Proceedings of the 14th International Middle East Power Systems Conference (MEPCON’10), Cairo University, Egypt, December 19-21, 2010, Paper ID 151. . Steady-state and transient analyses of wind farm connected to an electric grid with varying stiffness Mazen Abdel-Salam*, Adel Ahmed, and Mahmoud Mahrous Electric Engineering Department, Assiut University, Assiut, Egypt * Corresponding author: mazen2000as@yahoo.com requirements for the connection of wind farms to electrical network are defined by the new connection code [2]. Abstract- This paper is aimed at investigating the steady state and transient analysis behaviour of a squirrel cage induction generator of wind farm connected to a variable stiffness grid using MATLAB/SIMULINK. Different types of faults including three-phase-to-ground, double-line-toground, line-line and single-line-to-ground are studied. The calculated temporal variations of speed, voltage, active power and reactive power of the generator agreed reasonably with those obtained using PSCAD for threephase and single-line-to-ground faults. The three-phase-toground is the most severe fault as expressed by the time required for the voltage to recover to its pre-fault value and the maximum current drawn by the faulted bus. The analysis of a configuration consisting wind farm based on conventional fixed speed induction generator has been reported before [3] using EMTDC/PSCAD digital simulator. It was reported that the transient stability conditions of generator was increased and the short-term voltage and rotor stability performance were improved for three-phase to ground and single-phase to ground faults because of the use of STATCOM as an active voltage/var supporter. This paper is aimed at investigating the effect of the short circuit ratio (SCR) on the steady- state and transient performance (symmetrical and unsymmetrical faults) of the same wind farm whose details are reported before [3]. The well known software package MATLAB/SIMULINK was used. This makes it possible to compare between the MATLAB simulator and the PSCAD simulator for three-phase to ground fault and single-line to ground fault for a strong (stiff) grid of SCR =16. Other faults including line-to-line and double line to ground faults are also investigated using MATLAB/SIMULINK package. Keywords: Wind energy; Fixed speed wind turbine; Induction generator; Short circuit ratio (SCR). I. INTRODUCTION Wind turbine technology has undergone a dramatic transformation during the last 15 years, developing from a fringe science in the 1970s to the wind turbines of the 2000s utilizing the latest technology in power electronics, aerodynamics and mechanical drive train designs. Induction generators are more attractive than synchronous generators for wind turbines due to their robust construction, low cost, low maintenance, long life (more than 50 years) and low power to weight ratio [1]. However the reactive power management is a major concern, not only to compensate for the reactive power requirements of the wind generator itself but also to support the system voltage in particular for wind farms based on fixed speed induction generators. II. NETWORK There are a number of possible interconnection structures for wind farms and thus it is not possible to cover every type of network configuration, load, and interconnection point of the wind farm. Frequently wind parks are connected to weak systems, as they are typically located far from major load centers and central generation. This reflects itself in the short circuit ratio (SCR) of the interconnection, given by: In the past, there was no requirement by the grid code for a wind farm to remain connected to the grid during a fault or a voltage disturbance. The protection of the wind farms has mainly been focused on turbine protection without considering the impact it might have on the power system. This implies that the wind turbine is disconnected from the grid as soon as a violation of voltage or frequency operating limits is exceeded. SCR = SCC Sbase (1) Where S base is the rated power of wind farm and SCC or short circuit capacity is the short circuit power delivered from the grid for a three-phase fault at the wind park: However, increasing wind power penetration means that wind power plants have to behave more like conventional power plants and hence have to take over many of the control tasks that hold the power system stable. The 2 Vbase SCC = Z line 203 (2) When the short circuit fault is cleared, the electrical torque has to be re-established and has to be larger than the mechanical torque for decelerating the generator to its original speed. However, the dependence of the terminal voltage influences the behavior of the generator