Turnpike Tentative Work Program, FDOT District

advertisement
Florida’s Turnpike Enterprise
Tentative Five-Year Work Program - FY 2015/16 thru FY 2019/20
Summary of Projects in FDOT District Four
DISTRICT FOUR PROJECT OVERVIEW
Florida’s Turnpike Enterprise continues to make significant project investments in District Four. In fiscal years 2014
and 2015, current Turnpike projects total over $127 million within Broward, Indian River, Martin, Palm Beach and St.
Lucie Counties.
Summary of Major Project Funding by Project Type:
The table below summarizes the funding programmed for the major Turnpike projects in the Tentative Five-Year Work
Program (FY 2015/2016 through FY 2019/2020) that are located in District Four. The project descriptions below this
section identify and describe the major projects by county. The following phase abbreviations are used in the project
tables:
 ENV – Environmental (Funding Phase Codes: C2, C8)
 PDE – Project Development and Environment (Funding Phase Codes: 21, 22)
 PE – Preliminary Engineering (Funding Phase Codes: 31, 32)
 DSB – Design-Build (Funding Phase Codes: 52, 53, 54, 58, 61, 62)
 CST – Construction (Funding Phase Codes: 52, 53, 54, 58, 61, 62)
Work Description
Add Lanes & Reconstruction
Interchange Improvements
Resurfacing & Other Work
PD&E/EMO Study
All-Electronic Tolling Conversion
Major Projects Total
FY 2016
$35,450,000
$11,087,000
$1,811,000
$1,200,000
$0
$49,548,000
FY 2017
$0
$755,000
$26,651,000
$0
$0
$27,406,000
Fiscal Year
FY 2018
$170,084,717
$9,677,000
$16,845,000
$0
$38,513,000
$235,119,717
FY 2019
$1,000,000
$3,623,000
$449,000
$0
$68,565,000
$73,637,000
FY 2020
$13,317,000
$45,000
$0
$0
$33,594,000
$46,956,000
5 Year Total
$219,851,717
$25,187,000
$45,756,000
$1,200,000
$140,672,000
$432,666,717
Summary of Major Projects by County:
The major Turnpike project expenditures by county in the Tentative Five-Year Work Program are shown in the table
below. Please note that the funding for AET Phase 5A ($46,406,000), a major regional project in Broward and Palm
Beach Counties and AET Phase 8 ($94,266,000) a major regional project spanning Palm Beach, Martin, St Lucie, and
Indian River Counties in District Four, Osceola County in District Five and Okeechobee County in District One is not
included these totals and is addressed later in this document.
County
Broward
Indian River
Palm Beach
St. Lucie
Total
FY 2016
$22,297,000
$456,000
$26,645,000
$150,000
$49,548,000
FY 2017
$40,000
$6,051,000
$19,930,000
$1,385,000
$27,406,000
Fiscal Year
FY 2018
$170,399,717
$153,000
$9,945,000
$16,109,000
$196,606,717
1 – As of January 7, 2015
FY 2019
$3,367,000
$0
$1,256,000
$449,000
$5,072,000
FY 2020
$501,000
$0
$12,861,000
$0
$13,362,000
5 Year Total
$196,604,717
$6,660,000
$70,637,000
$18,093,000
$291,994,717
Florida’s Turnpike Enterprise
Tentative Five-Year Work Program - FY 2015/16 thru FY 2019/20
Summary of Projects in FDOT District Four
Broward County Projects:
Widen the Turnpike/SR 91 from Sawgrass Expressway/SR 869 (MP 71) to the Palm Beach County Line
73) – FPN: 415927-1
(MP
This project widens a two-mile segment on the Turnpike/SR 91 from the Sawgrass Expressway
Interchange (MP 71) to the Palm Beach County Line (MP 73). This widening will increase the number of travel lanes
from six to eight.
Phase
PE
Total
FY 2016
$3,500,000
$3,500,000
FY 2017
$0
$0
Fiscal Year
FY 2018
$0
$0
FY 2019
5 Year Total
FY 2020
$0
$0
$0
$0
$3,500,000
$3,500,000
Sample Road Resurfacing and Intersection Improvements – FPN: 435614-1,-2
This project resurfaces the Turnpike/SR 91 at Sample Road (MP 69). This project also includes intersection
improvements along with guardrail installation, and sigining and pavement marking improvements.
