CONTENTS SECTION-1 SECTION-2 SECTION-3 Chapter-1 SECTION-4 Chapter-1 Chapter-2 Chapter-3 SECTION-5 Chapter-1 Chapter-2 Chapter-3 Chapter-4 Chapter-5 SECTION-6 Chapter-1 Chapter-2 Chapter-3 Chapter-4 Chapter-5 Chapter-6 Chapter-7 Chapter-8 Chapter-9 Chapter-10 Chapter-11 Chapter-12 SECTION-7 SECTION-8 SECTION-9 SECTION-10 Chapter-1 Chapter-2 Chapter-3 Chapter-4 Chapter-5 TECHNICAL SPECIFICATIONS BID DOCUMENT NO.: REC-145 FOR 66kV GIS SUBSTATION MATERIAL GENERAL GENERAL TECHNICAL REQUIREMENTS TECHNICAL SPECIFICATIONS OF POWER TRANSFORMER 25/31.5 MVA, 66/11kV Power Transformer TECHNICAL SPECIFICATIONS OF SWITCH-GEAR 72.5 KV GIS 198, 120, 30 & 9 KV Gapless Surge Arrestor 11 KV 15 Panel Board 1250 Amp TECHNICAL SPECIFICATIONS OF PROTECTIVE GEAR 245, 72.5, & 12kV NCT 245 &72.5 kV CVT 220 kV & 66 kV C& R PANELS for substations having substation automation system Sub-Station Automation System Inter-utility Metering System TECHNICAL SPECIFICATION OF ELEC. AND MECH. AUX. 415 V ACDB 220V and 48V VRLA DC Battery 220V DC Battery charger DCDB Fire fighting equipments 66KV XLPE Cable 11kV XLPE Cable LT Power Cable Air Conditinging System 200KVA 11/0.4KV Station T/F 13.608MVAR 11kV Automatic Capacitor Bank Armoured Control Cable SWITCHYARD ERECTION AND INSTALLATION STEEL STRUCTURE CIVIL WORKS PLCC Equipment & Protection Coupler Line Traps Coupling Device 48 V Battery Charger HF Cable 150 Ohm (Balanced) LIST OF DRAWINGS SECTION-1 (GENERAL) 1.0 1.1 66kV GIS SECTOR-21-D, Faridabad The scope of this Project is to establish 66kV Gas Insulated Substation (GIS) at Sector-21- D, Faridabad with complete automation and civil work configuration. The intent of this specification covers the following: The specification includes the design, engineering, manufacture, fabrication, testing at 1.2 manufacturers works, delivery, unloading at site, storage, erection, testing and commissioning at site of the complete 66kV switchyard including: Indoor 66kV SF6 gas insulated metal enclosed switchgear (GIS), Two 25/31.5MVA, 66/11kV Power Transformer, one 200KVA 11/0.433kV LT Transformers, 11kV VCB Panels, 11kV Automated Switched Capacitor banks, Fire Extinguishers, Testing equipment’s, associated civil works including soil investigation, internal roads, drains, necessary buildings etc., 66kV XLPE copper Power Cables, 11kV XLPE Aluminium Power Cables, Indoor & outdoor End Termination Boxes, Substation Automation with Relay & Protection, Communication (Converter) equipments and other electrical and mechanical auxiliary systems on turnkey basis. Bidder shall also ensure GIS compatibility for line feeder and provide the ancillary equipment required for the same. For connecting 66kV GIS with primary of transformers, lines bidder will use XLPE copper Power Cables along with cable termination for both end and flexible ACSR zebra conductor, structures etc. as per GELO. For connecting 11kV side of 66/11kV Transformer bidder will use 11kV XLPE Aluminium Power Cables and as per GELO drawing no. HGD-3C/579. 1.3. The supply will include all supporting structures, auxiliary equipments, mechanical linkages, SF6 gas piping, auxiliary circuits wiring, interlocking devices, current and voltage transformers, cable end boxes and SF6 bus ducts. 1.4. Support structure required for installation and commissioning of above equipments shall be provided by the bidder/manufacturer. 1.5. It is the intent of this specification to describe primary features, materials, and design & performancerequirements and to establish minimum standards for the work. 1.6. The specification is not intended to specify the complete details of various practices of manufactures/ bidders. But to specify the requirements with regard to performance, durability and satisfactory operation under the specified site conditions. 1.7. Whenever a material or article is specified or described by the name of a particular brand, manufacturer or trade mark, the specific item shall be understood as establishing type, function and quality desired. Products of other manufactures may also be considered, provided sufficient information is furnished so as to enable the purchaser to determine that the products are equivalent to those named. 1.8. Any deviation or variation from the scope requirement and/or intent of this specification shall be clearly mentioned under Deviation Schedule of the Bid Proposal Sheets irrespective of the fact that such deviation/variation may be standard practice or a possible interpretation of the specification by the bidder. Except for the deviation/variations which are accepted by the purchaser before the award of the contract, it will be the responsibility of the bidder to fully meet the intent and the requirements of the specification within the quoted price. No other departure from the specification except for the declared deviation indicated by the bidder in his proposal shall be considered. The interpretation of the purchaser in respect of the scope, details and services to be performed by the bidder shall be binding, unless specifically clarified otherwise by the purchaser in writing before the award of contract. 1.9. The drawings enclosed with the specification are preliminary drawings for bidding purpose only and subject to changes that may be necessary during detailed engineering after award, keeping the basic parameters as specified. 1.10 1.10.1 Scope of Work Design, Engineering, manufacture, testing, supply on CIP basis, transportation to site including port and custom clearance if required, insurance, storage, testing and commissioning of following items:- a) 66kV System The 72.5kV SF6 Gas Insulated Switchgear for three phase system shall have double bus bar arrangement with 7 bays (2 No. 25/31.5MVA Transformer, 1 No. bus-coupler and 4 nos. feeder bays. Space for 3 Nos. future bays (1 No. 66/11kV T/F and 2No. line bays) shall be kept in GIS hall for adding future bays and jointing plugs required for connecting GIS of different makes. The SF6 Gas Insulated Switchgear rated for 66kV, 3-phase, 50Hz, 31.5kA fault level shall be of the indoor metal-enclosed type, comprising of following items. Unit Qty 1 72.5kV, 1250A, single 3 – φ or three 1 –φ, SF6 gas Set 2 insulated, metal enclosed bus bars arrangement, consisting of 1250A single 3 – φ or three 1 –φ SF6 gas insulated switchgears, each Bus Bar comprising of :Bus bar enclosures running through the length of the i) switchgear to interconnect each of the circuit breaker bay modules in double main bus system. ii) Three, 2-core, single phase voltage transformers/ PTs. iii) 1250A, One 3 – φ or three 1 – φ, single pole, group operated isolator/disconnector and one, 3 – φ or three 1 – φ, single pole, group operated earthing switch with manual and motor driven operating mechanisms. iv) 1250A, One high speed fault make 3 – φ or three 1 – φ, single pole, group operated earthing switches, complete with manual and motor driven operating mechanisms. v) Each GIS compartment with gas monitoring device, pressure switch etc. as required. vi) Terminal boxes/ Local Control Cubicle. vii) Interconnecting wiring/ piping. viii) Grounding, support structures and platforms. 2 1 72.5kV, 800A, single 3 – φ or three 1 –φ, Bus coupler Set bay module, consisting of 800A single 3 – φ or three 1 –φ SF6 gas insulated switchgears, comprising of: i) 800A, One 3 – φ or three 1 –φ, SF6 gas insulated circuit breaker, complete with operating mechanism. ii) Three,3-core,single phase current transformers (600-300-150/ 1-1-1A) iii) Two sets of isolator/disconnector switches each of 800A, One 3 – φ or three 1 – φ, single pole, group operated isolator/disconnector switches each with 3 – φ or three 1 – φ, single pole, group operated earthing switch and complete with manual and motor driven operating mechanisms. iv) Each GIS compartment with gas monitoring device, pressure switch etc. as required. v) Terminal boxes/ Local Control Cubicle. vi) Interconnecting wiring/ piping. vii) Grounding, support structures and platforms. 3 i) ii) iii) iv) v) vi) vii) viii) ix) x) 4. i) ii) iii) iv) v) 72.5kV, 800A, single 3 – φ or three 1 –φ, Transmission SET line feeder circuit breaker bay modules, consisting of 800A single 3 – φ or three 1 –φ SF6 gas insulated switchgears, each comprising of:800A, One 3 – φ or three 1 –φ, SF6 gas insulated circuit breaker, complete with operating mechanism for outgoing feeder. Three, 66kV LAs Three, 3-core, single phase current transformers (600-300-150/1-1-1A) 800A, One 3 – φ or three 1 – φ, single pole, group operated isolator/disconnector without earthing switch, complete with manual and motor driven operating mechanisms. 800A, One 3 – φ or three 1 – φ, single pole, group operated isolator/disconnector with one, 3 – φ or three 1 – φ, single pole, group operated earthing switch, complete with manual and motor driven operating mechanisms. 800A, One 3 – φ or three 1 – φ, single pole, group operated isolator/disconnector with one normal and one high speed fault make 3 – φ or three 1 – φ, single pole, group operated earthing switches, complete with manual and motor driven operating mechanisms. Each GIS compartment with gas monitoring device, pressure switch etc. as required. Terminal boxes/ Local Control Cubicle. Interconnecting wiring/ piping. Grounding, support structures and platforms. 72.5kV, 400A, single 3 – φ or three 1 –φ, Transformer Set feeder circuit breaker bay modules, consisting of 400A single 3 – φ or three 1 –φ SF6 gas insulated switchgears, for 66/11kV transformer, each comprising of: One 3 – φ or three 1 – φ, SF6 gas insulated circuit breaker, complete with operating mechanism for incomer bay from 66/11kV transformer. Three, 3-core, single phase current transformers (300-150/11-1A). 400A, One 3 – φ or three 1 – φ, single pole, group operated isolator/disconnector without earthing switch, complete with manual and motor driven operating mechanisms. 400A, One 3 – φ or three 1 – φ, single pole, group operated isolator/disconnector with one, 3 – φ or three 1 – φ, single pole, group operated earthing switch, complete with manual and motor driven operating mechanisms. 400A, One 3 – φ or three 1 – φ, single pole, group operated isolator/disconnector with two earthing switches each 4 2 c) d) e) f) g) h) i) j) k) l) m) n) o) comprising of one 3 – φ or three 1 – φ, single pole, group operated earthing switches complete with manual and motor driven operating mechanisms. vi) Each GIS compartment with gas monitoring device, pressure switch etc. as required. vii) Local Control Cubicle. viii) Interconnecting wiring/ piping. ix) Grounding, support structures and platforms. 5 66kV XLPE copper Cable 4X1C (800mm2) along with one no. spare cablecoated with fire retardant Paint for each Line feeder bay with GIS with termination kit for both end for all four cables. 6 66kV XLPE copper Cable 4X1C (400mm2) along with one no. spare cable coated with fire retardant Paint for connecting 66kV side of 66/11kV transformer with GIS with GIS with termination kit for both end for all four cables. 2x25/31.5 MVA, 66/11 kV T/Fs along with all accessories and mandatory spares. All type of Neutral CT’s, Surge Arrestors, CVTs for line with their terminal connectors & mandatory spares. Lightning protection. Complete Sub-Station automation including Hardware & Software. Complete 66kV C&R Panels and 11 kV VCB Panels with SEMs on each T/F I/C VCB Panel. Associated mechanical & electrical auxiliaries & EOT cranes & mechanical operated crane etc. 1.1kV grade power & Armoured (FRLS) control copper cables along with complete accessories for switchgear, metering and protection equipments Substation structures for sub-station towers & beams and equipment structures. Insulator strings, hardware clamps and connectors, junction box, copper lug, glands & PVC ferrules for control cabling, fibrecleats, aluminum clamps, bolts, nuts, washers etc. for fixing control cables in trenches, galvanized iron trays & clamps, ACSR conductor, GS earth wire, spares. Cables supporting angles/channels, buried cable trenches & outdoor trenches with channels with trench covers. C-wedge connector & equipment interconnections shall be suitable for Single/Triple Zebra Conductor. Complete lighting and illumination of the switchyard, GIS cum Control room Building, receptacles etc. as per technical specification/BOM. Air Conditioning system as per specification in Section-6, Chapter-12 & Ventilation system for GIS hall-AHU. The requirement of ventilation system shall be as per Annexure V and separate room for air handling unit to be provided adjacent/inside (as per space availability) GIS hall however their design will be in scope of bidder as per requirement. (i) The multi- level building should accommodate 66kV GIS Hall (at ground floor) and control room (at first floor) along with intermediate floor. The height of intermediate floor should be provided enough, for free movement of man power. (ii) The entry of power cable should be made independently transformer wise, to be provided in multilayer type trays for proper/easy maintenance purpose. (iii) The detailed design/drawing of multilevel control room building for proposed substation will be submitted by firm for approval. The tentative floor wise plan for multilevel GIS building is as under:- p) q) r) s) t) u) v) w) x) y) z) Grounding system of the substation i.e. complete Earth mat lying will be designed/quoted for soil resistivity of 50Ωm. In case soil resistivity is more than 50Ωm then the earth mat will be designed for actual soil resistivity. The payment of extra material to be used for earth mat shall be made on pro rata basis & equipotential mat beneath the floor of GIS building as per IEEE/tech. specification/IS./IEC etc. Complete fire - fighting equipment. One set of 220V 100 AH DC battery with battery charger & DCDB along with associated accessories. 415V LT A.C. DB 300A along with associated accessories. 1X200 KVA 11/0.4 kV station T/Fs for auxiliary supplies. Providing 2 No. 13.608 MVAR 11 kV Automatically Switched Capacitor Bank along with allied equipment (1 no. capacitor bank for each 66/11kV T/F is to be provided) Cable support structure for 66kV XLPE cable for each bay shall be of Galvanized steel and shall be designed along with civil foundation by the successful bidder after award of the contract. The supply, installation, erection, testing and commissioning of PLCC equipment for this end will be in scope of bidder. The shifting of Wave Trap/CVT/protection coupler/PLCC terminal etc. if required for matching purpose will be in scope of bidder. Mandatory Spares, Special Equipments for testing and maintenance. Recommended spare parts, maintenance tools and other equipment necessary for maintenance purposes for fifteen years of trouble free service other than those specified as mandatory spares. Any other equipment/material required to complete the specified scope. 1.10.2 Civil Works a) Foundation for S/Stn main gantry/steel structures and equipments as per drawings attached. b) Foundation for 2 No. 25/31.5MVA transformer including associated radiator. Complete in all respects as per approved T/F, substation transformer, 2 No. 13.608MVAR 33kV Capacitor Bank with allied equipments complete as per technical specifications. The successful bidder shall submit foundation design & drawings as per approved equipment drawing for approval before execution. c) Foundation for lighting poles, junction box, panels & control cubicles of equipments (wherever required) without any extra cost to HVPNL. d) RCC outdoor cable trenches along with RCC covers, cable racks, trench culverts crossings the road, drainage system including drainage pipes, manholes with RCC covers whenever required, installation of pump, cable etc. complete. The design/drawings shall be evolved by the successful bidder and got approved from employer before execution. e) Laying of roads leading to switch yard, switch house & GIS buildings (as applicable) from HUDA/PWD/village road including earth filling for road and berms, if required and PCC in front, rear or side (as applicable) of the switch house building for parking as per drawings attached. The above shall be as per GELO/CLO/site requirement. f) Provision of one/two pipe(s) culvert of suitable dia. as per technical specifications on approach road leading to switch yard & switch house/GIS building from HUDA/PWD/village road (as per site requirement). g) Fencing & Boundary wall for the S/Stn. along with main entrance gates as per drawings attached. h) Site surfacing including leveling, dressing, compaction, laying of lean concrete/PCC in areas under scope of contract/wherever required in the switchyard area as per site requirement. i) The weed growth/ tree cutting shall be responsibility of the contractor. Contractor may note that purchaser shall not pay any compensation for any loss or damage to the properties or for tree cutting due to contractor’s works. j) Construction of Control room building as per HVPNL drawings. For GIS building, the successful bidder has to develop architectural & structural/foundation drawings and shall submit the same to HVPNL before execution. Both the building shall include indoor cable trenches, all services such as lighting, sanitary, drainage, RW pipes, collection tank, soakage pit, etc. Collection tank & soakage pit shall be required if HUDA’s sewerage system is not in place. k) The GIS halls dimensions and functional details given in GELO are minimum since the detailed engineering is in scope of successful bidder, nothing extra on account of increased area/size of GIS halls shall be paid. l) Cutting/Filling of earth to required depth including leveling, dressing, compaction etc. in S/Stn. including switchyard and roads wherever required to achieve required formation level as decided by employer. Construction of one no. rain harvesting system (rechargeable bore/well) for entire subm) station including control room/GIS buildings and yard for collection of water from switch house/GIS buildings and yard. The disposal/drainage scheme for draining rain water shall include open drains, RCC pipes, inspection chambers, manholes, RCC covers where ever required, settlement tank, sum pit-cum-pump chamber with pump motor, GI Suction delivery pipes, electric control panels, cables etc. complete in all respects. The bidder shall evolve design and drawing for rechargeable well, settlement tank, sump pitcum-pump chamber and drainage scheme and got the same approved before execution. n) All civil works associated with construction of buildings, indoor/outdoor equipment/tower foundations, erection of EOT crane, indoor/outdoor cable trenches, drains, services, anti fire wall, rechargeable well, sump pit-cum pump chamber, settlement tank, septic tanks etc. are in the scope of successful bidder. 1.10.3 The Switchgear shall be complete with all necessary terminal boxes, SF6 gas filling, interconnecting power and control wiring, pressure switches, grounding connections, gas monitoring equipment and piping, support structures etc. 1.10.4 The work to be done under this specification comprises the provision of all labour, plant, equipment and material and the performance of all work necessary for the complete installation and commissioning of switchyard on turnkey basis. It is hereby required that the contractor should provide all apparatus, appliances, material and labour etc. not specifically mentioned or included, but are necessary to complete the entire work or any portion of the work in compliance with the requirements implied in this specification is deemed to be included in the scope of contractor. 1.10.5 The contractor shall be fully responsible for:Complete project management i) Design and engineering of entire work of (GIS+AIS) Substation including supply of ii) complete documentation i.e. design drawings, design memorandums, O&M manuals for all works which shall be identified at the time of contract. Insulation coordination including studies for selection of metal oxide surge arrestors, iii) parameters, location for complete switchyard. The specifications and quantity provided else where are indicative only. The final quantities shall be worked out during detailed engineering of insulation coordination. The quality of all materials and workmanship of the complete work. iv) The Contractor shall be responsible for detailed design and engineering of overall v) system, sub-systems, elements, system facilities, equipments, auxiliary services, etc. It shall include proper definition and execution of all interfaces with systems, equipment, material and services of purchaser for proper and correct design, performance and operation of the project. Contractor shall provide complete engineering data, drawings, reports, manuals, etc. vi) for purchaser’s review, approval and records. vii) The scope shall also include the design and engineering as per details elaborated elsewhere in this specification. viii) The Contractor shall carry out earth resistivity measurements at the substation site(s) (based on four electrode method). For all structural works, the contractor shall prepare all fabrication drawings. ix) The Contractor shall be responsible for design, engineering, manufacture, testing & x) inspection at manufacturer’s works, supply transportation, insurance, delivery at site, unloading, storage, in plant transportation at site, complete erection & supervision, site testing & inspection, and successful commissioning of all equipment and material listed at ‘Bill of Quantities’ enclosed as Annexure-A1(ii) to E1(ii) of this section, detailed elsewhere in specification and as shown on the tender drawings. Any item though not specifically mentioned, but is required to complete the project works in all respects for its safe, reliable, efficient and trouble free operation shall also be taken to be included, and the same shall be supplied and erected by the Contractor without extra cost unless it is explicitly excluded elsewhere in the specifications. All consumables, wastages and damages shall be to the account of contractor. xi) xii) The contractor shall construct, erect and install all equipment and material required for completion of substation(s) covered under the project. He shall be responsible for provision of all labor, tools and tackles and supervisory staff for safe, reliable, proper and correct erection of all equipment required for successful completion of the substation(s). xiii) The tools and plant shall include, but not limited to, special hoisting equipment, cranes, slings, consumables and all other articles and supplies as required. xiv) The contractor shall ensure periodic cleaning of work site and removal of all waste material, packaging material, surplus earth and left-over and their proper disposal. xv) The contractor has to employ suitable manpower and supervision personnel. The contractor is solely and fully responsible for the safety of personnel and materials. Any damages to the existing facilities shall be made good by the contractor at no extra cost to the purchaser. The contractor shall coordinate with site personnel for arranging shut down for interconnection with the existing systems, if required. xvi) The contractor shall be responsible for the overall management and supervision of works. He shall experiences, skilled, knowledgeable and competent personnel for all phase of the project, so as to provide the purchaser with a high quality system. xvii) The contractor’s supervisory personnel shall provide operation and maintenance assistance during the warranty period. xviii) A Project execution schedule called Master Network (MNW) in the form of PERT chart/network shall be prepared by the contractor for purchaser’s approval. The MNW shall identify milestones of key event for each work/ component in the areas of engineering, procurement, manufacturer, dispatch, erection and commissioning. It shall indicate interfaces and inputs required to be given by Purchaser. xix) The scope includes testing and commissioning of all equipment, subsystems and systems of the project and putting them into successful commercial operation. The scope shall include but not limited to the requirements given elsewhere in the specification. xx) The contractor shall be responsible to provide all necessary testing and commissioning personnel, tools and plant, testing equipment, etc. All expenses for carrying out the routine tests as specified in relevant standard shall be to contractor’s account. However the expenses w.r.t. purchaser/purchaser’s representative for witnessing these tests which contractor shall take into account shall be as follows:For Inspections/tests to be carried out for equipment offered from within a) purchaser’s country. All tour expenses shall be borne by purchaser. For inspections/tests to be carried out for equipment offered from outside b) purchaser’s country:It is envisaged that inspection/testing of all such equipment shall be witnessed. Each inspection shall be carried out by a team of 3 to 4 engineers nominated by the purchaser. Their To & Fro travel expenditure from purchaser’s country to the place of inspection/testing shall be borne by the bidder including all boarding and lodging charges. xxii) The contractor shall identify all interface issues with purchaser and other agencies, and shall be responsible for such interfacing, coordination and exchange of all necessary information. a) The approach road up to the GIS substation area shall be provided by the Purchaser. All internal roads (if any) shall have to be constructed by the contractor. b) Bidder will solely be responsible for obtaining statuary clearances for providing temporary connections for construction of power and water. The contractor shall arrange for necessary meters etc. and shall pay applicable energy and water charges as per applicable rates to the concerned authorities. xxiii) Contractor shall make his own necessary arrangements for the following and for those listed anywhere else in this specification. a) Construction power supply at all work areas. Provision of water supply arrangement. b) c) Construction office and store (open and covered) Construction workshop and material/field testing laboratory d) e) Boarding & lodging arrangement for their personnel. f) Fire protection and security arrangements during construction stage. g) Any other requirements of the Haryana Government and as per the purchaser’s rules, regulations and practices. h) the contractor shall make his own necessary arrangements like diesel generator sets, water etc., at his own cost so that progress of work is not affected and Employer shall in no case be responsible for any delay in works because of non-availability of power, water etc. i) Provide labour license as per Govt. Rules. 1.10.6 SF6 gas filling & evacuating plant with gas cylinders shall be supplied by the bidder as per Bid Price Schedules and shall be utilized by the bidder for commissioning. The contractor would be required to hand over the same in good working condition with enough gas for one charging of complete system with 20% extra gas as indicated in mandatory spares of relevant Bid Price Schedule. EOT crane shall be provided in 66KV GIS building for GIS equipment handling during 1.10.7 installation, commissioning and maintenance etc. Crane lifting capacity shall be 1.10.8 1.10.9 2.0 3.0 4.0 adequate to handle the heaviest package of GIS but shall not be less than 5 tonnes for 66kV System. The crane shall also be provided with speed drive mechanism. Further, the mechanical operated crane for uplifting the equipments from ground floor to first floor should be provided adjacent to multi storey building &adequate to handle the heaviest equipment (lying at first floor i.e. control room) but shall not be less than 2 tonnes. The same should be provided as per site requirement for handling during maintenance (i.e. to & fro of equipments from outside the ground floor to first floor) as per relevant IS & confirming to safety norms. Supply, erection, testing and commissioning of all items of work required to make the 66kV bays fully functional. Bidder shall submit along with the bid and also during detailed engineering the computation and calculation for enclosure loss and details about the measures taken to reduce losses so as to limit the temperature rise of enclosure as per the requirement of clause 4.37 of section: GIS. Mandatory Maintenance Equipment The Bidder shall include in his scope mandatory maintenance equipment as specified The prices of these shall be indicated in respective schedules. These would be considered in bid evaluation. A List of mandatory maintenance equipment is given at Annexure-A-1 to G-1, of this section. The Owner reserves the right to buy any or all of these. The Bidder shall furnish the itemized and total prices for this equipment in the offer. In Compliance with the requirements of Bid documents, the prices for mandatory maintenance equipment must be given separately, and shall be used for bid evaluation purposes. All mandatory maintenance equipment shall be delivered at site. Commissioning spares The bidder shall supply spares, which he expects to consume during installation, testing and commissioning of system. The quantity of these spares shall be decided based on his previous experience, such that site works shall not be hampered due to non-availability of these spares. Bidder shall submit a complete list of such spares along with the bid, the cost of which shall be deemed to have been included in the lump sum proposal price of the package. The unused commissioning spares may be left at the site for use by the purchaser, if so agreed at a cost to be negotiated. No mandatory or recommended spares will be used during the commissioning of the equipment/plant before take over by the purchaser. Recommended spares In addition to the mandatory maintenance equipment, the bidder shall also provide a list of recommended spares giving unit prices and total prices for 5 years of normal operation of equipment in the relevant schedule of the BPS. The Purchaser reserves the right to buy any or all the recommended spares. The recommended spares parts shall be delivered at the site(s). The list of recommended spares to be furnished by the bidder should also contain the following: a) b) 4.1 Population of each item installed along with reference drawing number. Service life expectancy of each item. c) Offer validity period. Price of recommended spares will not be used for evaluation of bids. The price of these spares will remain valid for a period of not less than 120 days after the date on which the validity of main bid expires. The prices of any recommended spares shall be subject to review by the purchaser and shall be finalized after mutual discussions. 5.0 6.0 6.1 7.0 8.0 9.0 9.1 9.2 10.0 11.0 Tools & Tackles The Bidder shall also supply at each substation site one set of all special tool and tackles, etc. which are required by the purchaser’s maintenance staff to maintain the works successfully at no extra cost. The list of such tools and tackles shall be enclosed with the offer. Training of purchaser’s Personnel (a) Training at Manufacturer’s works: The successful bidder shall arrange for training of 2 persons of the employer at the manufacturer’s works of GIS for 5 working days in Design, manufacturing and testing of GIS being supplied. The traveling, lodging, boarding & visa arrangement including all expenses shall be made by the successful bidder for the above training. (b) Training at Site: The successful bidder shall arrange for training of 5 persons including operating field staff of Employer for five working days at each GIS sub-station in operation and maintenance of GIS. The expenses for training including traveling, lodging, boarding of the trainer shall be borne by the successful bidder. The detailed design shall be submitted for approval by the employer, during detailed engineering. SCHEDULE OF QUANTITIES The detailed description of various items/equipment and civil works are indicated at Annexure – I to V & Schedule A1,B1,C1, D1, E1, F1, G1. The bill of quantity of major equipment is also indicated and wherever the quantities are not indicated the bidder is required to compute the quantity. Bidder is required to indicate unit rate and total price of the items under a particular head in bid proposal sheets. Bidder should include all such items in the bid proposal sheets, which may not be specifically mentioned but are essential for the execution of the contract. SOIL DATA The earth resistivity for 66 kV Substation Sector-21-D, Faridabad shall be ascertained by the bidder himself. Physical and Other Parameters Location of the Substations The location of the substations is in Faridabad for Sector 21-D Faridabad. Meteorological data The meteorological data of the substation is indicated at Annexure-III. However, for design purpose, ambient temperature should be considered as 50° C. Basic Reference Drawings For 66/11kV voltage level, Double bus-switching scheme (GIS) layout arrangement shall be used. The Single line diagram and layout arrangements are attached with bidding documents Annexure-IV, which shall be further engineered by the bidder. The dimensions of GIS rooms are indicative; Bidder may increase the dimensions of building as per requirement (with the provision of service bay). DRAWING 1. The bidder shall maintain inter equipment distances, bay length, bay width etc in accordance with the enclosed general/electrical layouts of the substation, while doing so the bidder will ensure that the statutory electrical clearances required for substation are maintained. (Annexure-IV). 2. The drawing enclosed gives the basic scheme, layout of substation, substation buildings, associated service etc. In case of any discrepancy between the drawing and text of specification the bidder is advised to get these clarified before submission of bid. No claim what-so-ever on this score shall be entertained after award of contract. 3. The bidder shall adopt HVPNL design of galvanized steel structure for tower, beam and equipment supporting structures for /66/11kV S/Stn. 12.0 In case of any discrepancy between the drawings and text of specification, the requirements of text shall prevail in general. However, the Bidder is advised to get these clarified from Employer. In case of any discrepancy between Section-GTR and individual sections for various equipments, requirement of individual equipment section shall prevail. Specific Requirement The bidder shall be responsible for safety of human and equipment during the working. It will be the responsibility of the Contractor to co-ordinate and obtain Electrical Inspector’s clearance before commissioning. Any additional items, modification due to observation of such statutory authorities shall be provided by the Contractor at no extra cost to the Employer. Notes: 13.0 a) The bidder or his authorized representative should visit the site of works and its surroundings to obtain himself at his responsibility and expenses, all information regarding general site characteristics, accessibility, infrastructure details and factual position in respect of scope of work viz-a-viz GELO drg. attached with the bid document. Any alteration/addition envisage in the document must be got clarified before submission of the bid. b) No extra payment shall be made on account of any change in the layout drgs. required for providing DSLP as per Rezvik method. ANNEXURE-I 66kV SUB-STATION Sr. No. Name of S/Stn. 1 66kV GIS Sector21-D, Faridabad Scope of Work The specification includes the design, engineering, manufacture, fabrication, testing at manufacturers works, delivery, unloading at site, storage, erection, testing and commissioning at site of the complete 66kV switchyard including: Indoor 66kV SF6 gas insulated metal enclosed switchgear (GIS), Two 25/31.5MVA, 66/11kV Power Transformer, one 200KVA 11/0.433kV LT Transformers, 11kV VCB Panels, 11kV Automated Switched Capacitor banks, Fire Extinguishers, Testing equipment’s, associated civil works including soil investigation, internal roads, drains, necessary buildings etc., 66kV XLPE copper Power Cables, 11kV XLPE Aluminium Power Cables, Indoor & outdoor End Termination Boxes, Substation Automation with Relay & Protection, Communication (Converter) equipments and other electrical and mechanical auxiliary systems on turnkey basis. Bidder shall also ensure GIS compatibility for line feeder and provide the ancillary equipment required for the same. For connecting 66kV GIS with primary of transformers, lines bidder will use XLPE copper Power Cables along with cable termination for both end and flexible ACSR zebra conductor, structures etc. as per GELO. For connecting 11kV side of 66/11kV Transformer bidder will use 11kV XLPE Aluminium Power Cables and as per GELO drawing no. HGD-3C/579. For detailed BOQ for S.no.1 refer Annexures A1,B1,C1, D1, E1, F1, G1 Scheme Double bus bar (66 kV, with Bus coupler) ANNEXURE-II LOCATION OF SUB-STATIONS Sr. No. 1. Name of Substation 66kV GIS S/Stn.Sector-21-D, Faridabad Nearest Rail Head Faridabad ANNEXURE-III METEOROLOGICAL DATA 1.1 Equipment to be supplied against this specification shall be suitable for satisfactory continuous operation under the following tropical conditions: i) Location ii) Max. Ambient air temp. (deg. C) 50 iii) Min ambient air temp. -2.5 iv) Daily average air temp. (deg. C) 35 v) Average no. of Thunder storm days per Annum 45 vi) Maximum Relative Humidity (%) 100 vii) Minimum Relative Humidity (%) 26 viii) Average annual rain fall (mm) 900 ix) Max. wind pressure (kg/sq m) 195 x) xi) Max. altitude above mean sea level (meters) Isoceraunic level (days/year) 1000 45 xii) Seismic level (horizontal acceleration) Average no. of rainy days per Annum 0.3 g xiii) In the state of Haryana (deg. C) 120 NOTE: Moderately hot and humid tropical climate conductive to rust and fungus growth. The climate conditions are also prone to wide variations in ambient condition. Smoke is also present in the atmosphere. Heavy lightening also occurs during June to October. ANNEXURE-IV Sr. No. 1. Name of Substation 66kV GIS S/Stn.Sector-21-D, Faridabad GELO DRAWING NO HGD-3C/579 ANNEXTURE V VENTILATION SYSTEM FOR GIS HALL Each GIS hall shall have an independent ventilation system. Each ventilation system shall consist of two 100% capacity systems, one operating and one standby. To ensure that the air being supplied to the GIS hall is free from dust particles, a minimum two stage dust filtration process shall be supplied. This shall consist of at least the following: 1) Pre Filters: To remove dust particles down to 10 micron in size with at least 95% efficiency. 2) Fine Filters: To remove dust particles down to 5 microns in size with at least 99% efficiency. All the filters shall be panel type. Easy access should be available to the filters for replacement/ cleaning. The ventilation of the GIS hall shall be of a positive pressure type with minimum 4 air changes per hour. The pressure inside the GIS hall shall be maintained 5 mm of Water above the atmospheric pressure. Fresh outdoor air shall be filtered before being blown into the GIS hall by the air fans to avoid dust accumulation on components present in the GIS hall. Each GIS hall shall be provided with motorized exhaust dampers with local control. EQUIPMENTS/MATERIALSTO BE SUPPLIED AND ERECTED FOR 66 KV GIS SUB-STATION Sector 21- D, Faridabad a) Annexure-A1 66kV System The 72.5kV SF6 Gas Insulated Switchgear for three phase system shall have double bus bar arrangement with 7 bays (2 No. 25/31.5MVA Transformer, 1 No. bus-coupler and 4 nos. feeder bays. Space for 3 No. future bays (1 No. 66/11kV T/F and 2No. line bays) shall be kept in GIS hall for adding future bays and jointing plugs required for connecting GIS of different makes. The SF6 Gas Insulated Switchgear rated for 66kV, 3-phase, 50Hz, 31.5kA fault level shall be of the indoor metal-enclosed type, comprising of following items. Unit Qty 1 2 72.5kV, 1250A, single 3 – φ or three 1 –φ, SF6 Set gas insulated, metal enclosed bus bars arrangement, consisting of 1250A single 3 – φ or three 1 –φ SF6 gas insulated switchgears, each Bus Bar comprising of :i Bus bar enclosures running through the length of the switchgear to interconnect each of the circuit breaker bay modules in double main bus system. ii Three, 2-core, single phase voltage transformers/ PTs. iii 1250A, One 3 – φ or three 1 – φ, single pole, group operated isolator/disconnector and one, 3 – φ or three 1 – φ, single pole, group operated earthing switch with manual and motor driven operating mechanisms. iv 1250A, One high speed fault make 3 – φ or three 1 – φ, single pole, group operated earthing switches, complete with manual and motor driven operating mechanisms. v Each GIS compartment with gas monitoring device, pressure switch etc. as required. vi Terminal boxes/ Local Control Cubicle. vii Interconnecting wiring/ piping. viii Grounding, support structures and platforms. 2 1 72.5kV, 800A, single 3 – φ or three 1 –φ, Bus Set coupler bay module, consisting of 800A single 3 – φ or three 1 –φ SF6 gas insulated switchgears, comprising of: i 800A, One 3 – φ or three 1 –φ, SF6 gas insulated circuit breaker, complete with operating mechanism. ii Three,3-core,single phase current transformers(600300-150/1-1-1A) iii Two sets of isolator/disconnector switches each of iv v vi vii 3 i ii iii iv v vi vii viii ix x 4. i ii 800A, One 3 – φ or three 1 – φ, single pole, group operated isolator/disconnector switches each with 3 – φ or three 1 – φ, single pole, group operated earthing switch and complete with manual and motor driven operating mechanisms. Each GIS compartment with gas monitoring device, pressure switch etc. as required. Terminal boxes/ Local Control Cubicle. Interconnecting wiring/ piping. Grounding, support structures and platforms. 72.5kV, 800A, single 3 – φ or three 1 –φ, SET Transmission line feeder circuit breaker bay modules, consisting of 800A single 3 – φ or three 1 –φ SF6 gas insulated switchgears, each comprising of:800A, One 3 – φ or three 1 –φ, SF6 gas insulated circuit breaker, complete with operating mechanism for outgoing feeder. Three, 66kV LAs Three, 3-core, single phase current transformers (600-300-150/1-1-1A) 800A, One 3 – φ or three 1 – φ, single pole, group operated isolator/disconnector without earthing switch, complete with manual and motor driven operating mechanisms. 800A, One 3 – φ or three 1 – φ, single pole, group operated isolator/disconnector with one, 3 – φ or three 1 – φ, single pole, group operated earthing switch, complete with manual and motor driven operating mechanisms. 800A, One 3 – φ or three 1 – φ, single pole, group operated isolator/disconnector with one normal and one high speed fault make 3 – φ or three 1 – φ, single pole, group operated earthing switches, complete with manual and motor driven operating mechanisms. Each GIS compartment with gas monitoring device, pressure switch etc. as required. Terminal boxes/ Local Control Cubicle. Interconnecting wiring/ piping. Grounding, support structures and platforms. 72.5kV, 400A, single 3 – φ or three 1 –φ, Set Transformer feeder circuit breaker bay modules, consisting of 400A single 3 – φ or three 1 –φ SF6 gas insulated switchgears, for 66/11kV transformer, each comprising of: One 3 – φ or three 1 – φ, SF6 gas insulated circuit breaker, complete with operating mechanism for incomer bay from 66/11kV transformer. Three, 3-core, single phase current transformers 4 2 iii iv v vi vii viii ix 5(a) (b) 6(a) (b) (300-150/1-1-1A). 400A, One 3 – φ or three 1 – φ, single pole, group operated isolator/disconnector without earthing switch, complete with manual and motor driven operating mechanisms. 400A, One 3 – φ or three 1 – φ, single pole, group operated isolator/disconnector with one, 3 – φ or three 1 – φ, single pole, group operated earthing switch, complete with manual and motor driven operating mechanisms. 400A, One 3 – φ or three 1 – φ, single pole, group operated isolator/disconnector with two earthing switches each comprising of one 3 – φ or three 1 – φ, single pole, group operated earthing switches complete with manual and motor driven operating mechanisms. Each GIS compartment with gas monitoring device, pressure switch etc. as required. Local Control Cubicle. Interconnecting wiring/piping. Grounding, support structures and platforms. 66kV XLPE copper Cable 1XC (400mm2) along with one no. spare cable coated with fire retardant Paint for connecting 66kV side of 66/11kV transformer with GIS. Termination kit for both ends for 66kV XLPE copper Cable 1XC (400mm2). 66kV XLPE copper Cable 1XC (800mm2) along with one no. spare cable coated with fire retardant Paint for each Line feeder bay. Termination kit for both ends for 66kV XLPE copper Cable 1XC (800mm2). Mtrs 400 Nos. 16 Mtrs 800 Nos. 32 66KV GIS SECTOR-21-D, Faridabad ANNEXURE-B1 BILL OF QUANTITIES Sr.No. DESCRIPTION UNIT Qty. 1 25/31.5MVA, 66/11 kV Power T/F along with10% extra T/F oil No. 2 2 220V 100 AH Battery Set 1 3 66 kV Surge Arrestor No. 6 4 11kV Surge Arrestor No. 6 5 66 kV NCT For 66/11kV T/F (300-150/1A) No. 2 6 11 kV NCT For 66/11T/F (1800-900/5A) No. 2 7 66 kV CVT For Line No. 4 8 66kV C&R Panels i Ckt breaker control panel without auto reclose & line protection Set Panel 4 ii Ckt breaker control panel without auto reclose and Transformer Set of 66/11kV protection Panel 2 iii Ckt breaker control panel without auto reclose & Bus coupler Set protection panel 1 9 Time synchronization equipment No. 1 10 11 kV 15 Panel Board (1250A) with one SEM on each T/F I/C Panel (including one no. bus coupler panel) Set 2 11 11 kV Power Cable XLPE 1C x630mm2 coated with fire retardant Paintfor T/F to 11kV incomer with termination kit for both ends (4 runs per phase and 2 runs per phase for each 11kV I/C) Mtr. 2000 11 kV Power Cable XLPE 1C x630mm2 coated with fire retardant Mtr. Paintfor bus coupler of T-1 to Bus Coupler of T-2 with termination kit for both ends (2 runs per phase for each 11kV Bus Coupler) 100 12 11 kV Power Cable XLPE 3C x 400sq mm coated with fire retardant Paint for Capacitor Bank with termination kit for both ends(2 runs) Mtr. 400 13 11 kV Power Cable XLPE 3C x 50 sq mm coated with fire Mtr. retardant Paint for station T/F with termination kit for both ends 100 14 13.608 MVAR 11 kV rating Capacitor Bank with 11 kV L&E Set Switch, RVTs and 11KV LA, reactor etc. as per technical specification. 2 15 220 V 100 AH Battery charger Set 1 16 220 V 100 AH D.C.D.B. Set 1 17 415 V LT AC Distribution Board 300 A No. 1 18 11/0.4 kV Station T/F 200 KVA No. 1 19 EOT-Crane as per clause 1.10.7 Section-1 and Clause 24.0 of GIS Specification. No. 1 Mechanical Operated Crane as per clause 1.10.7 section-1 No. 1 20 1.1 kV Copper Control Cable armoured (FRLS) for 66kV bays & Lot 11kV side of sizes 7CX4mm2, 2CX4mm2, 4CX4mm2, 2CX6mm2, 16CX2.5mm2, 10CX2.5mm2, 7CX2.5mm2, 3CX2.5mm2 etc. including junction box (as per Section-6 of copper control cable specification and Section-7 of Switchyard Erection). Lot 21 650/1100 Volts 3.5 core 240 mm2 aluminium power cable from Aux. T/F to ACDB Lot Lot 22 650/1100 Volt 3.5 core 70 mm2 aluminium cable for oil filtration set. Lot Lot 23 650/1100 Volt 4 core 16 mm2 armoured (FRLS) copper power cable for MLDB etc and other cable required as per contract for 66kV bays. Lot Lot 24 Grounding system of the substation. Earthing Mat Material. The Lot earth mat will be designed/quoted for soil resistivity of 50Ωm. In case soil resistivity is more than 50Ωm then the earth mat will be designed for actual soil resistivity. The payment of extra material to be used for earth mat shall be made on pro rata basis. The approximate area of earth mat to be laid is given in the corresponding columns of the substations. However, item will remain a Lot item. 25 Fire Fighting equipments as per section-6 i 22.5 Kg Capacity FE CO2 type, Trolley Mounted No 4 ii 25 Kg Capacity FE DCP type, Trolley Mounted No 4 iii DCP 10 Kg Capacity, Wall mounted No 4 iv FE CO2 6.5 Kg Capacity, Wall mounted No 2 v DCP 5 Kg Capacity, Wall mounted No 2 vi Foam Type 9 Litre Capacity, Wall mounted No 1 vii Water CO2 9 Litre, Wall mounted No 1 viii Fire Buckets (12 No.s with stand in one set) Set 2 26 Supply and installation of 1x400 watt HPSV lamps with all No accessories for Complete lighting of outdoor Switch yard area including all accessories, cables etc. as per clause 16.0 of section 7 of the specifications. 10 27 Complete lighting of road and street by providing 1x150W HPSV No lamps on tubular steel poles at a distance of 15meter along the roads and streets including all accessories, cables etc. as per clause 16.0 of section 7 of the specification. 8 28 Supply and installation of post top lantern 70W HPSV Lamps with all complete accessories at the entrance gate of substation. 4 29 Supply and installation of fluorescent tube fitting (2 x 40W) on No tubular steel poles along with boundary wall at a distance of 30 meter including all accessories, cables etc. as per clause 16.0 of section 7 of the specification. 10 30 High wall type split AC unit of 2 Ton capacity for computer Nos. room and specifically C&R Panel room (as per technical 5 900 sq meter (approx.,) specification) 31 Complete Substation automation system for 66/11 kV substations including hardware (for present bays) and software (for present & future bays) along with associated equipments for the following bays (bay as defined in the technical specification, sec-sub-station automation system) as per technical specification a) 66 kV (presently A bays &B for future) Nos. A=7, B=3 32 Testing of IUM System at NABL accredited lab Lot Lot 66KV GIS SECTOR-21-D, Faridabad ANNEXURE –C1 Sr. No DESCRIPTION UNIT Quantity 1 66 kV bolted type single suspension string assembly with No. 6 numbers ANTI FOG type disc insulators (E&M strength 9000 kg) per string with all hardware accessories including ball & socket connections and suspension clamp set suitable for single Zebra ACSR. Alternatively the bidder may quote silicon polymer composite insulator string in place of Disc Insulators (type of insulator whether disc or polymer insulator to be identified at the time of bidding and quoted accordingly which will not be altered at later stage by the bidder). 6 2 Bolted type 11kV Single tension string assembly with 3 numbers Anti FOG type disc insulators (E&M strength 9000 kg) per string with all hardware accessories including ball & socket connections and tension clamp sets suitable for triple Zebra Conductor. Alternatively the bidder may quote silicon polymer composite insulator string in place of Disc Insulators (type of insulator whether disc or polymer insulator to be identified at the time of bidding and quoted accordingly which will not be altered at later stage by the bidder). 12 3 C-Wedge connectors matching with conductor size. Lot Lot 4 Spacers suitable for triple zebra conductor Lot Lot 5 Copper lugs glands, PVC ferrules for control cabling. L/S L/S 6 Fibre cleats, Aluminium clamps, bolts, nuts, washers etc for fixing control cables in trenches L/S L/S 7 Galvanized iron perforated tray with side coupler plate bolts, nuts, washers and clamps etc. of size 75x25x2 mm, 150X25X2mm, 100X25X2mm etc. & G.I. Conduits of 50mm/100mm dia from equipment to main trench as per Section-7, Switchyard erection. L/S L/S Painted lattice type steel trays of adequate size as per site requirement for laying control and power cables from panels (placed on top floor) to GIS & Transformers and for 11kV Outgoing cables & other cables identified as per site requirement confirming to Section-7 & 9. L/S L/S 8 ACSR Zebra Conductor(approx) Mt 300 9 10 7/3.15 Earthwire Lot Lot Lot Lot U-bolt 20mm dia The quantities given in Annexure C-I is approx. and for evaluation purpose, however, the payment shall be made as per actual on the basis of unit price/Lot. 66KV GIS SECTOR-21-D, Faridabad ANNEXURE D1 Schedules of items for associated steel structure works to be quoted for each substation as applicable. The bidder is required to estimate the quantities and furnish the unit rate for each item/ works and the total price for each item in the bid proposal sheets. The list may not be exhaustive, and the bidder may modify/ append the same as required. Sr. No DESCRIPTION UNIT Quantity Item for associated structure work ‘Lattice type steel structure for 66kV GIS S/Stn.Sector-21-D, Faridabad. Supply of material, preparation of fabrication drawing, galvanizing and delivery of lattice type steel structure for tower and beams for 66/11kV switchyard fabricated from steel conforming to IS:2062 including nuts-bolts gusset plates foundation bolts and other accessories as per drawings supplied by the owner. 1. Main S/Stn. Tower and beam i Tower type CT-4 (HW/ST-5199) No. 2 ii Tower type CT-5 (HW/ST-5195) No. 2 iii Beam type CB-6 (HW/ST-5200) No. 2 iv Tower type DT-2 (HW/ST-5210) No. 2 v Tower type DT-3 (HW/ST-5211) No. 2 vi Beam type DB-2X (HTD/ST-154) No. 2 2. Equipment Supporting Structure i 66 kV NCT Drg. No. HTD/ST-145 No. 2 ii 66 kV CVT Drg. No. HTD/ST-66 No. 4 iii 66 kV Surge Arrestor Drg. No. HTD/ST-89R No. 6 iv 11 kV NCT Drg. No. HTD/ST-88 No. 2 v 66kV Cable structure of galvanized iron along with foundation to be designed by bidder as per site requirement/size of cable No. 24 Bill of quantities in respect of PLCC equipment Annexure-E1 Sr. No Line sections PLC terminals (No.) 1 LILO of 66kV D/C line from 220kV Palla66kV NH-3 D/C line Total 2/220kV Palla 2/Sector21-D, Faridabad 0 Wave Trap (630A) LTU (Set.) 48V Battery & Battery Charger (120AH) HF cable (kms. Approx.) 4/Sector21-D, Faridabad 4/Sector21-D, Faridabad 1/Sector21-D, Faridabad 1.0 0 0 1 1.0 Note: The wave trap will be provided by HVPNL & erection of the same will be covered in the scope of firm at 66kV GIS S/Stn. Sector-21-D, Faridabad. Further, the PLC & LTU termianls will be dismantled from 66kV NH-3 S/Stn. Faridabadand same will be erected at 66kV S/Stn. GIS Sector-21-D, Faridabad (This will be the part of scope to be covered by firm). ANNEXURE-F1 Furniture Description i) Executive Room UNIT Executive Table: No. (1800mmx900mm) (Wooden) Executive Chair: (Revolving mid No. back type) Visitor’s Chair ii) Computer Room 66kV GIS Sector-21 D, Faridabad 1 1 No. 4 (Revolving mid No. 1 Visitor’s Chair: No. 4 Steel Almirah LengthxWidthxHeight in mm (1016x560x1980) No. 1 Recta work station of size 1200mmx 600 mm, 25 mm thick work top with 3 drawer pedestal alongwith keyboard tray and CPU trolley. And partitions of thickness 53 mm and of height 1200 mm. No. 1 Executive Chair: back type) ANNEXURE-G1 MAINTENANCE EQUIPMENT & SPARES AT Sector 21- D, Faridabad Sr. No. 1.0 i. ii. iii. iv. v. vi. vii. viii. ix. x. 2.0 i. ii. iii. iv. v. vi. vii. viii. ix. x. xi. xii. xiii. Description Equipments for maintenance Portable circuit breaker operation analyzer. Digital Micro-Ohm meter for contact resistance measurement Ranges (0-100 ohm) (0-1 milliohm) (0-10 milliohm). Dew Point meter Portable partial discharge monitoring system for GIS. Digital Earth resistance meter. 5 kV Automated insulation resistance tester. SF-6 Gas filling and evacuating plant SF-6 Gas leak detector (Portable) Tools for gas handling LT DC Leakage detector from control cabinets and LT cables Common Spares, Maintenance and Testing Tools (66 KV) SF6 Gas pressure relief devices Pressure gauges (of each type) along with coupling device Rubber Gaskets, “ o” Rings and seals for SF6 Gas Molecular filter for SF6 Gas with filter bags Quantity 1 Set 1 Set 1 Set 1 Set 1No. 1No. 1 Set 1Set 1 Set 1No. 3 No. 1 Set 1 Set each type 1 Set 20% of total weight 1 No. each type 1 Set each type 20% 1 Set each type Density Monitors for SF6 Gas All types of Control Valves for SF6 Gas SF6 Gas of total gas requirement Enclosures, Insulators & main circuit to replace on each phase, any compartment of Busbar or bay Covers with all accessories necessary to close a compartment in case of dismantling of any part of the enclosure to ensure the sealing of this compartment (as applicable) For 3 Phase Enclosure 2No For Single phase enclosure 3No Locking device to keep the Disconnectors (Isolators) and Earthing switches in close or open position in case of removal of the driving Mechanism Bus Support insulator of each type for 3 phase/single phase enclosure Pipe length (Copper or Steel as applicable) for SF6 Circuit ofeach type SF6 to air bushing (66 KV of each type & rating) 1 set 5% of population 1 Set 1 No each total 3.0 i. ii. iii. iv. v. vi. vii. viii. ix. x. CIRCUIT BREAKERS (66 KV) Complete Circuit Breaker pole of each type & rating complete with interrupter, main circuit, enclosure and Marshalling Box with operating mechanism Fixed, moving and arcing contacts including insulating nozzles, (3 Nos. of each type) Rubber gaskets, `O' rings and seals for SF6 gas of each type Trip coil assembly with resistor as applicable, 3 Nos. of each type Closing coil assembly with resistor as applicable, 3 Nos. of each type Molecular filter for SF6 gas with filter bags 3 No 1 Set 1 Set 2 Set 2 Set 10 % of total quantity used SF6 Pressure gauge cum switch OR Density monitors and 1 Set pressure switch as applicable, 3 Nos. of each type Coupling device for pressure gauge cum switch/ for 1 Set connecting Gas handling plant, 3 Nos. of each type Corona rings if applicable 1 Set Relays, Power contactors, push buttons, timers & MCBs 1 Set etc of each type & rating xi. xii. xiii. xiv. xv. xvi. Closing assembly/ valve, 3 Nos. of each type Set 2 Set Trip assembly/ valve, 3 Nos. of each type 2 Set Auxiliary switch assembly, 3 Nos. of each type 1 Set xvii. Spring operated closing mechanism, 1 No. of each type, if applicable Terminal Pad & connectors Isolators , E/Switch & High Speed E/Switch (66 KV) Complete set of 3 nos. of single phase / one no. of 3phase dis-connector including main circuit, enclosure, driving mechanism. 3 nos. of single phase / one no. of 3-phase Earthing switch including main circuit, enclosure, driving mechanism. Copper contact fingers for dis-connector male & female contact – for one complete (3 phase) dis-connector of each type and rating. Copper contact fingers for earthing switch male & female contacts, for one complete (3 phase) earthing switch of each type and rating Open / Close contactor assembly, timers, key interlock for one complete (3 phase) dis-connector and (3 phase) earthing switch of each type and rating xviii. 4.0 i. ii. iii. iv. v. Operation Counter, 3 Nos. of each type 1 Set Rupture disc, 3 Nos. of each type 1 Set Windoscope/ Observing window, 3 Nos. of each type, if 1 Set applicable 1 Set 1 Set 1 Set 1 Set 1 Set 1 Set 1 Set vi. vii. Push button switch.-each type, as applicable 1 Limit switch and Aux. Switches for complete 3 phase equipment a) For isolator 3 b) For earth switch 1 viii. Rotor housing bearing assembly for complete 3 phase equipment a) For isolator 2 b) For earth switch 1 Motor with gear assembly for complete 3 phase ix. equipment a) For isolator 3 b) For earth switch 1 1 x. Corona shield rings as applicable xi. Hinge pins for complete 3 phase equipment a) For isolator 3 b) For earth switch 1 Bearings for complete 3 phase equipment xii. a) For isolator 5 b) For earth switch 1 xiii. Interlocking coil with resistors, timers, key interlock for 1 complete 3 phase xiv. Relays, Power contactors, resistors, fuses, push buttons & MCBs a) For isolator 3 b) For earth switch 1 Terminal pad and connectors (complete for one 3 phase xv. equipment) a) For isolator 2 b) For earth switch 1 xvi. Aux. switch assembly (complete) with 10 NO & 10 NC OR 1 more contacts xvii. 72.5 kV, 1250 A, 3 – φ or 1 –φ high speed fault making 1 grounding switch, Internal parts complete with all necessary gaskets mounting hardware etc. xviii. 72.5 kV, 1250 A, 3 – φ or 1 –φ high speed fault making 1 grounding switch operating mechanism complete with all necessary gaskets connecting apparatus. 5.0 Current Transformer i. 66kV 1 ph CT ratio 600-300-150/1-1-1A complete with all 6 gaskets and mounting hardware ii. 66kV 1 ph CT ratio 600-300-150/0.577-1-1A complete 3 with all gaskets and mounting hardware 2 iii. Secondary Bushing of each type ( for 66kV CT ) 6.0 Voltage Transformer/PT(66 KV) 1 i. 66kV, 1-phase VT as per technical specifications complete with all gaskets and mounting hardware. Note: All the rubber spare parts shall be vacuum impregnate Set Sets Set Sets Set Sets Set Set Sets Set Sets Set Set Sets Set Sets Set Set Set Set Nos. Nos. Sets Nos. SECTION 2 GENERAL TECHNICAL REQUIRMENTS 1. GENERAL 1.1 This section stipulates the general technical requirements under the contract and will form integral part of the technical specification. 1.2 The provisions under this specification are intended to supplement requirement for the materials, equipments and services covered under this specification and is not exclusive. However, in case of conflict between requirements specified in this section and requirements specified in other sections the requirements specified- under respective sections shall hold good. 2.0 INSTRUCTION TO BIDDERS 2.1 The bidders shall submit the technical requirements, data and information as per the technical data sheets provided in the Volume III of bid documents. 2.2 The bidders shall furnish catalogues, engineering data, technical information, design document, drawings etc fully in conformity with the technical specification. 2.3 It is recognised that the contractor may have standardised on the use of certain components, materials, processes or procedures different than those specified herein. Alternate proposals offering similar equipment based on the manufacturer's standard practice will also be considered provided such proposals meet the specified designs, standard and performance requirements and are acceptable to the employer. Unless brought out clearly, the Bidder shall be deemed to conform to this specification scrupulously, All deviations from the specification shall be clearly brought out in the respective schedule of deviations. Any discrepancy between the specification and the catalogues or the bid, if not clearly brought out in the schedule, will not be considered as valid deviation. 2.4 Wherever a material or article is specified or defined by the name of a particular brand, manufacturer or vendor, the specific name mentioned shall be understood as establishing type, function and quality and not as limiting competition. 2.5 Equipment furnished shall be complete in every respect with all mountings, fittings, fixtures and standard accessories normally provided with such equipment and/or needed for erection, completion and safe operation of the equipment as required by applicable codes though they may not have been specifically detailed in the technical specifications unless include in the list of exclusions. Materials and components not specifically stated in the specification but which are necessary for commissioning and satisfactory operation of the switchyard shall be deemed to be included in the scope of the 1 specification. All similar standard components/parts of similar standard equipment provided, shall be inter changeable with one another. 2.6 Unless brought out clearly in the respective schedule of deviations, it will be considered that, the bid proposal scrupulously conforms compliance to the specification. The bidder must bring out all the deviations in the bid proposal. 2.7 In case there is a discrepancy between the data offered equipment and catalogue furnished, and unless the deviations are brought out clearly in the Technical Deviation Schedule, the equipment will be deemed to conform compliance to the specification scrupulously. 3.0 STANDARDS 3.1 The works covered by the specification shall be designed, engineered, manufactured, built tested and commissioned in accordance with the Acts, Rules, Laws and Regulations of India. 3.2 The equipment to be furnished under this specification shall conform to latest issue with all amendments of standard specified under Annexure B of this section as well as under respective Sections/Chapters of the specification. 3.3 In addition to meeting the specific requirement called for in the respective sections of the Technical Specification, the equipment shall also conform to the general requirement of the relevant standards and shall form an internal part of the specification. 3.4 The Bidder shall note that standards mentioned in the specification are not mutually exclusive or complete in themselves, but intend to compliment each other. 3.5 The Contractor shall also note that list of standards presented in this specification is not complete. Wherever necessary the list of standards shall of the specification shall take precedence. 3.6 When the specific requirements stipulated in the specification exceed or differ than those required by the applicable standards, the stipulation of the specification shall take precedence. 3.7 Other internationally accepted standards which ensure equivalent or better performance than that specified in the standards referred shall also be accepted. 3.8 In case governing standards for the equipment is different from IS or IEC, the salient points of difference shall be clearly brought out in additional information schedule of Vol. III alongwith English language version of standard or relevant shall be subject to Employer's approval. 2 4. SERVICES TO BE PERFORMED BY THE EQUIPMENT BEING FURNISHED 4.1 The 220/132/33 kV system is being designed to limit the switching surge over voltage and the power frequency over voltage within limits of IEC. The equipment furnished under this specification shall perform all its functions and operate satisfactorily with out showing undue strain, re-strike etc. under such over voltage conditions and in system where line lengths would extend up to 200 km. 4.2 All equipments shall also perform satisfactorily under various Electromechanical and meteorological conditions of the site of installation. 4.3 All the Equipment shall be able to withstand all external and internal mechanical, thermal and electromechanical forces due to various factor like wind load, temperature variation, short circuit etc for the equipment. 4.4 The bidder shall design the various forces for terminal connectors of the equipment are required to withstand. 4.5 The equipment shall also comply to the following: 4.6 4.7 4.7.1 S.NO. 1. 2. 3. 4. i) ii) iii) 5. 6. a) All outdoor EHV equipments shall be suitable for hot line washing. b) To facilitate erection of equipment, all items to be assembled as site shall be "match marked". c) All piping, if any between equipment control cabinet operating mechanism to marshalling box of the equipment shall bear proper identification to facilitate the connection at site. Operating times of circuit breakers, protective relays and PLCC equipment have been specified in respective sections. EHV equipments and system shall be designed to meet the following major technical parameters as brought out hereunder. System Parameter Description of parameters System operating voltage Rated frequency No. of phase Rated Insulation levels Full wave impulse withstand voltage(1.2/50 micro sec.) Switching impulse withstand voltage (250/ 2500 micro sec.) dry and wet One minute power frequency dry and wet withstand voltage (rms) Corona extinction voltage Max. Radio interference voltage for frequency Between 0.5 MHz and 2 MHz 156kV rms for 220kV system & 92 kV rms for 132kV 220 kV 220 kV 50Hz 66 kV 66 kV 50Hz 11 kV 11 kV 50Hz 3 3 3 1050kVp 325kVp 75kVp - - - 460kV 140kV 28kV - - 156kV 1000 micro volt 500 micro volt 3 system. Minimum creepage distance 25 mm/kV (6125 mm) 25 mm/kV (1813 mm) 25 mm/kV (300 mm) 2100 mm 800 mm 280 mm 2100 mm ii) 5000 mm iii) Sectional clearances Rated short circuit current for 1 sec. 40 kA for AIS 9. 800 mm 140 mm 3000 mm 31.5 kA 3000 mm 26.2 kA 10. System neutral earthing Solidly earthed Solidly earthed 7. 8. i) Min. clearances Phase to phase (for Rod–conductor configuration) and (for conductor configuration) Phase to earth duration 4.7.2 (A) 1 50kA for GIS Solidly earthed Major Technical Parameters The major technical parameters of the equipments are given below. For other parameters and features respective technical sections should be referred. 25/31.5MVA 66/11KV Power Transformer Maximum Continuous Capacity (MVA) 2 Rated Voltage (kV) 3 4 5 Percentage Impedance Vector Group Insulation level Lightning Impulse withstand voltage (KVp) Power Frequency withstand voltage(KV rms) i) ii) (B) 1. 2. 3. 4. 5. a) b) 6. ONAF 31.5 LV 11 LV 95 100 FOR 245 kV & 72.5 kV CT/CVT/SA 220 kV Rated voltage kV (rms) 245 Rated frequency (Hz) 50 No. of Poles 3 Design ambient temperature (°C) 50 Rated insulation levels : Full wave impulse withstand voltage (1.2/50 micro sec.) between line terminals and ground for CVT and ± 1050 kVp arrester housing One minute power frequency dry and wet withstand voltage between line terminals and ground for CVT and 460 arrester housing (kV rms) Max. radio interference voltage (microvolts) for 1000 for CVT frequency between 0.5 MHz and 2 MHz in all 500 for SA (at positions of the equipments. 156 kVrms) Minimum creepage distance Phase to ground (mm) 8. System neutral earthing 9. Seismic acceleration 10. Partial discharge for :Surge arrester at 1.05 COV For CVT 7. ONAN 25 HV 66 10% at 31.5MVA Base YYO HV 325 140 6125 66 kV 72.5 50 3 50 11 kV 12.1 50 3 50 ±325 kVp ±75 kVp 140 28 - 500 (at 92 kV rms) 1813 300 -- Effectively earthed--- 0.3g horizontal -- <50pc <10pc <50pc <10pc <50pc <10pc 4 5.0 ENGINEERING DATA 5.1 The furnishing of engineering data by the Contractor shall be in accordance with the schedule for each set of equipment as specified in the technical specifications. 5.2 The review of these data by the Employer will cover only general conformance of the data to the specifications and documents, interfaces with the equipment provided under the specifications, external connections and of the dimensions which might affect substation layout. This review by the Employer may not indicate a through review of all dimensions, quantities and accuracy of the information submitted. This review and/or approval by the Employer shall not be considered by the Contractor, as limiting any of his responsibilities and liabilities for mistakes and deviation from the requirements, specified under these specifications and documents. 5.3 All engineering data submitted by the Contractor after final process including review and approval by the Employer shall from part of the Contract Document and the entire works performed under these specifications shall be performed in strict conformity, unless otherwise expressly requested by the Employer in Writing. 6.0 DOCUMENTS 6.1 LIST OF DOCUMENTS 6.1.1 The bidder must furnish a detailed list of drawings/documents along with the bid proposal which he intends to submit to the Employer after awarded of the contract. 6.1.2 The supplier shall necessarily submit all the drawings/ documents unless anything is waived. 6.1.3 The supplier shall submit 6 (six) sets of drawings/design documents/test reports as may be required for the approval of the Employer. 6.2 All engineering data submitted by the Contractor after final process including review and approval by the Employer shall from part of the Contract Document and the entire works performed under these specifications shall be performed in strict conformity, unless otherwise expressly requested by the Employer in Writing. 6.3 DRAWINGS 6.3.1 All drawing submitted by the Contractor including those submitted at the time of bid shall be in sufficient detail to indicate the type, size, arrangement, material description, Bill of Materials, weight of each component, break-up for packing and shipment, the external connections, fixing arrangement required, the dimensions required for installation and interconnections with other 5 equipments and materials, clearances and spaces required for installation and interconnection between various portions of equipments and any other information specifically requested in the specifications. Each drawing submitted by the Contractor shall be clearly marked with the name of the Employer, the unit designation, the specifications title, the specification number and the name of the Project. If standard catalogue pages are submitted, the applicable items shall be indicated therein. All titles, noting, markings and writings on the drawing shall be in English. All the dimensions should be in metric units. 6.3.3 Further work by the Contractor shall be in strict accordance with these drawing and no deviation shall be permitted without the written approval of the Employer if so required. 6.4 All manufacturing and fabrication work in connection with the equipment prior to the approval of the drawing shall be at the Contractor's risk. The Contractor may make any changes in the design which are necessary to make the equipment conform to the provisions and intent of the Contract and such changes will again be subject to approval by the Employer. Approval of Contractor's drawing or work by the Employer shall not relieve the contractor of any of his responsibilities and liabilities under the Contract. 6.3.2 6.5 APPROVAL PROCEDURE The scheduled dates for the submission of these as well as for, any data/information to be furnished by the Employer would be discussed and finalised at the time of award. The supplier shall also submit six (6) copies of all drawings/design documents/test report for approval of the Employer. The following schedule shall be followed generally for approval. i) Approval/comments/by employer on initial submission Within 4 weeks of receipt. ii) Resubmission Within 3 (three) weeks (whenever from date of comments required) including both ways postal time. iii) Approval or comments Within 3 weeks of receipt of resubmission iv) Furnishing copies 3 weeks from the date of last approval. of distribution Note: The contractor may please note that all resubmission must incorporate all comments given in the submission by the Employer failing which the submission of documents is likely to be returned. 6.6 The drawing which are required to be referred frequently during execution should be submitted on cloth lined paper. 6 6.7 6.7.1 6.7.2 OTHER REQUIREMENTS OF DOCUMENTATION One set of 4microfilm and 8 sets of all drawing per substation plus one set and four sets of all drawing for HVPN head office shall be furnished after approval of drgs. Microfilms submitted should be compatible with 35 mm microfilming system. The manufacturer shall also submit one video cassette (VHS-PAL) per substation and one for HVPN head office highlighting installation and maintenance techniques/requirements of Circuit Breaker & Isolators. 6.7.3 On completion of the entire works, the supplier shall also furnish eight bound sets of all as built drawings, duly signed by the site in-charge along with 1 set of microfilms. Computer CD/DVD for each substation and HVPN head office containing all "as-built drawing in Auto-Cad version 12 or better shall also be submitted". 6.7.4 8 copies of instruction/operation manuals per sub station and HVPN head office shall also be furnished. The instruction Manuals shall contain full details of drawing of all equipment being supplied under this contract, their exploded diagrams with complete instruction for storage, handing, erection, commissioning, testing, operation, trouble shooting, servicing and overhauling procedures. 6.7.5 After approval of test reports, 6(six) bound sets containing all drawings/manuals, type and routine test report etc. along with sub-vendor’s test reports for all bought out assemblies/components/parts including internal wiring diagrams and exploded diagrams of assemblies/ parts, shall be furnished. 6.8 If after the commissioning and initial operation of the substation, the instruction manuals require any modifications/additions/changes, the same shall be incorporated and the updated final instruction manual in the form of one (1) reproducible original and twelve( 12) copies shall be submitted by the Contractor to the Employer. The Contractor shall furnish to the Employers, twelve(12) sets of spare part catalogue. 7.0 7.1 COLOUR SCHEME AND CODES The contractor shall propose parts a color scheme for the those equipments /Items for which the colour scheme has not been specified in the specification, for the approval of Employer. The decision of Employer shall be final. The scheme shall include: Finishing colour of Indoor equipment. - Finishing colour of Outdoor equipment. - Finishing colour of all cubicals. - Finishing colour of various auxiliary system equipment including piping. 7 - Finishing colour of various building items. 7.2 All steel structures, plates etc shall be hot dip galvanised or painted with noncorrosive paint on a suitable primer as per the provisions of the respective Section. It may be noted that normally all Employer's electrical equipment in Employer's switchyard are painted with shade 631 of IS-5 and Employer will prefer to follow the same for this project also. All the indoor cubicles shall be of same colour scheme and for other miscellaneous items colour scheme will be approved by the Employer. 8.0 MATERIAL/ WORKMANSHIP 8.1 GENERAL REQUIREMENTS 8.1.1 Where the specification does not contain characteristics with reference to workmanship, equipment, materials and component of the covered Equipment, it is understood that the same must be new, of highest ,grade of the best quality of their kind, conforming to the best engineering practice and suitable for the purpose for which they are intended. 8.1.2 The equipment must be new, of highest grade, the best quality of their kind, to best engineering practice and latest state of ardent in accordance with purpose for which they are intended and to ensure satisfactory performance throughout the service life. 8.1.3 Incase where the equipment, material or components are indicated in the specification as "similar" to any special standard, the employer shall decide upon the question of similarly. When required by the specification or required by the employer the supplier shall submit, for approval, all the information concerning the material or components supplied, installed or used without such approval shall run the risk of subsequent rejection, it being understood that the cost as well as the time delay associated with the rejection shall be borne by the Supplier. 8.1.4 The design of the work shall be such that installation, future expansions, replacement and general maintenance may be undertaken with a minimum of time and expenses. Each component shall be designed to be consistent with its duty and suitable factors of safety, subject to mutual agreements and shall be used throughout the design. All joints and fastenings shall be devised; constructed and documented so that the component part shall be accurately positioned and retained to fulfil their require function. In general, screw threads shall be standard metric threads. The use of other thread forms will only be permitted when prior approval has been obtained from the Employer. 8.1.5 Whenever possible, all similar part of the works shall be made to gauge and shall also be made interchangeable with similar parts. All spare parts shall be interchangeable with, and shall be made of the same material and workmanship as the corresponding parts of the equipment supplied under specification. Where feasible, common component units shall be Employed in different pieces of the equipment in order to minimize spare parts stocking 8 requirements. All equipment of the same type and rating shall be physically and electrically interchangeable. 8.1.6 All material and equipment shall be. installed in strict accordance with the manufacturer's recommendation(s). Only first-class work in accordance with the best modern practice will be accepted. Installation shall be constructed as being the erection of equipment at its permanent location. This, unless otherwise specified, shall include unpacking, cleaning and lifting into position, grouping, leveling, aligning, coupling of or bolting down to previously installed equipment bases/ foundation, performing the alignment check and final adjusting prior to initial operation, testing and commissioning in accordance with the manufacturer's tolerances and instruction and the specification. All factory assembled rotating machinery shall be checked for alignment and adjustments made as necessary to re-establish the manufacturer's limits suitable guards shall be provided for the protection of personnel on all exposed rotating and/or moving machine parts and shall be designed for easy installation and removal for maintenance purpose. The spare equipment( s) shall be installed at designated location and tested for healthiness. 8.1.7 The Supplier shall apply oil and grease of the proper specification to suit the machinery, as is necessary for the installation of the equipment. Lubricants used for installation purpose shall be drained out and the system flushed through where necessary for applying the lubricant required for operation. The Supplier shall apply all operational lubricants to the equipment installed by him. 8.1.8 All oil, grease and other consumable used in the Works/Equipment shall be purchased in India unless the Supplier has any special requirement for the specific application of a type of oil or grease not available in India. In such is the case he shall declare in the proposal, where such oil or grease is available. He shall help Employer in establishing equivalent India make and Indian supplier. The same shall be applicable to other consumable too. 8.1.9 A cast iron or welded steel base plate shall be provided for all rotating equipment which are to be installed on a concrete base unless otherwise agreed to by the Employer. Each base plate shall support the units and its drive assembly, shall be of design with pads for anchoring the units and shall have a raised up all around and shall have threaded in air connections, if so required. 8.2 PROVISION FOR EXPOSURE TO HOT HUMID CLIMATE Outdoor equipment supplied under the specification shall be suitable for service and storage under tropical conditions of high temperature, high humidity, heavy rainfall and environment favorable to the growth of fungi and mildew. The indoor equipments located in non-aircollditioned areas shall also be same type. 9 8.2.1 SPACE HEATERS 8.2.1.1 The heater shall be suitable for continuous operation at 240 V as supply voltage. On-off switch and fuse shall be provided. 8.2.1.2 One or more adequately rated permanently or thermostatically connected heater'shall be supplied to prevent condensation in any compartment. The heaters shall be installed in the lower portion of the compartment and electrical connection shall be made from below the heaters to minimize deterioration of supply wire insulation. The heaters shall be suitable to maintain the compartment temperature to prevent condensation. This shall be demonstrated by tests. 8.2.1.3 The heaters shall be suitably designed to prevent any contact between the heater wire and the air and shall consist of coiled resistance wire centered in a metal sheath and completely encased in a highly compacted powder of magnesium oxide or other material having equal heat conducting and electrical insulation properties, or they shall consist of resistance wire wound on a ceramic and completely covered with a ceramic material to prevent any contact between the wire and the air. Alternately, they shall consist of a resistance wire mounted into a tubular ceramic body and embedded in vitreous gale. The surface temperature of the heater shall be restricted wire is wound on a tubular ceramic body and embedded in vitreous glaze. The surface temperature of the heaters shall be restricted to a value which will not shorten the life of the heater sheaths or that of insulated wire or other component in the compartments. 8.2.2 FUNGISTATIC VARNISH Besides the space heaters, special moisture and fungus resistant varnish shall be applied to parts which may be subjected or predisposed to the formation of fungi due to the presence or deposit of nutrient substances. The varnish shall not be applied to any surface of part where the treatment will interfere with the operation or performance of the equipment. Such surfaces or parts shall be protected against the application of the varnish. 8.2.3 VENTILATION OPENING In order to ensure adequate ventilation, compartments shall have ventilation openings provided with fine wire mesh of brass or galvanized steel to prevent the entry if insects and to reduce to a minimum the entry of dirt and dust. Outdoor compartment openings shall be provided with shutter type blinds. 8.2.4 DEGREE OF PROTECTION The enclosures of the control cabinets, junction boxes and marshalling boxes to be installed shall provide degree of protection as detailed here under: a) Installed outdoor: 1 – 55 10 b) Installed indoor in air conditioned area :1-31 c) Installed in covered are : 1 – 52 d) Installed indoor in non-airconditioned area where possibility of entry of water is limited: 1-41 The degree of protection shall be in accordance with IS: 13947(Part-l) or IEC947 (part-I). Type test report for degree of protection test, on each type of the box shall be submitted for approval. 9. RATING PLATES, NAME PLATES AND LABELS 9.1 Each main and auxiliary item of substation is to be permanently attached to it in a conspicuous position a rating plate of non-corrosive material upon which is to be engraved manufacturer's name, year of manufacture, equipment name, type or serial number together with details of the loading condition under which the item of substation in question has been designed to operate, and such diagram plates as may be required by the employer. The rating plates of each equipment shall be according to IEC requirement. 9.2 All such nameplates instruction plates, rating plates shall be bilingual with Hindi inscription first followed by English. Alternatively two separate plates one with Hindi and the other English Instruction may be provided. 10. FIRST FILL OF CONSUMABLE, OIL AND LUBRICANT All the first fill consumable such as oil, lubricant, filling compounds, touch up paints, soldering/brazing material for all copper piping of circuit breakers and essential chemicals etc. which will be required to put the equipment covered under the scope of the specifications, into successful operation, shall be furnished by the Contractor unless specification excluded under the exclusions in these specifications and documents DESIGN IMPROVEMENTS 11. 11.1 The bidder may note that the equipments offered by him in the bid only shall be acceptable, however, the Purchaser or the Supplier may propose changes in the specification of the equipment or quality thereof and if the parties agreed upon any such changes, the specification shall be modified accordingly. 11.2 If any such agreed upon change is such that if affects the price. and schedule of completion, the parties shall agree in writing as to the extent of any change in the price and/or schedule of the completion before the contractor proceeds with the change. Following such agreement, the provision thereof, shall be deemed to have been amended accordingly. 12. QUALITY ASSURANCE PROGRAMME 12.1 To ensure that the equipment and services under the scope of this contract whether manufactured or performed within the contractor's Work or at his Subcontractor's premises or at the Employer's site or at any other place of 11 work are in accordance with the specification, the Contractor shall adopt suitable quality assurance programme to control such activities at all points necessary. Such programme shall be outlined by the contractor and shall be finally accepted by the employer after discussions before the award of contract. A quality assurance programme of the contractor shall generally covered the following: a) His Organization structure for the management and implementation of the proposed quality assurance programme: b) Qualification data for bidder's key personnel: c) Documentation control System: d) The procedure for purchases of material, parts components and selection of subcontractor’s services including vendor analysis,. source, inspection, incoming raw material inspection, verification of material purchases etc: e) System for shop manufacturing and ,site erection control including process controls and fabrication and assembly control: f) Control and non-conforming items and system for corrective actions: g) Inspection and test procedure both for manufacture and field activities: h) Control of calibration and testing of measuring instruments and field activities: i) System for indication and appraisal of inspection status: j) System for quality audits: k) System for authorising release of manufactured product to the Purchaser: l) System for maintenance of records: m) System for handling storage and delivery: and n) A quality plan detailing out the specific quality control measures and procedures adopted for controlling the quality characteristics relevant to each item of equipment furnished and/or services ordered. The Employer or his duly authorised representative reserves the right to carry out quality audit and quality surveillance of the system and procedure of the Contractor/his vendor's quality management and control activities. 12.2 QUALITY ASSURANCE DOCUMENTS 12 The contractor shall be required to submit the following quality Assurance Documents within three weeks after despatch of the equipment. a) All Non-destructive Examination procedures, stress relief and weld repair procedure actually used during fabrication and report including radiography interpretation reports. b) Welder identification list, listing welder’s and welding operator qualification procedure and welding identification symbols. c) Welder and Welding operator qualification certificate. d) Raw material test reports on components as specified by the specification and lor agreed to in the quality plan. e) Stress relief time temperature chart/oil impregnation til)1e temperature chart. f) Factory test results for testing required as per applicable codes/ mutually agreed quality plan/ standards referred in the technical specification. g) The quality plan with verification of various customer inspection points(CAP) as mutually agreed and methods used to verify the inspection and testing points in the quality plan were performed satisfactory. 13. 13.1 INSPECTION, TESTING & INSPECTION CERTIFICATE The Employer his duly authorised representative and/or outside inspection agency acting on behalf of the Employer shall have at all reasonable times free access to the Contractor's premises or Works and shall have the power at all reasonable times to inspect and examine the material and the Workmanship of the Works during its manufacture or erection and if part of the works during its manufacturing or erection and if the part of works being manufactured or assembled at other premises or works, the contractor shall obtain for the Engineer and for his duly authorised representative permission to inspect as if the work were manufactured or assembled on the Contractor own premises or works, Inspection may be made at any stage of manufacture, despatch or at site at the option of the Employer and equipment if found unsatisfactory due to bad workmanship or quality, material is liable to be rejected. 13.2 All equipment being supplied shall conform to valid type tests as per IEC/IS & same shall not be older than 7 years as on the date of bid opening and shall be subject to routine tests in accordance with relevant standards. 13.3 The Contractor shall give the Employer/Inspector thirty(30) days written notice of any material being ready for testing alongwith work test certifi!:ate. Such tests shall be to the Contractor's account except for the expenses of the 13 Inspector. The Engineerllnspector, unless witnessing of the tests is virtually waived, will attend such tests with thirty(30) days of the date of which the equipment is notified as being ready for tests/inspection, failing which the contractor may proceed with the test which shall be deemed to have been made in the Inspector's presence and he shall forthwith forward to the Inspector duly certified copies of tests in triplicate. 13.4 13.5 The Employer or Inspector shall, within fifteen (15) days from the date of inspection as defined here in give notice in writing to the contractor, of any objection to any drawings and all any equipment and workmanship which in his opinion is not in accordance with the contract. The Contractor shall give due consideration to such objections and shall either made the modifications that may be necessary to meet the said objections or shall confirm in writing to the Engineer/Inspector giving reasons therein, that no modifications are necessary to comply with the Contract. When the, factory tests have been completed at the Contractor's or Subcontractor's Works the Employer/Inspector shall issue a certificate to this effect within fifteen (15) days after completion of tests but if the tests are not witnessed by the Employer/Inspector, the certificate shall be issued within fifteen(15) days of receipt of the contractor's Test certificate by the Engineer/Inspector. Failure of the Engineer/Inspector to issue such a certificate shall not prevent the Contractor from proceeding with the Works. The completion of these tests or the issue of the certificate shall not bind the employer to accept the equipment should, it, on further tests after erection be found not to comply with the Contract. The equipment shall be dispatched to site only after approval of test reports and issuance of MICA by the Employer. 13.6 In all cases where the Contract provides for tests whether at the premises or at the works of the contractor or of any Sub-Contractor. The Contractor except where otherwise specified shall provide free of charge such items as labour, material electrically, field water, stores, apparatus and instruments as may be reasonably demanded by the Employer/Inspector or his authorised representative to carry out effectively such tests of the equipment in accordance with the contractor and shall give facilities to the Employerllnspector or to his authorised representative to accomplish testing. 13.7 The inspection by Employer and issue of Inspection Certificate thereon shall in no way limit the liabilities and responsibilities of the Contractor in respect of the agreed quality assurance programme forming a part of the contractors. 13.8 The Employer will have the right of having at his own expenses any other test(s) of reasonable nature carried out at Contractor premises or at site of in any other place in addition of aforesaid type and routine tests, to satisfy that the material comply with the specification. 13.9 The Employer reserves the right for getting any field tests conducted on the completely assembled equipment at site. 14. TESTS 14 14.1 CHARGING On completion of erection of the equipment and before charging, each item of the equipment shall be thoroughly cleaned and then inspected jointly by the Employer and the Contractor for correctness and completeness of installation and acceptability for charging, leading to initial pre-commissioning tests at site. The list of pre-commissioning tests to be performed shall be included in the Contractor's quality assurance programme. 14.2 COMMISSIONING TESTS 14.2.1 The available instrumentation and control equipment will be used during such tests and the Employer will calibrate, all such measuring equipment and devices as far as practicable. However un measurable parameters shall be taken into account in a reasonable manner by the Employer for the requirement of these tests. The tests will be conducted at the specified load points and as near the specified cycle condition as practicable. The employer will apply proper corrections in calculation, to take into account conditions which do not correspond to the specified condition. 14.2.2 Any special equipment, tools and tackles required for the successful completion of the Commissioning Tests shall be provided by the Contractor, free of cost. 14.2.3 The specified tests to be conducted on equipment have been brought out in the respective chapters of the technical specification. 14.3 The Contractor shall be responsible for obtaining statutory clearances from the concerned authorities for commissioning the equipment and the switchyard. However, necessary fee shall be paid by employer. 15. PACKING AND SHIPPING All the equipment shall be suitably protected, coated, covered or boxes and crated to prevent damage or deterioration during transit, handling and storage at site till the time of erection. While packing all the materials, the limitation from the point of view of availability of Railway wagon sizes in India should be taken account. The Contractor shall be responsible for any loss or damage during transportation, handling and storage due to improper packing. Employer takes no responsibility of the wagons. 16. PROTECTION All coated surfaces shall be protected against abrasion, impact, discoloration and any other damages. All exposed threaded portions shall be suitably protected with either a metallic or a non-metallic protecting device. All ends of all valves and pilings and conduit equipment connections shall be properly sealed with suitable devices to protect them form damage. The parts which are likely to get rusted, due to exposure to weather should also be properly treated and protected in a suitable manner. 15 17. PAINTING AND FINISHING OF METAL SURFACES 17.1 GENERAL All metal surfaces shall be subjected to treatment for anti-corrosion protection. All ferrous surfaces for external use shall be hot-dip galvanized after fabrication. High tensile steel nuts and bolts and spring washers shall be electro-galvanized to service condition. All steel conductors including those used for earthing/grounding (above ground level) shall also be galvanized according to 1S: 2629. 17.2 HOT DIP GALVANIZING 17.2.1 The minimum weight of the zinc coating shall be 610g/sq.m and minimum thickness of coating shall be 85 microns for all items thicker than 6mm. For items lower than 6mm thickness requirement of coating thickness shall be as per relevant A5TM. 17.2.2 The galvanized surfaces shall consist of a continuous and uniform thick coating of zinc, firmly adhering to the surface of steel;. The finished surfaces shall be clean and smooth and shall be free from defects liked is colour patches, are spots, unevenness of coating, plate which is loosely attached to the steel globules, spiky deposits, blistered surface, flaking or peeling off, etc. The presence of any of these defects notices on visual or microscopic inspection shall render the material liable to rejection. 17.2.3 After galvanizing, no drilling or welding shall be performed on the galvanized parts of the equipment excepting that nuts may be threaded after galvanizing. Sodium dichromate treatment shall be provided to avoid formation of white rust after hot dip galvanization. 17.2.4 The galvanized steel shall be subjected to six one minute dips in copper sulphate solution as per IS-2633. 17.2.5 Sharp edges with radii less than 2.5mm shall be able to withstand four immersions of the standard price test. All other coating shall withstand six immersions. The following galvanizing tests should essentially be performed as per relevant Indian Standards. Coating - Uniformity of zinc - Adhesion test - Mass of Zinc 16 17.2.6 Galvanized material must be transported properly to ensure that galvanized surfaces are not damaged during transit. Application of zinc rich paint at site shall not be allowed. 17.3 PAINTING 17.3.1 All sheet steel work shall be digressed, pickled, phosphated in accordance with the IS-6005 "code of practice for phosphating iron and sheet". All surfaces which will not be easily accessible after shop assembly shall before hand to be treated and protected for the life of the equipment. The surface which are to be finished painted after installation, shall be shop painted with atleast two coats of primer. Oil, grease, dirt and swart shall be thoroughly removed by emulsion cleaning. Rust and scale shall be removed by pickling with dilute acid followed by washing with running water, rinsing with slightly alkaline hot water and drying. 17.3.2 After phosphating, thorough rinsing shall be carried out with clean water followed by final rinsing with dilute dichromate solution and over drying. The phosphate coating shall be sealed with application of two coats may be "flash dried" while the second coat shall be stoved. 17.3.3 After application of the primer, two coats of finishing synthetic enamel paint shall be applied, each coat followed by stoving. The second finishing coat shall be applied after inspection of first coat of painting. 17.3.4 The exterior color of the paint shall be as per shade No.:631 of IS-5 and inside shall be glossy white. Each coat of primer and finishing paint shall be of slightly different shade to enable inspection of the painting. A small quantity of finishing paint shall be supplied for minor touching up required at site after installation of the equipments. 17.3.5 In case the bidder proposes to follow his own standard surface finish and protection procedures or any other established painting procedures, like electrostatic painting etc. the procedure shall be submitted alongwith the bids for employer's review & approval. 18. 18.1 HANDILING, STORING AND INSTALLTION In accordance with the specific installation instructions as shown on manufacturer's drawings or as directed by the employer or his representative, the contractor shall unload, store, erect, install, wire test and place into commercial use all the electrical equipment included in the contract. Equipment shall be installed in a neat, workmanlike manner so that it is level, plumb, square and properly aligned and oriented. Commercial use of switchyard equipment means completion of all site tests specified and energisation at rate voltage. 18.2 Contractor may engage manufacturer's engineer to supervise the unloading, transportation to site, storing, testing and commissioning of the various equipment being procured by them separately. Contractor shall unload, transport, store, erect, test and commission the equipment as per instructions 17 of the manufacturer's supervisory Engineer(s) and shall extend full cooperation to them,. 18.3 In case of any doubt/misunderstanding as to the correct interpretation of manufacture's drawing or instruction, necessary clarifications shall be obtained from the Employer: Contractor shall be held responsible for any damage to the equipment consequent to not following manufacturer's drawing/instructions correctly. 18.4 Where assemblies are supplied in more than one section, Contractor shall make all necessary mechanical and electrical connections between section including the connection between buses. Contractor shall also do necessary adjustments/alignments necessary for proper operation of circuit breakers, isolators and their operating mechanisms. All components shall be protected, testing and commissioning. Any equipment damaged due to negligence or carelessness or otherwise shall be replaced by the Contractor at his own expense. 18.5 Supplier shall be responsible for examining all the shipment and notify the Employer immediately of any damage, shortage, discrepancy etc. for the purpose of Employer's information only. The supplier shall submit to the Employer every week a report detailing all the receipts for any shortages or damages in transit, handling and/or in storage and erection of the equipment at Site. Any demurrage, wharfage and other such charges claimed by the transporters, railways etc. shall be to the account of the Supplier. 18.6 The Contractor shall be fully responsible for the equipment material unit the same is handed over to the Employer in an operating condition after commissioning. Contractor shall be responsible for the maintenance of the equipment material while in storage as well as after erection unit taken over by Employer, as well as protection of the same against theft, element of nature, corrosion, damages etc. 18.7 Where material/equipment is unloaded by Employer before the Contractor arrives at site or even when he is site. Employer by right can hand over the same to Contractor and there upon it will be the responsibility of Contractor to store the material in an orderly and proper manner. 18.8 The Supplier shall be responsible for making suitable indoor storage facilities, to store all equipment which require indoor storage. 18.9 The words 'erection' and 'installation' used in the specification are synonymous. 18.10 Exposed live parts shall be placed high enough above ground to meet the requirements of electrical and other statutory safety codes. 18 19. PROTECTIVE GUARD Suitable guards shall be provided for protection of personnel on all exposed rotating and/ or moving machine parts. All such guards with necessary spares and accessories shall be designed for easy installation and removal for maintenance purpose. 20. DESIGN CO-ORDINATION 20.1 The Contractor shall be responsible for the selection and design of appropriate equipments to provide the best co-ordinate performance of the entire system. The basic design requirements are detailed out in this Specification. The design of various components, sub-assemblies and assemblies shall be so done so that it facilitates easy field assembly and maintenance. 20.2 The Contractor has to coordinate designs and termination with the agencies (If any)who are Consultants/Contractor for the Employer. The names of agencies shall be intimated to the successful bidders. 21. DESIGN CO-ORDINATION MEETING The Contractor will be called upon to attend design co-ordination meeting with the Engineer, other Contractor's and the Consultants of Employer (If any) during the period of Contract. The Contractor shall attend such meeting at his own cost as and when required and fully cooperate with such person and agencies involved during those discussions. 22. TOOLS AND TACKELS The Contractor shall supply with the equipment one complete set of all special tools and tackles for the erection, assembly,dis-assembly and maintenance of the equipment. However, these tools and tackles shall be separately, packed and brought on to Site. 23. EQUIPMENT BASES A cast iron or welded steel base.plate shall be provided for all rotating equipment which is to be installed on a concrete base unless otherwise agreed to by the Employer. Each base plate shall support the unit and its drive assembly, shall be of a neat design with pads for anchoring the units, shall have a raised lip all around, and shall have threaded drain connections. 24. FACILITIES TO BE PROVIDED BY THE BIDDER 24.1 The sub-station auxiliary supply is met through a system indicated having the following parameters. The auxiliary power for station supply including the equipment drive, cooling system of any equipment, air-conditioning, lighting etc shall be designed for the specified Parameters as under. The DC supply 19 for the instrumentation and PLCC system shall also conform the parametres as indicated in the following. Normal Voltage Variation In Voltage Frequency In Hz Phase / Wire Neutral Connection 415 V + 10% - 15% 50:1:5% 3 4 wire Solid Earthed 240 V + 10% - 15% 50:1:5% 1 2 wire Solid Earthed 220 V 190 to 220 DC 2 wire Isolated System Combined variation of voltage and frequency shall be limited to +/- 10%. Fault level for AC and DC system shall be 20 kA for 1 sec and 4 kA for 1 sec respectively. 25. SUPPORT STRUCTURE 25.1 The support structures should be hot dip galvanised with minimum 610 gram/m2 net of Zinc. 25.2 In case of any deviation in this regard the bid is liable to be rejected. 25.3 Support structure shall meet the following mandatory requirements. 25.4 The minimum vertical distance from the bottom of the lowest porcelain part of the bushing, porcelain enclosures or supporting insulators to the bottom of the equipment base, where it rests on the foundation pad shall be 2.55 meters. 25.5 The design calculations taking into account the environmental conditions of the substations shall be furnished for sizing of the structures. 26. CLAMPS AND CONNECTORS INCLUDING TERMINAL CONNECTORS 26.1 All power clamps and connectors shall conform to IS:5561 & NEMA CC1 and shall be made of materials listed below: a) For connecting Tarantulla /ACSR conductors The Fired ‘C’ wedge connector, as per clause 1.4.4 of section 7 b) For connecting conductors ACSR Aluminium alloy casting conforming to designation A6 of IS:617 and shall be tested for all test as per IS:617 c) For connecting equipment Bimetallic connectors made 20 terminals made of copper with ACSR conductors from aluminium alloy casting, conforming to designation A6 of IS 617 with 2mm thick bimetallic liner and shall tested as per IS:617 d) For connecting GI shield wire Galvanised mild steel e) i) Bolts, nuts & plain washer galvanised ii) Spring washers for items 'a' to 'c' i) Electro galvanisation for sizes Plain, washers below M12, for others hot dip galvanised. ii) Electro-galvanised mild steel suitable for at least service condition-3 as per IS: 1573 26.2 Each equipment shall be supplied with the necessary terminals and connectors, as required by the ultimate design for the particular installation. The conductor termination of equipment shall be suitable for Triple/Twin/ single Zebra/ Twin Tarantulla Conductor with 330/250mm Sub Conductor spacing. The requirement regarding external RIV as specified for any equipment shall include its terminal fittings and the equipment shall be factory tested with the connectors in position. If corona rings are required to meet these requirements they shall be considered as part of that equipment and included in the scope of work. 26.3 Where copper to aluminium connections are required, are required, bi-metallic clamps shall be used, which shall be properly designed to ensure that any deterioration of the connection is kept to a minimum and restricted to parts which are not current carrying or subjected to stress. The design details of the joint shall be furnished to the employer by the supplier. 26.4 Low voltage connectors, grounding connectors and accessories for grounding all equipment as specified in each particular case, are also included in the scope of work. 26.5 No current carrying part of any of any clamp shall be less than 12 mm thick. All ferrous parts shall be hot dip galvanised. Copper alloy liner of minimum 2 mm thickness shall be cast integral with aluminium body for Bi-metallic clamps. 26.6 Lateral load deflection test shall be carried out as an acceptance test. The test procedure and accepted norms shall be mutually discussed and agreed to. 26.7 All casting shall be free blow holes, surface blisters, cracks and cavities. All sharp edges and corners shall be blurred and rounded off. 26.8 Clamp shall be designed to carry the same current as the conductor and the temperature rise shall be equal or less than that of the conductor at the 21 specified with respect to the specified reference ambient temperature, shall also be indelibly marked on each component of the clamp/connector, except on the hardware. 26.9 All current carrying parts shall be designed and manufactured to have minimum contact resistance. 26.10 Clamps and connectors shall be designed to be corona controlled. RIV level for 220 kV/ 132 kV system shall not be more then 1000/ micro volts respectively at the specified test voltage as per IS/NEMA. 26.11 TESTS Clamps and connectors shall conform to type tests and shall be subjected to routine tests as per IS:5561. 27. 27.1 CONTROL CABINETS, JUNCTION BOXES, TERMINAL BOXES & MARSHALLING BOXES FOR OUTDOOR EQUIPMENT All type of boxes, cabinets etc. shall generally conform to & be tested in accordance with IS-5039/IS-8623, IEC-439, as applicable, and the clauses given below. 27.2 Control cabinet, junction boxes, Marshalling boxes & terminal boxes shall be made of sheet steel or aluminium and shall be dust, water and vermin proof. Sheet used shall be least 2.0 mm cold rolled or 2.5 mm hot rolled. The box shall be properly braced to prevent wobbling. There shall be sufficient reinforcement to provide level surfaces, resistance to vibrations and rigidity during transportation and installation. In case of aluminum enclosed box the thickness of aluminum shall be such that it provides adequate rigidity and long life as comparable with sheet of specified thickness. 27.3 The enclosures of the control cabinets, junction boxes, terminal boxes &marshalling boxes shall provide a degree of protection of not less than Ip 55 as per IS: 2147 . The bidder shall offer type tested (IP:55) Marshalling kiosk and type test report for degree of protection test each type of box shall be furnished for arrival. After protection degree test of marshalling kiosk, 2.0 kV r.m.s for 1 (one) minute, insulation resistance and functional test should have been conducted. In case these tests have not been carried out during IP55 test, then the contractor shall carry out the IP-55 test alongwith these tests, at his cost. Cabinet/boxes shall be free standing floor mounting type, wall mounting type or pedestal mounting type as per requirements. 27.4 27.5 All door, removable covers and plates shall be gasketed all around with suitably profiled EPDM gaskets. The gasket shall be tested in the presence of Employers representative. The quality of gasket shall be such that it does not get damaged/cracked during the years of the equipment or its major overhaul whichever is earlier. All gasketed surfaces shall be smooth straight and reinforced of necessary to minimize distortion and to make a tight seal. 22 27.6 Ventilating Louvers, if provided, shall have screen and filters. The screen shall be fine wire mesh made of brass or GI wires. All boxes/cabinets shall be designed for the entry of cables from bottom by means of weather proof and dust-proof connection. Boxes and cabinet shall be designed with generous clearances to avoid interference between the wiring entering from below and any terminal blocks or accessories mounted within the base of the marshalling kiosk/box shall be provided for this purpose along with the proper blanking plates. Necessary number of cable glands shall be supplied and fitted on this gland plate. The gland shall project at lest 25mm above gland plate to prevent entry of moisture in cable crutch. Gland plate shall have provision for some future glands to be provided later, if required. The Nickel plated glands shall be dust proof, screw on & double compression type and made of brass. The gland shall have provision for securing armour of the cable separately and shall be provided with earthing tag. The glands shall conform to BS:6121. 27.7 A 240V, single phase, 50Hz, 15 amp AC plug and socket shall be provided the cabinet with ON-OFF switch for connection of hand lamps. Plug and socket shall be of industrial grade. 27.8 For illumination of control cabinet a 20 Watts fluorescent tube or 15 Watts CFL shall be provided. 27.9 All control switches shall be of rotary switch type and Toggle/piano switches shall not be provided. 27.10 EARTHING Positive earthing of the cabinet shall be ensured by providing two separate earthing pads. The earth wire shall be terminated on to the earthing pad and secured by the use of star of self etching washer. Earthing of hinged door shall be done by using a separate earth wire. 27.11 TESTS a) b) The marshalling kiosks shall be subject to routine tests as per 18:5039 The following routine tests shall also be conducted: i) Check for wiring ii) Visual and dimension check Marshalling kiosks shall be provided with danger plate and a diagram showing the numbering/connection/ferruling by pasting the same on the inside of the door. 28. AUXILIARY SWITCHES The auxiliary switch shall confirm to the following type tests: 23 a) Electrical endurance test -A minimum of 2000 operation for 2A DC with a time constant examination of mV drop/visual defects/temperature rise test. b) Mechanical endurance test. A minimum of operations as specified in the relevant ISS with a subsequent checking of contact pressure tesUvisual examination. c) Heat run test on contacts. 29. TERMINAL BLOCKS AND WIRING 29.1 Control and instrument leads from the switchboards or from other equipment will be brought to terminal boxes or control cabinets in conduits. All interphase and external connections to equipment or to control cubicles will be made through terminal blocks. 29.2 Terminal blocks shall be 1100 v grade and have continuous rating to carry the maximum expected current on the terminals. Those shall be of moulded piece complete with insulated barriers stud type terminals, washers, nuts and lock nuts. Screw clamp, overall insulated, insertion type, rail mounted terminals can be used in place of stud type terminals. But preferably the terminal blocks shall be non-disconnecting stud type equivalent to Elmex type CATM4, Phoenix cage clamp type of Wedge or equivalent. The insulating material of terminal block shall be nylon 6.6 which shall be free of halogens, fluorocarbons etc. 29.3 Terminal block for current transformer and voltage transformer secondary leads shall be provided with test links and isolating facilities. The current transformer secondary leads shall also be provided with short circuiting and earthing facilities. 29.4 The terminal shall be that maximum contact area is achieved when a cable is terminated. The terminal shall have a locking characteristic to prevent cable from escaping from the terminal clamp unless it is done intentionally. 29.5 The conducting part in contact with cable shall preferably be tinned or silver plated however Nickel plated copper or zinc plated steel shall also be acceptable. 29.6 The terminal blocks shall be of extensible design. 29.7 The terminal blocks shall have locking arrangement to prevent its escape from the mounting rails. 29.8 The terminal blocks shall be fully enclosed with removable covers of transparent, non deteriorating type plastic material. Insulating barriers shall be provided between the terminal blocks. These barriers shall not hinder the operator from carrying out the wiring without removing the barriers. 24 29.9 Unless otherwise specified terminal blocks shall be suitable for connecting the following conductors on each side. a) All circuits except CT circuits Minimum of 2.5 copper flexible b) All CT circuits copper flexible. Minimum of 4 sq.mm. sq.mm 29.10 The arrangements shall be in such a manner so that it is possible to safely connect or disconnect terminals on live circuits and replace fuse links when the cabinet is live. 29.11 At least 20 % spare terminals shall be provided on each panel/cubicle/box and these spare terminals shall be uniformly distributed on all terminals rows. 29.12 There shall be a minimum clearance of 250 mm between the First/bottom row of terminal block and the associated cable gland plate. Also the clearance between two rows of terminal blocks shall be a minimum of 150 mm. 29.13 The Supplier shall furnish all wire, conduits and terminals for the necessary inter-phase electrical connection (where applicable) as well as between phases and common terminal boxes or control cabinets. The wiring required in these items shall be run in metallic ducts or shielded cables in order to avoid surge over-voltage either transferred though the equipment or due to transients induced from the EHV circuits. 29.14 All input and output terminals of each control cubicle shall be tested for surge withstand capability and transverse modes. The supplier shall also provide all necessary to achieve an impulse withstand level at the cable interfaces of the cable interfaces of equipment. 30. LAMPS AND SOCKETS 30.1 LAMPS All incandescent lamps shall use a socket base as per IS-1258, except in the case of signal lamps. 30.2 SOCKETS All sockets (convenience outlets) shall be suitable to accept both 5 A &15 A pin round Standard Indian plugs. They shall be switched sockets with shutters. 30.3 HAND LAMP A 240 Volts, single phase, 50 Hz AC plug point shall be provided in the interior of each cubicle with ON-OFF Switch for connection of hand lamps. 30.4 INTERIOR LIGHTING 25 Each panel shall be provided with a fluorescent lighting fixture of Standard Indian type or compact fluorescent tube rates for 240 Volts, single phase, 50 Hz supply for the interior illumination of the panel during maintenance. The Fitting shall be controlled by the respective panel door switch. 30.5 SWITCHES AND FUSES 30.5.1 Each control panel shall be provided with necessary arrangements for receiving, distributing, isolating and fusing of DC and AC supplies for various control, signaling, lighting and space heater circuits. The incoming and subcircuits shall be separately provided with switch fuse units. Selection of the main and Sub-circuit fuse rating shall be such as to ensure selective clearance of sub-circuit faults. Potential circuits for relaying and metering shall be protected by fuses. 30.5.2 All fuses be of HRC cartridge type conforming to IS:9228 mounted on plug-in type fuse bases. Miniature circuit breakers with thermal protection and alarm contacts will also be accepted. AII'accessible live connection to fuse bases shall be adequately shrouded. Fuses shall have operation indicators for indicating blown fuse condition. Fuses carrier base shall have imprints of the fuse rating and voltage. 31. BUSHINGS, HOLLOW COLUMN INSULATORS, SUPPORT INSULATORS: 31.1 Bushing shall be manufactured and tested in accordance with IS:2099 &IEC: 137 while hollow column insulators shall manufactured and tested in accordance with IEC 233/18 5621. The support insulators shall be manufactured and tested as per IS 2544/1EC 168 and IEC 273. The Insulators shall also conform to IEC 815 as applicable. The bidder may also offer composite silicon insulator, conforming to IEC-11 09. 31.2 Support insulators, bushings and hollow column insulators shall be manufactured from high quality porcelain. Porcelain used shall be homogeneous, free from lamination, cavities and other flaws or imperfections that might affect the mechanical or dielectric quality and shall be thoroughly vilified tough and impervious to moisture. 31.3 Glazing of the porcelain shall be uniform brown in colour, free from blisters, burrs and similar other defects. 31.4 Support insulators/bushings/hollow column insulators shall be designed to have ample insulation ,mechanical and rigidity for the conditions under which they will be used. 31.5 When operating at rated voltage there shall be no electric discharge between the conductors and busing which would causes corrosion or injury to conductors, insulators or supports by the formation of substances produced by 26 chemical action. No radio interference shall be caused insulators/bushings when operating at the normal rated voltage. by the 31.6 Bushing porcelain shall be robust and capable of withstanding the internal pressures likely to occur in service. The design and location of clamps and the shape and the strength of the porcelain flange securing the bushing to the tank shall be such that there is no risk of fracture. All portions of the assembled porcelain enclosures and support other than gaskets, which may in any way be exposed to the atmosphere shall be composed of completely non hygroscopic material such as metal as metal or glazed porcelain. 31.7 All iron parts shall be hot dip galvanised and all joints shall be air tight. Surface of joints shall be trued up porcelain parts by grinding and metal parts by machining. Insulator/bushing design shall be such as to ensure a uniform compressive pressure on the joints. 31.8 TESTS Bushing hollow column insulators and support insulators shall conform to type tests and shall be subjected to routine tests in accordance with IS:2099 & IS: 2544. 31.9 Technical parameters of bushing/Hollow column insulators/support insulators: 220 kV 132 kV 66 kV 33 kV System System System System 32. a) Rates Volatge (kV) b) 245 145 72.5 36 Inpulse withstand voltage (dry 1050 and wet) (kVp) 650 325 170 c) Power frequency with stand 460 volatge (dry and wet (kV) (rms)) 275 140 80 d) Total creepage distance (mm) ----------------25 mm per KV--------------- e) Pollution Class – III heavy (as per IEC 71) and as specified in section 2 for all class of equipment. f) Insulator shall also meet requirement of and IEC-815 as applicable having alternate long and short sheds. MOTORS Motors shall be "Squirrel Cage" three phase induction motors of sufficient size capable of satisfactory operation for the application and duty as required for the driven equipment and conform to type tests and shall be subjected to 27 routine tests as per applicable standards. The motors shall be of approved make. 32.1 ENCLOSURES a) Motor to be installed outdoor without enclosure shall have hose proof enclosure equivalent to IP 55 as per IS:4691. For motors to be installed indoor Le, inside a box, the motor enclosure, shall be dust proof equivalent to IP 44 as per IS: 4691. b) Two independent earthing points shall be provided on opposite sides of the motor for bolted connection of earthing conductor. c) Motors shall have drain plugs so located that they will drain water resulting from condensation or other causes from all pockets in the motor casing. d) Motor weighing more than 25 kg. shall be provided with eyebolts, lugs or other means to facilitate lifting. 33. RATING PLATES, NAME PLATES AND LABELS a) Each main and auxiliary item of equipment is to have permanently attached to it in a conspicuous position a rating plate of non-corrosive material upon which is to be engraved manufacturer's name, year of manufacture, equipment, type or serial number together with details of loading conditions under which the item of equipment in question has been designed to opera'te and such diagram plates as may be required by the Employer. The rating plate shall conform to lEG requirement. b) All such name plates, instruction plates rating plates etc. shall be in bilingual with Hindi inscription first followed by English. Alternatively, two separate plates one with Hindi & the other with English inscription may be provided. 28 RADIO INTERFERENCE VOLTAGE (RIV) TEST 1. GENERAL Unless otherwise stipulated, all equipment together with its associated connectors, Where applicable, shall be tested for measurement of radio interference voltage (RIV). 2. TEST LEVELS The test voltage levels for measurement of external RIV are listed under the relevant clauses of the specification. 3. TEST METHOD FOR RIV 3.1 RIV tests shall levels for according to measuring as per International SpecialCommittee on ratio Interference (CISPR)Publication 16-1 (1993) Part-1. The measuring circuit shall preferably be tuned to frequency with 10 % of 0.5 MHz but other frequency being recorded. The results shall be in microvolts. 3.2 Alternatively, RIV tests shall be in accordance with NEMA standard Publication No.107-1964, except otherwise noted herein. 3.3 In measurement, RIV, temporary additional external shielding may be provided. In measurements of RIV only standard fitting of identical type supplied with the equipment and a simulation of the connections as used in the actual installation will be permitted in the vicinity within 3.5 meters of terminals. 