AR No. IR No. 858 5881 EIELSON AFB ALASKA NOTES: Administrative Record Cover Sheet 4th Quarter Federal Facilities Agreement (FFA) Progress Report Eielson Air Force Base (AFB), Alaska 10 January 2014 For the Period 1 October 2013 through 31 December 2013 Remedial, Removal, and Investigation Activities: Documents submitted for this quarter are covered under Timetables/Deadlines section of this report below. Documents, fieldwork, and all other remedial activities completed this quarter are also listed in detail in the attached schedule excerpt. Conducted Remedial Project Manager (RPM) monthly meetings on 30 October, 12-13 November, and 18 December 2013. See approved minutes attached for the RPM meetings held on 29 August, 27 September, 30 October, and 12-13 November 2013. NOTE: Meeting Minutes are not yet signed for the 25 December RPM meeting and will be included in the next quarter quarterly report. Meeting Minutes included in this report are non-restricted. During the reporting period, the following field work was performed by various contractors, as follows: Completed IC/LUC inspections during 10-15 October. Performed berm maintenance at Containment Cell Nos. 1 and 2 in October. IWMP VI Phase 2 sampling event for cold weather was completed along with installation and sampling of soil gas wells between 24 October and 20 November. Installed institutional control signs at 10 locations. Two signs along Garrison Slough were replaced (one due to frost-jacking and one due to issues with wobbling). Three signs were replaced at the Waste Water Treatment Plant because they were leaning. Four new signs were installed at the PCB landfill as signage was not present. One new sign was installed along Garrison Slough at its intersection with Broadway where no other signs were located (all the other intersections have signs). Photographs are provided in the attachments section. Completed Stage III field work for additional soil borings and groundwater grab samples at LF03/FT09, ST13/DP26, SS37, CS081, and CS082 from 16-19 October and completed waste load-out and demobilized of field trailer from 20-22 October. Completed field work under the CSM Update investigations at source areas ST20 9 November. Completed field work under the CSM Update investigations at source areas ST48 12 November. Institutional Controls (ICs)/Land Use Controls (LUCs) Construction Update: Provided RPMs construction updates during the monthly meetings using a spreadsheet report and map of the construction sites in relation to the source areas and CRP sites. A copy of the most recent spreadsheet report and map are provided in the attachments to this report. There are no certificates for soil remediation or off-site disposal this quarter. Reviewed 11 Work/Excavation Clearance Requests (All) (AF103), 44 Base Civil Engineer Work Requests (All) (AF332), and reviewed 2 projects for LUC conflicts during the quarter. Total year to date of 48 Work/Excavation Clearance Requests, 204 Base Civil Engineer Work Requests, and 48 Projects for LUCs conflicts. ICs/LUCs Action Updates: The following updates are in accordance with the ICs/LUCs Settlement Agreement and are only required to continue for six months from the execution date of this agreement: 4th Quarter FFA Progress Report Eielson AFB, Alaska 10 January 2014 (1) Inaccurate site boundaries in the Geo Base mapping system (GIS). (2) Incomplete plume delineation – extent of contamination is unknown. STATUS: Field investigations of known contaminated sites were conducted in summer 2012. The sampling data from these investigations is now available in the Draft Installation Wide Monitoring Program Report which was delivered on 23 April 2013. In addition, a GIS contract was awarded on 27 March 2013 intended to update analytical data layers and estimated site plume boundaries based on current data within the USAF Environmental Restoration Program Information Management System (ERPIMS) data base. Development of plume boundaries is ongoing, taking into consideration both historical and new sampling data. Final plume boundaries will be adjusted upon agreement by the RPM’s. 12 areas, including areas of potential contamination, were added to the Eielson GIS system, in addition to updating 17 boundary areas from points plus a 200 foot buffer to more accurate polygon shape based on previous sampling plus a 200 foot buffer. (3) Lack of clear reporting requirements to Eielson Environmental and the regulatory agencies when contamination is encountered. STATUS: Many discussions have occurred and further clarification has been received from the regulatory agencies and incorporated into the formal checklist. The formal checklist was provided to the fire department operators group. The Draft LUC/IC Management which is currently in development will include details of reporting requirements, as specified in the 16 April 2013 IC/LUC Settlement Agreement, to Eielson Environmental and the regulatory agencies when contamination is encountered. (4) Lack of defined communication protocols between Engineering and EM staff. STATUS: The Fighter Wing instruction has been returned to the Judge Advocate for review. In lieu of an approved instruction, the draft procedures are followed by Environmental, Engineering, and Operations at a minimum. The instruction defines the roles and responsibilities for all Air Force (AF) parties. The instruction also points to using the design guide, which includes a checklist of required actions for projects. Information of the Fighter Wing instruction was included in the Draft LUC/IC Management Plan. (5) Lack of clear requirements for characterizing and managing contaminated media from discovery or generation until disposal. STATUS: All current contaminated media stockpiles were removed from base and final disposal occurred during the summer 2013 field season when the incineration plant re-opened. For any contamination discovered within known contamination areas on base, contractors and/or local base personnel shall follow the state requirements for reporting and disposal as outlined in the approved work plan. For any contamination newly created, or found, in unknown contaminated areas, the contractor and/or local base personnel shall comply with state spill reporting and response procedures and as outlined within the Eielson AFB work plan template, or approved equal. The Dig Permits (AF Form 103) shall not be signed off until the work plan has been approved. -2- 4th Quarter FFA Progress Report Eielson AFB, Alaska 10 January 2014 (6) Lack of oversight by Eielson Environmental to ensure that all construction projects comply with regulations for sampling, soil (and other media) handling and offsite transport and disposal. STATUS: Construction projects are being tracked as a special interest item by Asset Management and construction project meetings have occurred to identify environmental concerns and requirements regarding any construction activity taking place within 200 feet of known areas of concern. These construction projects have been layered within GIS and a printed map has been made available and briefed during the monthly RPM meetings. Eielson contracted environmental support oversight for the 2013 field season. (7) Lack of follow-through on precautions and procedures delineated in the Authorization Form approval. (8) Environmental review deficient due to lack of clear documentation of Compliance Restoration Sites… as CRP sites not included in Geo Base… STATUS: A wing form has been developed for concurrent approval with the wing instruction and is currently being staffed through upper management for approval. Compliance restoration sites have been added to the base GIS system and are incorporated into environmental reviews of projects. 12 areas, including areas of potential contamination, were added to the Eielson GIS system, in addition to updating 17 boundary areas from points plus a 200 foot buffer to more accurate polygon shape based on previous sampling plus a 200 foot buffer. (9) AAFES Service Station project did not initiate work clearance forms and dig permits until ADEC alerted Eielson Environmental staff. STATUS: No further update since the clarification from the 13 April 2012 letter. Current Schedule Items Status: Refer to the MS Project schedule excerpt attached to this letter for further details on planned IC/LUC activities. Below is a summary of the current status of scheduled IC/LUC items. 1. LUC Updates: a. Data Gaps Investigation – Ongoing. b. Update the Conceptual Site Models of the IRP Sites – Ongoing with revised target completion after the 2013 Five-Year Review. c. Update Base Management Plans – Ongoing with target completion after 2013 Five-Year Review. d. 2013 Five-Year Review – Ongoing with target completion by October 2013. 2. The Fighter Wing Instruction is being revised before being re-staffed for approval through wing management. 3. Annual regulatory training on spill reporting procedures and contaminated soil management will incorporate updated spill response requirements. Additionally, informal cross functional meetings to identify new regulatory requirements versus past practices will be incorporated into planning meetings. – Ongoing. -3- 4th Quarter FFA Progress Report Eielson AFB, Alaska 10 January 2014 4. More Formal Training – Ongoing. 5. Digging Permit (AF Form 103) Updates and Implementation – Ongoing with informal implementation until final approval of the Wing Instruction. Effective as of the date of the signed, fully-executed IC/LUC Settlement Agreement (16 April 2013), no dig permit for major construction will be approved without a regulatory-approved work plan / sampling and analysis plan. 6. Soil stockpiles within LF03 Cell #1 and #2 have been disposed of with approval by regulatory personnel and no further stockpiles are on hand. Soil generated during the 2013 construction season are stockpiled on the construction site. 7. Eielson AFB has awarded a land use control contract. A revised Draft LUC/IC Management Plan is tentatively scheduled to be delivered for regulatory review on 17 August 2013. A GIS contract to update source area boundaries was awarded on 27 March 2013. Community Relations Activities: The RAB adjournment memorandum was prepared and is being reviewed at the Public Affairs office prior to further staffing for the Wing Commander’s approval. Planned Activities for Next Quarter (1 January – 31 March 2014): The 4th quarter activities planned are primarily related to preparing reports for the IWMP, CSM Update, CRP, and SER sites; finalizing the SMP and Five-Year Review amendments, and formally adjourning the RAB with the signing of the RAB Adjournment Memorandum. See schedule excerpt with more detailed listing of activities planned for the next quarter. Timetables / Deadlines: The table below summarizes documents submitted for this quarter. Document Summary 2014 SMP Amendment 3rd Quarter FFA Progress Report* Draft Spring 2013 IWMP Groundwater Sampling Tech Memo Draft SS35 CSM Update Report Draft Background Groundwater Study PSG, GPR, Landfill Survey and Landfill Inspection, and Monitoring Wells Maintenance and Repairs Technical Memorandum Draft IWMP VI Tech Memo (only warm weather data) Draft CS082 Site Characterization Report Draft CS081 Site Characterization Report Submittal Date 1-Oct-13 18-Oct-13 4-Nov-13 4-Nov-13 27-Nov-13 14-Dec-13 19-Dec-13 19-Dec-13 24-Dec-13 *The 3rd Quarter FFA Progress Report due date of 10 October was extended due to the federal government furlough and in accordance with the Eielson AFB FFA Section XXVI on Force Majeure. The USAF’s document schedule is maintained in Microsoft Project and reviewed with the RPMs on a monthly basis. Provided in the attachments are several schedule excerpts that detail the documents and other activities for this quarter, as well as projected activities for the next quarter. -4- 4th Quarter FFA Progress Report Eielson AFB, Alaska 10 January 2014 Off Base Monitoring / Rights of Entry: x There are no monitoring or right of entry issues off the installation. Other Activities Affecting Phases in FFA Attachments: x To be discussed in future RPM and Triad meetings. Prepared by: BEISTEL.DAVID.EU GENE.1036841784 Digitally signed by BEISTEL.DAVID.EUGENE.1036841784 DN: c=US, o=U.S. Government, ou=DoD, ou=PKI, ou=USAF, cn=BEISTEL.DAVID.EUGENE.1036841784 Date: 2014.01.10 14:04:04 -09'00' David E. Beistel, DAF Chief, Installation Restoration Program AFCEC OLA-E 2310 Central Ave Ste 100 Eielson AFB, AK 99702-2299 -5- 4th Quarter FFA Progress Report Eielson AFB, Alaska 10 January 2014 This page intentionally left blank. 4th Quarter FFA Progress Report Eielson AFB, Alaska 10 January 2014 ATTACHMENTS 4th Quarter FFA Progress Report Eielson AFB, Alaska 10 January 2014 This page intentionally left blank. 4th Quarter FFA Progress Report Eielson AFB, Alaska 10 January 2014 Approved RPM Monthly Meeting Minutes 4th Quarter FFA Progress Report Eielson AFB, Alaska 10 January 2014 This page intentionally left blank. Eielson Air Force Base, Alaska Remedial Project Managers' Monthly Meeting Government and Contractor Session Smith Associates 29AUGUST 2013 Final Agenda II I I l' I <, ' LOCATION: DATE/TIME: CONFERENCE LINE: ACCESS CODE: ADOBE CONNECT: I' I I' <l I I \~ ll I< 1-: H I I I I R I <l I <, I II I R Westmark Fairbanks Hotel & Conference Center, Harper Board Room 813 Noble Street, Fairbanks, Alaska 99701 Thursday, 29 AUGUST 2013 1115-1630 AKDT 800-768-2983 or 647-723-6913 Participant: 3343909# [Chairperson: 9501] http: 1/smithcollaboration.adobeconnect.com /eielson- rpm-meeting-august- 2 013/ Topic Pu ose i Presenter : Time ADMINISTRATIVE (1115-1145) Introductions Technical/Field Meetings Decision Points ** Review Action Items Introduce participants and provide overvie~ of the agenda. • Review non-procurement-sensitive decision points reached during government-only sessions. • Solicit and discuss any recommended decision points from contractors. • Review non-procurement-sensitive action items determined during government-only sessions. • Solicit and discuss any recommended action items from contractors. Tim Sueltenfuss David Beistel 1115-1125 Tim Sueltenfuss 1135-1145 All contractors 1145-1155 1125-1135 - ORGANIZATIONAL UPDATES (1145-1155) Contractors • • • Policy updates Leadership changes Staff out of office/authority in absence 1155-1310 TECHNICAL DISCUSSIONS (1310-1600) IRP • Schedule review • • RI/SRIInvestigations • SS67 • WP45/SS57 Installation-wide Investigations • IWMP • Background Study '7 00 orrh t. • • • • • Brief review of changes with no schedule impact; Detailed review of changes that affect schedule; Review of field work schedule excerpt Schedule Deliverables Regulatory comments Fieldwork Issues to be resolved ·1a ry\ llr. , uire 1290 .111 David Beistel/ Cristina Radu 1310-1410 Kevin Maher 1410-1440 Mark Wilkinson Anr o ni o , TX '7 820) / T : 2 10 .270 .77 61 f : 2 10 .200.6272 To ic CSM Updates • ST20 • ST48 • SS35 CSM Updates • LF03/LF09 • ST10/SS14 • ST13/DP26 • SS37 SERs • SS084-AOC 16 • SS085-UIC Bldg 3386 • SS086-Taxiway Golf SERs • CH2MHill SER contract sites CRP • CS081 (former SER001-2008) • CS082 (former SER001-2010) MMRP MMRP Update and Field Status Briefing Pu • • ose Implication to 2013 FYR (as appropriate) Funding and contracting (as appropriate) - Kyle Waldron Carolyn Tallant • • • • • • Schedule Deliverables Regulatory comments Fieldwork Issues to be resolved Funding and contracting (as . apQr_<_>priate) - - Pat Roth/ Kevin Maher 1440-1450 David Beistel/ Carolyn Tallant Tim Sueltenfuss 1450-1505 - Update current and planned MMRP activities. Discuss prioritization of activities that have not yet been placed on contract. BREAK WRAP UP (1600-1630) Review and confirm agreement on the following: • Upcoming meetings, • New and existing non -procurementsensitive action items, • Success stories, and • New non-procurement-sensitive decision points. Page 2 of3 1505-1530 1530-1545 1545-1600 Additional Discussion Topics Recap Meeting Outcomes Time Pat Roth/ Kevin Maher - Priority /Effort Review Presenter Kyle Waldron Tim Sueltenfuss 1600-1615 To ic Decision Point Review Pu ose Review decision point tracker to accomplish the following, if needed: • Revise previously agreed decision points • Withdraw decision points that are no longer valid _ Confirm location, date, and time for the Set/Confirm Future Meetings following: • 24-25 SEP 2013 RPM Meeting t • 29-30 OCT 2013 RPM Meeting t • 20 NOV 2013 RPM Teleconference • 18 DEC 2013 RPM Teleconference • 29 JAN 2014 RPM Meeting • Other Meetings [t Note: Day 1 is a technical session and Day 2 is the RPM Monthly J\1eeting.] _ Identify agenda items and associated Identify Future Agenda Items meeting/ date: • Scope CoC Audit (TBD) • Source Area Boundaries (within Construction Update) (Sep 2013) • Site Closure Planning (Fall 2013) ADJOURN RPM MONTHLY MEETING ** standing agenda item Page 3 of3 ... Time 1 1615-1625 - 1625-1630 ' I DEPARTMENT OF THE AIR FORCE PACIFIC AIR FORCES Eielson Air Force Base (AFB), Alaska Non-Restricted - RPM Monthly Meeting Minutes 29 August 2013, 1115- 1630 The following minutes are non-restricted and not procurement-sensitive. 1. PARTICIPATION: The meeting was conducted at Westmark Inn located at 813 Noble Street, Fairbanks, Alaska. Participants in attendance, either in the room or over the telephone, included the following: • • • • • • • • • • • • • • • • • • David Beistel - Eielson AFB/354 CES/CEAN Carolyn Tallant- Eielson AFB/354 CES/CEAN David Bell*- Air Force Civil Engineer Center (AFCEC) Paul Jurena* - AFCEC Patrick Roth - AFCEC Joann Socash* -Nob lis, Inc. Tim Sueltenfuss- SMITH/Associates Kristen Villarreal- SMITH/Associates Kimberly DeRuyter- Alaska Department of Environmental Conservation (ADEC) Eric Breiten berger- ADEC Aaron Lambert*- U.S. Environmental Protection Agency (EPA) Jackie Kramer- EPA Kelly Findlay - EA Engineering, Science, and Technology, Inc. (EA) Michael Jones - EA Cristina Radu* - EA Kyle Waldron*- EA Mark Wilkinson- EA Kevin Maher* - Jacobs Engineering Group, Inc. *Participated via telecom. 