Phase
CST
Total
FY 2016
$1,797,000
$1,797,000
FY 2017
$40,000
$40,000
Fiscal Year
FY 2018
$0
$0
FY 2019
5 Year Total
FY 2020
$0
$0
$0
$0
$1,837,000
$1,837,000
Widen the Turnpike/SR 821 from NW 57th Avenue (MP 43) to Miramar Toll Plaza (MP 47) - FPN: 429328-1,-2
This project adds one lane in both directions on the Turnpike/SR 821 from NW 57th Avenue/Red Road (MP 43) to the
Miramar Toll Plaza (MP 47), creating a six-lane section between the interchange and the toll plaza. The project also
widens the southbound off-ramp at NW 57th Avenue to two lanes and provides turn-lane improvements on NW 57th
Avenue (previously included in FPN 423371-2). This improvement also includes widening the existing bridge structures
and facilitating storm-water permitting to accommodate the ultimate eight-laning within the project limits. Improvements
to NW 27th Avenue in the area of the Turnpike/SR 821 Interchange are also included. Upon implementation, this
project will reduce the potential for bottlenecks along this corridor.
Phase
FY 2016
PE
DSB
CST
Total
FY 2017
$0
$0
$0
$0
$0
$0
$0
$0
Fiscal Year
FY 2018
$490,000
$55,189,000
$0
$55,679,000
2 – As of January 7, 2015
FY 2019
FY 2020
$0
$0
$0
$0
$0
$0
$456,000
$456,000
5 Year Total
$490,000
$55,189,000
$456,000
$56,135,000
Florida’s Turnpike Enterprise
Tentative Five-Year Work Program - FY 2015/16 thru FY 2019/20
Summary of Projects in FDOT District Four
Improve the Interchange at Sawgrass Expressway/SR 869 and Coral Ridge Drive (MP 14) – FPN: 435461-1,-2
This project improves the interchange at Sawgrass Expressway/SR 869 and Coral Ridge Drive (MP 14) by modifying
the existing diamond interchange into a diverging diamond interchange. This interchange project improves safety and
operations along Coral Ridge Drive by reducing congestion.
Phase
FY 2016
PE
CST
Total
FY 2017
$0
$0
$0
$0
$0
$0
Fiscal Year
FY 2018
$315,000
$0
$315,000
FY 2019
5 Year Total
FY 2020
$0
$3,367,000
$3,367,000
$0
$45,000
$45,000
$315,000
$3,412,000
$3,727,000
Widen the Sawgrass Expressway/SR 869 from Coral Ridge Drive (MP 14) to State Road 7 (MP 18) FPN: 435461-3
This project widens a four-mile segment of the Sawgrass Expressway/SR 869 from Coral Ridge Drive (MP 14) to SR
7/US 441 (MP 18). This widening will increase the number of travel lanes from six to eight.
Phase
PE
Total
FY 2016
$3,500,000
$3,500,000
FY 2017
$0
$0
Fiscal Year
FY 2018
$0
$0
FY 2019
5 Year Total
FY 2020
$0
$0
$0
$0
$3,500,000
$3,500,000
Project Development and Environment Study for Sawgrass Expressway/SR 869 Widening – FPN: 437153-1
This is a Project Development and Environment Study evaluating widening the Sawgrass Expressway/SR 869 from SR
7/US 441 (MP 18) to Powerline Road (MP 22).
Phase
PDE
Total
FY 2016
$1,200,000
$1,200,000
FY 2017
$0
$0
Fiscal Year
FY 2018
$0
$0
3 – As of January 7, 2015
FY 2019
5 Year Total
FY 2020
$0
$0
$0
$0
$1,200,000
$1,200,000
Florida’s Turnpike Enterprise
Tentative Five-Year Work Program - FY 2015/16 thru FY 2019/20
Summary of Projects in FDOT District Four
Widen the Sawgrass Expressway/SR 869 from Sunrise Boulevard (MP 1A) to Coral Ridge Drive (MP 14) FPN:
437155-1
This project widens a 13-mile segment of the Sawgrass Expressway/SR 869 from Sunrise Boulevard (MP 1A) to
Coral Ridge Drive (MP 14). This widening will increase the number of travel lanes from six to eight.
