addendum no

advertisement
ADDENDUM NO. 2
Date: September 29, 2015
for
Site Work for Portable Classrooms and Restroom
Saddleback College - BID No. 2039
South Orange County Community College District
General-All project documents including contract documents, drawings, and specifications, shall remain
unchanged with the exception of those elements added, revised, deleted, or clarified by this addendum.
CONTENTS
ADDENDUM ITEMS
INDEX
PAGE 1
ITEMS:
2-1
Revise Notice Calling for Bids
PAGE 2
2-2
Revise Supplemental Conditions
PAGE 2
2-3
Revise Contract Drawings
PAGE 2
2-4
Revise Project Manual
PAGE 3
2-5
Questions and Answers
PAGE 3-5
Page 1 of 5
Site Work for Portable Classrooms and Restroom,
Saddleback College
South Orange Community College District - BID No. 2039
Addendum #2
September 29, 2015
2-1 Revise Notice Calling for Bids
2-1.1
The Bid Deadline has been extended to 2:00 p.m., October 6, 2015.
2-1.2
Notwithstanding Information for Bidders, Paragraph 10, the deadline for prebid questions has been extended to 2:00 p.m. October 1, 2015. Pre-bid questions will
not be accepted after the deadline.
2-2 Revise Supplemental Conditions
2-2.1
For Supplemental Conditions, Exhibit 3. INCLUDED SCOPE OF WORK
AND CONSTRUCTION PHASING, Part II. EXPANDED DESCRIPTION, Paragraph 2,
add Subparagraph 2.b. as follows, “Contractor shall provide asphalt transition landing
at the end of each Portable Manufacturer’s ramp. Elevations as indicated on contract
drawing Sheet AS-02 to achieve maximum cross slope of 2 percent in the direction of
the path of travel.”
2-3 Revise Contract Drawings
2-3.1
Revise Contract Drawing Sheet AS-03 as indicated on attached 8-1/2x11
Sheet AR-2.01 dated 9/29/15.
2.3.2
For Contract Drawings Sheet E001, General Notes, Legend, Abbreviations
and Sheet Index, revise Site Utility Note 2 in its entirety to read as follows: “Upon
Notice to Proceed, District will provide to the Contractor a map indicating the location
of existing underground utilities prepared by an electronic locator service company to
be used as a guide during excavation for new utilities. Contractor shall pot hole to
locate exact location and depth of existing utilities prior to starting excavation or
trenching.”
2-3.3
Replace Contract Drawing Sheet E101 with revised Sheet E101, Rev.1
dated 9/29/15.
2-3.4
Replace Contract Drawing Sheet E501 with revised Sheet E501, Rev.1
dated 9/29/15.
2-3.5
Replace Contract Drawing Sheet FA001 with revised Sheet F, Rev.1 dated
9/29/15.
2-3.6
Replace Contract Drawing Sheet FA101 with revised Sheet FA101, Rev.1
dated 9/29/15.
Page 2 of 5
Site Work for Portable Classrooms and Restroom,
Saddleback College
South Orange Community College District - BID No. 2039
Addendum #2
September 29, 2015
2-3.7
Add Contract Drawing Sheet T001, Rev. 1 dated 9/29/15
2-3.8
Add Contract Drawing Sheet T101, Rev. 1 dated 9/29/15
2-3.9
Add Contract Drawing Sheet T102, Rev. 1 dated 9/29/15
2-4 Revise Project Manual
2-4.1
The following new specification sections are a part of Addendum No. 2:
2705 26
27 05 28
27 11 00
27 13 13
27 13 23
Grounding and Bonding for Communications System
Pathways for Communications System
Communications Equipment Room fittings
Communications Copper Backbone Cabling
Communications Optical Fiber Backbone Cabling
2-5 Questions and Answers
Q1: Description: AS-02 general note 20 calls for the contractor to level out surfaces at the
ramp locations. There is not a note as to who procures the ramp system at the new modular
villages or installs them. Please confirm that the access ramps are a part of the modular
system and will not be provided by the contractor.
A1: Refer to item 2-1.1.
Q2: The portable units do not show any penetrations through the flooring, however, the
portables are completely installed by another company. Are there any pre-installed points of
entry for utilities in the modular buildings? Please confirm if the portables have pre
manufactured/pre designated penetrations for utilities (MEP).
A2:
For 24X40 units: An exterior mounted (18” AFF - rear of building) gutter box (6x6x4) with
3/4” conduit stubbed into attic space is provided and meant for FA hook up only. (Box is
located in the rear 24’ wall of building near elect panel stub-outs.) Any other means of entry
into the building for low voltage, data, etc. will be provided by the Site Work contractor. All
connections/conduits/devices by Site Work contractor. Electrical panel feeds/stubs are through
the rear of the panel.
For 24X60 unit : An exterior mounted recessed J-BOX with 3/4” conduit stubbed into attic space
is provided and meant for FA hook up only. (J-BOX is located in the side 24’ wall of the building
near elect panel stub-outs.) Any other means of entry into the building for low voltage, data,
etc. will be provided by the Site Work contractor. All connections/conduits/devices by Site
Work contractor. Electrical panel feeds/stubs are thru the rear of the panel.
Page 3 of 5
Site Work for Portable Classrooms and Restroom,
Saddleback College
South Orange Community College District - BID No. 2039
Addendum #2
September 29, 2015
For 12X40 unit: An exterior mounted recessed J-BOX (18” AFF) with 3/4” conduit stubbed
into attic space is provided and meant for FA hook up only. (J-BOX is located in the side 12’
wall of the building near elect panel stub-outs.) Any other means of entry into the building for
low voltage, data, etc. will be provided by the Site Work contractor. All
connections/conduits/devices by Site Work contractor. Electrical panel feeds/stubs are thru the
rear of the panel.
Q3: Plans do not show a scope for asphalt replacement or repair at new modular buildings or
for installation of new parking at buildings. Please provide a scope of work for any asphalt
replacement required.
A3: New parking is not a part of the scope of work. Provisions are met with the existing
parking lot 2. Asphalt is existing to remain with a new slurry coat over existing as indicated on
sheet AS-02.
Q4: Testing of any spoils (environmental testing) or testing requirements of any soil at the
modular buildings locations was not found in the plans. Please advise to any soil testing
requirements for the project. If testing is required, who is responsible for the required testing
of soils at the modular building location?
A4: Should the Contractor discover any soils or other material that they expect to be
hazardous, the Contractor shall notify the District.
Q5: Exhibit 2 says Renovation, transportation, and installation of the portables will be done by
others on separate agreements. The modular building drawings show two doors being
relocated and one interior door added and electrical boxes and receptacles added in Village
12. Is this work by portable manufacture or by Contractor? Also electrical boxes and
receptacles are shown added in Modtech 24 x 40 classroom. Is this work by others or by
Contractor? In general our question is are the modular building drawings for reference only or
is there work required by Contractor included in the modular building drawings? Renovation is
by others per Exhibit 2.
A5: All work within the relocatables shall be done by the portable manufacturer, including the
relocation and addition of doors. Installation of electrical outlet circuits and J-boxes are also
provided by the portable manufacturer. (J-boxes for data and A/V are provided by the portable
manufacturer with conduits stubbed into attic only). Site Work Contractor shall make all power
connections from the power panels to the substation. All data wiring connections to be done
by the Site Work Contractor.
Q6: Do you know of any subcontractors that will supply and install the required Air blown fiber
optics for the new portables on this project that was mentioned at the Job walk? Please
advise.
A6: The subcontractor shall be a manufacturer authorized/licensed air blown fiber installation
Page 4 of 5
Site Work for Portable Classrooms and Restroom,
Saddleback College
South Orange Community College District - BID No. 2039
Addendum #2
September 29, 2015
Contractor. The manufacturer of the fiber optic cable is Sumitomo Electric Lightwave.
Determination of qualified subcontractors shall be by contractor.
Q7: Plan sheet AS-03 Keynote 5 (address of building). Is this item to be included in our bid? If
yes please supply detail and address for each building.
A7: All signage shall be done by Contractor. Coordinate with campus standard for style,
lettering and mounting height. For reference, refer to existing signage on adjacent portables.
Q8: Note 1 on plan sheets E501calls for new 200 amp 3 pole breakers to be installed in an
existing distribution board. Pages e1.0 and 8A of the stockpile drawings indicate the panel
provided by the building manufacturer will be 150 amp single phase panels. Please verify if
the building feeders are indeed 3 phase.
A8: Electrical panels in modular buildings are single phase.
Q9: Page A8 of the stockpile drawings does not reflect accurate fire alarm device
configuration. Please verify if this will be corrected by the building manufacturer or part of
our work.
A9: Required fire alarm devices are shown on Sheet FA 101 and are to be provided by the
Site Work Contractor. Conduit and J-Boxes are by portable manufacturer.
Q10: Page FA001 indicates we will be adding on to an existing Notifier fire system. Does the
college utilize a sole source for connection and programming of this system that we would
be limited to using, or can we list any certified Notifier installer?
A10: Fire Alarm installation shall be by Site Work Contractor. Programming of new Fire Alarm
system will be performed by Pyro-Comm through the District.
Q11: On page E501 detail 1, will the area we are trenching and providing duct bank in be
regarded as roadway due to being a parking area, or will it not be required to lace the trench
with #4 rebar?
A11: No roadway sections are present.
Q12: Please provide a requirement for sack ratio and color of encasement concrete.
A12: 2-sack slurry & red coloring for fire alarm encasing concrete.
Q13: Is the work described on page AS-03 notes 1 and 6, signage and curb painting already
in place?
A13: Contractor to provide painted red curb per keynote 1; post mounted signs per keynotes 2
& 6; and building signage per keynote 5.
Page 5 of 5
PROVIDE MINIMUM 8" X 8" NEMA 3R WIREWAY, MOUNTED
ON EXISTING CONCRETE PAD, CONDUIT STUB-UP
CONNECTING DUCT BANK TO DISTRIBUTION PANEL 'DP3'.
SEE DETAIL 2 ON SHEET E501 FOR STUB-UP
INFORMATION.
4
CONDUIT STUB-UP TO MINIMUM 6" X 6" X 6" NEMA 3R
JUNCTION BOX. CONNECT THROUGH EXTERIOR WALL TO
RECESSED ELECTRICAL PANEL PROVIDED BY TRAILER
MANUFACTURER. CONFIRM EXACT LOCATIONS WITH
TRAILER MANUFACTURER PRIOR TO SITE WORK. REFER
TO DETAIL 2 ON SHEET E501 FOR RISER INFORMATION.
5
PROVIDE TRAFFIC-RATED ROUND CONCRETE GROUND
WELL BOX, J&R MODEL#E1-RC. SEE DETAIL 3 ON SHEET
E501 FOR MORE INFORMATION.
7
PROVIDE 1" UNDERGROUND CONDUIT TO GROUND WELL,
BURIED MINIMUM 24" BELOW GRADE.
8
PROVIDE TRAFFIC-RATED CONCRETE ELECTRICAL
PULLBOX, MINIMUM 12" X 24" X 12" DEEP.
9
PROVIDE POWER TO FIRE ALARM POWER SUPPLY 'FA-V12'.
SEE SHEET FA 001 AND FA101 FOR MORE INFORMATION.
D
O F E S S I ON
AL
S
I T
I
J
N
G
PR
No. E16124
A
NE E R
GI
EN
H
G
PROVIDE (3) 2" UNDERGROUND CONDUIT DUCT BANK.
SEE DETAIL 1 ON SHEET E501 FOR MORE INFORMATION.
2900 Bristol Street, Suite E205
Costa Mesa, CA 92626-7909
ph: 714.435.0380
fx: 714.435.0383
ST
6
2
R A ARCHITECTURE
E
L
L
A
TE ECT R I C
R
FO
OF
CA L I
IA
3
N
PROVIDE (1) 2" UNDERGROUND CONDUIT, BURIED
MINIMUM 24" BELOW GRADE.
E
2
ER
PROVIDE (4) 2" UNDERGROUND CONDUIT DUCT BANK.
SEE DETAIL 1 ON SHEET E501 FOR MORE INFORMATION.
J A
1
R EG I S T
NOTES
architecture
planning
interiors
GENERAL NOTES
3
4
PANEL 'V13-A'
2
1.
CONDUIT FOLLOWS COMMUNICATION AND FIRE ALARM
CONDUITS IN SHARED DUCT BANK WHERE POSSIBLE.
2.
DISTRICT TO PROVIDE 3RD PARTY SOIL TESTING TO
VERIFY 95% COMPACTION OF TRENCHES PER THE
REQUIREMENTS OF THE DSA TESTING AND INSPECTION
FORMS. COORDINATE WITH INSPECTOR OF RECORD FOR
MORE INFORMATION.
P2S Engineering, Inc.
5000 East Spring Street, 8th Floor
Long Beach, CA 90815-5218
T 562.497.2999 F 562.497.2990
www.p2seng.com
5
1
7
(E) 36"X22" PULLBOX
6
7
2
4
Division of the State Architect
San Diego Regional Office
16680 West Bernardo Drive
San Diego, California 92127
ph: 858.674.5400
fx:
858.674.5471
8
PANEL 'V11-B'
5
2
4
PANEL 'V11-A'
7
5
2
V12-A-12
2
9
2
4
8
PANEL 'V12-A'
7
5
J7819-E101
A, Sassoon
J. Singh
SITE PLAN
NORTH
1
SITE PLAN
1/8" = 1'-0"
0
8
E101
3
ELECTRICAL PANELS PROVIDED BY TRAILER
MANUFACTURER. PROVIDE CONNECTIONS TO SYSTEM
POWER AND GROUNDING ELECTRODES.
4
ELECTRICAL CONTRACTOR TO FURNISH AND INSTALL
CONDUIT AND CONDUCTORS. SEE SITE PLAN SHEET E101
FOR ADDITIONAL REQUIREMENTS.
R EG I S T
REUSE EXISTING CIRCUIT BREAKER.
2900 Bristol Street, Suite E205
Costa Mesa, CA 92626-7909
ph: 714.435.0380
fx: 714.435.0383
D
O F E S S I ON
AL
S
I T
I N
J
G
PR
No. E16124
ST
A
NE ER
GI
EN
H
G
5
2
R A ARCHITECTURE
E
L
L
A
TE ECT R I C
R
FO
OF
CA L I
IA
PROVIDE GROUNDING ELECTRODE PER CEC 250.32(B)(1),
CONNECTED TO THE PANEL GROUND BUS. MEASURE
GROUND RESISTANCE AT GROUNDING ELECTRODE AND
PROVIDE ADDITIONAL GROUNDING ELECTRODES AS
REQUIRED PER CEC 250.53(A)(2) AND (3). DISTRICT TO
PROVIDE GROUND TESTING AND INSPECTION PER THE
DSA TESTING AND INSPECTION FORMS.
N
2
E
3/4"x10' LONG COPPER
CLAD STEEL GROUND ROD
REPLACE EXISTING 100A/2P TYPE BLH CIRCUIT BREAKER
WITH 150A/2P CIRCUIT BREAKER. MATCH EXISTING
CIRCUIT BREAKER MANUFACTURER AND TYPE INSTALLED
IN SWITCHBOARD.
ER
CAST IRON OR PRECAST CONCRETE COVER
LABELED "GROUND" IN 1/2" ENGRAVED LETTERS
1
J A
NOTES
architecture
planning
interiors
(E) MAIN SWITCHGEAR 'MSB'
CIRCUIT #2
GROUND ROD
CONNECTOR, BURNDY
TYPE GP6429 OR
APPROVED EQUAL
(E) (2)4"C WITH 3#250KCMIL
& 1#2 GRD. IN EACH
GROUND ROD CLAMP,
BURNDY TYPE GRC34 OR
APPROVED EQUAL
CONTINUOUS LOOP
PRECAST 8-3/4" DIA TRAFFIC BOX
P2S Engineering, Inc.
5000 East Spring Street, 8th Floor
Long Beach, CA 90815-5218
T 562.497.2999 F 562.497.2990
(E) TRANSFORMER 'T3'
300KVA, Z=5.0%
(E) BARE CU GEC
TO 5/8" GROUND ROD
REFER TO PLAN FOR
GND CONDUCTORS REQUIRED
www.p2seng.com
(E) DISTRIBUTION SWITCHBOARD 'DP3'
(E)
1200A MAIN
3P
5
(E) 100A
2P
1
150A
2P
1
150A
2P
2"C - (3)#3/0 AWG &
(1)#6 AWG GND (220')
NO SCALE
ELECTRICAL PULLBOX
ON BUILDING EXTERIOR WALL
1
150A
2P
(E) 150A
3P
2"C - (3)#1 AWG &
(1)#8 AWG GND (80')
(E) 150A
3P
2"C - (3)#3/0 AWG &
(1)#6 AWG GND (165')
GROUND ROD AND WELL
(E) 150A
3P
2"C - (3)#3/0 AWG &
(1)#6 AWG GND (165')
3
(E) 150A
3P
3
3
3
3
(E) 100A
2P
(E) 100A
2P
(E) 100A
2P
(E) 100A
2P
(E) 100A
2P
(E) 100A
2P
(E) 100A
2P
(E) 100A
2P
(E) 250A
3P
(E) 400A
3P
Division of the State Architect
San Diego Regional Office
16680 West Bernardo Drive
San Diego, California 92127
ph: 858.674.5400
fx:
858.674.5471
PB
4
(E) V8
(E) V9
(E) W
2
(E) K
V11-A
V-11B
V13-A
V12-A
G
G
G
G
(1)#4 AWG BARE CU GEC
TO 3/4" GROUND ROD
47.3 FLA
47.3 FLA
5.4 FLA
83.3 FLA
Isc=4672A Isc=4672A Isc=6604A Isc=4933A
%VD=0.8 %VD=0.8 %VD=0.06 %VD=1.2
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPACE
SPACE
(E)
VIL 10A
(E)
VIL 10B
GRADE
RGS CONDUIT WRAPPED WITH
PIPE TAPE
PVC CONDUIT
COUPLING
2
CONDUIT RISER
NO SCALE
J7819-E501
A. Sassoon
J. Singh
6" RED DETECTABLE WARNING TAPE
HARRIS INDUSTRIES DU-SERIES
FINISHED GRADE
24" MIN
3"
(4) 2" DUCTS
PVC SCHEDULE 40
2"
CONCRETE ENCASEMENT
4#4 RE-BARS IN
ROADWAY SECTIONS
CROSS TIES @24"O.C.
1
95% COMPACTION AND BACKFILL (NO SLURRY)
DISTRICT TO PROVIDE 3RD PARTY SOIL TESTING
PER THE REQUIREMENTS OF THE DSA TESTING AND
INSPECTION FORMS.
SINGLE LINE DIAGRAM
3"
3"
2"
3"
DUCT BANK
NO SCALE
E501
NOTIFIER
AREA SMOKE
DETECTOR
7272-0028:206
NOTIFIER
AREA HEAT
DETECTOR
7270-0028:0196
NBG-12LX
NOTIFIER
MANUAL PULL
STATION
7150-0028:199
DSM-12/24
WHEELOCK
SYNC MODULE
7300-0785:132
FSP-851
FST-851(A)
F
FSD-751P
REL-47K
E.O.L.
WEATHERPROOF
HORN
WHEELOCK
75 CD WALL
STROBE
NOTIFIER
END-OF-LINE
RESISTOR
0.048
0.0003
0.0065
PROVIDED
5' - 6" AFF TO TOP
4S
ON FINISHED
CEILING
0.0065
4S WITH B210LP(A)
BASE
0.000375
0.035
0.0003
3240-0028:205
0.0003
7125-0785:131
7125-0785:141
-
0.000
2013 CALIFORNIA CODE, TITLE 24 C.C.R. (2012 INTERNATIONAL BUILDING CODE OF THE INTERNATIONAL CODE
COUNCIL, WITH CALIFORNIA AMENDMENTS)
2013 CALIFORNIA ELECTRICAL CODE, TITLE 24 C.C.R. (2011 NATIONAL ELECTRICAL CODE OF THE NATIONAL FIRE
PREVENTION ASSOCIATION, NFPA)
2013 CALIFORNIA MECHANICAL CODE, TITLE 24 C.C.R. (2012 UNIFORM MECHANICAL CODE OF THE INTERNATIONAL
ASSOCIATION OF PLUMBING AND MECHANICAL OFFICIALS, IAPMO)
2013 CALIFORNIA PLUMBING CODE, TITLE 24 C.C.R. (2012 UNIFORM PLUMBING CODE OF THE INTERNATIONAL
ASSOCIATION OF PLUMBING AND MECHANICAL OFFICIALS, IAPMO)
PART 2
PART 3
PART 4
PART 5
0.005
4S WITH SINGLE
GANG RING
+48" AFF
PART 6
2013 CALIFORNIA ENERGY CODE, TITLE 24 C.C.R.
PART 7
CURRENTLY VACANT
0.080
4S
+48" AFF
PART 8
2013 CALIFORNIA HISTORICAL BUILDING CODE, TITLE 24 C.C.R.
PART 9
2013 CALIFORNIA FIRE CODE, TITLE 24 C.C.R. (2012 INTERNATIONAL FIRE CODE OF THE INTERNATIONAL CODE
COUNCIL)
PART 10
2013 CALIFORNIA EXISTING BUILDING CODE, TITLE 24 C.C.R. (2012 INTERNATIONAL EXISTING BUILDING CODE OF THE
INTERNATIONAL CODE COUNCIL, WITH AMENDMENTS)
4S
WEATHERPROOF
BACKBOX
PROVIDED
0.050
0.000
2013 CALIFORNIA BUILDING STANDARDS ADMINISTRATIVE CODE, TITLE 24 C.C.R.
PART 1
IN ATTIC
0.0003
0.000
MOUNTING HEIGHT
0.165
4S WITH 4S
EXTENSION
0.000
4S WITH COVER
PLATE
IN DUCT
+90" AFF
+80" AFF
+90" AFF
1.
1.
CONTROL CIRCUITS ARE NON POWER LIMITED. MINIMUM RECOMMENDED WIRE SIZE TO BE
DETERMINED BY CIRCUIT LOAD.
2.
WIRING SHALL NOT BE LOOPED THROUGH DEVICES UPON TERMINATION. (WIRE MUST BE CUT FOR IN
AND OUT RUNS PRIOR TO DEVICE TERMINATION.
3.
WHERE SHIELDED CABLE IS USED, THE SHIELD SHALL BE CONTINUOUS AND GROUNDED ONLY AT THE
RESPECTIVE CONTROL PANEL.
PROVIDE CONNECTIONS FROM EXISTING SITE FIRE ALARM SYSTEM IN VILLAGE 10 TO FIRE ALARM
DEVICES IN LEASE TRAILERS, NAME AND DESCRIPTION AS FOLLOWS:
1.1.
VILLAGE 11 - (2) COMPUTER CLASSROOM
1.2.
VILLAGE 12 - ADMINISTRATIVE OPEN OFFICE AND CONFERENCE ROOM
1.3.
VILLAGE 13 - MEN'S & WOMEN'S RESTROOM
2
2013 CALIFORNIA GREEN BUILDING STANDARDS CODE (CALGREEN), TITLE 24 C.C.R.
PART 12
2013 CALIFORNIA REFERENCED STANDARDS CODE, TITLE 24 C.C.R.
TOP OF SWITCH,
DEVICE, OUTLET
NFPA 13
AUTOMATIC SPRINKLER SYSTEMS (CALIFORNIA AMENDED)
2013 EDITION
NFPA 14
STANDPIPE SYSTEMS (CALIFORNIA AMENDED)
2013 EDITION
TOP OF SWITCH,
DEVICE, OUTLET
48" MAX
NFPA 17
DRY CHEMICAL EXTINGUISHING SYSTENS
2013 EDITION
NFPA 17A
WET CHEMICAL EXTINGUISHING SYSTEMS
2013 EDITION
NFPA 20
STATIONARY PUMPS
2013 EDITION
NFPA 24
PRIVATE FIRE SERVICE MAINS (CALIFORNIA AMENDED)
2013 EDITION
NFPA 72
NATIONAL FIRE ALARM CODE (CALIFORNIA AMENDED) (NOTE: SEE UL STANDARD 1971
FOR "VISUAL DEVICES")
2013 EDITION
NFPA 80
FIRE DOOR AND OTHER OPENINGS PROTECTIVES
2013 EDITION
NFPA 253
CRITICAL RADIANT FLUX OF FLOOR COVERING SYSTEMS
2006 EDITION
NFPA 2001
CLEAN AGENT FIRE EXTINGUISHING SYSTEMS
2012 EDITION
FINISHED
FLOOR
2013 CBC
FIG. 11B-308.2.1
2013 CBC
FIG. 11B-308.2.2
2013 CBC
FIG. 11B-308.3.2
THROUGH-PENETRATION FIRESTOP SYSTEM
1A
1B
DSA NOTES
2
1C
4A
ALL WORK SHALL CONFORM TO TITLE 24, 2001 EDITION OF CALIFORNIA CODE OF REGULATIONS (CCR).
CHANGES TO THE APPROVED DRAWINGS AND SPECIFICATIONS SHALL BE MADE BY AN ADDENDUM OR A CHANGE ORDER APPROVED BY
THE DIVISION OF THE STATE ARCHITECT, AS REQUIRED BY SECTION 4-338, PART 1, TITLE 24, CCR.
A PROJECT INSPECTOR EMPLOYED BY THE DISTRICT (OWNER) AND APPROVED BY THE DIVISION OF THE STATE ARCHITECT SHALL PROVIDE
CONTINUOUS INSPECTION OF THE WORK. THE DUTIES OF THE INSPECTOR ARE DEFINED IN SECTION 4-232, PART 1, TITLE 24, CCR.
NOTES FOR THIS DETAIL ONLY:
2-CONDUCTOR TWISTED PAIR SOLID CABLE NON-SHIELD #18 AWG WEST PENN
980 FPLR, CSFM #7161-0859:101
SLC ADDRESSABLE DATA CIRCUITS
V
2-CONDUCTOR TWISTED #12 AWG SOLID THHN
NOTIFICATION APPLIANCE CIRCUIT
P
2-CONDUCTOR TWISTED PAIR CABLE SOLID NON-SHEILDED #14 AWG WEST
PENN 990 FPLR, CSFM #7161-0859:101
AUXILIARY POWER
ALL WIRE AND CABLE TO BE SIGNED, TYPED AND CONDUIT FILL PER
CALIFORNIA ELECTRICAL CODE AND MANUFACTURER'S RECOMMENDATION.
WIRE FILL CHART
AREA - SQUARE INCHES
B.
PERCENT REDUCTION PER NUMBER OF 18AWG TWISTED SHIELDED PAIRS
TOTAL 100%
OVER 2 COND.
40%
1
2
3
4
5
6
8
7
1/2
0.622
0.30
0.12
33%
66%
99%
X
X
X
X
X
3/4
0.824
0.53
0.21
19%
38%
57%
76%
95%
X
X
X
1
1.049
0.86
0.34
12%
24%
36%
48%
60%
72%
84%
96%
(6)
(2)
(2)
(1)
1 1/4
1.380
1.50
0.60
7%
14%
21%
28%
35%
42%
49%
56%
75cd
75cd
75cd
1 1/2
1.610
2.04
0.82
5%
10%
15%
20%
25
30%
35%
40%
(2)
(2)
(2)
2
2.067
3.36
1.34
3.00%
6%
9%
12%
15%
18%
21%
24%
D.
NOTES:
(E) FIRE ALARM POWER
SUPPLY 'FA7'
FA-V12.1
FA-V12.2
FA-V12.3
FIRE ALARM POWER SUPPLY 'FA-V12'
CONNECT TO EXISTING WIRING TO EXTEND
SIGNAL TO NEW FIRE ALARM POWER SUPPLY
1
ALARM, TROUBLE AND SUPERVISORY SIGNALS FROM ALL INTELLIGENT REPORTING DEVICES SHALL BE ENCODED ON AN NFPA STYLE 6
(CLASS A) SIGNALING LINE CIRCUIT (SLC).
2.
INITIATION DEVICE CIRCUITS (IDC) SHALL BE WIRED CLASS B (NFPA STYLE B) AS PART OF AN ADDRESSABLE DEVICE CONNECTED BY THE
SLC CIRCUIT.
3.
NOTIFICATION APPLIANCE CIRCUITS (NAC) SHALL BE WIRED CLASS B (NFPA STYLE Y) AS PART OF AN ADDRESSABLE DEVICE CONNECTED BY
THE SLC CIRCUIT.
4.
ON STYLE 6 OR 7 (CLASS A) CONFIGURATIONS A SINGLE GROUND FAULT OR OPEN CIRCUIT ON THE SYSTEM SIGNALING LINE CIRCUIT
SHALL NOT CAUSE SYSTEM MALFUNCTION, LOSS OF OPERATING POWER OR THE ABILITY TO REPORT AN ALARM.
2.
FA-V12.4
Z12
TO EXISTING FIRE ALARM
CONTROL PANEL
1.
RISER DIAGRAM
5.
3.
ALARM SIGNALS ARRIVING AT THE FACP SHALL NOT BE LOST FOLLOWING A PRIMARY POWER FAILURE (OR OUTAGE) UNTIL THE ALARM
SIGNAL IS PROCESSED AND RECORDED.
NO SCALE
SEQUENCE OF OPERATIONS
MANUAL PULL STATION
DEVICE ACTION
AREA SMOKE
DETECTOR
4.