2. ADMINISTRATIVE (Minutes/Action Items): a. Minutes Review/Approval (Mr. Beistel): The Remedial Project Managers (RPM) reviewed and approved the meeting minutes for the 3 l July 2013 monthly meeting. Mr. Beistel and Ms. DeRuyter signed the meeting minutes in-person. Mr. Lambert will sign electronically post meeting after the hard copy of the signed minutes is e-mailed to him. b. OLD Action Items (Mr. Sueltenfuss/Ms. Findlay): The RPMs reviewed the latest action items, which are non-restricted and not procurement-sensitive, provided on the 20 August 2013 Open Action ltems list, as follows: • Action Item No. 179 (previously No. 24) was for the RPMs to discuss prioritization of the SERICRP site list. This item was determined to be overtaken by Performance-Based Remediation/Minimum Performance Objective review during the government-only RPM Non-Restricted - RPM Monthly Meeting Minutes 29 August 2013 meeting on 28 August 2013 and will be moved to the Completed Action Items list. • Action Item No. 215 (previously No. 60) was converted to a restricted action item. • Action Item No. 217 (previously No. 62) was for the U.S. Air Force (USAF) to provide ADEC/EPA with slides and handouts from the Unit Environmental Coordinator course, including base supplements. This item was confirmed complete during the governmentonly RPM meeting on 28 August 2013 and will be moved to the Completed Action Items list. • Action Item No. 220 (previously No. 65) was to discuss with regulatory agency attorneys on the interpretation of which documents are Primary and Secondary. Specifically, there are some data reports that are Secondary/Other documents that do not have a Primary document to feed into. Of note, language in Sec. 20.2 of the FFA says "they may" feed into Primary documents. Mr. Lambert is continuing to work on this action item and Ms. Kramer has been added as an owner. A new due date of24 September 2013 was determined. • Action Item No. 224 (previously No. 69) was for the USAF and ADEC will nominate workgroup members to develop procedure for utilizing the values in the background study in future investigation reports. All parties determine participants who should be a part of the workgroup. This item was confirmed complete during the government-only RPM meeting on 28 August 2013 and will be moved to the Completed Action Items list. • Action Item No. 225 (previously No. 70) was for the EPA to develop model language for complying with Section 5.4.3 of the Institutional Controls (IC)/Land Use Controls (LUC) Settlement Agreement. Mr. Lambert will initially develop language and then send out to other RPMs for review with a due date of28 August 2013. This action was revised to read "Concurrently obtain advice from agency management on how best to comply with Section 5.4.3 of IC/LUC Settlement Agreement" and reassigned to all RPMs. A new due date of 24 September 2013 was determined. • Action Item No. 226 (previously No. 71) was for the USAF to disseminate data for source area ST48 to enable the RPMs to determine if sufficient data have been collected to properly delineate the boundaries of polycyclic aromatic hydrocarbons. This item was assigned to Ms. Radu with a due date of 6 August 2013. Field Status Report for source areas ST48, ST20, and SS35 disseminated on I August 2013. This action will be moved to the Completed Action Items list. c. NEW Action Items (Mr. Sueltenfuss/Ms. Findlay): The RPMs agreed to add the following new action items, which are non-restricted and not procurement-sensitive, to the Open Action Items list: • Action Item No. 228: Provide a written statement (with timelines and lessons learned) concerning recent activity at containment cells. This action item was opened during the government-only RPM meeting on 28 August 2013 and assigned to Ms. Tallant and Mr. Wilkinson with a due date of ll Sep 2013. • Action Item No. 229: Describe the proposed disposal of drums including a timeline and comprehensive list by work plan. This action item was opened during the governmentPage 2 of3 Non-Restricted - RPM Monthly Meeting Minutes 29 August 2013 only RPM meeting on 28 August 20 13 and was assigned to Ms. Tallant and Mr. Jones with a due date of 16 Sep 2013 . • Action Item No. 230: Generate a letter for file confirming the 17 sites moving under state regulation . This action item was opened during the government-only RPM meeting on 29 August 2013 and was assigned to Mr. Beistel with a due date of 16 Sep 2013. • Action Item No. 199 (previously No. 44): Cross-reference the DEC and the Enterprise Environmental, Safety, and Occupational Health Management Information System site identifications. Create a spreadsheet containing the appropriate site information. A monthl y review will occur during standing agenda topic at RPM meetings. Action item "Present and review a consolidated comprehensive site list" created 27 Feb 2013 and completed 24 May 2013 (with comment "Discuss site identifier and site status. Work with Eric Breitenberger and Aaron Lambert."). This action item was re-opened during the government-only RPM meeting on 29 August 2013 and changed to current wording. This action item was assigned to Mr. Breitenberger with a due date of24 Sep 2013. • Action Item No. 231: Review most recent version U.S. Army Corps of Engineers, Alaska District manual for electronic deliverables and consider for potential use as a standard data deliverable format. This action item was opened during the governmentonly RPM meeting on 29 August 2013 and was assigned to the RPMs with a due date of 24 Sep 2013. • Action Item No. 232: Review regulations for Investigation-Derived Wastes and convey those in writing to USAF . This action item was opened during the government-only RPM meeting on 29 August 2013 and was assigned to DEC/EPA with due date to be determined. 3. DECISION POINTS: The RPMs approved to withdraw two previous decision points and approved one new decision point during this meeting. These decision points are non-restricted and not procurement-sensitive, and are attached to these meeting minutes. 4. SUCCESS STORIES: Two success stories were discussed during this meeting, as follows: a. The efforts of the EPA, DEC, and USAF to approve work on the volunteer disc golf project allowed installation of the course to occur this season. Thi s enabled USAF personnel to hold a disc golf tournament and provide engaging on-base activities for Airmen stationed at Eielson AFB . b. The EPA, DEC, and USAF were highly effective in coordinating to obtain expedient reviews and approvals of construction sampling and analysis work plans, which ensured that $78 million in construction efforts affected by contaminated site concerns were not delayed for the 2013 construction season. 5. 1630: Meeting Concluded. USAF Project Manager ~ UJ ~ t0 KBiRLYD~~R DEC Project Manager Page 3 of3 _ _ _ J_ _ Eielson AFB RPM Decision Tracker NON-RESTRICTED · Approved Decision Points Updated as of 29AUG2013 lr::r.n::rnT'il:ti: [ {""~''" The SMP is enforceable via the IC/LUC Settlement Agreement and it is an "other'' type document. The submission of the initia l (2013) SMP will be submitted/reviewed in accordance with Section 5.4 of the IC/LUC Settlement Agreement. Subsequent amend ments (5.4.4) will be reviewed in accordance with the schedule for "primary" type __ documenls as..des.cdb.ed.in Jb!LEEA-._ '"' -I"" "'""' .... _ -· _ ....F.l .. ~. o~mmM< and Contractor Session ,.~. ]"'"~ ·---- -- - Page 1 of 1 tr.lr. 29-Aug-131Replaced DP 5B _l_ __ J .... ~~T•" ~. FYR In order to meet the tight deadline for completion of the FYR , the delivery date of the draft final FYR on 31 JUL2013 will be the official delivery date for this document. The RPMs agreed that the 31JUL2013 deliverable will include the following : (1) the draft final version of the FYR and (2) a redline version; the redl ine version will consist of the changed pages in track form and the RTCs table , which will be included as an appendix to the draft fin al FYR . Note that this redline document is consistent with redline procedures implemented programmatically at Eielson AFB. The EPA and AD EC RPMs agreed during this meeting that the 31JUL2013 draft fina l version may undergo changes based on forthcoming AF legal review and that the version revised based on AF legal review is the one that will be submitted within the regulatory agencies for upper management review; however, the regulatory RPMs will benefit from added review time by initiating technical review on the 31 JUL2013 version of the document. 57 r YR Delivery Date I 1 j I I - '" 1 I ~• I'"'"'' ,..,,. j LJ ... Eielson AFB RPM Decision Tracker NON-RESTRICTED ·Withdrawn Decision Points Updated as of 29AUG2013 cyoO """•-<'ore•m••' "' '"' 0 'an""other" " " "type '""''"""'"" '"'it"" document; and wi ll follow the same review cycle as a "primary" type document. l'r-. Draft FYR Comments Reconciliation Meeting - Part 2 lr. 24-Jui-13 IWithdrawn 1 -'~'""~ •~octoC-1 "·'-'"IW'M"~ ' • 1 "" technical session __ -------- Page 1 of 1 1 _ 28 -Aug-13 IApproved during RPM Monthly Meeting ,...,.n~eplaced by DP #59meeting after determination during 29 Aug RPM that one element of this DP does not align with ~=-~~~of the IC/LUC Settlement DEPARTMENT OF THE AIR FORCE PACIFIC AIR FORCES I Eielson Air Force Base (AFB), Alaska Non-Restricted - RPM Monthly Meeting Minutes 27 September 2013,0800-1030 AKDT The following minutes are non-restricted and not procurement-sensitive. 1. PARTICIPATION: The meeting was conducted via teleconference and Adobe Connect. Participants in attendance included the following: • • • • • • • • • • • • • • • David Beistel - Eielson AFB/354 CES/CEAN David Bell- Air Force Civil Engineer Center (AFCEC) Eric Breitenberger- ADEC Anthony Gennaro - AFCEC Tony Hernandez- AFCEC Paul Jurena - AFCEC Jackie Kramer-EPA Julene May- Eielson AFB/354 CES/CEA Chris Morriss - AFCEC Patrick Roth - AFCEC Bob Shirley- AFCEC Joann Socash- Noblis, Inc. Tim Sueltenfuss - SMITH/Associates Kristen Villarreal - SMITH/ Associates William Watts - AGEISS, Inc. 2. ACTION ITEMS: a. OLD Action Items (Mr. Sueltenfuss/Ms. Villarreal): The RPMs reviewed the latest action items, which are non-restricted and not procurement-sensitive, provided on the 26 September 2013 Open Action Items list, as follows: • Action Item No. 199 (previously No. 44): Was for DEC to cross-reference the DEC and the Enterprise Environmental, Safety, and Occupational Health Management Information System site identifiers and to create a spreadsheet containing the appropriate site information. This action item was re-opened during the government-only RPM meeting on 29 August 2013 and changed to current wording." This action item was assigned to Mr. Breitenberger. A new due date of 30 October 2013 was determined. • Action Item No. 220 (previously No. 65) was to discuss with regulatory agency attorneys on the interpretation of which documents are Primary and Secondary. This action was determined to be overcome by events due to the Site Management Plan approval and was moved to the Closed Action Items list. • Action Item No. 225 (previously No. 70) was for all RPMs to concurrently obtain advice from agency management on how best to comply with Section 5.4.3 ofiC/LUC Non-Restricted - RPM Monthly Meeting Minutes 29 August 2013 Settlement Agreement. Mr. Bell provided a proposed process (indicated in Pending NonRestricted Decision Point No. 60). The EPA and DEC RPMs will discuss this with their management prior to accepting, altering, or rejecting this pending decision point. • Action Item No. 228 was for USAF to provide a written statement (with timelines and lessons learned) concerning recent activity at containment cells. This action item was assigned to Ms. Tallant and she completed it on 17 September 2013. It was moved to the Closed Action Items list. • Action Item No. 229 was for the USAF and EA to describe the proposed disposal of drums including a timeline and comprehensive list by work plan. This action was deferred to the next RPM meeting and a new due date of30 October 2013 was determined. • Action Item No. 230 was for USAF to generate a letter for file confirming the 17 sites moving under state regulation. The following comment was included: "Transmitted on 24 Sep 2013. 18 sites were listed on the multi-SER report." This action was moved to the Closed Action Items list. • Action Item No. 231 was for the RPMs to review the most recent version of the U.S. Army Corps of Engineers, Alaska District manual for electronic deliverables and consider for potential use as a standard data deliverable format. This action remains open. • Action Item No. 232 was for DEC/EPA to review regulations for Investigation-Derived Wastes and convey those in writing to USAF. The due date is to be determined and this action remains open. b. NEW Action Items (Mr. Sueltenfuss/Ms. Villarreal): The RPMs agreed to add the following new action item, which is non-restricted and not procurement-sensitive, to the Open Action Items list: • Action Item No. 233: Generate a Geobase map to incorporate all spill sites within the airfield I flightline. This action item was assigned to Mr. Beistel with a due date of 30 October 2013. 3. HIGH-LEVEL SCHEDULE REVIEW: a. Five Year Review (FYR) Update (D. Beistel): Regulators are working on comments on the Draft Final FYR as well as the concurrence letter. Their intent is to provide these by 30 September 2013. The Air Force will begin to incorporate regulatory comments and issue a final FYR thereafter. 4. CONSTRUCTION UPDATE: a. CLOSED Sites (Ms. May): The RPMs agreed to close the following sites: • ID 16 Replace Runway Deck Sheaves • ID 22 Demo Various Buildings atE-Hill • ID 42 Install Electrical Circuit Page 2 of3 Non-Restricted - RPM Monthly Meeting Minutes 29 August 2013 • ID 46 Add/Alter 168th Comm Bldg 5. DECISION POINTS: a. APPROVED Decision Points (Mr. Sueltenfuss/Ms. Villarreal): The RPMs did not approve any new decision points. b. PENDING Decision Points (Mr. Sueltenfuss/Ms. Villarreal): The RPMs added one new pending decision point. This decision point is non-restricted and not procurement-sensitive. • Decision Point No. 60: Meet the requirement of Section 5.4.3 of the IC/LUC Settlement Agreement by doing the following upon a new or changed task that has a Primary or Secondary document: 1. Revise the Milestone Schedule Table of the SMP by adding a new line/entry or changing a due date. 2. Post the table/SMP to the SharePoint site, and then 3. Air Force sends an e-mail to EPA and ADEC indicating that the SMP Milestone Schedule has been revised and posted. This should be done within 14 days of a new or revised Target or Deadline date c. WITHDRAWN Decision Points (Mr. Sueltenfuss/Ms. Villarreal): The RPMs did not withdraw any previous decision points. 6. 1030: Meeting Concluded. ~ ~~ DAVID BEISTEL USAF Project Manager BERL Y DE TER DEC Project Manager Page 3 of3 This page intentionally left blank. Eielson Air Force Base, Alaska Remedial Project Managers’ Monthly Meeting Government and Contractor Session 30 OCTOBER 2013 Final Agenda LOCATION: DATE/TIME: CONFERENCE LINE: ACCESS CODE: ADOBE CONNECT: meeting/ Westmark Fairbanks Hotel & Conference Center, Harper Board Room 813 Noble Street, Fairbanks, Alaska 99701 Wednesday, 30 October 2013 1315-1630 AKDT 800-768-2983 or 647-723-6913 Participant: 3343909# [Chairperson: 9501] http://smithcollaboration.adobeconnect.com/eielson-rpm-gov-contractor-monthly- Topic Introductions Review Non-Restricted Decision Tracker ** Contractors Soils Background Study Discussion Purpose ADMINISTRATIVE (1315-1335) Introduce participants and provide overview of the agenda. Review non-restricted decision tracker to advise contractors of any decision points or action items reached during government-only sessions. • Solicit and discuss any decision points or action items, which contractors recommend or have input on. ORGANIZATIONAL UPDATES (1335-1340) • Policy updates • Leadership changes • Staff out of office/authority in absence TECHNICAL DISCUSSIONS (1340-1610) • Discuss whether the soils background study (a secondary document) can and should be approved by the regulators. • If so, discuss the process by which to obtain this approval. • If not, discuss whether and how to use the information and decision logic developed in the soils background study for evaluating CoCs found at other source areas. • Presenter Time Kristen Villarreal/ Tim Sueltenfuss Kristen Villarreal/Tim Sueltenfuss 1315-1320 All contractors 1335-1340 Paul Jurena 1340-1410 1320-1335 Topic IRP Schedule review Purpose • • • RI/SRI Investigations • SS67 • WP45/SS57 Installation-wide Investigations • IWMP • Background Study CSM Updates • ST20 • ST48 • SS35 CSM Updates • LF03/LF09 • ST10/SS14 • ST13/DP26 • SS37 SERs • SS084-AOC 16 • SS085-UIC Bldg 3386 • SS086-Taxiway Golf SERs • CH2MHill SER contract sites • USACE contract for 17 SERs CRP • CS081 (former SER001-2008) • CS082 (former SER001-2010) MMRP MMRP Update • • • • • • • Brief review of changes with no schedule impact; Detailed review of changes that affect schedule; Review of field work schedule excerpt Schedule Deliverables Regulatory comments Fieldwork Issues to be resolved Implication to 2013 FYR (as appropriate) Funding and contracting (as appropriate) Presenter Time David Beistel/ Mike Jones 1410-1440 Kevin Maher 1440-1525 Mike Jones Kyle Waldron Pat Roth/ Kevin Maher Kyle Waldron Carolyn Tallant • • • • • • Schedule Deliverables Regulatory comments Fieldwork Issues to be resolved Funding and contracting (as appropriate) BREAK Pat Roth/ Kevin Maher Update current and planned MMRP activities. David Beistel/ Carolyn Tallant Page 2 of 3 1525-1535 1535-1550 1550-1600 Topic Community Relations Update Purpose Discuss progress toward adjourning the RAB. WRAP UP (1610-1630) Review and confirm agreement on the following: • Upcoming meetings • New and existing action items • Existing decision points o Revise previously approved decision points o Withdraw decision points that are no longer valid • New decision points • Success stories Set/Confirm Future Meetings Confirm location, date, and time for the following RPM meetings: • 19-20 or 20-21 NOV 2013 (in-person) • 18 DEC 2013 teleconference • 21-22 or 28-29 JAN 2014 (in-person) • 25-26 FEB 2014 (in-person) • 25-26 MAR 2014 (in-person) • 29-30 APR 2014 (in-person) Identify Future Agenda Items Identify agenda items and associated meeting/date: • Site Closure Planning (Fall 2013) • USAF notification to EPA and ADEC of the actual amounts budgeted per FFA Section 27.6 (prior to 1 February 2014) ADJOURN RPM MONTHLY MEETING Recap Non-Restricted Meeting Outcomes ** standing agenda item Page 3 of 3 Presenter David Beistel/ Kelly Findlay Time 1600-1610 Kristen Villarreal/ Tim Sueltenfuss 1610-1625 1625-1630 1630 DEPARTMENT OF THE AIR FORCE PACIFIC AIR FORCES Eielson Air Force Base (AFB), Alaska Non-Restricted- RPM Monthly Meeting Minutes 30 October 2013, 1315-1630 The following minutes are non-restricted and not procurement-sensitive. 1. PARTICIPATION: The meeting was conducted at Westmark Inn located at 813 Noble Street, Fairbanks, Alaska. Participants in attendance, either in the room or over the telephone, included the following: • • • • • • • • • • • • • • • • • • • David Bell*- Air Force Civil Engineer Center (AFCEC) David Beistel - Eielson AFB/AFCEC Eric Breitenberger- Alaska Department of Environmental Conservation (ADEC) Kimberly DeRuyter- ADEC Kelly Findlay- EA Engineering, Science, and Technology, Inc. (EA) Michael Jones- EA Paul Jurena* - AFCEC Jackie Kramer- U.S. Environmental Protection Agency (EPA) Kevin Maher*- Jacobs Engineering Group, Inc. Julene May- Eielson AFB/354 CES/CEI Cristina Radu * - EA Patrick Roth*- AFCEC/611 th Robert Shirley*- AFCEC Western Regional Environmental Joann Socash*- Noblis, Inc./AFCEC Tim Sueltenfuss- SMITH/Associates Carolyn Tallant* - Eielson AFB/AFCEC Kristen Villarreal* - SMITH/Associates Kyle Waldron- EA William Watts- AGEISS/AFCEC *Participated via telecom. 2. ADMINISTRATIVE (Minutes/Action Items): a. Minutes Review/Approval (Mr. Beistel): The Remedial Project Managers (RPM) reviewed and approved the meeting minutes for the 29 August 2013 and 27 September 2013 monthly meetings. b. OLD Action Items (Mr. Sueltenfuss/Ms. Findlay/Ms. Villarreal): The RPMs reviewed the latest action items, which are non-restricted and not procurement-sensitive, provided on the 17 October 2013 Decision Tracker. • Action Item No. 199 remains open with a new due date of 13 November 2013 . Non-Restricted - RPM Monthly Meeting Minutes 30 October 2013 • Action Item No. 225 remains open with a new due date of 15 November 2013. The owner was changed to Mr. Bell. • Action Item No. 229 was changed to proposed for closure to open with new a due date of 12 November 2013. • Action Item No. 231 remains open with a new due date of 13 November 2013. The owners were changed to Mr. Roth and Ms. Tallant. • Action Item No. 232 was revised with a new due date of 13 November 2013. • Action Item No. 233 was completed and moved to the Closed Action Items list. c. NEW Action Items (Mr. Sueltenfuss/Ms. Findlay/Ms. Villarreal): The RPMs agreed to add new action items No. 234 and No. 235, which are non-restricted and not procurementsensitive, to the Open Action Items list. 3. DECISION POINTS: The RPMs revised Decision Point No. 60 and approved new Decision Point No. 61. 4. SUCCESS STORIES: One success story was approved during this meeting and is provided on in the attachments. 5. REMEDIAL INVESTIGATIONS DISCUSSION: RPMs discussed the manner by which Remedial Investigations might be modified, as requested in U.S. EPA's concurrence letter on the Draft Final 2013 Five-Year Review. Discussion on this topic is ongoing. 6. 1630: Meeting Concluded. /::!~,~ Wvlo BEISTEL USAF Project Manager ~gg~ DEC Project Manager Page 2 of2 This page intentionally left blank. Eielson AFB RPM Decision Tracker NON-RESTRICTED - OPEN ACTION ITEMS Updated as of 30OCT2013 No. Date Created 29-Aug-13 Action Item Cross-reference the DEC and EESOH-MIS site IDs. Create a spreadsheet containing the appropriate site information. 