Phase
PE
DSB
Total
FY 2016
$5,000,000
$0
$5,000,000
FY 2017
$0
$0
$0
Fiscal Year
FY 2018
$702,520
$113,703,197
$114,405,717
FY 2019
5 Year Total
FY 2020
$0
$0
$0
$0
$5,702,520
$0 $113,703,197
$0 $119,405,717
Widen the Turnpike/SR 821 from I-75 (MP 39) to NW 57th Ave (MP 43) – FPN: 435546-1
This project widens a four-mile segment of the Turnpike/SR 821 from I-75 (MP 39) to NW 57th Ave (MP 43). This
widening will increase the number of travel lanes from four to six. These new lanes will be express lanes and includes
pavement milling and resurfacing and right-of-way costs. The project limits begin in Miami-Dade County and end in
Broward County.
Phase
PE
Total
FY 2016
$7,300,000
$7,300,000
Fiscal Year
FY 2018
FY 2017
$0
$0
FY 2019
$0
$0
5 Year Total
FY 2020
$0
$0
$0
$0
$7,300,000
$7,300,000
Indian River County Projects:
Resurface the Turnpike/SR 91 MP 178.3 to MP 181.1 – FPN: 435167-1, -2, -3
This project resurfaces a three-mile segment of the Turnpike/SR 91 from MP 178.3 to MP 181.1. This project also
includes guardrail installation, and signing and pavement marking improvements.
Phase
PE
CST
Total
FY 2016
$264,000
$0
$264,000
FY 2017
$0
$3,499,000
$3,499,000
Fiscal Year
FY 2018
$0
$94,000
$94,000
FY 2019
4 – As of January 7, 2015
5 Year Total
FY 2020
$0
$0
$0
$0
$0
$0
$264,000
$3,593,000
$3,857,000
Florida’s Turnpike Enterprise
Tentative Five-Year Work Program - FY 2015/16 thru FY 2019/20
Summary of Projects in FDOT District Four
Resurface the Turnpike/SR 91 from MP 188.5 to MP 190.5 – FPN: 435168-1, -2, -3
This project resurfaces a two-mile segment of the Turnpike/SR 91 from MP 188.5 to MP 190.5. This project also
includes guardrail installation, and signing and pavement marking improvements.
Phase
PE
CST
Total
FY 2016
$192,000
$0
$192,000
FY 2017
$0
$2,552,000
$2,552,000
Fiscal Year
FY 2018
$0
$59,000
$59,000
FY 2019
5 Year Total
FY 2020
$0
$0
$0
$0
$0
$0
$192,000
$2,611,000
$2,803,000
Palm Beach County Projects:
Widen the Turnpike/SR 91 from Lake Worth Road (MP 93) to Okeechobee Boulevard (MP 99) – FPN: 406143-1
This project widens a six-mile segment of the Turnpike/SR 91 from Lake Worth Road (MP 93) to Okeechobee Boulevard
(MP 99). This widening will increase the number of travel lanes from four to eight.
Phase
PE
Total
FY 2016
$9,650,000
$9,650,000
FY 2017
$0
$0
Fiscal Year
FY 2018
$0
$0
FY 2019
5 Year Total
FY 2020
$0
$0
$0
$0
$9,650,000
$9,650,000
Widen the Turnpike/SR 91 from Broward/Palm Beach County Line (MP 73) to Glades Road (MP 75) – FPN:
418214-1
This project widens a three-mile segment of the Turnpike/SR 91 from the Broward/Palm Beach County Line (MP 73)
to Glades Road (MP 75). This widening will increase the number of travel lanes from six to eight.
Phase
PE
Total
FY 2016
$6,500,000
$6,500,000
FY 2017
$0
$0
Fiscal Year
FY 2018
$0
$0
FY 2019
5 – As of January 7, 2015
5 Year Total
FY 2020
$0
$0
$0
$0
$6,500,000
$6,500,000
Florida’s Turnpike Enterprise
Tentative Five-Year Work Program - FY 2015/16 thru FY 2019/20
Summary of Projects in FDOT District Four
Widen the Turnpike/SR 91 from Okeechobee Boulevard (MP 99) to PGA Boulevard (MP 109) – FPN: 415748-1
This project widens a ten-mile segment of the Turnpike/SR 91 from Okeechobee Boulevard (MP 99) to PGA
Boulevard (MP 109). This widening will increase the number of travel lanes from four to six.