3.4 Ambient noise shall be measured before and after each series of tests to ensure that there is no ambient noise level. If variation is present, the lowest ambient noise level will form basis for the measurements. RIV levels shall be measured at increasing voltages 85%, 100%, 115% and 130% of the specified RIV test voltage for all equipment unless otherwise specified. 3.5 The metering instruments shall be as per CISPR recommendation or equivalent device so long as it has been used by other testing authorities. 29 LIST OF STANDARDS AND SPECIFICATIONS GENERAL STANDARDS INDIAN ELECTRICITY RULES IS-5 Colors for Ready Mixed Paints and Enamels IS-335 Insulating Oil for Transformers and 8witchgear IS-375 Marketing and Arrangement for Bus-bars, Main Connection & Auxiliary Winding IS-617 Aluminium and Aluminium alloy & Ingots and Castings for General Engineering Purposes IS-1448 Methods of Test for Petroleum and its Products. IS-2071 Measuring Devices IS-2147 Degree of Protection Provided by Enclosures of for Low voltage switch gear and control Gear IS-2165 Phase-to-Phase Insulation Co-ordination, Principles and Rules IS-2362 Determination of Water by the Karl fisher Method IS-3043 Codes of practice for earning IS-3202 Code of Practice for climate proofing of electrical equipment IS-3637 Gas Operated Relays IS-6103 Methods of Test for specific resistance (Resistivity) of Electrical Insulating Liquids IS-6104 Method of Test for Interfacial Tension of Oil against Water by the Ring Method. IS-6262 Method for Determination of Electric strength of insulating liquids. IS-6792 Method for Radio interference Tests on High Voltage Insulators IEC-214 On-Load Tap-Changers IEC-289 Reactors IEC-354 Loading Guide for Oil Immersed power transformers. IEC-551 Determination of Transformer and reactor Sound levels 30 ANSI-C57, 12, 80 General requirements for Distribution, Power and Regulating Transformers. ANSI-C57, 12, 90 Test Code for Distribution, Power and Regulation Transformers. ANSI-C57, 16 Terminology & Test Code for current limiting Reactors. ANSI-C57,21 Requirements Terminology and Test Code for Shunt Reactors Rates over 500 KVA. ANSI-C57, 92 Guide for loading Oil-Immersed Power Transformer upto and including 100 MVA with 55oC or 65oC Winding Rise ANSI-CG, IEEE-4 Standard Techniques for high Voltage Testing NEMA-TR-1 Transformers, Regulators and Reactors IS-4379 Identification of the Contents of Industrial Gas Cylinders CIRCUIT BREAKERS IEC-56 High Voltage Alternating Currenrt Circuit Breakers IS 13118 IEC-427 Synthetic Testing of high voltage alternating current circuit breakers CURRENT TRANSFORMERS, VOLTAGE TRANSFORMERS AND COUPLING CAPACITOR VOLTAGE TRANSFORMERS IS-2705 Current Transformers IS-3156 Voltage Transformers IS-7311 Coupling capacitor and capacitor divider IEC-185 Current transformers IEC-186A Voltage Transformers IEC-186B Coupling capacitors and capacitor dividers IEC-44 Instrument Transformers measurement of Partial discharges IEC-481 Requirements for instrument transformers ANSI-C93.1 Requirements for power line carrier coupling capacitor BUSHING 31 IS-2099 Bushing for alternating Voltages above 1000V IEC-137 Insulated Bushings for Alternating voltages above 1000 V SURGE ARRESTERS IS-3070 Lightning arrestors for alteranting current systems: Metal (part-3) oxide lightning arrestors without gaps. IEC 99-4 Metal oxide urge arresters without gaps CUBICLES AND PANELS & OTHER RELATED EQUIPMENTS IS:722 AC Electricity Meters (P1 to P9) IS 1248 Direct acting indicating anaogne electrical measuring instruments their accessories. IS-722, IS-1248, IS-3231, 3231 (PO-3) Electrical relays for power system protection. IEC-68.2.2 Basic environmental testing proceduresPart 2: Test B: Dry heat IEC-529 Degree of Protection provided by enclosures IEC-158 Low Voltage control gear, contractors IEC-439 Low voltage switchgear and control gear assemblies ANSI-C37.20 Switchgear assemblies, incluidng metal enclosed bus. ANSI-C37.50 Test Procedures for low voltage alternating current power circuit breakers ANSI-C39 Electric Measuring instrument. ANSI-C83 Components for electric equipment IS:8623 Specification for sugar NEMA-AB-Molded Case circuit and systems LT SWITCHGEAR IS:8623 Specification for factory built assemblies of Switchgear & Control gear for voltages upto and including 1000 V AC/ 1200V DC IS:4237 General requirements for switchgear and control gear for ves not exceeding 1000 V. IS-2147 Degree of protection provided by enclosuers for low voltage switchgear and control gear. 32 IS:3202 Conde of practice for climate proofing of electrical equipment. IS:3072 Code of practice for installation and maintenance of switchgear IS:8544 AC motor starters of voltage not exceeding 1000 Volts IS:4064 Air-break switches, air break dis-connctorsm air break dis-connectors and fuse combination unit for voltages not exceeding 1000V AC or 1200V DC. IS:3231 Electrical relays for power system protection. IS:1248 Electricity indicating instruments IS:722 AC Electricty meters. IS:375 Marking and arrangements of bus bars. IS:9224 HRC Cartridge fuses (Part II) IS:6875 Switches and push-buttons IS:6005 Code of practice of phosphating iron and steel IS:5082 Wrought Aluminium and Aluminium alloys for elctrical purposes. DISCONNECTING SWITCHES IEC-129 Alternating Current Dis-connectors (Isolators) and Earthing switches IS-9921 Isolators IEC-265 High voltage switches ANSI-C37.32 Schedule of prefered Ratings, manufacturing specification and application guide of high voltage air swicthes, bus supports and switch accessories. ANSI-C37.34 Test code for high voltage air switches NEMA-SG6 Power switching equipment. PROTECTION AND CONTROL EQUIPMENT IEC-51 Recommendations for Direct acting indicating analogue electrical measuring instruments and their accessories. IEC-255 Electrical relays 33 IEC-297 Dimensions of mechanical structures of the 482.6mm (19 inches) series. IEC-359 Expression of the performance of electrical & electronic measuring equipment. IEC-387 Symbols for Alternating-Current Electricity meters IEC-447 Man machibne interface/ MM-Alternating principles IEC-521 Class 0.5, 1 and 2 alternating current wall hour meters IEC-547 Modular plug-in unit and standard 19-inch rack mounting unit based on NIM standard (for electronic nuclear instruments) ANSI-81 Screw threads. ANSI-B18 Bolts and Nuts ANSI-C37.1 ANSI-C37.2 Relays, Station controls etc. Manual and automatic station control, supervisory and associated telemetering equipment. ANSI-C37.2 Relays and relay system associated with electric power apparatus. ANSI-C39.1 Requirements for electrical analog indicating instrumnets. MOTORS IS-325 IS-4691 Three phase induction motors Degree of protection provided by enclsoure for rotating electrical machinery IEC-34 Rotating electrical machines IEC-68 (P1 to P5) Environmental testing IEC-326 (P1 to P2) Printed boards. MATERIAL AND WORKMANSHIP STANDARDS IS-1363 Hexagon headbolts, screws and nuts of product grade C. IS-1364 Hexagon head bolts, screws and nuts of products grades A and B IS-3138 Hexagonal Bolts and nuts (M42 to M150) IS-898 Fasteners: Bolts, screws and studs 34 CLAMPS AND CONNECTORS IS:2121 Fitting for aluminium and steel cored aluminium conductors for overhead power lines. IS:731 Porcelain insulators for overheadpower line with a nominal voltage than 1000 V IS:2486 Insulator fitting for overhead power lines with a nominal voltage greater than 1000 V IEC-120 Dimensions of Ball and socket couplings of string insulator units. IEC-137 Insulated turning for alternating voltages above 1000 V. IEC-168 Tests on indoor and outdoor post insulators of glass for system with nominal voltages greater than 1000 V. IEC-233 Tests on Hollow insulators for use in electrical equipment. IEC-273 Characteristics of indoor and outdoor post insulators for systems with nominal voltage greater than 1000 V. IEC-305 Insulators for overhead lines with nominal volt above 1000 V-ceramic or glass mull units for AC system characteristics of string insulator units of the cap and pin type. IEC-372 Locking devices for ball and socket couplings of string insulator units dimensions and tests IEC-383 Insulators for overhead lines with a nominal voltage above 1000 V. IEC-433 Characteristics of string insulator units of the long rod type. IEC-471 Dimensions of Clevis and tongue coupling of string insulator units ANSI-C29 Wet Process procelain insulators ANSI-C29.1 Test Methods for electrical power insulators ANSI-C29.2 For insulators, wet-process procelain and toughened glass suspension type. ANSI-C29.8 For wet-process porcelain insulators apparatus, post-type. ANSI-G.8 Iron and steel hardware ASTM A-153 Zinc Coatring (Hot-Dip) on iron and steel hardware 35 STRAIN AND RIGID BUS-CONDUCTOR IS-2678 Dimensions & tolerances for wrought aluminium and aluminium alloys. IS-5082 Wrought aluminium and aluminium alloy bars, Roads, tubes and sections for electrical purposes. ASTM-B 230-82 Aluminium 1350 H19 Wire for eletrical purposes ASTM-B 221-81 Concentric – lay – stranded, aluminium 1350 conductors ASTM-B 221 Aluminium – Alloy extruded bard, road, wire shape. ASTM-B 236-83 Aluminium bars for electrical purpose (Bus-bars) ASTM-B 317-83 Aluminium – Alloy extruded bar, rod, pipe and structural shapes for electrical purposes (Bus Conductors) BATTERY CHARGERS IS:3895 Mono-Crystaline Semiconductor Rectifier Cells and stacks IS:4540 Mono-crystalline semiconductor rectifier assemblies and equipment IS:6619 Safety code for semiconductor rectifier equipment. IS:2026 Power Transformer IS:2959 AC Contractors for voltage not exceeding 1000 Volts IS:1248 Indicating Instruments IS:2208 HRC Fuses IS:4064 Air break switches, air break disconnectors & fuse combination units for voltage not exceeding 1000V Ac or 1200V DC. IS:2147 Degree of protection provided by enclosures for low voltage switchgear and controlgear. IS:6005 Code of practice for phosphating of Iron and steel. IS:3231 Electrical relays for power system protection IS:3842 Electrical relay for AC systems. IS:5 Colors for ready mix paints. 36 BATTERY IS:1651 Stationary Cella and Batteries, Lead-Acid Type (with Tubular Positive Plates). IS:1652 Stationary Cella and Batteries, Lead-Acid Type (with Plant Positive Plates). IS:1146 Rubber and plastic containers for Lead-Acid Batteries IS:6071 Synthetic separators for Lead-Acid batteries. IS:266 Specification for Sulphuric Acid. IS:1069 Specification of water for storage batteries IS:3116 Specification for sealing compound for lead-acid batteries IS:1248 Indicating Instruments WIRE AND CABLES IS-694 PVC insulated cables for working voltages upto and including 1100 Volts. IS-1255 Code of practice for installation and maintenance of power cables upto and including 33 kV rating. IS-1554 PVC insulated (heavy duty) electric cables (part 1) for working voltage upto and including 1100 V Part (2) for working voltage from 3.3 upto including 11 kV. IS-1753 Aluminium conductors for insulated cables IS-2982 Copper conductors in insulated cables and cords. IS-3961 Recommended current rating for cables. IS-3975 Mild steel wires, formed wires and tapes for armouring of cables IS-5831 PVC insulated and sheath of electric cables IS-6380 Elastomeric insulating and sheath of electric cables. IS-7098 Cross linked polythylene insulated PVC sheathed cables for working voltage upto and including 1100 volts. Part (2) Cross-linked polythyle insulated PVC sheathed cables for working voltage from 3.3 kV upto and including 33 kV. 37 IS-8130 Conductors for insulated electrical cables and flexible cords. IS-10418 Specification for drums for electrical cables. IEC-96 Radio Frequency cables IEC-183 Guide to the selection of High Voltage Cables. IEC-189 Low frequency cables and wires with PVC insulation and PVC Sheath IEC-227 Polyvinyl Chloride insulated cables of rated voltages upto and including 450/750 V. IEC-228 Conductors of insulated cables. IEC-230 Implulse tests on cables and their accessories. IEC-287 Calculation of the continuous current rating of cables (100% load factor). IEC-304 Standard colors for insulation for low frequency cables and wires. IEC-331 Fire resisting characteristics of Electric cables.IEC-332 IEC-332 Tests on electric cables under fire conditions IEC-502 Extruded solid dielectric insulated power cable for rates voltages from 1 kV upto 30 kV. IEC-754 Tests on gases evolved during combustion of eledtric cables. NEMA-WC1 Asbestos and asbestos-varnished cloth and asbestosthermoplastic insulated wire and cable NEMA-WC2 Steel armour and associated covering for impregnated paper insulated cables NEMA-WC3 Rubber insulated wire and cable for transmission and distribution of electrical energy. NEMA-WC5 Thermoplastic insulated wire and cable for the transmission and distribution of electric energy. NEMA-WC7 Cross linked thermo setting polyethylene insulated wire and cable for the transmission and distribution of electrical energy. NEMA-WC8 Ethylene-propylene-rubber insulated wire and cable for the transmission and distribution of electrical energy. 38 NEMA-W67 Cross linked thermo setting polyethyle IS-659 Safety code for air conditioning IS-1391 Room air conditioners. IS-6272 Industrial cooling fans. GALVANIZING IS-209 Zinc Ingot. IS-2629 Recommended practice for Hot-Dip galvanizing on iron and steel. IS-2629 Methods for testing uniformity of coating of zinc coating articles. ASTM-a-123 Specification for zinc (Hot galvanizing) coatings on prodicts fabricated from rolled, pressed and forged steel shapes, plates, bars and strips. ASTM-A-153 Speciufication for Zinc coating (Hot Dip) on iron and steel hardware ASTM-A-239 Test method for locating the thinnest. Spot in a Zinc (galvanised) coating on iron and steel articles by the preece test (Copper sulfated dip). FIRE PROTECTION IS-554 Dimensions for pipe threads where pressure tight joints are required on the threads. IS-638 Sheet rubber jointing and rubber insertion jointing. IS-778 Copper alloy gate, globe and check values for water works purposes. IS-780 Sluice valves for water-works purposes(50 to 300 mm size) IS-1536 Centrifugally cast (spun) iron pressure pipes for water gas and sewage. IS-1538(1993) IS-1703(1989) Cast iron fitting for pressure pipes for water gas and sewage. Copper aloy bar values (horizontal plunger type) for water supply fittings. Colour code for identification of pipe lines. Dimensions for pipe threads for fastening purposes. IS-2379(1990) IS-2643 (P1 to P3 : 1990) IS-2685(1992) Code of practice for selection, installation and maintenance of sluice valves. 39 IS-2906(1990) Specification for sluice valves for water works purposes (350 to 1200 mm size) IS-3589(1991) Seamers or eclectically welded steel pipes for water, gas and sewage (168.3 to 2032 mm outside diameter). IS-4038(1990) Foot valves for water works purposes IS-4927(1991) Unlined flax canvas hose for fire fighting. IS-5321-(P1 and P2 1991) - Swing check type reflux (non-return) valves 13095 (1991) Butterfly valves for general purposes STEEL STRUCTURES IS-228 Method of chemical analysis of pig iron, cast iron and plain carbon and low alloy steels. IS-802 Code of practice for use of structural steel in overhead transmission line towers. IS-806 Code of practice for use of steel tubes in general building construction. IS-808 Dimensions for hot rolled steel beam column channel and angle sections. IS-814 Covered electrodes for manual arc welding of carbon manganese steel IS-816 Code of practice for use of metal arc welding for general construction in mild steel. IS-817 Code of practice for training and testing of metal arc welders. Part 1 : Manual metal arc welding IS-875 Code of practice for design loads (other than earthquake) for buildings and structures. IS-1161 Steel tube for structural purposes. IS-1182 Recommended practice for radiographic examination of fusion welded but joints in steel plates. IS-1363 Hexagonal head bolts, screws and nuts of products grade C. IS-1364 Hexagon head bolts, screw & nuts of products grade A and B. 40 IS-1367 Technical supply condition for threaded steel fasteners IS-1599 Method for bend test. IS-1608 Method for tensile testing of steel products. IS-1893 Criteria for earthquake resistant design of structures IS-1978 Line pipe IS-2062 Steel for general structural purposes IS-2595 Code of practice for Radiographic testing IS-3063 Single built rectangular section spring washers for bolts, nuts and screws. IS-3664 Code of practice for ultra sonic pulse echo testing by contact and immersion methods. IS-7205 Safety code for erection of structural steel work. IS-9595 Recommendations for metal arc welding of iron and carbon managese steels. ANSI-B18.2.1 Inch series square and Hexagonal bolts and screws. ANSI-B18.2.2 Square and hexagonal nuts ANSI-G8.14 Round head bolts OTHER CIVIL WORKS STANDARDS IS-269 33 grade ordinary portland cement IS-2721 Galvanized steel chain link fence fabric. IS-278 Galvanized steel barbed wire for fencing IS-383 Coarse and fine aggregates from natural sources for concrete. IS-432 Mild steel and medium tensile steel bars and hard-dawn steel wire for concrete reinforcement IS-456 Code of practice for plain and reinforced concrete. IS-516 Method of test for strngth of concrete IS-800 Code of practice for general construction in steel 41 IS-806 Steel tubes for structural purposes IS-1172 Basic requirements for water supply, drainage and sanitation IS-1199 Method of sampling and analysis of concrete IS-1566 Hard-dawn steel wire fabricated concrete reinforcement IS-1742 Building drainage IS-1785 Plain hard-drawn steel wire for pre stressed concrete IS-1786 High strength deformed and wires for concrete reinforcement IS-1811 Method of sampling Foundry sands. IS-1893 Criteria for earthquake resistant design of structures. IS-2062 Steel for general structural purposes IS-2065 Code of practice for water supply in buildings IS-2090 High tension steel bars used in prestressed concrete IS-2140 Standard galvanised steel wire for fencing IS-2470 Code of practice for installation of septic tanks IS-2514 Concrete vibrating tables IS-2645 Integral cement waterproofing compounds IS-3025 Method of sampling and test physical chemical for water waste water. IS-4091 Code of practice for design and construction of foundations for transmission line tower and poles IS-4111 Code of practice for ancillary structure in sewerage system IS-4990 Plywood for concrete shuttering work IS-5600 Seweage and drainage pimps 42 SECTION-3 CHAPTER-1 TECHNICAL SPECIFICATION FOR 25/31.5 MVA, 66/11 kV POWER TRANSFORMERS 1.0 SCOPE: a) This specification covers the Design, Engineering, manufacture, testing, supply on CIP basis, transportation to site, insurance, storage, testing of 31.5 MVA 66/11 kV Power Transformers. b) All drawings, schedules and annexures appended to this specification shall form part of the specification and supplement the requirements specified. The equipment/materials offered by the bidder shall be complete in all respects and whether called for specifically or not, all accessories, hardware and services required for normal satisfactory operation of the system shall be deemed to be included in unit rates quoted. Design and manufacture shall also be such that equipment/accessories of the same type and rating would be interchangeable. 2.0 Specific reference in this specification and documents to any material by trade name, make or catalogue number shall be construed as establishing standard of quality and performance and not as limiting competition. All equipment/accessories offered shall also be of proven design and manufacture. The make of all accessories and hardware shall be subject to purchaser’s approval. Codes & Standards : All standards, specifications and codes of practice referred to herein shall be the latest editions including all applicable official amendments and revisions as on date of opening of bid. The following standard and codes shall be applicable: IS : 5 Colour for ready mix paints. IS : 325 Three phase induction motors IS : 335 New insulating oils for transformer. BS:148/IEC:296 IS : 375 Marking & arrangement of switch-gear bus bars main connections and auxiliary wiring. IS : 1866 Code of practice for maintenance of insulation oil. IS : 2026 & IEC : 76 Specification Power transformers IS : 2099 & 3347 Bushing for alternative voltages above 1000 volts IS : 2147 Degree of protection provided by enclosures for low voltage switchgear and control gear IS : 2705 Current transformer IS : 3637 Gas operated relay. IS : 3639 Fittings and accessories for Power Transformers IS : 6600 & IEC : 354 Guide for loading of oil immersed transformers IS : 8468 & IEC : 214 On load tap changer. IS : 5561 Electric power connectors IS : 617 Aluminium Alloy grade. IS : 2629 Recommended practice for hot dip galvanising IS : 8478 On load tap changer application guide. IS : 8603 Dimensions for porcelain transformer bushings for use in heavily polluted atmosphere (36 kV Class) Dimensions for oil filled porcelain transformer bushings for use in medium polluted atmosphere. IS : 9434 Guide for sampling and analysis of free and dissolved gas in oil filled equipment. IS : 10028 Code of practice for selection, installation and maintenance of transformers IS : 12676 Dimensions for OIP insulated condenser bushings CBIP Manual on transformer 3.0 4.0 4.1 4.2 4.2.1 4.2.2 4.2.3 4.2.4 4.2.5 4.2.6 4.2.7 4.2.8 4.2.9 Equipment complying with other internationally accepted standard will also be considered if these ensure performance and constructional features equivalent or superior to standard listed above. In such a case, the bidder shall clearly indicate the standards adopted, furnish a copy in English of the latest revision of standard alongwith copies of all official amendments and revisions in force as on date of opening of bid and clearly bring out the salient features for comparison. CLIMATIC CONDITIONS : The transformers are required to operate satisfactorily under the following site conditions: 3.1 Max. Temperature 500 C 3.2 Min. Temperature - 2.50 C 3.3 Max. Relative Humidity 100% 3.4 Min. Relative Humidity 26% 3.5 Average number of rainy days per annum nearly 120 days 3.6 Average annual rainfall 900 m 3.7 Average number of dust storm days per annum 35 3.8 Isoceraunic level 45 3.9 Max. wind pressure 195-kg-sq.m 3.10 Altitude above mean sea level Less than 1000 m. TYPE AND RATING The transformer shall be of two winding 3-phase oil immersed core type with ONAN/ONAF cooling suitable for outdoor service as step down transformers. These transformers shall not be provided with the tertiary delta winding. The ratings and other characteristics which are not covered elsewhere shall be, as detailed in following clauses : Max. continuous capacity : a) ONAN 25 MVA b) ONAF 31.5 MVA Number of phases 3 Frequency 50 Hz s(± 5%) Rated Voltage : a) HV side. 66 kV b) LV side. 11 kV Connections : a) HV side. Star b) LV side. Star Vector group YYO %age Impedance 10% at 31.5 MVA base ON load taps on HV side. a) Insulation level i) Impulse withstand test voltage. ii) Power frequency withstand voltage. b) Insulation level of Bushings. Impulse voltage. Power frequency voltage. 4.2.10 Creepage Distance : a) Total 5.0 5.1 +5% to –15% in steps of 1.25% each 66 kV 11 kV 325 kV (P) 95 kV (P) 140 kV 38 kV (rms) (rms) 325 kV(P) 140 kV (rms) 95 kV(P) 38 kV (rms) 25 mm per kV corresponding to highest system voltage i.e.72.5 kV 50% of the total creepage distance b) Protected GENERAL DESIGN OF TRANSFORMER : The transformer and accessories shall be so designed as to facilitate inspection cleaning and repairs. The requirement of Indian Electricity Rules shall be kept in view. 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 5.10 5.11 5.12 5.13 5.14 5.15 5.16 5.17 5.18 5.19 The design shall ensure satisfactory operation under severe working conditions due to fluctuating load of steel furnaces and voltage variations in the system including those due to short circuits. The transformers shall be designed so as to minimize the risk of accidental short circuits caused by animals, birds or vermins. The design shall incorporate every reasonable precaution and provision for the safety of all those concerned in the operation and maintenance of the equipment keeping in view the requirements of Indian Electricity Rules. All material used shall be of the best quality and of class most suitable for working under specified conditions and shall withstand the atmospheric conditions and temperature variations without undue deterioration or distortion or setting up of undue stress in any part thereof. Cast iron shall not be used for any parts other than the large valve bodies. Corresponding parts liable to be replaced shall be interchangeable. All taper pins to be used in the mechanism shall be split type as per latest edition of IS : 2393. All mechanism should be rust and corrosion proof. Means shall be provided for lubrications of moving parts not immersed in oil. The construction shall be such as to avoid air or water pockets. Special care shall be exercised to reduce noise and vibration to the minimum level. Steel bolts of suitable finish will be used for diameters above 6 mm brass bolts or studs used for electrical connections shall not be of less than 6 mm diameter. On outdoor equipment, all bolts, nuts and washers in contact with current carrying non-ferrous parts shall be phosphor bronze. All nuts, bolts and pins shall be locked except those, which are external to the transformer. If bolts and nuts are so placed as to be inaccessible by means of ordinary spanners, suitable special spanners shall be provided by the supplier. Labels shall be provided for all apparatus like relays, switches, fuses etc. housed in any cubicle or marshalling kiosks. These shall be of in corrodible material with matt/satin finish and permanent lettering. Labels mounted on black surface shall have white letters and danger notices shall have red lettering on a white background. The labels shall be secured by means of brass screws or rust protected steel screws. Surface in contact with oil shall not be galvanized or cadmium plated. Before painting, all un-galvanized parts shall be cleaned, made free from rust, scale and grease and external wrought surfaces smoothened (filled with metal deposition). The interior of the tank and other oil filled chambers shall be cleaned by shot blasting or any other suitable method. All external surfaces shall be given three coats of paints except for nuts, bolts and washers which may be given one coat after assembly transformer at works. The final coat shall be glossy oil and weather proof, non fading paint of shade 631 of IS : 5. The interior of mechanism chambers and kiosks shall be given 3 coats of paint, the final coat being of a light colored anti-condensation mixture. The outer most radial spacers of the winding shall be locked in position by means of vertical strips so that the same cannot fall off/got displaced. Proper & complete tightening of the nuts of the coil clamping bolts must be ensured by the manufacturers. The nuts of all the coil clamping bolts will be tightened to designed value and the job be carried out with torque spanners. The devices used for locking the nuts of coil clamping bolts must be of such a quality and such care should be taken first in tightening the nuts and next in locking them in position so that the arrangement does not become loose due to stresses caused by short circuits and fluctuating loads etc. The noise level shall not be more than 5 dB above NEMA standard publication TR:1. The transformers shall be designed to have short circuit rating of five seconds as per IS:2026. 6.0 7.0 7.1 7.2 7.3 8.0 9.0 10.0 10.1 10.2 10.3 [ 10.4(a) INSULATING OIL : Sufficient insulating oil of Napthenic type (made from Naphthenic crude) in which paraffinic content should be less than 50% and aromatic content 4 to 12% conforming to BS: 148/IEC:296 class-1 shall be supplied for first filling of each transformer. Particular attention shall be paid to deliver the oil at site free from moisture and of uniform quality through out in non-returnable steels drums. The quantity of oil for first filling of each transformer shall be stated in tender along-with trade mark of the oil to be supplied. Use of inhibitors in oil shall not be resorted to. 10% extra oil of the total quantity of oil shall be supplied along with the transformer. LIMIT OF TEMPERATURE RISE With the above climatic conditions, given in clause-3 each transformer shall be capable of operating continuously on any tap at their normal rating without exceeding following temperature rises : i) 350 C in oil by thermometer. ii) 450 C in winding by resistance. iii) Winding gradient i.e. the difference between average winding and average oil temperature not to exceed 130 C. iv) Temperature of hot spot in winding not to exceed 950C when calculated over max. Annual weighted average temperature of 400 C The limits of temperature rise mentioned above will have to be satisfied by the manufacturer by carrying out the heat run test at the lowest negative tap. This test shall be carried out by feeding 1.1 times the total losses at 750 C at highest current tap. OVERLOAD CAPACITY & CONTINUOUS RATING. The safe over load capacity of the transformer and the duration of overload under maximum temperature conditions without any damage to the winding or harmful effects on the insulation shall be clearly stated in the tender which must be as per IEC-354/IS:6600, guide for loading of oil immersed transformer. IMPEDANCE: The transformer shall have 10% impedance on 31.5 MVA base with tolerance as per IS:2026/Part-1 (1983). Impedance shall include positive and zero sequence and shall be expressed in terms of the branches of the star connected equivalent diagram, all on the same kVA base and range shall be given for each branch of the equivalent circuit in turn. The percentage impedance on normal tap should be 10% and on extreme taps i.e at tap No.1 it should be 10.3% and on tap No.17 it should be 9.5%. Percentage tolerance allowed at extreme tap be as applicable to normal tap. FREQUENCY: The transformer shall be suitable for continuous operation with a +/-5% frequency variation from a normal of 50 Hz without exceeding the temperature rise as specified in Clause 7.1 above. FLUX DENSITY, CORE CONSTRUCTION AND INSPECTION The transformer should be so designed that the working flux density should not exceed 1.57 Tesla at normal voltage, frequency. Tenders with higher flux density than specified limit shall not be considered. The core shall be built up with thin laminations of high grade. non-ageing, low loss, high permeability cold rolled super grain oriented silicon steel. Known as MOH High B Grade or superior grade CRGO steels of maximum 0.27 mm or low lamination thickness especially suitable for transformer core. (i)Bidder should have in house core cutting facility for proper monitoring & control on quality and also to avoid any possibility of mixing of prime material with defective/second grade material. The purchaser may witness the core-cutting operation. In case the in house core cutting facility for core cutting is not available then the same shall be carried out in the presence of the representative of HVPN. (ii)Inspection call notice for the purpose should be accompanied with the following documents as applicable as a proof toward use of Prime core materials :a) Invoice of supplier. b) Mills test certificates. c) Packing list. d) Bill of loading. e) Bill of entry certificates by customs. Core material shall be directly procured either from the manufacturer or through their accredited marketing organisation of repute and not through any agent. 10.4(b)After being sheared, the laminations shall be treated to remove all burrs. They shall be coated with a baked enamel insulation coating. The insulation shall be inert to the action of hot transformer oil and shall be perfectly adhesive. Paper and varnish insulation shall not be accepted. Particulars of proposed insulation shall be stated in the tender. Laminations shall be checked for burrs during stage inspection. 10.5 10.6 10.7 10.8 The core shall be rigidly clamped and/or bolted to ensure adequate mechanical strength and to prevent vibrations during operation. The bolts used in the assembly of the core shall be suitably insulated and the clamping structure shall be constructed that the eddy currents will be minimum. Construction of the core shall be such that number of steps in the limb and yoke shall be matching and dimensionally identical to minimize the effect of cross fluxing and better mechanical strength. The core shall be provided with Lugs suitable for lifting the complete core and coil assembly of transformer. The Core & coil shall be fixed in the tank such that its shifting will not occur when the transformer in moved or when a short circuit occurs. The design of magnetic circuit shall be such as to avoid static discharge development of short circuit paths within itself or to the earthing clamping structure and the production of flux components at right angles to the plane of the lamination which may cause local heating. 10.9 Every care shall be exercised in the selection treatment and handling of core steel to ensure that the laminations are flat and that finally assembled core is free from distortions. 10.10 The supporting frame work of the core shall be so designed as to avoid the presence of pockets which would prevent complete emptying of the tank through the drain valve or cause trapping of air during filling. 10.11 Oil ducts where necessary should be formed across the plane of the lamination and be given a suitable slope to assist oil circulation. The overall design of core and winding should be such that free flow of oil is not obstructed. 10.12 The frame work and clamping arrangement shall be earthed by connecting to the tank body through a copper strip. Yoke bolt area should be compensated if bolts are used for fastening of the core. 10.13 The insulation of core to bolts and core to clamp plates shall be able to withstand a voltage of 2 KV RMS for one minute. 10.14 Core and windings shall be capable of withstanding shocks during transport, installation, service and adequate provision shall be made to prevent movement of core and winding relative to tank during these conditions. 10.15 All steel sections used for supporting the core shall be thoroughly sand blasted after cutting drilling and welding. 10.16 All the CRGO vendors having BIS certification and approval from PGCIL shall be considered. 10.17 The tenderers should indicate the maximum flux density allowable continuously as well as for time intervals of 1 minute and 5 secs. and the limit of flux density at which core material used by them saturates. 10.18 The name of the core material must be mentioned in the tender. The successful tenderer shall be required to furnish magnetization curves of the core material/design calculations and such other data/documents deemed fit by the Purchaser for being satisfied that flux density is as desired. 10.19 Purchaser shall inspect the built-up core for verification of flux density for which all facilities shall be provided. The purchaser shall inspect/test the core material for various tests as per relevant IEC/IS to ensure quality. Core may also be inspected during horizontal assembly, built-up assembly. NOTES : i) The above flux density has been specified to meet with the over fluxing of the core due to temporary over voltage of the order of 31% for l min, 44%for 5 sec. that may appear abnormal conditions such as those following sudden loss of large loads. ii) Yoke bolt area and flitch plate areas shall not be counted in the net core area if these are provided for fastening core. iii) The design of limb and yoke shall be so co-ordinate that there is no cross fluxing at the joints. iv) The tenderer shall ensure that the CRGO supplier should have BIS certification. 11.0 SUPPRESSION OF HARMONICS: The transformer shall be so designed as to suppress the harmonics voltage specially the 3rd & 5th, to eliminate wave form distortion and interference with communication circuits due to higher frequency disturbances. Percentage of harmonics at normal voltage and at maximum system voltage shall be stated in the tender. 12.0 WINDING: 12.1 The 66 kV winding shall have graded insulation whereas all other windings shall be fully insulated and the neutral points shall be insulated as amended in IS:2026. 12.2 The transformers shall be capable of operation without danger on any particular tapping at the rated KVA when the voltage may vary by +/- 10% of the voltage corresponding to the tapping. 12.3 The windings and connections as well as the insulations material shall not soften ooze, shrink or collapse during service. 12.4 No strip conductor wound on edge shall have a width exceeding six times its thickness. The conductors shall be transposed at sufficient intervals to minimize eddy currents and equalize the current and temperature distribution along the windings. 12.5 The windings and connections shall be properly brazed to withstand shocks during transportation or transient conditions during service. 12.6 The adequate pre-shrinkage of the coil assembly using pre-compressed press board material having low moisture content for the radial spacer blocks shall be ensured by the manufacturers so that there is no displacement of the radial spacer blocks due to frequent short circuits on the transformers. 12.7 All windings after being wound and all fibrous hygroscopic materials used in the construction of the transformer shall be dried under vacuum and impregnated with hot oil. In addition to this the drying process be sufficiently extended for proper stabilization of the coil assembly. More than one cycle of soaking in oil followed by re-tightening of the coil assembly should be adopted. 12.8 The coil clamping rings wherever used shall preferably be of flat insulated steel laminations. Axial laminated material except bakelised paper shall not be used. 12.9 The clamping arrangement shall exert equal pressure on all columns of spacers of the transformer windings built of sections or disc-coils separated by spacers. In no case, spiral winding will be used either for HV or LV windings. 12.10 The radial spacer blocks must be made of pre-compressed pressboard material. Which will not soften out while in contact with oil or fray out into fibers or edges. The slots should be so dimensioned that the blocks will not come out of the slots. Uniform distribution of coil clamping force shall be designed by using an adequately large number of coil clamping bolts and by transferring the clamping force from clamping bolts to the clamping plates through intermediate members which can spread the clamping force over a large area. 12.11 All joints shall be brazed/crimped considering the vibrations due to short circuits and load fluctuations. 13.0 CURRENT DENSITY: The transformer shall be so designed that the current density at any tap should not exceed 250 Amp./cm. Sq. in HV and regulating winding and 200Amp./cm. Sq. in LV winding. [ The purchaser shall be at liberty to inspect built-up winding for its quality, weight of copper, insulation and overall weight of coil assembly. The size of conductor used for different windings shall also be checked during stage inspection to check the current density vis-à-vis guaranteed values. 14.1 TANK CONSTRUCTION : 14.1.1 The tank shall be fabricated of a suitable grade steel and strong enough to allow the lifting of complete transformer with oil by means of a crane or jacks and transported to site without over-straining the joints etc. 14.1.2 The main tank body shall be capable of withstanding a vacuum of 100.64 kNm2 (760 mm of Hg.) 14.1.3 The base shall be so designed as to allow the transformer to be moved by skidding without any injury. 14.1.4 All channeled constructions and stiffeners shall be designed to avoid retention of water. 14.1.5 The tank construction shall be free of air pockets. Where such pockets cannot be avoided, vent pipes of 15-mm internal diameter shall be provided to vent gases into the main expansion pipes. In case of short branch pipes, however, minimum diameter may be taken as 6mm. 14.1.6 All joints other than those, which may have to be broken, shall be welded. When required they shall be double welded. All bolted joints to the tank shall be fitted with suitable oil tight gaskets, which shall give satisfactory service under the operating conditions and guaranteed temperature rise conditions. Special attention shall be given to the methods of making hot oil tight joints between the tank and the cover and also, between the cover and the bushings and all other out-lets to ensure that the joints can be remade satisfactorily at site and with ease by semi-skilled labour. 14.1.7 Suitable lifting lugs for lifting the transformer filled with oil shall be provided on the tank. 14.1.8 Four jacking lugs shall be provided to enable the transformer complete with oil to be lifted or lowered by means of jacks. The lugs shall be fitted at a minimum height (excluding under base if detachable) of 300mm for transformer upto 10 tonnes weight and of 500 mm for transformer above 10 tonnes weights. 14.1.9 The transformer shall be provided with detachable steel flanged wheels of 250 mm dia and suitable for moving transformer complete with oil. These shall be bi-directional and mounted on swivels which may be turned through 900 when the tank is jacked up and capable of being locked in position paralled to and at right angles to the longitudinal axis. The wheel be suitable for standard gauge track of 1676mm. 14.1.10 The Transformer tank should be designed in such a way that over all length of transformer does not exceed 7 meters. 14.2 TANK COVER: 14.2.1 The tank cover shall be of bolted type and of adequate strength so as not to distort, when lifted. Suitable inspection cover shall be provided with lifting arrangements to give access to bushings, winding connections or testing the earth connections. The weight of each inspection cover shall not exceed 25 Kg. 14.2.2 Pockets shall be provided in the position of Max. oil temperature at CMR for fitting a thermometer and for bolts of oil and winding temperature indicators. The thermometer pockets shall be fitted with a captive screwed cap to prevent ingress of water. 14.2.3 Suitable No. of jacking bolts shall be provided on tank cover, inspection covers/windows including OLTC. 14.3 CONSERVATOR TANK, OIL GUAGE AND BREATHER : 14.3.1 An adequate conservator tank complete with sump and drain valves shall be provided in such a position as not to obstruct the electrical connections to the transformer. 14.3.2 If the sump is formed by extending the feed pipe inside the conservator, this extension shall be atleast 25mm. 14.3.3 One end of the conservator shall be bolted type to facilitate cleaning. 14.3.4 The conservator shall be provided with a magnetic oil level gauge. 14.3.5 The oil connections from the transformer tank to the conservator shall be at rising angle of 3 to 9 degrees to the horizontal upto Buchholz relay. The inside diameter of the pipe shall be 80 mm. the buchholz relay will have suitable valves on its both side so as to facilitate its testing at site as well as cut off oil supply to the transformer. 14.3.6 The conservator shall be provided with oil preservation system, which should be suitable either to remove moisture continuously from air entering the air space with which they are connected or may not allow direct contact of atmospheric air with oil during operation, in addition to silica gel breather. 14.4 VALVES: 14.4.1 The transformers shall be provided with a filter valve of 50 mm size mounted on top of the main tank oil circulations and one drain valve of 80 mm size with plug. The conservator shall have drain plug of 25 mm size. 14.4.2 Three robust sampling valves with spouts suitable for taking samples of top middle and bottom oil shall be provided. The top and middle sampling valves shall be brought down by internal pipe connections. Suitable nameplates shall be affixed to the sampling valves. The sampling device shall not be fitted on the filter valve. 14.4.3 Two – air release plug of 15 mm shall be provided. 14.4.4 Plugs shall be supplied for all valves opening to atmosphere. 14.4.5 All valves shall comply with the latest edition of IS:3639. 14.5 PRESSURE RELIEF DEVICES:A suitable pressure relief device of 6” dia shall be provided on the main tank and of 3” dia shall be provided on OLTC for rapid release of any pressure in transformers which may endanger the equipment. The device(s) shall operate at static pressure of less than hydraulic test pressure for transformers tank OLTC chamber. If the device is mounted on tank cover, it shall be fitted with a skirt projecting 25 mm inside the tank and of such construction as to avoid gas accumulation. In addition to pressure relief device(s) the provision of explosion vent should also be made and the diaphragm shall be situated above max. oil level. 14.6 EARTHING TERMINAL:14.6.1 Two earthing pads suitable for connecting 50x8 mm mild steel flat shall be provided at positions close to the two diagonally opposite bottom corners of tank. These grounding terminal shall be suitable for bolted connection. Two earthing terminal shall also be provided each on marshalling box an any other equipment mounted separately. 14.7 JOINTS AND GASKETS:14.7.1 All gaskets used for making oil tight joints shall be of granulated cork bonded with synthetic rubber. Metal tops shall be provided for preventing over compression wherever compressible gaskets are provided. 14.8 RATING AND DIAGRAM PLATES:14.8.1 Each transformer shall carry a diagram plate showing internal connections, voltage vector relationship of different windings, plan view of the transformers showing physical relationship of the terminals and no load voltage for each tap. 14.8.2 Each transformers shall be provided with a rating plate & diagram as specified in IS:2026. 14.8.3 I. R. values along with oil temperature at the time of testing at manufacturer’s works shall be indicated on rating plate or separate plate, to be provided on transformers. 14.9 THERMOSYPHON FILTER ARRANGEMENT Thermosyphon filter arrangement shall be provided on the transformer for preserving the quality of Transformer Oil. The filter assembly shall be mounted on the Transformer as well as ground supported and connected with pipes and shut off valves. Suitable instructions required to be followed for commissioning, dismantlement & maintenance of the filter arrangement, re-generation and storage of the adsorbent etc. must be included in the instruction manual. A detailed drawing showing internal arrangement, shall also be required to be submitted. Suitable capacity pump (alongwith motor) shall also be provided to boost circulation of oil. The pump and motor should not be in main pipe line. It should be in bypass pipe line having suitable valve to isolate from main pipe line. The main pipe line should have two shut off valves at the bottom. NOTE : The pump and motor should be weather proof(Flow well Type). The oil & sorbent capacity required in the Thermosyphon Filter is as under: (i) Quantity of oil 2.0% of total oil by weight. (ii) Quantity of adsorbent 1.25% of total oil by weight. 15.0 15.1 COOLING PLANT:Detachable radiators shall be fitted on the main tank with machined flanged outlet and inlet. Each radiator shall be provided with 19 mm drain plug at bottom and 19 mm air release plug at the top. Valves shall be provided on the tank at each point of connection to radiators. 15.2 In case separate cooler banks are used, they shall be suitable for mounting on a flat concrete base. These shall be provided with a valve (25mm) at each point of connection to the transformers tank, removable blanking plates to blank off main oil connections to each cooler. Thermometer pockets with captive screwed cap at inlet and outlet of each separate cooler, filter value at top and bottom and air release plug of 15 mm shall be provided. 15.3 The motor blowers shall be direct driven suitable for continuous out door operation and complete with necessary air dusting. These shall be mounted independently from the radiator and in case, these are radiator mounting type use shall be made of some anti-vibration means. Care shall be taken that the lower unit is capable of being removed without disturbing the radiator structure. The blades shall be suitably painted and shall not be of hollow sections. Suitably painted wire mesh guards with mesh not greater than 25 mm shall be provided to prevent accidental contact with the blades. 15.4 MOTORS:15.4.1 The motor shall be squirrel cage totally enclosed weatherproof type suitable for direct starting and for continuous running from 415/240 volts, three phase/single phase 50 HZ supply. The motors shall comply with IS as applicable for continuous rated machine. 15.4.2 All motors shall be capable of continuous operation at frequency 50 Hz with variation of “5% and 415/240 V AC” 10% variation of the normal voltage without injurious over heating. 15.4.3 All motors shall have ball or roller bearing with hexagonal nipples for greasing. In case of vertical spindle, motor shall have bearing capable of withstanding thrust, due to weight of the moving parts. 15.4.4 Varnished cambric or glass insulator shall be used for connections from stator winding to the terminal suitable for external wiring. The motor terminals shall be of stud type and totally enclosed. 15.5 COOLER CONTROL:15.5.1 Each motor or group of motors shall be provided with a 3 pole electrically operated contractor with control gear for motor operation by hand and automatically through winding temperature indicator. Provision shall be made for over load protection but no volt release coil shall not be provided. 15.5.2 All connection shall be so arranged as to allow either individual or collective operation of the motors. Alarm indication (audio and visual) for failure of fans and to indicate failure of power supply shall be provided. 15.5.3 The control equipment shall be installed in the marshalling box as specified in CL:23 in a readily accessible position. 15.5.4 The alarm indication for failure of power supply and failure of individual fans be provided through independent non trip alarm scheme to be wired on the remote tap change control cubicle conforming to the following:i. The closing of an initiating contact shall actuate a buzzer and will be accompanied by a flag indication on the concerned auxiliary relay. ii. The closing of an initiating contact shall glow a lamp, which will not reset until the fault has been cleared. iii. It shall be possible to silence the buzzer by pressing ‘Accept’ push button. If, after canceling the alarm but before resetting the visual signal, the same fault persists the buzzer shall be suppressed. iv. If after canceling the alarm but before resetting the visual signal, some other fault takes place, the alarm accompanied by flat indication on appropriate auxiliary relay shall take place. v. If after canceling the alarm and after resetting the visual signal, the same fault appears or some other fault take place, the alarm, flag indication and non-trip lamp indication shall reappear as usual. vi. The non-trip alarm acceptance shall be by means of push button and resetting of visual signal may also preferably be done through a push button. vii. Means shall be provided for test checking the lamp and alarm circuit at frequent intervals. viii. The equipment shall be suitable for 220 Volt DC operation. Static facia annunciator conforming to the foregoing requirements of non-trip alarm scheme too would be acceptable. 16.0 VOLTAGE CONTROL (ON LOAD TYPE) : 16.1 The transformers shall be provided with voltage control equipment of the tap changing type for varying its effective transformation ratio while the transformers are on loan and without producing phase displacement. 16.2 Equipment for ‘local’ an ‘remote’ electrical and ‘local’ manual operation shall be provided and shall comply with the following conditions. Local/remote switch may be housed in remote control panel or in tap changer drive mechanism. 16.2.1 It shall not be possible to operate the electric drive when the manual operating gear in use. 16.2.2 It shall not be possible for any two electric controls to be in operation at the same time. 16.2.3 The equipment suitable for supervisory control and indication on a multi way switch, makebefore break having one fixed contact for each tap position, shall be provided and wired to the tap changer drive gear. This switch shall be provided in addition to any, which may be required for remote tap change position indication purpose. Supervisory indication shall also be provided in the form of contacts to close on. “Tap change incomplete” condition. All other components of the supervisory gear, if required be specified separately. 16.2.4 Operation from the local or remote control switch shall cause one tap movement only. The control switch shall be returned to the ‘neutral’ position between successive operations. 16.2.5 All Electrical control switches on the local operation gear shall be clearly labeled in a suitable manner to indicate the direction of tap changing. 16.2.6 The local control switches shall be mounted, in the drive gear housing. 16.3 The equipment shall be so arranged as to ensure that when a tap change has commenced, it shall be competed independent to the operation of the control relays or switches. In case of failure of the auxiliary supply while the tap change is in progress or any other contingency such as stuck tap changer, adequate means shall be provided to safe guard the transformers and its auxiliary equipment. 16.4 Suitable apparatus shall be provided for each transformer to give indications as follows:16.4.1 To give indication, mechanically at the transformer and electrically at the remote control cubicle of the position of tap in use. 16.4.2 To give an indication at the remote control cubicle that a tap change is in progress, by means of an illuminated lamp. 16.5 For remote control, the switches, tap position indicator, etc shall be supplied duly mounted on remote control cubicle. 16.6 All relays and operating devices shall be operated correctly at any voltage between the limits specified in the relevant ISS. 16.7 The tap changing mechanism shall be mounted in the oil tank or compartment mounted in an accessible position on the transformer. 16.8 Any non-oil filled compartment shall be adequately ventilated, Thermostatically controlled heaters shall be provided in the driving mechanism chamber and in the marshalling box. All contactors & auxiliary relay coils or other parts shall be suitably protected against corrosion or deterioration due to condensation, fungi etc. 16.9 The tap changer contacts which are not used for making or breaking current like separate selector switch contacts inside main transformer tank where tap changer construction permits such as arrangement. In case of on load tap changer having separate compartment for selector contacts the oil in such compartment shall be maintained under conservator head by means of pipe connection from the highest point of the chamber to the conservator. Such pipe connection shall be controlled by suitable valve and shall be arranged so that any gas leaving the chamber will pass into the gas oil actuated relay. A separate buchholz relay may be provided for this compartment. 16.10 It shall not be possible for the oil in these compartments of the tap change equipment which contain contacts used for making or breaking current, to mix with the oil in the compartments containing contacts and not used for making or breaking current. 16.11 Any ‘DROP DOWN’ tanks associated with the tap changing apparatus shall be fitted with guide rods to control the movement during lifting or lowering operations. The guide rods shall be so designed as to take support of the associated tank when in the fully lowered position with oil. Lifting gear fitted to ‘Drop Down’ tanks shall include suitable device to prevent runaway during lifting & lowering operations. They shall be provided with adequate breathing arrangement. The tap changer shall be mounted in such a way that the cover of the transformer can be lifted without removing connections between windings and tap changer. 16.12 Each compartment in which the oil is not maintained under conservator head shall be provided with a suitable direct reading oil gauge. 16.13 The alternating supply for electrical operation of the control and indicating gear shall be standard 415 Volts, three-phase, 3 Wire, 50 HZ. alongwith 240 Volts single phase, 2 wire 50 HZ, subject to a variation of + 5 percent so that the equipment offered can withstand variation in AC. 16.14 Limit switches shall be provided to prevent over-running of the mechanism and except where modified in clause 16.15 shall be directly connected in the circuit of the operating motor. In addition a mechanical stopper or other approved device shall be provided to prevent overrunning of the mechanism under any condition. 16.15 Limit switches may be connected in the control circuit of the operating motor provided that a mechanical de-clutching mechanism is incorporated. 16.16 Thermal devices or other means like motor circuit breakers with shunt trip coil shall be provided to protect the motor and control circuits. All relays, switches, fuses, etc. shall be mounted in the marshalling box or driving gear housing. These shall be clearly marked for purpose of identification. They shall withstand the viberation associated with tap changer gear operation. 16.17 The control circuits shall operate at 110V single phase to be supplied from a transformer having a ratio of 415 0r 240/55-0-55 V with the center point earthed through a removable link mounted in tap changer drive. 16.18 The whole of the apparatus shall be of robust design and capable of giving satisfactory service under conditions to be met in service including frequent operation. 16.19 A five-digit counter shall be fitted to the tap changing mechanism to indicate the number of operations completed by the equipment. 16.20 A permanently legible lubrication chart shall be fitted within the driving mechanism chamber, where applicable. 16.21 The indigenous make OLTC (Internal/External) suitable for 66 kV voltage class & current rating 350 Amp. should be duly. Type tested from CPRI or other Govt. Test House or reputed lab abroad to the extent the facilities of Type test available in CPRI. 17.0 PARALLEL OPERATION: 17.1 In addition to individual control of tap changer, provision shall be made to enable parallel operation of the tap changer when one unit is running in parallel with another similar unit of same rating. 17.2 Suitable selector switch and controls shall be provided so that any transformer of the group can at a time be selected as master, follower or independent. Arrangement shall be made that only one of the transformers can be selected as master at a time. 17.3 An out of step device shall an indicating lamp be provided for each transformer indicating out of step condition by an indicating lamp and buzzer. It shall be arranged to prevent further tap changing when transformers in a group operating in parallel control are one tap out of step. 18.0 BUSHING INSULATORS AND TERMINALS: 18.1 Transformer shall be fitted with bushing insulators as follows:L.V. Bushing: 36kV class oil communicating type porcelain bushing of 2000 Amp. rating with suitable arcing horns. LV-N Bushing: 36kV class oil communicating type porcelain bushing of 2000 Amp. rating but without arcing horns. HV Bushing: 72.5 kV class. Condenser bushing of 800 Amp. rating with arcing horns. HV-N Bushing: 36kV class oil communicating type porcelain bushing of 630 Amp. rating but without arcing horns. 18.2 18.3 18.4 18.5 18.6 18.7 18.8 19.0 19.1 19.2 19.3 19.4 19.5 19.6 19.7 20.0 20.1 20.2 The characteristics of the bushings shall be in accordance with IS: 2099 and IS: 3347. The bushing insulators except for neutral bushing shall be provided with adjustable arcing horns and the bidder shall furnish calibration gap to decide actual gap setting. A continuous flexible pull through lead suitably sweated to the end of winding copper shall be connected to the connector in the helmet of the 66 kV Bushing. The bushings may be filled with oil, which may not be in communication with the oil in transformer. All porcelain shall be free from defects and thoroughly vitrified with a smooth, hard and uniform brown glaze. It should be capable of satisfactory use under the climatic conditions as specified in clause-3.0. In case of paper insulation care shall be taken to prevent ingress of moisture and a final coat of non-hygroscopic varnish shall be given to them. All clamps and fittings made of malleable iron or steel shall be galvanized as per IS: 2629. The bushing flanges shall not be of re-entrant shape, which may trap air. Bi-metallic terminal connectors shall be supplied suitable for single 0.4 Sq. inch ACSR Zebra conductor for HV side, LV Neutral & HV Neutral. For LV side the terminal connectors shall be suitable for triple 0.4 sq. inch ACSR ZEBRA conductor. The take off for H.V & L.V connectors will be Vertical and for H.V Neutral and L.V. Neutral, it should be suitable for horizontal take off. The connectors shall have six number bolts provided with check nuts & washers. The connectors shall have rating corresponding to those equipment or higher and shall be designed most liberally with a higher factor of safety to comply in all respects with temperatures rise. Resistance, tensile strength short-circuit withstand capability tests as specified in IS: 5561-1970 or amendment thereof (Latest edition). Aluminum alloy used in the manufacture of bimetallic connectors shall conform to designation Grade 4600 of IS: 6171975. The steel bolts, nuts washers and check nuts shall be hot dip galvanized marked with ISI certification mark or of GKW make. TEMPERATURE INDICATING DEVICES: All transformers shall be provided with a dial type thermometer for indicating oil temperature. The indicator shall be fitted with a pointer to register maximum temp recorded and adjustable set of mercury contact for alarm and trip. In addition, all the transformer shall be provided with a dial type Hot Spot winding temperature indicator in HV and LV winding. The indicator shall have a pointer to register maximum temperature reached and four sets of adjustable mercury contacts for alarm trip for automatic control of fans. The static remote repeater (for winding temperature indicator) suitable for flush mounting shall be installed on remote tap change control cubicle. The temperature indicators shall be housed in marshalling box. The alarm (mercury) contact of WTI & OTI shall be adjustable between 500C to 1000C where as their trip (mercury) contacts shall be adjustable between 600C and 1200C. The temperature differential between opening & closing of these mercury contacts shall not be more than 100C. The mercury contacts used for controlling cooling plant motors shall be adjustable to close between 500C and 1000C. The temperature differential between opening & closing of this mercury contact shall be between 100C to 150C. All contacts should be accessible on removal of the cover adjustable to scale. It shall also be possible to move the pointers by hand for checking the operation of contacts and associated equipment. In addition each transformer shall be provided with a dial type thermometer for indicating the ambient temperature. GAS AND OIL ACTUATED RELAYS: The transformer shall be provided with a gas and oil actuated relay fitted with alarm and trip contacts for main tank & a oil surge relay for its OLTC as per IS 3637. Each such relay shall be provided with a test cock to take a flexible connection for checking relay operation. 20.3 20.4 20.5 21.0 21.1 21.2 21.3 21.4 21.5 22.0 22.1 22.2 22.3 22.4 22.5 22.6 22.7 23.0 A machined surface shall be provided on top of checking mounting angles in the pipe crosslevel of relay and its setting. The pipe work shall be such as to allow any gas formed in the tank to pass through the relay. The oil circuit through the relay shall not form a parallel delivery path with any circulating oil pipe, nor shall be tied into or connected through the pressure relief vent. Adequate clearance between oil pipe work and live metal parts shall be provided. MARSHALING BOX: A sheet steel (of 10 SWG size) vermin proof well ventilated and weather proof marshaling box of suitable construction shall be provided for the transformer auxiliary apparatus. The box shall have domed or sloping roofs. Ventilation louvers, suitably padded with felt shall also be provided. It shall be painted as per Cl.5.14. The marshaling box shall accommodate temperature indicators. Local electrical control of tap changer (if same cannot be housed in motor drive housing.), control & protection equipment for cooling plant, terminal boards and gland plants for cable etc. The equipment shall be mounted on panels and panels wiring shall be done at the back for interconnections. The temperature indicators shall be mounted at about 1600mm from ground level. A metal clad heater with thermostat, controlled by a waterproof rotary switch on the outside of the both, shall be provided. The incoming cables shall enter from the bottom with gland plate not less than 450mm from the base of the box. Care shall be taken to avoid ingress of water from the cable trench. CONTROL CONNECTIONS, INSTRUMENTS WIRING, TERMINAL BOARD AND FUSES: All cables and wiring shall be suitable for use under the conditions as specified in Clause 3.0. Any wiring liable to come in contact with oil shall be of oil resisting insulation. The bare ends of stranded wire shall be sweated together to prevent oil from creeping along the wire. The instrument and panel wiring shall be run in PVC or non-rusting metal cleats of limited compression type. The box wiring shall be as per relevant ISS. All wiring shall be of stranded copper of 660V grade and size not less than 4 sq. mm. For CT leads and not less than 2.5 sq. mm. for other connections. The panels wires and multi core cable shall bear ferrules of white insulation material with indelible marking in black and as per relevant ISS. Same ferrule number shall not be used on wires in different circuits. Double ferrules may be provided where a change in number is required. Stranded wires shall be terminated with tinned Ross Courtney terminals, washers or crimped tubular lugs. Separate washers shall be used for each wire. Wire shall not be jointed/tied between terminal points. Where apparatus is mounted on panels all metal cases shall be separately earthed by copper wire of strip not less than 2.5 sq. mm. The screens of screened pairs of multi core cables shall be earthed at one end of the cable only. All terminal boards shall be of stud-type & mounted obliquely towards the rear door and these boards shall be spaced not less than 100mm apart. Suitable insulation barriers shall be provided between adjacent connections. No live metal shall be exposed at the back of terminal boards. All fuses shall be of cartridge type and fuses and links shall be properly labelled. EQUALIZATION FORMULA: The losses at principal tap of each transformer shall be stated in the tender ONAF rating at full load at 750C. For the purpose of arriving at comparable prices, the iron, copper and auxiliary losses shall be capitalised as per capitalization formula given below: =3,86,700( Wi + 0.45 Wc + 0.45 Wp) Where Wi = Iron (No load) Losses Wc = Copper (Load Losses) Wp = Auxiliary Losses The maximum sealing of component and weightage average losses shall be as per clause 24.0 and no positive tolerance shall be allowed on these values In case losses of the T/F are found to be higher then the specified values at any stage within three years from the date of commissioning the capaitalized value of excess losses, as compare to the specified value shall be recovered as per following capitalization formula:Amount recoverable (Rs.)= 3,86,700(Wi + 0.45 Wc + 0.45Wp) 24.0 Losses:The losses of each transformer shall be stated in the tender for OFAF rating at principal tap (at full load at 75 deg. C) which shall be less than:Sr. No. 1 2 3 4 24.1 Type of Losses No Load Losses Load Losses Auxiliary Losses Maximum weighted average losses 31.5 MVA, 66/11 KV T/F 17.70 KW (Max) 118.00 KW(Max) 2.00 KW (Max) 65KW Noise level : 80 dB Transformer offers shall be rejected if audible sound level is higher than max. 80 dB. 25.0 25.1 TESTS: ROUTINE TESTS: All routine tests shall be carried out on each transformer as per IS-2026/IEC-76. 25.2 TYPE TEST: Following type tests and over load withstand capacity test (as per IEC-354) shall be carried out on one of units ordered on the successful bidder as per IEC-76/ISS:2026. i. Temp. rise test (Along with DGA test before and after temp. rise test). ii. Impulse voltage withstand test with chopped impulse on any one phase. iii. Power drawn by cooling fans/oil pumps as perISS:2026. 25.3 In addition, the following tests shall be carried out on the transformer tank. 25.3.1 OIL LEAKAGE TEST: All tanks and oil filled compartments shall be tested for oil tightness by being completely filled with oil of viscosity not greater than that of insulating oil to IS:335 at ambient temperature and subjected to a pressure equal to normal pressure plus 35KN/M2 (5Ibs/Sq. inch.) measured at the base of the tank. This pressure shall be maintained for period not less than 12 hours, during which period no leakage shall occur. 25.3.2 Following tests shall be carried out on each Transformer as reference test. i) Measurement of tan delta and capacitance of T/F Winding and bushings at 5 kV & 10 kV. ii) Magnetic balance test. iii) Magnetising current at low voltage. iv) Measurement of percentage impedance at all taps at low voltage. 25.3.3 TRANSFORMER OIL: Sufficient quantity (along with 10% extra) of insulating oil of napthenic type (as per Clause-6 of specification) conforming to BS:148/IEC-296 Class-1 shall be put up for inspection, at least 3 weeks before putting up the transformer for testing/inspection, at sub-supplier works as per IS:335/BS/IEC. One sample of the oil shall also be got tested from CPRI or any other Govt. approved testing house. The inspected oil shall be dispatched to site as per dispatch instructions of purchaser. 25.3.4 SHORT CIRCUIT TEST Short circuit test in accordance with latest IS-2026 Part (5) clause 4.2, IEC-60076-5 and CEA regulation-2010 shall be got conducted on one of the units of each voltage and capacity at any test Agencies where facilities exist in the presence of Purchaser's representative. However, in case of those manufacturers who have already got short circuit test in accordance with Cl. 4.2 of IS-2026 Part(5) or latest edition conducted during the last 7 years on same design and capacity of the Transformer, fresh short circuit test is not required to be conducted. The bidder in such a case shall submit the copy of type test report along with the bid. If this test is not conducted by the firm earlier, then charges for this test shall be borne by the bidder. The warranty in case of Power Transformer shall be 18 months from the date of commissioning or 24 months from the date of receipt whichever is earlier. All other stipulations of Warranty Clause as per Schedule-D of purchase regulation shall remain same 25.3.5 The purchaser reserves the right to have any other, reasonable test carried out at his expense either before shipment or at site to ensure that the transformer complies with the requirement of this specification. 25.4 STAGE INSPECTION : Stage inspection of built up core (in horizontal/vertical position), windings, tank and radiators shall be carried-out as detailed below:a. CORE: i. Measurement of flux Density. ii. No Load Loss Measurement by providing dummy oils. iii. Tests of CRGO sample taken from the core shall be carried-out for Carlite test (Resistance Measurement), Watt Loss Test, Lamination Thickness & Aging Tests. iv. Physical inspection for quality of workmanship. v. Slitting/Cutting of core. b. WINDINGS : i. Measurement of cross-sectional area for current density. ii. Measurement of weight of bare copper/cover by resistance methods. iii. The purity test of copper for winding shall be got conducted on sample of copper for assessing its quality, from two independent NABL accredited laboratories. c. TANK : i. Vacuum Test One transformer tank out of the lot shall be subjected to vacuum pressure of 100.64 kN (760 mm of Hg.). the tanks to be designed for full vacuum shall be tested at an internal pressure of 3.33 KN/M2 (25mm of Hg.) for one hour. The permanent deflection of flat plates after the vacuum has been released shall not exceed the values given below without affecting the performance of the transformer. Horizontal length of flat plate(mm). Permanent deflection (mm) Upto & including 750 5.0 751-1250 6.5 1251-1750 8.0 1751-2000 9.5 2001-2250 11.0 2251-2500 12.5 2501-3000 16.0 above 3000 19.0 ii. d. NOTE: a. b. c. d. 26.0 26.1 26.1.1. 26.1.2 26.2 PRESSURE TEST: One transformer out of the lot shall be subjected to the pressure corresponding to twice the normal head of oil or normal pressure plus 35KN/M2 (which ever is lower) measured at the base of the tank and maintained for one hour. The permanent deflection of flat plates after removal of excess pressure shall not exceed the figures specified as above. RADIATORS: Radiators shall be routine type tested at sub-supplier’s works as per relevant standard. Test reports are required to be supplied at the time of final inspection. The insulation resistance values of the transformer windings will be recorded at the time of carrying out routine tests, for 20 seconds, one minute, two minutes with the help of 5000V motorised meggar (preferably EVERSHED/AVO & VIGNOLE MAKE). The polarisation index values (ratio of 120/20-Sec. Value) will be accordingly calculated and recorded in the test certificates and it should not be less than 1.5. Dissolved gas analysis test shall be got carried out before and after heat run test at CPRI Bangalore. Capacitance and Tan Delta values for each transformer and condenser bushings will be taken and recorded in the test certificates at 5 kV & 10 kV. Insulation resistance value of condenser bushings shall also be recorded. Lightening impulse test with the chopped wave applications as per clause 13 of IS:2026/1981 (Part-III) amended upto date. This test will be carried out on one of the limbs of HV and LV winding with positive polarity. e. The tenderer should clearly indicate the testing facilities available with them and tests, which are to be arranged outside. Supplier shall submit in-house test certificates at lest 15 days in advance for final testing of T/F. for testing T/F: all measuring instruments shall be of highest efficiency and best quality. These shall be got calibrated from NPL/Govt. Agency and be got sealed by calibrating agency. HVPN reserves the right to calibrate the instruments in the manner it desires. Losses shall be measured with 3-wattmeter method only. Resistance shall be taken with Double-Kelvin Bridge. Losses can be measured directly from CTs and PTs and not through the panel. Ratio of the measuring instrument shall be such that the multiplying factor is the minimum. All tests shall be carried out in the presence of the purchaser before despatching the material. Test certificates in quadruplicate will be submitted to the purchaser for approval. No material shall be despatched without prior inspection and approval of test certificates unless otherwise agreed to. Type and routine test certificates of all bought out items from recognised testing agency shall be submitted for approval before commencing supplies. OLTC scheme including the master follower functioning shall also be checked. Only fully assembled transformer including mounting of radiators shall be put-up for inspection. DRAWINGS: The following drawings shall be supplied as part of the tender. Outline dimensional drawing of transformer and accessories. Bushing and terminal connectors drawings. The successful bidder shall submit final version of drawings complete in all respects in quadruplicate within 15 days of placement of order for purchaser's approval. The purchaser shall communicate his comments/ approval on the drawings to the supplier within one month of their receipt. The manufacturer shall, if so required by the purchaser, modify the drawings and resubmit the same for purchaser's approval within two weeks of receipt of comments. Such duly revised drawings will be approved by the purchaser within two weeks of their receipt. After receipt of purchaser's approval to drawings, the manufacturer will submit five sets of all approved drawings and five sets of manual of instructions to our Design Office. 26.2.1 a. b. c. d. e. f. g. h. 26.2.2 26.2.3 26.2.4 26.2.5 26.2.6 26.2.7 26.2.8 26.2.9 26.2.10 26.2.11 One set of all the approved drawings and manual of instructions will be supplied along with each equipment without which the supply will not be considered as complete supply. Outline general arrangement drawings showing plan, front elevation & side elevation with all fittings and accessories etc. The following information must be specifically included on drawings:Make of transformer oil. Electrical clearances, minimum as well as actual. The no. of radiator headers, number of radiator element in each header. Small sketch showing un-tanking details. Thickness of transformer tank bottom, sides & top plates. Type, shade and shade No. and thickness of transformer paints. Roller, rail gauge sketch. Weight of oil, bare copper weight windings core, un-tanking mass, transportation mass and dimensions etc. Detailed drawing of bushings showing plan, elevation, terminal details, mounting details make and type number incorporating electrical characteristics, description of various parts, total creepage & protected creepage distance, weight of oil, total weight of bushing, dimensions, short time current rating etc. Drawing showing HV & LV windings with arrangement of insulation and terminal connections. Schematic control and wiring diagram for auxiliary equipment like OLTC control gear, cooler control gear, marshaling kiosk. Detailed write-up for schematic shall also be supplied. Combined rating & diagram plate. Valve schedule plate. Core assembly drawing with flux density calculations. Interconnection diagram between OLTC panel, drive mechanism and marshalling kiosk. Detailed calculations showing short circuit withstand capacity due to radial and axial forces during short circuit also calculation for thermal withstand capability during short circuit will be supplied. Cable arrangement on the transformers. Drawings showing connection of HV, LV lead with the respective bushing and their place of storage during transportation. 1. 2. 2. FITTINGS AND ACCESSORIES Each transformer shall be complete with the following fittings and accessories: One 150mm (16”) dial type indicating thermometer (OTI) of robust construction mounted on the side of the transformer at a convenient height to read the temperature of oil and fitted with alarm and trip contacts. Provision in the OTI for connection to repeater in RTCC shall also be provided. 2 Nos. 150mm dial type winding hot spot temperature indicators (WTI) one each placed in HV & LV winding, as described below. “It shall be indicating type responsive to the combination of top oil temperature and winding current calibrated to follow the hot spot temperature of transformer winding. The device shall have on additional pointer to register the highest temperature reached. Each winding temperature indicator should have four sets of contacts. Two contacts of one of the WTI shall be used for trip and alarm purpose, wiring of which will go to the main control and relay panel of the transformer (External control cables from the marshalling box to the C&R panel to be provided by the purchaser). [ Third set of contacts shall be spare. Provision in the WTI for connection to repeater in RTCC shall also be provided. The contacts of each WTI should be adjustable to close between 600C to 120 0C and shall reopen when the temperature has fallen by 100C-150C. However, supplier should mention in the their manuals the actual adjustable settings of these contacts.” Repeater for both WTIs shall also be provided in the RTCC Panel. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. One conservator alongwith 2 no. shut off valves, oil surge relay, breather connecting pipe etc. exclusively for OLTC. One pressure relief valve/device (PRV) of minimum 6 inch size for main tank and 1 No. PRV for OLTC of size 3 inch (approx.) with provision for trip contacts. Inspection covers with jacking bolts in the top cover plate of the tank. One drain valve with plug or blanking flange at the bottom of the tank size 80 mm. One filter valve each at top & bottom of transformer tank size 50mm Three oil sampling valves for taking samples of top, middle and bottom oil. Set of lifting lugs/jacking lugs and eyebolts on all parts for ease of handling. One double float gas/oil surge detecting (Buchholz) relay in the pipe connecting the conservator with tank, complete with alarm and tripping contacts to detect accumulation of gas and sudden changes of oil pressure, complete with shut off valves on conservator side as well as tank side. Th size of shut off valve shall be 80 mm. Two grounding terminals on diagonally opposite bottom corners of tank. However, if provided on the length side of tank, then these grounding terminal shall be out side the rail gauge. One ONAN cooling equipment comprising of suitable radiators with shut off valves, air release and drain plugs. One ONAF cooling equipment comprising of fan motors with auto & manual control. Skids and pulling eyes on both sides. One marshalling box housing dial type thermometers for winding and oil temperature indicators, heater, fan, control switches with fan fail alarm and complete wiring and local/auto selector switch, and supply isolating switches with HRC fuses. Two thermometer pockets for mercury in glass thermometer. A set of universal type bi-metallic multi-bolt double grooved conductor clamps each capable of receiving single ACSR Zebra/ double ACSR ZEBRA conductor respectively for HV side LV side. Suitable bi-metallic flexible connectors for neutral terminals. Suitable size bi-directional wheels for 1676 mm rail gauge in both direction-4 No. 19. 20. 21. 22. 23. 24. One OLTC alongwith remote control panel with each transformer complete with wiring, oil surge relay etc. a) OLTC conservator pipe and valve diameter should be 25mm. c) The height of RTCC panel should be 2312 mm & shade of paint should be of 631 of IS:5. The following plates in English shall be fixed to the transformer tank at about 1750-mm above ground level: a) Rating Plate bearing data as specified in IS: 2026/1977. It must contain insulation levels of various windings, impedance at tap 1/5/17 & short circuit duration. b) Terminal marking plate showing the internal connections and voltage vector relationship of various windings in accordance with IS: 2026/1977 (Latest Edition). c) Valve schedule plate showing the location and function of all valves and air release cocks/plugs. A plate showing the rated no load voltage at various taps shall be affixed on the RTCC in order to facilitate the operator in deciding the tap position on which the transformer is to be operated corresponding to the incoming voltage. Oil conservator (for main tank) fitted with flexible separator (as oil preservative system) complete with magnetic type oil level gauge, filling hole and cap, drain valve-size 19mm, shut off valve, inter connecting pipes etc. Magnetic type oil level gauge shall be provided with low oil level alarm contacts and a dial showing minimum, maximum and normal oil level. The gauge shall be readable from the transformer base level. Silica gel breather with oil seal, shall be fitted as already prescribed. Breather should be made of see through material. One drain pipe upto floor level with one valve may be provided. One No. ladder with provision for anti-climbing. Any other item which is not included above but it is essential for the satisfactory operation of the equipment. 1.0 2.0 FOR 66KV GIS SECTOR-21-D, FARIDABAD SECTION- 4 (Chapter – 1) TECHNICAL SPECIFICATION FOR SF6 GAS INSULATED METAL ENCLOSED SWITCHGEAR (GIS) RATED 72.5kV General Characteristics The SF6 gas insulated metal enclosed switchgear shall be totally safe against inadvertent touch of any of its live constituent parts. It should be designed for indoor (as specified) application with meteorological conditions at site as per Section Project. All parts of the switchgear should be single phase/three phase enclosed for 66kV GIS (1250A for feeder & Transformer modules and 2000A for bus coupler & bus bar bay module). However the type of enclosure whether single or three phase at each voltage level to be identified by the bidder at the time of bidding and quoted accordingly which will not be altered at later stage. The arrangement of gas sections or compartments shall be such as to facilitate future extension of any make on either end without any drilling, cutting or welding on the existing equipment. To add equipment, it shall not be necessary to move or dislocate the existing switchgear bays. The design should be such that all parts subjected to wear and tear are easily accessible for maintenance purposes. The equipment offered shall be protected against all types of voltage surges and any equipment necessary to satisfy this requirement shall be deemed to be included The required overall parameters of GIS are as follows:S. Technical Particulars 66 kV System No a) Rated Voltage 72.5 kV (rms) b) Rated frequency 50 HZ c) Grounding Solidly Earthed d) Rated power frequency withstand Voltage 170 kV (rms) (1min) line to earth e) Impulse withstand BIL (1.2/50/mic. Sec) Line to ±325 kVp earth f) Rated switching impulse Voltage (Peak ) line to -earth g) Rated short time withstand current for 1s (rms) 31.5 kA h) Rated peak withstand current 80 kA (peak) i) Guaranteed maximum gas losses for complete installation as well as for all individual sections in %age shall be As per IEC- 62271- 203 j) Seismic level shall be considered as Zone- IV, as per IS-1893, Year- 2002 The metal-enclosed gas insulated switchgear, including the operating devices, accessories and auxiliary equipment forming integral part thereof, shall be designed, manufactured, assembled and tested in accordance with the IEC-62271-203 publications including their parts and supplements as amended or revised to date. Reference Standards The metal-enclosed gas-insulated switchgear, including the operating devices, accessories and auxiliary equipment forming integral part thereof, shall be designed, manufactured, assembled and tested in accordance with the following International Electro-technical Commission (IEC) Publications including their parts and supplements as amended or revised to date: IEC 62271-203 Gas Insulated metal-enclosed switchgear for rated voltages above 52KV. IEC 60376 New sulphur hexafluoride IEC 62271- 100 High voltage alternating current Circuit breakers IEC 60694 Common clauses for high voltage Switchgear and control-gear standards IEC 62271-102 Alternating current disconnectors (isolators) and earthing switches. 1 IEC 61128 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 4.0 4.1 Alternating current disconnectors. Bus-transfer current switching by disconnectors. IEC 61129 Alternating current earthing switches. Induced current switching IEC 66044-1 Current transformers IEC 66044-2 Voltage transformers IEC 60137 Bushings for alternating voltages above 1000 V IEC 60859 Cable connections for gas-insulated switchgear IEC 60480 Guide to checking of sulphur hexafluoride taken from electrical equipment IEC 60099-1/4 Non-linear resistor type arresters for AC systems IEC 60439 Factory-built assemblies of low-voltage switchgear and control gear. IEC 60427 Report on synthetic testing of high-voltage alternating-current circuit breaker. IEEE 80(2000) IEEE Guide for Safety in AC Substation grounding. CIGRE-44 Earthing of GIS- an application guide.(Electra no.151,Dec’93) The components and devices which are not covered by the above standards shall conform to, and comply with, the latest applicable standards, rules, codes and regulations of the internationally recognized standardizing bodies and professional societies as may be approved by the Employer. The manufacturer shall list all applicable standards, codes etc. and provide copies thereof for necessary approval. In case the requirements laid down herein differ from those given in above standard in any aspect the switchgear shall comply with the requirements indicated herein in regard thereto. Definitions Assembly Assembly refers to the entire completed GIS equipment furnished under contract. Bay Bay refers to the area occupied by one Circuit Breaker and associated equipments used to protect one feeder/line/bus coupler in double bus scheme. Compartment When used in conjunction with GIS equipment, compartment refers to a gas tight volume bounded by enclosure walls and gas tight isolating barriers. Enclosure When used in conjunction with GIS equipment, enclosure refers to the grounded metal housing or shell which contains and protects internal Power system equipment (breaker, disconnecting switch, grounding switch, voltage transformer, current transformer surge arresters, interconnecting bus etc.) Manual Operations Manual operation means operation by hand without using any other source of Power. Module When used in conjunction with GIS equipment, module refers to a portion of that equipment. Each module includes its own enclosure. A module can contain more than one piece of equipment, for example, a module can contain a disconnecting switch and a grounding switch. Reservoir When used in conjunction with GIS equipment reservoir refers to a larger gas tight volume. General Design & Safety Requirement It is understood that each manufacturer has own particular GIS design concept and it is not the purpose of this specification to impose unreasonable restrictions. However, in the interest of safety, reliability and maintainability, the switchgear offered shall meet the following minimum requirements stipulated herein. The GIS assembly shall consist of separate modular compartments e.g. Circuit Breaker compartment, Bus bar compartment filled with SF6 Gas and separated by gas tight partitions so as to minimize risk to human life, allow ease of maintenance and limit the effects of gas leaks failures & internal arcs etc. These compartments shall be such that 2 4.2 4.3 4.4 4.5 4.6 4.7 4.8 4.9 4.10 4.11 4.12 maintenance on one bus- bar/compartment may be performed without de-energising the adjacent bus-bar/feeders. These compartments shall be designed to minimize the risk of damage to adjacent sections and protection of personnel in the event of a failure occurring within the compartments. Rupture diaphragms with suitable deflectors shall be provided to prevent uncontrolled bursting of pressures developing within the enclosures under worst operating conditions, thus providing controlled pressure relief in the affected compartment. The workmanship shall be of the highest quality and shall conform to the latest modern practices for the manufacture of high technology machinery and electrical switchgear. The switchgear, which shall be of modular design, shall have complete phase isolation. The conductors and the live parts shall be mounted on high graded epoxy resin insulators. These insulators shall be designed to have high structural strength and electrical dielectric properties and shall be shaped so as to provide uniform field distribution and to minimize the effects of particle deposition either from migration of foreign particles within the enclosures or from the by-products of SF6 breakdown under arcing conditions. Gas barrier insulators and support insulators shall have the same basis of design. The support insulators shall have holes on both sides for proper flow of gas. Gas barrier insulators shall be provided so as to divide the GIS into separate compartments. They shall be suitably located in order to minimize disturbance in case of leakage or dismantling. They shall be designed to withstand any internal fault thereby keeping an internal arc inside the faulty compartment. Due to safety requirement for working on this pressurized equipment, whenever the pressure of the adjacent gas compartment is reduced, it should be ensured by the bidder that adjacent compartment would remain in service with reduced pressure. The gas tight barriers shall be clearly marked on the outside of the enclosures. The material and thickness of the enclosures shall be such as to withstand an internal flash over without burn through for a period of 500 ms at rated short time withstand current. The material shall be such that it has no effect of environment as well as from the by-products of SF6 breakdown under arcing condition. Each section shall have plug- in or easily removable connection pieces to allow for easy replacement of any component with the minimum of disturbance to the remainder of the equipment. The material used for manufacturing the switchgear equipment shall be of the type, composition and have physical properties best suited to their particular purposes and in accordance with the latest engineering practices. All the conductors shall be fabricated of aluminum/ copper tubes of cross sectional area suitable to meet the normal and short circuit current rating requirements. The finish of the conductors shall be smooth so as to prevent any electrical discharge. The conductor ends shall be silver plated and fitted into finger contacts or tulip contacts. The contacts shall be of sliding type to allow the conductors to expand or contract axially due to temperature variation without imposing any mechanical stress on supporting insulators. Each pressure filled enclosure shall be designed and fabricated to comply with the requirements of the applicable pressure vessel codes and based on the design temperature and design pressures as defined in IEC-62271-203/ IEC-62271-200. The manufacturer shall guarantee that the pressure loss within each individual gas-filled compartment shall not be more than half percent (0.5%) per year. Each gas-filled compartment shall be equipped with static filters, density switches, filling valve and safety diaphragm. The filters shall be capable of absorbing any water vapour which may penetrate into the enclosures as well as the by-products of SF6 during interruption. Each gas compartment shall be fitted with separate non-return valve connectors for evacuating & filling the gas and checking the gas pressure etc. The switchgear line-up when installed and operating under the ambient conditions shall perform satisfactorily and safely under all normal and fault conditions. Even repeated operations up to the permissible servicing intervals under 100% rated and fault conditions shall not diminish the performance or significantly shorten the useful life of the switchgear. Any fault caused by external reasons shall be positively confined to the originating 3 4.13 4.14 4.15 4.16 4.17 4.18 4.19 4.20 4.21 4.22 4.23 compartment and shall not spread to other parts of the switchgear. The internal components shall be maintenance free for at least 10 years. Routine replacements of insulating gas shall not be required in intervals of less than ten years. The thermal rating of all current carrying parts shall be minimum for one sec for the rated symmetrical short – circuit current. The switchgear shall be of the free standing, self-supporting with easy accessibility to all the parts during installation & maintenance with all high-voltage equipment installed inside gas-insulated metallic and earthed enclosures. It shall be suitably sub-divided into individual arc and gas-proof compartments at least for : a) Bus bars b) Intermediate compartment c) Circuit breakers & Line Lightning Arrestors d) Bus/Line disconnectors e) Voltage Transformers f) Gas Insulated bus section between GIS and XLPE cable/overhead conductor g) Gas Insulated bus section between GIS & Transformer The bus enclosure should be sectionalized in a manner that maintenance work on any bus disconnector (when bus and bus disconnector are enclosed in a single enclosure) can be carried out by isolating and evacuating the small effected section and not the entire bus. The arrangement of the individual switchgear bays shall be such so as to achieve optimum space- saving, neat and logical arrangement and adequate accessibility to all external components. It is required that the three phases of each switchgear bay be arranged side by side. The arrangement of the equipment offered must provide adequate access for operation, testing and maintenance. Local Control & Substation Automation System:Separate control cubicle including gas monitoring kiosk shall be provided for each bay which shall be installed near the switchgear for local control & monitoring of respective switchgear bay. Each LCC shall contain the local control, interlocking, operation and indication devices for the associated GIS feeder bay. The LCC shall be free-standing / integrated with the GIS switchgear. A general arrangement drawing showing the installation position shall be submitted with the quotation. Local control cubicle for GIS shall be equipped with suitable hardware & software for remote control operation and conform to the bay level controller as detailed in Section: Substation Automation System. All the elements shall be accessible without removing support structures for routine inspections and possible repairs. The removal of individual enclosure parts or entire breaker bays shall be possible without disturbing the enclosures of neighboring bays. It should be impossible to unwillingly touch live parts of the switchgear or to perform operations that lead to arcing faults without the use of tools or brute force. In case of any repair or maintenance on one busbar, disconnectors, the other busbar/other equipments should be live and in service. All interlocks that prevent potentially dangerous mal-operations shall be constructed such that they can not be operated easily, i.e. the operator must use tools or brute force to override them. In general the contours of energized metal parts of the GIS and any other accessory shall be such, so as to eliminate areas or points of high electrostatic flux concentrations. The surfaces shall be smooth with no projection or irregularities which may cause visible corona. No corona shall be visible in complete darkness which the equipment is subjected to specified test voltage. There shall be no radio interference from the energized switchgear at rated voltage. The enclosure shall be of continuous design and shall meet the requirement as specified in clause no. 10 (special considerations for GIS) of IEEE- 80, Year- 2000. The enclosure shall be sized for carrying induced current equal to the rated current of the 4 Bus. The conductor and the enclosure shall form the concentric pair with effective shielding of the field internal to the enclosure. 4.24 The fabricated metal enclosures shall be of Aluminium alloy having high resistance to corrosion, low electrical loses and negligible magnetic losses. All joint surfaces shall be machined and all castings shall be spot faced for all bolt heads or nuts and washers. All screws, bolts, studs and nuts shall conform to metric system. The other type of nonmagnetic enclosures may be considered. 4.25 The breaker enclosure shall have provision for easy withdrawal of the interrupter assemblies. The removed interrupter assembly must be easily and safely accessible for inspection and possible repairs. 4.26 The enclosure shall be designed to practically eliminate the external electromagnetic field and thereby electrodynamic stresses even under short circuit conditions. 4.27 The elbows, bends, cross and T-sections of interconnections shall include the insulators bearing the conductor when the direction changes take place in order to ensure that live parts remain perfectly centered and the electrical field is not increased at such points. 4.28 The Average Intensity of electromagnetic field shall not be more than 50 µ Tesla. The contractor shall furnish all calculations and documents in support of the above during detailed engineering. 4.29 The Bidder shall furnish the following information regarding the loosely distributed metallic particles within the GIS encapsulation. a) Calculations of critical field strength for specific particles of defined mass and geometry. b) The methodology and all the equipment for electrical partial discharge (PD) detection and/or acoustic detection methods, including that mentioned in the specification elsewhere. 4.30 The switchgear shall have provision for connection with ground mat risers. This provision shall consist of grounding pads to be connected to the ground mat riser in the vicinity of the equipment. 4.31 The ladders and walkways shall be provided wherever necessary for access to the equipment. A portable ladder with adjustable height may also be supplied to access to the equipment. 4.32 Wherever required, the heaters shall be provided for the equipment in order to ensure the proper functioning of the switchgear at specified ambient temperatures. The heaters shall be rated for 230V AC supply and shall be complete with thermostat, control switches and fuses, connected as a balanced 3-phase 4-wire load. The possibility of using heaters without thermostats in order to achieve the higher reliability may be examined by the bidder and accordingly included in the offer but it shall be ensured by the bidder that the temperature rise of different enclosures where heating is provided should be within safe limits as per relevant standards. One copy of the relevant extract of standard to which the above arrangement conforms along with cost reduction in offer. If any, shall also be furnished along with the offer. The heaters shall be so arranged and protected as to create no hazard to adjacent equipment from the heat produced. 4.33 The enclosure & support structure shall be designed that a mechanic 1780 mm in height and 80Kg in weight is able to climb on the equipment for maintenance. 4.34 The sealing provided between flanges of two modules / enclosures shall be such that long term tightness is achieved. 4.35 Alarm circuit shall not respond to faults for momentary conditions. The following indications including those required elsewhere in the specifications shall be generally provided in the alarm and indication circuits. 4.35.1 Gas Insulating System: a) Loss of Gas Density. b) Loss of Heater power(if required) c) Any other alarm necessary to indicate deterioration of the gas insulating system. 4.35.2 Operating System: a) Low operating pressure 5 4.36 4.37 4.38 4.39 4.40 5.0 6.0 b) Loss of Heater power c) Loss of operating power d) Loss of control e) Pole Disordance The equipment will be operated under the following ambient conditions: a) The ambient temperature varies between 0oC and 50oC. However, for design purposes, ambient temperature should be considered as 50oC. b) The humidity will be about 95% (indoors) c) The elevation is less than 1000 meters. Temperature rise of current carrying parts shall be limited to the values stipulated in IEC694, under rated current and the climatic conditions at site. The temperature rise for accessible enclosure shall not exceed 20oC above the ambient temperature of 50oC. In the case of enclosures, which are accessible but need not be touched during normal operation, the temperature rise limit may be permitted upto 30oC above the ambient of 50oC. In case of any internal arc fault regardless whether it occurs in a bus bar section, a bus bar isolator or the circuit breaker, repair works should be possible without shutting down the substation; at least one busbar and the undisturbed feeder should remain in operation. It should be possible to remove and replace a fully assembled circuit breaker without interfering the operation of the adjacent feeder. All circuit breakers should be interchangeable. The GIS equipments shall be arranged in such a manner that in case of maintenance works on any of the equipment, at least one bus bar should be available for operation. Inter bay width shall be sufficient to allow access to all drive mechanisms and other termination boxes without the need of dismantling other apparatuses. These conditions shall be taken into account by the supplier in the design of the equipment. Bellows or Compensating Units:Adequate provision shall be made to allow for the thermal expansion of the conductors and of differential thermal expansion between the conductors and the enclosures. The bellows shall be metallic (preferably of stainless steel) of following types or other suitable equivalent arrangement shall be provided wherever necessary. 1) Lateral / Vertical mounting units: These shall be inserted, as required, between sections of busbars, on transformer and XLPE cable etc. Lateral mounting shall be made possible by a sliding section of enclosure and tubular conductors. 2) Axial compensators: These shall be provided to accommodate changes in length of busbars due to temperature variations. 3) Parallel compensators: These shall be provided to accommodate large linear expansions and angle tolerances. 4) Tolerance compensators: These shall be provided for taking up manufacturing, site assembly and foundation tolerances. 5) Vibration compensators: These bellow compensators shall be provided for absorbing vibrations caused by the transformers when connected to SF6 switchgear by oil- SF6 bushings. 6) The electrical connections across the bellows or compensating units shall be made by means of suitable connectors. Indication and Verification of Switch Positions Indicators shall be provided on all circuit breakers, isolators and earth-switches, which shall clearly show whether the switches are open or closed. The indicators shall be mechanically coupled directly to the main contact operating drive rod or linkages and shall be mounted in a position where they are clearly visible from the floor or the platform in the vicinity of the equipment. Windows shall also be provided with all isolators and earth switches so that the switch contact positions can be verified by direct visual inspection. 6 7.0 8.0 9.0 Pressure Relief Devices Pressure relief devices shall be provided in the gas sections to protect the main gas enclosures from damage or distortion during the occurrence of abnormal pressure increase or shock waves generated by internal electrical fault arcs (preferably in downward direction). Pressure relief shall be achieved either by means of diaphragms or plugs venting directly into the atmosphere in a controlled direction. If the pressure relief devices vent directly into the atmosphere, suitable guards and deflectors shall be provided. Contractor shall submit to the Employer the detailed criteria design regarding location of pressure relief devices/rupture diaphragms. Pressure Vessel Requirements The enclosure shall be designed for the mechanical and thermal loads to which it is subjected in service. The enclosure shall be manufactured and tested according to the pressure vessel code (ASME/CENELEC code for pressure Vessel.) Each enclosure has to be tested as a routine test at 1.5 times the design pressure for one minute. The bursting strength of Aluminium castings has to be at least 5 times the design pressure. A bursting pressure test shall be carried out at 5 times the design pressure as a type test on each type of enclosure. Grounding The grounding system shall be designed and provided as per IEEE-80-2000 and CIGRE44 to protect operating staff against any hazardous touch voltages and electro-magnetic interferences. As the area involved is small, contractor has to take special measures for the same. The GIS supplier shall define clearly what constitutes the main grounding bus of the GIS. The GIS supplier must supply the entire material for grounding bus of GIS viz. conductor, clamps, joints, operating and safety platforms etc. The GIS supplier is also required to supply all the earthing conductors and associated hardware material for the following: 1) Connecting all GIS equipment, enclosures, control cabinets, supporting structure etc. to the ground bus of GIS. 2) Grounding of transformer and other outdoor switchyard equipments/ structures etc. The enclosure of the GIS may be grounded at several points so that there shall be grounded cage around all the live parts. A minimum of two nos. of grounding connections should be provided for each of circuit breaker, transformer terminals, cable terminals, surge arrestors, earth switches and at each end of the bus bars. The grounding continuity between each enclosure shall be effectively interconnected with Cu/ Al bonds of suitable size to bridge the flanges. In case the bidder does not offer external bonding, the bidder shall demonstrate that the connectivity offered by them between each enclosure is effective and does not require external bonding. Further similar design should have been in service for offered voltage. Subassembly to subassembly bonding shall be provided to provide gap & safe voltage gradients between all intentionally grounded parts of the GIS assembly & between those parts and the main grounding bus of the GIS. Each marshalling box, local control panel, power and control cable sheaths and other non current carrying metallic structures shall be connected to the grounding system of GIS via connections that are separated from GIS enclosures. The grounding connector shall be of sufficient mechanical strength to withstand electromagnetic forces as well as capable of carrying the anticipated maximum fault current without overheating. At least two grounding paths shall be provided to connect each point to the main grounding bus. Necessary precautions should be under taken to prevent excessive currents from being induced into adjacent frames, structures of reinforcing steel and to avoid establishment of current loops via other station equipment. All flexible bonding leads shall be tinned copper. All connectors, for attaching flexible bonding leads to grounding conductors and grounding conductors to support structures shall be tinned bronze with stainless steel or tinned bronze hardware. The contractor shall provide suitable measure to mitigate transient enclosure voltage caused by high frequency currents caused by lightning strikes, operation of surge arrestor, 7 ph./ earth fault and discharges between contacts during switching operation. The grounding system shall ensure safe touch & step voltages in all the enclosures. The contractor shall provide suitable barrier of non- linear resistor/ counter discontinued SF6/ Air termination, SF6/ Transformer termination, SF6/ HV cable bushing etc. to mitigate transient enclosure voltage. The bidders shall provide lightening mast/GS shield wire at suitable place for protection of whole sub-station including transformers, GIS cum control room building etc. The bidder shall submit detailed proposal for grounding system of whole substation including indoor and outdoor equipments with earthmat using 40mm diameter MS rod for approval of purchaser. The risers shall be GS flat of size 75X12mm above ground level. The bidder shall submit detailed proposal for grounding system for approval of purchaser. Any provision to be made in the building design to take care of earthing requirement shall also be clearly spelt-out. 10 Circuit Breakers General SF6 gas insulated metal enclosed circuit breakers (for 66kV) shall comply with the latest revisions of IEC- 62271-100 & relevant IEC except to the extent explicitly modified in the specification and shall meet with requirements specified. Circuit breakers shall be equipped with the operating mechanism. SF6 Circuit breakers shall be of self blast / single pressure (puffer) type. Complete circuit breaker with all necessary items for successful operation shall be supplied. The circuit breakers shall be designed for high speed single and three phase reclosing with an operating sequence and timing as specified. 10.1 Duty Requirements Circuit breaker shall be C2 – M2 – E1 class as per IEC 62271-100. Circuit breaker shall meet the duty requirements for any type of fault or fault location also for line charging and dropping when used on 66kV effectively grounded system and perform make and break operations as per the stipulated duty cycles satisfactorily. 10.2 The circuit breaker shall be capable of: i. Interrupting line/cable charging current as per IEC without re-strikes and without use of opening resistors. ii. Clearing short line fault (Kilometric faults) with source impedance behind the bus equivalent to symmetrical fault current specified. iii. Breaking 25% the rated fault current at twice the rated voltage under phase opposition condition. iv. The breaker shall satisfactorily withstand the high stresses imposed on them during fault clearing, load rejection and re-energisation of lines with trapped charges. 10.3 Total Break Time The total break time shall not be exceeded under any of the following duties: i. Test duties T10,T30,T60,T100 (with TRV as per IEC- 62271-100 ) ii. Short line fault L90, L75 (with TRV as per IEC-62271-100 ) The Bidder may please note that total break time of the breaker shall not be exceeded under any duty conditions specified such as with the combined variation of the trip coil voltage (70-110%), hydraulic pressure and SF6 gas pressure etc. While furnishing the proof for the total break time of complete circuit breaker, the bidder may specifically bring out the effect of non simultaneity between poles and show how it is covered in the total break time. The values guaranteed shall be supported with the type test reports. 10.4 Constructional Features The features and constructional details of breakers shall be in accordance with requirements stated hereunder: 10.4.1 Contacts All making and breaking contacts' shall be sealed and free from atmospheric effects. Contacts shall be designed to have adequate thermal and current carrying capacity for the duty specified and to have a life expectancy so that frequent replacement due to excessive 8 10.4.2 10.4.3 10.4.4 10.4.5 10.4.6 10.4.7 10.5 10.5.1 10.5.2 burning will not be necessary. Provision shall be made for rapid dissipation of heat generated by the arc on opening. Any device provided for voltage grading to damp oscillations or, to prevent re-strike prior to the complete interruption of the circuit or to limit over voltage on closing, shall have a life expectancy comparable of that of the breaker as a whole. Breakers shall be so designed that when operated within their specified rating, the temperature of each part will be limited to values consistent with a long life for the material used. The temperature rise shall not exceed that indicated in IEC-62271-100 under specified ambient conditions. For C.B’s, the gap between the open contacts shall be such that it can withstand atleast the rated phase to ground voltage for eight hours at zero pressure above atmospheric level of SF6 gas due to its leakage. The breaker should be able to withstand all dielectric stresses imposed on it in open condition at lockout pres-sure continuously (i.e. 2 pu power frequency voltage across the breaker continuously) For C.B’s In the interrupter assembly there shall be an adsorbing product box to minimize the effect of SF6 decomposition products and moisture. The material used in the construction of the circuit breakers shall be such as to be fully compatible with SF6 gas decomposition products. Provisions shall be made for attaching an operational analyzer to record travel, speed and making measurement of operating timings etc. after installation at site. Static Contact Resistance Meter and Dynamic Contact Resistance Meter shall also be provided along with CB operational analyzer. Operating Mechanism General Requirements: a) Circuit breaker shall be operated by spring charged mechanism or hydraulic mechanism or a combination of spring and hydraulic mechanism. The mechanism shall be housed in a dust proof cabinet and shall have IP: 42 degree of protection. b) The operating mechanism shall be strong, rigid, not subject to rebound or to critical adjustments at site and shall be readily accessible for maintenance. c) The operating mechanism shall be suitable for high speed reclosing and other duties specified. During reclosing the breaker contacts shall close fully and then open. The mechanism shall be anti-pumping and trip free (as per IEC definition) under every method of closing. d) The mechanism shall be such that the failure of any auxiliary spring will not prevent tripping and will not cause trip or closing operation of the power operating devices. e) A mechanical indicator shall be provided to show open and close position of the breaker. It shall be located in a position where it will be visible to a man standing on the ground level with the mechanism housing closed. An operation counter shall also be provided in the central control cabinet. f) Working parts of the mechanism shall be of corrosion resisting material, bearings which require grease shall be equipped with pressure type grease fittings. Bearing pin, bolts, nuts and other parts shall be adequately pinned or locked to prevent loosening or changing adjustment with repeated operation of the breaker. g) The bidder shall furnish detailed operation and maintenance manual of the mechanism alongwith the operation manual for the circuit breaker. Control a) The close and trip circuits shall be designed to permit use of momentary-contact switches and push buttons. b) Each breaker pole / breaker shall be provided with two (2) independent tripping circuits, valves, pressure switches, and coils each connected to a different set of protective relays. c) The breaker shall normally be operated by remote electrical control. Electrical tripping shall be performed by shunt trip coils. However, provisions shall be made for local electrical control. For this purpose a local/remote selector switch and close and trip control switch/push buttons shall be provided in the breaker central control 9 cabinet. d) The trip coil shall be suitable for trip circuit supervision during both open and close position of breaker. e) Closing coil and associated circuits shall operate correctly at all values of voltage between 85% and 110% of the rated voltage. Shunt trip and associated circuits shall operate correctly under all operating conditions of the circuit breaker upto the rated breaking capacity of the circuit breaker and at all values of supply voltage between 70% and 110% of rated voltage. If additional elements are introduced in the trip coil circuit their successful operation and reliability for similar applications on circuit breakers shall be clearly brought out in the additional information schedules. In the absence of adequate details the offer is likely to be rejected. f) Density meter contacts and pressure switch contacts shall be suitable for direct use as permissive in closing and tripping circuits. Separate contacts have to be used for each of tripping and closing circuits. If contacts are not suitably rated and multiplying relays are used then fail safe logic/schemes are to be employed. DC supplies for all auxiliary circuit shall be monitored and for remote annunciations and operation lockout in case of dc failures. g) The auxiliary switch of the breaker shall be positively driven by the breaker operating rod. 10.5.3 Spring operated Mechanism a) Spring operated mechanism shall be complete with motor in accordance with Section GTR. Opening spring and closing spring with limit switch for automatic charging and other necessary accessories to make the mechanism a complete operating unit shall also be provided. b) As long as power is available to the motor, a continuous sequence of the closing and opening operations shall be possible. The motor shall have adequate thermal rating for this duty. c) After failure of power supply to the motor one close open operation shall be possible with the energy contained in the operating mechanism. d) Breaker operation shall be independent of the motor which shall be used solely for compressing the closing spring. Facility for manual charging of the closing spring shall also be provided. The motor rating shall be such that it required preferably not more than 60 seconds for full charging of the closing spring. e) Closing action of circuit breaker shall compress the opening spring ready for tripping. f) When closing springs are discharged after closing a breaker, closing springs shall automatically be charged for the next operation and an indication of this shall be provided in the local and remote control cabinet. g) Provisions shall be made to prevent a closing operation of the breaker when the spring is in the partial charged condition. h) Mechanical interlocks shall be provided in the operating mechanism to prevent discharging of closing springs when the breaker is in the closed position. i) The spring operating mechanism shall have adequate energy stored in the operating spring to close and latch the circuit breaker against the rated making current and also to provide the required energy for the tripping mechanism in case the tripping energy is derived from the operating mechanism. 10.5.4 Hydraulically Operated Mechanism : a) Hydraulically operated mechanism shall comprise of operating unit with power cylinder, control valves, high and low pressure reservoir, motor etc. b) The hydraulic oil used shall be fully compatible for the temperature range to be encountered during operation. c) The oil pressure switch controlling the oil pump and pressure in the high pressure reservoir shall have adequate no. of spare contacts, for continuous monitoring of low pressure, high pressure etc. at switchyard control room. d) The mechanism shall be suitable for at-least two close open operations after failure 10 of AC supply to the motor starting at pressure equal to the lowest pressure of auto reclose duty plus pressure drop for one close open operation. e) The mechanism shall be capable of operating the circuit breaker correctly and performing the duty cycle specified under all conditions with the pressure of hydraulic operated fluid in the operating mechanism at the lowest permissible pressure before make up. f) Trip lockout shall be provided to prevent operations of the circuit breaker below the minimum specified hydraulic pressure. Alarm contacts for lost of Nitrogen shall also be provided. g) All hydraulic joints shall have no oil leakage under the site conditions and joints shall be tested at factory against oil leakage. 10.6 Additional Data To Be Furnished Alongwith The Offer or during detailed engineering after receipt of order: a) Drawing showing contacts in close, arc initiation, full arcing, arc extinction and open position. b) Data on capabilities of circuit breakers in terms of time and number of operations at duties ranging from 100 fault currents to load currents of the lowest possible value without requiring any maintenance or checks. c) Curves supported by test data indicating the opening time under close open operation with combined variation of trip coil voltage and hydraulic pressure. 10.7 Tests 10.7.1 In accordance with the requirements stipulated under Section GTR the circuit breaker alongwith its operating mechanism shall conform to the type tests as per IEC-62271-100. 10.7.2 Routine Tests Routine tests as per IEC: 62271-100 shall be performed on all circuit breakers. In addition to the mechanical and electrical tests specified by IEC, the following shall also be performed. Speed curves for each breaker shall be obtained with the help of a suitable operation analyzer to determine the breaker contact movement during opening, closing, autoreclosing and trip free operation under normal as well as limiting operating conditions (control voltage, pneumatic pressure etc.). The tests shall show the speed of contacts directly at various stages of operation, travel of contacts, opening time, closing time, shortest time between separation and meeting of contacts at break make operation etc. This test shall also be performed at site for which the necessary operation analyzer alongwith necessary transducers, cables, console etc. shall be furnished as mandatory maintenance equipment. The test for getting signature of the dynamic contact resistance measurement shall also be carried out at factory. The test result shall be treated as reference signature for condition monitoring in future. 10.7.3 Technical Parameters - Circuit Breaker S.No. Technical Particulars a) b) c) d) e) f) Rated voltage kV (rms) Rated frequency (Hz) No. of poles Type of circuit breaker Rated continuous current (A) at an ambient temperature of 50o C Rated short circuit capacity 66 kV System 72.5 50 3 SF6 insulated 1250/800/400A 31.5 kA with %age of DC component as per IEC62271- 100 corresponding to minimum opening conditions as specified. 11 g) Symmetrical interrupting capability kA (rms) h) Rated short circuit making current kAp i) Short time current carrying capability for one second kA(rms) j) Rated line charging interrupting current at 90 deg. Leading power factor angle(A rms) (The breaker shall be able to interrupt the rated line charging current with test voltage immediately before opening equal to the product of U/√3 and 1.4 as per IEC- 62271-100) k) First pole to clear factor l) Rated break time as IEC (ms) Total break time (ms) m) Total closing time (ms) n) Rated operating duty cycle o) Rated insulation levels i) Full wave impulse with stand voltage (1.2/50 µ sec.) - between line terminals and ground - between terminals with circuit breaker open ii) One minute power frequency withstand voltage - between line terminals and ground - between terminals with circuit breaker open p) Max. radio interference voltage for frequency between 0.5 MHz and 2 MHz q) Max. difference in the instants of closing/opening of contacts (ms) between poles r) Trip coil and closing coil voltage s) Auxiliary Contacts Auxiliary switch shall also comply with requirements as given. Independent single pole reversible contacts (from NO to NC & vice versa) i) ii) Rating of Auxiliary contacts Breaking capacity of Aux. Contacts. t) System neutral earthing 31.5 80 31.5 As per IEC As per IEC 60 65 65 O-0.3s-CO-3 min-CO ± 325 kVp ± 375 kVp As per IEC As per IEC < 500 Micro volts (at 92 kV rms) As per IEC 220V DC with variation as specified in Sec. GTR Each CB pole shall be provided with an auxiliary switch with 20% of spare - NO and 20% spare NC contact for use in future with due provision to add more if required. 