199 31-Jul-13 225 28-Aug-13 229 29-Aug-13 231 29-Aug-13 232 29-Oct-13 234 235 29-Oct-13 Concurrently obtain advice from agency management on how best to comply with Section 5.4.3 of IC/LUC Settlement Agreement. Describe the proposed disposal of drums including a timeline and comprehensive list by work plan. Comments/Resolution Do a monthly review during standing agenda at RPM meetings. Action item “Present and review a consolidated comprehensive site list” created 27 Feb 2013 and completed 24 May 2013 (with comment “Discuss site identifier and site status. Work with Eric Breitenberger and Aaron Lambert.”). Re-opened 29 Aug 2013 and changed to current wording of action item. Status Open Owner Due Date ADEC (E. Breitenberger) 13-Nov-13 Old No. 44 Open USAF (D. Bell) 15-Nov-13 70 Describe whether disposal is in accordance with the work plans. If Open not, seek regulatory approval. Submitted to ADEC and EPA on 17 Sep 2013. Includes tabulated data. Open Review the most recent version of the USACE Alaska District manual for electronic deliverables and consider for potential use as a standard data deliverable format. Review regulations/policy for Investigation-Derived Open Wastes (IDW) (specifically well purge water) and convey those in writing to USAF. Confirm their agency’s designation of project manager Open and alternate (per FFA Section 9.1). Submit a letter as required. Generate a letter formalizing the recommendations of the 18 sites to be addressed under State regulations; the remainder to Open multiple site SER for site disposition. stay under the FFA. Page 1 of 29 USAF/EA (C. Tallant/M. Jones) 12-Nov-13 USAF (P. Roth/C. Tallant) 13-Nov-13 DEC/EPA 13-Nov-13 RPMs 13-Nov-13 USAF (D. Beistel) 13-Nov-13 Eielson AFB RPM Decision Tracker NON-RESTRICTED - CLOSED ACTION ITEMS Updated as of 30OCT2013 No. Date Created 10-Nov-11 1 10-Nov-11 2 10-Nov-11 3 4 23-Nov-11 23-Nov-11 5 23-Nov-11 6 2-Dec-11 7 2-Dec-11 8 2-Dec-11 9 2-Dec-11 10 11 2-Dec-11 2-Dec-11 12 13 14 2-Dec-11 2-Dec-11 Action Item Comments/Resolution Status Owner EPA Date Completed Research scheduling\process involved in the 2008 Five Year ROD Review to aid in planning for 2013 Five Year ROD Review; particularly, time required for EPA’s review cycle on protectiveness reviews and legal review. This will help establish enforceable dates. Closed Will do addendum to 2008 FYR. Verify if the re-opened RI satisfies the 2008 Five Year ROD Review recommendations. Verify that the use of DEC guidance (i.e., common sense EPA guidance needs to be followed. approach) on sediments is acceptable to EPA. Inquire internally; pending as of 07DEC11. Review changes to Worksheet 12 for WP45/SS57 QAPP. Closed Closed EPA 29-Nov-11 Confirm the policies regarding 10/90 percent split of full and cursory validation to be performed. Confirm with Earl. Closed ADEC 2-Dec-11 Review last changes regarding IDW characterization in Worksheet 14 for WP45/SS57 QAPP - pending as of 05DEC11. Send ST48 QAPP template to A. Lambert; followed by DEC review to start on 09DEC11; DEC to review and reconcile with EPA by 12-13 DEC11 when it will be distributed to all. Send out ST48 QAPP template to group prior to meeting on 15DEC11. This will include the review of and reconciliation of the approach on background for metals. A. Lambert to distribute after review by DEC. Research scheduling\process involved in the 2008 Five Year ROD Review (FYR) to aid in planning for 2013 FYR; particularly, time required for EPA’s review cycle on protectiveness reviews and legal review. Minutes to be sent out for the following meetings: 18-21 OCT11 RAB Meeting; 10NOV11 RPM Workgroup Meeting for Garrison Slough; 15NOV11 Meeting on Document Prioritization; 23NOV11 meeting on RTCs for WP45/SS57 SRI QAPP final Submit project schedule in MS Project format. On hold until the MS Excel version is finalized. Send materials for the Garrison Slough RTCs meeting (including revised worksheets) to AF for distribution to team. Submit PMP for Garrison Slough; this is an enforceable date. Submit draft IWMP; this is an enforceable date. Closed Old No. 29-Nov-11 13 EPA 5-Dec-11 14 Closed EPA 15-Dec-11 16 12 13 EPA 7-Dec-11 15 Closed EPA 14-Dec-11 17 Closed EPA 14-Dec-11 19 Closed Closed USAF USAF No completion date specified 48 5-Dec-11 49 Closed USAF 29-Mar-12 Closed USAF 17-Jan-12 98 106 Page 2 of 29 Closed USAF 13-Jan-12 Closed USAF 13-Jan-12 107 108 Eielson AFB RPM Decision Tracker NON-RESTRICTED - CLOSED ACTION ITEMS Updated as of 30OCT2013 No. 15 Date Created 2-Dec-11 2-Dec-11 16 2-Dec-11 17 2-Dec-11 18 2-Dec-11 19 2-Dec-11 20 21 2-Dec-11 7-Dec-11 22 7-Dec-11 23 7-Dec-11 24 7-Dec-11 25 26 27 7-Dec-11 7-Dec-11 Action Item Comments/Resolution Status Owner Date Completed Submit PMP for WP45/SS57; this is an enforceable date. Closed USAF 13-Jan-12 Submit Final v.2 UFP SRI QAPP for WP45/SS57; this is an enforceable date. Final V.2 QAPP for WP45/SS57 will refer to Generic QAPP for VOCs by TO 15 SIM. Closed USAF 30-Dec-11 Send out Garrison Slough Scoping Meeting documents to group for review before the meeting on 06JAN12. J. Neubauer to send documents to C. Radu to distribute in D. Beistel’s absence. Submit a two-page tech memorandum on path forward with 2013 FYR driver for EPA/DEC review. Note: K. Beutel provided a first draft on 02DEC11. Submit project schedule in MS Excel format. C. Radu. Completed by M. Wilkinson and discussed by stakeholders on 07DEC11. Provide to stakeholders target analytes and achievable detection limits for TO-15 Selected Ion Monitoring. Details will be captured in the Generic QAPP. Note: Final V.2 QAPP for WP45/SS57 will refer to Generic QAPP for VOCs by TO 15 SIM. Distribute WS #15 updates for the Generic QAPP. Technology Evaluations/TI waiver ST 56, Engineer Hill – needs 2008 FYR addendum as well. Action item deferred as not appropriate to evaluate at this time. If possible, send out a good example of recommendations/conclusions before the meeting to discuss SER001-2008 Phase II Report recommendations/conclusions. To ask K. Boateng regarding how many sampling events are required for the IWMP, and if it is acceptable if we have 2 sampling events for existing wells and 1 for new wells. 2008 FYR Addendum to be completed for SS67 and WP45/SS57. A. Lambert will draft addendum and send to K. DeRuyter and D. Beistel with the purpose of the Addendum, the current flutters from EPA and ADEC, and summarize the actions to date and path forward. This will need to go to the EPA Region 10 Division Director for approval. Due date not specified at this time, before 2013 FYR; to be added to schedule after date is determined. Closed Resend 15NOV11 Meeting Minutes to group without Adobe anomalies. Research 1998-99 detection limits for PCB 03MO9. Send out memo with data. Closed USAF 5-Dec-11 Closed USAF 27-Apr-12 Old No. 109 114 USAF 30-Dec-11 117 Closed USAF 7-Dec-11 118 Closed USAF 7-Dec-11 119 Closed USAF 2-Dec-11 121 Closed Closed USAF EPA Completed 25-Jul-12 124 5 Closed ADEC 9-Dec-11 12 Closed EPA 15-Dec-11 18 Closed USAF/ADEC/EPA 25-Jul-12 20 Page 3 of 29 47 52 Eielson AFB RPM Decision Tracker NON-RESTRICTED - CLOSED ACTION ITEMS Updated as of 30OCT2013 No. Date Created 7-Dec-11 28 29 30 7-Dec-11 7-Dec-11 15-Dec-11 31 15-Dec-11 32 33 34 35 36 37 15-Dec-11 20-Dec-11 20-Dec-11 20-Dec-11 20-Dec-11 20-Dec-11 38 20-Dec-11 39 20-Dec-11 40 20-Dec-11 41 42 20-Dec-11 4-Jan-12 43 44 45 46 47 4-Jan-12 4-Jan-12 6-Jan-12 31-Jan-12 Action Item Comments/Resolution Status Owner USAF Date Completed Send out the draft schedule summary spreadsheet revised in the 07DEF11 meeting, and send out the IWMP spreadsheet to group for an informal, discussion purposes only review. Provide Organizational Chart for generic QAPP for review. Closed Closed USAF 7-Dec-11 Post on SharePoint the Lab Control Limit files. SS35 Drum Removal: Evaluate the Interim Removal Action (IRA) or Emergency Removal Action (ERA) procedures per contracting and Eielson AFB procedures. Closed Closed USAF USAF 7-Dec-11 27-Jun-12 Send out 02DEC11 Meeting Minutes and Review / Finalize Previous Minutes: 18 – 21 Oct, 10 Nov, 15 Nov, 23 Nov, 02 Dec, 07 Dec, 15 Dec, 20 Dec Send 2003 letter report to parties for review. Review Tables 15 for SW, sediment, and addition of TO15SIM to air table. Review lab limits for Generic QAPP Review Tables 15 for SW, sediment, and addition of TO15SIM to air table. Review lab limits for Generic QAPP Setup Alert for the Eielson AFB SharePoint Announcements. See quick instructions available in the Documents > 05 Guides. Setup Alert for the Eielson AFB SharePoint Announcements. See quick instructions available in the Documents > 05 Guides. Decide what type of sample will be collected for metals analysis (both dissolved and total or just dissolved) if turbidity stabilizes in a well above 5 NTU. Tech Memo from EA to Regulators on the subject. Setup Alert for the Eielson AFB SharePoint Announcements. See quick instructions available in the Documents > 05 Guides. Send out all lab limits for Generic QAPP. Review FOIA language with legal to determine if it should be removed or only apply to specific sections in ST48 QAPP Edit ST48 WS15 to reflect changes in handling of detection limits. Draft language to address Sampling Rationale column in Table 11-1 Field Sampling Program ST48 Draft letter for stakeholder acceptance of electronic submittals process for Draft and Draft Finals. (Findlay) Reviewed and Commented on Pending Meeting Minutes: 18-21 Oct, 10 Nov, 15 Nov, 23 Nov Closed Old No. 7-Dec-11 120 122 123 26 USAF 12-Jan-12 45 Closed Closed USAF ADEC 12-Jan-12 29-Feb-12 113 Closed Closed ADEC EPA 29-Feb-12 29-Feb-12 9 Closed Closed EPA ADEC 29-Feb-12 12-Dec 10 8 9 11 Closed USAF Completed 46 Closed USAF 27-Apr-12 55 Closed USAF Completed 110 Closed Closed USAF USAF/EPA 20-Dec-11 16-Feb-12 116 44 Page 4 of 29 Closed USAF 9-Jan-12 Closed USAF 9-Jan-12 Closed USAF No due date specified Closed ADEC 31-Jan-12 111 112 115 10 Eielson AFB RPM Decision Tracker NON-RESTRICTED - CLOSED ACTION ITEMS Updated as of 30OCT2013 No. Date Created 16-Feb-12 50 54 55 Owner Closed USAF 16-Feb-12 Garrison Slough QAPP Draft v2 Delivery Closed USAF 16-Feb-12 Final SER001-2008 Changes: Make changes to recommendations and executive summary. Add note regarding 2-party agreement and make modifications to schedule. Remove FOIA statement from SER001-2008 report Send RTCs on Final v.2 QAPP for SRI at WP45/SS57 Resend files for SER001-2010 RTC to Dave Beistel SS50-52 (Blair Lakes): Review March 1995 Permafrost Study. ST48: Conduct site visit at ST48 Cooling Pond next time 27JUN12-Site visit scheduled for 29 July 2012. A. Lambert is in Fairbanks. ST13/DP26: USAF will see if they can access grassy area Mark\Dave confirmed access to grassy area. Well install at this near building 1232; if so, add staff gauge near building location dependent on utility clearance. 1232. Another option is to the left of well 26-14 (if security permits access). SS50-52 (Blair Lakes): Locate and distribute permafrost study to stakeholders for hydrogeologists to review. Closed USAF Locate March 1997 CRREL report on ST48 Groundwater Transport Modeling Study to distribute to stakeholders. Closed 16-Feb-12 16-Feb-12 12-Mar-12 12-Mar-12 12-Mar-12 56 12-Mar-12 57 12-Mar-12 58 Status 16-Feb-12 51 52 53 Comments/Resolution Closed 48 49 Action Item Follow-up with Amy Dahl on her comment in paragraph 1 of comment No. 1 on the Draft Final v2 Generic QAPP regarding selecting the lowest of the EPA and Alaska screening levels rather than utilizing EPA values only if the Alaska Administrative Code did not specify a level for the respective compound. WP45/SS57 RI/FS Management Plan Delivery EPA Date Completed Old No. 29-Feb-12 11 19MAR12 EPA/ DEC Delivery Due 16MAR12 EPA/DEC Delivery Due 29-Feb-12 99 101 103 Closed Closed Closed USAF USAF ADEC/SLR 16-Feb-12 16-Feb-12 No due date specified Closed USAF/EPA 29-Jul-12 Closed USAF 6-Apr-12 104 105 7 28 41 Closed USAF 13-Mar-12 42 USAF 13-Mar-12 43 Page 5 of 29 Eielson AFB RPM Decision Tracker NON-RESTRICTED - CLOSED ACTION ITEMS Updated as of 30OCT2013 No. Date Created 12-Mar-12 Action Item Comments/Resolution SS50-52 (Blair Lakes): Check into topography data to add Follow-up: Blair Lakes figures only available in AutoCAD. to figures. No monitoring wells to be added for 2012 (PSG) Status Closed Owner USAF Date Completed 59 67 12-Mar-12 60 12-Mar-12 61 12-Mar-12 62 63 64 65 Old No. 27-Apr-12 12-Mar-12 12-Mar-12 12-Mar-12 ST49 Figure 11-3: Send someone out to ST49 to determine if 1301 wells are suitable for water gauging. If surface water bodies exist, add staff gauge to one of the 1301 wells (MW1, MW2, or MW3) on ST49 Figure 11-3. G. Manning confirmed wells are suitable for monitoring. Closed USAF ST20 (E9) Figure 10-1C: Add data for well 20MW20. Data not found for 20MW20. Mark suggested removing 20MW20 from Figure 10-1C, and show 20M20 as an existing well (on the assumption that they are actually the same well, which contractors have misidentified historically). Reference Data for 20M20 in 2002 SWMP Report (see Page 2-161). Figure 10 Global Change: Fix the bolded red colors on Figure 10 data points to be a more discerning color. Closed ST20 (E7) Figure 11-1A: Move well 20MO9B to well 20MO2. ST20 (E8) Figure 10-1B: Add data for well 20M19. Closed USAF Closed USAF ST20 (E9) Figure 11-1C: Move well 20MW31 west on the other side of the street nearby well 20PS12B. Closed USAF 6-Apr-12 70 USAF 6-Apr-12 71 Closed Page 6 of 29 USAF Will be incorporated into IWMP Will be incorporated into IWMP Will be incorporated into IWMP Will be incorporated into IWMP 82 83 84 85 Eielson AFB RPM Decision Tracker NON-RESTRICTED - CLOSED ACTION ITEMS Updated as of 30OCT2013 No. 66 Date Created 12-Mar-12 12-Mar-12 67 12-Mar-12 68 12-Mar-12 69 70 71 72 73 74 12-Mar-12 12-Mar-12 12-Mar-12 12-Mar-12 12-Mar-12 12-Mar-12 75 12-Mar-12 76 12-Mar-12 77 78 20-Mar-12 20-Mar-12 79 20-Mar-12 80 Action Item Comments/Resolution Status Owner ST20 (E9) Figure 11-1C: Move well 20MW30 to 20PS22V. ST20 (E9) Figure 11-1C: Instead of adding replacement well 20MO8B, add a replacement well near 20PP58. Closed USAF Closed USAF ST48 Figure 11-2: Add wells 48M04, 48MO5, and 48MO6 to the IWMP for sampling and revise language in Legend to say “Existing Monitoring Well, to be sampled under IWMP” SS14/ST10 Figure 10-5: Fix typos on Figure 10-5 where new wells on Figure 11-5 are illustrated on Figure 10-5 as existing monitoring wells. Revise Figure 10-5 to illustrate wells 10-2 and 10-2a. QC Figure 10-5 to ensure no misplaced wells/data from site specific QAPP. Closed SS14/ST10 Figure 11-5: Add well to area where well GMW-11 was. ST11 Figure 11-6: Add staff gauge next to well 11-9. Closed USAF Closed USAF ST11 Figure 10-6/11-6: Revise to say “Lined Water Treatment Pond” on both figures. ST13/DP26 Figure 11-7: Add staff gauging of Garrison Slough near well 26MW26. ST18 Figure 11-8: Remove wells 18-1B and 18PMWO1B. Closed USAF Closed USAF Closed USAF LF05 Figure 11-10: Move well 05MO1B south east (place above smaller pond), closer to Garrison Slough and add staffing gauge. SS31 Figure 11-11: Move location of well W-4B to north west, middle-left of current SS31 approximated boundary. Closed USAF SS14/ST10 Figure 11-5: Send G. Manning to determine if well 10MW17 is a serviceable well. If so, no need to add well 10MW11B. If 10MW17 is plugged, add well 10MW11B. Send out the decision points. SS14/ST10 Figure 11-5: Remove proposed well 10MW11B and use 10MW17 as replacement well instead. Closed SS61: Add staff gauge at Garrison Slough downstream and tie in the data from staff gauge at ST11. Closed Closed USAF USAF Date Completed Will be incorporated into IWMP Will be incorporated into IWMP Will be incorporated into IWMP Old No. 86 87 88 Will be incorporated into IWMP 89 Closed Closed Closed Page 7 of 29 USAF USAF EPA/TechLaw USAF USAF Will be incorporated into IWMP Will be incorporated into IWMP Will be incorporated into IWMP Will be incorporated into IWMP Will be incorporated into IWMP Will be incorporated into IWMP Will be incorporated into IWMP Will be incorporated into IWMP 90 91 92 93 94 95 96 102 Completed Will be incorporated into IWMP 76 Will be incorporated into IWMP 77 8 Eielson AFB RPM Decision Tracker NON-RESTRICTED - CLOSED ACTION ITEMS Updated as of 30OCT2013 No. Date Created 20-Mar-12 83 84 Closed USAF 20-Mar-12 SS35: Staff gauging at culvert in Garrison Slough. Closed USAF 20-Mar-12 SS37: Add a staff gauge in Garrison Slough where appropriate, or in include it with LF03. LF06: A. Lambert: Look into CERCLA/RCRA integration, find proper certificate of RCRA closure. Closed USAF 28-Mar-12 28-Mar-12 28-Mar-12 88 28-Mar-12 89 Owner ST27: Add collection sample from 25M05. 85 87 Status 20-Mar-12 28-Mar-12 86 Comments/Resolution Closed 81 82 Action Item DP25: Collect a sample from 25PS9 (if exists; if decommissioned install a replacement well at 25PS9). Collect water level from Unkown-01. Install one additional monitoring well between 25PS4 and B-6. USAF Date Completed Old No. Will be incorporated into IWMP 78 Per e-mail on 10JUL12 A. Lambert, EPA has determined that there Closed is no need for RCRA closure certificates at any of the historic Eielson landfills, with the exception of the RCRA closure of the munitions part of LF04. The closure certificates would be an administrative requirement (as Dave had thought) that is not needed due to the CERCLA / RCRA integration in the Eielson FFA. LF06: K. DeRuyter/K. Beutel: Find Sept. 11, 1992 (13pgs) Closed NOV for LF04 and other sites. WP38: E-mail boring logs to M. Wilkinson. Closed LF02: 1: Assess equipment and whether it is feasible to 27JUN12: Item 3 complete Closed install 4-inch wells. 2: Investigate whether surface water was ever sampled for dioxins at French Creek (K. DeRuyter requested), and 3: whether there were ever any salts/deicers used on this snow dump (A. Lambert). EPA LF04: EPA: A. Lambert: Find RCRA closure certificate. USAF/EPA Per e-mail on 10JUL12 A. Lambert, “EPA has determined that Closed there is no need for RCRA closure certificates at any of the historic Eielson landfills, with the exception of the RCRA closure of the munitions part of LF04. The closure certificates would be an administrative requirement (as Dave had thought) that is not needed due to the CERCLA / RCRA integration in the Eielson FFA. With regard to LF04 I thought and correct me if I am wrong, that the LF04 closure for the munitions portion of that site was closed under the RCRA program. If that is the case, then a RCRA closure certificate should probably be in the site file. I do not think the closure certificate for LF04 is a critical issue, however, I do think we want to find that certificate, or if we determine it is missing, we should probably take the appropriate steps to get one in the site file.” Per follow-up e-mail on 10JUL12 from EPA, this action item is completed. D. Beistel found the closure certificate. Page 8 of 29 Will be incorporated into IWMP Will be incorporated into IWMP Will be incorporated into IWMP 25-Jul-12 79 80 81 4 ADEC ASAP ADEC/SLR USAF ASAP 25-Jul-12 5 6 22 13-Jun-12 23 Eielson AFB RPM Decision Tracker NON-RESTRICTED - CLOSED ACTION ITEMS Updated as of 30OCT2013 No. Date Created 28-Mar-12 90 28-Mar-12 91 28-Mar-12 92 28-Mar-12 93 28-Mar-12 94 95 28-Mar-12 Decision Tree for IWMP: J. Socash: Develop a decision tree or flow chart to help select the type of well to use. J. Snyder: Write-up frost jacking solution. This action item was determined to no longer be necessary based Closed on decisions in the 11APR12 meeting minutes. USAF Closed USAF Date Completed 36 All Sites Addressing PSG Work: Write PSG Work Plan Addendum 2 of IWMP. Modify IWMP text and worksheets accordingly to reference PSG work plan addendum. Change Background Study Addendum to Addendum 1 and PSG work plan will be Addendum 2. WP38: Evaluate 38M06 to see if it can be useable, or water levels can be measured. Will be verified in the field. Inaccessible now due to snow/permafrost. WP38: Make changes per DPs. Find old figures that show tank locations at top of ski hill (see OU6 RI/FS and soil gas data (AR288)). Organize existing data (survey, well log tables, groundwater elevation data, etc.) and review, develop figures that show groundwater and elevations of bedrock (subcrop map of the bedrock). Make contour maps if possible (talk to K. Waldron) NA 37 27-Apr-12 60 Closed USAF 27-Apr-12 61 Closed USAF 27-Apr-12 65 19-Apr-12 ST58: TI Waiver boundary needs to be added to figure for this site (see 2008 ROD FYR, Figure ST58-1, parallels west side of Wabash Ave and end at edge of parking lot (PMW01)), extends west of 58PMW03 location. Closed USAF 28-Mar-12 SS64: Fix figures per DPs. Closed USAF 28-Mar-12 LF02: R. Mullen: Fix figures per DPs. Closed USAF 28-Mar-12 LF04: Fix figures per DPs. Closed USAF 100 29-Mar-12 29-Mar-12 Old No. 11-Apr-12 USAF 97 102 Owner USAF 27-Apr-12 28-Mar-12 101 Status Closed USAF 96 99 Comments/Resolution North Boundary Wells: Fix figure per DPs and figure markClosed ups from meeting. North Boundary Wells: Verify if existing well 51MB3 is Alex confirmed that he went out to the NBW 51MB3 and there is Closed serviceable (not frost jacked). Find the well logs or field slight frost-jacking, so leave as no sampling under IWMP on figure; verify well diameter, water level for wells at this site. will be re-verified in field. 28-Mar-12 98 Action Item SS63: Find removal report noted in footnote of 16MAY95 report (AR360) and send out to parties for review. 