Phase
FY 2016
ENV
PE
FY 2017
$0
$0
$0
Total
$0
$0
$0
Fiscal Year
FY 2018
$0
$0
$0
FY 2019
$1,000,000
$0
$1,000,000
5 Year Total
FY 2020
$0
$9,900,000
$9,900,000
$1,000,000
$9,900,000
$10,900,000
Improve the Interchange at Turnpike/SR 91 and PGA Boulevard (MP 109) – FPN: 429334-1,-2,-4
This project includes intersection improvements at the Turnpike/SR 91 interchange with PGA Boulevard (MP 109). The
improvements include the addition of a second eastbound left-turn lane, second westbound right-turn lane and a second
westbound left-turn lane. This additional capacity improves safety and operations at PGA Boulevard by reducing
congestion.
Phase
CST
Total
FY 2016
$1,419,000
$1,419,000
Fiscal Year
FY 2018
$0
$0
FY 2017
$17,000
$17,000
FY 2019
5 Year Total
FY 2020
$0
$0
$0
$0
$1,436,000
$1,436,000
Widen the Turnpike from the Lantana Toll Plaza (MP 88) to Lake Worth Road (MP 93) – FPN: 406144-1 &
429324-1
This project widens the Turnpike/SR 91 from the Lantana Toll Plaza (MP 88) to Lake Worth Road (MP 93). This widening
will increase the number of travel lanes from four to eight.
Phase
FY 2016
PE
Total
FY 2017
$0
$0
$0
$0
Fiscal Year
FY 2018
$0
$0
6 – As of January 7, 2015
FY 2019
$0
$0
FY 2020
$2,961,000
$2,961,000
5 Year Total
$2,961,000
$2,961,000
Florida’s Turnpike Enterprise
Tentative Five-Year Work Program - FY 2015/16 thru FY 2019/20
Summary of Projects in FDOT District Four
Improve the Interchange at Turnpike/SR 91 and Glades Road (MP 75) – FPN: 435615-1,-2,-4,-5
This project constructs a second lane to the existing northbound off-ramp, providing an additional southbound right-turn
lane at the intersection with Glades Road. This project also includes an additional westbound right-turn lane and
adjustments to traffic signal timings and offsets at the intersection.
Phase
ENV
CST
Total
FY 2016
$60,000
$8,081,000
$8,141,000
FY 2017
$0
$51,000
$51,000
Fiscal Year
FY 2018
$0
$0
$0
FY 2019
5 Year Total
FY 2020
$0
$0
$0
$0
$0
$0
$60,000
$8,132,000
$8,192,000
Resurface the Turnpike/SR 91 from MP 92.53 to MP 102.6 (Northbound and Southbound), and from MP 90.1 to
MP 90.3 (Northbound) – FPN: 435171-1, -2, -3
This project resurfaces a ten-mile segment of the Turnpike/SR 91 from MP 92.53 to MP 102.6 (northbound and
southbound), and from MP 90.1 to MP 90.3 (northbound). This project also includes guardrail installation, and signing
and pavement marking improvements.
Phase
PE
CST
Total
FY 2016
$1,205,000
$0
$1,205,000
FY 2017
$0
$16,031,000
$16,031,000
Fiscal Year
FY 2018
$0
$507,000
$507,000
FY 2019
5 Year Total
FY 2020
$0
$0
$0
$0
$0
$0
$1,205,000
$16,538,000
$17,743,000
Resurface the Turnpike/SR 91 from MP 103.7 to MP 106.1 – FPN: 435172-1, -2, -3
This project resurfaces a three-mile segment of the Turnpike/SR 91 from MP 103.7 to MP 106.1. This project also
includes guardrail installation, and signing and pavement marking improvements.
Phase
FY 2016
CST
Total
$0
$0
FY 2017
$3,184,000
$3,184,000
Fiscal Year
FY 2018
$76,000
$76,000
7 – As of January 7, 2015
FY 2019
5 Year Total
FY 2020
$0
$0
$0
$0
$3,260,000
$3,260,000
Florida’s Turnpike Enterprise
Tentative Five-Year Work Program - FY 2015/16 thru FY 2019/20
Summary of Projects in FDOT District Four
Resurface the Turnpike/SR 91 from MP 106.1 to MP 111.7 – FPN: 436521-1, -2, -3
This project resurfaces a five-mile segment of the Turnpike/SR 91 from MP 106.1 to MP 111.7. This project also
includes guardrail installation, and signing and pavement marking improvements.
Phase
FY 2016
PE
CST
$0
$0
$0
Total
FY 2017
$647,000
$0
$647,000
Fiscal Year
FY 2018
$0
$9,362,000
$9,362,000
FY 2019
$0
$256,000
$256,000
5 Year Total
FY 2020
$0
$0
$0
$647,000
$9,618,000
$10,265,000
St. Lucie County Project:
Resurface the Turnpike/SR 91 from MP 153.23 to MP 169.32 – FPN: 436517-1, -2, -3
This project resurfaces a 16-mile segment of the Turnpike/SR 91 from MP 153.23 to MP 169.32. This project also
includes guardrail installation, and signing and pavement marking improvements.