after the fault as well. When the fault is cleared, the terminal voltage Vs is a decreasing function of the generator speed where Z line is the impedance of the line connecting the grid with wind farm and Vbase is the rated voltage of the grid. For weak systems the SCR will usually be less than 6 [4].The wind generator system have matched capacities in terms of real and reactive power, whereby reactive power is supplied from the generator itself and from the STATCOM for the fixed speed machines [4]. and stator current, resulting that, in a weak connected grid system, the electrical torque may not exceed the mechanical torque, the over speeding may continue and generator runs away. Hence, the behavior of the induction generator depends also on the value of short circuit impedance viewed from the generator terminal into the electric power grid [3]. III. THE STABILITY OF INDUCTION GENERATORS The dynamic stability of induction generators connected to a grid depends on the characteristic of the generator, the grid configuration and the characteristic of the disturbance. IV. SYSTEM UNDER STUDY The over speed of the induction generator resulted from a transient short circuit in the electrical power system can exceed the stability limit resulting in collapse of the system. The one line diagram of the test system employed in this study is shown in Fig. 1. The wind farm consists of 75 units of 1.6 MVA wind turbines. Each of these wind turbine units consists of rotor, gear box, squirrel-cage induction generator, shunt capacitors for the reactive power compensation of the generator (connected to the 0.69 kV network) and a 0.69/10.5 kV transformer. The representation of the power plant has been made by aggregating all wind turbines in one coherent lumped equivalent model. Assuming generator operating condition, the generator will accelerate during fault in the power system according to the following movement equation 2H dω (t ) = Tmech − Telec dt (3) The wind farm includes a power station transformer, rated to 10.5/115 kV, 150 MVA. The large wind farm is connected to a 115-kV line, which is then connected to the electric grid. The short circuit power of this grid is dependent on the SCR. The reactive power required for the wind farm is 44 MVAr, being fed by both the fixed capacitor (34 MVAr) installed at bus # 1 as well as the grid itself. The reactive power required for the transmission line and transformers is 11 MVAr being fed by the grid. For weak grids, a 21 MVAr switched capacitor is connected at bus # 4 to cover the deficiency of the generated reactive power. The wind turbine induction generator (WTIG) model is used in phasor model [5]. All the relevant data are given in appendix. Where H = the inertia constant, ω = the angular speed of generator, Tmech = the mechanical torque of generator and Telec = the electrical torque of generator. During the failure event in the power system the mechanical torque Tmech is practically unchanged; on the other hand the electrical torque will be reduced since the electrical torque is proportional to the square of terminal voltage ( Telec ∝ Vs2 ) (where the voltage Vs , the voltage level at the terminal of the generator during the fault). This means that the resulted over speed is a function of the inertia constant H of the generator, the duration of the fault and severity of the fault. Fig. 1: Network model 204 connection to grid (bus B5). This corresponds to SCC values in the range 250 MVA to 500 MVA. Fig. 2 shows the temporal variation of the generator speed for different SCR values. As shown in Fig. 2, the grid cannot feed the reactive power requirement of the transmission lines and transformers for SCR less than 4 and overspeed of the machine is expected. The speed, the voltage, the active power and the reactive power of the induction generator at SCR ≥ 4 assume constant values as given in Table I. V. SIMULATION STUDIES In the simulation studies, the reactive power requirements of the wind farm under both steady state and transient conditions were investigated. The strength of the electric grid, to which the wind farm is connected, influences the reactive power requirements. Therefore, different values of the SCR of the wind farm to grid connection are attempted and the steady state and the transient analysis of the wind farm are studied. The strength of the electric grid reflects itself on injecting the reactive power required by the 115-kV transmission line and transformers with no need for the switched capacitor at bus 4. All p.u data have base MVA=100. TABLE I SPEED, VOLTAGE, ACTIVE POWER AND REACTIVE POWER OF THE INDUCTION GENRATOR AT SCR ≥ 4. A. The steady state behaviour The circuit shown in Fig. 1 was simulated without