66 69 Will be incorporated into IWMP 72 Had this AI in for the 20MAR12(EA) draft minutes, but this should come out., since in the 28MAR12 meeting it was decided that 2inch will be fine for short-term monitoring at this site (similar to DP for LF06) ICs/LUCs: Scope the work involved in developing a Basewide Interim IC/LUC Plan. ICs/LUCs: D. Beistel will look into Div 1 Specs and 27JUN12-Determined not to be applicable. contractor-signed certificates. Page 9 of 29 Will be incorporated into IWMP Will be incorporated into IWMP Will be incorporated into IWMP Closed USAF 30-Sep-12 Closed USAF 27-Jun-12 73 74 75 21 27 Eielson AFB RPM Decision Tracker NON-RESTRICTED - CLOSED ACTION ITEMS Updated as of 30OCT2013 No. Date Created 29-Mar-12 103 29-Mar-12 104 29-Mar-12 105 29-Mar-12 106 29-Mar-12 107 29-Mar-12 108 9-Apr-12 109 9-Apr-12 110 9-Apr-12 111 9-Apr-12 112 9-Apr-12 113 9-Apr-12 114 Action Item MMRP Mailing List: Request USACE to add A. Lambert to USACE mailing list to receive any Eielson AFB MMRPrelated reports. Schedule: Review/re-visit the Path Forward memo/schedule to address EPA/DEC suggested changes. RAB Meeting Public Announcements: D. Beistel will get approval from Public Affairs for announcement and flyers. K. Findlay will post announcement in newspapers and post flyers at designated areas in North Pole\Moose Creek. RAB Meeting Presentation: Prepare presentation materials and work with parties to complete prior to week of 19 April 2012. Path Forward Memo: Update USAF due date for IWMP QAPP Draft Final on schedule to 22 April 2012. Send D. Beistel edits to Path Forward memo. Move outstanding minutes for December to March out of Pending folder to their appropriate meeting archive folders on SharePoint and mark as DRAFT. IWMP RTCs Comment 32: K. DeRuyter will check for a reference for the depth of the groundwater aquifer in the Tanana Flats region, and if she does not find one she will see if Ann Farris has some resources. Per Kim, this should not be on AI list; internal action item. WP33: A. Lambert needs to review permit with EPA NPDES specialists. K. DeRuyter: Review NPDES Permit to see what analytes are being tested. IWMP RTCs Comment 15: Changed MNA to geochemical parameters. Locate MNA EPA guidance and distribute to group. IWMP RTCs Comment 59: If possible, provide a prioritized list of borings to GPS. 50ft or deeper wells should be measure for groundwater/surface water elevations. WP33: Follow-up with Eielson Water Compliance Manager on history of dredging activities. Need to gather the existing sampling data, if possible. IWMP RTCs Comment 63: Check into whether 4-inch (drilling ROD) pilot hole is possible to minimize risks. 2inch is fine, but may be better to step up to 4-inch for sample recovery. K. DeRuyter suggested adding this to the decision tree and agreed with Jay about keeping all tools/options available. Comments/Resolution Status Closed Owner USAF Date Completed Old No. Completed 32 Closed USAF 25-Apr-12 35 Closed USAF 6-Apr-12 40 Closed USAF 13-Apr-12 68 Closed USAF 30-Mar-12 97 Closed USAF 2-Apr-12 100 Closed ADEC 31-May-12 4 Kim clarified that Dave needed to provide PAH data; it’s unknown Closed if PAH sampling is included in the IWMP QAPP. Katie verified that PAH data is included in the IWMP QAPP. Closed EPA/DEC 31-May-12 6 EPA Completed 7 Closed USAF 25-Apr-12 33 Closed USAF 25-Apr-12 34 This action item was determined to no longer be necessary based Closed on decisions in the 11APR12 meeting minutes. USAF NA 38 Page 10 of 29 Eielson AFB RPM Decision Tracker NON-RESTRICTED - CLOSED ACTION ITEMS Updated as of 30OCT2013 No. Date Created 9-Apr-12 115 116 9-Apr-12 9-Apr-12 117 9-Apr-12 118 119 9-Apr-12 11-Apr-12 120 11-Apr-12 121 11-Apr-12 122 Action Item Comments/Resolution Status Owner Date Completed Well Construction Follow-up: If possible, list of Source This action item was determined to no longer be necessary based Closed Areas that have had issues with turbidity and frost jacking on decisions in the 11APR12 meeting minutes. and include this into the decision tree/solution Have prepared for Wednesday meeting to finalize discussion. USAF WP33: Fix figure per DPs and figure mark-ups from meeting. IWMP RTCs Comment 64: Check SOP to ensure changes made in worksheet 14. Create figure of well construction w/out depths. IWMP RTCs Comment 45: Add FOC soil analysis to select source areas to evaluate plume stability and eventual MNA for hydrocarbons. Joann and Jay will review Table 11-1 to select some sites to collect FOCs in soils. Closed USAF 27-Apr-12 Closed USAF 27-Apr-12 SS36 Well Placement: Make changes per DPs and marked-up figures. RPMs to evaluate and review the Project Cost Estimating Assumptions Document (PCEADs) for the next fiscal year funding. Verify that there are no sampling areas in the IWMP planned downstream from a pressure tank at Engineer Hill. Need to discuss and consider collecting soil from source areas (need to identify areas) for possible later analysis, and look into locations available sediment sample storage (Comment 64). Closed USAF 27-Apr-12 Rescheduled meeting for 27 Sept. Held meeting 27 Sept.; will meet again to revisit. Closed ADEC/EPA 21-Jan-13 Reference Comment 66, Worksheet #14, pg. 14-6. This must be done before sampling. Closed Old No. NA 39 58 59 Closed USAF 27-Apr-12 63 6 RPMs decided to collect and store samples per QAPP. In the Closed 27JUN12 RPM monthly meeting, the RPMs discussed their various experiences and ideas on soil collection and storage for later soil properties testing. Mr. Shirley stated that in his experience, very often, soils or other type of samples are collected to analyze later, and nothing is ever done with the samples, the labeling fades or is otherwise destroyed, the tracking documents are lost, or the samples themselves are lost. Mr. Shirley does not support samples for physical analysis at a later date because if the physical analysis is important, then it should be accomplished at the time the samples are collected. According to the Site Specific IWMP QAPP, the last paragraph on Page 14-3 states the following: “Disturbed soil samples will be collected for each source area from different soil types encountered from within the vadose zone and aquifer. Soil will be transferred from soil cores into polyethylene bags, labeled, and stored onsite. Following completion of well installation, boring logs will be reviewed and select samples will be submitted to a laboratory for grain size analysis (by ASTM D422).” Page 11 of 29 64 USAF TBD 13 USAF/EPA/ADEC 25-Jul-12 16 Eielson AFB RPM Decision Tracker NON-RESTRICTED - CLOSED ACTION ITEMS Updated as of 30OCT2013 No. Date Created 11-Apr-12 123 11-Apr-12 124 11-Apr-12 125 23-Apr-12 126 23-Apr-12 127 128 27-Apr-12 27-Apr-12 129 27-Apr-12 130 27-Apr-12 131 27-Apr-12 132 133 31-May-12 Action Item Comments/Resolution Status Owner USAF Date Completed IWMP RTCs Changes: Add text to Worksheet #14, pg. 143 (Comment 65). Add wording from WP45/SS57 QAPP that clarifies and specifies instructions about re-using downhill tubing (Comment 70). Edit Worksheet 14 groundwater task to clarify we will collect the depth-togroundwater readings concurrently with parameters (Comment 79). SS36/SS39/SS63/ LF03/FT09 Well Placement Changes: Make changes to figures\IWMP QAPP per DPs. Closed K. Waldron will discuss with J. Snyder and M. Wilkinson the exact plans for production wells to avoid problems with geoprobe equipment in the field (Comment 74). J. Snyder will look into whether seal/gaskets can be used for hollowstem augers (Comment 85). J. Snyder\ and K. Waldron will discuss options for silty locations (Comment 86). Closed WP45/SS57 RI/FS Management Plan Draft: Discuss with Cristina to revisit plan based on regulatory feedback to use Elmendorf AFB approved RI/FS Mgt. Plan as a basis for structure, organization, and language for use as boilerplate material. WP45/SS57 QAPP Final v3: Mark\Kyle need to follow-up with Cristina to verify all comments were addressed in v3. Closed Minutes Pending Signature: Review/Comment/Sign Pending Meeting Minutes: April 9th, May 30th Institutional Controls: Dave to draft a new letter to 27JUN12-Not applicable as it will be handled by legal. address ICs (i.e., what has been done so far, what is planned, specifies dates, when and what type of training is planned, and ensure to compare the two prior letters so nothing is missed in the new letter draft). Closed USAF/ADEC/EPA 27-Jun-12 Closed USAF 27-Jun-12 Dave will address the Site-Specific QAPPs and other document changes in the Path Forward Memorandum and will send out as soon as possible. IWMP QAPP Well Construction Approval: Mark will email EPA\DEC requirements regarding interim approval. Closed K. Findlay will gather marked-up IWMP well placement figures to include in next submittal, update schedule per Decision Points, and coordinate print production of the Draft Final 3386 hard copies printed and shipped. Closed DSMOA budget update (added to upcoming meetings, scheduled for 29 June). Closed Old No. 27-Apr-12 56 Closed USAF 27-Apr-12 57 USAF 27-Apr-12 62 USAF 27-Apr-12 53 Closed USAF 27-Apr-12 54 29 30 USAF 27-Jun-12 31 Closed USAF 27-Apr-12 50 USAF 5-May-12 51 Page 12 of 29 ADEC/USAF 27-Jun-12 3 Eielson AFB RPM Decision Tracker NON-RESTRICTED - CLOSED ACTION ITEMS Updated as of 30OCT2013 No. Date Created 27-Jun-12 Action Item Meet to discuss outline for the VI WP addenda. 134 27-Jun-12 135 27-Jun-12 136 27-Jun-12 137 138 27-Jun-12 27-Jun-12 139 27-Jun-12 140 141 142 143 144 27-Jun-12 27-Jun-12 27-Jun-12 27-Jun-12 27-Jun-12 145 146 27-Jun-12 27-Jun-12 147 Comments/Resolution Sent VI Addendum review documents to RPMs 9 Aug 2012. Documents included: List of Elements to be Included in a VI Addendum (Word file) and Table 1 Building Characteristics for Vapor Intrusion Evaluation (Excel file). Status Closed Owner USAF Date Completed Old No. 2-Oct-12 2 Determine if fish sampling can be completed prior to the collection of sediment samples with mercury samples being sent out immediately after collection and the remainder of the fillets frozen and stored. Review the fish collection methodologies mercury laboratory analysis proposed in QAPP since sampling will occur prior to QAPP approval. Review screening levels for Worksheet 15 tables and text Previous supporting item (“USAF to provide materials for review by for replacement in all ongoing QAPPs. 8 Aug was accomplished when Cristina Radu sent tables on 9 Aug for RPM review. Revise the Path Forward Memo to address 22 sites with Path Forward Memo draft has been submitted and is circulating; NFA. would like to have comments received and document approved for final by 6 July 2012. ADEC wants to ensure concurrence on the method selected, and would like language added to Path Forward Memo. EAFB will develop a brief contaminated soil Work Plan This is intended for small construction projects. This will be added template for contractors. as an agenda item for the RPM monthly meeting. The next RAB Meeting was re-scheduled for 17 October Confirmed Salcha Elementary School gym for next RAB meeting 2012 (Note – 18 October 2012 was initially proposed, but on 23 Aug 12. was moved due to the Alaska Day holiday). USAF needs to determine location and develop agenda for meeting. October RPM Monthly Meeting will be scheduled for 17 October 2012. Update the existing Document Schedule for upcoming PDF copies of the new MS. Project schedules for IRP and CRP FYR activities. Add working meetings and other activities documents and other activities were sent to RPMs on 22 Aug to schedule. 2012. These schedules were uploaded to SharePoint under the Schedules library. Report from Technical Assistance Visit will be distributed Will be distributed and uploaded to SharePoint site 29 August. to RPM Team. Schedule a Triad Meeting to discuss sampling locations Sent meeting invite 22 Aug 12. Meeting held 24 Aug 12. Follow-up for WP45/SS57. meeting scheduled for Thursday, 30 August 2012. Schedule a meeting for the chemists to discuss screening levels and tap water RSLs. Training presentation on the PCEAD process for the RPM Team. Schedule a meeting to discuss programmatic changes to document the most efficient way to update previously approved documents. Create an “Other” document tab on the current schedule. Closed ADEC/EPA 12-Jul-12 Closed USAF 3-Jul-12 Meeting scheduled for 17 July 2012 at 0830 between ADEC and EAFB to discuss the sites for inclusion to the 2party agreement. Closed USAF 27-Jun-12 2 Closed EPA (A. Lambert) 31-Aug-12 2 Closed USAF (D. Beistel) 5-Oct-12 4 Complete USAF (C. Tallant) 30-Jan-13 Closed USAF 29-Aug-12 8 9 Closed USAF 29-Aug-12 10 Closed AFCEE (J. Socash) 3-Aug-12 Closed USAF (D. Beistel) 15-Aug-12 Closed USAF/ADEC/EPA 25-Jul-12 Closed AFCEE (C. Morriss) 25-Jul-12 Closed USAF/ADEC/EPA 25-Jul-12 13 14 17 18 19 24 25 Page 13 of 29 Eielson AFB RPM Decision Tracker NON-RESTRICTED - CLOSED ACTION ITEMS Updated as of 30OCT2013 No. 148 Date Created 28-Jun-12 28-Jun-12 149 25-Jul-12 150 25-Jul-12 151 152 25-Jul-12 25-Jul-12 153 25-Jul-12 154 155 156 25-Jul-12 25-Jul-12 25-Jul-12 157 25-Jul-12 Action Item Comments/Resolution Prepare a response to the EPA and ADEC’s draft Five Year Review Addendum for WP45/SS57 and SS67. Provide a draft Five Year Review Addendum for WP45/SS57 and SS67 to the USAF by November Monthly Meeting. Determine how detailed the CRP schedule for the Two Party Agreement needs to be. A follow-on to action item #13. No longer needed as an AI as the FYR Addendum may or may not occur This is pending whether the FYR Addendum will be necessary. There will be no 2008 FYR Addendum. This will be captured in the 2013 FYR. RPMs agreed this item could be closed as until the Two Party Agreement is in place, the CRP schedule details cannot be determined. Will be addressed in the RTCs to the MPs Provide a letter to ADEC and EPA with recommended path forward for ARARs for all of the Records of Decision. 160 29-Aug-12 163 29-Aug-12 164 TBD Old No. 8 12 Closed Closed DEC (E. Breitenberger) 26-Sep-12 USAF (S. Lufkin) 41178 1 Closed USAF (1. D. 14-Sep-12 Beistel/2. S. Parker) Identify the date for the next Eielson MAP. Evaluate repercussions of potential investigation of MMRP contractor. Sky Research is still on board. Provide updated list of documents that need to be in at least draft final stage such that data can be incorporated in the draft Five Year Review currently scheduled to be submitted on 1 May 2013. Submit a revised schedule for WP45/SS57 and SS67. Completed Closed Provide letter to memorialize decision to transfer Taxiway Golf site from SER program into the CRP. Conduct a scoping meeting to discuss innovative technologies to be evaluated at chlorinated solvent sites within the scope of the IWMP. Deliver letter responses (to the two informal dispute notices) proposing a path forward for WP45/SS57 and SS67. Provide an update to stakeholders concerning effort to expedite contract packages for initiating field work at WP45/SS57 and SS67. Formally notify EPA and ADEC legal counterparts that the CRP PA/SI will be designated a Phase 1 SER. 29-Aug-12 EPA (A. Lambert) USAF (D. Beistel) 29-Aug-12 162 Complete Closed Suggest a prioritization of CRP sites. 161 Date Completed 26-Sep-12 Decision Point was reached during RPM Meeting. Minutes will be signed. Bldg 1211 response should explain why the two sampling events were missed. The AAFES Demolition Supplemental Information package was sent on 13 Sep. Conduct a meeting to walk through base-wide Regulators conducted site visit on 26 July. USAF will schedule construction practices to include a discussion on the LF-06 time the week of the October RPM monthly to have regulators on excavation and the Arctic Survival School excavation. base for demonstration/walk-through visit. 25-Jul-12 29-Aug-12 Owner USAF (D. Beistel) 1 Document a modified FFA review schedule and obtain RPM signatures. Provide response to letter dated 20 June 2012 concerning 1. Building 1211 AAFES service station interim removal 158 159 Status Closed Develop the path forward. Closed 3 5 25-Oct-12 7 PDF copies of the new MS. Project schedules for IRP and CRP Closed documents and other activities were sent to RPMs on 22 Aug 2012. These schedules were uploaded to SharePoint under the Schedules library. Pending resolution of Informal Dispute. Schedule will be updated Closed once resolved. Jacobs sent updated schedule for WP45/SS57 field work. Will provide list before meeting. Closed No longer necessary; DF QAPP written/issued 9/26 under SER (IRP) program. Meeting scheduled for 10/2. USAF (D. Beistel) 26-Sep-12 Closed Closed AFCEC (P. Roth) 14-Nov-12 USAF (Dave Beistel) 29-Aug-12 USAF (Cristina Radu) 1-Aug-12 USAF (D. Beistel) TBD 10 11 12 14 USAF (Carolyn 24-Aug-12 Tallant) US EPA (A. 30-Aug-12 Lambert) USEPA (A. Lambert) 2-Oct-12 15 1 3 Letter sent and received. Closed USAF (D. Beistel) 30-Aug-12 4 Contract will be awarded by end of the week. Accomplished 11 Sep 2012 in Steve Lufkin’s discussions with ADEC and EPA counsel. Page 14 of 29 Closed Closed USAF (J. Socash/K. Thomas) 26-Sep-12 USAF (S. Lufkin) 26-Sep-12 6 7 Eielson AFB RPM Decision Tracker NON-RESTRICTED - CLOSED ACTION ITEMS Updated as of 30OCT2013 No. Date Created 29-Aug-12 165 166 167 26-Sep-12 26-Sep-12 26-Sep-12 168 26-Sep-12 169 11-Oct-12 170 11-Oct-12 171 172 17-Oct-12 17-Oct-12 173 174 17-Oct-12 17-Oct-12 Action Item Date Completed Update on proposed SER process flow chart for potential adoption. Review the most recent EPA guidance on FYR to confirm that the 2008 FYR outline is acceptable to use for the 2013 FYR. Determine if SER sites will be mentioned in the 2013 FYR in terms of protectiveness. Document the abandoned piping at DLA Rail Line project. Complete RPMs 30-Jan-13 Completed EPA (A. Lambert) 14-Nov-12 This cannot be adopted at this time due to the lack of 2-party agreement. Closed Closed Closed Closed TBD USAF (Julene May) USAF (Joann Socash) USAF (Joann Socash) 3-Oct-12 3-Oct-12 USAF (D. Beistel) 17-Oct-12 5 Completed EPA (A. Lambert) 26-Oct-12 15 Completed EPA (A. Lambert) 26-Oct-12 16 17 18 This will be addressed in bi-weekly FYR scoping meetings. Complete Check with Jay Klaassen on USACE Report. This will be converted Complete to an upcoming meeting. EPA (A. Lambert) 18-Dec-12 30-Jan-13 Provide update on status of Settlement Agreement. Closed 14-Nov-12 Provide response to ADEC's 13 Nov 2012 letter concerning PFOA/PFOS. Provide update on progress related to 15 Apr 2012 letter concerning IC/LUCs. Closed USAF D. Beistel) 12-Dec-12 Closed USAF (D. Beistel/Julene May) 18-Dec-12 14-Nov-12 2 3 14-Nov-12 14-Nov-12 1 3-Oct-12 Complete 177 Old No. 11 Build in surveying task for Garrison Slough in next PCEAD cycle for execution in FY2014. Build in development of ESD. Inform regulators whether CSM updates will be Available data will be used in FYR incorporated into the FYR. 14-Nov-12 181 Owner US EPA (A. Lambert) USAF (Alan Simmons/Carolyn Tallant) USAF (D. Beistel/Joann Socash) USAF (D. Beistel/Kevin Thomas) USAF (Bob Shirley) 176 180 Status Complete 175 178 Comments/Resolution Begin writing the TI waiver section of the FYR addendum. This is pending whether the FYR Addendum will be necessary. There will be no 2008 FYR Addendum. This will be captured in the 2013 FYR. Conduct meeting to review IC/LUCs. Meeting scheduled 27 September. Conduct meeting to provide a recommended path forward Meeting scheduled 1 October. for WP45/SS57. Conduct meeting to provide a recommended path forward Meeting scheduled 27 September. for Garrison Slough and the interrelationship between sites SS67 and SS62. USAF needs to formally convey to ADEC and EPA its Will discuss during IC/LUCs meeting position if approval needs to be given for grounddisturbing construction at IRP sites. Provide a decision on what action levels to use (residential For methods TO15 and TO15SIM, for some compounds the or non-residential) for buildings that are not currently and method reporting limits (MRLs) exceed the lowest agreed upon are not planned for residential land use. action level (lowest of Alaska or EPA) for residential land use. However, several of the buildings present are clearly not for residential use (i.e., hangars). Aaron Lambert sent comments on 18 Oct, action item in progress. Provide a decision on alternate approaches to utilize for Some buildings, such as hangars, may have numerous potential buildings that may have numerous potential indoor air indoor air sources of VOCs due to aircraft maintenance activities. sources of VOCs due to aircraft maintenance activities. The potential indoor air sources may not be able to be removed for sufficient time to allow indoor air sampling to be completed. Aaron Lambert sent comments on 18 Oct, action item in progress. Propose to add as a standing agenda item for future RPM meetings. Send response to regulators on 15DEC12. Review this response at the 18DEC12 RPM conference call. Converted to a standing agenda item. Page 15 of 29 Closed 19 20 30-Jan-13 21 12-Dec-12 22 16-Nov-12 23 25 26 Eielson AFB RPM Decision Tracker NON-RESTRICTED - CLOSED ACTION ITEMS Updated as of 30OCT2013 No. Date Created 14-Nov-12 182 14-Nov-12 Action Item Add to a standing agenda item. Move to completed. Review Garrison Slough source area identifier draft decision point to determine consensus. 