AIR DUCT SMOKE
DETECTOR
SPRINKLER WATER
FLOW SWITCH
SPRINKLER POST
INDICATOR SWITCH
120VAC POWER
FAILURE
SOUND CONTROL PANEL
TROUBLE BUZZER
YES
YES
YES
NO
NO
YES
ACTIVATE RELAY FOR
MONITORING (ALARM OR
TROUBLE)
NO
NO
NO
NO
NO
NO
SOUND SPRINKLER BELL
NO
NO
NO
NO
NO
NO
ANNUNCIATE AT FIRE ALARM
CONTROL PANEL (ALARM OR
TROUBLE)
YES
YES
YES
NO
NO
YES
ANNUNCIATE AT REMOTE FIRE
ALARM ANNUNCIATOR (ALARM
OR TROUBLE)
NO
ACTIVATE AUDIBLE/ VISUAL
ALARM SIGNALS THROUGHOUT
BUILDING
YES
YES
YES
NO
NO
YES
SHUT DOWN AIR HANDLING
(HVAC) THROUGHOUT BUILDING
IN ALARM
NO
NO
NO
NO
NO
NO
RELEASE SMOKE/ FIRE
DAMPERS
NO
NO
NO
NO
NO
NO
WALLBOARD, GYPSUM -NOM 1/2 OR 5/8 IN. THICK 4FT WIDE WITH SQUARE OR TAPERED EDGES.
WALLBOARD INSTALLED VERTICALLY ON BOTH SIDES OF STUD FRAMING WITH JOINTS
CENTERED OVER STUDS. THE GYPSUM WALLBOARD TYPE, THICKNESS NUMBER OF LAYERS
AND SHEET ORIENTATION SHALL BE AS SPECIFIED IN THE INDIVIDUAL U300 - OR U400 - SERIES
DESIGN IN THE UL FIRE RESISTANCE DIRECTORY.
C. FASTENERS- WHEN WOOD STUD FRAMING IS EMPLOYED FOR MAX 2 HR FIRE-RATED WALL
ASSEMBLY. GYPSUM WALLBOARD ATTACHED TO STUDS WITH CEMENT-COATED NAILS. WHEN
STEEL CHANNEL STUD FRAMING IS EMPLOYED, GYPSUM WALLBOARD ATTACHED TO STUDS
WITH TYPE S SELF DRILLING, SELF- TAPPING BUGLE-HEAD STEEL SCREWS. THE TYPE, LENGTH
AND SPACING OF FASTENERS SHALL BE AS SPECIFIED IN THE INDIVIDUAL U300 - OR U400 SERIES DESIGN IN THE UL FIRE RESISTANCE DIRECTORY
(6)
(8)
WALL ASSEMBLY - THE 1,2,3,OR 4 HR FIRE-RATED *MASONARY, CMU WALL OR FLOOR CEILING
ASSEMBLY GYPSUM WALL BOARD/STUD WALL ASSEMBLY SHALL BE CONSTRUCTED OF THE
MATERIALS AND IN THE MANNER DESCRIBED IN THE INDIVIDUAL WALL OD PARTITION DESIGN IN THE
UL FIRE RESISTANCE DIRECTORY AND SHALL INCLUDE THE FOLLOWING CONSTRUCTION FEATURES:
A. STUDS - WALL FRAMING MAY CONSIST OF EITHER WOOD STUDS MAX 2H FIRE RATED
ASSEMBLIES OR STEEL CHANNEL STUDS. WOOD STUDS TO CONSIST OF NOMINAL 2 BY 4 IN.
LUMBER SPACED 16 IN. OC WITH NOMINAL 2 BY 4 IN. LUMBER END PLATES AND CROSS
BRACES. STEEL STUDS TO BE MINIMUM 3- 5/8 IN. WIDE BY 1-3/8 IN. DEEP CHANNELS WITH
NOMINAL 1/4 IN. FOLDED BACK RETURN FLANGE EDGES, FORMED FROM MINIMUM 0.025 IN
THICK (NO 25 GAUGE) GALVANIZED STEEL. STEEL STUDS CUT 3/4 IN. LESS IN LENGTH THAN
ASSEMBLY HEIGHT WITH ENDS NESTING IN AND SECURED TO CHAN- NEL-SHAPED
GALVANIZED STEEL FLOOR AND CEILING TRACKS WITH 1/2 IN. LONG TYPE S-12 SELF-DRILLING
SELF TAPPING STEEL SCREWS ON BOTH SIDES OF STUDS OR BY WELDING OR BOLTED
CONNECTIONS DESIGNED IN ACCORDANCE WITH AISI SPECIFICATIONS. STEEL STUD SPACING
NOT TO EXCEED 24 IN. OC
NUMBER OF CONDUCTOR PAIRS
WIRE TYPE DESIGNATION
METALLIC RACEWAY/OPEN CABLE/PLENUM
CABLE/ETC. (WHERE APPLICABLE)
ABOVE EXAMPLE "2B" MEANS "2 PAIRS OF #14 AWG WIRE"
TRADE SIZE
8.
FIRE ALARM SIGNAL SHALL MEET ANSI S3.41, AUDIBLE EMERGENCY EVACUATION SIGNAL (TEMPORAL
PATTERN).
9.
AUDIBILITY OF ALARM SHALL BE NOT LESS THAN 15DB ABOVE AMBIENT SOUND THROUGHOUT THE
AREA OF ALARM.
No. E16124
A
E
L
L
A
TE ECT R I C
R
FO
OF
CA L I
11. STROBE APPLIANCE LOCATIONS ARE BASED ON 10 FOOT CEILING HEIGHTS AND ARE INSTALLED IN
ACCORDANCE WITH NATIONAL FIRE ALARM CODE (NFPA 72) UNLESS OTHERWISE NOTED. REFERENCE
APPLICABLE EDITIONS UNDER APPLICABLE CODES & REGULATIONS".
P2S Engineering, Inc.
12. WALL-MOUNTED STROBE AND HORN/STROBE APPLIANCES SHALL BE MOUNTED A MINIMUM OF 80
INCHES ABOVE FINISHED FLOOR OR 6 INCHES MINIMUM BELOW THE CEILING, (WHICH EVER IS LOWER).
MEASUREMENT ARE TO BE TAKEN FROM BOTTOM OF STROBE.
5000 East Spring Street, 8th Floor
Long Beach, CA 90815-5218
T 562.497.2999 F 562.497.2990
13. PHOTOELECTRIC DETECTORS SHALL NOT BE IN DIRECT AIR STREAM SUPPLY AIR OUTLETS.
www.p2seng.com
14. REFER TO RESPECTIVE CATALOG CUT SHEETS FOR ELECTRICAL MOUNTING HARDWARE.
15. THE USE OF OTHER THAN SIEMENS DETECTORS AND BASES WITH SIEMENS CONTROL EQUIPMENT
WILL BE CONSIDERED A MISAPPLICATION OF SIEMENS EQUIPMENT AND SUCH, VOIDS ALL
WARRANTIES EITHER EXPRESSED OR IMPLIED WITH REGARDS TO LOSS, DAMAGE, LIABILITIES AND/OR
SERVICE PROBLEMS.
16. ALL DEVICES OF THE FIRE ALARM SYSTEM SHALL BE APPROVED AND LISTED BY THE CALIFORNIA
STATE FIRE MARSHAL.
20. DIFFERENTIAL PRESSURE SWITCHES SHALL BE SUPPLIED AND INSTALLED BY A LICENSED
MECHANICAL CONTRACTOR. THE ELECTRICAL CONNECTION TO THE DIFFERENTIAL PRESSURE SWITCH
SHALL BE MADE BY SIEMENS.
USED ON
1.
(4)
ALL WIRING, INITIATING DEVICES AND ANNUNCIATOR PANELS SHALL BE SUPERVISED TO THE
PRINCIPAL POINT OF ANNUNCIATION. (FIRE ALARM CONTROL PANEL(S) TO SUPERVISE ANNUNCIATOR
PANEL(S), SUB-PANEL(S), ALL CIRCUITS AND INITIATING DEVICES).
19. DUCT SMOKE DETECTORS SHALL BE TESTED FOR DUCT VELOCITY AND PRESSURE DIFFERENTIAL IN
ACCORDANCE WITH THE MANUFACTURERS SPECIFICATIONS.
4A
M
INTERNAL
DIAMETER
INCHES
7.
18. ALL FIRE ALARM CIRCUITS SHALL BE LABELED AT CONNECTIONS AND AT JUNCTION BOXES.
WIRE LEGEND
2B
POINT AND COMMON ANNUNCIATION AND T-TAPPING PROHIBITED.
O F E S S I ON
AL
S
I T
I N
J
G
PR
17. AUDIBILITY WILL BE DETERMINED BY THE FIELD FIRE MARSHAL.
2
WIRE DESCRIPTION
6.
D
10. ALL STROBE APPLIANCES SHALL BE SYNCHRONIZED IN ACCORDANCE WITH NATIONAL FIRE ALARM
CODE (NFPA 72). REFERENCE APPLICABLE EDITIONS UNDER "APPLICABLE CODES & REGULATIONS".
15" MIN
EXAMPLE:
ELECTRICAL CONTRACTOR IS REQUIRED TO USE: COLOR CODE, WIRE NUMBERS, OR AS SPECIFIED IN
THE PROJECT SPECIFICATIONS ON ALL CIRCUITS AND SHALL BE CONTINUOUS, OTHERWISE, NO FINAL
CONNECTIONS OR TESTING SHALL BE PERFORMED. IF WIRE COLOR CODING IS USED, GREEN WILL BE
USED FOR GROUND BONDING ONLY.
2900 Bristol Street, Suite E205
Costa Mesa, CA 92626-7909
ph: 714.435.0380
fx: 714.435.0383
46" MAX
34" MAX
WIRE TYPE
DESCRIPTION
5.
24" MAX
PARTIAL LIST OF APPLICABLE STANDARDS:
2013 CALIFORNIA BUILDING CODE (FOR SFM) REFERENCED STANDARDS CHAPTER 35
3.
T-TAPPING OR PARALLEL BRANCHING OF NOTIFICATION APPLIANCE DEVICE CIRCUITS IS PERMITTED
ON CLASS B CIRCUITS.
MOUNTING HEIGHT OVER OBSTRUCTION
PART 11
1.
2.
4.
R A ARCHITECTURE
ST
RSS-24MCW
WHEELOCK
DUCT SMOKE
DETECTOR
0.048
BACKBOX
NE ER
GI
EN
H
G
AH-24WP
NOTIFIER
7315-0028:225
MAXIMUM
CURRENT (A)
IA
NOTIFIER
FIRE ALARM
POWER SUPPLY
FCPS-24S6
C.S.F.M.
E
DESCRIPTION
ER
FAPS
STANDBY
CURRENT (A)
MANUFACTURER
J A
MODEL
GENERAL NOTES
R EG I S T
SYMBOL
SCOPE OF WORK
N
APPLICABLE CODES
DEVICE SCHEDULE
architecture
planning
interiors
JOINT TAPE AND COMPOUND- VINYL OR CASEIN, DRY OR PREMIXED JOINT COMPOUND
APPLIED IN TWO COATS TO JOINTS AND SCREW OR NAIL HEADS OF OUTER LAYER OF GYPSUM
WALLBOARD. PERFORATED PAPER TAPE, 2IN. WIDE, EMBEDDED IN FIRST LAYER OF
COMPOUND OVER ALL JOINTS OF OUTER LAYER OF GYPSUM WALLBOARD.
PIPE OR CONDUIT- NOM 12 IN. DIAM(OR SMALLER) SCHEDULE 10S (OR HEAVIER) STEEL PIPE, NOM 6 IN.
DIAMETER (OR SMALLER) RIGID STEEL CONDUIT, NOM 4 IN. DIAMETER (OR SMALLER) STEEL E.M.T.,
NOM 4 IN. DIAMETER (OR SMALLER) TYPE L (OR HEAVIER) COPPER PIPE OR NOM 1 IN. DIAM (OR
SMALLER) FLEXIBLE STEEL CONDUIT. WHEN COPPER PIPE OR FLEXIBLE STEEL CONDUIT IS USED, MAX
F RATING OF FIRESTOP SYSTEM (ITEM 4) IS 2 H. STEEL PIPES OR CONDUITS LARGER THAN NOM. 4 IN.
DIAM MAY ONLY BE USED IN WALLS CONSTRUCTED USING STEEL CHANNELS STUDS. A MAX OF ONE
PIPE OR CONDUIT IS PERMITTED IN THE FIRESTOP SYSTEM. PIPE OR CONDUIT TO BE INSTALLED NEAR
CENTER OF STUD CAVITY WIDTH AND TO BE RIGIDLY SUPPORTED ON BOTH SIDES OF WALL
ASSEMBLY.
PIPE COVERING -(OPTIONAL) NOM 1 OR 2 IN. THICK HOLLOW CYLINDRICAL HEAVY DENSITY (MIN. 3.5
PCF) GLASS FIBER UNITS JACKETED ON THE OUTSIDE WITH FOIL-SCRIM-KRAFT. LONGITUDINAL JOINTS
SEALED WITH METAL FASTENERS OR FACTORY-APPLIED SSL. TRANSVERSE JOINTS SEALED WITH
METAL FASTENERS OR WITH BUTT STRIP TAPE SUPPLIED WITH THE PRODUCT. SEE PIPE AND
EQUIPMENT COVERINGS-MATERIALS (BRGU) CATEGORY IN BUILDING MATERIALS DIRECTORY FOR
NAMES OF MANUFACTURES. ANY PIPE COVERING MATERIAL MEETING THE ABOVE SPECIFICATIONS
AND BEARING THE UL CLASSIFICATIONS MARKING WITH FLAME SPREAD VALUE 25 OR LESS AND A
SMOKE DEVELOPED VALUE OF 50 OR LEDD MAY BE USED.
FIRESTOP SYSTEMS-INSTALLED SYMMETRICALLY ON BOTH SIDES OF WALL ASSEMBLY. THE HOURLY F
RATING OF THE FIRESTOP SYSTEM IS DEPENDANT UPON THE HOURLY FIRE RATING OF THE FIRESTOP
SYSTEM IS DE- PENDANT UPON THE TYPE OR SIZE OF THE PIPE OR CONDUIT, THE ABSENCE OR
PRESENCE OF PIPE COVERING (ITEM 3). THE FIRESTOP CONFIGURATION AND THE HOURLY FIRE
RATING OF THE WALL ASSEMBLY IN WHICH IT IS INSTALLED. THE FIRESTOP CONFIGURATION (A,B,C,OR
D) ID DEPENDENT UPON THE SIZE OF THE ANNULAR SPACEBETWEEN THE PIPE OR CONDUIT (OR PIPE
COVERING) AND THE PERIMETER OF THE CIRCULAR THROUGH OPENING IN THE GYPSUM WALLBOARD
LAYERS AS TABULATED BELOW.
MAX PIPE OR
CONDUIT
DIAM, IN.
NOM PIPE
COVERING
THKNS IN.
ANNULAR
SPACE IN.
FIRESTOP
CONFIG. (A)
F RATING HR.
T RATING HR.
-
-
-
-
-
-
Division of the State Architect
San Diego Regional Office
16680 West Bernardo Drive
San Diego, California 92127
ph: 858.674.5400
fx:
858.674.5471
21. SIEMENS EQUIPMENT IS BOTH UNDERWRITERS LABORATORIES (UL) AND CALIFORNIA STATE FIRE
MARSHAL (CSFM) LISTED FOR POWER LIMITED INSTALLATION.
22. UNLESS OTHERWISE NOTED ALL WIRING AND INSTALLATION METHODS SHALL CONFORM TO
CALIFORNIA ELECTRICAL CODE (CEC), ARTICLE 760. SEE APPLICABLE EDITION UNDER "APPLICABLE
CODES & REGULATIONS".
23. ALL WIRE CONDUCTORS SHALL BE POWER LIMITED COPPER WIRING AND INSTALLED WITHIN A
METALLIC RACEWAY.
24. PER SPECIFICATION CONDUIT RISERS SHALL BE INSTALLED INSIDE A TWO HOUR FIRE RATED
ENCLOSURE PROVIDED BY OTHERS. HORIZONTAL OFFSET CONDUITS AND JUNCTION BOXES SHALL BE
PROTECTED BY TWO HOUR FIRE RATED ENCLOSURES PROVIDED BY OTHERS.
25. ALL RACEWAY RUNS INDICATED WITHIN THIS DRAWING PACKAGE ARE SHOWN DIAGRAMMICALLY AND
ARE FOR CIRCUITING PURPOSES ONLY. ALL RUNS SHOWN SHOULD NOT SERVE IN ANY WAY AS AN
ACTUAL ROUTING GUIDE FOR INSTALLATION OF RACEWAYS. EXACT INSTALL LOCATION SHALL BE
FIELD DETERMINED.
26. ADDITIONAL JUNCTION BOXES NOT SHOWN MAY BE REQUIRED TO ACCOMMODATE PROPER RACEWAY
INSTALLATIONS. IT IS THE ELECTRICAL CONTRACTORS RESPONSIBILITY TO DETERMINE THE
NECESSARY AMOUNT OF JUNCTION BOXES REQUIRED.
27. SUBMITTED DRAWING PACKAGE MUST BE REVIEWED BY COLLEGE REPRESENTATIVE AND ONE COPY
OF THE REVIEWED DRAWING AND SUBMITTAL MUST BE RETURNED TO SIEMENS BEFORE ANY
EQUIPMENT IS SHIPPED OR INSTALLED. CUSTOM ANNUNICATORS WILL NOT BE FABRICATED UNTIL
WRITTEN APPROVAL OF LAYOUT AND/OR ARTWORK IS RECEIVED.
28. NOTICE: DO NOT APPLY POWER TO CONTROL PANEL(S) UNTIL A SIEMENS SERVICE TECHNICIAN HAS
CHECKED THE SYSTEM INSTALLATIONS. UPON SATISFACTORY COMPLETION OF HIS INSPECTION,
POWER WILL BE APPLIED TO THE CONTROL PANEL(S). SIEMENS ASSUMES NO LIABILITY FOR ANY
DAMAGE TO THE EQUIPMENT SUPPLIED IF POWER IS APPLIED TO THE CONTROL PANEL(S) PRIOR TO
INSPECTION OF THE INSTALLATION BY SIEMENS TECHNICIAN.
29. FOR INSPECTION AND OR TESTING THE FIRE MARSHAL SHALL BE NOTIFIED FOR SCHEDULING AN
APPOINTMENT.
30. A CERTIFICATE OF COMPLIANCE SHALL BE PREPARED BY THE INSTALLER AND GIVEN TO THE FIRE
MARSHAL UPON COMPLETION OF THE INSTALLATION.
31. ANY DISCREPANCIES BETWEEN THE DRAWINGS AND THE CODE OR RECOGNIZED STANDARDS SHALL
BE BROUGHT TO THE ATTENTION OF THE INSPECTOR OF RECORD. THE STRICTER REQUIREMENT WILL
PREVAIL.
32. A STAMPED SET OF APPROVED FIRE ALARM PLANS SHALL BE ON THE JOB SITE AND USED FOR
INSTALLATION. ANY DEVIATION FROM APPROVED PLANS, INCLUDING THE SUBSTITUTION OF DEVICES
SHALL BE APPROVED BY THE FIRE MARSHAL.
33. UPON COMPLETION OF THE FIRE ALARM SYSTEM, A SATISFACTORY TEST OF THE ENTIRE SYSTEM
SHALL BE MADE IN THE PRESENCE OF THE FIRE MARSHAL.
34. UNLESS SPECIFICALLY SHOWN ON THESE PLANS NO STRUCTURAL MEMBERS SHALL BE CUT, DRILLED
NOR NOTCHED WITHOUT PRIOR WRITTEN AUTHORIZATION FROM THE STRUCTURAL ENGINEER AND
THE DISTRICT STRUCTURAL ENGINEER FROM THE DIVISION OF THE STATE ARCHITECT.
J7819-FA001
A. Sassoon
J. Singh
SHEET INDEX
SHEET
DESCRIPTION
FA001
GENERAL NOTES, LEGEND, ABBREVIATIONS AND SHEET INDEX
FA101
SITE PLAN
+ WHEN COPPER PIPE IS USED, T RATING IS 0H
(A)A INDICATE FIRESTOP CONFIGURATION, AS DESCRIBED IN THE FOLLOWING
NO
NO
NO
NO
NO
A.
FILL VOID OR CAVITY MATERIAL-CAULK- CAULK FILL MATERIAL INSTALLED TO COMPLETELY
FILL ANNU- LAR SPACE BETWEEN PIPE OR CONDUIT AND GYPSUM WALLBOARD AND WITH A
MIN 1/4 IN. DIA BEAD OF CAULK APPLIED TO PERIMETER OF PIPE OR CONDUIT AS IT EGRESS
FROM THE WALL. MINNESOTA MINING & MANUFACTURING-TYPES CP-25 S/L, CP-25 N/S, CP-25
W/B
U.L. SYSTEM # WL1001
GENERAL NOTES,
LEGEND, ABBREVIATIONS
AND SHEET INDEX
FA001
4
DEVICE BOXES AND CONDUIT STUB-OUTS TO ACCESSIBLE
CEILING SPACE PROVIDED BY TRAILER MANUFACTURER.
WIRING, DEVICES AND CONNECTIONS BY ELECTRICAL.
COORDINATE EXACT LOCATIONS WITH TRAILER
MANUFACTURER.
5
PROVIDE MINIMUM 6" X 6" X 4" NEMA 3R PULLBOX FOR FIRE
ALARM POWER SUPPLY CONNECTIONS, MOUNTED ON
TRAILER EXTERIOR. PROVIDE CONDUIT UP TO PULLBOX
FROM UNDERGROUND.
PROVIDE (1) TYPE M AND (1) TYPE P FIRE ALARM
CONDUCTORS, RUN THROUGH EXISTING EMPTY 2"
CONDUIT.
7
SPLICE PROVIDED FIRE ALARM CONDUCTORS TO
EXISTING CONDUCTORS IN PULLBOX. VERIFY
CONNECTIONS AT THE EXISTING FIRE ALARM POWER
SUPPLY AND PROVIDE ADDITIONAL CONDUCTORS AND
CONNECTIONS AS NECESSARY.
D
O F E S S I ON
AL
S
I T
I N
J
G
PR
No. E16124
ST
6
2900 Bristol Street, Suite E205
Costa Mesa, CA 92626-7909
ph: 714.435.0380
fx: 714.435.0383
A
E
L
L
A
TE ECT R I C
R
FO
OF
CA L I
IA
PROVIDE MINIMUM 12" X 24" X 8" DEEP TRAFFIC-RATED
PULLBOX.
NE ER
GI
EN
H
G
3
2
R A ARCHITECTURE
N
EXTEND EXISTING FIRE ALARM VISUAL AND DATA WIRING
FROM EXISTING FIRE ALARM POWER SUPPLY TO VILLAGE
12 FIRE ALARM POWER SUPPLY.
E
2
2
ER
6" X 6" X 4" NEMA 3R FIRE ALARM PULLBOX ON TRAILER
EXTERIOR PROVIDED BY TRAILER MANUFACTURER.
COORDINATE WITH MANUFACTURER FOR EXACT
LOCATION PRIOR TO SITEWORK. PROVIDE CONDUIT UP
TO PULLBOX FROM UNDERGROUND.
J A
(E) FIRE ALARM POWER SUPPLY 'FA7'
1
R EG I S T
NOTES
architecture
planning
interiors
GENERAL NOTES
1.
CONDUIT FOLLOWS COMMUNICATION AND POWER
CONDUITS IN SHARED DUCT BANK WHERE POSSIBLE. SEE
UNDERGROUND CONDUIT TRENCH DETAIL 1 ON SHEET
E501.
2.
DISTRICT TO PROVIDE 3RD PARTY SOIL TESTING TO
VERIFY 95% COMPACTION OF TRENCHES PER THE
REQUIREMENTS OF THE DSA TESTING AND INSPECTION
FORMS. COORDINATE WITH INSPECTOR OF RECORD FOR
MORE INFORMATION.
P2S Engineering, Inc.
5000 East Spring Street, 8th Floor
Long Beach, CA 90815-5218
T 562.497.2999 F 562.497.2990
www.p2seng.com
2"C - 1M, 1P (70')
2"C - 1M, 1V (40')
4
Z12-26
Z12-25
Z12-27
1
4
Z12-23
Division of the State Architect
San Diego Regional Office
16680 West Bernardo Drive
San Diego, California 92127
ph: 858.674.5400
fx:
858.674.5471
2"C - 1M, , 1V, 1P (70')
J
Z12-28
Z12-24
75cd
FA-V12.3-1
WP
FA-V12.3-2
WP
FA-V12.2-4
4
Z12-22
Z12-18
Z12-20
75cd
FA-V12.2-3
Z12-21
Z12-17
2"C - 1M, 1V (15')
1M
1V
J
3
J
1
1"C - 1M, 1V (5')
Z12-14
Z12-11
Z12-13
75cd
FA-V12.2-1
Z12-12
2"C - 1M, 2V, 1P (65')
4
WP
FA-V12.2-2
Z12-15
WP
FA-V12.1-4
WP
FA-V12.1-1
75cd
FA-V12.1-2
75cd
FA-V12.1-3
Z12-7
1M
Z12-1
J
4
Z12-6
Z12-5
J7819-FA101
5
1V
4
Z12-3
Z12-2
A, Sassoon
J. Singh
FIRE ALARM POWER
SUPPLY 'FA-V12'
SITE PLAN
NORTH
1
SITE PLAN
1/8" = 1'-0"
0
8
FA101
18MM/6SM
IN LINE EQUALIZER
A OR AMP
ABF
ACCU
AFF
AIC
ARCH.
AWG
BDF
OPTICAL CONNECTOR
OPTICAL ATTENUATOR
BUILDING NUMBER
RF ATTENUATER
FIBER OPTIC CABLE WITH SIX MULTIMODE FIBERS.
DIRECTIONAL COUPLER
FIBER OPTIC CABLE WITH EIGHTEEN MULTIMODE & 6 SINGLEMODE
FIBERS.
8-PORT TAP
OPTICAL TRANSMITTER
100 CABLE PAIRS.
CONCEALED CONDUIT
TWO WAY SPLITTER
EXPOSED CONDUIT
INDOOR TWO WAY SPLITTER
EXISTING EXPOSED CONDUIT
THREE WAY SPLITTER
UNDERGROUND CONDUIT
INDOOR THREE WAY SPLITTER
EXISTING UNDERGROUND CONDUIT
FOUR WAY SPLITTER
FUTURE CONDUIT
COPPER CABLE
SIX WAY SPLITTER
EXISTING COPPER CABLE
EIGHT WAY SPLITTER
FIBER CABLE
EXISTING FIBER CABLE
COAXIAL CABLE
EXISTING COAXIAL CABLE
CABLE TO BE REMOVED
EXISTING CABLE TO BE ABANDONED OR RETURNED
COPPER CABLE TAPER SPLICE
STRAIGHT COPPER CABLE SPLICE
CONDUIT TURNED UP
CONDUIT TURNED DOWN
CONDUIT WITH CAP
VOICE/DATA OUTLET-WALL MOUNTED
DATA OUTLET-WALL MOUNTED
VOICE OUTLET-WALL MOUNTED
VIDEO (COAXIAL) OUTLET-WALL MOUNTED
VOICE/DATA OUTLET-SURFACE MOUNTED
DATA OUTLET-SURFACE MOUNTED
VOICE OUTLET-SURFACE MOUNTED
VIDEO (COAXIAL) OUTLET-SURFACE MOUNTED
VOICE/DATA OUTLET-FLOOR MOUNTED
DATA OUTLET-FLOOR MOUNTED
VOICE OUTLET-FLOOR MOUNTED
VIDEO (COAXIAL) OUTLET-FLOOR MOUNTED
VOICE/DATA OUTLET-CEILING MOUNTED
DATA OUTLET-CEILING MOUNTED
VOICE OUTLET-CEILING MOUNTED
VIDEO (COAXIAL) OUTLET-CEILING MOUNTED
K
KEY PAD
REFERENCE WILL BE MADE TO ANSI Y1.1, MILITARY
STANDARD IN THE EVENT ABBREVIATIONS NOT MENTIONED
HEREIN ARE USED, ABBREVIATIONS, AND OTHER STANDARD
INDUSTRY CONVENTIONS.
O
D
1-24
SM
2.
IN THE EVENT OF A CONFLICT OR INCONSISTENCY BETWEEN ITEMS INDICATED ON THE PLANS AND/OR
SPECIFICATIONS OR WITH CODE REQUIREMENTS, THE NOTE SPECIFICATION OR CODE WHICH
PRESCRIBES AND ESTABLISHES THE MORE COMPLETE JOB OR THE HIGHER STANDARD SHALL
PREVAIL.
MM
MULTI-MODE
2
SINGLE-MODE
DESIGNATION BY NUMBERS OF
FIBER STRANDS IN CABLE
DESIGNATION OF THIS
PARTICULAR CABLE
3.
OPTICS
FIBER
COPPER CABLE DESIGNATION
OMISSIONS FROM THE DRAWINGS OR SPECIFICATIONS OR THE MISDESCRIPTION OF DETAILS OF
WORK WHICH ARE CLEAR AND NECESSARY TO CARRY OUT THE INTENT OF THE DRAWINGS AND
SPECIFICATIONS, OR WHICH ARE CUSTOMARILY PERFORMED, SHALL NOT RELIEVE THE CONTRACTOR
FROM PERFORMING SUCH OMITTED OR MISDESCRIBED DETAILS OF THE WORK BUT THEY SHALL BE
PERFORMED AS IF FULLY AND CORRECTLY SET FORTH AND DESCRIBED IN THE DRAWINGS AND
SPECIFICATIONS.
1-1500
DESIGNATION BY NUMBERS OF
COPPER PAIRS IN CABLE
DESIGNATION OF THIS
PARTICULAR CABLE
ALL MATERIALS AND EQUIPMENT SHALL BE NEW AND SHALL BEAR THE UNDERWRITERS LABEL (UL)
AND SHALL BE INSTALLED IN THE MANNER FOR WHICH THEY ARE DESIGNED AND APPROVED.
6.
THE CONTRACTOR SHALL NOT BORE, NOTCH OR IN ANYWAY CUT INTO ANY STRUCTURAL MEMBER
WITHOUT WRITTEN APPROVAL FROM THE ARCHITECT OR STRUCTURAL ENGINEER.