10A at 220 V DC 2A DC with the circuit time constant of not less than 20 ms Solidly Earthed 12 11.0 11.1 11.2 11.2.1 11.2.2 11.2.3 11.2.4 11.2.5 Disconnectors (Isolators) General Disconnectors shall be of the single-pole, group operated type, installed in the switchgear to provide electrical isolation of the circuit breakers, the transformers, double bus and transmission lines/cables. The disconnectors shall conform to IEC- 62271-102 and shall have the following ratings as specified Technical Parameter S. Particulars 66kV No a) Rated voltage (rms) Un 72.5 kV b) Rated frequency 50 Hz c) System earthing Solidly Earthed d) Type SF6 insulated 1250/800/400A e) Rated continuous current (A) at 50o C ambient temp. f) Rated short time withstand current of isolator and 31.5 kA for 1 earth switch Sec g) Rated dynamic short circuit withstand current 80 kAp withstand current of isolator and earth switch h) Rated insulation level: One minute power freq. Withstand voltage: To earth : As per IEC Across isolating distance As per IEC i) Rated insulation levels; 1.2/50 µ sec. Lighting impulse withstand voltage (+ve or –ve polarity) To earth: ± 325 kVp Across isolating distance ± 375 kVp j) Rated mechanical terminal load As per IEC k) No. of spare auxiliary contacts on each isolator 6 NO and 6NC l) No. of spare auxiliary contacts on each earthing 6 NO and 6NC switch m) Max. radio interference voltage for frequency < 500 Micro between 0.5MHz and 2MHz volts (at 92 kV rms) Construction & Design The three pole group operated/common operating mechanism disconnectors shall be operated by electric motor suitable for use on 220V DC system and shall be equipped with a manual operating mechanism for emergency use. The motor shall be protected against over current and short circuit. Disconnectors shall be designed as per relevant IEC. These shall be suitable to make and break the charging currents during their opening and closing. They shall also be able to make and break loop current which appears during transfer between bus bars. The contact shielding shall also be designed to prevent restrikes and high local stresses caused by transient recovery voltages when these currents are interrupted. The disconnecting switches shall be arranged in such a way that all the three phases operate simultaneously. All the parts of the operating mechanism shall be able to withstand starting torque of the motor mechanism without damage until the motor overload protection operates. It shall be possible to operate the disconnecting switches manually by cranks or handwheels. The contacts shall be both mechanically and electrically disconnected during the manual operation. The operating mechanisms shall be complete with all necessary linkages, clamps, 13 11.2.6 11.2.7 11.2.8 11.2.9 11.2.10 11.2.11 11.2.12 11.2.13 11.2.14 11.2.15 11.2.16 11.2.17 11.2.18 11.2.19 11.2.20 12.0 12.1 couplings, operating rods, support brackets and grounding devices. All the bearings shall be permanently lubricated or shall be of such a type that no lubrication or maintenance is required. The opening and closing of the disconnectors shall be achieved by either local or remote control. The local operation shall be by means of a two-position control switch located in the bay module control cabinet. Remote control of the disconnectors from the control room shall be made by means of remote/local transfer switch. The disconnector operations shall be inter-locked electrically with the associated circuit breakers in such a way that the disconnector control is inoperative if the circuit breaker is closed. Each disconnector shall be supplied with auxiliary switch having six normally open and six normally closed contacts for future use and provision shall be made to add more if required over and above those required for switchgear interlocking and automation purposes. The auxiliary switch contacts are to be continuously adjustable such that, when required, they can be adjusted to make contact before the main switch contacts. The signaling of the closed position of the disconnector shall not take place unless it is certain that the movable contacts will reach a position in which the rated normal current, peak withstand current and short-time withstand current can be carried safely. The signaling of the open position of the disconnector shall not take place unless the movable contacts have reached such a position that the clearance between the contacts is at least 80 percent of the rated isolating distance. All auxiliary switches and auxiliary circuits shall be capable of carrying a current of at least 10 A DC continuously. The auxiliary switches shall be capable of breaking at least 2A in a 220V DC circuit with a time constant of not less than 20 milliseconds. The disconnectors and safety grounding switches shall have a mechanical key (pad locking key) and electrical inter-locks to prevent closing of the grounding switches when isolator switches are in the closed position and to prevent closing of the disconnectors when the grounding switch is in the closed position. The local control of the Isolator and high-speed grounding switches from the bay module control panel should be achieved from the individual control switches with the remote/local transfer switch set to local. All electrical sequence interlocks will apply in both remote and local control modes. Each disconnector shall have a clearly identifiable local, positively driven mechanical position indicator, together with position indicator on the bay module control cabinet and provisions for taking the signals to the control room. The details of the inscriptions and colouring for the indicator are given as under : SIGN COLOUR Open or ‘O’ Green Open position Closed or ‘I’ Red Closed position All the disconnecting switches shall have arrangement allowing easy visual inspection of the travel of the switch contacts in both open and close positions, from the outside of the enclosure. The disconnecting switches shall be provided with rating plates and shall be accessible for inspection. The disconnecting switches shall be capable of being padlocked in both the open and closed positions with the operating motor automatically disengaged. The padlocking device shall be suitable for a standard size lock with a 10 mm shank. The padlock must be visible and directly lock the final output shaft of the operating mechanism. Integrally mounted lock when provided shall be equipped with a unique key for such three phase group. Master key is not permitted. Safety Grounding Switches Three-pole, group operated / common operating mechanism disconnectors, safety grounding switches shall be operated by electric motor for use on 220V DC ungrounded 14 system and shall be equipped with a manual operating mechanism for emergency use. The motor shall be protected against over-current and short circuit. 12.2 Each safety grounding switch shall be electrically interlocked with its associated disconnector and circuit breaker such that it can only be closed if both the current breaker and disconnector are in open position. Safety grounding switch shall also be mechanically key interlocked with its associated disconnector. 12.3 Each safety grounding switch shall have clearly identifiable local positive driven mechanical indicator together with position indicator on the bay module control cabinet and provision for taking the signal to Control room. 12.4 The details of the inscription and colouring for the indicator are given as under SIGN COLOUR Open or ‘O’ Green Open position Closed or ‘I’ Red Closed position 12.5 Interlocks shall be provided so that manual operation of the switches or insertion of the manual operating device will disable the electrical control circuits. 12.6 Each ground switch shall be fitted with auxiliary switches having six normally open and six normally closed contacts for use by others& provision shall also be made to add more if required in future, over and above those required for local interlocking and position indication purposes. 12.7 Provision shall be made for padlocking the ground switches in either the open or closed position. 12.8 All portions of the grounding switch and operating mechanism required for grounding shall be connected together utilizing flexible copper conductors having a minimum crosssectional area of 50 sq. mm. 12.9 The main grounding connections on each grounding switch shall be rated to carry the full short circuit rating of the switch for 1 sec. and shall be equipped with a silver - plated terminal connector suitable for steel strap of adequate rating for connection to the grounding grid. 12.10 The safety grounding switches shall conform to the requirements of IEC - 62271- 102 12.11 Mechanical position indication shall be provided locally at each switch and remotely at each bay module control cabinet/ substation automation system. 12.12 The rated Induced Current and Voltage for earth switches for both electrostatic and electromagnetic coupling shall be as per IEC 62271-102. 13.0 High Speed Make Proof Grounding Switches 13.1 Grounding switches located at the beginning of the feeder bay modules shall be of the high speed, make proof type and will be used to discharge the respective charging currents, in addition to their safety grounding function. These grounding switches shall be capable of interrupting the inductive currents and to withstand the associated TRV. 13.2 Single phase switches shall be provided with operating mechanism suitable for operation from a 220V DC. 13.3 The switches shall be fitted with a stored energy closing system to provide fault making capacity. 13.4 The short circuit making current rating of each ground switch shall be at least equal to its peak withstand current rating. The switches shall have inductive/ capacitive current switching capacity as per IEC-62271-102. 13.5 Each high speed make proof grounding switch shall have clearly identifiable local positive driven mechanical indicator together with position indicator on the bay module control cabinet and provision for taking the signal Control Room. 13.6 The details of the inscription and colouring for the indicator shall be as under:SIGN COLOUR Open or ‘O’ Green Open position Closed or ‘I’ Red Closed position 13.7 High speed ground switch operation should be possible locally from the bay module control cabinet, or remotely from the control room in conjunction with opening of the 15 13.8 13.9 13.10 13.11 13.12 13.13 13.14 14.0 14.1 A) B) C) D) associated disconnector. These high speed grounding switches shall be electrically interlocked with their associated circuit breakers and disconnectors so that the grounding switches can not be closed if the circuit breakers and disconnectors are closed. Interlocks shall be provided so that the insertion of the manual operating devices will disable the electrical control circuits. Each high speed ground switch shall be fitted with auxiliary switches having six NO & six NC auxiliary contacts for use by others & provision shall also be made to add more if required in future, over and above these required for local interlocking and position indication. All contacts shall be wired to terminal blocks in the local bay control cabinet. Provision shall be made for padlocking the ground switches in their open or closed position. All portion of the grounding switches and operating mechanism required for connection to ground shall be connected together utilizing copper conductor having minimum crosssectional area of 100 sq. mm. The main grounding connection on each grounding switch shall be rated to carry the short time withstand current rating of the switch for 1 sec. and shall be equipped with a silver plated terminal connector suitable for steel strap of adequate design for connection to the grounding grid. The high speed make proof grounding switches shall confirm to the requirements of IEC62271-102. The rated Induced Current and Voltage for earth switches for both electrostatic and electromagnetic coupling shall be as per IEC 62271-102. Instrument Transformers Current Transformers General: i. The current transformers and accessories shall conform to IEC: 60044-1 and other relevant standards except to the extent explicitly modified in the specification. ii. The Principle parameters shall be as per clause 14.4.1. Ratios and Characteristics The number, rating, ratios, accuracy class, etc. for the individual current transformers secondary cores shall be in accordance with Table I – A , II – A , I – B, II – B & III - B. Where multi-ratio current transformers are required the various ratios shall be obtained by changing the effective number of turns on the secondary winding. Rating and Diagram Plates Rating and diagram plates shall be as specified in the IEC specification incorporating the PO No, Date and year of manufacture. The general knee point voltage formula and rated continuous thermal current shall also be marked on the name plate. The diagram plates shall show the terminal markings and the relative physical arrangement of the current transformer cores with respect to the primary terminals (P1 & P2). The position of each primary terminal in the current transformer SF6 gas section shall be clearly marked by two plates fixed to the enclosure at each end of the current transformer. Constructional Details: a) The current transformers incorporated into the GIS will be used for protective relaying and metering and shall be of metal- enclosed type. All the current transformers shall have effective electromagnetic shields to protect against high frequency transients. b) Each current transformer shall be equipped with a marshalling box with terminals for the secondary circuits, which are connected to the local control cubicle. The star/delta configuration and the inter connection to the protection panels will be done at the CT terminal block located in the local control cubicle. c) Current transformers guaranteed burdens and accuracy class are to be intended as simultaneous for all cores. 16 d) e) f) g) h) 14.2 A) B) C) D) E) F) 14.3 The rated extended primary current shall be 125% at all ratios. The instrument security factor at all ratios shall be as per table I – A, II – A, I – B, II-B & III – B for metering cores wherever aux CT’s/Reactors are allowed in the CT’s then all parameters specified shall have to be met treating auxiliary CT’s as an integral part of the CT’s. The aux CT’s/Reactors shall preferably be built in construction of the CT’s. The wiring diagram, for the interconnections of the three single phase CTs shall be provided inside the marshalling box. Provisions shall be made for primary injection testing either within CT or outside. Electromagnetic shields to be provided against high frequency transients typically 130 MHz. Voltage Transformers General The voltage transformers shall conform to IEC- 60044-2 and other relevant standards except to the extent explicitly modified in the specification. Voltage transformers shall be of the electromagnetic type with SF6 gas insulation. The earth end of the high voltage winding and the ends of the secondary winding shall be brought out in the terminal box. The Principle parameters shall be as per clause 14.4.2. Ratios and Characteristics The rating, ratio, accuracy class, connection etc. for the voltage transformers shall be in accordance with Table III – A & IV– B . Rating and diagram plates Rating and diagram plate shall be provided complying with the requirements of the IEC specification incorporating the PO No., Date and year of manufacture and including turns ratio, voltage ratio, burden, connection diagram, rated continuous and short time voltage factor etc. Secondary Terminals, Earthing and Fuses/MCBs The beginning and end of each secondary winding shall be wired to suitable terminals accommodated in a terminal box mounted directly on the voltage transformer section of the SF6 switchgear. All terminals shall be stamped or otherwise marked to correspond with the marking on the diagram plate. Provision shall be made for earthing of the secondary windings inside the terminal box. The transformer shall be able to sustain full line to line voltage without saturation of transformer. Constructional Details of Voltage Transformers: a) The voltage transformers shall be located in a separate bay module on the bus and will be connected phase to ground and shall be used for protection, metering and synchronization. b) The voltage transformers shall be of inductive type, nonresistant and shall be contained in their own-SF6 compartment, separated from other parts of installation. The voltage transformers shall be effectively shielded against high frequency electromagnetic transients. c) Voltage transformer’s secondary shall be protected by HRC cartridge type fuses/MCBs for all the windings. In addition fuses/MCBs shall be provided for the protection and metering windings for fuse monitoring scheme. The secondary terminals of the VT’s shall be terminated to the stud type non-disconnecting terminal blocks in the secondary boxes via the fuse/MCB. d) The voltage transformer should be thermally and dielectrically safe when the secondary terminals are loaded with the guaranteed thermal burdens. e) The diagram for the interconnection of the VTs shall be provided inside the marshalling box. Tests Current and voltage transformers shall conform to type tests and shall be subjected to 17 routine test in accordance with IEC. 14.4 Principle Parameters: 14.4.1 Current Transformers S. No a) b) c) Particulars 66kV Rated voltage Un Rated frequency System neutral earthing d) Rated short time thermal current e) f) j) Rated dynamic current Rated insulation levels i)1.2/50 micro second impulse voltage ii)1 Minute power frequency withstand voltage One minute power frequency withstand voltage between secondary terminal & earth Maximum temperature rise over an ambient temperature of 50o C Radio interference voltage at 1.1 Un/√3 and frequency range 0.5 to 2 MHz Partial discharge level as per IEC 72.5kV (rms) 50 Hz Solidly Earthed 31.5 kA for 1 second 80 kAp k) Rated continuous thermal current g) h) i) 14.4.2 Voltage Transformers S. Particulars No a) Rated voltage Un b) Rated frequency c) System neutral earthing d) e) f) g) h) i) j) 15.0 A) System fault level ( for 1 second) Rated insulation levels i)1.2/50 micro second impulse voltage ii)1 Minute power frequency withstand voltage One minute power frequency withstand voltage between secondary terminal & earth Radio interference voltage at 1.1 Un/√3 and frequency range 0.5 to 2 MHz Rated voltage factor ±325 kVp 170 kV (rms) 5kV (rms) As per IEC 60044-1 < 500 Micro volts ≤10 pico coulomb 125% on all taps 66kV 72.5kV (rms) 50 Hz Solidly Earthed 31.5 kA ±325 kVp 170 kV (rms) 3kV (rms) < 500 µV 1.2 continuous & 1.5 for 30secs ≤10 pC As per IEC 60044-2 Partial discharge level as per IEC(pico coulomb) Maximum temperature rise over an ambient temperature of 50o C Outdoor Bushings General Outdoor bushings, for the connection of conventional external conductors to the SF6 metal enclosed switchgear, shall be provided where specified and shall conform to the requirements given in GTR. The dimensional and clearance requirements for the metal enclosure will be the responsibility of the manufacturer and their dimensions must be coordinated with the 18 B) C) D) E) 16.0 switchgear. Bushings shall generally be in accordance with the requirements of IEC publication 60137 as applicable. Insulation levels and creepage distances All bushings shall have an impulse and power frequency withstand level that is greater than or equal to the levels specified for GIS. The creepage distance over the external surface of outdoor bushings shall not be less than 25 mm/kV. Bushing types and fitting Condenser type bushings will be preferred but alternative types can also be considered. Liquid filled bushings shall be provided with liquid level gauges clearly visible from ground level, preferably of the direct reading prismatic type or the magnetic type. Other types of liquid level gauges will only be accepted if specifically approved. Mechanical forces on bushing terminals Outdoor bushings must be capable of withstanding cantilever forces due to weight of conductor, wind force and short circuit forces etc. Design calculations in support of the cantilever strength chosen shall be submitted for Employers review and approval. The major parameters of the bushings shall be as follows:S. Particulars 66kV No a) Rated voltage (kV) 72.5kV b) Rated current 1250/800/400A c) Lightning impulse withstand voltage (kVp) 325 d) One minute power frequency withstand voltage kV (rms) 170 e) Minimum total creepage distances (mm) 1815 Surge Arrestors The surge arrestors shall confirm in general to latest IEC – 60099 – 4. The technical specification of the surge arrestor is placed as under:4.0 SYSTEM PARAMETERS: The Surge Arrestors offered under this specification shall conform to the parameters given below: Sl. Particulars System Voltage (KV rms) No. 66 1. Nominal system voltage (kV rms) 66 2. Highest system voltage (kV rms) 72.5 3. 1.2/50 microsecond impulse voltage withstand level a) Transformers and Reactors (kVp) 325 b) Other equipment and lines (kVp) 325 4. Minimum prospective symmetrical fault current for 1 31.5 second at Arrestor location (kA rms) 5. Anticipated levels of Temporary over voltage and its duration a) Voltage (p.u.) 1.5/1.2 b) Duration (Seconds) 1/10 6. System frequency(Hz) 50 ± 2.5 C/S 7. Neutral Grounding E.E* 8. Number of Phases Three *E/E = Effectively earth 19 TECHNICAL REQUIREMENTS SURGE ARRESTORS Sl. Particulars System voltage wise requirement of parameters(kV) No. 66 1. Rated Arrestor Voltage 60 2. M.C.O.V. (kV rms) 49 3. Nominal discharge current corresponding to 10KA 8/20 microsec wave shape (kA rms) 4. Long duration discharge class 3 5. Max. Switching Surge kV(P) Protective level 140 voltage at 1000 Amp. 6. Max. residual voltage kV(P) for nominal 170 discharge current 10 KA with 8/20 micro second wave 7. Max.residual voltage kV(P) steep fronted 186 current impulse of 10 KA. 16.1 INSULATION CO-ORDINATION AND SELECTION OF SURGE ARRESTOR The contractor shall be fully responsible for complete insulation co-ordination of switchyard including GIS. Contractor shall carry out detailed studies and design calculations to evolve the required parameters locations, energy capability etc. of surge arrestors such that adequate protective margin is available between peak impulse, surge and power frequency discharge voltages and BIL of the protected requirement. The locations of surge arrestors shown in single line diagram are indicative only. If the bidders feel that at some more locations the surge arrestors are required to be provided the same should also be included in the offer. The contractor shall perform all necessary studies. The report shall detail the limits of all equipment parameters which could affect the insulation co-ordination .The report shall also detail the characteristics of the surge arrestor and shall demonstrate that the selected arrestor’s protective and withstand levels, discharge and coordinating currents, and arrestor ratings and comply with the requirement of this specification. The contractor shall also consider in the studies the open circuit breaker condition, fast transients generated by slow operation of disconnecting switches. The study report and design calculations shall be submitted for Owner’s approval. 17. 66 kV GIS BUILDING (If applicable): a) The buildings shall house 66 KV Gas Insulated Switchgear (GIS) separately and other associated equipments inside in each of the GIS building. b) The bidder shall submit the design & construction proposal of the building along with necessary information, data, and drawings in the techno- commercial bid according to the complete requirements. c) The plot plan of floor for 66 KV GIS building is enclosed. The dimension given is for reference only and may vary according to requirement of the equipment to be installed inside. The bidder shall finalize the dimensions according to the equipment offered by them providing enough space & access for erection, operation and maintenance. 18.0 Seismic Design Criteria: The equipment shall be designed for operation in seismic zone for earthquake resistance. The seismic loads are due to the horizontal and vertical acceleration which may be assumed to act non concurrently. Seismic level Zone- IV, as per new IS- 1893, Year-2002 has to be considered for the design of equipment. The seismic loads shall be equal to static loads corresponding to the weight of the parts multiplied by the acceleration. The equipments along with its parts shall be strong enough and sufficiently well connected to 20 19.0 20.0 21.0 21.1 resist total operating stresses resulting from the forces in normal operation but in case of abnormal condition shall also resist with forces superimposed due to earthquakes. The copies of type test reports for similar rated equipment, if tested earlier, should be furnished along with the tender. If the equipment has not been type tested earlier, design calculations of simulated parameters should be furnished along with the offer. To prevent the movement of GIS sub assemblies i.e. various bay modules during the earthquake, suitable devices shall be provided for fixing the sub assemblies to the foundation. The contractor shall supply necessary bolts for embedding in the concrete foundation. The fixing of GIS sub assemblies to the foundation shall be designed to withstand the seismic events. It will also be ensured that the special devices as well as bolts shall not be over stressed. The details of the devices used and the calculations for establishing the adequacy shall be furnished by the supplier and shall be subject to the purchase’s approval. Partial Discharge Monitoring System & Dew Point Meter etc Static Contact Resistance Meter and Dynamic Contact Resistance Meter, CB operational Analyzer, SF6 Gas Detector Meter, Portable P.D meter & Dew point meter shall be offered as per relevant schedule of BPS and shall be considered for evaluation of bid. The specifications are enclosed at Annexure A. Quality of SF6 Gas a) The SF6 gas insulated metal-clad switchgear shall be designed for use with SF6 gas complying with the recommendations of IEC 376, 376A & 376B, at the time of the first charging with gas. All SF6 gas supplied as part of the contract shall comply with the requirements of IEC as above as a minimum & should be suitable in all respects for use in the switchgear under all operating conditions. b) The high pressure cylinders in which SF6 gas is supplied & stored at site shall comply with the requirements of following standards & regulations: IS: 4379 Identification of the contents of industrial gas cylinders. IS : 7311 Seamless high carbon steel cylinders for permanent & high pressure liquefiable gases. The cylinders shall also meet Indian Boilers Regulations. (Mandatory) c) Test SF6 gas shall be tested for purity, dew point, air, hydrolysable fluorides and water contents as per IEC: 376, 376A & 376B and test certificates shall be furnished to the Employer indicating all test results as per IEC standards for each lot of SF6 gas. Further site tests for moisture, air con-tent, flash point and dielectric strength to be done during commissioning of GIS. Gas bottles should be tested for leakage during receipt at site. d) The successful bidder after award of contract shall indicate diagnostic test methods for checking the quality of gas in the various sections during service. The method proposed shall, as a minimum check the moisture content & the percentage of purity of the gas on annual basis. e) The successful bidder after award of contract shall also indicate clearly the precise procedure to be adopted by maintenance personnel for handling equipment that are exposed to the products of arcing in SF6 Gas so as to ensure that they are not affected by possible irritants of the skin and respiratory system. Recommendations shall be submitted for suitable protective clothing, method of disposal of cleaning utensils and other relevant matters. f) The successful bidder after award of contract shall also indicate the details and type of filters used in various gas sections, and should also submit the operating experience with such filters. SF6 Gas Monitoring Devices and Alarm Circuits Dial type temperature compensated gas density or density monitoring devices with associated pressure gauge will be provided. The devices shall provide continuous & automatic monitoring of the state of the gas & a separate device shall be provided for each gas compartment so that each compartment can be monitored simultaneously as follows:- 21 21.2 22.0 Compartments except circuit breaker a) Gas Refill level This will be used to annunciate the need for the gas refilling. The contractor shall provide contact for remote indication. b) 'Zone Trip' level This is the minimum level at which the manufacturer will guarantee the insulation rating of the assembly. Contacts shall be in accordance with requirement. Circuit Breakers a) 'Gas Refill' level This will be used to annunciate the need for gas refilling. The contractor shall provide a contact for remote indication. b) 'Breaker Block' level This is the minimum gas density at which the manufacturer will guarantee the rated fault interrupting capability of the breaker. At this level the breaker block contact shall operate & the trip-ping & closing circuit shall be blocked. c) 'Zone Trip' level This is the minimum level at which the manufacturer will guarantee the insulation rating of the assembly. Contacts shall be in accordance with requirement. The bidder should furnish temperature v/s pressure curves for each setting of density monitor along with details of the monitoring device. It shall be possible to test all gas monitoring relays/devices without de-energizing the primary equipment & without reducing pressure in the main section. Plugs & sockets shall be used for test purposes. It shall also damp the pressure pulsation while filling the gas in service, so that flickering of the pressure switch contacts does not take place. a) Gas Leakage The maximum gas leakage shall not exceed 0.5% (half percent) per year for the whole equipment and for any individual gas compartment separately. b) Gas Supply The contractor shall include the supply of all SF6 gas necessary for filing & putting into operation the complete switchgear installation being supplied. In addition 20% of total gas requirement shall be supplied in separate cylinders as spare requirement, over & above the requirement of gas for successful commissioning. Pl. refer list of mandatory spares in this connection. Gas Filling and Evacuating Plant All the plant necessary for filling and evacuating the SF6 gas in the switchgear shall be supplied with the contract to enable any maintenance work to be carried out. This shall include all the necessary gas cylinders for temporarily storing the evacuated SF6 gas. The capacity of the temporary storage facilities shall at least be sufficient for storing the maximum quantity of gas that could be removed when carrying out maintenance or repair work on the switchgear and associate equipment of at least one complete bay. Where any item of the filling and evacuating plant is of such a weight that it cannot easily be carried by maintenance personnel, it shall be provided with lifting hooks for lifting and moving with the overhead cranes. The minimum capacity of evacuation plant will be as under : Vacuum Pump: 40 M3/Hour(Nominal suction pressure) Compressor: 15 M3/Hour(Delivery) The capacity of the plant should be such that it is capable of excavation/ filling of maximum quantity of gas contained in a compartment could be removed/ filled within 30 minutes while carrying out maintenance/ repair work. The evacuation equipment shall be provided with all the necessary pipes, couplings, flexible tubes and valves for coupling up to the switchgear for filling or evacuating all the gases. The gas compartments shall preferably be fitted with permanent non-return valves through which the gas is pumped into or evacuated form the compartments. 22 23.0 24.0 25.0 26.0 27.0 28.0 Details of the filling and evacuating plant that will be supplied, as well as the description of the filling and evacuating procedures shall be provided along with the bid. SF6 GIS to XLPE Cable Termination (if applicable) The underground XLPE cables are to be connected to GIS by the interfacing of XLPE cable sealing end to GIS Cable termination enclosure for making connection (as applicable) XLPE cables. This interface section shall be designed in a manner which will allow ease of operation and maintenance. The SF6 GIS to XLPE cable termination shall conform to IEC-859 (latest edition). The provision shall be made for a removable link. The gap created when the link is removed should have sufficient electric strength to withstand the switchgear high voltage site tests. The bidder may suggest alternative arrangements to meet these requirements. The corona rings/stress shields for the control of electrical field in the vicinity of the isolation gap shall be provided by the GIS manufacturer. All supporting structures for the connections between the XLPE cable sealing ends and the GIS shall be supplied by the supplier. The supplier may specify alternative connecting & supporting arrangements for approval of the purchaser. The opening for access shall be provided in each phase terminal enclosures as necessary to permit removal of connectors to isolate the XLPE cables to allow carrying out the insulation tests. The typical arrangement drawing of interconnecting cables from GIS bay module to XLPE cable termination end shall be submitted along with offer. Electric Overhead Crane (If Applicable) EOT Crane of suitable capacity shall be provided for erection & maintenance of largest GIS component/assembly. The crane shall consist of all special requirements for erection & maintenance of GIS equipments. The crane shall be possible to be operated through the cable & through the pendant control, which shall be easily accessible from the floor of GIS building. EOT crane for 66kV GIS shall be of 5T capacity. The crane shall also be provided with speed drive mechanism (frequency drive mechanism). Painting of Enclosure All enclosures shall be painted externally as per manufacturer’s painting procedure. The painting procedures as followed shall be enclosed with the bid. Heaters Wherever required, heaters shall be provided to prevent moisture condensation. Heaters are not allowed in side the main circuit. Identification & Rating Plate Each bay shall have a nameplate showing a) A listing of the basic equipment from air entrance bushing to air entrance bushing (such as a breaker, disconnectors grounding switches, current transformers, voltage transformers, Line Lightning Arrestors and bushings). b) A schematic diagram indicating their relative locations. c) HVPNL Contract Number. Each module will have its own Identification & rating plate. The rating plate marking for each/individual equipment like circuit breaker, disconnectors, grounding switches, Line Lightning Arrestors, current transformer, voltage transformers etc shall be as per their relevant IEC. TRANSPORT OF EQUIPMENT TO SITE. The contractor shall be responsible for the loading, transport, handling and offloading of all equipment and materials from the place of manufacture or supply to site. The contractor shall be responsible to select and verify the route, mode of transportation and make all necessary arrangement with the appropriate authorities as well as determining any transport restrictions and regulations imposed by the government and other local authorities. All transport packages containing critical units viz Circuit breakers, 23 29.0 disconnectors, earthswitches, surge arrestors and bus sections exceeding 3 metres length shall be provided with sufficient number of electronic impact recorders ( on returnable basis ) during transportation to measure the magnitude and duration of the impact in all three directions. The acceptance criteria and limits of impact in all three directions which can be withstood by the equipment during transportation and handling shall be submitted by the contractor during detailed engineering. The recording shall commence in the factory and must continue till the units reach site. The data of electronic impact recorders shall be downloaded at site and a soft copy of it shall be handed over to Engineer – in –charge. Further, within three weeks the contractor shall communicate the interpretation of the data. PACKING, STORAGE AND UNPACKING. All the equipment shall be carefully packed for transport by sea, rail and road in such a manner that it is protected against the climatic conditions and the variations in such conditions that will be encountered enroute from the manufacturer’s works to the site. The SF6 metalclad equipment shall be shipped in the largest factory assembled units that the transport and loading limitations and handling facilities on site will allow to reduce the erection and installation work on site to a minimum. Where possible all items of equipment or factory assembled units shall be boxed in substantial crates or containers to facilitate handling in a safe and secure manner. Should the units be considered too large for packing in crates, they shall be suitably lagged and protected to prevent damage to any part, particularly small projections, during transport and handling. Special lugs or protective supports shall be provided for lifting to prevent slings and other lifting equipment from causing damage. Each crate, container or shipping unit shall be marked clearly on the outside to show where the weight is bearing and the correct position for the slings. Each individual piece to be shipped, whether crate, container or large unit, shall be marked with a notation of the part or parts contained therein. Special precautions shall be taken to protect any parts containing electrical insulation against the ingress of moisture. This applies particularly to the metal clad equipment of which each gas section shall be sealed and pressurized prior to shipping. Either dry nitrogen/air or dry SF6 gas shall be used and the pressure shall be such as to ensure that, allowing for reasonable leakage, it will always be greater than the atmospheric pressure for all variations in ambient temperature and the atmospheric pressure encountered during shipment to site and calculating the pressure to which the sections shall be filled to ensure positive pressure at all times during shipment. The type of gas, the maximum pressure to which sections will be filled prior to shipment and the minimum allowable pressure during shipment shall be advised prior to dispatch. All banking plates, caps, seals, etc., necessary for sealing the gas sections during shipment to site shall be provided as part of the contract and shall remain the property of HVPNL. If considered necessary, blanking plates or other sealing devices shall be provided with facilities for measuring the gas pressure and recharging at any time during the transport period. Any seals, gaskets, ‘O’ rings, etc. that may be used as part of the arrangement for sealing off gas sections for shipment of site, shall not be used in the final installation of the equipment at site. Identification serial numbers shall be stamped into the blanking plates, etc., and on the switchgear equipment to which they are fitted so that they can easily be identified and refitted should it ever be necessary to ship sections of the switchgear back to the manufacturer’s works for repair. Valves and other gas couplings associated with the switchgear gas systems shall be adequately protected against damage from any bumps or physical blows. They shall also be capped to prevent ingress of dirt or moisture or damage to any coupling, pipes, threads or special fittings. Any explosion vents and other pressure relief devices shall be suitably sealed and protected to prevent accidental exposure of the sealed sections during shipment to site. For bus ducts involving male and female joints of the current carrying conductor, the same 24 shall be transported in disassembled condition to avoid any damage during transit. All bright parts liable to rust shall receive a coat of anti rusting composition and shall be suitably protected. The contractor will be able to use the available storage areas at site. The contractor shall ensure that during the period between arrival at site and erection, all materials and parts of the contract works are suitably stored in such approved manner as to prevent damage by weather, corrosion, insects, vermin or fungoral growth. The scope of providing the necessary protection, storing off the ground, as required etc. is included in the works to be performed by the contractor. The equipment shall only be unpacked or removed from the containers immediately prior to being installed. They shall not be left lying unnecessarily in open crates or containers. Special precautions shall be taken when gas sections which have been sealed and pressurized for shipping are opened up to reduce the ingress of dirt and atmospheric moisture to a minimum. Whenever possible this shall only be done immediately prior to installation and if any section is to be left outside for any length of time after being opened, it shall be resealed and pressurized with either dry nitrogen/air or SF6 gas until required. 25 TABLE I – A COREWISE DETAILS OF 72.5kV TRANSFORMER CT FOR 25/31.5 MVA T/F (300-150/0.577-1-1) No. OF CORES = 3 Core Application No. 1 1 2 3 Current Ratio (A) 2 3 DIFFERENTIAL 300-150/0.577 PROTECTION REF PROTECTION 300-150/1 OVER CURRENT PROTECTION 300-150/1 Maximum A.L.F Exciting Current (mA) Output Accuracy Formula for burden class minimum knee(VA) as per point voltage At IEC 185 CT Secondary resistance at 750C at 300A tap (Volt) 4 5 6 7 8 - PS 40(RCT+4) 30 at VK/2 - - PS 40(RCT+4) 30 at VK/2 - 25 5P - - 10 TABLE II – A COREWISE DETAILS OF 72.5kV LINE CT (600-300-150/1-1-1A) No. OF CORES = 3 Core Application No. 1 1 2 3 2 Current Ratio (A) 3 DISTANCE 600-300-150/1 PROTECTION OVER 600-300-150/1 CURRENT & EARTH FAULT PROTECTION METERING 600-300-150/1 Output Accuracy Formula for minimum burden class knee point voltage At CT Secondary (VA) as per resistance at 750C at IEC 185 300A tap (Volt) 4 5 6 Maximum A.L.F./ Exciting I.S.F. Current (mA) 7 8 - PS 80(RCT+4) 40 atVK/2 - 15 5P - - ALF 10 20 0.2S - - ISF<5 for ratio 150/1, ISF<10 for ratio 300/1, ISF<20 for ratio 600/1 NOTE: 1. CT secondary terminals of Line CT shall be brought out in two separate terminal boxes. Box -1 for Core 1& 2and Box 2 for core 3. The second box (Box – 2) shall be provided with proper sealing facility. 2. The provision of auxiliary CT’s is not acceptable in 66kV line CT as these are to be used for commercial metering. 26 TABLE III – A COREWISE DETAILS OF 72.5kV BUS COUPLER CT (600-300-150/1-1A) No. OF CORES = 2 Core Application No. 1 2 Current Ratio (A) 3 Output Accuracy Formula for minimum burden class knee point voltage (VA) as per At CT Secondary IEC 185 resistance at 750C at 300A tap (Volt) 4 5 6 Maximum A.L.F./ Exciting I.S.F. Current (mA) 7 8 1 OVER 600-300-150/1 CURRENT & EARTH FAULT PROTECTION 15 5P - - ALF 10 2 METERING 20 0.2S - - ISF<5 for ratio 150/1, ISF<10 for ratio 300/1, ISF<20 for ratio 600/1 600-300-150/1 27 TABLE I – B COREWISE DETAILS OF 72.5kV POTENTIAL TRANSFORMER (PT) Sl. No. Particulars 1. 2. 3. 4. Rated Primary voltage Type No. of Secondaries Rated voltage factor 5. Rated voltage (volts) 6. 7. 8. 9. Application Accuracy Output burden (VA) Percentage voltage error & phase displacement (minutes) for respective specified accuracy classes. Requirement 66/√3kV Single phase 2 1.2 continuous & 1.5 for 30 seconds Secondary-I Secondary-II 110/√3 110/√3 Protection & Measurement Protection 1/3P 3P 250 25 As per ISS/IEC Note:- Each winding shall fulfill its respective specified accuracy requirement within its specified output range whilst at the same time the other winding has an output of any value form zero to 100% of the output range specified for the other winding in line with clause 6.2.1 of IS 3156 (Part-2 & Part-3) 1992 or its equivalent IEC. 28 1.0 2.0 3.0 i. ii. iii. iv. v. vi. vii. viii. ix. x. xi. i. ii. iii. ANNEXTURE A TECHNICAL SPECIFICATION FOR SPECIAL EQUIPMENTS This part of the document covers detailed technical requirement for the diagnostic tools complete with associated components and accessories including required software for storage of data and interpretation of results etc. DEW POINT METER The meter shall be capable of measuring the due point of SF6 Gas of the Circuit Breaker/ GIS equipment. It should be portable and adequately protected for outdoor use. The meter shall be provided with due point hygrometer with digital indication to display the due point temperature in degree C., degree F or PPM. It should be capable of measuring the corresponding pressure at which due point is being measured. The measurement and use of the instrument must be simple, direct without the use of any other material/ chemical like dry ice/ acetone etc. It should be suitable for operation on 220 Volts AC mains supply. TECHNICAL SPECIFICATION: 1. Measuring Range: Upto-100 º C dew point. 2. Accuracy : ± 2 º C. 3. Display: 4 digit LCD, 0.5 inch high. DIGITAL MICRO-OHM METER FOR CONTACT RESISTANCE MEASUREMENT (As per Annexure A) CIRCUIT BREAKER OPERATIONAL ANALYSER General : Main Equipment The Computer Aided CB Analyzer system comprising of CB operation unit, programme unit, travel analyzer unit & analysis software should be capable to perform close, open, close-open, open-close, open-close, open operation on CB under test, with a facility to introduce time delays between composite operation. The CB Analyzer should be capable to measure, record and analyze the CB operation timing. The CB Analyzer should be able to measure and record current rise and fall of tripping coils as well as of closing coils of all three poles of CB simultaneously. The CB Analyzer should be capable to measure and record travel and speed of movement of operating mechanism of CB. The CB Analyzer should be capable to measure and record dynamic contact resistance of main and arcing contacts of CB with injection of minimum 100 Amp. DC current. The CB Analyzer should be capable to measure pole discrepancy timing. The CB Analyzer should be capable of measuring contact closing & opening timing up to four (04) main and four (04) no. PIR contact. The CB Analyzer should be capable to calculate and print all contact closing & opening tuning in tabular form also. Suitable mounting kits for transducers and sensors, alongwith sensor cable of suitable length should be supplied with CB analyzer system. Test leads with suitable clamp and connectors and having length suitable for leads with suitable clamp and connectors and having length suitable for connection to EHV CBs should be supplied with CB Analyzer system for Necessary custom built travel transformer cum fixtures suitable for mounting on BHEL/ABB/CGL/Siemens/ALSTOM (66 KV and above) makes of CBs, to monitor travel related parameters like contact gap. Contact insertion, over travel etc. should be supplied with CB Analyzer. System Operation hardware/software, peripherals and analysis software. The test report for recording motion should provide test results both in form of curve and tables. The tables should consist of calculated CB parameters such as closing/opening speed etc. The entry of various data/parameters (pertaining to CB) be possible using built in display of menu. The battery backup and real time clock should be provided for automatic date and 29 time functions. a) The computer aided analysis software should have sampling frequency upto 40 KHz or more. b) The analyzer should be capable to record transient phenomenon for a duration at least 500 ms. v. The binary channel accuracy and analogue channel accuracy should be suitable meet all desired functions(stated above) vi. The CB analyzer should be provided with facility of down loading data to a IBM compatible PC. Also the CB analyzer should be provided with facility of down loading data to Laptop to be provided with portable partial discharge monitor for GIS. vii. The printer provided with CB analyzer should be preferably a plain paper printer. viii. The computer aided CB analysis software should be supported with suitable report generation. ix. It should be possible to change scale factor of time axis to enable enlarged view of part of diagram. x. It should be possible to change amplitude scale to make best use of available space. xi. It should be possible to study on speed curve, the damping and speed variations at CB opening and closing time. xii. The CB analyzer should be supplied with portable memory bank to store test result taken by test kit to enable further down loading to centrally located PC. xiii. Window based PC down loading software should be provided with CB analyzer to facilities downloading test result from memory bank to PC where it can be analyzed and stored in proper directory/file. It should be possible to compare present results with previous one. The feature of xiv. Zooming the graph and moving the cursors on graph, thereby indicating instantaneous values of test parameters should also be provided. xv. The latest version of CB analyzer system (hardware’s and software’s) to be supplied and time to time updating of software should be offered. xvi. As and when required, technical support for analysis of critical test result to be offered, on regular basis. Other Essential Requirements. The CB analyzer should operate on power supply of 220 volts (± 10%) at 50 Hz i. (±5%) frequency. The CB analyzer should be capable of working in high electro-magnetic and ii. electrostatic conditions. iii. The CB analyzer should be capable of functioning accurately in environmental condition of temperature 0° to 50° C and humidity (RH) up to 95 %( noncondensing). iv. The CB analyzer should be portable so as to facilitate moment from one site to other and supplied with suitable transportation case. v. The supplier should have adequate after sale service facility. As per ISO: 9001 requirement, celebration certificates for each instrument should be vi. supplied. vii. Installation : a) Indoor/outdoor b) The equipment should be portable easy to handle robust and sturdy, for field applications. 4.0 SF6 GAS LEAK DETECTOR The SF6 gas leak detector shall comprise of circuit breaker operation unit, programme unit, travel analyzer, analyzer software and transducers and other accessories. 4.1 The detector shall be free from induced voltage effects. 4.2 The sensing probe shall be such that it can reach all the points on the breaker where leakage is to be sensed. 5.0 PORTABLE PARTIAL DISCHARGE MONITOR FOR GIS 5.1 GENERAL The equipment shall be used for detecting different types of defects in Gas Insulated Stations(GIS) such as Particles, Loose shields and Partial Discharges as well as for detection of Partial discharges in other types of equipment such as Cable Joints, iv. 30 CTs and PTs. It shall be capable for measuring PD in charged GIS environment as EHV which shall have bandwidth in order of 10 KHz – 500 KHz with possibility to select a wide range of intermediate bandwidths for best measurement results. The principal of operation shall be on acoustic technique and the method of measurement shall be non-intrusive. The instrument is able to detect partial discharges in cable joints, terminations, CTs and PTs etc., with the hot sticks. 5.1.2 Detection and measurement of PD and bouncing particles shall be displayed on built in large LCD display and the measurement shall be stored in the instrument and further downloadable to a PC for further analysis to locate actual source of PD such as free conducting particles, floating components, voids in spacers, particle on spacer surfaces etc. 5.2 TECHNICAL SPECIFICATION: 5.2.1. Measurement shall be possible in noisy environment. 5.2.2. Stable reading shall be possible in presence of vibrations within complex GIS assemblies, which can produce signals similar to PD. 5.2.3. Equipment should have necessary synchronizing circuits to obtain PD correlation with power cycle and power frequency. 5.2.4. The equipment shall be battery operated with built-in-battery charger. It shall also be suitable for 230V AC/50 Hz input. 5.2.5. Measurement shall be possible in the charged switchyard in the presence of EMI/EMC. Supplier should have supplied similar detector for GIS application to other utilities. Performance certificate and the list of users shall be supplied along with the offer. 5.2.6. Instrument shall be supplied with standard accessories i.e., re-locatable sensors with mounting arrangements, connecting cables (duly screened) to sensors, Lap-top (i5/i7 or higher version fully compatible with PD measurement device & CB Analyser with required software’s), diagnostic software, carrying case, rechargeable battery pack with charger suitable for 230V AC, 50Hz supply connecting cables (duly screened) to view in storage. 5.2.7. The function of software shall be covering the following: Data recording, storage and retrieval in computer − Data base analysis − Template analysis for easy location of fault inside the GIS − Evaluation of PD measurement i.e, Amplitude, Phase Synchronization etc. − Evaluation of bouncing/loose particles with flight time and estimation on size − of particle. Report generation − 5.2.8. To prove the suitability in charged switchyard condition, practical demonstration shall be conducted before acceptance. 5.2.9. Supplier shall have “Adequate after sales service” facility in India. 5.2.10. Necessary training may be accorded to personnel to make use of the kit for locating PD sources inside the GIS 5.2.11. Instrument shall be robust and conform to relevant standard. 6.0 SPECIFICATION FOR DIGITAL EARTH RESISTANCE METER (As per Annexure B) 5.1.1 7.0 8.0 5 kV AUTOMATED INSULATION RESISTANCE TESTER (As per Annexure C) DC LEAKAGE TESTER 31 ANNEXURE-‘A’ TECHNICAL SPECIFICATION OF CONTACT RESISTANCE/ MICRO OHM METER GENERAL REQUIREMENTS 1.0 SCOPE: 1.1 This specification covers the design, engineering, manufacture, inspection & testing at manufacturer’s work before dispatch, packing, forwarding and delivery at the discretion of Purchaser of various testing equipment listed in the schedule of requirements at Annexure-A. 1.2 Unless specifically excluded from the offer, all fittings and accessories, not specifically stated in this specification but which are necessary for satisfactory operation of the scheme or to complete the work in a good workman like manner shall be deemed to have been included in the scope of supply of the Bidder. 1.3 The Demonstration of the equipment in live EHV switchyard upto 400kV S/Stn. and satisfactory performance as per GTP requirement i.e. the consistency and repeatability of test results shall be the criteria of acceptability of successful bidder thereafter part-II (price bid) of the tender shall be opened. 2.0 SERVICE CONDITIONS: Equipment to be supplied against this specification shall be suitable for satisfactory continuous operation under the following tropical conditions:i. ii. iii. iv. v. vi. vii. viii. ix. x. Location IN THE STATE OF HARYANA Max. ambient air temp (0C) 50 0 Min. ambient air temp ( C) -2.5 Max. relative humidity (%) 100 Min. relative humidity (%) 26 Average annual rainfall (mm). 900 Max. Wind pressure (kg/sq.m) 195 Max.Altitude above mean sea level (meters) 1000 Isoceraunic level (days/year) 50 Seismic level (horizontal acceleration) 0.3g Note: Moderately hot and humid tropical climate conducive to rust and fungus growth. The climatic conditions are also prone to wide variations in ambient conditions. 3.0 MATERIAL AND WORKMANSHIP: All the materials used in the construction of the equipment shall be of the best quality obtainable of their respective kinds and whole of the work shall be of the highest class, well finished and of approved design and make. Castings shall be free from blowholes, flaws, cracks or other defects and shall be smooth grained and of true dimensions and forms. 4.0 DEPARTURE FROM THE SPECIFICATIONS: Should the tenderer wish to depart from provision of this specification either on account of a manufacturing practice or for any other reasons, he will draw specific attention to the proposed points of departure on the prescribed performa (enclosed) at Annexure-B in his tender and submit such full information, drawings & specifications as will enable the merit the merit of his proposal to be appreciated. 32 In the event of contractor drawings, specification and table etc. disagreeing with this specification during the execution of the contract, this specification shall be held binding unless the departures have been fully recorded as required above. 5.0 SITE DEMONSTRATION:- The successful bidder(s) will be required to demonstrate the performance of their offered equipment(s) at four locations in Haryana so as to familiarize the purchaser’s Engineers/technicians for use of a given testing equipment. These demonstrations will be free of charge & will be planned soon after the supplies are made so as to make use of the testing equipments. Apart from the detailed demonstration at site, the supplier shall also have to arrange necessary training to HVPNL engineers. 6.0 NAME PLATE: An easily accessible engraved or painted name plate shall be provided on each equipment. It must include purchase order No., supplier’s reference No. & item number as per purchase order. 7.0 INSPECTION AT MANUFACTURERS WORKS: 7.1 All equipment shall be subject to routine tests according to the relevant standards and to such other tests as may be required to ensure that all equipment is satisfactory and in accordance with this specification. The Purchaser reserves the right to witness all the tests, unless dispensed with in writing by the purchaser. 7.2 The supplier shall give sufficient advance intimation at least 15 days notice to the purchaser to enable him to depute his representative for witnessing the tests to prove the test equipment. 8.0 GENERAL TECHNICAL REQUIREMENT: (i) (ii) Supply Voltage Frequency (iii) The testing set shall be capable of working in hostile condition of electrostatic field prevailing in charged HV/EHV Substations up to 400 kV of high voltage and of high interference environment. 9.0 DOCUMENTATION: : : Single Phase AC, 230 Volt +10% 50 Hz + 3% The supplier shall furnish nicely printed and bound volumes of the instruction manuals in English language, prior to the dispatch of the equipment. The instruction manual shall contain step by step instructions for all operational & maintenance requirements for all the testing equipments. If should also include the GA & detailed schematic drawings including internal wiring diagram of the various equipments to facilitate its repair at site incase of any defect. The number of sets of instruction manuals to be supplied shall be as under: i) Two sets for CE/MM, HVPNL, Panchkula ii) Five sets separately bound for each item for SE/M&P-Cum-Carrier Circle, HVPNL, Delhi & five sets for SE/M&P-Cum-Carrier Circle, HVPNL, Ambala. 33 TECHNICAL SPECIFICATION OF CONTACT RESISTANCE METER/MICRO OHM METER GENERAL:- The instrument should be capable of measuring contact resistance of EHV circuit breakers, isolators, Bus Bar joints & connectors/jumpers etc. ranging from few micro Ohms to few hundred milli Ohms, by applying continuous D.C. current min. 100 Amps. From a constant current source built in inside the instrument; having digital read out of the value of resistance measured and test current using microprocessor based control logic & precision instrumentation. The instrument should be capable of carrying out the measurement in live EHV switchyards having high electrostatic & electromagnetic interference. The size (cross sectional area) of test lead should be suitable to carry out Min. 100 Amps. Current or higher continuously without appreciable rise in temp. The Clamp & connectors should also be suitable for accurate measurement of contact resistance of specimen. Technical Specs: 1. The instrument should provide direct reading of the resistance of specimen & test current. 2. Test current: Min. 100 Amps. (or higher), continuous variation, regular or in steps. 3. Resistance: Range 0 to 1999 micro Ohm 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. Resolution 0.1 Micro Ohm or better Accuracy ± 1% or better Display: Digital Readout Test Lead Length : 15 Meter long Input Power: Mains operated; 230 Volts (nominal) ±10%, 50Hz±3% Memory : On Board of upto 100 test results. Interface: PC Interface and Inbuilt Printer Environment: a) Operating Temp. Range: 00 to 500 C b) Operating R.H.: at least upto 90% (non condensing) Calibration Facility i.e. Standard Shunt (of accuracy better than equipment) should be provided with test kit as additional attachment. Calibration certificate for complete range of test instrument should not be older than 2 months shall be supplied with it. Successful demonstration in live EHV switchyard is criteria for acceptability. Kit should be able to make measurement of contact resistance safely while keeping both the sides of breakers grounded and with jumper connected. Accessories:- 2 Nos. of certified Shunts of value 75µΩ and 500 µΩ each of sufficient current cap to check accuracy of kit during testing should be provided. Safety : Should meet the requirement of EN61010-1 and EN61326 Equipment shall be portable. 34 ANNEXURE-B TECHNICAL SPECIFICATION OF PORTABLE DIGITAL EARTH RESISTANCE TESTER GENERAL REQUIREMENTS 1.0 SCOPE: 1.1 This specification covers the design, engineering, manufacture, inspection & testing at manufacturer’s work before dispatch, packing, forwarding and delivery at the discretion of Purchaser of various testing equipment listed in the schedule of requirements at Annexure-A. 1.2 Unless specifically excluded from the offer, all fittings and accessories, not specifically stated in this specification but which are necessary for satisfactory operation of the scheme or to complete the work in a good workman like manner shall be deemed to have been included in the scope of supply of the Bidder. 1.3 The Demonstration of the equipment in live EHV switchyard upto 400kV S/Stn. and satisfactory performance as per GTP requirement i.e. the consistency and repeatability of test results shall be the criteria of acceptability of successful bidder thereafter part-II (price bid) of the tender shall be opened. 2.0 SERVICE CONDITIONS: Equipment to be supplied against this specification shall be suitable for satisfactory continuous operation under the following tropical conditions:i. ii. iii. iv. v. vi. vii. viii. ix. x. Location IN THE STATE OF HARYANA 50 Max. ambient air temp (0C) 0 Min. ambient air temp ( C) -2.5 Max. relative humidity (%) 100 Min. relative humidity (%) 26 Average annual rainfall (mm). 900 Max. Wind pressure (kg/sq.m) 195 Max.Altitude above mean sea level (meters) 1000 Isoceraunic level (days/year) 50 Seismic level (horizontal acceleration) 0.3g Note: Moderately hot and humid tropical climate conducive to rust and fungus growth. The climatic conditions are also prone to wide variations in ambient conditions. 3.0 MATERIAL AND WORKMANSHIP: All the materials used in the construction of the equipment shall be of the best quality obtainable of their respective kinds and whole of the work shall be of the highest class, well finished and of approved design and make. Castings shall be free from blowholes, flaws, cracks or other defects and shall be smooth grained and of true dimensions and forms. 35 4.0 DEPARTURE FROM THE SPECIFICATIONS: Should the tenderer wish to depart from provision of this specification either on account of a manufacturing practice or for any other reasons, he will draw specific attention to the proposed points of departure on the prescribed performa (enclosed) at Annexure-B in his tender and submit such full information, drawings & specifications as will enable the merit the merit of his proposal to be appreciated. In the event of contractor drawings, specification and table etc. disagreeing with this specification during the execution of the contract, this specification shall be held binding unless the departures have been fully recorded as required above. 5.0 SITE DEMONSTRATION:- The successful bidder(s) will be required to demonstrate the performance of their offered equipment(s) at four locations in Haryana so as to familiarize the purchaser’s Engineers/technicians for use of a given testing equipment. These demonstrations will be free of charge & will be planned soon after the supplies are made so as to make use of the testing equipments. Apart from the detailed demonstration at site, the supplier shall also have to arrange necessary training to HVPNL engineers. 7.0 NAME PLATE: An easily accessible engraved or painted name plate shall be provided on each equipment. It must include purchase order No., supplier’s reference No. & item number as per purchase order. 7.0 INSPECTION AT MANUFACTURERS WORKS: 7.1 All equipment shall be subject to routine tests according to the relevant standards and to such other tests as may be required to ensure that all equipment is satisfactory and in accordance with this specification. The Purchaser reserves the right to witness all the tests, unless dispensed with in writing by the purchaser. 7.2 The supplier shall give sufficient advance intimation at least 15 days notice to the purchaser to enable him to depute his representative for witnessing the tests to prove the test equipment. 8.0 GENERAL TECHNICAL REQUIREMENT: (i) (ii) Supply Voltage Frequency (iii) The testing set shall be capable of working in hostile condition of electrostatic field prevailing in charged HV/EHV Substations up to 400 kV of high voltage and of high interference environment. 9.0 DOCUMENTATION: : : Single Phase AC, 230 Volt +10% 50 Hz + 3% The supplier shall furnish nicely printed and bound volumes of the instruction manuals in English language, prior to the dispatch of the equipment. The instruction manual shall contain step by step instructions for all operational & maintenance requirements for all the testing equipments. If should also include the GA & detailed schematic drawings including internal wiring diagram of the various equipments to facilitate its repair at site incase of any defect. 36 The number of sets of instruction manuals to be supplied shall be as under: i) Two sets for CE/MM, HVPNL, Panchkula ii) Five sets separately bound for each item for SE/M&P-Cum-Carrier Circle, HVPNL, Delhi & five sets for SE/M&P-Cum-Carrier Circle, HVPNL, Ambala. 10.0 A. PORTABLE DIGITAL EARTH RESISTANCE TESTER Digital earth resistance tester shall be suitable for accurate measurement of earth resistance of electrical installations and soil resistivity. The tester should be free from the effect of AC earth stray & electrolytic fields as the same is to be used in the live switchyard up to 400 kV. The tester should be powered by rechargeable battery. Low battery indication be provided enabling the user to charge it by connecting it to 230Volt, 50 Hz main supply. (The supply is subject to + 10% fluctuation in voltage and + 3% fluctuation in frequency). The instrument shall have range of 0-20 K ohms with a resolution of 0.01 ohm. The accuracy of the instrument shall be + 2% of selected range. 1. The instrument should be supplied along with its measurement leads (Red-15m, Yellow-10m, Green-5m), earth spikes (2 Nos.), charging leads, battery charger and a metal carrying case for safe transportation. 2. The output voltage = 30V peak minimum (at a test frequency different from 50Hz to avoid electro magnetic interference. The indication of high noise and high resistance of spikes (current & potential) provided in test instrument. Comply with testing requirements set by international standards. Measurement should not be influenced by electrostatic/electromagnetic interference present in EHV switchyards. Measurement of disturbance voltage be provided. 3. 4. 5. 6. 7. Should be able to perform fall of potential and clamp on technique in same kit for earth resistance measurement along with soil resistivity and touch potential. The size of clamp shall be such that it can measure for earthing flats of size 75x12 mm2. 8. In-built printer or printer port for external printer connection/PC interface and having inbuilt memory for atleast 100 measurements. B) Technical Specifications: Sr. No. 1. 2. 3. Parameters Data Earth Resistance Range Accuracy (At Temp. 230 C Test Frequency 0.01 Ohm to 20 K Ohms (Auto ranging and digital) ±2% upto 200 ohm, ±3% above 200ohm 100 Hz to 150 Hz maximum output voltage : ≤50 Volts 37 4. Display Digital LCD/Key Pad 5. Environmental Conditions 6. EMC 7. IP Rating Operating Temp. : Upto 500 C Operating R.H.: Upto 90% (at 400 C), non condensing In accordance with IEC-61326 (including amendment No. 1) IP54 C) Power Supply: a) Rechargeable Battery/Cells b) Charger: Internal/External c) Charger: Suitable for 230 Volts. Single Phase 50 Hz, AC supply. d) Other essential requirements: 1. The calibration certificate should not be older than 2 months from the date of supply of test kit (for entire range). 2. The earth testing kit should be supplied complete in all respect i.e. with suitable spikes and test leads, clamps for stakes less measurement etc. 3. The acceptable criteria of the equipment demonstration in live EHV switchyard. 4. Test kit shall be hand held/portable and carrying case shall be provided. 5. The test kit shall be compatible for EMC/EMI/Safety environment requirement as per IEC. shall be successful 38 ANNEXURE-‘C’ TECHNICAL SPECIFICATION OF SELF DIAGNOSTIC 5 KV DIGITAL INSULATION RESISTANCE TESTER GENERAL REQUIREMENTS 1.0 SCOPE: 1.1 This specification covers the design, engineering, manufacture, inspection & testing at manufacturer’s work before dispatch, packing, forwarding and delivery at the discretion of Purchaser of various testing equipment listed in the schedule of requirements at Annexure-A. 1.2 Unless specifically excluded from the offer, all fittings and accessories, not specifically stated in this specification but which are necessary for satisfactory operation of the scheme or to complete the work in a good workman like manner shall be deemed to have been included in the scope of supply of the Bidder. 1.3 The Demonstration of the equipment in live EHV switchyard upto 220kV S/Stn. and satisfactory performance as per GTP requirement i.e. the consistency and repeatability of test results shall be the criteria of acceptability of successful bidder thereafter part-II (price bid) of the tender shall be opened. 2.0 SERVICE CONDITIONS: Equipment to be supplied against this specification shall be suitable for satisfactory continuous operation under the following tropical conditions:i. ii. iii. iv. v. vi. vii. viii. ix. x. Location IN THE STATE OF HARYANA 0 50 Max. ambient air temp ( C) Min. ambient air temp (0C) -2.5 Max. relative humidity (%) 100 Min. relative humidity (%) 26 Average annual rainfall (mm). 900 Max. Wind pressure (kg/sq.m) 195 Max.Altitude above mean sea level (meters) 1000 Isoceraunic level (days/year) 50 Seismic level (horizontal acceleration) 0.3g Note: Moderately hot and humid tropical climate conducive to rust and fungus growth. The climatic conditions are also prone to wide variations in ambient conditions. 3.0 MATERIAL AND WORKMANSHIP: All the materials used in the construction of the equipment shall be of the best quality obtainable of their respective kinds and whole of the work shall be of the highest class, well finished and of approved design and make. Castings shall be free from blowholes, flaws, cracks or other defects and shall be smooth grained and of true dimensions and forms. 39 4.0 DEPARTURE FROM THE SPECIFICATIONS: Should the tenderer wish to depart from provision of this specification either on account of a manufacturing practice or for any other reasons, he will draw specific attention to the proposed points of departure on the prescribed performa (enclosed) at Annexure-B in his tender and submit such full information, drawings & specifications as will enable the merit the merit of his proposal to be appreciated. In the event of contractor drawings, specification and table etc. disagreeing with this specification during the execution of the contract, this specification shall be held binding unless the departures have been fully recorded as required above. 5.0 SITE DEMONSTRATION:- The successful bidder(s) will be required to demonstrate the performance of their offered equipment(s) at four locations in Haryana so as to familiarize the purchaser’s Engineers/technicians for use of a given testing equipment. These demonstrations will be free of charge & will be planned soon after the supplies are made so as to make use of the testing equipments. Apart from the detailed demonstration at site, the supplier shall also have to arrange necessary training to HVPNL engineers. 6.0 NAME PLATE: An easily accessible engraved or painted name plate shall be provided on each equipment. It must include purchase order No., supplier’s reference No. & item number as per purchase order. 7.0 INSPECTION AT MANUFACTURERS WORKS: 7.1 All equipment shall be subject to routine tests according to the relevant standards and to such other tests as may be required to ensure that all equipment is satisfactory and in accordance with this specification. The Purchaser reserves the right to witness all the tests, unless dispensed with in writing by the purchaser. 7.2 The supplier shall give sufficient advance intimation at least 15 days notice to the purchaser to enable him to depute his representative for witnessing the tests to prove the test equipment. 8.0 GENERAL TECHNICAL REQUIREMENT: (i) (ii) Supply Voltage Frequency (iii) The testing set shall be capable of working in hostile condition of electrostatic field prevailing in charged HV/EHV Substations up to 220 kV of high voltage and of high interference environment. 9.0 DOCUMENTATION: : : Single Phase AC, 230 Volt +10% 50 Hz + 3% The supplier shall furnish nicely printed and bound volumes of the instruction manuals in English language, prior to the dispatch of the equipment. The instruction manual shall contain step by step instructions for all operational & maintenance requirements for all the testing equipments. If should also include 40 the GA & detailed schematic drawings including internal wiring diagram of the various equipments to facilitate its repair at site incase of any defect. The number of sets of instruction manuals to be supplied shall be as under: i) Two sets for CE/MM, HVPNL, Panchkula ii) Five sets separately bound for each item for SE/M&P-Cum-Carrier Circle, HVPNL, Delhi & five sets for SE/M&P-Cum-Carrier Circle, HVPNL, Ambala. TECHNICAL SPECIFICATION OF DIGITAL HIGH VOLTAGE 5 KV INSULATION RESISTANCE TESTER Sr. Parameters Data No. 1. Test Voltage (DC V) 50V to 1KV in steps of 10V , 1kV to 5kV in steps of 25V with fixed ranges of 500, 1000, 2.5kV and 5KV 2. Insulation Resistance 0 to 1 TΩ Measuring Ranges (AutoRange) 3. Accuracy ±5% of reading 4. Capacitance measuring 10nF to 25 uF with accuracy of ±10% range 5. Current measuring range ±0.01nA to 5mA with accuracy of ±5% 6. Timer Range 0 to 99 minutes 7. Testing parameters IR, PI, DAR, 8. Guarding 2% error guarding 500 k Ohm leakage with 100 M Ohm load 9. IP Rating IP65 10. Storage On board storage of measurement with time stamping upto 100 results or more 11. Dimensions Should be portable 12. Weight (Battery Included) Approx. 10Kg 13. Power Source In Built Rechargeable Battery (Li ion) with 6 Hrs continuous testing at 5Kv with 100 MΩ load and shall be operational on main and battery individually and simultaneously. BATTERY SHALL MEET IEC 62133 14. Accessories Test leads 15 meters each (good insulation)+ large clips, software, screened USB Cable. Features:• Microprocessor controlled with advanced safety features. • Display and sound warning if external voltage is present • Continuous Battery monitoring. • Auto-Ranging/Auto Power –off • Built –in –Carrying case, test leads in separate pouch. • Real-time bar graph display on test voltage and voltage decay during discharge • Audible and visual message displayed if external voltage is present • Large LCD • Automatic Calculation of P.I., DAR. • Should display direct reading of test voltage across the test piece when test is in progress. 41 • Should meet safety requirement of EN 61010-1 and EMC requirement of 6EN61326-1. • Should work in presence of high interference of switch yard up to 220KV. • Should have PC interface for transfer of Data. • Instrument should have Cat-IV 600 V Safety. • Shall have self auto calibration feature at the time of starting or calibration box of suitable value decayed resistance of 5 kV shall be supplied with testing equipment. • The testing equipment shall work satisfactorily in presence of noise i.e. electromagnetic/electrostatic or any other interference in live switchyard upto 220kV S/Stns. and shall provide suitable noise rejection upto level of 4mA or less with filter option enabling the testing equipment to work satisfactorily in live switchyard of 220kV level having high interference (substation will be as per selection of HVPNL). 42 Section – 4, Chapter – 2 TECHNICAL SPECIFICATION FOR SURGE ARRESTORS (LIGHTNING ARRESTORS) 1.0 1.1 1.2 2.0 2.1 Note: i.) ii.) 2.2 3.0 3.1 a) b) c) SCOPE: This specification provides for the design, engineering, manufacture, assembly, stage testing, inspection and testing before dispatch, packing, forwarding and delivery at site of Metal Oxide (gapless) 198 kV, 120 kV, 60 kV, 30 kV & 9 kV Surge Arrestors complete with discharge counter, insulating base and other accessories for all rating arresters except 9 kV & 30 kV surge arrester as specified hereunder. It is not the intent to specify completely herein all the details of design and construction of Surge Arrestors. However, Surge Arrestors shall conform in all respects to the high Standard of design and workmanship and be capable of performing in continuous commercial operation up to Bidder's guarantee in a manner acceptable to HVPNL. The Arrestors offered shall be complete with all parts, necessary for their effective and trouble free operation. Such components shall be deemed to be within the scope of supply, irrespective of whether they are specifically brought out in the commercial order or not. STANDARDS: The Surge Arrestors shall conform to the latest editions and amendments available at the time of supply, of the standards listed hereunder. Sl. Standard Title No. Ref. No. 1. IEC:99-4 Specification Part-4 for Surge Arrestors without gap for AC system. 2. IS:3070 Specification for Lightning Arrestors for alternating current system (Part-III) 3. IS: 2629 Recommended practice for hot dip galvanizing of iron and steel. 4. IS: 2633 Method for testing uniformity of coating on zinc coated articles. 5. IS:5621 Specification for large hollow porcelain for use in electrical installation. 6. IS:2147 Degree of protection provided by enclosures for low voltage switchgear and control. 7. Indian Electricity Rules, 1956. For the purpose of this specification all technical terms used hereinafter shall have the meaning as per IEC/ISS specification. For the parameters of the Arrestor which are not specified in IEC specification for Surge Arrestors, the provisions of IS: 3070 (Part-I) shall be applicable. Surge Arrestors meeting with the requirements of other authoritative standards, which ensure equal or better quality than the standards mentioned above shall also be acceptable. Where the equipment offered by the Bidder conforms to other standards, salient points of difference between the standards adopted and the specified standards shall be clearly brought out in the offer. Four (4) copies of the reference standards in English language shall be furnished along with the offer. SERVICE CONDITIONS: As per section-1 Vol-II AUXILIARY POWER SUPPLY: The equipment offered under this specification shall be suitable for the following auxiliary power supplies. Power Devices (like drive motors) 415V, 3 Phase, 4 wire 50 Hz, neutral grounded AC supply AC Control and protective devices, lighting 240V, single space, 2 wire 50 Hz, fixtures, space heaters neutral grounded AC supply DC alarm, control and protective devices 220V, DC 2-Wire Each of the foregoing supplies shall be made available by the HVPNL at the terminal point for each equipment for operation of accessories and auxiliary equipment. Bidder’s scope -1- i.) ii.) 4.0 5.0 5.1 5.2 5.3 5.4 5.5 5.6 5.6.1 5.6.2 5.6.3 shall include supply of interconnecting cables, terminal boxes, etc., The above supply voltages may vary as below and all devices shall be suitable for continuous operation over entire range of voltages. AC Supply-voltage+10%&-15% frequency + 5% DC Supply-15% to +10% SYSTEM PARAMETERS: The Surge Arrestors offered under this specification shall conform to the parameters given below: Sl. Particulars System Voltage (KV rms) No. 220 132 66 33 11 1. Nominal system voltage (kV rms) 220 132 66 33 11 2. Highest system voltage (kV rms) 245 145 72.5 36 12 3. 1.2/50 microsecond impulse voltage withstand level a) Transformers and Reactors (kVp) 900 550 325 170 75 b) Other equipment and lines (kVp) 1050 650 325 170 75 4. Minimum prospective symmetrical 40 31.5 31.5 26.3 18.4 fault current for 1 second at Arrestor location (kA rms) 5. Anticipated levels of Temporary over voltage and its duration a) Voltage (p.u.) 1.5/1.2 1.5/1.2 1.5/1.2 1.5/1.2 1.5/1.2 b) Duration (Seconds) 1/10 1/10 1/10 1/10 1/10 6. System frequency(Hz) --------------------- 50 ± 2.5 C/S ---------------------7. Neutral Grounding E.E* E.E* E.E* E.E* E.E* 8. Number of Phases ----------------------- Three -------------------*E/E = Effectively earth GENERAL TECHNICAL REQUIREMENTS: The Surge Arrestors shall conform to the technical requirements as per Annexure-II. The energy handling capability of each rating of Arrestor offered, supported by calculations, shall be furnished in the offer. The Surge Arrestors shall be fitted with pressure relief devices and arc diverting ports and shall be tested as per the requirements of IEC specification for minimum prospective symmetrical fault current as specified in Clause 4.0 (4). The grading ring on each complete Arrestor for proper stress distribution shall be provided if required for attaining all the relevant technical parameters. PROTECTIVE LEVELS: The basic insulation levels and switching impulse withstand levels of the lines and equipment to be protected, have been specified in clause 4.0, "Principal Parameters". The protective characteristics of the Arrestors offered shall be clearly specified in the schedule of guaranteed technical particulars. GENERAL REQUIREMENTS: The materials and components not specifically stated in this specification but which are necessary for satisfactory operation of the equipment are deemed to be included in the scope of supply unless specifically excluded. Unless otherwise brought out separately by the Bidder in the schedule of deviations the Surge Arrestors offered shall conform to the specification scrupulously. All deviations from the specification shall be brought out in the schedule of deviations. The discrepancies between the specification and the catalogues or literature submitted as part of the offer shall not be considered as valid deviations unless specifically brought out in the schedule of deviations. Any deviation which has not been specifically brought out in the schedule of deviations of the Bid Proposal Sheets, shall not be given effect to. The deviations brought out in the -2- 5.6.4 5.6.5 5.6.6 5.7 5.7.1 5.7.2 5.7.3 5.7.4 5.7.5 5.8 5.8.1 5.8.2 5.8.3 5.8.4 5.8.5 5.9 5.9.1 5.9.2 5.9.3 5.10 5.10.1 5.10.2 5.10.3 5.11 schedule shall be supported by authentic documents, standards and other references. Each individual unit of Surge Arrestor shall be hermetically sealed and fully protected against ingress of moisture. The hermetic seal shall be effective for the entire life time of the Arrestor and under the service conditions as specified. The Bidder shall furnish sectional view of the Arrestor, showing details of sealing employed. The Bidder shall furnish in the offer, a sectional view of pressure relief device employed in the Surge Arrestors offered. The Surge Arrestors shall be suitable for hot line washing. CONSTRUCTION: All the units of Arrestors of same rating shall be inter changeable without adversely affecting the performance. The Surge Arrestors shall be suitable for pedestal type mounting. All the necessary flanges, bolts, nuts, clamps etc., required for assembly of complete Arrestor with accessories and mounting on support structure to be supplied by the HVPNL, shall be included in Bidder's scope of supply. The drilling details for mounting the Arrestor on HVPNL's support shall be supplied by the Contractor. The minimum permissible separation between the Surge Arrestor and any earthed object shall be indicated by the Bidder in his offer. PORCELAIN HOUSING: All porcelain housings shall be free from lamination cavities or other flaws affecting the maximum level of mechanical and electrical strengths. The porcelain shall be well vitrified and nonporous. The Creepage distance of the Arrestor housing shall be as per Annexure-I. The porcelain petticoat shall be preferably of self-cleaning type (Aerofoil design). The details of the porcelain housing such as height, angle of inclination, shape of petticoats, gap between the petticoats, diameter (ID and OD) etc., shall be indicated by the Bidder in his offer in the form of a detailed drawing. The Arrestor housing shall conform to the requirements of IEC/ISS specification. GALVANISATION, NICKEL PLATING ETC.: All ferrous parts exposed to atmosphere shall be hot dip galvanised as per IS:2629 as amended from time to time., Tinned copper/brass lugs shall be used for internal wiring of discharge counter. Screws used for electrical connections shall be either made of brass or nickel plated. Ground terminal pads and name plate brackets shall be hot dip galvanised. The material shall be galvanised only after completing all shop operations. ACCESSORIES AND FITTINGS: Discharge counters shall be provided for the Arrestors except for 9 kV and 30 kV Arresters. The discharge counter shall be provided with milli-ammeter for measuring the leakage current and shall not require any DC or AC Aux. supply. It shall be suitable for outdoor use. The installation of discharge counter shall not adversely affect the Arrestor performance. The discharge counter shall register operation whenever lightning or any other type of surge strikes the Surge Arrestor. All necessary accessories and Earthing connection leads between the bottom of the Arrestor and the discharge counter shall be in the Bidder's scope of supply. The connecting lead between discharge counter and Surge Arrestor shall be of copper flexible tape of size 25x4 mm and minimum of 1.5 meter length. The discharge counter shall be so designed that the readings of discharges recorded by the counter and the readings of milli– ammeter shall be clearly visible through an inspection window to a person standing on ground. The minimum height of HVPNL's support shall be 2.5 Meters. Terminal connector conforming to IS: 5561 shall be supplied along with the arrester. Each Surge Counter shall have terminals of robust construction for connection to Earthing lead and these shall be suitably arranged so as to enable the incoming and outgoing connections to be made with minimum bends. -3- 5.11.1 Suitable grounding terminal shall be provided for earthing of surge arrestors up to water level. Proper functioning of the Surge counter with Surge Arrestor shall be ensured by the Bidder. 5.12 NAME PLATE: The arrestor shall be provided with non-corrosive legible name plate indelibly marked with the following information: 1. Haryana Vidyut Prasaran Nigam Ltd. 2. Order No. 3. Manufacturer's name or trade mark and identification of the Arrestor being supplied. 4. Rated voltage. 5. Maximum continuous operating voltage. 6. Type. 7. Rated Frequency. 8. Nominal discharge current. 9. Long duration discharge class. 10. Pressure relief current in kA rms. 11. Year of manufacture. 6.0 TESTS: 6.1 TYPE TESTS: The equipment should be offered type test. Test reports should not more then seven years old reckoned from date of bid opening in respect of all the tests carried out in accredited laboratories (based on ISO/IEC) by a reputed accredited body or witnessed by HVPN or another electric power utility and be submitted by the successful bidder to HVPNL for approval as schedule given in Bar Chart. i.) Insulation withstand test. ii.) Residual voltage test. iii.) Long duration current impulse withstand test. iv.) Operating duty test. v.) Pressure relief test. vi.) Test of arrestor dis-connector. vii.) Artificial pollution test on porcelain housed arrestors. viii.) Temperature cycle test on porcelain housed arrestors. ix.) Porosity test on porcelain house arrestors. x.) Galvanising test on exposed ferrous metal parts. 6.2 ROUTINE TESTS: As per quality assurance program (QAP). 6.3 ACCEPTANCE TESTS: The following acceptance tests as stipulated in the relevant IS:3070 (PART-III) 1993 shall be carried out by the Supplier in presence of HVPNL representative, unless dispensed with in writing by the HVPNL. i.) Measurement of power frequency reference voltage. ii.) Lightening impulse residual voltage test. iii.) Partial discharge test. 6.4 SURGE MONITOR The following routine test shall be performed in the presence of HVPNL’s representative: i.) Tests for satisfactory operation of surge counter while discharging surges. ii.) Test for correctness of leakage current meter before and after the passage of surges. iii.) Visual examination tests. 7.0 INSPECTION: The inspection may be carried out by the HVPNL at any stage of manufacture. The 7.1 successful Bidder shall grant free access to the HVPNL's representative at all times to the works and all other places of manufacture, where equipment are being manufactured and the Contractor shall provide all facilities without extra charges, for unrestricted inspection of the Contractor's works, raw materials, manufacture of the equipment., all the accessories -4- and for conducting necessary test as detailed herein. The Contractor shall keep the HVPNL informed in advance, about the manufacturing program so that arrangement can be made for inspection. No material shall be dispatched from its point of manufacture unless the material has been 7.3 satisfactorily inspected and tested. The HVPNL reserves the right to insist for witnessing the acceptance/routine testing of the 7.4 bought out items. The Contractor shall submit their internal inspection report containing manufacturer's test 7.5 certificates before offering the material for inspection. 7.6 The acceptance of any quantity of equipment shall in no way relieve the Contractor of his responsibility for meeting all the requirements of this specification and shall not prevent subsequent rejection if such equipment are later found to be defective. 8.0 DOCUMENTATION: 8.1 The successful bidder shall submit four sets of following drawings for HVPNL approval. List of drawings:i.) General outline drawings of the complete Arrestors with technical parameters. ii.) Drawing showing clearance from grounded and other live objects and between adjacent poles of Surge Arrestors, required at various heights of Surge Arrestors. iii.) Drawings showing details of pressure relief devices. iv.) Detailed drawing of discharge counters along with the wiring and schematic drawing of discharge counter and meter. v.) Outline drawing of insulating base. vi.) Details of grading rings, if used. vii.) Mounting details of Surge Arrestors. viii.) Details of line terminal and ground terminals. ix.) Volt-time characteristics of Surge Arrestors. x.) Details of galvanising being provided on different ferrous parts. xi.) The detailed dimensional drawing of porcelain housing such as ID, OD, thickness and insulator details such height, profile of petticoats, angle of inclination and gap between successive petticoats, total Creepage distance etc., NOTE: All above drawings should bear a minimum space (14x10cm) for stamping the approval of drawings by HVPNL. 7.2 -5- ANNEXURE - I (Surge Arrestors) Sl. No. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. TECHNICAL REQUIREMENTS FOR METAL OXIDE (GAPLESS) SURGE ARRESTORS System voltage wise requirement of parameters(kV) Particulars 220 132 66 33 11 Rated Arrestor Voltage 198 120 60 30 9 M.C.O.V. (kV rms) 168 104 49 25 7 Installation ----------------------- Outdoor ----------------------Class -------------------- Station Class ------------------Type of construction for 10 kA --------- Single Column, Single Phase---------rated Arrestor. Nominal discharge current 10KA 10KA 10KA 10KA 10KA corresponding to 8/20 microsec wave shape (kA rms) Min. discharge capability. 5 KJ/kV (Referred to rated arrester voltage corresponding to Min. discharge characteristics) Type of mounting ----------------------- Pedestal ---------------------Connection P/E P/E P/E P/E P/E (Between phase to earth P/E) (Between phase to phase P/P) Long duration discharge class 3 3 3 2 1 Max. Switching Surge kV(P) 455 280 140 70 21 Protective level voltage at 1000 Amp. Max. residual voltage kV(P) for 550 340 170 85 25 nominal discharge current 10 KA with 8/20 micro second wave Max.residual voltage kV(P) steep 600 372 186 93 28 fronted current impulse of 10 KA. Minimum pros-symmetrical fault 40 31.5 31.5 26.3 18.4 current for pressure relief test (kA rms) a) Terminal Connector suitable for ---------------Single Tarantula--------------------AAC conductor size b) Take off Vertical Vertical Vertical Vertical Vertical Voltage (kV rms) (corona Rated voltage of the Arrestor extinction) Maximum radio Interference ------------------------ 500 -------------------------voltage (Microvolt) when energized at MCOV Whether insulating base and Yes Yes Yes Yes Yes discharge counter with milli-ammeter are required. Minimum creepage distance of 6125 3625 1813 900 300 Arrestor housing (mm) -6- SECTION-4 CHAPTER-3 TECHNICAL SPECIFICATION FOR 11 kV SWITCHGEAR PANELS VACUUM TYPE 1250 AMP RATING 1.0 SCOPE: This specification covers the design, manufacture, assembly, testing at manufacturer's works before despatch, supply and delivery F.O.R. destination as per schedule of requirement (Annexure 'B') of Vacuum Type, 15 Panel 11 kV Switch boards including 11kV bus coupler having normal current rating of 1250 Amps. with rupturing capacity of 500 MVA. 2.0 STANDARDS: The switchgear panels shall comply in all respects the requirement laid down in the latest editions of IS: 13118-1991, IS: 3427 & IS: 3231. 3.0 CLIMATIC CONDITIONS: 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 The equipment is required to operate satisfactorily under the following site conditions: Max. temperature 500C Min. Temperature -2.50C Max. relative humidity 100% Min. relative humidity 26% Average number of rainy days per Nearly 120 days/annum. Average annual rainfall 900mm Average number of dust storm days 35 per annum. Isoceraunic level 45 Max. wind pressure 195 kg/Sq.mt. Altitude above mean sea level Less than 1000 mts. 3.11 Auxiliary Power Supply:Auxiliary electrical equipment shall be suitable for operation on the following supply system:- a) Power devices (like drive motors) b) DC alarm, control and protective devices i) c) Lighting 415 V, 3 phase 4 wire 50Hz, neutral grounded AC supply 220V DC, underground 2 wire for 220 KV 132 KV & 66 KV Sub-Station. 245 V, single phase, 50 Hz AC Supply. Each of the foregoing supplies shall be made available by the purchaser at the terminal point for each circuit breaker for operation of accessories and auxiliary equipment. Bidders scope include supply of interconnecting cables terminal boxes etc. The above supply voltage may vary as below and all devices shall be suitable for continuous operation over the entire range of voltages. i) AC Supply ii) DC Supply voltage + 10% & -15 %, frequency ± 5% ± 10% 1 4.0 TYPE & RATING: The panels 11 kV switchgear panels shall comprise of 11 kV Vacuum Type circuit breakers, instrument panels and instrument transformers etc. suitable for indoor use. The equipment shall be totally enclosed in a metal clad cubicle, dust and vermin proof with necessary isolation arrangement. Each panel shall be easily extensible on either side and should be complete with necessary internal copper connections, small wiring, L.T. fuses and supporting frame work with bolts to secure it to the floor. The Circuit Breakers shall be draw out type in horizontal position. Principal parameters 4.1 4.2 The breakers shall have the following ratings: Type Vacuum No of poles 3 4.3 Nominal system voltage 11 kV 4.4 Highest system voltage 12 kV 4.5 Rated frequency 50 +/- 1.5 Hz 4.6 Rated continuous current rating at an ambient temp. as specified in IS : 13118-1991 (Latest edition) 4.7 Symmetrical breaking capacity 500 MVA 4.8 Impulse withstand test voltage 75 kV (Peak) 4.9 One minute power frequency withstand test voltage 28 kV (rms) 4.10 Short time current rating Not less than 26.2 kA current corresponding to 500 MVA for 1 sec. 4.11 System neutral Solidly earthed. 5.0 GENERAL DESIGN OF SWITCHGEAR PANELS : 5.1 OPERATING MECHANISM: The vacuum type circuit breaker shall be draw out type & trip free. The VCBs shall be suitable for operation from 220 V DC auxiliary supply. The operating mechanism shall be motor operated spring charged type. There shall be provision(s) for manual charging of closing spring and emergency hand trip. The motor used for the purpose will be suitable for 240 V AC as well as for 220 V DC. 1250 Amp for incoming & bus coupler and 400 Amp for outgoing feeders. 2 The operating mechanism shall work satisfactorily at 85 % - 110 % of rated supply voltage. The VCB shall have 2 normally open & 2 normally-closed auxiliary contacts over & above the ones required for various control & supervision circuits. 5.2 INSTRUMENT PANELS : Each unit shall have its own instrument panel provided at the top & complete with small wiring connections from relays, instrument transformers, metering instruments, indicating instruments, selector switches & circuit breaker control switch. All wiring shall be carried out by using stranded single annealed copper conductor insulated with poly vinyl chloride insulation suitable for 650 V service and in accordance with IS:732-1963. CT/PT circuit shall use wire of not less than 4.0 mm2 cross-sectional area whereas control/alarm/supervision circuit shall use wire of not less than 2.5 mm2 cross-sectional area. All wires will be continuous from one terminal to the other and, also will have no Tee-junction enroute. The connections shall be securely made with the help of connecting lugs duly crimped on to the copper conductor. The meters and relays shall be mounted in a convenient position so as to be readily accessible for inspection or repair. The terminal board provided in the instrument panel of VCBs will be made of moulded dielectric having brass studs, washers, holding nuts & locking nuts. All holding nuts shall be secured by locking nuts. The connection studs shall project 6 mm from the lock nut surface. NO OTHER TYPE OF TERMINAL BOARD IS ACCEPTABLE. The panels shall have a degree of protection of IP-4x. The leads from metering CTs shall be directly terminated at TTB & there from at the KWH meter/SEM with a provision to seal TTB and KWH meter/SEM. The said CT leads will be concealed to prevent their tempering enroute. Similarly PT leads from secondary box of the PT to TTB & there from to energy meter including inter panel PT leads will also be concealed to prevent their tempering. The mode & extent of concealing the metering leads of CTs & PTs to prevent their tempering (by unscrupulous operating personnel) will be discussed & mutually agreed upon with the successful bidder(s). TTB used on the instrument panel should be suitable for front connections. Earthing of current free metallic parts or metallic bodies of the relays/switches mounted on the instrument panel and metal enclosed switchgear shall be done by a suitably sized copper conductor. Earth bus made of 25x3 mm bare copper flat will be extended through entire length of 11 kV switch-board with suitable provision to connect it to the sub-station earth at the extremities. The earthing arrangement will meet with the requirements laid down in IS : 3427 read with its latest amendment. 5.3 VACUUM INTERRUPTER: The Vacuum interrupter of 12 kV minimum 26.2 kA short time current rating, 2000 Amp. normal current rating capable of withstanding minimum 100 full short circuit operations as per test duty 1 to 5 of IEC-56. Vacuum Interrupters for incomers & bus coupler as well as outgoing shall be of same type. These vacuum interrupters shall be of approved make only. 5.4 INSTRUMENT TRANSFORMER: The secondary voltage & current rating of the instrument transformers shall match with the metering or protective equipment. The CTs shall have ratio & accuracy class as mentioned in the schedule of requirement. The CTs shall be wound/ring type in accordance with their ratings. The terminal boards associated with differential CTs, REF CTs & over current/earth fault protection CTs will be of disconnecting type having short circuiting facility &thus facilitate secondary testing of 3 concerned protective relay without disturbing the associated small wiring. Interchangeability of housing of CTs from one panel to another must be ensured. A resin cast potential transformers shall be provided on the Incoming side of each panel set & shall be star/star connected as per attached Schedule of Requirement “Annexure-‘A’. The neutral point of star connected secondary windings of instrument transformers shall be earthed to the main earth bus referred to in the concluding paragraph of clause 5.2. Multiple earthing of any instrument transformers shall be avoided. 5.5 BUS - BARS: All the panels shall be provided with one set of 3 phase 1250 Amps. heat shrunk PVC Sleeves insulated Main electrolytic copper bus bars for all switchboards and shall be connected in a separate moisture and vermin proof sheet metal chamber. The bus-bars connections & insulator supports shall be mechanically strung & rigidly supported so as to withstand the stresses generated by vibrations, variations in temperature and due to severe short circuits. The bus bars shall be Heat shrunk PVC Sleeves insulated type and supported on insulators at short intervals keeping adequate clearance as per IE rules between bus bars and earth. The bus bar chamber shall be provided with inspection covers with gaskets & bus bar shutters. Provision shall be made for future extension of bus bar & switch board. 5.6 LIMIT OF TEMPERATURE RISE: The temperature rise of the current carrying parts shall not exceed the permissible limits above the ambient temperature as per relevant standards (latest edition). However, the reference maximum ambient temperature may be taken as 500C. 5.7 BUSHING INSULATORS: These shall comply with the latest issue of IS : 2099 in all respects. 5.8 DISCONNECTORS OF CIRCUIT BREAKER & THEIR INTERLOCKS: All disconnectors (isolators) of the 11 kV VCBs & interlocks between different pieces of apparatus provided for reasons of safety & for convenience of operation of switchgear shall meet with the requirement of IS:3427-1969 read with its latest amendment. Efficient mechanical interlocking shall be provided to meet the following conditions i) It shall be possible to insert/withdraw the breaker only after circuit breaker has been opened. ii) It shall be possible to insert/withdraw the breaker only when it is fully open position as well as it is in Isolated/test position. iii) It shall not be possible to remove the breaker until the moveable plug unit having secondary connections has been withdrawn. iv) It shall not be possible to replace in position moveable plug unit unless the circuit breaker has been racked in. v) Provision of shutters or locks shall be made to prevent access to bus bar chambers and receptacles when the circuit breaker is withdrawn. vi) Provision shall be made for locking the circuit breaker closing mechanism in open position. 4 vii) 5.9 Provision shall be made for locking the circuit breaker closing mechanism of bus coupler when it is charged from one side only i.e. either from bus side or outgoing side. CABLE BOXES: Each 11 kV incoming VCB & 11kV bus coupler shall be provided with cable boxes suitable for receiving 2 sets of cable each comprising 3 nos 630 mm2, 11 kV single core XLPE, outer PVC sheathed cables. Accordingly, joining kits and sealing material shall be provided for 2 sets of cables. The 11kV Capacitor controlling VCB (panel with CT ratio 800-400/5A) shall be provided with 2 sets of cable boxes suitable to receive 2x3 core 11kV XLPE PVC sheathed cable of size upto 400mm2. The 11 kV station transformer VCB shall be provided with cable boxes suitable to receive 3 core, 11 kV, XLPE cables of size upto 50 mm2 (panel with CT ratio 60-30/5 A). Each cable box shall have vertical entry from below. These cable boxes shall be complete in all respects including cable glands of requisite size. The cable boxes should only be either heat shrinkable or push on type. The cable boxes for outgoing panels are not in the scope of this specification. 5.9 A EARTHING TRUCK: One no. earthing trolley should be provided for each incomer panel. Earthing trolley must be full fault make type device which is capable of making fault at 65.5 KA(peak) and carry 26.2 KA for one second. The earthing truck for incoming panel must be so designed that it is impossible to earth a live circuit. 5.10 SUPERVISION SCHEME : 5.10.1 Instrument panels on each of the 11 kV VCB covered by this specification shall be provided with the following indicating lamps/relay:Circuit breaker `open' Green Circuit breaker `close' Red Auto trip White Circuit breaker spring charged Blue For monitoring of trip circuit both in pre-close and post- close position of the circuit breaker, 1 no. automatic trip circuit supervision relay will be provided on each of the 11 kV (incoming) instrument panel. In case of trip circuit becoming faulty, the operation of this relay shall be accompanied by visual and audio annunciation in accordance with clause 5.10.1 of the specification. However, the trip circuit of each of the 11 kV outgoing/bus coupler/capacitor/Stn. VCB will be monitored `on demand' with the help of an indicating lamp & a push button both when the VCB is `open & closed'. The lamp will be `amber' coloured. Circuit breaker `close' & `open' lamps will be wired so as to be on 240 V AC under `normal' condition. These lamps will be switched over to 220 V DC automatically in the event of failure of 240 V AC supply. Each of 11 kV (incoming) instrument panel will be equipped with a suitable relay for the purpose. 5.11 ALARM SCHEME : 5.11.1 NON TRIP ALARM SCHEME: Each of 11 kV (incoming) panel will be provided with a non-trip alarm scheme comprising suitable auxiliary relay (rated for 220 V DC), accept push button, reset push button & a buzzer. It will cater to non-trip condition such as trip circuit faulty & 5 PT secondary fuses blow `off'. The non-trip alarm scheme will meet with the following requirements: i) The closing of an initiating contact shall actuate a buzzer and will be accompanied by a flag indication on the concerned auxiliary relay. ii) The closing of an initiating contact shall glow a lamp which will not reset until the fault has cleared. iii) It shall be possible to silence the buzzer by pressing `accept' push button. If after cancelling the alarm but before resetting the visual signal, the same fault persists the buzzer shall be suppressed. iv) If after canceling the alarm but before resetting visual signal some other fault takes place, the alarm accompanied by flag indication on appropriate auxiliary relay shall take place. v) If after canceling the alarm and after resetting the visual signal, the same fault appears or some other fault take place, the alarm, flag indication and non-trip lamp indication shall reappear as usual. vi) The non-trip alarm acceptance shall be by means of a push button and resetting of visual signal may also preferably be done through a push button. vii) Means shall be provided for test checking the lamp and alarm circuit at frequent intervals. viii) The equipment shall be suitable for 220 Volts DC operation. 5.11.2. TRIP ALARM SCHEME: Trip commands due to operation of protective relay on any of 11 kV VCB constituting the switchboard will trip the concerned VCB. Its auxiliary contact will actuate a bell (provided in each of the 11 kV incoming VCB) & will be cancelled by the associated circuit breaker control handle. Auto trip lamp will glow on the concerned 11 kV VCB & there will be flag indication on the concerned protective relay. 5.12 PT FUSE FAIL ALARM SCHEME: Each of the 11 kV (incoming) instrument panel is to be provided with a relay to monitor the fuses on the secondary side of 11 kV metering PT. The failure of any of secondary fuse on the 11 kV PT will be accompanied by visual & audio indication in accordance with clause 5.10.1 of the specification. None of the 11 kV outgoing/capacitor/Stn. VCB will be provided with fuses & inter-circuit PT leads may run from one bus wire board to the other. METERING SCHEME: Each of the 11 kV VCB will be provided with a suitably sealed ammeter (additional dials, if any, required to cover all the taps of the CTs shall be included at the time of bidding) with a selector switch facilitating measurement of phase currents as well as unbalance current. The coil of ammeter shall be rated for 5 Amp. The instrument shall be of moving iron spring controlled type of industrial grade `A' classification having accuracy class 1.0 & shall conform to IS:1248(1968). 5.13. 5.13.1 6 5.13.2 Each of the 11 kV (incoming) VCB will be provided with a suitably sealed voltmeter with a selector switch. The selector switch shall facilitate the measurement of phase to phase & phase to neutral voltage of all the three phases one by one. The coil of the voltmeter shall be rated for 110 V (phase to phase). The instrument shall be of moving iron spring controlled type of industrial grade `A' classification with accuracy class 1.0 & shall conform to IS:1248(1968). 5.13.3 Each of the 11 kV VCB except the 11 kV capacitor VCB & Incomer VCBs will be equipped with a three-phase four-wire Electronic KWH meter as per Annexure-‘D’. 11kV incomer VCB will be equipped with SEM as per Annexure-‘C’. 5.13.4 Each of the 11 kV (incoming) VCB will be provided with a power factor meter. The PF meter having a range of 0.5Lag - one - 0.5lead shall be of 2 element type suitable for use on three phase three wire unbalanced system. It shall be rated for 5 A CT secondary & 110 V (phase to phase) available from 11 kV PT mounted on each of the 11 kV incoming VCB. The instrument shall be iron-cored dynamometer type having accuracy class 1.0. N.B. Routine test certificates of all the indicating & integrating instruments will be submitted alongwith the routine test certificates of 11 kV switchgear. 5.14 CONTROL SCHEME : 5.14.1 The instrument panel of each of the 11 kV VCB will be equipped with a circuit breaker control handle of pistol grip type with spring return to neutral position and having bell alarm cancellation contacts. The control handle shall be so designed that after being operated to `close' a VCB the operation can not be repeated until the control handle has been turned to `trip' position making it impossible to perform two closing operation consecutively. 5.14 .2 The rating of the control handle shall be suitable for the duty imposed by the closing and opening mechanism of VCB. The moving and fixed contacts shall be of such a shape & material to ensure good contact and long life under service operating duty. All contacts shall be readily renewable. 5.14.3 The number of contacts in the control handle will be decided by the bidder keeping in view the requirements of this specification. Two pairs of contacts shall be kept spare. The total number of contacts proposed to be provided shall be stated in the bid. 5.14.4 Safety against inadvertent operation due to light touch on the control handle shall be ensured. 5.15 PROTECTION SCHEME: 5.15.1 FOR INCOMING PANELS: The back up protection shall be in the form of a combined over current and earth fault relay(two over current and one earth fault). The relay shall be housed in draw out flush mounting case. 7 This shall be triple pole having Inverse Definite Minimum Time (IDMT) characteristics with a 3/10 time current curve i.e. the relay operating time shall be 3 second at 10 times the plug setting at TMS 1. The outer element of the relay shall be arranged for over current protection and shall have a setting range of 50-200 % of 5 A (The relay for station transformer shall have a setting range of 20-80 % of 5 A) and adjustable in suitable equal steps by means of a plug board. The central element shall be used for earth fault protection with a setting range of 20-80 % of 5 A adjustable in suitable equal steps by means of a plug board (for station transformer panels, the setting range shall be 10-40% of 5 A ) Each of the three elements shall be fitted with shunt reinforcing unit with hand reset operation indicator. 5.15.2 FOR OUTGOING FEEDERS & BUS COUPLER PANELS: Each outgoing feeder panel shall be provided with a triple pole IDMTL type combined over current and earth fault relay (two over current and one earth fault element) conforming to the technical specification stated in the clause : 5.14.1 above and one set of triple pole instantaneous relay (high set element) in the form of two over current and one earth fault element. The outer element of the relay shall be arranged for over current protection and shall have a setting range of 500-2000 % of 5 A (The relay for station transformer shall have a setting range of 200-800 % of 5 A) and adjustable in suitable steps. The central element shall be used for earth fault protection with a setting range of 200-800 % of 5 A (The relay for station transformer shall have setting range of 100-400 % of 5 A) adjustable in suitable steps. The relay shall have low transient over reach with a high pick-up/ drop of ratio. The relay will be connected in series with the triple pole combined over-current and earth fault relay referred to above and shall be so wired so as to take this (instantaneous) out, if so desired by the purchaser at any time during operation of the equipment. 5.15.3 FOR CAPACITOR PANEL: Each capacitor panel shall be provided with the following relays for protection of capacitor banks:i) ii) Triple pole non-directional IDMTL type combined over current & earth fault relay (two over current & one earth fault element) conforming to the technical specification stated in clause 5.14.1 above. 1 no. inverse time over voltage relay with setting range 100 % to 130 % of 110 V available from 11 kV PT mounted in the 11 kV (incoming) VCB along with auxiliary transformers(for external mounting) of ratio 110/103.5 to 116.5 V (in steps of one volt) to be used for compensating the error of over voltage relay. iii) 1 no. inverse time under voltage relay with setting range of 50 % to 90 % of 110 V (phase to phase connections). iv) 1 no. neutral displacement rely with settings 5.4, 7.5, 12.5 & 20 volts and to be fed from open delta winding of three phase (11000//3/(110//3) Volts. Residual voltage transformer (Residual voltage transformer is not a part of this 8 specification). The bidders offering relays with different settings than above shall technically justify their offer. v) 5.15.4 a) b) N.B. 5.16 6.0 6.1 10 minute timer to ensure that the capacitor bank is fully discharged once it has been switched "OFF" before it can be switched "ON" again. COMMUNICATION COMPATIBILTY OF RELAYS All relays shall conform to the requirements of IS:3231/IEC-60255/IEC 61000 or other applicable standards. Relays shall be suitable for flush or semi-flush mounting on the front with connections from the rear. All protective relays shall be in draw out or plug-in type modular cases with proper testing facilities. Necessary test plugs/test handles shall be supplied loose and shall be included in contractor’s scope of supply. All main protective relays (viz over current and earth fault, Restricted Earth Fault, Over voltage and neutral displacement) shall be numerical type and communication protocol shall be as per IEC 61850. Further, the test levels of EMI as indicated in IEC 61850 shall be applicable to these. For numerical relays, the scope shall include the following: Necessary software and hardware to up/down load the data to/from the relay from/to personal computer installed in the substation. However, the supply of PC is not covered under this clause. The relay shall have suitable communication facility for future connectivity to SCADA. The relay shall be capable of supporting IEC 61850 protocol (with optical port). The relay shall be suitable for 220 V DC auxiliary supply. The relay cover & case shall be dust proof, water proof & vermin proof. Operating indicators shall be provided on all protective relays/ on their immediate auxiliary units to indicate the type of fault & phase/phases involved. It shall be possible to reset the operation indication without opening the relay case. The routine test certificates of all protective & auxiliary relays will be submitted along with routine test certificates of 11 kV switchgear covered by the specification. D.C. FAIL ALARM SCHEME: A suitable relay for monitoring the DC supply to the 11 kV switchboard shall be mounted on each of the 11 kV incoming instrument panel. The operation of DC fail scheme shall be accompanied by visual (indicating lamp on the instrument panel) & audio (ringing of hooter) annunciation. It shall be possible to silence the hooter by pressing the `accept' push button while the lamp shall continue to glow till the fault has been attended to & DC supply restored. A DC fail `Test' push button may be provided to test the lamp circuit of the scheme. TEST All routine tests shall be carried out in accordance with IS : 13118-1991 (latest edition thereof). TYPE TESTS The equipment offered should be type tested. Type test report should not be more than seven years old, reckoned from the date of bid opening, in respect of the following tests, carried out in accordance with ISS-13118/IEC-56, from Govt./ Govt. approved test house, shall be submitted along with bid: i) Impulse with-stand voltage tests. ii) Power frequency voltage dry & wet tests on main circuits. iii) Short circuit with stand capability tests. iv) Mechanical endurance tests. v) Temperature rise test 9 However Mechanical endurance tests and Temperature rise test conducted at Firm’s works in the presence of representative of any of the SEBs/State Power Utilities shall also be acceptable. The remaining type test report as per clause 6.0 of ISS-13118/IEC-56 shall be submitted by the successful bidder with in three month from the date of placement of Purchase Order. These type test reports will also be from Govt./ Govt. approved test house & shall not be more than seven years old reckoned from the date of placement of order. Voltage transformers & current transformers shall comply with the type tests as stipulated in the latest version of IS : 3156 & IS: 2705 respectively. The reports of all type tests conducted shall be supplied. The 11 kV VCB & associated CTs & PTs shall be subjected to routine tests as specified in the latest version of the relevant ISS in the presence of purchaser's representative, if so desired by the purchaser. The routine test certificates of bought out components such as relays, switches, indicating instruments, KWH Meter & SEM will also be presented to HVPNL's inspecting officer who will forward them to the purchaser alongwith his inspection report for the main equipment. All test reports should be got approved from the purchaser before despatch of equipment. 7.0 DRAWINGS: In addition to any other drawing which the tenderer may like to furnish to explain the merits of his proposal, following drawings shall be submitted with the tender in quadruplicate : i Principal dimensional details of 11 kV Switchgear. ii General arrangement of 15 Panel 11kV switchboard including its foundation details. iii Schematic drawings of control, metering & protection circuits in respect of 11kV incoming VCB, 11kV bus coupler, 11kV outgoing VCB including station transformer VCB & 11 kV capacitor VCB along with detailed write-up. iv Drawing showing height of 11 kV bus bars & arrangement of bus bars v Vacuum interrupter drawing. The successful bidder shall submit final version of drawings complete in all respects in quadruplicate within 15 days of placement of order for purchaser's approval. The purchaser shall communicate his comments/ approval on the drawings to the supplier within one month of their receipt. The manufacturer shall, if so required by the purchaser, modify the drawings and resubmit the same for purchaser's approval within two weeks of receipt of comments. Such duly revised drawings will be approved by the purchaser within two weeks of their receipt. After receipt of purchaser's approval to drawings, the manufacturer will submit five sets of all approved drawings and five sets of manual of instructions to our Design Office. One set of all the approved drawings and manual of instructions will be supplied along with each equipment without which the supply will not be considered as complete supply. 10 In order to ensure timely receipt of all the drawings, literature & reproducibles etc., the purchase section of MM organization will issue despatch instruction for despatch of 11 kV switchgear. 8.0 SPECIAL TOOLS: The tenderer shall separately quote for a set of special tools, if so required, for erection and maintenance of the switchgear panels. 9.0 DEVIATION FROM SPECIFICATION: Should the tenderer wish to deviate from the provisions of the specification either on account of manufacturing practice, or any other reasons, he shall draw attention to the proposed point of deviation in the tender and submit such full information drawing and specification so that merits of his proposal may be fully understood. The specification shall be held binding unless the deviation have been fully recorded as required above. 10.0 TRAINING FACILITIES: VOID 11.0 GUARANTEED AND OTHER TECHNICAL PARTICULARS: These particulars shall be furnished strictly as per Annexure-A. Any deviation from this specification shall be clearly brought out separately. 11 ANNEXURE -'A' SCHEDULE OF REQUIREMENT VACUUM TYPE 15 PANELS, 11 kV SWITCH BOARDS AND EACH SWITCH BOARD COMPRISING OF THE FOLLOWING:1.01. 1 NO. INCOMING PANEL EQUIPPED AS BELOW: -1 No. Triple pole 500 MVA, 11 kV 1250 A draw out type vacuum circuit breaker fitted with arc control device, interlocks, auxiliary switches isolating contacts, emergency hand trip device, mechanical `ON' & `Off' indicator and motor operated spring charged mechanism. -1 Set Bus bars 3 phase 1250 A. Cable boxes located at the rear of the unit for receiving 2 set of power cables each comprising 3 no. single core 630 mm2 11 kV XLPE PVC sheathed cables & complete in all respect with jointing kits etc. as per clause 5.9 of the specification. -3 No. CTs of ratio 1800-900/0.577-5 A with first core for differential protection having a minimum knee point voltage equal to 40 RCT (neglecting lead resistance) and the 2nd core for REF protection having a minimum knee point voltage of 92(RCT)V on 1800 A tap where RCT secondary winding resistance. These CTs shall conform to accuracy class PS of ISS:2705 (Part-IV) and shall have Magnetising current as low as possible but in no case exceeding the value corresponding to class 5 P of IS:2705 (Part-III). -3 No. CTs of 1800-900/5 A of 15 VA output and 5P10 accuracy for over current and earth fault protection & Ampere meter etc. -3 No. CTs of 1800-900/1 A of 15 VA output, accuracy class 0.2S and ISF less than 5 for SEM.CT secondary terminals shall be brought out in weather proof sealable terminal box & shall be connected to SEM through TTB. Both TTBs and SEM shall be sealable type. -1 No. 3 phase star/star connected resin cast voltage transformer as per IS: 3156 (Part-II)1965 complete with HT & LT fuses, isolating plugs and sockets for HT & LT copper connectors, current limiting resistances as per following specifications:Sr.No. Core Ratio VA Burden Accuracy 1. Core-I 11000/√3/110/√3 100VA 1/3p 2. Core-II 11000/√3/110/√3 10VA 0.2 CT Secondary terminal of metering core i.e. Core-II shall be brought out in whether proof terminal box and shall be connected to SEM through TTB. Both TTBs and SEM shall be sealable type. -1 set Vermin and dust proof fitments. -1 NO. INSTRUMENT PANEL MOUNTED ON TOP AND EQUIPPED AS BELOW: -1 No. Ammeter with selector switch as per clause: 5.13.1 of the specification. -1 No. Voltmeter with selector switch as per clause: 5.13.2 of the specification. -1 No. PF meter with TTB as per clause: 5.13.4 of the specification. 12 -1 Set Triple pole combined over current and earth fault IDMTL relay as per clause: 5.15.1 of the specification. -1 Set Over voltage relay for incomer panels only. -1 No. Tripping relay with hand reset contacts suitable for 220 V DC auxiliary supply. -4 No. Indicating lamps with fittings to indicate breaker `open', `close', `auto trip' & spring charged as per clause 5.10 of the specification. -1 No. Automatic trip circuit supervision scheme as per clause 5.10 of the specification. -1 No. PT fuse alarm scheme as per clause 5.12 of the specification. -1 No. DC fail alarm scheme as per clause 5.16 of the specification. -1 No. Circuit breaker control handle as per clause 5.14 of the specification. -1 No. Alarm equipment for non-trip & trip fault annunciation as per clause 5.11.1 & 5.11.2 of the specification. -1 No. Cubicle illumination lamp with door operated ON/OFF switch. -1 No. 15 A power socket with switch. -1 No. Anti-condensation tubular space heater suitable for connection to 240 V AC supply with a thermostat & a miniature circuit breaker. -1 No. Special Energy Meter as per specification attached (Annexure-‘C’). 1.02 8 N0. OUTGOING FEEDER PANELS EACH COMPRISING OF: -1 No. Triple pole 400 A, 500 MVA 11 kV circuit breaker fitted with Arc control devices, interlock arrangement, auxiliary switches, isolating contacts, emergency hand trip device, mechanical ON & OFF indicator & motor operated spring charged mechanism operate at 220 V DC. -1 Set Bus bars 3 phase 1250 A. -1 No. Trifurcating main cable box for receiving 3 core XLPE PVC sheathed cable upto 400 mm2 size & complete in all respects with cable glands and jointing kits etc. as per clause 5.9 of the specification. -3 No. CTs of ratio 300-150/5-5 A with first core of 15 VA output & 5P10 accuracy for O/C & E/F protection & second core 15 VA output & accuracy class 1.0 for metering. -1 No. Anti-condensation tubular space heater for connection to 240V AC supply with a thermostat & a miniature circuit breaker. -1 Set Vermin proof & dust proof fitments. -1 No. Instrument panel mounted on top & equipped as below:13 -1 No. Ammeter with selector switch as per clause: 5.13.1 of specification. -1 No. KWH meter with TTB as per clause: 5.13.3 & 5.2 of the specification. -1 set Triple pole combined 2 O/C & 1 E/F IDMTL relay supplemented with triple pole instantaneous relay (high set element) in the form of 2 O/C & 1 E/F as per clause : 5.14.2 of the specification. -1 No. Tripping relay with hand reset contacts suitable for 220V DC auxiliary supply. -4 No. Indicating lamps with fittings to indicate breaker `open', `close', `auto-trip' & 'spring charged' as per clause 5.10 of the specification. -1 No. Indicating lamp with fittings & push button switch to indicate trip circuit healthy in pre-close & post-close conditions as per clause: 5.10 of the specification. -1 No. Circuit breaker control handle as per clause: 5.14 of the specification. -1 No. Cubicle illumination lamp with door operated ON/OFF switch. -1 No. 15 A power socket with switch. -1 No. Anti-condensation tubular heater suitable for connection to 240 V AC supply with a thermostat & a miniature circuit breaker. 