considering the 21 MVAr switched capacitor bank for different SCR values in the range 2 to 4 at the point of The speed (p.u) The voltage (p.u) The active power (p.u) The reactive power (p.u) 1.015 0.915 -0.8 0.33 1.8 SCR=2 SCR=3 SCR=4 Speed (p.u) 1.6 1.4 1.2 1 0 2 4 6 8 10 Time (sec) 12 14 16 18 20 Fig. 2: Temporal variation of the generator speed of different values of SCR. B. Fault analysis values of SCR in the range 2-6. Fig. 3 shows the temporal variation of the generator speed as influenced by the value of SCR. 1) Three-phase to ground fault A three phase to ground fault is applied to the connection point between the wind farm and the 115-kV transmission line at t =3 s for a duration of 140ms (detection time and operation time of the breakers is 140 ms) [3] with different As shown in Fig. 3, the grid cannot feed the reactive power requirement of the transmission lines and transformers for SCR less than 6 and overspeed of the machine is expected 1.7 Speed (p.u) 1.5 1.4 Speed (p.u) SCR=2 SCR=3 SCR=4 SCR=5 SCR=6 1.6 1.3 1.2 1.06 1.04 1.02 2 1.1 1 0 2 4 6 8 10 Time (sec) 12 14 Fig. 3: Temporal variation of the generator speed of different values of SCR. 205 16 4 6 8 10 12 Time (sec) 18 20 line at t =3 s for a duration of 140ms (detection time and operation time of the breakers is 140 ms) [3]. Therefore, the system is in need for the 21 MVAr switched capacitor at SCR=5. For SCR equal or greater than 6, the system is not in need for the 21 MVAr switched capacitor. For SCR equal or greater than 6, the system is not in need for the 21 MVAr switched capacitor. Figure 4 shows the temporal variations of the speed, the voltage, the active power and the reactive power of the induction generator at SCR value of 16 before, during and after the fault in comparison with those obtained using PSCAD simulator [3]. Figure 5 shows the temporal variations of the speed as well as the voltage, the active power and the reactive power of the induction generator at SCR value of 16 before, during and after the fault in comparison with those obtained using PSCAD simulator [3]. As shown in Fig. 4, the present calculated pre-fault and the post-fault values of the speed are 1.015 p.u, which are almost of the same values as obtained previously using PSCAD simulator calculation [3]. During the fault, the speed reaches to 1.03 p.u against 1.06 p.u in the previous calculation [3]. The voltage, the active power and the reactive power have the same trend during the fault as that reported before [3]. Generally, the mismatch between the previous and present calculation of the active and reactive power is nearly negligible and doesn't exceed 0.1%. As shown in Fig. 5, the present calculated pre-fault value of the speed is 1.015 p.u against 1.014 p.u using PSCAD simulator [3]. During the fault, the speed reaches to 1.018 p.u against 1.03 p.u in the previous calculation [3]. After the fault, the speed is 1.015 p.u against 1.02 p.u in the previous calculation [3]. The present calculated pre-fault value of the voltage is 1.0 p.u which is almost of the same value and obtained previously using PSCAD simulator [3]. After the fault, the voltage decreased to 0.87 p.u [3] against the constant voltage value of 1.0 p.u in the present calculation. The pre-fault and the post-fault values of the active power and the reactive power have the same and trend as that reported before [3] during the fault. Generally, the mismatch between the previous and present calculation of the active and reactive power is nearly negligible and doesn't exceed 0.1%. The temporal-variation trends of the speed, the voltage, the active power and the reactive power of the induction generator at SCR values less than 16 are the same as those of SCR=16. 2) Single line to ground fault A single line to ground fault is applied at the connection point between the wind farm and the 115-kV transmission 1.5 1.04 V (p.u) Speed (p.u) 1.06 1.02 1 2 3 4 5 Time (sec) 6 0 2 3 4 5 Time (sec) 6 7 1 0 Q (p.u) 1 P (p.u) 0.5 7 2 0 -1 -2 1 -1 -2 -3 2 3 4 5 Time (sec) 6 -4 7 2 3 4 5 Time (sec) 6 7 Present calculation Previous calculation [3] Fig. 4: Present and previous [3] calculated temporal variations of the speed as well as voltage, active power and reactive power of the induction generator. 