7.
FOR PURPOSES OF CLEARNESS AND LEGIBILITY THE TELECOM DRAWINGS ARE ESSENTIALLY
DIAGRAMMATIC. THE SIZE AND LOCATION OF EQUIPMENT IS SHOWN TO SCALE WHEREVER POSSIBLE.
THE CONTRACTOR SHALL VERIFY ALL CONDITIONS, DATA INFORMATION AS INDICATED ON THE
DRAWINGS AND IN THE SPECIFICATION SECTIONS WHERE TELECOM WORK INTERFACES WITH OTHER
TRADES.
8.
CONTRACTOR TO SEE ELECTRIC DRAWINGS FOR STATION CABLE PATHWAYS.
P2S Engineering, Inc.
9.
USE "J" HOOKS FOR THE BULK OF THE STATION CABLE DISTRIBUTION. DO NOT USE CEILING TILE WIRE
HANGERS, WATER OR ELECTRICAL PIPES, OR LIGHT FIXTURES TO HANG CABLE. CABLE MUST BE A
MINIMUM OF SIX INCHES ABOVE THE CEILING TILE AND MUST NOT COME WITHIN TWELVE INCHES OF A
LIGHT FIXTURE.
5000 East Spring Street, 8th Floor
Long Beach, CA 90815-5218
T 562.497.2999 F 562.497.2990
10. ALL STATION CABLES SHALL BE NEATLY DRESSED AND SECURED EVERY FIVE FEET AT A MINIMUM.
No. E16124
A
E
L
L
A
TE ECT R I C
R
FO
OF
CA L I
www.p2seng.com
11. THE CONTRACTOR SHALL BE RESPONSIBLE FOR REMOVAL AND REPLACEMENT OF CEILING TILE
INCLUDING REPLACEMENT OF BROKEN OR DAMAGED TILES.
12. ALL LOCATIONS PASSING THROUGH A FIRE OR A SMOKE BARRIER MUST BE FIRE STOPPED USING
APPROVED (UL CLASSIFIED) FIRE STOP MATERIAL INSTALLED, PER THE MANUFACTURER'S
INSTRUCTIONS.
13. ALL STATION CABLE SHALL BE PLACED WITH A MINIMUM 1 METER MAINTENANCE LOOP ABOVE CEILING
AT EACH LOCATION.
14. CONDUIT SHALL BE FILLED TO MAXIMUM CAPACITY (PER STANDARD) BEFORE UTILIZING ANOTHER
VACANT CONDUIT.
15. ALL STATION OUTLETS AND TERMINALS INCLUDING EXISTING SHALL BE PROPERLY IDENTIFIED USING
THE STANDARD CAMPUS INTERNAL DISTRIBUTION NUMBERING SCHEME. ALL LABELS BE PREPRINTED
OR TYPED.
16. EACH OSP CABLE SHALL BE EQUIPPED WITH A PERMANENT LABEL INDICATING CABLE TYPE, PAIR OR
OPTIC COUNTS, DISTANT END AND CABLE LENGTH. BOTH ENDS SHALL OF EACH CABLE SHALL BE SO
LABELED.
Division of the State Architect
San Diego Regional Office
16680 West Bernardo Drive
San Diego, California 92127
ph: 858.674.5400
fx:
858.674.5471
17. FIBER CABLE SHALL BE PLACED WITH SIX FOOT (6) MAINTENANCE LOOP AT BOTH ENDS OF THE RUN.
THE MAINTENANCE LOOP SHALL BE SECURED IN SUCH A MANNER TO PROVIDE PROTECTION DURING
SUBSEQUENT CABLE PULLS.
18. ANY DEVIATIONS FROM PLANS OR SPECIFICATIONS MUST BE APPROVED IN WRITING BY THE ENGINEER
AND DISTRICT REPRESENTATIVE.
19. ALL NEW STATION CABLES/OUTLETS SHALL BE TESTED AND DOCUMENTED USING A PAIR SCANNER
SPECIFICALLY DESIGNED TO TEST THE TYPE OF CABLE INSTALLED (CATEGORY 6). TEST RESULTS
SHALL BE ONE PAGE PER AND NOTED WITH THE STATION/JACK NUMBERING SCHEME THAT IS
STANDARDIZED FOR THE DISTRICT.
20. ALL WORK MUST BE COMPLETED IN A NEAT AND PROFESSIONAL MANNER. THE WORK SITE SHALL BE
KEPT CLEAN AND ALL DAMAGE TO DISTRICT PROPERTY REPAIRED. THE CONTRACTOR SHALL BE
RESPONSIBLE FOR CONDUCTING A FINAL CLEANUP OF THE WORK SITE PRIOR TO FINAL SYSTEM
ACCEPTANCE.
21. ALL FIBER OPTIC STATION AND RISER CABLE SHALL BE TESTED END-TO-END AND THE RESULTS (LOSS
IN DB) NOTED ON A SEPARATE TYPED SHEET.
22. LADDER RACK SHALL BE PLACED IN MDF AS SHOWN ON DRAWINGS AND AS REQUIRED TO PROPERLY
SECURE CABLES AND WIRE.
23. FIBER CABLES SHALL BE SPLICED TOGETHER USING A FUSION SPLICE AND PLACED IN A FIBER SPLICE
CASE THAT IS RE-ENTERABLE, FULLY DRESSED AND ENCLOSED TO FIT THE NUMBER AND TYPE OF
CABLES TERMINATED.
24. ALL FOOTAGES ON DRAWINGS ARE ESTIMATED AND MUST BE VERIFIED BY CONTRACTOR PRIOR TO
ORDERING MATERIAL.
25. ALL CABLE TRAYS, LADDER RACKS, CONDUIT, EQUIPMENT RACKS, PROTECTOR PANELS, AND CABLE
SHEATHS SHALL BE BONDED & GROUNDED TO EQUIPMENT GROUND WITH #6 WIRE.
PROXIMITY CARD READER
27. PULL ROPES SHALL BE PLACED IN ALL VACANT CONDUITS.
AR
PROXIMITY CARD READER WITH KEY PAD
28. ALL CHANGES TO STRUCTURES (BUILDING, DRILLING, CORING, ETC.) NOT SHOWN ON THE DRAWINGS
SHALL BE APPROVED IN WRITING BY STRUCTURAL ENGINEER.
D
ELECTRIFIED DOOR LATCH
MD
O F E S S I ON
AL
S
I T
I N
J
G
PR
5.
26. ALL SPLICES SHALL BE CONTAINED WITHIN AN APPROVED SPLICE CASE DESIGNED FOR MULTIPLE
CLOSURE.
A
D
THE CONTRACTOR SHALL CHECK ALL DRAWINGS FURNISHED IMMEDIATELY UPON THEIR RECEIPT AND
SHALL PROMPTLY NOTIFY THE OWNER OF ANY DISCREPANCIES.
CARD READER
CR
2900 Bristol Street, Suite E205
Costa Mesa, CA 92626-7909
ph: 714.435.0380
fx: 714.435.0383
4.
EXAMPLE: 1500X 1500 PAIR CABLE
5,
R A ARCHITECTURE
ST
EXISTING CONCEALED CONDUIT
OPTICAL RECEIVER
F
ALL TELECOMMUNICATIONS WORK SHALL COMPLY WITH THE LATEST EDITION OF THE BSUD
TELECOMMUNICATIONS INFRASTRUCTURE STANDARDS AND ALL OTHER APPLICABLE FEDERAL, STATE
AND LOCAL CODES. WHERE THE CONSTRUCTION DOCUMENTS INDICATE MORE RESTRICTIVE
REQUIREMENTS, THE DOCUMENTS SHALL GOVERN BUT THE CONSTRUCTION DOCUMENTS SHALL NOT
BE INTERPRETED AS AUTHORITY TO VIOLATE ANY CODE OR REGULATION.
NE ER
GI
EN
H
G
100X
C
CKT
CLG.
C.O.
CU
DWG
EA
EMT
ENT
EQUIP
EXIST / (E)
E/W
FCU
FIN.
FIXT
FLR
FLUOR
FOC
FT
FTU
GFI
GRC
GND
IDF
JB
LTG.
MDF
MH
MM
MTG.
N
NEC
NIC
NO.
PH
PNL
PWR
P.O.C.
PRO
REC/RECEPT
REQ'D
RM
SF
SHT
SM
SP
SPECS
SW
TDU
TYP
TERM
UG
U.O.N.
V
V-A
W
W/
W/O
AMPERES
AIR BLOWN FIBER
AIR COOLED CONDENSING UNIT
ABOVE FINISHED FLOOR
AMPERE INTERRUPTING CAPACITY
ARCHITECT; ARCHITECTURAL
AMERICAN WIRE GAUGE
BUILDING DISTRIBUTION FRAME
CONDUIT
CIRCUIT
CEILING
CONDUIT ONLY WITH PULL WIRE
COPPER
DRAWING
EACH
ELECTRICAL METALLIC TUBING
ELECTRICAL NONMETALLIC TUBING
EQUIPMENT
EXISTING
EQUIPPED WITH
FAN COIL UNIT
FINISH
FIXTURE
FLOOR
FLUORESCENT
FIBER OPTIC CABLE
FEET
FIBER TERMINAL UNIT
GROUND FAULT INTERRUPTER
GALVANIZED RIGID CONDUIT
GROUND
INTERMEDIATE DISTRIBUTION FRAME
JUNCTION BOX
LIGHTING
MAIN DISTRIBUTION FRAME
MOUNTING HEIGHT
MULTIMODE
MOUNTING
NORTH
NATIONAL ELECTRICAL CODE
NOT IN CONTRACT
NUMBER
PHASE
PANEL
POWER
POINT OF CONNECTION
PROTECTED TERMINAL
RECEPTACLE
REQUIRED
ROOM
SQUARE FEET
SHEET
SINGLE MODE
SINGLE POLE
SPECIFICATIONS
SWITCH
TERMINAL DISTRIBUTION UNIT
TYPICAL
TERMINATION
UNDERGROUND
UNLESS OTHERWISE NOTED
VOLTS
VOLT-AMPERES
WATTS
WITH
WITHOUT
1.
IA
6MM
ABBREVIATION DESCRIPTION
N
DETAIL CALLOUT
- NUMBER ON TOP DENOTES DETAIL NUMBER
- NUMBER ON BOTTOM DENOTES SHEET DETAIL IS SHOWN
DESCRIPTION
E
NOTE CALLOUT
SYMBOL
GENERAL NOTES
ER
-
DESCRIPTION
FIBER CABLE DESIGNATION
J A
SYMBOL
ABBREVIATIONS
R EG I S T
LEGEND
architecture
planning
interiors
29. ALL STATIONS CABLES SHALL BE TERMINATED ON THE SAME FLOOR BDF OR IDF UNLESS OTHERWISE
NOTED.
MOTION DETECTOR
M
MONITOR
IC
INTERCOM
PANIC BUTTON
FIXED CEILING MOUNT CAMERA
12" CABLE TRAY
30. ALL STATION CABLE SHALL BE PLACED INTO CEILING AND WALL SPACES UNLESS SPECIFICALLY
NOTED IN THE CONTRACT DOCUMENTS. NO CABLES SHALL BE PLACED EXPOSED BUT MUST BE
INSTALLED WITHIN CONDUIT, WALL AND CEILING SPACES, OR SURFACE MOUNTED RACEWAY.
31. PULLBOXES MUST BE USED ON ANY INTRA-BUILDING CONDUIT RUN MORE THAN 100 FEET IN LENGTH
OR WITH MORE THAN 180 DEGREES OF BEND. PULLBOXES SHALL BE A MINIMUM OF TWELVE (12)
TIMES THE DIAMETER OF THE LARGEST CONDUIT. ALL COMMUNICATIONS CONDUIT SHALL ENTER AND
LEAVE PULL BOXES IN THE SAME DIRECTION - NO RIGHT ANGLE BENDS WILL BE ALLOWED WITHIN
PULL BOXES.
J7819-T001
A. Sassoon
J. Singh
SHEET INDEX
18" CABLE TRAY
24" CABLE TRAY
SAW CUT TO PLACE NEW CONDUITS
SHEET
DESCRIPTION
T001
GENERAL NOTES, LEGEND, ABBREVIATIONS AND SHEET INDEX
T101
FIBER OPTIC SITE PLAN
T102
TELECOMMUNICATIONS SITE PLAN
EXISTING SAW CUT
LADDER RACK
19" X 7' EQUIPMENT RACK
TELECOMMUNICATIONS PULLBOX
COPPER CABLE CROSSCONNECT (BDF)
COPPER CABLE CROSSCONNECT (IDF)
MAIN BUILDING FIBER TERMINAL (BDF)
INTERMEDIATE FIBER TERMINAL (IDF)
PROTECTED CROSS CONNECT TERMINAL
GENERAL NOTES,
LEGEND, ABBREVIATIONS
AND SHEET INDEX
75 OHM TERMINATOR
AMPLIFIER
T001
PROVIDE 2-CELL AIR BLOWN FIBER DUCT TO MH-39 VIA
HH-34, HH-35 AND HH-36.
5
CONNECTION TO EXISTING ABF NETWORK IN MH-39 VIA
HANDHOLES 34, 35 & 36. ROUTE FIBER OPTIC CABLE
BACK TO MDF VIA EXISITNG SPARE CELL IN 19-CELL ABF
CABLE.
EXISTING MAIN DISTRIBUTION FRAME (MDF) IN LIBRARY.
O F E S S I ON
AL
S
I T
I
J
N
G
PR
No. E16124
A
6
D
E
L
L
A
TE ECT R I C
R
FO
OF
CA L I
IA
4
N
PROVIDE 2" UNDERGROUND CONDUIT WITH 2-CELL AIR
BLOWN FIBER DUCT. ROUTE UNDERGROUND CONDUIT IN
DUCT BANK WITH POWER AND FIRE ALARM CONDUITS
WHERE POSSIBLE. SEE UNDERGROUND CONDUIT
TRENCH DETAIL 1 ON SHEET E501.
E
3
2900 Bristol Street, Suite E205
Costa Mesa, CA 92626-7909
ph: 714.435.0380
fx: 714.435.0383
NE E R
GI
EN
H
G
(1) 12-STRAND SINGLE-MODE FIBER OPTIC CABLE ROUTED
IN ACCESSIBLE CEILING SPACE TO VILLAGE 12 BDF.
ST
2
2
R A ARCHITECTURE
ER
VILLAGE 12 BUILDING DISTRIBUTION FRAME (BDF). PATCH
PANELS PROVIDED BY THE CONTRACTOR, SWITCHES AND
DATA RACK PROVIDED BY THE DISTRICT, INSTALLED BY
COMMUNICATIONS CONTRACTOR. COMMUNICATIONS
CONTRACTOR TO PROVIDE AND INSTALL AIR BLOWN
FIBER (ABF) TERMINAL DISTRIBUTION UNIT (TDU) AND
SUPPORTING FIBER TERMINATION HARDWARE FOR ALL
NEW PROJECT FIBER OPTIC CABLES. (1) 12-STRAND
SINGLE-MODE FIBER OPTIC CABLE CONNECTS VILLAGE 12
BDF TO MAIN DISTRIBUTION FRAME IN LIBRARY.
J A
1
R EG I S T
NOTES
architecture
planning
interiors
GENERAL NOTES
1.
NOTIFY COLLEGE MINIMUM 72 HOURS IN ADVANCE OF
ANY CONDUIT AND FIBER INSTALLATION WORK.
2.
DISTRICT TO PROVIDE 3RD PARTY SOIL TESTING TO
VERIFY 95% COMPACTION PER THE REQUIREMENTS OF
THE DSA TESTING AND INSPECTION FORMS.
COORDINATE WITH INSPECTOR OF RECORD FOR MORE
INFORMATION.
P2S Engineering, Inc.
5000 East Spring Street, 8th Floor
Long Beach, CA 90815-5218
T 562.497.2999 F 562.497.2990
3
www.p2seng.com
2
Division of the State Architect
San Diego Regional Office
16680 West Bernardo Drive
San Diego, California 92127
ph: 858.674.5400
fx:
858.674.5471
J7819-T101
A, Sassoon
J. Singh
FIBER OPTIC SITE PLAN
NORTH
1
SITE PLAN
1/16" = 1'-0"
0
8
T101
PROVIDE 2" UNDERGROUND CONDUIT WITH 2-CELL ABF
DUCT FOR FIBER OPTIC ROUTING TO CAMPUS MDF
ROOM. CONDUIT FOLLOWS UNDERGROUND FIRE ALARM
CONDUIT WHERE POSSIBLE.
5
SHARED FIRE ALARM/COMMUNICATIONS PULLBOX.
COORDINATE WITH FIRE ALARM.
6
PROVIDE 2-CELL ABF DUCT IN EXISITNG 4"
UNDERGROUND CONDUIT.
PROVIDE MINIMUM 8" X 12" X 18" NEMA 3R PULLBOX FOR
CAT 5E CONNECTIONS BETWEEN VILLAGE 12 BDF AND
VILLAGE 11.
8
PROVIDE (2) 4" UNDERGROUND CONDUIT. SEE
UNDERGROUND CONDUIT TRENCH DETAIL 1 ON SHEET
E501.
9
ROUTE CAT 5E CABLES FROM VILLAGE 12 BDF SWITCH TO
COMMUNICATIONS DEVICES VIA DEVICE STUB-UPS IN
ACCESSIBLE CEILING SPACE. QUANTITY OF CABLES TO
EACH DEVICE AS SHOWN.
10
PROVIDE 4" RGS CONDUIT IN ACCESSIBLE CEILING SPACE
BETWEEN VILLAGE 11 DEMISING WALLS FOR ROUTING OF
CAT5E CABLES.
11
PROVIDE (1) HDMI AND (1) VGA CONNECTIONS TO
PROJECTION SYSTEM DEVICES. CABLE SHALL BE PLENUM
RATED AND SHALL RUN THROUGH STUBBED-UP CONDUIT
FROM DEVICE TO ACCESSIBLE CEILING SPACE.
12
CONNECTION TO CEILING-MOUNTED HDMI/VGA DEVICE.
13
PROVIDE (1) USB-B AND (1) AUDIO COAX DEVICES,
CONNECTED TO PRESENTATION SYSTEM.
14
EXISTING 11'-7" X 6'-2" WIRE MESH ENCLOSURE TO BE
TRANSPORTED FROM OWNER STORAGE AND INSTALLED
AT LOCATION SHOWN BY THE CONTRACTOR. ANY
ADDITIONAL REQUIRED FITTINGS AND ANCHORAGE TO BE
OBTAINED FROM ENCLOSURE MANUFACTURER (KING
WIRE PARTITIONS INC).
D
O F E S S I ON
AL
S
I T
I N
J
G
PR
No. E16124
A
NE ER
GI
EN
H
G
7
2900 Bristol Street, Suite E205
Costa Mesa, CA 92626-7909
ph: 714.435.0380
fx: 714.435.0383
E
L
L
A
TE ECT R I C
R
FO
OF
CA L I
IA
4
2
R A ARCHITECTURE
N
PROVIDE MINIMUM 6" X 6" X 4" NEMA 3R PULLBOX FOR
CONNECTION TO TRAILER CEILING SPACE. 2" RGS
CONDUIT WITH 2-CELL ABF DUCT DOWN TO
UNDERGROUND COMMUNICATIONS CONDUIT.
E
3
ER
PLENUM RATED SINGLE-MODE FIBER OPTIC CABLE, HUNG
ABOVE CEILING. CABLE CONNECTS VILLAGE 12 BDF AND
CAMPUS MDF.
J A
2
P2S Engineering, Inc.
5000 East Spring Street, 8th Floor
Long Beach, CA 90815-5218
T 562.497.2999 F 562.497.2990
www.p2seng.com
GENERAL NOTES
4
2"C (70')
(2)
LOCATION OF VILLAGE 12 BDF.
ST
2"C (35')
1
R EG I S T
NOTES
architecture
planning
interiors
(2)
(2)
4
1.
NOTIFY COLLEGE MINIMUM 72 HOURS IN ADVANCE OF
ANY CONDUIT AND FIBER INSTALLATION WORK.
2.
DISTRICT TO PROVIDE 3RD PARTY SOIL TESTING TO
VERIFY 95% COMPACTION OF TRENCHES PER THE
REQUIREMENTS OF THE DSA TESTING AND INSPECTION
FORMS. COORDINATE WITH INSPECTOR OF RECORD FOR
MORE INFORMATION.
Division of the State Architect
San Diego Regional Office
16680 West Bernardo Drive
San Diego, California 92127
ph: 858.674.5400
fx:
858.674.5471
(2)
(1)
11
HDMI
VGA
12
10 4"C
(4)
(4)
(4)
(4)
(4)
(4)
(4)
(4)
5
11
12
HDMI
VGA
(1)
2"C (70')
(4)
(4)
(4)
(4)
(2)
8
4
(2)
(2) 4"C (50')
(2)
(2)
13 11
9
11
J7819-T102
HDMI
9
VGA
A, Sassoon
J. Singh
HDMI, +96"
VGA, +96"
2
(2)
(2)
J
3
TELECOMMUNICATIONS
SITE PLAN
NORTH
1
SITE PLAN
1/8" = 1'-0"
0
8
T102
PROJECT MANUAL
for:
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
28000 Marguerite Parkway
Mission Viejo, CA 92692
Prepared By:
R2A Architecture
2900 Bristol Street, Suite E-205
Costa Mesa, CA 92626
(714) 435-0380
15018.00
09/28/2015
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
Seals Page
ARCHITECT
R2A Architecture
2900 Bristol Street, Suite E-205
Costa Mesa, CA 92626-7909
P: (714) 435-0380
F: (714) 435-0383
Architect of Record:
License:
Expiration Date:
Etienne G. Runge, AIA
C 28482
10-31-2015
ELECTRICAL ENGINEER
P2S Engineering, Inc.
5000 Spring Street, 8th Floor
Long Beach, CA 90815
P: (562) - 497-2999
F: (562) - 497-2990
Electrical Engineer of Record:
License:
Expiration Date:
Jagjit Singh
E16124
03/2016
Seals Page
Page Number - 1
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables #11, 12, 13 Addendum No. 2
Saddleback College
South Orange County Community College District
TABLE OF CONTENTS
Introductory Documents
Title Page
Seals Page
Table of Contents
Division 27
Communications
27 05 26
27 05 28
27 11 00
27 13 13
27 13 23
Grounding and Bonding for Communication Systems
Pathways for Communication Systems
Communications Equipment Room Fittings
Communications Copper Backbone Cabling
Communications Optical Fiber Backbone Cabling
End of Table of Contents
Table of Contents
1
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
SECTION 27 05 26
GROUNDING AND BONDING FOR COMMUNICATIONS SYSTEMS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A.
SECTION 27 05 28 - PATHWAYS FOR COMMUNICATIONS SYSTEMS.
B.
SECTION 27 11 00 - COMMUNICATIONS EQUIPMENT ROOM FITTINGS.
C.
SECTION 27 13 13 - COMMUNICATION COPPER BACKBONE CABLING.
D.
SECTION 27 13 23 - COMMUNICATIONS OPTICAL FIBER BACKBONE
CABLING.
1.2 WORK INCLUDED
A.
Provide all labor, materials, tools and equipment required for the complete
installation of work called for in the Construction Documents
1.3 SCOPE OF WORK
A.
This document describes the products and execution requirements relating to
furnishing and installing Grounding/Earthing and Bonding for
Communications Systems.
B.
This section includes minimum requirements for the following:
• Grounding/Earthing System
• Telecommunications Grounding Busbar (TGB)
• Telecommunications Main Grounding Busbar (TMGB)
• Telecommunications Bonding Backbone (TBB)
• Rack Grounding/Earthing and Bonding
C.
All cables and related terminations, support and grounding/earthing hardware
shall be furnished, installed, wired, tested, labeled, and documented by the
telecommunications contractor as detailed in this document.
D.
Product specifications, general design considerations, and installation
guidelines are provided in this document. Quantities grounding/earthing
products, typical installation details and cable routing will be provided as an
attachment to this document. If the bid documents are in conflict, this
specification shall take precedence. The successful vendor shall meet or
exceed all requirements for the cable system described in this document.
1.4 REGULATORY REFERENCES
Grounding and Bonding for Communications Systems
27 05 26 - 1
R2A Architecture
Costa Mesa, CA
09/28/2015
A.
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
The following industry standards are the basis for the grounding/earthing and
bonding system described in this document.
1. TIA/EIA
•
TIA-942
Telecommunications Infrastructure
Standard for Data Centers
•
J-STD-607-B
Commercial Building Grounding/Bonding
Requirements
•
TIA/EIA-606
Administration Standard for the
Telecommunications
Infrastructure of Commercial Buildings
2. IEEE
• Std 1100 IEEE
Recommend Practice for Powering and
Grounding Electronic Equipment (IEEE
Emerald Book)
3. NFPA
• NFPA-70
National Electric Code (NEC)
B.
Federal, state, local codes, rules, regulations and ordinances governing the
work, as well as S.O.C.C.C.D. guidelines and practices may apply and shall
be incorporated as part of these specifications.
C.
In reviewing the various Contract Documents, the Structured
Telecommunications Cable Contractor shall be responsible for noting
conflicts between proposed design/concepts and the applicable standards,
guidelines and practices. A written Request for Information (RFI) shall be
developed by the Structured Telecommunications Cable Contractor and
submitted to S.O.C.C.C.D prior to commencing any work impacted by such
conflicts. Such RFIs shall describe the conflict/violation and, if appropriate,
recommend alternative solutions with associated costs. S.O.C.C.C.D
warrants that they will diligently strive to address such RFIs in order to
minimize negative impact on each SCCS installation completion schedule.
D.
Where the requirements of the Contract Documents are more stringent than
applicable codes, rules, regulations, ordinances, standards, guidelines and
practices, the Contract Documents shall apply. In all other instances, the
most current standards, guidelines and practices shall apply.
1.5 QUALITY ASSURANCE
A.
See the Panduit Electrical Product Warranty on www.panduit.com/warranty
1.6 APPROVED PRODUCTS
A.
Approved grounding/earthing system manufacturer: PANDUIT
Grounding and Bonding for Communications Systems
27 05 26 - 2
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
B.
Approved telecommunications grounding busbar manufacturer: PANDUIT
C.
Approved rack grounding kit manufacturer: PANDUIT
D.
Approved retrofit rack grounding kit manufacturer: PANDUIT
1.7 DEFINITIONS
A.
Bonding – The permanent joining of metallic parts to form an electrically
conductive path that will assure electrical continuity and the capacity to
conduct safely any current likely to be imposed.
B.
Common Bonding Network (CBN) – The principal means for affecting
bonding and earthing inside a building.
C.
Ground/Earth – A conducting connection, whether intentional or incidental, by
which an electric circuit or equipment is connected to earth, or to some
conducting body of relatively large extent that serves in place of the earth.
D.
Retrofit Rack Grounding/Earthing – The application of grounding/earthing
products and technology where equipment is already deployed and
functioning.
1.8 OVERVIEW
A.
The purpose of the grounding/earthing system is to create a low impedance
path to earth ground for electrical surges and transient voltages. Lightning,
fault currents, circuit switching (motors turning on and off), and electrostatic
discharge are common causes of these surges and transient voltages. An
effective grounding/earthing system minimizes the detrimental effects of
these electrical surges, which include degraded network performance and
reliability and increased safety risks.
B.
The grounding/earthing system must be intentional, visually verifiable,
adequately sized to handle expected currents safely, and directs these
potentially damaging currents away from sensitive network equipment. As
such, grounding/earthing must be purposeful in its design and installation.
Four issues require special consideration:
1. Although AC powered equipment typically has a power cord that contains
a ground/earth wire, the integrity of this path cannot be easily verified.
Thus, many equipment manufacturers require grounding/earthing above
and beyond that which is specified by local electrical codes, such as the
National Electrical Code, etcetera. Always follow the grounding/earthing
recommendations of the manufacturer when installing equipment.
Grounding and Bonding for Communications Systems
27 05 26 - 3
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
2. While the building steel and metallic water piping must be bonded to the
grounding/earthing system for safety reasons, neither may be substituted
for the telecommunications bonding backbone (TBB).
3. Electrical continuity throughout each rack or cabinet is required to
minimize safety risks. Hardware typically supplied with bolt-together
racks is not designed for grounding/earthing purposes. Additionally, most
racks are painted. Paint is an insulator. Unless rack members are
deliberately bonded, continuity between members is incidental, and in
many cases, unlikely.
4. Any metallic component that is part of the data center, including
equipment, racks, ladder racks, enclosures, cable trays, etc. must be
bonded to the grounding/earthing system.
1.9 WORKMANSHIP
A.
The ground/earth system must be designed for high reliability. Therefore, the
grounding/earthing system shall meet following criteria:
1. Local electrical codes shall be adhered to.
2. The grounding/earthing system shall comply with ANSI/TIA-942 and
J-STD-607-A.
3. All grounding/earthing conductors shall be copper.
4. Lugs, HTAPs, grounding strips, and busbars shall be UL Listed and made
of premium quality tin-plated electrolytic copper that provides low
electrical resistance while inhibiting corrosion. Antioxidant shall be used
when making bonding connections in the field.
5. Wherever possible, two-hole lugs shall be used because they resist
loosening when twisted (bumped) or exposed to vibration. All lugs shall
be irreversible compression and meet NEBS Level 3 as tested by
Telcordia. Lugs with inspection windows shall be used in all noncorrosive environments so that connections may be inspected for full
conductor insertion (battery rooms are an exception where windowless
lugs may be used).
6. Die index numbers shall be embossed on all compression connections to
allow crimp inspection.
7. Cable assemblies shall be UL Listed and CSA Certified. Cables shall be
a distinctive green or green/yellow in color, and all jackets shall be UL,
VW-1 flame rated.
Grounding and Bonding for Communications Systems
27 05 26 - 4
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
PART 2 - PRODUCTS
2.1 EQUIVALENT PRODUCTS
A.
