MJG11 (Merrijig) ............................................................................... 4
3.2
High Bushfire Risk Area - Murrindindi (MDI1) ............................................................................ 4
3.3
High& Low Bushfire Risk Area - Kalkallo (KLO24) .................................................................... 4
3.4
High & Low Bushfire Risk Area - Eltham (ELM15) .................................................................... 5
3.5
High & Low Bushfire Risk Area - Belgrave (BGE11) ................................................................. 5
3.6
High Bushfire Risk Area - Woori Yallock (WYK11) .................................................................... 6
4.
General Observations .................................................................................................................... 6
5.
Database ........................................................................................................................................ 7
6.
Conclusion ...................................................................................................................................... 8
7.
Recommendations.......................................................................................................................... 9
8.
Attachment – Database Line Clearance Field Audit 2014 – AusNet Services............................. 10
9.
Attachment – Photos Line Clearance Field Audit 2014 – AusNet Services ................................. 11
IJM Consulting Pty Ltd
Page 1 of 11
AusNet Services BFM Line Clearance Audit Report 2014
1.
Audit Scope, Objective and Criteria
The audit was conducted on AusNet Services (AS) in accordance with the agreement with Energy
Safe Victoria (ESV) Bushfire Mitigation Audits July 2014 Scope of Works and Briefing Notes for
Electric line Clearance Auditing presented to IJM Consulting on the 14 August 2014.
The Electricity Safety Regulations and other subordinate legislation, the Company’s Electric Line
Clearance (Vegetation) Management Plan and vegetation database were used as the base reference
documents to outline the Company’s standard of performance, and activities undertaken to comply
with the intent of the Regulations.
AusNet Services was given approximately 3 weeks’ notice on the aspects of the audit to be
undertaken.
The audit was conducted taking into account the following:

The pre fire season Electric Line Clearance (ELC) readiness and the compliance to the
transitioned spans cleared;

That it was carried out late in the preparation to this years fire danger period, and it was carried
out concurrently with ESV’s Asset and Safety Program Audits and while the Company was still
progressing with their pre-summer cutting;

That for statistical certainty quantities of sites audited must generally equal or exceed 400 spans;

That the same approach is to be utilised for each of the five Companies; and

That ESV provides the listing of sites/electric line/s to be audited to ensure an appropriate crosssection is achieved.
The auditor is to confirm:

That the Electricity Company is programming the inspections in accordance with their
process/procedures for vegetation inspections;

That the inspections are conducted in accordance with their process/procedures for vegetation
inspections;

That the findings and cutting directions noted in the inspection data are correct;

That the Company is achieving Electric Line Clearance (ELC) compliance; and

That the notification process has been compliant.
2.
Audit Methodology
th
th
The audit was conducted between 20 November and 24 November 2014, which included a detailed
assessment of the vegetation line clearance in the field. Prior to the audit AusNet Services Contract
Management, Select Solutions, provided an electronic copy of their vegetation database with the
selected feeders to be audited as well as an iPad with AusNet Services asset locations. A full listing
of the audited sites is provided in this report as attachment A.
This Bushfire Mitigation Line Clearance audit sampled sites on 6 feeders in the HBRA and 3 in the
LBRA covering both declared and non-declared areas within AusNet Services operational area, which
required a total of 1330Kms driven to achieve the aims of the audit.
IJM Consulting Pty Ltd
Page 2 of 11
AusNet Services BFM Line Clearance Audit Report 2014
A larger audit sample was taken than the minimum required by the audit scope to enable the Auditor
to make a determination on the standard of clearance work being achieved across the HBRA (High
Bushfire Risk Areas) of the network. The level of the Company's compliance was determined from the
selection;
2.1
HBRA Sites Audit
The auditor received HBRA data for 500 sites that represented inspected spans, spans cleared or
spans yet to be cleared and the auditor was requested by ESV to audit a minimum of 350 of these
spans.
Feeder
Sites Audited
HBRA
Additional
HBRA sites
Audited
MJG11
Merrijig
73
3
MDI11
Murrindindi
81
KLO24
Kalkallo
55
ELM15
Eltham
57
1
BGE11
Belgrave
51
2
WYK11
Woori Yallock
53
Area
There were a total of 374 spans audited in the HBRA. The 6 additional HBRA sites audited were
locations where assets defect were sighted during the audit.
2.2
LBRA Sites Audit
The auditor received the LBRA data for 120 sites that represented inspected spans, spans cleared or
spans yet to be cleared and was requested by ESV to audit a minimum of 50 of these spans.
Area
Feeder
Sites Audited
LBRA
Additional
LBRA sites
Audited
KLO24
Kalkallo
37
0
ELM15
Eltham
27
1
BGE11
Belgrave
32
1
There were a total of 98 spans audited in the LBRA including the 2 additional LBRA sites audited
where locations were defect assets were sighted during the audit.
The level of the Company’s compliance has been determined from these selections.
IJM Consulting Pty Ltd
Page 3 of 11
AusNet Services BFM Line Clearance Audit Report 2014
3.
Summary of Identified Compliance Matters
3.1
High Bushfire Risk Area - MJG11 (Merrijig)
76 locations were audited within AusNet Services HBRA (MJG11) and of these sites 8% had some
form of non-conforming asset defect or vegetation clearance:

Of the 76 locations audited 5% (4 non-conforming sites) related to asset defects (AusNet Services
responsibility to correct);

Of the 76 locations audited 7% (5 non-conforming sites) related to vegetation line clearances
(AusNet Services responsibility to clear); and

Of the 76 poles audited in the HBRA 1% of services audited (Customer responsibility) were nonconforming.
The mains in the Merrijig are code compliant but allowance for regrowth is marginal however you
could identify the areas that have been cut this year and at these sites good clearances were
achieved. There are a number of sites where the auditor identified hazard trees that should be
removed as they are close to the edge of the bank above the Mt Buller line and in some cases the
bank has started to collapse.
Note: The asset defects identified were close to audited sites or at an audited site. The priority
allocated was determined from viewing the item from the ground using binoculars.
3.2
High Bushfire Risk Area - Murrindindi (MDI1)
81 locations were audited within AusNet Services HBRA (MDI1) and of these sites 1% had some form
of non-conforming asset defect or vegetation clearance:

Of the 81 locations audited no non-conforming sites relating to asset defects were found (AusNet
Services responsibility to correct);

Of the 81 locations audited 1% (1 non-conforming site) related to vegetation line clearance
(AusNet Services responsibility to clear); and

Of the 81 poles audited no services were found that were non-conforming (Customer
responsibility).
There was one site that will require cutting before the commencement of the fire danger period
however the mains in the Murrindindi have good clearances and are code compliant with adequate
allowance to cover for regrowth until the next pre-summer inspection and cut.
The auditor viewed the asset conditions at each of the audited sites and did not identify any asset that
required attention before the commencement of fire danger period.
3.3
High& Low Bushfire Risk Area - Kalkallo (KLO24)
There were 92 locations audited within AusNet Services HBRA & LBRA (KLO24) and of these sites
17% had some form of non-conforming asset defect or vegetation line clearance issue:

Of the 92 locations audited 1% (1 non-conforming sites in the HBRA) related to asset defects
(AusNet Services responsibility to correct);

Of the 92 locations audited no non-conforming sites in the HBRA related to vegetation line
clearance (AusNet Services responsibility to clear);

Of the 92 locations audited 4% (4 non-conforming sites in the LBRA) related to vegetation line
clearance (AusNet Services responsibility to clear); and
IJM Consulting Pty Ltd
Page 4 of 11
AusNet Services BFM Line Clearance Audit Report 2014

Of the 92 poles audited 13% (12 Non-Conforming sites in the LBRA) of services audited
(Customer responsibility) were non-conforming.
The HBRA & LBRA mains in the Kalkallo area are code compliant but services still remain an issue in
the LBRA. There was evidence that work was being carried out on service clearances that are the
responsibility of AusNet Services to cut in the HBRA.
3.4
High & Low Bushfire Risk Area - Eltham (ELM15)
There were 86 locations audited within AusNet Services HBRA & LBRA (ELM15) and of these sites
13% had some form of non-conforming asset defect or vegetation clearance issue:

Of the 86 locations audited 3% (2 non-conforming sites in the HBRA & LBRA) related to asset
defects (AusNet Services responsibility to correct);

Of the 86 locations audited in the HBRA no non-conforming sites were found relating to
vegetation line clearance (AusNet Services responsibility to clear);

Of the 86 locations audited 6% (5 non-conforming sites in the HBRA) related to vegetation line
clearance (Customer responsibility to clear);

Of the 86 locations audited 5% (4 non-conforming sites in the LBRA) related to vegetation line
clearance (AusNet Services responsibility to clear); and

Of the 86 locations audited 2% (2 Non-Conforming sites in the LBRA) related to services
(Customer responsibility to clear).
Although there were no vegetation line clearance non-conformance sites found in the HBRA (AusNet
Services responsibility), there is minimal clearance on services and mains in the Eltham, Research,
Hurstbridge etc. area.
In the auditors opinion the fire danger rating for Howell Rd Plenty is incorrectly classified as LBRA. It
is a heavily vegetation area with limited access and with high ground fuel content.
Note: The level of priority allocated to asset defects was assigned without the benefit of an aerial view
to determine the remaining life of the item.
3.5
High & Low Bushfire Risk Area - Belgrave (BGE11)
There were 84 locations audited within AusNet Services HBRA & LBRA (BGE11) and of these sites
44% had some form of non-conforming asset defect or vegetation clearance issue:

Of the 84 locations audited 4% (3 non-conforming site in the HBRA) related to an asset defect
(AusNet Services responsibility);

Of the 84 locations audited 2% (2 non-conforming sites in the HBRA) related to vegetation line
clearance (AusNet Services responsibility to clear);

Of the 84 locations audited 21% (18 non-conforming sites in the HBRA) related to vegetation line
clearance (Customer responsibility to clear);

Of the 84 locations audited 1% (1 non-conforming sites in the LBRA) related to asset defects
(AusNet Services responsibility to correct);

Of the 84 locations audited 6% (5 non-conforming sites in the LBRA) related to vegetation line
clearance (AusNet Services responsibility to clear); and

Of the 84 Locations audited 10% (8 Non-Conforming sites in the LBRA) related to services (Other
Person responsibility to clear).
The audit identified 2 sites where overhanging vegetation was present. These were not shown in the
database provided as transitional spans;
IJM Consulting Pty Ltd
Page 5 of 11
AusNet Services BFM Line Clearance Audit Report 2014
Note: There were 4 (P1) assets defects identified that will have to be addressed before the
commencement of the Fire Danger Period.
3.6
High Bushfire Risk Area - Woori Yallock (WYK11)
There were 53 locations audited within AusNet Services HBRA (WYK11) and of these sites 26% had
some form of non-conforming asset defect or vegetation clearance issue;

Of the 53 locations audited 2% (1 non-conforming site in the HBRA) related to an asset defect
(AusNet Services responsibility);

Of the 53 locations audited 6% (3 non-conforming sites in the HBRA) related to vegetation line
clearance (AusNet Services responsibility to clear); and

Of the 53 locations audited 21% (11 non-conforming sites in the HBRA) related to vegetation line
clearance (Customer responsibility to clear).
It appeared to the auditor that the AusNet Services were in the process of completing their
presummer clearing in this area.
The data information supplied by Select Solutions / ESV for this area cannot not relied upon other
than the Camm No., and any Comments that have been included from the Auditor.
Note: There was 1 (P1) assets defect identified that will have to be addressed before the
commencement of the Fire Danger Period.
4.
General Observations
Although the audit was conducted during the AusNet Services preparation for the 2014/2015 Fire
Danger Period the vegetation line clearances in the HBRA where generally in good condition where
they had completed all pre-season work:

There is evidence that work has been carried out this season and contractors are accomplishing
good work maintaining the easements in the HBRA;

Select Solutions was still working on Woori Yallock - WYK11 feeder as that was the final area of
work to be completed prior to the commencement of Fire Danger Period;

There were considerable distances covered between audit sites and although the auditor never
stopped at sites that were not allocated for auditing (within the database provided), particular
attention was given to the general line clearances. It confirmed consistent code clearances were
being achieved throughout the HBRA and the LBRA where it is AusNet Services responsibility to
clear;

There were exceptions with 56m clearances (within the HBRA) as several sites were identified but
not shown on the database and were in reality above the line or within the 56M clearance space.

Where cutting had been carried out on hedgerows (farm wind breaks) throughout the HBRA’s
audited excellent clearances had been achieved. The result was neat and well formed;

The auditor photographed the non-compliant sites that were Code 55 (vegetation in contact with
the conductors) and Code 56 (vegetation within the clearance space). All LV service nonconformances were only noted;
IJM Consulting Pty Ltd
Page 6 of 11
AusNet Services BFM Line Clearance Audit Report 2014

Non-conforming Services (vegetation) that are the responsibility of the customer to cut remain an
issue, as the process being used by AusNet Services to address this item is only producing
results in some areas. The auditor confirmed with a number of customers that notices had been
issued.

The iPad provided with AusNet Services Asset locations installed was extremely accurate and
very easy to use. It is a exceptionally good tool for this type of audit.

