DOCUMENT 009101 - ADDENDUM NO. 2 Issued to all Bidders: Date: October 29, 2014 Contract Name: 69,000 Volt Transformers SUA Bid No.: #04-14/15 This addendum forms a part of the Bid described above. The original Contract documents and any prior addenda remain in full force and effect except as modified by the following which shall take precedence over any contrary provisions in the prior documents. BIDDER QUESTIONS AND ANSWERS: 1. See the document included with this addendum “SUA Bid 04-1415 Bidders Correspondence Log.” This document contains the questions and answers provided in Addendum No. 1, and, in addition, contains a question 3 and corresponding answer. Each Bidder shall acknowledge receipt of this addendum by affixing signature below, by noting this addendum on Bidder’s Bid Form, and by attaching this addendum to the Bid. ACKNOWLEDGEMENT The undersigned acknowledges receipt of this addendum and the Bid submitted is in accordance with information, instructions, and stipulations set forth herein. Bidder: ___________________________ By: ______________________________ Date: _____________________________ END OF DOCUMENT 009101 75644.5110 009101-1 Issued for: Addendum 2 Issue Date: 10/29/2014 Revision: 0 Stillwater Utilities Authority SUA Bid #04-14/15 - 69,000 Volt Transformers Bidders' Correspondence Log Item Category Date Rcv'd 1 2 3 Question RFP Section Technical Exception, Clarification or Question The rating 20/25/28 MVA is calculated improperly. In order to provide the ONAF rating, 25MVA, a nonstandard capacity of 25% Attachment (typically 33% for this rating) is required. The 28MVA rating would 13-Oct-2014 B, SECTION be another 12% above the 25MVA which is consistent with a 55/65 337313 degree C rise. Your specification indicates a 65 degree C rise and two stages of fans. Please reconsider the specified capacity and issue an addendum as necessary. N/A As you may guess, [without an answer to question 1], we are unable to process this design, compressing the time needed to provide a comprehensive quotation. Unless an addendum is received today, please grant an extension allowing submittal on or before Friday, November 7th. Question 13-Oct-2014 Question The drawing that is provided in the spec places the LV bushings on ANSI segment 4 and the HV bushings on segment 2. The problem Attachment is there isn't enough space on segment 2 to locate 4 HV bushings 24-Oct-2014 B, 481923- and maintain proper clearances. Typically we would see the LV SK1 bushings mounted on the front wall or segment 1 and the HV bushings on the cover on the opposite side, segment 3. Is that arrangement acceptable? Resp. Initials Response Date SUA Response TOB Supplier shall provide a Bid for transformers specified in SECTION 337313 with rating of 16.8/22.4/28 MVA. Please see the revisions 15-Oct-2014 to the Contract documents as identified in Addendum 1. TOB Extension to Friday, November 7th will not be granted. TOB The drawing 481923-SK1 is shown with IEEE segment 1 rotated counterclockwise 45 degrees from the orientation in Figure 1 of IEEE C57.12.10. For the generator step-up transformer specified in SECTION 481923, the LV bushings shall be mounted in segment 1 on the side (front wall) of the transformer as specified 29-Oct-2014 and as shown on 481923-SK1. The HV bushings shall be mounted on the cover in segment 3 as you have stated, as is shown in Figures 1 and 3 of IEEE C57.12.10, and as shown on 481923SK1. Page 1 of 1 15-Oct-2014 Bidder Reply Response Date SUA Response Response Date