Installation Guide- Full Height Panels

advertisement
Tensar Installation Guide for Contractors
IGC/Full Height Panels_10.07.08
Full Height Panels
1.
Prepare a level foundation as required by the
Contract.
2.
Cast a U-shaped in-situ concrete footing or
alternatively place precast foundation beam
3.
Set temporary timber reaction supports into
ground
1.
2.
3.
4.
Pitch the full height panels. The panel will
need to be held in postion until the push pull
props are in place
5.
Install a pair of folding wedges between the
toe of the panels and the forward upstand on
the footing and install temporary push-pull
props. Props to be inclined between 45° and
60° to the horizontal. With the illustration
opposite the push pull prop needs to have
a bolted type of fixing to the panel
4.
5.
Installation guidelines for contractors
1/3
IGC/Full Height Panels_10.07.08
6.
Adjust facing panels to required batter
7.
Connect adjacent panels by the use of a fish plate
and then adjust horizontal alignment of these
panels
8.
Place drainage material (if required) behind units.
Place and compact fill to Contract's specification
up to the level of the lowest cast-in grid tail. Join
the main geogrid to the starters using Tensar
bodkin and lay out the geogrid over the fill
9.
Fill should be placed by plant such as an
excavator bucket or a dozer with an opening
bucket which causes the fill to cascade onto the
grids. A minimum of 150 mm thick cover of fill
must be maintained between the tracks of any
plant and the grid to avoid damage. Use plant
with a total mass less than 1000 kg within 2 m
of the face
7.
8.
9.
10.
No traffic or site plant shall be permitted to travel
directly on the grid
11.
Use a vibrating plate compactor or a vibrating
roller with a mass per metre width ≤ 1300 kg
and a total mass
≤ 1000 kg within 2 m of
the face
11.
Installation guidelines for contractors
2/3
IGC/Full Height Panels_10.07.08
12.
13.
14.
12.
Apply a load to the free end of the grid using a
tensioning beam (see TN/SRREBeam) inserted
through the apertures in the grid, until the slack
is removed from the joint.Whilst maintaining
tension, place a layer of fill on the grid, which is
sufficient to restrain it in position when the load
is released. Release the tension and remove the
beam
Folding and slack in the geogrid is not allowed.
Continue construction up to approx. 1/3 of the
full height of the wall. Remove the folding
wedges from the toe of the wall
15.
Continue construction up to approx. 2/3 of the
full height of the wall. Remove props and make
good the holes.
16.
17.
Continue construction up to the top of the wall
13.
The Contractor must fully asses the safety risk
associated with working at height and where
appropriate install any necessary temporary edge
protection.
14.
15.
The information in this document is of an illustrative nature and is supplied without charge. It does not form part of any contract or intended contract with the user. Final
determination of the suitability of any information or material for the use contemplated and the manner of use is the sole responsibility of the user and the user must assume all risk
and liability in connection therewith.
Tensar is a registered trade mark
Tensar International Limited
Tel: +44 (0) 1254 262431
Fax: +44 (0) 1254 266867
E-mail: sales@tensar.co.uk
www.tensar-international.com
UK Head Office
Cunningham Court
Shadsworth Business Park
Blackburn
BB1 2QX
United Kingdom
Installation guidelines for contractors
3/3
IGC/Full Height Panels_10.07.08
Download