183 184 18-Dec-12 18-Dec-12 185 18-Dec-12 186 18-Dec-12 187 188 30-Jan-13 30-Jan-13 189 190 30-Jan-13 30-Jan-13 191 27-Feb-13 192 27-Feb-13 193 27-Feb-13 194 195 27-Feb-13 Comments/Resolution Begin a discussion (or schedule a meeting) on the most effective manner by which to incorporate GIS information with the complementary sampling data in future reports. Status Owner Date Completed ADEC/USAF (Eric Breitenberger/Pat Roth) 30-Jan-13 Proposed approach: “Terminology for Garrison Slough and Closed associated sub-sites has been presented in the Draft Settlement Agreement for Garrison Slough. The terminology used is very close to what the RPM team discussed during the November RPM meeting and consensus will be documented when the settlement agreement is finalized.” Complete USAF/ADEC/EPA RPMs 12-Dec-12 EPA/ADEC 24-Dec-12 Complete USAF (D. Beistel) 30-Jan-13 Complete regulatory review of D WP45/SS57 QAPP Addendum No. 1 for Photoshop Investigation. Request a 20-day extension for the DF Phase 2 Source Evaluation SS085-UIC Bldg 3386 due to holiday schedule. New due date will be 2 Feb 2013. Work with base leadership to determine why approval for Dig permit received. dig permits at WP45/SS57 is tied up in an ANG - Union Worker's legally defined 30 day review period. Disseminate letters to CIP mailing list and the Letters sent 24 January and copies received by regulatory RPMs. communities of Moose Creek, Salcha, and North Pole to recommend appointment or recruitment of community RAB members. USAF will send a summary email of contractual Completed on 26FEB13 via email from David Beistel. ramifications related to schedule changes. USAF will request a 30-day extension for delivery of the draft final Phase 2 SER QAPP for SS084 (AAA AOC 16) Complete 27 28 29 30 Complete USAF (J. May) 30-Jan-13 31 Complete USAF (K. Findlay) 24-Jan-13 32 Complete USAF (D. Beistel) 27-Feb-13 Complete USAF (D. Beistel) 31-Jan-13 33 34 2012 Field Effort Status Report will be provided to include updated figures and status of CSM Updates. Provide DEC/EPA with a response regarding CE notified bio environmental of solvent concerns and provided environmental health concerns for Bldg 1140, 1141, 1142. copy of PSG results on 30JAN13. CE will request response for occupation, safety, and health concerns. Verbal update provided by Carolyn Tallant at the 27FEB13 RPM meeting. Converted to agenda item for 25MAR13 RPM meeting (Carolyn Tallant). Closed USAF (M. Wilkinson) 4-Mar-13 Complete USAF (D. Beistel) Determine if it is necessary to revise the approved RI/FS Management Plans for SS67 and WP45/SS57 relative to the Risk Assessment Work Plan Research how the AF ERPIMS system has been handling and receiving data for CSM Updates and how it fits in with the FFA and CERCLA process. Provide roadmap identifying for each QAPP if there is a Generic or Site-Specific, and identify the Analytical Laboratory under contract for sample analysis. Provide an interim schedule update to stakeholders as soon as possible. Kevin Maher (Jacobs) will work with Patrick Roth on this action item. Closed What is the path forward after the CSM Update Report (i.e. Remedial Operations Performance Monitoring)? Complete Completed on 05 March by C. Radu. QAPP list distributed by K. Findlay 05 March. Closed 35 27-Feb-13 36 USAF (D. Beistel) 15-Mar-13 37 USAF (J. Socash) 24-Apr-13 38 USAF (C. Radu) 1-Mar-13 39 Closed Page 16 of 29 Old No. USAF (C. Radu) 13-Mar-13 40 Eielson AFB RPM Decision Tracker NON-RESTRICTED - CLOSED ACTION ITEMS Updated as of 30OCT2013 No. 196 197 Date Created 27-Feb-13 27-Feb-13 27-Feb-13 198 200 27-Feb-13 27-Feb-13 201 27-Feb-13 202 203 204 27-Feb-13 25-Mar-13 25-Mar-13 205 25-Mar-13 206 25-Mar-13 207 25-Mar-13 208 5-Apr-13 209 12-Apr-13 210 Action Item Comments/Resolution Status Owner Date Completed Provide Generic Construction Work Plan to Stakeholders Provided on SharePoint, under Regulatory Review. Closed USAF (C. Tallant) 1-Mar-13 Update the disturbed soils site map for Construction Site ID #40 Provide environmental update in construction spreadsheet. Indicate any environmental actions taken/needed/required during constructions activities. Determine path forward for RAB adjournment Provide clarification to EA on comments sent to EPA/ADEC for the SS084 (AOC 16/AAA) Draft Phase 2 Source Evaluation QAPP EA to provide RTCs table and changed pages to EPA/ADEC for review prior to the SS084 (AOC 16/AAA) Draft Phase 2 Source Evaluation QAPP RTCs meeting (05APR13) Provide a flow chart of how the document review process is supposed to work Include MMRP schedule in the MS Project master schedule. Confirm the upcoming WP45/SS57 and SS67 document submittals are accurately titled in accordance with their respective titles in the Settlement Agreement (i.e., SRI or RI). Determine if CERCLA covers how a CSM Update Report should be titled. ID #40 was inaccurately mapped Closed USAF (J. May) 25-Mar-13 Add a column, if possible. Closed USAF (J. May) 24-Apr-13 Old No. 41 42 43 Refer to DoD RAB Rule Handbook, EPA, etc. guidance. A. Lambert e-mailed clarifications on 01 March. Conducted meeting 05APR13, sent revised RTCs and changed pages on Draft doc for Regulatory Review. MMRP schedule was included in the Eielson Master schedule update distributed on 11APR13. A. Lambert confirmed the upcoming WP45/SS57 and SS67 documents are titled in the Settlement Agreements as RI, no reference to Supplement. IC/LUC Settlement Agreement same reference confirmed. Recommend calling it a CSM Update Technical Memorandum for brief report for inclusion in the FYR. When we have full reports in the future, what should they be titled? Closed Closed Complete USAF (D. Beistel) EPA/ADEC (A. Lambert/K. DeRuyter) USAF (K. Waldron) 25-Mar-13 5-Mar-13 45 46 1-Apr-13 47 Complete EPA/ADEC 24-Apr-13 Complete USAF (Beistel/Radu) 29-Mar-13 Complete EPA (A. Lambert) 48 49 24-Apr-13 50 Complete Provide a written statement of work for dredging of water treatment pond for Construction Update Discussion. Complete Regarding QAPP optimization, determine if there is a way AFCEC confirmed it is acceptable to have two or more ELAP to have 2-3 ELAP certified labs pre-approved certified labs pre-approved in a QAPP. EPA will confirm with QA/QC. Review Draft SS084 Phase 2 Source Evaluation QAPP revised RTCs and changed pages, and provide clarification if any responses as noted are not sufficient. Complete USAF (Socash/Jurena) 8-Apr-13 USAF (J. May) 24-Apr-13 51 52 Complete Vapor Intrusion under IWMP QAPP Addendum: a. Status: Part A was sent 19APR13 via memo. Verifying whether Complete Compile information relative to sample collection for Part B was addressed in the memo. Part B is covered in Table 17Radon analysis and analytical methods and calculation of 1 of the IWMP QAPP Addendum for VI. attenuation factors. ADEC (Todd Blessing) and EPA will evaluate the information for inclusion in the draft final QAPP Addendum. Compile justification for not collecting indoor/outdoor air samples at buildings 4377, 4378, 4387, and 6390. Page 17 of 29 USAF/EPA (Jurena/Lambert) 24-Apr-13 EPA/ADEC 12-Apr-13 53 54 USAF/EA (R. Casey, 19-Apr-13 B. Nuding, M. Kelley) 55 Eielson AFB RPM Decision Tracker NON-RESTRICTED - CLOSED ACTION ITEMS Updated as of 30OCT2013 No. Date Created 12-Apr-13 211 12-Apr-13 212 213 214 24-Apr-13 24-Apr-13 16-May-13 216 218 EPA (A. Lambert) 26-Apr-13 57 Do the Settlement Agreements override the RODs? Yes, per Steve Complete Lufkin. Completed 10 May 2013 Complete USAF (J. May) 16-May-13 USAF (J. Socash) 15-May-13 For ST20, ST48, SS35 source areas, which contractor is doing the Complete CSM Update Report and when? 26JUN13-EA will complete the CSM Reports matching the same format as Jacobs. USAF (P. Roth/P. Jurena) 26-Jun-13 Complete. Need to send to regulators. USAF/ADEC/EPA (C. Tallant) USAF (C. Tallant) 24-May-13 ADEC (K. DeRuyter) 7-Jun-13 Complete ADEC/EPA 31-Jul-13 14-Nov-12 16-May-13 Gauge Background Monitoring wells and provide comparison of Fall 2012 and current groundwater elevations to RPMs. Tabulate number of documents reviewed in FY13. Compile a prioritized SER/CRP site list. Provide ADEC/EPA with slides and handouts from the UEC course, including base supplements. Nominate workgroup members to develop procedure for utilizing the values in the background study in future investigation reports. This will be added to the IWMP Report introduction and will be a part of the redlined content that goes back to the regulators. Complete 58 59 61 Complete 31-Jul-13 215 Open Provide specific examples of previous reports that depict historical data on figures. Review clarification on the distinction of COCs and COPCs, use of FRGs, and explanation that MCL and State cleanup levels are not being ignored. 5-Jun-13 Old No. 56 Complete 26-Jun-13 224 Date Completed 25-Apr-13 Prioritize remaining sites on the CRP/SER list not Eric previously prioritized 37 SER sites. Item 24 will cover this previously prioritized and gain agreement from the RPMs. action item. 223 217 Owner ADEC/EPA (T. Blessing) 16-May-13 222 179 Status Closed Finalize the CRP/SER list 5-Jun-13 227 Comments/Resolution 16-May-13 219 221 Action Item Vapor Intrusion under IWMP QAPP Addendum: ADEC and EPA review the information provided by AF relative to sample collection for Radon analysis and analytical methods and calculation of attenuation factors and the additional justification provided for not collecting indoor/outdoor samples in select buildings (reference previous action item). This will be discussed in a conference call on 26APR13 Vapor Intrusion under IWMP QAPP Addendum: Determine what is the process to defer a site where VI was evaluated to OSHA? Sample collection time for indoor samples differs under VI evaluation and OSHA. Are indoor OSHA samples required to be met in buildings that store chemicals? Review requirements for IC inspection reports due per the Settlement Agreement sections 3.4 and 5.3.10. Section Provide feedback to Cristina Radu with dates for SMP and other scheduled activities. Convey to regulators what will be done with the CSM Update field data. 63 7-Jun-13 64 66 31-Jul-13 67 AF incorporated clarification into the Final IWMP Report issued 24 June 13. As of 2 July, this item was completed by Kyle Waldron. Complete USAF (M. Wilkinson) 31-Jul-13 68 Action completed 31JUL13. Action overtaken by PBR/MPO review. Closed on 28 AUG 2013. Complete Complete USAF (C. Radu) USAF (C. Tallant) 31-Jul-13 27-Aug-13 Closed on 28 AUG 2013. Complete USAF (C. Tallant) 27-Aug-13 All parties determine participants who should be a part of workgroup. Closed on 28 AUG 2013. Complete USAF/ADEC (D. 9-Aug-13 Beistel/K. DeRuyter) Update 28 AUG 2013: Converted to restricted action item R7. Page 18 of 29 72 24 62 69 Eielson AFB RPM Decision Tracker NON-RESTRICTED - CLOSED ACTION ITEMS Updated as of 30OCT2013 No. Date Created 31-Jul-13 Status Owner Date Completed USAF (C. Radu) Specifically, there are some data reports that are Secondary/Other Closed documents that do not have a Primary document to feed into. Of note, language in Sec 20.2 of the FFA says “they may” feed into Primary documents. OBE by SMP approval. EPA (A. Lambert/J. Kramer) 28-Aug-13 Provide a written statement (with timelines and lessons learned) concerning recent activity at containment cells. C. Tallant distributed this on 17 Sep 2013 USAF (C. Tallant/M. 11-Sep-13 Wilkinson) 29-Aug-13 Generate a letter for file confirming the 17 sites moving under state regulation. Generate a Geobase map to incorporate all spill sites within the airfield / flightline. Transmitted on 24 Sep 2013. 18 sites were listed on the multi-SER Closed report. Closed 5-Jun-13 220 228 233 Comments/Resolution Field Status Report for ST48, ST20, SS35 dissiminated on 1-Aug- Closed 13. 226 230 Action Item Disseminate ST48 data to enable RPMs to determine if sufficient data has been collected to properly delineate the boundaries of PAH. Discuss with regulatory agency attorneys on the interpretation of which documents are Primary and Secondary. 27-Sep-13 Page 19 of 29 Closed Old No. 6-Aug-13 71 24-Sep-13 65 USAF (D. Beistel) 24-Sep-13 USAF (D. Beistel) 30-Oct-13 Eielson AFB RPM Decision Tracker NON-RESTRICTED - Approved Decision Points Updated as of 30OCT2013 DP # Title 1 WP45/SS57 RI/FS MP RTCs Decision Point Topic(s) Draw source area boundaries for soil and groundwater based on 2011 field investigation RI/FS (boundary defined as results exceeding ADEC cleanup levels). In addition to recommendations described in the Technical Memorandum, the following will RI/FS be added: Collect soil samples from 4-5 ft bgs at locations SB06, SB16, and SB21 for analysis of volatile organic compounds (VOCs)./Collect soil samples from 4-5 ft bgs at locations SB05, SB06, and SB10 for analysis of polynuclear aromatic hydrocarbons (PAHs)./Complete three soil borings near MW13 and collect surface and vadose zone samples from each boring for analysis of lead./Submit Field Change Form to include analysis of lead for groundwater samples collected from permanent monitoring wells due to the detection of EDB in MW. Lead to be sampled in accordance with the Generic QAPP. Associated Meeting WP45/SS57 RI/FS MP RTCs Approach Meeting WP45/SS57 RI/FS MP RTCs Approach Meeting Mtg. Date 30-Aug-12 Status Approved 30-Aug-12 Approved Prepare an addendum to investigate Building 1183 (Photo Lab) for silver and total chromium as these analytes were not previously included in the QAPP, but are potential contaminants of concern associated with historic photo lab floor drains. Include figures or edits as follows: Add site figure depicting potential source areas (Fire Training Area, Dry Well at Building 1186, Former Maintenance Shed, Suspected Dry Well at Building 1206)./Add figure to identify Injection Locations./Do not show historical Source Area boundaries. Originally planned locations for the deployment of PSG samplers at WP38, the top of the ski hill, were revised. RI/FS WP45/SS57 RI/FS MP RTCs Approach Meeting 30-Aug-12 Approved RI/FS WP45/SS57 RI/FS MP RTCs Approach Meeting 30-Aug-12 Approved 30-Aug-12 Approved SER001-2010 (CS082) Site Characterization QAPP Scoping Meeting SER001-2010 (CS082) Site Characterization QAPP Scoping Meeting SER001-2010 (CS082) Site Characterization QAPP Scoping Meeting RPM Monthly Meeting 30-Aug-12 Approved 30-Aug-12 Approved 30-Aug-12 Approved 13-Sep-12 Approved 2 WP45/SS57 RI/FS MP RTCs 3 WP45/SS57 RI/FS MP RTCs 4 WP45/SS57 RI/FS MP RTCs 6 WP38 PSGs 7 SER001-2010 (CS082) Site Characterization QAPP Add Non-Aqueous Phase Liquid (NAPL) screening in the capillary fringe. QAPP 8 SER001-2010 (CS082) Site Characterization QAPP Use temporary wells for collection of a groundwater sample during Step 1. QAPP 9 SER001-2010 (CS082) Site Characterization QAPP Use permanent monitoring wells if collecting additional groundwater samples in Step 2. QAPP 10 ST48 PAHs Since the ST48 site has a large area of PAH contamination in surface soil that pose a direct contact exposure risk, the playground in close proximity to this site will also be sampled for PAHs to determine whether PAH direct contact exposure pathways present. PAHs 11 SS35 EM and GPR Survey RPM Monthly Meeting 13-Sep-12 Approved 12 SS67 The parameters for the EM and GPR Survey at SS35 were reestablished; and locations for EM, GPR 3 additional surface soil samples at SS35 was determined by the project team. The EM and GPR survey at SS35 will be completed according to the QAPP at the end of September. 3 additional surface soil samples, were added to SS35 between Garrison Slough and the Ball Fields. EPA, ADEC, and AF (David Beistel) conducted a site visit on 15 Nov 12. It was noted the FYR field conditions differed from what was anticipated. The slough had not frozen solid even though temperatures have been well below freezing. This differing site condition has slowed the sampling effort to the point of making it not feasible to continue. The work is to stop and restart in the spring of 2013. Delaying the work will impact the five-year review. The data that was to be collected will not be available for the fiveyear review. All parties acknowledged this but still agreed stopping the work and restarting in the spring is the correct thing to do. RPM Monthly Meeting 16-Nov-12 Approved 13 Generic QAPP and SS35 QAPP – Worksheet 15 All Eielson AFB Draft or Draft Final QAPP Worksheet 15s The AF will submit changed pages for Worksheet 15 to adjust screening levels for nonQAPP carcinogenic compounds to a hazard index of 0.1 for all media. The AF will incorporate the requested change in all Draft and Draft Final QAPPs and show QAPP the RSLs for all media as a hazard index of 0.1 for non-carcinogenic compounds. RPM Monthly Meeting 18-Dec-12 Approved RPM Monthly Meeting 18-Dec-12 Approved 15 QAPP Worksheet 15 RSL Text and Table Reference The version of the US EPA RSL tables in effect when a draft QAPP is submitted will QAPP become the benchmark for reviewing the QAPP and ultimately the data included in reports. The AF will use the most current RSL values in the report submittals. RPM Monthly Meeting 18-Dec-12 Approved 16 2008 FYR Addendum RPM Monthly Meeting 30-Jan-13 Approved 17 Regulatory Comments on Draft Documents Regulatory RPM Monthly Meeting Comments 30-Jan-13 Approved 19 FYR Report Outline There will be no 2008 FYR Addendum this year. All applicable recommendations from the 2008 FYR will be captured in the 2013 FYR. Shortly after receipt of regulatory comments on draft documents, the AF will advise regulators of a) acceptance, b) rejection, or c) required clarification of those comments. As an initial target, the AF will attempt to provide this response within 5 days of receipt of regulatory comments. In the outline for the FYR report, the Community Involvement section will be moved out of the individual sections into Section 1, Introduction. FYR 12-Feb-13 Approved 14 PSG FYR Page 20 of 29 FYR Document Discussion Meeting Date Approv. Reference/Notes References/Attachments: Attached PDF includes locations of PSGs at the site as decided by the project team. References/Attachments: Attached PDF includes a map of locations of concentrations of select TPHs and PAHs in direct push soil samples at the site. References/Attachments: Attached PDF includes locations of additional surface soil samples at the site. An Email from Kyle Waldron explains the EM and GPR survey process and revised schedule. Eielson AFB RPM Decision Tracker NON-RESTRICTED - Approved Decision Points Updated as of 30OCT2013 DP # Title 20 FYR Report Revised Outline Topic(s) FYR Associated Meeting FYR Document Discussion Meeting Mtg. Date 26-Feb-13 Status Approved 21 WP, SAP RPM Monthly Meeting 27-Feb-13 Approved NR2, FFA RPM Monthly Meeting 27-Feb-13 Approved RAB RPM Monthly Meeting 27-Feb-13 Approved QAPP RPM Monthly Meeting 27-Feb-13 Approved Tech Eval Tech Evaluation Comments Clarification Meeting 8-Mar-13 Approved Reference(s)/Attachment(s): RTCs table with comments, which was reviewed with stakeholders during the meeting via GoTo Meeting and teleconference. FYR Document Discussion Meeting 12-Mar-13 Approved Drafted during 12 March 2013 meeting and later revised during 22 March and 16 April 2013 meetings. FYR Document Discussion Meeting 12-Mar-13 Approved Drafted during 12 March 2013 meeting and later revised during 22 March and 16 April 2013 meetings. Drafted during 12 March 2013 meeting and later revised during 22 March and 16 April 2013 meetings. 22 23 24 25 Decision Point The revised outline of the FYR report, which was provided as part of the revised meeting agenda on 14FEB2013, has been approved by U.S. EPA. ADEC had no comments on the outline. Work Plan and Sampling and Analysis When the AF receives Work Plan and Sampling and Analysis Plan documents well in Plan Documents advance of construction, they will endeavor to prepare them as close to 100% prior to sending them to the regulators for sequential review, and will improve communicating timeframes on construction projects. NR2 Site NR2 is outside of the Eielson AFB cantonment area as defined in the FFA and on State land; therefore, should be cleaned up per State regulations. RAB Adjournment AF/EPA/ADEC conducted an effort to engage community interest in RAB participation and has received no inquiries or Community Interest Form responses; therefore, will begin the process of adjournment of the RAB in accordance with the DoD RAB Rule Handbook. The April RAB meeting will be cancelled. SS084 (AOC 16/AAA) Draft Final Phase 2 AF/EPA/ADEC RPMs agree to extend the due date by an additional 45 days for the SS084 Source Evaluation QAPP (AOC 16/AAA) Draft Final Phase 2 Source Evaluation QAPP. Tech Evaluation Report Comments Comment #1: The Technical Evaluation Report will be revised to incorporate language that provides a reference to specific AF follow-up actions. Comment # 5: Parties concur that these data will be provided in the 2012 IWMP Report as the appropriate document. Modify text in the Technology Evaluation Report to state additional data will be released in the draft IWMP Report. Date Approv. Reference/Notes Comment # 12 & 13: Text changes are not necessary; parties concur on text; comments 12 and 13 will be withdrawn. Comment #20: Comment will be withdrawn. What is provided is adequate for the scope of the document. 