206 1.04 1.4 1.03 1.2 1.02 1 1.01 1 0.8 2 3 4 5 Time (sec) 6 7 0 1 -0.5 0.5 Q (p.u) P (p.u) the point of connection between the wind farm and the 115-kV transmission line before and during the fault and the time required to recover pre-fault values for different types of fault. V (p.u) Speed (p.u) The same as for three-phase-to-ground fault, the temporal-variation trends of the speed, the voltage, the active power and the reactive power of the induction generator at SCR values less than of 16 are the same as those of SCR=16. Table II shows voltage and current at -1 -1.5 -2 2 3 4 5 Time (sec) 6 7 2 3 4 5 Time (sec) 6 7 0 -0.5 2 3 4 5 Time (sec) 6 -1 7 Present calculation Previous calculation [3] Fig. 5: Present and previous [3] calculated temporal variations of the speed as well as voltage, active power and reactive power of the induction generator TABLE II VOLTAGE AND CURRENT AT THE POINT OF CONNECTION BETWEEN THE WIND FARM AND THE 115-kV TRANSMISSION LINE BEFORE AND DURING THE FAULT AND THE TIME REQUIRED TO RECOVER PRE-FAULT VALUES. The fault During the fault Voltage (p.u) pre-fault value Current (p.u) Voltage (p.u) Pre-fault recovery after fault Voltage recovered Current (p.u) Value (p.u) Time to recovery (sec) Current recovered Value (p.u) Time to recovery (sec) Va Vb Vc Ia Ib Ic 0 0 0 5.5 5.5 5.5 1 1.05 1 1.5 1.05 1.5 Single-phase 0 1.4 1.4 0.5 1.2 1.2 1 1.05 1 1 1.05 1.5 Line to line 0.5 0.5 0.8 5 5 1 1 1.05 1 1 1.05 1 Double line 0 0 1.4 5 5 1 1 1.05 1 1 1.05 1 Three-phase 207 One can conclude from Table 2 that the three-phase-toground fault is the most severe fault where the time taken for the voltage to recover to its pre-fault value is approximately 1.5 sec which is greater than that for the other faults. The time required for the voltage to recover to its pre-fault is approximately 1 sec for the other faults; namely, double-line-to-ground, line-to-line and single-lineto ground faults. For the three-phase-to-ground fault, the current of faulted bus reaches 5.5 p.u against 5 p.u and 1.2 p.u for double-line and single-line-to-ground faults, respectively Rotor unsaturated mutual reactance: 0.0374 Frequency: 50 No. of poles pair: 2 Reactive power compensation in the wind farm: 34 MVAr. Each Wind farm transformer: Rating: 1.6 MVA Winding voltages: 10.5/0.69 Leakage reactance: 0.0626 No-load losses and cooper losses: 0.0017 17 and 0.0002 Magnetizing current: 0.3 68 Step-up transformer: Rating: 150 MVA Winding voltages: 10.5/115 kV Leakage reactance: 0.06 No-load losses and cooper losses: 0.0017 and 0.0002 Magnetizing current: 0.3 68 Load connected at the end terminal of the line: 100 MW System connected at the end terminal of the line: Short Circuit Power: 2000 MVA, impedance angle 80° VI. CONCLUSIONS 1) The simulation results show that the dynamic model of wind farm using MATLAB simulator agrees with that using PSCAD simulator. The mismatch between the present calculation using MATLAB and the previous calculation using PSCAD is negligibly small (about 0.1%). 2) REFERENCES Three-phase-to-ground fault is the most severe fault regarding over speeding and voltage drop. The current of the faulted bus reaches 5.5 p.u against 5 p.u and 1.2 p.u for double-line and single-line-to-ground faults, respectively. [1] Bhadra SN, Kastha D, Banerjee S. Wind electrical systems. Oxford: Oxford University, U.K., 2005. [2] Jauch C, Sorensen P, Bak-Jensen B. International review of grid connection requirements for wind turbines.In: Proceedings of the Nordic wind power conference, Sweden, 2004. [3] Paulo Fischer de Toledo, Hailian Xie KTH, Kungl Tekniska Högskolan, EME department Teknikringen 33-35, Stockholm, Sweden "WIND FARM IN WEAK GRIDS COMPENSATED WITH STATCOM". Proceedings of the Nordic wind power conference, Topic 7, Sweden, 2005. [4] C. Abbey, Student Member, B. Khodabakhchian, Member, F. Zhou, Nonmember, S. Dennetière, Member J. Mahseredjian, Member, and G. Joos, Senior Member “Transient Modeling and Comparison of Wind Generator Topologies”, Paper No. IPST05, Presented at the International Conference on Power Systems Transients, Montreal, Canada on June 19-23, 2005. [5] H.M.EL-Helw and Sarath B. Tennakoon, “Evaluation of the suitability of a fixed speed wind turbine for large scale wind farms considering the new UK grid code”, Renewable Energy 33, pp.1-12, 2008. 3) For the three-phase fault, the time taken for the voltage to recover to its pre-fault value is approximately 1.5 sec against 1 sec for the other faults. 4) The single-line-to-ground fault is the less severe fault when compared with the other faults. APPENDIX Detailed description of input data to model the system in MATLAB/SIMULINK 115 kV Transmission line data: Length of line = 70 km Positive- and zero-sequence resistances:R1 =0.0739 ohm/km, R0 =0.388 ohm/km Positive- and zero-sequence inductances:X L1 =0.449 ohm/km, X L 0 =1.522 ohm/km Positive- and zero-sequence capacitances:X C1 =0.272 Mega ohm-km, X C 0 =0.427 Mega ohm-km The squirrel-cage induction generator: Generator rating: 1.62 MVA (75 units) Rated RMS line voltage: 690V Stator resistance: 0.00408 1 Cage resistance: 0.0165 Stator unsaturated leakage reactance: 0.06 1 Mutual unsaturated reactance: 3.434 208