1.03 2 NO. OUTGOING FEEDER PANELS: Similar to item 1.02 but with the following cable box/CTs: - -1 No. Trifurcating main cable box for receiving 3 core XLPE, PVC sheathed cable upto 400 mm2 size and complete with cable glands and jointing kits etc. as per clause: 5.8 of the specification. -3 No. CTs of ratio 400-200/5/5 A with first core of 15 VA output & class 5P10 accuracy for O/C & E/F protection & second core of 15 VA output & accuracy class 1.0 for metering. 1.04 1 NO. PANEL FOR CAPACITOR BANK: The capacitor controlling breaker should be suitable to meet all conditions required for capacitor operation & should be suitable for controlling capacitive current upto 800A at 11 kV which is equivalent to 15 MVAR approx. & equipped similar to item No. 1.02 except KWH meter but with the following changes/additions: -3 No. CTs of ratio 800-400/5A output & 5P10 accuracy for over current & earth fault protection. - Protection scheme including closing circuit interlock timer shall be as per clause: 5.15.3 of the specification. 1.05 1 NO. STATION TRANSFORMER FEEDER PANEL: Similar to item No. 1.02 but with the following cable box & CTs:- 14 -1 No. Trifurcating main cable box for receiving 3 core XLPE cable upto 50 mm2 size & complete in all respect as per clause: 5.8 of the specification. -3 No. CTs of ratio 60-30/5-5 A with first core of 15 VA output & class 5P10 accuracy for O/C & E/F protection & second core of 15 VA output & accuracy class 1.0 for metering. 1.06 1 No. INCOMING PANEL EQUIPPED EXACTLY IDENTICAL TO ITEM 1.01 DETAILED ABOVE NOTE: The panels at Sr. No. 1.01 (incoming panels) shall be placed adjacent to the both sides of the 11kV bus coupler and further all the outgoings panels, capacitor panel & station transformer panel will be adjusted on both sides of the aforesaid incomer panels/site requirement. Provision shall be made to split the 12 panels boards into two parts each having an incoming panel at its end with complete non-trip alarm, trip alarm & protection schemes. 1.07 1 N0. BUS COUPLER OUTGOING FEEDER PANEL EACH COMPRISING OF: -1 No. Triple pole 1250 A, 500 MVA 11 kV circuit breaker fitted with Arc control devices, interlock arrangement, auxiliary switches, isolating contacts, emergency hand trip device, mechanical ON & OFF indicator & motor operated spring charged mechanism operate at 220 V DC. -1 Set Bus bars 3 phase 1250 A. -1 No. Trifurcating main cable box for receiving single core XLPE PVC sheathed cable upto 630 mm2 size & complete in all respects with cable glands and jointing kits etc. as per clause 5.9 of the specification. -3 No. CTs of ratio 1800-900/5 A with first core of 15 VA output & 5P10 accuracy for O/C & E/F protection & second core 15 VA output & accuracy class 1.0 for metering. -1 No. Anti-condensation tubular space heater for connection to 240V AC supply with a thermostat & a miniature circuit breaker. -1 Set Vermin proof & dust proof fitments. -1 No. Instrument panel mounted on top & equipped as below:- -1 No. Ammeter with selector switch as per clause: 5.13.1 of specification. -1 set Triple pole combined 2 O/C & 1 E/F IDMTL relay supplemented with triple pole instantaneous relay (high set element) in the form of 2 O/C & 1 E/F as per clause : 5.14.2 of the specification. -1 No. Tripping relay with hand reset contacts suitable for 220V DC auxiliary supply. -4 No. Indicating lamps with fittings to indicate breaker `open', `close', `auto-trip' & 'spring charged' as per clause 5.10 of the specification. -1 No. Indicating lamp with fittings & push button switch to indicate trip circuit healthy in pre-close & post-close conditions as per clause: 5.10 of the specification. 15 -1 No. Circuit breaker control handle as per clause: 5.14 of the specification. -1 No. Cubicle illumination lamp with door operated ON/OFF switch. -1 No. 15 A power socket with switch. -1 No. Anti-condensation tubular heater suitable for connection to 240 V AC supply with a thermostat & a miniature circuit breaker. 2. 11 kV INCOMING & OUTGOING FEEDER VCBs. 2.1 11 kV incoming VCBs equipped exactly identical to the item 1.01 detailed above. 2.2 11 kV outgoing VCBs equipped identical to either 1.02 or 1.03 detailed above. The precise split up will be intimated to the successful bidder. 2.3 11kV Outgoing bus coupler equipped identical to 1.08 detailed above. NOTE : These incoming & outgoing panels' bus orientation, physical dimension and auxiliary wiring etc. shall be such that these can be connected with the already installed/running 11 kV switchgear. 16 HARYANA VIDYUT PRASARAN NIGAM LTD. TECHNICAL SPECIFICATION FOR 245kV, 145kV, 72.5kV ,36kV &12kV NCTs E:\DATA AFTER - Copy.doc 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-1 NCT spec- November 2014 CT-1 CONTENTS CLAUSE NO. 1.0 2.0 3.0 4.0 5.0 6.0 7.0 TITLE SCOPE STANDARDS SERVICE CONDITIONS PRINCIPAL PARAMETERS GENERAL TECHNICAL REQUIREMENTS TESTS DOCUMENTATION PAGE NO. 3 3 4 4 6 9 10 ANNEXURES I. COREWISE DETAILS FOR A-(i) B-(i) C-(i) C-(ii) D-(i) D-(ii) D-(iii) E-(i) E-(ii) E-(iii) 245kV NCTs (450-300/1A) 145kV NCTs (250-150-100/1A) 72.5kV TRANSFORMER INCOMER NCTs (1500-1000/1A) 72.5kV NCTs (300-200-150/1A) FOR 66/11kV T/Fs 36kV T/F I/C NCTs (1000-600-400/5A) FOR 132/33KV T/F WITH 26.3KA STC 36kV T/F I/C NCTs (2000-1000/5A) FOR 220/33KV T/F ITH 26.3KA STC 36kV T/F NCT (100-50/5A) FOR 4 MVA 33/11KV T/F WITH 26.3KA STC 12kV NCTs (1800-900/5A) FOR 25/31.5 MVA 12kV NCTs (1200-900/5A) FOR 12.5/16 MVA & 16/20 MVA 12kV NCTs (300-150/5A) FOR 4 MVA 33/11KV T/F 12 12 13 13 14 14 14 15 15 15 II. GUARANTEED TECHNICAL PARTICULARS 16 E:\DATA AFTER - Copy.doc 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-1 NCT spec- November 2014 CT-2 E:\DATA AFTER - Copy.doc 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-1 NCT spec- November 2014 CT-3 1.0 SCOPE 1.1 This specification provides for design, engineering, manufacture, testing of out-door instrument transformers alongwith terminal connectors for protection and metering services in different 400/220/132/66kV S/Stns. in the state of Haryana. 1.2 It is not the intent to specify herein complete / all details of the design and construction of equipment. However the equipment shall conform in all respects to high standards of engineering design and workmanship and shall be acceptable to the purchaser, who will interpret the meanings of drawings and specifications and shall have the power to reject any work or material, which in his judgement is not in accordance therewith. The equipment offered shall be complete with all components necessary for its effective and trouble free operation. Such components shall deemed to be within the scope of supply irrespective of whether those are specifically brought out in this specification and or the commercial order or not. 2.0 STANDARDS Unless otherwise specified elsewhere in this specification the rating as well as performance and testing of the instrument transformers shall conform but not limited to the latest revisions and amendments available at the time of placement of order of all the relevant standards as listed hereunder. 2.1 INSTRUMENT TRANSFORMERS : Sr. No. 1. 2. 3. 4. 5. 6. 7. Standard No. IS:2165 IS:2705 (I to IV) IS:2099 IS:3347 IS:2071 IS:335 IS:2147 8. 9. 10. 11. 12. IS:2633 IS:4800 IS:5561 IS:11065 IEC 44-1 13. IEC-270 (or IS:11322) IEC-44(4) IEC-171 IEC-60 IEC-8263 14. 15. 16. 17. 18. 19. E:\DATA AFTER - Copy.doc IS:5621 Title Insulation Co-ordination for equipment of 100kV and above. Current Transformers. Bushings for alternating voltages above 1000Volts. Dimensions of porcelain transformer bushings. Method of High Voltage Testing. Insulating oil for transformers Switchgears. Degree of protection provided by enclosures for low voltage switchgear and control. Method of testing hot dipped galvanized articles. Enameled round winding wires. Terminal connectors. Drawings. Current Transformers. Partial Discharge Measurement Instrument Transformer measurement of PDs. Insulation co-ordination. High voltage testing techniques. Method for RIV test on high voltage insulators. Indian Electricity Rules 1956. Hollow porcelain insulators. 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-1 NCT spec- November 2014 CT-4 2.2 Equipment meeting with the requirements of other authoritative standards, which ensure equal or better performance than the standards mentioned above, shall also be considered. When the equipment offered by the supplier conforms to other standards salient points of difference between standards adopted and the standards specified in this specification shall be clearly brought out in the relevant schedule. Four copies of such standards with authentic translation in English shall be furnished alongwith the offer. 3.0 3.1 SERVICE CONDITIONS: Equipment to be supplied against this specification shall be suitable for satisfactory continuous operation under the following tropical conditions:1. 2. 3. 4. 5. 6. 7. 8. Location IN THE STATE OF HARYANA Max. ambient air temp(OC) 50 Min. ambient air temp (0C) -2.5 Maximum Relative humidity (%) 100 Minimum Relative humidity (%) 26 Average annual rainfall (mm) 900 Max. wind pressure (Kg/sq.m.) 195 Max. altitude above mean sea level 1000 (meters) 9. Isoceraunic level (days/year) 50 10. Seismic level (horizontal 0.3g acceleration) Note : Moderately hot and humid tropical climate conducive to rust and fungus growth. The climatic conditions are also prone to wide variations in ambient conditions. Smoke is also present in the atmosphere. Heavy lightening also occurs during June to October. 4.0 PRINCIPAL PARAMETERS: The current transformers covered in this specification shall meet the technical requirements listed hereunder. PRINCIPAL TECHNICAL PARAMETERS: Sr. No. Item 420kV 1. Type of installation. 2. 3. Type of Mounting Suitable for system Frequency Highest system Voltage (KV rms) Minimum Neutral CT Insulating Voltage Current Ratio A/A Line CT 4. 5. 6. a. E:\DATA AFTER - Copy.doc C.T./ 245kV 145kV 72.5kV 36kV 12kV Single phase, dead/live tank, oil filled, Hermetically sealed, outdoor type. Steel Structures 50 Hz 420 245 145 72.5 36 12 - 33 15 15 15 8.66 2000-1000500/1-1-1-1-1 1200-800-400/ 1-1-1-1-1, 2000-1000/1-11-1-1 600-300-150/ 1-1-1 600-300-150/ 1-1-1 400-300/5-1 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-1 NCT spec- November 2014 CT-5 - b. Transformer CT 2000-1000500/1-1-1-1-1 450-300/0.5771-1-1-1 250-150-100/ 0.577-1-1-1 300-200150/0.577-1-1 Sr. No. Item 400kV 245kV 145kV c. Transformer Incomer CT - 900-600-300/11-1-1-1 750500/ 0.577-1-1-1 d. e. Capacitor CT NCT - f. Bus Coupler/Tie CT 7. Method of Earthing the Solidly Earthed System Rated Continuous 125% for all taps Thermal current Ratio taps The tapings shall be only on secondary winding. Acceptable limit of As per IS:2705 or equivalent IEC temperature rise above the specified ambient temperature for continuous operation at rated current. Acceptance partial As per IS:11322-1985 or equivalent IEC discharge level at 1.1 times the rated voltage. 1.2/50 microsecond lightning impulse withstand voltage (kVp) 1425 1050 650 325 170 CTs 170 95 95 95 NCTs 1 minute dry & wet power frequency withstand Voltage primary (kV rms) 630 460 275 140 70 CTs 70 38 38 38 NCTs 3 Power frequency over voltage withstand requirement for secondary winding (kV rms) (for 1 minute) Min. creepage distance of porcelain housing (mm) 10500 6125 3625 1815 900 CTs 900 440 440 440 NCTs 40 40 31.5 31.5 Rated short time 26.3 withstand current (kArms) for 1 Second. 100 100 78.75 78.75 65.75 Rated Dynamic withstand current (kAp) 4.0 Maximum Creepage 8. 9. 10. 11. 12. a. b. 13. a. b. 14. 15. a. b. 16. 17. 18. E:\DATA AFTER Copy.doc 2000-1000500/1-1-1-1-1 - 72.5kV 100-50/5-5 1500-1000/ 0.577-1-1-1 - - 450-300/1 250-150-100/1 300-200150/1, 15001000/1 2400-1200/ 1-1-1-1, 1200800-400/1-1-11-1 750-500/1-1A, 600-300-150/ 11-1 1500-1000/11A, 600-300150/ 1-1-1 - 36kV 12kV 2000-1000/ 0.577-5-5-1, 1000-600400/0.577-5-5-1 400-300/5-1A 2000-1000/5, 1000-600-400/5, 100-50/5 - 2000-1000/5 1800900/5, 1200900/5, 300150/5 - 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-1 NCT spec- November 2014 - CT-6 75 28 250 18.4 46 Factor 5.0 5.1 GENERAL TECHNICAL REQUIREMENTS : The insulation of the instrument transformer shall be so designed that the internal insulation shall have higher electrical withstand capability than the external insulation. The designed dielectrics withstand values of external and internal insulation's shall be clearly brought out in the guaranteed technical particulars. The dielectric withstand values specified in this specification are meant for fully assembled instrument transformers. 5.2 PORCELAIN HOUSING: 5.2.1. The details of location and type of joint, if provided on the porcelain, shall be furnished by the Supplier alongwith the offer. The housing shall be made of homogeneous, vitreous porcelain of high mechanical and dielectric strength, glazing of porcelain shall be uniform brown or dark brown colour with a smooth surface arranged to shed away rain water or condensed water particles (fog). 5.2.2 Details of attachment of metallic flanges to the porcelain shall be brought out in the offer. Nuts and bolts or screws used for fixation of the interfacing porcelain bushings for taking out terminals shall be provided on flanges cemented to the bushings and not on the porcelain. 5.3 METAL TANK: The metal tanks shall have bare minimum number of welded joints so as to minimize possible locations of oil leakage. The metal tanks shall be made out of mild steel/stainless steel/aluminum alloy, depending on the requirement. Welding in horizontal plane is to be avoided as welding at this location may give way due to vibrations during transport resulting in oil leakage. Supplier has to obtain specific approval from purchaser for any horizontal welding used in the bottom tank. The castings of base, collar etc, shall be diecast and tested before assembly to detect cracks and voids if any. 5.4 SURFACE FINISH : The ferrous parts exposed to atmosphere shall be hot dip galvanized or shall be coated with atleast two coats of Zinc Rich Epoxy painting. All nuts, Bolts and washers shall be of stainless steel. 5.5 INSULATING OIL: Insulating oil required for first filling of the instrument transformer shall be covered in Supplier's scope of supply. The oil shall meet the requirements of latest edition IS:335 or equivalent IEC. 5.6 5.6.1 PREVENTION OF OIL LEAKAGE & ENTRY OF MOISTURE: The supplier shall ensure that the sealing of instrument transformer is properly achieved. In this connection the arrangement provided by the Supplier at various locations including the following ones shall be described, supported by sectional drawings. i) Locations of emergence of primary and secondary terminals. ii) Interface between porcelain housing and metal tank/s. iii) Cover of the secondary terminal box. 5.7 GASKETS: For gasketed joints, wherever used nitrile butyl rubber gaskets shall be used. The gasket shall be fitted in properly machined groove with adequate space for accommodating the gasket under compression. E:\DATA AFTER Copy.doc 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-1 NCT spec- November 2014 - CT-7 5.8 E:\DATA AFTER OIL LEVEL INDICATORS: Instrument transformers shall be provided with oil sight window (Prismatic Type) at suitable location so that the oil level is clearly visible with naked eye to an observer standing at ground level. 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-1 NCT spec- November 2014 - Copy.doc CT-8 5.9 EARTHING: Metal tank of instrument transformer shall be provided with two separate earthing terminals for bolted connection to 50x8mm MS flat to be provided by the Purchaser for connection to station earth mat. 5.10 LIFITING AND TRANSPORTATION ARRANGEMENTS: Instrument transformer shall be provided with suitable lifting arrangement to lift the entire unit. The lifting arrangement shall be clearly shown in the general arrangement drawing. Lifting arrangement (lifting eye) shall be positioned in such a way as to avoid any damage to the porcelain housing or the tanks during lifting for installation/transport. Necessary string guides, if required shall be offered which shall be removable type. The CT/NCT shall be so constructed that it can be easily transported to site within the allowable transport limitation and in horizontal position, if the transport limitations so demand. 5.11 NAME PLATE: The instrument transformer shall be provided with non-corrosive, legible name plate with the information specified in relevant standards, duly engraved/punched on it. In addition to these the following specific points shall also be marked on the name plate. P.O. No. with date and (item No, if any) Connection diagram. Rated continuous thermal current. General knee point voltage formula. The size of nameplate and its location on the equipment should be such that it is clearly readable with naked eyes while standing on ground. i) ii) iii) iv) 5.12 5.12.1 5.12.2. 1) 2) 3) 4) 5) 6) 7) 8) 5.13 E:\DATA AFTER TERMINAL CONNECTORS: Suitable terminal connectors of type 4” IPS Aluminium tube for 400kV CTs (Rigid type for one side and expansion type for other side) and suitable terminal connectors for connecting twin tarantulla for 220kV T/F I/C CTs, 220kV B/C CT (2400-1200/1-1-1-1A),220kV Line CT (2000-1000/1-1-1-11A), 33kV B/C CTs, 33kV T/F I/C CT (2000-1000/0.577-5-5-1A), 33kV T/F I/C NCT (2000-1000/5A), 132kV B/C CT(750-500/1-1A), 66kV B/C CT(1500-1000/1-1A), 66kV T/F I/C CT, 66kV T/F I/C NCT & single Tarantulla conductor for 220kV T/F, Line/B.C CTs, 220kV NCTs, 132kV T/F I/C CT, 33kV Line cum Capacitor CT (400-300/5-1A) meant for 220/33kV T/F, twin ACSR Zebra for 33kV T/F I/C CT (1000-600-400/0.577-5-5-1A), 33kV T/F I/C NCT (1000-600-400/5A) meant for 40/50MVA 132/33kV T/F & for Single ACSR Zebra for remaining CTs/NCTs shall be supplied. Suitable terminal earth connectors for earthing connections shall also be provided. The terminal connectors shall meet the following requirements: Terminal connectors shall be manufactured and tested as per IS:5561 or equivalent IEC. All castings shall be free from blowholes, surface blisters, cracks and cavities. All sharp edges and corners shall be blurred and rounded off. No part of a clamp shall be less than 10mm thick. All ferrous parts shall be hot dip galvanized conforming to IS:2633 or equivalent IEC. For bimetallic connectors, copper alloy liner of minimum 2mm thickness shall be cast integral with aluminium body. Flexible connectors shall be made from tinned copper/ aluminium sheets. All current carrying parts shall be designed and manufactured to have minimum contact resistance. Connectors shall be designed to be corona free in accordance with the requirements stipulated in IS:5561 or equivalent IEC. INTERNAL INSULATION: Enamel, if used for conductor insulation, shall be polyvinyl acetate type and shall meet the 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-1 NCT spec- November 2014 - Copy.doc CT-9 requirements of IS:4800 or equivalent IEC. Polyester enamel shall not be used. Double cotton cover, if used, shall be suitably covered to ensure that it does not come in contact with oil. 5.14 TEMPERATURE RISE: The temperature rise on any part of equipment shall not exceed maximum temperature rise specified in IS:2705 or equivalent IEC. However, the permissible temperature rise is for a maximum ambient temperature of 50o C. 5.15 PRESSURE RELIEF DEVICE: Suitable arrangement shall be made for compensation of variation in the oil volume due to ambient variation and to take care of internal abnormal pressures. The pressure variation shall be kept within limits, which do not impair the tightness of the instrument transformer. A pressure relief device capable of releasing abnormal internal pressure shall be provided. 5.16 SECONDARY TERMINAL BOXES: The CT secondary terminals except for CTs with metering core having accuracy class 0.2S shall be brought out in a weather proof terminal box. The terminal box shall be provided with removable gland plate. In case of CTs, with metering core having accuracy class 0.2S, CT secondary terminals shall be brought out in two separate weatherproof terminal boxes. In the first box, all the terminals of cores of CTs except metering core having accuracy class 0.2S shall be brought out. The terminal box shall be provided with removable gland plate. 5.17 The terminal of metering core having accuracy class 0.2S CTs, shall be brought out in the second terminal box. This shall also be provided with a removable gland plate. This terminal box shall be provided with proper sealing facility. The terminal box/boxes shall be dust and vermin proof. The dimensions of the terminal box/boxes and its/their openings shall be adequate to enable easy access and working space with use of normal tools. POLARITY : Polarity shall be indelibly marked on each primary and secondary terminal. Facility shall be provided for short-circuiting and grounding of the secondary terminals inside the terminal box. 5.18 OIL FILLING AND DRAIN VALVES: The instrument transformers shall be vacuum filled with oil after processing and thereafter hermetically sealed to eliminate breathing and to prevent air and moisture from entering the tanks. Sealing type oil filling and/or oil sampling cocks shall be provided with facility to reseal the same. The method adopted for hermetic sealing shall be described in the offer. 5.19 INSTRUMENT SECURITY FACTOR: For all type of CTs, the instrument security factor at all ratios shall be less than 5 for metering core. If any, auxiliary CTs / reactor are used in the CTs then all the parameters specified shall have to be met treating auxiliary CTs as integral part of the current transformer. 5.20 PRIMARY WINDING: The design density for short circuit current as well as conductivity of the metal used for primary winding shall meet the requirement of IS:2705 or equivalent IEC. The supplier shall in his offer furnish detailed calculations for selection of winding cross-sections. 5.21 E:\DATA AFTER SECONDARY WINDING: 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-1 NCT spec- November 2014 - Copy.doc CT-10 Suitably insulated wire of electrolytic grade shall be used for secondary windings. Type of insulation used shall be described in the offer. For multi ratio design, suitable tapping shall be provided on secondary winding only. Ratio tap selection through primary side shall not be acceptable. 5.22 CORE: The exciting current of the CT shall be as low as possible. The supplier shall furnish alongwith his offer the magnetization curve/s for all the core/s. The cores shall be of high grade, non-ageing electrical silicon laminated steel of low hysterisis loss and high permeability to ensure high accuracy at both normal and over current. 5.23 PRIMARY TERMINALS: For 400kV CT, 220 kV Line CT (2000-1000/1-1-1-1-1A), 220kV Bus Coupler CT (2400-1200/1-1-11A), 66kV T/F I/C CT (1500-1000/0.577-1-1-1A), 66kV T/F I/C NCT (1500-1000/1A), 66kV B/C CT (1500-1000/1-1A), 33kV T/F I/C CT (2000-1000/0.577-5-5-1A & 1000-600-400/0.577-5-5-1A), 33kV T/F I/C NCT (2000-1000/5A & 1000-600-400/5A) & 33kV Bus Coupler CT the primary terminal shall be made out of rods of not less than 40mm dia. copper or equivalent as per IS/IEC and for remaining CTs/NCTs the primary terminals shall be made out of rods not less than 30mm dia. copper or equivalent as per ISS\IEC. 5.24 DEVIATION FROM SPECIFICATION: Any deviation from the specification shall be clearly brought out separately. In the absence of any specific mention, it shall be implied that the equipment offered is entirely according to this specification. 5.25 TEST TAP: The 72.5 kV and above voltage level, instrument transformers shall be provided with suitable test tap for measurement of tests such as partial discharges etc. in factory as well as at site. Provision shall be made of a screw on cap for solid and secured earthing of the test tap connection, when not in use. A suitable caution plate shall be provided duly fixed on the cover of the secondary terminal box indicating the purpose of the test tap and necessity of its solid earthing as per prescribed method before energizing the equipment. NOTE:- The Overall Tolerance for dimensions, Quantity of Oil, Weight, etc should be +5% max. The General Tolerance should be as per ISS. Tolerance for Mounting Dimension should be +5mm. 6.0 6.1 TESTS: TYPE TESTS The equipment offered should be fully type tested. In case, the equipment of the type and design offered has already been type tested, the supplier shall furnish 4 sets of type test reports alongwith the offer. The type test reports should not be more than seven years old, reckoned from the date of bid opening and the type test should have been carried out in accordance with ISS2705(1992)/equivalent IEC from Govt./ Govt. approved test house. However, temperature rise test although covered under type tests will be got conducted by the supplier on one piece of total ordered quantity of each type, at his premises in the presence of the inspecting officer of the purchaser, without any extra charges. The purchaser reserves the right to demand repetition of some or all the type tests in the presence of purchaser's representative. 6.2 ACCEPTANCE AND ROUTINE TESTS: i) E:\DATA AFTER All acceptance including Tan Delta test and routine tests as stipulated in the relevant standards shall be carried out by the Supplier in presence of purchaser's representative, unless dispensed 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-1 NCT spec- November 2014 - Copy.doc CT-11 ii) with in writing by the Purchaser. Immediately after finalisation of the programme of routine /acceptance testing, the Supplier shall give sufficient advance intimation to the Purchaser to enable him to depute his representative for witnessing the testing. 7.0 DOCUMENTATION: 7.1 All drawings shall conform to international standards organisation (ISO) `A' series of drawing sheet/Indian Standards Specification IS:11065. All drawings shall be in ink and suitable for microfilming. If drawings are computerized than all drawings shall be nicely printed. All dimensions and data shall be in S.I.Units. 7.2 List of drawings: a) b) c) i) ii) iii) iv) v) d) e) f) g) h) General outline and assembly drawings of the equipment. Graphs showing the performance of equipment's in regard to magnetisation characteristics; ratio & phase angle curves, ratio correction factor curves. Sectional views showing: General Constructional Features. Materials/Gaskets/Sealing used. The insulation & the winding arrangements, method of connection of the primary / secondary winding to the primary/ secondary terminals etc. No. of Turns, Cross-Sectional Area, Current density of Primary and secondary windings. Porcelain used and its dimensions. Arrangement of terminals and details of connection studs provided. Name plate. Schematic drawing. Detailed drawing of pressure release device with detailed literature. Terminal connector drawing. NOTE:- All above drawings should bear a minimum space (14X10cm) for stamping the approval of drawings by the purchaser. 7.3 The bidder shall submit four sets of final versions of complete and correct equipment drawings except 7.2 (b) above (actual of which shall be supplied at the time of inspection) for purchaser’s approval alongwith bid in a sealed envelope. The purchaser shall communicate his comments/approval on the drawings to the supplier within 21 days from the date of issue of LOI. The submission of complete and correct readable drawings for approval is the responsibility of the bidder/supplier. The supplier shall, if so required by the purchaser, modify the drawings and resubmit four copies of the modified drawings for purchaser’s approval within two weeks from the date of purchaser’s comments. Then, the purchaser shall approve the revised drawings within two weeks from the date of its receipt. The manufacturing of the equipment shall be strictly in accordance with the approved drawings and no deviation shall be permitted without the written approval of the purchaser. All manufacturing and fabrication work in connection with the equipment prior to the approval of the drawing shall be at the supplier's risk. 7.4 7.5 E:\DATA AFTER The successful bidder shall also supply one set of nicely bound all the approved drawings & instruction manual containing handling, installation, testing and commissioning of equipment at the time of despatch of material to the consignee with each equipment for our field staff without which the supply will not be considered as complete supply. In addition, 5 sets of such bound manuals and final approved drawings shall be supplied for reference & record in our design office 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-1 NCT spec- November 2014 - Copy.doc CT-12 alongwith one good quality soft copy (CD) of approved drawings and instruction manuals, if computerized. 7.6 Approval of drawings / work by Purchaser shall not relieve the Supplier of his responsibility and liability for ensuring correctness and correct interpretation of the latest revision of applicable standards, rules and codes of practices. The equipment shall conform in all respects to high standards of engineering, design, workmanship and latest revisions of relevant standards at the time of ordering and purchaser shall have the power to reject any work or material which in his judgement is not in full accordance therewith. NOTE :- (i) In case the equipment offered by the Supplier does not meet with the requirement of technical specification the offer of the firm shall not be considered. (ii) Supplier shall provide special label on the LIVE Tank CTs and its packing for caution in handling the CTs carefully. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-1 NCT spec- November 2014 - Copy.doc CT-13 ANNEXURE I-A(i) COREWISE DETAILS OF 245kV NEUTRAL CTs (450-300/1A) NUMBER OF CORE - 1 Application Current Accuracy Formula for minimum Ratio (A) class knee-point voltage at CT as per Secondary resistance at IEC 185 750C at 300Atap(Volt) 1 2 REF PROTECTION 3 450-300/1 Maximum Exciting Current (mA) 4 PS Minimum Insulation Voltage (kV) 5 14(RCT+2) 6 30 @ VK/2 33 ANNEXURE I-B(i) COREWISE DETAILS OF 145kV NEUTRAL CT (250-150-100/1A) No. OF CORE= 1 Core Application No. 1 1 2 REF PROTECTION E:\DATA AFTER Current Ratio (A) Output burden (VA) Accurac y class as per IEC 185 3 4 5 250-150100/1 - PS Formula for minimum knee-point voltage At CT Secondary resistance at 750C at 100A tap (Volt) 6 20 (RCT+1) Maximum Exciting Current (mA) Minimum Insulatio n Voltage (kV) 7 30 @ VK/2 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-1 NCT spec- November 2014 - Copy.doc CT-14 8 15 E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-1 NCT spec- November 2014 - Copy.doc CT-15 ANNEXURE I-C(i) (COREWISE DETAILS OF 72.5kV TRANSFORMER INCOMER NCT (1500-1000/1A) No. OF CORES= 1 Core Application No. 1 1 Current Ratio (A) 2 Output burden (VA) 3 REF PROTECTION Accuracy class as per IEC 185 4 5 - PS 1500-1000/1 Formula for min knee point voltage At CT Secondary res. at 750C at 1000A tap (Volt) 6 14 (RCT+2) Maximum Exciting Current (mA) Minimum Insulatio n Voltage (kV) 7 8 30 @ VK/2 15 ANNEXURE-I C(ii) COREWISE DETAILS OF 72.5 kV NEURAL CT FOR 66/11kV T/Fs (300-200-150/1) No. OF CORE = 1 Core No. Application Current Ratio (A) Output burden (VA) 1 2 3 4 1. REF PROTECTION 300-200150/1 - E:\DATA AFTER Maximum exciting current (mA) Minimum Insulation voltage (kV) 5 Formula for minimum knee point voltage at CT secondary resistance at 750 at 300A tap (Volt) 6 7 8 PS 20 (RCT+1) 30 @ Vk/2 15 Accuracy class as per IEC 185 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-1 NCT spec- November 2014 - Copy.doc CT-16 ANNEXURE-I-D(i) COREWISE DETAILS OF 36kV TRANSFORMER INCOMER NCT FOR 40/50MVA 132/33kV T/F AND OTHER RATINGS OF 132/33KV T/Fs WITH 26.3KA STC (1000-600-400/5) No. OF CORES = 1 Core Application No. 1 Current Ratio (A) 2 1 Output burden (VA) 3 REF PROTECTION 1000-600-400/5 Accuracy class as Per IEC 185 4 5 - PS Formula for minimum knee point voltage At CT Secondary resistance at 750C at 400A tap (Volt) 6 100 (RCT+1) Maximum Exciting Current (mA) Minimum Insulation Voltage (kV) 7 8 75@ VK/2 15 ANNEXURE-I-D(ii) COREWISE DETAILS OF 36kV TRANSFORMER INCOMER NCT FOR 220/33KV T/F WITH 26.3KA STC (2000-1000/5) No. OF CORES = 1 Core Application No. 1 1 Current Ratio (A) 2 Output Burden (VA) 3 REF PROTECTION 2000-1000 /5 Accuracy class as per IEC 185 4 5 Formula for minimum knee-point voltage At CT Secondary resistance at 750C at 2000A tap (Volt) 6 - PS 100 (RCT+1) Maximum Exciting Current (mA) Minimum Insulatio n Voltage (kV) 7 8 75@ VK/2 15 ANNEXURE-I-D(iii) COREWISE DETAILS OF 36kV TRANSFORMER NCT WITH 26.3KA STC FOR 4 MVA 33/11kV T/F (100-50/5) No. OF CORE = 1 Core Application No. 1 1 E:\DATA AFTER Current Ratio (A) 2 3 REF PROTECTION 100-50/5 Accuracy class as per IEC 185 4 PS Formula for minimum knee-point voltage At CT Secondary resistance at 750C at 100A tap (Volt) 5 100 (RCT+1) Maximum Exciting Current (mA) 6 75@ VK/2 Minimum Insulatio n Voltage (kV) 7 15 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-1 NCT spec- November 2014 - Copy.doc CT-17 ANNEXURE-I E(i) COREWISE DETAILS OF 12 kV NEUTRAL CT FOR 25/31.5 MVA T/F (1800-900/5) No. OF CORE = 1 Maximum exciting current (mA) Minimum Insulation voltage (kV) 4 Formula for minimum knee point voltage at CT secondary resistance at 750 at 1800A tap (Volt) 5 6 7 PS 95 (RCT+1) 75@ Vk/2 8.66 Core No. Application Current Ratio (A) Accuracy class as per IEC 185 1 2 3 1. REF PROTECTION 1800-900/5 ANNEXURE I-E(ii) COREWISE DETAILS OF 12kV NEUTRAL CT FOR 12.5/16 MVA & 16/20 MVA T/F (1200-900/5) No. OF CORE = 1 Core Application No. 1 1 Current Ratio (A) 2 3 REF PROTECTION 1200-900/5 Accuracy class as per IEC 185 4 PS Formula for minimum knee-point voltage At CT Secondary resistance at 750C at 1200A tap (Volt) 5 95 (RCT+1) Maximum Exciting Current (mA) 6 Minimum Insulatio n Voltage (kV) 7 75@ VK/2 8.66 ANNEXURE I-E(iii) COREWISE DETAILS OF 12kV NEUTRAL CT for 4MVA 33/11kV T/F (300-150/5) No. OF CORE = 1 Core Application No. 1 1 E:\DATA AFTER Current Ratio (A) 2 3 REF PROTECTION 300-150/5 Accuracy class as per IEC 185 4 PS Formula for minimum knee-point voltage At CT Secondary resistance at 750C at 300A tap (Volt) 5 95 (RCT+1) Maximum Exciting Current (mA) 6 75@ VK/2 Minimum Insulatio n Voltage (kV) 7 8.66 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-1 NCT spec- November 2014 - Copy.doc CT-18 ANNEXURE-II GUARANTEED TECHNICAL PARTICULARS (To be filled in by the Supplier separately for each type and voltage rating). 1. Manufacturer's Name 2. Type/Installation. 3. Conforming to standard. 4. Rated voltage. 5. Rated frequency. 6. Detail of cores. *Core No. I 6.1 Purpose of cores. 6.2 Rated Secondary Current. 6.3 Class of accuracy. 6.4 Accuracy limit factor. 6.5 Formula governing minimum II III IV V knee point voltage at CT Secondary resistance corrected to 75 C. 6.6 Instrument security factor. 6.7 Secondary limiting voltage. 6.8 Maximum Secondary resistance corrected to 75 C. 6.9 Rated burden. 6.10 Exciting current for Distance protection core at Vk, for Bus Bar protection core & REF Core at E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-1 NCT spec- November 2014 - Copy.doc CT-19 Vk/2. and for differential protection Core at Vk/4 * No. of cores as per applicability for a particular type of current 7. Rated primary current. 8. Rated short time withstand current (kA rms) for 1 second duration. 9. Rated dynamic withstand current (kA peak). 10. Rated continuous thermal current (pu). 11. One minute power frequency withstand voltage (kV rms) a) Dry b) Wet 12. 1.2/50 micro-second impulse withstand voltage (kV peak) 13. One minute power frequency withstand voltage of secondary winding (kV rms) 14. Minimum creepage distance (mm) 15. Maximum creepage factor. 16. Winding a) b) No. of primary turns Primary amp. turns E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-1 NCT spec- November 2014 - Copy.doc CT-20 (Dynamic condition) c) Current density d) Area of Cross-section & material i) ii) Primary turns Secondary turns 17. I.S. to which the oil conforms. 18. Weight of oil (kg). 19. Quantity of oil (Ltrs) 20. Total weight (kg). 21. Maximum shipping weight (kg) 22. Overall dimension. 23. Mounting details. 24. Maximum permissible temperature rise of winding when referred to maximum ambient temperature of 50 C in terms of clause 7.2 (Table 2 of IS:2705 Part-1-1992 ) or Equivalent IEC E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-1 NCT spec- November 2014 - Copy.doc CT-21 HARYANA VIDYUT PRASARAN NIGAM TECHNICAL SPECIFICATION FOR 420kV CVTs, 245kV, 145kV & 72.5kV CAPACITOR VOLTAGE TRANSFORMERS & POTENTIAL TRANSFORMERS AND 36kV POTENTIAL TRANSFORMERS E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-2 PT & CVT-Nov, 2012.doc CONTENTS ----------------------------------------------------------------------------CLAUSE NO. TITLE -----------------------------------------------------------------------------1.0 SCOPE PAGE NO. 3 2.0 STANDARDS 3 3.0 SERVICE CONDITIONS 4 4.0 PRINCIPAL PARAMETERS 4 5.0 GENERAL TECHNICAL REQUIREMENTS 5 6.0 TESTS 10 7.0 DOCUMENTATION 11 ANNEXURES I. COREWISE DETAILS FOR A-(i) 420kV CVTs 13 B-(i) 245kV CVTs 14 B-(ii) 245kV PTs 15 C-(i) 145kV CVTs 16 C-(ii) 145kV PTs WITH METERING CORE 17 D -(i) 72.5kV CVTs 18 D-(ii) 72.5kV PTs 19 E (i) 36kV PTs 20 GUARANTEED TECHNICAL PARTICULARS OF CVTs 21 GUARANTEED TECHNICAL PARTICULARS OF PTs ----------------------------------------------------------------------- 23 II. A II. B E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-2 PT & CVT-Nov, 2012.doc 1.0 SCOPE : 1.1 This specification provides for design, engineering, manufacture, testing of outdoor instrument transformers alongwith terminal connectors for protection and metering services in different 420/220/132/66kV S/Stn. in Haryana. It is not the intent to specify completely herein all details of the design and construction of equipments. However the equipment shall conform in all respects to high standards of engineering design and workmanship and shall be acceptable to the purchaser, who will interpret in a manner the meanings of drawings and specifications and shall have the power to reject any work or material, which in his judgement is not in accordance therewith. The equipment offered shall be complete with all components necessary for its effective and trouble free operation. Such components shall be deemed to be within the scope of supply irrespective of whether those are specifically brought out in this specification and or the commercial order or not. 1.2 2.0 STANDARDS: Sl.No. Standard No. 1. IS : 3156 (Part-I to Part-III) 2. IS : 3156 (Part-IV) 3. IS : 2099 4. IS : 3347 5. IS : 2071 6. IS : 335 7. IS : 2165 8. IS : 2147 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. IEC- 186 IEC - 186A IEC - 270 IS - 5561 IS -4800 IEC- 44 (4) IEC-171 IEC - 358 IEC-60 IEC-8263 IS: 9348 IS: 2633 IS: 11065 2.2 IS: 5621 Title. Voltage transformer Capacitor Voltage Transformer High Voltage porcelain bushing. Dimensions of porcelain transformer bushings Method of High Voltage Testing Insulating oil for transformers and switchgears Insulation Co-ordination for equipments of 100 kV and above. Degree of protection provided by enclosures for low voltage switchgear and control. Voltage Transformers First supplement to IEC publication 186 Partial discharge Measurement Terminal Connectors Enameled round winding wires Instrument Transformer measurement of PDs Insulation Co-Ordination Coupling capacitor divider. High Voltage testing techniques. Method for RIV test on high voltage insulators. Coupling capacitors and capacitor dividers Methods of testing hot dipped galvanized articles Drawings. Indian Electricity Rules 1956 Hollow porcelain insulators. Equipment meeting with the requirements of other authoritative standards, which ensure equal or better performance than the standards mentioned above, shall also be considered. When the equipment offered by the supplier E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-2 PT & CVT-Nov, 2012.doc conforms to other standards salient points of difference between standards adopted and the standards specified in this specification shall be clearly brought out in the relevant schedule. Four copies of such standards with authentic translation in English shall be furnished alongwith the offer. 3.0 SERVICE CONDITIONS : Equipment to be supplied against this specification shall be suitable for satisfactory continuous operation under the following tropical conditions:i) Location IN THE STATE OF HARYANA ° ii) Max. ambient air temp( C) 50 -2.5 iii) Min. ambient air temp (°C) iv) Maximum Relative humidity (%) 100 v) Minimum Relative humidity (%) 26 vi) Average annual rainfall (mm) 900 vii) Max. wind pressure (Kg/sq.m.) 195 viii)Max. altitude above mean sea level (meters) 1000 ix) Isoceraunic level (days/year) 50 x) Seismic level (horizontal acceleration) 0.3g. Note : Moderately hot and humid tropical climate conducive to rust and fungus growth. The climatic conditions are also prone to wide variations in ambient conditions. Smoke is also present in the atmosphere. Heavy lightening also occur during June to October. 4.0 PRINCIPAL PARAMETERS : The capacitor voltage transformers and potential transformers covered in this specification shall meet the technical requirements listed hereunder. PRINCIPAL TECHNICAL PARAMETERS: Sl. No. 1. Type/Installation 2. Type of mounting 3. Highest system voltage (kV rms) Suitable for system frequency Rated primary voltage (kV rms No. of Secondary Cores & Secondary Voltage (Volts) PT 4. 5. 6. i) Item Specification 420kV 245kV 145kV 72.5kV 36kV Single Phase, Oil filled,Self cooled, Hermetically sealed Outdoor type _____ -----Steel structure---------420 245 145 72.5 36 66/√3 33/√3 50 Hz 400/√3 - 220/√3 Core I,II 110/√3 132/√3 Core I,II,III 110/√3 Core I,II 110/√3 E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-2 PT & CVT-Nov, 2012.doc Core I,II 110/√3 ii) CVT 7. Method of earthing the system 1.2/50 microsecond lightning impulse withstand voltage (kVp) 1 Minute dry & wet power frequency withstand voltage primary (kV rms) Min. creepage distance of porcelain housing (mm) Creepage factor (max.) Rated voltage factor Equivalent capacitance at power frequency for carrier coupling for CVT (PF) Resultant high frequency capacitance for CVT (PF) One minute power frequency withstand voltage for secondary winding (kV rms) Max. temperature rise over ambient of 50°C 8. 9. 10. 11. 12. 13. 14. 15. 16. 5.0 5.1 5.1.1 Core I,II,III 110/√3 Core I,II, III 110/√3 Core I,II, III 110/√3 Core I,II 110/√3 - Solidly earthed 1425 1050 650 325 170 630 460 275 140 70 10500 6125 3625 1815 900 4.0 1.2 continuous and 1.5 for 30 seconds 8800+10% -5% N.A 8800 in carrier frequency range of 40 KHz N.A to 500 KHz with variation in capacitance as contained in IEC-358 (i.e- 20% & +50%) 3.0 As per IS:3156 or equivalent IEC GENERAL TECHNICAL REQUIREMENTS: Common for all CVTs & PTs The insulation of the instrument transformers shall be so designed that the internal insulation shall have higher electrical withstand capability than the external insulation. The designed dielectric withstand values of external and internal insulations shall be clearly withstand values specified in this E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-2 PT & CVT-Nov, 2012.doc 5.1.2 5.1.2.1 5.1.2.2 5.1.3 5.1.4 5.1.5 5.1.6 5.1.6.1 i) ii) iii) 5.1.7 5.1.8 5.1.9 guaranteed technical particulars. The dielectric withstand values specified in this specification are meant for fully assembled instrument transformers. Porcelain Housing : The details of location and type of joint, if provided on the porcelain, shall be furnished by the supplier alongwith the offer. The housing shall be made of homogeneous, vitreous porcelain of high mechanical and dielectric strength, glazing of porcelain shall be of uniform brown or dark brown colour with a smooth surface arranged to shed away rain water or condensed water particles (fog). Details of attachment of metallic flanges to the porcelain shall be brought out in the offer. Nuts and bolts or screws used for fixation of the interfacing porcelain bushings for taking out terminals, shall be provided on flanges cemented to the bushings and not on the porcelain. METAL TANK: The metal tanks shall have bare minimum number of welded joints so as to minimise possible locations of oil leakage. The metal tanks shall be made out of mild steel/Stainless steel/aluminium alloy, depending on the requirement. Welding in horizontal plane is to be avoided as welding at ths location may give way due to vibratins during transport resulting in oil leakage. Supplier has to obtain specific approval from purchaser for any horizontal welding used in the bottom tank. Surface Finish: The ferrous parts exposed to atmosphere shall be hot dip galvanised or shall be coated with atleast two coats of zinc rich epoxy painting. All nuts, bolts and washers shall be made out of stainless steel. Insulating Oil: Insulating oil required for first filling of the instrument transformer shall be covered in supplier's scope of supply. The oil shall meet the requirements of latest edition IS:335 or equivalent IEC. Prevention of Oil leakages and Entry of Moisture: The supplier shall ensure that the sealing of instrument transformer is properly achieved. In this connection the arrangement provided by the supplier at various locations including the following ones shall be described, supported by sectional drawings. Locations of emergence of primary and secondary terminals. Interface between porcelain housing and metal tanks. Cover of the secondary terminal box. GASKETS: For gasketed joints, wherever used nitrile butyl rubber gaskets shall be used. The gasket shall be fitted in properly machined groove with adequate space for accommodating the gasket under compression. Oil level indicators: Instrument transformers shall be provided with oil sight window (Prismatic Type) at suitable location so that the oil level is clearly visible with naked eye to an observer standing at ground level. EARTHING: E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-2 PT & CVT-Nov, 2012.doc Metal tank of the instrument transformer shall be provided with two separate earthing terminals for bolted connection to 50X8mm MS flat to be provided by the Purchaser for connection to station earth-mate. LIFTING & TRANSPORTATION ARRANGEMENTS: Instrument transformer shall be provided with suitable lifting arrangement, to lift the entire unit. The lifting arrangement shall be clearly shown in the general arrangement drawings. Lifting arrangement (lifting eye) shall be positioned in such a way so as to avoid any damage to the porcelain housing or the tanks during lifting for installation/transport. If necessary, string guides shall be offered which shall be of removable type. The instrument transformers shall be so constructed that it can be easily transported to site within the allowable transport limitation and in horizontal position, if the transport limitations so demand. 5.1.10 5.1.11 NAME PLATE: The instrument transformer shall be provided with non-corrosive, legible name plate with the information specified in relevant standards, duly engraved/punched on it. In addition to these P.O. NO.& Connection diagram shall also be marked in rating plate. 5.1.12 TERMINAL CONNECTORS: Suitable terminal connectors of type 4” IPS Aluminium tube for 400kV CVTs and suitable terminal connectors for connecting single Tarantulla conductor for 220kV CVTs/PTs & for Single ACSR Zebra in 132kV, 66kV CVTs/PTs & 33kV PTs shall be supplied. Suitable terminal earth connectors for earthing connections shall also be provided. The terminal connectors shall meet the following requirements: Terminal connectors shall be manufactured and tested as per IS:5561 or equivalent IEC. All castings shall be free from blow holes, surface blisters, cracks and cavities. All sharp edges and corners shall be blurred and rounded off. No part of a clamp shall be less than 10mm thick. All ferrous parts shall be hot dip galvanized conforming to IS:2633 or equivalent IEC. For bimetallic connectors, copper alloy liner of minimum 2mm thickness shall be cast integral with aluminium body. Flexible connectors shall be made from tinned copper/aluminium sheets. All currents carrying parts shall be designed and manufactured to have minimum contact resistance. Connectors shall be designed to be corona free in accordance with the requirements stipulated in IS: 5561 or equivalent IEC. 5.1.12.1 1) 2) 3) 4) 5) 6) 7) 8) 5.1.13 INSULATION: Enamel, if used for conductor insulation, shall be polyvinyl acetate type or amide emide type and shall meet the requirements of IS:4800 or equivalent IEC. Polyester enamel shall not be used. Double cotton cover, if used, shall be suitably covered to ensure that it does not come in contact with oil. 5.1.14 TEMPERATURE RISE: The temperature rise on any part of equipment shall not exceed maximum temperature rise specified in IS:3156 or equivalent IEC. However, the permissible temperature rise indicated is for a maximum ambient temperature of 50°C. OIL FILLING & DRAIN VALVES: 5.1.15 E:\DATA AFTER 2012.doc 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-2 PT & CVT-Nov, 5.1.16 5.2 5.2.1 5.2.2 5.2.3 5.2.4 5.2.5 5.2.6 5.2.7 5.2.8 5.2.9 5.2.10 E:\DATA AFTER 2012.doc The instrument transformers shall be vacuum filled with oil after processing and thereafter hermetically sealed to eliminate breathing and to prevent air and moisture from entering the tanks, sealing type oil filling and/or oil sampling cocks shall be provided with facility to reseal the same. The method adopted for hermetic sealing shall be described in the offer. PRESSURE RELIEF DEVICE: Suitable arrangement shall be made to accommodate the expansion and contraction of oil due to temperature variation. The pressure variation shall be kept within limits which do not impair the tightness of the instrument transformer. A pressure relief device capable of releasing abnormal internal pressure shall be provided. CAPACITOR VOLTAGE TRANSFORMER (CVT): The CVTs comprising of a capacitor divider unit and electromagnetic unit shall be single phase, oil filled hermetically sealed, self cooled, outdoor type and suitable for direct line connection without any fuse and isolating switches, These CVTs are required to be used on interlinking substations in Haryana power system for the purpose of protection, synchronising, interlocking, carrier coupling and metering. CVTs shall be suitable for connecting the carrier terminals to single circuit and double circuit transmission lines for phase to phase coupling for power line carrier, voice communication, telemetering & teleprinting services. The secondary terminals of potential unit, high frequency coupling terminal and the earthing terminals shall be brought out separately and housed in a water proof cabinet outside the main steel chamber. The capacitor voltage transformer shall be suitable for simultaneous use as measuring unit, for feeding voltage supply to protective relays and as coupling capacitor for carrier transmission i.e. for voice communication, carrier protective relays, telemetering, teleprinting services over one or more carrier channels in the frequency range of 40 to 500KHz. The capacitors shall be designed for wide frequency band and low dielectric loss. Their natural frequency shall be considerably higher than the carrier frequency range of 40 KHz to 500 KHz. The unit capacitors shall be so designed that no damage to internal elements or change in electrostatic capacitance is resulted by the application of impulse voltage. Each CVT including its emvt unit shall be filled with insulating oil conforming to IS:335 or equivalent IEC. And shall be hermetically sealed against moisture and dust. The electromagnetic voltage transformer unit of CVT intended for out-door installation whose primary is to be fed by the inter-mediate tapping of capacitor divider shall be of oil immersed, self cooled design and shall be suitable for metering, relaying & synchronising services. The core of this transformer shall be of high accuracy at normal & high voltages. The primary winding shall be connected through a compensating reactor to compensate the voltage increase at inter-mediate tapping, whatever is the load within range of rated burden. The design shall be free from corona effect to keep noise level of carrier frequency link very low. Use may be made of grading rings or Electrostatic screen for this purpose if required. The design shall be suitable for rapid reclosing of the circuit and shall be capable of accurate and proportionate transmission of sudden variation in the primary voltage. Each CVT shall be provided with a suitable damping device so that ferro resonance oscillation due to saturation of iron core of transformer or any inductance connected in 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-2 PT & CVT-Nov, 5.2.11 i) ii) iii) parallel with it and initiated by either over voltages on the net work side or by opening of the short circuited primary or secondaries, shall be practically zero. Oscillations of the secondary voltages which may arise as a result of breakdown of primary voltages due to short circuits shall not affect the proper working of protective relays. This shall confirm to provisions of clause:42 of IEC recommendations 186-A. Design of the potential units of the CVT shall be based on the following requirements in connection with protective relaying. They must transmit accurately sudden drops of primary voltage. The CVTs must not enter into sub-harmonic resonance and transient oscillations during energisation. They must be damped out with sufficient rapidness. They must have sufficiently low short circuit impedance as seen from secondary. 5.2.12 A device shall be incorporated in a capacitor voltage transformer for the purpose of limiting over voltages which may appear across one or more of its components and/or to prevent sustained ferro resonance. The device may include a spark gap and may be located in several different ways according to its nature. (Clause 2.12 of IS:3156 (Part-IV)-1978 or IEC-186A Clause 37.12) 5.2.13 5.2.13.1 SECONDARY TERMINAL BOXES: Suitable terminal boxes with removable gland plate for facilitating the entry of H.F. Cable & VT control cables shall be provided at an accessible position. The secondary terminals of 420kV, 245kV, 145kV & 72.5kV CVTs shall be brought out in two separate weather proof terminal boxes and it shall be provided with a removable gland plates. In case of 420kV, 245kV & 145kV CVTs, in the first box, secondary terminals of CoreI & II (i.e. Protection and measurement cores) shall be brought out. For 72.5kV CVT in the first box the secondary terminals of 1st core (i.e. Protection and measurement core) shall be brought out. In the second box the secondary terminals of 3rd core (i.e metering Core) of 420kV, 245kV & 145kV CVTs and 2nd core (i.e metering Core) of 72.5kV CVT shall be brought out. The Metering secondary terminal box shall be provided with proper sealing facility. 5.2.13.2 5.3 Voltage Transformer (PT): 5.3.1. 5.3.1.1 CORE: The voltage transformers shall be oil immersed, sealed type and self cooled, suitable for the services indicated & conforming to the modern practices of designs and construction. The core shall be of high grade, non ageing, electrical silicon laminated steel of low hysteresis loss and high permeability to ensure high accuracy at both normal and over voltages. 5.3.1.2 i) ii) The design of PT shall be based on following requirements. They must transmit sudden drops of primary voltages. They must have sufficiently low short circuit impedance as seen from secondary. 5.3.2. 5.3.2.1 SECONDARY TERMINAL BOXES: The secondary terminals of the PTs except 145KV PTs (having 3 cores) & 36kV PTs (Having two cores) shall be brought out in a weather proof terminal box and it shall be provided with a removable gland plate. In case of 145kV & 36kV PTs, two separate weather proof terminal boxes shall be provided. E:\DATA AFTER 2012.doc 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-2 PT & CVT-Nov, In the first box, the terminals of core-I & II of 145kV PT and Core-II of 36kV PT shall be brought out. The terminal box shall be provided with a removable gland plate. In the second box, the terminals of Core-III of 145kV PT (i.e. metering core) and core-I of 36kV PT shall be brought out. The terminal box shall be provided with a removable gland plate and with proper sealing facility. 5.3.2.2 All the fuses and the links shall be provided at the V.T terminal boxes. 5.3.2.3 The primary winding of voltage transformers will be connected phase to ground. 6.0 6.1 6.1.1 TESTS : TYPE TEST TYPE TESTS OF POTENTIAL TRANSFORMERS (PT's) The equipment offered should be fully type tested. In case, the equipment of the type and design offered has already been type tested, the supplier shall furnish 4 sets of type test reports alongwith the offer. The type test reports should not be more than seven years old, reckoned from the date of bid opening and the type test should have been carried out in accordance with ISS-2705(1992)/equivalent IEC from Govt./ Govt. approved test house. However, temperature rise test although covered under type tests will be got conducted by the supplier on one piece of total ordered quantity of each type, at his premises in the presence of the inspecting officer of the purchaser, without any extra charges. The purchaser reserves the right to demand repetition of some or all the type tests in the presence of purchaser's representative. 6.1.2 TYPE TESTS OF CAPACITIVE VOLTAGE TRANSFORMERS (CVT's) The equipment offered should be fully type tested. In case, the equipment of the type and design offered has already been type tested, the supplier shall furnish 4 sets of type test reports of the following tests alongwith the offer. Tests as per clause No. 12.1, 12.2 & 14 of IEC-358 (1990)and clause 10.1 (b), 10.1 (d), 10.1(e), 10.1(f), 49,51,52 & 53 of IEC-186 (1987) latest addition of IEC's to be considered. 6.2 i) ii) 7.0 E:\DATA AFTER 2012.doc The type test reports should not be more than seven years old, reckoned from the date of bid opening and the type test should have been carried out in accordance with IEC358(1992) and IEC-186 (1987) from Govt. approved test house. However, temperature rise test although covered under type tests will be got conducted by the supplier on one place of total ordered quantity of each type, at his premises in the presence of the inspecting officer of the purchaser, without any extra charges. The purchaser reserves the right to demand repetition of some or all the type tests in the presence of purchaser's representative. ACCEPTANCE AND ROUTINE TESTS : All acceptance and routine tests as stipulated in the relevant standards shall be carried out by the Supplier in presence of purchaser's representative, unless dispensed with in writing by the Purchaser. Immediately after finalisation of the programme of routine /acceptance testing , the Supplier shall give sufficient advance intimation to the Purchaser to enable him to depute his representative for witnessing the testing. DOCUMENTATION: 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-2 PT & CVT-Nov, 7.1 All drawings shall conform to international standards organisation (ISO) `A' series of drawing sheet/Indian Standards Specification IS:11065. All drawings shall be in ink and suitable for microfilming. If drawings are computerized than all drawings shall be nicely printed. All dimensions and data shall be in S.I.Units. 7.2 List of drawings: General outline and assembly drawings of the equipment. Graphs showing the performance of equipment's in regard to magnetisation characteristics; ratio & phase angle curves, ratio correction factor curves. Sectional views showing: General Constructional Features. Materials/Gaskets/Sealing used. The insulation & the winding arrangements, method of connection of the primary / secondary winding to the primary/ secondary terminals etc. Porcelain used and its dimensions. Arrangement of terminals and details of connection studs provided. Name plate. Schematic drawing. Detailed drawing of pressure release device with detailed literature. Terminal connector drawing. a) b) c) i) ii) iii) iv) d) e) f) g) h) NOTE:- All above drawings should bear a minimum space (14X10cm) for stamping the approval of drawings by the purchaser. 7.3 The bidder shall submit four sets of final versions of complete and correct equipment drawings except 7.2 (b) above (actual of which shall be supplied at the time of inspection) for purchaser’s approval alongwith bid in a sealed envelope. The purchaser shall communicate his comments/approval on the drawings to the supplier within 21 days from the date of issue of LOI. The submission of complete and correct readable drawings for approval is the responsibility of the bidder/supplier. The supplier shall, if so required by the purchaser, modify the drawings and resubmit four copies of the modified drawings for purchaser’s approval within two weeks from the date of purchaser’s comments. Then, the purchaser shall approve the revised drawings within two weeks from the date of its receipt. 7.4 The manufacturing of the equipment shall be strictly in accordance with the approved drawings and no deviation shall be permitted without the written approval of the purchaser. All manufacturing and fabrication work in connection with the equipment prior to the approval of the drawing shall be at the supplier's risk. 7.5 The successful bidder shall also supply one set of nicely bound all the approved drawings & instruction manual containing handling, installation, testing and commissioning of equipment at the time of dispatch of material to the consignee with each equipment for our field staff without which the supply will not be considered as complete supply. In addition, 5 sets of such bound manuals and final approved drawings shall be supplied for reference & record in our design office alongwith one good quality soft copy (CD) of approved drawings and instruction manuals, if computerized. 7.6 Approval of drawings / work by Purchaser shall not relieve the Supplier of his E:\DATA AFTER 2012.doc 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-2 PT & CVT-Nov, responsibility and liability for ensuring correctness and correct interpretation of the latest revision of applicable standards, rules and codes of practices. The equipment shall conform in all respects to high standards of engineering, design, workmanship and latest revisions of relevant standards at the time of ordering and purchaser shall have the power to reject any work or material which in his judgement is not in full accordance therewith. NOTE :- 1. In case the equipment offered by the Supplier does not meet with the requirement of technical specification the offer of the firm shall not be considered. E:\DATA AFTER 2012.doc 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-2 PT & CVT-Nov, ANNEXURE- I A (i) COREWISE DETAILS OF 420kV CAPACITOR VOLTAGE TRANSFORMER (CVT) Sl. Requirement No. 1. Rated Primary voltage 2. Type 3. No. of Secondaries 4. Rated voltage factor 5. Capacitance (minimum) 6. Rated voltage (volts) 7. Application 8. Accuracy 9. Output burden (VA) 10Percentage voltage error & phase displacement (minutes) for respective specified accuracy classes. Note:- E:\DATA AFTER 2012.doc Particulars 400/√3kV Single phase 3 1.2 continuous & 1.5 for 30 seconds 8800 (+10%, -5%) pico farads Secondary-I Secondary-II Secondary-III 110/√3 110/√3 110/√3 Metering & Protection Metering Protection 1/3P 3P 0.2 100 50 50 As per ISS/IEC Each winding shall fulfill its respective specified accuracy requirement within its specified output range whilst at the same time the other winding has an output of any value form zero to 100% of the output range specified for the other winding in line with clause 6.2.1 of IS 3156 (Part-2 & Part-3) 1992 or its equivalent IEC. 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-2 PT & CVT-Nov, ANNEXURE- IB(i) COREWISE DETAILS OF 245kV CAPACITOR VOLTAGE TRANSFORMER (CVT) Sl. Requirement No. 11. Rated Primary voltage Particulars 220/√3kV 12. Type 13. No. of Secondaries 3 14. Rated voltage factor 1.2 continuous & 1.5 for 30 seconds 15. Capacitance (minimum) 16. Rated voltage (volts) 17. Application Single phase 8800 (+10%, -5%) pico farads Secondary-I Secondary-II Secondary-III 110/√3 110/√3 110/√3 Protection & Protection Metering Measurement 18. Accuracy 1/3P 3P 0.2 19. Output burden (VA) 100 50 10 20. Percentage voltage error & phase displacement (minutes) for respective specified accuracy classes. Note:- E:\DATA AFTER 2012.doc As per ISS/IEC Each winding shall fulfil its respective specified accuracy requirement within its specified output range whilst at the same time the other winding has an output of any value form zero to 100% of the output range specified for the other winding in line with clause 6.2.1 of IS 3156 (Part-2 & Part-3) 1992 or its equivalent IEC. 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-2 PT & CVT-Nov, ANNEXURE- IB(ii) COREWISE DETAILS OF 245kV POTENTIAL TRANSFORMER (PT) Sl. Particulars No. 1. Rated Primary voltage Requirement 2. Type Single phase 3. No. of Secondaries 2 4. Rated voltage factor 1.2 continuous & 1.5 for 30 seconds 5. Rated voltage (volts) 6. Application 220/√3kV Secondary-I Secondary-II 110/√3 110/√3 Protection & Protection Measurement 7. Accuracy 1/3P 3P 8. Output burden (VA) 150 50 9. Percentage voltage error & phase (minutes) As per ISS/IEC displacement for respective specified accuracy classes. Note:- E:\DATA AFTER 2012.doc Each winding shall fulfil its respective specified accuracy requirement within its specified output range whilst at the same time the other winding has an output of any value form zero to 100% of the output range specified for the other winding in line with clause 6.2.1 of IS 3156 (Part-2 & Part-3) 1992 or its equivalent IEC. 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-2 PT & CVT-Nov, ANNEXURE- IC(i) COREWISE DETAILS OF 145kV CAPACITOR VOLTAGE TRANSFORMER (CVT). Sl. Requirement No. 1. Rated Primary voltage Particulars 132√3kV 2. Type 3. No. of Secondaries 3 4. Rated voltage factor 1.2 continuous & 1.5 for 30 seconds 5. Capacitance (minimum) 6. Rated voltage (volts) 7. Single phase Application 8800 (+10%, -5%) pico farads Secondary-I Secondary-II Secondary-III 110/√3 110/√3 110/√3 Protection & Protection Metering 1/3P 3P 0.2 50 25 10 Measurement 8. Accuracy 9. Output burden (VA) 10. Percentage voltage error & phase (minutes) As per ISS/IEC displacement for respective specified accuracy classes. Note:- E:\DATA AFTER 2012.doc Each winding shall fulfil its respective specified accuracy requirement within its specified output range whilst at the same time the other winding has an output of any value form zero to 100% of the output range specified for the other winding in line with clause 6.2.1 of IS 3156 (Part-2 & Part-3) 1992 or its equivalent IEC. 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-2 PT & CVT-Nov, ANNEXURE- IC(ii) COREWISE DETAILS OF 145kV POTENTIAL TRANSFORMER (PT). Sl. Particulars No. 1. Rated Primary voltage Requirement 2. Type Single phase 3. No. of Secondaries 3 4. Rated voltage factor 1.2 continuous & 1.5 for 30 seconds 5. Rated voltage (volts) 6. Application 132/√3kV Secondary-I Secondary-II Secondary-III 110/√3 110/√3 110/√3 Protection & Protection METERING Measurement 7. Accuracy 1/3P 3P 0.2 8. Output burden (VA) 250 25 20 9. Percentage voltage error & phase (minutes) As per ISS/IEC displacement for respective specified accuracy classes. Note:- E:\DATA AFTER 2012.doc Each winding shall fulfil its respective specified accuracy requirement within its specified output range whilst at the same time the other winding has an output of any value form zero to 100% of the output range specified for the other winding in line with clause 6.2.1 of IS 3156 (Part-2 & Part-3) 1992 or its equivalent IEC. 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-2 PT & CVT-Nov, ANNEXURE- ID(i) COREWISE DETAILS OF 72.5kV CAPACITOR VOLTAGE TRANSFORMER (CVT)S. Sl. Requirement No. 1. Rated Primary voltage Particulars 66/√3kV 2. Type 3. No. of Secondaries 2 4. Rated voltage factor 1.2 continuous & 1.5 for 30 seconds 5. Capacitance (minimum) 6. Rated voltage (volts) 7. Single phase Application 8800 (+10%, -5%) pico farads Secondary-I Secondary-II 110/√3 110/√3 Protection & Metering Measurement 8. Accuracy 9. Output burden (VA) 10. Percentage voltage error & phase (minutes) 1/3P 0.2 50 10 As per ISS/IEC displacement for respective specified accuracy classes. Note:- E:\DATA AFTER 2012.doc Each winding shall fulfil its respective specified accuracy requirement within its specified output range whilst at the same time the other winding has an output of any value form zero to 100% of the output range specified for the other winding in line with clause 6.2.1 of IS 3156 (Part-2 & Part-3) 1992 or its equivalent IEC. 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-2 PT & CVT-Nov, ANNEXURE- ID(ii) COREWISE DETAILS OF 72.5kV POTENTIAL TRANSFORMER (PT). Sl. Particulars No. 1. Rated Primary voltage Requirement 2. Type Single phase 3. No. of Secondaries 2 4. Rated voltage factor 1.2 continuous & 1.5 for 30 seconds 5. Rated voltage (volts) 6. Application 66/√3kV Secondary-I Secondary-II 110/√3 110/√3 Protection & Protection Measurement 7. Accuracy 1/3P 3P 8. Output burden (VA) 250 25 9. Percentage voltage error & phase (minutes) As per ISS/IEC displacement for respective specified accuracy classes. Note:- E:\DATA AFTER 2012.doc Each winding shall fulfil its respective specified accuracy requirement within its specified output range whilst at the same time the other winding has an output of any value form zero to 100% of the output range specified for the other winding in line with clause 6.2.1 of IS 3156 (Part-2 & Part-3) 1992 or its equivalent IEC. 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-2 PT & CVT-Nov, ANNEXURE- IE(i) COREWISE DETAILS OF 36kV POTENTIAL TRANSFORMER (PT) OF 2 CORES. Sl. Requirement No 1. Rated Primary voltage Particulars 33/√3kV 2. Type Single phase 3. No. of Secondaries 2 4. Rated voltage factor 1.2 continuous & 1.5 for 30 seconds 5. Rated voltage (volts) Secondary-I Secondary-II 110/√3 110/√3 Main metering Metering & Protection 6. Application 7. Accuracy 0.2 1/3P 8. Output burden (VA) 10 50 9. Percentage voltage error & phase As per ISS/IEC displacement (minutes) for respective specified accuracy classes. Note:- E:\DATA AFTER 2012.doc Each winding shall fulfil its respective specified accuracy requirement within its specified output range whilst at the same time the other winding has an output of any value form zero to 100% of the output range specified for the other winding in line with clause 6.2.1 of IS 3156 (Part-2 & Part-3) 1992 or its equivalent IEC. 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-2 PT & CVT-Nov, ANNEXURE-IIA GUARANTEED TECHNICAL PARTICULARS CAPACITIVE VOLTAGE TRANSFORMER E:\DATA AFTER 2012.doc 1. Name of manufacturer 2. Type and model 3. Rated voltage (kV) 4. Capacitance : a) Primary capacitance C1 (pf) b) Secondary capacitance C2 (pf) c) Equivalent capacitance C (pf) 5. Number of secondary windings 6. Rated secondary windings : a) Winding-I (volts) b) Winding -Ii (volts) 7. Rated secondary burden: a) Winding - I (VA) b) Winding - II (VA) 8. Accuracy class of each secondary : a) Winding -I (VA) b) Winding - II (VA) 9. Rated voltage factor with rated burden. 10. One minute power frequency withstand: Test (Dry) voltage (kV rms) 11. One minute power frequency withstand test (wet) voltage (kV rms) 12. 1.2/50 micro second impulse wave withstand test voltage (kV rms) 13. One minute power frequency withstand voltage on secondaries (kV rms) 14. Total creepage distance (mm) 15. Creepage factor 16. Is CVT suitable for carrier frequency in the range of 40 to 500 KHz? (Yes/No) 17. Natural frequency of coupling capacitors 18. Rated Primary 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-2 PT & CVT-Nov, burden of potential devices (VA) E:\DATA AFTER 2012.doc 19. Temperature rise at 1.2 times rated voltage with rated burden (°C) 20. Guaranteed value of temp. coefficient. (percent per °Ce 21. Guaranteed value of radio interference voltage in micro-volts at different voltages. 22. Guaranteed sealing test. The pressure at which sealing test is to be carried out. 23. Guaranteed value of the H.F capacitances and equivalent series resistance at different. 24. Value of stray capacitance and stray conductance in the carrier frequency range of 40 to 500 KHz. 25. 26. Weight of oil and the standard to which it conforms i) In capacitor unit (Kg/IS) ii) In measuring unit. (Kg/IS) Total weight (Kg) 27. Over -all dimensions (mm) 28. Mounting flange dimensional details 29. Whether CVT are suitable for Carrier communication, carrier protection, carrier telemetering and carrier teleprinting services, metering, relaying protection, synchronising and interlocking purposes. 30. Do the CVTs contain built in compensating reactors and damping device in P.T. portion? (Yes/No) 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-2 PT & CVT-Nov, ANNEXURE-IIB POTENTIAL TRANSFORMER 1. Manufacturer's type and designation. 2. Type 3. Rated Frequency 4. Rated primary voltage 5. Number of secondary windings 6. Rated secondary windings : a) Winding-I b) Winding -II c) Winding -III 7. Class of Accuracy. a) Winding - I b) Winding - II c) Winding -III 8. Limits of errors. a) Winding -I i) Percentage voltage ratio error ii) Phase displacement. (Minutes) b) Winding - II i) Percentage voltage ratio error ii) Phase displacement (minutes) c) Winding - III i) Percentage voltage ratio error iii) Phase displacement (minutes) 9. Rated burden. a) Winding - I b) Winding -II c) Winding-III 10. 11. Temperature rise at 1.2 times rated applied continuously with rated burden (°C) 12. Insulation class of a) Primary windings b) Secondary windings 13. One minute power frequency: (Dry) withstand Test voltage (kV) One minute power frequency (wet) 14. E:\DATA AFTER 2012.doc Rated voltage factor and time voltage when 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-2 PT & CVT-Nov, withstand test voltage (kV) E:\DATA AFTER 2012.doc 15. 1.2/50 micro second impulse withstand test voltage (kV peak) 16. One minute power frequency withstand voltage on secondaries (volts) 17. 18. a) Creepage distance. c) Creepage factor Standard to which the equipment conforms 19. Standard to which the oil conforms 20. Total weight of the P.T. 21. Overall dimensions 22. Mounting details 23. Weight of the oil 24. Total shipping weight. 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-2 PT & CVT-Nov, HARYANA VIDYUT PRASARAN NIGAM TECHNICAL SPECIFICATION FOR 400kV, 220 kV, 132 kV, 66 kV & 33 kV CONTROL AND RELAY PANEL BOARDS FOR SUBSTATIONS WITH SUBSTATION AUTOMATION SYSTEM E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 1 CONTENTS -------------------------------------------------------------------------------CLAUSE NO. TITLE PAGE NO. --------------------------------------------------------------------------------1.0 2.0 3.0 4.0 5.0 6.0 7.0 SCOPE STANDARDS SERVICE CONDITION PRINCIPAL PARAMETERS GENERAL TECHNICAL REQUIREMENTS TESTS DOCUMENTATION 3 3 4 5 6 26 26 ANNEXURES 1. 2. A. B. C. D. E. F. G. H. TECHNICAL SPECIFICATION FOR SUBSTATION AUTOMATION SYSTEM SIGNAL LIST OF BASIC MONITORING REQUIREMENTS GUARANTEED TECHNICAL PARTICULARS TECHNICAL PARTICULARS OF CTs, NCTs, PTs & CVTs TRANSMISSION LINE DATA SCHEDULE OF DEVIATIONS FROM THE SPECIFICATION LINE PARAMETERS DETAILS OF CARRIER EQUIPMENTS SAS ARCHITECTURE TECHNICAL SPECIFICATION FOR AC KIOSK 29 54 58 63 79 80 81 82 83 84 --------------------------------------------------------------------------------- E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 2 1.0 1.1 1.2 1.3 SCOPE: This specification covers the design, engineering, manufacture, inspection & testing at manufacturer's work before dispatch, packing, forwarding and delivery at discretion of purchaser of Control & Relay Panels for 400kV,220 kV, 132 kV & 66 kV S/Stns. having Substation Automation System in the state of Haryana. Unless specifically excluded from the offer, all fittings and accessories, not specifically stated in this specification but which are necessary for satisfactory operation of the scheme or to complete the work in a good workman like manner shall be deemed to have been included in the scope of supply of the Bidder. CO-ORDINATION : Circuit Breakers, CT's, PT's/CVT's & Isolating Switches, etc. are being purchased against separate specification. The particulars of CTs, PTs and CVTs existing/ to be arranged are listed at Annexure 'B'. The Supplier of control & relay boards shall be responsible for preparing complete wiring diagram of 33kV,66kV,132 kV, 220 kV & 400kV C&R panel boards and shall also undertake to mount & wire any equipment received from other supplier. The schematic of breakers & isolators are required to be incorporated in the panel schematic. The technical specification of substation automation system provided at the sub station is enclosed as Annexure-1.The panels to be supplied should be compatible to the existing automation system at the substation. 1.4 EXPERIENCE: 1.4.1 For 400kV & 220kV C&R Panels: The supplier of C&R panels shall be manufacturer of relays and all the main relays on the C&R panels shall be of his make only. However, one of the distance protection schemes on each 400kV & 220 kV feeder C&R panel can be of different make in view of the fact that both the distance protection scheme (Main-I & Main-II) should have different measuring techniques. 1.4.2 For 132kV, 66kV & 33kV C&R Panels: The supplier of C&R panels shall be manufacturer of relays and all the main relays on the C&R panels shall be of his make only. The supplier’s own make relay includes the relays manufactured by their Principals/Associates and they have their service centre with them. 2.0 2.1 STANDARDS : The equipment offered shall conform to latest relevant Indian Standards listed hereunder or equivalent IEC :Sr. No. 1. 2. Standard IS: 5 IS: 375 3. IS: 694 4. 5. IS: 722 IS: 1248 Part-I& IV IS: 2419 6. Title Colour for ready mix paints. Marking & arrangements for switchgear, bus bars, main connections & auxiliary wiring. PVC insulated cable for working voltage upto and including 1100 V. AC Electricity meters. Direct acting indicating analogue electrical measuring instruments & their accessories. Dimensions for panel mounted indicating & recording electrical instruments. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 3 Sr. No. 7. 8. 9. Standard IS :3231 IS :8686 IS :2147 Title Electrical relays for power system protection. Static protective relays. Degree of protection provided by enclosures for low voltage switchgear & control gear. 2.2 The works covered by the specification shall be designed, engineered, manufactured, built, tested and commissioned in accordance with the Acts, Rules, Laws and Regulations of India. 2.3 The equipment to be furnished under this specification shall conform to latest issue with all amendments of standard specified above. 2.4 In addition to meeting the specific requirement called for in the Technical Specification, the equipment shall also conform to the general requirement of the relevant standards and shall form an integral part of Specification. 2.5 The Bidder shall note that standards mentioned in the specification are not mutually exclusive or complete in themselves, but intended to compliment each other. 2.6 The Contractor shall also note that list of standards presented in this specification is not complete. Whenever necessary the list of standards shall be considered in conjunction with specific IS/IEC. 2.7 When the specific requirements stipulated in the specification exceed or differ than those required by the applicable standards, the stipulation of the specification shall take precedence. 2.8 Other internationally accepted standards which ensure equivalent or better performance than that specified in the standard referred shall also be accepted. 2.9 In case governing standards for the equipment is different from IS or IEC, the salient points of difference shall be clearly brought out alongwith English language version of standard or relevant extract of the same. The equipment conforming to standards other than IS/IEC shall be subject to Employer's approval. 2.10 The bidder shall clearly indicate in his bid the specific standards in accordance with which the works will be conformed. 3.0 SERVICE CONDITIONS: 3.1 Equipment to be supplied against this specification shall be suitable for satisfactory continuous operation under the following tropical conditions:- E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 4 i. Location In the state of Haryana ii. Max. ambient air temp (°C) 50 iii. Min. ambient air temp (°C) -2.5 iv. Maximum Relative humidity (%) 100 v. Minimum Relative humidity (%) 26 vi. Average annual rainfall (mm) 900 vii. Max. wind pressure (kg/sq. m.) 195 viii. Max. altitude above mean sea level (meters) 1000 ix. Isoceraunic level (days/Year) 50 x. Seismic level (horizontal acceleration) xi. Average number of dust storm (days per annum) 0.3 g 35 Note:-i) Moderately hot and humid tropical climate conducive to rust and fungus growth. The climatic conditions are also prone to wide variations in ambient conditions. ii) Air conditioning or any special arrangement for making the control room dust proof shall not be provided in any of the S/Stn. 3.2 All control wiring, equipment & accessories shall be protected against fungus growth, condensation, vermin & other harmful effects due to tropical environments. 3.3 AUX. POWER SUPPLY : i) A.C. Supply Voltage variation Frequency variation ii) D C Supply Variation : : : : : 415/240 Volts, 3-phase, 4-wire, 50 Hz ± 10% ± 3% 220 Volts, 2 wire available from S/Stn. battery(insulated) ±10%. 3.4. 400kV, 220 kV, 132 kV, 66 kV & 33 kV voltages will be three phase having normal frequency of 50 Hz subject to a variation of ± 3%. Neutrals of the Power Transformers at the S/Stn. covered in this specification are solidly earthed. 4.0 PRINCIPAL PARAMETERS: The panel shall have the principal dimensions as detailed below:i). Depth of panels = 610 mm ii). a) Height of switchboard above base frame = 2210 mm b) Height of base frame = 102 mm iii). Type of Panels = Simplex Control & Relay Panel Note:- The offer of the bidder not conforming to above requirement shall be out rightly rejected. 4.1 E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 5 4.2 ARRANGEMENT OF PANELS: The panels shall be fabricated so that even if the serial of panels is changed no difficulty will be faced in the placement of panels and cabling etc. The sequence of various panels in a panel board at S/Stn. shall be supplied to successful bidder. 5.0 GENERAL TECHNICAL REQUIREMENTS: 5.1 MATERIAL & WORKMANSHIP: All material used in the construction of the panels/relays shall be of the best quality obtainable of their respective kind and whole of the work shall be of the highest class, well finished and of approved design and make. Castings shall be free from blow-holes, flaws, cracks or other defects and shall be smooth grained and of true dimensions and forms. The draw out mechanism in respect of draw out relays should be smooth and convenient so as to give adequate service during their use. 5.2 DEPARTURE FROM THE SPECIFICATION: Should the tenderer wish to depart from the provisions of this specification either on account of manufacturing practice or for any other reasons, he will draw specific attention to the proposed points of departure on the prescribed Performa (enclosed) at annexure-D in his tender and submit such full information, drawings and specifications as will enable the merit of his proposal to be appreciated. In the event of contractor drawings, specification and tables etc. disagreeing with this specification during the execution of the contract this specification shall be held binding unless the departures have been fully recorded as required above. 5.3 PAINTING: All unfinished surfaces of steel panels and frame works shall be sand blasted to remove rust scale, foreign adhering matter & grease. A suitable rust resistance primer shall be applied on the interior & exterior of steel which will be followed by application of an under coat suitable to serve as base for finishing coat. The finishing coat shall be as under: Stove enameled light grey as per shade No.631 of IS: 5/IEC. Exterior Interior stove enameled white. Base frame Stove enameled glossy black. 5.4. TESTING EQUIPMENT AND TESTING FACILITIES ON THE RELAYS: The tenderer shall recommend suitable testing equipment (alongwith quantity) required for field testing of protective schemes and other relays offered against this specification. The actual quantity to be ordered shall be determined by the Purchaser. Also adequate testing facilities should be provided on the relay so as to test them without the necessity of their removal or making any extra connections. The Bidder will clearly indicate the testing procedure to be followed in respect of relays offered. 5.5 The transmission lines shall be either in form of overhead conductor or combination of overhead conductor & underground cable. The tentative transmission line data in respect of 400kV, 220kV, 132kV & 66 kV lines covered in this specification is given at Annexure-C. The standard chart providing the details of per unit values of Z1, Z2 & Z0 on 100 MVA base per 100 km of line for calculating these values for full lengths of lines are enclosed at Annexure-E. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 6 The tentative details of carrier equipment are enclosed at Annexure-F. The suitability of distance scheme offered with reference to the above parameters may be seen. Guaranteed test sheets as per Annexure A shall be submitted by the tenderer. Relevant literature shall be supplied along with the bid for proper appreciation of the offered equipment. 5.6 SUPERVISORY SERVICES: The tenderer may offer supervisory services, panel wise testing & commissioning of 400kV, 220kV, 132 kV, 66 kV & 33 kV panel included in the specification. The tenderer may quote their rates on diem basis category-wise with their terms & conditions. The rates quoted should be valid for at least three years form the date of receipt of equipment by us. 5.7 TRANINING OF PERSONNEL: The contractor will provide free facilities for training the purchaser's technicians /Engineers at his works, design office and HVPNL's site. He will intimate in advance the schedule of completion of designs and manufacture of equipment against the contract (of this specification) or similar equipment to be manufactured at the works so that the purchaser may depute upto 3 technicians & 3 engineers for training at the manufacture assembly, testing, operation and commissioning etc. including testing and commissioning of protective relays, covering training in detecting faults in static relays complete explanation of the schematic wiring and wiring schedule of the relays/scheme together with full understanding regarding the functional modules of the relays/scheme shall be given to the Engineer / technicians. The topics of CTs & PTs towards relay application shall also be kept under the scope of training. The training shall be arranged by the contractor at the works in such a way that the persons under training shall be freely acquainted with the equipment. The engineers / technicians shall also be provided with relay/scheme guides/instruction manuals covering drawings of functional modules of relays/schemes. The period of training will be not exceeding 15 days and all expenses shall be borne by the purchaser. 5.8 GENERAL DESCRIPTION: 5.8.1. SIMPLEX C&R PANEL BOARDS: The panels shall be of `simplex' type & consisting of separate cubicles (for each circuit complete with side covers) made of sheet steel of thickness not less than 10 SWG for the base frame, door frame and front portions of the cubicles and not less than 14 SWG for door, side, top & bottom portion having provision for extension at both ends with internal wiring, illumination with door operated off & on switch. The cubicle shall be suitable for floor mounting with its bottom open. Each cubicle shall be fitted with flush mounted steel hinged door & lock at the back & all the equipments will be mounted in front. The supply shall include suitable grouting bolts and nuts etc. All holes and extension windows shall be blanked and access doors shall be provided with compressible liners at the edges. These simplex panels offered may, therefore, match in following respects:i) Height-wise and depth-wise matching. The control & relay Panels shall be completely dust & vermin proof. The enclosure shall provide degree of protection not less than IP-31 in accordance with IS: 2147 and shall be suitable for tropical use. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 7 NOTE:- For testing purpose a small opening with a cap to close the same is required to be provided to extend the testing leads on front side of the relay panel. 5.9 GENERAL REQUIREMENTS OF RELAYS: All relays shall conform to the requirements of IS:3231/IEC-60255/IEC 61000 or other applicable standards. Relays shall be suitable for flush or semi-flush mounting on the front with connections from the rear. All protective relays shall be in draw out or plug-in type modular cases with proper testing facilities. Necessary test plugs/test handles shall be supplied loose and shall be included in contractor’s scope of supply. All main protective relays shall be numerical type and communication protocol shall be as per IEC 61850. Further, the test levels of EMI as indicated in IEC 61850 shall be applicable to these. For numerical relays, the scope shall include the following: a) Necessary software and hardware to up/down load the data to/from the relay from/to personal computer installed in the substation. However, the supply of PC is not covered under this clause. b) The relay shall have suitable communication facility for future connectivity to SCADA. The relay shall be capable of supporting IEC 61850 protocol (with fibre optical port) and shall be compatible with existing SAS (may be of other make). c) Numerical relays should have clock (Real Time Clock) with inbuilt battery back up having life span of about 10 years. d) Numerical relays shall have adequate no. of output contacts and LEDs to meet the specification / Scheme requirement. All numerical relays shall be supplied preconfigured as per specification / scheme requirements / approved drgs. 5.10 CONTROL SCHEME: 5.10.1 CONTROL SWITCH FOR CIRCUIT BREAKER: 5.10.1.1 It shall be possible to close various circuit breakers from the control room. For this purpose control switches having pistol grip type and of the spring return to neutral position type non lockable handles with alarm cancellation contacts shall be provided for `OP' of ckt. breakers. These shall be so designed that after being operated to `close' a circuit breaker, the operation cannot be repeated until the switch has been turned to a `trip' position making it impossible to perform two `closing' operations consecutively. 5.10.1.2 The rating of the control switch contacts shall be suitable for the duty imposed by the closing & opening mechanism of circuit breakers and shall conform to the recommendations which may be made by the suppliers of circuit breakers. The moving & fixed contacts shall be of such a form & material as will ensure good contact and long service under severe operation duty. All contacts shall be readily renewable. 5.10.1.3 The number of contacts in the control switches shall be decided by the tenderer in view of various requirements of this specification. Two pairs of contacts one normally open and one normally closed shall be kept spare. The total number of contacts proposed to be provided shall be stated in the tender. 5.10.1.4 Safety against inadvertent operation due to light touch in the control switches shall be ensured. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 8 5.11 TRIP CIRCUIT SUPERVISION RELAY: The relay shall be capable of monitoring the healthiness of each trip coil and associated circuit of circuit breaker during "on & off" conditions. The relay shall have time delay on drop-off of min. 200 milli seconds and shall be provided with operation indicator. 400kV & 220 kV circuit breakers being procured are generally equipped with 2 trip coils in each phase/pole of the breaker. For monitoring of trip circuits, both in `open' & `close' position of the circuit breaker, 6 Nos. automatic trip circuit supervision relays (one for each pole and each trip coil) are proposed. For monitoring of entire trip circuit (from control & relay panel terminal to the trip coil of circuit breaker) both in `open' & `close' position of the circuit, 2 No. automatic trip circuit supervision relays are proposed for 132kV,66kV & 33kV panels except 1No. Automatic trip circuit supervision relay is proposed for 33kV Line & Capacitor Panels. 5.12 D.C. FAIL ALARM RELAY: A suitable relay for monitoring the Trip Circuit D.C. wiring of the control and relay panels shall be provided. The relay shall have time delay on drop-off of min. 100 milli seconds and shall be provided with operation indicator. 5.13 VOLTAGE SELECTION SCHEME: The 400kV, 220kV, 132kV, 66kV & 33kV bus PTs exist on all the phases of both the 400kV, 220kV, 132kV, 66kV & 33kV buses at substations having double bus arrangement. Proper voltage selection scheme shall be provided on panels. 5.14 AUTO RECLOSING SCHEME: 5.14.1The protective scheme shall incorporate the necessary equipment to impart auto-reclosing impulse to the circuit breaker when it has tripped either due to the operation of the line protection scheme in the first zone or the accelerated operation of it with the help of carrier equipment. No auto-reclosing impulse shall be transmitted in the event of a fault cleared by the 2nd, 3rd & 4th zone of line protection scheme. Auto-reclosing will also be blocked in case the circuit breaker is tripped manually. 5.14.2The provision of single & three phase auto-reclosing is to be made on 400kV & 220 kV feeder C&R panels. 5.14.3 CHECK SYNCHRONIZING & DEAD LINE CHARGING SCHEME : Check synchronizing relay and dead line charging equipment shall be provided for 400kV & 220 kV feeder C&R panels. The check synchronizing relay shall compare the phase angle & frequency of the `incoming' and `running' supplies and allow the auto-reclose to take place only if the said parameters are within the permissible limits. The dead line charging equipment shall ensure auto-reclosing a circuit breaker on to a `dead' line leaving the checking of synchronism of two supplies to the other end of it. Synchronizing check relay with necessary auxiliary equipments shall be provided which shall permit breakers to close after checking the requirements of synchronizing of incoming and running supply. The phase angle setting shall not exceed 35 degree and have voltage difference setting not exceeding 10%. This relay shall have a response time of less than 200 milliseconds when the two E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 9 system conditions are met within preset limits and with the timer disconnected. The relay shall have a continuously adjustable time setting range of 0.5-3secs. 5.14.4 A four position stay-put non-locking type of auto-reclose selector-switch shall be provided on each of the 400kV & 220 kV feeder C&R panels and shall have the following four positions: a) `Single phase auto’: In this position, the relay shall allow single shot single pole auto reclosing for single line to ground fault. For any other fault, the scheme shall allow all the three poles of the circuit breaker to trip & lock them out. b) `Single & three phase auto’: In this position the relay shall allow single shot single pole auto-reclosing for single line to ground fault and three pole auto-reclosing for other faults such as line to line, double line to ground and three phase faults. c) `Three phase auto' : In this position, the relay shall impart three pole, single shot-reclosing impulse irrespective of the type of fault. d) `Non - auto' : By putting the switch in this position it shall be possible to make the reclosing scheme totally inactive and all the three poles of the circuit breaker shall trip irrespective of the nature of a fault. 5.14.5 The reclosing scheme shall automatically reset after any successful reclosure and shall lock out in case the circuit breaker trips immediately after reclosure. Also the (reclosing) scheme shall not initiate reclosing upon an unsuccessful attempt to manually close circuit breaker. 5.14.6 There shall be clear target indications for successful & un-successful operation. 5.14.7 The auto-reclosing scheme shall have continuously variable dead time setting range of 0.1-2secs for single phase reclosing as well as for three phase reclosing. The scheme shall have continuously variable reclaim time setting range of 5300secs. Note:- The auto reclosing scheme in built with numerical distance protection relays is acceptable provided it is available in both Main -I and Main-II distance protection schemes and meets the above specification. 5.15 PROTECTION SCHEME: Note:-1) The Protection Scheme shall be suitable for 5A current (instead of 1A) in case of 33kV Level. 2) O/C & E/F relay for 11kV T/F Panel has to be provided on LV side i.e. 11kV VCB Panel as per latest VCB Panel specifications of HVPNL. 5.15.1 PROTECTION SCHEME FOR POWER TRANSFORMERS. A) TRANSFORMER DIFFERENTIAL PROTECTION : The relay shall i) Be triple pole numerical type. ii) Have 3 instantaneous high set over-current units. iii) Have second harmonic restraint or other inrush proof feature and be stable under normal over fluxing condition. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 10 iv) v) vi) vii) viii) ix) x) xi) • • • • a) • • • b) • • • • Xii) Have fifth harmonic by pass filter or similar other arrangement to prevent mal-operation of the relay under operating conditions. Be suitable for rated current of 1A and include necessary ICTs for ratio & phase angle correction. Have operating current setting sufficiently low (15% or less) so as to cover practically the whole of the transformer against all types of faults. Have adjustable bias setting range of 20- 50%. Have maximum operating time of 30milli seconds at 5 times the rated current. Be provided with necessary terminals & links to measure current in restraining circuits & in the operating circuits of all the phases under load without making any wiring changes. Cover the lightning arrestors (proposed to be provided very close to the transformer) in the zone of protection. The Scheme shall have in-built features of disturbance recorder and event logger. For disturbance recorder and event logger features, it shall have 8 analog and 16 digital channels (out of which at least 8 shall be external digital inputs). It shall have its own time generator and the clock of the time generator shall be such that the drift is limited to +0.5 seconds/day, if allowed to run without synchronization. Further, it shall have facility to synchronize its time generator from Time Synchronization Equipment having output of following types. Voltage signal: (0-5V continuously settable, with 50m Sec. minimum pulse duration) Potential free contact (Minimum pulse duration of 50 m Sec.) IRIG-B RS232C The recorder shall give alarm in case of absence of synchronizing pulse within specified time. The disturbance recorder shall meet the following requirements: The frequency response shall be 5 Hz on lower side and 250 Hz or better on upper side. Scan rate shall be 1000 Hz/Channel or better. Pre–fault time shall not be less than 100 milliseconds and the post fault time shall not be less than 2 seconds (adjustable). If another system disturbance occurs during one post-fault run time, the recorder shall also be able to record the same. However, the total memory of acquisition unit shall not be less than 5.0 seconds. The event logger shall meet the following requirements: The time resolution shall be 1milli second. Cope with up to 40 changes in any one 10milli seconds interval. The date and time should be printed to the nearest 1milli second followed by a message describing the point which has operated. Events occurring whilst a previous event is in process of being printed are to be stored to await printing. Display resolution of differential/pickup current should be 0.01A (10mA). E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 11 B) NON DIRECTIONAL THREE OVER CURRENT+ ONE EARTH FAULT PROTECTION WITH HIGH SET: The 3 O/C & 1 E/F elements shall be either independent or composite units. The relay shall be single pole inverse definite minimum time lag having definite min. time of 3 secs. at 10 times settings. Over current relay with a setting range of 50%-200% of 1 Amp. supplemented with high set units having a setting range of 500% to 2000% of 1 Amp. shall be provided. Earth fault relay with a setting range of 20%-80% of 1 Amp. supplemented with high set units having a setting range of 200% to 800% of 1 Amp. shall be provided. The relay shall be numerical type. C) RESTRICTED EARTH FAULT PROTECTION: It shall be single pole type for the clearance of earth faults in the protected zone. The relay shall be of high impedance type with a suitable setting to cover at least 90% of the winding & shall have a setting range of 10% to 40% of 1 Amp. or suitable voltage setting. The relay shall be complete with tuned 50 Hz circuit & stabilizing resistance. The tuned circuit will help reject harmonics produced by CT saturation and thus make the relay operative for fundamental frequency only. The stabilizing resistance may appropriately be set to avoid mal-operation under through fault conditions. The relay shall be numerical type. D) 8No. auxiliary relays for various transformer trip functions (Main Buch. Trip, OLTC Oil Temp. Trip, Winding Temperature Trip, Oil Temp Trip, Pressure Relief Trip, Surge Relay Trip and two no. spare) shall be provided. E) OVER FLUXING PROTECTION: An over fluxing detecting relay for the protection of the transformer against overfluxing conditions is proposed to be provided on each of the transformer C&R panels covered by this specification. The relay shall be numerical in design with adjustable setting so as to avoid its operation on momentary system disturbances. The relay shall be suitable for 110 Volts. The relay shall have inverse time characteristics, matching with transformer over-fluxing withstand capability curve. The relay shall provide an alarm with v/f setting range of 100% to 130% of rated values and time delay continuously settable from 0.1 to 6 seconds to draw the operator's attention about the existence of over-fluxing conditions. The tripping time shall be governed by v/f versus time characteristics to cause tripping of transformer controlling circuit breaker if the over-fluxing conditions continue to exist. Note:- The over fluxing relay in built with the numerical differential protection relay is acceptable provided it meets the above specification. F) OVER LOAD ALARM RELAY: It is proposed to provide an over current (i.e. single phase) relay for initiating an alarm during transformer overload condition on the T/F C&R panels. The relay shall have CONTINUOUS VARIABLE setting range of 50-120% of 1Amp. and shall be supplemented by a continuously variable timer of 1 to 10 seconds. The relay shall be arranged to sound an alarm when the transformer exceeds the setting for a given period of time to draw the operator's attention. Note:- The over load alarm relay in built with the numerical differential protection relay or Over current & Earth Fault Protection Relay is acceptable provided it meets the above specification. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 12 5.15.2 PROTECTION SCHEME FOR LINES: A) MAIN- I NON-SWITCHED DISTANCE PROTECTION [FOR 400kV & 220 kV LINES]: The scheme shall:i) be numerical & modular in construction. Relay shall have continuous self monitoring & diagnostic feature. ii) have high speed non-switched distance relays for three phase systems to clear all type of line faults within the set reach of the relay. iii) It should cover at least line sections completely with 20% in hand margin. iv) Measure all type of faults without the need to switch the measuring elements to the faulty phase or phases. Zone switching to extend the reach of the measuring elements is not allowed. The reach of each zone shall be independently & individually adjustable and shall have setting in steps of 1%. Memory circuits with defined characteristics shall be provided in all three phases to ensure correct operation during close-up 3 phase faults and other adverse conditions. v) have a max. operating time up-to trip impulse to circuit breaker (complete protection time including applicable carrier & trip relay time) under source to line impedance ratios (SIR) under all possible combinations of fault with PT being used on the line (with all filters included) at 50% of zone-1 reach : for SIR 0.01-4:as 40 ms at nearest end & 60 ms at other end of line. for SIR 4-15 :as 45 ms at nearest end & 65 ms at other end of line. (carrier transmission time is taken as 20 ms provided that any reduction in carrier time shall be directly reflected as reduction in maximum operating time). vi) have stepped time-distance characteristics and shall have at least four independently variable time graded distance protection zones to cover two adjacent line sections out of which Zone-1, 2 & 3 should be selectable in forward direction and Zone-4 should be selectable in reverse direction. vii) The relay shall have mho or quadrilateral or other suitably shaped characteristics for zone-1, 2, 3 & 4. The relay shall have an adjustable characteristics angle setting range of 30 - 85 degree or shall have independent resistance(R) & reactance(X) setting.. viii) ensure that this long coverage is consistent with limitations imposed by heavy loading and sound phase component of fault current. If the characteristics of starting relays are such that it cannot pick-up because of very low in-feed, under-voltage relays may also be used as supplementary relays. ix) have two independent continuously variable time setting range of 0-3 seconds for zone-2 and 0-5 seconds for zone-3 & 4. x) have a maximum resetting time of less than 35milli-seconds. xi) have facilities for offset features with adjustable 10-20% of Zone-3 setting. xii) have residual compensation variable from 30-150%. xiii) operate instantaneously when circuit breaker is closed to zero-volt 3 phase fault. xiv) be suitable for single & three phase tripping. xv) have a continuous current rating of two times of rated current. The voltage circuit shall be capable of operation at 1.2 times rated voltage. The relay shall also be capable of carrying a high short time current of 80 times rated current without damage for a period of 1 sec. xvi) be selective between internal and external faults. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 13 xvii) have adequate contacts to meet the complete scheme requirements & if required incorporate three separate high speed self reset trip relays for single phase faults and a fourth high speed trip relay for multi-phase faults. xviii) have suitable number of potential free contacts. Multiplication relays, if required, shall be provided for Carrier aided features, Auto reclosing, Event Logger, Disturbance recorder & Data acquisition system. xix) include power swing blocking protection which shall: a1) be of triple pole type a2) have suitable setting range to encircle the distance protection described above. a3) have a continuously adjustable time delay on pick up of setting range 0-2seconds. a4) block tripping during power swing conditions. a5) be of numerical type xx) include fuse failure protection which shall: a1) monitor all the three fuses of PTs/CVTs and associated cable against open circuit. a2) inhibit trip circuits on operation and initiate annunciation. a3) remain inoperative for system earth faults. a4) be of numerical type. xxi) be wired for carrier inter-tripping (PUR/POR) & carrier blocking features selectable at site. xxii) be suitable for 1 Amp. rated CT secondary, 110V (phase to phase ) VT supply and 220 V DC supply. Mode of conversation of DC supply from 220 V DC to the voltage level required for their scheme may be mentioned in detail. Requirement of CTs & VTs for the satisfactory working of the scheme may also be indicated in the tender. xxiii) The relay shall be suitable for series compensated line and must have a current reversal guard feature. xxiv) The Scheme shall have in-built features of broken conductor detection, distance to fault locator, disturbance recorder and event logger. For disturbance recorder and event logger features, it shall have 8 analog and 32 digital channels (out of which at least 16 shall be external digital inputs). It shall have its own time generator and the clock of the time generator shall be such that the drift is limited to +0.5 seconds/day, if allowed to run without synchronization. Further, it shall have facility to synchronize its time generator from Time Synchronization Equipment having output of following types. • Voltage signal: (0-5V continuously settable, with 50m Sec. minimum pulse duration) • Potential free contact (Minimum pulse duration of 50 m Sec.) • IRIG-B • RS232C The recorder shall give alarm in case of absence of synchronizing pulse within specified time. a) The disturbance recorder shall meet the following requirements: • The frequency response shall be 5 Hz on lower side and 250 Hz or better on upper side. • Scan rate shall be 1000 Hz/Channel or better. • Pre–fault time shall not be less than 100 milliseconds and the post fault time shall not be less than 2 seconds (adjustable). If another system E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 14 b) • • • • c) • • • • B) C) disturbance occurs during one post-fault run time, the recorder shall also be able to record the same. However, the total memory of acquisition unit shall not be less than 5.0 seconds. The event logger shall meet the following requirements: The time resolution shall be 1 milli second. Cope with up to 40 changes in any one 10 milli seconds interval. The date and time should be printed to the nearest 1 milli second followed by a message describing the point which has operated. Events occurring whilst a previous event is in process of being printed are to be stored to await printing. Over 100 such events must be stored. The distance to fault locator shall meet the following requirements: Be On-Line type and suitable for breaker operating time of 2 cycles. The display shall be directly in percent of line length or kilometers without requiring any further calculations. Shall have an accuracy of 3% or better for the typical conditions defined for operating timings measurement of distance relays. The above accuracy should not be impaired by presence of remote end infeed, predominant D.C. component in fault current, high fault arc resistance, severe CVT transients. Shall have parallel line mutual zero sequence compensation feature. MAIN -II NON-SWITCHED DISTANCE PROTECTION [FOR 400kV & 220 kV LINES] : For Main-II distance protection, scheme shall be numerical and shall have same features as that of Main-I protection against sub para 5.14.2 (A) above but with different measuring technique. NON-SWITCHED DISTANCE PROTECTION SCHEME [FOR 132kV & 66kV LINES]: The main protection scheme for these lines will be distance scheme working on definite distance measuring principle both for phase & earth faults. The scheme shall:i) be numerical & modular in construction. Relay shall have continuous self monitoring & diagnostic feature. ii) have high speed non-switched distance relays for three phase systems to clear all type of line faults within the set reach of the relay. iii) It should cover at least line sections completely with 20% in hand margin. iv) measure all type of faults without the need to switch the measuring elements to the faulty phase or phases. Zone switching to extend the reach of the measuring elements is not allowed. The reach of each zone shall be independently & individually adjustable and shall have setting in steps of 1%. Memory circuits with defined characteristics shall be provided in all three phases to ensure correct operation during close-up 3 phase faults and other adverse conditions. v) have a max. operating time up-to trip impulse to circuit breaker (complete protection time including trip relay time) under source to line impedance ratios (SIR) :0.01-4 as 50ms under all possible combinations of fault at 50% of zone-1 reach. vi) have stepped time-distance characteristics and shall have at least four independently variable time graded distance protection zones to cover two E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 15 vii) viii) ix) x) xi) xii) xiii) xiv) xv) xvi) xvii) xviii) a1) a2) a3) a4) a5) xix) a1) a2) a3) a4) xx) adjacent line sections out of which Zone-1, 2 & 3 should be selectable in forward direction and Zone-4 should be selectable in reverse direction. The relay shall have mho or quadrilateral or other suitably shaped characteristics for zone-1, 2, 3 & 4. The relay shall have an adjustable characteristics angle setting range of 30 - 85 degree or shall have independent resistance(R) & reactance(X) setting. ensure that this long coverage is consistent with limitations imposed by heavy loading and sound phase component of fault current. If the characteristics of starting relays are such that it cannot pick-up because of very low in-feed, under-voltage relays may also be used as supplementary relays. have two independent continuously variable time setting range of 0-3 seconds for zone-2 and 0-5 seconds for zone-3 & 4. have a maximum resetting time of less than 55milli-seconds (including the resetting time of trip relays). have facilities for offset features with adjustable 10-20% of Zone-3 setting. For correct measurement of earth faults necessary equipment for residual compensation shall be included. It shall have residual compensation variable from 30-150%. operate instantaneously when circuit breaker is closed to zero-volt 3 phase fault. be suitable for three phase tripping. have a continuous current rating of two times of rated current. The voltage circuit shall be capable of operation at 1.2 times rated voltage. The relay shall also be capable of carrying a high short time current of 80 times rated current without damage for a period of 1 sec. have adequate contacts to meet the complete scheme requirements & if required incorporate separate high speed self reset trip relays. have suitable number of potential free contacts. Multiplication relays, if required, shall be provided for Event Logger, Disturbance recorder & Data acquisition system. include power swing blocking protection which shall be of triple pole type have suitable setting range to encircle the distance protection described above. have a continuously adjustable time delay on pick up of setting range 0-2seconds. block tripping during power swing conditions. be of numerical type include fuse failure protection which shall monitor all the three fuses of PTs/CVTs and associated cable against open circuit. inhibit trip circuits on operation and initiate annunciation. remain inoperative for system earth faults. be of numerical type. be suitable for 1 Amp. rated CT secondary, 110V (phase to phase ) VT supply and 220 V DC supply. Mode of conversation of DC supply from 220 V DC to the voltage level required for their scheme may be mentioned in detail. Requirement of CTs & VTs for the satisfactory working of the scheme may also be indicated in the tender. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 16 xxi) D) The Scheme shall have in-built features of broken conductor detection, distance to fault locator, disturbance recorder and event logger. THREE OVER CURRENT+ ONE EARTH FAULT PROTECTION: The 3 O/C & 1 E/F elements shall be either independent or composite units. It shall include VT fuse failure relays for alarm purposes. i) ii) iii) iv) v) vi) i) ii) iii) iv) v) vi) DIRECTIONAL OVER CURRENT RELAY : The relay shall have IDMTL characteristic with a definite minimum time of 3.0 seconds at 10 times setting. have a variable setting range of 50-200% of 1 Amp. have a characteristic angle of 45 degree lead. include operatio indicator. be suitable for 110V VT secondary. be numerical type. DIRECTIONAL EARTH FAULT RELAY: The relay shall be numerical type. have IDMTL characteristic with a definite minimum time of 3.0 seconds at 10 times setting. have a variable setting range of 20-80% of 1 Amp. have a characteristic angle of 45 degree lag. include operation indicator. be suitable for connection across open delta formed by 110/√3 volt rated secondary of VT. E) FEEDER OVER LOAD ALARM RELAY: It is proposed to provide a single pole over current relay for the purpose of monitoring the load flow on feeders to sound an alarm whenever load flow in the line exceeds the setting for a given period of time to draw the operator's attention. The relay shall have CONTINUOUS VARIABLE setting range of 50-200% of 1 Amp. and shall be supplemented by a continuously variable timer of 1 to 10 seconds. F) LINE OVERVOTAGE PROTECTION RELAY FOR 400KV : The relay shall: monitor all three phases have two independent stages and stage- 1 & II relay are acceptable as built in with line distance relays Main I & II both . have an adjustable setting range of 100-170% of rated voltage with an adjustable time delay range of 1 to 60 seconds for the first stage. have an adjustable setting range of 100-170% of rated voltage with a time delay of 100-200 mill seconds for the second stage. be tuned to power frequency provided with separate operation indicators (flag target) for each stage relays. have a drop-off to pick-up ratio greater than 95%. provide separate out-put contacts for each 'Phase' and stage for breaker trip relays, event logger and other scheme requirements. (a) (b) (c) (d) (e) (f) (g) (h) E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 17 Note:- The Feeder over Load Alarm Relay in-built with numerical distance protection relay or Over current & Earth Fault Protection Relay is acceptable provided it meets the above specification. 5.15.3 PROTECTION SCHEME FOR BUS COUPLER: NON DIRECTIONAL THREE OVER CURRENT + ONE EARTH FAULT PROTECTION WITH HIGH SET: The 3 O/C & 1 E/F elements shall be either independent or composite units. The relay shall be single pole inverse definite minimum time lag having definite min. time of 3secs. at 10 times settings. Over current relay with a setting range of 50%-200% of 1Amp. supplemented with high set units having a setting range of 500% to 2000% of 1Amp. shall be provided. Earth fault relay with a setting range of 20%-80% of 1Amp. supplemented with high set units having a setting range of 200% to 800% of 1Amp. shall be provided. The relay shall be numerical type. 5.15.4 i. ii. iii. iv. v. vi. vii. viii. ix. x. xi. xii. xiii xiv. xv. xvi. BUS BAR PROTECTION SCHEME: The duplicate/ redundant (1+1) busbar protection scheme shall be provided for each bus system for 400kV having one & a half breaker scheme. One bus bar protection scheme shall be provided for each main bus for 220kV having double bus arrangement. Bus bar protection scheme shall:be of numerical, low impedance type and modular in construction. The scheme shall be complete in all respects to cater the need of at-least 14 feeders/ bays. have maximum operating time up-to trip impulse to trip relay for all types of faults of 15milli seconds at 5 times setting value. operate selectively for each bus bar. give hundred percent security up-to 40 kA fault level. incorporate check feature. incorporate continuous supervision for CT secondaries against any possible open circuit and if it occurs, shall tender the relevant zone of protection inoperative and initiate an alarm. not give false operation during normal load flow in bus bars. incorporate clear zone indication. be of phase segregated, triple pole type and provide independent zones of protection for each bus. include necessary auxiliary relays for each circuit as required for the scheme. shall be biased differential type and shall have operate and restraint characteristics. be transient free in operation. include continuous DC supply supervision for alarm and trip circuits separately and provide separately non-trip alarm for B/B protection alarm circuit DC fail & B/B protection trip circuit DC fail conditions. shall include necessary multi-tap auxiliary CTs for each bay. include protection 'in/out' switch for each zone. include necessary CT switching relays. Also provide indication to monitor `Operate' status of the CT switching relays with a common push button and shall have CT selection incomplete alarm with adequate time delay when proper CT switching has not taken place. CT switching relay should have adequate contacts for selection of trip bus instead of direct isolator contact. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 18 xvii. xviii. xix bus bar protection scheme should cover the blind zone on account of single CT on B/C circuit. Include high speed tripping relays for each bay. The Scheme shall have in-built features of disturbance recorder and event logger. The disturbance recorder should record the disturbance data baywise (all bays phase and neutral current). 5.15.4.1 LOCAL BREAKER BACK UP PROTECTION SCHEME: The relay shall be provided to take care of stuck breaker conditions. The local breaker back up protection scheme will under such conditions, immediately after the operation of primary / back up protection, transmit the tripping impulse to all the circuit breakers connected to that bus zone of which the circuit breaker forms part. The scheme shall be supplemented with a timer suitable for station DC supply and continuously adjustable setting of .05 to .5 sec. on pick up. The relay shall : i) be triple pole type with a setting range of 20% -80% of rated current. ii) have operating time of not more than 15 m-sec. iii) have a resetting time of not more than 15 m-sec. iv) be of numerical type. v) have a continuous thermal with stand of two times rated current irrespective of setting. Note:- The LBB protection scheme in built with numerical bus bar protection scheme is acceptable provided it meets the above specification. 5.15.5 PROTECTION SCHEME FOR CAPACITOR C&R PANELS: A) NON DIRECTIONAL THREE OVER CURRENT+ ONE EARTH FAULT PROTECTION WITH HIGH SET: The 3 O/C & 1 E/F elements shall be either independent or composite units. The relay shall be single pole inverse definite minimum time lag having definite min. time of 3 secs. at 10 times settings. Over current relay with a setting range of 50%-200% of 1 Amp. supplemented with high set units having a setting range of 500% to 2000% of 1 Amp. shall be provided. Earth fault relay with a setting range of 20%-80% of 1 Amp. supplemented with high set units having a setting range of 200% to 800% of 1 Amp. shall be provided. The relay shall be numerical type. B) TIME DELAY RELAY:A time delay relay must be included with adjustable setting range of 0-5 minutes to provide a time lag before which the bank shall not be again switched on (to avoid closing of the circuit breaker on a trapped charge). C) UNDER VOLTAGE PROTECTION :One inverse time under voltage relay having setting range of 50% to 90% of 110/√3 volt (Phase-to-neutral) shall be provided to disconnect the capacitor bank under low voltage conditions. D) OVER VOLTAGE PROTECTION :One inverse time over voltage relay suitable for operation with 110/√3 volt AC supply (Phase to neutral) with setting range of 100% to 130% shall be provided. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 19 E) UNBALANCE PROTECTION :The unbalance protection shall be provided through current unbalance relay connected to the NCT in neutral of capacitor bank connected in double star. Two such relays, one each for alarm & trip are required. The setting of the relay shall be 10% to 40% of the CT secondary (i.e. 1A for 132 kV& 66kV voltage levels and 5A for 33 kV voltage levels) followed by a time delay through a timer of 0.1 sec. for transient free operation of the protection. The relays shall be numerical type. The relay should not operate for healthy state spill current in neutral. Number of units of failure on which alarm shall come and tripping is initiated, be clearly mentioned for proper setting of the relays. Note:- The under voltage Relay and over voltage relay in-built with numerical unbalance protection relay is acceptable provided it meets the above specification. 5.16 TRIPPING RELAY: High speed tripping relay shall i) be instantaneous ( operating time not to exceed 10 milli-seconds.) ii) reset within 20 milli-seconds. iii) Be 220 Volt DC operated. iv) Have adequate contacts to meet the scheme requirement v) Be provided with operation indicators for each element/coil. 5.17 RELAY SETTINGS : The successful bidder will be responsible for calculating the relay setting of the protection schemes included in the bid and obtain HVPN's M&P wing clearance before their adoption. Any data\ information in regard to the power system required by the supplier for this purpose shall be supplied by HVPN. 5.18 TIME SYNCHRONISATION EQUIPMENT: i) The Time synchronisation equipment shall receive the co-coordinated Universal Time (UTC) transmitted through Geo Positioning Satellite System (GPS) and synchronize equipments to the Indian Standard Time in a substation. ii) Time synchronisation equipment shall include antenna, all special cables and processing equipment etc. iii) It shall be compatible for synchronisation of Event Loggers, Disturbance recorders and SCADA at a substation through individual port or through Ethernet realized through optic fibre bus. iv) The synchronisation equipment shall have 2 micro second accuracy. Equipment shall give real time corresponding to IST (taking into consideration all factors like voltage & temperature variations, propagation & processing delays etc). v) Equipment shall meet the requirement of IEC 60255 for storage & operation. vi) The system shall be able to track the satellites to ensure no interruption of Synchronisation signal. vii) The output signal from each port shall be programmable at site for either one hour, half hour, minute or second pulse, as per requirement. viii) The equipment offered shall have six (6) output ports. Various combinations of output ports shall be selected by the customer, during detailed engineering, from the following: E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 20 • • • • ix) x) xi) Voltage signal: Normally 0-5V with 50milli Seconds minimum pulse duration. In case any other voltage signal required, it shall be decided during detailed engineering. Potential free contact (Minimum pulse duration of 50milli Seconds.) IRIG-B RS232C The equipment shall have a periodic time correction facility of one second periodicity. Time synchronisation equipment shall be suitable to operate from 220V DC as available at Substation. Equipment shall have real time digital display in hour, minute, second (24 hour mode) & have a separate time display unit to be mounted on the top of control panels having display size of approx. 