PANDUIT shall manufacture all products, including but not limited to
grounding/earthing and bonding for communications systems.
B.
Products of equal performance and warranty will be allowed.
2.2 GROUNDING/EARTHING AND BONDING
A.
The Telecommunications Grounding Busbar (TGB) in each
telecommunications space will be grounded/earthed to the
Telecommunications Main Grounding Busbar (TMGB) located at the service
entrance. The gauge of the connecting ground/earth cable, known as the
Telecommunications Bonding Backbone (TBB) will follow J-STD-607-A
guidelines, as is shown in the table below.
Sizing of the TBB
TBB Length in Linear meters (feet)
TBB Size (AWG)
Less than 4 (13)
6
4-6 (14-20)
4
6-8 (21-26)
3
8-10 (27-33)
2
10-13 (34-41)
1
13-16 (42-52)
1/0
16-20 (53-66)
2/0
Greater than 20 (66)
3/0
B.
The TMGB will be bonded to building steel and grounded/earthed to the
electrical service ground according to BICSI TDM Manual and J-STD-607-B
guidelines. Local codes may supersede these requirements. In
telecommunications spaces with only one rack, the rack jumper cable can be
connected directly to the TGB.
Cable Sizes for Other Grounding/Earthing Applications
Purpose
Copper Code Cable Size
Aisle grounds (overhead or under
#2 AWG or larger (1/0 preferred)
floor) of the common bonding
network
Bonding conductor to each PDU or
Size per NEC 250.122 &
panel board serving the room.
manufacturer recommendations
Bonding conductor to HVAC
6 AWG
equipment
Building columns
4 AWG
Cable ladders and trays
6 AWG
Conduit, water pipe, duct
6 AWG
Grounding and Bonding for Communications Systems
27 05 26 - 5
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
2.3 COMPONENTS, KITS AND HARDWARE
A.
PANDUIT® StructuredGround™ Grounding System (StructuredEarth™
Earthing System) kits, components, and hardware shall be used to construct
the grounding/earthing system.
B.
Use PANDUIT GB4 series BICSI/J-STD-607-A telecommunications
grounding busbars for the TMGB, which is ideally located at the AC service
entrance. Use a PANDUIT GB2 series busbar for the TGB in each of the
other telecommunications/equipment spaces throughout the building. Use
PANDUIT
LCC-W series lugs when connecting conductors to the TMGB and TGB.
C.
Route the TBB to each TGB in as straight a path as possible. The TBB
should be installed as a continuous conductor, avoiding splices where
possible. Use PANDUIT HTAP kits, family HTWC, to provide a tap from the
TBB to each TGB. When more than one TBB is used, bond them together
using the TGBs on the top floor and every third floor in between with a
conductor known as a Grounding Equalizer (GE). Use the J-STD-607-A
guidelines for sizing of the TBB when sizing the GE (shown in the table
above).
D.
Avoid routing grounding/earthing conductors in metal conduits. If the
grounding/earthing conductor must be routed through a metal conduit, bond
each end of the conduit to the grounding/earthing conductor. Use PANDUIT
GPL series grounding clamps to bond to the conduit, a PANDUIT HTWC
HTAP with clear cover to bond to the grounding/earthing conductor, and a #6
AWG copper conductor to connect the GPL grounding clamp to the HTWC
HTAP.
2.4 RACK GROUNDING/EARTHING
A.
Equipment and racks shall be bonded in accordance with the methods
prescribed in ANSI/TIA-942, as is shown in the figure below.
Grounding and Bonding for Communications Systems
27 05 26 - 6
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
Aisle Ground
Common Bonding Network to
Rack Jumper (Alternate
Location)
Paint Piercing
Grounding Washer
Rack Ground Strip
Electrostatic
Discharge (ESD) Port
Standard Equipment
Rack
Network Equipment
Equipment Jumper
Common Bonding Network
Common Bonding
Network to Rack Jumper
Figure 1 - Properly Grounded/Earthed Rack (Back of Rack Shown)
B.
To provide electrical continuity between rack elements, PANDUIT paint
piercing grounding washers, series RGW, shall be used where rack sections
bolt together, on both sides, under the head of the bolt and between the nut
and rack.
C.
All racks shall utilize a full-length rack ground strip, PANDUIT part number
RGS134, attached to the rear of the side rail with the thread-forming screws
provided to ensure metal-to-metal contact.
Grounding and Bonding for Communications Systems
27 05 26 - 7
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
D.
Mount an electrostatic discharge (ESD) port kit, PANDUIT part number
RGESD-1 directly to the rack grounding strip on the back of the rack at
approximately 48 inches from the floor. Mount a second RGESD-1 directly to
the vertical mounting rail of the rack in the front at approximately the same
height. Use the thread-forming screws provided to form a bond to the rack.
Place the ESD protection identification stickers directly above the ESD ports.
E.
When the equipment manufacturer provides a location for mounting a
grounding connection, that connection shall be utilized. Use the appropriate
PANDUIT RG series jumper for the equipment being installed and the threadforming screws provided in the kit.
F.
Use PANDUIT part number RGCBNJ660P (common bonding network to rack
jumper) to attach the rack ground strip to the common bonding network. Do
not bond racks or cabinets serially. Use the copper compression HTAP that
comes with the kit to bond the conductor to the common bonding network.
G.
Patch panels will be bonded to racks using the PANDUIT bonding screws,
part number RGTBS-C for racks having #12-24 equipment mounting holes,
and RGTBSM6-C for racks having M6 equipment mounting holes.
2.5 RETROFIT RACK GROUNDING/EARTHING
A.
If the racks already have network equipment installed, it may not be feasible
to install the rack ground strip without disrupting data cables. Further, it may
be undesirable to disassemble rack hardware to install paint piercing
grounding washers. In these circumstances, the PANDUIT retrofit rack
grounding kits, PANDUIT part family RGR, are to be installed.
B.
For retrofit rack grounding/earthing installations, use PANDUIT part number
RGRKCBNJ to ground/earth the rack to the common bonding network. Use
PANDUIT part number RGEJ696 (provided with #6 AWG grounding
conductor) or PANDUIT part number RGEJ1096 (provided with #10 AWG
grounding conductor) to ground/earth equipment chassis to the rack
grounding busbar provided with the RGRKCBNJ as is shown in the figure
below.
Grounding and Bonding for Communications Systems
27 05 26 - 8
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
Network Equipment
Rack Grounding Busbar
Grounding Jumper
Grounding Jumper
Figure 2 - Retrofit Rack Grounding/Earthing
C.
RGW paint piercing grounding washers are not used in this scenario. Thus,
the grounding busbar provides continuity through the vertical channels of the
rack, but not the top and bottom of the rack. Thus, wherever practical, the
solution using the RGS rack grounding strip and the RGW paint piercing
washers shall be used instead of the retrofit rack grounding kits.
D.
All other grounding/earthing requirements apply to retrofit installations without
exception.
E.
Use PANDUIT® STRUCTUREDGROUND™ Grounding System
(STRUCTUREDEARTH™ Earthing System) in every application possible. See
http://www.panduit.com for the latest grounding and bonding solutions.
Grounding and Bonding for Communications Systems
27 05 26 - 9
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
PART 3 - EXECUTION
3.1 GROUNDING SYSTEM
The communications grounding system shall be designed and/or approved by a
qualified PE, or RCDD. The communications grounding system shall adhere to the
recommendations of the ANSI/TIA-942 and J-STD-607-B standards, and shall be
installed in accordance with best industry practice.
A licensed electrical contractor shall perform installation and termination of the main
bonding conductor to the building service entrance ground.
END OF SECTION 27 05 26
Grounding and Bonding for Communications Systems
27 05 26 - 10
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
SECTION 27 05 28
PATHWAYS FOR COMMUNICATIONS SYSTEMS
PART 1 - GENERAL
1.1
1.2
RELATED DOCUMENTS
A.
SECTION 27 05 26 - GROUNDING AND BONDING FOR
COMMUNICATIONS SYSTEMS.
B.
SECTION 27 11 00 - COMMUNICATIONS EQUIPMENT ROOM FITTINGS.
C.
SECTION 27 11 16 - COMMUNICATIONS CABINETS AND ENCLOSURES.
D.
SECTION 27 13 13 - COMMUNICATION COPPER BACKBONE CABLING.
E.
SECTION 27 13 23 - COMMUNICATIONS OPTICAL FIBER BACKBONE
CABLING.
WORK INCLUDED
A.
1.3
Provide all labor, materials, tools and equipment required for the complete
installation of work called for in the Construction Documents
SCOPE OF WORK
A.
This document describes the products and execution requirements relating to
furnishing and installing Telecommunications Cabling pathways.
Communication cabling support is covered under this document.
B.
This section includes minimum requirements for the following:
1. Non-Continuous Cable Support
2. Underground Pull Boxes
3. Pull Boxes
4. Communications Dust Banks and Conduit
C.
D.
All cables and related terminations, support and grounding hardware shall be
furnished, installed, wired, tested, labeled, and documented by the
telecommunications contractor as detailed in this document.
Product specifications, general design considerations, and installation
guidelines are provided in this document. Quantities of telecommunications
outlets, typical installation details, cable routing and outlet types will be
provided as an attachment to this document. If the bid documents are in
conflict, this specification shall take precedence. The successful vendor shall
Pathways for Communications Systems
27 05 28 - 1
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
meet or exceed all requirements for the cable system described in this
document.
1.4 REGULATORY REFERENCES
A.
The following industry standards are the basis for the structured cabling
system described in this document.
1. TIA/EIA
•
TIA/EIA-568-B
•
TIA/EIA-569-A
Pathways
Commercial Building Telecommunications Cabling
Standard
Commercial Building Standard for Telecom
And Spaces
TIA/EIA-606
Administration Standard for the
Telecommunications
Infrastructure of Commercial Buildings
• TIA/EIA-607
Commercial Building Grounding/Bonding
Requirements
2. NFPA
• NFPA-70
National Electric Code (NEC)-1999
•
3. ISO/IEC
•
ISO/IEC 11801
Generic Cabling for Customer Premises
4. PUBLIC WORKS STANDARDS, INC.
• GREENBOOK; Green Book Standard Specifications for Public Works
Construction 2012.
B.
Federal, state, local codes, rules, regulations, ordinances governing the work,
as well as S.O.C.C.C.D. guidelines and practices may apply and shall be
incorporated as part of these specifications.
C.
In reviewing the various Contract Documents, the Structured
Telecommunications Cable Contractor shall be responsible for noting
conflicts between proposed design/concepts and the applicable standards,
guidelines and practices. A written Request for Information (RFI) shall be
developed by the Structured Telecommunications Cable Contractor and
submitted to S.O.C.C.C.D prior to commencing any work impacted by such
conflicts. Such RFIs shall describe the conflict/violation and, if appropriate,
recommend alternative solutions with associated costs. S.O.C.C.C.D
warrants that they will diligently strive to address such RFIs in order to
minimize negative impact on each SCCS installation completion schedule.
D.
Where the requirements of the Contract Documents are more stringent than
applicable codes, rules, regulations, ordinances, standards, guidelines and
practices, the Contract Documents shall apply. In all other instances, the
most current standards, guidelines and practices shall apply.
Pathways for Communications Systems
27 05 28 - 2
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
1.5 QUALITY ASSURANCE
A.
Structured Communications Cabling System pathways, raceways and
supports shall be installed per the following:
1. Meet all TIA and BICSI commercial building wiring standards.
B.
1.5
All Networks shall be installed per applicable standards and manufacturer's
guidelines.
PATHWAY INSTALLATIONS
A.
Comply with TIA/EIA-569-A, NEC and CEC.
B.
Shall be installed in accordance with NEC Article 314 and Article 800.51 (J),
(K), or (L), as applicable, and installed in accordance with Articles 362.24
through 362.56, where the requirements applicable to electrical nonmetallic
tubing apply.
C.
Conceal interior conduit under floor slabs and within finished walls, ceilings,
and floors where possible.
D.
Keep conduit minimum 6 inches away from parallel runs of electrical power
equipment, flues, steam, and hot water pipes.
E.
Install conduit parallel with or at right angles to ceilings, walls, and structural
members where located above accessible ceilings and where conduit is
visible after completion of project.
F.
Run conduits in crawl spaces and under floor slabs as if cable is exposed.
G.
Install no more than two 90-degree bends for a single horizontal cable run.
H.
Run conduits and surface mounted raceway as determined by site survey or
as noted on drawings.
I.
Provide Pullboxes with “Sealtight” flex conduit only where flexible connections
are required. S.O.C.C.C.D approval required prior to all “Sealtight" flex
conduit installations.
J.
Provide all coring, patching and painting as needed for Intra-Building and
Inter-Building pathways. Caulking is not an acceptable patching method for
conduit penetrations into exterior walls. Coordinate with S.O.C.C.C.D for
acceptable patching methods.
Pathways for Communications Systems
27 05 28 - 3
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
PART 2 - PRODUCTS
2.1
NON-CONTINUOUS CABLE SUPPORT
A.
Material
1. Contractor shall provide and install all non-continuous cable supporting
hardware.
2. Non-continuous cable supporting hardware consists of J-hooks, multifunction clips, beam clamps, etc. Bridle rings are not permitted.
3. Non-continuous cable supports shall provide a load bearing surface of
sufficient width to comply with required bend radii of high-performance
cables; UL Listed. Bridle rings are not permitted.
4. Non-continuous cable supports shall have flared edges to prevent
damage while installing cables.
5. Non-continuous cable supports sized 1 5/16” and larger shall have a
cable retainer strap to provide containment of cables within the hanger.
The cable retainer strap shall be removable and reusable and be suitable
for use in air handling spaces.
6. Non-continuous cable supports shall have an electro-galvanized or G60
finish and shall be rated for indoor use in non-corrosive environments.
7. Multi-tiered non-continuous cable support assemblies shall be used
where separate cabling compartments are required. Assemblies may be
factory assembled or assembled from pre-packaged kits. Assemblies
shall consist of a steel angled hanger bracket holding up to six noncontinuous cable supports, rated for indoor use in non-corrosive
environments; UL Listed.
8. If required, the multi-tier support bracket may be assembled to
manufacturer recommended specialty fasteners including beam clamps,
flange clips, C and Z purlin clips, etc.
9. Tee-bar support bracket with one non-continuous cable support, factory
or jobsite assembled; rated for indoor use in non-corrosive environments;
UL Listed.
10. Fastener to wire/rod with one non-continuous cable support, factory or
jobsite assembled; rated for indoor use in non-corrosive environments;
UL Listed.
11. Fastener to beam or flange with one non-continuous cable support,
factory or jobsite assembled; rated for indoor use in non-corrosive
environments; UL Listed.
Pathways for Communications Systems
27 05 28 - 4
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
12. Fastener to C or Z purlin with one non-continuous cable support, factory
or jobsite assembled; rated for indoor use in non-corrosive environments,
UL Listed.
13. Fastener to wall, concrete, or joist with one non-continuous cable support,
factory or jobsite assembled; rated for indoor use in non-corrosive
environments, UL Listed.
14. Fastener to threaded rod with one non-continuous cable support, factory
or jobsite assembled, rated for indoor use in non-corrosive environments,
UL Listed.
15. The multi-tiered support bracket shall have a static load limit of 300 lbs.
16. U-hooks and double J-hooks shall attach directly to threaded rod using
standard nuts.
B.
2.2
Manufacturer: Panduit, Copper B-Line, or S.O.C.C.C.D approved equal.
UNDERGROUND PULL BOXES AND PULLBOXES
A.
Underground pull boxes shall be made of concrete and the minimum size
shall be 2’-10” x 4’-10” x 4’-0” I.D...
B.
Underground pull covers shall be rated for traffic (type T.05) and shall be
marked communications.
C.
Metal covers shall be used in all location subject to vehicle traffic.
D.
Gravel shall be installed below all ground boxes for drainage.
E.
Ground boxes and pull boxes shall not be placed in areas subject to flooding.
F.
Establish drainage to meet Public Works Construction Standards (Green
Book).
G.
Unless otherwise noted, pull boxes shall have minimum dimensions of 20” x
20” x 6”.
1. Interior pull boxes shall consist of 16 gauge steel minimum, unless
otherwise noted on plans.
2. Indoor enclosures shall conform to NEMA Type 4, unless otherwise
noted.
3. Size pull boxes to not less than minimum Code requirements. Increase
size above Code requirements where necessary to provide space for
Pathways for Communications Systems
27 05 28 - 5
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
pulling, racking or splicing enclosed conductors, or where specified or
indicated dimensions exceed Code requirements.
4. Exterior metal pull boxes exposed to weather (and not installed in or
below grade) shall be equipped with rain-tight or weatherproof-hinged
doors.
5. Exterior pull boxes shall have 16 gauge steel bodies and 14 gauge steel
doors.
6. Exterior pull boxes shall be equipped with external mounting feet.
7. Exterior pull boxes shall be equipped with stainless steel door clamps on
three sides and a removable stainless steel continuous hinge pin.
8. Exterior pull boxes shall be equipped with a hasp and staple for
padlocking
9. Enclosures installed on vertical exterior walls shall conform to NEMA
Type 3R.
10. Enclosures installed on exterior horizontal surfaces such as rooftops or
breezeways shall conform to NEMA Type 4 unless otherwise noted.
11. Rain tight or weatherproof boxes shall use threaded watertight hubs for
top or side entry and may use knockout for bottom entry only.
12. Exterior pull boxes shall conform to these industry standards:
•
UL 508 Type 4
•
NEMA/EEMAC Type 3, Type 4, Type 12, Type 13
•
JIC standard EGP-1-1967
•
CSA Type 4
•
IEC 529, IP66
13. Tamper resistant screws shall be used on all exterior, aboveground
junction/pull boxes that are exposed to public/student areas.
14. Exterior pull boxes shall be manufactured by Hoffman or S.O.C.C.C.D
approved equal.
2.5
COMMUNICATION DUCT-BANKS AND CONDUITS
A.
Trenches
1. All underground trenches shall be minimum 24” wide by 30” deep.
Pathways for Communications Systems
27 05 28 - 6
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
2. Trenches shall be back-filled at 95% compaction.
3. Contractor shall restore surface to same or better condition.
4. Contractor shall contact Dig Alert a minimum of 48 hours prior to
excavation to verify the location of existing underground utilities.
5. Modifications to pathway design may be dictated by field conditions
subject to approval by S.O.C.C.C.D.
6. Compaction testing notification must be provided to the District, 48 hours
prior to testing so that a District inspector may be present.
7. Slurry fill trenches to within three inches (3”) of finished grade whenever
crossing paved areas. “Two Sack” slurry shall be used.
8. Pavement removal and patching shall conform to specifications and
standards listed in the Public Works Standards (Green Book 2006).
B.
Conduit
1. Underground conduit shall consist of Schedule 40 PVC - 2 inch or 4”
inside diameter or type C telephone conduit - 2 inch inside diameter (if
concrete encased)
2. Conduit shall have a factory formed bell on one end for interconnecting
segments.
3. Conduit located under heavy use highways or railroad rights-of-ways shall
be encased in steel casing consistent with the AASHTO or AREA
specifications. The thickness of the steel casing shall be engineered for
each specific application. This may vary based on campus codes.
4. Spacers: High impact spacers shall be used in all multi-duct systems, for
either solely owned or joint telecommunications/power construction. They
shall conform to NEMA TC-2, TC-6, TC-8, and ASTM F 512 dimensions.
5. All fittings shall be designed specifically for use with the type of conduit
placed.
6. All conduits shall be equipped with seal plugs in all ground boxes and
expansion rubber seal plugs within all buildings.
7. A horizontal and vertical separation of 1 inch shall between the ducts be
maintained by installing high impact spacers with horizontal and vertical
locking intervals of ten feet.
8. All communications conduits shall be placed in a uniform manner
between ground boxes and pull boxes. Conduit in position #1 at one
ground box or pull box shall maintain its position within the duct run and
terminate in the #1 position at the next box. The position of all conduits
between ground boxes and pull boxes shall be maintained.
Pathways for Communications Systems
27 05 28 - 7
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
9. Long radius bends (over 30 feet) shall be used whenever possible to
make changes in direction. If it is found to be necessary to place a 90degree bend in the conduit run, a factory-made sweep of no less than 60inch radius shall be used.
10. No conduit run shall exceed a total of 180 degrees of bend between any
two points (such as manholes or buildings) considering both vertical and
horizontal sweeps.
11. Cold-formed trench bends shall have a radius of not less than 60 inches
and shall pass mandrel integrity. Bend radius criterion is 2" or less 6
times the diameter of the conduit and any conduit larger than 2" is 10
times the diameter of the conduit.
12. The length and destination of all conduits shall be identified in each
ground box, pull box and building. Embossed metal or heavy plastic tags
strapped to each conduit shall be used.
13. After installation of communications conduits, the contractor shall prove
all conduits by pulling a mandrel with a diameter ¼ inch smaller than the
conduit and 6 inches long through each conduit end-to-end. An inspector
designated by the contractor and S.O.C.C.C.D shall be notified 24 hours
before this procedure. Each conduit shall be cleaned with a bristle brush
to remove any debris.
14. Utility marking tape shall be buried 12 inches below the surface directly
above the conduit.
15. Where communications and power conduits occupy the same trench, all
conduit structures shall be built with the telecommunications conduits
placed above the power conduits and separated by a minimum of 12” of
compact earth or 3” of concrete encasement, unless otherwise called out
on the construction drawings and approved by S.O.C.C.C.D. If this type
of construction is required, it shall receive the prior approval of the
contractor and S.O.C.C.C.D.
16. Contractor shall install new ¼” pull rope in all conduits placed.
C.
Overhead Conduit
1. Where overhead conduit is required within buildings, Contractor shall
utilize EMT conduit with an inside diameter of 2” or 4”, unless otherwise
specified.
2. All fittings shall be compression type connectors and couplers designed
specifically for use with the type of conduit placed.
3. All fittings shall be watertight. Fitting types shall be pre-approved by the
designated District representative. Unless pre-approved by the
designated District representative, all conduits shall be installed by a
qualified electrical contractor who has at least five years experience in
similar installations within the Southern California area.
Pathways for Communications Systems
27 05 28 - 8
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
4. Contractor shall install conduit at roof locations utilizing the current District
approved methodology and process. All conduit pathways and locations
must be approved by S.O.C.C.C.D prior to installation.
5. All roof penetrations must be approved by S.O.C.C.C.D prior to
installation.
6. Contractor shall install new ¼” pull rope in all conduits placed.
D.
Communications Entrance Conduit
1. To prevent shear, all inter-building conduit (either underground or aerial)
shall transition from PVC or metal to Sealtite flex conduit when attaching
to a permanent structure. The contractor and S.O.C.C.C.D shall
determine the placement of all entrance conduits. All applicable
standards shall be adhered to, i.e., S.O.C.C.C.D, NEC, BICSI or G.O.
128.
2. Contractor shall install new ¼” pull rope in all conduits placed.
E.
Vertical Conduit
1. Where vertical conduit is required between pull boxes or within buildings,
Contractor shall utilize EMT conduit with an inside diameter of 2” or 4”
unless otherwise specified.
F.
Duct-bank locating cable (electronically detectable warning tape)
1. Warning tape shall be a minimum of 3" wide, orange in color, and shall
have a nondegradable imprint as follows:
G.
•
“Caution fiber optic cable buried below”
•
The tape shall be electronically detectable.
Pull Rope
1. Pull rope shall be new ¼" polypropylene over polyester rope with a
minimum 1700 lb. Tensile strength.
2. Pull rope shall be new material that is free of knots, kinks, and abrasions
and shall be placed as a single continuous length in every new conduit.
3. Pull rope shall be secured at each end.
2.7
FIRESTOPPING MATERIAL
A.
Contractor shall provide all necessary fire stopping of openings through which
cable is installed under this specification, in accordance with NFPA 70 and all
local codes. This includes installation in conduits, raceways, or bare
Pathways for Communications Systems
27 05 28 - 9
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
penetrations. Provide and install UL 1479 approved firestop systems
2.8
DUCT SEALANT
A.
Contractor shall provide Polywater® Duct Sealant kit #FST-kit to seal each
end of all underground communications duct bank conduits.
B.
Duct sealant shall be a two-part, “water-blown” urethane foam that cures to a
strong, rigid closed-cell structure.
C.
Duct sealant shall be capable of wetting and adhesion to metal, concrete and
plastic surfaces.
D.
Duct sealant shall be 100% water tight, holding 15-foot (5 meters) waterhead,
and acts as a barrier to smoke and air.
PART 3 - EXECUTION
3.1
OPEN CABLE INSTALLATION
A.
Use only where specifically indicated on plans or determined during site
surveys.
B.
C.
When not run in surface mounted raceway or conduit, utilize non-continuous
cable support above suspended ceilings and in all ceiling spaces.
Install cabling above suspended ceilings 6 to 12 inches above ceiling T-bar
using non-continuous cable support spaced on 24 to 48 inch centers and
securely attached to structural ceiling.
D.
Do not exceed cable pull tensions recommended by the manufacturer.
1. Avoid routing copper cable in areas where there may be high levels of
electromagnetic interference (EMI). EMI is caused by AC power lines,
broadcast signals, X-ray equipment, motors, generators, and fluorescent
lights. UTP cables shall be routed at least 5 inches away from
fluorescent lighting fixtures.
2. Cables shall be placed in the non-continuous cable support located every
2 to 4 feet, as long as they are separately bundled and tie-wrapped using
Velcro ties.
3. Cabling shall be organized and identified so as to facilitate locating and
handling individual sheaths for maintenance functions.
4. Each bundle shall be neatly tied without over cinching or stressing cable.
Pathways for Communications Systems
27 05 28 - 10
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
5. Bundles shall be clearly marked identifying the IDF and room to which
routed, the station numbers served by the bundle, and any other
information that may assist in administration.
6. Great care shall be taken to protect all cabling from physical damage.
7. A 20’ service loop shall be installed above ceiling on each cable
installation where possible.
3.2
FIRESTOP
A.
A firestop system is comprised of the item or items penetrating the fire rated
structure, the opening in the structure and the materials and assembly of the
materials used to seal the penetrated structure. Firestop systems comprise
an effective block for fire, smoke, heat, vapor and pressurized water stream.
B.
All penetrations through fire-rated building structures (walls and floors) shall
be sealed with an appropriate firestop system. This requirement applies to
through penetrations (complete penetration) and membrane penetrations
(through one side of a hollow fire rated structure). Any penetrating item (i.e.,
riser slots and sleeves, cables, conduit, cable tray, and raceways, etc.) shall
be properly fire stopped.
All firestop systems shall be installed in accordance with the manufacturer’s
recommendations and shall be completely installed and available for
inspection by the local inspection authorities prior to cable system
acceptance.
C.
3.3
DUCT SEALANT
A.
Contractor shall install duct sealant in each end of underground duct bank
conduits.
B.
All occupied and vacant communications duct bank conduits shall be sealed.
C.
Each underground duct bank conduit entering underground pull boxes shall
have duct sealant installed.
D.
Each underground duct bank conduit stubbing up through building foundation
shall have duct sealant installed.
E.
Each underground duct bank conduit through building wall shall have duct
sealant installed.
F.
Each underground duct bank conduit end shall be sealed to be 100% water
tight.
END OF SECTION 27 05 28
Pathways for Communications Systems
27 05 28 - 11
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
SECTION 27 11 00
COMMUNICATIONS EQUIPMENT ROOM FITTINGS
PART 1 – GENERAL
1.1
SUBMITTALS
A.
Refer to Division 01 33 00 for submittal procedures.
B.
Provide submittals for materials required by this section.
C.
Submittals shall consist of catalogue cut sheets and/or engineering specification sheets
provided by the manufacturer.
D.
Contractor shall submit for approval all proposed materials and equipment prior to
installation.
1.2
SECTION INCLUDES
A.
Installation of Equipment Racks, Brackets
B.
Installation of Cable Management – Vertical and Horizontal
C.
Installation of Overhead Cable Runway (Ladder racking)
D.
Installation of Cable Tray
1.3
RELATED DOCUMENTS
A.
Drawings and general provisions of the Contract, including General
Supplementary Conditions and all Specification Sections, apply to this section.
B.
SECTION 27 05 26 - GROUNDING AND BONDING FOR COMMUNICATIONS
SYSTEMS
C.
SECTION 27 05 28 – PATHWAYS FOR COMMUNICATIONS SYSTEMS
D.
SECTION 27 13 13 - COMMUNICATION COPPER BACKBONE CABLING
E.
SECTION 27 13 23 - COMMUNICATIONS OPTICAL FIBER BACKBONE CABLING.
1.4
A.
and
REFERENCES
American Society for Testing and Materials (ASTM):
1. A 123 - Standard Specification for Zinc (Hot-Galvanized) Coatings on Products
Fabricated From Rolled, Pressed, and Forged Steel Shapes, Plates, Bars and Strips.
2. A 569 - Standard Specification for Steel, Carbon (0.15 Maximum, Percent), HotRolled Sheet and Strip Commercial Quality.
Communications Equipment Room Fittings
27 11 00 - 1
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
3. A 570 - Standard Specification for Steel, Sheet and Strip, Carbon, Hot-Rolled,
Structural Quality.
4. A 653/A 653M - Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or
Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process.
5. B 209 - Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate.
6. B 209M - Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate
(Metric).
7. B 221 - Standard Specification for Aluminum and Aluminum-Alloy Extruded Bars,
Rods, Wire, Shapes, and Tubes.
8. A 240 - Standard Specification for Heat-Resisting Chromium and Chromium-Nickel
Stainless Steel Plate, Sheet and Strip for Pressure Vessels.
9. B 766 - Specification for Electrodeposited Coatings of Cadmium.
B.
National Fire Protection Association (NFPA) 70 - National Electrical Code.
C.
National Electrical Manufacturers Association (NEMA):
1. VE 1 - Metallic Cable Tray Systems.
2. VE 2 – Metallic Cable Tray Installation Guidelines.
D.