Phase
FY 2016
PDE
PE
CST
Total
$0
$150,000
$0
$150,000
FY 2017
$1,385,000
$0
$0
$1,385,000
Fiscal Year
FY 2018
$0
$0
$16,109,000
$16,109,000
8 – As of January 7, 2015
FY 2019
$0
$0
$449,000
$449,000
5 Year Total
FY 2020
$0
$0
$0
$0
$1,385,000
$150,000
$16,558,000
$18,093,000
Florida’s Turnpike Enterprise
Tentative Five-Year Work Program - FY 2015/16 thru FY 2019/20
Summary of Projects in FDOT District Four
Regional Projects:
Implement All-Electronic Tolling (AET) Phase 5A on the Turnpike/SR 91 – FPN: 429339-1,-2
This project implements Phase 5A of an overall program to convert portions of the Turnpike System to a cashless, allelectronic toll collection system. The project limits of Phase 5A begin at the I-595 Interchange (MP 54) on the
Turnpike/SR 91 in Broward County and end south of the Lantana Toll Plaza (MP 88) in Palm Beach County. The Phase
5A conversion includes modifications at the Cypress Creek Mainline Toll Plazas and at nine existing interchange ramp
toll plazas.
Phase
FY 2016
CST
Total
Fiscal Year
FY 2018
$36,513,000
$36,513,000
FY 2017
$0
$0
$0
$0
FY 2019
$0
$0
FY 2020
$9,893,000
$9,893,000
5 Year Total
$46,406,000
$46,406,000
Implement All-Electronic Tolling (AET) Phase 8 on the Turnpike/SR 91 – FPN: 431737-1
This project will implement Phase 8 of an overall program to convert portions of the Turnpike System into a cashless,
all-electronic toll collection system. The project limits of AET Phase 8 begin at the Lantana Toll Plaza on the
Turnpike/SR 91 in Palm Beach County, and extend 148 miles north through Martin, St. Lucie, Indian River, and
Okeechobee Counties, to the Three Lakes Toll Plaza on the Turnpike/SR 91 in Osceola County. The Phase 8 AET
conversion project includes the removal and replacement of 30 ramp toll plazas and two mainline toll plazas.
Phase
FY 2016
PE
DSB
Total
FY 2017
$0
$0
$0
$0
$0
$0
Fiscal Year
FY 2018
$2,000,000
$0
$2,000,000
9 – As of January 7, 2015
FY 2019
$390,000
$68,175,000
$68,565,000
FY 2020
$0
$23,701,000
$23,701,000
5 Year Total
$2,390,000
$91,876,000
$94,266,000
Florida’s Turnpike Enterprise
Tentative Five-Year Work Program - FY 2015/16 thru FY 2019/20
Summary of Projects in FDOT District Four
Summary of Minor Project Funding by Project Type:
The table below summarizes the funding programmed for minor projects (signing/pavement markings, landscaping,
environmental, bridge paintings, canal revetment and on-going project phases) for Turnpike roadways throughout the
District.
Work Description
Bridge Paintings
Signing/Pavement Markings
Minor Projects Total
FY 2016
$0
$8,000
$8,000
FY 2017
$168,000
$21,000
$189,000
Fiscal Year
FY 2018
$1,351,000
$150,000
$1,501,000
FY 2019
5 Year Total
FY 2020
$0
$0
$0
$0
$0
$0
$1,519,000
$179,000
$1,698,000
Summary of All Project Funding:
PROJECTS
Minor Projects Total
Major Projects Total
Total
FY 2016
$8,000
$49,548,000
$49,556,000
Fiscal Year
FY 2017
FY 2018
$189,000
$1,501,000
$27,406,000 $235,119,717
$27,595,000 $236,620,717
10 – As of January 7, 2015
FY 2019
$0
$73,637,000
$73,637,000
FY 2020
$0
$46,956,000
$46,956,000
5 Year Total
$1,698,000
$432,666,717
$434,364,717
Florida’s Turnpike Enterprise
Tentative Five-Year Work Program - FY 2015/16 thru FY 2019/20
Summary of Projects in FDOT District Four
11 – As of January 7, 2015