100 mm height. 5.19. SMALL WIRING: a) All wiring shall be of switch board type consisting of stranded /single annealed copper conductor insulated with polyvinyl chloride insulation suitable for 650 volts service and in accordance with IS : 694. b) The wiring of the following circuits shall not be less than the size specified below: CTs, PTs & CVTs circuits : 2.5 mm2 Control, alarm & supervision circuits etc. : 1.5 mm2 c) All wires will be continuous from one terminal to the other and also will have no tee - junction en-route. The connections shall be securely made with the help of connecting lugs to ensure non-oxidation of the bare copper conductor. At the terminal connections, washers shall be interposed between stud type terminals and holding nuts. All holding nuts shall be secured by locking nuts. The connection studs shall project at least 6 mm from the lock nut surface. d) Bus wires shall be fully insulated and run separately. MCB’s shall be provided to enable all the circuits in a panel to be isolated from the bus wire. Wherever practicable, all circuits in which the voltage exceeds 125 volts shall be kept physically separated from the remaining wiring. The function of each circuit shall be marked on the associated terminal boards. e) All wiring diagrams for the control and relay boards shall be drawn as viewed from the back of the cubicle and shall be in accordance with IS:375 or equivalent IEC. Multi core cable tails shall be so bound to its cable that each wire may be traced without difficulty. f) All potential bus wiring, non-trip and trip alarm bus wiring, AC & DC control supply, panel lighting bus wires and such other wiring which runs from panel to panel within a C&R panel board shall be laid out in gutters and shall be suitably screened. In case of `simplex' type C&R boards these common wires will run through bus wire holes. 5.20. TERMINAL BOARDS, TEST BLOCKS & SPARE CONTACTS: a) Terminal block connectors built from cells of moulded dielectric and brass stud inserts shall be provided for terminating the outgoing ends of the panel wiring and the corresponding tail ends of control cables. Insulating barriers shall be provided between adjacent connections. The height of the barriers and the spacing between terminals shall be such as to give adequate E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 21 b) c) d) e) f) protection while allowing easy access to terminals. Provision shall be made on each pillar for holding 10% extra connectors. The terminal blocks shall be suitable for 650 Volts service and for connection with both copper and aluminum wires. Terminal boards shall be mounted in such a manner as to afford easy access to terminations and to enable ferrule numbers to be read without difficulty. Wire ends shall be so connected at the terminals that no wire terminal gets marked due to succeeding connections. Terminal board rows shall be adequately spaced and shall not be less than 100 mm apart so as to permit convenient access to wires and terminations. Labels in the form of engraved plastic plates shall be provided on the fixed portion of terminal boards. No live metal parts shall be exposed at the back of terminal boards. Switch board type back connected test block with contacts shall be provided with links or other devices for shorting terminals of CT leads before interrupting the normal circuit for injection from an external source or for inserting testing instruments in the circuit without causing open circuit of the CT. The potential testing studs shall preferably be housed in narrow recesses of the block, wherever required, shall be placed as close to the equipments as possible. Test blocks shall be of flush mounting pattern and the number of test blocks being provided on each control and relay panel shall be stated in the tender. The purpose of all the relays (including the auxiliary relays) switches, lamps & push buttons etc. is required to be indicated just below the respective equipment through engraving or painting. Spare contacts of relays are required to be brought on T.B's and shall be indicated on the drawings. 5.21. BUS WIRES: The VT, DC, AC, trip alarm , non-trip alarm & DC fail etc. inter panel bus wire terminals shall be brought on Bus T.B's as well as on T.B's so that any panel specified herein can be used separately at the Substation specified in this specification. The said bus wires for the panels specified in case of existing substations shall be matched with the bus wires of the C&R panels already available at site, the drawing for matching purposes for which shall be supplied to the successful bidder. The bus wire terminals shall be indicated on the panel schematic drawings as well. The bus wire diagram shall also be supplied alongwith the schematic drawings for each panel. 5.22. FERRULES: Wire No. shall be indicated on panel schematic and wiring diagrams and accordingly engraved ferrules with the same numbers and letters as indicated in the said diagrams shall be provided on the terminal ends of all wires for easy identification of circuits for inspection and maintenance. Ferrules shall be of strong & flexible insulating material with glossy finish to prevent adhesion. These shall be engraved and marked clearly and shall not be affected by dampness. Ferrule numbering shall be in accordance with IS: 375. The same ferrule number shall not be used on wires in different circuits on a panel. At those points of interconnection between the wiring carried for equipments of different suppliers where a change of number cannot be avoided double ferrules shall be provided on each wire with the appropriate connection diagram of the equipment. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 22 5.23. SPACE HEATERS: Tubular space heaters suitable for connection to the single phase 220 Volts AC supply complete with switches located at convenient positions shall be provided at the bottom of each control and relay panel to prevent condensation of moisture. The watt loss per unit surface of heater shall be low enough to keep surface temperature well below visible heat. 5.24. ILLUMINATION: The C&R panel shall be provided with 220/240 Volts AC interior lighting. The lamp shall be free from hand shadows. A door operated button switch shall be provided in each simplex panel. Each simplex panel shall be provided with one no. illumination lamp with door switch. 5.25. POWER SOCKET : Single phase 240 volt AC, 5-Pin, 5/15A power socket with power on/off switch shall be provided in each simplex panel. 5.26. SAFETY EARTHING: Earthing of current free metallic parts or metallic bodies of the equipment mounted on the switch boards shall be done with bare copper conductor. Copper bus of size 25 mm x 6 mm extending through entire length of a control and relay board shall be provided. The earthing conductor shall be connected by Rose Courtney terminals and clamp junctions. The neutral point of star connected secondary windings of instrument transformers and one corner of the open delta connected LV side of potential transformer, if used shall be similarly earthed with the main earth bar of the switch board earthing system. Multiple earthing of any instrument transformer shall be avoided. An electrostatic discharge point shall be provided in each panel connected to earth bus via 1 Mega Ohm resistor. 5.27. NAME PLATE: An easily accessible engraved or painted panel name plate shall be provided inside each panel. It must include G.A. drawing No., purchase order No., Contractor's reference No., name of S/Stn. as per purchase order and name of circuit. In addition to this, an engraved plate indicating the purchase order no. alongwith name of S/Stn. is required to be affixed on the panel at appropriate height so that it is readable while standing in front of the panel. These are required to be indicated on the G.A. drawings also. An engraved label indicating the purpose of all the relays & switches shall also be provided. 5.28 PANEL DETAILS: The mountings on various 400kV, 220 kV, 132kV, 66kV & 33kV C&R panels against various Substations specified herein shall be as under. The bidders shall give the details of the various panel mountings in the same serial as specified herein as under for the convenience of checking of the same w.r.t. the provision in the specification. Any trip relay, auxiliary relay, timers, contact multiplication relay, ICT, IVT & test block etc. required for the completeness of the scheme shall be added by the Bidder as per scheme requirements and no cost addition on these accounts shall be considered at a later date. The following is the general criteria for the selection of the equipments to be provided in each type of panel. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 23 (A) LINE PROTECTION AND CIRCUIT BREAKER PANEL: Each Line Protection and Circuit breaker panel for transmission lines shall consist of following: S. N. Description 400kV 220kV 1. Main-1 Numerical Distance protection Scheme Main-2 Numerical Distance protection Scheme Over Voltage Protection Scheme Directional back up Over-current and E/F protection scheme Overload alarm scheme 3 phase Trip Relays 1 phase Trip Relays Voltage selection scheme Flag relays, carrier receive relays ,aux Relays, timers etc as per scheme Requirements Under Voltage relay for isolator/earth switch LBB Protection Scheme DC supply Supervision scheme Trip Circuit supervision relays Auto reclose scheme with check synchronising and dead line charging scheme Bay control unit, Ethernet switch etc. as per technical specification enclosed as annex.1 1 Set 1 Set 132 kV 33KV and 66kV 1 Set NIL 1 Set 1 Set NIL NIL 1 Set 1 Set NIL 1 Set NIL 1 Set NIL 1 Set 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. (with high set) 1 Set Nil 6 Nos. 1 set Lot 1 Set Nil 6 Nos. 1 set Lot 1 Set 2 Nos. Nil 1 set Lot 1 Set 1 No. Nil 1 set Lot 2 Nos. 2 Nos. 2 Nos. 2 Nos. 1 set 1 set 6 Nos 1 set 1 set 1 set 6 Nos 1 set NIL 1 set 2 Nos Nil NIL 1 set 1 No. Nil 1 Set 1 Set. 1 Set. 1 Set. (B) TRANSFORMER PROTECTION AND CIRCUIT BREAKER PANEL: Each transformer protection and circuit breaker panel shall consist of the following: S.N. 1. 2. Description HV Side Transformer Differential Protection 1 Set scheme Restricted Earth fault protection scheme 1 Set MV/LV side Nil 1Set @ @ 3. 4. Non-Directional back up O/C and E/F 1 set scheme with high set feature Over Fluxing Protection scheme 1 Set Not applicable autotransformer for 1 set 1 Set $ $ applicable only for 400/220kV Transformer 5. 6. 7. 8. 9. 10. 11. Overload alarm scheme Three phase trip relays Voltage selection scheme Flag relays ,aux .relays, timers etc as per scheme requirement including transformer alarms and trip functions LBB Protection Scheme DC supply Supervision scheme Trip Circuit supervision relays 1 Set 2 nos 1 set Lot Nil 2 nos 1 set Lot 1 set 1 set 6 Nos* 1 set 1 set 6 Nos # *applicable only for 400 kV and 220 kV or 2 No. for 132 kV, 66 kV & 33 kV # applicable only for 220 kV or 2 No. for 132 kV, 66 kV & 33 kV E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 24 S.N. 12. 13. (C) Description HV Side Special Energy Meter (Main) as per Interutility Nil Metering System Specification No. HPD/S95/HPM-461/Vol-II/Prot.(July 2015) Bay Control unit, Ethernet switch etc. as per 1 No. technical specification enclosed as annex.1 MV/LV side 1 No. ** **applicable only for 33kV T/F I/C Panels 1 No. BUS COUPLER PROTECTION AND CIRCUIT BREAKER PANEL Each bus coupler Protection and Circuit Breaker Panel shall consist of following: S.N. Description 220kV 1. 2. 3. 4. 5. 6. Non-Directional Overcurrent and E/F protection scheme with highset 3 phase Trip Relays LBB Protection Scheme DC supply Supervision scheme Trip Circuit supervision relays Flag relays, aux relays, timers, trip relays as per scheme requirements Bay control unit, Ethernet switch etc. as per technical specification enclosed as annex.1 1Set 2 Nos. 1 set 1 set 6 Nos Lot 132/66 / 33kV 1Set 2 Nos. 1 set 1 set 2 Nos Lot 1 Set. 1 Set. 7. (D) S.N. 1. (E) BUS BAR PROTECTION AND CIRCUIT BREAKER PANEL The bus bar Protection and Circuit Breaker Panel shall consist of following: Description Complete bus bar protection scheme as per clause 5.14.4 above 400kV 1Set 220kV 1Set CAPACITOR PROTECTION AND CIRCUIT BREAKER PANEL Each capacitor Protection and circuit breaker panel shall consist of following: S.N. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. Description Neutral Unbalance protection Scheme Over Voltage Protection Scheme Under Voltage Protection Scheme Non Directional Overcurrent and E/F protection scheme with high set Time Delay relay 3 phase Trip Relays Voltage selection scheme Under Voltage relay for isolator/earth switch DC supply Supervision scheme Trip Circuit supervision relays Flag relays, aux relays, timers, trip relays as per scheme requirements Bay control unit, Ethernet switch etc. as per technical specification enclosed as annex.1 Note:- 1) 2) 33 kV 2 set 1 set 1 set 1 set 1 set 1 Nos 1 set 2 Nos 1 set 1 Nos Lot 1 Set. The CT secondary current is 5A for 11kV & 33kV in all panels. O/C & E/F relay for 11kV T/F Panel has to be provided on LV side i.e. 11kV VCB Panel as per latest VCB Panel specifications of HVPNL. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 25 6.0 TESTS : 6.1 TYPE TESTS : The equipment offered should be type tested. Type test report of similar equipment should not be more than seven years old, reckoned from the date of bid opening, in respect of the following tests, carried out in accordance with ISS3231(1965)/equivalent IEC from Govt./ Govt. approved test house & shall be submitted along with bid: a) Insulation tests as per IEC 60255-5 b) High frequency disturbance test as per IEC 60255-22-1 (applicable for all type of numerical relays). c) Fast transient test as per IEC 1000-4, Level-III (not applicable for electromechanical relays) d) Relay characteristics, performance and accuracy test as per IEC 60255. e) Tests for thermal and mechanical requirements as per IEC 60255-6 f) Tests for rated burden as per IEC 60255-6 g) Contact performance test as per IEC 60255-0-20 h) Conformance tests as per IEC 61850 The above tests shall be supplied for distance protection, over current and earth fault protection, restricted earth fault protection, Bus bar protection and transformer differential protection as per the applicability of the relay alongwith bid. The remaining type test reports of above relays & all the type test reports of remaining relays and type test reports of meters shall be submitted by the successful bidder within three months of placement of order. These type test reports will also be from Govt./ Govt. approved test house & should not be more than seven years old, reckoned from the date of placement of order. The failure to do so will be considered as a breach of contract. 6.2 ROUTINE TESTS: All equipment shall be subject to routine tests according to the relevant standards / Quality Assurance Program (QAP) and to such other tests as may be required to ensure that all equipment is satisfactory and in accordance with this specification. The Purchaser reserves the right to witness all the tests, unless dispensed with in writing by the Purchaser. 6.3 ACCEPTANCE TESTS: The Supplier shall give sufficient advance intimation (at least 15 days’ notice for Indian Supplier and 30 days notice for Foreign Supplier) to the Purchaser to enable him to depute his representative for witnessing the tests. Following tests shall be carried out at the manufacturer's works after complete assembly:i) Checking wiring of circuits and their continuity. ii) One minute high voltage test. iii) Insulation resistance of complete wiring, circuit by circuit with all equipment mounted on the panel. iv) Checking the operation of protection schemes. 7.0 7.1 DOCUMENTATION: All drawings shall conform to international standards organization (ISO) `A' series of drawing sheet/Indian Standards Specification IS: 11065. All drawings shall be in E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 26 7.2 ink and suitable for microfilming. If drawings are computerized than all drawings shall be nicely printed. All dimensions and data shall be in S.I.Units. The successful Supplier shall submit four sets of G.A. and schematic drawings for Purchaser's approval within two weeks of the date of placement of order. The Purchaser shall communicate his comments/approval on the drawings to the Supplier within four weeks of the date of receipt of above drawings. The Supplier shall, if necessary, modify the drawings and resubmit four copies of the modified drawings for Purchaser's approval within two weeks from the date of Purchaser's comments. After receipt of Purchaser's approval, the Supplier shall submit 10 prints of final drawings for each Item/Circuit and one good quality soft copy (CD) of the following drawings and instruction manuals :i) Board-wise arrangement drawing (applicable for the panel board at a Substation having more than one panel). ii) G.A. drawing alongwith G.A. legend and foundation details. iii) Schematic drawings alongwith legend & internal wiring details of main relays like transformer differential relay, REF relay, and local breaker back up schemes, distance protection scheme, bus-bar protection scheme, voltage selection scheme etc. iv) Equipment-wise & wire-wise wiring diagrams. Each set of drawings shall be bound separately. The final documents shall be supplied before despatch of equipment. 7.3 The manufacturing of the equipment shall be strictly in accordance with approved drawings and no deviation shall be permitted without the written approval of the Purchaser. All manufacturing & fabrication work in connection with the equipment prior to the approval of the drawings shall be at the Supplier's risk. 7.4 The Supplier shall furnish specified no. of nicely printed and bound volumes of the instruction manuals in English language, prior to the despatch of the equipment. The instruction manual shall contain step by step instructions for all operational & maintenance requirements for all the protective and aux. relays, switches, instruments etc. mounted on the panel and shall include the following aspects. i) Storage for prolonged duration. ii) Unpacking. iii) Erection. iv) Handling at site. v) Pre commissioning tests. vi) Operating procedures. vii) Maintenance procedure. viii) Precautions to be taken during operation & maintenance work. ix) Catalogue numbers of all the components liable to be replaced during the life of the panels. x) Internal wiring diagrams of all the relays. 7.5 Ten (10) copies of instruction manuals for each Circuit/Item shall be supplied free of cost before despatch of equipment. Each set of instruction manuals shall be bound separately. One master set for all the Circuits/Items shall be supplied with in a week of placement of order to the Design Directorate to facilitate the checking and approval of drawings. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 27 7.6 Approval of drawings by Purchaser shall not relieve the Supplier of his responsibility and liability for ensuring correctness & correct interpretation of the latest revision of applicable standards, rules & codes of practices. The equipment shall conform in all respects to high standards of engineering, design, workmanship and latest revisions of relevant standards at the time of ordering. NOTE:- In case the equipment offered by the Supplier does not meet with the requirements of technical specification, the offer of the firm shall not be considered. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 28 ANNEXURE-1 TECHNICAL SPECIFICATION FOR SUBSTATION AUTOMATION SYSTEM E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 29 CONTENTS Clause No. 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0 12.0 13.0 14.0 TITLE GERNERAL SYSTEM DESIGN BAY LEVEL FUNCTIONS SYSTEM HARDWARE SOFTWARE STRUCTURE TESTS SYSTEM OPERATION POWER SUPPLY DOCUMENTATION TRAINING, SUPPORT SERVICES, MAINTENANCE AND SPARES MAINTENANCE GURANTEES REQUIRED SPARES LIST OF EQUIPMENTS Page No. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 30 1.0 GENERAL: The substation automation system shall be offered from a manufacturer who must have designed, manufactured, tested, installed and commissioned substation automation system which must be in satisfactory operation on 220kV system or higher for at least 2 (Two) years as on the date of bid opening. 1.2 The Substation Automation System (SAS) shall be installed to control and monitor all the sub-station equipment from remote control centre (RCC) as well as from local control centre. The SAS shall contain the following main functional parts: i) Bay control Intelligence Electronic Devices (IED s) for control and monitoring. ii) Station Human Machine Interface (HMI) iii) Redundant managed switched Ethernet Local Area Network communication infrastructure with hot standby. iv) Peripheral equipment like printers, display units, key boards, Mouse etc. 1.3 It shall enable local station control via a PC by means of human machine interface (HMI) and control software package, which shall contain an extensive range of supervisory control and data acquisition (SCADA) functions. 1.4 It shall include communication gateways, intelligent electronic devices (IED) for bay control and inter IED communication infrastructure. An architecture drawing for SAS is enclosed at Annexure-G. 1.5 The communication gateways shall facilitate the information flow with remote control centers. The bay level intelligent electronic devices (IED) for protection and control shall provide the direct connection to the switchgear without the need of interposing components and perform control, protection, and monitoring functions. 2.0 SYSTEM DESIGN : 2.1 GENERAL SYSTEM DESIGN: The Substation Automation System (SAS) shall be suitable for operation and monitoring of the complete substation including future extensions as given in Section-Project. The systems shall be of the state-of-the art suitable for operation under electrical environment present in Extra high voltage substations, follow the latest engineering practice, and ensure long-term compatibility requirements and continuity of equipment supply and the safety of the operating staff. The offered SAS shall support remote control and monitoring from Remote Control centers via gateways. The system shall be designed such that personnel without any background knowledge in Microprocessor-based technology are able to operate the system. The operator interface shall be intuitive such that operating personnel shall be able to operate the system easily after having received some basic training. The system shall incorporate the control, monitoring and protection functions specified, self-monitoring, signaling and testing facilities, measuring as well as memory functions, event recording and evaluation of disturbance records. Maintenance, modification or extension of components may not cause a shutdown of the whole substation automation system. Self-monitoring of components, E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 31 modules and communication shall be incorporated to increase the availability and the reliability of the equipment and minimize maintenance. Bidder shall offer the Bay level unit (a bay comprises of one circuit breaker and associated disconnector, earth switches and instrument transformer), bay mimic along with relay and protection panels and PLCC panels (described in other sections of technical specifications) housed in air-conditioned Kiosks suitably located in switchyard and Station HMI in Control Room building for overall optimization in respect of cabling and control room building. 2.2 SYSTEM ARCHITECTURE: The SAS shall be based on a decentralized architecture and on a concept of bayoriented, distributed intelligence. Functions shall be decentralized, object-oriented and located as close as possible to the process. The main process information of the station shall be stored in distributed databases. The typical SAS architecture shall be structured in two levels, i.e. in a station and a bay level. At bay level, the IEDs shall provide all bay level functions regarding control, monitoring and protection, inputs for status indication and outputs for commands. The IEDs should be directly connected to the switchgear without any need for interposition or transducer. Each bay control IED shall be independent from each other and its functioning shall not be affected by any fault occurring in any of the other bay control units of the station. The data exchange between the electronic devices on bay and station level shall take place via the communication infrastructure. This shall be realized using fibreoptic cables, thereby guaranteeing disturbance free communication. The fibre optic cables shall be run in G.I conduit pipes. Data exchange is to be realized using IEC 61850 protocol with a redundant managed switched Ethernet communication infrastructure. The communication shall be made in 1+1 mode, excluding the links between individual bay IEDs to switch, such that failure of one set of fibre shall not affect the normal operation of the SAS. However it shall be alarmed in SAS. Each fibre optic cable shall have four (4) spare fibres. At station level, the entire station shall be controlled and supervised from the station HMI. It shall also be possible to control and monitor the bay from the bay level equipment at all times. Clear control priorities shall prevent operation of a single switch at the same time from more than one of the various control levels, i.e. RCC, station HMI, bay level or apparatus level. The priority shall always be on the lowest enabled control level. The station level contains the station-oriented functions, which cannot be realized at bay level, e.g. alarm list or event list related to the entire substation, gateways for the communication with remote control centers. The GPS time synchronizing signal (as specified in the section relay & protection) for the synchronization of the entire system shall be provided. The SAS shall contain the functional parts as described in Para 1.2 above. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 32 2.3 FUNCTIONAL REQUIREMENTS: The high-voltage apparatus within the station shall be operated from different places: i) Remote control ii) Station HMI. iii) Local Bay controller IED (in the bays) Operation shall be possible by only one operator at a time. The operation shall depend on the conditions of other functions, such as interlocking, synchrocheck, etc. (see description in”Bay level control functions”). 2.3.1 SELECT-BEFORE-EXECUTE: For security reasons the command is always to be given in two stages: selection of the object and command for operation under all mode of operation except emergency operation. Final execution shall take place only when selection and command are actuated. 2.3.2 COMMAND SUPERVISION: BAY/STATION INTERLOCKING AND BLOCKING Software Interlocking is to be provided to ensure that inadvertent incorrect operation of switchgear causing damage and accidents in case of false operation does not take place. In addition to software interlocking hardwired interlocking are to be provided for: a) Bus Earth switch Interlocking b) Transfer Bus interlocking (if applicable) It shall be a simple layout, easy to test and simple to handle when upgrading the station with future bays. For software interlocking the bidder shall describe the scenario while an IED of another bay is switched off or fails. A software interlock override function shall be provided which can be enabled to bypass the interlocking function. 2.3.3 RUN TIME COMMAND CANCELLATION Command execution timer (configurable) must be available for each control level connection. If the control action is not completed within a specified time, the command should get cancelled. 2.3.4 SELF-SUPERVISION Continuous self-supervision function with self-diagnostic feature shall be included. 2.3.5 USER CONFIGURATION The monitoring, controlling and configuration of all input and output logical signals and binary inputs and relay outputs for al built-in functions and signals shall be possible both locally and remotely. It shall also be possible to interconnect and derive input and output signals, logic functions, using built-In functions, complex voltage and currents, additional logics (AND-gates, OR gates and timers). (Multi-activation of these additional functions should be possible). The Functional requirement shall be divided into following levels: a) Bay (a bay comprises of one circuit breaker and associated disconnector, earth switches and instrument transformer) Level Functions. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 33 b) System Level Functions. 3.1 BAY LEVEL FUNCTIONS: In a decentralized architecture the functionality shall be as close to the process as possible. In this respect, the following functions can be allocated at bay level: a) Bay control functions including data collection functionality. b) Bay protection functions Separate IEDs shall be provided for bay control function and bay protection function. 3.1.1 3.1.1.1 BAY CONTROL FUNCTIONS: OVERVIEW: FUNCTIONS: i) Control mode selection ii) Select-before-execute principle iii) Command supervision: a) Interlocking and blocking b) Double command iv) Synchrocheck, voltage selection v) Run Time Command cancellation vi) Transformer tap changer control (for power transformer bays) vii) Operation counters for circuit breakers and pumps viii) Hydraulic pump/ Air compressor control and runtime supervision ix) Operating pressure supervision x) Display of interlocking and blocking xi) Breaker position indication per phase xii) Alarm annunciation xiii) Measurement display xiv) Local HMI (local guided, emergency mode) xv) Interface to the station HMI. xvi) Data storage for at least 200 events xvii) Extension possibilities with additional I/O's inside the unit or via fibre-optic communication and process bus. 3.1.1.2 CONTROL MODE SELECTION: BAY: As soon as the operator receives the operation access at bay level the operation is normally performed via bay control IED. During normal operation bay control unit allows the safe operation of all switching devices via the bay control IED. EMERGENCY OPERATION: It shall be possible to close or open the selected Circuit Breaker with ON or OFF push buttons even during the outage of bay IED. REMOTE MODE: Control authority in this mode is given to a higher level (Remote Control Centre) and the installation can be controlled only remotely. Control operation from lower levels shall not be possible in this operating mode. 3.1.1.3 SYNCHRONISM AND ENERGIZING CHECK: The synchronism and energizing check functions shall be bay-oriented and distributed to the bay control and/or protection devices. These features are: a) Settable voltage, phase angle, and frequency difference. b) Energizing for dead line - live bus, live line - dead bus or dead line – dead bus with no synchrocheck function. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 34 c) Synchronizing between live line and live bus with synchrocheck function. 3.1.1.4 VOLTAGE SELECTION: The voltages relevant for the Synchrocheck functions are dependent on the station topology, i.e. on the positions of the circuit breakers and/or the isolators. The correct voltage for synchronizing and energizing is derived from the auxiliary switches of the circuit breakers, the isolator, and earthing switch and shall be selected automatically by the bay control and protection IEDs. 3.1.1.5 TRANSFORMER TAP CHANGER CONTROL: Raise and lower operation of OLTC taps of transformer shall be facilitated through Bay controller IED. 3.1.2 BAY PROTECTION FUNCTIONS: 3.1.2.1 GENERAL: The protection functions are independent of bay control function. The protection shall be provided by separate protection IEDs (numerical relays) and other protection devices as per section Relay & Protection. IEDs, shall be connected to the communication infrastructure for data sharing and meet the real-time communication requirements for automatic functions. The data presentation and the configuration of the various IEDs shall be compatible with the overall system communication and data exchange requirements. 3.1.2.2 EVENT AND DISTURBANCE RECORDING FUNCTION: Each IED should contain an event recorder capable of storing at least 200 timetagged events. This shall give alarm if 70% memory is full. The disturbance recorder function shall be as per detailed in the technical specification of C&R Panels. 3.2 3.2.1 SYSTEM LEVEL FUNCTIONS: STATUS SUPERVISION: The position of each switchgear, e.g. circuit breaker, isolator, earthing switch, transformer tap changer etc., shall be supervised continuously. Every detected change of position shall be immediately displayed in the single-line diagram on the station HMI screen, recorded in the event list and a hard copy printout shall be produced. Alarms shall be initiated in the case of spontaneous position changes. The switchgear positions shall be indicated by two auxiliary switches, normally closed (NC) and normally open (NO), which shall give ambivalent signals. An alarm shall be initiated if these position indications are inconsistent or if the time required for operating mechanism to change position exceeds a predefined limit. The SAS shall also monitor the status of sub-station auxiliaries. The status and control of auxiliaries shall be done through separate one or more IED and all alarm and analogue values shall be monitored and recoded through this IED. 3.2.2 MEASUREMENTS: Analogue inputs for voltage and current measurements shall be connected directly to the voltage transformers (VT) and the current transformers (CT) without intermediate transducers. The values of active power (W), reactive power (VAR), frequency (Hz), and the rms values for voltage (U) and current (I) shall be calculated. The measured values shall be displayed locally on the station HMI and in the control centre. The abnormal values must be discarded. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 35 The analogue values shall be updated every 2 seconds. Threshold limit values shall be selectable for alarm indications. Suitable no. of Transducers shall be provided to facilitate the flow of 4-20mA Analogue signals as per Annexure–II from the bay level equipments (i.e circuit breaker, AC Kiosks, Transformers, etc.) to its respective C&R Panel BCU and Station level equipments (i.e. ACDB, DCDB, Battery Chargers, L.T. Transformer, Generator, etc.) to station auxiliary BCU, as per its respective approved drawings, for remote control & supervision at Station HMI’s thereof by the successful SCADA supplier. 3.2.3 EVENT AND ALARM HANDLING: Events and alarms are generated either by the switchgear, by the control IEDs, or by the station level unit. They shall be recorded in an event list in the station HMI. Alarms shall be recorded in a separate alarm list and appear on the screen. All, or a freely selectable group of events and alarms shall also be printed out on an event printer. The alarms and events shall be time-tagged with a time resolution of 1 ms. 3.2.4 STATION HMI: 3.2.4.1 SUBSTATION HMI OPERATION: On the HMI the object has to be selected first. In case of a blocking or interlocking conditions are not met, the selection shall not be possible and an appropriate alarm annunciation shall occur. If a selection is valid the position indication will show the possible direction, and the appropriate control execution button shall be pressed in order to close or open the corresponding object. Control operation from other places (e.g. REMOTE) shall not be possible in this operating mode. 3.2.4.2 PRESENTATION AND DIALOGUES: GENERAL: The operator station HMI shall be a redundant with hot standby and shall provide basic functions for supervision and control of the substation. The operator shall give commands to the switchgear on the screen via mouse clicks or keyboard commands. The HMI shall give the operator access to alarms and events displayed on the screen. Aside from these lists on the screen, there shall be a printout of alarms or events in an event log. An acoustic alarm shall indicate abnormalities, and all unacknowledged alarms shall be accessible from any screen selected by the operator. 3.2.4.3 The following standard pictures shall be available from the HMI: a) Single-line diagram showing the switchgear status and measured values b) Control dialogues with interlocking and blocking details. This control dialogue shall tell the operator whether the device operation is permitted or blocked. a) Measurement dialogues b) Alarm list, station / bay-oriented c) Event list, station / bay-oriented d) System status HMI DESIGN PRINCIPLES: E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 36 Consistent design principles shall be adopted with the HMI concerning labels, colors, dialogues and fonts. Non-valid selections shall be dimmed out. The object status shall be indicated using different status colors for: a) Selected object under command b) Selected on the screen c) Not updated, obsolete values, not in use or not sampled d) Alarm or faulty state e) Warning or blocked f) Update blocked or manually updated g) Control blocked h) Normal state 3.2.4.4 PROCESS STATUS DISPLAYS AND COMMAND PROCEDURES: The process status of the substation in terms of actual values of currents, voltages, frequency, active and reactive powers as well as the positions of circuit breakers, isolators and transformer tap-changers shall be displayed in the station single-line diagram. In order to ensure a high degree of security against undesired operation, a "selectbefore-execute" command procedure shall be provided. After the "selection" of a switch, the operator shall be able to recognize the selected device on the screen, and all other switchgear shall be blocked. As communication between control centre and device to be controlled is established, the operator shall be prompted to confirm the control action and only then final execute command shall be accepted. After the “execution” of the command the operated switching symbol shall flash until the switch has reached its new position. The operator shall be in a position to execute a command only, if the switch is not blocked and if no interlocking condition is going to be violated. The interlocking statements shall be checked by the interlocking scheme implemented at bay and station level. After command execution the operator shall receive a confirmation that the new switching position has been reached or an indication that the switching procedure was unsuccessful with the indication of the reason for non-functioning. 3.2.4.5 SYSTEM SUPERVISION & DISPLAY: The SAS system shall be comprehensively self-monitored such that faults are immediately indicated to the operator, possibly before they develop into serious situations. Such faults are recorded as a faulty status in a system supervision display. This display shall cover the status of the entire substation including all switchgear, IEDs, communication infrastructure and remote communication links, and printers at the station level, etc. 3.2.4.6 EVENT LIST: The event list shall contain events that are important for the control and monitoring of the substation. The event and associated time (with1 ms resolution) of its occurrence has to be displayed for each event. The operator shall be able to call up the chronological event list on the monitor at any time for the whole substation or sections of it. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 37 A printout of each display shall be possible on the hard copy printer. The events shall be registered in a chronological event list in which the type of event and its time of occurrence are specified. It shall be possible to store all events in the computer for at least one month. The information shall be obtainable also from a printed event log. The chronological event list shall contain: a) Position changes of circuit breakers, isolators and earthing devices b) Indication of protective relay operations c) Fault signals from the switchgear d) Indication when analogue measured values exceed upper and lower limits. Suitable provision shall be made in the system to define two level of alarm on either side of the value or which shall be user defined for each measure and. i) Loss of communication. Filters for selection of a certain type or group of events shall be available. The filters shall be designed to enable viewing of events grouped per: a) b) c) d) e) 3.2.4.7 Date and time Bay Device Function e.g. trips, protection operations etc. Alarm class. ALARM LIST: Faults and errors occurring in the substation shall be listed in an alarm list and shall be immediately transmitted to the control centre. The alarm list shall substitute a conventional alarm tableau, and shall constitute an evaluation of all station alarms. It shall contain unacknowledged alarms and persisting faults. The date and time of occurrence shall be indicated. The alarm list shall consist of a summary display of the present alarm situation. Each alarm shall be reported on one line that contains: a) b) c) d) The date and time of the alarm The name of the alarming object A descriptive text The acknowledgement state. Whenever an alarm condition occurs, the alarm condition must be shown on the alarm list and must be displayed in a flashing state along with an audible alarm. After acknowledgement of the alarm, it should appear in a steady (i.e. not flashing) state and the audible alarm shall stop. The alarm should disappear only if the alarm condition has physically cleared and the operator has reset the alarm with a reset command. The state of the alarms shall be shown in the alarm list (Unacknowledged and persistent, Unacknowledged and cleared, Acknowledged and persistent). Filters for selection of a certain type or group of alarms shall be available as for events. 3.2.4.8 OBJECT PICTURE: E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 38 When selecting an object such as a circuit breaker or isolator in the single-line diagram, the associated bay picture shall be presented first. In the selected object picture, all attributes like a) Type of blocking b) Authority c) Local / remote control d) RSCC / SAS control e) Errors f) Etc., Shall be displayed. 3.2.4.9 CONTROL DIALOGUES: The operator shall give commands to the system by means of mouse click located on the single-line diagram. It shall also be possible to use the keyboard for command activation. Data entry is performed with the keyboard. Dedicated control dialogues for controlling at least the following devices shall be available: a) Breaker and disconnector b) Transformer tap-changer 3.2.5 USER-AUTHORITYV LEVELS: It shall be possible to restrict activation of the process pictures of each object (bays, apparatus...) within a certain user authorization group. Each user shall then be given access rights to each group of objects, e.g.: a) Display only b) Normal operation (e.g. open/close of switchgear) c) Restricted operation (e.g. by-passed interlocking) d) System administrator For maintenance and engineering purposes of the station HMI, the following authorization levels shall be available: (i) No engineering allowed (ii) Engineering/configuration allowed (iii) Entire system management allowed The access rights shall be defined by passwords assigned during the log-in procedure. Only the system administrator shall be able to add/remove users and change access rights. 3.2.6 REPORTS: The reports shall provide time-related follow-ups of measured and calculated values. The data displayed shall comprise: A. • • • • Trend reports: Day (mean, peak) Month (mean, peak) Semi-annual (mean, peak) Year (mean, peak) • • • • Historical reports of selected analogue Values: Day (at 15 minutes interval) Week Month Year B. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 39 It shall be possible to select displayed values from the database in the process display on-line. Scrolling between e.g. days shall be possible. Unsure values shall be indicated. It shall be possible to select the time period for which the specific data are kept in the memory. Following printouts shall be available from the printer and shall be printed on demand: i. ii. iii. iv. v. vi. vii. viii. 3.2.7 Daily voltage and frequency curves depicting time on X-axis and the appropriate parameters on the Y-axis. The time duration of the curve is 24 hours. Weekly trend curves for real and derived analogue values. Printouts of the maximum and minimum values and frequency of occurrence and duration of maximum and minimum values for each analogue parameter for each circuit in 24 hr period. Provision shall be made for logging information about breaker status like number of operation with date and time indications. Equipment operation details shift wise and during 24 hours. Printout on adjustable time period as well as on demand for MW, MVAR, Current, Voltage on each feeder and transformer as well as Tap Positions, temperature and status of pumps and fans for transformers. Printout on adjustable time period as well as on demand system frequency and average frequency. Reports in specified formats which shall be handed over to successful bidder. Trend display (historical data) It shall be possible to illustrate all types of process data as trends - input and output data, binary and analogue data. The trends shall be displayed in graphical form as column or curve diagrams with a maximum of 10 trends per screen. Adjustable time span and scaling ranges must be provided. It shall be possible to change the type of value logging (direct, mean, sum, or difference) on-line in the window. It shall also be possible to change the update intervals on-line in the picture as well as the selection of threshold values for alarming purposes. 3.2.8 Automatic disturbance file transfer All recorded data from the IEDs with integrated disturbance recorder as well as dedicated disturbance recording systems shall be automatically uploaded (event triggered or once per day) to a dedicated computer and be stored on the hard disc. 3.2.9 Disturbance analysis The PC-based work station shall have necessary software to evaluate all the required information for proper fault analysis. 3.2.10. IED Parameter Setting It shall be possible to access al protection and control IEDs for reading the parameters (settings) from the station HMI or from a dedicated monitoring computer. The setting of parameters or the activation of parameter sets shall only be allowed after entering a password. 3.2.11 Automatic sequences The available automatic sequences in the system should be listed and described, (e.g. sequences related to the bus transfer). It must be possible to initiate pre- E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 40 defined automatic sequences by the operator and also define new automatic sequences. 3.3 3.3.1 Gateway Communication Interface (a) (b) The Substation Automation System shall have the capability to support simultaneous communications with multiple independent remote master stations. The Substation Automation System shall have communication ports as follows:Two ports for Remote Control Centre Two ports for Regional System Coordination Centre (RSCC) The communication interface to the SAS shall allow scanning and control of defined points within the substation automation system independently for each control centre. The substation automation system shall simultaneously respond to independent scans and commands from employer's control centres (RCC & RSCC). The substation automation system shall support the use of a different communication data exchange rate (bits per second), scanning cycle, and/or communication protocol to each remote control centre. Also, each control centre’s data scan and control commands may be different for different data points within the substation automation system's database. 3.3.2 Remote Control Centre Communication Interface Employer will supply communication channels between the Substation Automation System and the remote control centre. The communication channels provided by Employer will consist either of power line carrier, microwave, optical fibre, VSAT or leased line, the details of which shall be provided during detailed Engineering. 3.3.3 Interface Equipment: The Contractor shall provide interface equipment for communicating between Substation Automation system and Remote control centre and between Substation Automation system and Regional System Coordination Centre (RSCC). However, the communication channels available for this purpose are specified in section project. In case of PLCC communication any modem supplied shall not require manual equalization and shall include self-test features such as manual mark/space keying, analogue loop-back, and digital loop-back. The modems shall provide for convenient adjustment of output level and receive sensitivity. The modem (for both ends) should be standalone type complete in all respects including power supply to interface the SAS with communication channel. The configuration of tones and speed shall be programmable and maintained in non-volatile memory in the modem. All necessary hardware and software shall also be in the scope of bidder except the communication link along with communication equipment between substation control room and Remote Control Centre. 3.3.4 Communication Protocol The communication protocol for gateways to control centre must be open protocol and shall support both the telecommunication protocols i.e. IEC 60870-5-101 (Serial) & IEC 60870 – 5 – 104 (TCP/IP) and IEC 61850 for all levels of communication for sub-station automation such as Bay to station HMI, gateways to remote stations etc. 4.0 System Hardware: E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 41 4.1 Redundant Station HMI, HMI View Node, Remote HMI and Disturbance Recorder Work station: The contractor shall provide redundant station HMI in hot standby mode. It shall be capable to perform all functions for entire substation including future requirements as indicated in the SLD. It shall use industrial grade components. Processor and RAM shall be selected in such a manner that during normal operation not more than 30% capacity of processing and memory are used. Supplier shall demonstrate these features. 1. 2. 3. The capacity of hard disk shall be selected such that the following requirement should occupy less than 50% of disk space: Storage of al analogue data (at 15 Minutes interval) and digital data including alarm, event and trend data for thirty (30) days, Storage of all necessary software, 20GB space for OWNER'S use. Supplier shall demonstrate that the capacity of hard disk is sufficient to meet the above requirement. 4.1.1 HMI (Human Machine Interface) The VDU shall show overview diagrams (Single Line Diagrams) and complete details of the switchgear with a color display. Al event and alarm annunciation shall be selectable in the form of lists. Operation shall be by a user friendly function keyboard and a cursor positioning device. The user interface shall be based on WINDOWS concepts with graphics & facility for panning, scrolling, zooming, decluttering etc. 4.1.2 Visual Display Units/TFT's (Thin Film Technology) The contractor shall provide three display units, one for station HMI, one for redundant HMI and one for DR work station. These shall have high resolution and reflection protected picture screen. High stability of the picture geometry shall be ensured. The screen shall be at least 21" diagonally in size and capable of color graphic displays. The display shall accommodate resolution of 1280 X 1024 pixels. The HMI shall be able to switch the key board and cursor positioning device, as unit among all the monitors at a consol vis push button or other controls. 4.1.3 Printer It shall be robust & suitable for operation with a minimum of 132 characters per line. The printing operation shall be quiet with a noise level of less than 45 dB suitable for location in the control room. Printer shall accept and print all ASCII characters via master control computer unit interface. The printer shall have in built testing facility. Failure of the printer shall be indicated in the Station HMI. The printer shall have an off line mode selector switch to enable safe maintenance. The maintenance should be simple with provisions for ease of change of print head, ribbon changing, paper insertion etc. All printers mounted in the control room shall be provided with a separate printer enclosure each. The enclosure shall be designed to permit full enclosure of the printers at a convenient level. Plexiglas windows shall be used to provide visual inspection of the printers and ease of reading. The printer enclosures shall be E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 42 designed to protect the printers from accidental external contact & each should be removable from hinges at the back and shall be provided with lock at the front. All reports and graphics prints shall be printed on laser printer. One dot matrix printer shall be exclusively used for hourly log printing. All printers shall be continuously online. 4.1.4 Mass Storage Unit The mass storage unit shall be built-in to the Station HMI. All operational measured values and indications shall be stored in a mass-storage unit of CD-ROM / DVDROM with 700 MB or more capacity. The unit should support at least Read (48X), Write (24X), and Re-Write (10X) operations, with Multi-Session capability. It should support ISO9660, Rockridge and Joliet File systems. It should support formatting and use under the operating system provided for Station HMI. The monthly back up of data shall be taken on disc. The facility of back up of data shall be inherent in the software. 4.1.5 Switched Ethernet Communication Infrastructure: The bidder shall provide the redundant switched optical Ethernet communication infrastructure for SAS. The bidder shall keep provision of 100% spare capacity for employer use. One switch shall be provided to connect all IEDs in one diameter of each 765 and 400kV yard and for two adjacent bays of 220kV, 132kV, 66kV & 33kV yard to communication infrastructure. 4.2 Bay Level Unit The bay unit shall use industrial grade components. The bay level unit, based on microprocessor technology, shall use numerical techniques for the calculation and evaluation of externally input analogue signals. They shall incorporate select-beforeoperate control principles as safety measures for operation via the HMI. They shall perform all bay related functions, such as control commands, bay interlocking, data acquisition, data storage, event recording and shall provide inputs for status indication and outputs for commands. They shall be directly connected to the switchgear. The bay unit shall acquire and process all data for the bay (Equipment status, fault indications, measured values, alarms etc.) and transmit these to the other devices in sub-station automation system. In addition, this shall receive the operation commands from station HMI and control centre. The bay unit shall have the capability to store all the data for at least 24 hours. One no. Bay level unit shall be provided for supervision and control of each 765kV, 400kV, 220kV, 132kV, 66kV and 33kV bay (a bay comprises of one circuit breaker and associated disconnector, earth switches and instrument transformer). The Bay level unit shall be equipped with analogue and binary inputs/outputs for handling the control, status monitoring and analogue measurement functions. All bay level interlocks are to be incorporated in the Bay level unit so as to permit control from the Bay level unit/ local bay mimic panel, with all bay interlocks in place, during maintenance and commissioning or in case of contingencies when the Station HMI is out of service. The Bay level unit shall meet the requirements for withstanding electromagnetic interference according to relevant parts of IEC 61850. Failure of any single component within the equipment shall neither cause unwanted operation nor lead to a complete system breakdown. 4.2.1 Input/Output (I/O) modules The I/O modules shall form a part of the bay level unit and shall provide coupling to the substation equipment. The I/O modules shall acquire all switchgear information E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 43 (i.e. data coming directly from the switchgear or from switchgear interlocking devices) and transmit commands for operation of the switchgear. The measured values of voltage and current shall be from the secondary of instrument transformers. The digital inputs shall be acquired by exception with 1 ms resolution. Contact bouncing in digital inputs shall not be assumed as change of state. 4.3 Air-conditioned kiosk (applicable only for 400 kV and 220 kV substations) The Air-conditioned Kiosk offered shall house Bay level units, bay mimic, relay and protection panels, PLCC panels etc. one each for a diameter in 765 & 400kVsub-stations, for two adjacent bays in 220kV, 132kV & 66kV Level, for four adjacent bays in 33kV level of 220/33kV T/F and all 33kV bays of 132/33kV T/F starting from Bay No.1 as per GELO drg. In case of incomplete diameter the kiosk shall have necessary space for accommodating the future bay IEDs. The layout of equipment/panel shall be subject to Owner’s approval. The Kiosk shall be provided with fire alarm system with at least two detectors and it shall be wired to SAS. The detailed requirement of Kiosk is enclosed as Annexure-H The air conditioner provided in Kiosk shall be controlled and monitored from substation automation system. One additional Kiosk for each voltage level, if required, shall be provided for housing bus bar protection panels at suitable location in switchyard. Note: For 132 kV and 66 kV substations the control and relay panels shall be housed in the control room building itself. 4.4 Extendibility in future Offered substation automation system shall be suitable for extension in future for additional bays. During such requirement, all the drawings and configurations, alarm/event list etc. displayed shall be designed in such a manner that its extension shall be easily performed by the employer. During such event, normal operation of the existing substation shall be unaffected and system shall not require a shutdown. The contractor shall provide all necessary software tools along with source codes to perform addition of bays in future and complete integration with SAS by the user. These software tools shall be able to configure IED, add additional analogue variable, alarm list, event list, modify interlocking logics etc. for additional bays/equipment which shall be added in future. 5.0 Software structure The software package shall be structured according to the SAS architecture and strictly divided in various levels. Necessary firewall shall be provided at suitable points in software to protect the system. An extension of the station shall be possible with lowest possible efforts. Maintenance, modification or an extension of components of any feeder may not force a shut-down of the parts of the system which are not affected by the system adaptation. 5.1.1 5.1.1.1 Station level software Human-machine interface (HMI) The base HMI software package for the operator station shall include the main SAS functions and it shall be independent of project specific hardware version and operating system. It shall further include tools for picture editing, engineering and system configuration. The system shall be easy to use, to maintain, and to adapt according to specific user requirements. Systems shall contain a library with standard functions and applications. 5.1.2 Bay level software E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 44 5.1.1.1 System software The system software shall be structured in various levels. This software shall be placed in a non-volatile memory. The lowest level shall assure system performance and contain basic functions, which shall not be accessible by the application and maintenance engineer for modifications. The system shall support the generation of typical control macros and a process database for user specific data storage. In case of restoration of links after failure, the software along with hardware shall be capable of automatically synchronizing with the remaining system without any manual interface. This shall be demonstrated by contractor during integrated system test. 5.1.1.2 Application software In order to ensure robust quality and reliable software functions, the main part of the application software shall consist of standard software modules built as functional block elements. The functional blocks shall be documented and thoroughly tested. They form part of a library. The application software within the control/protection devices shall be programmed in a functional block language. 5.1.1.3 Network Management System: The contractor shall provide network management system software for following management functions: a. Configuration Management b. Fault Management c. Performance Monitoring This system shall be used for management of communication devices and other IEDs in the system. This NMS can be loaded in DR work-station and shall be easy to use, user friendly and menu based. The NMS shall monitor all the devices in the SAS and report if there is any fault in the monitored devices. The NMS shall (a) (b) (c) (d) Maintain performance, resource usage, and error statistics for all managed links and devices and present this information via displays, periodic reports and on demand reports. Maintain a graphical display of SAS connectivity and device status. Issue alarms when error conditions occurs Provide facility to add and delete addresses and links 5.1.1.4 The contractor shall provide each software in two copies in CD to load into the system in case of any problem related with Hardware/Communication etc. 6.0 TESTS The substation automation system offered by the bidder shall be subjected to following tests to establish compliance with IEC 61850 for EHV sub-station equipment installed in sheltered area in the outdoor switchyard and specified ambient conditions: 6.1 6.1.1 Type Tests: Control IEDs and Communication Equipment: Power Input: i. Auxiliary Voltage ii. Current Circuits iii. Voltage Circuits iv. Indications a. b. Accuracy Tests: E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 45 i. Operational Measured Values ii. Currents iii. Voltages iv. Time resolution c. Insulation Tests: i. Dielectric Tests ii. Impulse Voltage withstand Test d. Influencing Quantities i. Limits of operation ii. Permissible ripples iii. Interruption of input voltage e. 6.2 Electromagnetic Compatibility Test: i. 1 MHZ. burst disturbance test ii. Electrostatic Discharge Test iii. Radiated Electromagnetic Field Disturbance Test iv. Electrical Fast transient Disturbance Test v. Conducted Disturbances Tests induced by Radio Frequency Field vi. Magnetic Field Test vii. Emission (Radio interference level) Test. viii. Conducted Interference Test f. Function Tests: i. Indication ii. Commands iii. Measured value Acquisition iv. Display Indications g. Environmental tests: i. Cold Temperature ii. Dry Heat iii. Wet heat iv. Humidity (Damp heat Cycle) v. Vibration vi. Bump vii. Shock Factory Acceptance Tests: The supplier shall submit a test specification for factory acceptance test (FAT) and commissioning tests of the station automation system for approval. For the individual bay level IED’s applicable type test certificates shall be submitted. The manufacturing phase of the SAS shall be concluded by the factory acceptance test (FAT). The purpose is to ensure that the Contractor has interpreted the specified requirements correctly and that the FAT includes checking to the degree required by the user. The general philosophy shall be to deliver a system to site only after it has been thoroughly tested and its specified performance has been verified, as far as site conditions can be simulated in a test lab. If the FAT comprises only a certain portion of the system for practical reason, it has to be assured that this test configuration contains at least one unit of each and every type of equipment incorporated in the delivered system. If the complete system consists of parts from various suppliers or some parts are already installed on site, the FAT shall be limited to sub-system tests. In such a E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 46 case, the complete system test shall be performed on site together with the site acceptance test (SAT). 6.3 Integrated Testing; The integrated system tests shall be performed as detailed in subsequent clauses as per following configuration: (i) Redundant Station HMI, DR work station, two switches (i.e. for two diameters) along with all IEDs for the Dia and printers. All other switches for complete sub-station as detailed in section project shall be simulated as needed. 6.3.1 Hardware Integration Tests: The hardware integration test shall be performed on the specified systems to be used for Factory tests when the hardware has been installed in the factory. The operation of each item shall be verified as an integral part of system. Applicable hardware diagnostics shall be used to verify that each hardware component is completely operational and assembled into a configuration capable of supporting software integration and factory testing of the system. The equipment expansion capability shall also be verified during the hardware integration tests. 6.3.2 Integrated System Tests: Integrated system tests shall verify the stability of the hardware and the software. During the tests all functions shall run concurrently and all equipment shall operate a continuous 100 Hours period. The integrated system test shall ensure the SAS is free of improper interactions between software and hardware while the system is operating as a whole. 6.4 Field Tests: The field tests shall completely verify all the features of SAS hardware and software. 7.0 7.1 7.1.1 SYSTEM OPERATION Substation Operation NORMALOPERATION Operation of the system by the operator from the remote RCC or at the substation shall take place via industry standard HMI (Human Machine interface) subsystem consisting of graphic color VDU, a standard keyboard and a cursor positioning device (mouse). i) ii) iii) The colored screen shall be divided into 3 fields: Message field with display of present time and date Display field for single line diagrams Navigation bar with alarm/condition indication For display of alarm annunciation, lists of events etc a separate HMI View node shall be provided. All operations shall be performed with mouse and/or a minimum number of function keys and cursor keys. The function keys shall have different meanings depending on the operation. The operator shall see the relevant meanings as function tests displayed in the command field (i.e. operator prompting). For control actions, the switchgear (i.e. circuit breaker etc.) requested shall be selectable on the display by means of the cursor keys. The switching element selected shall then appear on the background that shall be flashing in a different color. The operator prompting shall distinguish between:- E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 47 - Prompting of indications e.g. fault indications in the switchgear, and - prompting of operational sequences e.g. execution of switching operations The summary information displayed in the message field shall give a rapid display of alarm/message of the system in which a fault has occurred and alarm annunciation lists in which the fault is described more fully. Each operational sequence shall be divided into single operation steps which are initiated by means of the function keys/WINDOW command by mouse. Operator prompting shall be designed in such a manner that only the permissible keys are available in the command field related to the specific operation step. Only those switching elements shall be accessed for which control actions are possible. If the operation step is rejected by the system, the operator prompting shall be supported by additional comments in the message field. The operation status shall be reset to the corresponding preceding step in the operation sequence by pressing one of the function keys. All operations shall be verified. Incorrect operations shall be indicated by comments in the message field and must not be executed. The offer shall include a comprehensive description of the system. The above operation shall also be possible via WINDOWS based system by mouse. 8.0 POWER SUPPLY Power for the substation automation system shall be derived from substation 220V DC system. Inverter of suitable capacity shall be provided for station HMI and its peripheral devices e.g. printer etc. In the event of Power failure, necessary safeguard software shall be built for proper shutdown and restart. 9.0 DOCUMENTATION The following documents shall be submitted for employer’s approval during detailed engineering: (a) (b) (c) (d) (e) System Architecture Drawing Hardware Specification Sizing Calculations of various components Response Time Calculation Functional Design Document The following documentation to be provided for the system in the course of the project shall be consistent, CAD supported, and of similar look/feel. All CAD drawings to be provide in “dxf” format. • • • • • • • • • • • • List of Drawings Substation automation system architecture Block Diagram Guaranteed technical parameters, Functional Design Specification and Guaranteed availability and reliability Calculation for power supply dimensioning I/O Signal lists Schematic diagrams List of Apparatus List of Labels Logic Diagram (hardware & software) Panel Room Layout drawing Control Room Lay-out E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 48 • • • • • • • Test Specification for Factory Acceptance Test (FAT) Product Manuals Assembly Drawing Operator’s Manual Complete documentation of implemented protocols between various elements Listing of software and loadable in CD ROM Other documents as may be required during detailed engineering. Four sets of hard copy and Four sets of CD ROM containing all the as built documents/drawings shall be provided. 10.0 TRAINING, SUPPORT SERVICES, MAINTENANCE AND SPARES 10.1 Training Contractor personnel who are experienced instructors and who speak understandable English shall conduct training. The contractor shall arrange on its own cost al hardware training platform required for successful training and understanding in India. The Contractor shall provide all necessary training material. Each trainee shall receive individual copies of al technical manuals and al other documents used for training. These materials shall be sent to Employer at least two months before the scheduled commencement of the particular training course. Class materials, including the documents sent before the training courses as well as class handouts, shall become the property of Employer. Employer reserves the right to copy such materials, but for in-house training and use only. Hands-on training shall utilize equipment identical to that being supplied to Employer. For all training courses, the travel (e.g., airfare) and per-diem expenses will be borne by the participants. The Contractor shall quote training prices individually for each of the courses as indicated in BPS. Employer will have the option to cancel any or all-training courses. In the case of cancellation, the rate quoted against the respective course will not be paid to the Contractor. The schedule, location, and detailed contents of each course will be finalized during Employer and Contractor discussions. 10.2 Computer System Hardware Course A computer system hardware course shall be offered, but at the system level only. The training course shall be designed to give Employer hardware personnel sufficient knowledge of the overall design and operation of the system so that they can correct obvious problems, configure the hardware, perform preventive maintenance, run diagnostic programs and communicate with contract maintenance personnel. The following subjects shall be covered: a) b) (c) System Hardware Overview: Configuration of the system hardware. Equipment Maintenance: Basic theory of operation, maintenance techniques and diagnostic procedures for each element of the computer system, e.g., processors, auxiliary memories, LANs, routers and printers. Configuration of all the hardware equipments. System Expansion: Techniques and procedures to expand and add equipment such as loggers, monitors, and communication channels. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 49 (d) (e) (f) 10.3 Computer System Software Course The Contractor shall provide a computer system software course that covers the following subjects: (a) (b) (c) (d) (e) (f) 10.4 System Programming: Including all applicable programming languages and all stand-alone service and utility packages provided with the system. An introduction to software architecture, Effect of tuning parameters (OS software, Network software, database software etc.) on the performance of the system. Operating System: Including the user aspects of the operating system, such as program loading and integrating procedures; scheduling, management, service, and utility functions; and system expansion techniques and procedures. System Initialization and Failover: Including design, theory of operation, and practice. Including the execution of diagnostic procedures and the Diagnostics: interpretation of diagnostic outputs. Software Documentation: Orientation in the organization and use of system software documentation. Hands-on Training: One week, with allocated computer time for trainee performance of unstructured exercises and with the course instructor available for assistance as necessary. Application Software Course The Contractor shall provide a comprehensive application software courses covering all applications including the database and display building course. The training shall include: (a) (b) (c) (d) (e) (f) 10.5 System Maintenance: Theory of operation and maintenance of the redundant hardware configuration, failover hardware, configuration control panels and failover switches. Maintenance of protective devices and power supplies. Subsystem Maintenance: Theory of design and operation, maintenance techniques and practices, diagnostic procedures, and (where applicable) expansion techniques and procedures. Classes shall include hands-on training for the specific subsystems that are part of Employer's equipment or part of similarly designed and configured subsystems. All interfaces to the computing equipment shall be taught in detail. Operational Training: Practical training on preventive and corrective maintenance of all equipment, including use of special tools and instruments. This training shall be provided on Employer equipment, or on similarly configured systems. Overview: Block diagrams of the application software and data flows. Programming standards and program interface conventions. Application Functions: Functional capabilities, design, and major algorithms. Associated maintenance and expansion techniques. Techniques and conventions to be used for the Software Development: preparation and integration of new software functions. Software Generation: Generation of application software from source code and associated software configuration control procedures. Software Documentation: Orientation in the organization and use of functional and detailed design documentation and of programmer and user manuals. One week, with allocated computer time for trainee Hands-on Training: performance of unstructured exercises and with the course instructor available for assistance as necessary. Requirement of training: The contractor shall provide training for two batches for two weeks each for following courses. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 50 S. No. 1 2 3 Name of Course Computer System Hardware Computer System Software Application Software 11.0 Maintenance 11.1 Maintenance Responsibility during the Guaranteed Availability Period: During Guaranteed Availability Period, the Contractor shall take continual actions to ensure the guaranteed availability and shall make available all the necessary resources such as specialist personnel, spare parts, tools, test devices etc. for replacement or repair of all defective parts and shall have prime responsibility for keeping the system operational. 11.2 RELIABILITYAND AVAILABILITY The SAS shall be designed so that the failure of any single component, processor, or device shall not render the system unavailable. The SAS shall be designed to satisfy the very high demands for reliability and availability concerning: • Mechanical and electrical design • Security against electrical interference (EMI) • High quality components and boards • Modular, well -tested hardware • Thoroughly developed and tested modular software • Easy-to-understand programming language for application programming • Detailed graphical documentation and application software • Built-in supervision and diagnostic functions • Security − Experience of security requirements − Process know-how − Select before execute at operation − Process status representation as double indications • Distributed solution • Independent units connected to the local area network • Back-up functions • Panel design appropriate to the harsh electrical environment and ambient conditions • Panel grounding immune against transient ground potential rise 1) Outage Outage The state in which substation automation system or a unit of SAS is unavailable for Normal Operation as defined in the clause 7.1 due to an event directly related to the SAS or unit of SAS. In the event, the owner has taken any equipment/ system other than Sub-station Automation System for schedule/forced maintenance, the consequent outage to SAS shall not be considered as outage for the purpose of availability. 2) Actual outage duration (AOD) The time elapsed in hours between the start and the end of an outage. The time th th shall be counted to the nearest 1/4 of an hour. Time less than 1/4 of an hour shall th be counted as having duration of 1/4 of an hour. 3) Period Hours (PH) The number of hours in the reporting period. In a full year the period hour are 8760h (8784h for a leap year). E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 51 4) Actual Outage hours (AOH) The sum of actual outage duration within the reporting period AOH = ∑ AOD 5) Availability: Each SAS shall have a total availability of 99.98 % i.e. the ratio of total time duration minus the actual outage duration to total time duration. 12.0 Guarantees Required The availability for the complete SAS shall be guaranteed by the Contractor. Bidder shall include in their offer the detailed calculation for the availability. The contractor shall demonstrate their availability guaranteed by conducting the availability test on the total sub-station automation system as a whole after commissioning of total Sub-station Automation system. The test shall verify the reliability and integrity of all sub-systems. Under these conditions the test shall establish an overall availability of 99.98%. After the lapse of 1000 Hours of cumulative test time, test records shall be examined to determine the conformance with availability criterion. In case of any outage during the availability test, the contractor shall rectify the problem and after rectification, the 1000 Hours period start after such rectification. If test object has not been met the test shall continue until the specified availability is achieved. The contractor has to establish the availability in a maximum period of three months from the date of commencement of the availability test. After the satisfactory conclusion of test both contractor and employer shall mutually agree to the test results and if these results satisfy the availability criterion, the test is considered to be completed successfully. After that the system shall be taken over by the employer and then the guarantee period shall start. 13.0 13.1 Spares Consumables: All consumables such as paper, cartridges shall be supplied by the contractor till the SAS is taken over by the owner. 13.2 Availability Spares: In addition to mandatory spares as listed in section project for SAS, the bidder is required to list the spares, which may be required for ensuring the guaranteed availability during the guaranteed availability period. The final list of spares shall form part of scope of supply and accordingly the price thereof shall be quoted by the bidder and shall be considered in the evaluation of the bids. During the guaranteed availability period, the spare parts supplied by the Contractor shall be made available to the Contractor for usage subject to replenishment at the earliest. Thus, at the end of availability period the inventory of spares with the Employer shall be fully replenished by the Contractor. However, any additional spares required to meet the availability of the system (which are not a part of the above spares supplied by the Contractor) would have to be supplied immediately by the Contractor free of cost to the Employer. 14.0 LIST OF EQUIPMENTS Quantity of equipments shall be decided by bidder in order to achieve guaranteed reliability and availability as declared by bidder. i) Station HMI ii) Redundant Station HMI (in Hot-standby mode) iii) Bay level units along with bay mimic iv) Disturbance Recorder Work Station (Maintenance HMI) E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 52 v) vi) vii) viii) Color Laser Printer – 1 No. (For Reports & Disturbance records) Dot matrix printers - (one each for Alarms and log sheets) All interface equipment for gateways to RCC and RSCC Communication infrastructure between Bay level units, Station HMI, Printers, gateways, redundant LAN etc. as required ix) Any other equipment as necessary. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 53 Annexure-II Basic Monitoring requirements are: - Switchgear status indication - Measurements (U, I, P, Q, f) - Event - Alarm - Winding temperature of Transformers. - Ambient temperature. - Status and display of 415V LT system, 220V & 48V DC system. - Status & Display of Fire protection System and AC System. - Acquisition of all counters in PLCC panels through potential free contacts from PLCC or independently by counting the receive/send commands. - Acquisition of alarm and fault record from protection relays Disturbance. - Monitoring the state of batteries by displaying DC voltage, charging current and load current etc. - Tap-position of Transformer List of Inputs The list of input for typical bays is as below:Analogue inputs i) For line Current Voltage R phase Y phase B phase Y-B phase B-R phase ii) For Transformer Current R phase Y phase B phase WTI (for transformer) Tap position (for transformer only) iii) iv) a) b) c) For Bus coupler Current R phase Y phase B phase Common Voltage for Bus-I, Bus-II and Transfer bus wherever applicable Voltage R-Y phase Y-B phase B-R phase Frequency for Bus-I and Bus-II Ambient temperature (switchyard). E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 54 d) i) ii) iii) iv) v) vi) vii) viii) ix) x) xi) xii) xiii) xiv) xv) xvi) xvii) xviii) LT system Voltage R-Y, Y-B, B-R of Main Switch Board section-I Voltage R-Y, Y-B, B-R of Main Switch Board section-II Voltage R-Y, Y-B, B-R of Diesel Generator Current from LT transformer-I Current from LT transformer-II Current from Diesel Generator Voltage of 220V DCDB-I Voltage of 220V DCDB-II Current from 220V Battery set-I Current from 220V Battery set-II Current from 220V Battery charger-I Current from 220V Battery charger-I Voltage of 48V DCDB-I Voltage of 48V DCDB-II Current from 48V Battery set-I Current from 48V Battery set-II Current from 48V Battery charger-I Current from 48V Battery charger-I Digital Inputs The list of input for various bays/SYSTEM is as follows: 1. i) ii) iii) iv) v) vi) vii) viii) ix) x) xi) xii) xiii) xiv) xv) xvi) xvii) xviii) xix) xx) xxi) xxii) xxiii) xxiv) xxv) xxvi) xxvii) xxviii) xxix) xxx) xxxi) xxxii) xxxiii) Line bays Status of each pole of CB, Isolator, Earth switch CB trouble CB operation/closing lockout Pole discrepancy optd Trip coil faulty LBB optd Bus bar protn trip relay optd Main bkr auto recloser operated Tie/transfer auto recloser operated A/r lockout Tie/transfer bkr a/r lockout Direct trip-I/II sent Direct trip-I/II received Main I/II blocking Main I/II-Inter trip send Main I/II-Inter trip received O/V STAGE – I operated O/V STAGE – II operated FAULT LOCATOR FAULTY MAIN-I/II CVT FUSE FAIL MAIN-I PROTN TRIP MAIN-II PROTN TRIP MAIN-I PSB ALARM MAIN-I SOTF TRIP MAIN-I R-PH TRIP MAIN-I Y-PH TRIP MAIN-I B-PH TRIP MAIN-I START MAIN-I/II Carrier aided trip MAIN-I/II fault in reverse direction MAIN-I/II ZONE-2 TRIP MAIN-I/II ZONE-3 TRIP MAIN-I/II weak end infeed optd E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 55 xxxiv) xxxv) xxxvi) xxxvii) xxxviii) xxxix) xl) xli) xlii) xliii) xliv) xlv) xlvi) xlvii) 2. i) ii) iii) iv) v) vi) vii) viii) ix) x) xi) xii) xiii) xiv) xv) xvi) xvii) xviii) xix) xx) xxi) xxii) xxiii) xxiv) xxv) xxvi) xxvii) xxviii) xxix) xxx) xxxi) 3. i) ii) iii) iv) v) vi) vii) MAIN-II PSB alarm MAIN-II SOTF TRIP MAIN-II R-PH TRIP MAIN-II Y-PH TRIP MAIN-II B-PH TRIP MAIN-II start MAIN-II aided trip MAIN-I/II fault in reverse direction Back-up o/c optd Back-up e/f optd 220V DC-I/II source fail SPEECH CHANNEL FAIL PLCC Protection Channel-I FAIL PLCC Protection Channel-II FAIL Transformer bays Status of each pole of CB, Isolator, Earth switch CB trouble CB operation/closing lockout Pole discrepancy optd Trip coil faulty LBB optd Bus bar protn trip relay optd REF OPTD DIF OPTD OVERFLUX ALARM (MV) OVERFLUX TRIP (MV) OVERFLUX ALARM (HV) OVERFLUX TRIP (HV) HV BUS CVT ½ FUSE FAIL MV BUS CVT ½ FUSE FAIL OTI ALARM/TRIP PRD OPTD OVERLOAD ALARM BUCHOLZ TRIP BUCHOLZ ALARM OLTC BUCHOLZ ALARM OLTC BUCHOLZ TRIP OIL LOW ALARM back-up o/c (HV) optd back-up e/f (HV)optd 220v DC-I/II source fail TAP MISMATCH GR-A PROTN OPTD GR-B PROTN OPTD back-up o/c (MV) optd back-up e/f (MV)optd Transformer bays Status of each pole of CB, Isolator, Earth switch CB trouble CB operation/closing lockout Pole discrepancy optd Trip coil faulty LBB optd Bus bar protn trip relay optd E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 56 viii) ix) x) xi) xii) xiii) xiv) xv) xvi) xvii) xviii) xix) 4 REF OPTD DIF OPTD HV BUS CVT ½ FUSE FAIL OTI ALARM/TRIP PRD OPTD BUCHOLZ TRIP BUCHOLZ ALARM OIL LOW ALARM Back-up impedance relay 220v DC-I/II source fail GR-A PROTN OPTD GR-B PROTN OPTD Bus Bar Protection i) ii) iii) iv) v) vi) vii) 5. i) ii) iii) iv) v) vi) vii) viii) ix) x) xi) xii) xiii) xiv) xv) xvi) xvii) Bus bar main-I trip Bus bar main-II trip Bus bar zone-I CT open Bus bar zone-II CT open Bus transfer CT sup. Optd Bus transfer bus bar protn optd Bus protection relay fail Auxiliary system Incomer-I On/Off Incomer-II On/Off 415V Bus-I/II U/V 415v bus coupler breaker on/off DG set bkr on/off Alarm/trip signals as listed in Section: DG set LT transformer-I Bucholz Alarm & trip LT transformer-II Bucholz Alarm & trip LT transformer-I WTI Alarm & trip LT transformer-II WTI Alarm & trip LT transformer-I OTI Alarm & trip LT transformer-II OTI Alarm & trip PLCC exchange fail Time sync. Signal absent Alarm/trip signals as listed in Section: Battery and Battery charger 220v dc-I earth fault 220v dc-II earth fault NOTE:The exact number and description of digital inputs shall be as per detailed engineering requirement Apart from the above mentioned digital inputs, minimum of 200 inputs shall be kept for use in future. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 57 ANNEXURE -A GUARANTED TECHNICAL PARTICULARS CONTROL AND RELAY PANEL BOARDS FOR SUBSTATIONS WITH SUBSTATION AUTOMATION SYSTEM I. PANELS. 1. Dimension of the C&R panels. i) Depth ii) Overall height 2. Dimension of supporting channel. 3. Thickness of the sheet steel proposed for fabrication of panels. II. 1. 2. 3. i) ii) iii) iv) v) 4. 5. III. 1. 2. 3. 4. 5. 6. 7. 8. 9. IV. 1. 2. 3. 4. 5. 6. 7. SWITCH BOARD WIRING. Insulation of wiring. Material of wiring conductor. Size of wiring conductor for: C.T. Circuits. C.V.T./P.T. Circuits. D.C. supply circuits. A.C. Supply Circuit. Other circuits. Size of earthing bar for safety earthing. Type of terminals used in wiring the panel. CONTROL SWITCHES FOR CIRCUIT BREAKER & ISOLATORS. Make. Type. Type of handle provided. Number of position . Whether no. of Normally closed & Normally open contacts sufficient for seheme requirements? (Yes / No). Whether spring return to neutral or stay-put type. Type of lock provided. Making capacity/breaking capacity at 220 Volt DC for both inductive & non-inductive current. Descriptive leaflet number submitted. OVER CURRENT & EARTH FAULT RELAY. Make. Type of relay. Current coil rating. Potential coil rating (applicable only in case of directional relays). Tap range. Range of high set elements (wherever applicable). VA burden. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 58 8. 9. 10. V. a) Highest tap. b) Lowest tap. Time V/S current characteristics. Trip contact rating. Descriptive leaflet No. submitted. AUXILIARY RELAYS. Make. Type. Capacity of contacts: i) Continuously. ii) for 3 seconds. 4. Operating coil VA burden. 5. Voltage operated or current operated. 6. No. of Normally closed & Normally open contacts sufficient for scheme requirements (Yes / No). 7. Contacts hand or self reset type. 8. Descriptive leaflet number submitted. 1. 2. 3. VI. 1. 2. 3. 4. 5. 6. 7. VII. 1. 2. 3. 4. 5. 6. 7. VIII. 1. 2. 3. 4. 5. 6. 7. 8. TRANSFORMER DIFFERENTIAL RELAY. Make. Type. Minimum differential current at which relay operations. Range & steps of bias setting. Operating time at twice the relay setting. VA burden of the relay. Descriptive leaflet No. submitted. TRIP CIRCUIT SUPERVISION RELAY. Make. Type Rating Minimum voltage for satisfactory operation (% of rated voltage). Monitoring of breaker trip coil in both close & open position provided. Safety resistors provided to limit the current if the relay coil is short-circuited. No. of Normally closed & Normally open contacts sufficient for seheme requirements (Yes / No). RESTRICTED EARTH FAULT RELAY . Make. Type. Tap range. Timer setting range. V A Burden. Time/Current characteristics Short time rating of relay. Descriptive leaflet No. submitted. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 59 IX. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. X. T/F OVER FLUXING RELAY. Make Type. Rated Voltage (V,AC) Rated DC Voltage. Operating principle. No. of Normally closed & Normally open contacts sufficient for seheme requirements (Yes / No). Contacts self/hand reset. Burden. Setting range. i) V/F ii) Time for alarm. iii) Time for tripping. Whether inverse time operating characteristics provided. Whether different time multiplier settings provided. Max. operating time of the relay at i) 1.4 times the rated value of V/F. ii) 1.25 times the rated value of V/F. Reset time. LOCAL BREAKER BACK UP RELAYS . 1. Make. 2. Type. 3. Setting range (% of rating) a) Phase faults. b) Ground faults. 4. Operating time (m sec.) 5. Reset time (m sec). 6. Burden. 7. Timer range. 8. Whether no. of Normally closed & Normally open contacts sufficient for seheme requirements? (Yes / No). XI. 1. 2. 3. 4. 5. 6. OVER LOAD ALARM RELAY. Make. Type. Rated Voltage. Setting Ranges. Operating time. Setting range continuously variable. 1. 2. 3. 4. 5. SELECTOR SWITCHES (AUTORECLOSING IN/OUT, CARRIER PROTECTION IN/OUT SWITCH, TRIP TRANSFER SWITCH). Make. Type. Type of handle. No. of positions. No. of Normally closed & Normally open XII. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 60 6. 7. XIII. contacts sufficient for seheme requirements (Yes / No). Making & breaking capacity of contacts. Descriptive leaflet number submitted. 11. DISTANCE RELAYS. Make. Type of relay. Type of distance measuring elements. Details of starting units and their switching sequence, if applicable. Range of settings (in secondary ohms). for Zone-I, Zone-2 & Zone-3. Operating times: i) First zone timing. ii) Second zone time setting adjustable between-------- secs to ------- secs. iii) Third zone time setting adjustable between -------- secs to ------- secs. Contacts rating: i) First Zone. ii) Second Zone. iii) Third Zone. VA burden : i) Current circuit of the scheme. ii) Potential circuit of the scheme. Is the VA burden at Sr.No.8 above is continuous ? (yes/No) Operating time versus ZS/ZL curves of the distance scheme. Descriptive leaflet no. submitted. 1. 2. 3. 4. 5. 6. 7. CHECK SYNCHRONIZING RELAY: Make. Type. Rating ( V, ac ) Aux. Voltage ( V, dc ) Permissible voltage difference (%) Permissible phase angle difference (degree) Response time of relay (without timer)( m Sec ) 1. 2. 3. 4. 5. 6. 7. 8. 9. AUTO RECLOSING : Make. Type. Multi shot or single shot. Rating (V, dc) Suitable for 1 & 3 phase. Dead time setting range (Sec.) Reclaim time setting range (sec.) Four position selector switch provided. Alarm contacts provided for `Auto-reclosed', `Reclosure unsuccessful'. 1. 2. 3. 4. 5. 6. 7, 8. 9 10. XIV. XV. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 61 XVI. 1. 2. 3. 4. 5. 6. 7. BUS-BAR PROTECTION Make. Type. Applicable standard. Rated Voltage/Frequency. Operating time (maximum). Resetting time (maximum). Does the offer meet the requirements of technical specification? Yes/No E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 62 ANNEXURE –B TECHNICAL PARTICULARS OF CTs, PTs, CVTs & NCTs. COREWISE DETAILS OF 420 kV CTs (2000-1000-500/1-1-1-1-1A) NUMBER OF CORES – 5 Core No. 1 1 2 3 4 5 Application Current ratio Output burden (VA) 2 BUS DIFF MAIN BUS DIFF CHECK METERING 3 2000-1000 /1 20001000/1 2000-1000500/1 TRANS. BACKUP/ LINE PROTN. TRANS. DIFF/ LINE PROTN. 2000-1000500/1 2000-1000500/1 Accuracy class 4 Min. knee Pt. Voltage Vk Max. CT sec. wdg. Resistance (ohms) Max. Excitation current at Vk (in mA) 8 30 on 2000/1 Tap; 60 on 1000/1 Tap 30 on 2000/1 Tap; 60 on 1000/1 Tap - - 5 PS 6 2000/1000 7 10/5 - PS 2000/1000 10/5 10 - - - 0.2S ISF<5 for 500/1A, ISF<10 for 1000/1A, ISF<20 for 2000/1A PS 4000/2000 /1000 10/5/2.5 - PS 4000/2000 /1000 10/5/2.5 30 on 2000/1 Tap;60 on 1000/1 Tap; 120 on 500/1 Tap 30 on 2000/1 Tap;60 on 1000/1 Tap; 120 on 500/1 Tap COREWISE DETAILS OF 245kV Transformer CTs (450-300/0.577-1-1-1-1A) NUMBER OF CORES - 5 Core No. 1 1 2 3 4 5 Application 2 DIFFERENTIAL PROTECTION REF PROTECTION Current Ratio (A) 3 450-300/ 0.577 450300/1 OVER CURRENT 450PROTECTION / BUS 300/1 BAR PROTECTION 450BUSBAR PROTECTION (FOR 300/1 LOW IMPEDANCE SCHEME) METERING 450300/1 Output burden (VA) 4 Accuracy class as per IEC 185 Formula for minimum kneepoint voltage At CT Secondary resistance at 750C at 300A tap (Volt) Maximum Exciting Current (mA) I.S.F. / A.L. F - 5 PS 6 40 (RCT+2) 7 30 @Vk/4 8 - - PS 14 (RCT+2) 30 @Vk/2 - - PS 40 (RCT+4) 30 @Vk/2 - - PS 40 (RCT+4) 30 @Vk/2 - 10 0.2S - - <5 E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 63 NOTE : 4th core for bus bar protection has been kept in view of general design being followed in HVPNL. In case this CT is used on a sub station having high impedance bus bar protection scheme or no bus bar protection scheme then this core shall be short-circuited at site. COREWISE DETAILS OF 245kV LINE CUM BUS-COUPLER CTs (1200-800-400/1-1-1-1-1 A) NUMBER OF CORES – 5 Core No. 1 1. 2. 3. 4. 5. Application Current Ratio (A) 2 MAIN–I DISTANCE PROTECTION MAIN–II DISTANCE PROTECTION BUS DIFFERENTIA L MAIN BUS DIFFERENTIA L CHECK METERING 3 1200800400/1 1200800400/1 1200800400/1 1200800400/1 1200800400/1 Output Accuracy Formula for minimum burden class knee point voltage At CT (VA) as per Secondary resistance at IEC 185 750C at 800Atap (Volt) 4 5 6 PS 80(RCT+9) Maximum Instrument Exciting Security Current factor (mA) 7 8 80 @ Vk - - PS 80(RCT+9) 80 @ Vk - - PS 100(RCT+4) 30 @ Vk/2 - - PS 100(RCT+4) 30 @ Vk/2 - 10 0.2S - - ISF<5 for ratio 400/1, ISF<10 for ratio 800/1, ISF<20 for ratio 1200/1 NOTE : 1. 5 cores of 245kV line CT have been kept in view of general design being followed in HVPNL. 2. In case this CT is used exclusively for bus bar protection purpose on a transformer circuit at sub station having high impedance bus bar protection scheme then core no 1, 2 & 5 shall be short circuited at site. 3. In case this CT is used for feeder circuit on a sub station having low impedance bus bar protection scheme then core no. 4 shall be short circuited at site and where there is no bus bar protection scheme core no. 3 & 4 shall be short circuited at site. COREWISE DETAILS OF 245kV LINE CTs (2000-1000/1-1-1-1-1 A) NUMBER OF CORES – 5 Core No. 1 1. Application 2 MAIN–I DISTANCE PROTECTION Current Ratio (A) 3 20001000/1 Output Accuracy Formula for minimum burden class knee point voltage At CT (VA) as per Secondary resistance at IEC 185 750C at 1000A tap (Volt) 4 5 6 - PS 1600 Maximum Exciting Current (mA) 7 Instrument Security Factor/ A.L.F 8 20-40 E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc - 64 2. MAIN–II DISTANCE PROTECTION BUS DIFFERENTIAL MAIN BUS DIFFERENTIAL CHECK METERING 3. 4. 5. 20001000/1 - PS 1600 20-40 - 20001000/1 - PS 1600 20-40 - 20001000/1 - PS 1600 20-40 - 20001000/1 10 0.2S - - ISF<5 for ratio 1000/1, ISF<10 for ratio 2000/1, NOTE : 1. 5 cores of 245kV line CT have been kept in view of general design being followed in HVPNL. 2. In case this CT is used exclusively for bus bar protection purpose on a transformer circuit at sub station having high impedance bus bar protection scheme then core no 1, 2 & 5 shall be short circuited at site. 3. In case this CT is used for feeder circuit on a sub-station having low impedance bus bar protection scheme then core no. 4 shall be short circuited at site and where there is no bus bar protection scheme core no. 3 & 4 shall be short circuited at site. COREWISE DETAILS OF 245 kV BUS COUPLER CTs FOR 400KV S/STNS. (2400-1200/1-1-1-1A) NUMBER OF CORES - 4 Core No. 1 1. 2. 3. 4. Application Current Ratio (A) Output burden (VA) Accuracy class as per IEC 185 2 O/C & E/F PROTECTION BUS DIFFERENTIAL BUS DIFFERENTIAL CHECK METERING 3 2400-120 0/1 2400-120 0/1 2400-120 0/1 4 15 5 5P Formula for minimum knee point voltage At CT Secondary resistance at 750C at 2400Atap (Volt) 6 - - PS - 2400-120 0/1 10 Maximum Exciting Current (mA) ALF/ISF 7 - 8 10 100(RCT+4) 30 @ Vk/2 - PS 100(RCT+4) 30 @ Vk/2 - 1.0 - - ISF<5 E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 65 COREWISE DETAILS OF 245 kV Transformer INCOMER CTs (900-600-300/1-1-1-1-1A) NUMBER OF CORES - 5 Core Application No. 1 1 2 3 4 5 Current Ratio (A) Output burden (VA) Accuracy class as per IEC 185 4 5 Formula for minimum knee point voltage At CT Secondary resistance at 750C at 900Atap (Volt) Maximum Exciting Current (mA) 6 40 (RCT+2) 7 30 @Vk/4 I.S.F./ A.L.F 2 DIFFERENTIAL PROTECTION OVER CURRENT & EARTH FAULT PROTECTION METERING BUSBAR PROTECTION MAIN DIFF. 3 900-600-300/1 - PS 900-600-300/1 15 5P 900-600-300/1 900-600-300/1 10 - 0.2S PS 40 (RCT+4) 30 @Vk/2 <5 - BUSBAR PROTECTION CHECK DIFF. 900-600-300/1 - PS 40 (RCT+4) 30 @Vk/2 - - 8 - - 10 COREWISE DETAILS OF 245kV NEUTRAL CTs (450-300/1A) NUMBER OF CORE - 1 Application Current Ratio (A) 1 Accuracy class as per IEC 185 2 REF PROTECTION 450-300/1 Formula for minimum kneepoint voltage at CT Secondary resistance at 750C at 300Atap(Volt) 3 Maximum Exciting Current (mA) 4 PS Minimum Insulation Voltage (kV) 5 14(RCT+2) 30 @ VK/2 6 33 COREWISE DETAILS OF 145kV TRANSFORMER INCOMER CT (750-500/0.577-1-1-1A) NUMBER OF CORES – 4 Core No. 1 1. 2. 3. 4. Application 2 DIFFERENTIAL PROTECTION REF PROTECTION OVER CURRENT AND EARTH FAULT PROTECTION METERING Current Ratio (A) Output burden (VA) Accurac y Class as per IEC 185 Formula for minimum knee-point voltage At CT Secondary resistance at 750C at 500Atap (Volt) Maximum Exciting Current (mA) I.S.F./ A.L.F. 3 4 5 6 7 8 750-500/ 0.577 750-500/1 - PS 40 (RCT+2) 30 @ Vk/4 - - PS 90 (RCT+2) 37.5 @ Vk/2 - 750-500/1 15 5P - - ALF10 750-500/1 10 0.2S - - ISF<5 E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 66 COREWISE DETAILS OF 145kV TRANSFORMER CT (250-150-100/0.577-1-1-1A) No. OF CORES = 4 Core No. 1 1. 2. 3. 4. Application Current Ratio (A) 2 DIFFERENTIAL PROTECTION REF PROTECTION OVER CURRENT PROTECTION METERING 3 250-150100/0.577 250-150100/1 250-150100/1 Accurac y class as per IEC 185 Formula for minimum kneepoint voltage At CT Secondary resistance at 750C at 100A tap (Volt) Maximum Exciting Current (mA) - 5 PS 6 40 (RCT+1) 7 30 @ Vk/4 8 - - PS 20 (RCT+1) 30 @ Vk/2 - 15 5P - - 10 0.2S - - ISF<5 Output burden (VA) 4 250-150100/1 10 A.L.F. COREWISE DETAILS OF 145kV LINE CT AND 145kV BUS COUPLER CT for 132kV S/STNS. (600-300-150/1-1-1A) No. OF CORES = 3 Core Application No. 1 1 2 3 2 DISTANCE PROTECTION OVER-CURRENT & EARTH FAULT PROTECTION METERING Current Ratio (A) 3 Output Accura burden cy class (VA) as per IEC 185 4 5 Formula for minimum kneepoint voltage At CT Secondary resistance at 750C at 300Atap (Volt) 6 Maximum Exciting Current (mA) A.L.F./ I.S.F. 7 8 600-300-150/1 - PS 120 (RCT+4.5) 80 @ VKP - 600-300-150/1 15 5P - - ALF 10 600-300-150/1 10 0.2S - - ISF<5 for ratio 150/1, ISF<10 for ratio 300/1, ISF<20 for ratio 600/1 E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 67 COREWISE DETAILS OF 145kV NEUTRAL CT (250-150-100/1A) No. OF CORE= 1 Core Application No. 1 Current Ratio (A) 2 1 REF PROTECTION Output burden (VA) Accurac y class as per IEC 185 3 4 5 250-150100/1 - PS Formula for minimum kneepoint voltage At CT Secondary resistance at 750C at 100A tap (Volt) 6 20 (RCT+1) Maximum Exciting Current (mA) Minimum Insulatio n Voltage (kV) 7 8 30 @ VK/2 15 COREWISE DETAILS OF 145kV BUS COUPLER CT for 160MVA 220/132kV T/Fs. (750-500/1-1A) No. OF CORES = 2 Core Application No. 1 2 3 Current Ratio (A) 2 Output burden (VA) 3 OVER-CURRENT & EARTH FAULT PROTECTION METERING Accuracy class as per IEC 185 5 4 A.L.F./ I.S.F. 8 750-500/1 15 5P ALF 10 750-500/1 10 1.0 ISF<5 COREWISE DETAILS OF 72.5kV TRANSFORMER INCOMER CT (1500-1000/0.577-1-1-1A) NUMBER OF CORES - 4 Core Application No. 1 1 2 3 4 2 Current Ratio (A) Output burden (VA) 3 4 Accuracy class as per IEC 185 5 Formula for minimum kneepoint voltage At CT Secondary resistance at 750C at 1000A tap (Volt) 6 Maximum Exciting Current (mA) A.L.F./ I.S.F. 7 8 DIFFERENTIA L PROTECTION REF PROTECTIO N OVER CURRENT & EARTH FAULT PROTECTIO N 1500-1000/0.577 - PS 40 (RCT+2) 30 @ VK/4 1500-1000/1 - PS 14 (RCT+2) 30 @ VK/2 1500-1000/1 15 5P - - ALF 10 METERING 1500-1000/1 10 0.2S - - ISF <5 E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc - 68 COREWISE DETAILS OF 72.5kV TRANSFORMER CT FOR 66/11kV T/Fs (300-200-150/0.577-1-1) No. OF CORES = 3 Core Application No. 1 1 2 3 Current Ratio (A) 2 Output Accuracy Formula for burden class minimum knee(VA) as per point voltage At IEC 185 CT Secondary resistance at 750C at 300A tap (Volt) 4 5 6 3 DIFFERENTIAL 300-200PROTECTION 150/0.577 REF PROTECTION 300-200-150/1 OVER CURRENT PROTECTION 300-200-150/1 Maximum A.L.F Exciting Current (mA) 7 8 - PS 40(RCT+4) 30 @ VK/2 - - PS 40(RCT+4) 30 @ VK/2 - 15 5P - - 10 COREWISE DETAILS OF 72.5kV LINE CT AND 72.5kV BUS COUPLER CT for 66kV S/STNS. Core Application No. 1 1 2 3 2 DISTANCE PROTECTION OVER CURRENT & EARTH FAULT PROTECTION METERING Current Ratio (A) 3 (600-300-150/1-1-1A) No. OF CORES = 3 Output Accuracy Formula for min knee point burden class voltage At CT as per (VA) Secondary res. IEC 185 at 750C at 600A tap (Volt) 4 5 6 Maximum A.L.F./ Exciting I.S.F. Current (mA) 7 8 600-300-150/1 - PS 80(RCT+4) 40 @VK/2 - 600-300-150/1 15 5P - - ALF 10 0.2S - - 600-300-150/1 10 ISF<5 for ratio 150/1, ISF<10 for ratio 300/1, ISF<20 for ratio 600/1 COREWISE DETAILS OF 72.5kV TRANSFORMER INCOMER NCT (1500-1000/1A) No. OF CORES= 1 Core Application No. 1 1 2 Current Ratio (A) 3 REF PROTECTION 1500-1000/1 Output burden (VA) Accuracy class as per IEC 185 4 5 - PS Formula for min knee point voltage At CT Secondary res. at 750C at 1000A tap (Volt) 6 14 (RCT+2) Maximum Exciting Current (mA) Minimum Insulation Voltage (kV) 7 8 30 @ VK/2 E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 15 69 COREWISE DETAILS OF 72.5 kV NEURAL CT FOR 66/11kV T/Fs (300-200-150/1) No. OF CORE = 1 Core No. Application Current Ratio (A) Output burden (VA) Accuracy class as per IEC 185 1 2 3 4 5 Formula for minimum knee point voltage at CT secondary resistance at 750 at 300A tap (Volt) 6 1. REF PROTECTION 300-200150/1 - PS 20 (RCT+1) Maximum exciting current (mA) Minimum Insulation voltage (kV) 7 8 30 @ Vk/2 15 COREWISE DETAILS OF 72.5kV BUS COUPLER CT for 160MVA 220/66kV T/Fs. (1500-1000/1-1A) No. OF CORES = 2 Core Application No. 1 2 3 Current Ratio (A) 2 Output burden (VA) 4 3 OVER-CURRENT & EARTH FAULT PROTECTION METERING Accuracy class as per IEC 185 5 A.L.F./ I.S.F. 8 1500-1000/1 15 5P ALF 10 1500-1000/1 10 1.0 ISF<5 COREWISE DETAILS OF 36kV TRANSFORMER INCOMER CT FOR 40/50MVA 132/33kV T/F AND OTHER RATINGS OF 132/33KV T/Fs WITH 26.3KA STC (1000-600-400/0.577-5-5-1) No. OF CORES = 4 Core No. 1 1 2 3 4 Application 2 DIFFERENTIAL PROTECTION REF PROTECTION OVER CURRENT & EARTH FAULT PROTECTION MAIN METERING Current Ratio (A) 3 Output Accuracy Formula for burden class as minimum knee (VA) Per IEC point voltage At 185 CT Secondary resistance at 750C at 400A tap (Volt) 4 5 6 1000-600-400/0.577 Maximum Exciting Current (ma) A.L.F./ I.S.F. 7 PS 40 (RCT+1) 30@VK/4 8 1000-600-400/5 - PS 100(RCT+1) 75@VK/2 1000-600-400/5 15 5P - - 10 1000-600-400/1 10 0.2S - - <5 for ratio 300/1 <10 for ratio 400/1 <20 for ratio 600/1 E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 70 COREWISE DETAILS OF 36kV TRANSFORMER INCOMER CT FOR 220/33KV WITH 26.3KA STC (2000-1000/0.577-5-5-1) No. OF CORES = 4 Core Application No. 1 1 2 3 4 Current Ratio (A) 2 Output Burden (VA) 3 DIFFERENTIAL PROTECTION REF. PROT. OVER CURRENT & EARTH FAULT PROT. MAIN METERING Accuracy class as per IEC 185 4 5 Formula for minimum kneepoint voltage At CT Secondary resistance at 750C at 2000A tap (Volt) 6 Maximum Exciting Current (mA) A.L.F. / ISF 7 8 2000-1000/ 0.577 2000-1000/ 5 2000-1000/5 - PS 40 (RCT+1) 30@ V K/4 - 15 PS 5P 100 (RCT+1) - 75@ V K/2 - 10 2000-1000/1 10 0.2S - - For ratio 1000/1 ISF<5. For ratio 2000/1 ISF<10 . COREWISE DETAILS OF 36kV LINE CUM CAPACITOR CT for 33kV LINE BAY AND FOR 20MVAR & 10MVAR CAPACITOR BANKS ON 220/33KV T/F & 40/50MVA 132/33kV T/F WITH 26.3KA STC (400-300/5-1) No. OF CORES = 2 Core No. Current Ratio (A) (VA) Output Burden A.L.F. 1. 2. 3. 4. Accuracy Class as per IEC 185 5. 1. OVER CURRENT & EARTH FAULT PROTECTION METERING 400-300/5 15 5P 10 400-300/1 10 0.2S 75 2. Application E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 6. 71 COREWISE DETAILS OF 36kV TRANSFORMER INCOMER NCT FOR 40/50MVA 132/33kV T/F AND OTHER RATINGS OF 132/33KV T/Fs WITH 26.3KA STC (1000-600-400/5) No. OF CORES = 1 Core Application No. 1 Current Ratio (A) 2 1 3 REF PROTECTION 1000-600-400/5 Output burden (VA) Accuracy class as Per IEC 185 4 5 - PS Formula for minimum knee point voltage At CT Secondary resistance at 0 75 C at 400A tap (Volt) 6 100 (RCT+1) Maximum Exciting Current (mA) Minimum Insulation Voltage (kV) 7 8 75@ VK/2 15 COREWISE DETAILS OF 36kV TRANSFORMER INCOMER NCT FOR 220/33KV T/F WITH 26.3KA STC (2000-1000/5) No. OF CORES = 1 Core Application No. 1 1 Current Ratio (A) 2 REF PROTECTION 3 20001000 /5 4 5 Formula for minimum knee-point voltage At CT Secondary resistance at 750C at 2000A tap (Volt) 6 - PS 100 (RCT+1) Output Burden (VA) Accuracy class as per IEC 185 Minimum Insulatio n Voltage (kV) Maximum Exciting Current (mA) 7 8 75@ VK/2 15 COREWISE DETAILS OF 36kV BUS COUPLER CT FOR 220/33KV WITH 26.3KA STC (2000-1000/5A) No. OF CORES = 1 Core No. 1 1 Application 2 OVER CURRENT & EARTH FAULT PROTECTION Current Ratio (A) 3 2000-1000/ 5A Output Burden (VA) 4 15 Accuracy class as per IEC A.L.F. 185 5 5P 6 10 E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 72 COREWISE DETAILS OF 36kV TRANSFORMER CT WITH 26.3KA STC FOR 4 MVA 33/11kV T/F (100-50/5-5) No. OF CORES = 2 Core Application No. 1 Current Ratio (A) 2 1 REF PROTECTION OVER CURRENT PROTECTION 2 Output burden (VA) Accuracy class as Per IEC 185 Formula for minimum knee point voltage At CT Secondary resistance at 750C at 100A tap (Volt) 6 3 4 5 100-50/5 - PS 100 (RCT+1) 100-50/5 15 5P - Maximum Exciting Current (mA) Minimum Insulatio n Voltage (kV) 7 8 75@ VK/2 - - 10 COREWISE DETAILS OF 36kV TRANSFORMER NCT WITH 26.3KA STC FOR 4 MVA 33/11kV T/F (100-50/5) No. OF CORE = 1 Core Application No. 1 1 Current Ratio (A) 2 REF PROTECTIO N 3 Accuracy class as per IEC 185 4 100-50/5 PS Formula for minimum knee-point voltage At CT Secondary resistance at 750C at 100A tap (Volt) 5 Maximum Exciting Current (mA) 6 100 (RCT+1) Minimum Insulatio n Voltage (kV) 7 75@ VK/2 15 COREWISE DETAILS OF 12 kV NEUTRAL CT FOR 25/31.5 MVA T/F (1800-900/5) No. OF CORE = 1 Core No. Maximum exciting current (mA) Minimum Insulation voltage (kV) 3 Accuracy Formula for minimum class as per knee point voltage at IEC 185 CT secondary resistance at 750 at 1800A tap (Volt) 4 5 6 7 1800-900/5 PS 75@ Vk/2 8.66 Application Current Ratio (A) 1 2 1. REF PROTECTION 95 (RCT+1) COREWISE DETAILS OF 12kV NEUTRAL CT FOR 12.5/16 MVA & 16/20 MVA T/F (1200-900/5) No. OF CORE = 1 Core Application No. 1 1 2 REF PROTECTION Current Accuracy Formula for minimum Ratio (A) class knee-point voltage At CT as per Secondary resistance at IEC 185 750C at 1200A tap (Volt) 3 4 5 1200-900/5 PS 95 (RCT+1) Maximum Exciting Current (mA) 6 75@ VK/2 Minimum Insulatio n Voltage (kV) 7 8.66 E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 73 COREWISE DETAILS OF 12kV NEUTRAL CT for 4MVA 33/11kV T/F (300-150/5) No. OF CORE = 1 Core Application No. 1 1 2 REF PROTECTION Current Accuracy Formula for minimum Ratio (A) class knee-point voltage At CT as per Secondary resistance at IEC 185 750C at 300A tap (Volt) 3 4 5 300-150/5 PS 95 (RCT+1) Maximum Exciting Current (mA) 6 75@ VK/2 Minimum Insulatio n Voltage (kV) 7 8.66 COREWISE DETAILS OF 420kV CAPACITOR VOLTAGE TRANSFORMER (CVT) Sl. No. 1. 2. 3. 4. Requirement Rated Primary voltage Type No. of Secondaries Rated voltage factor 5. Capacitance (minimum) 6. Rated voltage (volts) 7. Application Particulars 400/√3kV Single phase 3 1.2 continuous & 1.5 for 30 seconds 8800 (+10%, -5%) pico farads Secondary-I Secondary-II Secondary-III 110/√3 110/√3 110/√3 Metering & Protection Metering Protection 1/3P 3P 0.2 100 50 50 As per ISS/IEC 8. Accuracy 9. Output burden (VA) 10 Percentage voltage error & phase displacement (minutes) for respective specified accuracy classes. Note:- Each winding shall fulfill its respective specified accuracy requirement within its specified output range whilst at the same time the other winding has an output of any value form zero to 100% of the output range specified for the other winding in line with clause 6.2.1 of IS 3156 (Part-2 & Part-3) 1992 or its equivalent IEC. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 74 COREWISE DETAILS OF 245kV CAPACITOR VOLTAGE TRANSFORMER (CVT) Sl. Requirement Particulars No. 11. Rated Primary voltage 220/√3kV 12. Type 13. No. of Secondaries 3 14. Rated voltage factor 1.2 continuous & 1.5 for 30 seconds 15. Capacitance (minimum) 16. Rated voltage (volts) 17. Application Single phase 8800 (+10%, -5%) pico farads Secondary-I Secondary-II Secondary-III 110/√3 110/√3 110/√3 Protection & Protection Metering Measurement 18. Accuracy 1/3P 3P 0.2 19. Output burden (VA) 100 50 10 20. Percentage voltage error & phase displacement (minutes) for respective specified accuracy classes. Note:- As per ISS/IEC Each winding shall fulfil its respective specified accuracy requirement within its specified output range whilst at the same time the other winding has an output of any value form zero to 100% of the output range specified for the other winding in line with clause 6.2.1 of IS 3156 (Part-2 & Part-3) 1992 or its equivalent IEC. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 75 COREWISE DETAILS OF 245kV POTENTIAL TRANSFORMER (PT) Particulars Requirement Sl. No. 1. 2. 3. 4. 5. Rated Primary voltage Type No. of Secondaries Rated voltage factor Rated voltage (volts) 6. Application 7. 8. 9. Accuracy Output burden (VA) Percentage voltage error & phase displacement (minutes) for respective specified accuracy classes. Each winding shall fulfil its respective specified accuracy requirement within its specified output range whilst at the same time the other winding has an output of any value form zero to 100% of the output range specified for the other winding in line with clause 6.2.1 of IS 3156 (Part-2 & Part-3) 1992 or its equivalent IEC. Note:- 220/√3kV Single phase 2 1.2 continuous & 1.5 for 30 seconds Secondary-I Secondary-II 110/√3 110/√3 Protection & Protection Measurement 1/3P 3P 150 50 As per ISS/IEC COREWISE DETAILS OF 145kV CAPACITOR VOLTAGE TRANSFORMER (CVT). Sl. No. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. Note:- Requirement Particulars Rated Primary voltage Type No. of Secondaries Rated voltage factor Capacitance (minimum) Rated voltage (volts) 132√3kV Single phase 3 1.2 continuous & 1.5 for 30 seconds 8800 (+10%, -5%) pico farads Secondary-I Secondary-II Secondary-III 110/√3 110/√3 110/√3 Application Protection & Protection Metering Measurement Accuracy 1/3P 3P 0.2 Output burden (VA) 50 25 10 Percentage voltage error & As per ISS/IEC phase displacement (minutes) for respective specified accuracy classes. Each winding shall fulfil its respective specified accuracy requirement within its specified output range whilst at the same time the other winding has an output of any value form zero to 100% of the output range specified for the other winding in line with clause 6.2.1 of IS 3156 (Part-2 & Part-3) 1992 or its equivalent IEC. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 76 COREWISE DETAILS OF 145kV POTENTIAL TRANSFORMER (PT). Particulars Requirement Sl. No. 1. 2. 3. 4. 5. Rated Primary voltage Type No. of Secondaries Rated voltage factor Rated voltage (volts) 6. Application 7. 8. 9. 132/√3kV Single phase 3 1.2 continuous & 1.5 for 30 seconds Secondary-I Secondary-II Secondary-III 110/√3 110/√3 110/√3 Protection & Protection METERING Measurement 1/3P 3P 0.2 250 25 20 As per ISS/IEC Accuracy Output burden (VA) Percentage voltage error & phase displacement (minutes) for respective specified accuracy classes. Note:- Each winding shall fulfil its respective specified accuracy requirement within its specified output range whilst at the same time the other winding has an output of any value form zero to 100% of the output range specified for the other winding in line with clause 6.2.1 of IS 3156 (Part-2 & Part-3) 1992 or its equivalent IEC. COREWISE DETAILS OF 72.5kV CAPACITOR VOLTAGE TRANSFORMER (CVT). Requirement Particulars Sl. No. 1. 2. 3. 4. 5. 6. Rated Primary voltage Type No. of Secondaries Rated voltage factor Capacitance (minimum) Rated voltage (volts) 7. Application 8. 9. 10. 66/√3kV Single phase 2 1.2 continuous & 1.5 for 30 seconds 8800 (+10%, -5%) pico farads Secondary-I Secondary-II 110/√3 110/√3 Protection & Metering Measurement 1/3P 0.2 50 10 As per ISS/IEC Accuracy Output burden (VA) Percentage voltage error & phase displacement (minutes) for respective specified accuracy classes. Note:- Each winding shall fulfil its respective specified accuracy requirement within its specified output range whilst at the same time the other winding has an output of any value form zero to 100% of the output range specified for the other winding in line with clause 6.2.1 of IS 3156 (Part-2 & Part-3) 1992 or its equivalent IEC. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 77 COREWISE DETAILS OF 72.5kV POTENTIAL TRANSFORMER (PT). Sl. Particulars Requirement No. 1. Rated Primary voltage 66/√3kV 2. Type Single phase 3. No. of Secondaries 2 4. Rated voltage factor 1.2 continuous & 1.5 for 30 seconds 5. Rated voltage (volts) Secondary-I Secondary-II 110/√3 110/√3 6. Application Protection & Protection Measurement 7. Accuracy 1/3P 3P 8. Output burden (VA) 250 25 9. Percentage voltage error & As per ISS/IEC phase displacement (minutes) for respective specified accuracy classes. Note:Each winding shall fulfil its respective specified accuracy requirement within its specified output range whilst at the same time the other winding has an output of any value form zero to 100% of the output range specified for the other winding in line with clause 6.2.1 of IS 3156 (Part-2 & Part-3) 1992 or its equivalent IEC. COREWISE DETAILS OF 36kV POTENTIAL TRANSFORMER (PT) OF 2 CORES. Sl. Requirement Particulars No 1. Rated Primary voltage 33/√3kV 2. Type Single phase 3. No. of Secondaries 2 4. Rated voltage factor 1.2 continuous & 1.5 for 30 seconds 5. Rated voltage (volts) Secondary-I Secondary-II 110/√3 110/√3 6. Application Main metering Metering & Protection 7. Accuracy 0.2 1/3P 8. Output burden (VA) 10 50 9. Percentage voltage error As per ISS/IEC & phase displacement (minutes) for respective specified accuracy classes. Note:Each winding shall fulfil its respective specified accuracy requirement within its specified output range whilst at the same time the other winding has an output of any value form zero to 100% of the output range specified for the other winding in line with clause 6.2.1 of IS 3156 (Part-2 & Part-3) 1992 or its equivalent IEC. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 78 ANNEXURE-C TRANSMISSION LINE DATA (TENTATIVE) --------------------------------------------------------------------------------------------------------------------------------Sr. Name of Circuit Line Conductor size No. length Sq. inch ACSR in KM. Copper equivalent --------------------------------------------------------------------------------------------------------------------------------- --------------------------------------------------------------------------------------------------------------------------------* The line lengths and conductor size shall be supplied to successful Bidder. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 79 ANNEXURE-D SCHEDULE OF DEVIATIONS FROM THE SPECIFICATION In the table the Bidder shall set out all deviations clause by clause from the specification of the equipment offered. The bid shall be deemed to conform to Purchaser's specification in all respects unless specifically mentioned in this table. Sr.No. ------ Clause No. ---------- Detailed deviations with justification. -------------------------------------- E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 80 ANNEXURE-E LINE PARAMETERS (per UNIT)/100 MVA BASE/100 km WITH CONDUCTOR SIZE & POWER CAPACITY No.of Ckt. Conduct or size (inch2) Resistan ce R Ω Reactanc e X Ω Susceptan ce Y Ω Resistanc e R0 Ω Reactanc e X0 Ω Line Capacity (MW ) 220 D/C 0.40 0.0088 0.0443 0.2700 0.05109 0.21666 300 220 S/C 0.40 0.0176 0.0886 0.1350 0.05951 0.26180 150 132 D/C 0.20 0.0445 0.1167 0.0970 0.15648 0.64289 112 132 S/C 0.20 0.0890 0.2335 0.0485 0.19776 0.76814 56 66 D/C 0.15 0.2347 0.4637 0.0272 0.71210 2.70857 50 66 S/C 0.15 0.4695 0.9275 0.0136 0.93744 3.20761 25 Volta ge (kV) Remarks: 1. Size of Earth wire for:220 kV = 7/3.15 mm 132 kV = 7/2.5 mm 66 kV = 7/2.5 mm 2. Resistance of conductor at 20 C. 3. Resistivity of Earth Assumed = 100. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 81 ANNEXURE-F DETAILS OF CARRIER EQUIPMENT The carrier terminals available in carrier equipment for feeders are as under:- CARRIER BOOST CARRIER SEND (MAIN-I) CARRIER SEND (MAIN-II) + VE + VE - VE DIRECT TRIP (SEND) + VE - VE CARRIER HEALTHY (MAIN-I) CARRIER HEALTHY (MAIN-II) CARRIER SIGNAL RECEIVE (MAIN-I) CARRIER SIGNAL RECEIVE (MAIN-II) DIRECT TRIP (RECEIVE) E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-3 C&R Panel (with automation) including SAS Spec..doc 82 HARYANA VIDYUT PRASARAN NIGAM LTD. TECHNICAL SPECIFICATIONS FOR INTERUTILITY METERING SYSTEM AND COMMON METER READING INSTRUMENT (CMRI) TECHNICAL SPECIFICATION FOR INTERUTILITY METERING SYSTEM 1.0 The specification covers the design, manufacturing, testing, inspection, delivery of interutility metering system and /or common meter reading instrument (CMRI). 2.0 The energy meters specified herein shall be used for tariff metering for bulk, Inter -utility power flows in HVPNL/DISCOM. The meters shall be installed on each circuit as a self contained device for measurement of active energy & reactive energy in each successive 15-minute block and certain other functions as described in the following paragraphs. 3.0 The meters shall be suitable for being connected through Test terminal blocks to the voltage transformer having a rated secondary line to line voltage of 110 V, and to current transformers having a rated secondary current of 1 A. Any further transformer/transducers required for their functioning shall be in built in the meters. Necessary isolation and / or suppression shall also be built in for protecting the meters from surges and voltage spikes that occur in the VT/CT circuits of the switchyards. The reference frequency shall be 50Hz. 4.0 The microprocessor based 3 phase 4 wire meters shall conform to class 0.2S as per IS 14697 for Indian manufacturers or IEC- 62053-22 (2003) for foreign manufacturers & technical specification and meter shall be stand alone type. The meters shall bear BIS certification mark, if required as per Govt. of India Gazette notification. It will be the responsibility of the bidder to get these meters marked with BIS certification. The BIS certification shall be supplied with the tender. 5.0 Meters shall be supplied with associated TTBs. The Meters shall have following features: - a) Meter shall be stand alone type. b) For transfer of data, system should have multiple communication ports as described in the following paragraphs 6.0 The active energy measurement (Wh) shall be carried out on 3 phase 4 wire principle with an accuracy as per class 0.2S of IS 14697/IEC- 62053- 22 (2003) In the meters the energy shall be computed directly in CT/VT secondary quantities and indicated in Watt-hours. The meters shall compute the net active energy (Wh) sent out from the Sub-Station during each successive 15 minute block, and store in its memory along with +/- sign. It shall also display on demand the net WH sent out during the previous 15 minute block, with a minus sign if it is a net Wh receipt. 7.0 Further, the meter shall continuously integrate and display on demand the net cumulative active energy sent out from the Sub-Station upto that time. The cumulative Wh reading at each midnight shall be stored in the meter’s memory. The register shall move backwards when active power flows backwards into the Sub-Station. 8.0 The meter shall count the number of cycles in VT output during each successive 15-minutes block, and divide the same by 900 to arrive at the average frequency. This shall be stored in the meter’s memory as a 2-digit code which shall be arrived at by subtracting 49.5 from the average frequency, multiplying by 100 and neglecting all decimals. For example, 49.89 Hz shall be recorded as 39. In case the average frequency is less than 49.5 Hz, it shall be recorded as 00. In case it is 50.5 Hz or higher, it shall be recorded as 99. The average frequency of the previous 15-minutes block shall also be displayed, on demand in hertz. The accuracy of the voltage measurement / computation shall be at-least 0.5%, a better accuracy such as 0.2% in the 95-105% range being desirable. 9.0 The meters shall continuously compute the average of the RMS value (fundamental only) of the three lines to neutral VT secondary voltage as a percentage of 63.51 V and display the same on demand. 10.0 The meter shall also compute the reactive power (VAR) on 3 phase 4 wire principle. Limits of error shall be corresponding to class 1.0 as per IS 14697 for reactive energy for Indian manufacturers or half (50%) of those permitted corresponding to class 2.0 for reactive energy as per IEC 62053-23 (2003) for foreign manufacturers, and integrate the reactive energy (VARh) algebraically in 2 separate registers, one for the period for which the average RMS voltage is 103% or higher and the other for the period for which the average RMS voltage is below 97%. The current reactive power (VAR) with a minus sign if negative, and cumulative reactive energy (VARh) reading of the 2 registers shall be displayed on demand. The readings of the 2 registers at each midnight shall also be stored in the meter's memory. In the meter, the reactive power and reactive energy transmittals shall be computed in VAR/VARh directly calculated in VT and CT secondary quantities. When lagging reactive power is being sent out from the Sub-Station. VAR display shall have no sign and VARh registers shall move forward. When reactive power flow is in the reverse direction. VAR display shall have a negative sign and VARh registers shall move backwards. 11.0 The meter shall fully comply with all the stipulations of IS 14697/IEC- 60687-2000 (or latest revision) for class 0.2S for static watt-hour meters except those specifically modified by this specification. The reference ambient temperature shall be 50 deg. C. 12.0 Error shall be as per IS-14697/ IEC- 62053- 22 (2003) for all power factor angles from 0 deg. to 360 deg. 13.0 Each meter shall have a test output device (visual) for checking the accuracy of active energy Wh and reactive energy (VARh) measurement using a suitable test equipment. The test output shall be software configurable for active energy import/export and reactive energy import/export. 14.0 No rounding off to the next higher last decimal shall be done for voltage and frequency displays. 15.0 5) There shall be provisions of below mentioned Tempers and Events in the Interutility Meters of 0.2S accuracy class:Tempers:Current Reversal/Current Failure/Current Unbalance/Current bypass. Magnetic Tempering. Under voltage/Voltage unbalance. Abnormally Low PF 0.45 (lag or lead) of any of the phases indicative of phase sequence mismatch in 3-phases. Power on/off. 15.2 Events:- 1) Over Voltage:- If any of the phase voltage is more than 110% of rated voltage & it is continuing for more than 15 minutes, meter records over voltage as an event. 2) Under Voltage:- The three line to neutral voltages shall be continuously monitored by individual phase wise LED's, and in case any of these falls below 70%, the normally flashing lamp provided on the meters front becomes steady. The time blocks in which such a voltage failure occurs/persist shall also be recorded in the meter's memory. The lamp shall automatically resume flashing when corresponding VT secondary voltage is healthy again. LCD indication are 15.1 1) 2) 3) 4) also acceptable. The two VARh registers specified in clause-10 shall remain stay-put while VT supply is unhealthy. This feature shall be recorded as an event. 