1.3
National Uniform Seismic Installation Guidelines (NUSIG).
SYSTEM REQUIREMENTS
A.
General: Coordinate the features of materials and equipment so they form an integrated
system. Match components and interconnections for optimum future performance.
B.
Expansion Capability: Unless otherwise indicated, provide spare conductor pairs in
backbone cables, and provide spare positions in cross-connects, patch panels and
terminal strips to accommodate 20 percent future increase in active workstations.
1.4
MOUNTING ELEMENTS
A.
Pathways: Comply with Section 27 05 28 – PATHWAYS FOR COMMUNICATIONS
SYSTEMS.
B.
Backboards: 0.75-inch, interior-grade, fire-retardant-treated plywood.
C.
Where appropriate, racks shall be secured to the concrete floor and/or plywood
backboard using minimum 0.125-inch hardware or as required by local codes.
D.
Stand alone equipment racks shall be placed with a minimum of 36 inches clearance
between front and back of racks and walls.
Communications Equipment Room Fittings
27 11 00 - 2
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
E.
All racks and cable runways shall be grounded to the telecommunications ground bus
bar in accordance with Section 27 05 26 - GROUNDING AND BONDING FOR
COMMUNICATIONS SYSTEMS.
F.
Rack mount screws not used for installing patch panels and other hardware shall be
bagged and left with the rack upon completion of the installation.
G.
General Contractor provided plywood shall be mounted vertically 6 inches above the
finished floor.
H.
Wall mounted termination blocks field shall be installed with the lowest edge of the
mounting frame a minimum 18 inches above the finished floor.
PART 2 - PRODUCTS
2.1
2-POST DISTRIBUTION RACKS
A.
Freestanding modular aluminum units designed for telecommunications terminal support
and coordinated with dimensions of units to be supported.
B.
MATERIAL:
1.
Approximate Module Dimensions: 84 inches high by 19 inches wide by 6 inches
channel depth.
2.
Racks shall be all high strength, lightweight 6061-T6 aluminum extrusion
construction.
3.
Racks shall be equipped with two top angles or top bars and heavy-duty assembly
hardware.
4.
Racks shall have ANSI/TIA hole pattern on front and rear.
5.
Racks shall assemble as 19 inches with no additional hardware required to
assemble.
6.
Racks shall have ANSI/TIA Channel: 6 inches x 1.265 inch x 0.25 inch thick flange.
7.
Racks shall have Base Angles: 3.5 inches by 6 inches by 0.125 inch thick (pair).
8.
Racks shall have Top Angles: 1.5 inch by 1.5 inch by 0.25 inch (pair).
9.
Racks shall have Top Bars: 1.5 inch by 0.25 inch (pair).
10.
Racks shall have a weight capacity of 1000 lbs. Weight must be evenly distributed.
11.
Racks shall be black over a brushed aluminum finish.
12.
Racks shall provide floor and ceiling access for cable management and
distribution.
Communications Equipment Room Fittings
27 11 00 - 3
R2A Architecture
Costa Mesa, CA
09/28/2015
C.
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
13.
Racks shall provide pre-drilled base for floor attachment of rack.
14.
Racks shall be seismic/earthquake braced.
15.
Racks shall be black in color.
MANUFACTURERS:
1.
Chatsworth Products #66353-703 (Equipment Rack)
2.
Or ACC Approved Equal
Communications Equipment Room Fittings
27 11 00 - 4
R2A Architecture
Costa Mesa, CA
09/28/2015
2.2
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
EQUIPMENT RACKS (WALL-MOUNTED)
A.
Standard Swing Gate Wall Rack units designed for telecommunications terminal support
and coordinated with dimensions of units to be supported.
B.
Material:
Approximate Module Dimensions: 36 inches high by 19 inches wide by 25 inches depth.
C.
2.3
1.
Racks shall have EIA hole pattern on front.
2.
Racks shall assemble as 19 inches with no additional hardware.
3.
Racks shall have a load rating of 150 lbs. Weight must be evenly distributed.
4.
Racks shall be black over a brushed aluminum finish.
5.
Racks shall provide floor and ceiling access for cable management and
distribution.
6.
Racks shall provide pre-drilled base for wall attachment of rack.
7.
Racks shall be seismic/earthquake braced.
8.
Racks shall be black in color.
9.
Opens to right or left, stopping in 90° position
10.
Racks shall be EIA-310-E compliant
11.
Racks shall have universal 5/8”-5/8”-1/2” alternating hole pattern.
12.
Racks shall contain (50) each #12-24 mounting screws.
13.
Support 150 lbs of equipment in the open and closed position when securely
mounted.
14.
Supports single-sided and double-side shelves.
15.
Include all installation hardware.
Rack Manufacturer:
1.
Cooper B-Line Part Number SB708197925.
2.
Or S.O.C.C.C.D. Approved Equal
CABLE RUNWAY (LADDER RACKING)
Communications Equipment Room Fittings
27 11 00 - 5
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
A.
Cable support ladder racks shall be installed in the Telecommunication Rooms as shown
on the drawings. Size: 18 inches wide, plus side channel, as needed.
B.
Classified by Underwriters Laboratories (UL) as suitable for equipment grounding.
C.
Ladder rack shall be used for voice, data and video communications cabling only. No
electrical wiring shall be placed on ladder rack with voice and data cabling.
D.
Wall angle supports shall be steel angles. Ends to be smooth without hooks or
projections. Brackets shall be able to support an end load of 600 lb. with a safety factor
of 1.65.
E.
Elbows, Tees, 90 degree bends and crosses: All horizontal and vertical 90 degree
elbows, tees, 90 degree bends and crosses, shall be made with right angle couplings
which clamps to the runway without the need for drilling or cutting.
F.
At all horizontal 90-degree bends, tees, and crosses, provide adjustable junction splice
kits for large radius cable bends.
G.
Seismically supported by end wall supports, angular wall supports and communications
equipment racks.
H.
Black baked enamel finish.
I.
Contractor shall provide cable runway elevation kit for each installed rack.
J.
Contractor shall provide cable runway end caps to protect edges.
K.
Contractor shall install Cable Runway Radius Drops above each vertical wire manager
installed.
L.
MANUFACTURERS:
1.
Chatsworth Products #10250-718 (18”)
2.
Chatsworth Products #10506-706 (Runway Elevation Kit)
3.
Chatsworth Products #12100-718 (Radius Drop, Cross Member)
4.
Chatsworth Products #10642-001 (End Caps)
5.
Chatsworth Products #10608-701 (Vertical wall bracket)
6.
Chatsworth Products #11301-701 (Butt-Splice Kit)
7.
Chatsworth Products #11302-701 (Junction-Splice Kit)
8.
Chatsworth Products #11421-718 (Wall angle support Kit)
9.
Or S.O.C.C.C.D. Approved Equal
Communications Equipment Room Fittings
27 11 00 - 6
R2A Architecture
Costa Mesa, CA
09/28/2015
2.4
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
WIRE MANAGEMENT
A.
Materials: All equipment racks shall be equipped with vertical and horizontal wire
management organizers. All horizontal wire managers shall be heavy duty painted black
metal units designed specifically to connect to equipment frames. All vertical wire
managers shall be aluminum with a black finish. All wire managers shall be secured to
the frames and shall provide a clear and unobstructed pathway in which to route the
cables.
B.
VERTICAL WIRE MANAGERS:
C.
1.
Single-sided vertical cable managers shall be constructed of metal backbone with
pass through holes and plastic cable management fingers.
2.
The cable management fingers shall be molded out of plastic and incorporate bend
radius control throughout the entire length.
3.
The panel shall have a metal door that will be capable of opening to the left or right
when mounted.
4.
The panel shall be capable of mounting to ANSI/TIA standard channel, deep
channel and Telco style racks.
5.
Vertical wire managers shall be 6 inches wide by 7 feet tall. Vertical wire managers
shall have evenly spaced 1 RMU wire rings designed to maintain jumper, patch, or
cross-connect wire in place.
6.
Vertical wire managers shall be designed to extend past the frame to allow
placement of equipment in any position within the rack. When mounted between
equipment frames, they shall be designed to direct cables into either frame and
shall be securely mounted to both units.
7.
Wide cable rings, purchased separately, shall be installed at the rear of the vertical
manager.
8.
Vertical wire managers shall be black in color.
HORIZONTAL WIRE MANAGERS:
1.
The in-frame horizontal managers shall be 2 and 3 RMU in height and shall extend
from side rail to side rail.
2.
Single-sided design and pass-through slots for easy organization of front and rear
cables.
3.
Include cable guide fingers at 1.75” intervals for proper cable bend radius and
organization of patch cords.
4.
Flanged pass-through slots to route cables from front to back.
Communications Equipment Room Fittings
27 11 00 - 7
R2A Architecture
Costa Mesa, CA
09/28/2015
D.
2.5
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
5.
Include Snap-on, hinged door/cover.
6.
Horizontal wire managers shall be black in color.
MANUFACTURERS:
1.
Chatsworth Products: 12831-703 (Vertical)
2.
Chatsworth Products: 3013x-719 (Horizontal)
3.
Or S.O.C.C.C.D. Approved Equal
PLYWOOD BACKBOARD
A.
General Contractor shall provide .75-inch thick high A/C grade void-free, fire rated
plywood, on all TR and MDF walls as noted on construction drawings.
B.
Backboards shall be mounted vertically, starting 6 inches above the finished floor, and
secured to the walls.
C.
All backboards are to be constructed of 4 feet by 8 feet plywood.
D.
All plywood panels must be mounted vertically in contact with one another, leaving no
gaps between sheets.
E.
All exposed edges must be chamfered. Screws, bolts, washers and/or nuts are to be
counter sunk to be flush with the surface of the plywood.
2.6
A.
CABLE TRAY
GENERAL
1. Provide cable tray of types and sizes indicated; with connector assemblies, clamp
assemblies, connector plates, splice plates and splice bars. Construct units with
rounded edges and smooth surfaces; in compliance with applicable standards; and
with the following additional construction features.
B.
MATERIALS AND FINISHES
1. Materials: All cable tray sections, fittings and accessories shall be made from
corrosion resistant metal or metal with a factory applied corrosion resistant finish. All
materials shall be as indicated on drawings and in accordance with NEMA Standard
VE1 Sections 4.1 and 4.:
a. Construction: Fabricated of two side rails and bottom.
b. Duty: Medium.
c. Steel Sheet: ASTM A 569.
Communications Equipment Room Fittings
27 11 00 - 8
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
d. Bottom: Sheet perforated for ventilation, minimum 60 percent solid plane for
support.
e. Finish: ASTM A 653/A 653M, hot dip shop galvanized before fabrication.
f.
Minimum Inside Depth: 4 inches
g. Minimum Inside Width: 12 inches
h. Minimum Section Lengths: 12 feet
2. Fittings: Manufacturer's standard splice plates, elbows, risers, tees, crosses, Y,
reducer plates, blind ends, barrier strips, radiused drop-outs, divider strips with
resilient PVC cap strip; ventilated. Each item plated or coated same as cable tray.
3. Attachment Accessories: Manufacturer's standard bolt and nut fasteners, clamps, Jbolts, hangers, and connectors. Each item electro-zinc plated or coated same as
cable tray.
4. Grounding Straps: 600 ampere rated, insulated 2 AWG copper cable with tin-plated
terminals ends.
5. Warning Signs: Manufacturer’s standard self-adhering label, black letters on white
background, identified with following:
a. "WARNING: NOT TO BE USED AS WALKWAY.”
b. Manufacturer name and address.
c. UL Classification.
d. Minimum area, catalog number with code descriptions, and customer order
number.
6. Cable Tray (Rung Bottom):
a. Length of Straight Sections: Actual lengths and quantities shall be as indicated
on drawings. Standard manufacturer lengths shall be 12 ft or 24 ft not including
connectors if attached. Straight section lengths shall be greater than or equal to
the support span length. Straight section lengths shall be used such that a
maximum of one splice joint is between any two-tray supports.
b. Widths: Actual widths shall be as indicated on drawings. Standard manufacturer
widths shall be in accordance with NEMA Standard VE1 Section 4.3.3.1 and
shall be 12 inches.
c. Side Rail Height: Actual tray side rail height shall be 4 inches. Standard
manufacturer heights shall be in accordance with NEMA Standard VE1 Section
4.3.4.3 and shall be 4 inches.
d. Traverse Elements: The maximum open spacing between traverse elements
shall be 4 inches measured in the direction parallel to the side rails.
Communications Equipment Room Fittings
27 11 00 - 9
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
e. Rung Spacing: Standard manufacturer rung spacing on straight sections shall be
4-inch wide channels on 8-inch centers for aluminum trays. Rung spacing on
fittings shall be 1-inch wide on 5-inch centers for steel trays. Rungs shall be
attached to side rails by welding.
f.
Bottoms: Standard manufacturer bottoms shall include solid corrugated bottoms
welded to the side rails. Corrugated bottom shall be 0.5" high with 0.875" top rib
spaced 2.185" on center along tray length.
g. Tray Fittings: Tray fittings types and quantities shall be as indicated on the
drawings. All tray fittings shall be constructed of same material as straight tray
sections. Manufacturer tray fittings shall include the following minimum standard
fittings types:
h. Horizontal elbow fittings in 30, 45, 60, and 90-degree angles.
•
Vertical elbow fittings in 30, 45, 60 and 90-degree angles with inside and outside radius options.
•
Horizontal adjustable elbow fittings with adjustable angle.
•
Horizontal and vertical tee fittings, branch at 90-degree angle.
•
Horizontal wye fittings, branch at 45-degree angle.
•
Horizontal and vertical cross fittings, branch at 90-degree angles.
1. Fitting Radius: The nominal bend radius of all fittings shall be 12 inches as measured
on the smallest side as indicated on the drawings and shall be appropriate for the
allowable bending radius of the cables to be installed in the fitting. Standard
manufacturers fitting radii in accordance with Working (Allowable) Load Capacity:
2. Working (Allowable) Load Capacity: Working load capacity shall be in accordance
with NEMA Standard VE1 Sections 4.8, 5.2, and Table 1. NEMA Load/Class
designation per Table 1 shall be Class 20A. Tray deflection shall not exceed
manufacturers published engineering data for project cable tray working load
capacity and minimum support span requirements.
3. Safety Factor: Minimum load capacity safety factor shall be 1.5 in accordance with
NEMA Standard VE1 Section 5.2.8.
4. Aluminum (ALUM.): Cable tray straight section side rails shall be constructed from
copper free alloy type 6063-T6. All fittings and accessories shall be constructed from
corrosion resistant aluminum alloy that is compatible with alloy 6063 such as type
5052 or type 3003.
5. Connectors: Connector splice shall have less than 0.00033 ohms electrical
resistance. Expansion connectors shall provide for minimum 1" tray expansion and
shall be placed as shown on drawings or as required to prevent damage to the tray
system from thermal expansion and contraction. Grounding bonding jumpers shall be
installed at all adjustable connectors and expansion connectors.
Communications Equipment Room Fittings
27 11 00 - 10
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
6. Connector Hardware: 3/8" diameter, truss head, ribbed neck steel screw with phillips
recess and a free spinning, lock type steel nut which does not need a washer.
Connector hardware finish shall be protected against corrosion. Connector hardware
finish shall be cadmium plated with yellow iridite finish.
7. Grounding: Provide continuous ground from cable tray to building ground in
accordance with Grounding section of specifications. The cable tray system shall be
capable of being is used as equipment grounding conductor in accordance with the
National Electric Code (NEC) Article 318-7(b). Cable tray sections and fittings shall
be marked to show the minimum cross sectional area in accordance with the
National Electric Code (NEC) Article 318-7. Bonding jumpers shall be constructed of
laminated aluminum or insulated copper wire with a minimum of 200 rated amperes
or in accordance with NEC 250-95.
8. Accessories:
a. Covers: Tray covers shall be provided as indicated on drawings. Covers for fittings shall be available in same configuration as covers for straight tray. Covers
for tray shall be supplied of the same material as straight tray and fittings or as
indicated on drawings. Manufacturers standard tray covers shall include flat covers with side flanges. Provide standard manufacturer's hardware as required to
hold covers to cable tray sections. "Clip Type" clamps may be used on indoor,
horizontal cable trays. Heavy duty "Strap Type" clamps shall be used on all vertical cable tray sections.
b. Blind End Plates: Blind end plates shall be provided as indicated on drawings.
Blind end plates shall be supplied of the same material as straight tray and fittings.
c. Cable Dropouts: Cable dropouts shall be provided as indicated on drawings. Cable dropouts shall be supplied of the same material as straight tray and fittings.
d. Wall Penetration Sleeves: Provide wall penetration sleeves for all wall penetrations where indicated on drawings. Wall penetration sleeves shall be fabricated
from steel, hot dipped galvanized after fabrication material per ASTM A-123. The
penetration sleeve shall be designed for a single run of cable tray in standard
overall tray widths and overall tray depths. In fire rated locations, install Nelson
PLW firestop pillows in sufficient quantities to meet maximum 2 hour wall fire rating.
e. Conduit and Pipe Clamps: Provide standard manufacturer designed conduit and
pipe clamps and/or brackets as required by code to clamp conduit and pipe.
C.
SUPPORT COMPONENTS
1. Product: Support Components must be provided from the same manufacturer as
Cable Tray.
2. Hanger Channels:
a. Configuration: Regular channel type.
Communications Equipment Room Fittings
27 11 00 - 11
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
b. Material: Plain steel, ASTM A 570, Grade 33.
c. Finish: G90 galvanized.
3. Accessories: Brackets, anti-sway devices, seismic bracing, attachments, and others
to suit project conditions. Each item plated or coated same as cable tray.
PART 3 - EXECUTION
3.1
EQUIPMENT RACKS
A.
Coordinate all work for final mounting locations of all equipment.
B.
Provide and install all cable runways as defined in the Telecommunications Drawings
and Specifications.
C.
Provide and install all equipment racks as indicated on the Telecommunication
Drawings.
D.
Provide and install all vertical and horizontal wire managers as indicated on the
Telecommunication Drawings.
E.
Provide and install all grounding as identified within Telecommunications Drawings and
Specifications.
F.
Provide and install dedicated #6 AWG grounding conductors from each rack to the
TGB/TMGB in each Telecommunications Room. “Daisy Chaining” of conductors
between equipment racks is not acceptable.
3.2
CABLE MANAGEMENT
A.
Provide and install 6” single-sided vertical wire management panels to each 19” x 7’
equipment rack installed.
B.
Within the stand alone equipment racks, provide and install horizontal wire management
panels for each rack as indicated on the Telecommunication Drawings.
3.3
CABLE RUNWAY (LADDER RACKING)
A.
Provide and install all ladder racking as defined within the Telecommunications
Drawings.
B.
Provide and install runway elevation kits.
C.
Provide and install runway radius drops at each vertical wire manager location.
D.
Provide and install #6 AWG grounding conductor from ladder racking system to
TGB/TMGB.
E.
Provide #6 AWG bonding conductors between all ladder racking junction points.
Communications Equipment Room Fittings
27 11 00 - 12
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
F.
Provide and install protective end caps.
G.
Provide and install all required mounting/supporting hardware required.
3.4
VELCRO TIE WRAPS
A.
Provide and install Velcro tie wraps to manage and secure all installed cables.
B.
Where place on ladder racking, all cables shall be neatly bundled and routed to
designated location.
C.
Installation of plastic ties is not acceptable.
3.5
CABLE TRAY
A.
Install cable tray in accordance with NEMA VE 2, manufacturer’s instructions, and DSA
requirements.
B.
Support trays in accordance with NUSIG requirements for seismic stabilization and to
meet Zone 4 and DSA seismic bracing standards.
C.
Cable trays will not be placed within 5 inches of any overhead light fixture and within 12
inches of any electrical ballast. A minimum of 8 inches above the cable tray must be
maintained at all times. All bends and T-joints in the cable trays must be fully accessible
from above. Provide sufficient space encompassing cable runways to permit access for
installing and maintaining cables.
D.
Cable trays shall not extend more than 2 feet over a fixed ceiling area.
E.
Provide supports at each connection point, at the end of each run, and at other points to
maintain spacing between supports of 8 feet maximum.
F.
Use expansion connectors where required; install per NEMA VE1 and VE2.
G.
Provide firestopping to requirements to sustain ratings when passing cable tray through
fire rated construction.
H.
Cable tray shall start and end at each fire rated wall. Four- inch EMT conduit shall be
installed through each fire rated wall penetration.
I.
A U.L. listed firestop system shall be used on the outside and inside perimeters of the
four-inch EMT conduit that makes up the fire rated wall penetration.
J.
Ground and bond cable tray to requirements of Section 27 05 26 Telecommunications
Grounding and Bonding.
K.
Provide continuity between tray components.
L.
Use antioxidant compound to prepare and coat aluminum contact surfaces before
assembly.
Communications Equipment Room Fittings
27 11 00 - 13
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
M.
Provide equipment-grounding conductor through entire length of tray; bond to each
component.
N.
Connections to tray may be made using mechanical or exothermic connectors.
O.
Install warning signs at 24-foot centers along cable tray; locate in location that is visible
after surrounding components are installed or placed.
END OF SECTION 27 11 00
Communications Equipment Room Fittings
27 11 00 - 14
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
SECTION 27 13 13
COMMUNICATIONS COPPER BACKBONE CABLING
PART 1 - GENERAL
1.1
WORK INCLUDED
A.
Provide all labor, materials, tools, and equipment required for the complete installation of
work as called for in the Contract Documents
1.2
A.
B.
SCOPE
This section includes the copper cable installation and splicing requirements for interbuilding backbone cabling. Also included in this section will be the installation of cable
racking hardware and racking of cable in designated manholes and pullboxes.
1.
Communications contractor shall coordinate specific pair counts to be transferred
from existing 600-pair cable to new 50-pair cable.
2.
Communications contractor shall install new 50-pair OSP rated cable in existing
conduit, alongside existing 600-pair.
3.
Communications contractor shall provide and install all work required in MH 11 and
HH 27. Work includes splice cases, splice case end pieces, splice modules,
bonding, grounding, labeling and duct seal.
4.
Campus IT shall rearrange telephone circuit cross-connects to re-assign existing
telephone circuits into sequential 50-pair count within existing 600-pair cable.
5.
Communications contractor splicing and cable pair transfer work shall take place in
MH 11 and HH 27.
6.
Communications contractor shall demo existing 600-pair cable between MH 11 and
HH 28 to make room for new tube cell ducts for air blown fiber. This work shall take
place after normal business hours.
7.
Communications contractor shall confirm with campus IT, that all telephone circuits
are working prior to closing up splice cases.
This section includes minimum requirements for the following:
1.
Inter-building Backbone Cabling (Outside Plant)
a)
Twisted multi-pair OSP-rated (type PE-39/CM) copper cable (voice).
b)
Splice case
c)
Splice modules
Communications Copper Backbone Cabling
27 13 13 - 1
R2A Architecture
Costa Mesa, CA
09/28/2015
1.2
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
SUBMITTALS
A.
Provide submittals for materials required by this section.
B.
Submittals shall consist of catalogue cut sheets and/or engineering specification sheets
provided by the manufacturer.
C.
Contractor shall submit for approval all proposed materials and equipment prior to
installation.
1.2
RELATED DOCUMENTS
A.
Section 27 05 26 - GROUNDING AND BONDING FOR COMMUNICATIONS
SYSTEMS
B.
SECTION 27 05 28 - PATHWAYS FOR COMMUNICATIONS SYSTEMS.
B.
SECTION 27 11 00 - COMMUNICATIONS EQUIPMENT ROOM FITTINGS.
C.
SECTION 27 13 23 - COMMUNICATIONS OPTICAL FIBER BACKBONE CABLING.
1.3
A.
SECTION INCLUDES
Copper UTP Backbone Cables
PART 2 – PRODUCTS
2.1
COPPER BACKBONE CABLE
A.
Application: Use for voice backbone connectivity between the MDF and each IDF.
B.
Materials –24-gauge, twisted pair, solid conductor, black polyethylene sheath, shielded
of corrugated aluminum. Pair counts as indicated on the drawings.
C.
Shall be 300-pair
D.
Manufacturer – General Cable, Superior Essex (SEALPIC-F, Type REA PE39) or
equal.
2.2
A.
2.3
MISCELLANEOUS COPPER BACKBONE TERMINATION CONSUMABLES
Provide all miscellaneous consumables necessary to support, and terminate copper
backbone cable.
OSP COPPER SPLICE CASE AND SPLICE MODULES
Communications Copper Backbone Cabling
27 13 13 - 2
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
A.
Materials – OSP rated multiple entries, straight in-line type with 900 pair capacity.
Complete with appropriately sized and fitted endplates, 710-type connecting modules
and grounding hardware. Installed in manhole and handhole locations.
B.
Manufacturer – Superior Modular Products (Preformed Line Products)
2.4
MANHOLE RACKING HARDWARE
A.
Materials – Hot dipped galvanized steel cable racks equipped with 24 support holes.
Installed in designated manhole locations.
B.
Manufacturer – Inwesco Incorporated (P/N 10A12)
C.
Materials – Hot dipped, galvanized steel cable rack hooks. To be installed in designated manhole locations.
D.
Manufacturer – Inwesco Incorporated (P/N 10A36 or 10A37)
PART 3 – EXECUTION
3.1
A.
3.2
OSP-RATED CABLING
Backbone cabling shall be rated to meet building combustible and non-combustible
requirements as well as local building codes.
BACKBONE CABLE INSTALLATION
A.
Backbone cables shall be installed in existing conduits.
B.
A nylon pull cord, 0.125 inch (3.175 mm) minimum shall be co-installed with all cable
installed in any conduit.
C.
Where cables are housed in conduits, the backbone and horizontal cables shall be
installed in separate conduits.
D.
All backbone cables shall be securely fastened to the sidewall and near room corners.
E.
Vertical runs of cable shall be supported with D-rings, J Hooks, cable tray, or other
method to provide proper support for the weight of the cable.
F.
Large bundles of cables and/or heavy cables shall be attached using metal clamps
and/or metal banding to provide proper support for the weight of the cables.
G.
Contractor shall install mounting/racking hardware within vaults and hand holes as
required. All cable shall be neatly dressed and secured in Maintenance and Hand
holes.
3.3
BACKBONE CABLE SPLICING
Communications Copper Backbone Cabling
27 13 13 - 3
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
A.
Communications contractor shall coordinate specific pair counts to be transferred from
existing 600-pair cable to new 50-pair cable.
B.
Communications contractor shall install new 50-pair OSP rated cable in existing
conduit, alongside existing 600-pair.
C.
Communications contractor shall provide and install all work required in MH 11 and HH
27. Work includes splice cases, splice case end pieces, splice modules, bonding,
grounding, labeling and duct seal.
D.
Campus IT shall rearrange telephone circuit cross-connects to re-assign existing
telephone circuits into sequential 50-pair count within existing 600-pair cable.
E.
Communications contractor splicing and cable pair transfer work shall take place in
MH 11 and HH 27.
F.
Communications contractor shall demo existing 600-pair cable between MH 11 and
HH 28 to make room for new tube cell ducts for air blown fiber. This work shall take
place after normal business hours.
G.
Communications contractor shall confirm with campus IT, that all telephone circuits are
working prior to closing up splice cases.
END OF SECTION 27 13 13
Communications Copper Backbone Cabling
27 13 13 - 4
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
SECTION 27 13 23
COMMUNICATIONS OPTICAL FIBER BACKBONE CABLING
PART 1 – GENERAL
1.1
SCOPE OF WORK
A.
The work under this section includes all design, material, equipment, supplies,
labor, testing, and accessories required to furnish and install a complete and
factory warranted campus wide air blown fiber optic data backbone system as
specified herein.
B.
The campus wide fiber optic data backbone system shall be defined as:
1.
all cables,
2.
equipment,
3.
products, etc, as mentioned in these specifications and to include
requirements of related documents.
4.
Please note, for this project, that the campus wide fiber optic data
backbone system includes underground conduit duct bank installations
and communications vault replacements.
C.
All miscellaneous system components including, but not limited to, cables,
termination equipment, patch panels, ladder racks, equipment racks, support,
seismic bracing as required and any other related items shall be furnished and
installed.
D.
Schedule is paramount to the project’s success. With this, the
authorized/licensed FutureFLEX contractor will have to continually work with the
team to facilitate expeditious design, procurement, and construction processes.
E.
Provide all necessary labor, material, and equipment, including but not limited to
the following requirements of this section.
F.
Fiber Upgrade Project will be completed in three phases as detailed below:
1.
Phase 1 – Installation of new factory warranted campus wide air blown
fiber optic data backbone system by a manufacturer authorized/licensed
contractor.
2.
Phase 2 – S.O.C.C.C.D. migration of network to new factory warranted
campus wide air blown fiber optic data backbone system.
3.
Phase 3 - The manufacturer authorized/licensed contractor shall
remove and dispose of all existing fiber optic data backbone systems.
Communications Optical Fiber Backbone Cabling
27 13 23 - 1
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
Removal scope of work shall include cleanup of all communications pullboxes, vaults and handholes. Removal scope of work shall included
installation of OSP rated duct plugs and conduit seals.
1.2
1.3
RELATED DOCUMENTS
A.
Drawings and general provisions of the Contract, including General and
Supplementary Conditions and Division 1 Specification Sections, apply to this
section.
B.
SECTION 27 05 26 - GROUNDING AND BONDING FOR
COMMUNICATIONS SYSTEMS
C.
SECTION 27 05 28 – PATHWAYS FOR COMMUNICATIONS SYSTEMS
D.
SECTION 27 11 00 - COMMUNICATIONS EQUIPMENT ROOM FITTINGS
E.
SECTION 27 13 13 - COMMUNICATION COPPER BACKBONE CABLING
SUMMARY
A.
For performance criteria, Sumitomo Electric Lightwave (SEL) FutureFLEX air
blow fiber is stated in this specifications section Appendix 1
B.