26 27 Comment #21: Parties agree this comment will be withdrawn from the Technology Evaluation Report. This comment will be addressed in the WP45/SS57 RI/FS and path forward. Non-ROD/Decision Sites Within the Foot For non-ROD/Decision sites within the foot print of an OU, they will be mentioned in the FYR Print of an OU discussion of the OU, the site would be shown on a figure, and included in discussion of remedy performance for an individual site within the OU if there is potential for co-mingling plume or contribution to the existing site’s contamination. NOn-ROD/Decision Sites Outside the Foot For non-ROD/Decision sites outside the foot print of an OU, map and status discussion will FYR Print of an OU be included in an attachment to the FYR. 28 FYR Executive Summary 29 CSM Updates Project Data 30 Cut-Off Date for Validated Data 31 Source Areas WP45/SS57 FYR Sections 32 Site Visit Documentation In the executive summary to the FYR, include a complete site list showing both three-party and two-party program sites at Eielson AFB (i.e.,IRP, SER, and CRP sites), which will provide a brief status (e.g., list the program they fall under, current status, etc.). This was done for the 611th. Refer to this document as an example. Data that are being obtained under the CSM Updates project will be included after the CSM after-action reports are finalized in a FYR Addendum. The timeline will be provided for this addendum in the FYR. RPMs agree that 12 March 2013 is the cut-off date for validated data that will be included in the FYR. The only exception will be the metals background reports for soil and groundwater, which will be expedited such that the information is utilized in the Draft Final FYR. The RPMs agree that a cut-off date will be necessary to determine what data to include in the FYR Addendum, and this determination will be made at an appropriate time in upcoming future FYR meetings. For FYR sections discussing source areas WP45/SS57: a. Will include discussion of Pilot Study data presented in the attachment found within the Innovative Technologies Evaluation Report. b. Screening level data consists of the 2011 Soil Gas Survey and reference of the screening level data of the groundwater. c. Will include validated data from 2012 letter report prepared by Jacobs Engineering. d. Will include validated data available for soil sampling performed in 2011 as well as baseline sampling of monitoring wells that was performed prior to the Triad groundwater screening effort. FYR FYR Document Discussion Meeting 12-Mar-13 Approved FYR FYR Document Discussion Meeting 12-Mar-13 Approved FYR FYR Document Discussion Meeting 12-Mar-13 Approved FYR FYR Document Discussion Meeting 12-Mar-13 Approved Drafted during 12 March 2013 meeting and later revised during 22 March and 16 April 2013 meetings. The Draft FYR will include a placeholder for the RPM team site visits and site interviews. RPMs agree the site visit documentation will be included at the Draft Final stage. FYR FYR Document Discussion Meeting 12-Mar-13 Approved Drafted during 12 March 2013 meeting and later revised during 22 March and 16 April 2013 meetings. Page 21 of 29 Drafted during 12 March 2013 meeting and later revised during 22 March and 16 April 2013 meetings. Drafted during 12 March 2013 meeting and later revised during 22 March and 16 April 2013 meetings. Eielson AFB RPM Decision Tracker NON-RESTRICTED - Approved Decision Points Updated as of 30OCT2013 DP # Title 33 2013 IWMP Sampling Decision Point The 2013 IWMP sampling will be accomplished under a revised Worksheet #16 to include the 2013 Spring and Fall sampling. The revised Worksheet #16 will be incorporated into the 2012 IWMP QAPP. This is proposed based on the conference call during which the stakeholders discussed the AF's evaluation of the regulatory comments received for the Draft IWMP QAPP Addendum for Vapor Intrusion: Concentrations for subslab soil gas and indoor air samples will be compared to screening levels for commercial/industrial use scenario. Text will be included in the reports that the evaluation of the VI pathway is only made for industrial/commercial use of the buildings and, if any of the buildings will be released for residential use in the future, an evaluation of the VI pathway will be performed at that time. Topic(s) IWMP Associated Meeting RPM Monthly Meeting Mtg. Date 25-Mar-13 Status Approved IWMP, VI, QAPP IWMP Vapor Intrusion QAPP Addendum Comments Clarification Meeting 12-Apr-13 Approved 34 Draft IWMP QAPP Addendum for Vapor Intrusion 35 Blair Lakes Sites SS53 and DP54 Blair Lakes sites SS53 and DP54 will not be included for discussion in the FYR. Although they were originally included in the list of sites, evaluation of the ROD revealed that they are already No Further Action sites with no requirement for monitoring. FYR FYR Document Discussion Meeting 16-Apr-13 Approved 36 Background Groundwater Data A second round of groundwater is planned for collection, therefore, any inclusion of background groundwater data is deferred from the 2013 Five Year Review (FYR) Report. FYR FYR Document Discussion Meeting 23-Apr-13 Approved 37 ST16 (formerly known as SS16) ST16 (formerly known as SS16) will not be included in the 2013 FYR Report. The RPMs concurred that the available documents in the Admin Record conclude that the source area status is closed; however, further investigation is planned due to contamination identified at an adjacent source area tentatively attributed to ST16. FYR FYR Document Discussion Meeting 23-Apr-13 Approved 38 Recommendation for Contaminant of Concern Language and Proposed Path Forward Recommendation for Contaminant of Concern Language: Eielson AFB investigations, findings, and Records of Decision (RODs) objectives were conducted and developed appropriately according to the technical standards of the 1990s. Since that time, however, a number of changes in analytical methods and regulatory statutes have led to corresponding new technical standards. The criteria and documentation needed for achieving site closure to UU/UE have also changed. As a result, a COC audit and review of remedial action objectives is recommended for all source areas. FYR FYR Document Discussion Meeting 23-Apr-13 Approved Proposed Path Forward: A significant portion of this audit and review can be accomplished as sites are evaluated through the IWMP and conceptual site models are updated. Data collected during the 2012 field season was already expanded to include COPCs. The updated list of COCs will be developed through a COC audit. The audit will include COPC data from the 2012 IWMP Report and a thorough review of site history and historical data. The outcome of the COC audit will be compiled in a stand-alone report evaluating the completeness of both the historic COC and updated COPC lists. Recommendations for adding COPCs to the COC list may be made on a site by site basis. Additionally, recommendations for additional site investigation may be made if: a.) the Air Force chooses to pursue UU/UE and data is required to support site closure b.) evaluation of soil gas and/or groundwater identifies COPCs in excess of screening levels in areas inconsistent with the original investigation and data is required to support site closure c.) evaluation of soil gas and/or groundwater identifies COPCs in excess of cleanup levels and at levels or in areas inconsistent with the original investigation 39 IC/LUC Report After review of the requirements for IC inspection reports due per the Settlement IC/LUC Agreement sections 3.4 and 5.3.6, Section 3.4 references a ROD requirement for a 60-day requirement for an IC field inspection report; Section 5.3.6 requires an annual report due by the end of the first quarter of the calendar year, which, at minimum, includes the inspection reports, noted deficiencies, and corrective actions taken. It has been determined that the Settlement Agreement requirement in Section 5.3.6 overrides the ROD reference in Section 3.4. All RPMs concur that the annual IC/LUC Report will be prepared in accordance with Section 5 of the IC/LUC Settlement Agreement. RPM Monthly Meeting 24-Apr-13 Approved 40 Soil Remediation or Off-Site Disposal of Soil Certificate Copies RPM Monthly Meeting 24-Apr-13 Approved 41 "Foot Print" Term A copy of certificates for any soil remediation or off-site disposal of soil should be provided IC/LUC to ADEC/EPA on a quarterly basis and included as an appendix in the annual IC/LUC Report. The term “foot print” referenced in the FYR Decision Points drafted in 12 March, 22 March, FYR and 16 April meetings is intended to be identified as a 200-foot buffer zone around the historical IRP source area boundaries. CRP/SER sites within this buffer zone will be referenced in the Physical Characteristics section of the 2013 FYR. RPM Monthly Meeting 24-Apr-13 Approved Page 22 of 29 Date Approv. Reference/Notes Notes just for the AF: 1) we do not currently have this activity included in the FY13 out of cycle or FY14 PCEADs 2) Outcomes from items “b” and “c” above differ mainly in terms of level of effort for the investigation and evaluation of the current remedy’s applicability to the ‘new’ COPCs Eielson AFB RPM Decision Tracker NON-RESTRICTED - Approved Decision Points Updated as of 30OCT2013 DP # Title 42 IWMP QAPP VI Addendum Scoping Decisions Decision Point Project-Level Decisions: Topic(s) IWMP, VI Associated Meeting Meeting to Reach Agreement on VI Scope under IWMP QAPP Mtg. Date 26-Apr-13 Status Approved Date Approv. Reference/Notes Approved during 16MAY13 RPM Monthly Meeting. RPM Meeting for Various Topics 15-May-13 Approved Approved during meeting. RPM Monthly Meeting 16-May-13 Approved Approved during meeting. 1. The attenuation factors based on radon sampling results can be utilized for buildings of similar construction type and period of construction with approval of ADEC/EPA. 2. The need for radon sampling and/or the application of site-specific attenuation factor will be determined after the first round of vapor intrusion evaluations are completed. ADEC may require more than two indoor air radon samples per building based on the size of the building. 3. The measurement and evaluation of radon should be conducted in accordance with EPA’s May 1993 document (EPA-402-R-92-003) titled “Protocols for Radon and Radon Decay Measurement in Homes”. Quality Assurance criteria will be collected in addition to the analyses of radon. 4. Scintillation counter make/model and laboratory calibration/performance criteria will be provided within the QAPP. Programmatic-Level Decision: 1. A stakeholder’s meeting will be setup after receipt of validated data from the first VI sampling event to determine if: a. Based on the building surveys and concentrations to which the default attenuation factor (0.1) is applied, the sampling for the winter event may be reduced/increased. Based on those validated data, the stakeholders will decide to only cover those analyses for which 1/10th the ADEC target level is still exceeded. b. There is a need to perform radon sampling and will agree upon the number of samples and locations. 43 Final Letter Work Plans for Geophysical Surveys, Landfill Inspections, and Monitoring for Multiple Source Areas, and PSG Survey Field Work 44 SER/CRP List for FYR 45 46 47 48 The 2013 Letter Work Plan for Geophysical Surveys, Landfill Inspections, and Monitoring WP, GPR, for Multiple Source Areas (submitted to stakeholders on 13 May 2013), and the Passive PSG, LF Soil Gas Survey Letter Work Plan (to be submitted on 17 May 2013) are submitted as Final documents. An official regulatory letter of concurrence will be prepared by the ADEC/EPA and, if any changes recommended, these changes will be identified in Field Change Forms. The Source Evaluation Report/Compliance Restoration Program list (Appendix B) will be FYR provided in the Draft Final 2013 Five-Year Review Report. SS67 2013 Fieldwork QAPP Update The SS67 QAPP attached to the RI/FS Management Plan will be revised through a QAPP Supplement. SS67 2013 Sampling Technical Approach The main purposes of the SS67 QAPP Supplement will to: 1) Identify the area of investigation as the immediate vicintity of the SS67 PCB Source Area 2) Eliminate the Mulit-Incremental sampling approach and replace it with discrete samples 3) Identify the laboratory providing testing services QAPP Update Sampling Approach 2013 CSM Updates and Supplemental Investigation Combined Scoping Session for Multiple Sites: Sites QAPP SS37, ST10/SS14, ST13/DP26, LF03/FT09, CS81 and CS82 Field Status Field Status Update - WP45/SS57 Update Deep Drilling for Vertical TCE Profile A QAPP that combines Sites SS37, ST10/SS14, ST13/DP26, LF03/FT09, and CS81 will be produced for 2013 field work. Organizational chart notes will be provided to identify roles/responsibilities for the three party and two party sites. WP45/SS57 Deep Drilling for Vertical TCE The first deep well ("in-plume" boring location) will be screened at approximately 208 feet Profile to 218 feet below ground surface (bgs). Due to significant heaving sand issues, drilling could not be advanced any deeper into the subsurface using dual tube tooling. Page 23 of 29 Site SS67 Scoping Meeting 1-May-13 Approved Site SS67 Scoping Meeting 1-May-13 Approved 6-May-13 Approved 11-Jun-13 Approved AFCEC (Air Force Civil Engineering Center). 2013 (June). Vertical and Horizontal Delineation Strategy for the WP45/SS57 TCE Plume, Eielson AFB, Alaska Eielson AFB RPM Decision Tracker NON-RESTRICTED - Approved Decision Points Updated as of 30OCT2013 DP # Title Decision Point 49 WP45/SS57 Deep Drilling for Vertical TCE Groundwater grab sample results from 17 feet to 227 feet bgs did not identify any TCE Profile above the project screening level. Based on the grab results and the decision tree in the final work plan (Figure 2), the team will precede using Scenario 2-No Deep TCE Plume. Topic(s) Associated Meeting Field Status Field Status Update - WP45/SS57 Update Deep Drilling for Vertical TCE Profile Mtg. Date Status 11-Jun-13 Approved Date Approv. Reference/Notes AFCEC (Air Force Civil Engineering Center). 2013 (June). Vertical and Horizontal Delineation Strategy for the WP45/SS57 TCE Plume, Eielson AFB, Alaska 50 WP45/SS57 Deep Drilling for Vertical TCE The second boring location will be moved from "Plume Delineation #1" to "Downgradient Profile Screening". Field Status Field Status Update - WP45/SS57 Update Deep Drilling for Vertical TCE Profile 11-Jun-13 Approved AFCEC (Air Force Civil Engineering Center). 2013 (June). Vertical and Horizontal Delineation Strategy for the WP45/SS57 TCE Plume, Eielson AFB, Alaska 51 WP45/SS57 Deep Drilling for Vertical TCE A total of two additional wells will be drilled and completed as a cluster at the "In-Plume" Profile boring location. The wells will be screened from 107 to 117 feet bgs and 177 to 187 feet bgs, respectively. Field Status Field Status Update - WP45/SS57 Update Deep Drilling for Vertical TCE Profile 11-Jun-13 Approved AFCEC (Air Force Civil Engineering Center). 2013 (June). Vertical and Horizontal Delineation Strategy for the WP45/SS57 TCE Plume, Eielson AFB, Alaska 52 CSM Updates CSM, SMP Eielson RPM Technical Session Government Only SMP RPM Monthly Meeting 26-Jun-13 Approved during RPM meeting. Draft SMP 26-Jun-13 Approved 26-Jun-13 Approved during RPM meeting. 54 Soil Sampling CSM Update ST20 AF will respond within the draft final SMP to agency’s concerns that CSM updates do not feed into primary documents. Regulatory review period for Draft SMP is extended pursuant to Part 25 of Eielson FFA. Agreed-upon target date for regulatory review comments is 8 July 2013, and AF target date is adjusted in accordance with FFA 30-day procedure. Soil sampling at CSM Update source area ST20 can proceed prior to the approval of the Addendum No. 2 of the Generic QAPP. 25-Jun-13 Approved 53 Generic, RPM Monthly Meeting ST20, CSM 26-Jun-13 Approved 26-Jun-13 Approved during RPM meeting. 55 CSM Update QAPP for LF03/FT09, ST10/SS14, ST13/DP26, SS37, CS081 RPMs had prior agreement to an accelerated review schedule for CSM Update QAPP for LF03/FT09, ST10/SS14, ST13/DP26, SS37, and CS081, and that initiation of fieldwork will occur prior to the QAPP being finalized. RPMs agree pursuant to the Eielson FFA this document is a Primary Document. CSM, RPM Monthly Meeting LF03/FT09, ST10/SS14, ST13/DP26 , SS37, CS081 26-Jun-13 Approved 26-Jun-13 Approved during RPM meeting. 56 Field Status Update – WP45/SS57 Deep Drilling for vertical TCE profile 1. A single well will be set at boring location 2. The wells will be screened from 248 to 258 feet bgs. 2. The third boring location will be “close downgradient screening” as identified in figure 5 of the deep drilling work plan. 3. If groundwater grab sample screening results at location 3 are consistent with locations 1 and 2 (no deep chlorinated analytes over project screening level), deep drilling will be complete. WP45/SS5 RPM Monthly Meeting 7 26-Jun-13 Approved 26-Jun-13 Reference(s): AFCEC (Air Force Civil Engineering Center). 2013 (June). Vertical and Horizontal Delineation Strategy for the WP45/SS57 TCE Plume, Eielson AFB, Alaska Note: A final stakeholder meeting will be needed once location 3 “close downgradient screening” groundwater grab results are available. Page 24 of 29 Approved during RPM Monthly Meeting Eielson AFB RPM Decision Tracker NON-RESTRICTED - Approved Decision Points Updated as of 30OCT2013 DP # Title SMP Review Cycle 59 61 Regulatory Reviews of documents that present data which do not contain conclusions or recommendations Decision Point The SMP is enforceable via the IC/LUC Settlement Agreement and it is an "other" type document. The submission of the initial (2013) SMP will be submitted/reviewed in accordance with Section 5.4 of the IC/LUC Settlement Agreement. Subsequent amendments (5.4.4) will be reviewed in accordance with the schedule for "primary" type documents as described in the FFA. Regulators will generally not comment on deliverables that contain data which do not contain conclusions or recommendations. Comments will be deferred until the data are presented in a future primary, secondary, or other document. Topic(s) SMP Associated Meeting RPM Monthly Meeting - Government and Contractor Session Mtg. Date Status 29-Aug-13 Approved Tech Memo RPM Monthly Meeting - Government/ Contractor Meeting 30-Oct-13 Approved Page 25 of 29 Date Approv. Reference/Notes 29-Aug-13 Replaced DP 58 Eielson AFB RPM Decision Tracker NON-RESTRICTED - Pending Decision Points Updated as of 30OCT2013 DP # Title 60 IC/LUC Settlement Agreement 5.4.3 Compliance Decision Point Topic(s) Meet the requirement of Section 5.4.3 of the IC/LUC Settlement Agreement by doing the SA following upon approval of a Primary or Secondary document which impacts the schedule or a subsequent document tracked by the SMP: 1. Revise the Milestone Schedule Table of the SMP by adding a new line/entry or changing a due date. 2. Post the table/SMP to the SharePoint site, and then 3. Air Force sends an e-mail to EPA and ADEC indicating that the SMP Milestone Schedule has been revised and posted. This should be done within 14 days of a new or revised Target or Deadline date Page 26 of 29 Associated Meeting RPM Monthly Meeting - Government Only Conference Call Mtg. Date 27-Sep-13 Status Pending Date Approv. Reference/Notes This also extends to other Primary Documents that are approved and which contain deadlines, target dates or schedules (i.e., SERs are to include proposed target dates and deadlines for appropriate subsequent secondary and primary documents; when a SER is finalized and the RPMs agree on the proposed target dates and deadlines, the AF needs to update the SMP accordingly within 14 days. Similarly, within 21 days after a ROD (or ROD amendment) is signed, the AF is to propose target dates for subsequent secondary documents and deadlines for the RD and RA workplan, when the RPMs agree on these the SMP needs to be updated accordingly). Eielson AFB RPM Decision Tracker NON-RESTRICTED - Withdrawn Decision Points Updated as of 17OCT2013 Title DP # 5 WP45/SS57 RI/FS MP RTCs 18 Bi-Weekly Stakeholder Meetings 57 FYR Delivery Date 58 SMP type and review cycle Decision Point Topic(s) Regulators to review permanent monitoring well locations, screen RI/FS intervals, and provide input on preferred construction type as proposed in the Technical Memorandum. Bi-weekly stakeholder meetings will take place to discuss FYRFYR related items until the draft report is delivered. New agenda items will be added to the list provided by AF in February and at the end of each meeting, the stakeholders will evaluate the items for priority and establish the agenda for the next meeting. In order to meet the tight deadline for completion of the FYR, the FYR delivery date of the draft final FYR on 31JUL2013 will be the official delivery date for this document. The RPMs agreed that the 31JUL2013 deliverable will include the following: (1) the draft final version of the FYR and (2) a redline version; the redline version will consist of the changed pages in track form and the RTCs table, which will be included as an appendix to the draft final FYR. Note that this redline document is consistent with redline procedures implemented programmatically at Eielson AFB. The EPA and ADEC RPMs agreed during this meeting that the 31JUL2013 draft final version may undergo changes based on forthcoming AF legal review and that the version revised based on AF legal review is the one that will be submitted within the regulatory agencies for upper management review; however, the regulatory RPMs will benefit from added review time by initiating technical review on the 31JUL2013 version of the document. Associated Meeting WP45/SS57 RI/FS MP RTCs Approach Meeting Mtg. Date 30-Aug-12 Status Withdrawn FYR Document Discussion Meeting 12-Feb-13 Withdrawn Draft FYR Comments Reconciliation Meeting - Part 2 24-Jul-13 Withdrawn 28-Aug-13 Approved during RPM Monthly Meeting The SMP is enforceable via the IC/LUC Settlement Agreement; it is an "other" type document; and it will follow the same review cycle as a "primary" type document. RPM government and contractor technical session 30-Jul-13 Withdrawn 29-Aug-13 Replaced by DP #59 after determination during 29 Aug RPM meeting that one element of this DP does not align with section 5.4 of the IC/LUC Settlement Agreement. SMP Page 27 of 29 Date Withdrawn Reference/Notes Eielson AFB RPM Decision Tracker SUCCESS STORIES Updated as of 30OCT2013 SS # Success Story 1 Installed 126 groundwater monitoring wells. Turbidity is below requisite levels. At the time of the meeting, all but 30 of the 126 wells had already been successfully developed. 