16.0 17.0 18.0 19.0 The meters shall operate with the power drawn from the VT secondary circuits, without the need for any auxiliary power supply. The total burden imposed by a meter for measurement and operation shall not exceed 10 VA on any of the phases. An automatic backup for the continued operation of the meter's calendar clock shall be provided through a long life battery, which shall be capable of supplying the required power for atleast two years. The meters shall be supplied duly fitted with the battery which shall not require to be changed for atleast 10 years, as long as total VT supply interruption does not exceed two years. The battery mounting shall be designed to facilitate easy battery replacement without affecting PCB of meter. Each meter shall have a built-in calendar and clock, having an accuracy of 30 seconds per month or better. The calendar and clock shall be correctly set at the manufacturer's works. The date (day-month-year) and time (hour-minute-second) shall be displayed on the meter front on demand. Clock adjustment shall be possible at site using the Meter Reading Instrument (MRI) or remotely using time synchronization signal through RS 485. For the purpose of getting the standard time, the computer (s) from where the meter will be read shall be equipped with GPS signal receiver. This computer and the GPS receiver, however, are not in the scope of this specification. When an advance or retard command is given, six subsequent time blocks shall be contracted or elongated by 10 seconds each. The meter shall not accept another clock correction command for seven days. The meter time shall automatically be corrected every time the remote computer interrogates it. All clock corrections shall be registered in the meter's memory and shall be suitably shown on the print out of the collected data Each meter shall have a unique identification code, which shall be marked permanently on the front as well as in its memory. All meters supplied to HVPN, as per this specification shall have their identification code starting with HVPN, which shall not be used for any other supply. HVPN shall be followed by a dash and a four digit running serial number. The series of four digit running serial no. indicating the unique identification code of each meter shall be provided by HVPN to the successful bidder. The measured value(s) shall be displayed through LED/back-lit LCD display with proper identification for indication of the following (one at a time) on demand. 19.1 Meter Serial No. 19.2 Date (dd-mm-yy) 'd' 19.3 Time (hr-min-sec) 't' 19.4 Cumulative Wh reading 'c' 19.5 Average frequency of the previous 15-minute block 'F' 19.6 Net Wh transmittal in the previous 15-minute block, with +/- sign 'E' 19.7 Average percentage voltage 'U' 19.8 Reactive power (VAR) with +/- sign 'r' 19.9 Voltage high VARh register reading 'H' 19.10 Voltage-Low VARh register reading 'L' 19.11 Low Battery Indication 20.0 A keypad or scrolling facility shall be provided on the front of the meter for switching on the display of the meter parameters selected and for changing from one indication to next. 21.(A) Meter shall have a non-volatile memory in which the following shall be automatically stored. 21.1 21.2 21.3 21.4 21.5 21.6 21.(B) Average frequency for each successive 15-minute block upto second decimal/as a two-digit code. Net Wh transmittal during each successive 15-minute block upto second decimal/with plus minus sign. Cumulative Wh transmittal at each midnight in 7 digits including one decimal. Cumulative VARh transmittal for voltage high condition, at each midnight in 7 digit including one decimal. Cumulative VARh transmittal for voltage low condition, at each midnight in 7 digit including one decimal. Date & time blocks of failure of VT supply on any phase, as a star (*) mark. Battery backed memory shall not be accepted. 22.0 The meter shall store all the above listed data in their memories for a period of The data older than 35 days shall get erased automatically. 23.0 CMRI/DCD: To ensure inter operability of system at the meter reading instrument end, the common meter reading instrument (CMRI) or data collection devices (DCD) confirming to DOS platform and having min. 16 MB memory shall be used to enable different manufacturers to download into same hand held terminal & the meters of various makes to be read through the same hand held terminal. Each CMRI shall be complete with:- i) ii) iii) iv) v) 35 days. a lead with optical head for coupling it to the meter, a lead for plugging it to a personal computer; an internal battery for powering the devices; a case for safely carrying it about a battery charger The total arrangement shall be such that one (1) operation can carry out the whole operation, in about five (5) minutes per meter. Portable Meter Reading Instruments (MRI)/data collection devices (DCD) shall have a key for starting the data tapping from the coupled meter’s memory, a key to start data transfer to the PC, and a lamp, which would light up on completion of data collection, remain ‘on’ while the data is held in the device and would go ‘off’ when all data has been transferred to the PC. Data tapping operation from CMRI/DCD shall not erase the data from the meter’s memory, or effect the meter operation in any way. The memory of the CMRI/DCD shall get automatically cleared when the data has been transferred to the PC only then the CMRI/DCD shall accept data from another meter. CMRI/DCDs shall also have necessary provision for meter clock correction. CMRI/ DCDs shall be compatible with earlier supplied meters in regard to data downloading etc. 23.1 Each meter shall have an optical communication port compatible to RS 232 on its front for tapping all data stored in its memory. In addition to the above each meter shall be provided with a RS485 port on one of its sides, from where all the data stored in the meter’s memory can also be tapped. Portable Meter Reading Instruments (MRI)/data collection devices (DCD) of SANDS, ANALOGIC make have already been provided separately for this purpose, one for each SubStation, to serve as interface between the meters specified above and the local PC. Meter shall be compatible with earlier supplied CMRI/DCD. Each meter shall be provided with a lead having optical head for coupling the meter to CMRI/DCD. 23.2 i) ii) iii) iv) v) vi) Software Package: The existing metering system records all the parameters required for the Availability Based Tariff. Suitable software for CMRI shall be provided by the bidder for smooth downloading of the data to/ from the CMRI. For data analysis & billing, the different meter manufacturers shall provide the meter reading software to interpret the data collected through CMRI or through RS485 for conversion into a common ASCII format. The Data of the existing meters is available in the specified ASCII Format; details of which are enclosed at Annexure-II (Page1 to 3). A similar output in the same ASCII format (space delimited, fixed length values) shall be made available from the new meters by the successful bidder for future use of data for generation of BST & ABT Bills/Reports or any other purpose. In addition to this successful bidder shall make provision to supply load survey data in Excel format as per Annexure-III.The supplier shall provide above software which would enable a local PC to:accept the data from the CMRI and/or from a interface device connected to the optical port/RS485 port and store it in it’s memory in binary read only format. Polling feature along with a task scheduler to run the data downloading software at a predesignated date and time repeatedly or by manually selecting a meter. A detailed activity log shall also be available for each downloading operation. Display the collected data on PC’s screen on demand as per annexure-II & III in text format, with forward/backward rolling. Print out in text format the data collected from one or more meters as per annexure-II & III, starting from a certain date and time, as per operator’s instructions. Transmit the collected data, in binary format, through an appropriate communication link to the central computer, starting from a certain date and time, as per operator’s instructions. Store the collected data, in binary format, on a floppy disc/CD/Pen drive/DVD. The above software shall further ensure that absolutely no tampering (except total erasures) of the collected metering data is possible during its handling by the PC. The software shall be suitable for the commonly available PCs and shall be supplied to owner in a compatible form to enable its easy loading into the PC’s available at the various Sub-Stations/Energy Accounting Centre. 23.3 The overall intention is to tap the data stored in the meter memory at any time from any of the two ports mentioned above and transmit same to a remote centre computer using communication links, through the local PC. It should also be possible to obtain a print out (hard copy) of all data collected from the meters, using the PC. The received/ downloaded meter data should be the original output from the meter. 23.4 As a part of commissioning the Contractor shall load the software in the PCs at the respective substations, and fully commission the total meter reading scheme. He shall also impart the necessary instructions to substation engineers. 24.0 The whole system shall be such as to provide a print out (both from the local PC and the remote central computer) of the following form: 23 55 +16.28 56 +15.95 55 +15.32 54 +15.66 55 +14.93 55 +14.26 54 +14.85 56 +15.17 HVPNL **** 12345.6 01234.5 00123.4 99-04-28 57 +14.72 56 +13.83 55 +13.57 53 +12.91 01 52 +13.34 51 +12.76 52 +14.11 52 +15.28 25.0 All the meters shall be identical in all respects except for their unique identification codes. They shall also be totally sealed and tamper proof, with no possibility of adjustment at site except for a restricted clock correction. 26.0 The meter shall safely withstand the usual fluctuations arising during faults in particular, VT secondary voltage 115% of rated applied continuously and 190% of rated for 3 seconds and CT secondary current 150% of rated applied continuously and 30 times of rated applied for 0.5 seconds, shall not cause any damage to or the mal-operation of the meters. 27.0 The meter shall continue to function for remaining healthy phase(s), in case of failure of one or two phases of VT supply. In case of a complete VT supply failure, the computation of average frequency (as per 8.0) shall be done only for the period during which the VT supply was available in the 15-minute block. Any time block contraction or elongation for clock correction shall also be duly accounted for. 28.0 The harmonics shall be filtered out while measuring the Wh, VAR and VARh and only fundamental frequency quantities shall be measured or computed. 29.0 VOID 30.0 VOID 31.0 Every meter shall be indelibly marked with connection diagram showing the phase sequence for which it is intended and shall be attached on the meters. In case of any special precautions need to be taken at the time of testing the meter, the same shall be indicated alongwith the circuit diagram. 32.0 VOID 33.0 Sealing arrangement: Sealing arrangement for meters and TTBs shall be provided as under: 33.1 TTBs: Each TTB shall have the provision for two seals. 33.2 Meters: Meter body or cover & meter terminal blocks shall be sealable including each optical communication port. 34.0 The meters shall be supplied housed in compact and sturdy; metallic or moulded cases of nonrusting construction and/or finish. The cases shall be designed for simple mounting on a plane, vertical surface such as a control/relay panel front. All terminals for CT and VT connections shall be arranged in a row along the meter’s lowerside. Terminals shall have a suitable construction with barriers and cover, to provide a secure and safe connection of CTs and VTs leads through stranded copper conductors of 4.0 sq. mm. size. The meters shall also withstand without any damage or maloperation reasonable mechanical shocks, earthquake forces, ambient temperature variations, relative humidity etc. They shall have an IP-51 category dust-tight construction, and shall be capable of satisfactory operation in an indoor, non-air conditioned installation. The contractor shall be responsible for total installation and commissioning of the meters (alongwith test blocks, if supplied separately)as per Owner’s advice, including unpacking and inspection on receipt at site, mounting the meters on existing control and relay panels at an appropriate viewing height., connection of CT and VT circuits including any required rewiring (however, supply & installation of 4cx4mm2 control cables (laid through 2.5’ dia HDD PVC Pipe) from CT, VT to metering system are not in the scope of this specification), functional testing, commissioning and handing over. The Contractor’s personnel shall procure/carry the necessary tools, equipment, materials and consumables (including insulated wires, lugs, ferrules, hardware etc.). 35.0 Inspection & Testing: 35.1 Type Tests: The meter should be fully type tested as per IS 14697 for Indian Manufacturers or IEC-62053-22 (2003) & IEC-62053-23 (2003) for foreign manufacturers. 35.2 Routine Tests: All Routine tests as per IS 14697 shall be carried out by the supplier on the meters for compliance in both directions of power flow. 35.3 Acceptance Tests: All equipment, after final assembly and before despatch from manufacturer's works shall be duly tested as per IS 14697 for compliance in both directions of power flow in presence of purchaser's representative, unless dispensed with in writing by the purchaser. In addition, the following acceptance tests shall also be conducted:1. Functional checks for display and memory. 2. Accuracy of voltage and frequency measurement. All DCDs/MRIs after final assembly and before dispatch from Manufacturer’s works shall be duly tested to verify that they are suitable for supply to the purchaser. In particular, each and every DCD/MRI shall be subjected to the following acceptance test:1. Functional checks 2. Downloading Meter Data from the Meter(s). 3. Compatibility with PC software 4. Downloading the meter data on PC 5. Functioning of advance and retard time commands. 6. Per meter downloading time verification 7. Capacity of DCD/MRI for data storage. 36.0 Quality Assurance The quality control procedure to be adopted during installation of the specified equipment shall be mutually discussed and finalized in due course, generally based on the established and proven practices. 37.0 Any meter, which fails to fully comply with the specification requirements, shall be liable to be rejected by the purchaser. 38.0 VOID 39.0 39.1.1 Following technical information shall be furnished by the bidders in their offers.: The prospective bidder shall be required to submit complete type test reports from Govt. approved laboratory alongwith bid. The type test reports shall not be more than seven years old reckoned from the date of opening of part-1 tender. 39.2 Guaranteed Technical Particulars as per Annexure-I. 40.0 SERVICE CONDITIONS Equipment to be supplied against this specification shall be suitable for satisfactory continuous operation under the following tropical conditions:i. Location IN THE STATE OF HARYANA ii. Max. ambient air temp (0C) 50 iii. Min. ambient air temp (0C) -2.5 iv. Maximum Relative humidity (%) 100 v. Minimum Relative humidity (%) 26 vi. Average annual rainfall (mm) 900 vii. Max. wind pressure (Kg/sq.m.) 195 viii. Max. altitude above mean sea level 1000 (meters) ix. Isoceraunic level (days/year) 50 x. Seismic level (horizontal acceleration) 0.3g Note: Moderately hot and humid tropical climate conducive to rust and fungus growth. The climatic conditions are also prone to wide variations in ambient conditions. Smoke is also present in the atmosphere. Heavy lightening also occur during June to October. Annexure-I GUARANTEED TECHNICAL PARTICULARS FOR THREE-PHASE FOUR WIRE CLASS 0.2S ACCURACY POWER MONITORING SYSTEM. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27. 28. Maker’s name and country Type of Meter/Model Standards to which the meter conform Accuracy class Parameters measured P.F. Range Overload capacity Variation of voltage at which system function normally Minimum starting current MD reset provisions Reset count No. of digits of display Particulars of readout by CMRI Non volatile memory retention time in absence of power Memory capacity (kb) Demand integration period Pulse output for each meters Metrology indicator for each meters Communication capability on a. Local port b. Remote port Load survey parameters Power Consumption per phase i) Voltage circuit. ii) Current circuit. Self diagnostics features, if any (Provide details) Principle of operation (Provide details) Foreseen dimensions of proposed meter. Expected weight of proposed meter Foreseen dimensions of DCD/MRI. Expected weight of DCD/MRI. Dimensions and weight of the test block, if supplied separately. Annexure-G TYPICAL ARCHITECTURAL DRAWING OF SUBSTATION AUTOMATION SYSTEM Router HMI View Node Gateway Station HMI GPS DR Work Station Redundant Managed Ethernet Station Bus Clock IEC 61850 IEC 61850 Switch for Dia 1 Switch for Dia. 3 Switch for Dia. 2 Switch for Dia. N Fibre optic Connection IEC 61850 IEDs for Control & protection IEDs for Control & protection IEDs for Control & protection IEDs for Control & protection Note: 1. The redundant managed bus shall be realized by high speed optical bus using industrial grade components and shall be as per IEC 61850. 2. (Applicable only for 400 kV and 220 kV substations): The IEDs and switches for each of the dia. of 765kV and 400kV shall have separate kiosk. For 220kV, 132kV, 66kV yards, IEDs for two adjacent bays can be housed in one Kiosk along with its switch. For 220/33kV T/F, IEDs for four adjacent 33kV bays can be housed in one Kiosk along with its switches and For 132/33kV T/F, IEDs for all 33kV bays of a T/F can be housed in one Kiosk along with its switches. Note: For 132 kV and 66 kV substations the control and relay panels shall be housed in the control room building itself. 3. Inside the sub-station, all connections shall be realized as per IEC 61850 protocol. 4. For gateway, it shall communicate with Remote Supervisory Control Centre (RSCC) on IEC 60870-5-101 protocol. 5. The router to Remote Control Centre (RCC) shall communicate on IEC 608705-101 protocol. 6. The printer as required shall be connected to station bus directly and can be managed either from station HMI, HMI view node or disturbance recorder work station. 33 E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-5 Chapter-5 SAS Arch..doc SECTION-6 CHAPTER 1 TECHNICAL SPECIFICATION OF 415 VOLTS L.T. SWITCH BOARDS. 1. SCOPE : This specification covers design, Engineering, manufacture, stage testing, inspection and testing before despatch, packing, forwarding and delivery at site of 415 Volts AC LT Switch Board complete with all fittings, accessories and associated auxiliary equipment mandatory spares as per Volume II which are required for efficient and trouble free operation as specified hereunder. It is not the intent to specify herein all the details of design and construction of equipments. However, the equipment shall conform in all respects to the high standards of engineering, design and workmanship and shall be capable of performing in continuous commercial operation up to the Bidder’s guarantee in a manner acceptable to the Purchaser. The equipment offered shall be complete with all components necessary for its effective and trouble free operation along with associated equipment, interlocks protection schemes etc. irrespective of whether those are specially brought out in this specification and commercially added or not. All similar parts particularly movable ones shall be interchangeable. 1.02 CLIMATIC CONDITIONS : The equipment is required to operate satisfactorily under the following site conditions:i. ii. iii. Max. Temperature Min. Temperature Relativehumidity a) Max. b) Min. iii. Average number of rainy days per annum iv. Average rain fall per year. v. Average number of dust storm days per annum vi. Isoceraunic level vii. Max. Wind pressures viii. Altitude above mean sea level 500C -2.50C 100% 26% Nearly 120 days 900 mm 35 45 195 kg/sqmt. Less than 1000 mt. 1.03 STANDARDS: The metal clad (preferably sheet metal) air break switch to be supplied against this Specification shall meet with the requirements laid down in IS-4064-1978 (part I & II) (latest edition). The HRC fuses shall comply with the Is-2208-1962 (latest amended). All other equipments shall also comply with the requirements of the latest edition of the respective Indian Standards. 1.04 MATERIAL AND WORKMANSHIP: All the materials used in the construction of the equipment shall be of the best quality obtainable of their respective kinds and whole of the work shall be of the highest class, well finished and of approved design and make of the true form and dimensions. All machined surfaces shall be true and smooth and well finished. 1.05 INTER CHANGEABILITY: Corresponding parts of plant and equipment shall be made to gauge or jig and shall be interchangeable in every respect. 1.06 DOCUMENTATION The successful bidder shall submit four sets of drawings for HVPNL approval. NOTE: All above drawings should be a minimum space (14x10cm) for stamping the approval of drawings by HVPNL. 1.07 1.08 FOUNDATIONS AND FIXINGS: All plants and equipment shall be provided with a complete set of foundation holding down bolts, washers, nuts plants and other fixtures as may be required and these shall be supplied by the contractor. These fittings will be fixed by the purchaser on the foundations unless otherwise specified. INSTRUCTION AND MARKING PLATES: All gauge meters, instruments etc. shall have dials or scales calibrated in metric system of units. All name plates, instruction plate, warning signs and any marking what-so-ever on the equipment and its parts and accessories shall be in Hindi-English Language, using idioms, words and meaning as in current use in India. In order to facilitate sorting and erection at site every part of the plant and equipment shall be suitably marked. 1.09 PAINTING The whole of the plant except bright parts, valves and such portions as are finished shall be painted with two painting coats of approved rust resisting paint in plain colours for packing and the parts not so painted shall be protected from deterioration during transit. All the ferrous parts shall be painted with battle ship grey paint by means of spray painting. The painting should be as per relevant ISS. All the non ferrous parts including the bus bars, thimbles, jumpers shall be tinned plated and sleeves of proper thickness and size shall be provided on all the jumpers. After erection at site every painted part shall be well cleaned filed and chopped and shall then receive two coats of best oil paint of approved colour, to be supplied by the contractor without any extra cost. 1.10 TESTS: 1.10.1 TYPE TEST The equipment should be offered type test. Test reports should not more then seven years old reckoned from date of bid opening in respect of all the tests carried out in accredited laboratories (based on ISO/IEC) by a reputed accreditatic body or witnessed by HVPN or another electric power utility and be submitted by the successful bidder to HVPNL for approval as schedule given in Bar Chart. 1.10.2 Routine Test As per quality assurance program (QAP). 1.10.3 Acceptance Test The following acceptance tests shall be carried out by the Supplier in presence of HVPNL representative, unless dispensed with in writing by the HVPNL. i) Dimensional test ii) Continuity test iii) Insulation resistance test iv) High voltage test v) Inter locking test 1.11 INSTRUCTION BOOKS: Applicable parts, lists, catalogues and operating instructions in English Language specially prepared to cover all the equipment furnished under this specification which may be needed or prove useful in operation, maintenance, repair, dismantling or assembling and for the repair and identification of parts for ordering replacements shall be assembled under a common cover and submitted in duplicate for each unit to the purchaser free of cost. 1.12 REPRODUCIBLE DRAWINGS: The contractor shall supply two sets of full size reproducible drawings (approved by the purchaser) along with detailed drawings of various major components/accessories etc. (showing sectional views, wherever necessary) on oil cloth to prove useful in the erection, operation maintenance and repair of the equipment. He shall also supply twenty sets of azo prints of the above mentioned drawings for use in field and design offices. 1.13 PARTICULARS OF THE SYSTEM: The equipment shall be suitable for 415 Volts 50 cycles, 3 Phase 4 wire system with neutral solidly earthed. 1.14 RISE IN TEMPERATURE: The equipment shall be operated at maximum ambient temperature of 500C and as such the temperature rise of its parts should be proportionately below the figure provided in respective standards. 1.15 EACH SWITCH SHALL COMPRISE OF: Metal clad floor mounting combination fuse switch board consisting of a suitable bus bar of 320 Amps rating for 15 Ckts. Triple pole and neutral bus bar chamber, mounted on a high floor stand arranged and equipped for the circuits given in the schedule of requirement and mounted above and below the bus bar chamber to form a suitable arrangement. The bus bar chamber shall have provision for adding two more switch units as given in the schedule at a later date. The switches shall be quick make and break type. The switch boards shall be installed indoors. The enclosing chambers shall be dust-tight and vermin proof. All equipments shall be suitable for reception of Alumiium cable rising from the ground. The details of equipment required for each switch board has been given in the schedule of requirement. 1.16 BUS BARS: The bus shall be made of high conductivity copper or Aluminium and shall have adequate cross section so as to be capable of carrying 300 Amps in phase and 150 Amps. in neutral. The bus bar shall be so designed and mounted in the separate chamber such that their expansion or contraction does not subject either the bus bars or their insulation supports to any stresses. The bus bar shall be properly spaced so as to provide easy access during maintenance and inspection etc. There should be no joints in the bus bars. The current density for copper and aluminium bus bars must not exceed 1 A/cm2 and 87 A/cm2 respectively. 1.17 CONNECTIONS: All the connections for the tee’s from the bus bars shall be bolted type and suitable spring washers shall be provided to ensure proper jointing and material of the bolts shall be of suitable metal. All the connections shall be provided with thimbles of suitable rating. 1.18 METERING EQUIPMENT Metering equipment for the station transformer/Incomer shall be located between the L.T. side of the transformer and L.T. Bus Bars. The metering equipment shall include 300/5 Amps C.T.s having burden 15 VA with accuracy class 1 and 3 phase 4wire unbalanced load integrating electronic KWH meter. A 100 mm dial flush mounted MISC (moving iron spring controlled) Voltmeter and a 100 mm dial flush mounted MISC ammeter both with phase selector switch shall also be provided on each switchboard to indicate the bus bar voltage and total load on the station transformer/Incomer feeder. All the meters shall be enclosed in separate chamber to have a flush pattern type appearance. The meters shall be dust tight. 1.19 EARTHING Two separate earths shall be run and each and every metallic parts of the stand/switches/bus bar chambers shall be earthed at two different places independently. The size of the earthing conductor for the switches and individual parts shall not be less than No. 8 SWG copper conductor and size of the main for earthing shall not be less than No. 3 SWG copper conductor. 1.20 BUS BAR CHAMBER The bus bar chamber shall be made out of angle iron of suitable size as specified below along with other details: a) Thickness of sheet steel enclosures, doors, covers i) Cold rolled 2mm minimum ii) Hot rolled +2.5mm minimum b) Degree of protection c) Colour finish shade i) Interior ii) Exterior IP-54 as per BS2817/IEC-144 Glossy white Light grey Semi glossy shade d) Earthing bus material size Copper 25x6 mm e) Purchaser’s earthing conductor Material Size Clearance in air of live parts Galvanised steel f) 30x6 mm 1.21 i) ii) LABELS: Phase to Phase Phase to earth 80 mm 80 mm Each switch shall be provided with suitable labels paginated on hard plastic sheet and duly held in boss framed of the size 75x50 mm for the incoming and outgoing feeders. The hard plastic sheet shall be of white colour and will be painted in black for the outgoing feeders whereas it shall be painted bright red for the incoming feeders. 1.22 INTERLOCKING Interlocks must be provided to ensure that the switch cover cannot be opened when the switch is in the closed position. It should however be possible for competent examiner to over ride this interlock and operate the switch with enclosure open. 1.23 FIRE HAZARDS The switch and its associated apparatus shall be arranged to minimize fire hazards. 1.24 CLEARANCES The clearances between phases and between phases and earth shall be as per IS3072-1975 with latest amendments. 1.25 CONTACTS All live contacts of the switch shall be adequately shrouded to prevent accidental contact when the equipment is either in the isolated or normal closed position and shall be silver plated of suitable thickness. The fixed contacts of the fuse switch unit shall be fully shrouded with arc resistant material. Material needs to be specified in the tender. 1.26 CABLE AND BOXES: a) The incoming switch and outgoing switches shall be provided with cable and boxes of suitable size capacity and rating suitable for PVC cables. Suitable cleating arrangement shall also be provided for the cables entering the switch fuse units in the top tier. The cabling arrangement shall be such that cables outgoing from Isolator unit can be connected or disconnected easily and safely. 1.27 RUPTURING CAPACITY The rupturing capacity of the bus bar switchgear/cartridges shall not be lower than 2 MVA at 415 volts. 1.28 The individual fuse switch unit shall be provided in such a way that they can be removed from the front of the switch board for servicing and maintenance. 1.29 a) b) c) d) e) f) g) MARKING All the switches shall be clearly marked with the following particulars: Reference to the standard. Rated voltage. Rated normal current. Rated marking capacity. Breaking capacity. Type of fuse/links to be used. Name plate. 1. 2. 3. 4. 5. 6. 1.30 a) b) c) d) e) 1.31 Supplier name. Purchaser P.O. No. Rating. Serial no. Year of manufacturing. OTHER PARTICULARS The Bidder should clearly furnish the following information in their offer: Material and plating of the contacts. Current density assumed. Temperature rise under continuous full load over the ambient temp. of 500C. Temperature rise under short circuit condition. Guaranteed Technical particulars as required in appendix-A. List of references if similar L.T. Switch Board already in service/supplied with complete details shall be furnished. ANNEXURE ‘A’ SCHEDULE OF REQUIREMENTS A. 132kV & 66kV Sub-Stations 415 V 3 Phase 4 wire L.T. Switch Board comprising of 15 circuits TP & N switch fuse units consisting of two incomer of 320 A, 1 voltmeter (0-500V) with suitable CTs and selector switch and 13 Nos. circuits of outgoing switchgear units and HRC fuses having the following ratings for 132kV & 66kV S/Stns. Sr. No. L.T.Feeders 1. Incoming from Station transformer Switch rating (Amps) 320 2. Alternate Source 320 300 1 3. Oil filtration set feeder 200 160 1 4. Colony lighting feeder 160 100 1 5. Yard lighting feeder 160 100 1 6. Transformer fans & OLTC feeder 100 63 1 7. Breakers operation feeder 32 25 1 8. Outdoor street lighting feeder 32 25 1 9. Water pump and sewerage pump 63 50 1 10. Carrier room 32 25 1 11. Battery charger 32 25 1 12. Control panel indicator 32 25 1 13. Spare feeder 160 100 1 14. Provision for additional switch fuse unit 15. To be mounted at a later stage. TOTAL Fuse rating No. (Amps) (Amps) 300 1 15 Nos. NOTES: 1. Each circuit as indicated above shall have switch rating, HRC fuse rating and LT feeder labeling as mentioned against each. It shall include bus bar connections, terminals, cable glands and cable lugs etc. 2. Each Incomer shall be provided with the following equipment: i) One 100mm dial flush mounting moving iron spring controlled (MISC) ammeter of scale of 0-300A with phase selector switch. ii) One No. 100 mm dial flush mounting MISC voltmeter of range 0-500V with phase selector switch. iii) 3 Nos. 300/5A CTs having burden 15 VA and accuracy class 1 and instrument security factor. iv) One 3 phase , 4 wire unbalanced load integrating watt hour meter (operatable on 300/5A CTs). v) TTB for LT CT meter. 3. Make of each component must be listed in bid.. 4. The bus bar shall be designed for 320 A for phase and 150 A for neutral. SECTION-6 CHAPTER-2 TECHNICAL SPECIFICATION FOR 220V (600AH / 200AH & 100AH) AND 48V (800AH / 300AH & 120AH) BATTERY BANKS 1.0 SCOPE: The scope of this specification covers design, manufacture, assembly, supply, testing at works, packing, forwarding, dispatch of VRLA batteries along with necessary accessories, fittings etc. to the destination. These equipments are to be complete in every respect, details to the functions designated to the entire satisfaction of the purchaser. It is required that the supplier accepting the contract agrees to furnish all apparatus, appliances and material whether specifically mentioned or not but which may be found necessary to complete, to perform and testing any of the herein specified equipment (s) for compliance with the requirements implied without extra charges. The erection/maintenance tools and specific tools if any will also form part of supply. 2.0 General Technical Requirement All the materials/components used in Battery Chargers and Valve Regulated Lead Acid Battery (VRLA) shall be free from flaws and defects and shall conform to relevant standards and good engineering practices:- 2.0.1 For 400 KV Sub-stations, DC System shall consist of two (2) battery sets for each of 220V and 48V systems respectively. 2.0.2 For 220 KV, 132 KV & 66 KV sub-stations, DC System shall consist of two (2) float-cum-boost charger and one (1) battery set for each of 220V and for 48V system. DC scheme shall consists of one (1) battery. 2.0.3 Bidder shall select number of cells, float and Boost voltage to achieve following requirement : System Voltage 220 Volt 48 Volt 2.1 Maximum Voltage during Float Operation 242 Volt 52.8 Volt Minimum voltage available when no charger working and battery fully discharged up to 1.85 V per cell. 198 Volt 43.2 Volt Minimum Nos of Cell 107 23 CLIMATIC CONDITIONS: The equipment to be supplied against the specification shall be suitable for satisfactory continuous operation under the following tropical conditions: Max. ambient air temperature 500 C Max. daily average ambient temperature 450 C Max. yearly weighted ambient temperature 350 C Min. air temperature (-) 50 C Max. humidity 100% Min. relative humidity 26 % Average number of thunder storm days per annum 40 Average annual rain fall 15 cm to 100 cm. Number of months during which tropical monsoon conditions prevail altitude above MSL 4 months (June to Sept). Varies from 61 meters to 815.00 mtrs. Average number of rainly days per annum. 120 days Seismic level (Horizontal acceleration) 0.3g. Degree of pollution Heavy Intensity of solar radiation 1.0 KW/sq.m. Max. Wind load 195 kg/sq.m. 3.0 Battery 3.1 Type The DC Batteries shall be Normal Discharge type Valve Regulated Lead Acid (VRLA) and shall conform to IS 15549: 2004/IEC 60896-21 & 22, 2004 standard. These shall be factory filled, charged & suitable for a long life under continuous float operations and occasional discharges. The 220 V DC systems should be unearthed and 48V DC system is Positive Earth system. Battery sets shall be capable of operating at a peak ambient temperature of 50 Deg.C. The offered battery shall be compact and shall require no maintenance. All safety equipment required for installation shall be provided by the manufacturer. 3.2 Constructional Requirement Plates: Positive plates shall be made of flat pasted type using high corrosion resistant alloy for durability, maintenance free, long life both in cyclic as well as in float applications. The Grids are of Semi Radial Squarish grid to reduce internal Resistance and travel current in shorter time. Negative plates shall be heavy duty, durable flat plate using lead alloy pasted Semi Radial Squarish Grid. Negative plates shall be designed to match the life of positive plates and combination of positive and negative plates shall ensure long life, durability and trouble free operation of battery. Computer controlled/PLC operated in house equipment should be deployed for preparation of lead oxide and paste to ensure consistency in paste quality & properties. Conventional / manual type of paste preparation will not be allowed. 3.3 Containers & Lids The container & lids shall be made of polypropylene Copolymer material and shall have chemical and electro-chemical compatibility along with acid resistant and shall conform to UL-94/ ASTM-D-2863 standard. The material shall meet all the requirements of VRLA batteries and be consistent with the life of battery. The porosity of the container shall be such as not to allow any gases to escape except from the regulation valve. The tensile strength of the material of the container shall be such as to handle the internal cell pressure of the cells in the worst working condition. The container shall be capable of withstanding the rigours of transport, storage and handling. The containers shall be enclosed in a steel tray. For identification each cell / module shall be marked in a permanent manner to Indicate the Following information. I. Cell Serial number. II. Positive and Negative is embossed on the cover III. Month and Year of manufacturing. 3.4 Cell Covers The cell covers shall be made of suitable material compatible with the container material and permanently fixed with container by Hermetic Heat Sealing technique. It shall be capable to withstand internal pressure without bulging or cracking. Fixing of pressure regulation Valve & terminals posts in the cover shall be such that the seepage of electrolyte, gas escapes and entry of electrostatic spark are prevented. 3.5. Separators The separators used in manufacturing of battery cells shall be spun glass micro porous Matrix having high acid absorption capability & resistant to battery grade Sulphuric acid along with good insulating properties. Sufficient separator overlap and PVC shield protection to bottom edges of the plates is to be provided to prevent short circuit formation between the edges of adjacent plates. 3.6. Pressure Regulation Valve Each cell shall be provided with a pressure regulation valve. The valve shall be self re-sealable. The vent plug shall be made with suitable grade of fire retardant plastic material. Each valve opening shall be covered with flame barrier capable in preventing the ingress of flame into the cell interior when the valve opens and hydrogen / oxygen gas mixture is released. The valve unit shall be such that it cannot be opened without a proper tool. 3.7. Terminal Posts Both the Positive and Negative terminals of the cells shall be capable of proper termination and shall ensure its consistency with the life of battery. The terminals shall have adequate solid copper core cross-section to avoid overheating at maximum current load. The surface of the terminal post extending above the cell cover including bolt hole shall be coated with an acid resistant and corrosion retarding material. Terminal posts or any other metal part which is in contact with the electrolyte shall be made of the same alloy as that of the plates or of a proven material that does not have any harmful effect on cell performance. Both Positive and negative terminal posts of VRLA Battery shall be colored Red and Black to make it unambiguously identifiable. 3.8. Connectors, Nuts & Bolts, Heat Shrinkable Sleeves The connectors shall be non corroding lead coated copper of suitable size to enable connections of cells. Copper connections shall be suitably lead coated to withstand corrosion due to Sulphuric acid/fumes. Nuts and bolts for connecting the cells shall be made of stainless steel with good acid resistant characteristics. All inter cell connectors shall be protected with heat shrinkable silicon sleeves for reducing the environmental impact including a corrosive environment. 3.9. Flame Arrestors Each cell shall be equipped with a Flame Arrestor to defuse the Hydrogen gas escaped during charge and discharge. Material of the flame arrestor shall not affect the performance of the cell. 3.10. Battery Bank Stand All batteries shall be mounted in a suitable metallic stand/frame. The frame shall be powdered coated with acid resistant paint (2 coats) and should have protection against fungus growth and other harmful effect due to tropical environment. The suitable insulation shall be provided between stand/frame and floor to avoid the grounding of the frame/stand. The joining of the frames should not leave crevices and ensure proper and tight fit. 3.11. Capacity Requirements When the battery is discharged at 10 hour rate, it shall deliver 80% of C (rated capacity, corrected at 27º Celsius) before any of the cells in the battery bank reaches 1.85V/cell. The battery shall be capable of being recharged from the fully exhausted condition (1.75V/cell) within 10 hrs up to 90% state of charge. All the cells in a battery shall be designed for continuous float operation at the specified float voltage throughout the life. The capacity (corrected at 27ºCelcius) shall also not be less than C and not more than 120% of C before any cell in the battery bank reaches 1.75V/cell. The battery voltage shall not be less than the following values, when a fully charged battery is put to discharge at C/10 rate: (a) After Six minutes of discharge: 1.98V/cell (b) After Six hours of discharge: 1.92V/cell (c) After 8 hours of discharge: 1.85V/cell (d) After 10 hours of discharge: 1.75V/cell Loss in capacity during storage at an average ambient temperature of 35º Celsius for a period of 6 months shall not be more than 60% and the cell/battery shall achieve 85% of its rated capacity within 3 charge/discharge cycles and full rated capacity within 5 cycles, after the storage period of 6 months. Voltage of each cell in the battery set shall be within 0.05V of the average voltage throughout the storage period. Ampere hour efficiency shall be better than 90% and watt hour efficiency shall be better than 80%. 3.12. Expected Battery Life The battery shall be capable of giving 1200 or more charge/discharge cycles at 80% Depth of discharge (DOD) at an average temperature of 27º C. DOD (Depth of Discharge) is defined as the ratio of the quantity of electricity (in Ampere-Hour) removed from a cell or battery on discharge to its rated capacity. The battery sets shall have a minimum expected life of 20 years at float operation. 3.13. Accessories along with Battery System Each battery shall be supplied with following accessories and devices: a) Torque Wrench. b) Cell Test Voltmeter (-3-0-+ 3) Volts with least count of 0.01 Volt 3.14. Type Test of Battery The contractor/Supplier shall supply type tested battery per IS 15549: 2004/IEC 60896-21 & 22 over the range of at least one capacity per design and should have met requirement of Service Life test as per above stated IEC standards within last seven years. The Contractor/Supplier shall submit necessary evidences enclosed along with tender documents. Sr.No 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 Description Gas Emission High Current Tolerance Short Circuit Current and DC internal resistance Protection against internal ignition from external spark source Protection against ground short propensity Content & durability of required marking Material Identification Valve Operation Flammability Rating of material Intercell connector performance Discharge Capacity Charge Retention during storage Float Service with daily discharge for reliable mains power Recharge behavior Service life at an operating temperature of 400 C for brief duration exposure time Impact of stress temperature of 60oC for brief duration exposure time with 3 hours discharge test Abusive Over discharge Thermal runway sensitivity Low temperature sensitivity Dimensional sensitivity at elevated internal pressure & temperature Stability against mechanical abuse of units during installation Test shall be conducted in accordance with IEC 60896-21 & 22,2004 3.14.1 Routine Test of Battery 1. Physical examination test 2. Visual Inspection 3. Dimensions, Mass & Layout 4. Marking & Packing 3.14.2 Acceptance Test of Battery 1. Polarity Marking 2. Verification of Dimensions 3. Test of AH Capacity. 3.15. List of Factory & Site Tests for Battery Sr.No Test Factory Tests 1 2 Physical Verification C/10 Capacity test on the cell Yes Site Tests Yes 3.16. Installation and Commissioning Manufacturer of battery shall supervise the installation as recommended in O&M manual/or relevant standards. All necessary instruments, materials, tools and tackles required for installation, testing at site and commissioning are to arranged by battery manufacturer/Contractors. 4.0 MARKING AND PACKING: 4.1 MARKING: The following information shall be indeligibly and durably marked on the outside of the cell. a) b) c) d) e) f) Nominal Voltage Manufacturer’s name, type and trade name. AH capacity at 10 hour rate. Voltage for float operation at 20 deg. C with tolerance of (+/-) 1%. Month & year of manufacturer Country of origin. S.No. of cell/cell No. 4.1.1 The cells and batteries may also be marked with the ISI certification mark, if any. 4.2 PACKING: The cells shall be suitably packed so as to avoid any loss or damage during transit. 5.0 INSTRUCTION MANUAL: The manufacturer shall supply one copy of instructions manual for initial charging (if required)/treatment, and routine maintenance during service, with each and every battery set. The manufacturer shall supply 5 copies of instructions manual to the purchaser. The following information shall be provided on, the instruction cards. a) Designation of cell or battery b) Ampere hour capacity. c) Nominal voltage d) Manufacturer’s instructions for charging e) Voltage for float operation at 20 deg.C with tolerance (+/-) 1%. f) Maintenance instructions g) Environmental & safety provisions required. 6.0 TESTS: All the acceptance tests as per relevant standards mentioned shall be carried out for batteries in presence of our inspecting officer free of cost. Type test certificates (not older than 7 years from the date of opening of tender) are to be submitted for approval of purchaser. 7.0 DRAWINGS: The tenderer will submit the detailed dimensional drawings for battery sets including stands. 8.0 TYPE TEST CERTIFICATES: The tenderer will submit the complete type test certificates as per relevant standards mentioned (not older than 7 years from the date of opening of tender) for battery sets with their tenders, without which the offers are likely to be ignored. 9.0 GUARANTEED TECHNICAL PARTICUALRS: Guaranteed Technical Particualrs for battery sets as per Annexure-A attached shall be furnished along with the tender. 10.0 ACCESSORIES: Each battery set shall be supplied complete with all necessary accessories viz. stand, inter connections, cell no. Plates with sticker, multi meter complete with leads, spanners. 11.0 BILL OF MATERIAL: The firm shall also have to furnish the bill of material used in battery set. SECTION-6 CHAPTER-3 TECHNICAL SPECIFICATION FOR220V DC BATTERY CHARGER WITH 20AMP. FLOAT AND 30AMP. BOOST 1. Battery Charger The DC system for 220V DC is unearthed. The Battery Chargers as well as their automatic regulators shall be of static type and shall be compatible with VRLA batteries. All battery chargers shall be capable of continuous operation at the respective rated load in float charging mode, i.e. Float charging the associated LeadAcid Batteries at 2.13 to 2.27 Volts per cell while supplying the DC load. The chargers shall also be capable of Boost charging the associated DC battery at 2.28 to 2.32 volts per cell at the desired rate. Charger shall regulate the float/boost voltage in case of prescribed temperature rise of battery as per manufacturer’s recommendation to avoid thermal runaway. Necessary temperature sensors shall be provided in mid location of battery banks and shall be wired up to the respective charger for feedback control. The manufacturer shall demonstrate this feature during testing of each charger. Each of the two chargers in this float-cum-boost charger for float mode & for boost mode shall be provided with independent transformer & associated circuitary. 1.1 The battery chargers shall be provided with facility for both automatic and manual control of output voltage and current. A selector switch shall be provided for selecting the mode of output voltage/current control, whether automatic or manual. When on automatic control mode during float charging the chargers output voltage shall remain within + 1% of the set value, for AC input voltage variation of + 1% frequency variation of + 5% a combined voltage and frequency variation of + 1% and a DC load variation from zero to full load. 1.2 All battery chargers shall have a constant voltage characteristics throughout the range (from zero to full load) at the floating value of the voltage so as to keep the battery fully charged but without harmful overcharge. All chargers shall have load limiters having drooping characteristics, which shall cause, when the voltage control is in automatic mode, a gradual lowering of the output voltage whet eh DC load current exceeds the Load limiter setting of the Charger. The Load-limiter characteristics shall be such that any sustained overload or short circuit in DC system shall not charge the Charger nor shall it cause blowing of any of the Charger fuses. The Charger shall not trip on overload or external short circuit. Uniform and step less adjustments of voltage setting (in both manual and automatic modes) shall be provided on the front of the Charger panel covering the entire float charging output range specified. Step less adjustments of the Load-limiter setting shall also be possible from 80% to 100% of the rated output current for Charging mode. During Boot Charging, the Battery Charger shall operate on constant current mode (when automatic regulator is in service). It shall be possible to adjust the Boost charging current continuously over a range of 50 to 100% of the rated output current for Boost charging mode. 1.3 1.4 1.5 -1- The Charger output voltage shall automatically go on rising, when it is operating on Boost mode, as the Battery Chargers up. For limiting the output voltage of the Charger, a potentiometer shall be provided on the front of the panel, whereby it shall be possible to set the upper limit of this voltage any where in the output range specified for Boost Charging mode 1.6 The Charger manufacturer may offer an arrangement in which the voltage setting device for Float charging mode is also used as output voltage limit setting device for Boost charging mode and the Load-limiter of Float charging mode is used as current setting device in boost charging mode. 1.7 Suitable filter circuits shall be provided in all the chargers to limit the ripple content ( Peak to Peak) in the output voltage to 1% irrespective of the DC load level, when they are not connected to a battery. 1.8 The charger shall be capable of delivering 20A in float mode & 30A in boost mode separately at rated voltage. 1.9 MCCB All Battery Chargers shall have 2 Nos. MCCBs on the input side to receive cables from two sources. Mechanical interlock should be provided such that only one shall be closed at a time. It shall be of P2 duty and suitable for continuous duty MCCB’s should have auxiliary contacts for annunciation. 1.10 Rectifier Transformer The rectifier transformer shall be continuously rated, dry air cooled (A.N) an of class F insulation type. The rating of the rectifier transformer shall have 10% overload capacity. 1.11 Rectifier Assembly The rectifier assembly shall be fully/half controlled bridge type and shall be designed to meet the duty as required by the respective charger. The rectifier shall be provided with heat sink having their own heat dissipation arrangements with natural air cooling. Necessary surge protection devices and rectifier type test acting HRC fuses shall be provided in each arm of the rectifier connections. 1.12 Instruments One AC voltmeter and one AC ammeter along with selector switches shall be provided for all chargers. One DC voltmeter and DC ammeter (with shunt) shall be provided for all chargers. The instruments shall be flush type, dust proof and moisture resistant. The instruments shall have easily accessible means for zero adjustment. The instruments shall be of 15 accuracy class. In addition to the above a centre zero voltmeter with selector switch shall also be provided for 220 V Chargers for testing purpose. -2- 1.13 Air Break Switches One DC output switch shall be provided in all chargers. They shall be air break type suitable for 500 Volts AC/ 250 DC. The contacts of the switches shall open and close with a snap action. The operating handle of the switch shall be fully insulated from circuit. ‘ON’ and ‘OFF’ position on the switch shall be clearly indicated. Rating of switches shall be suitable for their continuous load. Alternatively, MCCB’s of suitable ratings shall also acceptable in place of Air Break Switch. 1.14 Fuses All fuses shall be HRC Link type. Fuses shall be mounted on fuse carriers which are in turn mounted on fuse bases. Wherever it is not possible to mount fuses on carriers, fuses shall be directly mounted on plug-in type base. In such case one insulated fuse pulling handle shall be supplied for each charger. Fuse rating shall be chosen by the Bidder depending on the circuit requirement. All fuses in the chargers shall be monitored. Fuse failure annunciation shall be provided on the failure of any fuse. 1.15 Blocking Diode Blocking diode shall be provided in the positive pole of the output circuit of each charger to prevent current flow from the DC battery into the charger. 1.16 Annunciation System Audio-visual indications through bright LEDs shall be provided in all Chargers for the following abnormalities:a) AC Power failure. b) Rectifier/chargers fuse blown. c) Over voltage across the battery when boost charging. d) Abnormal voltage (High/Low) e) Any other annunciation if required Potential free NO contacts of above abnormal conditions shall also be provided for common remote indication “CHARGER TROUBLE” in Owner’s Control Board. Indication for charger in float mode and boost mode through indication lamps shall be provided for chargers. A Potential free contact for float/boost mode shall be provided for external interlocks. 1.17 Name Plates and Marking The name plates shall be white with black engraved letters. On top of each Charger, on front as well as rear sides, larger and bold name plates shall be provided to identify the Charger. Name plates with full and clear inscriptions shall also be provided on and inside of the panels for identification of the various equipments and ease of operation and maintenance. -3- 1.18 Charger Construction The Chargers shall be indoor, floor-mounted, self-supporting sheet metal enclosed cubicle type. The Contractor shall supply all necessary base frames, anchor bolts and hardware. The Chargers shall be fabricated from 2.0mm cold rolled sheet steel and shall have folded type of construction. Removable gland plates for all cables and lugs for power cables shall be supplied by the Contractor. The lugs for power cables shall be made of electrolytic copper with tin coat. Power cable sizes shall be advised to the Contractor at a later date for provision of suitable lugs and drilling of gland plates. The Charger shall be tropicalised and vermin proof. Ventilation louvers, if provided shall be backed with screens. All doors and covers shall be fitted with synthetic rubber gaskets. The chargers shall have hinged double leaf doors provided on front and on backside for adequate access to the Charger’s internals. All the charger cubicle doors shall be properly earthed. The degree of protection of Charger enclosure shall be at least IP-42 as per IS: 13947 Part -1. 1.18.1 All indicating instruments, control switches and indicating lamps shall be mounted on the front side of the Charger. 1.18.2 Each Charger shall be furnished completely wired upto power cable lugs and terminal blocks and ready for external connections. The control wiring shall be carried out with PVC insulated, 1.5 sq.mm. stranded copper wired. Control terminals shall be suitable for connecting two wires, with 2.5 sq.mm stranded copper conductors. All terminals shall be numbered for ease of connections and identification. Each wire shall bare a ferrule or tag on each end for identification. At least 20% spare terminals shall be provided for control circuits. The insulation of all circuits, except the low voltage electronic circuits shall withstand test voltage of 2 KV AC for one minute. An air clearance of at least ten (10) mm shall be maintained throughout for such circuits, right up to the terminal lugs. Whenever this clearance is not available, the live parts shall be insulated or shrouded. 1.18.3 1.19 Painting All sheet steel work shall be pre-treated in tanks, in accordance with IS:6005 Degreasing shall be done by alkaline cleaning. Rust and scale shall be removed by pickling with acid. After pickling, the parts shall be washed in running water. Then these shall be rinsed in slightly alkaline hot water and dried. The phosphate coating shall be ‘Class-C’ as specified in IS:6005. Welding shall not be done after phosphating. The phosphating surfaces shall be rinsed and passivated prior to application of stoved lead oxide primer coating. After primer application, two coats of finishing synthetic enamel paint of shade -692 (smoke grey) of IS-5 shall be applied, unless required otherwise by the Owner. The inside of the chargers shall be glossy white. Each coat of finishing synthetic enamel paint shall be properly staved. The paint thickness shall not be less than fifty (50) microns. 1.20 TESTS 1.20.1 Battery Chargers shall conform to all type tests as per relevant Indian Standard Performance test on the Chargers as per Specification shall also be carried out on each charger as per specification. Rectifier transformer shall conform to all type tests -4- in IS:4540 and short circuit test as per IS:2026. Following type tests shall be carried out for compliance of specification requirements:i) ii) iii) iv) v) vi) 1.20.2 1.20.3 1.20.4 Voltage regulation test. Load limiter characteristics test Efficiency tests High voltage tests Temperature rise test Short circuit test at no load and full load at rated voltage for sustained short-circuit. vii) Degree of protection test viii) Measurement of ripple by oscilloscope. ix) Temperature compensation feature demonstration The contractor may be required to demonstrate to the OWNER that the chargers conform to the specification particularly regarding continuous rating, ripple free output, voltage regulation and load limiting characteristic, before despatch as well as after installation at site. At site the following tests shall be carried out:i) Insulation resistance test ii) Checking of proper annunciation system operation If a Charger fails to meet the specified requirements, the Contractor shall replace the same with appropriate Charger without affecting the commissioning schedule of the Sub-Station, and without any extra cost to the OWNER. The Contractor shall present for inspection, the type and routine test certificates for the following components whenever required by the OWNER. (i) (ii) (iii) (iv) (v) (vi) (vii) (viii) (ix) (x) (xi) (xii) Switches Relays/MCCBs Instruments DC fuses SCR Diodes Condensers Potentiometers Semiconductor Annunciator Control wiring Push buttons and contactors Makes of above equipment shall be subject to Owner’s approval. -5- SECTION-6 CHAPTER 4 TECHNICAL SPECIFICATION OF D.C. DISTRIBUTION BOARD. 1. 1.02 SCOPE: This specification provides for design, Engineering, manufacture, stage testing, inspection and testing before dispatch, packing, forwarding and delivery at site of D.C. Distribution Board, complete with all fittings accessories and associated auxiliary equipment mandatory which are required for efficient and trouble free operation as per specified here under. It is not the intent to specify completely all the details of design and construction of equipment. However, the equipment shall conform in all respects to the high standard of engineering, design and workmanship and shall be capable of performing in continuous commercial operation up to the Bidder’s guarantee acceptable to the purchaser. The equipment offered shall be complete in all component necessary for its effective and trouble free operation along with associated equipment interlocks protection scheme etc. Such components shall be deemed to be within the scope of supply irrespective of whether those are specially brought out in this Specification and or the commercial order or not. All similar parts particularly movable ones shall be interchangeable. CLIMATIC CONDITIONS : As per Section-I Vol-II. 1.03 STANDARD: All material and equipment shall comply in every respect with the requirements of the latest edition of the relevant Indian Standard IS:1651. 1.04 MANUFACTURE AND WORKMANSHIP: All the material used in the construction of the equipment shall be of the best quality obtainable of their respective kinds and whole of the work shall be of the highest class, well finished and of approved design and make. Casting shall be free from blow holes, flaws and of the true form and dimensions. 1.05 1.06 All machined surfaces shall be true and smooth and well finished. DUTY AND GENERAL ARRANGEMENTS: The power for the charging apparatus shall be given through an independent 4-core cable connection from an A.C. 50 cycles 3 phase 415 ± 10% volts switchboard fed from a Station Transformer. D.C. Distribution shall be through fuse protected rotary switches mounted on a separate distribution board. TYPE OF EQUIPMENT: All equipment shall be located indoors. D.C. Distribution panel are to be mounted on the floor in the control room adjacent to the Battery room. Necessary doors and screens shall be provided wherever required. All equipment shall be vermin proof. The overall design of the entire equipment should be adequate for the duty in view to ensure trouble free and dependable service. The various cables for D.C. Distribution circuits, which are to be arranged by the Bidder shall have P.V.C. insulation. The conductors may be of copper or aluminum. All panel wiring to be provided by the supplier, shall consist of suitable colored/marked P.V.C. insulated cables. 1.07 BUS BARS AND SUPPORTS: The bus bars shall be of aluminium having adequate cross-sections. The bus bars shall be so designed and mounted that their expansion and contraction does not subject, either the Bus Bars or their supports, to any stresses. All bus bars and connections shall be duly marked and colored for identification. -1- 1.08 1.09 1.10 1.11 1.12 INSTRUMENTS: All instruments shall have 96 sq mm dials and flush mounted on the panels. Moving coil spring controlled instruments shall be used except those for A.C. which may be of the moving iron type. The error of indication shall not exceed 1% throughout the effective range of the meter. RESPONSIBILITY FOR DESIGNS: The Bidder shall assume full responsibility for co-ordinate and adequate design and shall conform to the best engineering practice for the operating conditions specified. In case the equipment covered by this specification is to be co-ordinate with other equipment, the Bidder shall furnish complete information and data as may be desired by the purchaser. GROUNDING: All metal parts should be grounded according to Indian Electricity Rules. Main ground Bus shall be provided by the purchaser. Special grounding lugs of adequate size shall be provided by the supplier on the charging equipment. INTER CHANGEABILITY: Corresponding parts of plant and equipment shall be made to gauge or jig and shall be interchangeable in every respect. DOCUMENTATION The successful bidder shall submit four sets of drawings for HVPNL approval. The following drawing shall be supplied with the tender: i) Outline drawings of all apparatus showing sufficient details to enable the purchaser to determine whether the design proposed can be installed satisfactorily or not. NOTE: All above drawings should be a minimum space (14x10cm) for stamping the approval of drawings by HVPNL. 1.13 FOUNDATIONS AND FIXINGS: All plants and equipment shall be provided with a complete set of foundation holding down bolts, washers, nuts plants and other fixture as may be required and these shall be supplied by the Bidder. These fittings will be fixed by the purchaser in the foundations unless otherwise specified. All foundation bolts, fixtures etc. shall be supplied as soon as possible after the contract drawings have been approved. 1.14 INSTRUCTION AND MARKING PLATES: All gauges, meters, instruments etc. shall have dials or scales calibrated in metric system of units. All name plates, instruction plate, warning signs and any marking what-so-ever on the equipment and its parts and accessories shall be in Hindi-English Language, using idioms, words and meaning as in current use in India. In order to facilitate sorting and erection at site every part of the plant and equipment shall be suitably marked. 1.15 TROPICAL TREATMENT & PAINT: All corrodible parts and surfaces shall be of such material and shall be provided with such paint or other protective finish that no part of the installed equipment shall be injuriously affected by the atmospheric moisture, heat and fumes. The panels shall be finally painted with light grey paint having shade No.631 of IS:5 with stove enameled finish. 1.16 PLACE OF MANUFACTURE AND INSPECTION: The Bidder shall state in his tender the place(s) of manufacture, testing and inspection of the various portions of the work included in the tender. The purchaser or his duly authorised agent shall have access to the Bidder's or sub Bidder's work at any time during working hours for the purpose of inspecting the manufacture and testing of materials, equipment and completed plant and the Bidder shall provide the necessary facilities for inspection. TESTS: Type Tests The equipment should be offered type test. Test reports should not more then seven years old reckoned from date of bid opening in respect of all the tests carried out in accredited 1.17 1.17.1 -2- 1.17.2 1.17.3 laboratories (based on ISO/IEC) by a reputed accreditatic body or witnessed by HVPN or another electric power utility and be submitted by the successful bidder to HVPNL for approval as schedule given in Bar Chart. i) Verification of constructional requirements ii) Verification of marking iii) Verification of dimensions Routine Tests As per quality assurance program (QAP). Acceptance Tests The following acceptance tests for DCDB shall be carried out by the Supplier in presence of HVPNL representative, unless dispensed with in writing by the HVPNL. i) Dimension test ii) Visual check test iii) quantative check iv) Functional checks v) wiring HV Test vi) Insulation resistance test 1.17.4 SAMPLING SCHEME AND CRITERIA FOR ACCEPTANCE: The sampling scheme and criteria for acceptance for cells up to and including 600 AH capacity shall be in accordance with clause 5 1.4 of IS-8320-1976. The sampling scheme for cells of higher capacities shall be subject to agreement between the user and the manufacturer. 1.18 SPARE PARTS :The Bidder shall quote separately in his tender for spare parts as he world recommend for the main maintenance operation of the equipment for the period of 5 years. Of detailed list of such spares parts which item wise prices shall be given under schedule of requirement and prices. The purchaser may order spares subsequently as may be finally decided upon, at the rates given in the tender. All spares parts shall be interchangeable and shall be of same make material and both workmanship as the corresponding parts furnished with the main equipment. 1.19 DETAILS OF TECHNICAL PARTICULARS AND SPECIFICATION: Details of the technical particulars and specification required have been given in Appendix (b). Any other particulars considered necessary by the supplier may also be given in addition to the above listed in Data requirement sheet. 1.20 COMPLETENESS OF EQUIPMENT: Any fittings, accessories or apparatus which may not have been specifically mentioned in the specification, but which are usually necessary in the equipment shall be deemed to be included in the contract and shall be supplied by the Bidder without extra cost. -3- APPENDIX 'A' SCHEDULE OF REQUIREMENT D.C. DISTRIBUTION BOARD: The D.C. Distribution Board shall be housed in a sheet steel cubicle with adequate ventilation and it should be vermin proof as far as possible and should be provided with louvers for ventilation backed by fine wire mesh, which applies to both charging equipment and D.C. Distribution Board. The DCDB shall match with the battery charging equipment and should be complete with bus bars of suitable capacity, wiring, rating plates, glands and fixing bolts. The minimum size of cubical should be 600X700X1600 mm. The following components shall be provided on the D.C. distribution board: FOR 200 AH & 100 AH BATTERIES 1. Double pole ON/OFF rotary switch of 200 Amps. for 200 AH rating Battery with 1 set 2 Nos. HRC fuses of 100 Amps 2. Moving coil ammeter of 96mm sq. and range 0-200 amps. for 200 AH battery 1 No for measuring the load on the bus. 3. Change over contactor : a) 20 Amps. for 200 AH battery change over contractor AC/DC for switching 1 No indication over to DC. On failure of AC supply and also for emergency pilot light in the event of AC failure. b) 10 Amps HRC fuses for pilot light 4. 2 Nos. Double pole D.C. Rotary switches with HRC fuses for each of following feeders: a) 220 kV closing supply of 50 Amps, capacity 1 No. b) 132 kV closing supply 50 Amp. Capacity 1 No. c) 66 kV -do- 1 No. d) 33 kV -do- 1 No. e) 11 kV closing supply 100 Amps. capacity 1 No. f & g) spare 100 Amp. Capacity 2 Nos. h & i) spare 50 Amp. capacity 2 Nos. 5. Double pole D.C. rotary switch of 10 Amps. rating with 10 Amp. HRC fuses for each of the following feeders: a) 11 kV Tripping supply 10 Amp capacity 1 No. b) 33 kV -do- 1 No. c) 66 kV -do- 1 No. d) 132 kV -do- 1 No. e) 220 kV -do- 1 No. f) Carrier telephone 10 Amp. capacity 1 No. g) 33 kV Relay & Board panel 10 Amp. capacity 1 No. h) 66 kV Relay & Board panel 10 Amp. capacity 1 No. -4- i) 132 kV Relay & Board panel 10 Amp capacity 1 No. j) 220 kV Relay & Board panel 10 amp. capacity 1 No. k) Spare 10 Amp capacity 3 Nos. All the instruments shall be of flush mounted type. The rotary switches shall also be flush mounted except for the protection portion in the panels. All switches shall be mounted on the front panel and all the HRC fuses together with their fuse fittings on the front panel but within a chamber that can be opened by half doors, to occasion accessibility to the fuses. The various components shall be of the best quality and from reputed manufacturers. The layout of components, wiring workmanship reliability etc. shall be of the best quality. Adequate room should be provided within the charger/DC distribution board cubicles for easy accessibility of components and also to facilitate ventilation. -5- SECTION-6 CHAPTER 5 FIRE FIGHTING EQUIPMENT 1.0 SCOPE Portable fire extinguishers of Carbon Dioxide type and Dry chemical Powder type shall be provided in adequate numbers for protection the Control Room Building and all other Buildings in the sub-stations. The protection shall cover all the rooms/areas of the buildings. The quantity and location of the extinguishers shall be as per the requirements of Fire protection Manual (Part-I) issued by Tariff Advisory Committee of India (TAC) and IS:2190. 1.1 Trolley Mounted fire extinguishers of 22.5 kg Carbon Dioxide type and 22.5 kg Dry Chemical Powder type shall be used for protection of all 220kV, 132/66kV Transformers and reactors in the S/Stn. Two DCP type and two CO2 type extinguishers shall be provided for each transformer/reactor. 2.0 PORTABLE TYPE FIRE EXTINGUISHERS: 2.1 2.7 2.8 2.9 This Specification lays down the requirement regarding fire extinguishers of following types: a) Carbon Dioxide type b) Dry Chemical powder type All the portable extinguishers shall be capable of discharging freely and completely in upright position. Each extinguisher shall have the instructions for operating the extinguishers on its body itself. All extinguishers shall be supplied with initial charge and accessories as required. Portable type extinguishers shall be provided with suitable clamps for mounting on walls or columns. All extinguishers shall be painted with durable enamel paint of fire red colour confirming to relevant Indian Standards. Capacities of each type shall be as indicated in the schedule of quantities. Carbon Dioxide (CO2 type) extinguishers shall conform to IS:2878. Dry chemical powder type extinguisher shall conform to IS:2171. 2.10 TESTS AND INSPECTION 2.10.1 All tests required to ensure that the equipment conforms to the Specification requirements and relevant standards and codes. A performance demonstration test at site of five (5) percent or one (1) number whichever is higher, of the extinguishers shall be carried out by the Contractor. All consumable and replaceable items required for this test would be supplied by the Contractor without any extra cost to the Purchaser. Performance listing of extinguishers shall be in line of applicable Indian Standards. In case, where no Indian Standard is applicable for a particular type of extinguishers, the method of testing shall be mutually discussed and agreed to before placement of order for the extinguishers. 2.2 2.3 2.4 2.5 2.6 2.10.2 2.10.3 -1- 2.11 PERFORMANCE GUARANTEE The contractor shall guarantee all equipment supplied by him against any defect due to faulty design, materials and workmanship. The equipment shall be guaranteed to operate satisfactorily at the rated conditions at site. 2.12 PAINTING Each fire extinguisher shall be painted with durable enamel paint of fire red colour conforming to relevant Indian Standards. 3.0 TROLLEY MOUNTED DRY CHEMICAL POWDER TYPE MOBILE FIRE EXTINGUISHER The Specification lays down the requirement regarding wheeled fire extinguisher of dry chemical powder type. Design, Manufacture, Material of construction and performance of mobile type fire extinguisher shall comply with the requirements of latest Indian Standards & shall have BIS approval (ISI marked). 3.1 PERFORMANCE REQUIREMENT The capacity of the mobile dry chemical powder type fire extinguisher shall be 22.5 kg which means the total capacity of the container, when powder completely filled to the specified level shall be 22.5 kg. The fire extinguishers shall be used for Class ‘B’, ‘C’, and ‘E’ fires. The extinguishers shall operate in the vertical position, mounted on solid rubber tyre trolley wheels. The effective throw during operation of the extinguishers shall not be less than 10 meter. A carbon dioxide cartridge fitted with valved discharge head, shall provide sufficient carbon dioxide to expel the dry chemical powder. 3.2 DESIGN AND CONSTRUCTION The construction of wheeled fire extinguishers shall conform to IS standard and not be limited to the requirements mentioned here. The shape of the body of the fire extinguisher shall be cylindrical. It shall have adequate supporting arrangement. The balance of the fully equipped assembly shall be so arranged that it can be easily towed speedily behind a jeep or a car and also wheeled by a single operator. Two solid rubber tyred trolley wheels shall be fitted to the body of the mobile fire extinguisher. The rubber tyres shall have an effective life, and less than three (3) years. The extinguisher shall be fitted with a discharge hose and nozzle connection. The hose shall be of rubber or composite construction, having a length of 4.5-meter minimum. The bursting pressure of the hose shall be minimum 42 kgf/cm (g). -2- The design of discharge nozzle shall be such that when the extinguisher is operated in still air the powder will be thrown in the form of a jet having a range of 10m (minimum) for a period of 50-60 seconds. The nozzle shall be fitted with a hand control device. Provision shall be therefore making a pressure test on the body. To minimize corrosion, the various components shall be provided with suitable anticorrosive as per the requirement of applicable codes. Each mobile extinguisher shall be complete with initial charge, discharge fittings and accessories. 3.3 TESTS AND INSPECTION Testing at manufacturer’s works. The manufacturer shall conduct all tests required to ensure that the equipment furnished will conform to this Specification requirements, relevant Indian Standards and applicable codes. Everybody shall be capable of withstanding an internal hydraulic pressure of 25 kgf/cm (g) without leakage or visible distortion, prior to painting, for a minimum period of 5 minutes. In destruction tests, if called for, ultimate failure shall occur at a test pressure not less than 32 kgf/cm (g) and if it occurs below 35 kgf/cm (g) there shall not be damage in any joint, seam casting of fittings. A performance demonstration test at site on five (5) percent or one (1) number, whichever is higher, shall be required to be carried out by the CONTRACTOR. All consumable and replaceable items required for the test shall be supplied by the CONTRACTOR without any extra cost to Purchaser. After conduction tests as in 1.1 and 1.4 the body shall be properly washed and drained off. After 24 hours, the interior shall be examined and it must be free from any stain, rust etc. 3.4 PERFORMANCE GUARANTEE The CONTRACTOR shall guarantee all equipment supplied by him against any defect due to faulty design, materials and workmanship. The equipment shall be guaranteed to operate satisfactorily at the rated conditions at site. 3.5 PAINTING Each mobile fire extinguisher shall be painted with durable enamel paint of red colour conforming to relevant Indian Standard. The mobile foam type fire extinguisher shall be of make approved by Tariff Advisory Committee/NFPA/FOC/UL. Appliances conforming to the relevant BS/NFPA Standards are also acceptable provided the construction generally conform to the IS Standards so that spares refills/cartridges of Indian make conforming to IS Specification can be used after the operation of the extinguisher. Spare charge cartridges equivalent to requirements of 2 Nos. extinguishers shall also be supplied. -3- 4.0 TROLLEY MOUNTED CARBON-DIOXIDE TYPE MOBILE FIRE EXTINGUISHER 1.1 This Specification lays down the requirements regarding wheeled fire extinguisher of carbon-dioxide. 1.2 Design, manufacture, material of construction and performance of extinguisher as specified herein after shall comply with the requirements of latest applicable Indian Standards IS-2878 or equivalents and shall have BIS approval (ISI marked). 1.3 1.3.1 PERFORMANCE REQUIREMENT The capacity of the extinguisher shall be 22.5 kg of carbon-dioxide when filled in the container to a filling ratio of about 0.66, 7. The extinguisher shall be designed for use where larger high intensity fire hazards are involved requiring versatility of action. These shall be used for Class ‘B’ fire, i.e. fire in flammable liquid. Class ‘C’ fire i.e. fire in gaseous substances under pressure and Class ‘E’ fire, i.e. fires in live electrical equipment. The extinguisher shall be operated in upright position, by releasing a suitable valve. The range of effective operation of the extinguishers shall be about 4 meters. 1.3.2 1.3.3 1.3.4 1.4 1.4.1 1.4.2 1.4.3 1.4.4 1.4.5 1.4.6 1.4.7 1.4.8 1.4.9 1.4.10 1.4.11 1.4.12 DESIGN AND CONSTRUCTION The construction of wheeled fire extinguisher, carbon-dioxide type, shall in general conform to IS:2828 subject to the requirements mentioned hereunder: The carbon-dioxide gas shall conform to IS:307. The shape of the body of the extinguisher shall be cylindrical. The body shall be of steel cylinder. It shall have adequate supporting arrangement so that it can rest on the wheeled body in upright position and the operator be free to direct the stream. The balance of the full equipped trolley unit shall be so arranged, that despite its considerable weight, it can be easily wheeled by one man. It should be capable of being towed speedily behind a jeep or car. The cylinder shall be mounted on a trolley fitted with two cushion tyred wheels and fitted with suitable handle. The overall wheel diameter shall be about 280 mm. The frame of the trolley shall be made of welded steel section. The design shall permit easy maintenance and operation with one man service. The extinguisher shall be fitted with a high pressure flexible hose of about 9 m length and internal dia to hoses shall not be more than 12 mm. A discharge horn made of fibre or any material non-conducting to electricity shall be fitted with a handle made of thermal insulating material capable of protecting operators hand from freezing effects. Suitable provision for firmly securing the horn to the body, when it is not in use, shall be provided. The fixing device shall not interfere with the operation or mobility of the extinguisher. The discharge valve or operating head shall be capable of being operated satisfactorily. It shall be made of material as specified in IS:2878. There shall be no leakage of CO2 from valve or fitting during the use of extinguisher. Valve shall be provided with suitable safety device to prevent over pressure in cylinder. A seal or device shall be fitted to indicate that the extinguisher has not been used. Each extinguisher shall be complete with initial charge, discharge fittings and other accessories as required. -4- 1.5 TEST AND INSPECTION 1.5.1 The extinguisher at ambient temperature shall expel at least 95% of its content as continuous discharge with in a maximum of 90 seconds and minimum of 30 seconds. The extinguisher without its attachment shall be shelved for 21 days after filling and shall be check weighed at the end of the period. There shall be no loss of mass. Carbon-dioxide cylinder shall be hydrostatically tested at a pressure of 236 kgf/cm (g) to prove leak tightness for a period of one hour. Hose assembly with its coupling shall be hydrostatically tested at a pressure of 315 kgf/cm (g) without failure. All tests required to ensure that the equipment conforms to the Specification requirements and relevant standards and codes shall be conducted by the manufacturer. Adequate time ahead of these shop tests the Purchaser shall be informed so that if he so desires, his representative may witness the tests. A performance demonstration test at site on five (5) percent or one (1) number, whichever is higher, shall be required to be carried out by the CONTRACTOR. All consumable and rechargeable items required for the test shall be supplied by the CONTRACTOR without any extra cost to Purchaser. 1.5.2 1.5.3 1.5.4 4.5.5 1.5.5 1.6 PERFORMANCE GUARANTEE The CONTRACTOR shall guarantee all equipment supplied by him against any defect due to faulty design, materials and workmanship. The equipment shall be guaranteed to operate satisfactorily at the rated conditions at site. 1.7 PAINTING & MARKING Each extinguisher shall be painted in red and permanently marked in accordance with the requirements laid down in IS-2878. besides permanently making on the front of the extinguisher indicating its purpose, content and usage shall also be provided. 1.7.1 The mobile Carbon-dioxide type fire extinguisher shall be of make approved by Chief Inspector of Explosives, Nagpur, India and Tariff Advisory Committee/NFPA/FOC/UL. 2. VENTILATION SYSTEM Mechanical ventilation systems using exhaust fans shall be provided for all the rooms which are not considered for air conditioning. Capacity of the fan shall be selected so as to have the minimum air changes in the various rooms as below: Battery room, Pantry, toilets Changes/hr. All other rooms Changes/hr. : 15 air : 12 air For Battery room, the fan shall be bifurcated type spare proof construction. -5- SECTION-6 CHAPTER-6 PART-I TECHNICAL SPECIFICATION FOR 66 KV (CROSS LINKED POLYETHYLENE INSULATED POWER CABLE: 1.1 SCOPE 1.1.1 The scope under this section covers design, manufacturer, testing, packing, supply, delivery and laying of 66 KV, XLPE, insulated power cable for use with effectively earthed distribution systems. 1.2 STANDARDS: Unless otherwise specified, the cables shall conform, in all respects, to IEC-60840 and IS:7098 (Part-III)/1993 with latest amendment or latest edition for cross linked polyethylene insulated PVC sheathed cable for working voltage of 66KV. 1.3 CLIMATIC CONDITIONS: The climatic conditions under which the cable shall operate satisfactorily are as follows:a) Location : IN THE STATE OF HARYANA b) Maximum ambient temperature of air in shade 0 : 50 c) Minimum ambient temperature of air in shade 0 : -2.5 d) Maximum daily average ambient temperature 0 : 40 e) Maximum yearly average ambient temperature 0 C : 30 f) Maximum relative humidity % : 100 g) Minimum relative humidity % : 26 h) Average number of thunder storm days per annum : 35 i) Average annual rain fall mm : 900 j) Max. wind pressure kg/m2 : 195 k) Altitudes not exceeding above MSL Meter : 1000 l) Max. soil temp. at cable depth 0 : 30 m) Isoceranic level days/year : 50 n) Seismic level (horizontal acceleration) : 0.3g C C C C -1- 1.4 1.4.1 PRINCIPAL PARAMETERS: 66 kV (E) grade XLPE single core power cable conductor electrolytic grade copper of single length, with formation of stranded compacted circular conductor for size upto 800mm2 and segmental type for size above 800mm2 as per IEC-60228, tapped with semi conducting tap, shielded with extruded semi-conducting layer, insulated with cross linked polyethylene (XLPE) insulation, screened with extruded semi-conducting layer, lapped with a combination of semi-conducting water swell able tape & copper-woven semi conducting tape and extruded aluminium sheath with anti-corrosive layer & graphite coating HDPE outer sheathed, confirming to IEC-60840 for construction and also confirming to IS:7098 (Part-III)/1993 or any latest amendments thereof. 1.4.2 Outer sheathing should be designed to afford high degree of mechanical protection and should also be heat, oil chemicals and weather resistant. Common acid. Alkalis and saline solution should not have adverse effect on the PVC sheathing material used. 1.4.3 The cable should be suitable for laying in covered trenches and/or under ground for outdoor. 1.4.4 The sheath/screen bonding system shall provide a continuous current path through the cable sheath and jointing kits and shall be bonded. The bonding ends shall be suitably earthed with/without SVL as per approved configuration/design. The sheath voltage under full load condition shall not exceed the voltage specified/allowed in relevant standard for safety of personal as well as satisfactory working of cable. Sheath shall be solidly grounded at suitable location with or without SVL. Bidder must indicate details of configuration proposed along with sufficiency calculation with the bid so as to limit induced voltage of sheath within 65V. 1.4.5 CABLE PARAMETERS Sr. No. Description 66 KV i) Voltage Grade (Uo/U) 38/66 ii) No. of cores Single iii) Size (mm2) 400mm2,630mm2, 800mm2,1000mm2, 1200 mm2 iv) Nominal system voltage KV 66 v) vi) vii) viii) ix) Highest system voltage KV System Frequency Hz Variation in Frequency Fault level individually for i) Conductor ii) Cu.Screen/Armour Maximum allowable temperature 72.5 50 + 3% 31.5 KA for1sec 31.5 KA for 1sec a) Design continuous operation at rated full load 90 current, the max, temp. of conductor shall not 0 exceed. C b) The conductor temperature after a short 250 circuit for 1.0 sec shall not exceed. 0C x) xi) xii) Basic insulation level (1.2/50 Micro Second 325 KVP Wave) 1-min. power frequency withstand voltage (rms) 140 KV System earthing Effectively earthed -2- 1.5 GENERAL TECHNICAL REQUIREMENTS: 1.5.1 CONDUCTOR: The cable conductor shall be made from electrolytic grade copper with formation as stranded compacted circular conductor for size upto 800mm2 and segmental type as per IEC-60228 for the size above 800mm2.The conductor shall confirm to IS:8130/1984. CONDUCOTR SHIELD: The conductor having a semi-conducting screen shall ensure perfectly smooth profile and avoid stress concentration. The conductor screen shall be extruded in the same operation as the insulation; the semi-conducting polymer shall be cross-linked. 1.5.2 1.5.3 INSULATION: The XLPE insulation should be suitable for specified 66 kV system voltage. The manufacturing process shall ensure that insulations shall be free from voids. The insulation shall withstand mechanical and thermal stressed under steady state and transient operating conditions. The extrusion method should give very smooth interface between semi-conducting screen and insulation. 1.5.4 INSULATION SHIELD: To confine electrical field to the insulation, non-magnetic semiconducting shield shall be put over the insulation. The insulation shield shall be extruded in the same operation as the conductor shield and the insulation by suitable extrusion process. The XLPE insulation shield should be bonded type. Metallic screening shall be provided. The metallic screen shall be of copper wire having fault current capacity same as the conductor (31.5KA for 1-sec). 1.5.5 INNER SHEATH/ARMOUR: The inner sheath shall comprise of a combination of semiconducting water swell able and extruded aluminium sheath with anti-corrosive layer. The sheath shall be suitable to withstand the site conditions and the desired temperature. It should be of adequate thickness, consistent quality and free from all defects. The armour shall be having fault current capacity same as conductor (31.5KA for 1 sec.) 1.5.6 OUTER SHEATH: Extruded HDPE outer sheath confirming to IEC: 60840, shall be applied over armouring with suitable additives to prevent attack by rodents and termites. 1.5.7 CONSTRUCTION: 1.5.7.1 All materials used in the manufacture of cable shall be new unused and of finest quality. All materials should comply with the applicable provision of the tests of the specification. IS, IEC, Indian Electricity Rules, Indian Electricity Act and any other applicable statutory provisions rules and regulations. 1.5.8 CURRENT RATING: The cable will have current ratings and derating factors as per relevant standard IEC. 1.5.8.1 The one-second short circuit rating values each for conductor, screen & armour shall be furnished and shall be subject to the purchaser’s approval. 1.5.8.2 The current ratings shall be based on maximum conductor temperature of 90 deg. C with ambient site condition specified for continuous operation at the rated current. 1.5.8.3 SIZE: The different sizes of cable shall be 66 KV Single Core -3- a) b) c) d) e) 400mm2 630mm2 800mm2 1000mm2 1200mm2 1.5.9 OPERATION: 1.5.10.1Cables shall be capable of satisfactory operation under a power supply system frequency variation of plus minus 3% voltage variation of plus, minus 10% and combined frequency voltage variation of 10% (absolute sum). 1.5.10.2 Cable shall be suitable for laying in ducts or buried under ground. 1.5.10.3 Cable shall have heat and moisture resistance properties. These shall be of type and design with proven record on transmission network service. 1.5.11 LENGHTS: The cable shall be supplied in standard drum lengths as below: Size of cable Standard Drum Length a) 1c x 400mm2, 630mm2,800mm2, 1000mm2, 1200 mm2 750 meters + 5% tolerance and + 2% overall tolerance in total quantity of cable. 1.5.10 INDENTIFICATION MARKING: Identification of cables shall be provided externally at three meters’ intervals to identify as under:i) ‘Name of Manufacture’ ii) ‘Year of manufacture’ iii) ‘Voltage grade’ to be printed/embossed at the interval of one meter-length. The identification, by printing or embossing shall be done only on the outer sheath. Name of purchaser shall also be embossed. 1.6.0 TESTS 1.6.1 Type Tests The equipment offered should be type tested. Type test report should not be more than seven years old, reckoned from the date of bid opening, in respect of the following tests, carried out in accordance with ISS-7098/IEC-871, from Govt./Govt. approved test house, shall be submitted along with bid: i) Physical tests for insulation and outer sheath. ii) Bending test. iii) Di-electrical power factor test. iv) Heating cycle test followed by di-electrical power factor as a function of voltage and partial discharge test. v) Impulse withstand test. The remaining type test report as per clause 3 of ISS-7098/IEC-871/IEC-60840 shall be submitted by the successful bidder within three months from the date of placement of order. These type test reports shall be from Govt./Govt. approved test house and shall not be more than seven years old, reckoned from the date of placement of order. The failure to do so will be considered as a breach of contract. 1.6.2 ROUTINE TESTS AND ACCEPTANCE TESTS All routine and acceptance tests shall be carried as per relevant ISS in the presence of Nigam’s representative. -4- 1.7 INSPECTION The material shall be inspected and tested before dispatch by an authorised representative of the Nigam in respect of quality. The inspecting officer shall also satisfy himself about the correctness of length of cables as provided in Instruction No. 208 of E.B. Manual of Instruction 1963 Edition amended vide O/O No. G/BD-33(57) 75 dt. 18.04.75 now HVPNL. In case the supplier is not in a position to get these tests carried out at his works, such tests may be got carried out by him at any Govt. recognized test agency at his own expense. 1.8 TEST CERTIFICATES The supplier shall supply test certificates from a Govt. agency in respect of quality as per IS:7098(part-II) 1985 with latest amendments thereof for approval of the purchaser. 1.9 PACKING The cable shall be supplied in non-returnable wooden drum as per IS:10418:1982 so constructed, as to enable the cable to be transported on each drum. The cable wound on such drum shall be one continuous length. The ends of cables shall be sealed by means of non-hygroscopic sealing material. 1.10 MARKING The marking on the drum shall have the following information: a) b) c) d) e) f) g) h) i) j) k) l) m) 1.11 Reference to Indian Standard & cable code. Name of the manufacturer & trade name. Nominal cross section area of conductor for the cables. Number of core. Sequential No. at each meter. Type of the cable & voltage for which it is suitable. Length of cable on the drum. Approximate gross weight. Net weight of the cable. Drum identification number. P.O. No. and date. Consignee’s name with designation. Year of manufacture. DRAWINGS & INSTRUCTION MANUAL The tenderer shall supply the following drawings with the tender: i) Detailed drawing of the cable showing conductor, screening insulation, Armoring, outer sheath etc. ii) Detailed drawing showing jointing of cable and sealing of end boxes. Copies of instruction manuals for testing, installation jointing operation and maintenance of cables shall also be submitted with the offer for reference of the purchaser. 1.12 TECHNICAL & GUARANTEED PARTICULARS: The tenderer shall furnish guaranteed technical particulars as called for in appendix-I (Schedule-A) of this specification. Particulars, which are subject to guarantee, shall be clearly marked. Offer not containing this information will not be considered. -5- PART-II TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF 66kV XLPE UNDERGROUND POWER CABLE SECTION-1 SPECIFICATION FOR LAYING OF CABLE 1.1 1.1.1 LAYING OF POWER CABLE: The 66kV(E) XLPE cable shall be installed underground and normally buried directly in the ground complying with all applicable standards and IS:1255 & their amendments. 1.1.2 The sealing of power cable ends should be made during the storage; execution & completion of jointing works shall be in the scope of successful tenderer. In no circumstances, the cable ends shall be kept open. 1.1.3 Three single core cables shall be laid in trefoil formation. 1.1.4 The power cable shall be laid generally at a depth of 1500mm and can vary, if obstacles like power cable of other rating/telephone cable/water pipe line etc, come in the way of installation. At least minimum Depth of 1000 mm shall be maintained from nearest road level. 1.1.5 The cables shall be completely surrounded by a layer of having a low thermal resistivity (selected sand) sand about 250mm over & below of the cable surface throughout width of the cable trench at no extra cost. (River sand shall be allowed for surrounding layer). 1.1.6 The extra protection of pre-cost flat RCC slab with proportion 1:2:4 having size 600(L) X300(B) X 50(Thk) mm shall be provided about 250mm over the power cables for complete route of the cable. The RCC slab shall be with proportion not less than 1:2:4 (M-150) and also shall have steel reinforced of 6/8 mm dia. Steel bar (4 nos. of 300mm side and 5 Nos. on 600 mm side ) at adequate required distance. The slab shall be given curing time of minimum 15 days. 1.1.7 Normally, the back filling shall consist of the materials earlier excavated, however, bigger stones or piece of rock should be removed OR if required new soil has to be provided and used for back filling with no extra cost. 1.1.8 The cable drum must be handled correctly and with care during transport and laying of the power cables, in order to avoid damage to the cables. 1.1.9 The minimum bending radius of the cable shall be 30xD where D is diameter of the cable. 1.2 CROSSINGS: 1.2.1 a) Where road crossing comes in way of laying power cable, the power cable shall be laid through NP-4 RCC Hume Pipes. b) The RCC Hume pipe inner dia-meter shall not be less than 400mm. -6- c) The RCC pipes to be laid shall have minimum depth in such a way that the back filling on top surface of the pipe shall be at least 600mm in depth. The pipe joints shall be smooth so that cables are not damaged during pulling & operation. d) During the crossing of utilities like water line, drainage lines, telephone lines, gas lines etc. sufficient care shall be taken & protection shall be made available so that other utilities do not damage the cable mechanically and/or electrically or do not effect the performance of the cable. e) NALA CROSSINGS/CULVERT CROSSINGS: The Nala crossings are to be made with separate fly-over bridges of adequate sizes to carry all the cables in required formation. The bridges are to be made at the sufficient distances from the edge of Nala considering the further expansions of roads. The strength shall be such that it should not wash away with the flow of water during heavy rain. 1.3 IDENTIFICATOIN, MARKING AND WARNING: 1.3.1 The identification marker shall be of adequate size fabricated from 3mm thick, 25mmx25mm aluminium strip. The marker shall be embossed with letter as stated below: “Name of S/Stn” and “Phase R or Y or B" as the case may be . The marker shall be tightened with nylon thread along with each cable at interval of 3 meters in such a way that it does not damage/penetrate the outer sheath of cable because of the dead weight of back filled materials OR soil. 1.3.2 A pre-warning PVC yellow tape with size 152 mm (width) x 100 microns thick (HDDPE)/LLDPF shall also be laid as per following clause of the specification. The warning tape shall also contain the “WARNING” printed in black letters as under (In English as well as Hindi). “CAUTION: 66000 VOLTS HVPNL CABLE” CABLE” and “CAUTION: 132000 VOLTS HVPNL 1.3.3 A pre-warning tap as per above clause shall be laid below ground level in the earth about 400/500 mm deep along the route of cable and in jointing bays. 1.3.4 The cable route marker is to be made from R.C.C. blocks duly embossed on all the side as under:“HVPNL 66 KV CABLE LINE” The minimum size shall be 600x400x50mm. It shall be at least embedded in ground upto 400mm depth. The exposed portions shall be painted with non-washable paints. The interval should be minimum 30meters between two markers. It should be put at bends, curves, road crossing etc. of cable route. 1.4 TEST AFTER INSTALLATION: 1.4.1 Pre-commissioning tests on site, shall include the following:a) Insulation Resistance of each cable drum length after laying and before jointing. b) Tests for detection of damage to outer sheath, if any. -7- c) Serving insulation resistance after laying each cable length shall withstand a voltage of 10 KV DC for one minute between each reinforcement and external conducting surface; In addition, the serving insulation resistance shall be measured and checked with the values obtained during routine factory tests. d) On completion of the cable laying and jointing work, the complete installation shall be checked with a D.C. voltage of 3 Uo applied for 15 minutes between each conductor and sheath. e) f) Conductor resistance of each cable of each complete circuit. Test for 5 min. with system voltage applied between the conductor and the screen. g) Test for 24 hours with normal operating voltage of the system. h) Continuity & phase confirmation. Note: The pre-commissioning test at (f) or (g) at site to be undertaken as an alternative to the test (d). 1.5 1) 2) GENERAL: The cable laying shall have to be done, as per actual site condition at the time of execution, and as per the instruction of the engineer-in-charge. The end of cut pieces of cables left out during executions shall be sealed to prevent ingress of any moisture in the cable before handing over to consignee. -8- 1. 2. 3. 4. 5. 6. 6.1 6.2 SECTION-6 CHAPTER-7 TECHNICAL SPECIFICATION FOR 11 kV CROSS LINKED ETHYLENE INSULATED PVC SHEATHED SINGLE CORE AND THREE CORE POWER CABLES SCOPE This specification covers the design, manufacture, testing, inspection at manufacturer’s work, supply & delivery F.O.R. destination of 630mm2 Single Core XLPE insulated PVC sheathed Cable and three core XLPE cable suitable for solidly grounded system size as per clause(5) mentioned below. PARTICULARS OF THE SYSTEM The cable should be suitable for use on 50 Cycles, 3 Phases solidly earth neutral system & working voltage of 11kV. STANDARDS The cable covered under this Specification shall conform in all respects with the latest editions of IS-7098 (Part-2) 1985 & IS-8130-1984 & IEC:502 of the latest version thereof. TECHNICAL PARTICULARS 11kV, Single Core under ground XLPE insulated PVC sheathed cable suitable for working potential of 11kV on earthed system manufactured in accordance with IS-7098 (Part-2) 1985 with latest amendments. The Aluminium conductor shall comply with requirements specified in IS:8130-1984. The insulation shall be chemically cross-linked polyethylene confirming to the physical, electrical and ageing property as required in latest edition of IS-7098 (Part-2) 1985. Cable shall be provided with both conductor screening and insulation screening. The conductor screening shall be non-metallic and shall be consisting of either semi-conducting tape or a layer of semi-conducting compound or combination of two. The insulation screening shall consist of non-metallic semi conducting tape of extruded semi conducting compound layer in combination with non-magnetic metallic shield. Armouring shall be arranged over the core and it shall be of non-magnetic material. The material for the Armouring shall be as per relevant ISS. Over the Armouring the cable shall be provided with extruded PVC outer sheath. The composition of PVC compound shall be type ST-2 of IS-5831-1984. The colour of outer sheath shall be black or grey. SIZE The different size of the cable shall be: a) Single Core 630mm2 . b) Three Core 400mm2. c) Three Core 185mm2. d) Three Core 50mm2. TESTS Type Tests The equipment should be offered type test. Test reports should not more then seven years old reckoned from date of bid opening in respect of all the tests carried out in accredited laboratories (based on ISO/IEC) by a reputed accreditatic body or witnessed by HVPN or another electric power utility and be submitted by the successful bidder to HVPNL for approval as schedule given in Bar Chart. i) Physical tests for insulation and outer sheath. ii) Bending test. iii) Di-electrical power factor test. iv) Heating cycle test followed by di-electrical power factor as a function of voltage and partial discharge test. v) Impulse withstand test. The remaining type test report as per clause 3 of ISS-7098/IEC-871 shall be submitted by the successful bidder within three months from the date of placement of order. These type test reports shall be from Govt./Govt. approved test house OR from reputed Lab Abroad and shall not be more than seven years old, reckoned from the date of placement of order. The failure to do so will be considered as a breach of contract. ROUTINE TESTS AND ACCEPTANCE TESTS All routine and acceptance tests shall be carried as per relevant ISS in the presence of Nigam’s representative. -1- 7. 8. 9. INSPECTION The material shall be inspected and tested before dispatch by an authorised representative of the Nigam in respect of quality. The inspecting officer shall also satisfy himself about the correctness of length of cables as provided in Instruction No. 208 of E.B. Manual of Instruction 1963 Edition amended vide O/O No. G/BD-33(57) 75 dt. 18.04.75 now HVPNL. In case the Bidder is not in a position to get these tests carried out at his works, such tests may be got carried out by him at any Govt. recognized test agency OR from reputed Lab Abroad at his own expense. TEST CERTIFICATES The Bidder shall supply test certificates from a Govt. agency OR from reputed Lab Abroad in respect of quality as per IS:7098(part-II) 1985 with latest amendments thereof for approval of the HVPNL. PACKING The cable shall be supplied in non-returnable wooden drum as per IS:10418:1982 so constructed, as to enable the cable to be transported on each drum. The cable wound on such drum shall be one continuous length. The ends of cables shall be sealed by means of non-hygroscopic sealing material. 10. MARKING The marking on the drum shall have the following information: a) Reference to Indian Standard & cable code. b) Name of the manufacturer & trade name. c) Nominal cross section area of conductor for the cables. d) Number of core. e) Sequential No. at each meter. f) Type of the cable & voltage for which it is suitable. g) Length of cable on the drum. h) Approximate gross weight. i) Net weight of the cable. j) Drum identification number. k) P.O. No. and date. l) Consignee’s name with designation. m) Year of manufacture. Note: Cable should be marked with ISI Certification mark. 11. DRAWINGS & INSTRUCTION MANUAL The tenderer shall supply the following drawings with the tender: i) Detailed drawing of the cable showing conductor, screening insulation, Armouring, outer sheath etc. ii) Detailed drawing showing jointing of cable and sealing of end boxes. Copies of instruction manuals for testing, installation jointing operation and maintenance of cables, shall also be submitted with the offer for reference of the HVPNL. -2- SECTION-6 CHAPTER – 8 TECHNICAL SPECIFICATION FOR LT TWO CORE, 3½ CORE AND FOUR CORE PVC INSULATED UNARMOURED CABLE OFF SIZES FOR WORKING VOLTAGE UPTO & INCLUDING 1100 V, FOR SERVICE CONNECTIONS. 1. SCOPE:- This specification provides for design, manufacture, inspection at manufacturer’s works, testing before dispatch, supply and delivery of unarmoured 2 core, 3½ core and 4 core PVC sheathed Aluminium conductor cables for voltage upto 1.1 kV. 2. STANDARD:- LT distribution unarmoured cables shall be suitable for service voltage of 1100 volts (640 volts to earth) and made from high conductivity Aluminium conductor insulated with PVC compound and having inner and outer sheathing of PVC compound. The cables shall be strictly in conformity with ISS-1554/Part-I/1988 with latest amendments/ edition if any and shall be ISI/ IEC marked. The inner and outer sheathing shall be carried out as per relevant ISS. However, material manufactured as per any other International Standard which offers equivalent or materials better in quality and workmanship as compared to mentioned standards shall also be acceptable. Aluminium conductor complying with IS:8130-1984 shall be used. 3. CLIMATIC CONDITIONS:- The cable shall work satisfactorily under the following climatic conditions:i) ii) iii) iv) v) Maximum ambient temperature Minimum ambient temperature Maximum relative humidity Minimum relative humidity Altitude vi) vii) viii) Average no. of Rainy days per annum. Average annual Rain fall. Maximum wind pressure 50oC -2.5oC 100% 26% Below 1000 meters above mean sea level. 120 900 mm 195 Kg/ meter2 4 TECHNICAL PARTICULARS:- The cable shall be suitable for use on 50 Hz three phase AC solidly earthed Neutral power system working voltage of 3 x 240/ 415 Volt. 4.1 Sheathing:a) 4 Core Cables:- The Contractor has the option to provide inner and outer sheathing of PVC compound by single or separate pressure extrusion process as per relevant ISS. b) 3 ½ Core Cables. c) 2 core cable. i) ii) Inner and outer sheathing shall be provided by separate operation process only. Where inner and outer sheathing are to be provided with PVC compound (by separate operation) the sheathing are to be provided by pressure extrusion process. -1- iii) Where inner sheathing is to be provided with thermo plastic material or proofed tape which shall not be harder than PVC used for insulating and outer sheathing shall be provided with pressure extrusion process. Note:- Cable with sheathing by sleeves extrusion shall not be accepted. 5. SIZES:- The normal sizes of the cables shall be as per schedule of requirements as per requirement. 6. TESTS:- 6.1 TYPE TESTS:The equipment should be offered type test. Test reports should not more then seven years old reckoned from date of bid opening in respect of all the tests carried out in accredited laboratories (based on ISO/IEC) by a reputed accreditatic body or witnessed by HVPN or another electric power utility and be submitted by the successful bidder to HVPNL for approval as schedule given in Bar Chart. i) Tensile Test ii) Wrapping Test iv) Annealing Test v) Resistance Test 6.2 ROUTINE TEST As per quality assurance program (QAP) 6.3 ACCEPTANCE TEST:- The following acceptance tests as stipulated in the relevant IS8130:1984 shall be carried out by the Supplier in presence of HVPNL representative, unless dispensed with in writing by the HVPNL. a) b) c) d) Tensile test. Wrapping test. Resistance test. Annealing test. 7. MANUFACTURER IDENTIFICATION:- HVPNL alongwith brand name, manufacturer name, voltage rating, size and year of manufacture in English shall be embossed on the outer sheath of the cable at regular intervals of approximately 1 to 1.5 metre. 8. INSPECTION AND TEST:- An authorised representative of the HVPNL shall inspect, examine and test the equipment/ material in respect of quality, size and ratings as per ISS/ IEC mentioned above at the manufacturer’s works during or after the manufacture of goods prior to dispatch on receipt of a clear notice of minimum two weeks in advance to be reckoned from the date of receipt of the same by the HVPNL. No material will be allowed to be dispatched without prior inspection and approval. The inspecting officer of the HVPNL may also inspect the material during the course of manufacture. In case, inspection of any consignment is waived off by the HVPNL, the Contractor will be required to furnish the requisite test certificates (for acceptance as well as routine tests) for approval. It will be the responsibility of the Contractor to make adequate arrangements for testing of material at their works without any additional charge to the HVPNL. All testing instruments and appliances will be made available and material destroyed/ consumed during testing will be to the account of the Contractor. -2- 8.1 SAMPLING OF CABLES:a) Scale of sampling:- Samples shall be taken and tested from each lot for ascertaining the conformity of the lot to the required specifications. b) The number of samples to be selected as per table given below at random (the randomness of selection, random number tables shall be used as per IS:49051968. No. of drums to be taken permissible number of as sample (a). S.No. of drums/ No. of coils/ reels in lot. (n) Upto 50 51 to 100 101 to 300 301 to 500 501 to above No. of drums to be taken Permissible number of as sample. refectives. (n) (n) 3 0 5 0 13 0 20 1 31 2 The inspector shall have the option to take the sample (s) from any point in the length of any drums selected at random for carrying out various tests and total length of that particular drum(s) of such two pieces because of this sampling in such a particular case will be considered as one length. 9. 10. PACKING:- The cable shall be packed and supplied in non-returnable wooden drums provided with cast iron bushings to resist any damage during transit. Material offered for inspection should be duly packed provided with blank lead seals for the purpose of sealing by the Inspecting Officer. The Contractor will put their own seals also on the two ends of the cables. DRUM LENGTH:- The cable shall be supplied in standard lengths as under:Cable upto 185 sq.mm. = 500 Metres + 5% Cable above 185 sq.mm. = 250 Metres + 5% Non standards lengths not less than 100 metres each shall be acceptable upto 5% of the ordered quantity. A tolerance of + 5% is permissible allotted to each consignee with overall + 2% tolerance on the ordered quantity for completion of order. 11. MARKING:- The marking on the drums shall have the following informations:a) Trade mark, if any. b) Name of the manufacturer. c) Nominal cross sectional area of conductor of the cable. d) Year of manufacture. e) Type of cable and voltage for which it is suitable. f) Length of cable on the drum/ reel. g) Approximate gross weight. h) Number of cores and colour of cores. i) Net weight of the cable. j) Drum/ reel identification no. k) Purchase Order No. and Date. l) Consignee’s name with designation. m) ISI mark/ IEC mark. n) Direction of rotation of drum/ reel (by means of an arrow). o) Reference IS:1554/Part-I/1988. -3- SECTION-6 Chapter-9 TECHNICAL SPECIFICATION FOR AIR CONDITIONING SYSTEM 1.00.00 GENERAL 1.01.00 This specification covers supply, installation, testing and commissioning and handing over to HVPNL of Air Conditioning system for the control room building. Air conditioning units for control room building shall be set to maintain the following inside conditions. DBT 24.40 C +/- 20 C 1.02.00 The computer room and control room i.e. C&R Panel Room shall be air conditioned. 1.03.00 Air conditioning requirement of room indicated at clause No. 1.02.00 shall be met using split AC units. High wall type split AC units of 2TR capacity each with high wall type indoor evaporator unit shall be used for all rooms. 1.04.00 Scope The scope of the equipment to be furnished and services to be provided under the contract are outlined herein after an the same is to be read in conjunction with the provision contained in other sections/clauses. The scope of work under the contract shall be deemed to include all such items, which although are not specifically mentioned in the bid documents and/or in Bidder’s proposal, but are required to make the equipment/system complete for its safe, efficient, reliable and trouble free operation. 1.04.01 High wall type split AC units of 2TR capacity each complete with air cooled outdoor condensing unit having hermetically sealed compressor and high wall type indoor evaporator unit with cordless remote controller. 1.04.02 Copper refrigerant piping complete with insulation between the indoor and remote outdoor condensers as required. 1.04.03 PVC drain piping from the indoor units upto the nearest drain point. 1.04.04 Power and control cabling between the indoor unit and outdoor unit and earthing. 1.04.05 MS brackets for outdoor condensing units, condensers as required. 2.00.00 Specification of Split AC units 2.01.00 The split AC units will be complete with indoor evaporator and outdoor condensing units and cordless remote control units. -1- 2.02.00 Outdoor unit shall comprise of hermetically sealed reciprocating/rotary compressors mounted on vibration isolators, propeller type axial flow fans and copper tube aluminum finned coils all assembled in a sheet metal casing. The casing and the total unit shall be properly treated and shall be weatherproof type. They shall be compact in size and shall have horizontal discharge of air. 2.03.00 The indoor units shall be high wall type. The indoor unit shall be compact and shall have elegant appearance. They shall have low noise centrifugal blowers driven by special motors and copper tube aluminum finned cooling coils. Removable and washable polypropylene filters shall be provided. They shall be complete with multi function cordless remote control unit with special features like programmable timer, sleep mode and soft dry mode etc. 2.04.00 The split AC units shall be of reputed make. -2- SECTION-6 CHAPTER-10 TECHNICAL SPECIFICATIONS FOR OUTDOOR NON SEALED TYPE THREE PHASE 11 KV/433V DISTRIBUTION TRANSFORMERS OF 200 & 400 KVA CAPACITIES 1.0 SCOPE: This specification covers the design, engineering, manufacture, shop testing, supply & delivery of oil immersed, naturally cooled, three-phase, 50 Hz, double-would, outdoor type Distribution transformers of 200 &400KVA, capacity for use on systems with nominal voltages of 11 KV. Any other parts not specifically mentioned in this specification, but otherwise required for proper functioning of the equipment should be included by the tenderer in his offer. Transformers will be plinth mounted 2.0 STANDARDS: The transformers shall conform in all respect to IS: 1180-1981 & IS: 2026-1977 except where specified otherwise. Equipment meeting any other authoritative Standards which ensures an equal or better quality than the standards mentioned above will also be acceptable. In such cases the copy of standards (English Version) adopted should be enclosed with the tender. 3.0 CLIMATIC CONDITIONS: As per Vol-II Section-1. 4.0 PRINCIPAL PARAMETERS OF THE TRANSFORMER The transformer shall be suitable for outdoor service as step down transformer. The electrical parameters of the transformer shall be as follows:- 5.0 6.0 1) Rated HV voltage 11 KV 2) Rated LV voltage 433 volts 3) Connection (HV) Delta 4) Connection (LV) Star neutral brought out 5) Vector Group Dyn11 6) Material of winding For 200 KVA Aluminium, double wound type and for 400KVA Copper double wound type 7) Type of cooling ONAN 8) Max. current density in HV & LV Winding a) b) For aluminium wound 200 KVA T/F 1.5A/mm2 For copper wound T/F 400KVA 2.6 A/mm2 9) Method of system earthing NO-LOAD VOLTAGE RATIO The no-load voltage ratio shall be 11000/433V. TEMPERATURE RISE Neutral solidly earthed system The transformer shall be capable of operating continuously at its normal rating without exceeding the temperature rise limit. The temperature rise shall not exceed the limits of -1- 500C (measured by resistance) for transformer windings and 400C (measured by thermometer) in top oil above the ambient temperature when tested in accordance with IS. The transformer with higher temperature rise shall not be acceptable. Hot spot temperature shall not exceed 950C when calculated on an annual weighted average temperature of 350C as per IS:2026. 6.1 The limits of temperature rise mentioned above will have to be satisfied by the manufacturer by carrying the Heat run test at the lowest negative tap by feeding losses corresponding to the rated current of the tap. 7.0 (a) Equalization Formula: The losses at principal tap of each transformer shall be stated in the tender ONAN rating at full load at 750C. For the purpose of arriving at comparable prices, the iron, copper and auxiliary losses shall be capitalized as per capitalization formula given below: =3,86,700( Wi + 0.45 Wc) Where Wi = Iron (No load) Losses Wc= Copper (Load Losses) The maximum sealing of component and weightage average losses shall be as per clause 7.0 (b) and no positive tolerance shall be allowed on these values In case losses of the T/F are found to be higher then the specified values at any stage within three years from the date of commissioning the capitalized value of excess losses, as compare to the specified value shall be recovered as per following capitalization formula:Amount recoverable (Rs.)= 3,86,700(Wi + 0.45 Wc) 7.0 (b) Losses:The no load and load losses for 11/0.433 KV shall not exceed the values given in the following table:KVA No load losses in Load losses in Watts (Max) At Maximum Rating Watts (Max.) 75Deg.C. Weighted average losses (watt) 200 400 3135 1600 400 750 5000 2700 These losses are maximum allowable and there would not be any positive tolerance However, the manufacturer can offer losses less than above. The Bidder shall quote No-Load loss in KW at the rated voltage and frequency. The load loss in KW at principal tap at rated voltage, frequency & out put, for the temperature 75 degree centigrade at full load shall also be quoted. The Bidder shall guarantee these loss figures. 7.1 Noise level : 80 dB Transformer offers shall be rejected if audible sound level is higher than the values required by the owner. 8.0 IMPEDANCE: The recommended percentage impedance at 750C is 4.5% for 200KVA and 400KVA T/F with a tolerance as per IS:2026. -2- 9.0 9.1 WINDING The primary (HV) windings shall be connected in Delta and the secondary (LV) winding in Star (Vector system DYn11) so as to produce a positive displacement of 30 degree from the primary to secondary vectors of the same phase. The neutral of secondary windings shall be brought out to a separate insulated neutral terminal. The neutral is to be solidly earthed in a separate earth pit and the transformer body is to be connected to station grounding system. HV windings shall consist of single coil design. The copper wires for coil formation shall be of sufficient cross-sectional area to impart desired mechanical strength. All delta leads from HT coils as well as HT line leads should be taken out through DPC. The current density in these leads should not exceed 0.8A/sq.mm. 9.2 The winding shall be so designed as to produce minimum out of balance forces in the transformers. Transformers of 200 KVA shall be aluminium wound and sizes above 200 KVA shall be copper wound. The current density for aluminium wound transformer shall be limited to 1.5A/mm sq. and for copper wound transformer shall be limited to 2.6A/mm.sq. 9.3 The winding design shall ensure that all the coil assemblies are of identical voltage ratio and shall be interchangeable and repairing of the winding could be made easily without special equipment. 9.4 The conductor used in the coil shall be best suitable to the equipment and all the permanent current carrying joints in the winding and leads shall be properly sleeved and crimped/brazed instead of jointing with solder or welding. All LV coils ends shall be provided with brazed/crimped lugs and HV coil ends by brazing/crimping. 9.5 Double paper covering shall be used for winding insulation both for HV & LV windings. Electrical grade epoxy coated insulated paper shall be used for inter-layer insulation of the HV & LV coils, corrugated cylinder made of pre-compressed board shall be provided between HV & LV winding. Angle shaped and rings made from pre-compressed board shall be used between end coil and the core. OR For 200 KVA transformers DPC insulation shall be used, Electrical Grade Insulation Kraft paper in layers of total thickness not less than 4 mm shall be used for interlayer insulation, DPC and Kraft paper used shall be of uniform density and free from any foreign particles and shall conform to IS:698/56 and latest amendments thereof. The end turn of each layer shall be properly and fully covered to avoid interlayer flashover. Corrugated Cylinder made from pre-compressed insulation board should preferably be used between LV and HV windings. The insulation of coils shall be vacuum impregnated in oil to develop full electrical strength in the windings. All material used in the insulation and assembly of the winding shall be insoluble non catalytic and chemically inactive in the hot transformer oil and shall not soften or otherwise be adversely effected under operating conditions. The core and coil assembly shall be fully dried out in ‘Air Drying Oven’ till the coils are shrunken to the designed level and are completely dried. Only then they will be impregnated in the transformer oil. 9.6 Minimum gap of 25 mm shall be maintained between the end coils and core. 9.7 The overloading capacity of transformer shall be as per IS-6600. 9.8 The value of unbalance current shall not be more than 2% of the full load current. 10.0 10.1 CORE CONSTRUCTION The core shall be constructed from high grade, non-aging Cold Rolled Grain Oriented (CRGO) silicon steel laminations conforming to grade M4 or better. The maximum flux -3- density in any part of the cores and yoke at normal voltage and frequency shall be such that the flux density with + 12.5% voltage variation from rated voltage or frequency variation of -5% shall not exceed 1.6 Tesla. The bidder shall provide saturation curve of the core material proposed to be used. 10.2 The design of magnetic circuit shall be such as to avoid static discharge development of short circuit within itself or in the earthed clamping structure. 10.3 Each lamination shall be insulated such that it will not deteriorate due to mechanical pressure and the action of hot transformer oil. 10.4 a) Core material shall be directly procured either from the manufacturer or through their accredited marketing organization of repute and not through any agent. 10.4 b) All parts of the core shall be of robust design, capable of withstanding any shock to which they may be subjected during handling, lifting, transportation, installation and service including short circuit condition. Clamping of core and winding assembly with tank should be done by angle iron pieces, bolted to tank wall. 10.4 c) Adequate arrangement shall be provided to enable the core and winding be lifted by lifting lugs. Use of seconds CRGO steel for core construction is strictly prohibited. Bidder can –offer transformer made of other superior (Low, Loss) for material and they should furnish design details in their bid. Successful bidders should submit require type test certificates after issue of P.O. but before material offered for inspection. Note: “The core material should be imported directly from the reputed manufacturer. Core material shall be processed by slitting only. Core cutting/slitting be done in front of inspecting officers deputed by HVPN.” The tenderer shall ensure that the CRGO supplier should have BIS certification. 