The manufacturer authorized/licensed air blown fiber installation
contractor (hereafter referred to as the Contractor) shall supply equipment,
materials, labor, and services to provide the air blown fiber
telecommunications distribution system including, but not limited to:
(1)
Optical fiber riser backbone cable and terminations.
(2)
Fiber optic cross-connect and patch panel systems.
(3)
Equipment racks and accessories installation.
(4)
Grounding of communications systems components.
(5)
Indoor Tube Cables and Tube Distribution Units
(6)
Outdoor Tube Cables and Outdoor Enclosures
(7)
Labeling of all tube cabling, and optical fiber bundles, terminations,
splices, patch panels, racks, and outlets.
(8)
Testing and test documentation of all tube cable, and optical fiber
bundles and connections.
(9)
Fire stopping.
(10)
Documentation preparation including but not limited to submittals, asbuilt drawings, system O&M documents, and product documentation.
Communications Optical Fiber Backbone Cabling
27 13 23 - 2
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
(11)
C.
1.4
Extended warranty and manufacturer’s certification of systems,
products, and labor.
Provide all equipment, materials, labor, whether specifically mentioned or not,
which be necessary to complete or perfect all parts of the installation.
Ensure that they are in compliance with requirements stated or reasonably
inferred by the contract documents.
REFERENCES
A.
ANSI/TIA/EIA 568-B.1 - Commercial Building Telecommunications Wiring
Standards, General requirements.
B.
ANSI/TIA/EIA 568-B.2 - Commercial Building Telecommunications Wiring
Standards, Balanced Twisted Pair Cabling Components.
C.
ANSI/TIA/EIA 568-B.3 - Commercial Building Telecommunications Wiring
Standards, Optical Fiber Cabling Components standards.
D.
ANSI/TIA/EIA 569 - Commercial Building standard for Telecommunications
Pathways and Spaces.
E.
ANSI/TIA/EIA 606-A – Administration Standards for Telecommunications
Infrastructures.
F.
ANSI/TIA/EIA Joint Standard – 607-A – Commercial Building Grounding
and Bonding requirements for Telecommunications.
G.
ANSI/TIA/EIA 526-7 – Measurement of Optical power Loss of Installed Singlemode Fiber Cable Plant (Method A).
H.
ANSI/TIA/EIA 526-14-A - Measurement of Optical power Loss of Installed
Multi-mode Fiber Cable Plant.
I.
ANSI/TIA/EIA 758 – Customer Owned Outside Plant Telecommunications
Cabling Standard.
J.
ANSI/TIA/EIA 758-1 - Customer Owned Outside Plant Telecommunications
Cabling Standard.
K.
Building Industry consulting services International (BICSI) Distribution
Methods Manual (TDMM).
L.
Building Industry consulting services International (BICSI) Customer
Owned Outside Design Manual.
M.
National Electrical Manufacturers Association (NEMA).
N.
National Fire Protection association (NFPA) 72, National Electrical Code (NEC).
Communications Optical Fiber Backbone Cabling
27 13 23 - 3
R2A Architecture
Costa Mesa, CA
09/28/2015
P.
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
Each agency's relative codes, standards, and recommended practices apply to
the voice / data cabling systems and their components as specified herein:
1.
Building Industry Consulting Service International (BICSI)
a.
Telecommunications Distribution Methods Manual (TDMM) – latest
edition.
b.
1.5
1.6
1.7
Customer Owned Outside Plant Design Manual (CO-OSP) latest
edition.
PERMITS, FEES, AND CERTIFICATES OF APPROVAL
A.
The contractor will make application and pay for all required permits.
B.
As prerequisite to final acceptance, the Contractor shall supply to the owner
certificates of inspection from an inspection agency acceptable to the owner
and approved by local municipality and utility company serving the project.
SYSTEM DESCRIPTION
A.
Design, manufacture, test, and install an ANSI/TIA compliant enterprise
network/LAN/SAN/Data Center/Campus system comprised of interconnecting
tube cables and tube distribution hardware, as the basic infrastructure to
provide reusable pathways for reusable PEF jacketed (Polyethylene Extruded
Foam), single bundled fiber optic cabling containing from 2 to 18 fibers,
installed per manufacturer’s requirements.
B.
Vertical/horizontal backbone cabling consists of an interconnecting tube cable
infrastructure of appropriately rated tube cables (riser, plenum, outdoor)
connected at strategic points implementing the appropriately rated tube
distribution hardware (NEMA rated) populated with reusable PEF jacketed,
air-blown fiber bundles of (62.5/125µm multimode and single mode) optical
fiber cable installed from the main distribution frame (MDF) to building
distribution frame (BDF), to the intermediate distribution frame (IDF).
C.
Provide cable runway (as indicated by construction documents).
D.
Provide communications grounding system (as indicated by construction
documents).
E.
Reflect as separate bid alternate costs for 62.5/125µm multimode.
SUBMITTALS
A.
General:
(1)
Provide submittals in accordance with Division 01 Submittal
Procedures and Division 01 Closeout Procedures.
(2)
Submit additional copies to Owner (South Orange County Community
College District) and Owner representatives.
Communications Optical Fiber Backbone Cabling
27 13 23 - 4
R2A Architecture
Costa Mesa, CA
09/28/2015
B.
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
Shop Drawings:
(1)
Show PEF jacketed, bundled optical fiber cable numbering and labeling.
(2)
Provide a schedule of materials list with quantities and manufactures
indicated for all materials installed in the project.
Provide Tube cable system block diagram including interconnection
and numbering of all tube cabling.
(3)
C.
D.
(4)
Provide fabrication drawings for any proposed custom-built equipment.
(5)
Submit for initial review 3 weeks after notice to proceed and for final
review at substantial Completion.
Product Data:
(1)
Provide manufacturer’s product data specifications sheets indicating
products being submitted.
(2)
Provide submittals for products with long lead times (4) weeks prior to
ordering the materials.
(3)
Provide submittals (3) weeks after receiving notice to proceed and prior
to installation of any of the product.
Schedule:
(1)
E.
Submit a coordinated schedule (3) weeks after notice to proceed to
include the following;
a.
Preconstruction meeting and walkthrough.
b.
Start and duration of communications rooms and closets
construction work.
c.
d.
Start and duration of tube cable installation, connection, and routing.
Start and duration of air-blown fiber optics installation and
termination.
e.
Punch List.
f.
Final Punch List.
Cable Test Results:
(1)
Tube Cable Tests
a.
Pressure Tests shall be submitted to the Owner’s
Representative on appropriate forms showing;
1.
2.
3.
Test date
Installer’s name
Tube Cable ID
Communications Optical Fiber Backbone Cabling
27 13 23 - 5
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
4.
5.
6.
7.
b.
(2)
F.
G.
Tube # (in)
Tube # (out)
Test Pressure (P.S.I.)
Time held
Obstruction Tests shall be submitted to the Owner’s
Representative on appropriate forms showing;
1.
Test date
2.
Installer’s name
3.
Tube Cable ID
4.
Tube # (in)
5.
Tube # (out)
6.
Span Length
7.
Travel time
8.
P.S.I. test rate
PEF jacketed, Bundled Fiber Optics Testing shall be submitted to the
engineer and copies to the Owner’s Representative.
a.
Submit manufacturer’s test reports for each reel of fiber bundle
provided prior to installation.
b.
Submit Contractors on-reel test results at 850 and 1300 nm for
multi-mode and 1310 and 1550nm for Single-mode.
c.
Submit Contractor’s test results after bundled fiber terminations
are installed.
d.
Submit soft copy PEF jacketed, bundled fiber optic cable OTDR
test results on compact disc (CD). Format CD test results in
comma separated variable (CSV) format wherever possible.
Provide proprietary software on the CD to enable viewing of the
soft-copy test results.
Project Record Drawings
(1)
Submit project record documents at Contract Closeout.
(2)
The contractor shall deliver three (3) sets of as-built drawings to the
owner within four (4) weeks of completion of the project. A set of asbuilt drawings shall be provided to the owner in digital form (floppy
disk or CD-ROM) and utilizing software that is acceptable to the
owner. The contractor shall deliver the digital media to the owner
within six (6) weeks of completion of the project.
Submit within 3 weeks after notice to proceed the names of those persons
who will have management and supervisory positions over the employees on
the job site. Submit the name of the supervisory person who will be on the
job site daily and have responsibility for day-to-day decisions. Submit the
name of the person who will attend meetings and have authority to make
decisions for issues and requirements that arise from such meetings.
Communications Optical Fiber Backbone Cabling
27 13 23 - 6
R2A Architecture
Costa Mesa, CA
09/28/2015
H.
Upon request by the engineer/designer, the Owner, and/or the Owner’s
representative furnish a list of references with specific information regarding
the type of project and involvement in providing other products and/or support
equipment used on this project.
I.
Where equipment and materials have industry certification, labels, or
standards (i.e., NEMA-National Electrical Manufacturer’s Assn.), this
equipment shall be labeled as certified or complying with the standards.
Material and equipment shall be new, and conform to grade, quality, and
standards specified. Equipment and materials of the same type shall be a
product of the same manufacturer throughout.
J.
1.8
1.9
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
QUALITY ASSURANCE
A.
Submit documentation signed by the manufacturer with the bid that states
the Contractor is authorized and certified by the manufacturer to provide
the Air Blown Fiber cable products installation and warranty certification.
Bids from non-compliant firms will be rejected.
B.
Submit documentation with the bid listing the names of employees that will
be used on this project indicating their experience, level of expertise, and
certificates of training signed by manufacturer representatives. Bids from noncompliant firms will be rejected.
C.
Complete all above Quality Assurance requirements.
WARRANTY REQUIREMENTS
A.
Submit at project closeout a signed and registered manufacturer (25) Year
P r e m i u m Warranty consisting of extended product warranty and
applications assurance in accordance with the Manufacturer Extended
Warranty Program.
B.
Submit, at " notice to proceed", the most current copy of the Manufacturer
certificate of registration and the warranty terms and conditions that apply to
the Manufacturer solution.
C.
Submit a statement, at notice to proceed, of any Contractor warranties in
addition to the manufacturer’s stated and supplied warranties. Submit at
closeout signed copies of the Contractor provided warranties that are in in
addition to manufacturer’s stated and supplied warranties.
D.
Twenty-Five (25) Year Premium Warranty
E.
SEL warrants the FutureFLEX products to be free of defects in material and
workmanship for a period of twenty-five (25) years from the date of shipment.
F.
This warranty shall be available for installations utilizing FutureFLEX tube
Communications Optical Fiber Backbone Cabling
27 13 23 - 7
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
cables, fiber bundles, fiber termination equipment and which have been
accepted by SEL into the Extended Warranty Program.
G.
1.10
The following is a list of items that must be submitted for application for this
warranty:
1.
Complete the Warranty registration Form on the FutureFLEX website
and submit to SEL.
2.
Testing data for the Obstruction and Pressure Test for each tube and
tube cable in the system.
3.
Sample Test Data Sheets are available on the SEL FutureFLEX website.
4.
Original handwritten test results from the field are required; typed results
are not acceptable.
5.
Electronic copies of all end to end fiber test results, using an optical
power meter or OTDR with fiber spans identified per As-Built Drawing.
6.
Power Meter - measurements at the highest wavelength.
7.
OTDR - Bi-Directional measurements at the highest wavelength.
Viewing software for OTDR results required.
8.
All software required to run or view the test data must accompany the
application.
9.
Copies of as built drawings must be submitted to SEL via electronic or
hard copy to SEL (Drawings must be in AutoCAD 2013).
10.
Submit copies of purchase invoices for the FutureFLEX products used in
the installation (Hard copies only).
H.
For the Premium Warranty program, SEL will evaluate the data supplied by the
Licensed FutureFLEX Installer (LFI). SEL engineers will review the data and
make a determination as to whether the installation will be accepted and an
extended warranty granted.
I.
If the application is accepted SEL will issue a warranty certificate to the LFI in
the name of the end- user. The LFI must sign the certificate and send it to the
End User.
J.
If the application is rejected, a letter explaining the reason for the rejection will
be issued to the LFI who applied for the extended warranty.
DELIVERY, STORAGE, AND HANDLING
A.
Protect equipment during transit, storage, and handling to prevent damage,
Communications Optical Fiber Backbone Cabling
27 13 23 - 8
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
theft, soiling, and misalignment. Coordinate with the owner for secure
storage of equipment and materials.
B.
C.
D.
1.11
1.13
Do not install damaged equipment; remove from site and replace damaged
equipment with new equipment.
SEQUENCE AND SCHEDULING
A.
1.12
Do not store equipment where conditions fall outside manufacturer’s
recommendations for environmental conditions.
Follow manufacturer’s recommended procedures for storage of materials &
equipment.
Refer to Submittals Section 1.7.D.1 above.
USE OF THE SITE
A.
Use of the site shall be at the owner’s direction in matters in which the
owner deems it necessary to place restriction.
B.
Access to building wherein the work is performed shall be as directed by the
owner.
C.
The owner will occupy the premises during the entire period of construction
for conducting his or her normal business operations. Cooperate with the
owner to minimize conflict and to facilitate the owner’s operations.
D.
Schedule necessary shutdowns of plant services with the owner, and
obtain written permission from the owner.
E.
Proceed with the work without interfering with ordinary use of streets, aisles,
passages, exits, and operations of the owner.
F.
Refer to Master Format Division 1 requirements.
CONTINUITY OF SERVICES
A.
Take no action that will interfere with, or interrupt, existing building
services unless previous arrangements have been made with the owner’s
representative. Arrange the work to minimize shutdown time
B.
Owner’s personnel will perform shutdown of operating systems. The contractor
shall give three (3) days’ advance notice for systems shutdown.
C.
Should services be inadvertently interrupted, immediately furnish labor,
including overtime, material, and equipment necessary for prompt restoration
of interrupted service.
PART 2 - PRODUCTS
Communications Optical Fiber Backbone Cabling
27 13 23 - 9
R2A Architecture
Costa Mesa, CA
09/28/2015
2.1
2.2
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
MANUFACTURERS
A.
Provide products of manufacturers as required in individual specifications
sections.
B.
Where no manufacturer is specified, provide products of manufacturers in
compliance with requirements.
C.
See APPENDIX 1 FutureFLEX® ABF® Product List for specific product part
numbers and description.
TUBE CABLES AND HARDWARE
The Contractor shall furnish and install all cables, connectors, and equipment as
shown on drawings and as specified below.
A.
B.
Indoor Tube Cable
(1)
Unless otherwise specified, tube cables shall provide at least two
times the number of tubes needed to complete the initial fiber
bundle installation requirements.
(2)
All indoor tube cables shall be composed of dielectric materials and
properly rated (i.e. – plenum/riser/general purpose) per application.
(3)
During installation, tube cable ends are to be completely sealed per
manufacturer’s recommended procedures to prevent ingress of
contaminants.
(4)
The minimum bend radius shall be 20 times the cable diameter during
installation and 10 times the cable diameter after installation.
(5)
Upon completion of tube cable installation, all tubes shall pass the
standard 150 psi pressure test and 5 mm bead obstruction test per
the cable manufacturer’s recommended procedures.
(6)
All unoccupied tubes shall
manufacturer’s specifications.
(7)
All Tube Distribution Units (NEMA rated per application), tube-splice
enclosures/Tube Splice Cases/cold-shrink closures per manufacturer’s
recommendations.
be
plugged
on
both
ends
per
Outdoor Tube Cables
(1)
Unless otherwise specified, tube cables shall provide at least two
times the number of tubes needed to complete the initial fiber
bundle installation requirements.
(2)
Tube cables may be composed of dielectric and metallic materials
Communications Optical Fiber Backbone Cabling
27 13 23 - 10
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
and shall be
applications.
C.
D.
suitable for underground, buried, and/or aerial
(3)
Tube cables for direct buried applications shall be steel armored for
rodent protection.
(4)
Conductive material(s) shall
ANSI/TIA/EIA-J Std- 607.
(5)
During installation, tube cable ends are to be completely sealed per
manufacturer’s recommended procedures to prevent ingress of
contaminants, including water.
(6)
The minimum bend radius of tube cable shall be 20 times the cable
diameter during installation and 10 times the cable diameter after
installation.
(7)
Upon completion of tube cable installation, all tubes shall pass the
standard 150 psi pressure test and 5 mm bead obstruction test per
the cable manufacturer’s recommended procedures.
(8)
All unoccupied tubes shall
manufacturer’s specifications.
(9)
All Tube Distribution Units (NEMA rated per application), Tube-splice
enclosures/Tube Splice Cases/cold-shrink closures per manufacturer’s
recommendations.
be
be
bonded
plugged
and
on
grounded
both
ends
per
per
TUBE DISTRIBUTION UNITS (TDUs)
(1)
A NEMA-rated enclosure, suitable for the site environmental conditions
(i.e. NEMA 1 for indoor use) shall be provided for tube distribution,
routing, and termination.
(2)
TDUs shall be installed as shown in the drawings, wherever several
cables enter the same location or where tube cable type transitions
take place.
(3)
The contractor is responsible for selecting the TDU hardware to meet
site conditions.
(4)
Choose TDU size based on the number of tubes to enter the unit.
(5)
TDUs shall be wall-, floor-, rack-, or ceiling-mounted to provide better
protection and geometry for distribution.
Outdoor Enclosure/Splice Case
(1)
Outdoor NEMA-rated enclosure, or splice case suitable for the site
environmental conditions shall be provided for outside plant tube
Communications Optical Fiber Backbone Cabling
27 13 23 - 11
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
distribution and routing.
(2)
(3)
2.3
a.
Splice Cases – Re-enterable splice cases that do not require reentry kits, are water-tight, and air-tight are recommended as a
cost effective alternative to NEMA 4, 4X, 6, & 6P enclosures.
b.
Recommended Outdoor Closure: Preformed Line Products,
Armadillo Series Splice Case – or equivalent.
Outdoor enclosures/splice cases shall be installed as shown in the
drawings wherever several cables enter the same location or cable
type transitions take place.
The contractor is responsible for selecting the enclosure/splice case
hardware to meet site conditions.
(4)
NEMA-4 and 4X enclosures or properly rated splice cases shall be
used in areas where hosing and splashing environmental conditions
exist.
(5)
NEMA-6 and 6P enclosures or properly rated splice cases shall be
used in areas where temporary or long term flooded environmental
conditions exist.
(6)
Kellems Grips shall be used to secure tube cables to outdoor
enclosures.
Choose outdoor enclosure size based on the number of tubes to
enter the enclosure.
REUSABLE, PEF JACKETED FIBER OPTIC BUNDLES
A.
All single mode and multi-mode fiber optic cabling will be in PEF (polyethylene
extruded foam) jacketed, bundled fibers available in 2, 4, 6, 12, and 18-fiber
bundles.
B.
Fiber bundles shall be provided based on immediate needs only.
C.
All fiber bundles shall be installed within the properly rated tube cable
infrastructure.
D.
The contractor shall furnish and install optical fiber bundles as identified on the
drawings.
E.
Fiber bundles shall not be spliced or patched at transition points from indoor
to outdoor environments.
F.
Fiber bundles shall be installed end to end or “home run” from CD to MC, BD,
FD, TR, or work area outlet whenever possible to minimize splicing and
patching.
G.
Zero tensile stress shall be placed upon the fiber bundles during installation to
eliminate micro-fractures within the glass.
Communications Optical Fiber Backbone Cabling
27 13 23 - 12
R2A Architecture
Costa Mesa, CA
09/28/2015
2.4
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
MULTIMODE 62.5/125µM
Reusable, PEF jacketed Fiber Optic Bundles - The optical fiber, with fiber counts as
indicated on drawings, shall have the following specifications:
2.5
A.
Dual window, 850 nm and 1300 nm.
B.
Minimum bandwidth – 220 MHz-km at 850 nm, 600 MHz-km at 1300 nm.
C.
Maximum attenuation – 3.5 dB/km at 850 nm, 1.5 dB/km at 1300 nm
D.
Standard Ethernet Distances – 300m at 850nm, 500m at 1300nm
E.
Extended Gigabit Ethernet Distances—500m at 850nm, 1000m at 1300nm
SINGLE-MODE
The optical fiber, with fiber counts as indicated on drawings, shall have the following
specifications:
2.6
A.
Dual window, 1310 nm and 1550 nm.
B.
Maximum attenuation – 0.40 dB/km at 1310 nm, 0.30 dB/km at 1550 nm.
C.
Dispersion unshifted, matched-clad, zero water peak.
BUNDLED FIBER ACCESSORIES
A.
Fiber Termination Units (FTUs)
(1)
A suitable enclosure (FTU) shall be provided at all locations where
fiber is to be terminated.
(2)
FTUs shall provide for strain relief of incoming tube cables as well as
providing connector panels and connector couplings adequate to
accommodate the number of fibers to be terminated.
(3)
All FTUs shall incorporate radius control mechanisms to limit
bending of the fibers to the manufacturer’s recommended minimums
or 3”, whichever is larger.
(4)
FTUs shall be wall or rack-mounted as specified in the drawings.
a.
(5)
f rack-mount fiber termination hardware is required, wall-mount a
TDU near the rack and use individual tube cabling (provided with
the fiber termination unit) to route and connect fiber bundle
passing through the TDU to the fiber termination hardware.
All terminated fibers shall be mated to (state preference) couplings
mounted on patch panels.
Communications Optical Fiber Backbone Cabling
27 13 23 - 13
R2A Architecture
Costa Mesa, CA
09/28/2015
B.
C.
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
(6)
Couplers shall be mounted on a panel that, in turn, snaps into the
housing assembly.
(7)
Panels shall be available to accommodate a changing variety of
connector types.
(8)
All FTUs shall have a common key lock that opens all FTUs
installed for this project.
(9)
Size FTUs to accommodate the total fiber count to be installed at
each location as defined in the drawings.
(10)
The contractor is responsible for selecting the FTU hardware to
meet site conditions
Optical Fiber Patch Cables
(1)
Optical fiber jumpers shall incorporate (state preference) connectors.
(2)
The connector body shall be of materials similar to that used in the
proposed couplings.
(3)
Channels shall be of equal length.
(4)
The optical fiber patch cables shall be (62.5/125µm multimode and
single mode) fiber utilizing tight buffer construction.
(5)
The optical fiber patch cables shall be a minimum of 3 meters long.
Connectors - SM/MM
(1)
The connector type shall be LC.
(2)
The attenuation per mated pair shall not exceed 0.75 dB (individual)
and 0.5 dB (average).
(3)
Connectors shall sustain a minimum of 200 mating cycles per
EIA/TIA-455-21 without violating specifications.
(4)
Connectors shall meet the following performance criteria:
Test
Cable Retention
Durability
Impact
Thermal Shock
Humidity
PART 3 – EXECUTION
Communications Optical Fiber Backbone Cabling
27 13 23 - 14
Procedure
FOTP-6
FOTP-21
FOTP-2
FOTP-3
FOTP-5
Maximum Attenuation Change
0.2 dB
0.2 dB
0.2 dB
0.2 dB
0.2 dB
R2A Architecture
Costa Mesa, CA
09/28/2015
3.1
3.2
PRE-INSTALLATION SITE SURVEY
A.
Prior to the start of systems installation, meet at the project site with the
owner’s representative and representatives of trades performing related work
to coordinate efforts. Review areas of potential interference and
resolve
conflicts
before proceeding with the work. Facilitation with the general
contractor shall be necessary to plan the crucial scheduled completions of the
equipment rooms and telecommunications rooms.
B.
Examine areas and conditions under which the system is to be installed. Do
not proceed with the work until satisfactory conditions have been achieved.
C.
Exact location of tube cable terminations shall be field verified with owner.
HANDLING AND PROTECTION OF EQUIPMENT AND MATERIALS
A.
3.3
3.4
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
The contractor shall be responsible for safekeeping own materials and
subcontractor’s property, such as equipment and materials, on the job site.
The owner assumes no responsibility for protection of above-named
property against fire, theft, and environmental conditions.
PROTECTION OF OWNER’S FACILITIES
A.
Effectively protect the owner’s facilities, equipment, and materials from dust,
dirt, and damage during construction.
B.
Remove protection at completion of work.
C.
Should it be found by the engineer that the materials, or any portion thereof,
furnished and installed under this contract fail to comply with the
specifications and drawings, with respect or regard to the quality, amount of
value of materials, appliances, or labor used in the work, it shall be rejected
and replaced by the contractor, and all work distributed by changes
necessitated in consequence of said defects or imperfections shall be
made good at the contractor’s expense.
INSTALLATION
A.
Tube Cable Installation
(1)
Prior to pulling tube cable, thoroughly swab conduits to remove
foreign material before pulling cables.
(2)
Beginning installation means contractor accepts existing conditions.
(3)
Contractor shall furnish all required installation tools to facilitate
Tube Cable installation without damage to the cable jacket. Such
equipment is
to
include, but not be limited to, sheaves, winches, cable reels, cable
reel jackets, duct entrance funnels, pulling tension gauges, and similar
Communications Optical Fiber Backbone Cabling
27 13 23 - 15
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
(4)
B.
devices.
All equipment shall be of substantial construction to allow steady
progress once pulling has begun. Makeshift devices that may move
or wear in a manner to pose a hazard to the cable shall not be used.
(5)
Tube Cable pulling shall be done in accordance with cable
manufacturer’s recommended procedures and ANSI/IEEE C2
standards. Manufacturer’s recommendations shall be a part of the
cable submittal. Recommended pulling tensions and minimum
bending radii shall not be exceeded. Any tube cable bent or kinked to a
radius less than recommended shall not be installed.
(6)
During tube cable pulling operation, an adequate number of
workers shall be present to allow cable observation at all points of
duct entry and exit as well as to feed cable and operate pulling
machinery.
(7)
Pulling lubricant shall be used to ease pulling tensions. Lubricant
shall be of a type that is non-injurious to the cable material used.
Lubricant shall not harden or become adhesive with age.
(8)
Avoid abrasion and other damage to cables during installation.
(9)
Tube Cable slack is required for thermal expansion/contraction per
manufacturer’s recommendations.
(10)
All exposed tube cable shall be labeled at 35-foot (maximum) intervals
with tags indicating ownership, cable type, and fiber type installed.
(11)
Tube cable shall be riser or plenum-rated if required by the
installation environment.
(12)
Where not installed in a continuous length, tube cable segments shall
be spliced using couplings designed for that purpose and housed
within a properly rated TDU (tube distribution unit), splice case, or cold
shrink wrap per manufacturer’s specifications.
Fiber Bundle Installation
(1)
Reusable, PEF jacketed (Polyethylene Extruded Foam), fiber bundles
shall be installed according to manufacturer’s recommended
procedures.
(2)
PEF jacketed optical fiber cable bundles shall be continuously inserted
and propelled or blown into the individual tubes utilizing compressed
nitrogen as the propellant per the manufacturer’s instructions. The
blowing installation process and the fiber bundles must also be
designed to allow removal, replacement, and reuse of the fiber
bundles at any time in the future as deemed necessary by the owner.
Communications Optical Fiber Backbone Cabling
27 13 23 - 16
R2A Architecture
Costa Mesa, CA
09/28/2015
C.
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
(3)
Slack in each PEF jacketed fiber bundle shall be provided as to allow
for future re-termination in the event of connector or fiber end-face
damage. Adequate slack shall be retained to allow termination at a
30” high workbench positioned adjacent to the termination
enclosure(s). A minimum of 1 meter (39”) of slack shall be retained
at the work area, and a minimum of 3 meters (approximately 10’) of
slack shall be retained in equipment rooms and telecommunications
closets.
(4)
Qualified personnel utilizing state-of-the-art equipment and techniques
shall complete all optical fiber terminations.
Labeling
(1)
All labeling shall be in accordance with ANSI/TIA/EIA-606 unless
otherwise noted by the owner.
(2)
Mark up floor plans showing outlet locations, type, and cable marking
of cables.
Turn these drawings over to the owner two (2) weeks prior to movein to allow the owner’s personnel to connect and test owner-provided
equipment in a timely fashion.
The contractor shall deliver three (3) sets of as-built drawings to the
Owner’s Representative within four (4) weeks of completion of the
project. A set of as- built drawings shall be provided to the owner in
digital form (floppy disk or CD- ROM) and utilizing software that is
acceptable to the owner. The contractor shall deliver the digital media
to the owner within six (6) weeks of completion of the project.
COOPERATION
(3)
3.5
A.
3.6
The contractor shall cooperate with other trades and owner’s personnel in
locating work in a proper manner. Should it be necessary to raise or lower or
move longitudinally any part of the work to better fit the general installation,
such work shall be done at no extra cost to the owner, provided such
decision is reached prior to actual installation. The contractor shall check
location of electrical outlets with respect to other installation before installing.
TESTING
A.
Tube Cable Tests
(1)
The contractor shall provide to the Owner’s Representative, obstruction
and pressure test data for each tube installed. Both pressure and
obstruction tests shall be completed prior to installing fiber bundle(s)
(2)
Pressure testing is required for testing end-to-end tube spans after
completion of tube cable installation and tube inter-connection.
Communications Optical Fiber Backbone Cabling
27 13 23 - 17
R2A Architecture
Costa Mesa, CA
09/28/2015
B.
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
(3)
Tube pressure testing shall be completed before proceeding with
end-to-end tube obstruction testing.
(4)
Obstruction testing shall be performed on all tubes upon completion of
tube cable installation and prior to fiber bundle installation.
Bundled Fiber Optic Testing
(1)
The contractor shall provide to engineer/Owner’s representative, the
cable manufacturer’s test report for each reel of fiber bundle
provided. These test reports shall include manufacturer’s on-reel
attenuation test results at both 850 nm and 1300 nm for multimode
and 1310 nm and 1550 nm for single-mode for each optical fiber of
each reel prior to shipment from the manufacturer.
(2)
The contractor will perform end to end attenuation test with an OTDR of
each optical fiber of each fiber bundle reel prior to installation. The
contractor shall supply this test data to the engineer prior to installation.