2 Fish collection completed for Garrison Slough. 3 SER 001-2008 was officially transferred to the State program. 4 The document schedule was successfully converted to MS Project. In addition to the document schedule, the new Project schedule includes RPM meetings, field work, and other activities to aid the RPMs with planning activities in the future. 5 For the Installation Wide Monitoring Program (IWMP), as of 25 September, 124 wells were installed; 119 wells were developed; groundwater samples have been collected from 61 of 224 wells and achieved turbidity levels of less than 5 Nephelometric Turbidity Unit (NTU) with the exception of five wells for which results ranged from 9 -12 NTU; and, 13 background wells were installed. 6 For source area SS35, the scope of work of the CSM update as approved is nearing completion. 7 The Draft SS084-AOC 16 Phase 1 SER QAPP was approved on 17 Jul2012. 8 Completed survey of well location and type for 95% of wells-on Eielson AFB. 9 Installed PSG samplers at 6 of the 7 source areas, the tentative schedule is to install PSG samplers at the final source area, Blair Lakes, on 3 October 2012. Date Reported 29-Aug-12 Status Approved 29-Aug-12 29-Aug-12 Approved Approved Approved 26-Sep-12 Approved 26-Sep-12 26-Sep-12 26-Sep-12 26-Sep-12 Approved Approved Approved Approved 10 17-Oct-12 Approved 17-Oct-12 Approved 17-Oct-12 Approved 14-Nov-12 14-Nov-12 Approved Approved 11 12 13 14 Progress on Soil Transportation: 123 cubic yards (CY) have been approved for transport. There is another approximately 914 CY that had samples taken with results anticipated to be received by 23 October, at which time an authorization to transport will be submitted. Eielson AFB has had 1,659 CY additional soils that has either been transported to OIT, Inc. or has had authorization to transport approved. Soil-Disturbing Construction Report and Map: The USAF is now providing a summary report and color-coded map of soil-disturbing construction sites at Eielson AFB. This report and map will be updated as needed and provided during the RPM monthly meetings. Interim Removal Action: Eielson AFB has reduced the mass and source of contaminated soil at the DLA Rail Line Upgrade project site, essentially completing an interim removal action. Jacobs Engineering started field work at Garrison Slough this winter. Contaminated soil stockpiles will all be removed from Eielson AFB by next week. Page 28 of 29 Eielson AFB RPM Decision Tracker SUCCESS STORIES Updated as of 30OCT2013 SS # Success Story Date Reported 15 2012 Field Work Progress: 14-Nov-12 • Installation Wide Monitoring Program o 124 new wells installed and developed o Groundwater samples collected from 210 monitoring wells o Groundwater samples were not collected from approximately 11 monitoring wells because wells were damaged, destroyed, or not located o One production well was not sampled because it no longer exists o Two monitoring wells were not sampled due to the presence of light non-aqueous phase liquid. o Over 250 passive soil gas samplers were installed and retrieved from seven source areas (approximately 25-45 samplers per source area) o Base wide gauging of 210 monitoring wells was completed over a three day period o Monitoring wells and staff gauges were surveyed by a surveyor licensed in the state of Alaska • Installation Background Study o Background soil samples were collected from fluvial and loess soils o 13 new background monitoring wells were installed and developed o Groundwater samples were collected from 15 monitoring wells and low-flow purging achieved turbidity measurements of less than 5 NTU prior to collecting samples • Conceptual Site Model Update for Source Area ST48 o Field work was performed using the Triad approach from July – August with follow-up work performed August – September. Completed activities included collecting groundwater samples from existing monitoring wells, performing groundwater delineation sampling using temporary groundwater screen points, and collecting surface and subsurface soil samples. o In response to soil data, six surface soil samples were collected in October to assess whether polycyclic aromatic hydrocarbon impacts extend to locations north of source area ST48 (Power Plant). • Conceptual Site Model Update for Source Area ST20 o Field work was performed using the Triad approach during September. Completed activities included collecting groundwater samples from existing monitoring wells, performing groundwater delineation using temporary field screen points, and collecting surface and subsurface soil samples from Area E-8. • Conceptual Site Model Update for Source Area SS35 o Field work as performed in accordance with the QAPP September – October. Completed activities included collecting sediment, surface water, soil, and groundwater samples; performing geophysical survey; and installing, developing, and sampling five new groundwater monitoring wells. Status Approved 16 29-Aug-13 Approved 29-Aug-13 Approved During construction of projects on Eielson Air Force Base, contractors need to know if they will be working within contaminated sites so that adequate measures can 27-Sep-13 be put in place to ensure worker safety and the safe handling of contaminated soil. During 2013, Eielson AFB made substantial improvements in applying institutional controls to the contracting and construction processes. A base-wide generic sampling and analysis plan (SAP) was developed. For some projects, specific SAPs were developed. Regulatory agencies (ADEC and EPA) expedited their reviews of SAPs as much as possible to allow construction projects to proceed within the constraints of the short Alaska construction season. A close collaboration between regulatory agencies, Air Force environmental staff, contracting staff, and contractors ensured that environmental, contracting, and logistical concerns were promptly and efficiently addressed. Approximately fifteen project-specific SAPs were produced, reviewed, and approved, and a number of other projects were completed under the generic SAP. As a result, construction projects totaling approximately $78 million were completed with appropriate environmental safeguards in place and with minimal delays and contract modifications. Approved 17 18 The efforts of the EPA, DEC, and USAF to approve work on the volunteer disc golf project allowed installation of the course to occur this season. This enabled USAF personnel to hold a disc golf tournament and provide engaging on-base activities for Airmen stationed at Eielson AFB. The EPA, DEC, and USAF were highly effective in coordinating to obtain expedient reviews and approvals of construction sampling and analysis work plans, which ensured that $78 million in construction efforts affected by contaminated site concerns were not delayed for the 2013 construction season. Page 29 of 29 This page intentionally left blank. This page intentionally left blank. 4th Quarter FFA Progress Report Eielson AFB, Alaska 10 January 2014 Approved Decision Points 4th Quarter FFA Progress Report Eielson AFB, Alaska 10 January 2014 This page intentionally left blank. Eielson AFB RPM Decision Tracker NON-RESTRICTED - Approved Decision Points Updated as of 18DEC2013 DP # Title Regulatory Reviews of documents that 61 present data which do not contain conclusions or recommendations Soil and Groundwater Background Studies 62 LUC Boundaries 63 64 65 Associated Meeting Mtg. Date Status RPM Monthly Meeting - Government/ 30-Oct-13 Approved Contractor Meeting Date Approv. 30-Oct-13 Reference/Notes RPM November Monthly Meeting 12-Nov-13 Approved 12-Nov-13 Address EPA comment 14, ADEC comment 1, and ADEC comment 8 from the soil background study RTC document in the memorandum of record. To determine initial LUC areas associated with the 2013 LUCIP, utilize the union of the administrative site boundary (plus 200’ buffer) and the proposed ERPIMS-derived LUC boundary. Update LUC boundaries as additional data becomes available. If possible, create separate soil and groundwater LUC boundaries. If detections are encountered, apply a 200’ buffer. If non-detections are encountered (two consecutive non-detections for groundwater), the LUC boundary may be reduced or modified by RPM agreement. Update the LUC boundaries annually. Intersection with surface water bodies will encompass the whole of the water body unless otherwise determined by the RPMs. RPM November Monthly Meeting 12-Nov-13 Approved 12-Nov-13 Final 2013 FYR Delivery Date The final 2013 FYR will be delivered on 21 Feb 2014. AF Recommended Conceptual Approach The stakeholders generally support the conceptual approach described by the Air Force at the 17 Dec 2013 Eielson AFB Program Review Meeting and the 18 Dec 2013 RPM meeting. They generally support non-time critical removal action for SS35 and SS67. They have a general preference for an aggressive rather than a conservative schedule. Prior to obtaining specific agreement, the stakeholders need to review COC audit results and review a detailed schedule which emanates from this conceptual approach. RPM November Monthly Meeting RPM Monthly Meeting - Government Only Session 13-Nov-13 Approved 18-Dec-13 Approved 13-Nov-13 18-Dec-13 Remedial Investigations for Operable Units The stakeholders express a mutual preference for accomplishing Remedial Investigations for Operable Units rather than Remedial Investigations for source areas. However, they reserve the right to alter this approach in order to achieve efficient sequencing of activities based upon results of COC audit and related efforts. RPM Monthly Meeting - Government Only Session 18-Dec-13 Approved 18-Dec-13 IC/LUC Settlement Agreement 5.4.3 Compliance To meet the requirement of Section 5.4.3 of the IC/LUC Settlement Agreement the AF is responsible to immediately incorporate deadlines, target dates and schedules into the SMP by doing the following: RPM Monthly Meeting - Government Only Conference Call 27-Sep-13 Approved 18-Dec-13 66 60 Decision Point Topic(s) Regulators will generally not comment on deliverables that contain data which do not Tech Memo contain conclusions or recommendations. Comments will be deferred until the data are presented in a future primary, secondary, or other document. The soil background study and the groundwater background study will remain secondary documents; review cycles associated with primary documents will be utilized for the soil background study and the groundwater background study; a memorandum of record documenting agreement on soil and groundwater background levels will be prepared. SA 1. Within 14 (calendar) days upon approval of a Work Plan that specifies a Primary or Secondary document, the corresponding deadline or target date and related schedule will be incorporated into SMP by revision of the Milestone Schedule Table portion of the SMP by adding a new line/entry or changing a due date. 2. Post the table/SMP to the SharePoint site, and then 3. Air Force sends an e-mail to EPA and ADEC RPMs, and EPA/DEC/AF attorney's of notification that the SMP Milestone Schedule has been revised and posted. Other deadlines, target dates and schedules are subject to section 5.4.1 of the LUC Settlement Agreement, as well as the FFA (paragraphs 24.4 and 24.7). Page 1 of 1 Refer to Non-Restricted Meeting Minutes for 17-18 Dec 2013. This also extends to other Primary Documents that are approved and which contain deadlines, target dates or schedules (i.e., SERs are to include proposed target dates and deadlines for appropriate subsequent secondary and primary documents; when a SER is finalized and the RPMs agree on the proposed target dates and deadlines, the AF needs to update the SMP accordingly within 14 days. Similarly, within 21 days after a ROD (or ROD amendment) is signed, the AF is to propose target dates for subsequent secondary documents and deadlines for the RD and RA workplan, when the RPMs agree on these the SMP needs to be updated accordingly). This page intentionally left blank. 4th Quarter FFA Progress Report Eielson AFB, Alaska 10 January 2014 Institutional Control Signs Installed 4th Quarter FFA Progress Report Eielson AFB, Alaska 10 January 2014 This page intentionally left blank. Photograph No. 01 Date Taken: 30-7-2013 Description: Sign along Transmitter Road prior to replacement. Photograph No. 02 Date Taken: 30-7-2013 Description: Sign along Arctic Avenue prior to replacement. Photograph No. 03 Date Taken: 6-8-2013 Description: Sign in the vicinity of the Waste Water Treatment Plant prior to replacement. Photograph No. 04 Date Taken: 6-8-2013 Description: Sign in the vicinity of the Waste Water Treatment Plant prior to replacement. Photograph No. 05 Date Taken: 6-8-2013 Description: Sign in the vicinity of the Waste Water Treatment Plant prior to replacement. Photograph No. 06 Date Taken: 27-11-2013 Description: Sign along Transmitter Road after replacement. Photograph No. 07 Date Taken: 27-11-2013 Description: Sign along Arctic Avenue after replacement. Photograph No. 08 Date Taken: 27-11-2013 Description: New sign installed along Garrison Slough at intersection of Broadway Avenue. Photograph No. 09 Date Taken: 27-11-2013 Description: Sign in the vicinity of the Waste Water Treatment Plant after replacement. Photograph No. 10 Date Taken: 27-11-2013 Description: Sign in the vicinity of the Waste Water Treatment Plant after replacement. Photograph No. 11 Date Taken: 27-11-2013 Description: Sign in the vicinity of the Waste Water Treatment Plant after replacement. Photograph No. 12 Date Taken: 26-11-2013 Description: New sign installed near PCB landfill (LF03). Photograph No. 13 Date Taken: 26-11-2013 Description: New sign installed near PCB landfill (LF03). Photograph No. 14 Date Taken: 27-11-2013 Description: New sign installed near PCB landfill (LF03). This page intentionally left blank. 4th Quarter FFA Progress Report Eielson AFB, Alaska 10 January 2014 Construction Update Report and Map 4th Quarter FFA Progress Report Eielson AFB, Alaska 10 January 2014 This page intentionally left blank. To Qu arry Hill Legend CRP Site Buffers Potential Project Construction Outside Construction Inside IRP Sites IRP Sites 200' Buffers IT MIL AR YP IP E LIN E 5 43 4 33 45 38 34 N M 38 23 ¢ 38 Declination = 20° 24' E changing by 0° 22' W/year February 2012 38 40 Feet 0 41 50 250 0 500 1,000 125 1,500 250 500 Meters Th is map is f or reference only. Although every ef fort has been made to ensure the accuracy o f in formation, errors and con ditions originating f rom ph ys ical so urces used to develop the database may be reflected on this map. GeoBase shall not be liable for an y errors, omissions, or damages th at result fro m inappropriate use of this do cumen t. 46 48 Th is material is For Official Use Only. U nautho rized reproduction, distribution, p ublication, or exhib itio n of this material is STRICTLY PROHIBITED. Destroy as "For Official Use Only". 38 35 Engineer Hill Inset 38 49 44 12 U.S. Army Yukon Training Area Fort Wainwright Moose Creek 49 36 38 12 R i ch ar ds on 37 H ig 49 49 Quarry Hill Inset CIP Area hw ay Eielson Air Force Base n Ta 17 an a Riv ± 1 22X34 er Miles Salcha DEPARTMENT OF THE AIR FORCE PACIFIC AIR FORCES COMPREHENSIVE PLAN Dig Sites EIELSON A.F.B. ALASKA AIR FORCE COMPREHENSIVE PLANS AFI 32-7062 Custom 36X65 Prepared By: Heather Dauel Printing Date: December 16, 2013 File: P:\CEOG_Geobase\05_Maps\05_Customer_Maps\CEA\ Job 3562 High Vis Projects Dig Sites 2012\MXD \High_Vis_Dig_Projects.mxd This page is intentionally left blank. ID # Project # 4 FTQW031037 5 12 FTQW127802 FTQW122004 Project Title Upgrade Rail Line Repair Pipe Supports, E-6 Airfield Paving and Maintenance Cns % Est Cns Start 95 100 100 20-Aug-12 04-Jun-2012 15-May-2013 Cns Start 20-Aug-12 04-Jun-2012 07-Jun-2013 Est Cns Comp Project Description 31-Dec-13 Repair 10,000 feet and construct 8,000 feet of rail line. Construct covered offloading catwalk and header to support 7 rail cars. Comments Environmental Actions Status: 95% Construction. Next Step: Complete Canopy electrical and punch list. Awaiting final SAP report. Issues: Working mod to replace rail bridge, etc. at garrison slough - work to be accomplished next spring. 07-Sep-2012 Add 6" adjustments to VSM (vertical support member) pipe supports, dig/remove 4'x8' of soil, and backfill with frost acceptable soil. Align fuel pipes to its original design slope and elevation. VSM's that Complete are used to anchor pipe movement laterally may need additional 40' added to VSM. Add a 12" cushion to the dike liners for additional movement. Awaiting final OIT report. 30-Jul-2013 Airfield pavements maintenance; joint/crack repair, concrete/asphalt patching in multiple areas around the airfield. The actual scope of work cannot be determined until after the snow completely melts; sometime in the spring. Status: Project Complete Next Step: OIT report Issues: Awaiting final OIT report. STATUS: project complete, all paperwork recieved NEXT: determine warrranty start date ISSUES: none Landspread by CE Add and replace runway intersection and instrument hold signs as required by AFI 32-1076. 17 FTQW052521 Add/Repair Airfield Signs and Lights 100 26-Aug-2013 28-Aug-2013 01-Sep-2013 Included project FTQW 03-2453, Install Runway Guard Lights: position runway guard lights (WigWag) at all runway hold markings and signs on airfield (Taxiways A,B,C,D,E) Contractor may need to replace handholes in ground thus penetrating more than 6 inches. 