11.0 TANK CONSTRUCTION 11.1 The tank shall be of robust construction in accordance with the best engineering practice. The main tank of the transformer shall be fabricated from tested quality of mild steel of adequate thickness i.e. minimum 4.00 mm. (for side walls) and 6.00mm (for top & bottom plates). The tank shall be valid (V shape welding fillet) inside of tank two outside welding of tank to bear more pressure to avoid bursting. 11.2 To provide rigidity and to meet the pressure inside the tank, due to short circuit current, the tank shall be suitably stiffened. The stiffeners wherever applicable are provided on all the four side walls of the tank, designed not to retain water. 11.3 The tank cover shall be slightly sloping towards HV bushing and shall provide facilities for draining of water. 11.4 The transformer tank shall be complete with al accessories, lifting lugs and shall be designed as to allow the complete transformer tank, filled with oil to be lifted by crane or other means without risk of any damage and transported by Rail/Road without straining any joint and without causing leakage of oil. 11.5 Bolted inspection covers shall be provide on tank and top cover to inspect core, winding and have access to the bottom of bushing. -4- 11.6 The tank shall be capable of with standing the pressure of +/- 1 kg/cm2 without deformation. The permanent deflection of plate after pressure has been released shall not exceed the values given below: LENGTH OF PLATE DEFLECTION 750 mm 5 mm 751-1250 mm 6 mm 12.0 FINISH 13.0 The exterior of the transformer tank and other ferrous fittings shall be thoroughly cleaned, scraped and given a priming coat and two finishing coats of durable oil and weather resisting paints or enamel. The colour of the finishing coats shall be dark admiralty grey conforming to No. 632 of IS:5-1961 “Colours for Ready Mixed Paints (second revision)”. CLEARANCES The external electrical clearance between phase to phase and phase to earth shall be in accordance with Clause 7.1 of IS: 2099 shall not be less than the values given below:Voltage Medium Clearance Phase to Clearance Phase to earth (mm) Phase (mm) 11 KV Air 255 205 433V Air 75 55 The aforesaid clearances are minimum and no negative tolerance on these clearances shall be allowed. 14.0 BUSHINGS 14.1 Terminal arrangement: The transformer shall be fitted with three high voltages and four low voltage outdoor types porcelain bushing of appropriate voltage and current rating. Each terminal including the neutral shall be distinctly marked and coloured for phase voltage on both HV and LV sides. The system of marking shall be in accordance with the latest amendment of relevant IS. The electrical characteristics of high voltage bushing shall conform to latest version of IS: 2099 and IS: 3347. The low voltage bushing shall conform to latest version of IS: 7421. All porcelain bushing shall be homogeneous, free from flaws effecting its mechanical strength or dielectric quality. They should be well vitrified, uniformly glazed, tough and impervious to moisture. The creepage distance of all the bushing shall be 25mm per KV of highest system voltage suitable for heavily polluted atmosphere and the protected creepage distance not less than 50% of total. 14.2 14.3 14.4 Bushing terminals: To avoid bimetallic action at the point of connection to the copper windings and to the external aluminium cables/conductors, both- HV & LV bushing stems shall be made of aluminium alloy/copper confirming to the requirement of IS:3347. The terminal connectors shall receive ACSR on HT side. The terminals shall be directly screwed on to the stem to secure effective sealing the bushing. The transformers shall be provided with bimetallic connectors bushings both on HV & LV Side. 15.0 FITTINGS AND ACCESSORIES 15.1 The transformer shall be fitted with the following fittings & accessories. -5- (a) Two earthing terminals (b) Oil level indicator (c) Lifting lugs and platform lugs (d) Rating, diagram and terminal marking plate(s) (e) Silica gel breather of approved design containing min. 0.25kg dehydrated silica get (f) Drain-cum-Sampling valve (steel) welded to the tank. (g) Thermometer pocket with dial type thermometer on tank cover. (h) Air Release Plug (i) Pressure relief device in the form of explosion release vent. (j) Filling hole having P1-1/4 thread (with cover) on the conservator. (k) Filter valve-2 nos. on top and bottom ends of tank at opposite sides. (l) Conservator with filling hole and drain plug. (m) Porcelain bushings with arcing horns and terminal connectors on HV side. (n) Porcelain bushings on LV side and HV side conforming to IS-3347, part-1 and III of the latest version thereof with brass studs fitted with single gap arcing horns. (o) Off load tap changer (for above 200 KVA transformers with tapping range of +3% to -6% in steps of 3% each with a locking device. (p) Bimetallic terminal connector for HV/LV Bushings connecting to ACSR. (q) PSR Radiators duly tested for leakage and pressure. (r) Plain rollers ( 4 nos. bi-directional) suitable for use on 1000 mm gauge track with clamping device or base mounting arrangement as required. Note: (i) The fittings listed above are indicative and any other fittings which are generally required for satisfactory operation of the transformer are deemed to be included in the quoted price of the transformer. 16.0 CONSERVATOR 16.1 A conservator shall be provided with each transformer. The oil level gauge and the plain silica gel breathing device shall be fixed to the conservator which shall also be provided with a drain plug and a filling hole with a cover .In addition, the cover of the main tank shall be provided with an air release plug to enable trapped air to be released unless the conservator is so located as to eliminate the possibility of air being trapped in the main tank. 16.2 The inside diameter of the pipe connecting the conservator to the main tank shall be within 20 to 50 mm and it should project into the conservator in such a way that its end is approximately 20 mm above the bottom of the conservator, so as to create a sump for collection of impurities. The minimum oil level (corresponding to -50C) should be above the -6- sump level. Breather pipe should be connected at top of the conservator tank with two bends at right angles. 17.0 SEALING GASKETS All sealing washers and gaskets shall be made of oil and heat resistant Nitrile/Neoprene rubber/synthetic rubber bonded cork type RC-70C Gaskets. The oil level in the transformer shall be made up to the required level while the transformer filled with oil is maintained at a temperature of 450C. All steel screws, nuts and fasteners exposed to atmosphere shall be either galvanized or cadmium plated. 18.0 TRANSFORMER OIL The transformer shall be supplied complete with first filling of oil. The insulating oil shall comply with the requirements of IS:335/1983 with latest version thereof. Oil shall be filled under vacuum with a vacuum type filtering machine. 19.0 BASE MOUNTING ARRANGEMENT The under base of all transformers shall be provided to make them suitable for fixing mounting on plinth. 20.0 RATING AND TERMINAL MARKING PLATES(S) Each transformer shall be provided with non-detachable rating diagram and terminal marking plate(s) of weather proof material, fitted in a visible position and showing the complete information as given under clause 16 of IS:1980 (Part-I)-1981or any authoritative standards for transformers including the following details:i) HVPNL order no. & Date ii) Date of inspection iii) Property of HVPN. RADIATORS These shall be made of ERW tubes with minimum side thickness of 18 SWG. These tubes should be used in vertic formation without any bending and properly welded on both ends to common headers. These radiators should be individually test for leakage and pressure tests etc. before welding with the main tank. 21.0 22.0 TESTS AND INSPECTION All the tests shall be carried out in accordance with clause 16 of IS (Part-I) 1977 22.1 ROUTINE TESTS: All transformers shall be subjected to the following routine tests at the manufacturer’s works in accordance with IS 2026 and 1180 (Part-I): a) b) c) d) e) f) g) h) i) j) 22.2 Measurement of winding resistance. Ratio, Polarity and phase relationship. Measurement of Impedance voltage/short circuit impedance. Load losses. No load losses and no load current. Insulation resistance. Induced over voltage withstand. Separate source voltage withstand. Oil leakage test. Magnetic balance test and magnetizing current and low voltage. TYPE TESTS The following type tests shall be made on the transformers in addition to the routine tests from (a) to (f) as indicated in 22.1 above: -7- i) Temperature rise test shall be carried out on one unit from each lot as offered for inspection. ii) Air pressure tests: The tank shall be fixed with a dummy cover with all fittings including bushings in position and shall be subjected to the following pressure created inside the tank: a) 0.8 kg/cm2 above the atmospheric pressure for 10 minutes. b) A vacuum corresponding to (-) 0.7 kg/cm2 for 10 minutes. Permanent deflection of flat plate after pressure has been released, shall not exceed the value given below: LENGTH OF PLATE i) ii) iii) DEFLECTION Upto 750 mm 5 mm 751-1250 mm 6 mm Impulse voltage withstand test on all the three limbs of HT side as per clause 13 of ISS 2026/1991/Part-II conducted at some recognized/Govt. Test house not more than 7 years old from the date of bid opening shall required to be submitted. The dispatches shall only be allowed after successful conductance of this test. SHORT CIRCUIT TEST: This test shall be made in accordance with the details specified in IS 2026/1977 conducted at some recognized/Govt. Test house OR from reputed Lab Abroad not more than 7 years old from the date of bid opening shall required to be submitted. The dispatches shall only be allowed after successful conductance of this test. If short circuit tests on unit of similar design of transformer with capacity as per schedule had been conducted earlier than certificate shall be produced along with tender and the test need not be conducted. Unbalance Current Test: The value of unbalanced current indicated by the ammeter shall not be more than 2% of the full load current. No supplies will be allowed to be despatched without inspection by the HVPNL/its representative and without carrying out the impulse and short circuit tests satisfactorily. 22.3 FLUX DENSITY TEST: The Bidder shall arrange to conduct the flux density test on one of the cores of the transformers in each lot so as to ensure that the flux density does not exceed the maximum specified limit of 1.6 Tesla at normal voltage & frequency. 22.4 OIL TEST At least two samples of oil shall be drawn out of any two sizeable lots from total ordered quantity to ensure that the oil used complies with the requirements of the Specification as per ISS-335. However, inspecting officer can draw oil samples from any number of lots if considered necessary so as to ensure that transformer oil conforming to ISS is being used. The despatches for such lots shall be allowed only after receipt of satisfactory oil test results. 22.5 OIL LEAKAGE TEST: The air pressure tests provided as a routine test shall be carried out on 10% of the transformers in each lot. The firm shall ensure to get this test carried out strictly as per relevant ISS. 22.6 PHYSICAL CHECK ON VARIOUS DIMENSIONS (INTERNAL & EXTERNAL WEIGHT CLEARANCE ETC.) One No. transformer from each lot shall be opened for checking of core weight, size and weight of HT & LT conductor, quantity of oil and various clearances etc. -8- 22.7 INSPECTION The inspection shall be carried out by an outside inspection agency to be nominated by the Nigam’s representative. All tests & inspection shall be made at the place of manufacturer unless otherwise specifically agrees upon between the manufacturer and the HVPNL at the time of placing the order. The manufacturer shall afford the inspector representing the HVPNL all reasonable facilities, without charge, to satisfy himself that the material is being furnished in accordance with this Specification. 22.8 The HVPNL has the right to have the tests carried out at its own cost by an independent agency whenever there is any dispute regarding the quality of supply. If the transformer fails in the tests, the cost shall be borne by the Bidder and if it passes, the cost shall be borne by the Nigam. 22.9 The purity test of aluminium for winding shall be got conducted on sample of aluminium for assessing its quality, from two independent NABL accredited laboratories. 23.0 INSULATION RESISTANCE OF WINDINGS: The minimum insulation resistance values in Mega ohms between winding and earth when the transformer is filled with oil should be as below: INSULATED RESISTANCE VALUES IN MEGA OHMS BETWEEN WINDING AND EARTH 11000 Volt(HV) 433 Voltage(LV) 200C 800 400 300C 400 200 400C 200 100 500C 100 50 600C 50 25 The insulation resistance values will be measured with a 2500V, preferably motorized meggar and of some good standard manufacturer such as M/s Evershed & Vignole make. 24.0 TEST VOLTAGE Transformers shall be capable of withstanding the power frequency and impulse test voltages prescribed as below: NOMINAL SYSTEM VOLTAGE 11KV (rms) HIGHEST SYSTEM IMPULSE VOLTAGE TEST VOLTAGE 12KV (rms) 75KV (peak) POWER FREQUENCY TEST VOLTAGE 28KV (rms) 25.0 TOLERANCE OF ELECTRICAL PERFORMANCE Tolerance shall be according to clause 11 of IS:2026 (part-I/General:1977). 26.0 DRAWING AND LITERATURE The bidder shall submit four sets of final versions of complete and correct equipment drawings for purchaser’s approval along with bid in a sealed envelope. The purchaser shall communicate his comments/approval on the drawings to the supplier within 21 days from the date of issue of LOI. The submission of complete and correct readable drawings for approval is the responsibility of the bidder/supplier. The supplier shall, if so required by the purchaser, modify the drawings and resubmit four copies of the modified drawings for purchaser’s approval within two weeks from the date of purchaser’s comments. Then, the purchaser shall approve the revised drawings within two weeks from the date of its receipt. -9- The successful bidder shall also supply one set of instruction manual containing handling, installation, testing and commissioning of equipment at the time of despatch of material to the consignee with each equipment for our field staff. In addition, 5 sets of such bound manuals and final approved drawings shall be supplied for reference & record in our design office. One set of all the approved drawings and manual of instructions will be supplied along with each equipment without which the supply will not be considered as complete supply. 27.0 PACKING Transformers shall be delivered suitably packed. Although the method of packing is left to the discretion of the manufacturer, it should be robust enough for rough handling, that is occasioned during transportation by rail/road. - 10 - SECTION-6 CHAPTER-11 TECHNICAL SPECIFICATION OF 13.608MVAR 11KV AUTOMATICALLY SWITCHED CAPACITOR BANKS AT 66/11KV Power T/F. 1. SCOPE: 1.1. This specification covers design, engineering manufacture, testing at manufacturer’s works, supply and delivery, erection, testing and commissioning of 11 KV outdoor types 3 phase capacitor banks at site for out door installation along with necessary equipments in all respect. The ratings mentioned in the specification are given as per minimum requirement. Equipment of higher rating, if required be mentioned during bidding by the firm, otherwise it will be the responsibility of the firm to install the capacitor bank as per requirement without any extra cost. 1.2. The specification covers 3 phase, 50 Hz, Out door type automatically switched shunt capacitor bank intended for installation at 11 KV side of 66/11KV power transformers in various sub-stations. The equipment covered in this specification comprises Capacitor banks in steps, 0.2 % Series Reactors, Vacuum contactors, HT Fuses, RVT, CT, CRCA cubicle etc. 2. Climate Condition:1. Max. ambient air temperature 2. Min. ambient air temperature 3. Average Daily Max. Ambient temperature 4. Max. yearly weighed average ambient temperature 5. Max. altitude above mean sea level (Meters) 6. Minimum Relative Humidity (% age) 7. Maximum Relative Humidity (% age) 8. Avg. No. of Rainy days/year 9. Avg. annual rainfall 10. Maximum wind pressure 3. 500C - 2.50C 400C 320C 1000 26 100 120 900mm 195 Kg./m Sq. Applicable Standard: 3.1 Unless otherwise modified in this specification, the capacitor shall comply with latest version of IS: 13925:1998. The other components such as Vacuum Circuit Breaker, Isolator, CT, PT, LA, Vacuum Contactors, HT fuses, Series Reactors, Auxiliary equipment shall comply with the latest version of relevant Indian Standards/International standards. A. Capacitor banks: The capacitor banks are for use in a 3 phase 50 Hz 11 KV system. Capacitor bank shall consists series/parallel combination of small units of capacitor cells per phase, each with an out put rating of 400/200 KVAR, 7.3 KV single phase for 18000KVAR Capacitor Bank. Capacitor units should be connected in externally star with appropriate number of capacitors in parallel as per requirement. For Example 3 single units connected in star to obtain 1200/600 KVAR at 12.65 KV 3 phase or 2 capacitors units in parallel per phase with 3 phase connection in star to obtain 2400/1200KVAR at 12.65 KV 3 phase. Necessary number of steps should be provided to meet requirement given in the schedule. Table 1.0: Capacitor Bank Rating: Total Step Fixed Sr. Transformer Capacitor Configuratio Bank Rating base No Rating configur- n kVAr X No. at 12.65KV of units ation 1 25/31.5MVA, 18000KVAR 3600KVAR 3600KVARx4 3600KVAR+ 66/11kV T/F or 3600 KVAR 1800KAVARx8 x4 (with 400KVAR Cell) or 3600KVAR +1800KVARx8 (with 200KVAR Cell) Each capacitor unit shall be provided with external HT HRC fuse 12 KV class with suitable current rating. Capacitor shall meet following specifications: 4. Temperature Category: The capacitor shall be suitable for operation with upper limit of ambient 0 60 C. of temperature 5. Rated Voltage: The rated voltage of 3 phase capacitor banks shall be 11 KV (phase to phase) and maximum operational voltage shall be rated for 12.65 kV. 6. Rated Output: The Rated output of 3 phase capacitor banks shall be 3600, 7200, 10800, 14400, 18000KVAR at the maximum operational voltage of 12.65 KV intended for use in suitable combination on power transformers rating of 31.5 MVA. The standard basic unit rating of capacitors (single phase) shall be 400KVAR. The unit shall be connected in externally star formation with floating neutral. Permissible Overloads: For capacitor covered in this specification, the maximum permissible overloads with regard to voltage, current and reactive output shall not exceed the limits specified in IS:13925. 7. 8. Power Loss: The power loss in capacitors shall not exceed 0.2 watt / KVAR (Subject to tolerance of + 10 %). The capacitors offered should be built from best material obtainable and should develop min. losses. For comparison of various offers, equalization charges on account of differences in losses of capacitors in various offers shall be made at the rate of Rs. 66676/- per K.W. 9. Capacitor bank losses should be given at 500 C. The successful bidder shall also be penalised at the rate given, if during testing measured losses are found to be more than the guaranteed losses. Discharge device: Suitable discharge device shall be connected across the capacitor unit in accordance with the provision of IS:13925. The discharge device shall reduce the residual voltage from the crest value of the rated voltage to 50 V or less within 10 Minutes after the capacitor is disconnected from the source of the supply. 10. Earthing Connections: The container of each capacitor unit shall be provided with suitable earthing terminal clearly marked with “Earth” symbol. 11. Protective Fuses: The capacitor units shall be provided with either internal or external fuses, as per standard practice of the manufacturer shall supply the external HRC fuses together with fixing accessories; a set of six spare fuse links shall be supplied along with each capacitor bank. 12. General Requirements: The capacitor shall be of non-PCB type, using polypropylene film as the dielectric. Complete mounting brackets supporting insulators and all other components for formation of capacitor banks racks shall be supplied along with the capacitor units. Necessary foundation bolts/nuts shall also be supplied. The outside of the capacitor container and other structures should have smooth and tidy look and should be coated with the weather proof, corrosion-resistant paint of white or light grey. 13. Marking: The capacitor unit shall be provided with a rating plate and terminal markings as stipulated in IS: 13925. 14. TESTS: The bidder shall submit the type test report along with the bid. The switched capacitors shall be subjected to all the type, routine and acceptance test in accordance with IS: 13925. B. AUTOMATIC CONTROL UNIT 15. Switching Arrangement: The Automatic control unit shall be provided inside the control room to continuously monitor total KAVR requirement on secondary side of the transformer and shall automatically switch ON or switch OFF the capacitor banks through the operation of 12 KV Vacuum Contactor. Overriding provision shall be made for electrical switching ON or OFF of the capacitor switch by the operator from the ACU control box. 16. Time Delay: The switching ON operation will take place for period of 10 minutes. The switching OFF operation of relevant steps will be instantaneous. 17. Switching logic for optimum utilization of capacitor bank shall be submitted by bidder and shall be got approved from Purchaser. The decision of purchaser in this regard will be final. 18. Controls: The Automatic control unit shall instantly switch OFF the incomer VCB of capacitor bank in the following contingencies occurring in any of the phases. a) Voltage increased by 10% above the rated voltage of 11 KV. b) Power transformer current impedance (due to single phasing and for any other reasons) between any of the two phases exceeding 20 % of the lowest. c) Current increases in any capacitor unit by 30% above the rated current (only the relevant capacitor switch will open). Current between any of the two phases of the capacitor bank differs more than 15% of the lowest current of the 3 phases (only the relevant capacitor switch will open). 19. Monitoring Facility: A suitable ammeter with selector switch to indicate the capacitor current in each phases of the capacitor bank shall be provided on the ACU panel inside the control room. Indicating lamps will also be provided to indicate ON & OFF status of each capacitor bank. 20. Control Power: The DC control voltage for operation of the ACU shall be taken from sub-station battery. The standard DC control voltage at HVPNL Substations is 220 Volts. 21. Temperature Variation: The control equipment and associate circuitry shall be suitable for operation at an o o ambient temperature in the range of -5 C to (+) 60 C. 22. Protection of ACU: Besides in-built protection against lines surges and transient over voltages, suitable fuses shall be provided for protection against over current. The ACU shall remain fully functional during and after line surges and transient over voltages. 23. Control Unit Casing: Except for the terminals, the ACU shall be enclosed in a suitable casing so as to avoid ingress of dust. 24. SCOPE This specification covers 11 KV, 50 Hz, out-door type automatic capacitor switches suitable for switching capacitor banks of 3600 KVAR ratings or any other higher rating specified. 25. APPLICABLE STANDARDS Unless otherwise stipulated in this specification the capacitor switch shall comply with the latest version of IS:9920 (AC Switches for voltages above 1000 V). 26. RATED VOTAGE The rated voltage for the capacitor switch shall be 12 KV. This represents the highest system voltage corresponding to the nominal system voltage of 11 KV. 27. RATED CURRENT The switches shall be suitable for 200A for step configuration of 3600/1800KVAR Switches. 28. RATED CAPACITIVE SWITCHING CURRENT Note: The capability of the switch shall also take into account the parallel switching of capacitor bank steps. 29. RATED SHORT TIME CURRENT The rated short time symmetrical current for 1 second shall be 10KA (rms A.C. component). 30. RATED MAKING CURRENT The rated making current shall be 2.5 times the rms value of the a.c. component of rated short time capacity. 31. BASIC IMPULSE LEVEL (BIL) The rated basic impulse level of switch to earth as also across the open terminals shall be 75 KV. 32. CONTROL SUPPLY The control power for closing the switch shall be 230 V single phase AC supply. The closing mechanism shall be suitable for a voltage variation of (+) 10% to (-)20%. 33. DESIGN & CONSTRUCTION REQUIREMENSTS 33.1 TYPE The switches shall be of either vacuum or SF6 type. 33.2. The capacitor switches shall be of three phase construction and shall be suitable for remote operation. 33.3 The capacitor switch shall be suitable for outdoor installation and shall have sealed weather proof type construction. 33.4 The capacitor switch shall be provided with a mechanical indicator to show whether the contact is in open/closed position, locally, as also through indication on the ACU panel. Provision shall also be made for manual closing and opening. 33.5 The capacitor switch shall be provided with a mechanical indicator to show whether the contact is in open/closed position, locally, as also through indication on the ACU panel. Provision shall also be made for manual closing and opening. 33.6 The bushing provided on the switch shall have clamp type of terminals to directly receive aluminium conductors up to 10mm dia in both horizontal and vertical directions. The terminal arrangement shall be such as to avoid bimetallic corrosion. 34. OPERATING MECHANSIM The operating mechanism shall be either solenoid or motor charged spring for which the control supply shall be as per clause 32. 35. MECHANICAL AND ELECTRICAL ENDURANCE The switch shall be capable of performing not less than 10,000 mechanical operations and 10,000 electrical operations at 200A capacitive current without getting damaged. 36. MARKING The capacitor switch shall be provided with a legible and indelibly marked name plate with the following: a) Name of utility (i.e. HVPNL) b) Name of the manufacturer. c) Type, designation and serial number. d) Rated voltage and current. e) Rated frequency. f) Number of poles. g) Rated short time current (symmetrical). h) Rated making current. i) Rated capacitive switching current. j) P.O.No. 37. TESTS The switch shall be subjected to the following tests in accordance with the IS:9920 (Part-IV). 37.1 Type Tests a) Tests to verify the insulation level, including withstand tests at power frequency voltages on auxiliary equipment. b) Tests to prove that the temperature rise of any part does not exceed the specified values. c) Making and breaking tests including tests for the rated capacitive current. d) Tests to prove the capability of the switch to carry the rated short time current. e) Tests to prove satisfactory operation and mechanical/electrical endurance. 37.2 Routine Tests a) Power frequency voltage dry tests. b) Voltage tests for auxiliary circuits. c) Measurement of the resistance of the main circuits. d) Tests to prove satisfactory operation. D. AUXILARY EQUIPMENTS 38. Isolator: 38.1 The Isolator shall be outdoor type, 11 KV, 1250Amp, Single throw Double Break, off load type, triple pole, vertical gang operated switch and with earth switch. 38.2 Tests: The Isolator shall be type tested and shall be subjected to routine and acceptance test in accordance with IS: 1818-1972. 38.3 The bidder shall submit guaranteed technical particulars along with their bid. 39. 11 KV Indoor Vacuum Circuit Breaker with Panel: Already available in 11kV Panel Board Specification. 40. Current Transformer: 1.0 The current transformers shall be dry type, suitable current ratio and burden for measuring the capacitor current shall form part of the equipment to be supplied. These CT’s shall be form an either an integral part of Indoor VCB or integral part of Capacitor bank enclosure or may be separate outdoor type on structure. The accuracy class for the purpose of measuring the current shall be1.0. 1.1 Tests: The Current Transformer shall be type tested and shall be subjected to routine and acceptance test in accordance with IS: 2705. 1.2 The bidder shall submit guaranteed technical particulars along with their bid. 41. Lightning Arrestor: 1.0 The specification covers the supply, delivery, erection, testing & commissioning of 9 KV, 10 KA, station class heavy rating, gapless, metal (zinc) oxide surge arrestors complete along with clamps, complete fitting and accessories for installation on outdoor type 11 KV switchgear, transmission lines, transformers etc. 1.1 Tests: The Lightning Arrestors shall be type tested and shall be subjected to routine and acceptance test in accordance with IS: 3070. 1.2 The bidder shall submit guaranteed technical particulars along with their bid. 42. Residual Voltage Transformer: 1.0 The Residual Voltage Transformer shall be dry type, 11 KV class, 5 Limb, with three windings i.e. Star/ Star – Open delta. The Primary winding-I in Star, Secondary-I in Star for metering and Secondary-II in Open delta for protection. 1.1 Tests: The residual Voltage Transformer shall be type tested and shall be subjected to routine and acceptance test in accordance with IS: 3156. 1.2 The bidder shall submit guaranteed technical particulars along with their bid. 43. Vacuum Contactors: 1.0 The Vacuum contactor shall be 12 KV Class, 200 Amps, Three pole Vacuum contactors suitable for capacitor switching. It shall be electrically (solenoid) operated with operational voltage of 230 Volts AC or 220V DC and rated short time symmetrical current for 1 second shall be 10KA (rms A.C. component). 1.1 Tests: The vacuum contactors shall be type tested and shall be subjected to routine and acceptance test in accordance with IS/IEC. 1.2 The bidder shall submit guaranteed technical particulars along with their bid. 44. HT HRC Fuses: 1.0 Suitable indoor type 11 KV HRC fuses along with the mounting insulators etc. to provide proper protection for the entire installation shall form part of the equipment to be supplied. The rupturing capacity of the fuses shall be 12.5 KA. 45. Series Reactors: 1.0.0.2 % Series reactor per phase per step of capacitor rating for inrush current restriction to be connected on neutral end as per IS: 5553. The rated voltage shall be 12 KV. The reactor shall be dry type single phase reactors mounted on post insulators and designed to carry 130 % of rated current continuously without exceeding the temperature rise & shall be applicable for thermal class of insulation used. The reactor shall be mounted inside outside the capacitor cubicle on foundation. 1.1 Tests: The series reactor shall be type tested and shall be subjected to routine and acceptance test in accordance with IS: 5553. 1.2 The bidder shall submit guaranteed technical particulars along with their bid. 46. 11 KV HT Cable (XLPE): A Power Cable: 1.0 11 KV power cable shall be hot cured XLPE of following size conforming to IS: 7098 (P-II) amended latest. 11 KV Incoming: Three/Single core 2x400 Sq. MM. 11KV (E). Jointing kit shall be heat shrink type as per latest relevant IS specification for indoor and out door utilization matching with the above cables. [ 1.1 Cable Jointing: Jointing should be heat shrink type. All materials required for such type of jointing of XLPE cable shall be supplied by the contractor. The work shall be carried out only by licensed/ experienced cable jointer holding necessary license of cable jointing of appropriate grade. Sufficient surplus cable in the form of loop shall be left on both sides of the cable. B Control cable: The control cable shall conform to IS: 1554 (Part-I) 1976. All control cable shall be of copper and armored type. The bidder may furnish cable such schedule after finalization of sub-station layout, associated cable connection. 47. Capacitor Cubicle: It shall be free standing outdoor type sheet steel enclosure fabricated from 2 mm. thick CRCA sheets. Capacitor cubical shall be mounted on mild steel channel frame and base frame shall be provided with mounting holes for fixing on concrete foundation. All doors and covers shall be designed to avoid ingress of water, moisture, dust etc. and shall be provided with suitable gaskets to achieve IP-55 degree of protection. Covers and doors shall be provided with electrical interlocks to avoid access to live parts. In case some unauthorized person opens the door or covers, the main incomer breaker should be tripped. Viewing glasses shall be provided to view inside parts like fuses, contactors. CFL type internal panel lighting shall also be provided to have proper view in the night. Capacitor enclosure shall be duly painted with base coat of Epoxy based primer and final coat of polyurethane paint. FRP canopy shall be provided at the top and which projects about 200 mm beyond cubicle on all sides. All LT internal wiring shall be fire retardant cable of 2.5sq.mm. All cable entries shall be from bottom through cable glands of suitable size. HT XLPE cable entry shall be through a cable entry box mounted on cubicle or fixed separately on foundation and coupled to the cubicle. Necessary Danger plate & Name plate etc shall be provided at prominent places. All other necessary fittings and accessories should be provided by manufacturer to ensure safe and smooth operation of the equipment. 48. SUBMISSION AND APPROVAL OF DRAWINGS: Following drawings and technical documents shall be submitted along with the bid. • Technical data sheet • GA drawings. • Bill of Material. • General Technical Particulars. 49. INSTALLATION OPERATION AND MAINTAINANCE: The supplier shall provide: 1) Necessary manual on installation, operation and maintain ace as also the schedule for the routine testing or check ups of all the equipments covered by the installation. 2) List of recommended spares indicating prices and specialized test equipments required for the routine testing of the system. 50. GUIDANCE FOR PROCUREMENT: The entire equipment covered under this specification shall be covered as a single package to avoid the problem of mismatching for maintenance etc. 51. WARRANTY: The suppler shall guarantee satisfactory performance of the complete capacitor bank installation for a period of 18 months from the date of supply or 12 months from the date of commissioning, which ever is earlier. During the warranty period all repairs/replacements shall be carried out free of cost. 52. INSPECTION: All tests and inspection shall be made at the place of the manufacturer unless otherwise especially agreed upon by the manufacturer and the purchaser at the time of purchase. The manufacturer shall afford the inspector representing the purchaser, all reasonable facilities, without charge, to satisfy him that the material being supplied is in accordance with the specification. The purchaser has the right to get the tests carried out at his own cost from an independent agency, whenever there is a dispute regarding the quality of the supply. The manufacturer shall be responsible to pay penalty of Rs 20,000/- for each occasion at which the fake inspection call has been made or the material is rejected during testing/inspection by the authorized agency/representative of the Nigam. This penalty would be in addition to the expenses incurred by the Nigam in deputing the Inspecting Officer, carrying out such inspection. 53. Challenge Clause:The material offered/received after the inspection by the authorized inspecting officer may again be subjected to the test for or any parameter from any testing house/inhouse technique of the Nigam & the results if found deviating un-acceptable or not complying to approved GTP’s the bidder shall arrange to supply the replacement within thirty (30) days of such detection at his cost including to & fro transportation. In addition , penalty @10% of cost of the inspected lot of material shall be imposed. HARYANA VIDYUT PRASARAN NIGAM LIMITED TECHNICAL SPECIFICATION OF EXTRUDED FRLS PVC TYPE COPPER CONTROL CABLE (ARMOURED) E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-6 Chapter-12 Armoured Cont. Cable EXTRUDED FRLS PVC TYPE.doc -1- LIST OF CONTENTS CLAUSE NO 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.10 1.11 1.12 1.13 1.14 APPENDIX 'A' APPENDIX 'B' DESCRIPTION SCOPE STANDARDS ARMOURING INSULATION MATERIAL PACKING TEST AND INSPECTION QUANTITY GUARANTEED TECHNICAL PARTICULARS LIST OF REFERENCES DEVIATION FROM THE SPECIFICATION CLIMATIC CONDITIONS MARKING INSTRUCTIONS FOR STORAGE PAGE NO. 3 3 3 3 4 4 4 5 5 5 5 5 5 6 SCHEDULE OF REQUIREMENT GURANTEED TECHNICAL PARTICULARS 7 8 E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-6 Chapter-12 Armoured Cont. Cable EXTRUDED FRLS PVC TYPE.doc -2- 1.01 SCOPE :This specification covers the manufacture testing supply and delivery of P.V.C insulated, extruded FRLS PVC armoured copper control cables. The cables are required for 66kV voltage level circuits at 66kV Sub Station for the supervision, control & protection of H.V. power transformers and H.V transmission circuits. The reliability and long life of the control cable is therefore of paramount importance. All the control cables offered against this specification must bear I.S.I. certification mark. 1.02 STANDARDS:Copper control cable to be supplied shall be P.V.C insulated P.V.C Sheathed (FRLS), galvanized steel wire armoured for indoor and outdoor applications in air, in ground, in water and in concrete trenches. The control cables shall conform in all respects to the requirements of the latest edition of IS-1554 (Part-I) 1988 and its subsequent amendment (s), if any. 1.03 ARMOURING:The insulated cores shall be provided with inner sheath armouring and extruded FRLS PVC outer sheath as specified in standards stated under point 1.02 above. The control cable offered shall be suitable for use in systems upto 1100 volts. The conductors shall be composed of plan annealed high conductivity copper which before stranding shall be approximately circular in section, smooth, uniform in quality and free from scale, inequalities, spills, splits and other defects. The conductors shall conform to appropriate dimensions and resistance as per IS-1554 (part-I & II) 1988. The armouring shall be arranged over the inner sheath nominal diameter over the insulation of inner sheath does not exceed 13 mm. The armour of cable having a specified nominal dia greater than 13 mm shall consist of either galvanized round steel wires or galvanized steel strips. The dimension of the galvanized steel wires/strips shall conform to IS:1554 (part-I) 1988. The steel wires of strips used for armouring shall confirm to IS-3975-1967. The direction of lay of armour shall be opposite to that of outer layer of outer layer of cores. 1.04 INSULATION: The basic material approved as insulating compound shall consist of compounded polyvinyl chloride (PVC) or suitable co-polymers of which major constituent shall be vinyl chloride or mixture of polyvinyl chloride and suitable co-polymers which have been suitable compounded and processed so as to comply with the requirement of IS-1554 (part-I) 1988. The PVC compound going into the formation of insulation shall also comply with the provisions of IS-5831-1978 PVC insulation and sheath of electric cable. The insulation shall not crack or retract in normal use. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-6 Chapter-12 Armoured Cont. Cable EXTRUDED FRLS PVC TYPE.doc -3- The colour code of the cores of control cable shall be as per clause 10.1 of IS1554 (part-I) 1988. However, the outer PVC sheath shall be black or Grey. The colour coding as employed in the formation of the cables for individual cores and sheath shall be indicted in the bid. The PVC/co-polymer compounds going into the formation of the outer sheathing shall afford a high degree of mechanical protection besides being oil and weather resistant. 1.05 MATERIAL: All the material used in the manufacture of the cables shall be of the best available quality with regard to strength durability and shall also be manufactured according to best engineering practices. 1.06 PACKING: The cable shall be supplied in reels so constructed as to avoid any damage to the cable. The reels should be able to withstand rough handling during transportation and storage any loss on account of improper design of reel shall be borne by the supplier. The bidder shall clearly state the standard/lengths which are cable shall be supplied alongwith tolerance if any in their quotations. The cable wound on one drum shall be of continuos length and minimum length of control cable per drum shall not be less than 500 meters + 5%. However, the variation in total ordered quantity shall be limited to + 2%. 1.07 TEST AND INSPECTION: 1.07.1 TYPE TESTS: All armoured (FRLS) copper control cables would comply with the requirement of type tests as per IS-1554 (part-I) 1988 read with its subsequent amendment(s) if any. The type test report should not be more than seven years old reckoned from the date of opening of the price bid. However, those firms who do not possess above mentioned type test report shall have to submit type test report in the event of order within thirty days of issue of LOA. 1.07.2 ACCEPTANCE TEST: The control cables would be subjected to tests laid down in para 15.2 of IS1554 (part-I) 1988 before accepting a lot at the time of inspection. 1.07.3 ROUTING TESTS: Tests laid down in para 15.3 of IS-1554 (part-I) 1988 any other would be carried out in the presence of HVPN's representative and the test report would be submitted to the Chief Engineer/MM, HVPNL, Panchkula for approval before effecting despatch of armoured copper control cables. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-6 Chapter-12 Armoured Cont. Cable EXTRUDED FRLS PVC TYPE.doc -4- 1.08 QUANTITY: The required quantity of the cable is as per the schedule of requirement appendix 'A' to the specification. The length of the cable may be increased or decreased by 10% at the time of placement of purchase order or thereafter but in any case before the expiry of the contract. The contract shall supply such additional cable lengths on the same rates, terms and conditions. 1.09 GUARANTEED TECHNICAL PARTICULARS: The bidder shall give in his bid the guaranteed technical particular of the cables as per Appendix ‘B’ attached. Any additional information considered necessary by bidder (s) with a view to highlight the technical aspects of his offer may also be supplied under this head. The bidder(s) shall clearly state the current rating factors applicable to control cable as per item 23 of appendix 'B'. 1.10 LIST OF REFERENCES: List of references of similar cable already supplied with complete detail shall be furnished. 1.11 DEVIATION FROM THE SPECIFICATION: This should be clearly listed and brought out. 1.12 CLIMATE CONDITIONS: The control cables are required to operate satisfactorily under the following site conditions:a) b) c) d) e) f) g) h) 1.13 Maximum temperature Minimum temperature Maximum relative humidity Minimum relative humidity Isoceraunic level No. of rainy days per year Average rainfall per year Altitude 50°C -2.5°C 100% 26% 45 120 900 mm Below 1000 meters above mean sea level. MARKING: Every cable drum shall be clearly marked with indelible ink of with suitable weather resistant pain and shall bear the following particulars. i) ii) iii) iv) Manufacturer named and trade mark, if any Purchase order No. and date Year of manufacture. Nominal sectional area of conductor of the cable E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-6 Chapter-12 Armoured Cont. Cable EXTRUDED FRLS PVC TYPE.doc -5- v) vi) vii) viii) ix) x) 1.14 No. of cores Type of cable and voltage for which it is suitable Length of cable on the drum Gross weight of the drum Weight of tare Direction of rolling the drum. INSTRUCTION FOR STORAGE: Detailed instruction in regard to safe and proper storage of armoured control cables in our stores would be made available by the successful bidder (s) well before commencing despatch of the material. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-6 Chapter-12 Armoured Cont. Cable EXTRUDED FRLS PVC TYPE.doc -6- APPENDIX 'A' SCHEDULE OF REQUIREMENTS Sr. No. Description Qty. (in KMs) As per indent. E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-6 Chapter-12 Armoured Cont. Cable EXTRUDED FRLS PVC TYPE.doc -7- APPENDIX 'B' GUARANTEED TECHNICAL PARTICULAR To be filled in separately for each size of the armoured control cable. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. Name of manufacture Year of manufacture No of cores Cross-section of cores No. and diameter of wires Shape of conductor Material of conductor Current carrying capacity Insulation resistance Insulation thickness and material Thickness & material of inner sheath Nominal dia over inner sheath Conductor resistance Colour scheme of cores Thickness and material of outer sheath Test voltages both A.C. and D.C Type of armouring Cross section details of the galvanized steel wire/strips Maximum dia over armouring Length of cable per drum Net weight per drum length Gross weight per drum Current rating factors based on :a) Variation in ground temperature b) Variation in ambient air temperature c) Groups laid direct in ground in horizontal formation d) Groups laid direct in ground in tier formation e) Depth of laying in ground f) Ground laid in covered trenches in horizontal formation. 24. Standard E:\DATA AFTER 12.07.2011\REC Projects\REC-21D 06.01.2015\REC-21D Technical Document\Section-6 Chapter-12 Armoured Cont. Cable EXTRUDED FRLS PVC TYPE.doc -8- SECTION-7 1.0 1.1 1.1.1 1.2 1.3 1.3.1 1.3.2 TECHNICAL SPECIFICATION FOR SWITCHYARD ERECTION GENERAL This section covers the Technical requirements of various ancillary items and general switchyard erection practices. All ancillary items under the contractor’s scope of supply shall conform to the type tests and routine tests as per the relevant standards. STRING INSULATORS & HARDWARE GENERAL The insulators for suspension and tension strings shall conform to IS:731, long rod insulator shall conform to IEC-433(1980) and composite long rod insulator shall confirm to various standard mentioned in the specifications. Insulator Hardware shall conform to IS:2486. CONSTRUCTIONAL FEATURES Suspension and tension insulator shall be wet process porcelain with ball and socket connections. Insulator shall be interchangeable and shall be suitable for forming either suspension or strings. Each insulator shall have rated strength marking on porcelain printed and applied before firing. Porcelain used in insulator manufacture shall be homogeneous, free from Laminations, cavities and other flaws or imperfections that might affect the mechanical or dielectric quality and shall be thoroughly vitrified, tough and impervious to moisture. Glazing of the porcelain shall be uniform brown colour, free from blisters, burrs and other similar defects. When operating at normal rated voltage there shall be no electric discharge between conductor and insulator which would cause corrosion or injury to conductor or insulator by the formation of substances due to chemical action. No radio interferences shall be caused when operating at normal rated voltage. The design of the insulator shall be such that stresses due to expansion and contraction in any part of the insulator shall not lead to deterioration. All ferrous parts shall be hot dip galvanised in accordance with the latest edition of IS:2629. the zinc used for galvanising shall be of grade Zn-99.5 as per IS-209. the zinc coating shall be uniform, adherent, smooth, reasonably bright, continuous and free from imperfections such as flux, ash, rust stains, bulky white deposits and blisters. Bidder shall make available data on all the essential features of design including the method of assembly of discs and metal parts, number of discs per insulators, the manner in which mechanical stresses are transmitted through discs to adjacent parts, provision for meeting expansion stresses, results of corona and thermal shock tests, recommended working strength and any special design or arrangement employed to increase life under service conditions Insulator Hardware shall conform to the requirements stipulated for clamps and connectors. All Hardware shall be designed for tensile load with a factor of safety 2. Insulator Hardware shall be of forged steel. Malleable cast iron shall not be accepted except for insulator disc cap. The surface of Hardware must be clean, smooth, without cuts, abrasion or projections. No part shall be subjected to excessive localized pressure. The metal parts shall not produce any noise-generating corona under operating conditions. The tension insulator string shall be designed for the required tensile load Earth wire tension clamp shall be designed for the required tensile load with a factor of safety two (2). The tension insulator string assembly shall be supplied along with suitable turnbuckle at the rate of one turnbuckle per string. All Hardware shall be bolted type. TESTS In accordance with the requirements stipulated in section1 and section2, the suspension and tension strings, insulator discs and Hardware shall be conform to type tests as per relevant IS/IEC and shall be subjected to the following acceptance tests and routine tests. ACCEPTANCE TESTS FOR DISC INSULATOR Visual Examination (IS 2486-1971) Part 1. Verification of Dimensions : Cl no. 10.5 IS:731-1971 Temperature cycle test: Cl no. 10.6 IS:731-1971 Puncture Test: Cl no. 10.10 IS:731-1971 Galvanising Test: CI no. 10.12 IS:731-1971 Mechanical performance test : IEC:575-1977 Cl.4 Test on locking device for ball and socket coupling IEC:372(2)-1976. Porosity test Cl no. 10.11 IS:7311-971. ACCEPTANCE TEST ON HARDWARE FITTING Visual Examination: CI. 5. 10 IS:2486 (Part-1). Verification of Dimensions :CI. 5.8 IS:2486 (part-I)-1971. Galvanizing/Electroplating tests : CI. 5.9 IS:2486 (Part-I)-1971 Slip strength test :CI 5.4 of IS:2486 (Part-I). -1- 1.3.3 1.3.4 a) b) c) d) e) 1.4 1.4.1 1.4.2 Shore hardness test for the Elasto-meters (if applicable as per the value guaranteed by the Bidder). Mechanical strength test for each component. The load shall be so supplied that the component is stressed in the same way as it would be in actual service and the procedure as given in 13.1 (g) above should be followed. Test on locking devices for ball and socket coupling : IEC:372(2) – 1976. ROUTINE TEST ON DISC INSULATOR/ LONG ROAD INSULATOR Visual inspection :Cl. No. 10.13 IS:731-1971. Mechanical Routine Test : Cl. No. 10.14 IS:731-1971. Electrical Routine Test: Cl. No. 10.15 IS:731-1971. ROUTINE TEST OF HARWARE FITTINGS Visual examination :Cl. 5.10 of IS-2486(I). Mechanical strength test: Cl. 5.10 of IS-2486 (I). Samples taken from the zinc ingot shall be chemically analyzed as per IS:209 - 1966. The purity of zinc shall not be less than 99.5%. Chemical Analysis, mechanical hardness tests and magnetic – particle inspection for malleable casting: The chemical analysis, hardness tests and magnetic particle inspection for malleable castings will be as per the internationally recognised procedures for these tests. The sampling will be based on heat number and heat treatment batch. The details regarding tests will be as discussed and mutually agreed to by the Contractor and HVPNL in Quality Assurance Program. CHEMICAL ANALYSIS, HARDNESS TESTS AND MAGNETIC PARTICLE FOR FORGINGS The chemical analysis, hardness tests and magnetic particle inspection for forgings will be as per the internationally recognized procedures for these tests. The sampling will be based on heat number and heat treatment batch. CHEMICAL ANALYSIS, HARDNESS TESTS AND MAGNETIC PARTICLE INSPECTION FOR FABRICATED HARDWARE: The chemical analysis, hardness tests and magnetic particle inspection for fabricated hardware will be as per the internationally recognised procedures for these tests. The sampling will be based on heat number and heat treatment batch. PARAMETERS DISC INSULATORS a) Type of insulators : Anti Fog type b) Size of insulator units (mm) : 280 x 145 for 12000 kg. 255 x 145 for 9000/4500 kg. c) Electro mechanical strength : 12000/ 9000/ 4500 kg for Twin/ single conductor. d) Creepage distance of individual insulator units : Markings on porcelain shall be (minimum and as required to meet total creepage printed and applied before firing. distance).e) Markings. INSULATOR STRING 220 kV 132 kV 66 kV 33 kV 11 kV Power frequency withstand 460 kV (rms) 275 kV 140 kV 75 kV 28 kV (rms) voltage of the complete string with (rms) (rms) (rms) arcing horns (dry & wet) Lightning impulse withstand 1050 kV 650 kV 325 kV 170 kV 75 kV voltage of the complete string with corona control rings (+ and – peaks) Power frequency puncture 1.3 times actual wet flashover voltage of the unit. withstand voltage for a string insulator unit. RIV level of the complete string 1000 micro volts with CC rings at 1.1 U/-3 (max) Total creepage distance of the ---------------- 25 mm/kV -----------------complete insulator string (mm) Total no. of discs per strings. 15 S/T 10 S/T 6 S/T 3 S/T 2 S/T 14 S/S 9 S/S 5 S/S 3 S/S 2 S/S 1.4.3 Technical Description of Composite Long Rod Insulators 1.4.3.1 Details of Composite Long Rod Insulators The insulators of the strings shall consist of composite long rod insulators for a three phase, 50 Hz, effectively earthed 220kV sub-station application in a very heavy polluted environment. Couplings shall be ball and socket type. Bidder shall quote such composite insulators which have proven use under foggy/humid operational -2- S.No 1 1 2 1 2 1 2 1 2 1 2 1.4.3.2 1.4.3.3 1.4.3.4 conditions in polluted industrial environment combined with smoke and dust particles. The Bidder shall furnish evidence in the form of certification from the power utilities that the similar type of product supplied to them had been performing satisfactory. The Bidder shall also submit certified test report for an accelerated ageing test of 5000 hours such as that described in Appendix-C of IEC-61109. Insulators shall have sheds of the “open aerodynamic profile without any under ribs” with good selfcleaning properties. Insulator shed profile, spacing projection etc. shall be strictly in accordance with the recommendation of IEC-60815. The size of long rod insulator, minimum creepage distance, the number to be used in different type of strings, their electromechanical strength and mechanical strength of insulator string alongwith hardware fittings shall be as follows: Mechanical Type of *Size of Min. No. of ElectroStrength of String Composite Creepage individual Mechanical Insulator String Insulator Distance Units per Strength of String Insulator Unit along with (Core dia x (mm) (Nos.) (kN) Hardware Fittings Nominal (kN) length) (mm) 2 3 4 5 6 7 FOR 220kV AC yard of substations with AAC Tarantula/ACSR Zebra Conductor Single 20x2030 7595 1x1 90 90 Suspension Single 20x2175 7595 1x1 90 90 Tension FOR 132kV AC yard of substations with AAC Tarantula/ACSR Zebra Conductor Single 20x1305 4495 1x1 90 90 Suspension Single 20x1450 4495 1x1 90 90 Tension FOR 66kV AC yard of substations with AAC Tarantula/ACSR Zebra Conductor Single 20x725 2248 1x1 90 90 Suspension Single 20x870 2248 1x1 90 90 Tension FOR 33kV AC yard of substations with AAC Tarantula/ACSR Zebra Conductor Single 20x435 1124 1x1 90 90 Suspension Single 20x435 1124 1x1 90 90 Tension FOR 11kV AC yard of substations with AAC Tarantula/ACSR Zebra Conductor Single 20x290 750 1x1 90 90 Suspension Single 20x290 750 1x1 90 90 Tension Note: *The core dia of composite insulators mentioned at column No.3 is minimum requirement. The bidder shall offer composite long rod insulators of suitable core dia to meet specified E&M strength requirements. For offered core dia, the bidder shall submit documentary evidence of past supplies & satisfactory operation of the same for minimum period of three years. However, the overall string length shall be within the limits specified in the drawing. Pin and Cap Pin and cap shall be designed to transmit the mechanical stress and develop uniform mechanical strength in the insulator. The cap shall be circular with the inner and outer surfaces concentric of such design that it will not yield or distort under load conditions. The design shall be such as to permit easy removal of replacement of either insulator units or fittings under the live line conditions. Ball and Socket Designation The dimensions of the Ball and Socket shall be of 16mm designation for 90kN Insulator in accordance with the standard dimensions stated in IEC:120/ IS:2486 (Part-II). Dimensional Tolerance of Composite Insulators The tolerances on all dimensions e.g. diameter, length and creepage distance shall be allowed as follows: ± (0.04d+1.5) mm when d≤300 mm. ± (0.025d+6) mm when d>300 mm. Where, d being the dimensions in millimeters for diameter, length or creepage distance as the case may be. However, no negative tolerance shall be applicable to creepage distance. -3- 1.4.3.5 Interchangeability The composite long rod insulators inclusive of the ball & socket connection shall be standard design suitable for use with the hardware fittings of any make conforming to relevant IEC standards. 1.4.3.6 Corona and RIV Performance All surfaces shall be clean, smooth, without cuts, abrasions or projections. No part shall be subjected to excessive localized pressure. The insulator and metal parts shall be so designed and manufactured that it shall avoid local corona formation and shall not generate any radio interference beyond specified limit under the operating conditions. Maintenance The long rod insulators offered shall be suitable for employment of hot line maintenance technique so that usual hot line operation can be carried out with ease, speed and safety. All insulators shall be designed to facilitate cleaning and insulators shall have the minimum practical number of sheds and grooves. All grooves shall be so proportioned that any dust deposit can be removed without difficulty either by wiping with a cloth or by remote washing under live line condition. Materials Core It shall be a glass-fiber reinforced (FRP rod) epoxy resin rod of high strength. Glass fibers and resin shall be optimized. The rod shall be electrical grade corrosion resistant (ECR), boron free glass and shall exhibit both high electrical integrity and high resistance to acid corrosion. Housing & Weather sheds The FRP rod shall be covered by a seamless sheath of a silicone rubber compound of a thickness of minimum 3mm. The housing & weather sheds should have silicon content of minimum 30% by weight. It should protect the FRP rod against environmental influences, external pollution and humidity. It shall be extruded or directly molded on the core. The interface between the housing and the core must be uniform and without voids. The strength of the bond shall be greater than the tearing strength of the polymer. The manufacturer shall follow non-destructive technique (N.D.T.) to check the quality of jointing of the housing interface with the core. The technique being followed with detailed procedure and sampling shall be furnished along with the bid. The details for this shall be finalized during detailed engineering and finalization of MQP. The weather sheds of the insulators shall be of alternate shed profile. The weather sheds shall be vulcanized to the sheath (extrusion process) or molded as part of the sheath (injection moulding process) and free from imperfections. The vulcanization for extrusion process shall be at high temperature and for injection moulding shall be at high temperature & high pressure. Any seams / burrs protruding axially along the insulator, resulting from the injection moulding process shall be removed completely without causing any damage to the housing. The track resistance of housing and shed material shall be class 1A4.5 according to IEC60587. The strength of the weather shed to sheath interface shall be greater than the tearing strength of the polymer. The composite insulator shall be capable of high pressure washing. End Fittings End fittings transmit the mechanical load to the core. They shall be made of malleable cast iron spheroidal graphite or forged steel. They shall be connected to the rod by means of a controlled compression technique. The manufacturer shall have in-process Acoustic emission arrangement or some other arrangement to ensure that there is no damage to the core during crimping. This verification shall be in-process and done on each insulator. The gap between fitting and sheath shall be sealed by a flexible silicone rubber compound. The system of attachment of end fitting to the rod shall provide superior sealing performance between housing and metal connection. The sealing must be humidity proof and durable with time. Grading Rings Grading rings shall be used at both ends of each composite insulator unit for reducing the voltage gradient on and within the insulator and to reduce radio and TV noise to acceptable levels. The size and placement of the metallic grading rings shall be designed to eliminate dry band arcing/corona cutting/ exceeding of permissible electrical stress of material. The bidder shall furnish calculations along with the proposed placement and design of corona ring in support of the above. Grading rings shall be capable of installation and removal with hot line tools without disassembling any other part of the insulator assembly. The supply of grading rings shall be in the scope of the composite insulator supplier. Workmanship All the materials shall be of latest design and conform to the best modern practices adopted in the extra high voltage field. Bidders shall offer only such insulators as are guaranteed by him to be satisfactory and suitable for transmission lines specified and will give continued good service. The design, manufacturing process and material control at various stages shall be such as to give maximum working load, highest mobility, best resistance to corrosion, good finish and elimination of sharp edges and corners to limit corona and radio interference. 1.4.3.7 1.4.3.8 i) ii) iii) iv) 1.4.3.9 -4- 1.4.3.10 a) b) c) d) e) f) g) h) 1.4.3.11 (a) (b) (c) (d) (e) The design of the insulators shall be such that stresses due to expansion and contraction in any part of the insulator shall not lead to deterioration. The core shall be sound and free of cracks and voids that may adversely affect the insulators. Weather sheds shall be uniform in quality. They shall be clean, sound, smooth and free from gross defects and excessive flashing at parting lines. End fittings shall be free from cracks, seams, shrinks, air holes and rough edges. End fittings should be effectively, sealed to prevent moisture ingress, effectiveness of sealing system must be supported by test documents. All surfaces of the metal parts shall be perfectly smooth with the projecting points or irregularities which may cause corona. All load bearing surfaces shall be smooth and uniform so as to distribute the loading stresses uniformly. All ferrous parts shall be hot dip galvanized to give a minimum average coating of zinc equivalent to 600 gm/sq.m. and shall be in accordance with the requirement of ISO:1461 (E) and shall satisfy the tests mentioned in ISO:1460 (E). The zinc used for galvanizing shall be of purity of 99.95%. The zinc coating shall be uniform, adherent, smooth, reasonably bright continuous and free from imperfections such as flux, ash rust stains, bulky white deposits and blisters. The galvanized metal parts shall be guaranteed to withstand at least six successive dips each lasting for one (1) minute duration under the standard preece test. The galvanizing shall be carried out only after any machining. Equipment Marking Each composite long rod unit shall be legibly and indelibly marked with the trade mark of the manufacturer, name of HVPNL and month & year of manufacture. The guaranteed combined mechanical and electrical strength shall be indicated in kilo Newton followed by the word ‘kN’ to facilitate easy identification and to ensure proper use. One 10 mm thick ring or 20 mm thick spot of suitable quality of paint shall be marked on the cap/end fitting of each composite long rod of particular strength for easy identification of the type of insulator. The paint shall not have any deteriorating effect on the insulator performance. Following codes shall be used as identification mark : For 90 kN long rod unit : Orange Bid Drawings The Bidder shall furnish full description and illustration of the material offered. The Bidder shall furnish along with the bid the outline drawing (6 copies) of each insulator unit including a cross sectional view of the long rod insulator unit. The drawing shall include but not limited to the following information : Long rod diameter and ball to ball spacing with manufacturing tolerances Minimum Creepage distance with positive tolerance Protected creepage distance Eccentricity of the long rod unit Axial run out Radial run out Unit mechanical and electrical characteristics Size and weight of ball and socket parts Weight of composite long rod units Materials Identification mark Manufacturer's catalogue number After placement of award, the Supplier shall submit full dimensioned insulator drawings containing all the details as given in Clause No. 3.2 above, in four (4) copies to Employer for approval. After getting approval from Employer and successful completion of all the type tests, the Supplier shall submit 20 more copies of the same drawing to the Employer for further distribution and field use at Employer's end. After placement of award the Supplier shall also submit fully dimensioned insulator crate drawing for different type of insulators. After placement of award, the Supplier shall submit full dimensioned manufacturing drawing of composite long rod insulator unit in six (6) copies to the Employer for reference and record. Tests and Standards Type Tests The following type tests shall be conducted on long rod units, components, materials or complete strings: On the complete composite Long Rod Insulator String with Hardware Fittings Power frequency voltage withstand test with corona control IEC:383-1993/ rings/grading ring and arcing horns under wet condition Annexure A Switching surge voltage withstand test under wet condition IEC:383-1993 Impulse voltage withstand test under dry condition IEC:383-1993 Corona and RIV test under dry condition Annexure-A Mechanical Strength test Annexure-A -5- (f) (g) (a) (b) (c) (d) (e) (f) (g) (h) (i) (j) a) b) c) d) d) e) f) a) b) a) b) c) d) Vibration test Annexure-A Salt-fog pollution withstand test Annexure-A On Composite Insulator Units Tests on interfaces and connections of metal fittings (Tests to be IEC: 61109 performed on the same samples in the sequence given below) i) Dry power frequency voltage test ii) Sudden load release test iii) Thermal mechanical test iv) Water immersion test v) Steep front impulse voltage test vi) Dry power frequency voltage test Assembled core load time test IEC: 61109 i) Determination of the average failing load of the core of the assembled unit ii) Control of the slope of the strength time curve of the insulator Brittle fracture resistance test Annexure-A Test of housing, Tracking and erosion test IEC: 61109 Tests for the core material IEC:61109 i) Dye penetration test ii) Water diffusion test Flammability test IEC:61109 Recovery of Hydrophobicity test Annexure-A Mechanical Load Time test and test of tightness between end firings IEC:61109 and insulator housing Silicone content test Annexure-A High Pressure washing test Annexure-A All the type test given in Clause No. 4.1.1 shall be conducted on Single ‘I’ suspension, Double tension, Double ’I’ suspension & Quadruple tension insulator string along with hardware fittings. All the type tests given in Clause No. 4.1.1 (a) to (e) shall also be conducted on Single 'I' Pilot suspension & Single tension insulator string along with hardware fittings. Acceptance Tests: For Composite Long Rod Insulators Verification of dimensions IEC : 61109 Galvanising test IEC : 60383 Verification of locking system IEC : 60383 Verification of tightness of interface between end fittings and IEC : 61109 insulator housing and of specified mechanical load Recovery of Hydrophobicity Annexure-A Tests on interfaces and connections of metal fittings (Tests to be IEC: 61109 performed on the same samples in the sequence given below i) Dry power frequency voltage test ii) Sudden load release test iii) Thermal mechanical test iv) Water immersion test v) Steep front impulse voltage test vi) Dry power frequency voltage test Silicone content test Annexure-A The test 4.2.1.(e) shall be carried out in case total quantity of insulators of a particular rating exceeds 5000 nos. The test 4.2.1.(f) shall be done against each lot or against every 5000 nos. of insulators whichever is less. In the event of failure of the sample to satisfy the acceptance test(s) specified in 4.2 above, the retest procedure shall be as per clause 7.6 of IEC 61109. Routine Tests For Composite Long Rod Insulator Units Visual Inspection As per IEC:61109 Mechanical routine test As per IEC:61109 Tests During Manufacture On all components as applicable Chemical analysis of zinc used for galvanising As per Annexure-A Chemical analysis, mechanical, metallographic test and magnetic As per Annexure-A particle inspection for malleable castings. Chemical analysis hardness tests and magnetic particle inspection for As per Annexure-A forgings Tracking and erosion test on insulating material IEC 60587 Testing Expenses -6- a) b) c) d) Testing charges for the type test specified shall be indicated separately in the prescribed schedule. Bidder shall indicate unit type test charges for all type tests covered under Clause 4.1.1 and 4.1.2 separately, in the relevant schedule of Prices as applicable. Charges for each type tests shall be separately indicated. For Type Tests which involves the tests on the complete insulator string with hardware fitting, the Contractor of hardware fittings shall supply the necessary number of sets of hardware fittings at the place of testing free of cost. In case of failure in any type test the supplier whose material has failed is either required to modify the design of the material & successfully carryout all the type tests as has been detailed out in Clause 4.1 of this specifications or to repeat that particular type test at least three times successfully at his own expenses. In case of failure of the complete string in any type test, the manufacturer whose product has failed in the test shall get the test repeated at his cost. The Supplier whose material has not failed in the test shall be required to supply the requisite quantity of material (that is insulator or hardware fittings as the case may be) required for repeat testing at the place of testing and the cost of supply shall be borne by the Supplier whose material has failed in testing. Bidder shall indicate the laboratories in which they propose to conduct the type tests. They shall ensure that adequate facilities are available in the laboratory and the tests can be completed in these laboratories within the time schedule guaranteed by them in the appropriate schedule. The entire cost of testing for acceptance and routine tests and tests during manufacture specified herein shall be treated as included in the quoted Ex-works/CIF Price. In case of failure in any type test, if repeat type tests are required to be conducted, then all the expenses for deputation of Inspector/ Employer's representative shall be deducted from the contract price. Also if on receipt of the Bidder's notice of testing, the Employer's representative does not find the material or test setup / equipments to be ready for testing, the expenses incurred by the Employer for redeputation shall be deducted from contract price. The Bidder shall intimate the Employer about carrying out of the type tests along with detailed testing programme at least 2 week in advance (in case of testing in India) and at least 6 weeks advance (in case of testing abroad) of the scheduled date of testing during which the Employer will arrange to depute his representative to be present at the time of carrying out the tests. Sample Batch for Type Testing The Bidder shall offer material for sample selection for type testing only after getting Quality Assurance Programme approved by the Employer. The Bidder shall offer at least three times the quantity of materials required for conducting all the type tests for sample selection. The sample for type testing will be manufactured strictly in accordance with the Quality Assurance Programme approved by the Employer. Before sample selection for type testing, the Supplier shall be required to conduct all the acceptance tests successfully in presence of Employer's representative. Schedule of Testing The Bidder has to indicate the schedule of following activities in their bids : Submission of drawing for approval. Submission of Quality Assurance Programme for approval. Offering of material for sample selection for type tests. Type testing. Additional Tests The Employer reserves the right of having at his own expenses any other test(s) of reasonable nature carried out at Supplier's premises, at site, or in any other place in addition to the aforesaid type, acceptance and routine tests to satisfy himself that the material comply with the Specifications. The Employer also reserves the right to conduct all the tests mentioned in this specification at his own expense on the samples drawn from the site at Supplier's premises or at any other test centre. In case of evidence of non compliance, it shall be binding on the part of the Supplier to prove the compliance of the items to the technical specifications by repeat tests or correction of deficiencies or replacement of defective items, all without any extra cost to the Employer. Guarantee The Supplier of insulators shall guarantee overall satisfactory performance of the insulators. Test Reports Copies of type test reports shall be furnished in at least six (6) copies along with one original. One copy shall be returned duly certified by the Employer only after which the commercial production of the concerned material shall start. Copies of acceptance test reports shall be furnished in at least six (6) copies. One copy shall be returned duly certified by the Employer, only after which the material shall be dispatched. Record of routine test reports shall be maintained by the Supplier at his works for periodic inspection by the Employer’s representative. Test certificates of test during manufacture shall be maintained by the Supplier. These shall be produced for verification as and when desired by the Employer. -7- 1.4.3.12 1.4.3.13 1.4.3.14 Sl. No. 1. 2. 3. 4. 5. Inspection The Employer’s representative shall at all times be entitled to have access to the works and all places of manufacture, where insulator, and its component parts shall be manufactured and the representatives shall have full facilities for unrestricted inspection of the Supplier’s and subSupplier’s works, raw materials, manufacture of the material and for conducting necessary test as detailed herein. The material for final inspection shall be offered by the Supplier only under packed condition as detailed in clause No.4.13 of the specification. The Employer shall select samples at random from the packed lot for carrying out acceptance tests. The lot should be homogeneous and should contain insulators manufactured in 3-4 consecutive weeks. The Supplier shall keep the Employer informed in advance of the time of starting and the progress of manufacture of material in their various stages so that arrangements could be made for inspection. No material shall be dispatched from its point of manufacture before it has been satisfactorily inspected and tested unless the inspection is waived off by the Employer in writing. In the latter case also the material shall be dispatched only after satisfactory testing for all tests specified herein have been completed. The acceptance of any quantity of material shall be no way relieve the Supplier of his responsibility for meeting all the requirements of the specification and shall not prevent subsequent rejection, if such material are later found to be defective. Packing and Marking All insulators shall be packed in suitable PVC/ plastic tubes/any other suitable packing along with temporary wrap-on shields/shrouds for each insulator unit. The packing shall provide protection against rodent. The shields/shrouds shall be for protection during transport and for preventing bird pecking during erection. Further, the shields/shrouds shall be made of opaque, weather proof material of adequate strength and shall be colour coded. The shields/shrouds shall have smaller diameter than the insulator to stay in place against winds & weather and shall be designed so as to leave only the end fittings exposed for attachment of insulator to tower and line hardware until line construction is complete. The shield/shroud shall have suitable pull off loop for easy detachment just prior to charging of the line without causing any damage to the insulator. The bidder/Supplier shall furnish detailed design of the packing and shield/shroud along with attachment and detachment procedure in this regard. For marine transportation, crates shall be palleted. The packing shall be of sufficient strength to withstand rough handling during transit, storage at site and subsequent handling in the field. Suitable cushioning, protective padding, or dunnage or spacers shall be provided to prevent damage or deformation during transit and handling. The Supplier shall guarantee the adequacy of the packing and shall be responsible for any loss or damage during transportation, handling, storage and installation due to improper packing. All packing cases shall be marked legibly and correctly so as to ensure safe arrival at their destination and to avoid the possibility of goods being lost or wrongly dispatched on account of faulty packing and faulty or illegible markings. Each case/crate shall have all the markings stenciled on it in indelible ink. Standards The insulator strings and its components shall conform to the following Indian/International Standards which shall mean latest revision, with amendments/changes adopted and published, unless specifically stated otherwise in the Specification. In the event of supply of insulators conforming to standards other than specified, the Supplier shall confirm in his bid that these standards are equivalent or better to those specified. In case of award, salient features of comparison between the standards proposed by the Supplier and those specified in this document will be provided by the Supplier to establish equivalence. Indian Title International Standard Standard IS:209-1992 Specification for zinc BS:3436 IS:406-1991 Method of Chemical Analysis of Slab Zinc BS:3436 IS:731-1991 Porcelain insulators for overhead Power lines with a BS:137- (I&II) IEC:60383 nominal voltage greater than 1000 V IS:2071 Part Methods of High Voltage Testing IEC:60060-1 (I)- 1993 (Part(II)1991 Part(III)1991 IS:2486 Specification for Insulator fittings for Overhead Power Part- I-1993 Lines with a nominal voltage greater than 1000V Part- II-1989 General Requirements and Tests Dimensional BS:3288 Requirements IEC:60120 Part-III-1991 Locking Devices IEC:60372 -8- 6. IS:26291990 IS:26331992 IS:31881988 IS:67451990 IS:82631990 IS:82691990 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 1.4.3.15 a. b. c. d. Recommended Practice for Hot, Dip Galvanisation for iron and steel Testing of Uniformity of Coating of zinc coated articles ISO-1461 (E) Dimensions for Disc Insulators IEC:60305 Determination of Weight of Zinc Coating on Zinc coated iron and steel articles Methods of RI Test of HV insulators BS:433-1969 ISO:14601973 IEC:60437,NEMA Publn No.07/1964/ CISPR IEC:60506 Methods for Switching Impulse test on HV insulators Thermal Mechanical Performance test and mechanical IEC: 60575 performance test on string insulator units Salt Fog Pollution Voltage Withstand Test IEC:60507 Composite insulators for A.C. Overhead lines with IEC 61109 nominal voltage greater than 1000V – Definitions, test methods and acceptance criteria Guide for the selection of insulators in respect of IEC:60815 polluted conditions Tests on insulators of Ceramic material or glass or IEC:60383 glass for overhead lines with a nominal voltage greater than 1000V Characteristics of string insulator units of the long rod IEC : 60433 type Tests on Complete Strings with Hardware Fittings Annexure-A Corona Extinction Voltage Test (Dry) The sample assembly when subjected to power frequency voltage shall have a corona extinction voltage as per ISS/IEC applied line to ground under dry condition. There shall be no evidence of corona on any part of the sample. The atmospheric condition during testing shall be recorded and the test results shall be accordingly corrected with suitable correction factor as stipulated in IEC : 383. RIV Test (Dry) Under the conditions as specified in Corona Extinction Voltage Test (Dry)(a) above, the insulator string along with complete hardware fittings shall have a radio interference voltage level below 1000 micro volts at one MHz when subjected to 50 Hz AC voltage as per ISS/IEC applied line to ground under dry condition. The test procedure shall be in accordance with IS:8263 /IEC : 60437. Mechanical Strength Test The complete insulator string along with its hardware fitting excluding arcing horn, corona control ring, grading ring and suspension assembly/dead end assembly shall be subjected to a load equal to 50% of the specified minimum ultimate tensile strength (UTS) which shall be increased at a steady rate to 67% of the minimum UTS specified. The load shall be held for five minutes and then removed. After removal of the load, the string components shall not show any visual deformation and it shall be possible to disassemble them by hand. Hand tools may be used to, remove cotter pins and loosen the nuts initially. The string shall then be reassembled and loaded to 50% of UTS and the load shall be further increased at a steady rate till the specified minimum UTS and held for one minute. No fracture should occur during this period. The applied load shall then be increased until the failing load is reached and the value recorded. Vibration Test The suspension string shall be tested in suspension mode, and tension string in tension mode itself in laboratory span of minimum 30 metres. In the case of suspension string, a load equal to 600 kg shall be applied along the axis of the suspension string by means of turn buckle. The insulator string along with hardware fittings and the sub-conductors each tensioned at 43 kN shall be secured with clamps. The system shall be suitable to maintain constant tension on each sub-conductors throughout the duration of the test. Vibration dampers shall not be used on the test span. All the sub-conductors shall be vertically vibrated simultaneously at one of the resonance frequencies of the insulators string (more than 10 Hz) by means of vibration inducing equipment. The peak to peak displacement in mm of vibration at the antinode point, nearest to the string, shall be measured and the same shall not be less than 1000/f1.8 where f is the frequency of vibration in cycles/sec. The insulator string shall be vibrated for not less than 10 million cycles without any failure. After the test the insulators shall be examined for looseness of pins and cap or any crack in the cement. The hardware shall be examined for looseness, fatigue failure and mechanical strength test. There shall be no deterioration of properties of hardware components and insulators after the vibration test. The insulators shall be subjected to the Mechanical performance test followed by mechanical strength test as per relevant standards. -9- e. 1.4.3.16 1.4.4 1.4.4.1 1.4.4.2 1.4.4.3 1.4.4.4 1.4.4.5 1.4.4.6 1.4.4.7 1.4.4.8 1.4.4.9 Salt-fog pollution withstand test This test shall be carried out in accordance with IEC : 60507. The salinity level for composite long rod insulators shall be 160 Kg/m3 NACL. Composite Long rod Insulator Units Brittle Fracture Resistance Test Assembled core load time test with container that contains1n-HNO3 concentric acid that is applied at the naked rod. The rod should be held at 80% of SML for the duration of the test. The rod should not fail within the 96 hour test duration Recovery of Hydrophobicity Test The surface of selected samples shall be cleaned with isopropyl alcohol. Allow the surface to dry and spray with water. Record the HC classification. Dry the sample surface. Treat the surface with corona discharges to destroy the hydrophobicity. This can be done utilizing a high frequency corona tester, Holding the electrode approximately 3mm from the sample surface, slowly move the electrode over an area approximately 1” x 1”. Continue treating this area for 2 – 3 minutes, operating the tester at maximum output. Immediately after the corona treatment, spray the surface with water and record the HC classification. The surface should be hydrophilic, with an HC value of 6 or 7. If not, dry the surface and repeat the corona treatment for a longer time until an HC of 6 or 7 is obtained. Dry the sample surface. Allow the sample to recover and repeat the hydrophobicity measurement at several time intervals. Silicone rubber should recover to HC 1 – HC 2 within 24 to 48 hours, depending on the material and the intensity of the corona treatment. Silicone content test Minimum content of silicone as guaranteed by supplier shall be verified through FT-IR spectroscopy & TGA analysis or any other suitable method mutually agreed between Employer & Supplier in Quality Assurance Programme. High Pressure washing test The test is to be carried out at 3800 kPa with nozzles of 6 mm diameter at a distance of 3m from nozzles to the insulator, followed by a dry power frequency voltage test as per IEC 61109. Tests on All components (As applicable) Chemical Analysis of Zinc used for Galvanizing Samples taken from the zinc ingot shall be chemically analysed as per IS:209-1979. The purity of zinc shall not be less than 99.95%. Tests for Forgings The chemical analysis hardness tests and magnetic particle inspection for forgings, will be as per the internationally recognised procedures for these tests. The sampling will be based on heat number and heat treatment batch. The details regarding test will be as discussed and mutually agreed to by the Supplier and Employer in Quality Assurance Programme. Tests on Castings The chemical analysis, mechanical and metallographic tests and magnetic, particle inspection for castings will be as per the internationally recognised procedures for these tests. The samplings will be based on heat number and heat treatment batch. The details regarding test will be as discussed and mutually agreed to by the Supplier and Employer in Quality Assurance Programme. C-WEDGE CONNECTOR Wedge connector should be FIRED-ON or powder actuated only The power booster should be colour coded for proper installation of wedge connectors Wedge connector members- taperd ‘C’ shaped spring member and wedge should be made from a special Aluminium alloy of high ductility and electrical conductivity. When Installed, it will provide a tenable electrical and mechanical connection for solid or stranded conductor combinations including ACSR conductor The dimensions for the wedge shall be manufactured to close tolerance to ensure repeatability and reliability of the connection. All sharp edges and burrs shall be removed. The wedges shall be burnished to achieve optimum surface roughness for electrical contact. The wedge connector shall meet the current cycle test requirements as per ANSI C119.4-1998 Class AA. When connected as specified samples shall indicate electrical stability for terminated connectors. The resistance of connection, when measured as specified shall be stable through out test. The sample shall be tested to 500on/off current cycle with the control conductor raised between 1750C to 1800C above ambient. The wedge connector shall meet the mechanical requirements as per ANSI C119.4-1998 Class-3, minimum tension. When tested as specified or 5% of the rated cable strength of the weaker conductor. The Wedge connector shall meet the following thermal shock/salt spray test:a) Hours at 1500C b) 15 minutes at 0C water, immediately from the oven c) 30 minutes at 1500C - 10 - 1.4.4.10 1.4.4.11 1.4.4.12 1.4.4.13 2.0 2.1 2.1.1 2.1.2 2.1.3 a) b) c) d) e) f) g) h) i) j) a) b) c) d) e) 2.1.4 2.1.5 2.1.6 d) 20.75 hours at room temperature Salt spray corrosion, samples shall be subjected to a 30 day salt spray corrosion test. Each daily exposure shall consist of :a) 15 hours in 5% salt spray atmosphere b) 1 hour in drying over at 1000C c) 8 hours at room temperature During installation, the wedge of wedge shall be driven inside the “C” member at high velocity between the run & tap conductor so as to spread the “C” member to ensure high retentive force on the conductors. A locking tab, formed balance on the tool should prevent the wedge from loosening once it has been driven into position The wedge terminal shall have back up conductor cleaning capability during application. The wedge terminals should ensure stable & low contact resistance under varying load conditions & the thermal cycling effects. An oxide inhibiting compound placed in the wedge & “C” member groove of Wedge Terminals. CONDUCTOR AAC TARANTULA CONDUCTOR DETAILS OF CONDUCTOR SCOPE This specification provides for design, manufacture, engineering, inspection, stage testing and testing before dispatch, packing and delivery at site of All Aluminium conductor specified herein for its satisfactory operation on various Transmission lines and substations of the State. AAC Tarantula conductor is to be used as power conductor on single circuit and double circuit transmission lines and sub-stations of the HVPNL. STANDARDS The power conductor shall conform to the following Indian Standards, which shall mean latest revision, amendments/changes adopted and published, unless otherwise specified herein before. Sr ISS Title No 1. IS: 398 Part I to Specification for Aluminium conductors for overhead Transmission V (As relevant) purpose. 2. IS : 1778 Reels and Drums for Bare conductors 3. IS : 1841 EC grade Aluminium rod produced by rolling 4. IS : 5484 EC grace Aluminium rod produced by continuous casting and rolling PRINCIPAL PARAMETERS The detail of conductor are tabulated below Stranding and wire diameter 37/5.23 mm Al. Code name AAC TARANTULA Number of strands per layer of aluminium Wire Central 1 1st Aluminium layer 6 2nd Aluminium layer 12 18 3rd Aluminium layer Total Sectional area of aluminium (Sq. mm) 795.6 mm2 Overall diameter (mm) 36.61mm Approximate weight (kg/km) 2198 kg/km Calculated max. d.c. resistance at 20 Deg. C (ohm/km) 0.03656 Minimum UTS (kN) of conductor 11,600 kg. Modulus of Elasticity 0.5976x106 kg/cm2 Coefficient of linear expansion (per Deg.C) 23X10-6 The details of aluminium strand are as follows: Minimum breaking load of strand before stranding (kN) Minimum breaking load of strand after stranding (kN) 3.08 Maximum D.C resistance of strand of 20 Deg. C (ohm/km) 1.350 Diameter mm (Standard/Max/Min) 5.23/5.28/5.18 Mass (Kg/Km) 59.40 GENERAL TECHNICAL REQUIREMENT The ACC Tarantula conductor shall be suitable for being installed directly in air supported on suspension insulator strings or anchored through tension insulator strings at the power cross arms of single circuit and double circuit transmission line towers. The conductor shall therefore be suitable for satisfactory operation under the tropical climatic conditions listed under the Annexure III of Section 1. Physical constants of materials Physical constants for Hard-drawn Aluminium Resistivity The resistivity of aluminium depends upon its purity and its physical condition. For the purpose of this specification the maximum value permitted is 0.028264 Ω mm2/m at 20oC and this value has - 11 - Note: 2.1.7 2.1.8 2.1.9 2.1.10 2.1.11 2.1.12 2.1.13 2.1.13.1 Note: 2.1.14 Note: 2.1.15 Note: been used for calculation of the maximum permissible value of resistance. It is not intended to check the resistivity from the measured values of resistance. Density At a temperature of 20oC the density of hard drawn aluminium has been taken as 2.703 g/cm3. Constant-Mass Temperature Co-efficient of Resistance At a temperature of 20o C the constant – mass temperature co-efficient of resistance of hard drawn aluminium measured between two potential points rigidly fixed to the wire, the metal being allowed to expand freely, has been taken as 0.004 per degree Celsius. Co-efficient of Linear Expansion The co-efficient of linear expansion of hard-drawn aluminium at 0oC has been taken as 23.0x10-6 per deg. C. This value holds good for all practical purposes over the range of temperatures from 0o C to highest safe operating temperature. Materials The conductor shall be manufactured from EC grade aluminium rods suitably hard-drawn on wire drawing machines. The aluminium rods used shall comply with IS:1841-1978 and IS:5484. The mechanical and electrical properties of aluminium wire shall comply with the requirements given in relevant standard. The aluminium wire shall be manufactured from not less than 99.5% pure electrolytic aluminium rods of E.C. Grade. Freedom from Defects The wires shall be smooth and free from all imperfections such as spills, spilts, slag inclusion, die marks, scratches, fittings, blow-holes, projections, looseness, overlapping of strands, chipping of aluminium layers etc. and all such other defects which may hamper the mechanical and electrical properties of the conductor. Special care should be taken to keep away dirt, grit etc. during stranding. Wire Sizes Nominal Size The aluminium for the stranded conductor covered by this standard shall have diameters specified in clauses 2.1.3 Tolerances on normal size Aluminium Wires A tolerance of + 1% is permitted on the nominal diameter of AAC conductor. In order to maintain the circularity of the wires the tolerance allowed in 2.1.13.1 shall apply to both the measurement at right angles taken at the same cross-section as per clause 2.2 of IS:398 (PartII) (Second Revision with latest Amendments). Joints in wires Aluminium wires No joints shall be permitted in the aluminium wires in the outermost layer of the ACSR conductor. Joints in the inner layers are permitted, in addition to those made in the base rod or wire before final drawing, but no two such joints shall be less than 15 metres apart in the complete stranded conductor. Such joints shall be made by cold pressure butt-welding. Joints are not permitted in the outermost layer of the conductor in order to ensure a smooth conductor finish and reduce radio interference levels and corona losses on the extra high voltage lines. Stranding The wires used in the construction of all aluminium conductor shall, before stranding, satisfy all the relevant requirements of this specification. The lay ratio of the different layers shall be within the limits given in the table below LAY RATIO OF ALL ALUMINIUM CONDUCTOR No. of Lay Ratios for Aluminium Wires wires Al. Outside Layer Layer Immediately Innermost Layer of conductor with beneath out side layer three Aluminium Wire Layers Min. Max. Min. Max. Min. Max. 37 11.25 14 14 21 18 21 For the purpose of calculation, the mean lay ration shall be taken as the arithmetic mean of the relevant minimum and maximum values given in this table In all constructions, the successive layers shall have opposite directions of lay, the outermost layer being right-handed. The wires in each layer shall be evenly and closely stranded. The lay ratio of any aluminium layer shall not be greater than the lay ratio of the aluminium layer immediately beneath it. Standard Length The standard length of the conductor shall be 500 meters. A tolerance of +5% on the standard length shall be permitted. All lengths outside this limit of tolerance shall be treated as random lengths. Random lengths will be accepted provided no length is less than 70% of the standard length specified and the total quantity of such random lengths shall not be more than 5% of the total quantity ordered. - 12 - 2.2 2.2.1 2.2.2 a) b) c) d) e) f) g) h) 2.2.3 i) ii) iii) 2.2.4 i) ii) iii) 3.0 3.1 a) b) c) d) Supplier shall also indicate the maximum single length above the standard length, he can manufacture, in the guaranteed technical particulars. The conductor shall be supplied in standard drum length of manufacturer as per actual requirement. ACSR MOOSE/ ZEBRA CONDUCTOR DETAILS OF CONDUCTOR The conductor shall conform to IS:398(Part V)-1982 except where otherwise specified herein. The details of the conductor are tabulated below: Moose Zebra Stranding and wire diameter 54/3.53mm AL+7/3.53mm 54/3.18mm AL+7/3.18mm steel steel Number of strands core 1 1 1st Layer 6 6 2nd Layer 12 12 3rd Layer 18 18 4th Layer 24 24 Sectional area of Aluminium 528.5 mm2 428.9 mm2 2 Total sectional area 597 mm 484.50 mm2 Overall diameter 31.77mm 28.62 mm Approximate weight 1998 kg/km 1621 kg/km Calculated DC resistance at 0.05595 ohm/km 0.06868 ohm/km 20 degree C Minimum UTS 159.60 KN 130.32 KN The details of aluminium strand are as follow: Minimum breaking load of 1.57 kN 1.29 kN strand before stranding Minimum breaking load of 1.49 kN 1.23 kN strand after stranding Maximum D.C resistance of 2.954 ohms/KM 3.651 ohms/KM strand at 200C The details of steel strand are as follows: Minimum breaking load of 12.86 kN 10.43 kN strand before stranding Minimum breaking load of 12.22 kN 9.95 kN strand after stranding 18-before stranding Minimum no. of twist to be 18-before stranding 16-after stranding with stood in torsion test 16-after stranding when tested on a gauge length of 100 times diameter of wire Tests The type, acceptance and routine tests and tests during manufacture, shall be carried out on the conductor. For the purpose of this clause: Type tests shall mean those tests, which are to be carried out to prove the process of manufacture and general conformity of the material to this specification. These tests shall be carried out on samples prior to commencement of commercial production against the order. The supplier shall indicate his schedule for carrying out these tests in the activity schedule. Acceptance tests shall mean those tests, which are to be carried out on samples taken from each lot offered for pre-dispatch inspection, for the purposes of acceptance of that lot. Routine tests shall mean those tests which are to be carried out on each strand/spool/length of the conductor to check requirements which are likely to vary during production. Tests during manufacture shall mean those tests, which are to be carried out during the process of manufacture and end inspection by the Supplier to ensure the desired quality of the end product to be supplied by him. Samples for individual wires for tests shall be taken before stranding from not less than ten percent of the spools in the case of aluminium wires. If samples are taken after stranding, they shall be obtained by cutting 1.2 metres from the outer end of the finished conductor from not more than ten percent of the finished reels. The standards and norms to which these tests will be carried out are listed against them. For type and acceptance tests, the acceptance values shall be the values guaranteed by the Supplier in the Performa for “Guaranteed Technical Particulars”, furnished in the Annexure-II or the acceptance value specified in this specification, whichever is more stringent for that particular test. Acceptance Tests Visual and dimensional check Visual check for joints, scratches etc. and lengths of conductor. Dimensional check on aluminium strands Check for lay ratios of various layers - 13 - e) f) g) Note: 3.2 a) b) c) d) 3.3 3.4 3.5 3.6 3.7 3.8 Breaking load test on aluminium strands Wrap test on aluminium strands DC resistance test on aluminium strands All the above tests shall be carried out on aluminium strands after stranding only. Routine Tests Check to ensure that the joints are as per specification Check that there are no cuts, etc. on the strands. Check that drums are as per specifications. All acceptance tests are mentioned in Clause 6.2 above shall be carried out on each coil. Testing Expenses The testing charges for the type tests specified shall be indicated separately in the prescribed schedule. The supplier shall indicate the type test charges for each type test separately. In case of failure in any type, the supplier is either required to modify the design of the material or repeat the particular type test three times successfully at his own expenses. The decision of the Purchaser in this regard shall be final binding. Suppliers shall indicate the laboratories in which they propose to conduct the type tests. They shall ensure that the tests can be completed in these laboratories within the time schedule guaranteed by them in the appropriate schedule. The entire cost of testing for the acceptance and routine tests and tests during manufacture specified herein shall be treated as included in the quoted unit price of conductor, except for the expenses of the inspector/Purchaser’s representative. Additional Tests The Purchaser reserves the right of having at his own expenses any other test(s) of reasonable nature carried out at Supplier’s premises, at site, or in any other place in addition to the aforesaid type, acceptance and routine test, to satisfy himself that the material comply with the specifications. Sample Batch for testing Samples shall be obtained by cutting 2mtrs. length from the outer end of the finished conductor from minimum 10% of the finished drums offered for inspection. The Supplier is required to carry out all the acceptance tests successfully in the presence of Purchaser’s representative before dispatch. Test Reports Copies of type test reports shall be furnished in at least six(6) copies alongwith one original. One copy shall be returned duly certified by the Purchaser only after which the material will be dispatched. Record of routine test reports shall be maintained by the supplier at his works for periodic inspection by the Purchaser’s representative. Test Certificates of tests conducted during manufacture shall be maintained by the supplier. These shall be produced for verification as and when desired by the Purchaser. Test Facilities The following additional test facilities shall be available at Supplier’s works Calibration of various testing and measuring equipment including tensile testing machine, resistance measurement facilities, burette, thermometer, barometer etc. Standard resistance for calibration of resistance bridges. Finished conductor shall be checked for length verification and surface finish on separate rewinding machine at reduced speed (variable from 8 to 16 meters per minute). The rewinding facilities shall have appropriate clutch system and shall be free from vibrations, jerks etc. with transverse layering facilities. INSPECTION The Purchaser’s representative shall, at all times, be entitled to have access to the works and all places of manufacture where conductor shall be manufactured and the representative shall have full facilities for unrestricted inspection of the Supplier’s works, raw materials and process of manufacture and conducting necessary tests as detailed herein. The Supplier shall keep the Purchaser informed in advance of the time of starting and of the progress of manufacture of conductor in its various stages so that arrangements can be made for inspection. No material shall be dispatched from its point of manufacture before it has been satisfactorily inspected and tests, unless the inspection is waived off by the Purchaser in writing. In the later case also, the conductor shall be dispatched only after satisfactory testing for all tests specified herein has been completed and approved by the Purchaser. The acceptance of any quantity of material shall in no way relieve the Supplier of any of his responsibilities for meeting all requirements of the specification, and shall not prevent subsequent rejection if such material is later found to be defective. At least 10% of the total number of drums subject to minimum of two in any lot put up for inspection shall be selected at random to ascertain the length of conductor by the following method. “At the works of the manufacture of the conductor, the conductor shall be transferred from one drum to another at the same time measuring its length with the help of a graduated pulley & Cyclometer. - 14 - 4.0 5.0 The difference in the average length thus obtained and as declared by the Supplier in the packing list shall be applied to all the drums if the conductor is found short during checking.” DOCUMENTATION Six sets of type test reports, duly approved by the Purchaser shall be submitted by the Supplier for distribution, before commencement of supply. Adequate copies of acceptance and routine test certificates, duly approved by the Purchaser shall accompany the dispatched consignment. Approval of drawing/work by Purchaser shall not relieve the Supplier of his responsibility and liability for ensuring correctness and correct interpretation of the latest revision of applicable standards, rules and codes of practices. The material shall conform in all respects to high standards of engineering, design, workmanship and latest revisions of relevant standards at the time of ordering and Purchaser shall have the power to reject any work or material which in his judgement is not in full accordance therewith. PACKING & FORWARDING The conductor shall be supplied in non-returnable, strong wooden drums provided with lagging of adequate strength capable of withstanding displacement during transit, storage and subsequent handling and stringing operation in the field. The drums shall generally conform to IS: 1778-1980 except otherwise specified hereinafter. The drums shall be suitable for wheel mounting and for jetting off the conductor under a minimum controlled tension of the order of 5 kN. The Supplier shall submit the proposed drum drawings alongwith the bid. However, the same shall be in line with the requirements as stated herein. After placement of the Letter of Award, the Supplier shall submit four copies of fully dimensioned drawing of the drum he wishes to supply , for Purchaser’s approval before taking up manufacturing of Conductor. After getting approval from the Purchaser, the Supplier shall submit 30 more copies of the approved drawing to Purchaser for further distribution and field use at Purchaser’s end. All wooden components shall be manufactured out of seasoned soft wood free from defects that may materially weaken the component parts of the drums. Preservative treatment for anti-termite /anti fungus (Aldrime /Aldruse) shall be applied to the entire drum with preservatives of a quality which is not harmful to the conductor. The flanges shall be of two/three ply construction with each ply at right angles to the other and nailed together. The nails shall be driven from the inside face flange, punched and then clenched on the other face. The tolerance in thickness of each ply shall be +3 mm only. There shall be at least 3 nails per plank of ply with maximum nail spacing of 75mm. Where a slot is cut in the flange to receive the inner end of the conductor, the entrance shall be in line with the periphery of the barrel. The wooden battens used for making the barrel of the conductor shall be of segmental type. These shall be nailed to the barrel supports with at least two nails. The battens shall be closely butted and shall provide a round barrel with smooth external surface. The edges of the battens shall be rounded or chamfered to avoid damage to the conductor. Barrel studs shall be used for construction of drums. The flanges shall be holed and the barrel supports slotted to receive them. The barrel studs shall be threaded over a length on either end, sufficient to accommodate washers, spindle plates and nuts for fixing flanges at the required spacing. The Barrel studs should be tack-welded with the nuts after tightening. Normally, the nuts on the studs shall stand proud of the flanges. All the nails used on the inner surface of the flanges and the drum barrel shall be countersunk. The ends of barrel shall generally be flushed with top of the nuts. The inner check of the flanges and drum barrel surface shall be painted with a bitumen based paint. Before reeling, card board of double corrugated or thick bituminized waterproof bamboo paper shall be secured to the drum barrel and inside of flanges or the drum by means of a suitable commercial adhesive material. The paper should be dried before use. Medium grade Kraft paper shall be used in between the layers of the conductor. After reeling the conductor, the exposed surface of the outer layer of conductor shall be wrapped with think polythene sheet across the flanges to preserve the conductor from dirt, grit and damage during transportation and handling and also to prevent ingress of rain water during storage/transport. A minimum space of 125mm shall be provided between the inner surface of the external protective layer and outer layer of the conductor. Each batten shall be securely nailed across grains as far as possible to the flange edges with at least 2 nails per end. The length of the nails shall not be less than twice the thickness of the battens. The nail shall not protrude above the general surface and shall not have exposed sharp edges or allow the battens to be released due to corrosion. Outside the protective layer, there shall be a minimum of two binders consisting of hoop iron/galvanized steel wire. Each protective layer shall have two recess to accommodate the binders. The conductor ends shall be properly sealed and secured with the help of U-nails on one side of the flanges. The conductor shall be hinged by use of galvanized steel wire/aluminium wire at three locations at least 75mm apart or more covered with PVC adhesive tape so as to avoid loosening of conductor layers in transit and handling. Only one length of conductor shall be wound on each drum. - 15 - Marking Each drum shall have the following information stenciled on it in indelible ink alongwith other essential data: Purchase order number Name and address of consignee Manufacture’s name and address Drum Number Size of conductor Length of conductor in meters Gross weight of drum with conductor Weight of empty drum with lagging Arrow marking for unwinding a) b) c) d) e) f) g) h) i) 6.0 6.1 a) b) c) d) e) f) g) h) 6.2 6.2.1 6.2.2 6.2.3 6.2.4 6.2.5 6.3 6.4 6.5 6.5.1 GALVANISED STEEL EARTHWIRE DETAILS OF EARTHWIRE The galvanised steel earth wire shall generally conform to the Specification of ACSR core wire as mentioned in IS:398 (Part-II)-1976 except where otherwise specified herein. The details of the earthing are tabulated below: Stranding and wire diameter 7/2.50 mm steel 7/3.15 mm steel 7/3.66 mm steel Number of strands Steel core 1 1 1 Outer steel layer 6 6 6 Total sectional area 35.30 mm2 54.55 mm2 73.65 mm2 Overall diameter 7.50 mm 9.45 mm 10.98 mm Approximate weight 271 kg/km 428 kg/km 583 kg/km Calculated DC resistance at 5.56 Ω/km 3.375 Ω/km 2.5 Ω/km 200C Minimum ultimate tensile 36 KN 57 KN 68.4 KN strength Direction of lay of outer layer Right hand Right hand Right hand WORKMANSHIP All steel strands shall be smooth, uniform and free of all imperfections, such as spills and splits, die marks, scratches, abrasions and kinks after drawing and also after stranding. The finished material shall have minimum brittleness, as it will be subjected to appreciable vibration while in use. The steel strands shall be hot dip galvanised and shall have a minimum zinc coating of 275 gms/sq. m.) after stranding of the uncoated wire surface. The zinc coating shall be smooth, continuous, of uniform thickness, free from imperfections and shall withstand three and a half dips after stranding in standard preece test. The steel wire rod shall be of such quality and purity that, when drawn to the size of the strands specified and coated with zinc, the finished strands shall be of uniform quality and have the same properties and characteristics in ASTM designation B498-74. The steel strands shall be performed and post formed in order to prevent spreading of strands while cutting of composite earth wire. Care shall be taken to avoid damage to galvanization during pre forming and post forming operation. To avoid susceptibility towards wet storage stains (white rust), the finished material shall be provided with a protective coating of boiled linseed oil. JOINTS IN WIRES There shall be no joint of any kind in the finished steel wire strand entering into the manufacture of the earth wire. There shall be no strand joints or strand splices in any length of the completed stranded earth wire. TOLERANCES The manufacturing tolerances to the extent of the following limits only shall be permitted in the Diameter of the individual steel strands and lay length of the earth wire: Earth wire Standard Dia. Maximum Dia. Minimum Dia. 7/2.50 2.50 mm 2.56 mm 2.47 mm 7/3.15 3.15 mm 3.20 mm 3.10 mm 7/3.66 3.66 mm 3.75 mm 3.57 mm Lay length Earth Wire Standard Maximum Minimum 7/2.50 113 mm 135 mm 90 mm 7/3.15 160 mm 175 mm 145 mm 7/3.66 181 mm 198 mm 165 mm MATERIALS STEEL The steel wire strands shall be drawn from high carbon steel rod and shall conform to the following - 16 - 6.5.2 6.5.3 6.6 6.6.1 a) b) c) d) e) f) g) h) i) j) 6.6.2 a) b) 6.7 6.7.1 6.8 i.) ii.) iii.) 6.9 requirements as to the chemical composition: Element %Composition 7/2.50 mm steel 7/3.15 mm steel 7/3.66 mm steel Carbon 0.55 Max. 0.55 Max. 0.55 Max. Manganese 0.4 to 0.9 0.4 to 0.9 0.4 to 0.9 Phosphorus 0.040 Max. 0.040 Max. 0.04 Max. Sulphur 0.040 Max. 0.040 Max. 0.04 Max. Silicon 0.15 to 0.35 0.15 to 0.35 0.15 to 0.35 ZINC The zinc used for galvanising shall be electrolytic High Grade Zinc of 99.95% purity. It shall conform to and satisfy all the requirements of IS:209-1979. STANDARD LENGTH The earth wire shall be supplied in standard drum length of manufacturer as per actual requirement. TESTS In accordance with the requirements stipulated in Section1 and Section2, earth wire shall conform to type tests as per relevant IS/IEC and shall be subjected to the following acceptance tests and routine tests: ACCEPTANCE TESTS Visual check for joints, scratches etc. and length ) of Earth wire. Dimensional check ) Galvanising test ) Lay length check ) Torsion test ) Elongation test ) Wrap test ) DC resistance test ) IS:398 (Part – III) 1976 Breaking load test ) Chemical analysis of steel ) ROUTINE TESTS Check that there are no cuts, fins etc. on the strands. Check for correctness of stranding. TESTS DURING MANUFACTURING Chemical analysis of zinc used for galvanising. ) Chemical analysis of steel ) MARSHALLING KIOSK PRINCIPAL PARAMETERS The Marshalling Kiosk shall be suitably fixed so as to provide no opening to inside and shall be sufficiently projected to prevent splash of rainwater to the inside of the Marshalling Kiosk. The Marshalling Kiosk will be 1400 mm (height) 1200 mm (width) and 550 mm (depth) complete with double door in front provided with pad-locking facility in the door handle. The Marshalling Kiosk shall be bolted on the 550 mm high angle-iron frame work made of 35x35x6 mm MS angle braced lengthwise by 35x6 mm MS Flat. The Marshalling Kiosk shall be equipped with 3 No. earth test links made of tinned copper for CT circuits. TERMINAL BLOCK CONNECTORS Terminal block shall conform to requirements given in Section 2(GTR). The terminal connector will conform to the following details: Current & Voltage 30 Amps, 660VAC/900 VDC Ratings Capacity up to three ring-tongue crimped copper wires of 4mm2, cross sectional area. disconnecting type terminal blocks for CTs and PTs Terminal connectors for CT/PTs shall have provision of disconnecting and shortening links for measurement of CT currents without opening the CTs and isolation of PT circuits. DISTRIBUTION OF TERMINALS AND THEIR IDENTIFICATION NUMBERS The no. of terminals required shall be as follows: 220kV-300, 132kV-250 & 66kV-200. The total number of terminals in the Marshalling Kiosk will be distributed in ten rows. Terminal block connector row’s shall be adequately spaced and in no case less than 100 mm apart center of the terminal block so as to permit convenient access to terminations. Labels in the form of plastic/steel plates carrying numerals for terminal identification shall be so mounted as to cause no interference with regard to access to terminal nuts. The numerals marked from top to bottom in ascending order starting from left-hand side as viewed from the front of the - 17 - 6.10 6.10.1 6.11 6.11.1 6.11.2 6.12 6.12.1 6.13 6.14 6.14.1 6.14.2 a) b) 7.0 7.1 7.1.1 7.1.2 a) b) c) d) 7.2 a) b) c) d) e) f) Marshalling Kiosk and a progressively increasing from left hand side to right hand side. The numbering of Terminals and their arrangement in a 200, 250 and 300 terminals Marshalling Kiosks shall be as per sketch enclosed (Drg. No. C/ENG/HSEB/MB). EARTHING CONDUCTORS GENERAL All conductors buried in earth and concrete shall be of mild steel. All conductors above ground level and earthing leads shall be of galvanised steel. CONSTRUCTIONAL FEATURES GALVANISED STEEL Steel conductors above ground level shall be galvanised according to IS:2629. The minimum weight of the zinc coating shall be 610 gm/sq.m. and minimum thickness shall be 85 microns. The galvanised surfaces shall consist of a continuous and uniformly thick coating of zinc, firmly adhering to the surfaces of steel. The finished surface shall be clean and smooth and shall be free from defects like discolored patches, bare spots, unevenness of coating, spelter which is loosely attached to the steel globules, spiky deposits, blistered surfaces, flaking or peeling off etc. The presence of any of these defects noticed on visual or microscopic inspection shall render the material liable to rejection. TESTS Galvanised steel shall be subjected to four one minute dips in copper sulphate solution as per IS:2633. SPACERS GENERAL Spacers shall conform to IS-10162. CONSTRUCTIONAL FEATURES No magnetic material shall be used in fabrication of spacers except for GI Bolts and nuts. Spacer design shall be made to take care of fixing and removing during installation and maintenance. The design of the spacers shall be such that the conductor does not come in contact with any sharp edge. TESTS In accordance with requirements stipulated in Section1 and Section2, each type of spacer shall conform to type tests as per relevant IS/IEC and shall be subjected to the following, acceptance tests and routine tests in addition to those specified in IS/IEC: ACCEPTANCE TEST The acceptance tests shall be as per IS:10162 (latest revision). ROUTINE TEST Visual Examination Dimensional verification. EARTHING The earthing shall be in accordance with requirements given hereunder. The earthmat design shall be done by the contractor as per IEEE 80. The earthmat shall be connected to the existing earthmat in case of substations where earthmat is already laid. GENERAL Exact location of earthing connections shall be designed to suit the site conditions. Neutral points of system of different voltages, metallic enclosures and frame works associated with all current carrying equipments and extraneous metal works associated with electric system shall be connected to a single earthing system unless stipulated otherwise. Code of practice for Earthing IS:3043. Code of practice for the protection of building and allied structures against lightning IS:2309. Indian Electricity Rules 1956 with latest amendments. National Electricity Safety Code IEEE-80. DETAILS OF EARTHING SYSTEM ITEM SIZE MATERIAL Main Earthing Conductor 40 mm dia MS Rod Mild Steel Conductor above ground & 75x12 mm GS Flat Galvanised Steel earthing leads (for equipment) Conductor above ground & 75x12 mm GS Flat Galvanised Steel earthing leads (for columns & aux. Structures) Earthing of indoor LT panels, 50x6 mm GS Flat Galvanised Steel control panels marshalling boxes, MOM boxes, junction boxes & lightning panels etc. Rod electrode 40 mm dia, 3000 mm Mild Steel Pipe electrode upto water level 100 mm dia CI pipe with 13 CI mm thickness - 18 - g) h) 7.3 7.3.1 7.3.2 7.3.3 7.3.4 7.3.5 7.3.6 7.3.7 7.4 7.4.1 7.4.2 7.4.3 7.4.4 7.4.5 7.4.6 7.4.8 7.4.9 7.4.10 7.4.11 7.4.12 7.4.13 7.5 7.5.1 7.5.2 7.5.3 7.5.4 Earthing for motors flat 25x3 mm steel Galvanised Earthing conductor along 50x6 mm GS Flat Mild Steel painted with Red outdoor cable trenches primer Oxide EARTHING CONDUCTOR LAYOUT Earthing conductors in outdoor areas shall be buried at least 600 mm below finished grade level unless stated otherwise. Wherever earthing conductors cross cable trenches, underground service ducts, pipes, tunnels, railway tracks etc. It shall be laid minimum 300 mm below them and shall be re-routed in case it fouls with equipment/structure foundations Tap-connections from the earthing grid to the equipment/structure to be earthed, shall be terminated on the earthing terminals of equipment/structure. Earthing conductors or leads along their run on cable trench, ladder columns, beams, walls etc. shall be supported by suitable welding/cleating at intervals of 750 mm. Wherever it passage through walls, floors etc., galvanised iron sleeves shall be provided for the passage of the conductor and both ends of the sleeves shall be sealed to prevent the passage of water through the sleeves. Earthing conductor around the building shall be buried in earth at a minimum distance of 1500 mm from the outer boundary of the building. In case high temperature is encountered at some location, the earthing conductor shall be laid minimum 1500 mm away from such location. Earthing conductor crossing the road shall be laid 300 mm below road or at a greater depth to suit the site conditions. Earthing conductor embedded in the concrete shall have approximately 50 mm concrete cover. EQUIPMENT AND STRUCTURE EARTHING Earthing pads shall be provided by the Contractor of the apparatus/equipment at accessible position. The connection between earthing pads and the earthing grid shall be made by short and direct earthing leads free from kinks and splices. In case earthing pads are not provided on the item to be earthed, same shall be provided in consultation with engineer. Whether specifically shown in drgs. or not, steel/structure columns, metallic stairs etc. shall be connected to the nearby earthing grid conductor by two earthing leads. Electrical continuity shall be ensured by bonding different sections of hand-rails and metallic stairs. Metallic pipes, conduits and cable tray sections for cable installation shall be bonded to ensure electrical continuity and connected to earthing conductors at regular. Apart from intermediate connections, beginning points shall also be connected to earthing system. Metallic conduits shall not be used as earth continuity conductor. A separate earthing conductor shall be provided for earthing lighting fixtures, receptacles, switches, junction boxes, lighting conduits etc. Wherever earthing conductor crosses or runs along metallic structures such as gas, water, steam conduits etc. and steel reinforcement in concrete it shall be bonded to the same. Light poles, junction boxes on the poles, cable and cable boxes/glands, lockout switches etc. shall be connected to the earthing conductor running along with the supply cable which in turn shall be connected to earthing grid conductor at a minimum two points whether specifically shown or not. Railway tracks within switchyard area shall be earthed at a spacing of 30 mm and also by both the ends. Earthing conductor shall be buried 500 mm inside the switchyard fence. Every alternate post of the fence and gates shall be connected to earthing loop by one lead. Flexible earthing connectors shall be provided for the moving parts. All lighting panels, junction boxes, receptables fixtures, conduits etc. shall be grounded in compliance with the provision of I.E. rules. A continuous ground conductor of 16 SWG GI wire shall be run all along each conduit run and bonded at every 600 mm by not less than two turns of the same size of wires. The conductor shall be connected to each panel ground bus. All junction boxes, receptacles, lighting fixtures etc. shall be connected to this 16 SWG ground conductor. 50 mm x 6 mm MS flat shall run on the top tier and along the cable trenches and the same shall be welded to each of the racks. Further this flat shall be earthed at both the ends at an interval of 30m. The MS flat shall be finally painted with two coats of Red Oxide primer and coats of post office and red enamel paint. JOINTING Earthing connections with equipment earthing pads shall be bolted type. Contact surfaces shall be free from scale, paint, enamel, grease, rust or dirt. Two bolts shall be provided for making each connection. Equipment bolted connections, after being checked and tested, shall be painted with anti-corrosive paint/compound. Connection between equipment earthing lead and main earthing conductors and between main earthing conductors shall be welded/brazed type. For rust protections, the welds should be treated with red lead and afterwards thickly coated with bitumen compound to prevent corrosion. Steel to copper connections shall be brazed type and shall be treated to prevent moisture ingression. Resistance of the joint shall not be more than the resistance of the equivalent length of the conductor. - 19 - 7.5.5 7.5.6 7.5.7 7.6 7.7 7.7.1 7.7.2 7.7.3 7.7.4 7.7.5 7.7.6 7.7.7 7.8 7.8.1 7.8.2 7.8.3 7.8.4 7.8.5 8. 8.1 8.2 a) b) c) d) e) 9. 10. 10.1 10.2 11. 