(3)
The fibers utilized in the installation shall be traceable to the
manufacturer. On-the-reel bandwidth performance as tested at the
factory shall be provided upon request.
(4)
Optical fiber bundle shall be tested before utilization as follows:
(5)
a.
Perform all tests and provide copies of all test results to the
engineer/Owner’s Representative.
b.
The contractor is responsible for supplying all equipment and
personnel necessary to conduct the acceptance tests. The
bidder should detail the proposed test plan for each cable type
including equipment to use, test frequencies, and wavelengths,
etc.
c.
The contractor shall conduct acceptance testing according to a
schedule coordinated with the owner. Representatives of the
Owner may be in attendance to witness the test procedures.
d.
The contractor shall offer adequate advance notice (at least one
week) to the Owner’ Representative as to allow for such
participation.
e.
The contractor is to describe how they will conduct the tests
and provide copies of all test results to the architect/engineer
Owner’s Representative.
All fibers shall be initially tested, end to end, with a light source and
OTDR utilizing procedures as stated in ANSI/TIA/EIA-526-14A:
OFSTP-14A Optical Power Loss Measurements of Installed Multimode
Fiber Cable Plant and ANSI/TIA/EIA-526- 7: OFSTP-7 Measurement
of Optical Power Loss of Installed Single-mode Fiber Cable Plant.
Measured results shall be plus/minus 1 dB of the submitted loss
Communications Optical Fiber Backbone Cabling
27 13 23 - 18
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
budget calculations. If loss figures are outside this range, test cable
with an optical time domain reflectometer to determine cause of
variation. Correct improper splices and replace damaged fiber at no
charge to the owner.
3.7
a.
Fibers shall be tested at 850 nm and 1300 nm for multimode
optical fiber bundles. Fibers shall be tested at 1310 nm and
1550 nm for single-mode optical fiber bundles.
b.
Testing procedures shall utilize “Method B” – One jumper reference.
c.
Bi-directional testing of optical fibers is required.
(6)
Test results shall include a record of wavelength, fiber type, fiber
and bundle number, test equipment and model number, date
reference setup, and operator (crew members).
(7)
The contractor shall provide written reports of all test data in written
form to the owner. At such time the contractor turns over test data to
the engineer.
(8)
In the event that test results are not satisfactory, the contractor
shall make adjustments, replacements, and changes as necessary
and shall then repeat the test or tests that disclosed faulty or
defective material, equipment, or installation method, and shall
perform additional tests as the engineer deems necessary.
(9)
Tests related to connected equipment of others shall only be
done with the permission and presence of the contractor involved.
The contractor shall perform only that testing as required to prove the
fiber connections are correct.
(10)
Three (3) record copies of all test data shall be submitted to the
architect/engineer for approval. The contractor shall notify the
architect/engineer at least one week in advance of the test date so
that the architect/engineer may be present.
(11)
Refer to Part 1.7-E Submittals.
GENERAL INSTALLATION DESCRIPTION
A.
The structured cabling system shall consist of any or all of the following
subsystems:
1.
2.
3.
B.
Administration Subsystem
Backbone Subsystem
Support Subsystem
Administration Subsystem: The Administration Subsystem links all of the
subsystems together. It consists of labels, diagrams, drawings, manuals, and
Communications Optical Fiber Backbone Cabling
27 13 23 - 19
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
tools necessary to manage the Structured Cabling System after installation. The
Administration Subsystem includes:
1.
2.
3.
4.
5.
6.
Labels
As-built drawings
Operations manuals
Record drawings
Test results
Warranty documents
C.
Backbone Subsystem: The main cable route within a building is called the
Backbone Subsystem. It links the main cross connect (MDF) in the equipment
room to intermediate cross connects (IC) in the BDFs and/or IDFs. It consists of
the backbone transmission media between these locations and the associated
connecting hardware terminating this media. It is normally installed in a star
topology with first-level backbone cables beginning at the main cross connect. If
needed, a second-level backbone cables begin at intermediate cross connects.
D.
A Backbone Subsystem in a single building will consist of a single MDF
connected to one or more IDFs on a single floor or on multiple floors. The
backbone will also connect the MDF to a Main Point of Entry (MPOE) which
houses the incoming telecommunications services for the building.
E.
A Backbone Subsystem in a multi-building campus will consist of a single MDF
connected to more than one BDF (one per building). Each BDF will be
connected to the IDFs of each respective building. The MDF will also connect to
the campus MPOE. Additional MPOEs may connect to the campus backbone
through the BDFs.
F.
The Backbone Subsystem includes:
1.
2.
3.
4.
5.
G.
OSP/Riser/Plenum rated fiber optic cable
Patch panels
Wall and rack mounted termination fields
Patch cables
Cross-connect wire
Support Subsystem: The Support Subsystem consists of hardware and
equipment required to facilitate and sustain the Structured Cabling System. The
Support Subsystem includes the cabling pathways, cabinets, and racks that hold
the structured cabling in place. The Support Subsystem includes:
1.
2.
3.
4.
5.
6.
Cable tray
Ladder Rack
Fire Stop systems
Conduit
Data Equipment Racks
Cabinets
Communications Optical Fiber Backbone Cabling
27 13 23 - 20
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
7.
8.
3.8
Vertical and Horizontal Wire Managers
Backboards
INSTALLATION REQUIREMENTS
A.
All materials shall be new. No used or re-manufactured parts or components
shall be accepted.
B.
All communications cabling used throughout this project shall comply with the
requirements as outlined in the NEC Articles 725, 760, 770, and 800 and the
appropriate local codes. All fiber optic cabling shall bear OFNP (Plenum Rated)
and/or OFNR (Riser Rated.
The contractor is responsible for installing
appropriately rated cable for the environment in which it is installed.
C.
Cable Storage: Do not roll or store cable reels without an appropriate underlay
and the prior written approval of District’s Project Manager.
D.
All installation shall be done in conformance with ANSI/TIA/EIA 568-C standards
and manufacturers installation guidelines. Ensure that the maximum pulling
tensions of the specified distribution cables are not exceeded and cable bends
maintain the proper radius during the placement of the facilities.
E.
The system must meet all local and other prevailing codes.
F.
All cabling installations shall be performed by qualified technicians. The labor
employed shall be regularly employed in the installation and repair of
communication systems and shall be acceptable to the District’s Project Manager
to engage in the installation and service of this system.
G.
Special Equipment and Tools: In order to ensure the least amount of cable
untwisting, it is required that all cables shall be stripped using a cable
manufacturer’s recognized special tool. It shall be the responsibility of the
Contractor to furnish any special installation equipment or tools necessary to
properly complete the System. This may include, but is not limited to, tools for
terminating cables, testing and splicing equipment for copper/fiber cables,
communication devices, jack stands for cable reels, or cable winches.
H.
The cable’s minimum bend radius and maximum pulling tension shall not be
exceeded.
I.
No cable is to be pulled through a conduit “L-bend” (condulets).
J.
Conduit runs shall not exceed 100 feet or contain more than two 90 degree
bends without utilizing appropriately sized pull boxes. Pull boxes are not to be
used in lieu of a bend.
K.
Reinstate all pull-wires in conduits and ducts after use to facilitate future addition
of cables.
L.
Cable raceways and conduits shall not be filled greater than the TIA/EIA
recommended fill for the particular raceway or conduit size.
M.
The use of lubricants (i.e. Yellow 77, Polywater) to facilitate the installation of
cables in conduits is highly discouraged, however, if such a lubricant must be
used, a lubricant specifically designed for the environment and type of cable
being installed shall be used. (E.G. the use of outside plant, low temperature
Communications Optical Fiber Backbone Cabling
27 13 23 - 21
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
cable lubricants shall not be acceptable in an indoor plenum environment.)
Under no circumstances shall cable pulling lubricant be allowed to accumulate on
walls, floors, backboards, or other surfaces outside the conduit.
N.
Any cable damaged or exceeding recommended installation parameters during
installation shall be replaced before final acceptance at no cost to the District.
O.
Power Separation: No distribution cabling shall be placed alongside power lines,
or share the same conduit, channel or sleeve with electrical apparatus. At no
point shall the communications cables be tied to power cables or other building
services. Station cables and tie cables installed within ceiling spaces shall be
routed through these spaces at right angles to electrical power circuits.
P.
Avoid electromagnetic interference (EMI) by maintaining adequate physical
separation between telecommunications cabling and possible sources such as,
but not limited to, electric motors, electric pencil sharpeners, transformers,
fluorescent lights that share distribution space with telecommunications cabling,
copiers that share work area space with line cords and terminals, large fax
machines and power cords that supports such equipment.
Q.
All cable or innerduct shall run parallel or at right angles to building wall
structures.
R.
Within walls, all cabling shall be installed within conduit to an elevation of + 6"
above the accessible ceiling space.
S.
Cable tray shall be provided as designated by drawings in the
telecommunications room. The cable tray shall be basket type and sized per
code to accommodate all cabling to be installed plus spare.
T.
In suspended ceiling and raised floor areas where duct, cable trays or conduit
are not available, cable bundles shall be supported via "J" hooks attached to the
building structure and framework at a maximum of five (5) foot intervals.
Minimum 1” wide J-hooks shall be appropriately sized to allow a minimum of 50%
spare capacity for future cable installation. The Contractor shall include all costs
in base bid for any additional supports/seismic bracing required by the Local
Authority having Jurisdiction.
U.
Cables shall be bundled, in groups of 18 or less, station or other cabling with half
inch hook and loop (Velcro®) strips tight enough to hold the bundle together in a
cylindrical shape, but not so tight as to deform the cable geometry. It shall be
possible to completely rotate all cable ties around all cable bundles. Plenum
rated hook and loop ties will be used in all plenum areas.
V.
Cables or J hooks shall not be attached to lift out ceiling grid supports or laid
directly on the ceiling grid.
W.
Cables or J hooks shall not be attached to or supported by fire sprinkler heads or
delivery systems or any environmental sensor located in the ceiling air space.
X.
Conduit(s) and sleeve(s) shall be of suitable material, sized, installed, firestopped, and grounded as required by the NEC, ANSI/TIA/EIA standards and all
other applicable codes and standards. Any conduit(s) and sleeve(s) added shall
be approved by the District’s Project Manager prior to rough-in.
Communications Optical Fiber Backbone Cabling
27 13 23 - 22
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
Y.
Removal of the ceiling grid must be coordinated with the District’s Project
Manager. All insulation shall be replaced in its original location.
Z.
Cabling and Termination Identifications: A numbering and marking scheme must
be used to identify all cable and cabling terminations. All cables, regardless of
length, shall be marked and/or numbered at both ends. Marking codes and
methodologies shall correspond to the instructions in this specification.
AA.
Ensure that all waste materials are disposed of in a safe manner. Pay particular
attention to waste materials produced during the termination of optical fiber
cabling. Ensure that all used components and fiber cut-offs are collected in
purpose-made containers and disposed of properly.
BB.
Ladder tray mounting brackets shall be screwed to studs or to the properly
mounted plywood wall field, not to drywall.
CC.
Seismic Requirements: All equipment racks, equipment cabinet enclosures,
cable runways, etc. shall be installed according to the local, state and/or federal
seismic code.
DD.
All exposed parts of the equipment, cabinets, and other equipment shall be left in
a clean condition, unblemished and free of all dirt, dust, smudges, spots,
fingerprints, etc.
EE.
Conduits: All backbone cabling will run through dedicated conduits. All new
conduits will be supplied with a pull string. Existing conduits shall be proven to
be clear prior to pulling of cables. Supply pull string and pull rope for the
installation of all cables in existing conduits. For all conduits left with available
capacity, replace pull strings with ¼-inch pull rope during the course of his work.
The installing contractor must seal all conduits with an approved sealing
compound.
FF.
Use purpose-built pulling grips during cable installation. Do not pull cables by
attaching pull wires to cable jackets, elements or reinforcement. The cable
pulling tension shall be applied smoothly without jerks. Use strain gauges or
equivalent measures to ensure that the maximum manufacturer recommended
tensile load rating of the cables is not exceeded during installation.
GG.
The number of cables in each conduit shall be controlled to allow for future cable
installation and to stay within the manufacturer’s maximum allowable cable
pulling tension. Conduit fill ratios shall not exceed the current requirements of
the NEC.
HH.
Provide expansion plugs in all ducts/conduits entering the building. Seal all
unused ducts/conduits with plugs that allow the pull-string to be tied off on the
inside.
II.
All cabling shall be splice free unless otherwise noted on drawings.
JJ.
All grounds shall consist of #6 AWG copper wire and shall be supplied from an
approved building ground and bonded to the main electrical ground. All cable
sheaths and splice cases shall be grounded to a Telecommunications Ground
Bus. Grounding must be in accordance with the NEC, NFPA, ANSI/TIA-607-B2011 and all local codes and practices. Bond all metallic sheath communications
Communications Optical Fiber Backbone Cabling
27 13 23 - 23
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
cables entering the building per manufacturer specifications and NEC 770-33,
800-33 and 800-40.
KK.
Each equipment cabinet and rack requires its own dedicated grounding
connection to the grounding infrastructure. Grounding infrastructure can consist
of either an “aisle ground” conductor placed at the ladder tray above each
rack/cabinet, or by providing every rack/cabinet with its own dedicated #6 AWG
(min.) green conductor back to the TMGB/TGB.
All ground conductor
attachments to the TMGB/TGB shall utilize 2-hole compression lugs.
LL.
Rack mounted equipment shall be grounded via the chassis, in accordance with
manufacturer’s instructions. The equipment chassis shall be bonded to the
rack/cabinet using one of the following methods:
1.
2.
MM.
3.9
If the equipment has a separate grounding hole or stud, use a #6AWG
ground wire from the chassis ground hole/stud to the rack grounding bus.
If the manufacturer suggests grounding via the chassis mounting flanges,
use tri-lobular thread-forming screws (not self-tapping or sheet metal
screws) to attach the equipment to the rack/cabinet rails. If the
equipment mounting flanges are painted, remove the paint and apply an
anti-oxidant, or use tri-lobular thread-forming screws and two (2) “Type B”
internal-external tooth lock washers to safely ground equipment to the
rack.
Bonding of ladder tray sections- Attach bonding straps to each ladder tray
section by utilizing either two (2) tri-lobular thread-forming screws (not selftapping or sheet metal screws) or by using two (2) standard bolts with two (2)
“Type B” internal-external tooth lock washers per bolt. If thread-forming screws
are not used, remove paint at each connection point and use an approved antioxidant prior to attaching the bonding strap.
PENETRATIONS OF WALLS FLOORS AND CEILINGS
A.
Any penetrations through acoustical walls or other walls for cable pathways /
cables shall be sealed in compliance with applicable code requirements and as
directed by District’s Project Manager.
B.
Replace all moisture and fire barrier material in ducts, conduits and other
penetrations disturbed during installation of communications cabling.
C.
Any penetrations through fire-rated walls for cable pathways / cables shall be
sealed by use of a non-permanent fire blanket or other method in compliance
with the current edition of NFPA and the NEC or other prevailing code and must
be an approved UL Listed system. Do not use concrete or other non-removable
substance for fire stopping on cable trays, wireways or conduits. This
requirement also applies to maintaining fire ratings of all floors penetrated by
conduits or devices designated for use by voice and data cabling.
D.
Sealing material and application shall be an approved UL Listed system and shall
be accomplished in such a manner that is acceptable to the local fire and building
Communications Optical Fiber Backbone Cabling
27 13 23 - 24
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
authorities having jurisdiction over this work. Any openings left unused shall also
be sealed as part of this work.
3.10
1.
Firestopping work shall be performed by a single contractor to maintain
consistency and accountability on the project.
2.
Firestop installer shall be certified, licensed or otherwise qualified by the
firestopping manufacturer as having been provided the necessary training
to install manufacturer’s products per specified requirements.
3.
All installed through penetration firestops shall be identified via label, or
stencil. Label shall state that the fill material around the penetrating item
is a firestop, and that it shall not be disturbed unless by an authorized
contractor. The label shall include the firestop brand name, and the
classified system number for which it was installed.
LABELING REQUIREMENTS
A.
Labeling: Provide printed labels for all cables and cords, distribution frames, and
outlet locations, according to the specifications. No labels are to be written by
hand.
B.
Riser Cable Labeling. All riser cables will be labeled to reflect the origin and
destination abbreviation for the cable and pair counts on large font (16 pitch) selflaminating labels, which shall be located within 18 inches of each end of the
cable. Labels shall be placed on the cable to be visible without relocating
surrounding cables.
Example #1: BDF1/IDF31/SM1/01-06
BDF1 Cable Origination
DF31 Cable Destination
SM1 Cable Type & Pair or Strand Count (ex. SM1 for single-mode fiber). Other
possibilities include HB for hybrid fiber cable, MM for multimode cable, and SM
for singlemode cable.)
01- 06 Cable pair or strand identification number (ex. cable 01- 01, indicates a 6strand fiber cable)
C.
Patch Panel Labels, Horizontal. All patch panels will be labeled using selflaminating laser patch panel label markers.
Example: 001A
001
Station Number
A
Cable Identification (“A” for data cable #1, “B” for data cable #2)
Communications Optical Fiber Backbone Cabling
27 13 23 - 25
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
1.
D.
Data cable #1 shall be terminated adjacent to data cable #2 moving left to
right and top to bottom.
Fiber Patch Panel Labels. All fiber patch panels will be labeled using selflaminating laser patch panel label markers. The scheme shall indicate:
destination of connected cables on the patch panel followed by a slash (/),
origination of connected cables on the patch panel followed by a slash (/), and
the port number adjacent to the port
Example: BDF/IDF2/01
BDF
Destination Patch Panel Location Designation
IDF22 Origination Patch Panel Location Designation
01
E.
Indicates port number on both origin and destination patch panels.
Equipment Rack Labeling: All equipment racks shall be labeled according to
their room identifier and a two-digit number. The labels will be engraved plastic
plates, with 1”-high white letters on black background. The labels will be
attached to the crossmember at the top front of each frame or rack with
appropriately-sized sheet metal screws. Self-adhesive strips, glues, etc. are
unacceptable.
Example: BDF1-01
BDF1 Room Designation
01
F.
3.11
Rack Identifier
MDF/BDF/IDF Floor Plan Mounting Frame: Provide wall mountable floor plan
mounting frame with removable Plexiglas front cover in each MDF/BDF/IDF.
Frame and cover shall be sized to house 30”x42” floor plan drawing. Coordinate
location of frame with District’s Project Manager prior to installation.
TESTING/WARRANTY
A.
The testing is to show that there are no errors, damaged or incorrectly installed
components, that the installation is correctly labeled and that all the installed
components meet or exceed the criteria detailed in these specifications. Any test
that does not show that a component is satisfactorily installed, as per these
specifications, shall be repeated. If a test procedure needs to be modified to
satisfactorily test some components, the modification shall be submitted for
approval of the District’s Project Manger prior to the tests being conducted.
B.
All cables, patch panels and associated components shall be fully assembled
and labeled prior to testing. Any testing performed on incomplete systems shall
Communications Optical Fiber Backbone Cabling
27 13 23 - 26
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
be redone on completion of the work.
C.
Provide the Districts' Project Manager with the opportunity to witness all testing.
On reasonable request, the installer shall demonstrate that the test procedure
competently identifies the fault conditions being tested for.
D.
Complete all of the tests identified in these specifications.
E.
Ensure that all test equipment is in calibration before delivery to site and
throughout the testing period. The Installer shall be responsible for ensuring that
any necessary tests and rework to maintain equipment's calibration status is
carried out. Any tests performed on uncalibrated test equipment shall be
repeated at the Installer’s cost.
F.
The test documentation shall be available for inspection by the Districts' Project
Manager during the installation period and copies shall be submitted to the
Districts' Project Manager within fourteen days of completion of tests on cables in
each area. The Installer shall retain a copy to aid preparation of Record
Documents information. See Records Documents details under submittals
section.
G.
If on submittal of the Record documentation there are any missing test results or
incorrectly named files, the test shall be repeated at the Installer’s expense.
H.
Provide competent, factory-trained engineers and/or technicians, authorized by
the manufacturer of the cabling system, to technically supervise and participate
during all tests for the systems. Personnel shall be competent in and qualified by
experience or training for comprehensive TDR and OTDR operation and
troubleshooting, for optical fiber testing.
I.
All cables and termination hardware shall be 100% tested for defects in
installation and to verify cable performance under installed conditions. All
conductors of each installed cable shall be verified usable by the installing
contractor before system acceptance. Any defect in the cable system installation
including but not limited to cable, connectors, feed-through couplers, patch
panels, splices, and connector blocks shall be repaired or replaced in order to
ensure 100% useable conductors in all cables installed.
J.
Each installed cable shall be tested for installed length using a Time Domain
Reflectometer (TDR) device. The cables shall be tested from patch panel to
patch panel, block to block, patch panel to outlet or block to outlet as appropriate.
The cable length shall conform to the maximum distances set forth in the
ANSI/TIA-568-C Standard. Cable lengths shall be recorded, referencing the
cable identification number and circuit or pair number.
K.
When repairs and re-tests are performed, the problem found and corrective
action taken shall be noted, and both the failed and passed test data shall be
collocated in the binder. Correction of all damaged cables shall include replacing
damaged cables with new cables in complete runs, replacing damaged
connectors or remaking poor terminations. In-line cable joints, splices or
distribution points will not be acceptable except where specified in this document.
All damaged cables shall be removed from site.
L.
Manufacturer Warranty: Provide a Manufacturer (25) Year P r e m i u m
Warranty.
Communications Optical Fiber Backbone Cabling
27 13 23 - 27
R2A Architecture
Costa Mesa, CA
09/28/2015
M.
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
Optical Fiber Cable Testing: All fiber testing shall be performed on all fibers in
the completed end to end system including any and all fusion splices.
1.
Testing shall consist of a bi-directional end to end power meter test
performed per TIA-526-7. The system loss measurements shall be
provided at 1310 and 1550 for single mode fibers.
2.
Loss Budget: Fiber links shall have a maximum loss of: (allowable cable
loss per km)*(km of fiber in link) + (.4dB)*(number of connectors) =
maximum allowable loss.
3.
For all end to end fiber runs greater than 300 ft. in length, and any run
less than 300 ft. in length that does not meet the minimum loss
requirement, testing shall also include a bi-directional end to end OTDR
trace.
4.
Graphical printouts shall be taken of OTDR trace tests for each element.
These printouts shall be stapled or otherwise attached to 11" x 8.5" size
sheets. They shall be printed at an appropriate scale, such as 0.5 dB per
division for the attenuation axis. Provide electronic copies of the OTDR
traces to the District on completion of the testing. Provide a copy of the
emulation software and the appropriate license to the client.
5.
Pre-installation cable testing: It is recommended that all fiber cable be
tested prior to the installation.
6.
Any link not meeting the requirements of the standard shall be brought
into compliance at no additional charge to District.
END OF SECTION 27 13 23
Communications Optical Fiber Backbone Cabling
27 13 23 - 28
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
APPENDIX 1
FutureFLEX® ABF® Product List
INDOOR TUBE CABLES
SEL PART NUMBER DESCRIPTION
“TC01TBX”
“TC”
“01, 02, etc.”
TBX”
Sumitomo Part Number (typical)
Tube Cable
Number of Individual Tubes
Tube Cable Description
NON-RATED INDOOR TUBE CABLES
INDOOR NON-RATED TUBE CABLE DESCRIPTIONS & APPLICATIONS
TBX
Black tube
No fire rating
For general tube drops or interconnections
TXX
Semi-transparent tube
No fire rating
For general tube drops or interconnections
INDOOR NON-RATED TUBE CABLE TYPES & SIZES AVAILABLE
TYPE
Black Tube
Semi-Transparent Tube
SINGLE-TUBE
TC01TBX
TC01TXX
INDOOR NON-RATED TUBE CABLE SPECIFICATIONS
PROPERTY
Operation Temperature Range
Minimum Bend Radius (During and
After Installation) for Single Tubes:
SPECIFICATION
-40° to +158°F (TBX & TXX only)
7” (Radius) when installing 2mm OD Fiber
Bundles
9” (Radius) when installing 3mm OD Fiber
Bundles
Communications Optical Fiber Backbone Cabling
27 13 23 - 29
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
FIRE-RATED INDOOR TUBE CABLES
INDOOR RATED TUBE CABLE DESCRIPTIONS & APPLICATIONS
TRX
TGX
OFN
General Purpose Fire Rated
Individual black tubes
No outer jacket
Multiple tubes wrapped
with Kevlar string binder
TPX
OFNR
RiserInner fire retardant jacket
and
Orange-colored fire
blocking outer jacket
OFNP
Plenum-Rated
Individual black tubes
No outer jacket
Multiple tubes wrapped
with Kevlar string binder
INDOOR RATED TUBE CABLE TYPES & SIZES AVAILABLE
TYPE
OFN
OFNR
OFNP
1-TUBE
TC01TGX
--TC01TPX
2-TUBE
TC02TGX
TC02TRX
TC02TPX
3-TUBE
--TC03TRX
TC03TPX
7-TUBE
TC07TGX
TC07TRX
TC07TPX
19-TUBE
TC19TGX
TC19TRX
TC19TPX
INDOOR RATED TUBE CABLE SPECIFICATIONS
PROPERTY
OFN General Purpose Fire Rated
OFNR Riser-Rated
OFNP Plenum-Rated
Operation Temperature Range
Minimum Bend Radius for Multi-Tube
Cables
Minimum Bend Radius for Multi-Tube
Cables
Minimum Bend Radius for Single Tubes
(During and After Installation):
Communications Optical Fiber Backbone Cabling
27 13 23 - 30
SPECIFICATION
UL 1581
UL 1666
UL 910
-20° to +158°F
20X cable diameter
10X cable diameter or
9” Radius whichever is greater
7” Radius when installing 2mm Fiber
Bundles
or
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
INDOOR TUBE CABLE PHYSICAL CHARACTERISTICS
Sumitomo
Part No.
Cable OD
(in)
TC01TBX
TC01TGX
TC01TPX
TC01TXX
TC02TGX
TC02TPX
TC02TRX
TC03TPX
TC03TRX
TC07TGX
TC07TPX
TC07TRX
TC19TGX
TC19TPX
TC19TRX
0.31
0.31
0.31
0.31
0.6
0.6
1.0
0.6
1.0
1.0
1.0
1.3
1.6
1.6
1.9
Max.
Weight
(lbs/kft)
Max. Tensile Load
(lbs.)
60
60
60
60
100
120
200
180
200
150
360
400
250
400
500
15
17
27
15
70
53
229
80
282
119
189
437
325
513
806
INDOOR TUBE CABLE STANDARD REEL DATA
Sumitomo
Part No.
Std Reel
Length
(ft)
Std Reel
HxW
(in)
TC01TBX
TC01TGX
TC01TPX
TC01TXX
TC02TGX
TC02TPX
TC02TRX
TC03TPX
TC03TRX
TC07TGX
TC07TPX
TC07TRX
TC19TGX
TC19TPX
TC19TRX
--100
1000
500
100
100
100
100
100
1000
100
100
1000
100
100
--25 x 13
41 x 6
17 x 5
36 x 34
54 x 10
54 x 20
54 x 20
54 x 36
54 x 20
54 x 20
54 x 36
64 x 40
64 x 40
60 x 48
Notes:
•
•
•
•
Minimum
Drum
Diameter
(in)
--20
36
5
18
40
40
40
40
40
40
40
46
46
40
Std Reel
Weight
(lbs)
Empty
--17
33
1
66
105
116
116
137
116
116
137
248
248
246
Std Reel
Weight
(lbs) Full
--34
60
16
136
158
345
196
419
235
305
574
573
761
1052
Cut Lengths are also available. Contact SEL or FutureFLEX® Distributor
for additional information.
Maximum Reel Length tolerances are +5%.
All Reel Widths shown are approximate values only and measured from outsideof-flange to outside-of-flange.
If tube cable is re-spooled, the Minimum Drum Diameter of the new reel SHALL be
Communications Optical Fiber Backbone Cabling
27 13 23 - 31
R2A Architecture
Costa Mesa, CA
09/28/2015
•
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
as shown to avoid damaging tube cable product
All Empty and Full Reel Weights shown are approximate values only.
INDOOR TUBE CABLE MAXIMUM REEL DATA
Sumitomo
Part No.
Max Reel
Length
(ft)
TC01TBX
TC01TGX
TC01TPX
TC01TXX
TC02TGX
TC02TPX
TC02TRX
TC03TPX
TC03TRX
TC07TGX
TC07TPX
TC07TRX
TC19TGX
TC19TPX
TC19TRX
330
3000
300
--3000
300
300
300
300
3000
300
300
3000
300
300
Notes:
•
•
•
•
•
Max Reel
HxW
(in)
28 x 20
28 x 20
54 x 10
--36 x 34
54 x 36
60 x 48
54 x 36
60 x 48
60 x 48
60 x 48
72 x 40
72 x 50
72 x 50
84 x 50
Minimum
Drum
Diameter
(in)
20
20
40
--18
40
40
40
40
40
40
46
46
46
30
Max Reel
Weight (lbs)
Empty
Max Reel
Weight (lbs)
Full
18
18
105
--66
137
246
137
246
246
246
309
333
333
288
68
69
186
--276
296
933
377
1092
603
813
1620
130
187
2706
Cut Lengths are also available. Contact SEL or FutureFLEX® Distributor
for additional information.
Maximum Reel Length tolerances are +5%.
All Reel Widths shown are approximate values only and measured from outsideof-flange to outside-of-flange.
If tube cable is re-spooled, the Minimum Drum Diameter of the new reel SHALL be
as shown to avoid damaging tube cable product
All Empty and Full Reel Weights shown are approximate values only.
OUTDOOR TUBE CABLES
SEL PART NUMBER DESCRIPTION
“TC02TOX”
“TC”
“01, 02, etc.”