23 33 FTQW121041 FTQW122208 Repair Arctic Utilidor Near CE Shops Demo Outdoor Recreation Buildings (B6213 & B6214) 88 1 01-May-2013 01-May-2014 05-Jun-2013 01-Oct-2013 01-Oct-2014 Repair by replacement approximately 1,800 LF of concrete utilidor and its associated water, steam, condensate, and sewer lines. Replace and upgrade pipe supports. Repair by replacement lighting, electrical system, and sump pumps. Remove communications cables and place in conduit outside utilidor as needed. Abate asbestos and PCB's as necessary. Replace any damaged or destroyed utilidor concrete, replace lids with traffic rated lids along entire length. Finish manholes with new split face brick covering and install lockable AT/FP approved lids. Cover repaired ducts and landscape to match original condition to maximum extent possible. Demolish two Outdoor Rec Buildings (B6213 and B6214) and consolidate their functions into existing facilities. Demolition shall include all of the facility, utilities, asphalt surfaces, and man-made infrastructure; work effort will return land beneath the facility and man-made infrastructure to improved grounds (green area). Utilities shall be demolished back to the main line utilidor connection and main line utilidor shall be patched to prevent water/rodent infiltration. Page 1 of 4 Status: final inspection on construction held 7 Oct 2013, winter exclusion Next Step: awaiting as-builts; after winter seeding/landscaping, manhole upgrades and other work pending receipt of OARS Awaiting final SAP report. funding Issues: request for OARS funding (soil testing, repair lateral, repair utilidor structure) in coord w/ PACAF Status: Hunstville District awarded demo for $64,462. Alaska District awarded consolidation to B/6001 for $569,445. Prices inlcude SIOH) Next Step: Wait for new faciity to be constructed prior to demo Issues: Wait for new facility to be constructed prior to demo Will require a site specific workplan and SAP. ID # 35 36 37 Project # FTQW062458 FTQW091009 Project Title Repair Fire Station 1 Repair AGE Equipment Refueling Area FTQW991033P4 Repair Twy Golf - North, Ph4 Cns % Est Cns Start 1 100 1 Cns Start 05-May-2014 15-May-2013 15-Jul-2014 15-Jul-2013 Est Cns Comp Project Description Comments Environmental Actions 22-Aug-2014 Perform complete renovation of Fire Station 1 including repair of room finishes, heating, ventilation, and air conditioning (HVAC), plumbing, fire detection, fire alarm, fire sprinkler (including smoke and carbon monoxide detectors, and a mass notification system), electric power, and communications systems throughout the building. The renovation shall include, but not be limited to, replacement of all kitchen appliances and cabinets, and installation of a new storage mezzanine and access staircase (less than 25% of the facility footprint). The renovation will include floor plan changes or room use changes to improve the functionality and safety of the facility. Repair work shall include exterior windows, roof and lightning protection, cracked slabs in vehicle bays, all exterior doors, service water line, electrical service, upgrading the exterior finish to an exterior insulation and finish system (EFIS), and all necessary supporting facilities for a complete and usable facility. Construction shall include addition of a new patio area, and Arctic Entry Vestibules at two entries. Additionally, the work will include relocation of the emergency generator and its accessories, and hazardous materials abatement, as necessary. All work will comply with DoD anti-terrorism and force protection requirements per Unified Facilities Criteria. Status: 65% design Next Step: review conf expected early Jan 2014 Issues: relocation, construction start date Fire Station sits on IRP site. Project will disturb soil to excavate and rebury underground utilities to the building, add foundations for two new entryways, demo small section of asphalt, replace floor slab in Crash Bay, and to add CMU wainscot around entire perimeter of bldg. Vapor issues expected from sub-slab gases when indoor slab is removed and replaced. Info has gone to USACE to include in package for contractor submittal. Jacobs report on indoor air/subslab has been provided to regulators. 30-Sep-2013 Repair AGE equipment refueling area to include repairing all electrical deficiencies to dispensers, defueling area and fuel pumps. This is to include replacement of all dispensers, all containment tubs, ECCO leak detection system and all piping back to the fuel tanks. The containment tub between the tanks and the dispensers need to be removed. Recommend replacing the ECCO system with a Veeder Root system as it is more user friendly. Status: Complete Draft reports have been reviewed and returned for comment. 01-Oct-2014 Repair the AC pavement on Twy Golf. This project will repair a 75ft wide section for the full length of the taxiway from Twy Echo to Twy Charlie. Scope DOES NOT INCLUDE the center section (approx 825 ft x 75 ft) which will be replaced with PCC by a separate Red Flag funded project. The existing AC pavement has block, alligator and longitudinal/transverse cracks; patches; depressions Status: Awarded and weathering/raveling. Scope includes removing Next Step: Coordinate Survey Team NTP existing AC pavement, scarifying and recompacting Issues: None base course and placing new AC pavement on full strength and shoulder areas. Existing base course material should be replaced as needed. Repairs also include saw cutting and sealing control joints for thermal cracking, restoration of pavement markings and other related work. This project should be accomplished as companion to the Red Flag PCC pad project. Page 2 of 4 Site specific Amendment due prior to construction start. ID # 38 Project # FTQW107714 Project Title UIC IDENTIFICATION AND REMOVAL - PHASE III Cns % Est Cns Start 80 01-Aug-2012 Cns Start 01-Aug-2012 Est Cns Comp Project Description 31-Jan-2014 Phase III of this phased project would implement recommendations in the December 2007 Identification/Removal Planning of Base Class V UIC Structures to identify and remove Base Class V UIC Structures. Class V UICs are regulated by the UIC program under the authority of the Safe Drinking Water Act. Class V UICs are authorized by 40 CFR 144 and do not require an EPA permit if they do not endanger underground sources of drinking water and comply with other UIC program requirements. Implementation will require that a updated Class V UIC inventory be submitted to the U.S. Environmental Protection Agency (EPA) and appropriate state agencies and the construction, operation and closure of Class V UICs are done in a manner protective of underground aquifers. Comments Environmental Actions Report complete, awaiting comments to finalize. Due to groundwater recharge faster than expected, not all contaminated soils were able to be removed. Draft report is under review. 332 #10077. Form 9 #F1U3C12180A001 40 Dredge Sludge in Water Treatment Plant Pond 41 Remove Abandoned Utilidor 44 Repair Electrical circuit 45 FTQW083007 Repair Central Heat and Power Plant Boilers, Phase 1 Dredge sludge from Water Treatment Plant backwash wastewater pond. Dispose of dewatered sludge. 100 58 15-Jul-2013 15-Jun-2011 23-Jul-2013 17-Jun-2011 05-Aug-2013 23-Nov-2014 No expected contamination to be found, but within 200 ft buffer so Project may not be completed this year due generic work plan and SAP to be to funding. May defer project for 3 to 4 submitted. Samples to be taken early years. Sampling has not been done to determine further need of sampling because of funding issue. during full excavation. Waiting for generic work plan & SAP Remove abandoned utilidor located in old trailer park approval. directly in front of driving range Project likely delayed until 2014. Dig up and repair HV circuit feeding flightline fire Project is complete. Soil has been pumps. Circuit Runs between building 1209 and transported to OIT and is awaiting thermal 1211. treatment. Repair by replacement new 120,000 lb/hr boiler at CH&PP. The new boiler will replace the existing spreader stoker boiler #6. No additional footprint is anticipated for this replacement. The project includes: demolition of the existing boiler; purchase and installation of new boiler; and all auxiliary equipment to support boiler operation to include: coal feed; ash handling; condensate handling; deaerator and boiler feedwater; soot blowers; boiler combustion air and forced draft fans; boiler flue gas; induced draft fans and stacks; as well as extensions of the plant control; electrical; glycol and steam systems; and installation of emission control equipment. New environmental control elements (selective catalytic reduction utilizing aqueous ammonia used to control nitrogen oxide and dry flue gas desulfurization used to control sulfur dioxide) will be included as part of the boiler package. Existing baghouses will be utilized. Additionally, a continuous emission monitoring system and a continuous opacity monitoring system will be required. Page 3 of 4 No expected contamination to be found, but within 200 ft buffer so generic work plan and SAP to be submitted. Awaiting thermal treatment certifications for submission to state. All earthwork complete except for some site clean-up when the contractor removes his trailers and offices, and some very minor Draft reports have been reviewed and work around entry steps and the like. Soil returned for comment. samples were taken at site and so a final SAP will be submitted. ID # Project # Project Title Cns % Est Cns Start Cns Start Est Cns Comp Project Description Comments Phase IV of this phased project is required to implement the recommendations from the FY11 Identification and Removal of UIC Project. Class V UICs are regulated by the UIC program under the authority of the Safe Drinking Water Act. Class V UICs are authorized by 40 CFR 144 and do not require an EPA permit if they do not endanger All field work is done as per the statement underground sources of drinking water and comply of work. Contractor is working on report. with other UIC program requirements. Implementation will require that an updated Class V UIC inventory be submitted to the U.S. Environmental Protection Agency (EPA) and appropriate state agencies and the construction, operation and closure of Class V UICs are done in a manner protective of underground aquifers. Environmental Actions 47 FTQW117615 UIC IDENTIFICATION AND REMOVAL - PHASE IV 80 01-Aug-2013 48 FTQW072802 Upgrade Rail Line - Trestle 0 2-Jun-14 31-Jul-14 Repair by replacement the current railroad trestle at French Creek entrance to base with a culvert system. Status: Design complete. Uploaded 1391 and government estimate to DLA Next Step: Funding Issues: Arsenic Levels in soil Permits 49 FTQW122004 Airfield Paving and Maintenance 2 15-May-2014 30-Jul-2014 Airfield pavements maintenance; joint/crack repair, concrete/asphalt patching in multiple areas around the airfield. Project awarded. Site specific Amendment due prior to construction start. 50 FTQW083005 New Dormitory 3 31-Mar-14 15-Jun-16 Construct new 168 person dorm after demolishing two existing dorms, 2206 and 2208. Project in solicitation. While not on contaminated soil, is within 200' buffer on northeast side of project. Soil samples were taken by CoE, will verify results. Potential need for SAP. Projects removed 15-Aug-2013 31-Jan-2014 Comments Page 4 of 4 Draft report is under review. 4th Quarter FFA Progress Report Eielson AFB, Alaska 10 January 2014 Project Schedules of 4th Quarter Activities Conducted and 1st Quarter Activities Planned 4th Quarter FFA Progress Report Eielson AFB, Alaska 10 January 2014 This page intentionally left blank. Documents Delivered 4th Quarter (2013-10-01 and 2013-12-31) Task Name Duration Start Finish Submit D 2014 SMP Amendment Submit D SS35 CSM Update Report Submit D Spring 2013 IWMP Groundwater Sampling TM Submit D Background Groundwater Study PSG, GPR, Landfill Survey and Landfill Inspection, and Monitoring Wells Maintenance and Repairs Technical Memorandum Submit D CS082 Site Characterization Report (SER001-2010) Submit D IWMP VI TM (only warm weather data) Submit D CS081 (SER001-2008) SI Report 0d 0d 0d 0d Tue 10/1/13 Mon 11/4/13 Mon 11/4/13 Wed 11/27/13 Tue 10/1/13 Mon 11/4/13 Mon 11/4/13 Wed 11/27/13 0d Wed 12/4/13 Wed 12/4/13 2d 0d 0d Wed 12/18/13 Thu 12/19/13 Thu 12/19/13 Thu 12/19/13 Tue 12/24/13 Tue 12/24/13 Predecessors Date Context Program Target Target Target Target IRP IRP IRP IRP Other Target IRP NA 228 Other NA NA Target NA CRP IRP CRP TRK Other Other 195 Other 252 SEC 101FS+120 d,107FS+120 d Regulatory Reviews Completed 4th Quarter (2013-10-01 and 2013-12-31) Task Name Regulatory Review of D LUCIP (20-day extension requested on 9/18/13 on due date of 9/17/13 followed by extension due to government shutdown agreed-upon on 10/7/13) Regulatory Review of D SS35 CSM Update Report Regulatory Review of F Background Soil Study Duration Start Finish Predecessors 74 d Sat 8/17/13 Tue 10/29/13 18FS+1 d 30 d 31 d Mon 11/4/13 Tue 12/3/13 Wed 11/13/13 Fri 12/13/13 TRK Date Program Context Other Target IRP 356 Other Target IRP SEC Target IRP Field Work Completed 4th Quarter (2013-10-01 and 2013-12-31) Predecessors TRK Date Context Task Name Duration Start Finish Program 2013 Annual IC Field Inspection (Section 5.3.5) Stage III FW - additional soil borings and groundwater grab samples at LF03/FT09, ST13/DP26, SS37, CS081, and CS082 Stage III FW - additional soil borings and groundwater grab samples at LF03/FT09, ST13/DP26, SS37, CS081, and CS082 Stage III FW - additional soil borings and groundwater grab samples at LF03/FT09, ST13/DP26, SS37, CS081, and CS082 Stage III FW - additional soil borings and groundwater grab samples at LF03/FT09, ST13/DP26, SS37, CS081, and CS082 Stage III FW - additional soil borings and groundwater grab samples at LF03/FT09, ST13/DP26, SS37, CS081, and CS082 IWMP VI Sampling Phase 2 (cold weather), including installation and sampling of soil gas wells Spring 2014 IWMP Groundwater Sampling VI Sampling (based on VI Addendum) - warm weather Fall 2014 IWMP Groundwater Sampling 2014 Annual Field Inspection (Section 5.3.5) VI Sampling (based on VI Addendum) - cold weather 6d Thu 10/10/13 Tue 10/15/13 4d Wed 10/16/13 Sat 10/19/13 IRP 4d Wed 10/16/13 Sat 10/19/13 IRP 4d Wed 10/16/13 Sat 10/19/13 IRP 4d Wed 10/16/13 Sat 10/19/13 CRP 4d Wed 10/16/13 Sat 10/19/13 IRP 28 d Thu 10/24/13 Wed 11/20/13 IRP 46 d 30 d 46 d 3d 30 d Tue 5/6/14 Fri 5/30/14 Fri 8/8/14 Wed 10/15/14 Sat 11/1/14 Fri 6/20/14 Sat 6/28/14 Mon 9/22/14 Fri 10/17/14 Sun 11/30/14 IRP IRP IRP IRP IRP IRP Documents Planned to Deliver 1st Quarter (2014-1-1 and 2014-3-31) Target IRP Target IRP Finish 4th Quarter Report 2013 (inclusive of IC/LUC Update) 0d Fri 1/10/14 Fri 1/10/14 Submit F Background Soil Study (date adjusted fro weekend) 0d Sun 1/12/14 Sun 1/12/14 Submit D SS085 - Building 3386 UIC Well Phase 2 SER Submit D SS086, Taxiway Golf, Phase 2 SER Submit D ST13/DP26 CSM Update Report 0d 0d 0d Mon 1/13/14 Mon 1/13/14 Mon 1/13/14 Mon 1/13/14 Tue 1/14/14 Tue 1/14/14 Submit D SS67 RI Report (does not include the BRA report) 0d Tue 1/14/14 Tue 1/14/14 Submit D SS084 - AOC16 Phase 2 Source Evaluation Report (date adjsuted for weekend) 0d Sat 1/18/14 Sat 1/18/14 Submit D WP45/SS57 RI Report (inclusive of the BRA report) 0d Wed 1/22/14 Wed 1/22/14 Submit RTCs on D SS35 CSM Update Report (a 20 day extension 0d was communicated by e-mail by C. Tallant on 12/31/13) Wed 1/22/14 Wed 1/22/14 0d Wed 1/22/14 Wed 1/22/14 0d 0d 0d Fri 1/24/14 Fri 1/24/14 Fri 1/24/14 Fri 1/24/14 Fri 1/24/14 Fri 1/24/14 SEC SEC SEC Submit D IWMP QAPP Addendum No. 3 for 2014 Groundwater 0d Monitoring (Af request for extension was sent on 11/26/13) Fri 1/31/14 Fri 1/31/14 Primary Deadline IRP Submit D QAPP Addendum No. 2 for VI at WP45/SS57 (estimated date based on anticipated contractual action) 0d Fri 1/31/14 Fri 1/31/14 Primary Deadline IRP Submit DF LUCIP Submit DF Background Groundwater Study Submit D ST20 CSM Update Report Submit D 2013 IWMP Groundwater Monitoring Report (report contains data from both 2013 sampling events) Submit D ST48 CSM Update Report Submit F 2014 SMP Amendment Submit RTCs on D CS082 Site Characterization Report (SER0012010) 0d 0d 0d Fri 1/31/14 Sun 2/2/14 Fri 2/7/14 Fri 1/31/14 Sun 2/2/14 Fri 2/7/14 20 Other 255 SEC 335 Other Target Target Target IRP IRP IRP 0d Sun 2/9/14 Sun 2/9/14 199 Other Target IRP 0d 0d Mon 2/10/14 Mon 2/10/14 Mon 2/17/14 Mon 2/17/14 524 Other Other Target Target IRP IRP 0d Mon 2/17/14 Mon 2/17/14 791 NA NA CRP Submit F CS082 Site Characterization Report (SER001-2010) 0d Mon 2/17/14 Mon 2/17/14 791 NA NA CRP Submit F FYR Report Submit RTCs on D CS081 (SER001-2008) SI Report Submit F CS081 (SER001-2008) SI Report Submit D Multi-Site Characterization Work Plan Submit DF SS085 - Building 3386 UIC Well Phase 2 SER Submit DF SS086, Taxiway Golf, Phase 2 SER Submit RTCs on D ST13/DP26 CSM Update Report Submit F ST13/DP26 CSM Update Report 0d 0d 0d 0d 0d 0d 0d 0d Fri 2/21/14 Sat 2/22/14 Sat 2/22/14 Sat 3/1/14 Fri 3/14/14 Fri 3/14/14 Sat 3/15/14 Sat 3/15/14 74 Primary Deadline 772 NA NA 772 NA NA NA NA 700 Primary Deadline 725 Primary Deadline 317 SEC Target 317 SEC Target Fri 2/21/14 Sat 2/22/14 Sat 2/22/14 Sat 3/1/14 Fri 3/14/14 Fri 3/14/14 Sat 3/15/14 Sat 3/15/14 TRK Program Duration Start Submit F SS35 CSM Update Report (a 20 day extension was communicated by e-mail by C. Tallant on 12/31/13) Submit D LF03/FT09 CSM Update Report Submit D ST10/SS14 CSM Update Report Submit D SS37 CSM Update Report Predecessors Date Context Task Name Other 248 SEC 697 Primary Deadline 722 Primary Deadline SEC Target SEC Target 674 Primary Deadline SEC IRP IRP IRP IRP IRP Target IRP 358 Other Target IRP 358 Other Target IRP Target Target Target IRP IRP IRP IRP CRP CRP CRP IRP IRP IRP IRP Submit RTCs on D SS67 RI (does not include the BRA report) 0d Sat 3/15/14 Sat 3/15/14 630 SEC Target IRP Submit F SS67 RI Report (does not include the BRA report; note that this RI, a secondary document, is finalized because the 0d results are to be considered at SS62) Sat 3/15/14 Sat 3/15/14 630 SEC Target IRP Submit DF SS084 - AOC16 Phase 2 Source Evaluation Report 0d Wed 3/19/14 Wed 3/19/14 677 Primary Deadline IRP 0d Sun 3/23/14 Sun 3/23/14 463 SEC Target IRP 0d 0d 0d 0d 0d 0d 1d Tue 3/25/14 Tue 3/25/14 Tue 3/25/14 Tue 3/25/14 Tue 3/25/14 Tue 3/25/14 Thu 3/27/14 Tue 3/25/14 Tue 3/25/14 Tue 3/25/14 Tue 3/25/14 Tue 3/25/14 Tue 3/25/14 Thu 3/27/14 276 276 296 296 380 380 SEC SEC SEC SEC SEC SEC NA Target Target Target Target Target Target NA IRP IRP IRP IRP IRP IRP MMRP Other Target IRP Submit RTCs to D WP45/SS57 RI Report (inclusive of the BRA report) Submit RTCs on D LF03/FT09 CSM Update Report Submit F LF03/FT09 CSM Update Report Submit RTCs on D ST10/SS14 CSM Update Report Submit F ST10/SS14 CSM Update Report Submit RTCs on D SS37 Report Submit F SS37 Report MMRP - Submit DF CSE Phase II Report Submit 2013 D Annual IC Report (to include the field inspection 0d report and per Section 5.3.9, IC/LUC database and Atlas) Mon 3/31/14 Mon 3/31/14 Submit DF Addendum No. 2 for VI at WP45/SS57 Submit DF Addendum No. 2 for VI at WP45/SS57 Mon 3/31/14 Mon 3/31/14 Mon 3/31/14 Mon 3/31/14 0d 0d 422 Primary Deadline 426 Primary Deadline IRP IRP Regulatory Reviews Planned for 1st Quarter (2014-1-1 and 2014-3-31) Task Name Regulatory Review of D 2014 SMP Amendment (a 20-day extension was requested and granted on 10/30/13) ADEC Review of D CS082 Site Characterization Report (SER001-2010) ADEC Review of D CS081 (SER001-2008) SI Report Regulatory Review of D SS085 - Building 3386 UIC Well Phase 2 SER Regulatory Review of D SS086, Taxiway Golf, Phase 2 SER Regulatory Review of D ST13/DP26 CSM Update Report Regulatory Review of D SS67 RI Report (does not include the BRA report) Regulatory Review of D SS084 - AOC16 Phase 2 Source Evaluation Report Regulatory Review of D WP45/SS57 RI Report (inclusive of the BRA report) Regulatory Review of D LF03/FT09 CSM Update Report Regulatory Review of D ST10/SS14 CSM Update Report Regulatory Review of D SS37 CSM Update Report Regulatory Review of D QAPP Addendum No. 2 for VI at WP45/SS57 Regulatory Review of DF LUCIP Regulatory Review of D IWMP QAPP Addendum No. 3 for 2014 Groundwater Monitoring Regulatory Review of DF Background Groundwater Study Regulatory Review of D ST20 CSM Update Report Regulatory Review of D 2013 IWMP Groundwater Monitoring Report (report contains data from both 2013 sampling events) Regulatory Review of D ST48 CSM Update Report ADEC Review of D Multi-Site Characterization Work Plan ADEC Review of D Multi-Site Characterization Work Plan TRK Date Context Program 34 Other Target IRP NA NA Deadline Deadline Target Target Deadline Target Target Target Target Deadline Target CRP CRP IRP IRP IRP IRP IRP IRP IRP IRP IRP IRP IRP Primary Deadline IRP Duration Start Finish Predecessors 50 d Tue 10/1/13 Tue 11/19/13 30 d 30 d 30 d 30 d 30 d 30 d 30 d 30 d 30 d 30 d 30 d 30 d 30 d Fri 12/20/13 Wed 12/25/13 Tue 1/14/14 Tue 1/14/14 Wed 1/15/14 Wed 1/15/14 Sun 1/19/14 Thu 1/23/14 Sat 1/25/14 Sat 1/25/14 Sat 1/25/14 Fri 1/31/14 Sat 2/1/14 Sat 1/18/14 Thu 1/23/14 Wed 2/12/14 Wed 2/12/14 Thu 2/13/14 Thu 2/13/14 Mon 2/17/14 Fri 2/21/14 Sun 2/23/14 Sun 2/23/14 Sun 2/23/14 Sat 3/1/14 Sun 3/2/14 789 770FS+1 d 698 723 315FS+1 d 628FS+1 d 675 461FS+1 d 274FS+1 d 294FS+1 d 378FS+1 d 419 21 NA NA Primary Primary SEC SEC Primary SEC SEC SEC SEC Primary Other 30 d Sat 2/1/14 Sun 3/2/14 167FS+1 d 30 d 30 d Mon 2/3/14 Sat 2/8/14 Tue 3/4/14 Sun 3/9/14 256 SEC 336 Other Target Target IRP IRP 30 d Mon 2/10/14 Tue 3/11/14 200 Other Target IRP 30 d 30 d 30 d Tue 2/11/14 Sat 3/1/14 Sat 3/1/14 Wed 3/12/14 Sun 3/30/14 Sun 3/30/14 525 Other 797 NA 801 NA Target NA NA IRP CRP CRP