11.1 All ground connections shall be made by electric arc welding. All welded joints shall be allowed to cool down gradually to atmospheric before putting any load on it. Artificial cooling shall not be allowed. Bending of large rod/thick conductor shall be done preferably by gas heating. All arc welding with large dia. Conductors shall be done with low hydrogen content electrodes. POWER CABLE EARTHING Metallic sheaths and armour of all multi core power cables shall be earthed at both equipment and switchgear end. Sheath and armour of single core power cable shall be earthed at switchgear end only. SPECIFIC REQUIREMENT FOR EARTHING SYSTEMS Each earthing lead from the neutral of the power transformer shall be directly connected to one pipe electrode in independent treated earth pit up to water level which in turn, shall be buried in cement concrete pit with a cast iron cover hinged to a cast iron frame to have an access to the joints. One directly driven three meter MS Rod of 40 mm dia electrode shall also be provided on each neutral. In one substation minimum four number of independent pipe electrodes up to water level shall be provided at least one each at every neutral point of all transformer. All the pipe electrodes and rod electrodes shall be connected to the station main earth grid. Earthing terminal of each lightning arrester shall be directly connected to two rod electrode which in turn, shall be connected to station earthing grid. Capacitor voltage transformer , PT and down conductors of tower with peak etc. shall be directly connected to rod electrode which in turn, shall be connected to station earthing grid. Auxiliary earthing mat comprising of closely spaced (300mm x 300mm) conductors of 40 mm dia rod shall be provided at depth of 300 mm from ground level below the operating handles of the MOM Boxes of Isolators in area of 1.5m x 1.5m. MOM Boxes shall be directly connected to the auxiliary earthing mat. The auxiliary earthing mat shall be connected to main earth mat. Earthing of each Post Insulator base of Isolator and support Insulators of circuit Breakers is required to be connected with earthing strip. The earthing strips are required to be connected at the top of support structure on both sides and not at bottom. Insulating strings in the gantry beam are required to be connected at the base with common strip. SPECIFIC REQUIREMENTS FOR LIGHTNING PROTECTION SYSTEM Conductors of the lightning protection system shall not be connected with the conductors of the safety earthing above ground level. Down conductors shall be cleated on the structures at 2000 mm interval. Connection between each down conductor and rod electrodes shall be made via test joint located approximately 1500 mm above ground level. The bidders shall include the cost of test links in the erection price component of respective equipment/structure and no extra payment shall be made for the same. Lightning conductors shall not pass through or run inside G.I. conduits. All metallic structures within a vicinity of 2000 mm in air and 5000 mm below ground shall be bounded to the conductors of lightning protection system. MAIN BUS BARS The brief description of the bus switching scheme, bus bar layout and equipment connection already adopted are indicated in the SLDs enclosed with Section 1. The bidder shall furnish supporting calculations for the bus bars/conductors to show adequacy of design parameters for: Cantilever strength of Post Insulators. Short circuit forces and spacer location for each span of ACSR conductor stringing. Earthing design calculations. Direct stroke lightning protection. Ampacity calculations. BAY EQUIPMENT # The disposition of various bay equipment is shown in single line diagrams and standard section drawing/layout drawing enclosed with Section 1. LIGHTNING PROTECTION Direct stroke lightning protection (DSLP) shall be provided in the switchyard by shield wires. The layout drawings enclosed indicate arrangement. The final arrangement shall be decided after approval of the DSLP calculations. Rezvik method of lightning protection shall be followed. Any additional expenditure resulting from change of layout if required shall be to the firm’s account. The lightning protection system shall not be in direct contact with underground metallic service ducts and cables. TERMINAL POINTS The terminal points for the scope of work of switchyard are given below: LINE FEEDERS The transmission line shall terminate on line side gantry structure. The supply and erection of tension insulator string for line termination and tension clamps for earthwire are included in the scope of the bidder. - 20 - 11.2 12. 12.1.1 12.1.2 12.1.3 12.1.4 12.1.5 12.1.6 12.1.7 12.2 13 (A) a) b) Sr. No. 1. 2. 3. 4. 5. 6. Lightning protection down conductor at this end, tap offs and jumper connections from this dead end to all equipment in the switchyard are in Contractor’s scope. EQUIPMENT ERECTION NOTES All support insulators, circuit Breaker interrupters and other fragile equipment shall preferably be handled with cranes having suitable booms and handling capacity. The slings shall be of sufficient length to avoid any damage to insulator due to excessive swing, scratching by sling ropes etc. Handling equipment, sling ropes etc. should be tested periodically before erection for strength. Bending of compressed air piping should be done by a bending machine and through cold bending only. Bending shall be such inner diameter of pipe is not reduced. Cutting of the pipes wherever required shall be such as to avoid flaring of the ends. Hence only a proper pipe cutting tool shall be used. Hacksaw shall not be used. Muslin or leather cloth shall be used for cleaning the inside and outside of hollow insulators. All the equipment, instruments and auxiliaries required for testing and commissioning of equipment shall be arranged at site by the contractor. STORAGE The contractor shall provide and construct adequate storage shed for proper storage of equipments, where sensitive equipments shall be stored indoors. All equipments during storage shall be protected against damage due to acts of nature or accidents. The storage instructions of the equipment manufacturer/HVPNL shall be strictly adhered to. WIRING DIAGRAM AND CABLE SCHEDULES FOR TURNKEY PROJECTS At 400kV & 220kV Sub-Stations, Armoured Copper Control Cables with 350TB or more (depends upon control circuit termination) & 300TB MK resp. and at 132/66kV Sub-Stations Unarmoured Copper Control Cables with 250TB/200TB MKs are used. All cables from each equipment installed in a bay shall be routed through BMK to Control Room (for S/Stns without SAS). However, for 33kV voltage level MKs are not provided and Unarmoured Copper Control Cables from each equipment installed in a bay shall be routed directly to Control Room(for S/Stns without SAS). Further, Control cables shall be routed directly from equipments to AC kiosks for S/Stns. with SAS except for 400kV S/Stns. where cables shall be routed through BMKs to AC Kiosks. Voltage level for 400kV is designated by ‘AA’, 220kV is designated by ‘A’, 132kV is designated by ‘B’, 66kV is designated by ‘C’, 33kV is designated by ‘D’ and 11kV is designated by ‘E’. As per standard practice in HVPNL, following sizes of copper control cables are being used for 400/220/132/66/33kV voltage levels:3CX2.5Sq.mm, 7CX2.5Sq.mm, 10CX2.5Sq.mm, 16CX2.5Sq.mm, 4CX4Sq.mm, 2CX4Sq.mm, 2CX6Sq.mm and 7CX4Sq.mm and routed as under:- Size of Cables (Cores X Sq.mm) 7CX4 & 4CX4 4CX4 & 2CX4 7CX4 & 4CX4 4CX4 & 2CX4 4CX4 & 2CX4 2CX4 2CX4 4CX4 & 2CX4 MK TB No. TB-1 TB-1 TB-1 TB-1 TB-1 TB-2 7. 8. 2CX6 16CX2.5 or 10CX2.5 TB-2 TB-3 9. TB-3 10. 16CX2.5 or 10CX2.5 16CX2.5 or 10CX2.5 11. 10CX2.5 or 7CX2.5 TB-5 12. 13. 10CX2.5 or 7CX2.5 or 3CX2.5 16CX2.5 or 10CX2.5 TB-6 14. 15. 3CX2.5 16CX2.5 or 10CX2.5 TB-6 TB-7 TB-4 - Equipment Circuits to be used For 220kV CT Circuit (from Top) From MK to C&R Panel For 132/66kV CT circuits (From Top). From MK to C&R Panel For 33kV CT circuit Directly to C&R Panel. For 220/132/66kV NCT Circuit (Bottom TBs). For 33kV NCT circuit Directly to C&R Panel. For 230VAC Supply (From Top). (3-Phase 4wire & 1-Phase) For 220VDC Supply (From Bottom). From top, CB Trip Circuit (DC Supply-1/Auto Reclose / Remote Close / Remote Tip-1/ Prot. Trip-I / Remote Trip-II / Prot. Trip-II/ Post-Pre Close Sup. TC-I / Post-Pre Close Sup. TC-II / DC Supply-II) etc. For CB Alarm Circuit including spring charge indications (After CB Trip Circuits) For all CB N/C Contacts (Semaphore / Auto Trip / Trip Alarm / Close Indication / Digital Status), etc. For all CB N/O Contacts (Semaphore / Open Indication / Digital Status), etc. For 33kV VCB Tripping Circuit, Alarms and Indication For Bus Isolator-A N/C Contacts (From Top) For Bus IsolatorB N/C Contacts (From Middle) For Bus Isolator-A Electrical Interlocking Coil (Bottom). For Bus Isolator-A N/O Contacts (From Top) For Bus IsolatorB N/O Contacts (From Middle) - 21 - 16. 17. 3CX2.5 16CX2.5 or 10CX2.5 TB-7 TB-8 18. 19. 3CX2.5 16CX2.5 or 10CX2.5 TB-8 TB-9 20. 21. 22. 3CX2.5 3CX2.5 4CX4 TB-9 TB-10 23. 4CX4 TB-10 3CX2.5 TB-10 24. 2CX4 TB-10 25. 3CX2.5 TB-10 16CX2.5 or 10CX2.5 or TB-10 7CX2.5 1. 2. 3. 4. 5. c) For Bus Isolator-B Electrical Interlocking Coil (Bottom). For Line Isolator N/C Contacts (From Top) For Earth Switch N/C Contacts (From Middle) For Line Isolator Electrical Interlocking Coil (Bottom). For Line Isolator N/O Contacts (From Top) For Earth Switch N/O Contacts (From Middle) For Earth Switch Electrical Interlocking Coil (Bottom). For 33kV Isolators / Line &Earth Switch semaphore. In case of Bus Coupler Bay PT Circuits (From Top) In case of Line Bay with 3No. CVTs CVT Circuits (From Top) KCVT Supply for Electrical Interlocking (From Bottom) In case of Line Bay with 1No. CVT CVT Circuits and KCVT Supply for Electrical Interlocking (From Bottom) In case of T/F Bay T/F Tripping Contacts (From Top) T/F Alarm Circuits (After trip Circuits) NOTE:In case of transformer and Bus Coupler bays, TB No. 8 & 9 of MK will remain spare since L&E does not exist. In case, all CB alarm wires do not get accommodated on Bottom part of TB-3 of MK then shift all CB alarm wires on Bottom part of TB-5 of MK. In case of 33kV Bays suitable Terminal Junction Box shall be erected near CTs and wires from CT will be taken to JB & then to Control Room. Suitable rating of fuses & links shall be provided for AC & DC Supply by firm. 10% spare capacity of cores shall be kept spare in each size of cables used for each circuit and intermixing of cables is not allowed for wiring. As per HVPNL standard practice cable marking be done as given below and Cable ferrule Numbering shall start from equipment and the numbers will continue in sequential order for outgoing cables to Control Room for same equipment. MK TB Purpose Cable Numbering No. TB-1 CT/NCT Circuit Starting from 401 TB-2 For AC AC Supply for Adj. MK / ACDB -801 AC Supply for C&R Panel from ACDB -802 TB-2 For DC DC Supply for Adj. MK / DCDB -101 DC Supply for C&R Panel from DCDB -102 TB-2 For AC Supply to 501 The Cable No. from MK to CB Control Room in next sequential TB-3 For CB trip 502 order 5XX. Circuits. TB-3 For CB Alarms 503 TB-4 N/C Contacts of 504 CB TB-5 N/O Contact of 505 CB TB-8 & 9 N/C and N/O 601 The Cable No. from MK to Contacts of Line Control Room in next sequential Isolator. order 6XX. 602 TB-8 Electrical Interlocking Coil of Line Isolator. 603 TB-6 & 7 N/C and N/O Contacts of Bus Isolator-A 604 TB-8 Electrical Interlocking Coil of Bus Isolator-A TB-6 & 7 N/C and N/O 605 Contacts of Bus - 22 - TB-8 TB-8 & 9 TB-8 TB-10 TB-10 TB-10 TB-10 TB-10 1. 2. 3. i) ii) iii) iv) d) 1. 2. 3. 4. 5. 13.(B) 13.1 13.2 13.3 13.4 13.5 Isolator-B Electrical Interlocking Coil of Bus Isolator-B N/C and N/O Contacts of Earth Switch Electrical Interlocking Coil of Earth Switch KCVT Supply for Interlocking For AC Supply for T/F For T/F Trip Circuits For T/F Alarms For PT/CVT Circuits 606 301 302 303 701 The Cable No. from MK to Control Room in next sequential order 7XX. 702 703 Starting from 201 NOTE:Incase of Isolators / L&E Switch the cable numbering for AC & DC supply shall be in continuation to the numberings marked above. Each cable number is to be followed by respective bay number and same method of cable numbering is to be followed for 400kV, 220kV,132kV, 66kV and 33kV bays. Example:- In case of 132kV Bay with Bay No. B-10; cable numbering for AC supply to Circuit Breaker be done as2C X 4mm2 C.No.501B10 Where, 2C X 4mm2 is Size of Cable. 501 is cable number. B is Voltage level. 10 is bay number. Cable termination shall be done as described below. At MK, LHS of each TBs shall have respective equipment cable ferrule no. / MK TB No. and RHS shall have MK TB No./ C&R Panel cable ferrule no. At Each Equipment, LHS of TBs shall have MK TB No./Equipment ferrule no. At C&R Panel, LHS of TBs shall have respective MK TB No./ C&R panel ferrule no. In Wiring Diagram, single line Diagram shall have complete TB details of all equipment installed in a bay with cable core ferrule no. as per approved drawings has to be provided. Electrical Interlocking Scheme for Double Bus-Bar sub-stations The main requirement of Electrical Interlocking Scheme for grid sub-stations having Double BusBar sub-stations is as under:The Isolator shall not operate unless the circuit breaker is locked in open position. The earthing switch shall close only when the line Isolator is open and line is “OFF”. The line Isolator shall close only when the corresponding Circuit Breaker is open. The Bus Isolator of Bus Coupler Bay shall operate only when the Bus Coupler Circuit Breaker is open. When one Bus Isolator of any bay excepting the Bus Coupler is closed, the other shall close only when the Bus Coupler Circuit Breaker & its both the Isolators are closed. A typical Interlocking Scheme satisfying the above requirement is shown in figure – 1 enclosed. Further, Electrical Interlocking Scheme for Single Bus-Bar sub-stations be prepared in this pattern accordingly. These schemes shall be provided in respective wiring diagrams and interlinking be shown in MK. Note:CS/WD as per above shall be prepared by the bidder after award of contract and submitted in 5sets for consideration and approval to the purchaser. CABLE TAGS AND MARKERS Each cable and conduit run shall be tagged with numbers that appear in the cable and conduit schedule. The tag shall be of Aluminium with the number punched on it and securely attached to the cable conduit by not less than two turns of 20 SWG GI wire conforming to IS:280. Cable tags shall be of rectangular shape for power cables and circular shape for control cables. Location of cables laid directly underground shall be clearly indicated with cable marker made of galvanised iron plate. Location of underground cable joints shall be indicated with cable marker with an additional inscription “Cable Joints”. The marker shall project 150mm above ground and shall be spaced at an interval of 30 meters - 23 - 13.6 13.7 13.7.1 13.7.2 13.7.3 13.7.4 13.8 13.8.1 13.8.2 13.8.3 13.8.4 13.8.5 13.8.6 13.8.7 13.8.8 13.8.9 13.8.10 13.8.11 13.8.12 13.8.13 13.8.14 13.8.15 14. 14.1 14.2 14.3 15. 15.1 and at every change in direction. They shall be located on both sides of road and drain crossings. Cable tags shall be provided on all cables at each end (just before entering the equipment enclosure), on both sides of a wall or floor crossing, on each duct/conduit entry and at every twenty meters (20 m) in cable tray/trench runs. Cable tags shall be provided inside the switchgear, motor control centers, control and relay panels etc., wherever required for cable identification, where a number of cables enter together through a gland plate. CABLE SUPPORTS AND CABLE TRAY MOUNTING ARRANGEMENTS The contractor shall provide embedded steel insert on concrete floors/walls to secure supports for by welding to these inserts or available building steel structures, for the purpose of casting in the control room. The supports shall be fabricated from standard structural steel members. Insert plates will be provided at an interval of 750 mm wherever cables are to be supported without the use of cable trays, such as in trenches, while at all other places these will be an interval of 1000 mm (as per drg. attached). Painted lattice type steel trays (with width 300,450 & 600mm) of adequate size i.e. MS angle 50x50x6mm with 50x6mm MS Flat & MS angle 25x25x3mm with 25x25mm MS Flat each MS Flat at a distance of 300mm as per site requirement for laying control and power cables from panels (placed on top floor) to GIS & Transformers and for 11kV Outgoing cables & other cables identified as per site requirement. Further, it should be ensured that lattice type steel trays of size MS angle 25x25x3mm with 25x25mmMS Flat should not be used for power cables. CABLE TERMINATION AND CONNECTIONS The termination and connection of cables shall be done strictly in accordance with cable and termination kit manufacturer’s instructions, drawing and/or as directed by the HVPNL. The work shall include all clamping, fittings, fixing, plumbing, soldering, drilling, cutting, taping, heat shrinking, (where applicable), connecting to cable terminal, shorting and grounding as required to complete the job. Supply of all consumable material shall be included in the scope of the contractor. The equipment will be generally provided with un-drilled gland plates for cables/conduit entry. The contractor shall be responsible for drilling of gland plates painting and touching up. Holes shall not be made by gas cutting. Control cable cores entering control panels /switchgear /MCC / miscellaneous panels shall be neatly bunched, clamped and tied with nylon strap or PVC perforated strap to keep them in position. The contractor shall tag/ferrule control cable cores at all terminations, as instructed by the HVPNL. In panels where a large number of cables are to be terminated and cable identification may be difficult, each core ferrule may include the complete cable no. as well Spare cores shall be similarly tagged with cable numbers and coiled up. All cable entry points shall be sealed and made vermin and dust proof. Unused openings shall be effectively closed. Double compression type tinned/nickel plated brass cable glands shall be provided by the contractor for all power and control cables to provide dust and weather proof terminations. The cable glands shall be tested as per BS:6121. They shall comprise of heavy duty brass casting, machine finished and tinned to avoid corrosion and oxidation. Rubber components used in cable glands shall be neoprene and of tested quality. The cable glands shall be of approved make. The cable gland shall also be tested for dust proof and weather proof termination. The test procedure has to be discussed and agreed to between the HVPNL and cable glands manufacturer. If the cable and box or the terminal enclosure provided on the equipment is found unsuitable and requires modification, the same shall be carried out by the contractor, as directed by the HVPNL. Crimping tool shall be of approved design and make. Cable lugs shall be tinned copper solderless crimping type conforming to IS:8309 and 8394. The cable lugs shall be of approved make. Solderless crimping of terminals shall be done by using corrosion inhibitory compound. The cable lugs shall suit the type of terminals provided. DIRECTLY BURIED CABLES The contractor shall construct the cable trenches required for directly buried cables. The scope of work shall include excavation, preparation of sand bedding, soil cover, supply and installation of brick or concrete protective covers back filling and ramming supply and installation of route markers and joint markers. The Bidder shall ascertain soil conditions prevailing at site, before quoting the unit rates. The power and control cable between LT station, Control room, shall be laid in the buried cable trenches. Further, for lighting purposes also, buried cable trench can be used in the outdoor area. Cable route and joint markers and RCC warning covers shall be provided wherever required. The voltage grade of cables shall be engraved on the marker. INSTALLATION OF CABLES Cabling shall be on cable racks, in built-up trenches, vertical shafts, excavated trenches for direct - 24 - 15.2 15.3 15.4 15.5 15.6 15.7 15.8 15.9 15.10 15.11 15.12 15.13 15.14 15.15 15.16 15.17 15.18 15.19 15.20 burial, pulled through pipes, and conduits laid in concrete ducts, run bare and clamped on wall/ceiling/steel structures etc. as shown in the drawings in detailed engineering stage. Where specific cable layouts are not shown on drawings, contractor shall route these as directed by the HVPNL. The contractor shall fabricate and install mounting arrangements for the support and installation of all the cables on angles at 1000 mm spacing in the trenches, as shown in the drawing enclosed with Specification. These mounting structures/cable racks shall be fabricated from structural steel members (channels, angles and flats) of the required size. The fabrication, welding and erection of these structures shall conform to the relevant clauses of Section STR, in addition to the Specifications given herein. Cable racks and supports shall be painted after installation with two coats of metal primer (comprising of red oxide zinc chromate in a synthetic medium) followed by two finishing coats of Aluminium paint. The red oxide and zinc chromate shall conform to IS:2074. All welding works inclusive of the consumables required for Specifications given herein. All inter pole cables (power & control) for all equipment shall be laid in cable trenches/Gl conduit pipes of NB 50/100 mm diameter, class medium as per IS 4736 which shall be buried in the ground at a depth of 250 mm. The interpole cabling piping of Breakers shall be laid in cable trenches. The scope shall include all labour,material, equipment for transporting, laying, burying etc. including required bends and seals. Cable shall be generally located adjoining the electrical equipment through the pipe insert embedded in the floor. In the case of equipments located away from cable trench either pipe inserts shall be embedded in the floor connecting the cable trench and the equipment or in case the distance is small, notch/opening on the floor shall be provided. In all these cases necessary bending radius as recommended by the cable Contractor shall be maintained. Cabling in the control room shall be done on ladder type cable trays. Cables from the equipment to trench shall run in GI conduits. Necessary conduits of adequate sizes and length shall be supplied and installed by the contractor. Flexible conduit should be used between fixed conduit/cable trays (perforated type) and equipment terminal boxes, where vibration is anticipated. The flexible conduit shall be as per the relevant IS. Power and control cables shall be laid in separate tiers. The order of laying of various cables shall be as follows, for cables other than directly buried: Power Cable on top tiers. Control instrumentation and others service cables in bottom tiers. Single core cables in trefoil formation shall be laid with a distance of three times the diameter of cable between trefoil centerlines. All power cables shall be laid with a minimum center-to-center distance equal to twice the diameter of the cable. Trefoil clamps for single core cable shall be pressure die cast Aluminium (LM-6), Nylon or fibre glass and shall include necessary fixing GI nuts, bolts, washers etc. These are required at every 2 meter of cable runs. The cost of supply and erecting these clamps shall be made on the unit rate basis. Power and control cable shall be securely fixed to the trays/supports with self locking type nylon ties with deinterlocking facility at every 5 meter interval for horizontal run Vertical and inclined cable runs shall be secured with 25 mm wide and 2 mm thick Aluminium strip clamps at 2 m. Cables shall not be bent below the minimum permissible limit. The permissible limits are as follows: Table of cable and Minimum bending radius voltage grade Power cable 12 D. Control cable 10 D. D is overall diameter of cable. The cables are to be laid in single layers on racks and are to be routed through culvert whenever there is road crossing. In each cable run some extra length shall be kept at a suitable point to enable one (for LT cables)/two (for HT cables) straight through joints to be made in case the cable develop fault at later date. Selection of cable drums for each run shall be so planned as to avoid using straight through joints. Cable splices will not be permitted except where called for by the drawings, unavoidable or where permitted by the HVPNL. If straight through joints are unavoidable, the contractor shall use the straight through joints kit of reputed make. Control cable terminations inside equipment enclosures shall have sufficient lengths so that changing of termination blocks can be done without requiring any splicing. Metal screen and armour of the cable shall be bonded to the earthing system of the station, wherever required by the HVPNL. Rollers shall be used at intervals of about two meters while pulling cables. All due care shall be taken during unreeling, laying and termination of cable to avoid damage due to twist, kinks, sharp bends etc. Cable ends shall be kept sealed to prevent damage. Inspection on receipt, unloading and handling of cables shall generally be in accordance with - 25 - 15.21 15.22 15.23 15.24 15.25 15.26 15.26.a 15.26.b 15.26.c 15.26.d 15.27 e 15.27 15.27.1 15.27.2 15.28 15.28.1 15.28.2 15.28.3 15.28.4 15.28.5 15.28.6 15.28.7 15.28.8 15.28.9 15.28.10 15.28.11 IS:1255 and other Indian Standard Codes of practices. Wherever cable pass through wall openings or other partitions, wall sleeves with bushes having a smooth curved internal surface so as not to damage the cable, shall be supplied, installed and properly sealed by the contractor at no extra charges. Contractor shall remove the RCC/Steel trench covers taking up the work and shall replace all the trench covers after the erection-work in that particular area is completed or when further work is not likely to be taken up for sometime. Contractor shall furnish three of the report on work carried out in a particular week, indicating cable numbers, date on which laid, actual length and route, testing carried out, terminations carried out, along with the marked up copy of the cable schedule and interconnection drawing wherever any modifications are made. Contractor shall paint the tray identification number on each run of trays at an interval of 10 m. In case the outer sheath of a cable is damaged during handling/installation, the contractor shall repair it at his own cost to the satisfaction of the HVPNL. In case any other part of a cable is damaged, the same shall be replaced by a healthy cable at no extra cost to the HVPNL, i.e. the contractor shall be paid for installation and removal of the damaged cable. All cable terminations shall be appropriately tightened to ensure secure and reliable connections. The contractor shall cover the exposed part of all cable lugs whether supplied by him or not with insulating tape, sleeve or paint. Separate racks/trays will be utilised for different voltage levels from switchyard to control room. All the cable trenches will be constructed as per standard HVPNL design as far as electrical portion is concerned. The GI pipe duly lugged at both ends and by providing bends/elbows or trenches will be provided/constructed from equipment to trenches. Provision for accommodation of cables of future bays (All bays position marked on the drawing whether shown dotted or not to be included for future provision in main the trench size) are to be made in the main trenches. Power cables should be coated with fire retardant paint such that fire could be controlled automatically with low or no smoke propagation and no toxic gases should be released. The fire retardant coating should be such that it should not degrade the insulation properties of cable and should not degrade the current carrying capacity of cable. Further the fire retardant paint should confirms to relevant IS/IEC. TESTS ON CABLE TRAYS Test for galvanising (Acceptance test) to be done as per relevant standard. DEFLECTION TEST (TYPE TEST) A 2.5 meter straight section of all widths cable trays be simply supported at two ends a uniform distributed load of 76 kg meter shall be applied along the length of the tray. A maximum deflection at the mid span shall not exceed 7 mm. CONDUITS, PIPES AND DUCT INSTALLATION Contractor shall supply and install all rigid conduits, mild steel pipes, flexible conduits, hume pipes etc. including all necessary sundry materials such as tees, elbows, check nuts, bushing reducers, enlargers, coupling Cap, nipples, gland sealing fittings, pull boxes etc. as specified and to be shown in detailed engineering drawing. The size of the conduit/pipe shall be selected on the basis of 40% fill criterion. Contractor shall have his own facility for bending, cutting and threading the conduits at site. Cold bending should be used. All cuts & threaded ends shall be made smooth without leaving any edges. Anticorrosive paint shall be applied at all field threaded portions. All conduit/pipes shall be extended on both sides of wall/floor openings. The fabrication and installation of supports and the clamping shall be included in the scope of work by Contractor. When two lengths of conduits are joined together through a coupling, running threads equal to twice the length of coupling shall be provided on each conduit to facilitate easy dismantling of two conduits. Conduit installation shall be permanently connected to earth by means of a special approved type of earthing clamps. GI pull of adequate size shall be laid in all conduits before installation. Each conduit run shall be painted with its designation as indicated on the drawing such that it can be identified at each end. Embedded conduits shall have a minimum concrete cover of 50 mm. Conduit run sleeves shall be provided with the bushings at each end. Metallic conduit runs at termination shall have two locknuts and a bushing for connection. Flexible conduits shall also be suitably clamped at each end with the help of bushings. Bushings shall have rounded edges so as not to damage the cables. When embedded conduits turn upwards from a slab or fill, the termination dimensions shown on the drawings, if any, shall be taken to represent the position of the straight extension of the conduit external to and immediately following the bend. At least one half of the arc length of the bend shall be embedded. All conduits/pipes shall have their ends closed by caps until cable are pulled. After cables are pulled, the ends of conduits/pipes shall be sealed in an approved manner to prevent damage to - 26 - threaded portions and entrance of moisture and foreign material. 15.28.12 For underground runs, contractor shall excavate and back fill as necessary. 15.28.13 Contractor shall supply, unload, store and install conduits required for the lighting installation as specified. All accessories/fittings required for making the installation complete, including but not limited to pull out boxes ordinary and inspection tees and elbow, check nuts, male and female bushings (brass or galvanised steel), caps, square headed male plugs, nipples, gland sealing fittings, pull boxes, conduit terminal boxes, gaskets and box covers, saddle terminal boxes, and all steel supporting work shall be supplied by the contractor. 15.28.14 All unarmoured cable shall run within the conduits from lighting panels to lighting fixtures, receptacles etc. 15.28.15 Size of conduit for lighting shall be selected as per the table given in the attached drawings. 15.28.16 Exposed conduits shall be run in straight lines parallel to building columns, beams and walls. Unnecessary bends and crossings shall be avoided to present a neat appearance. 15.28.17 Conduit supports shall be provided at an interval of 750mm for horizontal runs and 100 mm for vertical runs. 15.28.18 Conduit supports shall be clamped on the approved type spacer plates or brackets by saddles or U-bolts. The spacer plates or brackets in turn, shall be securely fixed to the building steel by welding and to concrete or brickwork by grouting or by nylon rawl plugs. Wooden plug inserted in the masonry or concrete for conduit support is not acceptable. 15.28.19 Embedded conduits shall be securely fixed in position to preclude any movement. In fixing embedded conduit, if welding or brazing is used, extreme care should be taken to avoid any injury to the inner surface of the conduit. 15.28.20 Spacing of embedded conduits shall be such as to permit flow of concrete between them and in no case shall be less than 38 mm. 15.28.21 Where conduits are along with cable trays, they shall be clamped to supporting steel at an interval of 600 mm. 15.28.22 For directly embedding in soil, the conduits shall be coated with an asphalt-base compound. Concrete pier or anchor shall be provided wherever necessary to support the conduit rigidly and to hold it in place. 15.28.23 Conduit shall be installed in such a way as to ensure against trouble from trapped condensation. 15.28.24 Conduit shall be kept, wherever possible, at least 300 mm away from hot pipes, heating devices etc. when it is evident that such proximity may reduce the service life if cables. 15.28.25 Slip joints shall be provided when conduits cross structural expansion joints or where long run of exposed conduits are installed, so that temperature change will cause no distortion due to expansion or contraction of conduit run. 15.28.26 For long conduit run, pull boxes shall be provided at suitable intervals to facilitate wiring. 15.28.27 Conduit shall be securely fastened to junction boxes or cabinets, each with a lock nut inside and outside the box. 15.28.28 Conduits joints and connections shall be made thoroughly water-tight and rust proof by application of a thread compound which insulates the joints. White lead is suitable for application on embedded conduit and lead for exposed conduit. 15.28.29 Field bends shall have a minimum radius of four (4) times the conduit diameter. All bends shall be free of kinds, indentations of flattened surfaces. Heat shall not be applied in making any conduit bend. Separate bends may be used for this purpose. 15.28.30 The entire metallic conduit system, whether embedded or exposed, shall be electrically continuous and thoroughly grounded. Where slip joints are used, suitable bounding shall be provided around the joint to ensure a continuous ground circuit. 15.28.31 After installation, the conduits shall be thoroughly cleaned by compressed air before pulling in the wire. 15.28.32 Lighting fixtures shall not be suspended directly from the junction box in the main conduit run. 16. ILLUMINATION SYSTEM 16.1.1 The scope of work comprises of design, engineering, testing, supply, installation, testing and commissioning of various lighting fixtures complete with lamps, supports and accessories, lighting panels, lighting complete with distribution boxes, galvanised rigid steel conduits, lighting wires, G.I. Earthwire receptacles, switchboards, switches, junction boxes, pull out boxes complete with accessories, lighting transformer & Street steel light poles as per IS: 2713-1980 (Part-II). The details of area to be illuminated are given below: Control Room Building. Switch Yard area. Roads and streets. 16.1.2 The minimum lux levels to be maintained in the different areas shall be as per following: Sr. No. Area Lux. Level i) Switchyard 50 lux on power transformer and 20 lux on other equipment. ii) Street/Road 20 lux. Bidder shall submit detailed for reaching the above LUX levels. 16.1.3 Any material, wire, conduits, accessories etc. not specifically mentioned or specified but required for installation of lighting fixtures are included in the scope of contractor. - 27 - All lighting fixtures & accessories shall be designed for continuous operation under atmospheric conditions existing at site, without reduction in the life or without any deterioration. The lighting fixtures shall be of Philips or Bajaj or Crompton Greaves of make only. 16.2 TEMPERATURE RISE All lighting fixtures and accessories shall be designed to have a low temperature rise according to the relevant Indian Standards, the design average ambient temperature shall be taken as 500C. 16.3 LIGHTING FIXTURES 16.3.1 All fixtures shall be designed for minimum glare. 16.3.2 All lighting fixtures shall be complete with lamps a specified and shall be suitably wired up. 16.3.3 All lighting fixtures shall be complete with accessories. Outdoor type fixtures shall be provided with outdoor type weather proof box. 16.3.4 Each lighting fixtures shall be provided with an earthing terminal and all metal parts of the housing shall be constructed so as to ensure earthing continuity throughout the fixture up to the earthing terminal. 16.3.5 The mounting facility and conduit knock-outs for the fixtures shall be suitable for 20 mm conduit entry. 16.3.6 The wire shall be of 1100 V grade and PVC insulated with multi stranded copper conductor. 16.4 TESTS Manufacture’s type and routine test certificates shall be submitted for the fixtures and accessories. 16.5 SYSTEM DESCRIPTION The lighting system shall comprise of the following: 16.5.1 AC NORMAL LIGHTING All the lights connected to the AC lighting system in different area will be connected to the AC distribution boards to be supplied. 16.5.2 DC EMERGENCY LIGHTING DC emergency in Control room, relay and protection room, office, LT switchgear room, D.C.D.B. room shall be provided to avoid complete darkness in case of complete AC failure. The number of DC emergency lights to be provided shall be calculated on the basis that at least illumination level of at least 30 LUX is achieved when DC emergency lights get switched ON. 16.5.3 RECEPTACLES Adequate number of 5A, 15 A, (single phase) and 32 A (3phase) receptacles shall be provided at suitable locations to be mutually during the detailed engineering. 16.6 ERECTION, TESTING AND COMMISSIONING OF LT PANELS & BATTERY CHARGER 16.6.1 The Contractor shall unload, erect, install, test and put into commercial use all electrical equipment included in this Specification. 16.6.2 Equipment shall be installed in a neat, workman so that it is level plumb, square and properly aligned and oriented. Tolerance shall be as established in Contractor’s drawings or as stipulated by HVPNL. No equipment shall be permanently bolted down to foundations until the alignment has been checked and found acceptable by the HVPNL. 16.6.3 Contractor shall furnish all supervision, labour tools equipment rigging materials, bolts, wedges, anchors, concrete insert etc. in proper time required to completely install, test and commission the equipment. 16.6.4 Manufacture’s and HVPNL’s instructions and recommendations of all equipment. 16.6.5 Contractor shall move all equipment into the respective room through the regular door or openings specifically provided for this purpose. No part of the structure shall be utilised to lift or erect any equipment without prior permission of HVPNL. 16.6.6 All switchboards shall be installed in accordance with Indian standards IS:3072 and at HVPNL’s instructions. Switchboard panels shall be installed on finished surfaces, concrete or steel stills. Contractor shall be required to install and align any channel sills which from part of foundations. In joining shipping sections of switchboards together adjacent housing of panel section or flanged throat sections shall be bolted together after alignment has been completed. Power bus, enclosures ground and control splices of conventional nature shall be cleaned and bolted together being drawn up with torque spanner of proper size or by other approved means. 16.6.7 All switchboards shall be made completely vermin proof. 16.6.8 Contractor shall take utmost care in holding instruments, relaying and other delicate mechanism wherever the instruments and relays are supplied separately they shall be mentioned only after the associated panels have been erected and aligned. The blocking materials HVPNL for safe transit of instrument and relays shall be removed after ensuring that panel been completely installed and to further movement of the same should be necessary. Any damage shall be immediately reported to HVPNL. 16.6.9 Equipment furnished with finished coats of paint shall be touched by up Contractor if their surface is specified or marred while handling. 16.6.10 Foundation work for all switchboard panels will be carried out by Civil Contractor. However, minor modifications shall be carried out by the Contractor at no extra cost. 16.6.11 After installation of panels, power and control wiring and connections, Contractor shall perform operational tests on all switchboards, to verify proper operation of switchboards/panels and - 28 - 16.6.12 16.6.12.1 i. ii, iii. iv. v. vi. 16.6.12.2 i. ii. iii. iv. v. vi. vii. viii. ix. x. xi. xii. xiii. 16.2.12.3 i. ii, iii. iv. 16.2.12.4 i. ii, iii. iv. 16.2.12.5 i. ii, iii. iv. 16.2.12.6 i. ii. a) b) iii. iv. v. vi. vii. 16.2.12.6 i. ii, iii. 16.7 16.7.1 16.7.2 correctness of all equipment in each and every respect. COMMISSIONING CHECK TESTS The Contractor shall carry out the following commissioning check wherever applicable in addition to the other checks and tests recommended by the manufacturers: GENERAL Check nameplate details according to the Specification. Check for physical damage. Check tightness of all bolts, clamps, joints connecting terminals. Check earth connection, Check cleanliness of insulators and bushings. Check all moving parts for proper lubrication. CIRCUIT BREAKERS Check alignment of Breaker truck for free movement. Check correct operation of shutters. Check control wiring for correctness of connections, continuity and IR values. Manual operation of Breaker completely assembled. Power closing/opening operation, manually and electrically. Breaker closing and tripping time. Trip free and anti-pumping operation. IR values, minimum pick up voltage and resistance of coils. Contact resistance. Simultaneous closing of all the three phases. Check electrical and mechanical interlocks provided. Check on spring charging motor, correct operation of limit switches, and timeof charging. All functional checks. CURRENT TRANSFORMERS Megger between winding and winding terminals top body. Polarity test. Ratio identification checking of all ratios on all by primary injection of current. Spare CT cores, if any, to be shorted and earthed. VOLTAGE TRANSFORMER Insulation resistance test. Ratio test on all cores. Polarity test. Line connections as per connection diagram. CUBICLE WIRING Check all switch development. Each wire shall be traced by continuity tests and it should be made sure that the wiring is as per relevant drawing. All interconnection between panels/equipment shall similarly checked. All the wire shall be meggered to earth. Functional check of all control circuit e.g. closing, tripping control, interlock, supervision and alarm circuit. RELAYS Check connections and wiring. Megger all terminal to body. Megger AC to DC terminals. Check operations characteristics by secondary injection. Check minimum pick up voltage of DC coils. Check operation of electrical/mechanical targets. Relays settings. Check CT and VT connections with particular reference to their polarities for directional relays, wherever required. METERS Check calibration by comparing it with a sub-standard. Megger all insulated portions Check CT and VT connections with a particular reference to their polarities for power type meters. ERECTION, TESTING AND COMMISSIONING OF BATTERY BANK The control shall unload, erect, install, test and put into commercial use already electrical equipment included in this Specification. Equipment shall be installed in a neat, workman like manner so that it is level, plumb, square and properly aligned and oriented tolerance shall be established in Contractor’s drawings or as stipulated by HVPNL. No equipment shall be permanently bolted down to foundations until the alignment has been checked and found acceptable by the HVPNL. 16.7.3 Contractor shall furnish all labour tools equipment rigging materials, bolts, wedges, anchors, concrete inserts etc. in proper time required to completely install, test and commission the equipment. 16.7.4 Manufacturer’s and HVPNL’s instructions and recommendations shall be correctly followed in handling, testing and commissioning of Battery Bank. - 29 - - 30 - SECTION – 8 STRUCTURES 1.0 GENERAL 1.1 The scope of specification covers fabrication, proto-assembly supply and erection of galvanised steel structure for towers, latticed griders and equipment support structure. Towers, girder & equipment support structures shall be as per HVPN drawing conforming to IS 2062 (latest). The scope shall include all types of bolts, nuts, step bolts, inserts in concrete, gusset plates, equipment mounting bolts, structure Earthing bolts, foundation bolts, spring washers, fixing plates, angles and bolts for structure mounted or ground mounted marshalling boxes (AC/ DC Marshalling box & equipment control cabinet) and any other items as required to complete the job. The connection of all structures to their foundations shall be by base plates and embedded anchor/ foundation bolts. All steel structures and anchor/ foundation bolts shall be fully galvanized. The weight of the zinc coating shall be at least 0.610 kg/m2. One additional nut shall be provided below the base plate which may be used for the purpose of leveling. 2.0 DESIGN REQUIREMENTS 2.1 Minimum distance from the hole centre to edge shall be 1.5x bolt diameter. Minimum distance between center to center of holes shall be 2.5x bolt diameter. 2.2 The minimum bolt diameter shall be 16 mm. 2.3 In order to facilitate inspection and maintenance, the structures shall be provided with climbing devices. Each tower shall be provided with step bolts not less than 16 mm diameter & 175 mm long spaced not more than 450 mm apart, staggered on faces on one leg extending from about 0.5 meters above ground level to the top of the tower. The step bolt shall conform to IS:10238. Ladders on towers with lighting appliances shall be provided with safety guards. 2.4 If luminaries are proposed to be fixed on gantries/ towers, then the proper loading for the same shall be considered while designing. Also holes for fixing the brackets for luminaries should be provided wherever required. 2.5 Foundation bolts/ studs shall be designed for the loads for which the structures are designed. 3.0 FABRICATION OF STEEL 3.1 The supplier shall bear all the expenditure at all stages on account of loading/ unloading, transportation and other miscellaneous expenses and losses and damages for all materials upto the fabrication yard/ shop and there after to the erection site including all other expenses till the erection of work has been completed and accepted. The unit rates shall be deemed to be inclusive of all such incidental expenses and nothing extra shall be payable on any account in this regard. 3.2 The fabrication and erection works shall be carried out generally in accordance with IS:802. A reference however may be made to IS:800 in case of nonstipulation of some particular provision in IS:802. All materials shall be completely shop fabricated with proper connection material and erection marks for ready assembly in field. 4.0 ASSEMBLY 5.0 i) The component parts shall be assembled in such a manner that they are neither twisted nor otherwise damaged and shall be so prepared that the specified camber, if any, is provided. In order to minimise distortion in member the component parts shall be positioned by using the clamps, clips, dogs, jigs and other suitable means and fasteners (bolts and welds) shall be placed in a balanced patten. If the individual components are to be bolted, paralled and tapered drifts shall bed used to align the part so that the bolts can be accurately positioned. ii) Sample towers, beams and equipment support structure shall be trial assembled keeping in view the actual site conditions, before erection in the fabrication shop and shall be inspected and approved by Purchaser before mass fabrication. Necessary match marks shall be made on these components in the shop before disassembly and despatching. BOLTING i) Every bolt shall be provided with a spring washer under the nut so that no part of the threaded portion of the bolt is within the thickness of the parts bolted together. ii) All steel items, bolts, nuts and washers shall be galvanised. iii) 2.0% extra nuts and bolts shall be supplied for erection. 6.0 WELDING The work shall be done as per approved fabrication drawing which clearly indicate various details of joints to be welded, type of weld, length and size of weld, whether shop or site weld. Symbols for welding on erection and shop drawings shall be according to IS:813. Efforts shall be made to reduce site welding so as to avoid improper welding due to constructional difficulties. 7.0 FOUNDATION BOLTS 7.1 Foundation bolts for the towers and equipment supporting structures and elsewhere shall be embedded in first stage concrete while the foundation is cast. The Supplier shall ensure the proper alignment of these bolts to match the holes in the base plate. 7.2 The Supplier shall be responsible for the correct alignment and leveling of all steel work on site to ensure that the towers/ structures are plumb. 7.3 All foundation bolts for lattice structures are to be supplied by the supplier. 7.4 All foundation bolts shall be fully galvanised so as to achieve 0.61 kg per Sq.m of Zinc Coating as per specification. 8.0 STABILITY OF STRUCTURE The Supplier shall be responsible for the stability of the structure art all stages of its erection at site and shall take all necessary measures by the additions of temporary bracing and guying to ensure adequate resistance to wind and also to loads due to erection equipment and their operations. 9.0 GROUTING The method of grouting the column bases shall be subject to approval of Purchaser and shall be such as to ensure a complete uniformity of contact over the whole area of the steel base. The Supplier will be fully responsible for the grouting operations. 10.0 GALVANISING 10.1 All structure steel works and single pipe supports shall be galvanised after gabrication. 10.2 Zinc required for galvanising shall have to be arranged by the manufacturer. Purity of zinc to be used shall be 99.5% as per IS:209 (latest). 10.3 The Supplier shall be required to make arangement for frequent inspection by the Purchaser as well as continuous inspection by a resident representative of the Purchaser, if so desired for fabrication work. 11.0 INSPECTION BEFORE DISPATCH Each part of the fabricated steel work shall be inspected and certified by the Purchaser of his authorised representative as staisfactory before it is despatched to the erection site. Such certificate shall not relieve the Supplier of his responsibility regarding adeqaucy and completeness of fabrication. 12.0 TEST CERTIFICATE Copies of all test certificate relating to material procured by the Supplier works shall be forwarded to the Purchaser. 13.0 ERECTION The Supplier should arrange his own erection plant and equipment, welding set, tools and tackles, scaffoliding, trestles equipment etc. and any other accessories and ancillaries required for the work. 14.0 SAFETY PRECAUTIONS The Supplier shall strictly follow at all stages of fabrication, transportation and erection of steel structures, raw materials and other tools and tackles, the stipulations contained in Indian Standard Code for erection for structural steel work – IS:7205. SECTION-10 CHAPTER-1 TECHNICAL SPECIFICATIONS FOR PLCC EQUIPMENTS & PROTECTION COUPLER 1. 2. 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 2.10 3. 3.1 4. 4.1 4.2 4.3 GENERAL: The manufacturer whose PLCC panels are offered should have designed, manufactured, tested, supplied and commissioned PLCC panels for the specified voltage and fault level. STANDARD: All the PLCC equipment covered under the package shall conform to the requirements of the latest addition of the relevant IEC/IS Specification or equivalent National Standards, except to the extent mentioned by this specification. The works covered by the specification shall be designed, engineered, manufactured, built tested and commissioned in accordance with the Acts, Rules, Laws and Regulations of India. The equipment to be furnished under this specification shall conform to latest issue with all amendments of standard specified above. In addition to meeting this specific requirement called for in the Technical Specification, the equipment shall also conform to the general requirement of the relevant standards and shall form an integral part of specification. The Bidder shall nor that standards mentioned in the specification are not mutually exclusive or complete in themselves but intended to compliment each other. The contractor shall note that list of standards presented in this specification is not complete. Whenever necessary the list of standards shall be considered in conjunction with specific IS/IEC. When the specific requirements stipulated in the specification exceed or differ than required by applicable standards, the stipulation of the specification shall take precedence. Other internationally accepted standards which ensure equivalent or better performance than that specified in the standard referred shall also be accepted. In case governing standards for the equipment is different from IS or IEC, the salient points of difference shall be clearly brought out alongwith English language version of standard or relevant extract of the same. The equipment conforming to standards other than IS/IEC shall be subject to HVPNL’s approval. The bidder shall clearly indicates in his bid the specific standards in accordance with which the works will be conformed. TRAINING: As per clause 12 of section I General. LOCATION OF EQUIPMENT: The PLCC equipments as specified shall be installed at the respective ends of the transmission lines. FREQUENCY PLANNING: For planning frequency and output power of carrier terminals, bidders may plan for a minimum receive signal to noise ratio of 25dB for the speech channels without compander and 15dB for protection signalling & 29dB for data transmission. The details of line, tower, conductor shall be furnished to the Contractor to carry out the assessment of signal attenuation. IEC/CIGRE specifications/guidelines shall be adhered to. Frequency and output power of PLC terminals for protection shall be planned such that the protection signal is received with full reliability even when one of the phase is earthed or is on open circuit on the line side causing an additional minimum loss of 6dB. Successful Bidder shall be fully responsible for the co-ordination required with concerned State Electricity Board for finalising the frequency plan. -1- 4.4 5. 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 5.10 6. 6.1 The frequency plan will be referred to wireless Advisor/DOT Department for clearance and in case any change in the contractor’s recommended carrier frequency and power output is proposed by these authorities, the contractor shall have to modify his proposal accordingly. Change of power output shall however not involve repeater station. PROPOSED ARRANGEMENT: The power line carrier communication equipment required by the HVPNL is to provide primarily efficient, secure and reliable information link for carrier aided distance protection and direct tripping of remote and breaker and also for speech communication between sub-station. It shall include separate carrier terminals of multipurpose type for speech and protection purposes. Provision for super-imposing telex and data signals shall be made on speech terminals. All carrier terminals including those for protection shall be suitable for point to point speech communication also. Carrier aided protection is not being provided on 132kV and below transmission lines in HVPNL. For security reasons each transmission line shall be protected by Main-I and Main-ii protections or Main & Backup protections. The features of Direct Trip Send and Direct Trip Receive shall also be provided in the protection coupler. The requirement of carrier information on each link covered under this specification is for speech communication and protection signaling. The equipment for protection signals shall have high degree of reliability and speed. It shall be guaranteed to function reliably in the presence of noise impulse caused by isolator or breaker operation. It shall also be possible to effect direct tripping of breaker at one end when the other end breaker opens out either manually or by relays such as Bus fault relay etc. The time intervals between receipt of a trip command on the transmit side, its transmission over the carrier link, reception at the far end and giving command to the trip relays at the distant end shall not exceed 20 m.sec. for permissive inter-tripping and 30m.sec. for direct inter-tripping even for the longest line section. The above timings are Inclusive of operating time for auxiliary relays and interposing relays, if any, included in the PLCC equipment. The requirement of protection signaling channel is such that security against incorrect signals being received shall be atleast two to three orders higher than reliability against a signal not being received. The planning of frequencies for the PLCC terminals shall be done confederating the existing PLCC network as well as full communication channel requirement detailed above so that there is no problem of frequency allocation at a later date when the subsequent section communication requirements come up. For reasons of security and reliability, phase to phase coupling for S/C lines and intercircuit coupling for D/Clines shall be employed. The parameters of the equipment quoted shall be such that the mode of wave propagation on transmission line shall not impose any limitation on the efficient and reliable performance of information link from protection or communication point of view. The Bidder shall submit curves illustrating ‘incorrect tripping’ and ‘Failure to trip’ probability plotted against corona noise level in the presence of impulse noise due to switching of isolator and circuit breaker etc. Detail of Field tests and laboratory tests for successful operation of his equipment, under such adverse conditions shall be furnished by the bidder. These are to be related to end-to-end signaling and shall take into account the type of communication link. POWER LINE CARRIER TERMINAL: The offered PLCC equipment should be suitable for carrier transmission in high frequency of Speech, Facsimile, Telegraphy, RTU data, Teleprotection signals in frequency range of 40KHz to 500KHz over high voltage overhead power transmission lines. The system should have one/two speech channels each of which can be set for full bandwidth speech cum fax conversations or shared speech cum superimposed date channels or suitable for high sped 4 wire RTU data channel of 1200/2400 bits per second. The superimposed data channel can support upto 600 baud (2760-3720 Hz, -2- 6.2 6.3 a) b) c) d) e) f) g) h) i) j) 960 Hz BW or 2280-3360 Hz, 1080 Hz BW) channel as a backup for RTU/SCADA.The system should be fully field programmable and flexible easy to use and compact leading to simplified network design, installation and maintenance work. The system can provide up to 12/6Nos. of 50 baud, 8/4 Nos. of 100 baud or 1 Nos. of 600 baud voice band data for superimposed channels and speech up to 2 KHz/2.4KHz in VF circuits simply by changing plugin filters provided in channels modem. Optionally system can be provided to give speech and data only channels (upto 28/13/9 Nos. of 50/100/200 baud or 1 Nos. of 1200/2400 bps ) or Interface for protection coupler signal. As already indicated the information link shall be provided for speech, protection, telex and data services. PLC terminals shall be fully co-ordinated to match with the specific requirements. Because of strict requirement of high speed of operation, security, reliability and efficient operation of protection channel along with the carrier terminals, Bidder shall ensure the complete and fool-proof co-ordination of the PLC and protection equipments. It shall therefore be necessity to have these combinations as one unit without any mismatch or necessary of any intermediate co-ordination unit. PLC terminal shall use Amplitude Modulation and shall have single side band transmission mode. These shall be equipped for fixed frequency duplex working and shall be fully transistorised, however, this fixed frequency shall be programmable at site. Characteristic input and output parameters of the SSB PLC terminals shall be as per IEC-495, unless otherwise specified. The features of carrier terminal are detailed out below: Mode of transmission single side band with Amplitude Modulation suppressed carrier or reduced carrier. Carrier frequency range 40 to 500KHz Nominal carrier frequency band in either direction of 4.0KHz transmission Power output (PEP) of HF terminals 20 watt Frequency difference between a pair of PLC Frequency difference between terminals VF signal at the transmitting and receiving ends will not exceed 2 Hz with suppressed carrier. With reduced carrier frequency difference shall be zero. This shall include permissible ambient temperature variation and supply frequency and voltage variation of (+) 15 % and (-)10% Automatic gain control For 40dB change in carrier frequency signal level within the regulation range, change in VF receive levels of both speech and other signals shall be less than 1dB. Supply voltage 48V DC+15%-10% (Positive pole earthed). Nominal impedance -Carrier freq. Sides 150ohm balanced -VF sides 600ohm Return loss within nominal freq. Band: -Not less than 10dB on Carrier freq. Transmit side. -Not less than 14dB on VF side. Spurious emission at edge of nominal carrier freq. -10dBm(Max) Band. -3- k) Speech level across 600ohms. -Four wire transmit -Four wire receive -2 wire transmit -2 wire receive 0dBr to –17dBr 8 dBr to -3.5 dBr 0dBr -7dBr l) Permissible limits for variation of overall loss As per IEC 495/IS 9482 (attenuation) of the speech channel in relation to 800Hz for back to back operation of a pair of terminals without compander. m) Voltage withstand requirement D/C Power terminal. Capable of with standing 500V When isolated from earth DC for 1 minute between both terminals connected together and earth. When not isolated form earth. An impulse voltage of 1000v 1.2/50 applied between. VF signaling and alarm circuit when free from earth. 500V DC applied for 1 minute between both terminals of circuit connected together and earth. 6.4 Following facilities to be provided in the PLC terminals: 1) Loop test facility for local transmitted and receiver. 2) Changeover provision of termination of PLC terminals on dummy load. 3) Position of each module may be marked at the back side of chassis also. 4) Terminal blocks for power supply, telephone cable and two HF cable sockets. 5) Channel testing from terminal to terminal. 6.5 All the PLC terminals shall be of multipurpose type. The bidder shall confirm that the total transmission time for tele protection shall not exceed 20ms for permissive and 30ms for direct tripping signals. 6.6 In the input circuit of PLC terminal protective devices shall be provided in the form of zener diodes or surge suppressors in order to eliminate an surge transfer through the coupling device or the surge induced in the connecting path of HF cable. 6.7 To improve voice transmission characteristics for the system, companders and expanders shall be provided. The companders shall have atleast 2:1 compression ratio with a corresponding expansion ratio of 1:2. The operating range of compander shall be compel with the audio power levels specified for 4 wire operation. The improvement gained by companders shall however, not be taken into account for power allocation and shall be in-hand reserve. 6.8 Sudden changes in input level to the receiver shall not cause false tripping. The bidder shall clearly indication in his offer the methods adopted to ensure above phenomenon. The receiver design shall also provide protection against false tripping from random noise. 6.9 Fail-safe devices shall be provided, so that a malfunction in one unit or sub-assembly cannot cause damage elsewhere in the system. All plug-in equipment shall be fitted with features to prevent improper insertion. The electrical cables shall not be routed across sharp edges or near sources of high temperature. The adjustments, which are susceptible to misadjustment for accidental contact/vibration, shall be equipped with suitable locking devices. 6.10 The PLC set shall be designed to give guaranteed performance from 0 deg. C to 50deg. C ambient temperature. The thermal capability of the equipment shall be so designed that the equipment remains operational successful upto 60deg. C ambient temperature. Any ventilation fans provided for circulation of air inside the cabinets shall conform to relevant Indian Standards. 6.11 The terminals shall be provided with built-in indicating Instrument to facilitate checking of important voltages and current values and signal levels in different parts of the PLC terminals. Protection fuses shall be provided in all important circuits and fuses shall be so mounted as allow their easy inspection and replacement. All test points shall be easily accessible. -4- The carrier set shall be provided with suitable supervision and alarm facilities Individual parts of the carrier set should be accessible from front, making it possible to place the carrier cabinets side-by-side. All components and parts of the carrier sets shall be suitably tropicalised. 6.12 PLC terminals shall be housed in floor mounting sheet metal cabinets, suitable for mounting on concrete plinth as well as channel frame by means of nuts and bolts or welding. The cabinets shall be properly cleaned and spray painted with two coats or synthetic enamel paint. Exterior of the cabinets shall be painted with smoke-glossy finish. Interior of the cabinets shall be painted with white enamel paint with glossy finish. All the panels shall be provided with suitable point for earthling with the earth of the Grid/S/Stn.. Detailed drawings for earthing connections shall be submitted. 6.13 All cabinets having PLC terminals shall be provided with lamps of sufficient wattage for interior illumination with switch. 6.14 A name plate shall be provided on the front door of each cabinet indicating channel function, transmitter frequency and direction etc. 6.15 Bidder shall submit type test & routine test certificate from internationally reputed test authorities for the quoted PLC terminals in respect of characteristic input and output parameters of the PLC terminals in accordance with IEC-495 alongwith the Bid. 6.15.1 TYPE TESTS: The equipment should be offered type test. Test reports should not more then seven years old reckoned from date of bid opening in respect of all the tests carried out in accredited laboratories (based on ISO/IEC) by a reputed accreditatic body or witnessed by HVPN or another electric power utility and be submitted by the successful bidder to HVPNL for approval as schedule given in Bar Chart. I Carrier frequency side Nominal impedance, return loss and tapping loss Balance of ground Spurious omissions carrier frequency levels frequency accuracy Voice Frequency Side Automatic gain control Transmit/receive frequency difference Noise generated, within the termianls Harmonic distortion Selectivity Nominal impedance and return loss Balance of ground Telephone signalling channel Voltage withstand requirements Electromagnetic compatibility II Standard Equipment Attenuation distortion Group delay distortion Signals above 3400 Hz III Speech Plus Equipment Attenuation distortion Group delay distortion -5- IV V VI 7. (a) (b) (c) (d) (e) (f) (g) Multichannel Terminals Carrier frequency output power Nominal impedance, return loss Spurious omissions Inter channel cross talk attenuation Common Requirements AC Power Supply DC Power Supply Temperature and humidity Storage Conditions Subject to agreement between the manufacturer and the user Routine Test: As per quality assurance program (QAP). ACCEPTANCE TESTS: The following acceptance tests shall be carried out by the Supplier in presence of HVPNL representative, unless dispensed with in writing by the HVPNL. i) Carrier frequency levels ii) Frequency accuracy ii) Automatic gain control iv) Transmit/receive frequency difference v) Voltage withstand requirements vi) Attenuation distortion vii) Attenuation distortion viii) Carrier frequency output power SPEECH COMMUNICATION: PLC equipments offered shall provide telephone communication between the stations where the transmission line equipment shall be suitable for providing the following: It shall be possible for subscriber at any of the stations to contact the subscriber at all other stations connected in the system by dialing his call number. To achieve this a 24 lines EPAX with 4 wire interface & remote subscriber units shall be provide/available at different stations. The equipment shall contain all normal facilities like ring back tone, dial tone, engage tone & priority tone and suitable pluses to established and disconnect communication between subscribers. The equipment shall be provided with necessary alarm circuits and fuses etc. The equipment shall be of 4 kHz bandwidth on either direction for providing super imposed data and be suitable for teleprinter facilities at a later date without major modifications and high cost. The Bidder shall clearly indicate in his bid the provision made in his proposal for future development and the extent to which such additional facilities can be asked at a later date. Arrangement for over-riding facilities shall be provided by means of priority keys wherever specified. The over-riding facility shall enable cutting in ongoing calls with the priority key and ask the concerned parties to finish their conversation. The wanted number should then get automatically connected without having to redial the number. All the carrier telephone conversations shall be secret and it should not be possible for anybody to over hear the conversation going on between any two parties except those provided with over-riding facilities. All the relays etc, used in the equipment shall be of roubust design to cope with the duty imposed on them. Electronic components used in the equipment shall be of long life type and as far as possible a few types only shall be used. -6- (h) (i) (j) (k) (l) 8. 8.1 8.2 8.3 8.4 (i) (ii) (iii) 8.5 The cabinets housing the equipment for EPAX, four wire E/M interface & remote subscriber units (four wire) shall have mounting arrangement similar to that for PLC terminals and these cabinets shall also be painted with the same paint similar to that of PLC terminals. All the terminals for speech shall be supplied fully wired for addition of VFTs in future. However, the terminal supplied shall be equipped with programmable transit band pass filters. Equipment for speech communication must be fully compatible with HVPNL’s existing equipment. Any Interfaces required for proper matching and connection with the HVPNL’s existing equipment shall be provided by the Contractor. Terminals for protection shall be suitable between two ends of each transmission line or on tandem operation basis with back to back connection at the intermediates stations. Each PLC terminal for speech as well as protection purposes shall be provided with a plug-in type service telephone and buzzer. Further, 4 wire remote telephone instruments (parallel to service telephone) shall also be provided on one PLC terminals for protection for each link. These instruments shall be located in respective switchyard control room to enable the operator to make emergency calls on point-to-point basis. Each such instrument shall be equipped, with a buzzer and ‘press-to-call’ key and shall not require any additional power supply units. NETWORK PROTECTION EQUIPMENT (PROTECTION COUPLER) : The bidder shall offer voice frequency transmission equipment which shall work on frequency shift or coded signal principle for transmission/reception of protection signals as single purpose channel. The equipment shall be suitable for connection to the power line carrier terminal mentioned above. The voice frequency transmission equipment shall not only be insensitive to corona noise but shall also remain unaffected by impulse type noise which are generated by electrical discharge and by the opening and closing of circuit breakers, isolators, earthing switches etc. The equipment shall be made immune to a field strength of 10V/m expected to be caused by portable radio transmitters in the range of 20-1000 MHz . In his offer, the bidder shall clearly explain as to what measures have been taken to make the equipment insensitive to corona noise, white noise and to impulse noise of an amplitude larger than the wanted signal and submit full field test and laboratory test reports. The guarantee on design data shall not be acceptable. The equipment shall be unaffected by spurious tripping signals. The bidder shall submit proof as to how this is achieved satisfactorily. The equipment shall be suitable for transmission of direct and permissive trip signal as well as blocking signals for protective gear of power system. The equipment shall be operated in the audio frequency range in speech band or above speech band as superimposed channel in 4KHz band of SSR carrier. The equipment shall operate with full duplex frequency shift mode of operation. The protection signaling equipment shall be solid state design, modular in construction and have a proven operating record in similar application ever EHV systems. Details regarding application of the equipment over 220kV systems shall be submitted along with the bid Each protection signaling equipment shall provide: Transmission facilities for minimum tow protection signals. Reception facilities for minimum two protection signals. Direct trip Send and Direct Trip Receive facility in addition to above two protection signals. The equipment shall be designed for remote tripping/blocking on permissive basis and direct tripping for reactor fault and others. The overall time of PLC.VFT and transmission path for permissive trip/blocking shall be 20m. sec. or less and for direct tripping 30m.sec. or less even for the longest line section. -7- Operating time lower than specified above may be preferred provided they fulfill the requirements of security and reliability as mentioned below: False-trip probability >10-5 (Noise burst of nay amplitude) Fall to trip probability >10-5 For S/N dB In 3.1 KHz Band (while Noise Measurement) 8.6 It may be emphasised that specified time, as mentioned above is composed of the following: a) Back-to-Back signal delay in frequency shift or coded signals protection equipment. b) Back-to-Back delay in PLC terminal. c) Delay in transmission line. d) Operation time of interposting relay, if any in frequency shift or coding equipment. Reference is invited in this regard to the guide lines expressed in CIGRE Publication “Teleprotection” report by Committee 34-35. 8.7 a) b) c) 8.8 The following transfer criteria shall be provided by the equipments: Transmit side:One number potential free No (normally open) contact of protective relays (to be supplied by the HVPNL) of under noted rating of each of the following functions: i. Permissive trip command ii. Direct trip command Contact rating. Maximum voltage :360volts. Maximum current rating :5amps. Maximum power rating :1200 w/va. Receive side:Voice frequency transmission equipment for network protection shall be provided with one potential free No (normally open) contact of the under noted rating of each of the following functions: i. Permissive trip command ii. Direct trip command Contact rating. Rated voltage :250volts DC Rated current :0.1ADC. Other Parameters :as per IEC-255-0-20 Alarm:In addition, the voice frequency protection terminal shall provide at least one number potential free change over contact of the following rating for alarm purposes. Rated voltage :250volts DC Rated current :0.1ADC. Other Parameters :as per IEC-255-0-20 Frequency shift of coded signal protection equipment shall have atleast two channels. In order to ensure full availability of PLC protections channel, arrangement of parallel circuiting of these tow channels as main and stand by channels shall be made. This arrangement is generally shown in relevant specification drawing. Each arrangement shall be developed by the successful Bidder in co-ordination with protective relay Contractor. The parallel wiring should however retain the concept of two protection channels of each type of protection with each backing up the other 100% during normal operation and also permit testing without affecting the other. The contractor shall submit drawings showing Inter-connection between PLCC and protection panels for approval by the HVPNL. -8- 8.9 It has to be ensured that under no circumstances protection channel should share the power. Each protection channel shall be able to transmit power for which system is designed. For example, a 20 W PLC terminal shall transmit 20 Watt (Max.) for protection channel alone in the event of fault. Speech and superimposed data channels, in the same protection terminal must get disconnected momentarily during the operation of protection channels. 8.10 The equipment shall be constructed such that in permissive line protection system, operational reliability of the protection channel may be checked over the carrier link by means of a loop test. It shall be possible to carry out the above test from either end of the carrier link. During healthy condition of the transmission line, the loop test shall not initiate a tripping command. In the event of a system fault, while loop test is in progress, protection signal shall over-ride the test signal. 8.11 The equipment shall be complete with built in counters for counting the number of trip commands sent and number of trip commands received. 8.12 Contractor shall develop drawings showing inter-connection between protection panels and PLCC panels and submit the drawings for HVPNL’s approval. 8.13 The voice frequency transmission equipment shall be suitable for 48V (+) 15% and (-)10% DC power supply. 9. DOCUMENTATION 1. The successful bidder shall submit six sets of following drawings for HVPNL approval:2. Outline general arrangement 3. Name and rating plate 4. Face plan 5. Wiring Diagram 6. Terminal connectors 7. Block Diagram 8. Terminal plan 9. Any other drawing required to complete the equipment like bird barrier etc. NOTE: All above drawings should be a minimum space (14x10cm) for stamping the approval of drawings by HVPNL. 10. ELECTRONIC PRIVATE AUTOMATIC EXCHANGE (EPAX) 10.1 The Electronic private Automatic Exchange (EPAX) wherever specified shall be provided with 24 subscriber lines and 8 trunk lines. The trunk lines shall be connected to PLCC channel (speech panels as existing in HVPNL i.e. WSI, BPL, ABB make). The exchange will have its own ringing current and tone generator etc. The exchange shall be suitable for working on 48 VDC Power supply (Positive pole state & of modular construction and shall have multiple switching lines (minimum 4 routes). It shall be programmable, either to debar or provide over-riding facility to certain subscribers. 10.2 EPAX shall also be provided with two(2) additional interface units and operate exclusively with HVPNL’s leased subscriber lines of Department of Telecommunication (DOT) and compatible with 2 wires full duplex, voice grade mode of operation. The DOT leased lines shall be coordinated by the HVPNL with the leasing authority (DOT). -9- 10.3 The technology of the equipment supplied by the contractor must conform to C-DOT version. 11. TELEPHONE SET: The instrument should be sturdy & compact in form. It should have Tone/Pulse facility, flash and pause facility, last number redialing, visual ringing indication, ring volume control and fast dialing facility. It should be compatible with different types of switching units used in conjunction with PLCC system in HVPNL and also with the DOT line. It should be able to be feed from exchange with F 48 V, 2x200 ohm feed bridge or 56 V 2x400 ohms feed bridge. - 10 - SECTION-10 CHAPTER-2 TECHNICAL SPECIFICATIONS FOR LINE TRAPS 1. LINE TRAP: 1.1 General: The manufacturer whose line trap are offered should have designed, manufactured and tested as per IS/IEC or equivalent standard and supplied the line traps for the specified voltage and fault level. All the equipment covered under the package shall conform to the requirements of the latest edition of the relevant IEC/IS specifications or equivalent National Standards, except to the extent modified by this specification and shall also be in accordance with requirements under section I & II. 1.2 Location of equipment: The line traps as specified shall be installed at the respective ends of the transmission lines. 1.3 Line trap requirements: Line traps shall be inserted into Extra-high voltage transmission line to prevent undue loss of carrier signal for all power system conditions. Its impedance shall be negligible at power frequency (50Hz) so as not to disturb power transmission but shall be relatively high over the frequency band appropriate to carrier transmission. Line trap shall consist of a main coil designed to carry continuously the rated current without exceeding the limit of temperature rise. It shall be supplemented with a protective device and tuning device. Line trap shall be broad band tuned for its entire carrier frequency range form 50 to 500KHz. Resistive component of impedance of the line trap within its carrier frequency blocking range shall not be less than 570 ohms. Line trap shall be provided with a protective device in the form of surge arrestors which shall be designed and arranged such that neither significant alteration in its protective function nor physical damage shall result from either temperature rise or the magnetic field of the main coil at continuous rated current or rated short time current. The protective device shall neither enter into operation nor remain in operation, following transient actuation by the power frequency voltage developed across the line trap by the rated short time current. The protective device shall be shunt connected to the main coil and tuning device. The lightning arrestor shall be station class current limiting active gap type. Its rated discharge current shall be 10KA. The lightning arrestor provided with the line trap of each rating shall fully comply with the requirements of IEC-99-4. It shall conform to type tests as applicable and type test certificate for the same shall the submitted by the bidder. The lightning arrestor provided with the line trap shall be subject to the routine and acceptance tests as per IEC-99-4. Line trap shall be equipped with the bird barriers. -1- Line trap shall conform to IEC-353 (latest) fulfilling the all technical requirements as follows: Technical Parameter 220kV line 66kV line Rated power frequency 50 Hz 50 Hz Rated system voltage 220kV 66kV Highest system voltage 245kV 72.5kV Rated continuous, current at 50 degree C ambient. 1250A 630A 31.5KA ---------- 16KA Broad band to be indicated by bidder --------- ______ 1.0 1.0 Rated short time current for 1 second Type of tuning Rated blocking band-width Minimum resistive component of impedance within the rated blocking band-width Rated inductance of main coil (mH) Radio interference voltage Not more than 500 micro volt at 187 kV (rms) The Bidder shall indicate continuous current rating of the line trap at 65 deg. C ambient. The line trap shall conform in type tests and shall be subjected to routine tests as per IEC-353, as per following details: TYPE TEST: The equipment should be offered type test. Test reports should not more then seven years old reckoned from date of bid opening in respect of all the tests carried out in accredited laboratories (based on ISO/IEC) by a reputed accreditatic body or witnessed by HVPN or another electric power utility and be submitted by the successful bidder to HVPNL for approval as schedule given in Bar Chart. i) Short time current test. ii) iii) iv) v) vi) vii) viii) ix) x) Power frequency voltage test on tuning device. Impulse voltage test. Temperature rise test Measurement of radio influence voltage Measurement of the rated inductance of the main coil Measurement of power frequency inductance of the mail coil Measurement of blocking resistance and blocking impedance Measurement of tapping loss and tapping loss based on the blocking resistance Measurement of loss at power frequency. Routine Test: As per quality assurance program (QAP). ACCEPTANCE TESTS: The following acceptance tests as stipulated in the relevant IS-8793: 1995 shall be carried out by the Supplier in presence of HVPNL representative, unless dispensed with in writing by the HVPNL. -2- i) ii) iii) iv) 1.4 Power frequency voltage test on tuning device. Measurement of the rated inductance of the main coil Measurement of blocking resistance and blocking impedance Measurement of tapping loss and tapping loss based on the blocking resistance LINE TRAP MOUNTING: The line trap shall be suitable for outdoor suspension mounting and shall be mechanically strong enough to withstand the stresses due to maximum wind pressure of 260kg/Square meter. Contractor shall be required to co-ordinate the mounting arrangement with the existing arrangement at different sub-stations. Non-magnetic suspension hook/link of adequate length and tensile strength to provide necessary magnetic clearance between the line trap and suspension hardware shall be supplied by the Contractor. The line trap shall be supplied compete with disc insulators and hardware fittings. The disc insulators to be supplied with the line trap shall conform to IS: 731/1971 with latest amendments. All hardware fittings associated with these insulators shall conform to IS: 2486 (Part-I)/1971 (1st Revision), IS: 2486 (Part-II)/1971 (1st Revision), IS:2486 (PartIII)/1974 and IS:2486 (Part-IV)/1981 with latest amendments & revision. Copies of test certificates of type tests and routine tests as stipulated in the above quoted ISS shall be furnished with tender. 1.5 LINE TRAP TERMINAL CONNECTORS: The line traps shall be suitable for connecting to ACSR single/twin bundle Zebra conductor as per layout requirements. Necessary connector shall be supplied by the Contractor. Terminal connectors shall conform to IS: 5561 and shall also comply with requirements indicated in Section GTR. Terminal connectors shall be suitable for either horizontal or vertical take off the conductor. 1.6 Clamps/connectors shall be designed for the same current ratings as line trap and temperature rise shall not exceed 0.5 deg.C over 50 deg C ambient. DOCUMENTATION The successful bidder shall submit four sets of following drawings for HVPNL approval:- NOTE: 1. Outline general arrangement 2. Name and rating plate 3. line trap mounting arrangement 4. terminal connectors 5. Any other drawing required to complete the equipment like bird barrier etc. All above drawings should be a minimum space (14x10cm) for stamping the approval of drawings by HVPNL. -3- SECTION-10 CHAPTER-3 TECHNICAL SPECIFICATION FOR COUPLING DEVICE 1. COUPLING DEVICE: 1.1 The coupling devices shall be interposed between the capacitor voltage transformer/coupling capacitor and coaxial line to the PLC transmitter/receiver and in conjunction with the capacitor voltage transformer/coupling capacitor shall ensure: a) Efficient transmission of carrier frequency signals between the carrier frequency connection and the power line. Safety of personnel and protection of the low voltage parts and installation, against the effects of power frequency voltage and transient over voltage. b) The coupling device, in conjunction with the CVT/CC shall form and electric filter of band pass type. a) b) c) d) It shall match characteristic impedance of HT line to impedance of the carrier frequency connection. Impedance matching between power line and the carrier frequency connection may be done by a transformer or an auto-transformer. Galvanic isolation between primary and secondary terminals of the coupling device shall be performed by the above mentioned transformer. Power frequency currents derived by the CVT may be drained to the earth by a separate inductance termed drain coil of suitable rating or through primary of the above transformer. Voltage surges coming from the power line at the terminals of the coupling device shall be limited by a non-linear surge arrester of suitable rating in the primary side. Requirement of a gas type voltage arrester in secondary side of the coupling device shall have to be fully justified. The surges Arrester shall have power frequency spark over voltage co-ordinated with the equipment ahead of it. e) For direct and efficient earthing of its primary terminals, the coupling device shall be equipped with an earthing switch. The coupling device shall be designed such that it shall not be possible to remove the cover before the earthing switch is operated to the ‘earthed’ position. Further the Earth Switch shall be available for earthing of CVT-HT terminals, when the coupling filter units are removed from circuit for maintenance/replacement. The design shall take due regard of requirements for safety in accordance with the Indian Electricity Rules. 1.2 Two numbers ‘phase to earth’ type coupling filters shall be used to achieve in secure ‘phase to phase’ / ‘Inter-circuit coupling’. Connection between secondaries of the two phases to earth type coupling device shall be through a balancing transformer/hybrid such that reliable communication shall be ensured even when one of the coupled phase to earthed or open circuited on the line side. a) Coupling device shall conform to IEC-481/IS-8997 and IS-8998 shall have the following carrier frequency characteristics as applicable to a phase to earth type coupling device. Nominal line side 400 ohms for 220kV line Ph-E & impedance 600 ohms for Ph-Ph -1- b) Nominal line side impedance 150 ohms (balanced) c) Composite loss Not more than 2 dB d) Return loss Not less than 12 dB e) Band width shall suit the frequency plan between 40 and 500 KHz f) Nominal peak envelope Power Not less than 650 Watt. (for inter-modulation product 80 dB down) The coupling device shall be suitable for outdoor mounting. Temperature of metallic equipment mounted out door is expected to rise upto 65o C during the maximum ambient temperature of 50o C specified. The equipment offered by the Bidder shall operate satisfactorily under these conditions. The elements of coupling device shall be fitted on a base plate and enclosed in a metal box. The HT Terminal of coupling device shall be connected to HF terminal of the CVT by means of 6mm Sq. copper wire with suitable lugs & taped with 11kV insulation by the contractor. Coupling device shall have at least two terminals for carrier equipment connection. Bidder shall confirm that such a parallel connection to coupling device directly will not result in any additional attenuation. The coupling device including the drainage coil, surge arrestor and earthing switch shall conform to type tests and shall be subjected to routine tests as per IEC-481/IS:8998. 1.3 1.3.1 1.3.2 1.3.3 TESTS: Type Tests The equipment should be offered type test. Test reports should not more then seven years old reckoned from date of bid opening in respect of all the tests carried out in accredited laboratories (based on ISO/IEC) by a reputed accreditatic body or witnessed by HVPN or another electric power utility and be submitted by the successful bidder to HVPNL for approval as schedule given in Bar Chart. Routine Tests As per quality assurance program (QAP). Acceptance Tests All acceptance tests as stipulated in the relevant IS:8998 shall be carried out by the Supplier in presence of HVPNL representative, unless dispensed with in writing by the HVPNL. -2- SECTION-10 CHAPTER-4 TECHNICAL SPECIFICATION OF 48 VOLTS 120AH SMPS BASED BATTERY CHARGER SUITABLE FOR VRLA MAINTENANCE FREE BATTERY BANK 1. SCOPE: This specification provides for design, Engineering, manufacture, stage testing, inspection and testing before dispatch, packing, forwarding and delivery at site FOR destination of 48 Volts 300/120AH SMPS based battery charger suitable for indoor installation, complete with all fittings accessories and associated auxiliary equipment mandatory which are required for efficient and trouble free operation as per specified here under. It is not the intent to specify completely all the details of design and construction of equipment. However, the equipment shall conform in all respects to the high standard of engineering, design and workmanship and shall be capable of performing in continuous commercial operation up to the Bidder’s guarantee acceptable to the purchaser. The equipment offered shall be complete in all component necessary for its effective and trouble free operation along with associated equipment interlocks protection scheme etc. Such components shall be deemed to be within the scope of supply irrespective of whether those are specially brought out in this Specification and or the commercial order or not. All similar parts particularly movable ones shall be interchangeable. 1.02 1.03 1.04 CLIMATIC CONDITIONS : The equipment to be supplied against the specification shall be suitable for satisfactory continuous operation under the following tropical conditions: Max. ambient air temperature Max. daily average ambient temperature Max. yearly weighted ambient temperature 500 C 450 C 350 C Min. air temperature Max. humidity Min. relative humidity Average number of thunder storm days per annum Average annual rain fall Number of months during which tropical monsoon conditions prevail altitude above MSL (-) 50 C 100% 26 % 40 15 cm to 100 cm. 4 months (June to Sept). Varies from 61 meters to 815.00 mtrs. 120 days 0.3g. Heavy 1.0 KW/sq.m. 195 kg/sq.m. Average number of rainly days per annum. Seismic level (Horizontal acceleration) Degree of pollution Intensity of solar radiation Max. Wind load STANDARD: All material and equipment shall comply in all respect with requirement of the latest addition of the relevant IS/IEC/TEC/RDSO. A set of standards adopted, translated in English, if it is in language other than English, shall also be enclosed with the tender, to enable due comparison, wherever a standard is specially mentioned in these specification. It is understood that the corresponding standard amongst the sources mentioned above shall also apply. MANUFACTURE AND WORKMANSHIP: All the material used in the construction of the equipment shall be of the best quality obtainable of their respective kinds and whole of the work shall be of the highest class, -1- well finished and of approved design and make. Casting shall be free from blow holes, flaws and of the true form and dimensions. All machined surfaces shall be true and smooth and well finished. 1.05 DUTY AND GENERAL ARRANGEMENTS: The power for the charging apparatus shall be given through an independents 4-core cable connection from an A.C. 50 cycles 3 phase 415 ± 10% volts switchboard fed from a Station Transformer. 1.06 GENERAL TECHNICAL REQUIREMENT: The battery chargers of 48V/25Amp. in N+1 configuration with ultimate capacity 50Amp/75 Amp/100Amp shall be of SMPS type with positive earth. The system shall consist of a Distribution/Switching/Alarms arrangement (DSA) and Float Rectifier-cumChargers (FR/FCs) in a rack. It shall employ modular configuration for flexible provision of DC Power. It shall employ menu driven Micro Processor Controlled Techniques for DSA as well as module for control, monitoring and alarm to achieve better reliability of the system. The SMPS battery chargers shall be capable of continuous operation with float voltage 2.23 to 2.25 Volts per cell (at 27 Deg. C) and 2.3 Volt per cell (at 27 Deg C) for charge voltage while supplying the constant DC load 1.06.1 The SMPS battery chargers shall have constant voltage characteristics throughout the range (from zero to full load) at the floating value of the voltage so as to keep the maintenance free type VRLA batteries fully charged but without harmful overcharge. The system shall employ a modular configuration to provide flexibility in view the future load requirements of DC power. The modules shall be accommodated in a rack. Distribution/Switching/Alarm (DSA) shall be provided in first rack or in a separate rack as per manufacturer’s design for the ultimate system capacity. All factory wiring for the rack shall be for the ultimate capacity so that only plugging of FR/FC module shall enhance the DC power plant output. 1.06.2 Principal Parameters: Input Nominal Voltage i) 230 Volt +/-10% AC single phase for module of 25Amp.For ultimate capacity of 50Amp ii) System rack having ultimate capacity of 75 Amp and 125Amp will be provided AC Three phase input power supply and each module shall operate on individual phase of three-phase AC input power supply. Input Voltage Range 165V to 260 V AC Frequency 48Hz to 52Hz Power factor >0.98 at 50% and above load Efficiency >0.90 at 50% and above load Soft Start time 10 sec Min output current ramp up Output Voltage adj. 48V to 56V DC Current limit adjustable For 50Amps SMPS 5 to 50A Current limit adjustable For 25Amps SMPS 5 to 25A Regulation: 1) Output voltage +/-5% of DC output voltage for any load of 25% to 100% over shoot/under shoot when charger is switched +/-5% of DC output voltage for any load of 25% to 100% on 2) DC output voltage over shoot for a step change in AC voltage -2- 1.07. 165V to 260V single +/-5% of DC output voltage for any load of 25% to 100% phase 3) DC output voltage for a step load change of 25% to 100% Ripple <200mV RMS Load Sharing Better than +/-5% active current sharing at full load Cooling Convection Main Features of SMPS Charger 1.07.1 CONSTRUCTIONAL FEATURES: The rack structure shall be made up of rigid frame work of steel profiles and rear door may be of hinged or removable type. The rear door shall be provided with ventilation arrangement. Alternate design of aluminum and other rigid structure meeting the requirements are also permitted. The rack shall be free of sharp edges or sharp corners. The rack shall be designed for easy maintenance & installation. The rack mounting arrangement shall be such as to provide easy access from rear and top for installation and maintenance. The individual FR/FC module shall be easily mounted to/removed from the front side of the rack. The FR/FC module shall be designed to slide in to the rack on a suitable mechanical arrangement. The associated AC input, DC output connections, control/systems & interface cable connecting the modules shall be connected /disconnected easily without causing any interruption in the supply and damage to load or other working module. Proper thermal engineering of hardware design shall be done by the manufacturer so as to ensure the uninterrupted use of the equipment. The rack complete with all panels fitted shall be designed to allow cooling by natural convection. With the doors in position, all the common visual alarms and meters shall be clearly visible. However the fixtures on the door shall not restrict the movement of door in any way. The FR/FC modules shall be cooled by natural convection. AC input to FR/FC shall be through locking type arrangement. DC output shall be through hot plug in connector on the FR/FC side and through lugged termination on the bus bar/termination end. Control alarm and mentoring connection shall be through connectors. The FR/FC module shall be removable from the rack only. All AC input, DC output & alarm/control/monitoring cables interconnecting the modules and rack shall be easily disconnected by plugs or connectors. AC Terminations The input terminal should be single phase or three phases as the case may be cleared marked as R Y B and N and for AC three phase, L and N for AC single phase. AC input termination shall be suitably protected against the accidental touch/contact with the working staff for their protection and shall also have clear and prominent be “Danger” marking. Screening shall be provided between AC and DC components to prevent accidents. The AC input connection to the rectifier module shall be by means of locking type plug and socket arrangement. All the connection between distribution and FR/FC shall be through proper rated cables only. Fuses and circuit breakers for each FR/FC shall be easily accessible and properly rated. Proper termination for the AC input of the circuit breakers and its output to the FR/FC. The system racks having ultimate capacity of 100 Amp. will be provided AC three phase input power supply and each module shall operate on individual phase of three phase AC input power supply. -3- DC Terminations The output of each rectifier in the negative load shall be taken through full rated ISI marked MCBs. All the AC, DC control & alarm cabling shall be supplied with the rack. All DC +ve and - ve leads shall be clearly marked. Wiring All insulated conductors except those within the confines of a printed circuit board assembly shall be of the rating enough to withstand the maximum current and voltage during fault and overload. All the wires and cables used shall be fire retardant as per IS 1554 with amendment I (June 94). All wiring shall be neatly secured in position and accurately supported. Where wires pass through any part of metal or cover the holes through which they pass shall be suitably bushed. Earthing: Two power earth terminals shall be provided in the frame of the system. Mounting off component & layout: Components mounting and fixing methods shall be secured. Suitable mechanical structure/ arrangement for holding modules in position shall be provided so that the module is held firmly by sliding through it. The FR/FC modules shall be cooled convection. AC input to FR/FC shall be through locking type arrangement. DC out put shall be through hot plug in connector on the FR/FC side and through lugged termination on the bus-bar termination end. Control, alarm and monitoring connections shall be through connectors. The FR/FC module shall be removable from the front of the rack only. All AC input, DC output and alarm/control/monitoring cables interconnecting the modules and racks shall be easily disconnected by plugs or connectors. 1.07.02 Distribution, Switching, Control, alarm & Monitoring (DSA) The Distribution Switching sub - system of DSA shall preferably be in the modular from whereas control, alarm &, monitoring sub-system shall only be modular. The Controller must be Microprocessor based. The distribution switching sub-system 'may be accommodated in a rack with other FR/FCs or in separate rack. These sub systems shall be rack mountable. DSA shall preferably be housed in the upper portion of the rack above the FR/FC modules. The unit shall be equipped to meet the ultimate system capacity. 1.07.03. Battery Temperature Compensation. The charger shall be provided with the appropriate circuitry to interface with the temperature probe assembly. With the probe, the charger shall automatically compensate gassing and constant voltage setting inversely proportional to the probe’s temp/ battery ambient temp., so that over charging at high temperature and under charging at low temperature can be prevented. 1.07.04 Current Limiting (Voltage Drop) Current Limiting (Voltage" Drop) shall be provided for float/ charge operation. The float/charge limiting shall be continuously adjustable between 50% to 100% of rated out put current for out put voltages range of 44.4 to 56 volt. For test purposes upper limit of 100% +5% and lower limit of 50% - 5% shall be acceptable. The float and charge current limit adjustment shall be provided on the front panel of the rectifier module. The FR/FC modules shall be fully protected against short circuit. It shall be ensured that short circuit does not lead to any fire hazard. 1.07.5 Fuses All fuses shall be HRC Link type. Fuses shall be mounted on fuse carriers which are in turn mounted on fuse bases. Wherever it is not possible to mount fuses on carriers, -4- fuses shall be directly mounted on plug-in type base. In such case one insulated fuse pulling handle shall be supplied for each charger. Fuse rating shall be chosen by the Bidder depending on the circuit requirement. All fuses in the chargers shall be monitored. Fuse failure annunciation shall be provided on the failure of any fuse. 1.07.6 Blocking Arrangements Blocking arrangement shall be provided in the positive pole of the out put circuit of the charger to prevent current flow fr9m the DC battery into the charger. 1.07.7 Monitoring, Alarm and Indicating Lamps. The visual indications/ display such as LEDs, LCDs or a combination of both shall be provided on each FR/FC module to indicate: (A) Functional indications: The following functional indications shall be provided on FR/FC and DSA: a) Mains available. b) FR/FC on Auto Float. c) FR/FC on Auto charge. Note: The functional indication (a) shall be provided on both DSA & FR/FC module. While b and c may be provided either on DSA or both FR/FC & DSA. (B) Alarm indications (i) On FR/FC (a) FR/FC over voltage, under voltage or output fail. (b) FR/FC over load (voltage drop) Functional indications shall be extended as status and alarm. FR/FC fail to distribution / switching / control & alarm unit. (ii) On DSA a) Load voltage high (above 56v /low (below 45.6 v) b) FR/FC fail c) Mains out of range d) System Over Load e) Mains ON/Battery Discharge f) Temp. Compensation fail g) Battery Fail or No Battery h) Battery Isolated from the load All alarm circuits shall be provided with suitable delay to ensure that they do not operate to transient. All the protection /alarm shall be within tolerance of O.25v in case of DC voltage and 10/0 in case of current. For AC voltage it shall be +/- 5V. Every alarm, condition shall be accompanied with an audio alarm with audio cut off facility. Potential free contacts two (one for alarm and one redundant) shall be provided for extension of alarms to centralized display. . 1.07.8 Radio Interference The equipment shall be efficiently screened against interference to radio and also other communication equipment, which may be installed in the same building. All sources of noise shall be filtered if necessary with suppressors generally in accordant with relevant standards. 1.07.9 Name plates and marking The name plates shall be while with Black engraved letters. On top of each charger, on front as well as rear sides, larger and bold name plates shall be provided to identify the -5- charger. Name plates with full and clear inscriptions shall also be provided on and inside of the panels for identification of the various equipments and ease of operation and maintenance. An etched, engraved or anodizer name plate shall be fitted on each $MPS battery charger unit having following details inscribed. Manufacture's name. P.O . No. & date. S.No. of SMPS unit Rating of SMPS charger Input voltage of SMPS charger Output voltage of SMPS charger Year of Manufacture 8.0 RESPONSIBILITY FOR DESIGNS: The contractor shall assume full responsibility for co-ordinate and adequate design and shall conform to the best engineering practice for the operating conditions specified. In case the equipment covered by this specification is to be co-ordinate with other equipment, the contractor shall furnish complete information and data as may be desired by the purchaser. 9.0 TESTS & INSPECTION: The tenderer must furnish test reports carried out on one of the SMPS battery charge unit which shall pass all the prescribed type tests for conformity of relevant standards. These type test reports must be issued by a Govt. approved / Govt. recognized/ a Govt. accredited laboratory and must not be older than 7 years from the date of opening of tender. Routine/ acceptance tests shall also be carried out on each SMPS Battery Charger as per specification. Following type tests shall be carried out for compliance of specification requirements: TYPE TESTS: (I) (II) (III) (IV) (V) (VI) (VII) (VIII) 9.1 Visual Inspection Insulation Resistance Test Applied high Voltage test. Performance test. Test for protection device. Burn in test. Climatic test. Vibration test. ROUTINE & ACCEPTANCE TESTS: On each of the SMPS battery chargers following routine and acceptance tests shall be carried out at manufacturer's works before dispatch. (I) (II) (III) (IV) (V) Visual Inspection Insulation Resistance Test Applied high Voltage test. Performance test. Test for protection device & other tests shall be carried out as per requirement of -6- GTP in the presence of inspecting officer. 9.2 a) b) c) d) INSPECTION: The inspection of the equipments shall be carried out by the purchaser's representatives in accordance to the relevant standards. The purchaser shall have access at all times to the works and all other places of manufacture, where the equipments are being manufactured and; the supplier shall provide all facilities for unrestricted inspection of the Supplier's works, raw materials, manufacture of the material and for conducting necessary tests at any stage. The supplier shall keep the purchaser informed in advance about the manufacturing program so, that arrangements could be made for inspection. No equipments shall be dispatched from its point of manufacture unless the material has been satisfactorily inspected, tested and cleared. Inspection and acceptance of any quantity of equipment shall in no way relieve the Supplier from his responsibility for meeting all the requirements of this specification and shall not prevent subsequent rejection if such equipment is later found to be defective. 9.3 TESTS AT SITE: The purchaser reserves the right to conduct all the tests on the equipment after arrival at site and the supplier shall guarantee test certificate figures under actual service conditions. 10. DRAWINGS, LITERATURE AND MANUALS: In addition to any other drawings which the tenderer may like to submit lo show the arrangement and merits of the offered equipments. The following drawings shall be supplied with the tender. General installation layout of SMPS equipments showing position of all associated equipments. Detailed dimensional drawings and descriptive literatures of all the associated equipments separately. Circuit wiring diagram and schematic diagram. Literature/ pamphlets / manuals of SMPS and its associated equipments. i. ii. iii. iv. The successful tenderer shall within four weeks of placement of order, submit four sets of final version of all the drawings of the SMPS Battery Charger for purchaser’s approval. The purchaser shall communicate his comments/approval on drawings to the supplier within a period of four weeks. The supplier shall if necessary modify the drawings and resubmit three copies of modified drawings for purchaser’s approval within two weeks from the purchaser’s comment, which will be approved within 15 days. After receipt of purchaser’s approval the supplier shall submit four sets of drawings and literature containing erection, operating and maintenance instructions per equipment. A set of reproducibles of the approved drawing too will be supplied for the purchaser use. 11. i. ii. iii. iv. PACKING & MARKING All SMPS equipments shall be packed in strong seasoned wooden crates to avoid handling problem. The packing shall be of sufficient strength to withstand rough handling during transit, strong at site and subsequent handling in the field. Suitable cushioning, protective padding, or dunnage or spacers shall be provided to prevent damage or deformation during transit and handling. All packing cases shall be marked legibly with the appropriate caution symbol and -7- v. Each consignment shall be accompanied by a detailed packing list containing the following information: a) Name of the consignee. b) Details of consignment. c) Destination. d) Total weight of consignment. e) Sign showing upper/lower side of the crate. f) Handling and unpacking instruction. All gauges, meters, instruments etc. shall have dials or scales calibrated in metric system of units. All name plates, instruction plate, warning signs and any marking what-so-ever on the equipment and its parts and accessories shall be in Hindi-English Language, using idioms, words and meaning as in current use in India. In order to facilitate sorting and erection at site every part of the plant and equipment shall be suitably marked. 12. PLACE OF MANUFACTURE AND INSPECTION: The tenderer shall state in his tender the place(s) of manufacture, testing and inspection of the various portions of the work included in the tender. The purchaser or his duly authorised agent shall have access to the contractor's or sub contractor's work at any time during working hours for the purpose of inspecting the manufacture and testing of materials, equipment and completed plant and the contractor shall provide the necessary facilities for inspection. 13. DEPARTURE FROM SPECIFICATION: Should the tendered wish to depart from provision of this specification either on account of a manufacturing practice or for any other reasons, he will draw special attention to the proposed points of departure in his tender and submit such full information, drawings & specifications as will enable the merit of his proposal to be appreciated. -8- APPENDIX ‘A’ SCHEDULE OF REQUIREMENT Battery Charger: The Battery Charging equipment shall be housed in a sheet steel cabin finished in stove enameled light grey color conforming to shade of 631 of IS-5 specification. The charger cabin shall have thickness of 18 gauge or better with adequate ventilation. The minimum size of cubical should be 585mm Width, 500mm depth and 560mm Height. The rack shall be free of sharp edges or sharp corners. The rack shall be designed for easy maintenance & installation. The rack mounting arrangement shall be such as to provide easy access from rear and top for installation and maintenance. Two power earth terminals shall be provided in the frame of the system to provide effective earthing to the system. The individual Rectifier module shall be easily mounted to/removed from the front side of the rack. The Rectifier module shall be designed to slide in to the rack on a suitable mechanical arrangement. The associated AC input, DC output connections, control/systems & interface cable connecting the modules shall be connected /disconnected easily without causing any interruption in the supply and damage to load or other working module. There should be auto/manual change over between float and boost charger. Charger Section: The charger should be suitable for operation from single (230 ± 30% volts, 50Hz) or 3 phase (415 ± 30% volts, 50Hz) AC supply as per the system ultimate capacity and suitable for charging 24 cell at 2.16 to 2.40 per cell while simultaneously supplying a continuous load as per requirement at an ambient temp. of 45⁰C. The output of charger should be stabilized within 1% of the charging voltage. There should be individual MCB for each module and complete system. The charger section shall comprise of the following items: S No. Item Description Qty 1. Cabinet 1 2. Hot Swap Rectifiers Modules 25A/48V N+1 ( N = Load Current + Battery Charging Current) The rectifier Modules shall be hot swappable with Individual Alarm Indications for Over Voltage/ Under Voltage or Output Fail. 3 Dropping Diode During the Boost charging the full battery voltage should not be reflected on the bus bars, that is, it should be ensured that the constant voltage is available on DC bus bars irrespective of the fact whether the battery is on float or on boost charge and at same time all battery cell should be equally charged. There should be auto/manual change over between float and boost charger. 4 Voltage monitoring Card 1 5 AC Contactor 1 6 DC Contactor 1 7 Low Voltage Detection Card 1 8 MCB 10A 4 9 MCB 64A 2 10 Lightening Protection Device Class C 1 11 Battery temperature Compensation Probe 2m 12 Microprocessor based Controller 1 No The controller should be mounted so that it is front accessible , front monitored and Front Controlled. It shall be installed in such a manner that the LCD panel is visible without opening and Lock / Door of the unit. The controller should have the following facilities: -9- A. Metering : a) Load Voltage. b) Load Current. c) Battery Voltage. d) Battery Current. e) Battery Temp. f) Voltage and current of Individual module. B. Alarms and Indications : a) Load voltage high. b) Single Rectifier alarm c) Multiple Rectifier alarm d) Mains out of range e) System Over Load f) Mains ON/Battery Discharge g) Temp. Compensation fail h) Battery Fail or No Battery i) Battery Isolated from the load All alarm circuits shall be provided with suitable delay to ensure that they do not operate to transient. All the protection /alarm shall be within tolerance of O.25v in case of DC voltage and 10/0 in case of current. For AC voltage it shall be +/- 5V. Every alarm, condition shall be accompanied with an audio alarm with audio cut off facility. C. Functional Indications: a) Mains available. b) Rectifier on Auto Float. c) Rectifier on Auto Charge. d) Alarm to indicate general alarm condition 13. Potential free contacts: Potential free contacts should be provided for extension of alarms to centralized display. a) Mains out of range. b) Single Rectifier alarm c) Multiple Rectifier alarm d) Communication Error. e) System Over Load. f) System voltage high. g) System voltage low. All the components should be of best quality and from reputed manufacturers. The layout of components, wiring workmanship reliability etc. shall be of best quality. Adequate space should be provided within the charger section and Distribution, Switching, Control, alarm & Monitoring section for easy accessibility of MCB, Fuses, Alarms, protection devices etc. The charging equipment should be complete with the various component listed above but necessarily limited to the same. The charger shall also be complete with wiring, glands and fixing bolts. - 10 - SECTION-10 CHAPTER-5 TECHNICAL SPECIFICATION OF H.F.CABLE (150 OHMS BALANCED) FOR CONNECTING POWER LINE CARRIER COMMUNICATION TERMINAL WITH THE ASSOCIATED EQUIPMENT FOR HVPN CARRIER NETWORK 1. GENERAL: High frequency cable shall connect the coupling device installed in the switchyard to the PLC terminal installed indoor. The high frequency cable to be offered by the bidder shall be suitable for being laid directly in trenches or in ducts. The cable shall be tinned copper braided and steel armoured and its outer covering shall be protected against attack by termites. Bidder shall offer his comments on method employed by him for earthing of screen and submit full justification for the same with due regard to safety requirements. 1.1 1.1.1 SCOPE:This specification covers details of H.F. Cable (150 Ohms BALANCED) required for connecting Power Line carrier Communication terminals with the associated equipment for HVPN carrier Network. 1.1.2 The scope of supply shall Include design, manufacture, testing at manufacturer’s works before despatch and delivery of the H.F. Cable for use on Power Line carrier Communication equipment in HVPN. 1.2 1.2.1 CLIMATIC CONDITIONS:The EHV grid substations (66kV and above) where the HF Cable is required to be installed are located in the level plains of Haryana. The climatic conditions are of extreme nature varying from extreme cold to dry and tropical humidity to hot. 1.2.2 The HF Cable is required to serve satisfactorily conditions prevailing at site:Maximum ambient temperature : Minimum temperature : Relative humidity : a) Maximum : b) Minimum : Average Nos. of thunder Storms days per annum : Average Nos. of rainy days per annum : Average rain fall per annum. : Average number of dust storms days per annum : Attitude above mean sea level : Maximum temperature in the : shade. Maximum wind pressure : i) ii) iii) iv) v) vi) vii) viii) ix) x) -1- under the following climatic 50oC -2.5oC 100% 26% 45. 120 days 900mm 35 less than1000 45oC. 195 Kg/M2 1.2.3 The atmosphere is to be considered as laden with industrial and town gas and dust in suspension during dry-months. Fog smoke and mild acid are also present. Heavy lighting is also present during the months from June to October. The H.F.Cable is exposed to sunshine, rain, Fog, Hail, Snow etc. 1.3 MATERIALS AND WORKMANSHIP:- 1.3.1 All materials used in the construction/manufacture of the H.F.Cable shall be brand new and of the best quality obtainable of their respective kind and shall confirm to their respective Indian Standards or other equivalent International recognized standards whenever applicable. The successful bidder shall assume full reasonability for coordinated and adequate design. 1.3.2 The workmanship for HF Cable shall be of the highest grade and the entire construction in accordance with the best modern engineering practice. The HF Cable shall be designed to ensure satisfactory operation under the atmospheric conditions prevailing at site. 1.4 STANDARDS: 1.4.1 The HF Cable and all its materials covered by this specification shall unless otherwise stated complete in all respects with the requirements of the latest edition of IS-5026 and IS-11967 Part-II/Sec-3. 1.5 DEPARTURE FROM SPECIFICATION:Should the bidder wish to depart from the provisions of this specifications either on account of manufacturing practice for any other reasons he shall draw special attention to the proposed points of departure a separate sheet(s) in his tender as per Annexure-III of this specification and shall submit such full information, drawings and specification so that the merits of his proposal may be fully understood. This specification shall be held binding unless the departures have been fully recorded as required above. 1.6 1.6.1 DOCUMENTATION:The successful bidder shall submit four sets of drawings for HVPNL approval. 1. 2. Drawing showing the inside/inner of the HF Cable and dimensions of its various components and structures including its weight. Any other drawing to explain details and merits shall also be submitted. NOTE: All above drawings should be a minimum space (14x10cm) for stamping the approval of drawings by HVPNL. 1.7 TROPICAL TREATMENT:- 1.7.1 The H.F.Cable can be subjected during the service to extremely severe climatic conditions detailed under Sr. No. 1.2 of this specification. All corrodible parts and surfaces shall be provided with such protective finishes so that no part of the installed H.F.Cable shall be injuriously affected by the atmospheric conditions. The H.F.Cable, if required, may be given special treatments for tropical conditions. -2- 1.7.2 All part of the H.F.Cable that are likely to develop corrosion under normal working conditions shall be effectively protected against corrosion by standard methods to achieve durable results. 1.8 BIDDER’S EXPERIENCE:- 1.8.1 The bidder (s) shall clearly state in their experience and capability to undertake design, manufacture, testing and supply of the items similar to that covered in this specification giving complete information about their establishment i.e. design office, working personnel, plant and machinery and testing facilities available at the manufacturer’s works. Details of collaboration, if any, with other renowned experienced manufacturers shall be stated in the tender. 1.8.2 The bidder shall supply list of purchase orders of similar item executed by them during the past, giving the name of the purchase, year of supply and place of installation of the item. 1.8.3 Information regarding satisfactory services/operation of the equipment supplied in the past be also furnished with the tender. 1.9 RESPONSIBILITY OF DESIGN:The successful bidder shall assume full responsibility for adequate design for the duty in view to ensure trouble free long service and tropical conditions and shall use such arrangement and material as to confirm to the best engineering practice for the operating conditions specified. Impedance of the cable shall be such as to match the impedance of the PLC terminal on one side and to that of the coupling device on the other side over the entire carrier frequency range of 40-500 kHz. The H.F.Cable (150 ohms balanced) shall meet the following parameters:1. 2. 3. 4. 5. 6. 7. 8. Overall diameter of H.F.Cable shall be between 20-25 mm. The mutual capacitance at 1 kHz of the H.F.Cable be 34 pf (Nominal)/meter. Conductor resistance of cable shall not exceed 12.8 ohm per km at 20oC & dia to be 1.4mm. The H.F.Cable shall have bending radius of 20 times the overall diameter of the cable. Loop resistance of H.F.Cable will not exceed 30 ohms per km at 20oC. Withstand test Voltage between conductor and outer sheath for one minute to be 4kV. The attenuation per km of the cable at various frequencies in the range of 10 to 500 kHz shall remain in the range of 1 to 5.1 dB/km. H.F.Cable will be with semi spaced dielectric, polythene string and tube and annealed tinned braided copper wire with 90% coverage, polythene inner sheath, GI wire braided armoring and overall PVC sheathed, preferably grey. The protective armoring provided in the HF cable shall consist of 0.3 mm (approx) dia of standard GI wire braiding with 70% coverage. -3- 1.10 TESTS:Type Tests: The equipment should be offered type test. Test reports should not more then seven years old reckoned from date of bid opening in respect of all the tests carried out in accredited laboratories (based on ISO/IEC) by a reputed accreditatic body or witnessed by HVPN or another electric power utility and be submitted by the successful bidder to HVPNL for approval as schedule given in Bar Chart. i) Corona extinction voltage ii) Characteristic impedance Attenuation (insertion loss) iii) Structural return loss iv) Capacitance v) Capacitance Stability vi) Capacitance unbalance vii) Transmission unbalance viii) Mechanically induced noise Voltage ix) Time delay x) Ageing stability xi) Stress-crack resistance xii) Outer conductor integrity xiii) Screening efficiency xiv) Cold bend xv) Flow xvi) Dimensional stability xvii) Contamination xviii) Bendability xix) Flammability xx) Resistance to fluids xxi) Solderability Weight ROUTINE TESTS: As per quality assurance program (QAP). ACCEPTANCE TESTS: The following acceptance tests as stipulated in the relevant ISS:11967 (Part2/Sec-3), shall be carried out by the Supplier in presence of HVPNL representative, unless dispensed with in writing by the HVPNL. i) Visual and mechanical inspection ii) Physical dimensions Iii Marking iv) Workmanship v) Characteristic impedance Attenuation (insertion loss) -4- vi) Structural return loss vii) Corona extinction voltage viii) Capacitance ix) Capacitance unbalance x) Transmission unbalance xi) Mechanically induced noise voltage xii) Time delay xiii) Cold dend xiv) Contamination xv) Resistance of fluids xvi) Solderability Weight 1.11 INSPECTION:H.F.Cable shall be inspected by the authorised representative of the HVPNL at manufacturer’s premises and acceptance test shall be carried out in accordance with this specification. Inspection report alongwith the routine test certificates shall be forwarded to the HVPNL for approval before despatch 1.12 PACKING AND DESPATCH :- 1.12.1 After approval of the Inspection/Test Certificates, the H.F.Cable will be despatched as per the despatch instructions issued by the HVPNL. 1.12.2 The H.F.Cable shall be suitably packed in drum lengths of 500 meters with + 5% tolerance in drum lengths and total ordered quantity for transportation direct to the consignee and the Contractor shall be responsible for all damages and losses due to improper packing. 1.13 GUARANTEED TECHNICAL PARTICULARS:- 1.13.1 The bidders shall furnish with his offer Guaranteed Technical Particulars of the HF Cable offered as per Annexure-I of this specification alongwith his comments where his specification do not meet or exceed the requirements laid down in this specification. These guaranteed technical particulars should be supported by the published literature of the bidder. Any other additional technical particulars may be supplied by the bidder which he may like to give to prove the merits of the HF Cable offered by him. Tenders without Guaranteed Technical Particulars may not be considered. 1.13.2 -5-