“TOX”
Communications Optical Fiber Backbone Cabling
27 13 23 - 32
Sumitomo Part Number (typical)
Tube Cable
Number of Individual Tubes
Tube Cable Description
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
OUTDOOR “DIELECTRIC CORE” TUBE CABLE DESCRIPTIONS & APPLICATIONS
TOX
Dry to damp
environment
Duct, direct
buried
applications
TOD
Dry to damp
environments
Duct, direct
buried
applications
MSOS
Dry to damp
environments
Aerial, duct,
direct
buried
applications
AOX
Dry to damp
environments
Duct, direct
buried
applications
Dielectric c or e
Water-blocking
tape
Dielectric c or e
Water-blocking
tape
Dielectric c or e
Water-blocking
tape
Dielectric c or e
Water-blocking
tape
TAX *
Dry to damp
environment
Duct, direct buried
applications
Extremely rugged,
high crush
resistance
Dielectric c or e
Water-blocking
tape
Polyethylene
outer jacket
Polyethylene
outer jacket
Highperformance
outer jacket for
enhanced
thermal
stability
Polyethylene
outer jacket
Polyethylene
outer jacket
FRP (fiber
reinforced plastic)
central strength
member
Ultra-high
performance
tubes with low
friction liners
Corrugated steel Extra heavy duty
tape armor for
interlocked
rodent protection galvanized steel
armor jacket
Grounding &
Bonding
required
Grounding &
Bonding
required
Notes:
•
TAX-type Tube Cable is a non-standard product. Use TLA-type Tube Cable as
alternative.
Communications Optical Fiber Backbone Cabling
27 13 23 - 33
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
OUTDOOR “METALLIC CORE” TUBE CABLE DESCRIPTIONS & APPLICATIONS
TLW
Flooded environments
Duct, direct buried
applications
LWS
Flooded environments
Duct, direct buried
applications
Metallic core Water
blocking tape
Laminated Aluminum
Polyethylene (LAP)
wrap Polyethylene
outer jacket
Metallic core Water
blocking tape
Laminated Aluminum
Polyethylene (LAP)
wrap Polyethylene
outer jacket
Grounding & Bonding
recommended
TLA
Flooded environments
Duct, direct buried applications
Extremely rugged, high crush
resistance
Metallic core Water
blocking tape Laminated
Aluminum Polyethylene
(LAP) wrap Polyethylene
outer jacket
Corrugated steel tape armor
for rodent protection
Extra heavy duty interlocked
galvanized steel armor jacket
Grounding & Bonding
recommended
Grounding & Bonding
recommended
OUTDOOR TUBE CABLE TYPES & SIZES AVAILABLE
TYPE
OSP
OSP
OSP - AERIAL
OSP
OSP
OSP
OSP
OSP
2-TUBE
----TC02MSOS
--------TC02TOX
4-TUBE
----TC04MSOS
------TC04TOD
---
7-TUBE
TC07AOX
TC07LWS
TC07MSOS
TC07TAX *
TC07TLA
TC07TLW
--TC07TOX
19-TUBE
----TC19MSOS
TC19TAX *
TC19TLA
TC19TLW
--TC19TOX
Notes:
•
TAX-type Tube Cable is a non-standard product. Use TLA-type Tube Cable as
alternative.
OUTDOOR RATED TUBE CABLE SPECIFICATIONS
PROPERTY
Operation Temperature Range
Minimum Bend Radius for Multi-Tube
Cables
Minimum Bend Radius for Multi-Tube
Cables
Communications Optical Fiber Backbone Cabling
27 13 23 - 34
SPECIFICATION
-40° to +158°F
20X cable diameter
10X cable diameter
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
OUTDOOR TUBE CABLE PHYSICAL CHARACTERISTICS
Sumitomo
Part No.
TC02MSOS
TC02TOX
Cable OD
(in)
0.9
0.9
0.9
Max. Weight
(lbs/kft)
89
87
141
Max. Tensile Load
(lbs.)
200
200
200 with standard
basket-weave grip,
500 with pulling eye
0.9
137
1.4
1.4
1.1
1.5
1.5
1.1
1.1
1.7
2.1
2.1
1.8
1.7
438
479
196
825
870
223
205
399
115
1650
463
443
200 with standard
basket-weave grip,
500 with pulling eye
500
400
400
500
400
400
400
500
500
500
500
500
TC04MSOS
TC04TOD
TC07AOX
TC07LWS
TC07MSOS
TC07TAX *
TC07TLA
TC07TLW
TC07TOX
TC19MSOS
TC19TAX *
TC19TLA
TC19TLW
TC19TOX
Notes:
•
TAX-type Tube Cable is a non-standard product. Use TLA-type Tube Cable as
alternative.
Communications Optical Fiber Backbone Cabling
27 13 23 - 35
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
OUTDOOR TUBE CABLE STANDARD REEL DATA
Sumitomo
Part No.
Std Reel
Length
(ft)
Std Reel
H x W (in)
TC02MSOS
TC02TOX
TC04MSOS
TC04TOD
TC07AOX
TC07LWS
TC07MSOS
TC07TAX *
TC07TLA
TC07TLW
TC07TOX
TC19MSOS
TC19TAX *
TC19TLA
TC19TLW
TC19TOX
1000
1000
100
100
100
100
100
100
100
1000
1000
100
100
100
1000
1000
36 x 17
36 x 17
54 x 36
54 x 36
60 x 48
60 x 48
54 x 36
64 x 40
64 x 40
54 x 36
54 x 36
64 x 40
72 x 40
72 x 40
72 x 40
60 x 48
Notes:
•
•
•
•
•
•
Std Reel
Weight
(lbs)
Empty
55
55
137
137
246
246
137
248
248
137
137
248
309
309
309
246
Std
Reel
Weight (lbs)
Full
144
142
278
274
684
725
333
1073
1118
360
342
647
1461
1959
772
689
Cut Lengths are also available. Contact SEL or FutureFLEX® Distributor
for additional information.
Standard Reel Length tolerances are +5%.
All Reel Widths shown are approximate values only and measured from outsideof-flange to outside-of-flange.
If tube cable is re-spooled, the Minimum Drum Diameter of the new reel SHALL be
as shown to avoid damaging tube cable product
All Empty and Full Reel Weights shown are approximate values only.
TAX-type Tube Cable is a non-standard product. Use TLA-type Tube Cable as
alternative.
Communications Optical Fiber Backbone Cabling
27 13 23 - 36
Minimum
Drum
Diameter
(in)
18
18
40
40
40
40
40
46
46
40
40
46
46
46
46
40
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
OUTDOOR TUBE CABLE MAXIMUM REEL DATA
Sumitomo
Part No.
TC02MSOS
TC02TOX
TC04MSOS
TC04TOD
TC07AOX
TC07LWS
TC07MSOS
TC07TAX *
TC07TLA
TC07TLW
TC07TOX
TC19MSOS
TC19TAX *
TC19TLA
TC19TLW
TC19TOX
Notes:
•
•
•
•
•
•
Max Reel
Length
(ft)
3000
3000
3000
3000
3000
3000
3000
3000
3000
3000
3000
3000
2300
2300
3000
3000
Max
Reel H x W
(in)
60 x 48
60 x 48
60 x 48
60 x 48
72 x 50
72 x 50
60 x 48
72 x 50
72 x 50
60 x 48
60 x 48
72 x 50
72 x 50
72 x 50
72 x 50
72 x 50
Minimum
Drum
Diameter
(in)
40
40
40
40
46
46
40
46
46
40
40
30
30
30
30
30
Max Reel
Weight (lbs)
Empty
246
246
246
246
333
333
246
333
333
246
246
288
288
288
288
288
Max Reel
Weight
(lbs)
Full
513
507
669
657
1647
1770
834
2808
2943
915
861
1485
2938
4083
1677
1617
Cut Lengths are also available. Contact SEL or FutureFLEX® Distributor
for additional information.
Maximum Reel Length tolerances are +5%.
All Reel Widths shown are approximate values only and measured from outsideof-flange to outside-of-flange.
If tube cable is re-spooled, the Minimum Drum Diameter of the new reel SHALL be
as shown to avoid damaging tube cable product
All Empty and Full Reel Weights shown are approximate values only.
TAX-type Tube Cable is a non-standard product. Use TLA-type Tube Cable as
alternative.
Communications Optical Fiber Backbone Cabling
27 13 23 - 37
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
TUBE DISTRIBUTION HARDWARE
P/N
DE06MDU
DESCRIPTION
Wall-mount, indoor tube distribution unit (TDU). Key-locked hinged door.
Modular design; wall-mount fiber termination units (FT24WFM &
FT48WFM) can be attached to front of unit. Four knockouts per
horizontal side and two knockouts per vertical side for tube cable entry.
Includes instructions, four (4) tube clip organizers (DETC008), knockout
bushings, and hose clamps for mounting tube cables.
Unit Dimensions: 16”H x 16”W x 4”D.
Weight: 18 lbs.
Capacity: 42 tubes.
DE12IDU
Wall-mount, indoor NEMA 12-rated tube distribution unit (TDU). Gray
color.
Hole punch & cable clamps required for mounting tube cables; not
included. Unit Dimensions: 24”H x 20”W x 7”D.
Weight: 35 lbs.
DE24IDU
Wall-mount, indoor NEMA 12-rated tube distribution unit (TDU). Gray
color.
Hole punch & cable clamps required for mounting tube cables; not
included. Unit Dimensions: 36”H x 30”W x 9”D.
Weight: 86 lbs.
DEDTTP
Capacity: 168 tubes.
Steel bracket and aluminum bar with plastic tube clip organizers for
organizing
individual tubes. All mounting hardware and instructions included.
Capacity: Twelve 7-tube cables.
DEDTTP2
Steel bracket and aluminum bar with plastic tube clip organizers for
organizing
individual tubes. All mounting hardware and instructions included.
DETC008
Capacity: Six 19-tube cables.
Black plastic tube clip organizer for up to 8 tubes. Mounts using screws
provided.
DETCTB
L-bracket for mounting up to two tube clip organizers (DETC008).
DE08MC2
Clear plastic push/pull quick release pneumatic tube coupling for 8mm OD
tube.
200 psi pressure rated. Ten couplings per pack.
Communications Optical Fiber Backbone Cabling
27 13 23 - 38
R2A Architecture
Costa Mesa, CA
09/28/2015
DE08MB
DE08MT
DE08MA
DE06MP
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
Brass push/pull quick release bulkhead pneumatic tube coupling for 8mm
OD
tube for panel mounting. 200 psi pressure rated. Ten bulkhead couplings
per pack.
Black plastic push/pull quick release pneumatic tube tee coupling for 8mm
OD tube. 200 psi pressure rated. Available individually.
Slate plastic push/pull quick release pneumatic tube cap for 8mm OD
tube. 200
psi pressure rated. Seals opening of unoccupied tube.
Recommended for indoor or outdoor application. Ten caps per
pack.
Orange plastic pneumatic tube plug for 6mm ID tube. Seals opening
of unoccupied tube. Recommended for indoor application. Ten plugs
per pack.
DE04HS1
Heat shrink end cap for 2- to 4-tube cables. Seals tube cable end to
prevent contamination entry. Heat gun or torch required for installation.
DE07HS1
Heat shrink end cap for 7-tube cables. Seals tube cable end to prevent
contamination entry. Heat gun or torch required for installation.
DE19HS1
Heat shrink end cap for 19-tube cables (except riser tube cable
TC19TRX).
Seals tube cable end to prevent contamination entry. Heat gun
or torch required for installation.
DE19HS2
Heat shrink end cap for 19-tube riser cable TC19TRX. Seals tube cable
end to prevent contamination entry. Heat gun or torch required for
installation.
DE02T0X
Tapered rubber insert for 2-tube (TC02TOX) cable installation using
Hubbell
Grip No. 074011251.
DE04T0D
Tapered rubber insert for 4-tube (TC04TOD) cable installation using
Hubbell
Grip No. 07401026.
DE5KCAP
Aluminum end cap sealing disc for unoccupied 2-, 4-, and 7-tube
Kellems®
Grips with Form 5 Size compression nut:
074011251 (TC02TOX)
07401026 (TC04TOD)
07401027 (TC07TOX)
07401028 (TC07NA3)
07401032 (TC07AOX & TC07LWS)
Communications Optical Fiber Backbone Cabling
27 13 23 - 39
R2A Architecture
Costa Mesa, CA
09/28/2015
DE6KCAP
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
Aluminum end cap sealing disc for unoccupied 7- and 19-tube Kellems®
Grips with Form 6 Size compression nut:
07401033 (TC07TAX & TC07TLA)
07401034 (TC19TOX & TC19TLW)
DE7KCAP
Aluminum end cap sealing disc for unoccupied 19-tube Kellems® Grips
with
Form 7 Size compression
nut: 074011032
DE00SPL
(TC19NA3)
Tube cable splice kit for 2- to 4-tube cables. Includes cold shrink splice
sleeve, mastic tape, water-blocking tape, four tube couplings (DE08MC2),
and
instructions.
DE01SPL
Tube cable splice kit for 7- tube cables. Includes cold shrink splice
sleeve,
mastic tape, water-blocking tape, seven tube couplings (DE08MC2), and
instructions.
DE02SPL
Tube cable splice kit for 19-tube cables. Includes cold shrink splice
sleeve,
mastic tape, water-blocking tape, nineteen tube couplings (DE08MC2),
and instructions.
FIBER AND FIBER BUNDLES
SEL PART NUMBER DESCRIPTION
FB02SX
“FB”
“FR”
“02, 04, etc.”
“SX”
“SR”
“M5”
“G53”
“G55”
“M6”
“R6”
Sumitomo Part Number (typical)
Fiber “Bundle”
Fiber “Ribbon”
Number of Individual Fibers
Single Mode Fiber
Radiation Hardened Single Mode Fiber
50 / 125 Multi-mode Fiber (Standard Grade; 1 Gigabit))
50 / 125 Multi-mode Fiber (Extended Grade; 10 Gigabit 300 m)
50 / 125 Multi-mode Fiber (Maximum Grade; 10 Gigabit 500 m)
62.5 / 125 Multi-mode Fiber (Standard Grade)
Radiation Hardened 62.5 / 125 Multi-mode Fiber
Communications Optical Fiber Backbone Cabling
27 13 23 - 40
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
FIBER BUNDLE TYPES & SIZES AVAILABLE
TYPE
SX
SR
M5
G53
G55
M6
R6
2-FIBER
FR02SX
FR02SR
FB02M5
FB02G53
FB02G55
FR02M6
FB02R6
4-FIBER
FB04SX
FB04SR
FB04M5
FB04G53
FB04G55
FB04M6
FB04R6
6-FIBER
FB06SX
FB06SR
FB06M5
FB06G53
FB06G55
FB06M6
FB06R6
12-FIBER
FB12SX
FB12SR
FB12M5
FB12G53
FB12G55
FB12M6
FB12R6
18-FIBER
FB18SX
FB18SR
FB18M5
FB18G53
FB18G55
FB18M6
FB18R6
SINGLE MODE FIBER & FIBER BUNDLE SPECIFICATIONS
PROPERTY
Fiber Bundle Jacket material
Fiber Bundle Jacket color
SPECIFICATION
Polyethylene Extruded Foam (PEF)
Yellow
8.3 micron
Core diameter
Cladding diameter
125 micron
Buffer / acrylate diameter
Maximum Dispersion at 1310 / 1550 nm
Index of Refraction
EIA/TIA-455-44 Test Procedure
Operation Temperature Range
(for Fiber Bundle Assembly)
Minimum Fiber Bundle Bend Radius
250 micron
< 3.2 / 18.0 ps/nm-km
1310 nm
1550 nm
-40° to +158°F
1.46
6
1.5”
Communications Optical Fiber Backbone Cabling
27 13 23 - 41
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
62.5 MICRON MULTI-MODE FIBER & FIBER BUNDLE SPECIFICATIONS
PROPERTY
Fiber Bundle Jacket material
Fiber Bundle Jacket color
SPECIFICATION
Polyethylene Extruded Foam (PEF)
Blue
Core diameter
62.5 micron
Cladding diameter
125 micron
Buffer / acrylate diameter
250 micron
Maximum Attenuation at 850 / 1300 nm
Minimum Bandwidth at 850 / 1300 nm
Min. Gigabit Ethernet Distance
< 3.5 / 1.5 dB/km
> 220 / 600 MHz-km
Std. Grade
Ext. Grade
Group Index of Refraction
EIA/TIA-455-44 Test Procedure
850
nm
850
nm
300 m
500 m
500 m
1000 m
1.496
1.491
850
nm
1300 nm
-40° to +158°F
Operation Temperature
Range (for Fiber Bundle
Assembly)
Minimum Fiber Bundle Bend Radius
1.5”
FIBER BUNDLE REEL DATA
Sumitomo
Part No.
FB02XX or
FR02XX
FB04XX
FB06XX
FB12XX
FB18XX
Fiber
Bundle
OD (mm)
2
Small
Reel
Length
(ft)
7000
Small
Reel
Weight
(lbs)
16.5
Small
Reel
HxW
(in)
16 x 11
Large
Reel
Length
(ft)
14000
Large
Reel
Weight
(lbs)
36
Large
Reel
HxW
(in)
20 x 12
2
2
3
3
7000
7000
3500
3500
16.5
16.5
19
19
16 x 11
16 x 11
16 x 11
16 x 11
14000
14000
7000
7000
36
36
41
41
20 x 12
20 x 12
20 x 12
20 x 12
Notes:
•
•
Cut lengths are also available. Contact SEL or FutureFLEX® Distributor
for additional information.
Standard reel length tolerances are +2% / -0%.
Communications Optical Fiber Backbone Cabling
27 13 23 - 42
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
ABF FIBER COLORS
2-Fiber Ribbon (Standard Ribbonized Coating)
1st Pos
2nd Pos
Blue
Orange
No Ripcord
2-Fiber Bundles (1 Nylon Sub-Unit)
1st Pos
2nd Pos
3rd Pos
Blue
Ripcord
Ripcord
4th Pos
Orange
5th Pos
Ripcord
6th Pos
Ripcord
7th Pos
Ripcord
4-Fiber Bundles (1 Nylon Sub-Unit)
1st Pos
2nd Pos
3rd Pos
Blue
Orange
Ripcord
4th Pos
Green
5th Pos
Brown
6th Pos
Ripcord
7th Pos
Ripcord
6-Fiber Bundles (1 Nylon Sub-Unit)
1st Pos
2nd Pos
3rd Pos
Blue
Orange
Green
4th Pos
Brown
5th Pos
Slate
6th Pos
Ripcord
7th Pos
White
12-Fiber Bundles (3 Nylon Sub-Units)
1st Pos
2nd Pos
3rd Pos
4th Pos
Blue
Orange
Ripcord
Green
Slate
White
Ripcord
Red
Yellow
Violet
Ripcord
Rose
5th Pos
Brown
Black
Aqua
6th Pos
Ripcord
Ripcord
Ripcord
7th Pos
Ripcord
Ripcord
Ripcord
5th Pos
Slate
Slate
Slate
6th Pos
Ripcord
Ripcord
Ripcord
7th Pos
Red
Yellow
Violet
18-Fiber Bundles (3 Nylon Sub-Units)
1st Pos
Blue
Blue
Blue
2nd Pos
Orange
Orange
Orange
3rd Pos
Green
Green
Green
4th Pos
Brown
Brown
Brown
Note: All Ripcords are Black Polyester
Communications Optical Fiber Backbone Cabling
27 13 23 - 43
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
FIBER TERMINATION HARDWARE
P/N
DESCRIPTION
FT24WFM
24-port wall-mount, indoor fiber termination unit (FTU). Key locked
maintenance door and magnetic user access door. Modular design; can be
attached to front of small tube distribution unit (TDU) (DE06MDU).
Unit Dimensions: 16”H x 16”W x 4”D.
Weight: 20 lbs.
Capacity: Four EIA standard 6-pack panels/four splice trays (not included).
48-port wall-mount, indoor fiber termination unit (FTU). Key locked
maintenance door and 1/4 turn latched access door. Modular design – can be
attached to front of small tube distribution unit (TDU) (DE06MDU).
FT48WFM
Unit Dimensions: 16”H x 16”W x 6”D.
Weight: 22 lbs.
Capacity: Eight EIA standard 6-pack panels/four splice trays (not included).
FT18RFS
Rack-mount fiber termination unit. Fits both 19” and 23” equipment racks. Low
profile. Includes one 24-fiber splice tray.
Unit dimensions: 1.75”H x 17”W x 12”D. Weight:
10 lbs.
Capacity: 18 fibers.
FT36RFS
Rack-mount fiber termination unit. Fits both 19” and 23” equipment racks.
Includes three 12-fiber splice trays.
Unit dimensions: 3.5”H x 17”W x 12”D. Weight:
13 lbs.
FT48RFS
Capacity: 36 fibers.
Rack-mount fiber termination unit. Fits both 19” and 23” equipment racks.
Includes four 12-fiber splice trays. Unit
dimensions: 7”H x 17”W x 12”D.
Weight: 20 lbs.
Capacity: 48 fibers.
FT72RFS
Rack-mount fiber termination unit. Fits both 19” and 23” equipment racks. 72fiber capacity. Includes six 12-fiber splice trays.
Unit dimensions: 10.5”H x 17”W x 12”D. Weight:
25 lbs.
Capacity: 72 fibers.
Communications Optical Fiber Backbone Cabling
27 13 23 - 44
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
FIBER TERMINATION HARDWARE (Continued)
P/N
DESCRIPTION
FT18RFT
Rack-mount fiber termination unit. Fits both 19” and 23” equipment racks. Low
profile. For field termination only.
Unit dimensions: 1.75”H x 17”W x 12”D.
Weight: 9 lbs.
Capacity: 18 fibers.
Rack-mount fiber termination unit. Fits both 19” and 23” equipment racks. For
field termination only.
FT36RFT
Unit dimensions: 3.5”H x 17”W x 12”D.
Weight: 11 lbs.
Capacity: 36 fibers.
Rack-mount fiber termination unit. Fits both 19” and 23” equipment racks. For
field termination only.
FT72RFT
Unit dimensions: 5.25”H x 17”W x 12”D.
Weight: 17 lbs.
Capacity: 72 fibers.
Rack-mount fiber termination unit. Fits both 19” and 23” equipment racks. For
field termination only.
FT144RFT
Unit dimensions: 10.5”H x 17”W x 12”D.
Weight: 24 lbs.
FTBLNK2
FT12FHL
FT18FHL
Capacity: 144 fibers.
EIA standard push/pull-mount blank plate panel for fiber termination units.
Twelve position splice tray for heat-shrink or mechanical splices. Aluminum
with clear plastic cover.
Eighteen position splice tray for standard fusion splices. Aluminum with clear
plastic cover.
FT24SPL
Adhesive mount splice tray holder for four splice trays.
FTFLD1
Field termination kit for 6-fiber bundle. Includes bushing, tube, and splitter with
six 3mm color-coded sub-units. Kevlar and outer PVC jacket bonded to splitter.
Includes instructions.
FTFLD3
Field termination kit for 18-fiber bundle. Includes bushing, tube, and splitter with
eighteen 3mm color-coded sub-units. Kevlar and outer PVC jacket bonded to
splitter. Includes instructions.
FTFLD06
Field termination kit for 6-fiber bundle. Includes splitter with six 900 micron
color-coded sub-units. Includes instructions.
FTFLD12
Field termination kit for 12-fiber bundle. Includes splitter with twelve 900 micron
clear sub-units. Includes instructions.
Communications Optical Fiber Backbone Cabling
27 13 23 - 45
R2A Architecture
Costa Mesa, CA
09/28/2015
FTFLD18
FT2MFB
FT3MFB
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
Field termination kit for 18-fiber bundle. Includes splitter with eighteen 900
micron color-coded sub-units. Includes instructions.
Red rubber tapered fiber bushing for 2-, 4-, or 6-fiber bundles (2mm OD). Seals
opening of occupied tube at termination locations. Available individually.
Black rubber tapered fiber bushing for 12- and 18-fiber bundles (3mm OD).
Seals opening of occupied tube at termination locations. Available individually.
Lynx2 CustomFit® Splice-On Connector
LYNX2 - Part Numbering Guide
LYNX2-AABBBCCCCC-DDDDDD
Part Number Section Options
AA
Connector Housing /
Body Type
LC
Options Description
LC Style Connector
BBB
Ferrule End-Face Finish
(will only be 2 characters
for PC)
UPC
PC
Physical Contact (For Multimode Fiber Only)
CCCCC
Fiber Type
(will range from 2 to 5
characters)
DDDDDD
Media Type
(will range from 3 to 6
characters)
SM
Single Mode Fiber
M6
Multimode Fiber 62.5µm
Ultra Physical Contact (For Singlemode Fiber Only)
Media of 250µm and
250900 Accommodates
900µm Coated Fiber
Media of 250µm & Upjackets with 8”
250FT8 Accommodates
Furcation Tubing (for SC only)
Media of 900µm Loose Buffer
900LT Accommodates
Coated Fiber
1.6
Accommodates Media of 1.6mm Cabled Fiber
2.0
Accommodates Media of 2.0mm Cabled Fiber
2.4
Accommodates Media of 2.4mm Cabled Fiber
3.0
Accommodates Media of 3.0mm Cabled Fiber
4.8
Accommodates Media of 4.8mm Cabled Fiber
Communications Optical Fiber Backbone Cabling
27 13 23 - 46
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
BLOWING EQUIPMENT, TOOLS, & MISCELLANEOUS ACCESSORIES
P/N
DESCRIPTION
Blowing equipment monthly lease. Includes transit case with blowing head and
payoff stand assembly and the following items:
•
BE200RM
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
One pressure regulator assembly with quick-release 8mm tubing adapter
(BEREG01)
One filter/regulator assembly with payoff counter
One motor rate control valve
One exhaust muffler
One ½” x 14” steel shaft
Two reel payoff cams (fit large and small fiber reels)
One fiber bundle guide assembly
One toolbox
Two red 2- to 6-fiber bundle (2mm OD) drive wheels (BE02DW)
Two black 12- or 18-fiber bundle (3mm OD) drive wheels (BE03DW)
One black 2- to 6-fiber bundle (2mm OD) air seal (BE02SL)
One black 12- or 18-fiber bundle (3mm OD) air seal (BE03SL)
One red 2- to 6-fiber bundle (2mm OD) blowing tip (BE2MFT)
One black 12- or 18-fiber bundle (3mm OD) blowing tip (BE3MFT)
One tubing cutter (BETC001)
Two tee couplings (DE08MT)
Two Allen wrenches (3/32” & 7/64”)
One bottle air motor cleaner fluid
Two 2-feet ¼ in. red tubing
One 6-feet ¼ in. white tubing
One 1-foot 8 mm clear tubing
Instructions included
BE200RY
Blowing equipment yearly lease. Contents same as BE200RM.
BE02DW
Replacement blowing head red fiber bundle drive wheels for installing 2- to 6fiber bundles (2mm OD). Available in pairs.
BE02SL
Replacement blowing head black fiber bundle drive wheels for installing 12- and
18-fiber bundles (3mm OD). Available in pairs.
Replacement blowing head black rubber air seal for installing 2- to 6-fiber
bundles (2mm OD). Available individually.
BE03SL
Replacement blowing head black rubber air seal for installing 12- and 18-fiber
bundles (3mm OD). Available individually.
BE2MFT
Replacement red, reusable, threaded, aluminum fiber bundle blowing tip for
installing 2- to 6-fiber bundles (2mm OD). Available individually.
BE3MFT
Replacement black, reusable, threaded, aluminum fiber bundle blowing tip for
installing 12- and 18-fiber bundles (3mm OD). Available individually.
BE03DW
Communications Optical Fiber Backbone Cabling
27 13 23 - 47
R2A Architecture
Costa Mesa, CA
09/28/2015
Relocatables 11, 12 & 13 Addendum No. 2
Saddleback College
South Orange County Community College District
BLOWING EQUIPMENT, TOOLS, & MISCELLANEOUS ACCESSORIES (Continued)
P/N
DESCRIPTION
BEPT001
Tube test kit. Includes bypass switch/valve, 0-200 psi portable hand-held
pressure gage, and one hundred (100) 5mm plastic beads. (Tube Test Kit is not
included in BE200RM or BE200RY.)
BEBB01P
Replacement 5mm plastic beads for obstruction testing. One hundred (100) per
pack.
BEREG01
Two-stage pressure regulator assembly. Includes quick release adapter with
¼” NPT (male and female) Type 15 connectors and ¼” NPT adapter to plastic
push/pull quick release pneumatic coupling for 8 mm OD tube.
BETC001
Tubing cutter for individual tubes.
BETC00B
Replacement blade for tubing cutter (BETC001). Available individually.
BETL01
Tube cable cutter for cutting up to 2-inch diameter tube cables. (Not to be used
to cut steel strength members.)
BETL02
Replacement blade for tube cable cutter (BETL01). Available individually.
STANDARD FIBER BUNDLE BLOWING DISTANCES
2-, 4- & 6-FIBER BUNDLES (2mm OD)
APPROX. DISTANCE
OSP MSO Aerial tube cable
1200 meters or 4000 feet
All other OSP & TRX tube cables
1000 meters or 3300 feet
TGX, TPX, & NA3 tube cables
600 meters or 1950 feet
12- & 18-FIBER BUNDLES (3mm OD)
APPROX. DISTANCE
OSP MSO Aerial tube cable
600 meters or 1950 feet
All other OSP & TRX tube cables
500 meters or 1650 feet
TGX, TPX & NA3 tube cables
300 meters or 1000 feet
Notes:
•
•
All distances given are approximate using one (1) Blowing Head.
Several factors heavily influence actual blowing distances:
1. The location, number, and severity of bends in a tube cable run,
2. The fiber bundle size installed (2mm OD or 3mm OD), and
3. The tube cable type
END OF APPENDIX 1
Communications Optical Fiber Backbone Cabling
27 13 23 - 48
Download