Where 56M (overhanging vegetation) was not registered and determined by the auditor to be
within the clearance space it is shown as a non-conforming site. There were no transitional sites
shown in the data supplied to the auditor;

The Auditor witnessed several tree clearing parties working on pre-summer clearing throughout
AusNet Services operational area. Cutting had been completed with good clearances achieved
although clean-up of vegetation remained;

The Auditor made it a point to talk to the property owner at every opportunity and they confirmed
notification was being given for vegetation clearance work on their property. However there were
several property owners that were not happy with the lack of negotiation and wanted a say on
what was to be done. In most cases it was that they would have preferred the tree removed
instead of taking the side out of it and leaving it, in their view, unsafe and ugly;

There is a distinct difference in the standard of cutting clearance between the HBRA and LBRA
(AusNet Services responsibility) on mains as the allowance for regrowth was marginal in the
LBRA;

The issue of notices and follow-up on customers’ services needs to be strongly enforced if
regulated clearances are to be realised.
Note: Although this segment of the ESV Bushfire Mitigation 2014/15 was aimed at line clearance the
Auditor did have a general look at the assets in the HBRA at each site and considered they were
generally in a good serviceable condition.
5.
Database
The iPad provided with AusNet Services asset locations installed was extremely accurate and very
easy to use. Unfortunately there was one tab in the electronic vegetation database program (Woori
Yallock - WYK11) where addresses/information did not marry up. Where the address was incorrect
the majority of sites were updated by the auditor to assist with any follow-up work that maybe
required;
Any asset defect found was photographed so the Auditor could make a determination on a priority
allocation. All other non-conformances were only noted;
The auditor noted Code 55 services (vegetation in contact) but did not record Code 56 services
(vegetation within the clearance space), as it would have involved recording most services where
vegetation existed throughout the areas audited.
IJM Consulting Pty Ltd
Page 7 of 11
AusNet Services BFM Line Clearance Audit Report 2014
6.
Conclusion
The specific objective of this audit was to determine whether or not AusNet Services is satisfactorily
complying with the requirements of the Electricity Safety (Electric Line Clearance) Regulations 2010
S.R. No 47/2010, in particular with respect to inspection, vegetation clearances achieved and the
ability of the electricity Company to complete all outstanding works prior to the commencement of the
fire danger period.
As part of this Electric Line Clearance audit, AusNet services vegetation management (Select
Solutions), provided ESV with an extensive electronic database covering the 6 feeders chosen by
ESV to be audited. This was used as the base document to demonstrate the status at the chosen
sites and the Company’s intention for any future work.
The Auditor requested confirmation from AusNet Services that they intend to complete the prest
summer clearing by 1 December 2014 or prior to the declaration of the Fire Danger Period
(estimated to be late December) but no reply was received. From the sites audited in the HBRA
indications are that AusNet Services is nearing the end of their pre-summer cut and is achieving the
regulatory requirements with good allowance for regrowth however the sample audited in the LBRA
and LBRA Declared was not to the same standard as the spans were either marginally cleared, or
require further work.
AusNet Services is achieving and maintaining clearance to the mains where it is responsibility. The
clearances are in line with a 3-year cyclic cut.
The accuracy of Select Solutions’ vegetation database for the HBRA is well maintained in relation to
the description of the network assets and the clearances that exist in the field. It is also clear what
spans have been inspected, cut and the work remaining to be completed. With the asset locations
loaded onto the IPad along with the Camm Number supplied from the electronic database copy it
allowed the auditor to easily find sites to be audited.
Services that were the responsibility of AusNet Services to clear were, in general, completed although
with minimal clearances being achieved. You could establish that the vegetation had been cut back
but it was not cut hard enough to maintain a 3-year code clearance. Limited work had been carried to
clear services that were the responsibility of ORP’s although from discussion with property occupiers
they stated that they have received notices to clear.
In the Auditor’s opinion AusNet Services vegetation preparedness for the forthcoming fire season is in
line with their Electric Line Clearance Management Plans. The audit was carried out in the final
stages of the lead up to the Fire Danger Period and the areas audited indicated that AusNet Services
is well advanced with their pre-summer preparedness in the HBRA with good clearances being
achieved. If the areas audited are representative of all AusNet Services operational area then they
are in a good position for the commencement of the fire danger period.
IJM Consulting Pty Ltd
Page 8 of 11
AusNet Services BFM Line Clearance Audit Report 2014
7.
Recommendations
It is recommended that:

AusNet Services review the comments and notes contained in the attached audit result sheets
and action the points raised by the Auditor, where appropriate;

AusNet Services place more rigor in their program to achieve service clearances within their
operational area;

AusNet Services ensure their Vegetation Field Officers are taking into consideration the clearance
space required for 56M / overhanging sites;

AusNet Services consider reviewing their LV spreader policy as there are indications that the clips
are starting to fail.
Auditor’s Signature:
Ian J McDonald
th
Date: 25 October 2014
Ian J McDonald
IJM Consulting Pty Ltd
Page 9 of 11
AusNet Services BFM Line Clearance Audit Report 2014
8.
Attachment – Database Line Clearance Field Audit 2014 – AusNet Services
IJM Consulting Pty Ltd
Page 10 of 11
AusNet Services BFM Line Clearance Audit Report 2014
9.
Attachment – Photos Line Clearance Field Audit 2014 – AusNet Services
IJM Consulting Pty Ltd
Page 11 of 11
Download